How OC is issued
Process (1/2)
1. Make plans (Key plan, Site plan, Building plan)
2. Endorse plans (owner, certified engineer/architect/supervisor)
3. Submit to different authorities and get NOCs
(BDA, BWSSB, BESCOM, AAI, Fire Services, etc)
valid for 5 years; but expires after 2 years if work has not commenced
Process (2/2)
10. Work according to the sanctioned plans (Key plan, Site plan, Building plan)
11. Display the following documents at site
Sanctioned plans
Building license
Building specifications
Developer must stop work, and inform BBMP about the stage of completion.
If these conditions are not met, then the developer must apply for a fresh license.
Details
BDA
BWSSB
NOC
BESCOM
Fire
Services
AAI*
Telecom
NOC (for highrises > 7 floors)
Department
* Airport Authority of India
KSCIB*
Railways
* All the plans must be signed by the owner and the Registered Architect / Engineer / Supervisor
Site Plan
1. Title of drawing: property no., street/road, No. of the site if approved layout,
and ref No. of approval, the use of the building;
2. The boundaries of the site and of any contiguous land belonging to the owner
3. The North direction relative to the plan of the building;
4. The adjacent roads, street, or lanes (if any) and their widths
5. The position of the adjacent plots (whether vacant or built-up)
6. The area to be occupied by the proposed building and the proposed set backs
7. The nature of the ground (rocky, gravelly, clayey, sandy, etc.),
8. Whether natural or or made up ground. If made up, when, and using what material.
9. If ground has gradient > 5% (1:20), furnish block levels in the site plan
10. Any physical features such as wells, drains, transmission lines, etc.
11. Natural features like existing trees, ridges, valleys etc.,
12. Block levels in cases where basement is proposed below ground level
13. Other particulars specified by BBMP (??)