Professional Documents
Culture Documents
BETWEEN
FOR
Page 1
TABLE OF CONTENT
Page No.
1.
1.1
1.2
1.3
1.4
1.5
2.
Definition
Interpretation
Measurements and Arithmetic Conventions
Ambiguities and Discrepancies
Authority of Person Signing Document
SCOPE OF WORKS
2.1
3.
3.1
3.2
Handover of Site
Rights, Title and use of the Site
4.
CONTRACTORS OBLIGATIONS
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
Performance of Works
Performance security
Contractors Project Manager
Coordination of Works
Design, Drawings and Engineering
Implementation Schedule
Operation and Maintenance Manual
Contractors Documents
5.
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
5.10
5.11
5.12
5.13
5.14
5.15
5.16
5.17
5.18
5.19
6.
EMPLOYERS OBLIGATION
6.1
6.2
6.3
Permits
Employers Representatives
Independent Engineer
7.
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
Contract Price
Employers Payment Obligation
Mobilization Advance
Progress Payments
Back Charges
Set off
Withholding
Mode of Payment
7.9
8.
CHANGE OF SCOPE
8.1
8.2
8.3
8.4
Change of Scope
Execution for Change of Scope
Change in Contract Price
Change of scope due to non-availability of Forest Land
9.
WORKS COMPLETION
9.1
9.2
9.3
9.4
9.5
9.6
9.7
9.8
9.9
9.10
Testing
Completion
Defects Notification Period
Cost of Remedying Defects
Extension of Defects Notification Period
Failure of Remedy Defects
Removal of Defective Work
Further Tests
Performance Certificate
Unfulfilled obligations
10.
MAINTENANCE
10.1
10.2
10.3
11.
Maintenance
Maintenance during the Implementation Period
Operation and Management from the COD
LIQUIDATED DAMAGES AND BONUS
11.1
11.2
12
Liquidated Damages
Bonus
FORCE MAJEURE
12.1
12.2
12.3
12.4
12.5
13.
13.1
13.2
13.3
13.4
13.5
Events of Defaults
Termination due to Events of Default
Termination Payment
Rights of Employer in Termination
Right of Parties
14.
DISPUTE RESOLUTION
14.1
14.2
14.3
15.
Amicable Resolution
Mediation
Arbitration
REPRESENTATIONS AND WARRANTIES, DISCLAIMER
15.1
15.2
15.3
16.
16.1
16.2
16.3
16.4
Effective Date
Activities prior to Notice to Proceed
Notice to Proceed
Termination
17.
MISCELLANEOUS
17.1
17.2
17.3
17.4
17.5
17.6
17.7
17.8
17.9
17.10
17.11
17.12
17.13
Waiver
Benefit
Independent Contractor
Lenders Approval
Survival
Language
Severability
Entire Contract
Other Documents
Amendments
Notices
Assignment and Charges
Law
Page 4
This Agreement,being effective from the appointed date issued by Madhya Pradesh
Road development Corporation Ltd. is made on this ___ day of ________2014
(Agreement) by and between: attention
AGROH BIAORA TOLLWAYS PVT. LTD., a company incorporated in Madhya
Pradesh, India, under the Indian Companies Act, 1956 with its registered office
atAqua Point, Old A.B. Road,Umariya Mhow Dist. Indore (MP) , (hereinafter referred to
as the Employer or Concessionaire which expression shall unless repugnant to the
context or meaning thereof be deemed to mean and include its successors and
permitted assigns) of the ONE PART;
AND
M/s. AGROH INFRASTRUCTURE DEVELOPERS PVT. LTD., a company duly
organized and existing under the laws of the Companies Act, 1956 and having its
registered office at Aqua Point, Old A.B. Road,Umariya Mhow Dist. Indore (MP)
(hereinafter referred to as the Contractor, which expression shall unless repugnant
to the context or meaning thereof be deemed to mean and include its successors and
permitted assigns) of the OTHER PART.
WHEREAS
a) The Madhya Pradesh Road Development Corporation Limited (MPRDC or
Page 5
Page 6
COD means the date on which the Independent Engineer has issued the
Completion Certificate on completion of construction of the project road length under
the provisions of clause 14.4.2 of Concession Agreement.
Commencement Date means the date on which the Employer has issued Notice
to Proceed to the Contractor in accordance with Sub section 16.3.
Completion Certificate means the certificate to be issued by the Independent
Engineer in accordance with Sub-Section 9.1 b) certificate of completion of
construction of the Project in accordance with the Project Requirements as per the
scope of the Concession agreement.
Concession Agreement means the agreement dated 17/05/2013entered into
between the Concession Authority and the Employer.
Concession Authority means MPRDC as the context may admit or require.
Construction Contract means this agreement to be entered in to between the
Employer and M/s. AGROH INFRASTRUCTURE DEVELOPERS PVT. LTD. for
completion of construction of Project Road and all the associated facilities.
Construction Drawings means the designs and drawings to be prepared by the
Contractor for the purpose of construction of the Project Facilities and shall include
As- Built drawings of the Project Facilities.
Construction Requirements means the requirements as to construction of the
Project and the associated facilities set forth in the Concession Agreement.
Construction Works or Work means all works and things necessary to complete
the Project Highway for use of the traffic and other users thereof in accordance with
this agreement and concession agreement Schedules I, J and L
Page 7
Page 8
EPC Project Road under this EPC contract means the site comprising of
Biaorato MP/Rajasthan Border Road section of NH-12 in the state of Madhya Pradesh
Starting from existing chainage Km. 2/6 (project chainage Km. 0/00) at junction of
NH-3 on Biaora Bypass and terminates at existing chainage Km.67/0 (project
chainage Km.61/0)at MP/Rajasthan Border,of whose concession has been awarded
under the Concession Agreement, Further the EPC project Road shall also include
all project assets on the EPC project road length and its subsequent development and
augmentation during the Concession Period in accordance with the provisions of this
Agreement.
Equipment and Materials means any and all materials, machinery, equipment,
computer hardware, computer software and other apparatus, articles, things or items,
incorporated, placed, operated or intended to be incorporated, placed or operated in
the Project Facilities or to be used in the operation and maintenance of the Project
Facilities and to be furnished in connection with performance of the Works and
including the Project Facilities, any items procured by the Contractor to repair or
replace any Equipment and Materials, and spare parts for start-up, testing and
commissioning of the Project Facilities.
Event of Default shall have the meaning ascribed thereto in Section 13.
Page 9
Financial Close means the date on which the Financing Documents providing for
funding by the Lenders have become effective and the Employer has immediate access
to such funding under the Financing documents.
Financing Documents means collectively the documents evidencing Lenders
commitment to finance the debt component of cost of the Project.
Force Majeure and Force Majeure Event shall have the meaning ascribed
thereto in Article 12 of this Agreement.
Force Majeure Period means, as determined by the Independent Engineer, or
the Employers Engineer on site, the period commencing from the date of occurrence
of a Force Majeure Event and ending on (i) the date on which the affected party,
acting in accordance with the Good Industry Practice, resumes or should have
resumed such of its obligations the performance of which was excused in terms of
Sub-Section 12.2(b) of (ii) the Termination Date, as applicable.
GoI means the Government of India.
MPRDC means Madhya Pradesh Road Development Corporation
MPRDC Representative means such person or persons as may be authorized in
writing by MPRDCto act on its behalf under this Agreement and shall include
Independent Engineer or any person or persons having authority to exercise any
rights or perform and fulfill any obligations of MPRDC under this Agreement.
Page 10
O&M Contractor means the person(s) with whom the Employer may enter into
the O&M Agreement(s) and shall include such persons Sub-Contractors and their
respective successors and assigns.
O&M Requirements means the requirements as to operation and maintenance of
the Project Facilities set forth in the Concession Agreement.
Parties means the parties to this Agreement collectively and Party means either
of the Parties to this Agreement individually.
Performance Certificate shall have the meaning ascribed to it in Section 9.9.
Person or Persons means (unless otherwise specified or required by the
context), any individual, company, corporation, partnership, joint venture, trust,
unincorporated organization, or Governmental Authority or any other legal entity.
Project means financing, construction, operation and maintenance of the EPC
Project Road and the associated facilities and exercise and/or enjoyment by the
Employer of the rights, powers, benefits, privileges, authorizations and the
entitlements in accordance with the provisions of the Concession Agreement.
Project Agreements means collectively this Agreement, Concession Agreement,
O&M Contract(s) if any and any other material agreement entered into or that may
hereafter be entered into by the Employer in connection with the Project.
Project Facilities means all the amenities and facilities situated on the EPC
Project road.
Project Requirements means collectively Construction Requirements and
Maintenance Requirements or any of them as the context may admit or require.
Project Road means road length starting from existing chainage Km. 2/6 (project
chainage Km. 0/00) at junction of NH-3 on Biaora Bypass and terminates at existing
chainage Km.67/0 (project chainage Km.61/0) at MP/Rajasthan Border in the state of
Madhya Pradesh of whose concession has been awarded under the Concession
Agreement and all project assets on the EPC project road length and its subsequent
development and augmentation during the Concession Period in accordance with the
provisions of this Agreement
Protestor means any person engaged in protest action.
Page 11
Page 12
Termination Date means the date specified in the Termination Notice as the date
on which Termination occurs.
Termination Notice means the notice of Termination by either Party to the other
Party, in accordance with the applicable provisions of this Agreement.
Termination Payment means the amount payable by Employer to the Contractor
under this Agreement upon Termination for the actual Work done and certified by the
Employers Representative.
Tests means the tests to be carried out in accordance with the Construction
Requirements as specified in Schedule I of the Concession Agreement and the O&M
Requirements if O&M agreement is entered into with the EPC contractor for the EPC
Project Road.
Trespasser means any person (other than Protestor) not entitled to be on the Site.
Works mean all the works that are required to be carried out for construction of
the Project Road and Project Facilities and performance of all the obligations
undertaken by the Contractor under this Agreement in accordance with the Project
Requirements and include any work that may become necessary to satisfy the
requirements and expectations under the Concession Agreement.
1.2
Interpretation
(b)
references to Applicable Law shall include the laws, acts, ordinances, rules,
regulations, notifications, guidelines or byelaws which have the force of law in
any State or Union Territory forming part of the Union of India;
(c)
the words importing singular shall include plural and vice versa, and words
denoting natural persons shall include partnerships, firms, companies,
corporations, joint ventures, trusts, associations, organizations or other
entities (whether or not having a separate legal entity);
Page 13
(d)
The headings are for convenience of reference only and shall not be used in,
and shall not affect, the construction or interpretation of this Agreement;
(e)
(f)
(g)
Any reference to any period of time shall mean a reference to that according to
Indian Standard Time;
(h)
(i)
(j)
The Schedules to this Agreement form an integral part of this Agreement and
will be in full force and effect as though they were expressly set out in the body
of this Agreement;
(k)
(l)
(m)
(n)
1.3
Page 14
All measurements and calculations shall be in metric system and calculations done to
2 decimal places, with the third digit of 5 or above being rounded up and below 5
being rounded down.
1.4
(b)
between the written description on the Drawings and the specifications and
standards, the latter shall prevail;
(c)
between the dimension scaled from the Drawing and its specific written
dimension, the latter shall prevail; and
(d)
between any value written in numerals and that in words, the latter shall
prevail
and any obligation imposed upon the Contractor in one document but not expressly
included in the others shall be performed by the Contractor as if the obligation is
included in all documents forming part of this Agreement.
1.5
A Person signing any document forming a part of this Agreement on behalf of another
shall be deemed to warrant that he has authority to bind such other Person. Any
Person so signing shall submit satisfactory evidence of his authority. Each Party
represents that any Person signing any document forming a part of this Agreement
has the authority to bind such Party.
2.
SCOPE OF WORKS
2.1
a)
The Contractor shall have the right to propose changes or modifications to the
design of the Works, subject to the approval of the IE/MPRDCs representative/
as may be necessary under the terms of Concession Agreement. In the event,
any modifications and/or changes suggested by the Contractor are acceptable
to the IE/MPRDC/for implementation in the construction of the Works, then
any cost savings resulting from adopting the modifications and for changes
suggested by the Contractor shall be to the benefit of the Contractor and
similarly any additional costs incurred due to the adoption of the modifications
and/or changes suggested by the Contractor, shall be borne by the Contractor.
c)
Any inadequacy arising due to the adoption of any modification and/or change
proposed by the Contractor shall be attributable to the Contractor.
d)
2.2
3.
3.1
Handover of Site
a)
b)
Upon the Site or any part thereof being handed over pursuant to the preceding
clause (a), the Contractor shall, have the right to enter, occupy and commence
Page 16
construction works thereon or part thereof and to make at its cost and
expenses such investigation, developments and improvements in the Site as
may be necessary or appropriate to implement the construction works and to
provide Project Facilities in accordance with the provisions of this Agreement.
Provided that the Contractor shall only have possession use and access to the
Site to the same (and no greater) extent as the Employer has been granted
under the Concession Agreement and upon the same terms granted there
under.
3.2
a)
The Contractor shall have the right to the use of the Site in accordance with
the provisions of this Agreement and for this purpose it may regulate the
entry and use of the same by persons other than (i) parties of the other Project
Agreements, and (ii) those expressly permitted to enter and use the Site under
any of the Project Agreements for the purposes specified therein.
b)
The Contractor shall not part with or create any Encumbrances on the whole
or any part of the Site save and except as set forth and permitted under this
Agreement.
c)
The Contractor shall not without the prior written approval of the Employer
use the Site for any purpose other than for the purpose of the works under this
Agreement and purposes incidental or necessary thereto.
d)
The Contractor shall allow access to and use of the Site Facilities for
laying/installing telegraph lines, electric lines or for such other public
purposes as the Concession Authority may specify.
Provided that such access or use shall not result in a Material Adverse Effect
and in the event of any physical damage to the Site/Project Facilities on
account thereof, the Contractor shall be responsible to coordinate with the
Concession Authority to get the Site/Project Facilities promptly restored. The
Contractor will not be eligible for any compensation or any other payment from
the Employer on this account unless the same is received by the Employer
from the Concession Authority or the persons who laid/installed telegraphic
lines etc.
e)
authority and upon reasonable notice, the Contractor shall provide such
persons assistance reasonably required to catty out their respective duties and
functions.
f)
4.
CONTRACTORSS OBLIGATIONS
4.1
a)
b)
When completed, the Works shall be in strict compliance with the Project
Requirements and other standards and shall satisfy the requirements and
expectations under the Concession Agreement and be fit for the purpose for
which the Works are intended.
c)
The Works shall include any work, which is necessary to satisfy the Project
Requirements and expectations under the Concession Agreement and all
works, which (although not mentioned in the Agreement) are necessary for
stability, completion and proper operation of the Project Facilities.
d)
(i)
execute the Works with adequate skill, care and diligence which may
reasonably be expected from such qualified and experienced professionals with
experience in similar work, having the similar scope and nature, as is required
under the Agreement;
Engineer and execute the Works using the best engineering principles and
practices; and
(ii)
(iii)
Carryout the Works so that the Project Facilities may be fully, efficiently,
economically and safely used, operated and maintained with minimum
interruption for maintenance and repair and otherwise for the purposes
specified or referred to in the Agreement (and the documents referred to in it).
Page 18
e)
The Contractor agrees that it shall at all times save harmless and indemnify
the Employer from and against all claims, liabilities, expenses, costs and losses
suffered or incurred by the Employer which may arise out of or in connection
with any defect, inadequacy or unsuitability of workmanship or materials or
failure to meet in any or all respects the requirements of the Agreement or the
remedying thereof either by the Contractor or by others employed by the
Contractor.
4.2
Performance Security
Contractor shall not be obliged to provide any performance Bank Guarantee to
the Concessionaire under this agreement; however it has agreed to and has
already extended However the EPC contractor shall be obliged to arrange and
extend Bank guarantee equivalent to DSRA/MMRA requirement for the loan
to the concessionaire for the project, as part of its obligation under the EPC
contract which de-facto shall work as a performance guarantee also. its
Corporate Guarantee to the lender for all the project related risks specified in
the financing Agreements.
4.3
a)
b)
Page 19
b) The Contractor will be fully responsible for the acts or omissions of all his
subordinates, agents, workmen, suppliers, consultants, contractors and any
other persons for whom he is contractually responsible for, as if such acts or
omissions were its own.
4.4
a)
b)
4.5
Page 20
Implementation Schedule:
a)
Within 15 calendar days after the Effective Date, the Contractor shall deliver
to the Employer a Works schedule (implementation Schedule) describing
comprehensively and in adequate detail the delivery, procurement, fabrication,
transportation, startup, testing and commissioning activities required to
complete the Works in respect to all the Project Facilities and which shall be
reasonably satisfactory to the Employer in all respects. The Implementation
Schedule shall include the following:
b)
(i)
the order in which and the times by when the Contractor proposes to
carry out the Works (including engineering, placement of purchase
order for all major equipment, raw materials and construction, delivery
at site,) so as to demonstrate that the Works will be completed in
accordance with the Implementation Schedule;
(ii)
(iii)
(iv)
The times by which the Contractor requires the Employer (i) to provide
access to the Site, and (ii) to have provided such services and supplies
as are stated in this Agreement as being the responsibility of the
Employer.
Page 21
c)
The Contractor shall not without the Employers prior written consent make
any alterations to the Implementation Schedule. Consent by the Employer to
an alteration of the Implementation Schedule shall not relieve the Contractor
of any of its obligations under this Agreement.
d)
4.7
Contractors Documents
The Contractor shall make available to the Employer, the Employers
Representative, the Concession Authority, the Independent Engineer and the
Lenders Engineer all the Contractors Documents as may be necessary for
review, verification, inspection, carrying out Tests and exercising their rights
under this Agreement and the Concession Agreement, as the case may be. The
Contractor shall deliver to the Employer all the Contractors Documents at the
time of obtaining the Completion Certificate and at the end of the Defects
Liability Period. The Works shall not be treated as complete until the
Employer, has received all the Contractors Documents.
5.
5.1
a)
b)
The Contractor shall procure and provide all equipment necessary to complete
the Works. All Contractors equipment shall, when brought on to the Site, be
deemed to be exclusively intended for the execution of the Works.
c)
The Contractor shall ensure that all equipment shall be in a sound operating
condition, safe and fit for its intended purpose.
Page 22
d)
e)
The Contractor shall be responsible for providing and managing at the Site for
the purposes of the Works such supplies of industrial water, gas, air, sanitary
waste removal, rubbish disposal and other utilities necessary for completion of
the Works. The Contractor confirms that the cost of such utilities including
installation and utilization during the Works and their removal at the
completion of the Works at the direction of the Employer is included in the
Contract Price.
5.2
Reporting of Progress
a)
b)
The Contractor shall ensure that all documents, including without limitation
invoices, billings, waivers, certifications, releases, and reports, submitted by
the Contractor to the Employer or any other Person under this Agreement, are
complete, accurate and truly reflect the facts about the activities and
transactions to which they pertain and contain no material misstatements or
omissions. The Contractor acknowledges that the Employer and other
recipients will rely on those documents and reports. Acceptance of such
documents shall not constitute the agreement of the Employer with their
contents.
c)
The Contractor shall conduct a monthly (or more frequently if required by the
Employer) progress meeting with the Employer.
5.3
Rate of Progress
a)
If progress does not match the Implementation Schedule, the Contractor shall
take such steps as may be necessary to remedy or mitigate the likely delay,
including on its own initiative and at its own expense, increasing or
supplementing the supervision, labor force and procurement to such an extent
Page 23
If the Employer decides that progress does not match the Implementation
Schedule and that this is not due to a circumstance for which the Contractor is
entitled to an extension of time under this Agreement, the Employer may issue
a notice ordering the Contractor to revise the Implementation Schedule at the
Contractors expense. On receipt of such notice, the Contractor shall revise the
Implementation Schedule to show the modifications necessary to ensure that
the COD occurs in accordance with the Implementation Schedule. If the
Employer issues such a notice, it shall not relieve the Contractor from or
operate as a waiver of its obligations to maintain the rate of progress required
by this Agreement.
c)
If the Contractor fails to take necessary steps to remedy or mitigate the delay
and in the opinion of the Employer, the failure of the Contractor to take such
steps is likely to result in a delay in the Implementation Schedule, the
Employer may take such steps as may be necessary (including taking over and
completing the Works), at the Contractors expense, to remedy the delay in
progress of Works. Notwithstanding the immediately preceding sentence, the
Contractor shall at all times be responsible for the Works, irrespective of
whether the Contractor acts as a result of any advice of or reviews by the
Employer.
5.4
Sub-Contracting
a)
The Contractor may, at its discretion and convenience, sub-contract any part of
the Works. The Contractor shall, however, at the earliest possibility, furnish to
the Employer and the Employers Representative the details of the Works subcontracted and of the Sub Contractor(s)
b)
The Contractor shall ensure that all sub-contracts are made in writing and
awarded if persons/ companies are capable of executing the desired works as
per specifications.
c)
d)
there is no conflict with the work of other Sub Contractors, the Contractor or
other contractors.
e)
All contracts and arrangements between the Contractor and its SubContractors shall be subject to provisions, which the Contractor shall not
waive, release or impair, giving the Contractor an unrestricted right to assign
to the Employer the relevant sub-contract and all benefits, interests, rights
and causes of action arising under it and provisions whereby the Employer
may subsequently assign the sub-contract as it requires.
f)
The Contractor shall assign to the Employer all the Contractors rights under
the sub- contracts warranties within five (5) calendar days from (i) termination
of the Agreement; and (ii) the date of issuance of the Completion Certificate,
whichever is earlier. Till assignment, the Contractor holds these rights in trust
for itself and the Employer.
g)
Pursuant to any assignment, the Contractor shall inform each relevant SubContractor of the assignment. The Contractor shall also use all reasonable
efforts to ensure and procure that each Sub-Contractor delivers to the
Employer written acknowledgement of the assignment.
h)
Nothing contained in the Agreement shall render the Employer in any way
liable to any Subcontractor or supplier and the Contractor shall indemnify and
keep indemnified the Employer against all and any liabilities to, and costs,
claims and demands of whatsoever nature by any Subcontractor or supplier.
5.5
Suspension of Work
a)
protect, store and secure such part or the Works against any
deterioration, loss or damage;
(ii)
(iii)
c)
If the Contractor suffers delay and/or incurs additional cost in following the
Employers Representatives instructions under Sub-section (a) of this Section
5.5 and in resuming the relevant part of the Works, then the Contractor shall
be entitled to give notice to the Employers Representative, with a copy to the
Employer. Any additional liability on the Employer for extension of time for
completion on account of or arising out of suspension shall be only to the
extent, if any, received by the Employer from the Concession Authority.
5.6
a)
Not later than 15 calendar days prior to commencement of Works at the Site,
the Contractor shall propose the Contractors Site Representative and each
individual to act as Key Site Personnel at the Site. Such personnel shall
possess relevant experience in engineering, construction and project
management of road projects. The Contractor shall propose replacement Key
Site Personnel from time to time as necessary or desirable subject to the
approval procedures set forth below.
b)
In proposing Key Site Personnel, the Contractor shall provide the Employer
with resumes detailing the experience of each of such personnel. Following
such proposal, the prior approval of the Employer shall be required before each
person is assigned and accepted as one of the Key Site Personnel. The
Employer agrees to approve or disapprove any such personnel within 15
calendar days of the receipt of the resumes, provided that before the expiration
of such 15 calendar days period, the Employer may request supplemental
information regarding such personnel. If supplemental information is
requested, the Contractor shall supply the requested information within 5
calendar days and the Employer shall have 5 calendar days after receipt of
such information to approve or disapprove the relevant personnel (which
approval shall not be unreasonably denied). Failure of the Employer to approve
or disapprove any such personnel within the time periods provided shall
Page 26
d)
The Contractor agrees that Key Site Personnel shall be assigned at all
appropriate times solely to the performance of the Contractors obligations
under this Agreement and may not perform any other services for the
Contractor or its direct or indirect shareholders, or otherwise inconsistent
with their primary responsibility to perform the Contractors obligations
under this Agreement. Key Site Personnel shall not be absent from the Site for
business not related to the Works without prior notification to the Employer of
the person who will substitute during such persons absence, and the
Contractor shall obtain the Employers approval if such absence may extend
beyond 7 calendar days.
5.7
Personnel:
a)
The Contractor shall provide all personnel required for the Works. The
Contractor shall hire, discharge and designate the classification of work for
each employee in accordance with its best judgment and Good Industry
Practice. The Contractor shall select and supervise its personnel and SubContractors to maximize productivity and to avoid slow-downs, work stoppages
or other disruptive concerted actions of workers. The Contractor represents
that it has the experience and capability including sufficient competent
technical, supervisory and other personnel to perform the Works and shall
continually furnish such personnel until performance of the Works is
completed.
b)
Page 27
The Contractor shall at all times take all reasonable precautions to prevent
any unlawful, riotous or disorderly conduct by or amongst its staff and labour
and for the preservation of peace and protection of persons and property in the
neighborhood of the Site against such conduct.
d)
Upon notification from the Employer, the Contractor shall remove from the
Site any of its personnel who do not meet the standards of experience,
competency or comportment, or who in the opinion of the Employer otherwise
may be a detriment to the Works or unacceptable to the Employer, and the
Contractor shall ensure such personnel remain uninvolved with any aspect of
the Works. The Contractor shall provide replacements for such personnel
promptly thereafter in order that the performance of the Works in accordance
with the Implementation Schedule is not affected.
5.8
Site Conditions:
a)
b)
c)
The Contractor shall at all times during the Works keep the Site in a clean,
safe and workmanlike condition.
d)
The Contractor shall at all times during the Works, keep the Site clear of
construction materials and rubbish caused by the Works and promptly after
completion of the Works at the Site shall remove all remaining materials
(other than materials required to be supplied to the Employer in accordance
with this Agreement) from and about the Project Facilities and shall leave the
Project Facilities safe, clean and ready for use.
e)
The Contractor shall promptly dispose of all waste materials and rubbish in
accordance with Good Industry Practice and Applicable Law. If the Contractor
is notified by the Employer to clean up and remove construction debris or
unsafe materials, tools or equipment, and fails to execute the Employers
Page 28
directive within seven (7) calendar days, the Employer shall have the right, but
not the obligation, to correct the matter at the cost and risk of the Contractor.
5.9
a)
Insurance
The Employer shall at its cost and expenses, purchase and maintain insurance
in respect of the following risks:
i)
ii)
iii)
iv)
Out of the above policies the Contractor shall reimburse to the Employer the
amount of premium paid by the Employer for the CAR policy or shall have the
option to take the CAR policy in its own name.
b)
i)
ii)
iii)
The Contractor shall at its cost expense, purchase and maintain the following
insurances
d)
The Third Party Liability Insurance Policy shall include a cross liability clause
such that the insurance shall apply to the Contractor and the Employer as if
both are separately insured.
e)
f)
g)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
h)
i)
The Contractor shall provide all assistance to the Employer in the application
for, and finalization of, such comprehensive insurance package.
j)
The Contractor shall pay the Contractors share of the insurance premiums for
insurance premiums allocated under such comprehensive insurance package
policy to the insurances directly to the insurance provider promptly on
demand. In case the Contractor fails to make such payment in time, the
Employer may elect to pay the Contractors share and adjust it against
amounts payable to the Contractor under this Agreement.
In the case of occurrence of any event leading to an insurance claim, the
Contractor shall promptly follow the procedures specified by the insurance
provider, and provide full cooperation and access to the insurance provider or
its representative, to settle the claim expeditiously. In addition, the Contractor
shall keep the Employer and/or the Lenders fully informed and shall promptly
submit all reports and documents as may be requested by the Employer and/or
the Lenders.
k)
i)
m)
n)
Nothing in this Section 5.9 shall limit or relieve the Contractor of its liabilities
and obligations under this Agreement.
Page 31
5.10
Inspection
The Employer, the Concession Authority, the Independent Engineer and the
Lenders / Lenders Engineer may at all times inspect the Site and the Project
Facilities and the appropriate work records of the Contractor and its SubContractors to ascertain the Contractors compliance with this Agreement.
However, neither the existence nor exercise of such right shall relieve the
Contractor of its responsibility for managing or supervising the Works.
5.11
a)
The Contractor shall at all times during the Implementation Period, be solely
responsible for the adequacy, stability and safety of its operations of Project
Road. The Contractor shall prior to the commencement of work at the Site,
prepare and submit to the Employer for its approval, a comprehensive set of
safety regulations in connection with the Works. The Contractor shall comply
with and shall ensure that all of its employees, agents and Sub-Contractors of
any tier engaged in work at the Site comply with the provisions of such safety
regulations.
b)
The Contractor shall have on its staff at the Site a person dealing with the
safety and protection against accidents of all staff and labour. This person
shall be appropriately qualified for such work and shall have the authority to
issue instructions and to take protective measures in connection with the
prevention of accidents.
c)
The Contractor shall maintain such records and make such reports concerning
safety, health and welfare of persons at the Site and damage to property at the
Site, as the Employer shall from time to time reasonably require consistent
with Good Industry Practice. The Contractor shall in any event report to the
Employer details of any accident occurring at the Site or, if occurring
elsewhere which causes damage to the Project Facilities, as soon as reasonable
after its occurrence.
d)
The Contractor shall at its own cost take all due precautions to ensure the
health and safety of its staff and labour. In the event of the outbreak of any
illness of an epidemic nature, the Contractor shall comply with and carry out
such regulations, orders and requirements of any Governmental Authority for
the purpose of dealing with and overcoming the same.
e)
The Contractor shall initiate, maintain and supervise all safety measures and
programs in connection with the Works necessary to properly protect all
persons in the proximity of the Project Facilities from injury and danger to
health and all property from damage or loss. The Contractor shall never
permit a hazardous, unsafe, unhealthy or unsound condition or activity to be
conducted at the Site.
g)
The Contractor shall at all times take all reasonably necessary precautions to
protect all staff and labour employed on the Project Facilities from insect
nuisance, vermin and other pests and reduce the dangers to health and the
nuisance occasioned by the same.
h)
Prior to the commencement of work at the Site, the Contractor shall submit to
the Employer a list of any Hazardous Substances and associated Hazardous
Substances data sheets with respect to any Hazardous Substances that the
Contractor anticipates will be located at the Site, installed or otherwise
incorporated into the Project Facilities, or used in performing the Works. Such
list and data sheets shall be updated by the Contractor as required for the
Employer to have a complete list of such Hazardous Substances actual located
at the Site, installed or otherwise incorporated into the Project Facilities, or
used in performing the Works. The Contractors use and disposal of Hazardous
Substances shall at all times comply with Applicable Law. Except with the
prior written approval of the Employer, the Contractor shall remove all
Hazardous Substances from the Site not later than the COD. The Contractor
shall not use or incorporate into the Project Facilities any materials containing
asbestos.
5.12
operations of the Project Facilities and shall coordinate its activities with the
Employer.
5.13
a)
The Contractor shall implement and shall ensure that each of its SubContractors implements a quality assurance program that meets acceptable
international standards to provide reasonable assurances that the Works are
completed in accordance with the provisions of this Agreement. The
Contractor shall be fully responsible for reviewing and monitoring quality
assurance programs of its Sub-Contractors to reasonably assure such
programs meet acceptable international standards and are being implemented
in accordance with the terms thereof. The Contractor shall provide
information regarding the implementation of the quality assurance program in
the Contractors monthly reports.
b)
Not later than 60 calendar days following the Effective Date, the Contractor
shall present to the Employer for approval the Contractors detailed quality
assurance program and procedures. At the Employers request, the Contractor
shall provide the Employer with the quality assurance program of SubContractors for the Employers review.
5.14
a)
The Contractor shall observe and abide by all Applicable Law and the
Contractor shall provide and post as appropriate or required by Applicable
Law all Applicable Permits for the Works.
b)
The Contractor shall defend the Employer against the proposed imposition of
any penalty or liability with respect to alleged failures to observe and abide by
Applicable Law. The Contractor shall defend, indemnify and hold the
Employer harmless (including expenses and legal fees) from any liability or
penalty which may be imposed by reason of the Contractors failure to observe
and abide by Applicable Law, and shall pay all legal fees associated with the
enforcement of the indemnity
5.15
5.16
customs duties. All such Taxes of the Contractor shall be deemed included in
the Contract Price as stated in this Agreement. The Contractor shall at its
cost defend, indemnify and hold the Employer harmless from all losses
resulting from the Contractors or its vendors or Sub-contractors failure to
make timely payment or comply with the reporting, filing or other
requirements hereunder or under Applicable Law with respect to Taxes.
Notwithstanding the foregoing and any other provision to the contrary in this
Agreement, in no event shall the Employer be or become liable to pay or
otherwise be responsible for the payment of any Taxes other than Works
Contract tax.
5.17
Environmental Measures:
The Contractor shall, in discharging its responsibilities under this Agreement,
comply with the applicable environmental laws and requirements and shall
also be responsible for adopting measures required to ensure compliance
under environmental laws. The Contractor shall take all reasonable
precautions to avoid pollution or contamination of the air, land, or river and
ground water arising out of the performance of the Works. Should there be a
discharge or escape of any appreciable quantity of pollutants or contaminants
during performance of its obligations under this Agreement which occurs as a
result of activities of the Contractor or its Sub-Contractors, the Contractor
shall immediately take all action necessary to contain, control, recover, or
disperse the substance and to eliminate the safety and environmental risks
and correct the damage resulting there from in compliance with Applicable
Law. All costs associated with compliance with this Section shall be deemed to
be included in the Contract Price.
5.18
Project Funding:
The Contractor will provide reasonable cooperation and assistance to the
Employer in arranging for the overall financing for the Project, including but
not limited to cooperation with the Employer and the execution of documents
as may be required to convey consent with respect to the assignment of this
Agreement to the Lenders as security for the financing. Such consent and
agreement shall contain provisions that are customary for project financings.
5.19
EMPLOYERS OBLIGATION:
6.1
Permits:
The Employer shall obtain all the Applicable Permits required of it. The
Employer shall provide all reasonable assistance to the Contractor for
obtaining all Applicable Permits for carrying on the Works and in dealing with
any Governmental Authority so as to enable the Contractor to commence and
execute the Works. However, the onuses of obtaining all requisite statutory
permits are on the Contractors.
6.2
Employers Representatives:
a)
b)
The Employers Representative shall carry out the duties specified in, or
necessarily implied from the Agreement and shall exercise the authority
delegated to him, by the Employer. The Employers Representative shall have
no authority to amend the Agreement, to release the Contractor from any of
his duties, obligations or liabilities under this Agreement nor to create any
estoppels against them or the Project Company in respect thereof nor to waive
any right of the Employer under this Agreement. Unless and until the
Employer notifies the Contractor to the contrary, the Contractor shall take
instruction, notices, communication, decisions and approvals only from the
Employers Representative.
6.3
Independent Engineer
The Contractor agrees that it shall bear the fee payable by the Concessionaire
under the Concession Agreement for the services of the Independent Engineer
Page 36
7.1
Contract Price:
The Employer hereby covenants to pay the Contractor, in consideration of
execution and completion of the Works and the remedying of defects therein,
at the times and in the manner and subject to the necessary contractual and
statutory deductions, an amount of Rs.153.31 Crores. only in aggregate
(Price), being the fixed and lump sum consideration subject to adjustment
in accordance with the Agreement. This Contract price shall be paid by the
Employer to the Contractor at the times and in the amounts and manner
specified in Annexure 1 (b) - Billing Schedule for Payment along with
format of item wise work executed as certified by the Lenders Engineer. The
Contractor shall bear all Taxes, duties, specified insurance and fees payable
on the Contract Price. The Contractor shall be deemed to have satisfied itself
as to the correctness and sufficiency of the Contract Price. Unless otherwise
specifically stated in the Agreement, the Contract Price shall cover all its
obligations under the Agreement, all risks it has agreed to undertake under
the Agreement, associated with the performance of its obligations under the
Agreement and all things necessary for the provision of the Works.
7.2
7.3
Mobilization Advance:
Employer shall pay the Contractor an interest free mobilization advance of
an amount equivalent to15% of the Contract price on a date which shall not
be later than 15 days from receipt of first draw down from the Lenders. This
advance shall be recovered from the monthly running account bills of the
Contractor on a proportionate basis of the certified work done value. The
recovery shall commence after completion of 25% of the total work done in
value terms and shall be completed during the period of construction
hereafter.
7.4
Progress Payments:
a)
The Contractor shall submit to the Employer after the end of each month, no
later than 10th calendar day of the succeeding month, three copies of notice in
Page 37
ii)
The Taxes paid on behalf of employer except for taxes which though
have to be paid in the name of employer (but which has to be borne by
the EPC contractor that is on account of project permissions which are
required to be taken for the project by EPC contractor and where such
permissions are given in the name of the principal party only),
demanded of and paid by the Contractor in the relevant Monthly
Period; and
iii)
iv)
and
v)
Less
i)
ii)
iii)
b)
Certificate of Payment: Within 7 (Seven) days after the receipt of the Request
for Payment, the Employers Representative shall, subject to the Contractors
compliance with Section 7.3 inspect the relevant part of the Works and consult
with the Lenders Engineer in order to satisfy himself that the Request for
Payment is correct.
If the Employers Representative is so satisfied, he shall issue a Certificate of
Payment certifying what amounts are due to the Contractor pursuant to this
Page 38
Section 7.3 subject to the provisions of Sub-Section 7.3 (c) (less any amounts
which are subject to a Dispute) after giving credit to the Employer for any
sums to which the Employer is entitled under this Agreement. All Certificate
of Payment shall specify the amount, which the Employer proposes to pay to
the Contractor and the basis on which that amount was calculated. Such
amount shall become due on the issue of the said Certificate of Payment.
c)
In the event the Employer Representative ascertains that the value of the
Works properly executed in the relevant period is less than the Monthly Sum
for that period, he shall include in the Certificate of Payment, the value of the
works so ascertained by him.
d)
7.5
(i)
(ii)
Charges:
ii. to complete the Works which the Contractor has omitted or failed to properly
perform, and provided the Employer has given notice to the Contractor of such
costs and expenses incurred by the Employer and provided there is reasonable
substantiation of such costs and expenses,
the Contractor shall promptly pay or reimburse the Employer for such costs and
expenses on demand. The payment of Bank charges shall be in addition to any other
amounts required to be paid by the Contractor to the Employer hereunder, including
Liquidated Damages.
7.6
Set off:
The Employer may withhold and set off any amount owed by the Contractor to the
Employer determined strictly in accordance with the terms of this Agreement from
any payment due to the Contractor duly informing the Contractor with proper
reasons.
Page 39
7.7
Withholding:
The Employer shall be within its rights to withhold any Taxes which are required to
be withheld prior to making a payment to the Contractor and shall furnish a tax
deduction certificate to the Contractor in respect thereof.
7.8
Mode of Payment:
All payments to the Contractor by the Employer and all payments by the Employer to
the Contractor shall be made by wire transfer to a bank account designated by the
Contractor / Employer as the case maybe or by way of Cheques / Demand Drafts
8.
CHANGE OF SCOPE:
8.1
Consequent upon the exercise of by the Concession Authority its right under
sub-article 16.1 of the Concession Agreement to require changes or additional
works on or about the Project Road which are beyond the scope of the Project
as contemplated by the Concession Agreement (Change of Scope), the
Employer shall have an equivalent right to make the same changes to the
Works by following the procedure set out in Section 8.2. The items and
quantities in the BOQ are indicative and change in BOQ is the responsibility
of the contractor
8.2
a)
b)
Upon receipt of such Change of Scope Notice, the Contractor shall provide to
the Employer, the Concession Authority and the Independent Engineer such
information as is necessary and reasonable together with preliminary
documentation in support of the following:
(i)
the impact, if any, which the Change of Scope is likely to have on the
Implementation Schedule if the work is required to be carried out
before the completion of the Works;
(ii)
Page 40
(iii)
8.3.
a)
In the case of Change of Scope results in additional cost, the Employer shall
reimburse such additional cost to the Contractor as approved by the
Independent Engineer and only to the extent received/entitled to be received
from the Concession Authority by the employer.
b) In the case of Change of Scope results in reduction of cost, the Employer shall
be entitled for an adjustment for such amount as certified by the Independent
Engineer.
9.
9.1
Testing:
a)
For the purposes of determining whether the constructions and works are
being undertaken in accordance with the Design Requirements and
Construction Requirements and to be capable of meeting the O&M
Requirements, the Contractor shall with due diligence carry out all necessary
and periodical Tests in accordance with the instructions and under the
supervision of the MPRDC representative /IE and the Construction
Requirements and the O&M Requirements. The Contractor shall maintain
proper record of such Test and the remedial measures taken to cure the defects
or deficiencies, if any, indicted by the Test results.
b)
Page 41
If the Contractor fails to complete the Punch List items with the said period of
90 days, the Employer may, without prejudice to any other consequences to
which the Contractor is subject to under this Agreement, have such items
completed at the risk and costs of the Contractor. In such an event, the
Contractor shall reimburse to the Employer, the cost incurred in completing
the Punch List Items, with 30 calendar days from the date of receipt of a claim
in respect thereof from the Employer.
d)
9.2
Completion:
The Contractor shall adhere to the Construction Requirements to ensure
achievement of the COD on or before the Scheduled Project Completion Date.
The construction works for the Project Road shall be deemed to be complete to
open to the Traffic only when the Provisional Certificate or the Completion
Certificate is issued by the Independent Engineerin accordance with the
provisions hereof and as specifically laid down in the respective clause of CA.
9.3
9.4
Page 42
(i)
(ii)
(iii)
9.5
Page 43
9.6
9.7
9.8
Further Tests:
If the work involving the remedying of any defect or damage affects the
performance of the Works, the Employer may require the repetition of any of
the Tests described in the Agreement, including Tests on Completion. The
requirement shall be made by providing notice within fourteen (14) days after
the defect or damage is remedied. These Tests shall be carried out at the risk
and cost of the Contractor.
9.9
Performance Certificate:
a)
Page 44
the Contractor, stating the date on which the Contractor completed its
obligations under the Agreement.
b)
The Employer shall issue the Performance Certificate within Fourteen (14)
days after the latest of the expiry date of the Defects Liability Period for
defects other than those attributable to design of the Works or as soon
thereafter as the Contractor has supplied all the Contractors Documents and
completed and tested all the Works, including remedying any defects.
c)
d)
9.10
Unfulfilled Obligations:
After the Performance Certificate has been issued, each Party shall remain
liable for the fulfillment of any obligation, which may have remained
unperformed at that time. For the purposes of determining the nature and
extent of unperformed obligations, the Agreement shall be deemed to remain
in force.
10.
MAINTENANCE:
10.1
10.2
a)
b)
The Contractor shall be responsible for all traffic management on the existing
road forming and for maintenance of the existing road and the Project
Facilities under construction at the levels necessary to allow smooth flow of
traffic. The traffic levels to be maintained by the Contractor, shall, at no time
be at a level lower than that of the existing road till the time the construction
work is commenced on the existing road for its conversion into the Project
Facilities
Page 45
c)
The Contractor shall be responsible for all liabilities arising from the alternate
traffic arrangements, all traffic management and maintenance of the existing
road. The cost of maintenance of the existing road, traffic management,
diversions and maintenance of diversions during construction, markings and
signs, lookout persons, construction of temporary cross-drainage works, and
other similar works during the Implementation Period shall be deemed to have
been included in the Contract Price. The Contractor shall plan, organize and
execute the works in a manner so as to cause least disruption to the flow of
traffic and minimal inconvenience to the users. Such operations which involve
road diversions or any other impediments of like nature shall be made
pursuant to the consent of the Employers Representative, for which adequate
notice shall be given by the Contractor. The Contractor shall liaise with
regulatory authorities and various Governmental Authorities before affecting
the aforementioned steps excluding emergencies.
d)
e)
Prior to the execution of the Work the Contractor shall have prepared and
obtained the approval thereto of the Employers Representative for a
maintenance plan for the Project during the Implementation Period (the
Maintenance Plan-Implementation Period) which shall inter- alia include:
(i)
(ii)
(iii)
And shall ensure that the Implementation Plan and the Maintenance
Plan-Implementation period comply with the Project Requirements.
10.3 The Contractor in consultation with the Employer shall prepare and deliver to
the Employer prior to making an application for the Provisional Certificate or
the Completion Certificate (whichever is earlier) the operation and
maintenance manual which provides the Employer with such information as it
requires to operate and maintain the Project Facilities and comply with its
obligations under the Concession Agreement.
11.
11.1
b)
Liquidated Damages:
a) The contractor shall pay damages (Liquidated Damages) to the Employer for
delay in completion of the project milestones as defined in the Concession
Agreement and in section 9.2.
If the Contractor fails to comply with the time for completion of the whole
works or part of the works, the contractor shall pay to the employer liquidated
damages for such defaults which shall be equivalent to the liquidated damages
imposed on the Employer by MPRDC for delay in the project, reduced to the
proportion which the length of EPC project Road bears to the Length of the Project
road. The employer may, without prejudice to any other method of recovery, deduct
the amount of such damages from any monies due or to become due to the Contractor.
The payment or deduction of such damages shall not relieve the Contractor from his
obligation to complete the works.
11.2
Bonus:
No Bonus shall be payable due to early completion of the project.
12.
FORCE MAJEURE:
12.1
12.2
Obligation to Notice:
a)
As soon as practicable and in any case within 28 calendar days of the date of
occurrence of a Force Majeure Event or the date of knowledge thereof, the
Affected Party shall notify the other Party of the Force Majeure Event setting
out, inter alia, the following in reasonable detail:
(i)
(ii)
(iii)
Page 47
b)
(iv)
the measures which the Affected Party has taken or proposes to take to
alleviate/mitigate the impact of the Force Majeure Event and to resume
performance of such of its obligations affected thereby; and
(v)
(ii)
(iii)
c)
The Affected Party shall during the Force Majeure Period provide to the other
Party with regular (not less than weekly) reports concerning the matters set
out in the preceding clause (ii) as also any information, details or document,
which the other Party may reasonably require.
12.3
Performance of Obligations:
If the Affected Party is rendered wholly or partially unable to perform any of
its obligations under this Agreement because of a Force Majeure Event, it
shall be excused from performance of such obligations to the extent it is unable
to perform the same On account of such Force Majeure Event provided that:
(i)
(ii)
the Affected Party shall make all reasonable efforts to mitigate or limit
damage, if any, caused or is likely to be caused to the Project Facilities as a
result of the Force Majeure Event and to restore the Project Facilities, in
accordance with the Good Industry Practice and its relative obligations under
this Agreement;
Page 48
(iii)
The Affected Party shall take all remedial measures including duly
prosecuting and exhausting all such remedies available to the Affected Party
under the Applicable Laws;
(iv)
when the Affected Party is able to resume performance of its obligations under
this Agreement, it shall give to the other Party written notice to that effect
and shall promptly resume performance of its obligations hereunder; and
(v)
The Affected Party shall continue to perform such of its obligations which are
not affected by the Force Majeure Event and which are capable of being
performed in accordance with this Agreement.
12.4
a)
Termination:
The Contractors employment shall terminate automatically if the Concession
Agreement is terminated as a result of Force Majeure under provisions of the
Concession Agreement.
b)
Obligation of Parties:
Following the Termination, the Parties shall promptly take all such steps as
may be necessary or required to ensure that:
(i)
c)
Termination Payment:
Pursuant to Termination of the Agreement under Sub-Section 12.4 (a), the
Contractor shall, subject to the rights (if any, available under the financing
documents) of the Lenders, be entitled to receive from the Employer out of the
insurance proceeds or otherwise by way of Termination Payment an amount
equal to:
(i)
The amounts payable for Works carried out as per specifications up to the
Termination Date less payments made under Section 7.3;
(ii)
The cost of materials ordered for the Works which have been delivered to the
Contractor and/or of which the Contractor is liable to accept delivery, such
Page 49
materials shall become the property of (and be at the risk of) the Employer
when paid for by the Employer, and the Contractor shall place the same at the
Employers disposal; and
(iii)
12.5
13.
13.1
Events of Defaults:
Event of Default means either Contractors Event of Default or Employers
Event of Default or both as the context may admit or require.
a)
(ii)
The Contractor
Requirements.
(iii)
(iv)
is
in
Material
Page 50
Breach
of
the
Maintenance
b)
(v)
(vi)
(vii)
(viii)
The Contractor has delayed any payment that has fallen due under this
Agreement for 70 calendar days or more.
(ix)
(x)
(xi)
Any petition for winding up of the Contractor has been admitted and
liquidator or provisional liquidator has been appointed or the
Contractor has been ordered by Court of competent jurisdiction except
for the purpose of amalgamation or reconstruction with the prior
consent of the Employer.
(i)
(ii)
(iii)
Employer has delayed payment of any amount that has fallen due in terms of
this Agreement beyond 45 calendar days.
Page 51
(iv)
13.2
a)
Without prejudice to any other right or remedy which Employer may have in
respect thereof under this Agreement, upon the occurrence of a Contractors
Event of Default, Employer shall be entitled to terminate this Agreement by
issuing Termination Notice.
(i)
Without prejudice to any other right or remedy which the Contractor may have
in respect thereof under this Agreement, upon the occurrence of Employer
Event of Default, the Contractor shall be entitled to terminate this Agreement
by issuing Termination Notice.
(ii)
Page 52
(iii)
c)
d)
Termination Notice:
If a Party having become entitled to do so decides to terminate this Agreement
pursuant to the preceding sub-sections (a) or (b), it shall issue Termination
Notice setting out:
(i)
(ii)
The Termination Date which shall be a date occurring not earlier than 50
calendar days from the date of Termination Notice;
(iii)
(iv)
e)
Obligation of Parties:
Page 53
Until Termination the Parties shall, to the fullest extent possible, discharge
their respective obligations so as to maintain the continuity of services to the
users of the Project Facilities,
(ii)
(iii)
f)
13.3
Termination Payment
a)
In the case of Contractors Event of Default, the Contractor shall be eligible for
any Termination Payment to that extent due to him till termination.
b)
In the case of Employers Event of Default, the Contractor shall be eligible for
amounts certified as due to him till termination date by the Employers
Representative. Provided that the Employer shall be entitled to deduct from
the Termination Payment any amount due and recoverable by the Employer
from the Contractor as up to the Termination Date.
13.4
a)
b)
Right of Parties:
Notwithstanding anything to the contrary contained in this Agreement,
Termination pursuant to any of the provisions of this Agreement shall be
without prejudice to accrued rights of either Party including its right to claim
and recover money damages and other rights and remedies which it may have
in law or contract. The rights and obligations of either Party under this
Agreement, including without limitation those relating to Termination
Payment, shall survive the Termination but only to the extent such survival is
necessary for giving effect to such rights and obligations.
14.
DISPUTE RESOLUTION:
14.1
Amicable Resolution
a)
Save where expressly stated to the contrary in this Agreement, any dispute,
difference or controversy of whatever nature howsoever arising under, out of or
in relation to this Agreement, including non-completion of the Works, between
the Parties and so notified in writing by either Party to the other (the
Dispute) in the first instance shall be attempted to be resolved amicably in
accordance with the conciliation procedure set forth in Sub Section 14.1(b)
below.
b)
In the event of any Dispute between the Parties, either Party may call upon
the Employers Representative to mediate and assist the Parties in arriving at
an amicable settlement thereof. Failing mediation by the Employers
Representative or without the intervention of the Employers Representative,
either Party may require such Dispute to be referred to the CEO of the
Employer and the CEO of the Contractor, for the time being for amicable
settlement. Upon such reference, the CEOs of the Contractor and the
Employer shall meet not later than seven (7) days after the date of such
request to discuss and attempt to amicably resolve the Dispute. If such
meeting does not take place within the said period or the Dispute is not
amicably settled within fifteen (15) days of such meeting between the CEOs,
either Party may refer the Dispute to mediation in accordance with Section
14.2 or arbitration in accordance with the provisions of Section 14.3.
14.2
Mediation
Page 55
a)
If the Dispute is not amicably resolved the Employer or the Contractor may
within a period of thirty days (30) days after the periods stipulated in SubSection 14.1 (b), give notice to the other Party of its intention to refer the
Dispute to mediation (hereinafter referred to as the Request for Mediation).
b)
Provided, however, if the Request for Mediation is served after the expiration
of the thirty (30) day time limit stipulated in Sub-Section 14.2 (a), the
recipient shall not be obliged to participate in a mediation and the mediation
shall not proceed further without the recipients written consent.
c)
Upon the Dispute being resolved through mediation, such resolution shall be
recorded in a settlement agreement and the Parties shall give effect to this
Agreement accordingly.
14.3
Arbitration
a)
b)
14.4
Pending the submission of and/or decision on a dispute and until the arbitral
award is published; the parties shall continue to perform their respective
obligations under this Agreement, without prejudice to a final adjustment in
accordance with such award.
15.
15.1
a)
Page 56
The Contractor represents that it has inspected the Site and has reviewed
weather data, marine data and all other data provided by the Employer and as
required for the Contractor to enter into this Agreement. The Contractor
represents that the Site is an acceptable place to perform that portion of the
Works required to be performed at the Site and has sufficient lay down areas
and access.
c)
The Contractor represents that it has satisfied itself with respect to all
conditions and circumstances affecting the Works, including the general and
local conditions; technical information and Maintenance Requirements; access
and egress; disposal, handling, and storage of materials; availability and
conditions of roads and rights-of-way; availability of labour and housing;
climatic conditions and seasons and equipment and facilities needed for
performance of the Works.
d)
The Contractor represents that it is satisfied with the proximity of the existing
road to adjacent facilities and structures as proposed mentioned in the Site
and Project Facilities.
e)
f)
g)
The Contractors failure to acquaint itself with any applicable condition, will
neither relieve it from the responsibility for successfully performing this
Agreement, nor entitle the Contractor to a variation order adjusting the
Contract Price or the time for performance.
h)
and be responsible for the correctness of the Works under this Agreement. No
extra charge or compensation will be allowed for duplication of Works because
of an unverified difference between an actual dimension and the measurement
indicated in the specifications. Any discrepancy shall be submitted in writing
to the Employer for consideration before proceeding with the Works.
i)
j)
The Contractor is not in violation of any Applicable Law which for either an
individual violation or for a number of violations in the aggregate would
adversely affect its ability to perform its obligations under this Agreement.
k)
The Contractor is the holder of all national, state, local, or other governmental
consents, licenses, permits, or other governmental authorizations required to
conduct its business.
l)
m)
The Contractor by itself and through its Sub-Contractors possesses the full
experience and proper qualifications to perform the Works and to construct the
Project Facilities, including the requisite knowledge of and experience with the
relevant legal, labour and regulatory conditions in India. The Contractor
asserts that it is experienced in the design and procurement and supply of
equipment to be used in the construction of Project Facilities and that it
realizes that completion and refinement of detailing will occur during
performance of this Agreement
n)
The Contractor has obtained, or has no reason to expect that it will not in due
course and without undue delay obtain all Applicable Permits.
Page 58
o)
The Contractor further agrees that it will notify the Employer if at any time
prior to the COD any of the foregoing representations and warranties ceases to
be accurate and complete in any material respect.
15.2
The Employer has full power and authority to enter into this Agreement and
perform/disclose their obligations contained therein;
b)
The Employer has taken all necessary action to authorize the execution,
delivery and performance of this Agreement.
c)
This Agreement constitutes the Employers legal, valid and binding obligation
enforceable in accordance with the terms thereof
15.3
16.
16.1
Effective Date
This Agreement shall be valid and effective from the date first hereinabove
written.
16.2
16.3
Notice to Proceed
The Employer may issue the Notice to proceed at any time after it has achieved
Financial Closing for the financing of the Facilities.
16.4
Termination
Page 59
MISCELLANEOUS
17.1
Waiver
The failure of either Party to insist in any one or more instances upon strict
performance of any provisions of this Agreement or the waiver with respect to
any default or any other matter hereunder, shall not be construed as a waiver
with respect to any subsequent performance, default or matter. No waiver of
any of the terms or conditions hereof shall be valid or binding unless made in
writing and duly executed by both the parties.
17.2
Benefit
This Agreement and all rights hereunder are intended solely for the benefit of
the Parties hereto, and to the extent provided hereto, for the benefit of the
persons indemnities, and shall not imply or create any rights on the part of, or
obligations to, any other person.
17.3
Independent Contractor
The Parties are independent. This Agreement shall not be interpreted or
construed to create an association, joint venture, or partnership between the
Parties or to impose any partnership obligation or liability upon either Party.
Neither Party shall have any right, or authority to enter into any agreement or
undertaking for, or act on behalf of, or to act as or be an agent or
representative of, or to otherwise bind, the other Party, unless expressly
agreed otherwise
17.4
Lenders Approval
The Parties recognize that the terms and conditions of this Agreement would
be subject to the approval of the Lenders and agree to incorporate such
changes as may be required without materially altering the commercial
position agreed hereunder. If, as result of a review by the Lenders, additional
changes are required, the Parties agree to discuss and agree to such changes
in good faith.In case of any contradiction between terms and conditions hereof,
and documents executed with lender(s); terms and conditions as executed with
Lender(s) shall have precedence over the terms and conditions stipulated
hereof.
Page 60
17.5
Survival
Cancellation, expiration or earlier Termination of the Agreement (i) shall not
relieve the Contractor or the Employer of any obligations hereunder which
expressly or by implication survive Termination hereof; and (ii) except as
otherwise provided in any provision of the Agreement expressly limiting the
liability of either Party, shall not relieve either Party of any obligations or
liabilities for (x) loss or damage to the other Party arising out of or caused by
acts or omissions of such Party prior to the effectiveness of such Termination
or arising out of such Termination; and (y) warranties, remedies, promises of
indemnity and confidentiality.
17.6
Language
All notices, demands, requests, statements, instruments, certificates,
drawings, documents or other communications given, deli or made by, or on
behalf of, either Party to the other under or in connection with this Agreement
shall be in English. The Contractor shall be responsible for the accuracy of the
translation of any document submitted by it to the Employer.
17.7
Severability
Any provision hereof which is prohibited or unenforceable in any jurisdiction
shall, as to such jurisdiction, be ineffective to the extent of such prohibition or
unenforceability without invalidating the remaining provisions hereof and
without affecting the validity or enforceability of any provision in any other
jurisdiction.
17.8
Entire Contract
This Agreement, together with all Attachments, appendices and any valid
variation orders and amendments constitutes one contract between the Parties
with respect to the matters set out herein, unless specified otherwise in
separate agreement entered into by parties hereto.
17.9
Other Documents
Each Party agrees to execute and deliver any instruments and to perform any
acts which may be necessary or reasonably requested in order to give full effect
to the intent and purpose of this Agreement.
17.10 Amendments
No amendments, supplements or modifications of this Agreement shall be
valid unless evidenced in writing and signed by duly authorized
representatives of both Parties.
Page 61
17.11 Notices
Unless otherwise stated, notices to be given under this Agreement including
but not limited to a notice of waiver of any term, breach of any term of this
Agreement and termination of this Agreement, shall be in writing and shall
be given by hand delivery, recognized international courier, mail, telex or
facsimile transmission and delivered or transmitted to the Parties at their
respective addresses set forth below:
If to Employer:
The Director,
AGROH BIAORA TOLLWAYS PVT. LTD.
Subject to sub-sections (b) and (c) herein below, neither Party shall assign this
Agreement nor the rights, benefits nor obligations hereunder save and except
with prior consent of the other Party.
b)
Except as provided in Sub-Section (c) herein below, the Contractor shall not
create nor permit to subsist any Encumbrance over or otherwise transfer or
dispose of all or any of its rights and benefits under this Agreement except
with prior consent in writing of Employer, which consent Employer shall be
entitled to decline without assigning any reason whatsoever.
Page 62
c)
(i)
Restraint set forth in Sub-Sections (a) and (b) above shall not apply to:
liens/encumbrances arising by operation of law (or by an agreement evidencing
the same) in the ordinary course of business of the Contractor;
(ii)
(iii)
17.13 Law
The Agreement shall be construed and interpreted in accordance with and
governed by the laws of India and the Courts in the City of Chittor,Madhya
Pradeshshall have exclusive jurisdiction over all matters arising out of or
relating to the Agreement.
17.14 Counterparts
The Parties hereto may sign the Contract in any number of counterparts, all of
which taken together shall constitute one and the same instrument.
Page 63
ANNEXURE 1
A. SCOPE / BOQ OF THE WORK SCOPE OF EPC CONTRACTOR
ABSTRACT OF COST
TWO-LANING OF BIAORA-MP/RAJASTHAN ROAD SECTION OF NH-12 IN
THE STATE OF MADHYA PRADESH
S. No.
Item of Work
Bill No.
Rs
Bill 1 Total
1434487
Bill 2 Total
76839506
Bill 3 Total
245851530
Bill 4 Total
Bill 5 Total
310902990
Bill 6 Total
71006435
Bill 7 Total
20357869
Miscellenaous
Bill 8 Total
Maintenance
Bill 9 Total
10
Additional Items
Bill 10 Total
106178354
685779315
1518350486
151.84
1.47
153.31
*Cost interse in the heads is not fixed and mandatory and may change within the
total EPC construction cost.
Page 64
Sr.No.
Milestone Events
%age of
Milestone
Contract
Amount (in
value
Crores)
0.09%
0.14
5.01%
7.68
16.04%
24.59
44.73%
68.58
20.28%
31.09
4.63%
7.10
1.33%
2.04
Miscellenaous
0.00%
0.00
Maintenance
0.00%
0.00
10
Additional Items
6.93%
10.62
96.15%
151.84
0.96%
1.47*
100.00%
153.31
Page 65