Professional Documents
Culture Documents
Y
JAMMU
DETAILED PROJECT REPORT
(P.M.G.S.Y)
DISTRICT POONCH
Name of the Road
: Upgradation/Widening of Road
from Mendhar to Jaranwali Gali
Length of road
: 21.00 Kms
Construction Cost
: Rs. 3243.38 Lacs
Maintenance Cost
: Rs. 259.47 Lacs
Total Cost
: Rs. 3502.85 Lacs
Package No.
: JK 11-146
Block
: Mendhar
CHIEF ENGINEER
PMGSY (JKRRDA)
JAMMU
A. Contents
1.
Technical Report
2.
3.
Topographic Survey.
4.
5.
Traffic Survey
6.
Hydrological Survey
7.
8.
Alignment Design
9.
Pavement Design
10.
11.
12.
Land Acquisition
13.
Utility shifting/relocation
14.
15.
Specification
16.
Environmental Issues
17.
Analysis of Rates
18.
Cost Estimate
19.
Construction Program
B. Proforma
1.
2.
3.
4.
5.
6.
7.
Proforma B
Package Summary
Proforma C
Check List for PIU & STA
Format F1
Package-wise Summary Sheet
Format F2A
Roads proposed in PMGSY for Rural Connectivity
Format F2B
Pavement Layers
Format F3
Typical Cross Section of Existing Pavement
Format F4
Typical proposed cross section in Straight Section Flexible
Pavement
8. Format F5
Summary: Cost Estimate
9. Format F6
Cost estimate for Road Construction Works Pavement Works
10.Format F7
Cost estimate for Cross Drainage Works Slab Culvert
11.Format F8
Rate of Materials supplied at site Rate Analysis
12.Format F9A
Certificate of Ground Verification from Executive Engineer / Head
of PIU
13.Format F9B
List of DPRs verified on Ground
14. Environmental Checklist
15.Checklist for community consultation on engineering
C. List of figures
Figure-1
Figure-2
Figure-3
Figure-4
Figure -5
D. Annexure
Annexure-1
Annexure-2
Annexure-3
Annexure-4
1.
Technical Report
1.1
1.3
Core Network
The rural road network required for providing the basic access to all villages/
habitations is termed as the Core Network. Basic access is defined as one allweather road access from each village/ habitation to the nearby Market
Centre or Rural Business Hub (RBH) and essential social and economic
services.
The Core Network may not represent the most convenient or economic route
for all purposes. However, since studies show 85-90% of rural trips are to
market centres, the Core Network is likely to be a cost-effective conceptual
The Sub-project road from Mendhar to Jaranwali Gali Road, is a link road with
Code {LO28,L029, L030, L031, L32, L033,L034, & L035} in MENDHAR
block of {poonch} District. This road directly connects the habitations of
{ Ari(L), Harni, Phamranar, Gursai Hurmuta, Gursai Nahlla, Gursai & Jaranwali Gali } with
populations of {3000,1030,3044,3227, souls } respectively. Thus this link road
serves the total population of {14500 souls }.
1.4
Geography
The upgradation/widening road takes off from Mendhar to Jaranwali Gali Road. The
whole road passes through Mountainous terrain.
1.5
1.6
Climatic Condition
The terrain traverses from 650 to 750 M above MSL and is steep terrain in nature. The average
rainfall is about 500mm per year and the temperature ranges between (-) 3-15C during winter and
18-37C during summer.
The road passes through hilly terrain .The road provides connectivity to
Villages Ari(L), Harni, Phamranar, Gursai Hurmuta, Gursai Nahlla, Gursai & Jaranwali Gali
three Primary schools, four, Middle schools, three High Schools & one Higher
Sec. School are also connected by this road. Protection works and CD Works
are to be provided through the road.
District:
Block:
Road Name:
Road Code:
Package No:
Road Length:
Start Point:
End Point:
Sl.No.
Poonch
Mendhar
Mendhar to Jaranwali Gali
21.00 Kms
Gohlad (Lower)
Jaranwali Gali
Habitation
benefited
Population benefited
Chainage
1.
Ari (L)
Direct
3000
Indirect
4500
From
1/00
To
2/925
2.
Harni,
1030
2000
2/950
7/00
3.
Gursai Hurmuta
3300
3600
7/00
9/300
4.
Gursai Nahlla
1498
2300
9/300
11/500
5.
Phamranar
3044
3872
11/500
16/200
6.
Gursai
3227
10000
16/200
19/500
7.
Jaranwali Gali
2290
2895
19/500
21/00
2.
2.1
Key maps
Figure-1 Section of Block Maps showing all existing connectivity like District/block
HQ,
new townships, National and State highway network, mandis, hospitals, colleges,
schools etc.
PHOTOGRAPHS
CHAINAGE
Chainage 0.00km
Take off point of road private shopes on both sides
of road.
Chainage 0.100km
Agriculture land on left side of road.
Shops on right side of road.
Chainage 0.175km
Agriculture land on both side of road.
Chainage 0.375
Agriculture land on both side of road.
Chainage 0.500km
Agriculture land on both side of road.
Chainage 0.575km.
House on left side of road.
Chainage 0.650km
Private land on both side of road alignment.
Chainage 0.900km
Agriculture land on both side of road alignment.
Chainage 1.000km
Private land of both sides of road alignment.
Chainage 1.200km
Private land on both side of roa d alignment.
11
Chainage 1.300km
Private land on both side of road alignment.
12
chainage 1.400km
Damaged R/wall. Private land on both side of the
road
13
14
Chainage 1.800km
House on left side of the alignment of road.
15
Chainage 2.00km
Private shops on both side of the road
16
Chainage 2.100k
Private house on both side of the road
17
Chainage 2.200km
Hair pin curve. Private land on both side of the road
18
Chainage 2.300km
3.00 M Span R.C.C Culverts. Private land on both
side of the road
19
Chainage 2.450km
Hair pin curve. Private land on both side of the road
20
Chainage2.650km
Scupper. Private land on both side of the road
21
Chainage 2.700km
Shops on both side of the road.
22
Chainage2.825km
Damaged hume pipe culvert. Private land on both
side of the road
23
Chainage 2.900km
Private land on both side of the road alignment.
24
Chainage 3.000km
Damaged R/WALL. Private land on both side of the
road alignment.
25
Chainage 3.200km
3.00M span R.C.C culvert. Private land on both side
of the road alignment.
26
Chainage 3.400km
Private land on both side of the road alignment.
27
Chainage 3.600km
Private land on both side of the road alignment.
28
Chainage 3.800km
Private land on both side of the road alignment.
29
Chainage 3.900km
Private land on both side of alignment of road.
30
Chainage 4.000km
Private land on both side of the road alignment.
Private land on both side of the road alignment..
31
Chainage 4.300km
Private land on both side of alignment of road.R/wall
on left side of the road alignment.
32
Chainage 4.800km
Private land on both side of alignment of road.
33
Chainage 5.000km
Private land on both side of the road alignment..
34
Chainage 5.100km
Private land on both side of the road alignment.
35
Chainage 5.150km
Private land on both side of the road alignment.
36
Chainage 5.200km:
Private land on both side of the road alignment.
37
Chainage 2.900km
Private land on both side of alignment of road.
38
Chainage 5.525km
3.00M span culvert.Private land on both side of
alignment road.
39
Chainage 5.825km
Private land on both side of the road alignment.
40
Chainage 5.925km
Private land on both side of the road alignment..
41
Chainage 6/00km
R/wall on Left side of road.
Private land on both side of the road alignment..
42
Chainage 6/500km
B/wall on Left side of road.
Private land on both side of the road alignment..
43
Chainage 6/600km
Private land on both side of the road alignment..
44
Chainage 6/700km
Private house on both side of the road alignment..
45
Chainage 6/800km
Mosque on left side of the road alignment..
10 M Span Bridge.
46
Chainage 6/900km
10 M Span Bridge.
47
Chainage 7/00km
B/wall on left side of the road alignment..
48
Chainage 7/100km
Private land on both side of the road alignment..
49
Chainage 7/200km
Private land on both side of the road alignment..
50
Chainage 7/300km
B/Wall on left side of the road alignment..
51
Chainage 7/400km
B/Wall on left side of the road alignment..
52
Chainage 7/500km
B/Wall on left side of the road alignment..
53
Chainage 7/500km
Private land on both side of the road alignment..
54
Chainage 7/600km
Private house on right side of the road alignment..
55
Chainage 7/700km
Private house on left side of the road alignment..
56
Chainage 7/800km
Private land on left side of the road alignment..
57
Chainage 7/900km
Private land on rigth side of the road alignment..
58
Chainage8/00km
Private land on right side of the road alignment..
59
Chainage8/100km
Private land on right side of the road alignment..
60
Chainage8/200km
Private land on right side of the road alignment..
61
Chainage8/300km
Private land on right side of the road alignment..
62
Chainage8/400km
Private land on right side of the road alignment..
63
Chainage8/500km
Private land on right side of the road alignment..
64
Chainage8/600km
Private land on right side of the road alignment..
65
Chainage8/800km
Private land on right side of the road alignment..
66
Chainage9/00km
Private land on right side of the road alignment..
67
Chainage9/200km
Private land on right side of the road alignment..
68
Chainage9/400km
Private land on right side of the road alignment..
69
Chainage9/600km
Private land on right side of the road alignment..
70
Chainage9/900km
Forest land on left side of the road alignment..
71
Chainage10/00km
Damage B/wall on right side of the road alignment..
72
Chainage10/200km
Slide on the road alignment..
73
Chainage10/400km
Forest land on both side of the road alignment..
74
Chainage10/600km
Forest land on both side of the road alignment..
75
76
Chainage10/800km
Forest land on both side of the road alignment..
78
Chainage11/00km
Forest land on both side of the road alignment..
79
Chainage11/500km
Forest land on both side of the road alignment..
80
Chainage11/700km
Forest land on both side of the road alignment..
81
Chainage11/900km
Forest land on both side of the road alignment..
82
Chainage12/200Km
Forest land on both side of the road alignment..
83
Chainage12/300Km
Forest land on both side of the road alignment..
84
Chainage12/500Km
Shops on both side of the road alignment..
85
Chainage12/700Km
Private shops on left side of the road alignment..
86
Chainage12/800Km
Private land on both side of the road alignment..
87
Chainage13/00Km
Private land on both side of the road alignment..
88
Chainage13/100Km
Private land on both side of the road alignment..
89
Chainage13/300Km
Private shops on both side of the road alignment..
90
Chainage13/500Km
Private house on right side of the road alignment..
91
Chainage13/600Km
Private house on right side of the road alignment..
92
Chainage13/800Km
Damage R/wall on left side of the road alignment..
93
Chainage13/900Km
Private shops on both side of the road alignment..
94
Chainage14/00Km
Private shops on both side of the road alignment..
95
Chainage15/600Km
Private shops on both side of the road alignment..
96
Chainage15/800Km
Private shops on both side of the road alignment..
97
Chainage16/00Km
Private shops on both side of the road alignment..
98
Chainage16/300Km
Private shops on both side of the road alignment..
99
Chainage16/700Km
Private land on both side of the road alignment..
100
Chainage17/00Km
Private land on both side of the road alignment..
101
Chainage17/300Km
Private land on both side of the road alignment..
102
Chainage17/400Km
Private land on both side of the road alignment..
103
Chainage18/00Km
Private land on both side of the road alignment..
104
Chainage18/500Km
Forest land on both side of the road alignment..
105
Chainage18/800Km
Forest land on both side of the road alignment..
106
Chainage18/900Km
Forest land on both side of the road alignment..
107
Chainage19/00Km
Forest land on both side of the road alignment..
108
Chainage19/100Km
Forest land both side of the road alignment..
109
Chainage19/200Km
Private land left side of the road alignment..
110
Chainage19/400Km
Private land left side of the road alignment..
111
Chainage19/500Km
Private land left side of the road alignment..
112
Chainage19/700Km
Private land left side of the road alignment..
113
Chainage19/800Km
Private land left side of the road alignment..
114
Chainage19/925Km
Private land left side of the road alignment..
115
Chainage20/00Km
Private land left side of the road alignment..
116
Chainage20/00Km
Private land left side of the road alignment..
117
Chainage20/100Km
Private land left side of the road alignment..
118
Chainage20/300Km
Private land left side of the road alignment..
119
Chainage20/400Km
Private land left side of the road alignment..
120
Chainage20/600Km
Private land left side of the road alignment..
121
Chainage20/800Km
Private land on both side of the road alignment..
122
Chainage20/900Km
Private land both side of the road alignment..
123
Chainage21/00Km
Private land left side of the road alignment..
S
l.
1
Location
Issue
Design Solutions
Ch. 0.00km
The
road
is
connecting
Mendhar
village with
Jaranwali Gali
village. The
road starts between the
builtup area .
Ch.0 to 0.500 km
Ch 1.0 to 1.300
km
Ch. 1.300 to
2.450 km
Ch. 2.450 to
2.900 km
Ch. 2.900
to3.200 km
Ch. 3.200 to
4.600km
Ch. 4.600
to5.175 km
1
0
Ch. 5.175 to
5.750km
1
1
1
2
1
3
1
4
Ch. 10.00 to
through
Protection
work
proposed to protect
is
2.5
Chainage
Exist
ing
Land
Widt
h*
Additio
nal
Land
Requir
ed
LH
R
S
HS
3
4
2
5
4
4
4
2
0+150
1+700
2+700
0+325
3
4
4
6
2+425
2+900
2/925-3/00
3/00-4/00
5.00-5.500
6/00 7.00
8/00 9/00
10/00-11/00
11/00-12/00
12/50012/900
13/0013/500
13/500/14/0
0
14/00-15/00
15/00-16/00
17/00-18/00
18/0019/500
19/50020/00
20/50021/00
2.
5
2.
5
2.
5
2.
5
2.
5
2.
5
2.
5
2.
5
2.
5
2.
5
2.
5
2.
5
2.
5
2.
5
2.
5
2.
5
2.
5
Type of Loss
LHS
RHS
Shops
Houses
Masque
AGRICULT
URE LAND
Agriculture
Land
Agriculture
Land
School
Shops
Houses
Shops
NALLAH
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Forest
Land
Forest
Land
Agriculture
Land
Forest
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Agriculture
Land
Forest Land
Village
Ari (L)
Harni
Gursai
Hurmut
a
Gurssai
Nahlla
Forest Land
Agriculture
Land
Forest Land
Agriculture
Land
Agriculture
Land
Phama
nar
Jaranwa
li Gali
Remarks/Sugg
estions
No
Yes
No
No
Yes
Yes
No
No
Topographic Survey
3.1
General
Topographic survey true to ground realties have been done using Dumpy
level, tape staff,
The in-house standards, work procedures and quality plan prepared with
reference to IRC: SP 19-2001, IRC: SP 20, IRC: SP 13 (in respect of surveys for
rivers/streams) and current international practices have been followed during
the above survey.
3.2
Traversing
Traverse has been done by using prismatic compass.
3.3
Leveling
Leveling has been done using Dumpy level with height of instrument method.
3.4
3.5
Data Processing
All data from topographic survey recorded by dumpy level were recorded on
graph sheets manually and final alignment, plan, profile were prepared
3.6
3.7
Checklist
Yes
No
No
Yes
Yes
No
No
4.
4.1
General
The soil and material investigations were done following the guidelines of IRC:
SP: 20-2002 and IRC: SP: 72-2007 and other relevant IS codes. The potential
sources of borrow areas for soil and quarry sites have been identified.
4.2
4.3
to
Km 8th
5%
Km 9th
6.50%
10
Km 10th
5.1%
11
Km 11th
7.3%
12
Km 12th
7.3%
13
Km 13th
5.6%
14
Km 14th
6.5%
15
Km 15th
6.1%
16
Km 16th
8.1%
17
Km 17th
8%
7% .The soil
18
19
20
21
4.4
Km 18th
Km 19th
Km 20th
Km 21st
8%
6.1%
5.7%
7.6
Figure -3
Quarry Map
4.5 Checklist
Borrow pit suitable
Yes
SSI for existing ground
Investigation for coarse/fine aggregate
Quarry map
No
Yes
Yes
Yes
No
No
No
5.
Traffic Survey
5.1
General
In the present scenario of new connectivity, 3 day, 24 hr traffic volume count
has been conducted on the already completed or similar type of PMGSY road
in the vicinity of the project road. The Classified Volume Count survey has
been carried out in accordance with the requirements of the TOR and
relevant codes (IRC: SP: 19-2001, IRC: SP: 20, IRC: SP: 72-2007).The surveys
have been carried out by trained enumerators manually under the monitoring
of Engineering Supervisor.
5.2
5.3
Sl. No.
Type of Vehicle
Day-1
Day-2
Day-3 Average
1
Car, Jeep, Van, Auto Rickshaw
50
60
55
55
2
LCV
70
75
65
70
3
Scooters/Motorbikes
80
85
90
85
4
Bus / Minibus
7
6
6
6
5
Trucks
10
9
8
9
6
Tractors with trailer
30
32
35
32
7
Tractor without trailer
30
32
35
32
8
Cycles
8
8
4
7
9
Cycle Rickshaw / Hand Cart
10
Horse cart / Bullock Cart
11
Pedestrian
100
110
105
105
Total commercial vehicle per day (cvpd) 100
Total motorised vehicle per day
130
Total non-motorised vehicle per day
6
a) Traffic volume and mix do not vary along the road
b) Traffic volume and mix vary along the road
c) Traffic volume and mix will vary along the road in the future
d) There is a potential for through traffic using the road
e) % of loaded vehicles
Traffic Growth Rate and forecast
Type of Vehicle
Car, Jeep, Van, Auto Rickshaw
LCV
Scooters/Motorbikes
Bus / Minibus
Trucks
Tractors with trailers
Tractors without trailers
8
Cycles
9
Cycle Rickshaw / Hand Cart
10
Horse cart / Bullock Cart
11
Pedestrian
Total commercial vehicle per day (cvpd)
Total motorised vehicle per day
Total non-motorised vehicle per day
ADT
AADT
Growth
Rate
213.83
6%
55
70
85
12
19
32
25
7
28
298
7
6.
Hydrological Survey
6.1
General
Hydrological survey is necessary for design of adequate and safe Cross
Drainage Structures so that the rain water can pass as per natural slope.
Hydrological survey of the proposed road is based on the following
observations:
6.2
Rainfall Data
Catchments Area
Time of Concentration
Existing Cross Drainage Structures
Rainfall Data
Rainfall Data as applicable for the project road were collected with maximum
rainfall occurring in the months of July to September.
6.3
Catchment Area
The Catchments area is calculated by gathering local information and
topographical survey data as it was not possible to calculate from
topographical sheets due to their unavailability.
6.4
Time of Concentration
Sl.
1
2
3
4
5
7
8
9
12
13
14
15
16
17
18
19
20
21
Chainage (km)
0/775 KM 1ST
0/925
0/775
1/75 KM 2ND
1/400
1/600
2/00 KM 3ND
2/300
3/100 KM 4th
3/200
3/300
3/625-650
3/725
3/800
4/75 KM 5th
4/200
4/350
4/500
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
4/650
4/875
5/200 KM 6th
5/250-275
5/450-475
5/525
5/675
5/800
6/900 KM 7th
6/00-00/
6/450-475
6/525
6/675
6/800
6/900
7/00 KM 8th
7/250-275
7/450-475
7/525
7/675
7/800
8/200 KM 9th
8/450-475
8/525
8/675
8/800
8/900
9/100 KM 10th
9/525
9/675
9/800
9/800
10/100 KM 11th
10/525
10/675
11/100 KM 12th
11/525
11/675
12/100 KM 13th
12/525
12/675
KM 14th
13/525
13/675
13/525
13/625
KM 15th 14/675
14/525
14/625
KM 16th 15/675
15/525
Slab Culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Scupper
Scupper
Scupper
Scupper
Slab culvert
Scupper
Scupper
Scupper
Slab culvert
Slab culvert
2
3.00
1.00
2.00
1.00
1.00
3.00
1.00
2.00
1.00
2.00
2.00
2.00
1.00
1.00
3.00
2.00
2.00
1.00
2.00
1.00
2.00
2.00
2.00
10.00
1.00
1.00
1.00
2.00
1.00
1.00
2.00
1.00
1.00
2.00
1.00
3.00
3.00
3.00
3.00
1.00
3.00
3.00
3.00
1.00
2.00
-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
15/625
KM 17th
16/525
16/625
KM 18th
17/675
17/525
17/625
KM 19th
18/200
18/675
18/725
KM 20th
19/200
19/675
19/725
19/800
19/900
KM 21st
20/500
20/300
20/675
20/800
16/675
17/100
18/100
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
1.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
Slab culvert
1.00
3.00
3.00
3.00
3.00
3.00
2.00
3.00
1.00
2.00
-DO-DO-DO-DO-DO-DO-DO-DO-DO-DO-
19/300
20/400
7.
7.1
General
The geometric design standards for this project conform to PMGSY guidelines
and the guidelines as stated in IRC-SP 20:2002. Recommended design
standards vis--vis the standards followed for this road are described below.
7.2
Terrain
The classification of terrain was selected from hilly classification for which
following criteria will be applicable.
Terrain
classification
Mountainous
7.3
25-60%
1 in 4 to 1 in 1.67
Design Speed
The proposed design speed along this project road will be selected from the
following table:
Road
classificat
ion
Rural
Roads
(ODR and
VR)
7.4
Mountainous
terrain
Ruling
25
Min.
20
Road
classification
Rural roads
(ODR and VR)
7.5
Range
Norm
al
Range
12
12
12
Roadway Width
7.6
Carriageway Width :
3.75m.
7.7
7.8
Shoulders
It is proposed to have 1.20m wide shoulder as the case may be on both
sides .
Roadway width at cross-drainage structures 6.0mtrs.
The roadway width at culvert locations for this road is 6.0mtrs.
7.9
Sight Distance
The safe stopping sight distance is applicable in the geometric design. The
sight distance values for this road as per IRC recommendations are presented
below:
Design Speed
(km/hr)
20
30
40
50
7.10 Radius
Curve
of
Horizontal
7.12
Vertical Alignment
Camber (%)
Low rainfall
High rainfall
(Annual rainfall <1000mm)
(Annual rainfall >1000mm)
4.0
5.0
3.5
4.0
3.0
3.5
The present road is in mountainous terrain and vertical alignment has been
designed well within ruling gradient.
Generally, minimum gradient of 0.3% for drainage purpose is considered for
designing the vertical alignment of this road. Vertical curves are not required
when grade change is less than 1%, however a minimum vertical curve is
provided to avoid vertical kink.
7.13
Vertical Curves
For satisfactory appearance, the minimum length of vertical curve for
different design speed is given in IRC-SP 20:2002. Vertical curves will be
designed to provide the visibility at least corresponding to the safe stopping
sight distance. Valley curves will be designed for headlight sight distance.
7.14
Side slope
Side slope for this rural road where embankment height is less than 3.0m is
given in
Above
the
Radius of Curve (m)
Upto 20
21 - 60
60
table
Extra Widening for 5.50 m
below.
wide single lane
0.9
0.6
Nil
Condition
Slope (H:V)
carriageway, (m)
N.A
7.15
8.
Alignment Design
8.1
General
The basic aim of highway design is to identify technically sound,
environment-friendly and economically feasible highway alignment. The
ensuing sections deals with obligatory points, which control highway
alignment, design of cross-section, highway geometric design &
methodology, design of miscellaneous items.
8.2
Cross-sectional elements
Embankment
Horizontal alignment
Vertical profile
Junctions and/or Interchanges
Road furniture
Miscellaneous items
Horizontal alignment
Table 8.1 Features of Horizontal Alignment (Example)
Chainage
From
(km)
To
(km)
Leng
th
Description
(km)
21.00
0/000
Reason for
deviation from
existing
alignment, if
necessary
N.A
Checklist
a) Centre line of the existing and proposed horizontal alignment coincide
IP
Chaina
ge
Radiu
s
Ls
(m)
(m)
Spee
d
(Kmp
h)
Def Angle
Lc
Ltotal
(m)
(m)
S.E.
D
Hand
of
Curv
e
Chainag
e (m)
Sl.
N
O.
CurveSt. of
CurveEnd of
CurveSt. of
Level
Chainage
diferenceGrade
(%)Grade out
CurveEnd of
N.A
Grade in (%)
curveType of
curveLength of
8.3
Level of pvi
4
5
Vertical alignment
8.4
Design of Junctions
The proposed alignment intersects cross roads and forms junctions.
locations of junctions are given below:
The
Type of
intersection
Location
(km)
N.A
Exiting condition
Proposed
modification
9.
Pavement Design
9.1
General
9.2
Considering the subgrade strength , projected traffic and the design life, the
pavement design for low volume PMGSY roads was carried out as per
guidelines of IRC: SP: 72 2007, or IRC SP:77 Design of Gravel Road and
IRC SP:62-2004 Cement Concrete roads. In built up area for hygienic and
safety reasons
Pavement Design Approach
Indicative VDF values considered 10% of laden MCV and 10% laden HCV as
overloaded &
given below:
Vehicle
Un-laden /Partially
Laden
type
laden
HCV
2.86
0.31
MCV
0.34
0.02
Lane distribution factor (L) for Single lane road = 1.0 Cumulative ESAL
application = To x 4811 x L, where To = ESAL application per day. The
Cumulative ESAL application for the project road as per paragraph 3.5 of IRC:
SP: 72 2007 is presented below
9.2.4
Subgrade CBR
The subgrade CBR range of5%-9% was considered and the traffic falls in the
T-5 category.
9.4
Specify
design
alternati
ve
selected
marginal
materials.
Soil stabilization
and use of
locally available
Shoulder
widthEarthen full
To
Rigid
Fro
m
Flexible
Paveme
nt
Hard shoulder
0.875 m each
side
Chainage
Justification
Design Alternatives
Full widthHard
9.3
Pavement composition
Flexible Pavement
The designed pavement thickness and composition was calculated by
referring Figure 4 (Pavement design catalogue) of IRC: SP: 72 2007. The
ratio between heavy commercial vehicles and medium commercial vehicles
as given in Chapter 5 should be maintained as far as possible.
The pavement layers provided are given below:
Top Layer
20 mm
Bituminous
Macadam
Bituminous Layer
50mm
Base Layer
150+ 75 mm
Sub Base
Layer
300mm
10.
10.1
General
On the basis of hydrological survey, 158 No. new cross drainage structures
are recommended for the project road.
10.3
Design Feature
Design Standards for culverts has been prepared based on standard codes
and guidelines of IRC: SP: 20: 2002 and similar type of ongoing projects.
General features of the designed cross drainage structures are given below:
For hume pipe culvert, minimum road width has been taken as 6.00 m,
Width of culvert : 6.00m with parapet.
10.4
Sl. No.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.
0/25
0/425
0/575
0/750
0/850
0/950
1/100
1/200
1/700
2/100
2/200
2/300
2/400
2/500
2/800
2/900
3/100
3/200
3/225
3/500
3/800
3/900
3/975
4/125
4/200
4/300
4/400
4/500
4/600
4/700
4/800
4/900
5/100
5/200
5/300
5/400
5/500
5/600
5/700
5/800
5/900
6/100
6/200
6/275
6/300
6/400
6/700
6/800
6/900
7/250
Culvert
R.C.C
H.P.C
R.C.C
H.P.C
H.P.C
H.P.C
H.P.C
R.C.C
HPC
R.C.C
R.C.C
R.C.C
R.C.C
HPC
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
H.P.C
H.P.C
H.P.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
2.00
1.00
2.00
1.00
1.00
1.00
1.00
3.00
1.0
3.0
2.0
3.0
2.0
1.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
1.0
1.0
1.0
2.0
2.0
2.0
2.0
3.0
2.0
3.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
51.
52.
53.
54.
55.
56.
57.
58.
59.
60.
61.
62.
63.
64.
65.
66.
67.
68.
69.
70.
71.
72.
73.
74.
75.
76.
77.
78.
79.
80.
81.
82.
83.
84.
85.
86.
87.
88.
89.
90.
91.
92.
93.
94.
95.
96.
97.
98.
99.
100.
101.
7/350
7/500
7/600
7/700
7/800
7/900
8/100
8/150
8/300
8/400
8/500
8/600
8/700
8/800
8/900
8/950
9/100
9/200
9/300
9/400
9/500
9/675
9/800
9/850
9/975
10/100
10/200
10/300
10/400
10/700
10/800
10/900
11/100
11/200
11/225
11/600
11/800
12/75
12/150
12/175
12/300
12/500
12/525
12/800
12/900
13/00
13/50
13/200
13/500
13/700
13/800
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C
R.C.C Bridge
HPC
R.C.C
HPC
R.C.C
HPC
HPC
HPC
R.C.C
R.C.C
R.C.C
R.C.C
HPC
R.C.C
R.C.C
HPC
R.C.C
R.C.C
HPC
HPC
HPC
R.C.C
HPC
HPC
R.C.C
R.C.C
HPC
HPC
R.C.C
R.C.C
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
3.0
3.0
3.0
3.0
3.0
1.0
1.0
10.0
1.0
2.0
1.0
2.0
1.0
1.0
1.0
2.0
2.0
2.0
2.0
1.0
3.0
3.0
1.0
3.0
3.0
1.0
1.0
1.0
3.0
1.0
1.0
3.0
2.0
1.0
1.0
2.0
3.0
102.
103.
104.
105.
106.
107.
108.
109.
110.
111.
112.
113.
114.
115.
116.
117.
118.
119.
120.
121.
122.
123.
124.
125.
126.
127.
128.
129.
130.
131.
132.
133.
134.
135.
136.
137.
138.
139.
140.
141.
142.
143.
144.
145.
146.
147.
148.
149.
150.
151.
152.
14/25
14/300
14/500
14/800
15/50
15/150
15/200
15/300
15/400
15/500
15/600
15/700
15/800
15/900
16/100
16/200
16/400
16/500
16/800
16/900
17/00
17/100
17/200
17/300
17/375
17/400
17/500
17/600
17/700
17/775
17/800
17/900
17/975
18/100
18/200
18/300
18/500
18/600
18/800
18/700
18/900
18/975
19/100
19/200
19/500
19/575
19/825
19/900
19/950
20/100
20/250
HPC
R.C.C
R.C.C
HPC
HPC
HPC
HPC
HPC
HPC
HPC
HPC
HPC
HPC
HPC
R.C.C
R.C.C
R.C.C
HPC
HPC
HPC
HPC
R.C.C
R.C.C
R.C.C
HPC
R.C.C
R.C.C
R.C.C
HPC
HPC
HPC
HPC
HPC
HPC
R.C.C
R.C.C
HPC
R.C.C
HPC
R.C.C
HPC
R.C.C
R.C.C
HPC
R.C.C
HPC
HPC
R.C.C
HPC
R.C.C
HPC
1.0
2.0
3.0
1.0
1.0
1.0
1.0
1.0
1.0
1.0
1.0
1.0
1.0
1.0
2.0
2.0
2.0
1.0
1.0
1.0
1.0
3.0
3.0
3.0
1.0
3.0
3.0
3.0
1.0
1.0
1.0
1.0
1.0
1.0
3.0
3.0
1.0
3.0
1.0
3.0
1.0
3.0
3.0
1.0
3.0
1.0
1.0
3.0
1.0
3.0
1.0
153.
154.
155.
156.
157.
158.
159.
160.
20/350
20/425
20/500
20/575
20/825
20/900
20/925
20/975
HPC
R.C.C
R.C.C
HPC
HPC
R.C.C
R.C.C
R.C.C
1.0
3.0
3.0
1.0
1.0
3.0
3.0
3.0
General
Its a mountainous terrain, with quite a number of small non-perennial
nallahs crossing the alignment which requires CD structures.Rain water from
the road surface also needs to be drained out requiring CD structures.
11.2
11.3
Protective Works
Necessary protection works consisting of Kaccha pacca stone masonry
retaining walls and Breast walls are proposed where required as good quality
stones are available
Table 11.1 gives the chainage-wise protection works adopted.
Table 11.1 List of protective works
Sl.
No.
Chainage
Comments
LHS
RHS
0/700-0/1000
110 x (ht)
110 x (ht)
Breast wall
1/450-600
80 x 3(ht)
30 x (ht)
Breast wall
3/200-300
75 x 3(ht)
Breast wall
3/400-500
60 x 3(ht)
Breast wall
4/200-350
80 x 3(ht)
Breast wall
4/700-900
60x 3(ht)
Breast wall
5/100-150
30x 3(ht)
30x 2(ht)
Breast wall
5/350-500
80x3(ht)
40 x 2(ht)
Breast wall
5/700-800
60 x 3(ht)
60 x 2(ht)
Breast wall
10
7/600-630
30x3(ht)
30x 2(ht)
Breast wall
12
7/800-900
60 x 3(ht)
Breast wall
13
8/500-600
60 x 3(ht)
Breast wall
14
9/50-100
50 x 3(ht)
Breast wall
15
9/400-475
75 x 3(ht)
Breast wall
16
10/200-300
60 x 3(ht)
Breast wall
17
10/600-700
60 x 3(ht)
Breast wall
18
10/800-850
50 x 3(ht)
Breast wall
19
11/50-75
25 x 3(ht)
Breast wall
20
11/350-400
30 x 3(ht)
Breast wall
21
11/500-600
40 x 3(ht)
Breast wall
12.
Land Requirement
12.1
General
The existing roa
d is generally an earthen track. Thus the project road is a
new connectivity road. The existing Right of Way (ROW) is varying from 9.0 m
to 12.0 m.
12.2
Proposed ROW
The width of carriageway has been considered as 3.00 m in accordance with
the IRC-SP 20: 2002. The total roadway width is limited to 6.0 m with 1.20 m
earthen shoulder on either side of carriage way. The proposed ROW generally
varies from 12 m depending upon the embankment height and the proposed
ROW is even less than 9 m in some stretches of habitation area and in areas
having tree plantation.
12.3
Additional Land
N.A.
14.
14.1
Road Furniture
Road Furniture details include:
Road markings
Cautionary, mandatory and information signs
KM stones and 200m stones
Delineators and object markers
Guard posts, crash barriers and speed breakers
14.1.1Road Markings
Road markings perform the important function of guiding and controlling
traffic on a highway. The markings serve as psychological barriers and signify
the delineation of traffic paths and their lateral clearance from traffic hazards
for safe movement of traffic. Road markings are therefore essential to ensure
smooth and orderly flow of traffic and to promote road safety. The Code of
Practice for Road Markings, IRC: 35-1997 has been used in the study as the
design basis. Schedules of Road Markings are included in contract drawings.
14.1.2Cautionary, Mandatory and Informatory Signs
Cautionary, mandatory and informatory signs are provided depending on the
situation and function they perform in accordance with the IRC: 67-2001
guidelines for Road Signs.
Overhead signs are proposed in accordance with IRC: 67-2001.
14.1.3Kilometer Stone and Hectometer Stone
The details of kilometre stones are in accordance with IRC: 8-1980 guidelines.
Both ordinary and fifth kilometre stones are provided as per the schedule.
Kilometre stones are located on both the side of the road.
The details of 200m stones conform to IRC: 26-1967. 200m stones are
located on the same side of the road as the kilometre stones. The inscription
on the stones shall be the numerals 2,4,6 and 8 marked in an ascending
order in the direction of increasing kilometerage away from the starting
station. Table 14.1 gives the details of Km. stone.5 th km. stone and boundary
pillars provided.
Table 14.1
ST
Details of Km. stone.1
km. stone and boundary pillars
Sl.
Name of Road
Chainag
e (km)
Mendhar to Jaranwali
Gali
0-21
21. Km.
stone
(nos.)
1
Km.
stone
(nos.)
21
200m
stone
(nos.)
105
Boundar
y stone
(nos.)
840
14.2
14.3
j
k
l
m
n
o
p
q
r
Road safety issues identified during the design were and the mitigation
measures are included in all designs and shown on the DPR drawings. Details
of the issues and measures are:
15.
Specification
15.1
General
The Specification for Rural Roads published by IRC on behalf of the Ministry
of Rural Development, Govt. of India has been followed.
15.2
Construction Equipment
Construction by manual means and simple tools has been considered for the
project as per the guideline of NRRDA. For handling of bulk materials like
spreading of aggregates in sub-base & base courses by mix-in-place method,
use of motor grader & tractor-towed rotavator has been allowed in line with
the schedule of rate for PMGSY work. Compaction of all items shall be done
by ordinary smooth wheeled roller if the thickness of the compacted layer
does not exceed 100 mm. It is also considered that, hot mix plant of medium
type & capacity with separate dryer arrangement for aggregate shall be used
for bituminous surfacing work that can be easily shifted. A self-propelled or
towed bitumen pressure sprayer shall be used for spraying the materials in
narrow strips with a pressure hand sprayer. Now the vibratory rollers are
also being used for rapid progress.
For structural works, concrete shall be mixed in a mechanical mixer fitted
with water measuring device.
The excavation shall be done manually or mechanically using suitable
medium size excavators.
15.3
15.3.1
Construction Methods
Preparation for Earthwork
After setting out existing ground shall be scarified to a minimum depth of 150
mm and leveled manually and compacted with ordinary roller to receive the
first layer of earthwork. In filling area, existing embankment will be generally
widened on both sides as per the alignment plan. Continuous horizontal
bench, each at least 300 mm wide, shall be cut on the existing slopes for
bonding with the fresh embankment/ subgrade material as per Cl 301.7.
15.3.2
Embankment work
Material from borrow pits will be used for embankment construction as well
as the approved material deposited at site from roadway cutting and
excavation of drain & foundation may be used. Layer of the earth shall be laid
in not more than 25 cm (loose) thick layers & compacted each layer of the
soil up to 30 cm below the subgrade level at OMC to meet 97% of Standard
Proctor Density.
Material for embankment and sub-grade shall satisfy the requirements of
Table 300-1 and 300-2 as per the Specification for Rural Roads.
15.3.3
Sub-grade
Material from borrow pits will be used for construction of top 30 cm as subgrade. Soil in these sections is quite good for road construction. Top 30 cm
upto the subgrade level and shoulder at OMC to meet 100 % of Standard
Proctor Density by proper control of moisture and by required compaction
with a smooth wheeled roller.
15.3.4
Sub-base
Sub base material in the form of stone aggregates and sand as available in
the area to be used in GSB Grade II layer.
15.3.5
Base
Stone aggregates will be used in base course. 63 mm to 45 mm size (Grading
2) aggregate as been proposed for the bottom layer and 53 mm to 22.4 mm
(Grading 3) size has been proposed for the top layer.
15.3.6
Shoulder
Earthen shoulder shall be constructed in layers and compacted to 100% of
Proctors Density. First layer of shoulder shall be laid after the subbase layer
is laid. Thereafter earth layer shall be laid with base layer of pavement and
compacted.
15.3.7
Surfacing
Slow setting bitumen emulsion will be applied as primer on water bound
layer. Emulsion shall be sprayed on surface with pressure distributor. Rapid
setting bituminous emulsion shall be used for Tack coat.
Premixed carpet and mixed with equivalent viscosity grade bitumen shall be
laid as surfacing course. 6 mm thick Type B seal coat is considered for sealing
of the premixed carpet.
15.3.8
Structural Works
Following grades of concrete are proposed for Structural works and comply
with MORD and IRC specifications:
Concrete
Concrete
Concrete
Concrete
16.
16.1
Environmental Issues
Alignment
The proposed road has planned to be designed considering the impact on
environment. Proposed road alignment follows existing pathway to the
maximum extent so that huge land acquisition is not necessary for
construction of the project road. Proposed road, when completed, will be an
addition to the aesthetics of this rural area.
16.2
16.3
Construction Camp
Construction camps will be established away from forest area/water body. The
minimum facilities such as water supply, sanitation, storm water drainage,
solid waste management and first aid box will be provided during the
construction period of the project. Necessary provision for rehabilitation or
restoration after the completion of construction phase will be done.
16.4
Forest Department- If the project road passing thorough forest land and
acquisition of the same is involved and it will be taken by PIU from Forest
Department
16.5
Lease from Mines & Geology- This will be taken by the Contractor for new
Stone Quarry required for the project.
Borrow area
The filling soil will have to be procured from borrow pit. Borrow area will be so
excavated that the lands can reused as agricultural field. The depth of borrow
pit shall not exceed 450 mm (150 mm top soil included). The top soil shall be
stripped and stacked and shall be spread back on the land. As far as possible
the borrow pits shall not be dug close to the road embankment. The
Redevelopment of borrow area will be done before closure of the same and it
will be as per agreement between landowner and the Contractor.
16.6
Erosion Control
Turfing of the embankment slopes and earthen shoulder to prevent erosion of
slopes of the embankment, rain cuts and erosion of shoulder is being
suggested.
16.7
Drainage
Suitable cross drainage structures have been provided on the basis of
hydrological survey of the area. So, there will be no obstruction to the natural
drainage of the area. Road side drainage is also duly considered in a manner
so that surface water is led to the low points and is drained through the CD
structures.
16.8
Use of Material
Cut back bitumen is not proposed in the project to avoid contamination with
Kerosene. Bitumen emulsion is proposed for primer coat and tack coat.
17.
Analysis of Rates
17.1
General
Rates for various item of works of the project have been derived from the
Schedule of Rates 2012 for Road works, Culvert works & Carriage etc.
JKSRRDA and Addendum & Corrigendum to Schedule of Rates effective from
2012. However in general the basic rates of material have been taken from
SOR The rates of different items have been worked out inclusive of all labour
charges, hire charges of Tools & Plants, Machineries and all other cost
estimates for the item of work, overhead and contractors profit @ 12.5% and
1% cess on these.
17.2
17.3
from the district map and block level map of core network and finalizing the
same in discussion with PIU. The supply of different materials to worksite is
by road. Lead for bituminous & steel materials are similarly obtained using
SOR.
18.
Cost Estimate
18.1
General
Cost Estimate of project has been arrived on the following basis
18.2
18.3
Abstract of Cost
Unit rates will be derived by using the Schedule of Rates for Road Works,
Culvert works and Carriage etc. JKSRRDA. The abstract of Cost estimate is
given in the Table below.
18.4
Maintenance
Cost of Annual Maintenance for five years after completion of project will be
estimated as per the PMGSY Guidelines. Different activities of ordinary repairs
are done as and when.
19.
Construction Program
19.1
General
Assuming that the Construction of the Batch Dhargloon to Basooni road start
from MENDHAR This is a high rainfall area and rainy season extends from
April to September. However, the construction program is based for a total
working period of 12 months, considering the program set out by MoRD.
Generally, dry working season of about 8 months are required for
construction of PMGSY roads. However, works will be affected for the
monsoon during the month June to September.
It is anticipated that some activity like collection of materials, CD works if
required will continue in monsoon period also.
19.2
Realistic duration
Yes
For PIC
No
N/a