Professional Documents
Culture Documents
Page
01
1. Scope
2. Introduction
01
3. Specification
01
01
5. Methodology
02
02
02
05
6. Machinery Involvement
05
05
8. Appendix
Annex-1:Internal Inspection Sheet of Formwork
06
Annex-2:
07
1. SCOPE
This Section describes the details and method of formwork erection for structural concrete
work in accordance with the construction drawing.
2. INTRODUCTION
Formwork shall include all temporary or permanent forms or moulds required for casting the
concrete. It provides all the temporary support for the required construction.
3. SPECIFICATION
ICTAD specification and BOQ recommendation.
4. FLOW CHART FOR FORMWORK
Internal inspection
Rectify Work
Engineers Inspection one day before
finishing the Formwork
Not OK
5. METHODOLOGY
5.1. Material for Formwork
The following material shall be used for formwork
Panel
Timber
Steel pipe
: 48
Support
Other accessories
Film coated plywood sheets are used as formwork materials (to receive smooth
concrete surfaces).
The surfaces of formwork that would come in contact with concrete shall be
thoroughly wetted and coated with mould oil of approved make.
The inside surfaces of the F/W panels are thoroughly cleaned before application of
any of loosens materials.
Re-use of F/W panels shall be used only after the surface has been thoroughly cleaned
and repaired if necessary.
5.2. Propping and Centering
Formwork panels are prepared to fit for the internal dimensions of the column.
Off lines are marked on the floor to check the horizontal alignment of the column.
U- Heads are placed in the slab concreting to support the jacks. Jacks resist lateral
forces due to dumping of concrete, moment of construction equipment and wind of
action
U-Head
Slab
Fig.01. U-Head in slab
Bottom of the F/W panel are locked with the help of wooden support which is nailed
to the concrete.
Acro-jacks are used to support the columns in vertical. There are two numbers of
jacks in 600mm span. Turn buckles are used to maintain the accuracy of the vertical
alignment.
GI pipes, threaded bars and form ties are used to lock the formwork. There are four
numbers of locking positions in 8 height.
Vertical alignment of the column F/W is checked by plumb. The vertical alignment is
checked before and just after the concreting.
Before concreting is started all the jacks and ties shall be checked to see that they are
intact and suitable action taken in case they are loose. Just after concreting also should
do same thing with both vertical and horizontal alignment checking.
While the concreting is in progress, at least one carpenter/ fitter shall be readily (have
necessary tools in hand) available at site. Numbers of carpenters / fitters depend on the
number of columns going to be concreted. The carpenter shall keep a constant watch on
jacks, ties and take immediate remedial measures if any of these get loosened.
5.3.
Removal of F/W
The F/W shall be so removed not to cause any damage to concrete surfaces due to
shocks or vibration.
The removed F/W panels shall be oiled with form oil and store carefully to use again
easily.
6. Manpower involvement
.
Civil Engineer
Technical Officer
Supervisor
Carpenter
Helper
4
Annex- 1:
Annex-2:
Marking.
Level of bottom & top form.
Alignment and verticality of formwork
Spacing of support, Conditions of supports.
Sectional Dimension.
Required embedded material.
Gaps between formwork.
Cleaning of formwork.
Mistuning of formwork.
Provisions for services or other accessories.
Tightening of support and bracing.
Cleaning and tidiness of slab formwork.