IPMS 2000

START-UP
SCHEDULE

General Activities
Pre Start-Up Activities:
GE1000: Contract Award
GE1007: Review Lessons Learned
GE1008: Initial Start-Up Meeting
GE1010: Establish Labor System
GE1015: Acquire Financial & Accounting Number
GE1020: Establish Physical Facilities (Office, Tel, Etc.)
GE1025: Review Staff Req. & Assign Initial Personnel
GE1030: Identify Project Contractual Requirements
GE1035: Project Team Review IPMS Package Relationship
GE1040: Identify Personnel & Computer Requirements
GE1050: Identify Project Personnel/IPMS Access & Roles
GE1055: Define & Approve WBS, OBS, CBS Strategy
GE1110: Establish WBS/CBS

Start-Up Activities:
GE1005: Arrange/Conduct Project Kick-Off Meeting
GE1045 Define Project Execution Strategy
GE1065: Provide Functional & Systems Software Training
GE1070: Project Team Review Global Default Codes
GE1075: Project Team Approve WBS, OBS & CBS
GE1078: Shared Data Overview Meeting
GE1080: Discuss Process Systems & Services
GE1090: Identify & Input WBS/CBS Codes in IPMS

Planning Activities:
GE1060: Establish/Update Project Implementation/Execution Plan
GE1120: Review WPIDs, Quality Plan, Project Start-Up
GE1125: Develop Project Quality Plan
GE1130: Prepare Project Procedures
GE9999: IPMS Start-Up Complete

IPMS GENERAL START-UP ACTIVITIES


ACTIVITY ID
GE1000

DESCRIPTION

Contract Award
The responsibility to identify contract award and initiate set up of IPMS rests with
Project Management. The IPMS instance will be set up by the start-up team. The
instance will be loaded with a copy of all the Corporate data, as defined and
agreed upon by the project during Start-Up activity review.
Project Code (4 characters) and Sub-Project Code (4 characters) are required. This
combination must be unique. At least one sub-project is required. The Project
Code is generally descriptive (client, project name). Project Code and Sub-Project
Codes are set up in PMRR1212.

GE1005

Arrange/Conduct Project Kick-Off Meeting


The use of IPMS is defined in the Project Kick-Off Meeting.

GE1007

Review Lessons Learned


Lessons learned are reviewed to educate project staff so that known pitfalls may
be avoided.

GE1008

Initial Start-Up Meeting


All global support and project staff using IPMS attends the initial start-up
meeting. This begins the IPMS start-up process.

GE1010

Establish Labor System


The project must decide which labor system to use. The Business Unit typically
defines the labor system. The cost module must be set up specifically for the
chosen labor system.

GE1015

Acquire Financial & Accounting Number


The financial and accounting number is set up in IPMS for the procurement
module and accounting interface.

GE1020

Establish Physical Facilities (Office, Tel, Etc.)


This is a project responsibility.

GE1025

Review Staff Req. & Assign Initial Personnel


This is a project responsibility to define for the start-up.

GE1030

Identify Project Contractual Requirements


The project and start-up team is to identify all contractual requirements that relate
to all IPMS functions and ensure that IPMS setup for all modules complies with
the contract. This is done to assure that contract requirements are addressed
during set-up.

IPMS GENERAL START-UP ACTIVITIES


ACTIVITY ID
GE1035

DESCRIPTION

Project Team Review IPMS Package Relationship


Engineering progress measurement is defined by Workpackages in IPMS.
Standard Workpackages are loaded from Corporate. Workpackages are loaded
into Tracking. The Project Team requires training to develop understanding of the
Workpackage concept and options.

GE1040

Identify Personnel & Computer Requirements


The project must identify all personnel and their hardware requirements. The
project should coordinate with IT to ensure that these needs are met.

GE1045

Define Project Execution Strategy


The Global IPMS team will define the next steps to execute IPMS Start-Up.
Responsibilities for all other activities in the start-up schedule will be defined.

GE1050

Identify Project Personnel/IPMS Access & Roles


The project must identify all IPMS users and their roles. The IPMS System
Administrators will set up the users in the project database.

GE1055

Define & Approve WBS and CBS Strategy


Project must define and approve the WBS and CBS. The WBS/CBS is used by all
modules in IPMS.

GE1060

Establish/Update Project Implementation/Execution Plan


The project is to establish a Project Implementation/Execution Plan. The project
and start-up team should review the plan to ensure that IPMS setup for all
modules complies with the plan.

GE1065

Provide Functional & Systems Software Training


Project to identify needs and Global IPMS team will train project staff.

GE1070

Project Team Review Global Default Codes


The Global IPMS team will review all standard codes.

GE1075

Project Team Approve WBS, OBS & CBS


Full project team approval of the coding structures of the Work Breakdown
Structure (WBS), Organizational Breakdown Structure (OBS) & the Cost
Breakdown Structure (CBS) as available in IPMS.

IPMS GENERAL START-UP ACTIVITIES


ACTIVITY ID
GE1078

DESCRIPTION

Shared Data Overview Meeting


This is a presentation given by Mike Chidalek to the project to explain how
modules interact.

GE1080

Discuss Process Systems & Services


This is a set-up activity by MRP to put data in a table that provides a list of values
(LOV) for Systems and Services used on the project.

GE1090

Identify & Input WBS/CBS Codes in IPMS


WBS definitions are entered in PMRR1214 and used by all modules. The CBS is
used by the cost module.

GE1110

Establish WBS/CBS
It is the Project Team responsibility to define WBS & CBS.

GE1120

Review WPIDs for Project Start-Up


Project to review standards and ensure that IPMS Start-Up complies with WPIDs
for Project Start-Up.

GE1125

Develop Project Quality Plan


It is the Project Team responsibility to define Project Quality Plan.

GE1130

Prepare Project Procedures


Project to develop all Project Procedures including Procurement & Materials
Management procedures, Procurement procedures and Document procedures will
all be produced for the project and will incorporate agreed IPMS work processes.

GE9999

IPMS Start-Up Complete

Information Technology
Pre Start-Up Activities:
IT1000: Establish Instance on Appropriate Server
IT1005: Analyze/Consolidate Hardware/Software
IT1010: Requisition Equipment/Software (TCP/PC210 Etc)
IT1025: Install, Load and Set up Local Equipment
IT9999: IT Complete with IPMS Set-Up

IPMS Startup Schedule Activity Descriptions

05/09/00

IPMS INFORMATION TECHNOLOGY START-UP ACTIVITIES


ACTIVITY ID
IT1000

DESCRIPTION

Establish Instance on Appropriate Server


Set up the IPMS project and copy standard database to project.

IT1005

Analyze/Consolidate Hardware/Software
This is a Project/IT function intended to get the project to determine who needs
hardware and access to IPMS.

IT1010

Requisition Equipment/Software (TCP/PC210 Etc)


This includes acquiring all equipment/software (data lines) necessary to run IPMS
from the project location.

IT1025

Install, Load and Set up Local Equipment


Set up IPMS and AppWorx access on local machines for project staff.

IT9999

IT Complete with IPMS Set-Up

IPMS Startup Schedule Activity Descriptions

05/09/00

Reference
Start-Up Activities:
RE1000: Request IPMS Project/Sub-Project Number from Corporate
RE1010: Review Security Roles
RE1015: Review Discipline Codes
RE1020: Review Project Position Codes
RE1035: Obtain/Populate Financial Related Info (CO/AC/RC)
RE1040: Populate Number & Related Data in Instance
RE1045: Populate Sub-Project & Related Data in Instance
RE1065: Populate Security
RE1070: Populate Project Organization
RE1075: Define Project Process Systems from LOV
RE1080: Link Project Organization to Disciplines/Personnel
RE1085: Extract Project Suppliers from Corporate List
RE1090: Attach Suppliers List to Project
PMRR1215: Review Global & Default Reference Codes
PMRR1410B: Review Standard Narratives & Narrative Models
PMRR1238A: Populate Personnel in Personnel Table
PMRR1240B: Populate Addresses in IPMS
PMRR1240C: Populate Sub-Project Addresses
RE9999: IPMS Reference Tables Set-Up Complete

IPMS Startup Schedule Activity Descriptions

05/09/00

IPMS REFERENCE START UP ACTIVITIES


ACTIVITY ID
RE1000

DESCRIPTION

Request IPMS Project / Sub-Project Number from Corporate


Upon receiving the IPMS Instance Request, the Project Code (4 Characters) and
the Sub-Project Code (4 Characters) will be populated in IPMS. The Project
Codes is project descriptive and the Sub-Project Code is generally numeric.

RE1010

Review Security Roles


Project activity to review roles available and acknowledge whether or not a
project has needs for special roles which do not exist (special client access, etc.).

RE1015

Review Discipline Codes


Discipline codes are populated in PMRR1230 and is required by all IPMS
modules.

RE1020

Review Project Position Codes


Review the project positions defined for individuals receiving transmittals on the
project. In the transmittal process of Document Management, documents may be
transmitted either to individuals or to project positions.

RE1025

Define Legacy Financial No & Related Data (CO/AC/RC/Job No/BT)


The legacy financial number drives much of the processing in Cost. All financial
information (company, accounting center, responsibility center, job number, and
billing type) must be defined. On the set-up screen, there is the ability to choose
which (CO/AC/RC/Job No/BT) is defaulted to each Award Sub Line Item. Cost
uses this for the commitment process.

RE1035

Obtain/Populate Number & Related Data in Instance


This step is to populate the legacy financial number and the related data Award
sub line item default, different billing types valid on the project, etc.

RE1040

Populate Project Number to Project in IPMS Instance


This step is to populate the approved Project Number in IPMS.

RE1045

Populate Sub-Project & Related Data in Instance


The Project Contract requirement may be addressed by having the option to
choose to have separate sub-projects. Each Sub-Project is managed separately.
This option must be fully understood by the project management before being
deployed. Normal practice is to set the project up as a single sub-project.

IPMS Startup Schedule Activity Descriptions

05/09/00

IPMS REFERENCE START UP ACTIVITIES


ACTIVITY ID
RE1050

DESCRIPTION

Populate Project Addresses - PMRR1240


The project address code must be populated. The address code is used to set the
sub project addresses.

RE1065

Populate Security
Define user roles for tables, forms and views. Users can be connected to a single
or multiple roles in the security table.

RE1070

Populate Project Organization - PMRR1230


The Organization Code for the project must be populated, then linked with the
Discipline Code. Organization Discipline is required when registering any type of
documents to identify the owner and originator of the document.

RE1075

Define Project Process Systems for LOV


This is a set-up activity by MRP to put data in a table that provides an LOV for
Systems used on the project.

RE1080

Link Project Organization to Disciplines/Persons


Link Disciplines to the Organization codes and to Personnel.

RE1085

Extract Suppliers from Corporate List to Populate IPMS


This is a set up activity by the start-up team.

RE1090

Attach Suppliers list to Project


This is a set-up activity by Procurement after the project determines which
Suppliers to populate in IPMS.

PMRR1215

Review Global & Default Reference Codes


This includes a review of all codes for completeness and accuracy.

PMRR1238A Populate Project Personnel


The project personnel name and their Network Access # must be registered and a
title or position must be identified. This is only required for any personnel that
will receive documents.
PMRR1240B Populate Addresses in IPMS
This is required for any physical locations that will submit or receive documents
or materials: the project office(s), the jobsite, client office(s), suppliers, vendors,
fabricators, etc.

IPMS Startup Schedule Activity Descriptions

10

05/09/00

IPMS REFERENCE START UP ACTIVITIES


ACTIVITY ID

DESCRIPTION

PMRR1240C: Populate Sub-Project Addresses


No action is required if a single sub-project is used.
PMRR1410B Review Standard Narratives & Narrative Models
Procurement and Engineering responsibility to review the standard narratives.
Ensure the Document Type field is populated. Tape Clauses can be defined as
needed for project for RFQs or Purchase Awards.
RE9999

IPMS Reference Tables Set-Up Complete

IPMS Startup Schedule Activity Descriptions

11

05/09/00

MATERIAL REQUIREMENTS PLANNING


Pre Start-Up Activities:
PMRR1238: Identify MRP Personnel Codes & Roles
MC1070: Identify RFQW/RFQ/PO Numbering Scheme

Start-Up Activities:
MC1005: Identify Coding Structure for Project Tag No EDMS/IPMS
MC1010: Identify & Populate MTO Levels for Project Use
MC1030: Audit/Review Application Utilization
MC1033: Identify Document Numbering Scheme for Engineering MTO Interface
MC1040: Set-Up Bulk Tag Alert Message
MC1050: Identify Spec Automation Responsibilities
MC1075: Confirm Database Link for EDMS/IPMS
MC1085: Review Completeness of IPMS Project Instance
MC1090: Identify & Execute Design & Supplier Interfaces for IPMS
MC1125: Identify MTO Process (System/Manual)
PMDD1140: Populate Tags (Manually)
PMRR1213: Set MTO Sum Start Position & Length
PMRR1240: Define Address Rules & Populate Addresses
MC9999: MRP IPMS Start-Up Complete
Before the database administration group makes a copy of the corporate database, it is requested
that those individuals maintaining the corporate database be notified. This will insure that any
unfinished work that may be active can be committed, and the complete activities will be
reflected in the new instance
MRP has a table identified as BLD_ITEM that has a column name including proj_no. This
particular table must not be updated to the new project number and remain 0000. The script
written to change proj-no has been written as such.

IPMS Startup Schedule Activity Descriptions

12

05/09/00

IPMS MATERIAL START-UP ACTIVITIES


ACTIVITY ID
MC1005

DESCRIPTION

Identify Coding Structure for Project Tag Nos. for EDMS/IPMS Validation
Define the coding structure for the Project tag number and confirm that data
transfer through EDMS/IPMS Interface satisfies conditions of tag numbers. (WBS
code in correct format, Org-Disc. etc.)

MC1010

Identify & Populate MTO Levels for Project use


Identify and populate the various levels in which the project requirements will be
maintained in material takeoff and material summary. Including valve,
preliminary, intermediate and final material take-offs (MTO).

MC1030

Audit/Review Application Utilization


Ongoing audit/review of how personnel have utilized the MRP application.

MC1033

Identify Document Numbering Scheme for Engineering MTO Interface


The project will determine the document numbering scheme. This is necessary to
begin down loading data into IPMS.

MC1040

Set-Up Bulk Tag Alert Message


The Bulk Tag Alert feature notifies the project MRP via e-mail that MERLIN has
duplicated project valves in the catalog and piping material class.

MC1050

Identify Specification Automation Utilization


Define or confirm who will perform spec automation (MERLIN OR MRP)

MC1070

Identify RFQW/RFQ/REQN/P.O. Numbering System Strategy


Define the numbering scheme for the documents such as RFQW and Requisition.
BUSINESS UNIT has a Standard numbering scheme for Requisitions and POs.

IPMS Startup Schedule Activity Descriptions

13

05/09/00

IPMS MATERIAL START-UP ACTIVITIES


ACTIVITY ID
MC1075

DESCRIPTION

Confirm Database Link for EDMS/IPMS


Contact Database Administrator to confirm that the interface capability is created
for project implementation.

MC1085

Review Completeness of IPMS Project Instance


MRP responsibility to review MRP maintenance tables for assurance that
Corporate Default Codes are loaded properly.

MC1090

Identify & Execute Design & Supplier Interfaces for IPMS


Define the files that will be utilized for the IPMS interface. These files can be:
Tagged Items; Line Lists; MERLIN (spec. auto) and CAD.

MC1125

Identify MTO Process (System/Manual)


Define the roles for the MTO process. Definition needed if MTO's will be
populated manually by MRP or by electronic transfer?

PMDD1140

Populate Tags (Manually)


Identify whether the tagged items are to be loaded into the system manually.

PMRR1213

Set MTO Sum Start Position & Length


The value used in these fields determines the level of detail that Cost uses to
report project requirements by WBS.

PMRR1238

Identify MRP Personnel Codes & Roles


Confirm assignment of ID. & Corp Code for MRP personnel and identify all roles
that MRP personnel may require for Project (Ex. BBRH065 = H065)

PMRR1240

Define Address Rules and Populate Addresses PMRR1240


Define the association of a material reference number to a specific address to
facilitate the identification during the MTO Process or RFQW/REQN (ex.
destination; origin or admin. address) and populate addresses.

MC9999

MRP IPMS Start-up COMPLETE


Application is ready for the Material Control personnel to begin project activities

IPMS Startup Schedule Activity Descriptions

14

05/09/00

PROCUREMENT
Start-Up Activities:
PO0100: Identify Procurement / Purchasing Responsibilities
PO0220: Identify Procurement WP Numbering Scheme
PO0300: Review Global / Project Variable Reference Codes
PO0700: Develop Project Procurement Plan / Project Procedures
PO0705: Identify Procurement Distribution Requirements
PO0710: Identify Project Suppliers Requirements List
PO0712: Develop Client / Project Approved Suppliers List
PO0725: Identify Procurement Reporting Requirements & Data Dates
PO0730: Identify Procurement Chains with Durations
PMMP1100: Assign Commodity Types/Assign to Material Reference Number
PMRR1232: Review Suppliers by Commodities
PMRR1240A: Identify Procurement Address
PMRR1410: Review, Modify Standard Narratives
PMRR1410A: Modify & Populate Standard Narratives
PO1000: Procurement Set-Up Complete Issue First P.O.
Note: Make sure that the default corporate coding structure to be used for P.O.'s is set on form
PMRR1215. This is part of the IPMS Administration instructions.

IPMS Startup Schedule Activity Descriptions

15

05/09/00

IPMS PROCUREMENT START-UP ACTIVITIES


ACTIVITY ID
PO0100

DESCRIPTION

Identify Procurement Purchasing Responsibilities


Determine from the project what is to be bought and by whom (Client, 3rd Party,
or Business Unit). In addition, determine what commodities the Business Unit
will buy and where (home office or field). [Non-IPMS activity - part of project
start-up process!]

PO0220

Identify Procurement Work Package Numbering Schemes


Establish the work package numbering schemes to be used on the project
following corporate & Business Unit recommendations whenever possible. The
work package number is intended to be the same as the requisition and PO
number.

PO0300

Review Global Reference Codes PMRR1132/7019


Familiarize project personnel with these codes and determine if there are any that
need to be adjusted for the particular project.

PO0700

Develop Project Procurement Plan / Procedures


This is a standard project implementation task that establishes the ground rules for
how the Procurement effort will be executed on the project.

PO0705

Identify Project Distribution Requirements


Determine what the distribution requirements are for Procurement documents and
reports and provide these to Documentation for input into the project distribution
matrix. [No IPMS forms associated with this activity]

PO0710

Identify Project Suppliers Requirements List


Procurement needs to define and review the project supplier list. Upload of
Business Unit standard can be done and then adjusted for project needs.

PO0712

Develop Client / Project Approved Bidders List PMMP3322


Prepare lists of all bidders for each commodity from the supplier table. Develop
lists of client/project approved bidders for each commodity from these lists.

PO0725

Identify Procurement Reporting Requirements & Data Dates


The data dates are defined by the project and input by Tracking. The project is to
determine which Procurement reports are required regularly by the project and
what the issue frequency is. Provide this information to Document Management.

PO0730

Identify Procurement Chains with Durations


Each Business Unit has defined procurement chains for the projects to use. The
project procurement group can define the activity durations.

IPMS Startup Schedule Activity Descriptions

16

05/09/00

IPMS PROCUREMENT START-UP ACTIVITIES


ACTIVITY ID

DESCRIPTION

PMMP1100 Assign Commodity Types/Assign to Material Reference Number


Project and procurement to define commodity types for supplier selection.
Product Commodity Code (PCA) assignment can be selected from the glossary.
The project can review RFQ suppliers linked to the PCC product code.
PMRR1232: Review Suppliers by Commodities
Only the project list is transferred to IPMS. This is intended to be a one time
transfer. Additional suppliers identified later will be manually loaded.
PMRR1240A Identify Procurement Address PMRR1240/1241
Determine whether purchases are to be agency 3rd party, etc. and create addresses
with the proper purchasing entity title and liability code.
PMRR1410

Review & Modify Project Standard Narrative Models


Review the corporate standard narratives and modify as needed to make them
project specific. Determine which clauses will be used regularly for which
documents and establish narrative models to group them.

PMRR1410A Modify & Populate Project Standard Narrative Models


Modify and input the models and assign the clauses. Edit all clauses coded with
an ~. to fill in the blanks with project information. Create and input as many
additions/ standard clauses as desired for the particular project.
PO1000

Procurement Setup Complete

IPMS Startup Schedule Activity Descriptions

17

05/09/00

DOCUMENT MANAGEMENT
Pre Start-Up Activities:
DM1025: Review and Update Global and Default Codes

Start-Up Activities:
DM1000: Establish Document Management Execution/Responsibility Plan
DM1005: Identify Project Reporting Requirements
DM1010: Identify Job Book/Handover Requirements
DM1015: Review Project SDRL Requirements
DM1020: Identify Project Transmittal Recipients
DM1030: Identify Bar Coding Requirements and Schedule Interface
DM1040: Populate Transmittal Cover Letter
DM1045: Set up Bar Coding
DM1050: Identify Document Numbering Scheme
DM1055: Identify Construction Document Revision Requirements
DM1090: Review DM Access and Roles
DM1095: Populate Hand-Over Work Package Subtype
DM2000: Establish Document Management Project Staff Training
PMDC1102: Populate Document Revision
PMDC1103: Populate Transmittal Distribution Matrix
PMDC1104: Review Recipients Addresses
PMDC1701: Produce tray labels
PMDC170304: Review and Update Global & Default Codes
PMTR1640: Establish Transmittal/Doc Mapping Associations
PMTR1660: Review Document Default Chains
PMTR1660A: Review Transmittal Default Chains
DM2050: Document Management Set-Up Complete (Issue Data)

IPMS Startup Schedule Activity Descriptions

18

05/09/00

IPMS DOCUMENT MANAGEMENT START-UP ACTIVITIES


ACTIVITY ID
DM1000

DESCRIPTION

Establish Doc Management Execution/Responsibility Plan


The project is responsible to developing the Doc Management Responsibility
Plan.

DM1005

Identify Project Reporting Requirements


The start-up team will review the standard reports in IPMS with the project
document personnel.

DM1010

Identify Job Book / Handover Requirements


The project may or may not have the information for job books in the beginning
of the project, however, the project should follow up to ensure this information is
available as soon as possible.

DM1015

Review Project SDRL Requirements


The default SDRL Code details must be reviewed and updated based on the
project requirements. Each SDRL Code must be set up with review cycles
required, duration of each review cycles, the required copies and media. The
duration of the approval code must also be updated by review cycles of the
document.

DM1020

Identify Project Transmittal Recipients


The project is to identify the project personnel and their positions so they can be
attached in IPMS to transmittals. The start-up team will assist the project
counterpart in loading this information.

DM1025

Review/Update Other Default Document Management Reference Tables


Other Document Management default reference tables must be reviewed and
updated as necessary such as:

DM1030

Transmittal Cover Letter


Document Approval Status
Project Alpha File
Project Subject File
SDRL Review Codes
Qualification Reason
Review Action Type

Identify Bar Coding Requirements


The bar coding requirements will be defined in the start up meetings.

IPMS Startup Schedule Activity Descriptions

19

05/09/00

IPMS DOCUMENT MANAGEMENT START-UP ACTIVITIES


ACTIVITY ID
DM1040

DESCRIPTION

Populate Transmittal Cover Letter


The project will define the cover letters to be used for a specific project.

DM1045

Set up Bar-coding
If the project will use the bar-coding functions, then the bar-code hardware must
be installed to the PC system that will be used to do the bar-coding facility. The
network must be set up to facilitate the bar-coding.

DM1050

Identify Document Numbering Scheme


The document numbering scheme for any types of document, Engineering,
Supplier, and General must be identified by the project. Once the document has
been attached to other applications such as Tracking, e.g. Chain, WP, etc. the
document number can not be changed, or deleted.

DM1055

Identify Document Revision


The document revision scheme for engineering, supplier, and general documents
must be identified by the project. Once the document revision numbers are used
by any documents, the revision number can not be changed.

DM1090

Review DM Access and Roles


The project/start up counterpart will determine the access and roles needed for
document management.

DM2000

Establish Doc Management Project Staff Training


The training will be done by the IPMS start-up team as the project requires.

PMDC1102

Populate Document Revision (Engineering/Supplier/General) - PMDC1102


The document revisions for engineering, supplier and general documents must be
populated for both the Business Unit and Client if necessary.

PMDC1103

Populate Transmittal Matrices


The distribution matrix must be populated before creating any types of
Transmittals. The grouping of the matrix must be thought out before starting to
create matrices for all the purposes of transmittals. The grouping e.g. document
types, sub types, organization discipline and etc. The matrix recipients details
such as review actions, required copies and media must be specified. The
distribution matrix is used by the transmittal.

IPMS Startup Schedule Activity Descriptions

20

05/09/00

IPMS DOCUMENT MANAGEMENT START-UP ACTIVITIES


ACTIVITY ID
PMDC1104

DESCRIPTION

Review/Update Recipients Addresses - PMRR1238


The personnel address must be reviewed and updated. The address is used when
sending or mailing documents to the recipients.

PMDC1701

Produce Tray Labels


The document recipients bar-code tray labels must be created before using the barcoding functions.

PMDC170304Review & Update Global & Default codes


The document recipients bar-code tray labels must be created before using the barcoding functions.
PMTR1640

Establish Transmittal/Doc Mapping Associations


The default transmittal mapping association must be reviewed and updated for the
project with the scheduler and document management.

PMTR1660

Review/Update Document Default Chains - PMTR1660


The default document (item) chains must be reviewed and updated for the project
with the scheduler on the project. Default chains that will not be use by the project
should be VOIDED.

PMTR1660A Review Transmittal Default Chains


The default transmittal mapping association must be reviewed and updated for the
project with the scheduler. The transmittal mapping will populate the document
milestone dates, using the transmittal issue date and transmittal actual completion
dates.
DM2050

Document Management Set-Up Complete Issue Data

IPMS Startup Schedule Activity Descriptions

21

05/09/00

TRACKING
Pre Start-Up Activities:
PMTRXXXA: Review Corporate Tables From Glossary
PMTRXXXB: Review Default Tables in Project Instance

Start-Up Activities:
PMRR1132X: Define & Set-Up Project Calendars
PMTR1085: IPMS Work Package Training with Project Team
PMTR1095: Identify Work Package Numbering Scheme
PMTR1100: Identify Work Package Progress Options
PMTR1105: Engineers/Construction to Identify Work Packages
PMTR1115: Identify Work Package Type and Sub-Types
PMTR1120A: Populate Work Package Type & Sub-Types
PMTR1410A: Identify & Update Work Package Milestones and Chains
PMTR1524A: Review CPM definition tables
PMTR1604B: Review mapping
PMTR1630A: Define & Populate Project Data Dates
PMTR1640A: Review Transmittal Associations with Docs
PMTR1660B: Review default chains {Items)
PMTR9999: Tracking Start Up complete

Tracking needs sub-directories created in the temp directory for each project's subproject. E.g.: if
GPAC was a new project, we would need two sub-directories under the temp directory, one
would be 1990 and the other would be 0638. This is necessary to allow one project that has
multiple projects to run the Tracking Freeze. If we only have one subproject, then the directory
still must be created. Also if we add a new subproject to an existing project, a new sub-directory
must be created for the subproject.
This action item is one of the bullet items listed in the IPMS Database Administration section.

IPMS Startup Schedule Activity Descriptions

22

05/09/00

IPMS TRACKING START-UP ACTIVITIES


ACTIVITY ID

DESCRIPTION

PMRR1132X Define / Setup Project Calendar


The project is to define the project calendars and dates. The Tracking startup
person will populate in IPMS. Dates must be input to define working days and
times. Calendars need to be set up for engineering, procurement and construction.
PMTR1085

IPMS Work Package Training with the Project Team


The work package training is a presentation done by the Tracking startup team. It
is scheduled by the project just prior to beginning work package development.
Attendees should include the project management, all engineering discipline leads
and project controls.

PMTR1095

Identify Work Package Numbering Scheme


The project will create a work package numbering scheme. This should consist of
a common coding structure that has been defined by the Business Unit. The
maximum length of this number is 13 digits.

PMTR1100

Identify Work Package Progress Options


Each work package must have a progress option selected. The options are P, C, I
and U. This determines how progress is earned. This engineer will determine
which type of progress is to be used when the work packages is defined. Project
controls may assist with this assignment.

PMTR1105

Engineers/Construction to Identify Work Packages


The work group lead engineer will define the work packages for his/her discipline.
The construction work packages may be input from the estimate by the project
scheduler.

PMTR1115

Identify Work Package Type and Subtype


The work package type and subtype table should be reviewed. The Business Unit
has established standards for each discipline. A project has the option to add
project specific codes as needed. A start up person will need to add any project
coding. This must be coordinated with document management to maintain
alignment between items and work packages.

PMTR1120A Populate Work Package Type & Subtypes


The Business Unit standards will be loaded into IPMS once the instance is
established.

IPMS Startup Schedule Activity Descriptions

23

05/09/00

IPMS TRACKING START-UP ACTIVITIES


ACTIVITY ID

DESCRIPTION

PMTR1410A Identify & Update Work Package Milestones & Chains


The Business Unit has established standard chains for each discipline. The
project should review the chains and milestone. The project may make
adjustments for project specific scope and requirements. Adjustment may require
process owner approval. Process owner review is required for all changes to the
chains.
PMTR1524A Review CPM Definition Tables
The Business Unit standard chains contain the CPM definition. The project
should review the CPM definition table. The CPM activities can be adjusted to the
needs of the project. Changes to this table require process owner approval.
PMTR1604B Review Mapping
The mapping table must be reviewed by IPMS startup personnel and adjusted by
the Tracking startup person as required for project procedure and any Milestone
changes.
PMTR1630A Define & Populate Project Data Dates
The project is to define the project data dates or reporting dates. (Mid-Month,
End of Month, Etc.) The Tracking start-up contact will input into IPMS.
PMTR1640A Review Transmittal Associations with Docs
Startup and project personnel for documents, scheduling and tracking must review
the transmittal associations. This table must be adjusted to accommodate chain
defaults and any chain milestone changes.
PMTR1660B Review Default Chains
Default chains must be reviewed by procurement, document, scheduling project
and startup personnel. Item types selected by project personnel must be reviewed
and chain defaults must be adjusted as necessary to assure proper automatic chain
assignment upon item creation.
PMTRXXXA Review Corporate Tables From Glossary
Tracking responsibility to review Tracking maintenance tables for assurance that
Corporate Default Codes are loaded properly.
PMTRXXXB Review Default Tables in Project Instance
Review of standard chain models.

IPMS TRACKING START-UP ACTIVITIES


IPMS Startup Schedule Activity Descriptions

24

05/09/00

ACTIVITY ID
PMTR9999

DESCRIPTION

Tracking Module Functional


Notification of Tracking module functionality is the responsibility of the Tracking
startup representative. Project management and process owners should be
notified.

IPMS Startup Schedule Activity Descriptions

25

05/09/00

SCHEDULING
Pre Start-Up Activities:
PS1000: Develop/Update Level 1 Schedule

Planning Activities:
PS1005: Issue Standard 120-day Front End Detail Schedule
PS1010: Issue Project Specific 120-day Schedule
PS1020: Develop and Issue Level 2 schedule (Control Package)
PS1030: Project Team to Define Schedule Planning Areas
PS1040: Determine Logic & Durations in CPM & IPMS
PS1045: Define Engineering & Construction Interfaces
PS1050: Review Logic and Durations with PSS Department
PS1055: Review and Adjust Level 3 Early Schedule Dates
PS1060: Approve Level 3 Early Schedule
PS1065: Resource Level the Level 3 Schedule
PS1070: Adjust and Approve Level 3 Schedule
PS1075: Issue Level 3 Baseline
PS1085: Establish Level III Activity Structure
PS1095: Pass Level 4 Activities to ACLS/IPMS
PMTR1210A: Input Work Packages in IPMS
PMTR1210B: Input Work Package Budgets in IPMS
PMTR1555A: Download IPMS Work Package Data to CPM
PMTR1557A: Pass Baseline Dates into IPMS Tracking

Execution Activities:
PS1105: Train Construction Controls on Last Planner Work Plan
PS1115: Train Piping Last Planner on Work Plan Interface
PS1125: Establish Project Work Plan Interface
PS9999: Scheduling Start Up complete

IPMS Startup Schedule Activity Descriptions

26

05/09/00

IPMS SCHEDULE START-UP ACTIVITIES


ACTIVITY ID
PS1000

DESCRIPTION

Develope/Update Level 1 Schedule


If a Level 1 Schedule was loaded in the proposal, the Project Team should update
this schedule with current information within one week after contract award or
notice to proceed. If a Level 1 Schedule was not included in the proposal the
Project Team will complete one that meets all current contract requirements.

PS1005

Issue Standard 120 Day Front End Detail Schedule


Engineering management has developed a "Standard 120 Day Front-End Detail
Schedule. An electronic file can be downloaded from the Intranet. The project
scheduler will load this file and generate the reports contained in the file.
The Link for this file is:
http://halworld.halnet.com/ss/sspc/sspc_content/plan_scheduling/sspc_pands_pri
mproj.asp

PS1010

Issue Project Specific 120 Day Front-End Schedule


This schedule will contain project specific activities in sufficient detail to control
the project until the Level 3 Baseline Schedule is developed and issued.

PS1020

Develop & Issue Level 2 Schedule


After the Work Breakdown Structure (WBS) is approved, a Level 2 Schedule will
be developed and issued. This schedule will contain at least one activity for each
cost area/discipline combination. Additionally, activities depicting the path of
critical long-lead items should be included. The Level 2 Schedule should meet the
milestones established in the previously issued Level 1 Schedule.

PS1030:

Project Team to Define Schedule Areas


Once the plot plan has been confirmed, the project team will define schedule areas
using the Business Unit Standard. At KBR, First Planner helps to set the duration
of the project activities for each discipline with in a schedule area. The Level III
Schedule will be generated from the First Planner meetings.

PS1040

Determine Logic and Durations in CPM & IPMS


The scheduler will input inter-work package logic and refine the durations to
finalize the CPM network and produce an Early Date schedule. The durations
may need to be adjusted in IPMS to match the CPM dates.

IPMS Startup Schedule Activity Descriptions

27

05/09/00

IPMS SCHEDULE START-UP ACTIVITIES


ACTIVITY ID
PS1045

DESCRIPTION

Determine Engineering/Construction Interfaces


The scheduler, working with engineering and construction management, will
insert an interface activity between corresponding chains of logic in the
engineering and construction schedules. This interface activity will be used to set
target data for engineering deliverables, and allow sufficient backlog of work for
construction.

PS1050

Review Logic & Durations with PSS Department


When a preliminary CPM schedules is complete, it will be reviewed with Project
Support Services representatives.

PS1055

Review & Adjust Level III Early Schedule Dates


After PSS Department review of the preliminary Level III Schedule, the scheduler
will review the early dates with engineering, construction, and project general
management for approval of the logic, durations and resulting milestone dates.

PS1060

Approve Level III Early Schedule


After review of the early dates, engineering, construction and general project
management should sign the approved block on the schedule.

PS1065

Resource Level the Level III Schedule


Using the appropriate type (time limited or resource limited), the scheduler will
resource level the approved early schedule to optimize resource utilization.

PS1070

Adjust & Approve Level III Schedule (Baseline)


After Resource Leveled Dates are established, the scheduler will review these
dates with the appropriate supervisor and adjust specific activity dates.

PS1075

Issue Level III Schedule


The scheduler will officially issue, by cover letter under the Project Managers
signature, the approved Level III Schedule.

PS1085

Establish Level III Activity Structure


The project will determine the numbering structure for the level 3 schedule IDs.

PS1095

Pass Level 4 Activities to ACLS/IPMS


The pass of level 4 activity information is performed for the Last Planner Work
Plan for construction. This information is passed to ACLS to set pipe priorities.
A file is created by ACLS and passed to the site material control group.

IPMS Startup Schedule Activity Descriptions

28

05/09/00

IPMS SCHEDULE START-UP ACTIVITIES


ACTIVITY ID
PS1105

DESCRIPTION

Train Construction Controls on Last Planner Work Plan


Training for the Last Planner is required for the controls personnel. This is to
assure the interface is set up properly and the correct information is being passed
from scheduling to ACLS and on to material control.

PS1115

Train Piping Last Planner on Work Plan Interface


The Last Planner Work Plan for pipe determines what should be worked on at any
given time during the project. The material control group can give piping detailed
information about any MTO. This determines if the material is on site and can be
installed by the field.

PS1125

Establish Project Work Plan Interface Procedure


The project will determine the timing of the interface between scheduling, ACLS,
material control and the pipe department.

PMTR1210A Identify & Input Work Packages Into IPMS


Using the approved WBS and working with Engineering Management, the
discipline leads will quantify the scope of work and group the work into work
packages. This includes the estimated work hours. A work package input sheet
will be completed by the work group lead. From this input sheet the scheduler
will enter the work package in IPMS.
PMTR1210B Input Work Package Budgets
During the input step describe above the scheduler will input the work package
work hour budgets defined on the input sheet filled out by the discipline leads.
PMTR1557A Pass Baseline Dates into IPMS Tracking
Depending on how the work packages are mapped to the CPM, certain milestone
baseline dates may not be populated by this process. These dates can be calculated
and added manually (as determined by project requirements).
PMTR1555A Download IPMS Work Packages to CPM
Using the IPMS to CPM Interface Program, the scheduler will download work
package information to the CPM System. The initial download will create
activities with appropriate durations, start and finish data, work hour budgets, and
relationships between activities of the same work package.
PS9999

Scheduling Setup Complete


This is a Finish Milestone indicating that all scheduling startup activities are
complete.

IPMS Startup Schedule Activity Descriptions

29

05/09/00

COST CONTROL
Pre Start-Up Activities:
CC1005: Review Cost Reporting Requirements VS Standards
CC1010: Identity Level of Control for Project Budget

Start-Up Activities:
CC1000: Review Global & Default Codes
CC1015: Establish CDT/CDST Budget Defaults
CC1020: Review/Revise GL to Cost Category Codes
CC1025: Populate Currency Default by Month
CC1030: Establish/Populate WBS Codes
CC1035: Populate PCOA/Subproject PCOA
CC1040: Populate Cost Categories for PCOA Table
CC1045: Identify/Populate Control Package Numbering Schemes
CC1046: Establish Extraction Parameters
CC1050: Identify/Populate Bulk Material Allocation
CC1055: Populate PCOA Rules/Material Reference Codes for Tag Items and Non-standards
CC1056: Populate PCOA Rules for Bulk Materials
CC1065: Populate Project Hierarchies for Reporting
CC1085: Load Progress
CC9000: IPMS Cost Module Set-Up Complete

Planning Activities:
CC1060: Load Estimates
CC1075: Connect WBS/PCOA's to Work Packages
CC1080: Balance Estimate and Populate Control Estimate

Execution Activities:
CC1047: Create Freeze
CC1048: Post Actual Costs
CC1070: Identify IPMS Variance Matrix Approach
CC1090: Run Cost Summary Report

IPMS Startup Schedule Activity Descriptions

30

05/09/00

IPMS COST CONTROL START-UP ACTIVITIES


ACTIVITY ID
CC1000

DESCRIPTION

Review all Global and Default Codes - PMRR1132/PMCC1020.


Review and revise Cost Control Code Spec Tables in Reference (PMRR1132).
There are twelve Code Spec Types in Cost: Job Number Billing Type; Cost
Category Type; Cost Freeze Type; Commitment Header Type; Control Type;
Code of Account Type; Curve Type; General Ledger Code; Project Deviation
Notice Type; Problem Group; Allocation Method Type, and Variance Group.
Review Corporate Code of Account Table (PMCC1020).

CC1005

Review Cost Reporting Requirements vs. Standard


Cost reporting requirements, defined in the RFP/Contract, further identification of
client reporting/capitalization guidelines, and B&R Management needs, will
influence coding structure, level of control, variance matrices, labor interface
requirements (i.e. billed vs. actual) and other downstream activities.

CC1010

Identify Level of Control for Project Budget


Identifying control level for the original budget and variances is essential in that
this decision drives activities tied to MRP and Tracking. If the level of control is
at the Tag Item level, the tag member must exist in MRP catalog and the PCOA
must reside in the Tag Item Maintenance table before loading the estimate. If the
level of control is at the work package level, workpackages must exist in the work
package header form prior to bringing the estimate into IPMS.

CC1015

Establish CDT/CDST Defaults for Budgets - PMCC1110


CDT/CDST standards have been established for budget, commitment and actual
expenditure transactions. These need to be reviewed and populated in the project
database. The department process owner must approve any deviations.

CC1020

Review/Revise GL to Cost Category Codes - PMCC1050


IPMS budgets and records expenditures at a more summary level than the GL
Code by grouping like GL Codes and tying them to Cost Categories. The Cost
Category level is the summary level that is used in Cost. Departmental standards
have been established for this activity. They must be reviewed and revised as
required.

CC1025

Populate Currency Default by Month - PMCC1120


This table must be populated prior to any transactions occurring, i.e. loading
budgets and posting actuals. This table is based on the subprojects default
currency and is used for establishing the monthly conversions used by Halliburton
Corp. A conversion, even if it is the same as the subproject default, must be
established for each month of the project duration.

IPMS Startup Schedule Activity Descriptions

31

05/09/00

IPMS COST CONTROL START-UP ACTIVITIES


ACTIVITY ID
CC1030

DESCRIPTION

Establish/Populate WBS Code Tables - PMRR1214/1216


Upon determination of the WBS Codes to be used on the project, the WBS Code
Type and WBS Codes most be populated right away. The WBS Code table is one
of the most commonly used table by other applications and is required early on in
many start-up activities. Once WBS Codes are established, they should not be
changed.

CC1035

Populate PCOA/Subproject PCOA PMCC1020


Project specific code of accounts for engineering, project management, material
and construction directs/indirects must be populated in the Project Code of
Account Maintenance table. The subproject code of account must also be
populated.

CC1040

Populate Cost Categories for PCOA Table - PMCC1020/1050


Once activity CC1020 has completed, all relative cost cats must be tied to the
project code of accounts (PCOA's) before any budget, commitment or actual
transactions can occur.

CC1045

Identify/Populate Control Packages - PMCC1090


Based on reviews in activity CC1005, relative WBS Code/PCOA combinations
can be established and linked to Control Packages, which are used for reporting
purposes.

CC1046

Establish Extraction Parameters - PMCC1360/1365/1330/1440


The extraction parameters for the labor, accounting, and commitment interfaces
must be established prior to receiving any transactions of these types.

CC1047

Create Freezes
Before actuals are posted in the system, PMCC1700, Freeze Indicator, should be
established.

CC1048

Post Actual Expenditures


Labor and accounting costs can post to the system.

CC1050

Identify/Populate Bulk Material Allocation Method - PMCC1510


If bulk material will be allocated, then bulk PCOA's must have the allocation
method for distribution assigned.

IPMS Startup Schedule Activity Descriptions

32

05/09/00

IPMS COST CONTROL START-UP ACTIVITIES


ACTIVITY ID
CC1055

DESCRIPTION

Populate PCOA Rules for Tag Items and Non-Standards


Tag items must have a PCOA assigned to them in the Tag Item Maintenance
table. This is accomplished by creating a relationship between the tag number and
a PCOA in the PCOA Rules Table (PMCC1910). All non-standard material
references items must have a PCOA assigned via PCOA Rules Table.

CC1056

Populate PCOA Rules for Bulk Materials - PMCC1910


Like tag item maintenance, PCOA's must exist for each bulk material reference in
the MRP Catalog. To accomplish this, the PCOA Rules Table must be populated
for all bulk material. When all the material references have been populated with
PCOAs, commitments can be brought into the Cost Module.

CC1060

Load Estimate(s) - PMCC1310


The estimate Interface between Program Estimate and IPMS results in this form
being populated. If an estimate is to be loaded from a source other than B&R's
estimate program, a review for record layout must be discussed with Cost support
personnel so that an interface may be provided which will facilitate this activity.
After the loading the estimate, make the Control Type Assignment and release the
estimate to the control level.

CC1065

Populate Project Hierarchies for Reporting - PMRR1610


Certain reports within Cost Module require a hierarchy to be established prior to
executing. These are primarily Cost Comparison type report and Cost/Scheduling
analysis type. They are typically run at a Control Package or Workpackage level.
Obviously, these elements of data must be established before this activity can be
accomplished. Logs, listings, commitment reports and variance reports do not
require a hierarchy

CC1070

Identify IPMS Variance Matrix Approach - PMCC1170


Based on CDT/CDSts and variance types, a matrix must be established in order
for an approved variance to update the required budgets. PDNs, variances and
change orders can be tracked in IPMS.

CC1075

Connect WBS/PCOA's to Workpackage (if required) - PMTR1210


If the control level budget does not include a workpackage number, the
WBS/PCOA tie must be made in the budget pop-up of the Workpackage Header
PMCC1210.

IPMS Startup Schedule Activity Descriptions

33

05/09/00

IPMS COST CONTROL START-UP ACTIVITIES


ACTIVITY ID
CC1080

DESCRIPTION

Balance Estimate & Populate Control Estimate PMCC1320


The control estimate can be manually entered, released from the detail estimate
(PMCC1310), or loaded from workpackages. The control estimate must validate
against a series of tables within IPMS before it can be released to the Cost
Summary as the original budget.

CC1085

Load Progress PMCC1350


If progress will be reported in the cost module, use PMCC1350 for that purpose.

CC1090

Run Cost Summary Report PMCC1710/1720


All the cost data can be viewed in the cost summary forms PMCC1710/1720 and
printed using the various cost reports.

CC9000

Cost Module Functional

IPMS Startup Schedule Activity Descriptions

34

05/09/00

SITE MATERIAL CONTROL


Execution Activities:
PMRR1505: Create Priorities and Priority Dates PMRR1502
PMSC1105: Create Warehouse & Location Bins
PMSC1115: Attach Material Reference Numbers to Bin Locations - PMSC1115
PMSC1140: Establish Max / Max Inventory Levels PMSC1140
PMSC1205: Identify Items for Preventive Maintenance PMCS1205
PMSC1306: Set Parameters for Painted Pipe Extract PMCS1306
PMSC1415: Select Address and Warehouse For Work Planning PMCS1415
Create a warehouse of '001'_DEFAULT and bin location of 'DEFAULT' for each destination
address. IPMS Site Form PMSC1105 is used to do this.

IPMS Startup Schedule Activity Descriptions

35

05/09/00

IPMS SITE CONTROL & CONSTRUCTION SUPPORT STARTUP ACTIVITIES


ACTIVITY ID
PMRR1505

DESCRIPTION

Create Priorities and Priority Dates


Use this form to maintain the priority codes used by projects/subprojects. The
priority code information is used by MRP and Site Control for Last Planner work
plan.

PMSC1105

Create Warehouse & Bin Locations


Warehouse Locator Maintenance. Use this form to maintain inventory location(s)
for items identified by material reference numbers and stored in a given
warehouse. You can identify one primary location and multiple secondary
locations for each material reference number.

PMSC1115

Attach Material Reference Numbers to Bin Locations


Attach the material reference number to the actual bins in the warehouse.

PMSC1140

Set-Up Max/Min Inventory Levels


Max / Min Maintenance. Use this form to maintain an inventory of items that are
controlled on a reorder-point basis (max/min). Use the max/min feature for items
that are not generally considered as part of the material takeoff process (such as
small-bore pipe).

PMSC1205

Identify Items for Preventive Maintenance


Identify items requiring periodic Preventive Maintenance. Use this form to record
periodic maintenance performed on a tagged item. This form shows the complete
history of maintenance work performed on the tagged item and the next projected
date to perform the maintenance.

PMSC1306

Set Parameters for Painted Pipe Extract


Painted Pipe Selection Parameters. Use this form to identify the parameters and
rules used to extract requirements from the bills of material in the Material
Requirements Planning application. The extracted requirements are copied into
the Painted Pipe module in the Construction Support application.

PMSC1415

Select Address and Warehouse for Work Planning


Work Plan Address Selection for Available Material. Use this form to select
addresses and warehouses that will be used in the work plan available material
extract.

IPMS Startup Schedule Activity Descriptions

36

05/09/00

QUANTITY SURVEYING
Execution Activities:
QS1000: Confirm Set-Up of Network ACLS, Access to System
QS1005: Receive Estimate ACSII File
QS1010: Establish ACLS Coding & Sub-coding Structure
QS1015: Load Estimate to ACLS
QS1020: Develop/Load Project ACLS Milestones
QS1025: Set-Up Unit Rate Labor Sub-system
QS1030: Review IPMS Interface, Roles of ACLS Personnel
QS1035: Set-Up Work Plan Interface
QS1040: Perform ACLS Interface
QS1045: Balance Estimate Cost, Tracking & Scheduling

IPMS Startup Schedule Activity Descriptions

37

05/09/00

IPMS QUANTITY SURVEYING START-UP ACTIVITIES


ACTIVITY ID
QS1000

DESCRIPTION

Confirm Set-Up of Network ACLS, Access to System


Confirm Oracle Network Client Server ACLS Set-Up and access in coordination
with Business Unit IT Representatives. Run ACLS99 Winstall script on ACLS
PCs.

QS1005

Receive Estimate ACSII File


Receive Estimate Control File (ASCII) and review project scope pending WBS
Development.

QS1010

Establish ACLS Coding & Sub-coding Structure


Develop Detailed Sub-code to Control Estimate: Balance Estimate.

QS1015

Load Estimate to ACLS


Load Detailed Control Estimate to various ACLS tables.

QS1020

Develop/Load Project ACLS Milestones


Development/Acceptance of ACLS Project Milestones using the Standard
Milestone Guide list or adjusting to fit the project needs.

QS1025

Set-Up Unit Rate Labor Sub-system


Set-up and attach main stem, area stem and control package to ACLS detailed
codes for rollup and interface with Cost and Scheduling.

QS1030

Review IPMS Interface, Role of ACLS Personnel


Review IPMS interfaces with ACLS, Cost, and Scheduling personnel on IPMS
projects only. Verify work flow process for the Controls Group.

QS1035

Set-Up Work Plan Interface


Review level 4 Id's with Scheduling and Material Control. Verify work flow
process for Last Planner.

QS1040

Perform ACLS Interface


Perform IPMS interfaces according to Controls Group work flow process.
PMAI5010-Work Package download to ACLS
PMAI5040-Control Package Activity download to ACLS
PMAI500X-ACLS Progress back to IPMS
PMAI505X-Work Planner pass to IMPS

IPMS Startup Schedule Activity Descriptions

38

05/09/00

IPMS QUANTITY SURVEYING START-UP ACTIVITIES


ACTIVITY ID
QS1045

DESCRIPTION

Balance Estimate Cost, Tracking & Scheduling


The project needs to balance the budgets between the controls groups. This
should be done monthly at the very least.

IPMS Startup Schedule Activity Descriptions

39