Professional Documents
Culture Documents
DesignofSewerSystemCivilEngineersPK
Search
CivilEngineersPK
Search
EverythingRelatedtoCivilEngineering
Adsby Google
ExcelSheets
Adsby Google
PipingDesign
Codes
Books
SlopeDesign
HousePlans
FrontViews
PipingDesign
WaterTankDesign
VideoTutorials
ConstructionMachinery
SlopeDesign
PosterPresentation
WaterTankDesign
WastewaterAeration
SSIoffersdisc&tubemembranewastewatertreatmentsystems.Gotossiaeration.com/diffusers
DryMixMortarPlant
Drillpumps&sparepartsfromRussia
CVSengineeringGmbH
RealtimeEffluentMonitoringMonitorasperCPCBCompliance
PipeFitting
Download
Aerators
EffluentsEstruagua
WavebriteGreyWaterUnit
Adsby Google
PipingDesign
SlopeDesign
DrainageDesign
DesignofSewerSystem
38
DESIGNOFSEWERSYSTEM
http://civilengineerspk.com/designofsewersystem/
1/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
INTRODUCTION
DesignofSewerSystem.Sewersystemplaysavitalroleintheeconomicdevelopmentofacountry.Sewersaremustforthedrainageofwastewater.
Inordertohaveaneffectivesewagesystemthesewersshouldbeproperlydesignedandmorecareshouldbetakeninfindingtheinvertlevels
otherwisewholedesignmaygetwrong.DesignofSewerSystem.Sewersaredesignedforthedrainageofwastewatercomingfromhouses,
industries,streets,runoffetctoprotecttheenvironmentandpeoplefromseriousdiseases,asmorethan50diseasesspreadfromsewage.Sofora
goodliving,thesewersshouldbeproperlydesignedandthesewageshouldbetreatedproperlybeforedischargingitintotheriver.DesignofSewer
System
Someoftheimportantandrelevanttermsforsewersystemarediscussedbelow.
Sewage
ItisLiquidWasteorWasteWaterproduceasaresultofwateruse.DesignofSewerSystem
Sewer
Itisthepipeorconduitforcarryingsewage.Itisgenerallyclosedandflowtakesplaceundrgravity(AtmosphericPressure).DesignofSewerSystem
Sewerage
Sewerageisthesystemofcollectionofwastewaterandconveyingittoapointoffinaldisposalwithorwithouttreatment.DesignofSewerSystem
Sourcesofwastewater
Followingaretheprincipalsourcesofwastewater
Domestic
Industrial
Stormwater
http://civilengineerspk.com/designofsewersystem/
2/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
Domestic
Itisthewastewaterfromhouses,offices,otherbuildings,hotelsandinstitutions.DesignofSewerSystem
Industrial
Itistheliquidwastefromtheindustrialplacesfromtheirdifferentindustrialprocesseslikedying,papermatting,tanneries,chemicalindustries,
etc.DesignofSewerSystem
StormWater
Itincludessurfacerunoffgeneratedfromrainfallandthestreetwash.DesignofSewerSystem
TypesofSewerSystems
Followingarethetypesofsewerage.DesignofSewerSystem
SeparateSystem
Itisthesysteminwhichstormwateriscarriedseparatelyfromdomesticandindustrialwastewater.Thissystemispreferredwhen
Thereisanimmediateneedforcollectionofsanitarysewagebutnotforstormwater
Whensanitarysewageneedstreatmentbutthestormwaterdoesnot.DesignofSewerSystem
http://civilengineerspk.com/designofsewersystem/
3/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
CombinedSystem
Itisthetypeofsysteminwhichsewercarriesboththesanitaryandstormwater.Combined
systemisfavoredwhen
Combinedsewagecanbedisposedoffwithouttreatment
Bothsanitaryandstormwaterneedtreatment
Streetsarenarrowandtwoseparatesewerscannotbelaid.DesignofSewerSystem
http://civilengineerspk.com/designofsewersystem/
4/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
TypesofSewersDesignofSewerSystem
http://civilengineerspk.com/designofsewersystem/
5/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
SanitarySewers
Itcarriessanitarysewagei.e.wastewaterfrommunicipalityincludingDomesticandIndustrialwastewaters.DesignofSewerSystem
http://civilengineerspk.com/designofsewersystem/
6/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
StormSewer
ItcarriesstormsewageincludingSurfaceRunoffandStreetWash.DesignofSewerSystem
CombinedSewer
Itcarriesdomestic,industrialandstormsewage.DesignofSewerSystem
HouseSewer
Itisthesewerconveyingsewagefromplumbingsystemofbuildingtocommon/municipalsewers.
Lateralsewer
Thissewercarriesdischargefromtwoormorehousesewers.DesignofSewerSystem
http://civilengineerspk.com/designofsewersystem/
7/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
SubMainSewer
Thissewercarriesdischargefromtwoormorelaterals.DesignofSewerSystem
Main/TrunkSewer
Itreceivesdischargefromtwoormoresubmains.
OutfallSewer
Itreceivesdischargefromallcollectingsystemandconveysittothepointoffinaldisposal.
http://civilengineerspk.com/designofsewersystem/
8/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
Sewageflow
Itisflowderivedfromthesanitaryandindustrialsewagethatistherawwaterfromtheseindustriesandhouses,soitmeansithasdirectrelationwith
theamountofwaterconsumed.
Generally80to90%ofthewaterconsumptionistakenassewageorwastewaterflow.DesignofSewerSystem
Variationinsewageflow
Likewatersupply,sewageflowvariesfromtimetotime.SincesewersmustbeabletoaccommodateMaximumRateofFlow,thevariationinthe
sewageflowmustbestudied.
GenerallyHermanFormulaisusedtoestimatetheratioofMaximumtoAverageFlow
Pispopulationinthousands.DesignofSewerSystem
http://civilengineerspk.com/designofsewersystem/
9/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
WASALahoreDesignConsidersthefollowingrelationshipforsewerdesign
AverageSewageFlow(m3 /day)
PeakFactor
2500
4.0
25005000
3.4
500010000
3.1
1000025000
2.7
2500050000
2.5
50000100000
2.3
100000250000
2.15
250000500000
2.08
>500000
2.0
Infiltration
Itisamountofwaterthatentersintothesewersthroughpoorjoints,crackedpipes,wallsandcoversofmanholes.DesignofSewerSystem
Itisnonexistentduringdryweatherbutincreasesduringrainyseason.
WaterandSanitationAgency(WASA)Lahoreusesthefollowinginfiltrationratesforthedesignofsewersystem.
SewerDiameter
Infiltration
225mmto600mm
5%ofAvg.SewageFlow
>600mm
10%ofAvg.SewageFlow
http://civilengineerspk.com/designofsewersystem/
10/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
DesignPeriod
SewerSystem
Periodofdesignisindefinite.Thesystemisdesignedtotakecareforthemaximumdevelopmentofthearea.Butwetakedesignperiodof20yearsfor
oursewersystem.DesignofSewerSystem
SewerPumpingStation
Designperiodis10years.
RateofFlowareaveragedaily,peakandminimumflowincludingInfiltration.
PROJECTDESCRIPTION
TheprojectisbasedonthedesignofPartiallycombinedseweragesystemofacommunitywhichishavingapproximatelyaflatterrainbecausethe
differenceinthereducelevelsisverysmall.Ihavedesignedthesewagepumpingstationalongwiththehydraulicstatementandtherequireddrawings
plussomeextradrawings.Iamconfidentthatmydesignwillworksuccessfullyandtherewillbenotanyproblems.TheLayoutofthecommunityis
givenasunder.DesignofSewerSystem
http://civilengineerspk.com/designofsewersystem/
11/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
DESIGNCRITERIA
DesignFlow
Firstofallcalculatetheaveragesewageflowonthebasisofwaterconsumptionandthepopulationattheendofthedesignperiod.i.eatthefull
developmentofthearea.Thenthedesignflowforsanitarysewerandpartiallycombinedsewerscanbycalculatedbyusingthefollowing
formulae.DesignofSewerSystem
ForSanitarySewer
Qdesign =Peaksewageflow+infiltration
Forpartiallycombinedsewer(WASACriteria)
Qdesign =2xPeaksewageflow+infiltration
DesignEquation
http://civilengineerspk.com/designofsewersystem/
12/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
ManningsEquationisusedforsewersflowingundergravityDesignofSewerSystem
Where
V=Velocityofflowinm/sec
R=Hydraulicmeandepth(A/P)=D/4whenpipeisflowingfullorhalffull
S=Slopeofthesewer
n=Coefficientofroughnessforpipes
Minimum(SelfCleansing)Velocity
Sewageshouldflowatalltimeswithsufficientvelocitytopreventthesettlementofsolidmatterinthesewer.SelfCleansingVelocityistheminimum
velocitythatensuresnonsettlementofsuspendedmatterinthesewer.DesignofSewerSystem
Thefollowingminimumvelocitiesaregenerallyemployed
Sanitarysewer=0.6m/sec
Stormsewer=1.0m/sec
Partiallycombinedsewer=0.7m/sec
Maximumvelocity
Themaximumvelocitiesinthesewerpipesshouldnotexceedmorethan2.4m/sec.Thismaxvelocityinthesewershouldnotexceedthislimitof2.4
m/sec.Itistoavoidtheexcessivesewerabrasionandalsotoavoidsteepslopes.DesignofSewerSystem
MinimumSewerSize
225mmistakenastheminimumsewersize.Thereasonbeingthat,thechokingdoesnottakeplaceevenwiththebiggersizeparticles,whichare
usuallythrownintothesewerthroughmanholes.DesignofSewerSystem
http://civilengineerspk.com/designofsewersystem/
13/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
MinimumCoverofSewer
1mistakenastheminimumcoveroverthesewerstoavoiddamagefromliveloadscomingonthesewer.DesignofSewerSystem
SpacingofManhole(WASA,Criteria)
For(SewerSize)225mmto380mmspacingnotmorethan100m
For(SewerSize)460mmto760mmspacingnotmorethan120m
For(SewerSize)greaterthan760mmspacingnotmorethan150m
DirectionofSewerLine
Sewershouldflow,asforaspossibletheNaturalSlope.DesignofSewerSystem
DesignofSewer
SizeofSewer
Usethefollowingrelationtofindthediameterofsewer
Qf=AxV
SlopeofSewer
SelecttheminimumvelocityvalueandusetheManningsformula
http://civilengineerspk.com/designofsewersystem/
14/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
InvertLevel
ThelowestinsidelevelatanycrosssectionofasewerpipeisknownasInvertLevelatthatCrosssection.DesignofSewerSystem
InvertLevel=NGSL/RoadLevelDepthofSewerThicknessofSewerDia.ofSewer
JointsinSewers
Bell&SpigotJoint
Tongue&GrooveJoint
Manholes
Theseareprovidedfor
Cleaning
inspectionand
houseconnection
At
http://civilengineerspk.com/designofsewersystem/
15/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
ChangeinSewerdirection
Changeinsewerdiameter
Changeinslope
Onemanholetobeprovidedfor24plotsDesignofSewerSystem
DesignofSewerSystem
SEWERAGEDESIGNDATA
NoofPlots=281
NoofApartments=3
NoofFlats=3
Designperiod=20years
POPULATIONFORECAST
Persons/plot
http://civilengineerspk.com/designofsewersystem/
Present(2009)
Design(2029)
10
16/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
Persons/apartment
400
600
Persons/flat
200
400
POPULATIONFORECASTING
PresentPopulationPp=1)2817+4003+2003=3767
DesignPopulationPd=2)28110+6003+4003=5810
AnnualGrowthRate=2.1%(ForPakistan,2008report)
DesignPopulationPd
DesignofSewerSystem
1)Pd=Ppx(1+2.1/100)20
Pd=3767x(1+2.1/100)20 =5709
Pd=5810(FromTable)
Percapitawaterconsumption=350+44=394lpcd(literspercapitaperday)
AverageDesignflow=Pd xwaterconsumptionx0.8/1000
(80%goestosewersaswastewater)
=(394x5810x0.8)/1000
Qavg=1831.312m3 /day
Peakfactor=4(fromWASAtable)
ToCheckInfiltrationrates
http://civilengineerspk.com/designofsewersystem/
17/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
DESIGNOFWETWELL
Qmax=14742.1m3 /day=10.237m3 /min
http://civilengineerspk.com/designofsewersystem/
18/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
Pumpingcapacity
P=Qmax=10.237m3 /min
MinimumcycletimeDesignofSewerSystem
MinimumCycletimemustnotbelessthan5minutes
Forsmallerpumpstmin=15min
Volume=V=[Pxt(min)]/4
EffectiveVolume=(10.237x15)/4=38.39m3DesignofSewerSystem
DIMENSIONSOFWETWELL
Length=3.6mDesignofSewerSystem
Width=3.6m
Height=3m
Volume=3.6*3.6*3=38.88m3
Pumpmustrunforatleast2minutes
Checkthecycletime,shouldbegreaterthan2minutes
t=V/(PQmin)=38.39/(10.2370.6358)=3.99~=4
So4minutesisgreaterthan2minutes..(OK)DesignofSewerSystem
CycleTimeforMinimumandAverageFlow
CYCLETIME=t=(V/(PQ))+(V/Q)
ForQmin=38.39/(10.2370.6358)+38.398/0.6358=64.391min>15min(OK)
ForQavg=38.39/(10.2371.271)+38.39/1.271=34.48min>15min(OK)
http://civilengineerspk.com/designofsewersystem/
19/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
http://civilengineerspk.com/designofsewersystem/
20/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
http://civilengineerspk.com/designofsewersystem/
21/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
http://civilengineerspk.com/designofsewersystem/
22/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
MANHOLE
http://civilengineerspk.com/designofsewersystem/
23/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
http://civilengineerspk.com/designofsewersystem/
24/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
DROPMANHOLE
http://civilengineerspk.com/designofsewersystem/
25/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
http://civilengineerspk.com/designofsewersystem/
26/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
SEWERJOINTS
http://civilengineerspk.com/designofsewersystem/
27/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
http://civilengineerspk.com/designofsewersystem/
28/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
SEWERBEDDINGS
http://civilengineerspk.com/designofsewersystem/
29/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
http://civilengineerspk.com/designofsewersystem/
30/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
COMMENTS
Thisdesignisbasedonpartiallycombinedseweragesystemthusiseconomic.
AllthenecessarythingsaretakenfromtheWASAtablesandMinimumvelocityistakenas0.6m/secwhichistheselfcleansingvelocityand
velocitymustnotbemorethan2.4m/sec.
Minimumdiameterofseweristakenas225mmandotherdiametersareroundedtothelocallyavailableinthemarketaccordingtoWASA
standards.
Minimumrateofsewageflowistakenas50%ofaveragesewageflow.
Minimumclearcoverof1misprovidedabovethesewerinordertoavoidfromimpactofliveloading.
Flushtanksareprovidedwherevelocityislessthan0.6m/Sec.DesignofSewerSystem
RESULTS
Diametersarelessthen600mmsoInfiltrationrateusedis5%ofaveragesewageflow.
Bell&Spigotjointshavebeenusedasthediametersarelessthen600mm.
OneDropManholeiscomingatM15astheverticaldropismorethan0.6m.
InSewers(M9M8,M8M11,M10M11,M12M13,M5M18,M20M21,M24M21,M21M22,M25M26),Velocityislessthantheselfcleansing
velocitySo,Flushtankswillbeprovidedhere.
Mostofthediametersareof225mmensuringtheeconomicsideoftheproject.
http://civilengineerspk.com/designofsewersystem/
31/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
Wetwelldimensionsare2.53.54.4.
Cycletimeof15minutesissatisfiedensuringtheadaptabilityofsmallpumpssomoreeconomic.
RECOMMENDATIONS
Flushtanksshouldbeflushedoncein24hourstoavoidsedimentdeposition.
Iftheseweristobelaidunderthewatertablethencrushedstonebeddingshouldbeused.
Sewersshouldbejoinedinamanholekeepingthecrownsatthesamelevel.
DesignofSewerSystem,DesignofSewerSystem,DesignofSewerSystem,DesignofSewerSystem
40thoughtsonDESIGNOFSEWERSYSTEM
AnwaarAhmed
onNovember7,2014at16:12said:
GoodWorkSir
IamworkingasSubEngineerataTMA.Igotenoughguidancefromworkgoodwork.
Regards
UBAIDAHMAD
onNovember8,2014at07:56said:
THANKS
http://civilengineerspk.com/designofsewersystem/
32/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
Ebd
onFebruary26,2015at20:39said:
Yousaidthatthedrainagedesignisequaltotwotimesthemaximumdischargewhilewhencalculatedleakagereportedthat
drainagedesignisequaltotwotimestherateofdischarge..Ihopestatementthispointifallowed
MAYANKNAGLE
onNovember2,2016at14:14said:
Itbestdescriptionforsewardesign&itssohalpfullforme.Sothankusir
CIVILENGINEERSPK
onNovember2,2016at17:19said:
YouareWelcome
AbdulRaheemSiddiqui
onJanuary20,2015at07:24said:
http://civilengineerspk.com/designofsewersystem/
33/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
Verygoodmaterial,itwillbemorebeneficialifyoucouldhaveshownthecalculationoruploadedsupportingexcelfile.
UBAIDAHMAD
onJanuary20,2015at15:35said:
NOPE
Ebd
onFebruary26,2015at20:41said:
Yousaidthatthedrainagedesignisequaltotwotimesthemaximumdischargewhilewhencalculatedleakagereportedthatdrainagedesignisequalto
twotimestherateofdischarge..Ihopestatementthispointifallowed
ABEDELBASET
onMarch23,2015at09:17said:
HI:
IWOULDLIKETOBUYPROGRAMFORDESIGNSEWAGENETWORKWITHPROFILE.
UBAIDAHMAD
http://civilengineerspk.com/designofsewersystem/
34/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
onMarch23,2015at11:03said:
Allsoftwaresavailableonthesiterequiremembership.
http://civilengineerspk.com/membership/
QaziLitafatUrRehman
onJanuary2,2016at17:42said:
IcannotdownloadExcelsheetsasIrequireoneforthedesignofSeweragesystemthoughIgotthemembership
UBAIDAHMAD
onJanuary2,2016at18:29said:
Allexcelsheetsareavailablehereonly
http://civilengineerspk.com/excelsheets/
WanjalaDanielMasinde
onMarch31,2015at07:33said:
Wouldliketoinquiremoreonhowtoovercomeexcesssewageinplaceswherethereisalreadyestablishedsewerlineyetthereisincreasedpopulation
http://civilengineerspk.com/designofsewersystem/
35/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
UBAIDAHMAD
onMarch31,2015at13:09said:
Howmuchsewageyouaretalkingabout?
gebrewahid
onApril15,2015at09:21said:
IWOULDLIKETOBUYPROGRAMFORDESIGNSEWAGENETWORKWITHPROFILE
UBAIDAHMAD
onApril15,2015at14:59said:
itsalreadyavailablefreeonline
Sonia
onApril18,2015at10:23said:
http://civilengineerspk.com/designofsewersystem/
36/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
Thanxalot.Thisarticlewasalifesaver.Iamdoingsomethingsimilarformyundergradproject.IsthereinformationonABR(AnaerobiBaffleReactor)
sizingandformulas?
Thanxagain.
UBAIDAHMAD
onApril18,2015at18:29said:
yourwelcome
NomanKhan
onMay1,2015at09:24said:
Hellosiryourworkisveryappreciable,sircanyouplztellmehowmanytypesofnetworkingarethereinseweragesystemandwhataretheirnames.
Andalsowheredoesthepeakfacorlike4.5,4,3comefrom.
Hopeuwouldconsidermyquestion.
Thankyou!
UBAIDAHMAD
onMay5,2015at10:46said:
http://civilengineerspk.com/designofsewersystem/
http://civilengineerspk.com/designofsewersystem/
37/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
QaziLitafatUrRehman
onJanuary2,2016at18:06said:
PleasesendExcelsheetforthedesignofseweragesystemonmyIDlitafat@gmail.comPleasenotethatIgotthemembership,thanks
UBAIDAHMAD
onJanuary2,2016at18:27said:
Allexcelsheetsareavailableherehttp://civilengineerspk.com/excelsheets/
KHIDIRBALLA
onFebruary7,2016at08:03said:
IwouldliketoaskifIwanttodesignseparatesewersystemwhereisthedifferentwillbeisitintheslopesonly!!,andwhattypeofpipeyou
recommendUPVCorGRP
UBAIDAHMAD
onFebruary7,2016at08:58said:
http://civilengineerspk.com/designofsewersystem/
38/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
Youwillbeusingallparametersofseparatesewersystemlikedischarge,selfcleansingvelocityetc.
sam
onFebruary19,2016at02:24said:
couldyoupleasegivemeanexampleoftheAnalysisstatementformainsewerforanyarea?
UBAIDAHMAD
onFebruary19,2016at09:44said:
what?
Esa
onMarch15,2016at20:05said:
Impressive..canuplztellmewhatshouldbethecoveringthicknessforRccpipesBiniththemainroadifpipesizeisapproximately24inchindia
http://civilengineerspk.com/designofsewersystem/
39/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
yesha
onMarch27,2016at19:26said:
Thiswasreallyhelpful,imworkingonmycollegeprojectandthiskindahelpedmesavetimetogothroughalltheliteratureregardingdesignasm
alreadyrunningshortofit.Thankyou!
UBAIDAHMAD
onMarch28,2016at08:33said:
YoureWelcome
Wearegladthatithelpedyou.
JennyChristopher
onApril17,2016at21:02said:
Hello,
IamastudentattheUniversityofWisconsinStevensPoint.ForainterpretivemediaclassIhavetodesignasignforalocalwastewatertreatment
plantinGreenBaytousetoeducatetheirvisitors.Iamlookingforanimageofaseparatesewersystemtouseinthesignandcameacrossacouple
onyourwebsitethatwouldbeperfect.Iwaswonderingifyouwouldallowmetouseanyofyourimagesandifyouhaveanyhighqualityversionsof
them?
UBAIDAHMAD
onApril18,2016at02:51said:
http://civilengineerspk.com/designofsewersystem/
40/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
Youcanclickonthemanddownloadthemasperyourrequirement.
pemayangjey
onMay20,2016at08:43said:
Thesitewasworthvisitingforme.itwasindeedwhichhelpedmethemostindoingmyfinalyearprojectinDiplomacoursethisyear.soiwouldliketo
thankandsayiamverypleasedtogetaccessedtothis.thanksforthehelps.
UBAIDAHMAD
onMay20,2016at14:46said:
YouareWelcome
abdurahim
onAugust30,2016at18:29said:
canudoitpiiz
http://civilengineerspk.com/designofsewersystem/
41/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
CIVILENGINEERSPK
onAugust30,2016at19:52said:
Nowedontsolvequestionshere
faizalibnnazeer
onOctober3,2016at19:01said:
heredesignofsewerinsoftwaretoolwasmissingsirlikeautocadorstaadproectifuprovidethatitwillhelpforupcomingcivilenggstudentlikeme
BasitAli
onNovember15,2016at17:56said:
ThanksSirapkissdesignkiwajahsehaminkhudzyadatypenaikrnapara
CIVILENGINEERSPK
onNovember16,2016at04:30said:
SamajhAanichahiyetakkhudkarsako.
http://civilengineerspk.com/designofsewersystem/
42/43
12/23/2016
DesignofSewerSystemCivilEngineersPK
Esha
onNovember22,2016at20:38said:
whatistheminimumthresholdforoptingseparateseweragesystemintermsofIndianconditions?