Professional Documents
Culture Documents
Estimates
Operations Review
Special Mark-ups
Supplier Representatives
m. Project Schedule
3. Estimate Support Information
a. Overall Estimate Summary Sheet
b. Analysis of Estimate/Comparison to past projects
(1) Materials-Equipment, Bulks, Material Related, Subcontracts
(2)
e.
f.
g.
h.
Engineering
Construction/Plant Services representative
Procurement
Technology Acquisition and Development representative, when
appropriate
i. Manager, Estimating
j. Proposals
k. Financial representative
l. Appropriate Vice President Operations/ Sr. Vice President
Operations, if required.
NOTE: Attendance and sign-off may be delegated to
appropriate senior people, if necessary.
4. A quorum of two Vice Presidents, including one Vice President from
Project Management, must be present all EPC proposals/projects.
Construction only proposals require a Construction Vice President
present. Home Office only proposals require an Engineering Vice
President.
5. Distribution of key information shall be limited on each estimate to
those who are to participate in the review. The estimate summaries
are presented during the meeting and are not distributed in advance.
The recommended operations contingency approved by the Principal
Estimator, Manager of Estimating, and the Proposal/Project Manager
following the Estimating Department and team review are shown on
the signed estimate summary sheet.
6. Attendees are responsible for review of assessment of risk and liability
exposure.
7. The Proposal/Project Manager is responsible for ensuring that on
conclusion of the meeting, all key information packages are collected
in the meeting room and shredded, except those issued to key
individuals, such as the Vice President, Contract Management; Vice
Presidents Project Management; Manager, Estimating; and the
Proposal/Project Manager.
8. The Proposal/Project Manager is responsible for follow up actions as
necessary.
9. Upon completion of the review(s), the Proposal/Project Manager shall
have the estimate summary signed-off. (Refer to Section I for estimate
review levels.) If revisions occur during the Operations Review, the
Proposal/Project Manager will have the revised estimate summary
sheet hand-carried for sign-off.
10. The signed-off original of the estimate summary shall be returned to
the Principal Estimator for Estimating's secure files.
I. ESTIMATE REVIEW AND APPROVAL LEVELS
Review and approvals including sign-off are required for any estimate above
the dollar amounts shown.
Proposal, Product
VP
VP Project
Project Technology Project
Operations
Manager
VP/Dir.
Mgmt.
Review
Levels
Proposal
(1)
Reimbursable
All
(3)
Fixed Price
All
(3)
$250K(4)
All
(4)
(3)(5)(10)
$1MM
All
VP
Sr. VP
Sales/Director
Operations (Review Only)
(8)
Operations Review
Required (7)
$20MM(7)
$5MM
(7)
$40MM(7)
All
$20MM
All
(7)
(Lump Sum)
Non Binding /
Indicative
Capital Cost
All
All
(3)
(4)
All
$50MM(7)(11) $100MM(7)(11)
All
(9)
(6)
Reimbursable
All
$500K
(4)
$15MM
$25MM(11)
$50MM
Note
(12)
Fixed Price
(Lump Sum)
All
$250K
(4)
$5MM
$10MM(11)
$20MM
Note
(12)
NOTES:
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
Fixed rate and Firm Unit Price Projects are considered Fixed Price
Projects (Not Reimbursable) for review thresholds.
(11)