Professional Documents
Culture Documents
I. INTRODUCTION
In 1981, 1 investigated why some protective relays deenergized an important power transmission line. The first
task was to gather all relevant information. Clues were
available from the daily logs maintained by the power
system operators (also called dispatchers) or from the Supervisory Control And Data Acquisition (SCADA) system
log. In addition, oscillographs located at major transmission
Manuscript received February 27, 1991; revised March 21, 1991.
The author is with the Department of Engineering, University of Idaho,
Moscow, ID.
IEEE Log Number 9101205.
1009
ToNei hboring
tiities
Fig. 1. A diagram of a simplified power system. Note that the generation and loads are grouped
into three separate control areas connected by single transmission lines.
125 VDC
Contact In
Breaker
Conductor lo Conductor
Conductor to Ground
Substation Problems
Failed Breaker
ek
Technology-see
I-
Table 1 Time Error Correction Practices within Three North American Interconnected Power Systems.
1700-2000
+4
2000-2400
$8
+4
ni
I,
Equivalent
Generator
Equivalent
Generator
MU= ~ a u r i n unn
g
ic
Diagram
p-r
to
Fig. 5. Fig. 1 redrawn to show the basic idea of time domain fault
location. For a short circuit fault at the center of the transmission
line, the fault induced pulses would arrive at the substations at the
same time.
VI. DISCUSSION
Because of valid environmental, financial and biological
concerns, new high voltage transmission lines are difficult
to build. On the other hand, society is demanding more
electrical energy. One possibility is that the advanced
control techniques discussed here and in the literature will
allow heavier usage of the existing transmission system. An
issue is whether this can be done without any real loss of
reliability. If there is an incremental loss in reliability, will
the utility industry and society accept this loss of reliability
in exchange for fewer new transmission lines?
The utility industry is interested in the highest degree of
reliability and security. Within many utilities and federal
power agencies the discussion of using earth satellites as
part of power systems operations is guaranteed to start a
spirited debate. There is misunderstanding on this point.
A well designed satellite clock would have an internal
oscillator or other circuitry to "flywheel" over losses in
the synchronizing signal. Present proposals use satellite
receivers to synchronize a measuring unit. The measuring
unit and dedicated high-security control computers would
make any critical power system decisions.
A major advantage to satellite based timekeeping is
saving of limited bandwidth on the utility microwave radio
communications network. The communications network
will be needed for moving data to the centralized control
computers and decisions back to the substations. If the timekeeping network or the communications fails, the control
system must revert to a secure operating mode.
The futuristic concepts discussed here are for the high
voltage transmission systems that are the "super highways"
of our power systems. In early 1991, the cost of a synchronized clock ranges from about $5000 for a GOES unit to
1015
To Equipment
I
I
SubstationsWith No
Microwave Link
SerialPaCilM
I
I
i - -DispatehocContmlCenter
- -- - - - ----- --- -- - -. TO Equipment
I
I
Substafion or Plant
Microwave
Channel
SerialP&
!
Fig. 6. A typical power system millisecond timekeeping network.
just under $10 000 for a GPS unit. It is unlikely that GPS
synchronized measuring units will be installed in lower
voltage substations.
VII. CONCLUSIONS
The accuracy requirements of the power industry are
relatively modest when compared with other applications.
An important consideration is the continuity and availability
of any time and frequency broadcast service. For power
system operations, all components must be available at all
times.
Standardized frequency measurements and millisecond
timekeeping is a proven and accepted part of the operation of many electric utilities. Fault location is gaining
acceptance as a valuable tool. At the present, the estimated
distance to the fault is displayed but not programmed into
automatic control schemes.
The control of electric power systems is a very challenging problem. Microsecond timekeeping networks may
be part of an improvement in network response to large
and small events. It is my experience that our power
systems are operated on the basis of a worst case scenario.
The operating philosophy is: will power system conditions
be satisfactory upon loss of the most critical generator,
transformer, or transmission line? Possibly in the future
system-wide state vectors will aid in improved control. Any
possible move in this direction will be slow and deliberate
because an error in such a control system could put many
people and state officials in the dark.
REFERENCES
[l] R. 0. Bumett, Jr. Field experience with absolute time synchro-
JULY 1991
sients-some
case studies, presented at the Utility Fault and
Disturbance Analysis Conf., Denver, CO, Oct. 8-9, 1989.
J. Roberts and E. 0. Schweitzer, 111, Analysis of event reports,
presented at the Westem Protective Relay Conf., Spokane, WA,
Oct. 24-26, 1989.
L. E. Smith, The remote acquisition and analyzation of power
system disturbance data, presented at the Utility Fault and
Disturbance Analysis Conf., Denver, CO, Oct. 30-31, 1986.
D. S. Kolbenschlag, A step Forward: Automatic SER data
acquisition and analyzation, presented at the Utility Fault and
Disturbance Analysis Conference, Denver, CO, Oct. 1-2, 1987.
R. Orville and H. Songster, The east coast lightning detection
network, IEEE Trans. Power Delivery, vol. PWRD-2, pp.
899-907, July 1987.
J. Whitehead, R. Driggans, TVAs experience with the SUNYA
lightning detection network, IEEE Trans. Power Delivery, vol.
PWRD-5, pp. 2054-2062, Oct. 1990.
R. Henderson, State University of New York at Albany, Jan.
25, 1991, personal communications.
0. I. Elgerd, Electric Energy Systems Theory: An Introduction.
New York: McGraw-Hill, 1971, p. 57.
N. Cohn, Power systems-time and frequency, Leeds and
Northrup Tech. J., no. 7, pp. 3-11, Fall 1969.
North American Electric Reliability Council, Area interchange
error survey training document, Princeton, NJ, Jan. 1, 1989.
T. Kennedy, S. H. Hoyt, and C. F. Abell, Variable non-linear
tie-line frequency bias for interconnected systems control,
IEEE Trans. Power Syst., vol. PWRS-3, pp. 1244-1253, Aug.
1988.
D. M. Benjamin, North American Electric Reliability Council,
Feb. 14 and Mar. 4, 1991, personal communications.
North American Electric Reliability Council, Appendix to operating guide 1.C.-time error correction procedures, Princeton,
NJ, Feb. 1, 1990.
A. G. Phadke, J. S. Thorp, and S. H. Horowitz, Impact of
adaptive protection on power system control, in Proc. Ninth
Power System Computation Conf., Lisbon, Portugal, Aug. 1987.
G. D. Rockefeller, C. L. Wagner, J. R. Linders, K. L. Hicks,
and D. T. Rizy, Adaptive transmission relaying concepts for
improved performance, IEEE Trans. Power Delivery, vol. 3,
pp. 1446-1458, Oct. 1988.
L. M. Olmstead, W. D.Brown, and J. Bleiweis, The blackout:
It all happened in 12 minutes, Elec. World, pp. 67-73, Jan.
24, 1966.
D. N. Ewart, Whys and wherefores of power system blackouts, IEEE Spectrum, vol. 15, no. 4, pp. 36-41, Apr. 1978.
IEEE Task Force on Discrete Supplementary Controls, A
description of discrete supplementary controls for stability,
IEEE Trans. Power App. Syst., vol. PAS-97, pp. 149-165,
Jan./Feb. 1978.
IEEE Working Group on Special Stability Controls, Bibliography on the application of discrete supplementary controls to
improve power system stability, IEEE Trans. Power Syst., vol.
PWRS-2, pp. 474-485, May 1987.
IEEE Working Group on EHV Line Outages, Extra high
voltage line outages, IEEE Trans. Power App. Syst., vol. PAS86, pp. 547-562, May 1967.
IEEE Discrete Supplementary Controls Working Group,
Single-pole switching for stability and reliability, IEEE Trans.
Power Syst., vol. PWRS-1, pp. 25-36, May 1986.
D. J. Hansen, Real time digital encoding and telemetry of key
power system transient quantities, presented at the Western
Protective Relay Conf., Spokane, WA, Oct. 23-25, 1984.
D. J. Hansen, Recent progress on stability margin measurement, presented at the Second Conf. Precise Time and Frequency in Power Systems, Fort Collins, CO, Sept. 28-29, 1987.
H. E. Lokay and V. Burtnyk, Application of under frequency
relays for automatic load shedding, in Stability of Large
Electric Power Systems, R. T. Byerly, E. W. Kimbark, Eds.
New York IEEE Press, 1974, pp. 525-532.
T. E. Dy Liacco, The role of state estimation in power system
operation, presented at the 1982 Engineering and Operating
Computer Forum, Denver, CO, Sept. 20-22, 1982.
A. J. Wood and B. F. Wollenberg, Power Generation, Operation, and Control. New York: Wiley, 1984, pp. 391-436, ch.
12.
G. Missout, J. Bland, G. Bdard, and Y. Lafleur, Dynamic
measurement of the absolute voltage angle on long transmisWILSON TIME AND FREQUENCY IN POWER SYSTEMS
sion lines, IEEE Trans. Power App. Syst., vol. PAS-100, pp.
4428-4434, Nov. 1981.
J. S. Thorp, A. G. Phadke, S. H. Horowitz, and M. M. Begovic, Some applications of phasor measurements to adaptive
protection, IEEE Trans. Power Syst., vol. 3, pp. 791-798, May
1988.
J. Esztergalyos, D. C. Erickson, and J. M. Andres, The application of synchronous clocks for power system fault location,
control, and protection, presented at the Eleventh Annual
Western Protective Relay Conf., Spokane, WA, Oct. 23-25,
1984.
N. Rostamkolai, A. G. Phadke, W. F. Long, and J. S. Thorp,
An adaptive optimal control strategy for dynamic stability
enhancement of A C D C power systems, presented at the
CIGRE A C D C Symp., Boston, MA, Sept. 28-30, 1987.
A. G. Phadke, J. S. Thorp, and N. J. Karimi, Power system
monitoring with state vector measurement, presented at the
Second International Conf. Power System Monitoring, University of Durham, U.K., June 1986.
R. K. Gupta, Z. A. Allaywan, R. B. Stuart, and T. A. Reece,
Steady state voltage instability operations perspective, IEEE
Trans. Power Syst., vol. P W R S J , pp. 1345-1354, NOV.1990.
C. W. Taylor, Voltage stability, part 111: Equivalent system
analysis including generation, dynamics, and undervoltage load
shedding, presented at the Bonneville Power Administration
1990 Engineering Conf., Portland, OR, Mar. 7-8, 1990.
M. M. Begovic and A. G. Phadke, Voltage stability assessment
through measurement of a reduced state vector, IEEE Trans.
Power Syst., vol. 5, pp. 198-203, Feb. 1990.
E. 0. Schweitzer, 111, A review of impedance based fault
locating experience, presented at the Westem Protective Relay
Conf., Spokane, WA, Oct. 25-27, 1988.
T. W. Stringfield, D. J. Marihart, and R. F. Stevens, Fault location methods for overhead lines, AIEE Trans. Paper 57-160,
Aug. 1957.
D.C. Erickson and J. Andres, Automatic fault location using
microtime, Bonneville Power Administration Document No.
AFL-100-01, Portland, OR, May 25, 1982.
J. A. Jodice, Time synchronous end-to end relay testing,
presented at the Second Conf. Precise Time and Frequency in
Power Systems, Fort Collins, CO, Sept. 28-29, 1987.
B. Buxkemper, Future of automated protective relay test
equipment, presented at the Second Conf. Precise Time and
Frequency in Power Systems, Fort Collins, CO, Sept. 28-29,
1987.
K. Wright, Synchronization work at public service company
of Colorado, presented at the Second Conf. Precise Time and
Frequency in Power Systems, Fort Collins, CO, Sept. 28-29,
1987.
G. Missout, PITI applications in power utilities, presented
at the Eighteenth Annual Precise Time and Time Interval
Applications and Planning Meeting, Washington, DC, Dec. 2-4,
1986.
G. Missout and P. Girard, Measurement of bus voltage angle
between Montreal and Sept-Iles, IEEE Trans. Power App. Syst.
vol. PAS-99, pp. 536-539, MarJApr. 1980.
G. Missout, J. BCland, G. BCdard, and Y. Lafleur, Dynamic
measurement of the absolute voltage angle on long transmission lines, IEEE Trans. Power App. Syst., vol. PAS-100, pp.
44284434, Nov. 1981.
G. Missout, J. Btland, P. Lebel, G. Btdard, and P. Bussitres,
Time transfer by IRIG-B time code via dedicated telephone
link, presented at the Thirteenth Annual Precise Time and Time
Interval (PITI) Applications and Planning Meeting, Greenbelt,
MD, Dec. 2 4 1980.
R. 0. Burnett, Jr. Additional developments with the Georgia
Power Time Synchronizing Project for fault recorders and
sequence of events recorders, presented at the Second Conf.
Precise Time and Frequency in Power Systems, Fort Collins,
CO, Sept. 28-29, 1987.
R. E. Wilson, Methods and uses of precise time in power
systems, part two: Centralized and distributed timekeeping networks, submitted to IEEE Power Engineering Society Summer
Power Meeting, San Diego, CA, July 28-Aug. 1, 1991.
C. P. Dalpiaz and D.J. Hansen, High rate telemetry of system
voltage phase angle and other stability related quantities, IEEE
Trans. Power Syst., vol. PWRS-1, pp. 202-206, Aug. 1986.
D. J. Hansen, Jan. 23, 1991, personal communications.
1017
1018
___-