The letter notifies the Engineer that the whole of the Works will be complete and ready for taking over by the Employer in 14 days on a specified date, in accordance with Sub-Clause 10.1 of the contract. It requests the Engineer to make arrangements for the Employer to be prepared and ready to operate and safeguard the Works from the date of taking over. A note provides advice for the Contractor to liaise with the Engineer in advance to address any potential objections and investigate local taking over procedures well before anticipated completion if required by local law.
Original Description:
letter
Original Title
Sub-Clause 10.1 – Taking Over by the Employer - Whole of the Works
The letter notifies the Engineer that the whole of the Works will be complete and ready for taking over by the Employer in 14 days on a specified date, in accordance with Sub-Clause 10.1 of the contract. It requests the Engineer to make arrangements for the Employer to be prepared and ready to operate and safeguard the Works from the date of taking over. A note provides advice for the Contractor to liaise with the Engineer in advance to address any potential objections and investigate local taking over procedures well before anticipated completion if required by local law.
The letter notifies the Engineer that the whole of the Works will be complete and ready for taking over by the Employer in 14 days on a specified date, in accordance with Sub-Clause 10.1 of the contract. It requests the Engineer to make arrangements for the Employer to be prepared and ready to operate and safeguard the Works from the date of taking over. A note provides advice for the Contractor to liaise with the Engineer in advance to address any potential objections and investigate local taking over procedures well before anticipated completion if required by local law.
Application for Taking Over of the Whole of the Works
In accordance with the provisions of Sub-Clause 10.1, we hereby give 14 days
notice that the whole of the Works will be complete and ready for taking over by the Employer on (date). We request you to make arrangements with the Employer, so that he is prepared and ready to operate and safeguard the Works from the date of taking over. Yours etc.
Note: 1. The Contractor should continuously liaise with the Engineer prior to the sending of this letter, so that all potential objections are already dealt with. 2.
In some jurisdictions taking over is achieved by committees
appointed by the Employer in accordance with the local law. The taking over in such circumstances may be prolonged. The procedure is to be investigated well in advance of anticipated completion.
A Contractors Guide to the FIDIC Conditions of Contract, First Edition. Michael D.
Robinson. 2011 John Wiley & Sons, Ltd. Published 2011 by John Wiley & Sons, Ltd.