Design of Underdrain
Categorized under Item 501 of DPWH Standard Specifications.
Things to be considered when designing an underdrain:
The size and number of pipes and its locations of opening should be studied
carefully.
Filter materials should be fine enough so that the adjacent soil will not be
washed-out.
The top of underdrain should be sealed with impervious soil to prevent the
entrance of surface water.
Intercepting drains must extend into the impervious zone.
The pipes are laid with the flow line at least 1.20 meters below the finished
grade and carefully bedded with gravel or filter materials.
Materials
1. Zinc coated corrugated iron or steel pipe (AASHTO M-36)
2. Extra strength and standard strength clay pipe and perforated clay pipe
(AASHTO M-65)
3. Porous concrete (AASHTO M-176)
4. Perforated concrete (AASHTO M-175)
5. Bituminous fiber non-pressure sewer drain and underdrainage pipe system
(AASHTO M-177)
6. Asbestos cement perforated underdrain pipes (AASHTO M-189)
7. Granular backfill filter materials (AASHTO M-6)
Construction Requirements:
Pipe Installation
o Trenches are excavated to the dimension and grades required by the
plan.
o Bedding layer of Granular Backfill: <15cm
o Granular backfill are placed and compacted at the bottom of the
trench.
o Sub-drainage pipes are embedded firmly on the bedding.
Perforated Pipes
o Placed with the perforations downwardly secured joined with
appropriate fitting or bands.
Non-Perforated Pipes
o Laid with the bell end upgrade with open joints wrapped with suitable
material to permit entry of water, or unwrapped as may be specified.
Granular Backfill
o Placed 30cm above the top of the pipe
o Should not be displaced by the covering of open joints
Remainder of Granular Backfill
o Placed and compacted at every after 15 cm layers up to the required
height
Any remaining portion (of the trench) above it (GBM) shall be filled with
either granular or impervious material and thoroughly compacted.
Underdrain Outlet
Blind Drain
6.9
Debris Control