Professional Documents
Culture Documents
co-ordination
K.-H. Week
Indexing terms: Insulators and insulation, Cables and overhead lines, Transmission lines, System protection
Abstract: Certain key principles of insulation coordination quoted from IEC publications are
examined and shown to be sufficient to cover all
voltage stress situations, only if all factors
involved are considered. The complexity of insulation co-ordination is illustrated by examining
cases covering different types and configurations
of insulators, different load stress amplitudes and
shapes, and considering the effects of system
layouts.
1
Introduction
The task of co-ordinating insulation is many sided and
because of this, misunderstandings arise in discussions
within international standardisation organisations such
as the IEC or those with more technical objectives such
as CIGRE. The reasons for these misunderstandings are:
(a) the term 'insulation co-ordination' is not uniformly
understood
(b) the simplifications adopted during the preparation
of standards are not reported and, therefore, often not
known
(c) during the discussion of one particular feature,
others, which may be of greater importance for insulation, are disregarded.
The latter point applies especially to the recent IEE conference entitled 'Lightning and Power Systems'. The conclusions reached from this single event may or may not
lead to consequences for insulation, dependent on
whether other events are more important or not.
Accordingly it is necessary to reconsider the principles
of insulation co-ordination and, in particular, the principles forming the existing insulation co-ordination standards. Furthermore, the importance and applicability of
existing procedures need consideration in the light of
these principles. The aim in this paper is to give an overview, emphasising the lightning stresses but including
also the stresses from other events.
2
Principles
The basic principle of insulation co-ordination is as
denned in IEC Publication 71-1 [1]:
Principle 1
'Insulation co-ordination is the adjustment of the
dielectric strength of an equipment to the voltages at
the equipment in service, so that insulation damage or
impairments are reduced to an economically and operationally acceptable probability level.'
Paper 5139C (P7, S2), received 9th September 1986
The author is with FGH, Postfach 810169, 6800 Mannheim 81, West
Germany
IEE PROCEEDINGS, Vol. 134, Pt. C, No. 2, MARCH 1987
lightning
overvoltage
(a)
(b)
1
transformer
2
busbar
line
temporary
-
overvoltages
switching
-
phase-phase(b)
(tfx(a))
(1.4-1.8)x(a)
system-system (c)
(AC* (a))
insulation
phase-earth (a)
Fig. 1
AC* (a)
lightning
AC* (a)
of the variety existing in all three-phase systems irrespective of their operating voltage range. The horizontal division distinguishes the voltage stresses according to their
origin or duration:
(i) Operating voltage, continuously applied to the
equipment during its lifetime. It is not an overvoltage and
accordingly is not mentioned in the survey of Fig. 1.
(ii) Temporary overvoltages, which are low-frequency
overvoltages with durations longer than one period of
the power frequency voltage. The events which can lead
to such overvoltages are earth faults and load rejection,
but also other events such as resonance phenomena can
be of importance.
(iii) Switching overvoltages are transient overvoltages of short duration (less than 1 period of the
power frequency voltage) which arise from circuit
breaker or disconnector operations or from earth faults.
145
146
insulation type
'A safety factor has to be applied to the required withstand voltage in service to obtain the required (rated)
withstand voltage during a test, if unknown deviations
between the two have to be expected.'
Reasons for such deviations can be
(i) dispersion in production
(ii) contaminations during the erection on site (GIS)
(iii) aging of liquid and solid insulation
(iv) parallel insulation etc.
Usually a safety factor of 1.15 is sufficient, but higher
factors are also discussed for GIS, for which suitable
factors largely depend on the test adopted on site.
Apart from the inaccuracies in the determination of
the overvoltages, this definition is the same as that of the
'conventional safety factor' in IEC Publication 71-1. The
'statistical safety factor' also defined in this document is
not a safety factor, but a ratio of the 90% withstand
voltage of the insulation to the 2% overvoltage giving a
specified risk of insulation failure. It is based on the
assumption that the statistical variations of both overvoltage and insulation strength are known with sufficient
accuracy.
In the application guide IEC Publication 71-2 [2] the
ratio of the 90% withstand voltage to the protective level
of the protection device is also called a safety factor. Here
the overvoltage at this device is compared with the withstand voltage of apparatus which may be located far
away. The differences between the various definitions of a
'safety factor' in these standards have to be clarified in
their future revisions.
How the rated withstand voltages standardised today
have been derived and on what background assumptions
are explained in Fig. 3. This is a repetition of Fig. 2 as far
as overvoltages and withstand voltages required in
service are concerned. Applying the safety factor to these
withstand voltages, the required withstand voltages
during the test are obtained (squares).
In their principle voltage-amplitude/duration characteristic three types of insulation exist:
Type A: Insulation having a fiat characteristic at long
durations and a more or less pronounced increase at
short duration voltages. Typical representatives are gas
insulation including short air clearances. They are in
IEE PROCEEDINGS, Vol. 134, Pt. C, No. 2, MARCH 1987
lus
voltage duration
Fig. 3
Required voltages, rated withstand voltages, and safety factors
for various types of insulation
O
D
A
->
required voltages
rated withstand voltages
safety factors
Principle 5
'The lightning-impulse withstand voltage has to cover
also all voltage stresses between phases and between
systems, if no special tests for these stresses are introduced.'
-12-
Procedures
According to Principle 1 of insulation co-ordination, suitable procedures have to guarantee an acceptably low risk
of insulation failure in service. Owing to this requirement
only a probabilistic procedure seems to be applicable.
However, every statistical value has to be considered with
confidence and uncertainties in the data used in the
determination of the risk have to be remembered when
deriving the consequences from the result.
To demonstrate the influence of the many parameters
involved, the insulation co-ordination of a GIS connected
to an overhead line is carried out below for lightning
overvoltages as an example [4]. The dimensions and
necessary data are given in Figs. 4 and 5.
tower -^
number 8
Fig. 4
The most complete procedure is the so called 'statistical procedure'. Besides the statistical variation of the
lightning-flash data its most important feature is the
travelling-wave calculation of substation and overhead
line together. The steps in this procedure and the sensitive parameters involved are given in Fig. 6.
The procedure starts with assumptions about the
lightning flash. Here, in particular, the questions where
and how frequently it occurs are not sufficiently considered: usually it is assumed that the lightning flashes
are distributed homogeneously over the area and randomly in time. The relevant quantity is the ground-flash
density; in the example this is 4/km2. These assumptions
are simplifications, the justification of which is not yet
sufficiently proved. Besides the fact that the overhead line
may be situated in an area with a lightning activity substantially deviating from the average, there is a large difference between the assumption of randomness e.g. 1
148
Fig. 5
The importance of subsequent strokes is not completely investigated. Circuit-breaker failures during
thunderstorms seem to indicate that they may occur
after a shielding-failure flashover of the line insulation
has been cleared by this breaker. For insulation coordination such effects are important, since the openbreaker situation may represent a very unfavourable
condition, even if it is only temporary.
The next step in the procedure is the assumption for
the parameters of the first stroke, which determine the
location of the struck point. The most important parameters are polarity, current amplitude, charge in the lightning channel and current steepness. Since most
downward flashes have negative polarity, the stroke
parameters and the applicability of models are supported
by actual line observations only for this polarity. An
open question is how to deal with positive flashes.
The models to determine the struck point were also
widely discussed during the conference. Without going
into details a model dependent only on the line geometry
has been used as the example.
If the stroke hits the tower of the earthwire, the result
'back flashover or not' is strongly influenced by the
assumption referring to the tower footing impedance and
particularly to its current dependence. For this, generally
applicable relations have not yet been found, although
the number of back flashovers predicted may vary by
orders of magnitude with the adopted representation of
this impedance. On the other hand, another important
factor, the flashover characteristic of the overhead-line
insulation, seems to be sufficiently well known [5].
Up to this point the procedure is similar to that for
the determination of the overhead-line performance.
From here it deviates. For the insulation co-ordination
of the substation, the overvoltage at the struck point
is of primary in erest. As opposed to overhead-line performance, shielding failures, which do not cause a flashover of the line insulation, have also to be considered,
especially when the energy stress of the surge arrester in
the substation is included.
IEE PROCEEDINGS,
lightning flash:
where,how frequent?
how many strokes?
J_
prospective parameters
of the first stroke
overvoltage in
the substation
v/////////////////y/y//////////////////^^^
tower footing impedance
frequency and current dependence
Fig. 6
AOOOr
V%
1
3000
s...
2000
i
^iii)
1000
x> (II)
(i) ^ - ^
2000
2000
1000
3000
l.m
=> 1000
Fig. 7
a Corona
b Pulse shape
c Overvoltage-steepness/travel-distance characteristic
(i) single conductor: 23.6 mm diameter, U = 850 kV
(ii) single conductor: 23.6 mm diameter, U = 1700 kV
(iii) conductor bundle 4 x 22.4 mm diameter, U = 1500 kV
149
a o.oi
0.005
1200kV
-1500
, UOOkV
1
1
u
1
L
-1000
D
350
-500
10
-1500 -1000 -1
3
" ^ .
^ ^ ^
-500-
10
t.HS
b
-1500 -
-1000 -500-
10
Fig. 8
Examples of overvoltage shapes
a At struck point
b After 1000 m
c In substation
950
X.m
1550
Fig. 9
Back-flashover and overvoltage rate in the substation against
tower number
back-flashover rate
overvoltage rate
(a) Due to good substation earthing, no back flashovers occur at the first tower and dangerous overvoltages
due to close lightning are thus avoided. The towers
further along the line then have a constant backflashover rate of 0.0125 per tower per year. This means
that a 100 km long line containing 330 towers has a
back-flashover rate of about 4 per year.
(b) Not all back flashovers cause high overvoltages in
the substation. Even for back flashovers close to the
station (towers 2 and 3) only one third cause overvoltages
higher than 1200 kV. For the further towers this portion
decreases due to the effect of corona. It is zero after
approximately 1.5 km.
The latter observation indicates that for the insulation
co-ordination of substation equipment only the lightning
activity and the line parameters close to the substation
are important, when any protection device is connected
to the line entrance. Averages such as average line performance or average ground-flash density, therefore, may
lead to incorrect results, a problem which has already
been mentioned.
The total rate at which a given voltage value is
exceeded in the substation is the sum of all individual
tower rates. The rate that a value of 1200 kV is exceeded
is
r (1200 kV) = 0.014/year
and
r (1400 kV) = 0.005/year
It is more convenient to use the mean time between
voltage return MTBV, which is the inverse of the overvoltage rates
MTBV (1200 kV) = 70 years
and
MTBV (1400 kV) = 200 years
1EE PROCEEDINGS,
!1
200
Fig. 1 0
above
400
Um.kV
600
800
line
substation
Conclusions
The conclusions will be drawn for an example: the traditional design of power transformers in a 132 kV system
shall be based on a rated power-frequency withstand
voltage of 275 kV and a rated lightning-impulse withstand voltage of 650 kV according to IEC Publication
151
76-3 [9]. These values are based on conventional protection devices. The development of modern metal-oxide
arresters with remarkably low protection levels suggests a
reconsideration of insulation co-ordination.
It is a common assumption that lightning overvoltages
are predominant in this voltage range. Therefore, extensive investigations are carried out with the result that for
metal-oxide arresters, with their lightning protective level
of 280 kV, lightning overvoltages of 370 kV occur at the
transformers with a sufficiently low risk. According to
Principle 3, a safety factor of 1.15 is applied, resulting in a
required lightning-impulse withstand voltage of 425 kV.
Thus the new transformers shall have a rated lightningimpulse withstand of 450 kV and a rated powerfrequency withstand voltage of 185 kV [9]. The
protective ratio of 1.6 resulting from these values is in
agreement with those for which good service experience
has been obtained.
However, Principle 1 means that not only lightning
overvoltages but all voltage stresses have to be considered and, in this case, especially switching overvoltages. From system measurements it is known that the
highest phase-to-earth switching overvoltages at the
transformer are 2.6 p.u., i.e. 305 kV. Between phases these
overvoltages were at maximum, 460 kV, i.e. 1.5 times
higher.
The new protection limits the phase-to-earth switching
overvoltages to 230 kV. It has, however, nearly no effect
on the phase-to-phase overvoltage, since these can have
equal amplitudes and opposite polarity resulting in 2
times 230 kV, i.e. 460 kV. With the safety factor of 1.15,
the required switching-impulse withstand voltages are
265 kV phase-to-earth and 530 kV between phases.
The consequences now depend on the decision on
whether single-phase or three-phase transformer units are
installed. If single-phase transformers are used, the rated
power-frequency withstand voltage of 185 kV, i.e. 262 kV
peak, indeed covers the required switching-impulse withstand voltage phase-to-earth of 265 kV.
References
1 'Insulation co-ordination, Part 1: terms, definitions, principles and
rules'. IEC Publication 71-1, 1976, 6th edn.
2 'Insulation co-ordination, Part 2: application guide'. IEC Publication
71-2, 1976, 2nd edn.
3 'Insulation co-ordination, Part 3: phase-to-phase insulation coordination. Principles, rules and application guide'. IEC Publication
71-3, 1982, 1st edn.
4 HILEMAN, A.R., and WECK, K.-H.: 'Insulation co-ordination and
testing of GIS. Part 1: practical methods for GIS insulation coordination'. SC 33 Colloquium, Edinburgh, UK, 1983
5 BALDO, G., PIGINI, A., and WECK, K.-H.: 'Non-standard lightning impulse strength'. SC 33 Colloquium, Rio de Janeiro, Brazil,
1981
6 WAGNER, C.F., CROSS, I.W., and LLOYD, B.L.: 'High voltage
tests on transmission lines', Trans. Amer. Inst. Electr. Eng., 1954,
PAS-73, pp. 196-209
7 INOUHE, A.: 'High-voltage travelling waves with corona discharge
on bundled conductors'. IEEE winter meeting, 1976, Paper A 78180-3
8 CIGRE SC 23: 'Insulation characteristics of substations with a
nominal voltage up to 765 kV, Electra, 1975, 39, pp. 31-46
9 'Power transformers, Part 3: insulation levels and dielectric tests'.
IEC Publication 76-3, 1st edn.
Erratum
MENON, S.G. and RAO, B.B.V.R.: 'Planning of distribution systems in developing countries', IEE Proc. C,
Gen. Trans. & Distrib., 1986, 133, (7), pp. 384-388
In section 9 (p. 387), in the subsection 'Consumption
levels', the units for electricity consumption should be
'kWh/month' and not 'kWh' as stated.
In the subsection 'Consumption growth' (p. 387), on the
second and third lines 'variation' should read 'elasticity'.
5231C
152