You are on page 1of 99

FINAL SUMMARY BILL OF QUANTITY

ITEM NO.

COST PLANT

SUMMARY

AMOUNT

4.00 BILL NO. 1 PRELIMINARIES Rp.

188,000,000.00

5.00 BILL NO. 2 RECEPTIONIST Rp.

1,079,248,353.19

6.00 BILL NO. 3 GYMNASIUM Rp.

495,605,211.00

7.00 BILL NO. 4 SPA Rp.

263,412,659.75

8.00 BILL NO. 5 SHOP Rp.

354,461,149.25

9.00 BILL NO. 6 TREATMENT PAVILLION Rp.

1,531,456,853.00

10.00 BILL NO. 7 MANAGER'S RESIDENCE Rp.

1,062,564,365.44

11.00 BILL NO. 8 CHEF'S RESIDENCE Rp.

1,062,564,365.44

12.00 BILL NO. 9 BUILDING STRUCTURE Rp.

1,289,785,835.00

13.00 BILL NO. 10 TENNIS COURT Rp.

741,610,921.65

14.00 BILL NO. 11 ROAD WAY Rp.

618,385,068.00

15.00 BILL NO. 12 LANDSCAPE Rp.

554,140,599.40

16.00 BILL NO. 13 MAIN M/E/P Rp.

1,371,701,000.00

TOTAL SUMMARY Rp.

10,612,936,381.11

ROUNDED Rp.

10,612,936,000.00

PT. NUSANTARA ISLAND RESORT

FINAL SUMMARY - 1

AMANKILA STAGE 2 PROJECT

AREA : 4.00 BILL NO. 1 PRELIMINARY

DESCRIPTION

COST PLAN
AMOUNT

4.1.0 CONDITIONS OF TENDERING


4.1.1 Preparation and Submission of Tenders
4.1.2 Surat Ijin Usaha Jasa Konstruksi
4.1.3 Tenders to visit Site
4.1.4 Area for the Works
4.1.5 Use of the Site
4.1.6 Alterations to text
4.1.7 Tendered Amount
4.1.8 Tenders
4.2.0 PRELIMINARY PARTICULARS
4.2.1 Definitions
4.2.2 Description of the Works
4.2.3 Site of the Works
4.2.4 Possession of the Site
4.2.5 Contract Period
4.3.0 CONTRACT PARTICULARS
4.3.1 The Contract Documents
4.3.2 Conditions of Contract
4.3.3 Appendix to Conditions of Contract
4.3.4 Completion of the Contract Works
4.3.5 Practical Completion
4.3.6 Liquidated and Ascertained Damages for Non completion
4.3.7 Programmed of Work
4.3.8 Approval of Programmed
4.3.9 Method of Measurement
4.3.10 Contractors claims for extras and extensions of time
4.3.11 Taxes and Customs Duties
4.3.12 Specification
4.3.13 Discrepancies
4.3.14 The Contract Sum
4.3.15 Fixed Price Contracts

PT. NUSANTARA ISLAND RESORT

4.00 BILL NO. 1 - 2

AMANKILA STAGE 2 PROJECT

AREA : 4.00 BILL NO. 1 PRELIMINARY

DESCRIPTION
4.3.16 Variations
4.3.17 Pricing of Preliminaries
4.3.18 Contingency Sum
4.3.19 Tender Drawings
4.3.20 Surety Bond
4.3.21 Contractors address
4.3.22 Payments to the Contractor
4.3.23 Assignment or Sub-Letting
4.3.24 Insurance of the Works and Public Liability Insurance
4.3.25 Insurance of the Works
4.3.26 Public Liability Insurance
4.3.27 Employer not Liable for Workmen Compensation
4.3.28 Contractor to Insure Workmen
4.3.29 Remedy of Failure to Insure
4.3.30 Contractor to give Notice of Injury
4.3.31 Fluctuations in Exchange Rates

COST PLAN
AMOUNT

15,000,000.00

10,000,000.00

5,000,000.00

4.4.0 GENERAL MATTERS


4.4.1 Site Management and Establishment Costs
4.4.2 Plant, Tools, Materials, Labor etc
4.4.3 Labor on Costs
4.4.4 Working Hours, Rates of Wages etc
4.4.5 Overtime
4.4.6 Contractors Employees
4.4.7 Workmen Living on Site
4.4.8 Safety, Health and Welfare of Workpeople
4.4.9 Report to Supervisor
4.4.10 Contractors Weekly Site Meetings
4.4.11 Site Instructions
4.4.12 Visitors
4.4.13 Permits and Fees
4.4.14 Drawings
4.4.15 Setting out the Works
4.4.16 Dimensions
4.4.17 Samples and Prototypes
4.4.18 Testing of Materials
4.4.19 Safeguarding the Works

PT. NUSANTARA ISLAND RESORT

4.00 BILL NO. 1 - 3

50,000,000.00

15,000,000.00
15,000,000.00
10,000,000.00
5,000,000.00

AMANKILA STAGE 2 PROJECT

AREA : 4.00 BILL NO. 1 PRELIMINARY

DESCRIPTION
4.4.20 Maintenance and Protection of existing roads, footpaths, fences,
etc
4.4.21 Protection of private and Public Services
4.4.22 Protection of adjoining Property
4.4.23 Progress Photographs
4.4.24 Safety Helmets and Protective Clothing
4.4.25 Restricted use of the Site
4.4.26 Advertisements
4.4.27 Telephones
4.4.28 Water
4.4.29 Lighting and Power
4.4.30 Fire Protection
4.4.31 Defects Liability Period
4.4.32 Making Good Defects
4.4.33 Cartage of Materials to the Site and Removal of Spoil and
Surplus materials
4.4.34 Limiting Disturbances
4.4.35 Settlements for Nuisance

COST PLAN
AMOUNT
2,500,000.00

2,500,000.00
5,000,000.00

5,000,000.00
5,000,000.00
10,000,000.00
2,000,000.00

10,000,000.00

4.5.0 TEMPORARY WORKS


4.5.1 Temporary Access
4.5.2 Temporary Buildings
4.5.3 Sitting of Temporary Structures
4.5.4 Contractors Storage Sheds
4.5.5 Contractors Site Office
4.5.6 Removal of Temporary Structures Plant and equipment
4.5.7 Temporary Screens and Safety Netting
4.5.8 General Scaffolding and Staging
4.5.9 Shoring, Propping and Strutting
4.5.10 Protection of the Work
4.5.11 Removal of Rubbish

1,000,000.00

5,000,000.00
5,000,000.00

5,000,000.00

5,000,000.00

4.6.0 PREAMBLES FOR ALL TRADES


4.6.1 Notes
4.6.2 Abbreviation
4.6.3 Definitions

PT. NUSANTARA ISLAND RESORT

4.00 BILL NO. 1 - 4

AMANKILA STAGE 2 PROJECT

AREA : 4.00 BILL NO. 1 PRELIMINARY


COST PLAN
AMOUNT

DESCRIPTION
4.6.4 Generally
4.6.5 Method of Measurement
4.6.6 Working Space
4.6.7 Rates to Include

4.00 BILL NO. 1 PRELIMINARY

188,000,000.00

To Final Summary

PT. NUSANTARA ISLAND RESORT

4.00 BILL NO. 1 - 5

AMANKILA STAGE 2 PROJECT

AREA

: 5.00 BILL NO. 2 RECEPTIONIST

ITEM NO.

DESCRIPTION

UNIT

QTY.

M2

462.00

COST PLAN
RATE
AMOUNT

PREPARATION WORK
1 Site clearance and soil stripping

10,000.00

Sub Total
II

4,620,000.00

SOIL AND SANDS


1 Excavation to building level

M3

325.60

25,000.00

8,140,000.00

2 Ditto to foot foundation

M3

240.00

25,000.00

6,000,000.00

3 Ditto to river stone strip foundation

M3

185.00

25,000.00

4,625,000.00

4 Compacted sand bed 5 cm to river stone strip foundation

M3

18.50

88,600.00

1,639,100.00

5 Ditto to under concrete slab Reception Ground floor

M3

29.15

88,600.00

2,582,690.00

6 Polyethelane sheet damp proof 0.5 mm bed to concrete M2


slab Reception Ground floor on level

291.50

7,500.00

2,186,250.00

7 Anti termite to soil equal to Lentrex 400 EC on building M2


area

462.00

25,000.00

11,550,000.00

Sub Total
III

4,620,000.00

36,723,040.00

CONCRETE
1 Pour concrete K225 to Foot foundation as indicated in M3
drawing and specification.

17.01

1,500,000.00

25,515,000.00

2 Ditto to Sloof beam as indicated in drawing and M3


specification.

14.80

1,650,000.00

24,420,000.00

3 Ditto to Column

M3

16.20

1,750,000.00

28,350,000.00

4 Ditto to Beam

M3

24.98

2,250,000.00

56,193,750.00

PT. NUSANTARA ISLAND RESORT

5.00 BILL NO. 2 - 6

AMANKILA STAGE 2 PROJECT

AREA

: 5.00 BILL NO. 2 RECEPTIONIST

M3

69.30

COST PLAN
RATE
AMOUNT
1,750,000.00
121,275,000.00

6 Pour concrete K175, 8 Cm thickness c/ with reinforcement M3


steel bars dia. 8-20 single layer and formwork to concrete
slab Ground floor

23.32

1,100,000.00

25,652,000.00

7 Water proofing coating c/w wire mesh and sloping plaster M2


to Toilet floor

54.33

90,000.00

4,889,250.00

ITEM NO.

DESCRIPTION

UNIT

5 Ditto to concrete slab 1 st floor

QTY.

8 Ditto to Lotus Pond

M2

235.42

90,000.00

21,187,890.00

9 Cementitius water proofing with 2 M hight to Toilet wall

M2

176.40

35,000.00

6,174,000.00

Sub Total
IV

313,656,890.00

MASONRY
1 Broken river stone masonry with mortar 1pc: 3 sand to M3
strip stone foundation as mentioned in drawing

77.81

236,388.00

18,392,168.34

2 Half brick masonry to with mortar 1pc: 4 sand to wall

M2

443.70

62,604.00

27,777,394.80

3 One brick masonry to with mortar 1pc: 4 sand to wall

M2

198.00

125,208.00

24,791,184.00

Sub Total
V

PLASTER
1 Plaster 1pc: 5 sand as indicated in drawing to 1 st floor M2
wall inside

207.00

17,895.00

3,704,265.00

2 Ditto to Ground floor wall inside

M2

227.70

17,895.00

4,074,691.50

3 Plaster 1pc: 5 sand as indicated in drawing to 1 st floor M2


wall outside

96.00

17,895.00

1,717,920.00

Sub Total
VI

70,960,747.14

9,496,876.50

ROOF

PT. NUSANTARA ISLAND RESORT

5.00 BILL NO. 2 - 7

AMANKILA STAGE 2 PROJECT

AREA

: 5.00 BILL NO. 2 RECEPTIONIST

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

1 Bingkirai timber profile expose to Trusses c/w other M3


accessories as described in drawing and specification

14.20

3,660,000.00

51,972,000.00

2 Bamboo rafter for thatched roof c/w rope as described in M2


drawing and specification

171.00

30,000.00

5,130,000.00

3 Thatch roof ties by "Ate rope" as described in drawing and M2


specification

171.00

75,000.00

12,825,000.00

4 Thatch ridge roof as described in drawing and specification M1

35.00

52,500.00

1,837,500.00

5 Bingkirai timber 1st eave board 6/15 as described in M1


drawing and specification

50.00

65,880.00

3,294,000.00

6 Bingkirai timber 2nd eave board 6/15 as described in M1


drawing and specification

54.00

65,880.00

3,557,520.00

7 Bingkirai timber tatab 3/12 as described in drawing and M1


specification

54.00

50,000.00

2,700,000.00

Sub Total
VII

81,316,020.00

CEILING
1 Gypsum board 9 MM thickness c/w bingkirai timber frame, M2
hanger and galvanized nails (screw) as indicated in
drawing and specification to Office Reception

24.25

81,600.00

1,978,800.00

2 Ditto to Store

M2

6.00

81,600.00

489,600.00

3 Ditto to Ground Store

M2

19.60

81,600.00

1,599,360.00

4 Ditto to Plant Room

M2

7.70

81,600.00

628,320.00

5 Ditto to Housekeeping

M2

21.08

81,600.00

1,720,128.00

PT. NUSANTARA ISLAND RESORT

5.00 BILL NO. 2 - 8

AMANKILA STAGE 2 PROJECT

AREA

: 5.00 BILL NO. 2 RECEPTIONIST

M2

24.96

COST PLAN
RATE
AMOUNT
81,600.00
2,036,736.00

7 Bingkirai timber lumbrisering 1/12 cm as described in M2


drawing to Change Room and Toilet

33.64

142,200.00

4,783,608.00

8 Ditto to Corridor Outside

M2

76.80

142,200.00

10,920,960.00

9 Gypsum board weather proof 9 MM thickness c/w bingkirai M2


timber frame, hanger and galvanized nails (screw) as
indicated in drawing and specification to Staff Toilet

11.78

110,400.00

1,300,512.00

10 Bingkirai timber cornice profile as described in drawing to M1


Office

24.00

15,000.00

360,000.00

11 Ditto to Store

M1

10.00

15,000.00

150,000.00

12 Ditto to Ground Store

M1

23.80

15,000.00

357,000.00

13 Ditto to Plant Room

M1

10.20

15,000.00

153,000.00

14 Ditto to Housekeeping

M1

19.80

15,000.00

297,000.00

15 Ditto to Corridor Inside

M1

30.90

15,000.00

463,500.00

16 Ditto to Corridor Outside

M1

66.40

15,000.00

996,000.00

17 Ditto to Change Room and Toilet

M1

62.60

15,000.00

939,000.00

18 Ditto to Staff Toilet

M1

25.60

15,000.00

384,000.00

ITEM NO.

DESCRIPTION

UNIT

6 Ditto to Corridor Inside

QTY.

Sub Total
VIII

29,557,524.00

FLOOR
1 Polished Palimanan stone 40x40 cm as indicated in M2
drawing to Reception

33.69

193,403.00

6,515,263.56

2 Ditto to Pre treatment Lounge

30.25

193,403.00

5,850,440.75

PT. NUSANTARA ISLAND RESORT

M2

5.00 BILL NO. 2 - 9

AMANKILA STAGE 2 PROJECT

AREA

: 5.00 BILL NO. 2 RECEPTIONIST

M2

43.50

COST PLAN
RATE
AMOUNT
193,403.00
8,413,030.50

3 Vinyl 40x40 cm as indicated in drawing and specification to M2


Office

20.81

150,000.00

3,121,875.00

M2

6.00

150,000.00

900,000.00

5 Polished Terrazzo pour in situ as indicated in drawing c/w M2


wire mesh and anti porous coating to Change Room and
Toilet

37.05

129,303.00

4,790,676.15

6 Ditto to Staff Toilet

M2

11.78

129,303.00

1,523,189.34

7 Ditto to Ground Store

M2

18.09

129,303.00

2,339,091.27

8 Ditto to Plant Room

M2

6.75

129,303.00

872,795.25

9 Ditto to Housekeeping

M2

21.08

129,303.00

2,725,707.24

10 Ditto to Corridor Inside

M2

25.30

129,303.00

3,271,365.90

11 Ditto to Corridor Outside

M2

76.80

129,303.00

9,930,470.40

12 Plaster with floor hardener to ME Room 1

M2

26.40

35,000.00

924,000.00

13 Ditto to ME Room 2

M2

42.04

35,000.00

1,471,400.00

14 Teak timber skirting profile as described in drawing to M1


Reception

21.60

44,228.80

955,342.08

15 Ditto to Pre treatment Lounge

M1

15.80

44,228.80

698,815.04

16 Bingkirai timber skirting profile as described in drawing to M1


Ground Store

22.20

15,000.00

333,000.00

ITEM NO.

DESCRIPTION

UNIT

3 Ditto to around building (outside) c/ border

4 Ditto to Store

QTY.

17 Ditto to Plant Room

M1

9.40

15,000.00

141,000.00

18 Ditto to Housekeeping

M1

19.00

15,000.00

285,000.00

19 Ditto to Corridor Inside

M1

25.30

15,000.00

379,500.00

PT. NUSANTARA ISLAND RESORT

5.00 BILL NO. 2 - 10

AMANKILA STAGE 2 PROJECT

AREA

: 5.00 BILL NO. 2 RECEPTIONIST

ITEM NO.

DESCRIPTION

UNIT

20 Ditto to Corridor Outside

QTY.

COST PLAN
RATE
AMOUNT

M1

52.00

15,000.00

780,000.00

21 Polished Terrazzo as indicated in drawing c/w wire mesh M1


and anti porous coating to Skirting Change Room and
Toilet

57.40

45,000.00

2,583,000.00

22 Ditto to Staff Toilet

M1

23.20

45,000.00

1,044,000.00

23 Palimanan stone 40x40 cm c/w facing and caping M2


described in drawing to Lotus Pond

235.42

193,403.00

45,531,127.66

Sub Total
IX

105,380,090.15

DOOR AND WINDOWS


1 Sliding door w/ Teak frames and glass infil c/ Bangkirai Set
jambs, hardware, finishing Lazur DL 350, and concrete
stiffener as indicated in drawing to Type SD 1

4.00

9,500,000.00

38,000,000.00

2 Sliding door w/ Teak frames and Sungkai veneer infil c/ Set


Bangkirai jambs, hardware, finishing Lazur DL 350, and
concrete stiffener as indicated in drawing to Type SD 2

1.00 12,000,000.00

12,000,000.00

3 Ditto to SD 3

Set

2.00

9,500,000.00

19,000,000.00

4 Door w/ Teak frames and Sungkai veneer infil c/ Bangkirai Set


jambs, hardware, finishing Lazur DL 350, and concrete
stiffener as indicated in drawing to Type D 1

15.00

5,000,000.00

75,000,000.00

5 Sliding and fix window w/ Teak frames and Glass infil c/ Set
Bangkirai jambs, hardware, finishing Lazur DL 350, and
concrete stiffener as indicated in drawing to Type SW 1

1.00

5,000,000.00

5,000,000.00

PT. NUSANTARA ISLAND RESORT

5.00 BILL NO. 2 - 11

AMANKILA STAGE 2 PROJECT

AREA

: 5.00 BILL NO. 2 RECEPTIONIST

ITEM NO.

DESCRIPTION

UNIT

6 Window w/ Teak frames and Glass infil c/ Bangkirai jambs, Set


hardware, finishing Lazur DL 350, and concrete stiffener
as indicated in drawing to Type W 1

QTY.
4.00

COST PLAN
RATE
AMOUNT
4,000,000.00
16,000,000.00

Sub Total
X

165,000,000.00

FINISHING WORK
Wall inside
1 Painted to 1 st floor

M2

207.00

18,000.00

3,726,000.00

2 Ditto to Ground floor

M2

227.70

18,000.00

4,098,600.00

3 Polished Terrazzo as indicated in drawing c/w wire mesh M2


and anti porous coating to Change Room and Toilet wall

172.20

129,303.00

22,265,976.60

4 Ditto to Staff Toilet

M2

69.60

129,303.00

8,999,488.80

5 Vinyl skirting as described in drawing to Office

M1

22.40

60,000.00

1,344,000.00

6 Ditto to Store

M1

9.20

60,000.00

552,000.00

7 Woodstain Lazur timber skirting profile to Reception

M1

21.60

25,000.00

540,000.00

8 Ditto to Pre Treatment Lounge

M1

15.80

25,000.00

395,000.00

9 Ditto to Ground Store

M1

22.20

25,000.00

555,000.00

10 Ditto to Plant Room

M1

9.40

25,000.00

235,000.00

11 Ditto to Housekeeping

M1

19.00

25,000.00

475,000.00

12 Ditto to Corridor Inside

M1

25.30

25,000.00

632,500.00

13 Ditto to Corridor Outside

M1

52.00

25,000.00

1,300,000.00

Ceilings

PT. NUSANTARA ISLAND RESORT

5.00 BILL NO. 2 - 12

AMANKILA STAGE 2 PROJECT

AREA

: 5.00 BILL NO. 2 RECEPTIONIST

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT
20,000.00
485,000.00

1 Painted to Office Reception

M2

24.25

2 Ditto to Store

M2

6.00

20,000.00

120,000.00

3 Ditto to Ground Store

M2

19.60

20,000.00

392,000.00

4 Ditto to Plant Room

M2

7.70

20,000.00

154,000.00

5 Ditto to Housekeeping

M2

21.08

20,000.00

421,600.00

6 Ditto to Corridor Inside

M2

24.96

20,000.00

499,200.00

7 Woodstain Lazur DL 350 timber lumbrisering to Change M2


Room and Toilet

33.64

60,000.00

2,018,400.00

8 Ditto to Corridor Outside

M2

76.80

60,000.00

4,608,000.00

9 Painted weatherproof to Staff Toilet

M2

11.78

25,000.00

294,500.00

10 Woodstain Lazur timber cornice profile to Office Reception

M1

24.00

25,000.00

600,000.00

11 Ditto to Store

M1

10.00

25,000.00

250,000.00

12 Ditto to Ground Store

M1

23.80

25,000.00

595,000.00

13 Ditto to Plant Room

M1

10.20

25,000.00

255,000.00

14 Ditto to Housekeeping

M1

19.80

25,000.00

495,000.00

15 Ditto to Corridor Inside

M1

30.90

25,000.00

772,500.00

16 Ditto to Corridor Outside

M1

66.40

25,000.00

1,660,000.00

17 Ditto to Guest Toilet

M1

62.60

25,000.00

1,565,000.00

18 Ditto to Staff Toilet

M1

25.60

25,000.00

640,000.00

Wall Outside

PT. NUSANTARA ISLAND RESORT

5.00 BILL NO. 2 - 13

AMANKILA STAGE 2 PROJECT

AREA

: 5.00 BILL NO. 2 RECEPTIONIST

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT
18,000.00
1,728,000.00

1 Painted to 1 st floor

M2

96.00

2 Paras buah to Columns

Unit

4.00

250,000.00

1,000,000.00

1 Woodstain Lazur expose trusses

M2

171.00

60,000.00

10,260,000.00

2 Ditto to Edge 1 timber

M1

50.00

25,000.00

1,250,000.00

3 Ditto to Edge 2 timber

M1

54.00

25,000.00

1,350,000.00

4 Ditto to tatab timber

M1

54.00

25,000.00

1,350,000.00

Roof

Sub Total
XI

77,881,765.40

FIXED FURNITURE
1 Vanity top table w/ terrazo polished finishing c/ concrete Set
and steel bars as detail in drawing to Change Room and
Toilet

2.00

3,000,000.00

6,000,000.00

2 Ditto to Staff Toilet

2.00

1,500,000.00

3,000,000.00

Set
Sub total

XII

9,000,000.00

SANITARY WARE
1 Under counter lavatory American Standard Ovalyn 21" c/w Set
p-trap, stop valve, and other necessary fittings as indicated
in drawing and specification to Guest Toilet

4.00

1,028,600.00

4,114,400.00

2 Ditto to Staff Toilet

Set

2.00

1,028,600.00

2,057,200.00

3 Toilet bowl Toto C 406 c/w stop valve, bolt, covered, and Set
other necessary fitting to Guest Toilet

2.00

3,882,000.00

7,764,000.00

4 Toilet bowl Toto Euro S trap c/w stop valve, bolt, covered, Set
and other necessary fitting to Staff Toilet

2.00

1,824,000.00

3,648,000.00

PT. NUSANTARA ISLAND RESORT

5.00 BILL NO. 2 - 14

AMANKILA STAGE 2 PROJECT

AREA

: 5.00 BILL NO. 2 RECEPTIONIST

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

5 Floor drain Toto TX 1B or equal approved c/w fitting and Set


other necessary fittings as indicated in drawing and
specification to Guest Toilet

4.00

146,400.00

585,600.00

6 Ditto to Staff Toilet

Set

3.00

146,400.00

439,200.00

7 Paper holder Toto TX 11 c/w other necessary fittings as Set


indicated in drawing and specification to Guest Toilet

2.00

93,600.00

187,200.00

8 Wash Basin Taps Ideal Standard 1897L282 w/ handle Set


Amarilis cover terrazzo sea shell c/ fittings and other
necessary fittings to Guest Toilet

4.00

1,500,000.00

6,000,000.00

9 Wash Basin Taps Toto T 205 c/ fittings and other Set


necessary fittings to Staff Toilet

2.00

120,900.00

241,800.00

Set

2.00

97,500.00

195,000.00

11 Beveled mirror 5 mm with teak timber frame as indicated in Set


drawing to Vanity Guest Toilet

2.00

1,750,000.00

3,500,000.00

12 Ditto to Staff Toilet

Set

2.00

500,000.00

1,000,000.00

13 Combination teak timber towel shelf w/ towel bar refer to Set


Toto TX 4 W c/w other necessary fittings to Change Room

2.00

886,500.00

1,773,000.00

10 Taps Toto T 23B13 complete fittings to Staff Toilet

Sub Total
XIII

31,505,400.00

ELECTRICAL WORK
1 Lighting c/w light, fittings, cable installation, conduit cable, Points
cable gland, 3M rubber insulation, connector and bracket
as indicated in drawing and specification

99.00

350,000.00

34,650,000.00

2 Outlet c/w fittings, cable installation, conduit cable, cable Points


gland, 3M rubber insulation, connector and bracket as
indicated in drawing and specification

37.00

200,000.00

7,400,000.00

PT. NUSANTARA ISLAND RESORT

5.00 BILL NO. 2 - 15

AMANKILA STAGE 2 PROJECT

AREA

: 5.00 BILL NO. 2 RECEPTIONIST

ITEM NO.

DESCRIPTION

UNIT

3 Electric panel 3 phase SDP c/w MCB, ELCB, Busbar, Points


motor protector to 3 phase motor, grounding, connecting,
commissioning test and other necessary fitting as
indicated in drawing and specification to Receptions

QTY.

1.00

COST PLAN
RATE
AMOUNT
7,500,000.00

Sub Total
XIV

49,550,000.00

COMMUNICATION AND COMPUTER WORK


1 Distribution telephone panel box c/w rustproof terminal, Units
recessed type on Building as indicated in drawing and
specification

1.00

200,000.00

200,000.00

2 Computer outlet standard Legrand Mosaic 45 c/w cable Points


installtion, based plate, covered plate, connector and other
supporting material as indicated in drawing and
specification

4.00

300,000.00

1,200,000.00

3 Telephone outlet standard Legrand Mosaic 45 c/w cable Points


installation, based plate, covered plate, connector and
other supporting material as indicated in drawing and
spefication

5.00

300,000.00

1,500,000.00

Sub Total
XV

7,500,000.00

2,900,000.00

MECHANICAL WORK
1 Hot water heater ex. Rheem glass 170 Lt. c/w cable Set
installation, bracket, based, double threads (water mur)
and other necessary fittings

1.00 10,000,000.00

10,000,000.00

2 A/C split ceiling concealed type ex Fujitsu or equal Set


approved c/w cable installation, insulated copper pipe,
insulated drain pipe, P trap on drain pipe, pipe glands,
bracket or based, commissioning test and other necessary
fittings

2.00 30,000,000.00

60,000,000.00

PT. NUSANTARA ISLAND RESORT

5.00 BILL NO. 2 - 16

AMANKILA STAGE 2 PROJECT

AREA

: 5.00 BILL NO. 2 RECEPTIONIST

ITEM NO.

DESCRIPTION

UNIT

3 Exhaust fan 750 CFM ex National or equal c/w cable Set


installation, ducting and other necessary fittings

QTY.
7.00

COST PLAN
RATE
AMOUNT
1,500,000.00
10,500,000.00

Sub Total
XVI

80,500,000.00

PLUMBING WORK
A. Potable and Hot Water Pipe
1 PVC pipe AW class from main pipe potable water to outlet Points
c/ with fitting, bracket and other necessary supporting
material

14.00

300,000.00

4,200,000.00

2 Thermaflex insulated copper pipe for hot water c/w fittings, Points
hanger, bracket and other necessary fittings on water
heater installation

6.00

500,000.00

3,000,000.00

10.00

400,000.00

4,000,000.00

B. Sewerage Pipe
1 PVC pipe AW class for sewerage pipe, c/w all fittings, Points
bracket, hanger, PVC clean out and other necessary
supporting material as indicated in drawing

Sub Total

11,200,000.00

PREPARATION WORK
SOIL AND SANDS
CONCRETE
MASONRY
PLASTER
ROOF
CEILING
FLOOR
DOOR AND WINDOWS
FINISHING WORK
FIXED FURNITURE
SANITARY WARE
ELECTRICAL WORK

4,620,000.00
36,723,040.00
313,656,890.00
70,960,747.14
9,496,876.50
81,316,020.00
29,557,524.00
105,380,090.15
165,000,000.00
77,881,765.40
9,000,000.00
31,505,400.00
49,550,000.00

COLLECTION
I
II
III
IV
V
VI
VII
VIII
IX
X
XI
XII
XIII
PT. NUSANTARA ISLAND RESORT

5.00 BILL NO. 2 - 17

AMANKILA STAGE 2 PROJECT

AREA

: 5.00 BILL NO. 2 RECEPTIONIST

ITEM NO.
XIV
XV
XVI

DESCRIPTION

UNIT

COMMUNICATION AND COMPUTER WORK


MECHANICAL WORK
PLUMBING WORK
5.00 BILL NO. 2 RECEPTION Rp.
To Final Summary

PT. NUSANTARA ISLAND RESORT

5.00 BILL NO. 2 - 18

QTY.

COST PLAN
RATE
AMOUNT
2,900,000.00
80,500,000.00
11,200,000.00
1,079,248,353.19

AMANKILA STAGE 2 PROJECT

AREA

: 6.00 BILL NO. 3 GYMNASIUM

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

CONCRETE
1 Pour concrete K225 to Column

M3

2.56

1,750,000.00

4,480,000.00

2 Ditto to Ring beam

M3

1.68

2,100,000.00

3,528,000.00

Sub Total
II

8,008,000.00

MASONRY
1 Half brick masonry to with mortar 1pc: 4 sand to wall

M2

204.00

62,604.00

12,771,216.00

2 One brick masonry to with mortar 1pc: 4 sand to wall

M2

90.00

125,208.00

11,268,720.00

Sub Total
III

24,039,936.00

PLASTER
1 Plaster 1pc: 5 sand as indicated in drawing to 1 st floor M2
wall inside

249.00

17,895.00

Sub Total
IV

4,455,855.00

4,455,855.00

ROOF
1 Bingkirai timber profile expose to Trusses c/w other M3
accessories as described in drawing and specification

18.25

3,660,000.00

66,795,000.00

2 Bamboo rafter for thatched roof c/w rope as described in M2


drawing and specification

266.70

30,000.00

8,001,000.00

3 Thatch roof ties by "Ate rope" as described in drawing and M2


specification

266.70

75,000.00

20,002,500.00

4 Thatch ridge roof as described in drawing and specification M1

41.00

52,500.00

2,152,500.00

PT. NUSANTARA ISLAND RESORT

6.00 BILL NO. 3 - 19

AMANKILA STAGE 2 PROJECT

AREA

: 6.00 BILL NO. 3 GYMNASIUM

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT
65,880.00
4,150,440.00

5 Bingkirai timber 1st eave board 6/15 as described in M1


drawing and specification

63.00

6 Bingkirai timber 2nd eave board 6/15 as described in M1


drawing and specification

67.00

65,880.00

4,413,960.00

7 Bingkirai timber tatab 3/12 as described in drawing and M1


specification

67.00

50,000.00

3,350,000.00

8 Teak timber profil to Column

36.00

382,320.00

13,763,520.00

M1
Sub Total

122,628,920.00

FLOOR
1 Export quality teak floor boards

M2

108.75

250,000.00

27,187,500.00

2 Export quality teak skirting floor boards

M1

83.00

150,000.00

12,450,000.00

Sub Total
VI

39,637,500.00

DOOR AND WINDOWS


1 Teak frames, Sungkai veneer doors w/ solid edge Set
strippings c/ Bangkirai jambs, hardware, finishing Lazur DL
350, and concrete stiffener as indicated in drawing to Type
SD 1

2.00 14,250,000.00

28,500,000.00

2 Sliding window w/ Teak frames, Glass infil and lattice c/ Set


Bangkirai jambs, hardware, finishing Lazur DL 350, and
concrete stiffener as indicated in drawing to Type SW 1

8.00 10,525,000.00

84,200,000.00

Sub Total
VII

112,700,000.00

FINISHING WORK
Wall inside
1 Mirror 5 mm w/ teak frames

PT. NUSANTARA ISLAND RESORT

M2
6.00 BILL NO. 3 - 20

249.00

112,000.00

27,888,000.00

AMANKILA STAGE 2 PROJECT

AREA

: 6.00 BILL NO. 3 GYMNASIUM

UNIT

QTY.

COST PLAN
RATE
AMOUNT

2 Woodstain Lazur timber floor w/ anti lack

M2

108.75

120,000.00

13,050,000.00

3 Woodstain Lazur timber skirting

M1

83.00

30,000.00

2,490,000.00

1 Paras buah

M2

168.00

85,000.00

14,280,000.00

2 Paras Jogja to Columns

Unit

16.00

350,000.00

5,600,000.00

3 Paras Jogja to Timber column base

Unit

12.00

250,000.00

3,000,000.00

1 Woodstain Lazur expose trusses

M2

266.70

60,000.00

16,002,000.00

2 Ditto to Edge 1 timber

M1

63.00

25,000.00

1,575,000.00

3 Ditto to Edge 2 timber

M1

67.00

25,000.00

1,675,000.00

4 Ditto to tatab timber

M1

67.00

25,000.00

1,675,000.00

5 Ditto to Column timber

M1

36.00

25,000.00

900,000.00

ITEM NO.

DESCRIPTION

Wall Outside

Roof

Sub Total
VIII

88,135,000.00

ELECTRICAL WORK
1 Lighting c/w light, fittings, cable installation, conduit cable, Points
cable gland, 3M rubber insulation, connector and bracket
as indicated in drawing and specification

42.00

350,000.00

14,700,000.00

2 Outlet c/w fittings, cable installation, conduit cable, cable Points


gland, 3M rubber insulation, connector and bracket as
indicated in drawing and specification

30.00

200,000.00

6,000,000.00

PT. NUSANTARA ISLAND RESORT

6.00 BILL NO. 3 - 21

AMANKILA STAGE 2 PROJECT

AREA

: 6.00 BILL NO. 3 GYMNASIUM

ITEM NO.

DESCRIPTION

UNIT

3 Electric panel 3 phase SDP c/w MCB, ELCB, Busbar, Points


motor protector to 3 phase motor, grounding, connecting,
commissioning test and other necessary fitting as
indicated in drawing and specification to Receptions

COST PLAN
RATE
AMOUNT
1.00 15,000,000.00
15,000,000.00

QTY.

Sub Total
IX

35,700,000.00

COMMUNICATION AND COMPUTER WORK


1 Telephone outlet standard Legrand Mosaic 45 c/w cable Points
installation, based plate, covered plate, connector and
other supporting material as indicated in drawing and
spefication

1.00

300,000.00

Sub Total
X

300,000.00

300,000.00

MECHANICAL WORK
1 A/C split ceiling concealed type ex Fujitsu or equal Set
approved c/w cable installation, insulated copper pipe,
insulated drain pipe, P trap on drain pipe, pipe glands,
bracket or based, commissioning test and other necessary
fittings

2.00 30,000,000.00

60,000,000.00

Sub Total

60,000,000.00

CONCRETE
MASONRY
PLASTER
ROOF
FLOOR
DOOR AND WINDOWS
FINISHING WORK
ELECTRICAL WORK
COMMUNICATION AND COMPUTER WORK
MECHANICAL WORK

8,008,000.00
24,039,936.00
4,455,855.00
122,628,920.00
39,637,500.00
112,700,000.00
88,135,000.00
35,700,000.00
300,000.00
60,000,000.00

COLLECTION
I
II
III
IV
V
VI
VII
VIII
IX
X

PT. NUSANTARA ISLAND RESORT

6.00 BILL NO. 3 - 22

AMANKILA STAGE 2 PROJECT

AREA

: 6.00 BILL NO. 3 GYMNASIUM

ITEM NO.

DESCRIPTION

UNIT

6.00 BILL NO. 3 GYMNASIUM Rp.


To Final Summary

PT. NUSANTARA ISLAND RESORT

6.00 BILL NO. 3 - 23

QTY.

COST PLAN
RATE
AMOUNT
495,605,211.00

AMANKILA STAGE 2 PROJECT

AREA

: 7.00 BILL NO. 4 SPA

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

CONCRETE
1 Pour concrete K225 to Column

M3

0.64

1,750,000.00

1,120,000.00

2 Ditto to Ring beam

M3

0.93

1,300,000.00

1,209,000.00

Sub Total
II

2,329,000.00

MASONRY
1 Half brick masonry to with mortar 1pc: 4 sand to wall

M2

112.00

62,604.00

7,011,648.00

2 One brick masonry to with mortar 1pc: 4 sand to wall

M2

66.00

125,208.00

8,263,728.00

Sub Total
III

15,275,376.00

ROOF
1 Bingkirai timber profile expose to Trusses c/w other M3
accessories as described in drawing and specification

6.30

3,660,000.00

23,058,000.00

2 Bamboo rafter for thatched roof c/w rope as described in M2


drawing and specification

123.63

30,000.00

3,708,750.00

3 Thatch roof ties by "Ate rope" as described in drawing and M2


specification

123.63

75,000.00

9,271,875.00

4 Thatch ridge roof as described in drawing and specification M1

29.00

52,500.00

1,522,500.00

5 Bingkirai timber 1st eave board 6/15 as described in M1


drawing and specification

39.00

65,880.00

2,569,320.00

6 Bingkirai timber 2nd eave board 6/15 as described in M1


drawing and specification

43.00

65,880.00

2,832,840.00

7 Bingkirai timber tatab 3/12 as described in drawing and M1


specification

43.00

50,000.00

2,150,000.00

PT. NUSANTARA ISLAND RESORT

7.00 BILL NO. 4 - 24

AMANKILA STAGE 2 PROJECT

AREA

: 7.00 BILL NO. 4 SPA

ITEM NO.

DESCRIPTION

UNIT

8 Teak timber profil to Column

M1

QTY.

COST PLAN
RATE
AMOUNT

18.00

382,320.00

Sub Total
IV

51,995,045.00

FLOOR
1 Polished Terrazzo pour in situ as indicated in drawing c/w M2
wire mesh and anti porous coating

39.25

129,303.00

5,075,142.75

2 Ditto to skirting

44.00

45,000.00

1,980,000.00

M1
Sub Total

7,055,142.75

DOOR AND WINDOWS


1 Teak frames, Sungkai veneer doors w/ solid edge Set
strippings c/ Bangkirai jambs, hardware, finishing Lazur DL
350, and concrete stiffener as indicated in drawing to Type
SD 1

4.00

8,000,000.00

32,000,000.00

2 Sliding window w/ Teak frames, Glass infil and lattice c/ Set


Bangkirai jambs, hardware, finishing Lazur DL 350, and
concrete stiffener as indicated in drawing to Type SW 1

3.00

7,000,000.00

21,000,000.00

3 Window w/ Teak frames, Glass infil and lattice c/ Bangkirai Set


jambs, hardware, finishing Lazur DL 350, and concrete
stiffener as indicated in drawing to Type W

2.00

5,000,000.00

10,000,000.00

Sub Total
VI

6,881,760.00

63,000,000.00

FINISHING WORK
Wall inside
1 Polished Terrazzo pour in situ as indicated in drawing c/w M2
wire mesh and anti porous coating

PT. NUSANTARA ISLAND RESORT

7.00 BILL NO. 4 - 25

132.00

129,303.00

17,067,996.00

AMANKILA STAGE 2 PROJECT

AREA

: 7.00 BILL NO. 4 SPA

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

Wall Outside
1 Paras buah

M2

66.00

85,000.00

5,610,000.00

2 Paras Jogja to Columns

Unit

6.00

350,000.00

2,100,000.00

3 Paras Jogja to Timber column base

Unit

6.00

250,000.00

1,500,000.00

1 Woodstain Lazur expose trusses

M2

123.63

60,000.00

7,417,500.00

2 Ditto to Edge 1 timber

M1

39.00

25,000.00

975,000.00

3 Ditto to Edge 2 timber

M1

43.00

25,000.00

1,075,000.00

4 Ditto to tatab timber

M1

43.00

25,000.00

1,075,000.00

5 Ditto to Column timber

M1

18.00

25,000.00

450,000.00

Roof

Sub Total
VII

37,270,496.00

SANITARY WARE
1 Floor drain Toto TX 1B or equal approved c/w fitting and Set
other necessary fittings as indicated in drawing and
specification to Guest Toilet

4.00

146,400.00

585,600.00

2 Shower head Toto TX 422 S

Set

4.00

882,000.00

3,528,000.00

3 Shower taps Toto TX 419 SC

Set

4.00

882,000.00

3,528,000.00

4 Curtain w/ timber holder

Set

4.00

600,000.00

2,400,000.00

5 Combination teak timber towel shelf w/ towel bar refer to Set


Toto TX 4 W c/w other necessary fittings to Change Room

4.00

886,500.00

3,546,000.00

Sub Total

PT. NUSANTARA ISLAND RESORT

7.00 BILL NO. 4 - 26

13,587,600.00

AMANKILA STAGE 2 PROJECT

AREA

: 7.00 BILL NO. 4 SPA

QTY.

COST PLAN
RATE
AMOUNT

1 Lighting c/w light, fittings, cable installation, conduit cable, Points


cable gland, 3M rubber insulation, connector and bracket
as indicated in drawing and specification

22.00

350,000.00

7,700,000.00

2 Outlet c/w fittings, cable installation, conduit cable, cable Points


gland, 3M rubber insulation, connector and bracket as
indicated in drawing and specification

12.00

200,000.00

2,400,000.00

3 Electric panel 3 phase SDP c/w MCB, ELCB, Busbar, Points


motor protector to 3 phase motor, grounding, connecting,
commissioning test and other necessary fitting as
indicated in drawing and specification to Receptions

1.00

7,500,000.00

7,500,000.00

ITEM NO.
VIII

DESCRIPTION

UNIT

ELECTRICAL WORK

Sub Total
IX

17,600,000.00

COMMUNICATION AND COMPUTER WORK


1 Telephone outlet standard Legrand Mosaic 45 c/w cable Points
installation, based plate, covered plate, connector and
other supporting material as indicated in drawing and
spefication

1.00

300,000.00

Sub Total
X

300,000.00

300,000.00

MECHANICAL WORK
1 Hot water heater ex. Rheem glass 170 Lt. c/w cable Set
installation, bracket, based, double threads (water mur)
and other necessary fittings

2.00 10,000,000.00

20,000,000.00

2 A/C split ceiling concealed type ex Fujitsu or equal Set


approved c/w cable installation, insulated copper pipe,
insulated drain pipe, P trap on drain pipe, pipe glands,
bracket or based, commissioning test and other necessary
fittings

1.00 30,000,000.00

30,000,000.00

Sub Total
PT. NUSANTARA ISLAND RESORT

7.00 BILL NO. 4 - 27

50,000,000.00
AMANKILA STAGE 2 PROJECT

AREA

: 7.00 BILL NO. 4 SPA

ITEM NO.

XI

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

PLUMBING WORK
A. Potable and Hot Water Pipe
1 PVC pipe AW class from main pipe potable water to outlet Points
c/ with fitting, bracket and other necessary supporting
material

4.00

350,000.00

1,400,000.00

2 Thermaflex insulated copper pipe for hot water c/w fittings, Points
hanger, bracket and other necessary fittings on water
heater installation

4.00

500,000.00

2,000,000.00

4.00

400,000.00

1,600,000.00

B. Sewerage Pipe
1 PVC pipe AW class for sewerage pipe, c/w all fittings, Points
bracket, hanger, PVC clean out and other necessary
supporting material as indicated in drawing

Sub Total

5,000,000.00

CONCRETE
MASONRY
ROOF
FLOOR
DOOR AND WINDOWS
FINISHING WORK
SANITARY WARE
ELECTRICAL WORK
PLUMBING WORK
MECHANICAL WORK
PLUMBING WORK

2,329,000.00
15,275,376.00
51,995,045.00
7,055,142.75
63,000,000.00
37,270,496.00
13,587,600.00
17,600,000.00
300,000.00
50,000,000.00
5,000,000.00

7.00 BILL NO. 4 SPA Rp.


To Final Summary

263,412,659.75

COLLECTION
I
II
III
IV
V
VI
VII
VIII
XI
X
XI

PT. NUSANTARA ISLAND RESORT

7.00 BILL NO. 4 - 28

AMANKILA STAGE 2 PROJECT

AREA

: 8.00 BILL NO. 5 SHOP

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

CONCRETE
1 Pour concrete K225 to Column

M3

1.92

1,750,000.00

3,360,000.00

2 Ditto to Ring beam

M3

1.50

1,300,000.00

1,950,000.00

Sub Total
II

5,310,000.00

MASONRY
1 Half brick masonry to with mortar 1pc: 4 sand to wall

M2

176.00

62,604.00

Sub Total
III

11,018,304.00

PLASTER
1 Plaster 1pc: 5 sand as indicated in drawing to 1 st floor M2
wall inside

176.00

17,895.00

Sub Total
IV

11,018,304.00

3,149,520.00

3,149,520.00

ROOF
1 Bingkirai timber profile expose to Trusses c/w other M3
accessories as described in drawing and specification

18.25

3,660,000.00

66,795,000.00

2 Bamboo rafter for thatched roof c/w rope as described in M2


drawing and specification

266.70

30,000.00

8,001,000.00

3 Thatch roof ties by "Ate rope" as described in drawing and M2


specification

266.70

75,000.00

20,002,500.00

4 Thatch ridge roof as described in drawing and specification M1

41.00

52,500.00

2,152,500.00

5 Bingkirai timber 1st eave board 6/15 as described in M1


drawing and specification

63.00

65,880.00

4,150,440.00

PT. NUSANTARA ISLAND RESORT

8.00 BILL NO. 5 - 29

AMANKILA STAGE 2 PROJECT

AREA

: 8.00 BILL NO. 5 SHOP

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT
65,880.00
4,413,960.00

6 Bingkirai timber 2nd eave board 6/15 as described in M1


drawing and specification

67.00

7 Bingkirai timber tatab 3/12 as described in drawing and M1


specification

67.00

50,000.00

3,350,000.00

8 Teak timber profil to Column

48.00

382,320.00

18,351,360.00

M1
Sub Total

127,216,760.00

FLOOR
1 Polished Terrazzo pour in situ as indicated in drawing c/w M2
wire mesh and anti porous coating

96.75

129,303.00

12,510,065.25

2 Ditto to skirting

58.67

45,000.00

2,640,000.00

M1
Sub Total

VI

15,150,065.25

DOOR AND WINDOWS


1 Teak frames, Sungkai veneer doors w/ solid edge Set
strippings c/ Bangkirai jambs, hardware, finishing Lazur DL
350, and concrete stiffener as indicated in drawing to Type
SD

2.00

9,000,000.00

18,000,000.00

2 Sliding window w/ Teak frames, Glass infil and lattice c/ Set


Bangkirai jambs, hardware, finishing Lazur DL 350, and
concrete stiffener as indicated in drawing to Type SW

2.00

8,000,000.00

16,000,000.00

Sub Total
VII

34,000,000.00

FINISHING WORK
Wall inside
1 Sungkai veneer

M2

176.00

250,000.00

44,000,000.00

2 Teak edge stripping

M1

22.00

75,000.00

1,650,000.00

PT. NUSANTARA ISLAND RESORT

8.00 BILL NO. 5 - 30

AMANKILA STAGE 2 PROJECT

AREA

: 8.00 BILL NO. 5 SHOP

ITEM NO.

DESCRIPTION

COST PLAN
RATE
AMOUNT

UNIT

QTY.

1 Paras buah

M2

176.00

85,000.00

14,960,000.00

2 Paras Jogja to Columns

Unit

14.00

350,000.00

4,900,000.00

3 Paras Jogja to Timber column base

Unit

11.00

250,000.00

2,750,000.00

1 Woodstain Lazur expose trusses

M2

266.70

60,000.00

16,002,000.00

2 Ditto to Edge 1 timber

M1

63.00

25,000.00

1,575,000.00

3 Ditto to Edge 2 timber

M1

67.00

25,000.00

1,675,000.00

4 Ditto to tatab timber

M1

67.00

25,000.00

1,675,000.00

5 Ditto to Column timber

M1

48.00

25,000.00

1,200,000.00

Wall Outside

Roof

Sub Total
VIII

90,387,000.00

SANITARY WARE
1 Kitchen zink Toto

Set

1.00

2,500,000.00

2,500,000.00

2 Kitchen zink Taps Toto TR 221 AM

Set

1.00

1,429,500.00

1,429,500.00

Sub Total
IX

3,929,500.00

ELECTRICAL WORK
1 Lighting c/w light, fittings, cable installation, conduit cable, Points
cable gland, 3M rubber insulation, connector and bracket
as indicated in drawing and specification

30.00

350,000.00

10,500,000.00

2 Outlet c/w fittings, cable installation, conduit cable, cable Points


gland, 3M rubber insulation, connector and bracket as
indicated in drawing and specification

16.00

200,000.00

3,200,000.00

PT. NUSANTARA ISLAND RESORT

8.00 BILL NO. 5 - 31

AMANKILA STAGE 2 PROJECT

AREA

: 8.00 BILL NO. 5 SHOP

ITEM NO.

DESCRIPTION

UNIT

3 Electric panel 3 phase SDP c/w MCB, ELCB, Busbar, Points


motor protector to 3 phase motor, grounding, connecting,
commissioning test and other necessary fitting as
indicated in drawing and specification to Receptions

QTY.

1.00

COST PLAN
RATE
AMOUNT
7,500,000.00

Sub Total
X

21,200,000.00

COMMUNICATION AND COMPUTER WORK


1 Telephone outlet standard Legrand Mosaic 45 c/w cable Points
installation, based plate, covered plate, connector and
other supporting material as indicated in drawing and
spefication

2.00

300,000.00

Sub Total
XI

600,000.00

600,000.00

MECHANICAL WORK
1 Hot water heater ex. Rheem glass 170 Lt. c/w cable Set
installation, bracket, based, double threads (water mur)
and other necessary fittings

1.00 10,000,000.00

10,000,000.00

2 A/C split ceiling concealed type ex Fujitsu or equal Set


approved c/w cable installation, insulated copper pipe,
insulated drain pipe, P trap on drain pipe, pipe glands,
bracket or based, commissioning test and other necessary
fittings

1.00 30,000,000.00

30,000,000.00

Sub Total
XII

7,500,000.00

40,000,000.00

PLUMBING WORK
A. Potable and Hot Water Pipe
1 PVC pipe AW class from main pipe potable water to outlet Points
c/ with fitting, bracket and other necessary supporting
material

PT. NUSANTARA ISLAND RESORT

8.00 BILL NO. 5 - 32

2.00

350,000.00

700,000.00

AMANKILA STAGE 2 PROJECT

AREA

: 8.00 BILL NO. 5 SHOP

ITEM NO.

DESCRIPTION

UNIT

2 Thermaflex insulated copper pipe for hot water c/w fittings, Points
hanger, bracket and other necessary fittings on water
heater installation

2.00

COST PLAN
RATE
AMOUNT
500,000.00
1,000,000.00

2.00

400,000.00

QTY.

B. Sewerage Pipe
1 PVC pipe AW class for sewerage pipe, c/w all fittings, Points
bracket, hanger, PVC clean out and other necessary
supporting material as indicated in drawing

800,000.00

Sub Total

2,500,000.00

CONCRETE
MASONRY
PLASTER
ROOF
FLOOR
DOOR AND WINDOWS
FINISHING WORK
SANITARY WARE
ELECTRICAL WORK
COMMUNICATION AND COMPUTER WORK
MECHANICAL WORK
PLUMBING WORK

5,310,000.00
11,018,304.00
3,149,520.00
127,216,760.00
15,150,065.25
34,000,000.00
90,387,000.00
3,929,500.00
21,200,000.00
600,000.00
40,000,000.00
2,500,000.00

8.00 BILL NO. 5 SHOP Rp.


To Final Summary

354,461,149.25

COLLECTION
I
II
III
IV
V
VI
VII
VIII
IX
X
XI
XII

PT. NUSANTARA ISLAND RESORT

8.00 BILL NO. 5 - 33

AMANKILA STAGE 2 PROJECT

AREA

: 9.00 BILL NO. 6 TREATMENT

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

CONCRETE
1 Pour concrete K225 to Column

M3

1.60

1,750,000.00

2,800,000.00

2 Ditto to Ring beam

M3

1.82

1,300,000.00

2,359,500.00

3 Ditto to floor slab

M3

24.78

1,750,000.00

43,370,570.25

4 Water proofing coating c/w wire mesh and sloping plaster M2


to Toilet floor

28.00

90,000.00

2,520,000.00

106.25

35,000.00

3,718,750.00

5 Cementitius water proofing with 2 M hight to Toilet wall

M2

Sub Total
II

54,768,820.25

MASONRY
1 Half brick masonry to with mortar 1pc: 4 sand to wall

M2

198.00

62,604.00

Sub Total
III

12,395,592.00

PLASTER
1 Plaster 1pc: 5 sand as indicated in drawing to 1 st floor M2
wall inside

198.00

17,895.00

3,543,210.00

2 Plaster 1pc: 5 sand as indicated in drawing to 1 st floor M2


wall outside

140.25

17,895.00

2,509,773.75

Sub Total
IV

12,395,592.00

6,052,983.75

ROOF
1 Bingkirai timber profile expose to Trusses c/w other M3
accessories as described in drawing and specification

PT. NUSANTARA ISLAND RESORT

9.00 BILL NO. 6 - 34

11.20

3,660,000.00

40,992,000.00

AMANKILA STAGE 2 PROJECT

AREA

: 9.00 BILL NO. 6 TREATMENT

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT
30,000.00
4,950,000.00

2 Bamboo rafter for thatched roof c/w rope as described in M2


drawing and specification

165.00

3 Thatch roof ties by "Ate rope" as described in drawing and M2


specification

165.00

75,000.00

12,375,000.00

4 Thatch ridge roof as described in drawing and specification M1

32.50

52,500.00

1,706,250.00

5 Bingkirai timber 1st eave board 6/15 as described in M1


drawing and specification

45.00

65,880.00

2,964,600.00

6 Bingkirai timber 2nd eave board 6/15 as described in M1


drawing and specification

49.00

65,880.00

3,228,120.00

7 Bingkirai timber tatab 3/12 as described in drawing and M1


specification

49.00

50,000.00

2,450,000.00

Sub Total
V

68,665,970.00

FLOOR
1 Polished Terrazzo pour in situ as indicated in drawing c/w M2
wire mesh and anti porous coating

90.75

129,303.00

Sub Total
VI

11,734,247.25

11,734,247.25

CEILING
1 Bingkirai timber lumbrisering 1/12 cm as described in M2
drawing to Change Room and Toilet

28.00

142,200.00

3,981,600.00

2 Gypsum board 9 MM thickness c/w bingkirai timber frame, M2


hanger and galvanized nails (screw) as indicated in
drawing and specification to Staff Prep.

5.00

81,600.00

408,000.00

3 Bingkirai timber cornice profil to Change Room and Toilet

M1

42.50

15,000.00

637,500.00

4 Ditto to Staff Prep.

M1

9.00

15,000.00

135,000.00

PT. NUSANTARA ISLAND RESORT

9.00 BILL NO. 6 - 35

AMANKILA STAGE 2 PROJECT

AREA

: 9.00 BILL NO. 6 TREATMENT

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

Sub Total
VII

5,162,100.00

DOOR AND WINDOWS


1 Teak frames, Sungkai veneer doors w/ solid edge Set
strippings c/ Bangkirai jambs, hardware, finishing Lazur DL
350, and concrete stiffener as indicated in drawing to Type
SD 1

1.00

9,000,000.00

9,000,000.00

2 Ditto to SD 2

Set

1.00

8,000,000.00

8,000,000.00

3 Ditto to SD 3

Set

3.00

7,500,000.00

22,500,000.00

4 Ditto to D 1

Set

1.00

5,000,000.00

5,000,000.00

5 Sliding Window w/ Teak frames, Glass infil and lattice c/ Set


Bangkirai jambs, hardware, finishing Lazur DL 350, and
concrete stiffener as indicated in drawing to Type SW 1

2.00

6,500,000.00

13,000,000.00

6 Ditto to W 1

Set

5.00

5,000,000.00

25,000,000.00

7 Ditto to W 2

Set

2.00

3,000,000.00

6,000,000.00

Sub Total
VIII

88,500,000.00

FINISHING WORK
Wall inside
1 Painted wall

M2

198.00

18,000.00

3,564,000.00

1 Woodstain Lazur to ceilings Change Room and Toilet

M2

28.00

60,000.00

1,680,000.00

2 Painted ceilings to Staff Prep.

M2

5.00

20,000.00

100,000.00

3 Woodstain Lazur to cornice Change Room and Toilet

M1

42.50

25,000.00

1,062,500.00

Ceilings

PT. NUSANTARA ISLAND RESORT

9.00 BILL NO. 6 - 36

AMANKILA STAGE 2 PROJECT

AREA

: 9.00 BILL NO. 6 TREATMENT

ITEM NO.

DESCRIPTION

UNIT

4 Ditto to Staff Prep.

QTY.

COST PLAN
RATE
AMOUNT

M1

9.00

25,000.00

225,000.00

1 Painted wall

M2

140.25

18,000.00

2,524,500.00

2 Paras Jogja to Columns

Unit

6.00

350,000.00

2,100,000.00

1 Woodstain Lazur expose trusses

M2

165.00

60,000.00

9,900,000.00

2 Ditto to Edge 1 timber

M1

45.00

25,000.00

1,125,000.00

3 Ditto to Edge 2 timber

M1

49.00

25,000.00

1,225,000.00

4 Ditto to tatab timber

M1

49.00

25,000.00

1,225,000.00

Wall Outside

Roof

Sub Total
IX

24,731,000.00

FIXED FURNITURE
1 Vanity top table w/ terrazo polished finishing c/ concrete Set
and steel bars as detail in drawing to Change Room and
Toilet

2.00

3,000,000.00

6,000,000.00

2 Ditto to Staff Toilet

Set

1.00

2,000,000.00

2,000,000.00

3 Terrazzo pour in situ to Bathtub

Set

1.00

4,500,000.00

4,500,000.00

Sub total
X

12,500,000.00

SANITARY WARE
1 Under counter lavatory American Standard Ovalyn 21" c/w Set
p-trap, stop valve, and other necessary fittings as indicated
in drawing and specification to Guest Toilet

2.00

1,028,600.00

2,057,200.00

2 Ditto to Staff Toilet

1.00

1,028,600.00

1,028,600.00

PT. NUSANTARA ISLAND RESORT

Set
9.00 BILL NO. 6 - 37

AMANKILA STAGE 2 PROJECT

AREA

: 9.00 BILL NO. 6 TREATMENT

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

3 Toilet bowl Toto C 406 c/w stop valve, bolt, covered, and Set
other necessary fitting to Guest Toilet

1.00

3,882,000.00

3,882,000.00

4 Bathtub Taps Ideal Standard 1897L382 w/ handle Amarilis Set


cover terrazzo sea shell c/ fittings and other necessary
fittings to Guest Toilet

1.00

1,845,000.00

1,845,000.00

5 Shower head Toto TX 422 S

Set

1.00

882,000.00

882,000.00

6 Shower taps Toto TX 419 SC

Set

1.00

882,000.00

882,000.00

7 Floor drain Bathtub Toto TB 55 AS or equal approved c/w Set


fitting and other necessary fittings as indicated in drawing
and specification

1.00

1,650,000.00

1,650,000.00

8 Floor drain Toto TX 1B or equal approved c/w fitting and Set


other necessary fittings as indicated in drawing and
specification to Guest Toilet

3.00

146,400.00

439,200.00

9 Paper holder Toto TX 11 c/w other necessary fittings as Set


indicated in drawing and specification to Guest Toilet

1.00

93,600.00

93,600.00

10 Wash Basin Taps Ideal Standard 1897L282 w/ handle Set


Amarilis cover terrazzo sea shell c/ fittings and other
necessary fittings to Guest Toilet

2.00

1,500,000.00

3,000,000.00

11 Wash Basin Taps Toto T 205 c/ fittings and other Set


necessary fittings to Staff Toilet

1.00

120,900.00

120,900.00

12 Beveled mirror 5 mm with teak timber frame as indicated in Set


drawing to Vanity Guest Toilet

2.00

1,750,000.00

3,500,000.00

13 Ditto to Staff Toilet

Set

1.00

500,000.00

500,000.00

14 Combination teak timber towel shelf w/ towel bar refer to Set


Toto TX 4 W c/w other necessary fittings to Change Room

2.00

886,500.00

1,773,000.00

PT. NUSANTARA ISLAND RESORT

9.00 BILL NO. 6 - 38

AMANKILA STAGE 2 PROJECT

AREA

: 9.00 BILL NO. 6 TREATMENT

ITEM NO.

DESCRIPTION

UNIT

QTY.

Sub Total
XI

COST PLAN
RATE
AMOUNT
21,653,500.00

ELECTRICAL WORK
1 Lighting c/w light, fittings, cable installation, conduit cable, Points
cable gland, 3M rubber insulation, connector and bracket
as indicated in drawing and specification

30.00

350,000.00

10,500,000.00

2 Outlet c/w fittings, cable installation, conduit cable, cable Points


gland, 3M rubber insulation, connector and bracket as
indicated in drawing and specification

10.00

200,000.00

2,000,000.00

3 Electric panel 3 phase SDP c/w MCB, ELCB, Busbar, Points


motor protector to 3 phase motor, grounding, connecting,
commissioning test and other necessary fitting as
indicated in drawing and specification to Receptions

1.00

7,500,000.00

7,500,000.00

Sub Total
XII

COMMUNICATION AND COMPUTER WORK


1 Distribution telephone panel box c/w rustproof terminal, Units
recessed type on Building as indicated in drawing and
specification

1.00

200,000.00

200,000.00

2 Computer outlet standard Legrand Mosaic 45 c/w cable Points


installtion, based plate, covered plate, connector and other
supporting material as indicated in drawing and
specification

1.00

300,000.00

300,000.00

3 Telephone outlet standard Legrand Mosaic 45 c/w cable Points


installation, based plate, covered plate, connector and
other supporting material as indicated in drawing and
spefication

2.00

300,000.00

600,000.00

Sub Total
XIII

20,000,000.00

1,100,000.00

MECHANICAL WORK

PT. NUSANTARA ISLAND RESORT

9.00 BILL NO. 6 - 39

AMANKILA STAGE 2 PROJECT

AREA

: 9.00 BILL NO. 6 TREATMENT

ITEM NO.

DESCRIPTION

UNIT

1 Hot water heater ex. Rheem glass 170 Lt. c/w cable Set
installation, bracket, based, double threads (water mur)
and other necessary fittings

COST PLAN
RATE
AMOUNT
1.00 10,000,000.00
10,000,000.00

QTY.

2 A/C split ceiling concealed type ex Fujitsu or equal Set


approved c/w cable installation, insulated copper pipe,
insulated drain pipe, P trap on drain pipe, pipe glands,
bracket or based, commissioning test and other necessary
fittings

1.00 37,500,000.00

3 Exhaust fan 750 CFM ex National or equal c/w cable Set


installation, ducting and other necessary fittings

1.00

1,500,000.00

Sub Total
XIV

37,500,000.00

1,500,000.00

49,000,000.00

PLUMBING WORK
A. Potable and Hot Water Pipe
1 PVC pipe AW class from main pipe potable water to outlet Points
c/ with fitting, bracket and other necessary supporting
material

7.00

300,000.00

2,100,000.00

2 Thermaflex insulated copper pipe for hot water c/w fittings, Points
hanger, bracket and other necessary fittings on water
heater installation

5.00

500,000.00

2,500,000.00

5.00

400,000.00

2,000,000.00

B. Sewerage Pipe
1 PVC pipe AW class for sewerage pipe, c/w all fittings, Points
bracket, hanger, PVC clean out and other necessary
supporting material as indicated in drawing

Sub Total

6,600,000.00

CONCRETE
MASONRY
PLASTER

54,768,820.25
12,395,592.00
6,052,983.75

COLLECTION
I
II
III
PT. NUSANTARA ISLAND RESORT

9.00 BILL NO. 6 - 40

AMANKILA STAGE 2 PROJECT

AREA

: 9.00 BILL NO. 6 TREATMENT

ITEM NO.
IV
V
VI
VII
VIII
IX
X
XI
XII
XIII
XIV

DESCRIPTION

UNIT

ROOF
FLOOR
CEILING
DOOR AND WINDOWS
FINISHING WORK
FIXED FURNITURE
SANITARY WARE
ELECTRICAL WORK
COMMUNICATION AND COMPUTER WORK
MECHANICAL WORK
PLUMBING WORK
TREATMENT 1 UNIT Rp.
9.00 BILL NO. 6 TREATMENT 4 UNIT Rp.
To Final Summary

PT. NUSANTARA ISLAND RESORT

9.00 BILL NO. 6 - 41

QTY.

COST PLAN
RATE
AMOUNT
68,665,970.00
11,734,247.25
5,162,100.00
88,500,000.00
24,731,000.00
12,500,000.00
21,653,500.00
20,000,000.00
1,100,000.00
49,000,000.00
6,600,000.00
382,864,213.25
1,531,456,853.00

AMANKILA STAGE 2 PROJECT

AREA

: 10.00 BILL NO. 7 MANAGER'S RESIDENCE

ITEM NO.

DESCRIPTION

UNIT

QTY.

M2

847.00

COST PLAN
RATE
AMOUNT

PREPARATION WORK
1 Site clearance and soil stripping

10,000.00

Sub Total
II

8,470,000.00

SOIL AND SANDS


1 Excavation to foot foundation

M3

126.00

25,000.00

3,150,000.00

2 Ditto to river stone strip foundation and retaining wall

M3

453.75

25,000.00

11,343,750.00

3 Compacted soil to building level

M3

363.00

44,400.00

16,117,200.00

4 Compacted sand bed 5 cm to river stone strip foundation

M3

18.15

88,600.00

1,608,090.00

5 Ditto to under concrete slab floor

M3

4.54

88,600.00

402,022.50

6 Polyethelane sheet damp proof 0.5 mm bed to concrete M2


slab

45.38

7,500.00

340,312.50

7 Anti termite to soil equal to Lentrex 400 EC on building M2


area

847.00

25,000.00

21,175,000.00

Sub Total
III

8,470,000.00

54,136,375.00

CONCRETE
1 Pour concrete K225 to Column

M3

2.40

1,750,000.00

4,200,000.00

2 Ditto to Ring beam

M3

2.39

1,300,000.00

3,110,250.00

3 Ditto to floor slab

M3

63.72

1,650,000.00

105,138,000.00

4 Water proofing coating c/w wire mesh and sloping plaster M2


to Bathroom floor

39.03

90,000.00

3,512,250.00

PT. NUSANTARA ISLAND RESORT

10.00 BILL NO. 7 - 42

AMANKILA STAGE 2 PROJECT

AREA

: 10.00 BILL NO. 7 MANAGER'S RESIDENCE

ITEM NO.

DESCRIPTION

UNIT

5 Cementitius water proofing with 2 M hight to Toilet wall

M2

QTY.
46.50

COST PLAN
RATE
AMOUNT
35,000.00
1,627,500.00

Sub Total
IV

117,588,000.00

MASONRY
1 Half brick masonry to with mortar 1pc: 4 sand to wall

M2

381.75

62,604.00

23,899,077.00

2 One brick masonry to with mortar 1pc: 4 sand to wall

M2

131.25

125,208.00

16,433,550.00

3 River stonen retaining wall

M3

147.38

236,388.00

34,837,681.50

Sub Total
V

75,170,308.50

PLASTER
1 Plaster 1pc: 5 sand as indicated in drawing to 1 st floor M2
wall inside

381.75

17,895.00

6,831,416.25

2 Plaster 1pc: 5 sand as indicated in drawing to 1 st floor M2


wall outside

224.25

17,895.00

4,012,953.75

Sub Total
VI

10,844,370.00

ROOF
1 Bingkirai timber profile expose to Trusses c/w other M3
accessories as described in drawing and specification

22.12

3,660,000.00

80,959,200.00

2 Bamboo rafter for thatched roof c/w rope as described in M2


drawing and specification

484.75

30,000.00

14,542,500.00

3 Thatch roof ties by "Ate rope" as described in drawing and M2


specification

484.75

75,000.00

36,356,250.00

4 Thatch ridge roof as described in drawing and specification M1

80.25

52,500.00

4,213,125.00

PT. NUSANTARA ISLAND RESORT

10.00 BILL NO. 7 - 43

AMANKILA STAGE 2 PROJECT

AREA

: 10.00 BILL NO. 7 MANAGER'S RESIDENCE

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT
65,880.00
7,997,832.00

5 Bingkirai timber 1st eave board 6/15 as described in M1


drawing and specification

121.40

6 Bingkirai timber 2nd eave board 6/15 as described in M1


drawing and specification

129.40

65,880.00

8,524,872.00

7 Bingkirai timber tatab 3/12 as described in drawing and M1


specification

129.40

50,000.00

6,470,000.00

Sub Total
VII

159,063,779.00

FLOOR
1 Polished Terrazzo pour in situ as indicated in drawing c/w M2
wire mesh and anti porous coating

205.56

129,303.00

26,579,847.94

2 Pebblewash to floor and stepping

M2

195.63

65,000.00

12,715,625.00

3 Keramik to bathroom Maid House

M2

6.90

45,000.00

310,500.00

Sub Total
VIII

39,605,972.94

CEILING
1 Gypsum board weatherproof 9 MM thickness c/w bingkirai M2
timber frame, hanger and galvanized nails (screw) as
indicated in drawing and specification to Manager's
Bathroom

23.13

110,400.00

2,553,000.00

M2

6.90

110,400.00

761,760.00

3 Gypsum board 9 MM thickness c/w bingkirai timber frame, M2


hanger and galvanized nails (screw) as indicated in
drawing and specification to Maid's Room

39.00

81,600.00

3,182,400.00

4 Bingkirai timber cornice profil to Manager's Bathroom

M1

38.00

15,000.00

570,000.00

5 Ditto to Maid's Bathroom

M1

13.00

15,000.00

195,000.00

2 Ditto to Maid's Bathroom

PT. NUSANTARA ISLAND RESORT

10.00 BILL NO. 7 - 44

AMANKILA STAGE 2 PROJECT

AREA

: 10.00 BILL NO. 7 MANAGER'S RESIDENCE

ITEM NO.

DESCRIPTION

UNIT

6 Ditto to Maid's Room

M1

QTY.
40.00

COST PLAN
RATE
AMOUNT
15,000.00
600,000.00

Sub Total
IX

7,862,160.00

DOOR AND WINDOWS


1 Teak frames, Sungkai veneer doors w/ solid edge Set
strippings c/ Bangkirai jambs, hardware, finishing Lazur DL
350, and concrete stiffener as indicated in drawing to Type
SD 1

7.00 12,500,000.00

87,500,000.00

2 Ditto to SD 2

Set

3.00

9,000,000.00

27,000,000.00

3 Ditto to SD 3

Set

1.00

7,500,000.00

7,500,000.00

4 Ditto to D 1

Set

1.00

6,000,000.00

6,000,000.00

5 Ditto to D 2

Set

7.00

5,000,000.00

35,000,000.00

6 Window w/ Teak frames, Glass infil and lattice c/ Bangkirai Set


jambs, hardware, finishing Lazur DL 350, and concrete
stiffener as indicated in drawing to Type W 1

2.00

6,000,000.00

12,000,000.00

7 Ditto to W 1

8.00

5,000,000.00

40,000,000.00

Set
Sub Total

215,000,000.00

FINISHING WORK
Wall inside
1 Painted wall

M2

381.75

18,000.00

6,871,500.00

1 Painted ceilings to Manager's Bathroom

M2

23.13

20,000.00

462,500.00

2 Ditto to Maid's Bathroom

M2

6.90

20,000.00

138,000.00

Ceilings

PT. NUSANTARA ISLAND RESORT

10.00 BILL NO. 7 - 45

AMANKILA STAGE 2 PROJECT

AREA

: 10.00 BILL NO. 7 MANAGER'S RESIDENCE

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT
20,000.00
780,000.00

3 Ditto to Maid's Room

M2

39.00

4 Woodstain Lazur to cornice Manager's Bathroom

M1

38.00

25,000.00

950,000.00

5 Ditto to Maid's Bathroom

M1

13.00

25,000.00

325,000.00

6 Ditto to Maid's Room

M1

40.00

25,000.00

1,000,000.00

1 Painted wall

M2

224.25

18,000.00

4,036,500.00

2 Paras Jogja to Columns

Unit

17.00

350,000.00

5,950,000.00

3 Paras pilah plaster walls

M2

187.00

150,000.00

28,050,000.00

1 Woodstain Lazur expose trusses

M2

484.75

60,000.00

29,085,000.00

2 Ditto to Edge 1 timber

M1

121.40

25,000.00

3,035,000.00

3 Ditto to Edge 2 timber

M1

129.40

25,000.00

3,235,000.00

4 Ditto to tatab timber

M1

129.40

25,000.00

3,235,000.00

Wall Outside

Roof

Sub Total
XI

87,153,500.00

FIXED FURNITURE
1 Vanity top table w/ terrazo polished finishing c/ concrete Set
and steel bars as detail in drawing to Manager's Bathroom

4.00

3,000,000.00

12,000,000.00

2 Vanity top table w/ ceramics finishing c/ concrete and steel Set


bars as detail in drawing to Maid's Bathroom

1.00

2,000,000.00

2,000,000.00

3 Terrazzo pour in situ to Bathtub

2.00

4,500,000.00

9,000,000.00

Set
Sub total

PT. NUSANTARA ISLAND RESORT

10.00 BILL NO. 7 - 46

23,000,000.00
AMANKILA STAGE 2 PROJECT

AREA

: 10.00 BILL NO. 7 MANAGER'S RESIDENCE

ITEM NO.

XII

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

SANITARY WARE
1 Under counter lavatory American Standard Ovalyn 21" c/w Set
p-trap, stop valve, and other necessary fittings as indicated
in drawing and specification

4.00

1,028,600.00

4,114,400.00

2 Ditto to Maid's Bathroom

Set

1.00

1,028,600.00

1,028,600.00

3 Toilet bowl Toto C 406 c/w stop valve, bolt, covered, and Set
other necessary fitting to Manager's Bathroom

4.00

3,882,000.00

15,528,000.00

4 Toilet bowl Toto Strap c/w stop valve, bolt, covered, and Set
other necessary fitting to Manager's Bathroom

1.00

1,824,000.00

1,824,000.00

5 Bathtub Taps Ideal Standard 1897L382 w/ handle Amarilis Set


cover terrazzo sea shell c/ fittings and other necessary
fittings to Manager's Bathroom

2.00

1,845,000.00

3,690,000.00

6 Shower head Toto TX 422 S

Set

2.00

882,000.00

1,764,000.00

7 Shower taps Toto TX 419 SC

Set

2.00

882,000.00

1,764,000.00

8 Floor drain Bathtub Toto TB 55 AS or equal approved c/w Set


fitting and other necessary fittings as indicated in drawing
and specification

2.00

1,650,000.00

3,300,000.00

9 Floor drain Toto TX 1B or equal approved c/w fitting and Set


other necessary fittings as indicated in drawing and
specification

7.00

146,400.00

1,024,800.00

10 Paper holder Toto TX 11 c/w other necessary fittings as Set


indicated in drawing and specification

3.00

93,600.00

280,800.00

11 Wash Basin Taps Ideal Standard 1897L282 w/ handle Set


Amarilis cover terrazzo sea shell c/ fittings and other
necessary fittings

4.00

1,500,000.00

6,000,000.00

12 Wash Basin Taps Toto T 205 c/ fittings and other Set


necessary fittings

2.00

120,900.00

241,800.00

PT. NUSANTARA ISLAND RESORT

10.00 BILL NO. 7 - 47

AMANKILA STAGE 2 PROJECT

AREA

: 10.00 BILL NO. 7 MANAGER'S RESIDENCE

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

13 Beveled mirror 5 mm with teak timber frame as indicated in Set


drawing

4.00

1,750,000.00

7,000,000.00

14 Ditto to Maid's Bathroom

Set

1.00

500,000.00

500,000.00

15 Combination teak timber towel shelf w/ towel bar refer to Set


Toto TX 4 W c/w other necessary fittings

3.00

886,500.00

2,659,500.00

Sub Total
XIII

50,719,900.00

ELECTRICAL WORK
1 Lighting c/w light, fittings, cable installation, conduit cable, Points
cable gland, 3M rubber insulation, connector and bracket
as indicated in drawing and specification

85.00

350,000.00

29,750,000.00

2 Outlet c/w fittings, cable installation, conduit cable, cable Points


gland, 3M rubber insulation, connector and bracket as
indicated in drawing and specification

40.00

200,000.00

8,000,000.00

3 Electric panel 3 phase SDP c/w MCB, ELCB, Busbar, Points


motor protector to 3 phase motor, grounding, connecting,
commissioning test and other necessary fitting as
indicated in drawing and specification to Receptions

1.00

7,500,000.00

7,500,000.00

Sub Total
XIV

45,250,000.00

COMMUNICATION AND COMPUTER WORK


1 Distribution telephone panel box c/w rustproof terminal, Units
recessed type on Building as indicated in drawing and
specification

1.00

200,000.00

200,000.00

2 Telephone outlet standard Legrand Mosaic 45 c/w cable Points


installation, based plate, covered plate, connector and
other supporting material as indicated in drawing and
spefication

2.00

300,000.00

600,000.00

PT. NUSANTARA ISLAND RESORT

10.00 BILL NO. 7 - 48

AMANKILA STAGE 2 PROJECT

AREA

: 10.00 BILL NO. 7 MANAGER'S RESIDENCE

ITEM NO.

DESCRIPTION

UNIT

QTY.

Sub Total
XV

COST PLAN
RATE
AMOUNT
800,000.00

MECHANICAL WORK
1 Hot water heater ex. Rheem glass 170 Lt. c/w cable Set
installation, bracket, based, double threads (water mur)
and other necessary fittings

2.00 10,000,000.00

20,000,000.00

2 A/C split ceiling concealed type ex Fujitsu or equal Set


approved c/w cable installation, insulated copper pipe,
insulated drain pipe, P trap on drain pipe, pipe glands,
bracket or based, commissioning test and other necessary
fittings

4.00 30,000,000.00

120,000,000.00

3 Exhaust fan 750 CFM ex National or equal c/w cable Set


installation, ducting and other necessary fittings

5.00

1,500,000.00

Sub Total
XVI

7,500,000.00

147,500,000.00

PLUMBING WORK
A. Potable and Hot Water Pipe
1 PVC pipe AW class from main pipe potable water to outlet Points
c/ with fitting, bracket and other necessary supporting
material

11.00

300,000.00

3,300,000.00

2 Thermaflex insulated copper pipe for hot water c/w fittings, Points
hanger, bracket and other necessary fittings on water
heater installation

19.00

500,000.00

9,500,000.00

19.00

400,000.00

7,600,000.00

B. Sewerage Pipe
1 PVC pipe AW class for sewerage pipe, c/w all fittings, Points
bracket, hanger, PVC clean out and other necessary
supporting material as indicated in drawing

Sub Total

20,400,000.00

COLLECTION
PT. NUSANTARA ISLAND RESORT

10.00 BILL NO. 7 - 49

AMANKILA STAGE 2 PROJECT

AREA

: 10.00 BILL NO. 7 MANAGER'S RESIDENCE

ITEM NO.

I
II
III
IV
V
VI
VII
VIII
IX
X
XI
XII
XIII
XIV
XV
XVI

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

PREPARATION WORK
SOIL AND SANDS
CONCRETE
MASONRY
PLASTER
ROOF
FLOOR
CEILING
DOOR AND WINDOWS
FINISHING WORK
FIXED FURNITURE
SANITARY WARE
ELECTRICAL WORK
COMMUNICATION AND COMPUTER WORK
MECHANICAL WORK
PLUMBING WORK

8,470,000.00
54,136,375.00
117,588,000.00
75,170,308.50
10,844,370.00
159,063,779.00
39,605,972.94
7,862,160.00
215,000,000.00
87,153,500.00
23,000,000.00
50,719,900.00
45,250,000.00
800,000.00
147,500,000.00
20,400,000.00

10.00 BILL NO. 7 MANAGER'S RESIDENCE Rp.


To Final Summary

1,062,564,365.44

PT. NUSANTARA ISLAND RESORT

10.00 BILL NO. 7 - 50

AMANKILA STAGE 2 PROJECT

AREA

: 11.00 BILL NO. 8 CHEF'S RESIDENCE

ITEM NO.

DESCRIPTION

UNIT

QTY.

M2

847.00

COST PLAN
RATE
AMOUNT

PREPARATION WORK
1 Site clearance and soil stripping

10,000.00

Sub Total
II

8,470,000.00

SOIL AND SANDS


1 Excavation to foot foundation

M3

126.00

25,000.00

3,150,000.00

2 Ditto to river stone strip foundation and retaining wall

M3

453.75

25,000.00

11,343,750.00

3 Compacted soil to building level

M3

363.00

44,400.00

16,117,200.00

4 Compacted sand bed 5 cm to river stone strip foundation

M3

18.15

88,600.00

1,608,090.00

5 Ditto to under concrete slab floor

M3

4.54

88,600.00

402,022.50

6 Polyethelane sheet damp proof 0.5 mm bed to concrete M2


slab

45.38

7,500.00

340,312.50

7 Anti termite to soil equal to Lentrex 400 EC on building M2


area

847.00

25,000.00

21,175,000.00

Sub Total
III

8,470,000.00

54,136,375.00

CONCRETE
1 Pour concrete K225 to Column

M3

2.40

1,750,000.00

4,200,000.00

2 Ditto to Ring beam

M3

2.39

1,300,000.00

3,110,250.00

3 Ditto to floor slab

M3

63.72

1,650,000.00

105,138,000.00

4 Water proofing coating c/w wire mesh and sloping plaster M2


to Toilet floor

39.03

90,000.00

3,512,250.00

PT. NUSANTARA ISLAND RESORT

11.00 BILL NO. 8 - 51

AMANKILA STAGE 2 PROJECT

AREA

: 11.00 BILL NO. 8 CHEF'S RESIDENCE

ITEM NO.

DESCRIPTION

UNIT

5 Cementitius water proofing with 2 M hight to Toilet wall

M2

QTY.
46.50

COST PLAN
RATE
AMOUNT
35,000.00
1,627,500.00

Sub Total
IV

117,588,000.00

MASONRY
1 Half brick masonry to with mortar 1pc: 4 sand to wall

M2

381.75

62,604.00

23,899,077.00

2 One brick masonry to with mortar 1pc: 4 sand to wall

M2

131.25

125,208.00

16,433,550.00

3 River stonen retaining wall

M3

147.38

236,388.00

34,837,681.50

Sub Total
V

75,170,308.50

PLASTER
1 Plaster 1pc: 5 sand as indicated in drawing to 1 st floor M2
wall inside

381.75

17,895.00

6,831,416.25

2 Plaster 1pc: 5 sand as indicated in drawing to 1 st floor M2


wall outside

224.25

17,895.00

4,012,953.75

Sub Total
VI

10,844,370.00

ROOF
1 Bingkirai timber profile expose to Trusses c/w other M3
accessories as described in drawing and specification

22.12

3,660,000.00

80,959,200.00

2 Bamboo rafter for thatched roof c/w rope as described in M2


drawing and specification

484.75

30,000.00

14,542,500.00

3 Thatch roof ties by "Ate rope" as described in drawing and M2


specification

484.75

75,000.00

36,356,250.00

4 Thatch ridge roof as described in drawing and specification M1

80.25

52,500.00

4,213,125.00

PT. NUSANTARA ISLAND RESORT

11.00 BILL NO. 8 - 52

AMANKILA STAGE 2 PROJECT

AREA

: 11.00 BILL NO. 8 CHEF'S RESIDENCE

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT
65,880.00
7,997,832.00

5 Bingkirai timber 1st eave board 6/15 as described in M1


drawing and specification

121.40

6 Bingkirai timber 2nd eave board 6/15 as described in M1


drawing and specification

129.40

65,880.00

8,524,872.00

7 Bingkirai timber tatab 3/12 as described in drawing and M1


specification

129.40

50,000.00

6,470,000.00

Sub Total
VII

159,063,779.00

FLOOR
1 Polished Terrazzo pour in situ as indicated in drawing c/w M2
wire mesh and anti porous coating

205.56

129,303.00

26,579,847.94

2 Pebblewash to floor and stepping

M2

195.63

65,000.00

12,715,625.00

3 Keramik to bathroom Maid House

M2

6.90

45,000.00

310,500.00

Sub Total
VIII

39,605,972.94

CEILING
1 Gypsum board weatherproof 9 MM thickness c/w bingkirai M2
timber frame, hanger and galvanized nails (screw) as
indicated in drawing and specification to Manager's
Bathroom

23.13

110,400.00

2,553,000.00

M2

6.90

110,400.00

761,760.00

3 Gypsum board 9 MM thickness c/w bingkirai timber frame, M2


hanger and galvanized nails (screw) as indicated in
drawing and specification to Maid's Room

39.00

81,600.00

3,182,400.00

4 Bingkirai timber cornice profil to Manager's Bathroom

M1

38.00

15,000.00

570,000.00

5 Ditto to Maid's Bathroom

M1

13.00

15,000.00

195,000.00

2 Ditto to Maid's Bathroom

PT. NUSANTARA ISLAND RESORT

11.00 BILL NO. 8 - 53

AMANKILA STAGE 2 PROJECT

AREA

: 11.00 BILL NO. 8 CHEF'S RESIDENCE

ITEM NO.

DESCRIPTION

UNIT

6 Ditto to Maid's Room

M1

QTY.
40.00

COST PLAN
RATE
AMOUNT
15,000.00
600,000.00

Sub Total
IX

7,862,160.00

DOOR AND WINDOWS


1 Teak frames, Sungkai veneer doors w/ solid edge Set
strippings c/ Bangkirai jambs, hardware, finishing Lazur DL
350, and concrete stiffener as indicated in drawing to Type
SD 1

7.00 12,500,000.00

87,500,000.00

2 Ditto to SD 2

Set

3.00

9,000,000.00

27,000,000.00

3 Ditto to SD 3

Set

1.00

7,500,000.00

7,500,000.00

4 Ditto to D 1

Set

1.00

6,000,000.00

6,000,000.00

5 Ditto to D 2

Set

7.00

5,000,000.00

35,000,000.00

6 Window w/ Teak frames, Glass infil and lattice c/ Bangkirai Set


jambs, hardware, finishing Lazur DL 350, and concrete
stiffener as indicated in drawing to Type W 1

2.00

6,000,000.00

12,000,000.00

7 Ditto to W 1

8.00

5,000,000.00

40,000,000.00

Set
Sub Total

215,000,000.00

FINISHING WORK
Wall inside
1 Painted wall

M2

381.75

18,000.00

6,871,500.00

1 Painted ceilings to Manager's Bathroom

M2

23.13

20,000.00

462,500.00

2 Ditto to Maid's Bathroom

M2

6.90

20,000.00

138,000.00

Ceilings

PT. NUSANTARA ISLAND RESORT

11.00 BILL NO. 8 - 54

AMANKILA STAGE 2 PROJECT

AREA

: 11.00 BILL NO. 8 CHEF'S RESIDENCE

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT
20,000.00
780,000.00

3 Ditto to Maid's Room

M2

39.00

4 Woodstain Lazur to cornice Manager's Bathroom

M1

38.00

25,000.00

950,000.00

5 Ditto to Maid's Bathroom

M1

13.00

25,000.00

325,000.00

6 Ditto to Maid's Room

M1

40.00

25,000.00

1,000,000.00

1 Painted wall

M2

224.25

18,000.00

4,036,500.00

2 Paras Jogja to Columns

Unit

17.00

350,000.00

5,950,000.00

3 Paras pilah plaster walls

M2

187.00

150,000.00

28,050,000.00

1 Woodstain Lazur expose trusses

M2

484.75

60,000.00

29,085,000.00

2 Ditto to Edge 1 timber

M1

121.40

25,000.00

3,035,000.00

3 Ditto to Edge 2 timber

M1

129.40

25,000.00

3,235,000.00

4 Ditto to tatab timber

M1

129.40

25,000.00

3,235,000.00

Wall Outside

Roof

Sub Total
XI

87,153,500.00

FIXED FURNITURE
1 Vanity top table w/ terrazo polished finishing c/ concrete Set
and steel bars as detail in drawing to Manager's Bathroom

4.00

3,000,000.00

12,000,000.00

2 Vanity top table w/ ceramics finishing c/ concrete and steel Set


bars as detail in drawing to Maid's Bathroom

1.00

2,000,000.00

2,000,000.00

3 Terrazzo pour in situ to Bathtub

2.00

4,500,000.00

9,000,000.00

Set
Sub total

PT. NUSANTARA ISLAND RESORT

11.00 BILL NO. 8 - 55

23,000,000.00
AMANKILA STAGE 2 PROJECT

AREA

: 11.00 BILL NO. 8 CHEF'S RESIDENCE

ITEM NO.

XII

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

SANITARY WARE
1 Under counter lavatory American Standard Ovalyn 21" c/w Set
p-trap, stop valve, and other necessary fittings as indicated
in drawing and specification

4.00

1,028,600.00

4,114,400.00

2 Ditto to Maid's Bathroom

Set

1.00

1,028,600.00

1,028,600.00

3 Toilet bowl Toto C 406 c/w stop valve, bolt, covered, and Set
other necessary fitting to Manager's Bathroom

4.00

3,882,000.00

15,528,000.00

4 Toilet bowl Toto Strap c/w stop valve, bolt, covered, and Set
other necessary fitting to Chef's Bathroom

1.00

1,824,000.00

1,824,000.00

5 Bathtub Taps Ideal Standard 1897L382 w/ handle Amarilis Set


cover terrazzo sea shell c/ fittings and other necessary
fittings to Chef's Bathroom

2.00

1,845,000.00

3,690,000.00

6 Shower head Toto TX 422 S

Set

2.00

882,000.00

1,764,000.00

7 Shower taps Toto TX 419 SC

Set

2.00

882,000.00

1,764,000.00

8 Floor drain Bathtub Toto TB 55 AS or equal approved c/w Set


fitting and other necessary fittings as indicated in drawing
and specification

2.00

1,650,000.00

3,300,000.00

9 Floor drain Toto TX 1B or equal approved c/w fitting and Set


other necessary fittings as indicated in drawing and
specification

7.00

146,400.00

1,024,800.00

10 Paper holder Toto TX 11 c/w other necessary fittings as Set


indicated in drawing and specification

3.00

93,600.00

280,800.00

11 Wash Basin Taps Ideal Standard 1897L282 w/ handle Set


Amarilis cover terrazzo sea shell c/ fittings and other
necessary fittings

4.00

1,500,000.00

6,000,000.00

12 Wash Basin Taps Toto T 205 c/ fittings and other Set


necessary fittings

2.00

120,900.00

241,800.00

PT. NUSANTARA ISLAND RESORT

11.00 BILL NO. 8 - 56

AMANKILA STAGE 2 PROJECT

AREA

: 11.00 BILL NO. 8 CHEF'S RESIDENCE

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

13 Beveled mirror 5 mm with teak timber frame as indicated in Set


drawing

4.00

1,750,000.00

7,000,000.00

14 Ditto to Maid's Bathroom

Set

1.00

500,000.00

500,000.00

15 Combination teak timber towel shelf w/ towel bar refer to Set


Toto TX 4 W c/w other necessary fittings

3.00

886,500.00

2,659,500.00

Sub Total
XIII

50,719,900.00

ELECTRICAL WORK
1 Lighting c/w light, fittings, cable installation, conduit cable, Points
cable gland, 3M rubber insulation, connector and bracket
as indicated in drawing and specification

85.00

350,000.00

29,750,000.00

2 Outlet c/w fittings, cable installation, conduit cable, cable Points


gland, 3M rubber insulation, connector and bracket as
indicated in drawing and specification

40.00

200,000.00

8,000,000.00

3 Electric panel 3 phase SDP c/w MCB, ELCB, Busbar, Points


motor protector to 3 phase motor, grounding, connecting,
commissioning test and other necessary fitting as
indicated in drawing and specification

1.00

7,500,000.00

7,500,000.00

Sub Total
XIV

45,250,000.00

COMMUNICATION AND COMPUTER WORK


1 Distribution telephone panel box c/w rustproof terminal, Units
recessed type on Building as indicated in drawing and
specification

1.00

200,000.00

200,000.00

2 Telephone outlet standard Legrand Mosaic 45 c/w cable Points


installation, based plate, covered plate, connector and
other supporting material as indicated in drawing and
spefication

2.00

300,000.00

600,000.00

Sub Total
PT. NUSANTARA ISLAND RESORT

11.00 BILL NO. 8 - 57

800,000.00
AMANKILA STAGE 2 PROJECT

AREA

: 11.00 BILL NO. 8 CHEF'S RESIDENCE

ITEM NO.

XV

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

MECHANICAL WORK
1 Hot water heater ex. Rheem glass 170 Lt. c/w cable Set
installation, bracket, based, double threads (water mur)
and other necessary fittings

2.00 10,000,000.00

20,000,000.00

2 A/C split ceiling concealed type ex Fujitsu or equal Set


approved c/w cable installation, insulated copper pipe,
insulated drain pipe, P trap on drain pipe, pipe glands,
bracket or based, commissioning test and other necessary
fittings

4.00 30,000,000.00

120,000,000.00

3 Exhaust fan 750 CFM ex National or equal c/w cable Set


installation, ducting and other necessary fittings

5.00

1,500,000.00

Sub Total
XVI

7,500,000.00

147,500,000.00

PLUMBING WORK
A. Potable and Hot Water Pipe
1 PVC pipe AW class from main pipe potable water to outlet Points
c/ with fitting, bracket and other necessary supporting
material

11.00

300,000.00

3,300,000.00

2 Thermaflex insulated copper pipe for hot water c/w fittings, Points
hanger, bracket and other necessary fittings on water
heater installation

19.00

500,000.00

9,500,000.00

19.00

400,000.00

7,600,000.00

B. Sewerage Pipe
1 PVC pipe AW class for sewerage pipe, c/w all fittings, Points
bracket, hanger, PVC clean out and other necessary
supporting material as indicated in drawing

Sub Total

20,400,000.00

COLLECTION

PT. NUSANTARA ISLAND RESORT

11.00 BILL NO. 8 - 58

AMANKILA STAGE 2 PROJECT

AREA

: 11.00 BILL NO. 8 CHEF'S RESIDENCE

ITEM NO.
I
II
III
IV
V
VI
VII
VIII
IX
X
XI
XII
XIII
XIV
XV
XVI

DESCRIPTION

UNIT

PREPARATION WORK
SOIL AND SANDS
CONCRETE
MASONRY
PLASTER
ROOF
FLOOR
CEILING
DOOR AND WINDOWS
FINISHING WORK
FIXED FURNITURE
SANITARY WARE
ELECTRICAL WORK
COMMUNICATION AND COMPUTER WORK
MECHANICAL WORK
PLUMBING WORK
11.00 BILL NO. 8 CHEF'S RESIDENCE Rp.
To Final Summary

PT. NUSANTARA ISLAND RESORT

11.00 BILL NO. 8 - 59

QTY.

COST PLAN
RATE
AMOUNT
8,470,000.00
54,136,375.00
117,588,000.00
75,170,308.50
10,844,370.00
159,063,779.00
39,605,972.94
7,862,160.00
215,000,000.00
87,153,500.00
23,000,000.00
50,719,900.00
45,250,000.00
800,000.00
147,500,000.00
20,400,000.00
1,062,564,365.44

AMANKILA STAGE 2 PROJECT

AREA

: 12.00 BILL NO. 9 BUILDING STRUCTURE

ITEM NO.

DESCRIPTION

UNIT

QTY.

M2

1,849.00

COST PLAN
RATE
AMOUNT

PREPARATION WORK
1 Site clearance and soil stripping

10,000.00

Sub Total
II

18,490,000.00

SOIL AND SANDS


1 Excavation to foot foundation Spa, Gym and Shop

M3

209.25

25,000.00

5,231,250.00

2 Ditto to foot foundation Treatment

M3

108.00

25,000.00

2,700,000.00

3 Ditto to river stone strip foundation

M3

369.00

25,000.00

9,225,000.00

4 Ditto to retaining wall

M3

99.00

25,000.00

2,475,000.00

5 Fill and Compacted soil to Garden Terracce

M3

121.00

44,400.00

5,372,400.00

6 Ditto to Garden between staircase

M3

84.00

44,400.00

3,729,600.00

7 Compacted sand bed 5 cm to river stone strip foundation

M3

24.60

88,600.00

2,179,560.00

8 Anti termite to soil equal to Lentrex 400 EC on building M2


area

1,849.00

25,000.00

46,225,000.00

Sub Total
III

18,490,000.00

77,137,810.00

CONCRETE
1 Pour concrete K225 to Foot foundation Spa, Gym and M3
Shop

35.15

1,500,000.00

52,731,000.00

2 Ditto to Foot foundation Treatment

M3

18.14

1,500,000.00

27,216,000.00

3 Ditto to Foot foundation Pathway

M3

14.18

1,500,000.00

21,262,500.00

4 Ditto to Column Spa, Gym and Shop

M3

22.32

1,750,000.00

39,060,000.00

PT. NUSANTARA ISLAND RESORT

12.00 BILL NO. 9 - 60

AMANKILA STAGE 2 PROJECT

AREA

: 12.00 BILL NO. 9 BUILDING STRUCTURE

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT
1,750,000.00
20,160,000.00

5 Ditto to Column Treatment

M3

11.52

6 Ditto to Column Pathway

M3

6.75

1,750,000.00

11,812,500.00

7 Ditto to Beam

M3

154.46

2,200,000.00

339,817,500.00

8 Ditto to Beam Pathway

M3

61.79

2,200,000.00

135,927,000.00

9 Ditto to concrete floor and staircase slab Spa, Gym and M3


Shop

147.22

1,750,000.00

257,630,625.00

10 Ditto to Treatment Pavillion

M3

91.41

1,750,000.00

159,969,600.00

11 Ditto to Pathway

M3

53.10

1,750,000.00

92,925,000.00

12 Water proofing coating c/w wire mesh and sloping plaster M2


to Lotus pond around Gym and Shop wall and floor

396.07

90,000.00

35,646,300.00

Sub Total

1,194,158,025.00

PREPARATION WORK
SOIL AND SANDS
CONCRETE

18,490,000.00
77,137,810.00
1,194,158,025.00

12.00 BILL NO. 9 BUILDING STRUCTURE Rp.


To Final Summary

1,289,785,835.00

COLLECTION
I
II
III

PT. NUSANTARA ISLAND RESORT

12.00 BILL NO. 9 - 61

AMANKILA STAGE 2 PROJECT

AREA

: 13.00 BILL NO. 10 TENNIS COURT

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

PREPARATION WORK
1 Site clearance and soil stripping

M2

690.00

10,000.00

Sub Total
II

6,900,000.00

SOIL AND SANDS


1 Excavation to levelling

M3

516.00

25,000.00

12,900,000.00

2 Ditto to river stone strip foundation

M3

165.00

25,000.00

4,125,000.00

3 Fill and Compacted soil to levelling

M3

157.50

44,400.00

6,993,000.00

4 Compacted sand bed 5 cm to river stone strip foundation

M3

11.00

88,600.00

974,600.00

5 Ditto to under concrete slab

M3

65.50

88,600.00

5,803,300.00

6 Polyethelane sheet damp proof 0.5 mm bed to concrete M2


slab

655.00

7,500.00

4,912,500.00

7 Anti termite to soil equal to Lentrex 400 EC on building M2


area

690.00

25,000.00

17,250,000.00

Sub Total
III

52,958,400.00

CONCRETE
1 Pour concrete K225 to floor tennis

M3

98.25

1,650,000.00

162,112,500.00

2 Ditto to Column

M3

5.00

1,750,000.00

8,750,000.00

3 Ditto to Beam

M3

15.00

1,750,000.00

26,250,000.00

Sub Total
IV

6,900,000.00

197,112,500.00

MASONRY

PT. NUSANTARA ISLAND RESORT

13.00 BILL NO. 10 - 62

AMANKILA STAGE 2 PROJECT

AREA

: 13.00 BILL NO. 10 TENNIS COURT

1 Half brick masonry to with mortar 1pc: 4 sand to wall

M2

134.28

COST PLAN
RATE
AMOUNT
62,604.00
8,406,565.29

2 River stone foundation and retaining wall

M3

216.03

236,388.00

ITEM NO.

DESCRIPTION

UNIT

QTY.

Sub Total
V

59,472,992.15

PLASTER
1 Plaster 1pc: 5 sand w/ hardener as indicated in drawing to M2
tennis floor
2 Plaster 1pc: 5 sand as indicated in drawing to wall

M2

655.00

44,737.50

29,303,062.50

44.00

17,895.00

787,380.00

Sub Total
VI

51,066,426.86

30,090,442.50

ROOF
1 Bingkirai timber profile expose to Trusses c/w other M3
accessories as described in drawing and specification

5.20

3,660,000.00

19,032,000.00

2 Bamboo rafter for thatched roof c/w rope as described in M2


drawing and specification

41.00

30,000.00

1,230,000.00

3 Thatch roof ties by "Ate rope" as described in drawing and M2


specification

41.00

75,000.00

3,075,000.00

4 Thatch ridge roof as described in drawing and specification M1

16.75

52,500.00

879,375.00

5 Bingkirai timber 1st eave board 6/15 as described in M1


drawing and specification

24.70

65,880.00

1,627,236.00

6 Bingkirai timber 2nd eave board 6/15 as described in M1


drawing and specification

25.70

65,880.00

1,693,116.00

7 Bingkirai timber tatab 3/12 as described in drawing and M1


specification

25.70

50,000.00

1,285,000.00

Sub Total
PT. NUSANTARA ISLAND RESORT

13.00 BILL NO. 10 - 63

28,821,727.00
AMANKILA STAGE 2 PROJECT

AREA

: 13.00 BILL NO. 10 TENNIS COURT

ITEM NO.

VII

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

FLOOR
1 Polished Palimanan stone 40x40 cm as indicated in M2
drawing
2 Sintethic grass

M2

40.00

129,303.00

5,172,120.00

261.00

500,000.00

130,500,000.00

Sub Total
VIII

135,672,120.00

FINISHING WORK
1 Painted wall

M2

44.00

18,000.00

792,000.00

2 Paras Jogja to Columns

Unit

4.00

350,000.00

1,400,000.00

3 Paras pilah

M2

167.32

150,000.00

25,098,240.00

1 Woodstain Lazur expose trusses

M2

61.50

60,000.00

3,690,000.00

2 Ditto to Eave 1 timber

M1

24.70

25,000.00

617,500.00

3 Ditto to Eave 2 timber

M1

25.70

25,000.00

642,500.00

4 Ditto to tatab timber

M1

25.70

25,000.00

642,500.00

Roof

Sub Total
IX

32,882,740.00

ELECTRICAL WORK
1 Lighting c/w light, fittings, cable installation, conduit cable, Points
cable gland, 3M rubber insulation, connector and bracket
as indicated in drawing and specification

6.00

350,000.00

2,100,000.00

2 Outlet c/w fittings, cable installation, conduit cable, cable Points


gland, 3M rubber insulation, connector and bracket as
indicated in drawing and specification

3.00

200,000.00

600,000.00

PT. NUSANTARA ISLAND RESORT

13.00 BILL NO. 10 - 64

AMANKILA STAGE 2 PROJECT

AREA

: 13.00 BILL NO. 10 TENNIS COURT

ITEM NO.

DESCRIPTION

UNIT

3 Tennis Special Lighting c/w light, fittings, cable installation, Points


conduit cable, cable gland, 3M rubber insulation,
connector and bracket as indicated in drawing and
specification

4 Electric panel 3 phase SDP c/w MCB, ELCB, Busbar, Points


motor protector to 3 phase motor, grounding, connecting,
commissioning test and other necessary fitting as
indicated in drawing and specification

COST PLAN
RATE
AMOUNT
12.00 15,000,000.00
180,000,000.00

QTY.

1.00 15,000,000.00

15,000,000.00

Sub Total

197,700,000.00

PREPARATION WORK
SOIL AND SANDS
CONCRETE
MASONRY
PLASTER
ROOF
FLOOR
FINISHING WORK
ELECTRICAL WORK

6,900,000.00
52,958,400.00
197,112,500.00
59,472,992.15
30,090,442.50
28,821,727.00
135,672,120.00
32,882,740.00
197,700,000.00

13.00 BILL NO. 10 TENNIS COURT Rp.


To Final Summary

741,610,921.65

COLLECTION
I
II
III
IV
V
VI
VII
VIII
IX

PT. NUSANTARA ISLAND RESORT

13.00 BILL NO. 10 - 65

AMANKILA STAGE 2 PROJECT

AREA

: 14.00 BILL NO. 11 ROAD WAY

ITEM NO.

DESCRIPTION

UNIT

QTY.

M2

1,038.60

COST PLAN
RATE
AMOUNT

PREPARATION WORK
1 Site clearance and soil stripping

10,000.00

Sub Total
II

10,386,000.00

SOIL AND SANDS


1 Excavation to leveling

M3

1,557.90

25,000.00

38,947,500.00

2 Ditto to river stone strip foundation

M3

2,336.85

25,000.00

58,421,250.00

3 Fill and Compacted soil

M3

525.00

44,400.00

23,310,000.00

4 Compacted sand bed 5 cm to river stone strip foundation

M3

155.79

88,600.00

13,802,994.00

Sub Total
III

134,481,744.00

CONCRETE
1 Pour concrete K225 to water channel dia. 100 cm

Unit

16.00

1,500,000.00

24,000,000.00

2 Ditto to box trench

M3

108.15

1,000,000.00

108,150,000.00

Sub Total
IV

132,150,000.00

MASONRY
1 Half brick masonry to with mortar 1pc: 4 sand to wall

M2

515.00

62,604.00

32,241,060.00

2 River stone retaining wall

M3

328.00

236,388.00

77,535,264.00

Sub Total
V

10,386,000.00

109,776,324.00

FLOOR
1 Hot mix finished c/w sub base, base and other materials M2
appropriate specification

PT. NUSANTARA ISLAND RESORT

14.00 BILL NO. 11 - 66

1,336.60

150,000.00

200,490,000.00

AMANKILA STAGE 2 PROJECT

AREA

: 14.00 BILL NO. 11 ROAD WAY

ITEM NO.

DESCRIPTION

UNIT

2 Pebblewash c/w concrete K225 to Foot access

M2

QTY.

309.00

COST PLAN
RATE
AMOUNT
65,000.00

Sub Total
VI

20,085,000.00
220,575,000.00

FINISHING WORK
1 Siaran to wall

M2

612.00

18,000.00

11,016,000.00

Sub Total

11,016,000.00

PREPARATION WORK
SOIL AND SANDS
CONCRETE
MASONRY
FLOOR
FINISHING WORK

10,386,000.00
134,481,744.00
132,150,000.00
109,776,324.00
220,575,000.00
11,016,000.00

14.00 BILL NO. 11 ROAD WAY Rp.


To Final Summary

618,385,068.00

COLLECTION
I
II
III
IV
V
VI

PT. NUSANTARA ISLAND RESORT

14.00 BILL NO. 11 - 67

AMANKILA STAGE 2 PROJECT

AREA

: 15.00 BILL NO. 12 LANDSCAPE

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

SOIL AND SANDS


1 Fill good soil to Garden Terracce

M3

110.10

44,400.00

4,888,440.00

2 Ditto to Garden Treatment Pavillion

M3

72.00

44,400.00

3,196,800.00

3 Ditto to Garden Parking

M3

13.20

44,400.00

586,080.00

4 Planting grass to Garden

M2

611.50

75,000.00

45,862,500.00

Sub Total
II

54,533,820.00

FLOOR
1 Water proofing coating c/w wire mesh and sloping plaster M2
to Lotus pond around Gym and Shop wall and floor

393.50

90,000.00

35,415,000.00

2 Palimanan stone to staircase floor and facing to Reception

M2

80.00

193,403.00

15,472,240.00

3 Ditto to Ground Floor

M2

12.00

193,403.00

2,320,836.00

4 Ditto to Tennis Court

M2

21.60

193,403.00

4,177,504.80

5 Ditto to Pathway Treatment Pavillion

M2

13.20

193,403.00

2,552,919.60

6 Ditto to Pathway connecting existing Pavillion

M2

13.50

193,403.00

2,610,940.50

7 Palimanan stone c/w facing and capping to Lotus Pond M2


around Gym and Shop floor

393.50

193,403.00

76,104,080.50

8 Pebblewash floor to Terracce

M2

275.00

65,000.00

17,875,000.00

9 Ditto to Corridor between Gym and Spa

M2

35.00

65,000.00

2,275,000.00

10 Ditto to Around Spa

M2

55.00

65,000.00

3,575,000.00

11 Ditto to Around Spa

M2

55.00

65,000.00

3,575,000.00

PT. NUSANTARA ISLAND RESORT

15.00 BILL NO. 12 - 68

AMANKILA STAGE 2 PROJECT

AREA

: 15.00 BILL NO. 12 LANDSCAPE

ITEM NO.

DESCRIPTION

UNIT

QTY.

COST PLAN
RATE
AMOUNT

12 Ditto to Around Treatment Pavillion

M2

46.00

65,000.00

2,990,000.00

13 Ditto to Pathway

M2

354.00

65,000.00

23,010,000.00

Sub Total
III

191,953,521.40

MASONRY
1 Half brick masonry to with mortar 1pc: 4 sand to wall

M2

793.50

62,604.00

49,676,274.00

2 River stone foundation and retaining wall

M3

276.00

125,208.00

34,557,408.00

Sub Total
IV

84,233,682.00

PLASTER
1 Plaster 1pc: 5 sand as indicated in drawing

M2

588.80

17,895.00

Sub Total
V

10,536,576.00
10,536,576.00

FINISHING WORK
1 Painted wall

M2

793.50

18,000.00

14,283,000.00

2 Paras pilah plaster wall

M2

1,324.00

150,000.00

198,600,000.00

Sub Total

212,883,000.00

SOIL AND SANDS


FLOOR
MASONRY
PLASTER
FINISHING WORK

54,533,820.00
191,953,521.40
84,233,682.00
10,536,576.00
212,883,000.00

COLLECTION
I
II
III
IV
V

PT. NUSANTARA ISLAND RESORT

15.00 BILL NO. 12 - 69

AMANKILA STAGE 2 PROJECT

AREA

: 15.00 BILL NO. 12 LANDSCAPE

ITEM NO.

DESCRIPTION

UNIT

15.00 BILL NO. 12 LANDSCAPE Rp.


To Final Summary

PT. NUSANTARA ISLAND RESORT

15.00 BILL NO. 12 - 70

QTY.

COST PLAN
RATE
AMOUNT
554,140,599.40

AMANKILA STAGE 2 PROJECT

AREA

: 16.00 BILL NO. 13 MAIN M / E / P

QTY.

COST PLAN
RATE
AMOUNT

1 Main Power Cable NYFGBY installation, cable gland, M1


connector and bracket as indicated in drawing and
specification to Reception

384.00

700,000.00

268,800,000.00

2 Ditto to Manager's and Chef's Residence

M1

285.30

700,000.00

199,710,000.00

3 Ditto to Garden Lighting

M1

10.00

350,000.00

3,500,000.00

4 Electric panel 3 phase MDP c/w MCB, ELCB, Busbar, Unit


motor protector to 3 phase motor, grounding, connecting,
commissioning test and other necessary fitting as
indicated in drawing and specification to Receptions

1.00 25,000,000.00

25,000,000.00

5 Ditto to Garden Lighting c/w timer

1.00

7,500,000.00

7,500,000.00

6 Lighting c/w light, fittings, cable installation, conduit cable, Points


cable gland, 3M rubber insulation, connector and bracket
as indicated in drawing and specification to Road

60.00

1,500,000.00

90,000,000.00

7 Ditto to Foot access

Points

22.00

350,000.00

7,700,000.00

8 Ditto to Walk way

Points

45.00

350,000.00

15,750,000.00

9 Ditto to Garden

Points

26.00

350,000.00

9,100,000.00

10 Outlet c/w fittings, cable installation, conduit cable, cable Points


gland, 3M rubber insulation, connector and bracket as
indicated in drawing and specification

15.00

300,000.00

4,500,000.00

2.00 40,000,000.00

80,000,000.00

ITEM NO.

DESCRIPTION

UNIT

ELECTRICAL WORK

Unit

11 Lightning Protection

Unit
Sub Total

II

711,560,000.00

COMMUNICATION AND COMPUTER WORK

PT. NUSANTARA ISLAND RESORT

16.00 BILL NO. 13 - 71

AMANKILA STAGE 2 PROJECT

AREA

: 16.00 BILL NO. 13 MAIN M / E / P

1 Main Installation Telephone cable underground type on M1


Building as indicated in drawing and specification

640.80

COST PLAN
RATE
AMOUNT
300,000.00
192,240,000.00

2 Ditto to Manager's and Chef's Residence

M1

285.30

300,000.00

85,590,000.00

3 Main Installation Computer cable c/w connector and other M1


supporting material as indicated in drawing and
specification

384.00

200,000.00

76,800,000.00

ITEM NO.

DESCRIPTION

UNIT

QTY.

Sub Total
III

354,630,000.00

MECHANICAL WORK
1 Sumersible grindle pump c/w panel, control level to Set
collection tank sewerage

4.00 22,500,000.00

Sub Total
IV

90,000,000.00

90,000,000.00

PLUMBING WORK
Potable Water
1 Main potable water ring system PVC pipe AW class dia. 3" M1
c/w fitting, bracket and other necessary supporting
material

684.00

96,000.00

65,664,000.00

2 Ditto to Manager's and Chef's Residence

M1

310.30

96,000.00

29,788,800.00

3 Ditto dia. 2" to Fire Hydrant

M1

100.00

54,000.00

5,400,000.00

4 Ditto dia. 1" to Main Garden pipe

M1

65.00

22,800.00

1,482,000.00

5 Garden taps

Unit

6.00

250,000.00

1,500,000.00

6 Check valve 3"

Unit

2.00

2,250,000.00

4,500,000.00

7 Ball valve 3"

Unit

7.00

2,520,000.00

17,640,000.00

8 Fire hydrant box c/ hose

Unit

20.00

7,500,000.00

150,000,000.00

PT. NUSANTARA ISLAND RESORT

16.00 BILL NO. 13 - 72

AMANKILA STAGE 2 PROJECT

AREA

: 16.00 BILL NO. 13 MAIN M / E / P

QTY.

COST PLAN
RATE
AMOUNT

1 Main sewerage PVC pipe AW class dia. 5" c/w all fittings, M1
bracket, hanger, PVC clean out and other necessary
supporting material as indicated in drawing

333.00

198,000.00

65,934,000.00

2 Ditto to Manager's and Chef's Residence

M1

340.30

198,000.00

67,379,400.00

3 Ditto dia. 4"

M1

81.60

108,000.00

8,812,800.00

4 Ditto to 3" from collection tank

M1

150.00

96,000.00

14,400,000.00

5 Ditto to 2.5" from collection tank

M1

210.00

78,000.00

16,380,000.00

6 Collection tank capacity 3000 lt for sewerage

Unit

2.00 15,000,000.00

30,000,000.00

7 Check valve 2.5"

Unit

2.00

ITEM NO.

DESCRIPTION

UNIT

Sewerage

630,000.00

1,260,000.00

Drainage
1 Culvert arround road way

M1

2 Ditto to Building area

M1
Sub Total

480,141,000.00

ELECTRICAL WORK
COMMUNICATION AND COMPUTER WORK
MECHANICAL WORK
PLUMBING WORK

711,560,000.00
90,000,000.00
90,000,000.00
480,141,000.00

16.00 BILL NO. 13 MAIN M / E / P Rp.


To Final Summary

1,371,701,000.00

COLLECTION
I
II
III
IV

PT. NUSANTARA ISLAND RESORT

16.00 BILL NO. 13 - 73

AMANKILA STAGE 2 PROJECT

PERHITUNGAN VOLUME PEKERJAAN


PROYEK : AMANKILA

NO.

JENIS PEKERJAAN

I
1.00
2.00
3.00

Galian
Tanah u/ pondasi batukali menerus
Tanah u/ pondasi setempat
Tanah u/ sloof

II
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.0

Urugan
Tanah kembali u/ pondasi menerus
Tanah kembali u/ pondasi setempat
Tanah kembali u/ sloof
Tanah u/ area Bangunan Utama
Tanah u/ area Bangunan Service
Pasir 5 cm bawah pondasi menerus
Pasir 5 cm bawah pondasi setempat
Pasir 5 cm bawah sloof
Pasir 5 cm bawah slab lantai B.U.
Pasir 5 cm bawah slab lantai B.S.

III
1.00
2.00
3.00

Polyetheline sheet
Bawah pasir sloof
Bawah pasir slab lantai B.U.
Bawah pasir slab lantai B.S.

IV
1.00
2.00
3.00

Pekerjaan Pasangan
Pondasi menerus batu kali 1 : 3
Rollag batu bata 1 : 3
Dinding 1/2 Batu Batu bata 1
Ground
- Horizontal
- Vertikal

PANJANG
M1

LEBAR
M1

TINGGI
M1

17.10
18.60
31.60
16.00

3.00
3.00
3.00
3.00

4.00 Dinding 1/2 Batu Batu bata 1 : 4 1st


floor
- Horizontal

37.10

3.00

- Vertikal

27.50

3.00

4 34.00

3.00

32.00

3.00

5.00 Dinding
Ground

Batu

Batu

bata

6.00 Dinding batako 1 : 3


V
1.00
2.00
3.00
4.00
5.00

Pekerjaan Beton
Pondasi Setempat
Sloof
Kolom Balok
Ring Balok
Kolom praktis
Waterproof
shop

lotus

pond

to

gym

and

floor shop
dinding shop

114.35
78.00

floor gym
dinding gym

141.02
62.70

VI

Pekerjaan Lantai

VII

Pekerjaan Kusen, Pintu & Jendela

VIII Pekerjaan Plafond


IX

Pekerjaan Atap

Pekerjaan Baja

192.35

203.72
396.07

XI

Pekerjaan Finishing

XII

Pekerjaan Artwork

XIII Pekerjaan Fix Furnitures


XIV

Pekerjaan Lain-lain

LUAS
M2

51.30
55.80
94.80
48.00
249.90

VOLUME KETERANGAN
M3

111.30
82.50
193.80
102.00
96.00
198.00

ANALISA HARGA SATUAN


JENIS PEKERJAAN

Galian tanah / M3
Upah kerja
Material bantu

Urug tanah kembali pondasi / M3


Upah kerja
Material bantu

Urug tanah urug dipadatkan / M3


Tanah urug
Upah pemadatan
Upah kerja

Urug pasir bawah pondasi & lantai / M


Pasir pasang
Upah kerja
Material bantu

Pasangan batu kali 1:3 / M


Batu kali
Semen (PC)
Pasir pasang
Upah pas. Batu kali

Pasangan bata merah 1:3 / M2


Bata merah
Semen (PC)
Pasir pasang
Upah pas. Bata merah

VOL.

1.00
1.00

1.00
1.00

1.20
1.00
1.00

1.20
1.00
1.00

1.20
3.30
0.52
1.00

65.00
0.45
0.04
1.00

SAT

ls
ls

ls
ls

ls
ls
ls

m
ls
ls

m
zak
m
ls

HRG. SATUAN
@ Rp.

7,800.00
1,000.00

5,400.00
500.00

30,000.00
3,000.00
5,400.00

66,000.00
8,400.00
1,000.00

66,000.00
30,000.00
66,000.00
24,000.00

JUMLAH
Rp.

7,800.00
1,000.00
8,800.00

8,800.00

5,400.00
500.00
5,900.00

5,900.00

36,000.00
3,000.00
5,400.00
44,400.00

44,400.00

79,200.00
8,400.00
1,000.00
88,600.00

88,600.00

79,200.00
99,000.00
34,188.00
24,000.00
236,388.00

236,388.00

bj
zak
m

600.00
30,000.00
66,000.00

39,000.00
13,500.00
2,904.00

m2

7,200.00

7,200.00
62,604.00

Plesteran 1:4 tebal 15 mm / M2


Semen (PC)
Pasir pasang

0.24
0.02

zak
m

30,000.00
66,000.00

7,200.00
1,320.00

Upah plesteran

1.00

m2

4,800.00

4,800.00
13,320.00

Acian dinding dengan semen / M2


Semen (PC)

0.07

zak

30,000.00

2,175.00

Upah acian

1.00

m2

2,400.00

2,400.00
4,575.00

Plesteran + Acian / M2
Plesteran

1.00

m2

13,320.00

JUMLAH
Rp.

13,320.00

62,604.00

13,320.00

4,575.00

Acian

1.00

m2

4,575.00

4,575.00
17,895.00

17,895.00

Plesteran 1:4 tebal 15 mm dengan floor hardener / M2


Semen (PC)
0.24 zak

30,000.00

7,200.00

Floor hardener
Pasir pasang

1.20
0.02

m2
m

30,000.00
66,000.00

36,000.00
1,320.00

Upah plesteran

1.00

m2

4,800.00

4,800.00
49,320.00

49,320.00

114,000.00
31,200.00
47,520.00
60,000.00
1,000.00
253,720.00

253,720.00

270,000.00
33,000.00
51,084.00
60,000.00
1,000.00
415,084.00

415,084.00

Beton rabat cor 1 : 3 : 5 / m3


Semen
Pasir cor
Split
Upah kerja
Alat bantu

3.80
0.52
0.88
1.00
1.00

Beton cor 1 : 2 : 3 (K - 225) / m3


Semen
Pasir cor
Split
Upah kerja
Alat bantu

9.00
0.55
0.95
1.00
1.00

zak
m
m
ls
ls

zak
m
m
ls
ls

30,000.00
60,000.00
54,000.00
60,000.00
1,000.00

30,000.00
60,000.00
54,000.00
60,000.00
1,000.00

Beton cor 1 : 2 : 3 (K - 175) / m3

0.85

ls

415,084.00

352,821.40

352,821.40

Pekerjaan Besi Beton / Kg


Besi beton
Kawat beton
Upah besi beton

1.05
0.03
1.00

kg
kg
kg

4,800.00
7,200.00
600.00

5,040.00
180.00
600.00
5,820.00

5,820.00

31,680.00
26,040.00
2,880.00
12,000.00
72,600.00

72,600.00

352,821.40
285,907.50
196,020.00
834,748.90

834,748.90

7,938.48
17,634.60
43,560.00
69,133.08
3,072,581.40

3,072,581.40

Pekerjaan Bekisting / M2
Kayu bekisting
Multipleks 9 mm
Paku
Upah bekisting

0.03
0.35
0.40
1.00

Plat lantai 8 cm w/ besi dia. 8 - 20


Beton K 175
Besi 8 - 20
Bekesting

Kolom praktis 15/15 / M1


Beton K 175
Besi 4 dia. 10; 6 - 20
Bekisting
1 M3

Balok praktis 15/15 / M1

1.00
49.13
2.70

m
lb
kg
m2

m
kg
m2

0.02
3.03
0.60

m
kg
m2

44.44

m1

960,000.00
74,400.00
7,200.00
12,000.00

352,821.40
5,820.00
72,600.00

352,821.40
5,820.00
72,600.00

Beton K 175
Besi 4 dia. 10; 6 - 20
Bekisting
1 M3

Sloof praktis 15/15 / M1


Beton K 175
Besi 4 dia. 10; 6 - 20
Bekisting
1 M3

Balok sloof 20/20 cm C / M1


Beton K 225
Besi dia. 16
Bekisting
1 M3

Balok sloof 30/40 cm / M1


Beton K 225
Besi dia. 16
Bekisting
1 M3

0.02
3.03
0.45

m
kg
m2

44.44

m1

0.02
3.03
0.30

m
kg
m2

44.44

m1

0.04
7.70
0.40

m
kg
m2

25.00

m1

0.12
8.87
0.80

m
kg
m2

8.33

m1

352,821.40
5,820.00
72,600.00

352,821.40
5,820.00
72,600.00

415,084.00
5,820.00
72,600.00

415,084.00
5,820.00
72,600.00

Plat lantai beton Ground Tank 15 cm / M3 w/ double tulangan


Beton K 225
0.15
m
415,084.00
Besi dia. 12 - 15
23.67
kg
5,820.00
Bekisting
0.00
m2
72,600.00
Alat bantu
1.00
ls
15,000.00
1 M3

6.67

Dinding beton Ground Tank 15 cm / M3 w/ double


Beton K 225
0.15
Besi dia. 12 - 12.5
23.67
Bekisting
1.20
Alat bantu
1.00
1 M3

tulangan
m
415,084.00
kg
5,820.00
m2
72,600.00
ls
50,000.00

6.67

Plat atap beton GT 15 cm / M3 w/ double tulangan


Beton K 225
0.15
m
Besi dia. 12 - 12.5
23.67
kg
Bekisting
1.00
m2
Alat bantu
1.00
ls
1 M3

Pondasi setempat / Unit


Beton K 225
Besi dia. 19
Bekisting
Alat bantu

6.67

0.68
66.90
1.20
1.00
1 M3

415,084.00
5,820.00
72,600.00
50,000.00

1.47

m
kg
m2
ls

415,084.00
5,820.00
72,600.00
50,000.00

7,938.48
17,634.60
32,670.00
58,243.08
2,588,581.40

2,588,581.40

7,938.48
17,634.60
21,780.00
47,353.08
2,104,581.40

2,104,581.40

16,603.36
44,787.81
29,040.00
90,431.17
2,260,779.25

2,260,779.25

49,810.08
51,649.59
58,080.00
159,539.67
1,329,497.25

1,329,497.25

62,262.60
137,731.23
0.00
15,000.00
214,993.83
1,433,292.21

1,433,292.21

62,262.60
137,731.23
87,120.00
50,000.00
337,113.83
2,247,425.54

2,247,425.54

62,262.60
137,731.23
72,600.00
50,000.00
322,593.83
2,150,625.54

2,150,625.54

282,423.15
389,358.00
87,120.00
50,000.00
808,901.15
1,188,861.19

1,188,861.19

Pasangan teraso tile 40x40 + Border Palimanan / M


Teraso 40x40
13.40
m
Palimanan 40/40/5
10.72
m
Finishing wash u/ terrazzo
13.40
m
Screed lantai
24.12
m
AM grout
3.38
kg
Upah pas
24.12
m
Material bantu
24.12
m

964,800.00
1,608,000.00
134,000.00
431,627.40
24,312.96
120,600.00
120,600.00
3,403,940.36
141,125.22

141,125.22

72,000.00
10,000.00
17,895.00
1,008.00
5,000.00
5,000.00
110,903.00

110,903.00

1,031,760.00
143,300.00
676,317.60
254,016.00
256,435.35
14,444.64
95,000.00
95,000.00
2,566,273.59
135,067.03

135,067.03

Pasangan teraso tile 50x50 + Border Kayu 2/15 dalam & 2/30 luar / M
Teraso 50x50
100.93
m
78,000.00
7,872,345.00
Finishing polish
100.93
m
18,000.00
1,816,695.00
Kayu BKR 2/30
50.00
m1
38,340.00
1,917,000.00
Kayu BKR 2/15
227.15
m1
19,170.00
4,354,465.50
Finishing Lazur DL 350
49.07
m
48,000.00
2,355,480.00
Screed lantai
100.93
m
17,895.00
1,806,097.61
AM grout
14.13
kg
7,200.00
101,734.92
Upah pas.
150.00
m
5,000.00
750,000.00
Material bantu
150.00
m
5,000.00
750,000.00
21,723,818.03
1 M2 150.00
m
144,825.45

144,825.45

1 M2

Pasangan teraso wash 40x40 / M


Teraso 40x40
Finishing wash
Screed lantai
AM grout
Upah pas.
Material bantu

24.12

1.00
1.00
1.00
0.14
1.00
1.00

m
m
m
kg
m
m

Pasangan teraso tile 40x40 + Border Kayu 2/30 / M


Teraso 40x40
14.33
m
Finishing wash
14.33
m
Kayu BKR 2/30
17.64
m1
Finishing Lazur DL 350
5.29
m
Screed lantai
14.33
m
AM grout
2.01
kg
Upah pas.
19.00
m
Material bantu
19.00
m
1 M2

Pasangan teraso tile 40x40 / M


Teraso 40x40
Finishing polish
Screed lantai
AM grout
Upah pas.
Material bantu

Pasangan teraso tile 30x30 / M


Teraso 30x30
Finishing polish
Screed lantai
AM grout
Upah pas.
Material bantu

19.00

1.20
1.00
1.00
0.14
1.00
1.00

1.20
1.00
1.00
0.14
1.00
1.00

72,000.00
150,000.00
10,000.00
17,895.00
7,200.00
5,000.00
5,000.00

72,000.00
10,000.00
17,895.00
7,200.00
5,000.00
5,000.00

72,000.00
10,000.00
38,340.00
48,000.00
17,895.00
7,200.00
5,000.00
5,000.00

m
m
m
kg
m
m

m
m
m
kg
m
m

72,000.00
18,000.00
17,895.00
7,200.00
5,000.00
1,000.00

60,000.00
18,000.00
17,895.00
7,200.00
5,000.00
1,000.00

86,400.00
18,000.00
17,895.00
1,008.00
5,000.00
1,000.00
129,303.00

129,303.00

72,000.00
18,000.00
17,895.00
1,008.00
5,000.00
1,000.00
114,903.00

114,903.00

Pasangan keramik Roman 2243, 30x30 / M


Keramik 30/30
1.00
Screed keramik
1.00
AM 50
0.14
Upah kerja
1.00
Material bantu
1.00

m
m
kg
ls
ls

30,000.00
17,895.00
7,200.00
2,000.00
1,000.00

Pasangan keramik Roman anti slip, homogeneus, 30x30 / M


Keramik 30/30
1.00
m
75,000.00
Screed keramik
1.00
m
17,895.00
AM 50
0.14
kg
7,200.00
Upah kerja
1.00
ls
2,000.00
Material bantu
1.00
ls
1,000.00

Pasangan Marmer 30x30 / M


Marmer 30/30
Screed keramik
AM 50
Upah kerja
Material bantu

1.00
1.00
0.14
1.00
1.00

Pasangan palimanan 40x40 / M


Palimanan 40x40
Paras krobokan art
Screed lantai
AM grout
Upah pas
Material bantu
1 M2

Pasang skirting kayu / M'


Kayu Bingkirai 2x12
Paku
Upah pas. Skirting

Pasang skirting kayu / M'


Kayu Jati 2x12
Paku
Upah pas. Skirting

Pasang capping kayu / M1


Kayu BKR 4x19
Paku
Upah pas. Capping

Pasang capping kayu / M1


Kayu BKR 4x24
Paku
Upah pas. Skirting

Pasangan palimanan 40x40x5 / M2

m
m
kg
ls
ls

1.10
0.00
1.10
0.15
1.10
1.10

m
m
m
kg
m
m

1.10

1.20
0.10
1.00

m'
kg
m'

1.20
0.10
1.00

1.20
0.20
1.00

1.20
0.20
1.00

m'
kg
m'

m'
kg
m'

m'
kg
m'

108,000.00
17,895.00
7,200.00
5,000.00
1,000.00

150,000.00
35,790.00
17,895.00
7,200.00
5,000.00
1,000.00

10,224.00
7,200.00
1,000.00

35,424.00
7,200.00
1,000.00

27,816.00
7,200.00
2,500.00

35,136.00
7,200.00
2,500.00

30,000.00
17,895.00
1,008.00
2,000.00
1,000.00
51,903.00

51,903.00

75,000.00
17,895.00
1,008.00
2,000.00
1,000.00
96,903.00

96,903.00

108,000.00
17,895.00
1,008.00
5,000.00
1,000.00
132,903.00

132,903.00

165,000.00
0.00
19,684.50
1,108.80
5,500.00
1,100.00
192,393.30
174,903.00

174,903.00

12,268.80
720.00
1,000.00
13,988.80

13,988.80

42,508.80
720.00
1,000.00
44,228.80

44,228.80

33,379.20
1,440.00
2,500.00
37,319.20

37,319.20

42,163.20
1,440.00
2,500.00
46,103.20

46,103.20

Palimanan 40x40
Screed lantai
AM grout
Upah polish
Material bantu
Upah pas.

Pasangan palimanan 30x30x5 / M2


Palimanan 30x30
Screed lantai
AM grout
Material bantu
Upah pas.

1.00
1.00
0.14
1.00
1.00
1.00

1.00
1.00
0.14
1.00
1.00

m
m
kg
m
m
m

m
m
kg
m
m

150,000.00
17,895.00
7,200.00
18,000.00
500.00
6,000.00

138,000.00
17,895.00
7,200.00
500.00
6,000.00

150,000.00
17,895.00
1,008.00
18,000.00
500.00
6,000.00
193,403.00

193,403.00

138,000.00
17,895.00
1,008.00
500.00
6,000.00
163,403.00

163,403.00

Pasangan palimanan 30x30x5 / M1

0.33

ls

163,403.00

54,467.67

54,467.67

Pasangan palimanan 15x30x5 / M2

0.50

ls

163,403.00

81,701.50

81,701.50

Pasangan palimanan 15x30x5 / M1

0.33

ls

81,701.50

27,233.83

27,233.83

Pasangan paras silakarang random / M2


Paras silakarang random
Screed lantai
AM grout
Material bantu
Upah pas.

1.20
1.00
0.14
1.00
1.00

m
m
kg
m
m

66,000.00
17,895.00
7,200.00
500.00
5,000.00

79,200.00
17,895.00
1,008.00
500.00
5,000.00
103,603.00

103,603.00

pada dinding diatas 2 m x


pada dinding diatas 4 m x

Pasangan batu karang bukit 1:3 / M


Batu karang bukit
Semen (PC)
Pasir pasang
Upah pas. Batu kali

pada dinding diatas 2 m x


pada dinding diatas 4 m x

Plafond Gypsum 9 mm / M2
Kayu usuk bkr
Paku
Gypsum
Upah pas.

Plafond Gypsum weatherproof 9 mm / M2


Kayu usuk bkr
Paku
Gypsum weatherproof
Upah pas.

List Plafond / M'


Kayu BKR 4/6
Paku
Upah pas. List plafond

1.3
1.5

1.20
3.30
0.52
1.00

1.1
1.2

0.01
0.40
1.20
1.00

0.01
0.40
1.20
1.00

1.20
0.10
1.00

ls
ls

m
zak
m
ls

134,683.90
202,025.85

30,000.00
30,000.00
66,000.00
24,000.00

36,000.00
99,000.00
34,188.00
24,000.00
193,188.00

ls
ls

m3
kg
m2
ls

m3
kg
m2
ls

m'
kg
ls

193,188.00

212,506.80
255,008.16

3,660,000.00
7,200.00
24,000.00
6,000.00

3,660,000.00
7,200.00
48,000.00
6,000.00

8,784.00
7,200.00
3,600.00

43,920.00
2,880.00
28,800.00
6,000.00
81,600.00

81,600.00

43,920.00
2,880.00
57,600.00
6,000.00
110,400.00

110,400.00

10,540.80
720.00
3,600.00

Plafond Lambersiring / M2
Kayu usuk bkr
Paku
Lambersiring
Upah pas.

Pasang Kayu 6/12 / M1


Kayu BKR 6/12
Paku
Upah pek kayu

Pasang Rangka atap genteng / M2


Usuk 5/7
Reng 2/3
Reng 2/3
Tripleks 3 mm
Karpet
Paku
Upah pasang

Pasang Atap genteng / M2


Genteng pejaten rendam olie bekas
Upah pasang

Pasang Genteng Nok / M1


Genteng Nok pejaten
Pasir
Semen
Papan 3/20 cm
Upah pasang

Pasang Talang patahan atap / M1


Papan 3/20
Rangka kayu penopang
Seng BJLS 50
Paku
Upah pasang

Pasang Lisplank 6/15 + 3/8 / M1


Balok 6/15
Balok 3/8
Paku
Upah pasang

Pasang Atap Colorbond / M2


Colorbond
Skrup
Upah pasang

0.01
0.40
1.20
1.00

1.20
0.40
1.00

3.00
3.00
6.00
1.20
1.20
0.20
1.00

25.00
1.00

5.00
0.03
0.34
1.20
1.00

2.10
0.33
1.00
0.07
1.00

1.20
1.20
0.15
1.00

1.20
5.00
1.00

m3
kg
m2
ls

m'
kg
m'

m'
m'
m'
m2
m2
kg
m2

bh
m2

m'
m3
zak
m'
m2

m'
m'
m'
kg
m'

m'
m'
kg
m'

m2
bh
m2

3,660,000.00
7,200.00
72,000.00
9,000.00

28,080.00
6,000.00
4,000.00

12,810.00
2,196.00
2,196.00
10,069.44
8,000.00
7,200.00
6,000.00

1,584.00
6,000.00

4,752.00
66,000.00
30,000.00
25,560.00
8,000.00

25,560.00
4,800.00
15,500.00
7,200.00
8,000.00

32,940.00
17,568.00
1,584.00
8,000.00

97,000.00
1,000.00
3,000.00

14,860.80

14,860.80

43,920.00
2,880.00
86,400.00
9,000.00
142,200.00

142,200.00

28,600.00
2,400.00
4,000.00
35,000.00

35,000.00

38,430.00
6,588.00
13,176.00
12,083.33
9,600.00
1,440.00
6,000.00
87,317.33

87,317.33

39,600.00
6,000.00
45,600.00

45,600.00

23,760.00
2,112.00
10,140.00
30,672.00
8,000.00
74,684.00

74,684.00

53,676.00
1,584.00
15,500.00
475.20
8,000.00
79,235.20

79,235.20

39,528.00
21,081.60
237.60
8,000.00
68,847.20

68,847.20

116,400.00
5,000.00
3,000.00
124,400.00

124,400.00

Pasang Nok Colorbond / M1


Colorbond
Skrup
Upah pasang

Pasang Flasing Colorbond / M1


Colorbond
Skrup
Material bantu
Upah pasang

Pasang Wastafel KIA Ovalin / Unit


Wastafel KIA Ovalin 21"
P trap THX1A-3
Stop valve TL340C5
Supporting fitting TL 516 G
Upah pasang

1 UNIT PINTU TYPE D1


Daun Pintu Kaca 12 mm tempered - clear

Kend PT 2224
Kend PT 2220
Kend PT 2210/C
Cisa floor 602
Lock Kend US 2200; double cylinder 085
Bolt US 1219
Handle made kayu as cisa
Upah pasang

1 UNIT PINTU TYPE D5


Daun Pintu Kaca 10 mm tempered - clear

E371.US3
Handle made kayu as neck
Upah pasang

1 UNIT PINTU TYPE D5'


Daun Pintu Kaca 10 mm tempered - clear

E371.US3
Handle made kayu as neck
Upah pasang

1 UNIT PINTU TYPE D5C


Daun Pintu Kaca 10 mm tempered - clear

E371.US3
Handle made kayu as neck
Upah pasang

1 UNIT PINTU TYPE D5C'


Daun Pintu Kaca 10 mm tempered - clear

1.20
5.00
1.00

1.20
5.00
1.00
1.00

1.00
1.00
2.00
1.00
1.00

6.14
2.00
2.00
2.00
2.00
1.00
1.00
2.00
1.00

3.00
2.00
2.00
1.00

3.24
2.00
2.00
1.00

3.24
2.00
2.00
1.00

3.24

m1
bh
m1

m1
bh
ls
m1

bh
bh
bh
ls
bh

m2
bh
bh
bh
bh
bh
bh
set
ls

m2
set
bh
ls

m2
set
bh
ls

m2
set
bh
ls

m2

50,100.00
1,000.00
3,000.00

25,500.00
1,000.00
1,500.00
3,000.00

462,600.00
145,200.00
87,600.00
195,600.00
50,000.00

352,000.00
72,000.00
370,000.00
370,000.00
2,050,000.00
450,000.00
350,000.00
350,000.00
100,000.00

297,000.00
1,050,000.00
25,000.00
100,000.00

297,000.00
1,050,000.00
25,000.00
100,000.00

297,000.00
1,050,000.00
25,000.00
100,000.00

297,000.00

60,120.00
5,000.00
3,000.00
68,120.00

68,120.00

30,600.00
5,000.00
1,500.00
3,000.00
40,100.00

40,100.00

462,600.00
145,200.00
175,200.00
195,600.00
50,000.00
1,028,600.00

1,028,600.00

2,162,688.00
144,000.00
740,000.00
740,000.00
4,100,000.00
450,000.00
350,000.00
700,000.00
100,000.00
9,486,688.00

9,486,688.00

891,000.00
2,100,000.00
50,000.00
100,000.00
3,141,000.00

3,141,000.00

962,280.00
2,100,000.00
50,000.00
100,000.00
3,212,280.00

3,212,280.00

962,280.00
2,100,000.00
50,000.00
100,000.00
3,212,280.00

3,212,280.00

962,280.00

Film one way

E371.US3
Handle made kayu as neck
Upah pasang

1 UNIT PINTU TYPE D5A


Daun Pintu Kaca 10 mm tempered - clear
Film one way

E372.US26
Handle made kayu as neck
Upah pasang

1 UNIT PINTU TYPE D5A'


Daun Pintu Kaca 10 mm tempered - clear
Film one way

E372.US26
Handle made kayu as neck
Upah pasang

1 UNIT PINTU TYPE D5B


Daun Pintu Kaca 10 mm tempered - clear
Film one way

E372.US26
Handle made kayu as neck
Upah pasang

1 UNIT PINTU TYPE WG


Daun Pintu Kaca 8 mm tempered - clear
Film one way

E371.US26
Handle made kayu as neck
Upah pasang

1 UNIT PINTU TYPE WG'


Daun Pintu Kaca 8 mm tempered - clear
Film one way

E371.US26
Handle made kayu as neck
Upah pasang

1 UNIT PINTU TYPE D2


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12; 4/20
Door hinges Kend SEL 0007 US 32D
Door handle HRE 46.10.US26
Door lock Cisa 52120-60; double cylind
Door closer Cisa 60511-03
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

3.24
2.00
2.00
1.00

5.37
5.37
2.00
2.00
1.00

5.37
0.00
2.00
2.00
1.00

7.47
0.00
2.00
2.00
1.00

0.93
0.00
2.00
2.00
1.00

1.48
0.00
2.00
2.00
1.00

0.06
2.27
2.00
1.00
1.00
1.00
6.00
5.30
1.00
1.00

m2
set
bh
ls

m2
m2
set
bh
ls

m2
m2
set
bh
ls

m2
m2
set
bh
ls

m2
m2
set
bh
ls

m2
m2
set
bh
ls

m3
m3
set
set
unit
set
nos
m2
ls
ls

150,000.00
1,050,000.00
25,000.00
100,000.00

297,000.00
150,000.00
1,800,000.00
25,000.00
100,000.00

297,000.00
150,000.00
1,800,000.00
25,000.00
100,000.00

297,000.00
150,000.00
1,800,000.00
25,000.00
100,000.00

297,000.00
150,000.00
1,050,000.00
25,000.00
100,000.00

297,000.00
150,000.00
1,050,000.00
25,000.00
100,000.00

3,660,000.00
350,000.00
50,000.00
350,000.00
350,000.00
1,050,000.00
500.00
40,000.00
100,000.00
0.00

486,000.00
2,100,000.00
50,000.00
100,000.00
3,698,280.00

3,698,280.00

1,594,890.00
805,500.00
3,600,000.00
50,000.00
100,000.00
6,150,390.00

6,150,390.00

1,594,890.00
0.00
3,600,000.00
50,000.00
100,000.00
5,344,890.00

5,344,890.00

2,218,590.00
0.00
3,600,000.00
50,000.00
100,000.00
5,968,590.00

5,968,590.00

276,091.20
0.00
2,100,000.00
50,000.00
100,000.00
2,526,091.20

2,526,091.20

438,787.80
0.00
2,100,000.00
50,000.00
100,000.00
2,688,787.80

2,688,787.80

201,592.80
793,800.00
100,000.00
350,000.00
350,000.00
1,050,000.00
3,000.00
212,040.00
100,000.00
0.00
3,160,432.80

3,160,432.80

1 UNIT PINTU TYPE D2A


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12; 4/20
Kaca 5 mm
Film one way
Upah stained
Door hinges Kend SEL 0007 US 32D
Door handle HRE 46.10.US26
Door lock Cisa 52120-60; double cylind
Door closer Cisa 60511-03
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1 UNIT PINTU TYPE D2A'


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12; 4/20
Kaca 5 mm
Film one way
Upah stained
Door hinges Kend SEL 0007 US 32D
Door handle HRE 46.10.US26
Door lock Cisa 52120-60; double cylind
Door closer Cisa 60511-03
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1 UNIT PINTU TYPE D3


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12; 4/20
Door hinges Kend SEL 0007 US 32D
Door handle HRE 46.10.US26
Door lock Cisa 52120-60; knob cylinder
Door closer Cisa 60511-03
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1 UNIT PINTU TYPE D3'


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12; 4/20
Alluminium
Door hinges Kend SEL 0007 US 32D
Door handle HRE 46.10.US26
Door lock Cisa 52120-60; half cylinder
Door closer Cisa 60511-03
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1 UNIT PINTU TYPE D3A


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12; 4/20
Alluminium
Door hinges Kend SEL 0007 US 32D
Door handle HRE 46.10.US26
Door lock Cisa 52120-60; knob cylinder

0.06
1.23
0.86
0.86
1.00
2.00
1.00
1.00
1.00
6.00
3.23
1.00
1.00

0.06
1.23
0.86
0.86
1.00
0.00
0.00
0.00
0.00
6.00
3.23
1.00
1.00

0.05
2.02
2.00
1.00
1.00
0.00
6.00
4.80
1.00
1.00

0.05
2.02
0.00
2.00
1.00
1.00
0.00
6.00
4.80
1.00
1.00

0.05
2.02
1.68
2.00
1.00
1.00

m3
m3
m2
m2
ls
unit
set
unit
set
nos
m2
ls
ls

m3
m3
m2
m2
ls
unit
set
unit
set
nos
m2
ls
ls

m3
m2
unit
set
unit
set
nos
m2
ls
ls

m3
m2
m2
unit
set
unit
set
nos
m2
ls
ls

m3
m2
m2
unit
set
unit

3,660,000.00
350,000.00
50,000.00
150,000.00
250,000.00
50,000.00
350,000.00
350,000.00
1,050,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
350,000.00
50,000.00
150,000.00
250,000.00
50,000.00
350,000.00
350,000.00
1,050,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
350,000.00
50,000.00
400,000.00
375,000.00
1,500,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
350,000.00
50,000.00
50,000.00
400,000.00
350,000.00
1,500,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
350,000.00
50,000.00
50,000.00
400,000.00
375,000.00

201,592.80
430,920.00
43,200.00
129,600.00
250,000.00
100,000.00
350,000.00
350,000.00
1,050,000.00
3,000.00
129,096.00
100,000.00
0.00
3,137,408.80

3,137,408.80

201,592.80
430,920.00
43,200.00
129,600.00
250,000.00
0.00
0.00
0.00
0.00
3,000.00
129,096.00
100,000.00
0.00
1,287,408.80

1,287,408.80

197,640.00
705,600.00
100,000.00
400,000.00
375,000.00
0.00
3,000.00
191,880.00
100,000.00
0.00
2,073,120.00

2,073,120.00

197,640.00
705,600.00
0.00
100,000.00
400,000.00
350,000.00
0.00
3,000.00
191,880.00
100,000.00
0.00
2,048,120.00

2,048,120.00

197,640.00
705,600.00
84,000.00
100,000.00
400,000.00
375,000.00

Door closer Cisa 60511-03


Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1 UNIT PINTU TYPE D3A'


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12; 4/20
Alluminium
Door hinges Kend SEL 0007 US 32D
Door handle HRE 46.10.US26
Door lock Cisa 52120-60; double cylind
Door closer Cisa 60511-03
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1 UNIT PINTU TYPE D4


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12; 4/20
Kaca 5 mm
Door hinges Kend SEL 0007 US 32D
Door handle HRE 46.10.US26
Door lock Cisa 52120-60; double cylind
Door closer Cisa 60511-03
Barrelt bolt Kend 311-12"
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1 UNIT PINTU TYPE D4A


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12; 4/20
Kaca 5 mm
Door hinges Kend SEL 0007 US 32D
Door handle HRE 46.10.US26
Door lock Cisa 52120-60; double cylind
Door closer Cisa 60511-03
Barrelt bolt Kend 311-12"
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1 UNIT PINTU TYPE D6


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12; 4/20
Kaca 5 mm
Door hinges Kend SEL 0007 US 32D
Handle made kayu as neck
Kend 529 adjustable roller catch + Ken
Door closer Cisa 60511-03
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

0.00
6.00
4.80
1.00
1.00

0.05
2.02
0.00
2.00
1.00
1.00
0.00
6.00
4.80
1.00
1.00

0.06
1.71
1.73
2.00
1.00
1.00
1.00
2.00
6.00
4.18
1.00
1.00

0.06
3.78
0.00
2.00
1.00
1.00
1.00
2.00
6.00
8.33
1.00
1.00

0.05
1.76
0.00
2.00
2.00
1.00
0.00
6.00
4.29
1.00
1.00

set
nos
m2
ls
ls

m3
m2
m2
unit
set
unit
set
nos
m2
ls
ls

m3
m3
m2
unit
set
unit
set
unit
nos
m2
ls
ls

m3
m3
m2
unit
set
unit
set
unit
nos
m2
ls
ls

m3
m2
m2
unit
set
unit
set
nos
m2
ls
ls

1,500,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
350,000.00
50,000.00
50,000.00
400,000.00
350,000.00
1,500,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
350,000.00
50,000.00
50,000.00
400,000.00
350,000.00
1,500,000.00
80,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
350,000.00
50,000.00
50,000.00
400,000.00
350,000.00
1,500,000.00
80,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
150,000.00
50,000.00
50,000.00
25,000.00
35,000.00
1,500,000.00
500.00
40,000.00
100,000.00
0.00

0.00
3,000.00
191,880.00
100,000.00
0.00
2,157,120.00

2,157,120.00

197,640.00
705,600.00
0.00
100,000.00
400,000.00
350,000.00
0.00
3,000.00
191,880.00
100,000.00
0.00
2,048,120.00

2,048,120.00

225,309.60
597,240.00
86,400.00
100,000.00
400,000.00
350,000.00
1,500,000.00
160,000.00
3,000.00
167,112.00
100,000.00
0.00
3,689,061.60

3,689,061.60

225,309.60
1,323,000.00
0.00
100,000.00
400,000.00
350,000.00
1,500,000.00
160,000.00
3,000.00
333,000.00
100,000.00
0.00
4,494,309.60

4,494,309.60

193,687.20
264,600.00
0.00
100,000.00
50,000.00
35,000.00
0.00
3,000.00
171,720.00
100,000.00
0.00
918,007.20

918,007.20

1 UNIT PINTU TYPE D7


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12; Louvre
Kaca 5 mm
Door hinges Kend SEL 0007 US 32D
Handle made kayu as neck
Kend 529 adjustable roller catch + Ken
Door closer Cisa 60511-03
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1 UNIT PINTU TYPE D8


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12; Louvre
Door leaf with Bingkirai 4/12;4/20
Kaca 5 mm
Door hinges Kend SEL 0007 US 32D
Door handle HRE 46.10.US26
Door lock Cisa 52120-60; double cylind
Door closer Cisa 60511-03
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1 UNIT PINTU TYPE D8'


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12; Louvre
Door leaf with Bingkirai 4/12;4/20
Kaca 5 mm
Door hinges Kend SEL 0007 US 32D
Door handle HRE 46.10.US26
Door lock Cisa 52120-60; double cylind
Door closer Cisa 60511-03
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1 UNIT PINTU TYPE D9


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12
Door leaf with Bingkirai 4/12;4/20
Kaca 5 mm
Door hinges Kend SEL 0007 US 32D
Handle made kayu as neck
Kend 529 adjustable roller catch
Door closer Cisa 60511-03
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1 UNIT PINTU TYPE DG1


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12
Door leaf with Bingkirai 4/12;4/20
Kaca 5 mm
Grill

0.05
2.02
0.00
2.00
2.00
1.00
0.00
6.00
4.80
1.00
1.00

0.06
0.86
2.27
0.00
2.00
1.00
1.00
1.00
6.00
2.49
1.00
1.00

0.06
2.27
0.00
0.00
0.00
0.00
0.00
0.00
6.00
5.30
1.00
1.00

0.05
1.76
0.00
0.00
1.00
1.00
1.00
0.00
6.00
4.29
1.00
1.00

0.13
2.92
0.00
0.72
2.35

m3
m2
m2
unit
set
unit
set
nos
m2
ls
ls

m3
m2
m2
m2
unit
set
unit
set
nos
m2
ls
ls

m3
m2
m2
m2
unit
set
unit
set
nos
m2
ls
ls

m3
m2
m2
m2
unit
set
unit
set
nos
m2
ls
ls

m3
m2
m2
m2
m2

3,660,000.00
200,000.00
50,000.00
50,000.00
25,000.00
35,000.00
1,500,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
200,000.00
200,000.00
50,000.00
50,000.00
400,000.00
350,000.00
1,500,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
200,000.00
200,000.00
50,000.00
50,000.00
400,000.00
350,000.00
1,500,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
150,000.00
200,000.00
50,000.00
50,000.00
25,000.00
15,000.00
1,500,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
350,000.00
200,000.00
50,000.00
150,000.00

197,640.00
403,200.00
0.00
100,000.00
50,000.00
35,000.00
0.00
3,000.00
191,880.00
100,000.00
0.00
1,080,720.00

1,080,720.00

201,592.80
172,800.00
453,600.00
0.00
100,000.00
400,000.00
350,000.00
1,500,000.00
3,000.00
99,720.00
100,000.00
0.00
3,380,712.80

3,380,712.80

201,592.80
453,600.00
0.00
0.00
0.00
0.00
0.00
0.00
3,000.00
212,040.00
100,000.00
0.00
970,232.80

970,232.80

193,687.20
264,600.00
0.00
0.00
50,000.00
25,000.00
15,000.00
0.00
3,000.00
171,720.00
100,000.00
0.00
823,007.20

823,007.20

482,241.60
1,020,600.00
0.00
36,000.00
352,500.00

Door hinges Kend SEL 0007 US 32D


2.00
Door handle HRE 46.10.US26
1.00
Door lock Cisa 52120-60; double cylind
1.00
Door closer Cisa 60511-03
0.00
Barrelt bolt Kend 311-12"
2.00
Anchor
6.00
Finishing with lazur DL 350
11.30
Upah pasang
1.00
Tool and equipment
1.00

1 UNIT PINTU TYPE DG1A


Door frame with Bingkirai 6/15 cm
0.13
Door leaf with Bingkirai 4/12
3.78
Door leaf with Bingkirai 4/12;4/20
0.00
Kaca 5 mm
0.00
Grill
2.35
Door hinges Kend SEL 0007 US 32D
2.00
Door handle HRE 46.10.US26
1.00
Door lock Cisa 52120-60; double cylind
1.00
Door closer Cisa 60511-03
0.00
Barrelt bolt Kend 311-12"
2.00
Anchor
6.00
Finishing with lazur DL 350
13.03
Upah pasang
1.00
Tool and equipment
1.00

1 UNIT PINTU TYPE DG2


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12
Door leaf with Bingkirai 4/12;4/20
Kaca 5 mm
Grill
Door hinges Kend SEL 0007 US 32D
Door handle HRE 46.10.US26
Door lock Cisa 52120-60; double cylind
Door closer Cisa 60511-03
Barrelt bolt Kend 311-12"
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1 UNIT PINTU TYPE DG3


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12
Door leaf with Bingkirai Louvre 1/4
Kaca 5 mm
Grill
Door hinges Kend SEL 0007 US 32D
Door handle HRE 46.10.US26
Door lock Cisa 52120-60; double cylind
Door closer Cisa 60511-03
Barrelt bolt Kend 311-12"
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1 UNIT PINTU TYPE W2


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 4/12
Door leaf with Bingkirai 4/12;4/20

0.12
2.02
0.00
0.00
1.13
2.00
1.00
1.00
1.00
2.00
6.00
7.05
1.00
1.00

0.16
0.05
3.36
0.00
1.13
2.00
1.00
1.00
0.00
2.00
6.00
3.11
1.00
1.00

0.03
0.02
0.00

unit
set
unit
set
unit
nos
m2
ls
ls

m3
m2
m2
m2
m2
unit
set
unit
set
unit
nos
m2
ls
ls

m3
m2
m2
m2
m2
unit
set
unit
set
unit
nos
m2
ls
ls

m3
m3
m2
m2
m2
unit
set
unit
set
unit
nos
m2
ls
ls

m3
m3
m2

50,000.00
400,000.00
350,000.00
1,500,000.00
80,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
350,000.00
200,000.00
50,000.00
150,000.00
50,000.00
400,000.00
350,000.00
1,500,000.00
80,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
350,000.00
200,000.00
50,000.00
150,000.00
50,000.00
400,000.00
350,000.00
1,500,000.00
80,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
3,660,000.00
200,000.00
50,000.00
150,000.00
50,000.00
400,000.00
350,000.00
1,500,000.00
80,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
3,660,000.00
200,000.00

100,000.00
400,000.00
350,000.00
0.00
160,000.00
3,000.00
451,880.00
100,000.00
0.00
3,456,221.60

3,456,221.60

482,241.60
1,323,000.00
0.00
0.00
352,500.00
100,000.00
400,000.00
350,000.00
0.00
160,000.00
3,000.00
521,000.00
100,000.00
0.00
3,791,741.60

3,791,741.60

434,808.00
705,600.00
0.00
0.00
168,750.00
100,000.00
400,000.00
350,000.00
1,500,000.00
160,000.00
3,000.00
281,880.00
100,000.00
0.00
4,204,038.00

4,204,038.00

589,362.48
171,463.68
672,000.00
0.00
168,750.00
100,000.00
400,000.00
350,000.00
0.00
160,000.00
3,000.00
124,347.84
100,000.00
0.00
2,838,924.00

2,838,924.00

128,070.72
68,304.38
0.00

Kaca 5 mm
Grill
Kend Casement 8" CMT 0001 US5
Door handle HRE 46.10.US26
Door lock Cisa 52120-60; double cylind
Door closer Cisa 60511-03
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1 UNIT PINTU TYPE W3 / W3A


Door frame with Alluminium + karet
Door leaf with Bingkirai 4/12
Door leaf with Bingkirai 4/12;4/20
Kaca tempered 10 mm
Grill
Door hinges Kend SEL 0007 US 32D
Door handle HRE 46.10.US26
Door lock Cisa 52120-60; double cylind
Door closer Cisa 60511-03
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

0.45
0.00
2.00
0.00
0.00
0.00
0.00
0.58
1.00
1.00

9.96
0.00
0.00
4.70
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.00
1.00

1 UNIT PINTU TYPE W3B


Door frame with Alluminium + karet
10.13
Door leaf with Bingkirai 4/12
0.00
Door leaf with Bingkirai 4/12;4/20
0.00
Kaca tempered 10 mm
4.92
Grill
0.00
Door hinges Kend SEL 0007 US 32D
0.00
Door handle HRE 46.10.US26
0.00
Door lock Cisa 52120-60; double cylind
0.00
Door closer Cisa 60511-03
0.00
Anchor
0.00
Finishing with lazur DL 350
0.00
Upah pasang
1.00
Tool and equipment
1.00

1 UNIT PINTU TYPE DW2


Door frame with Bingkirai 6/15 cm
0.08
Door leaf with Bingkirai 5/7 cm
0.14
Door leaf with Bingkirai 4/12;4/20
0.04
Kaca 10 mm
11.70
Grill
0.00
Door hinges Kend SEL 0007 US 32D
1.00
Door handle HRE 46.10.US26
1.00
Door lock Cisa 52120-60; double cylind
1.00
Door closer Cisa 60511-03
0.00
Anchor
6.00
Finishing with lazur DL 350
10.35
Upah pasang
1.00
Tool and equipment
1.00

1 UNIT PINTU TYPE DL1


Door frame with Bingkirai 6/15 cm
Door leaf with Bingkirai 5/7 cm
Door leaf with Bingkirai 4/12;4/20
Kaca 10 mm
Louver 1/4 mm

0.06
0.00
0.04
0.00
1.83

m2
m2
unit
set
unit
set
nos
m2
ls
ls

m1
m3
m2
m2
m2
unit
set
unit
set
nos
m2
ls
ls

m1
m3
m2
m2
m2
unit
set
unit
set
nos
m2
ls
ls

m3
m3
m3
m2
m2
unit
set
unit
set
nos
m2
ls
ls

m3
m3
m3
m2
m2

50,000.00
150,000.00
75,000.00
400,000.00
350,000.00
1,500,000.00
500.00
40,000.00
25,000.00
0.00

50,000.00
50,000.00
200,000.00
297,000.00
150,000.00
75,000.00
400,000.00
350,000.00
1,500,000.00
500.00
40,000.00
100,000.00
0.00

50,000.00
50,000.00
200,000.00
297,000.00
150,000.00
75,000.00
400,000.00
350,000.00
1,500,000.00
500.00
40,000.00
100,000.00
0.00

3,660,000.00
3,660,000.00
3,660,000.00
150,000.00
0.00
75,000.00
400,000.00
350,000.00
1,500,000.00
500.00
40,000.00
50,000.00
0.00

3,660,000.00
3,660,000.00
3,660,000.00
150,000.00
200,000.00

22,500.00
0.00
150,000.00
0.00
0.00
0.00
0.00
23,112.00
25,000.00
0.00
416,987.10

416,987.10

498,000.00
0.00
0.00
1,395,306.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
100,000.00
0.00
1,993,306.00

1,993,306.00

506,400.00
0.00
0.00
1,462,665.60
0.00
0.00
0.00
0.00
0.00
0.00
0.00
100,000.00
0.00
2,069,065.60

2,069,065.60

280,648.80
522,648.00
151,506.43
1,755,000.00
0.00
75,000.00
400,000.00
350,000.00
0.00
3,000.00
414,000.00
50,000.00
0.00
4,001,803.23

4,001,803.23

230,448.24
0.00
152,068.61
0.00
365,000.00

Door hinges Kend SEL 0007 US 32D


Door handle HRE 46.10.US26
Door lock Cisa 52120-60; double cylind
Door closer Cisa 60511-03
Anchor
Finishing with lazur DL 350
Upah pasang
Tool and equipment

1.00
1.00
1.00
0.00
0.00
3.65
1.00
1.00

Pintu FD2A
Kusen bangkirai 6/8; 8/12
0.13
Kayu bangkirai 4/20; 4/12
15.28
Kaca 10 mm clear
Rail Hillaldam F - 340
1.00
Door hinges Kend SEL 0007 US 32D
18.00
Door lock Cisa 52120-60; double cylind
1.00
Door handle FPP 08.03.US3 + E.08.03.US
1.00
Barrelt bolt Kend 311-12"
5.00
Slidingtrack rail bottom alluminium
3.65
Sliding track cover bingkirai 3/22
0.07
Finishing lazur
34.29
Upah pasang pintu
6.00
Upah kerja pasang kusen
1.00

Pintu FD2
Kusen bangkirai 6/12; 8/12
0.13
Kayu bangkirai 4/20; 4/12
8.94
Kaca 10 mm clear
6.34
Rail Hillaldam F - 340
1.00
Door hinges Kend SEL 0007 US 32D
18.00
Door lock Cisa 52120-60; double cylind
1.00
Door handle FPP 08.03.US3 + E.08.03.US
1.00
Barrelt bolt Kend 311-12"
5.00
Slidingtrack rail bottom alluminium
3.04
Sliding track cover bingkirai 3/22
0.07
Finishing lazur
27.96
Upah pasang pintu
6.00
Upah kerja pasang kusen
1.00

Pintu DW1
Kusen bangkirai 6/8; 8/12
0.07
Kusen bangkirai 6/15
0.33
Kayu bangkirai 4/20; 4/12
5.80
Kaca 10 mm clear
8.21
Rail Hillaldam F - 340
0.00
Door hinges Kend SEL 0007 US 32D
2.00
Door lock Cisa 52120-60; double cylind
1.00
Door handle HRE 46.10.US26
1.00
Barrelt bolt Kend 311-12"
0.00
Slidingtrack rail bottom alluminium
0.00
Sliding track cover bingkirai 3/22
0.07
Finishing lazur
26.08
Upah pasang
1.00

unit
set
unit
set
nos
m2
ls
ls

m3
m2
m2
unit
bh
bh
set
bh
m1
m3
m2
dn
ls

m3
m2
m2
unit
bh
bh
set
bh
m1
m3
m2
dn
ls

m3
m3
m2
m2
unit
bh
bh
set
bh
m1
m3
m2
ls

75,000.00
400,000.00
350,000.00
1,500,000.00
500.00
40,000.00
50,000.00
0.00

3,660,000.00
350,000.00
150,000.00
3,000,000.00
75,000.00
350,000.00
450,000.00
80,000.00
50,000.00
350,000.00
40,000.00
40,000.00
50,000.00

3,660,000.00
350,000.00
150,000.00
3,000,000.00
75,000.00
350,000.00
450,000.00
80,000.00
50,000.00
350,000.00
40,000.00
40,000.00
50,000.00

3,660,000.00
3,660,000.00
350,000.00
150,000.00
3,000,000.00
75,000.00
350,000.00
400,000.00
80,000.00
50,000.00
350,000.00
40,000.00
200,000.00

Grill G1 uk. 2.47 x 0.8 M / bh + kawat nyamuk equal Ona


Kusen bangkirai 6/15
0.07
m3
3,660,000.00
Grill bingkirai 4/4
26.88
m1
11,712.00
Mosquito screen
2.37
m2
99,000.00
Finishing Lazur
4.74
m2
40,000.00
Upah pasang
2.47
m1
75,000.00

75,000.00
400,000.00
350,000.00
0.00
0.00
146,000.00
50,000.00
0.00
1,768,516.85

1,768,516.85

488,039.04
5,347,608.00
0.00
3,000,000.00
1,350,000.00
350,000.00
450,000.00
400,000.00
182,400.00
26,056.80
1,371,648.00
240,000.00
50,000.00
13,255,751.84

13,255,751.84

488,039.04
3,130,008.00
950,400.00
3,000,000.00
1,350,000.00
350,000.00
450,000.00
400,000.00
152,000.00
26,056.80
1,118,208.00
240,000.00
50,000.00
11,704,711.84

11,704,711.84

247,708.80
1,204,813.44
2,029,174.00
1,231,200.00
0.00
150,000.00
350,000.00
400,000.00
0.00
0.00
26,056.80
1,043,328.00
200,000.00
6,882,281.04

6,882,281.04

258,513.12
314,818.56
234,748.80
189,696.00
185,250.00
1,183,026.48

1,183,026.48

M1
Grill G1 uk. 2.47 x 0.8 M / bh
Kusen bangkirai 6/15
Grill bingkirai 4/4
Mosquito screen
Finishing Lazur
Upah pasang

2.47

0.07
26.88
0.00
4.74
2.47

M1
Grill G2 uk. 1.85 x 0.5 M / bh
Kusen bangkirai 6/15
Grill bingkirai 4/4
Mosquito screen
Finishing Lazur
Upah pasang

m3
m1
m2
m2
m1

3,660,000.00
11,712.00
99,000.00
40,000.00
75,000.00

m3
m1
m2
m2
m1

3,660,000.00
11,712.00
99,000.00
40,000.00
75,000.00

185,781.60
147,571.20
0.00
88,800.00
138,750.00
560,902.80

1.85

1.85

948,277.68

383,918.09

Grill G2 uk. 1.85 x 0.5 M / bh + kawat nyamuk equal ona


Kusen bangkirai 6/15
0.05
m3
3,660,000.00
Grill bingkirai 4/4
12.60
m1
11,712.00
Mosquito screen
1.11
m2
99,000.00
Finishing Lazur
2.22
m2
40,000.00
Upah pasang
1.85
m1
75,000.00

M1

258,513.12
314,818.56
0.00
189,696.00
185,250.00
948,277.68

2.47

0.05
12.60
0.00
2.22
1.85

M1

478,958.09

560,902.80

303,190.70

185,781.60
147,571.20
109,890.00
88,800.00
138,750.00
670,792.80

670,792.80

362,590.70

DAFTAR MATERIAL

NO.

JENIS MATERIAL

SAT.

HARGA Rp.

A. BAHAN

KETERANGAN

20.0%

1 Tanah urug

30,000.00

2 Pasir urug

60,000.00

3 Limestone

33,000.00

4 Pasir pasang

66,000.00

5 Pasir beton

60,000.00

6 Batu kali

66,000.00

7 Batu karang bukit

30,000.00

8 Bata merah

bj

600.00

9 Bataco

bj

1,200.00

10 Roster

bj

0.00

11 Koral beton

54,000.00

12 Semen (PC) Gresik

zak

30,000.00

13 Besi beton

kg

4,800.00

14 Kawat beton

kg

7,200.00

15 Paku

kg

7,200.00

16 Kayu bekisting

960,000.00

17 Multiplek 9 mm

lbr

74,400.00

18 Plywood 6 mm

lbr

48,000.00

19 Triplek 9 mm

lbr

72,000.00

20 Multiplek 12 mm

lbr

91,200.00

21 Teakblock 12 mm

lbr

91,200.00

22 Usuk bambu

m1

23 Atap Genteng ABADI

bh

2,400.00
1,584.00

24 Balok Bingkirai

3,300,000.00

25 Papan bingkirai

3,900,000.00

26 Balok Bingkirai (oven)

3,660,000.00

27 Papan bingkirai (oven)

4,260,000.00

28 Balok Jati

13,800,000.00

29 Papan Jati

14,400,000.00

30 Balok Jati (oven)

14,160,000.00

31 Papan Jati (oven)

14,760,000.00

32 List Profil bingkirai 3/4

m1

7,200.00

33 List Profil bingkirai 4/4

m1

10,080.00

34 List bingkirai 3/4

m1

4,560.00

35 List bingkirai 1/3

m1

1,200.00

36 List bingkirai 2/3

m1

3,600.00

37 Timber Slate bingkirai 1,5/10

m2

72,000.00

38 Louvre bingkirai 1/4

m2

180,000.00

39 Marmer 30/30

m2

108,000.00

40 Marmer 40/40

m2

156,000.00

41 Marmer 50/50

m2

210,000.00

42 Terazo 50/50

m2

78,000.00

43 Terazo 40/40

m2

72,000.00

44 Terazo 30/30

m2

60,000.00

45 Keramik Roman Anti Slip 30 x 30

m2

60,000.00

46 Keramik 30 x 30 roman 3343

m2

36,000.00

47 Keramik Impero 30x30

m2

102,000.00

48 Palimanan 30x30

m2

138,000.00

49 Palimanan 35x35

m2

150,000.00

50 Paras silakarang random

m2

66,000.00

51 Floor Hardener

m2

30,000.00

52 AM grout

kg

7,200.00

53 Gypsum 9 mm

m2

24,000.00

54 Gypsum weatherproof 9 mm

m2

48,000.00

55 GRC

m2

24,000.00

56 List Gypsum 5/5

m1

10,800.00

57 List Gypsum 6/12

m1

58 Site clearence and soil striping

m2

18,000.00
6,000.00

59 Water proofing membrane ex Tremproof

m2

54,000.00

60 Water proofing ex baralistik

m2

52,800.00

61 Wire mesh u/ water proofing

m2

10,200.00

62 Waterproofing coating

m2

26,400.00

63 Cat Dind. Dalam Dulux ICI

m2

24,000.00

64 Cat Dind. Luar Texture Dulux ICI Weathersield

m2

48,000.00

65 Cat Dind. Luar Dulux ICI Pentalite

m2

27,000.00

66 Wood Stain Lazur DL 350

m2

48,000.00

67 Cat Besi

m2

21,000.00

68 Cat list plafond

m1

4,200.00

69 Polythelene sheet 0.5 mm

m2

7,200.00

70 Antitermite lentrek

m2

18,000.00

71 Kawat nyamuk ONA

m2

99,000.00

72 Pad Lock 22010 - 50

bh

105,600.00

73 Handle Steel Bars

bh

120,000.00

74 Engsel KEND 492

bh

22,800.00

75 Door Clooser CISA 60511 - 03

bh

1,146,000.00

76 Engsel KEND Sel 0015.US3

bh

79,800.00

77 Handle Kend HRE 08-19US3

m1

739,200.00

78 Engsel Kend Floor Hinges 60221

bh

1,444,800.00

79 Stoper Kend 015

bh

75,600.00

80 Lock CISA 52110-60W/double cylinder 08510 master key

bh

421,200.00

81 Bolt Kend 306 Brass Plated color 6"

bh

72,000.00

82 Lock Cisa 52110-60W/double cylinder 09214-6

bh

332,400.00

83 Hinges Hillaldam-Foldaside 340

bh

3,000,000.00

84 Hinges Kend Casement US5/CMT 003

m1

33,000.00

85 Lock SringKnife Kend 317 US3

bh

94,800.00

86 Raven RPM8 Door Seal

m1

6,000.00

87 Engsel Jendela Bouvent Kend Casement US5 (Antique)

bh

25,200.00

88 Grendel Jendela Spring Knip Kend 317.US3

bh

94,800.00

89 Brass Flush Handle

bh

180,000.00

90 Engsel Pintu KEND SEL 0020 US 32 D

bh

91 Flush Bolt KEND 306 US2 6D

set

92 Engsel Pintu KEND 492

45,600.00

93 Lock CISA 52110-60 W/Tumb turn cylinder 06653 Cutted

bh

444,000.00

94 Sliding Track Rail (Hillaldam S100 complete Bottom Rail)

bh

1,620,000.00

95 Sliding Track Rail (Plexy Glass bottom rail w/ball bearing rolleron)

bh

90,000.00

96 Handle (timber Knob Fixed)

bh

60,000.00

97 Kunci Roller Cath KEND 529

bh

517,200.00

98 Kunci Catch Riller US26 D

442,800.00

99 Kunci Catch 46216 w/ double cylinder 08510 Master key

182,400.00

100 Kunci YALE w/ Brass Thumb Turn Concealed on Window

bh

240,000.00

101 Angker + Meni

bh

2,400.00

102 Daun Pintu (steel dia.1,5, Steel plate 1 mm - Wire Mesh)

bh

1,200,000.00

103 DP (Galv. Medium dia. 2"+ BKR 3/15) uk. 135 x 178

bh

895,596.00

104 Sliding Track Rail (Steel L70.70.5+st.wheel 4" w/ball bearing)

bh

1,140,000.00

105 Daun jendela kaca

m2

300,000.00

106 Daun Jendela

m2

240,000.00

107 Daun pintu panil

m2

336,000.00

108 Daun Jendela Kaca Bovent

m2

264,000.00

109 Daun pintu blasted 5 mm uk. 80x200

bh

420,000.00

110 Daun Pintu Kaca tempered 5 mm 85x200

bh

2,400,000.00

111 Pintu Panil = kaca 5mm uk. 82x200

bh

442,800.00

112 Kusen Siku baja 70x70x5

m1

76,200.00

113 Daun Pintu Baja + Plat 1mm + Louvre

m2

1,422,000.00

114 Daun Pintu Baja

m2

1,422,000.00

115 Ventilasi Louvre Plat

454,200.00

116 Kolom tiang kelapa segi 8 t.4m

bh

360,000.00

117 Vanity table

m1

1,020,000.00

118 Kitchen table

m1

54,000.00
198,000.00

540,000.00

119 Cabinet Below Vanity

set

1,020,000.00

120 Kitchen cabinet

set

1,500,000.00

121 Rock Wool 5 cm

m2

60,000.00

122 Kain Super Capri

m2

33,000.00

123 Kain Raphael

m2

42,000.00

124 Pipa Galvanies dia. 2"

m1

48,000.00

125 Buis beton dia. 20 cm

m1

27,000.00

126 Buis beton dia. 30 cm

m1

36,000.00

127 Buis beton dia. 40 cm

m1

45,000.00

128 Buis beton dia. 50 cm

m1

54,000.00

129 Buis beton dia. 60 cm

m1

66,000.00

130 Buis beton dia. 80 cm

m1

69,000.00

131 Buis beton dia. 100 cm

m1

75,000.00

132 Pipa AW 6"

m1

180,000.00

133 Pipa AW 5"

m1

132,000.00

134 Pipa AW 4"

m1

72,000.00

135 Pipa AW 3"

m1

48,000.00

136 Pipa AW 2,5"

m1

39,000.00

137 Pipa AW 2"

m1

27,000.00

138 Pipa AW 1,5"

m1

21,000.00

139 Pipa AW 1"

m1

11,400.00

140 Pipa AW 3/4"

m1

9,900.00

141 Pipa AW 1/2"

m1

7,200.00

142 Gate/ball valve 6"

Unit

3,840,000.00

143 Gate/ball valve 5"

Unit

0.00

144 Gate/ball valve 4"

Unit

0.00

145 Gate/ball valve 3"

Unit

1,680,000.00

146 Gate/ball valve 2.5"

Unit

960,000.00

147 Gate/ball valve 2"

Unit

480,000.00

148 Gate/ball valve 1.5"

Unit

300,000.00

149 Gate/ball valve 1"

Unit

180,000.00

150 Gate/ball valve 3/4"

Unit

102,000.00

151 Gate/ball valve 1/2"

Unit

84,000.00

152 Check valve 6"

Unit

2,100,000.00

153 Check valve 5"

Unit

0.00

154 Check valve 4"

Unit

0.00

155 Check valve 3"

Unit

1,500,000.00

156 Check valve 2.5"

Unit

0.00

157 Check valve 2"

Unit

420,000.00

158 Check valve 1.5"

Unit

330,000.00

159 Check valve 1"

Unit

0.00

160 Check valve 3/4"

Unit

78,000.00

161 Check valve 1/2"

Unit

60,000.00

m
m
m
m
m

7,800.00
3,000.00
5,400.00
8,400.00
24,000.00

6 Upah pas. batu merah

m2

7,200.00

7 Upah pas. bataco

m2

5,400.00

8 Upah plesteran

m2

4,800.00

9 Upah acian
10 Upah cor beton
11 Upah besi beton

m2
m
kg

2,400.00
60,000.00
600.00

12 Upah bekisting
13 Upah pek. kap non ekspose

m2
m

12,000.00
540,000.00

14 Upah pek. Kayu

m1

4,800.00

15 Upah pek. usuk ekspose

m2

9,600.00

16 Upah pas. Teakblock

m2

3,000.00

17 Upah pas. skirting

m2

4,200.00

B. UPAH KERJA
1
2
3
4
5

Upah
Upah
Upah
Upah
Upah

Galian tanah
pemadatan
urugan kembali
urugan pasir
pas. batu kali

18 Upah pas. penutup plafond

m1

4,200.00

19 Upah pek. dedeleg

m1

4,800.00

20 Upah pas. list plafond

m1

3,600.00

21 Upah pas. rk. plafond gypsum

m2

6,000.00

22 Upah pas. lantai marmer

m2

12,000.00

23 Upah pas. plafond triplek

m2

10,800.00

24 Upah pas. lantai keramik

m2

4,800.00

25 Upah pas. Dinding keramik

m2

12,000.00

26 Upah Polished

m2

18,000.00

27 Upah pas. plint keramik


28 Upah sebar readymix

m1
m

3,600.00
30,000.00

29 Upah pas. lambresering

m2

9,000.00

30 Upah pas. Genteng

m2

6,000.00

You might also like