NIPCO Plc.
ds
HYDRO-TEST REPORT
REPORT NO: ECL/HT/0005
PIGGING
LINE FILLING
PRESSURE TESTING
LEAK TIGHTNESS TEST
&
DEWATERING OF
4 X 158m
Table of Contents
1.0
ABBREVIATIONS
2.0
PURPOSE
3.0
SCOPE
4.0
SYNOPSIS
5.0
REFERENCE DOCUMENTS
6.0
7.0
8.0
SAFETY
10
9.0
10
8.1
8.2
10
10
10.0
LINE FILLING
14
11.0
HYDROSTATIC TEST
14
10.1
10.2
STRENGTH TEST
LEAK TIGHTNESS TEST
15
16
12.0
RECTIFICATION OF DEFECTS
16
13.0
16
14.0
DOCUMENTATION
17
15.0
ATTACHMENT
18
1.0ABBREVIATIONS
The following abbreviations are used freely in this document;
Abbreviation
GGL
ECL
AG
ASME
DP
EG
MAWP
MAOP
PEP
RPM
SMYS
STP
Description
Green Gas Limited
Enikkom Construction Limited
Associated Gas
American Society of Mechanical Engineers
Design Pressure
Export Gas
Maximum Allowable Working Pressure
Maximum Allowable Operating Pressure
Project Execution Plan
Revolution per Minute
Specific Minimum Yield Stress
Specified Test Pressure
2.0 PURPOSE
The aim of hydrostatic test is to ascertain the integrity - strength and leak tightness of the
4,8 & 12 dia flow line/pipelines after fabrication, laying and installation by exerting a
specified pressure @ 147 Bar generated through water medium on the gas flowline/
pipelines.
3.0 SCOPE
This procedure covers the Flushing, Pigging, and Gauging and Hydrostatic Pressure testing
of gas pipelines, using corrosion inhibited water pumped from the dredged slot. Other
considerations like Dewatering, Drying and Nitrogen purging are for commissioning, while the
introduction of the Product into the line is Commissioning. These shall be covered under
separate work procedure
.
4.0 SYNOPSIS
This work shall be carried out in accordance with the requirement of GGL Standard
Construction Specification.
The test section shall be prepared prior to pressurizing by cleaning, gauging and filling. For
the gas pipeline to be accepted, it must sustain the Specified Test Pressure (STP) for a
defined period otherwise cause of failure shall be detected, rectified and the gas /pipeline retested in accordance with the stated pipeline specifications.
Prior to commencement of the test, sample of water to be used for filling, flushing and
pressure testing of the gas lines/pipeline shall be taken to GGL approved independent
laboratory, tested and report presented to the client representative for approval. GGL may
equally carry out independent testing of the water samples.
All necessary documentations as indicated in the specifications mentioned above, shall be
carried out at every stage of the activity. The detail test schedule which comprises the
proposed test dates, locations and the mobilization plan of the pressure testing crew shall be
prepared and be made available to GGL minimum of 3 days before planned test date.
5.0 REFERENCE DOCUMENTS
The following document will be referred to in determining the procedural requirement for
carrying out this work.
calibrated to the specified accuracy and their certificates made available to GGL for
confirmation, minimum of 3 days prior to commencement of the hydro test. Besides, the
calibration status for each of the instruments shall also be documented in the ECL Hydro test
Instrument Calibration Record a copy of which is attached, after which a tag reflecting the
calibration date, expiry date and serial number of instrument is posted on each of the
instruments.
At any point in time during the test, the actual position of a pig in the test section shall be
tracked by using the Volume, Speed and Flow rate of the driving medium (water) of the pig.
These 3 variables shall be determined from the flow meter installed across the water delivery
line.
The test packages, schedule and necessary punch list shall be made available to GGL for
review and concurrence prior to hydro testing the lines. At completion of every hydro test, all
items removed or repositioned for the purpose of the test shall be reinstated. Efforts shall be
made to ensure that the environment in which the test is being carried out is preserved.
Listed below are the major components of the test assemblies which must be tested and
certified by GGL before commencement of this activity.
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.
n.
o.
p.
q.
r.
s.
Flush Pump (Make KSB) 6 Suction & 5 Discharge outlet (up to 30 Bar Pressure)
Pressure Pump 2 HP Pump (Union Pump) (500 bar)
High Pressure hoses 206.86n /3000 psi
Mannesmann Compressor 15bar Maximum Pressure
Ingersoll-Rand XP 750 cfm Compressor
Flow meter Serial No. 96AWQ24432
12 Hight Density Criss Cross Foam Pig w/t Wire Brushes
12 Medium Density Criss Cross Foam Pig
Silver Gauging plates wt 7-9mm and OD 266mm
Pig Launcher/Receiver 12
ITT BARTON Pressure / Temperature Recorder -3000PSI, 150oF and 24Hr. 9 Days Wind
(S. # 435167, Model # 3452E)
Temperature Charts
Pressure Gauges Wika (0-160 Bar)
Pressure Guage (0-400 Bar)
Pressure testing header
Cork Valves
Flexible and high pressure flushing Hose and couplings
Water Tanks
Pressure relief Valve 0 155 Bar
Description
12 Dia Pipe OD
323.85mm
12 Dia Pipe ID
304.8mm
Length of 2
8,997 Meter
2,750 Meter
r2 h Or L
649.481m3
r2 h Or L
200.75m3
3.14*(0.152)2 *8997*1000
6
45 Degree Bend OD
323.85
45 Degree Bend ID
279
10
11
90 Degree Bend OD
323.85
12
90 Degree Bend ID
279
13
14
265.05
15
Design Pressure
98 Bar
16
147 Bar
17
2.3 Bar
18
2.5 Bar
19
1.5 Meter
20
23 Meter
21
36 Meter
22
2.15 Bar
23
3.5 Bar
24
1.07 Bar
25
5.52 Bar
26
7.07 Bar
9.525mm
22.53
22.53
(1)
where
f = friction head loss in feet of water per 100 feet of pipe (fth20/100 ft pipe)
c = Hazen-Williams roughness constant = 120
q = volume flow (m3/s) =0.31 @0.5m/s
dh = inside hydraulic diameter (m) =0.91
Actual Frictional Head loss 1087otal /b8.5mmH20 = 1.07bar
Table 6 Expected Total Back Pressure for different types of Pig / Line Filling
Pig
Types
Filling
Water
Foam
Pig
cup pig
Bi-di Pig
coated
foam pig
Brush
Pig
Filling
Water
Foam
Pig
cup pig
Bi-di Pig
coated
foam pig
Brush
Pig
DP
(Bar
g)
0
0.19
0.22
0.39
0.41
0.62
0
0.19
0.22
0.39
0.41
0.62
Static
Head
(bar)
Frictional
Back
Head
Pressure
Loss
(bar)
(bar)
1st Section
2.30
2.15
1.07
2.30
2.30
2.30
2.15
2.15
2.15
1.07
1.07
1.07
2.30
2.15
1.07
2.30
2.15
1.07
2nd Section
2.5
3.5
1.07
2.5
2.5
2.5
3.5
3.5
3.5
1.07
1.07
1.07
2.5
3.5
1.07
2.5
3.5
1.07
Safety Factor
2.5 Bar
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
Total Back
Pressure
(bar)
8.02
8.21
8.24
8.41
8.43
8.64
9.57
9.76
9.79
9.96
9.98
10.19
For this project the expected backpressure for pigging activities can be estimated to fluctuate
between 6 8 bars and additional 2.5 bar might be a safety factor taking into consideration heavy
wall sections of road crossings, HDD and bends.
Filling and Cleaning Pump Requirements.
The pump required for the operation must be rated to 1.25 times the expected backpressure.
Therefore the expected discharge pressure for the pump is approximately.
1.25 * 10.19 bar 12.74 bar
The discharge pressure rating for the pump recommended for this operation must be able to
discharge at a pressure capacity well above 12.74 bars.
The pig speed in a normal pigging operation should be within 0.5 1m/s if we assume a maximum
pig speed of 1m/s for this operation the equivalent flow rate would be = 8997/1 = 8997 s =2.5h
Flow rate = 649.481/2.5 = 4.32m3 /mins = 4.32*6.289= 27.01 BPM (1m3 = 6.289 Barrel)
Compressed Air Design
The pig speed should be between 2 8km for normal pig runs and 2 -4km/h for gauging plate
runs while using compressed air as a medium to propel the pig,
By assuming an average pig speed of 4km/h the air flow required
= (649.48 / 8,997) * 4,000 = 289 m3/h = V1
The required driving pressure when the pipeline is full of water must
Total Driving pressure required 12.74 bar = P1
Total Back pressure = 10.5 = P2
Using equation = P1*V1 = P2*V2
V2 = ( P1*V1 ) / P2 = ( 12.74 X 289 ) / 10.5
V2 = 350.65 m3/h
@ 1 m3 = 35.315 CFM
Compressed air requirement = 350 x 35.315 = 12,383ft3/h = 207 CFM
To give allowance for error in calculation 1.25 time the required air will be used = 259CFM
Therefore, a 650 CFM @ 15 Bar compressor should be adequate for the project. To achieve an
8km/hr pigging speed a second compressor would be added while a third would be on standby for
in case of breakdown.
The pig delivery time at average speed of 4-8km/hr less dawn 2 4 hours
1. HYDROSTATIC TEST PUMP DESIGN
The pressurizing pump required should be suitable to pressurize the test section at approximately
1 bar per minute. The volume required to inject to give 1bar pressure can be estimated using the
theoretical equation for volume change V per Pressure change P for pipeline with liquid under
pressures at constant temperature, disregarding effects of air absorption or free air in the line. The
Pressure-volume relationship considering elastic strain in the pipe and Compressibility of the water
is calculated thus
V=
D
1
( 1 ) + ) PV
( Et
B
2
DV/DP = V * [(D/ (E * t) (1 v) + C]
Where,
dV
dP
v
C
=
=
= Vr (Xm-Xout) /1000
= 1180 (12.8-0.33)/1000 = 14.72 kg/h
The expected remaining water in the pipeline after successful dewatering, assuming a water film
of 0.1 mm.
Remaining water = W= 3.14/4(D12-D22)*L*1000
W = 3.14/4(0.3142- 0.2952)* 8.997*1000 = kg water
=0.00908 x 8997
= 82 kg of water
The total drying time for this project T:
T
W/Vm
8.0 SAFETY
a. Care shall be taken to open or close any valve too quickly
b. Closed valves shall be electrically isolated or locked out (depending on the clients
operating system). The vents on the valve bodies should be opened where applicable.
c. Work area associated with the launcher and receiver test header traps shall be cordoned
off as a no-entry area for non-authorized persons.
d. Warning signs marked STAY CLEAR PRESSURE TESTING IN PROGRESS and hazards
tapes shall be installed.
e. An experienced Safety Officer will be available to ensure safety at all times during
pressure testing.
9.0 SELECTION AND PREPARATION OF TEST SECTION
7.1SELECTION OF TEST SECTION
The test section shall be the entire completed line or section of line on which there will be
no further work between the inlet and outlet. The elevation difference in the test section
shall not exceed 5% of the SMYS of the flow lines or 50m. Also, the inlet and outlet of the
test section shall be provided with suitable flanges to enable pigging and temporary
coupling of the test head and the pig launcher/receiver.
7.2PREPARATION OF THE TEST SECTION
NDT reports for all welds and repairs on the line to be hydro tested shall be cross checked
again by ENIKKOM CONSTRUCTION LIMITED QA/QC Engineer and confirmed by the GGL
Representative to ensure that all welds/repairs meet the minimum standard of
acceptability stated in DEP 61.40.20.30-Gen., before commencement of any of hydro test
activity.
Prior to pressure testing, each line shall be cleaned by flushing and Pigging to remove
construction debris and other loosely adhered material on the metal and ensure that the
line is free of deformation and obstructions.
These pre-test activities shall be
continuously carried out until the requirements of GGL are satisfied. The physical content
and color of the discharge water determines the level of cleanliness of the flow line.
Detailed procedure for the execution of each of the activities highlighted above is stated
as follows:
PROCEDURES
1. The launch and receiver trap dimension shall be
assessed and adjudged capable of accommodating the
pigs
2. All necessary equipment is available for the work
3. Ensure that Permit to Work and relevant permits are
obtained for the proposed test
4. Prior to the installation of the testing assemblies at each
end of The gas pipeline/, ensure each component of the
assemblies are thoroughly inspected and all measuring
instruments currently calibrated
5. Check and use competent personnel
6. Set up warning signs, danger signals, and safety
barricade about 20m away from the test locations.
7. Ensure no other work is permitted on the test section
during the period of the pressure testing.
8. Reemphasize as stated in the ENIKKOM CONSTRUCTION
LIMITED
Emergency
Procedure
in
ENIKKOM
CONSTRUCTION LIMITED PEP the actions and responses
of the pressure testing crew members in case of
emergency.
9. Establish and maintain walkie-talkie or mobile link
between the crew members
10. Define the boundaries of the test equipment sites with
safety hazard tapes.
ACTION PARTY
Project Engr
Test Supervisor/QC
Engr
Test Supervisor
Safety Officer
Field Engr/Test
Supervisor
Safety Officer
8.1.1 FLUSHING/PIGGING
11. Connect the flushing pump and accessories to
the pipeline/flow line in readiness for flushing.
12. Introduce water from the client approved source
corresponding to minimum of 2% of the section
volume, to wash away the foreign materials.
13. Repeat step 11 until the pipeline / flow line is
acceptably clean to the satisfaction of the GGL
Representative, for the first pig (bi directional
type) to be introduced.
14. Connect the pig trap/receiver together with the
throttling valve set -up at the discharge end of
the line prior to introduction of the first bidirectional pig.
15. Ensure the GGL Representative is present
before the commencement of any pigging
operation.
16. Alert the recording technician to get pig register
copy of which is attached and other necessary
documents ready and ensure the by-pass of the
bi directional pig is kept open before inserting
the pig.
17. Make necessary connections and drive the bidirectional pig by with water through the line to
be received into the pig receiver at the
discharge end.
18. As the bi directional pig moves in the line, its
speed shall be controlled within the range of
0.5m/s - 2.5m/s by adjusting the throttling valve
connected to the receiving end, in order to
ensure effective cleaning of the line.
19. Repeat step 16 and 17 using cleaning brush pig
installed in succession so long the volume of
the discharged material is not lesser than 5
liters. Notwithstanding, the pigging shall still be
done to the satisfaction of the GGL
Representative before proceeding to gauging.
20. Clear the immediate surroundings of the
discharge end of the line of debris received with
the pigs and dispose in accordance with
ENIKKOM
CONSTRUCTION
LIMITED
Waste
Management Procedure, A temporary piping
shall be fabricated to transport the waste water
from the test sections into the waste disposal
area.
8.1.2 GAUGING
21. When the test section has been accepted clean
by the Client
Representative, then the bidirectional pig with 2 sets of separate guiding
and sealing discs shall be fitted with one or two
aluminum gauging plate and located as stated
in section of the DEP 31.40.40.38 Gen. Ensure
the gauging plates are inspected by the GGL
Representative before driving them into the test
sections. The gauge pjlate is dimensioned to
the 95% of the smallest possible ID of the
pipeline.
22. After the inspection, the gauging pig shall be
introduced into the test section and driven
through the line to be received into the pig trap
at the discharge end.
23. Repeat step 17 as the gauging pig is being
driven through the test section.
24. At the emergence of the gauging pig from the
test section, the plate shall be inspected by the
Test supervisor and GGL Representative for
bending, notching and other irregularities as
specified in the above mentioned specification.
25. Photographic records of condition of the
aluminum gauging plate shall be kept after
each test
26. In situation where the aluminum gauging plates
do not meet the acceptance criteria in the
specification, the cause of the defect shall be
located, rectified and the gauging pig re-run
until it emerges in an acceptable condition.
27. In case any of the test pigs gets stuck in the
test section and cannot be removed by the
normal pumping pressure high density pigs
shall be used to unblock the line failing which
the line shall be cut to remove the pig. Then,
the defect shall be repaired in accordance with
appropriate construction specification and the
qualified ENIKKOM CONSTRUCTION LIMITED
Weld Repair procedure.
Test Supervisor /
Photographer
Field Engr/Test Supervisor /
Pressure Testing Technician
Field Engr/Pressure
Testing Technician
Field Engr/Pressure
Testing Technician /Helper
Field Engr/ Test Supervisor
Line Size
12Pipeline
Material
Specification
X52
Design Pressure
(barg)
98
33. Disconnect the filling pump and connect the high pressure
pump, hoses and the pressure testing manifold ready to
pressurize the line.
34. Double check the pressure-testing manifold to ensure all its
components are still in order using the pre- test checklist
copy of which is shown in appendix C.
35. Check again to ensure all warning signs, safety hazard
tapes and barricades are still in place.
36. Provide a canopy to shelter the pressure-testing header
before
pressurizing the pipe to prevent temperature
variation.
37. Commence pressurization by raising the pressure at
constant rate of 1bar per minute up to 30 bar or 20% of the
Specified Test Pressure (STP) for each test section.
38. During this period the graph of pressure (Y-axis ) against
water input volume shall be plotted at minimal 1 bar
interval
39. During this period, check thoroughly for leakage on all
exposed part of the test section and test manifold fitting
and connections.
40. After satisfactory completion of the 2hours pressure holding
period and leak check, raise the pressure at a constant rate
of 1 bar per minute up to 70% of the STP
41. During this period the volume and pressure readings should
be recorded at 10 minutes intervals until the 70% of the STP
Test Pressureure
Barg
147
Test Supervisor /
Pressure Testing
Tech.
Field Engr/Pressure
Testing Technician
Safety Officer
Field Engr/ Test
Supv/Pressure
Testing Technician
Pressure Testing
Technician
Test Supervisor /
Field Engineer
Field Engr/ Test
Supv/ Pressure
Testing Technician
Pressure Testing
Technician
Pressure Testing
Technician
is reached.
42. During this water pressure stabilization period accessible
flanges shall be checked again for small leaks. If any are
found,
the line shall be depressurized at the rate of 2
bar/min to 70bar
or to MAOP, whichever is lesser, prior
to bolt tightening
43. If no leak is found, the pressure shall be built up at the rate
of 0.5 bar/min to 95% of the STP and held for 30 minutes,
after which pressurization shall be continued to the STP of
the line.
1. STRENGTH TEST
44. After attainment of the STP specified in Section IV3 of the GGL Contract document the pressure shall
be held at this point for 1 hours.
45. During strength test the test pressure shall be
recorded continuously on the dead weight tester
readings and the air temperature recorded at
every 30 minutes.
46. The Pipe and ground temperature shall be recorded
at the beginning and the end of the 1 hour test
period, while the ambient temperature is recorded
continuously.
47. Ensure that the pressure is maintained at the STP
+/- 1 bar by bleeding or adding water as required.
48. If a leak is suspected, actions shall be taken as
stated in section 13.0 of this procedure to rectify it.
Afterwards, the strength test shall be repeated.
49. After satisfactory completion of the strength test,
disconnect the high pressure pump and blank off
all necessary connections. Ensure the STP is still
maintained
while
carrying
out
these
disconnections.
Pressure Testing
Technician
Field Engr/Pressure
Testing Technician
Pressure Testing
Technician
Field Engr / Test
Supervisor /
Pressure Testing
Technician
Pressure Testing
Technician
Field Engr/Pressure
Testing Technician
Field Engr/Pressure
Testing Technician
Field Engr/Pressure
Testing Technician
53. The pressure testing of the line shall end when the
chart is submitted and accepted by the GGL
Representative.
54. Ensure the ambient temperature and the pipeline
water temperature are recorded at the same time
as the pressure readings.
Field Engr/Test
Supervisor
Field Engr/Pressure
Testing Technician
the
GGL
Representative.
Field Engr /
Pressure Testing
Technician
Field Engr /
Pressure Testing
Technician
Field Engr/Test
Supvr
Field Engr/
Pressure Testing
Technician
Field Engr/
Pressure Testing
Technician
Field Engr/ Site
Supv.
Field Engr/ Site
Supv.
Field Engr/ Site
Supv.
Field Engr/ Site
Supv.
14.0 DOCUMENTATION
Records of all parameters mentioned in this procedure shall be kept during each operation.
Hydrostatic pressure test records shall be reviewed by GGL in the beginning, at the end and
at least once during the test.
The ENIKKOM CONSTRUCTION LIMITED Representative shall sign every recorder chart before
and after placing it on the recorder. For recorder charts taken during the hydrostatic
pressure, the GGL Representative shall sign them.
Upon successful completion of the test a Hydrostatic Test Certificate shall be completed
and signed by both the ENIKKOM CONSTRUCTION LIMITED and GGL representatives
(ECL/GGL) and backed up by original hand written test data of which photocopies is given to
the GGL representative.
A comprehensive hydrostatic report with general introduction including all relevant pipeline
data, and detailing shall be compiled for each test section and submitted to GGL. The
contents of this report, as a minimum, shall include all documents highlighted.14.0
Attachment.
15.0 ATTACHMENT
S. #
Description
Reference
1.
Pigging Record
Attachment # 01
2.
Attachment # 02
3.
Pressurizing Report
Attachment # 03
4.
Attachment # 04
5.
Attachment # 05
6.
Attachment # 06
7.
Attachment # 07
8.
Calibration Record
Attachment # 08
9.
Attachment # 09
10.
Check List
Attachment # 10
ATTACHMENT 1.0
REPORT NO: ECL/HT/0005/01
ENIKKOM CONSTRUCTION LIMITED
PIGGING RECORD
PROJECT:LAYING OF NATURAL GAS PIPE LINE NIPCO II TEST
DATE:10/05/2016
PIPE DATA
Pipeline Identification: 4DIA PIPELINE AT NIPCO LAND FROM (CH 0+ 0.00) TO (CH 0+158.46).
Pipe Diameter:4.5 Grade. W.T.:6.4mm Length:158m..
Location: NIPCO LAND
Activity/PhasePHASE II
PIG DATA
S/
N
DATE
10/5/16
PIG
TYPE
M.
Density
foam Pig.
PIG
LAUNCH
TIME
PIG
RECEIV
E TIME
PEAK
PRESSU
RE
14:45HRS
14:56H
R
2.0SSBA
R
ARRIVA
L
CONDIT
ION OF
PIG
Okay
VOLUME
OF
FOREIGN
MATERIAL
DISCHARG
E WITH PIG
Clean Water.
Propelling medium:WATER
REMARKS
OKAY
For ENIKKOM CONSTRUCTION LIMITED
LIMITED.
Name
Name.
Sign / Date..
Date
Sign /
ATTACHMENT 2.0
REPORT NO; ECL/HT/0005/02
ENIKKOM CONSTRUCTION LIMITED
LINE FILLING LOG
TIME
(hours)
10Min
PUMP
DISCHARGE
PRESSURE (bar)
1.0 Bar
CUMULATIVE WATER
VOLUME PUMPED
(m3)
1,281.1 Litres.
Total Volume
Pumped.
1,281.1 Litres
10/05/16
REMARKS
OKAY
Name
Name.
Sign / Date..
Date
Sign /
ATTACHMENT 3.0
REPORT NO; ECL/HT/0005/03
ENIKKOM CONSTRUCTION LIMITED
HYDROTESTING
Sheet 1 of 2
Project:LAYING OF NATURAL GAS PIPELINE, NIPCO PHASE II
Pipeline Identification: 4DIA PIPELINE AT NIPCO LAND FROM (CH 0+ 0.00) TO (CH 0+158.).
Pipe OD:4.5.. Pipe W.T6.4mm. Pipe Length95m..
Date of Hydro testing:08/05/16.....................................................
Initial Pipe Temperature at Pressurizing.34.3 oC, Time..15:16h
Initial Testing Pressure0bar, Final Testing Pressure.147.bar.
Pipe Temperature at 80% of Pressure.37.5 oC, Time.h.
Air Content..Nil..% of the line volume,
Test Pressure:147..bar
STRENGHT TEST
10/05/16
TIME
(hours)
15:13 15:14
PIPELINE PRESS.
(bar)
0 - 35
PIPELINE GUAGETEMP.
(o
C)
31.8
10/05/16
35-104
33.0
15MINS HOLD TO
15:50HRS.
15:50 15:51
104 140.5
33.0
10 MINS HOLD TO
16:05HRS.
16:03 16:04
140.5 - 148
32.1
DATE
10/05/16
10/05/16
60MINS HOLD TO
17:06HR
VISUAL INSPECTION
(Carried out at 80% of the strength test pressure)
Pipe Temperature at 80% of Test Pressure32.1 oC, Time15:51.. h
Result:
OKAY
.....
..
Sheet 2 of 2
LEAK TIGHTNESS TEST
DATE
TIME
(hours
)
P.PRESS.
GUAGE
@RECO
RDER
SIDE
(bar)
P.PRESS.
GUAGE
2
@RECO
RDER
SIDE
(bar)
GUAGE
PIPELIN
E TEMP.
( oC)
SURF
SOIL
INFRARE
D TEMP.
( oC)
AIR
INFRARED
TEMP.
( oC)
REMARK
10/5/16
10/5/16
10/5/16
10/5/16
10/5/16
10/5/16
10/5/16
11/5/16
11/5/16
11/5/16
11/5/16
11/5/16
11/5/16
11/5/16
11/5/16
11/5/16
11/5/16
11/5/16
11/5/16
11/5/16
11/5/16
17:06
18:06
19:06
20:06
21:06
22:06
23:06
00:06
01:06
02:06
03:06
04:06
05:06
06:06
07:06
08:06
09:06
10:06
11:06
12:06
13:06
148
148.5
148
147
147
146
148.2
147
147
146.5
145.2
144
144
145.5
144
144
144.5
144.5
144.5
144
143.5
143
142
141.5
141.6
142
142.3
144
144.5
145
30.4
28.2
27.2
26.0
24.8
23.5
22.0
21.5
21.5
1.5
21.0
21.0
22.0
22.0
22.5
26.8
30.2
33.8
35.2
39.0
145
144.5
144
144
143
142
142
142
143
144.5
145.0
26.6
25.9
25.7
25.0
23.9
23.2
22.1
22.2
22.0
21.7
21.5
21.5
20.8
20.4
23.8
24.0
32.1
34.5
39.0
39.4
25.7
25.6
24.5
24.0
22.7
22.6
20.2
19.8
19.6
19.5
19.5
19.3
19.0
19.1
22.7
30.0
28.2
28.8
29.5
32.2
11/5/16
11/5/16
11/5/16
11/5/16
COMMENT(S)
Name
Name.
Sign / Date..
Date
For REFLECT ENGINEERING SERVICES LTD
Name
Sign / Date..
ATTACHMENT 5.0
REPORT NO; ECL/HT/0003/05
Sign /
S/N
1
DATE
27/06/1
6
2&3
27/06/1
6
28/06/1
6
4
5
28/06/1
6
6
28/06/1
6
7&8
28/06/1
6
PIG
LAUNCH
TIME
20:23
PIG
RECEIVE
TIME
20:40
PEAK
PRESSUR
E(Bar)
2.7
ARRIVAL
CONDITION OF
PIG
Okay with
Much Water.
M.D Foam
Pig.
21:25
21:34
1.2
Little Water.
M.D Foam
Pig.
10:36
10:42
0.7
Okay with No
Water.
Coated
Foam Pig.
11:09
11:15
0.5
Okay with No
Water
M.D Foam
Pig.
13:12
13:20
1.0
No Water.
M.D Foam
Pig.
14:58
15:07
0.8
No Water.
PIG TYPE
Coated
Form Pig.
.
For ENIKKOM CONSTRUCTION LIMITED
LIMITED
Name
Name.
Sign / Date..
Date
Sign /
THIS IS TO CERTIFY
That the pipeline or flow line section described in this certificate was pressure tested in
accordance with the terms of the following Specifications:
Specification: 12 X 1.066 Km (CLASS 1 ASME B31.8)
Pipeline identification: 12DIA FROM SHAGAMU INTERCHANGE (KP27+972.20) TO CDK
(KP29+38.70)
Testing Location: SHAGAMU INTERCHANGE.
Pipe OD (mm): 323.85
Name
Name.
Sign / Date..
Date..
Sign /
ATTACHMENT 8.0
HYDROTEST INSTRUMENTS CALIBRATION RECORD
S/N
EQUIPMENT DESCRIPTION
MODEL/
SERIAL NO
CALIBRATION
DATE
EXPIRY
DATE
EQUIPMENT
RECALL DATE FOR
RECALIBRATION
Note: This record sheet shall be completed when all instruments to be used for hydro test of the
pipelines / flow lines have
been duly calibrated.
ATTACHMENT 9.0
ENIKKOM CONSTRUCTION LIMITED
GGL 12 X 50KM GAS PIPELINE PROJECT
GAUGE PLATE PHOTOGRAPHIC RECORD
S/N
PHOTOGRAPH
DESCRIPTION
PHOTOGRAPH
NO
PHOTOGRAPH
DATE
GAUGE PLATE
DIAMETER/
THICKNESS
REMARK
REC