Professional Documents
Culture Documents
An Important figure:-
If 1000Watt power consumes throughout an hour it is known as 1 Unit
It means if 1MW(1000kW) project runs for 100% of the time in a year it would ideally
generate “ 8.76 MU ”electricity.
1. Installed Hydro power capacity in India
In the year 2006-07 the percentage of installed hydro power was 26% of the total Installed power in India.
( Data Annexed)
(MW)
Year Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
1989-90 17586 17586 17666 17681 17886 17946 17948 17948 17948 17948 18031 18085
1990-91 18147 18152 18152 18152 18152 18280 18280 18395 18395 18395 18395 18443
1991-92 18443 18443 18443 18443 18575 18575 18593 18613 18613 18628 18632 18672
1992-93 18752 18752 18752 18752 19042 19132 19152 19163 19260 19340 19340 19355
1994-95 20224 20236 20238 20246 20311 20311 20311 20351 20351 20391 20506 20505
1995-96 20506 20506 20506 20506 20506 20506 20506 20506 20506 - 20506 20531
1996-97 20531 20531 20531 20542 20542 20542 20542 21162 21282 21402 21421 21471
1997-98 21645 21645 21694 21713 21773 21841 21841 21845 21862 21862 21862 21891
1998-99$ 21899 21959 22007 22007 22007 22007 22017 22017 22083 22083 22083 22443
1999-00$ 22443 22455 22663 22675 22737 22752 23025 23032 23182 23527 23529 23816
2000-01$ 23816 23816 23891 24412 24562 24712 24712 24712 24724 24746 24804 25142
2001-02$ 25182 25202 25203 25290 25313 25364 25574 25574 25574 25844 25859 26261
2002-03$ 26261 26261 26261 26267 26302 26402 26410 26560 26560 26660 26760 26910
2003-04$ 26910 27010 27010 27010 27010 27410 27410 27760 27885 28135 28860 29500
2004-05$ 29507 29507 29507 29632 29632 29682 29857 29912 30087 30142 30335 30936
2005-06$ 31136 31136 30995 31390 31745 31877 31877 32077 32077 32077 32277 32277
2006-07$ 32270 32270 32920 32935 33137 33294 33544 33544 33586 33836 33966 34476
2007-08$ 34581 34610 34610 34900 35294 35359 35557 35847 36072 36298 36298 36468
2008-09$ 37086 37211 37211 37336 37336 37375 37675 37825 37825 37945 38060 38060
Note : $ : Capacity figures relate to the end of month of the year stated. Source : Data as per Central
Statistical Organisation (CSO), Compiled by Indiastat.
In the year of 2006-07 the percentage of hydro power generation was only 17% of the total power
generation in India ( data annexed ).This poor contribution of hydro power surprise but
Shockingly We See that 2008-09 generation(112697MU) was below the 2006-07 generation figure of
113359 Million Units, even though the installed capacity at the end of 2006-07 was 34476 MW, about 3600
MW below the March 2009 installed capacity. Now look at the surprising Generation loss and under
performance of the HEP’s:-
Year Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Generation
Also a detail study of under performance has been done by “South Asia Network on Dams, Rivers and
People” (SANDRP) which shows the decreasing trend line of performance(power generation per MW
installed has been decreasing) and there is a fall about 20% in these sixteen years.
The fall in the trend line is clearly seen ( Detail study by “SANDRP” is attached ).
If one says that the low rainfall is the reason for this generation loss then it is to be cleared that the
period we are looking at , has generally seen above average national rainfall. Some figures of previous
rainfall are shown below.
1996 1154.6
1997 1220.2
1998 1226
1999 1111.5
2000 1026.9
2001 1075.4
2002 941.7
2003 1205.1
2004 1035.6
2005 1175.4
Since, 1 MW at 100% performance produces 8.76 MU. So, the ideal trend of performance should be linear.
(Straight line shows the linearity in the Generation as the function of Installed capacity.)
But in the graph between the actual generation vs installed capacity We can see that
According to the generation statistics from CEA the performance of Tehri dam has been decreasing
continuously . The table below shows the generation performance of Tehri dam in different time
periods. (Detail of data is annexed).
We can see that the production in the current year is continuously decreasing and is not fulfilling
its target anywhere . In the month of June-July surprisingly we see the great loss in generation in
comparison of last year.
One more point to be noticed that 1000 MW Tehri dam was programmed for total 2817 MU
electricity generation in the year 2008.
Ideally it should be 1000*8.76 = 8760 MU.
This clearly shows that even programmed efficiency of the project is only 32.15% (???)
Further it has produced 3138 MU in 2008 Which is due to surprising over performance of the
project in the month of July and august 2008 but on another side if we look at the performance
of June and July 2009 the generation is far low in spite of no big changes in programmed
capacity.
This all represent the great uncertainty and discrepancy in the performance of Tehri Dam.
Loharinag- Pala HEP is on the upstream of Bhagirathi and almost 35 Km. above the Maneri dam
There are 7-8 tributaries join the Bhagirathi between this 35 Km long stretch, hence the water
availability for this 600 MW project is much less than that of Maneri Bhali 1.
Also there were no studies have been done on Retreating Glacier in conjunction with water
availability and no study on the cumulative impact of these dams before the clearance of
Loharinag-Pala hydro project.
Study done by
Ganga Ahvaan
www.gangaahvaan.org