Professional Documents
Culture Documents
11.1
11.1.1
11.1.1.1
Definitions
In this specification the terms approved,' approval and required
mean approved by the Engineer. approval of the Engineer. and
required by the Engineer respectively.
11.1.1.2
11.1.2
11.1.2.1
11.1.2.2
Progress Report
The contractor shall submit to the Engineer on the first day of each
week, or at such longer periods as the Engineer may from time to time
direct, a progress report showing the current rate of progress and
progress during the previous period on all important items of each
section of the works.
11.1.3
Materials
11.1.3.1
Sources of Supply
The sources of supply of materials shall not be changed without prior
approval.
11.1.3.2
Rejected Materials
Rejected materials are to be removed promptly from the site.
S11/1
11.1.4
Safety
11.1.4.1
Standards
Safety precautions throughout the piling operations shall comply with
the requirements of the various Acts, Orders, Regulations and other
Statutory instruments for the provision and maintenance of safe
working conditions, and with BS 557.73 and BS 8004.
11.1.4.2
Life-Saving Appliances
The contractor shall provide and maintain on the site sufficient proper
and efficient life-saving appliances to the approval of the Engineer.
The appliances must be conspicuous and available for use at all times.
Site operatives shall be conversant with the use of safety equipment
and drills shall be carried out sufficiently frequently to ensure that all
necessary procedures can be correctly observed.
11.1.4.3
Diving
Diving operations shall be carried out in accordance with the
requirements of the relevant Acts, Orders, Regulations and other
statutory instruments.
Before any diving is undertaken the contractor shall supply the
Engineer with two copies of the code of signals to be employed, and
shall have a copy of the code prominently displayed adjacent to the
diving control station on the craft or structure from which any diving
operation takes place.
11.1.5
Ground Conditions
11.1.5.1
11.1.5.2
S11/2
Tolerances
11.1.6.1
Setting Out
Setting out of the main grid lines shall be carried out by the contractor.
The installation of marker pins at pile positions as required by the
contract shall be carried out from the main grid lines of the proposed
structure by the contractor. Prior to installation of the pile, the pile
position relative to the main grid lines shall be checked.
11.1.6.2
Position
For a pile cut off at or above ground level the maximum permitted
deviation of the pile centre from the centre-point shown on the setting
drawing shall be 75mm in any direction. An additional tolerance for a
pile head cut off below ground level will be permitted in accordance
with Clauses 11.1.6.3 and/or 11.1.6.4.
11.1.6.3
Verticality
At the commencement of installation, the pile, or pile-forming
equipment in the case of a driven pile, or the relevant equipment,
governing alignment in the case of the bored pile, shall be made
vertical to a tolerance of within 1 in 100. The maximum permitted
deviation of the finished pile from the vertical is 1 in 75.
11.1.6.4
Rake
As in Clause 11.1.6.3 the pile, or driving or other equipment governing
the direction and angle of rake shall be set to give the correct alignment
of the pile to within a tolerance of 1 in 50. The piling rig shall be set
and maintained to attain the required rake. The maximum permitted
deviation of the finished pile from the specified rake is 1 in 25 for piles
raking up to 1:6 and 1 in 15 for piles raking more than 1:6.
11.1.6.5
Tolerance Variations
In exceptional circumstances where these tolerances are difficult to
achieve, the tolerances of Clauses 11-1.6.3 and/or 11-1.6.4 may be
relaxed by the Engineer, subject to consideration of the implications of
such action.
11.1.6.6
S11/3
Piling Method
The contractor shall supply for approval all relevant details of the
method of piling and the plant he proposes to use. Any alternative
method to that specified shall be subjected to approval.
11.1.8
Piling Programme
The contractor shall inform the Engineer each day of the intended
programme of piling for the following day and shall give adequate
notice of his intention to work outside normal hours and at weekends.
11.1.9
Records
The contractor shall keep at least records as indicated by an asterisk in
Table 11.1.1 of the installation of each pile and any other information
the Engineer may require and shall submit two signed copies of these
records to the Engineer not later than noon of the next working day
after the pile was installed. The signed records will form a record of
the work.
Any unexpected driving or boring conditions reported in accordance
with other clauses of this Section of the Specifications shall be noted
briefly in the records.
11.1.10
11.1.10.1
11.1.10.2
11.1.10.3
Damage To Piles
S11/4
The contractor shall ensure that during the course of the work,
displacement or damage which would impair either performance or
durability does not occur to completed piles.
The contractor shall submit to the Engineer his proposed sequence and
timing for driving or boring piles, having regard to the avoidance of
damage to adjacent piles.
11.1.10.4
Temporary Support
The contractor shall ensure that where required, any permanently freestanding piles are temporarily braced or stayed immediately after
driving to prevent loosening of the piles in the ground and to ensure
that no damage resulting from oscillation, vibration or movement can
occur.
S11/5
Data
Contract
Pile reference
number
(location)
Pile type
Nominal crosssection
dimensions or
diameter
Nominal
diameter
of
under ream/base
Length of
preformed pile
Standing
groundwater
level from
direct
observation or
given site
investigation
data
Date and time of
driving,
redriving or
boring
Date of
concreting
Ground level at
pile position at
commencement
of installation of
pile
(commencing
surface)
Working level
on
which piling
base machine
stands
Continuou
s
Flight
Auger
Concrete
or Grout
Piles
Micropiles
Driven
Precast
Concrete,
Steel and
Timber
Piles
Driven
Segmental
Concrete
Piles
Driven
Segmental
Prestressed
Precast
Piles
Driven
Cast-InPlace
Concrete
Piles
Bored
Cast-InPlace
Concrete
Piles
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
S11/6
Data
Depth from
ground level at
pile position to
pile toe
Toe level
Pile head level
as constructed
Pile cut-off
level
Length of
temporary casing
Length of
permanent
casing
Type, weight.
drop and
mechanical
condition of
hammer and
equivalent
information for
other equipment
Number and type
of packing used
and type and
condition of
dolly used
during driving
of the pile
Set of pile or
pile tube in
millimetres per
3 blows or
number of blows
per 25mm of
penetration
Continuou
s
Flight
Auger
Concrete
or Grout
Piles
Micropiles
Driven
Precast
Concrete,
Steel and
Timber
Piles
Driven
Segmental
Concrete
Piles
Driven
Segmental
Prestressed
Precast
Piles
Driven
Cast-InPlace
Concrete
Piles
Bored
Cast-InPlace
Concrete
Piles
*
*
*
*
*
*
*
*
*
*
*
*
*
*
S11/7
Data
If required, the
sets taken at
intervals during
the last 3m of
driving
If required,
temporary
compression of
ground and pile
from time of a
marked increase
in driving
resistance until
pile reached its
final level
If required,
driving
resistance taken
at regular
intervals over
the last 3m of
driving
Soil samples
taken and in
situ tests
carried out
during pile
formation or
adjacent to pile
position
Length and
details of
reinforcement
Concrete mix
Continuou
s
Flight
Auger
Concrete
or Grout
Piles
Micropiles
Driven
Precast
Concrete,
Steel and
Timber
Piles
Driven
Segmental
Concrete
Piles
Driven
Segmental
Prestressed
Precast
Piles
Driven
Cast-InPlace
Concrete
Piles
Bored
Cast-InPlace
Concrete
Piles
Data
Driven
Precast
Driven
Segmental
Driven
Segmental
S11/8
Driven
Cast-In-
Bored
Cast-In-
Continuou
s
Micropiles
Concrete,
Steel and
Timber
Piles
Concrete
Piles
Prestressed
Precast
Piles
Place
Concrete
Piles
Place
Concrete
Piles
Flight
Auger
Concrete
or Grout
Piles
Volume of
concrete
supplied to pile
where this can
be measured in
practice
All information
regarding
obstructions
delays and other
interruption to
the sequence of
work
11.2
11.2.1
General
S11/9
Cement
11.2.2.1
Type of Cement
Cement shall be ordinary Portland, sulphate-resisting Portland, Portland
blast-furnace cement or rapid-hardening Portland cement unless
otherwise specified or approved. When forwarding his piling method
statement and programme to the Engineer, the contractor shall submit for
approval the type of cement, other than ordinary Portland cement, he
proposes to use. High alumina cement shall not be used.
11.2.2.2
11.2.2.3
11.2.3
Aggregate
11.2.3.1
Type of Aggregate
Aggregates shall consist of approved naturally occurring material unless
otherwise specified or ordered. The contractor shall inform the Engineer
of the source of supply of the aggregates before the commencement of
work and, at the request of the Engineer, provide evidence regarding
their properties and consistency.
Where shell is present in the aggregate, the content shall be limited as
shown in Table 11.2.1.
The total equivalent anhydrous sodium chloride content of the mix used
in steel-reinforced concrete whether arising from aggregates, water,
admixtures or any other source, shall not exceed 0.5% of the mass of
S11/10
TABLE 11.2.1
11.2.3.2
Storage of Aggregates
All aggregates brought to the site shall be free and kept free from
deleterious matter. Aggregates of different types and sizes shall be
stored separately in different hoppers or different stockpiles.
11.2.4
Water
11.2.4.1
Availability
If water for the works is not available from a public supply, approval
shall be obtained regarding the source of water.
11.2.4.2
Tests
When required by the Engineer, the contractor shall arrange for tests of
the water for the works to be carried out in accordance with BS 3148
before and during the progress of work.
11.2.5
Admixtures
Admixtures complying with BS 5075 may be used if approved and shall
be used as and when required.
S11/11
Concrete Mixes
11.2.6.1
Grade Designation
Grades of concrete shall be denoted by the characteristic 28 days test
cube strength in Newtons per square millimetre.
11.2.6.2
Mix
Concrete mixes shall be in accordance with Clause 11.2.6.3 (designed
mix) or Clause 11.2.6.4 (prescribed mix) and of grades 20, 25, 30, 40,
50, or 60 or BS 5328 or other grades approved appropriate to the work.
The free alkali content of the concrete mix shall be less than 3kg per
cubic metre of concrete and the alkali content shall be calculated from
the formula A = Ca/100, where A is the alkali content of the concrete
(kg/m3), C is the maximum expected Portland cement content of the
concrete (kg/m3), and a is the alkali content of Portland cement (%).
The latter percentage is to be the declared monthly mean alkali content
+0.1%.
Where low alkali sulphate-resisting cement to BS 4027 is specified, the
alkali content (equivalent sodium oxide) of the cement shall not exceed
0.6% by weight.
The contractor shall submit the slump factor he proposes for approval
before work commences. Neither trial mixes nor strength tests are
required for prescribed mixes.
The concrete shall have sufficient workability to enable it to be placed
and compacted by the methods used in forming the piles.
11.2.6.3
Designed Mix
When a designed mix is specified the contractor shall be responsible for
selecting the mix proportions to achieve the required strength and
workability, but the Engineer will be responsible for specifying the
minimum cement content and any other properties required to ensure
durability.
Designed mixes shall be in accordance with grades 20, 25 or 30 (for
cast-in-place piles) or grades, 40, 50 or 60 (for precast piles) of BS 5328.
Other grades may be approved if appropriate to the work. Complete
information on the mix and sources of aggregate for each grade of
S11/12
Piling Mix
Workability
Slump
Limits
Prescribed Mix
mm
Cement
kg/m3
Total
Aggregate
kg/m3
Percentage Sand in
Total Aggregate
Grading C
20
25
30
A
B
C
A
B
C
A
B
C
75 -150
30 -200
150 or over
75 -150
30 -200
150 or over
75 -150
100-200
150 or over
320
350
400
360
400
460
410
460
520
1840
1790
1790
1790
1740
1680
1750
1680
1600
37
40
40
37
40
40
37
40
40
Grading M
35
38
38
35
38
38
35
38
38
2.
3.
The weight of cement and dry aggregates are those which will
produce approximately one cubic metre of compacted concrete.
4.
5.
6.
S11/13
7.
11.2.6.4
Prescribed Mix
When a prescribed mix is specified, the Engineer will specify the mix
proportions and the Contractor shall undertake to provide a properly
mixed concrete containing the constituents in the specified proportions.
Prescribed mixes for cast-in-place piling shall be in accordance with
Table 11.2.2. This table is applicable to concrete for use in cast-in-place
piling, where high workability is essential and where the use of internal
vibrators is precluded.
11.2.6.5
Durability
The piles exposed to potentially aggressive ground or groundwater,
approved measures shall be taken to ensure durability. Reference should
be made to Building Research Establishment Digest 250 relating to
sulphate attack.
11.2.6.6
11.2.7
Trial Mixes
11.2.7.1
General
When designed mixes are specified, trial mixes shall be prepared for
each grade of concrete in accordance with BS 1881, unless there are
existing data acceptable to the Engineer showing that the proposed mix
proportions and manufacture will produce a concrete of the strength and
quality required, having adequate workability for compaction by the
method to be used in placing.
11.2.7.2
S11/14
11.2.7.4
Workability
The workability of each batch of the trial mixes shall be determined by
the slump test as described in BS 1881 or by an alternative approved
method.
11.2.7.5
Standard of Acceptance
Unless other acceptance criteria are specified or approved, the trial mix
proportions will be regarded as satisfactory if the compliance
requirements of BS 5328 are met in relation to characteristic strength.
11.2.7.6
11.2.8
11.2.8.1
Sampling
Concrete of the piles shall be sampled in accordance with BS 1881.
11.2.8.2
Workability
The workability of concrete shall be determined by the slump test as
described in BS 1881 or by an alternative approved method.
11.2.8.3
S11/15
For each grade of concrete four cubes shall be made from a single batch
when required for each 50m3 of concrete or part thereof in each days
work. The cubes shall be made, cured and tested in accordance with BS
1881 or as otherwise approved. Testing shall be carried out by an
independent and approved laboratory. One cube shall be tested at an age
of 7 days, two at 28 days, and one cube shall be held in reserve for
further testing if required. Alternatively, cubes may be tested in
accordance with an approved accelerated testing regime. The contractor
shall submit certified copies of the results of all tests to the Engineer.
11.2.8.4
Standard Of Acceptance
The standard of acceptance of the works cubes shall be in accordance
with BS 5328 or as otherwise approved. Where the contract is a small
one and of short duration (less than 28 days) the contractor shall submit
for approval an alternative standard of acceptance before the
commencement of work.
11.2.8.5
Records Of Tests
The contractor shall keep a detailed record of the results of all tests on
concrete and concrete materials. Each test shall be clearly identified
with the piles to which it relates.
11.2.9
Batching Concrete
11.2.9.1
General
Facilities shall be provided for the Engineer to inspect the concrete
mixing plant or plants when requested.
Unless otherwise specified the requirements in Clauses 11.2.9.2, 11.2.9.3
and 11.2.9.4 shall be met.
11-2.9.2
11.2.9.3
Tolerance In Weights
The weights of the quantities of each size of aggregate and of cement
shall be within 2% of the respective weights per batch after due
allowance has been made for the presence of free water in the
aggregates, which shall be determined by the contractor by an approved
method.
S11/16
11.2.9.4
11.2.10
Mixing Concrete
11.2.10.1
Type Of Mixer
The mixer shall be of the batch type, unless otherwise approved, and
shall have been manufactured in accordance with BS 1305 or shown by
tests in accordance with BS 3963 to have mixing performance within the
limits of Table 6 of BS 1305.
11.2.10.2
11.2.10.3
Cleaning Of Mixers
Mixers which have been out of use more than 30 minutes shall be
thoroughly cleaned before another batch of concrete is mixed. Unless
otherwise specified by the Engineer, the first batch of concrete through a
mixer shall contain the normal batch quantity of cement and sand, but
only two thirds of the normal quantity of coarse aggregate. Mixing plant
shall be cleaned thoroughly between the mixing of different types of
cement.
11.2.10.4
Minimum Temperature
The temperature of fresh concrete shall not be allowed to fall below 3oC.
No frozen material or materials containing ice shall be used. In cold
weather when the ambient air temperature is less than 5oC, the heads of
newly cast piles are to be covered to protect them against freezing unless
the final cut-off level is least 0.25m below the final head level as cast.
Where a pile is cast in frozen ground, appropriate precautions shall be
taken to protect any section of the pile in contact with the frozen soil
where this occurs below the cut-off level. In the construction of precast
piles the requirements of BS 5328 shall be observed.
11.2.11
Transporting Concrete
11.2.11.1
Method Of Transporting
S11/17
Pumping Concrete
Pumped concrete complying with this Specification may be used. The
methods employed in its use shall be subject to approval.
11.2.12
Ready-Mixed Concrete
11.2.12.1
Conditions Of Use
Subject to approval the contractor may use ready-mixed concrete in
accordance with BS 5328. Approval shall be obtained for each proposed
use of ready-mixed concrete in different sections of the works and for
each different mix, which shall comply with this specification.
11.2.12.2
Mixing Plant
Unless otherwise agreed by the Engineer, truck mixer units and their
mixing and discharge performance shall comply with the requirements
of BS 4251.
11.2.13
Steel Reinforcement
11.2.13.1
Condition
Steel reinforcement shall be stored in clean conditions. It shall be clean,
and free from loose rust and loose mill scale at the time of fixing in
position and subsequent concreting.
11.2.13.2
Grade
The grade of steel shall be as specified.
11.2.13.3
Bending Of Reinforcement
No reinforcement shall be bent at a temperature lower than 5oC without
prior approval. Before bending, reinforcement may be warmed to a
temperature not exceeding 100oC. If reinforcement already cast into
concrete has to be bent, the internal radius of the bend shall be not less
than twice the diameter of bars of mild steel or three times the diameter
of bars of high-yield steel.
S11/18
11.2.13.4
Placing Of Reinforcement
Reinforcement in the form of a cage shall be assembled with additional
support, such as spreader forks and lacings, necessary to form a cage
which can be lifted and placed without permanent distortion.
Intersecting bars shall be fixed together by approved means. Hoops,
links or helical reinforcement shall fit closely around the main
longitudinal bars and be bound to them by approved wire, the ends of
which shall be turned into the interior of the pile. Reinforcement shall
be placed and maintained in position to provide the specified projection
of reinforcement above the final cut-off level.
The cover to all reinforcement in cast-in-place piles shall be not less than
40mm unless otherwise approved. Spacers shall be designed and
manufactured using durable materials which will not lead to corrosion of
the reinforcement or spalling of the concrete cover. For precast piles,
cover shall be in accordance with BS 8110.
11.2.13.5
Welding Of Reinforcement
Welded joints and welding procedures shall be carried out in accordance
with BS 5135
11.3
11.3.1
General
All materials and work shall be in accordance with Sections 11.1 and
11.2 of this specification, the Particular Specification and this section,
except where there may be conflict of requirements, in which case those
in the Particular Specification and this section shall take precedence.
11.3.2
Ordering Of Piles
The contractor shall order the piles to suit the construction programme
and seek the Engineers approval before placing the order. When
preliminary piles are specified the approval for the piles for the main
work will not necessarily be given until the results of the driving and
tests on preliminary piles have been received and evaluated.
11.3.3
Particular Specification
11.3.3.1
Concrete
The type of cement, type of aggregate and mixer shall be as per Section
11.2 - General Requirements for Concrete Piles.
The grade of concrete shall be as shown in the drawings.
S11/19
11.3.3.2
11.3.3.3
11.3.3.4
Driving Resistance
Unless otherwise specified in the contract piles shall be driven to
achieve an ultimate static resistance not less than twice the working load
shown in the contract.
Before commencement of pile driving the contractor shall submit pile
driving methodology, equipment and details to the Engineer for his
approval.
11.3.3.5
Depth of Penetration
If the Engineer is not satisfied with the depth of penetration irrespective
of the driving resistance being attained, the Engineer shall specify the
penetration and the contractor shall carry on driving by increasing the
driving resistance which may include a change to a heavier hammer.
Driving shall be continued until the desired depth of penetration has
been attained.
11.3.3.6
After removal of the test load, the residual settlement under the
working load and under twice the working load exceeds 6mm
and 3mm respectively;
OR
(ii)
S11/20
(iii)
(iv)
11.3.3.7
The settlement under the working load exceeds 10% of the least
width of the pile.
Pile Shoes
Pile shoes shall be as shown in the drawings and shall comply with the
following as relevant :(i)
Chilled - hardened cast iron shoes as used for making grey iron
casting to BS 1452, Grade 10;
(ii)
(iii)
Mild steel straps cast into the shoes shall be as shown in the drawings.
Rock shoes where required shall consist of wrought iron shoes and mild
steel straps cast into chilled - hardened cast iron blocks, as shown in
the drawings.
11.3.3.8
11.3.4
11.3.4.1
British Standards
In the manufacture of jointed precast concrete segmental piles,
fabricated steel components shall comply with BS 3100 grade A, and
ductile iron components with BS 2789.
11.3.4.2
Pile Joints
The joints shall be close-fitting face to face and the locking method shall
be such as to hold the faces in intimate contact. The design and
S11/21
Pile Toes
Pile toes shall be constructed so as to ensure that damage is not caused to
the pile during installations. Where positional fixity is required on an
inclined rock surface or in other circumstances, an approved shoe may
be required (see Clause 11.4.3.)
11.3.4.4
11.3.5
11.3.6
Reinforcement
The main longitudinal reinforcing bars shall be in one continuous length.
Splicing of bars will not be permitted except at element ends.
S11/22
Formwork
If a pile is constructed with a shaped point or shoe, then the end of the
pile shall be symmetrical about the longitudinal axis of the pile.
Holes for handling or pitching, where provided in the pile, shall be lined
with steel tubes; alternatively, approved inserts may be cast in.
Formwork shall be robust, clean and so constructed as to prevent loss of
grout or aggregate from the wet concrete and ensure the production of
uniform pile sections. The piles are to be removed from the formwork
carefully so as to prevent damage.
11-3.8
Pile Quality
If the piles are manufactured at a precasting works away from the site, a
certificate of quality from the pile manufacturer shall be provided to the
Engineer when required stating that the requirements of this
specification have been fulfilled during manufacture.
11.3.8.1
Concrete
11.3.8.1.1
Compacting concrete
Unless otherwise agreed by the Engineer, concrete shall be compacted
with the assistance of vibrators. Internal vibrators shall be capable of
producing not less than 150Hz and external vibrators not less than
50Hz. Internal vibrators shall operate not closer than 75mm to
shuttering.
Vibrators shall be operated in such a manner that neither segregation of
the concrete mix constituents nor displacement of reinforcement
occurs.
11.3.8.1.2
S11/23
Type Of Cement
Ordinary Portland
Sulphate-resisting Portland
Portland blast-furnace
Super-sulphated
Rapid hardening Portland
4 days
4 days
4 days
4 days
4 days
Table 11-3.1
11.3.8.2
Prestressing
11.3.8.2.1
General
Tensioning shall be carried out only when the Engineer is present,
unless otherwise approved. In cases where piles are manufactured off
the site, the contractor shall ensure that the Engineer is given adequate
notice and every facility for inspecting the manufacturing process.
Prestressing operations shall be carried out only under the direction of
an experienced and competent supervisor. All personnel operating the
stressing equipment shall have been trained in its use.
S11/24
Concrete strength
The contractor shall cast sufficient cubes, cured in the same manner as
the piles, to be able to demonstrate by testing two cubes at a time, with
approved intervals between pairs of cubes, that the specified transfer
strength of the concrete has been reached.
Unless otherwise permitted, concrete shall not be stressed until two test
cubes attain the specified transfer strength.
11.3.8.2.3
Records
The contractor shall keep detailed records of times of tensioning,
measured extensions, pressure gauge readings or load cell readings and
the amount of pull-in at each anchorage. Copies of these records shall
be supplied to the Engineer within such reasonable time from
completion of each tensioning operation as may be required, and in any
case not later than noon on the following working day.
Grouting procedure
Grout shall be mixed for a minimum of 2 minutes and until a uniform
consistency is obtained.
Ducts shall not be grouted when the air temperature in the shade is
lower than 3oC.
Before grouting is started all ducts shall be thoroughly cleaned by
means of compressed air.
Grout shall be injected near the lowest point in the duct in one
continuous operation and allowed to flow from the outlet until the
consistency is equivalent to that of the grout being injected.
S11/25
Grout
Unless otherwise directed or agreed by the Engineer.
11.3.8.3
(a)
(b)
(c)
Records
The contractor shall keep records of grouting, including the date, the
proportions of the grout and any admixtures used, the pressure, details
of interruption and topping up required. Copies of these records shall
be supplied to the Engineer within such reasonable time after
completion of each grouting operation as may be required, and in any
case not later than noon on the following working day.
11.3.9
Marking Of Piles
(a)
(b)
S11/26
11.3.11
Driving Piles
11.3.11.1
Strength of piles
Piles shall not be driven until the concrete has achieved the specified
characteristic strength.
11.3.11.2
S11/27
11.3.11.3
11.3.11.4
Length Of Piles
The length of pile supplied to be driven in any position and any
additional lengths to be added during driving shall be approved prior to
the commencement of pile-driving. During the execution of the works
any changes to the supplied lengths shall be approved.
11.3.11.5
S11/28
Final Set
When driving to a set criterion, the final set of each pile shall be
recorded either as the penetration in millimetres per 10 blows or as the
number of blows required to produce a penetration of 25mm (see Table
11-1.1.).
When a final set is being measured, the following requirements shall be
met:-
11.3.11.7
i)
ii)
iii)
The hammer blow shall be in line with the pile axis and the
impact surfaces shall be flat and at right angles to the pile and
hammer axis;
iv)
v)
11.3.11.8
Preboring
S11/29
Jetting
Jetting shall be carried out only when the contractors detailed
proposals have been approved.
11.3.12
11.3.12.1
11.3.12.2
Lengthening Of Piles
Where piles are required to be driven to depths exceeding those
expected, leaving insufficient projection for bonding into the following
works, the piles shall be extended or replaced as required by the
Engineer using approved materials and methods.
11.3.13
11.4
11.4.1
Integrity-Testing Of Piles
S11/30
11.4.1.1
General
Integrity-testing of piles is designed to give information about the
physical dimensions, continuity and consistency of materials used in
piles, and not to give direct information about the performance of piles
under the conditions of loading. The methods available are normally
applied to preformed concrete piles made in a single length, to steel
piles and to cast-in-place concrete piles. The constituent material of
any pile should have a large differential modulus of elasticity
compared with the ground in which it is embedded.
This type of testing will not be regarded as a replacement for static load
testing, but as a source of supplementary information.
There is normally a limit to the length/diameter ratio of pile which can
be successfully and fully investigated in this way, depending on the
ground conditions.
In the event that any anomaly is found in the results of such testing, the
Engineer may call for further testing to be carried out or for the
relevant part of the pile to be exposed where practicable for inspection,
in order to investigate the cause, nature and extent of the anomaly and
whether the pile is satisfactory for its intended use.
11.4.1.2
Particular specification
The following matters are, where appropriate, described in the
Particular Specification:a)
b)
c)
d)
e)
11.4.1.3
Method of testing
Where integrity-testing is called for but the method is not specified, the
method to be adopted shall be approved by the Engineer and shall be
one of the following:a)
b)
c)
S11/31
11.4.1.4
11.4.1.5
11.4.1.6
11.4.1.7
Interpretation of tests
The interpretation of tests shall be carried out by competent persons
and the full test results and findings shall normally be given to the
Engineer within 3 days of the completion of each phase of testing.
Full details of the ground conditions, pile dimensions and construction
method shall be made available to the specialist firm when required in
order to facilitate interpretation of the tests.
11.4.2
Dynamic Pile-Testing
11.4.2.1
General
Dynamic load test for the preliminary test pile shall include:(i)
(ii)
Dynamic load test for a specified no. of working piles shall include
monitoring of pile response when the pile is subjected to an impact
provided by the pile driving hammer after completion of driving.
S11/32
11.4.2.2
Measurements
Measurements of strain, force and acceleration shall be carried out
close to the pile head, such parameters shall be measured continuously
with time and stored on electronic data capture units with the capability
of producing graphs of measured:(i)
(ii)
(iii)
(iv)
Force - time;
Acceleration - time;
Velocity - time;
Displacement - time;
(ii)
(iii) The force and velocity shall be output on a display unit during
measurements;
(iv) The product of force and velocity shall be integrated over time to
obtain the energy transferred to the top of the pile. The energy
shall be continuously zeroed except during impact;
(v)
11.4.2.4
Measurement devices
All instruments for measurements and all equipment for receiving and
processing data shall be suitable for the purpose and to the Engineers
approval. Equipment required to be attached to the pile shall be
appropriately positioned and fixed to the approval of the Engineer. No
S11/33
(ii)
Hammer
The hammer and all site equipment shall be capable of delivering an
impact force sufficient to mobilise the equivalent specified test load
without injury to the pile.
11.4.2-6
11.4.2.7
Personnel
All personnel involved in Dynamic Load Testing shall be persons
experienced in the task.
11.4.2.8
Preliminary results
S11/34
Detailed Report
Subsequently a full detail report shall be given to the Engineer in
triplicate within 3 days of the completion of testing for all the piles.
These shall include the following:(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
(ix)
(x)
(xi)
(xii)
(xiii)
(xiv)
(xv)
11.5
PILE TEST
11.5.1
Definition
11.5.1.1
Test Pile
Any pile to which a test is, or is to be, applied.
11.5.1.2
Types of Pile
S11/35
Kentledge
The dead weight used in a loading test.
11.5.1.4
11.5.1.5
11.6
S11/36
In all cases the contractor shall ensure that when the hydraulic jack and
load measuring device are mounted on the plate the whole system will be
stable up to the maximum load to be applied.
The hydraulic jack, pump, hoses, pipes, couplings and other apparatus to
be operated under hydraulic pressure shall be capable of withstanding a
test pressure of 1 1/2 times the maximum working pressure without
leakage.
11.6
11.6.1
General
Construction of a preliminary pile which is to be tested.
11.6.2
Notice Of Construction
The S.O. shall be given in at least forty eight (48) hours notice of
commencement of construction of preliminary pile which is to be test
loaded.
11.6.3
Method Of Construction
Each preliminary test pile shall be constructed in a manner similar to that
to be used for the construction of the working piles, by the use of similar
equipment and materials. Any variation will only be permitted with the
prior approval of the Engineer.
11.6.4
Boring Record
For each preliminary pile which is to be test loaded, a full record of the
soils encountered during boring, or of the progress during boring shall be
made and given to the Engineer as required.
In bored piles where the Engineer requires soil samples to be taken, or in
situ tests to be made, the contractor shall give results of such tests to the
Engineer without delay.
11.6.5
11.6.6
Pile Head
S11/37
The pile head or cap shall be formed to give a plane surface which is
normal to the axis of the pile, sufficiently large to accommodate the load
applying apparatus and settlement measuring equipment and shall be
adequately reinforced or protected to prevent damage due to the
concentrated application of load from the loading equipment.
The joint between a pile and pile cap shall be constructed in such a
manner as to provide equal strength with the pile section. The pile cap
shall be concentric with the test pile.
A sufficient clear space shall be made under any part of the cap projecting
beyond the section of the pile so that at the maximum anticipated
settlement, load is not transmitted to the ground except through the pile.
11.6.7
Cut-Off Level
Where the pile cap is formed above the cut-off level of the working piles
in soils which would influence the load bearing capacity of the pile, a
sleeve shall be left in place during testing to eliminate friction which
would not arise in working piles. Alternatively if the friction above the
designed cut-off level can be calculated with reasonable accuracy, then
with the approval of the Engineer a sleeve need not be used, but the
calculated friction must be taken into account in assessing the load being
applied to the pile.
11.7
11.8
CONCRETE TESTING
Three test cubes shall be made from the concrete or grout used in the
preliminary test pile and from the concrete used for building up a working
pile as in Preparation of a Working Pile which is to be Tested (Clause
11.4 above). If a concrete cap is cast separately from a preliminary pile or
a working pile or if concrete is used for building up a working pile a
further three cubes shall be made and tested in accordance with BS. 1881.
The pile test shall not be commenced until the strength of the cube taken
from the pile exceeds twice the average direct stress in any pile section
under the maximum required test load and the strength of the cubes taken
S11/38
from the cap exceeds twice the average stress at any point in the cap under
the same load. Variation of procedure will only be permitted if expressly
agreed by the Engineer.
11.9
REACTION SYSTEMS
11.9.1
11.9.2
11.9.3
Kentledge
Where kentledge is to be used, this shall be supported on cribwork
disposed around the plate. The bearing pressure under supporting cribs
shall be such as to ensure stability of the kentledge stack. This
specification does not cover the use of kentledge carried directly on the
pile, and this method of loading shall not be used except at the express
direction of the Engineer.
11.10
11.10.1
11.10.2
Measurement Of Load
The load shall be measured by a load measuring device and also by means
of a calibrated pressure gauge included in the hydraulic system of the
S11/39
jack. The load as shown on the load measuring device shall be recorded.
The calibrated pressure gauge is required to check for gross error and
shall also be recorded. The load measuring device shall be calibrated
every twelve months or whenever adjustments are made to the device, or
at intervals appropriate to the type of equipment. The pressure gauge and
hydraulic jack shall be calibrated together. Certificates of calibration
shall be produced for the Engineers inspection. The Engineers
agreement shall be obtained in writing before any modification of this
procedure shall be used.
11.10.3
Adjustability Of Equipment
The equipment shall be capable of adjustment throughout the test to
obtain a smooth increase of load or to maintain each load constant at the
required stages of a maintained loading test.
11.11
11.11.1
Methods
In a maintained load test, movement of the pile load head shall be
measured by one of the methods (i), (ii), (iii) or (iv) below in the case
of vertical piles or by one of the methods (ii), (iii) or (iv) in the case of
raking piles as required by the Engineer.
(i)
Levelling method
By optical or other levelling method by reference to an external
datum.
(ii)
Where a level and staff are used the level and scale of the staff
shall be chosen to enable readings to be made to an accuracy of
0.5mm (1/50). A scale attached to the pile of pile cap may be
used instead of a levelling staff. A datum shall be established on
a permanent object or other well founded structure or deep datum
point. The datum shall be situated so that only one setting up of
level is needed. The datum shall be duplicated. Neither datum
shall be affected by the test loading nor by other operations in the
site.
S11/40
Other Methods
Any other approved method.
11.11.2
11.12
11.12.1
11.12.2
Prevention Of Disturbance
Construction equipment and persons who are not involved in the testing
process shall be kept at a sufficient distance from the test to avoid
disturbance of the measurement apparatus.
11.12.3
Notice of Test
The S.O. shall be given not less than 24 hours notice of intention to
commence the test.
11.12.4
Records
During the progress of the test, the testing equipment and all records of
the test shall be available as required for inspection by the Engineer's
representative.
11.12.5
Test Piles
S11/41
11.12.7
Supervision
The contractor shall provide an experienced supervisor to be present full
time during the duration of the pile tests to ensure that the loading
sequence and method of taking settlement reading are strictly followed
and that the true load is maintained at all times. Pile tests shall be carried
out only in the presence of the Engineer or his representative.
11.13
TEST PROCEDURE
11.13.1
S11/42
11.13.2
(ii)
(iii)
A total penetration of the pile base equal to ten per cent (10%)
of the base diameter has been reached in the test or some other
greater value of penetration that the Engineer shall require.
The load shall then be reduced in five (5) approximately equal stages to
zero load, recording penetration and load at each stage and at zero load.
11.13.3
11.13.4
Records Confidential
All pile test records shall be considered confidential and shall not be
disclosed by the contractor to any third party without the express
permission in writing of the Employer.
11.13.5
S11/43
The contractor shall carry out load tests on working piles to be selected
by the Engineer. A provisional number is given in the Bills of
Quantities.
11.14
(ii)
the total pile movement exceeds 6mm under the working load,
or
(iii)
the total pile movement exceeds 20mm under the maximum test
load. (The maximum test load shall be 2.5 times the working
load)
11.15.1
Scope Of Work
11.15.1.1
The contractor is to design the pile length and construct the piles in
accordance with the requirements contained herewith.
11.16
DESIGN CODES
The contractor's proposed design has to comply in all relevant aspects
with British Standard BS 8004 : 1986 "Code of Practice for
Foundations", and where relevant British Standard CP 114. "Structural
Use of Reinforced Concrete in Buildings".
The Construction
Specification shall be in accordance with the Institution of Civil
Engineers, London (1978) "Piling, Model Procedures and
Specifications".
11.16.1
S11/44
All boring shall be carried out in accordance with this specification and
shall also conform to the Codes of Practice BS 8004:1986 and CP
2011.
11.17
DEFINITIONS
In this specification the terms 'approved,' 'approval' and 'required' mean
'approved by the Engineer,' 'approval of the Engineer' and 'required by
the Engineer' respectively.
The following definitions shall apply:-
Grade III
Grade IV
Grave V
Grade VI
DESIGN BASES
11.18.1
General
The contractor shall design the lengths of the piles for the pile types,
pile sizes and pile loads given in the drawings in accordance with the
design codes mentioned herebefore and the specific conditions given
hereafter and to the criteria for acceptance given in Clause 11.5.16.
11.18.2
Specific Requirements
S11/45
(i)
The ultimate bearing capacity of the pile shall not exceed that
derived using the static capacity formula as follows:Qult = K N A + Kb Nb Ab
Where: K is the shaft resistance factor;
N is the average N (S.P.T.) value along the shaft or
average N values for different segments of the pile length;
Kb is the base resistance factor;
Nb is the N (S.P.T.) value at the pile base;
A is the shaft area;
Ab is the base area.
Where N (S.P.T.) values are in excess of 50, the N value adopted
may be increased as follows:"N" = 50 x Penetration recorded for 50 Blows (cm)
30 cm
but subject to a maximum value of 200.
11.19
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
S11/46
11.20
(i)
(ii)
(iii)
(ii)
The tenderer shall submit a report giving his full interpretation and
evaluation of the design data for the foundations together with his
tender. This should include the criteria used for determining his
foundation depths during tendering and during the actual works.
11.21
CUT-OFF LEVEL
The cut-off level of the piles shall be at least 75mm above the pile cap
base level, which shall depend on the thickness of the cap shown on the
drawings supplied to him.
Starter bars for columns shall be provided, and the projecting portion
of the starter bars shall be coated with an approved temporary
corrosion resistant coating which can be removed when forming the
columns.
11.22
S11/47
11.22.1
(ii)
(iii)
(d)
(e)
11.23
S11/48
11.24
RECORD, DRAWINGS
11.24.1
11.24.2
Size of Drawings
All drawings shall be A1 size unless otherwise approved by the
Engineer or his representative.
11.24.3
Cost of Drawing
The contract price shall be deemed to include the cost of preparation,
supply and delivery of all drawings and information, and copies
thereof, which the contractor is required to provide under the terms of
the contract.
11.25
TOLERANCES
11.25.1
Setting Out
Setting out shall be carried out from reference lines and points shown
in the drawings. Immediately before installation of the pile, the pile
position shall be marked with suitable identifiable pins or markers.
11.25.2
Position
The maximum permitted deviation of the pile centre from the centre
point shown on the setting out drawing shall be 75mm in any direction.
11.25.3
Verticality
The maximum permitted deviation of the finished pile from the vertical
is 1 in 75.
11.25.4
Rake
The piling rig shall be set and maintained to attain the required rake.
The maximum permitted deviation of the finished pile from the
specified rake is 1 in 25.
11.5.5
Forcible Correction
S11/49
11.26
PILING METHOD
The contractor shall supply for approval all relevant details of the
method of piling and the plant he proposes to use. Any alternative
method to that specified shall be in accordance with the specification.
11.27
PILING PROGRAMME
The contractor shall inform the Engineer each day of the programme of
piling for the following day and shall give adequate notice of his
intention to work outside normal hours and at weekends.
11.28
Contract, Section;
Reduced level on the pile position;
Pile reference number;
Nominal diameter of the borehole;
Length of the borehole;
Nominal diameter of the under-ream;
Standing ground water level;
Date bored;
Date concreted;
Depth from working level to pile toe;
Depth from working level to specified cut-off level;
Length of temporary casing used;
Length of permanent casing used;
Soil samples taken and in situ tests carried out - inclusive
S11/50
(xv)
(xvi)
(xvii)
(xviii)
(xix)
(xx)
(xxi)
11.29.1
11.28.2
11.28.3
Damage to Piles
The contractor shall ensure that damage does not occur to completed
piles.
The contractor shall submit to the Engineer his proposed sequence and
timing for driving or boring piles having regard to the avoidance of
damage to adjacent piles.
11.30
MATERIALS
(a)
Permanent Casings
Tubes to be used as permanent casing in the ground shall be
subject to approval.
(b)
Bentonite
S11/51
WORKMANSHIP
(a)
General
Workmanship shall be in accordance with BS 8004 and C.P.
2011 and the specifications.
(b)
Setting Out
The setting out shall be as described and the contractor shall
check all pile positions during and immediately after placing
the casing.
(c)
11.32
BORING
(a)
(b)
S11/52
(d)
(e)
(f)
Inspection
Each pile boring shall be inspected prior to the placing of
concrete in it. This inspection shall be carried out from the
ground surface in the case of dry bores.
(g)
Temporary Casings
Temporary casings are to be free from significant distortion and
of uniform cross-section throughout each continuous length.
During concreting they shall be free from encrusted concrete or
S11/53
REINFORCEMENT
Where provided, reinforcement shall conform with the relevant clauses of
this specification and, prior to placing, the bore shall be cleaned of all
debris and loose material and the reinforcing cage then placed so that it
will not be displaced during the concreting operation. Steel reinforcement
shall be provided for the whole length of piles and shall be fixed in the
form of a cage with lateral ties. The length of the reinforcement provided
shall be such that it shall protrude not less than 30 times the diameter
above the cut-off level to bond with the pile cap and ground beams.
Joints in the main longitudinal steel bars by means of welding will not be
permitted. Bars longer than 20ft. will be extended with sufficient overlapping according to the British Standard Codes of Practices.
11.34
CONCRETING
Concreting shall conform to the relevant clauses of this specification and
shall be placed and tamped to ensure the formation of a solid compact
pile.
11.35
11.36
11.37
S11/54
The pipe shall rest on the base of the boring at the commencement of
concrete pouring and it shall at all times penetrate into concrete which has
previously been poured. The concrete shall be a rich coherent mix of high
workability in accordance with the specified strength.
The diameter of the tremie pipe shall not be less than 150mm (6 in.)for
concrete made with 20mm (3/4 in.) aggregate and not less than 200mm (8
in.) for 40mm (1 1/2 in.) aggregate. It shall be so designed that external
projections are minimised allowing the tremie to pass through reinforcing
cages without causing damage. The lateral face of the tube shall be free
from projections.
A sliding plug shall be placed in the tube to prevent direct contact inside
the tremie between the first change of concrete and water.
11.38
WORKABILITY OF CONCRETE
The concrete slump and the water cement ratio shall be so determined that
the concrete strength will comply with all the relevant codes of practice
and the specification.
The workability of concrete shall be determined by the slump test as
described in BS 1881 or an alternative approved method.
Slump measured at the time of discharge into the pile boring shall be in
accordance with the following standards:Piling Mix
Workability
11.39
Slump
Minimum
Maximum
75mm
(3 in.)
125mm
(5 in.)
100mm
(4 in.)
175mm
(7 in.)
150mm
(6 in.)
DAMAGED PILES
S11/55
11.40
11.41
EXTRACTION OF CASING
Temporary casings shall be extracted during the tamping and concreting
operation so as to prevent necking. The concrete shall remain sufficiently
workable to ensure the concrete is not lifted.
When the casing is being extracted a sufficient quantity of concrete shall
be maintained within it to ensure that external water or soil pressure is
exceeded and that the pile is not reduced in section nor contaminated.
No further concrete is to be placed in the boring once the bottom of the
casing has been lifted above the concrete level.
If jointing of two or more casings is found required, the casings will be
jointed by full welding to ensure water tightness.
The contractor will not be permitted the use of the vibrating casing.
11.42
11.43
DOUBLE CASING
Where two or more discontinuous lengths of casing are required in the
construction, the contractor shall ensure that water or other fluid does not
create an artificial fluid level outside the inner casing in excess of the head
of concrete within the inner casing.
S11/56
11.44
11.45
11.46
Top of pile;
Mid-length of the section of the pile in soil with N less than 50;
Bottom of the section of the pile in soil with N less than 50;
Mid-length of the pile socketed into N greater than 50 blows per
300mm material;
Bottom of the pile
S11/57
At each level at least three gauges for measuring vertical strains shall be
located at 60o intervals. At least 2 rod extensometers shall be installed at
each level.
Strain gauges or vibrating wire gauges shall be read at time intervals
coincident with settlement readings specified in the other sections of the
specification pertaining to pile testing.
Installation and monitoring of all instruments shall be carried out by
technicians or engineers experienced and skilled in pile instrumentation
and shall be subject to the approval of the Engineer.
S11/58