Professional Documents
Culture Documents
10/29/01,2:16 PM
TUNNEL W ARM -UP PROC4--HIGHLITED REQUIRED ACTIONS.DOC
psig
psid
#/hr
Per Telecom I.C. Thomasson. Drawings requested 3-9-2000 to verify. I.C. Thomasson cannot locate. Still trying
Ditto, footnote 1.
3
Pressure gauge read 20 psi 8 feet above steam line on 3-30-2000, i.e. 22.5 psi. Previous reading was 8 psi? (Recommend a pressure and temperature gauge be installed in condensate mains at Junction DSA with communication points to the EMS).
4
Drip legs on the TSU system are very small, holding only about a quart of liquid each so they readily overflow.
5
Psid= pounds per square inch differential pressure
6
See spreadsheet entitled TSU Tunnel Steam Pipe Heat Loss
7
I.E., one where condensate is not drained manually
2
10/29/01,2:16 PM
TUNNEL W ARM -UP PROC4--HIGHLITED REQUIRED ACTIONS.DOC
Condensate Load. I calculate the condensate load at 25 psig will be 53 #/hr at the critical trap T-4. Thus if
my heat transfer presumptions are accurate, at 25 psig(actually 5 psid above the condensate backpressure)- traps can handle the condensate load being generated in the steam tunnel with a safety factor of 2. The
following presumptions were made in the heat transfer calculations:
1. 3 fiberglass insulation covering 99% of pipe being served by T-4
2. Both tunnel ventilation fans on creating a 10 mph breeze at T-4
3. 60F in tunnel
I calculate that if more than 4% of the pipe being served by T-4 is uninsulated, the T-4 trap will be overcome
at 5 psid/25 psig. Therefore, its paramount to insure pipes stay well insulated.
Prior to reaching 5 psid (~25 psig) during warm-up, another method of draining condensate is necessary to
keep it from accumulating at low spots in the system.
Phase I of Start-Up : 70F 212F (0 psig)
The steam plant shall admit steam to the steam system at a pressure a few psi above 0 psig after having
warmed up the boiler(s) to 212F. Phase I shall not end until the system is warmed to 212F as indicated by
a reduction in steam flow from the boiler plant and the read out of a temperature sensor near the end of the
steam system.
Condensate Generated. Over 2,500 #s of condensate (~325 gallons) will form in the tunnel steam mains
in warming the steel from 70F to 212F not including condensate which forms in the North A & B lines
which do not drain into the central steam main. (Not included in this amount is the additional condensate
which forms due to heat loss as the pipes warm. This can be substantial where pipes are uninsulated). This
condensate must be
removed before additional steam flow and
pressure is applied to
the steam distribution
system to warm it the
rest of the way to final
steam temperature of
344F at 110 psig. If
Trap T-4 had to act
alone to remove this
condensate after it had
all flowed to Junction
DSA, I calculate it
would take trap T-4
acting alone over 28
hours to drain accumulated condensate8 after
steam pressure was
raised above 30 psig (to
provide 10 psid of
positive pressurization).
8
(See TSU Tunnel Report\CondensateFormation.xls for calculation). Calc does not include condensate formed due to heat loss
during period pipes are warming.
10/29/01,2:16 PM
TUNNEL W ARM -UP PROC4--HIGHLITED REQUIRED ACTIONS.DOC
Because this is unacceptable, other provisions have been made to remove condensate during the period traps
are inoperable.
Thermotons. To help drain condensate at start-up, Sarco Thermotons (pictured above) were provided at trap
assemblies in the Summer 1999 Repair of the Tunnel Steam System designed by I.C. Thommason. The
thermotons automatically open to discharge condensate to the tunnel floor whenever condensate temperature
is less than 212F 9 -- which it should be during the initial Phase I of start-up. The capacity of thermotons to
remove condensate, however, is limited. The CL-6 model provided at TSU has only a 3/8 orifice. At 1 psid
(equal to a water head of 2.3 feet with no steam pressure), a thermoton will only discharge about 3.3 #s10 of
condensate a minute or 0.4 gpm. Consequently, unless steam is admitted very slowly to the steam system,
condensate can easily overwhelm the capacity of a thermoton to drain it, fill the drip leg, and ultimately flow
to the low spot in the system at Junction DSA. Based on the amount of condensate that flows to the nextmost critical trap after T-4 during start-up, the thermoton at T-5 needs as much as an hour to drain condensate during Phase I. If condensate is formed more rapidly, it will overflow the T-5 drip leg toward T-4 at
Junction DSA. The T-4 trap station which receives condensate from two directions will take about 1.8 hours
to drain just the warm-up condensate it normally receives11 . My guess is that even with a slow and careful
start-up employing the thermotons, a substantial amount of condensate from the entire system could overflow trap stations and end up at T-4. If the condensate were allowed to accumulate there, the thermoton at T4 would be very slow to drain a large puddle of condensate12 .
Manual Verification. Thus, the drain at the T-4 trap assembly as well as those at T-30 and T-4513 shall
be manually opened at the end of the Phase I warm-up period (as signified by the achievement of 212F at
the end of the steam system) to: (#1) purge any condensate not removed, and (#2) verify that all Phase I
condensate has been removed from the steam system. This may be accomplished relatively safely since
there is minimum steam pressure in the system. After verification that all condensate is out of the system at
each low point, the manual drain may be closed and Phase II of the Start-up may proceed.
Air Removal. Another benefit of the thermotons is that they will vent air during warm-up where they have
enough time to clear condensate before condensate temperature exceeds their set point. This will be the case
at the farthest reaches of the tunnel steam lines.
Phase II of Start-up: 212F 274F (30 psig)
From 70F to 212F is a 142F temp rise. The system has 132F further to go to warm to 344F, so during
Phase I, just over one-half of the warm-up condensate has been formed and expelled. Above 212F, Thermotons are closed, so the rest of the condensate to be formed during warm-upabout 2400 #s (~300 gallons)-- must be removed by other means. Traps, as discussed earlier, will not remove condensate until the
steam pressure exceeds the backpressure in the condensate system which I presume to be not more than 20
psig (based on the height of the riser to the condensate receiver in the steam Plant). Consequently, once it is
confirmed that all condensate is drained from Phase I by manually checking for condensate at T-4, steam
pressure may be hiked steadily to > 25 psig say 30 psig-- to enable traps to discharge conde nsate.
10/29/01,2:16 PM
TUNNEL W ARM -UP PROC4--HIGHLITED REQUIRED ACTIONS.DOC
At 30 psig (assuming this is 10 psi above the CR backpressure), the FS3-10 TLV traps will discharge 135
#/hr of condensateabout gpm. T-4, with the greatest condensate load, will receive 156 #s of warm-up
condensate in warming from 212F to 274F plus roughly 53 #/hr due to heat losses after warming up. The
trap can discharge this condensate in less than 2 hours. Thus, the duration of Phase II will be 2 hours. (This
time duration could be more than cut in half by replacement of the TLV-FS3 trap with a larger FS5 model).
Back-up Bucket Traps. Once again, it is possible that if steam is admitted too quickly to the system, condensate could overflow trap stations and end up at T-4 adding to its condensate load. Thus, to relieve any
possible overload at T-4 which could result in a condensate accumulation, a low-pressure high-capacity
bucket trap shall be piped in above the T-4 trap in the T-4 trap assembly. The purpose of the bucket will
be to discharge any condensate that backs up at T-4. Like the thermotons, the bucket shall discharge to the
tunnel floor. But, above 30 psid (~50 psig), the bucket shall be selected to automatically seal closed so it is
inactive at normal steam operating pressure. An ARMSTRONG 812 trap with orifice will discharge
1500 #s of condensate per hour at 10 psid (~30 psig) and seal shut at 30 psid (~50 psig). The bucket will
perform the same function as the thermoton in dumping subcooled condensate, but it has 2.4 times the capacity of the thermoton and will remain operable through Phase II of the Start-up Procedure. An additional
benefit is that it will speed up Phase I of the Start-up-- the bucket trap will cut the condensate drain time at
T-4 in half to less than 1 hour14 . The thermoton at T-4 may be removed from service to simplify the trap
assembly.15
Using the same logic as above, back-up low-pressure bucket traps shall also be installed at T-30 and T47.
Phase IIIa of Start-up: 274F(~30 psig) 293F (60 psig)
Increase steam pressure to 60 psig (~40 psid). At 60 psig (40 psid), the traps capacity increases to
265#/hr. 86 #s of warm-up condensate will form and flow to T-4 during this portion of the warm-up plus
condensate generated by heat lossless than 40#s over hour. Condensate can be removed in hour.
Phase IIIb of Start-up: 293F(~60 psig) 344F (110 psig)
At 110psig (90 psid ), trap capacity is almost 400#/hr. Raise steam pressure to 110 psig over the next
hour, allow it to remain at 110 for another hour.
14
I have not recommended the bucket be used to reduce the duration of Phase II, however, because during Phase II, hot condensate
(T> 212F) would be dumped.
15
An ALTERNATE PLAN is to install a pumped trap at T-4 which can lift condensate the ~45 to the condensate receiver
through a dedicated discharge pipe. The pumped trap would act as a regular trap when steam pressure was sufficient to overcome
condensate backpressure to expel condensate, but when steam pressure was insufficient, it would be automatically powered by 70
psi air pressure (or an auxiliary steam pressure source) to lift condensate to the condensate receiver. (The air pressure available in
the steam plant, Im told, is 100 psig). An advantage of this configuration is that it could avoid dumping some or most of the
condensate to the tunnel floorespecially if use of the thermotons were abandoned. This could amount to about 2600#s of
condensate saved at start -up if the thermotons use were abandoned except for a few at the end of the line for air venting. (Could
is in italics since the steam plant dumps most condensate return during start-up due to overfilling of the boilers, so the majority of
returned condensate is not recovered). The rest of the condensate would still be emptied by traps once steam pressure exceeded 20
to 30 psig. Like the low-pressure bucket trap, the primary function of the pumped trap would be to act as a backup to catch any
condensate not emptied by other traps in the tunnel system (other than those in North A & B lines). It would perform this duty
even during normal steam pressure operation (when the bucket trap would be sealed closed by steam pressure). Flow of compressed air to the pump trap could be alarmed and monitored to give a warning when thermotons or traps were not remo ving all
condensate formed.
The pumped trap solution is more elegant, but is also more costly. An air or steam line would have to be run beneath the street
and down the tunnel shaft from the Steam Plant to Junction DSA. I adjudge the additional advantage of the pumped trap to not be
worth the extra installation cost.
10/29/01,2:16 PM
TUNNEL W ARM -UP PROC4--HIGHLITED REQUIRED ACTIONS.DOC
At Completion of Warm-up
Re-enter Tunnel. (1) To insure no condensate is backed up in steam lines, compare temperature of condensate-filled portion of drip leg at T-30, T-4, and T-47 trap assemblies with steam filled portion using an infrared radiation gun. If temperature of condensate is subcooled compared to steam, a condensate back-up is
indicated as shown below. If there is a condensate back up, DO NOT attempt to drain it under full steam
pressure. Reduce steam pressure to 0 psig, drain the line, troubleshoot the problem.
(2) Close isolation valves upstream of thermotons at
each trap assembly to keep them from dribbling
condensate.
Steam
Subcooled
To Trap
Assembly
10/29/01,2:16 PM
TUNNEL W ARM -UP PROC4--HIGHLITED REQUIRED ACTIONS.DOC
10/29/01,2:16 PM
TUNNEL W ARM -UP PROC4--HIGHLITED REQUIRED ACTIONS.DOC
Condensate
Receiver in
Steam Plant
Tunnel
Entrance
UV-2
North A
60,000 cfm
from 2 fans
T-30
12
792
T-3
192 10
T-25
496
T-4
North B
T-5
DSB
T-41
974
T-6
Slope
T-7
T-8
T-9
T-10
1941