Professional Documents
Culture Documents
Table of Contents
Double Contingency
Line 2 and line 3 have both experienced contingencies and are out-of-service. If we inject 1200 MW at
bus A, and withdraw 1200 MW at bus B, how much power will flow on line 1?
10
Double Contingency
Line 2 and 3 have experienced contingencies and are out-of-service. If we inject 1200 MW at bus A, and
withdraw 1200 MW at bus B, how much power will flow on lines 1?
11
12
13
14
15
16
17
18
19
20
21
22
Supplemental Questions
If everything else is held constant, what happens to the power flow on a transmission line as its
impedance goes up? As its impedance goes down?
What physical parameters are needed to calculate power flows on a transmission line?
When different sets of injections and withdrawals are laid on top of each other, is it possible for
those separate flows to add up to a zero net flow?
On a 3-bus network, when impedance is the same on every line, why does power flow around
the network in a 1/3 to 2/3 ratio?
23
24
25
26
LMPs
What will the LMP be at Bus A and Bus B?
This is answering the question: what is the least cost dispatch for serving the next increment of load at
Bus A and at Bus B?
27
28
29
Generation Info
Generator A has a maximum output of 800 MW, an offer of $45/MWh for up to 300 MW, an offer of
$50/MWh for up to 500 MW and an offer of $55/MWh for above 500 MW.
Generator B has a maximum output of 600 MW, an offer of $10/MWh for up to 550 MW and an offer of
$12/MWh for above 550 MW.
Generator C has a maximum output of 900 MW and an offer of $40.
30
31
LMPs
Given the load and dispatch information, what are the LMPs at Bus A, Bus B and Bus C?
32
Load Increase
Well increase the load at Bus C to 900 MW so we can see the impacts on dispatch, power flow and
LMPs.
33
Dispatch of Generator B
Because Generator B is our least expensive resource, we will dispatch it to the top 600 MW. What will
the power flows look like from Generator B?
Because Generator C is next in line as the least expensive resource, we will dispatch it to 300 MW.
Because it is at the sum bus as our load, there are no power flow impacts to consider.
34
35
Load Increase
In this next scenario, we will increase load to 1600 MW and observe the impacts on dispatch, power
flow and LMPs.
36
37
38
LMPs
Based on the dispatch and power flows, what are the LMPs at Bus A, Bus B and Bus C?
Supplemental Questions
Why are LMPs the same at every bus when there is no congestion?
Under an economic dispatch with no congestion, what happens to LMPs as load increases?
39
40
41
42
LMPs
What are the LMPs at Bus A and Bus B under this dispatch?
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
Supplemental Questions
What is the underlying mechanism that causes LMPs to separate when a transmission line
becomes constrained?
Why do LMPs decrease on the unconstrained side of a transmission line or interface? Why do
LMPs increase on the constrained side of a transmission line or interface?
When a transmission line becomes constrained, why are LMPs at some busses set by multiple
generators (why are there multiple marginal generators)?
62
63
64
65
66
67
68
69
70
71
72
73
74
75
Supplemental Questions
Generally, what happens to LMPs when the limits on constrained transmission lines are
reduced?
With tighter transmission constraints, what happens to LMPs on the constrained side of a
transmission line or interface? Why?
With tighter transmission constraints, what happens to LMPs on the unconstrained side of a
transmission line or interface? Why?
76
77
78
79
LMPs
In this scenario, what are the LMPs at each bus?
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
Supplemental Questions
What are the two definitions for shadow price? Why are these two definitions really the same?
Why is the shadow price of a constrained transmission line different than zero?
What happens to the shadow price of a transmission line as the limit tightens and LMPs
separate more?
All else equal, if all generator offers were doubled, what would happen to the shadow price of a
constrained transmission line? What would happen if all generator offers were halved?
107
108