You are on page 1of 144

Dams

Literally speaking Dam means a body of water confined by a barrier.


Dams, structure that blocks the flow of river, stream, or other water way. Some
dams divert the flow of river into a pipeline, canal, or channel. Others raise the
level of inland water ways to make them navigable by ships and barrages. Many
dams harness the energy of falling water to generate electric power. Dams also
hold water for drinking and crop irrigation, and provide flood control.
The oldest known human made dams were built more than 5000 years ago in
arid parts of the Middle East to divert river water to irrigate crops. Today there
are more than 500000 dams world wide. The wast majority of these are small
structures less than 3m (10ft) high. Engineers regard dams that measure more
than 15m (50ft) high as large dams. About 40000 large dams exist in the world
today.

Dams are of two types,

1. Concrete dams
2. Embankment dams

1. Concrete dams
Concrete dams are those which
are constructed of concrete and
they are mainly of three types,
a. Gravity dams
b. Arc dams
c. Buttress dams

a. Gravity dams

Gravity dams are the concrete dams


which stayed due to their weight. A
concrete gravity dam has a cross
section such that with a flat bottom,
the dam is free standing. That is, the
dam has a center of gravity low
enough that the dam will not topple if
unsupported at the abutments. Gravity
dams require maximum amounts of
concrete for their construction as
compared with other kinds of concrete
dams, and resist dislocation by the
hydrostatic pressure of reservoir water by sheer weight. A favourable site usually
is one in a constriction in a valley where the sound bedrock is reasonably close
to the surface both in the floor and abutments of the dam. The availability of
suitable aggregate for manufacture of concrete is also an important
consideration.

Masonry dams that relied upon their weight for stability against sliding and
overturning date back 3000 to 4000 years, both upstream and downstream faces
were sloped and the base thickness was many times the height. In 1872 Rankine
proposed that there should be no tensile stress in a gravity dam. In 1895 Levy
proposed that the compressive stress in the material of the dam at the upstream
face should be greater than the water pressure at the corresponding depth in the
reservoir.

The danger from uplift had been recognized in 1882, and the danger of sliding
was highlighted by the failure of the Austin Dam, USA. The most recent advance
has been in the application of the finite element method of analysis.

Typical Section Example

Hoover Dam, Nevada-Arizona (221m)

Grand Coulee Dam, Washington State (168m)

Fontana Dam, Tennessee (137m)

Studen Kladenetz, Bulgaria (67.5m)


Design Concepts and Criteria

A gravity dam shall be:

Safe against overturning at any horizontal plane within the dam.


Safe against sliding at any horizontal place within the dam.
So proportioned that the allowable stresses in both the concrete and the
foundation shall not be exceeded.

Loading Criteria

See Loading and Factor of Safety Page

In 1940 Houk and Keener, listed twenty five basic assumptions that should be
considered relative to the design of important masonry dams.

1. The rock that constitutes the foundation and abutments at the site is
strong enough to carry the forces imposed by the dam with stresses well
below the elastic limit at all places along the contact planes.
2. The bearing power of the geologic structure along the foundation and
abutments is great enough to carry the total loads imposed by the dam
without rock movements of detrimental magnitude.
3. The rock formations are homogeneous and uniformly elastic in all
directions, so that their deformations may be predicted satisfactorily by
calculations based on the theory of elasticiy, by laboratory measurements
on models constructed of elastic materials, or by combinations of both
methods.
4. The flow of the foundation rock under the sustained loads that result from
the construction of the dam and the filling of the reservoir may be
adequately allowed for by using a somewhat lower modulus of elasticity
than would otherwise be adopted for use in the technical analyses.
5. The base of the dam is thoroughly keyed into the rock formations along
the foundations and abutments.
6. Construction operations are conducted so as to secure a satisfactory bond
between the concrete and rock materials at all areas of contact along the
foundation and abutments.
7. The concrete in the dam is homogeneous in all parts of the structure.
8. The concrete is uniformly elastic in all parts of the structure, so that
deformations due to applied loads may be calculated by formulae derived
on the basis of the theory of elasticity or may be estimated from laboratory
measurements on models constructed of elastic materials.
9. Effects of flow of concrete may be adequately allowed for by using a
somewhat lower modulus of elasticity under sustained loads than would
otherwise be adopted for use in technical analyses.
10. Contractions joints are properly grouted under adequate pressures, or
open slots are properly filled with concrete, so that the dam may be
considered to act as a monolith.
11. Sufficient drains are installed in the dam to reduce such uplift pressures as
may develop along areas of contact between the concrete and rock
materials.
12. Effects of increases in horizontal pressures caused by silt contents of
flood waters usually may be ignored in designing high storage dams, but
may require consideration in designing relatively low diversion structures.
13. Uplift forces adequate for analysing conditions at the base of the dam are
adequate for analysing conditions at horizontal concrete cross sections
above the base.
14. Internal stresses caused by natural shrinkage and by artificial cooling
operations may be adequately controlled by proper spacing of contraction
joints.
15. Internal stresses caused by increases in concrete temperature after
grouting are beneficial.
16. Maximum pressures used in contraction joint grouting operations should
be limited to such values as may be shown to the safe by appropriate
stress analyses.
17. No section of the United Sates may be assumed to be entirely free from
the occurrence of earthquake shocks.
18. Assumptions of maximum earthquake accelerations equal to one tenth of
gravity are adequate for the design of important masonry dams without
including additional allowances for resonance effects.
19. Vertical as well as horizontal accelerations should be considered,
especially in designing gravity dams.
20. During the occurrence of temporary abnormal loads, such as those
produced by earthquake shocks, some increases in stress magnitudes
and some encroachments on usual factors of safety are permissible.
21. Effects of foundation and abutment deformations should be included in the
technical analyses.
22. In monolithic straight gravity dams, some proportions of the loads may be
carried by twist action and beam action at locations along the sloping
abutments, as well as by the more usually considered gravity action.
23. Detrimental effects of twist and beam action in straight gravity dams, such
as cracking caused by the development of tension stresses, may be
prevented by suitable construction procedure.
24. In monolithic curved gravity and arch dams, some proportions of the loads
may be carried by tangential shear and twist effects, as well as by the
more usually considered arch and cantilever actions.
25. The distribution of loads in masonry dams may be determined by bringing
the calculated deflections of the different systems of load transference into
agreement at all conjugate points in the structure.
Uplift

Two factors directly affect the design of a dam,


the intensity of hydrostatic pressure at various
points within or under the dam and the area
upon which pressure acts.

It is now accepted for design purposes that uplift


pressures act on the full area of the section. The
intensity of pressure may be represented by the
diagram showing the ideal case of underflow
conditions for an impermeable dam with a
straight base on a homogeneous isotropic
foundation of unlimited depth and horizontal
extent.

Headwater and tailwater depth are represented


by H and h, respectively. The concentric semi-ellipses represent lines of flow of
water passing through the foundation. The hyperbolas, drawn normal to the lines
of flow at all points, represent lines of equal hydrostatic pressure within the
foundation and at the base of the dam. This network of flow lines and pressure
lines is called a flow net. The diagram indicates an almost linear distribution of
pressure on the base, and this is the distribution for which the stability of the dam
should be checked if no drainage is provided. (or all drainage is blocked.)

Drainage is in the form of curtain of cored vertical holes 150mm or more in


diameter at 3-5m spacing and located 304m from the upstream face. A gallery
runs from one end to the other of the dam, above the tailwater level. Drainage
from the holes is led away via open gutters, with measuring weirs installed to
record the flow.

It is now general to adopt a distribution of uplift pressure as above, the value of


factor k being decided having due regard to the porosity of foundation rock and
the existence of joints and cracks therein. It is important to expend effort and
money on a drainage system to ensure satisfactory function over the
entire life of the dam.

Stresses

Considering vertical cantilever sectionsm of unit width it is a simple


matter to compute vertical stresses on horizontal planes for the
cases of reservoir empty and reservoir full. In general, efforts are
made to avoid tensile stresses in the concrete for normal loadings.
Compressive stresses are not usually high in gravity dams.

The usual analysis stresses normal to horizontal planes are


assumed to have a linear trapezoidal distribution. Finite element methods show
the stress distribution to be as in the figure.

It is significant that the maximum stresses do not occur at the downstream toe,
and there may be tension rather than compression at the upstream heel.
However, there is similarity between the two methods. It is important to check the
distribution and intensity of stress around galleries and other openings in the dam
and to provide adequate reinforcement to prevent propagation of cracks from
points of high stress concentration.

Contraction joints

Transverse Joints

It is good practice for normal methods of construction to provide contraction joints


in gravity dams. They are usually spaced about 15m apart, experience having
shown that cracks are likely to develop in monoliths much wider than this. It is
however, essential to locate the joints to best advantage relative to the shape of
the abutments.

Longitudinal Joints

For large structures the problems of cooling


large masses of concrete are enormous.
Resulting in limiting the dimensions of
monoliths to 15m squares, keyed on all sides.
There is now a tendency to decrease the
number of longitudional joints or even omit
them all, since there are doubts of the final
behaviour of dams built in columns.

Galleries

The normal function of a gallery is to provide access for


inspection purposes, to monitor the behaviour of the dam, and
to carry out remedial work if required. It must therefore be of
sufficient height to permit easy movement of personnel and
minor equipment, commonly 2.13m but varied to suit
construction methods. The width is usually 1.5m but should be
related to the function of the gallery. Wide opennings induce
quite high local stresses with consequent cracking of the concrete. Spiral
staircases can link other galleries, ventillation and pipes in quite a small shaft.
Circular shafts are the most desirable, with a removable floor covering drainage,
but it is harder and more expensive to form. Rectangular galleries require greater
amounts of reinforcement. Galleries also should be well lit and ventillated.

Appurtenant structures

These are the power station and spillway.

Prestressed gravity dams

Strengths of rocks in foundation and elements within concrete dams are


increased by installation of steel rocks or steel cables which are injected to
tensioning. The procedure that is followed is called prestressing.

The reluctance to use cables has been related to a lack of knowledge of steel
cables when embedded in concrete. It is however generally agreed that steel
does not rust when embedded in high quality concrete or cement grout in which
there are no cracks or interconnected voids.

If prestressing is accepted in the design then it is prudent to make provision for


retensioning if required, replacement of bars or cables, or the installation of new
cables. Serious corrosion of cables can be detected by the regular measurement
of their electrical resistance.

The actual behaviour of the dam will depend upon the nature of the foundation
rock, any initial stress in the rock and the effect of saturation of the rock mass.

For reasonable stress distribution the depth of the anchorage should be not less
than the width of the base of the dam. The advantages of wires over bars are:

The allowable working stress in high tensile wires is usually greater than in
bars
Wire cables can be fabricated on site in one length, avoiding the use of
couplers that are necessary with bars and are a source of trouble
Cables can be accomodated in drilled holes whereas bars with couplers
usually require larger pits.

b. Arc Dams

The ultimate complexity of design and analysis of stresses is attained in arch and
dome dams. These dams are thin, curved structures commonly containing
reinforcement, either steel rods or prestressed steel cables the volume of
concrete required is much less than for gravity and gravity arch dams, but the
competency of bedrock in foundations and abutments to sustain or resist loads
must be of a high order.
Arch dams are usually built in narrow, deep gorges in mountainous regions
where access and availability of construction materials pose especially acute
problems.

Arch dams are of two kinds.

Constant radius arch dams - commonly have a vertical upstream face with a
constant radius of curvature

Variable radius dams - have upstream and downstream curves (extrados and
intrados curves) of systematically decreasing radii with depth below the crest.

When a dam is also doubly curved, that is, it is curved in both horizontal and
vertical planes, it is sometimes called a dome dam. Some dams are constructed
with two or several contiguous arches or planes and are described as multiple
arch or multiple dome dams.

Analysis assumes that two major kinds of deflections or dislocations affect the
dam and its abutments. Pressure of water on the upstream face of the dam and
uplift pressures from seepage beneath the dam tend to rotate the dam about its
base by cantilever action. In addition the pressure of reservoir water tends to
flatten the arch and push it downstream.

Design Concepts and Criteria

An arch dam transfers loads to the abutments and foundations both by cantilever
action and through horizontal arches, and a method of distribution was
developed by Stucky in Switzerland and the USBoR.

The assumptions made are not strictly true so the effect of each must be
understood before accepting the design.

The concrete in the dam and the rock foundations are homogeneous and
isotropic;
Stresses within the elastic limit for both concrete and the rock formations
and that stress will be proportional to strain;
That plane sections before bending remain plane after bending;
That direct stresses vary linearly between the upstream and downstream
faces, in both arch and cantilever elements;
That the modulus of elasticity of concrete and the modulus of deformation
of the foundation are the same in tension as in compression;
That temperature stresses and strains are proportional to temperature
changes;
That water load on the reservoir walls does not cause differential
movements at the damsite;
That foundation deformations are independent of the shape of the
foundation;
That tensions are relieved by cracking so that all loads are carried by
compression and shear in the uncracked portions;
That the dam acts as a monlith, i.e. that contraction joints or slots have
been tightly grouted and that all shrinkage of the concrete has taken place
before this.

The parameters controlling design, other than actual geometry include:

The loads on the dam; Loading and Factor of Safety


The degree of fixity to foundation and abutments;
The properties of the component materials of the dam and the
foundations.

Steel reinforcement can reduce the thickness of the dam but at a cost. If
reinforcement was not used then cracking in the faces of an arch dam may result
from:

Excessive tensile stress due to dam geometry;


Secondary tension resulting from high compressive forces in thin
members;
Secondary tensile stresses at the arch haunches and parallel to the
abutments;
'Hang up' of concrete adjacent to a near vertical abutment;
Temperature effects - either due to hydration of the cement or climatic
conditions.

Definition of different arch dams based on base thickness (h is height of the


dam):
Thin arch <0.2h
Medium arch 0.2h - 0.3h
Thick arch >0.3h
Arch-gravity >0.5h

Reinforcement is not generally required in arch-gravity dams or thick arch dams.


Its use in thin arch dams is favoured, however for a 90m high dam the cost of
reinforcement will be many millions of dollars, which could mitigate the adoption
of such a dam.
Uplift - is not usually of importance in thin arch dams, but in thick arch dams
provision is made for internal drainage, as for gravity dams. If the design
assumes that the concrete will crack if tensions exceed say 0.4MPa, then it is
consistent to assume that full hydrostatic pressure can act in such cracks.

Tensile stresses - the aim of the designer is to eliminate tensile stresses,


although this is not always possible since an irregular cross-section can generate
local stress concentrations, and necessary excavation of abutments beyond the
design limits will alter the geometry of the dam, and possibly affect the degree of
fixity.

Abutment Stability

In the rock body the following are involved:

The weight of the rock;


Static tectonic and dynamic seismic stresses;
Hydrostatic thrusts and buoyancy after filling of the reservoir;
Forces transmitted from the dam.

Minimum safety is usually found in the upper part of the double curvature dams
because:

The upper zones of the valley are less tight and earthquake forces here
cause stronger reactions;
The rock overburden is less - providing less normal loading on possible
sliding planes;
The direction of the resultant forces from the dam often meet the
abutments at less favourable angles.

Percolation of water under pressure may affect the strength of a rock abutment:

Saturation frequently decreases the strength of rocks, probably due to


infiltration of microcracks;
Natural rock stresses will be modified by the water pressure, and
Shearing resistance may be decreased

Shell Geometry

Constant-Radius Arch Dam


The simplest form of arch dam with a vertical cylindrical upstream face and a
uniformly inclined downstream face. Used in wide valleys with the possibility of
slip forming construction methods.
Constant-Angle Arch Dam

Variable-Radius Arch Dam


Double curvature - Cupola Dam

Vertical curvature introduced so that the weight of the dam will offset vertical
tensions due to water load. Cupola dams are ideal for narrow valleys and are
similar to the thin arch dams in regard to foundation requirements.

Cross Sections of typical arch dams

Contraction Joints
It has been normal practice to provide radial contraction joints in arch dams at
approximately 15 meter spacing. This dimension has evolved from experience
since cracks often appeared in monoliths of 20 meter or more in length, where
full control of concrete temperature was either impractical or uneconomical;
cracking occurred particularly at sides subject to sudden and large falls in
ambient temperature. For constant radius arch dams the joints are radial and
plane, whereas for double curvature dams they are frequently warped; in some
cases they are formed to leave the rock almost normal to the contact surface.

Since monolithic action is required in the arch, provision is made for the injection
of cement grout into the joints after the concrete has cooled to mean
temperature, or has been artificially cooled to a little below mean temperature in
order to introduce some compression into the arches.
Each joint is usually divided by horizontal grout stops so that zones from ten to
fifteen meters high may be grouted progressively to ensure stability of the
completed sections against
inadvertent overtopping by
floods.

Arch dams are usually


sufficiently flexible to defect
measurably under the forces
exerted by joint grouting; the
effectiveness of the grouting
can therefore be assessed by
comparing measured with
calculated deformations. To
prevent harmful overstress
regular observations should
be made during grouting on
joint meters embedded in the
concrete across the joints, on
dial gauges fixed to be
upstream and downstream
faces of the joint, on
clinometers on faces of the
dam and galleries and on
plumbobs and survey targets
as convenient.

Prestressing

In seeking further economies in the construction of arch dams it appears to be


necessary to consider means of applying external loads to the dam to counteract
undesirable tensile stresses that would otherwise develop. Many dams have now
been built with compressive stresses up to 8.5 MPa but to increase these
stresses would most likely not be possible without prestressing to counteract the
higher tensions.
Potential application of prestressing to arch dams
Prestressing induces vertical compressive stresses
upstream at the heel of the dam and downstream
near the crest. This can be achieved by two
processes, firstly by the information of flat jacks to
force open the end joints of the shell which would
defect the dam upstream, secondly by applying a
radial load at the crest by means of a horizontal cable
to defect the upper part of the dam downstream.
c. Buttress dams

Buttress dams were first


developed to conserve
water in regions where
materials were scarce or
expensive but labour was
cheap. Dams were used for
irrigation and mining
purposes. As designs have
become more sophisticated,
the virtues and weaknesses
of the buttress type dams
have become apparent.

The pressure of water


on the inclined
upstream at face adds to the stability of the dam, both by its magnitude
and direction.
With free drainage of the foundations between the buttresses, uplift on
their bases is considerably reduced.
The general flexibility of the dam can accommodate differential movement
of the foundations.
Unless the foundation material was erodible minor leakage should not
endanger the dam.
A minimum of materials is required but its accurate placement involves
skilled tradesmen and higher unit costs.
Whilst construction is at low levels, the work can be overtopped by floods
without serious damage - with considerable saving in river diversion
works.
For large dams the stress distribution in the buttresses [from water load,
own weight, thermal effects and foundation movements] is complex and
does not conform to linear distribution on horizontal planes. Models show
tensile stresses near the foundation of buttress heads in the case of good
foundations - though such stresses are not evident from conventional
analytical analysis. Preliminary designs should therefore be supplemented
by detailed studies using finite elements or photoelastic methods.
The buttress type of dam finds particular application in wide valleys where
sound rock would be the exception rather than the rule. Thorough
investigations are therefore essential particularly if the dam is to be rigid.
If a buttress dam is of slender dimensions, especially a multiple arch, and
flood waters are to pass over it, a very careful examination is necessary of
possible modes of vibration. What may not be serious for a gravity dam
could be disastrous for a buttress dam.
Lateral stability of buttresses is not now considered to be serious except
for high dams, but it should be checked, especially in areas of known
seismicity.
There appears to be a case for studying large span multiple arches in
wide valleys, i.e. the arches would be thick, unreinforced, and constructed
by mass concrete methods.
There is considerable scope for the application for prestressing to modify
stresses within buttress dams as well as to improve their stability.

Concrete Slab Deck

The flat slab is simply supported on the buttress heads to avoid negative bending
and cracking on the upstream face of the slabs. Flexible seals should be installed
to prevent water loss around the ends of the slab as they defect. Some buttress
dams have been constructed with the slab continuous over one or more
buttresses.

1. Simple slab deck

2. Continuous slab deck

Massive Head Buttress


To avoid tensile stresses in a thin slab, and hence the need for reinforcement,
the massive head buttresses were developed.

1. Massive Head (flat head)

2. Massive Head (round head)


The relative economy of buttress dams will depend on the foundations, the cost
of the materials, and the cost and reliability of the skilled tradesmen at the
particular site. However, for a height of 20m a flat head buttress would require
40% of the concrete used in a gravity dam.

For dams up to 150 meters high it should be possible to dimension a buttress


type of dam so that the first principal stress does not exceed 7 MPa, i.e. a stress
comparable with that in a thin arch dam.

Multiple Arch Dam

Multiple arch dams evolved at approximately the same time as the slab and
buttress dam, but at a slower rate. The factors influencing the selection of
multiple arch dams as a preferred type are similar to those for slab and buttress
structure relative to reduction in materials, low uplift forces, and adaptability to a
wide variety of canyon configurations.

Multiple arches are


continuous monolithic
structures where loss
of an important
structure component
could lead to loss of
the entire dam. Thus
these structures
require better
foundations.

The majority of multiple arch dam where constructed before 1935, and although
state of the art at the time, by today's standards are deficient relative to seismic
and hydrologic conditions.

Buttresses

For small dams the buttresses are usually analysed as gravity blocks subject to
the inclined water load, their own weight and small uplift. A buttress can also be
considered as composed of a system of curved beams, each of which trasmits
part of the water load and its own weight to the foundations.

The columns can be proportioned to develop uniform compressive stress and


curved to avoid eccentricity of loading. In order to avoid secondary tensile
stresses the buttresses of many large dams have been built with contraction
joints following the directions of the principle stresses
Uplift and Sliding
A major advantage claimed for buttress dams, including
the hollow gravity dam is that uplift forces acring on the
dam are minimal. It is usual to adopt a distribution of
uplift pressure, acting on 100% of the area, as shown in
the figure.

For this to be factual there must be


release to atmosphere, or tailwater
pressure, around the buttress footing.
Should the foundation be horizontally
stratified then uplift could act on a layer of
rock only a little distance below the dam;
drainage of such a foundation is therefore
essential.

Example, Muda Dam, Malaysia. Using


post tensioned restressible cables fixed
to the foot of the buttress to prevent uplift
and sliding.

Spill-over Buttress Dams


When flood waters are to be passed over buttress dams the following factors
deserve attention:

The nappe must be adequately aerated to avoid vibrations or pulsations


that could be transferred into the dam to cause overstressing or into the
foundations to weaken their shearing resistance.
The nappe should impact on to reinforced concrete slabs that are
adequately anchored into the foundations. Erosion behind the buttress
heads or arches should be prevented by provision of a concrete
turbulence control wall or suitable paving.
It must be possible to destroy most of the energy of the surcharge withiut
rupture of the river bed downstream from the dam. Should excesscive
erosion occur the shearing resistance of the foundation could be lost.

Prestressing

Prestessing is used to minimise the quantity of concrete and counteract tensions


that would otherwise exist. It is usually used as an extra factor of safety on an
otherwise adequate structure, for example to cope under extreme flooding or
earthquake conditions.
Prestressing can be applied in at least three manners to a buttress dam,

1. To 'pull down' the upstream face


2. To 'jack up' the downstream face
3. To compact the buttress on to the foundation rock to improve the
resistance to sliding of dam onrock, at the same time tightening seams to
improve the resistance to sliding within the foundations.

2. Embankment dams

ICOLD defined an embankment dam as, "any dam constructed of


excavated materials placed without addition of binding materials other than those
inherent in the natural material. The materials are usually obtained at or near the
damsite" The materials available locally control the size and
configuration of the dam. Many small embankment dams are built
entirely of a single type of material such as stream alluvium,
weathered bedrock, or glacial till. These are homogeneous dams,
constructed more or less of uniform natural material.

Larger embankment dams are zoned and constructed of a variety of materials,


either extracted from different local sources or prepared by mechanical or
hydraulic separation of source material into fractions with different properties. An
important element in a zoned dam is an impermeable blanket or core which
usually consists of clayey materials obtained locally. In locations where naturally
impermeable materials are unavailable the dams are built of rock or earth-rock
aggregates, and the impermeable layers of reinforced concrete, asphaltic
concrete, or riveted sheet steel are placed on the upstream face of the dam.

Embankment dams have been built on a variety of foundations, ranging from


weak glacial deposits to strong rock. An advantage compared with concrete
dams is that the bearing strength requirements of the foundation are much less.
Minor settlement during and after construction is generally not serious because
of the adjustability of the material.

There are two types of embankment dams

a. Earth fill dams


b. Rock fill dams

a. Earth fill dams

An earthfill dam is an embankment dam, constructed primarily of compacted


earth, either homogeneous or zoned, and containing more than 50% of earth.

A rockfill dam where all the voids have been filled by finer materials by hydraulic
sluicing is usually regarded as an earthfill dam.
Terminology of Earthfill dams
Types of Earthfill Dam
1. Homogenous
2. Central Impervious Core
3. Sloping Impervious Core
4. Hydraulic Dams

Slopes of 1 in 1.33
are suitable for
concrete faced
rockfill dams, but
for effective placing
and stability of an
asphaltic concrete
facing, the
upstream slope
must be about 1 in
1.7. It is significant
that men can walk
on this slope without ropes, but on a slope of 1 in 1.33 safety ropes are essential.
An asphaltic concrete allows for more movement due to settlement that for a rigid
concrete deck.

Homogeneous Earthfill Dams

Such embankments are made of a single type of material or material from the
same source. This may be small particles placed by hydraulic means, or
compacted earth or gravels that are handled and compacted mechanically.

Basic properties required in the material for an homogeneous embankment or for


the core of a rockfill dam are:

It must be sufficiently impervious to prevent excessive loss of water


through the dam, the acceptable loss being determined by the safety of
the structure and the value of the lost water;
It must be capable of being placed and consolidated to give a practically
homogeneous mass, free from potential paths of percolation, either
through the fill or along its contact with the foundation;
The soil should develop a maximum practical shear strength under
compaction and maintain most of it after the filling of the reservoir;
It must not consolidate, soften or liquify upon saturation.

The stability of an embankment dam is enhanced if the downstream portion can


be maintained free from seepage. Internal drains are therefore put within the
dam. See figure, leaving the 'dry' compacted fill as support. The section A-A
represents the filter, drainage, filter divisions.

The location and inclination will depend on the materials used. It has been
suggested that maximum stability would result from locating it nearer the
upstream face with the angle ø less than a right angle.

Central Impervious Core Earthfill Dams


Where there is only limited supply of soil for
the impervious core but plenty of pervious
material for the embankment, the designer
has no option but to decide on a thin core
dam. However, where there are plentiful
supplies of pervious and impervious
material, a thin core dam may be more
economically or easily constructed for a
number of reasons:

1. The unit cost of placing impervious


materials may be more than the unit
cost of placing pervious materials.
2. The amount of embankment volume can be reduced in a thin core dam
more effectively than in any other type of dam.
3. The construction time available and the weather conditions may not allow
the use of an impervious core of large thickness.

The minimum thickness of core is dependent on a number of factors:

1. tolerable seepage loss;


2. minimum width which will allow proper construction;
3. the type of material chosen for the core and shoulders of the dam;
4. design of proposed filter layers;
5. past experience on similar projects.
Core Stability - The core material usually has less shear strength than the rest of
the embankment, therefore from a stability standpoint, a thinner core is better.
However, a thicker core has increased resistance to differential cracking; which
may lead to piping. Therefore, piping resistance is dependent upon the soil
properties such as plasticity and gradation of the core material.

Advantages of vertical cores:

1. One advantage of the vertical core is that higher pressures will exist on
the contact between the core and the foundation, and will provide more
protection against the possibility of leakage along the contact.
2. The vertical core tends to be slightly thicker for a given quantity of
impervious soil than the thickness of a sloping core.

The following criteria represent a rough cross-section of opinion among


experienced earth dam engineers:

Cores with a width 30% to 50% of the head of water have proved
satisfactory on many dams under diverse conditions. Cores of this width
are adequate for any soil type and dam height.
Cores with a width of 15% to 20% of the head of water are considered
thin. However, when adequately designed and constructed filter layers are
used, then the core is satisfactory under most circumstances.
Core widths of less than 10% of the head of water are not used widely and
should only be used when a large leak through the core would not lead to
failure of the dam.

Sloping Impervious Core Earthfill Dams


Advantages of sloping cores:

1. The principal advantage of the upstream sloping core is that the


downstream portion of the embankment can be constructed first and the
core placed later. This a distinct advantage when there is only a short
season of dry weather suitable to allow construction of a core from fine-
grained soils.
2. Another advantage is that the foundation grouting can take place whilst
the embankment is being placed.
3. Filter zones between the upstream and downstream pervious zones can
be constructed more thinly and are easier to install than in vertical core
dams.
4. The sloping core dam is advantageous with the speed and economy of
foundation grouting which can be achieved. The advantage comes from
the fact that grouting can be performed while the main downstream
pervious embankment is being constructed.

Disadvantages of sloping cores:


1. At some sites the area of contact between the core and the foundation
depends on the depth of the foundation excavation: i.e. when the
excavation is carried deeper, the contact area moves upstream. However,
in some cases the depth of excavation required to provide a suitable
contact between the earth core and foundation cannot be determined
reliably in advance of construction.
2. Due to the reason above it may be difficult to locate the grout curtain in the
desired position relative to the core contact area.
3. If it is anticipated that additional grouting is required through the
embankment after the dam is completed then a central core design is
preferred, because the work can be done from the crest of the dam
without lowering the reservoir.

Hydraulic Fill Earthfill Dams

A hydraulic fill dam is one in which the material is transported in suspension in


water to the embankment where it gets placed by sedimentation. The sorting
effect of flowing water is utilised in creating a fine-grained core at the centre of
the embankment with coarse shells on the sides. In a semi-hydraulic fill dam the
material is transported by hauling units and dumped at the edge of the
embankment. It is then washed to its final position by water jets. The use of this
type of dam is rare, because;

The cost of rolled earth has droped rapidly with the development of larger
more economical earth moving equipment.
It is difficult to control the quality which makes them less dependable than
other types of dam.

Drainage of the core takes place in two ways, some of the water percolates
horizontally into the more pervious shell. The remainder moves upward to the
surface, allowing the centre of the dam to subside. The downward movement
eventually develops arching in the core and prevents its full consolidation.

Materials
The thouroughness with which borrow areas are investigated can have a major
effect on the cost of the dam. The best information is derived from trenches cut
by bulldozer. Two questions must be asked;
1. Is the material acceptable?
2. How will it be excavated?

The materials must be tested in the laboratory and must be representative of


what would be used in the final dam.

When selecting earth for a core or for a homogeneous dam, one must consider
its permeability, resistance to piping, shear strength, flexibility and resistance to
cracking. The water content will effect each of these differently; testing and
judgement are required to determine the optimum mositure content for the
particular soil in the particular part of the dam.

Earthfill Design
An earth dam is basically a trapezoidal embankment built in a valley to form a
water reservoir. The design has to ensure:

1. It is impermeable enough to prevent excessive loss of water from the


reservoir.
2. The design must ensure stable slopes.
3. Settlement of the dam must not be excessive so as to reduce the
freeboard of the dam.
4. The upstream slope of the dam must be protected from the destructive
action of waves, and the downstream slope must withstand rainfall
erosion.
5. A sufficient bond between the embankment and its foundation must exist
to prevent the development of seepage paths; excessive hydrostatic uplift
must be controlled by proper drainage.

Freeboard
A homogeneous embankment dam should never be overtopped and for
preference no permanent embankment dam should be overtopped. However,
provision for freeboard can be expensive because it requires enlargement of the
dam section and hence much more materials.

It may be convenient to pave the crest and downstream face. The level of the
crest is then determined to allow for only spray to pass over, or for the peak flood
discharge to pass over or even more frequent overtopping. However this is only
used for dams under 30m high.

An alternative method of reducing the quantity of fill is to provide a wave wall


along the crest of the embankment. See figure.
Crest Width
This is often governed by construction procedure and the access required either
during construction or as a permanent feature. The Japanese Code 1957
specifies crest width (W) in terms of the height of the dam, as
W=3.6H1/3-3(m)
which would give crest widths as in the table.
Height of dam (m) Crest Width
30 8
50 10
70 11
100 13
200 18

Culverts under Embankments


At some locations it is necessary to construct a large culvert under the dam,
although this should be avoided where possible.

The conventional culvert is one of reinforced concrete designed to withstand both


the internal water pressure and external embankment loading. It is important that
leakage does not occur within the core area or upstream from it, or anywhere
within an homogeneous bank. To prevent this cut-off collars usually encircle the
pipe, their location and dimensions being governed by the head from the
reservoir.

b. Rockfill dams
ICOLD defined a rockfill dam as, "an embankment type of dam, dependent for its
stability primarily on rock. As rockfill dams must contain an impervious zone -
now usually selected earth with filter zones, comprising a substantial volume of
the dam - the term Rockfill dam usually represents a dam that contains more
than 50% of compacted or dumped pervious fill. The dam is dependent for
watertightness on an impervious upstream blanket or an impervious core."
Like an earth dam it is composed of fragmental materials, with each particle
independent of the others. The mass stability is developed by the friction and
inter-reaction of one particle on another rather than by any cementing agent that
binds the particles together.

Types of Rockfill dams

Composite Earth and Rockfill

Central earth core

Sloping earth core

Upstream core

Rock with a thin membrane or diaphragm


to hold water

Central thin membrane


Upstream thin
membrane or deck

Unbonded or dry masonry

Dam with rubble retaining zone

Advantages of Rockfill Construction

Economical - due to the use of cheap local materials.


Suitable where the foundation conditions are not good, especially where
high hydrostatic uplift is likely to be a factor in design.

Rockfill is particularly suitable when there is no satisfactory earth available and


when a plentiful supply of sound rock is at hand. The rockfilling is especially
adapted to construction during wet and cold weather and permits continuous
work under weather conditions that would not permit earth or concrete
construction.

Very rapid constructions are possible with rockfill because of its adaptability to
bad weather and because the process of filling does not have to be interrupted
for rolling or other separate compaction operations.

The rockfill dam with an upstream diaphragm is very well adapted to stage
construction. The dam height can be increased merely by dumping more rock
behind the impervious diaphragm without interfering with or encroaching on the
reservoir. The dam is then made water-tight by continuing the impervious face
upward. The stage construction concept is also suitable for cofferdamming, as
the first part of the dam serves as a cofferdam which protects the remainder of
the foundation for further construction.

Rockfill Materials
The quality of the rock is a major factor in the choice of a rockfill dam and in the
design of the structure. Extensive testing is necessary to judge whether the rock
is suitable for construction.

Quarrying - The cost of drilling and blasting constitutes a large part of the unit
price of rockfill. Quartzite for example has excellent qualities for rockfill but is
extremely expensive to drill. The way the rock breaks up is also important,
sandstone produces a lot of fines, others produce flat slate pieces which do not
lend themselves to dumped rockfilling.

Rock Durability - There is no entirely satisfactory test to determine durability of


rock over centuries, and hence good judgement has to be used. Examining old
structures such as walls and bridge piers built of the same material is helpful.
Accelerated durability tests do exist, where the samples are subjected to
alternate cycles of wetting and drying or freezing and thawing. Compressive
strength tests can be made after each series of wet-dry and freeze-thaw testing if
there are sufficient samples.

Strength - In high dams where crushing of the corners of the rock pieces will
result in settlement, the strength is important. In general strengths of over 35MPa
or more are desirable for dams over 40m, while strengths as low as 14MPa are
more suitable for dams less than 15m in height. Friability, the tendency to
become a powder during crushing is important because too many fines can
seriously interfere with construction.

Petrography - The study of the rock under chemical reaction and under a
microscope to establish rock breakage.

Likely to be satisfactory Likely to be unsatisfactory


Granite, diorite Shale
Gneiss Slate
Basalt Schist
Sandstone Siltstone
Dense limestone Porous limestone
Dolomite Chalky limestone
Quartzite
Massive Schist

Shear Strength - Large size triaxial or direct shear tests are the best method for
determining strength.

Earth Core Rockfill Dams


The rockfill dam consists of a number of components:
1. The main rockfill
2. The impervious zone
3. Auxiliary supporting members

The main rockfill provides the structural support for the dam by its weight and
internal stability. The impervious zone holds back the water. It is made up of the
membrane which holds the water and transition zone which transfers the water
load to the rockfill. The membrane may be a thick blanket or core of earth or a
thin diaphragm or deck of wood, concrete, steel, asphalt, dry rubble masonry or
stone masonry. The auxiliary support members help to sustain the membrane or
parts of the main rockfill. These components are similar to the shell, core, and
appurtenances of the earth-fill dam and are analysed in a similar way.

Cores
The core may be defined as a membrane built within an embankment dam to
form the impermeable barrier, the balance of the dam being provided to ensure
stability. It may be of natural materials, clay, gravels etc. or prepared materials
such as cement or asphaltic concrete, or of metal, plastic, rubber, etc.

The thickness of the core will depend primarily on the material available, i.e. if a
good clay is available at low cost one would tend to be liberal with the core. The
core width will often be related to the type of foundation, the permissible
hydraulic gradient along the contact zone.

A core of natural materials may be central, inclined and close under the upstream
face or in some intermediate position. A general core thickness is one half of the
height of the dam, depending on materials available. Permeability of the
compacted core should not exceed 10-5 cm/s.

The hydraulic gradient relative to the core is the ratio of maximum head of water
to the thickness of the core. Thin cores may be adequate for impermeability but it
is essential to provide well designed filters on either side. The greatest danger
with thin filters is the possibility that a 'blow through' may occur in a segregated
zone.

The principal factors considered in determining core dimensions and


embankment zoning are:

The type and volume of core materials available;


The relative economics of earthfill and rockfill;
The plasticity of the available core material and its effect on the risk of
core cracking;
The extent and rate of reservoir draw-down;
The nature of the foundation rock under the core.
Cracking of Core - cracks frequently occur in earthfill dams and in cores of rockfill
dams. Care must be taken to prevent such cracking and the Engineer must
decide whether the cracks are likely to extend and become serious or whether
they are stable and can be backfilled.

Influence of Post Construction Settlement at Crest on Cracking

Crest
Kind of cracking
Settlement (mm)
Less than 50 No cracking of dams
Equal or greater
Transverse cracking of dams compacted dry may appear
than 50
Greater than 100 Reinforced concrete facing without perimetral joint may crack
Equal or greater
Longitudinal cracking between core and shell may appear
than 130
Greater than 160 Longitudinal cracking of core compacted dry may appear
Greater than 180 Hydraulic fracturing may appear
Transverse cracking of core compacted wet may appear.
Equal or greater
Longitudinal cracking between core compacted wet and shell
than 220
may appear.
Equal or greater Asphaltic concrete facing may crack (self healed for
than 350 settlement of 350mm)
Longintudinal cracking of core compacted wet may appear.
Greater than 400
Reinforced concrete facing with perimetral joint will crack
Greater than
No uncracked dam in those studied
1000
Greater than
All dams exhibit transverse cracking
1200
Equal or greater
Serious cracking of asphaltic concrete facing
than 1400
Equal or greater
Cracking needing substitution of reinforced concrete facing
tahn 3800

Decked Rockfill Dams


Timber Face - used mostly for mining purposes, relying upon dumped rock for
stability with a
facing of timber for

watertightness. Leakage under and around the dam could not be prevented, but
usually did no harm to a free-draining rockfill. Although not used in present day
construction, the value of timber should not be overlooked.

Steel Face - consists of large welded panels, connected by flexible joints to allow
for expansion and contraction and any displacement of the plates relative to the
face of the rockfill. To help reduce corrosion, coats of coal-tar epoxy resin
preparation and supplementary cathodic protection are provided below water
level, giving about a 50 year life.

Cement Concrete Face - since cement has a very long life, it is an obvious
watertight membrane on rockfill dams. Details of typical facing are shown in the
figure.

The facing can be tied to the dam in two ways, either poured directly onto the
rubble transition zone. A mortar bed is initially placed which penetrates into the
rubble a few centimeters. This is immediately covered with the concrete to form a
monolithic mass which extends into the rubble and is thus bonded to the dam.

Or, ribs are placed in the bottom of the slab by forcing grooves in the facing. The
ribbed support, however, is unnecessary if the bonding with the backing is
effective.

Two types of facing have been used.


One is a thin monolithic slab of concrete with no joints. It is sufficiently flexible to
conform to movements in the backing without failure and the tensile forces are
distributed by the reinforcements so that numerous small cracks develop rather
than any major failures.

The second type, used in most concrete faced dams, has a facing which consists
of monolithic slabs, 10 to 30 sqm each. The concrete thickness is largely a
matter if experience. Only nominal reinforcement is required, about 0.5%
concrete area in each direction. Water tightness is ensured by copper water
stops.

Asphaltic Concrete Face - two types of asphaltic facings have been used, a
laminated facing consisting of:

1. Rubble concrete masonry transition


2. 10cm thick porous concrete
3. 15cm bituminous concrete, placed in two layers and rolled
4. Reinforced concrete protective and insulating layer 12cm thick.

The outer layer of concrete only serves to protect the bituminous side from
sunshine and physical damage. It is sprayed with water during very hot weather
to keep the bituminous concrete from sagging in plastic flow. The second form
employs an asphaltic concrete paving similar to that used in highways. It is
placed in layers and rolled as for paving. The advantage of a purely asphaltic
paving is that it tends to adjust itself to movement by plastic flow. As with other
thin facings, a transition zone is required to equalise settlement movements and
to provide uniform support.

Rubble Retaining Zone - used in the upstream face to permit a slope that is
steeper than the angle of repose of the rockfill. This makes it possible to reduce
the volume of rockfill, but at the expense of construction of the retaining zone.
There are two types for this zone, a wedge of compacted rockfill, where the
steeper slope is merely the angle of repose of dense rather than loose rock.
Slope angles of 45 degrees can be obtained this way.

The second form is an unbonded rubble masonry retaining wall. It is essentially a


retaining wall, and should be designed as such. The typical width of the base of
the supporting zone is 0.25 the height of the dam.

Impermeable Zone Location

The location of the impermeable zone in a rockfill dam involves the same factors
as it does in the case of an earth dam.

The upstream deck has a number of advantages:


1. It is more stable under the water load, because the downward force of the
water produces frictional resistance to sliding
2. The permeable rock embankment develops no uplift, since the
embankment permits no movement of water upward from the foundation.
3. The impermeable deck can easily be inspected and repaired if necessary.
4. During construction the height of the dam can be increased by dumping
only on the downstream side and extending the membrane upward on the
sloping surface.

The disadvantages of an upstream deck are:

1. The deck is vulnerable to weather and wave attack.


2. If constructed of earth, sudden drawdown greatly reduces its stability and
may cause it to slide.
3. Settlement of the rock embankment tends to produce tensile cracks in the
membrane.

The central core location has a number of advantages:

1. The core is equally supported and is more stable during a sudden


drawdown (if constructed from earth).
2. Settlement of the rockfill induces compressive stresses in the core,
tending to make it more compact.
3. There is less core volume and less cross sectional area for leakage for a
given height of dam and thickness of core.

The choice for dams with impermeable zones depends largely on the stability of
the core material. If it is strong, a near upstream location is often the most
economical. However, if the core material is weak a central location is better.

Filter and Transition Zones

Since the core is established with rock or gravel zones, it is necessary to prevent
the fine core material being sucked into the upstream shell material during rapid
drawdown of the reservoir, or forced into the downstream shell by seepage water
under reservoir head. Transition or filter zones must therefore be provided on
each side of the core.

The upstream filter, if non-cohesive and of proper grading, can serve a valuable
service by providing material for induced self-healing should a transverse crack
appear in the core. Selection of the best material for this purpose is well justified.
Although its prime function is to retain the core material against movement into
the rockfill, the downstream transition material should be selected and placed so
as to inhibit the propagation of a core crack into the compacted rockfill. It is good
practice to widen the transition zones towards each abutment, i.e. where tension
and oblique cracking may occur.
To prevent migration of fines from the core:

D15/D85 < 4-5


(filter)/(zone being filtered)

D50/D50 < 25
(filter)/(zone being filtered)

For sufficient permeability:


D15/D15 > 4-5
(filter)/(zone being filtered)
To prevent segregation of the filter:
D60/D10 < 20
(filter)/(filter)

Single filter between core and rockfill


Double filter to core

Settlement
Settlement is a problem for embankment dams. It begins during construction and
continues for many years after the dam is complete. The two main causes are:

1. The migration or working of fines from between the points of contact


between the larger rock allows the particles to re-orient themselves into a
more dense structure
2. The crushing of the contact points between the larger rocks under the
extreme stress developed by the embankment weight causes the rocks to
develop new points of contact which in turn crush again.

The problem can be avoided by proper compaction during construction. In


earthfill dams it may be possible to overbuild the dam, to make a, say 50% higher
dam which will settle to the correct height. Multi-stage construction also helps.
a. Settlement in section
b. Settlement - elevation
c. Irregular abutment
d. Overhanging abutment

Slope Stability

Introduction

Failure of an embankment dam can result from instability of either the upstream
or downstream slopes. The failure surface may lie within the embankment or may
pass through the embankment and the foundation soil. The critical stages in an
upstream slope are at the end of construction and during rapid drawdown. The
critical stages for the downstream slope are at the end of construction and during
steady seepage when the reservoir is full.

It is common to install piezometers to measure pore water pressures and


compare data with the predicted values used in design. Since pore water
pressures are a dominant influence on the factor of safety of slopes, remedial
action should be taken if the factor of safety, based on the measured values, is
considered to be too low.

To ensure stability a number of conditions must be investigated:

1. The slopes must be safe against surface slipping. To ensure this the
slopes must be no steeper than the angle of repose
2. The dam must be safe against sliding on the foundation
3. The mass of the embankment must be safe against a circular arc failure or
composite linear failure. This is likely to occur within an earth core or weak
foundation

The safety against failure can be increased by reducing the gradient of the
slopes.
Homogeneous Embankment

1. Slip within embankment


2. Slip circle through foundation

Zoned Embankment

1. Within rockfill
2. Through rockfill and foundation
3. Through core and foundation

End of construction

Most slope failures occur either during, or at the end of construction. Pore water
pressures depend on the placement water content of the fill and on the rate of
construction. A commitment to achieve rapid completion will result in high pore
water pressures at the end of construction. However, the construction period of
an embankment dam is likely to be long enough to allow partial dissipation of
excess pore water pressure, especially for a dam with internal drainage.
Dissipation of excess pore water pressures can be accelerated by installing
horizontal drainage layers within the dam. However, a total stress analysis would
result in an over conservative design. An effective stress analysis is therefore
preferred. A factor of safety as low as 1.3 may be acceptable at the end of
construction provided there is reasonable confidence in the design data.

Steady seepage

When the reservoir has been full for some time, conditions of steady seepage
become established through the dam with the soil below the top flow line in the
fully saturated state. This condition must be analysed in terms of effective stress
with values of pore pressure being determined from the flow net. The factor of
safety for this condition should be at least 1.5. Internal erosion is a particular
danger when the reservoir is full because it can arise and develop within a
relatively short time, seriously impairing the safety of the dam.

Rapid drawdown in low permeability soils

Rapid drawdown of the reservoir after a condition of steady seepage will result in
a change in the pore water pressure distribution. If the permeability of the soil is
low, a drawdown period measured in weeks may be 'rapid' in relation to the
dissipation time and the change in pore water pressure.

Rapid Drawdown in high permeability soils

The pore water pressure distribution after drawdown in soils of high permeability
decreases as pore water drains out of the soil above the drawdown level. The
saturation line moves downwards at a rate dependant upon the permeability of
the soil. A series of flow nets can be drawn for different positions of the saturation
line and values of pore water pressure obtained. The factor of safety can then be
determined, using an effective stress analysis, for any position of the saturation
line.

Slope Protection
Both faces of an embankment dam must be protected against structural damage.
In normal circumstances the downstream will only be subject to the forces of
nature. The upstream face must be protected against erosion or disturbance by
wave action, ice or by impact of floating debris. Various methods of protection
include large rocks (rip-rap), precast concrete forms, soil cement or the
waterproofing membrane of the dam. Protection must be well above and below
the operating range of the reservoir.
Soil Cement Slope Protection

Rip-rap size : Mass of individual rock = 1000 x (Wave Height Hs)3 (kg)

The rip-rap must be durable, weatherproof and of good quality sound rock to
enable it to withstand the changing harsh conditions.

Seepage Paths

Piping

Internal erosion of the foundation or embankment caused by seepage is known


as piping. Generally, erosion starts at the downstream toe and works back
toward the reservoir, forming channels or pipes under the dam. The channels or
pipes follow paths of maximum permeability and may not develop until many
years after construction.

Resistance of the embankment or foundation to piping depends on:

1. plasticity of the soil


2. the gradation
3. the degree of compactness

Plastic clays with a plasticity index >15, for both well and poorly compacted are
the materials which are most resistant to piping. Minimum piping resistance is
found in poorly compacted, through to well-graded cohesionless soils with
practically no binder. It is also found in uniform, fine, cohesionless sand, even
when well compacted. Settlement cracks in resistant materials may also produce
piping.

Piping can be avoided by lengthening the flowpaths of water within the dam and
its foundations. This decreases the hydraulic gradient of the water flow and
hence its velocity. The flowpaths can be increased by:

Cutoff walls

Impermeable cores

Impermeable blankets extending upstream from the upstream face

Seepage control

Seepage is the continuous movement of water from the upstream face of the
dam toward its downstream face. The upper surface of this stream of percolating
water is known as the phreatic surface. The phreatic surface should be kept at or
below the downstream toe.
The phreatic surface within a dam can be controlled by properly designed cores
or walls.

Internal drain systems

Purpose

A homogeneous dam with a height of more than about 6 m to 8 m should have


some type of downstream drain. The purpose of a drain is:

1. to reduce the pore water pressures in the downstream portion of the dam
therefore increasing the stability of the downstream slope against sliding.
2. to control any seepage that exits the downstream portion of the dam and
prevent erosion of the downstream slope: i.e. to prevent 'piping'.

The effectiveness of the drain in reducing pore pressures depends on its location
and extent. However, piping is controlled by ensuring that the grading of the
pervious material from which the drain is constructed meets the filter
requirements for the embankment material.

Toe drains

The design of a downstream drainage system is controlled by the height of the


dam, the cost and availability of permeable material, and the permeability of the
foundation.

For low dams, a simple toe drain can be used successfully. Toe drains have
been installed in some of the oldest homogeneous dams in an effort to prevent
softening and erosion of the downstream toe.
For reservoir depths greater than 15 m, most engineers would place a drainage
system further inside the embankment where it will be more effective in reducing
pore pressures and controlling seepage.

Horizontal drainage blanket

Horizontal drainage blankets are often used for dams of moderate height.

Drainage blankets are frequently used over the downstream one-half or one-third
of the foundation area. The Bureau of Reclamation's 45 m Vega Dam is a
homogeneous dam which has been constructed with a horizontal downstream
drain. Where pervious material is scarce, the internal strip drains can be placed
instead since these give the same general effect.

Disadvantages of horizontal drainage blankets

An earth dam embankment tends to be more pervious in the horizontal direction


than in the vertical. Occasionally, horizontal layers tend to be much more
impervious than the average material constructed into the embankment, so the
water will flow horizontally on a relatively impervious layer and discharge on the
downstream face despite the horizontal drain.,p> Where this has occurred the
downstream slope is prone to slipping and piping. Repairs can be made by
installing pervious blankets on the downstream slopes or constructing vertical
drains to connect with the horizontal blanket. Such vertical drains are normally
composed of sand and gravel.
Chimney drains

Chimney drains are an attempt to prevent horizontal flow along relatively


impervious stratified layers, and to intercept seepage water before it reaches the
downstream slope. Chimney drains are often incorporated in high homogeneous
dams which have been constructed with inclined or vertical chimney drains.

In some major dam projects, chimney drains have been inclined at a


considerable slope, both upstream and sometimes downstream. An upstream
inclined drain can act as a relatively thin core. In addition to controlling seepage
through the dam and increasing the stability of the downstream slope, the
chimney drain is also useful in reducing pore water pressures both during
construction and following rapid reservoir drawdown.

Dimensions and permeability of drains

The dimensions and permeability of permeable drains must be adequate to carry


away the anticipated flow with an ample margin of safety for unexpected leaks. If
the dam and the foundations are relatively impermeable, then the expected
leakage would be low. A drain should be constructed of material with a coefficient
of permeability of at least 10 to 100 times greater than the average embankment
material.

Thin upstream sloping core

In an earth dam with an upstream sloping core of low permeability, the


foundation is assumed to be impermeable and in a steady state. Under steady
state conditions the small amount of water that seeps through the core flows
vertically downward in a partially saturated zone and then more or less
horizontally in a thin saturated layer along the impermeable foundation. For this
type of dam the downstream shell must be several hundred times more
permeable than the core.
Partial cutoffs

An earth dam constructed without a cutoff on permeable or semi-permeable


foundations of earth or rock may lead to seepage beneath the dam creating
unacceptable uplift pressures and causing instability. If an impermeable cutoff is
installed to 60 % of the depth of the permeable foundation, the flow net and
downstream slope gradient is only slightly modified to a lower level. A theoretical
line of seepage for several depths is given here.

For an effective cutoff the positioning and depth of cutoff must be essentially
'perfect'. Since this is impossible to achieve, other methods of seepage control
should be used in conjunction with cutoffs.

Spillways
The provision of adequate spillway facilities can pose more problems than the
design of the dam. Complete protection against the greatest flood that might
occur would in almost all circumstances be unjustifiable. The existing or possible
future habitation in the valley below the dam must influence decisions to be made
regarding the spillway. Four standards for dam design have been suggested;
Freeboard and still capacity sufficiently to ensure that the dam will not be
overtopped by floods up to probable maximum categories;
Such that the dam can be overtopped without failing, and in so far as
practicable, without suffering serious damage;
Such as to ensure that breaching of the structure would occur at a
relatively gradual rate; and
The height of the dam and storage are small enough that no serious
hazard exists downstream in the event of breaching.

Handling of Flood Waters

Retention in Storage - In rare cases it is economically possible to store the


entire volume of the design flood within the reservoir without overtopping the
dam. The occurence of a subsequent storm shortly after the first must also be
considered. In some cases an auxillary spillway or fuse plug spillway may be built
in for emergencies.

Auxiliary Spillway to another valley. At certain locations it is possible to build


one or more spillway outlets on the rim of the storage basin and to divert flood
waters into adjacent valleys. Impact on the total environment must be considered
before floods can be by-passed in this manner. Generally the main valley will
have carried floods of maybe half the design flood and it is simple to assess the
damage likely to be done by larger floods.
The owner of the dam will be responsible for
damage resulting from diversion of a major
flood into a valley not normally subject to
large floods.

Fuse-Plug Spillways are structures built


instead of an auxiliary spillway. They may be
simple earth banks, flash boards, or other
devices designed to fail when overtopped.
Such plugs should only be used when the
sudden release of water is both safe and not
over-destructive to the environment. For
preference fuse plugs should be so
constructed as to make their intensional
destruction. This is much more positive than
endeavouring to design a structure to fail at a
predetermined overload.

Spillway Location Options - The sites indicated by the red areas are the most
favourable locations for spillway positioning. The order of preference for rapid
concrete construction is indicated by the numbering.
Passage over or through the dam - Many dams are designed for the safe
passage of controlled and uncontrolled flood waters over the crest. Radial or
sector gates are also used in large diversion weirs, however spilling over the
crest is the cheaper method.

Bottom spillway:Advantage - provision can


usually be made for its use for the passage of
floods during construction.
Disadvantage once built its capacity is finite
wheras the forecasting is indefinite.
a single outlet can be blocked by flood debris.

Siphon Spillway
Disadvantage - construction is expensive
- sudden appearance of flood water
downstream
- large flood debris can block outlet.

Gates or no gates - many Engineers


are not inclined to place full reliance
on effective operation of gates at the
time of a major flood. The provision
of gated spillways is usually
economic, whatever height of dam
the cost remains roughly the same
and is only dependent on the
magnitude of the flood provision. The
possibility of maloperation can not be
overlooked and their accessibility is
important.

If proper gate operation can not be guaranteed then the effect of flood water
passing over the top of gates must be investigated. Hydraulic gates are most
reliable, followed by mechanically and electrically operated gates.

Spillway gates may therefore be installed:

Purely on economic considerations of total cost of dam and spillway, or


In order to protect upstream property or installations, or
In order to exercise control over the magnitude and duration of flood flows
below the dam - having due regard to flow in downstream tributaries, or
In order to derive some economic benefit from water stored above the
fixed crest level.
Uncontrolled Spillways

The discharge over a spillway crest is given by the formula:


Q=C.L.H3/2

where Q=discharge, C=coefficient, L=length of the crest, H=effective head of


water.

Crest Profile - the crest of an overfall spillway is usually


dimensioned to conform to the underside of the nappe of the
free-falling jet. Greater efficiency is obtained by operating a
spillway at greater than design head, as can be seen in the
figure showing the effect of nappe profile on coefficient.

It is common practice to choose the design head for the


nappe as 75%-80% of the maximum expected head. When
the spillway so designed does pass the greater flows,
pressures lower than atmosphere will occur over the crest, causing problems
associated with cavitation.

The flow over a spillway gives rise to self-excited vibration, in which three
coupled elements are involved; the jet, the overflow crest and the air cushion
between dam and jet. This can be avoided by using splitters on the crest.

The cross section of a dam is normally determined to


meet stability requirements. Optimum nappe can be
obtained by the provision of an upstream overhang, as
can be seen in the figure on the left, with the overhang
not less than 0.3 times the height of the dam.

With the reservoir at a particular level the discharge over the spillway will be
proportional to its length. It is possible to introduce variations in the plan shape of
the spillway crest so that the effective length is increased, for example,
rectangular 'duckbill' spillway or triangular sections.

In narrow gorges it is often expedient to adopt the glory-hole spillway. The design
of a glory hole spillway is involved since it includes flow over the weir, free or
forced flow in the shaft, flow around the bend and flow in the discharge tunnel.
Since velocities are very high at the bottom of the shaft damage to lining is likely
to occur. The main disadvantage with the glory-hole spillway is that beyond a
certain surcharge the discharge only increases slowly with increased head. It
does not provide any substantial margin for underestimation of the maximum
flood.

Foundation
The foundations of a dam must be able to withstand without unacceptable
deformation the loads imposed upon it by the structure, both immediately after
filling the reservoir and in the long term.

With time, deteriotation by saturation and percolation of water can occur, whilst
soft rocks and clays usually exhibit lower residual strengths under sustained
loading than under rapid testing. It is the 10-20m of rock immediately below the
dam that is of greatest importance.

Terzaghi's advice might well apply to foundation testing - "...because of


unavoidable uncertainties involved in the fundamental assumptions of the
theories and the numerical values of the soil constants, simplicity is of much
greater importance than accuracy." The Engineer must use all the available
resources, concentrating on the zones of foundation that appear weak and that
will be subject to stresses once loaded.

Foundation Preparation

Introduction

If it is economically feasible, all material under the base of a proposed dam which
could cause excessive settlement and leakage should be removed. If this cannot
be done, the dam design should be modified to take account of such material.
Sometimes it may be necessary to remove material to considerable depths in
isolated areas of the foundation. This is known as dental work. The general
overall removal of material is termed stripping, whereas the removal of loose
masses of rocks on the abutments is termed scaling. The engineering geologist
has to determine the expected depth of weathered or unsound rock or
overburden that must be removed in advance of construction.

Foundation programme

A planned programme of foundation excavation should be initiated with the view


that the volume of excavation and configuration of the excavation will
approximate reasonably to the plans and specifications established. It is the
responsibility of the construction engineer to ensure slopes for excavations will
be permanently stable or will not fail during construction. In earth materials
slopes of 1.5:1 to 2:1 are excavated in permanent cuts and slopes of 1:1 are
established in temporary cuts, except where unusual conditions are anticipated.
In bedrock that is not closely fractured or does not contain inclined planes of
potential slippage, such as bedding planes in weak rocks, slopes are excavated
at angles up to the vertical.

Problematic foundation materials

In foundations in unconsolidated material excavation of natural deposits may


reveal inadequate localised or widespread foundation materials that require
special treatment or total removal. Unacceptable or inadequate materials rich in
organic substances such as topsoil, swamp muck or peat, loose deposits of sand
or silt, talus accumulations and plastic, active, sensitive, or swelling clays.

Poor foundation conditions in rocks are associated with close fracturing,


weathering or hydrothermal alteration, or poorly indurated sedimentary rocks.

Excavation in bedrock

The objective of excavation is the preparation of a clean surface that will provide
optimum contact with the dam materials, whether earth or concrete is to be
placed on that surface. Therefore excavations in bedrock should extend into firm,
fresh rock. Any closely fractured zones extending downward, especially if
containing soft altered materials such as clay gouge or other products of
weathering, should be removed if feasible.

Prolonged exposure of both earth and rock foundations to the atmosphere or to


water frequently results in deterioration by hydration, dehydration, frost action,
shrinkage, and expansion with changes in temperature. It is good practice to
protect reactive surfaces that will be exposed for long periods of time with
bituminous materials. Alternatively, original cover is not removed until final
cleanup and just prior to placement of the dam.

Construction on unconsolidated deposits

At an ideal site, excavations in unconsolidated deposits should extend to solid


bedrock for the full width of the dam, whether it is constructed of concrete or
earth/rock fill. However, there are many locations where the depth of the valley fill
is so great that dams must be constructed in part or entirely on unconsolidated
deposits. Where this is the case steps must be taken to improve the engineering
properties of the foundation materials and to reduce subsurface seepage to
allowable levels.

Except for low dams of small gross weight, concrete dams are not built on
unconsolidated deposits because of their generally low bearing strength. Larger
dams constructed in whole or in part on unconsolidated deposits should without
exception, be earth or rockfill dams with the capacity to adjust to settlement in the
foundation materials.
For concrete dams

Preparation of foundations - the extent of the work that will be necessary in the
foundations for a concrete dam will be determined by two main factors, their
strength to sustain the loads that will be imposed by dam and the reservoir water,
and the effect of water entering the foundations under pressure from the
reservoir.

Generally the quality of foundations for a gravity dam will improve with depth of
excavation however the abutments for an arch dam often do not improve with
distance excavated into the sides of the valley. Deterioration of clay could
endanger the dam and/or lead to collapse of abutments downstream from the
dam.

Frequently the course of the river has been determined by geological faults or
weaknesses; proving of the river bed is therefore of first importance in the
investigation stage. The depth to be excavated will depend upon the nature of
the infilling material, the shape of the excavated zone, and the depth of cutoff
necessary to ensure an acceptable hydraulic gradient after the reservoir is filled.

Concrete dams may be constructed on foundations other than massive rock, i.e.
shales, glacial deposits or even sand for river works. Each case must be
examined relative to permeability, settlement, and load-carrying capacity (vertical
and horizontal).

The final preparation of the foundation should be undertaken just prior to the
placement of concrete. It should include the removal of loose rock and all debris,
roughening of smooth rock surfaces, washing down of all surfaces, and the
removal of excess water from pools to leave a clean damp surface to receive the
concrete.

Foundation Design

1. Pressures associated with dams and reservoirs


2. Mechanisms of Foundation Failure
3. Geologic Conditions Promoting Foundation Failure
4. Bearing capacity
5. Seepage
6. Settlement

1. Pressures Associated with Dams and Reservoirs

Construction of a dam and filling of the reservoir behind it create load stresses on
the floor and sides of a valley that did not exist previously.
The kinds and distributions of imposed stresses created by a dam on its
foundation depend on the shape of the dam and the materials used in its
construction.

Dams built of masonry or concrete can be considered to behave as cohesive,


rigid, monolithic structures. The stresses acting on the foundation is a function of
the gross weight of the dam as
distributed over the total area of the
foundation on which the dam rests.

Earth and rock fill dams exhibit gross


semi plastic behavior, and the
pressure on the foundation at any
point depends on the thickness of
the dam above the point.

Pressure due to water in reservoir

The pressures exerted by earth and rock-fill dams resemble in some respects
those exerted by the water in a reservoir, but pressure distribution is modified by
the fact that the materials of construction have some inherent strength, and fail
only after some threshold stress has been exceeded. Pressures exerted by water
in the reservoir behind a dam are hydrostatic and increase linearly with depth.

The pressures are


hydrostatic and increase
with depth. On the
assumption that the
pressures are directed
normal to the floor and
sides, they are shown as
vectors of increasing
magnitude with depth.

Pressures from the weight of a rigid concrete dam

The deadweight load of a concrete dam is distributed over the total area of the
foundation and is shown by vectors normal to the surface beneath the dam. The
figures are essentially static, and depend only on the weight of the dam and the
area of the foundation.

Water exerts hydrostatic pressures not only on the floor and walls of a reservoir
but also on the upstream face of a dam. D is the depth of water in a reservoir, P
is the hydrostatic pressure per unit area acting on the vertical face of a concrete
dam assumed to behave as a rigid body. The change in pressure with depth (in
the y direction) is given by dP/dY=þg in which þ is the density of water and g is
the acceleration due to gravity.

Torque about 0 = þgD³/6

Resultant Pressure = þgD²/2

In calculations of the stability of the dam


the torque tending to rotate the dam
about 0 should be added to the
tendency of the dam to be rotated in the
same direction about the same point by
uplift forces related to seepage beneath
the dam.
Forces acting on a rigid dam owing to hydrostatic pressures

Figure 1 illustrates an earth dam, a non rigidstructure that under stress behaves
semiplastically. Because of relatively easy internal adjustments to loads, the
pressure exerted on the
foundation are
approximately equal to
the weight of overlying
prisms of material of
different heights.
Pressures exerted on
the dam by water in the
reservoir tend to cause
greater adjustments
near the base of the
dam than at shallower
depths.
A cross section of a concrete gravity dam, presumed to behave as a rigid body.
When the reservoir is empty, the weight of the dam is directed vertically
downward. When the reservoir
is full, a combination of
hydrostatic pressure on the
upstream face of the dam and
the weight of the dam produces
a force vector inclined
downstream away from the
vertical force vector, and there
is a tendency for the dam not
only to be displaced
downstream but also to rotate
about the downstream toe of
the dam because of a torque.
These figures show force vectors for empty and filled reservoirs behind concrete
arch dams. Unlike gravity dams, arch dams because of the egg-shell effect tend
to resist downstream dislocation and the displacing forces, instead, are
transmitted laterally through the dam and toward the abutments.

Geologic Conditions Promoting Foundation Failure


The geologic conditions in foundations for concrete dams that should be avoided
are indicated below.

Brittle, fractured sandstones rest on a weak


shale layer dipping upstream.

Horizontally layered limestones rest on a


weak shale layer which extends
downstream to a steep slope in the valley
floor.
Fractured crystalline rocks lie above a flat
fault containing sheared, gougy materials of
very low strength.

Intersecting strong conjugate joints have


attitudes that promote easy mass shear
dislocations.

Sedimentary rocks dipping downstream are


intersected by a fault dipping upstream and
containing materials of low strength.

Folded rocks containing thin, weak layers of


shale present a potential for foundation
failure.

Slope failures toward abutments (in direction of the dam axis) which disturb or
dislocate the abutments are rare. In concrete dams in which slopes in the
abutment areas maintain
themselves during
excavation for the
foundation, the possibility
of downslope movement
along surfaces that
intersect the foundation
of the dam is remote
because of the added
stability provided by the
weight and strength of
the dam. However, the
possibility that slopes
above the dam, especially in deep valleys, may fail and bury surface structures
with rock and/or soil debris.
Figure - Conditions promoting possible slope failure beneath abutments of an
earth or rock-fill dam along curves shear surfaces. Shale beneath a sandstone
layer has been weakened by infiltration of water from the reservoir.

Bearing capacity

To avoid shear failure, the foundation pressures used in design should have an
adequate factor of safety when compared with the ultimate bearing capacity of
the foundation. If failure is to be avoided, then a factor of safety must be applied
to the ultimate bearing capacity, the value being obtained being the safe bearing
capacity. The ultimate bearing capacity is defined as the least pressure which
would cause shear failure of the supporting soil immediately below and adjacent
to a foundation. However, this value still may mean risk of excessive settlement
or differential settlement. Thus the allowable bearing capacity which is used in
design will take into account all possibilities of ground movement and so its value
will normally be less than the safe bearing capacity.

Seepage

Seepage under an embankment is much more dangerous than that for a


concrete dam, since embankments are usually built on soft material which is
liable to be scoured out and it is also vulnerable to influx of water; whereas a
concrete dam is usually built on rock which is not worn away so rapidly by the
scouring action of water; and even then a defective dam will not necessarily be
endangered by passage of water through it or even under it.

Basic seepage problems

Stored water behind dams, gives rise to three basic seepage problems, which
can lead to difficulties and in serious cases to total failure:

1. Piping occurs when water picks up soil particles and moves them through
unprotected exits, developing unseen channels or pipes through a dam or
its foundation.
2. Heave or slope failures caused by seepage forces.
3. Excessive loss of water.

Three basic methods for controlling seepage are:

1. Use of filters to prevent piping and heave


2. Seepage reduction
3. Drainage
Settlement

All structures undergo some settlement, regardless of their construction or of the


quality of their foundations. Structures made of soil or founded on soil settle so
much that their performance is affected and their safety is compromised.

Concrete dams are almost always based on strong rock foundations where
settlement of the dam is kept to a minimum otherwise the dams would crack
leading to serious structural faults. Embankment dams can be founded on soft
compressible materials and are able to withstand large settlements.

Causes of settlement
Measurement of settlement
Effects of settlement on structures
Settlement due to changes in environment

Causes of settlement

1. Bearing capaicty failure or instability, including landslides.


2. Failure or deflection of the foundation structure.
3. Elastic or distortion of the soil or rock.
4. Consolidation (compression) of the soil or rock.
5. Shrinkage due to desiccation.
6. Change in density due to shock or vibration.
7. Chemical alteration of constituents, including decay.
8. Underground erosion.
9. Collapse of underground openings such as caves or mines.
10. Structural collapse due to weakening of cementation upon saturation.

Measurement of settlement

Measurement of settlement within a dam should illustrate the progress of


consolidation in the dam and point out whether addition of height will be
necessary to maintain freeboard. In embankment dams settlement
measurements are helpful in computing the volume of material placed in the dam
from the dimensions of the completed structure and provide a check on original
design specifications.

Measurement of Crest Settlement

Crest settlement is measured by bench marks placed at intervals along the top of
the dam. Obviously these are tied to a reference bench mark on the abutment
which is immovable.
Measurement of Internal Settlement

Measurement of internal settlement is made using settlement plates embedded


in the dam or the foundation.

Diagram of settlement plates -

Effects of settlement on structures


The settlement configuration of a uniform load on a thick deposit of compressible
soil is a saucer shaped depression which extends beyond the limits of the
structure. If the loading is irregular or the soil uniform, the saucer shaped curve is
distorted. If the deposit is thin, the 'saucer' is flattened at the centre. The effect
that the settlement has on a structure depends on where the structure is located
in the depression and on how the movements at that location influence the
performance of the structure.

Total settlement
Tilting
Distortion

Total Settlement

The total amount of settlement a structure can undergo without damage is large
provided it is relatively uniform. However, with large amounts of settlement
several forms of trouble develop. In embankments and dams on earth
foundations the result will be a lowering of the crest. This is an insidious form of
trouble since it usually develops slowly, often without the operators of
maintenance personnel being aware of the loss of height and free board.

Allowances must be made for settlement in the design height, and periodic
measurements should be taken to be sure that the proper crest level is
maintained. A considerable part of the settlement, both of the foundation and of
the embankment, occurs during the construction period. This can result in
discrepancies in the computed volume of the structure unless it is anticipated and
careful records of the settlement are kept. With proper allowances, embankment
settlements of a few metres can be tolerated. Total settlement is not a serious
matter if it is anticapted and provisions made before hand.

Tilting

Tilting occurs in the parts of the structure that are outside the centre of the
saucer-like depression. It also takes place when the structure is unevenly loaded,
or when the soils are non-uniform. It is of importance mainly with tall structures
such as large retaining walls, transmission towers, water tanks, and smoke
stacks. It is particularly serious in structures that are inter-connected. The
amount of tilt which can be tolerated depends on the height-width ratio of the
structure.

Distortion
Differential settlement which produces relative movement is known as distortion.
The load of an embankment on a uniform soil produces a settlement profile as
shown below. There is also a tendency for cracks to develop as indicated. These
cracks may lead to accelerated seepage, erosion, and even failure.

Figure 1 - The load of an embankment on a uniform soil produces a settlement


profile as shown and a tendency to develop cracks at the points indicated. Such
cracks can possibly lead to accelerated seepage, erosion and even seepage
failure.

Figure 2 - The non uniform foundation thickness and the greater loading at the
centre than at the abutments brings about a sagging profile along the axis. Shear
cracks tend to form as shown. These are far more serious because they extend
from upstream to downstream and several dam failures have been attributed to
such cracking.

Figure 3 - When a small portion of the embankment extends beyond the main
section shear cracks sometimes develop.

Figure 4 - Similar settlement adjacent to an overhanging abutment can create


cracks at their juncture.

Settlement due to changes in Environment

Changes in environment can bring about a reduction in void ratio in certain soils
and a corresponding settlement. Shock and vibration from earthquakes, blasting,
and construction machinery can cause loose cohesionless soils to densify. In
addition, flow failure may accompany the settlement if the soils are saturates.
Detioration of cementing agents from physical and chemical changes brought on
by exposure and inundation can cause the collapse of loose skeleton soil
structures and settlement. Bacteriological decay of organic materials can
produce settlement accompanied by formation of gas pockets. Such decay is
inhibited by permanent submergence.

Exposure to soils to hot dry weather during construction can cause both
settlement and shrinkage cracking. A desiccated clay that is subsequently
inundated may swell and damage a superimposed structure or embankment by
heave. Moreover, the cracked, swollen soil is weakened and can be a cause of
foundation failure.

Foundations Improvement
1. Pre-Consolidation
2. Densification of cohesionless soils
3. Dynamic Compaction
4. Grouting

Pre-Consolidation

Pre-consolidation is a useful foundation treatment method in compressible soils,


depending on the rate of consolidation. If the rate is rapid (one to two months for
50%) it will be possible to pile up the soils removed from stripping and scaling of
the abutments to form an artificial surcharge.

If the rate is slower (one to two years for 50%) the dam weight can be used to
consolidate the soil and increase it's strength. It would be necessary to control
the rate of construction so that the weight applied does not exceed the ability of
the foundation to support the structure safely. It may, however, be necessary to
increase the length of the construction period to obtain a sufficient gain in
strength. Drainage of the foundation can also help to accelerate consolidation.

Densification of cohesionless soils

Densification of cohesionless soils is carried out using shock and vibration.


Vibroflotation is used to improve poor foundations. The process may reduce
settlement by more than 50% and the shearing strength of treated soils is
increased substantially. Vibrations can convert loosely packed soils into a denser
state.

A vibroflot can be used to penetrate the soil and can operate efficiently below the
water table. The best results are obtained in coarse sands which contain little or
no silt or clay, since both reduce the effectiveness of the vibroflot.
Dynamic compaction

Dynamic compaction improves the mechanical properties of the soil by repeated


application of very high intensity impacts to the surface. This is achieved by
dropping a weight, typically 10 to 20 tonnes, from crawler cranes, from heights of
10 to 20 metres at regular intervals across the surface. Passes should be
repeated over a site, although several tampings may be made at each imprint
during a pass. Each imprint is back-filled after tamping. The first pass at widely
spaced centres improves the bottom layer of the treatment zone and subsequent
passes consolidate the upper layers. In finer materials the increased pore water
pressures must be allowed to dissipate between passes, which may take several
weeks.

Grouting

1. Grouting Operations in Bedrock


2. Dam Construction on Unconsolidated Deposits
3. Grout
4. Types of Grouting
5. Pattern Grouting
6. Blanket Grouting
7. Curtain Grouting
8. Off-pattern, Special Purpose Grouting
9. Grouting Consistency and GroLuting Pressure

Grouting Operations in Bedrock

The goal of foundation and abutment grouting in bedrock is improvement of


strength and bearing capacity and the filling with grout of underground
channelways that have a potential for impermissible seepage. The most general
technique uses drilling and pressure grouting, either with water-cement mixtures
or with other types of sealants.

Preliminary geological and geophysical investigations usually reveal only the


general characteristics of the bedrock, it is not until the keyway for the dam has
been excavated and the bare rock can be examined. This is a critical time
because the constructor is eager to proceed with the dam construction, however
this is the last chance to ensure that all the fissures are sealed to prevent water
loss at a later stage and must be extensively treated to assure ultimate safety of
the dam.

Although grouting of a rock foundation may be conducted with meticulous care,


the possibiliy always exists that some channelways of underground water
circulation remain and that flow through these chanelways will accelerate as the
reservoir is filled. If the volumes are excessive then remedial steps must be
taken, otherwise the flows may be intercepted and diverted by drain holes or
porous prisms.

Dam Construction on Unconsolidated Deposits

There are many locations where the depth of valley fill is too great to remove and
so the dam or parts of it may have to be built on unconsolidated deposits. Cross
sections of several earth and/or rockfill dams constructed at least in part on
unconsolidated subsurface deposits are shown below. It is clear that
considerable information as to the distribution and permeabilities of subsurface
materials is required prior to the design and construction of cut-off features.

Rockfill dam. Impervious


membrane (asphaltic concrete)
extends to a grout cap on
bedrock.

Cut-off trench extends to bedrock

Cut-off trench penetrates


impervious layer in
unconsolidated valley fill.

Cut-off extends to layer of


impervious material in
unconsolidated valley fill. Grout
holes extend through a limestone
layer in bedrock below valley fill.
A cut-off is provided by sheet
piling driven into an
impervious layer in valley fill.

Flow beneath dam is reduced


by a leyer of impervious
material placed upstream from
the dam.

Grout

Grout is a liquid, either a uniform chemical substance or an aqueous suspension


of solids that is injected into rocks or unconsolidated materials through specially
drilled boreholes to improve bulk physical properties and/or to eliminate seepage
of groudwater.

There are three basic types;

1. Portland cement-base slurries


2. Chemical Grouting solutions
3. Organic resins, including epoxy resins.

Portland based are the most widely used.

Types of Grouting

In dam foundations three kinds of grouting programs are identified:


1. Shallow blanket or consolidation grouting over critical portions
2. Curtain grouting from a gallery or concrete grout cap
3. Off pattern, special purpose grouting to improve strength

Some cross sections of dams with rock foundations showing locations


of drilled holes for foundation treatment.

A - Curtain grout holes


B - Blanket grout holes
C - Special purpose, off-pattern grout holes
D - Drain holes

Rockfill dam with


impermeable concrete face

Zoned earth and rock-fill


dam

Zoned earth and rock-fill


dam
Earth dam

Concrete gravity dam with


'C' holes intersecting a
fault zone

Concrete gravity dam with


double grout curtain and
'C' holes intersecting a
permeable fault zone

Concrete gravity dam with


special purpose 'C' holes
Concrete gravity dam wiht
a porous filter to collect
seepage water

Hollow conrete gravity


dam

Concrete buttress dam


Concrete arch-dam

Concrete arch-dam

Pattern Grouting

Plans for dams commonly include broad specifications for a systematic program
of blanket and/or curtain grouting. Grouting is an uncertain process, it is
impossible to accurately estimate the amount of grout required, and usually the
'take' amounts moderately to greatly in excess of the estimate. 'Grouting is an art
and not a science.'

Pattern grouting is grouting included in the plans and specifications for a dam
and commonly is the basis for estimation prior to construction of the total footage
of grout holes and the expected amount of grout consumption. It is general
practice to lay out locations of grout holes in the plans with a definite, systematic
pattern, spacing and assumed depths.

Blanket Grouting

Are intended to remedy flaws in the foundation, such as fractured rock, by


reducing permeability and increasing bulk strength. Although holes may be
routinely drilled normal to the foundation surface, there is considerable merit in
directing the holes to intersect specific local features identified in the dam
foundation during excavation. Blanket grouting must be completed before
construction of a dam.

Locations of blanket grout


holes may usefully be
indicated on plans and
specifications for several
types of dams. The
drawings are entirely
schematic, and no scale is
shown, on the assumption
that the actual number of
holes will be determined by
the area and the cross-
sectional configuration of the excavation for the dam foundation.

Curtain Grouting

In earth / rockfill dams, curtain grouting is usually completed before a dam is


constructed and involves filling a narrow excavated trench in the foundation with
concrete. The exception to the timing of the grouting operation is grouting after
construction for a grouting cap at the upstream heel of a dam.

Curtain grouting of the foundations of concrete dams is most effective after


completion of the dam, at a time when the full load is being applied to the
foundation. Under such circumstances higher pressures may be used in grouting
so as to assure maximum travel of grout in all directions along flow paths
intersected by grout holes.

In gravity and gravity arch


dams of moderate to large
size it is common practice to
construct a gallery inside the
dam for drilling curtain grout
holes and drainage holes.
Foundations of small gravity
and thin arch dams are
efficiently grouted from grout
caps along the contact of
the upstream face of the
dam with rock.

Where there are no geological controls the depths of curtain pattern grout holes
are determined by a formula. A frequently used formula is: the vertical depth of
grout holes shall be a third of the dam height at the location of the hole plus (15 -
20m).
Off-pattern, Special Purpose Grouting

During investigations prior to dam construction, or as unanticipated geological


conditions are exposed in foundation excavations, the need for 'off-pattern' grout
holes may be required. These holes are drilled and grouted to improve the
strength and / or reduce the permeability of rock masses that are not intersected
by blanket or curtain grout holes.

The depths, directions and inclinations of the grout holes are determined by the
three-dimensional geometry of zones of incompetent and / or permeable rocks as
revealed by field examination of bedrock exposures in foundation and abutment
excavations

Inclined holes from the surface and


horizontal holes from a shaft intersect
steep faults and associated fractures at
depth.

Inclined holes are drilled to


intersect sheeted zones in
crystalline rocks.
Dipping sedimentary layers present a potential for seepage under a dam.
Inclined holes are drilled to intersect a limestone layer and a brittle sandstone
layer.

Inclined holes are drilled into


jointed and sheared rock in crests
and troughs of folds.

Holes are drilled to intersect a


closely jointed igneous dyke at
depth.

Off-pattern grout holes intersect a


jointed, weathered zone in
crystalline rocks below an
unconformity.
Grouting Consistency and Grouting Pressure
The ability of cement grout to penetrate interconnected open spaces is limited by
the dimensions of the open spaces and the amount and size of the cement
particles suspended in the water base. Openings of slightly greater than capillary
size that may permit free circulation of groundwater are quickly filled and
obstructed by cement particles and lateral and/or vertical travel of the grout
suspension is greatly impeded or brought to a halt. In larger openings,
presupposing interconnecting avenues of circulation, grout suspensions move
with ease and in some instances travel surprisingly large distances.

If easy grout circulation continues with the progress of the grouting operation, the
suspension is gradually thickened and, if necessary, the pressure
correspondingly increased until filling of available openings is indicated by refusal
of the grout hole to accept additional grout. Grout leaks at the surface should be
calked or otherwise sealed to promote confined subsurface movement of grout
suspensions.

The definitions of thin and thick are not precise, but generally thin mixtures are
construed to mean mixtures prepared by mixing 8-10 volumes water with one
volume of cement. Thick mixtures have volume proportions of cement to water of
approximately 1:1, or thicknesses that are not so great that the grout can not be
pumped with reasonable ease. In highly permeable materials thick grout mixtures
are indicated with inert additives such as clay or sand may be added to grout
suspensions as inexpensive fillers.

If grout pressures exceed certain limits there is the possibility of foundation


dislocation and new channelways being created. Because of a wide range in
complexity of patterns of underground circulation it is not possible to establish a
rigid formula for controlling grout pressures at the top of a grout hole. For curtain
grouting, a rule that is sometimes followed states that pressure in an initially thin
grout suspension is increased to a level which establishes a free circulation
(assuming channelways for circulation are present) but not in excess of the
calculated hydrostatic pressure of the filled reservoir at the elevation of the collar
of the grout hole plus 0.7-3.5 bar.

Premature thickening of grout or reduction of pressures to cause grout refusal in


a grout hole should be avoided unless it can be demonstrated that grout is
escaping to the surface well outside of the foundation area. So long as grout is
circulating somewhere in the foundation of a dam or in the near proximity of the
foundation, it must be assumed that it is contributing to an improvement of the
engineering properties of foundation materials and to a reduction in permeability
to groundwater seepage.
Prevention of Piping Failures

Piping failures

Water that percolates through earth dams and their foundations can carry soil
particles that are free to migrate. The seepage forces tend to cause the erodible
soil or soft rock to move towards the downstream face of the dam. That is if the
seepage forces are large enough and the pore spaces in the material are large
enough. Along the unprotected discharge face AB, the soil will heave if the
gradients are large enough.

Every seepage discharge surface, both internal and external, which could be
susceptible to piping or heave must be covered with filters that permit water to
pass but will hold the soil particles firmly in place.

Filter criteria

Since the core is stabilised with rock or gravel zones, it is necessary to prevent
the fine core material being sucked into the upstream shell material during rapid
drawdown of the reservoir, or forced into the downstream shell by seepage water
under reservoir head. Transition or filter zones must therefore be provided on
each side of the core.

The upstream filter, if non-cohesive and of proper grading, can serve a valuable
service by providing material for induced self-healing should a transverse crack
appear in the core. Selection of the best material for this purpose is well justified.
Although its prime function is to retain the core material against movement into
the rockfill, the downstream transition material should be selected and placed so
as to inhibit the propagation of a core crack into the compacted rockfill. It is good
practice to widen the transition zones towards each abutment, i.e. where tension
and oblique cracking may occur.
To prevent migration of fines from the core:

D15/D85 < 4-5


(filter)/(zone being filtered)

D50/D50 < 25
(filter)/(zone being filtered)

For sufficient permeability:


D15/D15 > 4-5
(filter)/(zone being filtered)
To prevent segregation of the filter:
D60/D10 < 20
(filter)/(filter)
Problems associated with natural formations

The foundations and abutments of dams are usually stable under the influence of
the natural groundwater flow. However, reservoir filling greatly changes the
groundwater regime and may lead to piping and internal erosion. The potential
for internal erosion and piping may occur at joints in rock, beds of gravel and in
cavities left by rotting roots, animals’ burrows or other buried organic matter.

Recommendations for preventing piping in natural formations

Field exploration and geological mapping for dam projects should identify the
important soil and rock formations that could cause failure by internal piping or
heave. The geotechnical properties of these materials should be thoroughly
investigated. If the materials are proven to be unsuitable then remedial action
should be taken to improve their geotechnical properties. All new dams and
reservoirs should be carefully observed and monitored once in service to detect
the development of unsafe conditions. If seepage quantities increase or if there is
an unexplained change in seepage conditions then protective measures should
be put into action. Such actions should include lowering the reservoir and placing
weighted filters over areas where seepage discharges occur.

Seepage Reduction
Basic considerations

Seepage-reduction methods make use of impermeable cutoffs, grout curtains,


and upstream blankets, which consume energy at locations within cross sections
where large water pressures and seepage forces have no detrimental effects.
The net result of these methods is that water pressures and seepage forces are
reduced in the downstream region. These seepage-reducing features are usually
combined with properly designed filters and drainage features, since seepage
reduction can only be partially effective by itself.

Drainage Methods

Permeable downstream shells

At dam sites where there is an abundance of at least two different materials with
significantly different permeabilities, a zoned dam may be constructed. In such
cases permeable material is placed downstream of less permeable material,
often with a transition zone between. For example, in a zoned dam which has a
thick impermeable core and rests on an impermeable foundation, the flowpaths
within the downstream portion of the dam will be low. Thus seepage has a
negligible effect on the stability of the downstream slope, which is the ideal
condition in zoned earth dams.

Internal drain systems

Purpose

A homogeneous dam with a height of more than about 6 m to 8 m should have


some type of downstream drain. The purpose of a drain is:

1. to reduce the pore water pressures in the downstream portion of the dam
therefore increasing the stability of the downstream slope against sliding.
2. to control any seepage that exits the downstream portion of the dam and
prevent erosion of the downstream slope: i.e. to prevent 'piping'.

The effectiveness of the drain in reducing pore pressures depends on its location
and extent. However, piping is controlled by ensuring that the grading of the
pervious material from which the drain is constructed meets the filter
requirements for the embankment material.

Toe drains

The design of a downstream drainage system is controlled by the height of the


dam, the cost and availability of permeable material, and the permeability of the
foundation.
For low dams, a simple toe drain can be used successfully. Toe drains have
been installed in some of the oldest homogeneous dams in an effort to prevent
softening and erosion of the downstream toe.

For reservoir depths greater than 15 m, most engineers would place a drainage
system further inside the embankment where it will be more effective in reducing
pore pressures and controlling seepage.

Horizontal drainage blanket

Horizontal drainage blankets are often used for dams of moderate height.

Drainage blankets are frequently used over the downstream one-half or one-third
of the foundation area. The Bureau of Reclamation's 45 m Vega Dam is a
homogeneous dam which has been constructed with a horizontal downstream
drain. Where pervious material is scarce, the internal strip drains can be placed
instead since these give the same general effect.

Disadvantages of horizontal drainage blankets

An earth dam embankment tends to be more pervious in the horizontal direction


than in the vertical. Occasionally, horizontal layers tend to be much more
impervious than the average material constructed into the embankment, so the
water will flow horizontally on a relatively impervious layer and discharge on the
downstream face despite the horizontal drain.,p> Where this has occurred the
downstream slope is prone to slipping and piping. Repairs can be made by
installing pervious blankets on the downstream slopes or constructing vertical
drains to connect with the horizontal blanket. Such vertical drains are normally
composed of sand and gravel.

Chimney drains

Chimney drains are an attempt to prevent horizontal flow along relatively


impervious stratified layers, and to intercept seepage water before it reaches the
downstream slope. Chimney drains are often incorporated in high homogeneous
dams which have been constructed with inclined or vertical chimney drains.

In some major dam projects, chimney drains have been inclined at a


considerable slope, both upstream and sometimes downstream. An upstream
inclined drain can act as a relatively thin core. In addition to controlling seepage
through the dam and increasing the stability of the downstream slope, the
chimney drain is also useful in reducing pore water pressures both during
construction and following rapid reservoir drawdown.

Dimensions and permeability of drains

The dimensions and permeability of permeable drains must be adequate to carry


away the anticipated flow with an ample margin of safety for unexpected leaks. If
the dam and the foundations are relatively impermeable, then the expected
leakage would be low. A drain should be constructed of material with a coefficient
of permeability of at least 10 to 100 times greater than the average embankment
material.

Geology of dams
1. INTRODUCTION
2. TERMINOLOGY
3. CLASSIFICATION OF ROCKS
4. TYPES OF ROCK
5. ROCK PROPERTIES
6. SURFACE FEATURES OF VALLEYS
7. EXCAVATION AND FILLING OF VALLEYS
8. TOPOGRAPHICAL AND GEOLOGICAL CONDITIONS
9. SEISMIC ACTIVITY
10. GEOLOGICAL HAZARDS

Introduction

The geological services required for the engineering of a large dam are in the
following areas;

The safety of the dam on its foundations;


The watertightness of the reservoir basin;
The availability of natural materials for its construction.

The engineering geologist is a key member of an engineering team, since he will


ensure the feasibility of the project, continuing through the design stage and
terminating only when construction has either proved that geological conditions
revealed are in conformity with the premises adopted in design, or he has made
possible proper evaluation of any conditions not foreseen in the earlier stages.

The safety, viability and cost of a dam are all dependent upon geology. Most
rocks have adequate strength but their weakness is in the orientation and dip of
discontinuities relative to the loading from the dam, as well as the infilling
material in, and depth of, weathering in such discontinuities.

It is necessary to investigate both the regional geology and the specific local
geology to ensure a global picture is developed.

Terminology

1. Bedding planes - The planes marking the termination of one sedimentary


deposit and the beginning of another; they usually constitute a weakness
along which the rock tends to break.
2. Foliation - In rocks that have been subjected to heat and deforming
pressures during regional metamorphism, some new materials such as
muscovite and biotite mica, talc and chlorite may be formed by
recrystallisation. These new minerals are arranged in parallel layers of flat
or elongated crystals - the property of foliation.
3. Joints - These are fractures along which no movement has occured. All
rocks are jointed to some extent and weathering occurs in these joints.
They offer pathways for water, any clay infilling offering little resistance to
sliding.
4. Faults - These are fractures along which movement has occured. They
may range from rather inconspicious zones hundreds of metres wide and
many kilometres long. The movement may have formed a zone that is so
crushed and chemically altered as to be unable to support any weight. The
presence of faults may be recognised from such physical features as;

Offset of beds, dykes or veins;


Slickensides;
Gouge;
Brecciation or crushing;
Topographic features like escarpments, linear trenches or sag valleys.

5. Weathering - The following definitions appeared in the Quarterly Journal


of Engineering Geology, UK, 1970.

Fresh Rock No visible signs of weathering


Slightly Penetrative weathering developed in open discontinuity
Weathered surfaces but only slight weathering of rock material.
Moderately Weathering extends throughout the rock mass, but the rock is
Weathered not friable.
Highly Weathering extends throughout the rock mass, but the rock
Weathered material is partly friable.
Completely Rock is wholly decomposed, and in a friable condition but rock
Weathered texture and structure are preserved.

A soil material with the original texture, structure and


Soil
mineralogy of the rock completely destroyed.

Classification of rocks

1. Uniaxial Compressive Strength

Weak - less than 35MPa


Strong 35-115MPa
Very Strong - greater than 115MPa

2. Prefailure Deformation

Elastic
Viscous

3. Failure Characteristics
Brittle
Plastic

4. Gross Homogeneity

Massive
Layered

5. Continuity in Formation

Solid - joint spacing greater than 2m


Blocky - joint spacing 1-2m
Broken - fragmented

Types of Rock

1. Granite
2. Gabbros, Andesites, Dolerite and Basalt
3. Amphibolites
4. Metamorphic Rocks
5. Limestone
6. Sandstones
7. Clays
8. Gravel, Sands and Boulder Clay

Granite

Can bear great pressures


Generally watertight

Investigation must be made for

Fissures
Disintegration due to weathering
China clay

Caution must be taken when large masses of china clay appear, for
it is not feasible to anchor pre-stressed cables in china clay.

Example: The Sarrans dam had a broad foundation of 11,000 sqm of


decomposed granite. To improve the strength, and bearing capacity and to
reduce seepage of the foundations and abutments a grouting programme was
undertaken. This involved 691 tonnes of cement in 81 boreholes which had an
aggregate length of 2800 m or 240 kg per m.

Gabbros, Andesites, Dolerite and Basalt


These types of rock cannot be trusted for dams and reservoirs.
Porphyritic rocks need careful grouting.

Example: The Rieutord dam which is on a tributary of the Loire, necessitated a


considerable amount of grouting. Conversely, the Tirso multiple arch dam in
Sardinia is founded on trachytes and volcanic tuffs with little grout.

Amphibolites

Gneiss, mica schists and associated rocks are considered to be


satisfactory for sustaining bearing pressure and for water-tightness.
However, gneiss and particularly mica schist are less favourable due to
the mica which may facilitate slipping.
Where gneiss and mica schists are associated, a very weak zone of
disintegrated rock may be found at the junction of these two rocks.

Example: the Forks dam, California, founded on gneiss and mica schists, had to
be abandoned in 1929 because of bad foundations which occurred at the
junction of these two rocks which, in themselves, were quite sound.

Metamorphic Rocks

Metamorphic and intrusive igneous rocks are to an extent unpredictable.


However, many satisfactory dams have been constructed on them
particularly in Scotland (for example Pitlochry, Errochty, Shira), but
grouting of the foundations is generally essential. The usual types of dams
constructed are gravity, buttress and rockfill.
Where the rock is weathered at the surface, an investigation is usually
required since weathered formations may prove exceptionally difficult
when the foundations are dug out.

Example: The Lavaude-Gelade dam in the Central Massif, Creuse, France was
founded on altered granulite. The alteration in the granulite was found to persist
to a depth of 20m, in addition to being broken and fissured. The site required an
extensive grouting injection with cement, clay and bentonite.

Limestone

Limestone dam sites vary widely in their suitability. Thickly bedded


horizontally lying limestones which are relatively free from solution cavities
afford excellent dam sites. On the other hand, thin bedded, highly folded,
or cavernous limestones are likely to present serious foundation or
abutment problems involving bearing capacity and water tightness.
Concrete dams have been constructed on Jurassic limestone at Castillon,
where slips and leakage problems have occurred. These have been
surmounted by an extensive grouting scheme.

Sandstones
Sandstones have a wide range of strength depending largely upon the amount
and type of cement matrix material occupying the voids of the rock. Generally
sandstones do not deteriorate rapidly on exposure to the surface with the
exception of shaly sandstone.

As a foundation rock sandstone is not susceptible to plastic deformation, even


with poorly cemented sandstones. However, sandstones are susceptible to
erosion due to the scouring and plucking action from the overflow of dams and so
have to be adequately protected by suitable hydraulic structures.

Sandstones are frequently interbedded with shales. The sandstone-shale contact


may allow seepage of water and may cause potential sliding. Severe uplift
pressures may also develop beneath beds of shale in a dam due to the swelling
characteristics of shales.

Many dams in the English Pennines have been constructed on Carboniferous


sandstones interbedded with shales, most of them as earth embankments.

Example : Longdendale, Langsett, Scar House reservoirs and Ladybower


reservoir on the Sabden shales in the Derwent valley.

Clays

Clay formations are often thick and massive and are frequently associated with
thin seams of sandstone or limestone.

Earth dams or rockfill dams are usually constructed on clay foundations because
clays lack the load bearing properties necessary to support concrete dams.

Example : The embankments of the Staines, Chingford, and other reservoirs in


the Thames and Lee valleys may be cited as reservoirs wholly in London Clay
,whilst the Cheddar reservoir near Bristol lies on Keuper Marl.

Gravel, Sands and Boulder Clays

Gravels, sands and boulder clay of glacial origin are notoriously variable in
composition both laterally and vertically.
As a result dam sites in glaciated areas are among the most difficult to appraise
on the basis of surface evidence. Generally, earth dams are constructed in areas
of glacial deposits.

Example : Selset reservoir in the North East of England is founded on Boulder


Clay.

Rock Properties

The following properties must be examined to ensure the dam will be


stable and the reservoir watertight -

Crushing strength
Shearing strength
Elasticity of rock
Deformability of the rock mass
Tectonic stresses

Crushing Strength

In general the compressive load from a dam on to its foundations will not exceed
10 MPa.

The strength of a rock will depend upon its -

Quality
The degree of weathering
Presence of micro-cracks

The strength of a rock mass will depend upon -

The number of cracks and joints


The nature of their infilling material
Whether there are any rock-to-rock contacts across the joints
Planarity and continuity of seams and foliations

Table - Unconfined compressive strength of rocks

Rock type Strength (MPa)


Siltstone 24-120
Greywacke 20-30
Shale 35-110
Sandstone 40-200
Limestone 50-240
Dolomite 50-150
Granite 90-230
Basalt 200-350
Dolerite 240-320
Gneiss 80-330

Shearing Strength

The minimum angle of friction for sound rock is 55°.

Table - Angle of internal friction of rock

Rock Tangent of Angle of Internal Friction


Tuff 0.9
Schist Biotite 0.5
Limestone 0.6
Limestone (med. grained) 0.5
Granite (weathered) 0.8
The shear strength of a rock mass may be seriously affected by saturation since
both the cohesion and angle of friction will decrease.

Elasticity of Rock

It is not appropriate to classify rocks by elastic constants alone, since many rocks
are nonelastic. Elasticity refers to the property of reversibility of deformation
when subjected to a load. Many fresh, hard rocks are elastic when considered as
laboratory specimens. But on the field scale rocks can be expected to contain
fractures, fissures, bedding planes, contacts, zones of altered rock and clays with
plastic properties.

Therefore, most rocks do not exhibit perfect elasticity. The extent of


irrecoverability of strain in response to load cycles may be important for the
design and can be determined by the slope of the load/deformation curve.

The concave upward curvature of this load/deflection path is typical for fractured
rocks on first loading because the fractures close and stiffen at low loads. When
the reservoir is lowered, the rock unloads along path 2, with a permanent
deflection.

The dam will try to follow the loading, but since it is often more elastic than the
rock, it will move away from the rock on unloading. This could open joints in the
rock or concrete or simply lower the compressive stress flowing through the
structure. Repeated cycles of loading and unloading in response to cyclic
operation of the reservoir would produce the series of loops ('hysteresis').

Some sites have been considered unacceptable for concrete dams because of
large hysteresis even though the modulus of elasticity of the rock itself was
considered reasonable.

Table of Modulus of Elasticity


Rock Type Modulus of Elasticity
- (MPa x 1000)
Limestone 3-27

Dolomite 7-15
Limestone (very hard) 70
Sandstone 10-20

Quartz-sandstone 60-120
Greywacke 10-14
Siltstone 3-14

Gneiss - fine 9-13


Gneiss - coarse 13-23
Schist - Micaceous 21

Schist - Biotite 40

Schist - Granitic 10
Schist - Quartz 14
Granite - very altered 2

Granite - slightly altered 10-20


Granite - good 20-50
Quartzite - Micaceous 28

Quartzite - sound 50-80

Dolerite 70-100
Basalt 50

Andesite 20-50

Amphibolite 90

The large ranges emphasize the need for testing at each site.

Deformability

The modulus of elasticity of rock is normally adequate, but due to the existence
of joints, faults amd seams in the rock mass - sometimes open and sometimes
filled with products of decompostion, the modulus of deformation may be
inadequate.

The capacity of a rock to strain under applied loads or in response to unloading


on excavation is known as deformability. The strains present in rock concern
engineers even when there is little risk of rock failure, because large rock
displacements can raise stresses within structures.

For example a dam founded on varying rock types of different deformability


properties will develop shear and diagonal tension stresses due to the unequal
deflections of the foundations. The deflections can be handled by structuring the
dam correctly, if the rock properties are known and the variation of properties
within the foundations are determined.

Tectonic Stresses

The fact that rock may be in a state of high internal stress is often overlooked. It
is common to assume a vertical stress field due to the weight of overlying rock.
The corresponding horizontal stress will vary with the rock and the rock
formation. Frequently one horizontal principal stress will equal or exceed the
vertical stress, the other being much lower - indicating the existence of large
shearing stresses.

Crustal horizontal stress increases with depth. As excavation proceeds and


loading on the strata is reduced, there will be upward changes in level. As a
result of the reduction in vertical restraint the strata can no longer transfer the
horizontal forces, but buckle upwards with horizontal cracking. This deformation
reduces the horizontal load on the layer so that the underlying strata tend to carry
the horizontal tectonic stress. As a result the strata down to considerable depths
suffer disturbance to their equilibrium. f horizontal cracks are caused then
erosion can occur and resistance to sliding will be decreased.

Testing for rock properties

Laboratory testing

Compressive strength

Unconfined compression
Triaxial compression
Splitting tension (Brazilian)
Four-point flexure
Ring shear

Shear tests

Direct shear
Triaxial shear

Field Testing

In-situ shear tests

Commonly carried out on 'undisturbed' specimens in the galleries of the dam.


Disturbance of the specimen should be kept to a minimum as the specimen is
exposed from the parent rock. The specimen is then protected and loaded in two
directions. It is important that the axes of the jacks pass through the centre of the
zone under test. A normal load is applied and held until any displacements have
stabilised, the tangential load is then applied in steps and displacements
measured. By repeating the test with different normal loads, values of cohesion
and angle of friction can be derived.

Techniques for measurement

Hydraulic Fracturing
Flat Jack Method
Overcoring

Surface Features of Valleys


The shape of a valley and the rock with which it is formed affect the type of dam
and its dimensions.
Type Chord-height ratio
Gorges Under 3
Narrow Valleys 3-6
Wide Valleys Above 6 or 7
Flat country plains -

Dams in Gorges - Cupola or Dome

When the crest chord-height ratio is under 3 and the rock is capable of
withstanding high pressures, not being able to fail by shearing, thin arch or thin
cupola dams are the most successful and the most economical.

Soundness of the foundation is of paramount importance for all arch and cupola
dams.

Dams in narrow valleys

Narrow valleys have a chord-height ratio of between 3 and 6. Gravity arch dams
are normally constructed in narrow valleys providing that the foundations are
suitable.

Example : Piave di Cadore dam (Italy) was constructed as a thick arch dam with
a chord-height ratio of 5.5. It's thickness was less than a gravity dam but more
than a thin arch dam.

If the narrow valley is filled with permeable and compressible material, for
example from a glacial origin, the dam engineer has two choices:

To increase the depth of excavation to bedrock


If the depth of material is economically unfeasible to remove, then
redesigning the dam to an earthfill or rockfill design may be the only
option.

More and more thick arch dams with a thickness of less than the gravity section
will be constructed in the future as more confidence is gained in:

The reliability of new models confirm and even supplant the


mathematical analyses.
The experience of strengthening weak foundations to carry heavier unit
pressures which are to be sustained compared with the gravity section.

Dams in wide valleys


Wide valleys may be defined where the chord-height ratio of the dam is above 6
or 7. In a wide valley nearly every type of dam can be constructed, except a thick
or thin arch dam. The most influential factors in a wide valley in determining the
type of dam are:

The geology of the site.


The proximity of materials from which the dam is to be made.

Many different types of dams have been built in wide valleys;

Gravity Dams : there are many examples of masonry and concrete gravity dams
in wide valleys, especially where the bedrock is close to the surface. The earliest
large example in Great Britain is the Vyrnwy dam (masonry), which supplies
water to the city of Liverpool. The chord-height ratio of the dam is 7.

Earthfill Dams : because there are a great many wide valleys in England, there
are a number of examples of earthfill dams. These dams are most suitable if the
foundation is soft compressible sedimentary strata.

Rockfill Dams : the wide valley is suitable for all forms of rockfill dams.

Buttress Dams : with suitable foundations capable of withstanding direct


pressures and resistance to sliding, the buttress dam can usefully be adopted in
a wide valley.

Example : Scotland, the Errochty and Shira dams are situated in wide valleys
and have chord-height ratios of 10 and 15 respectively.

Dams in Country Plains

Normally, dams are associated with valleys and are not built on level ground in
the middle of sandy plains. However, examples of dams on plains are to be
found on the Rhone diversion canals, the Rhone being diverted by means of
gate-control barrages, into canals. These canals are some 30 miles in length and
lead the water from the Rhone to normal gravity section dams, built several miles
away on alluvial permeable strata.

Other types of dams constructed on flat country and which may certainly be
considered dams, are the embankments of the large reservoirs of the
Metropolitan Water Board, and the large reservoirs at Cheddar, Bristol. There are
also many instances of what might be considered to be dams; the embankments
of which are measurable in terms of kilometres in length and which retain water
well above ground, such as the man-made levees on the Mississppi River.

Excavation and Filling of Valleys


Introduction

Valleys have been formed or have been modified by downward and lateral
erosion of running water and/or ice, and commonly contain unconsolidated
deposits transported by water, ice, or wind. The individual characteristics of a
valley are a function of the topography, climate, rock type and geologic structure.

Artificial reservoirs are usually created by construction of a dam or dams in a


large or small valley, commonly in a constriction. Correct interpretation of the
various physical aspects of a valley reveals much concerning the characteristics
of bedrock beneath a dam site and beneath the floor and sides of the reservoir
basin above the dam site.

Erosion, transportation, and deposition by running water

Running water erodes the materials in the bottom and sides of the channel by
corrosion, corrasion and cavitation.

Corrosion - is a chemical process whereby materials are taken into solution so as


to become part of the dissolved load of a stream. Limestone is very susceptible
to this process.

Corrasion - is a mechanical process that causes materials to wear away and


includes abrasion by solid particles carried by the stream, and evorsion, which
wears down compact materials by the impact of clear water carrying no
suspended load.

Cavitation - requires high velocities in running water and results first from
formation of vapour bubbles because of pressure decrease associated with
velocity increase in accordance with the Bernoulli theorem, and then explosive
collapse of the bubbles where the velocity diminishes.

Deposition of the solid load is a consequence of a decrease in the stream


gradient, volume or velocity. Features of deposition in a stream are alluvial flood
plains, deltaic deposits and alluvial fans.

When considering the construction of a dam and reservoir in a valley the concern
generally is with only a relatively short segment of the total length of a stream,
and particular attention is given to whether in the floor of the valley erosional
features on the average dominate or are subsidiary to depositional features.

Glaciated Valleys
Streamcut valleys that have been modified by glaciers moving through them are
of interest. The figure shows an idealised plan and sections of a stream and
glacier eroded valley with two stages of glacier advance and retreat and prior and
intervening periods of stream erosion. Morainal ridges formed by deposition of
glacial till along the sides of the glacier are called lateral moraines. Stationary
moraine is termed end or terminal moraine.

Gravity slips dislocations in steep-walled valleys

The alluvial, glacial, and landslide deposits on the floors and sides of valleys
generally have locations, configurations, and physical properties that are
identified in the field with relative ease. During planning, design, and construction
of a dam and reservoir an assessment of these deposits can be made without
difficulty, and appropriate measures can be taken for their removal or
stabilisation.
In many steep-walled valleys, stream-cut or glaciated a relatively inconspicuous
kind of slope failure is present, especially in highly competent, crystalline igneous
and metamorphic bedrocks. Although they may not be easily observed, gravity-
slip surfaces may be present in bedrock as indicated in the figure below and
contribute to the instability of the foundation and abutments of a dam that might
be constructed at the site.

Obstructions in Stream Valleys

The two major consequences of impounding water in a natural or artificial


reservoir are -
Deposition of all or much of the suspended and traction load transported
by the stream;
Increase in downward and lateral erosion by clear or desilted water
downstream from the obstruction.

Attempts to control the rate of filling of reservoirs by sediment may include


construction of dams and reservoirs to intercept sediment upstream from a major
facility, such as a large dam for electric power generation, and regional programs
for soil stabilisation and conservation in upstream drainage basins.

Topographical and Geological Conditions for Different Types of


Dams

Gravity Dams

Hard rock at or near the surface.


Depth of soft material above the rock should not exceed 7-10m thereby
avoiding excavation.
Materials for concrete, i.e. aggregate, stone and sand should easily be
accessible within 5-10 miles.
Gravity dams are suited when the length of the crest is five times or more
than the height of the dam.

Buttress Dams

The buttress dam is suitable where the rock is capable of bearing


pressures of 2 - 3 MPa.
Buttress dams require between a half and two thirds of the concrete
required for a gravity section, hence making it more economical for dams
over 14m.
Additional skilled labour is required to create the formwork.
Threat of deterioration of concrete from the impounded water is more
likely than from a thick gravity section.
There is also an elimination of a good deal of uplift pressure, the pressure
resulting from the water in the reservoir and possibly of water from the
hillside rocks gaining access through or under any grout curtain and
exerting upwards underneath the mass concrete dam.

An arch dam utilises the strength of an arch to resist loads placed upon it by 'arch
action'. The foundations and abutments must be competent not only to support
the dead weight of the dam on the foundation but also the forces that are
directed into the abutments because of arch action in response to the forces
acting on the dam. Therefore, the strength of the rock mass at the abutments and
immediately downvalley of the dam must be unquestionable and its modulus of
elasticity must be high enough to ensure deformation under thrust from the arch
is not so great as to induce excessive stresses in the arch.

Multiple Arch Dams

The multiple arch concrete dam is a variety of buttress dam.


The chief geological criterion is that the rock must be absolutely reliable to
bear 2-3 MPa or more without any appreciable settlement (<8mm)
There is some saving in concrete compared with buttress dams.
In respect of uplift, corrosion and economy the two types are very similar.

Thick Arch Dams

The thick arch dam can be built where the crest chord-height ratio is
between 3 and 5.
The chief geological criterion is that the rock must be absolutely reliable to
bear 3.5 MPa or more without any appreciable settlement.
A substantial saving in material compared with that of gravity dams.
Thick arch dams are difficult to design on paper but are well determined
from trials on models.

Thin Arch Dams

Thin arch dams require valleys to have a crest chord-height ratio of under
3, with a radius of under 150m.
The pressure exerted on the valley sides is between 5.5 - 8 MPa
Where there is a vertical radius of curvature as well as a horizontal, this is
known as a cupola or dome type.
Used where cement is expensive and labour is cheap.

Rockfill Dams

Rockfill dams can be built where the following conditions exist -

Uncertain or variable foundation which is unreliable for sustaining the


pressure necessary for any form of concrete dam.
Suitable rock in the vicinity which is hard and will stand up to variations of
weather.
An adequate amount of clay in the region which may be inserted in the
dam either as a vertical core or as a sloping core.
Accessibility of the site and the width of the valley is suitable for the
manipulation of heavy earth-moving machinery, caterpillar scrapers,
sheepfoot rollers and large bulldozers.

Hydraulic Fill Dams

Suitable in valleys of soft material and are constructed by pumping soft


material duly consolidated up to moderated heights up to 30m.

Earthen Embankments

Near the site there must be clay to fill the trench and embanking material
capable of standing safely, without slipping, to hold up a clay core.
An advantage of earthen embankments is that troubles due to the
deterioration of the structure by peaty waters of low pH do not arise.

Composite Dams

Not only can different types of dam can be built in the same valley, but the
same dam can be of different types owing to the varying geological and
topographical features of the dam site.
Many buttress dams also join up with gravity mass concrete dams at their
haunches at the sides of the valley, and again at the centre have a mass
concrete gravity dam to form a suitable overflow or spillway.

Seismic Activity

An engineer is interested in two aspects of seismic activity:

1. Whether natural earthquakes are likely to occur in close proximity to the


dam and would they be of an intensity to cause damage to the dam or
appurtenant structures.
Natural Events

2. Whether filling of the reservoir might induce earthquake activity, with the
possibility of damage to the dam or liability for damage to other structures
or persons. Although the magnitude of the shocks maybe low, the
proximity of the epicenters could make the effects more serious.
Triggered Events
Natural Events

Preliminary investigations should include researching the earthquake history of


the region. This should involve investigating official records and local
newspapers which often reveal shocks felt by people in centres remote from any
seismographs. If no evidence of earthquake activity in the region is apparent, it
would be unwise to assume nothing could happen in the future. Field surveys
should include the recording of all faults in the region and the installation of
seismographs in the region.

The scope of the seismic investigation is decided by the engineer. The engineer
must consider the probable cost in comparison with the cost of conservative
assumptions in design, the effect of such extra cost on the viability of the project,
and the damage that might occur by neglect of such investigations.

Appraisal of the seismicity of the site should be undertaken at the earliest


possible date. Seismographs should be installed to establish the magnitude of all
natural events, their epicentres and depths of focus. Background noise, such as
quarry blasting should be filtered out of the records. Records should be
continued for at least 5 years after filling of the reservoir, and preferably to cover
periods of large drawdown and refilling of the reservoir.

Seismographs - For large dams the installation of seismographs is not


expensive. These seismographs will be triggered to record major events of a
predetermined magnitude. It is usual to install such instruments on rock at the
base of the dam, on the crest of the dam and preferably on rock at a short
distance from the dam.

The magnitude of an earthquake is an indication of its absolute size, or total


energy release. It is measured by the Richter Scale which is an arbitrary
logarithmic scale. It defines the magnitude in terms of the maximum amplitude of
a standard seismometer at a distance of 100 km from the epicentre.

Triggered Events

In this type of seismic activity there is a big seismic trigger system is blasting.
Blasting in nearly situated quarry or any excavation.

Geological Hazards

Valley wall stability


Valley bulging
Mining
Valley Wall Stability

A gorge wherein the side slopes are equal to or steeper than the angle of repose
of loose rock is attractive as a damsite, however, in such a gorge instability of the
slopes can pose serious problems.

Landslips are a common feature of valleys in mountainous areas and large slips
often cause narrowing of a valley which may then look topographically suitable
for a dam. Unless they are shallow seated and can be removed or effectively
drained, it is prudent to avoid land slip areas in dam location, because their
unstable nature may result in movement during construction or subsequently on
drawdown.

Valley Bulging

Valley bulges consist


of folds formed by
mass movement of
argillaceous material
in valley bottoms, the
argillaceous material
being overlain by
thick, competent
strata. These features
cause stress-relief,
that is, as stream
erosion occurs within
the valley the excess
loading on the sides
causes the
argillaceous material to squeeze out towards the area of minimum loading. This
causes the rocks in the valley to bulge upwards.
The valley movement of argillaceous material results in cambering of the
overlying competent strata, blocks of which become detached, and move down
the hillside. Fracturing of cambered strata produces deep debris-filled cracks
which run parallel to the trend of the valley.

Mining

The existence of a mine either under a reservoir or a dam will present many
problems such as:

Possible subsidence of the foundation of the dam


Loss of water from the reservoir
Flooding of the mine
Excessive hydrostatic pressure at faces in the mine

When the mine is under a reservoir there is the possibility that sufficient water
could pass through the intervening rocks to flood the mine, or at least increase
drainage problems. Even if the rock series were sufficiently impermeable to
impede the flow of water, there is the possibility that excessive interstical
pressure could build up - with the danger to mine faces. If the mine is above and
adjacent to the reservoir, saturation of the hillside and change in the water table
could lead to potential instability. Seismic effects from blasting within the mine
might then be sufficient to trigger a landslide.

Any site investigation must include both existing mines and potential mines, for
matters of liability.

Hydrology
1. INTRODUCTION
2. HYDROLOGICAL CYCLE
3. STORAGE CAPACITY
4. FREEBOARD
5. FLOODS
6. HYDRODYNAMIC FLOW NETS
7. ANISOTROPIC BEDROCKS
8. FILLED RESERVOIRS

Introduction

Hydrology is a science of prediction - the likelihood of recurrence of natural


events. Mathematicians may try to predict events based on past history but
Nature is unpredictable as to time and magnitude of occurence.
Based on past information the low flow characteristics of the river will control the
storage required and hence the normal full supply level of the reservoir. High flow
records and flood forecasting techniques provide the basis for design of the
spillway, and hence the flood storage required above normal full supply level.

Meteorology - Weather forecasting is important to the dam engineer because


future seasonal weather could influence the decision as to which type of dam is
built. For example, too short a dry season may preclude the economical
construction of an earthfill dam. A weather station should be established at a
proposed dam site at the earliest possible date. Records of temperature,
humidity, rainfall, wind and air pressures can materially assist the meteorologists
in synthesising storm patterns and is one step in the process of maximum flood
estimation.

Whatever dimensions the Engineer selects for the dam and spillway there will
always be some risk, assessment of the acceptable risk is the art of dam
engineering.

Hydrological Cycle

The cyclic movement of water from the sea to the atmosphere and thence by
precipitation to the Earth, where it collects in streams and runs back to the sea, is
referred to as the hydrological cycle. The cycle is not as simple as that, firstly,
precipitation may fall at all stages, secondly, there is no uniformity in the time a
cycle takes, thirdly, the intensity and frequency of the cycle depend on
geography and climate.

Water in the sea evapourates under solar radiation, and clouds of water vapour
move over land
areas.
Precipitation
occurs as snow,
hail, rain and
condensate in the
form of dew, over
land and sea.
Snow and ice on
land are water in
temporary
storage. Rain
falling over land
surfaces may be
intercepted by vegetation and evaporate back to the atmosphere. Some of it
infiltrates into the soil and moves down or percolates into the saturated ground
zone beneath the water table, or phreatic surface. The water in this zone flows
slowly through aquifers to river channels or sometimes directly to the sea. The
water that infiltrates also feeds the surface plant life and some gets drawn up into
this vegetation where transpiration takes place from leafy plant surfaces.

The water remaining on the surface partially evapourates back to vapour, but the
bulk of it coalesces into streamlets and runs as surface runoff to the river
channels. The river and lake surfaces also evapourate, so still more is removed
here. Finally, the remaining water that has not infiltrated or evapourated arrives
back at the sea via the river channels. The groundwater, moving much more
slowly, either emerges into the stream channels or arrives at the coastline and
seeps into the sea, and the whole cycle starts again.

Man can exercise some control only when the rain has fallen on the land and is
making its way back to the sea.

Storage Capacity

The storage capacity required in a reservoir may be determined in a number of


ways. In tropical regions it may be decided to store the whole runoff from
precipitation in one season. Whether this would ensure continuity of flow would
depend upon the season selected and the seasons occurring later. It may be
decided to provide sufficient storage to ensure continuity based upon a repetition
of past history.

In evaluating storage requirements a hydrologist would use various hydrological


tools such as cumulative mass curves, runoff, estimation of flood design, flood
routing and other factors.

The storage capacity of a reservoir is defined as the volume of water which can
be stored. Initial estimates of storage capacity can be made from topographic
maps or aerial photographs.
The reservoir volume
can be estimated by
planimetering areas
upstream of the
proposed dam site up
to the proposed top
water level. The mean
of the two successive
contour areas is
multiplied by the
contour interval to give
the interval volume, the
summation of the
interval volumes
provides the total
volume of the reservoir
site.

The figure shows a


typical mass curve.

Freeboard

Freeboard - 'The vertical distance between the top of the dam and the full supply
level on the reservoir.'

The top of the dam is the level of watertightness of the structure and may be the
top of a parapet that is watertight throughout its length. Full supply level is the
level adopted in design for the maximum operation of the reservoir.

To determine a value for freeboard the following must be considered;

Flood Surcharge
Seiche effects
Wind set-up of the water surface
Wave action
Run-up of waves on the dam.
Inaccuracy of data;
Large risks if breached;
Type of dam
Floods

Estimation of design flood

There are two methods now commonly used;

The statistical analysis of past floods with extrapolation to estimate the


magnitude and probability of occurence of future floods, and;
The estimation of probable maximum precipitation on to the particular
catchment under the worst meteorological conditions likely to occur over
the catchment, followed by an estimation of the run-off that would result
from such a storm.

The determination of probable maximum precipitation for a particular drainage


basin requires comprehensive study of major storms on record and is a job for
experts. One is limited by the lack of data, records usually do not go back more
than 50 years, which makes prediction of more than the 100 year flood
impossible. As it is, 50 years of data will predict a 100 year flood to within 25%,
and 115 years will predict it to 10%.

The Engineer is faced with conflicting requirements in terms of safety and


economy, he is therefore obliged to use to the best advantage the data and
procedures that are available;

Statistical analysis of past flow records at the site - and extrapolation;


As above, but with extension of the flow records by correlation with flows
from adjacent catchments;
Statistical analysis of rainfall records and extrapolation;
As preceeding, but with extension of data by correlation with other
stations;
Correlation studies including both rainfall and flow records;
Estimation of 'maximum possible' rainfall by Meteorological Services and
application of such data to the estimation of 'probable maximum flood'
from catchment;
Comparison with known events and other designs adopted for the region
by the use of such means as the Creager coefficients.

When a flood enters a reservoir it will cause the water level to rise, with
consequent discharge over the spillway. The reservoir level will continue to rise
until the free discharge over the spillway equals the inflow at time 'X' on the
figure. Spillway discharge will then exceed inflow until the reservoir level falls to
spillway crest level.

If spillway gates are installed they can be opened in advance of peak of the flood.
The rate at which they can be opened will usually be governed by permissible
river rise conditions downstream. There is the danger that the flood inflow will not
reach the volume
anticipated and the
water will be wasted or
a flood of unjustifable
size will be created
downstream of the
dam.

Hydrodynamic Flow Nets

Flow of water through permeable materials is directional and is in response to


head differentials. Flow can be graphically portrayed by hydrodynamic flow nets,
which are drawn in vertical section parallel to the general direction of flow. A flow
net consists of two sets of lines, flowlines and equipotential lines. Flowlines or
streamlines are the loci of the paths of flow of individual water particles.
Equipotential lines pass through points of equal pressure. All intersections
between the streamlines and equipotential lines are at right angles.

Symmetrical hydrodynamic flow net beneath a dam with its base at ground level
When the base of the dam figure 2, is set below ground elevation and a cut-off is
constructed there is a change in flow net compared to figure 1, that results in the
following advantages:

1. The uplift pressure at the heel of the dam is reduced and the total uplift
pressure downstream from the cut-off has been diminished. Accordingly,
the moment of uplift forces tending to lift the dam has been reduced.
2. The danger of piping and erosion at the toe of the dam has been reduced
or eliminated.
3. The longer flow paths along the streamlines below the cut-off causes a
notable decrease in the exit velocities downstream in the proximity of the
dam and reduces total seepage under the dam.

Hydrodynamic flow net beneath a dam with its base below ground level and with
an impermeable cut-off near the heel of the dam

Hydrology of Anisotropic Bedrocks

Almost an infinite number of possibilities exists with respect to the magnitude and
space distribution of zones of potential seepage in bedrock in the vicinities of
dams and in the reservoirs behind the dams. A few of the many possible
configurations of zones of potential are shown below;
Idealised cross sections of dams showing various kinds of zones of
potential seepage in bedrock.

Brittle, fractured sandstones in


horizontal sedimentary
sequence beneath dam present
a potential seepage.

Dam is situated on basltic lava


flows and interlayered
pyroclastic deposits. Lava flows
are fractured, brecciated at
their tops, and contain lava
caves.

A brittle layer of quartzite in


tightly folded metamorphic
rocks is likely to contain
numerous intersecting
fractures.
Sandstone layers alternating
with shale layers in a syncline
contain fractures associated
with development of a syncline.

A fault provides access of water


to brittle sandstone layers
which dip upstream.

A fault provides egress for


water moving through inclined,
brittle sandstone layers.
Brittle sandstone layers have
been extensively fractured
during development of an
anticline.

Fractured sandstones in folded


rocks are intersected by a fault
zone which expedites
groundwater movement to the
surface beneath the dam.

Faults in brittle crystalline rock


provide channelways for
groundwater circulation.
Fractured sandstones, a
weathered zone on granite
beneath the sediments, and a
fault zone create channelways
for subsurface circulation of
water.

Extensively jointed crystalline


rocks are permeable to
groundwater flow.

A closely jointed igneous dike


intersects a sedimentary
sequence and provides a
channel for groundwater
movement.
Idealised cross section of valleys at dam and/or reservoir sites.

Jointed sandstones present


potential for seepage
around dam abutments
when reservoir is full.

Basaltic lava flows and


layers of pyroclastic rocks
create potential for
seepage. Lava flows are
jointed, have breccia tops,
and contain lava caves.

Fractured sandstones in a
strike valley are prone to
seepage.
A subsided block (arrow)
has created an open
channelway in a massive
horizontal sandstone layer.

Gravity-slip faults and


fractures formed by elastic
rebound produce potential
zones for groundwater
movement in a glaciated
valley.

A strong fault system


renders crystalline rocks
permeable on one side of a
valley.
A wide fault zone promotes
deep circulation of water
beneath dam.

Fractured sandstones and a


weathered zone beneath an
angular unconformity enable
easy circulation of
groundwater.

Fractured sandstones in an
anticline create a permeable
zone parallel to the valley.
Folded, jointed rocks and a
strong fault create a
potential for groundwater
flow.

A sheeted, jointed zone in


crystalline rocks create a
permeable zone.

Joints in a brittle quartzite


layer and a fault produce
channelways for
underground water
circulation.
Hydrology of Filled Reservoirs
Failure of slopes on sides of reservoirs frequently during drawndown when the
reservoir is nearly empty doesn't produce unmanageable problems. However, of
more concern is when rock and earth slides into a full reservoir causing sudden
destructive overflow of the dam.

Filling of a reservoir causes adjustments in the groundwater table in adjacent


materials. Over a period of time when the reservoir is full a new groundwater
table is established with coincides with the elevation of the water surface. The
groundwater surface is a free surface in contact through unfilled pore spaces with
the atmosphere, changes in atmospheric pressure are accompanied by changes
in pore pressure in the saturated zone. Wave action also undercuts the slopes
and oversteepens them.

Figure 1 - Glacial till deposits in a glaciated canyon in crystalline rocks


A reservoir is located in an extensively glaciated valley in crystalline rocks.
Lateral morraines, consisting of a jumbled mixture of large and small boulders,
gravel, and rock flour have been deposited by the glacier that occupied the valley
high on its sides. Filling of the reservoir causes an elevation of the water table in
the rill in the moraines, and because of the cross-sectional configuration of the
valley, considerably increases the possibility for sudden downslope movement of
the moraine material. Failure of the slopes might occur at any time.

The bedrock profile of a canyon eroded by a stream in a tilted succession of


sandstones and clay-rich shales. Unconsolidated materials in rock slides and
stream deposits are not shown. Water from the reservoir, by seepage through
the sandstones, comes into contact with the shale layers for a considerable
distance into the canyon walls, and by slow penetration of the shales, greatly
reduces their strength. Under these circumstances, a highly unstable condition is
created, especially where the sedimentary layers dip into the reservoir.
LOADING AND FACTOR OF SAFETY

1. INTRODUCTION
2. STATIC LOADING
3. DYNAMIC LOADING
4. FACTOR OF SAFETY - Gravity Dams
5. FACTOR OF SAFETY - Concrete Arch Dams
6. FACTOR OF SAFETY - Embankment Dams
7. FACTOR OF SAFETY - Abutments and Foundations

Introduction

A dam is a three dimensional structure and despite assumptions, it is not


homogeneous and its integrity is in the hands of the constructors.

The foundations are neither isotropic or truly elastic.


Concrete and rock are brittle, although elastic theories are applied in
stress calculations.
The dam and foundation will become saturated with varying effects on the
materials.
The dam will be subjected to water load, daily and seasonal temperature
cycles.
It will be subjected to random events such as : Floods, Waves, Seiche
Effects, Earthquakes, Ice Formation and other natural phenomena.

The factor of safety must relate to the strength, stability and durability with
consideration to magnitude of economic and personal loss that would result from
its failure.

The aim of the Engineer must be to reduce the number of uncertainties, both as
regards loading on the dam and in the means by which the dam and the
foundations withstand such loads. The Engineer must also be satisfied that there
is no feasible mechanism that could result in failure.

Static Loading

Horizontal Loads

Headwater (H1) - For the basic calculation of stability the level in the reservoir will
be assumed at or above the level required for the passage of the design flood. In
many instances the dam is designed for the highest level of watertightness, e.g.
a concrete parapet.
Silt (H2) - A changed
land usage as a
result of a dam may
well result in
increased erosion,
causing a deposition
of silt. Unless very
deep deposits of silt
are likely it is
adequate to assume
a triangular load
allotting an
appropiate relative
density to the fluid. This would have a maximum value of 1.4

Reservoir Behaviour (H3) - Wind and other natural causes will induce movement
in the reservoir as waves, reservoir set-up or seiche effect.

Ice Loading (H4) - It is assumed that ice will not form and exert pressure on the
dam at times of maximum flood. The slope of the upstream face of the dam as
well as the slope and roughness of the valley walls will influence the magnitude
of ice loading. Even wind blowing down the reservoir at 50km/hr may increase
the ice loading by 4-5 t/m of exposed face.

Tailwater (H5) - In some cases water is ponded downstream from the dam.
Assistance from this may be assumed but it must not be overlooked that, in the
case of an overflow dam, flood waters passing over the dam might well evacuate
such water from the face of the dam.

Seismic Force (H6) - Force acting on dam in horizontal plane.

Seiche effect (H7) - Is an undulation in the reservoir water due to natural causes,
intermittent wind, variation in atmospheric pressure, earthquake and motion of
the Earth. Usually less than 0.5m, though levels of 2m have been reported in
Lake Geneva

Vertical Loads

Weight of Dam (V1)- The unit weight of material


in the dam should be determined as accurately
as possible. An underestimation by 1% will
represented a considerable additional cost on
the dam.

Vertical Water Loading (V2) - Imposed on any


sloping surface of the dam, usually the upstream
face, but also on the downstream for overflow dams.

Uplift (V3)- Hydrostatic forces acting within a dam and its foundations including
interstitial or pore pressures. Some Engineers rely on drainage to prevent
occurence of uplift, assuming the drainage will be effective for the entire life on
the dam, therefore some inclusion for uplift must be included in the design. See
diagram for distribution of pressure. [k values vary between 0.25 to 0.50
depending on conditions.]

Seismic Force (V4) - Force acting on dam in vertical plane.

Other loads on the dam

Water Density - Some rivers carry very heavy silt load in seasons which changes
the density of the reservoir.

Reservoir set-up - The result of continuing wind causing one end of the reservoir
to be at a higher level. Calculations for a large reservoir in which the fetch is
38km would indicate the following values:

Return Period Wind Speed Set-up


(years) (km/h) (m)
1000 160 0.75
100 125 0.45
10 95 0.26
5 88 0.22
2 77 0.17

Thermal Effects - Concrete dams will be subject to loading from temperature


variation within the dam caused by hydration of the cement and due to seasonal
variations. Water as depth doesn't vary, but towards the surface it varies with
season. A skew loading is used to describe solar and air temperature effects.

Construction Loads - Concrete dams of cupola and buttress shape offer good
resistance to water loading when complete but during construction it is necessary
to control the rate of construction and to include reinforcement in overhanging
sections.

Direction of Forces - At certain locations it may be appropiate to increase the


radius of an arch dam and accept higher stresses within the dam in order to
ensure better angle of incidence of the resultant thrust with the abutment. The
direction of resultant forces is important for gravity and buttress dams - especially
on stratified rock.
Hydrostatic Loading within the Foundation or Abutment - Faults, cracks and joints
are present in most damsites. Forces due to a large dam may cause cracks to
appear in the rock upstream from the dam, this may cause jacking loads that
could cause failure. To avoid this, careful surveys should be made of the
orientation and inclination of faults, joints and cracks.

Tectonic Forces - Besides seismic effects, there may be significant tectonic


forces on the Earth's crust at the site and these may be upset by deep
excavation or saturation due to the filling of the reservoir.

Dynamic Loading

The Earth's crust is in a state of stress. When the stress is great enough, and the
crust is weak enough, adjustments may occur. These adjustments will release
energy in the form of shock waves, propagated from an epicentre. These waves
will vary in wavelength and frequency. Short-period waves have predominant
frequencies within the range of natural frequencies for dams, they are apt to
produce conditions of resonance in the dam. Engineers are therefore more
concerned with the possibility of moderate earthquakes occurring within 80 to
120 km of the dam than larger earthquakes occurring outside this limit.

For gravity dams a horizontal coefficient is adopted and applied as an additional


static load. For arch dams the dynamic effects receive greater attention with both
model tests and in situ testing by vibrating the dam. For embankment dams
additional horizontal static loads are considered and a dynamic analysis has
been developed with close attention being paid to the characteristics of fill
material.

In October 1969 the Committee on Earthquakes of the International Commission


on Large Dams (ICOLD) summarized 1969 practice :

Design
For gravity dams a horizontal coefficient was generally adopted and
applied as an additional static load. Vertical effects were taken into
account in very few circumstances and dynamic analysis was used by
very few.
For arch dams the dynamic effects received greater attention in model
tests and in situ testing by vibration of the dam.
For embankment dams additional horizontal static loads were
considered; dynamic analysis was being developed and closer
attention was being given to the characteristics of fill material.
Zoning - Many countries were adopting the principle of seismic zoning.
Seismic Coefficients - A coefficient of from 0.1 to 0.2 was commonly used.
Seismic Waves - Analyses had been made by applying sinusoidal or
modified earthquake records - but actual earthquake records had only
been applied in rare cases for dynamic analyses.
Properties of Materials - Different mechanical properties of various
materials when subjected to static and dynamic loading.
Loads Considered - For dynamic water pressure the formulae of
Westergaard, Zanger and the USBoR were in use.
Allowable Stresses - In many cases the permissible compressive stress
under dynamic loading was increased by up to 30% above the permissible
static stress. Factors of Safety for arch dams were usually 4, based on
compressive stress and 1.2 minimum for fill dams.
Deformations - An embankment dam which employed dynamic analysis
was assumed to suffer 5% axial strain.
Models - These were popular for arch dams and were used for some
gravity dams. There was a tendency to employ model tests for fill dams.
In Situ Tests - Some arch dams were shaken by vibrating machines to
study natural frequeny and modes of vibration.
Seismographs - In a majority of large dams seismographs were used.

Factor of Safety
- Gravity Dams

A gravity dam must


be designed to
safeguard against
overturning and
sliding. For the
former it is usual to
design the dam so
that the resultant of
all forces intersects
the base within its
middle third. This will
provide a factor of
safety in excess of 2.

The ratio of the sum of the horizontal forces to the sum of the vertical forces is
referred to as the sliding factor (Fss). This is usually about 0.75 but must not
exceed 0.90 under extreme loading. These figures represent the range of the
coefficient of static friction normally encountered at the site of a gravity dam.

At or in the foundations, the horizontal loading will be resisted by cohesion and


friction. The ratio of the total resistance by cohesion and friction to the horizontal
load is termed the shear friction factor (Fsf). Most countries accept 4 as a
minimum value. In practice the foundation is usually prepared in steps or is
sloped upward in a downstream direction to provide resistance to failure far in
excess of the above figure.

Range of shearing resistance parameters.


Location of plane of shearing/sliding Cohesion (c) Friction tan ø
mass concrete intact 1.5-3.5 1.0-1.5
mass concrete horizontal construction joint 0.8-2.5 1.0-1.5
conrete/rock interface 1.0-3.0 0.8-1.8
rock mass sound 1.0-3.0 1.0-1.8
rock mass inferior <1.0 <1.0

Recommended shear friction factors, Fsf (USBR 1987)

Load Combination
Location of sliding plane Normal Unusual Extreme
dam concrete, base interface 3.0 2.0 <1.0
foundation rock 4.0 2.7 1.3

Factor of Safety - Concrete Arch Dams


The factor of safety for an arch dam is the ratio of the compressive strength of
concrete to the maximum calculated compressive stress in the dam. The
compressive strength is usually referred to as the strength of concrete at the age
of 91 days when tested in 150 mm x 300 mm cylinders.

The design criterion adopted by the U.S. Bureau of Reclamation is for a factor of
safety of 4 based on the strength of concrete at 1 year. Except for extreme
loading combinations the maximum compressive stress is usually limited to 6.9
MPa.

Factor of Safety - Embankment Dams

The minimum factors of safety for embankment dams would be:

Upstream Slope

1.3-
Immediately after completion with full construction pore pressure
1.5
Following rapid drawndown (slip circles between high and low water 1.2-
levels) 1.3

Downstream Slope

Earthquake and Reservoir Full 1.2


Reservoir full - steady seepage 1.5

In an area subject to earthquakes the following factors are indicative of


acceptable values:

Seismic coefficient 0.1 FoS 1.8


Seismic coefficient 0.3 FoS 1.15

Factor of Safety - Abutments and Foundations

The dam foundations and abutments should be thoroughly investigated for any
possible mechanism of failure. This would involve identification of joints, faults
and any other forms of weakness.

A reasonable factor of safety is

- the ratio of shearing resistance to the maximum shearing stress predicted; the
lowest value of the ratio in the foundation being the factor of safety of the
foundation

SITE INVESTIGATION
1. INTRODUCTION
2. TIME AND MONEY FOR INVESTIGATIONS
3. DESK STUDY
4. PRELIMINARY INVESTIGATION
5. GEOPHYSICAL INVESTIGATION
6. EXPLORATORY INVESTIGATION METHODS
7. EVALUATION OF SELECTED SITES
8. DETAILED INVESTIGATION
9. MONITORING

Introduction

Most failures are due to lack of appreciation of how the particular damsite would
react to the superposition of the dam and reservoir. It is therefore essential that a
detailed site investigation takes place and the results are appropriately used by
Engineers.

In the planning stage possible damsites will have been chosen from contour
maps and aerial photography, selected primarily on topography. A narrow gorge
is best, hoping for minimum quantities in the dam and a valley opening upstream
to provide the required storage. There maybe alternative sites along the length of
a river and hence further investigation has to be done to assertain the best
possible position.

Time and Money for Investigation

The amount of money required to investigate a damsite will depend upon the site
and the type of dam. An experienced department of engineers, hydrologists,
geologists and surveyors may produce sufficient information for an outlay of 2-
3% of the dam cost. This figure could reach 6% in remote locations where basic
information is not available.

It is not unusual to spend 3 years on site investigations, this will depend on the
location and size of the dam, but time must not be underestimated. To meet
stringent requirements for environmental studies and public opinion polls could
add 2 years to the time and several percent to the cost.

If, as a result of the site investigation another site is to be chosen, the same time
and money must be spent investigating the new site. Adequate time and money
must always be available to all disciplines to give them the opportunity to
investigate and report.

Desk Study

Initial desk study can be done by researching from these sources of information -

1. Ordnance Survey Maps or equivalent


2. Admiralty Charts
3. Geological Maps and Memoirs
4. Old OS Maps or equivalent

Past users of site


Concealed mines and adits
Infilled pits
Original topography and drainage conditions
Changes in stream and river courses
Changes in landslide areas, fence lines, path lines

5. Aerial Photography

Landsat Images
Colour and infra red photography

6. Previous Site Investigation Reports


7. Local people and authorities
Preliminary Investigation

Aerial Reconnaissance - An initial comissioned flyover is essential, providing


the Engineer with an idea of the topography and enabling him to form an opinion
of the probable hydrological characteristics of catchment.

A Geologist will assist the Engineer in the selection of the damsite, and a
construction Engineer will study the access and possible sources of materials.

Ground Reconnaissance - Features that should be sought during early


reconnaissance include old and potential land slides, geological faults and major
joints parallel with the valley.

The joints may be open or infilled with products of decomposition, they


present construction hazards and possible leakage paths around the dam.
Examination along the beds of the river and tributary streams will indicate
the strike and dip of rock formations.
Any springs or underground water should be identified since they provide
leakage paths from the reservoir.
The depth of alluvium or soil should be determined to indicate the
excavation required and the probable quantity of material required for the
dam.

At this stage, the preliminary geological data should be assessed and enhanced
by mapping and modelling. This can help to highlight important considerations
about which type of dam may be most appropriate, and any problems which may
be encountered, before extensive drilling or exploratory works are performed.
Assessment of preliminary data will assist in the choice of exploratory methods
and in the design of the exploratory programme as a whole.

Geophysical Investigation

Geophysical methods provide an indirect evaluation of certain underground


conditions. Several procedures have been developed, all of which measure some
force pattern in the earth.

Advantages of Geophysical Methods - They permit a rapid coverage of large


areas at a relatively low cost which is useful in selecting possible dam sites
during reconnaissance phases. They are also not hampered by boulders or
coarse gravel which interfere greatly with the direct methods such as boring and
sampling.

Limitations of Geophysical Methods - There is difficulty in correct


interpretation when the strata are not well defined and horizontal. For this reason
it is imperative that all geophysical work is confirmed by borings and other direct
observations.
Exploratory Investigation

Purpose - to secure accurate information about the soil and rock stratification,
the composition of the materials and the location of ground water.

Boring and Sampling

Auger Boring - Generally limited to firm soils, above the watertable. Gravel
larger than about a third of the diameter of the hole cannot be drilled but
very hard soil and soft rock can often be penetrated if sufficient power is
available.
Test Boring -
Core Drilling -
Diamond Drilling -
Short Drilling or Calyx Drilling -

Programme of Exploration Work for Foundations

Boring layout
Procedure
Laboratory testing
Correlation of results

Planning and Conducting Borrow Pit Explorations

Field Work
Testing and Correlation

Evaluation of Selected Site

At this stage, potential hazards and problems should have been identified.
However, it is still necessary to remain alert for indications of hazardous or
problematic features which were not identified during the earlier stages of the
investigation. The main effort is directed in producing parameters for the final
design. This would involve high quality boring and drilling, with particular
attention being paid to sample quality and high core recovery, careful logging of
trenches, shafts and adits, in situ testing such as plate loading tests and in situ
shear tests in adits, trial embankments, grouting trials and so on.

Foundation testing

Undisturbed Sampling
Pit Sampling
Thin-walled Samplers
Foil Samplers
Rotary Samplers
Laboratory Testing
Correlation of Test Results

Field testing

Test Pit
Plate Load Test
Seepage Test

Borrow pit investigations

Sampling
Laboratory Testing
Test Strip

Detailed Investigation

The evaluation of preliminary desk and field work should assess the potential for
major hazards and qualitatively assess the likelihood of encountering any more
hazards. This should allow a ranking of the potential sites in order of their
probable suitability.

Following the desk study and preliminary field work, it may be necessary to
establish a pattern and base level of seismicity for later evaluation of induced
seismicity. If potential active faults are identified, seismic arrays should be
installed to monitor these. This will help assess the need for criteria changes
should seismic activity occur after the feasibility stage has been completed and
the design is well advanced.

The next stage is to produce a detailed investigation of the chosen site.

Monitoring

Monitoring during construction will include the work of an engineering geologist


on site, who will examine all excavations to see whether the expectations of the
preceeding investigations have been realised. The identification of exceptions
may then lead to an early diagnosis and redemption of any problems.

For the post-commissioning stage, monitoring will involve regular reading of


installed instrumentation to check performance against design criteria. This
should serve as an 'early warning' system which will initiate a contingency
programme, thus minimising the delays which would result from the development
of an adverse situation.

CONSTRUCTION
1. GENERAL
2. RIVER DIVERSION
3. CONCRETE DAMS
4. EMBANKMENT DAMS

General

1. Safety
2. Specifications
3. Plant
4. Cost and its control

Safety - with the ever increasing height of dams there is greater need for
precautions, especially against falling objects or persons. Double curvature
structures have made access and movement of personnel difficult. All site
personnel must be alert at all time for the accidents that might happen. The
insurance is regular meetings of staff and representatives of the work force,
where knowledge and experience can be pooled - especially in the planning
stage of an unusual operation.

Specifications
For all types of dam, the specification should cover the following:

The required date for completion, with a schedule to indicate dates for
completion of stages of the work;
The degree of responsibility to be accepted by the Contractor in the
dimensioning of diversion works, for losses due to floods, for river pollution
and general care of the river;
Clearing of the site and works areas;
The extent of foundation preparation required and the sharing of
responsibility for unforeseen conditions;
Protection of the environment, disposal of soil, rehabilitation of borrow
areas, beautification, etc.;
Premliminary work that will be done by the Owner and the degree of
responsibility accepted by the Owner for consequences of such work.

Plant - The cost of purchasing plant and its operation are major items. On a dam
involving 2 million cum of concrete, the purchase and operation might each
represent 18-20% of the direct cost of the dam. For an embankment dam this
may be of the order of 25-35%. It is therefore important to select the correct plant
to achieve optimum cost.

The specification for some major contracts calls for the use of only new plant and
the main advantage is that suitable plant can be matched to the particular job.
Material transporters can be matched to quarry equipment for example. For
compaction of embankments - soil or rock, it is important to select the most
appropiate equipment and this can be best determined by means of a trial
embankment. It is also necessary to have a supply of spare parts since many
sites are remote. Plant should be simple and rugged, and preferably modular to
simplify the replacement of parts.

Consistently high quality of materials is the objective of all dam builders and to
sacrifice quality for a doubtful saving in cost is poor engineering.

Cost and its Control - Safety, Time and Cost are interrelated and usually
conflicting. Safety is always paramount, and hence time and cost directly relate
to quality and degree of perfection required. There is an optimum time for any
operation and beyond this time will incur extra costs. Cost is made up of direct
charges for manpower and materials, plus overheads and interest. Interest is out
of the control of the Engineer.

With regard to the direct charges, the selection of the type of dam will be the
major decision and this might well be influenced by local conditions rather than
mathematical economies.

Is a labour-intensive job required in the interests of the local community?


Is skilled labour available?
What degree of mechanisation is desirable or possible at the particular
site?
For a concrete dam, for example, the dissection of costs may be;
Materials 25%
Formwork 20%
Plant Purchase 19%
Plant Operation 19%
Placing and consolidation of concrete 4%
Precooling concrete 3%
Concrete Treatment 3%

For an embankment dam, for example. the dissection of costs may be;

Quarry Operation 30-40%


Haulage 20-30%
Spreading and Compaction 25-30%
Face rolling, mesh, etc. 15-20%

River Diversion
Regardless of the type of dam, it is necessary to de-water the site for final
geological inspection, for foundation improvement and prepartation, and for the
first stage of dam construction. The magnitude, method and cost of river
diversion works will depend upon the cross-section of the valley, the bed material
in the river, the type of dam, the expected hydrological conditions during the time
required for this phase of the work, and finally upon the consequences of failure
of any part of the temporary works.

At most sites it will be necessary to move the river whilst part of the dam is
constructed; this part will incorporate either permanent or temporary openings
through which the river will be diverted in the second stage. If the first diversion is
not large enough the initial stages of construction will be inundated, if the second
stage outlets are too small, the whole works will be flooded.

At some sites there is a distinct seasonal pattern of river flows and advantage
can be taken of such conditions but noting that Nature is random.

Construction of the Hendrik Verwoerd Dam, South Africa required a sophisticated


arrangement of cofferdams. An approach was developed based on the frequency
and distribution of floods that could occur over a five year period of construction.
The following is an extract of the original detailed specification:

First Stage (A) -


Construction from each bank of the river of groynes a short distance
upstream of the dam, to alter the direction of flow and thus to move the
low water channel towards the left bank of the river at the dam site.
Construction of a semi circular concrete arch cofferdam on the right bank
of the river.
De-watering of this cofferdam and excavation within it for the main dam
blocks, the proportion of the overspill apron and the sections of the mid
channel cofferdams.
Concreting of the dam blocks, numbers 14 to 28 up to a minimum level of
1200 meters, the portions of the overspill apron and of the mid channel
cofferdams within this cofferdam. In blocks of the dam constructed on this
stage, temporary openings were formed through which the river was later
diverted.

Second stage (B) & (C) -

Construction of a semi circular arch cofferdam on the left bank of the river.
Construction of the flanking portions of each of the upstream and
downstream mid channel concrete arch cofferdams which cross the river
upstream and downstream of the central section of the dam.
Excavation of a channel along the right bank, leading to the temporary
openings through the dam, demolition of portions of the right bank
cofferdam to permit the diversion of the river through the temporary
openings and such clearing out of the right bank diversion channel as may
be necessary.
The cutting of a channel through the portion of the right bank groyne
adjacent to the bank to form an entrance to the diversion channel
described above.
The placing of rockfill to connect together the right and left bank groynes
so as to divert the river flow into the right bank diversion channel, thereby
cutting down the velocity of the water in the vicinity of the mid river
cofferdams.
Completion of the upstream mid river cofferdam completion of the
downstream mid river cofferdam.
Placing of spoil, excavated from the works, in the flood channel on the left
bank upstream of the dam to prevent the river flooding into the area to the
protected by the mid river cofferdams.
Third stage (C) & (D) & (E) -

De-watering of the left bank cofferdam and excavation for the dam blocks
and the portion of the overspill apron within this cofferdam.
Concreting of the dam blocks numbers 9 to 27 to a minimum level of 1206
meters.
Demolition of the left bank cofferdam.
Demolition of the remaining portion of the right bank cofferdam within the
areas protected by the mid channel cofferdams.
The de-watering of the mid channel cofferdam and excavation within it for
dam block numbers 1 to 7 and 2 to 12 and portion of the overspill apron.
Concreting of dam blocks 1 to 7 and 2 to 12 to such levels that the
contraction joints in the lower part of the dam up to gallery can be grouted.
Concreting within the mid channel cofferdams of the portion of the
overspill apron downstream of blocks 1 to 7 and 2 to 12.
Cooling of the concrete and grouting of the dam construction joints.
Diversion can also be achieved by means of a tunnel, which depends on the
nature of the rock and depth of weathering and should be far away from the dam
itself to not interferre with the foundations. The tunnel also should be large
enough to avoid the possibility of job jams.

Concrete Dam Construction

1. Aggregate Production
2. Concrete Handling, Placing and Consolidation
3. Formwork
4. Built in items
5. Cooling of Concrete
6. Economical Construction

Aggregate Production - The acceptability of natural aggregates is judged upon


the physical and chemical properties of the material and the accessibility,
proximity to the site and economic workability of the deposit.

Concrete Handling, Placing and Consolidation - The procedure to be adopted


for moving concrete from the mixers on to the dam will be governed by site
conditions. The problem is to transport it to the dam with the least possible
segregation or change in its consistency so it may be compacted uniformly into
the dam without unreasonable effort. The cableway is probably the simplest
arrangement. The tilting mixers will feed the buckets; these are then moved to a
pick up point under the cableway, transported smoothly to the block and emptied
quickly through an air operated gate.

Three Tower Cableway

The use of a belt conveyor has also been considered, but problems occur in
keeping the belt temperature stable in warm weather and also in windy
conditions. The conveyors are usually covered and cold air is blown over the
concrete to lower its placing temperature.
The placing of a low-slump concrete, four layers in 2.3m lift

Tractor mounted vibrators at Emosson Dam, Switzerland

Proper consolidation of low-slump concrete is laborious and requires continuous


supervision. The most efficient compactor is usually the two man hand-held high-
speed vibrator.

Formwork - Probably the most widely used lift is 1.5m, however, on large dams
a height of 2.3-3.0m is frequently used. With the larger lifts there are fewer
movements of forms and fewer horizontal lift surfaces to be cleaned. The high-lift
formwork is unique and expensive with less prospect for re-use, heavier
equipment is required for lifting the forms and the heat problems and risks of
cracking in the concrete are accentuated. Modern steel formwork is of cantilever
design, see figure. Where possible the use of slip forms will expedite the work
and lower the costs. At some locations it may be expedient to use precast
concrete slabs for formwork with set-retarding agent on the inner surface.

Built in items - The installation of built in items is always a major source of delay
on construction. Advance planning is required with close attention to detail. The
complication of installation of reinforcement, prestressing, gate hinges, drainage
wells and gate wells are common on spillways. There has been a tendency to
use precast concrete units for galleries to save time, however this prevents the
inspection of the concrete in the interior of the dam. The simplest method of
forming galleries is vertical formwork extending the full height of a lift. When this
is removed, precast concrete beams or slabs can be laid over the opening and
concreted into the next lift. Reinforcement is usually required above and below
rectangular galleries and this is best installed as prefabricated units.

Cooling of Concrete - The method of cooling concrete during the first few days
after placing can be of the utmost importance if cracking is to avoided. It is
essential to give attention to both internal and external factors that may induce
cracking;

Temperature rise, which will depend upon the heat of hydration of the
cement, the quantity of cement per cubic metre, the concrete placing
temperature and the rate of construction;
Heat dissipation, which will depend upon the conditions of exposure -
including the temperature of the underlying concrete and the thermal
diffusivity of the concrete. If it is considered necessary to heat the
underlying concrete the rate of rise of its temperature should not exceed
2° Celsius per day;
The effects of restraint from a cold surface, i.e. rock or concrete say 14
days old, it will depend upon the temperature gradient which can be
reduced by placing concrete in half lifts for a predetermined height, say
3m above the cold surface;
The arrangement of cooling pipes - at 0.25 and 0.75 of the height of the lift
may be more efficient than on the top of the old lift and at mid-height of the
new lift. The horizontal spacing will depend upon the rate of heat removal
required and the temperature of the cooling water (i.e. river water of
varying temperature or refrigerated water);
The local weather conditions - humidity, temperature and wind.

Economical Construction - Concrete dams are expensive, however


mechanisation over the last 40 years has reduced by a factor of four the number
of man hours required to place a cubic metre of concrete in a mass concrete
dam. Although every Engineer strives for perfection, consideration must be given
to the degree of perfection that is really necessary. Close co-operation between
the Owner and Contractor will save time and money. Questions have to be asked
at all stages such as;

Is it permissible to design for tensile stress in the concrete?


Will arching of the dam result in overall economy?
Are longitudinal contraction joints necessary in large gravity dams?
Can the transverse contraction joints be omiited, located at wider spacing
etc?
What clean up is necessary on horizontal construction joints?
Should the height of lift be specified by the designer?
Should the cement content of the concrete be specified or only the
properties required in the concrete?
Can the dams of intricate shape be justified?
Should ancillary works be separated from the dam to minimise
interference with a continuous or cyclic process of dam building?
What is the optimum layout and design for galleries?

Looking at the 'Construction - General Section' to see the proportion of costs in a


concrete dam, assumuing that the materials have been predetermined, the
Contractor should concentrate on formwork, the purchase of plant and its
operation.
Embankment Dam Construction

1. General
2. Phases of Construction
3. Quarry development and Haul Roads
4. Material Compaction
5. Earth Dams
6. Hydraulic Fill Dams
7. Rockfill Dams

General - Considerable economy can often accrue if there is 'Progressive


Design' - the aim is to provide design flexibility to cover the probability that
materials will not be in true accord with samples tested nor will foundations
conform to assumptions.

Phases of Construction -

1. Evaluation of plans, specifications, basic requirement, and features of the


site.
2. Planning and scheduling of the job
3. Making the site ready
4. Building up the structure
5. Clean Up

Quarry development and Haul Roads - The quarry site should be determined
primarily on the basis of rock quality, i.e. the fragmented rock must be sound,
hard and clean. If the location is not dictated by rock quality, then it is desirable to
separate the quarry and the haul roads from other works such as the intake,
spillway or power station construction. Attention should be given to
environmental factors such as noise, vibration from explosives and dust. In
designing the explosive charge, the form of muck pile must be considered, i.e. for
rubber-tyred loaders a wide low pile thrown well out from the face is desirable for
minimum loading costs.

Haul roads must be built to suit the required speed of construction, and this
involves the size of the haulage units. The roads should be at least 13m wide for
two way traffic, for preference, on way traffic should be organised on a large job.
The gradients must be such as to give minimum cost for the vehicles involved.
The general layout of haul roads and ramps can be greatly facilitated with scale
models.

Material Compaction -

Fine - Trial embankments should be constructed to determine


relationships between moisture content, layer thickness, type of roller,
number of passes of the roller and the resulting density and permeability
of the fill. Additional water during compaction usually improves the
impermeability of residual soils by a factor of at least ten compared with
compaction on the dry side of optimum moisture content.
Plastic clays - a little wetter than optimum moisture content, can be
compacted by rubber-tyred rollers, which are water ballasted. A
disadvantage of the rubber-tyred roller is that layer and shear planes tend
to form in some materials. Since the fine materials are usually sensitive to
moisture the field Engineer must be extremely weather conscious. If heavy
rain is expected the surface of the fine material should be rolled smooth
with sufficient gradient to shed water from the working area.
Filter or Transition Material - The thickness of the filter and transition
zones will depend upon the water pressure to be sustained and the
materials economically available. For a large dam the fine filter is often of
crushed rock which is expensive. Its width would normally be the
narrowest than can be placed and compacted. Setting out of the zone
boundaries is important, especially for curved dams with a thin fine filter.
The number of passes should be determined such that future settlement
of the core and the filter zone will correspond as closely as possible.
Rock Compaction - The steel-faced vibratory roller is normally used for the
compaction of rock. On the sloping faces a roller of 1.5t is most useful.
The thickness of the layer of rockfill and the maximum acceptable size for
rocks should be regarded as factors pertinent to the design of the dam.
Water to aid compaction of rockfill - Wet rock will compact better under
rolling than dry rock. Firstly, the friction is less between the rocks and
secondly many rocks lose strength when wetted so that crushing occurs at
points of contact during the third or fourth pass of the rollers.
Provision for Instrumentation - This will inconvenience construction and
failure of the equipment to work will represent a financial loss for the cost
of its purchase and installation, and little can be done about it after the
dam is built. Vital information about the behaviour of the dam will be lost if
care is not taken in its installation.

Earth Dams -

The most important variables affecting construction of earthfill embankments are


the distribution of soils, method of placement, water content, and compaction.

Soils may be classified by engineering properties into various groups. These


groups fall into two main divisions, the course grains and the fine grains. Course
grains are those larger than a number 200 sieve size and include gravels and
sands. Fine grains are smaller than a number 200 sieve size and include silts
and clays. Course grain material is used for the outer zones of an earthfill
embankment, and fine grain material is used for the impervious core or central
portion of the dam. A sieve analysis test will determine the percent of material
passing a given sieve size.
The soil material must be placed in horizontal layers not more than 15 cm. thick
after being compacted. The soil should be homogeneous and free from lenses,
pockets, organic material, or other imperfections. Prior to placement, the material
should have the optimum moisture content required for the purpose of
compaction. The optimum moisture content, or the water content that produces
the maximum density, may be obtained by a laboratory Proctor test.

Good compaction of a cohesive soil reduces permeability and increases shear


strength and the stability of the dam. Compaction equipment includes sheep-foot
rollers, pneumatic rollers, and hand tampers. The dry density of the soil should
not be less than 95 percent of standard Proctor test.

Hydraulic Fill Dams -

Excavation - dredging, with hydraulic giants or dry with the aid of a hog box. The
choice of the methods depends on the cohesion of the soil and on the
topography of the site.

Transport - The materials are transported in suspension in pipelines. Typical


mixes are from 10-20% solids by volume or 25-50% solids by weight.

Fill Construction - To start the fill two parallel dikes are constructed at or just
inside the embankment toes as shown in the figure. Often these are the
permanent rock toes themselves but they can also be made of rolled pervious
earth. The pipelines (called beach pipes) are laid on top of these dikes or are
carried on low trestles just above them. Outlets are provided to allow full
discharge of the pipe. In filling, several adjacent outlets are allowed to discharge
into the area between the dikes. The coarse materials settle close to the
discharge points while the finer ones are carried to the centre, still in suspension.
A pool is created between the 'beaches'. The core level is always below the
beach level because the rate of sedimentation there is much slower.

The width of the core is controlled by the percentage of fines in the borrow soil
and the level of water in the core pool. At the start of each 1-2m lift, the level in
the core pool is raised to provide a width somewhat greater than the maximum
limit of core in the shell. Filling commences when the coarse materials settling on
the beach above the pool and encroaching on the pool limits. As the beach rises
the core pool narrows and becomes deeper. Filling is stopped when the pool
width is close to the minimum permissible core width. A core zone with jagged
edges, as shown, is the result.

Re-working the Fill - It is seldom that the beach will conform exactly to the
desired dam shape since the deposition will vary with the distance from the
outlet. Draglines are placed on the outer edges of the shell to reshape the dam to
the proper dimensions. A new pair of dikes, if necessary, is built and the process
is repeated.

From time to time fingers of core develop into the shell beyond the established
limits. These are removed by digging them out, and replacing them with the shell
material. Zones of shell material in the core are likewise equally dangerous.
These develop from slides into an excessively deep core pool or as a result of
too small a proportion of fines available from the borrow pits. A small hydraulic
dredge is used to excavate the core material and discharge the mix back into the
core pool so that the coarse materials will be widely dispersed.

Reworking the shell also tends to reduce the loose structure which often
develops when fine sands are deposited out of water. Such loose cohesionless
soils are potential sources of failures and are real hazards in hydraulic dam
construction.

Rockfill Dams -

Pore Pressures - Excessive compactive effort relative to the particular material


may induce pore pressures in the earthfill greater than uplift pressures that will
result from filling of the reservoir. This would mean a lower factor of safety during
construction than when the dam is in operation. If this is not acceptable then
extra money must be spent to ensure slope stability during construction. On the
other hand, a slope slide during construction would not compare in importance to
a slide in a completed dam. It may therefore be a justifiable risk for the short
term. If this were to be done then it would be mandatory to monitor pore
pressures so that it would be known definitely when the design factor of safety
was established. There is justifaction for reduction of construction pore pressures
especially when the height reaches 150m for example.

An advantage of the thin core is that construction pore pressures should normally
drop by 50% by the end of the construction period. In thick cores, the pressures
may remain for years.

Dumped Rockfill - the main body of fill is placed by dumping. The initial part of
the fill is dumped from clamshell cranes, cableways, or from ramps on the
abutments to form a mound or bank. The remainder of the fill is dumped from the
top of this mound, allowing the rock to fall down the sloping surface. The
combined effect of sliding, tumbling and impact casue the pieces to become
tightly wedged together. Not more than 15% fines should be in the dumped
rockfill, since they prevent good compaction and make drainage of water difficult.

Rolled Rockfill - if the rock is soft and breaks readily into pieces less than a third
of a cubic metre, a rolled rockfill can be used. It is placed in layers and then
rolled by heavy rubber tyred rollers and heavy vibrating rollers. Four to eight
passes are required for compaction.

Reshaping the Fill - the dumped rockfill assumes side slopes of the angle of
repose. If a flatter slope is required it can be formed by introducing horizontal
berms as required.

GENERAL ABOUT DAMS


Engineering Responsibility

An Engineer's responsibility is to safety. They must act with integrity giving due
consideration to the purpose of the project and the ultimate effects of the project
on fellow human beings.

At the same time the Engineers are responsible to the community for the cost of
the structure. There is always a limit to the finance, so any cut in cost must not
sacrifice safety. The Engineers also carries a legal responsibility, and are
responsible at all times for both what they do and what they say.

Consequences of Failure

Failure happens with fearful rapidity and usually without little warning, with the
potential to cause a national catastrophe.

When the Oros Dam failed in Brazil in March 1960, between 30 and 50 people
were lost and 100 000 people were evacuated, some 730 million cubic metres of
water were released in 34 hours with a peak flow of 9600 cubic metres per
second.

Statistics - Classification of Risk according to Gruner

45% Hydraulic Conditions


30% Type of Structure amd Construction
7% Geology
6% Environment
6% Consequences
Table based on International Commission on Large Dams 1965 report.

Number of incidents

Arch Buttress Gravity Earthfill Rockfill Misc Total


Exploration 9 5 6 49 2 1 72
Material 1 - 2 8 - - 11
Layout - 1 4 17 3 - 25
Design 4 6 13 48 3 2 76
Construction 1 1 2 32 5 - 41
Operation - - - 5 1 - 6
Supervision 1 1 - 3 - - 5
Total 16 14 27 162 14 3 236

Appurtenant Features

Coffer Dams - Coffer dams usually are temporary structures built upstream from
a dam to prevent stream flow around the excavation for a dam. In valleys of
steep profile diversion commonly is accomplished by a tunnel or tunnels in the
walls of the valley. Commonly the diversion tunnels are put to further use to
control flow from the reservoir either for drainage of the reservoir or for flow
under pressure into a hydroelectric generating plant. In valleys of low profile
diversion is by tunnels, canals, or by conduits which subsequently are buried by
the dam. It is not unusual in embankment dams to incorporate the coffer dam into
the larger embankment structure comprising the designed dam.
Hydroelectric power plants - many dams are constructed to generate
hydroelectric power. The powerhouse is located at,or in the vicinity of, the toe of
a dam or at some distance downstream. Flow of water into the powerhouse is
controlled by valves upstream from the dam, within the dam downstream, or in
valve vaults excavated in rock outside of the dam.
Fish ladders - dams constructed on streams that are the migration paths for
spawning fish commonly make provisions for movement of the fish up or in the
vicinity of the downstream face of the dam. The facility that permits fish migration
is usually called a fish ladder. See figure.
Gates - gates are devices installed in the tops of spillways to control the flow of
water over the spillway.
Locks - locks are movable dams or portions of dams utilized in navigation along
rivers and canals.

Penstocks - a penstock is a sluice or conduit used for control of water flow,


especially into a hydroelectric power plant.

Spillways - a spillway is designed to contain and control overflow of reservoir


water when the reservoir is full. Spillways are, or should be, designed to
accommodate flows during maximum flood stage so as to prevent damage to the
dam and appurtenant features. Their size and location with respect to the dam is
determined by the size and kind of dam, local topography, geology, and a careful
review of the History of stream flow at the site of the dam.

Overflow of embankment dams outside of a spillway can have especially


disastrous consequences so that safety usually requires a spillway capable of
containing at least a hundred year flood.

Spillways are located within or on the downstream face of a dam, outside of the
dam on one side or the other, or within the reservoir, where water spills into a
glory hole and passes through a shaft and tunnel or tunnels in the abutment of
the dam.

Tunnels - tunnels in bedrock outside of dams serve a variety of purposes. Flow


through them is controlled by valves external to the dam or in valve chambers or
vaults within the dam or in bedrock outside of the dam. Tunnels for control of the
water level in the reservoir are commonly called gravity tunnels and serve a
principal function of diverting water to some point downstream from the dam.
Tunnels that transmit water under pressure to elevate the water to a higher level
than the intake of the tunnel or to generate hydroelectric power are called
pressure tunnels and usually require considerable competency in the rock
through which they are constructed.

Valves and valve vaults - Valves control the flow of water through tunnels and
penstocks. In many large dams the valve are installed in underground vaults or
chambers to which access is gained downstream from the dam.

Water Resources - National and International

Water is probably Man's most vital commodity; its optimum utilization will be of
prime importance in our expanding civilisation. Planning is therefore essential on
a geographically wide scale and over a long period of time. The greatest obstacle
is usually the unavailability of finance for comprehensive investigations.

It would be desirable from the engineering viewpoint to start development high up


in a river and then progress downstream. This would improve quality and
gradually increasing control of the river would facilitate and lower the cost of the
downstream stages. However there is usually less potential, difficult access and
hence construction costs are higher, and therefore the benefit to cost ratio is
generally lower.

For example the Hoover Dam, used to prevent floods, generate electricty and
provide irrigation has two mighty spillways, which due to subsequent
development upstream will probably never be used. Such occurences are
unavoidable when only part of a river system is developed, i.e. when the
economy requires the 'best' damsites be exploited first.

On a larger scale the major rivers of the world often form international boundaries
or they rise in one country and flow through several others. International
agreements may exist between countries with regards the usage of the river for
example. For the satisfactory allocation of costs a basic programme for the full
development of the river basin must be evolved and accepted.

Reservoir Utilization

Single Purpose Reservoirs

Mainly for industry, such as mining where the life of the dam depends on the
mines resources, town water supply or for beautification and recreation.

Multipurpose Reservoirs

1. Water supply (requires a high reservoir)


2. Irrigation
3. Silt retention
4. Transportation
5. Electricity generation
6. Recreation and beautification (requires a constant reservoir level)
7. Flood mitigation (requires a low reservoir)

Life of a dam

Many dams are in existence that are over 1000 years old. Gravity and rockfill
dams must qualify for long structural lives wheras thin arches, multiple arches or
buttress dams have more limited lives, especially if they retain aggresive water.

It is usual to finance the building of a dam on the basis of repayment of its cost
over 50 or 60 years. After this the only cost will be maintenance. The life of a
dam may be prejudiced by the amount of silt carried by the river, since the
reservoir loses capacity. It is possible to raise the dam by building up, but at a
considerable expense.
Environmental Implications

1. Land inundation - creation of a reservoir will inundate frequently good


land, and may cause people to be displaced. These factors lead to loss of
productivity and personal hardship.
2. Dislodgment of people.
3. Wildlife - some species being destroyed is almost inevitable.
4. Archaeology - inundation of items of value.
5. Beauty - areas of beauty will be destroyed.
6. Silt - retention of silt from the lower valley which would normally enrich the
land.
7. River Regime - a period of dry river bed below the dam will occur.
8. Flood Warnings - alteration of natural flow can be serious to inhabitants
and wildlife.
9. Effects of Storage on Quality of Water
10. Eutrophication
11. Thermal Stratification
12. Fish - Nitrogen Problem
13. Water-bourne diseases
14. Requirement of fish ladders for fish to continue spawning
15. Induced Earthquakes consequent to filling large reservoirs
16. Climatological Change
17. Access roads during construction destroying the natural environment
18. River pollution from

Waste water from excavations


Construction and removal of cofferdams
Wash water from concrete and aggregate plants
Oil leakage and waster disposal
Sewage and stormwater
Hot water effluents
Soil erosion during reservoir cleaning

19. Fire Risks


20. Aesthetic appearance of final dam
21. Air pollution
22. Noise pollution
23. Dust pollution

Multidisciplinary Approach

We have reached an era when the Engineer must cooperate with members of
other disciplines if a project is to be completed for optimum benefits and
minimum adverse effects.
An example of the number of disciplines involved, relative to the Auburn Dam
project;

Civil Engineering Sanitary Engineering Hydraulic Engineering


Structural Engineering Electrical Engineering Illumination Engineering
Air Pollution Engineering Acoustic Engineering Demography
History Landscape Planning Traffic
Landscape Architecture Transportation Ecology
Geography Environmental Engineering Geomorphology
Geology Hydrology Hydrography
Meteorology Soil Agricultural Economics
Biology Forestry Range Management
Fish Wildlife Legal
Photogrammetry Cartography Systems Programming
Mathematical Construction Methods Remote Sensor
Programming Analysis Interpreting

You might also like