No.
Project Phase
1.1
Concept
1.2
Concept
1.3
Concept
1.4
Concept
2.1
Feasibility
2.2
Feasibility
2.3
Feasibility
2.4
Feasibility
3.1
Planning
3.1
Planning
3.3
Planning
3.4
Planning
3.5
Planning
4.1
Execution
4.2
Execution
4.3
Execution
4.4
Execution
4.5
Execution
4.6
Execution
Closure
Key Areas
Strategic Alignment & Business Case
Sponsor Commitment
Business Process Impact Assessment
Interdependency Management
Resource Management
Risk Management
Benefits Management
Stakeholder Engagement & Communications
Scope (Requirements ) Management
Budget Management
Schedule Management
Contingency Planning
Quality Planning
Issue Management
Change Management
Procurement
Implementation Plan
Training Plan
Governance Control
PM Artifacts Management
Total
Score
Target Total
Weight %
Weighted Score
15.00%
0.10
15
5.00%
0.02
13
18
5.00%
0.04
11
15
5.00%
0.04
24
36
5.00%
0.03
11
15
5.00%
0.04
17
24
10.00%
0.07
23
36
10.00%
0.06
18
4.00%
0.02
17
33
4.00%
0.02
25
36
4.00%
0.03
11
18
4.00%
0.02
14
21
4.00%
0.03
15
4.00%
0.02
16
24
4.00%
0.03
12
2.00%
0.01
15
24
2.00%
0.01
30%
30%
20%
15
2.00%
0.01
17
24
2.00%
0.01
16%
12
18
4.00%
0.03
4%
271
426
100.00%
64.13%
100%
Total
Weighting
Total
Weighting
Total
Weighting
Total
Weighting
Total
Weighting
1. CONCEPT STAGE
ID
1.1
1.1.1
1.1.2
1.1.3
ID
1.2
1.2.1
1.2.2
1.2.3
1.2.4
1.2.5
ID
1.3
1.3.1
1.3.2
1.3.3
1.3.4
1.3.5
1.3.6
ID
1.4
1.4.1
1.4.2
1.4.3
1.4.4
1.4.5
1. CONCEPT STAGE
Category
STRATEGIC ALIGNMENT AND BUSINESS CASE
Is the current programme clearly aligned to the business strategy and to strategic priorities?
Does the programme reflect business needs within their objectives and supporting information, be they in
The organisation understands how important the programme is to delivering value to the business and the
Category
SPONSOR COMMITMENT
The programme sponsor and programme manager has the right process and content skills and complem
The programme sponsor understands not only the process of delivering the programme but understands
order to be able to make the right decisions when appropriate
The programme sponsor are committed to the successful delivery of the programme and its business outc
Is the business providing the necessary level of support?
Is there sufficient executive support for the project?
Category
BUSINESS PROCESS IMPACT ASSESSMENT
Will there be an impact on business processes?
Are they being planned for by the business?
How and when will they be implemented?
Do we know they will work?
What impacts are likely to occur outside the company?
Are they being planned for?
Category
INTERDEPENDENCY MANAGEMENT
Are interdependencies between projects within the programme or other programs highlighted in the progr
perspective?
Is there a clear understanding of the interdependency risks and how they can compound each other?
Is the nature of the interdependency clearly identified technical, business processes, organisational?
Have dependencies and constraints been documented?
Score
Status
Score
Status
Score
Status
Score
Status
1
8
Key
1
No
Some
Yes
2. FEASIBILITY STAGE
ID
2.1
2.1.1
2.1.2
2.1.3
2.1.4
2.1.5
2.1.6
2.1.7
2.1.8
2.1.9
2.1.10
2.1.11
2.1.12
ID
2.3
2.3.1
2.3.2
2.3.3
2.3.4
2.3.5
ID
2.4
2.4.1
2.4.2
2.4.3
2.4.4
2.4.5
2.4.6
2.4.7
2.4.8
ID
2.5
2.5.1
2.5.2
2.5.3
2.5.4
2.5.5
2.5.6
2.5.7
2.5.8
2.5.9
2.5.10
2.5.11
2.5.12
2. FEASIBILITY STAGE
Category
RESOURCE MANAGEMENT AND INFRASTRUCTURE
Resources for the programme are available and identified. Are resources being used efficiently?
Infrastructure for the programme are available and identified
Are the required skills available for a successful programme?
Are there sufficient resources?
Are they the right resources?
Are they able to allocate sufficient time to the project?
Is there a sense of cooperation within the project?
Are the team being well managed?
Are the resources being used efficiently?
What is morale like in the team?
Are roles and responsibilities clearly defined? (including Stakeholders)
Are they an accurate reflection of what is really happening?
Category
RISK AND ISSUE MANAGEMENT
Is there an up to date risk plan and key stakeholders involved in the plan?
Are risk mitigation strategies in place and are regularly reviewed?
Have key stakeholders been involved in developing the plan?
Are there mitigation strategies in place, and are they being monitored?
Are regular risk reviews undertaken?
Category
BENEFITS MANAGEMENT
Were the benefits of the programme clearly identified at the start of the programme?
Have they reviewed recently?
How will the benefits realisation will be achieved?
What systems and processes will be used to track progress and how the benefits will be quantified and m
Are they still relevant?
Have new benefits been identified and are they built into the project outcome?
Are the benefits being, or will they be, measured?
Have benefit delivery owners been identified?
Category
STAKEHOLDER ENGAGEMENT AND COMMUNICATIONS
All stakeholders are informed of major changes in the programme and their input is sought?
A plan & process exists for communicating progress and escalating issues to the Business, the Steering
key stakeholders
Have all key stakeholders been identified?
Do the stakeholders feel they are being kept up to date?
Are there any general areas of concern in communication?
Is that plan being implemented and expectations monitored?
Is an Agenda prepared for key meetings? (E.g. Team Meeting)
Are minutes kept for key meetings
Are proper signed authorities in place for key decisions?
Is there a decision register?
Is there an action item log for the project?
Score
Status
24
Score
Status
11
Score
Status
17
Score
Status
1
23
Key
1
No
Some
Yes
3. PLANNING STAGE
ID
3.1
3.1.1
3.1.2
3.1.3
3.1.4
3.1.5
3.1.6
ID
3.2
3.2.1
3.2.2
3.2.3
3.2.4
3.2.5
3.2.6
3.2.7
3.2.8
3.2.9
3.2.10
3.2.11
ID
3.3
3.3.1
3.3.2
3.3.3
3.3.4
3.3.5
3.3.6
3.3.7
3.3.8
3.3.9
3.3.10
3.3.11
3.3.12
ID
3.4
3.4.1
3.4.2
3.4.3
3.4.4
3.4.5
3.4.6
ID
3.5
3.5.1
3.5.2
3.5.3
3.5.4
3.5.5
3.5.6
3.5.7
3. PLANNING STAGE
Category
SCOPE MANAGEMENT
Was the scope well defined at the start of the project?
Is there a scope variation process in place?
Are there variations that have not been subject to that process?
Can the team identify the cumulative impact in time and cost of the variations?
Are actuals tracked against estimated impacts for variations?
Has the project plan been adjusted to cater for variations?
Category
BUDGET MANAGEMENT
Was the budget clearly agreed and approved at the beginning of the project?
Is there a cost tracking system in place?
Are costs being tracked?
Category
SCHEDULE MANAGEMENT
The programme and underlying projects have a list of defined and identified tasks and the structure of the
Milestones against which progress will be checked have been set appropriately and are on target?
Are tools, processes and skills available for a successful programme?
Is a suitably detailed schedule in place?
Is it up to date?
Does it reflect the current scope?
Are there regular milestones to track progress or are there reporting cycles of the project that have no mil
Is time being monitored through a time sheeting system?
Is there a solid and realistic plan for the remaining work?
Is there a structured method for tracking completion against schedule?
Category
CONTINGENCY PLANNING
Is there a contingency plan in place if the implementation fails to meet the deadline?
Has the plan been signed off by all concerned?
Has the plan been tested?
Are the impacts of a contingency plan understood by management?
What is the timeframe to implement the plan?
How long can the contingency arrangements last? What will happen then?
Category
QUALITY PLANNING
Is there a quality plan in place?
Are deliverables subject to a quality plan?
What actions happen after a quality review, and are they monitored?
Does the plan have time allocated for rework after quality review?
Is the test plan realistic (test strategy, test plan and test cases in place)?
Are the appropriate people allocated to testing?
Is testing inclusive of system, performance and interface testing?
Score
Status
Score
Status
17
Score
Status
25
Score
Status
11
Score
Status
14
Key
1
No
Some
Yes
4. EXECUTION STAGE
ID
4.1
4.1.1
4.1.2
4.1.3
4.1.4
4.1.5
ID
4.2
4.2.1
4.2.2
4.2.3
4.2.4
4.2.5
4.2.6
4.2.7
4.2.8
ID
4.3
4.3.1
4.3.2
4.3.3
4.3.4
ID
4.4
4.4.1
4.4.2
4.4.3
4.4.4
4.4.5
4.4.6
4.4.7
4.4.8
ID
4.5
4.5.1
4.5.2
4.5.3
4.5.4
4.5.5
ID
4.6
4.6.1
4.6.2
4.6.3
4.6.4
4.6.5
4.6.6
4.6.7
4.6.8
4. EXECUTION STAGE
Category
ISSUE MANAGEMENT
Is there an up to date Issue Log and key stakeholders involved in the plan?
Are Issue Actions in place and are regularly reviewed?
Are issues managed to resolution?
Is there an issue escalation process in place? Does it work?
Is the issue log current and up to date?
Category
CHANGE MANAGEMENT
Changes to the scope and plan of the programme follow the change management governance process an
strategy?
Are all programme changes evaluated for impact on the programme, other programmes, the business cas
realisation?
Are requirements documented and signed off?
Is there a documented change management plan for the project?
Category
PROCUREMENT
Are external resources being used?
Are up to date contracts in place to manage those resources through to the end of the project?
Is there a contingency to retain those resources beyond the scheduled end of the project if required?
Does the project involve purchase of equipment or software, and if so is there a plan in place for contract
Category
IMPLEMENTATION PLAN
Is there an implementation plan in place (assuming the project is well progressed)?
What support will be provided during and after launch?
Category
TRAINING PLAN
Is there a training plan in place?
Is there time to produce training materials?
Are the trainers identified?
Will staff be available for training?
Is there a plan to pilot the training?
Category
Has the programme passed any governance review checkpoints? Are all decisions and their reasons rec
Is the programme adhering to company policies and standards?
Are changes to the scope, budget and schedule been subject to governance management and control? Is
successful completion?
Are the checkpoint documents up to date with the required signed off?
Does the project team have the necessary tools, skills and processes to undertake the project successfull
Who is monitoring compliance?
Is the Marsh methodology (if it exists) being adhered to?
Is there a project governance Board?
Score
Status
Score
Status
16
Score
Status
Score
Status
15
Score
Status
Score
Status
17
Key
1
No
Some
Yes
5. CLOSURE STAGE
ID
5.1
5.1.1
5.1.2
5.1.3
5.1.4
5.1.5
5.1.6
5. CLOSURE STAGE
Category
PM Artifacts Management
Are documents held in a central project location?
Is the location well organized to enable documents to be easily located?
Is proper version control in place?
Are the major documents generally well constructed?
Is there a signed of Business Requirements Document (Business Case)?
Is there a signed PID (Project Initiation document)?
Score
Status
1
12
Key
1
No
Some
Yes