ABSTRACT
Time and expense is an important aspect of a construction project to achieve the
desired project a complete success. It is necessary for the existence of the
Scheduler and good cost control. In doing so, the level of delay and lack of costs
can be minimized or even avoided. One way of controlling costs and time is to use
a value analysis results (Earned Value) that can inform against cost and time are
precise and clear, so that it can cope with how to evaluate back against the
magnitude of the cost and time of project implementation against the value of the
contract, by applying the method value results in Advanced Development Project
project Beltway Ujong Blang Pusong , and count how many time and cost
required to complete the project. Research objectives to evaluate the amount of
the fees and the use of time has been used on this project. The methods used in
this study is the concept of the value of the results to assess the propensity of the
schedule and cost variants variants in a period as long as the project progresses,
and knowing the implementation experience a gain or loss in working on this
project from the application of the method of the value of the results, then the cost
needed to complete this project, the Estimated Completion Date (EAC) until
completion is Rp. 4,698,740,176.20 and larger than the project budget is Rp.
4,386,181,872.15 , as well as the presence of the addition Cost Variance at
Completion (VAC) of Rp. 310,558,304.05. While the project schedule
experienced aspects of the addition of time from 16 weeks into plan 17 weeks
indicated the value of SPI < 1. The project was completed at a cost higher than the
budget called cost overrun or suffered a loss and the onset delay or schedule
oveeun.