Professional Documents
Culture Documents
Contents
Pipe Sizing
Avoid oversizing & undersizing
Oversizing
High cost extra but unnecessary
Delay in getting at outlets
Increase heat loss from distributing piping
Undersizing
Slow or even no water during peak demand
Variation in temperature & pressure at outlet (obvious in mixer for
shower)
High noise level
4
Pipe insulation :
Pipe insulation:
reasons:
Heat conservation.
Reduce noise.
Control surface condensation.
Freeze prevention.
The insulating material is the same used in duct insulation
(Fiber glass)
Insulation thickness
Thicknesses or insulation to be supplied and installed for the various
systems shall conform to the following table:
(Fiber glass thickness)
a. Conditioned air supply and return (ductwork)
1 1/2"
b. Refrigerant suction and liquid lines:
1/2"
c. Condensate drain pipes
1/2"
d. Acoustic duct liner.
1
e: Heating water pipes up to 1" diameter:
1"
f. Heating water pipes above 1 :
1 1/2"
g. Domestic hot water pipes:
1"
k. Boiler, water heater
2
L. Boiler breeching & steel chimney
2.1/2
Instantaneous or semi-instantaneous
types of heaters
Thermostat
Drain
1.25 "
4 bar
Pressure Releif valve
Temp.
Size of EWH :
1"
Cold water
1"
3/4 of the total fixture units are used forc old water
Power =
S .hc Kg T .
4.2 150 (65 10)
=
= 4.2 Kw
Heating time Efficiency
3 3600 0.75
Where Shc is the specific heat capacity of water ( 4.2 Kj/kg. K), Heating time or recovery period T = 3
hrs, The mass of water 150 Liters = 150 Kg., Temperature rise from 10 to 65 C.
Insulation efficiency is 75-80 %.
12
Maximum Demand:
is the peak value of the demand. The values Hot of
water demand
are shown
Demand factor :
is the ratio of the maximum demand of the hot water
heating system to the total connected load or the
total of the individual requirements of all the fixtures
of the system.
The hot water storage for Buildings & Hotels will be calculated based on unit hourly
demand rates as follows :
galon per hour
Fixture type
Building
Hotels
Lavatory
2 gph
2 gph
bathtub
20 gph
20 gph
Shower
30 gph
75 gph
Sink
10 gph
30 gph
Laundry
20 gph
28 gph
Dishwashers
15 gph
50 gph
Demand factor
0.3
0.25
Storage factor
1.25
0.8
Domestic hot water temperature will be 60 C.
Ref [2]
Table Hw-1
Table Hw-2
Ref [2]
Example
Suppose you have to calculate , the hot water storage
capacity , the boiler power of an apartment house
(building) having the following data:
60 Lavatories , 40 kitchen sinks ,and 10 laundry 60
showers, and 40 dishwasher .
Step1& 2. The probable water demand are as follows:
From table HW-1;
Lavatories =
Shower
Dishwasher
Step 3 :
The Maximum demand of the hot water demand is:
=((602gph)+ (6030gph)+ (4010gph) + (40 x 15 gph)
+(10x 20 gph ))= 3120 gph.
Step 4
Building demand factor = 0.3 (from table HW-1 ).
Hourly heating capacity = (31200.3) = (936 gph)= 15.6
gpm.= 0.985 liter /sec or 3546 L/hr.
Step 5
The required capacity of the storage tank is:
Usable capacity = 936 x 1.25 = 1170 gal i.e. (4429 liters)
[1.25 is the storage factor from table Hw-1]
Safety storage:
Since only 70% of the tank is usable, so the actual
Q = m C T
In U.S.units
Boiler Power Q (BTU/h) = GPM (60min/hou r) T1 (8.3 lb/gal)
Q (boiler in BTU/h) = 500 gpm T1
Where
Ref [2]
Boiler power
1 Kw = 860 Kcal/hr. = 3413 BTU/ hr.
1boiler hp = 9.81 KW.
The required gross boiler power for heating water + overcome the heat
loss from pipe and boiler + the heat needed to rise the initial water
temperature ( Pick up ) is given by:
QBoiler = QT [1+ a + b]
QT = Calculated boiler power
,a = additional heat coefficient to overcome the heat loss in the pipe
systems and boiler. [0.1]
b = additional heat coefficient to overcome the pick up period [0.1 to 0.2]
. The required gross output is then;
QBoiler = [1.2 or 1.3 ] QT
As mentioned before : for QT= 230 Kw ,
T=82 C
T=10 C
T=72 C
4
4
2
4
2
showers
lavatories
bath tubes
bidet
sinks
x 2 x 0.75 = 6
x 1 x 0.75 = 3
x 2 x 0.75 = 3
x 2 x 0.75 = 6
x 2 x 0.75 = 3
_________
Total = 21 FU
For every 20 FU provide 1 gpm of
circulation 21 FU/ 20 FU = 1.05 gpm .
Or:
0.5 gpm (0.03161/s) for each 0.75- or 1 riser;
1 gpm (0.06311/s) for each 1.25 - or 1.5 riser;
2 gpm for each 2 riser.
Circulating
pump 1
H.W. S
R.H.W.
H.W.Storage tank
H.W. S
R.H.W.
Circulating pump
C.W.S
60 x 1 x 0.75 = 45 Fus.
= 10 x 2 x 0.75 = 15 Fus .
Shower
= 60 x 2 x 0.75 = 90 Fus.
Dishwasher
= 40 x 1 x 0.75 = 30 Fus .
Total = 240 FU
For every 20 FU provide 1 gpm of circulation 240 FU/ 20
FU = 12 gpm
This is the discharge of the circulated pump , which
circulate the water from (boiler tank) to building.
P T
P.R.V.
H.W.Storage tank
H.W. S
R.H.W.
BOILER
Boiler
Circulating pump
FUEL Supply
Expansion Vessel
Pump 2
Circulating pump
C.W.S
In SI units:
Power KW = Kg/sec. 4.2Kj/Kg.C (11) C
Power Kw
227
Kg/sec =
=
= 4.9 L/s
4.2 11
4.2 11
This is the discharge of the circulated pump 2, which
circulate the water from boiler-storage tank- Boiler.
h A = hL
Instantaneous or semi-instantaneous
types of heaters
Instantaneous Type:
The instantaneous indirect water heater is used to meet a demand for a
steady, continuous supply of hot water. In this type of unit, the water is
heated instantaneously as it flows through the tubes of the heating coil.
The heating medium (steam or hot boiler water) flows through the steel
pipe shell yielding a small ratio of hot water volume to heating medium
volume. Instantaneous water heaters are designed to provide sufficient
capacity to heat the required quantity of water (usually expressed in gpm
(l/s)) at the time the hot water draw occurs. Storage tanks are not usually
part of an instantaneous water heater, although a separate storage tank
may be used to provide hot water. Since instantaneous heaters are of the
Semi-Instantaneous Type:
They are similar to instantaneous water heater except
that, Semi-instantaneous water heaters have limited
storage. Storage capacities are determined by the
manufacturer to average momentary surges of hot water.
6 x 2.5 = 15 Fus.
Service sink
= 2 x 2.5 = 5 Fus .
Pantry sink
Showers
= 30 x 1.5 = 45 Fus.
Private lavatory basins = 4 x 0.75 = 3Fus ,
Total Fixture units = 70.5 FUs
HW-3
Ref [2]
HW-4
Another way to
determine gpm
HW-4
(b)
15 gpm
Ref [2]
Drawing of Water
Distribution
Systems
BOILER SPECIFICATIONS
Selection of a boiler
The selection criteria of a boiler depends very much on the
purpose of the boiler i.e. the load requirement. Boiler may be
either used to produce steam to a steam turbine, or for
heating process. If steam is required for power Generation
then superheated steam with the pressure of inlet to the
turbine is essential.
On the other hand, if the boiler is required for a heating
process like an industrial load other applications like hospitals,
hotels, kitchens steam or hot water boilers must be
considered.
For power generation we need essentially a water tube boiler.
On the other hand, for Heating process all types are
possible. Hot water are usually produced around 100C And
pressure from 2 ~ 8 atm, and high-temp hot water HTHW
from 121C~260C and pressure over 10.8 atm
Diesel Fuel
Gas
boilers
25 to 200 horsepower
Water
15 to 1500 horsepower
Burner
References
1- Mechanical & electrical equipment for buildings by Stein/Reynolds,
Ninth edition, John Wiley, 2000.
2-Practical Plumbing Engineering, Cyril M.Harris, ASPE,1998.
3- Building Services & equipment (I/II/III), F.Hall, Third edition,
1994.
4- Upland engineering, Mechanical consulting office, Dr. Ali Hammoud.
5- Applied hydraulics Part I & II .Lecture notes." by
A. Hammoud BAU- 1995
6- Pumps with practical applications, .Lecture notes. by A. Hammoud
BAU- 1999.
7- Lowara catalogue
8- Plumbers & pipefilters , Calculations Manual by R. Dodge Woodson.
9- Plumbing Design & practice by S G Deolalikar
10-
L = L T
L =Amount of change in pipe length, mm
= Coefficient of linear expansion, mm/m. C ( for (API ) PPr =0.15 mm/m C)
T= Temperature difference , C
L = is the original length of pipe m
For example : A 6 m copper pipe is subjected to temperature difference of 50 C
Calculate the pipe expansion L :
L = 0.15 x 6 x 50 =45 mm
Ls = 30 25 45 = 10 cm
73