CONSTRUCTION ENGINEERING
NAME: SHER SHAH
REG-NO: 24-FET/BSCE/F14
Excavator:
Backhoes are mainly used to clean up construction areas, to dig holes in the ground, to
smooth uneven ground, to make trenches, ditches and to help remove deep roots from
trees.
It can exert high tooth pressures and hence can excavate stiff material which normally
cannot be excavated by dragline. Output of hoe is greatest when the excavation is done
near the machine, because cycle time of operation reduces.
A backhoe, also called a rear actor or back actor, is a piece of excavating equipment or
digger consisting of a digging bucket on the end of a two-part articulated arm. They are
typically mounted on the back of a tractor or front loader.
Generally used to excavate trenches, pits for basements and also for grading works,
which requires precise control of depths.
In storm drain and utility work the hoe can perform the trench excavation and can handle
the pipe by eliminating a second machine.
There are special buckets for everything from light sand to hard rock digging.
The basic parts are boom, Jack boom, Boom foot drum, Boom sheave, stick sheave,
Stick, Bucket and Bucket sheave.
The section of the arm closest to the vehicle is known as the boom, and the section
which carries the bucket is known as the dipper or dipper stick (the terms "boom" and
"dipper" having been used previously on steam shovels). The boom is attached to the
vehicle through a pivot known as the kingpost, which allows the arm to slew left and
right, usually through a total of around 200 degrees. Modern backhoes are powered by
hydraulics.
CONSTRUCTION ENGINEERING
NAME: SHER SHAH
REG-NO: 24-FET/BSCE/F14
Application:
It is the most suitable machine for digging below the machine level, such
as, trenches, footings, basements etc.
It can be efficiently used to dress or trim the surface avoiding the use of manual effort
for dressing the excavated the surface.
Parts:
CONSTRUCTION ENGINEERING
NAME: SHER SHAH
Ideal production:
REG-NO: 24-FET/BSCE/F14
CONSTRUCTION ENGINEERING
NAME: SHER SHAH
REG-NO: 24-FET/BSCE/F14
Front shovel
excavator:
It is used to excavate earth of all classes except hard rock and load it into wagons.
Basics parts of power shovel including the track system, cabin, cables, rack, stick, boom
foot-pin, saddle block, boom, boom point sheaves and bucket.
Power shovels are used principally for excavation and removal of overburden in opencut mining operations, though it may include loading of minerals, such as coal. They are
the modern equivalent of steam shovels, and operate in a similar fashion.
Front shovel are mainly used for excavation purposes above its own track or wheel level.
They are suitable for heavy positive cutting in all types of dry soils.
CONSTRUCTION ENGINEERING
NAME: SHER SHAH
REG-NO: 24-FET/BSCE/F14
Used predominately for hard digging above track level and loading haul units
The material being excavated should be such that it will stand with a fairly vertical face
High excavation rate due to unique front shovel and side tip operation
Prolec laser system enables excavation to a more accurate level resulting in quicker
excavation rates while reducing the chance of over-digging
Improved track quality due to the excavation action (pushing into spoil rather than
pulling it back)
Fewer machine controllers on site meaning less risk and safer operations
CONSTRUCTION ENGINEERING
NAME: SHER SHAH
REG-NO: 24-FET/BSCE/F14
Problem:
Find the base diameter and
height of the conical pile that will contain 100
bank cubic yard, the angle of repose is 32 and swell is 12 %.
Solution:
As we know by the formula
base diameter=
7.64 v
tan R
1
3
loose volume
1 100
bank volume
12
loose volume
=
1
100
100
CONSTRUCTION ENGINEERING
NAME: SHER SHAH
0.12=
loose v olume
1
100
0.12+1=
1.12=
REG-NO: 24-FET/BSCE/F14
loose volume
100
loose volume
100
7.64 v
base diameter=
tan R
base diameter=
1
3
7.64 112
tan32
855.68
base diameter=
tan 32
1
3
1
3
base diameter=10.15m
For height:
1
3
CONSTRUCTION ENGINEERING
NAME: SHER SHAH
As we know
d
height=h= tan R
2
h=
11.10
tan 32
2
h=3.46 yards
h=10.4 feets
h=3.17 m
REG-NO: 24-FET/BSCE/F14