Professional Documents
Culture Documents
TECHNICAL SPECIFICATION
FOR H.V.A.C WORKS
RMLA AT LUCKNOW
LIST OF CONTENTS
I)
A)
B)
C)
D)
E)
F)
G)
H)
I)
J)
K)
L)
M)
N)
O)
P)
Q)
R)
S)
T)
U)
V)
W)
X)
Y)
Z)
AA)
II)
III)
AB)
HVAC-TS-1
TECHNICAL SPECIFICATIONS
I)
A)
1.0
SCOPE OF WORK
The general scope of work to be carried out under this HVAC subhead is illustrated in Drawings,
Specifications and Schedule of Quantities. The Contractor shall carry out and complete the said
work under this contract in every respect in conformity with the contract documents and with
the direction of and to the satisfaction of the Engineer-in-charge. The contractor shall furnish all
labour, materials and equipment as listed under Schedule of Quantities (SOQ) and specified
otherwise, transportation and incidental necessary for supply, installation, testing and
commissioning of the complete air conditioning system as described in the SOQ, Specifications
and as shown on the drawings. This also includes any material, equipment, appliances and
incidental work not specifically mentioned herein or noted on the Drawings/Documents as
being furnished or installed, but which are necessary and customary to be performed under this
contract. The central Heating, Ventilation and Air-Conditioning (HVAC) system shall comprise of
following:
a.
b.
c.
Cooling towers.
d.
e.
f.
Air handling units (AHUs) & Treated Fresh Air (TFAs) units.
g.
h.
Precision AC units.
i.
Split Units.
j.
Chilled water, condensing water and condensate drain piping inclusive of all valves and
fittings.
k.
l.
m.
n.
2.0
HVAC-TS-2
o.
Sheet metal ducts inclusive of external insulation, acoustic lining, canvas connections,
volume control dampers and smoke dampers as required.
Supply and return air registers, diffusers etc.
p.
Vane axial, tube axial, propeller fans for mechanical ventilation systems.
q.
r.
s.
t.
u.
Wiring and earthing from MCC panels to various air conditioning and mechanical
ventilation equipment, control wiring and interlocking.
v.
Cutting all openings/holes, chases in walls or slab for duct/pipe crossings, including
sealing, frame work, fire proofing, providing sleeves, cover plates, making good
structure and finishes to an approved standard. No additional payment shall be made
by Owners on this account.
w.
Provide larger size sleeve for crossing of pipe, conduits & cables through fire rated
wall/partition. The sleeve shall be sealed with fiberglass and fire sealant.
x.
y.
Balancing, testing and commissioning of the entire HVAC and mechanical ventilation
installation.
z.
aa.
RCC foundation for water chilling machines pumps & centrifugal fans with angle iron
frame work at the edges to protect these from damage.
ii.
iii.
PCC foundation blocks with angle iron frame work edging for all motor control centre.
HVAC-TS-3
iv.
v.
vi.
Supply and fixing of G.I frame for mounting of grilles in masonry walls.
3.0
3.1
All associated Electrical works listed below are excluded from the scope of this HVAC subhead
but these works shall be executed by the contractor through specialized agency engaged by the
contractor for executing Electrical(Internal EI) works as per the requirements and in accordance
with approved shop drawings of HVAC system.
i.
Providing power supply with earthing at the incoming of control panel in A/C plant
room.
ii.
Providing power supply and earthing at the incoming MCCB in each air handling unit
control panel.
iii.
Providing power and earthing at the incoming MCCB in each fan panel and pump panel
at locations called for on HVAC shop drawings.
iv.
Providing 15 amps power outlet within 2 meter reach of each fan coil unit at locations
called for on HVAC shop drawings.
v.
Providing 15 amps power outlet within 2 meter reach of each single phase propeller fan
at locations called for on HVAC shop drawings.
vi.
Providing wiring and earthing for sump pumps in air conditioning plant room.
Note:
The specialized agency executing the HVAC works shall closely coordinate with agency
executing the Electrical works (Internal EI) for executing the above works. Agency executing the
HVAC works shall conform in writing indicating desired electrical load and incoming cable size to
the electrical contractor for his equipment. But the contractor is fully responsible for proper coordination and execution of the above works.
3.2
All associated PLUMBING WORKS listed below are excluded from the scope of this HVAC
subhead but these works shall be executed by the contractor through specialized agency
engaged by the contractor for executing Plumbing works as per the requirements and in
accordance with approved shop drawings of HVAC system. Items available in BOQ under
Plumbing subhead shall be operated for executing these works.
i.
Providing soft makeup water required for cooling tower, air washers chilled water / hot
water and expansion tank.
ii.
Providing sump pumps and necessary piping for drainage of air conditioning plant room
and other machine rooms.
iii.
Providing floor drains in cooling tower area and in air handling unit rooms.
4.0
HVAC-TS-4
iv.
Disposal of condensate drain from fan coil units beyond the condensate drain riser.
BUILDING AUTOMATION SYSTEM (BAS)
The scope of HVAC work shall include the following for the interface to Building Automation
System.
5.0
i.
Stop/Manual/ Auto switches along with potential free contacts for monitoring the
manual operation status, to be provided for those equipment whose start / stop is
controlled by Building Automation System.
ii.
iii.
Necessary contactor with potential free contacts and Stop/Manual/ Auto switches to be
provided for which requires starting / stopping through Building Automation System.
iv.
Sockets /Nipples with shut-off valve for mounting sensors/transmitters on pipe lines.
v.
Installation of all motorized control valves with provision of counter flanges shall be
provided by the contractor. Interface cards (0-10 V or 4-20 mA) if required shall be the
scope of contractor for operation of valves & all the mixing valve shall be calibrated
before connecting it to BAS.
vi.
The space provision in all the equipment panel ( MCC) such as AHUs, Pumps, Chillers
etc. for mounting Current/ Potential transformers & transducers and power supply to
the transducer shall be provided by the contractor. Separate current transformers shall
be provided for monitoring current / KWH (wherever required) through BAS.
vii.
The installation of current transformer & Transducer along with wiring between Current
Transformer & Transducer up to the terminal block shall be provided by the
contractor.
viii.
The low voltage BAS Cables shall be brought up to the electric panel by the agency
executing BAS works and all terminations into the electrical panels shall be made by
HVAC executing agency after satisfying himself of the wiring system. It is to be clearly
understood that the final responsibility for the sufficiency, adequacy and conformity to
the contract requirements, of the HVAC system, lies solely with the contractor.
ix.
Provision for mounting level switch on cooling tower sump & expansion tank shall be
provided by agency executing HVAC works.
x.
15 Amps. Power supply with MCB shall be provided on all AHU panels and 32 Amps
MCB on HVAC plant room panel for power supply to DDC. Panel.
xi.
All necessary Hardware/ Software shall be made available by the HVAC agency on the
chiller Microprocessor panel for the integration of chiller panel to Building Automation
System for remote monitoring / controlling of all parameters of chiller thru BAS.
HVAC-TS-5
The contractor shall carry out the work in accordance with the Drawings, Specifications,
Schedule of Quantities and other documents forming part of the Contract.
The contractor shall be fully responsible for the performance of the selected equipment at the
specified parameters and for the efficiency of the installation to deliver the required end result.
Complete set of architectural drawings is available with the owner and reference may be made
to same for any details or information. The contractor shall also guarantee that the
performance of various equipment individually, shall not be less than the quoted capacity; also
actual power consumption shall not exceed the quoted rating, during testing and
commissioning, handing over and guarantee period.
The contractor shall verify the AC load computed by consultant. For this, the contractor shall
obtain the latest design basis from the owner (i.e. lighting load, equipment load, latest
architectural & interior plans and occupancy) to cross-check and calculate the capacity of
various equipment.
The contractor shall test the entire HVAC installation in first SUMMER, WINTER AND
MONSOON on following the completion of the installation to check and do everything
necessary to ensure that the specified indoor conditions in all spaces are maintained, that
all water and air systems are properly balanced, that all controls are calibrated accurately, and
that all units are functioning satisfactorily. In case of failure to demonstrate the result of system
in any season, the test shall be repeated in following year and the defects liability period shall
be extended accordingly and the contractor has to extend / submit the performance guarantee
accordingly.
6.0
7.0
8.0
DRAWINGS
The HVAC Drawings are diagrammatic only and indicate arrangement of various systems and
the extent of work covered in the contract. These Drawings indicate the points of supply and of
termination of services and broadly suggest the routes to be followed. Under no circumstances
shall dimensions be scaled from these Drawings. The architectural/interiors drawings and
details shall be examined for exact location of equipment, controls, grilles and diffusers.
The contractor shall follow the tender drawings in preparation of his shop drawings, and for
subsequent installation work. The contractor shall check the drawings of other trades to verify
HVAC-TS-6
spaces in which his work will be installed. Any changes/modifications required at site due to
lack of coordination with other agencies shall be carried out at contractors cost.
Maximum headroom and space conditions shall be maintained at all points. Where headroom
appears inadequate, the contractor shall notify the owners representative before proceeding
with the installation. In case installation is carried out without notifying, the work shall be
rejected and contractor shall rectify the same at his own cost.
The contractor shall examine all architectural, structural, plumbing, electrical and other services
drawings and check the as-built works before starting the work, report to the owner any
discrepancies and obtain clarification. Any changes found essential to coordinate installation of
his work with other services and trades, shall be made with prior approval of the owner
representative without additional cost to the owner. The data given in the Drawings and
Specifications is as it could be procured.
9.0
TECHNICAL DATA
The Contractor before placing purchase order for the equipments of HVAC system, shall submit
the Technical data of all major equipments. The contractor must follow all the technical
specifications mentioned in the tender.
10.0
SHOP DRAWINGS
10.1
All the shop drawings shall be prepared on computer through Autocad System based on
Architectural Drawings and site measurements. All heat load calculations shall be done using
latest version of HAP/Trace 600 only. Within agreed time frame with Engineer-in-charge after
award of the contract, contractor shall furnish, for the approval of the consultant, two sets of
detailed shop drawings of all equipment and materials including layouts for Plant room, AHU
rooms, cooling towers, fan coil units, ventilation fans; detailed ducting drawings showing exact
location of supports, flanges, bends, tee connections, reducers, guide vanes, silencers,
distribution grids, volume control dampers, collars, grilles, diffusers; detailed piping drawings
showing exact location and type of supports, valves, fittings etc; acoustic lining and external
insulation details for ducts, pipe insulation etc; electrical panels inside/outside views, power
and control wiring schematics, cable trays, supports and terminations. These shop drawings
shall contain all information required to complete the Project as per specifications and as
required by the owner/architect/consultant. These Drawings shall contain details of
construction, size, arrangement, operating clearances, performance characteristics and capacity
of all items of equipment, also the details of all related items of work by other contractors. Each
shop drawing shall contain tabulation of all measurable items of equipment/materials/works
and progressive cumulative totals from other related drawings to arrive at a variation-inquantity statement at the completion of all shop drawings. Minimum 06 sets of drawings shall
be submitted after final approval along with CD.
Each item of equipment/material proposed shall be a standard catalogue product of an
established manufacturer strictly from the manufacturers listed in Approved makes for
enclosed in the tender.
When owner/architect/consultant makes any amendments in the above drawings, the
contractor shall supply two fresh sets of drawings with the amendments duly incorporated
along with check prints, for approval. The contractor shall submit further 06 sets of shop
drawings to the client for the exclusive use by the owner and all other agencies. No material or
HVAC-TS-7
equipment may be delivered or installed at the job site until the contractor has in his
possession, the approved shop drawing for the particular material/equipment/installation.
10.2
Shop drawings shall be submitted for approval four weeks in advance of planned delivery and
installation of any material to allow owner ample time for scrutiny. No claims for extension of
time shall be entertained because of any delay in the work due to his failure to produce shop
drawings at the right time, in accordance with the approved programme.
10.3
Manufacturers drawings, catalogues, pamphlets and other documents submitted for approval
shall be in four sets. Each item in each set shall be properly labeled, indicating the specific
services for which material or equipment is to be used, giving reference to the governing
section and clause number and clearly identifying in ink the items and the operating
characteristics. Data of general nature shall not be accepted.
10.4
Samples of all materials like grilles, diffusers, controls, insulation, pre-moulded pipe section,
control wires etc shall be submitted to the owner prior to procurement. These will be submitted
in two sets for approval and retention by owner and shall be kept in their site office for
reference and verification till the completion of the Project. Wherever directed a mockup or
sample installation shall be carried out for approval before proceeding for further installation.
10.5
10.6
Where the contractor proposes to use an item of equipment, other than that specified or
detailed on the drawings, which requires any redesign of the structure, partitions, foundation,
piping, wiring or any other part of the mechanical, electrical or architectural layouts; all such redesign, and all new drawings and detailing required therefore, shall be prepared by the
contractor at his own expense and got approved by the owner. Any delay on such account shall
be at the cost of and consequence of the Contractor.
Where the work of the contractor has to be installed in close proximity to, or will interfere with
work of other agencies, he shall assist in working out space conditions to make a satisfactory
adjustment. If so directed by the owner the contractor shall prepare composite working
drawings and sections at a suitable scale, not less than 1:50, clearly showing how his work is to
be installed in relation to the work of other agencies, If the Contractor installs his work before
coordinating with other agencies, or so as to cause any interference with work of other
agencies, he shall make all the necessary changes without extra cost to the owner.
10.7
The contractor during execution shall strictly follow the approved shop drawing. In case of any
change in route, size or any other item, contractor shall obtain written approval from
owner/architect/consultant prior to execution at site.
10.8
Along with shop drawings, the contractors shall submit comprehensive variation in quantity
statement to owner for approval.
11.0
HVAC-TS-8
All equipment shall operate under all conditions of load without any sound or vibration which is
objectionable in the opinion of the owner. In case of rotating machinery, sound or vibration
noticeable outside the room in which it is installed, or annoyingly noticeable inside its own
room, shall be considered objectionable. Such conditions shall be corrected by the Contractor
at his own expense. The contractor shall guarantee that the equipment installed shall maintain
the specified NC levels.
12.0
ACCESSIBILITY
The Contractor shall verify the sufficiency of the size of the shaft openings, clearances in cavity
walls and suspended ceilings for proper installation of his ducting and piping. His failure to
communicate insufficiency of any of the above shall constitute his acceptance of sufficiency of
the same. The Contractor shall locate all equipment which must be serviced, operated or
maintained in fully accessible positions. The exact location and size of all access panels,
required for each concealed control damper, valve or other devices requiring attendance, shall
be finalized and communicated in sufficient time, to be provided in the normal course of work.
Failing this, the Contractor shall make all the necessary repairs and changes at his own expense.
Access panel shall be standardized for each piece of equipment / device / accessory and shall be
clearly nomenclatured / marked and coordinate with other agencies.
It shall be responsibility of contractor to monitor the works executed by other agencies which
may affect the performance of HVAC system.
13.0
14.0
MANUFACTURERS INSTRUCTIONS
Where manufacturer has furnished specific instructions, relating to the material and equipment
used in this project, covering points not specifically mentioned in these documents, such
instructions shall be followed in all cases.
15.0
ELECTRICAL INSTALLATION
The electrical work related to air conditioning services, shall be carried out in full knowledge of,
and with the complete coordination of the contractor. The electrical installation shall be in total
conformity with the control wiring drawings prepared by the contractor and approved by the
owner/architect/consultant. All air conditioning equipment shall be connected and tested in the
presence of an authorised representative of the contractor.
The air conditioning system shall be commissioned only after the contractor has certified in
writing that the electrical installation work for air conditioning services has been thoroughly
checked, tested and found to be totally satisfactory and in full conformity with the contract
Drawings, Specifications and manufacturers instructions. It is to be clearly understood that the
final responsibility for the sufficiency, adequacy and conformity to the contract requirements,
of the electrical installation work for air conditioning services, lies solely with the contractor.
16.0
COMPLETION CERTIFICATE
HVAC-TS-9
On completion of the Electrical installation for air conditioning, a certificate shall be furnished
by the contractor, counter signed by the licensed supervisor, under whose direct supervision
the installation was carried out. This certificate shall be in the prescribed form as required by
the local authority.
The contractor shall be responsible for getting the entire electrical installation for air
conditioning system duly approved by the local authorities concerned, and shall bear expenses
if any, in connection with the same.
17.0
18.0
COMPLETION DRAWINGS
Contractor shall periodically submit completion drawings as and when work in all respects is
completed in a particular area. These drawings shall be submitted in the form of two sets of
CDs and four portfolios (300 x 450 mm) each containing complete set of drawings on approved
scale indicating the work as - installed. These drawings shall clearly indicate complete plant
room layouts, ducting and piping layouts, location of wiring and sequencing of automatic
controls, location of all concealed piping, valves, controls, dampers, wiring and other services.
Each portfolio shall also contain consolidated control diagrams and technical literature on all
controls. The contractor shall frame under glass, in the air-conditioning plant room, one set of
these consolidated control diagrams.
19.0
20.0
ON SITE TRAINING
21.0
HVAC-TS-10
Upon completion of all work and all tests, the Contractor shall train the owners Engineers /
Personnel in the operation, adjustment and maintenance of all equipment installed.
HANDING OVER OF SYSTEM
The system shall be taken over by owner after successful commissioning and completion of
work in all respect.
22.0
22.1
Complaints
The Contractor shall receive calls for any and all problems experienced in the operation of the
system under this contract, attend to these immediately after receiving the complaints and
shall take steps to correct any deficiencies that may exist.
22.2
Repairs
All equipment that require repairing shall be immediately serviced and repaired. Since the
period of Mechanical Maintenance runs concurrently with the defects liability period, all
replacement parts and labour shall be supplied promptly free-of-charge to the owner.
23.0
23.1
24.0
24 hours a day, year round by engaging one Operator & one Helper in each shift (Each
shift is 8 hours duration) including relievers for the above staff for operating the system
on all holidays / Sundays / weekly off.
ii.
iii.
iv.
v.
vi.
HVAC-TS-11
HVAC-TS-12
B)
DESIGN PARAMETERS:
1.0
Given below are some design parameters which should be followed in addition to those given in
various sections of technical specifications enclosed.
2.0
: 12.22
: 6.67
: 0.00050
: 32.22
: 37.77
: 0.0010
3.0
4.0
5.0
AIR - HANDLERS
a) Maximum Face velocity across cooling coil MPM
: 152.0
: 152.0
4.6
2.5
e)
10.0
AIR - WASHERS
a) Maximum Face velocity across cooling pad MPM
: 152.0
: 200.0
: 152.0
: 90 %
: 1000
DUCTING WORK
a) Method of Duct Design
: 550.0
: 305.0
: 8.33
: 150.00
6.0
7.0
HVAC-TS-13
PIPING WORK
a) Friction loss (maxm.) Mt / 30 Mt length
1.60
2.50
INSULATION
Maximum temperature rise in the supply air duct from Air-handlers outlet to farthest outlet in
C 1.10
8.0
REFRIGERANT
The Imported Rotary Screw Water Cooled Chiller shall be selected for R-134A refrigerant.
C)
STANDARD SPECIFICATION:
1.0
SCOPE OF WORK
HVAC-TS-14
The complete scope of work shall cover supply, erection, testing and commissioning of the
entire HVAC system as detailed under specification.
2.0
BASIS OF DESIGN
The entire system has been based and designed on climatological data available as given under
Basis of Design and Scheme.
3.0
ASHRAE
ASME
ASA
B.S.
British Standards.
CMH
US GPM
IGPM
RPM
BTU/Hr.
Kcal/Hr.Kilo
HZ
Hertz.
H.P.
Horse Power
Kg/Cm2 Kilo
SAG
SAD
SAF
4.0
FD
Fire Damper.
VCD
RAD
FAD
RH
Relative Humidity.
DB
WB
MV
Mechanical Ventilation.
DP
Drain Point.
VAV
HVAC-TS-15
The codes, regulation as detailed below shall be followed in this contract :1.
3.
IS 11338 : 1965
(reaffirmed 1991)
4.
5.
IS 2062 : 1992
6.
Piping Work
7.
Welding
IS : 3589
8.
Refrigeration
9.
IS 4736 : 1968
10.
Butterfly Valve
IS 13095 : 1991
2.
HVAC-TS-16
11.
IS : 6392
12.
Gaskets
13.
AP : 194
14.
IS 2379 : 1963
15.
IS 2208 : 1976
16.
Starter
17.
18.
IS 277 : 1977
19.
IS : 325
20.
21.
IS 732 : 1989
22.
IS 3043 : 1966
23.
IS : 1620
24.
IS : 3624
25.
IS : 996
26.
27.
IS 2959 : 1975
28.
29.
IS 3914
5.0
HVAC-TS-17
30.
IS 4821
31.
32.
33.
IS 12065 : 1987
34.
IS 3106 : 1966
35.
IS : 778
36.
SAFTEY CODES
The following IS codes shall be followed:
6.0
IS 660
IS 659
IS 3696
IS 3016
IS 5216
IS 3696
SPACE
All shop drawings shall be prepared by the A.C Contractor after examining the Architectural &
AC drawings.
7.0
HVAC-TS-18
D)
1.0
The air conditioning contractor must take all necessary precautions to have minimum noise
generation and its transmission. Minimum vibration as permitted by IS relevant code shall be
ensured. A few points for guidance only are given below:
2.0
a)
Double fire retardant flexible connections shall be provided from air discharge to outlet
of air-handler to the duct.
b)
c)
Vibration isolation springs of suitable size to suit the weight of water chilling machine if
recommended by the manufacturer for elimination of vibrations shall be provided as
suitable for type & model of water chilling unit.
d)
All end suction pumps shall be bolted and grouted to the inertia base which in turn shall
be supported on suitable vibration isolation rubber pads duly sandwitched with 20G GI
sheets. Concrete inertia blocks shall be formed of suitable thickness and of adequate
mass.
e)
The floor supported piping shall be mounted on pipe supports with 7.5mm ribbed
neoprene pads between the base plate of the pipes and the floors.
f)
All items suspended from false ceiling shall be isolated on separate hangers.
g)
In case of ducts, conduits, pipes & tubes the annular space between construction and
penetrating element shall be sealed with sand cement plaster.
h)
The air-conditioning contractor shall take all other precautions or shall make his own
arrangements even if not specified in the tender documents for eliminating high noise
levels & shall minimize vibrations in all mechanical equipments without any additional
cost to owner.
E)
I.
1.0
GENERAL
HVAC-TS-19
The contractor shall furnish and install where indicated on plans water cooled water chilling
unit. The construction, performance and rating of the chillers shall be in accordance with latest
ARI standard 550 / 590 -1998 and shall comply with ANS.B 9.1 safety code, National Electrical
code and ASME pressure vessel code, section-VIII, division (1). Necessary 3 phase, 50 Hz, 415
volts, A.C. Power supply shall be made available for all units. The unit shall be guaranteed by
chilling unit manufacturer to produce a capacity of not less than specified tons of refrigeration
at specified leaving chilled water temperature, entering condenser water temperature, fouling
factor. The chiller models offered should be either ARI or EUROVENT certified.
1.1
QUALITY ASSURANCE
Compressor shall be dynamically balanced by the manufacturer and over-speed tested by the
manufacturer at a minimum of 120% design operating speed. Each compressor assembly shall
under go a mechanical run-in test to check proper operation of various components and to
verify that vibration levels, oil pressure / temperatures, and efficiency are within acceptable
limits. Each compressor assembly shall be pneumatically proof tested at 232 psig for R-134a and
leak tested with a tracer gas at 185 psig.
Both cooler and condenser shall be proof tested at 232 psig for R-134a on the refrigerant side
and leak tested with a refrigerant tracer gas at 185 psig. The waterside of each heat exchanger
shall be hydro-statically tested at 1.5 times the rated working pressure.
The entire chiller assembly shall be leak tested with a refrigerant tracer gas at 300 psig.
Prior to shipment the chiller controls shall be power tested to verify proper controls operation.
Chiller shall be furnished with unit-mounted starters for compressor motor and shall be factory
tested under power to verify proper compressor rotation and proper starter operation prior to
shipment.
1.2
1.3
HVAC-TS-20
WARRANTY
Warranty shall include parts and labour for one year after start-up. Rates for Annual
Maintenance contract inclusive of labour and spares for three years after warranty period shall
be quoted separately.
2.0
BASIC UNIT
The unit shall consist in general of one / two semi hermetic / hermetic chiller, Microprocessor
based automatic control panel, Star Delta close transition type motor starter, accessories and
devices as listed. The chiller package performance shall be tested as per ARI standards. These
shall be suitable for HCFC-134a refrigerant.
3.0
3.1
Each unit shall have a rotary screw bolted semi hermetic / hermetic / open type compressors
horizontal or vertical type with field serviceable helical rotor / semi hermetic rotary type
compressor duly sealed joints with O rings.
3.2
The rotary screw shall be manufactured from forged steel, with asymmetrical profiles. The
profile of screws, shall permit safe operation upto a Speed of 3000 RPM for 50 HZ operation.
3.3
The compressor housing shall be of high grade cast iron, machined with precision, to provide a
very close tolerance between the rotors and the housing.
3.4
The rotors shall be mounted on anti-friction bearings designed to reduce friction and power
input. There shall be multiple cylindrical bearings to handle the radial and axial loads.
3.5
There shall be built in oil reservoir to ensure full supply of lubricants to all bearings and a check
valve to prevent backspin during shut down.
3.6
There shall be oil pump or other means of forced lubrication of all parts during startup,
running and coasting for shut down. An oil header shall be provided in the casing.
3.7
The unit shall be complete with capacity control mechanism, to permit modulation between
20% to 100% of Capacity range. The compressor control mechanism shall have automatic spring
return capability to ensure return of capacity control valve to minimum load position to ensure
starting of compressor at minimum load. The manufacturer shall submit the load position at
starting point. The compressor shall unload from fully loaded to the minimum capacity by
means of a hydraulically actuated slide valve.
3.8
An oil separator shall be included to remove oil from the refrigerant and there shall be suitable
heat exchanger for oil separation, if required.
3.9
The motor shall be suction or discharge gas cooled in case of hermatic/ semi-hermatic machines
having redundant overload protection having thermal overload as well as current overload
protection.
3.10
Economizer, if provided in the design capacity, shall be constructed out of corrosion resistant
stainless steel plates so as to have turbulent flow and higher heat transfer area. The economizer
shall be minimum tested for 450 psig as per ASME certifications.
HVAC-TS-21
3.11
Compressor shall be fully field serviceable with full acoustical attenuation as per ARI standard
575 (latest) and easily serviceable type compressor safeties shall also include high compressor
discharge temperature, high motor winding temperature, low oil pressure, reverse rotation,
high discharge pressure, motor over load protection.
3.12
Compressor shall be equipped with internal pressure relief valve to protect against over
pressure at high side and chiller shall be protected with an external relief valve.
4.0
CONDENSER
4.1
Condenser shall be of shell and tube type construction. Heat exchanger shall be fabricated with
high-performance tubing, steel shell and tube sheets with cast-iron water boxes. Water boxes
shall be nozzle-in-head types with integral flanged water connections.
4.2
Tubing shall be copper, high-efficiency type, with integral internal and external enhancement.
Tubes shall be nominal 3/4" OD with nominal wall thickness of 0.025" measured at the root of
the fin. Tubes shall be rolled into tube sheets and shall be individually replaceable. Tube sheet
holes shall be double grooved for joint structural integrity. Cooler tubes shall be expanded into
intermediate support sheets. Intermediate support sheet spacing shall not exceed 36 inches.
4.3
Water boxes and nozzle connections shall be designed for 150-psig maximum working pressure,
unless otherwise noted. Nozzles shall feature standard ASA flanged connections.
4.4
4.5
Water boxes shall have vents; drains and covers to permit tube cleaning. A temperature sensor
shall be factory installed in each water nozzle.
4.6
The condenser shell shall include a thermal economiser, which cools the condensed liquid
refrigerant to a reduced temperature thereby increasing the refrigeration cycle efficiency. A
compressor discharge isolation valve and liquid return isolation valve shall be factory installed
to allow isolation of the refrigerant charge in the condenser.
5.0
COOLER
5.1
The cooler shall be direct expansion / flooded, shell and tube type, with steel shell and seamless
copper tubes. The refrigerant head shall be removable type. The tubes shall be supported in the
shell by adequate stiff supports to eliminate vibrations and noise. The tube ends shall be fixed
firmly into the tube sheets to prevent leakage of refrigerant gas.
5.2
The cooler shall be tested against leaks and stamped in accordance with ASME code for the
refrigerant being used and otherwise tested and constructed and tested in accordance with
ASME or equivalent approved code requirements.
5.4
5.5
The cooler shall be factory insulated with 19 mm thick closed cell polyethylene/nitrile butile.
HVAC-TS-22
6.0
CONTROLS
6.1
All the controls shall be factory wired and located in a weather proof enclosure. These shall
include fuses, selector switch, oil safety switch, high and low pressure cutouts, interlocks for
crankcase heaters and inherent motor protection devices, recycling pump-down circuit, high
discharge temperature cutout indicator lamps shall be provided for the compressor units. The
control center shall have a 40 / 80 character alphanumeric LCD display. All in one glance access
to chiller operating area.
6.2
Necessary starters for compressor motors shall be included and provided within the unit. The
compressor, cooler and the condenser shall be electrically interlocked such that the compressor
can run only when the water flow through both the heat exchangers is established. The chiller
shall have factory installed microprocessor control for various control functions.
6.3
e.
6.4
Service Function:
a.
Capacity control shall be by means of slide valve located at the rotor inlet. Load
modulation shall be from 100% to 20% of full load without the use of hot gas by-pass
under normal ARI condition. The slide valve control shall be precise, positioned by a PID
(proportional- integral- derivative) control algorithm to ensure precise control (+/- .5
degree F) of desired chilled water temperature without hunting or overshooting the set
point.
b.
HVAC-TS-23
c.
Upon request to start the compressor, the control system shall start the chilled water
pump, condenser water pump and cooling tower fans; verify that flow has been
established; and then compare leaving chilled water temperature with the chilled water
set point. If the chilled water temperature is less than the chilled water set point, the
control system will shut down the condenser water pump and wait for the cooling load
to be established.
d.
The control system shall include two compressor timers to protect the motor from
rapid cycling. The start-inhibit timer shall prevent rapid compressor restart by limiting
the start time to 3 minutes minimum. In addition the compressor shall be inhibited
from restarting from if more than 8 manual starts within a 12-hour period have
occurred.
e.
The control system shall automatically cycle the compressor off to minimise energy
usage whenever the leaving chilled water temperature is 5 degree F below the desired
chilled water set point. The chilled water pump shall remain on, and when the leaving
chilled water temperature rises above the set point by a user-configured amount, the
compressor shall automatically be recycled back on. During the shutdown period, a
message shall be displayed informing the operator a recycle restart is pending.
f.
The control centre shall monitor line voltage and if loss of voltage, high or low line
voltage, or single cycle dropout is sensed, the chiller shall shut down. Upon restoration
of line voltage, if the auto restart after power failure algorithm is enabled in the
configuration mode, the chiller shall automatically restart and resume the mode of
operation prior to shutdown.
g.
The control centre shall allow reset of chilled water temperature set point based on
water temperature rise across the evaporator. Optional input/output module shall be
provided so the following can also be achieved:
6.5
The microprocessor based control system shall maximize both compressor and motor life by
equalizing the number of starts and operating hours. The unit control module shall start the
compressor with the least number of starts and turn off the compressor with most number of
operating hours, thereby equalizing the starts and running hours and compressor wear.
6.6
6.6.1
HVAC-TS-24
6.6.2
6.7
The control logic shall make it possible to keep the chiller unit in operation and provide the
maximum available capacity to rapidly satisfy demand.
The control logic shall make it possible to rest the set point for water depending on the return
water and ambient temperature without having to make use of external adjustment.
The microprocessor shall monitor the following parameters and shall have provision to be
connected to a printer for generating operating logs at pre-programmed time interval:
a.
b.
c.
d.
e.
f.
g.
HVAC-TS-25
It shall give audio alarm and screen display on equipment failure. Microprocessor control shall
duly cycle the equipment, provide equal run time for all units and start the other compressor in
case of failure of one unit.
6.8
7.0
REFRIGERANT CIRCUIT
The refrigerant piping between compressors, chiller and condenser shall be of heavy gauge
copper with brazed joints. The circuit shall include sight glass, moisture indicator, solenoid
valves, electronic expansion valves / metering devices, filter driers and necessary shut off valves
with charging connections.
8.0
MISCELLANEOUS
Each unit shall be provided with the following:
8.1
Necessary full charge of refrigerant gas and lubricating oil. Interconnecting refrigerant piping.
8.2
External Control of chilled water temperature through a 4-20mA signal from other source.
8.3
8.4
MS Joists, channels and all other building works required for installation and commissioning.
Steel structure as required for assembling / manufacturing above equipment.
8.5
Spring vibration isolators below the unit rated by the isolator manufacturers to absorb 90% of
unit vibration and as approved by the engineer
8.6
9.0
INTERLOCKS
Manual / automatic Remote start.
Starting / stopping sequence.
Pre flow/past flow.
Compressor starter press interlock.
Pre start check of safeties & Alerts.
Low chilled water (load) recycle.
Hours / Number compressor starts & hours.
Manual reset of safeties.
10.0
HVAC-TS-26
INDICATIONS
Chiller operating status messages.
Power on, pre start Diagnostic checks.
Compressor motor Amps.
Pre alarm alert.
Alarm.
Contact for remote alarm.
Safety shutdown messages.
Elapsed time (Hours of operation).
Chiller input KW.
An operating configurable custom report.
11.0
SAFETY CUTOUTS
Each of these protective limits shall have manual reset and cause an alarm message to be
displayed at LCD screen informing the operator of shut down cause.
Motor high temperature.
Refrigerant high pressure.
Refrigerant low temperature.
CLube oil low pressure.
Lube oil sump level.
Compressor discharge temp. .
Under voltage.
Over voltage.
Cooler and condenser water flow.
Motor over current.
Motor Acceleration time.
Intermittent power loss.
Compressor starter fault.
Excessive starter transition time.
Lack of motor current signal.
Motor power supply phase reversal
Temperature sensor and transducer faults.
Single cycle drops out.
Motor miswired.
12.0
CAPACITY CONTROL.
Leaving and chilling water controls.
Soft loading control by Temperature or load.
Slide valve Actuator module.
Hot gas by pass valve.
Power (demand) limiter.
Auto chilled water reset.
13.0
HVAC-TS-27
Starter Management Module (SMM) to communicate with the chiller control system to
perform starting and stopping of the chiller, water pumps as well as monitoring starter
operation including single cycle dropout protection.
*
*
Branch circuit breaker for control power and oil heater. Pilot relays for controls of chilled
water pump, condenser water pump, customer remote alarm, and main power
disconnect shut trip.
14.0
PERFORMANCE TEST
The contractor shall carry out tests on equipment as specified in the presence of Owners /
Owners representative; Consultant in order to enable them to determine whether equipment
installation in general comply with specifications.
The Refrigeration capacity of the unit shall be computed from the measurement of water flow
and entering and leaving water temperatures. Flow measurement shall be by accurately
calibrated flow meter and temperature by Mercury in glass thermometer. Computed results
shall confirm to the specified capacities and quoted ratings. The power consumption shall be
computed from measurements of incoming voltage & input current. These tests shall be carried
out during peak summer & monsoon season as under:
a.
Main duration in continuous full load shall not be less than 72 hours.
b.
Minor interruption during the trial run shall not exceed 4 hours at a time.
c.
HVAC-TS-28
If the above conditions are not met, the period of trial run shall be extended as mutually agreed
for.
Report of recordings of trial run shall be prepared by the contractor as per test result performa
and submitted to Owners in triplicate.
15.0
POWER CONSUMPSION
The Water chilling unit should be selected for the duty as specified. The water chilling unit
should be selected for power consumption of not more than 0.65 IKW / TR at 100 % load at
operating conditions. The loading in price at the time of evaluation stage shall be done at the
rate of Rs. 2.0 Lakh per chilling machine for every increase of 0.01 IKW / TR at 100 % load in
machine IKW than the offered machine IKW by the bidder at satisfied condition in Schedule of
equipment.
If the power consumption in KW / TR of the Rotary Screw Water Chilling Machine at 100 %
capacity is found to be more than that offered by the bidder & accepted by the Client in the
contract then for every increase of 0.01 IKW / TR over the aforesaid figure, a recovery of Rs. 2.0
Lakh per machine would be effected from the contract.
F)
HVAC-TS-29
1.0
GENERAL
This section comprises the supply, erection, testing and commissioning of Pumps required for
the project.
2.0
DESIGN
The pump shall be capable of developing the required total head at rated capacity for
continuous operation. The pump shall operate satisfactorily at any point on discharge head
characteristic curve over a range of 30% to 120% capacity or capacity corresponding to 70% of
the total head whichever is lower. The pump shall run smooth without undue noise, vibration.
3.0
CONSTRUCTION
Pumps shall be as per IS:1520-1660, IS:9079,IS:325 and shall be of the following construction:
S.No. Pump Description
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Casing
Impeller
Impeller ring
Shaft
Shaft sleeve
Bearings
Base Plate
Flanges
Seal
Max. Speed
Driver
Starter
Pumps of a particular category shall be identical and shall be suitable for parallel operation with
equal load division. Components of identical pumps shall be interchangeable.
Impeller shall be made in one piece and securely keyed to the shaft. Measures to prevent
loosening during operation including rotation in the reverse direction shall be provided.
The critical speed of the pump shall be at least 30% above the rated speed. All the pumps shall
be provided with mechanical seals.
Common base plate shall be provided for pump and motor. Suitable holes shall be provided for
grouting and these shall be so located that the base can be grouted in place without disturbing
the pump and the motor. Adequate space shall be provided between pump drain connection
and base plate for installation of minimum 15mm dia. drain piping. Foundation bolts shall be
complete with nuts and washers.
HVAC-TS-30
The performance curves (capacity vs total head, efficiency, NPSH and KW requirement) ranging
from 0 to maximum capacity along with pump catalogue indicating dimensional details shall be
submitted by the contractor alongwith their bid.
Driver ratings shown are only tentative and contractor shall select their drivers at least 15% in
excess of the maximum B.H.P of the pump plus transmission losses if any. Drivers shall be
supplied with starters unless otherwise stated.
Pump and driver shall be mounted on a single bed-plate and directly driven through flexible
coupling in case of horizontal split casing pumps.
4.0
5.0
INSTALLATION
Pump shall be installed as per manufacturer's recommendations. Pump-sets shall be mounted
on isolation pads or any other equivalent vibration isolation fitting. Concrete floating
foundation shall be provided as per approved shop drawings and specifications. The isolation
pads between foundation and floor (as mentioned in schedule of quantities), foundation bolts
etc. shall be supplied by the contractor. Contractor shall ensure that the foundation bolts are
correctly embedded.
Pump-sets shall preferably be factory aligned, wherever necessary, site alignment shall be done
by competent person. Before the foundation bolts are grouted and the couplings are bolted,
the bed plate levels and alignment results shall be submitted to the Engineer in charge.
6.0
INSULATION
Pumps used for chilled water service shall be insulated as specified in section- "INSULATION".
Insulation shall be applied so that the split casing is not affected. Accessories and fittings shall
also be insulated as required.
7.0
HVAC-TS-31
TESTING
Tenderers shall submit the performance curves of the pumps supplied by them. They shall also
check the capacity and total head requirements of each pump to match his own piping and
equipment layout.
On completion of the entire installation, pumps shall be tested, wherever possible, for their
discharge, head, flow rate, B.H.P. Where it is not possible at least the discharge, head and
B.H.P. (as measured on the input side) shall be field tested. Test results shall correspond to the
performance curves.
8.0
PAINTING
After complete installation and testing, pumps accessories and fittings shall be given two coats
of approved finishing paint.
HVAC-TS-32
G)
1.0
2.0
GENERAL
This section includes the following :
3.0
4.0
A.
1.0
Individual Components
2.0
3.0
4.0
Sensor Transmitters
5.0
Sequence of Operation
The following references has been broadly considered while designing variable pumping
system.
A.
Hydraulic Institute
B.
ANSI
C.
NEMA
D.
UL
E.
ETL
F.
CSA
G.
NEC
H.
ISO
I.
IEC
The following submittals shall be submitted but not limited to the list given below by the HVAC
CONTRACTOR for approval.
HVAC-TS-33
1.
2.
Sequence of operation
3.
Shop drawing indicating dimensions, required clearances and location and size of each
field connection.
4.
5.
System profile analysis including variable speed pump curves and system curve. The
analysis shall also include staging points.
6.
5.0
6.0
QUALITY ASSURANCE
A.
The pumping package supplier shall assume Unit Responsibility for the complete
pumping package. Unit responsibility shall be defined as responsibility for interface and
successful operation of all system components supplied by the pumping system
supplier.
B.
All function of the variable speed pump controller shall be tested at the factory prior to
shipment and it shall test all inputs, outputs and program execution specific to this
application.
C.
AC contractor shall comply with all sections of this specifications relating to packaged
pumping system. Any deviations from this specification shall be bid as alternate clearly
defined in writing. If exceptions are not defined clearly the contractor shall be bound by
these specifications only.
7.0
MANUFACTURED UNITS
A.
Furnish and install as shown on the plans Variable Speed Pump controller.
B.
The control system shall include as, a minimum, pumps, the programmable logic pump
controller, adjustable frequency drive(s) and remote sensor / transmitters.
C.
The pumps, variable speed pump logic controller, adjustable frequency drives and
remote sensor / transmitter (s) shall be shipped as individual components to the job
site.
D.
Pumps, logic controller, adjustable frequency drives, sensor / transmitters and related
equipment shall be installed.
HVAC-TS-34
E.
Line voltage power wiring shall be installed by the HVAC contractor as shown on the
field connection drawings and wiring diagrams supplied with the pumping package.
F.
Low voltage (24 VDC and 115 VAC) wiring shall be installed by the controls HVAC
Contractor as shown on the field connection drawings and wiring diagrams supplied
with the pumping package.
8.0
COMPONENTS
8.1
The Technologic pump logic controller assembly shall be listed by and bear the label of
Under writers Laboratory, Inc. (Canadian Standards Association (CSA) listing available
upon request). The controller shall meet Part 15 of FCC regulations pertaining to class A
computing devices. The controller shall be specifically designed for variable speed
pumping applications.
b)
The controller shall function to a proven program that safeguards against damaging
hydraulic conditions including :
i)
Motor overload
ii)
iii)
Hunting
iv)
End of Curve.
c)
The pump logic controller shall be capable of accepting 4 discrete analog inputs from
zone sensor / transmitters indicated on the plans. The analog input resolution shall be
12 bit minimum, and the controller shall scan each analog input a minimum of once
every 500 milliseconds. The use of a multiplexer for multiple sensor inputs is not
acceptable. All sensor / transmitter inputs shall be individually wired to the pump logic
controller for continuous scan and comparison feature.
d)
The pump logic controller shall select the analog input signal which has deviated the
greatest amount from the set point. The selected signal will be used as the command
feedback input for a closed loop hydraulic stabilization function to minimize hunting.
e)
f)
g)
The pump logic controller shall be self prompting & all messages shall be displayed in
plain English. The following features shall also be provided.
a)
b)
c)
d)
h)
i)
HVAC-TS-35
The variable speed pumping system shall be provided with a user friendly operator
interface complete with membrane switches and numeric keypad. Display shall be no
less than four lines with each line capable of displaying up to twenty characters. The
human interface panel shall display the following values :
a)
b)
c)
d)
e)
f)
g)
Temperature in degree F or C
Individual Alarm Conditions
Trouble shooting diagnostics
User adjustable parameters such as alternation, PID, set points, etc.
The pump controller shall communicate to the Building Automation System (BAS) by
both hard-wired and serial communications.
a)
b)
j)
The pump logic controller shall be supplied by the pump supplier and the enclosure
shall be conforming to NEMA 1.
9.0
HVAC-TS-36
The adjustable frequency drive (s) shall be pulse width modulation (PWM) type,
microprocessor controlled design.
ii)
The AFD, including all factory installed options, shall have CSA approval.
iii)
AFD shall utilize a diode bridge rectifier to convert three phase AC to a fixed DC voltage.
Power factor shall remain above 0.95 regardless of speed or load. AFDs employing
power factor correction capacitors shall not be acceptable.
iv)
Insulated gate bipolar transistors shall be used in the inverter section to convert the
fixed DC voltage phase adjustable frequency AC output. A DC line reactor shall be
provided to minimize harmonic and current distortion of the input power line.
v)
Accel time
Decel time
Minimum frequency
Maximum frequency
Analog input filter
Analog outputs filter
Overload protection
:
:
:
:
:
:
:
vi)
Speed reference signal shall be customer selectable for 1-10 VDC or 4-20 MA.
vii)
The AFD shall be capable of displaying the following information in plain English via a
40 character alphanumeric display :
a.
b.
c.
d.
e.
f.
g.
h.
i.
viii)
Frequency
Voltage
Current
Kilowatts per hour
Fault identification
Percent torque
Percent power
RPM
Setting of O/L protection
The AFD controller shall be suitable for elevation upto 1000 meters above sea level.
11.0
HVAC-TS-37
SEQUENCE OF OPERATION
i)
The system shall consist of a Technologic pump logic controller, multiple pump / AFD
sets with manual and automatic alternation and pump staging.
ii)
The pumping system shall start upon the closure of customers contact when the pump
logic controller Mode of Operation selector switch is in the REMOTE position.
iii)
When the pump logic controller selector switch is in the LOCAL position, the pumping
system shall operate automatically.
iv)
v)
Each sensor / transmitters shall send a 4-20Ma signal to the pump logic controller,
indicative of process variable condition.
vi)
The pump logic controller shall compare each signal to the independent, engineer /
user determined set points.
vii)
When all set points are satisfied by the process variable, the pump speed shall remain
constant at the optimum energy consumption level.
viii)
The pump logic controller shall continuously scan compare each process variable to its
individual set point and control to the least satisfied zone.
ix)
If the set point cannot be satisfied by the designed lead pump, the pump logic
controller shall initiate a timed sequence of operation to stage a lag pump.
x)
The lag pump shall accelerate resulting in the lead pump (s) decelerating until they
equalize in speed.
xi)
Further change in process variable shall cause the pumps to change speed together.
xii)
When the set point criteria can be safely satisfied with fewer pumps, the Technologic
pump logic controller shall initiate a timed sequence and continue variable speed
operation.
xiii)
As the worst case zone deviates from set point, the pump logic controller shall send the
appropriate analog signed to the AFD to speed up or slow down the pump motor.
xiv)
In the event of a system differential pressure failure due to a pump of AFD fault, the
Technologic pump logic controller shall automatically start the next variable speed
pump / AFD set in sequence and continue variable speed operation.
xv)
In the event of the failure of a zone sensor / transmitter, its process variable signed
shall be removed from the scan / compare program. Alternative zone sensor /
transmitters, if available, shall remain in the scan / compare program for control.
xvi)
The zone number corresponding to the failed sensor / transmitter shall be displayed on
the operator interface of the pump logic controller.
xvii)
In the event of failure to receive all zone process variable signals, all AFDs shall maintain
100% speed, reset shall be automatic upon correction of the zone failure.
xviii)
PUMP or AFD fault shall be continuously scrolled through the display on the operator
interface of pump logic controller until the fault has been corrected and the controller
has been manually reset.
HVAC-TS-38
H)
1.0
GENERAL
These specifications covers the general requirements of design, material, manufacture,
inspections, testing at works, delivery, installation, performance testing and commissioning of
induced draft cooling tower.
2.0
3.0
DESIGN CRITERIA
The equipment offered shall be capable of cooling the rated quantity of water through the
specified range at the design wet bulb temperature.
In multi-cell construction, each cell shall be identical with other cells of the tower in all
respects. The total heat load and flow shall be equally shared amongst the number of operating
cells.
The structure shall be designed for wind and other loads as per IS: 875. The tower configuration
shall be such that it shall offer minimum restriction to airflow. The tower design shall be
compatible with manufacture of pre-fabricated parts to achieve simple, inexpensive field
erection.
4.0
CONSTRUCTION
The cooling tower shall be complete with tower, basin, foundation and mechanical equipment
as described/required. The tower shall be of single or double inlet, counter flow type of
construction. The tower shall be of induced draft type with fan located on top of the tower.
5.0
CASING
Towers shall be induced/forced draft type and in Fibreglass Reinforced Plastic construction. The
enclosure/casing shall be single mounted and preferably rectangular shaped in appearance.
The material of construction of enclosure/casing shall be F.R.P. and should be strong enough to
withstand wind pressure. The casing shall be finished smoothly to minimize air friction.
Filling material shall be polyvinylchloride (PVC), shall be laid in a manner to achieve high heat
transfer efficiency.
Water collection sump shall also be of F.R.P. material and in single molded construction to
make the sump leak proof. The tower shall be carefully designed to avoid probability of water
spillage. The sump shall be complete with outlet, overflow, quick-fill and drain connections of
adequate sizes.
Inlet louvers for air intake shall be provided.
6.0
INLET LOUVERS
Louvers shall be given a proper slope. Spacing of the louvers shall be so arranged that the water
loss is prevented. Design of louvers shall be such that it gives uniform distribution of air with
minimum pressure drop.
7.0
HVAC-TS-39
FILL
Fill sheets shall be of heavy gauge fire-retardant PVC and shall be shaped to offer minimum
resistance. Film type fill shall be supported and stabilised by structural tubing elevated above
the cold water basin floor to facilitate cleaning.
8.0
DRIFT ELIMINATORS
The drift eliminators shall be designed to restrict the drift loss below 0.2 percent of the
circulation rate. The air pressure drop across the eliminators shall be kept to a minimum. The
water collected in the eliminators shall be returned to the tower basin and shall not mix with
the discharge air stream.
9.0
WATER DISTRIBUTION
The hot water shall be distributed to the fill through distribution basin, troughs, distribution
nozzles or orifices. The water shall be equally distributed among the working cells.
10.0
FAN DECK
Fan deck shall be sturdy in construction to transmit the live loads to the frame, to support the
stack and act as an access platform for the mechanical equipment and distribution system.
11.0
HARDWARE
All hardware materials such as supporting angles, channel, rods, nut bolts etc. shall be of
stainless steel.
12.0
FAN
Fan shall be of multi-blade construction with aerofoil section blades. Air velocity at the fan
blade tip speed shall not exceed 65M/sec. Fan blade shall be of cast or moulded construction.
These shall be of easily removable and adjustable pitch type. Blade shanks and hubs shall be
suitably insulated to prevent electrolytic corrosion.
13.0
FAN DRIVES
Fan drive shall be either of direct drive type or reduction gear type. The drive shaft shall have
flexible coupling at both driving and non-driving ends. The flexible coupling bushings shall be of
rubber. Drive shaft shall be dynamically balanced.
14.0
FAN MOTOR
Fan motor shall be an AC electric motor of squirrel cage induction type suitable for 3 phase 415
+ 10% voltage variation, 50 Hz. The drive shall be weather proof with IP-55 protection.
The fan motor shall be suitable for VFD operation.
Fan shall be protected with a Fan Guard. The entire assembly should be easily accessible for
maintenance.
HVAC-TS-40
Complete performance ratings and power consumption at varying loads and outdoor wet bulb
temperatures and sound power data at full load shall be furnished with Tenders and the same
shall be verified at the time of testing and commissioning the installation.
15.0
ACCESSORIES
Cooling tower shall be provided with accessories stated as under:
a) A stainless steel pipe ladder from ground level for access to fan deck.
b) The hot water distribution basin shall be provided with suitable cover to avoid external
falling objects.
c) Each fan shall be provided with a suitable safety guard.
d) Gauge type thermometer on the hot water inlet to each cell.
e) Vibration isolators between fan and tower.
f) Foundation bolts.
16.0
TESTS
After completion, the equipment shall be offered for visual inspection by Engineer-in-charge.
Any work or component not in accordance with the specification and approved drawings shall
be replaced to the entire satisfaction of the inspection authority.
Test certificates for materials of various components of cooling tower shall be furnished.
Cooling capacities of the cooling tower shall be computed from the measurement of water
flow rate, temperature of entering and leaving water and ambient air wet bulb temperature.
Computed result shall conform to the specified capacities and quoted ratings. Power
consumption shall be computed from the measurement of input voltage and input current.
For every incremental KW of power (or part thereof) above the guaranteed power
consumption of the fan penalty shall be levied. Noise level at various locations shall be
measured at night, by a sound pressure level meter.
HVAC-TS-41
I)
1.0
SCOPE
This section sets out the general requirements in respect of shell type hot water generator as
per ASME Standards.
2.0
3.0
4.0
HEATERS
Electric heaters shall be provided in banks of equal capacity distributed our three power phase,
heaters shall be mounted within seamless copper / Incoloy sheathed electrically resistant Utubes floor mounted with EPDM Rubber and S.S steel with magnesium anode for Longevity and
easy maintenance of heaters. The heaters shall be easily removable externally, without opening
terminal plate or disturbing other components. Heaters shall be suitable for 415 + 10% volts, 50
cycles, three phase AC supply and shall be in direct contact with water contained in shell.
5.0
6.0
PRESSURE TESTING
The shell shall be tested in the factory upto two times the working pressure as specified by head
of water column in tender or 21 kg/sq. cm. gauge whichever is higher.
7.0
HVAC-TS-42
INSULATION
The shell shall be insulated with 50mm thick resin bonded fiberglass wool insulation and
covered with 26 SWG aluminium cladding.
8.0
9.0
PAINTING
The external surface of the shell shall be cleaned, derusted and applied with three with three
coats of printer.
The hot water generator shall be factory finished with durable Backed enamel paint on outside.
Shop coats of paints that have become marred during shipment / erection shall be cleaned off
with mineral spirits, then coated with enamel paint to match the finish over the adjoining shop
painted surface
HVAC-TS-43
J)
1.0
SCOPE
The Scope of this section comprises the supply, erection, testing and commissioning of air
handling units conforming to these Specifications and in accordance with requirements.
2.0
TYPE
The air handling units shall be double skin construction, draw-thru type comprising of various
sections, filter section, coil section and fan section, mixing box, (wherever the return air and
fresh air are ducted) as shown on drawings and included in schedule of quantities.
3.0
CAPACITY
The air moving and coil capacities shall be as shown in schedule of quantities.
4.0
CASING
The housing/ casing of the air handling unit shall be of double skin construction. The housing
shall be so made that it can be delivered at site in total/ semi knock down conditions depending
upon the conditions. The framework shall be of extruded aluminium hollow sections fitted with
pre-formed insulated sections. All the members shall be assembled thru mechanical joints to
make a sturdy and strong framework for various sections.
Double skin panels (each not exceeding 750mm wide) shall be made of 0.60mm pre-plasticised
coated Galvanised sheet steel and 0.60mm galvanised sheet inside with minimum 25mm thick
P.U. insulation of 38 Kg/Cu.M injected between the panels.
Double skin panels (each not exceeding 750mm wide) shall be made of 0.60mm pre-plasticised
coated Galvanised sheet steel and 0.60mm galvanised sheet inside with minimum 43mm thick
P.U. insulation of 38 Kg/Cu.M injected between the panels for TFAs and AHUs in non A/C
areas.
The panels shall be bolted from inside on to the framework with soft rubber gasket in between
to make the joints airtight. Suitable doors with powder coated hinges and latches shall be
provided for access to various panels for maintenance.
The Fan and the motor arrangement shall be mounted on to the extruded aluminum
framework. The entire housing i.e. The Air Handling Unit shall be mounted on GI Base channel
framework.
Drain pan shall be constructed of 18 gauge SS sheet with 25 mm thick 38 Kq/Cu.M. nitrile foam
insulation. The K-value shall not be more than 0.014 Kcal/hr-sq.mtr-C/M at 10C mean
temperature. The pan shall have necessary slope to facilitate for fast removal of condensate.
The coil shall be mounted on the rollers in order to facilitate easy removal of the coil from the
drain pan for cleaning. Outlet shall be provided on both the sides of drain pan.
5.0
HVAC-TS-44
MIXING BOX
AHUs requiring mixing boxes as specified in Schedule of Quantities shall be complete with fresh
and return air dampers.
6.0
DAMPER
Dampers shall be opposed blade type. Blades shall be made of double skinned aerofoil
aluminium sections with integral gasket and assembled within a rigid extruded aluminium alloy
frame. All linkages and supporting spindles shall be made of aluminium or nylon, turning in
teflon bushes. Manual dampers shall be provided with a bakelite knob for locking the damper
blades in position. Linkages shall be extended wherever specified for motorised operation.
Damper frames shall be sectionalised to minimise blade warping. Air leakage through dampers
when in the closed position shall not exceed 1.5% of the maximum design air volume flow rate
at the maximum design air total pressure.
7.0
8.0
FAN
Fans shall be centrifugal, forward inclined blades (upto 4000 cfm) and backward inclined blades
(above 4000 cfm). Fans driven by variable frequency drive shall be backward inclined
irrespective of static pressure value. Fan casing shall be made of galvanised steel sheet. Fan
wheels shall be made of galvanised steel. Fan shaft shall be grounded C40 carbon steel and
supported in self-aligning plummer block operating less than 75% of first critical speed, grease
lubricated bearings. Fan wheels and pulleys shall be individually tested and precision balanced
dynamically. Fan motor assembly shall be statically and dynamically balanced to G6.3 grade as
per relevant ISO/AMCA standard. Computerized fan selection print outs shall be submitted
along with the offer.
Motors shall be mounted inside the AHU casing on slide rails for easy belt tensioning, and be
totally enclosed,EFF1 fan cooled, to be class `F insulation. Motors shall drive heavy duty V-belt,
constant pitch, drive selected at 110% of motor horsepower.
Both fan and motors assemblies shall be mounted on a deep section aluminium alloy or
galvanized steel (depending on size) base frame.
Combination spring and rubber anti vibration mounts shall be provided for isolating the unit
casing. Frame retardant, waterproof silicone rubber impregnated flexible connection shall be
provided at the fan discharge.
9.0
COOLING COILS
Chilled water coils shall have 12.5mm (1/2") to 15mm (5/8") dia. tubes minimum 0.5 mm thick
with aluminium fins firmly bonded to copper tubes assembled in a zinc coated steel frame. Face
and surface areas shall be such as to ensure rated capacity from each unit and such that the air
velocity across each coil shall not exceed 150 meters per minute. The coil shall be pitched in the
HVAC-TS-45
unit casing for proper drainage. Each coil shall be factory tested at 21 Kg./Sq.cm air pressure
under water. Tube shall be hydraulically/mechanically expanded for minimum thermal contact
resistance with fins. Fins spacing shall be 11 to 13 fins per inch (4 to 5 fins per centimeter).
10.0
FILTERS
Each unit shall be provided with a factory assembled filter section containing washable
synthetic type air filters having anodised aluminium frame. The filter shall have minimum 90%
efficiency down to 10 microns. The media shall be supported with HDPE mesh on one side and
aluminium mesh on other side. Filter banks shall be easily accessible and designed for easy
withdrawal and renewal of filter cells. Filter framework shall be fully sealed and constructed
from aluminium alloy.
Design Parameters of Filters
Parameter
Type
Flange type
Grade
EU-3
Efficiency
Recommended size (mm)
2000
5 mm
Aluminium Anodised
Sealing of medium
Epoxy or equivalent
Medium
12 mm
No. of folds
20
No
Packing
Yes
Test Method
Washable
11.0
Filter
BS-6540-Part-I / EN-779
Yes
FILTER ASSEMBLY
The housing shall be made from extruded aluminium sections. All joints shall be sealed airtight
and shall be made free of all burrs and sharp edges.
The filter loading mechanism shall be sliding type or front loading type. The locking mechanism
shall be a spring loaded, toggle type mechanism with a bolt and thrust assembly which shall
thrust the filter evenly against the sealing flange of the housing when it is installed.
12.0
HVAC-TS-46
ISOLATORS
Vibration isolators shall be provided with all air handling units. The fan and motor framework
shall be isolated from the AHU framework by means of spring type vibration isolators. The AHU
shall be mounted on 8/9 nos. 200x200x200 P.C.C. blocks suitable for weight of the AHU. The
framework of the AHU and the P.C.C. blocks shall be isolated by means of neoprene mats of size
150mmx150mm in two layers with 20g G.S.S. sheet sandwiched in between.
13.0
ACCESSORIES
Each air handling unit shall be complete with the accessories including but not restricted to the
following.
Insulated isolation valves, Y-strainer, header drain valves, unions and insulated
condensate drain piping upto sump or floor drain in air handling unit room / nearest
point, as described in section "Piping of Schedule of quantities".
Manual air vents at high points in the cooling coil and drain plug in the bottom of the coil.
to be included in the cost of the AHU.
Thermometers in thermometer wells and pressure gauges in test points in chilled water
supply and return lines. to be included in the cost of the AHU.Air and Water side control
as specified under section "Control and Instruments"
14.0
PAINTING
Powder coated paint that have become marred during shipment or erection shall be cleaned off
with mineral spirits, wire brushed and spot primed over the affected areas, then coated with
enamel paint to match the finish over the adjoining shop-painted surfaces.
15.0
NOISE CONTROL
Air Handling Units shall be selected for the lowest operating noise level of the equipment. Fan
performance rating, power consumption, and sound power data with operating points clearly
indicated shall be submitted with the tenders and verified at the time of testing and
commissioning of the installation. The sound level within the AHU room shall be less than 75
dB.
16.0
CONNECTIONS
Piping installation requirements are specified in other section. The Drawings indicate the
general arrangement of piping, valves, fittings, and specialities. The following are specific
connection requirements:
Arrange piping installations adjacent to units to allow unit servicing and maintenance.
Connect piping to air-handling units with flanges enabling easy removal of the coil.
Connect condensate drain pans using 50 mm (2-0 inch) minimum, insulated G.I. pipe
and extend to nearest floor drain. Construct deep trap (depth as per detail) at
connection to drain pan and install cleanouts at changes in direction.
Duct installations and connections are specified in other sections. make final duct
connections with flexible connections.
17.0
Grounding: Connect unit components to ground in accordance with the Indian Electrical
Code.
18.0
Adjust water coil flow, with control valves to full coil flow, to indicate l/s (gpm).
Adjust damper linkages for proper damper operation.
Clean unit cabinet interiors to remove foreign material and construction dirt and dust.
Vacuum clean fan wheel, fan cabinet, and coils entering air face.
COMMISSIONING
19.0
HVAC-TS-47
Final Checks Before Start-Up: Perform the following operations and checks before
start-up:
Remove shipping, blocking and bracing.
Verify unit is secure on mounting and supporting devices, connections for piping,
ductwork and electrical are complete. Verify proper overload protection is installed in
motors, starters, and disconnects.
Perform cleaning and adjusting specified in this Section.
Disconnect fan drive from motor and verify proper motor rotation direction and verify
fan wheel free rotation and smooth bearing operations. Reconnect fan drive system
and align belts.
Lubricate bearings, pulleys, belts, and other moving parts with factory recommended
lubricants.
Set outside-air / supply air dampers to minimum outside-air setting.
Comb coil fins for parallel orientation.
Install temporary throw away filters for initial run and finally install clean filters.
Verify manual and automatic volume control, and fire dampers in connected ductwork
system are in the full-open position.
Disable automatic temperature control operators.
Starting procedures for central-station air-handling units:
Energize motor, verify proper operation of motor, drive system, and fan wheel. Adjust
fan to indicate RPM.
Replace fan and motor pulleys as required to achieve design conditions.
Measure and record motor electrical values for voltage and amperage.
Shut unit down and reconnect automatic temperature control operators.
TESTING
Cooling capacity of various Air handling units shall be computed from the measurements of air
flow and dry and wet bulb temperatures of air entering and leaving the coil. Flow
measurements shall be by a calibrated rotating vane anemometer and temperature
measurements by accurately calibrated mercury-in-glass thermometers. Computed ratings shall
conform to the specified capacities and quoted ratings. Power consumption shall be computed
from measurements of incoming voltage and input current, whereas, noise level at various
locations within the conditioned spaces shall be measured by a sound pressure level meter.
K)
1.0
SCOPE
HVAC-TS-48
The Scope of this section comprises the supply, erection, testing and commissioning of Fan Coil
units conforming to these Specifications and in accordance with requirements of Drawings.
2.0
TYPE
The fan coil units shall be horizontal type for ceiling suspension. All units shall be complete
with chilled water coil of three rows deep and one or more centrifugal fans and motor,
cleanable filters as detailed in section Filters, double-walled insulated condensate drain pan
as detailed in item drain pan, and 22 gauge galvanised steel casing panels insulated on
discharge side of the fan. Horizontal units shall have U-slots in top panels for ease of
installation. Horizontal fan coil units shall be provided with auxiliary secondary condensate
drain pans.
3.0
CAPACITY
The air moving and coil capacities shall be as scheduled B.O.Q.
4.0
CABINET
Cabinets shall be constructed of 22 gauge Pre coated GSS sheet steel, bonderized and provided
with powder coated finish. Corners shall be rounded without break lines. The cabinets shall be
of sufficient size to enclose all piping and control valves, and shall have access doors to piping
and controls. Access panels shall have positive locking fasteners for easy removal. Cabinets shall
be provided with all floor-mounted vertical units and ceiling-suspended horizontal units.
5.0
INTERIOR CHASSIS
The interior chassis shall be constructed of not less than 16 gauge galvanized steel sheet and
coated with a rust inhibiting paint. All cold panel surfaces shall be covered with not less than 8
mm thick expanded poly-ethylene insulation. All fan coil units shall be securely mounted from
the building structure and shall be set dead level in both directions.
6.0
DRAIN PAN
Primary drain pans shall be fabricated from 20 gauge galvanized sheet steel with all corners
welded, and an additional inner bottom panel of 20 gauge galvanized sheet steel shall be
provided to prevent damage to the bottom insulation panel. The pans shall be insulated with
not less than 10 mm thick poly-ethylene insulation sandwiched between top and bottom
panels to effectively prevent condensation. The pans shall be of sufficient size to catch all
drippage of condensation from any part of the unit; in all cases pans shall be large enough to
cover cooling coil supply and return water headers and bends, and control valves. An extension
condensate pan similar to primary drain pan shall be provided by the manufacturer on those
units where coil connections are to be made on both ends of the coil.
7.0
HVAC-TS-49
COOLING COIL
All coils shall be of staggered seamless copper tube with aluminium plate fins mechanically
bonded to copper tubes. Number of the row for cooling coils shall be as called for in the
schedule of quantities. Tubes shall be minimum 10mm OD and wall thickness shall be minimum
0.5mm. All bends and joints shall be enclosed within insulated end sections of the base unit for
protection against sweating. Each coil shall be provided with an air vent and drain plug. All
coils shall be factory tested at 21Kg. per Sq.cm (300 psig) air pressure while submerged in
water. Fin spacing shall be 12 or 13 fins per inch. Tubes shall be Mechanically / Hydraulically
expanded for minimum thermal contact resistance with fins.
8.0
FANS
Fans shall be centrifugal, forward-curve, direct-driven by a shaded-pole motor equipped with
built-in overload protection.
9.0
MOTOR
Motor shall be 220+/- 10% volts 50 cycles, single phase, six-pole, shaded pole type, speed not
exceeding 1050 RPM at maximum airflow. Motors shall have three speed windings and shall be
factory-wired to a junction box.
10.0
ISOLATORS
Ceiling-suspended horizontal units and units mounted within the ceiling space shall be hung
through neoprene in shear type vibration isolation suspensions, placed between the suspender
rods of sizes as per the details.
11.0
ACCESSORIES
All fan coil units shall be provided with the following accessories as detailed item-wise in the
schedule of quantities:
Wall mounted thermostat for individual unit, containing three-speed and on-off control for fan
speed, temperature control for summer air conditioning.
Set of Ball Valves (one with strainer) and 3/2-way motorized valve in water lines for individual
unit for each coil connection.
Fireproof double layer canvass connection.
Flexible copper piping for each coil connection.
12.0
FILTERS
The filters shall be made out of minimum three layers of aluminium wire mesh woven in
diamond shape. The filters frame work shall be out of aluminium channels. Thickness of filter
shall be minimum 10 mm.
13.0
PAINTING
Powder coating that have become marred during shipment or erection shall be cleaned off with
mineral spirits, wire brushed and spot primed over the affected areas, then coated with enamel
paint to match the finish over the adjoining surfaces.
14.0
HVAC-TS-50
NOISE CONTROL
Fan coil units shall be selected for the lowest operating noise level of the equipment. Fan
performance rating, power consumption and sound power data with operating points clearly
indicated shall be submitted with the tenders and verified at the time of testing and
commissioning of the installation.
15.0
TESTING
Cooling capacity of various fan coil units shall be computed from the measurements of air flow
and dry and wet bulb temperatures of air entering and leaving the coil. Flow measurements
shall be by a anemometer and temperature measurements by accurately calibrated
mercury-in-glass thermometers. Computed ratings shall conform to the specified capacities and
quoted ratings Noise level at various locations within the conditioned spaces shall be measured
by a sound pressure level meter.
L)
1.0
SCOPE
HVAC-TS-51
The scope of this section comprises the supply, erection, testing and commissioning of precision
AC unit conforming to these Specifications and in accordance with requirements of drawings
and of the Schedule of Quantities.
2.0
CAPACITY
The precision AC unit capacity & design parameters shall be as shown on Drawings and in
Schedule of Quantities.
3.0
CASING
Double skinned panels shall be 23 mm thick made of galvanized steel, pressure injected with
Foam insulation (density 40 kg/m3) with K factor not exceeding 0.02 Watt/Mc shall be fixed to
1.5 mm thick aluminium alloy twin box section structural framework with stainless steel screws.
Outer sheet of panels shall be made of galvanized preplasticised sheet of 0.63 mm thick, and
inner sheet of 24 Gauge plain G.I.Sheet.
The entire framework shall be mounted on an aluminium alloy or galvanized steel (depending
on size) channel base as per manufacturers recommendation. The panels shall be sealed to the
framework by heavy duty `O ring gaskets held captive in the framed extrusion. All panels shall
be detachable orhinged. Hinges shall be made of die cast aluminium with stainless steel pivots,
handles shall bemade of hard nylon and be operational from both inside and outside of the
unit. Units supplied withvarious sections shall be suitable for onsite assembly with continuous
foam gasket. All fixing and gaskets shall be concealed.
Units shall have hinged, quick opening access door in the fan section and also in filter section
where filters are not accessible from outside. Access doors shall be double skin type.
4.0
COMPRESSOR
The compressor shall be hermetic / semi-hermetic sealed type and suitable for operation on
Eco-friendly refrigerant R-407c/R-134 a/ R-410a. The compressor shall be located in separate
compartment isolated from air stream to permit servicing without shutting down the system.
Compressor shall be installed on spring mounted floating platform / rubber pads or
manufacturers recommended approved mounting. The compressor should be capable of
operating continuously even at design ambient of 42deg C (108 deg F).
Suitable overload protection shall be provided in compressor. Isolating valves shall be provided
at suction & discharge. Compressor shall be fitted with electrically operated oil heaters with
built-in thermostats.
Heaters shall be automatically actuated when the compressor is stopped. In built TIME DELAY
shall be provide for restart of compressor.
5.0
HVAC-TS-52
COOLING COIL
Cooling coils shall be of fin and tube type having aluminium fins firmly bonded to copper tubes
assembled in zinc coated steel frame. Face and surface areas shall be such as to ensure rated
capacity from each unit and air velocity across each coil shall not exceed 500 FPM. The coil shall
be pitched in the unit casing for proper drainage. Each coil shall be factory-tested at 21 Kg. per
sq.cm air pressure under water. Tube shall be mechanically / hydraulically expanded for
minimum thermal contract resistance with fins. The no. of fins per cm. shall be 4 to 5.
6.0
EVAPORATOR SECTION
Evaporator coil shall be constructed out of copper expanded on to aluminum fins to give a good
mechanical bond for maximum heat transfer and should have hydrophilic coating.
Approximately 12 to 14 number of fins per inch shall be provided. Face area of coil shall be
selected corresponding to air velocity not exceeding 2.5 m/sec.
A condensate drip tray duly insulated of stainless steel construction of minimum 18 SWG thick
shall be provided.
7.0
BLOWER SECTION
The unit shall be under floor discharge type and should be able to deliver minimum 550 CFM
per ton. Total external static pressure shall be 2.5 mm of WG. The fan speed of the blower
should automatically vary as per the inside conditions during the operation on Chilled Water
operation. The units should be equipped with direct driven backward curved radial fans with
electronically commutated brushless motors & suitable for 415 + 10% variations 3 Phase, 50 Hz
AC supply. The motors high efficiently should make for less energy absorption, especially at
partial loads and during starting.
The motor housing shall be of IP 54 or IP 55 grade. The fan shall be directly coupled / belt
driven having a maximum speed of 1400 r.p.m.
8.0
DEHUMIDIFICATION SECTION
Dehumidification shall be achieved by either reducing effective coil area by solenoid valve
arrangement or using Dew point method of control or through any other suitable method.
Whenever dehumidification is required, the control system shall enable a solenoid valve to limit
the exchange surface of the evaporating coil, thereby providing a lower evaporating
temperature.
9.0
REFRIGERANT PIPING
Each refrigerant circuit shall be suitable for operation on R-407c / R-134 A/ R-410a and shall
include the following items:
a.
b.
c.
d.
e.
f.
HVAC-TS-53
The serviceable / removable components shall have union connection for easily removal /
assembly. All pipe work shall be carried out with 16G refrigerant quality copper tube and where
bends are required, the same shall be completed using either a proprietary bending tool or
radius fittings.
10.0
ELECTRICAL SYSTEM
The electrical power system shall confirm to relevant IS standard. A main isolator (MCB) shall be
provided by the side of each unit, sized to meet the system total power requirement. Within
the panel individual power loads shall be distributed equally across the three phases.
All individual wires shall be of cross linked polythene insulated, armoured Copper cabling, with
a low smoke and flame sheath (XLPE/SWA/LSF) and colour coded or shall be numbered at their
point of termination to facilitate servicing. Low voltage control wiring and power wiring shall be
segregated from each other.
The following shall be incorporated:
a.
Contactors for automatic Micro Processor Control
b.
Single phase preventors
c.
Separate over load preventor for all individual components.
11.0
12.0
13.0
FILTERS
Each unit shall be provided with a factory assembled filter section containing washable
synthetic type air filters having anodised aluminum frame. The media shall be supported with
HDP mesh on one side and aluminum mesh on other side. Filter banks shall be easily accessible
and designed for easy withdrawal and renewal of filter cells. Filter framework shall be fully
sealed and constructed either from aluminum alloy or GI powder coated. Filter banks face
HVAC-TS-54
velocities shall not exceed 150 Mt. / minute. The filter shall be suitable for high efficiency dust
filtration.
14.0
SAFETY CONTROLS
Following minimum safety controls shall be provided for each unit :
1) High pressure trip - Manual reset (for each compressor)
2) Low pressure trip - Manual reset (for each compressor)
15.0
SAFETY INTERLOCKS
Operation of heaters & humidifier shall be possible only when blower fan is in operation.
Condenser fan shall stop after a suitable time delay on Compressors stopping.
16.0
MICROPROCESSOR CONTROLS
Following information shall be available on the display on the units:
a.
Room temperature and humidity.
b.
Supply fan working status
c.
Compressor working status
d.
Condenser fans working status.
e.
Electric heaters working status
f.
Humidifier working status.
g.
Manual / Auto unit status.
h.
Line voltage value.
i.
Temperature set point.
j.
Humidity set point.
k.
Working hours of main component i.e. compressors, fans, heater, humidifier etc.
l.
Unit working hours.
m.
Current date and time.
n.
Type of alarm (with automatic reset or block)
o.
The last 10 intervened alarms.
The microprocessor shall be able to perform following functions:
a.
Testing of the working of display system.
b.
Password for unit calibration values modification.
c.
Automatic re-start of program.
d.
Cooling capacity control.
e.
Compressor starting timer.
f.
Humidifier capacity limitation.
g.
Date and time of last 10 intervened alarm.
h.
Start / Stop status storage.
i.
Random starting of the unit.
j.
Outlet for the connection to remote system.
k.
Temperature and humidity set point calibration..
l.
Delay of General Alarm activation.
m.
Alarm calibration.
Following alarms shall be displayed on screen of microprocessor unit:
a.
Air flow loss.
b.
Clogged Filters.
c.
d.
e.
f.
g.
h
i.
j.
HVAC-TS-55
17.0
e.
Each microprocessor shall have the capability of linking up via high level interface with a
BMS for switching to a secondary unit upon any of eight (8) field selectable alarm
signals (vendor to provide details of available options). Any BMS control function should
be considered secondary to the duty/standby sequencing control of the PRESICION unit
systems.
f.
18.0
FLOOR STAND
The unit shall be supplied with an adjustable floor stand fabricated from structural steel and
painted to match the frame of the air conditioner. Nominal heights of floor stand shall be such
that they shall flush with the top surface of the raised floor tiles. The height of the floor stand
shall be adjustable plus or minus 36 millimeters. The 19 millimeters threaded rod pedestals
shall have vibration pads and a two nut locking system.
19.0
SMOKE DETECTOR
The unit shall be supplied with a factory installed and wired smoke detector to sense smoke
concentration in the return air. The smoke detector shall be specially designed to operate in the
higher air velocities it will experience in the unit. Upon detecting smoke concentrations, the
unit shall automatically stop the system and activate an alphanumeric SMOKE ALARM
indicator and audible alarm on the Microprocessor Indicator Panel.
20.0
HVAC-TS-56
Note :
Only start/stop and duplication of data shall be carried out on BAS. Once switched ON, the
operation of microprocessor unit shall be as per their standard built-in logic
M)
1.0
HVAC-TS-57
Air cooled split units shall be as per approved make, energy efficient hermitically or semihermitically compressor complete with vibration isolators & factory installed controls (like HP &
LP cutouts, inter locking Fan & Compressor, Thermostat with selector switch etc) & accessories
including wiring. Efficient cooling coil shall be selected for low velocity with 3/8"/1/2" OD
copper tubing having extended aluminium fins. Hydraulic expansion of tubes assures tight
bonding between tubes & fins for high heat transfer. Tubes shall be arranged in a staggered
design for best air contact thus giving low bypass. The cooling coil circuits are fed with liquid
refrigerant through the thermostatic expansion valve and a distributor. Blower of an
evaporating unit shall be statically and dynamically balanced and shall be selected to give
required airflow as identified in the drawings. Filters shall be minimum 25mm thick synthetic
type or equivalent wire aluminium frame. Drain pan shall be of 18 gauge insulated with
expanded polyethylene sheet. Casing shall be heavy gage factory painted to provide better
protection against rusting.
Remote air cooled condensing unit shall have to be most efficient condenser coils made out of
copper tubing with extended aluminium fins. Tubes shall be arranged in a staggered design for
better efficiency. Condenser fans shall be selected to operate quietly for required CFM to keep
condensing temperature low. The compressor may be in the indoor unit or with the outdoor
unit, but, it should be capable of operating continuously even at high ambient of 46 deg C (115
deg F). The condensing unit shall be installed with steal base frame, along with cushy foot
mounting vibration isolation pads.
Interconnected refrigerant piping between outdoor unit & indoor unit shall be of heavy gauge
copper complete with thermostatic expansion valve, liquid line strainer, drier, shut off valves,
high & low pressure gauges including insulated suction line. 25mm thick neoprene rubber pads
shall be supplied for each indoor/outdoor units. The units shall be tested in accordance with
IS:1391.
2.0
3.0
INSTALLATION
The units shall be mounted on ribbed rubber pads for vibration isolation. The contractor shall
supply the required charge of refrigerant, lubricant and other consumables, for commissioning
and testing of the equipment.
All the equipment shall be thoroughly tested and checked for leaks. All safety controls shall be
suitably set and a record of all setting shall be furnished to the project supervisor.
4.0
TESTING
Unit capacity in tons Refrigeration, shall be computed from the temperature readings and airflow measurements. Flow measurements shall be preferably by a hot-wire anemometer or a
HVAC-TS-58
velometer. Computed results shall conform to the specified capacities and the power
consumption shall conform to the figures furnished by the manufacturer.
5.0
PAINTING
Shop coats of paint that have become marred during transportation or erection shall be cleaned
off with mineral spirits, wire brushed and spot primed over the affected areas, then coated with
enamel paint to match the finish over the adjoining shop- painted surfaces.
6.0
7.0
8.0
REFRIGERANT PIPING
a.
All refrigerant pipes and fittings shall be type `L' hard drawn copper tubes and wrought
copper fitting suitable for connection with silver solder phos copper.
b.
All joints in copper piping shall be sweat joints using low temperature brazing and/or
silver solder. Before jointing any copper pipe or fittings, its interior shall be thoroughly
cleaned be passing a clean cloth via wire or cable through its entire length. The piping
shall be continuously kept clean of dirt etc. while construction the joints. Subsequently,
it shall be thoroughly blown out using carbon dioxide/nitrogen.
c.
Refrigerant lines shall be sized to limit pressure drop between evaporator and
condensing unit to less than 0.2 kg per Sq.cm.
d.
Removable type combination drier and filter shall be installed in liquid line of the
refrigeration system incorporating a three way valve bypass. After ninety days of operation, liquid line drier and filter cartridges must be replaced.
e.
After the refrigerant piping installation has been completed the refrigerant piping
system shall be pressure tested using, Freon mixed with nitrogen/carbon dioxide at a
pressure of 20 Kg per Sq. cm. (High side) and 10 Kg per Sq. cm (Low side) pressure shall
be maintained on the system for a minimum of 12 hours. The system shall then be
evacuated to a minimum vacuum of 70 cm. of mercury and held for 24 hours, during
which time, change in vacuum shall not exceed 12 cm of mercury. Vacuum shall be
checked with vacuum gage.
f.
All refrigerant piping shall be installed strictly as per the instructions and
recommendations of air conditioning equipment manufacturers.
All piping shall be tested to hydrostatic test pressure of at least two and half times the
maximum operating pressure, but not less than 24 hours. All leaks and defects in joints
revealed during the testing shall be rectified and gotten approved at site.
HVAC-TS-59
b.
Piping repaired subsequent to the above pressure test shall be retested in the same
manner.
c.
System may be tested in sections and such sections shall be securely capped, then
retested for entire system.
d.
The contractor shall give sufficient notice to all other agencies at site, of his intention to
test a section or sections of piping and all testing shall be witnessed and recorded by
Owner's site representative.
e.
The contractor shall make sure that proper noiseless circulation of fluid is achieved
through all coils and other heat exchange equipment in the system concerned. If proper
circulation is not achieved the contractor shall rectify the defective connection. He shall
bear all expenses for carrying out the above rectifications, including the tearing up and
refinishing of floors and walls as required.
f.
The contractor shall provide all materials, tools, equipment, instruments, services and
labour required to perform the test.
g.
Complete certified report shall be submitted for evaluation and approval. Upon
approval, four copies of the balancing report shall be submitted with complete
drawings and documents.
HVAC-TS-60
N)
1.0
SCOPE
The scope of this section comprises the supply and laying of pipes, pipe fittings and valves,
testing and balancing of all water and refrigerant piping required for the complete installation
as shown on the Drawings. All piping inclusive of fittings and valves shall follow the applicable
Indian Standards.
2.0
PIPE SIZES
Pipe sizes shall be as required for the individual fluid flows. Various pipe sizes have been
indicated on the Drawings, these are for Contractors guidance only and shall not relieve
contractor of responsibility for providing smooth noiseless balanced circulation of fluids.
i.
3.0
Material Specification
IS 1239 Part-1 (Mild steel medium class (Black steel)
tube)
IS 3589 Gr. FE 48 (6mm thick <300NB, 8mmthick >
300NB & < 600NB, 10mm thick above 600 NB) (welded
black steel pipe, class 2)
Material Specification
Socket welded, ASTM A85 as per ANSI B16.9
Butt welded, ASTM A234 Gr. WPB as per ANSI B16.9
Site fabricated from IS 3589 Gr. FE 48 (6mm)
Material Specification
ASTM A85 as per ANSI B16.5 (#150 class)
IS 2062 Gr.A, as per ANSI B16.5 (#150 class)
All jointing in the pipe system shall generally be by welding, unless otherwise mentioned, or
directed at site. All welding shall be done by qualified welders and shall strictly conform to BIS
Code of practice for manual metal arc, welding of Mild Steel.
Out of three weld one butt weld of each welder shall be fully radiographed for testing
purposes. Upon approval of welding joints the concerned welder shall be allowed to carry
further welding of pipes. Rest of the welds shall have 80% visual inspection.
a.
All welded joints (except pipe welded end-to-end) shall be made by use of one-piece
welding flanges, caps, nozzles, elbows, branch outlets and tees of approved make. Cut
samples shall be submitted for approval, if directed. All such fittings etc., shall be of a
type which maintain full wall-thickness at all points, simple radius and fillets, and
HVAC-TS-61
proper bevels or shoulders at ends. All job welding shall be done by the electric arc
welding process in accordance with the following :
All joints shall have 45 degree bevel type, pipe mill-bevelled or machine-bevelled by
the contractor.
All scale and oxide shall be removed with hammer, chisel or file and bevel left smooth
and clean.
Pipe lengths shall line up straight with abutting pipe ends concentric.
Both conductors from the welding machine shall be extended to locations at which
welding work is being done. The leads from welding machine to location of welding
work shall be held together with tape or other approved means so as to prevent
induced current in structural steel, in piping or in other metals within the building.
The ground lead shall be connected to length of pipe through joints in pipe, structural
steel of building or steel pipe supports.
b.
All pipes and their steel supports shall be thoroughly cleaned and given one primary
coat of red oxide paint before being installed. For vibration isolators remoulded
polyurethane pipe sections of 160 Kg/m3 density with adhesive shall be fixed
between pipe and MS support. 8 mm thick MS U clamp with resistoflex shall be fixed
on the pipe so that the pipe is kept in position. All welded piping shall be subject to
the approval at site.
c.
Fittings shall be malleable casting of pressure rating suitable for the piping system.
Fittings used on welded piping shall be of the weldable type. These shall form part of
piping and are not separately identified in Schedule of Quantities.
d.
e.
Ball and butterfly valves conforming to the following specifications shall be provided
as shown on Drawings:
---------------------------------------------------------------------------------------------------------------Size
Construction
Ends
Type
---------------------------------------------------------------------------------------------------------------15 to 40 mm
Brass
ASTM B62
Screwed
Ball
50 mm and over
Wafer
Butterfly
BUTTERFLY VALVES
Butterfly valves shall perform the function of isolating valves. Butterfly valves shall have cast
iron body with black nitrile rubber seat and shall be suitable for PN 10/ PN 16 rating as
HVAC-TS-62
indicated in the schedule of quantities. All butterfly valves shall be provided with locking
devices. Valves 250 mm and above dia shall be gear driven.
Butterfly/Ball valves shall be provided at
i. Suction and delivery side of pumps.
ii. Inlet and outlet of each condenser, chiller & cooling towers.
iii. Inlet and outlet of AHU, FCU, TFA etc.
iv. All drain connection from equipments.
5.0
6.0
7.0
To balance the HVAC installation and calculate the necessary valve settings, based on
system measurements.
To store the results of balancing.
To log measured values from a valve (differential pressure, flowrate or temperature).
To printout saved data in computerised measurement protocol (CMP) consisting of:
- Name and size of Balancing Valve (BV)
- Presetting position of BV
- P at BV
- Flow at BV
- Design Flow
HVAC-TS-63
8.0
Flanges shall be of approved make. The supply of flanges shall form part of piping (not
separately identified in Schedule of Quantities) and shall also include supply of bolts, washers,
nuts and suitable asbestos fibre / rubber insertion gaskets (minimum 3 mm thick).
9.0
All ball valves and ball valves with Y strainer shall be bronze forged body construction with
chrome plated bronze ball and handle of stainless steel constructions. These are separately
identified in Schedule of Quantities.
10.0
Flanged
The spring and hinge/stop pin shall be SS304 and bearing PTFE material. Valves shall be PN
10/ PN 16 rating as indicated in the schedule of quentities.
11.0
12.0
HVAC-TS-64
EXPANSION BELLOWS
The expansion bellows shall be flanged type expansion joint. Flanges shall be non-compressible
and mechanically strong tye and the Neoprene rubber shall be provided in between the flange
ends. The below shall works for a temperature range of minus 10C to 70c.
The length and working pressure of bellows shall be as follows:
Nominal Bore (mm)
20-25
32-200
250-350
Length (mm)
125
150
200
Pressure (Bars)
15
15
10
Bellows shall be provided with control roads to control the excessive elongation or compression
of piping systems.
It shall have torsional movement up to 3 without damage.
In plant room pipe shall not be supported from ceiling and shall have steel supports of
adequate strength firmly fixed to the floor only.
13.0
BTU METER
Meter should be a tamper proof meter with Single button design. No tampering can be done on
the meter through the keypad. Parameters of the meter can be changed through software only.
Meters need to be calibrated Online after installation to guarantee Accuracy. The calibration
have to be done onsite after installation and the same is mandatory for every meter installed
All meters need to be wet calibrated (temperature sensor and flow meter need to be calibrated
together) and calibration certificate to be provided for the BTU meters
Meters need to have an inbuilt battery backup guaranteed for a minimum of 6 years. There is
no requirement of Power supply.
The flow sensor needs to be a high capacity flow meter and can take velocities as high as 10
m/s.
One single model for line sizes ranging from 15mm to 700mm.
Meters need to be CE certified and needs to have IP68 Protection
Meter should have the facility to be used as a hot meter as well as a cold meter without any
modifications. The meter should have auto switching of Hot/ Cold meters
14.0
All pipes to be used for drain from AHU drains pans and chilled water pumps glands,
condensate drain and fittings shall be high density PVC pipe/ G.I. class B type.
15.0
HVAC-TS-65
b.
All jointing in the pipe system shall be by screwed joints and/or by screwed flanges
using 3mm 3 ply rubber insertion gaskets. Pipe threads and flanges shall be as per
relevant BIS Codes.
c.
All pipes supports shall be mild steel, thoroughly cleaned and given one primary coat
of red oxide paint before being installed.
d.
Fittings shall be galvanized steel `medium class malleable casting of pressure rating
suitable for the piping system. Flanges shall be of approved make. Supply of flanges
shall include bolts, nuts, gaskets as required. Sufficient number of flanges and unions
shall be provided for future cleaning and servicing of piping. Tee-off connection shall
be through equal or reducing tees. All equipment and valve connections, or
connections to any other mating pipes shall be through flanges required for the
mating connections. Fittings & flanges shall form part of piping and are not separately
identified in Schedule of Quantities.
e.
Gate valves, globe valves, check valves and strainers shall be similar to those specified
for chilled, condensing and hot water piping.
f.
For proper drainage of AHU Condensate, U trap shall be provided in the drain piping.
g.
All condensate drain piping shall be insulated and painted as per the section
Insulation as indicated in Schedule of Quantities.
All galvanized steel tube shall be conforming to IS 1239 class specified. When class is
not specified they shall be heavy class.
b.
Fittings shall be of malleable iron galvanized of approved make. Each fitting shall have
manufacturers trade mark stamped on it. Fittinga for G.I. pipes shall include
couplings, bends, tees, reducers, nipples, unions and bushes. Fittings shall conform to
I.S. 1879-(Part I to X).
c.
Pipes and fittings shall be joined with screwed joints. After cutting a pipe with a
hacksaw or a cutting machine care shall be taken to remove burr from the end of the
pipe after reaming with a proper file.
d.
Threaded joints will be made by applying non toxic pipe sealent for metal joints as per
BS 5290. Or with pipe sealing cord sealant as per manufacturers recommendations
used for drinking water supply. Use of red or white lead and sutli will not be
permitted for screwed joints.
e.
No pipes shall be run inside a sunken floor as far as possible. Pipes may be run under
the ceiling.
f.
Pumps suction and delivery headers shall be Galvanized iron pipes/MS heavy class
with matching fittings. The pipe joints shall be threaded as per manufacturers
instructions.
j.
Vibration Eliminators
HVAC-TS-66
Provide on all suction and delivery lines as shown the drawings double flanged
reinforced neoprene flexible pipe connectors. Connectors should be suitable for a
working pressure of each pump and tested to the test pressure given in the relevant
head. Length of the connectors shall be as per site requirements in accordance with
manufacturer details.
16.0
17.0
REFRIGERANT PIPING
a.
All refrigerant pipes and fittings shall be hard drawn copper tubes and wrought
copper / brass fittings suitable for connection with silver solder / phos-copper.
b.
All joints in copper piping shall be sweat joints using low temperature brazing and / or
silver solder. Before jointing any copper pipe or fittings, its interiors shall be
thoroughly cleaned by passing a clean cloth via wire or cable through its entire length.
The piping shall be continuously kept clean of dirt etc. while constructing the joints.
Subsequently, it shall be thoroughly blown out using carbon dioxide / nitrogen.
c.
Refrigerant lines shall be sized to limit pressure drop between the evaporator and
condensing unit to less than 0.2 kg per sq.cm.
d.
Sight glass with moisture indicator and removable type combination dryer cum filter
with MS housing and brass wire mesh / punched brass sheet shall be installed in
liquid line of the refrigeration system incorporating a three valve by pass. After ninety
days of operation, liquid line drier cartridges shall be replaced.
e.
Heat exchanger shall be MS heavy duty pipe in pipe type and without any joint in the
inner pipe.
f.
Horizontal suction line shall be pitched towards the compressor and no reducers shall
be provided for proper oil return.
g.
After the refrigerant piping installation has been completed, the refrigerant piping
system shall be pressure tested using Freon mixed with nitrogen / carbondioxide at a
pressure of 20 kg per sq. cm (high side) and 8 kg per sq. cm (low side). Pressure shall
be maintained in the system for a minimum of 12 hours. The system shall then be
evacuated to a minimum vacuum of 70 cm of mercury and held for 24 hours. Vacuum
shall be checked with a vacuum gage.
h.
All refrigeration piping shall be installed strictly as per the instructions and
recommendations of air conditioning equipment manufacturer.
PIPING INSTALLATION
a.
Design Drawings indicate schematically the size and location of pipes. The Contractor,
on award of the work, shall prepare detailed shop drawings, showing the crosssection, longitudinal sections, details of fittings, locations of isolating and control
valves, drain and air valves, and all pipe supports. He must keep in view the specific
openings in the building through which pipes are designed to pass.
b.
Piping shall be properly supported on, or suspended from, stands, clamps, hangers as
specified and as required. The Contractor shall adequately design all the brackets,
HVAC-TS-67
saddles, anchors, clamps and hangers and be responsible for their structural
sufficiency.
c.
All pipes in HVAC plant room shall be supported with pipes and channels from floor
only with necessary PUF pipe supports and resistoflex sheet.
d.
Pipe supports shall be of steel, adjustable for height and primer coated with rust
preventive paint and finish coated black. Where pipe and clamps are of dissimilar
materials, a gasket shall be provided in between. Spacing of pipe supports shall not
exceed the following:
_____________________________________________________________________
Pipe size
Spacing between supports
Rod Size
____________________________________________________________________
Upto 12 mm
1.5 Meter
8 mm
15 to 25 mm
2.0 meter
8 mm
30 to 150 mm
2.0 meter
8 mm
Over 150 mm
2.5 meter
12.5 mm
d.
Vertical pipes passing through floors shall be plumb and parallel to wall. Pipes shall be
supported on alternate floor. MS cleats shall be welded on pipes and rest on MS
channel placed on the floor with 15 mm thick resistoflex pads between the cleat and
channel. U clamps with resistoflex sheet shall be provided to keep the pipe in
position.
e.
f.
g.
Wherever pipes pass through the brick or masonry / slab openings, the gaps shall be
sealed with fire sealant such as fire barrier caulks.
h.
Insulated piping shall be supported in such a manner as not to put undue pressure on
the insulation. 20 gage metal sheet shall be provided between the insulation and the
clamp, saddle or roller, extending atleast 15 cm on both sides of the clamp, saddles or
roller.
j.
All piping work shall be carried out in a workmen like manner, causing minimum
disturbance to the existing services, buildings and structure. The entire piping work
shall be organized, in consultation with other agencies work, so that laying of pipes,
supports, and pressure testing for each area shall be carried out in one stretch.
k.
Cut-outs in the floor slabs for installing the various pipes are indicated in the
Drawings. Contractor shall carefully examine the cut-outs provided and clearly point
out where the cutouts shown in the Drawings do not meet with the requirements.
l.
The Contractor shall make sure that the clamps, brackets, clamp saddles and hangers
provided for pipe supports are adequate. Piping layout shall take due care for
expansion and contraction in pipes and include expansion joints where required.
18.0
HVAC-TS-68
m.
All pipes shall be accurately cut to the required size in accordance with relevant BIS
Codes, edges bevelled and burrs removed before laying. Open ends of the piping shall
be closed as the pipe is installed to avoid entrance of foreign matter. Where reducers
are to be made in horizontal runs, eccentric reducers shall be used for the piping to
drain freely. In other locations, concentric reducers may be used.
n.
Flanged inspection pieces 1.5 meters long, with bolted flanges on both ends, shall be
provided no more than 30 meters centres, or where-ever shown in Approved-forConstruction shop drawings, to facilitate future cleaning of all welded pipes.
o.
All buried pipes shall be cleaned and coated with zinc chromate primer and bitumen
paint, and placed on concrete blocks with PUF saddles dipped in bitumen at every 2
meters and wrapped with three layers of fibre glass tissue, each layer laid in bitumen.
p.
Insulated buried pipes shall be cleaned, de-rusted, then coated with rust-resistant
primer and placed on concrete blocks with PUF saddles dipped in bitumen at every 2
meters. Insulation shall be applied as per the section Insulation, wrapped with GI
wire and covered with polyethylene sheet. Two coats (each 6 mm thick) of cement
plaster shall be applied over chicken wire mesh lath. Where indicated in Schedule of
Quantities, buried insulated pipes shall be water-proofed using coat of Shalibond, or
approved adhesive, over the plastered surface; wrapping one layer of fibre glass RP
tissue and one layer of roofing tarfelt with sufficient overlaps, set and sealed with the
adhesive, held in position by 16 gage G.I wire tied at 15 cm intervals.
19.0
AIR VENTING :
Air valve shall be provided at the summit of piping system for air venting. Globe valve of
same size as air valves shall be incorporated. The sizes of air valves shall be as specified
hereunder. All such valves will be measured & paid.
MAINS
Up to 100 mm
101 to 300 mm
20.0
AIR VALVES
25 mm
40 mm
Drains :
Pump room :
Drains shall be provided at all low points in the system. All the drain points of Pumps shall be
collected and brought to a common header provided by other agency. Air venting valves shall
also be connected to the nearest floor trap / drain through equal size GI pipe.
AHU Rooms:
A floor trap drain point will be provided in each room. The tenderer shall extend the drain
pipe from AHU to the floor trap.
21.0
HVAC-TS-69
22.0
23.0
INSULATION
Chilled water piping, condensate drain piping etc. shall be insulated as per the specification
enumerated under the specification Insulation.
24.0
TESTING
a)
b)
Piping shall be flushed with water 2 times thoroughly before commencement of test.
Piping shall be tested by hydrostatic test pressure at 2.5 times the maximum working
pressure for a period of 24 hours.
However, minimum test pressure shall be 10 Kg/sq. cm. The defects in joints and leaks
observed during the test shall be rectified to the entire satisfaction of the Engineer-in-charge
and piping shall again be subjected to pressure test. The testing of piping system shall be
conducted in presence of Engineer in-charge. No insulation shall be carried out till the
satisfactory completion of pressure testing. The contractor shall furnish all the necessary
equipment, tools, instruments and labour to perform the test, to re-water and clean space.
25.0
BALANCING
After the completion of installation and testing of piping, all the piping system shall be
adjusted and balanced to deliver the water quantities as specified / as required /as directed.
The instruments /equipment required to adjusting the balancing of water system shall be
accurately calibrated before taking any measurement. Calibrated orifices and portable flow
meters may be used to adjust and balance the water flow. The contractor shall furnish
certificate/ balancing report to the Engineer-in-charge for evaluation and approval.
26.0
HVAC-TS-70
PAINTING
a)
After successful completion of installation, testing and insulation all exposed piping shall
be given two coats of approved synthetic enamel paint as per the colour coding
requirements.
b)
All the underground piping shall be given one coat of Zinc chromate and two coats of
black anti-corrosive paint or bituminous paint.
HVAC-TS-71
O)
1.0
SCOPE
The scope of this section comprises the supply, erection, testing and commissioning of
automatic controls and instruments conforming to these specifications and in accordance with
the requirements of Drawings and Schedule of Quantities.
2.0
TYPE
All automatic controls shall be of approved equal, electric controls as described in the various
sections of these specifications.
3.0
AUTOMATIC CONTROLS
Automatic controls required for various types of equipment/machines have been described in
the various sections of these specifications. The individual safety controls and various automatic
controls shall be installed within the equipment/machines by the manufacturers before
shipment. However, the following automatic controls, if not already installed on the
equipment/machines, may need to be installed at site by the Contractor, as per the Schedule of
Quantities.
4.0
5.0
THERMOSTATS
Shall be electronic type with 3 point output for modulating 2 position reversible motor of Two
way valve of AHU/FCU with sensing element located in the return air stream. The profile,
mounting arrangements and exact location of the thermostats shall be as approved by the
Engineer in charge. All thermostats shall be supplied with the standard mounting boxes, as
recommended by the manufacturer.
Electronic type thermostats for air-conditioning application for actuating the two way valve at
each air handling unit.
6.0
INSTRUMENTS
Instruments required for different types of machines have been described in the various
sections of these specifications and shown on the drawings. Following instruments shall be
provided as per the schedule of quantities.
HVAC-TS-72
Thermometers shall be of approved make, mercury-in-glass type with cast brass scale in a steel
casing. Thermometers shall be filled with red reading mercury. Thermometers shall be of the
separable socket type and shall have extended neck, where required, for insulated pipes. The
scale shall be 23 cm long. Thermometers shall be installed at chilled water supply and return at
air handling units, supply and return at chillers and condensers. Range of scales shall be 30-120
F (0-50 ) for air conditioning applications.
Pressure Gages shall be approved make, installed on suction and discharge sides of pumps,
chilled water supply and return at air handling units, inlet and outlet at chillers, and condensers
and as shown on the drawings and included in Schedule of Quantities. Suction side gauges at
pumps shall be compound gauges of 150 mm dia.
7.0
8.0
HVAC-TS-73
P)
1.0
EXPANSION TANKS
Expansion tanks shall be have full acceptance factor and shall be ASME rated pre-charged
bladder-type pressure vessels. The thank shall be designed to absorb the expansion forces of
heating/cooling system water while maintaining proper system pressurization under varying
operating conditions. The heavy duty bladder should contain system water thereby eliminating
tank shall be provided with insulation.
2.0
MATERIALS OF CONSTRUCTION
i.
ii.
iii.
iv.
3.0
AIR SEPARATOR
Furnish and install, as shown on plans, a centrifugal type air separator. The unit shall inlet and
outlet connections tangential to the vessel shell. The unit shall have an internal stainless steel
collector tube with 5/32 (4mm) diameter perforations and 63% open area designed to direct
accumulated air to the compression tank on an air control system or an air vent on air
elimination via an NTP vent connection at top of the unit.
A blow down connection shall be provided to facilitate routine cleaning of the separator.
Manufacturer to furnish data sheet specifying air collection efficiency and pressure drop at
rated flow.
Vessel shell diameter is to be three times the nominal inlet/outlet pipe diameter, with a
minimum vessel volume for sufficient velocity reduction. The air separator must be designed,
constructed and stamped for 125 paig@350F (862 kPa @177C) in accordance with section
VIII, division I of the ASME Boiler and pressure vessel inspectors. The air separator(s) shall be
painted with one shop coat of light gray air dry enamel.
A manufacturers data report for pressure vessels, Form U-1 as required by the provisions of the
ASME boiler and pressure vessel code, shall be furnished for each air separator upon request.
Q)
HVAC-TS-74
1.0
SCOPE
The scope of this section comprises supply fabrication, installation and testing of all sheet
metal / aluminum ducts, supply, installation, testing and balancing of all grilles, registers and
diffusers. All to be in accordance with these specifications and the general arrangement
shown on the Drawings.
2.0
Round Duct
dia (mm)
Thickness of
GS Sheet in mm
Upto 750
Upto 600
0.63 (24 G)
751 to 1500
1501 to 2250
2251 & above
601 to 750
750 to 900
901 & above
0.80 (22 G)
1.00 (20G)
1.25 (18 G)
The fabrication of duct shall be done as per IS : 655 (latest edition). Transverse joints,
connections, bracing, seam etc. shall be as per IS : 655.
All the ducts over 300 mm in either dimension shall be cross broken except those on which
rigid board insulation is applied.
Stiffening angles shall be black structural steel and riveted to the duct work. The longitudinal
seam on all ducts may be Pittsburgh seam hooked and hammered.
Ducts of size 600 mm and above shall be reinforced between the joints. Where drive-slips are
used, angles shall be riveted to the ducts 50mm from slips.
2.1
Duct Construction:
The intent of the above specification is to obtain duct pieces that are robust and rigid; enough
to preclude flutter & to achieve minimum amount of air leakage. The contractor may
fabricate ducts conforming to any other approved standard to achieve the desired result.
Factory fabricated ducts also acceptable subject to meeting all other specifications. However,
detailed specifications shall be submitted for approval before adopting the same. Suitable
vapour seal type gaskets shall be provided between the duct flanges. Ducting shall be
supported from independent hangers fixed to the building structure. In any case the duct
shall not be supported from false ceiling, ceiling hangers, light fixtures, support for light
fixtures or piping work etc. In case the structure is under construction, inserts and anchors
HVAC-TS-75
required for duct support shall be set in the building structure at the time of pouring
concrete. The Contractor shall prepare detailed drawings of hangers and supports and submit
for the approval of Engineer-in-charge. Anchoring of rods shall be done by using metallic
expansion fasteners in ceiling for concrete roof. Where ducts are required to be lined or
insulated on inner surface, their dimensions have to be enlarged so that cross-section area is
not reduced as compared to those shown on the drawings by the contractor.
2.2
2.3
Transformation:
Duct transformation shall be made with a side slope of 10mm to 70mm. Gradual changes
shall be used so as to maintain uniform velocities accompanied by decreased turbulence,
lower resistance & minimum noise.
2.4
Obstructions:
Where ducting has to avoid building structural members, piping, electrical pipes and cables,
ducts shall be transformed, divided or curved to one side and a stream lined collar shall be
used in all such cases (the reduction in area shall not exceed 20% of the original area) subject
to approval of Engineer in charge. Factory fabricated ducts are also acceptable subject to
meeting above specification.
2.5
Take offs:
All branch take-offs and collars shall be provided with turning vanes. Straightening vanes shall
be provided in the collars wherever practicable.
2.6
2.7
Fire Dampers:
Fire dampers shall be provided in the ducting wherever required as per the local codes.
However, fire dampers shall be provided in the ducts passing through fire walls and where
HVAC-TS-76
the ducts serves more than two floors, fire dampers shall have same fire resistance as that of
fire walls, ceiling etc. The fire damper shall be installed in the duct in such a manner that
vibration and rattling does not occur due to the passage of air. All fire damper units shall be
provided with motor operated switch for operating the damper as and when the fire signals
are received from the fire panel. The scope of work includes laying of cable from
corresponding fire panel to fire dampers and connection thereof. The item will be measured
and paid as per schedule of quantities.
2.8
2.9
Access Doors
Hinged or bolted access doors shall be provided in ducting for fire dampers, plenums and any
apparatus requiring frequent servicing for inspection. Access doors shall be rigid and shall be
provided with air tight rubber gaskets. Insulated ducts shall be provided with insulated doors.
2.10
2.11
Installation
The installation of ducting shall conform to standard practice of the trade. Suitable fire
resistant frame work for fixing of grilles and diffusers (if required) shall be provided by AC
contractor and no separate payment will be made on this account.
The contractor shall upon the award of work prepare detailed shop drawings of ducting for
approval by Engineer-in-charge. The drawings shall indicate the exact route of ducting,
ducting dimensions, details of splitters, vanes, dampers, fire dampers, heaters, filters etc. as
specified and required. The drawings shall also incorporate cross section indicating beams,
obstruction, piping, cables etc. The ducting shall be suitably designed to avoid all obstructions
HVAC-TS-77
and at the same time utilizing a minimum number of bends / transformations /divisions etc.
Every duct layout drawing shall clearly indicate the location and spacing of supports and
hangers.
Ducting over the false ceiling area shall be supported from the ceiling slab or from beams. In
no event, the ducting shall be supported from false ceiling hangers, cable trays / racks, pipe
supports or be permitted to rest on the false ceiling. The tenderer shall take suitable
precaution while designing the duct route so that the duct routing does not foul with beams
/columns and of other equipments.
All the ducts shall be rigid and shall be adequately supported and braced wherever required
with Tees, angles or adequate size to prevent buckling vibration or breathing. The contractor
should mention the total quantity of various sizes ducting sheet along with each floor drawing
of duct layout.
2.12
Insulation
Duct work shall be insulated as per specification given under insulation.
2.13
Testing
After completion of ducting, the entire system shall be tested for air leakages. The maximum
allowable air leakage shall be 10%. On commissioning of the plant, the entire air distribution
system shall be balanced to supply the required air quantities to various regions and rooms to
maintain the specified inside conditions. The readings of air quantities after final balancing of
the system through each diffuser or grill shall be recorded and submitted to the Engineer-inCharge.
3.0
3.1
Scope
The scope of this section comprises supply fabrication, installation and testing of all sheet
metal / aluminum ducts, supply, installation, testing and balancing of all grilles, registers and
diffusers. All to be in accordance with these specifications and the general arrangement
shown on the Drawings.
3.2
Raw Materials
Galvanizing shall be Class VII light coating of zinc, nominal 180gm/sq.m surface area and Lock
Forming Quality prime material along with mill test certificates. In addition, if deemed
necessary, samples of raw material, selected at random by owners site representative shall be
subject to approval and tested for thickness and zinc coating at contractor's expense.
3.3
Rectangular
HVAC-TS-78
Pressure 250 Pa
Duct Section Length 1.2 m (4 ft)
Maximum Duct
Size
Gauge
Joint Type
Bracing
Spacing
Nil
1750 mm
751 1000 mm
26
C & SS
26
1001 1200 mm
1201 1500 mm
1501 1800 mm
1801 2100 mm
24
24
22
20
2101 2700 mm
18
4 Bolt TDC-J
Nil
Nil
Nil
Nil
Zeebar
stiffener 1-S
Zeebar
stiffener 1-S
3.4
Upto 50 mm Wg static
pressure (+ve)
Spiral
Longitudinal
seam
seam gauge
gauge
51 250 mm Wg
static pressure (+ve)
Spiral Longitudinal
seam
seam gauge
gauge
Upto 50 mm Wg static
pressure (-ve)
Spiral
Longitudinal
seam
seam gauge
gauge
22
24
Upto 650
26
24
24
22
651-900
24
22
22
20
22
901 1250
22
20
20
20
20
1251 1500
20
18
18
18
18
1501 2100
18
16
18
16
16
20
18
16
14
HVAC-TS-79
2) All ducts, transformation pieces and fittings to be made on CNC profile cutter for requisite
accuracy of dimensions, location and dimensions of notches at the folding lines.
3) All edges to be machine treated using lockformers, flangers and rollers for turning up edges.
3.5
Duct Construction
All ducts shall be fabricated and installed in workmanlike manner, conforming to relevant
SMACNA codes.
a)
Ducts so identified on the Drawings shall be acoustically lined and insulated from outside
as described in the section Insulation and as indicated in schedule of Quantities. Duct
dimensions shown on drawings, are overall sheet metal dimensions inclusive of the
acoustic lining where required and indicated in Schedule of quantities. The fabricated
duct dimensions should be as per approved drawings and care should be taken to ensure
that all connecting sections are dimensionally matched to avoid any gaps.
b)
Ducts shall be straight and smooth on the inside with longitudinal seams shall be airtight
and at corners only which shall be either Pittsburgh or snap button as per SMACNA
practice, to ensure airtightness.
c)
All ducts up to 75cms width within conditioned spaces shall have slip and drive (C & S/SS)
joints. The internal ends of slip joints shall be in the direction of airflow. Care should be
taken to ensure that S/SS Cleats are mounted on the longer side of the duct and Cleats on
the shorter side. Ducts and accessories within ceiling spaces, visible from air-conditioned
areas shall be provided with two coats of mat black finish paint.
d)
Changes in dimensions and shape of ducts shall be gradual (between 1:4 and 1:7). Airturns (vanes) shall be installed in all bends and duct collars designed to permit the air to
make the turn without appreciable turbulence.
e)
Ducts shall be fabricated as per details shown on Drawings. All ducts shall be rigid and
shall be adequately supported and braced where required with standing seams, tees, or
angles, of ample size to keep the ducts true to shape and to prevent buckling, vibration or
breathing.
f)
All sheet metal connection, partitions and plenums, required to confine the flow of air to
and through the filters and fans, shall be constructed of 18 gauge GSS / 16gauge
aluminum, thoroughly stiffened with 25mm x 25mm x 3mm galvanized steel angle braces
and fitted with all necessary inspection doors as required, to give access to all parts of the
apparatus. Access doors shall be not less than 45cm x 45cm in size.
g)
Plenums shall be shop/factory fabricated panel type and assembled at site. Fixing of
galvanized angle flanges on duct pieces shall be with rivets heads inside i.e. towards GS
sheet and riveting shall be done from outside.
h)
Self adhesive Neoprene rubber / UV resistant PVC foam lining 5mm nominal thickness
instead of felt, shall be used between duct flanges and between duct supports in all
ducting installation.
3.6
HVAC-TS-80
Installation Practice
All ducts shall be installed generally as per tender drawings, and in strict accordance with
approved shop drawings to be prepared by the Contractor:
a) The Contractor shall provide and neatly erect all sheet metal work as may be required to
carry out the intent of these Specifications and Drawings. The work shall meet with the
approval of Owners site representative in all its parts and details
b) All necessary allowances and provisions shall be made by the Contractor for beams, pipes,
or other obstructions in the building, whether or not the same are shown on the drawings.
Where necessary to avoid beams or other structural work, plumbing or other pipes, and
conduits, the ducts shall be transformed, divided or curved to one side (the required area
being maintained) all as per the site requirements.
c) If a duct cannot be run as shown on the drawings, the contractor shall install the duct
between the required points by any path available in accordance with other services and as
per approval of owners site representative.
d) All ductwork shall be independently supported from building construction. All horizontal
ducts shall be rigidly and securely supported, in an approved manner, with trapeze hangers
formed of galvanized steel rods and galvanized steel angle/channel or a pair of brackets,
connected by galvanized steel rod under ducts. The spacing between supports should be
not greater than 2.0 meter. All vertical ductwork shall be supported by structural members
on each floor slab. Duct supports may be through galvanized steel insert plates left in slab
at the time of slab casting. Galvanized steel cleat with a hole for passing the hanger rods
shall be welded to the plates. Trapeze hanger formed of galvanized steel rods shall be hung
through these cleats. Wherever use of metal insert plates is not feasible, duct support shall
be through dash/anchor fastener driven into the concrete slab by electrically operated gun.
Hanger rods shall then hang through the cleats or fully threaded galvanized rods can be
screwed into the anchor fasteners.
e) Ducting over furred ceiling shall be supported from the slab above, or from beams after
obtaining approval of Owners site representative. In no case shall any duct be supported
from false ceiling hangers or be permitted to rest on false ceiling. All metal work in dead or
furred down spaces shall be erected in time to occasion no delay to other contractors work
in the building.
f)
Where ducts pass through brick or masonry openings, it shall be provided with 25mm thick
TF quality expanded polystyrene around the duct and totally covered with fire barrier
mortar for complete sealing.
g) All ducts shall be totally free from vibration under all conditions of operation. Whenever
ductwork is connected to fans, air handling units or blower coil units that may cause
vibration in the ducts, ducts shall be provided with a flexible connection, located at the unit
discharge. Flexible connections shall be constructed of fire retarding flexible heavy canvas
sleeve at least 10cm long securely bonded and bolted on both sides. Sleeve shall be made
smooth and the connecting ductwork rigidly held by independent supports on both sides of
the flexible connection. The flexible connection shall be suitable for pressure at the point of
installation.
HVAC-TS-81
h) Duct shall not rest on false ceiling and shall be in level from bottom. Taper pieces shall
taper from top.
4.0
DAMPERS:
All dampers shall be of Galvanised iron construction with louver dampers of robust
construction and tightly fitted. The design, method of handling, and control shall be suitable for
the location and service required.
The damper shall be of opposed blade type. The sheet thickness of blade shall be 0.8 mm and
of the frame shall be 1.0 mm.
Dampers shall be provided with suitable links, levers and quadrants as required for their proper
operation; control or setting devices shall be made robust, easily operable and accessible
through suitable access doors in the ducts. Every damper shall have an indicating device clearly
showing the damper position at all times.
Dampers shall be placed in ducts and at every branch of supply air duct connections, whether
or not indicated on the drawings, for the proper volume control and balancing of the system.
All the dampers at grille collars shall be of extruded aluminium construction with louver
dampers of robust construction and tightly fitted
5.0
6.0
7.0
HVAC-TS-82
continuously for 48 hours for driving away any dust or foreign material lodged within ducts
during installation.
The entire air distribution system shall be balanced using approved anemometer. Air quantities
at the fan discharge and at various outlets shall be identical to, or less than 5 percent in excess
of, those specified and quoted. Leakage in each air distribution system shall be within 3
percent so that supply air volume at each fan shall be identical to, or no greater than 3 percent
in excess of, the total air quantity measured at all supply outlets served by the fan. Branch duct
adjustments shall be made by volume or splitter dampers. Dampers shall be permanently
marked after air balance is complete so that these can be restored to their correct position if
disturbed at any time. Complete air balance report shall be submitted to the Engineer.-incharge for scrutiny and approval, and six copies of the approved report shall be provided with
completion documents.
R)
HVAC-TS-83
1.0
DAMPERS:
a) The fire dampers of at least one and a half hour rating shall be provided in all return air
ducts at AHU room wall crossing.
b) The fire dampers shall be fabricated out of 1.6 mm galvanized sheet steel. These
dampers shall be multi leaf type. The damper blades shall be provided on both ends
using chrome plated spindles in self lubricating bushes. The damper shall have spring
type motorized actuators, control panels and temperature sensors. Stop seals shall be
provided on top and bottom of the damper housing made of 16G GSS. For preventing
smoke leakage side seals shall be provided.
c) In the normal position the blades of the dampers shall remain open to allow maximum air
to flow. The dampers shall be actuated using electrical means to block the air. This motor
shall also be operated from the signals received from the fire control panel in case of any
fire. Also an electrical inter connection is provided such that the AHU motor is tripped
immediately a signal is received from Fire Alarm System for closing the damper.
d) All fire dampers shall be mounted in fire rated wall with a duct sleeve 400mm/500mm
long depending on the wall thickness. The sleeve shall be factory fitted on the fire
damper. The joint at the sleeve end shall be slip on type. Minimum thickness of GI sheet
used for sleeves shall be 18G.
2.0
S)
1.0
SCOPE
HVAC-TS-84
The scope of this section comprises the supply and application of insulation conforming to
these specifications.
2.0
MATERIAL
Thermal insulation material for Duct & Pipe insulation shall be closed cell Elastomeric Nitrile
Rubber . The duct insulation shall have self adhesive backing with a peal-off cover for easy
installation at site. Thermal conductivity of the insulation material shall not exceed 0.038
W/moK or 0.212 BTU / (Hr-ft2-oF/inch) at an average temperature of 30oC. Density of the
nitrile rubber shall be 40-60 Kg/m3. The product shall have temperature range of 40 oC to
105oC. The insulation material shall be fire rated for Class 0 as per BS 476 Part 6 : 1989 for fire
propagation test and for Class 1 as per BS 476 Part 7, 1987 for surface spread of flame test.
Water vapour permeability shall be not less than 0.024 per inch (2.48 x 10-14 Kg/m.s.Pa i.e.
>7000: Water vapour diffusion resistance).
Thickness of the insulation shall be as specified for the individual application. Each lot of
insulation material delivered at site shall be accompanied with manufacturers test certificate
for thermal conductivity values, density, water vapour permeability and fire properties.
Samples of insulation material from each lot delivered at site may be selected by Owners site
representative and gotten tested for thermal conductivity and density at Contractors cost.
Adhesive used for sealing the insulation shall be non-flammable, vapour proof adhensive strictly
as per manufacturers recommendations.
3.0
4.0
DUCT INSULATION
HVAC-TS-85
Duct surfaces shall be cleaned to remove all grease, oil, dirt, etc. prior to carrying out
insulation work. Measurement of surface dimensions shall be taken properly to cut closed
cell elastomeric rubber sheets to size with sufficient allowance in dimension.
Material shall be fitted under compression and no stretching of material shall be permitted.
A thin film of adhesive shall be applied on the back of the insulating material sheet and then
on to the metal surface. When adhesive is tack dry, insulating material sheet shall be placed
in position and pressed firmly to achieve a good bond. All longitudinal and transverse joints
shall be sealed as per manufacturer recommendations. The adhesive shall be strictly as
recommended by the manufacturer.
5.0
PIPING INSULATION
All chilled water, refrigerant, and condensate drain piping shall be insulated in the manner
specified herein. Before applying insulation, all pipe work and fittings shall be brushed and
cleaned, and dust, dirt, mortar and oil removed. All MS pipes shall be provided with a coat of
zinc chromate primer, followed by two coats of cold setting adhesive compound. Thermal
insulation shall then be applied as follows :
------------------------------------------------------------------------------------------------------
HVAC-TS-86
finished in neat and clean manner so as to achieve true surface. All longitudinal and transverse
joints in the outer cladding shall have a minimum overlap of 50 mm duly beaded and grooved
and shall be sealed with elastomeric metal sealant 95-44 of Benjamin Foster USA, or equivalent.
Use of screws for fastening may puncture vapour barrier hence GI bands 0.50mm thick x 25 mm
wide shall be provided at every 500 mm to retain cladding in position. Adhesive component
once opened shall be used immediately and no leftovers shall be permitted to be used
following day.
All insulation work shall be carried out by skilled workmen specially trained in this kind of work.
All insulated clad pipes shall be labeled (S, R or RR) and provided with 300 mm wide band of
paint along the circumference at every 1200 mm distance for color coding. Direction of fluid
shall also be marked. Un-insulated M S pipes shall be painted throughout and direction of fluid
marked. All painting shall be as per relevant BIS codes.
6.0
PUMP INSULATION
Chilled water pump shall be insulated to the same thickness as the pipe to which they are
connected and application shall be same as above. Care shall be taken to apply insulation in a
manner as to allow the dismantling of pumps without damaging the insulation.
7.0
SHELL INSULATION
The chiller shells shall be factory insulated in accordance with the manufacturers standards.
8.0
ACOUSTIC LINING OF AHU ROOMS AND SUPPLY AIR DUCT & PLENUM
Two walls and ceiling of air conditioning plant room and air handling unit rooms may be
provided with acoustic lining of resin bonded fibreglass wool as per Schedule of Quantities and
as shown on the Drawings. The surface shall be cleaned and frame work of 24 gage GI
fabricated Channels 25 mm x 50 mm screwed back to back at 60 cm centres shall be provided
vertically and horizontally so that 60 x 60 cm squares are formed. The gaps between frames
shall be filled with 50 mm thick about 60 cm x 60 cm cut panels of resin bonded fibreglass slabs.
The entire surface shall then be covered with fibreglass tissue and 26 gage perforated
aluminium sheet, 60 cm or 120 cm wide having atleast 15 percent perforations, fixed with sheet
metal screws. Over-lapping of sheets shall be covered with Aluminium beading. Acoustic lining
of walls shall be terminated approximately 15 cm above the finished floor to prevent damage to
insulation due to accidental water-logging in plant/AHU rooms.
9.0
Method of Application
a)
Clean RCC slab and make it free from dust and other laitance matter.
b)
Lay cement based water proofing on roof with a minimum slope of 1:80 and average
thickness of 18 mm using brickbats of appropriate size and shape suitable to achieve the
required slope laid over 15 mm thick waterproof c3ement mortar 1:4 and finished with 20
mm thick waterproof plaster wing cement mortar 1:4 and making false squares of 300
mm size including rounding off the junction of roof and parapet walls for a height of 300
mm with brickbats and 20 mm thick waterproof plaster and conducting necessary leakage
/ dampers tests, etc.
HVAC-TS-87
c)
Lay 65 mm thick extruded polystyrene boards over prepared surface fixing with adhesive.
Adhesive shall be strictly as per recommendations from manufacturer.
d)
e)
Note :
If contractor is awarded work of waterproofing + overdeck insulation, follow all steps from (a) to
(e).
if contractor is awarded work of only overdeck insulation follow step (c) and (d). Rest will be
done by Civil Contractor).
10.0
UNDERDECK INSULATION
Underdeck insulation shall be 50mm thick TF Quality expanded polystyrene (32 Kg/m3) or
30mm thick phenotherm. Underdeck surface of ceiling shall be cleaned and made dirt free.
Insulation panels shall be pasted on this surface with black CPRX compound. 28g wire net
shall be tightened around insulation so as to avoid any kind of sagging. Ends of net shall be
overlapping by at least 25mm. Overlaps shall be screwed with galvanised screws to avoid
rusting.
11.0
EQUIPMENTS:
All equipments such as AHUs, Fan coil units, water chiller equipments shall be suitably
insulated as required and as per manufacturers requirements. The cost of such insulation is
deemed to be included in the cost of equipments. The insulation shall be applied after
applying of necessary primer, factory applied insulation of chiller is also acceptable.
HVAC-TS-88
T)
1.0
GENERAL
1.1
Fans shall be of the type, size, arrangement and capacity as indicated in the schedule and/or as
shown on the drawings.
1.2
Unless specified, fan performance rating data shall be tested accordance with AMCA Standard
210-85(Air Moving and Conditioning Association), ANSI/ASHRAE Standard 51-1985 Laboratory
Methods of Testing Fans for Rating. Sound ratings shall conform to AMCA Standard 300-85,
Reverberant Room Method for Sound Testing of Fans.
1.3
A computer printout of fan performance rating corresponding to the AMCA licensed data, with
corrected ratings for altitude and temperature, fan operating speed, bearing life, etc. shall be
submitted for approval.
1.4
All fans shall be dynamically trim-balanced to ISO1940 and AMCA 204/3 - G2.5 quality grade
after assembly. A computer printout with the vibration spectrum analysis shall be attached to
the fans.
1.5
Fan motors shall comply in all respects with continuous rating in accordance with IEC34 or
equivalent. Motor bearings shall be of ball or roller type, grease or lubricant sealed for life. Fan
and drive shall be earthed to prevent accumulation of static charge.
1.6
Kitchen exhaust fan shall be of Bifurcated Axial or SISW Centrifugal direct or belt driven type.
DIDW Centrifugal and Direct Drive Axial Flow Fan where belts or motor are in the air stream are
not acceptable.
1.7
Fans shall be installed at staircase or lobby where fresh air intake is free from any obstruction
and shall be energized only by fire alarm system. Fan shall be of Axial Flow Fan or DIDW
Centrifugal Fan. Protective grille at the suction of the fan is required.
1.8
Fans for elevated temperature (Smoke Extraction Fans) with components rated for high
temperature (250C, 2Hrs) service, with belt drive assemblies exposed to the air stream are not
acceptable.
1.9
For Smoke Extraction Fans where motor is in the air stream with electrical/electronic
temperature limit switch for motor protecting shall not be used.
1.10
Fan should be of G.S.S. , the Steel sheet should be JFE Galvazinc (Base metal cold rolled),
JIS G3302, SGCC with Z22 (minimum coating weight on both sides @ 220 g/m2) zinc coating &
Zero Spangle, skinpassed, chromated and dry.
1.11
If fan is open to atmosphere, Fans shall be with Pure polyester powder coating for minimum
thickness of 60 microns.
2.0
2.1
Fans shall be licensed to bear the AMCA Seal. The test standard used shall be ANSI/AMCA 21085, ANSI/ASHRAE Standard 51-1985 Laboratory Method of Testing Fans for Rating and AMCA
300 Reverberant Room Method for Sound Testing of fans.
2.2
To achieve the minimum and equal clearance between the blade tips and casing, tube casing
shall maintain its roundness by means of using one piece of sheet metal with 90 edge flanging
up.
2.3
Fan motor base support shall be properly secured (locked and sealed) to the fan housing and be
of adjustable type to have precise control of motor shaft central position as well as running
HVAC-TS-89
clearance between blade tips and casing. Motor (KW/HP) shall be able to be changed or
upgraded at site without changing fan housing or ducting construction.
2.4
Fans supplied shall be complete with factory fabricated mounting bracket (ceiling or foot
mounted) and suction/discharge matching flanges as accessories.
2.5
All hubs shall be cast Aluminum alloy (Grade LM2) unless for Smoke Extractor Fans where high
temperature (250C/2Hrs) air is expected then Aluminum alloy or steel fan impeller blades are
required. Otherwise impeller blade material with Polypropylene (PP), Glass-reinforced
Polypropylene (PPG) and Glass-reinforced Polyamid (PAG), to provide self-balancing, anti-static,
anti-sparking characteristic is preferable.
2.6
Running clearance between blade tips and casing shall not exceed 1% of the impeller diameter,
and 2% for smoke spill high temperature fan where mechanical expansion coefficient is
different from normal ambient temperature. Fan manufacturer shall provide the fan assembled
with the dame clearance between blade tips and casing of the tested prototype. Note that the
air performance and pressure loss are greatly affected by this clearance.
2.7
Impellers shall be secured to the drive shaft by a key and keyway. Axial location shall be
provided by a collar or shoulder on the drive shaft together with a retaining washer and screw
fitted into a tapped hole at the end of the shaft and locked in position. Blades shall be secured
in place to the angle setting by setscrews, locking nuts or setting pins.
2.8
Fan motor shall be totally enclosed and external terminal box of at least IP55 shall be provided.
2.9
2.10
All fans after assembly shall be dynamically trim-balanced to ISO1940 and AMCA 204/3 - G2.5
quality grade. A computer printout with vibration spectrum analysis shall be attached to the
fans.
2.11
Fan should be of G.S.S. , the Steel sheet should be JFE Galvazinc (Base metal cold rolled),
JIS G3302, SGCC with Z22 (minimum coating weight on both sides @ 220 g/m2) zinc coating &
Zero Spangle, skinpassed, chromated and dry.
3.0
3.1
3.2
Fan Casing should be provided with Special Designed Integral Straightening Vanes to reduced
turbulence provide high performance & low noise level.
3.3
Fan motor base support shall be properly secured (locked and sealed) to the fan housing and be
of adjustable type to have precise control of motor shaft central position as well as running
clearance between blade tips and casing. Motor (KW/HP) shall be able to be changed or
upgraded at site without changing fan housing or ducting construction.
3.4
3.5
All hubs shall be cast Aluminum alloy (Grade LM2) unless for Smoke Extractor Fans where high
temperature (250C/2Hrs) air is expected then Aluminum alloy or steel fan impeller blades are
required. Otherwise impeller blade material with Polypropylene (PP), Glass-reinforced
(ceiling or foot
HVAC-TS-90
Polypropylene (PPG) and Glass-reinforced Polyamide (PAG), to provide self-balancing, antistatic, anti-sparking characteristic is preferable.
3.6
Impellers shall be secured to the drive shaft by a key and keyway. Axial location shall be
provided by a collar or shoulder on the drive shaft together with a retaining washer and screw
fitted into a tapped hole at the end of the shaft and locked in position. Blades shall be secured
in place to the angle setting by setscrews, locking nuts or setting pins.
3.7
3.8
All fans after assembly shall be dynamically trim-balanced to ISO1940 and AMCA 204/3 - G2.5
quality grade. A computer printout with vibration spectrum analysis shall be attached to the
fans.
The Fan should be AMCA Certified for Air Performance.
3.9
Fan should be of G.S.S. , the Steel sheet should be JFE Galvazinc (Base metal cold rolled),
JIS G3302, SGCC with Z22 (minimum coating weight on both sides @ 220 g/m2) zinc coating &
Zero Spangle, skinpassed, chromated and dry.
4.0
4.1
Smoke and heat exhaust fans are required to be in compliance with the'BSEN12101-3:2002'.
This requires the fan to be subjected to a rated temperature of 250C for a rated duration of 120
minutes.
4.2
The Type test report is to be submitted by fan manufacturer & same clearly indicate the make
of motor used during the testing and the same make/model of motor should be supplied by the
fan manufacture at the site
4.3
4.4
The testing certificate or test report shall be issued by Warrington Fire Research Centre Ltd in
U.K., PSB Singapore or approval equivalent test laboratory.
4.5
4.6
application, each impeller shall be driven by a separate motor within a separate casing.
4.7
Fan should be of G.S.S., the Steel sheet should be JFE Galvazinc (Base metal cold rolled),
JIS G3302, SGCC with Z22 (minimum coating weight on both sides @ 220 g/m2) zinc coating &
Zero Spangle, skinpassed, chromated and dry.
5.0
PROPELLER FAN
5.1
Fans shall be of the ring-mounted type and the blades constructed from heavy gauge metal. An
aerodynamically designed bell mouth constructed from heavy gauge metal shall be provided.
The fan speed shall not exceed 1400RPM at 50Hz operation.
5.2
Propeller fans shall be direct driven type, the motor either a single-phase capacitor start-run or
a three-phase squirrel cage induction type. The motor shall have inbuilt inherent protection
against overloading. Motor with shaded pole or centrifugal switch type is not acceptable.
5.3
Bearings shall be maintenance free permanently lubricated type. Fans shall be complete with
wire guards. External grilles, fan chambers and volume control damper shall be provided where
indicated in the specification drawings.
HVAC-TS-91
6.0
CENTRIFUGAL FANS
6.1
Fans, Aerofoil, forward or backward curved, SISW or DIDW, shall be licensed to bear the AMCA
Air and Sound Certified Ratings Seal. The test standard used shall be ANSI/AMCA 210-85,
ANSI/ASHRAE Standard 51-1985 Laboratory Method of Testing Fans for Rating and AMCA 300
Reverberant Room Method for Sound Testing of fans.
6.2
All fans shall be dynamically trim-balanced to ISO1940 and AMCA 204/3 - G2.5 quality grade
after assembly. A computer printout with vibration spectrum analysis shall be attached to the
fans.
6.3
Fan should be of G.S.S. , the Steel sheet should be JFE Galvazinc (Base metal cold rolled),
JIS G3302, SGCC with Z22 (minimum coating weight on both sides @ 220 g/m2) zinc coating &
Zero Spangle, skinpassed, chromated and dry.
6.4
Fans housing shall be of an appropriate thickness to prevent vibration and drumming. The fan
scroll shall be attached to the side plate by means of continuous lock seam or intermittent spot
welding. The wheel and inlet cone shall be aerodynamically designed and constructed to
provide maximum performance and efficiency as published by the manufacturer.
6.5
Fans must be physically capable of operating safely at every point of rating at or below the
minimum performance limit for that class as defined in AMCA standard 99-2408-69
Performance Class of Operating Limits for Centrifugal Fans.
6.6
Shafts sizes shall be carefully calculated and designed such that the maximum operating speed
(RPM) shall not exceed 75% of the first critical speed. For any application that is not a standard
product from catalogue of the fan manufacturer detailed calculation of critical speed
characteristic shall be submitted for approval.
6.7
Shafts shall be made of carbon steel (C45) machined and polished to tolerance of standard ISO
286-2 - grade g6. Protective coat of anti-rusting shall be applied to all bare surfaces of the shafts
at the factory.
6.8
Bearings shall be of self-alignment (concentric) type with adaptor sleeve bearing. Bearings of
eccentric locking collar with grub screw type are not acceptable. Bearing shall be maintenance
free with permanently lubricated sealed ball bearing type. Bearing life shall be at least 75,000
hours based on basic rating life, L10 of ISO 281 standard. Calculation sheet of Bearing Life shall
be submitted for approval.
6.9
Motor installed shall be of a minimum 130% of the fan power absorbed (Brake horsepower) and
shall have sufficient torque available for starting and continuous operation.
6.10
Belts and pulleys shall be sized for a minimum 150% of the installed motor horsepower. The belt
speed shall not exceed 30m/s. The pulley shall be of Taper Lock SPZ, SPA, SPB or SPC type.
Conventional type of pulley is not acceptable. Both fan and motor pulley shall be balanced to
the quality grade G.2.5.
6.11
Fan outlet velocity shall not exceed 10% of the main duct air velocity designed (0.1 per 100 ft
or 1 Pascal per meter duct length). Pressure Loss is as referred to in SMACNA Standard, unless
otherwise specified.
6.12
Computer printout on fan performance rating corresponding to the AMCA licensed data, with
corrected rating for altitude and temperature, fan operating speed, bearing life, etc. shall be
submitted for approval.
6.13
For Air washer Application, fans should have to coat of Pure polyester powder coating. Fans
should have Inspection door & Drain plug.
HVAC-TS-92
7.0
7.1
Fan shall be of SISW / DIDW, forward or backward curved centrifugal, direct driven type.
7.2
Casing shall be of Galvanized steel with Oven-baked Pure polyester powder coating. Impeller
material shall be either Galvanized Steel or Glass Reinforced Polypropylene.
7.4
7.5
Fan should be of G.S.S. , the Steel sheet should be JFE Galvazinc (Base metal cold rolled),
JIS G3302, SGCC with Z22 (minimum coating weight on both sides @ 220 g/m2) zinc coating &
Zero Spangle, skinpassed, chromated and dry.
U)
1.0
SCOPE
HVAC-TS-93
The scope of this section comprises the supply, erection, testing and commissioning of air
washer conforming to these specifications and in accordance with the requirement of drawings
and schedule of quantities.
2.0
TYPE
The air washers shall be fill type or spray type as indicated on drawings and identified in
Schedule of Quantities.
3.0
CAPACITY
The capacity of air washer shall be as shown on drawings and Schedule of Quantities.
4.0
5.0
HOUSING
Double skinned panels shall be 23 mm thick made of galvanized steel, pressure injected with
foam insulation (density 40 Kg / m3) with K factor not exceeding 0.02 watt / Mc shall be fixed to
1.5 mm thick aluminium alloy twin box section structural framework with stainless steel screws.
Outer sheet of panels shall be made of galvanized preplasticised sheet of 0.8 mm thick, and
inner sheet of 0.8mm thick plain GI sheet.
The entire framework shall be mounted on an aluminium alloy or galvanized steel (depending
on size) channel base as per manufacturers recommendation. The panels shall be sealed to the
frame work by heavy duty O rings gaskets held captive in the framed extrusion. All panels shall
be detachable or hinged. Hinges shall be made of die cast aluminium with stainlees steel pivots,
handles shall be made of hard nylon and be operational from both inside and outside of the
unit. Units supplied with various sections shall be suitable for on site assembly with continuous
foam gasket. All fixing and gaskets shall be concealed.
Units shall have hinged, quick opening access door in the fan section and also in filter section
where filters are not accessible from outside. Access doors shall be double skin type.
Recirculation tank hall be fabricated from 18 gage stainless steel sheet with all corners welded.
The tank shall be complete with double brass strainers, makes-up connection with float, drain
and overflow connections.
6.0
FAN
The blower section shall be constructed out of 16 G GI sheet in folded construction and shall
include Centrifugal Forward Curved DIDW fan wheel of totally GI Construction with Inlet Cones
and shall be 5complete with individual motor and drive and shall be mounted on C Channel
frame and Cushy Foot or Spring Mounts. Each Air-washer system shall comprise of one / two
HVAC-TS-94
nos. fans to handle air quantities as stipulated in BOQ. Each fan shall be driven by suitable HP
TEFC motor. The fan wheel will be of the multiblade type and mounted on two self-aligning
pillow block bearings of the requisite size. The fan shall be run with the help of V Groove
drives as per the recommendation the drive supplier. The blower housing will of the Pittsburgh
joint construction and the drive will be provided by a motor of adequate capacity. The motor
plate will be constructed out of 12 G MS or heavier metal with slotted holes, which permit belt
adjustment in both the directions.
7.0
FILL
Fill shall be of imported cellulose paper pads and of cross fluted configuration assembled in
selfsupporting pads in a light weight construction. The pads shall be able to redistribute the
water and shall be impregnated with insoluble antirot salts, rigidifying saturants and wetting
agents with built in eliminators. The velocity across the fill shall not exceed 350 fpm (1.8 m/s)
and shall not allow carry over of water. Minimum thickness of fill shall be 200 mm and
minimum efficiency of pads 90%.
8.0
WATER DISTRIBUTOR
A FRP distributor shall evenly distribute water on the fill.
9.0
FILTERS
Filters section shall incorporate synthetic washable filtes of at least 50 mm thickness in suitable
aluminium frame. Velocity of air across the filters shall not exceed 500 FPM.
10.0
ELIMINATOR
Eliminator plates shall be four bend made from 24 gauge galvanized sheet steel or PVC.
11.0
INTERCONNECTING PIPES
Air washer shall be complete with interconnecting GI piping from pumps to air washer, valves,
gauges, fittings, strainers etc.
12.0
PUMPS
Specification for recirculation pumps shall be as listed in earlier section of the tender.
13.0
PAINTING
Shop coats of paint that have become marred during shipment or erection shall be cleaned off
with mineral spirits, wire brushed and spot primed over the affected areas, than coated with
paint to match the finish over the adjoining shop painted surface.
14.0
TESTING
Efficiency of air washer shall be computed from the measurements of air flow and dry and wet
bulb temperature of air entering and leaving the air washer and ambient temperatures.
V)
1.0
GENERAL:
HVAC-TS-95
The kitchen Scrubber will be self-contained and will consist of the following component parts
listed in the following paragraph. The entire unit shall be WEATHERPROOFED and CORROSION
PROTECTED as herein after specified. The unit shall be factory fabricated and will include.
2.0
BLOWER SECTION:
The blower section shall be constructed out of 16G GI sheet in folded construction and shall
include Centrifugal forward curved DIDW fan wheel of totally GI construction with inlet cones
and shall be complete with individual motor and drive and shall be mounted C Channel frame
and Cushy Foot or Spring Mounts. The fan shall have a capacity not less than the one specified
in the catalogues and shall be constructed and rated based on delivery against the rated static
pressure with the media and filters in place. The fan will be of riveted construction and made
with GI sheet of required thickness. The fan wheel will be of the multiblade type and mounted
on two self-aligning pillow block bearings of the requisite size. The fan shall be run with the help
of ''groove drives as per the recommendation of the drive supplier. The blower housing will of
the Pittsburg joint construction and the drive will be provided by a motor of adequate capacity.
The motor plate will be constructed out of 12G MS or heavier metal with slotted holes, which
permit belt adjustment in both the direction. The outlet velocity of the blowers will be kept low.
3.0
EVAPORATIVE/SCRUBBER SECTION:
The wet section will have 16G GI tank and body with folded construction with the bolted
openable sides also in 18G SS sheet/FRP. The wet section will contain 50 mm thick rigid media
to act as the first stage of scrubber to be sprayed by water through WIDE ANGLE NOZZLES to
wet, scrub and clean the media installed at the inlet. These nozzles will be provided on a pipe
grid such that the total face of the first bank of rigid media is kept fully wet and also gets
pressure cleaning.
The wet section will have a also have another subsequent layer of 150 mm thick RIGID MEDIA
which will act as the cleaning media for the smoke and smell, these media banks will be
designed @ 2.5 m/s to give 90% adiabatic efficiency. For the second bank 2 mm thick FRP
specially fabricated header will be provided for the water distribution using perforated PVC
piping 15 mm brass bleed off cock alongwith 20 mm heavy duty brass float. PVC drain/overflow
and bleed off outlet are to be provided on all wet sections.
4.0
FILTER SECTION:
All wet sections will include 5 layer 30 micron aluminium wiremesh filters of 50 mm thickness
including the mounting channels in SS 304 16G GI for ease of removal and renewal of filter cells.
The filters to be designed at 2.5 m/s to give 90% efficiency down to 30 microns.
5.0
PUMPS
The unit will have a horizontal single phase 220 Volts + 6% 50 c/s single phase power supply
monoblock self priming pump assembly to provide recirculated tank water and a pressurized
flow via a piping system for proper pad and media water distribution. The pump capacity will be
such that it can take care of the bank of nozzles provided for cleaning the first bank and also
feed water to wet the second bank.
W)
HVAC-TS-96
PAINTING WORK:
All equipment shall be painted as specified under respective headings. Grilles/ diffusers shall be
powder coated as per approved colour matching with interiors. The contractor has to get
approval of the quality and colour of paints for all types of painting work.
All pipes for chilled water shall be painted as per standard code of practice and arrows
indicating direction of flow of water shall be marked.
Colour scheme for the plant and equipment
i. Colour scheme for equipment like chilling unit, pumps, AHUs etc shall be as per
manufacturer's standard colour scheme,
ii. The scheme of colour code painting of pipe work services for air conditioning installation
shall be as per National building code and is indicated below:
Sea Green
Sea Green
Lettering
colour
Black
Black
Sea Green
Black
Pump sets
Battle
White
Light grey or
any
Black
Description
Ground colour
Black
White
White
Black
White with black Black
handles
Belt guard
Black & Yellow
diagonal strips
Machine Bases, Inertia Bases Charcoal
Grey
and Plinth
Black
Steel Support
Ship
iii. Colour bands shall be 150mm wide, superimposed on ground colour to distinguish type
and condition of fluids. The spacing of band shall not exceed 4.0m.
In addition to the colour bands specified above all pipe work shall be legibly marked with black
or white letters to indicate the type of service and the direction of flow identified as follows:-
X)
HVAC-TS-97
MODE OF MEASUREMENT:
The following measurement code shall apply to this contract:-
i.
Ducting
All sheet metal ducting work shall be measured in terms of final sheet area installed in Sq. m.
Eg:- Measurement of 600 mm x 300 mm duct of 1 m length = [(600+300)x2x1] = 1.80 Sq.m.
Duct fittings such as bends, elbows, tap-offs, collars, transformation pieces etc. shall be treated
as ordinary duct pieces with their length measured along their centre line as mentioned in point
(i).
Vanes, splitters, duct dampers, deflectors, access doors, etc. which are required to be installed
in the duct work shall not be measured separately as it shall form part of the duct work.
Duct supports, stiffening members, etc. shall not be measured separately. All such
supports/hangers shall form part of duct work.
Equipment connections such as canvas/asbestos/rexine shall be deemed to be part of the duct
work, and no separate measurement shall be allowed.
No separate special measurement shall be made for bends, transformation pieces, tap offset,
elbows, etc.
Fire dampers - shall be measured by their cross sectional area perpendicular to the direction of
air flow. Quoted rates shall include the necessary collars and flanges for mounting, inspection
pieces with access door, electrical actuators and panel. No special allowance shall be payable
for extension of cross section outside the air stream.
Control panel for Fire/Smoke dampers shall be measured by numbers which shall include FRLS
cable for interconnection of control panel, actuator & AHU panel. No additional payment on
account of FRLS cable shall be made.
ii.
Grilles:
All grills will be measured in terms of effective area in Sq.m.
iii.
Diffusers:
Diffusers will be measured in terms of effective area in Sq.m.
iv.
Ducting Insulation
Ducting insulation will be measured on the basis of centerline of insulation and not the outer
line of insulation.
i)
HVAC-TS-98
b) Insulation item shall include all accessories and finishes as specified. No separate
measurement will be made for such items.
v.
vi.
No separate measurement of insulation shall be made for valves, fittings such as bends,
elbows, reducers, expanders, tees, crosses, flanges, etc. All such insulation shall be linear
in metres measured along the center line of piping.
1. All accessories and finishes connected with insulation work shall be deemed to form part
of insulation, and no separate measurement will be made for such items.
2. No separate measurement of insulation on valves will be made.
vii.
Equipment Insulation:
No separate measurement for insulation of any equipment shall be made. Insulation of
equipment shall be deemed to form part of the equipment. Insulation on equipment shall be
done as per spec. provided.
viii.
Y)
HVAC-TS-99
Foundations
Installation of all equipment including construction of machinery
foundations, positioning of foundation bolts, grouting, etc.. The
contractor has to furnish detailed specifications of foundations and
drawings and the same has to be got approved before proceeding for
foundation erection work. Foundation shall be of RCC 1:1 1/2:3 grade.
2.
Approvals
To obtain necessary statutory approvals from all Govt. local bodies,
agencies, etc., if required. The fee and incidental charges for the same
shall be borne by the contractor. No such payments will be reimbursed by
IIT.
Painting
All exposed metal work furnished under these specifications, except as
otherwise specified shall be painted after installation. Painting shall be
with 2 or more coats of Synthetic enamel of approved brand over a coat of
zinc chromate yellow primer. All exposed chilled water lines should be
painted with the approved colour. Chilled water lines should be painted
with two coats of cement paint of approved make and colour.
Safety of Material
The contractor shall provide proper and adequate storage facilities to
protect all the materials and equipment against damage from any cause
whatsoever. The watch & ward of the stores, equipment & materials shall
be the responsibility of the contractor till the completion, commissioning
& handing over to IIT.
3.
4.
5.
6.
7.
8.
9.
Training to staff
Necessary familiarization shall be given to IIT operating staff for a
minimum period of one month to operate the air-conditioning system.
IIT reserves the right to inspect the materials at factory /site. If inspection
of equipment at the factory is to be done, intimation should be given in
advance. All arrangements for conducting the inspection/ testing at the
factory/ site shall be the responsibility of the contractor.
Supply of wooden/ GI frames for fixing the grilles/ diffusers to the false
ceiling as per requirement.
Openings of walls, slabs, trenches, etc. and making them good thereof to
original finish.
Providing all consumables and hardware such as welding electrodes,
sealing compounds, bolts, nuts, washers, gasket material, cement, bricks,
graded stone, etc.
10.
11.
12.
13.
14.
HVAC-TS-100
15.
The contractor shall take away the balance of any materials left at the site
after commissioning of the system. The cost, if already paid, for such
items shall be deducted from the subsequent running bills. IIT shall not be
liable to pay for any of the incidental charges connected with the above.
16.
17.
All materials, tools and tackles, equipment, labour skilled and semi-skilled
including their housing, sanitation, procurement of food stuff, medical aid
etc. are to be arranged by the contractor. Cost of Transportation of
labour and materials shall be borne by the contractor.
The contractor shall be responsible for any damage resulting from his
negligence to existing facilities /installations and will restore, replace or
repair any such damages at his cost to the complete satisfaction of IIT.
18.
19.
The tenderer has to select the equipment meeting the general/ technical
specifications mentioned in the tender.
20.
The drawings enclosed are for reference only. The tenderer has to check
the exact requirement suitable to the site conditions.
21.
The tenderer has to return the original tender document duly signed and
stamped in all pages.
22.
IIT shall not be responsible for any postal delay in respect of receipt of
tender document, etc. It is the responsibility of the tenderer to make sure
that the tender is received in time.
The contractor shall furnish and install in the machine room a duly typed
set of operating instructions securely framed and shall also supply one set
of tools free of cost required for routine and special maintenance work.
Catalogue /brochure/ technical information with drawings of all
equipment/machinery /item shall also be enclosed along with the Tender.
23.
24.
Z)
HVAC-TS-101
HVAC-TS-102
Air quantity across the filters = Velocity of air across the filter in FPM x Net filter area in
Sq.ft.
The wet bulb temperature of air entering the coil and that leaving the coil shall be
measured. The enthalpy of entering and leaving air shall be noted from psychometric chart,
Corresponding to the WB temperature recorded.
Say,
HVAC-TS-103
AIR BALANCING
After the desired inside conditions are achieved the quantity of air through every outlet shall be
measured:
Air Qty (CFM) = Air velocity at the outlet in FPM x Effective area of the outlet in Sft.
PERFORMANCE TESTING AT VARIOUS LOADING CONDITIONS:
The performance tests shall be conducted for various loads such as 100%, 75%, 50%, and 25%
of the capacity of the plant.
Functional Tests
Electrical Equipment:
1) All the cables shall be tested for continuity and absence of cross phasing. Insulation
resistance between the phase conductors and the earth shall be measured with the help
of a 500 V megger.
2) Motors:
a) Insulation Resistance of all motors shall be tested with megger and the value shall not
be less than 1 Meg-ohm.
b) Starting current shall be recorded.
c) Starter operation shall be checked for single phasing by removing one of the phases.
d) Overload protection shall be checked by altering the starter thermal overload setting.
SAFETY DEVICES & CONTROLS:
a)
b)
c)
d)
e)
f)
g)
Interlocks for compressor motor with that of chilled water pumps shall be checked.
Flow switches in chilled water lines shall be checked.
High pressure-stat shall be checked by varying the setting of the cutout.
Low pressure stat shall be tested by closing the pilot solenoid valve.
Anti-freeze thermostat shall be tested by varying the setting.
Oil failure switch shall only be tested by varying the setting.
Functions of safety device and controls to be checked.
CAPACITY CONTROL:
The capacity control arrangement shall be tested by varying the load on the plant. Any other
procedure recommended by the manufacturers may be adopted with prior permission.
The following readings shall be recorded hourly during the tests and capacity of the plant shall
be computed.
HVAC-TS-104
Compressor
Kg/cm2 (psi)
oC (oF)
a)
Suction pressure
b)
Suction temperature
c)
Discharge pressure
d)
Condensing Tempr.
Kg/cm2 (psi)
oC (oF)
e)
f)
Oil pressure
Compressor Speed
Kg/cm2 (psi)
RPM
Rated capacity
Rated volts
Rated current
Starting current
HP
Volts
Amps
Amps
Amps
Volts
Amps
a)
b)
Kg/cm2 (psi)
oC (oF)
c)
oC (oF)
d)
e)
oC (oF)
lit/sec. (gpm)
a)
b)
c)
Kg/cm2 (psi)
oC (oF)
d)
lit/sec. (gpm)
oC (oF)
e)
oC (oF)
f)
kg/cm2
a)
Air velocity
b)
M/Hr. (FPM)
M2 (SFT)
c)
Air quantity
d)
M3/Hr. (CFM)
oC (oF)
e)
oC (oF)
f)
oC (oF)
g)
oC (oF)
h)
oC (oF)
Compressor motor:
a)
b)
c)
d)
Evaporator
HVAC-TS-105
i)
oC (oF)
j)
k)
l)
Kg/Cm2 (psi)
Kg/Cm2 (psi)
a)
Flow Rate
b)
Discharge pressure
lit/Sec. (gpm)
Kg/Cm2 (psi)
c)
Suction pressure
Kg/Cm2 (psi)
Rated HP
Rated current
Rated volts
Actual current
Starting current
HP
Amps
Volts
Amps
Volts
a)
b)
Area of Grilles
Velocity
c)
d)
Temperature DB
M2 (Sft)
M/Hr (FPM)
- M3 (FPM)
- oC (oF)
e)
Temperature WB
oC (oF)
a)
b)
Area
Velocity
c)
M2 (Sft)
M/Hr (FPM)
M3 (FPM)
d)
Temperature DB
oC (oF)
e)
Temperature WB
oC (oF)
a)
Total area
b)
c)
Effective area
Velocity of air
M2 (Sft)
M2 (Sft)
d)
Quantity of air
lit/sec. (gpm)
Pump motor
a)
b)
c)
d)
e)
Air Grilles
-
Air Diffusers
Filters
M/Hr (FPM)
M3 (CFM)
AA)
HVAC-TS-106
1.
i)
a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
ii)
a)
b)
c)
d)
COMPRESSOR MOTOR :
Motor manufacturer
Type
K W Rating.
Electrical Characteristics (10% voltage
variation)
Motor RPM.
Insulation class.
Enclosure/protection class.
Efficiency.
Starter manufacturer & mode of start.
Starting current (Amps)
Full load current FLA (Amps)
Locked rotor current (Amps)
Type of vibration Isolation for
compressor and motor.
e)
f)
g)
h)
i)
j)
k)
l)
m)
n)
iii)
a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
CONDENSER
Manufacturer (Make) Model
Coil Material
Fin Material
Face Area
Row Deep
Fan CMH
Fan Motor KW
No. of Fans.
Air temperature In/Out (Deg F/Deg C)
ACTUAL capacity of condenser at above
conditions(TR)
iv)
a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
CHILLER
Manufacturer (Make) Model
Shell Material
Tube material
Fouling factor (FPS)
Water Flow (USGPM)
Water velocity (FPS)
Pressure drop (FT of water)
Shell insulation at MFR works Material & Thickness
(mm)
Water temperature, IN/OUT (Deg F/Deg C)
ACTUAL capacity of chiller at above conditions (TR)
v)
a)
b)
HVAC-TS-107
vi)
GENERAL.
a) Original computer printout of machine selection from
manufacturer to be attached with the
b) Offer confirm.
c) Overall Dimension(M)
d) Length
e) Breadth
f) Height
g) Operating weight (kg) / shipping wt.
h) Service clearance required (M) L x B x H.
i) Noise level at 1 M distance.
j) Type of vibration isolators
2.
a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)
m)
n)
o)
p)
q)
r)
s)
t)
u)
HVAC-TS-108
Fan Section.
Manufacturer.
Type of fan
Material and thickness of fan wheel blades
Material and thickness of housing.
Confirm statically and dynamically balanced
Type of bearings.
Fan RPM
HVAC-TS-109
iii)
Motors
a) Manufacturer
b) Type
c) Electrical characteristics (10% voltage
variation)
d) Motor speed (RPM)
e) Motor Efficiency
f) Class of Insulation
iv)
Cooling Coil
a) Manufacturer
b) Material of tubes
c) Material of fins
d) No of fins/ cm.
e) Test pressure.
v)
a)
b)
c)
d)
e)
Air Filters
Manufacturer
Type of filters
Filter medium
Pressure drop across filters (mm. of water) /
Clean & Dirty
Efficiency
vi)
a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)
m)
vii)
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.
HVAC-TS-110
PID Controller
Interface with BAS.
Hormonic filter builtin (Confirm)
Fault Indication.
Dimensions (mm)
No. of Steps
Operating Weight
4. AIR WASHER
i)
General
a) Manufacturer
b) Model
c) Type of unit (Double/Single skin) (drawthru/blow thru)
d) Material and thickness of casing (inner/outer)
e) Material and thickness of drain pan.
f) Material and thickness of sandwiched
insulation for drain pan
g) Type of flexible connection
h) Type of vibration isolator
ii)
a)
b)
c)
d)
e)
f)
g)
Fan Section.
Manufacturer.
Type of fan
Material and thickness of fan wheel blades
Material and thickness of housing.
Confirm statically and dynamically balanced
Type of bearings.
Fan RPM
iii)
Motors
a) Manufacturer
b) Type
c) Electrical characteristics (10% voltage
variation)
d) Motor speed (RPM)
e) Motor Efficiency
f) Class of Insulation
iv)
FILLS
a) Manufacturer
b) Fill Type
c) Fill Thickness
v)
a)
b)
c)
d)
e)
Air Filters
Manufacturer
Type of filters
Filter medium
Pressure drop across filters (mm. of water) /
Clean & Dirty
Efficiency
vi)
a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)
Pumps
Manufacturer
Model
Type
Capacity (USGPM) / (LPM)
Head (M-Wg)
Efficiency (%)
Pump (RPM)
B.H.P
Motor (KW)
Motor make.
Motor efficiency
Class of insulation.
HVAC-TS-111
1.5
2.5
a)
b)
c)
Manufacturer
Model Type
Actual Capacity (TR) at
HI Speed.
MED Speed
LO speed.
d) Actual Air Quantity (CFM) at
HI Speed.
MED Speed
LO speed.
e) Coil detail
face area (m2)
CHILLED WATER IN/OUT TEMP
AIR LEAVING TEMP AT COIL
f) Unit size : L mm
W mm
H mm
g) Material/Gage
Casing
Blowers
h)
i)
j)
k)
l)
m)
n)
HVAC-TS-112
6. FAN SECTION
i)
a.
b.
c.
d.
e.
f.
g.
General
Manufacturer.
Type of fan
Material and thickness of fan wheel blades
Material and thickness of housing.
Confirm statically and dynamically balanced
Type of bearings.
Fan RPM
ii)
a.
b.
c.
d.
e.
f.
MOTORS
Manufacturer
Type
Electrical characteristics (10% voltage variation)
Motor speed (RPM)
Motor Efficiency
Class of Insulation
iii)
a.
b.
c.
d.
AIR FILTERS
Manufacturer
Type of filters
Filter medium
Pressure drop across filters (mm. of water) / Clean
& Dirty
e. Efficiency
HVAC-TS-113
HVAC-TS-114
8. INLINE FANS
a. Manufactures Name :
b. Capacity CMH :
c. Static Pressure :
d. Motor BHP & HP :
e. Fan Diameter mm :
9. PROPELLER FANS/ROOF EXTRACTORS
a) Manufacturer
b) Motor HP
c) Capacitors provided.
d) Speed Regulator
e) Gravity louvers
f) Single phase preventor
g) Back draft damper.
h) Bird Screen
i) Wire guard
10. CONTROLS
i) 2 Way Valve AHUs FCUs
a) Make of valve
b) Model
c) Type (Modulating/Diverting)
d) Modulating Motor make
e) Model
f) Spring return function
g) Pressure rating
h) Voltage of motor
i) Transformer provided
j) Valve linkage make and model.
ii) Thermostat
a) Make / Type
b) Model
c) Cooling/heating or cooling only
d) Range
e) Differential
f) Electrical characteristics
11. WATER PIPING
Item
a. Make of pipes / class of pipes
b. Pipe Wall thickness
c. Valves
Make
Material
HVAC-TS-115
Butterfly valves
Gate valve
Globe valve
Check valve
Ball valve
Ball valve with strainer
Balancing valve
Pot Strainer
Y-Strainer
d. Pressure Gauge
Make
Range
Dial Size
e. Thermometer (Make/Type &
Range)
f. Flow Meter
Type and Make
Size of flow meter
g. Make of Manometer
Make
Material
Make
14. INSULATION
Item
a) Duct acoustic lining
b) Duct insulation
c) Pipe insulation
Make
HVAC-TS-116
II)
HVAC-TS-117
PART I: GENERAL:
1.0
SUMMARY:
Furnish all labor, materials, equipment, and service necessary for a complete and operating
Building Management System (BMS), utilizing Direct Digital Controls as shown on the drawings,
as in attached Input/Output Summary and as described herein. Drawings are diagrammatic
only.
All labor, material, equipment and software not specifically referred to herein or on the plans,
that is required to meet the functional intent of this specification, shall be provided without
additional cost to the Client.
Client shall be the named license holder of all software associated with any and all incremental
work on the project(s).
2.0
SYSTEM DESCRIPTION:
The entire Building Management System (BMS) shall be comprised of a network of
interoperable, stand-alone digital controllers communicating via LonMark / LonTalk
communication protocols to a Network Area Controller (NAC) / Router. Building Management
System products shall be manufactured as per LonWorks products must be approved in writing
by the consulting Engineer and be submitted for approval ten (10) days prior to the date of the
bid submittal.
The entire Integrated Control and Monitor Management System (IBMS) shall be comprise of a
network of interoperable, stand-alone digital controllers communicating on an open protocol
communication network to a host computer within the facility (when specified) and
communicating via the Internet to a host computer in a remote location. The IBMS shall
communicate to third party systems such as Chillers, Boilers, Air-Handling Systems, Energy
metering systems, Lighting Management System & other energy management systems, Fire-Life
safety systems and other building management related devices with open, interoperable
communication capabilities.
The IBMS framework shall utilize JAVA based automation products and services with built-in
Internet connectivity to a broad range of distribution partners in the building automation,
energy services, power/utility, and industrial sectors. The Framework shall bring together the
computerization of control applications under the umbrella of single integrated system
architecture. The suite of component software applications shall support true plug-and-play,
multi-vendor interoperability, resulting in lower automation and information infrastructure
costs. The Network Area Controllers (NACs) shall run a JAVA Virtual Machine (JVM) platform
and use a common set of tools for accessing and integrating multiple protocols.
The Building Management System (BMS) shall be comprised of Network Area Controller or
Controllers (NAC) / Routers. The NAC / Router shall connect to the local or wide area network,
depending on configuration. Access to the system, either locally in each building, or remotely
from a central site or sites, shall be accomplished through standard Web browsers, via the
HVAC-TS-118
Internet and/or local area network. Each NAC shall communicate to LonMark/LonTalk and/or
BACnet Direct Digital Controllers (DDC) and other open protocol systems/devices.
The following software packages shall be loaded into the system as minimum standard :a)
b)
c)
d)
e)
f)
g)
3.0
SUBMITTAL
Eight copies of shop drawings of the components and devices for the entire control system shall
be submitted and shall consist of a complete list of equipment and materials, including
manufacturers catalog data sheets and installation instructions for all controllers, valves,
dampers, sensors, routers, etc. Shop drawings shall also contain complete wiring and schematic
diagrams, software descriptions, calculations, and any other details required to demonstrate
that the system has been coordinated and will properly function as a system. Terminal
identification for all control wiring shall be shown on the shop drawings. A complete written
Sequence of Operation shall also be included with the submittal package. BMS contractors
supplying products and systems, as part of their packages shall provide catalog data sheets,
wiring diagrams and point lists to other contractors for proper coordination of work.
Submittal shall also include a trunk cable schematic diagram depicting operator workstations,
control panel locations and a description of the communication type, media and protocol. BMS
contractors shall provide these diagrams for their portions of work; the Systems Integrator shall
be responsible for integrating those diagrams into the overall trunk cable schematic diagrams
for the entire Wide Area Network (WAN).
Submittal shall also include a complete point list of all points to be connected to the BMS.
Upon completion of the work, provide a complete set of as-built drawings and application
software on compact disk. Drawings shall be provided as AutoCAD compatible files. Eight
copies of the as-built drawings shall be provided in addition to the documents on compact
disk. BMS contractors shall provide as-built for their portions of work. The BMS contractor shall
be responsible for as-built pertaining to overall BMS architecture and network diagrams. All asbuilt drawings shall also be installed into the BMS server in a dedicated directory.
4.0
SPECIFICATION NOMENCLATURE
Acronyms used in this specification are as follows:
FMCS Facility Management and Control System
BMS Building Management System
NAC
Network Area Controller
DDC
Direct Digital Controller
IBC
Interoperable BACnet Controller
GUI
Graphical User Interface
WBI
Web Browser Interface
PMI
Power Measurement Interface
LAN
WAN
OOT
PICS
5.0
HVAC-TS-119
DIVISION OF WORK
The BMS contractor shall be responsible for all controllers (DDC), control devices, control
panels, controller programming, controller programming software, controller input/output and
power wiring and controller network wiring.
The BMS contractor shall also be responsible for the Network Area Controller(s) (NAC), software
and programming of the NAC, graphical user interface software (GUI), development of all
graphical screens, Web browser pages, setup of schedules, logs and alarms, LonWorks network
management and connection of the NAC to the local or wide area network.
6.0
7.0
8.0
9.0
HVAC-TS-120
JOB CONDITIONS
Cooperation with Other Contractors: Coordinate the Work of this section with that of other
sections to ensure that the Work will be carried out in an orderly fashion. It shall be this
Contractor's responsibility to check the Contract Documents for possible conflicts between his
Work and that of other crafts in equipment location, pipe, duct and conduit runs, electrical
outlets and fixtures, air diffusers, and structural and architectural features.
HVAC-TS-121
GENERAL:
The Building Management System (BMS) shall be comprised of a network of interoperable,
stand-alone digital controllers, a computer system, graphical user interface software, printers,
network devices, valves, dampers, sensors, and other devices as specified herein. All systems
and software within BMS shall be Year 2000 compliant and shall be supported by compliance
documentation from the manufacturer.
The installed system shall provide secure password access to all features, functions and data
contained in the overall BMS.
2.0
HVAC-TS-122
2) Maximum acceptable response time from any alarm occurrence (at the point of origin) to
the point of annunciation shall not exceed 60 seconds for remote or dial-up connected user
interfaces.
3.0
NETWORKS
The Local Area Network (LAN) shall be a 100 Megabits/sec Ethernet network supporting
BACnet, Java, XML, HTTP, and SOAP for maximum flexibility for integration of building data with
enterprise information systems and providing support for multiple Network Area Controllers
(NACs), user workstations and, if specified, a local server.
Local area network minimum physical and media access requirements:
1) Ethernet; IEEE standard 802.3
2) Cable; 100 Base-T, UTP-8 wire, category 5
3) Minimum throughput; 100 Mbps.
4.0
NETWORK ACCESS
Remote Access.
For Local Area Network installations, provide access to the LAN from a remote location, via the
Internet. The CLIENT shall provide a connection to the Internet to enable this access via high
speed cable modem, asynchronous digital subscriber line (ADSL) modem, ISDN line, T1 Line or
via the customers Intranet to a corporate server providing access to an Internet Service
Provider (ISP). Customer agrees to pay monthly access charges for connection and ISP.
5.0
HVAC-TS-123
HVAC-TS-124
2) Email of the complete alarm message to multiple recipients. Provide the ability to route
and email alarms based on:
a) Day of week
b) Time of day
c) Recipient
3) Pagers via paging services that initiate a page on receipt of email message
4) Graphic with flashing alarm object(s)
5) Printed message, routed directly to a dedicated alarm printer
The following shall be recorded by the NAC / Router for each alarm (at a minimum):
1) Time and date
2) Location (building, floor, zone, office number, etc.)
3) Equipment (air handler #, accessway, etc.)
4) Acknowledge time, date, and user who issued acknowledgement.
5) Number of occurrences since last acknowledgement.
Alarm actions may be initiated by user defined programmable objects created for that
purpose.
Defined users shall be given proper access to acknowledge any alarm, or specific types or
classes of alarms defined by the user.
A log of all alarms shall be maintained by the NAC / Router and/or a server (if configured in
the system) and shall be available for review by the user.
Provide a query feature to allow review of specific alarms by user defined parameters.
A separate log for system alerts (controller failures, network failures, etc.) shall be provided
and available for review by the user.
An Error Log to record invalid property changes or commands shall be provided and
available for review by the user.
6.0
HVAC-TS-125
4) For all logs, provide the ability to set the maximum number of data stores for the log
and to set whether the log will stop collecting when full, or rollover the data on a firstin, first-out basis.
5) Each log shall have the ability to have its data cleared on a time-based event or by a
user-defined event or action.
All log data shall be stored in a relational database in the NAC / Router and the data shall be
accessed from a server (if the system is so configured) or a standard Web browser.
All log data, when accessed from a server, shall be capable of being manipulated using standard
SQL statements.
All log data shall be available to the user in the following data formats:
1) HTML
2) XML
3) Plain Text
4) Comma or tab separated values
Systems that do not provide log data in HTML and XML formats at a minimum shall not be
acceptable.
The NAC / Router shall have the ability to archive its log data either locally (to itself), or
remotely to a server or other NAC / Router on the network. Provide the ability to configure the
following archiving properties, at a minimum:
1) Archive on time of day
2) Archive on user-defined number of data stores in the log (buffer size)
3) Archive when log has reached its user-defined capacity of data stores
4) Provide ability to clear logs once archived
7.0
AUDIT LOG
Provide and maintain an Audit Log that tracks all activities performed on the NAC / Router.
Provide the ability to specify a buffer size for the log and the ability to archive log based on time
or when the log has reached its user-defined buffer size. Provide the ability to archive the log
locally (to the NAC / Router), to another NAC / Router on the network, or to a server. For each
log entry, provide the following data:
1) Time and date
2) User ID
3) Change or activity: i.e., Change setpoint, add or delete objects, commands, etc.
8.0
HVAC-TS-126
The NAC / Router database shall be stored, at a minimum, in XML format to allow for user
viewing and editing, if desired. Other formats are acceptable as well, as long as XML format is
supported.
9.0
HVAC-TS-127
The controller shall have an internal time clock with the ability to automatically revert from a
master time clock on failure.
1) Operating Range: 24 hour, 365 day, multi-year calendar including day of week and
configuration for automatic day-light savings time adjustment to occur on configured
start and stop dates.
2) Accuracy: 1 minute per month at 77 F (25 C).
3) Power Failure Backup: 24 hours at 32 to 122 F (0 to 50 C).
The controller shall have Significant Event Notification, Periodic Update capability, and Failure
Detect when network inputs fail to be detected within their configurable time frame.
Rated voltage: 20-30 VAC, 50/60 Hz
The controller shall have an internal DC power supply to power external sensors.
a) Power Output: 20 VDC 10% at 75 mA.
The controller shall have a visual indication (LED) of the status of the device:
a) Controller operating normally.
b) Controller in process of download.
c) Controller in manual mode under control of software tool.
d) Controller lost its configuration.
e) No power to controller, low voltage, or controller damage.
f)
The controller shall have the additional approval requirements, listings, and approvals:
a) UL/cUL (E87741) listed under UL916 (Standard for Open Energy Management
Equipment) with plenum rating.
b) CSA (LR95329-3) Listed
c) Meets FCC Part 15, Subpart B, Class B (radiated emissions) requirements.
d) Meets Canadian standard C108.8 (radiated emissions).
e) Conforms requirements European Consortium standard EN 61000-6-1; 2001 (EU
Immunity)
f)
HVAC-TS-128
The controller shall provide for user defined Network Variables (NV) for customized
configurations.
10.0
2) Graphic screens shall have the capability to contain objects for text, real-time values,
animation, color spectrum objects, logs, graphs, HTML or XML document links, schedule
objects, hyperlinks to other URLs, and links to other graphic screens.
3) Graphics shall support layering and each graphic object shall be configurable for assignment
to a layer. A minimum of six layers shall be supported.
4) Modifying common application objects, such as schedules, calendars, and set points shall
be accomplished in a graphical manner.
a. Schedule times will be adjusted using a graphical slider, without requiring any keyboard
entry from the operator.
b. Holidays shall be set by using a graphical calendar without requiring any keyboard entry
from the operator.
HVAC-TS-129
5) Commands to start and stop binary objects shall be done by right-clicking the selected
object and selecting the appropriate command from the pop-up menu. No entry of text
shall be required.
6) Adjustments to analog objects, such as set points, shall be done by right-clicking the
selected object and using a graphical slider to adjust the value. No entry of text shall be
required.
System Configuration. At a minimum, the GUI shall permit the operator to perform the
following tasks, with proper password access:
1) Create, delete or modify control strategies.
2) Add/delete objects to the system.
3) Tune control loops through the adjustment of control loop parameters.
4) Enable or disable control strategies.
5) Generate hard copy records or control strategies on a printer.
6) Select points to be alarmable and define the alarm state.
7) Select points to be trended over a period of time and initiate the recording of values
automatically.
On-Line Help : Provide a context sensitive, on-line help system to assist the operator in
operation and editing of the system. On-line help shall be available for all applications and shall
provide the relevant data for that particular screen. Additional help information shall be
available through the use of hypertext. All system documentation and help files shall be in
HTML format.
Security : Each operator shall be required to log on to that system with a user name and
password in order to view, edit, add, or delete data. System security shall be selectable for
each operator. The system administrator shall have the ability to set passwords and security
levels for all other operators. Each operator password shall be able to restrict the operators
access for viewing and/or changing each system application, full screen editor, and object. Each
operator shall automatically be logged off of the system if no keyboard or mouse activity is
detected. This auto log-off time shall be set per operator password. All system security data
shall be stored in an encrypted format.
System Diagnostics : The system shall automatically monitor the operation of all workstations,
printers, modems, network connections, building management panels, and controllers. The
failure of any device shall be annunciated to the operator.
Programming software shall be same as GUI. The Same GUI can be used to configure the DDCs
& NAC.
Alarm Console
1) The system will be provided with a dedicated alarm window or console. This window
will notify the operator of an alarm condition, and allow the operator to view details of
the alarm and acknowledge the alarm. The use of the Alarm Console can be enabled or
disabled by the system administrator.
HVAC-TS-130
2) When the Alarm Console is enabled, a separate alarm notification window will
supercede all other windows on the desktop and shall not be capable of being
minimized or closed by the operator. This window will notify the operator of new
alarms and un-acknowledged alarms. Alarm notification windows or banners that can
be minimized or closed by the operator shall not be acceptable.
11.0
HVAC-TS-131
2. Summary Ranking Reports - By selecting this report, the user can identify the 10 worst or
10 best sites in the database. Once the report type has been selected, parameters to define
before the report can be generated will include the following:
a. Measurement unit KW, therms, CCF gallons, PSI, etc. The database will search for
all values matching the request.
b. Compare an entire facility or normalize by square foot
c. Time periods to compare
d. Highest values or lowest values Will be able to view either the best or worst 10
points matching the defined parameters
e. Cost or consumption in future revisions
3. Spectrum Summary Report A quick view of any point or aggregated point with color
coding identifying the reasonableness of the data value. The chart can report on up to one
year of data, with the ability to zoom to a higher definition. As data values approach and/or
exceed historical ranges, the color on the graph will change to identify such. If all data
values are within historical ranges, the user can move on to other functions. In the
following screen shot, the Spectrum Summary Report is reporting on total electricity for an
aggregated point, which consists of 6 schools. The reporting period is six weeks, with the
blue identifying low loads overnight and on weekends. The fourth weekend in the report
was a three day weekend which is identified by a larger blue gap. A user can also see rising
consumption (red) as temperatures rise going into the summer season. When the user
clicks on an area of the graph, the data value along with time stamp will appear. The colors
and associated data value ranges are user definable. The following screen shot is an
example of the Spectrum Summary Report.
HVAC-TS-132
4. Equipment Operation Reports - Users will have the ability to analyze digital points and
identify run times. Comparisons between sites or points can be made and run times can be
graphed. For example, comparing lighting or HVAC run hours in a group of stores or
comparing HVAC run hours in June for Store 1 versus Store 2. Data will be displayed in time
and percentage.
5. Relative Contribution Report This pie chart report will give users the ability to identify
how individual points contribute to a total from a point group. The user would select a
group of points, calculate the aggregate consumption of the group, and report on the
individual contribution of each. Data will be displayed both graphically in a pie chart as well
as in tabular format. Users could identify that HVAC is 48% of the building load; lighting is
42%, or Building 1 accounts for 14% of the total enterprise load and Building 2 contributes
19%. This report will allow users to identify inefficiencies and help perform budgeting.
HVAC-TS-133
6. Average Profile The report will allow the user to average the load for a single load across
time periods and give the average load, and/or aggregate multiple meters (loads) and view
the average aggregated load. This report will be very beneficial when negotiating with
energy service providers because it includes the load profile and consumption totals. With
the ability to filter by time periods, measurement units, points or point groups, weekdays,
and weekends, load profiles with associated data will allow the user to procure exactly the
amount of energy required. This reduces risk for the energy provider and therefore reduces
cost for the end-user.
The user will be able to manipulate between 1-minute intervals and hourly intervals. In addition,
users will be able to choose between auto scale and manual scale. For example, if the minimum
value is 100KW and the maximum is 500 kW, the user can have the chart automatically scale
between those values or they can select any range to scale the 400kW range. When printing charts,
this may be useful. This will be useful for sophisticated users who need a higher resolution of data.
The following screen shot is an example of the Average Profile Report.
7. Point Trending This report will allow the user to choose a single or multiple points and
trend the values over a specified time period. Either analog or digital points can be trended
and multiple variables can be selected to be report. For a visual representation of several
point values, the user will view all points on the left Y-axis. If the user would like to perform
a statistical analysis identifying correlation coefficient and standard deviation between
variables, they will have the ability to select a single point for each Y-axis. If a point group
has been created, it would be presented as a single point value. The same auto
scale/manual scale feature discussed in Average Profile Report is available in Point
Trending. The following screen shot is an example of the Point Trending Report.
HVAC-TS-134
8. Exception Report This report will identify all data values for the specified period that does
not fall in a user-defined range. Although the range will be user definable, the benchmark
or baseline to be compared against will be historical data. Users can get to this report by
selecting it among the library of report templates, or can automatically be taken here from
the Average Profile Report or Point Trending Report by clicking on an Exception button
once a profile is being viewed.
12.0
HVAC-TS-135
The Web browser software shall run on any operating system and system configuration that is
supported by the Web browser. Systems that require specific machine requirements in terms
of processor speed, memory, etc., in order to allow the Web browser to function with the
FMCS, shall not be acceptable.
The Web browser shall provide the same view of the system, in terms of graphics, schedules,
calendars, logs, etc., and provide the same interface methodology as is provided by the
Graphical User Interface. Systems that require different views or that require different means
of interacting with objects such as schedules, or logs, shall not be permitted.
The Web browser client shall support at a minimum, the following functions:
1) User log-on identification and password shall be required. If an unauthorized user
attempts access, a blank web page shall be displayed. Security using Java authentication
and encryption techniques to prevent unauthorized access shall be implemented.
2) Graphical screens developed for the GUI shall be the same screens used for the Web
browser client. Any animated graphical objects supported by the GUI shall be supported
by the Web browser interface.
3) HTML programming shall not be required to display system graphics or data on a Web
page. HTML editing of the Web page shall be allowed if the user desires a specific look or
format.
4) Storage of the graphical screens shall be in the Network Area Controller (NAC), without
requiring any graphics to be stored on the client machine. Systems that require graphics
storage on each client are not acceptable.
5) Real-time values displayed on a Web page shall update automatically without requiring a
manual refresh of the Web page.
6) Users shall have administrator-defined access privileges. Depending on the access
privileges assigned, the user shall be able to perform the following:
a. Modify common application objects, such as schedules, calendars, and set points in a
graphical manner.
i. Schedule times will be adjusted using a graphical slider, without requiring any
keyboard entry from the operator.
ii. Holidays shall be set by using a graphical calendar, without requiring any keyboard
entry from the operator.
b. Commands to start and stop binary objects shall be done by right-clicking the selected
object and selecting the appropriate command from the pop-up menu. No entry of
text shall be required.
c. View logs and charts
d. View and acknowledge alarms
e. Setup and execute SQL queries on log and archive information
7) The system shall provide the capability to specify a users (as determined by the log-on
user identification) home page. Provide the ability to limit a specific user to just their
defined home page. From the home page, links to other views, or pages in the system
shall be possible, if allowed by the system administrator.
8) Graphic screens on the Web Browser client shall support hypertext links to other
locations on the Internet or on Intranet sites, by specifying the Uniform Resource Locator
(URL) for the desired link.
13.0
HVAC-TS-136
HVAC-TS-137
Server Hardware Requirements: The server hardware platform shall have the following
requirements:
1) The computer shall be an Intel Pentium M based computer (minimum processing speed of
2.4 GHz with 1 GB RAM and a 100-gigabyte minimum hard drive). It shall include a DVDROM/CD-RW Combination Drive, 2-parallel ports, 2-asynchronous serial ports and 2-USB
ports. A minimum 17 flat panel color monitor, 1280 x 1024 optimal preset resolution, 25
ms response time shall also be included.
2) The server operating system shall be Microsoft Windows XP Professional.
Microsoft Internet Explorer 6.0 or later.
Include
3) Connection to the BMS network shall be via an Ethernet network interface card, 100
Mbps.
4) A system printer shall be provided. Printer shall be laser type with a minimum 600 x 600dpi resolution and rated for 60-PPM print speed minimum.
5) For dedicated alarm printing, provide a dot matrix printer, either 80 or 132 column width.
The printer shall have a parallel port interface.
14.0
SYSTEM PROGRAMMING
The Graphical User Interface software (GUI) shall provide the ability to perform system
programming and graphic display engineering as part of a complete software package. Access
to the programming functions and features of the GUI shall be through password access as
assigned by the system administrator.
A library of control, application, and graphic objects shall be provided to enable the creation of
all applications and user interface screens. Applications are to be created by selecting the
desired control objects from the library, dragging or pasting them on the screen, and linking
them together using a built in graphical connection tool. Completed applications may be stored
in the library for future use. Graphical User Interface screens shall be created in the same
fashion. Data for the user displays is obtained by graphically linking the user display objects to
the application objects to provide real-time data updates. Any real-time data value or object
property may be connected to display its current value on a user display. Systems requiring
separate software tools or processes to create applications and user interface displays shall not
be acceptable.
Programming Methods
1) Provide the capability to copy objects from the supplied libraries, or from a user-defined
library to the users application. Objects shall be linked by a graphical linking scheme by
dragging a link from one object to another. Object links will support one-to-one, many-toone, or one-to-many relationships. Linked objects shall maintain their connections to
other objects regardless of where they are positioned on the page and shall show link
identification for links to objects on other pages for easy identification. Links will vary in
color depending on the type of link; i.e., internal, external, hardware, etc.
2) Configuration of each object will be done through the objects property sheet using fill-in
the blank fields, list boxes, and selection buttons. Use of custom programming, scripting
language, or a manufacturer-specific procedural language for configuration will not be
accepted.
3) The software shall provide the ability to view the logic in a monitor mode. When on-line,
the monitor mode shall provide the ability to view the logic in real time for easy diagnosis
HVAC-TS-138
of the logic execution. When off-line (debug), the monitor mode shall allow the user to set
values to inputs and monitor the logic for diagnosing execution before it is applied to the
system.
4) All programming shall be done in real-time. Systems requiring the uploading, editing, and
downloading of database objects shall not be allowed.
5) The system shall support object duplication within a customers database. An application,
once configured, can be copied and pasted for easy re-use and duplication. All links, other
than to the hardware, shall be maintained during duplication.
15.0
16.0
OBJECT LIBRARIES
A standard library of objects shall be included for development and setup of application logic,
user interface displays, system services, and communication networks.
The objects in this library shall be capable of being copied and pasted into the users database
and shall be organized according to their function. In addition, the user shall have the capability
to group objects created in their application and store the new instances of these objects in a
user-defined library.
In addition to the standard libraries specified here, the supplier of the system shall maintain an
on-line accessible (over the Internet) library, available to all registered users to provide new or
updated objects and applications as they are developed.
All control objects shall conform to the control objects specified in the BACnet specification.
The library shall include applications or objects for the following functions, at a minimum:
1) Scheduling Object- The schedule must conform to the schedule object as defined in the
BACnet specification, providing 7-day plus holiday & temporary scheduling features and a
HVAC-TS-139
minimum of 10 on/off events per day. Data entry to be by graphical sliders to speed
creation and selection of on-off events.
2) Calendar Object- The calendar must conform to the calendar object as defined in the
BACnet specification, providing 12-month calendar features to allow for holiday or special
event data entry. Data entry to be by graphical point-and-click selection. This object must
be linkable to any or all scheduling objects for effective event control.
3) Duty Cycling Object- Provide a universal duty cycle object to allow repetitive on/off time
control of equipment as an energy conserving measure. Any number of these objects may
be created to control equipment at varying intervals
4) Temperature Override Object- Provide a temperature override object that is capable of
overriding equipment turned off by other energy saving programs (scheduling, duty cycling
etc.) to maintain occupant comfort or for equipment freeze protection.
5) Start-Stop Time Optimization Object- Provide a start-stop time optimization object to
provide the capability of starting equipment just early enough to bring space conditions to
desired conditions by the scheduled occupancy time. Also, allow equipment to be stopped
before the scheduled un-occupancy time just far enough ahead to take advantage of the
buildings flywheel effect for energy savings. Provide automatic tuning of all start / stop
time object properties based on the previous days performance.
6) Demand Limiting Object- Provide a comprehensive demand-limiting object that is capable
of controlling demand for any selected energy utility (electric, oil, and gas). The object shall
provide the capability of monitoring a demand value and predicting (by use of a sliding
window prediction algorithm) the demand at the end of the user defined interval period (160 minutes). This object shall also accommodate a utility meter time sync pulse for fixed
interval demand control. Upon a prediction that will exceed the user defined demand limit
(supply a minimum of 6 per day), the demand limiting object shall issue shed commands to
either turn off user specified loads or modify equipment set points to effect the desired
energy reduction. If the list of sheddable equipment is not enough to reduce the demand
to below the set point, a message shall be displayed on the users screen (as an alarm)
instructing the user to take manual actions to maintain the desired demand. The shed lists
are specified by the user and shall be selectable to be shed in either a fixed or rotating
order to control which equipment is shed the most often. Upon suitable reductions in
demand, the demand-limiting object shall restore the equipment that was shed in the
reverse order in which it was shed. Each sheddable object shall have a minimum and
maximum shed time property to effect both equipment protection and occupant comfort.
The library shall include control objects for the following functions. All control objects shall
conform to the objects as specified in the BACnet specification.
1) Analog Input Object - Minimum requirement is to comply with the BACnet standard for
data sharing. Allow high, low and failure limits to be assigned for alarming. Also, provide a
time delay filter property to prevent nuisance alarms caused by temporary excursions
above or below the user defined alarm limits.
2) Analog Output Object - Minimum requirement is to comply with the BACnet standard for
data sharing.
3) Binary Input Object - Minimum requirement is to comply with the BACnet standard for data
sharing. The user must be able to specify either input condition for alarming. This object
must also include the capability to record equipment run-time by counting the amount of
time the hardware input is in an on condition. The user must be able to specify either
input condition as the on condition.
HVAC-TS-140
4) Binary Output Object - Minimum requirement is to comply with the BACnet standard for
data sharing. Properties to enable minimum on and off times for equipment protection as
well as interstart delay must be provided. The BACnet Command Prioritization priority
scheme shall be incorporated to allow multiple control applications to execute commands
on this object with the highest priority command being invoked. Provide sixteen levels of
priority as a minimum. Systems not employing the BACnet method of contention resolution
shall not be acceptable.
5) PID Control Loop Object - Minimum requirement is to comply with the BACnet standard for
data sharing. Each individual property must be adjustable as well as to be disabled to allow
proportional control only, or proportional with integral control, as well as proportional,
integral and derivative control.
6) Comparison Object - Allow a minimum of two analog objects to be compared to select
either the highest, lowest, or equality between the two linked inputs. Also, allow limits to
be applied to the output value for alarm generation.
7) Math Object - Allow a minimum of four analog objects to be tested for the minimum or
maximum, or the sum, difference, or average of linked objects. Also, allow limits to be
applied to the output value for alarm generation.
8) Custom Programming Objects - Provide a blank object template for the creation of new
custom objects to meet specific user application requirements. This object must provide a
simple BASIC-like programming language that is used to define object behavior. Provide a
library of functions including math and logic functions, string manipulation, and e-mail as a
minimum. Also, provide a comprehensive on-line debug tool to allow complete testing of
the new object. Allow new objects to be stored in the library for re-use.
9) Interlock Object - Provide an interlock object that provides a means of coordination of
objects within a piece of equipment such as an Air Handler or other similar types of
equipment. An example is to link the return fan to the supply fan such that when the supply
fan is started, the return fan object is also started automatically without the user having to
issue separate commands or to link each object to a schedule object. In addition, the
control loops, damper objects, and alarm monitoring (such as return air, supply air, and
mixed air temperature objects) will be inhibited from alarming during a user-defined period
after startup to allow for stabilization. When the air handler is stopped, the interlocked
return fan is also stopped, the outside air damper is closed, and other related objects within
the air handler unit are inhibited from alarming thereby eliminating nuisance alarms during
the off period.
10) Temperature Override Object - Provide an object whose purpose is to provide the capability
of overriding a binary output to an On state in the event a user specified high or low limit
value is exceeded. This object is to be linked to the desired binary output object as well as
to an analog object for temperature monitoring, to cause the override to be enabled. This
object will execute a Start command at the Temperature Override level of start/stop
command priority unless changed by the user.
11) Composite Object - Provide a container object that allows a collection of objects
representing an application to be encapsulated to protect the application from tampering,
or to more easily represent large applications. This object must have the ability to allow the
user to select the appropriate parameters of the contained application that are
represented on the graphical shell of this container.
The object library shall include objects to support the integration of devices connected to the
Network Area Controller (NAC) / Router. At a minimum, provide the following as part of the
standard library included with the programming software:
HVAC-TS-141
1) LonMark/LonWorks devices. These devices shall include, but not be limited to, devices for
control of HVAC, lighting, access, and metering. Provide LonMark manufacturer-specific
objects to facilitate simple integration of these devices. All network variables defined in the
LonMark profile shall be supported. Information (type and function) regarding network
variables not defined in the LonMark profile shall be provided by the device manufacturer.
2) For devices not conforming to the LonMark standard, provide a dynamic object that can be
assigned to the device based on network variable information provided by the device
manufacturer. Device manufacturer shall provide an XIF file, resource file and
documentation for the device to facilitate device integration.
3) For BACnet devices, provide the following objects at a minimum:
a) Analog In
b) Analog Out
c) Analog Value
d) Binary
e) Binary In
f)
Binary Out
g) Binary Value
h) Multi-State In
i)
Multi-State Out
j)
Multi-State Value
k) Schedule Export
l)
Calendar Export
m) Trend Export
n) Device
4) For each BACnet object, provide the ability to assign the object a BACnet device and object
instance number.
5) For BACnet devices, provide the following support at a minimum
a) Segmentation
b) Segmented Request
c) Segmented Response
d) Application Services
e) Read Property
f)
g) Write Property
h) Write Property Multiple
i)
j)
HVAC-TS-142
k) Acknowledge Alarm
l)
m) Who-has
n) I-have
o) Who-is
p) I-am
q) Subscribe COV
r) Confirmed COV notification
s) Unconfirmed COV notification
t)
Media Types
u) Ethernet
v) BACnet IP Annex J
w) MSTP
x) BACnet Broadcast Management Device (BBMD) function
y) Routing
17.0
18.0
HVAC-TS-143
20.0
HVAC-TS-144
2.0
TEMPERATURE SENSOR
Temperature sensors for space, pipes and ducts, shall be of the Resistance Temperature
detector (RTD) type or thermistor. These shall be two wire type and shall conform to the
following specifications :
HVAC-TS-145
1)
Immersion sensors shall be high accuracy type with a high resistance versus
temperature change. The accuracy shall be atleast 0.33 degrees F and sensitivity of
atleast 2 ohm/F.
2)
Immersion sensors shall be provided with separate stainless steel thermo well. These
shall be manufactured from bar stock with hydrostatic pressure rating of atleast 10
kgf/cm2.
3)
The connection to the pipe shall be screwed inch NPT (M). An aluminum sleeve shall
be provided to ensure proper heat transfer from the well to the sensor.
Terminations to be provided on the head. Flying leads shall not be acceptable.
4)
The sensor housing shall plug into the base so that the same can be easily removed
without disturbing the wiring connections.
5)
Duct temperature sensors shall be with rigid stem and of averaging type. These shall be
suitable for duct installation.
6)
7)
The sensors shall not be mounted near any heat source such as windows, electrical
appliances etc.
HUMIDITY SENSOR
Space and duct humidity sensors shall be of capacitance type with an effective sensing range
of 10% to 90% RH. Accuracy shall be + 3% or better. Duct mounted humidity sensors shall be
provided with a sampling chamber. Wall mounted sensors shall be provided with a housing.
The sensor housing shall plug into the base so that the same can be easily removed without
disturbing the wiring connections. The sensors shall not be mounted near any heat source
such as windows, electrical appliances etc.
4.0
FLOW METER
Water flow meters shall be either Ultrasonic type or electromagnetic type. For
electromagnetic flow meter, teflon lining with 316 SS electrodes must be provided. The
housing shall have IP 55 protection. Vendors shall have to get their design/ selection
approved by the Consultant, prior to the supply.
The exact ranges to be set shall be determined by the contractor at the time of
commissioning. It should be possible to zero the flowmeter without any external
instruments, with the overall accuracy of atleast 1% full scale.
5.0
HVAC-TS-146
6.0
7.0
8.0
HVAC-TS-147
These shall be suitable for mounting in any plane. Output shall be 2 NO/NC potential free.
Site adjustable scale shall also be provided.
9.0
10.0
11.0
12.0
LEVEL SWITCH
The level switches shall have to meet the following requirement :
Type
Mounting
Connection
Float material
Stem Material
Output
Switch Enclosure
13.0
:
:
:
:
:
:
:
DIGITAL THERMOSTATS
Thermostats for FCUs should be Digital on/off OR Modulating Type for Actuating 2 way or 3
way Valves (On-off/Modulating)
HVAC-TS-148
Thermostats should display Room Temp and Setpoint simultaneously which is easy to read
from atleast 6-8 feet distance.
Thermostats should have Fan Speed Control Switch (Low-Med-High-Auto). Auto Mode
should be able to save energy by automatically reducing the Fan Speed when Room Temp
Achieves Set Point.
LCD Display should be available in Blue or Green Backlit for ease in viewing the Room
Temperature and Setpoint.
Thermostats should work on 230V PS for on-off models and 24V for Modulating Thermostats
The User Settings should be retained in Thermostat Memory in case of Power Failure
The Switching Relays should be separately wired and should be mounted inside the Junction
Box, so that the Thermostat front is sleek in mounting. Thermostat Thickness should be
17mm or less
Thermostats should have Energy Savings Feature with dual setpoint which can be
interlocked with Occupancy Sensor or Hotel Key Card input. This should be indicated in the
LCD Display in the mode it is being operated. This Programming should be possible by Hotel
maintenance Staff.
Thermostats should be similar or equivalent to Honeywell Halo Series Digital Thermostats
Model T6861 (on/off) or T6865 (modulating) version.
14.0
PICV should be capable of maintaining the max flow rate atleast +/-4% Accuracy
The PICV Should be capable of maintaining Linear Temperature Control, Pressure
Independence and Electric Modulation in one Valve body.
The Flow rates should be field settable electronically upto 60% of the valve Max set Flow
rate
The Differential Pressure Ranges for which the valve can maintain the flow rates should be
mentioned in the Product literature
Valve Actuator housing shall be rated to IP54
Actuator shall be driven by a 24Vac power supply and shall accept universal Input signals
like 0/2-10Vdc or 4-20mA signal
Actuator shall be capable of providing feedback Signal of 0/2-10Vdc to the Control
System/BMS
PICV should have an option for adjusting the Flow Characteristics as per AHU in every PICV
to ensure Linear Temp Control.
15.0
16.0
HVAC-TS-149
PICV should have an option for changing the Max Flow Rates in future and no additional
Instrument should be required. Flow Values can be changed by entering in LCD Display only
and not by any DIP Switches or Setting Dial to improve accuracy.
PICV shall provide full valve Authority
PICV Valve body shall be rated at least PN16
Max Close off Pressure shall be mentioned in the Product Datasheet.
Min Working Differential Pressure shall be 30Kpa
Valve shall be Internal BSP Threaded from DN25 to DN50 and Flanged end Connection for
DN65 to DN150
Min Stroke Length of the Valve shall be 20mm
Media Temperature : 0-130 deg C
Valve shall be of Brass/Bronze Construction upto DN50 and Cast Iron upto DN150
Shut off Leakage shall be 0.1 Kvs
:
:
:
:
:
:
:
:
:
Butterfly Valve
Cast Iron or Ductile Iron Body
Nickel plated Ductile Iron
SS416
EPDM
PN16
Bubble Tight
-10 dec C to 120 deg C
ISO7005-2
Actuator
Type
Motor Supply
Travel Angle
Enclosure
Indicator
Space Heater
Stall Protection
:
:
:
:
:
:
:
Manual Override
Torque Limit Switches
External Coating
Make
:
:
:
:
Electric
230 Vac, 50hz/60Hz
90 deg +/- 5 deg
IP67 Waterproof
Continuous Position Indicator
15W 220V Anti Condensation
Built-in thermal protection Cut off at 125 5
Reset at 95 5
By Handwheel, nonclutch design
2 nos.
Dry Aluminium Alloy in Painted Black
Honeywell
HVAC-TS-150
The ports are designated in such a way that flow through the two way valve can be in either
direction.
The valve shall be designed to handle the fluid temperature from1degreeC to 95O C
It can withstand the differential pressure upto 4 Bar.
The valve is of bronze body with stainless steel stem and Noryl cover.
The FCU valve shall have a minimum stroke length of 10mm so that it has the sufficient distance
to travel.
The hydronic FCU valves shall been designed to meet the European standard EN 60730-2-8.
The actuator shall require the power supply of 220 Volts AC so that no transformer is required.
The actuator is easily removable from the valve so that in case the actuator fails at site it can be
easily replaced without affecting the integrity of the water system.
The actuator shall have the provision to operate manually.
The actuator shall meet the low voltage directive 73/23/EEC. The actuator shall be selected in
such a way that the maximum power consumed by the actuator is 6 Watt.
The valve should be similar or equivalent to Honeywell VC6013 version.
17.0
HVAC-TS-151
Thermostats should have Energy Savings Feature with dual set point which can be interlocked
with Occupancy Sensor or Hotel Key Card input. This should be indicated in the LCD Display in
the mode it is being operated. This Programming should be possible by Hotel maintenance
Staff.
Thermostats should be similar or equivalent to Honeywell Halo Series Digital Thermostats
Model T6861 (on/off) version.
HVAC-TS-152
INSTALLATION
All work described in this section shall be performed by system integrators or contractors that
have a successful history in the design and installation of integrated control systems.
Install system and materials in accordance with manufacturers instructions, and as detailed on
the project drawing set.
Drawings of the BMS network are diagrammatic only and any apparatus not shown, but
required to make the system operative to the complete satisfaction of the Architect shall be
furnished and installed without additional cost.
Line and low voltage electrical connections to control equipment shown specified or shown on
the control diagrams shall be furnished and installed by this contractor in accordance with
these specifications.
Equipment furnished by the HVAC Contractor that is normally wired before installation shall be
furnished completely wired. Control wiring normally performed in the field will be furnished
and installed by this contractor.
2.0
WIRING:
All electrical control wiring and power wiring to the control panels, NAC, computers and
network components shall be the responsibility of the this contractor.
The electrical contractor shall furnish all power wiring to electrical starters and motors.
All wiring shall be in accordance with the Project Electrical Specifications, the National Electrical
Code and any applicable local codes. All BMS wiring shall be installed in the conduit types
specified in the Electrical Specifications unless otherwise allowed by the National Electrical
Code or applicable local codes. Where BMS plenum rated cable wiring is allowed it shall be run
parallel to or at right angles to the structure, properly supported and installed in a neat and
workmanlike manner.
3.0
WARRANTY
Equipment, materials and workmanship incorporated into the work shall be warranted for a
period of one year from the time of system acceptance.
Within this period, upon notice by the CLIENT, any defects in the work provided under this
section due to faulty materials, methods of installation or workmanship shall be promptly
(within 48 hours after receipt of notice) repaired or replaced by this contractor at no expense to
the CLIENT.
4.0
WARRANTY ACCESS
The CLIENT shall grant to this contractor, reasonable access to the BMS during the warranty
period.
HVAC-TS-153
The CLIENT shall allow the contractor to access the BMS from a remote location for the purpose
of diagnostics and troubleshooting, via the Internet, during the warranty period.
5.0
SOFTWARE LICENSE
CLIENT shall be the named license holder of all software associated with any and all incremental
work on the project(s). The owner, or his appointed agent, shall determine which organizations
to be named in the orgid of all software licenses.
CLIENT, or his appointed agent, shall be free to direct the modification of the orgid in any
software license, regardless of supplier.
The owner, or his appointed agent, shall receive ownership of all job specific software
configuration documentation, data files, and application-level software developed for the
project. This shall include all custom, job specific software code and documentation for all
configuration and programming that is generated for a given project and /or configured for use
within based controllers and/or servers and any related LAN / WAN / Intranet and Internet
connected routers and devices. Any and all required Ids and passwords for access to any
component or software program shall be provided to the owner.
6.0
ACCEPTANCE TESTING
Upon completion of the installation, this contractor shall load all system software and start-up
the system. This contractor shall perform all necessary calibration, testing and de-bugging and
perform all required operational checks to insure that the system is functioning in full
accordance with these specifications.
This contractor shall perform tests to verify proper performance of components, routines, and
points. Repeat tests until proper performance results. This testing shall include a point-by-point
log to validate 100% of the input and output points of the DDC system operation.
Upon completion of the performance tests described above, repeat these tests, point by point
as described in the validation log above in presence of CLIENT's Representative, as required.
Properly schedule these tests so testing is complete at a time directed by the CLIENT's
Representative. Do not delay tests so as to prevent delay of occupancy permits or building
occupancy.
System Acceptance: Satisfactory completion is when BMS contractor have performed
successfully all the required testing to show performance compliance with the requirements of
the Contract Documents to the satisfaction of CLIENT Representative. System acceptance shall
be contingent upon completion and review of all corrected deficiencies.
7.0
HVAC-TS-154
functions specified. Operator orientation of the systems shall include, but not be limited to; the
overall operation program, equipment functions (both individually and as part of the total
integrated system), commands, systems generation, advisories, and appropriate operator
intervention required in responding to the System's operation.
The training shall be in three sessions as follows:
1) Initial Training: One day session (8 hours) after system is started up and at least one week
before first acceptance test. Manual shall have been submitted at least two weeks prior to
training so that the owners' personnel can start to familiarize themselves with the system
before classroom instruction begins.
2) First Follow-Up Training: Two days (16 hours total) approximately two weeks after initial
training, and before Formal Acceptance. These sessions will deal with more advanced
topics and answer questions.
3) Warranty Follow Up: Two days (16 hours total) in no less than 4 hour increments, to be
scheduled at the request of the owner during the one year warranty period. These
sessions shall cover topics as requested by the owner such as; how to add additional points,
create and gather data for trends, graphic screen generation or modification of control
routines.
Sr.
No.
A
Description
AI
DI
AO
DO
Bacnet / Modbus
Interface License
Chillers - ON / OFF
5
2
By IBMS Contractor
Flow Meter
Flow Switch
CO sensor
IAQ Sensor
Pressure sensor
Water DP sensor
Air DP sensor
Duct type
temperature
DP switch Air
DP switch Water
Level switch
Outside T/RH
Immersion type t
sensor
PART IV IO SUMMARY
Sr.
No.
5
6
8
9
10
Description
AI
DI
AO
DO
By IBMS Contractor
10
Immersion
temperature sensor
10
Immersion
temperature sensor
Immersion
temperature sensor
10
10
Flow Metering
Ambient
temp/Humidity sensor
Potential Free Contact
from
BMS
to
motorised butter fly
valve with limit switch
for position status.
Flow Meter
Chilled
Status
Water
Flow
Suitable
provision
Pump ON / OFF
6
insertion
Flow Meter
Flow Switch
CO sensor
IAQ Sensor
Pressure sensor
Water DP sensor
Air DP sensor
Duct type
temperature
DP switch Air
DP switch Water
1
Butterfly Valves
2
11
Level switch
Outside T/RH
HVAC-TS-156
Immersion type t
sensor
Sr.
No.
2
C
1
Description
AI
DI
AO
DO
Differential
across Pumps
Differential
across Pumps
Secondary Chilled
Water Pumps (7 Nos)
Pump ON / OFF
Switch
Switch
7
6
Differential
pressure
sensor across Pump
Differential
Sensor
Pressure
Flow Meter
Flow Switch
CO sensor
IAQ Sensor
Pressure sensor
Water DP sensor
Air DP sensor
Duct type
temperature
DP switch Air
DP switch Water
7
2
By IBMS Contractor
Level switch
Outside T/RH
HVAC-TS-157
Immersion type t
sensor
Sr.
No.
7
8
Description
AI
DI
AO
DO
D
1
Differential pressure
switch across the CHW
pumps for ON/OFF
status.
Signal
switch.
A/M
from
Imm
type
sensor.
fan
10
temp
5
Acceptance of Potential Free Output
in CT Panel
Flow Meter
Flow Switch
CO sensor
IAQ Sensor
Pressure sensor
Water DP sensor
Air DP sensor
Duct type
temperature
DP switch Air
DP switch Water
By IBMS Contractor
Level switch
Outside T/RH
HVAC-TS-158
Immersion type t
sensor
10
Signal
switch
Cooling
Status
10
Tower
run
47
129
17
92
AHU Air Flow status
level
92
92
CO sensor
19
44
from
Flow Meter
10
Flow Switch
10
IAQ Sensor
10
By IBMS Contractor
Pressure sensor
DO
Water DP sensor
AO
Air DP sensor
DI
Duct type
temperature
AI
DP switch Air
Description
DP switch Water
Sr.
No.
3
Level switch
Outside T/RH
HVAC-TS-159
Immersion type t
sensor
19
Differential
Switch
across Fans
Potential Free Contact
at Auto/Manual Switch
92
AI
DI
AO
DO
92
92
By IBMS Contractor
8
9
Duct Pressure
Monitoring
Return Air Temperature
10
92
92
92
Duct
Temperature
Sensor
0-10 V DC Signal
92
11
12
13
92
92
92
92
92
552
368
368
92
CO sensor
IAQ Sensor
Pressure sensor
Water DP sensor
Air DP sensor
Duct type
temperature
DP switch Air
DP switch Water
Differential Pressure
Switch across filter
0-10 Vdc from BMS to
VFD
92
Flow Meter
Description
Flow Switch
Sr.
No.
4
Level switch
Outside T/RH
HVAC-TS-160
Immersion type t
sensor
92
92
92
IAQ Sensor
0-10 V DC Signal
0-10 V DC Signal
92
184
92
92
92
DO
By IBMS Contractor
30
30
Differential
across Fans
30
Differential Pressure
Switch across filter
0-10 Vdc from BMS to
VFD
0-10 Vdc from VFD
TFA ON/OFF
TFA Auto
status
Manual
30
30
Switch
30
7
8
9
Duct Pressure
Monitoring
Supply Air Temperature
10
30
30
30
30
Sub Total (G)
H
90
120
60
30
CO sensor
Air DP sensor
Duct type
temperature
DP switch Air
DP switch Water
30
30
Duct
Temperature
Sensor
0-10 V DC Signal
30
30
Flow Meter
AO
Flow Switch
DI
IAQ Sensor
AI
Pressure sensor
Description
Water DP sensor
Sr.
No.
1
Level switch
Outside T/RH
HVAC-TS-161
Immersion type t
sensor
60
30
30
DO
By IBMS Contractor
14
14
Differential
across Fans
14
Differential Pressure
Switch across filter
Duct Temperature
Air Temperature
Duct Pressure
Monitoring
VFD Trip Status
7
7
7
7
14
49
17
2
17
CO sensor
Air DP sensor
Duct type
temperature
DP switch Air
DP switch Water
Differential
across Fans
Switch
14
Liftwell Pressurization
Fans - 17 Nos.
Fan ON/OFF
14
14
28
Switch
Flow Meter
AO
Flow Switch
DI
IAQ Sensor
AI
Pressure sensor
Description
Water DP sensor
Sr.
No.
1
Level switch
Outside T/RH
HVAC-TS-162
Immersion type t
sensor
21
17
14
Fan ON/OFF
34
Fan
Auto / Manual
status
205
Differential
across Fans
205
CO Sensor
Sub Total (J)
L
1
205
90
90
615
17
CO sensor
205
205
17
205
IAQ Sensor
Pressure sensor
17
Flow Meter
Ventillation Fans
without VFD - 205 Nos
By IBMS Contractor
Flow Switch
DO
Water DP sensor
AO
Air DP sensor
Fan
Auto / Manual
status
DI
Duct type
temperature
AI
DP switch Air
Description
DP switch Water
Sr.
No.
3
Level switch
Outside T/RH
HVAC-TS-163
Immersion type t
sensor
90
0
205
90
Hydrant pressure
monitoring
Sprinkler pressure
monitoring
Jockey Pump run status
4
5
6
Immersion
temperature sensor
10
4
Pressure Sensor
Pressure Sensor
1
1
CO sensor
Butterfly Valves
Flow Meter
Flow Switch
IAQ Sensor
By IBMS Contractor
Pressure sensor
DO
Water DP sensor
AO
Air DP sensor
DI
Duct type
temperature
AI
DP switch Air
Description
DP switch Water
Sr.
No.
3
Level switch
Outside T/RH
HVAC-TS-164
Immersion type t
sensor
1
3
Domestic
Water
Transfer
Pump
Auto/Manual Status
Domestic Water Transfe
Pump run status
20
2
Level Switch
Sump
Pump
Auto/Manual Status
CO sensor
On/Off
Filter
Feed
Pump
Auto/Manual Status
Sump Pump
Control
Flow Meter
Flow Switch
IAQ Sensor
By IBMS Contractor
Pressure sensor
DO
Water DP sensor
AO
Air DP sensor
DI
Duct type
temperature
AI
DP switch Air
Description
DP switch Water
Sr.
No.
Level switch
Outside T/RH
HVAC-TS-165
Immersion type t
sensor
10
4
5
10
58
12
Electrical System - HT
Panels , LT Panels
HT / LT Breaker Phase
Voltage Monitoring (8
Nos.)
HT / LT Breaker Phase
Current Monitoring (35
Nos.)
HT / LT Breaker
Frequency Monitoring (4
Nos.)
10
HT / LT Breaker KW
Monitoring (24 Nos.)
HT / LT Breaker KWH
Monitoring (35 Nos.)
CO sensor
Flow Meter
Soft
Water
Pump
Auto/Manual Status
Flow Switch
IAQ Sensor
Pressure sensor
DO
Water DP sensor
By IBMS Contractor
AO
Air DP sensor
13
DI
Duct type
temperature
12
AI
DP switch Air
11
Description
DP switch Water
Sr.
No.
10
Level switch
Outside T/RH
HVAC-TS-166
Immersion type t
sensor
3
4
Flow Meter
CO sensor
40
0
0
Integration through
Modbus Protocol
Flow Switch
DG Start/Stop Stauts
82
40
IAQ Sensor
By IBMS Contractor
Pressure sensor
Diesel Generator
DO
Water DP sensor
AO
Air DP sensor
HT / LT Breaker Trip
Status
Sub Total (O)
DI
Duct type
temperature
HT / LT Breaker On/Off
status
Bus Coupler On/Off
Status
AI
DP switch Air
Description
DP switch Water
Sr.
No.
6
Level switch
Outside T/RH
HVAC-TS-167
Immersion type t
sensor
2
4
2
Flow Meter of 25 mm
AI
DI
AO
DO
Flame Proof
Transmitter
4
11
By IBMS Contractor
Integration of VFDs
through Modbus
Protocol / Bacnet
VAV - 89 on Bacnet IP
Integration of VAV
through Bacnet IP
Integration of BTU
Meter through M-BUS
Integration of FAS
through
Modbus/Bacnet/OPC
Protocols of all
devices/detectors
Grand Total (A to T)
826
1477
452
418
CO sensor
IAQ Sensor
Pressure sensor
Water DP sensor
Air DP sensor
Duct type
temperature
DP switch Air
DP switch Water
Level
Flow Meter
Description
Flow Switch
Sr.
No.
6
Level switch
Outside T/RH
HVAC-TS-168
Immersion type t
sensor
4
0
23
15
19
487
129
136
92
90
III)
ELECTRICAL SYSTEM:
I.
SCOPE
The scope of this section comprises of fabrication, supply, erection, testing and
commissioning of Motor Control Centre (MCC), wiring and cable tray of all air-conditioning
equipment, components and accessories.
A)
GENERAL
The electrical Installation work shall be carried out in accordance with Indian Standard Code
of Practice. It shall also be in conformity with the current Indian Electricity rules and
regulations and requirements of the Local Electricity Supply Authority and Fire Insurance
regulations so far as these becomes applicable to the installation. Electrical work in general
shall be carried out as per following CPWD Specifications.
General Specifications for Electrical Works.
- Part -I
Internal Work
- 2007.
- Part -II
External Work
- 1995/Latest.
- Part -IV
Substation Work
- 2007.
Wherever this specifications calls for a higher standard of material and or workmanship than
those required by any of the above mentions regulations and specification then the
specification here under shall take precedence over the said regulations and standards.
B)
1.0
STANDARDS OF CODES
This chapter covers the specifications for supply and laying of Medium Voltage XLPE
insulated PVC sheathed FRLS cables for 1100 volts.
All equipments, components, materials and entire work shall be carried out in conformity
with applicable and relevant Bureau of Indian Standards and Codes of Practice, as amended
upto date. In addition, relevant clauses of the Indian Electricity Act 1910 and Indian
Electricity Rules 1956 as amended upto date shall also apply. Wherever appropriate Indian
Standards are not available, relevant British and /or IEC Standards shall be applicable.
2.0
CABLES
Medium voltage cables shall be aluminium conductor XLPE insulated, PVC sheathed FRLS
armoured conforming to latest IS. Cables shall be rated for a 1100 Volts.
HVAC:TS-170
:
:
:
:
Red/Black/Yellow/Blue
Red and Black
Red, Yellow and Blue
Red, Yellow, Blue and Black
3.0
LAYING
Cables shall be laid as per the specifications given below :
3.1
Duct system
Wherever specified such as road crossing, entry to building or in paved area etc. cables shall
be laid in underground ducts. The duct system shall consists of a required number of stone
ware pipes, GI, CI or spun reinforced concrete pipe with simplex joints and all the jointing
work shall be done according to the CPWD building specifications or as per the instructions
of the Engineer-In-Charge as the case may be. The size of the pipe shall not be less than
100mm in diameter for a single cable and shall not be less than 150mm for more than one
cable and so on. The pipe shall be laid directly in ground without making any special bed but
wherever asbestos cement pipes are used, the pipes shall be encased in concrete of 75mm
thick. The ducts shall be properly anchored to prevent any movement. The top surface of
the cable ducts shall not be less than 60 cm. below the ground level. The ducts shall be laid
a gradient of at least 1:300. The duct shall be provided manholes of adequate size at regular
intervals for drawing the cables. The manhole cover and frame shall be of cast iron and
machine finished to ensure a perfect joint. The manhole covers shall be installed flush with
the ground or paved surfaces. The duct entry to the manholes shall be made leak proof with
lead-wool joints. The ducts shall be properly plugged at the ends to prevent entry of water,
rodents, etc. Suitable duct markers shall be placed along the run of the cable ducts. The
duct markers shall at least be 15 cm. square embedded in concrete, indicating duct. Suitable
cable supports made of angle iron shall be provided in the manholes for supporting the
cables. Proper identification tags shall be provided for each cable in the manholes.
3.2
HVAC:TS-171
making one long loop in the reverse direction. After the cable has been uncoiled and laid
into the trench over the rollers, the cable shall be lifted slightly over the rollers beginning
from one end by helpers standing about 10 mtrs. apart and drawn straight. The cable should
then be taken off the rollers by additional helpers lifting the cable and then laid in a
reasonably straight line.
For short cut runs and sizes upto 50 sq.mm of cables upto 1.1 KV grade any other suitable
method of direct handling and laying can be adopted with the prior approval of the
Engineer-in-charge.
When the cable has been properly straightened, the cores are tested for continuity and
insulation resistance and the cable length then measured. The ends of all cables shall be
sealed immediately. In case of PVC cables suitable moisture seal tape shall be used for this
purpose.
Cable laid in trenches in a single tier formation shall have a covering of clean, dry sand of not
less 17 cms above the base cushion of sand before the protective cover is laid. In the case of
vertical multi tier formation after the first cable has been laid, a sand cushion of 30 cms shall
be provided over the initial bed before the second tier is laid. If additional tiers
are formed, each of the subsequent tiers also shall have a sand cushion of 30 cms as stated
above. The top most cable shall have final sand covering not less than 17 cms before the
protective cover is laid.
Unless otherwise specified, the cables shall be protected by the second class bricks of not
less 20 cms x 10 cms x 10 cms (nominal size) protection covers placed on top of the sand
(bricks to be laid breadth wise) for the full length of the cable. Where more than one cable
is to be laid in the same trench, this protective covering shall cover all the cables and project
at 5 cm. over the sides of the end cables. The trenches shall be taken back filled with
excavated earth free from stones or other sharp edge debris and shall be rammed and
watered, if necessary, in successive layers not exceeding 30 cm, unless otherwise specified.
3.3
Route Marker
Cable route marker marked "Cable" shall be provided alongwith the route of the cable and
location of loops. The route markers shall be of tapered concrete slab of 60 x 60cm at
bottom and 50 x 50cm at top having a thickness of 10cm. Cable marker shall be mounted
parallel to and 50cm away from the edge of the trench.
3.4
3.5
Cable on Trays/Racks
Cable shall be laid on cable trays/racks wherever specified. Cable racks/trays shall be of
ladder, trough or channel design suitable for the purpose. The nominal depth of the
trays/racks shall be 150 mm. The width of the trays shall be made of steel or aluminium.
The trays/racks shall be completed with end plates, tees, elbows, risers, and all necessary
HVAC:TS-172
hardware, entire steel trays/ racks shall be hot dip galvanized including widths & accessories.
Cable trays shall be erected properly to present a neat and clean appearance. Suitable
cleats or saddles made of aluminium strips with PVC covering shall be used for securing the
cables to the cable trays. The cable trays shall comply with the following requirements :
i)
The tray shall have suitable strength and rigidity to provide adequate support for all
contained cables.
ii) It shall not present sharp edges, burrs or projections injurious to the insulation of
wiring/cables.
iii) If made of metal, it shall be adequately protected against corrosion or shall be made of
corrosion-resistant material.
iv) It shall have side rails or equivalent structural members.
v) It shall include fittings or other suitable means for changes in direction and elevation of
runs.
3.6
Installation
i) Cable trays shall be installed as a complete system. Trays shall be supported properly
from the building structure. The entire cable tray system shall be rigid.
ii) Each run of the cable tray shall be completed before the installation of cables.
iii) In portions where additional protection is required, non combustible covers/enclosures
shall be used.
iv) Cable trays shall be exposed and accessible.
v) Where cables of different system are installed on the same cable tray, non combustible,
solid barriers shall be used for segregating the cables.
vi) Cable trays shall be grounded by two nos, earth continuity wires. Cable trays shall not
be used as equipment grounding conductors.
vii) At no place the cable tray / rack / ladder running horizontally should rest on any building
partition like Brick wall, RCC beams etc. but instead proper MS supports/ hangers to be
provided at minimum of 1500 mm intervals and at every Turning Angles.
3.7
4.0
HVAC:TS-173
CABLE TRAYS
Cable Trays shall be Galvanized and factory fabricated out of MS channels, angleiron, tee,
bends, sections, flats and perforated sheet for different loads and number and size of cables
as given below :
Supply and fixing of perforated type cable trays of the following sizes of pre-galvanized iron.
i.
ii.
iii.
iv.
v.
SCOPE
This Section covers the detailed requirements of medium voltage switch Panel for 433V, 3
phase 50 Hz 4 wire system. These shall be branded and/or assembled/fabricated from a
factory of repute. All switchgears shall be fully rated at an ambient of 40 C.
2.0
TYPE OF PANEL
The medium voltage switch board panel shall comprise of any one of the following types of
switchgears or combination thereof as specified.
(a)
(b)
Switch Disconnector Fuse Units fixed type, MCCBs of suitable Ics ratings.
MCCBs shall invariably be Current Limiting type. Features like Double Break,
Positive Isolation functions shall be preferred.
The Panel shall be indoor type having incoming sectionalization and outgoing switchgears as
specified. The design shall be cubical type. The degree of enclosure protection shall be IP 42 as
per IS: 13947 (Part-I).
3.0
M.V PANEL
3.1
General Construction
The switchboard shall be floor mounted free standing totally enclosed and extensible type. The
switch board shall be dust & vermin proof and shall be suitable for the climate conditions as
specified. The design shall include all provisions for safety of operation and maintenance
personnel. The general construction shall conform to IS: 8623/1993 for factory assembled switch
board.
HVAC:TS-174
3.2
3.2.1
Cubical type panels shall be fabricated out of sheet steel not less than 2.0 mm thick. Wherever
necessary, such sheet steel members shall be stiffened by angle iron frame work. General
construction shall employ the principle of compartmentalization and segregation for each circuit.
Unless otherwise approved, incomer and bus section panels or sections shall be separate and
independent and shall not be mixed with sections required for feeders. Each section of the rear
accessible type panel shall have hinged access doors at the rear. Overall height of the panel shall
not exceed 2.4 meters. Operating levers, handle etc. of highest unit shall not be higher than 1.7
meters. Multi-tier mounting of feeder is permissible. The general arrangement for multi
tier construction shall be such that the horizontal tiers formed present a pleasing and aesthetic
look. The general arrangement shall be approved before fabrication. Cable entries for
various feeders shall be either from top or bottom. Through cable alleys located in between
two circuit sections, either in the rear or in the front of the panel. All cable terminations shall be
through gland plates. There shall be separate gland plate for each cable entry so that there will
not be dislocation of already wired circuits when new feeders are added. Cable entry plates shall
therefore be sectionalized. The construction shall include necessary cable supports for clamping
the cable in the cable alley or rear cable chamber.
Cubicle panels with more than 1000 Amps BUS shall be made of tested structural modular
sections.
3.2.2
3.2.3
Incomer I Termination
Incomer termination shall be suitable for receiving bus trunking /underground cables. Cable
terminations shall invariably be through terminal blocks (Poiyamide or superior) or brought
out solid terminals.
3.2.4
Instruments
All voltmeters and ammeters shall be flush mounted of size minimum 96 mm conforming to class
1,5 of IS: 1248 for accuracy. All voltmeters shall be protected with MCB.
3.2.5
Indicating Lamps
On all the incomers of M.V panels, ON/OFF indicating LED lamps shall be provided and shall
be suitable for operation on AC supply. Phase indicating LED lamps shall be associated with
necessary ON/OFF toggle switch.
3.2.6
Small Wiring
All small wiring for Controls, Indication etc, shall be of with suitable FRLS/HFFR (halogen
free fire retardant) copper conductor cables. Wiring shall be suitably protected within switch
HVAC:TS-175
board. Runs of wires shall be neatly bunched, suitably supported and clamped. Means shall be
provided for easy identifications of the wires. Where wires are drawn through steel conduits,
the works shall conform to CPWD General Specifications for Electrical works (Part IInternal) - 2005 and IS:732 as the case may be. Identification ferrules shall be used at both
ends of the wires. All control wiring meant for external connections are to be brought out of
terminal board.
OPERATIONAL REQUIREMENTS
The indoor type MV panel shall conform to the following: The panel shall comprise of incomers, outgoing feeders and bus coupler as specified.
The incomer shall be either a double break / contact repulsion MCCB or an Air Circuit
Breaker. The bus coupler shall be either a circuit breaker or a double break / contact
repulsion MCCB or switch disconnector fuse unit as specified. The outgoing feeders shall
be circuit breakers/MCCBs as specified.
(a) Bus bars for phase and neutral shall have a rating as specified in the format of Appendix II.
The entire switch panel shall be cubical type generally conforming to 18:8623/1993
for factory assembled switch board.
The incomer panel shall be suitable for receiving bus trunking or MV cable of size specified
either from top or from bottom.
All incoming AIRCIRCUIT BREAKER/MCCB shall have suitable adjustable tripping current and the
time delay settings.
(b) The entire panel shall have a common earth bar of size as specified with two terminals for
earth connections.
4.0
4. 1
4. 1.1
Switch Disconnector Fuse Units: All SDF units for feeders or outgoing circuits shall be
suitable for a Breaking capacity of 80 KA (57 MVA 433V) capacity at 433V 3 phase 50 Hz AC
system conforming to IS: 4064. The number of units and rated current shall be as per
detailed requirements specified. Switch Disconnector Fuse unit shall be double
break front operated type. The units shall be complete with following: (a)
(b)
(c)
Necessary set of CTs together with an ammeter and selector switch as specified.
(d)
(e)
(f)
HVAC:TS-176
4. 1.2
MCCB : All MCCBs shall be current limiting type with features of load line
reversibility and suitable for Horizontal / Vertical mounting without any
derating. Beyond 300Amps capacity MCCBs shall have positive isolation
and preferably double break / contact repulsion & double insulation features.
The MCCBs shall invariably be used with terminal spreaders,
5.0
6.0
INSTALLATION
The installation work shall cover assembly of various sections of the panels lining up, grouting
the units etc. In the case of multiple panel switch boards after connecting up the bus bars
etc., all joints shall be insulated with necessary insulation tape or approved insulation
compound. A common earth bar as per section 7 of these specifications shall be run
inside at the back of switch panel connecting all the sections for connection to frame
earth system. All protection and other small wirings for indication etc. shall be completed
before calibration and commissioning checks are commenced. All relays, meters etc. shall be
mounted and connected with appropriate wiring.
TESTING AND COMMISSIONING
Commissioning checks and tests shall include all wiring checks and checking up of connections.
Relay adjustment/setting shall be done before commissioning in addition to routine Megger
tests. Checks and tests shall include the following: (a)
(b)
(c)
(d)
(e)
C [II]
1.0
GENERAL
This section covers specification of Medium Voltage Switchboards incorporating items of
switchgear like Air Circuit Breaker, Moulded Case Circuit Breaker, Contactors and Metering
etc.
2.0
3.0
SWITCHGEAR:
3.1
3.1.1
General
3.1.2
HVAC:TS-177
The breaking capacity performance certificates shall be available for category A to the
above mentioned standards. . The test shall be carried out under the breaking
performance during the ultimate breaking capacity (Icu). Certificate for all the sequences
(Sequence 1 mandatory) should be available.
All circuit breakers shall have a rated operational voltage of 600V AC (50Hz).
The rated insulation voltage shall be 600V and 660V at 50/60 Hz. for low breaking
capacity and high breaking capacity MCCBs respectively.
Thermal overload release adjustment can be done from a single point. MCCB cover need
not to be opened for doing such adjustment.
There should be different levels of breaking capacities starting from 10kA upto 50kA for
flexibility in selection.
Production site organization shall be certified to comply with ISO 9001 standard.
Construction
Operating mechanism shall be of the quick make quick break type, with the speed of
operation independent of the operator, and mechanically trip free from the operating
handle so as to prevent the contacts from being held closed against short-circuit and
overload conditions. The operating mechanism shall be constructed to operate all poles
in a multi-pole breaker simultaneously during opening, closing and tripped conditions.
It shall not require any external power supply to operate the tripping mechanism.
The breakers shall be operated by a toggle which shall clearly indicate the three
fundamental position ON, OFF and TRIPPED.
The breaking and extinction of the electrical arc shall be achieved by means of nonwelding contacts and an arc chute surrounding these contacts.
3.1.3
HVAC:TS-178
Characteristics
3.1.4
3.1.5
Operation
If required, the breaker shall be provided with the facility for padlocking and door
interlocking.
The electrical and mechanical endurance of the moulded case circuit breakers should be
as defined.
The moulded case circuit breakers shall be equipped with a "push to trip" button in front
to test operation and the opening of the poles.
The circuit breaker rating, the "push to trip" button, outgoing circuit identification and
the contact position indication must be clearly visible and accessible from the front,
through the front panel or the door of the switchboard.
Options
It shall be possible to combine the following functions into the circuit breaker
Earth fault protection
Remote indication off circuit breaker trip condition and operational conditions (ON/OFF).
Auxiliary contacts, alarm contacts should be available if required.
3.1.6
Installation
It should be possible to terminate Aluminium cable of required size for the defined current
carrying capacity. The requisite size should be made available by means of extended
terminals (as a standard offer) in case the direct terminals are not of adequate size.
Adequate phase to phase clearance has to be ensured in case of extended terminations.
The circuit breaker should provide the flexibility of terminating line and load from any
direction. Manufacturers should test the circuit breaker for this condition and requisite test
certificate should be available.
Phase barrier should be provided as a standard feature.
3.2
HVAC:TS-179
CTs shall be mounded such that they are easily accessible for inspection, maintenance and
replacement. Wiring for CT shall be with copper conductor PVC insulated wires with proper
termination works and wiring shall be bunched with cable straps and fixed to the panel
structure in a neat manner.
Potential Transformer
PTs shall confirm to latest amendment upto date IS Codes.
Measuring Instruments
Direct reading electrical instruments shall conform to latest IS codes in all respects. Accuracy
of direct reading shall be 1.0 of voltmeter and 1.5 for ammeters. Other instruments shall
have accuracy of 1.5. Meters shall be suitable for continuous operation between -100C and
+5000C. Meters shall be flush mounting and shall be enclosed in dust tight housing. The
housing shall be of steel or phenolic mould . Design and manufacture of meters shall ensure
prevention of fogging of instrument glass. Pointer shall be black in colour and shall have Zero
position adjustment device operable from out side. Direction of deflection shall be from left
to right. Selector switches shall be provided for ammeters and volt meters used in three
phase system.
KWH Meter
Meter shall be of 3 phase digital dual type with communication port (or as specified in the
BOQ) and shall be provided with a maximum demand indicator.
HVAC:TS-180
AB)
HVAC:TS-181
S. No.
Manufacturers Name
I)
HVAC ITEM:
1.
York//Trane/ Carrier
2.
Savecon
(Kirloskar)/ Bell & Gossett/Wilo
(Mather+Platt)/ Grundfos
3.
Cooling Towers
Mihir/Advance /Paharpur
4.
Rapid Cool/Emerald/Thermax/Sandhu
5.
6.
Edgtech/Zeco/Syatem Air/Flaktwood
i)
Cooling Coil
ii)
Fan
iii)
Sinko/Carryaire/Trane
7.
Split AC
8.
9.
M.S. Pipes:
i)
Tata/Jindal Hissar/Sail
ii)
Tata/Jindal Hissar/Sail
10.
Butterfly Valves
Advance/Audco/Danfoss
11.
Belimo/Audco/Danfoss
12.
Check Valves
Advance/Audco/ Danfoss
13.
Ball valve
Zoloto/ Audco/ RC
14.
Balancing Valves
Danfoss/ Audco/Advance
15.
Belimo/Danfoss/Johnson Controls /
Honeywell
16.
Expansion Bellows
Resistoflex /Cori/Areaflex
17.
Pot/Y-Strainers
Sandhu/Rapid Cool/Sant/Emerald
18.
Anergy/Armstrong/Emerald
19.
20.
Rapid Control/Anergy/Sant
S. No.
HVAC:TS-182
Manufacturers Name
21.
Thermometers
Feibig/H.Guru/Sandhu
22.
23.
Air Separator
24.
Anergy/Rapid Cool/Oventrop
25.
Plug Valve
Anergy/Rapid Cool
26.
Ductofab/Zeco/Rolastar
27.
G.I. Sheets
Sail/Tata/Jindal
28.
Al. Sheets
Hindalco/Balco/ NALCO
29.
Fire Dampers
Ravistar/Greenheck/Flakt/Airflow
30.
Grills/Diffusers
Ravistar/ Caryaire/Flowel/Airflow
31.
Ravistar/Caryaire/Flowel/Airflow
32.
PUF Saddles
Lloyds/Beardsell/ Malanpur
Mechmaark/Thermodyne/Purolator/Anfilco
33.
34.
35.
36.
37.
Ventilation Fans:
i)
Tube/Vane Axial
ii)
Inline (Centrifugal)
iii)
Propeller Fans
Kruger/ GE/Alstom/Crompton
38.
Air Washers/Scrubber:
i)
Air Washer/Scrubber
Edgetech/Zeco/Roots Air/Ambassador
ii)
Fan
iii)
Pump
Kirloskar/Beacon
iv)
Filters
Mechmaark/Thermodyne/Purolator/Anfilco
39.
Flowcon / Oventrop / TA
S. No.
HVAC:TS-183
Manufacturers Name
II)
Electrical Item:
1.
2.
Distribution Boards
Ambit/CWS/Jackson/ Neptune
: MDS Legrand/ Hager/ Siemens/ Schneider
3.
: Siemens/ L&T/Schneider/ABB
4.
: Siemens/ L&T/Schneider/ABB
5.
6.
Electrical Terminals
: Elemax/ Connectwell
7.
8.
MPCBs
9.
10.
11.
12.
13.
14.
15.
Cable Tray
: MEM/Slotco/OBO
16.
: Gloster/RPG/Polycab/Universal/Finolex
S. No.
III)
BMS Item:
1.
Standalone DDCs
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
HVAC:TS-184
Manufacturers Name
********