DATE

HOURS

03/01/201
7

Site specific induction complete.

03/01/201
7

Set up office computer and introduce myself to all office staff.

03/01/201
7

Completed the work placement Agreement and work placement


plan with James

03/01/201
7

Collate the latest drawings for review and raised a list of questions
to go through with James.

03/01/201
7

04/01/201
7

04/01/201
7
04/01/201
7

04/01/201
7
4
04/01/201
7

05/01/201
7

ACTIVITY / ACHIEVEMENT

Reviewing my questions with James prior to commencing a


programme.
Walked Sight with Project Manager (PM) for the Poly Horizon
Project, Tarek Helmy and James.
James introduced me to a number of the team and sub-contractors
during the walk. We discussed some of the relevant issues that
arose during the walk. Meet the Formwork contractor.
Watched the pouring of Tower B, Level 2, Pour 1 (B-02-1).
Approximately 105 cubic metres of concrete was poured with a
boom pump installed on the roof of the jump form.
Took to studying the general architectural, civil, hydraulic,
mechanical and structural construction plans for Basements 1, 2
and 3, as well as A-GF, A-01, A-02, A-03, B-GF, B-01, B-02, C-GF
and C-01.
Met the client for the Poly Horizon project. Discussed supply and
procurement issues with Tarek and the client. Resolution was found
and a schedule was developed to deliver the agreed works within
the required timeline. Prepared meeting minutes for Tarek to
review.

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.

Updated meeting minutes following yesterdays meeting with the


client and Tareks review. Once they were updated I Issued them via
email to the meeting attendees.

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.

Meet with Formwork contractors to discuss a solution to current fall


protection issue. The problem arose during the jumping of the
Screens, where working platforms were not of an adequate
standard to prevent small objects from falling from the higher
levels.

05/01/201
7

05/01/201
7

05/01/201
7
05/01/201
7
06/01/201
7
06/01/201
7
06/01/201
7

Undertook a review with James as to why the Pre-cast contractors


have not been utilising the crane time effectively. The issue was
due to an error in fabrication of the pre-cast panels.

Gathered information from the site foreman as to any other issues


that they have been having with the precast contractor.

Site walk with James.

06/01/201
7
3

06/01/201
7
07/01/201
7
07/01/201
7

Inspected to tower A -02 columns and related formwork. Work


where not complete in order to finalise the ITP.

Site walk with James.

1
07/01/201
7

DATE
09/01/201
7
09/01/201
7

HOURS

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.
Took delivery of over 15 tonnes of reo for Pour 6 and 7. Cross
checked with a number of schedules and developed a system that
Ganellen has adopted. The system uses a simple colour code with
the steel colour corresponding to specific put-down zones onsite.

ACTIVITY / ACHIEVEMENT

Site walk with James.

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.

Completed an inspection with James of Tower A level 3 pour 2 as it


is experiencing issues with fall protection. In particular, screens are
too low and there are still significant gaps between the edge of
plywood and the face of the fall screens. Spoke to contractors and
issued non-compliance. If the issue isnt fixed by COB, the entire
deck will be closed until the issue is fixed.

Sat in the meeting with the precast contractor to discuss the issues

09/01/201
7

09/01/201

Finalised list of issues we have been having the precast contactor


ready for James to discuss with the site project manager.
Met with the site project manager to discuss the issues with the
precast contractor, it was decided that we bring them in for meeting
to go through these items in order to resolve everything. James
booked in a meeting on 09.01.2017.
Complete an Inspection and Test Plan for the Columns in C-B1-6
(ITP) with the Site Engineer responsible for Tower C. The ITP
required visual inspection and checking of the installed reo. There
was a total of 30 Columns checked. The checks included: Lap
Distances, Reo separation distances, reo diameters and
cleanliness of column bases.

that we are having on site. It was resolved that the majority of the
delays have been happening due to manufacture error. In order to
ensure such items are minimised the contractor confirmed that any
rectification works are to be completed within the factory.

09/01/201
7
10/01/201
7
10/01/201
7

Started to prepare meeting minutes following the meeting with the


precast contractor.

Site walk with James.

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.

10/01/201
7

10/01/201
7

11/01/201
7
11/01/201
7

3
11/01/201
7
5
11/01/201
7

Sat in to the internal site meeting, took notes in order to complete


the minutes for James review.
Met the client for the Poly Horizon project. Discussed current site
progress, sample sign offs & future works. Prepared meeting
minutes for Tarek to review.
Site walk with James.
Issued reinforcement delivery confirmation report to our supplier
following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.
Meet with Formwork contractor to reach an agreement the
outstanding items in relation to completing the formwork on tower A
level 4 pour 2. Original plans were to have ~200 cubic metres of
concrete poured on 13 Jan 17, but delays have forced the pour to
go ahead on 16 Jan 17.

Updated my programme following James review and progress on


site.

Site walk with James.

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.

12/01/201
7

Assisted the tower B foreman to enter the level 1 structural defect


within the online system onsite.

12/01/201
7

Assisted the tower A foreman to enter the level 1 structural defect


within the online system onsite.

DATE

HOURS

13/01/201
7

12/01/201
7
12/01/201
7

ACTIVITY / ACHIEVEMENT
Site walk with James.

13/01/201
7
3

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.

Over watched concrete pour of columns to basement 1 of tower C


with the tower foreman. 40 MPa concrete was poured into 24
Columns for a total of 15 cubic metres and 65 MPa concrete was
poured into 3 Columns for a total of 3 cubic metres. A concrete
pump was propped over the site from the main road and fully
extended to reach the furthest columns. Heat set in and the
concrete was setting within the pump line so the final 3 columns
were not poured.

Updated my programme following James review and progress on


site. Ready for James review again.

Site walk with James.

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.

Assisted site structure foreman with completing the remaining


works to tower a level 3 pour 2 slab, prior to the engineer
inspecting the slab.

Walked with the engineer who was inspecting the slab Level 3 pour
2 slab and reviewing all works to ensure everything was built as per
the drawings. Once the walk was done, issued the report of the
remaining works to the structural contractors.

Site walk with James.

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.

Updated my programme following James review and progress on


site.

Completed Mid placement review with James.

Site walk with James.

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.

13/01/201
7

13/01/201
7
14/01/201
7
14/01/201
7

14/01/201
7
14/01/201
7

16/01/201
7
16/01/201
7

16/01/201
7
16/01/201
7
17/01/201
7
17/01/201
7

17/01/201
7

Sat in to the internal site meeting, took notes in order to complete


the minutes for James review.

Assisted site structure foreman with completing the remaining


works to tower C basement 1 pour 6 slab, prior to the engineer
inspecting the slab.

Walked with the engineer who was inspecting the slab and
reviewing all works to ensure everything was built as per the
drawings. Once the walk was done, issued the report of the
remaining works to the structural contractors.

Site walk with James.

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.

18/01/201
7

Sat in subcontractor meeting, and took notes to prepare meeting


minutes.

18/01/201
7

Updated subcontractor meeting minutes for James review. And


issued to the minutes to the relevant subcontractors.

DATE

HOURS

17/01/201
7
17/01/201
7

18/01/201
7
18/01/201
7

19/01/201
7
19/01/201
7

ACTIVITY / ACHIEVEMENT

Site walk with James.

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.

19/01/201
7

Assisted the tower B foreman to enter the level 1 structural defect


within the online system onsite.

19/01/201
7

Assisted the tower A foreman to enter the level 1 structural defect


within the online system onsite.

Site walk with James.

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.

Complete Pre-Pour ITP. Checked final formwork installation for any


defects. Noted that 3 terminating columns had reo protruding
above the level of the deck reo. Steel-fixing contractors attended to
the issue and cut away the protruding steel and replaced it with 10x
N16 L-Bars.

20/01/201
7
20/01/201
7

20/01/201
7

20/01/201
7
21/01/201
7
21/01/201
7

2
2

Site walk with James.

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.

Inspected the EMF shielding for signs of rust and damage prior to
the installation of a waterproofing membrane. All surfaces
inspected were free from rust and damage.

Inspected to tower A Level 3 pour 1 columns and related formwork.


Assisted site foreman in completing ITP.

Site walk with James.

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.

Inspected the Water Proofing installed over the EMF Shielding on


A-GF-1. Areas of the shielding had significant air gaps between the
layers of material, which will become an issue when covering
concrete is poured in 2 days. An epoxy will be applied prior to the
pour to ensure a strong bond between the water proofing material
and the concrete.

23/01/201
7

Assisted the supervision of the final 2 hours of the concrete pour to


level 4 pour 1.

23/01/201
7

Assisted the tower B foreman to enter the level 2 structural defects


within the online system onsite.

Site walk with James.

Meet with the contractor responsible for the concrete used to seal
the EMF on A-GF. An issue was raised on the 21st regarding a
delivery of Concrete that was turned away due to the site not
prepared to receive it.

Issued reinforcement delivery confirmation report to our supplier


following consultation with James. Contacted Reinforcement
supplier to get the delivery time for tomorrows reinforcement.
Passed on this information to James.

24/01/201
7

Sat in to the internal site meeting, took notes in order to complete


the minutes for James review.

24/01/201
7

Completed Final placement review with James.

21/01/201
7
21/01/201
7
23/01/201
7
23/01/201
7

23/01/201
7

24/01/201
7
24/01/201
7

24/01/201
7