You are on page 1of 11

Shell Albian Sands

Area/Location

520 Aux Boilers

Procedure Number:
OS-OCA Number:

Title

Coupling Change out on Fan Driver of


Aux Boilers

Revision Number:

1.
0

Issue Date:
Approved By:

Classification

In Hand

Equipment Name:

Type

Normal

Page 1 of 5

Purpose

Allow to help one install, align and maintain the coupling

Prerequisites

Once approved, this document supersedes all other work practices when applicable. For points not
covered in this document, the respective work practice(s) still apply.

All personnel are familiar with the reason for this procedure.

Trained, qualified and competent personnel will perform the work.

Discuss and arrange with Froth PUS to ensure Froth Operators are available for Fire Watch in their unit
during job and Froth PTL is well informed.

Follow requirements of SCWP0006 Hazard Assessment Work Practice

Follow requirements of SCWP0016 Ladders

Follow requirements of SCWP0022 Mechanical Lifting and Hoisting

Follow requirements of SCWP0026 Energy Isolation.

Follow requirements of SCWP0008 Confined Space Entry Work Practice for assessment of space and
requirements for monitoring.

Follow requirements of SCWP0035 Gas Testing.

Follow requirements of SCWP0034 Diving Operations.

HSSE Requirements

Maintenance, Operations and Contractor Personnel understand the restrictions of this procedure.

All pertinent personnel are confined space entry/monitor trained.

Approved completed JSA

520 Aux Boilers

In Hand: Normal

References

SCWP0006 Hazard Assessment Work Practice

SCWP0008 Confined Space Entry Work Practice

SCWP0016 Ladders

SCWP0022 Mechanical Lifting and Hoisting

SCWP0026 Energy Isolation

SCWP0035 Gas Testing

SCWP0034 Diving Operations

Appendix A: Equipment Staging Layout

Activities
1.

Stage diving team's equipment and personnel appropriately.

Issue Date: 26.05.2016


This document is uncontrolled after printing.

Rev. 1.0

Page 2 of 11

520 Aux Boilers

In Hand: Normal

2.

Commission temporary jockey pump and isolate FW system.

3.

Commence diving and retrieval of the fallen pump.

4.

Hoist the pump out of the wet well and remove out of the pumphouse while
reinstating the FW system back to normal operation.

5.

Emergency procedure if FW system is required while work is being performed.

1. Stage diving team's equipment and personnel appropriately.


Step

Action
By

Action

Information

1.1

Diving
Contractor

Stage all above-surface diving


equipment as shown in Appendix A.

1.2

FO

Perform initial gas testing of the


confined space wet well access port
and prepare the area for confined space
entry as per work practice.

1.2

Diving
Contractor

Lower the floater bag down into the wet


well through the access port at the north
side of the wet well.

Utilize overhead hoist


and/or Shell
Maintenance support if
required.

1.3

Shell Maint.

Stage above-surface rigging and


removal equipment as shown in
Appendix A.

Avoid cluttering
emergency access
routes.

1.4

ERT

Stage emergency response equipment


and personnel as per Rescue Plan at
pumphouse.

Date
/
Initial

Avoid cluttering
emergency access
routes.

2. Commission and start temporary jockey pump and isolate FW system.


Step

Action By

2.1

Temp.
Pump
Contractor

Action

Information

Commission and start temporary


jockey pump as per MOC 11226.

Issue Date: 26.05.2016


This document is uncontrolled after printing.

Rev. 1.0

Date /
Initial

Allow 15 minutes for


the pump to reach rated
performance.

Page 3 of 11

520 Aux Boilers

In Hand: Normal

2. Commission and start temporary jockey pump and isolate FW system.


Step

Action By

Action

Information

2.2

Utilities
PTL

Inform Froth PTL that the Fire Water


System is being shutdown down and to
correctly position his Operators in
LTFT, HTFT, and the Tank Farm for
Fire Watch.

~Froth Ops to call


Utilities Operator
(Operator at job) on G2 if a fire is spotted
~This is to help reduce
the time it takes to
remove the driver from
the Wetwell and return
the system to service.

2.3

FO

Turn off 541-PU-042B jockey pump


and monitor the header pressure.

Continue monitoring the


header pressure for
~30min to ensure that
temporary jockey pump
is functioning
adequately.

2.4

FO

Isolate the FW system by:


a) Removing the positive battery leads
off both diesel engine battery packs
(541-PU-044A and 541-PU-044B) and
closing the first butterfly block valve
upstream of each pump.
b) Opening the 600V breaker on
electric pump (541-PU-043) and
closing the first butterfly block valve
upstream of the pump.
c) Opening the breaker on both jockey
pumps (541-PU-042A and 541-PU042B) and closing the first butterfly
block valve upstream of each pump.

With all the available


pumps isolated and
respective check valves
holding to prevent back
flow, all energy sources
in the wet well have
been removed. As
such, the wet well is
deemed safe for diving
operation. No further
isolation points and/or
blinds required.

2.5

FO

Operations to install isolation and


remote lock box.

~Remote Lock Box to


be with the assigned
operator while the
driver is in the wetwell.

Date /
Initial

Note: During step 2.3, if the header pressure falls too low, the main electric FW pump (541-PU-043)
may start. In this case, restart the main jockey pump (541-PU-042B), open its discharge valve, shut
off the temporary jockey pump and reset the main electric pump (541-PU-043).
If the header pressure goes too high (>1000 kPa), then restart the main jockey pump, open its
discharge valve, and shut off the temporary jockey pump.
In either of these two cases, consult with PS and Engineer before proceeding with the rest of this
procedure.

Issue Date: 26.05.2016


This document is uncontrolled after printing.

Rev. 1.0

Page 4 of 11

520 Aux Boilers

In Hand: Normal

3. Commence diving into the wet well and locate the fallen pump.
Step

Action By

Action

3.1

Diving
Contractor

Perform pre-dive safety and


communication checks as per
contractor specifications.

3.2

Diver(s)

Lock onto the remote lock box.

3.3

Diver

Enter the wet well and perform initial


hazard assessment of the wet well.

Dive around the wet


well, identify and report
any potential obstacles
and hazards.

3.4

Diver

Locate the fallen pump and report


back the orientation of the pump.

This information will


be used to determine
a safe rigging and
lifting plan.

3.5

All

Discuss and agree upon a safe


rigging and lifting plan.

3.6

Diver

Rig up the fallen pump to the floater


bag and lift the pump to the surface.

3.7

All

Once the pump is securely lifted to


the surface, it should be moved
towards the wet well access port by
either pulling it from up above or
pushing it in the wet well.

Issue Date: 26.05.2016


This document is uncontrolled after printing.

Information

Rev. 1.0

Date /
Initial

Diver to remain at
least 20ft away from
the pump when it's
being lifted. At no
point should the diver
be under the
suspended load.
Follow fill procedure
for filling floater bag
provided by the
vendor.

Page 5 of 11

520 Aux Boilers

In Hand: Normal

4. Hoist the pump out of the wet well and remove out of the pumphouse.
Step

Action By

Action

4.1

Shell Maint.

Lower the 3/4 ton hoist into the wet


well access port.

4.2

Diver

Diver to securely rig up the pump to the


hoist.

4.3

Shell Maint.

Lift up the pump slightly to ensure that


it's been rigged up adequately.

Diver should move 20ft


away from the pump
when it's being lifted.

4.4

Diver

Once the secure rigging is confirmed,


diver should unhook the pump from the
floater bag.

At no point should the


diver be under the
suspended load.

4.5

Diver

Exit the wet well and remove all diving


equipment and lifelines away from the
access port.

This is to make room


for the pump to be lifted
out of the wet well.

4.6

Diver(s)

Remove personal lock from remote


lock box

4.7

FO

Remove car seal from remote lock box


and remove isolation locks

4.8

FO

De-isolate jockey pump 541-PU-042B


by opening closed butterfly valve and
then closing the breaker. Turn on the
pump.

4.9

Temp.
Pump
Contractor

Shut off the temporary jockey pump.

4.10

FO

Monitor the header pressure and wait


until it stabilizes at 860 kPa.

4.11

FO

De-isolate the main FW pumps by:


a) Reattaching the battery leads and
opening the closed butterfly valves on
541-PU-044A/B (diesel pumps) and
placing the pumps in Auto mode.
b) Closing the 600V breaker and
opening the closed butterfly valve on
541-PU-043 (electric Pump).

4.11

Utilities
PTL

Inform Froth PTL that the Fire Water


system is back in service and that the
Fire Watch is not required anymore

4.12

Diving
Contractor

Decontaminate diver as per vendor


specifications.

4.13

ERT

With the diver out of the wet well, move


all emergency response equipment out
away from the access port.

Issue Date: 26.05.2016


This document is uncontrolled after printing.

Information

Rev. 1.0

Date /
Initial

This is to make room


for the pump to be lifted
out of the wet well.
Page 6 of 11

520 Aux Boilers

In Hand: Normal

4. Hoist the pump out of the wet well and remove out of the pumphouse.
Step

Action By

Action

4.14

Shell Maint.

Place appropriately sized pallets near


the wet well access port.

4.15

Shell Maint.

Lift up the pump out of the wet well


through the access port and tilt it onto
the pallets.

4.16

Shell Maint.

Move the pump out of the FW


Pumphouse through the main the
overhead door.

4.17

Mech.
Engineer

Confirm that the pump assembly


contains all the parts.

Issue Date: 26.05.2016


This document is uncontrolled after printing.

Information

Rev. 1.0

Date /
Initial

The pump will be


placed on top of these
pallets.

This is to ensure that


no large component of
the pump is left behind
in the wet well.

Page 7 of 11

520 Aux Boilers

In Hand: Normal

Note: If a large component of the pump is deemed to be left behind inside the wet well, the
diver may be asked to go back into the wet well, search for it and to retrieve. In this case,
repeat tasks 1, 2, 3 and 4 until all large pump components are accounted for.
4.18

Temp.
Pump
Contractor

Decommission and remove temporary


jockey pump skid.

Issue Date: 26.05.2016


This document is uncontrolled after printing.

Rev. 1.0

Page 8 of 11

520 Aux Boilers

In Hand: Normal

Note: If ERT demands the FW system to be reinstated for any reason during this work, then
the diver shall exit the wet well as soon as possible. Only then can the field operator deisolate the main fire water pumps.

Issue Date: 26.05.2016


This document is uncontrolled after printing.

Rev. 1.0

Page 9 of 11

520 Aux Boilers

In Hand: Normal

5. Emergency procedure if FW system is required while work is being performed.


Step

Action By

Action

5.1

Diver

Exit the wet well immediately

5.2

Diver(s)

Remove personal lock from remote


lock box

5.3

FO

Remove Carseal from Remote Lock


Box and remove locks from Electric
Fire Pump 541-PU-043

5.3

FO

Open closed butterfly valve on electric


pump (541-PU-043) and close the
600V breaker.

~Pump should start


immediately.
~If pump does not start
check pump panel and
try to start the pump
form the panel.
~If Operator cannot get
the pump to start with a
minute continue on to
next step and de-isolate
the Diesel fire pumps.

5.5

FO

Open closed butterfly valve on diesel


pump 541-PU-044A and reattach the
battery leads and place the pump in
Auto mode.

~Pump should start if


required (header
pressure below
755kPa)
~If pump doesnt
automatically start at
this header condition,
Operator is to force
pump on at the local
panel or by using the
manual cranks.

5.6

FO

Open closed butterfly valve on diesel


pump 541-PU-044B and reattach the
battery leads and place the pump in
Auto mode.

~Pump should start if


required (header
pressure below
685kPa)
~If pump doesnt
automatically start at
this header condition,
Operator is to force
pump on at the local
panel or by using the
manual cranks.

Issue Date: 26.05.2016


This document is uncontrolled after printing.

Information

Rev. 1.0

Date /
Initial

Page 10 of 11

520 Aux Boilers

In Hand: Normal

Execution Review and


Confirmation

Role

Pre-Execution

Lead

Post-Execution

Lead

Initials

Procedure Comments:

Document History
02-07-2015 Rev. 0.0 / Ben Azampour
08-07-2015 Rev 1.0 / Angela Nickel
11-07-2015 Rev 2.0 / Shawn Aucoin

Approval
Date:
Name:

Peter Hunter

Title:

Utilities Plant Production Unit Manager

Signature:

Issue Date: 26.05.2016


This document is uncontrolled after printing.

Rev. 1.0

Page 11 of 11

You might also like