KANDY

CONSTRUCTIONS
A

METHOD OF
STATEMENT
MECHANICAL
WORKS

2016

CONTENTS
M - 01

Method of Statement

Under ground drainage

M - 02

Method of Statement

Installation of high level drainage

M - 03

Method of Statement

Installation of water supply line at


High level

M - 04

Method of Statement

Installation of water supply line at


High level

M - 05

Method of Statement

Installation of Booster pump

M - 06

Method of Statement

Installation of Transfer pump

M - 07

Method of Statement

Installation of Submersible pump

M - 08

Method of Statement

Installation of Fire pump

KANDY CONSTRUCTIONS

Page 16

METHOD STATEMENT M 01

UNDER GROUND DRAINAGE PIPE WORK


1.0

Purpose
To define the method of installation of underground pipe work.

2.0

Scope
This method is applicable for drainage pipe work below ground.

3.0

Method
3.1

Preparation Work
3.1.1 Check the trench route to be made to ensure that the pipes
to be installed are as indicated on approved construction
drawings.
3.1.2 Check the materials to be used are as per the approved
make.
3.1.3 Levelling of ground before excavation to be done by the
main contractor.
3.1.4 Excavate the trench as per the route marked on approved
drawing. The trench bed must be compacted smooth and
must be free from foreign particles
3.1.5 Check whether the inside portion of pipe is properly cleaned
before installation / fit up.
3.1.6 Place concrete blocks at standard distance to support the
Pipes.
3.1.7 Lay the pipes as per the invert levels & slope mentioned in
the approved layout with proper supports, using the water
level & measuring tape with respect to the benchmark level.
3.1.8

Inspection of pipe work and levels to be checked.

3.1.9 Tangent Glue is applied on the pipe after cleaning it and


abrading the surface to roughness using sand paper and left
for few minutes to dry it.
3.1.10 Inspect the pipe work for leakage by gravity leakage test.
(by Consultant)

KANDY CONSTRUCTIONS

Page 16

3.1.11 Make bedding up to the bottom level of the pipe with aggregate and
compact properly.
3.1.12 Cover the pipe (up to top level) with aggregate as per
standards.
4.0

Reference documents
4.1

5.0

the

Approved shop drawings.

Inspection and Measuring Equipment Used


5.1 Spirit level.
5.2 Water level.
5.3 Measuring tape

6.0

Safety
6.1.1 Safety equipment (example Hard hats, Safety shoes, Coverall gloves,
Goggles when necessary etc) to be worn all the times.

KANDY CONSTRUCTIONS

Page 16

METHOD STATEMENT M 02

INSTALLATION OF PIPE WORK AT HIGH LEVEL (DRAINAGE)


1.0

Purpose
This method of statement is to define the installation of Pipe work at high level.

2.0

Scope
This method of statement is applicable for installation of Pipe works at high level
for drainage pipe works.

3.0

Installation Procedure
3.1.1 Installation of pipes
3.1.2 Mark out the location of hanger thread rods for pipe installation
as per the approved construction drawing.
3.1.3 Drill the marked position for hangers and supports by using the drill bit
of appropriate size.
3.1.4 Fix the unfix anchor at drilled position by gentle and uniformly
hammering.
3.1.5 Fix the threaded rod of 6mm diameter appropriate size & length in the
anchor by twisting by turning.
3.1.6 After fixing the threaded rod, insert a 6mm diameter washer of
appropriate size in to the rod.
3.1.7 Finally fix the washer near to the slab by tightening a nut over it, this
will improve the strength and load bearing capacity of threaded rod.
3.1.8 After cutting the pipes in the required length, both ends should be
chamfered properly to remove the unevenness and surface is made
rough using sand paper for length of 3 cm (approx) for good adhesive
surface preparations.
3.1.9

Install the pipe in position as per the approved layout and make the
end connection of pipes as standard specification for each service.

3.1.10 After completion of pipe end connection, fix / tight the support clamps
properly to make the pipe straight and level as per the layout.
3.1.11 Check the levels of pipe work with spirit levels and measuring tape.
KANDY CONSTRUCTIONS

Page 16

3.1.12 Pressure test and final inspection of the pipe work (by Consultant) as
per the testing philosophy ref.
4.0

Reference Documents
4.1

5.0

Inspection and Measuring Equipment Used


5.1
5.2
5.3

6.0

Pressure gauge
Level gauge / Spirit level.
Measuring tape

Equipment Required
6.1
6.2
6.3
6.4

7.0

Shop Drawings

Electric Drill Machine


Grinder
Electric Cutting Machine
Pressure test pump.

Safety
Safety equipment (example Hard hats, Safety shoes, Coverall Gloves,
Goggles when necessary etc) to be worn all the times.

KANDY CONSTRUCTIONS

Page 16

METHOD STATEMENT M 03

INSTALLATION OF PIPE WORK AT HIGH LEVEL (WATER SUPPLY)


3.0

Purpose
This method of statement is to define the installation of Pipe work at high level.

4.0

Scope
This method of statement is applicable for installation of Pipe works at high level
for water supply pipe works.

3.0

Installation Procedure
3.1.1 Installation of pipes
3.1.13 Mark out the location of hanger thread rods for pipe installation
as per the approved construction drawing.
3.1.14 Drill the marked position for hangers and supports by using the drill bit
of appropriate size.
3.1.15 Fix the unfix anchor at drilled position by gentle and uniformly
hammering.
3.1.16 Fix the threaded rod of 6mm diameter appropriate size & length in the
anchor by twisting by turning.
3.1.17 After fixing the threaded rod, insert a 6mm diameter washer of
appropriate size in to the rod.
3.1.18 Finally fix the washer near to the slab by tightening a nut over it, this
will improve the strength and load bearing capacity of threaded rod.
3.1.19 After cutting the pipes in the required length, both ends should be
chamfered properly to remove the unevenness and surface is made
rough using sand paper for length of 3 cm (approx) for good adhesive
surface preparations.
3.1.20 Install the pipe in position as per the approved layout and make the
end connection of pipes as standard specification for each service.
3.1.21 After completion of pipe end connection, fix / tight the support clamps
properly to make the pipe straight and level as per the layout.
KANDY CONSTRUCTIONS

Page 16

3.1.22 Check the levels of pipe work with spirit levels and measuring tape.
3.1.23 Flow and Leakage test and final inspection of the pipe work (by
Consultant) as per the testing philosophy ref.
4.0

Reference Documents
4.1

5.0

Inspection and Measuring Equipment Used


5.1
5.2
5.3

6.0

Pressure gauge
Level gauge / Spirit level.
Measuring tape

Equipment Required
6.1
6.2
6.3
6.4

8.0

Shop Drawings

Electric Drill Machine


Grinder
Electric Cutting Machine
Pressure test pump.

Safety
Safety equipment (example Hard hats, Safety shoes, Coverall Gloves,
Goggles when necessary etc) to be worn all the times.

KANDY CONSTRUCTIONS

Page 16

METHOD STATEMENT M 04

INSTALLATION OF PIPE WORK AT HIGH LEVEL (FIRE FIGHTING)


5.0

Purpose
This method of statement is to define the installation of Pipe work at high level.

6.0

Scope
This method of statement is applicable for installation of Pipe works at high level
for fire fighting pipe works.

3.0

Installation Procedure
3.1 Installation of pipes
3.1.2 Mark out the location of hanger thread rods for pipe installation
as per the approved construction drawing.
3.1.3 Drill the marked position for hangers and supports by using the drill bit
of appropriate size.
3.1.4 Fix the unfix anchor at drilled position by gentle and uniformly
hammering.
3.1.5 Fix the threaded rod of 6mm diameter appropriate size & length in the
anchor by twisting by turning.
3.1.6 After fixing the threaded rod, insert a 6mm diameter washer of
appropriate size in to the rod.
3.1.7 Finally fix the washer near to the slab by tightening a nut over it, this
will improve the strength and load bearing capacity of threaded rod.
3.1.8 After cutting the pipes to the required length, if the diameter of the pipe
is less than 2.5 inch both ends should be threaded by using a
threading machine and for pipe diameter above 2.5 inch the pipes are
groove cut to the required depth as per the installation specification.
3.1.9 The pipes are connected to each other using a grooved coupler
as per the standard pipe installation procedure.
3.1.10 After completion of pipe end connection, fix / tight the support clamps
properly to make the pipe straight and level as per the layout.
KANDY CONSTRUCTIONS

Page 16

3.1.11 Check the levels of pipe work with spirit levels and measuring tape.
3.1.12 Flow and Leakage test and final inspection of the pipe work (by
Consultant) as per the testing philosophy ref.
4.0

Reference Documents
4.1

5.0

Inspection and Measuring Equipment Used


5.1
5.2
5.3

6.0

Pressure gauge
Level gauge / Spirit level.
Measuring tape

Equipment Required
6.1
6.2
6.3
6.4
6.5

9.0

Shop Drawings

Electric Drill Machine


Threading Machine
Electric Cutting Machine
Pressure test pump.
Grooving Machine

Safety
Safety equipment (example Hard hats, Safety shoes, Coverall Gloves,
Goggles when necessary etc) to be worn all the times.

KANDY CONSTRUCTIONS

Page 16

METHOD STATEMENT M - 05

INSTALLATION OF BOOSTER PUMP


1.0

Purpose
To define the method of installation of Booster pump

2.0

Scope
This method is applicable for installation of Booster pump.

3.0

Method
3.1 Check the plinth for the Booster pump is of required size.
3.2 Booster pump installation works shall be carried out in accordance
with the specification.
3.3 Fixing position shall be marked out on the concrete base.
3.4 Rubber pad shall be laid before fixing the pump.
3.5 Pump installation shall be completed according to the manufactures
recommendation.
3.6. The size of the suction pipe shall be as per manufactures
.recommendation
3.7 Discharge side shall be connected to the water supply network of the
building through pressure gauge and isolating valve
3.8 The suction & discharge side of the Pump shall be connected to flexible
connector
3.9 Anti-vibration pad shall be fixed to the pump

4.0

Reference documents
4.1
4.2

5.0

Approved Drawings.
Approved Material Submittal.

Inspection and Measuring Equipment Used


4.1 Pressure Gauge, Measuring tape, Spirit level.
KANDY CONSTRUCTIONS

Page 16

6.0

Safety
6.1Safety equipment (example Hard hats, Safety shoes, Coverall,
Gloves, Goggles when necessary etc) to be worn all the times.

KANDY CONSTRUCTIONS

Page 16

METHOD STATEMENT M - 06

INSTALLATION OF TRANSFER PUMP


1.0

Purpose
To define the method of installation of Transfer pump

2.0

Scope
This method is applicable for installation of transfer pump.

3.0

Method
3.1 Check the plinth for the transfer pump is of required size.
3.2 Transfer pump installation works shall be carried out in accordance
with the specification.
3.3 Fixing position shall be marked out on the concrete base.
3.4 Rubber pad shall be laid before fixing the pump.
3.5 Pump installation shall be completed according to the manufactures
recommendation.
3.6 The suction side of the pump shall be connected to foot valve and
.

Isolating valve with suction pipe. The size of the suction pipe shall be as
per manufactures recommendation.

3.7 Discharge side shall be connected to the water supply network of the
building through pressure gauge and isolating valve
3.8 The suction & discharge side of the Pump shall be connected to flexible
connector
3.9 Anti-vibration pad shall be fixed to the pump

4.0

Reference documents
4.1
4.2

Approved Drawings.
Approved Material Submittal.

KANDY CONSTRUCTIONS

Page 16

5.0

Inspection and Measuring Equipment Used


4.2 Pressure Gauge, Measuring tape, Spirit level.

6.0

Safety
6.1Safety equipment (example Hard hats, Safety shoes, Coverall,
Gloves, Goggles when necessary etc) to be worn all the times.

KANDY CONSTRUCTIONS

Page 16

METHOD STATEMENT M - 07

INSTALLATION OF SUBMERSIBLE PUMP


1.0

Purpose
To define the method of installation of submersible pump

2.0

Scope
This method is applicable for installation of submersible pump.

3.0

Method
3.1 Check the support for the submersible pump is of proper size.
3.2 Submersible pump installation works shall be carried out in
accordance with the specification.
3.3 Fixing position shall be marked out on the manhole wall.
3.4 Pump installation shall be completed according to the manufactures
recommendation.
3.5 The suction side of the pump shall be connected with alarm switch,
Float valve and isolating valve. The pipe size to be as per the pump
Manufacturers recommendation.
3.6 Discharge side shall be connected through the pressure chamber
To the adjacent manhole

4.0

Reference documents
4.1
4.2

5.0

Approved Drawings.
Approved Material Submittal.

Inspection and Measuring Equipment Used


4.3 Pressure Gauge, Measuring tape, Spirit level.

6.0

Safety
6.1Safety equipment (example Hard hats, Safety shoes, Coverall,
KANDY CONSTRUCTIONS

Page 16

Gloves, Goggles when necessary etc) to be worn all the time.


METHOD STATEMENT M 11

INSTALLATION OF FIRE HOSE REEL PUMP


1.0

Purpose
To define the method of installation and operation of fire hose reel pump.

2.0

Scope
This method is applicable for installation and operation of fire hose reel pump.

3.0

Method
3.1

Check the foundation is ready as indicated on approved


Construction drawing.

3.2

Check the level of suction pipe line is to be below the level of


pump(suction header)

3.3

Check whether the required piping and valves are installed properly

3.4

Make sure that electrical panel for the pump is given correct power
Supply with protection.

3.5

Load the pump on a strong foundation. Use the expansion bolts to the
base frame to the concrete foundation. The surface of the foundation
should be smooth and level. Ensure easy access to the unit from all sides
for maintenance and services.

3.6

Pump set is accurately aligned in the factory before dispatch. However it is


essential to recheck the alignment at site after fixing pump set on the site.

3.7

The pump set should be located near to the suction reservoir.

3.8

Fix the gate valves non return valves vibration protected flexible connector
etc and suction discharge manifolds as shown on the dawning.

3.9

Connect the suction and discharge line to the manifold .check whether all
joints are straight.

3.10

Fix the pressure switch and pressure gauge on the discharge header.

3.11

Fill the water in the pump and suction line through the priming valve and
remove all the air blocks.

3.12

Interconnecting wiring between the panel and motor diesel engine


pressure switches float switches for dry run protection etc should be done.
KANDY CONSTRUCTIONS

Page 16

Panel, motors pressure switches and float switches must be grounded


with suitable wires.

4.0

3.13

Do the wiring from electrical supply source to the pump control panel.

3.14

Do the necessary piping between the fuel tank and diesel tank.

3.15

After installation has been completed an operational test has to be


conducted to ensure the proper operation of the pump set.

3.16

Keep starting point of electrical pump slightly higher than the starting point
of diesel pump. Keep starting point of jockey pump is slightly higher than
starting point of electrical pump.

Reference documents
4.1 Approved Drawings.

5.0

Inspection and Measuring Equipment Used


5.1 Pressure Gauge.
5.2 Spirit level.
5.3 MultiMate

6.0

Safety
6.1 Safety equipment (example Hard hats, Safety shoes, Coverall gloves,
Goggles when necessary etc) to be worn all the times.

KANDY CONSTRUCTIONS

Page 16