You are on page 1of 66

CHAPTER NO.

10

FLOORING
i) Rates for all finished works include the removal of surplus debris, unused
material and by products.

ii) For handling of all types of material for short lead including carriage upto
3 chains (90m) nothing is to be paid as extra. Where handling and carriage
involves an extra lead beyond 3 chains, (90m) carriage for whole of the distance
should be paid

DESCRIPTION OF ITEM
1 Laying Muram flooring consisting of 1" (25m) layer of fine powdery or flakey variety of Muram
laid over 6" (150mm) good hard layer of Muram spreaded over 9" (225mm) thick sub base
comprising of hand packed rubble or broken bricks properly watered and rammed provided
over well rammed earth

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 9" thick rubble or broken hard bricks 80.00 Cft 560.00 Per 100 Cft 448.00
2 6" Hard Muram 55.00 Cft 520.00 Per 100 Cft 286.00
3 1" Fine Powdery Muram 9.00 Cft. 550.00 Per 100 Cft 49.50
Total 783.50
Contractor's Profit & Overheads 20 Percent 156.70
Total 940.20

LABOUR

Mason 0.50 No. 300.00 per day 150.00


Coolies 3.00 Nos. 140.00 per day 420.00
Bahishti 0.5 No. 160.00 Per day 80.00
Total 650.00
Sundries 10 Percent 65.00
Total 715.00
Contractor's Profit & Overheads 20 Percent 143.00
Total 858.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. 858.00 Say 858.00


Labour Rate Per Sqm. Rs. 92.32 Say 92.30
Composite Rate per 100 Sft. Rs. 1,798.20 Say 1798.20
Composite Rate per Sqm. Rs. 193.49 Say 193.50

Page 1
DESCRIPTION OF ITEM

2 Earth flooring consisting of 6" thick consolidated layer of moistured


earth including ramming

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Earth (Loose measured) 50.00 Cft 150.00 Per 100 Cft 75.00
Contractor's Profit & Overheads 20 Percent 15.00
Total 90.00

LABOUR

Mason 0.125 No. 300.00 Per day 37.50


Coolly 1.00 No. 140.00 Per day 140.00
Bahishti 0.25 No. 160.00 Pay day 40.00
Total 217.50
Sundries 10 Percent 21.75
Total 239.25
Contractor's Profit & Overheads 20 Percent 47.85
Total 287.10

ITEM RATE

Labour Rate Per 100 Sft. Rs. 287.10 Say 287.10


Labour Rate Per Sqm. Rs. 30.89 Say 30.90
Composite Rate per 100 Sft. Rs. 377.10 Say 377.10
Composite Rate per Sqm. Rs. 40.58 Say 40.60

Page 2
DESCRIPTION OF ITEM

3 Providing, laying, watering and ramming brick ballast 1½" - 2" gauge mixed with
25% sand, for floor foundation, complete in all respects.

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Brick Ballast 100.00 Cft 560.00 Per 100 Cft 560.00


2 Sand 25.00 Cft 350.00 Per 100 Cft 87.50
Total 647.50
Contractor's Profit & Overheads 20 Percent 129.50
Total 777.00

LABOUR

Coolies 3.10 No. 140.00 per day 434.00


Bahishti 0.10 No. 160.00 Per day 16.00
Total 450.00
Sundries 10 Percent 45.00
Total 495.00
Contractor's Profit & Overheads 20 Percent 99.00
Total 594.00

ITEM RATE

Labour Rate Per 100 Cft. Rs. 594.00 Say 594.00


Labour Rate Per Cum Rs. 209.80 Say 209.80
Composite Rate per 100 Cft. Rs. 1,371.00 Say 1371.00
Composite Rate per Cum. Rs. 484.24 Say 484.25

Page 3
4 Mud Flooring

DESCRIPTION OF ITEM

Mud flooring consisting of 6" thick consolidated layer of moistured earth and
finished off with 1" mud plaster and gobri leeping.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Earth for filling 50.00 Cft 150.00 Per 100 Cft 75.00
2 Earth for Mud Plaster 10.00 Cft 150.00 Per 100 Cft 15.00
3 Bhoosa 34 lbs (15.44 Kg.) 2.00 Kg. 30.88
4 Fine Clay for Gobri Leeping 0.75 Cft. 150.00 Per 100 Cft 1.13
5 Cow Dung 0.75 Cft. (5.44 Kg.) 50.00 Per 100 Kg. 2.72
Total 124.73
Contractor's Profit & Overheads 20 Percent 24.95
Total 149.67

LABOUR

Mason 0.25 No. 300.00 Per day 75.00


Coolies 2.00 No. 140.00 Per day 280.00
Bahishti 0.25 No. 160.00 Per day 40.00
Total 395.00
Sundries 10 Percent 39.50
Total 434.50
Contractor's Profit & Overheads 20 Percent 86.90
Total 521.40

ITEM RATE

Labour Rate Per 100 Sft. Rs. 521.40 Say 521.40


Labour Rate Per Sqm. Rs. 56.10 Say 56.10
Composite Rate per 100 Sft. Rs. 671.07 Say 671.05
Composite Rate per Sqm. Rs. 72.21 Say 72.20

Page 4
5 Brick Flooring

DESCRIPTION OF ITEM

Dry brick paving laid flat, sand grouted including preparation of bed by watering, ramming and
bringing the same to proper camber by ½" mud plaster

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Brick 9" 350 Nos. 1200.00 Per 1000 No. 420.00


2 Sand 5 Cft. 350.00 Per 100 Cft 17.50
3 ½" Mud Plaster (Good earth) 6 Cft. 150.00 Per 100 Cft 9.00
Total 446.50
Contractor's Profit & Overheads 20 Percent 89.30
Total 535.80

LABOUR FOR 125 SFT.

Mason 0.50 No. 300.00 Per day 150.00


Coolies 1.00 No. 140.00 Per day 140.00
Bahishti 0.05 No. 160.00 Per day 8.00
Total 298.00
Sundries 10 Percent 29.80
Total 327.80
Contractor's Profit & Overheads 20 Percent 65.56
Total 393.36

ITEM RATE

Labour Rate Per 100 Sft. Rs. 314.69 Say 314.70


Labour Rate Per Sqm. Rs. 33.86 Say 33.85
Composite Rate per 100 Sft. Rs. 850.49 Say 850.50
Composite Rate per Sqm. Rs. 91.51 Say 91.50

Page 5
DESCRIPTION OF ITEM

6 Dry brick on edge paving sand grouted including preparation of bed by watering,
ramming and bringing the same to proper camber by ½ thick mud plaster

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Brick 9" (including wastage) 525 Nos. 1200.00 Per 1000 Nos. 630.00
2 ½" thick mud plaster (good earth) 6 Cft. 150.00 Per 100 Cft 9.00
2 Sand 6 Cft. 350.00 Per 100 Cft 21.00
Total 660.00
Contractor's Profit & Overheads 20 Percent 132.00
Total 792.00

LABOUR

Mason 0.67 No. 300.00 Per day 201.00


Coolies 1.50 No. 140.00 Per day 210.00
Bahishti 0.08 No. 160.00 Per day 12.80
Total 423.80
Sundries 10 Percent 42.38
Total 466.18
Contractor's Profit & Overheads 20 Percent 93.24
Total 559.42

ITEM RATE

Labour Rate Per 100 Sft. Rs. 559.42 Say 559.40


Labour Rate Per Sqm. Rs. 60.19 Say 60.20
Composite Rate per 100 Sft. Rs. 1,351.42 Say 1351.40
Composite Rate per Sqm. Rs. 145.41 Say 145.40

Page 6
DESCRIPTION OF ITEM

7 Grouting 4½" dry brick work with cement mortar ratio 1:5

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 0.70 Bag 230.00 Per Bag 161.00


2 Sand 4.50 Cft. 350.00 Per 100 Cft 15.75
Total 176.75
Contractor's Profit & Overheads 20 Percent 35.35
Total 212.10

LABOUR FOR 125 SFT

Mason 0.50 No. 300.00 Per day 150.00


Coolies (Unskilled) 0.50 No. 140.00 Per day 70.00
Bahishti 0.50 No. 160.00 Per day 80.00
Total 300.00
Sundries 10 Percent 30.00
Total 330.00
Contractor's Profit & Overheads 20 Percent 66.00
Total 396.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. 316.80 Say 316.80


Labour Rate Per Sqm. Rs. 34.09 Say 34.10
Composite Rate per 100 Sft. Rs. 528.90 Say 528.90
Composite Rate per Sqm. Rs. 56.91 Say 56.90

Page 7
DESCRIPTION OF ITEM

8 Flat brick flooring laid in 1:6 cement mortar over a bed of 3/4" thick cement mortar 1:6

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Bricks 9" size 350 Nos. 1200.00 Per 1000 No. 420.00
2 Cement (for laying) 0.50 Bag 230.00 Per Bag 115.00
3 Cement (for bedding mortar) 0.80 Bag 230.00 Per Bag 184.00
4 Sand for laying 4.00 Cft. 350.00 Per 100 Cft 14.00
5 Sand for bedding mortar 6.00 Cft. 350.00 Per 100 Cft 21.00
Total 754.00
Contractor's Profit & Overheads 20 Percent 150.80
Total 904.80

LABOUR FOR 125 SFT.

Mason 0.75 No. 300.00 Per day 225.00


Coolies 1.50 No. 140.00 Per day 210.00
Bahishti 0.50 No. 160.00 Per day 80.00
Total 515.00
Sundries 10 Percent 51.50
Total 566.50
Contractor's Profit & Overheads 20 Percent 113.30
Total 679.80

ITEM RATE

Labour Rate Per 100 Sft. Rs. 543.84 Say 543.85


Labour Rate Per Sqm. Rs. 58.52 Say 58.50
Composite Rate per 100 Sft. Rs. 1,448.64 Say 1448.65
Composite Rate per Sqm. Rs. 155.87 Say 155.85

Page 8
DESCRIPTION OF ITEM

9 Brick on edge flooring laid in 1:6 cement mortar over a bed of 3/4" thick cement mortar (1:6)

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Bricks 9" size 525 Nos. 1200.00 Per 1000 No. 630.00
2 Cement for laying 0.85 Bag 230.00 Per Bag 195.50
3 Cement for bedding mortar 0.88 Bag 230.00 Per Bag 202.40
4 Sand for laying 7.00 Cft. 350.00 Per 100 Cft 24.50
5 Sand for bedding mortar 6.00 Cft. 350.00 Per 100 Cft 21.00
Total 1,073.40
Contractor's Profit & Overheads 20 Percent 214.68
Total 1,288.08

LABOUR FOR 125 Sft.

Mason 1.00 No. 300.00 Per day 300.00


Coolies 2.00 No. 140.00 Per day 280.00
Bahishti 0.50 No. 160.00 Per day 80.00
Total 660.00
Sundries 10 Percent 66.00
Total 726.00
Contractor's Profit & Overheads 20 Percent 145.20
Total 871.20

ITEM RATE

Labour Rate Per 100 Sft. Rs. 696.96 Say 696.95


Labour Rate Per Sqm. Rs. 74.99 Say 75.00
Composite Rate per 100 Sft. Rs. 1,985.04 Say 1985.05
Composite Rate per Sqm. Rs. 213.59 Say 213.60

Page 9
DESCRIPTION OF ITEM

10 Brick tiles (12"x6"x2") laid in (1:6) cement mortar, over a bed of 3/4" thick cement mortar (1:6)

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Tiles 12"x6"x2" 210 Nos. 1250.00 Per 1000 No. 262.50


2 Cement 1.10 Bag 230.00 Bag 253.00
4 Sand 8.00 Cft. 350.00 Per 100 Cft 28.00
Total 543.50
Contractor's Profit & Overheads 20 Percent 108.70
Total 652.20

LABOUR

Mason 0.75 No. 300.00 Per day 225.00


Coolies 1.50 No. 140.00 Per day 210.00
Bahishti 0.50 No. 160.00 Per day 80.00
Total 515.00
Sundries 10 Percent 51.50
Total 566.50
Contractor's Profit & Overheads 20 Percent 113.30
Total 679.80

ITEM RATE

Labour Rate Per 100 Sft. Rs. 679.80 Say 679.80


Labour Rate Per Sqm. Rs. 73.15 Say 73.15
Composite Rate per 100 Sft. Rs. 1,332.00 Say 1332.00
Composite Rate per Sqm. Rs. 143.32 Say 143.30

Page 10
DESCRIPTION OF ITEM

11 Brick tiles (9" x 4½" x 1½") laid flat in 1:3 cement mortar over a bed of 3/4" thick cement mortar (1:6)

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Tiles 9"x4½"x1½" 350 Nos. 1050.00 Per 1000 No. 367.50


2 Cement 1.40 Bag 230.00 Bag 322.00
4 Sand 12.00 Cft. 350.00 Per 100 Cft 42.00
Total 731.50
Contractor's Profit & Overheads 20 Percent 146.30
Total 877.80

LABOUR

Mason 1.00 No. 300.00 Per day 300.00


Coolies (Unskilled) 1.50 No. 140.00 Per day 210.00
Bahishti 0.50 No. 160.00 Per day 80.00
Total 590.00
Sundries 10 Percent 59.00
Total 649.00
Contractor's Profit & Overheads 20 Percent 129.80
Total 778.80

ITEM RATE

Labour Rate Per 100 Sft. Rs. 778.80 Say 778.80


Labour Rate Per Sqm. Rs. 83.80 Say 83.80
Composite Rate per 100 Sft. Rs. 1,656.60 Say 1656.60
Composite Rate per Sqm. Rs. 178.25 Say 178.25

Page 11
DESCRIPTION OF ITEM

12 Cement tiles (8"x8"x¾") laid fiat in 1:2 cement mortar over 3/4" thick bed of cement mortar 1:2

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement tiles (8"x8"x3/4") 240 Nos. 7.00 Per No. 1,680.00


2 Cement 1.87 Bags 230.00 Per Bag 430.10
4 Sand 4.70 Cft. 350.00 Per 100 Cft 16.45
Total 2,126.55
Contractor's Profit & Overheads 20 Percent 425.31
Total 2,551.86

LABOUR FOR 200 SFT.

Mason 1.25 No. 300.00 Per day 375.00


Coolies (Unskilled) 2.00 No. 140.00 Per day 280.00
Bahishti 0.34 No. 160.00 Per day 54.40
Total 709.40
Sundries 10 Percent 70.94
Total 780.34
Contractor's Profit & Overheads 20 Percent 156.07
Total 936.41

ITEM RATE

Labour Rate Per 100 Sft. Rs. 468.20 Say 468.20


Labour Rate Per Sqm. Rs. 50.38 Say 50.40
Composite Rate per 100 Sft. Rs. 3,020.06 Say 3020.05
Composite Rate per Sqm. Rs. 324.96 Say 324.95

Page 12
DESCRIPTION OF ITEM

13 Cement concrete tiles laid in 1:2 cement mortar over 3/4" thick bed of cement mortar 1:2

a) 12" x 12" x 1"

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement concrete tiles (1" thick) 105 Nos 11.00 Each 1,155.00
2 Cement for bedding and laying of 1:2 ratio 1.85 Bags 230.00 Per Bag 425.50
4 Sand 4.67 Cft. 350.00 Per 100 Cft 16.35
Total 1,596.85
Contractor's Profit & Overheads 20 Percent 319.37
Total 1,916.21

LABOUR FOR 200 SFT

Mason 1.25 No. 300.00 Per day 375.00


Coolies 2.00 No. 140.00 Per day 280.00
Bahishti 0.34 No. 160.00 Per day 54.40
Total 709.40
Sundries 10 Percent 70.94
Total 780.34
Contractor's Profit & Overheads 20 Percent 156.07
Total 936.41

ITEM RATE

Labour Rate Per 100 Sft. Rs. 468.20 Say 468.20


Labour Rate Per Sqm. Rs. 50.38 Say 50.40
Composite Rate per 100 Sft. Rs. 2,384.42 Say 2384.40
Composite Rate per Sqm. Rs. 256.56 Say 256.55

Page 13
b) 9" x 9" x 3/4"

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement concrete tiles 186 Nos 8.00 Each 1,488.00


2 Cement for bedding and laying of 1:2 1.86 Bags 230.00 Per Bag 427.80
4 Sand 4.67 Cft. 350.00 Per 100 Cft 16.35
Total 1,932.15
Contractor's Profit & Overheads 20 Percent 386.43
Total 2,318.57

LABOUR FOR 200 SFT.

Mason 1.25 No. 300.00 Per day 375.00


Coolies 2.00 No. 140.00 Per day 280.00
Bahishti 0.34 No. 160.00 Per day 54.40
Total 709.40
Sundries 10 Percent 70.94
Total 780.34
Contractor's Profit & Overheads 20 Percent 156.07
Total 936.41

ITEM RATE

Labour Rate Per 100 Sft. Rs. 468.20 Say 468.20


Labour Rate Per Sqm. Rs. 50.38 Say 50.40
Composite Rate per 100 Sft. Rs. 2,786.78 Say 2786.80
Composite Rate per Sqm. Rs. 299.86 Say 299.85

Page 14
c) 6" x 6" x 3/4"

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement concrete tiles 420 Nos 6.50 Each 2,730.00


2 Cement for bedding and laying of 1:2 ratio 1.90 Bags 230.00 Per Bag 437.00
4 Sand 4.74 Cft. 350.00 Per 100 Cft 16.59
Total 3,183.59
Contractor's Profit & Overheads 20 Percent 636.72
Total 3,820.31

LABOUR FOR 200 SFT.

Mason 1.25 No. 300.00 Per day 375.00


Coolies 2.00 No. 140.00 Per day 280.00
Bahishti 0.34 No. 160.00 Per day 54.40
Total 709.40
Sundries 10 Percent 70.94
Total 780.34
Contractor's Profit & Overheads 20 Percent 156.07
Total 936.41

ITEM RATE

Labour Rate Per 100 Sft. Rs. 468.20 Say 468.20


Labour Rate Per Sqm. Rs. 50.38 Say 50.40
Composite Rate per 100 Sft. Rs. 4,288.51 Say 4288.50
Composite Rate per Sqm. Rs. 461.44 Say 461.45

Page 15
DESCRIPTION OF ITEM

14 Coloured cement tiles (8"x8"3/4") of approved dark shade laid flat in 1:2 cement
mortar over 3/4" bedding mortar of 1:2

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Tiles 240 Each 7.00 Each 1,680.00


2 Cement 1.87 Bag 230.00 Per Bag 430.10
3 Sand 4.70 Cft. 350.00 Per 100 Cft 16.45
4 Pigment 0.67 Lbs (0.30 Kg.) 70.00 Per Kg. 21.00
Total 2,147.55
Contractor's Profit & Overheads 20 Percent 429.51
Total 2,577.06

LABOUR FOR 200 SFT.

Mason 1.25 No. 300.00 Per day 375.00


Coolies 2.00 No. 140.00 Per day 280.00
Bahishti 0.34 No. 160.00 Per day 54.40
Total 709.40
Sundries 10 Percent 70.94
Total 780.34
Contractor's Profit & Overheads 20 Percent 156.07
Total 936.41

ITEM RATE

Labour Rate Per 100 Sft. Rs. 468.20 Say 468.20


Labour Rate Per Sqm. Rs. 50.38 Say 50.40
Composite Rate per 100 Sft. Rs. 3,045.26 Say 3045.25
Composite Rate per Sqm. Rs. 327.67 Say 327.65

Page 16
DESCRIPTION OF ITEM

15 Providing and laying topping of cement concrete (1:2:4) including


surface finishing and dividing into panels.

a) 1" (25mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 1.50 Bags 230.00 Per Bag 345.00


2 Sand 3.70 Cft. 350.00 Per 100 Cft 12.95
3 Shingle 7.40 Cft. 1000.00 Per 100 Cft 74.00
4 Form Work (Kail Wood) 0.034 Cft. 350.00 Per Cft. 12.01
Total 443.96
Contractor's Profit & Overheads 20 Percent 88.79
Total 532.75

LABOUR

Mason 1.00 No. 300.00 Per day 300.00


Coolies 0.50 No. 140.00 Per day 70.00
Bahishti 0.10 No. 160.00 Per day 16.00
Carpenter 0.25 No. 300.00 Per day 75.00
Total 461.00
Sundries 10 Percent 46.10
Total 507.10
Contractor's Profit & Overheads 20 Percent 101.42
Total 608.52

ITEM RATE

Labour Rate Per 100 Sft. Rs. 608.52 Say 608.50


Labour Rate Per Sqm. Rs. 65.48 Say 65.50
Composite Rate per 100 Sft. Rs. 1,141.28 Say 1141.30
Composite Rate per Sqm. Rs. 122.80 Say 122.80

Page 17
b) 1¼" (30mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 1.85 Bags 230.00 Per Bag 425.50


2 Sand 4.60 Cft. 350.00 Per 100 Cft 16.10
3 Shingle 9.20 Cft. 1000.00 Per 100 Cft 92.00
4 Form Work (Kail Wood) 0.034 Cft. 350.00 Per Cft. 12.01
Total 545.61
Contractor's Profit & Overheads 20 Percent 109.12
Total 654.73

LABOUR

Mason 1.00 No. 300.00 Per day 300.00


Coolies 0.50 No. 140.00 Per day 70.00
Bahishti 0.10 No. 160.00 Per day 16.00
Carpenter 0.25 No. 300.00 Per day 75.00
Total 461.00
Sundries 10 Percent 46.10
Total 507.10
Contractor's Profit & Overheads 20 Percent 101.42
Total 608.52

ITEM RATE

Labour Rate Per 100 Sft. Rs. 608.52 Say 608.50


Labour Rate Per Sqm. Rs. 65.48 Say 65.50
Composite Rate per 100 Sft. Rs. 1,263.25 Say 1263.25
Composite Rate per Sqm. Rs. 135.93 Say 135.95

Page 18
c) 1½" (40mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 2.20 Bags 230.00 Per Bag 506.00


2 Sand 5.50 Cft. 350.00 Per 100 Cft 19.25
3 Shingle 11.00 Cft. 1000.00 Per 100 Cft 110.00
4 Form Work (Kail Wood) 0.034 Cft. 350.00 Per Cft. 12.01
Total 647.26
Contractor's Profit & Overheads 20 Percent 129.45
Total 776.71

LABOUR

Mason 1.00 No. 300.00 Per day 300.00


Cooly (Unskilled) 1.00 No. 140.00 Per day 140.00
Bahishti 0.15 No. 160.00 Per day 24.00
Carpenter 0.25 No. 300.00 Per day 75.00
Total 539.00
Sundries 10 Percent 53.90
Total 592.90
Contractor's Profit & Overheads 20 Percent 118.58
Total 711.48

ITEM RATE

Labour Rate Per 100 Sft. Rs. 711.48 Say 711.50


Labour Rate Per Sqm. Rs. 76.56 Say 76.55
Composite Rate per 100 Sft. Rs. 1,488.19 Say 1488.20
Composite Rate per Sqm. Rs. 160.13 Say 160.15

Page 19
d) 1 3/4" (45mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 2.55 Bags 230.00 Per Bag 586.50


2 Sand 6.50 Cft. 350.00 Per 100 Cft 22.75
3 Shingle 12.80 Cft. 1000.00 Per 100 Cft 128.00
4 Form Work (Kail Wood) 0.040 Cft. 350.00 Per Cft. 14.00
Total 751.25
Contractor's Profit & Overheads 20 Percent 150.25
Total 901.50

LABOUR

Mason 1.00 No. 300.00 Per day 300.00


Cooly 1.00 No. 140.00 Per day 140.00
Bahishti 0.15 No. 160.00 Per day 24.00
Carpenter 0.25 No. 300.00 Per day 75.00
Total 539.00
Sundries 10 Percent 53.90
Total 592.90
Contractor's Profit & Overheads 20 Percent 118.58
Total 711.48

ITEM RATE

Labour Rate Per 100 Sft. Rs. 711.48 Say 711.50


Labour Rate Per Sqm. Rs. 76.56 Say 76.55
Composite Rate per 100 Sft. Rs. 1,612.98 Say 1613.00
Composite Rate per Sqm. Rs. 173.56 Say 173.55

Page 20
e) 2" (50mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 3.00 Bags 230.00 Per Bag 690.00


2 Sand 7.40 Cft. 350.00 Per 100 Cft 25.90
3 Shingle 14.70 Cft. 1000.00 Per 100 Cft 147.00
4 Form Work (Kail Wood) 0.040 Cft. 350.00 Per Cft. 14.00
Total 876.90
Contractor's Profit & Overheads 20 Percent 175.38
Total 1,052.28

LABOUR

Mason 1.00 No. 300.00 Per day 300.00


Cooly 1.50 No. 140.00 Per day 210.00
Bahishti 0.20 No. 160.00 Per day 32.00
Carpenter 0.25 No. 300.00 Per day 75.00
Total 617.00
Sundries 10 Percent 61.70
Total 678.70
Contractor's Profit & Overheads 20 Percent 135.74
Total 814.44

ITEM RATE

Labour Rate Per 100 Sft. Rs. 814.44 Say 814.45


Labour Rate Per Sqm. Rs. 87.63 Say 87.65
Composite Rate per 100 Sft. Rs. 1,866.72 Say 1866.70
Composite Rate per Sqm. Rs. 200.86 Say 200.85

Page 21
f) 2¼" (55mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 3.30 Bags 230.00 Per Bag 759.00


2 Sand 8.40 Cft. 350.00 Per 100 Cft 29.40
3 Shingle 16.50 Cft. 1000.00 Per 100 Cft 165.00
4 Form Work (Kail Wood) 0.046 Cft. 350.00 Per Cft. 16.00
Total 969.40
Contractor's Profit & Overheads 20 Percent 193.88
Total 1,163.27

LABOUR

Mason 1.00 No. 300.00 Per day 300.00


Cooly 1.60 No. 140.00 Per day 224.00
Bahishti 0.20 No. 160.00 Per day 32.00
Carpenter 0.25 No. 300.00 Per day 75.00
Total 631.00
Sundries 10 Percent 63.10
Total 694.10
Contractor's Profit & Overheads 20 Percent 138.82
Total 832.92

ITEM RATE

Labour Rate Per 100 Sft. Rs. 832.92 Say 832.90


Labour Rate Per Sqm. Rs. 89.62 Say 89.60
Composite Rate per 100 Sft. Rs. 1,996.19 Say 1996.20
Composite Rate per Sqm. Rs. 214.79 Say 214.80

Page 22
g) 2½" (60mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 3.65 Bags 230.00 Per Bag 839.50


2 Sand 2.20 Cft. 350.00 Per 100 Cft 7.70
3 Shingle 18.35 Cft. 1000.00 Per 100 Cft 183.50
4 Form Work (Kail Wood) 0.051 Cft. 350.00 Per Cft. 18.00
Total 1,048.70
Contractor's Profit & Overheads 20 Percent 209.74
Total 1,258.44

LABOUR

Mason 1.00 No. 300.00 Per day 300.00


Cooly 2.00 No. 140.00 Per day 280.00
Bahishti 0.25 No. 160.00 Per day 40.00
Carpenter 0.25 No. 300.00 Per day 75.00
Total 695.00
Sundries 10 Percent 69.50
Total 764.50
Contractor's Profit & Overheads 20 Percent 152.90
Total 917.40

ITEM RATE

Labour Rate Per 100 Sft. Rs. 917.40 Say 917.40


Labour Rate Per Sqm. Rs. 98.71 Say 98.70
Composite Rate per 100 Sft. Rs. 2,175.84 Say 2175.85
Composite Rate per Sqm. Rs. 234.12 Say 234.10

Page 23
h) 2 3/4" (70mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 4.00 Bags 230.00 Per Bag 920.00


2 Sand 10.00 Cft. 350.00 Per 100 Cft 35.00
3 Shingle 20.20 Cft. 1000.00 Per 100 Cft 202.00
4 Form Work (Kail Wood) 0.051 Cft. 350.00 Per Cft. 18.00
Total 1,175.00
Contractor's Profit & Overheads 20 Percent 235.00
Total 1,410.00

LABOUR

Mason 1.00 No. 300.00 Per day 300.00


Cooly 2.00 No. 140.00 Per day 280.00
Bahishti 0.25 No. 160.00 Per day 40.00
Carpenter 0.25 No. 300.00 Per day 75.00
Total 695.00
Sundries 10 Percent 69.50
Total 764.50
Contractor's Profit & Overheads 20 Percent 152.90
Total 917.40

ITEM RATE

Labour Rate Per 100 Sft. Rs. 917.40 Say 917.40


Labour Rate Per Sqm. Rs. 98.71 Say 98.70
Composite Rate per 100 Sft. Rs. 2,327.40 Say 2327.40
Composite Rate per Sqm. Rs. 250.43 Say 250.45

Page 24
i) 3" (75mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 4.40 Bags 230.00 Per Bag 1,012.00


2 Sand 11.00 Cft. 350.00 Per 100 Cft 38.50
3 Shingle 22.00 Cft. 1000.00 Per 100 Cft 220.00
4 Form Work (Kail Wood) 0.057 Cft. 350.00 Per Cft. 20.02
Total 1,290.52
Contractor's Profit & Overheads 20 Percent 258.10
Total 1,548.62

LABOUR

Mason 1.00 No. 300.00 Per day 300.00


Cooly 2.00 No. 140.00 Per day 280.00
Bahishti 0.25 No. 160.00 Per day 40.00
Carpenter 0.25 No. 300.00 Per day 75.00
Total 695.00
Sundries 10 Percent 69.50
Total 764.50
Contractor's Profit & Overheads 20 Percent 152.90
Total 917.40

ITEM RATE

Labour Rate Per 100 Sft. Rs. 917.40 Say 917.40


Labour Rate Per Sqm. Rs. 98.71 Say 98.70
Composite Rate per 100 Sft. Rs. 2,466.02 Say 2466.00
Composite Rate per Sqm. Rs. 265.34 Say 265.35

Page 25
DESCRIPTION OF ITEM

16 Providing and laying conglomerate flooring (two coat work) with top layer of ½" thick
wearing surface, consisting of one part of cement and two parts of stone chips passing
3/16" sieave, over bottom layer of cement concrete 1:3:6 including surface finishing and
dividing in panels:-

a) 1½" (40mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

i) ½" Thick Topping

1 Cement 1.25 Bags 230.00 Per Bag 287.50


2 Sand 3.00 Cft. 350.00 Per 100 Cft 10.50

ii) 1" Thick Bedding 1:3:6

Cement 1.08 Bags 230.00 Per Bag 248.40


Sand 3.83 Cft. 350.00 Per 100 Cft 13.41
Shingle 7.67 Cft. 1000.00 Per 100 Cft 76.70
Total 636.51
Contractor's Profit & Overheads 20 Percent 127.30
Total 763.81

LABOUR

i) ½" Thick Topping

Mason 0.50 No. 300.00 Per day 150.00


Cooly 0.25 No. 140.00 Per day 35.00
Bahishti 0.05 No. 160.00 Per day 8.00
Carpenter 0.25 No. 300.00 Per day 75.00

ii) 1" Thick Bedding 1:3:6

Mason 0.80 No. 300.00 Per day 240.00


Cooly 0.50 No. 140.00 Per day 70.00
Bahishti 0.15 No. 160.00 Per day 24.00
Carpenter 0.25 No. 300.00 Per day 75.00
Total 677.00
Sundries 10 Percent 67.70
Total 744.70
Contractor's Profit & Overheads 20 Percent 148.94
Total 893.64

ITEM RATE

Labour Rate Per 100 Sft. Rs. 893.64 Say 893.65


Labour Rate Per Sqm. Rs. 96.16 Say 96.15
Composite Rate per 100 Sft. Rs. 1,657.45 Say 1657.45
Composite Rate per Sqm. Rs. 178.34 Say 178.35

Page 26
b) 1 3/4" (45mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

i) ½" Thick Topping

1 Cement 1.25 Bags 230.00 Per Bag 287.50


2 Sand 3.00 Cft. 350.00 Per 100 Cft 10.50

ii) 1¼" Thick Bedding 1:3:6

Cement 1.35 Bags 230.00 Per Bag 310.50


Sand 4.06 Cft. 350.00 Per 100 Cft 14.21
Shingle 8.12 Cft. 1000.00 Per 100 Cft 81.20
Total 703.91
Contractor's Profit & Overheads 20 Percent 140.78
Total 844.69

LABOUR

i) ½" Thick Topping

Mason 0.50 No. 300.00 Per day 150.00


Cooly 0.25 No. 140.00 Per day 35.00
Bahishti 0.05 No. 160.00 Per day 8.00
Carpenter 0.25 No. 300.00 Per day 75.00

ii) 1¼" Thick Bedding 1:3:6

Mason 0.80 No. 300.00 Per day 240.00


Cooly 0.50 No. 140.00 Per day 70.00
Bahishti 0.15 No. 160.00 Per day 24.00
Carpenter 0.25 No. 300.00 Per day 75.00
Total 677.00
Sundries 10 Percent 67.70
Total 744.70
Contractor's Profit & Overheads 20 Percent 148.94
Total 893.64

ITEM RATE

Labour Rate Per 100 Sft. Rs. 893.64 Say 893.65


Labour Rate Per Sqm. Rs. 96.16 Say 96.15
Composite Rate per 100 Sft. Rs. 1,738.33 Say 1738.35
Composite Rate per Sqm. Rs. 187.04 Say 187.05

Page 27
c) 2" (50mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

i) ½" Thick Topping

1 Cement 1.25 Bags 230.00 Per Bag 287.50


2 Sand 3.00 Cft. 350.00 Per 100 Cft 10.50

ii) 1½" Thick Bedding 1:3:6

Cement 1.63 Bags 230.00 Per Bag 374.90


Sand 5.75 Cft. 350.00 Per 100 Cft 20.13
Shingle 11.50 Cft. 1000.00 Per 100 Cft 115.00
Total 808.03
Contractor's Profit & Overheads 20 Percent 161.61
Total 969.63

LABOUR

i) ½" Thick Topping 1:2

Mason 0.50 No. 300.00 Per day 150.00


Cooly 0.25 No. 140.00 Per day 35.00
Bahishti 0.05 No. 160.00 Per day 8.00
Carpenter 0.25 No. 300.00 Per day 75.00

ii) 1½" Thick Bedding 1:3:6

Mason 1.00 No. 300.00 Per day 300.00


Cooly 1.00 No. 140.00 Per day 140.00
Bahishti 0.20 No. 160.00 Per day 32.00
Carpenter 0.30 No. 300.00 Per day 90.00
Total 830.00
Sundries 10 Percent 83.00
Total 913.00
Contractor's Profit & Overheads 20 Percent 182.60
Total 1095.60

ITEM RATE

Labour Rate Per 100 Sft. Rs. 1,095.60 Say 1095.60


Labour Rate Per Sqm. Rs. 117.89 Say 117.90
Composite Rate per 100 Sft. Rs. 2,065.23 Say 2065.25
Composite Rate per Sqm. Rs. 222.22 Say 222.20

Page 28
DESCRIPTION OF ITEM

17 Add extra in cement concrete floor topping, if finished with pigment and polishing

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL
1 Grey Cement for Finishing 1/16" Thick 0.40 Bags 230.00 Per Bag 92.00
2 Pigment 4.5 Lbs (2.04 Kg.) 70.00 Per Kg. 142.80
3 Polish 0.5 Lbs (0.23 Kg.) 212.00 Per Kg. 48.76
Total 283.56
Contractor's Profit & Overheads 20 Percent 56.71
Total 340.27

LABOUR FOR 150 SFT.

Mason 0.50 No. 300.00 Per day 85.00


Cooly (Skilled) 0.50 No. 140.00 Per day 42.50
Total 127.50
Sundries 10 Percent 12.75
Total 140.25
Contractor's Profit & Overheads 20 Percent 28.05
Total 168.30

ITEM RATE

Labour Rate Per 100 Sft. Rs. 112.20 Say 112.20


Labour Rate Per Sqm. Rs. 12.07 Say 12.05
Composite Rate per 100 Sft. Rs. 452.47 Say 452.45
Composite Rate per Sqm. Rs. 48.69 Say 48.70

Page 29
DESCRIPTION OF ITEM

18 Extra labour for each storey above ground floor for moasic, conglomerate, tiles
stone and wooden floor

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

LABOUR FOR 125 SFT.

Cooly for carriage of material 0.75 No. 140.00 Per day 105.00
Sundries 10 Percent 10.50
Total 115.50
Contractor's Profit & Overheads 20 Percent 23.10
Total 138.60

ITEM RATE

Labour Rate per 100 Sft. Rs. 110.88 Say 110.90


Labour Rate per Sqm. Rs. 11.93 Say 11.95

DESCRIPTION OF ITEM

19 Flag stone flooring laid in lime mortar 1:2 over 3/4" bedding mortar in plat forms
and floors etc.

a) 2" (50mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Dressed Stone 2'x2'x2" 25.00 Nos. 35.00 Each 875.00


2 Lime 1.3 Mds (48.5 Kg.) 2.00 Per Kg. 97.00
3 Sand 5.00 Cft. 350.00 Per 100 Cft 17.50
4 Steel 0.76 Kg. 17.00 Per Kg. 12.99
5 Charcoal 1.75 Kg. 4.00 Per Kg. 7.01
Total 1,009.50
Contractor's Profit & Overheads 20 Percent 201.90
Total 1,211.40

LABOUR

Mason 2.50 No. 300.00 Per day 750.00


Coolies 3.00 No. 140.00 Per day 420.00
Bahishti 0.12 No. 160.00 Per day 19.20
Blacksmith 0.10 No. 170.00 Per day 17.00
Bollow Man 0.10 No. 75.00 Per day 7.50
Total 1,213.70
Sundries 10 Percent 121.37
Total 1335.07
Contractor's Profit & Overheads 20 Percent 267.01
Total 1602.08

ITEM RATE

Labour Rate Per 100 Sft. Rs. 1,602.08 Say 1602.10


Labour Rate Per Sqm. Rs. 172.38 Say 172.40
Composite Rate per 100 Sft. Rs. 2,813.48 Say 2813.50
Composite Rate per Sqm. Rs. 302.73 Say 302.75

Page 30
b) 3" (75mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Dressed Stone 2'x2'x3" 25.00 Nos. 45.00 Each 1,125.00


2 Lime 1.42 Mds (53 Kg.) 2.00 Per Kg. 106.00
3 Surkhi 5.00 Cft. 350.00 Per 100 Cft 17.50
4 Steel 0.75 Kg. 17.00 Per Kg. 12.75
5 Charcoal 1.81 Kg. 4.00 Per Kg. 7.24
Total 1,268.49
Contractor's Profit & Overheads 20 Percent 253.70
Total 1,522.19

LABOUR

Mason 2.50 No. 300.00 Per day 750.00


Cooly 3.00 No. 140.00 Per day 420.00
Bahishti 0.12 No. 160.00 Per day 19.20
Blacksmith 0.10 No. 170.00 Per day 17.00
Bollow Man 0.10 No. 75.00 Per day 7.50
Total 1,213.70
Sundries 10 Percent 121.37
Total 1335.07
Contractor's Profit & Overheads 20 Percent 267.01
Total 1602.08

ITEM RATE

Labour Rate Per 100 Sft. Rs. 1,602.08 Say 1602.10


Labour Rate Per Sqm. Rs. 172.38 Say 172.40
Composite Rate per 100 Sft. Rs. 3,124.27 Say 3124.25
Composite Rate per Sqm. Rs. 336.17 Say 336.15

Page 31
DESCRIPTION OF ITEM

20 Asphalt flooring including preparation of proper base, remelting, setting out and
finishing complete

a) 1" Thick Topping

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Asphalt 2.36 Cwt (119.90 Kg.) 14.00 Per Kg. 1,678.60


2 Steam Coal 0.5 Md (18.66 Kg.) 12.00 Per Kg. 223.92
3 Fine Aggregate 9.00 Cft. 1500.00 Per 100 Cft 135.00
4 Form Work (Kail Wood) 0.034 Cft. 350.00 Per Cft. 11.97
Total 2,049.49
Contractor's Profit & Overheads 20 Percent 409.90
Total 2,459.39

LABOUR

Mason for Setting out and laying 0.25 No. 300.00 Per day 75.00
Coolies 2.00 No. 140.00 Per day 280.00
Carpenter 0.25 No. 300.00 Per day 75.00
Total 430.00
Sundries 10 Percent 43.00
Total 473.00
Contractor's Profit & Overheads 20 Percent 94.60
Total 567.60

ITEM RATE

Labour Rate Per 100 Sft. Rs. 567.60 Say 567.60


Labour Rate Per Sqm. Rs. 61.07 Say 61.05
Composite Rate per 100 Sft. Rs. 3,026.99 Say 3027.00
Composite Rate per Sqm. Rs. 325.70 Say 325.70

Page 32
b) ½" Thick Topping

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Asphalt 1.20 Cwt (60.960 Kg.) 14.00 Per Kg. 853.44


2 Steam Coal 0.25 Md (9.33 Kg.) 12.00 Per Kg. 111.96
3 Fine Aggregate 4.51 Cft. 1500.00 Per 100 Cft 67.61
4 Form Work (Kail Wood) 0.034 Cft. 350.00 Per Cft. 11.90
Total 1,044.91
Contractor's Profit & Overheads 20 Percent 208.98
Total 1,253.89

LABOUR

Mason 0.20 No. 300.00 Per day 60.00


Coolies 1.50 No. 140.00 Per day 210.00
Carpenter 0.25 No. 300.00 Per day 75.00
Total 345.00
Sundries 10 Percent 34.50
Total 379.50
Contractor's Profit & Overheads 20 Percent 75.90
Total 455.40

ITEM RATE

Labour Rate Per 100 Sft. Rs. 455.40 Say 455.40


Labour Rate Per Sqm. Rs. 49.00 Say 49.00
Composite Rate per 100 Sft. Rs. 1,709.29 Say 1709.30
Composite Rate per Sqm. Rs. 183.92 Say 183.90

Page 33
c) ¼" Thick Topping

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Asphalt 0.60 Cwt (30.48 Kg.) 14.00 Per Kg. 426.72


2 Steam Coal 0.25 Md (8.58 Kg.) 12.00 Per Kg. 102.96
3 Fine Grit 2.51 Cft. 1500.00 Per 100 Cft 37.61
4 Form Work (Kail Wood) 0.034 Cft. 350.00 Per Cft. 11.90
Total 579.19
Contractor's Profit & Overheads 20 Percent 115.84
Total 695.02

LABOUR

Mason 0.17 No. 300.00 Per day 51.00


Cooly 1.00 No. 140.00 Per day 140.00
Carpenter 0.25 No. 300.00 Per day 75.00
Total 266.00
Sundries 10 Percent 26.60
Total 292.60
Contractor's Profit & Overheads 20 Percent 58.52
Total 351.12

ITEM RATE

Labour Rate Per 100 Sft. Rs. 351.12 Say 351.10


Labour Rate Per Sqm. Rs. 37.78 Say 37.80
Composite Rate per 100 Sft. Rs. 1,046.14 Say 1046.15
Composite Rate per Sqm. Rs. 112.56 Say 112.55

Page 34
DESCRIPTION OF ITEM

21 1 3/8" thick mosaic flooring consisting of 3/8" mosaic topping of one part of
cement and marble powder in the ratio 3:1 and two parts of marble chips laid
over 1" thick flooring of 1:2:4 cement concrete including rubbing and polishing
complete.

a) Using Grey Cement

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL for mosaic topping, rubbing & polishing

1 Cement For 3/8" topping 0.94 Bag 230.00 Per Bag 216.20
2 Marble Chips 3.00 Cwt (152.40 Kg.) 1.00 Per Kg. 152.40
3 Corborandom Stone 3.00 Nos. 35.00 Each 105.00
4 Wax Polish 0.5 Lbs (0.23 Kg.) 635.00 / Pack. of 3 Kg 48.68
5 Linen and Cotton 0.40 Kg. 25.00 P. Kg. 10.00
6 Marble Powder 0.31 Cwt (15.75 Kg.) 80.00 Per 100 Kg. 12.60
7 Tatric Acid 0.34 Lbs (0.15 Kg.) 65.00 Per Kg. 9.75
Total 554.63
Contractor's Profit & Overheads 20 Percent 110.93
Total 665.56

MATERIAL for 1" thick 1:2:4 concrete

1 Cement 1.50 Bags 230.00 Per Bag 345.00


2 Sand 3.70 Cft. 350.00 Per 100 Cft 12.95
3 Shingle 7.40 Cft. 1000.00 Per 100 Cft 74.00
4 Form Work 0.034 Cft. 350.00 P. Cft. 12.00
Total 443.95
Contractor's Profit & Overheads 20 Percent 88.79
Total 532.74
Total Material 1,198.30

LABOUR for mosaic topping

Mason for Laying 1.50 No. 300.00 Per day 450.00


Coolies 1.25 No. 140.00 Per day 175.00
Coolies (skilled for rubbing) 5.00 Nos. 160.00 Per day 800.00
Bahishti 0.75 No. 160.00 Per day 120.00
Total 1,545.00
Sundries 10 Percent 154.50
Total 1699.50
Contractor's Profit & Overheads 20 Percent 339.90
Total 2039.40

LABOUR for 1" Thick 1:2:4 Concrete

As per Item 15(a) 608.52


Total Labour 2,647.93

ITEM RATE

Labour Rate Per 100 Sft. Rs. 2,118.34 Say 2118.35


Labour Rate Per Sqm. Rs. 227.93 Say 227.95
Composite Rate per 100 Sft. Rs. 3,316.64 Say 3316.65
Composite Rate per Sqm. Rs. 356.87 Say 356.85

Page 35
b) Using White Cement

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL for 3/8"

1 Cement (White) 0.94 Bag 345.00 Per Bag 324.30


2 Marble Poweder 0.31 Cwt (15.75 Kg.) 80.00 Per 100 Kg. 12.60
3 Marble Chips 3.00 Cwt (152.40 Kg.) 1.00 Per Kg. 152.40
4 Carborandom Stone 3.00 Nos. 35.00 Each 105.00
5 Wax Polish 0.50 Lbs (0.23 Kg.) 635.00 Packet 3 Kg 48.68
6 Linen Cotton etc. 0.40 Kg. 25.00 P. Kg. 10.00
7 Tar Taric Acid 0.34 Lbs (0.15 Kg.) 65.00 Per Kg. 9.75
Total 662.73
Contractor's Profit & Overheads 20 Percent 132.55
Total 795.28

Add for cement concrete 1" thick


As per Item 15(a) Material 532.75
Total Material 1,328.03

LABOUR

Mason for Laying 1.50 No. 300.00 Per day 450.00


Coolies 1.25 No. 140.00 Per day 175.00
Coolies (skilled for rubbing) 5.00 Nos. 160.00 Per day 800.00
Bahishti 0.75 No. 160.00 Per day 120.00
Total 1,545.00
Sundries 10 Percent 154.50
Total 1699.50
Contractor's Profit & Overheads 20 Percent 339.90
Total 2039.40

Add Labour for 1" thick C.C. topping 1:2:4


As per item No. 15(a) 608.52
Total Labour 2,647.92

ITEM RATE

Labour Rate Per 100 Sft. Rs. 2,118.34 Say 2118.35


Labour Rate Per Sqm. Rs. 227.93 Say 227.95
Composite Rate per 100 Sft. Rs. 3,446.37 Say 3446.35
Composite Rate per Sqm. Rs. 370.83 Say 370.85

Page 36
DESCRIPTION OF ITEM

22 1½" thick mosaic flooring consisting of ½" mosaic topping of one part of
cement and marble powder in the ratio of 3:1 and two parts of marble chips laid
over 1" thick flooring of 1:2:4 cement concrete including rubbing and polishing
complete.

a) Using Grey Cement

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Grey Cement for ½" Topping 1.27 Bag 230.00 Per Bag 292.10
2 Marble Chips 3.00 Cwt (152.40 Kg.) 1.00 Per Kg. 152.40
3 Carborandom Stone 2.00 Nos. 35.00 Each 70.00
4 Wax Polish 0.50 Lbs (0.23 Kg.) 635.00 Packet 3 Kg 48.68
5 Linen Cotton etc. 0.72 Kg. 25.00 P. Kg. 18.00
6 Tar Taric Acid 0.34 Lbs / (0.15 Kg.) 65.00 Per Kg. 9.75
7 Marble Poweder 0.42 Cwt (21.34 Kg.) 80.00 Per 100 Kg. 17.07
Total 608.01
Contractor's Profit & Overheads 20 Percent 121.60
Total 729.61

Add Material for 1" thick cement concrete


Topping as per Item 15(a) 532.75
Total Material 1,262.35

LABOUR FOR 125 SFT.

Mason for Laying 1.50 No. 300.00 Per day 450.00


Coolies 1.25 No. 140.00 Per day 175.00
Coolies (skilled for rubbing and Polishing) 5.00 Nos. 160.00 Per day 800.00
Bahishti 0.75 No. 160.00 Per day 120.00
Total 1,545.00
Sundries 10 Percent 154.50
Total 1699.50
Contractor's Profit & Overheads 20 Percent 339.90
Total 2039.40

Add Labour for 1" thick cement concrete


Topping as per Item 15(a) 608.52
Total Labour 2,647.92

ITEM RATE

Labour Rate Per 100 Sft. Rs. 2,118.34 Say 2118.35


Labour Rate Per Sqm. Rs. 227.93 Say 227.95
Composite Rate per 100 Sft. Rs. 3,380.69 Say 3380.70
Composite Rate per Sqm. Rs. 363.76 Say 363.75

Page 37
b) Using White Cement

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement White 1.27 Bag 345.00 Per Bag 438.15


2 Marble Powder 0.42 Cwt (21.34 Kg.) 80.00 Per 100 Kg. 17.07
3 Marble Chips 4.16 Cwt (211.33 Kg.) 1.00 Per Kg. 211.33
4 Carborandom Stone 3.00 Nos. 35.00 Each 105.00
5 Wax Polish 0.50 Lbs (0.23 Kg.) 635.00 Packet 3 Kg 48.68
6 Linen Cotton etc. 0.72 Kg. 25.00 P. Kg. 18.00
7 Tar Taric Acid 0.34 Lbs (0.15 Kg.) 65.00 Per Kg. 9.75
Total 847.99
Contractor's Profit & Overheads 20 Percent 169.60
Total 1,017.58

Add for material of 1" thick cement concrete


Topping as per Item No. 15(a) 532.75
Total Material 1,550.33

LABOUR FOR 125 SFT.

Mason for Laying 1.50 No. 300.00 Per day 450.00


Coolies 1.25 No. 140.00 Per day 175.00
Coolies (skilled for rubbing and Polishing) 5.00 Nos. 160.00 Per day 800.00
Bahishti 0.75 No. 160.00 Per day 120.00
Total 1,545.00
Sundries 10 Percent 154.50
Total 1699.50
Contractor's Profit & Overheads 20 Percent 339.90
Total 2039.40

Add labour for 1" thick cement concrete


Topping as per Item No. 15(a) 608.52
Total Labour 2,647.92

ITEM RATE

Labour Rate Per 100 Sft. Rs. 2,118.34 Say 2118.35


Labour Rate Per Sqm. Rs. 227.93 Say 227.95
Composite Rate per 100 Sft. Rs. 3,668.66 Say 3668.65
Composite Rate per Sqm. Rs. 394.75 Say 394.75

Page 38
DESCRIPTION OF ITEM

23 Providing and laying floor of mosaic marble chips tiles 1" thick of approved quality and shade
laid in white cement and pigment over 3/4" bedding of cement sand mortar 1:2, incluidng
finishing and polishing complete.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Mosaic marble tiles 12"x12"x1" 105 Nos. 15.00 Each 1,575.00


2 Cement Grey 1.69 Bags 230.00 Per Bag 388.70
3 Sand 4.00 Cft. 350.00 Per 100 Cft. 14.00
4 Pigment 1.00 Lbs (0.45 Kg.) 70.00 Per Kg. 31.50
5 White Cement 0.08 Bag 345.00 Per Bag 27.60
Total 2,036.80
Contractor's Profit & Overheads 20 Percent 407.36
Total 2,444.16

LABOUR

Mason 1.84 No. 300.00 Per day 552.00


Coolies 2.80 No. 140.00 Per day 392.00
Bahishti 0.34 Nos. 160.00 Per day 54.40
Total 998.40
Sundries 10 Percent 99.84
Total 1098.24
Contractor's Profit & Overheads 20 Percent 219.65
Total 1317.89

ITEM RATE

Labour Rate Per 100 Sft. Rs. 1,317.89 Say 1317.90


Labour Rate Per Sqm. Rs. 141.80 Say 141.80
Composite Rate per 100 Sft. Rs. 3,762.05 Say 3762.05
Composite Rate per Sqm. Rs. 404.80 Say 404.80

Page 39
DESCRIPTION OF ITEM

24 Laying floor of approved white glazed tile 1/4" thick in white cement 1:2 over
3/4" thick cement mortar 1:2 complete.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Tile (Glazed) 6"x6"x¼" including 5% breakage 420 No. 9.00 Each 3,780.00
2 White Cement for laying 0.10 Bag 345.00 Per Bag 34.50
3 Grey Cement for Bed 2.16 Bag 230.00 Per Bag 496.80
4 Sand 5.20 Cft. 350.00 Per 100 Cft. 18.20
Total 4,329.50
Contractor's Profit & Overheads 20 Percent 865.90
Total 5,195.40

LABOUR

Masons 2.00 No. 300.00 Per day 600.00


Coolies 4.00 No. 140.00 Per day 560.00
Bahishti 0.50 No. 160.00 Per day 80.00
Total 1,240.00
Sundries 10 Percent 124.00
Total 1364.00
Contractor's Profit & Overheads 20 Percent 272.80
Total 1636.80

ITEM RATE

Labour Rate Per 100 Sft. Rs. 1,636.80 Say 1636.80


Labour Rate Per Sqm. Rs. 176.12 Say 176.10
Composite Rate per 100 Sft. Rs. 6,832.20 Say 6832.20
Composite Rate per Sqm. Rs. 735.14 Say 735.15

Page 40
DESCRIPTION OF ITEM

25 Laying floors of a approved coloured glazed tiles 1/4" thick laid in white
cement and pigment on a bed of 3/4" thick cement mortar 1:2

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Coloured glazed tiles 6"x6" including 5% breakage 420 No. 11.00 Each 4,620.00
2 White Cement 0.10 Bag 345.00 Per Bag 34.50
3 Grey Cement 2.16 Bag 230.00 Per Bag 496.80
4 Pigment 1.00 Lb/0.45 Kg. 70.00 Per Kg. 31.50
5 Sand 5.20 Cft 350.00 Per 100 Cft. 18.20
Total 5,201.00
Contractor's Profit & Overheads 20 Percent 1,040.20
Total 6,241.20

LABOUR

Masons 2.00 No. 300.00 Per day 600.00


Coolies 4.00 No. 140.00 Per day 560.00
Bahishti 0.50 No. 160.00 Per day 80.00
Total 1,240.00
Sundries 10 Percent 124.00
Total 1364.00
Contractor's Profit & Overheads 20 Percent 272.80
Total 1636.80

ITEM RATE

Labour Rate Per 100 Sft. Rs. 1,636.80 Say 1636.80


Labour Rate Per Sqm. Rs. 176.12 Say 176.10
Composite Rate per 100 Sft. Rs. 7,878.00 Say 7878.00
Composite Rate per Sqm. Rs. 847.67 Say 847.65

Page 41
DESCRIPTION OF ITEM

26 Rubbing and polishing old grit/mosaic floor including repairing voids, un-even
surface complete in all respects.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Carborandum Stone 0.50 No. 35.00 Each 17.50


2 Wax Polish 0.50 Lb (0.23 Kg.) 635.00 Packet of 3 Kg. 48.68
3 Tartric Acid 0.34 Lb (0.162 Kg.) 65.00 Per Kg. 10.50
4 Cotton waste cloth etc. 0.72 Kg. 25.00 P. Kg. 18.00
Total 94.68
Contractor's Profit & Overheads 20 Percent 18.94
Total 113.62

LABOUR FOR 125 SFT.

Skilled Cooly for rubbing and polishing 1.00 No. 160.00 Per day 160.00
Cooly 1.00 No. 140.00 Per day 140.00
Bahishti 0.25 No. 160.00 Per day 40.00
Total 340.00
Sundries 10 Percent 34.00
Total 374.00
Contractor's Profit & Overheads 20 Percent 74.80
Total 448.81

ITEM RATE

Labour Rate Per 100 Sft. Rs. 359.05 Say 359.05


Labour Rate Per Sqm. Rs. 38.63 Say 38.65
Composite Rate per 100 Sft. Rs. 472.67 Say 472.65
Composite Rate per Sqm. Rs. 50.86 Say 50.85

Page 42
DESCRIPTION OF ITEM

27 Rubbing and Polishing grit floor, including repairing voids, uneven surface
complete in all respects.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Carborandum Stone 1.50 No. 35.00 Each 52.50


2 Wax Polish 0.5 Lb (0.23 Kg.) 635.00 Packet of 3 Kg. 48.68
4 Cotton waste cloth etc. 0.08 Kg. 25.00 P. Kg. 2.00
Total 103.18
Contractor's Profit & Overheads 20 Percent 20.64
Total 123.82

LABOUR FOR 125 SFT.

Cooly 1.00 No. 140.00 Per day 140.00


Cooly Skilled 1.00 160.00 160.00
Bahishti 0.40 No. 160.00 Per day 64.00
Total 364.00
Sundries 10 Percent 36.40
Total 400.40
Contractor's Profit & Overheads 20 Percent 80.08
Total 480.48

ITEM RATE

Labour Rate Per 100 Sft. Rs. 384.38 Say 384.40


Labour Rate Per Sqm. Rs. 41.36 Say 41.35
Composite Rate per 100 Sft. Rs. 508.20 Say 508.20
Composite Rate per Sqm. Rs. 54.68 Say 54.70

Page 43
DESCRIPTION OF ITEM

28 Cleaning and washing mosaic or marble floor with caustic soda mixture

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Caustic Soda 1 Lb (0.45 Kg.) 65.00 Per Kg. 29.25


2 Hassein Cloth 0.5 Yard (0.46 m) 12.00 Per Metre 5.52
Total 34.77
Contractor's Profit & Overheads 20 Percent 6.95
Total 41.72

LABOUR FOR 150 SFT.

Mason 0.25 No. 300.00 Per day 75.00


Bahishti 0.12 No. 160.00 Per day 10.20
Total 85.20
Sundries 10 Percent 8.52
Total 93.72
Contractor's Profit & Overheads 20 Percent 18.74
Total 112.46

ITEM RATE

Labour Rate Per 100 Sft. Rs. 74.98 Say 75.00


Labour Rate Per Sqm. Rs. 8.07 Say 8.05
Composite Rate per 100 Sft. Rs. 116.70 Say 116.70
Composite Rate per Sqm. Rs. 12.56 Say 12.55

Page 44
DESCRIPTION OF ITEM

29 Shisham wood boarding or strips flooring 3/4" thick (sawn to required sizes)
tongued and grooved or splayed rebated fixed with brass screws on deedar wood
battens 1½"x2" placed at 12" centre to centre including two coats of bitumen laid
hot on the base.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Shisham Wood

100 x 3/4' x 1/12' 6.25 Cft.


Add 5% rebate 0.31 Cft.
Total 6.56 Cft.
Add 60% Wastage 3.94 Cft.
Total 10.50 Cft. 300.00 Per Cft. 3,150.00

Deodar Wood Battens

11 x 10' x 1/8' x 1/6' 2.29 Cft.


Add 50% Wastage 1.15 Cft.
Total 3.44 Cft. 500.00 Per Cft. 1,720.00

Bitumen 35 Lbs (15.89 Kg.) 14.00 Per Kg. 222.46


Fire Wood 0.125 Lbs (4.67 Kg.) 2.75 Per Kg. 12.84
Brass Screws 2" 7.00 Dozen 8.00 Per Dozen 56.00
Sand Paper Sheet 1.50 Dozen 72.00 Per Dozen 108.00
Total 5,269.30
Contractor's Profit & Overheads 20 Percent 1,053.86
Total 6,323.16

LABOUR FOR 300 SFT.

Carpenters 10.00 No. 300.00 Per day 3,000.00


Coolies 5.00 No. 160.00 Per day 800.00
Total 3,800.00
Sundries 10 Percent 380.00
Total 4180.00
Contractor's Profit & Overheads 20 Percent 836.00
Total 5016.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. 1,672.00 Say 1672.00


Labour Rate Per Sqm. Rs. 179.91 Say 179.90
Composite Rate per 100 Sft. Rs. 7,995.16 Say 7995.15
Composite Rate per Sqm. Rs. 860.28 Say 860.30

Page 45
DESCRIPTION OF ITEM

30 Decdar wood boarding or strips flooring 3/4" thick (sawn to required


sizes)tongued and grooved or splayed rebated fixed with brass screws on
deodar wood battens 1½"x2" placed at 12" c/c including two coats of bitumens
laid hot on the base.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Deodar wood planks 100 x 3/4' x 1/12' 6.25 Cft.


Add 5% for rebate 0.31 Cft.
Total 6.56 Cft.
Deodar wood batten 11x10' x 1/6' x 1/8' 2.29 Cft.
Total 8.85 Cft.
Add 50% Wastage 4.43 Cft.
Total 13.28 Cft. 500.00 Per Cft. 6,640.00

Bitumen 34 Lbs (15.44 Kg.) 14.00 Per Kg. 216.16


Fire Wood 0.125 Mds (4.67 Kg.) 2.75 Per Kg. 12.84
Brass Screws 2" long 7.00 Dozen 8.00 Per Dozen 56.00
Sand Paper 1.00 Dogen 72.00 Per Dozen 72.00
Total 6,997.00
Contractor's Profit & Overheads 20 Percent 1,399.40
Total 8,396.40

LABOUR FOR 200 SFT.

Carpenters 6.00 No. 300.00 Per day 1,800.00


Coolies 6.00 No. 140.00 Per day 840.00
Total 2,640.00
Sundries 10 Percent 264.00
Total 2904.00
Contractor's Profit & Overheads 20 Percent 580.80
Total 3484.80

ITEM RATE

Labour Rate Per 100 Sft. Rs. 1,742.40 Say 1742.40


Labour Rate Per Sqm. Rs. 187.48 Say 187.50
Composite Rate per 100 Sft. Rs. 10,138.80 Say 10138.80
Composite Rate per Sqm. Rs. 1,090.94 Say 1090.95

Page 46
DESCRIPTION OF ITEM

31 Teakwook boarding or strips flooring ½" thick (Sawn to required sized)


tongued and grooved screwed on deodar wood battens 1½" x 2" size, placed at 12"
centre to centre including 2 coats of bitumen laid hot on the base.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Teak Wood (100x½' x 1/12' 4.20 Cft.


Add 5% for rebate 0.20 Cft.
Total 4.40 Cft.
Add 20% Wastage 0.88 Cft
Total 5.28 Cft. 1400.00 Per Cft. 7,392.00

Deodar wood 11x10' x 1/8' x 1/6' 2.29 Cft.


Add. 50% Wastage 1.15
Total 3.44 Cft. 500.00 Cft. 1,720.00

Bitumen 34 Lbs (15.44 Kg.) 14.00 Per Kg. 216.16


Sand Paper 2.00 Dozen 72.00 Per Dozen 144.00
Fuel Wood 0.125 Mds (4.67 Kg.) 2.75 Per Kg. 12.84
Total 9,485.00
Contractor's Profit & Overheads 20 Percent 1,897.00
Total 11,382.00

LABOUR FOR 300 SFT.

Carpenters 10.00 No. 300.00 Per day 3,000.00


Coolies 5.00 No. 140.00 Per day 700.00
Total 3,700.00
Sundries 10 Percent 370.00
Total 4070.00
Contractor's Profit & Overheads 20 Percent 814.00
Total 4884.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. 1,628.00 Say 1628.00


Labour Rate Per Sqm. Rs. 175.17 Say 175.15
Composite Rate per 100 Sft. Rs. 13,010.00 Say 13010.00
Composite Rate per Sqm. Rs. 1,399.88 Say 1399.90

Page 47
DESCRIPTION OF ITEM

32 Shisham wood block flooring 1" thick cut to required size, fixed on a layer of
asphalt bitumen laid on base

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Shisham Wood of best quality 8.33 Cft.


100 x 1/12' sawan to required size
Add 100 % Wastage 8.33 Cft.
Total 16.66 Cft. 300.00 Per Cft. 4,998.00

Bitumen for laying and dipping blocks 80 Lbs (36.32 Kg.) 14.00 Per Kg. 508.48
Primer 5.00 Lbs (2.27 Kg.) 13.00 Per Kg. 29.51
Fire Wood 0.25 Md (9.33 Kg.) 2.75 Per Kg. 25.66
Sand Paper 2.00 Dozen 72.00 Per Dozen 144.00
Total 5,705.65
Contractor's Profit & Overheads 20 Percent 1,141.13
Total 6,846.78

LABOUR FOR 200 SFT.

Carpenters 6.00 No. 300.00 Per day 1,800.00


Coolies 5.00 No. 140.00 Per day 700.00
Total 2,500.00
Sundries 10 Percent 250.00
Total 2750.00
Contractor's Profit & Overheads 20 Percent 550.00
Total 3300.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. 1,650.00 Say 1650.00


Labour Rate Per Sqm. Rs. 177.54 Say 177.55
Composite Rate per 100 Sft. Rs. 8,496.78 Say 8496.80
Composite Rate per Sqm. Rs. 914.25 Say 914.25

Page 48
DESCRIPTION OF ITEM

33 Teak wood block 1" thick cut to required size fixed on a layer of asphalt bitumen laid on base

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Teak wood for blocks 1" 8.33 Cft.


thick sawn to size 100 x1/12'
Add 40% Wastage 3.33 Cft.
Total 11.66 Cft. 1400.00 Per Cft. 16,324.00

Bitumen 80 Lbs (36.32 Kg.) 14.00 Per Kg. 508.48


Primer 5.00 Lbs (2.27 Kg.) 13.00 Per Kg. 29.51
Fuel Wood 0.125 Lbs (4.67 Kg.) 2.75 Per Kg. 12.84
Sand Paper 2.00 Dozen 72.00 Per Dozen 144.00
Total 17,018.83
Contractor's Profit & Overheads 20 Percent 3,403.77
Total 20,422.60

LABOUR FOR 300 SFT.

Carpenters 10.00 No. 300.00 Per day 3,000.00


Coolies 5.00 No. 140.00 Per day 700.00
Total 3,700.00
Sundries 10 Percent 370.00
Total 4070.00
Contractor's Profit & Overheads 20 Percent 814.00
Total 4884.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. 1,628.00 Say 1628.00


Labour Rate Per Sqm. Rs. 175.17 Say 175.15
Composite Rate per 100 Sft. Rs. 22,050.60 Say 22050.60
Composite Rate per Sqm. Rs. 2,372.64 Say 2372.65

Page 49
DESCRIPTION OF ITEM

34 Laying wooden paving of hard wood on edge in coal tar and asphalt

a) Shisham Wood

Detail Unit Rate Per 100 Sft. (Per Inch Thickness)


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Shisham Wood Sawn into 8.33 Cft.


1" thick or any required size
Add 30% Wastage 2.50 Cft.
Total 10.83 Cft. 300.00 Per Cft. 3,249.00

Bitumen 34 Lbs / 15.44 Kg. 14.00 Per Kg. 216.16


Total 3,465.16
Contractor's Profit & Overheads 20 Percent 693.03
Total 4,158.19

LABOUR FOR 150 SFT.

Carpenters 1.00 No. 300.00 Per day 300.00


Coolies 3.00 No. 140.00 Per day 420.00
Mason 1.00 No. 300.00 Per day 300.00
Total 1,020.00
Sundries 10 Percent 102.00
Total 1122.00
Contractor's Profit & Overheads 20 Percent 224.40
Total 1346.40

ITEM RATE

Labour Rate Per 100 Sft. Rs. 897.60 Say 897.60


Labour Rate Per Sqm. Rs. 96.58 Say 96.60
Composite Rate per 100 Sft. Rs. 5,055.79 Say 5055.80
Composite Rate per Sqm. Rs. 544.00 Say 544.00

Page 50
b) Kikar Wood

Detail Unit Rate Per 100 Sft. (Per Inch Thickness)


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Kikar Wood = 100 x 1 8.33 Cft.


12
Wastage 30% 2.50 Cft.
Total 10.83 Cft. 250.00 Per Cft. 2,707.50

Bitumen 34 Lbs (15.44 Kg.) 14.00 Per Kg. 216.16


Total 2,923.66
Contractor's Profit & Overheads 20 Percent 584.73
Total 3,508.39

LABOUR FOR 150 SFT.

Carpenter 1.00 No. 300.00 Per day 300.00


Coolies 3.00 No. 140.00 Per day 420.00
Mason 1.00 No. 300.00 Per day 300.00
Total 1,020.00
Sundries 10 Percent 102.00
Total 1122.00
Contractor's Profit & Overheads 20 Percent 224.40
Total 1346.40

ITEM RATE

Labour Rate Per 100 Sft. Rs. 897.60 Say 897.60


Labour Rate Per Sqm. Rs. 96.58 Say 96.60
Composite Rate per 100 Sft. Rs. 4,405.99 Say 4406.00
Composite Rate per Sqm. Rs. 474.08 Say 474.10

Page 51
DESCRIPTION OF ITEM

35 Tile skirting laid in 1:2 cement mortar over 3/4" thick cement mortar 1:2 including
cement washing and filling joints complete.

a) Cement Tiles

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Cement tiles 8"x8" including 5% breakage 240 No. 7.00 Each 1,680.00
and Wastage
Cement for laying and pointing cement tiles 2.45 Bags 230.00 Per Bag 563.50
Sand 6.00 Cft. 350.00 Per 100 Cft. 21.00
Pigment 1 Lb (0.45 Kg.) 70.00 Per Kg. 31.50
Total 2,296.00
Contractor's Profit & Overheads 20 Percent 459.20
Total 2,755.20

LABOUR FOR 150 SFT.

Masons 1.56 No. 300.00 Per day 468.00


Coolies 2.50 No. 140.00 Per day 350.00
Bahishti 0.34 No. 160.00 Per day 54.40
Total 872.40
Sundries 10 Percent 87.24
Total 959.64
Contractor's Profit & Overheads 20 Percent 191.93
Total 1151.57

ITEM RATE

Labour Rate Per 100 Sft. Rs. 767.71 Say 767.70


Labour Rate Per Sqm. Rs. 82.61 Say 82.60
Composite Rate per 100 Sft. Rs. 3,522.91 Say 3522.90
Composite Rate per Sqm. Rs. 379.07 Say 379.05

Page 52
b) Mosaic Tiles

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Tiles 6"x6"x3/4" 420 No. 6.50 Each 2,730.00


Cement 2.54 Bag 230.00 Per Bag 584.20
Sand 6.00 Cft 350.00 Per 100 Cft. 21.00
Pigment 1 Lbs (0.45 Kg.) 70.00 Per Kg. 31.50
White Cement 0.08 Bag 345.00 Per Bag 27.60
Total 3,394.30
Contractor's Profit & Overheads 20 Percent 678.86
Total 4,073.16

LABOUR

Masons 2.00 No. 300.00 Per day 600.00


Coolies 2.50 No. 140.00 Per day 350.00
Bahishti 0.25 No. 160.00 Per day 40.00
Total 990.00
Sundries 10 Percent 99.00
Total 1089.00
Contractor's Profit & Overheads 20 Percent 217.80
Total 1306.80

ITEM RATE

Labour Rate Per 100 Sft. Rs. 1,306.80 Say 1306.80


Labour Rate Per Sqm. Rs. 140.61 Say 140.60
Composite Rate per 100 Sft. Rs. 5,379.96 Say 5379.95
Composite Rate per Sqm. Rs. 578.88 Say 578.90

Page 53
DESCRIPTION OF ITEM

36 Providing grey cement skirting or dado 3/8" thick including rounding of corner and
straightening of top edge and finishing to smooth surface after plastering

a) 1:2 Cement Sand Mortar

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Cement 0.96 Bag 230.00 Per Bag 220.80


Sand 2.50 Cft. 350.00 Per 100 Cft. 8.75
Total 229.55
Contractor's Profit & Overheads 20 Percent 45.91
Total 275.46

LABOUR FOR 125 SFT.

Masons 2.50 No. 300.00 Per day 750.00


Coolies 1.50 No. 140.00 Per day 210.00
Bahishti 0.34 No. 160.00 Per day 54.40
Total 1,014.40
Sundries 10 Percent 101.44
Total 1115.84
Contractor's Profit & Overheads 20 Percent 223.17
Total 1339.01

ITEM RATE

Labour Rate Per 100 Sft. Rs. 1,071.21 Say 1071.20


Labour Rate Per Sqm. Rs. 115.26 Say 115.25
Composite Rate per 100 Sft. Rs. 1,346.67 Say 1346.65
Composite Rate per Sqm. Rs. 144.90 Say 144.90

Page 54
b) 1:3 Cement Sand Mortar

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Cement 0.66 Bag 230.00 Per Bag 151.80


Sand 2.55 Bag 350.00 Per 100 Cft. 8.93
Total 160.73
Contractor's Profit & Overheads 20 Percent 32.15
Total 192.87

LABOUR FOR 125 SFT.

Masons 2.50 No. 300.00 Per day 750.00


Coolies 1.50 No. 140.00 Per day 210.00
Bahishti 0.34 No. 160.00 Per day 54.40
Total 1,014.40
Sundries 10 Percent 101.44
Total 1115.84
Contractor's Profit & Overheads 20 Percent 223.17
Total 1339.01

ITEM RATE

Labour Rate Per 100 Sft. Rs. 1,071.21 Say 1071.20


Labour Rate Per Sqm. Rs. 115.26 Say 115.25
Composite Rate per 100 Sft. Rs. 1,264.08 Say 1264.10
Composite Rate per Sqm. Rs. 136.01 Say 136.00

Page 55
c) Extra if skirting or dado is finished with pigment of any colour

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Pigment 6 Lbs (2.72 Kg.) 70.00 Per Kg. 190.40


Contractor's Profit & Overheads 20 Percent 38.08
Total 228.48

LABOUR FOR 200 SFT.

Cooly for mixing 0.50 No. 140.00 Per day 70.00


Sundries 10 Percent 7.00
Total 77.00
Contractor's Profit & Overheads 20 Percent 15.40
Total 92.40

ITEM RATE

Labour Rate Per 100 Sft. Rs. 46.20 Say 46.20


Labour Rate Per Sqm. Rs. 4.97 Say 4.95
Composite Rate per 100 Sft. Rs. 274.68 Say 274.70
Composite Rate per Sqm. Rs. 29.56 Say 29.55

Page 56
DESCRIPTION OF ITEM

37 White glazed tiles ¼" thick dado jointed in white cement and laid over 1:2 cement
sand mortar 3/4" thick including finishing complete

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Tiles 6"x6"x¼" 420 No. 9.00 Each 3,780.00


White Cement 0.10 Bag 345.00 Per Bag 34.50
Grey Cement 2.16 Bag 230.00 Per Bag 496.80
Sand 5.20 Cft. 350.00 Per 100 Cft. 18.20
Total 4,329.50
Contractor's Profit & Overheads 20 Percent 865.90
Total 5,195.40

LABOUR

Mason 2.50 No. 300.00 Per day 750.00


Coolies 5.00 No. 140.00 Per day 700.00
Bahishti 0.50 No. 160.00 Per day 80.00
Total 1,530.00
Sundries 10 Percent 153.00
Total 1683.00
Contractor's Profit & Overheads 20 Percent 336.60
Total 2019.60

ITEM RATE

Labour Rate Per 100 Sft. Rs. 2,019.60 Say 2019.60


Labour Rate Per Sqm. Rs. 217.31 Say 217.30
Composite Rate per 100 Sft. Rs. 7,215.00 Say 7215.00
Composite Rate per Sqm. Rs. 776.33 Say 776.35

Page 57
DESCRIPTION OF ITEM

38 Glazed tile dado ¼" thick dado laid in pigment over 1:2 cement sand mortar 3/4" thick
including finishing

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Tiles 6"x6"x¼" 420 No. 9.00 Each 3,780.00


White Cement 0.10 Bag 345.00 Per Bag 34.50
Grey Cement 2.16 Bag 230.00 Per Bag 496.80
Pigment 0.67 Lb (0.30 Kg.) 70.00 Per Kg. 21.00
Sand 5.00 Cft. 350.00 Per 100 Cft. 17.50
Total 4,349.80
Contractor's Profit & Overheads 20 Percent 869.96
Total 5,219.76

LABOUR

Mason 2.50 No. 300.00 Per day 750.00


Coolies 5.00 No. 140.00 Per day 700.00
Bahishti 0.50 No. 160.00 Per day 80.00
Total 1,530.00
Sundries 10 Percent 153.00
Total 1683.00
Contractor's Profit & Overheads 20 Percent 336.60
Total 2019.60

ITEM RATE

Labour Rate Per 100 Sft. Rs. 2,019.60 Say 2019.60


Labour Rate Per Sqm. Rs. 217.31 Say 217.30
Composite Rate per 100 Sft. Rs. 7,239.36 Say 7239.35
Composite Rate per Sqm. Rs. 778.96 Say 778.95

Page 58
DESCRIPTION OF ITEM

39 Masaic dado or skirting with one part of cement and marble powder in the ratio of
3:! and two parts of marble chips, laid over ½" thick cement plaster 1:3 including
rubbing and polishing complete with finishing:

a - i) Using Grey Cement 3/8" Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Grey Cement 0.94 Bags 230.00 Bag 216.20


Marble Powder 0.31 Cwt. (15.75 Kg.) 80.00 Per 100 Kg. 12.60
Marble Chips 3.00 Cwt.(152.40 Kg.) 1.00 Per Kg. 152.40
Carbordum Stone 3 No. 35.00 Per Kg. 105.00
Wax Polish 0.5 Lbs (0.23 Kg.) 635.00 Packet 3 Kg. 48.68
Tartric Acid 0.34 Lbs (0.15 Kg.) 65.00 Per Kg. 9.75
Total 544.63
Contractor's Profit & Overheads 20 Percent 108.93
Total 653.56

LABOUR

Mason 2.00 No. 300.00 Per day 600.00


Coolies 2.00 No. 140.00 Per day 280.00
Skilled Cooly 5.00 No. 160.00 Per day 800.00
Bahishti 1.00 No. 160.00 Per day 160.00
Total 1,840.00
Sundries 10 Percent 184.00
Total 2024.00
Contractor's Profit & Overheads 20 Percent 404.80
Total 2428.80

ITEM RATE

Labour Rate Per 100 Sft. Rs. 2,428.80 Say 2428.80


Labour Rate Per Sqm. Rs. 261.34 Say 261.35
Composite Rate per 100 Sft. Rs. 3,082.36 Say 3082.35
Composite Rate per Sqm. Rs. 331.66 Say 331.65

Page 59
a-ii) Using Grey Cement ½" Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Cement 1.27 Bags 230.00 Bag 292.10


Marble Powder 0.42 Cwt. (21.34 Kg.) 80.00 Per 100 Kg. 17.07
Marble Chips 3 Cwt. (152.40 Kg.) 1.00 Per Kg. 152.40
Carboradom Stone 3 No. 35.00 Each 105.00
Wax Polish 0.5 Lbs (0.23 Kg.) 635.00 Packet 3 Kg. 48.68
Linion Cloth 0.72 Kg. 25.00 P. Kg. 18.00
Tartric Acid 0.34 Lbs (0.15 Kg.) 65.00 Per Kg. 9.75

½"cement plaster under neath

Cement 0.88 Bag 230.00 Bag 202.40


Sand 3.40 Cft. 350.00 Per 100 Cft. 11.90
Total 857.31
Contractor's Profit & Overheads 20 Percent 171.46
Total 1,028.77

LABOUR

Mason 2.00 No. 300.00 Per day 600.00


Cooly 2.00 No. 140.00 Per day 280.00
Skilled Cooly 5.00 No. 160.00 Per day 800.00
Bahishti 1.00 No. 160.00 Per day 160.00
Total 1,840.00
Sundries 10 Percent 184.00
Total 2024.00
Contractor's Profit & Overheads 20 Percent 404.80
Total 2428.80

ITEM RATE

Labour Rate Per 100 Sft. Rs. 2,428.80 Say 2428.80


Labour Rate Per Sqm. Rs. 261.34 Say 261.35
Composite Rate per 100 Sft. Rs. 3,457.57 Say 3457.55
Composite Rate per Sqm. Rs. 372.03 Say 372.05

Page 60
b-i) Using White Cement 3/8" thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

i) 3/8" Thick

White Cement 0.94 Bags 345.00 Bag 324.30


Marble Powder 0.31 Cwt. (15.75 Kg.) 80.00 Per 100 Kg. 12.60
Marble Chips 3 Cwt. (152.40 Kg.) 1.00 Per Kg. 152.40
Carboradom Stone 3 No. 35.00 Each 105.00
Wax Polish 0.5 Lbs (0.23 Kg.) 635.00 Packet 3 Kg. 48.68
Linion Cloth 0.72 Kg. 25.00 P. Kg. 18.00
Tartric Acid 0.34 Lbs (0.15 Kg.) 65.00 Per Kg. 9.75

ii) ½"cement plaster under neath

Grey Cement 0.88 Bag 230.00 Bag 202.40


Sand 3.40 Cft. 350.00 Per 100 Cft. 11.90
Total 885.03
Contractor's Profit & Overheads 20 Percent 177.01
Total 1,062.04

LABOUR

Mason for Laying 2.00 No. 300.00 Per day 600.00


Coolies for rubbing and polishing 5.00 No. 160.00 Per day 800.00
Coolies 2.00 No. 140.00 Per day 280.00
Bahishti 1.00 No. 160.00 Per day 160.00
Total 1,840.00
Sundries 10 Percent 184.00
Total 2024.00
Contractor's Profit & Overheads 20 Percent 404.80
Total 2428.80

ITEM RATE

Labour Rate Per 100 Sft. Rs. 2,428.80 Say 2428.80


Labour Rate Per Sqm. Rs. 261.34 Say 261.35
Composite Rate per 100 Sft. Rs. 3,490.84 Say 3490.85
Composite Rate per Sqm. Rs. 375.61 Say 375.60

Page 61
b-ii) Using White Cement (½" thick)

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

i) ½ Thick

White Cement 1.27 Bags 345.00 Bag 438.15


Marble Powder 0.42 Cwt. (21.34 Kg.) 80.00 Per 100 Kg. 17.07
Marble Chips 3 Cwt. (152.40 Kg.) 1.00 Per Kg. 152.40
Carboradom Stone 3 No. 35.00 Each 105.00
Wax Polish 0.5 Lbs (0.23 Kg.) 635.00 Packet 3 Kg. 48.68
Linion Cloth 0.72 Kg. 25.00 P. Kg. 18.00
Tartric Acid 0.34 Lbs / 0.15 Kg. 65.00 Per Kg. 9.75

ii) ½"cement plaster 1:3 under neath

Grey Cement 0.88 Bag 230.00 Bag 202.40


Sand 3.40 Cft. 350.00 Per 100 Cft. 11.90
Total 959.35
Contractor's Profit & Overheads 20 Percent 191.87
Total 1,151.22

LABOUR

Mason 2.00 No. 300.00 Per day 600.00


Skilled Cooly 5.00 No. 160.00 Per day 800.00
Coolies 2.00 No. 140.00 Per day 280.00
Bahishti 1.00 No. 160.00 Per day 160.00
Total 1,840.00
Sundries 10 Percent 184.00
Total 2024.00
Contractor's Profit & Overheads 20 Percent 404.80
Total 2428.80

ITEM RATE

Labour Rate Per 100 Sft. Rs. 2,428.80 Say 2428.80


Labour Rate Per Sqm. Rs. 261.34 Say 261.35
Composite Rate per 100 Sft. Rs. 3,580.02 Say 3580.00
Composite Rate per Sqm. Rs. 385.21 Say 385.20

Page 62
DESCRIPTION ITEM

40 Rubber Flooring, consisting of 12"x12"x1/8" rubber tiles laid on firm foundation

Detail Unit Rate Per Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

(Assume for 100 Sft.)

MATERIAL

Rubber tiles (12"x12"x1/8") 105 Nos. 40.00 Each 4,200.00


including 5% wastage
Adhesive mixutre (10 Lbs) (4.56 Kg.) 4.56 Kg. 120.00 Kg. 547.20
Brushes etc. 0.04 No. 100.00 Each 4.00
Total 4,751.20
Contractor's Profit & Overheads 20 Percent 950.24
Total 5,701.44

LABOUR

Mason 1.00 No. 300.00 Per day 300.00


Coolies 1.50 No. 140.00 Per day 210.00
Total 510.00
Sundries 10 Percent 51.00
Total 561.00
Contractor's Profit & Overheads 20 Percent 112.20
Total 673.20

ITEM RATE

Labour Rate Per Sft. Rs. 6.73 Say 6.75


Labour Rate Per Sqm. Rs. 72.44 Say 72.45
Composite Rate per Sft. Rs. 63.75 Say 63.75
Composite Rate per Sqm. Rs. 685.91 Say 685.90

Page 63
DESCRIPTION OF ITEM

41 Providing and Fixing Glass Strip 5mm thick and 1½" wide
for dividing mosaic flooring into panels.

Detail Unit Rate Per Rft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

(Assume for 100 Rft.)

MATERIAL

Glass Strips 1½" wide


5mm Thick 100.00 Rft.
Wastage 10% 10.00 Rft.
Total 110.00 Rft. 220.00 Per 100 Rft 242.00
Contractor's Profit & Overheads 20 Percent 48.40
Total 290.40

ITEM RATE

Composite Rate per Rft. Rs. 2.90 Say 2.90

Composite Rate per R.M. Rs. 9.53 Say 9.55

Note : Labour for fixing already included in item 15 & 22 of this chapter

Page 64
DESCRIPTION OF ITEM

42 Providing and fixing marble strip of any shade for dividing the mosaic flooring into pannels.

a) Size 1½" x 3/8"

Detail Unit Rate Per Rft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

(Assume for 100 Rft.)

MATERIAL

Marble Strip 1½" x 3/8" 100.00 Rft.


Wastage 10% 10.00 Rft.
Total 110.00 Rft. 4.00 Per Rft. 440.00
Contractor's Profit & Overheads 20 Percent 88.00
Total 528.00

ITEM RATE

Composite Rate per Rft. Rs. 5.28 Say 5.30

Composite Rate per R/M Rs. 17.32 Say 17.30

Note Labour already included in item 15, 16 and 22 of this chapter.

Page 65
b) Size 1½" x ¼"

Detail Unit Rate Per Rft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

(Assume for 100 Rft.)

MATERIAL

Marble Strips 1½" x ¼" 100.00 Rft.


Wastage 10% 10.00 Rft.
Total 110.00 Rft. 3.00 Per Rft. 330.00
Contractor's Profit & Overheads 20 Percent 66.00
Total 396.00

ITEM RATE

Composite Rate per Rft. Rs. 3.96 Say 3.95

Composite Rate per R/M Rs. 12.99 Say 13.00

Note Labour already included in item 15, 16 and 22 of this chapter.

Page 66

You might also like