Rev 0
May 2012
Upstream Operations
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Table of Contents
1.0 FOREWARD 5
1.1 Scope of Document 5
1.2 Document Revisions and Approval 5
1.3 Distribution and Intended Audience 5
2.0 RESPONSIBILITIES 5
4.0 DESIGN 11
5.0 PLANNING 11
5.1 Survey of Area to be Excavated 12
5.2 Adjacent Buildings or Structures 12
5.3 Location of Underground Pipes and Cables 12
5.4 Excavation to Expose Existing Pipes or Cables 13
5.5 Excavation Around Live Underground Services 13
5.6 Excavation underneath electrical hazards or overhead obstructions 13
5.7 Selection and Transport of Excavation Equipment 14
5.8 Working Room and Working Alone 14
5.9 Work at Night/ Lighting 14
5.10 Backfilling 15
3 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
4 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
1.0 FOREWARD
1.1 Scope of Document
The purpose of the QGC Excavation procedure is to assist all personnel working on all QGC Operations
and Projects sites to carry out work in accordance with safe working practices for excavation and ground
penetrations.
The Excavation procedure has been developed to ensure compliance with applicable BG Standards and
is to be used in conjunction with all applicable legislation, including Codes of Practice, and relevant
Australian Standards.
The document applies to all QGC personnel and contracting staff working on sites under QGC Upstream
Operations or Project control and will follow the principles established in the QGC PTW Procedure
(QCOPS-BX00-HSS-PCE-000002).
The QGC Excavation and Digging procedure applies to all Operational sites (Brownfield sites) and to all
Upstream Project sites. Greenfield sites are designated through the Greenfield Construction Assessment
Process and a formal handover of Greenfield designated real-estate is undertaken before any Greenfield
construction work can commence.
Note: Where there are differences in process for Greenfield sites, these are clearly identified in Greenfield
text boxes.
This procedure addresses the HSE aspects of ground penetrations, open excavation, trenching and
shoring operations on QGC .
This document defines the responsibilities of nominated persons and approvals required for the
excavation.
Local legislation may detail additional requirements and workplaces must include any further detail when
considering the application of this procedure relevant to the workplace risk assessments.
2.0 RESPONSIBILITIES
The following responsibilities apply for all personnel undertaking activities covered by this document.
Role Responsibility
General Manager, Field a) Provide a safe system of work where persons are not exposed to
Operations hazards by ensuring that where reasonably practicable, any work
involving risk to health, safety or the environment is eliminated, or
appropriate control measures are in place to remove all
unacceptable risks.
b) Ensure that all aspects of the QGC Operations Excavation
5 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Role Responsibility
6 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Role Responsibility
7 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Role Responsibility
Work Party Member a) Participate in the review of the SWMS, JSEA, rescue plan and
other supporting documents under the PTW, prior to work
commencing.
b) Stop work activity and review the SWMS & JSEA with a
Supervisor and/or work group when workers foresee any new
hazard, potential issues or scope of work changes during the
course of the task.
c) Ensure individual familiarity with the approved PTW content,
including Excavation procedure requirements and comply while
completing the task.
d) Will ask questions and clarify SWMS content before signing onto
a SWMS or JSEA within the PTW form.
e) Will not perform any work unless trained, competent and holding
relevant, licences/certifications for the task at hand.
f) Will familiarise themselves with work hazards and relevant
controls (including isolations) and will not commence work unless
all control measures identified in the SWMS and JSEA are in
place.
g) Notify the Permit Holder of any damage or deficiency observed in
any equipment and remove from service where required.
Permit Issuer a) Ensure that all identified high risk work is undertaken under the
PTW system and that authorisations are obtained from Endorsing
Authorities for Excavation when required.
b) Review and approve the SWMS, PTW and supporting
documentation - specifically Excavation - prior to issuing to the
Permit Holder.
c) Ensure all persons performing high risk work hold the relevant
certificates/licences and are trained and competent to perform
the work.
d) Ensure all controls necessary for safe work involving Excavation
are documented in the SWMS and PTW and its supporting
documentation (Certificates and plans).
e) Ensure any Proximity TAN requirements are identified and
brought to the attention of the Permit Holder.
f) Recommend suitable tasks for inclusion on the Approved Task
List
Endorsing Authority a) Within their expertise ensure that all controls for specified high
risk work are documented in the SWMS, the PTW and the PTW
Certificate/s.
b) Certify on the PTW Certificates that all controls are appropriate
for the task.
c) Provide advice to the workforce on their area of expertise.
d) Ensure processes for monitoring, auditing and reviewing the
PTW system are established and maintained.
HSSE Manager a) Ensure the Excavation procedure complies with BG Group and
Australian Regulatory requirements.
b) Ensure the Excavation procedure is audited as per the audit
schedule and monitor close out of non-conformances.
c) Provide advice on Excavation best practice for continuous
improvement.
d) Ensure this procedure is reviewed and kept-up-to-date.
e) Ensure Excavation training and mentoring is provided to
applicable persons as per the requirements of this procedure.
8 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Role Responsibility
9 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
For excavations and trenches across roads, the control of traffic and pedestrians must be considered in
the SWMS. Consideration must be given to preparing a traffic management plan.
The SWMS must be retained with the PTW documentation for the excavation and may be used for
subsequent excavations at the same site if the conditions remain constant and unchanged from the
development of the original SWMS.
The SWMS must consider the reason for the excavation and all applicable hazards associated with the
work and the particular work site. The following provides a list of hazards that must be considered as a
minimum:
local site conditions, including access, ground slope, adjacent buildings and structures, water
courses (including underground) and trees;
depth of the excavation;
soil properties, including variable soil types, stability, shear strength, cohesion, presence or ground
water, effect of exposure to the elements;
proximity of live sewerage service line to the excavation;
potential for sewerage seepage, or methane gas/vapour migration;
the condition of the soil substrate;
fractures or faults in rocks, including joints, bedding planes, dip and strike directions and angles, clay
seams;
any specialised plant or work methods required (for example ground support);
the method(s) of transport, haul routes and disposal;
what exposures may occur, such as to noise or UV rays;
the number of people involved;
the need to enter/work in the excavation;
the possibility of unauthorised access to the work area;
local weather conditions, and
the length of time the excavation or trench will be open.
The SWMS must consider whether the excavation can become a confined space as defined in the QGC
Confined Space Entry Procedure QCOPS-BX00-HSS-PCE-000003. If so, those requirements must apply
in addition to the requirements of this procedure.
The SWMS must consider all reasonably foreseeable hazards and determine the required control
measures for these hazards. Based on the outcome of the risk assessment, all necessary safety systems
and equipment including PPE must be provided and an emergency plan must be prepared.
The JSEA process and/or Step back process must identify any new/ unique hazards specific to the work
area and ensure all persons involved with the activity are aware of the hazards, and controls required
commencing works in a safe manner.
10 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Most Elimination Can the need for excavation be avoided by installing cables or
Effective pipes above ground in pipe racks, cable racks or existing culverts?
Substitution Can an alternate method such as moling, directional drilling or other
non- destructive pipe laying technique be used instead of
excavating?
Engineering / Can barricades, barriers, fencing or handrails be put in place to
Isolation prevent the risk of falls?
Can benching, battering or shoring the sides of an excavation
reduce the risk of ground collapse?
Administrative Can JSEAs, procedures, SWMS, PTW, emergency plans, toolbox
Controls talks and regular inspections minimise exposure?
Least
Personal Protective Can hard hats, hearing protection and high visibility vests protect
Effective
Equipment workers from excavation hazards?
4.0 DESIGN
Designs must optimise the layout, constructability, operability, maintainability and accessibility of facilities,
whilst at the same time minimising the requirement for excavation or trenching during construction and
subsequent operation.
Excavations and any supports must be designed in accordance with acceptable engineering principals
and standards.
5.0 PLANNING
All excavation and trenching work must be planned.
Prior to any excavation works taking place, the ground conditions must be assessed. This can be
achieved through boreholes, trial pits or information from previous or current work in the area. If none of
the above is possible, the ground conditions must be examined when excavation commences.
Planning must consider:
nature and/or condition of the ground and/or working environment;
nature of the work and other activities that may affect safety;
static and dynamic loads near the excavation;
energised power, live gas services;
link up of existing sewerage;
interaction of other work activities;
site access;
management of surrounding vehicular traffic and ground vibration;
nearby structures;
type of equipment used for excavation work;
public safety;
provision of adequate amenities; and
11 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
The results of this survey must be accurately recorded and documentation attached to the PTW.
The excavation or trench must be sited so as to minimise excavation risks, and the possibility of
damaging other services in the vicinity.
For emergency work the relevant information should be obtained as soon as possible after work starts.
Greenfield
A Greenfield construction zone assessment must be undertaken for all Greenfield sites.
Unless the excavation is in stable rock, as determined by a competent person, any excavation that is
below the level of the footing of any structure or retaining wall that could affect the stability of the structure
must be secured by a suitable ground support system. Suitable supports for the structure may also be
required.
In all cases the Permit Holder must ensure that adjacent buildings or structures are not adversely affected
by vibration or concussion during the excavation work. Precautions must be taken to ensure that buildings
or structures containing equipment sensitive to shock and vibration are adequately protected if temporary
relocation of the equipment is not possible.
Excavation work must be carried out in a manner that does not cause flooding or water penetration to any
adjacent building or structure.
For excavation sites outside Operating Plant boundaries, it is a statutory requirement to contact the
national dial before you dig service (www.1100.com.au) and obtain a clearance before any excavation
work starts.
A secondary means of verifying the location of the underground service/s must be used, such as
potholing, prior to any mechanical excavation commencing.
Greenfield
A Greenfield construction zone assessment must be undertaken for all Greenfield sites.
12 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
In all cases where mechanical excavation is used, the exact location of underground pipes and cables
must be verified by hand excavation (with a hand shovel) when mechanical excavation approaches within
500 mm of the pipes or cables. Mechanical excavation is not permitted within 500 mm of existing pipes or
cables. Completion of excavations to expose pipes or cables must be done by hand.
Mechanical excavators must always utilise a machine bucket fitted with a blunt scraper bar to minimise
damage to underground services; buckets with tiger teeth must not be used.
A minimum limit of approach distance of 0.5 metres must apply to mechanical excavating with a spotter
present - towards live underground services (dependant on workplace risk assessment a greater limit
may be required).
Refer to AS 2885.3:2001
13 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
The equipment must be transported to the work site on the appropriate trailer, truck or carrier.
Equipment must be inspected prior to allowing it onto the worksite to ensure it is free of any soil or weeds
from previous jobs.
All ride-on tracked, wheeled or rubber tyre vehicles entering the excavation must be fitted with a certified
FOPS cab or canopy as a minimum and ROPS.
Tracked, wheeled and rubber tyre heavy equipment working around the excavation should also be fitted
with a ROPS cab or canopy.
All excavators working on the site must have ROPS/FOPS cabs or canopies.
All electrical and fuel powered equipment introduced into a trench or operation must be in good
mechanical and electrical order.
Workers must also be separated from active digging faces and active dumps to avoid being struck by
falling material, by an excavator bucket or by any part of the excavator within the excavator swing radius.
No persons must work alone unless there is another person close by that can render assistance or a
dedicated stand by person.
Excavations in public areas and near permanent public access ways need illumination of the edges.
Battery operated flashing lights placed at intervals are usually sufficient.
In deeper excavations or during times of reduced visibility, lighting may be necessary to allow work to
proceed in a safe manner. Lighting must be guarded and installed to prevent damage.
Power leads must be protected from water ingress and mechanical damage. The lighting must be placed
so that the level of illumination at the working area is not less than 200 LUX and access ways and
working areas are free of glare and deep shadow.
All electrical items must comply with the QGC Electrical Safety Procedures.
AS/NZS 3012:2010 Electrical installations Construction and demolition sites (Section 2.7 Lighting
and luminaries)
AS 2293.1 2005 Emergency escape lighting and exit signs for buildings Part 1: System design,
installation and operation (Section 5 Design of emergency escape luminaire installation)
14 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
5.10 Backfilling
Backfilling operations must be considered during the planning process to ensure that the operation is
planned and conducted safely and efficiently whilst achieving the planned standards of compaction.
The PTW can only be issued when the SWMS and the Excavation Certificate are complete and the
control measures are in place or readily available to be installed as the excavation proceeds. The controls
must consider management of the excavation and management of movement around and into the
excavation as well as the reason for the excavation.
For all excavations 1.2 m or greater, a QGC appointed Excavation Endorsing Authority must review and
approve/endorse all PTW applications and supporting documentation
Greenfield
A PTW is required is Greenfield sites as determined by SWMS, JSEA and Permit Issuer.
15 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
All personnel working within or in the region of the trench or excavation must wear high visibility clothing.
In addition to QGC minimum field PPE requirements, other PPE may be required if persons are exposed
to hazardous substances or contaminated soils, are entering confined or restricted areas, or are
conducting activities within the excavation/trench that require additional precautions, e.g. double face
eye/face protection for grinding works.
16 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
All deficiencies noted must be made good; any remedial or other works necessary must be carried out as
soon as possible and, in any intervening period, no other works must be carried out in the excavation.
Copies of the inspection results as well as copies of the excavation and other documents pertinent to the
job must be held with the PTW documentation at a prominent location in the working area.
Note: Anyone may stop the excavation works if the works appear to be unsafe.
The excavation register must record the identification numbers of all approved requests to excavate and
their Excavation Certificates.
Greenfield
Excavation register does not apply to Greenfield sites.
a minimum of two access/ egress points for every 9m or trench must be applied;
ladders may be used but they must extend at least 1 metre above the top; and
where possible, ladders must be placed at or near junctions or corners of an excavation.
If an excavation is more than 1.2 metres deep the following control measures apply to entry:
the Permit Holder must ensure there is ladder access installed at least every 9 metres of length;
for excavations shorter than 9 metres, an emergency means of access must be provided: this can
take the form of a second ladder placed near the excavation that can be installed quickly when
necessary or have ingress / egress ramps either end of trench;
no person must work alone in excavations or trenches and the Permit Holder must enforce this; and
entry points must be secured when work is suspended and the excavation is left unmanned, to avoid
pedestrian and vehicle encroachment. This protection will include, where appropriate, the use of
lighting and reflective signage.
Greenfield
Access / egress ramps must be constructed for all Greenfield excavations.
17 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Relevant details of this table must be included within QGCs Excavation Certificate (QCOPS-BX00-HSS-
CER-000002).
As a guide, section 6.4 below (as per AS 1345:1995 Identification of the contents of pipes, conduits and
ducts), highlights common services and associated colours.
Identification survey pegs must be uniquely labelled / numbered and include information referencing
service type, pipe/conduit configuration and known service depth.
18 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
is de-watering required, and if so, will it affect the stability of the trench?
As an alternative to shoring, at the discretion of a competent person, the sides of the trench may be
stepped or sloped to the natural angle of repose of the loose spoil, and by an angle of no more than 45
between the floor of the excavation and the sidewall.
A competent person must examine the ground conditions and submit a statement in writing detailing the
findings of the examination (as part of the pre-planning for the PTW process).
This statement must include the type(s) of ground encountered, the calculations used in deciding the
method of protection required and any particular issues that need to be addressed. This statement must
be signed by the competent person and kept on file in the project office.
The Area Superintendent must ensure that all legislative requirements are complied with.
For all excavations 1.2 m or greater, a QGC appointed Excavation Endorsing Authority must review and
approve/endorse all PTW applications and supporting documentation
However, these narrow excavations still constitute a hazard for other reasons, and therefore due
consideration must be given to implementing effective controls for those hazards, i.e. covering,
barricading etc.
Narrow excavations, i.e. trenches require a PTW to be issued prior to work commencing.
In circumstances where shoring or other similar support systems are used, they must be installed without
delay as the excavation progresses. The shoring must extend at least 300mm above the edge of the
excavation or a fender board of the same height provided.
Workers installing the system must be given clear instructions including drawings and sketches.
All shoring must be inspected on a daily basis prior to any work commencing.
Additional inspections must be conducted and documented after any fall of the sides or working face or
after blasting.
Where the installation of a support system differs to the requirement of the design plans, all changes must
be referred back to a competent person for approval.
19 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Workers must never work outside the protection of ground support systems, no matter what the
circumstances.
The overall slope of a benched or battered wall may not exceed 45 degrees to the horizontal unless
certified in writing by a competent person or geo-technical engineer.
Each bench cut into the side of a trench must be no higher that its width without the written approval of a
geo-technical engineer and must comply with relevant Australian Standards.
Note: Positive identification of services must occur within a minimum of 3 metres (dependant on
workplace risk assessment) of the planned excavation; this includes the area used to bench or batter.
Control measures must be properly installed and maintained until the work is completed or until there is
no longer any risk of persons falling into the excavation.
The risk of material falling into an excavation increases during high winds. Provision of overhead
protective structures must be assessed and documented where the hazard of falling objects has been
identified.
Every part of the trench or excavation where there is a likelihood of a person falling 1 metre or more must
be provided with barricades or handrails as soon as possible after excavation (dependant on workplace
risk assessment, in particular considering volume of traffic (pedestrian or vehicle) near the excavation
etc). Barriers and barricades must be located a minimum of 1.0 m from the edge of the excavation.
Walkways across trenches must be fitted with handrails. For trenches greater than 1.8 metres the
requirements of the Working at Heights Procedure (edge protection) apply.
Barricades or handrails can be removed to allow access or movement of plant, or materials. Once
access is no longer required the barricades or handrails must be re-instated.
AS1657 Fixed platforms, walkways, stairways and ladders Design, construction and installation
describes the requirements for walkways that must apply to excavations. AS 1657 requires:
20 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
guard rails must be at a height above the walkway of not less than 900 mm or more than 1100 mm;
another rail is required with a gap of no more than 450 mm between it and the top of the toe board
or the top rail unless the there is a sheet of sturdy mesh, sheeting or other material between the top
rail and the toe board;
toe boards must extend at least 100 mm above the surface of the walkway and the gap between the
toe board and the walkway must not exceed 10 mm; and
the minimum width for walkways is 550 mm for walkways with guard rails on both sides otherwise
the minimum width is 600 mm. The recommended width for two way traffic is 900 mm.
Note: refer also to QGC Fall Prevention Procedure (QCOPS-BX00-HSS-PCE-000004)
barricades;
barriers;
fencing; and
handrails.
Barriers or stop blocks must be installed where there is an identified risk of cranes, dumpers, tip trucks,
etc. manoeuvring too close to the edge of the trench and endangering its stability or falling into the
excavation.
Care must be taken with selecting barricading material. Substantial barriers or barricades must be used
instead of materials such as webbing fences.
Webbing fences must only be used for pedestrian traffic management, not for fall protection. Clear and
sufficient signs must be posted to at the entrances to the excavation to highlight the excavation hazard
and any particular hazards encountered within the excavation such as a confined space.
As a minimum, AS 1742.32009 Manual of uniform traffic control devices Part 3: Traffic control for works
on roads provides prescriptive detail regarding the type of barriers required to protect workers and the
public in addition to signage requirements and this must be complied with.
21 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Vibrating and impact machinery must be operated and kept well clear of excavation/trench sides.
It may be necessary to bridge excavations temporarily to provide access to premises or to permit the
passage of vehicles when work is temporarily suspended. In such situations a competent person must
determine the use and design of temporary bridging.
When road plates are used the following precautions must apply:
the trench sides must be stable or suitable supported(taking into account anticipated traffic loading);
no person must work under a road plate( unless traffic is halted);
the plate should be of sufficient length to be firmly supported for at least 600 mm on each side of the
trench and of a width sufficient to provide a distance of at least 250 mm from the wheels of vehicles
to the edge of the plate( or as determined by a competent person;
the thickness of the plate should be sufficient to support the range of traffic encountered;
ramps should be formed of a suitable material where the road plate is proud of the road surface;
when the site is not attended, or when subject to frequent use by heavy vehicles, consideration
should be given to securing the road plate(s) by pinning or sinking into the roadway.
appropriate ramp warning signs must be displayed;
all road plates on unmanned sites should be submitted to visual inspection on a regular basis;
appropriate lifting and handling precautions must be taken to ensure that the road plates are
transported, installed and removed safely; and
fabricated bridges must have engineering certification for load bearing capacity
A Confined Space Certificate is required before entering an excavation if the excavation is determined to
be a Confined Space (QCOPS-BX00-HSS-CER-000001).
The Area Superintendent must ensure that the requirements for confined spaces in trenches and
excavations are clearly defined and understood.
22 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Less hazardous substances must be used wherever possible. A MSDS (material safety data sheet)
register must be maintained on site and the MSDS must be readily available in the area where the
substances are used.
If it is determined that these substances may be present or if they are encountered during the excavation
process, then a system to eliminate or control these hazards must be investigated and implemented.
Consideration must also be given to the storage and eventual treatment or disposal of these materials
The Area Superintendent must ensure that any material imported as fill or exported as waste material has
been evaluated for contamination.
In some circumstances, exporting contaminated material from a site requires local/State government
approvals and these must be obtained before the material is allowed to leave the site.
The Area Superintendent must ensure geo-technical assessment of the site investigates the potential of
encountering acid sulphate soils during trenching and excavation operations.
Personnel involved in excavations where acid sulphate soils are an identified risk must receive training in
how to recognise acid sulphate soils and how to manage the risks.
Acid sulphate soils must be managed and treated through the application of lime or by ensuring that the
affected area is maintained in a water submerged state to control oxidation.
23 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Similarly when pipelines, mains or ducts are to be installed by non-destructive techniques (e.g. moling,
horizontal directional drilling) all other underground services in the vicinity of the route must be located
and exposed by hand digging in advance. Where the planned route crosses above other buried services
then the safe passage of the pipe laying tool must be verified by opening an excavation immediately
above the verified position of the third party services to an appropriate depth.
nsure that existing underground services are not damaged, particularly with respect to electrical cables.
Cables and pipe locators must be used to confirm the position of existing cables and other metallic
underground services prior to the commencement of work, and also at frequent intervals as excavation
proceeds.
Consideration must be given to isolation electrical services where practical (buried and overhead)>
Warning notices must be erected on the approaches to overhead power lines or obstructions.
For trenches or open excavations that shall be occupied by personnel, the minimum setback for spoil
must be 1.0m.
For excavations in trafficked roads where conditions permit, consideration should be given to placing the
excavated soil so as to form an additional barrier against traffic. In all cases, excavated materials must be
placed so as not to cause a hazard to personnel, pedestrians or road traffic. Toe boards must be installed
for deep excavations where there is an injury risk from falling spoil, tools or other objects.
Where the excavation material is to be re-used, the surface materials must be kept separate from the
subsoil, so that suitable layers may be replaced in the proper order during reinstatement. Inn these
circumstances the excavated material should be protected against adverse wet weather conditions or
excessive drying out. Consideration should be given to covering the excavated material in order to
maintain the moisture content.
Greenfield
A minimum of 1.0 m must be left between the trench and excavated material.
24 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Consideration must be given to the potential for exhaust gases from equipment outside the excavation
entering the workings and exhaust gases from equipment inside the workings not being carried away
from the work area by natural ventilation.
In particular, issues such as work hours, site access, and noise and traffic disruption must be considered
and appropriate measures included in the site environmental management plan to minimise their impact.
Where appropriate, notifying the community of upcoming works must assist in lessening their impact and
in some situations may be mandatory.
11.2 Noise
Provision must be made to manage noise within and around the excavation. This includes noise hazards
to those around and within the excavation and noise emission from the works.
All efforts must be made to eliminate or engineer the source of the noise consistent with the hierarchy of
controls.
Sources of water ingress are seepage, flooding from other existing watercourses, flooding from storm
events, flooding from burst water mains and sewers in the excavation and similar. Tidal or stream effects
may also impact excavations in coastal or fluvial environments.
Water that has occupied a trench or excavation for even a short period may not be suitable for direct
discharge to local waters or the storm water system.
The Area Superintendent must ensure the quality of water requiring disposal has been assessed and that
disposal meets local/State government regulations.
25 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Alternative water removing methods must be considered in any of the following circumstances:
11.6 Plant wash down (seed transfer) for excavation equipment and transport.
Vehicles and machinery are recognised as a major source spreading declared weeds. Plant and
equipment must arrive on, and exit the site clean and free from a build up of dirt or plant material.
Wash down facilities must be established as identified in the WAP or WP risk assessment, i.e. in a known
declared weed area.
be an issue, the Area Superintendent must ensure that the cultural, ecological and archaeological value
of the site has been assessed and appropriate measures are in place to maintain the values identified.
26 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
To protect pipe coatings and polyethylene pipe, subsoil fill must be clean, moist and free from sharp
stones greater than 18 mm in size. Backfill soil may be sieved to meet this requirement or soil may be
imported as required.
Cementatious materials must not be used as fine fill material around pipes. Fine fill material should be
packed firmly around pipes or fittings to give a minimum compacted thickness of 75 mm.
When placing fine fill around large diameter pipes, or where the side gap between the wall of the
excavation and the pipe is greater than 75 mm, special care must be taken to ensure firm compaction of
the fine fill especially around the lower half of the pipe.
The required thickness of other levels of reinstatement will depend on the location of the excavation or
trench (e.g. private land, carriageway, footway, etc.) and the requirements of the landowner or
management authority. All unbound materials used in these levels must be placed in layers no deeper
than 300mm within the trench and firmly compacted using approved mechanical compaction equipment.
Excavated material may be suitable for re-use as backfill material provided that the material is moist,
does not contain any particles larger than 75 mm and is not uniformly graded i.e. is not single-sized.
At the completion of the work, the work site must be cleared of all rocks, soil and other debris and
returned, as far as is practicable, to its original condition or finished to an agreed plan.
Drawings and other documentation must be updated to reflect any changes due to the work just
completed.
Any re-vegetation of the work area must be conducted with suitable species and in consultation with
relevant local government personnel.
All personnel involved in the activity must be consulted with regards to the agreed SWMS, JSEA and the
controls required completing the works safely.
Specific competencies for excavation and trenching e.g. confined space must be identified during the
work planning process to ensure persons have the correct competencies prior to commencing excavation
works.
13.1 Supervision
A supervisor is a suitably qualified / competent person responsible for / in charge of the excavation /
trenching work.
27 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
All relevant documentation must be sighted and recorded on a register and confirmed by the Permit
Issuer as part of the permit issue process.
All operators of powered plant and equipment must have their competency verified by an approved QGC
person before they can operate on site.
A detailed Annual Audit of the Excavation procedure will be carried out to examine the adequacy of the
procedure in terms of the range of work activities undertaken, effective application of the procedures.
The annual audit should examine the fundamental content and compliance to the procedure, and is best
performed by a person familiar with the PTW System and Excavation procedure, but independent from
the Operations and Project areas in question.
28 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Consulted:
Enter name/position of those required to review the document (excl. Key Consulted persons see
forward)
Dave Preston - HSSE Manager Trevor Love - Contractor - Cons Special Advisor
Carl Martin - Field GM Douglas Smith - Senior Project Manager
Joe Gogarty Permit Authority Rob Ries Training & Competency Supervisor
Brendan Galloway - Lead HSSE Advisor Louise Edgley - HSSE Mgt Systems & Audit Advisor
Vicki Wright Maintenance Supervisor Larry Buckeridge - Sen Project Manager
Nicole Copeland - Principal Safety Advisor Richard Schokman - Operations Support Manager
Andrew Raguse - Maintenance Eric Marsden Area Operations Superintendent(Kenya)
Superintendent
Charles Knecht - Field Operations Manager Carlos Abel - Area Operations Superintendent(Ruby Jo)
James Donnelly Water Treatment Super Ken Krieger Well Compliance Coordinator
Andrew Buhner Control Room Super Philip Christopher Control Room Supervisor
Andrew Austin Control Room Supervisor Russell Schroder Control Room Supervisor
Sonia Cogo Permit Authority Trevor Smith Permit Authority
Brian Boehm Permit Authority Bill Von Harten Permit Authority
Mitchell Peacock Permit Authority Rob Demaine Permit Authority
Rob Bailey Permit Authority David Horsford Permit Authority
Kirk Russell Permit Authority Shane OBrien Field HSSE Lead
Rob Shelton - General Manager Upstream - Steve Byatt - General Manager Gathering
North
Ken Larson Upstream Projects Director Paul Hannan Plant Supervisor
Reese Story Area Operations Superintendent Jason Andrews Area Operations Superintendent (Windibri)
Claire Pattison - HSSE Performance Res & Anthony Harland Pipeline Supervisor
Co-ord
Bryan Jenner Plant Supervisor Scott Taylor Gathering Supervisor
Tony Maiore Maintenance Supervisor Neville Hardwick - Production Supervisor CPS
Sarah Price Field HSSE Advisor Nathan Allan - Production Engineer
Blake Gillespie - First Delivery Supervisor Freeth Graham GTA Pipelines
Chad Pettitt AusSafe Senior consultant Kelly Johnstone AusSafe Senior consultant
Informed:
Enter name/position of those to receive the completed document
Responsible Person: Lynn OMalley Principal HSSE Advisor, Upstream Operations
Accountable Person: Rod McPherson HSSE Manager, Upstream Operations
Endorser: Dan McCoy General Manager Operations
QGC Operations and Projects Personnel
QGC Corporate HSSE
29 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
RACIE Terms
R Responsible: the person who actually produces the document
A Accountable: the person who has to answer for the success or failure of the quality and timeliness of
the document
C Consulted: those who must be consulted before the document is published
E Endorsed: the person who must approve the document before publication
Revision Record
30 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Term Meaning
Angle of repose The slope at which dumped or excavated material is naturally stable and does not
fall away
Backfill Material used for refilling excavations
Barricade An object such as jersey kerb or plant capable of providing effective protection
against traffic entering the work site. IMPORTANT: Barricade/Barriers <4.2m clear
of traffic at 60kmph, <3.0m clear of traffic at <60kmph and <6.8m clear of traffic at
80kmph require design verification and signoff by the traffic engineer (check with
local/state requirements)
Barrier A self-supporting structure or a self-supporting series of continuous solid barriers
erected or placed to restrict the entry to a workplace
Batter or slope The angle of an excavation in relation to the horizontal
Battering The development of a sloped wall to an excavation to a predetermined angle.
Benching The development of stepped sides to an excavation to lessen the overall slope of
the excavated walls to a predetermined angle
CAD Coordinator Person (engineer, senior surveyor etc) with the capability to access and use the
current services model or equivalent process/system. This person can be assigned
the responsibility to provide services information as identified in survey
documentation, services drawings, as built construction drawings and provide
overlay drawings such as service locations onto design drawings
Closed Sheeting A continuous frame with vertical or horizontal sheathing planks placed side by side
to form a continuous retaining wall supported by other members of a support
system used to secure the face of an excavation
Competent person A person who has acquired through training, qualification or experience the
knowledge and skills to carry out the task test or inspect equipment. Generally
'competency' is assessed by QGC or a third party.
Note: In relation to performing an inspection or other task for a control measure,
means a person who has acquired, through training, qualifications or experience the
knowledge and skills to do the task in a safe way, including knowledge of relevant
Australian Standards, Industry Standards, Codes of Practice and other legislation.
Confined space An enclosed or partially enclosed space that is not intended or designed primarily
for human occupancy, within which there is a risk of one or more of the following:
an oxygen concentration outside the safe oxygen range;
the potential to contain an airborne containment that may cause;
o impairment to senses
o loss of consciousness
o asphyxiation
o injury from fire or explosion
a stored free-flowing or a rising level of liquid potential that may cause
suffocation or drowning by engulfment.
31 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Term Meaning
Construction Zone A defined location that has been formally identified with clearly defined boundaries
in which the following activities may occur:
a Greenfield or Brownfield site with special cordoned off barriers and denoted
safe for the purpose of the work to be done;
excavation, including the excavation or filling of trenches, ditches, shafts, wells,
tunnels and pier holes, and the use of caissons and cofferdams;
building, including the construction (including the manufacturing of prefabricated
elements of a building at the place of work concerned), alteration, renovation,
repair, maintenance and demolition of all types of buildings; and
civil engineering, including the construction, structural alteration, repair,
maintenance and demolition of, for example, gas wells, pipelines, ponds,
compression plant, power stations, roads, bridges and tunnels, and works
related to the provision of services such as communications, drainage,
sewerage, water and energy supplies, etc.
Cover A steel plate or other suitable material capable of withstanding the loads that may
be imposed upon it and of sufficient weight or secured to prevent unauthorised
removal.
Dial before you dig A free referral service for information on underground pipes and cables anywhere is
(DBYD) Australia.
Disconnected service Applies to all services power/communications/gas/sewer-water/storm water, etc.)
A disconnected service is one which is rendered permanently out of service
These services are decommissioned, disconnected /cut off from the supply
source with the intention that they are redundant they are no longer part of
the service owners operational network.
Earthmoving Operator controlled mobile plant used to excavate, load, transport, compact or
machinery spread earth, overburden, rubble, spoil, aggregate or similar material, but does not
include a tractor or industrial lift truck
Excavation Work involving any penetration > 300 mm below the ground surface.
Exclusion Zone An area from which all persons are excluded during excavation work
Face An exposed sloping or vertical surface resulting from the excavation of material
Fence Continuous enclosure not less than 1800mm in height that prevents unauthorised
access to the work area and of such strength to remain erect in position during all
conditions
FOPS Acronym for falling object protection system A protective structure over an
operating cabin of a vehicle designed to prevent object falling from above from
entering the operators station-Often integrated with a ROPS cabin but may be
installed as a stand-alone system
Geo-technical An engineer, whose qualifications are acceptable for membership in the Institution
engineer of Engineers Australia and who has qualifications and experience in soil stability,
soil mechanics and excavations
Greenfield Zone A formally designated Zone that has been clearly identified, fully risk assessed, and
has been demonstrated to have limited operating infrastructure, live services or
above or below ground, prior to new work being undertaken.
Handrail A rail one meter in height (plus or minus 100mm) effectively supported, security and
of such rigidity and strength capable of providing support so as to prevent persons
falling
32 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Term Meaning
Isolated Service Applies to all services power/ communications/ gas/ sewer-water/ storm water etc.
An isolated service is one, which is rendered temporarily out of service. I.e.
electrical services power outage/water supply cut off stop valves closed/
sewer mains plugged etc.
Services are isolated for one of two purposes:
o To enable work to be carried out in close proximity to the service in safety
or to minimise risk of electrocution/explosion/fire/fluid leakage if the service
is inadvertently damaged during work activities; or
o To enable work on the service (cut tee into water main, install sewer
junction, CCTV camera inspection, connect power to switch gear etc) to be
undertaken safely and in such a manner that temporary disruption of supply
to consumers/public is controlled
Job Safety and A component of QGCs overall risk management process that occurs at the area of
Environment Analysis work immediately prior to commencement of the task under a PTW
(JSEA) A JSEA involves conducting a work party review of all relevant HSSE
documentation associated with the task and capturing any additional hazards not
already identified (e.g. in the, PTW, SOP or SWMS), assessing the risk/s and
deciding on appropriate controls to reduce the risks
Limits of approach A table, modified to suit local requirements which specifies the minimum distance
between the service and mechanical or hand excavation
Non destructive A process of digging holes with the use of air and water whilst the debris is
digging vacuumed and saved for back fill
Operator protective A roll-over protective structure (ROPS), falling object protective structure (FOPS),
device operator restraining device and seatbelt
Overburden Surface soil that must be displaced
Permit Holder A person deemed competent and approved by QGC to carry out the work specified
on a PTW and to whom a PTW can be issued by the Permit Issuer
Permit Issuer A person deemed competent and approved by QGC to define the control measures
to be implemented in establishing a safe work environment for the Work Party and
issue PTW and supporting documents
Positive identification Measures have been undertaken to determine that the service located is actually
the service it is believed to be:
Measures include pot holing - soft dig options including non destructive
excavation methods and scanning /detection techniques
Potholing The use of a high pressure water and vacuum system to safely locate buried
pipelines and cables
Powered mobile plant Plant that us provided with some form of self propulsion that is ordinarily under the
direct control of an operator
Prescribed Information about an underground service, necessary to safely undertake
information excavation/trenching work at or near the service, including:
(a) The location of the service
(b) The type of the service
(c) The depth of the service
(d) For an electrical servicewhether the service is live; and
(e) The restrictions to be followed in doing the work
Runners Any timbers, metal or sheet piling used to form the vertical members if an
excavation support
33 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
Term Meaning
Safe Slope The steepest slope at which an excavated face is stable against slips and slides,
having regard to the qualities of the material in the face, the height of the face, the
load above the face and the moisture conditions
Safe Work Method A work statement produced as part of the submission for a Permit to Work that:
Statement (SWMS) identifies the work activity to be undertaken and the proposed steps in the job;
states the safety hazards and or associated risks for each step;
describes the control measures that will be applied to the work activity and the
revised risk;
and includes a description of the equipment used in the work and the competencies
of the workers.
Scafftag Propriety trade mark commonly used to refer to a system of tagging scaffolds or
other equipment to visibly record inspections and status
Service authority The owner, controller or operator of an underground or overhead service-
For the purpose of this guideline an underground or overhead service includes
electrical, water, sewage and drainage, gas, telecommunications, petrochemicals
and hazardous substances
Must A mandatory term no deviation is permitted without written approval from the
Group Technical Authority.
Shoring The use of timber, steel or other structural material to provide effective and
adequate temporary support to maintain the stability of the walls of the excavation
Soft dig Is a non-mechanical means to expose / identify the location of underground
services by using wooden handled or other insulated implements, i.e. shovels,
mattocks etc.-Non destructive excavation includes methods such as Vacuum
techniques
Soldier Vertical upright timber or steel element used for supporting a trench wall
Strut or screw jack A timber or steel member usually horizontal in compression, resisting thrust or
pressure from the face or faces of an excavation. Screw jack struts are adjustable
Support Structure A shoring system to maintain the stability of the walls and roof of an excavation and
includes a trench shield
Tom Structural member used to hold soldiers against a trench wall or to press walers
apart in a close sheeted trench
Trench An excavation where the maximum depth is greater than the width-
Generally developed temporarily for the placement or repair of pipes and services
Trench Shield A structure with two vertical side plates permanently braced apart by cross frames
or struts designed to resist the pressure from the walls of a trench and capable of
being moved as a unit
Vacuum truck A truck mounted, heavy duty industrial vacuum loader designed to pneumatically
convey solids, liquids, sludge or slurry through suction lines typically 5-10 cm in
diameter
Waling A horizontal beam supporting vertical timbers, runners or sheeting
Water scouring An erosion process resulting from the action of the flow of water
Zone of influence The volume of soil around an excavation, measured from the bottom level of the
excavation, between the sides of the excavation and a line drawn at an angle from
the horizontal. Generally, the zone of influence extends some 30 degrees from the
horizontal for sands and 45 degrees for other material
34 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
35 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 May 2012
36 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 - May 2012
APPENDIX C CERTIFICATE
37 of 38
Upstream Operations
Excavation Procedure
QCOPS-BX00-HSS-PCE-000007
Revision 0 - May 2012
FEEDBACK FORM
This form should be used to notify comment or suggestions for improvement, relating to any aspect of the
document identified below. Please return the completed form by Email, to the Responsible identified in the
associated RACIE matrix
Issue No:
Issue Date:
38 of 38