ADES ENGINEERING PTE LTD

PROJECT: PROPOSED EXTENSION, ADDITIONS AND ALTERATION OF EXTG 7 - STOREY NURSING HOME TO BECOME
8-STOREY NURSING HOME WITH SUPERVISORY HEALTH CARE FACILITIES ON LOT 01402A PT 02390W PT MK21 AT
NO.70 BUANGKOK VIEW (HOUGANG PLANNING AREA)

Progress Claim No. 18 DATED: 23/01/2017

SCHEDULE OF VARIATION CLAIM

S/N Description Contract Work Done This Claim Remarks


$ % $

VO1 Supply and Diversion of Existing Fire Hydrant Main $9,528.00 100% $9,528.00 Fully Completed and
Pipe at 1st Storey G/L E-11/16 Commissioned.
(Our ref:ADES/BKH/20151023 dated 19th Jan 2016)
- DISCUSSED AND AGREED
VO2 Supply and Install Conventional RWDP System & 1)ZONE-1, ZONE-2 &
Planter Drain & Balcony Drain Pipe ZONE-3 U/G
(Our ref:ADES/BKH/20150923 Rev"02" dated 12th Mar connection to Drain
2016) done.
-DISCUSSED AND AGREED 2)ZONE- 3
INSTALLATION
1) 1st Storey $1,520.00 100% $1,520.00 COMPLETED UNTIL
ROOF
2) 2nd Storey $17,540.00 100% $17,540.00 3)Zone-1 up to 8th
3) 3rd Storey $3,820.00 100% $3,820.00 storey cast in pipes
done
4) 4th Storey $3,900.00 100% $3,900.00 4)Zone-2 UPTO 8TH
STOREY CAST PIPES
5) 5th Storey $3,900.00 100% $3,900.00 INSIDE COLUMN
6) 6th Storey $3,900.00 100% $3,900.00 COMPLETED.
7) 7th Storey $3,900.00 85% $3,315.00 PHASE-2 WORK WILL
8) 8th Storey $3,900.00 85% $3,315.00 CONTINUE.
9) Roof $4,860.00 85% $4,131.00

VO3 Supply and Install Additional Water Coolers at the New


and Existing Buildings
(ref:ADES/BKH/20151030"Rev02" dd 01.03.2016)

1) 2nd Storey $782.00 100% $782.00

2) 3rd Storey $410.00 100% $410.00 Additional water coller


3) 4th Storey $392.00 100% $392.00
installation work fully
4) 5th Storey $1,528.00 100% $1,528.00
completed.
5) 6th Storey $1,064.00 100% $1,064.00
6) 7th Storey $1,082.00 100% $1,082.00
7) 8th Storey $1,142.00 100% $1,142.00

VO4 Supply and Install Additional Floor Traps at the New


Isolation Rooms (ref:ADES/BKH/20151031"Rev04" dd
09.11.2016)

1) 5th Storey $1,718.00 100% $1,718.00


Floor traps installation
2) 6th Storey $730.00 100% $730.00
fully completed
3) 7th Storey $1,894.00 100% $1,894.00
4) 8th Storey $1,984.00 100% $1,984.00

TOTAL AMOUNT BEFORE GST = $69,494.00 $67,595.00