Professional Documents
Culture Documents
STATEMENT FOR
SURVEYING WORKS
1. DESCRIPTION OF WORK
1.1. Purpose
The purpose of this Method statement is to outline the strategy to be adopted on the Project: -
a. Define the specific task to be performed and ensure a safe system of work.
b. To set out the sequence of construction and work procedure.
c. Show the procedure to ensure work complies with the specification and drawings.
d. Ensure work is carried out without any adverse impact on environment.
The main purpose of this method statement is to describe the main activities relating to the
timely and proper setting out of the works in relation to the original survey points, lines and levels to
ensure work undertaken with reference to a fixed datum and to appropriate dimensions. Based
on the correctness of this information the works will proceed.
RMSE: Root Mean Square Error is the root of the sum of squared residuals divided
by the number of observations minus the degree of freedom.
Differential GPS: A positioning technique that uses two receivers, one (the Differential station)
at an unknown location, and the other (the reference station) at a known,
fixed location. The reference receiver computes corrections based on the
differences between its actual observed ranges to the satellites being
tracked. The co-ordinates of the unknown location can be computed with
great precision by applying these corrections to the satellite data received at
the differential station.
This is continuous process and will be completed during the closing out stage of the project.
1.4.1. Benchmarks
The location of the temporary benchmarks shall be discussed with the Engineer before they are
established. All Bench marks location will be coordinated with Airside works and other contractors
to avoid clashes with locations of utilities or services.
A 2Omm Diameter steel rod of 3Ocm in length shall be casted into the concrete & it should be
projected min. 1cm above the surface.
The concrete surface shall be clearly engraved with the reference number of the benchmark.
See Attachment C - Temporary Survey Control Points
The Contractor shall check these benchmarks at monthly intervals or necessary and should
be notified to the Engineer for their correctness or discrepancies.
The Contractor shall maintain and supply the records related to all reference pegs and
benchmarks to the Engineer in approved format.
The contractor and the ENGINEER will carry out joint survey to verify and check the
benchmarks established by contactor.
Prior to commencement of the works, all survey equipment will be calibrated checked and
certified in line with the manufacturer's recommendations.
The Total Station will carry a valid calibration certificate by the manufacturer and will be checked
on site every 6 months against known observations.
Calibration of GPS Survey equipment shall be according to coordinate system.
These test measurements will be carried out by the surveyor on site, to make sure that the
instrument is operating in accordance with the manufacturer's specifications.
The instrument will be returned to the manufacturer for re-calibration before the end of the
calibration validity or in case the accuracy of the observations are doubted.
Total stations will be checked on the optical plummet and horizontal and vertical circles.
The Leveling Instrument will carry a valid calibration certificate by the manufacturer and will be
checked on site every 6 months against standard techniques.
These test measurements will be carried out by the surveyor on site, to make sure that the
instrument is operating in accordance with the manufacturer's specifications.
Regular maintenance of the instruments will be undertaken as the works progress to ensure
instrument accuracy tolerances are maintained.
A calibration log shall be kept for all equipment and all checks recorded and filed.
The Contractor is responsible for all the setting-out of line and the levels of the Works
and shall employ adequate qualified staff to carry this out.
Where survey markers have been established by the Engineer the Contractor shall check the
accuracy of their position and level. In case of any discrepancies, it shall be notified to the Engineer
immediately.
The Contractor shall survey the alignment and shall mark out the center line with pegs. The
alignment shall be referenced by pegs at specified intervals.
These offset pegs shall be painted by a conspicuous color and shall have clearly written chainage.
Survey works will be carried out by qualified surveyors at locations identified by the
construction team.
Setting out of stations by adopting the traverse & triangulation method.
A minimum of two control points nearest to intended setting out location will be utilized. The
required station points will then be surveyed.
Maximum distances of station points will be 200m. The setting out is then closed by the same
control points and/or other two control points.
The errors in angles and distances will be adjusted using Traverse adjustment. The setting out
of the works (for example roads) can be done for control points and the newly established
stations.
Total stations will be utilized; valid Calibration Certificates of the instruments shall be available.
Prior to start of works the instruments will be checked by using triangulation method and errors
in the results are recorded indicating the instrument is ready for setting out.
Leveling will be done by using level differential machines. The certification of the instruments
will be available with the survey development.
Leveling will proceed to a temporary benchmark and the loop back to the starting bench mark.
Intermediate turning points shall be spaced not more than 100m.The data shall be recorded and
the error of above shall be determined. The maximum permissible error in mm shall be equal to
eight times the square root of the distance of level run in kilometer. One record copy will be kept
with the surveyor in site and ordinal with survey department.
Daily checking of the instrument will be done by recording measurements from two equal
distant points of approximately 100m to ensure that level instrument is appropriate. The
instruments will be stored in surveying department office: every surveyor will be responsible
for his assigned equipment. The instruments will be transported to the work place within the
casing covers.
The machine will always be kept free to rotate within their casing to avoid any change.
Temporary bench marks will be located mainly outside the roadways at approximately 200m
spacing longitudinally to the road at a maximum of 200m offset from the road. These locations
will be decided according to work in hand and work of other contractor.
They will be marked by steel pegs driven flush with the ground and/or concreted marked and
identified by warning tapes. Care will be taken to ensure TBM are clear of work areas and
protected from vehicle movements using elevated pins and warning tapes surrounding the
point.
Coordinates and levels of the benchmarks will be monitored on a monthly basis to check for
accuracy.
Survey team will consist of Senior Surveyor and teams of surveyors. Senior Surveyor will be
the overall responsible person and he will coordinate with the Construction Manager on site.
Survey records will be produced as hard copy on CD/diskettes and survey books.
Before commencement of the works, existing site condition will be surveyed in sections. This
will be completed gradually as the site area hand over proceeds.
The information will be compiled and submitted in order to verify the site conditions are in line
with the Engineers information presented on IFC drawings.
Cross sectional level survey shall be conducted at spot heights in a say 20m grid pattern over
the limit of survey. In addition, spot height shall be taken at high & low points, any changes in
grade, sufficient in order to compile a DTM, which is representative of original ground truth.
Final location and level information of the different element (as mentioned in specification) shall
be surveyed and recorded and final as-built record survey shall be submitted at the completion
of each section of work. As built data shall be provided to the Engineering team for updating
the as built drawings.
1.5. REPORTING
Daily records will be kept of survey operations. Composed logs will be generated and will minimally
include:
Date, time, location and vessel
Survey equipment status
Survey personnel
Breakdown of activities
survey area and sailed lines
Calibrations
Safety and environmental data
Survey results and experiences will be discussed in internal meetings with the Construction
Manager, to be followed by further activity planning.
Extensive reporting on survey results will follow all formal and major inspection surveys. The
reports will contain the information on how and under what conditions the data was obtained.
2. RESOURCES
Senior Surveyor
Site Surveyors
Chain men
HSE Officers
Skilled Labors
Drivers
All Subcontractor Surveying shall create and submit for approval a Method Statement for
Surveying. Their submittal shall follow the guidelines set out in this document
Project Director: Overall responsible for the project operations and activities in a manner
to ensure attaining the project objectives.
Construction Manager/Senior Engineer: Responsible for Management and Organization of the
execution of the construction works.
Senior Surveyor: The Surveyor in charge of the survey works will ensure that all survey
operations will be carried out according to the specifications. He is responsible for the
necessary calibrations, verifications and the associated processing (editing, plotting, volumes
etc.). The Surveyor's main activities are to survey records and reclamation process for quality
and quantity purposes, including compiling the 'as-built documentation'.
Senior Site Surveyor: Responsible to set out and collect all data from work site with reference to
permanent bench mark in presence of Engineers representative. To Ensure Survey works done
in relation to all construction activities related to the work as per IFC drawings.
Site Surveyor: Responsible for survey for all construction activities as per IFC drawings,
approved method statement and HSE plan.
HSE Manager: Responsible to ensure this activity is performed in an appropriate manner
fulfilling the project health, safety and environmental requirement.
Quality Manager: Responsible to ensure this activity is performed according to approved ITP,
CQP. All inspections, tests are carried out on site in order to secure the required Quality of work.
Total Station
Automatic level
Global Positioning system (Setting out equipment, main station and rovers)
Steel Measuring tapes and spirit levels
Surveying grade rods
Surveyor umbrellas (to be provided as per requirement)
Field Book
2.5. MATERIAL
3. RISK ASSESSMENT
Approved logistic and route plan shall be provided to Surveyor use the access on site
Before starting the work, surveyor should confirm access and egress are free from obstruction.
Not applicable
Surveyor will be provided ear plugs as a precautionary measure to be used when they have to
work near noisy area.
Waste materials (timber, cabling, mortar and other materials) shall have clearly labeled
containers for disposal. The container shall be emptied via the correct and approved waste
route.
All waste packaging resulting from the fit out of the contractor's site offices is to be disposed of
quickly and via the correct waste route.
All environment issues shall be reported to the engineer and the safety department, for
further investigation.
All chemicals hazardous to health and the environment such as paint and fuel shall have MSDS
and COSHH assessments prior to use. The COSHH assessment is to be followed at all times
and any PPE or other precautions are to be used.
Tool box talks shall be given regularly to reiterate the environmental hazards of an existing
work activity or to highlight the risks of a new activity.
All briefing should be given to the workers in a manner and language so the information is fully
understood.
The work area shall be maintained in clean, tidy and safe on daily basis.
Welfare in the form of toilets, shaded rest areas and drinking water shall be provided at location
of the works.
All Subcontractor Surveying shall create and submit for approval a Method Statement and Risk
Assessment for Surveying.
Emergency contact numbers will be displayed clearly and will be briefed in the pre job brief and
tool talks.
First box aid facilities and First aider will be available during working hours. Ambulance will be
available during working hours.
Site security Permit for access should be obtained for all manpower and equipment.
4.2. SECURITY A R R A N G E M E N T S
Security team will be responsible to curb unauthorized entries of vehicle and personnel.
All the records for entry and exit of the material and personnel will be maintained by this team.
Where special equipment is to be used staff will be trained and additional PPE will be provided
according to risk assessed.
Access plan should be submitted and approved prior to use for transportation.
All necessary permit and NOC"s should be obtained prior to commencement of work.
These accesses should be facilitated with all required sign boards and barricades.
This access should be maintained for smooth flow of traffic and dust control during the work.
7. COMMUNICATION
It is the intention of the Contractor to hold Method Statement Workshops on approved method
statements for the project before commencement of works. The purpose of these workshops is to
receive input, from all parties involved in specific sections of the works and to confirm their
understanding of the proposed methods.
Construction Manager
Survey Team
Record of attendance shall be completed and filed for all workshops / toolbox talks
Work execution inspection and test shall be conducted, monitored, witnessed and recorded
according to inspection and test plan.
The method and commencement will be briefed at the weekly coordination meeting prior to starting
the work to ensure other contractors are aware.
8. QUALITY
8.1. MONITORING
Inspection Request to be raised for activities related survey works, as per ITP
These Inspection requests to be supported with all check list provided in ITP.
Inspection Test Plan for this activity shall be submitted for approval. See Attachment B
Contractor shall prepare a method statement, ITP and checklist for each activity.
9. APPENDICES