OVERALL CONSOLIDATED KCT COMMENTS ISSUED FOR TRANSFORMER ON PHASE 11- 488D PROJECT

RAH3 SUBSTATION - KCT COMMENTS FOR TRANSFROMER

SR. NO. DESCRIPTION

1 Transformer Marshalling Kiosk internal component details name plate to be provided inside the panel engraved in Stainless Steel.

2 Touch Up paint to be provided in a neat manner wherever needed and should match with the existing paint.

3 Danger sign image to be provided in the door of the transformer climbing ladder.

4 Non return valve name plate to be removed which is not applicable to this transformer.

5 Missing permanent pad locks to be provided before PART-B NOSP.

6 Lot of oil seepage marks found in the top of the transformer tank to be cleaned properly and required touchup paint to be done.

7 Cable Box PRD,Main Tank PRD,OLTC PRD and OLTC oil level indicator rain guard protection covers to be provided.

8 Radiator valves for opening side knob should be painted with Green and close position with red paint.

9 Air bubble found inside the OLTC indicator in the top of the tank to be rectified.

10 Few gaskets came outside and damaged due to overtight of bolts to be rectified.

11 11KV cable box found all bolts not tightened properly to be rectified.

12 Transformer many areas found rust to be cleaned properly and if required touchup paint to be provided.

13 66KV Cable box structure foundation washer was not proper required size to be provided.
Transformer Main earthing supporting bolt missing to be rectified.
14

15 HV Side cable Box Protection cover missing to be provided.

16 AB 240 name plate to be corrected as per the approved drawing.

17 OLTC Rubber bag air to be filled.

18 OLTC box internal door opening key to be provided and to be placed inside the panel with proper arrangement.

19 OLTC - SWITCH OFF & ON CONTROL MCB (F2) BEFORE RESETTING Q1 MCB WHEN TRIPPED Label engraved in trafolite to be provided.

20 OLTC Q1,F2,F1,F3 & K9 labels to be provided in SS.

21 OLTC - Guard fault protection for socket MCB name plate to be provided

22 NER CFL lamp to be provided.


23 NER to be cleaned and gaskets in the door to be sealed properly to avoid dust entering the panel.

24 40 MVA Transformer T1 - explosion vent bolt damaged to be rectified.

25 Cable Trench floor opening to be closed properly.

RAH SUPER SUBSTATION - KCT COMMENTS FOR TRANSFROMER


In OLTC panel, SS name plates to be provided for Tap changer Raise/Lower, Emergency push button & (L/R/O)-Local, Off, Remote
26
Radiator Fan identification numbers shall be provided for individual Fans (with colour markings).
27
OLTC control cable tags to be provided.
28
OLTC name plates to be riveted
29
In OLTC, in the above MCBs reference details to be provided by yellow sticker
30
Oil pump valve-1,2,3,4 identification name plates to be riveted properly
31
In TCC panel Lamp is not working to be replaced
32
Main Tank Breather name plate found missing to be provided
33
H.V incomer cable box breather found loose to be tightened properly
34
In the above flange of H.V and L.V cable box 3 phase identification reference to be provided by colour markings.
35
Standing platform to be provided for M.K Box operation
36
H.V Neutral cable box rain guard protection shall be provided for Pressure Relief
37
Main Tank Oil Level gauge and Prismatic Level gauge is not visible to see from ground level
38
In Tx-1,maintenance Valve Oil pump-1&3 position found reversed to be corrected same as Tx-2
39
L.V control cables which are laid over the Tx. main tank should not touch with main tank
40
On Tap Changer during tap operation Tap changer progress in red colour & final tap position in white colour was given the same to be
41 labelled as Text
All Radiator valve open/close name plates to be provided
42
In OLTC panel, SS name plates to be provided for Tap changer Raise/Lower, Emergency push button & (L/R/O)-Local, Off, Remote
43
Radiator Fan identification numbers shall be provided for individual Fans (with colour markings)
44
OLTC control cable tags to be provided
45
In OLTC, in the above MCBs reference details to be provided by Trifoliate yellow sticker
46
In the above flange of H.V and L.V cable box 3 phase identification reference to be provided by colour markings
47
L.V control cables which are laid over the Tx. main tank should not touch with body of main tank
48
On Tap Changer during tap operation Tap changer progress in red colour & final tap position in white colour was given the same to be
49 labelled as Text
All Radiator valve open/close name plates to be provided
50
Stand by Fan should be grouped with Group-2
51
In TCC panel, Manual/Auto switches name plates to be provided for 1-Manual & 2-Auto
52
In TX-2,TCC door stopper to be adjusted tightly
53
OLTC Timer final settings for relays K701,K702,K601,K602 & TCC F41,F42,F51,T10,T20 to be finalised
54
In NER, name plates to be provided for Hygrostat, Socket.
55
In NER control wiring cable tags should be replaced by SS tags
56
In NER-2 Lamp is not working to be replaced
57

RAH 1 SUBSTATION - KCT COMMENTS FOR TRANSFROMER

58 Silica gel breather to be replaced with good one.

59 Due to more oil in the silica gel breather leaking .It should be in the mentioned level.

60 415V LV Cable Box connected bolts were in different size to be rectified.

61 415V LV Cable Box cable seperater missing. To be provided.

62 Civil Slab provided for cable trench not in Proper position.

63 All Temperory locks provided to be replaced with permanent locks before Part-B NOSP.

64 LV & HV cable entry fire sealant to be provided.

65 Name plate to be provided as TRANSFORMER CONTROL CUBICLE in the door.

66 OTI & WTI setting to be provided in name plate engraved in SS in the door of the transformer control cubicle.

67 PRD cover hinges to be replaced with good one.

68 All bolt nuts tightness to be re- checked.

69 Dummy holes to be sealed properly.


70 11KV All cable & bus bar shutters alignment to be rechecked for outgoing feeders.