Professional Documents
Culture Documents
Darchula, Nepal
A
Pre-feasibility Study Report On
Naugarh Gad Small Hydroelectric Project
Darchula, Nepal
Supervisor Prepared By
Prof Dr Hari Prasad Pandit Sailuj Shakya
Department of Civil Engineering Sanchita Neupane
IOE Pulchowk Campus Sonia Barakoti
Sujata Subedi
Sulav Dhakal
Swastik Bhandari
CERTIFICATE
This is to certify that the project work Pre-feasibility Study of Naugarh Gad Small
Hydroelectric Project has been examined and it has been declared successful for the
fulfillment of the academic requirement towards the completion of the Bachelor’s degree in
Civil Engineering.
Prof Dr Hari Prasad Pandit Prof Dr Prem Chandra Jha Er Suraj Lamichhane
Date: 2070/6/17
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
Team Composition
Supervisor:
Prof Dr Hari Prasad Pandit
Institute of Engineering, Pulchowk Campus
Department of Civil Engineering
Team Members:
Sailuj Shakya (2066/BCE/103)
Sanchita Neupane (2066/BCE/105)
Sonia Barakoti (2066/BCE/122)
Sujata Subedi (2066/BCE/130)
Sulav Dhakal (2066/BCE/131)
Swastik Bhandari (2066/BCE/139)
I
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
Acknowledgements
First and foremost, we would like to thank our supervisor Prof. Dr.Hari Prasad Pandit for his
valuable guidance and advice without which this work would not have been accomplished.
We express our gratitude to South Asia Engineering Pvt. Ltd. for the huge co-operation
extended to us during our study period. We are sincerely thankful to Mr. Guru Neupane for
constantly inspiring and guiding us. We would like to acknowledge Er. Mahendra Neupane,
Project Manager, South Asia Engineering Pvt. Ltd. and Mr. Sanjeev Neupane, Managing
director, South Asia Engineering Pvt. Ltd. for their tremendous support and help. We would also
like to thank Er. Sudesh Dahal, Ridi Hydropower, and Er. Nischal Rajbhandari, South Asia
Engineering Pvt. Ltd. and Er. Bhupal Adhikari for providing us with related data and
information.
We would like to acknowledge Prof. Dr. Prem Chandra Jha for his constant support and
conceptual guidance. We are also thankful to Er. Suraj Lamichhanne for his support without
which our work would not have been completed on time. We express our sincere gratitude to
Prof. Dr. Durga Prasad Sangraula for giving us his precious time to show demonstrations at
hydro-lab and providing us with educational materials. We would like to add our gratitude to
our friends who directly and indirectly helped us in the successful completion of the project.
II
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
ABSTRACT
This work entitled “Pre-feasibility Study of Naugarh Gad SHEP” is done as the final year
project according to the syllabus of final semester of Bachelor’s Degree of Civil Engineering
under IOE, TU. The objective of the final year project is to make the students familiar with the
real civil engineering practice and boost our confidence to tackle the real problems encountered
in civil engineering professional field.
At first, a 15 day tour to the project site was organized for topographical surveying. This trip
helped us visualize real engineering problems and gave us some experience to work in the field.
This particular work is the outcome of the academic workout of civil components in details.
Mostly we have tried to work out the design of dam, intake, spillway, stilling basin, gravel trap,
water conveyance system, penstock optimization, surge tank and powerhouse. We have tried to
incorporate hydrological study in detail whereas sedimentology and geological study in brief.
This report has been prepared for academic purpose and is bound to have many shortcomings in
it. However, our team has put our best effort to this project work. Healthy comments,
suggestions, and corrections are highly appreciated.
III
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
1.0 General
Location
- District : Darchula
- Zone : Mahakali
Q40% : 8 m3/s
Diversion Weir
- Length : 26 m
IV
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
Intake
Under sluice
-Size (B x H) : 4m x 4m
Length : 49.409 m
V
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
Material : Steel
Length : 4095.129 m
Thickness : 15 mm
Slope (Longitudinal) : 1 in 67
Length : 75 m
Slope (longitudinal) : 1 in 2
Type : Open
Thickness : 16mm
Length : 691.117 m
9.0 Powerhouse
Type : Surface
VI
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
10.0 Turbine
Rated efficiency : 94 %
Length : 96.886 m
12.0 Gates
- Number : 1 No.
- Hoisting : Electrical
Intake Gate
- Number : 4 Nos
VII
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
- Hoisting : Electrical
- Number : 2 Nos.
- Hoisting : Manual
- Number : 2 Nos.
- Hoisting : Manual
Coarse Trashtrack
- Type : Fixed
- Number : 1 sets
- Size of bars : 20 mm
VIII
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
IX
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
Table of Contents
Acknowledgements II
Abstract III
Salient Features IV
Table of Contents X
List of drawings XV
CHAPTER 1
Introduction
1.1 Background 1
CHAPTER 2
2.2 Accessibility 6
2.6 Tourism 7
2.7 Climate 8
CHAPTER 3
x
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
CHAPTER 4
Hydrological Study
4.1 General 17
4.1.1 Introduction 17
4.1.2 Objectives 17
CHAPTER 5
Sedimentation Studies
xi
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
CHAPTER 6
6.14 Penstock 62
xii
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
6.16.1 Tubine 66
6.17 Tailrace 71
CHAPTER 7
7.2 Methodology 76
CHAPTER 8
Cost Estimate
8.1 Assumption 82
8.2 Methodology 82
8.3 Recommendation 83
xiii
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
CHAPTER 9
9.1 Conclusion 84
9.2 Recommendation 84
References
Appendix
A. Alternatives Selection
B. Hydrological Calculations
C. Pipeline Optimization
D. Penstock Optimization
E. Bifurcation Design
F. Anchor block Design
G. Detail Cost Estimate
H. Headloss Calculations
I. Energy Calculations
J. Rating Curves
xiv
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
List of Drawings
Hydroelectric power
xv
Pre- Feasibility Study Report on Naugarh Gad SHEP 2070
Surge Tank
xvi
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
CHAPTER 1
INTRODUCTION
1.1 Background
Nepal is a tiny land locked sovereign independent country located in South Asia between India
& China. Nepal occupies a total area of 1, 47, 181 sq.km with a population of about 27 million.
Although it occupies a small area of land, it has unique topographical variations. The landscape
of this tiny nation varies from 60m above the mean sea level to the highest point of the earth, Mt.
Everest which is 8848 m above the mean sea level. Geographically the country is divided into
three main geographical regions The Himalayas, the Hills and the Terai.
The Himalayan region: The Himalayan region is the northernmost region of the country. Its
altitude ranges between 4,877 m. to 8,848 m. and the width north-south is 25-50 k. m. It extends
from east to west and accounts for 15% of the total land of Nepal. The northern 16 districts of
Nepal are mostly within this region. The snowline lies between 4000-5000 m.
The hilly region: In between the Himalayas and Terai are the mid-hills of Nepal, mainly made of
the Mahabharat, Siwalik and partly of Chure ranges, which contains 68% of the Nepalese land.
The altitude ranges between 600m to 4877 m. Altogether, 39 of the 75 administrative districts
are within this region.
Terai (The plain land): Terai covers 17% of the area of Nepal. It provides excellent farming land.
Average elevation is 60 to 300 meter above sea-level.
Besides being rich in geographical diversity, water resource is Nepal’s one of the major natural
heritages. Nepal has a mean annual precipitation of 1500mm, comprises of more than 6000
rivers and rivulets and hundreds of lakes and streams.
In Nepal, monsoon rains and snowmelt contribute to river flow. The Hydrology of Nepalese
Rivers is dominated by the Monsoon winds originating at the Bay of Bengal and entering Nepal
around the end of May and lasting until the end of September. About 75 to 80 percent of total
annual rainfall occurs during these four monsoon months. The annual precipitation is 2200-2500
1
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
mm in the Terai and Siwaliks range, 1500-2500 mm in the Mahabharata range, and less than
1000 mm in the Himalayan range. The months between October and May are mainly dry, though
a winter monsoon which travels eastward from the Mediterranean Sea occasionally brings rain.
Depending on the altitude some catchments are influenced by monsoon and some by snow melt.
On catchments that are entirely below 3000 m, there is no significant contribution from
snowmelt. On catchments that are above 5000 m, snow melting is major source for stream flow.
Catchments lying between 3000 and 5000 m are influenced by both monsoon and snowmelt.
The three main river systems of the country-the Koshi, Narayani and Karnali river systems
originate from glaciers and snow-fed lakes. These rivers run from north to south and ultimately
become major tributaries of the Ganges River in northern India.
Of the total energy consumption in Nepal, around 83.7% (FY 2010/2011) is from the traditional
sources among which fuel wood is the main source of energy. Petroleum provides 10.4 % of the
total energy whereas mere 2.3 % is from electricity. 92% of electricity is from hydropower
which is nearly 2 percent total energy consumption in Nepal. Another notable fact is that only
2
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
40% of the entire population of the country has an access to electricity. Higher dependency of
the country in the fuel wood is inviting deforestation, soil erosion and flood.
In Nepal, so far we have not been able to cultivate wind-power successfully. Few installed
projects did not work properly. Similarly, solar pico-plants that have been successfully marketed
by enthusiastic individuals and firms generate insignificant amount of electricity for the country.
Moreover, we lack resources for thermal and nuclear plants. In such a scenario, with more than
6000 rivers flowing down the steep topography of the country’s terrain, hydropower has the
highest potential in solving our everlasting energy crisis.
Hydropower is the power derived from the energy of falling water. The real beauty of
hydropower is that it is a renewable source of energy and produces least amount of green-house
gases compared to other sources of energy like fuel wood or petroleum products. Thermal
powers require coal as fuel whereas the fuel for hydro-power is water. However, the elegance of
water as the fuel is that it is neither consumed nor converted into something else. Water passes
3
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
through the turbines without decreasing its utility. It can be subsequently used for water supply
and irrigation.
Nepal has the financial-technical potential to generate 42000MW of electricity. Even after 100
years of the first hydropower plant-Pharping Hydroelectric power plant (500KW, 1911 A.D.), we
have been able to generate only 705.69 MW (FY 2011/2012) of electricity. By now we should
have been able to produce enough hydroelectricity to earn revenues to get rid of country’s
poverty. Nevertheless, the challenges in the field of hydropower are immense for a poor country
like Nepal. The investment required for the development of a Hydropower project is quite high
because of lack of road access and adverse socio-political condition. Obstacles are posed by
heavy sediments in river and foreign dependability in hydropower construction technology.
4
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
CHAPTER 2
The Naugarh Gad Small Hydroelectric Project is located in Dethala VDC of Darchula district in
the Far-Western Development Region of Nepal on the Naugarh Gad River within the Mahakali
River basin. Geographically the site is located between latitude 29 o 41’ 15” to 29o 43’ 08” North
and longitude 80o 36’ 15” to 80o 36’ 38” East.
Physiographically the project area including its whole catchment area belongs to Middle
Mountains. The drainage area of Naugarh Gad lies between the elevations of 800m to 4000m.
Seasonal snow fall occurs in winter season in the upper part of the catchment. The basin is
devoid of glaciers.
Turkmenistan
Afghanistan
China
Iran
Pakistan
Nepal
Bhutan
Bangladesh
India
Oman
Myanmar
Laos
Thailand
Cambodia
Sri Lanka
Malaysia
5
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
2.2 Accessibility:
The district is accessible both with air and road transport facilities. This district has an airport at
Gokuleshwor. The Naugarh Gad SHEP is accessible by road from about 16 km from
Gokuleshwor on Mahakali Highway on Gokuleshwor-Dhuligada feeder road.
6
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
About 58.4 percent population falls under below the poverty line. Population composition is
made by different caste such as Chhetri 63.55%, Brahmin 17.15%, Thakuri 4.01%, Dalit and
others contribute 15.39 percent. Hindu followers are high in numbers. Hindu, Buddhists as well
as others do regard nature as a gift of God and they worship nature on their own way.
The major caste groups of Darchula District are Brahmin, Chhetries, Dalit, Thakuri, Lohar,
Kaine, Newar, Byansi, Bandhe, Sanyasi etc. Among them 85.19% HHs are
Brahmin/Chheties/Thakuri, 10% Dalits, 0.12% Sauka and others are occupational caste groups.
Sauka are indigenous inhabitant’s caste group. The indigenous caste groups are dominated by
migrants from other villages. The Dalits (7.35%) and Thakuri (7.43%) shares equal proportion
and occupy the second largest group in the total population. Indigenous groups Byansi represent
1.32%, Lohar 1.38% and other minorities’ correspondent to 1.48 percent. Dalits are also defined
as the Special Target Groups (STGs).
Darchula is one of the least developed districts of the country. The major socioeconomic
indicator of Darchula district is still very poor. Life expectancy of the people was about 52 in
1996. About 89.90% of the total population depends upon agriculture. Subsistence agriculture,
lack of basic infrastructure, difficult geophysical condition, traditional agricultural practice, low
literacy rate and population growth are the root causes for deep rooted poverty.
2.6 Tourism:
Api Nampa Conservation Area is a famous gateway of Kailash Mansarobar holly region located
in Tibet. Many pilgrims pass through this Conservation Area to get Kailash Pravat. Not only
Nepalese but also foreigners visit Api Nampa Conservation Area to acquire spiritual satisfaction.
Panoramic view of Himalayas created by several peaks like Nampa, Jethi Bahurani etc. attract
tourists.
7
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
2.7 Climate
The climate of the area is generally characterized by high rainfall and humidity. The climatic
condition varies along with the elevation gradient. Climate of the Darchula District varies widely
from subtropical to alpine. In the north, most of the parts remain under snow having alpine
climate. In the southern part and valleys the climate is subtropical. Mid- hills has temperate type.
The average maximum temperature is 18.6°C and the minimum temperature is 7.7°C and most
precipitation falls between May and September. About eighty percent of the total annual rainfall
occurs during monsoon period (June to September). All areas experience very high rainfall
intensities, ranging between estimates of 125–350 mm for a 24 hour period. A cold, generally
dry climate exists in the high alpine valleys just north of the southern arm of the Himalaya that
cuts across the bottom of Darchula.
1. Licensing Requirements
Hydropower Policy, 1992 as well as the electricity Act, 1992 do not allow survey, generation,
transmission or distribution of electricity to be carried out in projects without obtaining a license,
if the capacity of the project is more than 100 kilowatts.
2. Environmental Aspects
In accordance with the Environmental Protection Regulation, 1997, a feasibility study of a
hydropower project with a capacity more than 1MW, involving a transmission line above 66kV
must be supplemented with an Initial Environmental Examination (IEE) study.
The environmental provisions were also specified in water and electricity related policies, Acts
and regulations. They are depicted as follows:
9
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
CHAPTER 3
This section summarizes the field investigation which were carried out; the field measurements
which were made and the data which were collected in connection with the following aspects of
the feasibility:
Surveying and topographic Mapping
Geological and Geotechnical investigation
Hydrological investigation
Sedimentation study
The senior surveyor and his group carried out the detailed topographical survey of the selected
schemes. All the data necessary to determine the locations, coordinates and levels were obtained
by direct measurement in the field. To achieve the required accuracy and standards Sokkia 610k
Total Station with least count of 5” were used.
10
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Close traverse survey was carried out to establish required ground control points at
various locations in the project area.
All the major ground control points were monument with marked on permanent boulders.
Topographical maps of headworks, desander, forebay, penstock and powerhouse sites
were prepared in appropriate scales.
Different cross-sections and river profiles were taken at headworks and powerhouse area.
3.2.3 Methodology
The methodology used for the entire survey works was developed as per the scope of works,
which includes desk study, reconnaissance survey, monumentation of control points, control
traversing, horizontal and vertical control, topographic survey, preparation of plan and profiles
and mapping of the project area.
11
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Altogether 28 traverse points were established in the main-traverse loop, 5.0 km in length.
Different offset points were established by carrying out the traverse survey from two main
control points whenever necessary. The list of main traverse points and their coordinate data are
given in the following table:
12
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
13
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
While surveying a traverse line, all angles and distances were measured by applying the force
centering method. Distance measurement was performed using Sokkia 610K Total Station with
standard reflecting prism with an accuracy of 5mm ± 5ppm. Both back sighting and fore sighting
of direct distance were measured.
14
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Similarly, some field data were evaluated and horizontal distance and elevations were calculated
reciprocally. All the coordinates and elevations of each station and survey points were then
computed. Finally, the topographic map was prepared in Civil3D 2012 format
The sediment concentrations are essential to the design of the desanding basin. However; there is
no data available for the Naugarh Gad. The sediment data in Pancheshwor High Dam
Multipurpose Project in the Mahakali River can be employed for the sediment estimation. Two
other empirical methods can also be employed to estimate the sediment load transported by the
Naugarh Gad - (a) Himalayan Sediment Yield Technique, and (b) Regional Method (Sharma &
Kansakar, 1992).
The survey was carried out to find the potential availability of the construction materials, both in
quantity and quality, in the project area. As the project requires a huge amount of construction
materials- coarse aggregates, sand and boulders, some borrow areas have been identified.
15
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Coarse Aggregate
Coarse aggregate is the major constituent of concrete and also used as filter material behind the
retaining structures. It is obtained naturally due to disintegration of rocks and produced
artificially by crushing of rocks. For construction of the project, the coarse aggregate will be
produced either by erection of crusher plant at site or screening the river bed materials.
Sand
Sand is mostly used in concrete and rubble masonry works. The screening plant will be set up at
an appropriate place to produce sand using river materials. There are sufficient quantities of river
bed materials required to produce/collect construction materials for the project.
Impervious Materials
The impervious materials are generally used to retain water. During construction of headwork
structures, these materials are used to divert the river flow by constructing cofferdam. The
impervious materials are found in excess at the site.
Nepal Electricity Authority (NEA) is constructing Chameliya Hydroelectric Project (30 MW) in
Balanch of Darchula and is also constructing 131 km long 132 kV transmission line from Attaria
to Balanch to evacuate the power. The power generated from Naugarh Gad Small Hydroelectric
Project shall be connected to the under construction 132 kV sub-station at Balanch through 7 km
long 33 kV transmission line from the proposed powerhouse site at Dethala village. The
transmission line route passes along the Gokuleshwore-Balanch road.
16
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
CHAPTER 4
HYDROLOGICAL STUDY
4.1 General
4.1.1 Introduction
The hydrological characteristics of a river play vital role in the planning, design and successful
operation of a hydropower project. The hydrology of a river influences the nature and size of
hydropower projects, the design of their components and the ability of these components to
fulfill their operational needs with Naugarh gad small hydropower project is a run-of-river
scheme located in Darchula district of Nepal. The hydrological study at proposed intake is
carried out based on regional stream flows nearby Naugarh gad.
4.1.2 Objectives
The principal objective of the present inception study is to review all the past studies, update
them using additional data wherever possible, use both stochastic and deterministic approaches
as far as data permit and recommend the hydrologic design parameters such as low flows and
mean monthly flows for energy calculations and capacity optimizations.
17
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Following relevant past studies, reports and literatures on regional hydrology have been collected
and reviewed for the study and finalization of key hydrological parameters of the project.
The Hydrology of Nepalese Rivers is dominated by the Monsoon winds originating at the Bay of
Bengal and entering Nepal around end of May and lasting until the end of September. About 75
to 80 percent of total annual rainfall occurs during these four monsoon months. In Nepal, the
intensity and pattern of monsoon is governed by the topography of the Himalayas. It usually
moves to the north and later on to the west, causing maximum precipitation in the southern Terai
belt, and diminishing gradually while moving towards the north. The annual precipitation is
2200-2500 mm in the Terai and Siwaliks range, 1500-2500 mm in the Mahabharata range, and
less than 1000 mm in the Himalayan range. The monsoon occurs first in the east and
progressively moves along the Himalayan chain, into the west covering the entire stretch of the
country.
The months between October and May are mainly dry, though a winter monsoon which travels
eastward from the Mediterranean Sea occasionally brings rain. The winter monsoon has more
influence in west than east. Precipitation in the form of hail may occur during February and
March.
The steep gradient, young geology, sharp physiographic changes within short distances and the
orographic influence due to high mountain barriers influence the spatial variability of
18
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
precipitation. On the other hand, depleting forest cover, population pressure and increasing
urbanizations, cultivation on steep slopes have a combined effect on the dynamics of hydrologic
cycle and water induced environmental degradation such as landslides and debris flow
contributing to ever increasing peak floods and sediment concentrations.
All major river basins except those of the southern rivers originate in the Himalaya or the
Tibetan Plateau. These river basins are partly snow or glacier fed. During the monsoon, these
rivers receive abundant runoff due to heavy rainfall, which results in floods. The effect of the
snowmelt factor becomes insignificant as they move from north to south. Rivers originating
south of the Mahabharata and flowing towards the Terai belt through the Siwalik Hills are
categorized as southern rivers and they depend entirely on rainfall for their runoff. The
hydrograph of these catchments show no rise in flow until the first monsoon rains.
In Nepal, monsoon rains and snowmelt contribute to river flow. Depending on the altitude some
catchments are influenced by monsoon and some by snow melt. On catchments that are entirely
below 3000 m, there is no significant contribution from snowmelt. On catchments that are above
5000 m, snow melting is major source for stream flow. Catchments lying between 3000 and
5000 m are influenced by both monsoon and snowmelt.
19
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Depending on whether a river is gauged or not, the methods available for estimating the flood
discharge of rivers can be broadly classified into two categories – direct methods and indirect
methods. Direct methods are used to estimate design floods for different return periods using the
flow data or precipitation data available at gauged locations. Indirect methods are helpful in
estimating floods for an ungauged basin, where no, or very few, data are available in the vicinity
of the study area.
Naugarh Gad can be classified as a gauged river. Very few flow measurement data are available.
For frequency analysis it is not sufficient. Hence, hydrologic analysis of this river was carried
out by indirect methods consisting of regional prediction methods and empirical methods. The
regional prediction methods used in this study include the WECS/DHM Method. Among several
empirical formulae tried in the study, Fuller’s, Dicken’s, Log-Pearson, Horton’s, Synder’s
formula provided comparable values to those obtained from the above methods. Details of
calculations of above methods are shown in the Appendix B.
20
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
4.3.1 Regional Regression Method developed by WECS (Water and Energy Commission
Secretariat) and DHM
The WECS/DHM Method was developed by WECS (1989) which estimates the hydrological
characteristics of ungauged sites in Nepal using a frequency distribution parameter technique that
is a variation of the multiple regression technique. In this method, the independent variable that
is most significant in the regression analysis is the area of the basin below the 3,000 m elevation,
i.e. the area of the basin influenced by monsoon precipitation. This method is not applicable to
basins located entirely above 3,000 m, and its results for basins with a very small portion below
the 3,000 m elevation are not particularly reliable. Since the basin of Naugarh Gad lies entirely
below 5,000 m, this method was used for flood flow analysis.
The WECS/DHM Method uses regression equations for 2-year (median flood) and 100-year
floods for both maximum daily and maximum instantaneous flood peaks of the form:
Qaby ( A3000 1)
where Qaby is the discharge in m3/s, subscript a is either a daily or an instantaneous flood peak,
subscript b is either a 2 year or a 100 year return period, A3000 is the catchment area below 3,000
m and and are coefficients and taken from reference book. Using this equation, floods of
other return periods can be calculated simply by the plotting the 2 year and 100 year floods on
log-normal probability paper, which results in a straight line. Alternatively, algebraic equation
can be used for this purpose.
So Flood flow of 2 years and 100 years return period are predicated using following equations:
Where, Q is in m³/sec
As per our calculations for 100 year return period Q= 315.89m3/s. Full calculations shown in
Appendix B.
21
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Where QT is the discharge in m3/s, Cf is Fuller’s coefficient ranging between 0.18 and 1.88, A is
the catchment area in sq. km and T is the return period in years. For Naugarh Gad, the value of
Cf was adopted as 1.88 (for small catchment), and flood values of different return periods were
computed using above formula. It should be noticed that the flood values of different return
periods yielded by Fuller’s formula are very low compared to others.
As per our calculations, for 100 year return period Q=287.39m3/s. Details of calculations shown
in Appendix B.
If Hydrological data of the required river is not available or if the available data has low
reliability, we can obtain it by correlation of the flow data from other hydro logically similar
basin. The discharge of the required basin is given by:
A
Q2 = 2 ×Q1
A1
The peak discharge of all the years are arranged in descending order and the each discharge is
assigned with numbers. The return period for each discharge is calculated by using formula
T
n 1
m
22
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
This extreme value distribution was introduced by Gumbel (1914) and is commonly kown as
Gumbel’s distribution. It is one of the most widely used probability- distribution functions for
extreme values in hydrologic and meteorological studies for prediction of flood peaks, maximum
rainfalls, maximum wind speed, etc.
Gumbel defined a flood as the largest of the 365 daily flows and the annual series of flood flows
constitute a series of largest values of flows. According to his theory of extreme events, the
probability of occurrence of an event equal to or larger than a value of x0
y
P( X x 0 ) 1 e e
y x a
a x 0.45005 x
Thus y
1.2825 x x 0.577
x
Where, x = mean and x = standard deviation of the variate X. In practice it is the value of X for
a given P that is required and the eqn. is transposed as
Y p ln ln 1 P
Noting that return period T=1/P and designating YT= the value of y, commonly called the
reduced variate, for a given T,
T
YT ln ln
T 1
T
YT 0.834 2.303 log log
T 1
xT x K x
yT 0.577
where, K
1.2825
23
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
From the available flow data of Sinja flood discharge of different return period is calculated as
transposed to Naugarh Gad Catchment. The values obtained from Gumbel’s Method are fitted on
the best fit line obtained from plotting position method.
The values obtained from this method turned out to be impractical. So, instead we used 7 years
of data of the Hasingbagar gauging station for flood prediction.
The Irrigation Research Institute, Roorkee, India has done frequency studies on Himalayan River
and suggested the following relationship to compute Dicken’s constant for desired return period
as:
1185
CT 2.342 log 0.6T log 4
p
where,
a 6
p 100
A a
Where, a is perpetual snow area in sq.km, A is total catchment area in sq.km and T is return
period in yrs.
QT CT A0.75
In this method the variant is first transformed into logarithmic form (base10) and the transformed
data is then analyzed. If X is variant of random hydrologic series, then the series of z variants
Where,
z log x
zT z K z z
24
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
z z
2
z
N 1
N z z
Cs
N 1( N 2) z 3
The variations of Kz =f (Cs, T) is given in table.
Snyder’s method was used for flood flow estimation by deriving a synthetic unit hydrograph
based on known physical characteristics of the basin. In this method, the peak discharge QPR, in
m3/s, was computed as
Q PR q PR C A AR
where qPR is the peak discharge per square km of the drainage area due to 1 cm of effective
rainfall for rainfall duration of tr in m3/s/sq. km., CA is an aerial reduction factor that accounts for
the fact that the average rainfall intensity over a large area is smaller than that over a small area,
R is the rainfall in cm for duration tR derived from the 24-hour rainfall with the reduction for
area. For use qPR shall be computed from the relation
CP
q PR 2.78
t PR
Where, CP is a coefficient depending upon basin characteristics and tPR is the lag time in hours
for rainfall duration tR, calculated as
t PR t pr .25t R t r
In the above equation, tr is the standard duration of effective rainfall in hours given by
25
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
t pr
tr
5.5
And tpr is the lag time from the midpoint of effective rainfall of duration tr to the peak of a unit
hydrograph in hours, computed as
Where, Ct is a coefficient depending upon basin characteristics, L is the length of stream from
the station to the upstream limit of the drainage area in km and Lc is the distance along the main
stream from the basin outlet to a point on the stream which is nearest to the centroid of the basin
in km.
The coefficients Ct and CP shall be determined from analysis of some known hydrographs in the
region. In the absence of hydrographs, the values of Ct and CP may be adopted as 1.5 and 0.62,
respectively. The flood flows for different return periods were obtained by Snyder’s method is
presented in tabular and graphical form.
Horton’s Formula may be used to compute the flood qtr in m3/s/km2, equaled or exceeded in a T
year return period using the relation
qtr=71.2T0.25/A0.5
As per our calculations, 100 years return period by Horton’s method is 319.2111m3/s.
26
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
5000.000
DIscharge, Q
Gumbell
log pearson
wecs
fuller
500.000
M.Dickens
synder
Horton
50.000
1 10 100 1000
Return Period, T
27
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Estimation of low flow characteristics of ungauged site using the WECS/DHM method requires
homogeneity of the characteristics of the gauged site to the physiographic and/or climatic
characteristics that can be measured in the ungauged basin. The method also recognizes that the
independent variable that is most significant in the analyses is the area of the basin below 5,000
m, i.e. the area of the basin below the approximate elevation of permanent snow. Goroshkov’s
Method (Hydrologic Designs, Leningrad, 1979)
Goroshkov’s Method is empirical but gives good estimates of low flow in the absence of data
and is extensively used in Russia and the former USSR. This method is based on the relation
Qmin(80%) a A f
n
where Qmin(80%) is the minimum monthly flow discharge of 80% reliability in m3/s, A is the
drainage area in sq. km., f is a part of the catchment area feeding the river with additional flow
due to the presence of springs (taken as 5 to 10% of A), a is a drainage area coefficient (= 0.0014
for winter season) and n is a rainfall coefficient (= 1.27 for winter season).
The Qmin for any probability p can be obtained using the equation
Qmin( p %) Qmin(80%)
Where, is a transition coefficient for determining minimum flow discharge with probability p.
The value of is equal to 1.04, 1.0, 0.94, 0.87, 0.80 and 0.75 for values of p equal to 75, 80, 85,
90, 95 and 97 percent, respectively.
For the Naugarh Gad, A = 201.3087 sq. km. and f = 20.23087 sq. km., giving Qmin(80%) = 1.3323
m3/s.
Indirect methods are used for obtaining low flow. The methods involved are WECS and
Goroshkov’s methods are used for our purpose. The design low flow is taken from WECS
Method for monthly for twenty years return period. Low flow generally depends on the
permanent source; hence low flow variance would not be much higher. The return period was
selected as 20 years so that firm power capacity could be increased in the PPA. It gives high rate
of return in the investment but increase the risk factor. Its value is 1.60m3sec.
28
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
From WECS method long term flow is calculated by using following equation:
Q mean = C×(Total basin area)A1 ×(Basin area below 5000m +1)A2 ×(Monsoon wetness index)A3
Where, C, A1, A2, A3 are constants derived from the regression analysis.
Q is discharge in m3/sec
The values of the constants for different months are different. The Monsoon Wetness Index for
the catchment area is taken as 1500mm
If two basins are hydro-meteorologically similar, data extension may accomplished simply by
multiplying the available long-term data at the HSC with the ratio of the basin areas of the base
station (proposed site under study) and the index (HSC) station. In this context, more accurate
results were obtained using Dicken’s flood formula,
3/ 4
A
Q b Q i b
Ai
Where Qb and Qi are the discharges at the base and index stations, respectively, and Ab and Ai are
the corresponding basin areas. The long term mean monthly flow obtained by BAR method is
presented in tabular form. The flow duration curve obtained is also shown.
29
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
80
70
60
Discharge(m3/s )
50
WECS
40 BAR
WECS
30
BAR
20
10
0
0 20 40 60 80 100
% Exceedence
Among the three methods, WECS method is recommended. For 40% exceedence, the design
discharge is 8m3/sec.
30
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
CHAPTER 5
SEDIMENTATION STUDIES
The sediment concentrations are required to design trashrack, the sedimentation tank, gravel trap
and turbine type, The cost of desanding basin is based on the sediment-laden flow. Otherwise,
sediment heavily damages the trashrack, turbine blades, scroll casing, valves and other
mechanical parts.
The main objectives to the sedimentation studies are to:
- confirm reliable long term flow without adverse effects due to sediment accumulation
- estimate the mode of sedimentation and the required flushing facilities.
- obtain sediment loading data required for the design
- evaluate the effects of the project on the river regime
31
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
The Fore-Himalaya
The fore-Himalaya, an intermediate physiographic division between the midlands and the great
Himalayas has generally an elevation above 3000m. The width of this zone varies from 10 km to
50 km with constituents ranging form limestone, Dolomite, quartzite, phyllite and gneiss to high
grade metamorphic rocks.
Naugarh Gad is one of the major tributary of the Chameliya River. It is a perennial river
originating from the Brahma and Korpu Lek of Iyarkot VDC and meets the Chameliya River
about 33.55 km downstream at Dethala village with average gradient of the river is about 1.5%.
The river basin boundary is separated by the Brahma and Korpu Lek in the north, Binayak dada
in west and Siptikhan Dada in east. The basin is elongated from north to south. Naugarh Gad
drains an area of 201 sq km at the proposed head works site and the drainage area of the Naugarh
Gad lies between the elevations of 800m to 4000m. The precipitation data from the stations
Kakerpakha, Darchula, Pipalkot and Patan were used to generate the Isohyetal map within the
catchment of the Naugarh Gad.
There is no sediment data available for the Chameliya River. Thus, indirect methods are utilized
for the sediment estimation at the intake site of the project. The sediment was estimated
indirectly based on the measured data from the Pancheshwor high dam project, Regional Method
and based on the Himalaya Sediment Yield Technique.
The sedimentation data are available from Pancheshwor (Sta. 150) gauging station in Mahakali
River; and from Chisapani (Station no 280) gauging station on Karnali River. The summary of
the sediment estimation of these two rivers are shown in the table 5.1.
32
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Table 5-1: The summary of the sediment estimation of Mahakali River and Karnali River
Mahakali River at
Karnali River at Chisapani
Parameters Unit Pancheshwor
(St. No 280)
(St. no. 150)
The sediment concentration data of the Mahakali River at Pancheshwor are available from May
1990 to Oct 1990 and from May 1991 to Oct 1991 respectively and presented. These data will be
used for the sediment estimation for the Naugarh Gad SHEP by establishing the relationship
between stream flow and sediment concentrations.
The sediment load data measured at the Pancheshwor High Dam Project at Mahakali River is
transferred to the Naugarh Gad by applying catchment ratio method. From the generated data;
regression equations were developed by establishing the relation between daily average sediment
load (in KT) and daily discharge that has correlation coefficient of 0.69. The regression equation
is as follows:
Ls = 0.013Q1.8118
Where,
Ls = Sediment Load in ton/day
Q = Discharge in m3/day
33
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
The sediment load of the Naugarh Gad SHEP at intake site is estimated by using the above
regression analysis. From the analysis; the total annual sediment load is 897810.37 ton/year.
Considering the density of the sediments as 1.4 ton/m3; the total annual sediment load is
641293.12 m3/year.
5.2.2 Sediment Estimation from Himalayan Sediment Yield Technique
Based on sediment data for stations in Nepal, India, and Pakistan, V.J. Galay (Estimating
Sediment Yield in Himalayan Rivers) pointed out that the current sediment production is linked
to geological zones. The Zone Specific Sediment Yield (ZSSY) has divided into five regions.
According to this theory, the five regions are as follows:
Siwalik 5000-15000
34
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Depending upon the condition of the watershed, the yield is low and high. For the Naugarh Gad
basin, where the catchment area lies at High Mountain and Middle Mountain, the yield estimate
is carried out in the following way.
5.2.3 Sediment Estimation from Regional Method (Sharma and Kansakar, 1992)
The regional method for estimating sediment yield by rivers; developed by K.P Sharma and S.R.
Kansakar (1992) is used to compute the sediment transport. This method is based on the
sediment data measured from 12 river catchment of Nepal. Based on the regression studies, the
following formula is used:
Where,
The total annual suspended sediment yield (Asy) = 0.635 million ton/year.
Hence the sediment yield by the Regional Method (Sharma and Kanshakar, 1992) is 3311.2 tom
/km2/year.
The sediment yield estimation from regression analysis of data of Mahakali River at
Pancheshwor, Himalayan sediment Yield Technique and the regional method are 3340.07
m3/km2/year, 4375 (t/km2/year) and 3311.2 ton /km2/year respectively. Since all of these values
35
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
are based on the limited data and empirical relations; field measurement and further analysis is
necessary.
36
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
CHAPTER 6
The design of weir includes computing the elevation of weir crest, length of weir, computing the
forces acting on the weir and checking the safety of the weir from all aspects like overturning,
sliding, crushing etc. They all are explained in the following articles.
There are various factors that affect the elevation of the crest, but in our case, diversion of water
is the purpose and the height should be sufficient to pond the water at a level that can facilitate
design flow in the intake. The height of the weir is governed by the height of intake sill, depth of
intake orifice and depth of the river at the intake site.
The height of the crest affects the discharge coefficient and consequently the water head
above the weir as well as the back water curve.
The elevation of the weir crest was fixed such that the design flood is safely discharged
to the downstream without severe damage to the downstream.
The elevation of the weir determined the head of the power production.
The height of the weir crest affected the discharge that can be diverted into the canal.
The length of the weir depends upon the width of the waterway at the intake site. Crest length
should be taken as the average wetted width during the flood. The upstream and downstream was
properly examined for the protection consideration.
We have designed the headworks so as to safely pass 80 % and 20 % of the design flood
respectively. The spillway is so designed that it can accommodate total flood design. The
undersluice portion is designed only for sluicing the bed load.
37
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
The spillway has been designed as free over fall Ogee shaped weir. The discharge capacity of
Ogee shaped spillway is maximum as compared to that of other type of weirs. Ogee shaped weir
increases hydraulic efficiency and prevent cavitations. The profile of the spillway is made similar
to the nappe profile of the free overfall weir to ensure that there is minimum possibility of
negative pressure development along its length.
-4 1 6 11
0
1
2
3
d/s weir profile
4
1:1 slope
5
d/s weir profile
6
7
8
9
10
38
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
-3 -1 1 3 5 7 9 11
-6 6
-4 4
-2 2
1
d/s weir
0 0
profile
1:1 slope -1
2 d/s weir -2
profile
-3
4 -4
-5
6 -6
-7
8 -8
-9
10 -10
39
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Y1+q2/2gy12=P+Hd
Therefore,
y1=2.12m
V1 = q/ y1 = 12.25m/s
F r1 = q/√( g y13) = v1/ gy1 = 2.69 (2.5< Fr1 < 4.5, Oscillating Jump)
y1
y2 = ( -1 + √( 1 + 8 F12))
2
y2= 7.07m
F r2 = q/(gy23)1/2=v2/(gy2)1/2=0.441
Headloss=(y2-y3)3/4y1y2= 2.023m
No of under sluices =1
Under sluice crest level =866 masl i.e. at the river bed level
Assume, a head of 5m above the weir crest during 100 year flood
40
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Y1+q2/(2gy12)=875.215-866
Y1+ (141/4)2/(2*9.81*y12)=9.215
Therefore, y1=3.26
V1=q/y1=10.813m/s
Y2=Y1/2*(-1 + (8Fr12+1)1/2)
Y2=7.33m
The main forces which are acting on the weir when it will be operation are: Water Pressure,
Uplift Pressure, Slit Pressure and Weight of the weir.
Water Pressure
It is the major external force acting on the weir. This is called hydrostatic pressure force and acts
perpendicular on the surface of the weir and its magnitude is given by: P 0.5 H2 b Where,
γ = Unit weight of water, H = Depth of water, b = Width of the Weir surface. This pressure force
acts on H/3 from the base.
Uplift Pressure
Water seeping through the pores, cracks and fissures of the foundation material, seeping through
the weir body itself and seepage from the bottom joint between the weir and its foundation exerts
41
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
an uplift pressure on the base of the weir. The uplift pressure virtually reduces the downward
weight of the weir hence acts against the dam stability.
Silt Pressure
The silt gets deposited on the upstream of the weir and exerts the horizontal and vertical pressure
as exerted by the water. So, flushing of the silt should be done regularly to reduce its effect of
destabilizing the weir. It is done by the use of undersluice gate. The silt pressure is given by the
relation: P silt 0.5 sub H2 Ka . Where, γsub=Submerged unit weight of silt; H= Depth of silt
deposited and Ka= Coefficient of Active earth pressure and is given by,
Ka
1 sin , Angle of internal friction of silt .But in our calculation we have taken the
1 sin
value of ka equal to 1. The silt pressure force also acts at a height of H/3 from the base.
But for practical consideration, Equivalent Liquid = Mix of silt and water
Weight of Weir
The weight of weir and its foundation is the major stabilizing/ resisting force. While calculating
the weight, the cross section is determined from the drawing (autocad). Also the C.G. is find out
by drawing and from this C.G. the total weight of dam act. the sectional area of each part is
multiplied by unit weight of concrete, weight of that part is obtained.
The weir is designed with ogee profile for spilling over its length. Hence weight is calculated by
knowing its section and multiplying by its unit weight.
If resultant of all the forces acting in the weir passes outside, the weir shall rotate and overturn
about the toe. Practically, this condition will not arise because the weir will fail much earlier by
compression. The ratio of resisting moment to the overturning moment about the toe is the factor
of safety against overturning and it should lie in between 2 & 3 for safety.
42
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Compression or Crushing
While designing the weir section it should be so design that the resultant should pass through
middle 3rd part of the section to avoid the possible tension on the weir section. The section
should be totally in compression. So, weir should be checked against the failure by crushing of
its material. If the actual compressive stress may exceed the allowable stress, the dam material
V e
may get crushed. The vertical combine stress at the base is given by: max/ min 1 6 ,
B B
B M
where e x, x ,e= eccentricity of the resultant force from the centre of the base.
2 V
Sliding
Sliding will occur when the net horizontal force above any plane in the weir or at the base of the
weir exceed the frictional resistance developed at that level. Factor of safety against the sliding is
For safety against sliding, SSF should be greater than 3-5. To increase the value of SSF, attempts
are always made to increase the magnitude of q, which is achieved by providing the stepped
foundation, ensuring the better bond between the dam base and rock foundation etc.
Overturning criteria
H
B= = 5.74 m
G 1
Geometric criteria
B =10.8 m
43
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
44
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
FS=µV/H = 2.4010031
>1 .5
OK
Factor of safety against overturning
FS=MR/MO = 2.417 >1.5
OK
P(max,min) v/B(1±6e/B)
P at heel = 96.40805 <2500KN/m²
P at toe = 36.350608 <2500KN/m²
We have used 100 years return period from probabilistic analysis of flood. A simple and
moderately priced construction is encouraged to minimize maintenance and repairs. For the
small projects with no automation facilities, hydraulically controlled structures become more
feasible than mechanically controlled units. In hydraulically controlled intake structure, usual
practice is to construct skimmer wall to restrict the flood water entering in the canal, such that
intake structure works as free flow weir at normal condition and as submerged orifice at high
flood conditions. The excess water is allowed to flow in canal up to a suitable point downstream
where it is returned back to river using escape structures.
There must be adequate provision to remove the suspended and bed load deposited upstream
behind the weir. This may be done using intermittent flushing using sluice gates or allowing
some water to flush it continuously.
45
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Topography, geology, height of bank, ratio of water diverted to that available, channel width,
routing of diversion canal, ease of diversion of river during construction, stability of river bank
and sides, river protection works governs the selection of the intake location and type. In rocky
banks, winding river, considerable suspended load it is not desirable. The lateral side intake
functions well in such case as in our project site. Intake sill with 1.5 m above the river bed is
used not to allow bed loads to enter the canals. Trash rack is used to prevent the entry of tree
branches, leaves and other coarse materials in the canal.
46
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
= 10.58m3
Provide 2 no of orifice
Width of orifice= 2m
Breadth of orifice= 2m
Pond level=869.9m
< 12 t
47
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Discharge = 10.58m3/s
0.01m
It is necessary to check or trap the particles incoming from the canal intake which would,
otherwise, flow in the downstream side and reduce the discharge capacity of canal and ultimately
cause the wearing and chocking of the turbine unit. The trap of coarse particle (>2mm) is
achieved by means of a hydraulic structure known as gravel trap. During the high flood season,
the river carries appreciable amount of gravel hence a gravel trap is provided to trap the design
size of gravel entering through intake.
Design Considerations
Gravel trap is located at a safe place but as close to the intake as possible so that debris is not
carried a long distance into the waterways. Gravel is checked in gravel trap by allowing water to
flow in a wide and deep channel at a slower velocity so as to reduce the capacity of water
thereby causing deposition of particles towards bed. Flow velocity of water and settling velocity
of the particles affect the settling of the particles. The flow velocity is not exceeded the upper
limit so as not to allow suspended again.
The flushing of settled particles is done to ensure proper working. Generally continuous flushing
is adopted for gravel trap as the sediment load is high. Gates are used to control flow at flushing
48
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
orifice at inlet. Sufficient bed slope and cross slope is required to make the flushing effective.
Standard methods are used to design the gravel trap. The concentration approach, which is
modern and rational approach, is used. Vetter's equation to calculate efficiency is used. Camp's
formula is used to calculate the transit velocity and Newton's formula is used to calculate the
settling velocity.
Continuous flushing system is used in the gravel trap which works continuously in the monsoon
season and can work as intermittent flushing at the time of low flow. 15% water is used for
flushing purpose.
Protection Works
Gates are used to control the flow across the gravel trap. Flushing gates are used to flush the
settled matters. The flushing orifices are controlled using the flushing gates. Flushed water and
the excess water are safely diverted to the river using open channel. The side protection works
fencing etc. are carried out.
Design
Discharge Q = 8m³/s
Flushing: Continuous
1. Design of gravel trap basin
Since d>2mm, fall velocity w= √ (3.33g(S-1)*d) = 0.33m/s
R = w*d/v
V = kinematic viscosity of water = 0.33*0.002/1.31*10^6 = 500m²/s
For R = 0.5 to 1000, Cd = 24/R + 3√R + 0.34 = 0.522
After iteration we get w = 0.283m/s
Transient velocity v = a√d
a = 36 for 2mm particles
v = 36√2 = 0.5m/s
Efficiency η = 1-e-wAs/Q
For η = 90%, As = 64.12
49
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Let Height H = 3m
Width B = Q/(v*H) = 6.13 = 6.2m
Length L = As/B = 10.34m
Provided Length = 10.34/0.85 = 12.16 =13m
2. Transition Design
Let inlet angle = 8o and outlet angle = 15o
Inlet length = (3-1.7)/ (2*tan8o) = 5m
Outlet length = 3m
Total length = 5 + 13 +3 = 21m
3. Flushing Canal Design
Flushing discharge = 0.15*Q = 1.38m³/s
Assume 0.5m X 0.5m size flushing canal
Area A = 0.5 X 0.5 = 0.25m²
Perimeter P = 0.5 + 2*0.5 = 1.5m
Hydraulic radius R =A/P = 0.167m
Assume bed slope = 1:30
V = 1/n * R2/3*S1/2 = 3.69m/s
Tractive shear stress τo = γwRS = 9.81*0.167*1/30 = 54.6N/m²
Critical shear stress τc = 0.056γwd(S-1) = 9.06N/m2
As τo>τc, OK.
The approach canal is designed to convey the abstracted flow from the intake to the settling basin
in a hydraulically efficient manner. Likewise, the gravel trap is designed to trap and efficiently
flush out the coarse sediments that manage to enter the approach canal through the intake
Design Criteria
The approach canal connecting the intake structure to the settling basin shall have an optimum
length chosen with due consideration to the topography of site. However, the canal shall be
economically effective and hydraulically efficient for transporting the specified size of sediments
passing through the intake structures.
50
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
The design of the approach canal shall be performed assuming steady (sub-critical) flow regime in
the canal. Under this assumption, the canal is designed using Manning’s formula.
Hydraulic Design
Regimes of Flow
The regime of flow in approach canal is non-pressure flow. A steady flow regime is maintained,
i.e. the mean flow velocity in the approach canal is considered to be constant, not changing in
time and space along and/or on the canal flow section.
Canal Cross-section
Hydraulic Characteristics
Based on the principle of non-silting and non-scouring velocity with efficient transporting
capacity of flow with regard to sediments, either Manning’s or Chezy’s formula may be applied to
determine the hydraulic characteristic of the approach canal. In our case we have used the
Maning’s Formula.
1 2 / 3 1/ 2
V R S
n
where V is the mean flow velocity in the canal in m/s, n is Manning’s rugosity coefficient, S is
A
the longitudinal bed slope and R is the hydraulic mean radius in m,given by R in which A
P
is the flow area of cross-section in m2 and P is the wetted perimeter in m.
51
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
A = 10.58/2 = 5.29m2
= 5.29/2.4 = 2.2m
V = R2/3s1/2/n
Where R = hydraulic radius
= A/P
= 5.29/(2.4+2*2.2) = 0.77
0.772/3 s1/2 /0.015 = 2
∴ S = 1: 784
General
The suspended particles entered in a canal, if allowed to flow through penstock pipe and turbine,
cause abrasion of such units and reduce efficiency as well as durability. In addition, problem of
clogging is always present due to such particles in turbine units. There is also the possibility of
siltation in canal. So, the finer particles escaped from gravel trap are to be removed before
entering in to penstock.
The severity of particles depends on effective head of water, hardness of particles, shape of
particles and size of pipe, valves opening and turbine blades and opening. It is very difficult to
trap all the particles. So, a particular size of particles is selected to make a design basis for
Settling Basin. The basin design philosophy is similar to that of gravel trap. Selection of width
and length depend on land available. For more reliable operation, more than one chamber is
employed. It will not interrupt whole system when it is to be stopped for maintenance. To ensure
52
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
uniform flow, transitions are provided at inlet and outlet. Both height and width vary gradually
inlet transition and width varies in outlet transition.
Flushing of deposited matters is essential for smooth operation of settling basin. The lateral and
longitudinal slope is provided for this purpose. There is control of flow in and from settling tank.
For this purpose gates are used. A continuous flushing system is operated continuously in wet
season when there is sufficient water and excessive sediments. In dry season, when there is clear
water in river and water is scare, it works as intermittent flushing.
Design Consideration
The settling basin is designed following standard practices. Concentration approach is used to
design it. Trap efficiency is selected as 90% removal of 0.2mm sized sedimentary particles.
Vetter's equation is used for efficiency calculation. Camp's equation and various charts are used
to compute the transit velocity and the settling velocity.
Settling basin with continuous flushing is designed to supply sediment free water to the water
conveyance system through simultaneous settling of the suspended sediments and flushing of
deposited sediments. The flushing is achieved by continuously abstracting water from the bottom
of the settling basin during operation.
Water level and water flow is maintained in the basin throughout the flushing period in order to
facilitate continuous power genreration. Removal of sediments while the basin is operational
may be achieved with continuous flushing or intermittent flushing or by use of some kind of
suction or dreding device.
In order to remove the settled particles by flushing it is necessary to generate a current close to
the particles able to erode and carry the particles away with the flushing flow without mixing
them with the main water flow in the basin.
53
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Where,
T= Temperautre =100C
Vf = =27.588 [4]
Re=Reynold's no= ,
Re=27.588*0.2/1.31/0.01/10/10=4.2119
Vf =
Where, CD=
So, CD=4.499
Vf = 23.99 mm/sec
This is less than initial assumed value of 27.588mm/sec, so repeat the process.
54
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
S.No Vf(mm/sec) Re CD Vf
Vf = 21.562 mm/sec
55
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
=Fall Velocity,
Q=discharge m3/sec
Taking L/B = 8
So, B = 8 m, L = 64m
Q = B*H*L
Volume of Storage=456.92 m3
Since the above calculation is considered for the case of rectangular base, we recalculate the
area for the base with the angle of inclination of slope = 40o, when the area resembles with
rectangular base.
56
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Design of Transition,
Inlet profile:
Provide slope 1 in 5
Outlet Profile:
Provide Slope 1 in 2
Flushing Canal
Q = 1.2m3/s
Area = 0.2 m2
B = 0.6m: H = 0.6 m
Area = 0.36 m2
Velocity Check,
R = 0.2 m
V = 3.22> 3 m/sec
Hence, OK.
57
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Where,
γw = Specific gravity
R = Hydraulic radius
S = Bed slope
= 39.24 N/m2
Critical shear stress for dmm dia Particles (τc) = 0.056* γw *d*(S-1)
Where,
D = diameter of particle
S = 2.65
Therefore,
= 18.12 N/m2
τ0> τc
Hence, OK.
The sediment free water from settling basin is needed to be conveyed to the surge tank. The
choice of conveyance system in our case is the pipe depending upon the topography, geology,
size and suitability of project site. Gentle slope and good geology of the area permitted the
option of pipe conveyance system. Landsides may affect this type of scheme frequently and
evaporation, seepage loss is also high. Steel pipe of 2.3m diameter is proposed in this project.
Surge tank is provided between the pipe and penstock to protect the pipe and the penstock from
water hammer pressure caused by sudden rejection and exceptance of load.
Design Consideration
The surge chamber is located such that the pressure variations caused by water hammer
are kept within acceptable limits.
The chamber is stable, i.e. the surge resulting from small partial load changes is naturally
damped and is not sustained or amplified under any circumstances.
b. The lowest down-surge will not allow air to be drawn into the pipe.
c. The range of surge is not greater enough to cause undesirably heavy governor movements
or difficulty in picking up load.
59
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Calculations:
Size of Surge Tank
By D. Thoma,
𝐴𝑡 𝐿𝑉𝑜2
Critical Area of Surge Tank, Ast,cric ≥ 2𝑔𝐻
𝑓 (𝐻𝑔 − 𝑓)
ZDownsurge = Zmax(-1+2Po)
where,
60
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Zmax =
= 15.08066 m2
Po=ht/Zmax
Then,
T=
T = 334.8 sec
Volume of surge Tank
V = 893.46 m3
61
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Since the topography does not allow the construction of vertical surge tank due to cost
considerations, inclined surge pipe is prefered and calculations for changes in the
diameter of the surge pipe are shown as below
Taking the diameter of the water surface equal to the above calculated diameter of
surge shaft,
6.14 Penstock
General
The potential energy of the flow at the inlet chamber is converted into the kinetic energy at the
turbine of a hydropower plant via the pipe known as penstock. Water flows under pressure in the
penstock. The penstock has to fulfill various serviceability requirements for safe and reliable
operation of the plant. It has to bear a very high pressure caused due water hammer effect at the
sudden closure of the gate by governing mechanism of the turbine. Penstock should be smooth
enough so as to result minimum head loss while flowing water and it corrosion resistance from
durability aspect. The thickness should be sufficient to resist hoop stress developed by water
hammer pressure and normal pressure not exceeding the allowable stress. Penstock alignment
must be straight to avoid head loss at bents and the extra cost of anchor block unless it is
mandatory by site condition. The penstock may be either embedded or exposed as per
topography, location of inlet chamber/ Surge Tank, Powerhouse and construction easiness etc.
For a particular head and discharge, there may be several options for the size of penstock
according to continuity equation (Q=AV). Also head loss increases squarely with increase in
62
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
flv 2
velocity as per Darcy-Weishbach equation h l . So, a smaller size penstock saves cost of
2gd
construction material but the loss of energy due to loss of head takes place and vice versa. Due to
this fact, we can deduce as optimum diameter which minimizes the total cost and the same is
adopted for the project. Water hammer pressure in excess of normal water pressure can be
Vo
expressed in equivalent water column height as, hm = Vc × , Where Vo= Velocity of water in
g
Km 1
penstock, Vc = Velocity of wave ; K m , Where K = Bulk Modulus of
1 D
K tE
water, D = Diameter of penstock, ttu = thickness of penstock, E = Young's Modulus of elasticity
Pd
of steel, ρ = density of water. Also, thickness of pipe, t ; Where, P = total pressure in pipe
2
and σ = Permissible hoop stress of steel in pipe.
If the penstock has to feed more than one turbine, various factors govern whether use
independent pipes in number equal to the equal to the no. of turbine or use one pipe and bifurcate
it at turbine inlet. Length from inlet chamber to powerhouse, construction feasibility, reliability,
transportation and fabrication feasibility are some important factors to be considered for this.
Optimization
Penstock is one of the costly and important structures in hydropower plant. The larger size incurs
more cost of the structure and a smaller size saves the cost of structure but is associated with
increased head loss (which is ultimately the power loss). So, there is always an optimum size of
penstock for which the total cost of loss and the material is minimum. To seek this size,
optimization technique is used. Increase in size tends to increase the thickness, as thickness is
directly proportional to diameter but this relation is no more valid as the water hammer pressure
decreases with increase in size. The optimization is carried out considering these aspects.
Penstock of Diameter 1.8m is selected as per the Optimization process shown in Appendix D.
63
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Power house is a house constructed to accommodate the electro mechanical equipment such as
turbine, generator, control panels etc. The main function of the building is to protect the
electromechanical equipments from adverse as well as the mishandling by unauthorized person.
The basic requirement of the power house is functional efficiency along with the aesthetic
beauty.
The size of the power house is strictly governed by the size and type of of the turbine and
generator. The arrangements and the number of units also govern the size of power house. The
size of the power house should be sufficient enough to arrange all the equipments with the clear
space for the installation and maintenance of these large equipments. The center to center
distance for one unit is taken as (5D+2.5m) for the vertical arrangement, where D is the diameter
of runner with casing while in case of the horizontal arrangements, the length is determined with
minimum clear spacing of 2m between two units.
Height of the power house is fixed by the dimensions of lower turbine block and its
superstructure. Height of the lower turbine block from the foundation to the floor of the machine
hall is to be determined by the thickness of foundation plate, dimensions of the turbine.
Sufficient clear space is also provided for crane operation.
Machine hall
C/C distance between two turbine = 7.5m
But for the provision of hatch for transporting the equipments provide extra = 5m
64
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
But the width of the power house is provided such that the draft tube also
lies within the power house. So considering the length of draft tube, the
width of the power house is obtained to be 9.85m.
Total height of the power house above the MIV floor = 16.55m
Loading Bay
Control Bay
General
A hydropower plant requires a great deal of mechanical and electrical equipment. The major
electrical components are: Generator, Exciters and Voltage regulators, Transformers,
Switchgear, Control room equipment including switch boards. Similarly, mechanical
components are: Shaft, bearing coupling etc for generators, oil circuits and pumps, compressors
and air ducts, braking equipments. The arrangements for lighting, water supply and drainage
should also be provided.
65
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
6.16.1 Turbine
General
Turbines are machines which convert kinetic energy into mechanical energy and transmit it to
the generator through direct coupling of shaft to it which in turns converts mechanical energy
into electrical energy. In our project, we have used the reactive turbine.
Reactive Turbine
The turbine, in which both kinetic energy and potential energy of water is utilized to rotate the
runner or the turbine is called the reactive turbine. The water flows through the runner under
kinetic and potential energy. The turbine runner is submerged and water enters all around the
periphery of the runner. Water is taken up to the tailrace by means of a closed draft tube and thus
whole passage of water is totally enclosed. The proposed reactive turbine is Francis
Design Philosophy
There are various types of turbines with wide of hydraulic features. Selection of suitable type of
turbine for the project depends upon several factors like head, discharge, power production, load
condition and corresponding efficiency, quality of water, tail water level, size, construction
feasibility etc. Selection of turbine is essential for the layout of the powerhouse, approaching and
discharging pipes, conditions of construction and exploitation and techno economic parameters.
The turbine is selected from the following basic criteria:
4 to 70 - Pelton
60 to 400 - Francis
66
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Different literatures had given various charts/graphs for the selection of the turbine.
For medium high to medium and low heads and normal quality of water, Francis turbine is
suitable for our siite. Turbine is designed based on the specific speed (Ns), which is the speed of
the geometrically similar (identical in shape, blade angles, gate opening etc.) turbine that would
develop unit power under a unit head. For specific speed between 60 to 400 rpm, Francis turbine
is suitable. Since, reaction turbine is susceptible to cavitations; setting of turbine is made based
on the cavitations criteria. A draft tube is always provided with the reaction turbine to receive the
pressure head at the outlet of the turbine. Efficiency of the Francis turbine decreases substantially
at part load operation. For runoff river plants, discharge of the river becomes lower than the
design discharge of the plant. So, part load operation is essential. If a Francis turbine is allowed
to run at part load for long time, cavitations become more serious. Thus, these criteria were kept
in mind while designing the turbine.
67
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
6.16.2Turbine Design
Selection of Turbine
For head between 25-250m, Francis medium head turbine can be chosen.
Number of turbine = 2
Frequency of AC supply = 50 Hz
#No. of poles is taken in the difference of 4 for upto 200m & in the difference of 2 for head
>200m
68
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Flow ratio = Take 0.2 (0.15-0.3); Speed ratio = Take 0.6 (0.6-0.9)
Inlet diameter = 1m
Outlet dimension:
69
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
70
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
6.17 Tailrace
General
Tailrace is the final civil structure that conveys the design flow from powerhouse back to the
river where it is disposed off. Open channels are used as tailrace structure.
Design Criteria
Design o the tailrace channel is similar to that of headrace channel. Since head loss does not need
to be minimized a higher velocity can be allowed in tailrace channel. Note that at higher
velocities higher grade of concrete is required to resist erosion. Reinforced concrete becomes
economical for a steep channel. The downstream end of tailrace is protected so that there is no
danger of erosion either by the river or by the flow from the tailrace.
71
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Hence, OK
𝑛𝑣 2
S = ( 2/3) )
𝑅
V = 2.35m/s
<3m/s
Hence, OK.
72
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
𝑛²𝑣²𝑙
𝐻𝑓 = 𝑅 4/3
RL of turbine = 724.250m
73
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Slide blocks are used to support the pipes at intermediate points so as to prevent excessive
bending stresses in the pipe. They resist the weight of the pipe and water and resist the lateral
movement but allow the longitudinal movement of the pipe. So, these blocks are lighter in
weight than anchor blocks and save the overall cost of the support action.
Design Philosophy
Water flowing under pressure when diverted from straight path exerts pressure as the bends.
To resist various forces these blocks are designed. The blocks act as the massive structures
and work as the gravity dams. Sliding, Overturning, tension and crushing are to be checked
for the blocks.
The support engages less than the full perimeter of the penstock, generally between 90 and
180 degrees of arc, and typically 120°. These are simpler to construct than full perimeter ring
girder supports, but generally are spaced closer together than the ring girders. It is usually
spaced between 6 to 8 m between the anchor blocks. It is constructed of concrete 1:3:6.
Design procedure is same as that of the anchor blocks but only the combination of load is
different.
74
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Expansion joint permit only the longitudinal movements. The joints are used primarily with
aboveground installations and are located between the supports at the points where the
penstock deflections are of equal magnitude and direction. These joints divide the barrel shell
into separate units, which are watertight, but structurally discontinuous. It should be provided
just below the anchor block. Length of the expansion joints tL
Construction
Anchor blocks are the support of the penstock and are constructed to meet this purpose. As
the penstock is circular, the anchor blocks are made to fit the curve surface. Saddle supports
are used in it and a sufficient cover is provided above the pipe for adequate fixity.
Anchor blocks are designed similar to the gravity dam. The blocks are to be designed to resist
overturning, sliding, crushing and tension failure. A firm foundation is required for the
blocks. The blocks should be prevented from gulley erosion due to rain water.
75
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
CHAPTER 7
GEOLOGICAL STUDY
This report deals with the geology of the Naugarh gad Hydroelectric Project area in Dethala,
VDC of Darchula District, Mahakali Zone, Far-Western Development Region. The study
includes regional geology of the project area, suitability of the different hydraulic structures and
availability of different construction materials in the project area.
The geological and geotechnical explorations were carried out as a part of field investigation.
The main objectives of the exploration were to collect, analyze and summarize geological and
geomorphic information to determine the physical properties of the rock in the project area and
in the major hydraulic structural site of the Project.
7.2 Methodology
The methodology adopted for the study consisted of desk study, field investigation and analysis.
Available literatures, papers and reports, maps, aerial photographs related to the project area
were collected and studied. The field investigation works was carried out last week of Jestha,
2070.
76
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
It is divided into two parts based upon the age. The lower part identified as the Lower Nawakot
Group is of Late Precambrian to early Mesozoic age while the unconformably resting upper part
known as the Upper Nawakot Group ranges from Permo-Carboniferrous to lower to middle
Eocene. Though the lesser Himalayan rocks are virtually unmetamorphosed, contain scant fossil
evidences thus making it difficult to date.
The Naugarh Gad Hydroelectric Project area is situated in the Lesser Himalaya.
7.5 Regional Geology of the Project Area
The regional geology of the project area is described on the basis of Geological Map of Far-
Western Nepal (Compiled) published by Department of Mines and Geology (DMG, 1987).
77
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Geologically, the project area consists of Galyang Formation and Lakharpata formation of
Midland Group (Upper Precambrian to Late-Paleozoic age), Lesser Himalaya.
Galyang Formation
This formation consists of dark grey slates finely intercalated with thin grey calcareous slates and
sandstones giving brown yellow and grey laminations oblique joint planes on weathering.
Frequently dark grey to bluish grey fine grained limestone and dolomitic limestone of various
sizes with in the slates. With in this formation; Baitadi Carbonate Unit also occurred which
consists of grey siliceous dolomite.
Lakharpata formation
This formation consists of fine grained, grey limestone and dolomitic limestone with thin
intercalations of black to grey shale. At places white pink dolomitic limestone purple and green
shale are present at the top. Algal structures and stromatolite are present.
The project area is located about 35 km south from the surface exposure of Main Central thrust
(MCT) and lies more than 60 km north from Main Boundary Thrust (MBT). The rocks in the
projects are fractured and faulted.
In spite of these major thrust systems, two major faults can be traced in the project area from the
Compiled Geological Map published by DMG (1987). One fault lies in the south of the
powerhouse site along the Chameliya River; the fault contact between the underlying Galyang
Formation and the overlying Lakharphata Formation. Another fault passes along the Hopari
Khola in the pipeline alignment and is about 1 km downstream from the intake area. This fault
separates the underlying dolomite and interbedded dolomite and dolomitic black slate and over
lying slate.
78
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
The project area lies mainly in Galyang Formation and Lakharpata Formation (Devthala
Dolomite of the Darchula Group of Upreti, 1990) in Far Western Nepal Lesser Himalaya. This
formation is predominantly composed of bluish-gray, thick bedded, stromatolitic dolomite with
minor black, purple slates and quartzite intercalations. The major rock type occurred in the
project area are as follows:
Light blue to Greenish-gray Dolomite
Dolomite interbedded with calcareous schist
Dolomite interbedded with Black Slate
Slate
Quaternary deposits
79
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
Quaternary Deposits
Most of the basal part of the hill slopes; river valley and river banks are covered by the
quaternary deposits. Following quaternary deposits are distributed in the project area:
a. Colluvial Deposits
The colluvial deposits are distributed along the basal slope of most of the hills on the both bank
of the Naugarh gad and its tributaries. In most of the places, the colluvium consists of mostly
angular to sub-angular fragments of dolomite and few slates and quartzites in silty and clayey
matrix. The thickness of the colluvial deposits varies place to place. Very thick sequences of
colluvium are deposited at the slopes of Suke Khola and Hopari Khola valley. Most of the
colluvial deposits are deposited by the small tributaries coming from the steep hills where mass
movement has been active.
b. Alluvial Deposits
The ancient river terraces and tars are formed by Chameliya River near the confluence of
Chameliya and Naugarh gad at Dethala village. At Dethala village, four levels of terraces are
developed which consist of mostly semi consolidated conglomerate and consists of mainly
80
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
quartzite, dolomite, slate and amphibolite with sandy and silty materials. The highest terrace
level is more than 70 m from the existing Chameliya River bed. Some narrow terraces are also
formed by the Naugarh gad on its course. Some river terraces are also formed by the Naugarh
gad on its course in the project area. These terraces formed by Naugarh gad are up to 20-25 m
high from the present river bed.
d. Residual Soil
The residual soils are developed along the ridges and upper part of maintains and hill slopes in
the project area. Most part of the terrain in the project area is covered by the residual soil. The
hills and gentle slopes in the north of Dethala village, around Tallo Manbhan, Mallo Manbhan,
Chalakikhal, Ratyada village are covered by the residual soil. These residual soil are red and
brown colored, and consist of few pebbles and boulders of dolomite, slate and quartzites. The
thickness varies place to place and may reach up to 5 m.
81
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
CHAPTER 8
COST ESTIMATE
This section of report describes the tentative capital cost estimation of the Naugarh Gad SHEP
and also describes the assumptions made and the methodology used in cost estimate of the
project. The project cost estimate is carried out in parallel with the quantities of various items
taken off from the feasibility level of drawings and quantities derived from empirical relations.
The approximate cost estimate of the alternatives is shown in Appendix A.
The overall cost estimate of the proposed alignment is shown in Appendix G.
The overall cost of the project is Rs 1153.188 million.
8.1 Assumptions
The following criteria and assumptions are the basis of the cost estimate:
All costs are in January 2009 price level.
For currency conversion, the following rate $1 = NRs.95.00.
Electromechanical costs are assumed.
Administrations costs are taken as 20% of (civil works + electromechanical cost).
8.2 Methodology
An essential first step in the estimating process is a break down done by major cost components.
For the Naugarh Gad SHEP the major component breakdowns for the estimating process are:
support facilities, access roads and other general items
main civil construction works
electromechanical equipment
adminstration and labour cost
82
Pre-feasibility Study Report on Naugarh Gad SHEP 2070
8.3 Recommendation:
The Naugarh Gad Small Hydroelectric Project is financially feasible and technically viable with
minimum socio-environmental impact. With the implementation of the proposed project, the
country is expected to get benefit which otherwise is flowing unused and envisaged to play a
critical role in furthering the economic activities of the project area as well as the country with
positive contribution to the national growth and poverty alleviation.
83
CHAPTER 9
CONCLUSION AND RECOMMENDATION
9.1 Conclusion
Naugarh gad SHEP is a run-off type hydro-power project with an installed capacity of
8.9MW generated through a net head of 127.09m and a design discharge of 8m 3/s. Nepal
is facing daily upto 16 hours of load shedding causing shut down of main industries.
Energy crisis is leading our country to economic crisis. Naugarh gad SHEP could be a
milestone in the history of hydro power development.
Site visit was done in the last week of Jestha and three alternatives were selected
according to cost-energy analysis. Proposed pipeline alignment was selected for pre-
feasibility analysis. The pondage area includes few cultivated and population settlement
area reducing rehabilitation cost. It can be concluded from this study that the proposed
hydropower project is technically viable and economically feasible. Hence, the project
can be subjected to feasibility studies.
9.2 Recommendation
Earthquake study must be done precisely and structures, water ways etc. must be desgned
with stand the effects of seismic stresses.
The detail economic and financial evaluation should be done considering various
financial resources, repayment policy adopted by government and the ability of the
project to meet the payment obligation.
84
REFERENCES
85
APPENDIX- A
(Alternatives Selection)
A. ALTERNATIVE SELECTION
Avge D/S release Q Available Q used Power Dry Season Wet Rate
Month 3 Days Amount (Rs.)
Discharge (m /s) (m3/s) (m3/s) Generation Energy Season (Rs./Unit)
Jan (m3/s) 2.55 0.196 2.357 2.357 (MW)2.614 31 (GWHr)1.945 Energy 7 13615245.90
Feb 2.17 0.196 1.978 1.978 2.194 28 1.474 7 10321439.97
Mar 1.96 0.196 1.766 1.766 1.959 31 1.457 7 10202230.59
Apr 2.03 0.196 1.833 1.833 2.033 30 1.464 7 10244747.08
May 2.74 0.196 2.548 2.548 2.826 31 2.102 5 10511383.69
Jun 10.84 0.196 10.644 8.000 8.872 30 6.388 5 31939790.40
Jul 33.23 0.196 33.030 8.000 8.872 31 6.601 5 33004450.08
Aug 40.19 0.196 39.994 8.000 8.872 31 6.601 5 33004450.08
Sept 31.28 0.196 31.085 8.000 8.872 30 6.388 5 31939790.40
Oct 13.43 0.196 13.235 8.000 8.872 31 6.601 5 33004450.08
Nov 6.35 0.196 6.150 6.150 6.820 30 4.911 7 34374659.17
Dec 4.06 0.196 3.865 3.865 4.286 31 3.189 7 22321236.77
Total 14.43993707 34.68086 274483874.2
Avge D/S release Q Available Q used Power Dry Season Wet Rate
Month 3 Days Amount (Rs.)
Discharge (m /s) (m3/s) (m3/s) Generation Energy Season (Rs./Unit)
Jan (m3/s) 2.55 0.196 2.357 2.357 (MW)2.552 31 (GWHr)1.898 Energy 7 13288577.25
Feb 2.17 0.196 1.978 1.978 2.142 28 1.439 7 10073799.14
Mar 1.96 0.196 1.766 1.766 1.912 31 1.422 7 9957449.93
Apr 2.03 0.196 1.833 1.833 1.984 30 1.428 7 9998946.32
May 2.74 0.196 2.548 2.548 2.758 31 2.052 5 10259185.56
Jun 10.84 0.196 10.644 8.000 8.659 30 6.235 5 31173463.57
Jul 33.23 0.196 33.030 8.000 8.659 31 6.443 5 32212579.02
Aug 40.19 0.196 39.994 8.000 8.659 31 6.443 5 32212579.02
Sept 31.28 0.196 31.085 8.000 8.659 30 6.235 5 31173463.57
Oct 13.43 0.196 13.235 8.000 8.659 31 6.443 5 32212579.02
Nov 6.35 0.196 6.150 6.150 6.657 30 4.793 7 33549912.88
Dec 4.06 0.196 3.865 3.865 4.183 31 3.112 7 21785686.52
Total 14.09348172 33.84877 267898221.8
Avge D/S release Q Available Q used Power Dry Season Wet Rate
Month 3 Days Amount (Rs.)
Discharge (m /s) (m3/s) (m3/s) Generation Energy Season (Rs./Unit)
Jan (m3/s) 2.55 0.196 2.357 2.357 (MW)3.361 31 (GWHr)2.501 Energy 7 17505316.15
Feb 2.17 0.196 1.978 1.978 2.821 28 1.896 7 13270422.82
Mar 1.96 0.196 1.766 1.766 2.519 31 1.874 7 13117153.61
Apr 2.03 0.196 1.833 1.833 2.613 30 1.882 7 13171817.67
May 2.74 0.196 2.548 2.548 3.633 31 2.703 5 13514636.17
Jun 10.84 0.196 10.644 8.000 11.407 30 8.213 5 41065444.80
Jul 33.23 0.196 33.030 8.000 11.407 31 8.487 5 42434292.96
Aug 40.19 0.196 39.994 8.000 11.407 31 8.487 5 42434292.96
Sept 31.28 0.196 31.085 8.000 11.407 30 8.213 5 41065444.80
Oct 13.43 0.196 13.235 8.000 11.407 31 8.487 5 42434292.96
Nov 6.35 0.196 6.150 6.150 8.769 30 6.314 7 44195990.36
Dec 4.06 0.196 3.865 3.865 5.511 31 4.100 7 28698732.99
Total 18.56563337 44.58968 352907838.3
Cost of Penstock
The cost of the penstock can be assumed as NRs 250/kg. The cost of head race pipe line is assumed to be NRS200/kg. The thickeness of pipeline is taken as 8mm and density of pipeline=7850kg/cubic meter.
alternativeavailable head Thickness of penstock pipe(mm)
x-sectional area of pipe material(m^2) length of penstock pipe(m) volume of cast iron used weight of cast iron(kg) total cost of penstock pipe(NRs)
1 140 20 6.04982 700 4234.88 3E+07 7569839296
2 160 20 6.04982 425 2571.17 1.8E+07 4595973859
3 180 20 6.04982 300.04 1815.19 1.3E+07 3244649404
Cost of Sediment
The cost of the sediment exclusion work can be assumed as NRs 15 mln/cumec flow
alternative installed discharge capacity(m^3/s) cost of sediment exclusion(NRs)
1 8 120000000
2 8 120000000
3 8 120000000
The cost per KW for alternative 3 is taken as NRS (4286879135 + X) where X is used to account for the cross drainage structures proposed in the alignment.
Since the geology of the project site is not suitable for tunnel alignment, alternative 1 has been discarded.
Alternative 2 doesn’t have any cross drainages structure; hence the construction cost is saved up. It consists of simple head race pipeline along the road.
So, considering the construction cost, ease in construction procedure and revenue generation; alternative 2 is the best option.
APPENDIX B
(Hydrological Calculations)
B. Hydrology Calculation
1000.00
WECS/DHM Method of flood prediction
100.00
Q
10.00 daily
1.00
1 10 100 1000
Return Period(yrs)
Qmax=Qt{1+2(A/2.59)^(-
Cf A T Qav=Cf*A^0.8 Qt=Qav(1+0.8logT) 0.3)}
Where,
Qt is the max 24 hour flood with frequency oncein T years in cumecs and A is the basin area in sq.km
Qav is the yearly average 24-hour flood over a number of years in cumecs
Cf is the Fuller's coefficient (0.18-1.88). For Nepal Cf is taken as average i.e, 1.03
Flood prediction by Fuller's Method
400
350
300
250
200
Series1
150
100
50
0
1 10 Recurrence interval(T) 100 1000
Perpetual Snow
Area (a) 0 km2
2.98507
p 5
QT, m3/s 239 466 635 693 791 946 1018 1116
B.5 FLOOD PREDICTION BY SNYDER'S METHOD
Mean 11.26
For N=
37 Yn = 0.54138 Sn= 1.1326
Table B.5.2 Standard and Normal variate for different return periods
S.No. R. interval Yt Kt Xt
QPR=qPR*(CA*A)*R
tPR=tpr+.025(tR-tr)
tr= tpr/5.5
tpr = 0.75Ct(LLc)0.3
CA =1.09352- .6628ln(A)
L = 48.224 km
Lc = 27.145 km
Table B.5.3 Flood Flows for Different Return Period by Snyder's Method
T R QPR
2 10.75 241.060
5 14.04 314.849
10 16.22 363.704
20 18.31 410.567
50 21.02 471.226
700
600
500
400
Series1
300
200
100
0
1 10 100 1000
Recurrence interval(T)
T qr Q
2 0.597227 120.0426
5 0.750973 150.9456
10 0.893063 179.5056
20 1.062037 213.4693
50 1.33544 268.4235
Table B.7.1
250
200
150
Gumbel
100 plotted
50
0 2.33
1 10 100 1000
Maximum
Maximum Discharge Discharge
Order number
Year at the guaging site at the z=logx Tp(years)
m
m3 /s intake site
m3 /s
N= 9
mean= 1.954267185
S.D= 0.093959359
Cs(coefficent of
skewness)= 1.221563155
(Kz) xT
(T) Recurrence ZT
frequency Kz*S.D =antilogzT
interval =Zmean+Kz*S.D
factor (m3/s)
300
250
200
150 Calculated
plotted
100
50
0
1 10 100 1000
B.9 Comparison of Floods by Different Methods
5000.000
Gumbell
log pearson
wecs
fuller
500.000 M.Dickens
synder
Horton
50.000
1 10 100 1000
Return Period, T
B.10 Long Term Flow Analysis
Qmean, monthly
C*(Area of basin)A1*(Area below 5000m +1) A2 * (Moonsoon wetness index)A3
=
Powe
r area
Power of Averag
of
Mont mean e Descendin Ran %
Basin
h moonsoo Monthl g order k Exceedenc
Constant below
n ppt y Flow e
Coefficien 5000
t m+1
0.977
JAN 0.01423 7 0 2.55 40.19 1 8.33
0.976
FEB 0.01219 6 0 2.17 33.23 2 16.67
0.994
MAR 0.009988 8 0 1.96 31.28 3 25.00
1.043
APR 0.007974 5 0 2.03 13.43 4 33.33
1.089
MAY 0.008434 8 0 2.74 10.84 5 41.67
1.009
JUL 0.02123 3 0.2523 33.23 4.06 7 58.33
0.996
AUG 0.02548 3 0.2620 40.19 2.74 8 66.67
0.989
SEP 0.01677 4 0.2878 31.28 2.55 9 75.00
0.988
OCT 0.009724 0 0.2508 13.43 2.17 10 83.33
80
70
60
50
40
30
20
10
0
0 20 40 60 80 100 120
% EXCEEDENCE
Fig B.10.1 Flow Duration Curve
Average Discharge at
Average
discharge at intake in Ran
Month discharge at %Exceedence
Gauging station descending k
intake (m3/s)
(m3 /s) order
Jan 4.18 4.16 45.08 1 8.33
100
80
60
40 BAR
20
0
0 20 40 60 80 100
% Exceedence
B.10.3 COMPARISION OF FLOW DURATION BY DIFFERENT METHODS
Discharge at intake in
S.N. %Exceedence
descending order
WECS BAR
% Exceedence
Table B.11 Comparison of long term mean monthly flows by WECS and BAR method
Figure B.11 Comparision of mean monthly hydrograph by WECS and BAR method
HYDROGRAPH
50
45
40
35
30
25
20 WECS
15 BAR
10
5
0
0 1 2 3 4 5 6 7 8 9 10 11 12
Time(MONTH)
B.12 Low Flow Analysis
B.12.1 GOROSHKOV'S
METHOD
Qmin(80%)=a(A+f)n
f=5%
a= 0.0014 for winter season
n=1.27 for winter season
Qmin(80%)= 0.0014(201+5%)1.27
= 1.215456
APPENDIX C
(Pipeline Optimization)
C. Pipe optimization
Allowable hoop stress σ 1200 kgf/cm2
Modulus of elasticity of pipe material E= 2.1E+11 N/mm2
Bulk modulus of water K 2060000000 N/m2
Design life= 25 yrs
interest rate=10% 0.12
present worth series factor= 7.843139112
Gross Head(H) 136.641
Gross head H 136.641 136.641 136.641 136.641 136.641 136.641 136.641 136.641 136.641 136.641 136.641
Internal dia(m) 1.4 1.5 1.6 1.7 1.8 1.9 2 2.1 2.2 2.3 2.4
PRESSURE,(Kgf/cm2) 13.6641 13.6641 13.6641 13.6641 13.6641 13.6641 13.6641 13.6641 13.6641 13.6641 13.6641
Thickness,(m) 0.00892 0.00956 0.01020 0.01084 0.01147 0.01211 0.01275 0.01339 0.01402 0.01466 0.01530
Adopted Thickness 0.00900 0.01000 0.01100 0.01100 0.01200 0.01300 0.01300 0.01400 0.01500 0.01500 0.01600
Area(m2) 1.5386 1.76625 2.0096 2.26865 2.5434 2.83385 3.14 3.46185 3.7994 4.15265 4.5216
Gross static head (m) 136.641 136.641 136.641 136.641 136.641 136.641 136.641 136.641 136.641 136.641 136.641
Average discharge(m3/s) 8 8 8 8 8 8 8 8 8 8 8
k/D 7.14286E-05 6.66667E-05 0.0000625 5.88235E-05 5.55556E-05 5.26316E-05 0.00005 4.7619E-05 4.54545E-05 4.34783E-05 4.16667E-05
Reynold's no(VD/U) 5199532.042 4852896.573 4549590.537 4281967.564 4044080.477 3831234.136 3639672.429 3466354.695 3308793.118 3164932.547 3033060.358
Friction factor 0.012 0.013 0.013 0.014 0.014 0.014 0.015 0.015 0.015 0.016 0.013
Length(m) 4095.129 4095.129 4095.129 4095.129 4095.129 4095.129 4095.129 4095.129 4095.129 4095.129 4095.129
Velocity (m3/s) 5.199532042 4.529370134 3.98089172 3.526326229 3.145395927 2.823014627 2.547770701 2.31090313 2.10559562 1.926480681 1.769285209
Wall loss(m) 48.36712933 37.11045691 27.5643698 20.86542521 16.06108034 12.5484025 9.935521966 7.96166738 6.449594601 5.276508809 3.539128962
Total head loss (m) 48.36712933 37.11045691 27.5643698 20.86542521 16.06108034 12.5484025 9.935521966 7.96166738 6.449594601 5.276508809 3.539128962
Revenue loss,Rs 45479977.05 33096795.81 24623100.67 18662847.81 14743134.86 11799330.21 9342448.48 7486415.98 6064589.34 4961551.65 4010518.17
present worth energy , Nrs 356705786.8 259582773.7 193122403.9 146375311.6 115632457.6 92543788.28 73274123.04 58717001.95 47565417.82 38914139.77 31455051.89
Density (Kg/m3) 7850 7850 7850 7850 7850 7850 7850 7850 7850 7850 7850
Pipe Area,solid (m2) 0.019677701 0.022589198 0.025701487 0.029014569 0.032528444 0.036243113 0.040158573 0.044274827 0.048591874 0.053109713 0.057828346
Weight (Kg) 632574.383 726169.5724 826219.6023 932724.4729 1045684.184 1165098.736 1290968.129 1423292.362 1562071.436 1707305.35 1858994.105
Cost of pipe/Kg (Rs) 200 200 200 200 200 200 200 200 200 200 200
Cost of pipe,Rs 126514876.6 145233914.5 165243920.5 186544894.6 209136836.8 233019747.2 258193625.7 284658472.4 312414287.1 341461070 371798821
Total cost,Rs 483220663.4 404816688.1 358366324.4 332920206.2 324769294.5 325563535.5 331467748.8 343375474.3 359979705 380375209.8 403253872.9
60000000
PIPEOPTIMISZATION
50000000
40000000
30000000
20000000
10000000
0
1 2 (METER)
DIAMETER 3
Final Result
The economical diameter obtained from optimization is 2 m, but this diameter results velocity of 2.54m/s>2m.s
which is not allowable, so adopting diameter of pipe 2.3 m with flow velocity of 1.9m/s <2m/s, so ok.
10000000
80000000
60000000
40000000
20000000
0
1 2 (METER)
DIAMETER 3
Final Result
Diameter of each
bifurcated pipe
Adopt Diameter 1.2 m
Adopt thickness of
pipe 15mm
Length of penstock
after bifurcation 28.5 m
friction (f) 0.016
0.30988
head loss 8 m
0.61977
Total Head Loss 6 m
APPENDIX –F
(Rating curve)
FJ. Rating Curves
F.2
J.2 Rating Curve at Tailrace
732
731
730
729
728
727
726
0 200 400 600 800 1000
Discharge m3/s
900
800 F.3
J.3 Rating curve at headworks
700
600
500 Weir Flow
400 Undersluice Flow
300 Total Flow
200
100
0
-100 0 2 4 Height of 6Water (m) 8 10 12
Appendix –G
(Detail cost estimate)
G. Detailed Cost Estimate
C Desander
1 Earthwork in Excavation 22334.6
Desilting basin transition
part1 1 8.75 3.475 7.523 228.746 228.746
part2 1 8.75 5.475 8.48 406.245 406.245
part3 1 8.75 9 8.29 652.838 652.838
part4 1 8.75 16 9.8 1372 1372
Desilting basin straight part
part1 1 12.8 16.3 18 3755.52 3755.52
part2 1 12.8 16.3 18.3 3818.11 3818.11
part3 1 12.8 16.3 19 3964.16 3964.16
part4 1 12.8 16.3 19.5 4068.48 4068.48
part5 1 12.8 16.3 19.5 4068.48 4068.48
Approach Canal
1 Site clearance m2 200 95.00 19000
2 Earthwork Excavation m3 705.322358
Excavation in normal soil m3 529 115.40 61043
Excavation in rock m3 176 2351.45 414632
3 Reiforced Cement Concrete C-20 m3 283.709256 12962.22 3677501
4 Reiforcement bars kg 6638.79659 150.00 995819
5 Formworks(Plain) m2 368.822033 520.00 191787
6 Backfilling by random materials m3 70.5322358 130.21 9184
Total 5,368,967 56,515.45
Desander
1 Site clearance m2 2000 95.00 190000
2 Earthwork Excavation m3 22334.5807
Excavation in normal soil m3 16751 115.40 1932984
Excavation in boulder mixed soil m3 5584 496.41 2771772
3 Reiforced Cement Concrete C-20 m3 881.3712 12962.22 11424526
4 Reiforcement bars kg 20624.0861 150.00 3093613
5 Formworks(Plain) m2 1145.78256 520.00 595807
6 Backfilling by random materials m3 2233.45807 130.21 290818
Total 20,299,520 213,679.16
HEADRACE(PIPE)
1 Site Clearance m2 500 95.00 47,500
2 Cost of pipeline kg 1707305 200.00 341,461,000
3 Cost of anchor block
1 Earthwork excavation m3 174 300.00 52,200
2 Concrete C-25 m3 348 -
Deduction for Pipe m3 17 -
Total Concrete work 331 12,962.22 4,295,433
3 Reinforcement bars kg 2601 100.00 260,134
4 Formworks plain m2 2784 0.00 -
Total 346,116,267 3,643,329
SURGETANK
1 Connecting Pipe kg 45450 200.00 9,090,000
2 Main Pipe kg 111336 2.00 222,672
3 Site Clearance m2 1000 95.00 95,000
Total 9,407,672.00 99,028
Penstock and ANCHOR BLOCKS
1 Site Clearance m2 500 95.00 47,500
2 Cost of pipeline kg 207352 200.00 41,470,331
3 Cost of anchor block
1 Earthwork excavation m3 2628 300.00 788,400
2 Concrete C-25 m3 1296 -
Deduction for Pipe m3 10 -
Total Concrete work 1286 12,962.22 16,667,096
3 Reinforcement bars kg 10174 100.00 1,017,360
4 Formworks plain m2 600 520.00
Powerhouse
1 Site Clearance m2 399.91 95.00 37991.45
2 Earthwork Excavation works m3 2589
Excavation in normal soil m3 1942 115.40 224,056.72
Excavation in rock m3 485 2351.45 1,141,415.09
3 Plain cement concrete m3 53 12962.22 680,865.12
4 Reinforced Cement Concrete C-20 m3 1623 12962.22 21,042,345.91
5 Stone Masonary m3 410 1900.95 779,499.49
7 Plastering (20 mm in 1:4) m2 3937 180.00 708,680.52
9 Woodworks m3 2 46000.00 78,675.46
10 Formworks m2 2110 520.00 1,097,391.32
11 Reinforcement bars kg 191151 150.00 28,672,594.94
12 Enamel Paintings m2 60 300.00 18,000.00
13 Switchyard (Civil works ) L.S. 342,000.00
14 Iron works for Truss m 70 98.00 6,860.00
15 Drainage and Sewage system L.S. 300,000.00
16 Crane bracket L.S. 150,000.00
17 Electrification L.S. 150,000.00
18 Sanitary fittings for control Building L.S. 150,000.00
21 Earthing L.S. 150,000.00
22 Dewatering L.S. 300,000.00
Total 56,030,376 589,793
Tailrace Canal
1 Site Clearance m2 242.215 95 23010.425
2 Earthwork Excavation m3 629.76
Excavation in normal soil m3 472 3923.33 1853062
Excavation in rock m3 157 2351.45 370211
3 Reiforced Cement Concrete C-20 m3 300.36 12962.22 3893319
4 Reiforcement bars kg 390.4667 200 78093
5 Formworks(Plain) m2 35367.2723 520.00 18390982
Total 24,608,677 259,038.71
A Total Of Civil Works 625,990,673 6,589,375.50
ELECTROMECHANICAL COST
1 Gates, Valves, trashrack 20,000,000.00
2 Electromechanical equipments 300,000,000.00
3 33 kv transmission line and substation 15,000,000.00
B TOTAL OF ELECTROMECHANICAL COST 335,000,000.00 3,526,315.79
C TOTAL OF ADMINISTRATION COST 192,198,134.51 2,023,138.26
D GRAND TOTAL 1,153,188,807.05 12,138,829.55
Appendix-H
(Head loss Calculations)
H.HEAD LOSS CALCULATION
31 Jan 2.55 0.20 2.36 0.93 0.14 0.01 0.013 0.16 136.48 2682.68 1995913 1936036
28.25 Feb 2.17 0.20 1.98 0.78 0.10 0.01 0.009 0.11 136.53 2252.37 1527106 1481293
31 Mar 1.96 0.20 1.77 0.69 0.08 0.01 0.007 0.09 136.55 2011.24 1496364 1451473
30 Apr 2.03 0.20 1.83 0.72 0.08 0.01 0.008 0.10 136.54 2086.84 751262 751262 728724 713699
31 May 2.74 0.20 2.55 1.00 0.16 0.02 0.015 0.19 136.45 2898.97 2156837 2048995
30 Jun 10.84 2.84 8.00 3.14 1.56 0.15 0.151 1.87 134.78 8990.58 6473218 6149557
31 Jul 33.23 25.23 8.00 3.14 1.56 0.15 0.151 1.87 134.78 8990.58 6688992 6354542
31 Aug 40.19 32.19 8.00 3.14 1.56 0.15 0.151 1.87 134.78 8990.58 6688992 6354542
30 Sep 31.28 23.28 8.00 3.14 1.56 0.15 0.151 1.87 134.78 8990.58 6473218 6149557
31 Oct 13.43 5.43 8.00 3.14 1.56 0.15 0.151 1.87 134.78 8990.58 6688992 6354542
30 Nov 6.35 0.20 6.15 2.42 0.92 0.09 0.089 1.10 135.54 6950.54 5004388 4754168
31 Dec 4.06 0.20 3.86 1.52 0.36 0.04 0.035 0.44 136.21 4389.25 1632802 1632802 1583818 1551162
K arn
a li
am K
Riv
er
Do z
30°00'
30°00' Simikot
Project Area Darchula
Mugu Karnali
r
ive
aR
liy
am
Ch
Gokuleswore
Mugu Karnali River
Chainpur
Lang
Gamgodhi u Ri 29°30'
r ver
Rive
29°30'
Seti
d
Ga
iya
r
ve
Martadi
rn
Ri
Su
ga
er
an
Sina Riv
Khola
Dadeldhura Jumla
ug
Dipayal
dh
Bu
Tila River
Jugdula
Sophegabar
ad
r Manma
Sulu G
Mangalsen ve
Ri
ali
rn
d
Ka
Ga
uli
Th
29°00'
29°00' Mahendranagar
r
ve
Ri
ri
he
iB
ul
Ataria Dailekh
Th
Jajarkot
Lamki Sani Bheri River
Birendranagar
Musikot
28°30'
28°30' 83°30'
SCALE Ba
bai
-10 0 10 20 30 40 50 km Kohalpur River
82°00' 82°30' 83°00'
80°30' 81°00'
Lamahi
Location Map of Naugarh Gad Hydroelectric Project
PREPARED BY: SUBMITTED TO: PROJECT TITLE: SCALE: DRAWING TITLE: SHEET NO.
PREPARED BY: SUBMITTED TO: PROJECT TITLE: SCALE: DRAWING TITLE: SHEET NO.
You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)
PREPARED BY:
SUBMITTED TO:
PROJECT TITLE:
SCALE:
DRAWING TITLE:
SHEET NO.
You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)
w
r Flo
Rive
X
Y
X
PREPARED BY: SUBMITTED TO: PROJECT TITLE: SCALE: DRAWING TITLE:
SHEET NO.
ALL DIMENSIONS
ARE IN METRE
PREPARED BY: SUBMITTED TO: PROJECT TITLE: SCALE: DRAWING TITLE:
SHEET NO.
1.0000
R1.1511
R0.5514
2.7758
2.4000
R0.6755
1.2500
1.2500 2.4004 R0.6727
SECTION AT Y-Y
1.4500
2.0500
2.3090
Y Y
FULL SPIRAL CASING DRAFT TUBE
20.3000
CONTROL ROOM
7.5 m X 5 m
X
HATCH
TOILET
3mX5m
2mX3m
15.1500
SPIRAL CASING
9.8500
SHAFT FOR LIFT
2.5 m X 3 m
DOWN
1.0000
3.9000
X
POWER HOUSE : PLAN VIEW AT MACHINE FLOOR LEVEL
PREPARED BY: SUBMITTED TO: PROJECT TITLE: SCALE: DRAWING TITLE:
SHEET NO.
1:150 POWER HOUSE PLAN VIEW 11
PREPARED BY: SUBMITTED TO: PROJECT TITLE: SCALE: DRAWING TITLE: SHEET NO.