DIELECTRIC TESTS
WITH PD & UHF MEASUREMENT
AFTER REPLACEMENT OF Q8 FAST SPEED EARTH SWITCH AT D08 & D09 PHASE R
CONTRACT N-7733
NEW 220/33kV GRID STATION IN ZAKHER
PROCEDURE D'ESSAI
TEST PROCEDURE
Le transformateur d'essai est connect au poste blind suivant schma d'essai ci-joint.
Test transformer is connected to GIS as shown in single line diagram.
Le poste sera essay phase par phase et section par section suivant schma unifilaire ci-joint.
The complete substation is tested section by section according to attached single line diagram.
HV TEST EQUIPMENT
CONTRACT N-7733
NEW 220/33kV GRID STATION IN ZAKHER
ALL COMPARTMENTS ARE FILLED WITH SF6 GAS AT RATED SF6 PRESSURE OK
TOUS LES TRANSFORMATEURS DE TENSION SONT DEPOSES OU ISOLES AU MOYEN D'UN SECTIONNEUR
NA OK
VT'S NOT DESIGNED FOR GIS TEST VOLTAGE ARE REMOVED OR INSULATED BY OPENING OF A DISCONNECTOR
Acceptance
(Hz)
criteria
CIRCUIT APPLIED PHASE TIME PD Measurement or DATE REMARKS
SECTION VOLTAGE UHF
at
pC/dB kV
304 kV R 3 min
1 380 kV R 1 min
170 kV R 1 min 5 pC
304 kV R 3 min
2 380 kV R 1 min
170 kV R 1 min 5 pC
304 kV R 3 min
3 380 kV R 1 min
170 kV R 1 min 5 pC
304 kV R 3 min
4 380 kV R 1 min
170 kV R 1 min 5 pC
304 kV R 3 min
5 380 kV R 1 min
170 kV R 1 min 5 pC
APPLIED
TEST SECTION PHASE TIME PD MEASUREMENT HV WITHSTAND
VOLTAGE
BB2A +
D08 +
D09
380 kV R 1min 2.01pC OK
TEST EQUIPMENT :
Pr amplifier 25 dB Sensor
Calibrator
Spectrum analyzer
SENSITIVITY TEST :
UHF TESTS
PDC008-08-R PDC009-09-R
OUTAGE OF BB 1A-2A
Apparatus locked in closed position Compartment at reduced pressure SF6 (< 0,3b rel)
Appendix 2 MS 3107
Cable box connection Apparatus locked in open position Compartment opened to the atmosphere
BAY : 08+09 Comp: G4 Phase : R Earth Mandatory Compartment at nominal pressure of SF6