Professional Documents
Culture Documents
Documents.
Session 3 SEC. 40. Failure to Enter into Contract and Post Performance
Secs 37-42 Implementation and Termination of Security. If, for justifiable causes, the bidder with the Lowest Calculated
Responsive Bid or Highest Rated Responsive Bid fails, refuses or is otherwise
Contract unable to enter into contract with the Procuring Entity, or if the bidder fails
to post the required performance security within the period stipulated in the
ARTICLE XI: AWARD, IMPLEMENTATION AND TERMINATION Bidding Documents, the BAC shall disqualify the said bidder and shall
OF THE CONTRACT undertake post-qualification for the next-ranked Lowest Calculated Bid or
SEC. 37. Notice and Execution of Award. Within a period not Highest Rated Bid. This procedure shall be repeated until an award is made.
exceeding fifteen (15) calendar days from the determination and declaration However, if no award is possible, the contract shall be subjected to a new
by the BAC of the Lowest Calculated Responsive Bid or Highest Rated bidding.
Responsive Bid, and the recommendation of the award, the Head of the In the case of a failure to post the required performance security, the bid
Procuring Entity or his duly authorized representative shall approve or security shall be forfeited without prejudice to the imposition of sanctions
disapprove the said recommendation. In case of approval, the Head of the prescribed under Article XXIII .
Procuring Entity or his duly authorized representative shall immediately SEC. 41. Reservation Clause. The Head of the Agency reserves the
issue the Notice of Award to the bidder with the Lowest Calculated right to reject any and all Bids, declare a failure of bidding, or not award the
Responsive Bid or Highest Rated Responsive Bid. contract in the following situations:
Within ten (10) calendar days from receipt of the Notice of Award, the (a) If there is prima facie evidence of collusion between appropriate public
winning bidder shall formally enter into contract with the Procuring Entity. officers or employees of the Procuring Entity, or between the BAC and any of
When further approval of higher authority is required, the approving the bidders, or if the collusion is between or among the bidders themselves,
authority for the contract shall be given a maximum of twenty (20) calendar or between a bidder and a third party, including any act which restricts,
days to approve or disapprove it. suppresses or nullifies or tends to restrict, suppress or nullify competition;
In the case of government-owned and/or -controlled corporations, the (b) If the BAC is found to have failed in following the prescribed bidding
concerned board shall take action on the said recommendation within thirty procedures; or
(30) calendar days from receipt thereof. (c) For any justifiable and reasonable ground where the award of the contract
The Procuring Entity shall issue the Notice to Proceed to the winning bidder will not redound to the benefit of the government as defined in the IRR.
not later than seven (7) calendar days from the date of approval of the SEC. 42. Contract Implementation and Termination. The rules
contract by the appropriate authority. All notices called for by the terms of and guidelines for the implementation and termination of contracts awarded
the contract shall be effective only at the time of receipt thereof by the pursuant to the provisions of this Act shall be prescribed in the IRR. The
contractor. rules and guidelines shall include standard general and special conditions for
SEC. 38. Period of Action on Procurement Activities. The contracts.
procurement process from the opening of bids up to the award of contract
shall not exceed three (3) months, or a shorter period to be determined by the 1.Philippine National Railways v Kanlaon
procuring entity concerned. Without prejudice to the provisions of the
preceding section, the different procurement activities shall be completed Construction Enterprises, Co., Inc. G.R. No.
within reasonable periods to be specified in the IRR. 182967 , April 6, 2011
If no action on the contract is taken by the head of the procuring entity, or by
his duly authorized representative, or by the concerned board, in the case of
governmentowned and/or -controlled corporations, within the periods
specified in the preceding paragraph, the contract concerned shall be deemed
approved.
2.Quisumbing v Garcia , G.R. No. 175527
SEC. 39. Performance Security. Prior to the signing of the contract, December 8, 2008
the winning bidder shall, as a measure of guarantee for the faithful FACTS:
performance of and compliance with his obligations under the contract
prepared in accordance with the Bidding Documents, be required to post a Gabriel Luis Quisumbing (Quisumbing), Estrella P. Yapha, Victoria G.
Corominas, and Raul D. Bacaltos (Bacaltos), collectively petitioners, assail
the Decision of the Regional Trial Court (RTC) of Cebu City, Branch 9, in Civil The lower court was directed to admit further evidence in order to determine
Case No. CEB-31560, dated July 11, 2006, which declared that under the the nature of the questioned contracts entered into by Gov. Garcia, and the
pertinent provisions of Republic Act No. 7160 (R.A. No. 7160), or the Local existence of ordinances authorizing her acts.
Government Code, and Republic Act No. 9184 (R.A. No. 9184), or the Nonetheless, the Supreme Court laid out the framework for the lower courts
Government Procurement Reform Act, respondent Cebu Provincial Governor guidance in resolving the issue.
Gwendolyn F. Garcia (Gov. Garcia), need not secure the prior authorization
of the Sangguniang Panlalawigan before entering into contracts committing Requirement of prior authorization by the Sanggunian
the province to monetary obligations. Sec. 22(c) of R.A. No. 7160 provides:
Sec. 22. Corporate Powers.(a) Every local government unit, as a
The subject COA report stated "Several contracts in the total amount of corporation, shall have the following powers:
P102,092,841.47 were not supported with a Sangguniang Panlalawigan xxx
resolution (c) Unless otherwise provided in this Code, no contract may be entered into
by the local chief executive in behalf of the local government unit without
authorizing the Provincial Governor to enter into a contract, as required prior authorization by the sanggunian concerned. A legible copy of such
under Section 22 of R.A. No. 7160." contract shall be posted at a conspicuous place in the provincial capitol or the
Gov. Garcia sought for reconsideration from COA but without waiting for its city, municipal or barangay hall.
resolution, she instituted an action for Declaratory Relief where she alleged Prior authorization by the sanggunian concerned is required before the local
that the infrastructure contracts complied with R.A. No. 9184 bidding chief executive may enter into contracts on behalf of the local government
procedures and were entered into pursuant to the general and/or unit.
supplemental appropriation ordinances passed by the Sangguniang Gov. Garcia argued that Sections 306 and 346 of R.A. No. 7160 are the
Panlalawigan, hence a separate authority to enter into such contracts was no exceptions to Sec. 22(c) and operate to allow her to enter into contracts on
longer necessary. behalf of the Province of Cebu without further authority from the
The trial court declared that Gov. Garcia need not secure prior authorization Sangguniang Panlalawigan.
from the Sangguniang Panlalawigan . It further declared that the However, the Court noted that Sec. 306 of R.A. No. 7160 merely contains a
Sangguniang Panlalawigan does not have juridical personality nor is it vested definition of terms. Read in conjunction with Sec. 346, Sec. 306 authorizes
by R.A. No. 7160 with authority to sue and be sued. It also ruled that it is only the local chief executive to make disbursements of funds in accordance with
when the contract (entered into by the local chief executive) involves the ordinance authorizing the annual or supplemental appropriations. The
obligations which are not backed by prior ordinances that the prior authority "ordinance" referred to in Sec. 346 pertains to that which enacts the local
of the sanggunian concerned is required. government units budget, for which reason no further authorization from the
Petitioners insisted that prior authorization from the Sangguniang local council is required, the ordinance functioning, as it does, as the
Panlalawiganshould be secured before Gov. Garcia could validly enter into legislative authorization of the budget.
contracts involving monetary obligations. To construe Sections 306 and 346 of R.A. No. 7160 as exceptions to Sec. 22(c)
The Province of Cebu was operating under a reenacted budget in 2004. Gov. would render the requirement of prior sanggunian authorization superfluous,
Garcia useless and
entered into contracts on behalf of the province while this reenacted budget irrelevant. There would be no instance when such prior authorization would
was in force. be required. Yet, this is obviously not the effect Congress had in mind when it
required the prior authorization of the sanggunian concerned.
ISSUE: Sec. 323 of R.A. No. 7160 provides that in case of a reenacted budget, "only
the annual appropriations for salaries and wages of existing positions,
Whether or not prior approval by the Sangguniang Panlalawigan is required statutory and contractual obligations, and essential operating expenses
before Gov. Garcia could have validly entered into the questioned contracts. authorized in the annual and supplemental budgets for the preceding year
shall be deemed reenacted and disbursement of funds shall be in accordance
RULING: therewith."
As indicated by the word "only" preceding the above enumeration, the items
The Court held that the case should be remanded to the lower court and for which disbursements may be made under a reenacted budget are
treated as an ordinary civil action rather than as a declaratory relief action. exclusive. Clearly, contractual obligations which were not included in the
previous years annual and supplemental budgets cannot be disbursed by the
local government unit. New contracts entered into by the local chief executive the appropriation ordinance nor encompassed within the regular personal
require the prior approval of the sanggunian. services and maintenance operating expenses
To give life to the intendment of the law and to avoid a construction which
would render Sec. 22(c) of R.A. No. 7160 meaningless, disbursement should
be understood to pertain to payments for statutory and contractual 3.Melchor v COA G.R. No. 84202,
obligations which the sanggunian has already authorized thru ordinances
enacting the annual budget and are therefore already subsisting obligations November 22, 1988
of the local government unit. Contracts are those which bind the local
government unit to new obligations for which the local chief executive needs
prior authority from the sanggunian.
Following are other provisions of R.A. No. 7160 which support petitioners 4.Vigilar v Aquino, G.R. No. 180388,
stand: (a) Sec. 465, Art. 1, Chapter 3 states that the provincial governor shall
"[r]epresent the province in all its business transactions and sign in its behalf
January 18, 2011
all bonds, contracts, and obligations, and such other documents upon Facts:
authority of theSangguniang Panlalawigan or pursuant to law or ordinances;"
(b) Sec. 468, Art. 3 also establishes the sanggunians power, as the provinces On 19 June 1992, petitioner Angelito M. Twao, then OfficerinCharge (OIC)-
legislative body, to authorize the provincial governor to negotiate and District Engineer of the Department of Public Works and Highways (DPWH)
contract loans, lease public buildings held in a proprietary capacity to private 2nd Engineering District of Pampanga sent an Invitation to Bid to
parties, among other things. respondent Arnulfo D. Aquino, the owner of A.D. Aquino Construction and
What the trial court should have done Supplies.
As things stand, the declaration of the trial court to the effect that no prior
authorization is required when there is a prior appropriation ordinance The bidding was for the construction of a dike by bulldozing a part of the
enacted does not put the controversy to rest. The question which should have
Porac River at Barangay AscomoPulungmasle, Guagua, Pampanga.
been answered by the trial court was whether, during the period in question,
there did exist ordinances (authorizing Gov. Garcia to enter into the
questioned contracts) which rendered the obtention of another authorization Subsequently, on 7 July 1992, the project was awarded to respondent, and a
from the Sangguniang Panlalawigan superfluous. It should also have "Contract of Agreement" was thereafter executed between him and concerned
determined the character of the questioned contracts, i.e., whether they were, petitioners for the amount of PhP1,873,790.69, to cover the project cost.
as Gov. Garcia claims, mere disbursements pursuant to the ordinances
supposedly passed by the sanggunian or, as petitioners claim, new contracts By 9 July 1992, the project was duly completed by respondent, who was then
which obligate the province without the provincial boards authority. issued a Certificate of Project Completion dated 16 July 1992.
Resort to appropriation ordinance is necessary
The question of whether a sanggunian authorization separate from the
appropriation ordinance is required should be resolved depending on the The certificate was signed by Romeo M. Yumul, the Project Engineer; as well
particular circumstances of the case. Should the appropriation ordinance, for as petitioner Romeo N. Supan, Chief of the Construction Section, and by
instance, already contain in sufficient detail the project and cost of a capital petitioner Twao.
outlay such that all that the local chief executive needs to do after undergoing
the requisite public bidding is to execute the contract, no further Respondent Aquino, however, claimed that PhP1,262,696.20 was still due
authorization is required, the appropriation ordinance already being him, but petitioners refused to pay the amount.
sufficient.
On the other hand, should the appropriation ordinance describe the
3
projects in generic terms such as "infrastructure projects," "inter-municipal He thus filed a Complaint for the collection of sum of money with damages
waterworks, drainage and sewerage, flood control, and irrigation systems before the Regional Trial Court of Guagua, Pampanga.
projects," "reclamation projects" or "roads and bridges," there is an obvious
need for a covering contract for every specific project that in turn requires :
approval by thesanggunian. Specificsanggunianapproval may also be Petitioners defense
required for the purchase of goods and services which are neither specified in
that the Complaint was a suit against the state; meruit basis, the total obligation due to the plaintiffappellee for his
undertaking in implementing the subject contract of public works, and to
that respondent failed to exhaust administrative remedies; and that the allow payment thereof, subject to COA Rules and Regulations, upon the
"Contract of Agreement" covering the project was void for violating completion of the said determination.
Presidential Decree No. 1445, absent the proper appropriation and the
Certificate of Availability of Funds. No pronouncement as to costs.
petitioners claim that the Complaint filed by respondent before the Regional Issue:
Trial Court was done without exhausting administrative remedies.
Petitioners aver that respondent should have first filed a claim before the 1. When the "Contract of Agreement" covering the project is void, should the
Commission on Audit (COA) before going to the courts. contractor who completed the project be paid? How?
Department of Public Works and Highways is hereby ordered to pay the SC Ruling:
plaintiff Arnulfo D. Aquino the following:
conforms to the entire contract amount. The contractor should be duly compensated for services rendered, which
were for the benefit of the general public. To deny the payment to the
On appeal, the Court of Appeals reversed and set aside the Decision of the contractor of the two buildings which are almost fully completed and
lower court and disposed as follows: presently occupied by the university would be to allow the government to
unjustly enrich itself at the expense of another. Justice and equity demand
Appeal is GRANTED. The "CONTRACT AGREEMENT" entered into between compensation on the basis of quantum meruit.
the plaintiffappellees construction company, which he represented, and the
government, through the Department of Public Works and Highway (DPWH) Under these circumstances, respondent may not validly invoke the Royal
Pampanga 2nd Engineering District, is declared null and void ab initio. Prerogative of Dishonesty and conveniently hide under the State's cloak of
invincibility against suit, considering that this principle yields to certain
In line with the pronouncement in Department of Health vs. C.V. settled exceptions. True enough, the rule, in any case, is not absolute
7 for it does not say that the state may not be sued under any
Canchela & Associates, Architects, the Commission on Audit (COA) is
hereby ordered to determine and ascertain with dispatch, on a quantum circumstance.
To be sure, this Court as the staunch guardian of the citizens' difference arises as to what the law is on a certain state of facts, and not as to
rights and welfare cannot sanction an injustice so patent on its the truth or the falsehood of alleged facts. Said question at best could be
face, and allow itself to be an instrument in the perpetration resolved only tentatively by the administrative authorities. The final decision
thereof. Justice and equity sternly demand that the State's cloak of on the matter rests not with them but with the courts of justice. Exhaustion of
invincibility against suit be shred in this particular instance, and administrative remedies does not apply, because nothing of an administrative
that petitionerscontractors be duly compensated on the basis of nature is to be or can be done. The issue does not require technical
quantum meruit for construction done on the public works knowledge and experience but one that would involve the interpretation and
housing project. application of law.
9.Luspo v People of the Philippines GR 3. The checks were all dated August 12, 1992 and payable respectively to DI-
188487, Feb 14, 2011 BEN Trading,
G.R. No. 188556 February 14, 2011 MT Enterprises, J-MOS Enterprises, and Triple 888 Enterprises, each to
J. Nachura receive 25 checks.
Sec. 65 Penal Clause All enterprises were owned and operated by Margarita Tugaoen
(TUGAOEN), who collected the proceeds of the checks from the United
DOCTRINES: Coconut Planters Bank (UCPB), Cubao Branch, on August 12, 13, and 14,
Splitting, defined: 1992.
As defined in COA Circular No. 76-41 dated July 30, 1976, splitting,
in its literal sense, means dividing or breaking up into separate parts or 4. In a sworn statement dated March 5, 1993 taken by Insp. Felicidad
portions, or an act resulting in fissure, rupture, or breach. Within the sphere Ramos, a member of the investigating committee, Tugaoen admitted that
of government procurement, splitting is associated with requisitions, she did not deliver any CCIE in exchange for the P10 million
purchase orders, deliveries, and payments. One form of splitting is the worth of checks, because the amount was allegedly intended as
breaking up of payments which consist in making two or more payments for payment for the previously accumulated debts of the PNP.
one or more items involving one purchase order. Splitting is intended to do
away with and circumvent control measure, such as the reviewing authority 5. The nondelivery was confirmed by P/CInsp. Isaias Braga (Braga), Chief
of a superior official. In this case, the ASA of P10,000,000.00 was split by Logistics Officer, North CAPCOM, and Rolando Flores, Supply
Duran and Montano into 100 checks of P100,000.00 each to elude the Accountable Officer, North CAPCOM. Both declared that, while they
reviewing authority of Director Sistoza, Regional Director, North CAPCOM. received CCIE in 1992, the same came from the PNP Logistics Command
and NOT from Tugaoen, and that the value of the items they received was
Penal and Civil Liability for Violation of Section 3(e), R.A. No. just P5,900,778.80 and had no relation at all to the P10 million CCIE
3019 purchase under investigation. Their statements were corroborated by
The penalty for violation of Section 3(e) of R.A. No. 3019 is P/Supt. Jesus Arceo, Chief of the Supply Center of PNP Logistics
"imprisonment for not less than six years and one month nor more than Command.
fifteen years, and perpetual disqualification from public office.
ISSUE:
FACTS: Whether the petitioners are liable for violation of Section 3(e) of RA
This case is about the ghost purchase of the combat, clothing, and 3019, the Anti-Graft and Corrupt Practices Act?
individual equipment (CCIE) in Regions 7 and 9 and North Capital
Command (CAPCOM) of Philippine National Police (PNP).
1. The investigation report disclosed that, on August 11, 1992, the Office of RULING:
the Directorate for Comptrollership (ODC) issued two (2) Advices of Sub- 1. Yes with respect to MONTANO, DURAN, and TUGAOEN. These three
Allotment (ASAs), each amounting to P5 million, purportedly for the are found guilty beyond reasonable doubt for violation of Section 3(e) of
purchase of CCIE for the North CAPCOM. The ASAs were approvedfor RA 3019, the Anti-Graft and Corrupt Practices Act and are ORDERED to
the chief Director General Nazareno by Director Guillermo Domondon solidarily indemnify the PNP of P10 million.
(Domondon), Chief Director of ODC, and signed for him by Police 2. No with respect to LUSPO. He is hereby acquitted.
RATIO: Evident bad faith and manifest partiality are imputed to Luspo,
1. MONTANO, DURAN, and TUGAOENare found GUILTY of Duran, and Montano when they caused the preparation, issuance, release,
violation of Section 3(e) of RA 3019. and payment of P10,000,000.00, without supporting documents, to DI-BEN
In Cabrera v. Sandiganbayan (2004), the Court explained that Trading, MT Enterprises, J-MOS Enterprises, and Triple 888 Enterprises, all
there are two ways for a public official to violate this provision in the owned and operated by Tugaoen.
performance of his functions, namely: (a) by causing undue injury to any
party, including the government; or (b) by giving any private party any 3rdelement:
unwarranted benefits, advantage, or preference. In that case, the Court The last essential element of the offense, damage or injury to the
enumerated the essential elements of the offense, viz.: government, is amply substantiated by the certification executed by Romulo
1. The accused must be a public officer discharging administrative, judicial, or Tuscano of the PNP Logistic Support Service, indicating that there is NO
official functions; available record regarding the DELIVERY OF P10 MILLION WORTH OF
2. He must have acted with manifest partiality, evident bad faith, or gross CCIE for North CAPCOM in 1992.
inexcusable negligence; and In fact, Tugaoen herself admitted that she did not deliver any CCIE in
3. His action caused undue injury to any party, including the government, exchange for her receipt of P10 million.
or gave any private party unwarranted benefits, advantage, or preference in
the discharge of his functions.
2. LUSPO is ACQUITTED.
1st element: Luspo, in the same manner as Domondon, had satisfactorily adduced
Montano is the Chief Comptroller, North CAPCOM while is the Chief, evidence of good faith to overturn and repudiate the imputation of evident
Regional Finance Service Unit, North CAPCOM. bad faith against him. He committed no prohibited act in signing and issuing
On the other hand, the indictment against Tugaoen, a private the assailed ASAs because there is ample documentary and testimonial
individual, is sanctioned by Section 1 of R.A. No. 3019, thus: evidence showing that:
Section 1. Statement of policy. It is the policy of the Philippine (1) Luspo was duly authorized by Domondon to release personal services
Government, in line with the principle that a public office is funds by signing ASAs in the latters behalf, which is merely a ministerial
a public trust, to repress certain acts of public officers duty. Luspos signature in the ASAs is attributable to Domondon who, in
and private persons alike which constitute graft or turn, was authorized by Nazareno to release funds for personnel services
corrupt practices or which may lead thereto. through the issuance of an ASA.
2nd element: (2) Contrary to the prosecutions contention, the issuance of ASAs by the
In the recent Albert v. Sandiganbayan (2009), we reiterated the ODC in favor of PNP regional commands did not have to be preceded by
definitions of such modalities, viz.: a program request from the Office of the Directorate for Personnel as
There is manifest partiality when there is a shown in the Delegation of Authority and its Schedule of Delegation issued by
clear, notorious, or plain inclination or predilection to favor Nazareno on March 20, 1992; and
one side or person rather than another. "Evident bad (3) There is no need for the DBMs prior authority before the ODC can
faith" connotes not only bad judgment but also palpably release funds for personnel services 01, under which CCIE are categorized, as
and patently fraudulent and dishonest purpose to do moral shown by GHQ Circular No. 8, dated 1985.
obliquity or conscious wrongdoing for some perverse
motive or ill will. "Evident bad faith" contemplates a state
of mind affirmatively operating with furtive design or with
some motive or self-interest or ill will or for ulterior 10.Office of the President v Cataquiz GR
purposes. "Gross inexcusable negligence" refers to
negligence characterized by the want of even the slightest 183445, Sept 14, 2011
care, acting or omitting to act in a situation where there is Jessie D. Tolentino
a duty to act, not inadvertently but willfully and 11385146
intentionally, with conscious indifference to consequences
insofar as other persons may be affected. Office of the President and Presidential Anti-Graft Commission
vs. CalixtoCataquiz
Issue: WON Board Resolution No. 28 which requires public bidding of the
Doctrine: remaining free fishpen areas in Laguna de Bay is valid even without the
Board Resolution No. 28 simply set forth the guidelines for the public approval of the President.
bidding of the remaining free fishpen areas in Laguna de Bay. It did not
require presidential approval because it did not regulate any fisheries
development activities. Hence, the questioned resolution cannot be declared Ruling:
invalid on the basis of the CAs ratiocination that the resolution lacked the Yes. A careful perusal of the PAGCs discussion on the violation of the
approval of the President. questioned board resolution discloses that PAGC was undoubtedly referring
to Board Resolution No. 28 which approved the policy guidelines for public
Facts: bidding of the remaining free fishpen areas in Laguna de Bay, and not
Respondent Cataquiz, then General Manager of the Laguna Lake Resolution No. 68 which had nothing at all to do with fishpen awards.
Development Authority, was being ousted in a petition by a majority of the Therefore, the reference to Board Resolution No. 68, instead of Board
members of the Management Committee and the rank and file employees of Resolution No. 28, in the PAGC Resolution is unmistakably a typographical
the Laguna Lake Development Authority (LLDA), on the grounds of corrupt error on the part of PAGC but, nonetheless, rectifiable.
and unprofessional behavior and management incompetence.
Moreover, the respondents counter-affidavit shows that he had knowledge of
In an investigation into the allegations against Cataquiz ordered by Secretary the fact that he was being charged with violation of Board Resolution No. 28.
Gozunof the DENR, it was determined that respondent may be found guilty He even argued that the said resolution was an invalid and illegal
for acts prejudicial to the best interest of the government and for violations of administrative rule. His position was that the resolution issued by the Board
several pertinent laws and regulations specifically the Board Resolution No. of Directors of LLDA was an unreasonable exercise of its legislative power
28 which requires public bidding of the remaining free fish pen areas in because the enabling law of LLDA, R.A. No. 4850, did not require the public
Laguna de Bay. It was recommended that the case be forwarded to the bidding of free fishpen areas. Then, in his motion for reconsideration before
Presidential Anti-Graft Commission. the OP, he argued that the resolution was invalid because it was never
approved by the President, contrary to Section 4(k) of R.A. No. 4850.
Later, a duly organized employees union of the LLDA, CELLDA, filed a
complaint before the PAGC charging Cataquiz with violations of RA 3019 The Revised Laguna de Bay Zoning and Management Plan allocated 10,000
(The Anti-Graft and Corrupt Practices Act), The Administrative Code and The hectares of the lake surface areas for fishpen operators. In the event that the
Code of Conduct and Ethical Standards for Public Officials and Employees. area would not be fully occupied after all qualified operators had been
assigned their respective fishpen areas, the residual free areas would be
The Office of the President adopted the findings and recommendations of opened for bidding to other prospective qualified applicants. Accordingly,
PAGC, and dismissed the respondent from service. The decision was Board Resolution No. 28 simply set forth the guidelines for the public
amended by the OP imposing the penalties of disqualification from re- bidding of the remaining free fishpen areas in Laguna de Bay. It did not
employment and forfeiture of retirement benefits because the penalty of require presidential approval because it did not regulate any fisheries
dismissal was no longer available to him because of his replacement as development activities. Hence, the questioned resolution cannot be declared
General Manager of LLDA. invalid on the basis of the CAs ratiocination that the resolution lacked the
approval of the President.
The Court of Appeals reversed the decision. Meanwhile, the Office of the
Ombudsman recommended the dismissal of the charges against respondent The petition is granted.
for violation of RA No. 3019.
Sec. 67-68 Civil Liabilities W/N the imposition of the 2% interest of the amount adjudged in
ARTICLE XXII CIVIL LIABILITY favor of Consunji is proper
SEC. 67. Civil Liability in Case of Conviction. Without prejudice to
administrative sanctions that may be imposed in proper cases, a conviction Held:
under this Act or Republic Act No. 3019 shall carry with it civil liability,
which may either consist of restitution for the damage done or the forfeiture Yes. The Court in its decision cited as primary basis the
in favor of the government of any unwarranted benefit derived from the act
agreement/contract of the parties. It must be noted that the
or acts in question or both, at the discretion of the courts.
SEC. 68. Liquidated Damages. All contracts executed in accordance agreement provided Consunjitwo options in case of delay in monthly
with this Act shall contain a provision on liquidated damages which shall be payments, to wit: a) suspend work on the project until payment is
payable in case of breach thereof. The amount thereof shall be specified in remitted by the owner or b) continue the work but the owner shall be
the IRR.
required to pay interest at a rate of two percent (2%) per month or a
fraction thereof. Evidently, Consunji chose the latter option, as the
11.Arwood Industries Inc. v Consunji
condominium project was in fact already completed.
Arwood Industries Inc. v DM Consunji, Inc. GR 142277, Dec
Moreover, as to Arwoods contention that the amount claimed does
11, 2002
not refer to monthly progress billings. The Court pointed out that it
(Arwood) did not provide an answer on what the amount represented.
This left the Courtwith no choice but to agree with Consunji that the
Facts: phrase "monthly progress billings" refers to a portion of the contract
price payable by Arwoodto Consunjibased on the percentage of
Petitioner Arwood Industries Inc. (Arwood) and respondent DM
completion of the project or on work accomplished at a particular
Consunji (Consunji) entered into a contract of Civil, Structural and
stage. It refers to that portion of the contract price still to be paid as
Architectural Works Agreement (Agreement) for the construction of
work progresses, after the downpayment is made.
Arwoods condominium project. The contract price aggregated for
20,800,000 php. Despite the completion of the condominium project, As a final point, the Court also explained that even if there was a
the amount of P962,434.78 remained unpaid by Arwood. Repeated default of stipulation or agreement on interest, respondent may still
demands by Consunji for Arwood to pay went unheeded. recover on the basis of the general provision of law, which is Article
2209 of the Civil Code. The provision provides that the payment of
Thus, Consunji filed its complaint for the balance of the contract price
penalty interest is in the rate agreed upon or if there was no
and for damages against Arwoodwith interest of 2% per month or a
agreement on the regular interest, then payment would consist of legal
fraction thereof, from November 1990 up to the time of payment.
interest or six percent (6%) per annum.
The lower court sided with Consunji. The Court of Appeals upheld the
lower courts decision but deleted the attorneys fees saying that the
same had no basis since it was not mentioned in the body of the
decision.
Issue: