You are on page 1of 1

PROJECT ORGANIZATION CHART BY AREA

QTY OF
Plan for Supervisor REMARKS ORGANIZATION CHART
PROJECT

PROJECT
Sharing supervisor 1. Total NOS of supervisor require is 6 peoples
Supv-01 RAPID
- AO Line Replacement Project
- Schenck Weight Feeder Control System Upgrade PHASE
#2

Supv-02 BLACK END WHITE END


NTUT

AREA CATEGORY
- Zirconium (BE) (WE)
- Cooler Tubesheet
9
Supv-03
- Centrifuge
- Schenck Weight Feeder CRITICA CRITICA
- AO Line NORMAL / L NORMAL / NORMAL /
L
MAJOR WORK MAJOR WORK MAJOR WORK

Dedicated suoervisor Compressor Air Drier Replacement Project


Dump Conveyor - Supv-04 1. 8 Tie-in points & can be manageable 1. TK-417 : 1. TK-401 :
Air Drier Compressor - Supv-05 REPLACE COMPRESSOR
Dump Conveyor Structure Replacement, Phase #2 CALCINER AIR DRIER

NORMAL HOUR
1. Manageable but a lot of work COOLER TUBE REPLACEMENT
SHEET PROJECT
Replace Calciner Cooler Tubesheet (Emergent) (EMERGENT)
1. Manageable. 2. TK-433 :
2. Constraint for WE start-up. 3 DUMP
CONVENYOR
STRUCTURE
REPLACEMENT,
PHASE #2

Centrifuge No.2 Work


1. Manageable 1. TK-414 :
1. CENTRIFUGE 1. TK-354 :
NO.2 WORK SCHENCK ZIRCONIUM

EXTENDED HOUR
New Precipitation Tank No 2 TANK
WEIGHT FEEDER
1. 24 Hours just for brick installation REPLACEMENT
2. TK-383 : CONTROL
2. Other works will be extended hours PROJECT
NEW SYSTEM
PRECIPITATION UPGRADE PHASE
Zirconium Tank Replacement Project
TANK NO.2 #2
1. TR92 can't be produced if zirconium tank delay 4
2. Critical Lifting

Schenck Weight Feeder Control System Upgrade PHASE #2


1. Ball mill will be critical project since it is single stream line.

Dedicated suoervisor AO Line Replacement Project


Boiler Feed Water - Supv-06 1. No risk interm of schedule (manageable)
1. TK-422 : 1. TK-396 :
2. Standby unit for dispersal switching train (supply acid ore to reactor
AO LINE BOILER FEED
for further reaction)
REPLACEMENT WATER PIPELINE
PROJECT & VALVE
Boiler Feed Water Pipeline & Valve Replacement Project
REPLACEMENT
2 SHIFT

1. Time constraint & area conjusted.


PROJECT
2. Application line for boiler start-up.
3. A lot of installation piping work. 2

BE NORMAL / MAJOR BE CRITICAL WE NORMAL NTUT NORMAL / MAJOR NTUT CRITICAL


QTY PROJECT PER CONDITION
3 1 2 2 1

QTY PROJECT PER AREA 4 2 3

TOTAL 9

You might also like