You are on page 1of 1986

CHAPTER NO.

BRICK WORK
DESCRIPTION OF ITEM:

Item No. 1 Pucca brick work in mud mortar in building.

(i) In foundation and plinth.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Good earth or stiff clay for mud master 35.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 1.50 Nos. per day


2 Coolies unskilled 2.00 Nos. per day
3 Bahishti 0.13 No per day

For Mud Mortar

1 Cooly unskilled 0.67 No. per day


2 Bahishty 0.33 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate per 100 Cft Rs. Say
Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 1
DESCRIPTION OF ITEM:

Item No. 1 Pucca brick work in mud mortar in building.

(ii) In ground floor.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Good earth or stiff clay for mud master 35.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 3.00 Nos. per day
3 Bahishti 0.13 No. per day

For Mud Mortar

1 Cooly unskilled 0.67 No. per day


2 Bahishty 0.33 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 2
DESCRIPTION OF ITEM:

Item No. 2 Add extra labour in item No.1 for brick work in

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft


First Floor

1 Mason 0.25 No. per day


2 Cooly unskilled 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate per 100 Cft
Say
Labour rate per Cum
Say
LABOUR for 125 Cft
Second Floor

1 Masons 0.75 No. per day


2 Coolies unskilled 2.00 Nos. per day
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft
Say
Labour rate per Cum
Say

Page 3
Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft


Third Floor

1 Masons 1.25 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate per 100 Cft
Say
Labour rate per Cum
Say
LABOUR for 125 Cft
4th & Subsequent Floor

1 Masons 2.25 Nos. per day


2 Coolies unskilled 4.50 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per cum Rs. Say

Page 4
DESCRIPTION OF ITEM:

Item No. 3 Pucca brick work in mud mortar other than building.

(i) Upto 20 ft. (6 metre) high.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Good earth or stiff clay 35.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Mud Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.33 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 5
DESCRIPTION OF ITEM:

Item No. 3 Pucca brick work in mud morter other than building:

(ii) Extra labour for every 5.0' (1.5 metre) additional height
thereof.

Detail Unit Rate (British System) per 100 Cft


Rate
Qty Per Unit Amount (Rs.)

LABOUR for 125 Cft

1 Mason 0.25 No. per day


2 Cooly unskilled 1.00 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Page 6
DESCRIPTION OF ITEM:

Item No. 4 (i) Pucca brick work in foundation & plinth in

Cement sand mortar Ratio (1:2).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 8.00 bags per bag
3 Sand 20.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

LABOUR for 125 Cft


For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 7
DESCRIPTION OF ITEM:

Item No. 4 (i) Pucca brick work in foundation & plinth in:

Cement sand mortar Ratio (1:3).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 6.00 bags per bags
3 Sand 22.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

LABOUR for 125 Cft


For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 8
DESCRIPTION OF ITEM:

Item No. 4 (i) Pucca brick work in foundation & plinth in:

Cement sand mortar Ratio (1:4).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 4.80 bags per bag
3 Sand 24.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 9
DESCRIPTION OF ITEM:

Item No. 4 (i) Pucca brick work in foundation & plinth in:

Cement sand mortar Ratio (1:5).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 4.00 bags per bag
3 Sand 25.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 10
DESCRIPTION OF ITEM:

Item No. 4 (i) Pucca brick work in foundation & plinth in

Cement sand mortar Ratio (1:6).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 3.40 bags per bag
3 Sand 25.70 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

LABOUR for 125 Cft


For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 11
DESCRIPTION OF ITEM:

Item No. 4 (i) Pucca brick work in foundation & plinth in

Cement sand mortar Ratio (1:7).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 3.00 bags per bag
3 Sand 26.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

LABOUR for 125 Cft


For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 12
DESCRIPTION OF ITEM:

Item No. 4 (i) Pucca brick work in foundation & plinth in

Cement sand mortar Ratio (1:8).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 2.66 bags per bag
3 Sand 26.67 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 13
DESCRIPTION OF ITEM:

Item No. 4 (ii) Pucca brick work in foundation & plinth in

Lime cement sand mortar Ratio (1:1:6).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 3.20 bags per bag
3 Slaked lime 59.72 kg per kg
4 Sand 24.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs.

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 14
DESCRIPTION OF ITEM:

Item No. 4 (ii) Pucca brick work in foundation & plinth in:

Lime cement sand mortar Ratio (1:1:7).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 2.85 bags per bag
3 Slaked lime 53.00 kg per kg
4 Sand 24.78 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 15
DESCRIPTION OF ITEM:

Item No. 4 (ii) Pucca brick work in foundation & plinth in

Lime cement sand mortar Ratio (1:1:8).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 2.56 bags per bag
3 Slaked lime 47.78 kg per kg
4 Sand 25.60 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 16
DESCRIPTION OF ITEM:

Item No. 4 (ii) Pucca brick work in foundation & plinth in

Lime cement sand mortar Ratio (1:1:9).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 2.32 bags per bag
3 Slaked lime 43.30 kg per kg
4 Sand 26.20 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs.

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 17
DESCRIPTION OF ITEM:

Item No. 4 (ii) Pucca brick work in foundation & plinth in

Lime cement sand mortar Ratio (1:1:10).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 2.14 bags per bag
3 Slaked lime 39.94 kg per kg
4 Sand 26.66 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 18
DESCRIPTION OF ITEM:

Item No. 4 (iii) Lime, sand mortar Ratio (1:2).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL
1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.
2 Lime Slaked 174.30 Kg. Per Kg.
3 Sand 23.33 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate per 100 Cft Rs. Say
Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 19
DESCRIPTION OF ITEM:

Item No. 5 (i) Pacca brick work in ground floor (including striking of jo

Cement sand mortar Ratio (1:2).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 8.00 bags per bag
3 Sand 20.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 20
DESCRIPTION OF ITEM:

Item No. 5 (i) Pacca brick work in ground floor (including striking of jo

Cement sand mortar Ratio (1:3).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 6.00 bags per bag
3 Sand 22.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 21
DESCRIPTION OF ITEM:

Item No. 5 (i) Pacca brick work in ground floor (including striking of jo

Cement sand mortar Ratio (1:4).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 4.80 bags per bag
3 Sand 24.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 22
DESCRIPTION OF ITEM:

Item No. 5 (i) Pacca brick work in ground floor (including striking of jo

Cement sand mortar Ratio (1:5).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 4.00 bags per bag
3 Sand 25.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 23
DESCRIPTION OF ITEM:

Item No. 5 (i) Pacca brick work in ground floor (including striking of jo

Cement sand mortar Ratio (1:6).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 3.40 bags per bag
3 Sand 25.70 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 24
DESCRIPTION OF ITEM:

Item No. 5 (i) Pacca brick work in ground floor (including striking of jo

Cement sand mortar Ratio (1:7).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 3.00 bags per bag
3 Sand 26.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 25
DESCRIPTION OF ITEM:

Item No. 5 (i) Pacca brick work in ground floor (including striking of jo

Cement sand mortar Ratio (1 : 8).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 2.66 bags per bag
3 Sand 26.57 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 26
DESCRIPTION OF ITEM:

Item No. 5 (ii) Lime cement sand mortar Ratio (1:1:6).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 59.72 kg per kg
3 Cement 3.20 bags per bag
4 Sand 24.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 27
DESCRIPTION OF ITEM:

Item No. 5 (ii) Lime cement sand mortar Ratio (1 : 1 : 7).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 53.37 kg per kg
3 Cement 2.85 bags per bag
4 Sand 24.78 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 28
DESCRIPTION OF ITEM:

Item No. 5 (ii) Lime cement sand mortar Ratio (1:1:8).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 47.78 kg per kg
3 Cement 2.56 bags per bag
4 Sand 25.60 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 29
DESCRIPTION OF ITEM:

Item No. 5 (ii) Lime cement sand mortar Ratio ( 1 : 1 : 9 ).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 43.30 kg per kg
3 Cement 2.32 bags per bag
4 Sand 26.20 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 30
DESCRIPTION OF ITEM:

Item No. 5 (ii) Lime cement sand mortar Ratio ( 1 : 1 : 10 ).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 40.00 kg per kg
3 Cement 2.14 bags per bag
4 Sand 26.66 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 31
DESCRIPTION OF ITEM:

Item No. 5 (iii) Lime sand mortar Ratio (1:2).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Lime 174.30 kg per kg
3 Sand 23.33 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 32
DESCRIPTION OF ITEM:

Item No. 6 Add extra labour in item No.5 for brick work in:-

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft


First Floor

1 Mason 0.25 No. per day


2 Cooly unskilled 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate per 100 Cft Rs.
Say
Labour rate per Cum Rs.
Say

LABOUR for 125 Cft


Second Floor

1 Masons 0.75 No. per day


2 Coolies unskilled 2.00 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate per 100 Cft Rs.
Say
Labour rate per Cum Rs.
Say

Page 33
Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft


Third Floor

1 Masons 1.25 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate per 100 Cft
Say
Labour rate per Cum
Say
LABOUR for 125 Cft
4th & Subsequent Floor

1 Masons 2.25 Nos. per day


2 Coolies unskilled 4.50 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per cum Rs. Say

Page 34
DESCRIPTION OF ITEM:

Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Cement sand mortar Ratio (1:2).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 8.00 bags per bag
3 Sand 20.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 35
Item No. 7 Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Cement sand mortar Ratio (1:3).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 6.00 bags per bag
3 Sand 22.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 36
DESCRIPTION OF ITEM:

Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Cement sand mortar Ratio (1 : 4).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 4.80 bags per bag
3 Sand 24.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 37
DESCRIPTION OF ITEM:

Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Cement sand mortar Ratio (1 : 5).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 4.00 bags per bag
3 Sand 25.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 38
DESCRIPTION OF ITEM:

Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Cement sand mortar Ratio (1 : 6).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 3.40 bags per bag
3 Sand 25.70 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 39
DESCRIPTION OF ITEM:

Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Cement sand mortar Ratio (1 : 7).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 3.00 bags per bag
3 Sand 26.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 40
DESCRIPTION OF ITEM:

Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Cement sand mortar Ratio (1 : 8).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 2.66 bags per bag
3 Sand 26.67 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 41
DESCRIPTION OF ITEM:

Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Lime, cement, sand mortar Ratio (1 : 1 : 6).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 59.72 kg per kg
3 Cement 3.20 bags per bag
4 Sand 24.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 42
DESCRIPTION OF ITEM:

Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Lime, cement, sand mortar Ratio (1 : 1 : 7).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 53.00 kg per kg
3 Cement 2.85 bags per bag
4 Sand 24.78 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 43
DESCRIPTION OF ITEM:

Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Lime, cement, sand mortar Ratio (1 : 1 : 8).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 47.78 kg per kg
3 Cement 2.56 bags per bag
4 Sand 25.60 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 44
DESCRIPTION OF ITEM:

Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Lime, cement, sand mortar Ratio (1 : 1 : 9).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 43.29 kg per kg
3 Cement 2.32 bags per bag
4 Sand 26.20 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 45
DESCRIPTION OF ITEM:

Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Lime, cement, sand mortar Ratio (1 : 1 : 10).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 39.94 kg per kg
3 Cement 2.14 bags per bag
4 Sand 26.66 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 46
DESCRIPTION OF ITEM:

Item No. 7 (iii) Lime, sand, mortar ratio (1 : 2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 174.30 kg per kg
3 Sand 23.33 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 47
DESCRIPTION OF ITEM:

Item No. 8 Additional extra labour in item No.7 for every 10 ft. (3 m
additional height.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Masons 0.25 No. per day


2 Cooly 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate Per 100 Cft. Rs. Say


Labour Rate Per Cum. Rs. Say

Page 48
DESCRIPTION OF ITEM:

Item No. 9 Extra labour for arch work in brick masonry including labo
centering and de-centering.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Masons 1.50 No. per day


2 Cooly 0.50 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate Per 100 Cft. Rs. Say


Labour Rate Per Cum. Rs. Say

Page 49
DESCRIPTION OF ITEM:

Item No. 10 Extra for Pacca brick work in steining of wells or any oth
circular masonry.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 82.00 No. % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft

1 Mason 1.25 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 50
DESCRIPTION OF ITEM:

Item No. 11 Extra labour for profile and flared walls.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Mason 0.43 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Composit rate per Cum Rs. Say

Page 51
DESCRIPTION OF ITEM:

Item No. 12 Extra labour for Pacca brick work in piers and abutment.

(i) From 10 ft. (3 metre) to 20 ft. (6 metre) height.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Mason 0.12 No. per day


2 Cooly unskilled 0.50 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Composit rate per Cum Rs. Say

Page 52
DESCRIPTION OF ITEM:

Item No. 12 Extra labour for Pacca brick work in piers and abutment.

(ii) Above 20 ft. (6 metre) height.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Mason 0.25 No. per day


2 Cooly unskilled 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Composit rate per Cum Rs. Say

Page 53
DESCRIPTION OF ITEM:

Item No. 13 Extra for face work (half brick thick) using special brick
of Ist class bricks.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Special moulded Stretcher


courses bricks 270.00
2 Header courses 513.00

Total 783.00
Add 5% wastage 39.15
Total 822.15

Difference in cost of special


moulded and ordinary Ist class
bricks

2 Extra cost = 0 - - = 0 %0 Nos.

Contractor's Profit & Ov 20 Percent


Total

Labour rate for 100 Cft Rs. Say


Composit rate per Cum Rs. Say

Page 54
DESCRIPTION OF ITEM:

Item No. 14 Reinforced brick work in lintels of opening, laid in (1:3)


sand mortar including, all labour material forms, moulds,
and shuttering etc., but excluding cost and labour of stee
reinforcement which shall be paid for separately.

Detail Unit Rate (British System) per Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 10.00 No. Nos.


2 Cement 0.11 bag per bag
3 Sand 0.41 Cft % Cft
4 Kikar wood for centring & shuttering
(10 x 1.60 x 0.2) Can be use 20 times 0.002 Cft Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft

1 Mason 0.067 No. per day


2 Cooly unskilled 0.11 No. per day
3 Bahishti 0.023 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per Cft Rs. Say


Composite rate per Cum Rs. Say

Page 55
DESCRIPTION OF ITEM:

Item No. 15 (a) Extra for dressing or chamfering of bricks (special or


architectaral shape).

Detail Unit Rate (British System) per 100 No.

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Mason 3.00 No. per day


2 Cooly unskilled 0.34 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 No. Rs. Say

Page 56
DESCRIPTION OF ITEM:

Item No. 15 (b) All other purposes.

Detail Unit Rate (British System) per 100 No.

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Mason 1.50 No. per day


2 Cooly unskilled 0.17 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 No. Rs. Say

Page 57
DESCRIPTION OF ITEM:

Item No. 16 Peforated Pacca brick walling 114 mm (4") thick in ground
floor in
(i) Mud mortar.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Good earth 8.75 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.00 No. per day


2 Coolies unskilled 1.83 Nos. per day
3 Bahishti 0.23 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 58
DESCRIPTION OF ITEM:

Item No. 16 (ii) Cement sand mortar Ratio (1 : 2).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Cement 2.00 bags per bag
3 Sand 5.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 59
DESCRIPTION OF ITEM:

Item No. 16 (ii) Cement sand mortar Ratio (1:3).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Cement 1.50 bags per bag
3 Sand 5.60 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 60
DESCRIPTION OF ITEM:

Item No. 16 (ii) Cement sand mortar Ratio (1:4).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Cement 1.20 bags per bag
3 Sand 6.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 61
DESCRIPTION OF ITEM:

Item No. 16 (ii) Cement sand mortar Ratio (1:5).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Cement 1.00 bags per bag
3 Sand 6.25 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 62
DESCRIPTION OF ITEM:

Item No. 16 (ii) Cement sand mortar Ratio (1:6).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Cement 0.86 bags per bag
3 Sand 6.40 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 63
DESCRIPTION OF ITEM:

Item No. 16 (ii) Cement sand mortar Ratio (1:7).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Cement 0.75 bags per bag
3 Sand 6.58 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 64
DESCRIPTION OF ITEM:

Item No. 16 (ii) Cement sand mortar Ratio (1:8).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Cement 0.67 bags per bag
3 Sand 6.67 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 65
DESCRIPTION OF ITEM:

Item No. 16 (iii) Lime cement sand mortar Ratio (1 : 1 : 6).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Slaked lime 14.93 kg kg
3 Cement 0.80 bags per bag
4 Sand 6.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 66
DESCRIPTION OF ITEM:

Item No. 16 (iii) Lime cement sand mortar Ratio (1 : 1 : 7).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Slaked lime 13.44 kg per kg
3 Cement 0.71 bags per bag
4 Sand 6.13 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 67
DESCRIPTION OF ITEM:

Item No. 16 (iii) Lime cement sand mortar Ratio (1 : 1 : 8).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Slaked lime 12.32 kg per kg
3 Cement 0.64 bags per bag
4 Sand 6.40 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 68
DESCRIPTION OF ITEM:

Item No. 16 (iii) Lime cement sand mortar Ratio (1 : 1 : 9).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Slaked lime 10.82 kg per kg
3 Cement 0.58 bags per bag
4 Sand 6.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 69
DESCRIPTION OF ITEM:

Item No. 16 (iii) Lime cement sand mortar Ratio (1 : 1 : 10).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Slaked lime 10.08 kg per kg
3 Cement 0.54 bags per bag
4 Sand 6.70 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 70
DESCRIPTION OF ITEM:

Item No. 16 (iv) Lime cement sand mortar Ratio (1 : 2).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 Nos. Nos.


2 Slaked lime 43.67 kg per kg
3 Sand 5.58 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 71
DESCRIPTION OF ITEM:

Item No. 17 Add. extra labour on item No.15 for pacca brick work.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Sft


First Floor

1 Mason 0.13 No. per day


2 Cooly unskilled 0.50 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate for 100 Sft Rs.
Say
Labour rate per Sqm Rs.
Say

LABOUR for 125 Sft


Second Floor

1 Masons 0.37 No. per day


2 Coolies unskilled 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate for 100 Sft Rs.
Say
Labour rate per Sqm Rs.
Say

LABOUR for 125 Cft


Third Floor

1 Masons 0.63 No. per day


2 Coolies unskilled 1.50 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate for 100 Sft
Say
Labour rate per Sqm
Say

Page 72
LABOUR for 125 Sft
4th & Subsequent Floor

1 Masons 1.12 Nos. per day


2 Coolies unskilled 2.12 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate for 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Page 73
DESCRIPTION OF ITEM:

Item No. 18 (i) Perforated pacca brick walling 9" thick in ground floor in
Mud Mortar

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MUD MORTAR

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Good earth 17.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.75 Nos. per day
3 Bahishti 0.35 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 74
DESCRIPTION OF ITEM:

Item No. 18 (ii) Cement sand mortar Ratio (1 : 2)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Cement 4.00 bags bags
3 Sand 10.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 75
DESCRIPTION OF ITEM:

Item No. 18 (ii) Cement sand mortar Ratio (1 : 3)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Cement 3.00 bags bags
3 Sand 11.25 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 76
DESCRIPTION OF ITEM:

Item No. 18 (ii) Cement sand mortar Ratio (1 : 4)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Cement 2.40 bags per bag
3 Sand 12.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 77
DESCRIPTION OF ITEM:

Item No. 18 (ii) Cement sand mortar Ratio (1 : 5)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Cement 2.00 bags per bag
3 Sand 12.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 78
DESCRIPTION OF ITEM:

Item No. 18 (ii) Cement sand mortar Ratio (1 : 6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Cement 1.72 bags per bag
3 Sand 12.80 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 79
DESCRIPTION OF ITEM:

Item No. 18 (ii) Cement sand mortar Ratio (1 : 7)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Cement 1.50 bags per bag
3 Sand 13.13 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 80
DESCRIPTION OF ITEM:

Item No. 18 (ii) Cement sand mortar Ratio (1 : 8)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Cement 1.33 bags per bag
3 Sand 13.34 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 81
DESCRIPTION OF ITEM:

Item No. 18 (iii) Lime cement sand mortar Ratio (1 : 1 : 6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Slaked lime 29.86 kg per kg
3 Cement 1.60 bags per bag
4 Sand 12.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 82
DESCRIPTION OF ITEM:

Item No. 18 (iii) Lime cement sand mortar Ratio (1 : 1 : 7)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Slaked lime 26.50 kg per kg
3 Cement 1.42 bags per bag
4 Sand 12.39 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 83
DESCRIPTION OF ITEM:

Item No. 18 (iii) Lime cement sand mortar Ratio (1 : 1 : 8)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Slaked lime 23.90 kg per kg
3 Cement 1.28 bags per bag
4 Sand 12.80 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 84
DESCRIPTION OF ITEM:

Item No. 18 (iii) Lime cement sand mortar Ratio (1 : 1 : 9)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Slaked lime 21.65 kg per kg
3 Cement 1.16 bags per bag
4 Sand 13.10 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 85
DESCRIPTION OF ITEM:

Item No. 18 (iii) Lime cement sand mortar Ratio (1 : 1 : 10)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Slaked lime 20.16 kg per kg
3 Cement 1.07 bags per kg
4 Sand 13.33 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 86
DESCRIPTION OF ITEM:

Item No. 18 (iv) Lime sand mortar Ratio (1 : 2)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Slaked lime 86.97 kg per kg
3 Sand 11.67 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 87
DESCRIPTION OF ITEM:

Item No. 19 Extra labour in item No.18 for per perforated pacca brick
work in

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

LABOUR
First Floor

Labour of item No.6 for 100 Cft 0.75


Say
Labour of item No.6 per Cum 0.75
Say
LABOUR
Second Floor

Labour of item No.6 for 100 Cft 0.75


Say
Labour of item No.6 per Cum 0.75
Say
LABOUR
Third Floor

Labour of item No.6 for 100 Cft 0.75


Say
Labour of item No.6 per Cum 0.75
Say
LABOUR
Fourth & Subsequent Floor

Labour of item No.6 for 100 Cft 0.75


Say
Labour of item No.6 per Cum 0.75
Say

Page 88
DESCRIPTION OF ITEM:

Item No. 20 Fire brick masonary in fire clay mortar.

(i) Upto 20 ft. (6 metre) height including all charges.

Detail Unit Rate (British System) per Cft

Qty Rate Per UnitAmount (Rs.)

Per 100 Cft


MATERIAL

1 Fire clay bricks 9" x 4" x 3" 1350.00 No. Each


2 Fire resistant Cement 8.80 bags per bag
3 Brick grinded sand 22.00 Cft per Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


for masonary work

1 Mason 3.00 Nos. per day


2 Coolies 3.00 Nos. per day
3 Bahishti 0.25 No. per day

for mortar

1 Cooly 1.00 No. per day


2 Bahishti 0.25 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per Cft Rs. Say


Composite rate per Cum Rs. Say

Page 89
DESCRIPTION OF ITEM:

Item No. 20 Fire brick masonary in fire clay mortar.

(ii) Extra for every 1.5 metre additional height.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Mason 0.25 No. per day


2 Cooly unskilled 1.00 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Page 90
DESCRIPTION OF ITEM:

Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with (1") 25 mm wide 18 gauge hoop iron.

(i) 4" (114 mm) thick walling with hoop iron bouding 6"
(150 mm) apart.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 525.00 Nos. Nos.


2 Cement 2.40 bags per bag
3 Sand 9.00 Cft % Cft
4 Hoop iron 45.00 lbs Per Kg.
20.41 Kg.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR

1 Mason 1.00 No. per day


2 Coolies unskilled 1.25 Nos. per day
3 Bahishti 0.25 No. per day
4 Black-smith 0.15 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 91
DESCRIPTION OF ITEM:

Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with 1" (25 mm) wide 18 gauge hoop iron.

(ii) 4" (114 mm) thick walling with hoop iron bouding
12" (300 mm) apart.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 525.00 Nos. Nos.


2 Cement 2.40 bags per bag
3 Sand 9.00 Cft % Cft
4 Hoop iron 22.50 lbs Per Kg.
10.20 kg.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR

1 Mason 1.00 No. per day


2 Coolies unskilled 1.00 No. per day
3 Bahishti 0.25 No. per day
4 Black-smith 0.10 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 92
DESCRIPTION OF ITEM:

Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with 1" (25 mm) wide 18 gauge hoop iron.

(iii) 3" (75 mm) thick walling with hoop iron bouding 6"
(150 mm) apart.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 350.00 Nos. Nos.


2 Cement 1.80 bags per bag
3 Sand 6.50 Cft % Cft
4 Hoop iron 45.00 lbs Per Kg.
20.41 Kg.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft

1 Mason 0.75 No. per day


2 Coolies unskilled 1.00 No. per day
3 Bahishti 0.20 No. per day
4 Black-smith 0.15 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 93
DESCRIPTION OF ITEM:

Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with 1" (25 mm) wide 18 gauge hoop iron.

(iv) 3" (75 mm) thick walling with hoop iron bouding 12"
(300 mm) apart.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 350.00 Nos. Nos.


2 Cement 1.80 bags per bag
3 Sand 6.50 Cft % Cft
4 Hoop iron 20.00 lbs Per Kg.
9.070 Kg.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft

1 Mason 0.75 No. per day


2 Coolies unskilled 1.00 No. per day
3 Bahishti 0.20 No. per day
4 Black-smith 0.15 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 94
DESCRIPTION OF ITEM:

Item No. 22 Ghilafi work (1 brick thick wall).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 B.B in mud ( of item No.1) x


2 Sundried bricks ( of item No.24) x

Total

LABOUR for 125 Cft

1 Mason 2.00 Nos. per day


2 Coolies unskilled 3.67 Nos. per day
3 Bahishti 0.50 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 95
DESCRIPTION OF ITEM:

Item No. 23 Dry brick pitching.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Ist class burnt brick 1350.00 Nos. Nos.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR

1 Mason 1.00 No. per day


2 Coolies unskilled 2.00 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 96
DESCRIPTION OF ITEM:

Item No. 24 Sun dried bricks in Mud mortar.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Sun dried bricks 1350.00 Nos. Nos.


2 Siff clay 35.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft

1 Mason 1.50 Nos. per day


2 Coolies unskilled 3.50 Nos. per day
3 Bahishti 0.25 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 97
DESCRIPTION OF ITEM:

Item No. 25 Pise wall (mud walling).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Coolies skilled 1.00 No. per day


2 Coolies unskilled 1.50 Nos. per day
3 Bahishti 0.50 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 98
DESCRIPTION OF ITEM:

Item No. 26 Providing Eave brick moulded weathered and throated with b
brick or drip course cornice in (1 : 3) cement mortar.

(i) 3" (76 mm) thick drip course.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

MATERIAL (FOR 100 RFT.)

1 Moulded brick 280.00 Nos. Nos.


2 Cement for laying and plastering 1.50 bag per bag
3 Sand 5.00 Cft % Cft
Deduct cost of ordinary bricks 140 Nos. Nos.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR (FOR 125 RFT.)

1 Mason 1.75 Nos. per day


2 Coolies unskilled 1.75 Nos. per day
3 Bahishti 0.25 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per Rft Rs. Say


Composite rate per R.M Rs. Say

Page 99
DESCRIPTION OF ITEM:

Item No. 26 Providing Eave brick moulded weathered and throated with b
brick or drip cornice in (1 : 3) cement mortars.

(ii) 4" (114 mm) thick drip course cornice.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

MATERIAL (FOR 100 RFT.)

1 Brick moulded I/C wastage 420.00 Nos. Nos.


2 Cement for laying and plastering 1.75 bag per bag
3 Sand 6.00 Cft % Cft
Deduct cost of ordinary bricks 210.00 Nos. Nos.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR (FOR 125 RFT)

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.00 Nos. per day
3 Bahishti 0.25 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per 100 Rft Rs. Say


Composite rate per R.M Rs. Say

Page 100
DESCRIPTION OF ITEM:

Item No. 26 Providing Eave brick moulded weathered and throated with b
brick or drip cornice in (1 : 3) cement mortar.

(iii) 4" (114 mm) thick eave brick with back brick.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

MATERIAL (FOR 100 RFT)

1 Brick moulded (including wastage) 465.00 Nos. Nos.


2 Back bricks ordinary 465.00 Nos. Nos.
3 Cement 1.20 bag per bag
4 Sand 5.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR (FOR 125 RFT.)

1 Mason for laying 1.00 No. per day


2 Coolies unskilled 2.00 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per Rft Rs. Say


Composite rate per R.M Rs. Say

Page 101
DESCRIPTION OF ITEM:

Item No. 27 Providing & laying dressed or moulded brick cornice in ( 1


cement mortar, plastering or pointing complete.

(i) One brick.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

MATERIAL (FOR 100 RFT.)

1 Pacca bricks I/C 10% wastage


As the rate is only for the projected protion
to the brick required 60.00 Nos. Nos.
2 Cement for laying & plastering or pointi 1.60 bag per bag
3 Sand for laying & plastering or plasteri 6.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Rft

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.00 Nos. per day
3 Bahishti 0.25 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per Rft Rs. Say


Composite rate per R.M Rs. Say

Page 102
DESCRIPTION OF ITEM:

Item No. 27 Providing & laying dressed or moulded brick cornice in ( 1


cement mortar, plastering or pointing complete.

(ii) Two brick.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

MATERIAL (FOR 100 RFT.)

1 Pacca bricks 175.00 Nos. Nos.


2 Cement for laying & plastering 5.00 bags per bag
3 Sand for laying & plastering 18.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Rft

1 Mason 3.00 Nos. per day


2 Coolies unskilled 3.00 Nos. per day
3 Bahishti 0.25 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per Rft Rs. Say


Composite rate per R.M Rs. Say

Page 103
DESCRIPTION OF ITEM:

Item No. 27 Providing & laying dressed or moulded brick cornice in ( 1


cement mortar, plastering or pointing complete.

(iii) Three bricks.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

MATERIAL (FOR 100 RFT.)

1 Pacca bricks 270.00 Nos. Nos.


2 Cement for laying & plastering 8.00 bags per bag
3 Sand for laying & plastering 60.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Rft

1 Mason 4.00 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.34 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per Rft Rs. Say


Composite rate per R.M Rs. Say

Page 104
DESCRIPTION OF ITEM:

Item No. 27 Providing & laying dressed or moulded brick cornice in ( 1


cement mortar, plastering or pointing complete.

(iv) Four brick.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

MATERIAL FOR 100 RFT.)

1 Pacca bricks 580.00 Nos. Nos.


2 Cement for laying & plastering 10.00 bags per bag
3 Sand for laying & plastering 37.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Rft

1 Mason 5.00 Nos. per day


2 Coolies unskilled 5.00 Nos. per day
3 Bahishti 0.50 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per Rft Rs. Say


Composite rate per R.M Rs. Say

Page 105
DESCRIPTION OF ITEM:

Item No. 28 Cleaning brick dismentled from kacha pacca masonry.

Detail Unit Rate (British System) per 1000 No.

Qty Rate Per UnitAmount (Rs.)

LABOUR for 1250 Nos.

1 Cooly unskilled 1.75 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rat per 1000 No. Rs. Say

DESCRIPTION OF ITEM:

Item No. 29 Scraping bricks dismantled from pacca masonary.

Detail Unit Rate (British System) per 1000 No.

Qty Rate Per UnitAmount (Rs.)

LABOUR for 1250 Nos.

1 Cooly unskilled 3.30 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rat per 1000 No. Rs. Say

Page 106
DESCRIPTION OF ITEM:

Item No. 30 Supplying and filling sand under floors or plugging in wel

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Sand 100.00 Nos. % Nos.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 150 Cft

1 Cooly unskilled 0.50 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft. Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft. Rs. Say


Composite rate per Cum. Rs. Say

Page 107
DESCRIPTION OF ITEM:

Item No. 31 Providing and laying 2" (50 mm) thick projected tile bank
(1: 2) cement sand mortar with hoop iron 1" (25 mm) wide 1
SWG flat iron sheet 9" (225 mm) apart.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

Rate Analysis for 8 Rft


MATERIAL

1 Title 225 x 114 x 40 mm title 43.00 Nos. Nos.


2 Cement 0.09 bag per bag
3 Sand 0.20 Cft % Cft
4 Cost of hoop iron 3.00 Kg. Per Kg.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR

1 Mason 0.50 No. per day


2 Coolies unskilled 0.50 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per Rft Rs. Say


Composite rate per R.M Rs. Say

Page 108
DESCRIPTION OF ITEM:

Item No. 32 Ist class brick tiles (9" 4" x 1") 225 x 114 x 40 mm cla
76 mm thick laid in cement sand mortar recifered with hoop
strips placed at 2 ft. (600 mm) apart vertically.

(i) Ratio (1 : 3).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Brick tiles 9" x 4" x 1" 810.00 No. Nos.


2 Cement 2.40 bags per bag
3 Sand 9.00 Cft % Cft
4 Hoop iron 4.54 Kg. per Kg.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR

1 Mason 1.00 No. per day


2 Coolies unskilled 1.00 No. per day
3 Bahishti 0.25 No. per day
4 Black-smith 0.10 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft. Rs. Say


Composite rate per Sqm Rs. Say

Page 109
DESCRIPTION OF ITEM:

Item No. 32 Ist class brick tiles (9" 4" x 1") 225 x 114 x 40 mm cla
76 mm thick laid in cement sand mortar recifered with hoop
strips placed at 2 ft. (600 mm) apart vertically.

(ii) Ratio (1 : 4).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Brick tiles 9" x 4" x 1" 810.00 No. Nos.


2 Cement 1.92 bags per bag
3 Sand 9.60 Cft % Cft
4 Hoop iron 4.54 Kg. per Kg.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR

1 Mason 1.00 No. per day


2 Coolies unskilled 1.00 No. per day
3 Bahishti 0.25 No. per day
4 Black-smith 0.10 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft. Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft. Rs. Say


Composite rate per Sqm Rs. Say

Page 110
DESCRIPTION OF ITEM:

Item No. 33 Chamfering sides of head regulators and masonry wall to


increase width.

Detail Unit Rate (British System) per Sft

Qty Rate Per UnitAmount (Rs.)

LABOUR (FOR 30 SFT)

1 Mason 1.00 No. per day


2 Cooly unskilled 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

Labour rate per Sft Rs. Say


Labour rate per Sqm Rs. Say

Page 111
DESCRIPTION OF ITEM:

Item No. 34 Replacing kallar eaten bricks.

Detail Unit Rate (British System) per Bricks

Qty Rate Per UnitAmount (Rs.)

Assume 60 Bricks
MATERIAL

1 Bricks 50.00 Nos. Nos.


2 Cement 0.005 Bag Bag
3 Sand 0.026 Cft % Cft.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR

1 Mason 2.00 No. per day


2 Cooly 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Brick Rs. Say


Composit rate per Brick Rs. Say

Page 112
DESCRIPTION OF ITEM:

Item No. 35 Repairing corner's of bridges and other hydraulic


masoney works.

Detail Unit Rate (British System) per No. / Assumed for 1

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Brick tiles 9" x 4" x 1" 10.00 No. Nos.


2 Cement 0.08 bags per bag
3 Sand 0.25 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 1.5 No.

1 Mason 0.25 No. per day


2 Coolies unskilled 0.25 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Each No. Rs. Say


Composite rate per Each No. Rs. Say

Page 113
DESCRIPTION OF ITEM:

Item No. 36 Extra labour for drains of bath roons etc.

Detail Unit Rate (British System) per Lft

Qty Rate Per UnitAmount (Rs.)

Assumed for 40 Lft


LABOUR

1 Mason 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

Labour rate per Lft Rs. Say


Labour rate per Meter Rs. Say

DESCRIPTION OF ITEM:

Item No. 37 Maroo corners.

Detail Unit Rate (British System) per No.

Qty Rate Per UnitAmount (Rs.)

LABOUR for 1.25 No.

1 Mason 0.20 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

Labour rate per Each No. Rs. Say

Page 114
CHAPTER NO. 11

SURFACE RENDERING
DESCRIPTION OF ITEM:

Item No. 1 Mud plaster on walls (excluding Gobri leeping) upto 20' (6.10 metre) height.

(a) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Clay 6.00 Cft 0.00per 100 Cft -


2 Bhoosa 7.50 kg 0.00 kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.17 No. 0.00 per day -


2 Cooly un-skilled 0.50 No. 0.00 per day -
3 Bahisthi 0.05 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 1
DESCRIPTION OF ITEM:

Item No. 1 Mud plaster on walls (excluding Gobiry leaping) upto 20' height
(6.10 metre).

(b) 1" (25 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Clay 12.00 Cft 0.00per 100 Cft -


2 Bhoosa 15.00 kg 0.00 kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.20 No. 0.00 per day -


2 Cooly un-skilled 0.75 No. 0.00 per day -
3 Bahishti 0.07 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 2
DESCRIPTION OF ITEM:

Item No. 2 Mud plaster on floor or roof (excluding Gobri Leaping).

(a) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Clay 6.00 Cft 0.00per 100 Cft -


2 Bhoosa 7.50 kg 0.00 kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.15 No. 0.00 per day -


2 Cooly un-skilled 0.45 No. 0.00 per day -
3 Bahishti 0.05 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 3
DESCRIPTION OF ITEM:

Item No. 2 Mud plaster on floor or roof (excluding Gobri Leaping).

(b) 1" (25 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Clay 12.00 Cft 0.00per 100 Cft -


2 Bhoosa 15.00 kg 0.00 kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft) (For 125 Sft)

1 Mason 0.15 No. 0.00 per day -


2 Cooly un-skilled 0.45 No. 0.00 per day -
3 Bahishti 0.05 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 4
DESCRIPTION OF ITEM:

Item No. 3 Cement lime plaster 1 : 7 : 12 (cemnt lime and sand) up to 20 ft.
(6.10 metre) height.

(a) " thick (6 mm).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.10 bag 0.00 bags -


2 Lime Slaked (ground) 12.70 kg 0.00 kg -
3 Sand 1.40 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 No. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. -0.01 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. -0.01 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 5
DESCRIPTION OF ITEM:

Item No. 3 Cement lime plaster 1 : 7 : 12 (cemnt lime and sand) up to 20 ft.
(6.10 metre) height.

(b) " thick (12 mm).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.20 bag 0.00 bags -


2 Lime Slaked (ground) 25.38 kg 0.00 kg -
3 Sand 2.80 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 No. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.01 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 6
DESCRIPTION OF ITEM:

Item No. 4 Cement neru plaster 1 : 2 (cement and sand) upto 20 ft. (6.10 metre).

(a) " thick (6 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.60 bag 0.00 bags -


2 Sand 1.54 Cft 0.00 Cft -
3 Chopped jute 1.41 kg 0.00 kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 No. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 7
DESCRIPTION OF ITEM:

Item No. 4 Cement neru plaster 1 : 2 (cement and sand) upto 20 ft. (6.10 metre).

(b) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.92 bag 0.00 bags -


2 Sand 3.08 Cft 0.00 Cft -
3 Chopped jute 2.72 kg 0.00 kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 No. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 8
DESCRIPTION OF ITEM:

Item No. 5 Stucco cement plaster 2" (50 mm) thick 1 : 2 : 4 (cement sand and shingle,
upto 20 ft (6.0 m) height.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Shingle 15.00 Cft -200.00 % Cft -


2 Sand 7.40 Cft 0.00 Cft -
3 Cement 3.70 bags 0.00 bags -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 4.00 Nos. 0.00 per day -
3 Bahishti 0.30 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 9
DESCRIPTION OF ITEM:

Item No. 6 Providing and laying machine sprayed plaster " (12 mm) thick, using
cement and chips zero gauge over the existing plastered and roughened
surface, upto 20 ft height (6 metre).

(i) Ratio 1 : 1.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.80 bag 0.00 bags -


2 Chips 2.30 Cft 0.00 kg -
157.00 kg

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 0.50 Nos. 0.00 per day -
3 Bahishti 0.13 No. 0.00 per day -
4 Spray machine L.S -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 10
DESCRIPTION OF ITEM:

Item No. 6 Providing and laying machine sprayed plaster "12 mm thick, using cement
and chips zero gauge over the existing plastered and roughened surface,
upto 20 ft height.

(ii) Ratio 1 : 1.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.45 bag 0.00 bags -


2 Chips 2.75 Cft 0.00 kg -
187.00 kg
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 0.50 Nos. 0.00 per day -
3 Bahishti 0.13 No. 0.00 per day -
4 Spray machine L.S -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 11
DESCRIPTION OF ITEM:

Item No. 6 Providing and laying machine sprayed plaster "12 mm thick, using cement
and chips zero gauge over the existing plastered and roughened surface,
upto 20 ft height.

(iii) Ratio 1 : 2.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.25 bag 0.00 bags -


2 Chips 3.00 Cft 0.00 kg -
204.00 kg
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 0.50 Nos. 0.00 per day -
3 Bahishti 0.13 No. 0.00 per day -
4 Spray machine L.S -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 12
DESCRIPTION OF ITEM:

Item No. 7 Cement plaster (1 : 2) upto 20 ft height (6.10) metre.

(i) 3/8" (10 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.96 bag 0.00 bags -


2 Sand 2.50 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.01 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 13
DESCRIPTION OF ITEM:

Item No. 7 Cement plaster (1 : 2) upto 20 ft height (6.10) metre.

(ii) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.25 bag 0.00 bags -


2 Sand 3.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 14
DESCRIPTION OF ITEM:

Item No. 7 Cement plaster (1 : 2) upto 20 ft height (6.10) metre.

(iii) " (19 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.92 bag 0.00 bags -


2 Sand 5.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 1.25 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 15
DESCRIPTION OF ITEM:

Item No. 8 Cement plaster (1 : 3) cement and sand upto 20 ft height (6.10 metre).

(a) 3/8" (10 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.66 bag 0.00 bags -


2 Sand 2.55 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 16
DESCRIPTION OF ITEM:

Item No. 8 Cement plaster (1 : 3) cement and sand upto 20 ft height (6.10 metre).

(b) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.88 bag 0.00 bags -


2 Sand 3.40 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. -0.01 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. -0.01 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 17
DESCRIPTION OF ITEM:

Item No. 8 Cement plaster (1 : 3) cement and sand upto 20 ft height (6.10 metre).

(c) " (19 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.32 bag 0.00 bags -


2 Sand 5.10 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 1.25 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 18
DESCRIPTION OF ITEM:

Item No. 9 Cement plaster (1 : 4) upto 20 ft. (6.10 metre) height.

(a) 3/8" (10 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.57 bag 0.00 bags -


2 Sand 3.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 19
DESCRIPTION OF ITEM:

Item No. 9 Cement plaster (1 : 4) upto 20 ft. (6.10 metre) height.

(b) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.73 bag 0.00 bags -


2 Sand 3.60 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 20
DESCRIPTION OF ITEM:

Item No. 9 Cement plaster (1 : 4) upto 20 ft. (6.10 metre) height.

(c) " (19 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.14 bag 0.00 bags -


2 Sand 5.50 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 1.25 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 21
DESCRIPTION OF ITEM:

Item No. 10 Cement plaster 3/8" (10 mm) thick under soffit of R.C.C. roof slab only, upto
20 ft. (6.10 meter) height.

(a) Ratio ( 1 : 2 ).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement for floating coat (0.20 bag)


Cemtnt (0.96 bag) 1.16 bag 0.00 bags -
2 Sand 2.55 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 22
DESCRIPTION OF ITEM:

Item No. 10 Cement plaster 3/8" (10 mm) thick under soffit of R.C.C. roof slab only, upto
20 ft. (6.10 meter) height.

(b) Ratio ( 1 : 3 ).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement for floating coat (0.20 bag)


Cement (0.66 bag) 0.86 bag 0.00 bags -
2 Sand 2.55 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 23
DESCRIPTION OF ITEM:

Item No. 10 Cement plaster 3/8" (10 mm) thick under soffit of R.C.C. roof slab only, upto
20 ft. (6.10 meter) height.

(c) Ratio ( 1 : 4 ).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement for floating coat (0.20 bag)


Cement (0.57 bag) 0.77 bag 0.00 bags -
2 Sand 3.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 24
DESCRIPTION OF ITEM:

Item No. 11 Cement plaster (1 : 5) upto 20 ft. (6.10 metre) height.

(a) 3/8" (10 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.50 bag 0.00 bags -


2 Sand 3.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 25
DESCRIPTION OF ITEM:

Item No. 11 Cement plaster (1 : 5) upto 20 ft. (6.10 metre) height.

(b) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.60 bag 0.00 bags -


2 Sand 4.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 26
DESCRIPTION OF ITEM:

Item No. 11 Cement plaster (1 : 5) upto 20 ft. (6.10 metre) height.

(c) " (19 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.00 bag 0.00 bags -


2 Sand 6.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 1.25 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 27
DESCRIPTION OF ITEM:

Item No. 12 Cement plaster (1 : 6) upto 20 ft. (6.10 metre) height.

(a) 3/8" (10 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.40 bag 0.00 bags -


2 Sand 3.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 28
DESCRIPTION OF ITEM:

Item No. 12 Cement plaster (1 : 6) upto 20 ft. (6.10 metre) height.

(b) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.53 bag 0.00 bags -


2 Sand 4.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 29
DESCRIPTION OF ITEM:

Item No. 12 Cement plaster (1 : 6) upto 20 ft. (6.10 metre) height.

(c) " (19 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.80 bag 0.00 bags -


2 Sand 6.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 1.25 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 30
DESCRIPTION OF ITEM:

Item No. 13 Applying floating coat of cement 1/32" (0.75 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.40 bag 0.00 bags -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 0.25 Nos. 0.00 per day -
3 Bahishti 0.10 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 31
DESCRIPTION OF ITEM:

Item No. 14 Lime pointing flush upto 20 ft (6.10 mm) height including raking joints.
Ratio (1 : 2) lime sand mortar.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Lime slaked (ground) 13.44 kg 0.00 kg -


2 Sand 1.80 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.50 No. 0.00 per day -


2 Cooly un-skilled 0.75 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 32
DESCRIPTION OF ITEM:

Item No. 15 Lime pointing struck joints on walls, upto 20 ft. (6.10 metre) height
including raking joints Ratio (1 : 2) lime sand mortar.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Lime slaked (ground) 13.44 kg 0.00 kg -


2 Sand 1.80 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 33
DESCRIPTION OF ITEM:

Item No. 16 Cement pointing Flush upto 20 ft. (6.10 metre) height.

(a) 1 : 2 (cement and sand)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.72 bag 0.00 bags -


2 Sand 1.80 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 34
DESCRIPTION OF ITEM:

Item No. 16 Cement pointing Flush upto 20 ft. (6.10 metre) height.

(b) 1 : 3 (cement and sand)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.54 bag 0.00 bags -


2 Sand 2.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.75 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 35
DESCRIPTION OF ITEM:

Item No. 17 Cement pointing (1 : 2) flush on floor.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.72 bag 0.00 bags -


2 Sand 1.80 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.50 No. 0.00 per day -


2 Cooly un-skilled 0.75 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 36
DESCRIPTION OF ITEM:

Item No. 18 Cement pointing struck joints on walls upto 20 ft. (6.10 metre) height.

(a) Ratio 1 : 2 (cement & sand).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.72 bag 0.00 bags -


2 Sand 1.80 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 37
DESCRIPTION OF ITEM:

Item No. 18 Cement pointing struck joints on walls.

(b) Ratio 1 : 3 (cement & sand).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.54 bag 0.00 bags -


2 Sand 2.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 38
DESCRIPTION OF ITEM:

Item No. 19 Pointing flush on stone work raised.

(a) In Lime Mortar Ratio 1 : 2 (Limet & Sand).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Lime slaked (ground) 18.66 kg 0.00 kg -


2 Sand 2.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 0.50 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 39
DESCRIPTION OF ITEM:

Item No. 19 Pointing flush on stone work raised.

(b) In Cement Mortar Ratio 1 : 3 (Cement & Sand).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.54 bag 0.00 bags -


2 Sand 2.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 0.50 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 40
DESCRIPTION OF ITEM:

Item No. 19 Pointing flush on stone work raised.

(c) (i) In Lime Mortar Ratio 1 : 2 (Lime & Sand).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL
0.54 bag
1 Slaked lime 18.66 kg 0.00 kg -
2 Sand 2.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 2.00 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 41
DESCRIPTION OF ITEM:

Item No. 19 Pointing flush on stone work raised.

(c) (ii) In Cement Mortar Ratio 1 : 3 (Cement & Sand).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.54 bag 0.00 bags -


2 Sand 2.00 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 2.00 No. 0.00 per day -


2 Cooly un-skilled 1.00 Nos. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 42
DESCRIPTION OF ITEM:

Item No. 20 Raking and washing joints of stone masonry (old work).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

LABOUR (For 125 Sft)

1 Cooly (Skilled) 1.00 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say -
Labour rate per Sqm Rs. 0.00 Say -

DESCRIPTION OF ITEM:

Item No. 21 Raking and washing joints of brick masonary (old work).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

LABOUR (For 125 Sft)

1 Cooly (Skilled) 0.50 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say -
Labour rate per Sqm Rs. 0.00 Say -

Page 43
DESCRIPTION OF ITEM:

Item No. 22 Priming coat of chalk under distemper.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Chalk 0.91 kg 0.00 kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.10 No. 0.00 per day -


2 Cooly un-skilled 0.10 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.01 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 44
DESCRIPTION OF ITEM:

Item No. 23 Distempering.

(a) New surface.

(i) One coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL
0.15 gln
1 Distemper 1.50 lbs 0.00 per gln -
2 Burshes (Large) 0.04 No. 0.00 Each -
3 Sand Paper 0.014 No. 0.00 Doz -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 150 Sft)

1 Painter 0.17 No. 0.00 per day -


2 Cooly un-skilled 0.08 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 45
DESCRIPTION OF ITEM:

Item No. 23 Distempering.

(a) New surface.

(ii) Two coats.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL
0.20 gln
1 Distemper 2.00 lbs 0.00 per gln -
2 Burshes (Large) 0.04 No. 0.00 Each -
3 Sand Paper 0.014 No. 0.00 Doz -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 150 Sft)

1 Painter 0.25 No. 0.00 per day -


2 Cooly un-skilled 0.12 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 46
DESCRIPTION OF ITEM:

Item No. 23 Distempering.

(a) New surface.

(iii) Three coats.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL
0.25 gln
1 Distemper 2.50 lbs 0.00 per gln -
2 Burshes (Large) 0.04 No. 0.00 Each -
3 Sand Paper 0.014 No. 0.00 Doz -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 150 Sft)

1 Painter 0.33 No. 0.00 per day -


2 Cooly un-skilled 0.16 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 47
DESCRIPTION OF ITEM:

Item No. 23 Distempering.

(b) Old surface.

(i) One coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL
0.10 gln
1 Distemper 1.00 lbs 0.00 per gln -
2 Burshes (Large) 0.04 No. 0.00 Each -
3 Sand Paper 0.014 No. 0.00 Doz -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 150 Sft)

1 Painter 0.15 No. 0.00 per day -


2 Cooly un-skilled 0.08 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 48
DESCRIPTION OF ITEM:

Item No. 23 Distempering.

(b) Old surface.

(ii) Two coats.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL
0.10 gln
1 Distemper 1.00 lbs 0.00 per gln -
2 Burshes (Large) 0.04 No. 0.00 Each -
3 Sand Paper 0.014 No. 0.00 Doz -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 150 Sft)

1 Painter 0.25 No. 0.00 per day -


2 Cooly un-skilled 0.12 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 49
DESCRIPTION OF ITEM:

Item No. 24 Colour washing.

(a) New surface.

(i) One coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 White lime 1.87 kg 0.00 per kg -


2 Rice 0.117 kg 0.00 per kg -
3 Colouring material 0.17 lbs 0.00 per kg -
0.077 kg
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Colly skilled 0.12 No. 0.00 per day -


2 Cooly un-skilled 0.06 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 50
DESCRIPTION OF ITEM:

Item No. 24 Colour washing.

(a) New surface.

(ii) Two coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 White lime 2.80 kg 0.00 per kg -


2 Rice 0.175 kg 0.00 per kg -
3 Colouring material 0.22 lbs 0.00 per kg -
0.10 kg
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Colly skilled 0.18 No. 0.00 per day -


2 Cooly un-skilled 0.09 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 51
DESCRIPTION OF ITEM:

Item No. 24 Colour washing.

(b) Old surface.

(i) One coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 White lime 1.40 kg 0.00 per kg -


2 Rice 0.044 kg 0.00 per kg -
3 Colouring material 0.10 lbs 0.00 per kg -
0.045 kg
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Colly skilled 0.12 No. 0.00 per day -


2 Cooly un-skilled 0.06 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 52
DESCRIPTION OF ITEM:

Item No. 24 Colour washing.

(b) Old surface.

(ii) Two coats.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 White lime 2.33 kg 0.00 per kg 6.99


2 Rice 0.073 kg 0.00 per kg -
3 Colouring material 0.15 lbs 0.00 per kg -
0.068 kg
Total 6.99
Contractor's Profit & Ove 20.00 Percent 1.40
Total 8.39

LABOUR (For 125 Sft)

1 Colly skilled 0.18 No. 0.00 per day -


2 Cooly un-skilled 0.09 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 8.39 Say 8.40


Composite rate per Sqm Rs. 0.90 Say 0.90

Page 53
DESCRIPTION OF ITEM:

Item No. 25 White washing.

(a) New surface.

(i) One coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 White lime 1.87 kg 0.00 per kg -


2 Rice 0.117 kg 0.00 per kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Colly skilled 0.12 No. 0.00 per day -


2 Cooly un-skilled 0.06 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 54
DESCRIPTION OF ITEM:

Item No. 25 White washing.

(a) New surface.

(ii) Two coats.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 White lime 2.80 kg 0.00 per kg -


2 Rice 0.175 kg 0.00 per kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Colly skilled 0.18 No. 0.00 per day -


2 Cooly un-skilled 0.09 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 55
DESCRIPTION OF ITEM:

Item No. 25 White washing.

(a) New surface.

(iii) Three coats.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 White lime 3.73 kg 0.00 per kg -


2 Rice 0.233 kg 0.00 per kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Colly skilled 0.23 No. 0.00 per day -


2 Cooly un-skilled 0.12 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 56
DESCRIPTION OF ITEM:

Item No. 25 White washing.

(b) Old surface.

(i) One coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 White lime 1.40 kg 0.00 per kg -


2 Rice 0.088 kg 0.00 per kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Colly skilled 0.12 No. 0.00 per day -


2 Cooly un-skilled 0.06 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 57
DESCRIPTION OF ITEM:

Item No. 25 White washing.

(b) Old surface.

(ii) Two coats.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 White lime 2.33 kg 0.00 per kg -


2 Rice 0.146 kg 0.00 per kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Colly skilled 0.18 No. 0.00 per day -


2 Cooly un-skilled 0.09 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 58
DESCRIPTION OF ITEM:

Item No. 26 (a) Gobri leeping on wall.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Mud (good earth) 0.25 Cft 0.00 per kg -


2 Cowdung 4.00 kg 0.00 per kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.15 No. 0.00 per day -


2 Bahishti 0.06 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 59
DESCRIPTION OF ITEM:

Item No. 26 (b) Gobri leeping over roofs.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Mud (good earth) 0.25 Cft 0.00 per kg -


2 Cowdung 4.00 kg 0.00 per kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 0.12 No. 0.00 per day -


2 Bahishti 0.06 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 60
DESCRIPTION OF ITEM:

Item No. 27 Striking joints of burnt bricks in lime or cement mortar.

Detail Unit Rate (British System) per 100 Sft


Rate
Qty Per Unit Amount (Rs.)

LABOUR (For 125 Sft)

1 Mason 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say -
Labour rate per Sqm Rs. 0.00 Say -

DESCRIPTION OF ITEM:

Item No. 28 Extra for lime Mud or cement plaster and pointing from 20' and above (for
each Addl: 10' height).

Detail Unit Rate (British System) per 100 Sft


Rate
Qty Per Unit Amount (Rs.)

LABOUR (For 125 Sft)

1 Mason 0.12 No. 0.00 per day -


2 Cooly un-skilled 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say -
Labour rate per Sqm Rs. 0.00 Say -

Page 61
DESCRIPTION OF ITEM:

Item No. 29 Caulking joint of sleeper wall with sand and coaltar.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Coaltar (Bitumen) 4.00 kg 0.00 per kg -


2 Sand 4.00 Cft 0.00 per Cft -
3 Fuel 2.18 Kg. 0.00 per kg. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Cooly skilled 0.50 No. 0.00 per day -


2 Cooly un-skilled 0.50 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 62
DESCRIPTION OF ITEM:

Item No. 30 Caulking joint of sleepers with mud and chopped straw.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Mud 4.00 Cft 0.00per 100 Cft -


2 Chopped Straw 1.50 kg 0.00 per kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Cooly skilled 0.50 No. 0.00 per day -


2 Cooly un-skilled 0.50 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 63
DESCRIPTION OF ITEM:

Item No. 31 Extra cost of labour and material for red oxide pigment in cement pointing
to match with the colour of bricks.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Red oxide pigment 2.50 lbs 0.00 per gln. -


0.25 gln
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR

for mixing red oxide in mortar


1 Cooly skilled 0.25 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 64
DESCRIPTION OF ITEM:

Item No. 32 (i) Providing grooved cement plaster 3/8" (10 mm) thick ratio (1 : 3) over
existing plastered and rough surface upto 20' height.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.66 bag 0.00 bags -


2 Sand 2.55 Cft 0.00 Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 1.00 No. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.01 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 65
DESCRIPTION OF ITEM:

Item No. 32 (ii) " (12 mm) thick

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.88 bag 0.00 per bag -


2 Sand 3.40 Cft 0.00 per Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 125 Sft)

1 Mason 1.00 No. 0.00 per day -


2 Cooly un-skilled 1.00 No. 0.00 per day -
3 Bahishti 0.25 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Composit rate per 100 Sft Rs. 0.00 Say -


Composite rate per Sqm Rs. 0.00 Say -

Page 66
DESCRIPTION OF ITEM:

Item No. 33 Providing & fitting expanded metal edge bead for corner's with nail on
both sides of edges.

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Edge bead (5" wide mesh 3/8" x " 1.00 Rft. 0.00 Per Rft. -
2" wide on each side of siled
strip 1" wide T 1 No.11)

2 Nails 0.012 Kg. 0.00 Per Kg. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (For 84 Rft)

1 Skilled Cooly 1.00 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total rate for 84 Rft -

ITEM RATES

Labour rate per Rft Rs. 0.00 Say -


Labour rate per R.M Rs. 0.00 Say -

Composit rate per Rft Rs. 0.00 Say -


Composite rate per R.M Rs. 0.00 Say -

Page 67
DESCRIPTION OF ITEM:

Item No. 34 Petty repair's to fire place.

(i) Single

Detail Unit Rate (British System) per each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.076 Bag 0.00 Bag -


Sand 0.38 Cft. 0.00 % Cft. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total (0.01)

LABOUR

1 Mason 0.14 No. 0.00 per day -


2 Cooly un-skilled 0.14 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate for each Rs. 0.00 Say -


Composit rate for each Rs. Say -

Page 68
DESCRIPTION OF ITEM:

Item No. 34 Petty repairs to fire place.

(ii) Double

Detail Unit Rate (British System) per each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

Cost of cement and sand As per item 34 (i)= Rs. x 2

LABOUR
As per item 34 ( - x 2 -

ITEM RATES

Labour rate for each Rs. 0.00 Say -


Composit rate for each Rs. 0.00 Say -

Page 69
DESCRIPTION OF ITEM:

Item No. 35 Petty repair's to main room

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.200 Bag 0.00 Bag -


2 Sand 1.15 Cft. 0.00 % Cft. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR

1 Mason 0.25 No. 0.00 per day -


2 Cooly un-skilled 0.34 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say -


Composit rate for Each Rs. 0.00 Say -

Page 70
DESCRIPTION OF ITEM:

Item No. 36 Petty repair's to small rooms.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.100 Bag 0.00 Bag -


2 Sand 0.57 Cft. 0.00 % Cft. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR

1 Mason 0.125 No. 0.00 per day -


2 Cooly un-skilled 0.17 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say -


Composit rate for Each Rs. 0.00 Say -

Page 71
DESCRIPTION OF ITEM:

Item No. 37 Petty repair's to verandah.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.16 Bag 0.00 Bag -


2 Sand 0.91 Cft. 0.00 % Cft. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR

1 Mason 0.25 No. 0.00 per day -


2 Cooly un-skilled 0.34 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say -


Composit rate for Each Rs. 0.00 Say -

Page 72
DESCRIPTION OF ITEM:

Item No. 38 Extra labour for white washing colour washing, priming coat and
distempering etc from 20 ft. (6 metre) height and above, requiring
scaffolding for every additional 10 ft. (3 metre) height, or part thereof.

Detail Unit Rate (British System) per 100 Sft (per coat)

Qty Rate Per Unit Amount (Rs.)

LABOUR (For 125 Sft)

1 Cooly skilled 0.02 No. 0.00 per day -


2 Cooly un-skilled 0.01 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say -


Labour rate per Sqm Rs. 0.00 Say -

Page 73
CHAPTER NO. 7

BRICK WORK
DESCRIPTION OF ITEM:

Item No. 1 Pucca brick work in mud mortar in building.

(i) In foundation and plinth.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Good earth or stiff clay for mud master 35.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 1.50 Nos. per day


2 Coolies unskilled 2.00 Nos. per day
3 Bahishti 0.13 No per day

For Mud Mortar

1 Cooly unskilled 0.67 No. per day


2 Bahishty 0.33 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate per 100 Cft Rs. Say
Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 1
DESCRIPTION OF ITEM:

Item No. 1 Pucca brick work in mud mortar in building.

(ii) In ground floor.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Good earth or stiff clay for mud master 35.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 3.00 Nos. per day
3 Bahishti 0.13 No. per day

For Mud Mortar

1 Cooly unskilled 0.67 No. per day


2 Bahishty 0.33 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 2
DESCRIPTION OF ITEM:

Item No. 2 Add extra labour in item No.1 for brick work in

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft


First Floor

1 Mason 0.25 No. per day


2 Cooly unskilled 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate per 100 Cft
Say
Labour rate per Cum
Say
LABOUR for 125 Cft
Second Floor

1 Masons 0.75 No. per day


2 Coolies unskilled 2.00 Nos. per day
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft
Say
Labour rate per Cum
Say

Page 3
Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft


Third Floor

1 Masons 1.25 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate per 100 Cft
Say
Labour rate per Cum
Say
LABOUR for 125 Cft
4th & Subsequent Floor

1 Masons 2.25 Nos. per day


2 Coolies unskilled 4.50 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per cum Rs. Say

Page 4
DESCRIPTION OF ITEM:

Item No. 3 Pucca brick work in mud mortar other than building.

(i) Upto 20 ft. (6 metre) high.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Good earth or stiff clay 35.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Mud Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.33 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 5
DESCRIPTION OF ITEM:

Item No. 3 Pucca brick work in mud morter other than building:

(ii) Extra labour for every 5.0' (1.5 metre) additional height
thereof.

Detail Unit Rate (British System) per 100 Cft


Rate
Qty Per Unit Amount (Rs.)

LABOUR for 125 Cft

1 Mason 0.25 No. per day


2 Cooly unskilled 1.00 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Page 6
DESCRIPTION OF ITEM:

Item No. 4 (i) Pucca brick work in foundation & plinth in

Cement sand mortar Ratio (1:2).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 8.00 bags per bag
3 Sand 20.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

LABOUR for 125 Cft


For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 7
DESCRIPTION OF ITEM:

Item No. 4 (i) Pucca brick work in foundation & plinth in:

Cement sand mortar Ratio (1:3).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 6.00 bags per bags
3 Sand 22.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

LABOUR for 125 Cft


For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 8
DESCRIPTION OF ITEM:

Item No. 4 (i) Pucca brick work in foundation & plinth in:

Cement sand mortar Ratio (1:4).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 4.80 bags per bag
3 Sand 24.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 9
DESCRIPTION OF ITEM:

Item No. 4 (i) Pucca brick work in foundation & plinth in:

Cement sand mortar Ratio (1:5).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 4.00 bags per bag
3 Sand 25.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 10
DESCRIPTION OF ITEM:

Item No. 4 (i) Pucca brick work in foundation & plinth in

Cement sand mortar Ratio (1:6).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 3.40 bags per bag
3 Sand 25.70 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

LABOUR for 125 Cft


For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 11
DESCRIPTION OF ITEM:

Item No. 4 (i) Pucca brick work in foundation & plinth in

Cement sand mortar Ratio (1:7).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 3.00 bags per bag
3 Sand 26.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

LABOUR for 125 Cft


For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 12
DESCRIPTION OF ITEM:

Item No. 4 (i) Pucca brick work in foundation & plinth in

Cement sand mortar Ratio (1:8).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Bricks 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 2.66 bags per bag
3 Sand 26.67 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 13
DESCRIPTION OF ITEM:

Item No. 4 (ii) Pucca brick work in foundation & plinth in

Lime cement sand mortar Ratio (1:1:6).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 3.20 bags per bag
3 Slaked lime 59.72 kg per kg
4 Sand 24.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs.

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 14
DESCRIPTION OF ITEM:

Item No. 4 (ii) Pucca brick work in foundation & plinth in:

Lime cement sand mortar Ratio (1:1:7).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 2.85 bags per bag
3 Slaked lime 53.00 kg per kg
4 Sand 24.78 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 15
DESCRIPTION OF ITEM:

Item No. 4 (ii) Pucca brick work in foundation & plinth in

Lime cement sand mortar Ratio (1:1:8).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 2.56 bags per bag
3 Slaked lime 47.78 kg per kg
4 Sand 25.60 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 16
DESCRIPTION OF ITEM:

Item No. 4 (ii) Pucca brick work in foundation & plinth in

Lime cement sand mortar Ratio (1:1:9).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 2.32 bags per bag
3 Slaked lime 43.30 kg per kg
4 Sand 26.20 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs.

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 17
DESCRIPTION OF ITEM:

Item No. 4 (ii) Pucca brick work in foundation & plinth in

Lime cement sand mortar Ratio (1:1:10).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 2.14 bags per bag
3 Slaked lime 39.94 kg per kg
4 Sand 26.66 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 18
DESCRIPTION OF ITEM:

Item No. 4 (iii) Lime, sand mortar Ratio (1:2).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL
1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.
2 Lime Slaked 174.30 Kg. Per Kg.
3 Sand 23.33 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.50 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate per 100 Cft Rs. Say
Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 19
DESCRIPTION OF ITEM:

Item No. 5 (i) Pacca brick work in ground floor (including striking of jo

Cement sand mortar Ratio (1:2).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 8.00 bags per bag
3 Sand 20.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 20
DESCRIPTION OF ITEM:

Item No. 5 (i) Pacca brick work in ground floor (including striking of jo

Cement sand mortar Ratio (1:3).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 6.00 bags per bag
3 Sand 22.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 21
DESCRIPTION OF ITEM:

Item No. 5 (i) Pacca brick work in ground floor (including striking of jo

Cement sand mortar Ratio (1:4).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 4.80 bags per bag
3 Sand 24.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 22
DESCRIPTION OF ITEM:

Item No. 5 (i) Pacca brick work in ground floor (including striking of jo

Cement sand mortar Ratio (1:5).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 4.00 bags per bag
3 Sand 25.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 23
DESCRIPTION OF ITEM:

Item No. 5 (i) Pacca brick work in ground floor (including striking of jo

Cement sand mortar Ratio (1:6).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 3.40 bags per bag
3 Sand 25.70 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 24
DESCRIPTION OF ITEM:

Item No. 5 (i) Pacca brick work in ground floor (including striking of jo

Cement sand mortar Ratio (1:7).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 3.00 bags per bag
3 Sand 26.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 25
DESCRIPTION OF ITEM:

Item No. 5 (i) Pacca brick work in ground floor (including striking of jo

Cement sand mortar Ratio (1 : 8).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 2.66 bags per bag
3 Sand 26.57 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 26
DESCRIPTION OF ITEM:

Item No. 5 (ii) Lime cement sand mortar Ratio (1:1:6).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 59.72 kg per kg
3 Cement 3.20 bags per bag
4 Sand 24.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 27
DESCRIPTION OF ITEM:

Item No. 5 (ii) Lime cement sand mortar Ratio (1 : 1 : 7).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 53.37 kg per kg
3 Cement 2.85 bags per bag
4 Sand 24.78 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 28
DESCRIPTION OF ITEM:

Item No. 5 (ii) Lime cement sand mortar Ratio (1:1:8).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 47.78 kg per kg
3 Cement 2.56 bags per bag
4 Sand 25.60 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 29
DESCRIPTION OF ITEM:

Item No. 5 (ii) Lime cement sand mortar Ratio ( 1 : 1 : 9 ).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 43.30 kg per kg
3 Cement 2.32 bags per bag
4 Sand 26.20 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 30
DESCRIPTION OF ITEM:

Item No. 5 (ii) Lime cement sand mortar Ratio ( 1 : 1 : 10 ).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 40.00 kg per kg
3 Cement 2.14 bags per bag
4 Sand 26.66 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 31
DESCRIPTION OF ITEM:

Item No. 5 (iii) Lime sand mortar Ratio (1:2).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Lime 174.30 kg per kg
3 Sand 23.33 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.25 No. per day

For Cement Mortar

1 Cooly unskilled 0.83 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 32
DESCRIPTION OF ITEM:

Item No. 6 Add extra labour in item No.5 for brick work in:-

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft


First Floor

1 Mason 0.25 No. per day


2 Cooly unskilled 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate per 100 Cft Rs.
Say
Labour rate per Cum Rs.
Say

LABOUR for 125 Cft


Second Floor

1 Masons 0.75 No. per day


2 Coolies unskilled 2.00 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate per 100 Cft Rs.
Say
Labour rate per Cum Rs.
Say

Page 33
Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft


Third Floor

1 Masons 1.25 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate per 100 Cft
Say
Labour rate per Cum
Say
LABOUR for 125 Cft
4th & Subsequent Floor

1 Masons 2.25 Nos. per day


2 Coolies unskilled 4.50 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per cum Rs. Say

Page 34
DESCRIPTION OF ITEM:

Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Cement sand mortar Ratio (1:2).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 8.00 bags per bag
3 Sand 20.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 35
Item No. 7 Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Cement sand mortar Ratio (1:3).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 6.00 bags per bag
3 Sand 22.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 36
DESCRIPTION OF ITEM:

Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Cement sand mortar Ratio (1 : 4).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 4.80 bags per bag
3 Sand 24.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 37
DESCRIPTION OF ITEM:

Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Cement sand mortar Ratio (1 : 5).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 4.00 bags per bag
3 Sand 25.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 38
DESCRIPTION OF ITEM:

Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Cement sand mortar Ratio (1 : 6).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 3.40 bags per bag
3 Sand 25.70 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 39
DESCRIPTION OF ITEM:

Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Cement sand mortar Ratio (1 : 7).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 3.00 bags per bag
3 Sand 26.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 40
DESCRIPTION OF ITEM:

Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Cement sand mortar Ratio (1 : 8).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Cement 2.66 bags per bag
3 Sand 26.67 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 41
DESCRIPTION OF ITEM:

Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Lime, cement, sand mortar Ratio (1 : 1 : 6).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 59.72 kg per kg
3 Cement 3.20 bags per bag
4 Sand 24.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 42
DESCRIPTION OF ITEM:

Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Lime, cement, sand mortar Ratio (1 : 1 : 7).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 53.00 kg per kg
3 Cement 2.85 bags per bag
4 Sand 24.78 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 43
DESCRIPTION OF ITEM:

Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Lime, cement, sand mortar Ratio (1 : 1 : 8).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 47.78 kg per kg
3 Cement 2.56 bags per bag
4 Sand 25.60 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 44
DESCRIPTION OF ITEM:

Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Lime, cement, sand mortar Ratio (1 : 1 : 9).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 43.29 kg per kg
3 Cement 2.32 bags per bag
4 Sand 26.20 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 45
DESCRIPTION OF ITEM:

Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.

Lime, cement, sand mortar Ratio (1 : 1 : 10).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 39.94 kg per kg
3 Cement 2.14 bags per bag
4 Sand 26.66 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 46
DESCRIPTION OF ITEM:

Item No. 7 (iii) Lime, sand, mortar ratio (1 : 2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.


2 Slaked lime 174.30 kg per kg
3 Sand 23.33 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


For Masonry Work

1 Mason 2.50 Nos. per day


2 Coolies unskilled 3.00 Nos. per day

For Cement Mortar

1 Cooly unskilled 1.00 No. per day


2 Bahishty 0.50 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 47
DESCRIPTION OF ITEM:

Item No. 8 Additional extra labour in item No.7 for every 10 ft. (3 m
additional height.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Masons 0.25 No. per day


2 Cooly 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate Per 100 Cft. Rs. Say


Labour Rate Per Cum. Rs. Say

Page 48
DESCRIPTION OF ITEM:

Item No. 9 Extra labour for arch work in brick masonry including labo
centering and de-centering.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Masons 1.50 No. per day


2 Cooly 0.50 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate Per 100 Cft. Rs. Say


Labour Rate Per Cum. Rs. Say

Page 49
DESCRIPTION OF ITEM:

Item No. 10 Extra for Pacca brick work in steining of wells or any oth
circular masonry.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 82.00 No. % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft

1 Mason 1.25 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 50
DESCRIPTION OF ITEM:

Item No. 11 Extra labour for profile and flared walls.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Mason 0.43 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Composit rate per Cum Rs. Say

Page 51
DESCRIPTION OF ITEM:

Item No. 12 Extra labour for Pacca brick work in piers and abutment.

(i) From 10 ft. (3 metre) to 20 ft. (6 metre) height.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Mason 0.12 No. per day


2 Cooly unskilled 0.50 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Composit rate per Cum Rs. Say

Page 52
DESCRIPTION OF ITEM:

Item No. 12 Extra labour for Pacca brick work in piers and abutment.

(ii) Above 20 ft. (6 metre) height.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Mason 0.25 No. per day


2 Cooly unskilled 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Composit rate per Cum Rs. Say

Page 53
DESCRIPTION OF ITEM:

Item No. 13 Extra for face work (half brick thick) using special brick
of Ist class bricks.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Special moulded Stretcher


courses bricks 270.00
2 Header courses 513.00

Total 783.00
Add 5% wastage 39.15
Total 822.15

Difference in cost of special


moulded and ordinary Ist class
bricks

2 Extra cost = 0 - - = 0 %0 Nos.

Contractor's Profit & Ov 20 Percent


Total

Labour rate for 100 Cft Rs. Say


Composit rate per Cum Rs. Say

Page 54
DESCRIPTION OF ITEM:

Item No. 14 Reinforced brick work in lintels of opening, laid in (1:3)


sand mortar including, all labour material forms, moulds,
and shuttering etc., but excluding cost and labour of stee
reinforcement which shall be paid for separately.

Detail Unit Rate (British System) per Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 10.00 No. Nos.


2 Cement 0.11 bag per bag
3 Sand 0.41 Cft % Cft
4 Kikar wood for centring & shuttering
(10 x 1.60 x 0.2) Can be use 20 times 0.002 Cft Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft

1 Mason 0.067 No. per day


2 Cooly unskilled 0.11 No. per day
3 Bahishti 0.023 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per Cft Rs. Say


Composite rate per Cum Rs. Say

Page 55
DESCRIPTION OF ITEM:

Item No. 15 (a) Extra for dressing or chamfering of bricks (special or


architectaral shape).

Detail Unit Rate (British System) per 100 No.

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Mason 3.00 No. per day


2 Cooly unskilled 0.34 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 No. Rs. Say

Page 56
DESCRIPTION OF ITEM:

Item No. 15 (b) All other purposes.

Detail Unit Rate (British System) per 100 No.

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Mason 1.50 No. per day


2 Cooly unskilled 0.17 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 No. Rs. Say

Page 57
DESCRIPTION OF ITEM:

Item No. 16 Peforated Pacca brick walling 114 mm (4") thick in ground
floor in
(i) Mud mortar.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Good earth 8.75 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.00 No. per day


2 Coolies unskilled 1.83 Nos. per day
3 Bahishti 0.23 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 58
DESCRIPTION OF ITEM:

Item No. 16 (ii) Cement sand mortar Ratio (1 : 2).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Cement 2.00 bags per bag
3 Sand 5.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 59
DESCRIPTION OF ITEM:

Item No. 16 (ii) Cement sand mortar Ratio (1:3).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Cement 1.50 bags per bag
3 Sand 5.60 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 60
DESCRIPTION OF ITEM:

Item No. 16 (ii) Cement sand mortar Ratio (1:4).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Cement 1.20 bags per bag
3 Sand 6.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 61
DESCRIPTION OF ITEM:

Item No. 16 (ii) Cement sand mortar Ratio (1:5).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Cement 1.00 bags per bag
3 Sand 6.25 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 62
DESCRIPTION OF ITEM:

Item No. 16 (ii) Cement sand mortar Ratio (1:6).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Cement 0.86 bags per bag
3 Sand 6.40 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 63
DESCRIPTION OF ITEM:

Item No. 16 (ii) Cement sand mortar Ratio (1:7).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Cement 0.75 bags per bag
3 Sand 6.58 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 64
DESCRIPTION OF ITEM:

Item No. 16 (ii) Cement sand mortar Ratio (1:8).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Cement 0.67 bags per bag
3 Sand 6.67 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 65
DESCRIPTION OF ITEM:

Item No. 16 (iii) Lime cement sand mortar Ratio (1 : 1 : 6).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Slaked lime 14.93 kg kg
3 Cement 0.80 bags per bag
4 Sand 6.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 66
DESCRIPTION OF ITEM:

Item No. 16 (iii) Lime cement sand mortar Ratio (1 : 1 : 7).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Slaked lime 13.44 kg per kg
3 Cement 0.71 bags per bag
4 Sand 6.13 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 67
DESCRIPTION OF ITEM:

Item No. 16 (iii) Lime cement sand mortar Ratio (1 : 1 : 8).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Slaked lime 12.32 kg per kg
3 Cement 0.64 bags per bag
4 Sand 6.40 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 68
DESCRIPTION OF ITEM:

Item No. 16 (iii) Lime cement sand mortar Ratio (1 : 1 : 9).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Slaked lime 10.82 kg per kg
3 Cement 0.58 bags per bag
4 Sand 6.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 69
DESCRIPTION OF ITEM:

Item No. 16 (iii) Lime cement sand mortar Ratio (1 : 1 : 10).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 No. Nos.


2 Slaked lime 10.08 kg per kg
3 Cement 0.54 bags per bag
4 Sand 6.70 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 70
DESCRIPTION OF ITEM:

Item No. 16 (iv) Lime cement sand mortar Ratio (1 : 2).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 338.00 Nos. Nos.


2 Slaked lime 43.67 kg per kg
3 Sand 5.58 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.42 Nos. per day
3 Bahishti 0.38 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 71
DESCRIPTION OF ITEM:

Item No. 17 Add. extra labour on item No.15 for pacca brick work.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Sft


First Floor

1 Mason 0.13 No. per day


2 Cooly unskilled 0.50 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate for 100 Sft Rs.
Say
Labour rate per Sqm Rs.
Say

LABOUR for 125 Sft


Second Floor

1 Masons 0.37 No. per day


2 Coolies unskilled 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate for 100 Sft Rs.
Say
Labour rate per Sqm Rs.
Say

LABOUR for 125 Cft


Third Floor

1 Masons 0.63 No. per day


2 Coolies unskilled 1.50 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES
Labour rate for 100 Sft
Say
Labour rate per Sqm
Say

Page 72
LABOUR for 125 Sft
4th & Subsequent Floor

1 Masons 1.12 Nos. per day


2 Coolies unskilled 2.12 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate for 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Page 73
DESCRIPTION OF ITEM:

Item No. 18 (i) Perforated pacca brick walling 9" thick in ground floor in
Mud Mortar

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MUD MORTAR

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Good earth 17.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.25 Nos. per day


2 Coolies unskilled 2.75 Nos. per day
3 Bahishti 0.35 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 74
DESCRIPTION OF ITEM:

Item No. 18 (ii) Cement sand mortar Ratio (1 : 2)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Cement 4.00 bags bags
3 Sand 10.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 75
DESCRIPTION OF ITEM:

Item No. 18 (ii) Cement sand mortar Ratio (1 : 3)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Cement 3.00 bags bags
3 Sand 11.25 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 76
DESCRIPTION OF ITEM:

Item No. 18 (ii) Cement sand mortar Ratio (1 : 4)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Cement 2.40 bags per bag
3 Sand 12.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 77
DESCRIPTION OF ITEM:

Item No. 18 (ii) Cement sand mortar Ratio (1 : 5)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Cement 2.00 bags per bag
3 Sand 12.50 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 78
DESCRIPTION OF ITEM:

Item No. 18 (ii) Cement sand mortar Ratio (1 : 6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Cement 1.72 bags per bag
3 Sand 12.80 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 79
DESCRIPTION OF ITEM:

Item No. 18 (ii) Cement sand mortar Ratio (1 : 7)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Cement 1.50 bags per bag
3 Sand 13.13 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 80
DESCRIPTION OF ITEM:

Item No. 18 (ii) Cement sand mortar Ratio (1 : 8)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Cement 1.33 bags per bag
3 Sand 13.34 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 81
DESCRIPTION OF ITEM:

Item No. 18 (iii) Lime cement sand mortar Ratio (1 : 1 : 6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Slaked lime 29.86 kg per kg
3 Cement 1.60 bags per bag
4 Sand 12.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 82
DESCRIPTION OF ITEM:

Item No. 18 (iii) Lime cement sand mortar Ratio (1 : 1 : 7)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Slaked lime 26.50 kg per kg
3 Cement 1.42 bags per bag
4 Sand 12.39 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 83
DESCRIPTION OF ITEM:

Item No. 18 (iii) Lime cement sand mortar Ratio (1 : 1 : 8)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Slaked lime 23.90 kg per kg
3 Cement 1.28 bags per bag
4 Sand 12.80 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 84
DESCRIPTION OF ITEM:

Item No. 18 (iii) Lime cement sand mortar Ratio (1 : 1 : 9)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Slaked lime 21.65 kg per kg
3 Cement 1.16 bags per bag
4 Sand 13.10 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 85
DESCRIPTION OF ITEM:

Item No. 18 (iii) Lime cement sand mortar Ratio (1 : 1 : 10)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Slaked lime 20.16 kg per kg
3 Cement 1.07 bags per kg
4 Sand 13.33 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 86
DESCRIPTION OF ITEM:

Item No. 18 (iv) Lime sand mortar Ratio (1 : 2)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 675.00 Nos. Nos.


2 Slaked lime 86.97 kg per kg
3 Sand 11.67 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Sft

1 Mason 1.90 Nos. per day


2 Coolies unskilled 3.63 Nos. per day
3 Bahishti 0.55 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 87
DESCRIPTION OF ITEM:

Item No. 19 Extra labour in item No.18 for per perforated pacca brick
work in

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

LABOUR
First Floor

Labour of item No.6 for 100 Cft 0.75


Say
Labour of item No.6 per Cum 0.75
Say
LABOUR
Second Floor

Labour of item No.6 for 100 Cft 0.75


Say
Labour of item No.6 per Cum 0.75
Say
LABOUR
Third Floor

Labour of item No.6 for 100 Cft 0.75


Say
Labour of item No.6 per Cum 0.75
Say
LABOUR
Fourth & Subsequent Floor

Labour of item No.6 for 100 Cft 0.75


Say
Labour of item No.6 per Cum 0.75
Say

Page 88
DESCRIPTION OF ITEM:

Item No. 20 Fire brick masonary in fire clay mortar.

(i) Upto 20 ft. (6 metre) height including all charges.

Detail Unit Rate (British System) per Cft

Qty Rate Per UnitAmount (Rs.)

Per 100 Cft


MATERIAL

1 Fire clay bricks 9" x 4" x 3" 1350.00 No. Each


2 Fire resistant Cement 8.80 bags per bag
3 Brick grinded sand 22.00 Cft per Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft


for masonary work

1 Mason 3.00 Nos. per day


2 Coolies 3.00 Nos. per day
3 Bahishti 0.25 No. per day

for mortar

1 Cooly 1.00 No. per day


2 Bahishti 0.25 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per Cft Rs. Say


Composite rate per Cum Rs. Say

Page 89
DESCRIPTION OF ITEM:

Item No. 20 Fire brick masonary in fire clay mortar.

(ii) Extra for every 1.5 metre additional height.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Mason 0.25 No. per day


2 Cooly unskilled 1.00 No per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Page 90
DESCRIPTION OF ITEM:

Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with (1") 25 mm wide 18 gauge hoop iron.

(i) 4" (114 mm) thick walling with hoop iron bouding 6"
(150 mm) apart.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 525.00 Nos. Nos.


2 Cement 2.40 bags per bag
3 Sand 9.00 Cft % Cft
4 Hoop iron 45.00 lbs Per Kg.
20.41 Kg.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR

1 Mason 1.00 No. per day


2 Coolies unskilled 1.25 Nos. per day
3 Bahishti 0.25 No. per day
4 Black-smith 0.15 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 91
DESCRIPTION OF ITEM:

Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with 1" (25 mm) wide 18 gauge hoop iron.

(ii) 4" (114 mm) thick walling with hoop iron bouding
12" (300 mm) apart.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 525.00 Nos. Nos.


2 Cement 2.40 bags per bag
3 Sand 9.00 Cft % Cft
4 Hoop iron 22.50 lbs Per Kg.
10.20 kg.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR

1 Mason 1.00 No. per day


2 Coolies unskilled 1.00 No. per day
3 Bahishti 0.25 No. per day
4 Black-smith 0.10 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 92
DESCRIPTION OF ITEM:

Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with 1" (25 mm) wide 18 gauge hoop iron.

(iii) 3" (75 mm) thick walling with hoop iron bouding 6"
(150 mm) apart.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 350.00 Nos. Nos.


2 Cement 1.80 bags per bag
3 Sand 6.50 Cft % Cft
4 Hoop iron 45.00 lbs Per Kg.
20.41 Kg.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft

1 Mason 0.75 No. per day


2 Coolies unskilled 1.00 No. per day
3 Bahishti 0.20 No. per day
4 Black-smith 0.15 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 93
DESCRIPTION OF ITEM:

Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with 1" (25 mm) wide 18 gauge hoop iron.

(iv) 3" (75 mm) thick walling with hoop iron bouding 12"
(300 mm) apart.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Pacca bricks 9" x 4" x 3" 350.00 Nos. Nos.


2 Cement 1.80 bags per bag
3 Sand 6.50 Cft % Cft
4 Hoop iron 20.00 lbs Per Kg.
9.070 Kg.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft

1 Mason 0.75 No. per day


2 Coolies unskilled 1.00 No. per day
3 Bahishti 0.20 No. per day
4 Black-smith 0.15 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft Rs. Say


Composite rate per Sqm Rs. Say

Page 94
DESCRIPTION OF ITEM:

Item No. 22 Ghilafi work (1 brick thick wall).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 B.B in mud ( of item No.1) x


2 Sundried bricks ( of item No.24) x

Total

LABOUR for 125 Cft

1 Mason 2.00 Nos. per day


2 Coolies unskilled 3.67 Nos. per day
3 Bahishti 0.50 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 95
DESCRIPTION OF ITEM:

Item No. 23 Dry brick pitching.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Ist class burnt brick 1350.00 Nos. Nos.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR

1 Mason 1.00 No. per day


2 Coolies unskilled 2.00 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 96
DESCRIPTION OF ITEM:

Item No. 24 Sun dried bricks in Mud mortar.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Sun dried bricks 1350.00 Nos. Nos.


2 Siff clay 35.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Cft

1 Mason 1.50 Nos. per day


2 Coolies unskilled 3.50 Nos. per day
3 Bahishti 0.25 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 97
DESCRIPTION OF ITEM:

Item No. 25 Pise wall (mud walling).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR for 125 Cft

1 Coolies skilled 1.00 No. per day


2 Coolies unskilled 1.50 Nos. per day
3 Bahishti 0.50 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 98
DESCRIPTION OF ITEM:

Item No. 26 Providing Eave brick moulded weathered and throated with b
brick or drip course cornice in (1 : 3) cement mortar.

(i) 3" (76 mm) thick drip course.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

MATERIAL (FOR 100 RFT.)

1 Moulded brick 280.00 Nos. Nos.


2 Cement for laying and plastering 1.50 bag per bag
3 Sand 5.00 Cft % Cft
Deduct cost of ordinary bricks 140 Nos. Nos.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR (FOR 125 RFT.)

1 Mason 1.75 Nos. per day


2 Coolies unskilled 1.75 Nos. per day
3 Bahishti 0.25 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per Rft Rs. Say


Composite rate per R.M Rs. Say

Page 99
DESCRIPTION OF ITEM:

Item No. 26 Providing Eave brick moulded weathered and throated with b
brick or drip cornice in (1 : 3) cement mortars.

(ii) 4" (114 mm) thick drip course cornice.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

MATERIAL (FOR 100 RFT.)

1 Brick moulded I/C wastage 420.00 Nos. Nos.


2 Cement for laying and plastering 1.75 bag per bag
3 Sand 6.00 Cft % Cft
Deduct cost of ordinary bricks 210.00 Nos. Nos.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR (FOR 125 RFT)

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.00 Nos. per day
3 Bahishti 0.25 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per 100 Rft Rs. Say


Composite rate per R.M Rs. Say

Page 100
DESCRIPTION OF ITEM:

Item No. 26 Providing Eave brick moulded weathered and throated with b
brick or drip cornice in (1 : 3) cement mortar.

(iii) 4" (114 mm) thick eave brick with back brick.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

MATERIAL (FOR 100 RFT)

1 Brick moulded (including wastage) 465.00 Nos. Nos.


2 Back bricks ordinary 465.00 Nos. Nos.
3 Cement 1.20 bag per bag
4 Sand 5.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR (FOR 125 RFT.)

1 Mason for laying 1.00 No. per day


2 Coolies unskilled 2.00 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per Rft Rs. Say


Composite rate per R.M Rs. Say

Page 101
DESCRIPTION OF ITEM:

Item No. 27 Providing & laying dressed or moulded brick cornice in ( 1


cement mortar, plastering or pointing complete.

(i) One brick.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

MATERIAL (FOR 100 RFT.)

1 Pacca bricks I/C 10% wastage


As the rate is only for the projected protion
to the brick required 60.00 Nos. Nos.
2 Cement for laying & plastering or pointi 1.60 bag per bag
3 Sand for laying & plastering or plasteri 6.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Rft

1 Mason 2.00 Nos. per day


2 Coolies unskilled 2.00 Nos. per day
3 Bahishti 0.25 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per Rft Rs. Say


Composite rate per R.M Rs. Say

Page 102
DESCRIPTION OF ITEM:

Item No. 27 Providing & laying dressed or moulded brick cornice in ( 1


cement mortar, plastering or pointing complete.

(ii) Two brick.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

MATERIAL (FOR 100 RFT.)

1 Pacca bricks 175.00 Nos. Nos.


2 Cement for laying & plastering 5.00 bags per bag
3 Sand for laying & plastering 18.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Rft

1 Mason 3.00 Nos. per day


2 Coolies unskilled 3.00 Nos. per day
3 Bahishti 0.25 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per Rft Rs. Say


Composite rate per R.M Rs. Say

Page 103
DESCRIPTION OF ITEM:

Item No. 27 Providing & laying dressed or moulded brick cornice in ( 1


cement mortar, plastering or pointing complete.

(iii) Three bricks.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

MATERIAL (FOR 100 RFT.)

1 Pacca bricks 270.00 Nos. Nos.


2 Cement for laying & plastering 8.00 bags per bag
3 Sand for laying & plastering 60.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Rft

1 Mason 4.00 Nos. per day


2 Coolies unskilled 4.00 Nos. per day
3 Bahishti 0.34 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per Rft Rs. Say


Composite rate per R.M Rs. Say

Page 104
DESCRIPTION OF ITEM:

Item No. 27 Providing & laying dressed or moulded brick cornice in ( 1


cement mortar, plastering or pointing complete.

(iv) Four brick.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

MATERIAL FOR 100 RFT.)

1 Pacca bricks 580.00 Nos. Nos.


2 Cement for laying & plastering 10.00 bags per bag
3 Sand for laying & plastering 37.00 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 125 Rft

1 Mason 5.00 Nos. per day


2 Coolies unskilled 5.00 Nos. per day
3 Bahishti 0.50 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per Rft Rs. Say


Composite rate per R.M Rs. Say

Page 105
DESCRIPTION OF ITEM:

Item No. 28 Cleaning brick dismentled from kacha pacca masonry.

Detail Unit Rate (British System) per 1000 No.

Qty Rate Per UnitAmount (Rs.)

LABOUR for 1250 Nos.

1 Cooly unskilled 1.75 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rat per 1000 No. Rs. Say

DESCRIPTION OF ITEM:

Item No. 29 Scraping bricks dismantled from pacca masonary.

Detail Unit Rate (British System) per 1000 No.

Qty Rate Per UnitAmount (Rs.)

LABOUR for 1250 Nos.

1 Cooly unskilled 3.30 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rat per 1000 No. Rs. Say

Page 106
DESCRIPTION OF ITEM:

Item No. 30 Supplying and filling sand under floors or plugging in wel

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Sand 100.00 Nos. % Nos.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 150 Cft

1 Cooly unskilled 0.50 Nos. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft. Rs. Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft. Rs. Say


Composite rate per Cum. Rs. Say

Page 107
DESCRIPTION OF ITEM:

Item No. 31 Providing and laying 2" (50 mm) thick projected tile bank
(1: 2) cement sand mortar with hoop iron 1" (25 mm) wide 1
SWG flat iron sheet 9" (225 mm) apart.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

Rate Analysis for 8 Rft


MATERIAL

1 Title 225 x 114 x 40 mm title 43.00 Nos. Nos.


2 Cement 0.09 bag per bag
3 Sand 0.20 Cft % Cft
4 Cost of hoop iron 3.00 Kg. Per Kg.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR

1 Mason 0.50 No. per day


2 Coolies unskilled 0.50 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per R.M Rs. Say

Composite rate per Rft Rs. Say


Composite rate per R.M Rs. Say

Page 108
DESCRIPTION OF ITEM:

Item No. 32 Ist class brick tiles (9" 4" x 1") 225 x 114 x 40 mm cla
76 mm thick laid in cement sand mortar recifered with hoop
strips placed at 2 ft. (600 mm) apart vertically.

(i) Ratio (1 : 3).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Brick tiles 9" x 4" x 1" 810.00 No. Nos.


2 Cement 2.40 bags per bag
3 Sand 9.00 Cft % Cft
4 Hoop iron 4.54 Kg. per Kg.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR

1 Mason 1.00 No. per day


2 Coolies unskilled 1.00 No. per day
3 Bahishti 0.25 No. per day
4 Black-smith 0.10 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft. Rs. Say


Composite rate per Sqm Rs. Say

Page 109
DESCRIPTION OF ITEM:

Item No. 32 Ist class brick tiles (9" 4" x 1") 225 x 114 x 40 mm cla
76 mm thick laid in cement sand mortar recifered with hoop
strips placed at 2 ft. (600 mm) apart vertically.

(ii) Ratio (1 : 4).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Brick tiles 9" x 4" x 1" 810.00 No. Nos.


2 Cement 1.92 bags per bag
3 Sand 9.60 Cft % Cft
4 Hoop iron 4.54 Kg. per Kg.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR

1 Mason 1.00 No. per day


2 Coolies unskilled 1.00 No. per day
3 Bahishti 0.25 No. per day
4 Black-smith 0.10 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft. Rs. Say


Labour rate per Sqm Rs. Say

Composite rate per 100 Sft. Rs. Say


Composite rate per Sqm Rs. Say

Page 110
DESCRIPTION OF ITEM:

Item No. 33 Chamfering sides of head regulators and masonry wall to


increase width.

Detail Unit Rate (British System) per Sft

Qty Rate Per UnitAmount (Rs.)

LABOUR (FOR 30 SFT)

1 Mason 1.00 No. per day


2 Cooly unskilled 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

Labour rate per Sft Rs. Say


Labour rate per Sqm Rs. Say

Page 111
DESCRIPTION OF ITEM:

Item No. 34 Replacing kallar eaten bricks.

Detail Unit Rate (British System) per Bricks

Qty Rate Per UnitAmount (Rs.)

Assume 60 Bricks
MATERIAL

1 Bricks 50.00 Nos. Nos.


2 Cement 0.005 Bag Bag
3 Sand 0.026 Cft % Cft.

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR

1 Mason 2.00 No. per day


2 Cooly 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Brick Rs. Say


Composit rate per Brick Rs. Say

Page 112
DESCRIPTION OF ITEM:

Item No. 35 Repairing corner's of bridges and other hydraulic


masoney works.

Detail Unit Rate (British System) per No. / Assumed for 1

Qty Rate Per UnitAmount (Rs.)

MATERIAL

1 Brick tiles 9" x 4" x 1" 10.00 No. Nos.


2 Cement 0.08 bags per bag
3 Sand 0.25 Cft % Cft

Total
Contractor's Profit & Ov 20 Percent
Total

LABOUR for 1.5 No.

1 Mason 0.25 No. per day


2 Coolies unskilled 0.25 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

ITEM RATES

Labour rate per Each No. Rs. Say


Composite rate per Each No. Rs. Say

Page 113
DESCRIPTION OF ITEM:

Item No. 36 Extra labour for drains of bath roons etc.

Detail Unit Rate (British System) per Lft

Qty Rate Per UnitAmount (Rs.)

Assumed for 40 Lft


LABOUR

1 Mason 1.00 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

Labour rate per Lft Rs. Say


Labour rate per Meter Rs. Say

DESCRIPTION OF ITEM:

Item No. 37 Maroo corners.

Detail Unit Rate (British System) per No.

Qty Rate Per UnitAmount (Rs.)

LABOUR for 1.25 No.

1 Mason 0.20 No. per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total

Labour rate per Each No. Rs. Say

Page 114
CHAPTER NO. 6

CONCRETE
DESCRIPTION OF ITEM:

Item No. 1 Mud concrete in foundation including watering and ramming using bri
or stone ballast 1" (40 mm) gauge.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brick/Stone Ballast 100.00 Cft - % Cft


2 Earth 50.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 0.13 No. - per day


2 Cooly un-skilled 4.00 Nos. - per day
3 Bahisthi 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composite rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 1
DESCRIPTION OF ITEM:

Item No. 2 Dry Ramming brick or stone ballast 1" to 2 (40 mm to 50 mm) gauge.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brick/Stone Ballast 110.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Coolies un-skilled 3.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composite rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 2
DESCRIPTION OF ITEM:

Item No. 3 Cement concrete brick or stone ballast 1" to 2" (40 to 50 mm) gaug
foundation and plinth.

(a) Ratio (1 : 3 : 6)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 13.00 Bags - per bag


2 Sand 46.00 Cft - % Cft
3 Brick/Stone ballast 92.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 0.25 No. - per day


2 Cooly un-skilled 5.00 Nos. - per day
3 Bahisthi 0.50 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composite rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 3
DESCRIPTION OF ITEM:

Item No. 3 Cement concrete brick or stone ballast 1" to 2" (40 to 50 mm) gaug
foundation and plinth.

(b) Ratio (1 : 4 : 8)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 9.60 bags - per bag


2 Sand 48.00 Cft - % Cft
3 Brick/Stone ballast 96.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 0.25 No. - per day


2 Cooly un-skilled 5.00 Nos. - per day
3 Bahisthi 0.50 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composite rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 4
DESCRIPTION OF ITEM:

Item No. 3 Cement concrete brick or stone ballast 1" to 2" (40 to 50 mm) gaug
foundation and plinth.

(c) Ratio (1 : 5 : 10)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 7.80 bags - per bag


2 Sand 49.00 Cft - % Cft
3 Bricks/stone ballast 98.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 0.25 No. - per day


2 Cooly un-skilled 5.00 Nos. - per day
3 Bahisthi 0.50 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composite rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 5
DESCRIPTION OF ITEM:

Item No. 3 Cement concrete brick or stone ballast 1" to 2" (40 to 50 mm) gaug
foundation and plinth.

(d) Ratio (1 : 6 : 12)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 6.50 bags - per bag


2 Sand 49.00 Cft - % Cft
3 Bricks/stone ballast 98.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 0.25 No. - per day


2 Cooly un-skilled 5.00 Nos. - per day
3 Bahisthi 0.50 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composite rate per 100 Cft Rs. Say


Composite rate per Cum Rs. Say

Page 6
DESCRIPTION OF ITEM:

Item No. 3 Cement concrete brick or stone ballast 1" to 2" (40 to 50 mm) gaug
foundation and plinth.

(e) Ratio (1 : 6 : 18)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 5.00 bags - per bag


2 Sand 37.00 Cft - % Cft
3 Bricks/stone ballast 112.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 0.25 No. - per day


2 Cooly un-skilled 5.00 Nos. - per day
3 Bahisthi 0.50 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composit rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 7
DESCRIPTION OF ITEM:

Item No. 3 Cement concrete brick or stone ballast 1" to 2" (40 to 50 mm) gaug
foundation and plinth.

(f) Ratio (1 : 7 : 20)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 4.40 bags - per bag


2 Sand 38.50 Cft - % Cft
3 Bricks/stone ballast 110.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 0.25 No. - per day


2 Cooly un-skilled 5.00 Nos. - per day
3 Bahisthi 0.50 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composit rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 8
DESCRIPTION OF ITEM:

Item No. 4 Extra on item No.3 above for Sedimentation tank or filter beds of P
Health Engineering Works.

(a) in bed.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Mason 0.60 No. - per day


2 Cooly un-skilled 1.00 Nos. - per day
3 Bahisthi 0.10 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES
Labour rate per 100 Cft Rs. - Say
Labour rate per Cum Rs. - Say

DESCRIPTION OF ITEM:

Item No. 4 Extra on item No.3 above for Sedimentation tank or filter beds of P
Health Engineering Works.

(b) on slope.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Mason 1.00 No. - per day


2 Cooly un-skilled 1.40 Nos. - per day
3 Bahisthi 0.10 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. Say


Labour rate per Cum Rs. Say

Page 9
DESCRIPTION OF ITEM:

Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).

(a) Ratio (1 : 1 : 2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 31.50 bags - per bag


2 Sand 39.00 Cft - % Cft
3 Aggregate (Stone) 78.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 No. - per day


2 Cooly un-skilled 6.00 Nos. - per day
3 Bahisthi 0.60 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composite rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 10
DESCRIPTION OF ITEM:

Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).

(b) Ratio (1 : 1 : 1)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 31.50 bags - per bag


2 Sand 58.00 Cft - % Cft
3 Aggregate 58.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 No. - per day


2 Cooly un-skilled 6.00 Nos. - per day
3 Bahisthi 0.60 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composite rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 11
DESCRIPTION OF ITEM:

Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).

(c) Ratio (1 : 1 : 3)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 22.50 bags - per bag


2 Sand 42.00 Cft - % Cft
3 Aggregate 84.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 No. - per day


2 Cooly un-skilled 6.00 Nos. - per day
3 Bahisthi 0.60 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composite rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 12
DESCRIPTION OF ITEM:

Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).

(d) Ratio (1 : 2 : 3)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 21.00 bags - per bag


2 Sand 52.00 Cft - % Cft
3 Aggregate 78.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 No. - per day


2 Cooly un-skilled 6.00 Nos. - per day
3 Bahisthi 0.60 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say 0.00


Labour rate per Cum Rs. - Say 0.00

Composite rate per 100 Cft Rs. - Say 0.00


Composite rate per Cum Rs. - Say 0.00

Page 13
DESCRIPTION OF ITEM:

Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).

(e) Ratio (1 : 3 : 3)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 17.60 bags - per bag


2 Sand 66.00 Cft - % Cft
3 Aggregate 66.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 No. - per day


2 Cooly un-skilled 6.00 Nos. - per day
3 Bahisthi 0.60 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composite rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 14
DESCRIPTION OF ITEM:

Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).

(f) Ratio (1 : 2 : 4)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 17.60 bags - per bag


2 Sand 44.00 Cft - % Cft
3 Aggregate 88.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 No. - per day


2 Cooly un-skilled 6.00 Nos. - per day
3 Bahisthi 0.60 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composite rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 15
DESCRIPTION OF ITEM:

Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).

(g) Ratio (1 : 2 : 6)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 13.70 bags - per bag


2 Sand 34.00 Cft - % Cft
3 Aggregate 102.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 No. - per day


2 Cooly un-skilled 6.00 Nos. - per day
3 Bahisthi 0.60 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composit rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 16
DESCRIPTION OF ITEM:

Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).

(h) Ratio (1 : 3 : 6)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 13.00 bags - per bag


2 Sand 46.00 Cft - % Cft
3 Aggregate 92.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 No. - per day


2 Cooly un-skilled 6.00 Nos. - per day
3 Bahisthi 0.60 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composite rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 17
DESCRIPTION OF ITEM:

Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).

(i) Ratio (1 : 4 : 8)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 9.60 bags - per bag


2 Sand 48.00 Cft - % Cft
3 Aggregate 96.00 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 No. - per day


2 Cooly un-skilled 6.00 Nos. - per day
3 Bahisthi 0.60 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composite rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 18
DESCRIPTION OF ITEM:

Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).
(a) (i) Reinforced cement concrete in roof slab, beams, columns, lintels, g
and other structural members laid in situ or pre cast laid in posit
stressed members cast in situ complete in all respect.

1- Type 'A' (Nominal mix 1 : 1: 2)

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit Amount (Rs.)


Analysis for 100 Cft
MATERIAL
1 Cement 31.50 bags - per bag
2 Sand (Harro) 39.00 Cft - % Cft
3 Bajri 78.00 Cft - % Cft
4 Shuttering
Assumed size for concrete slab
14' x 20' x 5" = 117 Cft
1" thick plank seperate slab 280x1/12 = 23.34 Cft
Joint (studs) for supporting planks
5 x 0.3' x 0.3' x 14' = 4.38 Cft
Props Mix. 20 x 3" x 3" x 14' = 17.50 Cft
0.28 Cft
Total 45.5 Cft
For 100 Cft 45.5 x 100 117 = 38.89
This material can be uses 24 times
For one operation 38.89 24 = 1.62 Cft
1.62 Cft @ 350.0 Cft (kail wood) 1.62 Cft - per Cft
Bolts and nuts, nails 3.5 Kg. - Per Kg.
Greasing and oiling for surfacing
and shuttering 2.67 Kg. - Per Kg.

Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR

1 Mason 1.00 Nos. - per day


2 Cooly skilled 1.50 Nos. - per day
3 Coolies un-skilled 10.00 No. - per day
4 Bahisthi 2.00 No. - per day
5 Carpanter 1.00 Nos. - per day
6 Helper 2.00 Nos. - per day
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 100 Cft
Rate/Cft
ITEM RATES
Labour rate per Cft Rs. - Say
Labour rate per Cum Rs. - Say

Composite rate per Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 19
DESCRIPTION OF ITEM:

Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).

(a) (i) Reinforced cement concrete in roof slab, beams, columns, lintels, g
and other structural members laid in situ or pre cast laid in posit
stressed members cast in situ complete in all respect.

2- Type 'B' (Nominal mix 1 : 1: 3).

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Cft


MATERIAL

1 Cement 22.50 bags - per bag


2 Sand (Harro) 42.00 Cft - % Cft
3 Bajri 84.00 Cft - % Cft

4 Shuttering

Wood for shuttering detail as per


item 5-(a) (i)-1 1.62 Cft - per Cft
Bolts and nuts, nails 3.5 Kg. - Per Kg.
Greasing and oiling for surfacing
and shuttering 2.432 Kg. - Per Kg.

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 Nos. - per day


2 Cooly skilled 1.50 Nos. - per day
3 Coolies un-skilled 10.00 No. - per day
4 Bahisthi 2.00 No. - per day
5 Carpanter 1.00 Nos. - per day
6 Helper 2.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 100 Cft
Rate per Cft
ITEM RATES
Labour rate per Cft Rs. - Say
Labour rate per Cum Rs. Say

Composite rate per Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 20
DESCRIPTION OF ITEM:

Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).

(a) (i) Reinforced cement concrete in roof slab, beams, columns, lintels, g
and other structural members laid in situ or pre cast laid in posit
stressed members cast in situ complete in all respect.

3- Type 'C' (Nominal mix 1 : 2: 4).

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Cft


MATERIAL

1 Cement 17.60 bags - bags


2 Sand (Harro) 44.00 Cft - % Cft
3 Bajri 88.00 Cft - % Cft

4 Shuttering

Kail Wood for shuttering detail as per


item 5-(a) (i)-1 1.62 Cft - per Cft
Bolts and nuts, nails 3.5 Kg. - Per Kg.
Greasing and oiling for surfacing
and shuttering 2.272 Kg. - Per Kg.

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 Nos. - per day


2 Cooly skilled 1.50 Nos. - per day
3 Coolies un-skilled 10.00 No. - per day
4 Bahisthi 2.00 No. - per day
5 Carpanter 1.00 Nos. - per day
6 Helper 2.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 100 Cft
Rate per Cft
ITEM RATES
Labour rate per Cft Rs. - Say
Labour rate per Cum Rs. Say

Composite rate per Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 21
DESCRIPTION OF ITEM:

Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).

(a) (ii) Reinforcement cement concrete in slab of roofs/strip foundation; ba


slab of column and retaining walls; etc., and other structural memb
other than those mentioned in 6(a) (i) above not requiring form wor
complete in all respects.

1- Type 'A' (Nominal mix 1 : 1 : 2).

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Cft


MATERIAL

1 Cement 31.50 bags - per bag


2 Sand (Harro) 39.00 Cft - % Cft
3 Bajri 78.00 Cft - % Cft
4 Kail Wood for shuttering 0.19 Cft. - P. Cft
5 Bolts, nuts & nails 3.5 Kg. - Per Kg.
6 Oiling, greasing, surface of shuttering 0.480 Kg. - Per Kg.

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 Nos. - per day


2 Cooly skilled 1.00 Nos. - per day
3 Coolies un-skilled 5.00 No. - per day
4 Bahisthi 1.00 No. - per day
5 Carpanter 1.00 Nos. - per day
6 Helper 1.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 100 Cft
Rate per Cft

ITEM RATES

Labour rate per Cft Rs. - Say


Labour rate per Cum Rs. Say

Composite rate per Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 22
DESCRIPTION OF ITEM:

Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).

(a) (ii) Reinforcement cement concrete in slab of roofs/strip foundation; ba


slab of column and retaining walls; etc., and other structural memb
other than those mentioned in 6(a) (i) above not requiring form wor
complete in all respects.

2- Type 'B' (Nominal mix 1 : 1 : 3).

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Cft


MATERIAL

1 Cement 22.50 bags - per bag


2 Sand (Harro) 42.00 Cft - % Cft
3 Bajri 84.00 Cft - % Cft
4 Kail Wood for shuttering 0.17 Cft. - P. Cft
5 Bolts, nuts & nails 0.5 Kg. - Per Kg.
6 Oiling, greasing, surface of shuttering 0.560 Kg. - Per Kg.

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 Nos. - per day


2 Cooly skilled 1.00 Nos. - per day
3 Coolies un-skilled 5.00 No. - per day
4 Bahisthi 1.00 No. - per day
5 Carpanter 1.00 Nos. - per day
6 Helper 1.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 100 Cft
Rate per Cft

ITEM RATES

Labour rate per Cft Rs. - Say


Labour rate per Cum Rs. Say

Composite rate per Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 23
DESCRIPTION OF ITEM:

Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).

(a) (ii) Reinforcement cement concrete in slab of roofs/strip foundation; ba


slab of column and retaining walls; etc., and other structural memb
other than those mentioned in 6(a) (i) above not requiring form wor
complete in all respects.

3- Type 'C' (Nominal mix 1 : 2 : 4).

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Cft


MATERIAL

1 Cement 17.60 bags - per bag


2 Sand (Harro) 44.00 Cft - % Cft
3 Bajri 88.00 Cft - % Cft
4 Kail Wood for shuttering 0.16 Cft. - P. Cft
5 Bolts, nuts & nails 0.5 Kg. - Per Kg.
6 Oiling, greasing, surface of shuttering 0.560 Kg. - Per Kg.

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 Nos. - per day


2 Cooly skilled 1.00 Nos. - per day
3 Coolies un-skilled 5.00 No. - per day
4 Bahisthi 1.00 No. - per day
5 Carpanter 1.00 Nos. - per day
6 Helper 1.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 100 Cft
Rate per Cft

ITEM RATES

Labour rate per Cft Rs. - Say


Labour rate per Cum Rs. Say

Composite rate per Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 24
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).

(b) Precast reinforced cement concrete and prestresed reinforced cement


concrete in columns, beams, lintels, stair cases, shelves etc.

1- Type 'A' (Nominal mix 1 : 1 : 2).

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Cft


MATERIAL
1 Cement 31.50 bags - per bag
2 Sand (Harro) 39.00 Cft - % Cft
3 Bajri 78.00 Cft - % Cft

4 Shuttering
Assume beam of 12' x 12" x 6" = 6 Cft
Wood
Planks = 2 x 12 1/6 x 13/12 x 2 1/12 = 2.2 Cft
1 x 12 1/6 x 1/12 x = 0.51 Cft
2 x 1/12 x 12/12 x 6/12 = 0.08 Cft
Studs = 2 x 5 x 1/6 x 1/12 = 0.04 Cft
Total 2.93 Cft
For 100 Cft 2.93 6 x 100 = 48.73 Cft
Can be used in 40 operation
One operation 48.73 40.0Cft = 1.22 Cf 1.22 Cft - Per Cft
Nails, nuts & bolts etc. 4.00 No. - Each
Greasing and oiling for shuttering surface 2.11 Kg. - Per Kg.

Total
Contractor's Profit & Overhe 20 Percent
Total

LABOUR

1 Mason 1.00 Nos. - per day


2 Carpanter 1.00 Nos. - per day
3 Coolies skilled 2.00 No. - per day
4 Bahisthi 1.00 No. - per day
5 Coolies un-skilled 8.00 Nos. - per day
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 100 Cft
Rate per Cft

ITEM RATES
Labour rate per Cft Rs. - Say
Labour rate per Cum Rs. Say

Composite rate per Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 25
DESCRIPTION OF ITEM:

Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).

(b) Precast reinforced cement concrete and prestresed reinforced cement


concrete in columns, beams, lintels, stair cases, shelves etc.

2- Type 'B' (Nominal mix 1 : 1 : 3).

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Cft


MATERIAL

1 Cement 22.40 bags - per bag


2 Sand (Harro) 42.00 Cft - % Cft
3 Bajri 84.00 Cft - % Cft

4 Shuttering

Kail Woood for shuttering as per item 5 (b) (1) 1.22 Cft - Cft
Nails, nuts & bolts etc. 4.00 No. - Each
Greasing and oiling etc. 2.11 Kg. - Per Kg.

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 Nos. - per day


2 Carpanter 1.00 Nos. - per day
3 Coolies skilled 2.00 No. - per day
4 Bahisthi 1.00 No. - per day
5 Coolies un-skilled 8.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 100 Cft
Rate per Cft

ITEM RATES

Labour rate per Cft Rs. - Say


Labour rate per Cum Rs. Say

Composite rate per Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 26
DESCRIPTION OF ITEM:

Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).

(b) (i) Precast reinforced cement concrete and prestresed reinforced cement
concrete in columns, beams, lintels, stair cases, shelves etc.

3- Type 'C' (Nominal mix 1 : 2 : 4).

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Cft


MATERIAL

1 Cement 17.60 bags - per bag


2 Sand (Harro) 44.00 Cft - % Cft
3 Bajri 88.00 Cft - % Cft

4 Shuttering

Kail Woood for shuttering as per item 5 (b) (1) 1.22 Cft - Cft
Nails, nuts & bolts etc. 4.00 No. - Each
Greasing and oiling etc. 1.71 Kg. - Per Kg.

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 Nos. - per day


2 Carpanter 1.00 Nos. - per day
3 Coolies skilled 2.00 No. - per day
4 Bahisthi 1.00 No. - per day
5 Coolies un-skilled 8.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 100 Cft
Rate per Cft

ITEM RATES

Labour rate per Cft Rs. - Say


Labour rate per Cum Rs. Say

Composite rate per Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 27
DESCRIPTION OF ITEM:

Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).

(c) Erecting and fixing in position, precast cement concrete or stone s


roofs or lintels, etc., lift upto 20 ft. (6.0 metre) including all

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 100 Cft


MATERIAL

1 Sand 1.00 Cft - % Cft


2 Bitumen 12.73 kg - kg
0.25 Cwt

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 1.00 Nos. - per day


2 Coolies un-skilled 5.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 100 Cft
Rate per Cft

ITEM RATES

Labour rate per Cft Rs. - Say


Labour rate per Cum Rs. Say

Composite rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 28
DESCRIPTION OF ITEM:

Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregated, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).

(d) Add extra labour for R.C. concrete in 2nd and subsequent stories.

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Coolies un-skilled 0.03 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Cft Rs. Say


Labour rate per Cum Rs. Say

Page 29
DESCRIPTION OF ITEM:

Item No. 7 Providing and casting in situ bored reinforced concrete pile with t
concrete (Nominal mix 1 : 2: 4), using 10% extra cement in dry mix,
course sand including all labour and material (except the cost of s
reinforcement and its labour for bending and laying in position etc
will be paid separately, including screening and washing of shingle
curing.

(i) 18" dia (450 mm) pile.

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)

MATERIAL Analysis for 100 Rft

1 Concrete x 100 =176.78 Cft


22 12 x 4
2 Cement 31.10 bags - per bag
3 Sand (Harro) 77.76 Cft - % Cft
4 Bajri 155.52 Cft - % Cft
5 Extra cement (10%) 3.11 bags - per bag
6 Cost of casing pipe
100' @ - = Rs. 0.00
Can be used 100 times
0 100 = Rs. 0.00

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 5.10 Nos. - per day


2 Cooly skilled 5.30 Nos. - per day
3 Coolies un-skilled 22.00 Nos. - per day
4 Bahisthi 1.00 Nos. - per day
5 Fitter 2.00 Nos. - per day
Total
6 Boring hole 18" dia (24" dia) 100.00 Rft - per foot
7 Working of rig during casting 2.50 hrs. - per hour
8 Construction of Temporary Island L.S
9 Carriage of material to site of work
(Boring Material) L.S

Total
Sundries 10 Percent o0.00
Total
Contractor's Profit & Overhea 20 Percent
on Rs. 4725.45 + 472.55 =
Total for 100 Rft

ITEM RATES
Labour rate per Rft Rs. Say
Labour rate per L.M Rs. - Say

Composite rate per Rft Rs. Say


Composite rate per L.M Rs. - Say

Page 30
DESCRIPTION OF ITEM:

Item No. 7 Providing and casting in situ bored reinforced concrete pile with t
concrete (Nominal mix 1 : 2: 4), using 10% extra cement in dry mix,
course sand including all labour and material (except the cost of s
reinforcement and its labour for bending and laying in position etc
will be paid separately, including screening and washing of shingle
curing.

(ii) 20" dia (500 mm) pile.

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Rft


MATERIAL

1 Concrete 22 x 100 =218.17 Cft


7 12x4
2 Cement 38.40 bags - per bag
3 Sand (Harro) 96.00 Cft - % Cft
4 Bajri 192.00 Cft - % Cft
5 Extra cement (10%) 3.84 bags - per bag
6 Cost of casing pipe
100 @ = Rs. 0.00
Can be used 100 times
0 100 = Rs. 0.00

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 7.00 Nos. - per day


2 Cooly skilled 7.00 Nos. - per day
3 Coolies un-skilled 35.00 No. - per day
4 Bahisthi 1.00 No. - per day
5 Fitter 3.00 Nos. - per day
Total
6 Boring hole 20" dia (500 mm) dia 100.00 Rft - per foot
7 Working of rig during casting 2.50 hrs. - per hour
8 Constructin of Temparary Island L.S
9 Carriage of material at site of work
(Boring Material) L.S

Total
Sundries 10 Percent o 0.00
Total
Contractor's Profit & Overhea 20 Percent
on Rs. 0.00 + - = 0.00
Total for 100 Rft

ITEM RATES
Labour rate per Rft Rs. - Say
Labour rate per L.M Rs. - Say

Composite rate per Rft Rs. - Say


Composite rate per L.M Rs. - Say

Page 31
DESCRIPTION OF ITEM:

Item No. 7 Providing and casting in situ bored reinforced concrete pile with t
concrete (Nominal mix 1 : 2: 4), using 10% extra cement in dry mix,
course sand including all labour and material (except the cost of s
reinforcement and its labour for bending and laying in position etc
will be paid separately, including screening and washing of shingle
curing.

(iii) 22" dia (550 mm) pile.

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Rft


MATERIAL

1 Concrete 22 x 100 =264.98 Cft


7 12x4
2 Cement 46.46 bags - per bag
3 Sand (Harro) 116.15 Cft - % Cft
4 Bajri 192.00 Cft - % Cft
5 Extra cement (10%) 4.60 bags - per bag
Cost of casing pipe
100'.0 @ - = Rs. 0.00
Can be used 100 times
0 100 = Rs. 0.00

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 7.00 Nos. - per day


2 Cooly skilled 7.00 Nos. - per day
3 Coolies un-skilled 70.00 Nos. - per day
4 Bahisthi 1.00 Nos. - per day
5 Fitter 3.75 Nos. - per day
Total
6 Boring hole 22" dia (550 mm) dia 100.00 Rft - per foot
7 Working of rig during casting 2.50 hrs. - per hour
8 Constructin of Tempary Island L.S
9 Carriage of material as site of work
(Boring Material) L.S

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
on Rs. 11245.00 + 1124.50 =
Total for 100 Rft

ITEM RATES
Labour rate per Rft Rs. - Say
Labour rate per L.M Rs. - Say

Composite rate per Rft Rs. - Say


Composite rate per L.M Rs. - Say

Page 32
DESCRIPTION OF ITEM:

Item No. 7 Providing and casting in situ bored reinforced concrete pile with t
concrete (Nominal mix 1 : 2: 4), using 10% extra cement in dry mix,
course sand including all labour and material (except the cost of s
reinforcement and its labour for bending and laying in position etc
will be paid separately, including screening and washing of shingle
curing.

(iv) 24" dia (600 mm) pile.

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)

MATERIAL Analysis for 100 Rft

1 Concrete 22 x 100 =314.16 Cft


7 12x4
2 Cement 55.29 bags - per bag
3 Sand (Harro) 138.23 Cft - % Cft
4 Bajri 276.46 Cft - % Cft
5 Extra cement (10%) 5.53 bags - per bag
Cost of casing pipe
100'.0 @ - = Rs. 0.00
Can be used 100 times
0 100 = Rs. 0.00

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 8.00 Nos. - per day


2 Cooly skilled 8.00 Nos. - per day
3 Coolies un-skilled 95.00 No. - per day
4 Bahisthi 1.00 No. - per day
5 Fitter 4.75 Nos. - per day
Total
6 Boring hole 24" dia (550 mm) dia 100.00 Rft - per foot
7 Working of rig during casting 2.50 hrs. - per hour
8 Constructin of Temparary Island L.S
9 Carriage of material to site of work
(Boaring Material) L.S

Total
Sundries 10 Percent o 0.00
Total
Contractor's Profit & Overhea 20 Percent
on Rs. 13528.75 + 1352.88 = Rs. 0.00
Total for 100 Rft

ITEM RATES
Labour rate per Rft Rs. - Say
Labour rate per L.M Rs. - Say

Composite rate per Rft Rs. - Say


Composite rate per L.M Rs. - Say

Page 33
DESCRIPTION OF ITEM:

Item No. 8 Fabrication of mild steel reinforcement bar cage for R.C.C bored pi
including cutting bending, laying in position, welding and fastenin
including cost of binding wire and labour charges for binding of st
reinforcement (also includes removal of rust from the bars).

(a) Plain bars.

Detail Unit Rate (British System) per Cwt

Qty Rate Per Unit Amount (Rs.)

Analysis for 48 Cwt


MATERIAL
2.443 Ton
1 Fabrication of steel (48.00 Cwt) - per ton
2 Welding electrode 1.00 bundle - er bundle
3 Hire charges of plant L.S
4 Working of rig during lowering of cage 3.00 hrs. - per hour

Total
Contractor's Profit & Overhea 20 Percent
Total
Material cost per Cwt

LABOUR for 2 Cwt

1 Welder 1.00 Nos. - per day


2 Coolies un-skilled 3.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Cwt Rs. - Say


Labour rate per 100 Kg Rs. - Say

Composite rate per Cwt Rs. - Say


Composite rate per 100 Kg Rs. - Say

Page 34
DESCRIPTION OF ITEM:

Item No. 8 Fabrication of mild steel reinforcement bar cage for R.C.C bored pi
including cutting bending, laying in position, welding and fastenin
including cost of binding wire and labour charges for binding of st
reinforcement (also includes removal of rust from the bars).

(b) Deformed bars.

Detail Unit Rate (British System) per Cwt

Qty Rate Per Unit Amount (Rs.)

Analysis for 48 Cwt


MATERIAL
2.443 Ton
1 Fabrication of steel (48.00 Cwt) - per ton
2 Welding electrode 1.00 bundle - er bundle
3 Hire charges of plant L.S
4 Working of rig during lowering of cage 3.00 hrs. - per hour

Total
Contractor's Profit & Overhea 20 Percent
Total
Material cost per Cwt

LABOUR for 2 Cwt

1 Welder 1.00 Nos. - per day


2 Coolies un-skilled 3.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Cwt Rs. - Say


Labour rate per 100 Kg Rs. - Say

Composite rate per Cwt Rs. - Say


Composite rate per 100 Kg Rs. - Say

Page 35
DESCRIPTION OF ITEM:

Item No. 9 Fabrication of mild steel reinforcement for cement concrete, includ
cutting, bending, laying in position, making joints and fastenings,
cost of binding wire and labour charges for binding of steel reinfo
(also includes the removal of rust from bars).

(a) Plain bars.

Detail Unit Rate (British System) per Cwt

Qty Rate Per Unit Amount (Rs.)

Analysis for One Cwt


MATERIAL
55 kg
1 M.S. bars including wastage (1.08 Cwt) - per tonne
2 Binding wire (0.25 lbs) - kg
0.114 kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Black Smith 0.25 Nos. - per day


2 Collies unskilled 0.25 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Cwt Rs. - Say


Labour rate per 100 Kg Rs. - Say

Composite rate per Cwt Rs. - Say


Composite rate per 100 Kg Rs. - Say

Page 36
DESCRIPTION OF ITEM:

Item No. 9 Fabrication of mild steel reinforcement for cement concrete, includ
cutting, bending, laying in position, making joints and fastenings,
cost of binding wire and labour charges for binding of steel reinfo
(also includes the removal of rust from bars).

(b) Deformed bars.

Detail Unit Rate (British System) per Cwt

Qty Rate Per Unit Amount (Rs.)

Analysis for One Cwt


MATERIAL
55.00 kg
1 M.S. bars including Wastage (1.08 Cwt) - per tonne
2 Binding wire (0.25 lbs) - per kg
0.114 kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Black Smith 0.25 Nos. - per day


2 Collies unskilled 0.25 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Cwt Rs. - Say


Labour rate per 100 Kg Rs. - Say

Composite rate per Cwt Rs. - Say


Composite rate per 100 Kg Rs. - Say

Page 37
DESCRIPTION OF ITEM:

Item No. 10 Pre cast cement concrete solid or face blocks (1 : 2 : 4) including
templates.

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Cft


MATERIAL

1 Cement 17.60 bags - per bag


2 Sand 44.00 Cft - % Cft
3 Shingle 88.00 Cft - % Cft
4 Kail Woden planks or steel plates for moulds 0.40 Cft - P. Cft.

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 2.00 Nos. - per day


2 Collies unskilled 3.00 Nos. - per day
3 Carpenter 0.50 No. - per day
4 Bahishti 1.00 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 100 Cft

ITEM RATES

Labour rate per Cft Rs. - Say


Labour rate per Cum Rs. - Say

Composite rate per Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 38
DESCRIPTION OF ITEM:

Item No. 11 Pre cast cement concrete hollow block (1 : 2 : 4) including cost of
and constructing walls thereof.

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Cft


MATERIAL

1 Cement 11.20 bags - per bag


2 Sand 28.00 Cft - % Cft
3 Shingle 56.00 Cft - % Cft
4 Kail Wood for templates 0.40 Cft - P. Cft.

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 4.50 Nos. - per day


2 Collies unskilled 8.00 Nos. - per day
3 Bahishti 1.50 No. - per day
4 Carpenter for template 0.50 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Cft Rs. Say


Labour rate per Cum Rs. Say

Composite rate per Cft Rs. Say


Composite rate per Cum Rs. Say

Page 39
DESCRIPTION OF ITEM:

Item No. 12 Providing and fixing ornamental concrete cement Jali 2" (50 mm) thi
(1 : 2 : 4) without steel.

Detail Unit Rate (British System) per Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 10 Sft


MATERIAL

1 Cement 0.30 bags - per bag


2 Sand 0.75 Cft - % Cft
3 Shingle 1.00 Cft - % Cft
4 Form work (Kail Wood) 0.01 Cft - P. Cft.

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 0.20 No. - per day


2 Collies unskilled 0.20 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composit rate per Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 40
DESCRIPTION OF ITEM:

Item No. 13 Extra labour for laying concrete plain or reinforced.

(a) Above 20' upto 40' (6 metre to 12 metre) height.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 125 Cft


LABOUR

1 Collies unskilled 4.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate for 100 Cft 363.00 x 10 0.00
125

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

DESCRIPTION OF ITEM:

Item No. 13 Extra labour for laying concrete plain or reinforced.

(b) For every additional 10' (3 metre) height.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 125 Cft


LABOUR

1 Collies unskilled 2.50 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate for 100 Cft 226.88 x 10 0.00
125

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Page 41
DESCRIPTION OF ITEM:

Item No. 14 Extra labour work of weir, rail or road bridges syphons and concret
super-structure.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 125 Cft


LABOUR

1 Collies unskilled 1.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate for 100 Cft 0.00
125
ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

DESCRIPTION OF ITEM:

Item No. 15 Making reinforced cement concrete spout, including fixing in positi
(2' x 6" x 5").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.09 Bag - P. Bag


2 Sand 0.22 Cft - % Cft.
3 Bajri 0.88 Cft - % Cft.
4 Steel 0.70 Kg. - P. Kg.
5 Wood (Kail Wood) 0.007 Cft - P. Cft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 0.25 No. - per day


2 Collies un-skilled 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES
Labour rate per Spout Rs. - Say
Composit rate per Spout Rs. - Say

Page 42
DESCRIPTION OF ITEM:

Item No. 16 Making hole upto 3" (75 mm) dia 18" (450 mm) deep in cement concret
stone masonry walls and repairing.

Detail Unit Rate (British System) per Hole

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Mason 0.60 No. - per day


2 Collies unskilled 0.60 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per hole Rs. - Say

DESCRIPTION OF ITEM:

Item No. 17 Extra labour for skipping concrete in wells.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 150 Cft


LABOUR

1 Well sinker/diver 1.00 No. - per day


2 Collies unskilled 6.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate per 100 Cft 750.20 x 10 0.00
150

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Page 43
DESCRIPTION OF ITEM:

Item No. 18 Nicking concrete surface.

(a) Cement concrete surface.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 125 Sft


LABOUR

1 Mason 0.50 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate per 100 Sft x 100
125

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

DESCRIPTION OF ITEM:

Item No. 18 Nicking concrete surface.

(b) Lime concrete surface.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 125 Sft


LABOUR

1 Mason 0.165 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate per 100 Sft x 100
125

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Page 44
DESCRIPTION OF ITEM:

Item No. 19 Preparing, watering and ramming surface for laying concrete (for he
works only).

(a) Horizontal floor.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 125 Sft


LABOUR

1 Mason 0.28 No. - per day


2 Cooly un-skilled 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate per 100 Sft x 100
125

ITEM RATES
Labour rate per 100 Sft Rs. - Say
Labour rate per Sqm Rs. - Say

DESCRIPTION OF ITEM:

Item No. 19 Preparing, watering and ramming surface for laying concrete (for he
works only).

(b) Glacis and crest.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 125 Sft


LABOUR

1 Mason 0.50 No. - per day


2 Cooly un-skilled 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate per 100 Sft x 100
125

ITEM RATES
Labour rate per 100 Sft Rs. - Say
Labour rate per Sqm Rs. - Say

Page 45
DESCRIPTION OF ITEM:

Item No. 19 Preparing, watering and ramming surface for laying concrete (for he
works only).

(c) Inverted filters.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 125 Sft


LABOUR

1 Mason 0.125 No. - per day


2 Cooly un-skilled 0.125 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate per 100 Sft x 100
125

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Page 46
DESCRIPTION OF ITEM:

Item No. 20 Fabrication of high tensile steel prestressing cables for prestress
(post tensioned) concrete, including assembling by drawing the H.T.
through metal spacer plate, inserting in helix core and taping or t
sheathing in longitudinally welded metal corrugated sheath, positio
anchorage with male and female set of anchorage cone, forming ducts
transverse cable, stressing cables with jack at both ends as per st
schedule, maintaining stressing record and supply the same in the
approved proforma to the Engineering-in-charge, making loop at blin
including all materials required for it, grouting the cable ducts w
cutting projected ends and making good recesses, etc., complete in
respects.

Detail Unit Rate (British System) 100 Kg

Qty Rate Per Unit Amount (Rs.)

MATERIAL

(a) Cable having 12 Nos. wire


12 x 209.86 x 75 = 188.87 lbs
1000
Wastage 8% = 15.11
203.98 92.54 kg - per ton
(b) Anchorage cone, set of one male and
female for 12/0.276" (7 mm dia cable) 2.00 sets - per set
(c) Self coupling longitudinally welded
carrogated sheath of 1-9/16" i/d for
12/0.276" (7 mm) cable 75.00 ft - per metre
22.86 metre
(d) Helical core (compressed for 10 tons)
extension for 12/0.276 (7 mm) cable
stretch length 75'/10 = 7.5 ft. 7.50 ft - per metre
2.29 metre
(e) Making good recessed with type 'A'
nominal mix 1:1:2: concrete
including curing
Cement 0.27 Bag - P. Bag
Sand (Harrow) 0.34 Cft. - % Cft.
Bajri 0.68 Cft. - % Cft.

(f) Injecting cable 12/0.276 (7 mm)


with cement grout
i) Cement for injecting cable = 0.38 bags
making good recess = 0.07 bags
0.45 ba 0.45 bag - per bag
ii) Sand 39 x 0.25 100 = 0.97 Cf 0.97 Cft - % Cft
iii) Bajri 78 x 0.25 100 = 0.194 C 0.194 Cft - % Cft

Total
Contractor's Profit & Overhea 20 Percent
Total
Rate for 100 Kg 0.00 x 100 =
85.65

Page 47
LABOUR for 4 Nos.

1 Foreman/Supervisor 2.00 No. - per day


2 Black Smith 6.00 Nos. - per day
3 Coolies skilled 4.00 Nos. - per day
4 Coolies un-skilled 8.00 Nos. - per day
Total
5 Hire charges of assembling bunch
cable wire cutter stressing, jack
Hydraulic pump, conce, fixer grout
injecting pump reliveable observation
and supply of recorded data of
stresses. L.S

Total
Sundries 10 Percent o 0.00
Total
Contractor's Profit & Overhea 20 Percent
Total for 4 Nos.
Rate for one cable (85.65 Kg) 0 4 =
Rate for 100 Kg - x 100
85.65

ITEM RATES

Labour rate per 100 Kg Rs.


Composite rate per 100 Kg Rs.
Say

Page 48
DESCRIPTION OF ITEM:

Item No. 21 Fabrication of High Tensile steel reinforcement for prestressed


(pretensioned) concrete work, including inserting wire in moulds, p
M.S. shear bars, spacers and lift hook, male and female anchorage,
down, struts, stressing cables, maintaining stress record and suppl
same in approved proforma to the Engineer-in-charge, cutting wires
projecting ends and making good recesses, etc., complet in all resp

Detail Unit Rate (British System) per 100 Kg

Qty Rate Per Unit Amount (Rs.)


MATERIAL

1 Cable having 5 mm dia = 5 Nos.


(a) 5 x 500 x 102.5 = 256.25 lbs
1000
Cable having 4 mm dia = 3 Nos.
(b) 3 x 500 x 66.6 =
1000 99.900 lbs
356.15 lbs
356.15 lbs or 161.55 kg = 161.55 kg
Wastage 8% = 12.92 kg
174.47 174.47 kg - per ton
2 Anchorage cone set one male and
one female for using
i) 5 mm dia = 4x2 = 8 sets @ = 2000 = Rs.
0.00
ii) 4 mm dia = 3x2 = 6 sets @ = 2500 = Rs.
0.00
Rs. 0.00
Using 4 times = - 4 =Rs.
0.00
3 Making good recesses with type 'A'
nominal mix 1:1:2 concrete
including curing 500 15 = 33+1
= 34 x 2 = 68 ends 68.00 ends - each end
4 Repair of plate for the down struts
spacers L.S
5 M.S bar used for spacer reinforcement
161.55 x 20 100 = 32.31 kg
Wastage 1% 0.32 kg
32.63 k 32.63 kg - per ton
6 Binding wire lbs 0.114 kg - kg

Total
Contractor's Profit & Overhea 20 Percent
Total

Material cost for 100 Kg


0.00 x 100 = 0.00
161.55
LABOUR

1 Foreman 0.25 No. - per day


2 Black Smith 1.00 Nos. - per day
3 Coolies skilled 1.00 Nos. - per day
4 Coolies un-skilled 1.00 Nos. - per day
Total
5 Hire charges of wire cutter
stressing, Jack, Hydraulic pump
relievable cone, observation and
supply of recorded data of stress. L.S
Total
Sundries (10on labour
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES

Labour rate per 100 Kg Rs. -


Composite rate per 100 Kg Rs. -

Page 49
DESCRIPTION OF ITEM:

Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam
Girder and other members (excluding battens) etc., in position on
bridge to correct alignment and level, etc., complete.

(i) Beam upto 50 ft. (15.0 metre) length.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

Assumed for 375 Cft


EQUIPMENT

1 Cost of lifting machinery including carriage 1.00 No. - each


2 Cost of trollies 3.00 Nos. - each
3 Cost of steel rope 1" 450.00 Rft - Rft
4 U Clamp i/c 5/8" bolts & nuts 3.00 Nos. - each
5 Steel rope " (3 x 20) 60.00 Rft - Rft
6 Railway track 200 ft. including sleepers bolts
& nuts complete 200' x 2 = 400 Rft @
235/-P-Rft 400.00 Rft Rft
7 Crow bar 6.00 Nos. - each
Total
Assume life of machinery = 5 years
depreciation for one year
0 5 = 0.00
Contractor's Profit & Overhea 20 Percent
Total

(a) Beam 50'.0 in length 50x2x3.75 = 375 Cft


The above equipment used to lift/
transport and fixing in postion
during one year = 200 beams
Cft = 200 x 375 75000 Cft
Amount per beam
- x 375 0.00
75000
For 100 Cft - x 100 0.00
375
LABOUR Working team for two beams of 375 Cft

1 Supervisor/foreman 1.00 No. - per day


2 Colies skilled 3.00 Nos. - per day
3 Crane operator 1.00 No. - per day
4 Coolies un-skilled 8.00 Nos. - per day
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 2 beams of 375 Cft each
Rate for 100 Cft - x 10.00
2 x 375

ITEM RATES
Labour rate per 100 Cft Rs. - Say
Labour rater per Cum Rs. - Say

Composite rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 50
DESCRIPTION OF ITEM:

Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam
Girder and other members (excluding battens) etc., in position on
bridge to correct alignment and level, etc., complete.

(ii) Beam above 50 ft. upto 75 ft (15 metre to 23 metre) length.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

EQUIPMENT

As per item 22(i)

(a) Beam 75 x 2 x 3.75 = 562.5 Cft


The equipment used to lift/
transport and fixing in postion
during one year = 80 beams
Cft = 80 x 562.5 = 45000 Cft
Amount per beam
- x 562 0.00
45000
LABOUR

Full shift of Labour is required for


one day as per item 22(i)

Total

ITEM RATES

Machinary + Labour required to operate the


machinary Rs.
Rate per 100 Cft Rs. - x 100
562.50
Rate per Cum Rs.

Page 51
DESCRIPTION OF ITEM:

Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam
Girder and other members (excluding battens) etc., in position on
bridge to correct alignment and level, etc., complete.

(iii) Beam above 75 ft. upto 100 ft (23 metre to 30 metre) length.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

EQUIPMENT

As per item 22(i)

(a) Beam = 100 x 2 x 3.75 = 750 Cft


The equipment used to lift/
transport and fixing in postion
during one year = 60 beams
Cft = 60 x 750.0 = 45000 Cft
Amount per beam
- x 750 0.00
45000
LABOUR

Full shift of Labour is required for


two days as per item 22(i) 2.00 -

Total

ITEM RATES

Machinary + Labour required to operate the


machinary Rs.
Rate per 100 Cft Rs. - x 100
750.00 Say
Rate per Cum Rs.

Page 52
DESCRIPTION OF ITEM:

Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam
Girder and other members (excluding battens) etc., in position on
bridge to correct alignment and level, etc., complete.

(iv) Beam above 100 ft. upto 150 ft (23 metre to 30 metre) length.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

EQUIPMENT

As per item 22(i)

(a) Beam = 150 x 2 x 3.75 1125 Cft


The equipment used to lift/
transport and fixing in postion
during one year = 34 beams
Cft = 34 x 1125 = 38250 Cft
Amount per beam 34 x 1125 =
- x 1125 0.00
38250
LABOUR

Full shift of Labour is required for


four days as per item 22(i) 4.00 -

Total

ITEM RATES

Machinary + Labour required to operate the


machinary Rs.
Rate per 100 Cft Rs. 0.00 x 100
1,125.00 Say
Rater per Cum Rs.
Say

Page 53
DESCRIPTION OF ITEM:

Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam
Girder and other members (excluding battens) etc., in position on
bridge to correct alignment and level, etc., complete.

(v) Beam above 150 ft. upto 175 ft (46 metre to 53 metre) length.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

EQUIPMENT

As per item 22(i)

(a) Beam = 175 x 2 x 3.75 1312.5 Cft


The equipment used to lift/
transport and fixing in postion
during one year = 28 beams
Cft = 28 x 1312.5 = 36750 Cft
Amount per beam
- x 1312 0.00
36750
LABOUR

Full shift of Labour is required for


six days as per item 22(i) 6.00 -

Total

ITEM RATES

Machinary + Labour required to operate the


machinary Rs.
Rate per 100 Cft Rs.
Say
Rater per Cum Rs.
Say

Page 54
DESCRIPTION OF ITEM:

Item No. 23 Providing and laying foam concrete 3" (75 mm) thick, using cement s
the ratio of 1 : 2 and aluminum powder at the rate of 0.2% of the c
mix.

Detail Unit Rate (British System) per Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 20 Sft


MATERIAL

1 Cement 1.00 bag - per bag


2 Sand 2.50 Cft - % Cft
3 Aluminum powder 0.2% od cement sand 0.66 lbs - per kg
mix 0.30 kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 0.20 Nos. - per day


2 Collies unskilled 0.50 Nos. - per day
3 Bahishti 0.10 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 55
DESCRIPTION OF ITEM:

Item No. 24 Providing and fixing 6" (150 mm) wide curved sheet of required shap
on face of the construction joint with G.I. Screw, 1.5" (40 mm) lon
construction joints vertically.

(i) Aluminum sheet 1/16" (1.6 mm) thick.

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)

Analysis for 12 Rft


MATERIAL

1 Aluminum sheet 1/16" (1.6 mm) thick 6" (150 mm)


wide 12' (3.6 metre) long = 12' x 6" = 6 Sft
6 Sft @ 0.39 kg per Sft = 2.34 Kg 2.34 kg - per kg
2 Gutties 1.5' (450 mm) c/c 16.00 Nos. - each
3 Screws 1" (40 mm) 17.00 Nos. - Doz

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

Mason 0.125 No. - per day


For making special slope 0.094 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per L.M Rs. - Say

Composite rate per Rft Rs. - Say


Composite rate per L.M Rs. - Say

Page 56
DESCRIPTION OF ITEM:

Item No. 24 Providing and fixing 6" (150 mm) wide curved sheet of required shap
on face of the construction joint with G.I. Screw, 1.5" (40 mm) lon
construction joints vertically.

(ii) G.I. sheet, 18 SWG.

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)

Analysis for 12 Rft


MATERIAL

1 G.I. Sheet 12' x 6" (3.60 x 0.150 metre) = 6 Sft 5.77 kg - per kg
2 Special shape i.e V shaped 2' (600 mm)
Interval 6.00 Nos. - each

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR for 15 Rft

1 Cutting of G.I Sheet in required pieces 6.00 Sft - Sft


2 Fixing special required Nos. 6.00 Nos. - each
3 Mason 0.13 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. Say


Labour rate per L.M Rs. - Say

Composite rate per Rft Rs. - Say


Composite rate per L.M Rs. - Say

Page 57
DESCRIPTION OF ITEM:

Item No. 25 Providing and fixing 1/8" (3 mm) thick 3" (75 mm) wide aluminum str
horizontal and vertical expansion joints in walls, columns, ceiling
etc., including cost of clips/screws etc., complete in all respect

(a) On interior surface (without mastic strip).

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)

Analysis for 12 Rft


MATERIAL

1 Aluminum sheet 1/8 (3 mm) thic 3" (75 mm)


wide and 12' (3.6 metre) long = 12 Rft = 3 Sft 2.34 kg - per kg
2 Gutties 1.5 c/c 16.00 Nos. - each
3 Screws 17.00 Nos. - Dozen

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR for 15 Rft

1 Mason 0.13 Nos. -


2 Moulder/Fitter 0.13 Nos. -

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. - Say


Labour rate per L.M. Rs. - Say

Composite rate per Rft Rs. - Say


Composite rate per L.M Rs. - Say

Page 58
DESCRIPTION OF ITEM:

Item No. 25 Providing and fixing 1/8" (3 mm) thick 3" (75 mm) wide aluminum str
horizontal and vertical expansion joints in walls, columns, ceiling
etc., including cost of clips/screws etc., complete in all respect

(b) On exterior surface (with mastic strip).

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)

Analysis for 12 Rft


MATERIAL

1 Aluminum sheet 1/8 (3 mm) thick 3" (75 mm)


wide & 12' (3.6 metre) long 3.6 metre long (3.00 Sf 2.34 kg - per kg
2 Gutties 1.5'(450 mm) c/c 16.00 Nos. - each
3 Screws 17.00 Nos. - P. Dozen
4 12 Rft (3.6 metre) mastic strip 12.00 Rft - per Rft

Total
Contractor's Profit & Overhea 20 Percent
Total
Cost of Material/Rft

LABOUR for 15 Rft

1 Mason 0.13 Nos. -


2 Moulder/Fitter 0.13 Nos. -

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. - Say


Labour rate per L.M. Rs. - Say

Composite rate per Rft Rs. - Say


Composite rate per L.M Rs. - Say

Page 59
DESCRIPTION OF ITEM:

Item No. 26 Providing and fixing 1/16" (1.6 mm) thick copper flashing on expans
complete in all respects.

Detail Unit Rate (British System) per Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Sft


MATERIAL

1 Coper flashing 100 Sft (9.35 metre)


with 5% wastage (105.00 Sft) 105.00 Sft - Per Sft
2 Nail & screws etc. 0.50 Kg. - Per Kg.

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Carpenter/Black Smith 1.00 Nos. -


2 Helper 1.00 Nos.

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 60
DESCRIPTION OF ITEM:

Item No. 27 Providing and fixing 6" (150 mm) wide G.I. sheet 18 SWG stopper to
joint.

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)

Analysis for 10 Rft


MATERIAL

1 G.I. Sheet 18 SWG (10' x 6") (5.00 Sft) 4.83 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Cuting of G.I sheet to required length


placing G.I sheet joint at required height 0.012 Nos. -
2 Mason 0.05 Nos. -

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. - Say


Labour rate per L.M Rs. - Say

Composite rate per Rft Rs. - Say


Composite rate per L.M Rs. - Say

Page 61
DESCRIPTION OF ITEM:

Item No. 28 Providing and embedding 10" (250 mm) wide 1/4" thick (6 mm) thick r
water stopper in expansion joints of R.C.C roof slab complete in al

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)

Analysis for 10 Rft


MATERIAL

1 Rubber water stopped 10 Rft (3.6 metre) 10.00 Rft - Rft

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason (for couting and embedding) 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. - Say


Labour rate per metre Rs. - Say

Composite rate per Rft Rs. - Say


Composite rate per metre Rs. - Say

Page 62
DESCRIPTION OF ITEM:

Item No. 29 Filling expansion joints with bitumen sand and sawdust in ratio (1

Unit Rate (British System)


Detail (Per Rft length per inch width)

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Rft length 2" width x 4" deep


MATERIAL

Contents = 100' x 1/6' x 1/3' = 5.5 Cft


1 Bitumen 5.5 5 = 1.1 Cft
65 lbs/Cft @ 71.5 lbs or 32.39 kg
32.39 kg - per kg
2 Sand 5.5 x 2 5 = 2.2 Cft 2.20 Cft - % Cft
3 Sawdust 5.5 x 2 5 = 2.2 Cft 2.20 Cft - per Cft
4 Wood for heating 4 seers = 1.82 kg 1.82 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Coolies un-skilled 1.00 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per inch/per foot Rs. - Say


Labour rate per 25 mm/per metre Rs. - Say

Composite rate per inch/per foot Rs. - Say


Composite rate per 25 mm/per metre Rs. - Say

Page 63
DESCRIPTION OF ITEM:

Item No. 30 Filling expansion joints with bitumen.

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)

Analysis for 10 Rft


LABOUR

1 Coolies skilled 0.65 No. - per day 0.00

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. - Say


Labour rater per metre Rs. - Say

DESCRIPTION OF ITEM:

Item No. 31 Laying asphaltic mixture in expansion joints.

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)

Analysis for 10 Rft


LABOUR

1 Cooly un-skilled 0.70 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. - Say


Labour rater per metre Rs. - Say

Page 64
DESCRIPTION OF ITEM:

Item No. 32 Providing and fixing thermopore (foamed polythene) sheet in horizon
vertical expansion joints.

(a) 1" (25 mm) thick thermopore sheet.

Detail Unit Rate (British System) per Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Sft


MATERIAL

1 Thermopore sheet 1" (25 mm) thick wastage 5%


(105 Sft = 9.76 Sqm) 9.76 Sqm - m

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 0.40 No. - per day


2 Cooly un-skilled 0.40 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 65
DESCRIPTION OF ITEM:

Item No. 32 Providing and fixing thermopore (foamed polythene) sheet in horizon
vertical expansion joints.

(b) 1" (40 mm) thick thermopore sheet.

Detail Unit Rate (British System) per Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Sft


MATERIAL

1 Thermopore sheet 1" (40 mm) thick wastage 5%


(105 Sft = 9.76 Sqm) 9.76 Sqm - m

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 0.40 No. - per day


2 Cooly un-skilled 0.40 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 66
DESCRIPTION OF ITEM:

Item No. 33 Providing and laying damp proof course of cement concrete 1 2 : 4 (
cement sand and shingle) including bitumen coating.

(a) With one coat of bitumen and one coat polythene sheet 500 gauge.

(i) 1" (40 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 2.25 bags - per bag


2 Sand 5.50 Cft - % Cft
3 Shingle 11.00 Cft - % Cft
4 Depreciation charges of wooden template (Kail Wood) 0.103 Cft - Per Cft
5 Fuel 5.82 Kg. - Per Cft
6 Brush 0.20 No. - Each
(20.00 lbs)
7 Bitumen 8.88 kg - per kg
8 Polythine 105 Sft @ 1.13 kg % Sft 1.18 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR for 150 Sft

1 Carpenter 0.15 No. - per day


2 Mason 0.50 No. - per day
3 Coolies un-skilled 2.00 Nos. - per day
4 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 67
DESCRIPTION OF ITEM:

Item No. 33 Providing and laying damp proof course of cement concrete 1 2 : 4 (
cement sand and shingle) including bitumen coating.

(a) With one coat of bitumen and one coat polythene sheet 500 gauge.

(ii) 2" (50 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 2.93 bags - per bag


2 Sand 7.50 Cft - % Cft
3 Shingle 15.00 Cft - % Cft
4 Depreciation charges of wooden template (Kail Wood) 0.103 Cft - Per Cft
5 Fuel 5.82 Kg. - Per Cft
6 Brush 0.20 No. - Each
(20.00 lbs)
7 Bitumen 8.88 kg - per kg
8 Polythine with 5% wastage 1.18 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR for 150 Sft

1 Carpenter 0.15 No. - per day


2 Mason 0.50 No. - per day
3 Coolies un-skilled 2.00 Nos. - per day
4 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 68
DESCRIPTION OF ITEM:

Item No. 33 Providing and laying damp proof course of cement concrete 1 2 : 4 (
cement sand and shingle) including bitumen coating.

(a) With one coat of bitumen and one coat polythene sheet 500 gauge.

(iii) 3" (75 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 4.50 bags - per bag


2 Sand 11.00 Cft - % Cft
3 Shingle 22.00 Cft - % Cft
4 Depreciation charges of wooden template (Kail Wood) 0.103 Cft - Per Cft
5 Fuel 5.82 Kg. - Per Cft
6 Brush 0.20 No. - Each
(20.00 lbs)
7 Bitumen 8.88 kg - per kg
8 Polythine with 5% wastage 1.18 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR for 150 Sft

1 Carpenter 0.25 No. - per day


2 Mason 0.50 No. - per day
3 Coolies un-skilled 2.00 Nos. - per day
4 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 69
DESCRIPTION OF ITEM:

Item No. 33 Providing and laying damp proof course of cement concrete 1 2 : 4 (
cement sand and shingle) including bitumen coating.

(b) With 2 coats of bitumen.

(i) 1" (40 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 2.25 bags - per bag


2 Sand 5.50 Cft - % Cft
3 Shingle 11.00 Cft - % Cft
4 Depreciation charges of wooden template (Kail Wood) 0.103 Cft - Per Cft
5 Fuel 5.82 Kg. - Per Cft
6 Brush 0.20 No. - Each
(34.00 lbs)
7 Bitumen 34 lbs/100 Sft (15.34 Kg/100 Sft) 15.08 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR for 150 Sft

1 Carpenter 0.15 No. - per day


2 Mason 0.50 No. - per day
3 Coolies un-skilled 2.00 Nos. - per day
4 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 70
DESCRIPTION OF ITEM:

Item No. 33 Providing and laying damp proof course of cement concrete 1 2 : 4 (
cement sand and shingle) including bitumen coating.

(b) With 2 coats of bitumen.

(ii) 2" (50 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 2.93 bags - per bag


2 Sand 7.50 Cft - % Cft
3 Shingle 15.00 Cft - % Cft
4 Depreciation charges of wooden template (Kail Wood) 0.103 Cft - Per Cft
5 Fuel 5.82 Kg. - Per Cft
6 Brush 0.20 No. - Each
(34.00 lbs)
7 Bitumen 34 lbs/100 Sft (15.34 Kg/100 Sft) 15.08 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR for 150 Sft

1 Carpenter 0.15 No. - per day


2 Mason 0.50 No. - per day
3 Coolies un-skilled 2.00 Nos. - per day
4 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 71
DESCRIPTION OF ITEM:

Item No. 33 Providing and laying damp proof course of cement concrete 1 2 : 4 (
cement sand and shingle) including bitumen coating.

(b) With 2 coats of bitumen.

(iii) 3" (76 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 4.50 bags - per bag


2 Sand 11.00 Cft - % Cft
3 Shingle 22.00 Cft - % Cft
4 Depreciation charges of wooden template (Kail Wood) 0.103 Cft - Per Cft
5 Fuel 5.82 Kg. - Per Cft
6 Brush 0.20 No. - Each
(34.00 lbs)
7 Bitumen 34 lbs/100 Sft (15.34 Kg/100 Sft) 15.08 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Coolies un-skilled 2.00 Nos. - per day
3 Carpenter 0.25 No. - per day
4 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 72
DESCRIPTION OF ITEM:

Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.

(a) With one coat of bitumen and one coat polythen sheet 500 gauge.
(i) Ratio 1 : 4.
(a) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.73 bags - per bag


2 Sand 3.60 Cft - % Cft
3 Fuel 5.82 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 8.86 kg - per kg
6 Polythene with 5% wastage 1.18 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Coolies un-skilled 2.00 Nos. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 73
DESCRIPTION OF ITEM:

Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.

(a) With one coat of bitumen and one coat polythen sheet 500 gauge.
(i) Ratio 1 : 4.
(b) " (20 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.14 bags - per bag


2 Sand 5.50 Cft - % Cft
3 Fuel 5.82 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 8.86 kg - kg
6 Polythene with 5% wastage 1.18 kg - kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 74
DESCRIPTION OF ITEM:

Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.

(a) With one coat of bitumen and one coat polythen sheet 500 gauge.
(ii) Ratio 1 : 3.
(a) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.88 bags - per bag


2 Sand 3.40 Cft - % Cft
3 Fuel 5.82 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 8.86 kg - kg
6 Polythene with 5% wastage 1.18 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate fore 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 75
DESCRIPTION OF ITEM:

Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.

(a) With one coat of bitumen and one coat polythen sheet 500 gauge.
(ii) Ratio 1 : 3.
(b) " (20 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.32 bags - per bag


2 Sand 5.10 Cft - % Cft
3 Fuel 5.82 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 8.86 kg - kg
6 Polythene with 5% wastage 1.18 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 76
DESCRIPTION OF ITEM:

Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.

(a) With one coat of bitumen and one coat polythen sheet 500 gauge.
(iii) Ratio 1 : 2.
(a) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.25 bags - per bag


2 Sand 3.00 Cft - % Cft
3 Fuel 3.63 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 9.72 kg - per kg
6 Polythene with 5% wastage 1.18 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent on items 1, 2, 3,4 & 6
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Coolies un-skilled 2.00 Nos. - per day
3 Bahishti 0.250 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 77
DESCRIPTION OF ITEM:

Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.

(a) With one coat of bitumen and one coat polythen sheet 500 gauge.
(iii) Ratio 1 : 2.
(b) " (20 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.92 bags - per bag


2 Sand 3.00 Cft - % Cft
3 Fuel 3.63 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 9.72 kg - per kg
6 Polythene with 5% wastage 1.18 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3, 4 & 6
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Coolies un-skilled 2.00 Nos. - per day
3 Bahishti 0.250 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 78
DESCRIPTION OF ITEM:

Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.

(b) With 2 coats of bitumen.


(i) Ratio 1 : 4.
(a) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.73 bags - per bag


2 Sand 3.60 Cft - % Cft
3 Fuel 3.65 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 16.50 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 79
DESCRIPTION OF ITEM:

Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.

(b) With 2 coats of bitumen.


(i) Ratio 1 : 4.
(b) " (20 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.14 bags - per bag


2 Sand 5.50 Cft - % Cft
3 Fuel 3.63 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 16.50 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 80
DESCRIPTION OF ITEM:

Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.

(b) With 2 coats of bitumen.


(ii) Ratio 1 : 3.
(a) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.88 bags - per bag


2 Sand 3.40 Cft - % Cft
3 Fuel 3.73 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 16.50 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent in item 1, 2, 3 & 4
i.e. on Rs -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 81
DESCRIPTION OF ITEM:

Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.

(b) With 2 coats of bitumen.


(ii) Ratio 1 : 3.
(b) " (20 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.32 bags - per bag


2 Sand 5.10 Cft - % Cft
3 Fuel 3.73 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 16.50 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent in item 1, 2, 3 & 4
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 82
DESCRIPTION OF ITEM:

Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.

(b) With 2 coats of bitumen.


(iii) Ratio 1 : 2.
(a) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.25 bags - per bag


2 Sand 3.00 Cft - % Cft
3 Fuel 3.73 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 16.50 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent in item 1, 2, 3 & 4
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 83
DESCRIPTION OF ITEM:

Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.

(b) With 2 coats of bitumen.


(iii) Ratio 1 : 2.
(b) " (20 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.92 bags - per bag


2 Sand 5.00 Cft - % Cft
4 Fuel 3.73 Kg. - Per Cft
5 Brush 0.20 No. - Each
5 Bitumen 16.50 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent in item 1, 2, 3 & 4
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 84
DESCRIPTION OF ITEM:

Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.

(a) With one coat of bitumen & one layer of polythene sheet 500 gauge.
(i) Ratio 1 : 4.
(a) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.73 bags - per bag


2 Sand 3.60 Cft - % Cft
3 Fuel 3.62 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 9.72 kg - per kg
6 Polythene with 5% wastage 1.18 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3, 4 & 6
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.250 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 85
DESCRIPTION OF ITEM:

Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.

(a) With one coat of bitumen & one layer of polythene sheet 500 gauge.
(i) Ratio 1 : 4.
(b) " (20 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.14 bags - per bag


2 Sand 5.50 Cft - % Cft
3 Fuel 3.63 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 9.72 kg - per kg
6 Polythene with 5% wastage 1.18 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3, 4 & 6
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.250 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 86
DESCRIPTION OF ITEM:

Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.

(a) With one coat of bitumen & one layer of polythene sheet 500 gauge.
(ii) Ratio 1 : 3.
(a) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.88 bags - per bag


2 Sand 3.40 Cft - % Cft
3 Fuel 3.63 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 9.72 kg - per kg
6 Polythene with 5% wastage 1.18 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3, 4 & 6
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 87
DESCRIPTION OF ITEM:

Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.

(a) With one coat of bitumen & one layer of polythene sheet 500 gauge.
(ii) Ratio 1 : 3.
(b) " (20 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.32 bags - per bag


2 Sand 5.10 Cft - % Cft
3 Bitumen 9.72 kg - per kg
4 Polythene with 5% wastage 1.18 kg - per kg
5 Fuel 3.63 Kg. - Per Cft
6 Brush 0.20 No. - Each

Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 4, 5 & 6
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 88
DESCRIPTION OF ITEM:

Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.

(a) With one coat of bitumen & one layer of polythene sheet 500 gauge.
(iii) Ratio 1 : 2.
(a) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.25 bags - per bag


2 Sand 3.00 Cft - % Cft
3 Fuel 3.63 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 9.72 kg - per kg
6 Polythene with 5% wastage 1.18 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3, 4 & 6
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 89
DESCRIPTION OF ITEM:

Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.

(a) With one coat of bitumen & one layer of polythene sheet 500 gauge.
(iii) Ratio 1 : 2.
(b) " (20 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.92 bags - per bag


2 Sand 5.00 Cft - % Cft
3 Fuel 3.63 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 9.72 kg - per kg
6 Polythene with 5% wastage 1.18 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3, 4 & 6
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 90
DESCRIPTION OF ITEM:

Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.

(b) With 2 coats of bitumen.


(i) Ratio 1 : 4.
(a) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.73 bags - per bag


2 Sand 3.60 Cft - % Cft
3 Fuel 3.63 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 16.50 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.250 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 91
DESCRIPTION OF ITEM:

Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.

(b) With 2 coats of bitumen.


(i) Ratio 1 : 4.
(b) " (20 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.14 bags - per bag


2 Sand 5.50 Cft - % Cft
3 Fuel 3.63 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 16.50 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 92
DESCRIPTION OF ITEM:

Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.

(b) With 2 coats of bitumen.


(ii) Ratio 1 : 3.
(a) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 0.88 bags - per bag


2 Sand 3.40 Cft - % Cft
3 Fuel 3.63 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 16.50 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 93
DESCRIPTION OF ITEM:

Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.

(b) With 2 coats of bitumen.


(ii) Ratio 1 : 3.
(b) " (20 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.32 bags - per bag


2 Sand 5.10 Cft - % Cft
3 Fuel 3.63 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 16.50 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 94
DESCRIPTION OF ITEM:

Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.

(b) With 2 coats of bitumen.


(iii) Ratio 1 : 2.
(a) " (12 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.25 bags - per bag


2 Sand 3.02 Cft - % Cft
3 Fuel 3.63 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 16.50 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total

LABOUR for 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 95
DESCRIPTION OF ITEM:

Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.

(b) With 2 coats of bitumen.


(iii) Ratio 1 : 2.
(b) " (20 mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement 1.92 bags - per bag


2 Sand 5.00 Cft - % Cft
3 Fuel 3.63 Kg. - Per Cft
4 Brush 0.20 No. - Each
5 Bitumen 16.50 kg - per kg

Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total

LABOUR 150 Sft

1 Mason 0.50 No. - per day


2 Cooly un-skilled 2.00 No. - per day
3 Bahishti 0.25 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Composite rate per 100 Sft Rs. - Say


Composite rate per Sqm Rs. - Say

Page 96
DESCRIPTION OF ITEM:

Item No. 36 Grouting concrete between the grooves of gates including shuttering

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Mason 2.00 Nos. - per day


2 Carpenter 0.50 No. - per day
3 Coolies un-skilled 5.00 Nos. - per day
4 Bahishti 1.00 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

DESCRIPTION OF ITEM:

Item No. 37 Chiesel dressing concrete surface on sides of grooves.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Mason 0.22 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Sft Rs. - Say


Labour rate per Sqm Rs. - Say

Page 97
DESCRIPTION OF ITEM:

Item No. 38 Laying and ramming dry ballast or kankar.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Coolies un-skilled 3.25 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

DESCRIPTION OF ITEM:

Item No. 39 Hoisting and placing in position R.C.C shelves.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

LABOUR for 32 Nos.

1 Mason 1.00 No. - per day


2 Coolies un-skilled 2.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per No. Rs. - Say

Page 98
DESCRIPTION OF ITEM:

Item No. 40 Breaking brick ballast, screaning and stacking.

(a) 2" (50 mm) ring.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Coolies un-skilled 2.50 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

DESCRIPTION OF ITEM:

Item No. 40 Breaking brick ballast, screaning and stacking.

(b) 1" (40 mm) ring.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Coolies un-skilled 2.80 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

Page 99
DESCRIPTION OF ITEM:

Item No. 40 Breaking brick ballast, screaning and stacking.

(c) 1" (25 mm) ring.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Coolies un-skilled 3.25 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Composite rate per Cum Rs. - Say

DESCRIPTION OF ITEM:

Item No. 40 Breaking brick ballast, screening and stacking.

(d) Jhama ballast " (20 mm) ring.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Coolies un-skilled 3.75 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Page 100
DESCRIPTION OF ITEM:

Item No. 41 Supplying and fixing broken glasses on courtyard walls, including 1
cement concrete coping.

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)

Assumed for 100 Rft


MATERIAL (for 100 Rft)
For Coping

Assume base 13" and height 4" (114 mm)


for segment angle subtended at the centre
150' (45.75 metre) = 0.43 x 100' = 43.00 Cft
Add 25% 0.107 Cft
53.7 Cft
1 Cement 4.40 bags - per bag
2 Sand 16.00 Cft - % Cft
3 Stone agregate 32.00 Cft - per Cft
4 Broken glass 2.00 mds - % kg
74.39 kg

Total
Contractor's Profit & Overhea 20 Percent
Total

LABOUR

1 Mason 0.50 No. - per day


2 Coolies un-skilled 2.00 Nos. - per day
3 Bahishti for fixing glass 0.15 No. - per day
4 Coolies un-skilled 5.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per Rft Rs. - Say


Labour rate per R.M Rs. - Say

Composite rate per Rft Rs. - Say


Composite rate per R.M Rs. - Say

Page 101
DESCRIPTION OF ITEM:

Item No. 42 Crushing stone ballast by machine.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Coolies un-skilled 2.50 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

DESCRIPTION OF ITEM:

Item No. 43 Breaking stone ballast screened and stacked.

(a) 2" (50 mm) ring.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Coolies un-skilled 2.80 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Page 102
DESCRIPTION OF ITEM:

Item No. 43 Beaking stone ballast screened and stacked.

(b) 1" (40 mm) ring.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Coolies un-skilled 3.25 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

DESCRIPTION OF ITEM:

Item No. 43 Beaking stone ballast screened and stacked.

(c) 1" (25 mm) ring.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Coolies un-skilled 3.75 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Page 103
DESCRIPTION OF ITEM:

Item No. 43 Beaking stone ballast screened and stacked.

(d) " (12 mm) ring.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Coolies un-skilled 5.00 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

DESCRIPTION OF ITEM:

Item No. 43 Beaking stone ballast screened and stacked.

(e) 1/8" (3 mm) to " (6 mm) ring.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Coolies un-skilled 8.50 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Page 104
DESCRIPTION OF ITEM:

Item No. 44 Screening and stacking stone ballast shingle or bajri etc.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Cooly un-skilled 0.80 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

DESCRIPTION OF ITEM:

Item No. 45 Washing ballast, bajri or shingle.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Cooly un-skilled 0.80 No. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per 100 Cft Rs. - Say


Labour rate per Cum Rs. - Say

Page 105
DESCRIPTION OF ITEM:

Item No. 46 Erecting and carting sun shades of precast R.C concrete upto 5' x 2
(1.50 x 0.760 metre).

Detail Unit Rate (British System) per Each

Qty Rate Per Unit Amount (Rs.)

Assume 5 Nos.
LABOUR

1 Mason 0.50 No. - per day


2 Coolies un-skilled 1.60 Nos. - per day

Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total

ITEM RATES

Labour rate per No. Rs. - Say

Page 106
CHAPTER NO.4

DISMANTLING

DESCRIPTION OF ITEM:

Item No. 1 Dismantling dry stone masonry.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Cooly un-skilled 0.85 No. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES

Labour rate per 100 Cft Rs. 0.00 Say 0.00


Labour rate per Cum Rs. 0.00 Say 0.00

Page 1
DESCRIPTION OF ITEM:

Item No. 2 Dismantling stone masonry in mud mortar.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Cooly un-skilled 1.25 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 3 Dismantling stone masonry in lime or cement mortar.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Cooly un-skilled 3.00 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

Page 2
DESCRIPTION OF ITEM:

Item No. 4 (a) Dismantling dry stone or spawl pitching.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 1.50 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 4 (b) Dismantling stone or spawl pitching (mud grouted).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 1.90 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

Page 3
DESCRIPTION OF ITEM:

Item No. 5 Dismantling stone or spawl pitching and apron in silted c

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 2.50 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 6 Dismantling stone pitching cement or lime grouted.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 4.00 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

Page 4
DESCRIPTION OF ITEM:

Item No. 7 Dismantling stone in crates.

(a) Wooden Crates

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR Analysis for 125 Cft

1 Coolies un-skilled 2.00 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 7 Dismantling stone in crates.

(b) Wire crates

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR Analysis for 125 Cft

1 Coolies un-skilled 2.50 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

Page 5
DESCRIPTION OF ITEM:

Item No. 8 Dismantling stone ware drain including base concrete.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 1.40 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 9 Dismantling mud/pise walling.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Cooly un-skilled 0.50 No. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

Page 6
DESCRIPTION OF ITEM:

Item No. 10 Dismantling sundried brick masonry.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 1.25 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 11 Dismantling dry brick masonry.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 0.85 No. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

Page 7
DESCRIPTION OF ITEM:

Item No. 12 Dismantling brick work in mud mortar.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 1.75 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 13 Dismantling brick work in lime or cement mortar.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 4.25 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

Page 8
DESCRIPTION OF ITEM:

Item No. 14 Dismantling cement block masonry.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 3.75 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 15 Dismantling Dhajji walling.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 1.00 No. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

Page 9
DESCRIPTION OF ITEM:

Item No. 16 Dismantling mud concrete.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 2.00 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 17 Dismantling lime concrete.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 2.75 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

Page 10
DESCRIPTION OF ITEM:

Item No. 18 Dismantling lime or cement concrete under water.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 10.50 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 19 (a) Dismantling cement concrete plain 1 : 4 : 8.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 5.50 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

Page 11
DESCRIPTION OF ITEM:

Item No. 19 (b) Dismantling cement concrete plain 1 : 3 : 6.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 9.00 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 19 (c) Dismantling cement concrete plain 1 : 2 : 4.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 11.00 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

Page 12
DESCRIPTION OF ITEM:

Item No. 19 (d) Dismantling cement concrete with brick aggregate.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 3.00 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 19 (e) Dismantling D.P.C of cement concrete 1" thick and cleari

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR Analysis for 125 Cft

1 Coolies un-skilled 1.50 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

Page 13
DESCRIPTION OF ITEM:

Item No. 20 Dismantling cement concrete reinforced, separating reinfo


concrete and straightening the same.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 18.00 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 21 Dismantling sirki sarkanda or thatched roofing supported


battens.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Sft


LABOUR

1 Coolies un-skilled 0.60 No. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

Page 14
DESCRIPTION OF ITEM:

Item No. 22 (a) Dismantling Ist class tile roofing.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Sft


LABOUR

1 Coolies un-skilled 1.50 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 22 (b) Dismantling 2nd class tile roofing.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Sft


LABOUR

1 Coolies un-skilled 1.25 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

Page 15
DESCRIPTION OF ITEM:

Item No. 23 Dismantling from any height asbestos sheet and ridge copi

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

LABOUR Analysis for 125 Sft

1 Fitter 0.25 No. 0.00per day 0.00


2 Coolies un-skilled 0.50 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 24 (a) Dismantling roof of wooden planks and battens upto any he

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Sft


LABOUR

1 Carpenter 0.20 No. 0.00per day 0.00


2 Cooly un-skilled 0.40 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

Page 16
DESCRIPTION OF ITEM:

Item No. 24 (b) Dismantling wooden ceiling above 6 m (20' height) in diff
including lifting with care and special scaffolding along
and with machines underneath.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

LABOUR Analysis for 125 Sft

1 Carpenter 0.60 No. 0.00per day 0.00


2 Cooly un-skilled 1.80 Nos. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 25 Dismantling Jack arch roofing including removal of joists

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

LABOUR Analysis for 125 Sft

1 Coolies un-skilled 2.00 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

Page 17
DESCRIPTION OF ITEM:

Item No. 26 Dismantling R.B. roof complete with mud and mud plaster i
separating reinforcement, cleaning and straightening the

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Sft


LABOUR

1 Coolies un-skilled 2.50 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 27 (a) Stripping and stackings slates or tiles from the truss ro

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

LABOUR Analysis for 125 Sft

1 Coolies unskilled 1.25 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

Page 18
DESCRIPTION OF ITEM:

Item No. 27 (b) Stripping and stacking G.I. sheet roof.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

LABOUR Analysis for 125 Sft

1 Fitter 0.12 No. 0.00per day 0.00


2 Cooly unskilled 1.00 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 27 (c) Extra for dismantling G.I. sheet roof above 6 m (20') in
position including lifting with special scaffolding alone
wires with machines under-neath.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

LABOUR Analysis for 125 Sft

1 Blacksmith 1.00 No. 0.00per day 0.00


2 Cooly unskilled 0.25 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

Page 19
DESCRIPTION OF ITEM:

Item No. 28 Dismantling slates or tiles including battens purlines &

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

LABOUR Analysis for 125 Sft

1 Coolies un-skilled 2.00 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 29 Dismantling brick or flagged flooring without concrete fo

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Sft


LABOUR

1 Coolies un-skilled 0.85 No. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

Page 20
DESCRIPTION OF ITEM:

Item No. 30 Dismantling plank or wooden block flooring etc.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Sft


LABOUR

1 Coolies un-skilled 1.25 Nos. 0.00per day 0.00

Sundries 10.00 Percent 0.00


Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say 0.00


Labour rate per Sqm Rs. 0.00 Say 0.00

Page 21
DESCRIPTION OF ITEM:

Item No. 31 Dis-jointing R.C.C. pipe inside the trench and dismentlin
the pipes from the trench and stacking them out side.

(a) 6" to 12" dia-metre.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Rft


LABOUR

i) For dis-jointing the pipe inside


the trench one mason will take
hour for disjointing each joint.
Day's out put is 16 joints
i.e. 100 Rft.

1 Mason 1.00 No. 0.00per day 0.00


2 Cooly un-skilled 1.00 No. 0.00per day 0.00

ii) For dismantling the pipe line and


removal of the pipe from trench
and stacking out-side.

1 Cooly un-skilled 1.00 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES

Labour rate per Rft Rs. 0.00 Say 0.00


Labour rate per R.M Rs. 0.00 Say 0.00

NOTE: 1) Bends, elbows, sluice valves etc should not be paid for e
of pipe line that is being dismantled.

2) The rate does not include the cost of excavation and refi

Page 22
DESCRIPTION OF ITEM:

Item No. 31 (b) Above 12 inches to 24 inches Dia-metre.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Rft


LABOUR

i) For dis-jointing the pipe inside


the trench one mason will take
hour for disjointing each joint.
Day's out put is 16 joints
i.e. 100 Rft.

1 Mason 1.00 No. 0.00per day 0.00


2 Cooly un-skilled 1.00 No. 0.00per day 0.00

ii) For dismantling the pipe line and


removal of the pipe from trench
and stacking out-side.

1 Cooly un-skilled 3.00 Nos. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES

Labour rate per Rft Rs. 0.00 Say 0.00


Labour rate per R.M Rs. 0.00 Say 0.00

Page 23
DESCRIPTION OF ITEM:

Item No. 31 (c) Above 24 inches to 36 inches Dia-metre.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

Analysis for 150 Rft


LABOUR

i) For dis-jointing the pipe inside


the trench one mason will take
hour for disjointing each joint.
Day's out put is 16 joints
i.e. 100 Rft.

1 Mason 1.50 Nos. 0.00per day 0.00


2 Cooly un-skilled 1.50 Nos. 0.00per day 0.00

ii) For dismantling the pipe line and


removal of the pipe from trench
and stacking out-side.

1 Cooly un-skilled 4.00 Nos. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES

Labour rate per Rft Rs. 0.00 Say 0.00


Labour rate per R.M Rs. 0.00 Say 0.00

Page 24
DESCRIPTION OF ITEM:

Item No. 31 (d) Above 36 inches Dia-metre.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

Analysis for 150 Rft


LABOUR

i) For dis-jointing the pipe inside


the trench one mason will take
one hour for disjointing each joint.
Day's out put is 8 joints or 50 Rft

1 Mason 2.00 Nos. 0.00per day 0.00


2 Cooly un-skilled 2.00 Nos. 0.00per day 0.00

ii) For dismantling the pipe line and


removal of the pipe from trench
and stacking out-side.

1 Cooly un-skilled 6.00 Nos. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES

Labour rate per Rft Rs. 0.00 Say 0.00


Labour rate per R.M Rs. Say

Page 25
DESCRIPTION OF ITEM:

Item No. 32 (a) Removing door with chowkat.

Detail Unit Rate (British System) per No.

Qty Rate Per UnitAmount (Rs.)

LABOUR

1 Cooly un-skilled 0.15 No. 0.00per day 0.00


2 Mason 0.10 No. 0.00per day 0.00
3 Carpenter 0.05 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATE
Labour rate per No. Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 32 (b) Removing window and sky lights with chowkat.

Detail Unit Rate (British System) per No.

Qty Rate Per UnitAmount (Rs.)

LABOUR

1 Cooly un-skilled 0.10 No. 0.00per day 0.00


2 Mason 0.08 No. 0.00per day 0.00
3 Carpenter 0.05 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATE
Labour rate per No. Rs. 0.00 Say

Page 26
DESCRIPTION OF ITEM:

Item No. 33 Removing ventilators and wooden sunshades etc.

Detail Unit Rate (British System) per No.

Qty Rate Per UnitAmount (Rs.)

LABOUR

1 Cooly un-skilled 0.05 No. 0.00per day 0.00


2 Mason 0.05 No. 0.00per day 0.00
3 Carpenter 0.02 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATE
Labour rate per No. Rs. 0.00 Say

DESCRIPTION OF ITEM:

Item No. 34 (a) Dismantling wooden beams upto 4 m (12') in length.

Detail Unit Rate (British System) per No.

Qty Rate Per UnitAmount (Rs.)

LABOUR

1 Cooly un-skilled 0.25 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATE
Labour rate per No. Rs. 0.00 Say 0.00

Page 27
DESCRIPTION OF ITEM:

Item No. 34 (b) Dismantling wooden beams above 4 m to 7 m in length.

Detail Unit Rate (British System) per No.

Qty Rate Per UnitAmount (Rs.)

LABOUR

1 Cooly un-skilled 0.40 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATE
Labour rate per No. Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 35 (a) Dismantling wooden partition Jaffary work etc.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

Rate analysis for 700 Sft


LABOUR

1 Carpenter 1.00 No. 0.00per day 0.00


2 Coolies un-skilled 2.00 Nos. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

Page 28
DESCRIPTION OF ITEM:

Item No. 35 (b) Dismantling wooden trusses.

Detail Unit Rate (British System) per 100 Kg

Qty Rate Per UnitAmount (Rs.)

Rate analysis for 6 Cwt


LABOUR

1 Carpenter 0.25 No. 0.00per day 0.00


2 Coolies un-skilled 4.00 Nos. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
Labour rate per Cwt 0.00
ITEM RATES

Labour rate 100 Kg Rs. Say 0.00

DESCRIPTION OF ITEM:

Item No. 36 Dismantling wooden pelisade fencing.

Detail Unit Rate (British System) per Rft

Qty Rate Per UnitAmount (Rs.)

Rate Analysis for 60 Rft


LABOUR

1 Carpenter 1.00 No. 0.00per day 0.00


2 Coolies un-skilled 1.00 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per Rft Rs. 0.00 Say 0.00
Labour rate per Metre Rs. 0.00 Say 0.00

Page 29
DESCRIPTION OF ITEM:

Item No. 37 Dismantling iron work of trusses, sheds, water tanks etc.
cutting of rivets.

Detail Unit Rate (British System) per 100 Kg

Qty Rate Per UnitAmount (Rs.)

Rate Analysis for 6 Cwt


LABOUR

1 Carpenter 1.00 No. 0.00per day 0.00


2 Coolies un-skilled 3.00 Nos. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
Labour rate per Cwt 0.00
ITEM RATES

Labour rate per 100 Kg Rs. Say 0.00

DESCRIPTION OF ITEM:

Item No. 38 Dismantling rolled steel beame or iron rails etc.

Detail Unit Rate (British System) per 100 Kg

Qty Rate Per UnitAmount (Rs.)

Rate Analysis for 15 Cwt (762.0 Kg)


LABOUR

1 Coolies un-skilled 5.00 Nos. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
Labour rate per Cwt 0.00
ITEM RATES

Labour rate per 100 kg Rs. 0.00 Say 0.00

Page 30
DESCRIPTION OF ITEM:

Item No. 39 Dismantling iron latrine.

Detail Unit Rate (British System) per Unit of 2 S

Qty Rate Per UnitAmount (Rs.)

LABOUR

1 Fitters 0.40 No. 0.00per day 0.00


2 Cooly un-skilled 1.00 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATE
Labour rate per unit of two seats Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 40 Dismantling tees, bends or sluice valves upto 12" bore.

Detail Unit Rate (British System) for each per inch

Qty Rate Per UnitAmount (Rs.)

Rate Analysis for 6 Nos. 12" bore


LABOUR

1 Fitters 1.00 No. 0.00per day 0.00


2 Coolies un-skilled 1.00 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
Labour rate for 1 No. 12" bore 0.00

ITEM RATES
Labour rate for each per 1" (25mm) bore Rs. 0.00 Say 0.00
Labour rate for each per cm bore Rs. 0.00 Say 0.00

Page 31
DESCRIPTION OF ITEM:

Item No. 41 (a) Dismantling B.G. water column.

Detail Unit Rate (British System) per Each

Qty Rate Per UnitAmount (Rs.)

LABOUR

1 Mason 0.75 No. 0.00per day 0.00


2 Black-smith 0.75 No. 0.00per day 0.00
3 Coolies un-skilled 8.00 Nos. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate for Each Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 41 (b) Dismantling M.G. or N.G water column.

Detail Unit Rate (British System) per Each

Qty Rate Per UnitAmount (Rs.)

LABOUR

1 Mason 0.50 No. 0.00per day 0.00


2 Black-smith 0.75 No. 0.00per day 0.00
3 Coolies un-skilled 5.00 Nos. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate for Each Rs. Say 0.00

Page 32
DESCRIPTION OF ITEM:

Item No. 42 Dismantling all types of wire fencing including rolling t


bundles and collecting material.

Detail Unit Rate (British System) per 100 Rft

Qty Rate Per UnitAmount (Rs.)

Rate Analysis for 250 Rft


LABOUR

1 Coolies un-skilled 1.70 Nos. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Rft Rs. 0.00 Say 0.00
Labour rate per R.M Rs. Say

DESCRIPTION OF ITEM:

Item No. 43 Dismantling wire netting of tennis court and frame work.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 SFt


LABOUR

1 Coolies un-skilled 0.40 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

Page 33
DESCRIPTION OF ITEM:

Item No. 44 Dismantling cloth ceiling and supporting timber.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Sft


LABOUR

1 Coolies un-skilled 0.75 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total

ITEM RATES
Labour rate per 100 Sft Rs. Say
Labour rate per Sqm Rs. Say

DESCRIPTION OF ITEM:

Item No. 45 Dismantling and removing road metalling.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 2.00 Nos. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

Page 34
DESCRIPTION OF ITEM:

Item No. 46 Dismantling and removing road pavement, etc., including s


and staking of by products upto one chain lead.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Coolies un-skilled 2.67 Nos. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 47 Removing mud Plaster from walls.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

Analysis for 600 Sft


LABOUR

1 Cooly un-skilled 1.00 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. Say 0.00
Labour rate per Sqm Rs. Say 0.00

Page 35
DESCRIPTION OF ITEM:

Item No. 48 Removing cement or lime plaster.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

Rate Analysis for 300 Sft


LABOUR

1 Cooly un-skilled 1.00 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 49 (a) Scrapping of white wash or colour wash.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

LABOUR

1 Coolies un-skilled 0.20 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

Page 36
DESCRIPTION OF ITEM:

Item No. 49 (b) Scrapping ordinary distemper, oil bound distemper or pain

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Sft


LABOUR

1 Cooly un-skilled 0.75 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 50 Dismantling glazed or encaustic tiles etc.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per UnitAmount (Rs.)

LABOUR Analysis for 125 Sft

1 Mason 1.00 No. 0.00per day 0.00


2 Cooly un-skilled 1.00 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00

Page 37
DESCRIPTION OF ITEM:

Item No. 51 Scraping boulders.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

Analysis for 125 Cft


LABOUR

1 Cooly un-skilled 3.50 Nos. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 52 Cleaning lime or cement mortar of old stones to be re-use

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per UnitAmount (Rs.)

LABOUR Analysis for 125 Cft

1 Coolies un-skilled 1.75 Nos. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00

ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00

Page 38
DESCRIPTION OF ITEM:

Item No. 53 Dismantling of light, fans & call bell point including ca
open type & making good damaged surface (building portion

Detail Unit Rate (British System) per point

Qty Rate Per UnitAmount (Rs.)

Rate Analysis for 30 Points


MATERIAL

1 Cement 0.02 Bag - Each B 0.00


2 Sand 0.11 Cft - % Cft, 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00

LABOUR

1 Electrician 1.00 No. 0.00per day 0.00


2 Cooly un-skilled 0.50 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00

ITEM RATES

Labour rate per point Rs. 0.00 Say 0.00


Composite rate for each point Rs. 0.00 Say 0.00

Page 39
DESCRIPTION OF ITEM:

Item No. 54 Dismantling plug point and making good damaged surface (b
portion).

Detail Unit Rate (British System) per point

Qty Rate Per UnitAmount (Rs.)

Rate Analysis for 35 Points


MATERIAL

1 Cement 0.02 Bag - Each B 0.00


2 Sand 0.11 Cft - % Cft, 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00

LABOUR

1 Electrician 1.00 No. 0.00per day 0.00


2 Cooly un-skilled 0.50 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00

ITEM RATES

Labour rate for each point Rs. 0.00 Say 0.00


Composite rate for each point Rs. 0.00 Say 0.00

Page 40
DESCRIPTION OF ITEM:

Item No. 55 Dismantling G.I conduit/M.S conduit/G.I Flexible/PVC Pipe


wiring etc of all sizes including making good damaged sur
portion).

(i) On surface.

Detail Unit Rate (British System) per foot

Qty Rate Per UnitAmount (Rs.)

Rate Analysis for 50 Metre


MATERIAL

1 Cement 0.02 Bag - Each B 0.00


2 Sand 0.11 Cft - % Cft, 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00

LABOUR

1 Electrician 1.00 No. 0.00per day 0.00


2 Cooly un-skilled 0.50 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00

ITEM RATES

Labour rate per Foot Rs. 0.00 Say 0.00


Composite rate per Foot Rs. 0.00 Say 0.00

Labour rate per R.M Rs. 0.00 Say 0.00


Composite rate per R.M Rs. Say

Page 41
DESCRIPTION OF ITEM:

Item No. 55 Dismantling G.I conduit/M.S conduit/G.I Flexible/PVC Pipe


wiring etc of all sizes including making good damaged sur
portion).

(ii) Recessed in wall.

Detail Unit Rate (British System) per foot

Qty Rate Per UnitAmount (Rs.)

Rate analysis for 30 Metre


MATERIAL

1 Cement 0.02 Bag - Each B 0.00


2 Sand 0.11 Cft - % Cft, 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00
LABOUR

1 Plumber 1.00 No. 0.00per day 0.00


2 Cooly un-skilled 1.00 No. 0.00per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00

ITEM RATES

Labour rate per Foot Rs. Say


Composite rate per Foot Rs. Say

Labour rate per R.M Rs. Say


Composite rate per R.M Rs. Say

Page 42
CHAPTER NO.3

EARTH WORK
(EXCAVATION & EMBANKMENT)
DESCRIPTION OF ITEM:

Item No. 1 Earth work excavation undressed lead upto a single throw of kassi,
Phaorah or shovel.

a) In ashes, sand, soft soil or silt clearance.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies un-skilled for digging 3.75 No. per day -


(including dagbelling for borrow pits)

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 1
DESCRIPTION OF ITEM:

Item No. 1 Earth work excavation undressed lead upto a single throw of kassi,
Phaorah or shovel.

b) In ordinary soil.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging 4.50 No. per day -


(including dagbelling for borrow pits)

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 2 Earthwork excavation in ashes, sand and soft soil or silt clearance,
undressed lead upto 50 ft (15 metre).

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies un-skilled for digging, filling, lifting (including


dab belling for borrow pits 2.5 Nos. per day -
2 Coolies unskilled for carrying 3.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 2
DESCRIPTION OF ITEM:

Item No. 3 Bed clearance and dressing slopes of drains to required sections
including the removal of weeds, roots, etc, disposal of excavated
materials within 50 ft (15 metre) lead.

a) Excavated material undressed.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging 4.00 Nos. per day -


2 Coolies unskilled for carrying 3.00 Nos. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 3 Bed clearance and dressing slopes of drains to required sections
including the removal of weeds, roots, etc., disposal of excavated
materials within 50 ft (15 metre) lead.

b) Excavated material dressed in the specified manner.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging 4.00 Nos. per day -


2 Coolies unskilled for carrying 3.00 Nos. per day -
3 Dresser 0.55 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 3
DESCRIPTION OF ITEM:

Item No. 4 Borrowpit excavation undressed lead upto 100 ft. (30 metre)

a) Ordinary Soil.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging and filling 4.00 Nos. per day -
2 Coolies unskilled for carrying 3.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 4 Borrowpit excavation undressed lead upto 100 ft. (30 metre).

b) Hard Soil.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging and filling 5.60 Nos. per day -
2 Coolies unskilled for carrying 3.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 4
DESCRIPTION OF ITEM:

Item No. 5 Earthwork in ordinary soil for embankments lead upto 100 ft. (30 metre)
including ploughing and mixing with blade grade or disc harrow or
other suitable equipment and compaction by mechanical means at
optimum moisture content and dressing to designed section, complete
in all respects:

(i) 95% to 100% maximum modified AASHTO dry-density with vibratory roller.
Mixing, Moisterning earth to optimum moisture contant in layer etc.
complete with tractor complete with rotorator blade.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft (65 m)


LABOUR

1 Coolies unskilled for digging 4.00 Nos. per day -


2 Coolies unskilled for carrying 3.00 Nos. per day -
3 Dresser cooly skilled 0.125 No. per day -
4 Cooly unskilled 0.142 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

MACHINERY (For 1000 Cft Compacted)

1 Tractor with rotarator blade 0.25 HR per hrs. -


2 Vibratory Road Roller 0.25 HR per hrs. -

Total -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 5
DESCRIPTION OF ITEM:

Item No. 5 Earthwork in ordinary soil for embankments lead upto 100 ft. (30 metre)
including ploughing and mixing with blade grade or disc harrow or
other suitable equipment and compaction by mechanical means at
optimum moisture content and dressing to designed section, complete
in all respects:

(ii) 90% maximum modified AASHTO dry density.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging 4.00 Nos. per day -


2 Coolies unskilled for carrying 3.00 Nos. per day -
3 Dresser cooly skilled 0.125 No. per day -
4 Cooly Unskilled 0.142 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

MACHINERY (For 1000 Cft Compacted)

1 Tractor with rotarator blade 0.25 HR per hrs. -


2 Vibratory Road Roller 0.20 HR per hrs. -

Total -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 6
DESCRIPTION OF ITEM:

Item No. 5 Earthwork in ordinary soil for embankments lead upto 100 ft. (30 metre)
including ploughing and mixing with blade grade or disc harrow or
other suitable equipment and compaction by mechanical means at
optimum moisture content and dressing to designed section, complete
in all respects:

(iii) 85% maximum modified AASHTO dry density.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging 4.00 Nos. per day -


2 Coolies unskilled for carrying 3.00 Nos. per day -
3 Dresser cooly skilled 0.125 No. per day -
4 Cooly Unskilled 0.142 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

MACHINERY (For 1000 Cft Compacted)

1 Tractor with rotarator blade 0.25 HR per hrs. -


2 Vibratory Road Roller 0.15 HR per hrs. -

Total -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 7
DESCRIPTION OF ITEM:

Item No. 6 Regular excavation dressed.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging carrying


and dagbelling. 4.50 Nos. per day -
2 Dresser 0.50 No. per day -
3 Cooly skilled for dressing 0.12 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 8
DESCRIPTION OF ITEM:

Item No. 7 Earthwork excavation in open cutting upto 5 ft (1500 mm) depth for storm
water channels, drains, sullage drains in open areas, roads, streets, lane
including under pinning of walls and shoring to protect existing works,
shuttering and timbering the trenches, dressed to designed level and
dimensions, trimming, removal of suface water from trenches, back filling
surplus excavated material disposed of and dressed within 50 ft (15 metre)
lead.

i) Ordinary

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 Kail Wood for shuttering 0.046 Cft. P. Cft. -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Coolies unskilled for digging, filling & dagbelling 4.00 Nos. per day -
2 Coolies unskilled for carrying 1.50 Nos. per day -
3 Coolies unskilled for temporary diviation 0.50 No. per day -
4 Coolies unskilled for removal of surplus water 0.50 No. per day -
5 Cooly un-skilled 1.00 No. per day -
6 Dresser 1.00 No. per day -
7 Skilled cooly for fixing and timbering
under pinning 0.20 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 9
DESCRIPTION OF ITEM:

Item No. 7 Earthwork excavation in open cutting upto 5 ft (1500 mm) depth for storm
water channels, drains, sullage drains in open areas, roads, streets, lane
including under pinning of walls and shoring to protect existing works,
shuttering and timbering the trenches, dressed to designed level and
dimensions, trimming, removal of suface water from trenches, back filling
surplus excavated material disposed of and dressed within 50 ft (15 metre)
lead.

ii) Hard

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 Kail Wood for shuttering 0.046 Cft. P. Cft. -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Coolies unskilled for digging, filling & dagbelling 5.60 Nos. per day -
2 Coolies unskilled for carrying 1.50 Nos. per day -
3 Coolies unskilled for temporary diviation 0.50 No. per day -
4 Coolies unskilled for removal of surplus water 0.50 No. per day -
5 Cooly un-skilled 1.00 No. per day -
6 Dresser 1.00 No. per day -
7 Skilled cooly for fixing and timbering
under pinning 0.20 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 10
DESCRIPTION OF ITEM:

Item No. 7 Earthwork excavation in open cutting upto 5 ft (1500 mm) depth for storm
water channels, drains, sullage drains in open areas, roads, streets, lane
including under pinning of walls and shoring to protect existing works,
shuttering and timbering the trenches, dressed to designed level and
dimensions, trimming, removal of suface water from trenches, back filling
surplus excavated material disposed of and dressed within 50 ft (15 metre)
lead.

iii) Very Hard

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 Kail Wood for shuttering 0.046 Cft. 0.00 P. Cft. -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Coolies unskilled for digging, filling & dagbelling 7.30 Nos. per day -
2 Coolies unskilled for carrying 1.50 Nos. per day -
3 Coolies unskilled for temporary diviation 0.50 No. per day -
4 Coolies unskilled for removal of surplus water 0.50 No. per day -
5 Cooly un-skilled 1.00 No. per day -
6 Dresser 1.00 No. per day -
7 Skilled cooly for fixing and timbering
under pinning 0.20 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 11
DESCRIPTION OF ITEM:

Item No. 7 Earthwork excavation in open cutting upto 5 ft (1500 mm) depth for storm
water channels, drains, sullage drains in open areas, roads, streets, lane
including under pinning of walls and shoring to protect existing works,
shuttering and timbering the trenches, dressed to designed level and
dimensions, trimming, removal of suface water from trenches, back filling
surplus excavated material disposed of and dressed within 50 ft (15 metre)
lead.
iv) Gravel and Shingle.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 Kail Wood for shuttering 0.046 Cft. P. Cft. -


As per item No.7 - (i) =

Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Coolies unskilled for digging, filling & dagbelling 10.00 Nos. per day -
2 Coolies unskilled for carrying 4.50 No. per day -
3 Coolies unskilled for temporary diviation 2.00 No. per day -
4 Coolies unskilled for removal of surplus water 1.00 No. per day -
5 Cooly un-skilled 0.50 No. per day -
6 Dresser 2.00 No. per day -
7 Skilled cooly for fixing and timbering
under pinning 0.20 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 12
DESCRIPTION OF ITEM:

Item No. 8 Earth work excavation in open cutting 5.01 ft.(1527mm) to 10.0 ft. (3000mm
depth for storm water channels, drains sullage drains in open areas, roads
streets, lanes including under pinning of walls and shoring to protect
existing works, shuttering and timbering the trenches, dressed to disigned
level and dimensions, trimming, removal of surface water from trenches,
back filling and surplus excavated material disposal of and dressed within
100 ft. (30 metre) lead.

i) Ordinary soil

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 Wood for shuttering 0.092 Cft. P. Cft. -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Coolies unskilled for digging and filling 4.00 Nos. per day -
2 Coolies unskilled for carrying 4.00 Nos. per day -
3 Coolies unskilled for removing surface water 0.50 No. per day -
4 Dresser for dressing, fixing shuttering
removing and temporary shuttering 1.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 13
DESCRIPTION OF ITEM:

Item No. 8 Earth work excavation in open cutting 5.01 ft.(1527mm) to 10.0 ft. (3000mm
depth for storm water channels, drains sullage drains in open areas, roads
streets, lanes including under pinning of walls and shoring to protect
existing works, shuttering and timbering the trenches, dressed to disigned
level and dimensions, trimming, removal of surface water from trenches,
back filling and surplus excavated material disposal of and dressed within
100 ft. (30 metre) lead.

ii) Hard Soil

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 Wood for shuttering 0.092 Cft. P. Cft. -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Coolies unskilled for digging and filling 5.60 Nos. per day -
2 Coolies unskilled for carrying 4.00 Nos. per day -
3 Coolies unskilled for removing surface water 0.50 No. per day -
4 Dresser for dressing, fixing shuttering
removing and temporary shuttering 1.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 14
DESCRIPTION OF ITEM:

Item No. 8 Earth work excavation in open cutting 5.01 ft.(1527mm) to 10.0 ft. (3000mm
depth for storm water channels, drains sullage drains in open areas, roads
streets, lanes including under pinning of walls and shoring to protect
existing works, shuttering and timbering the trenches, dressed to disigned
level and dimensions, trimming, removal of surface water from trenches,
back filling and surplus excavated material disposal of and dressed within
100 ft. (30 metre) lead.

iii) Very Hard

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 Wood for shuttering 0.092 Cft. P. Cft. -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Coolies unskilled for digging and filling 7.30 Nos. per day -
2 Coolies unskilled for carrying 4.00 Nos. per day -
3 Coolies unskilled for removing surface water 0.50 No. per day -
4 Dresser for dressing, fixing shuttering
removing and temporary shuttering 1.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 15
DESCRIPTION OF ITEM:

Item No. 8 Earth work excavation in open cutting 5.01 ft.(1527mm) to 10.0 ft. (3000mm
depth for storm water channels, drains sullage drains in open areas, roads
streets, lanes including under pinning of walls and shoring to protect
existing works, shuttering and timbering the trenches, dressed to disigned
level and dimensions, trimming, removal of surface water from trenches,
back filling and surplus excavated material disposal of and dressed within
100 ft. (30 metre) lead.

iv) Gravel and Shingle

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 Wood for shuttering 0.092 Cft. P. Cft. -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Coolies unskilled for digging 9.00 Nos. per day -


2 Coolies unskilled for carrying 6.00 Nos. per day -
3 Coolies unskilled for filling 4.00 Nos. per day -
4 Removing surface water 1.00 No. per day -
5 Dresser 2.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 16
DESCRIPTION OF ITEM:

Item No. 9 Excavation in shingle or gravel formation and rock, not, requiring
blasting, undressed lead upto 100 ft. (30 metre).

i) Dry

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging 9.00 Nos. per day -


2 Coolies unskilled for filling 4.00 Nos. per day -
3 Coolies unskilled for carrying 6.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 9 Excavation in shingle or gravel formation and rock, not, requiring
blasting, undressed lead upto 100 ft. (30 metre).

ii) Wet

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging 10.00 Nos. per day -


2 Coolies unskilled for filling 5.00 Nos. per day -
3 Coolies unskilled for carrying 7.00 Nos. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES
Labour rate per 1000 Cft Rs. Say -
Labour rate per Cum Rs. Say -

Page 17
DESCRIPTION OF ITEM:
Item No. 9 Excavation in shingle or gravel formation and rock, not, requiring
blasting, undressed lead upto 100 ft. (30 metre).

iii) In flowing water

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging 14.00 Nos. per day -


2 Coolies unskilled for filling 6.50 Nos. per day -
3 Coolies unskilled for carrying 7.50 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 10 Earth work excavation in irrigation channels, drains, etc., to designed
section, grades and profiles excavated material disposed off and dressed
with in 50 ft (15 metre) lead.

i) Ordinary soil

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging, filling


filling & dag belling 4.00 Nos. per day -
2 Coolies unskilled for carrying 3.00 Nos. per day -
3 Dresser (for slopes and bed) 1.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES
Labour rate per 1000 Cft Rs. Say -
Labour rate per Cum Rs. Say -

Page 18
DESCRIPTION OF ITEM:

Item No. 10 Earth work excavation in irrigation channels, drains, etc., to designed
section, grades and profiles excavated material disposed off and dressed
with in 50 ft (15 metre) lead.

ii) Hard soil

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging,


filling & dag belling 5.60 Nos. per day -
2 Coolies unskilled for carrying 3.00 Nos. per day -
3 Dresser (for slopes and bed) 1.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 10 Earth work excavation in irrigation channels, drains, etc., to


designed section, grades and profiles excavated material disposed
off and dressed with in 50 ft (15 metre) lead.

iii) Very hard soil

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging,


filling & dag belling 7.30 Nos. per day -
2 Coolies unskilled for carrying 3.00 Nos. per day -
3 Dresser (for slopes and bed) 1.00 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES
Labour rate per 1000 Cft Rs. Say -
Labour rate per Cum Rs. Say -

Page 19
DESCRIPTION OF ITEM:

Item No. 10 Earth work excavation in irrigation channels, drains, etc., to


designed section, grades and profiles excavated material disposed
off and dressed with in 50 ft (15 metre) lead.

iv) Shingle and gravel

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging,


filling & dag belling 8.00 Nos. per day -
2 Coolies unskilled for filling 4.00 Nos. per day -
3 Coolies unskilled for carrying 6.00 Nos. per day -
4 Dresser (for slopes and bed) 2.00 Nos. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES
Labour rate per 1000 Cft Rs. Say -
Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 11 Excavation in rock dressed to designed section, grades and profiles,
excavated material disposed off within 100 ft. (30 metre) and lift upto 5
(1.5 metre).

a) Soft rock, Slate, Shale, Schist or laterite works, with pick & crowbar.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies unskilled for digging & carrying 14.00 Nos. per day -
2 Dresser 4.00 Nos. per day -
3 Bahishti 1.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES
Labour rate per 1000 Cft Rs. Say -
Labour rate per Cum Rs. Say -

Page 20
DESCRIPTION OF ITEM:

Item No. 11 Excavation in rock dressed to designed section, grades and


profiles, excavated material disposed off within 100 ft. (30 metre) and
lift upto 5 ft. (1.5 metre).

b) Medium hard rocks requiring occasional blasting.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 Cost of gun powder and fuse


(1 lbs and 1 fuse) 3.00 Nos. each -
0.453 kg @ 14.00/kg = 6.34
1 fuse (1 metre) @ 14/- 14.00
20.34

Contractor's Profit & Ove ##### Percent -


Total -

LABOUR

1 Coolies skilled for boring holes with steel jumper 3.00 Nos. per day -
2 Coolies skilled for tempering & fixing charges 0.13 No. per day -
3 Blowman 1.00 No. per day -
4 Coolies unskilled for digging 12.00 Nos. per day -
5 Breaking coolies un-skilled stone and removing the spoil 9.00 Nos. per day -
6 Mate (skilled cooly) 0.50 No. per day -
7 Dresser 2.00 Nos. per day -
8 Hammerman 1.00 No. per day -
9 Blacksmith for repairing tools etc. 1.00 No per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 21
DESCRIPTION OF ITEM:

Item No. 12 (a) Excavation in hard rock requiring blasting, and disposal of excavated
material (blasted material) upto 50 ft. (15 metre) lead (including dressing
and levelling to designed section etc. complete.

i) Grade-I

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 (Powder and fuse) for blasting 3.00 No. each -


(1 lbs and one fuse)
0.543 kg @ 14.00/kg + 1 fuse 1 metre @ Rs.14/-

Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Quarrymen for boring hole and fixing


etc. (skilled cooly) 3.00 Nos. per day -
2 Quarrymen for digging and breaking
large stone into small ones 7.00 Nos. per day -
3 Chiselar for dressing 1.00 No. per day -
4 Bahishti 0.50 No. per day -
5 Coolies unskilled for remaining spoil
upto 50 ft. 15 metre lead 6.00 Nos. per day -
6 Blacksmith 0.25 No. per day -
7 Smithy cooly 0.25 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 22
DESCRIPTION OF ITEM:

Item No. 12 (a) Excavation in hard rock requiring blasting, and disposal of excavated
material (blasted material) upto 50 ft. (15 metre) lead (including dressing
and levelling to designed section etc. complete.

ii) Grade-II

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 (Powder and fuse) for blasting 5.00 No. each -


(1 lbs and one fus)
0.543 kg @ 14.00/kg + 1 fuse 1 metre @ Rs.14/-

Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Quarrymen for boring hole and fixing etc. 4.00 Nos. per day -
2 Digging and breaking
large stone into small one 7.00 Nos. per day -
3 Chiselar for dressing 1.00 No. per day -
4 Bahishti 0.50 No. per day -
5 Black-smith for repairing tools etc. 0.50 Nos. per day -
6 Smithy cooly 0.50 No. per day -
7 Coolies unskilled for remaining spoil
upto 50 ft. (15 metre) lead 6.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 23
DESCRIPTION OF ITEM:

Item No. 12 (a) Excavation in hard rock requiring blasting, and disposal of excavated
material (blasted material) upto 50 ft. (15 metre) lead (including dressing
and levelling to designed section etc. complete.

iii) Grade-III

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 (Powder and fuse) for blasting 6.00 No. each -


(1 lbs and 1 fuse)
0.543 kg @ 14.00/kg + 1 fuse 1 metre @ Rs.14/-

Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Quarrymen for boring hole and fixing etc. 5.00 Nos. per day -
2 Digging and breaking large stones
into small one. 8.50 Nos. per day -
3 Chiselar for dressing 1.50 No per day -
4 Bahishti 0.75 No. per day -
5 Blacksmith for repairing tools 0.75 No. per day -
6 Smithy cooly 0.75 No. per day -
7 Coolies un-skilled for removing spoil upto 50 ft.
(15 metre) 6.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 24
DESCRIPTION OF ITEM:

Item No. 11 (a) Excavation in hard rock requiring blasting, and disposal of excavated
material (blasted material) upto 50 ft. (15 metre) lead (including dressing
and levelling to designed section etc. complete.

iv) Grade-IV

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 (Powder and fuse) for blasting 7.00 No. each -


(1 lbs and 1 fuse)
0.543 kg @ 14.00/kg + 1 fuse 1 metre @ Rs.14/-

Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Quarrymen for boring hole and fixing etc. 6.00 Nos. per day -
2 Digging and breaking large stones
into small one. 9.00 Nos. per day -
3 Chiselar for dressing 2.00 No per day -
4 Bahishti 0.75 No. per day -
5 Blacksmith for repairing tools 1.00 No. per day -
6 Smithy cooly 1.00 No. per day -
7 Coolies un-skilled for removing spoil upto 50 ft.
(15 metre) 6.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 25
DESCRIPTION OF ITEM:

Item No. 12 Excavation in hard rock requiring blasting, and disposal of excavated
material (blasted material) upto 50 ft. (15 metre) lead (including dressing
and levelling to designed section etc., complete.

v) Grade-V

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 (Powder and fuse) for blasting 8.00 No. each -


(1 lbs and 1 fuse)
0.543 kg @ 14.00/kg + 1 fuse 1 metre @ Rs.14/-

Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Quarrymen for boring hole and fixing etc. 7.00 Nos. per day -
2 Digging and breaking large stones
into small one. 10.00 Nos. per day -
3 Chiselar for dressing 2.50 No per day -
4 Bahishti 1.00 No. per day -
5 Blacksmith for repairing tools 1.00 No. per day -
6 Smithy cooly 1.00 No. per day -
7 Coolies un-skilled for removing spoil upto 50 ft.
(15 metre) 6.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 26
DESCRIPTION OF ITEM:

Item No. 12 Excavation in hard rock requiring blasting, and disposal of excavated
material (blasted material) upto 50 ft. (15 metre) lead (including dressing
and levelling to designed section etc., complete.

vi) Grade-VI

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 (Powder and fuse) for blasting 9.00 No. each -


(1 lbs and 1 fuse)
0.543 kg @ 14.00/kg + 1 fuse 1 metre @ Rs.

Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Quarrymen for boring hole and fixing etc. 8.00 Nos. per day -
2 Digging and breaking large stones
into small one. 10.00 Nos. per day -
3 Chiselar for dressing 3.00 No per day -
4 Bahishti 1.00 No. per day -
5 Blacksmith for repairing tools 1.25 No. per day -
6 Smithy cooly 1.25 No. per day -
7 Coolies un-skilled for removing spoil upto 50 ft.
(15 metre) 6.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 27
DESCRIPTION OF ITEM:

Item No. 12 (b) Excavation in hard rock requiring blasting, but blasting prohibited, and
disposal of excavated material within 50 ft. (15 metre) lead (including
dressing and levelling to designed section etc., complete.

i) Grade-I

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

Add 100% to the rate on item No. 12 (a) (i) x 2 -

LABOUR

Add 100% to the rate on item No. 12 (a) (i) x 2 (0.01)

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 12 (b) Excavation in hard rock requiring blasting, but blasting prohibited, and
disposal of excavated material within 50 ft. (15 metre) lead (including
dressing and levelling to designed section etc., complete).

ii) Grade-II

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

Add 100% to the rate on item No. 12 (a) (ii) x 2 -

LABOUR

Add 100% to the rate on item No. 12 (a) (ii) x 2 -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 28
DESCRIPTION OF ITEM:

Item No. 12 (b) Excavation in hard rock requiring blasting, but blasting prohibited, and
disposal of excavated material within 50 ft. (15 metre) lead (including
dressing and levelling to designed section etc., complete.

iii) Grade-III

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

Add 100% to the rate on item No. 12 (a) (iii) x 2 -

LABOUR

Add 100% to the rate on item No. 12 (a) (iii) x 2 -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 12 (b) Excavation in hard rock requiring blasting, but blasting prohibited, and
disposal of excavated material within 50 ft. (15 metre) lead (including
dressing and levelling to designed section etc., complete.

iv) Grade-IV

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

Add 100% to the rate on item No. 12 (a) (iv) x 2 -

LABOUR

Add 100% to the rate on item No. 12 (a) (iv) x 2 -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 29
DESCRIPTION OF ITEM:

Item No. 12 (b) Excavation in hard rock requiring blasting, but blasting prohibited, and
disposal of excavated material within 50 ft. (15 metre) lead (including
dressing and levelling to designed section etc., complete.

v) Grade-V

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

Add 100% to the rate on item No. 12 (a) (v) x 2 -

LABOUR

Add 100% to the rate on item No. 12 (a) (v) x 2

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 12 (b) Excavation in hard rock requiring blasting, but blasting prohibited, and
disposal of excavated material within 50 ft. (15 metre) lead (including
dressing and levelling to designed section etc., complete.

vi) Grade-VI

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

Add 100% to the rate on item No. 12 (a) (vi) x 2 -


LABOUR

Add 100% to the rate on item No. 12 (a) (iv) x 2 -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 30
DESCRIPTION OF ITEM:

Item No. 13 Rehandling of Earth Work

a) Lead upto a single throw of Kassi, Phaorah or Shovel.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies un-skilled 2.50 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 13 Rehandling of Earth Work

b) Upto a lead of 50 ft. (15 metre)

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Cooly un-skilled for filling 1.50 No. per day -


2 Coolies un-skilled for carrying 2.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 31
DESCRIPTION OF ITEM:

Item No. 14 Rehandling of gravel work or excavated rock, lead upto 50 ft. (15 metre).

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Cooly un-skilled for filling 4.00 Nos. per day -


2 Coolies un-skilled for carrying 6.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 15 Filling watering and ramming earth under floors.

i) With surplus earth from foundation etc.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies un-skilled for ramming 1.50 Nos. per day -


2 Coolies un-skilled for carrying 2.00 Nos. per day -
3 Dresser earth work 1.00 No. per day -
4 Bahishti 0.50 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 32
DESCRIPTION OF ITEM:

Item No. 15 Filling, watering and ramming earth under floors.

ii) With new earth excavated from outside, lead upto one chain (30 metre).

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Diggers 4.00 Nos. per day -


2 Carrier 2.58 Nos. per day -
3 Dresser 1.00 No. per day -
4 Rammer Cooly un-skilled 1.50 Nos. per day -
5 Bahishti 0.50 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 33
DESCRIPTION OF ITEM:

Item No. 16 Extra for every 50 ft. (15 metre) additional lead or part thereof.

i) For earth work soft, ordinary, hard and very hard.


I) Earth work excavation in ashes sand soft soil or silt lead 500 ft. (150 me
By means of donkey labour.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Actual expenses of 4 No. belchas


LABOUR on monthly basis (for 30 days)

(a) 28 men detailed as below Kharkar (owner) 1.00 No. per month -
Belcha men for excavation 8.00 Nos. per month -
Gantiman (with pick axes) 4.00 Nos. per month -
Topalies (men with donkeys for carrying earth) 10.00 Nos. per month -
Langri (Cooks) 2.00 Nos. per month -
Chowkidars 2.00 Nos. per month -
Dobashi (man for supervision) 1.00 No. per month -

Total -
Exenditure per day 0 0.00 -
30
(b) Jamadari commission for supplying labour on Rs.
0.00 @ 6% -
(c) Food etc as under
i) One seer Atta per man daily for 28 men 28.00 seer per kg -
26.12 kg
ii) Kitchen expenses (tea meat, milk,
fuel, fat & aplienees) L.S. -
iii) Lantern, Patromax lamp depreciation
and K. oil consumption L.S. -
iv) Kitchen Utensil, cost of repair and
replacement etc. L.S. -

Total: = a + b + c = 0.00 -
II - i)Donkeys
28 Nos. Donkeys worker 500 ft. lead in belcha
7 No. Donkey in each belcha
Average working life of one donkey 6 years
Average cost price of one donkey = 0.00
After depriceation cost of one donkey = 0.00
Amount per day 28 x 0 = 0.00
6 x 365 Say -
ii) Food etc as under for 28 donkeys
Phak, 5 seers (4.67 kg) per day per donkey
= 28 x 5 = 3.50 mds 3.50 mds per Md -
40
Grams, 2 seers (0.933 x 2) = 1.866 kg per donkey
Per day 28 x 2 = 1.40 mds 1.40 mds per Md -
40
Total-II -
iii) Material

The following articles are required:


a) 4 No. pick axes and 8 Nos. belchas
cost of repairs and replacement 0.00 per day
b) Sharpening expenses for pick axes
and belchas 12 No. 12.00 No. each -
c) Palana with namda complete for one donckey
Rs.300 average life 4 months. Hence cost per
day 28 x 0 = 0.00 -
4 x 30
d) 2 sacks daily consumption repairs and

Page 34
replacement etc. 2.00 Nos. each -
e) Sutli consumption 0.6 Kg. - P. Kg. -

Total - III -

iv) Comp. Equipment


a) 4 No. tents are used for labour of
4 belchas, cost of one tent Rs.
Average life 12 month
Hence cost per day 4 x 0 0.00 per day -
365
b) Dondky hut expenditure = 2500/-
Average lift of hut = 6 months
Cost per day 0 0.00 -
6 x 30
Total - IV -
(v) Medical Expenditure

For 28 men and 28 donkey Total - V -

Grand Total I + II + III + IV + V = -

Contractor's Profit & Ove ##### Percent -


Total -

Hence cost per belcha 0.00 0.00


4
i) Progress per belcha in ashes sand, soft soil or
silt = 1650 Cft and lead 500 ft.
Rate for 1000 Cft 0.00 x 1000 0.00
1650
Rate for 1000 Cft lead 50 ft. (as per item No.2)
of this Chapter 0.00
Difference for 450 = 0.00 - 0.00
Rate for 50 ft. lead 0.00 0.00
9
ii) Progress per belcha in ordinary soil = 1260 Cft
Rate for 1000 Cft lead 500 ft.
0.00 x 1000 0.00
1260

Rate for 1000 Cft lead 50' as per item No. (10-i) SR
of this Chapter 0.00
Difference for lead 450ft 0.00 - 0.00 0.00
Rate for 50 ft. lead 0.00 0.00
9
Rate for every 50 ft. add lead or a part thereof
iii) Progress per belcha in hard soil 1150 Cft
Rate for 1000 Cft lead 500 ft.
0.00 x 1000 = 0.00
1150

Rate for 1000 Cft lead 50 ft.


(as per item No.10-ii of the Chapter
Difference for lead 450ft 0.00 - 0.00 = 0.00
Rate for 50 ft. lead 0.00 = 0.00
9

Rate for every 50 ft. Addl. lead or thereof


iv) Progress per belcha in very hard soil 990 Cft
Rate for 1000 Cft lead 500 ft.
0.00 x 1000 = 0.00
990

Rate for 1000 Cft lead 50 ft.


(as per item No.10-iii) of this Chapter
Difference for lead 450ft 0.00 - 0.00 = 0.00
Rate for 50 ft. lead 0.00 0.00

Page 35
9
Rate for eveyr 50 ft. Add. lead or part thereof

i) For earth work. Soft, ordifnary, hard and very hard


Extra lead for every 50 ft. or part thereof
(as per detail above i - iv)
Total
Average rate Vi + Vii + Viii + Viv 0.00

Labour rate per 1000 Cft = 0.00 -

(i) (iFor gravel, shingle or rock extra labour required This rate shall apply to
for 1000 Cft. The carriage of spoil from these lead upto mile when
formalities over and above that required for soil the lead is more than
is 20% mile lead shall be
paid as carriage of
material by
mechanical mean.

0.00 x 20 0.00 -
100.00

Stat 0.00 + 0.00 0.00 -

ITEM RATES

Labour rate per 1000 Cft Rs. -


Labour rate per Cum Rs. 0.00 -

Page 36
DESCRIPTION OF ITEM:

Item No. 17 Transportation of earth all types when the total distance, including the l
covered in the item of work, is more than 1000 ft.

(a) Upto mile

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Based on item No.1 of Chapter Carriage

Rate of Ist chain of 100 ft. = -


Rate of 2nd chain of 100 ft. =
Rate of 3rd chain to 10th chain
@ Rs. per Chain for 8 chains =
Rate of 1000 to 1320 ft. ( mile)
@ Rs.26.30 per 1000 ft. (26.30 1000 x 400) = -
Total rate for mile -

Deduct rate of Ist chain already included


in the item of earth work = -
Rate of mile for 100 Cft -
Rate of mile for 1000 Cft = (36.77 x 10) -

ITEM RATES

Labour rate per 1000 Cft Rs. Say


Labour rate per Cum Rs. 0.00 Say -

DESCRIPTION OF ITEM:

Item No. 17 (b) For every 330 ft. additional lead or part-thereof, beyond mile upto one m

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate of Ist mile of 100 Cft = -


Rate of Ist mile of 1000 Cft (129.55 x 10) = -
Deduct rate of mile as per item 17(a) = -
Net rate for mile upto one mile = -
Rate for 330 ft.:
5280 - 1320 = 12 0.00 -
330 12

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 37
DESCRIPTION OF ITEM:

Item No. 17 (c) For every mile additional lead or part thereof, beyond one mile upto 5 m

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate of 2nd mile for 100 Cft =


as per item 1 of chapter Carriage = -
Rate of 2nd mile per 1000 Cft = (25.75 x 10) = -
Rate for every mile (257.50 4) = -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 17 (d) For every mile additional lead or part thereof, beyond 5 miles.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

mile rate upto 5th mile beyond


one mile for 1000 Cft as per item 17(c) = -
Rate reduced as per percentage =
calculated between the rates
of item 17(c) and 17(d) of CSR-1979
15 - 10.25 = 75 x 100 =
15
Reduction in rate = 64.40 x 31.67% =
Thus rate for every mile additional lead
beyond 5 miles (64.40 - 20.40) =

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 38
DESCRIPTION OF ITEM:

Item No. 18 Dressing and levelling of earth work to designed section etc., complete:

a) Ashes, Sand, Silt or Soft Soil.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Dresser 0.20 No. per day -


2 Cooly un-skilled 0.12 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 18 Dressing and levelling of earth work to designed section etc., complete:

b) Ordinary or hard soil.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Dresser 0.50 No. per day -


2 Cooly un-skilled 0.12 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 39
DESCRIPTION OF ITEM:

Item No. 18 Dressing and levelling of earth work to designed section etc., complete:

c) Gravel work or soft rock not requiring blasting.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Quarryman for dressing 1.00 No. per day -


2 Cooly un-skilled 0.50 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 19 Dowel dressing.

Detail Unit Rate (British System) per Chain

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 150 Rft


LABOUR

1 Dresser 0.25 No. per day -


2 Cooly un-skilled 0.10 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 150 Rft -
Rate per 100 Rft

ITEM RATES

Labour rate per Chain Rs. Say -


Labour rate per R.M Rs. Say -

Page 40
DESCRIPTION OF ITEM:

Item No. 20 (a) Dressing Slopes of banks or ground surface.

Detail Unit Rate (British System) per 1000 Sft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Sft


LABOUR

1 Dresser 1.00 No. per day -


2 Cooly un-skilled 0.30 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Sft -

ITEM RATES

Labour rate per 100 Sft Rs. Say -


Labour rate per Sqm Rs. Say -

DESCRIPTION OF ITEM:

Item No. 20 (b) Dressing of earth work (done by Machinery or otherwise and left undressed)
to designed section.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1600 Sft


LABOUR

1 Dresser 1.00 No. per day -


2 Cooly un-skilled 2.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1600 Sft -

ITEM RATES

Labour rate per 100 Sft Rs. Say -


Labour rate per Sqm Rs. Say -

Page 41
DESCRIPTION OF ITEM:

Item No. 21 Excavation in foundation of building, bridges and other structures,


including dag belling, dressing refilling around structure with excavated
earth, watering and ramming, lead upto one chain (30 metre) and lift upto
5 ft. (1.5 metre).

a) In sand, ashes or loose soil.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies un-skilled for digging & refilling 5.00 Nos. per day -
2 Coolies un-skilled for carrying earth 3.00 Nos. per day -
3 Dresser 1.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 21 Excavation in foundation of building, bridges and other structures,


including dag belling, dressing refilling around structure with excavated
earth, watering and ramming, lead upto one chain (30 metre) and lift upto
5 ft. (1.5 metre).

b) In ordinary soil.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies un-skilled for digging & refilling 6.00 Nos. per day -
2 Coolies un-skilled for carrying earth 3.00 Nos. per day -
3 Dresser 1.50 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 42
DESCRIPTION OF ITEM:

Item No. 21 Excavation in foundation of building, bridges and other structures,


including dag belling, dressing refilling around structure with excavated
earth, watering and ramming, lead upto one chain (30 metre) and lift upto
5 ft. (1.5 metre).

c) In hard soil or soft murum.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies un-skilled for digging & refilling 7.00 Nos. per day -
2 Coolies un-skilled for carrying earth 3.00 Nos. per day -
3 Dresser 1.75 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 43
DESCRIPTION OF ITEM:

Item No. 22 Cutting hard rock such as granite, ballast hard line, stone or sand stone
with chisels and lammers for small foundations.

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


MATERIAL

1 Steel 50 Lbs
22.69 kg kg -
2 Charcoal 500 Lbs
##### kg kg -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Hammerman 4 No. for 7 days 28.00 No. per day -


2 Skilled Coolies 4 No. for 7 days 28.00 No. per day -
3 Black smith 1 No. for 7 days 7.00 No. per day -
4 Cooly un-skilled for carrying 1 No. for 7 days 7.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 44
DESCRIPTION OF ITEM:

Item No. 23 Extra for excavation requiring shoring.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


METERIAL

1 Kail Wood for shoring 54.00 0.154 Cft. - P. Cft. -


Total -
Contractor's Profit & Ove ##### Percent -
Total -

LABOUR

1 Cooly un-skilled 1.00 No. per day -


2 Carpenter 0.25 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 24 Compaction of earth work (soft, ordinary or hard soil)


a) Mixing, moistering earth to optimum moister content in layer for
compaction etc. complete.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR
1 Cooly un-skilled 0.12 No. per day -
2 Bahishti 0.30 No. per day -
3 Dresser earth 0.75 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES
Labour rate per 1000 Cft Rs. Say -
Labour rate per Cum Rs. Say -

Page 45
DESCRIPTION OF ITEM:

Item No. 24 Compaction of earth work (soft, ordinary or hard soil)

b) Compaction by rolling with animal driven roller/hand rammed.

i) Soft or sandy soil

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Bullockman 1.00 No. per day -


2 Cooly un-skilled 0.50 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 24 Compaction of earth work (soft, ordinary or hard soil)

b) Compaction by rolling with animal driven roller/hand rammed.

ii) Ordinary soil.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Bullockman 1.25 No. per day -


2 Cooly un-skilled 0.50 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 46
DESCRIPTION OF ITEM:

Item No. 24 Compaction of earth work (soft, ordinary or hard soil)

b) Compaction by rolling with animal driven roller/hand rammed.

iii) Hard soil.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Bullockman 1.25 No. per day -


2 Cooly un-skilled 0.75 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 24 Compaction of earth work (soft, ordinary or hard soil)

b) Compaction by rolling with animal driven roller/hand rammed.

iv) Admixture of shingle.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Bullockman 1.50 No. per day -


2 Cooly un-skilled 0.75 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 47
DESCRIPTION OF ITEM:

Item No. 24 Compection of earth work (soft, ordinary or hard soil)

c) Ramming earthwork (all type of soil)

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies un-skilled 1.50 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 24 Compaction of earth work (soft, ordinary or hard soil)

d) Ramming earthwork behind retaining walls.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies un-skilled for watering & ramming 2.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 48
DESCRIPTION OF ITEM:

Item No. 25 Compaction of earthwork with power road roller, including ploughing,
mixing, moistening earth to optimum moisture content in layers etc.
complete.

i) 95% to 100% maximum modified AASHTO dry density.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1000 Cft


LABOUR

As per item No. 5 (i) of this chapter for machi 0.00 1000 Cft Cft -

Total Rate for 1000 Cft -

ITEM RATES

Composite rate per 1000 Cft Rs. -


Composite rate per Cum Rs. -

DESCRIPTION OF ITEM:

Item No. 25 Compaction of earthwork with power road roller, including ploughing,
mixing, moistening earth to optimum moisture content in layers etc.
complete.

ii) 90% maximum modified AASHTO dry density.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1000 Cft


LABOUR

As per item No. 5 (ii) of this chapter for mach 0.00 1000 Cft Cft -

Total Rate for 1000 Cft -

ITEM RATES

Composite rate per 1000 Cft Rs. -


Composite rate per Cum Rs.

Page 49
DESCRIPTION OF ITEM:

Item No. 25 Compaction of earthwork with power road roller, including ploughing,
mixing, moistening earth to optimum moisture content in layers etc.
complete.

iii) 85% maximum modified AASHTO dry density.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1000 Cft


LABOUR

As per item No. 5 (iii) of this chapter for mac 0.00 1000 Cft Cft -

Total Rate for 1000 Cft -

ITEM RATES

Composite rate per 1000 Cft Rs. -


Composite rate per Cum Rs.

DESCRIPTION OF ITEM:

Item No. 26 Extra for wet earth work.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies un-skilled for digging, filling & lifting 3.50 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 50
DESCRIPTION OF ITEM:

Item No. 27 Extra for slush or daldal including dewatering.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies un-skilled for digging, filling & lifting


and dewatering 8.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 28 Extra for puddling.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Bahishti 1.50 per day -


2 Coolies un-skilled 4.75 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 51
DESCRIPTION OF ITEM:

Item No. 29 Earthwork on small rain water drains along canal banks roads and
plantion drains dressed etc., complete.

Detail Unit Rate (British System) per 100 Rft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 125 Rft


LABOUR

1 Coolies un-skilled 0.95 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate fore 125 Rft -

ITEM RATES

Labour rate per 100 Rft Rs. Say -


Labour rate per metre Rs. Say -

DESCRIPTION OF ITEM:

Item No. 30 Filling and compacting soil earth and boulders behind retaining walls
(including excavation of soil and lead upto 50 ft. (15 metre).

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Excavation, carriage & filling 7.00 Nos. per day -


2 Watering and compaction 2.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 52
DESCRIPTION OF ITEM:

Item No. 31 Dag belling 3" (75 mm) deep.

Detail Unit Rate (British System) per Mile

Qty Rate Per Unit Amount (Rs.)

Assume 2500 Rft


LABOUR

1 Dresser 1.40 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -

ITEM RATES

Labour rate for 1 Mile Rs. Say -


Labour rate for 1 Kilometre Rs. Say -

DESCRIPTION OF ITEM:

Item No. 32 Turfing slopes of banks or lawns with grass sods including ploughing
laying settling and watering (Turf got from within a distance of 5 miles
(8 kilometre) and maintenance for 15 days).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 300 Sft


LABOUR

1 Coolies un-skilled for digging sods 0.50 No. per day -


2 Coolies un-skilled for carrying load 8 km 1.00 No. per day -
3 Laying setting and watering 1.00 No. per day -
4 Watering for 15 days 1.50 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 300 Sft -

ITEM RATES

Labour rate per 100 Sft Rs. Say -


Labour rate per Sqm Rs. Say -

Page 53
DESCRIPTION OF ITEM:

Item No. 33 Berm cutting

a) Lead upto a single throw of Kassi, phaora or shovel (without dressing).

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies un-skilled for digging including


dag-belling for barrow pits 4.50 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 33 Berm cutting

b) Upto 50 ft. (15 metre) lead (including dressing).

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies un-skilled for digging filling, dag-belling 4.00 Nos. per day -
2 Carrying 3.00 Nos. per day -
3 Dresser (for slopes and load) 1.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 54
DESCRIPTION OF ITEM:

Item No. 34 Berm trimming both sides of channels

a) Upto 3 ft (1 metre) depth.

Detail Unit Rate (British System) per one Mile

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1.5 Miles


LABOUR

1 Dresser's earthwork (for dag-belling & dressing) 2.00 Nos. per day -
2 Coolies un-skilled coolies (for trimming etc.) 12.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1.5 miles -

ITEM RATES

Labour rate for 1 Mile Rs. Say -


Labour rate for 1 Kilometre Rs. Say -

DESCRIPTION OF ITEM:

Item No. 34 Berm trimming both sides of channels

b) Exceeding 3 ft. (1 metre) to 5 ft (1.5 metre) depth.

Detail Unit Rate (British System) per one Mile

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1.5 Miles


LABOUR

1 Dresser's earthwork (for dag-belling & dressing) 3.00 Nos. per day -
2 Coolies un-skilled 15.50 Nos. per day -
3 Mate earthwork for supervision 1.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1.5 Miles -

ITEM RATES

Labour rate for 1 Mile Rs. Say -


Labour rate for 1 Kilometre Rs. Say -

Page 55
DESCRIPTION OF ITEM:

Item No. 34 Berm trimming both sides of channels

c) Exceeding 5 ft. (1.5 metre) to 8 ft (2.4 metre) depth.

Detail Unit Rate (British System) per one Mile

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1.5 Miles


LABOUR

1 Dresser's earthwork (for dag-belling & dressing) 4.00 Nos. per day -
2 Coolies un-skilled 25.50 Nos. per day -
3 Mate earthwork for supervision 1.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1.5 Miles -

ITEM RATES

Labour rate for 1 Mile Rs. Say -


Labour rate for 1 Kilometre Rs. Say -

DESCRIPTION OF ITEM:

Item No. 35 Ploughing and leveling borrow pits.

i) Upto 3 ft. (914 mm) depth.

Detail Unit Rate (British System) per Acre

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Bullockman with pair of bullocks 60.00 1.00 No. per day -


2 Coolies un-skilled for leveling 1.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -

ITEM RATES

Labour rate per Acre Rs. Say -


Labour rate per Hectare Rs. Say -

Page 56
DESCRIPTION OF ITEM:

Item No. 35 Ploughing and leveling borrow pits.

ii) Above 3 ft (914 mm) depth.

Detail Unit Rate (British System) per Acre

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Double of item No. 35 (i) = 0.00 508.20 Acre -

ITEM RATES

Labour rate per Acre Rs. Say -


Labour rate per Hectare Rs. Say -

DESCRIPTION OF ITEM:

Item No. 36 Making boundry or service roads including dag-belling, levelling & dressing

(i) In unploughed land.

a) From 10 ft (3 metre) to 20 ft (6 metre) wide.

Detail Unit Rate (British System) per Chain

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1.5 Chain


LABOUR

1 Earth work dresser 0.50 No. per day -


2 Cooly un-skilled 1.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1.5 Chain -

ITEM RATES

Labour rate per Chain Rs. Say -


Labour rate per Running Metre Rs. Say -

Page 57
DESCRIPTION OF ITEM:

Item No. 36 Making boundry or service roads including dag-belling, levelling & dressing

(i) In unploughed land.

b) From 20 ft (6 metre) to 40 ft (12 metre) wide.

Detail Unit Rate (British System) per Chain

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1.5 Chain


LABOUR

1 Earth work dresser 1.00 No. per day -


2 Cooly un-skilled 1.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1.5 Chains -

ITEM RATES

Labour rate per Chain Rs. Say -


Labour rate per Running Metre Rs. Say -

DESCRIPTION OF ITEM:

Item No. 36 Making boundry or service roads including dag-belling, levelling & dressing

(ii) In ploughed land.

a) From 10 ft. (3 metre) to 20 ft. (6 metre) wide.

Detail Unit Rate (British System) per Chain

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 as per item No.36 (i) (a) 0.00 1.5 0.00 -


2 Ploughing charges 0.032 Acre P.Acre -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -

ITEM RATES

Labour rate per Chain Rs. Say -


Labour rate per Running Metre Rs. Say -

Page 58
DESCRIPTION OF ITEM:

Item No. 36 Making boundry or service roads including dag-belling, levelling & dressing

(ii) In unploughed land.

b) From 20.1 ft. (6.1 metre) to 40 ft. (12 metre) wide.

Detail Unit Rate (British System) per Chain

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 as per item No.36 (i) (b) 0.00 1.5 0.00 -


2 Ploughing charges L.S

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -

ITEM RATES

Labour rate per Chain Rs. Say -


Labour rate per Running Metre Rs. Say -

DESCRIPTION OF ITEM:

Item No. 37 Earthwork by boats including hire of boats.

i) Digging and loading into boats upto 50 ft. (15 metre) lead.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies un-skilled for digging, filling in baskets


and lifting 4.00 No. per day -
2 Coolies un-skilled for carrying and loading in
boats 3.50 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 59
DESCRIPTION OF ITEM:

Item No. 37 Earthwork by boats including hire of boats.

ii) Carriage by boat upto 10 chains (300 metres).

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

(Capacity of boat 200 Cft 5.66 m)


LABOUR

1 15 trips in a day/rate for one trip boatman with


large boats per trip 15 trips in a day 0.07 No. per day
2 8 No. extra boatmen (0.53 No. per trip) 0.53 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate for 1 trip (200 Cft -
Rate for 5 trips (100 Cft) 58.27 x 5

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 37 Earthwork by boats including hire of boats.

iii) Extra for every additional one chain (30 metre) or part thereof beyond
10 chain (300 metre).

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 1250 Cft


LABOUR

1 Extra boatman required for one chain (30 metre) 0.20 No. per day -
lead.

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate per 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 60
DESCRIPTION OF ITEM:

Item No. 37 Earthwork by boats including hire of boats including hire of boats.

iv) Unloading earth from Boats.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Coolies un-skilled 3.50 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 38 Unloading earth from B.G. Tracks and clearing 5 ft. (1.5 metre) from rail.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft


LABOUR

1 Cooly un-skilled for unloading and clear 5 ft.


(1.5 metre) 3.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 61
DESCRIPTION OF ITEM:

Item No. 39 Earthwork by train way, digging and loading in truck, upto 50 ft. (15 metr
lead.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 1250 Cft


LABOUR

1 Cooly un-skilled for digging and loading 7.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate for 1250 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 40 Unloading earth from B.G. trucks and spreading upto 15 ft. (4.5 metre) from
rail.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Cooly un-skilled for unloading 2.50 Nos. per day -


2 Coolies un-skilled for spreading 2.00 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Page 62
DESCRIPTION OF ITEM:

Item No. 41 Supplying clean and screened river or pit sand within 5 chain (150 metre).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Royalty 100 Cft. % Cft. -

Contractor's Profit & Ove ##### Percent -


Total -

LABOUR

1 Coolies (for excavation of sand, and


removal of pit earth loading and 0.424 No. per day -
screening etc.)

-
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -

TOTAL -

CARRIAGE

Ist Chain = -
2nd Chain = -
3rd Chain = -
4th Chain = - -
- -

ITEM RATES

Labour rate per 100 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 100 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 63
DESCRIPTION OF ITEM:

Item No. 42 Earth work excavation inopen cutting for sewers and manholes as shown in
drawing including shuttering and timbering, dressing to correct section an
dimension according to templates and levels and removing surface water, in
all types of soil except, shingle gravel and rock.

(i) 0 ft. to 7.0 ft.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For Shutterng 1750 Cft)

1 Vertical planks 26 x 4' x 10" x 1" = 10.83 Cft


Can be used 80 times
Per time 10.83 80 = 0.14 Cft

STRUTS

Wood 26 x 4.75' x 6" x 3" = 15.44 Cft


Can be used 100 times
for one time 15.44 100 = 0.154 Cft
Total 0.294 Cft
Wastage 5% 0.0147 Cft
0.31 Cft 0.31 Cft Cft -

Ist class sawing charges 0.31 x 10 = 3.10 Sft 3.1 Sft Sft -

Nail bolts & nuts 0.083 Kg. Per Kg. -

Total -
Contractor's Profit & Ove ##### Percent except sawing charges
i.e on Rs. 0.00 -
Total rate for 1750 Cft -
Total rate for 1000 Cft

1 For excavation coolies un-skilled for 1250 Cft 6.50 Nos. per day -
2 Dresser 1.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate for 1250 Cft -
Labour rate for 1000 Cft -

(b) LABOUR for removing surface water 1250 Cft

1 Cooly un-skilled 0.25 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate per 1250 Cft -
Labour rate per 1000 Cft

(c) LABOUR for shutterng for 1750 Cft

1 Carpenter 0.10 No. per day -


2 Cooly un-skilled 0.40 No. per day -

Page 64
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate for 1750 Cft -
Total rate for 1000 Cft

ITEM RATES

Labour rate for 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 65
DESCRIPTION OF ITEM:

Item No. 42 Earth work excavation in open cutting for sewers and manholes as shown in
drawing including shuttering and timbering, dressing to correct section an
dimension according to templates and levels and removing surface water, in
all types of soil except shingle, gravel and rock.

(ii) 7.01 to 15 ft. (2.1 metre to 4.5 metre).

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for rate for 2000 Cft


MATERIAL for Shuttering

1 Vertical planks 26 Nos. Ist class kail wood


26 x 8' x 10" x 1" = 21.67 Cft
Can be use 80 times
21.67 80 = 0.27 Cft

2 STRUTS 39 Nos.

Kail wood 39 x 4.75 x 6" x 3" = 23.16 Cft


Can be used 100 times
Wood for one time 23.16 100 = 0.23 Cft

Total 1 + 2 = 0.27 + 0.23 = 0.50 Cft


Wastage 5% = 0.03 Cft
0.53 Cft 0.53 Cft Cft -
Sawing charges = 0.53 x 10 = 5.3 Sft 5.30 Sft Sft -
Bolts, nuts & nails 0.083 Kg. Per Kg. -

Total -
Contractor's Profit & Ove ##### Percent 0.00 -
(except on sawing charges)
Total -
Cost per 1000 Cft 212.69 2 = 0.00 -

Analysis for 2000 Cft


(a) LABOUR for Shutterng

1 Carpenter 0.20 No. per day -


2 Cooly un-skilled 0.80 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate for 2000 Cft -
Total rate for 1000 Cft

Page 66
(b) For Excavation 1250 Cft

1 Coolies un-skilled 12.00 Nos. per day -


2 Dresser 1.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate for 1250 Cft -
Total rate for 1000 Cft -

(c) Labour For Dewatering

Coolies un-skilled 0.12 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 67
DESCRIPTION OF ITEM:

Item No. 42 Earth work excavation in open cutting for sewers and manholes as shown in
drawing including shuttering and timbering, dressing to correct section an
dimension according to templates and levels and removing surface water, in
all types of soil except shingle gravel and rock.

(iii) Above 15 ft. (4.5 metre) depth.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for rate for 2000 Cft

MATERIAL (For Shuttering)

1 Kail wood vertical plants 26 Nos.


26 x 8' x 10" x 1" = 21.67 Cft
Can be used 80 times
Wood for one time 21.67 80 = 0.27 Cft

STRUTS 39 Nos.

2 Kail wood 39 x 4.75 x 6" x 3" = 23.16 Cft


Can be used 100 times
Kail wood for one time 23.16 100 = 0.23 Cft

Total ( 1 + 2 ) = 0.27 + 0.23 = 0.50 Cft


Wastage (5%) 0.03 Cft
Total 0.53 Cft 0.53 Cft Cft -

Sawing charges 0.53 x 10 = 5.30 Sft 5.30 Sft Sft -


Bolt, nuts & nails 0.083 Kg. Per Kg. -

Total -
Contractor's Profit & Ove ##### Percent on 189.50 (Except sawing charges) -
Total rate for 2000 Cft -
Cost per 1000 Cft 212.69 2 = 0.00 -

Analysis for Rate for 2000 Cft


(a) LABOUR (For Shutterng)

1 Carpenter 0.20 No. per day -


2 Cooly 0.80 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate for 2000 Cft -
Total rate for 1000 Cft

Page 68
(b) For Excavation 1250 Cft

1 Coolies un-skilled 16.00 No. -


2 Dresser 1.00 No. -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate for 1250 Cft -
Total rate for 1000 Cft -

(c) Labour for Dewatering

1 Coolies un-skilled 0.12 No. -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total per 1000 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 69
DESCRIPTION OF ITEM:

Item No. 43 Earth work excavation of trenches in open cutting for Sewers and manhole
chambers etc. below sub soil water level to correct section and dimension
according to templates and levels, including shoring, timbering and
shuttering of M.S. Sheets on both sides of the trenches.

(i) 0 ft. (0 metre) to 4 ft. (1.2 metre) depth below S.S.W.L.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

(i) M.S. sheet 8' x 4' x " ft.


For
Excavation 10 Nos.
Platform 2 Nos.
12 Nos.
12 x 8' x 4' = 384 Sft @ 5 lbs/sft = 1920 lbs
Life = 200 times
For one operation 1920 200 = 9.60 lbs
(ii) R.S Joist 4 No. 12' long
4 x 12 = 48 Rft @ 20 lbs/Rft = 960 lbs
Life 1500 times
For one operation 960 1500 = 0.64 lbs
Total 9.6 + 0.64 = 10.24 lbs 10.24 lbs kg -
4.64 kg
(iii) Jhambs 2.00 Nos.
life = 100 time
One opertion = 2 100 = 0.02 No. 0.02 No. each -
(iv) Charakharies complete 2.00 Nos. each -
(v) Kail wood first class planks = 10 Nos.
10 x 10' x 10" x 1" = 10.41 Cft
Life 20 times
One operation 10.41 20 = 0.520 Cft
(vi) Ballies 16.00 Nos.
16 x 10 x 8" x 4" = 35.55 Cft
Life 200 time
One operation = 35.55 200 = 0.18 Cft
(vii) Struts = 16.00 Nos.
16 x 6.25' x 8" x 4" = 22.22 Cft
Life = 100 times
One operation = 22.22 100 = 0.22 Cft
Kail wood first class total 0.52 + 0.18 + 0.22 0.92 Cft
Wastage (5%) = 0.92 + 0.05 = 0.97 Cft 0.97 Cft Cft -
Sawing charges 0.97 Cft x 10 = 9.7 Sft 9.70 Sft Sft -
Bolts and nuts 0.083 Kg. - Per Kg. -
(viii) Manila Rope 1" 100' long
Life 25 times
One operation = 100 25 = 4.00 Rft 4.00 Rft Rft -

Total -
Contractor's Profit & Ove ##### % Except sawing 0.00 -
Total -

Page 70
LABOUR for 1500 Cft

1 Diver sinker 2.00 No. per day -


2 Charakhar-man 4.00 No. per day -
3 Cooly for pully out 2.00 No. per day -
4 Coolies for removing earth 2.00 No. per day -
5 Skilled coolies for hammering M.S sheet to 2.00 No. per day -
drive and takout
6 Cooly for making platform 0.50 No. per day -
7 Carpenter for making shuttering and removing 0.25 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate per 1500 Cft -
Total rate per 1000 Cft

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 71
DESCRIPTION OF ITEM:

Item No. 43 Earth work excavation of trenches in open cutting for Sewers and manhole
chambers etc. below sub soil water level to correct section and dimension
according to templates and levels, including shoring, timbering and
shuttering of M.S. Sheets on both sides of the trenches.

(ii) 4 ft. to 8 ft. (1.2 metre to 2.4 metre) depth below SSWL

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

(I) M.S. sheet (8' x 4' x " ft.)


For
Excavation 20 Nos.
Plate form 4 Nos.
24 Nos.
24 x 8' x 4' = 768 Sft @ 5 lbs/Sft = 3840 lbs
Life = 200 times
One operation 3840 200 = 19.20 lbs
(ii) R.S. Joist = 4 Nos. 12' long
4 x 12 = 48 Rft @ 20 lbs/Rft = 960 lbs
Life 1500 times
One operation 960 1500 = 0.64 lbs
Total 19.84 lbs 19.84 lbs kg -
9.00 kg
(iii) Jhambs = 2.00 Nos.
Life = 100 times
One operation 2 100 = 0.02 No. 0.02 No. each -
(iv) Charakharies complete = 2.00 Nos. 2.00 Nos. each -
(v) Wooden planks = 10.00 Nos.
Kail wood first class 10 x 10' x 10" x 1" = 10.41 Cft
Life 20 times
One operation = 10.41 20 = 0.52 Cft
(vi) Ballies = 16.00 Nos.
16 x 10' x 8" x 4" = 35.55 Cft
Life 200 time
One operation 35.55 200 = 0.18 Cft
(vii) Struts 16.00 Nos.
16 x 6.25' x 8" x 4" = 22.22 Cft
Life = 100 times
One operation 22.22 100 = 0.22 Cft
Kail wood Ist class total 0.52 + 0.18 + 0.22 = 0.92 Cft 0.97 Cft Cft -
Add 5% wastage 0.05 Cft
0.97 Sft
Sawing charges 0.97 x 10 = 9.7 Sft 9.70 Sft Sft -
Bolts and nuts 0.083 Kg. - Per Kg. -
(viii) Manila Rope 1" x 100' long
Life 25 times
One operation 100 25 = 4.00 Rft 4.00 Rft Rft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Page 72
LABOUR for 1500 Cft

1 Diver sinker 2.50 No. per day -


2 Charakhar-man 5.00 No. per day -
3 Cooly un-skilled for pully out 2.50 No. per day -
4 Coolies un-skilled ramming 2.50 No. per day -
5 Skilled coolies for hammering M.S sheet to 2.50 No. per day -
drive and takout
6 Cooly for making platform 0.63 No. per day -
7 Carpenter for making shuttering and removing 0.31 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate per 1500 Cft -
Total rate per 1000 Cft

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 73
DESCRIPTION OF ITEM:

Item No. 43 Earth work excavation of trenches in open cutting for Sewers and manhole
chambers etc. below sub soil water level to correct section and dimension
according to templates and levels, including shoring, timbering and
shuttering of M.S. Sheets on both sides of the trenches.

(iii) Exceeding 2.40 metre depth below SSWL.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

(i) M.S. sheet (8' x 4' x " ft.)


For
Excavation 26 Nos.
Plate form 4 Nos.
30 Nos.

30 x 8' x 4' = 960 Sft @ 5 lbs/Sft = 4800 lbs


One sheet for making jaharies
8 x 4 = 32 Sft @ 5lbs/Sft = 160 lbs
Life = 200 times
for one operation 4960 200 = 24.80 lbs
(ii) For R.S. Joist 4 No.
4 x 12 = 48 Rft @ 20 lbs/foot = 960 lbs
Life = 1500 time
One operation = 960 1500 = 0.64 lbs 25.44 lbs
Total (I + II) 24.80 + 0.64 = 25.44 lbs 11.54 kg kg -
(iii) Thambs = 2.00 Nos.
Life = 100 times
One operation 2 100 = 0.02 No. 0.02 No. each -
(iv) Charakharies complete = 2.00 Nos. 2.00 Nos. each -
(v) Wooden planks = 10.00 Nos.
Kail wood Ist class 10 x 10 x 10" x 5" = 10.41 Cft
Life 20 times
One operation 10.41 20 = 0.52 Cft
(vi) Ballies = 16.00 Nos.
16 x 10' x 8" x 4" = 35.55 Cft
Life 200 time
One operation 35.55 200 = 0.18 Cft
(vii) Struts = 16.00 Nos.
16 x 6.25 x 8" x 4" = 22.22 Cft
Life = 100 times
One operation = 22.22 100 = 0.22 Cft
0.52 + 0.18 + 0.22 = 0.92 Cft
Wastage (5%) 0.05 Cft
Total 0.97 Cft 0.97 Cft Cft -
Sawing charges 0.97 x 10 = 9.70 Sft 9.70 Sft Sft -
Bolts and nuts 0.083 Kg. Per Kg. -
(viii) Manila Rope 1" x 100' long
(vi) Cost of rope
Life 25 times
One operation 100 25 = 4.00 Rft 4.00 Rft Per Rft. -

Total -
Contractor's Profit & Ove ##### Percent -
Total Material cost -

Page 74
LABOUR for 1500 Cft

1.5 times of item No. (43-ii) 0.00 -

Total rate per 1500 Cft -


Total rate per 1000 Cft

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

Composite rate per 1000 Cft Rs. Say -


Composite rate per Cum Rs. Say -

Page 75
DESCRIPTION OF ITEM:

Item No. 44 Excavation of trenches in all kind of soil except cutting rock, for water
pipe lines upto to 5 ft. (1.5 metre) depth from ground level including trim
dressing sides, leveling the beds of trenches to correct grade and cutting
pits for joints etc. complete in all respects.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 1250 Cft


LABOUR

1 Coolies for dressing earth 6.50 No. per day -


2 Dewatering the rain 0.50 No. per day -
3 Dresser 0.50 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate per 1250 Cft -
Total rate per 1000 Cft -

ITEM RATES

Labour rate per 1000 Cft Rs. Say -


Labour rate per Cum Rs. Say -

DESCRIPTION OF ITEM:

Item No. 45 Cutting and removing trees within a distance of 100 ft. (30 metre).

a) Upto 2.5 ft. (0.75 metre) girth.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Carpenter 0.15 No. per day -


2 Coolies un-skilled 1.00 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -

ITEM RATES

Labour rate for each Rs. Say -

Page 76
DESCRIPTION OF ITEM:

Item No. 45 Cutting and removing trees within a distance of 100 ft. (30 metre).

(b) Above 2.5 ft. (0.75 metre) to 6 ft. (1.8 metre) grith.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Coolies un-skilled 2.00 Nos. per day -


2 Carpenter 0.25 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -

ITEM RATES

Labour rate for each Rs. Say -

DESCRIPTION OF ITEM:

Item No. 46 Uprooting stump and removing with in 100 ft. (30 metre) from 2" to 6 ft.
(0.61 metre to 1.83 metre) grith.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Coolies un-skilled 1.50 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -

ITEM RATES

Labour rate for each Rs. Say -

Page 77
DESCRIPTION OF ITEM:

Item No. 47 Jungle clearance and removing within 100 ft. (30 metre).

(a) Light

Detail Unit Rate (British System) per 1000 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 1250 Sft


LABOUR

1 Coolies un-skilled 0.25 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total for 1250 Sft -

ITEM RATES

Labour rate per 1000 Sft Rs. Say -


Labour rate per Sqm Rs. Say -

DESCRIPTION OF ITEM:

Item No. 47 Jungle clearance and removing within 100 ft. (30 metre).

(b) Thick

Detail Unit Rate (British System) per 1000 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 1250 Sft


LABOUR

1 Coolies un-skilled 0.50 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total for 1250 Sft -

ITEM RATES

Labour rate per 1000 Sft Rs. Say -


Labour rate per Sqm Rs. Say -

Page 78
DESCRIPTION OF ITEM:

Item No. 48 Up rooting sarkanda growth and disposal within 100 ft. (30 metre).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 125 Sft


LABOUR

1 Coolies un-skilled 0.12 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total for 125 Sft -

ITEM RATES

Labour rate per 100 Sft Rs. Say -


Labour rate per Sqm Rs. Say -

DESCRIPTION OF ITEM:

Item No. 49 Ploughing 3 times

Detail Unit Rate (British System) per Acre

Qty Rate Per Unit Amount (Rs.)

Assumed for 4.0 Acres


LABOUR

1 Bullock-man 3.25 Nos. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -

ITEM RATES

Labour rate per Acre Rs. Say -


Labour rate per Hectar Rs. Say -

Page 79
DESCRIPTION OF ITEM:

Item No. 50 Levelling, dressing and making lawns

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 150 Sft


LABOUR

1 Coolies un-skilled 0.60 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total for 150 Sft -

ITEM RATES

Labour rate per 100 Sft Rs. Say -


Labour rate per Sqm Rs. Say -

DESCRIPTION OF ITEM:

Item No. 51 Turfing lawns (excluding cost of turf).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 150 Sft


LABOUR

1 Mali 0.50 No. per day -

Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total for 150 Sft -

ITEM RATES

Labour rate per 100 Sft Rs. Say -


Labour rate per Sqm Rs. Say -

Page 80
CHAPTER NO. 24

ELECTRIC INSTALLATION
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
boxes, inspection boxes, bends, tees, etc., complete with all spec

(a) On surface including clamps etc.

(i) " dia (15 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. pipe " dia (15 mm i/d) 7.00 metre per mtr.
2 Clamp " dia (15 mm i/d) 10.00 Nos. each
3 G.I bend " dia (15 mm i/d) 1.00 No. each
4 Gutties 20.00 Nos. dozen
5 Screw 1" to " (25 to 20 mm) 1.50 Dozen dozen
6 Inspection box " dia (15 mm) 1.00 No. each
7 Cement 0.021 Cft. P. Bag
8 Sand 0.08 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 479.84 7 0.00

LABOUR (For 25 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES
Labour rate per Metre Rs. Say
Labour rate per Rft Rs. Say
Composite rate per Metre Rs. Say
Composite rate per Rft Rs. Say

Page 1
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.

(a) On surface including clamps etc.

(ii) " dia (20 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. pipe " dia (20 mm i/d) 7.00 metre per mtr.
2 G.I bend " dia (20 mm i/d) 1.00 No. each
3 Clamp " dia (20 mm i/d) 10.00 Nos. each
4 Gutties 20.00 Nos. dozen
5 Screw 1" to " (25 to 20 mm) 1.50 Dozen dozen
6 Inspection box " dia (20 mm) 1.00 No. each
7 Cement 0.021 Cft. P. Bag
8 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 626.14 7 0.00

LABOUR (For 25 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 2
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.

(a) On surface including clamps etc.

(iii) 1" dia (25 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. pipe 1" dia (25 mm i/d) 7.00 metre per mtr.
2 G.I bend 1" dia (25 mm i/d) 1.00 No. each
3 Clamp 1" dia (25 mm i/d) 10.00 Nos. each
4 Gutties 20.00 Nos. dozen
5 Screw " to 1" (25 to 20 mm) 1.50 Dozen dozen
6 Inspection box 1" dia (25 mm) 1.00 No. each
7 Cement 0.021 Cft. P. Bag
8 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 897.63 7 0.00

LABOUR (For 25 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 3
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.

(a) On surface including clamps etc.

(iv) 1" dia (32 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. pipe 1" dia (32 mm i/d) 7.00 metre per mtr.
2 Clamp 1" dia (32 mm i/d) 10.00 Nos. each
3 G.I bend 1" dia (32 mm i/d) 1.00 No. each
4 M.S. Inspection box 1" dia (32 mm) 1.00 No. each
5 Gutties 20.00 Nos. dozen
6 Screw " to 1" (25 to 20 mm) 1.50 Dozen dozen
7 Cement 0.021 Cft. P. Bag
8 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 1126.33 0.00

LABOUR (For 50 Metre)

1 Electrician 2.00 Nos. per day


2 Coolies skilled 3.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 4
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.

(a) On surface including clamps etc.

(v) 1" dia (40 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. pipe 1" dia (40 mm i/d) 7.00 metre per mtr.
2 G.I bend 1" dia (40 mm i/d) 1.00 Nos. each
3 M.S. Inspection box 1" dia (40 mm) 1.00 No. each
4 G.I. Clamp 1" dia (40 mm i/d) 10.00 Nos. each
5 Gutties 20.00 Nos. dozen
6 Screw 1 to " (25 to 20 mm) 1.50 Dozen dozen
7 Cement 0.021 Cft. P. Bag
8 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 1330.43 0.00

LABOUR (For 50 Metre)

1 Electrician 2.00 No. per day


2 Coolies skilled 3.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 5
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.

(a) On surface including clamps etc.

(vi) 2" dia (50 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. pipe 2" dia (50 mm i/d) 7.00 metre per mtr.
2 G.I bend 2" dia (50 mm i/d) 1.00 No. each
3 M.S. Inspection box 2" dia (50 mm) 1.00 No. each
4 G.I. Clamp 2" dia (50 mm i/d) 10.00 Nos. each
5 Gutties 20.00 Nos. dozen
6 Screw 1 to " (25 to 20 mm) 1.50 Dozen dozen
7 Cement 0.021 Cft. P. Bag
8 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 1758.85 0.00

LABOUR (For 42 Metre)

1 Electrician 2.00 No. per day


2 Coolies skilled 3.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 6
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.

(a) On surface including clamps etc.

(vii) 3" dia (80 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. pipe 3" dia (80 mm i/d) 7.00 metre per mtr.
2 G.I. Clamp 3" dia (80 mm i/d) 10.00 Nos. each
3 M.S. Inspection box 3" dia (80 mm) 1.00 No. each
4 G.I bend 3" dia (80 mm i/d) 1.00 No. each
5 Gutties 20.00 Nos. dozen
6 Screw 1 to " (25 to 20 mm) 1.50 Dozen dozen
7 Cement 0.021 Cft. P. Bag
8 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 2949.77 0.00

LABOUR (For 33 Metre)

1 Electrician 2.00 No. per day


2 Coolies skilled 3.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 7
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls, including hooks, cutting, jharries and repairin

(i) " dia (15 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. Pipe " dia (15 mm i/d) 7.00 metre per mtr.
2 G.I. Bend " dia (15 mm i/d) 1.00 Nos. each
3 Hooks 8.00 No. each
4 M.S. Inspection box " dia (15 mm) 1.00 Nos. each
5 Cement 0.021 Cft. P. Bag
6 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 442.55 7 0.00

LABOUR (For 25 Metre)

1 Electrician 1.00 No. per day


2 Coolies skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 8
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls, including hooks, cutting, jharries and repairin

(ii) " dia (20 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. Pipe " dia (20 mm i/d) 7.00 metre per mtr.
2 G.I. Bend " dia (20 mm i/d) 1.00 Nos. each
3 Hooks 7.00 No. each
4 M.S. Inspection box " dia (20 mm) 1.00 Nos. each
5 Cement 0.021 Cft. P. Bag
6 Sand 0.18 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 564.44 7 0.00

LABOUR (For 25 Metre)

1 Electrician 1.00 No. per day


2 Coolies skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 9
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls, including hooks, cutting, jharries and repairin

(iii) 1" dia (25 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. Pipe 1" dia (25 mm i/d) 7.00 metre per mtr.
2 G.I. Bend 1" dia (25 mm i/d) 1.00 Nos. each
3 Hooks 8.00 No. each
4 M.S. Inspection box 1" dia (25 mm) 1.00 Nos. each
5 Cement 0.052 Cft. P. Bag
6 Sand 0.18 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 820.19 7 0.00

LABOUR (For 24 Metre)

1 Electrician 1.00 No. per day


2 Coolies skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 10
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls, including hooks, cutting, jharries and repairin

(iv) 1" dia (32 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. Pipe 1" dia (32 mm i/d) 7.00 metre per mtr.
2 G.I. Bend 1" dia (32 mm i/d) 1.00 Nos. each
3 Hooks 8.00 No. each
4 M.S. Inspection box 1" dia (32 mm) 1.00 Nos. each
5 Cement 0.063 Cft. P. Bag
6 Sand 0.18 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1046.69 0.00

LABOUR (For 24 Metre)

1 Electrician 1.00 No. per day


2 Coolies skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 11
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls, including hooks, cutting, jharries and repairin

(v) 1" dia (40 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. Pipe 1" dia (40 mm i/d) 7.00 metre per mtr.
2 G.I. Bend 1" dia (40 mm i/d) 1.00 Nos. each
3 M.S. Inspection box 1" dia (40 mm i/d) 1.00 No. each
4 Hooks 8.00 Nos. each
5 Cement 0.074 Cft. P. Bag
6 Sand 0.20 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 1252.99 0.00

LABOUR (For 22 Metre)

1 Electrician 1.00 No. per day


2 Coolies skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 12
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls, including hooks, cutting, jharries and repairin

(vi) 2" dia (50 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. Pipe 2" dia (50 mm i/d) 7.00 metre per mtr.
2 G.I. Bend 2" dia (50 mm i/d) 1.00 Nos. each
3 M.S. Inspection box 2" dia (50 mm i/d) 1.00 No. each
4 Hooks 8.00 Nos. each
5 Cement 0.084 Cft. P. Bag
6 Sand 0.24 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 1679.21 0.00

LABOUR (For 16 Metre)

1 Electrician 1.00 No. per day


2 Coolies skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 13
DESCRIPTION OF ITEM:

Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls, including hooks, cutting, jharries and repairin

(vii) 3" dia (80 mm i/d).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I. Pipe 3" dia (80 mm i/d) 7.00 metre per mtr.
2 G.I. Bend 3" dia (80 mm i/d) 1.00 No. each
3 M.S. Inspection box 3" dia (80 mm) 1.00 No. each
4 Hooks 8.00 Nos. each
5 G.I. Socket 3" dia (80 mm) 1.00 No. each
6 Cement 0.08 Cft. P. Bag
7 Sand 0.24 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 2871.23 0.00

LABOUR (For 10 Metre)

1 Electrician 1.00 No. per day


2 Coolies skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 14
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.

(a) On surface, including clamps.

(i) " dia (16 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe " dia (16 mm) 7.00 metre per mtr.
2 M.S. Bend " dia (16 mm) 1.00 No. each
3 M.S. Inspection box " dia (16 mm) 1.00 No. dozen
4 Clamps " dia (16 mm) 10.00 Nos. each
5 Screw 1.20 Dozen dozen
6 Gutties 1.00 Dozen dozen

Total
Contractor's Profit & O ## Percent
Total
Material per metre 251.69 7 0.00

LABOUR (For 36 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 15
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.

(a) On surface, including clamps.

(ii) " dia (20 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe " dia (20 mm) 7.00 metre per mtr.
2 M.S. Bend " dia (20 mm) 1.00 No. each
3 M.S. Inspection box " dia (20 mm) 1.00 No. per doz.
4 M.S. Clamps " dia (20 mm) 10.00 Nos. each
5 Screw 1.20 Dozen dozen
6 Gutties 1.00 Dozen dozen
7 Cement 0.02 Cft. P. Bag
8 Sand 0.06 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 325.92 7 0.00

LABOUR (For 36 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 16
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.

(a) On surface, including clamps.

(iii) 1" dia (25 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 1" dia (25 mm) 7.00 metre per mtr.
2 M.S. Bend 1" dia (25 mm) 1.00 No. each
3 M.S. Inspection box 1" dia (25 mm) 1.00 No. per doz.
4 M.S. Clamps 1" dia (25 mm) 10.00 Nos. each
5 Screw 1.20 Dozen dozen
6 Gutties 1.00 Dozen dozen
7 Cement 0.042 Cft. P. Bag
8 Sand 0.12 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 334.40 7 0.00

LABOUR (For 36 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 17
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.

(a) On surface, including clamps.

(iv) 1" dia (32 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 1" dia (32 mm) 7.00 metre per mtr.
2 M.S. Conduit Bend 1" dia (32 mm) 1.00 No. each
3 M.S. Inspection box 1" dia (32 mm) 1.00 No. per doz.
4 M.S. Clamps 1" dia (32 mm) 10.00 Nos. each
5 Screw 1.20 Dozen dozen
6 Gutties 1.00 Dozen dozen
7 Cement 0.042 Cft. P. Bag
8 Sand 0.12 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 572.62 7 0.00

LABOUR (For 36 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 18
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.

(a) On surface, including clamps.

(v) 1" dia (40 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 1" dia (40 mm) 7.00 metre per mtr.
2 M.S. Bend 1" dia (40 mm) 1.00 No. each
3 M.S. Inspection box 1" dia (40 mm) 1.00 No. per doz.
4 M.S. Clamps 1" dia (40 mm) 10.00 Nos. each
5 Screw 1.20 Dozen dozen
6 Gutties 1.00 Dozen dozen
7 Cement 0.042 Cft. P. Bag
8 Sand 0.12 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 652.76 7 0.00

LABOUR (For 32 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 19
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.

(a) On surface, including clamps.

(vi) 2" dia (50 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 2" dia (50 mm) 7.00 metre per mtr.
2 M.S. Conduit Bend 2" dia (50 mm) 1.00 No. each
3 M.S. Inspection box 2" dia (50 mm) 1.00 No. per doz.
4 M.S. Clamps 2" dia (50 mm) 10.00 Nos. each
5 Screw 1.20 Dozen dozen
6 Gutties 1.00 Dozen dozen
7 Cement 0.042 Cft. P. Bag
8 Sand 0.12 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 822.43 7 0.00

LABOUR (For 26 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 20
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls including cutting, jharries, cost of hooks and r


surface etc.

(i) " dia (16 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe " dia (16 mm) 7.00 metre per mtr.
2 M.S. Bend " dia (16 mm) 1.00 No. each
3 M.S. Inspection box " dia (16 mm) 1.00 No. per doz.
4 M.S. Hooks 10.00 Nos. each
5 Cement 0.021 Cft. P. Bag
6 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 247.29 7 0.00

LABOUR (For 28 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 21
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls including cutting, jharries, cost of hooks and r


surface etc.

(ii) " dia (20 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Condict pipe " dia (20 mm) 7.00 metre per mtr.
2 M.S. Bend " dia (20 mm) 1.00 No. each
3 M.S. Inspection box " dia (20 mm) 1.00 No. per doz.
4 M.S. Hooks 10.00 Nos. each
5 Cement 0.042 Cft. P. Bag
6 Sand 0.12 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 310.12 7 0.00

LABOUR (For 28 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 22
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls including cutting, jharries, cost of hooks and r


surface etc.

(iii) 1" dia (25 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 1" dia (25 mm) 7.00 metre per mtr.
2 M.S. Bend 1" dia (25 mm) 1.00 No. each
3 M.S. Inspection box 1" dia (25 mm) 1.00 No. per doz.
4 Hooks 10.00 Nos. each
5 Cement 0.052 Cft. P. Bag
6 Sand 0.18 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 385.81 7 0.00

LABOUR (For 25 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 23
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls including cutting, jharries, cost of hooks and r


surface etc.

(iv) 1" dia (32 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 1" dia (32 mm) 7.00 metre per mtr.
2 M.S. Conduit Bend 1" dia (32 mm) 1.00 No. each
3 M.S. Inspection box 1" dia (32 mm) 1.00 No. per doz.
4 M.S. Hooks 10.00 Nos. each
5 Cement 0.063 Cft. P. Bag
6 Sand 0.18 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 524.22 7 0.00

LABOUR (For 24 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 24
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls including cutting, jharries, cost of hooks and r


surface etc.

(v) 1" dia (40 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 1" dia (40 mm) 7.00 metre per mtr.
2 M.S. Conduit Bend 1" dia (40 mm) 1.00 No. each
3 M.S. Inspection box 1" dia (40 mm) 1.00 No. per doz.
4 M.S. Hooks 10.00 Nos. each
5 Cement 0.074 Cft. P. Bag
6 Sand 0.20 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 606.56 7 0.00

LABOUR (For 23 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 25
DESCRIPTION OF ITEM:

Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.

(b) Recessed in walls including cutting, jharries, cost of hooks and r


surface etc.

(vi) 2" dia (50 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 M.S. Conduit pipe 2" dia (50 mm) 7.00 metre per mtr.
2 M.S. Conduit Bend 2" dia (50 mm) 1.00 No. each
3 M.S. Inspection box 2" dia (50 mm) 1.00 No. per doz.
4 Hooks 10.00 Nos. each
5 Cement 0.084 Cft. P. Bag
6 Sand 0.24 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 778.43 7 0.00

LABOUR (For 22 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 26
DESCRIPTION OF ITEM:

Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in
including inspection boxes, pull boxes, hooks, cutting, jharriers
repairing surface etc., complete with all specials.

(i) " dia (12 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe " dia (12 mm) 10.00 metre per mtr.
2 PVC Bend " dia (12 mm) 2.00 No. each
3 M.S. Hook 10.00 No. each
4 PVC Inspection box " (12 mm) 2.00 Nos. per doz.
5 Cement 0.042 Cft. P. Bag
6 Sand 0.12 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 129.43 1 0.00

LABOUR (For 31 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 27
DESCRIPTION OF ITEM:

Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in
including inspection boxes, pull boxes, hooks, cutting, jharriers
repairing surface etc., complete with all specials.

(ii) " dia (20 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe " dia (20 mm) 10.00 metre per mtr.
2 PVC Bend " dia (20 mm) 2.00 No. each
3 M.S. Hook 10.00 No. each
4 PVC Inspection box " dia (20 mm) 2.00 Nos. per doz.
5 Cement 0.052 Cft. P. Bag
6 Sand 0.18 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 163.53 1 0.00

LABOUR (For 30 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 28
DESCRIPTION OF ITEM:

Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in
including inspection boxes, pull boxes, hooks, cutting, jharriers
repairing surface etc., complete with all specials.

(iii) 1" dia (25 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 1" dia (25 mm) 10.00 metre per mtr.
2 PVC Bend 1" dia (25 mm) 2.00 No. each
3 M.S. Hook 10.00 No. each
4 PVC Inspection box 1" dia (25 mm) 2.00 Nos. per doz.
5 Cement 0.063 Cft. P. Bag
6 Sand 0.18 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 235.03 1 0.00

LABOUR (For 27 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 29
DESCRIPTION OF ITEM:

Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in
including inspection boxes, pull boxes, hooks, cutting, jharriers
repairing surface etc., complete with all specials.

(iv) 1" dia (30 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 1" dia (30 mm) 10.00 metre per mtr.
2 PVC Bend 1" dia (30 mm) 2.00 No. each
3 M.S. Hook 10.00 No. each
4 PVC Inspection box 1" dia (30 mm) 2.00 Nos. per doz.
5 Cement 0.065 Cft. P. Bag
6 Sand 0.37 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 228.053 1 0.00

LABOUR (For 25 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 30
DESCRIPTION OF ITEM:

Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in
including inspection boxes, pull boxes, hooks, cutting, jharriers
repairing surface etc., complete with all specials.

(v) 1" dia (40 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 1" dia (40 mm) 10.00 metre per mtr.
2 PVC Bend 1" dia (40 mm) 2.00 No. each
3 M.S. Hook 10.00 No. each
4 PVC Inspection box 1" dia (40 mm) 2.00 Nos. per doz.
5 Cement 0.070 Cft. P. Bag
6 Sand 0.40 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 454.67 1 0.00

LABOUR (For 24 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 31
DESCRIPTION OF ITEM:

Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in
including inspection boxes, pull boxes, hooks, cutting, jharriers
repairing surface etc., complete with all specials.

(vi) 2" dia (50 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 2" dia (50 mm) 10.00 metre per mtr.
2 PVC Bend 2" dia (50 mm) 2.00 No. each
3 M.S. Hook 10.00 No. each
4 Cement 0.084 Cft. P. Bag
5 Sand 0.24 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 625.35 1 0.00

LABOUR (For 23 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 32
DESCRIPTION OF ITEM:

Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including
inspection boxes, pull boxes bends, tees repairing surface etc.,
with all specials.

(i) " dia (12 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe " dia (12 mm) 10.00 metre per mtr.
2 PVC Bend " dia (12 mm) 2.00 Nos. each
3 M.S. Clamp/saddle 20.00 Nos. each
4 Gutties 20.00 Nos. each
5 Screws for " dia clamp 20.00 Nos. per doz.
6 PVC Inspection Box " dia (12 mm) 2.00 Nos. per doz.
7 Cement 0.021 Cft. P. Bag
8 Sand 0.06 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 176.37 1 0.00

LABOUR (For 80 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 33
DESCRIPTION OF ITEM:

Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including
inspection boxes, pull boxes bends, tees repairing surface etc.,
with all specials.

(ii) " dia (20 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe " dia (20 mm) 10.00 metre per mtr.
2 PVC Bend " dia (20 mm) 2.00 Nos. each
3 M.S. Clamp " dia (20 mm) 10.00 Nos. each
4 Screws for " dia clamp 20.00 Nos. per doz.
5 PVC Inspection Box " dia (20 mm) 2.00 Nos. per doz.
6 Cement 0.021 Cft. P. Bag
7 Sand 0.06 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 186.27 1 0.00

LABOUR (For 80 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 34
DESCRIPTION OF ITEM:

Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including
inspection boxes, pull boxes bends, tees repairing surface etc.,
with all specials.

(iii) 1" dia (25 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 1" dia (25 mm) 10.00 metre per mtr.
2 PVC Bend 1" dia (25 mm) 2.00 Nos. each
3 M.S. Clamp/saddle 1 dia (25 mm) 20.00 Nos. each
4 Screws for 1" dia clamp 20.00 Nos. per doz.
5 Gutties 20.00 Nos. per doz.
6 PVC Inspection Box 1" dia (25 mm) 2.00 Nos. per doz.
7 Cement 0.021 Cft. P. Bag
8 Sand 0.06 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 347.23 1 0.00

LABOUR (For 80 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 35
DESCRIPTION OF ITEM:

Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including
inspection boxes, pull boxes bends, tees repairing surface etc.,
with all specials.

(iv) 1" dia (30 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 1" dia (30 mm) 10.00 metre per mtr.
2 PVC Bend 1" dia (30 mm) 2.00 Nos. each
3 M.S. Clamp/saddle 1" dia (30 mm) 20.00 Nos. each
4 Gutties 20.00 Nos. per doz.
5 Screws for 1" dia clamp 20.00 Nos. per doz.
6 PVC Inspection Box 1" dia (30 mm) 2.00 Nos. per doz.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 484.73 1 0.00

LABOUR (For 70 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 36
DESCRIPTION OF ITEM:

Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including
inspection boxes, pull boxes bends, tees repairing surface etc.,
with all specials.

(v) 1" dia (40 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 1" dia (40 mm) 10.00 metre per mtr.
2 PVC Bend 1" dia (40 mm) 2.00 Nos. each
3 M.S. Clamp/saddle 1" dia (40 mm) 20.00 Nos. each
4 Gutties 20.00 Nos. per doz.
5 Screws for 1" dia clamp 20.00 Nos. per doz.
6 PVC Inspection Box 1" dia (40 mm) 2.00 Nos. per doz.
7 Cement 0.021 Cft. P. Bag
8 Sand 0.06 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 619.67 1 0.00

LABOUR (For 70 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 37
DESCRIPTION OF ITEM:

Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including
inspection boxes, pull boxes bends, tees repairing surface etc.,
with all specials.

(vi) 2" dia (50 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC pipe 2" dia (50 mm) 10.00 metre per mtr.
2 PVC Bend 2" dia (50 mm) 2.00 Nos. each
3 M.S. Clamp/saddle 2" dia (50 mm) 20.00 Nos. each
4 Gutties 20.00 Nos. per doz.
5 Screws for 2" dia clamp 20.00 Nos. per doz.
6 PVC Inspection Box 2" dia (50 mm) 2.00 Nos. per doz.
7 Cement 0.021 Cft. P. Bag
8 Sand 0.06 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 860.02 1 0.00

LABOUR (For 58 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 38
DESCRIPTION OF ITEM:

Item No. 5 Supply and erection of G.I Flexible pipe for wiring including weld
sockets, nipples and check nuts etc complete.

(i) " dia (12 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Flexible Pipe " dia (12 mm) 1.00 metre per mtr.
2 Socket " dia (12 mm) 2.00 Nos. each
3 Nipple " dia (12 mm) 2.00 Nos. each
4 Check Nuts " dia (12 mm) 2.00 Nos. each
5 Soldering etc. L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 32 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day
3 Welding charges 2.00 joints per joints

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 39
DESCRIPTION OF ITEM:

Item No. 5 Supply and erection of G.I Flexible pipe for wiring including weld
sockets, nipples and check nuts etc complete.

(ii) " dia (20 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Flexible Pipe " dia (20 mm) 1.00 metre per mtr.
2 G.I. Socket " dia (20 mm) 2.00 Nos. each
3 G.I. Nipple " dia (20 mm) 2.00 Nos. each
4 Check Nuts " dia (20 mm) 2.00 Nos. each
5 Solder joint L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 30 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day
3 Welding charges 2.00 joints per joint

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 40
DESCRIPTION OF ITEM:

Item No. 5 Supply and erection of G.I Flexible pipe for wiring including weld
sockets, nipples and check nuts etc complete.

(iii) 1" dia (25 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Flexible Pipe 1" dia (25 mm) 1.00 metre per mtr.
2 G.I. Socket 1" dia (25 mm) 2.00 Nos. each
3 G.I. Nipple 1" dia (25 mm) 2.00 Nos. each
4 Check Nuts 1" dia (25 mm) 2.00 Nos. each
5 Solder L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 29 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day
3 Welding charges 2.00 joints per joints

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 41
DESCRIPTION OF ITEM:

Item No. 5 Supply and erection of G.I Flexible pipe for wiring including weld
sockets, nipples and check nuts etc complete.

(iv) 1" dia (32 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Flexible Pipe 1" dia (32 mm) 1.00 metre per mtr.
2 G.I. Socket 1" dia (32 mm) 2.00 Nos. each
3 G.I. Nipple 1" dia (32 mm) 2.00 Nos. each
4 Check Nuts 1" dia (32 mm) 2.00 Nos. each
5 Solder L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 24 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day
3 Welding charges 2.00 joints per joints

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 42
DESCRIPTION OF ITEM:

Item No. 5 Supply and erection of G.I Flexible pipe for wiring including weld
sockets, nipples and check nuts etc complete.

(v) 1" dia (40 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Flexible Pipe 1" dia (40 mm) 1.00 metre per mtr.
2 G.I. Socket 1" dia (40 mm) 2.00 Nos. each
3 G.I. Nipple 1" dia (40 mm) 2.00 Nos. each
4 Check Nuts 1" dia (40 mm) 2.00 Nos. each
5 Solder L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 22 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day
3 Welding charges 2.00 joints per joints

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 43
DESCRIPTION OF ITEM:

Item No. 5 Supply and erection of G.I Flexible pipe for wiring including weld
sockets, nipples and check nuts etc complete.

(vi) 2" dia (50 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Flexible Pipe 2" dia (50 mm) 1.00 metre per mtr.
2 G.I. Socket 2" dia (50 mm) 2.00 Nos. each
3 G.I. Nipple 2" dia (50 mm) 2.00 Nos. each
4 Check Nuts 2" dia (50 mm) 2.00 Nos. each
5 Solder L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 20 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day
3 Welding charges 2.00 joints per joints

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 44
DESCRIPTION OF ITEM:

Item No. 5 Supply and erection of G.I Flexible pipe for wiring including weld
sockets, nipples and check nuts etc complete.

(vii) 3" dia (80 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Flexible Pipe 3" dia (80 mm) 1.00 metre per mtr.
2 G.I. Socket 3" dia (80 mm) 2.00 Nos. each
3 G.I. Nipple 3" dia (80 mm) 2.00 Nos. each
4 Check Nuts 3" dia (80 mm) 2.00 Nos. each
5 Solder L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 15 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day
3 Welding charges 2.00 joints per joints

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 45
DESCRIPTION OF ITEM:

Item No. 6 Supply and erection of PVC pipe for recessed wiring (main and sub-
purposes including bends special etc., in floor, wall or trenches

(i) 2" dia (50 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC Pipe 2" dia (50 mm) 10.00 metre per mtr.
2 PVC Bend 2" dia (50 mm) 2.00 Nos. each
3 M.S Hooks 10.00 Nos. each
4 PVC Inspection box 2.00 Nos. per doz.
5 Cement 0.084 Cft. P. Bag
6 Sand 0.24 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 631.22 0.00

LABOUR (For 23 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 46
DESCRIPTION OF ITEM:

Item No. 6 Supply and erection of PVC pipe for recessed wiring (main and sub-
purposes including bends special etc., in floor, wall or trenches

(ii) 3" dia (80 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC Pipe 3" dia (75 mm) 10.00 metre per mtr.
2 PVC Bend 3" dia (75 mm) 2.00 Nos. each
3 PVC Inspection box 2.00 Nos. per doz.
4 Cement 0.106 Cft. P. Bag
5 Sand 0.25 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 818.58 0.00

LABOUR (For 20 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 47
DESCRIPTION OF ITEM:

Item No. 6 Supply and erection of PVC pipe for recessed wiring (main and sub-
purposes including bends special etc., in floor, wall or trenches

(iii) 4" dia (100 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC Pipe 4" dia (100 mm) 10.00 metre per mtr.
2 PVC Bend 4" dia (100 mm) 2.00 Nos. each
3 PVC Inspection box 2.00 Nos. per doz.
4 Cement 0.106 Cft. P. Bag
5 Sand 0.25 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 1141.80 0.00

LABOUR (For 20 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 48
DESCRIPTION OF ITEM:

Item No. 7 Supply and erection of PVC pipe for on surface wiring (main and su
including clamps bends etc., complete with all specials.

(i) 2" dia (50 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC Pipe 2" dia (50 mm) 10.00 metre per mtr.
2 PVC Bend 2" dia (50 mm) 2.00 Nos. each
3 M.S Clamp 20.00 Nos. each
4 PVC Inspection boxes 2.00 Nos. per doz.
5 Gutties 20.00 Nos. per doz.
6 Cement 0.021 Cft. P. Bag
7 Sand 0.06 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 802.27 1 0.00

LABOUR (For 58 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 49
DESCRIPTION OF ITEM:

Item No. 7 Supply and erection of PVC pipe for on surface wiring (main and su
including clamps bends etc., complete with all specials.

(ii) 3" dia (80mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC Pipe 3" dia (75 mm) 10.00 metre per mtr.
2 PVC Bend 3" dia (75 mm) 2.00 Nos. each
3 M.S Clamp 20.00 Nos. each
4 PVC Inspection boxes 2.00 Nos. per doz.
5 Screws for 3" dia clamp 40.00 Nos. per doz.
6 Gutties 40.00 Nos. per doz.
7 Cement 0.042 Cft. P. Bag
8 Sand 0.12 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 1155.92 0.00

LABOUR (For 40 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 50
DESCRIPTION OF ITEM:

Item No. 7 Supply and erection of PVC pipe for on surface wiring (main and su
including clamps bends etc., complete with all specials.

(iii) 4" dia (100 mm dia).

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 PVC Pipe 4" dia (100 mm) 10.00 metre per mtr.
2 PVC Bend 4" dia (100 mm) 2.00 Nos. each
3 M.S Clamp 20.00 Nos. each
4 Gutties 40.00 Nos. per doz.
5 Screws for 4" dia clamp 40.00 Nos. per doz.
6 PVC Inspection boxes 2.00 Nos. per doz.
7 Cement 0.084 Cft. P. Bag
8 Sand 0.24 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 1533.77 0.00

LABOUR (For 35 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 51
DESCRIPTION OF ITEM:

Item No. 8 Supply and erection of wooden strip batten for wiring purposes inc
insulation cleats etc.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 100 Metre)

1 Strip casing 100.00 metre % per mtr.


2 Gutties 10.00 Nos. per doz.
3 Clamp & nails 300.00 Nos. % No.
4 Screw 7.25 Dozen Dozen
5 Insulated cleats 100.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total
Material per metre 491.70 1 0.00

LABOUR (For 200 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 52
DESCRIPTION OF ITEM:

Item No. 9 Supply and erection of sahl wood casing and capping for wiring pur
including insulation cleats, screws etc., complete.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 100 Metre)

1 Casing Sahlwood 100.00 metre per mtr.


2 Screw 20.00 Nos. P. Doz.
3 Gutties 20.00 Nos. per doz.
4 Insulated cleats 20.00 Nos. each
5 Screw for cover 0.60 Dozen Dozen

Total
Contractor's Profit & O ## Percent
Total
Material per metre 2662.00 0.00

LABOUR (For 200 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 53
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(i) 3/0.74 mm (3/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.029" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 439.49 9 0.00

LABOUR (For 100 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 54
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(ii) 3/0.91 mm (3.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.036" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 636.29 9 0.00

LABOUR (For 100 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 55
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(iii) 7/0.74 mm (7/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.029" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 908.55 9 0.00

LABOUR (For 100 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 56
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(iv) 7/0.91 mm (7/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.036" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 1150.22 0.00

LABOUR (For 90 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 57
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(v) 7/1.12 mm (7/0.044")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.044" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 1640.70 0.00

LABOUR (For 80 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 58
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(vi) 7/1.63 mm (7/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.064" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 4371.45 0.00

LABOUR (For 65 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 59
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(vii) 19/1.32 mm (19/0.052")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.052" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 5759.90 0.00

LABOUR (For 70 Metre)

1 Electrician 2.00 Nos. per day


2 Cooly skilled 3.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 60
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).

(a) 250/440 Volts PVC insulated.

(viii) 19/1.63 mm (19/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.064" = 1 coil 90.00 metre per 90 mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 13464.0 0.00

LABOUR (For 60 Metre)

1 Electrician 2.00 Nos. per day


2 Cooly skilled 3.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 61
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).

(b) 250/440 volts. PVC insulated cotton braided and compounded cables.

(i) 3/0.74 mm (3/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.029" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 509.85 9 0.00

LABOUR (For 90 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 62
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).

(b) 250/440 volts. PVC insulated cotton braided and compounded cables.

(ii) 3/0.91 mm (3/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.036" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 611.82 9 0.00

LABOUR (For 90 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 63
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).

(b) 250/440 volts. PVC insulated cotton braided and compounded cables.

(iii) 7/0.74 mm (7/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.029" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 815.76 9 0.00

LABOUR (For 90 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 64
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).

(b) 250/440 volts. PVC insulated cotton braided and compounded cables.

(iv) 7/0.91 mm (7/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.036" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 968.72 9 0.00

LABOUR (For 85 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 65
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).

(b) 250/440 volts. PVC insulated cotton braided and compounded cables.

(v) 7/1.12 mm (7/0.044")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.044" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 1529.55 0.00

LABOUR (For 76 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 66
DESCRIPTION OF ITEM:

Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).

(b) 250/440 volts. PVC insulated cotton braided and compounded cables.

(vi) 7/1.63 mm (7/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.064" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 4078.80 0.00

LABOUR (For 66 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 67
DESCRIPTION OF ITEM:

Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copp
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pi
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).

(i) 3/0.74 mm (3/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.029" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 505.77 9 0.00

LABOUR (For 100 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 68
DESCRIPTION OF ITEM:

Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copp
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pi
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).

(ii) 3/0.91 mm (3/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.036" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 740.30 9 0.00

LABOUR (For 100 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 69
DESCRIPTION OF ITEM:

Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copp
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pi
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).

(iii) 7/0.74 mm (7/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.074" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 1008.48 0.00

LABOUR (For 100 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 70
DESCRIPTION OF ITEM:

Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copp
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pi
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).

(iv) 7/0.91 mm (7/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.036" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 1517.31 0.00

LABOUR (For 90 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 71
DESCRIPTION OF ITEM:

Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copp
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pi
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).

(v) 7/1.12 mm (7/0.044")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.044" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 2143.41 0.00

LABOUR (For 80 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 72
DESCRIPTION OF ITEM:

Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copp
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pi
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).

(vi) 7/1.63 mm (7/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.064" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 4443.85 0.00

LABOUR (For 65 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 73
DESCRIPTION OF ITEM:

Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed cop
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S con
pipe/G.I wire/trenches etc., (rate per cable only).

(i) 7/1.63 mm (7/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.064" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 4329.01 0.00

LABOUR (For 66 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 74
DESCRIPTION OF ITEM:

Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed cop
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S con
pipe/G.I wire/trenches etc., (rate per cable only).

(ii) 19/0.32 mm (19/0.052")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.052" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 5759.90 0.00

LABOUR (For 60 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 75
DESCRIPTION OF ITEM:

Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed cop
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S con
pipe/G.I wire/trenches etc., (rate per cable only).

(iii) 19/0.63 mm (19/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.064" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 7847.16 0.00

LABOUR (For 55 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 76
DESCRIPTION OF ITEM:

Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed cop
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S con
pipe/G.I wire/trenches etc., (rate per cable only).

(iv) 19/2.11 mm (19/0.083")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.083" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 12207.59 0.00

LABOUR (For 50 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 77
DESCRIPTION OF ITEM:

Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed cop
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S con
pipe/G.I wire/trenches etc., (rate per cable only).

(v) 37/1.83 mm (37/0.072")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 37/0.072" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 21264.40 0.00

LABOUR (For 29 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 78
DESCRIPTION OF ITEM:

Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed cop
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S con
pipe/G.I wire/trenches etc., (rate per cable only).

(vi) 37/2.11 mm (37/0.083")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 37/0.083" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 26390.11 0.00

LABOUR (For 24 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 79
DESCRIPTION OF ITEM:

Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed cop
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S con
pipe/G.I wire/trenches etc., (rate per cable only).

(vii) 37/2.62 mm (37/0.103")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 37/0.103" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 40719.18 0.00

LABOUR (For 17 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 80
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(a) PVC insulated, PVC sheathed twin core, 250/440 volts.

(i) 3/0.74 mm (3/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.029" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 90 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 81
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(a) PVC insulated, PVC sheathed twin core, 250/440 volts.

(ii) 3/0.91 mm (3/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.036" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 90 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 82
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(a) PVC insulated, PVC sheathed twin core, 250/440 volts.

(iii) 7/0.74 mm (7/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.029" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 90 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 83
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(a) PVC insulated, PVC sheathed twin core, 250/440 volts.

(iv) 7/0.91 mm (7/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.036" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 85 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 84
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(a) PVC insulated, PVC sheathed twin core, 250/440 volts.

(v) 7/1.12 mm (7/0.044")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.044" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 76 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 85
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(a) PVC insulated, PVC sheathed twin core, 250/440 volts.

(vi) 7/1.63 mm (7/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.064" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 66 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 86
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(b) PVC insulated, PVC sheathed 3 core, 660/1100 volt cable.

(i) 3/0.74 mm (3/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3 core 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 85 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 87
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(b) PVC insulated, PVC sheathed 3 core, 660/1100 volt cable.

(ii) 3/0.91 mm (3/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3 core 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 85 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 88
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(b) PVC insulated, PVC sheathed 3 core, 660/1100 volt cable.

(iii) 3/0.74 mm (7/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.029" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 85 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 89
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(b) PVC insulated, PVC sheathed 3 core, 660/1100 volt cable.

(iv) 7/0.91 mm (7/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.036" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 76 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 90
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(b) PVC insulated, PVC sheathed 3 core, 660/1100 volt cable.

(v) 7/1.12 mm (7/0.044")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.044" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 72 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 91
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(b) PVC insulated, PVC sheathed 3 core, 660/1100 volt cable.

(vi) 7/1.13 mm (7/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.064" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 63 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 92
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cabl

(i) 3/70.74 m,m (3/0.29")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.029" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 80 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 93
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cabl

(ii) 3/0.91 mm (3/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 3/0.036" = 1 coil 90.00 metre per mtr.


Wastage (3%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 80 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 94
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cabl

(iii) 7/0.74 mm (7/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.029" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 76 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 95
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cabl

(iv) 7/0.91 mm (7/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.036" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 76 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 96
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cabl

(v) 7/1.12 mm (7/0.044")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.044" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 72 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 97
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cabl

(vi) 7/1.63 mm (7/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 7/0.064" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 63 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 98
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cabl

(vii) 19/1.32 mm (19/0.052")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.052" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 45 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 99
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
wire 16 SWG.

(i) 19/1.32 mm (19/0.052")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.052" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 11164.35 0.00

LABOUR (For 45 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 100
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
wire 16 SWG.

(ii) 19/1.63 mm (19/0.064")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.064" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 42 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 101
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
G.I wire 16 SWG.

(iii) 19/1.83 mm (19/0.072")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.072" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre 21288.60 0.00

LABOUR (For 40 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 102
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
G.I wire 16 SWG.

(iv) 19/2.11 mm (19/0.083")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 19/0.083" = 1 coil 90.00 per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 37 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 103
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
wire 16 SWG.

(v) 37/1.83 mm (37/0.072")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 37/0.072" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 36 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 104
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
wire 16 SWG.

(vi) 37/2.11 mm (37/0.083")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 37/0.083" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 30 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 105
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
wire 16 SWG.

(vii) 37/2.36 mm (37/0.093")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 37/0.093" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 25 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 106
DESCRIPTION OF ITEM:

Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).

(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
wire 16 SWG.

(viii) 37/2.62 mm (37/0.103")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 90 Metre)

1 PVC cable 37/0.103" = 1 coil 90.00 metre per mtr.


Wastage (2%)

Total
Contractor's Profit & O ## Percent
Total
Material per metre

LABOUR (For 20 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 107
DESCRIPTION OF ITEM:

Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm)
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring
making holes for regulators, switches, plugs, etc.

(i) 10 x 10 cm (4" x 4") (100 x 100 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 M.S Box 4" x 4" (100 x 100 mm) 1.00 No. each
2 Cement 0.021 Cft. P. Bag
3 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 20 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 108
DESCRIPTION OF ITEM:

Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm)
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring
making holes for regulators, switches, plugs, etc.

(ii) 17.5 x 10 cm (7" x 4") (175 x 100 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 M.S Box 7" x 4" (175 x 100 mm) 1.00 No. each
2 Cement 0.026 Cft. P. Bag
3 Sand 0.09 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 16 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 109
DESCRIPTION OF ITEM:

Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm)
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring
making holes for regulators, switches, plugs, etc.

(iii) 22.5 x 10 cm (9" x 4") (225 x 100 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 M.S Box 9" x 4" (225 x 100 mm) 1.00 No. each
2 Cement 0.032 Cft. P. Bag
3 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 12 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 110
DESCRIPTION OF ITEM:

Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm)
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring
making holes for regulators, switches, plugs, etc.

(iv) 20 x 25 cm (8" x 10") (200 x 250 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 M.S Box 8" x 10" (200 x 250 mm) 1.00 No. each
2 Cement 0.036 Cft. P. Bag
3 Sand 0.150 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 10 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Page 111
Labour rate for Each Rs. Say
Composite rate for Each Rs. Say

DESCRIPTION OF ITEM:

Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm)
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring
making holes for regulators, switches, plugs, etc.

(v) 25 x 30 cm (10" x 12") (250 x 300 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 M.S Box 10" x 12" (250 x 300 mm) 1.00 No. each
2 Cement 0.047 Cft. P. Bag
3 Sand 0.155 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 8 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 112
DESCRIPTION OF ITEM:

Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm)
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring
making holes for regulators, switches, plugs, etc.

(vi) 30 x 35 cm (12" x 14") (300 x 350 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 M.S Box 12" x 14" (300 x 350 mm) 1.00 No. each
2 Cement 0.052 Cft. P. Bag
3 Sand 0.180 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 113
DESCRIPTION OF ITEM:

Item No. 15 Supply and erectionof round block of Sahl wood, 10 x 4 cm 4" x 1"
(100 x 40 mm).

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Round block 0.544 No. each


2 W. Gutti 1" x 1" (40 x 25 mm) 1.00 No. per doz.
3 Screw 1.00 Dozen per doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 70 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 114
DESCRIPTION OF ITEM:

Item No. 16 Supply and erection of teak wood board, 4.5 cm 1" (45 mm) thick.

(i) 17.5 x 10 cm (7" x 4") (175 x 100 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Teak Wood Board 7" x 4" (175 x 100 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 115
DESCRIPTION OF ITEM:

Item No. 16 Supply and erection of teak wood board, 4.5 cm 1" (45 mm) thick.

(ii) 22.5 x 10 cm (9" x 4") (225 x 100 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Teak Wood Board 9" x 4" (225 x 100 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 116
DESCRIPTION OF ITEM:

Item No. 16 Supply and erection of teak wood board, 4.5 cm 1" (45 mm) thick.

(iii) 20 x 25 cm (8" x 10") (200 x 250 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Teak Wood Board 8" x 10" (200 x 250 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 45 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 117
DESCRIPTION OF ITEM:

Item No. 16 Supply and erection of teak wood board, 4.5 cm 1" (45 mm) thick.

(iv) 25 x 30 cm (10" x 12") (250 x 300 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Teak Wood Wooden Board 10" x 12" (250 x 300 mm) 1.00 No. each
2 W. Gutti 4.00 Nos. per dozen
3 Screw 4.00 Nos. per dozen

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 40 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 118
DESCRIPTION OF ITEM:

Item No. 16 Supply and erection of teak wood board, 4.5 cm 1" (45 mm) thick.

(v) 30 x 35 cm (12" x 14") (300 x 350 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Teak Wood Board 12" x 14" (300 x 350 mm) 1.00 No. each
2 W. Gutti 4.00 Nos. per dozen
3 Screw 4.00 Nos. per dozen

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 35 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 119
DESCRIPTION OF ITEM:

Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1" (45 mm) thick.

(i) 17.5 x 10 cm (7" x 4") (175 x 100 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Sahl Wood Board 7" x 4" (175 x 100 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 120
DESCRIPTION OF ITEM:

Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1" (45 mm) thick.

(ii) 22.5 x 10 cm (9" x 4") (225 x 100 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Sahl Wood Board 9" x 4" (225 x 100 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 121
DESCRIPTION OF ITEM:

Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1" (45 mm) thick.

(iii) 20 x 25 cm (8" x 10") (200 x 250 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Sahl Wood Board 8" x 10" (200 x 250 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 45 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 122
DESCRIPTION OF ITEM:

Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1" (45 mm) thick.

(iv) 25 x 30 cm (10" x 12") (250 x 300 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Sahl Wood Board 10" x 12" (250 x 300 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 40 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 123
DESCRIPTION OF ITEM:

Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1" (45 mm) thick.

(v) 30 x 35 cm (12" x 14") (300 x 350 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Sahl Wood Board 12" x 14" (300 x 350 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 35 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 124
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.

(a) Double pole:

(i) Main Switch 15/20 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main switch 15/20 Amp. 500 volts 1.00 No. each


2 G.I Flexible pipe 1" dia (25 mm) 0.50 metre per mtr.
3 Angle iron board including paints (9"x9"x1") 1.00 No. each
4 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. % No.
5 Nipple 1" dia (25 mm) 2.00 Nos. each
6 Socket 1" dia (25 mm) 3.00 Nos. each
7 Check nut 1" dia (25 mm) 1.00 No. each
8 Thimble 8.00 Nos. each
9 Cement 0.032 Cft. P. Bag
10 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 125
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.

(a) Double pole:

(ii) Main switch 30/35 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 30/35 Amp. 500 volts 1.00 No. each


2 G.I Flexible pipe 1" dia (25 mm) 0.50 metre per mtr.
3 L-Iron board including paint (9"x12"x1") 1.00 No. each
4 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. % No.
5 Nipple 1" dia (25 mm) 2.00 Nos. each
6 Socket 1" dia (25 mm) 3.00 Nos. each
7 Check nut 1" dia (25 mm) 1.00 No. each
8 Thimble 8.00 Nos. each
9 Cement 0.032 Cft. P. Bag
10 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 126
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.

(a) Double pole:

(iii) Main switch 60/65 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 60/65 Amp. 500 volts 1.00 No. each


2 G.I Flexible pipe 1" dia (38 mm) 0.50 metre per mtr.
3 L-Iron board including paint (10"x12"x1") 1.00 No. each
4 Nipple 1" dia (38 mm) 2.00 Nos. each
5 Socket 1" dia (38 mm) 2.00 Nos. each
6 Check nut 1" dia (38 mm) 2.00 Nos. each
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. % No.
8 Cement 0.032 Cft. P. Bag
9 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 127
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.

(a) Double pole:

(iv) Main switch 100 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 100 Amp. 500 volts 1.00 No. each


2 G.I Flexible pipe 1" dia (38 mm) 0.50 metre per mtr.
3 L-Iron board including paint (10"x12"x1") 1.00 No. each
4 Nipple 1" dia (38 mm) 2.00 Nos. each
5 Socket 1" dia (38 mm) 2.00 Nos. each
6 Check nut 1" dia (38 mm) 2.00 Nos. each
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. % No.
8 Cement 0.032 Cft. P. Bag
9 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 128
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.

(b) Triple pole:

(i) Main switch 15/20 Amp (500 Volts).

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 15/20 Amp. 500 volts 1.00 No. each


2 G.I Flexible pipe 1" dia (25 mm) 0.50 metre per mtr.
3 L-Iron board including paint (9"x12"x1") 1.00 No. each
4 Nipple 1" dia (25 mm) 2.00 Nos. each
5 Socket 1" dia (25 mm) 2.00 Nos. each
6 Check nut 1" dia (25 mm) 2.00 Nos. each
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. % No.
8 Cement 0.032 Cft. P. Bag
9 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 129
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.

(b) Triple pole:

(ii) Main switch 30/35 Amp (500 Volts).

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 30/35 Amp. 500 volts 1.00 No. each


2 L-Iron board including paint (10"x12"x1") 1.00 No. each
3 G.I Flexible pipe 1" dia (25 mm) 0.50 metre per mtr.
4 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. % No.
5 Nipple 1" dia (25 mm) 2.00 Nos. each
6 Socket 1" dia (25 mm) 2.00 Nos. each
7 Check nut 1" dia (25 mm) 2.00 Nos. each
8 Thimble 8.00 Nos. each
9 Cement 0.032 Cft. P. Bag
10 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 130
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.

(c) Triple pole, with neutral link:

(i) Main switch 30/35 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 30/35 Amp. 500 volts 1.00 No. each


2 L-Iron board including paint (10"x12"x1") 1.00 No. each
3 G.I Flexible pipe 1" dia (25 mm) 0.50 metre per mtr.
4 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. % No.
5 Nipple 1" dia (25 mm) 2.00 Nos. each
6 Socket 1" dia (25 mm) 2.00 Nos. each
7 Check nut 1" dia (25 mm) 2.00 Nos. each
8 Thimble 8.00 Nos. each
9 Cement 0.032 Cft. P. Bag
10 Sand 0.08 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 131
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.

(c) Triple pole, with neutral link:

(ii) Main switch 60/65 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 60/65 Amp. 500 volts 1.00 No. each


2 L-Iron board including paint (12"x15"x1") 1.00 No. each
3 G.I Flexible pipe 1" dia (32 mm) 0.50 metre per mtr.
4 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. % No.
5 Nipple 1" dia (40 mm) 2.00 Nos. each
6 Socket 1" dia (32 mm) 2.00 Nos. each
7 Check nut 1" dia (32 mm) 2.00 Nos. each
8 Cement 0.052 Cft. P. Bag
9 Sand 0.18 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 132
DESCRIPTION OF ITEM:

Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.

(c) Triple pole, with neutral link:

(iii) Main switch 100 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 100 Amp. 500 volts 1.00 No. each


2 L-Iron board including paint (12"x18"x1") 1.00 No. each
3 G.I Flexible pipe 1" dia (40 mm) 0.50 metre per mtr.
4 Brass Nipple 1" dia (40 mm) 2.00 Nos. each
5 Socket 1" dia (40 mm) 2.00 Nos. each
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. each
8 Cement 0.052 Cft. P. Bag
9 Sand 0.18 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.62 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 133
DESCRIPTION OF ITEM:

Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switche
pole and neutral link and HRC fuses, on angle iron board with 3 mm
thick M.S sheet covering, including bonding to earth with necessar
pipe and thimbles.

(i) 60/65 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch with triple pole and 1.00 No. each


2 Flexible pipe 1" (40 mm) 0.50 metre per mtr.
3 L-Iron board including paint (10"x15"x1") 1.00 No. each
4 Brass Nipple 1" dia (40 mm) 2.00 Nos. each
5 Brass check nut 1" (40 mm) 2.00 Nos. each
6 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. each
7 Brass Socket 1" dia (40 mm) 2.00 Nos. each
8 Thimble 60/65 Amp 4.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 134
DESCRIPTION OF ITEM:

Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switche
pole and neutral link and HRC fuses, on angle iron board with 3 mm
thick M.S sheet covering, including bonding to earth with necessar
pipe and thimbles.

(ii) 100 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 100 Amp. 500 volts 1.00 No. each


2 Flexible pipe 1" (40 mm) 0.50 metre per mtr.
3 L-Iron board including paint (12"x18"x1") 1.00 No. each
4 Brass Nipple 1" dia (32 mm) 2.00 Nos. each
5 Brass check nut 1" (32 mm) 2.00 Nos. each
6 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. each
7 Brass Socket 1" dia (40 mm) 2.00 Nos. each
8 Thimble 100 Amp. 4.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.62 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 135
DESCRIPTION OF ITEM:

Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switche
pole and neutral link and HRC fuses, on angle iron board with 3 mm
thick M.S sheet covering, including bonding to earth with necessar
pipe and thimbles.

(iii) 150 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 150 Amp. 500 volts 1.00 No. each


2 L-Iron board including paint (15"x18"x1") 1.00 No. each
3 Flexible pipe 1" (40 mm) 0.50 metre per mtr.
4 Brass Nipple 1" dia (32 mm) 2.00 Nos. each
5 Brass Socket 1" dia (40 mm) 2.00 Nos. each
6 Thimble 150 Amp. 4.00 Nos. each
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.62 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 136
DESCRIPTION OF ITEM:

Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switche
pole and neutral link and HRC fuses, on angle iron board with 3 mm
thick M.S sheet covering, including bonding to earth with necessar
pipe and thimbles.

(iv) 200 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 200 Amp. 500 volts 1.00 No. each


2 L-Iron board including paint (15"x18"x1") 1.00 No. each
3 Flexible pipe 1" (40 mm) 0.50 metre per mtr.
4 Brass Nipple 1" dia (32 mm) 2.00 Nos. each
5 Brass Socket 1" dia (40 mm) 2.00 Nos. each
6 Brass check nut 1" (32 mm) 2.00 Nos. each
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. each
8 Copper Thimble 200 Amp. 4.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 1 No.)

1 Electrician 1.00 No. per day


2 Coolies skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 137
DESCRIPTION OF ITEM:

Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switche
pole and neutral link and HRC fuses, on angle iron board with 3 mm
thick M.S sheet covering, including bonding to earth with necessar
pipe and thimbles.

(v) 300 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 300 Amp. 500 volts 1.00 No. each


2 Flexible pipe 1" (40 mm) 0.50 metre per mtr.
3 L-Iron board including paint (15"x18"x1") 1.00 No. each
4 Brass Nipple 1" dia (32 mm) 2.00 Nos. each
5 Brass Socket 1" dia (40 mm) 2.00 Nos. each
6 Brass check nut 1" (32 mm) 2.00 Nos. each
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. each
8 Copper Thimble 300 Amp. 4.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 1 No.)

1 Electrician 1.00 No. per day


2 Coolies skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 138
DESCRIPTION OF ITEM:

Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switche
pole and neutral link and HRC fuses, on angle iron board with 3 mm
thick M.S sheet covering, including bonding to earth with necessar
pipe and thimbles.

(vi) 400 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 400 Amp. 500 volts 1.00 No. each


2 L-Iron board including paint (15"x18"x1") 1.00 No. each
3 Flexible pipe 2" (50 mm) 0.50 metre per mtr.
4 Brass Nipple 2 dia (50 mm) 2.00 Nos. each
5 Brass Socket 2" dia (50 mm) 2.00 Nos. each
6 Brass check nut 2" (50 mm) 2.00 Nos. each
7 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. each
8 Copper Thimble 400 Amp. 4.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 1 No.)

1 Electrician 1.25 No. per day


2 Coolies skilled 3.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 139
DESCRIPTION OF ITEM:

Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switche
pole and neutral link and HRC fuses, on angle iron board with 3 mm
thick M.S sheet covering, including bonding to earth with necessar
pipe and thimbles.

(vii) 500 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Main Switch 500 Amp. 500 volts 1.00 No. each


2 L-Iron board including paint (15"x18"x1") 1.00 No. each
3 Flexible pipe 4" (100 mm) 0.50 metre per mtr.
4 Brass Nipple 4" dia (100 mm) 2.00 Nos. each
5 Brass Socket 4" dia (100 mm) 2.00 Nos. each
6 Brass check nut 4" (100 mm) 2.00 Nos. each
7 Reg bolts 12" x 5/8" (300 x 16 mm) 4.00 Nos. each
8 Copper Thimble 500 Amp. 4.00 Nos. each
8 Cement 0.203 Cft. P. Bag
9 Sand 0.99 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 1 No.)

1 Electrician 1.50 Nos. per day


2 Coolies skilled 3.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 140
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(i) 2 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/aluminium clad 2 way15 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 141
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(ii) 3 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/aluminium clad 3 way15 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 142
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(iii) 4 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 4 way15 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 143
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(iv) 5 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 5 way15 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 144
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(v) 6 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 6 way15 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 145
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(vi) 7 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 7 way15 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 146
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(vii) 8 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 8 way15 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 147
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(viii) 9 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 9 way15 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 148
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(ix) 10 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 10 way15 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 149
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(x) 11 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 11 way15 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 150
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(xi) 12 way, 15 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 12 way15 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 151
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(xii) 2 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 2 way 30 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 152
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(xiii) 3 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 3 way 30 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 153
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(xiv) 4 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 4 way 30 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 154
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(xv) 5 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 5 way 30 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 155
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(xvi) 6 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 6 way 30 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 156
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(xvii) 7 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 7 way 30 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 157
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(xviii) 8 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 8 way 30 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 158
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(xix) 9 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 9 way 30 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 159
DESCRIPTION OF ITEM:

Item No. 20 Supply and erection of iron/aluminium clad, branch distribution bo


on angle iron frame of suitable size with 3 mm (1/8") M.S sheet co

(xx) 10 way, 30 Amp. per way.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron/Aluminium clad 10 way 30 Amp. per way 1.00 No. each


2 L-Iron board (9"x 9"x1") (225 x 225 x 40 mm) 1.00 No. each
3 PVC Flexible pipe " dia (12 mm) 0.50 metre per mtr.
4 PVC Socket " dia (12 mm) 4.00 Nos. each
5 PVC Nipple " dia (12 mm) 4.00 Nos. each
6 PVC Check nut " dia (12 mm) 2.00 Nos. each
7 PVC bushes " dia (12 mm) 8.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. per day


2 Coolies skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 160
DESCRIPTION OF ITEM:

Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply
copper bars, including glazed porcelain bridges, on angle iron boa
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:

(i) 60 Amp. with 4 copper bars size 1" x 1/8" (40 x 3 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Porcelain (Imported) 8.00 Nos. each


2 Copper strip 1" x 1/8" x 14" (40 x 3 x 350 mm) 4.00 Nos. each
3 Box 1.5 mm thick 1.00 No. each
4 L-Iron board 18" x 12" x 1" (450 x 300 x 40 mm) 1.00 No. each
5 Reg bolts 9 x 5/8 (225 x 16 mm) 4.00 Nos. each
6 Cement 0.063 Cft. P. Bag
7 Sand 0.18 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 1.50 Nos. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 161
DESCRIPTION OF ITEM:

Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply
copper bars, including glazed porcelain bridges, on angle iron boa
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:

(ii) 100 Amp. with 4 copper bars size 1" x 1/8" (40 x 3 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Porcelain (Imported) 8.00 Nos. each


2 Copper strip 14" x 1" x 1/8" (350 x 40 x 3 mm) 4.00 Nos. each
3 Box 1.5 mm thick 1.00 No. each
4 L-Iron board 18" x 12" x 1" (450 x 300 x 40 mm) 1.00 No. each
5 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. each
6 Cement 0.063 Cft. P. Bag
7 Sand 0.18 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 1.50 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 162
DESCRIPTION OF ITEM:

Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply
copper bars, including glazed porcelain bridges, on angle iron boa
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:

(iii) 200 Amp. with 4 copper bars size 2" x 1/8" (50 x 3 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Porcelain (Imported) 8.00 Nos. each


2 Copper strip 14" x 2" x 1/8" (350 x 50 x 3 mm) 4.00 Nos. each
3 Box 1/16 (2 mm) thick 1.00 No. each
4 L-Iron board 18" x 12" x 1" (450 x 300 x 40 mm) 1.00 No. each
5 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. each
6 Cement 0.063 Cft. P. Bag
7 Sand 0.18 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 2.00 Nos. per day


2 Coolies (helper) 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 163
DESCRIPTION OF ITEM:

Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply
copper bars, including glazed porcelain bridges, on angle iron boa
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:

(iv) 300 Amp. with 4 copper bars size 2" x 3/16" (50 x 4 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Porcelain (Imported) 8.00 Nos. each


2 Copper strip 2" x 3/16" x 14" (50 x 4 x 350 mm) 4.00 Nos. each
3 Box 1/16" (2 mm) thick 1.00 No. each
4 L-Iron board 18" x 12" x 1" (450 x 300 x 40 mm) 1.00 No. each
5 Reg bolts 2 "x 5/8" (50 x 16 mm) 4.00 Nos. each
6 Cement 0.063 Cft. P. Bag
7 Sand 0.18 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 2.50 Nos. per day


2 Coolies skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 164
DESCRIPTION OF ITEM:

Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply
copper bars, including glazed porcelain bridges, on angle iron boa
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:

(v) 500 Amp. with 4 copper bars size 2" x " (50 x 6 mm)

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Porcelain (Imported) 8.00 Nos. each


2 Copper strip 14" x 2" x " (350 x 50 x 6 mm) 4.00 Nos. each
3 Box 1/16" (2 mm) thick 1.00 No. each
4 L-Iron board 18" x 12" x 1" (450 x 300 x 40 mm) 1.00 No. each
5 Reg bolts 9" x 5/8" (225 x 16 mm) 4.00 Nos. each
6 Cement 0.084 Cft. P. Bag
7 Sand 0.24 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 2.00 Nos. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 165
DESCRIPTION OF ITEM:

Item No. 22 (i) Supply and erection of plain pendent lamp holder, complete, with b
holder and flexible twin wire 23/0.0076" upto 2 metre length (with
shade).

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Pendent lamp holder bakelite 1.00 No. each


2 Flexible twin wire 23/0.0076 (23/0.195 mm) 2.00 metre per mtr.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 24 Nos.)

1 Electrician 0.50 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 166
DESCRIPTION OF ITEM:

Item No. 22 (ii) Extra for additional length of flexible wire, beyond 2 metres.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

2 Flexible twin wire 23/0.0076 (23/0.195 mm) 1.00 metre per mtr.

Total
Contractor's Profit & O ## Percent
Total

ITEM RATE

Composite rate per Metre Rs. Say


Composite rate per ft. Rs. Say

Page 167
DESCRIPTION OF ITEM:

Item No. 23 Supply and erection of counter weight pendent with porcelain count
and fitting on bakelite lamp holder, with flexible twin wire 23/0.
(without bulb & shade).

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Flexible twin wire 23/0.0076 (23/0.195 mm) 3.00 metre per mtr.
2 Bakelite lamp holder 1.00 No. each
3 Counter weight with accessories 1.00 No. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 12 Nos.)

1 Electrician 0.50 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 168
DESCRIPTION OF ITEM:

Item No. 24 Supply and erection of stiff pendent with brass/metal pipe 6.3 cm
15 mm (") dia brass oxidised or painted along lamp holder with VI
3/0.74 mm (3/0.029").

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass pipe " dia (12 mm) 2.00 metre per mtr.
2 Canopy nipple & hook 1.00 job per job
3 Brass lamp holder 1.00 No. each
4 VIR/PVC cable 3/0.29 2.00 metre per mtr.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 30 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 169
DESCRIPTION OF ITEM:

Item No. 25 Supply and erection of 22.5 cm (9") long swan neck plain brass/ste
oxidised bracket lamp holder, complete.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass bracket 1.00 No. each


2 Brass lamp holder 1.00 No. each
3 VIR/PVC Cable 3/0.029 0.50 metre per mtr.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 29 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 170
DESCRIPTION OF ITEM:

Item No. 26 Supply and erection of wall type/pole type bracket, with double co
tight reflector, flexible wire and brass holder.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Pipe " dia (20 mm) 1.00 metre per mtr.
2 Brass nipple 1.00 No. each
3 Brass lamp holder 1.00 No. each
4 Double cone reflector 1.00 No. each
5 Flexible wire 1.00 metre per mtr.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 21 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 171
DESCRIPTION OF ITEM:

Item No. 27 Supply and erection of bakelite button holder shade, large size.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Button Switch holder 1.00 No. each


2 Bakelite screwed cover 1.84 Dozen P. Doz

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 100 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.50 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 172
DESCRIPTION OF ITEM:

Item No. 28 Supply and erection of call bell 220/250 volts, fixed on teak wood
17.5 x 10 cm (7" x 4").

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Call bell 1.00 No. each


2 Board 7" x 4" (175 x 100 mm) 1.00 No. each
3 Screw 1.85 Dozen P. Doz

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 30 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 173
DESCRIPTION OF ITEM:

Item No. 29 Supply and erection of bell push or bed switch, with 5 metre twin
wire 23/0.0076"

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Bed switch/bell push 1.00 No. each


2 Flexible wire 23/0.0076" (23/0.195 mm) 5.00 metre per mtr.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 80 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 174
DESCRIPTION OF ITEM:

Item No. 30 Supply and erection of celling rose, bakelite.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Ceiling rose 1.00 No. each


2 Iron screw 1.50 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 48 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 175
DESCRIPTION OF ITEM:

Item No. 31 Supply and erection of switches 5 Amp.

(i) Open type.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Switch 5 Amp 1.00 No. each


2 Screw 1.50 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 176
DESCRIPTION OF ITEM:

Item No. 31 Supply and erection of switches 5 Amp.

(ii) Piano type.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Switch 5 Amp piano type 1.00 No. each


2 Screw 1.50 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 177
DESCRIPTION OF ITEM:

Item No. 31 Supply and erection of switches 5 Amp.

(iii) Switch ring type, recessed.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Switch ring type 1.00 No. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 178
DESCRIPTION OF ITEM:

Item No. 31 Supply and erection of switches 5 Amp.

(iv) Switch plate type recessed.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Switch plate type 1.00 No. each


2 Screw 1.50 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 179
DESCRIPTION OF ITEM:

Item No. 31 Supply and erection of switches 5 Amp.

(v) Double control, open type.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Double control switch 1.00 No. each


2 Screw 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 44 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.25 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 180
DESCRIPTION OF ITEM:

Item No. 31 Supply and erection of switches 5 Amp.

(vi) Double control, ring type recessed.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Double control switch recessed type 1.00 No. each


2 Screw 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 44 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.25 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 181
DESCRIPTION OF ITEM:

Item No. 31 Supply and erection of switches 5 Amp.

(vii) Double control, piano type.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Double control piano type 1.00 No. each


2 Screw 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 44 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.25 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 182
DESCRIPTION OF ITEM:

Item No. 32 Supply and erection of switches 10/15 Amp.

(i) Open type.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Switch 10/15 Amp 1.00 No. each


2 Screw 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 183
DESCRIPTION OF ITEM:

Item No. 32 Supply and erection of switches 10/15 Amp.

(ii) Recessed type switch 10/15 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Switch 10/15 Amp. recessed 1.00 No. each


2 Mechine Screw 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 184
DESCRIPTION OF ITEM:

Item No. 33 Supply and erection of wall socket with 3 pin 5 Amp. shoe.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 3 pin 5 Amp wall socket 1.00 No. each


2 Shoe 1.00 No. each
3 Screw 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 185
DESCRIPTION OF ITEM:

Item No. 34 Supply and erection of 3 pin 5 Amp. wall socket.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Wall socket 3 pin 5 Amp. 1.00 No. each


2 Screw 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 186
DESCRIPTION OF ITEM:

Item No. 35 Supply and erection of 3 pin 10/15 Amp. wall socket.

(i) Open type.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Wall socket 10/15 Amp. 1.00 No. each


2 Screw 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 187
DESCRIPTION OF ITEM:

Item No. 35 Supply and erection of 3 pin 10/15 Amp. wall socket.

(ii) Wall socket 10/15 Amp. recessed.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Wall socket 10/15 Amp. recessed 1.00 No. each


2 Machine Screw 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 188
DESCRIPTION OF ITEM:

Item No. 36 Supply and erection of 3 pin switch and plug combined, recessed ty

(i) 5 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Plugs 3 pin and switch (combine) 5 Amp. 1.00 No. each


2 Machine Screw 4.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 189
DESCRIPTION OF ITEM:

Item No. 36 Supply and erection of 3 pin switch and plug combined, recessed ty

(ii) 10/15 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Plugs 3 pin and switch (combine) 10/15 Amp. 1.00 No. each
2 Machine Screw 5.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 190
DESCRIPTION OF ITEM:

Item No. 37 Supply and erection of 3 pin 10/15 Amp. wall socket with shoe open

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Wall socket 3 pin 10/15 Amp. 1.00 No. each


2 Shoe 3 pin 1.00 No. each
3 Screw 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 50 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 191
DESCRIPTION OF ITEM:

Item No. 38 Supply and erection of cut out, bakelite:

(i) Open type.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cut out bakelite 1.00 No. each


2 Screw 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 90 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 192
DESCRIPTION OF ITEM:

Item No. 38 Supply and erection of cut out, bakelite:

(ii) Recessed type cut out.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cut out 1.00 No. each


2 Machine Screw 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 90 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 193
DESCRIPTION OF ITEM:

Item No. 39 Supply and erection of button holder:

(i) Bakelite large size.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Button holder large 1.00 No. each


2 Screw 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 80 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 194
DESCRIPTION OF ITEM:

Item No. 39 Supply and erection of button holder:

(ii) Button holder Brass.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Button holder 1.00 No. each


2 Screws 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 80 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 195
DESCRIPTION OF ITEM:

Item No. 40 Supply and erection of brass bracket with holder.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass bracket with holder 1.00 No. each


2 Screw 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 60 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 196
DESCRIPTION OF ITEM:

Item No. 41 Supply and erection of bell push, open/recessed type (without flex

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Bell push 1.00 No. each


2 Screw 2.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 90 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 197
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(i) 15/20 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 15/20 Amp. 1.00 No. each


2 Screw 1.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 60 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.25 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 198
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(ii) 30/35 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 30/35 Amp. 1.00 No. each


2 Screw 1.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 55 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.25 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 199
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(iii) 60/65 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 60/65 Amp. 1.00 No. each


2 Screw 1.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 36 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.25 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 200
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(iv) 100 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 100 Amp. 1.00 No. each


2 Screw 1.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 32 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.25 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 201
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(v) 200 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 200 Amp. 1.00 No. each


2 Screw 1.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 28 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.25 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 202
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(vi) 300 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 300 Amp. 1.00 No. each


2 Screw 1.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 28 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.25 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 203
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(vii) 400 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 400 Amp. 1.00 No. each


2 Screw 1.00 Nos. P. Doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 25 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.50 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 204
DESCRIPTION OF ITEM:

Item No. 42 Supply and erection of kit kat, 500 volt:

(viii) 500 Amp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Kit kat 500 Amp. 1.00 No. each


2 Screw 2.00 No. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 25 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.50 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 205
DESCRIPTION OF ITEM:

Item No. 43 Supply and erection of tube light, including rod, choke, starter w
flexible wire, including connection from ceiling rose, etc., compl

(i) Double rod (80 watts) with two chokes and 2 starters.

Detail Unit Rate (Metric System) per Set

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Tube rod 2.00 Nos. each


2 Chokes 2.00 Nos. each
3 Starters 2.00 Nos. each
4 Frame with holder 1.00 job per job
5 Flexible wire 2.00 metre per mtr.
Hooks, Chain L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Sets)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.50 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for each Set Rs. Say


Composite rate for each Set Rs. Say

Page 206
DESCRIPTION OF ITEM:

Item No. 43 Supply and erection of tube light, including rod, choke, starter w
flexible wire, including connection from ceiling rose, etc., compl

(ii) Single rod (40 watts) with one choke and one starter.

Detail Unit Rate (Metric System) per Set

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Tube rod 1.00 No. each


2 Choke 1.00 No. each
3 Starter 1.00 No. each
4 Frame set 1.00 No. each
5 Flexible wire 2.00 metre per mtr.
Hooks, Chain L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 5 Sets)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.50 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for each Set Rs. Say


Composite rate for each Set Rs. Say

Page 207
DESCRIPTION OF ITEM:

Item No. 43 Supply and erection of tube light, including rod, choke, starter w
flexible wire, including connection from ceiling rose, etc., compl

(iii) Single round tube, 32 watts, with one choke and one starter, witho

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Round tube 32 watts 1.00 No. each


2 Starter 1.00 No. each
3 Choke 1.00 No. each
4 Holder 2.00 Nos. each
5 Base 1.00 No. each
6 Flexeble wire 2.00 metre per mtr.
7 Hooks 1.00 No. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 5 Sets)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.50 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 208
DESCRIPTION OF ITEM:

Item No. 43 Supply and erection of tube light, including rod, choke, starter w
flexible wire, including connection from ceiling rose, etc., compl

(iv) Round tube, 32 watts, with one choke and one starter, with cover.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Round tube 32 watts 1.00 No. each


2 Starter 1.00 No. each
3 Choke 1.00 No. each
4 Holder 2.00 Nos. each
5 Base 1.00 No. each
6 Plastic cover 1.00 No. each
7 Flexeble wire 2.00 metre per mtr.
8 Hooks 1.00 No. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.50 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 209
DESCRIPTION OF ITEM:

Item No. 44 Providing and fixing M.S iron box for housing main switches, made
(1/16") thick M.S sheet, with locking arrangement, including paint

(i) 60 x 35 x 15 cm (24" x 14" x 6")

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL
1 M.S sheet 1.5 mm thick
Base side 1 x 24/12 x 14/12 (1 x 600 x 350 mm)
Long side 2 x 24/12 x 7 12 (2x600x190mm)
Short side 2 x 14/12 x 7 12 (2x350x190mm)
Top 1 x 24 x 12 x 14 (600 x 350 x 150 mm)
1.04 Sqm @ 12.20 Kg/Sqm 12.68 kg per kg
2 Angle Iron 25 x 25 x 3 mm/Sqm
2 x 24" = 48" (2 x 600 mm)
2 x 14" = 28" (2 x 350 mm)
4 x 7.12 = 30" (4 x 190 mm)
=
0.82 Sqm @ 6.08 Kg/Sqm 1.70 kg 1.70 kg each
3 Handle chromium plated 1.00 No. each
4 Painting 0.178 Gallon Gallon
5 Hinges 3.00 Nos. each
6 Locking arrangement L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Nos.)

1 Black Smith 1.00 No. per day


2 Cooly (helper) 1.00 No. per day
3 Painter 0.125 No. per day
4 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 210
DESCRIPTION OF ITEM:

Item No. 44 Providing and fixing M.S iron box for housing main switches, made
(1/16") thick M.S sheet, with locking arrangement, including paint

(ii) 95 x 40 x 20 cm (38" x 16" x 8")

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL
1 M.S sheet 38"x16"x 8" thick (1965x406x200mm)
Base side 1x38/12x16/12 (965x406mm) = 0.39 Sqm
Long side 2x38/12x8/12 (2x965x200mm) = 0.39 Sqm
Short side 2x16/12x8/12 (2x406x200mm) 0.17 Sqm
Top 1x38/12x16/12 (1x965x406mm) = 0.39 Sqm
1.34 Sqm
1.34 Sqm @ 12.45 Kg/Sqm 16.70 kg per kg
2 Angle Iron 1" x 1" x 1/8" (25 x 25 x 3mm)
2 x 965 mm = 1.93 R/m
2 x 406 mm = 0.82 R/m
4 x 200 mm = 0.80 R/m
3.55 R/m
3.55 R/m @ 0.632 Kg/R/m 2.25 kg per kg
3 Handle chromium plated 1.00 No. each
4 Paint 0.045 Gallon Gallon
5 Hinges 3.00 Nos. each
6 Locking arrangement L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 3 Nos.)

1 Black Smith 1.25 Nos. per day


2 Cooly (helper) 1.00 No. per day
3 Painter 0.125 No. per day
4 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES
Labour rate for Each Rs. Say
Composite rate for Each Rs. Say

Page 211
DESCRIPTION OF ITEM:

Item No. 44 Providing and fixing M.S iron box for housing main switches, made
(1/16") thick M.S sheet, with locking arrangement, including paint

(iii) 105 x 52.5 x 22.5 cm (42" x 21" x 9")

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL
1 M.S sheet 42" x 21" x 9" thick (1067 x 534 x 225mm)
Base side 1 x 42/12 x 21/12 (1076x534mm)
Long side 2 x 42/12 x 9/12 (2x1067x225mm)
Short side 2 x 21/12 x 9/12 (2x534x225mm)
Top 1 x 42 (1x1067x534mm)
12 12 1.872 Sqm
1872 Sqm @ 27.44 Per Sqm (51.36 lbs) 23.30 kg per kg
2 Angle Iron 1" x 1" x 1/8 (25x25x3mm)
2 x 42" = 84" (2x1076)
2 x 21" = 42" (2x534)
4 x 9" = 36" (4x225mm)
162" or 13.5 ft. (4.12 R/m)
412 ft. 1.394 lbs/PRM 5.74 lbs 2.60 kg per kg
3 P/F chromium plated 1.00 No. each
4 P/F Hinges 3.00 Nos. each
Paint 0.054 Gallon Gallon
Locking arrangement L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Black Smith 1.25 Nos. per day


2 Colly (helper) 1.00 No. per day
3 Painter 0.17 No. per day
4 Electrician 1.00 No. per day
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 212
DESCRIPTION OF ITEM:

Item No. 44 Providing and fixing M.S iron box for housing main switches, made
(1/16") thick M.S sheet, with locking arrangement, including paint

(iv) 135 x 70 x 27.5 cm (54" x 28" x 11")

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL
1 M.S sheet (54" x 28" 11") thick (1372x710x280mm)
Base side 1 x 54/12 x 28/12 (1372x710mm)
Long side 2 x 54/12 x 11/12 (2x1372x280mm)
Short side 2 x 28/12 x 11/12 (2x710x280mm)
Top 1 x 54/12 x 28/12 (1x1372x710mm)
3.12 Sqm
3.12 Sqm @ 27.44 lbs/Per Sqm (85.50 lbs) 38.78 kg per kg
2 Angle Iron 1" x 1" x 1/8" (25x25x3mm)
1x2 x 54"= 108" (2x1372mm)
2 x 28" = 56" (2x710mm)
4 x 11" = 44 (4x280mm)
5.28 R/M
5.28 R/M @ 1.39 lbs/Per R/M
7.36 lbs (7.36 lbs) 3.34 kg per kg
3 Handle chromium plated 1.00 No. each
4 Hinges with screws 4.00 Nos. each

5 Locking arrangement L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Black Smith 1.50 No. per day


2 Cooly (helper) 1.00 No. per day
3 Painter 0.25 No. per day
4 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES
Labour rate for Each Rs. Say
Composite rate for Each Rs. Say

Page 213
DESCRIPTION OF ITEM:

Item No. 45 Supply and erection of girder clamp hook, 16 mm (5/8") with M.S pl
with bolts and nuts for hanging ceiling fans.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Girder clamp hock 5/8" (16 mm) with


M.S plate 1" x " (25 x 6 mm) 1.00 No. each
2 Nut & bolts " (12 mm) 1" (40 mm) long 2.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 30 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.50 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 214
DESCRIPTION OF ITEM:

Item No. 46 Supply and erection of girder strut, of M.S tee section 40 x 40 x
1" x ") complete with clamp, bolts and nuts, etc., including fix
cement concrete 1 : 3 : 6.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

5.00 kg
1 T - Iron " x 1" x 1" x 5" (11.00 lbs)
Clamps 1.00 kg per kg
2 Nut & Bolts 1" (25 mm) 3.00 No. each
3 Manufacturing 1.00 No. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 30 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 215
DESCRIPTION OF ITEM:

Item No. 47 Supply and erection of roof suspension hook,16mm (5/8" dia) rod wi
(3 x 1" x 1/8") M.S Steel Channel, with clamp, bolts & nuts etc.,
with cement concrete 1:3:6.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Steel channel 75 x 40 x 3 mm
1.5 R/m @ 6.90 Kg/R/m 10.35 kg 10.35 kg per kg
2 Hook 5/8" (16 mm) with nut & bolts 1.00 No. each
3 Clamp 1.00 No. each
4 Cement 0.042 Cft. P. Bag
5 Sand 0.12 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 28 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 216
DESCRIPTION OF ITEM:

Item No. 48 Supply and erection of roof suspension hook, of M.S plate 75 x 40
(3 x 1" x ") with 16 mm (5/8") hook, complete with bolts and nut
with cement concrete 1 : 3 : 6.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Iron plate 3"x1"x" (0.862x40x12mm) 6.96 lbs


3.16 kg 3.16 kg per kg
2 Hook 5/8" with bolts & nut 1.00 No. each
3 Cement 0.063 Cft. P. Bag
4 Sand 0.18 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 21 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 217
DESCRIPTION OF ITEM:

Item No. 49 Supply and erection of 3/8" (10 mm) dia M.S bar fan hook placed at
casting of slab.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 M.S bar hook 3/8" (!0 mm) dia 1.00 No. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 39 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 218
DESCRIPTION OF ITEM:

Item No. 50 Erection of circular L.T pole in cement concrete 1 : 3 : 6, one me


ground level (excluding the cost of pole), including cement concre
(1 : 2 : 4) excavation of foundation and finishing surface.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cement concrete 1:3:6 (1.22x.300x1.0) 0.3714 Cum 0.3714 Cum Per Cum

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Nos.)

1 Cement concrete 1 : 3 : 6 0.3714 Cum Cum


2 Excavation of foundatin 0.3714 Cum Cum
3 Erection of pole in position
Plumber 0.50 No. per day
Helper 2.00 Nos. per day
4 Extra labour for shuttering L.S

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 219
DESCRIPTION OF ITEM:

Item No. 51 Supply and erection of bracket of M.S channel 75 x 40 x 6 mm (3"x1


section:

(i) 0.60 metre (2') long for 2 lines.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Steel channel (25 x 13 x 6 mm)


0.600 @ 5.22 Kg 3.18 Kg
Steel plate (75 x 20 x 20 mm) 0.79 Kg
3.97 Kg 3.97 Kg per kg
Bolts and nuts 5/8" dia (16 mm) 2.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 7 Nos.)

1 Black Smith 1.00 No. per day


2 Electrician 0.25 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 220
DESCRIPTION OF ITEM:

Item No. 51 Supply and erection of bracket of M.S channel 75 x 40 x 6 mm (3"x1


section:

(ii) 1.20 metre (4') long, for 4 lines.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Steel channel 75 x 13 x 6 mm
1.322 m @ 5.22 Kg/Rm 6.35 Kg
Iron plate 75 x 20 x 6 mm 0.80 Kg
7.15 Kg 7.15 Kg per kg
Bolts and nuts 5/8" dia (16 mm) 2.00 Nos. each
Manufacturing charges 1 job per job

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Nos.)

1 Black Smith 1.00 No. per day


2 Electrician 0.25 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 221
DESCRIPTION OF ITEM:

Item No. 52 Supply and erection of anchor rod Henley type for pole, including
clamps and 7/12" stay wire, straining screws, etc., erected in cem
1 : 3 : 6 and collar of cement concrete.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 10 Metre)

1 Stay wire 7/12" 10.00 metre per mtr.


2 Double clamp 1.00 No. each
3 Steining Screw 1.00 No. each
4 Eye bolts 1.00 No. each
5 Cement 0.064 Cft. P. Bag
6 Sand 0.16 Cft. Per % Cft.
7 Bajri 0.322 P. Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 235.40 1 0

LABOUR (For 70 Metre)

1 Electrician 1.00 No. per day


2 Cooly (helper) 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 222
DESCRIPTION OF ITEM:

Item No. 53 Supply and erection of stay for house service pipe, erected with s
screws and 7/14" stay wire, complete.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 5 Metre)

1 Stay wire 7/14" 5.00 metre per mtr.


2 Double clamp 9" dia (225 mm) 1.00 No. each
3 Stearining Screw 1.00 No. each
4 Hook size 1.00 No. each
5 Eye bolts 1.00 No. each
6 Cement 0.064 Cft. P. Bag
7 Sand 0.16 Cft. Per % Cft.
8 Bajri 0.322 P. Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 129.80 5 0

LABOUR (For 35 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 223
DESCRIPTION OF ITEM:

Item No. 54 Supply and erection of house service pipe Henley (G.I pipe water q
pole, type, 50 mm (2" dia) erected to install insulated overhead l
shackle insulator for holding insulated wire and straining devices
wire and other accessories, etc., complete.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 4 Metre)

1 G.I. pipe 2" dia (50 mm) 4.00 metre per mtr.
2 Shakle insulator 1.00 No. each
3 Clamp double 1.00 No. each
4 Clamp 2" dia (50 mm) 1.00 No. each
5 Rag bolts 5/8" 9" (16 x 225 mm) 1.00 No. each
6 G.I bend 2" (50 mm) cap 2.00 Nos. each
7 G.I Reducing socket 2 x " dia (50 x 20 mm) 1.00 No. each
8 M.S bolts for suport 1.00 No. each
9 Cement 0.064 Cft. P. Bag
10 Sand 0.16 Cft. Per % Cft.
11 Bajri 0.322 P. Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 1090.45 0.00

LABOUR (For 12 Metre)

1 Electrician 1.00 No. per day


2 Cooly skilled 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 224
DESCRIPTION OF ITEM:

Item No. 55 Supply and erection of house service pipe 50 mm (2" dia) G.I pipe
pole type, for bare copper wire overhead line, including shackle i
straining devices and other accessories, etc.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 4 Metre)

1 G.I. pipe (water quality) 4.00 metre per mtr.


2 Shakle insulator 1.00 No. each
3 Clamp double 1.00 No. each
4 Clamp 2" dia (50 mm) 1.00 No. each
5 Rag bolts 5/8" 9" (16 x 225 mm) 1.00 No. each
6 G.I bend 2" (50 mm) cap 2.00 Nos. each
7 G.I Reducing socket 2 x " dia (50 x 20 mm) 1.00 No. each
8 M.S bar suport 1.00 No. each
9 Cement 0.042 Cft. P. Bag
10 Sand 0.12 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per metre 1081.65 0.00

LABOUR (For 12 Metre)

1 Electrician 1.00 No. per day


2 Cooly (helper) 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 225
DESCRIPTION OF ITEM:

Item No. 56 Supply and erection of lightening arrestor horn type, complete.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Lightening arrestor 1.00 No. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 5 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 226
DESCRIPTION OF ITEM:

Item No. 57 Supply and erection of shackle insulator, medium size.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Shackle insulator (medium size) 1.00 No. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 7 Nos.)

1 Electrician 0.33 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 227
DESCRIPTION OF ITEM:

Item No. 58 Supply and erection of pin insulator, green medium size.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Pin insulator green (medium size) 1.00 No. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 7 Nos.)

1 Electrician 0.33 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 228
DESCRIPTION OF ITEM:

Item No. 59 Supply and erection of bare copper conductor wire, No.2 to No.10 S
including binding wire No.16 SWG.

Detail Unit Rate (Metric System) per Kg

Qty Rate Per Unit Amount (Rs.)

MATERIAL
13.61 kg
1 Copper wire No.2 to 10 (30.00 lbs) per kg
2 Binding wire No.16 1.00 lbs per kg
0.454 kg
Total
Contractor's Profit & O ## Percent
Total
Per Kg 1211.65 0.00

LABOUR (For 90 Lbs) 40.82 Kg

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Kg Rs. Say


Composite rate per Kg Rs. Say

Page 229
DESCRIPTION OF ITEM:

Item No. 60 Supply and erection of G.I wire of all sizes, including binding wi
for support of rubber wire or earthing wire, pole to pole, etc.

Detail Unit Rate (Metric System) per Kg

Qty Rate Per Unit Amount (Rs.)

MATERIAL
13.61 kg
1 G.I wire (all size) (30.00 lbs) per kg
2 Binding wire No.16 (1.00 lbs) per kg
0.454 kg

Total
Contractor's Profit & O ## Percent
Total
Material cost per Kg 418.20 1 0.00

LABOUR (For 90 Lbs) 40.83 Kg

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Kg Rs. Say


Composite rate per Kg Rs. Say

Page 230
DESCRIPTION OF ITEM:

Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on
No.8 SWG bearer wire and in house service pipe, including connecti
through joint box:

(i) 3/0.74 mm (3/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 47 Metre)

1 PVC/weather proof cable 3/0.029" (3/0.74 mm)


Single core 47.00 metre per mtr.
2 Leather or wooden cleats 25.00 Nos. each
1.81 kg
3 G.I wire No.8 SWG (4.00 lbs) kg
4 Eye - bolts 2.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total
Material cost per metre 573.62 4 0.00

LABOUR (For 90 Metre)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 231
DESCRIPTION OF ITEM:

Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on
No.8 SWG bearer wire and in house service pipe, including connecti
through joint box:

(ii) 7/0.74 mm (7/0.029")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 47 Metre)

1 PVC/weather proof cable /0.029" (7/0.74 mm)


Single core 47.00 metre per mtr.
1.81 kg
2 G.I wire No.8 SWG (4.00 lbs) kg
3 Eye - bolts 2.00 Nos. each
4 Cut out 2.00 Nos. each
5 T. Wooden board 7" x 4" (175 x 100 mm) 1.00 No. each
6 Wooden & leather cleats 25.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total
Material cost per metre 880.13 47 0.00

LABOUR (For 90 Metre)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 232
DESCRIPTION OF ITEM:

Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on
No.8 SWG bearer wire and in house service pipe, including connecti
through joint box:

(iii) 7/0.91 mm (7/0.036")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 47 Metre)

1 PVC/weather proof cable /0.036" (7/0.91 mm)


Single core 47.00 metre per mtr.
1.81 kg
2 G.I wire No.8 SWG (4.00 lbs) kg
3 Eye - bolts 2.00 Nos. each
4 Cut out 2.00 Nos. each
5 T. Wooden board 7" x 4" (175 x 100 mm) 1.00 No. each
6 Wooden & leather cleats 25.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total
Material cost per metre 1230.76 0.00

LABOUR (For 90 Metre)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 233
DESCRIPTION OF ITEM:

Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on
No.8 SWG bearer wire and in house service pipe, including connecti
through joint box:

(iv) 7/1.12 mm (7/0.044")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 47 Metre)

1 PVC/weather proof cable /0.044" (7/1.12 mm)


Single core 47.00 metre per mtr.
1.81 kg
2 G.I wire No.8 SWG (4.00 lbs) kg
3 Eye - bolts 2.00 Nos. each
4 Cut out 2.00 Nos. each
5 T. Wooden board 7" x 4" (175 x 100 mm) 1.00 No. each
6 Wooden & leather cleats 25.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total
Material cost per metre 1437.56 0.00

LABOUR (For 80 Metre)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 234
DESCRIPTION OF ITEM:

Item No. 62 Supply and erection of all aluminium stranded hard drawn bare cond
size 7/3.099 mm (7/0.122").

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Aluminium stranded hard drawn bare


conductor 7/3.099 mm (7/0.122") 1.00 No. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 26 Metre)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 235
DESCRIPTION OF ITEM:

Item No. 63 Supply and erection of street light pole bracket 30 mm (1") G.I p
long, complete with 2 No. pole clamp.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.I. Pipe 1" dia (32 mm) 7 ft. (2.13 metre) 2.13 metre per mtr.
2 Cost of clamp 2.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Metre)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 236
DESCRIPTION OF ITEM:

Item No. 64 Supply and erection of pole mounted street light, holders, shade a
etc., for fitting 125/250 watts mercury vapour lamp (excluding cos

(i) G.E.C design

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Pole street with holder shade and glass


for mercury vapour lamp 125/250 complete 1.00 No. each
2 Bracket 1.00 No. each
3 Clamps with bolts & nuts etc. 2.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 237
DESCRIPTION OF ITEM:

Item No. 64 Supply and erection of pole mounted street light, holders, shade a
etc., for fitting 125/250 watts mercury vapour lamp (excluding cos

(ii) Phillips design

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cost of fitting complete with holder


shade and glass 1.00 No. each
2 Cost of bracket 1" (32 mm) G.I pipe
7 ft. long half round 1.00 No. each
3 Cost of pole clamp with bolt & nuts 2.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 238
DESCRIPTION OF ITEM:

Item No. 65 Supply and fitting of mercury vapour lamp, complete with choke set

(i) 125 watt lamp

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Vapour mercury lamp 125 watt


with choke set 649 + 330 = 979.00 1.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 6 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.50 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 239
DESCRIPTION OF ITEM:

Item No. 65 Supply and fitting of mercury vapour lamp, complete with choke set

(ii) 250 watt lamp

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Vapour mercury lamp 250 watt


with choke set 2558 + 100 = 3658 1.00 Nos. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 5 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.50 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 240
DESCRIPTION OF ITEM:

Item No. 66 Manufacture and erection of angle iron lattice steel structure pol
long (9348 mm ground level) 355 mm square at base & 204 mm square
electric distribution line, using 1"x1"x3/16" angle iron legs an
angle iron bracings 420 mm long fixed between legs on all the four
diagonal position, and 1" x 1" x 3/16" angle iron on top and 4 b
flat iron 2" x ", 305 mm centre to centre, as per standard drawin
silverpainting of pole 3 coats, excavation and refilling of founda
concrete 1 : 2 : 4, 1807 x 500 x 500 mm for foundation, etc., comp
respects.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Angle iron 1"x1"x3/16" (32x32x4 mm)


Legs 4x10923 mm = 43692mm = 143.35 ft.
143.35 ft. @ 1.47 lbs/ft. = 210.72 lbs
2 Angle Iron "x"x1/8 (20x20x3 mm)
Bracing 18x4x420mm = 30240mm or 99.21 ft.
99.21 ft. @ 0.58 lbs/ft. = 57.54 lbs
3 Angle Iron 1"x1"1/8 (25x25x3 mm)
Bracing 3x4x385mm = 4620 mm or 15.16 ft.
15.16 ft. @ 0.80 lbs/ft. 12.13 lbs
280.39 lbs 127.22 kg per kg
4 M.S. flat 2x" (50 x 6 mm)
4x4x204 mm = 3264 mm = 10.71 ft.
10.71 ft. @ 1.70 lbs/ft. = 18.21 lbs 8.26 kg per kg
5 Angle Iron 1"x1"x3/16" (44x44x4 mm)
4x4x204 mm = 3264mm = 10.71 ft.
10.71 ft. @ 2.11 lbs/ft. = 22.60 lbs 10.25 kg per kg
6 Silver paint 0.25 gallon @ 550 per gallon 0.25 gallon per gln.
7 Cement concrete 1 : 2 :4
foundation 500x500x1728 mm = 0.43 m
15.06 Cft 15.06 Cft. per Cft
8 Pre cast cement concrete 1 : 2 : 4
2x100x100x100 = 2000000 mm or 0.07 Cft
0.07 Cft 0.07 Cft. per Cft

Total
Contractor's Profit & O ## Percent
Total

Page 241
Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Black Smith 1.50 Nos. per day


Cooly (helper) 3.00 Nos. per day
2 Welding charges
No. of weld 2(72+12+16) = 200 Nos. 200.00 Nos. each
3 Drilling hole 20.00 Nos. each
Painter 0.25 No. per day
4 Excavation 500x500x1576 mm = 394000000
or 13.91 Cft (Item 4b Chap. 3) 13.91 Cum per Cft
5 Concrete 1:2:4
Foundation 500x500x1728 mm = 432000000
15.06 Cft (Item 5f Chap. 6) 15.06 Cum per Cft
6 Pre cast cement concrete 1:2:4
2x100x100x100 = 2000000 mm or 0.07 Cft 0.07 Cum per Cft
(Item 10 Chap. 6)
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 242
DESCRIPTION OF ITEM:

Item No. 67 Manufacture and erection of galvanized angle iron lattice steel st
pole 11.30 metre long (9.85 metre above ground level), 875mm squar
base, 350mm square at top, for electric distribution line, using 5
high tensile steel angle iron legs, and 310x310x3mm M.S angle iro
fixed between legs on all the four sides in diagonal position, as
drawing including silver painting of pole, excavation and refilli
foundation, one ft. thick cement concrete 1:3:6 foundation of oute
2.44x1.067x1.067 metre complete in all respects.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Angle iron 50x50x4mm (lattice steel)


Legs 4x30 ft. = 120 ft.
Studs 4x7 = 28 = 148 ft. 1.96 lbs/Rft290.08 lbs
131.62 kg 131.62 kg per kg
2 Angle Iron 1 3/8 x 1 3/8 3 x 1/8
Braces 4x16x2.75 = 176 ft.
@ 1.55 lbs/ft. = 272.8 lbs = 123.77 kg 123.77 kg per kg
3 M.S plate 5/32" thick
13"x13"x5/32" = 0.017 Cft
@ 493 lbs/Cft = 8.38 lbs 3.80 kg 3.80 kg per kg

4 Silver paint 0.25 gallon 0.25 gallon per gln.


5 Cement concrete 1:3:6
(3.5 x 3.5 x 0.5) = 6.13 Cft
(1 x 3.5 x 6.5) = 22.75 Cft
(1 x 1.5 x 6.5) = 9.75 Cft
38.63 Cft 38.63 Cum per Cum

Total
Contractor's Profit & O ## Percent
Total

Page 243
Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Black Smith 1.50 Nos. per day


2 Cooly (helper) 3.00 Nos. per day
3 Welding charges (No. of weld)
Bacing 64 x 2 = 128 Nos.
T/plate 1 x 4 = 4 Nos.
132 Nos.
132 Nos. weld 132.00 Nos. per weld
4 Drilling hole 8.00 Nos. per hole
5 Painter 0.25 No. per day
6 Excavation of foundation
(3.5 x 3.5 x 7.5) (Item 4b Chap. 3) 91.88 Cft 91.88 Cft per Cft

7 Cement Concrete 1:3:6 (Item 3a Chap. 6) 38.630 Cft per Cft

8 Earth filling(1.5x.5 x 6.5) (Item 15(14.63 Cft 14.630 Cft per Cft

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 244
DESCRIPTION OF ITEM:

Item No. 68 Earthing of iron clad/aluminium switches, etc., with G.I wire No.8
pipe 15 mm (" dia) recessed or on surface of wall and floor, comp
1.5 metre long G.I pipe, 50 mm (2" dia) with reducing socket 4 to
below ground level, and 2 metre away from building plinth.

Detail Unit Rate (Metric System) per Job

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Boring 10.00 metre per mtr.


2 G.I pipe " (12 mm) (medium quality) 8.00 metre per mtr.
0.907 kg
3 G.I wire No.8 SWG @ (2 lbs) (2.00 lbs) kg
4 G.I pipe 2" (50 mm) (medium quality) 1.50 metre per mtr.
5 G.I reducing socket size 2 x " (50 x 13 mm) 1.00 No. each
6 G.I bend " (13 mm) 4.00 No. each
7 Cement 0.063 Cft. P. Bag
8 Sand 0.18 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 245
DESCRIPTION OF ITEM:

Item No. 69 Earthing of Metallic cases, etc., with G.I wire No.8 SWG, in 15 mm
pipe, best quality:

(i) On surface, including clamps, etc.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I pipe " dia (12 mm) 7.00 metre per mtr.
0.454 kg
2 G.I wire No.8 SWG (1.00 lbs) per kg
3 G.I clamp " dia (12 mm) 6.00 Nos. each
4 G.I bolts 2" x " dia (50 x 6 mm) 1.00 No. each
5 Gutties 10.00 Nos. per doz.
6 Screw " (20 mm) 10.00 Nos. each
7 G.I bend " dia (12 mm) 1.00 No. each

Total
Contractor's Profit & O ## Percent
Total
Material per Metre 145.48 0.00

LABOUR (For 40 Metre)

1 Electrician 1.00 No. 0.00 per day


2 Cooly (helper) 1.00 No. 0.00 per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 246
DESCRIPTION OF ITEM:

Item No. 69 Earthing of Metallic cases, etc., with G.I wire No.8 SWG, in 15 mm
pipe, best quality:

(ii) Recessed in wall, including hooks, jharries and making good surfac

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I pipe " dia (12 mm) 7.00 metre per mtr.
0.454 kg
2 G.I wire No.8 SWG (1.00 lbs) kg
3 G.I bolts 2" x " dia (50 x 6 mm) 1.00 No. each
4 Hooks 6.00 Nos. each
5 G.I bend " dia (12 mm) 1.00 Nos. each
6 Cement 0.063 Cft. P. Bag
7 Sand 0.18 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per Metre 470.64 0.00

LABOUR (For 25 Metre)

1 Electrician 1.00 No. per day


2 Cooly (helper) 2.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 247
DESCRIPTION OF ITEM:

Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.

(a) G.I wire:

(i) 8 SWG

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)


0.68 kg
1 G.I wire No.8 SWG (1.50 lbs) per kg
2 Copper themble 1.00 No. each
3 G.I Nuts & Bolts 2" long " (50 mm x 13 mm) 1.00 No. each
4 G.I clamp 1.00 No. each
5 Cement 0.042 Cft. P. Bag
6 Sand 0.12 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per Metre 51.00 0.00

LABOUR (For 50 Metre)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 248
DESCRIPTION OF ITEM:

Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.

(a) G.I wire:

(ii) 16 SWG

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 G.I wire No.16 SWG 0.112 kg per kg


2 Copper themble 1.00 No. each
3 G.I Nuts & Bolts 1" x " long (40 x 6 mm) 1.00 No. each
4 Cement 0.011 Cft. P. Bag
5 Sand 0.03 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per Metre

LABOUR (For 50 Metre)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 249
DESCRIPTION OF ITEM:

Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.

(b) Copper wire:

(i) 16 SWG

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 Copper wire No.16 SWG 0.133 kg per kg


2 Copper themble 1.00 No. each
3 G.I Nuts & Bolts 1" x " long (40 x 6 mm) 1.00 No. each
4 Cement 0.011 Cft. P. Bag
5 Sand 0.03 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per Metre 28.56 0.00

LABOUR (For 50 Metre)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 250
DESCRIPTION OF ITEM:

Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.

(b) Copper wire:

(ii) 20 SWG

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 Copper wire No.20 SWG 0.035 kg per kg


2 Copper themble 1.00 Nos. each
3 G.I Nuts & Bolts 1" x " long 1.00 Nos. each
4 Cement 0.011 Cft. P. Bag
5 Sand 0.03 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per Metre 15.04 0.00

LABOUR (For 50 Metre)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 251
DESCRIPTION OF ITEM:

Item No. 71 Erection only, of lightening conductor of copper staple, and coppe
cement, sand mortar.

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL (For 7 Metre)

1 Gutties 8.00 Nos. per doz.


2 Copper nail 8.00 Nos. each
3 Copper stapple 4.00 Nos. each
4 Cement 0.021 Cft. P. Bag
5 Sand 0.06 Cft. Per % Cft.

Total
Contractor's Profit & O ## Percent
Total
Material per Metre 44.00 0.00

LABOUR (For 25 Metre)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Ft. Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Ft. Rs. Say

Page 252
DESCRIPTION OF ITEM:

Item No. 72 Supply and erection of 600 x 600x3mm (2'x2x1/8") copper plate, inc
riveting to copper tape and placing in mixture of salt & charcoal,

Detail Unit Rate (Metric System) per Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL
9.98 kg
1 Copper plate 600x600x3mm=0.00133 Cum (22.00 lbs) per kg
@ 550 lbs/cft 22 lbs 36.30 kg
2 Char coal (80.00 lbs) per kg
18.15 kg
3 Salt (40.00 lbs) per kg

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 3 Metre)

1 Electrician 1.00 No. per day


2 Cooly (helper) 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 253
DESCRIPTION OF ITEM:

Item No. 73 Supply and erection of copper tape, including copper staple copper
cement, sand, etc.

(i) Tape 40 x 3 mm (1" x 1/8")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Copper tap 1"x1/8" = 1 metre 1.00 kg


1 metre = 0.004 Cft @ 550 lbs/Cft 2.2 lbs (2.20 lbs) per kg
2 Gutties 1.00 No. per doz.
3 Copper nail 1.00 No. each
4 Copper staple 1.00 No. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 25 Metre)

1 Electrician 1.00 No. per day


2 Cooly (helper) 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 254
DESCRIPTION OF ITEM:

Item No. 73 Supply and erection of copper tape, including copper staple copper
cement, sand, etc.

(ii) Tape 50 x 3 mm (2" x 1/8")

Detail Unit Rate (Metric System) per Metre

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Copper tap 2"x1/8" = 1 metre 1.22 kg


1 metre = 0.005 Cft @ 550 lbs/Cft 2.7 lbs (2.27 lbs) per kg
2 Copper nail 1.00 No. each
3 Copper staple 1.00 No. each
4 Gutties 1.00 No. per doz.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 25 Metre)

1 Electrician 1.00 No. per day


2 Cooly (helper) 2.00 Nos. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate per Metre Rs. Say


Labour rate per Rft Rs. Say

Composite rate per Metre Rs. Say


Composite rate per Rft Rs. Say

Page 255
DESCRIPTION OF ITEM:

Item No. 74 Supply and erection of 25 mm (1"/dia) and one metre long lightning
copper rod with 5 spikes on ball and base, etc., complete.

Detail Unit Rate (Metric System) per Job

Qty Rate Per Unit Amount (Rs.)

MATERIAL

Copper rod 1" dia (25 mm) = 1 metre


with 5 spikes on ball and base
1 Weight of rod 9.9 lbs
2 weight of ball 3.00 lbs
3 weight of base and spikes 1.00 lbs
13.90 lbs (13.90 lbs) per kg
6.30 kg

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Job Rs. Say


Composite rate for Each Job Rs. Say

Page 256
DESCRIPTION OF ITEM:

Item No. 75 Supply and erection of electric energy metre, including metre test

(a) Single phase:

(i) 1 x 10 Amp 250 volts

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Energy metre 10 Amp. Single phase 250 Volts 1.00 No. each
2 Testing Fee L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 257
DESCRIPTION OF ITEM:

Item No. 75 Supply and erection of electric energy metre, including metre test

(a) Single phase:

(ii) 1 x 30 Amp 250 volts

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Energy metre 30 Amp. Single phase 250 Volts 1.00 No. each
2 Testing Fee L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 258
DESCRIPTION OF ITEM:

Item No. 75 Supply and erection of electric energy metre, including metre test

(b) Three phase, 4 wires

(i) 3 x 15 Amp. 400 volts

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Energy metre 3 x 15 Amp. Three phase 400 Volts 1.00 No. each
2 Testing Fee L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 259
DESCRIPTION OF ITEM:

Item No. 75 Supply and erection of electric energy metre, including metre test

(b) Three phase, 4 wires

(ii) 3 x 50 Amp. 400 volts

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Energy metre 3 x 50 Amp. Three phase 400 Volts 1.00 No. each
2 Testing Fee L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.50 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 260
DESCRIPTION OF ITEM:

Item No. 75 Supply and erection of electric energy metre, including metre test

(b) Three phase, 4 wires

(iii) 3 x 80 Amp. 400 volts

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Energy metre 3 x 80 Amp. Three phase 400 Volts 1.00 No. each
2 Testing Fee L.S

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 2 Nos.)

1 Electrician 1.00 No. per day


2 Cooly (helper) 0.50 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 261
DESCRIPTION OF ITEM:

Item No. 76 Rewinding of A.C ceiling fan, capacitor type, including cost of wi
paper cotton tape, soldering, etc.

(i) 1200 mm (48") sweep, 275 - 300 RPM

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Leatheride paper L.S


1.02 kg
2 Copper wire No.32 SWG - 26 SWG (2.25 lbs) per kg
3 Soldring and vanishing hoop wire No.3 Job
4 Deduction cost of 2 lbs (1.02 kg) copper wire ol 2.25 lbs per kg
1.02 kg

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Nos.)

1 Electrician 1.50 No. per day


2 Cooly (helper) 0.50 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 262
DESCRIPTION OF ITEM:

Item No. 76 Rewinding of A.C ceiling fan, capacitor type, including cost of
wire, leatheride paper cotton tape, soldering, etc.

(ii) 1400 mm (56") sweep, 250 - 275 RPM

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Leatheride paper and cotten tape Job


1.13 kg
2 Enemal wire No.26 SWG to 32 SWG (2.50 lbs) per kg
3 Soldering and varnishing 1.00 No. each
4 Loop wire 4 loop 3/0.029 (3/0.74 mm) 4.00 ft. per Rft
5 Deduction cost of old material 2.50 lbs per kg
1.13 kg

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 4 Nos.)

1 Electrician 1.50 No. per day


2 Cooly (helper) 0.75 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 263
DESCRIPTION OF ITEM:

Item No. 77 Rewinding of A.C exhaust fan, including cost of wire,


leatheride paper, cotton tape, soldering, etc.

(i) 375 mm (15") sweep, and 1300 - 1500 RPM

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Leatheride paper and cotten tape Job


0.68 kg
2 Enamel wire No.26 SWG to 32 SWG (1.50 lbs) per kg
3 Varnishing and soldering Job
4 Deduction cost of old material 1.50 lbs per kg
0.68 kg

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 264
DESCRIPTION OF ITEM:

Item No. 77 Rewinding of A.C exhaust fan, including cost of wire,


leatheride paper, cotton tape, soldering, etc.

(ii) 450 mm (18") sweep, and 1300 - 1500 RPM

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Leatheride paper and cotten tape Job


0.79 kg
2 Enamel wire No.26 SWG to 32 SWG (1.75 lbs) per kg
3 Varnishing and soldering Job
4 Loop wire 3/0.029" (3/0.74 mm) 4.00 ft. per ft.
5 Deduction cost of old material 1.75 lbs per kg
0.79 kg

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 3 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 265
DESCRIPTION OF ITEM:

Item No. 78 Rewinding of pedestal fan 600 mm (24") sweep, and 900 - 950
RPM, including wire, leatheride paper, cotton, tape, etc.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Leatheride paper and cotten tape Job


0.91 kg
2 Enamel wire No.26 SWG to 32 SWG (2.00 lbs) per kg
3 Varnishing and soldering Job
4 Deduction cost of old material (2.00 lbs) per lbs
0.91 kg

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 5 Nos.)

1 Electrician 2.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 266
DESCRIPTION OF ITEM:

Item No. 79 Supply and fitting of regulator nob with shaft and plate of
electric fan regulator.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Knob with shaff and plate 1.00 No. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 16 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 267
DESCRIPTION OF ITEM:

Item No. 80 Supply and fitting of capacitor 2.2 uf, for ceiling fans.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Capacitor 2.2 uf 1.00 No. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 20 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 268
DESCRIPTION OF ITEM:

Item No. 81 Supply and fitting of ball bearing of size 6201, 6202 or 6203, for

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Ball bearing size (6201, 6202 or 6203) 1.00 No. each

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 16 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 269
DESCRIPTION OF ITEM:

Item No. 82 Rewinding regulator of ceiling fan (1200/1400 mm) sweep, to contro
3/4 speeds.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL
0.18 kg
1 Enamel copper wire No.26 SWG to 32 SWG (0.403 lbs) kg
2 Leathoride paper, cotten tape and vinishing L.S
3 Deduct cost of old material (0.403 lbs) per kg
0.18 kg
Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 8 Nos.)

1 Electrician 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 270
DESCRIPTION OF ITEM:

Item No. 83 Erection of ceiling fan alongwith regulator (all sizes), including
from local Railway Station/Store to site of work, electric wire/ca
suspension rod and board connection, and cutting threading on the
where necessary.

Detail Unit Rate (Metric System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 PVC wire 3/0.029" 2.00 metre per mtr.

Total
Contractor's Profit & O ## Percent
Total

LABOUR (For 10 Nos.)

1 Carriage from stone to site L.S


2 Cutting & threading G.I pipe (22mm) dia 8.00 Nos. each
3 Electrician 1.00 No. per day
4 Cooly (helper) 1.00 No. per day

Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 271
LIST EQUIPMENT
S. No. NAME OF MACHINERY CAPACITY COST
EQ-01 Bull Dozer D-6 (16 Ton) Per Hour
EQ-02 Motor Grader Per Hour
EQ-03 Wheel Loader (15 Ton) Per Hour
EQ-04 Rental Charges of equipment for desilting Per Day
EQ-05 3 Wheel Roller (10-15 Ton) Per Hour
EQ-06 Pneumatic Tyre Roller (8-13 Ton) Per Hour
EQ-07 Tandum/Road Roller (8-12 Ton) Per Hour
EQ-08 Vibratory Roller (8 Ton) Per Hour
EQ-09 Asphalt Plant (45-46 Ton) Per Hour
EQ-10 Asphalt Finishers (Paver) Per Hour
EQ-11 Electric Power Plant (Generator) (100 KW) Per Hour
EQ-12 Truck 2-Axle (Local) (10 Ton) Per Hour
EQ-13 Truck 3-Axle (Local) (15 Ton) Per Hour
EQ-14 Truck 3-Axle (Imported) (15-18 Ton) Per Hour
EQ-15 Dumper Truck (Imported) (15 Ton) Per Hour
EQ-16 Water Lorry (Local) Per Hour
EQ-17 Donkey Each
EQ-18 Wheel Tractor with Plough Per Hour
EQ-19 Wheel Tractor with Trolley Per Hour
EQ-20 Wheel Tractor with Sheep foot Roller Per Hour
EQ-21 Wheel Tractor with Water Tank Per Hour
EQ-22 Wheel Tractor with Blade Per Hour
EQ-23 Concrete Mixer 2 Bag
EQ-24 Concrete Mixer 1 Bag
EQ-25 Concrete Vibrator Per Hour
EQ-26 Plate Compactor Per Hour
EQ-27 Tar Boiler Per Hour
EQ-28 Cost of lifting machinery including carriage Each
EQ-29 Cost of trollies Each
EQ-30 Road Roller Per Day
EQ-31 Hire charges for a cart having a capacity of about 20 Cft/one ton Per Day
EQ-32 Hire charges of Rig Per Hour
EQ-33 Hire charges of truck (5 ton - 10 tons) excluding POL but including crew Per Day
EQ-34 Hire Charges of testing apparatus Per Day
EQ-35 Reg Pump Per Hour
EQ-36 Cost of pump set 6"x5" with 15 HP Diesel Engine Each
EQ-37 Generator set light Per Hour
EQ-38 Pumping for out water 0-1' to 0-8' Per Hour
EQ-39 Pumping for out water 0-9' to 0-12' Per Hour
EQ-40 Pumping Machinery Boring 0-1' to 0-8' Per Day
EQ-41 Pumping Machinery Boring 0-9' to 0-12' Per Day
EQ-42 Pump charges for pumping out water from 0-1' to 0-8' depth Per Hour
EQ-43 Pump charages for pumping out water from 0-9' to 0-12' depth Per Hour
EQ-44 Hire Charges of Assembling Machine for A.C. Pipe 3" to 6" --
EQ-45 Hire Charges of Assembling Machine for A.C. Pipe 8" to 10" --
EQ-46 Hire Charges of Assembling Machine for A.C. Pipe 12" to 18" --
EQ-47 Hire Charges of Assembling Machine for A.C. Pipe 20" to 24" --
EQ-48 Disposal of Pumped Out Water upto 100' distance for 1' depth --
EQ-49 Disposal of Pumped Out Water upto 100' distance upto 3' depth --
EQ-50 Disposal of Pumped Out Water upto 100' distance upto 5' depth --
EQ-51 Disposal of Pumped Out Water upto 100' distance upto 6' depth --
EQ-52 Disposal of Pumped Out Water upto 100' distance upto 7' to 12' depth --
EQ-53 Cost of Bulldozer-D6 140 HP
EQ-54 Cost of Motor Grader 135 HP

Page 1
LIST EQUIPMENT
S. No. NAME OF MACHINERY CAPACITY COST
EQ-55 Cost Wheel Loader 100 HP
EQ-56 Cost of 3 wheel-Static Roller (local) 10-12 Ton
EQ-57 Cost of Pneumatic Roller 8-13 Ton
EQ-58 Cost of Tandem Roller 8-12 Ton
EQ-59 Cost of Vibratory Roller 8-Ton
EQ-60 Cost of Asphalt Plant 45-46 Ton.
EQ-61 Cost of Asphalt Paver 145 HP
EQ-62 Cost of Electric power Generator 100 KW
EQ-63 Cost of Truck-2axle (local) 10 Ton
EQ-64 Cost of Truck-3axle (local) 15-18 Ton
EQ-65 Cost of Truck-3axle (imported) 18 Ton
EQ-66 Cost of Dump truck 18.0 Ton
EQ-67 Cost of Water lorry (local) --
EQ-68 Cost of Wheel Tractor with Plough --
EQ-69 Cost of Wheel Tractor with Trolley --
EQ-70 Cost of Wheel Tractor with Sheep foot roller --
EQ-71 Cost of Wheel Tractor with Water Tank --
EQ-72 Cost of Wheel Tractor with Blade --
EQ-73 Cost of Concrete Mixer 2 bags
EQ-74 Cost of Concrete Mixer 1 bag
EQ-75 Cost of Concrete vibrator --
EQ-76 Cost of Plate Compactor --
EQ-77 Cost of Tar Boiler 1000Ltr.

Page 2
CHAPTER NO. 10

FLOORING
i) Rates for all finished works include the removal of surplus debris, unused
material and by products.

ii) For handling of all types of material for short lead including carriage upto
3 chains (90m) nothing is to be paid as extra. Where handling and carriage
involves an extra lead beyond 3 chains, (90m) carriage for whole of the distance
should be paid

DESCRIPTION OF ITEM
1 Laying Muram flooring consisting of 1" (25m) layer of fine powdery or flakey variety of M
laid over 6" (150mm) good hard layer of Muram spreaded over 9" (225mm) thick sub base
comprising of hand packed rubble or broken bricks properly watered and rammed provided
over well rammed earth

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 9" thick rubble or broken hard bricks 80.00 Cft 0.00Per 100 Cft -
2 6" Hard Muram 55.00 Cft 0.00Per 100 Cft -
3 1" Fine Powdery Muram 9.00 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 0.50 No. 0.00 per day -


Coolies 3.00 Nos. 0.00 per day -
Bahishti 0.5 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 1
DESCRIPTION OF ITEM

2 Earth flooring consisting of 6" thick consolidated layer of moistured


earth including ramming

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Earth (Loose measured) 50.00 Cft 0.00Per 100 Cft -


Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 0.125 No. 0.00 Per day -


Coolly 1.00 No. 0.00 Per day -
Bahishti 0.25 No. 0.00 Pay day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 2
DESCRIPTION OF ITEM

3 Providing, laying, watering and ramming brick ballast 1" - 2" gauge mixed with
25% sand, for floor foundation, complete in all respects.

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Brick Ballast 100.00 Cft 0.00Per 100 Cft -


2 Sand 25.00 Cft 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Coolies 3.10 No. 0.00 per day -


Bahishti 0.10 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say 0.00


Labour Rate Per Cum Rs. - Say 0.00
Composite Rate per 100 Cft. Rs. - Say 0.00
Composite Rate per Cum. Rs. - Say 0.00

Page 3
4 Mud Flooring

DESCRIPTION OF ITEM

Mud flooring consisting of 6" thick consolidated layer of moistured earth and
finished off with 1" mud plaster and gobri leeping.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Earth for filling 50.00 Cft 0.00Per 100 Cft -


2 Earth for Mud Plaster 10.00 Cft 0.00Per 100 Cft -
3 Bhoosa 34 lbs (15.44 Kg. 0.00 Kg. -
4 Fine Clay for Gobri Leeping 0.75 Cft. 0.00Per 100 Cft -
5 Cow Dung 0.75 Cft. (5.44 Kg 0.00Per 100 Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 0.25 No. 0.00 Per day -


Coolies 2.00 No. 0.00 Per day -
Bahishti 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 4
5 Brick Flooring

DESCRIPTION OF ITEM

Dry brick paving laid flat, sand grouted including preparation of bed by watering, rammin
bringing the same to proper camber by " mud plaster

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Brick 9" 350 Nos. 0.00Per 1000 No -


2 Sand 5 Cft. 0.00Per 100 Cft -
3 " Mud Plaster (Good earth) 6 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 125 SFT.

Mason 0.50 No. 0.00 Per day -


Coolies 1.00 No. 0.00 Per day -
Bahishti 0.05 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 5
DESCRIPTION OF ITEM

6 Dry brick on edge paving sand grouted including preparation of bed by watering,
ramming and bringing the same to proper camber by thick mud plaster

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Brick 9" (including wastage) 525 Nos. 0.00er 1000 Nos -


2 " thick mud plaster (good earth) 6 Cft. 0.00Per 100 Cft -
2 Sand 6 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 0.67 No. 0.00 Per day -


Coolies 1.50 No. 0.00 Per day -
Bahishti 0.08 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 6
DESCRIPTION OF ITEM

7 Grouting 4" dry brick work with cement mortar ratio 1:5

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 0.70 Bag 0.00 Per Bag -


2 Sand 4.50 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 125 SFT

Mason 0.50 No. 0.00 Per day -


Coolies (Unskilled) 0.50 No. 0.00 Per day -
Bahishti 0.50 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 7
DESCRIPTION OF ITEM

3
8 Flat brick flooring laid in 1:6 cement mortar over a bed of /4" thick cement mortar 1:6

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Bricks 9" size 350 Nos. 0.00Per 1000 No -


2 Cement (for laying) 0.50 Bag 0.00 Per Bag -
3 Cement (for bedding mortar) 0.80 Bag 0.00 Per Bag -
4 Sand for laying 4.00 Cft. 0.00Per 100 Cft -
5 Sand for bedding mortar 6.00 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 125 SFT.

Mason 0.75 No. 0.00 Per day -


Coolies 1.50 No. 0.00 Per day -
Bahishti 0.50 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 8
DESCRIPTION OF ITEM

9 Brick on edge flooring laid in 1:6 cement mortar over a bed of 3/4" thick cement mortar (

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Bricks 9" size 525 Nos. 0.00Per 1000 No -


2 Cement for laying 0.85 Bag 0.00 Per Bag -
3 Cement for bedding mortar 0.88 Bag 0.00 Per Bag -
4 Sand for laying 7.00 Cft. 0.00Per 100 Cft -
5 Sand for bedding mortar 6.00 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 125 Sft.

Mason 1.00 No. 0.00 Per day -


Coolies 2.00 No. 0.00 Per day -
Bahishti 0.50 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 9
DESCRIPTION OF ITEM

10 Brick tiles (12"x6"x2") laid in (1:6) cement mortar, over a bed of 3/4" thick cement mort

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Tiles 12"x6"x2" 210 Nos. 0.00Per 1000 No -


2 Cement 1.10 Bag 0.00 Bag -
4 Sand 8.00 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 0.75 No. 0.00 Per day -


Coolies 1.50 No. 0.00 Per day -
Bahishti 0.50 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 10
DESCRIPTION OF ITEM

11 Brick tiles (9" x 4" x 1") laid flat in 1:3 cement mortar over a bed of 3/4" thick ceme

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Tiles 9"x4"x1" 350 Nos. 0.00Per 1000 No -


2 Cement 1.40 Bag 0.00 Bag -
4 Sand 12.00 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 1.00 No. 0.00 Per day -


Coolies (Unskilled) 1.50 No. 0.00 Per day -
Bahishti 0.50 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 11
DESCRIPTION OF ITEM

12 Cement tiles (8"x8"x") laid fiat in 1:2 cement mortar over 3/4" thick bed of cement mort

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement tiles (8"x8"x3/4") 240 Nos. 0.00 Per No. -


2 Cement 1.87 Bags 0.00 Per Bag -
4 Sand 4.70 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 200 SFT.

Mason 1.25 No. 0.00 Per day -


Coolies (Unskilled) 2.00 No. 0.00 Per day -
Bahishti 0.34 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 12
DESCRIPTION OF ITEM

13 Cement concrete tiles laid in 1:2 cement mortar over 3/4" thick bed of cement mortar 1:2

a) 12" x 12" x 1"

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement concrete tiles (1" thick) 105 Nos 0.00 Each -


2 Cement for bedding and laying of 1:2 rat 1.85 Bags 0.00 Per Bag -
4 Sand 4.67 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 200 SFT

Mason 1.25 No. 0.00 Per day -


Coolies 2.00 No. 0.00 Per day -
Bahishti 0.34 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. Say 0.00

Page 13
b) 9" x 9" x 3/4"

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement concrete tiles 186 Nos 0.00 Each -


2 Cement for bedding and laying of 1:2 1.86 Bags 0.00 Per Bag -
4 Sand 4.67 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 200 SFT.

Mason 1.25 No. 0.00 Per day -


Coolies 2.00 No. 0.00 Per day -
Bahishti 0.34 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 14
c) 6" x 6" x 3/4"

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement concrete tiles 420 Nos 0.00 Each -


2 Cement for bedding and laying of 1:2 rat 1.90 Bags 0.00 Per Bag -
4 Sand 4.74 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 200 SFT.

Mason 1.25 No. 0.00 Per day -


Coolies 2.00 No. 0.00 Per day -
Bahishti 0.34 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 15
DESCRIPTION OF ITEM

14 Coloured cement tiles (8"x8"3/4") of approved dark shade laid flat in 1:2 cement
mortar over 3/4" bedding mortar of 1:2

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Tiles 240 Each 0.00 Each -


2 Cement 1.87 Bag 0.00 Per Bag -
3 Sand 4.70 Cft. 0.00Per 100 Cft -
4 Pigment 0.67 Lbs (0.30 Kg 0.00 Per Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 200 SFT.

Mason 1.25 No. 0.00 Per day -


Coolies 2.00 No. 0.00 Per day -
Bahishti 0.34 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 16
DESCRIPTION OF ITEM

15 Providing and laying topping of cement concrete (1:2:4) including


surface finishing and dividing into panels.

a) 1" (25mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 1.50 Bags 0.00 Per Bag -


2 Sand 3.70 Cft. 0.00Per 100 Cft -
3 Shingle 7.40 Cft. 0.00Per 100 Cft -
4 Form Work (Kail Wood) 0.034 Cft. 0.00 Per Cft. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 1.00 No. 0.00 Per day -


Coolies 0.50 No. 0.00 Per day -
Bahishti 0.10 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 17
b) 1" (30mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 1.85 Bags 0.00 Per Bag -


2 Sand 4.60 Cft. 0.00Per 100 Cft -
3 Shingle 9.20 Cft. 0.00Per 100 Cft -
4 Form Work (Kail Wood) 0.034 Cft. 0.00 Per Cft. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 1.00 No. 0.00 Per day -


Coolies 0.50 No. 0.00 Per day -
Bahishti 0.10 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 18
c) 1" (40mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 2.20 Bags 0.00 Per Bag -


2 Sand 5.50 Cft. 0.00Per 100 Cft -
3 Shingle 11.00 Cft. 0.00Per 100 Cft -
4 Form Work (Kail Wood) 0.034 Cft. 0.00 Per Cft. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 1.00 No. 0.00 Per day -


Cooly (Unskilled) 1.00 No. 0.00 Per day -
Bahishti 0.15 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 19
3
d) 1 /4" (45mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 2.55 Bags 0.00 Per Bag -


2 Sand 6.50 Cft. 0.00Per 100 Cft -
3 Shingle 12.80 Cft. 0.00Per 100 Cft -
4 Form Work (Kail Wood) 0.040 Cft. 0.00 Per Cft. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 1.00 No. 0.00 Per day -


Cooly 1.00 No. 0.00 Per day -
Bahishti 0.15 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 20
e) 2" (50mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 3.00 Bags 0.00 Per Bag -


2 Sand 7.40 Cft. 0.00Per 100 Cft -
3 Shingle 14.70 Cft. 0.00Per 100 Cft -
4 Form Work (Kail Wood) 0.040 Cft. 0.00 Per Cft. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 1.00 No. 0.00 Per day -


Cooly 1.50 No. 0.00 Per day -
Bahishti 0.20 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 21
f) 2" (55mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 3.30 Bags 0.00 Per Bag -


2 Sand 8.40 Cft. 0.00Per 100 Cft -
3 Shingle 16.50 Cft. 0.00Per 100 Cft -
4 Form Work (Kail Wood) 0.046 Cft. 0.00 Per Cft. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 1.00 No. 0.00 Per day -


Cooly 1.60 No. 0.00 Per day -
Bahishti 0.20 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 22
g) 2" (60mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 3.65 Bags 0.00 Per Bag -


2 Sand 2.20 Cft. 0.00Per 100 Cft -
3 Shingle 18.35 Cft. 0.00Per 100 Cft -
4 Form Work (Kail Wood) 0.051 Cft. 0.00 Per Cft. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 1.00 No. 0.00 Per day -


Cooly 2.00 No. 0.00 Per day -
Bahishti 0.25 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 23
h) 2 3/4" (70mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 4.00 Bags 0.00 Per Bag -


2 Sand 10.00 Cft. 0.00Per 100 Cft -
3 Shingle 20.20 Cft. 0.00Per 100 Cft -
4 Form Work (Kail Wood) 0.051 Cft. 0.00 Per Cft. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 1.00 No. 0.00 Per day -


Cooly 2.00 No. 0.00 Per day -
Bahishti 0.25 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 24
i) 3" (75mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement 4.40 Bags 0.00 Per Bag -


2 Sand 11.00 Cft. 0.00Per 100 Cft -
3 Shingle 22.00 Cft. 0.00Per 100 Cft -
4 Form Work (Kail Wood) 0.057 Cft. 0.00 Per Cft. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 1.00 No. 0.00 Per day -


Cooly 2.00 No. 0.00 Per day -
Bahishti 0.25 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 25
DESCRIPTION OF ITEM

16 Providing and laying conglomerate flooring (two coat work) with top layer of " thick
wearing surface, consisting of one part of cement and two parts of stone chips passing
3/16" sieave, over bottom layer of cement concrete 1:3:6 including surface finishing and
dividing in panels:-

a) 1" (40mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

i) " Thick Topping

1 Cement 1.25 Bags 0.00 Per Bag -


2 Sand 3.00 Cft. 0.00Per 100 Cft -

ii) 1" Thick Bedding 1:3:6

Cement 1.08 Bags 0.00 Per Bag -


Sand 3.83 Cft. 0.00Per 100 Cft -
Shingle 7.67 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

i) " Thick Topping

Mason 0.50 No. 0.00 Per day -


Cooly 0.25 No. 0.00 Per day -
Bahishti 0.05 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -

ii) 1" Thick Bedding 1:3:6

Mason 0.80 No. 0.00 Per day -


Cooly 0.50 No. 0.00 Per day -
Bahishti 0.15 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. Say 0.00
Composite Rate per Sqm. Rs. Say 0.00

Page 26
b) 1 3/4" (45mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

i) " Thick Topping

1 Cement 1.25 Bags 0.00 Per Bag -


2 Sand 3.00 Cft. 0.00Per 100 Cft -

ii) 1" Thick Bedding 1:3:6

Cement 1.35 Bags 0.00 Per Bag -


Sand 4.06 Cft. 0.00Per 100 Cft -
Shingle 8.12 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

i) " Thick Topping

Mason 0.50 No. 0.00 Per day -


Cooly 0.25 No. 0.00 Per day -
Bahishti 0.05 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -

ii) 1" Thick Bedding 1:3:6

Mason 0.80 No. 0.00 Per day -


Cooly 0.50 No. 0.00 Per day -
Bahishti 0.15 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. Say 0.00

Page 27
c) 2" (50mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

i) " Thick Topping

1 Cement 1.25 Bags 0.00 Per Bag -


2 Sand 3.00 Cft. 0.00Per 100 Cft -

ii) 1" Thick Bedding 1:3:6

Cement 1.63 Bags 0.00 Per Bag -


Sand 5.75 Cft. 0.00Per 100 Cft -
Shingle 11.50 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

i) " Thick Topping 1:2

Mason 0.50 No. 0.00 Per day -


Cooly 0.25 No. 0.00 Per day -
Bahishti 0.05 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -

ii) 1" Thick Bedding 1:3:6

Mason 1.00 No. 0.00 Per day -


Cooly 1.00 No. 0.00 Per day -
Bahishti 0.20 No. 0.00 Per day -
Carpenter 0.30 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 28
DESCRIPTION OF ITEM

17 Add extra in cement concrete floor topping, if finished with pigment and polishing

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL
1 Grey Cement for Finishing 1/16" Thick 0.40 Bags 0.00 Per Bag -
2 Pigment 4.5 Lbs (2.04 Kg 0.00 Per Kg. -
3 Polish 0.5 Lbs (0.23 Kg. 0.00 Per Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 150 SFT.

Mason 0.50 No. 0.00 Per day -


Cooly (Skilled) 0.50 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 29
DESCRIPTION OF ITEM

18 Extra labour for each storey above ground floor for moasic, conglomerate, tiles
stone and wooden floor

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

LABOUR FOR 125 SFT.

Cooly for carriage of material 0.75 No. 0.00 Per day -


Sundries ## Percent -
Total -
Contractor's Profit & Ove ## Percent -
Total -

ITEM RATE

Labour Rate per 100 Sft. Rs. 0.00 Say 0.00


Labour Rate per Sqm. Rs. - Say 0.00

DESCRIPTION OF ITEM

19 Flag stone flooring laid in lime mortar 1:2 over 3/4" bedding mortar in plat forms
and floors etc.

a) 2" (50mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Dressed Stone 2'x2'x2" 25.00 Nos. 0.00 Each -


2 Lime 1.3 Mds (48.5 Kg 0.00 Per Kg. -
3 Sand 5.00 Cft. 0.00Per 100 Cft -
4 Steel 0.76 Kg. 0.00 Per Kg. -
5 Charcoal 1.75 Kg. 0.00 Per Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 2.50 No. 0.00 Per day -


Coolies 3.00 No. 0.00 Per day -
Bahishti 0.12 No. 0.00 Per day -
Blacksmith 0.10 No. 0.00 Per day -
Bollow Man 0.10 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 30
b) 3" (75mm) Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Dressed Stone 2'x2'x3" 25.00 Nos. 0.00 Each -


2 Lime 1.42 Mds (53 Kg.) 0.00 Per Kg. -
3 Surkhi 5.00 Cft. 0.00Per 100 Cft -
4 Steel 0.75 Kg. 0.00 Per Kg. -
5 Charcoal 1.81 Kg. 0.00 Per Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 2.50 No. 0.00 Per day -


Cooly 3.00 No. 0.00 Per day -
Bahishti 0.12 No. 0.00 Per day -
Blacksmith 0.10 No. 0.00 Per day -
Bollow Man 0.10 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 31
DESCRIPTION OF ITEM

20 Asphalt flooring including preparation of proper base, remelting, setting out and
finishing complete

a) 1" Thick Topping

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Asphalt 2.36 Cwt (119.90 Kg 0.00 Per Kg. -


2 Steam Coal 0.5 Md (18.66 Kg. 0.00 Per Kg. -
3 Fine Aggregate 9.00 Cft. 0.00Per 100 Cft -
4 Form Work (Kail Wood) 0.034 Cft. 0.00 Per Cft. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason for Setting out and laying 0.25 No. 0.00 Per day -
Coolies 2.00 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. Say 0.00

Page 32
b) " Thick Topping

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Asphalt 1.20 Cwt (60.960 Kg 0.00 Per Kg. -


2 Steam Coal 0.25 Md (9.33 Kg. 0.00 Per Kg. -
3 Fine Aggregate 4.51 Cft. 0.00Per 100 Cft -
4 Form Work (Kail Wood) 0.034 Cft. 0.00 Per Cft. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 0.20 No. 0.00 Per day -


Coolies 1.50 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 33
c) " Thick Topping

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Asphalt 0.60 Cwt (30.48 Kg 0.00 Per Kg. -


2 Steam Coal 0.25 Md (8.58 Kg. 0.00 Per Kg. -
3 Fine Grit 2.51 Cft. 0.00Per 100 Cft -
4 Form Work (Kail Wood) 0.034 Cft. 0.00 Per Cft. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 0.17 No. 0.00 Per day -


Cooly 1.00 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 34
DESCRIPTION OF ITEM

21 1 3/8" thick mosaic flooring consisting of 3/8" mosaic topping of one part of
cement and marble powder in the ratio 3:1 and two parts of marble chips laid
over 1" thick flooring of 1:2:4 cement concrete including rubbing and polishing
complete.

a) Using Grey Cement

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL for mosaic topping, rubbing & polishing

1 Cement For 3/8" topping 0.94 Bag 0.00 Per Bag -


2 Marble Chips 3.00 Cwt (152.40 Kg 0.00 Per Kg. -
3 Corborandom Stone 3.00 Nos. 0.00 Each -
4 Wax Polish 0.5 Lbs (0.23 Kg. 0.00Pack. of 3 -
5 Linen and Cotton 0.40 Kg. 0.00 P. Kg. -
6 Marble Powder 0.31 Cwt (15.75 Kg 0.00Per 100 Kg. -
7 Tatric Acid 0.34 Lbs (0.15 Kg 0.00 Per Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

MATERIAL for 1" thick 1:2:4 concrete

1 Cement 1.50 Bags 0.00 Per Bag -


2 Sand 3.70 Cft. 0.00Per 100 Cft -
3 Shingle 7.40 Cft. 0.00Per 100 Cft -
4 Form Work 0.034 Cft. 0.00 P. Cft. -
Total -
Contractor's Profit & Ove ## Percent -
Total -
Total Material -

LABOUR for mosaic topping

Mason for Laying 1.50 No. 0.00 Per day -


Coolies 1.25 No. 0.00 Per day -
Coolies (skilled for rubbing) 5.00 Nos. 0.00 Per day -
Bahishti 0.75 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

LABOUR for 1" Thick 1:2:4 Concrete

As per Item 15(a) -


Total Labour -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 35
b) Using White Cement

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL for 3/8"

1 Cement (White) 0.94 Bag 0.00 Per Bag -


2 Marble Poweder 0.31 Cwt (15.75 Kg 0.00Per 100 Kg. -
3 Marble Chips 3.00 Cwt (152.40 Kg 0.00 Per Kg. -
4 Carborandom Stone 3.00 Nos. 0.00 Each -
5 Wax Polish 0.50 Lbs (0.23 Kg 0.00Packet 3 Kg -
6 Linen Cotton etc. 0.40 Kg. 0.00 P. Kg. -
7 Tar Taric Acid 0.34 Lbs (0.15 Kg 0.00 Per Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

Add for cement concrete 1" thick


As per Item 15(a) Material -
Total Material 0.01

LABOUR

Mason for Laying 1.50 No. 0.00 Per day -


Coolies 1.25 No. 0.00 Per day -
Coolies (skilled for rubbing) 5.00 Nos. 0.00 Per day -
Bahishti 0.75 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

Add Labour for 1" thick C.C. topping 1:2:4


As per item No. 15(a) -
Total Labour -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 36
DESCRIPTION OF ITEM

22 1" thick mosaic flooring consisting of " mosaic topping of one part of
cement and marble powder in the ratio of 3:1 and two parts of marble chips laid
over 1" thick flooring of 1:2:4 cement concrete including rubbing and polishing
complete.

a) Using Grey Cement

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Grey Cement for " Topping 1.27 Bag 0.00 Per Bag -
2 Marble Chips 3.00 Cwt (152.40 Kg 0.00 Per Kg. -
3 Carborandom Stone 2.00 Nos. 0.00 Each -
4 Wax Polish 0.50 Lbs (0.23 Kg 0.00Packet 3 Kg -
5 Linen Cotton etc. 0.72 Kg. 0.00 P. Kg. -
6 Tar Taric Acid 0.34 Lbs / (0.15 Kg 0.00 Per Kg. -
7 Marble Poweder 0.42 Cwt (21.34 Kg 0.00Per 100 Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

Add Material for 1" thick cement concrete


Topping as per Item 15(a) -
Total Material -

LABOUR FOR 125 SFT.

Mason for Laying 1.50 No. 0.00 Per day -


Coolies 1.25 No. 0.00 Per day -
Coolies (skilled for rubbing and Polish 5.00 Nos. 0.00 Per day -
Bahishti 0.75 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

Add Labour for 1" thick cement concrete


Topping as per Item 15(a) -
Total Labour -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 37
b) Using White Cement

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Cement White 1.27 Bag 0.00 Per Bag -


2 Marble Powder 0.42 Cwt (21.34 Kg 0.00Per 100 Kg. -
3 Marble Chips 4.16 Cwt (211.33 Kg 0.00 Per Kg. -
4 Carborandom Stone 3.00 Nos. 0.00 Each -
5 Wax Polish 0.50 Lbs (0.23 Kg 0.00Packet 3 Kg -
6 Linen Cotton etc. 0.72 Kg. 0.00 P. Kg. -
7 Tar Taric Acid 0.34 Lbs (0.15 Kg 0.00 Per Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

Add for material of 1" thick cement concrete


Topping as per Item No. 15(a) -
Total Material -

LABOUR FOR 125 SFT.

Mason for Laying 1.50 No. 0.00 Per day -


Coolies 1.25 No. 0.00 Per day -
Coolies (skilled for rubbing and Polish 5.00 Nos. 0.00 Per day -
Bahishti 0.75 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

Add labour for 1" thick cement concrete


Topping as per Item No. 15(a) -
Total Labour -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 38
DESCRIPTION OF ITEM

23 Providing and laying floor of mosaic marble chips tiles 1" thick of approved quality and
laid in white cement and pigment over 3/4" bedding of cement sand mortar 1:2, incluidng
finishing and polishing complete.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Mosaic marble tiles 12"x12"x1" 105 Nos. 0.00 Each -


2 Cement Grey 1.69 Bags 0.00 Per Bag -
3 Sand 4.00 Cft. 0.00Per 100 Cft -
4 Pigment 1.00 Lbs (0.45 Kg 0.00 Per Kg. -
5 White Cement 0.08 Bag 0.00 Per Bag -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 1.84 No. 0.00 Per day -


Coolies 2.80 No. 0.00 Per day -
Bahishti 0.34 Nos. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 39
DESCRIPTION OF ITEM

24 Laying floor of approved white glazed tile 1/4" thick in white cement 1:2 over
3/4" thick cement mortar 1:2 complete.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Tile (Glazed) 6"x6"x" including 5% brea 420 No. 0.00 Each -


2 White Cement for laying 0.10 Bag 0.00 Per Bag -
3 Grey Cement for Bed 2.16 Bag 0.00 Per Bag -
4 Sand 5.20 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Masons 2.00 No. 0.00 Per day -


Coolies 4.00 No. 0.00 Per day -
Bahishti 0.50 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 40
DESCRIPTION OF ITEM

25 Laying floors of a approved coloured glazed tiles 1/4" thick laid in white
cement and pigment on a bed of 3/4" thick cement mortar 1:2

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Coloured glazed tiles 6"x6" including 5 420 No. 0.00 Each -


2 White Cement 0.10 Bag 0.00 Per Bag -
3 Grey Cement 2.16 Bag 0.00 Per Bag -
4 Pigment 1.00 Lb/0.45 Kg. 0.00 Per Kg. -
5 Sand 5.20 Cft 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Masons 2.00 No. 0.00 Per day -


Coolies 4.00 No. 0.00 Per day -
Bahishti 0.50 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 41
DESCRIPTION OF ITEM

26 Rubbing and polishing old grit/mosaic floor including repairing voids, un-even
surface complete in all respects.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Carborandum Stone 0.50 No. 0.00 Each -


2 Wax Polish 0.50 Lb (0.23 Kg. 0.00cket of 3 K -
3 Tartric Acid 0.34 Lb (0.162 Kg 0.00 Per Kg. -
4 Cotton waste cloth etc. 0.72 Kg. 0.00 P. Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 125 SFT.

Skilled Cooly for rubbing and polishing 1.00 No. 0.00 Per day -
Cooly 1.00 No. 0.00 Per day -
Bahishti 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 42
DESCRIPTION OF ITEM

27 Rubbing and Polishing grit floor, including repairing voids, uneven surface
complete in all respects.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Carborandum Stone 1.50 No. 0.00 Each -


2 Wax Polish 0.5 Lb (0.23 Kg.) 0.00cket of 3 K -
4 Cotton waste cloth etc. 0.08 Kg. 0.00 P. Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 125 SFT.

Cooly 1.00 No. 0.00 Per day -


Cooly Skilled 1.00 0.00 -
Bahishti 0.40 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 43
DESCRIPTION OF ITEM

28 Cleaning and washing mosaic or marble floor with caustic soda mixture

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Caustic Soda 1 Lb (0.45 Kg.) 0.00 Per Kg. -


2 Hassein Cloth 0.5 Yard (0.46 m) 0.00 Per Metre -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 150 SFT.

Mason 0.25 No. 0.00 Per day -


Bahishti 0.12 No. 0.00 Per day
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 44
DESCRIPTION OF ITEM

29 Shisham wood boarding or strips flooring 3/4" thick (sawn to required sizes)
tongued and grooved or splayed rebated fixed with brass screws on deedar wood
battens 1"x2" placed at 12" centre to centre including two coats of bitumen laid
hot on the base.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Shisham Wood

100 x 3/4' x 1/12' 6.25 Cft.


Add 5% rebate 0.31 Cft.
Total 6.56 Cft.
Add 60% Wastage 3.94 Cft.
Total 10.50 Cft. 0.00 Per Cft. -

Deodar Wood Battens

11 x 10' x 1/8' x 1/6' 2.29 Cft.


Add 50% Wastage 1.15 Cft.
Total 3.44 Cft. 0.00 Per Cft. -

Bitumen 35 Lbs (15.89 Kg. 0.00 Per Kg. -


Fire Wood 0.125 Lbs (4.67 Kg 0.00 Per Kg. -
Brass Screws 2" 7.00 Dozen 0.00 Per Dozen -
Sand Paper Sheet 1.50 Dozen 0.00 Per Dozen -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 300 SFT.

Carpenters 10.00 No. 0.00 Per day -


Coolies 5.00 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 45
DESCRIPTION OF ITEM

30 Decdar wood boarding or strips flooring 3/4" thick (sawn to required


sizes)tongued and grooved or splayed rebated fixed with brass screws on
deodar wood battens 1"x2" placed at 12" c/c including two coats of bitumens
laid hot on the base.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Deodar wood planks 100 x 3/4' x 1/12' 6.25 Cft.


Add 5% for rebate 0.31 Cft.
Total 6.56 Cft.
Deodar wood batten 11x10' x 1/6' x 1/8' 2.29 Cft.
Total 8.85 Cft.
Add 50% Wastage 4.43 Cft.
Total 13.28 Cft. 0.00 Per Cft. -

Bitumen 34 Lbs (15.44 Kg. 0.00 Per Kg. -


Fire Wood 0.125 Mds (4.67 Kg 0.00 Per Kg. -
Brass Screws 2" long 7.00 Dozen 0.00 Per Dozen -
Sand Paper 1.00 Dogen 0.00 Per Dozen -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 200 SFT.

Carpenters 6.00 No. 0.00 Per day -


Coolies 6.00 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 46
DESCRIPTION OF ITEM

31 Teakwook boarding or strips flooring " thick (Sawn to required sized)


tongued and grooved screwed on deodar wood battens 1" x 2" size, placed at 12"
centre to centre including 2 coats of bitumen laid hot on the base.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1
Teak Wood (100x' x /12' 4.20 Cft.
Add 5% for rebate 0.20 Cft.
Total 4.40 Cft.
Add 20% Wastage 0.88 Cft
Total 5.28 Cft. 0.00 Per Cft. -

Deodar wood 11x10' x 1/8' x 1/6' 2.29 Cft.


Add. 50% Wastage 1.15
Total 3.44 Cft. 0.00 Cft. -

Bitumen 34 Lbs (15.44 Kg. 0.00 Per Kg. -


Sand Paper 2.00 Dozen 0.00 Per Dozen -
Fuel Wood 0.125 Mds (4.67 Kg 0.00 Per Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 300 SFT.

Carpenters 10.00 No. 0.00 Per day -


Coolies 5.00 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 47
DESCRIPTION OF ITEM

32 Shisham wood block flooring 1" thick cut to required size, fixed on a layer of
asphalt bitumen laid on base

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Shisham Wood of best quality 8.33 Cft.


100 x 1/12' sawan to required size
Add 100 % Wastage 8.33 Cft.
Total 16.66 Cft. 0.00 Per Cft. -

Bitumen for laying and dipping blocks 80 Lbs (36.32 Kg. 0.00 Per Kg. -
Primer 5.00 Lbs (2.27 Kg 0.00 Per Kg. -
Fire Wood 0.25 Md (9.33 Kg. 0.00 Per Kg. -
Sand Paper 2.00 Dozen 0.00 Per Dozen -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 200 SFT.

Carpenters 6.00 No. 0.00 Per day -


Coolies 5.00 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 48
DESCRIPTION OF ITEM

33 Teak wood block 1" thick cut to required size fixed on a layer of asphalt bitumen laid on

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Teak wood for blocks 1" 8.33 Cft.


thick sawn to size 100 x1/12'
Add 40% Wastage 3.33 Cft.
Total 11.66 Cft. 0.00 Per Cft. -

Bitumen 80 Lbs (36.32 Kg. 0.00 Per Kg. -


Primer 5.00 Lbs (2.27 Kg 0.00 Per Kg. -
Fuel Wood 0.125 Lbs (4.67 Kg 0.00 Per Kg. -
Sand Paper 2.00 Dozen 0.00 Per Dozen -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 300 SFT.

Carpenters 10.00 No. 0.00 Per day -


Coolies 5.00 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 49
DESCRIPTION OF ITEM

34 Laying wooden paving of hard wood on edge in coal tar and asphalt

a) Shisham Wood

Detail Unit Rate Per 100 Sft. (Per Inch Thickness)


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Shisham Wood Sawn into 8.33 Cft.


1" thick or any required size
Add 30% Wastage 2.50 Cft.
Total 10.83 Cft. 0.00 Per Cft. -

Bitumen 34 Lbs / 15.44 Kg 0.00 Per Kg. -


Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 150 SFT.

Carpenters 1.00 No. 0.00 Per day -


Coolies 3.00 No. 0.00 Per day -
Mason 1.00 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 50
b) Kikar Wood

Detail Unit Rate Per 100 Sft. (Per Inch Thickness)


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Kikar Wood = 100 x 1 8.33 Cft.


12
Wastage 30% 2.50 Cft.
Total 10.83 Cft. 0.00 Per Cft. -

Bitumen 34 Lbs (15.44 Kg. 0.00 Per Kg. -


Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 150 SFT.

Carpenter 1.00 No. 0.00 Per day -


Coolies 3.00 No. 0.00 Per day -
Mason 1.00 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 51
DESCRIPTION OF ITEM

35 Tile skirting laid in 1:2 cement mortar over 3/4" thick cement mortar 1:2 including
cement washing and filling joints complete.

a) Cement Tiles

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Cement tiles 8"x8" including 5% breakage 240 No. 0.00 Each -


and Wastage
Cement for laying and pointing cement t 2.45 Bags 0.00 Per Bag -
Sand 6.00 Cft. 0.00Per 100 Cft -
Pigment 1 Lb (0.45 Kg.) 0.00 Per Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 150 SFT.

Masons 1.56 No. 0.00 Per day -


Coolies 2.50 No. 0.00 Per day -
Bahishti 0.34 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 52
b) Mosaic Tiles

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Tiles 6"x6"x3/4" 420 No. 0.00 Each -


Cement 2.54 Bag 0.00 Per Bag -
Sand 6.00 Cft 0.00Per 100 Cft -
Pigment 1 Lbs (0.45 Kg.) 0.00 Per Kg. -
White Cement 0.08 Bag 0.00 Per Bag -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Masons 2.00 No. 0.00 Per day -


Coolies 2.50 No. 0.00 Per day -
Bahishti 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 53
DESCRIPTION OF ITEM

36 Providing grey cement skirting or dado 3/8" thick including rounding of corner and
straightening of top edge and finishing to smooth surface after plastering

a) 1:2 Cement Sand Mortar

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Cement 0.96 Bag 0.00 Per Bag -


Sand 2.50 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 125 SFT.

Masons 2.50 No. 0.00 Per day -


Coolies 1.50 No. 0.00 Per day -
Bahishti 0.34 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 54
b) 1:3 Cement Sand Mortar

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Cement 0.66 Bag 0.00 Per Bag -


Sand 2.55 Bag 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 125 SFT.

Masons 2.50 No. 0.00 Per day -


Coolies 1.50 No. 0.00 Per day -
Bahishti 0.34 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 55
c) Extra if skirting or dado is finished with pigment of any colour

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Pigment 6 Lbs (2.72 Kg.) 0.00 Per Kg. -


Contractor's Profit & Ove ## Percent -
Total -

LABOUR FOR 200 SFT.

Cooly for mixing 0.50 No. 0.00 Per day -


Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 56
DESCRIPTION OF ITEM

37 White glazed tiles " thick dado jointed in white cement and laid over 1:2 cement
sand mortar 3/4" thick including finishing complete

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Tiles 6"x6"x" 420 No. 0.00 Each -


White Cement 0.10 Bag 0.00 Per Bag -
Grey Cement 2.16 Bag 0.00 Per Bag -
Sand 5.20 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 2.50 No. 0.00 Per day -


Coolies 5.00 No. 0.00 Per day -
Bahishti 0.50 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 57
DESCRIPTION OF ITEM

3
38 Glazed tile dado " thick dado laid in pigment over 1:2 cement sand mortar /4" thick
including finishing

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Tiles 6"x6"x" 420 No. 0.00 Each -


White Cement 0.10 Bag 0.00 Per Bag -
Grey Cement 2.16 Bag 0.00 Per Bag -
Pigment 0.67 Lb (0.30 Kg. 0.00 Per Kg. -
Sand 5.00 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 2.50 No. 0.00 Per day -


Coolies 5.00 No. 0.00 Per day -
Bahishti 0.50 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 58
DESCRIPTION OF ITEM

39 Masaic dado or skirting with one part of cement and marble powder in the ratio of
3:! and two parts of marble chips, laid over " thick cement plaster 1:3 including
rubbing and polishing complete with finishing:

a - i) Using Grey Cement 3/8" Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Grey Cement 0.94 Bags 0.00 Bag -


Marble Powder 0.31 Cwt. (15.75 Kg 0.00Per 100 Kg. -
Marble Chips 3.00 Cwt.(152.40 Kg 0.00 Per Kg. -
Carbordum Stone 3 No. 0.00 Per Kg. -
Wax Polish 0.5 Lbs (0.23 Kg. 0.00Packet 3 Kg -
Tartric Acid 0.34 Lbs (0.15 Kg 0.00 Per Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 2.00 No. 0.00 Per day -


Coolies 2.00 No. 0.00 Per day -
Skilled Cooly 5.00 No. 0.00 Per day -
Bahishti 1.00 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 59
a-ii) Using Grey Cement " Thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Cement 1.27 Bags 0.00 Bag -


Marble Powder 0.42 Cwt. (21.34 Kg 0.00Per 100 Kg. -
Marble Chips 3 Cwt. (152.40 Kg 0.00 Per Kg. -
Carboradom Stone 3 No. 0.00 Each -
Wax Polish 0.5 Lbs (0.23 Kg. 0.00Packet 3 Kg -
Linion Cloth 0.72 Kg. 0.00 P. Kg. -
Tartric Acid 0.34 Lbs (0.15 Kg 0.00 Per Kg. -

"cement plaster under neath

Cement 0.88 Bag 0.00 Bag -


Sand 3.40 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 2.00 No. 0.00 Per day -


Cooly 2.00 No. 0.00 Per day -
Skilled Cooly 5.00 No. 0.00 Per day -
Bahishti 1.00 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 60
b-i) Using White Cement 3/8" thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

i) 3/8" Thick

White Cement 0.94 Bags 0.00 Bag -


Marble Powder 0.31 Cwt. (15.75 Kg 0.00Per 100 Kg. -
Marble Chips 3 Cwt. (152.40 Kg 0.00 Per Kg. -
Carboradom Stone 3 No. 0.00 Each -
Wax Polish 0.5 Lbs (0.23 Kg. 0.00Packet 3 Kg -
Linion Cloth 0.72 Kg. 0.00 P. Kg. -
Tartric Acid 0.34 Lbs (0.15 Kg 0.00 Per Kg. -

ii) "cement plaster under neath

Grey Cement 0.88 Bag 0.00 Bag -


Sand 3.40 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason for Laying 2.00 No. 0.00 Per day -


Coolies for rubbing and polishing 5.00 No. 0.00 Per day -
Coolies 2.00 No. 0.00 Per day -
Bahishti 1.00 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 61
b-ii) Using White Cement (" thick)

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

i) Thick

White Cement 1.27 Bags 0.00 Bag -


Marble Powder 0.42 Cwt. (21.34 Kg 0.00Per 100 Kg. -
Marble Chips 3 Cwt. (152.40 Kg 0.00 Per Kg. -
Carboradom Stone 3 No. 0.00 Each -
Wax Polish 0.5 Lbs (0.23 Kg. 0.00Packet 3 Kg -
Linion Cloth 0.72 Kg. 0.00 P. Kg. -
Tartric Acid 0.34 Lbs / 0.15 Kg 0.00 Per Kg. -

ii) "cement plaster 1:3 under neath

Grey Cement 0.88 Bag 0.00 Bag -


Sand 3.40 Cft. 0.00Per 100 Cft -
Total
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 2.00 No. 0.00 Per day -


Skilled Cooly 5.00 No. 0.00 Per day -
Coolies 2.00 No. 0.00 Per day -
Bahishti 1.00 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per 100 Sft. Rs. - Say 0.00
Composite Rate per Sqm. Rs. - Say 0.00

Page 62
DESCRIPTION ITEM

40 Rubber Flooring, consisting of 12"x12"x1/8" rubber tiles laid on firm foundation

Detail Unit Rate Per Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

(Assume for 100 Sft.)

MATERIAL

Rubber tiles (12"x12"x1/8") 105 Nos. 0.00 Each -


including 5% wastage
Adhesive mixutre (10 Lbs) (4.56 Kg.) 4.56 Kg. 0.00 Kg. -
Brushes etc. 0.04 No. 0.00 Each -
Total -
Contractor's Profit & Ove ## Percent -
Total -

LABOUR

Mason 1.00 No. 0.00 Per day -


Coolies 1.50 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00

ITEM RATE

Labour Rate Per Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate per Sft. Rs. Say 0.00
Composite Rate per Sqm. Rs. Say 0.00

Page 63
DESCRIPTION OF ITEM

41 Providing and Fixing Glass Strip 5mm thick and 1" wide
for dividing mosaic flooring into panels.

Detail Unit Rate Per Rft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

(Assume for 100 Rft.)

MATERIAL

Glass Strips 1" wide


5mm Thick 100.00 Rft.
Wastage 10% 10.00 Rft.
Total 110.00 Rft. 0.00Per 100 Rft -
Contractor's Profit & Ove ## Percent -
Total -

ITEM RATE

Composite Rate per Rft. Rs. - Say 0.00

Composite Rate per R.M. Rs. - Say 0.00

Note :Labour for fixing already included in item 15 & 22 of this chapter

Page 64
DESCRIPTION OF ITEM

42 Providing and fixing marble strip of any shade for dividing the mosaic flooring into pann

a) Size 1" x 3/8"

Detail Unit Rate Per Rft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

(Assume for 100 Rft.)

MATERIAL

Marble Strip 1" x 3/8" 100.00 Rft.


Wastage 10% 10.00 Rft.
Total 110.00 Rft. 0.00 Per Rft. -
Contractor's Profit & Ove ## Percent -
Total -

ITEM RATE

Composite Rate per Rft. Rs. - Say 0.00

Composite Rate per R/M Rs. - Say 0.00

Note Labour already included in item 15, 16 and 22 of this chapter.

Page 65
b) Size 1" x "

Detail Unit Rate Per Rft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

(Assume for 100 Rft.)

MATERIAL

Marble Strips 1" x " 100.00 Rft.


Wastage 10% 10.00 Rft.
Total 110.00 Rft. 0.00 Per Rft. -
Contractor's Profit & Ove ## Percent -
Total -

ITEM RATE

Composite Rate per Rft. Rs. - Say 0.00

Composite Rate per R/M Rs. - Say 0.00

Note Labour already included in item 15, 16 and 22 of this chapter.

Page 66
CHAPTER NO. 25

IRON WORK
DESCRIPTION OF ITEM:

1 Laying, Linking & Packing


Tram way line.

Detail Unit of Rate 100 Rft.


Rate
Qty Per Unit Amount
Rate Analysis for 350 Rft
LABOUR

1 Jamadar (Mate) 1.00 No. 0.00 0.00


2 Keyman (Skilled Cooly) 1.00 No. 0.00 0.00
3 Coolies (Unskilled) 7.00 Nos. 0.00 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate Per 100 Lft. Rs. - Say 0.00


Labour Rate Per R M Rs. - Say 0.00

Page 1
2. Dismantling Tramway track.

Detail Unit of Rate 100 Rft.


Rate
Qty Per Unit Amount
Rate Analysis for 1400 Rft.
LABOUR

1 Jamadar (Mate) 1.0 No. 0.00 0.00


2 Skilled Cooly 1.0 No. 0.00 0.00
3 Coolies (Unskilled) 10.0 Nos. 0.00 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate Per 100 Lft. Rs. - Say 0.00


Labour Rate per RM Rs. - Say 0.00

Page 2
3. Laying, Linking of B.G Track including packing, straightening and levelling.

Detail Unit = 100 Rft


Rate
Qty Per Unit Amount
Rate Analysis per 120 Rft.
LABOUR

1 Jamadar (Mate) 1.0 No. 0.00 0.00


2 Keyman (Skilled Cooly) 1.0 No. 0.00 0.00
3 Coolies (Unskilled) 6.0 Nos. 0.00 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate Per 100 Lft. Rs. - Say 0.00

Labour Rate per RM Rs. - Say 0.00

Page 3
4. Linking points and crossings complete with fastenings.

Detail Unit = Each


Rate
Qty Per Unit Amount

LABOUR

1 Jamadar (Mate) 0.5 No. 0.00 0.00


2 Keyman (Skilled Cooly) 0.5 No. 0.00 0.00
3 Coolies (Unskilled) 5.5 Nos. 0.00 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total Say 0.00

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00

Page 4
5. Bending or straightening B.G. rail with Jim crow

Detail Unit Rate Per Each Point


Rate
Qty Per Unit Amount

LABOUR

1 Black Smith 0.20 No. 0.00 per day 0.00


2 Coolies (Unskilled) 0.50 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total Say 0.00

ITEM RATE

Labour Rate Per Each Point Rs. - Say 0.00

Page 5
6. Fixing street lamp post.

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

LABOUR

1 Coolies (Unskilled) 0.85 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate Per/Each Rs. - Say 0.00

Page 6
7. Binding ends of sleepers and timbers of all sizes and kinds including spreading and
restacking.

Detail Unit Rate Per 100 Nos.


Rate
Qty Per Unit Amount

LABOUR

1 Fitter 1.5 No. 0.00 per day 0.00


2 Mate 0.5 No. 0.00 per day 0.00
3 Coolies (unskilled) 5.75 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
Say

ITEM RATE

Labour Rate Per 100 Nos. Rs. - Say 0.00

Page 7
8. Opening stacks of sleepers and Timbers of all kinds and sizes including spreading for
inspection and restacking within chain lead.

Detail Unit Rate Per 100 Nos.


Rate
Qty Per Unit Amount
Rate Analysis for 1500 Nos.
LABOUR

1 Mate 1.0 No. 0.00 per day 0.00


2 Coolies (unskilled) 14.0 Nos. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
Say 0.00

ITEM RATE

Labour Rate Per 100 Nos. Rs. - Say 0.00

Page 8
9. Small Iron work such as gusset plates, knees, bends, strips, straps, rings etc. including
cutting, drilling, revitting, bending assembling & fixing but excluding erection in position.

Detail Unit = 1 Cwt.


Rate
Qty Per Unit Amount
Rate Analysis for 1 Cwt.
MATERIAL

1 Iron = 1.0 Cwt. 55.90 Kg 0.00 per Kg


wastage 10% = 0.1 Cwt.
1.10 Cwt. or 55.
2 Char Coal 8.40 Kg 0.00 per Kg
3 Steel Revits 0.68 Kg 0.00 per Kg

Total
Contractor's Profit & O 20.00 Percent
Total

LABOUR

Black Smith 1.50 Nos. per day


Coolies (Unskilled) 2.50 Nos. per day

Total
Sundries 10.00 Percent
Total
Contractor's Profit & O 20.00 Percent
Total
Say
ITEM RATE
Labour Rate for 1 Cwt. Rs. Say

Composite Rate for 1 Cw Rs. Say

Labour Rate/100 Kgs. Rs. Say

Composite Rate/100 Kgs. Rs. Say

Page 9
10. Fabrication of heavy steel work, with angle, tees, flat iron, round iron and sheet iron for
making trusses, girders, tanks etc. including cutting, drilling, revitting handling,
assembling and fixing but excluding erection in position.

Detail Unit = 1 Cwt.


Rate
Qty Per Unit Amount
Rate Analysis for 1 Cwt.
MATERIAL

1 Iron = 1.00 Cwt


wastage 5% = 0.05 Cwt 53.36 Kg 0.00 Per Kg. 0.00
1.05 Cwt.or (53.36 Kg.)
2 Char Coal 7.46 Kg 0.00 Per Kg. 0.00
3 Steel Revits 0.45 Kg 0.00 Per Kg. 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Black Smith 0.5 No. 0.00 per day 0.00


2 Hammer man 0.9 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate/Cwt Rs. 0.00 Say 0.00

Composite Rate/One Cwt. Rs. 0.00 Say 0.00

Labour Rate/100 Kg. Rs. 0.00 Say 0.00

Composite Rate/100 Kg Rs. 0.00 Say 0.00

Page 10
11. Erection and fitting in position of iron trusses, staging of water tanks.

Detail Unit = 100 Kg


Rate
Qty Per Unit Amount
Rate Analysis for 9.00 Cwt.

LABOUR

1 Fitter 2.0 No. 0.00 per day 0.00


2 Coolies (unskilled) 2.0 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

Rate/Cwt 0.00 = Rs. 65.88


9
ITEM RATE

Labour Rate / Cwt. Rs. - Say 0.00

Labour Rate 100 Kg Rs. 0.00 Say 0.00

Page 11
12. Fixing corrugated iron sheet including revitting.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 125 Sft.

LABOUR

1 Black smith 1.0 No. 0.00 Per day 0.00


2 Coolies (unskilled) 1.0 No. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate 100 Sft. Rs. - Say 0.00

Labour Rate/Sq.m Rs. - Say 0.00

Page 12
13. Erecting corrugated iron sheet tanks upto 20 ft. height.

Detail Unit = 100 Kg


Rate
Qty Per Unit Amount
Rate Analysis for 14.25 Cwt.

LABOUR

1 Black smith 2.0 Nos. 0.00 Per day 0.00


2 Coolies (unskilled) 9.5 Nos. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

Rate / Cwt. 0.00 = Rs. 0.00


14.25
ITEM RATE

Labour Rate/ One Cwt Rs. - Say 0.00

Labour Rate / 100 Kg. Rs. 0.00 Say 0.00

Page 13
14. Erecting rolled steel beams on old rails in roofs etc., erection and fixing in position.

Detail Unit 100 Kg.


Rate
Qty Per Unit Amount
Rate Analysis for 30 Cwt.

LABOUR

1 Black smith 0.5 No. 0.00 Per day 0.00


2 Coolies (unskilled) 14.5 Nos. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate /Cwt. Rs. - Say 0.00

Labour Rate / 100 Kg. Rs. 0.00 Say 0.00

Page 14
15. Erecting rolled steel beams or rails, erection for posts etc. (other than in roofs).

Detail Unit 100 Kg.


Rate
Qty Per Unit Amount
Rate Analysis for 30 Cwt.

LABOUR

1 Black smith 0.5 No. 0.00 Per day 0.00


2 Coolies (unskilled) 6.75 Nos. 0.00 Per day 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

Rate/Cwt. 0.01 = Rs. 0.00


30
ITEM RATE
Labour Rate /Cwt. Rs. - Say 0.00

Labour Rate / 100 Kg. Rs. 0.00 Say 0.00

Page 15
16. Making bolts and nuts of iron rods.

Detail Unit 100 Kg.


Rate
Qty Per Unit Amount
Rate Analysis for 1 Cwt.
MATERIAL

1 Mild Steel 1 .0 Cwt. 55.90 Kg 0.00 Per Kg. 0.00


wastage 10% 0.1 Cwt
1.1 Cwt. or (55.90 Kg)
2 Steel chisel 0.68 Kg 0.00 Per Kg. 0.00
3 Coal 46.51 Kg 0.00 Per Kg. 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Black Smith 1.5 Nos. 0.00 Per day 0.00


2 Hammer man 0.75 No. 0.00 Per day 0.00
3 Cooly (Unskilled) 0.75 No. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE
Labour Rate/ Cwt. Rs. 0.00 Say 0.00

Composite Rate/Cwt Rs. 0.00 Say 0.00

Labour Rate/100 Kg. Rs. 0.00 Say 0.00

Composite Rate/100 Kg. Rs. 0.00 Say 0.00

Page 16
17. Cutting rails, rolled steel joists and beams with hack saw:-
a) upto 6" size.

Detail Unit per cut


Rate
Qty Per Unit Amount
Rate Analysis for 1 Cut.
LABOUR

1 Fitter 0.15 No. 0.00 Per day 0.00


2 Coolies (unskilled) 0.15 No. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Cut Rs. - Say 0.00

Page 17
17. b) Above 6" size.

Detail Unit per Cut


Rate
Qty Per Unit Amount
Rate Analysis for 5 Cuts.
LABOUR

1 Fitter 1.20 Nos. 0.00 Per day 0.00


2 Coolies (unskilled) 1 No. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Cut. Rs. - Say 0.00

Page 18
18. Cutting rails or rolled steel beams of size below 6" with Jim.

Detail Unit per Cut


Rate
Qty Per Unit Amount
Rate Analysis for 14 Cuts
LABOUR

1 Fitter 1.00 No. 0.00 Per day 0.00


2 Coolies (unskilled) 1.00 No. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Cut. Rs. - Say 0.00

Page 19
19. Bending rolled steel beams on rails.

Detail Unit / Bend


Rate
Qty Per Unit Amount
Rate Analysis for 10 Bends
MATERIAL

1 Steam coal 139.95 Kg 0.00 Per Kg 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Black Smith 0.75 No. 0.00 Per day 0.00


2 Hammer man 0.75 No. 0.00 Per day 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate Per Bend Rs. - Say 0.00

Composite Rate/Bend Rs. - Say 0.00

Page 20
20. Drilling holes in plates upto 1/2" thick per inch dia or part thereof.

Detail Unit Rate per Hole


Rate
Qty Per Unit Amount
Rate Analysis for 40 holes

LABOUR

1 Fitter (Grade I) 0.50 No. 0.00 Per day 0.00


2 Coolies (unskilled) 2.00 No. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per hole Rs. - Say 0.00

Page 21
21. Extra for drilling holes in plates over each 1/2" thick per inch dia or part thereof.

Detail Unit Rate Per Hole


Rate
Qty Per Unit Amount
Rate Analysis for 120 holes

LABOUR

1 Fitter (Grade I) 0.25 No. 0.00 Per day 0.00


2 Coolies (unskilled) 4.00 Nos. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per hole Rs. - Say 0.00

Page 22
22. Riveting 1/8" dia

Detail Unit Rate Per 100 Nos.


Rate
Qty Per Unit Amount
Rate Analysis for 120 Nos.

LABOUR

1 Riveted 0.50 No. 0.00 Per day 0.00


2 Coolies (unskilled) 0.50 No. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate for 100 Nos. Rs. - Say 0.00

Page 23
23. Cutting out rivets, all sizes.

Detail Unit 100 Nos.


Rate
Qty Per Unit Amount
Rate Analysis for 160 Nos.

LABOUR

1 Fitter (Grade II) 2.00 Nos. 0.00 Per day 0.00


2 Hammer man 2.00 Nos. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate for 100 Nos. Rs. - Say 0.00

Page 24
24. Fitting and erection of gutters of sheet iron.

Detail Unit / Lft.


Rate
Qty Per Unit Amount
Rate Analysis for 115 Feet

LABOUR

1 Fitter (Grade II) 1.00 No. 0.00 Per day 0.00


2 Mason 1.00 No. 0.00 Per day 0.00
3 Coolies (Unskilled) 10.00 Nos. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate Per Lft. Rs. - Say 0.00

Labour Rate per RM Rs. - Say 0.00

Page 25
25. Cutting and fixing iron bars for barred windows

Detail Unit / Bar


Rate
Qty Per Unit Amount
Rate Analysis for 35 Bars

LABOUR

1 Fitter (Grade III) 0.50 No. 0.00 Per day 0.00


2 Carpenter 0.50 No. 0.00 Per day 0.00
3 Coolies (Unskilled) 1.00 No. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate Per Bar Rs. - Say 0.00

Page 26
26. Cutting GI sheets.

Detail Unit Rate Per Cut


Rate
Qty Per Unit Amount
Rate Analysis for 65 Cuts
LABOUR

1 Fitter (Grade II) 1.00 No. 0.00 Per day 0.00


2 Hammer man 1.00 No. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per cut Rs. - Say 0.00

Page 27
27. Notching web or foot of rail posts for housing rail beams.

Detail Unit Rate Per Notch


Rate
Qty Per Unit Amount
Rate Analysis for 3 Notches
MATERIAL

1 Steam Coal 28.00 Kg 0.00 Per Kg 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Black Smith 1.0 Nos. 0.00 Per day 0.00


2 Hammer man 1.0 Nos. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE
Labour Rate/Notch Rs. 0.00 Say 0.00

Composite Rate/Notch Rs. - Say 0.00

Page 28
28. Hoop Iron netted trellis work fixed with nails.

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 50 Sft.

LABOUR

1 Fitter (Grade - II) 1.00 No. 0.00 Per day 0.00


2 Coolies (Unskilled) 1.00 No. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00

Labour Rate per Sq.m Rs. - Say 0.00

Page 29
29. Fixing zinc Iron or GI Sheets on table tops.

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 85 Sft.

LABOUR

1 Carpenter 1.00 No. 0.00 Per day 0.00


2 Coolies (Unskilled) 1.00 No. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00

Labour Rate per Sq.m Rs. - Say 0.00

Page 30
30. Making and fixing steel grated doors, complete with locking arrangement, angle iron frame 2"x2"x3
3/4" square bars 4" center to center

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 7' x 4' = 28.00 Sft.
MATERIAL
a)
1 Angle Iron frame 2"x2"x3/8"
vertical 4x7 28 Rft
Top rail 2 x 4'-0" 8 Rft
Bottom & central rail 8 Rft.
44 Rft. 90.44 Kg.
2 Grating("x") = 9x7'-0" = 63 Rft. @ 53.74 Kg.
3 Gusset Plate (" thick)
8x6"x3" 1.0 0 Sft.
4x8"x3" 0.67 Sft.
1.67 Sf 7.58 Kg.
Total 151.76
Wastage 7.59
Total 159.35 Kg. 0.00 Per Kg. 0.00

b Hold fast with pivot and fixed 6.00 Nos. 0.00 Each 0.00
c Locking arrangement with sliding bolt 1 long
and 1" dia 1.00 No. 0.00 Each 0.00
d Coal 15.00 Kg. 0.00 Per Kg. 0.00
e Rivets and bolts 2.27 Kg. 0.00 Per Kg. 0.00
f Steel 1.13 Kg. 0.00 Per Kg. 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR

1 Black Smith 2.0 Nos. 0.00 Per day 0.00


2 Hammer man 3.0 Nos. 0.00 Per day 0.00
3 Blowman 2.0 Nos. 0.00 Per day 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00


Composite Rate per Sft. Rs. 0.00 Say 0.00

Labour Rate per Sq.m Rs. 0.00 Say 0.00


Composite Rate per Sq.m Rs. 0.00 Say 0.00

Page 31
31. Making and fixing steel grated door with 1/16" thick sheeting including angle iron frame
2"x2"x3/8" and 3/4" square bars 4" center to center with locking arrangement.

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 7'x4' = 28 Sft.

MATERIAL

1 As per Item No. 30 (a) to (f)


2 M.S. sheet 1/16" , 7x4= 28 Sft.
Wastage @ 5% 1.4 Sft
29.40 S 33.35 Kg. Per Kg.
@ lb/Sft.
Total
Contractor's Profit & O 20.00 Percent
Total

LABOUR

1 Black Smith 2.25 Nos. Per day


2 Hammer man 3.00 Nos. Per day
3 Blowman 2.00 Nos. Per day

Total
Sundries 10.00 Percent
Total
Contractor's Profit & O 20.00 Percent
Total
Say

ITEM RATE

Labour Rate/Sft. Rs. Say


Composite Rate per Sft. Rs. Say

Labour Rate Per Sq.m Rs. Say


Composite Rate per Sq.m Rs. Say

Page 32
32. Making and fixing grating in opening, including fixing at site with flat iron 2"x3/8" and 3/4"
square bars at 4" cetnre to center.

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 5'x8' = 40 Sft.
MATERIAL

1 Steel
a Frame 2" x 3/8"
3 x 6' = 18 Rft. @ 2.51 lb/Rft. = 45 lb 20.50 Kg.
b Grating 3/4"x3/4" 14x 8' = 112 Rft. @ 1.88 lb/ft.
= 210.5 95.54 Kg.
Total 116.04
Wastage @ 5% 5.80 Kg.
Total 121.84 Kg. 0.00 Per Kg. 0.00

2 Coal 1.40 Kg. 0.00 Per Kg. 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Black Smith 1.25 Nos. 0.00 Per day 0.00


2 Hammer man 1.25 Nos. 0.00 Per day 0.00
3 Blowman 1.50 Nos. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate/Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. 0.00 Say 0.00

Labour Rate per Sq.m Rs. 0.00 Say 0.00


Composite Rate per Sq.m Rs. 0.00 Say 0.00

Page 33
33. Providing and fixing stair railing (all types and designs) of hard wood, including bends
and corners, screwed to 5/8"x5/8" M.S. square bars 2.75 ft. high, at 5.5 inch center to
center, fixed in steps of stairs, M.S. flat 1"x1/8" welded to bars, painting/polishing 3 coats,
etc. complete.

Detail Unit Rate Per Rft.


Rate
Qty Per Unit Amount
Rate Analysis for 10 Rft.
MATERIAL

1 Wooden railing 10 Rft. 0.00 Per Rft. 0.00


2 M.S. flat 1"x1/8" 10 Rft. @ 0.42 LB/ft. =10x0 1.91 Kg. 0.00 Per Kg. 0.00
= 4.2 lbs/ft.
3 M.S. square bars (5/8"x5/8") 11x2 = 22 Nos x 3
=66 ft. @ 1.33 lbs/ft. 39.83 Kg. 0.00 Per Kg. 0.00
4 Painting 0.045 Gallon 0.00 Gallon 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Cutting 5/8" square bars. 22 cuts 0.00 per cut 0.00


2 Cutting flat iron 2 Nos. cuts 2 cuts 0.00 Per cut 0.00
3 Welding bar with M.S. flat 22 Nos. 22 Nos 0.00 per No. 0.00
4 Drilling holes in stone or masonry 22 Nos 0.00 per hole 0.00
5 Mason 0.75 No. 0.00 per day 0.00
6 Cooly (Unskilled) 1.0 No. 0.00 per day 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate/Rft. Rs. 0.00 Say 0.00


Composite Rate/Rft. Rs. - Say 0.00

Labour Rate per Rm Rs. 0.00 Say 0.00


Composite Rate per Rm Rs. 0.00 Say 0.00

Page 34
34. Providing/fixing stair railing consisting of M.S. Box section size 1-1/2"x3" of 16 SWG
welded with M.S. flat 1"x1/8" continuously and welded over M.S. square bars 5/8"x5/8"
punched in M.S. flat 2 ' high @ 5" c/c fixed in steps of stair I/C painting 3 coats
complete.

Detail Unit Rate Per Rft.


Rate
Qty Per Unit Amount

MATERIAL

1 Rate of stair railing with hard wood hand railing


(Item No. 33) Rate/ft. #####
Less: rate of shisham wood railing #####
(No. 31 (a) wood work ##### Per Rft.
Providing fixing M.S. Box section of 16 SWG
1"x3" for hand rail 1.00 Rft.
Add 5% wastage 0.05
1.05 Rft. 0.00 Per Rft.
Painting 3 coats (Item 5d i & ii Painting) 0.62 Sft. 0.00 Per Sft.
including Contractor Profit 54.73+72.6 Say 1.3
100
Contractor's Profit & O 20.00 Percent 0.00
Total
LABOUR

1 Stair railing Rs. 83.95


Less shisham wood rail Rs. 40.70
(Ref. 28 (a) (wood) Rs. 43. 1.00 Rft. Per Rft.
2 Labour for painting (Ref. as above) 0.62 Sft. Per Sft.
3 Making/fixing M.S. box section to required
shape i/c bends/corners welding i/c cost of 1.00 Rft. Per Rft.
welding rod.
Total
Sundries 10.00 Percent 0.00
Contractor's Profit & O 20.00 Percent
at Rs. (6.40+0.64) = 0.00
Total

ITEM RATE

Labour Rate/Rft. Rs. Say


Composite Rate/Rft. Rs. Say

Labour Rate/ RM Rs. Say


Composite Rate/RM Rs. Say

Page 35
35. Providing and fixing terrace railing of 2" i/d conduit pipe 16 SWG welded with 5/8"x5/8"
square bars 2.75 ft. high fixed at 5" center to center in reinforced cement concrete slab
with suitable arrangement, complete in all respects as per design and drawing.

Detail Unit Rate Per Rft.


Rate
Qty Per Unit Amount
Rate Analysis for 10 Rft.
MATERIAL

1 Conduit pipe including specials 10 Rft. 0.00 Per ft. 0.00


2 M.S. square bars 5/8"x5/8" @5" c/c =22x3 =66' 39.83 Kg. 0.00 Per Kg. 0.00
@ 1.33 lb/ft. = 87.78 lbs (39.83 Kg)
3 M.S. flat iron 1"x1/8"=10 ft. @ 0.42 LB/ft. =4 1.91 Kg. 0.00 Per Kg. 0.00
(1.91 Kg.)
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Cutting 5/8" square bars 22 Nos. 0.00 per cut 0.00


2 Welding square bar with conduit pipe 22 Nos. 0.00 per No. 0.00
3 Drilling hole 22x3 = 66 Nos. 66 Nos. 0.00 per hole 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate Rft. Rs. 0.00 Say 0.00


Composite Rate/Rft. Rs. - Say 0.00

Labour Rate per RM Rs. 0.00 Say 0.00


Composite Rate per RM Rs. 0.00 Say 0.00

Page 36
36. Providing and fixing collapsible gate made of 2"x2"x1/4" tee iron at top and bottom,
channel iron vertical 3/4"x1/4"x1/4"x1/8" at 3" to 5" center to center (Approximately) and flat
iron crosses 3"x3/16" and best quality rollers at bottom of 3" dia meter including holdfast,
handles 12" long of 3/4"x1/4"x1/4"x 1/8" channel iron, locking arrangement inside and out
side, painting 3 coats of black Japan enameled, complete in working order.

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 7'x10' = 75 Sft.
MATERIAL

i) Top and bottom tee 2"x2"x1/4", 2x8'=16 Rft


@ 3.2 Lbs/ft. = 51.20 lbs or 23.23 Kg. 23.23 Kg.
ii) Vertical channels 3"x1/4"x1/4"x1/8"
24x2x10' = 480 Rft.
Wastage @ 5% 24 Rft.
Total 504 Rf 128.06 Kg.
@ 0.56 lb per ft. = 282.24 lbs
iii) Flat iron 3/4"x3/16 crosses
12" long 4x4x1' = 16 Rft.
24" long 46x4x2' = 368 Rft.
384 Rft.
wastage @ 5% 19.20 Rft. 91.47 Kg.
403.20 Rft. @ 0.50 lb/ft.=201.60 lbs
Total 242.76 Kg. 0.00 Per Kg. 0.00

iv) 3" diameter rollers 6.00 Nos. 0.00 Nos. 0.00


v) Rivets with heads 2" long 11x24= 264 No. 264.00 0.00 Each 0.00
vi) Rivets 1" long 4x2x24 = 192 Nos 192.00 0.00 Each 0.00
vii) Handles 12" long 3/4"x1/4" channels inside
and outside 2.00 Nos. 0.00 Each 0.00
viii) Locking arrangement in & outside 2.00 Nos. 0.00 Each 0.00
ix) Holdfast 8.00 Nos. 0.00 Each 0.00
x) Cement 0.480 Cft. 0.00 P. Bag 0.00
Sand 1.30 Cft. 0.00 Per % Cft. 0.00
Bajri 2.450 Cft. Per % Cft. 0.00
xi) Painting 3 coats Qty. gallon 0.50 gln. 0.00 gln 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

Page 37
Detail Unit Rate Per Sft.
Rate
Qty Per Unit Amount

LABOUR

1 Black Smith 6 Nos 0.00 0.00


2 Coolies (Skilled) 12 Nos 0.00 0.00
3 Coolies (Unskilled) 6 Nos 0.00 0.00
4 Mason 0.50 No. 0.00 0.00
5 Coolies 1.50 No. 0.00 0.00
6 Painter 0.33 No. 0.00 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate/ Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. 0.00 Say 0.00

Labour Rate per Sq.m Rs. 0.00 Say 0.00


Composite Rate per Sq.m Rs. 0.00 Say 0.00

Page 38
37. Providing and fixing 24 SWG GI sheet rolling shutter, consisting of steel frame of M.S.
channel 2"x1"x1/8", angle iron 1"x1"x1/8", M.S. plat 1'x1'x1/8", GI pipe 1" dia, spring
2' center to center, rollers, 24 SWG, GI covering 1'x1', handles, holdfast & painting three
coats, complete in all respects.

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis shutter size 8'x9' = 72' Sft.
MATERIAL

1 M.S. channels 2"x1"x1/8"


Frame sides 2 Nos x 9' 18.00 Rft.
wastage @ 5% 0.9 Rft.
18.9 Rf 19.21 Kg. 0.00 Per Kg. 0.00
lbs/ft.
2 M.S. plate 1'x1'x1/8"
2 Nos x 1 x 1 2.00 Sft
wastage @ 5% 0.10 Sft
2.10 S 4.86 Kg. 0.00 Per Kg. 0.00
@ 5.10 lbs/Sft.
3 Angle Iron 1"x1"x1/8"
Bottom side 7'-10" 7.83 Rft.
wastage @ 5% 0.39 Rft.
8.22 R 4.59 Kg. 0.00 Per Kg. 0.00
@ 1.23 lbs/ft.
4 GI sheet 24 SWG
i) For shutter 1x7.83x9 = 70.47 Rft.
ii) For box 1x8x3.25 = 26.00 Rft.
iii) For covering plate = 2.00 Sft.
98.47 Sft.
Over lap 10% 9.85 Rft..
108.32 Sft.
Wastage 5% 5.41 Sft.
113.73 Sft.
@ 1.112 57.38 Kg. 0.00 Per Kg. 0.00
5 GI bracket 2.00 Nos. 0.00 Each 0.00

6 GI Holdfast 6.00 Nos. 0.00 Each 0.00

7 GI Pipe 1" dia:-


Pipe 8.00 Rft.
wastage 5% 0.40 Rft.
8.40 R 8.40 Rft. 0.00 Per Rft. 0.00

8 Handle 2 Nos 2.00 Nos. 0.00 Each 0.00

9 GI spring 2.00 Nos. 0.00 Each 0.00

10 Rolling gear 3 Nos. 3.00 Nos. 0.00 Each 0.00

11 Making (holes/khuda) 2.00 Nos. 0.00 Each 0.00

12 Rivets 0.86 Kg. 0.00 P. Kg. 0.00

13 Greasing 0.80 Kg. 0.00 P. Kg. 0.00

14 Cement Page 39 0.212 Cft. 0.00 P. Bag 0.00


15 Sand 0.50 Cft. 0.00 Per % Cft. 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Black Smith 2.50 Nos 0.00 0.00


2 Coolies (Skilled) 1.50 Nos 0.00 0.00
3 Coolies (Unskilled) 1.00 Nos 0.00 0.00
4 Mason 0.50 No. 0.00 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATES

Labour Rate/ Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. 0.00 Say 0.00

Labour Rate per Sq.m Rs. 0.00 Say 0.00


Composite Rate per Sq.m Rs. 0.00 Say 0.00

Page 40
38. Providing and fixing M.S. angle iron 1"x1"x" edge protector nozing of steps of stairs,
having holdfast of 3/8" dia M.S. bars 8" long welded at 2' center to center and embedded
in cement concrete on steps complete in all respects.

Detail Unit Rate Per Rft.


Rate
Qty Per Unit Amount
Rate Analysis for one step = 4 ft. long
MATERIAL

1 Angle Iron 1"x1"x" 4.00 Rft.


wastage 5% 0.20 Rft.
4.20 R 9.74 Lbs or
@ 2.32 lb/ft. 4.42 Kg. 0.00 Per Kg. 0.00

2 Holdfast 3/8" dia 3.00 Nos. 0.00 Each 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Welding charges of angle iron 4.00 No.weld 0.00 Each weld 0.00
2 Fixing charge 0.00 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per foot Rs. 0.00 Say 0.00


Composite Rate / Foot. Rs. - Say 0.00

Labour Rate per RM Rs. 0.00 Say 0.00


Composite Rate per RM Rs. 0.00 Say 0.00

Page 41
39. Providing and fixing stair railing of 2' i/d GI pipe, welded with 5/8"x5/8" square M.S.
bars 2'-9" high, fixed in each step, complete in all respects, including painting, polishing
three coats.

Detail Unit Rate Per Rft.


Rate
Qty Per Unit Amount
Rate Analysis for 10 Rft.
MATERIAL

1 GI pipe 2" dia 1.00 Rft.


wastage 5% 0.50 Rft.
10.50 10.50 Rft. 0.00 ft. 0.00
(Medium Quanlity)
2 M.S. flat 2"x1/8" 10.00 Rft.
wastage 5% 0.50 Rft.
10.50 3.90 Kg. 0.00 Per Kg. 0.00
@ 0.82 lbs/ft.
3 M.S. square bars 5/8"x5/8"
1x13x2.75 35.75 Rft.
wastage 5% 3.58 Rft.
39.33 Rft.
@ 1.33 23.73 Kg. 0.00 Per Kg. 0.00
4 Paint for 3 coats 0.089 Gallon 0.00 Gallon 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Black smith 0.50 No. 0.00 Per day 0.00


2 Mason 0.50 No. 0.00 Per day 0.00
3 Coolies (Unskilled) 0.75 No. 0.00 Per day 0.00
4 Welding GI pipe with M.S. flat 2"x1/8", 10' lo 10.00 Long 0.00 Each 0.00
5 Welding M.S. square bars with M.S. flat 13.00 Nos. 0.00 Each 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Rft Rs. 0.00 Say 0.00


Composite Rate per Rft. Rs. - Say 0.00

Labour Rate per RM Rs. 0.00 Say 0.00


Composite Rate per RM Rs. 0.00 Say 0.00

Page 42
40. Providing and fixing galvanized wire gauze 24 SWG 144 mesh per square inch fixed to
steel window, complete in all respects.

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 3'x5' = 15 Sft
MATERIAL

1 G. I. wire gauge 15.00 Sft.


wastage 5% over lap 0.75 Sft.
15.75 15.75 Sft. 0.00 Per Sft. 0.00

2 M.S. flat "x1/16"


4 x 3' 12.00 Rft.
4 No x 5 20.00 Rft.
32.00 Rft.
wastage 5% 1.60 Rft.
33.60 1.61 Kg. 0.00 Per Kg. 0.00
per foot = 3.56 lbs/ (1.61 Kg)
3 Machine screws 1/8"x1/2" 5.70 Dozen 0.00 Dozen 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Carpenter /Blacksmith 0.50 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. 0.00 Say 0.00

Labour Rate per Sq.m Rs. 0.00 Say 0.00


Composite Rate per Sq.m Rs. 0.00 Say 0.00

Page 43
41. Providing and fixing steel windows with openable glazed panels, using beam section for
frame 1"1x5/8"x1/8" Z section for beams 3/4"x1"x3/4"x1/8", T section sashes 1"x1"x1/8"
glass panes, wooden screeds for glazing, embedded over a thin layer of putty duly
screwed with beams, brass fittings, holdfast, duly painted, complete in all respects,
including all costs of material and labour, etc., as per approved design and as directed by the En

a) Without Wire Gauze

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 6' x 4' = 24 Sft.
MATERIAL (without glass panes)

1 Beam section 1"x1"x5/8"x1/8"


Horizontal 2x6' = 12.00 Rft.
vertical 5x4' = 20.00 Rft.
32.00 Rft.
wastage 5% 1.60 Rft
33.60 18.60 Kg. 0.00 Per Kg. 0.00
@ 1.22 lb/ft
2 Z-section "x1"x"x1/8"
Horizontal 8x1'-5" = 11.67 Rft.
vertical 8x3'-11" = 31'-8" 43.33 Rft
Add wastage 5% 2.16 Rft.
45.49 19.81 Kg. 0.00 Per Kg. 0.00
@ 0.96 lb/ft.
3 T-section 1"x1"x1/8"
Horizontal 8x 1-5" 11.66 Rft.
Add wastage 5% 0.59 Rft.
12.25 4.44 Kg. 0.00 Per Kg. 0.00
@ 0.798 lb/ft.
4 Iron holdfast 6.00 Nos. 0.00 Each 0.00

5 Window hinges 1/4" thick with 5/16 dia pins 8.00 Nos 0.00 Each 0.00

6 Brass casement handle 6" with screwing flat and


catching hook 4.00 Nos. 0.00 Each 0.00

7 Mild steel casement stay 15" long with gap flats


and catching pins 4.00 Nos. 0.00 Each 0.00

8 Wooden strips for fixing glass pans 68.00 Rft. 0.00 Per Rft. 0.00

9 96 Nos steel glazing clips for fixing glass panes in


position before applying putty 96.00 Nos. 0.00 Each 0.00
Total Rs. 0.00

Page 44
41 a (i) Using Glass Pans 2 mm thick
Material as per item No. 41 (a) above 1333.90
Cost of glass 2 mm thick 24.00 Sft. 0.00 Per Sft. 0.00
Total 1333.90
Contractor's Profit & O 20.00 Percent 266.78
Total 1600.68

LABOUR

1 Labour for 24 Sft. for fabrication, welding and


fixing fixtures 42 welds including grinding to 42.00 0.00 per weld 0.00
smoothern the surface.

2 Labour for 24 Sft. for fixing 12 Nos. glass pa 24.00 Sft. 0.00 Per Sft. 0.00
position by fixing 96 Nos. glazing clips in
position and then applying wooden strips

3 One job labour for fixing in position 0.00 0.00

4 Painting 24 Sft. 24.00 Sft. 0.00 Per Sft. 0.00

5 Carriage to site of work L.S. 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. 66.70 Say 66.70

Labour Rate per Sq.m Rs. -0.05 Say 0.00


Composite Rate per Sq.m Rs. 717.64 Say 717.65

Page 45
41 a (ii Using 2.5 mm thick glass of Panes

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 24 Sft.
MATERIAL

1 Same as per item No: 41 (a) 0.00


2 Cost of 2.5 mm glass panes 24.00 Sft. 0.00 Per Sft. 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR

1 Same as per item No. 41 a (i) 0.00

Total 0.00

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. 0.00 Say 0.00

Labour Rate per Sq.m Rs. -0.05 Say 0.00


Composite Rate per Sq.m Rs. 0.00 Say 0.00

Page 46
41 a (i Using 3 mm thick glass panes

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 6' x 4' = 24 Sft.
MATERIAL

1 Same as per item No: 41 (a) 0.00


(excluding cost of glass panes)
2 Cost of 3 mm thick glass 24.00 Sft. 0.00 Per Sft. 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

Same as per item No. 41 a (i) 0.01

Total 0.01

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. 0.00 Say 0.00

Labour Rate per Sq.m Rs. -0.05 Say 0.00


Composite Rate per Sq.m Rs. 0.00 Say 0.00

Page 47
41 a (ivUsing 4 mm thick glass panes

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 6' x 4' = 24 Sft.
MATERIAL

1 Same as per item No: 41 (a) 0.00


excluding cost of glass
2 Cost of 4 mm thick glass 24.00 Sft. 0.00 Per Sft. 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

Same as per item No. 41 a (i) 0.01

Total 0.01

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. 0.00 Say 0.00

Labour Rate per Sq.m Rs. 0.00 Say 0.00


Composite Rate per Sq.m Rs. 0.00 Say 0.00

Page 48
41 a (v Using 5 mm thick glass panes

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 6'x4' = 24 Sft.
MATERIAL

1 Same as per item No: 40 (a) 0.00


excluding cost of glass
2 Cost of 5 mm thick glass panes 24.00 Sft. 0.00 Per Sft. 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

Same as per item No. 40 a(i) 0.01

Total 0.01

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. 0.00 Say 0.00

Labour Rate per Sq.m Rs. -0.05 Say 0.00


Composite Rate per Sq.m Rs. 0.00 Say 0.00

Page 49
41 - b Fixed with Wire Gauze 22 SWG.

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 6' x 4' = 24 Sft.
MATERIAL

1 Beam section 1"1"x5/8"1/8"


Horizontal 2x6 12.00 Rft
Vertical 5x4 20.00 Rft.
Total 32.00 Rft.
Wastage 5% 1.60 Rft.
Total 33.60 Rft.
@ 1.22 18.60 Kg. 0.00 Kg 0.00
2 Z-section "x1"x"x1/8"
Horizontal 8'x1-5" 11.67 Rft.
Vertical 8x3'-11" 31.67 Rft.
Total 43.33 Rft.
Wastage 5% 2.16 Rft.
Total 45.49 Rft.
@ 0.96 19.81 Kg. 0.00 Per Kg. 0.00
3 T-section 1"x1"x1/8"
Horizontal 8x1-5" 11.66 Rft.
Add 5% wastage 0.59 Rft.
12.25 Rft.
@ 0798 4.44 Kg. 0.00 Per Kg. 0.00
4 Wire gauze 24x12 mesh
1x6'x4' 24.00 Sft.
Add wastage 5% 2.40 Sft.
Total 26.40 26.40 Sft. 0.00 Per Sft. 0.00

5 Flat Iron 3/4"x1/8"


Horizontal 2x6 12 Rft.
Vertical 5x3 1/8" 15.625 Rft.
Total 27.625 Rft.
Add 5% wastage 1.381 Rft
Total 29.006 Rft.
@ 0.32 4.21 Kg. 0.00 Per Kg. 0.00
6 Machine screws "x3/16" (3" apart for fixing
wire gauze)
Horizontal 2x6x12/3 48 Nos
Vertical 5x4x12/3 80 Nos
Total 128 No 13.00 Dozen 0.00 Dozen 0.00

7 Iron holdfast 6.00 Nos. 0.00 Each 0.00

Page 50
8 Window hinges 1/4" thick with 5/16" dia 8.00 Nos 0.00 Each 0.00

9 Mild steel casement handles 6" with screwing 4.00 Nos. 0.00 Each 0.00
flat & catching hook 4 Nos. @ Rs. 4.00 each

10 Mild steel casement, 15" long with gap flat an 4.00 Nos. 0.00 Each 0.00
catch pins

11 Wooden screeds to form the glass panes 68.00 Rft. 0.00 Per Rft. 0.00

12 96 Nos steel glazing clips for fixing glass pa 96.00 Nos. 0.00 Each 0.00
in position before applying putty

Total 0.00

Page 51
41 - b ( Using glass panes 2 mm thick

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 6' x 4' = 24 Sft.
MATERIAL

1 Same as per item No. 41 (b) excluding cost of 0.00


glass.
2 2 mm thick glass panes 24.00 Sft. 0.00 Per Sft. 240.00

Total 240.00
Contractor's Profit & O 20.00 Percent 48.00
Total 288.00

LABOUR

1 Labour for fabrication, welding & fixing 42.00 welds 0.00 per weld 0.00
fixture 42 welds for 24 Sft.

2 Labour for fixing 12 Nos. Glass panes in 24.00 Sft. 0.00 P.Sft 0.00
position by making 128 No. holes & fixing
128 Nos screws

3 Labour for fixing 12 No. glass panes in


position by fixing 96 Nos. glazing clips in position
and then fixing wooden strips with screws 24.00 Sft. 0.00 Per Sft. 0.00

4 Labour for fixing in position 0.00 0.00

5 Painting with black Japan paint i/c cost of pa 24.00 Sft. 0.00 Per Sft. 0.00

6 Carriage to site of work L.S 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE
Labour Rate per Sft Rs. 0.00 Say 0.00
Composite Rate/Sft. Rs. 11.95 Say 11.95

Labour Rate per Sq.m Rs. -0.05 Say 0.00


Composite Rate Sq.m Rs. 128.88 Say 128.90

Page 52
41 - b ( Using 2.5 mm thick glass panes

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 6'x4' = 24 Sft.
MATERIAL

1 Same as per item No. 41 (b) excluding cost of 0.00


glass.
2 2.5 mm thick glass panes 24 Sft. 0.00 Per Sft. 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Labour for fabrication, welding & fixing


fixture, 42 welds for 24 Sft. 42.00 welds 0.00 per weld 0.00

2 Labour for fixing 12 Nos. Glass panes in 24.00 Sft. 0.00 Per Sft. 0.00
position by making 128 No. holes & fixing
128 Nos screws

3 Labour for fixing 12 No. glass panes in


position by fixing 96 Nos. glazing clips in po 24.00 Sft. 0.00 Per Sft. 0.00
and then fixing wooden strips with screws
@ Rs. 0.75 per Sft.

4 Labour for fixing in position 0.00 0.00

5 Painting with black Japan paint i/c cost of pa 24.00 Sft. 0.00 per Sft/ 0.00

6 Carriage to site of work L.S. 0.00 0.00


Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. -0.05 Say 0.00

Labour Rate per Sq.m Rs. -0.05 Say 0.00


Composite Rate per Sq.m Rs. -0.24 Say -0.20

Page 53
41 - b ( Using 3 mm thick glass panes

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 6'x4' = 24 Sft.
MATERIAL

1 Same as per item No. 41 (b) excluding cost of 0.00


glass.
2 3 mm thick glass panes 24.00 Sft. 0.00 Per Sft. 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Labour for fabrication, welding & fixing 42.00 welds 0.00 per weld 0.00
fixture, 42 welds for 24 Sft.

2 Labour for fixing 12 Nos. Glass panes in 24.00 Sft. 0.00 Per Sft. 0.00
position by making 128 No. holes & fixing
128 Nos screws

3 Labour for fixing 12 No. glass panes in 24.00 Sft. 0.00 Per Sft. 0.00
position by fixing 96 Nos. glazing clips in position
and then fixing wooden strips with screws
@ Rs. 0.75 per Sft.

4 Labour for fixing in position 0.00 0.00

5 Painting with black Japan paint i/c cost of pa 24.00 Sft, 0.00 Per Sft. 0.00

6 Carriage to site of work L.S. 0.00 0.00


Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. -0.05 Say 0.00

Labour Rate per Sq.m Rs. -0.05 Say 0.00


Composite Rate per Sq.m Rs. -0.29 Say -0.20

Page 54
41 - b ( Using 4 mm thick glass panes

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 6'x4' = 24 Sft.
MATERIAL

1 Same as per item No. 41 (b) excluding cost of 0.00


glass.
2 4 mm thick glass panes 24.00 Sft. 0.00 Per Sft. 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Labour for fabrication, welding & fixing 42.00 Weld 0.00 per weld 0.00
fixture 42 welds for 24 Sft.

2 Labour for fixing 12 Nos. Glass panes in 24.00 Sft 0.00 Per Sft. 0.00
position by making 128 No. holes & fixing
128 Nos screws

3 Labour for fixing 12 No glass panes in 24.00 Sft. 0.00 Per Sft. 0.00
position by fixing 96 Nos. glazing clips in position
and then fixing wooden strips with screws
@ Rs. 0.75 per Sft.

4 Labour for fixing in position 0.00 0.00

5 Painting with black Japan paint i/c cost of pa 24.00 Sft. 0.00 Per Sft. 0.00

6 Carriage to site of work L.S. 0.00 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. -0.05 Say 0.00

Labour Rate per Sq.m Rs. -0.05 Say 0.00


Composite Rate per Sq.m Rs. -0.24 Say -0.20

Page 55
41 - b (vUsing 5 mm thick glass panes

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount

Rate Analysis for 6'x4' = 24 Sft.


MATERIAL

1 Same as per item No. 41 (b) excluding cost of 0.00


glass.
2 5 mm thick glass panes 24.00 Sft. 0.00 Per Sft. 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Labour for fabrication, welding & fixing 42.00 Weld 0.00 per weld 0.00
fixture, 42 welds for 24 Sft.

2 Labour for fixing 12 Nos. Glass panes in 24.00 Sft 0.00 Per Sft. 0.00
position by making 128 No. holes & fixing
128 Nos screws

3 Labour for fixing 12 No glass panes in 24.00 Sft. 0.00 Per Sft. 0.00
position by fixing 96 Nos. glazing clips in position
and then fixing wooden strips with screws

4 Labour for fixing in position 0.00 0.00

5 Painting with black Japan paint i/c cost of pa 24.00 Sft. 0.00 Per Sft. 0.00

6 Carriage to site of work L.S. 0.00 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. -0.05 Say 0.00

Labour Rate per Sq.m Rs. -0.05 Say 0.00


Composite Rate per Sq.m Rs. -0.29 Say -0.20

Page 56
42. Providing and fixing steel windows using M.S. sheet (16 SWG) moulded tubuler pipe
1"x1" for frame and 1"x1" for leaves including M.S. Square bars "x" welded around
each panel of frame, 5 mm thick glass panes fixed with double M.S. square tubular pipe
3/8"x3/8" (22 SWG) beading with 'U' shapped rubber lining, brass fitting, holdfast,
including painting three coats complete in all respects.

a) For openable pannels fixed with wire gauze 24 SWG, 12x12 mesh and glass panes 5 mm
thick

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 6'x6'=36 Sft.
MATERIAL
1 M.S. moulded tubular pipe of 18 SWG
1"x1"
a) Beam for frame
Horizontal 3x6' 18.00 Rft.
Vertical 4x5'-7" 22.50 Rft.
40.50 Rft.
Wastage 5% 2.02 Rft.
42.52 19.29 Kg. 0.00 Per Kg. 0.00
42.52 Rft. @ 1 lb/Rft.
b) Beams for openable pannels 1"x1 "
Upper Portion
i) Horizontal 2x3 x(1'-10") 11.00 Rft.
ii) Vertical 3x2 x(1'-1") 7.00 Rft.

Lower Portion
ii) Horizontal 2x3x (1'-10") 11.00 Rft.
iv) Vertical 3x2 x (4'-1") 24.25 Rft.

c) Hold fast 3x2 (0-6") 3.00 Rft.


56.25 Rft.
Add 5% wastage 2.81 Rft.
59.06 22.51 Kg. 0.00 Per Kg. 0.00
@ 0.84 lb/ft.
2 M.S. square beading 3/8"x3/8" tubuler pipe all
around the glass pannels
Upper Portion
i) Horizontal 2x3x (1'-7") 9.75 Rft.
ii) Vertical 3x2 x (1'-1") 6.62 Rft.

Lower Portion
ii) Horizontal 2x3 x(1'-7") 9.75 Rft.
iv) Vertical 3x2 x (3'-11") 23.87 Rft.
50.00 Rft.
For both sides 50x2 = 100 Rft.
Add 5% wastage 5 Rft.
@ 0.478 lb/ft. 105 Rf 22.77 Kg. 0.00 Per Kg. 0.00

3 M.S. square bars "x" fixed all around each


panes.

Page 57
a) Upper Portion
i) Horizontal 2x3x (1'-10") 11.00 Rft.
ii) Vertical 3x2 x (1'-4") 8.00 Rft.

b) Lower Portion
iii) Horizontal 2x3x (1'-10") 11.00 Rft.

iv) Vertical 3x2 x (4'-2") 25.25 Rft.


55.25 Rft.
Add 5% wastage 2.76 Rft.
@ 0.213 lb/ft. 58.00 5.61 Kg. 0.00 Per Kg. 0.00

4 Brass hinges (4" long) 12.00 Nos. 0.00 Each 0.00

5 Brass Handles (4" long) 3.00 Nos. 0.00 Each 0.00

6 5 mm thick glass
3x(1'-7")x(4'-1") 19.70 Sft.
3x(1-7")x(1'-2") 5.68 Sft.
25.38 Sft.
Add 5% wastage 1.25 Sft.
26.63 26.63 Sft. 0.00 Per Sft. 0.00

7 U' shapped rubber linning (" thick) single 50.00 Rft. 0.00per Per Rft 0.00
quality as in item No. 2

8 24 SWG (12x12) mesh wire gauze galvanized 36.00 Sft. 0.00 Per Sft. 0.00

9 Screws 15.00 Dozen 0.00 per Dozen 0.00

10 M.S. flat 3/4"x1/8" for fixing wire gauze


5x6' 30.00 Rft.
4x5'-8" 22.75 Rft.
52.75 Rft.
Add 5% wastage 2.63 Rft.
55.38 7.99 Kg. 0.00per Per Kg. 0.00
@0.318 lb/ft.
11 Painting 3 costs 0.50 gln 0.00 per gln 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
1 Black smith 0.50 No. 0.00 per day 0.00
2 Welder 0.50 No. 0.00 per day 0.00
3 Welding machine on hire basis 0.50 No./day 120.00 per day 60.00
4 Electric charges with electrode L.S 0.00 0.00
5 Painter 0.34 No. 0.00 per day 0.00
6 Glazier 0.50 No. 0.00 per day 0.00
Total
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Labour Rate per Sft. Rs. 0.00 Say 0.00
Composite Rate/Sft. Rs. 0.00 Say 0.00
Labour Rate per Sq.m Rs. 0.00 Say 0.00
Composite Rate per Sq.m Rs. 0.00 Say 0.00

Page 58
42.
b) For fixed pannels without wire gauze

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 6'x6' = 36 Sft.
MATERIAL

1 M.S. moulded tubular pipe of 16 SWG 1"x1"


a) Beam for frame
1 . Horizontal 3x6 18.00 Rft.
2 . Vertical 4x5'-7" 22.50 Rft.
3 . Holdfast 3x2x0.5 3.00 Rft.
43.50 Rft.
Wastage 5% 2.17 Rft.
45.67 Rft.
45.67 Rft. @ 1.33 lb/Rft. = 60.74 lbs = 27.56 27.56 Kg. 0.00 Per Kg. 0.00
2 M.S. square beading of 3/8"x3/8" (22 SWG)
tubular pipe all around the glass pannels
Upper Portion
i) Horizontal 2x3 (1'-10") 11.00 Rft.
ii) Vertical 3x2 (1'-3") 7.85 Rft.

Lower Portion
ii) Horizontal 2x3 (1'-10") 11.00 Rft.
iv) Vertical 3x2 (4'-2") 25.12 Rft.
Total 55 Rft.

For both sides 55x2 = 110.00 Rft.


Add 5% wastage 5.50 Rft.
115.50 7.60 Kg. 0.00per Per Kg. 0.00
@ 0.145 lb/Rft.
3 5 mm thick glass
Upper Portion
3(1'-4") (1'-10") 7.56 Sft.
Lower Portion
3(4'-3") (1'-10") 23.375 Sft.
30.935 Sft.
Add 5% wastage 1.54 Sft.
32.475 32.48 Sft. 0.00 Per Sft. 0.00
Say 32.48 Sft.
4 U-shapped rubber lining (" thick single 55.00 Rft. 0.00per Per Rft 0.00
quantity as per item No. 2

5 Screws (25 mm) for fixing 15.00 Dozen 0.00 per dozen 0.00

6 Painting 3 coats 0.25 gln 0.00 per gln 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Black smith 0.50 No. 0.00 per day 0.00


2 Welder 0.50 No. 0.00 per day 0.00
3 Welding machine on hire basis Page 59 0.50 120.00 60.00
4 Electric charges with electrodes L.S. 0.00
5 Painter 0.25 No. 0.00 per day 0.00
6 Glazier 0.50 No. 0.00 per day 0.00
Total
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. 0.00 Say 0.00

Labour Rate per Sq.m Rs. 0.00 Say 0.00


Composite Rate per Sq.m Rs. 0.00 Say 0.00

Page 60
43. Providing and fixing windows consisting of M.S. Box section frame 2"x1", leaves frame
1-"x1" Box section frame for glazing 3/8"x3/8" using 16 SWG sheet 'U' shaped rubber
supported with 1"x1/8" M.S. flat for fixing 5 mm thick glass panes M.S. box section frame
"x" of 16 SWG for fixing 24 SWG wire gauze on outer side by means of "x1/8" M.S. flat
and screws I/C all C.P. fitting and painting 3 coats complete in all respect.

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Ananysis for 6'x4' = 24 Sft.
MATERIAL

1 M.S. box section frame 1"x2" 16 SWG for


chowkat.

Vertical 2x6' 12.00 Rft.


central side 1x5' 5.75 Rft.
Horizontal wall top
bottom 2x4' 8.00 Rft.
Central 2x1'-13/16 3.63 Rft.
Total 29.375 Rft.
Add 5% wastage 1.468 Rft.
Total 30.343 21.34 Kg. 0.00 Per Kg. 0.00
@ 1.55 lb/ft.
2 M.S. box section for leaf 1'-1"x1" of 16 SWG
Vertical 2x2x4-' 17.00 Rft.
Horizontal 2x2x1 - 3/16' 7.25 Rft.
24.25 Rft.
Leaf for fixed light
Vertical 2x2x1-3/8' 5.50 Rft.
Horizontal 2x2x1-13/16' 7.25 Rft.
37.00 Rft.
Add 5% wastage 1.85 Rft.
Total 38.85 19.74 Kg. 0.00 Per Kg. 0.00
@ 1.12 lb/Rft.
3 M.S. Box section 3/8"x3/8" of 16 SWG for glazing.

for leave 2x2x4-' 17.00 Rft.


Horizontal 2x2x1-13/16 7.25 Rft.
Fan light 2x2x1'-3/8 5.50 Rft.
2x2x1'-13/16 7.25 Rft.
Total 37.00 Rft.
Add 5% wastage 1.85 Rft.
38.85 5.82 Kg. 0.00 Per Kg. 0.00
@ 0.33 lb/Rft.
4 M.S. box section "x" of 16 SWG for fixing wire
gauze
for leave 2x2x4'- 17.00 Rft.
2x2x1'-13/16 7.25 Rft.
for fan light 2x2x1'-3/6 5.50 Rft.
2x2x1'-13/16 7.25 Rft.
Total 37.00 Rft.
Add 5% wastage 1.85 Rft.
Total 38.85 7.93 Kg. 0.00 Per Kg. 0.00
@ 0.45 lb/Rft.
5 M.S. flat 1"x1/8" for fixing glazing.
for leaves 2x2x4-' 17.00 Rft.
2x2x1'-13/16 7.25 Rft.
for fixed glazing 2x2x1'-3/8 5.50 Rft.
2x2x1'-13/16 7.25 Rft.
Total 37.00 Rft.
Add 5% wastage Page
1.8561 Rft.
Total 38.85 7.47 Kg. 0.00per Per Kg. 0.00
@ 0.424 lb/ft.
6 M.S. flat for wire gauze "x1/8"
side 2x6' 12.00 Rft.
central 2x6' 12.00 Rft.
horizontal 2x4x1'-13/16 14.50 Rft.
38.50 Rft.
Add 5% wastage 1.93 Rft.
Total 40.43 5.83 kg. 0.00 Per Kg. 0.00
@ 0.318 lb/ft.
7 Holdfast of angle iron (1-"x1")x1/8" 2.59 Kg. 0.00 Per Kg. 0.00
6x' = 4.50 Rft. @ 1.27 lb/Rft.

8 G.I. wire gauze 24 SWG 12x12 meshes


2x4-'x1-13/16' 15.40 Sft.
2x1-3/8'x1-13/16' 4.98 Sft.
Total 20.38 Sft.
Add 10% wastage 2.04 Sft.
22.42 22.42 Sft. 0.00 Per Sft. 0.00

9 Glazing with glass panes 5 mm thick


2x4-1/6'x1-' 14.52 Sft.
2x1-1/3'x1-3/4' 4.66 Sft.
Total 19.18 Sft.
Add 10% wastage 1.92 Sft.
21.10 21.10 Sft. 0.00 Per Sft. 0.00

10 U' shape rubber


2x2x4-' 17.00 Rft.
2x2x1-13/16' 7.25 Rft.
2x2x1-3/8' 5.50 Rft.
2x2x1-13/16' 7.25 Rft.
Total 37.00 Rft.
Add 10% wastage 3.70 Rft.
Total 40.70 40.70 Rft. 0.00 Per Rft. 0.00

11 Machine screws 91.00 Nos. 0.00 per dozen 0.00

12 M.S. hinges special type 3x2 (100 mm long) 6.00 Nos. 0.00 Each 0.00

13 C.P. tower bolt (225 mm long) 2.00 Nos. 0.00 Each 0.00

14 Brass handle special type 2.00 Nos. 0.00 Each 0.00

15 G.I. stay 2.00 Nos. 0.00 Each 0.00

16 PCC 1:2:4 for fixing holdfast 64.00 L.S. 64.00

17 Paint 0.50 gln 0.00 per gln 0.00

Total
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Black smith 0.34 No. 0.00 per day 0.00


2 Welder 0.34 No. 0.00 per day 0.00
3 Welding machine on hire basis for day 0.34 day 0.00 per day 0.00
4 Electrode Page 62 L.S
5 Fixer (glass panes) (Glazier) 0.50 No. 0.00 per day 0.00
6 Painter 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. Say 0.00

Labour Rate per Sq.m Rs. Say 0.00


Composite Rate per Sq.m Rs. Say 0.00

Page 63
44. Providing and fixing windows consisting of M.S. Box section frames 2"1" leaves frame
1"1" box section frame for glazing 3/8"x3/8" using 16 SWG sheet 'U' shaped rubber
supported with 1"x1/8" M.S. flat for fixing 5 mm thick glass panes M.S. box section frame
"x" of 16 SWG for fixing 24 SWG wire gauze on outer side by means of "x1/8" M.S. flat
and screws including grill of M.S. flat "x1/8" or "x" square bar with independent frame
of "x" box section of 16 SWG i/c all C.P. fitting and painting 3 coats complete in all
respect.

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for 6'x4' = 24 Sft.
MATERIAL

1 M.S. box section frame 1"x2" 16 SWG for


chowkat.

Vertical side 2x6' 12.00 Rft.


central side 1x5'- 5.75 Rft.
Horizontal top
bottom 2x4' 8.00 Rft.
Central 2x1'-13/16 3.63 Rft.
Total 29.375 Rft.
Add 5% wastae 1.468 Rft.
Total 30.343 21.34 Kg. 0.00per Per Kg. 0.00
@ 1.55 lb/ft.
2 M.S. box section for leaf 1"x1" of 16 SWG

Vertical 2x2x4'- 17.00 Rft.


Horizontal 2x2x1 - 13/16' 7.25 Rft.
24.25 Rft.
Leaf for fixed light
Vertical 2x2x1-3/8' 5.50 Rft.
Horizontal 2x2x1'-13/16 7.25 Rft.
37.00 Rft.
Add 5% wastage 1.85 Rft.
Total 38.85 19.74 Kg. 0.00per Per Kg. 0.00
@ 1.12 lb/Rft.
3 M.S. Box section 3/8"x3/8" of 16 SWG for glazing.

for leaves 2x2x4'- 17.00 Rft.


Horizontal 2x2x1'-13/16 7.25 Rft.
Fan light 2x2x1'-3/8 5.50 Rft.
2x2x1'-13/16 7.25 Rft.
Total 37.85 Rft.
Add 5% wastage 1.85 Rft.
38.85 5.82 Kg. 0.00per Per Kg. 0.00
@ 0.33 lb/Rft.
4 M.S. box section "x" of 16 SWG for fixing
wire gauge
for leaves 2x2x4-' 17.00 Rft.
2x2x1'-13/16 7.25 Rft.
for fan light 2x2x1'-3/6 5.50 Rft.
2x2x1'-13/16 7.25 Rft.
Total 37.00 Rft.
Add 5% wastage 1.85 Rft.
Total 38.85 7.93 Kg. 0.00per Per Kg. 0.00
@ 0.45 lb/ft. Page 64
5 M.S. flat 1"x1/8" for fixing glazing.
for leave 2x2x4'- 17.00 Rft.
2x2x1'-13/16 7.25 Rft.
for fixed glazing 2x2x1'-3/8 5.50 Rft.
2x2x1'-13/16 7.25 Rft.
Total 37.00 Rft.
Add 5% wastage 1.85 Rft.
Total 38.85 7.47 Kg. 0.00per Per Kg. 0.00
@ 0.424 lb/ft.
6 M.S. flat for wire gauze "x1/8"
side 2x6' 12.00 Rft.
central 2x6' 12.00 Rft.
horizontal 2x4x1'-13/16 14.50 Rft.
38.50 Rft.
Add 5% wastage 1.93 Rft.
Total 40.43 5.83 Kg. 0.00per Per Kg. 0.00
@ 0.318 lb/ft.

7 Holdfast of angle iron 1-"x1" 2.59 Kg. 0.00per Per Kg. 0.00
6x = 4.50 Rft.

8 Porividng fixing M.S. grill "x1/8" M.S. flat


frame without holdfast including painting
2x4 1/6'x1-3/16' 15.09 Sft.
2x1 1/16'x1 13/16' 3.84 Sft.
Total 18.93 18.93 Sft. 0.00 Per Sft. 0.00

9 G.I. wire gauge 24 SWG 12x12 meshes


2x4-'x1-13/16' 15.40 Sft.
2x1-3/8x1-13/16 4.98 Sft.
Total 20.38 Sft.
Add 5% wastage 2.04 Sft.
22.42 22.42 Sft. 0.00 Per Sft. 0.00

10 Glazing with glass panes 5 mm thick


2x4-1/6x1- 14.52 Sft.
2x1-1/3x1-3/4 4.66 Sft.
Total 19.18 Sft.
Add 5% wastage 1.92 Sft.
21.10 21.10 Sft. 0.00 Per Sft. 0.00

Page 65
11 U' shape rubber
2x2x4-' 17.00 Rft.
2x2x1-13/16' 7.25 Rft.
2x2x21-3/8 5.50 Rft.
2x2x1-13/16 7.25 Rft.
Total 37.00 Rft.
Add 5% wastage 3.70 Rft.
Total 40.70 40.70 Rft. 0.00per Per Rft 0.00

12 Machine screws 91.00 Nos. 0.00 per dozen 0.00

13 M.S. hinges special type 3x2 (100 mm long) 6.00 Nos. 0.00 Each 0.00

14 C.P. tower bolt (225 mm long) 2.00 Nos. 0.00 Each 0.00

15 Brass handle special type 2.00 Nos. 0.00 Each 0.00

16 G.I. stay 2.00 Nos. 0.00 Each 0.00

17 Cement 0.250 Cft. 0.00 P. Bag 0.00


Sand 0.60 Cft. 0.00 Per % Cft. 0.00
Bajri 1.200 200.00 100 Cft. 2.40

18 Paint 0.25 gln 0.00 per gln 0.00

Total
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Black smith 0.50 No. 0.00 per day 0.00


2 Welder 0.50 No. 0.00 per day 0.00
3 Welding machine on hire basis for 1 day 0.50 No. 0.00 per day 0.00
4 Electrode 0.427 0.00 P. Bundle 0.00
5 Fixer (glass panes) (Glazier) 0.50 No. 0.00 per day 0.00
6 Painter 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate per Sft. Rs. 0.00 Say 0.00


Composite Rate/Sft. Rs. Say 0.00

Labour Rate per Sq.m Rs. Say 0.00


Composite Rate per Sq.m Rs. Say 0.00

Page 66
45. Flapping G.I. Pipes for bathroom drains

Detail Unit Rate Per Each Job


Rate
Qty Per Unit Amount
Rate Analysis for Each Job
MATERIAL

1 Cost of flaps including hinges Each 0.00 Each 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

Fitter 0.75 No. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate / Each Rs. - Say 0.00


Composite Rate/Each Rs. - Say 0.00

Page 67
46. Supply & Fixing iron grating for fire places

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount
Rate Analysis for Sft.
MATERIAL

1 Cost of grating 1.00 Sft. 0.00 Per Sft. 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Mason 0.10 Nos 0.00 Per day 0.00


2 Cololies (Unskilled) 0.05 Nos. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate /Sft. Rs. 0.00 Say 0.00


Composite Rate per Sft. Rs. 0.00 Say 0.00

Labour Rate per Sq.m Rs. Say 0.00


Composite Rate per Sq.m Rs. 0.00 Say 0.00

Page 68
47. Fixing Copper flashing, including cutting of sheets, grooving and rivetting.

Detail Unit Rate Per Lft.


Rate
Qty Per Unit Amount
Rate Analysis for 30 Lft.

LABOUR

1 Black Smith 1.00 No. 0.00 Per day 0.00


2 Coolies (Unskilled) 1.00 No. 0.00 Per day 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate /Lft. Rs. - Say 0.00


Labour Rate Per Metre Rs. - Say 0.00

Page 69
48. Providing and fixing angle Iron railing, using 2"x2"x3/8" angle iron post 4 foot long, 5' to 6'
2"x2"x3/8" angle iron top rail and two rows of M.S. flat 2"x" including fixing to side of bri
structure with "U" bolt 1' long " dia, painting etc complete in all respects.

Detail Unit Rate Per Rft.


Rate
Qty Per Unit Amount
Rate Analysis for 24 Rft.
MATERIAL

1 Angle Iron post 2"x2"x3/8"


Vertical 5x4' 22.50 Rft.
Horizontal 1x24 24.00 Rft.
46.50 Rft.
Wastage 5% 2.33 Rft.
Total 48.83 132.71 Kg. 0.00 Per Kg. 0.00
@ 5.99 lb/ft.
2 M.S. flat 2"x"
Horizontal 2x 24 48.00 Rft.
wastage 5% 2.40 Rft.
50.40 49.39 Kg. 0.00 Per Kg. 0.00
@ 2.16 lb/Rft.

3 1 ft. long M.S. U-Clamp 3/4" dia threaded at 5 Nos. 0.00 Each 0.00
both ends including nuts complete.

4 Paint for 2 coats 0.056 Litre 0.00 Per Litre 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

LABOUR

1 Welding 15 No . welds 15.00 Nos 0.00 Per weld 0.00


2 Fitter 0.375 No. 0.00 Per day 0.00
3 Coolies (Unskilled) 1.50 Nos. 0.00 per day 0.00
4 Painter 0.125 No. 0.00 per day 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE
Labour Rate /Rft. Rs. - Say 0.00
Composite Rate/Rft. Rs. - Say 0.00

Labour Rate per RM Rs. 0.00 Say 0.00


Composite Rate per RM Rs. 0.00 Say 0.00

Page 70
49. Providing and fixing barbed wire fencing, consisting of 1"x1"3/16" angle iron post 3 ft.
long 5 to 6 ft. centre to centre embedded in cement concrete 1:4:8 base of size 9"x9"12"
and three rows of barbed wire painting posts etc complete in all respects.

Detail Unit Rate Per 100 Rft.


Rate
Qty Per Unit Amount
Rate Analysis for 44 Rft.
MATERIAL

1 Angle Iron 1"x1"x3/16"


9 Nos.x 3.25' 29.25 Rft.
Wastage 5% 1.46 Rft.
Total 30.71 Rft.
@ 1.84 25.64 Kg. 0.00 Per Kg. 0.00
2 Cement Concrete 1:4:8
9x9"x9"x12" 5.06 C 5.06 Cft. 0.00 Cft. 0.00

3 Strained Barbed Wire 3 rows


3'x44 132 .00 Rft
Wastage 5% 6.60 Rft.
138.6 Rft.
@ 1.25 6.52 Kg. 0.00 Kg 0.00
4 Painting small detached articles not
exceeding one Sft. of painted surface, 2 coats 9.00 Nos. 0.00 per No. 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent Item 1 &3 0.00
Total 0.00

LABOUR

1 Cement concrete (1:4:8) 5.06 Cft. 0.00 per Cft. 0.00


2 Fixing barbed wire and angle iron
i) Black smith for wire and angle iron 0.25 No. 0.00 per day 0.00
ii) Coolies (Unskilled) 0.25 No. 0.00 per day 0.00
3 Painting small detached articles not exceeding 9 Nos. 0.00 Each 0.00
1 Sq.ft. area painted surface 2 coats
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE

Labour Rate /100 Rft. Rs. Say 0.00


Composite Rate/100Rft. Rs. Say 0.00

Labour Rate per RM Rs. 0.00 Say 0.00


Composite Rate per RM Rs. Say 0.00

Page 71
50. Providing and fixing barbed wire fencing on compound wall consisting of 1"x1"3/16"
angle iron post 3 ft. long 4 apart embedded in cement concrete 1:4:8 base of size 6"x6"x9"
and 4 rows of barbed wire , including binding wire, painting posts, etc. complete in all
respects.

Detail Unit Rate Per 100 Rft.


Rate
Qty Per Unit Amount
Rate Analysis for 48 Rft.
MATERIAL

1 Angle Iron 1"x1"x3/16"


13 Nos.x 3' 39.00 Rft.
Wastage 5% 3.90 Rft.
Total 42.90 Rft.
@ 1.84 35.81 Kg. 0.00 Per Kg. 0.00
2 Cement Concrete 1:4:8
13"x6"x6"x9" 2.44 C 2.44 Cft. 0.00 Cft. 0.00

3 Strained Barbed Wire 4 rows


4'x48 192 .00 Rft
Wastage 5% 9.60 Rft.
201.60 Rft.
@ 1.25 9.49 Kg. 0.00 Per Kg. 0.00
4 Painting small detached articles not
exceeding one Sft. of painted surface, 2 coats 13.00 Nos. 0.00 per No. 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent 0.00 0.00
Total 0.00

LABOUR

1 Cement concrete (1:4:8) 2.44 Cft. 0.00 per Cft. 0.00


2 Fixing angle iron and barbed wire fencing
i) Black smith 0.70 No. 0.00 per day 0.00
ii) Coolies 0.75 No. 0.00 per day 0.00
3 Painting small detached articles not exceeding 13 Nos. 0.00 Each 0.00
1 Sq.ft. area painting surface 2 coats
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
Say 0.00
ITEM RATE

Labour Rate /100 Rft. Rs. Say 0.00


Composite Rate/100Rft. Rs. Say 0.00
Labour Rate per RM Rs. Say 0.00
Composite Rate per RM Rs. Say 0.00

Page 72
51 Providing and fixing all types of partly fixed and partly openable glazed anodized bronze colour a
delux section of M/s. Al-Cop or Pakistan cables boring showkhat frame of size 40mm x 100mm and lea
x 40mm wide sections i/c the cos tof 5mm thick imported tinted glass with aluminium triangular gol
to support the glass and leaf edgings using approved standard fittings, locks, 3" wide long handle
required as approved by the engineer inchrage (Follow Note Below).

Detail Unit Rate Per 100 Rft.


Rate
Qty Per Unit Amount

MATERIAL 3

a) 1.6 mm thick
Unit = 4 x 10 = 40 Sft.
7
Cost of Material 4'x1"

i) Chowkhat Frame 40mm x 100 mm


13"x6"x6"x9" 4'-0

3 x 4 = 12.00 Rft.
2 x 10 = 20.00 Rft.
1 x 3 3.00 Rft.
Total 35.00 Rft.
Add Wastage 10% 3.50
Total 38.50 Rft. 0.00 Rft 0.00

ii) Leaf Frames Section

40mm x 60mm (1" 2")

4 x 6.75 = 27.00 Rft.


2x2x1.375 = 5.50 Rft.
Total 32.50 Rft.
Add Wastage 10% 3.25
Total 35.75 Rft. 0.00 per No. 0.00

iii) Leaf Edging

4 x 7 = 28.00 Rft.
2 x 4 = 8.00 Rft.
Total 36.00 Rft.
Add Wastage 5% 1.80
Total 37.80 Rft. 0.00 per No. 0.00

iv) Imported tinted glass 5 mm

4 x 10 = 40.00 Sft. 0.00 Sft. 0.00

v) Aluminum tringular gola and gasket

to 4 (2 + 3) = 20.00 Rft.
Leaver 4 x 7 = 28.00 Rft.
4 x 1.375 = 5.50 Rft.
Total 53.50 Rft.
Add Wastage 10% 5.35
Total 58.85 Rft. 0.00 per No. 0.00
Page 73
vi) Pivots 4.00 Nos. 0.00 Each 0.00

vii) Cost of Hardwares L.S 0.00

viii) Long Handle 4 x 2 = 8.00 Rft. 0.00 Rft. 0.00

ix) Lock 1.00 No. 0.00 Each 0.00

x) Aluminium tower bolts 2.00 Nos. 0.00 Each 0.00

Total 0.00
B) Labour

a) Labour Charges

For Manuracturing and Fabrication

Aluminium Technician 2.00 Nos. 0.00 per day 0.00


Carriage Cooly 3.00 Nos. 0.00 per day 0.00
Carriage Charges L.S. 0.00

b) Labour for Fixing the Glass Panes 40.00 Sft. 0.00 Sft. 0.00

Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00

ITEM RATE

Labour Rate /100 Rft. Rs. - Say 0.00

Composite Rate per RM Rs. 0.00 Say 0.00

Note :
i) Increase rate by 20/- P. Sft,. If sections will be of 2mm thickness
ii) Reduce rate by 20/- P. Sft. If sections will be of dull aluminium shade
iii) Reduce rate by 20/- P. Sft if using local pain glass

Page 74
ANALYSIS OF RATE
IRON WORK

52 Providing and fixing all types of glazed aluminium windows of anodized bronze colour partly fixed and
party sliding using deluxe section of M/s. Al-Cop or Pakistan Cables having Frame of size 100mm x
20mm and leaf frame sections of 50mm x 20mm, all of 1.6mm thickness i/c 5mm thick imported
tinted glass with rubber gasket using approved standard latches, hardware etc., as approved by the
engineer incharge.

Unit = 6 x 4.50 = 27.00 Sft. 4'

6'-0
(A) COST OF MATERIAL

a) Frame 100mm x 20mm (4" x ")

2x6 = 12.00 Rft.


2 x 4.50 = 9.00 Rft.
Total 21.00 Rft.
Wastage 10% 2.10 Rft.
Total 23.10 Rft.

@ Rs. 60/- Rs. -

b) Leaf frame sections 50mm x 20mm (2" x ")

4x4 = 12.00 Rft.


2x6 = 12.00 Rft.
Total 24.00 Rft.
Wastage 10% 2.40 Rft.
Total 26.40 Rft.

@ Rs. Rs. -

c) Rubber gasket

4x4 = 16.00 Rft.


2 x 5.25 = 10.50 Rft.
Total 26.50 Rft.
Wastage 10% 2.65 Rft.
Total 29.15 Rft.

@ Rs. Rs. -
Rs. -

B/F Rs. -

d) Cost of hardwares L.S Rs. -

e) Latches of matching
shade 1 No. Rs. -

f) Imported tinted glass Page 75


6 x 4.50 = 27 Sft.
@ Rs. Rs. -

g) Polistevene or polisulphide
for water tight L.S Rs. -
Total Rs. -
Contractor's 20% Prof Rs. -
Total Rs. -

(B) LABOUR

a) For Manufacturing & Fabricating

Aluminium technician 2 Nos. Rs. -


@ Rs.

Cooly 3 Nos. Rs. -


@ Rs.

b) Labour for fixing of glass panes

27 Sft. @ /Sft Rs. -


Total Rs. -
Sundries 10% Rs. -
Total Rs. -
Contractor's 20% Prof Rs. -
Total Rs. -

Notes :

i) Reduce rate by P. Sft if sections will be of 1.2mm thickness.


ii) Reduce rate by P. Sft if dull sections of aluminium will be used.
iii) Reduce rate by P. Sft if local plain glass will be used.

Labour Rate = - P. Sft


27

Composite Rate = - P. Sft


27

Say Rs. - P. Sft

Page 76
S.No. Labour UNIT RATE
LB-001 Chowkidar Per day
LB-002 Gate Keeper Per day
LB-003 Beldar Per day
LB-004 Boatman Per day
LB-005 Bullockman Per day
LB-006 Cartman Per day
LB-007 Camelman Per day
LB-008 Donkeyman Per day
LB-009 Greaser Per day
LB-010 Oiler Per day
LB-011 Punkha Cooly Per day
LB-012 Sweeper Per day
LB-013 Sewerman Per day
LB-014 White Washer Per day
LB-015 Cooly Un-skilled (all types) Per day
LB-016 Waherman Per day
LB-017 Bahishti Per day
LB-018 Chainman Per day
LB-019 Dresser Earthwork Per day
LB-020 Head Khalasi Survey Per day
LB-021 Hammar Man Per day
LB-022 Mali Per day
LB-023 Quarryman Per day
LB-024 Skilled Cooly Per day
LB-025 Tar Sprayer Per day
LB-026 Armature Winder Per day
LB-027 Auto Electric Mechanic Per day
LB-028 Blacksmith Per day
LB-029 Carpenter Per day
LB-030 Caner Per day
LB-031 Chiseler Per day
LB-032 Denter Per day
LB-033 Driller Per day
LB-034 Driver Per day
LB-035 Electrician Per day
LB-036 Furniture Polisher Per day
LB-037 Glazier Per day
LB-038 Instrument Machanic Per day
LB-039 Machine Man Per day
LB-040 Mason Per day
LB-041 Electric Motor Winder Per day
LB-042 Moulder Per day
LB-043 Mechanic Per day
LB-044 Pettern Maker Per day
LB-045 Pipe Fitter Per day
LB-046 Plumber Per day
LB-047 Spray Painter Per day
LB-048 Sawyer Per day
LB-049 Turner Per day
LB-050 Tailor Per day
LB-051 Tin Smith Per day
LB-052 Welder Per day
LB-053 Boatman with large boat Per day
LB-054 Boatman with small boat Per day
LB-055 Bullock (each) (without attendant) Per day
LB-056 Camel (each) (without attendant) Per day
LB-057 Donkey (each) (without attendant) Per day
LB-058 Bullock Cart (without bullock & attendant) Per day
Page 1
LB-059 Camel Cart (without bullock & attendant) Per day
LB-060 Donkey or Mule Cart (without animal & attendant) Per day
LB-061 Helper Per Day
LB-062 Painter Per day
LB-063 Polisher Per day
LB-064 Foreman Per day
LB-065 Mate Per day
LB-066 Diggers Per day
LB-067 Kharkar P.Month
LB-068 Belcha men P.Month
LB-069 Gantiman (with pick axes) P.Month
LB-070 Topalies (men with donkeys for carrying earth) P.Month
LB-071 Langri (Cooks) P.Month
LB-072 Dobashi (man for supervision) P.Month
LB-073 Bullockman with pair of bullocks P.Day
LB-074 Charkhara-man P.Day
LB-075 Aluminum Technician Per Day
LB-076 Riveted Per Day
LB-077 Blowman Per Day
LB-078 Crane operator P.Day
LB-079 Hire charges of cart with Bullock & Bullock man Per Day
LB-080 Diver Sinker Per Day
LB-081 Ploughing Charges P. Acre
LB-082 Carriage Charges of RCC Pipe 4" (Class L) Per Pipe
LB-083 Carriage Charges of RCC Pipe 6" (Class L) Per Pipe
LB-084 Carriage Charges of RCC Pipe 9" (Class L) Per Pipe
LB-085 Testing Charges of RCC Pipes 4" (Class L) Per Pipe
LB-086 Testing Charges of RCC Pipes 6" (Class L) Per Pipe
LB-087 Testing Charges of RCC Pipes 9" (Class L) Per Pipe
LB-088 Carriage Charges of Non-reinforced Concrete Pipe 4"(Class I) Per Pipe
LB-089 Carriage Charges of Non-reinforced Concrete Pipe 6"(Class I) Per Pipe
LB-090 Carriage Charges of Non-reinforced Concrete Pipe 8"(Class I) Per Pipe
LB-091 Carriage Charges of Non-reinforced Concrete Pipe 9"(Class I) Per Pipe
LB-092 Carriage Charges of Non-reinforced Concrete Pipe 10"(Class I) Per Pipe
LB-093 Testing Charges of Non-reinforced Concrete Pipe 4"(Class I) Per Pipe
LB-094 Testing Charges of Non-reinforced Concrete Pipe 6"(Class I) Per Pipe
LB-095 Testing Charges of Non-reinforced Concrete Pipe 8"(Class I) Per Pipe
LB-096 Testing Charges of Non-reinforced Concrete Pipe 9"(Class I) Per Pipe
LB-097 Testing Charges of Non-reinforced Concrete Pipe 10"(Class I) Per Pipe
LB-098 Carriage Charges of RCC Pipe 12" (Class II, III & IV) Per Pipe
LB-099 Carriage Charges of RCC Pipe 15" (Class II, III & IV) Per Pipe
LB-100 Carriage Charges of RCC Pipe 18" (Class II, III & IV) Per Pipe
LB-101 Carriage Charges of RCC Pipe 21" (Class II, III & IV) Per Pipe
LB-102 Carriage Charges of RCC Pipe 24" (Class II, III & IV) Per Pipe
LB-103 Carriage Charges of RCC Pipe 27" (Class II, III & IV) Per Pipe
LB-104 Carriage Charges of RCC Pipe 30" (Class II, III & IV) Per Pipe
LB-105 Carriage Charges of RCC Pipe 33" (Class II, III & IV) Per Pipe
LB-106 Carriage Charges of RCC Pipe 36" (Class II, III & IV) Per Pipe
LB-107 Carriage Charges of RCC Pipe 42" (Class II, III & IV) Per Pipe
LB-108 Carriage Charges of RCC Pipe 48" (Class II, III & IV) Per Pipe
LB-109 Carriage Charges of RCC Pipe 54" (Class II, III & IV) Per Pipe
LB-110 Carriage Charges of RCC Pipe 60" (Class II, III & IV) Per Pipe
LB-111 Carriage Charges of RCC Pipe 66" (Class II, III & IV) Per Pipe
LB-112 Carriage Charges of RCC Pipe 72" (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 12"
LB-113 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 15"
LB-114 (Class II, III & IV) Per Pipe

Page 2
Carriage Charges of Non-reinforced Concrete Pipe 18"
LB-115 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 21"
LB-116 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 24"
LB-117 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 27"
LB-118 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 30"
LB-119 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 33"
LB-120 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 36"
LB-121 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 42"
LB-122 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 48"
LB-123 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 54"
LB-124 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 60"
LB-125 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 66"
LB-126 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 72"
LB-127 (Class II, III & IV) Per Pipe

Page 3
CHAPTER NO. 14

LINING OF CANAL

DESCRIPTION OF ITEM NO 1: Formation, dressing and preparing sub-grade.

a) In Bed.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour
Rate Analyses for 125 Sft
Dresser 0.33 No P. Day -
Unskilled Cooly 0.77 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Sft Rs. Say -

Labour Rate for 1 Sqm Rs. Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

Page 1
Item No. 1 Formation, dressing and preparing sub-grade.

b) On Slope.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour
Rate Analyses for 125 Sft
Dresser 0.50 No P. Day -
Unskilled Cooly 1.00 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Sft Rs. Say -

Labour Rate for 1 Sqm Rs. Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

Page 2
DESCRIPTION OF ITEM NO 2: Stabilized layer of cement sand ratio 1:30 2"
(50mm) thick on slope.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.50 Bag P. Bag -


Sand 18.00 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour
Rate Analyses for 125 Sft
Mason 0.50 No P. Day -
Unskilled Cooly 1.50 No P. Day -
Bahishti 0.50 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Sft Rs. Say -
Labour Rate for 1 Sqm Rs. Say -

Composite Rate for 100 Sft Rs. Say -


Composite Rate for 1 Sqm Rs. Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

Page 3
DESCRIPTION OF ITEM NO 3: Cement plaster " (12mm) thick, ratio 1:10.

a) In Bed.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.34 Bag P. Bag -


Sand 4.20 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour
Rate Analyses for 125 Sft
Mason 0.33 No P. Day -
Unskilled Cooly 1.00 No P. Day -
Bahishti 0.50 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Sft Rs. Say -
Labour Rate for 1 Sqm Rs. Say -

Composite Rate for 100 Sft Rs. Say -


Composite Rate for 1 Sqm Rs. Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

Page 4
Item No. 3 Cement plaster " (12mm) thick, ratio 1:10.

b) On Slope.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.34 Bag P. Bag -


Sand 4.20 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour
Rate Analyses for 125 Sft
Mason 0.50 No P. Day -
Unskilled Cooly 1.25 No P. Day -
Bahishti 0.50 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total

Item Rates
Labour Rate for 100 Sft Rs. Say -
Labour Rate for 1 Sqm Rs. Say -

Composite Rate for 100 Sft Rs. Say -


Composite Rate for 1 Sqm Rs. Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

Page 5
DESCRIPTION OF ITEM NO 4: Cement plaster 3/8"(10mm) thick, ratio 1:3

a) In Bed.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.70 Bag P. Bag -


Sand 2.50 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour
Rate Analyses for 125 Sft
Mason 0.33 No P. Day -
Unskilled Cooly 1.00 No P. Day -
Bahishti 0.50 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Sft Rs. Say -
Labour Rate for 1 Sqm Rs. Say -

Composite Rate for 100 Sft Rs. Say -


Composite Rate for 1 Sqm Rs. Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

Page 6
Item No. 4 Cement plaster 3/8"(10mm) thick, ratio 1:3.

b) On Slope.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.70 Bag Each -


Sand 2.50 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour
Rate Analyses for 125 Sft
Mason 0.50 No P. Day -
Unskilled Cooly 1.25 No P. Day -
Bahishti 0.50 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total

Item Rates
Labour Rate for 100 Sft Rs. Say -
Labour Rate for 1 Sqm Rs. Say -

Composite Rate for 100 Sft Rs. Say -


Composite Rate for 1 Sqm Rs. Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

Page 7
DESCRIPTION OF ITEM NO 5: Cement plaster 1" (40mm) thick, ratio 1:6.

a) In Bed.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 1.56 Bag P. Bag -


Sand 11.70 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour for 125 Sft

Mason 0.50 No P. Day -


Unskilled Cooly 1.25 No P. Day -
Bahishti 0.50 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total

Item Rates
Labour Rate for 100 Sft Rs. Say -
Labour Rate for 1 Sqm Rs. Say -

Composite Rate for 100 Sft Rs. Say -


Composite Rate for 1 Sqm Rs. Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

Page 8
Item No. 5 Cement plaster 1" (40mm) thick, ratio 1:6.

b) On Slope.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 1.56 Bag P. Bag -


Sand 11.70 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour for 125 Sft

Mason 0.75 No P. Day -


Unskilled Cooly 1.50 No P. Day -
Bahishti 0.50 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Sft Rs. Say -
Labour Rate for 1 Sqm Rs. Say -

Composite Rate for 100 Sft Rs. Say -


Composite Rate for 1 Sqm Rs. Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

Page 9
DESCRIPTION OF ITEM NO 6: Tile lining (12"x6"x2") (300x150x50mm) in 1:6
cement sand mortar.

a) In Bed.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
Per
Brick Tiles ###### Nos 1000 Nos
Cement 3.44 Bag P. Bag -
Sand 25.70 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour

Mason 2.50 No -
Unskilled Cooly 5.00 No -
Bahishti 0.75 No -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate for 1 Cum Rs. - Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

The rates are only for laying tiles over 1/8" (6mm) thick layer of 1:6 mortar items 1 to 5
above are payable separately.

Page 10
Item No. 6 Tile lining (12"x6"x2") (300x150x50mm) in 1:6
cement sand mortar.

b) On Slope.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Brick Tiles ###### Nos 1000 Nos


Cement 3.44 Bag P. Bag -
Sand 25.70 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour

Mason 2.75 No P. Day -


Unskilled Cooly 6.00 No P. Day -
Bahishti 0.75 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total

Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate for 1 Cum Rs. - Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

The rates are only for laying tiles over 1/8" (6mm) thick layer of 1:6 mortar items 1 to 5
above are payable separately.

Page 11
DESCRIPTION OF ITEM NO 7: Tile lining (12"x6"x2") (300x150x50mm) in 1:3
cement sand mortar.

a) In Bed.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Brick Tiles ###### Nos 1000 Nos


Cement 6.00 Bag P. Bag -
Sand 22.50 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour

Mason 2.50 No P. Day -


Unskilled Cooly 5.00 No P. Day -
Bahishti 0.75 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate for 1 Cum Rs. - Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

The rates are only for laying tiles over 1/8" (6mm) thick layer of 1:3 mortar items
1 to 5 above are payable separately.

Page 12
Item No. 7 Tile lining (12"x6"x2") (300x150x50mm) in 1:3
cement sand mortar.

b) On Slope.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Brick Tiles ###### Nos 1000 Nos


Cement 6.00 Bag P. Bag -
Sand 22.50 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour

Mason 2.75 No P. Day -


Unskilled Cooly 6.00 No P. Day -
Bahishti 0.75 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total

Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate for 1 Cum Rs. - Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

The rates are only for laying tiles over 1/8" (6mm) thick layer of 1:3 mortar items
1 to 5 above are payable separately.

Page 13
DESCRIPTION OF ITEM 8: Brick lining (9"x4"x3") (225x114x75mm) in
1:6 cement sand mortar.

a) In Bed.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bricks ###### Nos 1000 Nos


Cement 3.44 Bags P. Bag -
Sand 25.70 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour

Mason 2.50 No P. Day -


Unskilled Cooly 5.00 No P. Day -
Bahishti 0.75 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate for 1 Cum Rs. - Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:6 mortar items
1 to 5 above are payable separately.

Page 14
Item No. 8 Brick lining (9"x4"x3") (225x114x75mm) in
1:6 cement sand mortar.

b) On Slope.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bricks ###### Nos 1000 Nos


Cement 3.44 Bags P. Bag -
Sand 25.70 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour

Mason 2.75 No P. Day -


Unskilled Cooly 6.00 No P. Day -
Bahishti 0.75 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate for 1 Cum Rs. - Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:6 mortar items
1 to 5 above are payable separately.

Page 15
DESCRIPTION OF ITEM No 9: Brick lining (9"x4"x3") (225x114x75mm) in
1:3 cement sand mortar.

a) In Bed.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bricks ###### Nos 1000 Nos


Cement 6.00 Bags P. Bag -
Sand 22.50 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour

Mason 2.50 No P. Day -


Unskilled Cooly 5.00 No P. Day -
Bahishti 0.75 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate for 1 Cum Rs. - Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:3 mortar items
1 to 5 above are payable separately.

Page 16
Item No. 9 Brick lining (9"x4"x3") (225x114x75mm) in
1:3 cement sand mortar.

b) On Slope.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bricks ###### Nos 1000 Nos


Cement 6.00 Bags P. Bag -
Sand 22.50 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour

Mason 2.75 No P. Day -


Unskilled Cooly 6.00 No P. Day -
Bahishti 0.75 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate for 1 Cum Rs. - Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:3 mortar items
1 to 5 above are payable separately.

Page 17
DESCRIPTION OF ITEM NO 10: Cement concrete lining, using washed screened
and graded stone aggregate.

a) In Bed.
i) Ratio 1:2:4

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 17.60 Bags P. Bag -


Sand 44.00 Cft Cft -
Aggregate 88.00 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour

Mason 1.00 No P. Day -


Unskilled Cooly 6.00 No P. Day -
Bahishti 0.60 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate for 1 Cum Rs. - Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

Page 18
Item No. 10 Cement concrete lining, using washed screened
and graded stone aggregate.

a) In Bed.
ii) Ratio 1:3:6

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 13.00 Bags P. Bag -


Sand 46.00 Cft Cft -
Aggregate 92.00 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour

Mason 1.00 No P. Day -


Unskilled Cooly 6.00 No P. Day -
Bahishti 0.60 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate for 1 Cum Rs. - Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

Page 19
Item No. 10 Cement concrete lining, using washed screened
and graded stone aggregate.

a) In Bed.
iii) Ratio 1:4:8

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 9.60 Bags P. Bag -


Sand 48.00 Cft Cft -
Aggregate 96.00 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour

Mason 1.00 No P. Day -


Unskilled Cooly 6.00 No P. Day -
Bahishti 0.60 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate for 1 Cum Rs. Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

Page 20
Item No. 10 Cement concrete lining, using washed screened
and graded stone aggregate.

b) On Slope.
i) Ratio 1:2:4

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 17.60 Bags P. Bag -


Sand 44.00 Cft Cft -
Aggregate 88.00 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour

Mason 1.25 No P. Day -


Unskilled Cooly 7.00 No P. Day -
Bahishti 0.50 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate for 1 Cum Rs. - Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

Page 21
Item No. 10 Cement concrete lining, using washed screened
and graded stone aggregate.

b) On Slope.
ii) Ratio 1:3:6

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 13.00 Bags P. Bag -


Sand 46.00 Cft Cft -
Aggregate 92.00 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour

Mason 1.25 No P. Day -


Unskilled Cooly 7.00 No P. Day -
Bahishti 0.50 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate for 1 Cum Rs. - Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

Page 22
Item No. 10 Cement concrete lining, using washed screened
and graded stone aggregate.

b) On Slope.
iii) Ratio 1:4:8

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 9.60 Bags P. Bag -


Sand 48.00 Cft Cft -
Aggregate 96.00 Cft Cft -

Total -
Contractor's Profit & Ov ## Percent -
Total -

Labour

Mason 1.25 No P. Day -


Unskilled Cooly 7.00 No P. Day -
Bahishti 0.50 No P. Day -

Total -
Sundries ## Percent -
Total -

Contractor's Profit & Ov ## Percent -


Total -

Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate for 1 Cum Rs. - Say -

1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.

Page 23
CHAPTER NO. 2

LOADING UNLOADING AND STACKING


DESCRIPTION OF ITEM NO 1: Loading or unloading into or from Railway
Wagons lead within one chain Shingle, sand,
ballast, surkhi ashes, kankar, brick bats, coal.
Lime or 1000 Nos. tiles size 12"x6"x2" or
9"x4"x1" properly laid and stacked.

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Bricks
Labour

Unskilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Cft Rs. 0.00 Say 0.00

Labour Rate Per Cum Rs. 0.00 Say 0.00

Page 1
DESCRIPTION OF ITEM NO 2: Loading or unloading bricks into or from Railway
Wagons laid and stacked lead within one chain.

a) Bricks 10" size.

Detail Unit Rate (British System) per 1000 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Bricks
Labour

Unskilled Cooly 1.25 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 1000 Nos Rs. 0.00 Say 0.00

Page 2
Item No. 2 Loading or unloading bricks into or from Railway
Wagons laid and stacked lead within one chain.

b) Bricks 9" or smaller size.

Detail Unit Rate (British System) per 1000 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Bricks
Labour

Unskilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 1000 Nos Rs. 0.00 Say 0.00

Page 3
DESCRIPTION OF ITEM NO 3: Loading or unloading into or from Railway
Wagons cement in bags (from inside or outside
the go-down) and stacking within one chain.

Detail Unit Rate (British System) per 100 Bags

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Bags
Labour

Unskilled Cooly 1.25 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Bags Rs. 0.00 Say 0.00

Page 4
DESCRIPTION OF ITEM NO 4: Loading or unloading into of from Railway
Wagons empty cement bags (from inside or
outside the go-down) and stacking.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos.
Labour

Unskilled Cooly 0.12 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Nos Rs. 0.00 0.00 Say 0.00
125

Page 5
DESCRIPTION OF ITEM NO 5: Loading or unloading into or from Railway
Wagons (from inside or outside the go-down) and
stacking white lime in bags.

Detail Unit Rate (British System) per 100 Mds

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Mds
Labour

Unskilled Cooly 0.75 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Mds Rs. 0.00 Say 0.00

Labour Rate Per 100 Kg Rs. 0.00 Say 0.00

Page 6
DESCRIPTION OF ITEM NO 6: Loading or unloading into or from Railway
Wagons structural steel, joists, broad, narrow or
meter gauge rail and rail fastening etc.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Ton
Labour

Unskilled Cooly 0.60 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per Ton Rs. 0.00 Say 0.00


Labour Rate per Tonne Rs. 0.00 Say 0.00

Page 7
DESCRIPTION OF ITEM NO 7: Loading or unloading 45 gallons drum full into
or from Railway Wagons lead upto one chain.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Unskilled Cooly 0.06 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per Each Rs. 0.00 Say 0.00

Page 8
DESCRIPTION OF ITEM NO 8: Loading or unloading packages or stock of all
sorts upto I cwt. except cement in jute or paper
bags.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Unskilled Cooly 0.03 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total

Item Rates

Labour Rate Per Each No. Rs. 0.00 Say 0.00

Page 9
DESCRIPTION OF ITEM NO 9: Loading or unloading sleepers other than wooden
including stacking lead within one chan in.

a) Broad gauge sleepers.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos.
Labour

Unskilled Cooly 2.50 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Nos Rs. 0.00 Say 0.00

Page 10
Item No. 9 Loading or unloading sleepers other than wooden
including stacking load within one chan in.

b) Metre guage and narrow guage sleepers.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour

Unskilled Cooly 1.25 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Nos Rs. 0.00 Say 0.00

Page 11
DESCRIPTION OF ITEM NO 10: Loading or unloading timber logs or timber for
shuttering into or from Railway Wagons of any
gauge including stacking, lead within one chain.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 20 Ton
Labour

Unskilled Cooly 5.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per Ton Rs. 0.00 Say 0.00


Per Tonne Rs. 0.00 Say 0.00

Page 12
DESCRIPTION OF ITEM NO 11: Loading or unloading bhoosa in Railway Wagons
lead upto 150 feet.

Detail Unit Rate (British System) per 100 Mds

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Mds
Labour

Unskilled Cooly 3.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Mds. Rs. 0.00 Say 0.00

Labour Rate Per 100 Kg Rs. 0.00 Say 0.00

Page 13
DESCRIPTION OF ITEM NO 12: Loading or unloading timber scrap or wooden
plugs into or from Railway Wagons and stacking
within one chain lead.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1.25 Ton
Labour

Unskilled Cooly 0.50 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per Ton Rs. 0.00 Say 0.00


Labour Rate Per Tonne Rs. Say 0.00

Page 14
DESCRIPTION OF ITEM NO 13: Loading or unloading pitching stone or spawl
from Railway Wagons of any gauge (including
clearing 5 feet away from the rail)

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft.
Labour

Unskilled Cooly 0.37 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Cft Rs. 0.00 Say 0.00

Labour Rate Per Cum Rs. 0.00 Say 0.00

Page 15
DESCRIPTION OF ITEM NO 14: Loading or unloading building stone (including
clearing 5 feet away from rails)

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft.
Labour

Unskilled Cooly 0.48 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Cft Rs. 0.00 Say 0.00

Labour Rate Per Cum Rs. 0.00 Say 0.00

Page 16
DESCRIPTION OF ITEM NO 15: Unloading oil, bitumen tar etc.

a) Crude oil (to be pumped from tank wagon, into


tank).

Detail Unit Rate (British System) per 1000 Gln

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Gallons
Labour

Unskilled Cooly 1.25 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 1000 Gln. Rs. 0.00 Say 0.00

Labour Rate Per 100 Liters Rs. 0.00 Say 0.00

Page 17
Item No. 15 Unloading oil, bitumen tar etc.

b) Crude oil (drained by gravity).

Detail Unit Rate (British System) per 1000 Gln

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Gallons
Labour

Unskilled Cooly 1.25 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 1000 Gln. Rs. 0.00 Say 0.00

Labour Rate Per 100 Liters Rs. 0.00 Say 0.00

Page 18
Item No. 15 Unloading oil, bitumen tar etc.

c) Crude oil materials from Railway Wagons.

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft
Labour

Unskilled Cooly 0.16 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Cft Rs. 0.00 Say 0.00

Labour Rate Per Cum Rs. 0.00 Say 0.00

Page 19
Item No. 15 Unloading oil, bitumen tar etc.

d) Fuel oil from tank into empty drums and stacking


within one chain.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 45 Ton
Labour

Unskilled Cooly 16.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per Ton Rs. 0.00 Say 0.00


Labour Rate Per Tonne Rs. 0.00 Say 0.00

Page 20
Item No. 15 Unloading oil, bitumen tar etc.

e) Petrol (2 gallon tin)

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour

Unskilled Cooly 0.63 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Nos Rs. 0.00 Say 0.00

Page 21
Item No. 15 Unloading oil, bitumen tar etc.

f) Kerosine oil (4 gallons tin).

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour

Unskilled Cooly 1.25 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Nos Rs. 0.00 Say 0.00

Page 22
DESCRIPTION OF ITEM NO 16: Removing and stacking within one chain lead.

a) Stones, Spawl, Brick Bats, shingle, sand, lime.


Surki, ashes, Kankar & Coal etc.

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft
Labour

Unskilled Cooly 0.50 No 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Cft Rs. 0.00 Say 0.00

Labour Rate Per Cum Rs. 0.00 Say 0.00

Page 23
Item No. 16 Removing and stacking within one chain lead.

b) Bricks

Detail Unit Rate (British System) per 1000 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 15,000 Nos
Labour

Unskilled Cooly 16.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 1000 Nos Rs. 0.00 Say 0.00

Page 24
Item No. 16 Removing and stacking within one chain lead.

c) Broad gauge wooden sleepers

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 2,500 Nos
Labour

Unskilled Cooly 16.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Nos Rs. 0.00 Say 0.00

Page 25
Item No. 16 Removing and stacking within one chain lead.

d) Metre gauge or narrow gauge wooden sleepers.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 4,200 Nos
Labour

Unskilled Cooly 16.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Nos Rs. 0.00 Say 0.00

Page 26
Item No. 16 Removing and stacking within one chain lead.

e) Rails, girders, pipes, cement etc.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 90 Ton
Labour

Unskilled Cooly 16.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per Ton Rs. 0.00 Say 0.00


Labour Rate Per Tonne Rs. Say 0.00

Page 27
Item No. 16 Removing and stacking within one chain lead.

f) Bridge and crossing timber etc.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 750 Nos
Labour

Unskilled Cooly 16.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Nos Rs. 0.00 Say 0.00

Page 28
DESCRIPTION OF ITEM NO 17: Loading into Wagons Girders, Rails, permanent
way material (except wooden sleepers) iron work,
M.S. Bars, Pipes, etc. including lead one chain
and stacking inside Wagons.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 40 Ton
Labour

Unskilled Cooly 16.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per Ton Rs. 0.00 Say 0.00


Labour Rate Per Tonne Rs. Say 0.00

Page 29
DESCRIPTION OF ITEM NO 18: Unloading from Wagons Girders, Rails,
permanent way material (except wooden sleepers)
iron work, M.S. Bars, Pipes, etc. lead upto one
chain but excluding stacking.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 70 Ton
Labour

Unskilled Cooly 16.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per Ton Rs. 0.00 Say 0.00


Labour Rate Per Tonne Rs. 0.00 Say 0.00

Page 30
DESCRIPTION OF ITEM NO 19: Loading into Wagons, wooden broad gauge
sleepers including one chain lead and stacking.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1,000 Nos
Labour

Unskilled Cooly 16.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Nos Rs. 0.00 Say 0.00

Page 31
DESCRIPTION OF ITEM NO 20: Unloading wooden broad gauge sleepers from
Wagons including one chain lead and stacking.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 2,100 Nos
Labour

Unskilled Cooly 16.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Nos Rs. 0.00 Say 0.00

Page 32
DESCRIPTION OF ITEM NO 21: Loading metre gauge or narrow gauge wooden
sleepers including one chain lead and stacking
inside Wagons.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 2,000 Nos
Labour

Unskilled Cooly 16.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Nos Rs. 0.00 Say 0.00

Page 33
DESCRIPTION OF ITEM NO 22: Unloading metre gauge or narrow gauge wooden
sleepers including one chain lead but excluding
stacking

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 3,800 Nos
Labour

Unskilled Cooly 16.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Nos Rs. 0.00 Say 0.00

Page 34
DESCRIPTION OF ITEM NO 23: Loading Bridge and grossing timber including
one chain lead and stacking.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour

Unskilled Cooly 4.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Nos Rs. 0.00 Say 0.00

Page 35
DESCRIPTION OF ITEM NO 24: Unloading Bridge and crossing timber including
one chain lead but excluding stacking.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour

Unskilled Cooly 2.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per 100 Nos Rs. 0.00 Say 0.00

NOTE :

Rate for loading and unloading for Mobile trucks/ boats, item 1-15 will be 80%
of the rate of Railway Wagons.

Page 36
DESCRIPTION OF ITEM NO 25: Loading or unloading bitumen, asphalt or tar in
drums, into or from Railway Wagons lead upto
one chain.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 25 Ton
Labour

Unskilled Cooly 6.00 Nos 0.00 P. Day -

Total -
Sundries #### Percent -
Total -

Contractor's Profit & Ove #### Percent -


Total -

Item Rates

Labour Rate Per Ton Rs. 0.00 Say 0.00


Labour Rate Per Tonne Rs. 0.00 Say 0.00

Page 37
LIST OF LUMPSUM ITEMS-1

S.No. MATERIAL Unit RATE


Kitchen Expenses (tea, meat, milt fuel fat & appliances)
LS-01 Ch. 3 Item 16 (i)
--
Lantern, Patromax lamp depreciation and K. oil
LS-02 consumption Ch. 3 Item 16 (i)
--
LS-03 Kitchen Utensil, cost of repair and replacement etc. Ch.
--
3 Item 16 (i)
LS-04 Kitchen Utensil, cost of repair and replacement etc. Ch. --
3 Item 16 (i)
LS-05 Construction of Temporary Island (Ch. 6 Item 7 (i) --
LS-06 Carriage of material to site of work (Boring Material) --
(Ch 6 Item 7 (i)
LS-07 Hire charges of plant (Ch. 6 Item 8 (a) & (b) --
Hire charges of assembling bunch cable wire cutter
LS-08 stressing, jack Hydraulic pump, conce, fixer grout
injecting pump relievable observation and supply of
recorded data of stresses. (Ch. 6 Item 20) --
LS-09 Repair of plate for the down struts spacers (Ch. 6 Item --
21)
Hire charges of wire cutter stressing, Jack, Hydraulic
LS-10 pump relievable cone, observation and supply of recorded
--
d f (Ch 6 21)
LS-11 Fixture (Ch. 9 Item 18) --
LS-12 Hire Charges of Spray Machine (Ch. 11 Item 6 i, ii & iii) --
LS-13 Nail & Screws bolt and brackets (Ch. 12 Item 24 (a) --
LS-14 Accessories for fixing of Eave Board (Ch. 12 Item 28 (b) --
LS-15 Cost of Putty and Nails (Ch. 12 Item 44 a) --
LS-16 Electricity Charges (Ch. 12 Item 51) --
LS-17 Hold Fast (Ch. 12 Item. 57 b) --
LS-18 Burner Charges, Kerosene Oil & Scraper (Ch. 13 Item 16) --
LS-19 Misc. i.e. small T&P, working of Crane & Tar Boiler (Ch. --
18 Item 10)
LS-20 Excavation and fixing (Ch. 18 Item 18 (iv) a) --
LS-21 Jointing Plate with T Iron (Ch. 18 Item 18 (iv) a) --
LS-22 Painting and lettering (Ch. 18 Item 18 (iv) a) --
LS-23 Fixing manhole frame & cover including carriage to site --
(Ch 21 Item 15)
LS-24 Rental Charges of T&P (Ch. 21 Item. 19 a i) --
Carriage from store to site of work for reverse rotary
LS-25 drilling reg complete set and generator set etc. (Ch. 23
Item 5 (a) i) --
LS-26 Mix. Expenditure (Ch. 23 Item 5 (a) i) --
LS-27 Taking and preserving box 2 lbs sample of strata. (Ch. 23 --
Item 7)
Taking samples of water from bore hole including bailing
LS-28 or 'pumping. (Ch. 23 Item 7)
--
Sealing the water sample and providing necessary packing
LS-29 etc. (Ch. 23 Item 7)
--
LS-30 Handling charges (Ch. 23 Item 7) --
LS-31 C. Oil (Ch. 23 item 17 i & ii) --
Providing and fixing temporary wooden tapered plug of
LS-32 hard wood to each end of pipe line for 3" (Ch. 23 Table
19 C) --
Providing and fixing temporary wooden tapered plug of
LS-33 hard wood to each end of pipe line for 4" (Ch. 23 Table
--
19 C)
Providing and fixing temporary wooden tapered plug of
LS-34 hard wood to each end of pipe line for 5" (Ch. 23 Table
--
19 C)

Page 1
LIST OF LUMPSUM ITEMS-1

S.No. MATERIAL Unit RATE


Providing and fixing temporary wooden tapered plug of
LS-35 hard wood to each end of pipe line for 6" (Ch. 23 Table
--
19 C)
Providing and fixing temporary wooden tapered plug of
LS-36 hard wood to each end of pipe line for 8" (Ch. 23 Table
--
19 C)
Providing and fixing temporary wooden tapered plug of
LS-37 hard wood to each end of pipe line for 10" (Ch. 23 Table
--
19 C)
Providing and fixing temporary wooden tapered plug of
LS-38 hard wood to each end of pipe line for 12" (Ch. 23 Table
--
19 C)
Providing and fixing temporary wooden tapered plug of
LS-39 hard wood to each end of pipe line for 15" (Ch. 23 Table
--
19 C)
Providing and fixing temporary wooden tapered plug of
LS-40 hard wood to each end of pipe line for 18" (Ch. 23 Table
--
19 C)
LS-41 Soldering etc. (Ch. 24 Item 5 i) --
LS-42 Locking arrangement (Ch. 24 Item 44 i) --
LS-43 Extra labour for shuttering (Ch. 24 Item 44 i) --
LS-44 Testing Fee (Ch. 24 Item 75 a & b) --
LS-45 Leatheride Paper (Ch. 24 Item 76 i) --
LS-46 Carriage from stone to site (Ch. 24 Item 42 a) --
LS-47 Carriage to site of work (Ch. 25 Item 41 a) --
LS-48 Carriage to site of work (Ch. 25 Item 41 b) --
LS-49 Electric charges with electrode (Ch. 24 Item 42 a) --
LS-50 Sewing charges (Labour) (Ch. 26 Item 4) --
LS-51 Cost of Polish & Nails (Ch. 26 Item 20) --
LS-52 Rope, rags, etc. (Ch. 26 Item 22) --
LS-53 Filling cement bags with coal (Ch. 26 Item 27) --
LS-54 Cotton Waste, Grease & Packing etc. (Ch. 26 Item 35 b) --
LS-55 Accessories, repair and replacement portion (Ch. 26 Item --
35 b)
LS-56 Spraying Machine (Ch. 26 Item 42) --

Page 2
LIST OF MATERIAL
ITEM MATERIAL UNIT RATE
01.001Cotton waste Per Kg
01.002Grease Per Kg
01.003H.S. Diesel oil Per Ltr.
01.004Kerosine oil Per Ltr.
01.005Mobil oil Per Ltr.
01.006Average diesel consumption of a truck miles/gallon
01.007Average mobile oil consumption of a truck miles/gallon
03.001Gun powder and fuse for blasting (1 pound and 1 fuse) Each
03.002Jhambs Each
03.003Charakharies complete Each
03.004Manila Rope 1" Rft
03.005Cost of repair and replacement of 4 Nos. picks axes and 8 No Per Day
03.006Palana with namda for one donkey Each
03.007Repair and replacement of sacks Each
03.008Tent Each
03.009Donkey hut Each
03.010Royalty for pit sand % Cft
03.011Nail bolts and nuts Kg.
03.012Atta P.Kg.
03.013Phak per Md
03.014Grams per Md
06.001Brick Ballast 1" (at site) 100 Cft
06.002Brick Ballast 1" to 1" (at site) 100 Cft
06.003Stone Ballast 1" to 1" (at source) 100 Cft
06.004Brick Bats 100 Cft
06.005Coarse sand (Chenab) (at site) 100 Cft
06.006Harrow/Sand (at site) 100 Cft
06.007Sand (Local) (at site) 100 Cft
06.008Cement (Grey) Per Bag
06.009Cement (White) Per Bag
06.010Shingle (Naturally Graded) at site (Bajri) 100 Cft
06.011Aggregate/Stone Crushed " to 1" (Graded) (at site) 100 Cft
06.012M.S. Bars (Plain) " and above (36000 PSI) M. Ton
06.013M.S. Bars (Deformed) (40 grade) M. Ton
06.014M.S. bars (Tor Steel 60 grade) M. Ton
06.015Cost of casing pipe of 18" dia Per Rft
06.016Cost of casing pipe of 20" dia Per Rft
06.017Cost of casing pipe of 22" dia Per Rft
06.018Cost of casing pipe of 24" dia Per Rft
06.019Nail and Screw (Copper) Per. Kg.
06.020Brush (Large) Each
06.021Brush (Small) Each
06.022Binding wire Kg
06.023Special Clamps with bolts and nuts Each
06.024Welding electrode P.Bundle
06.025Prestressing Cable having 12 Nos. wire P.Ton
06.026Anchorage cone per set
06.027Corrugated sheath of 1-9/16" for 12/0.276" (7mm) cable per metre
06.028Making good recesses Each end
06.029Steel rope 1" Rft
06.030U Clamp i/c 5/8" bolts & nuts each
06.031Steel rope " dia Rft
06.032Railway track including sleepers bolts & nuts complete Rft
06.033Crow bar Each
06.034Aluminum powder per kg
06.035Aluminum sheet 1/16" to 1/8" (1.6 to 3 mm) thick per kg
06.036Helical core (compressed for 10 tons) per metre
06.037G.I. Sheet special "V shaped " each
06.038Mastic strip P.Rft
06.039Copper flashing 1/16" thick P.Sft
06.040Rubber water stopper 10" wide and 1/4" thick P.Rft
06.041Bitumen P.Kg.
06.042Sawdust P.Cft
06.043Wood for heating P.Kg.
06.044Thermopore sheet 1" (40 mm) thick m
06.045Thermopore sheet 1" (25 mm) thick m
06.046Polythene @ 1.13 kg % Sft P.Kg.
06.047Broken glass % kg
07.001Ist class bricks 9" x 4" x 3" (225 x 112.5 x 75 mm) %o Nos.
07.002Fire Clay Bricks 225 x 112.5 x 75 mm Each
07.003Good earth/clay 100 Cft
07.004Fire resistant cement 0 Kg per bag

Page 1
ITEM MATERIAL UNIT RATE
07.005Moulded Special bricks 9" x 4" x 3" %o Nos.
07.006Sun dried bricks %o Nos.
07.007Lime (Slaked) Kg
07.008Lime (Unslaked) Kg
07.009Brick grinded and sand Cft
07.010Hoop Iron Per Kg.
08.001Quarried Stone at source 100 Cft
08.002Headers or through stone (1.5" x 8" x 10") Each
08.003Pitching stone at source % Cft
08.004Charcoal Per Kg
08.005Wood preservative (Heptaclore) Per Ltr.
08.006Steel Per Kg.
08.007Hand dressed stone average (2 Cft) Each
08.008Hand dressed stone average (4 Cft.) Each
09.001Brick tiles 300 x 150 x 50 mm (12"x6"x2" ) %o Nos.
1
09.002 Brick tiles 300 x 150 x 40 mm 12"x6"x1 /2") %o Nos.
09.003Brick tiles 300 x 150 x 32 mm (12"x6"x1" ) %o Nos.
09.004 Brick tiles 225 x 112.5 x 50 mm (9"x41/2"x2") %o Nos.
09.005Brick tiles 225 x 112.5 x 40 mm (9"x41/2"x1") %o Nos.
09.006G.I. Plain Sheet 18 - 20 SWG Per kg
09.007G.I Plain Sheet 22 - 24 SWG Kg
09.008G.I. Corrugated sheet 18 - SWG Per Kg
09.009G.I. Corrugated sheet 22 - 24 SWG Per Kg
09.010G.I. Corrugated sheet 20 SWG Per Kg
09.011G.I. Hook, Nuts and Bolts Doz
09.012G.I. Washers Per Kg
09.013Washers Limpet Per Dozen
09.014Bhoosa Kg
09.015Pig lead Kg
09.016Cowdung (wet) % Kg
09.017A.C. T-bend 100 mm Each
09.018A.C. Shoe 100 mm Each
09.019A.C. Ridge Sheet (6mm) Rft
09.020Fuel wood Per Kg.
09.021Wire Nails Per Kg.
09.022Wind tie (rod) P Kg.
09.023Bitumen washers Doz
09.024Brick Aggregate P. Cft
09.025Lead flashing 1/16" thick P. Sft
09.026C.I. Heads 4" Each
09.027Clamps with hold fasts etc. (For Rain Water Pipe) Each
09.028C.I. water down pipe 4" (100mm) dia P. Rft
09.029C.I. water down pipe down 3" (75mm) dia P. Rft.
09.030C.I. shoes bend or offsets 4" Each
09.031Corrugated A.C. sheets P.Sft
09.032G.I. or limpet washers and bitumastic washers Doz
09.033Wrought iron bracket complete with bolts, Nuts and rivets et Each
09.034Polythene 0.03" (0.08 mm) Pr. Kg.
09.035Thermopore " (12mm) thick Per Sft.
09.036Thermopore " (19mm) thick Per Sft.
09.037Thermopore 1" (25mm) thick Per Sft.
09.038A.C. pipe 4" (100mm) dia P.Rft
09.039U.I. Clips Kg.
09.040Screws 3" & 2" Kg.
10.001Murrum powder fine. % Cft
10.002Cement concrete tiles 200 x 200 x 20 mm (8" x 8" x ") Each
10.003Cement Concrete tiles 300 x 300 x 25 mm (12" x 12" x 1") Each
10.004Cement Concrete tiles 225 x 225 x 20 mm (9" x 9" ") Each
10.005Cement concrete tiles 150 x 150 x 20 mm (6" x 6" x ") Each
10.006White Tile (Glazed) 6"x6"x" Each
10.007Coloured Glazed tiles 150 x 150 x 6 mm (6" x 6" x ") Each
10.008Coloured Glazed tiles 300 x 300 x 6 mm (12" x 12" ") Each
10.009Mosaic marble chips tiles300 x 300 x 25 mm (12" x 12" x 1") Each
10.010Rubber tiles 300 x 300 x 3 mm (12" x 12" x 1/8") Each
10.011White glazed tiles 300 x 300 x 6mm (12" x 12" x ") Each
10.012Dressed Stone 2'x2'x2" Each
10.013Dressed Stone 2'x2'x3" Each
10.014Carborandum Stone Each
10.015Pigment for Cement/Concrete Per Kg
10.016Marble Chips Per Kg
10.017Marble Powder 100 Kg
10.018Neoprene strip 100 x 6 mm P. Foot
10.019Wax Polish 3 Kg.

Page 2
ITEM MATERIAL UNIT RATE
10.020Tartaric Acid Per Kg
10.021Hessian Cloth Per Mtr.
10.022Linen Cloth P. Kg.
10.023Asphalt P. Kg.
10.024Sand Paper Per Doz.
10.025Brass Screws 50 mm long Per Doz.
10.026Glass stip 3 mm thick 40 mm wide % Rft
10.027Glass Strips 4 mm thick 40 mm wide % Rft
10.028Glass Strips 5 mm thick 50 mm wide % Rft
10.029Marble strips 6 mm thick 40 mm wide Rft
10.030Marble strips 10 mm thick 40 mm wide Rft
10.031Sutli Per Kg
10.032Steam coal Kg
10.0339" thick rubble or broken hard bricks %Cft.
10.034Hard Marrum %Cft.
10.035Floor Polish P. Kg.
10.036Adhesive Mixture dry Per Kg.
10.037Surkhi P. % Cft.
10.038Fine Aggregate % Cft.
10.039Primer P.Kg.
11.001Chopped Jute Per Kg
11.002Distemper (Vinyle Emulsion) Per Gallon
11.003Distemper Plastic bound (Plastic Emulsion) Per Gallon
11.004Distemper Water bound Per Gallon
11.005Rice Per Kg
11.006Pigment for colour wash Per Kg
11.007Primer/red oxide pigment Per Gln.
11.008Chopped Straw P.Kg
11.009Expended metal edge bead 5" wide P. Rft
12.001Chir Ist Class CFT
12.002Deodar Wood best quality CFT
12.003Deodar Wood 2nd class CFT
12.004Fire Wood Kg
12.005Kail Ist class CFT
12.006Shisham wood Ist class CFT
12.007Teak wood CFT
12.008Partal wood CFT
12.009Kikar wood CFT
12.010Sheets Aluminum 8 - SWG - 24 SWG (local) Per Kg
12.011Sheets Aluminum " thick and above (local) Per Kg
12.012Copper sheet 0.80 mm to 2.50 mm Per Kg
12.013Copper sheet 3.00 mm to 6.00 mm Per Kg
12.014Formica sheet (8' x 4') Per sheet
12.015Plain Galvanized iron sheet Per Kg
12.016Corrugated Galvanized iron sheet Per Kg
12.017Commercial ply 6 mm thick SFT
12.018Commercial ply 3 mm thick SFT
12.019Shisham wood ply (6 mm thick) SFT
12.020Teak wood ply (6 mm thick) SFT
12.021Thermopore sheet " (12 mm) thick 20 kg/m (39" x 39") P. sheet
12.022Thermopore sheet " (20 mm) thick 20 kg/m (39" x 39") P. sheet
12.023Thermopore sheet 1" (25 mm) thick 20 kg/m (39" x 39") P. sheet
12.024Masonite sheet 5 mm thick for partitions P. Sft
12.025Masonite Sheet for ceiling P.Sft
12.026Bacolite sheet (2.50 mm) thick (size 4' x 4') eet 4'x4' size
12.027Bacolite sheet (3.75 mm) thick (size 4' x 4') eet 4'x4' size
12.028Bacolite sheet (4.00 mm) thick (size 4' x 4') eet 4'x4' size
12.029Rubber sheet 5 mm (size 4' x 6') eet 4'x6' size
12.030Zinc Plate 525 x 11 mm Kg
12.031Spike Per Kg
12.032Glass pan 3 mm thick 16 x to 18 oz SFT
12.033Glass pan 3 mm thick 24 x to 26 oz SFT
12.034Glass plate " (6 mm) thick upto 8 SFT SFT
12.035Glass plate " (6 mm) thick not exceeding 24 SFT SFT
12.036Glass Plate 6 mm thick SFT
12.037Glass Plate 8 mm SFT
12.038Glass Plate " (12 mm) thick PSF
12.039Glue Per Kg
12.040Machine Screws 38.10 x 7.35 mm Per Doz.
12.041Iron strips 1" x 1/8" Kg
12.042Brass finger plate Each
12.043Brass hinges 50 mm Each
12.044Brass hinges 63 mm Each

Page 3
ITEM MATERIAL UNIT RATE
12.045Brass hinges 75 mm Each
12.046Brass hinges 100 mm Each
12.047Brass hinges 125 mm Each
12.048Brass tower bolts 300 mm Each
12.049Brass tower bolts 225 mm Each
12.050Brass tower bolts 200 mm Each
12.051Brass tower bolts 150 mm Each
12.052Steel nut and bolts (all sizes) Per Kg
12.053Iron hold fast (for doors/windows) Each
12.054Iron handle 100 mm 4" Each
12.055Iron handle 150 mm (6") Each
12.056Iron handle 200 mm (8") Each
12.057Brass handle 100 mm Each
12.058Brass handle 150 mm Each
12.059C.P. handles 4" (2nd Quality) Rft
12.060C.P. handles 4" Each
12.061C.P Handle 6" P.Doz
12.062C.P. handles 6" (Best Quality) Each
12.063Handle Each
12.064Iron sliding bolt 200 mm (8") with screws Each
12.065Iron sliding bolt 250 mm (10") with screws Each
12.066Iron sliding bolt 300 mm (12") with screws Each
12.067Racal plugs 1" (40mm) long Each
12.068Racal Plug (small) Each
12.069Push plate (Stainless) Each
12.070Kikai plate (Aluminum) 4" wide 22 gauge 12" long Each
12.071Rim lock (China) Each
12.072Mortise lock (Local) Each
12.073Sliding bolts Brass 300 mm (12") Each
12.074Hinges (Iron) 50 mm Each
12.075Hinges (Iron) 75 mm Each
12.076Hinges (Iron) 100 mm Each
12.077Hinges (Iron) 125 mm Each
12.078Double action spring Hinges (Brass) Medium 4" - 5" (100 to 1 Per pair
12.079Double action spring Hinges (Iron) 4"-5" (100 to 125 mm) Each set
12.080Brass screw 20 mm Doz.
12.081Brass screw 25 mm Doz.
12.082Brass screw 40 mm Doz.
12.083Door Stops 150 mm Each
12.084Door stopper 150 mm (wooden) Each
12.085Foot hinges 1" Each
12.086Tee hinges 250 mm Each
12.087Tee hinges 150 mm Each
12.088Tee hinges 200 mm Each
12.089Butt Hinges (125mm) Each
12.090Butt Hinges (150mm) Each
12.091Hasp & staples (medium size) Each
12.092Iron tower bolt 100 mm long Per Doz.
12.093Iron tower bolt 150 mm long Per Doz.
12.094Iron tower bolt 225mm long Per Doz.
12.095Iron tower bolt 250 mm long Per Doz.
12.096Iron tower bolt 300 mm long Per Doz.
12.097Hold fast with pivot & clamp 4" Each
12.098Hold fast with pivot & clamp 6" Each
12.099Hold fast with pivot & clamp 8" Each
12.100spring hinges (doors/windows) Each
12.101Wrought Iron Hold Fast (small) Each
12.102Wrought Iron Hold Fast (Large) Each
12.103Deodar wooden beading (1" x ") Rft
12.104Deodar wooden lipping 6 mm Rft
12.105Deodar wooden lipping 3/8 Rft
12.106Chord with hook (" x ") Each
12.107Wooden cleat for door Each
12.108G.I. hook with clamp (doors/windows) Each
12.109Khunda - Chapka (For Almirah) Each
12.110Rubber Pad Stopper Each
12.111Wire Gauze (12x12) Sft.
12.112Wooden Plug for door Each
12.113Expended Metal (12mm to 20mm mesh of 16 gauge) Sft.
12.114Hinges 10" (250mm) Each
12.115Hinges chocks 4" (100mm) (for battened doors) Each
12.116Hasp and staple Each
12.117Hold fast with pivots & clamp for framed and braced doors Each

Page 4
ITEM MATERIAL UNIT RATE
12.118Sliding bolts 18" (450mm) long Each
12.119M.S. Angle Iron 1"x1"x" (40x40x6mm) P.Kg.
12.120M.S. Flat 6"x"x1/8" (150x6x3mm) P.Kg.
12.121Hinges Chocks 3" (75mm) Each
12.122Screws upto 1" long Doz
12.123Screws above 1" long Per Doz.
12.124Nails of sorts Pr. Kg.
12.125Brass spring hinges Complete with Screws Each
12.126Brass sliding bolt 10" (250mm) long 'complete with screws & Each
12.1271" (25mm) thick solid flush shutter Sft.
12.128Solid flush door 1" thick Sft.
12.129C.P. dasti I/C screws Each
12.130Hard Board Sft
12.131Brass butt hinges 2" (50mm) Each
12.132Brass butt hinges 6" (150mm) Each
12.133Sawing Charges Sft
12.134Tie rod welding and fixing arragement Each
12.135Vin board " thick Sft.
12.136Vin board " thick Sft.
12.137Chip Board " (20mm) 700 density P.Sft
12.138Chip Board " (12mm) 700 density P.Sft
12.139Full hinges " (20mm) wide (Imported) Rft
12.140Catcher Each
12.141lock China Each
12.142C.P. Hanger rod with 2 hooks Each
12.143Hanger hook including pull out rod Each
12.144Brass hooks Each
12.145Door rubber stopper Each
12.146G.I. Hook Each
12.147Hooks forPunkha Pole Per Dozen
12.148Nails P.Kg.
12.149Washers Each
12.150Hard Wood Gutty Each
12.151M.S clamp Each
12.152M.S hook Each
12.153Sand Paper Each
12.154Tower bolt C.P. Each
12.155C.P. finger plate with screws Each
12.156M.S. sheets (plain) 20 SWG Kg
12.157M.S. Sheet 18 SGW Sft
12.158M.S. Sheet 22 SGW Sft
12.159Curtain Railing Rft.
12.160Electrod Pkt
12.161Gola (Wood) P. Ft.
13.001Black Japan paint Gln.
13.002Chalk powder Per Kg
13.003Dana Lakh Per Kg
13.004Emulsion paint Per Gallon
13.005Paint Enamel P. Gln
13.006French Polish Per Kg
13.007Gum and Gun rasin Per Gallon
13.008Linseed oil Per Kg
13.009Road marking enamel Per Ltr.
13.010Solignum paint (Imported) Per Gallon
13.011Spirit Per Ltr.
13.012Varnish Kg
13.013White Enamel paint Per Gln.
13.014Caustic Soda Kg
13.015Painting Brushes (average rate) Each
13.016Mineral Pitch Kg
13.017Primer Paint P.Gln
13.018Reflective Paint P. Gln
13.019Reflective Tape/Paper P. Sft.
13.020Creosote P. Gln
13.021Steel Scrapper Each
13.022Kerosine Oil Litre
13.023Terpentine oil Per Ltr.
13.024Water Proofing Emulsion Paint P.Kg.
16.001Jute bag (Empty) (1.25 Cft.) Each
16.002New jute bag (4 to 5 Cft.) Each
16.003Pitching Stone % Cft
16.004Munj patha ban Per Kg
16.005G.I Wire No.15 Per Kg

Page 5
ITEM MATERIAL UNIT RATE
16.006Bamboo (60 - 120 mm dia) 2.5 meter to 3.0 metre long Each
16.007Bamboo (60 - 120 mm dia) 3.0 meter to 3.75 metre long Each
16.008Bamboo (60 - 120 mm dia) 3.75 meter to 4.25 metre long Each
16.009Bamboo (60 - 120 mm dia) 4.25 meter to 4.90 metre long Each
16.010Bamboo (60 - 120 mm dia) 4.90 meter to 6.25 metre long Each
16.011G.I Wire No. 8 to 10 Per Kg
16.012Sutli P.Kg
16.013wooden vertical stakes 7" to 12" dia for groynes P. % Nos.
16.014Royality charges of wooden stakes Each
16.015Shingle / spawl P.% Cft
16.016Boulder P.% Cft
16.017Supply pilchi lead within one mile P.% Cft
16.018Pilchi Roll 6" dia 5' long P.% Cft
16.019Bajri / shingle P.% Cft
16.020Royality kikar brush wood P.% Mds
16.021Kikar wood for pegs P. Cft
18.001Course aggregate (bajri) for surface dressing (Quarry site) 100 Cft
18.002Graded stone for base course (Quarry site) 100 Cft
18.003Brick Aggregate For Sub Base course (Quarry site) 100 Cft
18.004Pit-run/Bedrun graval (Quarry site) 100 Cft
18.005Stone screaned (Crusher site) 100 Cft
18.006Stone Dust (Quarry/Plant site) 100 Cft
18.007Steel bars (including binding wire) Per Kg.
18.008Iron post Per Kg
18.009Elbow 2" Each
18.010Tee 2" x 2" x 2" Each
18.011Steel bearing (standard quality) Each
18.012Rubber bearing pad 1" x 1" x 1" (2.5x2.5x2.5 cm) P.Cub
18.013A.C pipe 3" i/d per metre
18.014T.Iron and M.S Plate P. Kg.
18.015Lettering 4" height Each
18.016Lettering 3" height Each
19.001Cast iron head 4" Per Kg
19.002Cast iron shoe 4" Per Kg
19.003Cast iron bend 4" Per Kg
19.004Cast iron off set 4" Per Kg
19.005G.I spout 4" 460 mm long Each
19.006AC - bend 4" (100 mm) Each
19.007AC Shoe 4" (100 mm) Each
19.008AC Tee (100 mm) Each
19.009Angle Iron Bracket Set for W.H.B & Cistern Each
19.010'Angle Iron Bracket Set for Sink Each
19.011Waste pipe 3 cm (1") (PVC) Each
19.012Waste pipe 4 cm (1") (PVC) Each
19.013C.P. waste coupling 3 cm (1") Each
19.014C.P. waste coupling 4 cm (1") Each
19.015Rubber plug with chain 3 cm (1") Each
19.016Rubber plug with chain 4 cm (1") Each
19.017PVC Flushing bend 3 cm (1") Each
19.018PVC Flushing bend 4 cm (1") Each
19.019Plastic rubber connection with check nut Each
19.020Copper connectionn with check nut: Each
19.021C.P. Shower rose 1.5 x 10 cm (" x 4") Each
19.022C.P. Shower rose 2.0 x 15 cm (" x 6") Each
19.023C.I brackets for high level flushing cistern Per pair
19.024C.I. Bracket for Wash hand basin Each
19.025White Glazed earthen ware low down cistern 13.63 ltr. (3/Gln Each
19.026Coloured Glazed earthen ware low down cistern 13.63 ltr. (3/ Each
19.027White Glazed cast iron low down cistern 13.63 ltr. (3/Gln) Each
19.028RCC Pipe 4" dia Rft.
19.029Plastic made low down flushing cistern 13.63 litre (3 gallo Each
19.030Pedestal for W.H.B Each
19.031Bolt and Nuts for W.C. (European Type) Each
19.032A.C soil pipe 6cm (2" dia) Metre
19.033A.C soil pipe 7.5cm (3" dia) Metre
19.034A.C soil pipe 10cm (4" dia) Metre
19.035A.C soil pipe 15cm (6" dia) Metre
19.036C.I. Soil Down 50 mm (2") dia Metre
19.037C.I Soil Down 100 mm (4") dia (30 PSI) Metre
19.038Yarn per lbs
19.039Chromium plated T-stop cock 1.5 c.m (") Each
19.040Brass gas cock 1.5 c.m (") Each
19.041Brass gas cock 2.0 c.m (") Each

Page 6
ITEM MATERIAL UNIT RATE
19.042Brass bib cock " (1.5 cm) Each
19.043Brass bib cock " (2 cm) / brass stop cock Each
19.044Glazed Earthenware sink 60 x 45 cm (24" x 18") Each
19.045Glazed Earthenware sink 37.5 x 45 cm (15" x 18") Each
19.046Statinless steel sink with drain board 120 x 60 cm (48 x 24 Each
Terazzo concrete sink 60 x 45 cm (24" x 18") With drain
19.047 Each
board
19.048Brass ball float valves 15 mm (") dia Each
19.049Brass ball float valves 20 mm (") dia Each
19.050Brass ball float valves 25 mm (1") dia Each
19.051Brass ball float valves 30 mm (1") dia Each
19.052Brass ball float valves 40 mm (1") dia Each
19.053Brass ball float valves 50 mm (2") dia Each
19.054C.P. Mixing Valves " dia (Mixer) Each
19.055Glass Shelf 60 x 13 cm (24" x 5") Each
19.056Chromium plated bracket and railling for glass shelf Each
Glazed earthen ware shelf 60 x 13 cm (24" x 5") with
19.057 Each
chromium plated bracket and railing (Coloured)
Glazed earthen ware shelf 60 x 13 cm (24" x 5")
19.058 Each
withchromium plated bracket and railing (White)
19.059Soap dish chromium plated Each
19.060Soap dish glazed earthen ware white colour Each
19.061Soap dish plastic Each
19.062Toilet Paper Holder (Chromium plated) Each
19.063Toilet Paper Holder (Plastic) Each
19.064Towel Rail With Brackets (Chromium plated) 60 x 2 cm (24" x Each
19.065Towel Rail With Brackets (Chromium plated) 50 x 1.5 cm (20" Each
19.066Towel Rail With Brackets (Plastic) Each
19.067C.I floor trap including grating size 10 x 5 cm (4" x 2") Each
19.068Chromium plated bottle trap 3 cm (1") (with waste pipe) Each
19.069Chromium plated bottle trap 4 cm (1") (with waste pipe) Each
19.070Cast iron P-trap 10 cm (4") Each
19.071Concrete gully trap 4" Each
19.072Glazed Pee trap 10 cm (4" dia) Each
19.073PVC grating 15 x 15 cm (6" x 6") Each
White Glazed earthenware Wash Hand Basins (22" x 16") (56
19.074 Each
cm x 40 cm) with padestal
19.075Wash Hand Basin (22" x 16") (56 cm x 40 cm)} without pedesta Each
19.076Coloured wash hand basin with pedestal (22" x 16") (56 cm x Each
19.077Coloured wash hand basin without pedestal (22" x 16") (56 cm Each
19.078European type water closet without seat and cover (coloured) Each
19.079European type water closet without seat and cover (white) Each
19.080Double seat and cover Bekelite Each
19.081Double seat and cover Plastic Each
White Glazed earthenware squater (Orisa pattern) WC
19.082 Each
combined with footrest
Coloured {Glazed earthenware squater (Orisa pattern) WC
19.083 Each
combined with footrest}
19.084Terazzo concrete water closet squater type Each
Glazed earthen ware W.C squater type with seperate foot
19.085 Each
rest (Orisa pattern)
19.086Urinal Glazed earthenware flat back Each
19.087Pillar cock chromium plated heavy duty 2 cm (") Each
19.088Pillar cock chromium plated heavy duty 1.5 cm (") Each
19.089Stop cock under ground 15 mm (") with C.P cover Each
19.090Stop cock chromium plated heavy duty 2 cm (") Each
19.091Stop cock chromium plated heavy duty 1.5 cm (") Each
19.092Swan neck cock single way chromium plated 1.5 cm (") Each
19.093Swan neck cock double way chromium plated 1.5 cm (") Each
19.094Swan neck cock three way chromium plated 1.5 cm (") Each
19.095Gas cock chromium plated oxidised (") single way Each
19.096Gas cock chromium plated oxidised (") double way Each
19.097Gas cock chromium plated oxidised (") three way Each
19.098Looking glass 5 mm thick 55 x 40 cm (22" x 16") Each
19.099Hanger hook with pullout rod Each
19.100Gun metal peat/gate valve (screwed) 15 mm (") dia Each
19.101Gun metal peat/gate valve (screwed) 20 mm (") dia Each
19.102Gun metal peat/gate valve (screwed) 25 mm (1") dia Each
19.103 Gun metal peat/gate valve (screwed) 30 mm (1") dia Each
19.104 Gun metal peat/gate valve (screwed) 40 mm (1") dia Each
19.105Gun metal peat/gate valve (screwed) 50 mm (2") dia Each
19.106Gun metal peat/gate valve (screwed) 65 mm (2") dia Each
19.107Gun metal peat/gate valve (screwed) 80 mm (3") dia Each
19.108Foot rest for squatter type W.C. Each
19.109Waste coupling with bracket and waste pipe Each
19.110Screw (75 mm) 3" long Each

Page 7
ITEM MATERIAL UNIT RATE
C.I. High level flushing cistern 13.63 litre or 3 gallon
19.111 Each
capacity including accessories
19.112C.I. High level flushing cistern I/C all accessaries (1 gall Each
19.113Soap dish coloured (glazed earthen weare) Each
19.114Plastic shelf with railing Each
19.115Bracket Each
19.1162 cm (") bib cock Each
19.1171.5 cm (") bib cock Each
19.118Union brass cock " (1.5 cm) Each
19.119Union brass cock " (2 cm) Each
19.120C.I floor trap including grating size 10 x 7.5 cm (4" x 3") Each
19.121Manhole cover 30 cm (12" dia) Each
19.122C.I. manhole cover with frame 45 cm (18" dia) Each
19.123C.I. manhole cover with frame 60 cm (24" dia) Each
19.124 C.P Bottle trap with waste pipe 3cm (11/4" dia) Each
19.125 C.P Bottle trap with waste pipe 4cm (11/2" dia) Each
19.126Nail with Cutter for angle iron brackets Each
19.127 Copper connection with assessories " dia Each
19.1281.5 cm (" dia) brass ball valve with assessaries Each
21.001C.I. gully grating 12" x 12" with hinged safety type (81 lbs Each
21.002Concrete gully trap 12" x 12" Each
21.003China ware trap with C.I screen Each
21.004Iron Bolt 12" Each
21.005C.I Ventilating Shaft tool 6" to 12" I/d 18' to 36' long Kg
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.006 Per Ft.
B) 300
RCC mmpipes
sewer (12")confirming
i/d to ASTM C-76-79 (class III wall
21.007 Per Ft.
B) 375
RCC mm pipes
sewer (15") i/d
confirming to ASTM C-76-79 (class III wall
21.008 Per Ft.
B)
RCC450 mm pipes
sewer (18") i/d
confirming to ASTM C-76-79 (class III wall
21.009 Per Ft.
B) 525 mm (21") i/d
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.010 Per Ft.
B)
RCC600 mm pipes
sewer (24") i/d
confirming to ASTM C-76-79 (class III wall
21.011 Per Ft.
B) 675
RCC mm pipes
sewer (27") i/d
confirming to ASTM C-76-79 (class III wall
21.012 Per Ft.
B) 750
RCC mm pipes
sewer (30") i/d
confirming to ASTM C-76-79 (class III wall
21.013 Per Ft.
B) 825
RCC mm pipes
sewer (33") i/d
confirming to ASTM C-76-79 (class III wall
21.014 Per Ft.
B) 900 mm (36") i/d
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.015 Per Ft.
B) 1070 mm (42") i/d
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.016 Per Ft.
B) 1220 mm (48") i/d
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.017 Per Ft.
B) 1370 mm (54") i/d
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.018 Per Ft.
B) 1520 mm (60") i/d
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.019 Per Ft.
B) 1680 mm (66") i/d
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.020 Per Ft.
B) 1830 mm (72") i/d
RCC Pipes conforming (to BS 5911 part I, 1981 class 'L')
21.021 Rft
'100 mm (4")
RCC Pipes i/d
conforming (to BS 5911 part I, 1981 class 'L')
21.022 Rft
'150Pipes
RCC mm (6") i/d
conforming (to BS 5911 part I, 1981 class 'L')
21.023 Rft
225 mm (9") i/d
Non/reinforced concrete pipe 100 mm (4") dia conforming to
21.024 Rft
ASTM C-14-73 Class I
Non/reinforced concrete pipe 150 mm (6") dia conforming to
21.025 Rft
ASTM C-14-73 Class I
Non/reinforced concrete pipe 200 mm (8") dia conforming to
21.026 Rft
ASTM C-14-73 Class I
Non/reinforced concrete pipe 225 mm (9") dia conforming to
21.027 Rft
ASTM C-14-73 Class I
Non/reinforced concrete pipe 250 mm (10") dia conforming to
21.028 Rft
ASTM C-14-73 Class I
dia RCC Sewer pipe 300 mm (12") Conforming to ASTM C-76-79
21.029 Per Ft.
(ClassII
RCC Sewerwall
pipe'B')
'375 cc (15") dia Conforming to ASTM C-76-79
21.030 Per Ft.
(ClassII
RCC Sewerwall
pipe'B')
450 mm (18") dia Conforming to ASTM C-76-79
21.031 Per Ft.
(ClassII wall 'B')
RCC Sewer pipe 525 mm (21") dia Conforming to ASTM C-76-79
21.032 Per Ft.
(ClassII
RCC Sewerwall
pipe'B')
600 mm (24") dia Conforming to ASTM C-76-79
21.033 Per Ft.
(ClassII
RCC Sewer pipe'B')
wall 675 mm (27") dia Conforming to ASTM C-76-79
21.034 Per Ft.
(ClassII
RCC Sewerwall
pipe'B')
750 mm (30") dia Conforming to ASTM C-76-79
21.035 Per Ft.
(ClassII
RCC Sewerwall
pipe'B')
825 mm (33") dia Conforming to ASTM C-76-79
21.036 Per Ft.
(ClassII
RCC Sewerwall
pipe'B')
900 mm (36") dia Conforming to ASTM C-76-79
21.037 Per Ft.
(ClassII wall 'B')
RCC Sewer pipe 1070 mm (42") dia Conforming to ASTM C-76-79
21.038 Per Ft.
(ClassII wall 'B')
RCC Sewer pipe 1220 mm (48") dia Conforming to ASTM C-76-79
21.039 Per Ft.
(ClassII wall 'B')
RCC Sewer pipe 1370 mm (54") dia Conforming to ASTM C-76-79
21.040 Per Ft.
(ClassII wall 'B')

Page 8
ITEM MATERIAL UNIT RATE
RCC Sewer pipe 1520 mm (60") dia Conforming to ASTM C-76-79
21.041 Per Ft.
(ClassII wall 'B')
RCC Sewer pipe 1680 mm (66") dia Conforming to ASTM C-76-79
21.042 Per Ft.
(ClassII wall 'B')
RCC Sewer pipe 1830 mm (72") dia Conforming to ASTM C-76-79
21.043 Per Ft.
(ClassII wall 'B')
Per Inch
21.044Rubber Ring dia of
pipe
RCC Sewer pipe 300 mm (12") dia Conforming to ASTM C-76-79
21.045 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 380 mm (15") dia Conforming to ASTM C-76-79
21.046 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 460 mm (18") dia Conforming to ASTM C-76-79
21.047 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 535 mm (21") dia Conforming to ASTM C-76-79
21.048 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 610 mm (24") dia Conforming to ASTM C-76-79
21.049 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 685 mm (27") dia Conforming to ASTM C-76-79
21.050 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 760 mm (30") dia Conforming to ASTM C-76-79
21.051 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 800 mm (33") dia Conforming to ASTM C-76-79
21.052 Per Ft.
(class IV wall 'B'
RCC Sewer pipe 915 mm (36") dia Conforming to ASTM C-76-79
21.053 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 1070 mm (42") dia Conforming to ASTM C-76-79
21.054 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 1220 mm (48") dia Conforming to ASTM C-76-79
21.055 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 1370 mm (54") dia Conforming to ASTM C-76-79
21.056 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 1520 mm (60") dia Conforming to ASTM C-76-79
21.057 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 1680 mm (66") dia Conforming to ASTM C-76-79
21.058 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 1830 mm (72") dia Conforming to ASTM C-76-79
21.059 Per Ft.
(class IV wall 'B')
21.060Steel bolt 12" long Each
21.061Foundation bolts & nuts " dia 2' long . Each
21.062Rubber sheet 1/8" thick P.Kg
21.063Foundation bolts & nuts " dia 1' long Each
21.064Foundation bolts " dia 2' long. Each
21.065 Foundation bolts 7/8" dia 2' long. Each
22.001Winch including cost of tripod, tackle etc. for sinking of w Each
22.002Steel rope 3/4" dia Per Rft.
22.003One cusic capacity pumping set for dewatering Each
22.004Sleeper Each
22.005Bolts & Nuts P.Kg
A.C pressure pipe '80mm (3") dia Class 'B' BSS with comet
23.001 Per Ft.
joint and rubber rings
A.C pressure pipe 100 mm (4") dia Class 'B' BSS with comet
23.002 Per Ft.
joint and rubber rings.
A.C pressure pipe 150 mm (6") dia Class 'B' BSS with comet
23.003 Per Ft.
joint and rubber rings.
A.C pressure pipe 200 mm (8") dia Class 'B' BSS with comet
23.004 Per Ft.
joint and rubber rings.
A.C pressure pipe 250 mm (10") dia Class 'B' BSS with comet
23.005 Per Ft.
joint and rubber rings.
A.C pressure pipe 300 mm (12") dia Class 'B' BSS with comet
23.006 Per Ft.
joint and rubber rings.
A.C pressure pipe 350 mm (14") dia Class 'B' BSS with comet
23.007 Per Ft.
joint and rubber rings.
A.C pressure pipe 400 mm (16") dia Class 'B' BSS with comet
23.008 Per Ft.
joint and rubber rings.
A.C pressure pipe 450 mm (18") dia Class 'B' BSS with comet
23.009 Per Ft.
joint and rubber rings.
A.C pressure pipe 500 mm (20") dia Class 'B' BSS with comet
23.010 Per Ft.
joint and rubber rings.
A.C pressure pipe 600 mm (24") dia Class 'B' BSS with comet
23.011 Per Ft.
joint and rubber rings.
A.C pressure pipe 80 mm (3") dia Class 'C' BSS with comet
23.012 Per Ft.
joint and rubber rings
A.C pressure pipe 100 mm (4") dia Class 'C' BSS with comet
23.013 Per Ft.
joint and rubber rings.

Page 9
ITEM MATERIAL UNIT RATE
A.C pressure pipe 150 mm (6") dia Class 'C' BSS with comet
23.014 Per Ft.
joint and rubber rings.
A.C pressure pipes 200 mm (8") dia Class 'C' BSS with comet
23.015 Per Ft.
joint and rubber rings.
A.C pressure pipe 250 mm (10") dia Class 'C' BSS with comet
23.016 Per Ft.
joint and rubber rings.
A.C pressure pipe 300 mm (12") dia Class 'C' BSS with comet
23.017 Per Ft.
joint and rubber rings.
A.C pressure pipe 350 mm (14") dia Class 'C' BSS with comet
23.018 Per Ft.
joint and rubber rings.
A.C pressure pipe 400 mm (16") dia Class 'C' BSS with comet
23.019 Per Ft.
joint and rubber rings.
A.C pressure pipe 450 mm (18") dia Class 'C' BSS with comet
23.020 Per Ft.
joint and rubber rings.
A.C pressure pipe '500 mm (20") dia Class 'C' BSS with
23.021 Per Ft.
comet joint and rubber rings.
A.C pressure pipe 600 mm (24") dia Class 'C' BSS with comet
23.022 Per Ft.
joint and rubber rings.
A.C pressure pipe 80 mm (3") dia Class 'D' BSS with comet
23.023 Per Ft.
joint and rubber rings
A.C pressure pipe 100 mm (4") dia Class 'D' BSS with comet
23.024 Per Ft.
joint and rubber rings.
A.C pressure pipe 150 mm (6") dia Class 'D' BSS with comet
23.025 Per Ft.
joint and rubber rings.
A.C pressure pipe 200 mm (8") dia Class 'D' BSS with comet
23.026 Per Ft.
joint and rubber rings.
A.C pressure pipe 250 mm (10") dia Class 'D' BSS with comet
23.027 Per Ft.
joint and rubber rings.
A.C pressure pipe 300 mm (12") dia Class 'D' BSS with comet
23.028 Per Ft.
joint and rubber rings.
A.C pressure pipe 350 mm (14") dia Class 'D' BSS with comet
23.029 Per Ft.
joint and rubber rings.
A.C pressure pipe 400 mm (16") dia Class 'D' BSS with comet
23.030 Per Ft.
joint and rubber rings.
A.C pressure pipe 450 mm (18") dia Class 'D' BSS with comet
23.031 Per Ft.
joint and rubber rings.
A.C pressure pipe 500 mm (20") dia Class 'D' BSS with comet
23.032 Per Ft.
joint and rubber rings.
23.033G.I. pressure pipe 15 mm (") dia BSS-1387 - 1967 (light qua Per Ft.
23.034G.I. pressure pipe 20 mm (") dia BSS-1387 - 1967 (light qua Per Ft.
23.035G.I. pressure pipe 25 mm (1") dia BSS-1387 - 1967 (light qua Per Ft.
23.036G.I. pressure pipe 30 mm (1") dia BSS-1387 - 1967 (light qu Per Ft.
23.037G.I. pressure pipe 40 mm (1") dia BSS-1387 - 1967 (light qu Per Ft.
23.038G.I. pressure pipe 50 mm (2") dia BSS-1387 - 1967 (light qua Per Ft.
23.039G.I. pressure pipe 65 mm (2") dia BSS-1387 - 1967 (light qu Per Ft.
23.040G.I. pressure pipe 80 mm (3") dia BSS-1387 - 1967 (light qua Per Ft.
23.041G.I. pressure pipe 100 mm (4") dia BSS-1387 - 1967 (light qu Per Ft.
23.042G.I. pressure pipe 15 mm (") dia BSS-1387 - 1967 (medium qu Per Ft.
23.043G.I. pressure pipe 20 mm (") dia BSS-1387 - 1967 (medium q Per Ft.
23.044G.I. pressure pipe 25 mm (1") dia BSS-1387 - 1967 (medium q Per Ft.
23.045G.I. pressure pipe 30 mm (1") dia BSS-1387 - 1967 (medium Per Ft.
23.046G.I. pressure pipe 40 mm (1") dia BSS-1387 - 1967 (medium Per Ft.
23.047G.I. pressure pipe 50 mm (2") dia BSS-1387 - 1967 (medium q Per Ft.
23.048G.I. pressure pipe 65 mm (2") dia BSS-1387 - 1967 (medium Per Ft.
23.049G.I. pressure pipe 75 mm (3") dia BSS-1387 - 1967 (medium q Per Ft.
23.050G.I. pressure pipe 100 mm (4") dia BSS-1387 - 1967 (medium Per Ft.
23.051G.I. pressure pipe 125 mm (5") dia BSS-1387 - 1967 (medium Per Ft.
23.052G.I. pressure pipe 150 mm (6") dia BSS-1387 - 1967 (Medium q Per Ft.
23.053G.I. pressure pipe 15 mm (") dia BSS-1387 - 1967 (heavy qua Per Ft.
23.054G.I. pressure pipe 20 mm (") dia BSS-1387 - 1967 (heavy qua Per Ft.
23.055G.I. pressure pipe 25 mm (1") dia BSS-1387 - 1967 (heavy qua Per Ft.
23.056G.I. pressure pipe 30 mm (1") dia BSS-1387 - 1967 (heavy qu Per Ft.
23.057G.I. pressure pipe 40 mm (1") dia BSS-1387 - 1967 (heavy qu Per Ft.
23.058G.I. pressure pipe 50 mm (2") dia BSS-1387 - 1967 (heavy qua Per Ft.
23.059G.I. pressure pipe 65 mm (2") dia BSS-1387 - 1967 (heavy qu Per Ft.
23.060G.I. pressure pipe 75 mm (3") dia BSS-1387 - 1967 (heavy qua Per Ft.
23.061G.I. pressure pipe 100 mm (4") dia BSS-1387 - 1967 (heavy qu Per Ft.
23.062G.I. pressure pipe '125 mm (5") dia BSS-1387 - 1967 (heavy q Per Ft.
23.063G.I. pressure pipe 150 mm (6") dia BSS-1387 - 1967 (heavy qu Per Ft.
23.064 Jointing Material of Socket Joint for 1/2" dia G.I. Pipe for Per % Rft.
23.065 Jointing Material of Socket Joint for 3/4" dia G.I. Pipe fo Per % Rft.
23.066Jointing Material of Socket Joint for 1" dia G.I. Pipe for 1Per % Rft.
23.067 Jointing Material of Socket Joint for 11/4" dia G.I. Pipe fo Per % Rft.
23.068 Jointing Material of Socket Joint for 11/2" dia G.I. Pipe fo Per % Rft.
Page 10
ITEM MATERIAL UNIT RATE
23.069Jointing Material of Socket Joint for 2" dia G.I. Pipe for 1Per % Rft.
23.070 Jointing Material of Socket Joint for 21/2" dia G.I. Pipe fo Per % Rft.
23.071Jointing Material of Socket Joint for 3" dia G.I. Pipe for 1Per % Rft.
23.072Jointing Material of Socket Joint for 4" dia G.I. Pipe for 1Per % Rft.
23.073Jointing Material of Socket Joint for 5" dia G.I. Pipe for 1Per % Rft.
23.074Jointing Material of Socket Joint for 6" dia G.I. Pipe for 1Per % Rft.
23.075Testing charges of G.I. Pipes for 1" dia Per % Rft.
23.076Testing charges of G.I. Pipes for 1" dia Per % Rft.
23.077Testing charges of G.I. Pipes for 1" dia Per % Rft.
23.078Testing charges of G.I. Pipes for 2" dia Per % Rft.
23.079Testing charges of G.I. Pipes for 2" dia Per % Rft.
23.080Testing charges of G.I. Pipes for 3" dia Per % Rft.
23.081Testing charges of G.I. Pipes for 4" dia Per % Rft.
23.082Testing charges of G.I. Pipes for 5" dia Per % Rft.
23.083Testing charges of G.I. Pipes for 6" dia Per % Rft.
23.08450 mm (2") dia 3 mm (1/8") thick M.S blind pipes Per Ft.
23.08580 mm (3") dia 3 mm (1/8") thick M.S blind pipes Per Ft.
23.086100 mm (4") dia 3 mm (1/8") thick M.S blind pipes Per Ft.
23.087125 mm (5") dia 5 mm (3/16") thick M.S blind pipes Per Ft.
23.088150 mm (6") dia 5 mm (3/16") thick M.S blind pipes Per Ft.
23.089175 mm (7") dia 5 mm (3/16") thick M.S blind pipe Per Ft.
23.090200 mm (8") dia 5 mm (3/16") thick M.S blind pipes Per Ft.
23.091225 mm (9") dia 5 mm (3/16") thick M.S blind pipes Per Ft.
23.092250 mm (10") dia 6 mm (3/16") thick {M.S blind pipe Per Ft.
23.093300 mm (12") dia 6 mm (3/16") thick {M.S blind pipe Per Ft.
23.094375 mm (15") dia 6 mm (3/16") thick {M.S blind pipes Per Ft.
23.095450 mm (18") dia 6 mm (3/16") thick {M.S blind pipes Per Ft.
23.096500 mm (20") dia 6 mm (3/16") thick {M.S blind pipes Per Ft.
23.097550 mm (22") dia 6 mm (3/16") thick {M.S blind pipes Per Ft.
80-600 mm (3"-24") dia {C.I specials (with Commet joint and
23.098 Per Kg
rubber ring) For A.C Pipes}
23.09980-450 mm (3"- 18") dia C.I Specials of BSS Class B with S Per Kg
23.10080-450 mm (3"- 18") dia C.I Specials of BSS Class B With Fla Per Kg
23.10180-450 mm (3"- 18") dia C.I Specials of BSS Class B with Tyt Per Kg
23.10280 mm (3") dia Sluice Valves of BSS for AC & CI pipe line Each
23.103100 mm (4") dia Sluice Valves of BSS for AC & CI pipe line Each
23.104125 mm (5") dia Sluice Valves of BSS for AC & CI pipe line Each
23.105150 mm (6") dia Sluice Valves of BSS for AC & CI pipe line Each
23.106200 mm (8") dia Sluice Valves of BSS for AC & CI pipe line Each
23.107250 mm (10") dia Sluice Valves of BSS for AC & CI pipe line Each
23.108300 mm (12") dia Sluice Valves of BSS for AC & CI pipe line Each
23.109375 mm (14") dia Sluice Valves of BSS for AC & CI pipe line Each
23.110450 mm (18") dia Sluice Valves of BSS for AC & CI pipe line Each
23.111Single Air Valve 75 mm (3") Each
23.112Double Air Valve 75 mm (3") Each
23.113Fire Hydrant BSS 65 mm (2") Each
23.11480 mm (3") dia P.V.C tapperd core BSS Class 'B' Each
23.115100 mm (4") dia P.V.C tapperd core BSS Class 'B' Each
23.116125 mm (5") dia P.V.C tapperd core BSS Class 'B' Each
23.117150 mm (6") dia P.V.C tapperd core BSS Class 'B' Each
23.118200 mm (8") dia P.V.C tapperd core BSS Class 'B' Each
23.119250 mm (10") dia P.V.C tapperd core BSS Class 'B' Each
23.120300 mm (12") dia P.V.C tapperd core BSS Class 'B' Each
23.121350 mm (14") dia P.V.C tapperd core BSS Class 'B' Each
1
23.122 15 mm (1 /4") dia P.V.C tapperd core BSS Class 'D' Each
23.12340 mm (1") dia P.V.C tapperd core BSS Class 'D' Each
23.12450 mm (2") P.V.C tapperd core BSS Class 'D' Each
23.12575 mm (3") dia P.V.C Bends BSS class 'B' Each
23.126100 mm (4") dia P.V.C Bends BSS class 'B' Each
23.127100 mm (5") dia P.V.C Bends BSS class 'B' Each
23.128150 mm (6") dia P.V.C Bends BSS class 'B' Each
23.12930 mm (1") dia P.V.C Bends BSS class 'D' Each
23.13040 mm (1") dia P.V.C Bends BSS class 'D' Each
23.13150 mm (2") dia P.V.C Bends BSS class 'D' Each
23.13280 mm (3") dia P.V.C Bends BSS class 'D' Each
23.133100 mm (4") dia P.V.C Bends BSS class 'D' Each
23.134125 mm (5") dia P.V.C Bends BSS class 'D' Each
23.135150 mm (6") dia P.V.C Bends BSS class 'D' Each
23.13680 mmm (3") dia P.V.C Tee BSS Class 'B' Each
23.137100 mm (4") dia P.V.C Tee BSS Class 'B' Each
23.138125 mm (5") dia P.V.C Tee BSS Class 'B' Each
23.139150 mm (6") dia P.V.C Tee BSS Class 'B' Each
23.140200 mm (8") dia P.V.C Tee BSS Class 'B' Each

Page 11
ITEM MATERIAL UNIT RATE
23.141250 mm (10") dia P.V.C Tee BSS Class 'B' Each
23.142300 mm (12") dia P.V.C Tee BSS Class 'B' Each
23.143350 mm (14") dia P.V.C Tee BSS Class 'B' Each
23.14430 mm (1") dia P.V.C Tee BSS Class 'D' Each
23.14540 mm (1") dia P.V.C Tee BSS Class 'D' Each
23.14650 mm (2") dia P.V.C Tee BSS Class 'D' Each
23.14780 mm (3") dia P.V.C Tee BSS Class 'D' Each
23.148100 mm (4") dia P.V.C Tee BSS Class 'D' Each
23.149125 mm (5") dia P.V.C Tee BSS Class 'D' Each
23.150150 mm (6") dia P.V.C Tee BSS Class 'D' Each
23.15180 mmm (3") dia P.V.C sockets BSS Class 'B' Each
23.152100 mm (4") dia P.V.C sockets BSS Class 'B' Each
23.153125 mm (5") dia P.V.C sockets BSS Class 'B' Each
23.154150 mm (6") dia P.V.C sockets BSS Class 'B' Each
23.155200 mm (8") dia P.V.C sockets BSS Class 'B' Each
23.156250 mm (8") dia P.V.C sockets BSS Class 'B' Each
23.157300 mm (12") dia P.V.C sockets BSS Class 'B' Each
23.158350 mm (14") dia P.V.C sockets BSS Class 'B' Each
23.15930 mm (1") dia P.V.C sockets BSS Class 'D' Each
23.16040 mm (1") dia P.V.C sockets BSS Class 'D' Each
23.16150 mm (2") dia P.V.C sockets BSS Class 'D' Each
23.16280 mm (3") dia P.V.C sockets BSS Class 'D' Each
23.163100 mm (4") dia P.V.C sockets BSS Class 'D' Each
23.164125 mm (5") dia P.V.C sockets BSS Class 'D' Each
23.165150 mm (6") dia P.V.C sockets BSS Class 'D' Each
23.166Bleaching powder/chlorine Per Kg
23.16750 mm (2") dia 4 mm (5/32") Brass strainer incluidng specia Per Ft.
23.16875 mm (3") dia 4 mm (5/32") Brass strainer incluidng specia Per Ft.
23.169100 mm (4") dia 5 mm (3/16") Brass strainer incluidng spec Per Ft.
23.170125 mm (5") dia 5 mm (3/16") Brass strainer incluidng speci Per Ft.
23.171150 mm (6") dia 5 mm (3/16") Brass strainer incluidng speci Per Ft.
23.172175 mm (7") dia 5 mm (3/16") Brass strainer incluidng speci Per Ft.
23.173200 mm (8") dia 5 mm (3/16") Brass strainer incluidng speci Per Ft.
23.174225 mm (9") dia 5 mm (3/16") Brass strainer incluidng speci Per Ft.
23.175250 mm (10") dia 5 mm (3/16") Brass strainer incluidng spec Per Ft.
23.176250 mm (10") dia 6 mm (") Brass strainer incluidng special Per Ft.
23.177300 mm (12") dia 6 mm (") Brass strainer incluidng special Per Ft.
23.178375 mm (15") dia 6 mm (") Brass strainer incluidng special Per Ft.
23.179450 mm (18") dia 6 mm (") Brass strainer incluidng special Per Ft.
23.180500 mm (20") dia 6 mm (") Brass strainer incluidng special Per Ft.
23.181550 mm (22") dia 6 mm (") Brass strainer incluidng special Per Ft.
23.18275 mm (3") dia P.V.C strainer Class 'B' Per Ft.
23.183100 mm (4") dia P.V.C strainer Class 'B' Per Ft.
23.184125 mm (5") dia 60 cm P.V.C strainer Class 'B' Per Ft.
23.185150 mm (6") dia 60 cm P.V.C strainer Class 'B' Per Ft.
23.186200 mm (7") dia 60 cm P.V.C strainer Class 'B' Per Ft.
23.187250 mm (8") dia 60 cm P.V.C strainer Class 'B' Per Ft.
23.188300 mm (9") dia 60 cm P.V.C strainer Class 'B' Per Ft.
23.189350 mm (10") dia 60 cm P.V.C strainer Class 'B' Per Ft.
23.190PVC Stainer Class D 1" dia (30mm) Per Ft.
23.191PVC Stainer Class D 1 dia (40 mm) Per Ft.
23.192PVC Stainer Class D 2" dia (50 mm) Per Ft.
23.193PVC Stainer Class D 3" dia (75 mm) Per Ft.
23.194PVC Stainer Class D 4" dia (100 mm) Per Ft.
23.195PVC Stainer Class D 5" dia (125 mm) Per Ft.
23.196PVC Stainer Class D 6" dia (150 mm) Per Ft.
23.19750 mm (2") i/d, Bail Plug-mild steel Per Ft.
23.19875 mm (3") i/d Bail Plug-mild steel Per Ft.
23.199100 mm (4") i/dBail Plug-mild steel Per Ft.
23.200125 mm (5") i/d Bail Plug-mild steel Per Ft.
23.201150 mm (6") i/d Bail Plug-mild steel Per Ft.
23.202175 mm (7") i/d Bail Plug-mild steel Per Ft.
23.203200 mm (8") i/d Bail Plug-mild steel Per Ft.
23.204225 mm (9") i/d Bail Plug-mild steel Per Ft.
23.205250 mm (10") i/d Bail Plug-mild steel Per Ft.
23.206300 mm (12") i/d Bail Plug-mild steel Per Ft.
23.207375 mm (15") i/d Bail Plug-mild steel Per Ft.
23.208450 mm (18") i/d Bail Plug-mild steel Per Ft.
23.209500 mm (20") i/d Bail Plug-mild steel Per Ft.
23.210550 mm (22") i/d Bail Plug-mild steel Per Ft.
23.21175 mm (3") dia PVC BSS Class 'B' Bail Plug Each
23.212100 mm (4") dia PVC BSS Class 'B' Bail Plug Each
23.213125 mm (5") dia PVC BSS Class 'B' Bail Plug Each

Page 12
ITEM MATERIAL UNIT RATE
23.214150 mm (6") dia PVC BSS Class 'B' Bail Plug Each
23.215200 mm (8") dia PVC BSS Class 'B' Bail Plug Each
23.216250 mm (10") dia PVC BSS Class 'B' Bail Plug Each
23.217300 mm (12") dia PVC BSS Class 'B' Bail Plug Each
23.218350 mm (14") dia PVC BSS Class 'B' Bail Plug Each
23.21930 mm (1") dia P.V.C. Class 'D' Bail Plug Each
23.22040 mm (1") dia P.V.C. Class 'D' Bail Plug Each
23.22150 mm (2") dia P.V.C. Class 'D' Bail Plug Each
23.22280 mm (3") dia P.V.C. Class 'D' Bail Plug Each
23.223100 mm (4") dia P.V.C. Class 'D' Bail Plug Each
23.224125 mm (5") dia P.V.C. Class 'D' Bail Plug Each
23.225150 mm (6") dia P.V.C. Class 'D' Bail Plug Each
23.226G.I. pipe with flanged joint 1" dia 40mm (Heavy Quality) Per Ft.
23.227G.I. pipe with G.I. flanged joint 2" dia 50 mm (Heavy Qualit Per Ft.
23.228G.I. pipe with GI. flanged joint 2" dia 65 mm (Heavy Qualit Per Ft.
23.229G.I. pipe with G.I. flanged joint 3" dia 75 mm (Heavy Quali Per Ft.
23.230G.I. pipe with G.I. flanged joint 4" dia 100 mm (Heavy Quali Per Ft.
23.231G.I. pipe with G.I. flanged joint 5" dia 125 mm (Heavy Quali Per Ft.
23.232G.I. pipe with G.I. flanged joint 6" dia 150 mm (Heavy Quali Per Ft.
23.233G.I. pipe with C.I. flanged joint 1" dia 40mm (Medium Quali Per Ft.
23.234G.I. pipe with C.I. flanged joint 2" dia 50 mm (Medium Quali Per Ft.
23.235G.I. pipe with C.I. flanged joint 2" dia 65 mm (Medium Qual Per Ft.
23.236G.I. pipe with C.I. flanged joint 3" dia 75 mm (Medium Qual Per Ft.
23.237G.I. pipe with C.I. flanged joint 4" dia 100 mm (Medium Qual Per Ft.
23.238G.I. pipe with C.I. flanged joint 5" dia 125 mm (Medium Qual Per Ft.
23.239G.I. pipe with C.I. flanged joint 6" dia 150 mm (Medium Qual Per Ft.
23.24075 mm Sluice Valve for A.C. Pipe Line with commet joint & ru Each
23.241100 mm Sluice Valve for A.C. Pipe Line with commet joint & r Each
23.242150 mm Sluice Valve for A.C. Pipe Line with commet joint & r Each
23.243200 mm Sluice Valve for A.C. Pipe Line with commet joint & r Each
23.244250 mm Sluice Valve for A.C. Pipe Line with commet joint & r Each
23.245300 mm Sluice Valve for A.C. Pipe Line with commet joint & r Each
23.246400 mm Sluice Valve for A.C. Pipe Line with commet joint & r Each
23.247450 mm Sluice Valve for A.C. Pipe Line with commet joint & r Each
23.248Lock for wooden box for pressuring samples off strata from b Each
23.249Cost of Lubricant for PVC Pipe Per Kg.
23.250Steel Handle 4" (100mm) Each
23.25175 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.252100 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.253125 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.254150 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.255200 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.256250 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.257300 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.258350 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.25930 mm PVC Blind/Pressure Pipe Class "D" Per Ft.
23.26040 mm PVC Blind/Pressure Pipe Class "D" Per Ft.
23.26150 mm PVC Blind/Pressure Pipe Class "D" Per Ft.
23.26275 mm PVC Blind/Pressure Pipe Class "D" Per Ft.
23.263100 mm PVC Blind/Pressure Pipe Class "D" Per Ft.
23.264125 mm PVC Blind/Pressure Pipe Class "D" Per Ft.
23.265150 mm PVC Blind/Pressure Pipe Class "D" Per Ft.
23.266Loading expenses for pipes P. Day
23.267(Petty store) bolts & nuts etc. for 5" dia bore Per Ft.
23.268(Petty store) bolts & nuts etc. for 6" dia bore Per Ft.
23.269(Petty store) bolts & nuts etc. for 8" dia bore Per Ft.
23.270(Petty store) bolts & nuts etc. for10" dia bore Per Ft.
23.271(Petty store) bolts & nuts etc. for 12" dia bore Per Ft.
23.272(Petty store) bolts & nuts etc. for15" dia bore Per Ft.
23.273(Petty store) bolts & nuts etc. for 18" dia bore Per Ft.
23.274Hire charges of boring material, installation & Carriage (3 Per Ft.
23.275Hire charges of boring material, installation & Carriage (4 Per Ft.
23.276Hire charges of boring material, installation & Carriage (5 Per Ft.
23.277Hire charges of boring material, installation & Carriage (6 Per Ft.
23.278Hire charges of boring material, installation & Carriage (8 Per Ft.
23.279Hire charges of boring material, installation & Carriage (10 Per Ft.
23.280Hire charges of boring material, installation & Carriage (12 Per Ft.
23.281Hire charges of boring material, installation & Carriage (15 Per Ft.
23.282Hire charges of boring material, installation & Carriage (18 Per Ft.
Hire charges of boring material, installation & Carriage
23.283 Per Ft.
for (5" dia bore) from 100.10 to 200 Ft. depth
Hire charges of boring material, installation & Carriage
23.284 Per Ft.
for (6" dia bore) from 100.10 to 200 Ft. depth

Page 13
ITEM MATERIAL UNIT RATE
Hire charges of boring material, installation & Carriage
23.285 Per Ft.
for (8" dia bore) from 100.10 to 200 Ft. depth
Hire charges of boring material, installation & Carriage
23.286 Per Ft.
for (10" dia bore) from 100.10 to 200 Ft. depth
Hire charges of boring material, installation & Carriage
23.287 Per Ft.
for (12" dia bore) from 100.10 to 200 Ft. depth
Hire charges of boring material, installation & Carriage
23.288 Per Ft.
for (15" dia bore) from 100.10 to 200 Ft. depth
Hire charges of boring material, installation & Carriage
23.289 Per Ft.
for (18" dia bore) from 100.10 to 200 Ft. depth
Hire charges of boring material, installation & Carriage
23.290 Per Ft.
for (5" dia bore) from 200.10 to 300 Ft. depth
Hire charges of boring material, installation & Carriage
23.291 Per Ft.
for (6" dia bore) from 200.10 to 300 Ft. depth
Hire charges of boring material, installation & Carriage
23.292 Per Ft.
for (8" dia bore) from 200.10 to 300 Ft. depth
Hire charges of boring material, installation & Carriage
23.293 Per Ft.
for (10" dia bore) from 200.10 to 300 Ft. depth
Hire charges of boring material, installation & Carriage
23.294 Per Ft.
for (12" dia bore) from 200.10 to 300 Ft. depth
Hire charges of boring material, installation & Carriage
23.295 Per Ft.
for (15" dia bore) from 200.10 to 300 Ft. depth
Hire charges of boring material, installation & Carriage
23.296 Per Ft.
for (18" dia bore) from 200.10 to 300 Ft. depth
Hire charges of boring material, installation & Carriage
23.297 Per Ft.
for (8" dia bore) from 300.10 to 400 Ft. depth
Hire charges of boring material, installation & Carriage
23.298 Per Ft.
for (10" dia bore) from 300.10 to 400 Ft. depth
Hire charges of boring material, installation & Carriage
23.299 Per Ft.
for (12" dia bore) from 300.10 to 400 Ft. depth
Hire charges of boring material, installation & Carriage
23.300 Per Ft.
for (15" dia bore) from 300.10 to 400 Ft. depth
Hire charges of boring material, installation & Carriage
23.301 Per Ft.
for (18" dia bore) from 300.10 to 400 Ft. depth
23.302Repair charges of T&P for 5" dia bore hole Per Ft.
23.303Repair charges of T&P for 6" dia bore hole Per Ft.
23.304Repair charges of T&P for 8" dia bore hole Per Ft.
23.305Repair charges of T&P for 10" dia bore hole Per Ft.
23.306Repair charges of T&P for 12" dia bore hole Per Ft.
23.307Repair charges of T&P for 15" dia bore hole Per Ft.
23.308Repair charges of T&P for 18" dia bore hole Per Ft.
23.309Solvent for PVC Strainer 3" dia (Class B) Per Ft.
23.310Solvent for PVC Strainer 4" - 5" dia (Class B) Per Ft.
23.311Solvent for PVC Strainer 6" dia (Class B) Per Ft.
23.312Solvent for PVC Strainer 8" - 10" dia (Class B) Per Ft.
23.313Solvent for PVC Strainer 12" - 14" dia (Class B) Per Ft.
23.314Solvent for PVC Strainer 1" dia (Class D) Per Ft.
23.315Solvent for PVC Strainer 1" dia (Class D) Per Ft.
23.316Solvent for PVC Strainer 2" dia (Class D) Per Ft.
23.317Solvent for PVC Strainer 3" dia (Class D) Per Ft.
23.318Solvent for PVC Strainer 4" dia (Class D) Per Ft.
23.319Solvent for PVC Strainer 5" dia (Class D) Per Ft.
23.320Solvent for PVC Strainer 6" dia (Class D) Per Ft.
23.321Solvent for PVC Bail Plug 3" dia (Class B) Each
23.322Solvent for PVC Bail Plug 4" dia (Class B) Each
23.323Solvent for PVC Bail Plug 5" dia (Class B) Each
23.324Solvent for PVC Bail Plug 6" dia (Class B) Each
23.325Solvent for PVC Bail Plug 8" dia (Class B) Each
23.326Solvent for PVC Bail Plug 10" dia (Class B) Each
23.327Solvent for PVC Bail Plug 12" dia (Class B) Each
23.328Solvent for PVC Bail Plug 14" dia (Class B) Each
23.329Solvent for PVC Bail Plug 1" dia (Class D) Each
23.330Solvent for PVC Bail Plug 1" dia (Class D) Each
23.331Solvent for PVC Bail Plug 2" dia (Class D) Each
23.332Solvent for PVC Bail Plug 3" dia (Class D) Each
23.333Solvent for PVC Bail Plug 4" dia (Class D) Each
23.334Solvent for PVC Bail Plug 5" dia (Class D) Each
23.335Solvent for PVC Bail Plug 6" dia (Class D) Each
23.336Testing and Disinfecting of PVC Pipe 3" dia 100 Ft.
23.337Testing and Disinfecting of PVC Pipe 4" dia 100 Ft.
23.338Testing and Disinfecting of PVC Pipe 5" dia 100 Ft.
23.339Testing and Disinfecting of PVC Pipe 6" dia 100 Ft.
23.340Testing and Disinfecting of PVC Pipe 8" dia 100 Ft.

Page 14
ITEM MATERIAL UNIT RATE
23.341Testing and Disinfecting of PVC Pipe 10" dia 100 Ft.
23.342Testing and Disinfecting of PVC Pipe 12" dia 100 Ft.
23.343Testing and Disinfecting of PVC Pipe 14" dia 100 Ft.
23.344Testing and Disinfecting of G.I Pipe 40mm (1") dia 100 Ft.
23.345Testing and Disinfecting of G.I Pipe 50mm (2") dia 100 Ft.
23.346Testing and Disinfecting of G.I Pipe 63mm (2") dia 100 Ft.
23.347Testing and Disinfecting of G.I Pipe 75mm (3") dia 100 Ft.
23.348Testing and Disinfecting of G.I Pipe 100mm (4") dia 100 Ft.
23.349Testing and Disinfecting of G.I Pipe 125mm (6") dia 100 Ft.
23.350Testing and Disinfecting of G.I Pipe 150mm (7") dia 100 Ft.
23.351Disc for bail plugs P. Kg.
23.352Testing and Disinfecting of G.I Pipe P. Lbs
23.353Bottle 2 lbs capacity Each
23.35475 mm to 450 mm dia CI flanges for pipes P. Kg.
23.355Cost of C.I. Flanges for Pipe 100 cwt
23.356Welding Charges of spigot or socket, flanged or tyton ends er Inch Bore
23.357Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.358Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.359Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.360Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.361Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.362Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.363Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.364Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.365Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.366Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.367Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.368Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.369Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.370Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.371Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.372M.S. Bolt & Nut 6" to 22" dia bore hole bail plug Each
23.373M.S. Bolt & Nut 2" to 5" dia bore hole bail plug Each
23.374Threading Clamp 2" to 6" Each
23.375Threading Clamp 7" to 22" Each
23.376Water for testing and disinfecting of pipes %0 Gallon
23.377Lead Per Kg.
23.378Yarn Per Kg.
23.379Disinfecting agent for C.I. Pipe P. Kg.
23.380Bolt and nuts (3" to 4") for flanged joint Each
23.381Bolt and nuts (5" to 12") for flanged joint Each
23.382Bolt and nuts (15" to 18") for flanged joint Each
23.383Cost of ring for cast iron pipe(3") with tyton joints Each
23.384Cost of ring for cast iron pipe(4") with tyton joints Each
23.385Cost of ring for cast iron pipe(5") with tyton joints Each
23.386Cost of ring for cast iron pipe(6") with tyton joints Each
23.387Cost of ring for cast iron pipe(8") with tyton joints Each
23.388Cost of ring for cast iron pipe(10") with tyton joints Each
23.389Cost of ring for cast iron pipe(12") with tyton joints Each
23.390Cost of ring for cast iron pipe(15") with tyton joints Each
23.391Cost of ring for cast iron pipe(18") with tyton joints Each
23.392Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.393Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.394Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.395Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.396Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.397Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.398Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.399Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.400Material for jointing of fire hydrant Each
23.401Material for jointing of air valve Each
23.402Cost of Bolt and nuts for G.I. Flanged Joints 1" to 2" Each
23.403Cost of Bolt and nuts for G.I. Flanged Joints 2" to 7" Each
23.404Rubber Insertion for G.I. flanged joints Per Lbs
23.405Solvent for PVC bends Per Kg.
23.406Lubricant Per Kg.
23.407Material for C-I specials with spigot and socket joint fo 2 joints
23.408Material for C-I specials with spigot and socket joint fo 2 joints
23.409Material for C-I specials with spigot and socket joint fo 2 joints
23.410Material for C-I specials with spigot and socket joint fo 2 joints
23.411Material for C-I specials with spigot and socket joint fo 2 joints
23.412Material for C-I specials with spigot and socket joint fo 2 joints
23.413Material for C-I specials with spigot and socket joint fo 2 joints

Page 15
ITEM MATERIAL UNIT RATE
23.414Material for C-I specials with spigot and socket joint fo 2 joints
23.415Material for C-I specials with spigot and socket joint fo 2 joints
23.416Material for CI flanged speical with flanged and flanged joi 2 joints
23.417Material for CI flanged speical with flanged and flanged joi 2 joints
23.418Material for CI flanged speical with flanged and flanged joi 2 joints
23.419Material for CI flanged speical with flanged and flanged joi 2 joints
23.420Material for CI flanged speical with flanged and flanged joi 2 joints
23.421Material for CI flanged speical with flanged and flanged joi 2 joints
23.422Material for CI flanged speical with flanged and flanged joi 2 joints
23.423Material for CI flanged speical with flanged and flanged joi 2 joints
23.424Material for CI flanged speical with flanged and flanged joi 2 joints
Casting material (supply of speicals I/c moulding, painting
23.425 carriage to site of work) CI specials with Per Cwt
spigot an socket joint
Casting material (supply of speicals I/c moulding, painting
23.426 carriage to site of work) CI flanged Per Cwt
speical with flanged and flanged joints
Casting material (supply of speicals I/c moulding, painting
23.427 carriage to site of work) CI speicals with Per Cwt
tyton joints / with comet joint and rubber ring complete
23.428Material for AC pipe line with comet joint and rubber ring 2 joints
23.429Material for AC pipe line with comet joint and rubber ring 2 joints
23.430Material for AC pipe line with comet joint and rubber ring 2 joints
23.431Material for AC pipe line with comet joint and rubber ring 2 joints
23.432Material for AC pipe line with comet joint and rubber ring 2 joints
23.433Material for AC pipe line with comet joint and rubber ring 2 joints
23.434Material for AC pipe line with comet joint and rubber ring 2 joints
23.435Material for AC pipe line with comet joint and rubber ring 2 joints
23.436Material for AC pipe line with comet joint and rubber ring 2 joints
23.437Material for AC pipe line with comet joint and rubber ring 2 joints
24.00117.5 x 10 x cm (7" x 4") {Sal Wood Boards (4.5 cm) 1" thic Each
24.00222.5 x 10 x cm (9" x 4") {Sal Wood Boards (4.5 cm) 1" thic Each
24.00322.0 x 25 x cm (8" x 10") {Sal Wood Boards (4.5 cm) 1" thi Each
24.00425.0 x 30 x cm (10" x 12") {Sal Wood Boards (4.5 cm) 1" th Each
24.00530.0 x 37 x cm (12" x 14") {Sal Wood Boards (4.5 cm) 1" th Each
24.00617.5 x 10 x cm (7" x 4") {Teak Wood Boards (4.5 cm) 1.75" t Each
24.00722.5 x 10 x cm (9" x 4") {Teak Wood Boards (4.5 cm) 1.75" t Each
24.00820.0 x 25 x cm (8" x 10") {Teak Wood Boards (4.5 cm) 1.75" Each
24.00925.0 x 30 x cm (10" x 12") {Teak Wood Boards (4.5 cm) 1.75 Each
24.01030.0 x 37 x cm (12" x 14") {Teak Wood Boards (4.5 cm) 1.75 Each
2 way 15 Amp Branch distribution board iron/aluminium clad
24.011 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
3 way 15 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.012 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
4 way 15 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.013 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
5 way 15 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.014 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
6 way 15 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.015 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
7 way 15 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.016 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
8 way 15 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.017 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
9 way 15 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.018 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
10 way 15for
AmpBDB 250 volts
Branch distribution board iron/aluminium clad
24.019 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
11 way 15for
AmpBDB 250 volts
Branch distribution board iron/aluminium clad
24.020 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
12 way 15for
AmpBDB 250 volts
Branch distribution board iron/aluminium clad
24.021 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
2 way 30 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.022 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
3 way 30 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.023 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
4 way 30 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.024 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
5 way 30 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.025 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
6 way 30 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.026 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
7 way 30 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.027 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering for BDB 250 volts

Page 16
ITEM MATERIAL UNIT RATE
8 way 30 Amp Branch distribution board iron/aluminium clad
24.028 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering for BDB 250 volts
9 way 30 Amp Branch distribution board iron/aluminium clad
24.029 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering for BDB 250 volts
10 way 30 Amp Branch distribution board iron/aluminium clad
24.030 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering for BDB 250 volts
24.031PVC insulated single core copper conductor cable 3/0.029" 25 Metre
24.032PVC insulated single core copper conductor cable 3/0.036" 2 Metre
24.033PVC insulated single core copper conductor cable 7/0.029" 2 Metre
24.034PVC insulated single core copper conductor cable 7/0.036" 2 Metre
24.035PVC insulated single core copper conductor cable 7/0.044" 2 Metre
24.036PVC insulated single core copper conductor cable 7/0.064" 2 Metre
24.037PVC insulated single core copper conductor cable 19/0.052" 2 Metre
24.038PVC insulated single core copper conductor cable 19/0.064" Per Metre
PVC insulated cotton braided and compounded copper
24.039 Per Metre
conductor cable 3/0.029" 250/440 Volts
PVC insulated cotton braided and compounded copper
24.040 Per Metre
conductor cable 3/0.036" 250/440 Volts
PVC insulated cotton braided and compounded copper
24.041 Per Metre
conductor cable 7/0.029" 250/440 Volts
PVC insulated cotton braided and compounded copper
24.042 Per Metre
conductor cable 7/0.036" 250/440 Volts
PVC insulated cotton braided and compounded copper
24.043 Per Metre
conductor cable 7/0.044" 250/440 Volts
PVC insulated cotton braided and compounded copper
24.044 Per Metre
conductor cable 7/0.064" 250/440 Volts
PVC insulated sheathed single core copper conductor cable
24.045 Per Metre
3/0.029" 250/440 Volts
PVC insulated PVC sheathed single core copper conductor
24.046 Per Metre
cable 3/0.036" 250/440 Volts
PVC insulated PVC sheathed single core copper conductor
24.047 Per Metre
cable 7/0.074" 250/440 Volts
PVC insulated PVC sheathed single core copper conductor
24.048 Per Metre
cable 7/0.036" 250/440 Volts
PVC insulated PVC sheathed single core copper conductor
24.049 Per Metre
cable 7/0.044" 250/440 Volts
PVC insulated PVC sheathed single core copper conductor
24.050 Per Metre
cable 7/0.064" 250/440 Volts
PVC insulated PVC sheathed single core copper conductor
24.051 Per Metre
cable 7/0.064" 660/1100 volts grade
PVC insulated PVC sheathed single core copper conductor
24.052 Per Metre
cable 19/0.064" 660/1100 volts grade
PVC insulated PVC sheathed single core copper conductor
24.053 Per Metre
cable 19/0.064" 660/1100 volts grade
PVC insulated PVC sheathed single core, copper conductor
24.054 Per Metre
cable 19/0.083" 660/1100 volts grade
PVC insulated PVC sheathed single core, copper conductor
24.055 Per Metre
cable 37/0.072" 660/1100 volts grade
PVC insulated PVC sheathed single core, copper conductor
24.056 Per Metre
cable 37/0.083" 660/1100 volts grade
PVC insulated PVC sheathed single core, copper conductor
24.057 Per Metre
cable 37/0.103" 660/1100 volts grade
PVC insulated, PVC sheathed twin core copper conductor
24.058 Per Metre
cable 3/0.029" 250/440 volts
PVC insulated, PVC sheathed twin core copper conductor
24.059 Per Metre
cable 3/0.036" 250/440 volts
PVC insulated, PVC sheathed twin core copper conductor
24.060 Per Metre
cable 7/0.029" 250/440 volts
PVC insulated, PVC sheathed twin core copper conductor
24.061 Per Metre
cable 7/0.036" 250/440 volts
PVC insulated, PVC sheathed twin core copper conductor
24.062 Per Metre
cable 7/0.044" 250/440 volts
PVC insulated, PVC sheathed twin core copper conductor
24.063 Per Metre
cable 7/0.064" 250/440 volts
24.064PVC insulated, PVC sheathed three core cable 660/1100 volts Per Metre
24.065PVC insulated, PVC sheathed three core cable 660/1100 voltsPer Metre
24.066PVC insulated, PVC sheathed three core cable 7/0.029" 66Per Metre
24.067PVC insulated, PVC sheathed three core cable 7/0.036" 660Per Metre
24.068PVC insulated, PVC sheathed three core cable 7/0.044" 660Per Metre
24.069PVC insulated, PVC sheathed three core cable 7/0.064" 660/Per Metre
24.070PVC sheathed 4 core non armoured cable 3/0.029" 660/1100 vPer Metre
24.071PVC sheathed 4 core non armoured cable 3/0.036" 660/1100 vPer Metre
24.072PVC sheathed 4 core non armoured cable 7/0.029" 660/1100 vPer Metre

Page 17
ITEM MATERIAL UNIT RATE
24.073PVC sheathed 4 core non armoured cable 7/0.036" 660/1100 vPer Metre
24.074PVC sheathed 4 core non armoured cable 7/0.044" 660/1100 vPer Metre
24.075PVC sheathed 4 core non armoured cable 7/0.064" 660/1100 vPer Metre
24.076PVC sheathed 4 core non armoured cable 19/0.052" 660/1100 vPer Metre
PVC sheathed armoured with G.I. WIRE 16 SWG cable
24.077 Per Metre
19/0 052" 660/1100
PVC sheathed volts
armoured with G.I. WIRE 16 SWG cable
24.078 Per Metre
19/0sheathed
PVC 064" 660/1100 volts
armoured with G.I. WIRE 16 SWG cable
24.079 Per Metre
19/0sheathed
PVC 072" 660/1100 volts
armoured with G.I. WIRE 16 SWG cable
24.080 Per Metre
19/0sheathed
PVC 083" 660/1100 volts
armoured with G.I. WIRE 16 SWG cable
24.081 Per Metre
37/0sheathed
PVC 072" 660/1100 volts
armoured with G.I. WIRE 16 SWG cable
24.082 Per Metre
37/0sheathed
PVC 083" 660/1100 volts
armoured with G.I. WIRE 16 SWG cable
24.083 Per Metre
37/0 093" 660/1100 volts
PVC sheathed armoured with G.I. WIRE 16 SWG cable
24.084 Per Metre
37/0 103" stranded
Aluminium 660/1100hard
volts
drawn bare conductor 7/3.099 mm
24.085 Per Metre
(7/0 122")
Flexible wire 7/3.099 mm (7/.122") {PVC insulated PVC
24.086 sheathed armoured with G.I wire 16 SWG for service Per Metre
conneciton 3 core:}
24.087Flexible twin wire 23/.0076" (23/0.195mm) Per Metre
24.088PVC wire (3/.029") Per Metre
24.089Capacitor 2.2 UF for ceiling fan Each
24.090M.S Clamp " dia (16mm) Each
24.091M.S Clamp 3/4" dia (20mm) Each
24.092M.S Clamp 1" dia (25mm) Each
24.093M.S Clamp 11/4" dia (32mm) Each
24.094M.S Clamp 1" dia (40mm) Each
24.095M.S Clamp 2" dia (50mm) Each
24.096M.S Clamp 4" dia (100mm) Each
24.097Clamps for electric wiring 15 mm (") Each
24.098Clamps for electric wiring 20 mm (") Each
24.099Clamps for electric wiring '25 mm (1") Each
24.100Clamps for electric wiring '32 mm (1") Each
24.101Clamps for electric wiring 40 mm (1") Each
24.102Clamps for electric wiring 50 mm (2") Each
24.103Clamps for electric wiring '63 mm (2") Each
24.104Clamps for electric wiring '80 mm (3") Each
24.105Clamps for electric wiring 100 mm (4") Each
24.106PVC Inspection Boxes 15 mm (") Per Doz.
24.107PVC Inspection Boxes 20 mm (") Per Doz.
24.108PVC Inspection Boxes 25 mm (1") Per Doz.
24.109PVC Inspection Boxes 30 mm (1") Per Doz.
24.110PVC Inspection Boxes 40 mm (1") Per Doz.
24.111PVC Inspection Boxes 50 mm (2") Per Doz.
24.112PVC Inspection Boxes 75 mm (3") Per Doz.
24.113PVC Inspection Boxes 100 mm (4") Per Doz.
24.114Chokes 40 watts Each
24.115Chokes 20 watts Each
24.116Round block of Sahl wood Each
GEC design Pole mounted street light with holder shade and
24.117 glass for fitting 125/250 watts mercury Vapour lamp Each
(excluding cost of lamp) with bracket clamp nuts & bolts
24.118Street light pole bracket Each
24.119Cost of bracket 1" (32 mm) G.I pipe 7 ft. long half round Each
24.120Shackle Insulator for holding insulated wire Each
24.121Pin Insulator greeen (medium size) Each
24.122Staining screws for stay wire of electric pole Each
24.123Stay wire for electric pole 7/12" Metre
24.124Stay wire for electric pole 7/14" Metre
24.125Bakelite button holder shade large size Each
24.126Bakelite button holder shade Large size Each
24.127Bakelite Button Holder large size Each
24.128Bell push or bed switch Each
24.129Bakelite lamp holder Each
24.130Braket lamp holder Each
24.131Brass bracket with holder Each
24.132Brass bracket with holder Each
24.133Brass Button Holder Each
24.134Call bell 220/250 volts Each
24.135Ceiling rose bakelite Each
24.136Cut out bakelite open type Each
24.137Cut out backolite recessed type Each
24.138Electric Energy Metre Single Phase} 250 volts 10 AMP Each
24.139Electric Energy Metre Single Phase 250 volts 30 AMP Each
24.140Electric Energy Metre Single Phase 250 volts 60 AMP Each
24.141Three phase 4 wires, 400 volts: 3 x 15 Amps Each
24.142Three phase 4 wires, 400 volts:3 x 50 Amps Each
Page 18
ITEM MATERIAL UNIT RATE
24.143Three phase 4 wires, 400 volts: 3 x 80 Amps Each
24.144Electric shoe 3 pin 10/15 Amps Each
24.145Wall Shoe 3 pin 5 Amps Each
24.146Wall socket 3 pin 5 Amps Each
24.147Wall socket 3 pin 5 Amps without Shoe. Each
24.148Wall socket 3 pin 10/15 Amp open type Each
24.149Wall socket 3 pin 10/15 Amp recessed type Each
24.150Wall socket 3 pin 10/15 Amp with shoe Each
24.151Flouresent tube 40 watts Each
24.152Starter for Flourscent Tube 40 watts Each
24.153Kit kat fuses 500 volt 15/20 Amp Each
24.154Kit kat fuses 500 volt 30/35 Amp Each
24.155Kit kat fuses 500 volt 60/65 Amp Each
24.156Kit kat fuses 500 volt 100 Amp Each
24.157Kit kat fuses 500 volt 200 Amp Each
24.158Kit kat fuses 500 volt 300 Amp Each
24.159Kit kat fuses 500 volt 400 Amp Each
24.160Kit kat fuses 500 volt 500 Amp Each
24.161Leathoride paper Job
24.162Cooper nail 2" / 3" Each
24.163Cooper plates 600 x 600 x 3 mm (2' x 2' x 1/8") Kg
24.164Lightining arrestor Horn type Each
24.165Copper enamel wire No. 26 to 32 Kg
24.166Soldering and varnishing for A.C. ceiling fan each
24.167Wooden Gutties Dozen
24.168Switch double control open type (5 Amp) Each
24.169Switch double control piano type (5 Amp) Each
24.170Switch double controil ring type recessed (5 Amp) Each
24.171Switch Piano type (5 Amp) Each
24.172Switch plate type recessed (5 Amp) Each
24.173Switch ring type (5 Amp) Each
Double pole 15/20 Amp {Iron/Alminum clad 500 volt main
24.174 Each
switch with kit kat fuse}
Double pole 30/35 Amp {Iron/Alminum clad 500 volt main
24.175 Each
switch with kit kat fuse}
Double pole 60/65 Amp {Iron/Alminum clad 500 volt main
24.176 Each
switch with kit kat fuse}
Double pole 100 Amp {Iron/Alminum clad 500 volt main switch
24.177 Each
with kit kat fuse}
Tripple pole 15/20 Amp {Iron/Alminum clad 500 volt main
24.178 Each
switch with kit kat fuse}
Tripple pole 30/35 Amp {Iron/Alminum clad 500 volt main
24.179 Each
switch with kit kat fuse}
24.180Tripple pole with neutral link 30/35 Amp main switch Each
24.181Tripple pole with neutral link 60/65 Amp main switch Each
24.182Tripple pole with neutral link 100 Amp main switch Each
Iron/Aluminum clad 500 volt main switch with tripple pole
24.183 Each
and neutral link with HRC fueses: 60/65 Amps
Iron/Aluminum clad 500 volt main switch with tripple pole
24.184 Each
and neutral link with HRC fueses: 100 Amps.
Iron/Aluminum clad 500 volt main switch with tripple pole
24.185 Each
and neutral link with HRC fueses: 150 Amps.
Iron/Aluminum clad 500 volt main switch with tripple pole
24.186 Each
and neutral link with HRC fueses: 200 Amps.
Iron/Aluminum clad 500 volt main switch with tripple pole
24.187 Each
and neutral link with HRC fueses: 300 Amps.
Iron/Aluminum clad 500 volt main switch with tripple pole
24.188 Each
and neutral link with HRC fueses: 400 Amps.
Iron/Aluminum clad 500 volt main switch with tripple pole
24.189 Each
and neutral link with HRC fueses: 500 Amps.
24.190Thimble copper 60/65 Amp Each
24.191Thimble copper 100 Amp Each
24.192Thimble 150 Amp. each
24.193Thimble copper 200 Amp Each
24.194Thimble copper 300 Amp Each
24.195Thimble copper 400 Amp Each
24.196Thimble copper 500 Amp Each
24.197G.I bend " (15 mm) dia Each
24.198G.I bend " (20 mm) dia Each
24.199G.I bend 1" (25 mm) dia Each
24.200G.I bend 1" (32 mm) dia Each
24.201G.I bend 1" (40 mm) dia Each
24.202G.I. Bend 2" dia (50 mm) dia Each
24.203G.I bend 3" (80 mm) dia Each

Page 19
ITEM MATERIAL UNIT RATE
24.204M.S. Bend " (15 mm) dia Each
24.205M.S. Bend " (20 mm) dia each
24.206M.S. Bend 1" (25 mm) dia each
24.207M.S. Bend 1" (40 mm) dia each
24.208M.S. Conduit Bend 1" (32 mm) dia each
24.209M.S. Conduit Bend 1" (40 mm) dia each
24.210M.S. Conduit Bend 2" (50 mm) dia each
24.211PVC Bend " (12 mm) dia ordinary each
24.212PVC Bend " (20 mm) dia ordinary each
24.213PVC Bend 1" (25 mm) dia ordinary each
24.214PVC Bend 1" (30 mm) dia ordinary each
24.215PVC Bend 1" (40 mm) dia ordinary each
24.216PVC Bend 2" (50 mm) dia ordinary each
24.217PVC Bend 3" dia (75 mm) ordinary each
24.218PVC Bend 4" dia (100 mm) ordinary each
24.219Inspection box " (15 mm) dia Each
24.220Inspection box " (20 mm) dia Each
24.221Inspection box 1" (25 mm) dia Each
24.222M.S. Inspection box 1" (32 mm) dia per doz.
24.223M.S. Inspection box 1" (40 mm) dia to 3" (80mm) dia per doz.
24.224Hooks for " to 1" dia pipe Each
24.225 Hooks for 11/4" to 1" dia pipe Each
24.226Hook for 2" dia pipe Each
24.227Hook for 3" dia pipe Each
24.228 M.S. Conduit pipe " (15 mm) dia Per Mtr
24.229M.S. Conduit pipe " (20 mm) dia Per Mtr
24.230M.S. Conduit pipe 1" (25 mm) dia Per Mtr
24.231M.S. Conduit pipe 1" (32 mm) dia Per Mtr
24.232M.S. Conduit pipe 1" (40 mm) dia Per Mtr
24.233M.S. Conduit pipe 2" (50 mm) dia Per Mtr
24.234PVC pipe " (12 mm) dia ordinary Per Mtr
24.235PVC pipe " (20 mm) dia ordinary Per Mtr
24.236PVC pipe 1" (25 mm) dia ordinary Per Mtr
24.237PVC pipe 1" (30 mm) dia ordinary Per Mtr
24.238PVC pipe 1" (40 mm) dia ordinary Per Mtr
24.239PVC pipe 2" (50 mm) dia ordinary Per Mtr
24.240PVC Pipe 3" dia (75 mm) ordinary per mtr.
24.241PVC Pipe 4" dia (100 mm) ordinary per mtr.
24.242PVC Flexible Pipe " (12 mm) dia Per Mtr
24.243G.I. pipe " dia (15 mm i/d) Per Mtr
24.244G.I. Pipe " dia (20 mm i/d) Per Mtr
24.245G.I. Pipe 1" dia (25 mm i/d) Per Mtr
24.246G.I. pipe 1" dia (32 mm i/d) Per Mtr
24.247G.I. pipe 1" dia (40 mm i/d) Per Mtr
24.248G.I. pipe 2" dia (50 mm i/d) Per Mtr
24.249G.I. pipe 3" dia (75 mm i/d) Per Mtr
24.250G.I. Flexible Pipe " (12 mm) dia per mtr.
24.251G.I. Flexible Pipe " (20 mm) dia per mtr.
24.252G.I. Flexible Pipe 1" (25 mm) dia per mtr.
24.253G.I. Flexible Pipe 1" (32 mm) dia per mtr.
24.254G.I. Flexible Pipe 1" (40 mm) dia per mtr.
24.255G.I. Flexible Pipe 2" (50 mm) dia per mtr.
24.256G.I. Flexible Pipe 3" (80 mm) dia per mtr.
24.257G.I. Flexible pipe 4" (100 mm) each
24.258Screws 1" (25 mm) long Dozen
24.259Screws 2" (25 mm) long Dozen
24.260Screws 3" (25 mm) long Dozen
24.261Screws 4" (25 mm) long Dozen
24.262Screws 6" (25 mm) long Dozen
24.263G.I reducing socket size 2 x " (50 x 13 mm) each
24.264G.I Reducing socket 2 x " dia (50 x 20 mm) each
24.265Boring " dia Metre
24.266G.I. Socket " (12 mm) dia each
24.267G.I. Socket " (20 mm) dia each
24.268G.I. Socket 1" (25 mm) dia each
24.269G.I. Socket 1" (32 mm) dia each
24.270G.I. Socket 1" (40 mm) dia each
24.271G.I. Socket 2" (50 mm) dia each
24.272G.I. Socket 3" (80 mm) dia each
24.273Brass Socket 1" (40 mm) dia each
24.274Brass Socket 2" (50 mm) dia each
24.275Brass Socket 4" (100 mm) dia each
24.276PVC Socket " (12 mm) dia each

Page 20
ITEM MATERIAL UNIT RATE
24.277G.I. Nipple " (12 mm) dia each
24.278G.I. Nipple " (20 mm) dia each
24.279G.I. Nipple 1" (25 mm) dia each
24.280G.I. Nipple 1" (32 mm) dia each
24.281G.I. Nipple 1" (40 mm) dia each
24.282G.I. Nipple 2" (50 mm) dia each
24.283G.I. Nipple 3" (80 mm) dia each
24.284Brass nipple 1" dia (25mm) each
24.285Brass Nipple 1" dia (32 mm) each
24.286Brass Nipple 1" (40 mm) dia each
24.287Brass Nipple 2" (50 mm) dia each
24.288Brass Nipple 4" (100 mm) dia each
24.289PVC Nipple " (12 mm) dia each
24.290Brass Check nut " (12 mm) dia each
24.291Brass check nut 1" (40 mm) each
24.292Brass check nut 1" (25 mm) each
24.293Brass check nut 1" (32 mm) each
24.294Brass check nut 2" (50 mm) each
24.295Brass check nut 4" (100 mm) each
24.296Check Nuts " (12 mm) dia each
24.297Check Nuts " (20 mm) dia each
24.298Check Nuts 1" (25 mm) dia each
24.299Check Nuts 1" (32 mm) dia each
24.300Check Nuts 1" (40 mm) dia each
24.301Check Nuts 2" (50 mm) dia each
24.302Check Nuts 3" (80 mm) dia each
24.303M.S Box 4" x 4" (100 x 100 mm) each
24.304M.S Box 7" x 4" (175 x 100 mm) each
24.305M.S Box 9" x 4" (225 x 100 mm) each
24.306M.S Box 8" x 10" (200 x 250 mm) each
24.307M.S Box 10" x 12" (250 x 300 mm) each
24.308M.S Box 12" x 14" (300 x 350 mm) each
24.309Angle iron board including paints (9"x9"x1") each
24.310Angle Iron board including paint (9"x12"x1") each
24.311Angle Iron board including paint (10"x12"x1") each
24.312Angle Iron board including paint (12"x15"x1") each
24.313Angle Iron board including paint (12"x18"x1") each
24.314Angle Iron board including paint (10"x15"x1") each
24.315Anle Iron board including paint (15"x18"x1") each
24.316Copper strip 1" x 1/8" x 14" (40 x 3 x 350 mm) each
24.317Copper strip 14" x 2" x 1/8" to 3/16" (350 x 50 x 3 mm to 6 each
24.318Copper strip 14" x 2" x 1/4" (350 x 50 x 6 mm) to 6mm each
24.319Rag bolts 9" x 5/8" (225 x 16 mm) each
24.320Reg bolts 12" x 5/8" (300 x 16 mm) each
24.321Eye bolts Each
24.322Eye bolts (bigger size) for straining posts, stiffening post Each
24.323PVC/weather proof cable 3/0.029" (3/0.74 mm) Single core per mtr.
24.324PVC/weather proof cable /0.029" (7/0.74 mm) Single core per mtr.
24.325PVC/weather proof cable /0.036" (7/0.91 mm) Single core per mtr.
24.326PVC/weather proof cable /0.044" (7/1.12 mm) Single core per mtr.
24.327Nut & Screw Each
24.328Straining Screw for electric pole Each
24.329Sal wood casing for wiring Per mtr.
24.330Wooden strip casing Per % mtr.
24.331Insulated cleat (small) each
24.332Insulated cleat (big size) each
24.333Leather or wooden cleats each
24.334M.S Hooks each
24.335M.S bar hook 3/8" (!0 mm) dia each
24.336Canopy nipple & hook Per Job
24.337Hook 5/8" (16 mm) with nut & bolts each
24.338Girder clamp hook 5/8" (16 mm) each
24.339PVC bushes " (12 mm) dia each
24.340Glazed porcelain (Imported) each
24.341Glazed Porcelain counter weight with accessories each
24.342VIR/PVC cable 3/0.29 per mtr.
24.343Brass lamp holder each
24.344Brass lamp holder each
24.345Brass lamp holder each
24.346Double cone reflector each
24.347Switch ring type each
24.348Switch 10/15 Amp each
24.349Switch 10/15 Amp. recessed each

Page 21
ITEM MATERIAL UNIT RATE
24.350Plug 3 pin and switch (combined) 10/15 Amp. each
24.351Plug 3 pin and switch (recessed) 10/15 Amp. each
24.352Pole mounted street light holder shade and glass each
24.353Frame with holder Per Job
24.354Frame set Per Job
24.355Round tube 32 watts each
24.356Starter each
24.357Choke each
24.358Holder each
24.359Base patti for tube light each
24.360Ball bearing size (6201, 6202, 6203) each
24.361Plastic cover each
24.362Handle chromium plated for iron box each
24.363Nut & bolts " (12 mm) dia 1" (40 mm) long each
24.364T - Iron " x 1" x 1" x 5" P.kg
24.365Clamps P. Kg.
24.366Steel channel 75 x 40 x 3 mm P.Kg.
24.367steel plate 3"x1"x" )75x40x40 mm) P.Kg.
24.368 Steel plate 3"x 3/4 x 3/4 (75 x 20 x 20 mm) per kg
24.369Bolts and nuts 5/8" dia (16 mm) Each
24.370Double clamp for anchor rod henley type for pole Each
24.371Double clamp 9" dia (225 mm) Each
24.372Clamps with bolts & nuts etc. for street pole each
24.373Clamp double for erection of house service pipe Henley each
24.374Clamp 2" dia (50 mm) each
24.375Steel clamp " dia (12 mm) each
24.376G.I clamp (small) each
24.377G.I. Clamp (large) each
24.378Pole clamp with bolt & nuts for street light pole each
24.379Shakle insulator each
24.380M.S bolts for suport each
24.381Copper wire No.2 to 10 per kg
24.382G.I wire (all size) per kg
24.383Cut out each
24.384Wooden & leather cleats each
24.385Vapour mercury lamp 125 watt with choke set each
24.386Vapour mercury lamp 250 watt with choke set each
24.387Silver paint P.Gln
24.388G.I Nuts & Bolts 2" long " (50 mm x 13 mm) each
24.389G.I Nuts & Bolts 1" x " long (40 x 6 mm) each
24.390Copper wire No.16 & 20 SWG per kg
24.391Copper Wire Old per kg
24.392Enemal wire No.26 SWG to 32 SWG per kg
24.393 Copper tap 1" to 2" x1/8" per kg
24.394Copper rod 1" dia (25 mm) per kg
24.395Copper nail (small) each
24.396Copper stapple each
24.397Soldering and Vernishing each
24.398Salt per kg
24.399Loop wire 4 loop 3/0.029 (3/0.74 mm) Rft
24.400Knob with shaff and plate each
25.001Locking arrangements with sliding bolt 1' long and 1" dia Each
25.002Hard wood stair railing Rft
25.003M.S. Channels Kg
25.004Steel beam Kg
25.005Steel chisel P.Kg.
25.006Grating 3/4"x3/4" size P.Kg.
25.007M.S. Box section of 16 SWG 1" x 3" hand rail P.Rft
25.008Conduit pipe 2" dia including specials P.Ft
25.009Roller 3" dia each
25.010Rivets with heads 2" long Each
25.011Rivets 1" long Each
25.012Locking arrangement collapsible gate Each
25.013 Handles 12" long of 3/4"x1/4" steel channels for collapsibl Each
25.014GI sheet 24 SWG P.Kg.
25.015GI bracket for railing shutter Each
25.016GI Holdfast for railing shutter Each
25.017GI Pipe 1" dia (light quality) P. Rft
25.018Handle for railing shutter Each
25.019GI spring for railing shutter Each
25.020Rolling gear for railing shutter Each
25.021Iron Holdfast for steel windows Each
25.022GI pipe 2" dia (light quality) P. Foot
Page 22
ITEM MATERIAL UNIT RATE
1 5
25.023 Window hinges /4" thick with /16" dia pins Each
25.024Brass casement handle 6" for steel windows Each
25.025Mild steel casement stay 15" long for steel windows Each
25.026Wooden strips for fixing glass pans P.Rft
25.027Steel glazing clips for fixing glass panes Each
25.028Glass panes 2 mm thick P. Sft.
25.029Glass panes 2.5 mm thick P. Sft.
25.030Glass panes 3 mm thick P. Sft.
25.031Glass panes 4 mm thick P. Sft.
25.032Glass panes 5 mm thick P. Sft.
25.033M.S. moulded tubular pipe of 18 SWG P.Kg.
25.034Brass hinges (4" long) Each
25.035Brass Handles (4" long) Each
25.036U' shapped rubber linning (" thick) P. Rft
25.037Wire gauze galvanized 24 SWG (12x 12 mesh) P.Sft.
25.038 x M.S square box of 16 SWG for fixing wire gauge P. Kg.
25.039C.P. tower bolt (225 mm long) Each
25.040Brass handle special type for steel windows Each
25.041G.I. Stay for windows Each
1
25.042 Grill of M.S. flat "x /8" with frame P. Sft.
25.043Cost of flaps including hinges for G.I. Pipes Each
25.044Steel grating P.Sft
25.0451 ft. long M.S. U-Clamp 3/4" dia threaded at both ends incl Each
25.046Painting small detached articles not exceding 1" sft. Each
3
25.047 Aluminum frame 100x20mm (4"x /4") Rft
25.048Aluminum frame 100x40mm (4 x1") Rft.
25.049Aluminum frame 60x40mm (1" x 2") Rft.
3
25.050 Aluminum frame 50x20mm (2" x /4") Rft.
25.051Aluminum leaf edging for aluminium windows Rft.
25.052Tinted glass 5mm thick Sft.
25.053Aluminum tringular gola and gasket Rft.
25.054Pivot for aluminium doors each
25.055Alimuninum tower bolt 9" long each
25.056locking arrangement each
25.057Handle Large Rft
25.058Rubber gasket for Aluminium Windows Rft.
25.059Latch for Aluminium Windows each
25.060Steam Coal P. Kg.
26.0017 Strand barbed wire P.Kg.
26.002Anti termite (Heptachlore) P-Ltr
26.003Cane Singapore Per Kg.
26.0043/16" dia washers for straining posts, stiffening posts & in Dozn
26.005Cost of bamboo 10' to 12' long Each
26.006Cost of iron shoes for survey Jhandy Each
26.007Cost of red cloth for survey Jhandy Each
26.008Cost of ordinary wood for pegs P. Cft.
26.009Hooks for fixing iron gauges Dozen
26.010Filling cement bags with coal Per Kg.
26.011Cost of manure per Cart
26.012Polythene sheet of 300 gauge (0.003 thick) P.Kg.
26.013Soap P. Kg.
26.014Eye bolt Each
26.015Primer (Zinc) P. Kg.
26.016Weather Sheet Paint P. Lt

Page 23
CHAPTER NO. 26

MISCELLANEOUS

DESCRIPTION OF ITEM:

1. Notice Board made of cement sand mortar

Note : The board is to be of cement plaster " (12 mm) thick with 2" (50
1" (25mm) thick beading

Detail Unit Rate Per Sft.


Rate
Qty Per Unit Amount

Size of Board 4' x 5' = 20 Sft.


4' (1.22m) x 5' (1.53m) = 20 Sft. (1.87 Sqm)

MATERIAL

1 Sand 1.20 Cft 0.00 %Cft. -


2 Cement 0.3 bag 0.00 per bag -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Mason 0.75 No. 0.00 Per day -


2 Coolies 1 No. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Sft. Rs. - 0.00


Labour Rate Per Sqm Rs. - Say 0.00
Composite Rate Per Sft. Rs. - 0.00
Composite Rate Per Sqm. Rs. - Say 0.00

Page 1
2. Fixing handles to iron hammers.

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

FOR 12 NOS.

LABOUR

1 Carpenter 1.25 Nos. 0.00 Per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 12 Nos. -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00

Page 2
3. Providing and fixing barbed wire fencing with 4 horizontal and 2 number cross wires fixed
(1:2:4) straining posts 7'x9"x9" (2.14m x 225mm) at 100' (30m) centre to centre stiffenin
x 15 mmx 50mm) at 50' (15m) interval and intermediate posts 7'x5"x5" at 8' centre to centr
steel, its fabrication and placing of steel reinforcement, eye bolt, washers, etc. complet

Detail Unit Rate for 100 Cft.


Rate
Qty Per Unit Amount

MATERIAL FOR 48 RFT.

1 R.C.C. posts (1:2:4) straining


posts = x 7' x 0.75 x 0.75 2.00 Cft.
Collar around the straining posts
x (1.5)2xxx22/7= 0.44 Cft.
Stiffening post 6"x6"
x7xx 0.88 Cft.
Intermediate posts 5"x5"
5x7x5/12x5/12 6.07 Cft.
Deduction for portion of posts
xxx -0.14 Cft. 9.25 Cft. 0.00 Per Cft, -
9.25 Cft.

2 M.Steel with binding wire straining


posts
Vertical bars " dia 2x7 14
stirrups " = x 8 x 3 12
Stiffening posts
Vertical bars 3/8" dia = 2x7 14
stirrups = x 8 x 2 8
Intermediate Posts
Vertical bars 3/8" dia=5x4x7 140
Stirrups " = 5x8x5/3 = 67
weight " 14..0' @ 0.67 Lb/f 9.368 Lbs. 38.89 Kg. 0.00 Per Kg. -
" 12+8+67 = 87 ft. @ 0.167 14.53 Lbs. 85.73 Lbs.
3/8" 14+140 = 154' @ 0.37 lb 57.75
Total 81.648
add wastage 5% 4.082
85.73

Page 3
B / F : -

MATERIAL

3 7 Strand barbed wires


Horizontal 4x48 = 192 Rft.
cross wire 2x6x9 108 Rft.
300 Rft.
Add 5% wastage 15 Rft.
Total 315 14.82 Kg 0.00 Per Kg. -
315 Rft. @ 1.25 Cwt/450 Yards

4 Eye bolts (bigger size)


For straining posts 4 Nos
For stiffening posts 2 Nos
For intermediate posts 20 Nos
Total 26 No 26.0 Nos. 0.00 Each -
5 3/16" washers
For straining posts 4 Nos
For stiffening posts 2 Nos
For intermediate posts 20 Nos
Total 26 No 26.0 Nos 0.00 Dozen -

Total -
Contractor's Profit & Ove 20.0 Percent # -
Total -

Total for 100 Rft. 2462.21 x 100 Rs. -


48
LABOUR

i) R.C.C. work (Item 6a(ii) Chap. 6) 9.25 Cft. 0.00 Per Cft. -
ii) Fabrication of steel work 9Item 9(b) Chap. 6) 38.89 Kg. 0.00 Per Kg. -
iii) Blacksmith for wire fencing
erection. 0.75 No. 0.00 Per day -
iv) Coolies 2.00 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Lft. Rs. Say 0.00


Labour Rate Per LM Rs. Say 0.00
Composite Rate 100 Lft. Rs. Say 0.00
Composite Rate Per LM Rs. Say 0.00

4. Supplying bamboo jhandies 10' to 12' (3m to 2054m) with iron shoes and flag 15" (375 mm) s

Detail Unit Rate Each

Page 4
Rate
Qty Per Unit Amount

MATERIAL

1 Cost of bamboo 1.00 No. 0.00 Each -


2 Cost of iron shoes 1.0 No. 0.00 Each -
Cost of red cloth 1.0 No. 0.00 Each -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Carpenter 0.04 No. 0.00 Per day -


2 Sewing charges L.S. -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. - Say 0.00


Composite Rate for Each Rs. Say 0.00

Page 5
5. Supplying wooden pegs for leveling 1" (40mm) dia 6" (150mm) long

Detail Unit Rate Per 100 Nos


Rate
Qty Per Unit Amount

MATERIAL FOR 300 NOS.

Cost of wood 0.78 Cft. 0.00 Per Cft. -


Contractor's Profit & Ove 20.0 Percent -
Total for 300 Nos. -
Total for 100 Nos. -

LABOUR

1 Carpenter 0.50 No. 0.00 Per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 300 Nos. -
Total for 100 Nos. -

ITEM RATE

Labour Rate Per 100 Nos. Rs. - Say 0.00


Composite Rate Per 100 Nos. Rs. - Say 0.00

Page 6
6. Supplying wooden pegs for alignment 2" to 3" (50 to 75mm) dia 9" (225mm) long

Detail Unit Rate Per 100 Nos.


Rate
Qty Per Unit Amount

MATERIAL

Cost of wood 3.00 Cft 0.00 Per Cft. -


Contractor's Profit & Ove 20.0 Percent -

Total -

LABOUR

1 Carpenter 0.40 No. 0.00 Per day -


Sundries 10.00 Percent -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Nos. Rs. - Say 0.00


Composite Rate Per 100 Nos. Rs. - Say 0.00

Page 7
7. Fixing enamalled iron gauges flush with masonry including cost of hooks.

Detail Unit Rate Per Lft. / Assumed for 20 Lft.


Rate
Qty Per Unit Amount

MATERIAL

1 Hooks 6.00 Nos. 0.00 Each -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total for 20 Lft. -

LABOUR

1 Mason 1.00 No. 0.00 Per day -


2 Coolies 1.00 No. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 20 Lft. -

ITEM RATE

Labour Rate Per Lft. Rs. Say 0.00


Labour Per LM Rs. Say 0.00
Composite Rate Per Lft. Rs. Say 0.00
Composite Rate Per LM Rs. Say 0.00

8. Placing boundary pillars in position including digging pits.

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

LABOUR FOR 30 NOS.

1 Mason 1.00 No. 0.00 Per day -


2 Coolies 1.00 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 30 Nos. -

ITEM RATE

Labour Rate Each Rs. - Say 0.00

Page 8
9. Fixing mainline iron distance marks in position including making 1:3;6 cement concrete blo
size of block 10x14"x15" = 14.58 Cft.

Detail Unit Rate Per Each / Assumed for 10 Nos.


Rate
Qty Per Unit Amount

MATERIAL

1 Cement 1.80 Bags 0.00 per bag -


2 Sand 6.75 Cft. 0.00100 Cft. -
3 Aggregate stone 13.50 Cft. 0.00per Cft. -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Mason 1.00 No. 0.00 Per day -


2 Coolies 2.00 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00


Composite Rate Per Each - Say 0.00

Page 9
10. Cutting Pipes upto 2" (50mm) dia.

Detail Unit Rate Per Cut


Rate
Qty Per Unit Amount

LABOUR FOR 30 CUT

1 Blacksmith 1.00 No. 0.00 Per day -


2 Coolies 1.00 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 30 Nos. -

ITEM RATE

Labour Rate Per Cut Rs. - Say 0.00

11. Cutting Pipes above 2" (50mm) dia.

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

LABOUR FOR 25 CUTS

1 Blacksmith 1.75 Nos. 0.00 Per day -


2 Coolies 1.25 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 25 Nos. -

ITEM RATE

Labour Rate Per Cut Rs. - Say 0.00

Page 10
12. Threading pipe ends 1" to 4" (40 mm to 100 mm) dia

Detail Unit Rate Per Each End


Rate
Qty Per Unit Amount

LABOUR FOR 30 NOS.

1 Blacksmith 1.50 Nos. 0.00 Per day -


2 Coolies 1.00 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 30 Nos. -

ITEM RATE

Labour Rate Per Each End Rs. - Say 0.00

13. Assembling 1" (40mm) dia pressure pipes

Detail Unit Rate Per 100 Lft.


Rate
Qty Per Unit Amount

LABOUR FOR 800 LFT.

1 Fitter Grade II 1.00 No. 0.00 Per day -


2 Coolies 1.50 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 800 Lft. -

ITEM RATE

Labour Rate Per 100 Lft. Rs. - Say 0.00


Labour Rate Per Lm Rs. - Say 0.00

Page 11
14. Boring and fixing 1" (40mm) dia pressure pipe

Detail Unit Rate Per Lft.


Rate
Qty Per Unit Amount

LABOUR FOR 40 LFT.

a) In ordinary soil
Fitter 1.00 No. 0.00 Per day -
Coolies 3.50 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 40 Lft. -

Labour Rate Per Lft. Rs. - Say 0.00


Labour Rate Per Lm. Rs. - Say 0.00

b) In clay (For 40 Lft.)


Fitter 1.00 No. 0.00 Per day -
Coolies 8.00 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 40 Rft. -

Labour Rate Per Lft. Rs. - Say 0.00


Labour Rate Per Lm. Rs. - Say 0.00

c) In Shingle (For 40 Lft.)


Fitter 1.00 No. 0.00 Per day -
Coolies 12.50 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 40 Rft. -

ITEM RATE

Labour Rate Per 1 Lft. Rs. - -


Labour Rate Per Lm. Rs. - Say 0.00

Page 12
15. Repair to hand pumps pulling out and re-fitting.

Detail Unit Rate Per Lft.


Rate
Qty Per Unit Amount

LABOUR FOR 50 LFT

1 Blacksmith 0.50 No. 0.00 Per day -


2 Coolies 2.00 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 50 Rft. -

ITEM RATE

Labour Rate Per Lft. Rs. - Say 0.00


Labour Rate Per Lm. Rs. - Say 0.00

16. Fixing Hand pump (machine only)

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

LABOUR

1 Blacksmith 0.20 No. 0.00 Per day -


Sundries 10.00 Percent -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00

Page 13
17. Washing Niwar of Bed

Detail Unit Rate Per Bed


Rate
Qty Per Unit Amount

MATERIAL

1 Soap etc. 0.42 Kg. 0.00 P. Kg. -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Coolies (washerman) 0.75 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE

Labour Rate Per Bed Rs. Say 0.00


Composite Rate Per Bed Rs. Say 0.00

Page 14
18. Washing Durries

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit Amount

MATERIAL

Cost of Soap 1.00 Kg. 0.00 P. Kg. -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Coolies (washerman) 1.00 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
-
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate Per 100 Sft. Rs. - Say 0.00
Composite Rate Per Sqm. Rs. Say 0.00

Page 15
19 Recaning Chairs.

(i) Office chair single caning seat only.

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

MATERIAL

1 Cane 3.00 Ozs (0.085 Kg 0.00 Kg. -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Canners 0.35 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00


Composite Rate Per Each Rs. Say 0.00

Page 16
19 (i Office chairs double caning seat only

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

MATERIAL

1 Cane (Singapur) 4 Ozs. (0.12 Kg. 0.00 Kg. -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Canners 0.45 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00


Composite Rate Per Each - Say 0.00

Page 17
19 (i Office chairs single caning back only

Detail Unit Rate Per Each / Assumed for 8 Nos.


Rate
Qty Per Unit Amount

MATERIAL

1 Cane (Singapur) 1.5 Ozs (0.043 Kg 0.00 Kg. -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Canners 2.00 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Each Rs. Say 0.00


Composite Rate Per Each Rs. Say 0.00

Page 18
19 (i Office chairs double caning back only

Detail Unit Rate Per Each / Assumed for 5 Nos.


Rate
Qty Per Unit Amount

MATERIAL

1 Cane (Singapur) 0.23 Kg. 0.00 Kg. -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total for 5 Nos. -

LABOUR

1 Canners 2.00 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
-
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00


Composite Rate Per Each Rs. - Say 0.00

Page 19
19 (v Easy chairs single caning seat only

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

MATERIAL

1 Cane 0.114 Kg. 0.00 Kg. -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Canners 0.25 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -
-
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Each Rs. Say 0.00


Composite Rate Per Each Rs. Say 0.00

Page 20
19 (v Easy chairs double caning seat only

Detail Unit Rate Per Job


Rate
Qty Per Unit Amount

MATERIAL

1 Cane 0.17 Kg. 0.00 Kg. -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Canners 0.70 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00


Composite Rate Per Each Rs. - Say 0.00

Page 21
19 (v Easy chairs, single caning only back and seat in one piece.

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

MATERIAL

1 Cane 12 Ozs (0.70 Kg. 0.00 Kg. -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Canners 1.00 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00


Composite Rate Per Each Rs. - Say 0.00

Page 22
19 (v Easy chairs double caning back and seat in one piece or couches (caned area
about 16 Sft. 1.50 Sqm)

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

MATERIAL

1 Cane 32.00 Ozs (1.70 Kg 0.00 Kg. -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Canners 1.50 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00


Composite Rate Per Each Rs. - Say 0.00

Page 23
20 Making and fixing hat pegs ordinary

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

MATERIAL

1 Shisham wood 1x2.5'x.0.4' x 0.1' =00.1 0.17 Cft. 0.00 Cft


3x0.75' x 0.2' x 0.1' =0.04
Total 0.145
Wastage 20% 0.029
0.174 Cft

Cost of Polish & Nails L.S. -


Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Carpenter 0.18 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Each Rs. Say 0.00


Composite Rate Per Each Rs. Say 0.00

Page 24
21. Weaving charpoys

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

LABOUR

1 Coolies Skilled 0.65 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Say -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00

22 Sweeping Chimneys

Detail Unit Rate Per Each / Assumed for 12 Nos.


Rate
Qty Per Unit Amount

MATERIAL

Rope, rags, etc. L.S 0.00 -


Contractor's Profit & Ove 20.0 Percent -

Total -

LABOUR

Coolies Unskilled 2.00 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00


Composite Rate Per Each 13.20+181.50 Rs. Say 0.00
12

Page 25
23. Picture, railing including making, fixing and painting

Detail Unit Rate Per Lft. / Assumed for 20 Lft.


Rate
Qty Per Unit Amount

MATERIAL FOR 20 LFT.

1 Deodar wood for 0.3' x 0.1' x 1.5' = 0.45 Cft 0.50 Cft 0.00 Per Cft. -
+ coastage 10% = 0.05
2 Paint 0.38 / 0.04 Gallon 0.00Per Gallon
3 Nails 0.006 Kg. 0.00 Per Kg. -
4 Brush 0.05 No. 0.00 Each -
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Carpenter 1.00 No. 0.00 Per day -


2 Painter 0.03 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -
-
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Rft. Rs. - Say 0.00


Labour Rate Per Metre Rs. - Say 0.00
Composite Rate Per Rft. Rs. - Say 0.00
Composite Rate Per Metre 297.82 + 211.87 Rs. - Say 0.00
12

Page 26
24. Cutting fuel wood from plantation

Detail Unit Rate Per 100 Kg.


Rate
Qty Per Unit Amount

Analysis for 15 Mds. (560 Kg.)

LABOUR

1 Coolies 1.25 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Kg. Rs. - Say 0.00

25. Splitting fuel wood

Detail Unit Rate Per 100 Kg.


Rate
Qty Per Unit Amount

LABOUR FOR (385 Kg.)

1 Coolies Unskilled 1.80 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 385 Kg. -

ITEM RATE

Labour Rate Per 100 Kg. Rs. - Say 0.00

Page 27
26 Burning charcoal including loading unloading and repairing kiln

Detail Unit Rate Per 100 Kg.


Rate
Qty Per Unit Amount

LABOUR FOR 100 MAUNDS (3732 KG.)

1 Coolies for repairing kiln 3.00 Nos. 0.00 Per day -


2 Coolies for loading & unloading
wood 15.00 Nos. 0.00 per day -
3 Coolies skilled 8.00 Nos. 0.00 per day -
4 Mason for repairing kiln 1.00 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Kg. Rs. - Say 0.00

27. Filling cement bags with coal and sewing including cost of string.

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit Amount

MATERIAL FOR 500 CFT.


Filling cement bags with coal L.S 0.00 -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR
1 Coolies Unskilled 10.25 Nos 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE
Labour Rate Per 100 Cft. Rs. Say 0.00
Labour Rate Per Cum Rs. Say 0.00
Composite Rate Per 100 Cft. Rs. Say 0.00
Composite Rate Per Cum Rs. Say 0.00

Page 28
28. Supply manure (capacity of cart 200 ft. or 0.57 cum)

Detail Unit Rate Per Cart Load


Rate
Qty Per Unit Amount

MATERIAL

1 Cost of manure 1 Cart 0.00 per Cart -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Cart with cartman 0.25 Nos 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Cart Load Rs. - Say 0.00


Composite Rate Per Cart Load Rs. - Say 0.00

29 Washing punkha frills.

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

LABOUR

1 Washerman Cooly Skilled 0.20 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00

Page 29
30 Washing

a) Table Cloth

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

LABOUR FOR 10 NOS.

Washerman Cooly Skilled 0.50 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 10 Nos. -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00

b) Napkins, dusters etc.

Detail Unit Rate Per Job


Rate
Qty Per Unit Amount

LABOUR FOR 15 NOS.

Washerman Cooly Skilled 0.50 No. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 15 Nos. -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00

Page 30
31 Hoisting and placing sleepers for centring, including carriage within one chain.

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

LABOUR FOR 40 NOS.

1 Mason 0.50 No. 0.00 Per day -


2 Coolies 3.00 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 40 No.s -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00

32. Dismantling sleeper from centring including stacking within one chain

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

LABOUR FOR 80 SLEEPERS

1 Coolies (skilled) 1.00 No. 0.00 Per day -


2 Coolies (unskilled) 7.00 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00

Page 31
33. Dredging sumps

Detail Unit Rate Per Shift


Rate
Qty Per Unit Amount

LABOUR

1 Coolies Unskilled 3.75 Nos. 0.00 per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Shift Rs. - Say 0.00

34. Fixing 'U' bolt in masonry or concrete including leveling and tying for fixing angle iron
post.

Detail Unit Rate Per Each


Rate
Qty Per Unit Amount

LABOUR FOR 12 NOS.

1 Mason 1.00 No. 0.00 per day -


2 Blacksmith 1.00 No. 0.00 per day -
3 Cooly 1.00 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 12 Nos. -

ITEM RATE

Labour Rate Per Each Rs. - Say 0.00

Page 32
35. Bailing out water

a) By hand

Detail Unit Rate Per 1000 Cft.


Rate
Qty Per Unit Amount

LABOUR

1 Coolies 3.00 Nos. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 1000 Cft. Rs. - -


Labour Rate Per Cum. Rs. - Say 0.00

Page 33
35 b) By pump (Rate including cost of pump P.O.L etc. and operational charges)

Detail Unit Rate Per 1000 Cft.


Rate
Qty Per Unit Amount

Analysis for 800 Cft.


MATERIAL

i) Depreciation

Cost of pump set 6"x5" with 15 HP


diesel engine. 0
Anticipated life of pump 10000 Hours
Residual Charges 1/6 x 0 = 0
Rate of depriciation/hour0 - 0 -
10000
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

ii) Operation charges

LABOUR FOR 800 CFT.

1 Driver 1.00 No. 0.00 per day -


Cooly 1.00 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Rate Per Hour = 296.45 = Rs. 37.06 -


8
iii) P.O.L Charges Etc.

H.S. Diesel Oil


0.6 / Ltr Per Hour =0.6x8 4.80 Litre 4.80 Litre 0.00Per Litre -

Mobil Oil 1.00 Litre 0.00Per Litre -

Cotton Waste, Grease & Packing etc. L.S. -


Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Rate Per Hour = 148.50 = Rs. 18.56 -


8

iv) Accessories, repair and replacement portion


(maintenance charges etc.) L.S. -

ITEM RATE

Labour Rate Per 1000 Cft. Rs. Say 0.00


Labour Rate Per Cum Rs. Say 0.00
Composite Rate Per 1000 Cft. Rs. Say 0.00
Composite Rate Per Cum. Rs. Say 0.00

Page 34
36 Drilling holes in R.C. trough

Detail Unit Rate Per No.


Rate
Qty Per Unit Amount

LABOUR FOR 12 NOS.

1 Blacksmith 1.00 No. 0.00 per day -


2 Cooly 1.00 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 12 Nos. -

ITEM RATE

Labour Rate Per No. Rs. - Say 0.00

Page 35
37. Supplying and Laying polythene sheet over D.P.C., under floor and on roof etc.

i) 300 Gauge (0.003" thick)

Detail Unit Rate Per Sft. / Assumed for 100 Sft.


Rate
Qty Per Unit Amount

MATERIAL

1 Polythene of (0.003 thick) size 100 Sft. 1.500 Lbs.


Add 5%overlap = 5% 0.08 Lbs.
1.58 Lbs (0.717 Kg 0.00 Per Kg. -
Contractor's Profit & Ove 20.0 Percent -

Total

LABOUR

1 Cooly (skilled) 0.15 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Sft. Rs. Say 0.00


Labour Rate Per Sqm. Rs. Say 0.00
Composite Rate Per Sft. Rs. Say 0.00
Composite Rate Per SQm. Rs. Say 0.00

Page 36
37 ii 500 Gauge (0.005" thick)

Detail Unit Rate Per Sft. / Assumed for 100 Sft.


Rate
Qty Per Unit Amount

MATERIAL

1 Polythene sheet of 0.005" gauge 1.32 Lbs (0.600 Kg 0.00 Kg. -


Including 5% Extra for Overlap

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Cooly (skilled) 0.30 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Sft. Rs. Say 0.00


Labour Rate Per Sqm. Rs. Say 0.00
Composite Rate Per Sft. Rs. Say 0.00
Composite Rate Per Sqm Rs. Say 0.00

Page 37
38. Laying 2" thick sand and bitumen carpet on top of foundation of oil tanks

Detail Unit Rate 100 Sft. / Assumed for 246 Sft.


Rate
Qty Per Unit Amount

MATERIAL ( 2464 = 410 Cft.)


6
1 Sand 410.00 Cft. 0.00er 100 Cf -
2 Bitumen 1.23 Ton 0.00 Per Ton -
3 Coal 1.00 Mnd. (37.324 K 0.00 Per Kg. -
4 Fuel wood 58.20 Kg. 0.00 Per Kg. -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR

1 Mason 12.00 Nos. 0.00 Per day -


2 Cooly 35.00 Nos. 0.00 Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say 0.00


Labour Rate Per Sqm. Rs. - Say 0.00
Composite Rate Per 100 Sft. Rs. - Say 0.00
Composite Rate Per Sqm Rs. - Say 0.00

Page 38
39 Cutting hole 4" x 6" in stone masonry or brick wall with chisel, repairing masonry and
removing debris within one chain lead.

Detail Unit Rate Per Hole


Rate
Qty Per Unit Amount

LABOUR FOR 7 HOLES

1 Mason 1.00 No. 0.00 per day -


2 Cooly Unskilled 1.00 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Hole Rs. - Say 0.00

40 Making 1"x1" groove in wall of stone or brick masonry in cement for fixing planks upto
9" deep.

Detail Unit Rate Per Plank


Rate
Qty Per Unit Amount

LABOUR FOR 4 NOS. PLANKS

1 Mason 0.50 No. 0.00 per day -


2 Cooly 0.50 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Plank Rs. - Say 0.00

Page 39
41. Drilling holes in stone or bricks masonry upto 2" dia, per inch depth.

Detail Unit Rate Per Hole Per Inch. Depth


Rate
Qty Per Unit Amount

LABOUR FOR 10 NOS.

1 Cooly Unskilled 1.00 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Hole per Inch Depth Rs. - Say 0.00
Per CM Rs/ - Say 0.00

Page 40
42 Spraying anti termite liquid mixed with water in the ratio of (1.40)

Detail Unit Rate Per 100 Sft. / Assumed for 1000 Sft.
Rate
Qty Per Unit Amount

MATERIAL FOR 1000 SFT.

1 Termite Liquid 1.04 Litre 0.00 P. Litre -


2 Spraying Machine L.S. 0.00 -

Total -
Contractor's Profit & Ove 20.0 Percent -
Total -

LABOUR for 1000 sft

1 Sprayman 1.00 No. 0.00 per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. Say 0.00


Labour Rate Per Sqm. Rs. Say 0.00
Composite Rate Per 100 Sft. Rs. Say 0.00
Composite Rate Per Sqm. Rs. Say 0.00

Page 41
43 Providing and fixing barbed wire fencing with 4 horizontal and two cross wires, with RCC
1:2:4 posts 5.5' x 6" x9" at 8 ft. centre to centre. Reinforced with 4 number 3/8" dia ve
1/8" dia stirrups 12" centre to centre, complete in all respects.

i) Without cement concrete base.

Detail Unit Rate Per 100 Rft.


Rate
Qty Per Unit Amount

ASSUMED FOR 48 RFT.


MATERIAL
i) RCC Post (1:2:4)
6.5 x 5'.5x0.5x0.75 = 13.40 Cft.
(Item 6 a (i) of Concrete) 13.400 Cft. 0.00 Per Cft. -

ii) Fabrication of steel work as per


S No. 9 (b) Chapter Concrete
3/8" dia 4 x 5.5 = 22 Rft. @ Lbs /Rft
1/8 dia stirrups 5 x 2 = 10 Rft @ 0.042 Lbs/R
For 6.5 x 8.67 lbs = 56.3 8.67 Lbs 25.51 Kgs. 0.00 Per Kg. -

iii) Strained barbed wire


Horizontal 4x48' 192.00 Lft.
Cross 2 Nox6x9.4 112.8 Lft.
304.80 Lft.
Wastage 5% 15 14.74 Kg. 0.00 Per Kg. -
320.00 Lft.
320 Lt. @ 1.25 Cwt/450 Yard =0.29 Cwt

iv) Eye bolts 4 No.x7 post 28.00 Nos. 0.00 Each -

v) Washers 28.00 Nos. 0.00 dozen -

Contractor's Profit & Ove 20.00 Percent -


on item iii and iv and (v) -
Total (I to V) -
x 100
Rate per 100 Rft. 48

LABOUR

i) RCC as per item 6 - a (i) Chap. Concrete 13.40per Cft 0.00 Per Cft. -

ii) Fabrication of steel as per item 9 (b) Chap. 25.51 Per Kg. 0.00 Per Kg. -

iii) Fixing barbed wire black smith 0.75 No. 0.00 Per day -
Coolies 2.00 Nos. 0.00 Per day -

Total -
Sundries (Item-III) 10.00 Percent # -
Contractor's Profit & Ove 20.00 Percent # -
Total for 48 Rft. -

Rate per 100 Rft. 867.21 100 = Say


48
ITEM RATE
Labour Rate Per 100 Rft. Rs. Say 0.00
Labour Rate Per Metre Rs. Say 0.00
Composite Rate Per 100 Rft Rs. Say 0.00
Composite Rate Per Metre Rs. Say 0.00

Page 42
ii) In cement concrete base. (1:4:8) of size 12"x12"x21")

Detail Unit Rate Per 100 Rft.


Rate
Qty Per Unit Amount

MATERIAL FOR 48 RFT

i) RCC Post (1:2:4) as per part (i) Ref. 6 a (i) 13.40 Cft. Per Cft.

ii) Base (1:4:8) 12"X12"X21" 1.75 Cft.


d/D=0.5X0.75X0.75 = 0.28
Net 1.47 x 6.5 9.55 Cft. 0.00 Per Cft.

iii) Fabrication of steel


as per Item 9 (b) of Chapter Concrete 25.51 Kg. 0.00 Per Kg. -

iv) Strained barbed wire


Horizontal 4x48' 192.00 Lft.
Cross 2 Nox6x9.4 112.8 Lft.
304.80 Lft.
Add 5% wastage 15.2 Lft.
320.00 Lft.
14.74 Kg. 0.00 Per Kg. -

iv) Eye bolts 4 No.x7 post 28.00 Nos. 0.00 Each -

v) Washers 28.00 Nos. 0.00 dozen -


Total -
Contractor's Profit & Ove 20.00 Percent # -
Total for 48 Rft. -

Rate for 100 Rft. x 100 -


48 Say 0.00
LABOUR

i) RCC (1:2:4) (Rate as per item 6 a (i) of Chap 13.40 Cft. 0.00 Per Cft. -

ii) PCC (1:4:8) (Rate as per item 3 b of Chap No. 9.55 Cft. 0.00 Per Cft.

iii) Fabrication of steel as per item 9 (b) of Chap 25.51 Kg. 0.00 Per Kg.

iv) Fixing barbed wire

Blacksmith for wire 0.75 No. 0.00 Per day -


Coolies for erection 2.00 Nos. 0.00 Per day -
Total
Sundries (Item-IV) 10.00 Percent # -
Total -
Contractor's Profit & Ove 20.00 Percent # -
Total for 48 Rft. -

Rate for 100 Rft. x 100


48
ITEM RATE
Labour Rate Per 100 Rft. Rs. Say 0.00
Labour Rate Per Metre Rs. Say 0.00
Composite Rate Per 100 Rft. Rs. Say 0.00
Composite Rate Per Metre Rs. Say 0.00

Page 43
CHAPTER NO. 17

OUTLETS

DESCRIPTION OF ITEM:

1.0 Earth Work for Outlet excavation, refilling, ramming and Puddling

Rate for all finished works include the removal of the surplus debris un-used material and by

a) Channel Discharge upto 50 Cs.

Detail Unit Rate Per Job


Rate
Qty Per Unit Amount

Assumed for 1.5 Job

LABOUR

1 Coolies (Unskilled) 2.50 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Job Rs. 0.00 = Say -


1.5

b) Channels discharge from 51-100 Cs.

Detail Unit Rate Per Job


Rate
Qty Per Unit Amount

Assumed for 1.5 Job

LABOUR

1 Coolies (Unskilled) 3.30 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Job Rs. 0.00 = Say -


1.5

Page 1
c) Channels discharge from 101-200 Cs.

Detail Unit Rate Per Job


Rate
Qty Per Unit Amount

Assumed for 1.5 Job


LABOUR

1 Coolies (Unskilled) 5.00 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Job Rs. 0.00 = Say -


1.5

d) Channels discharge from 201-350 Cs.

Detail Unit Rate Per Job


Rate
Qty Per Unit Amount

Assumed for 1.5 Job


LABOUR

1 Coolies (Unskilled) 6.75 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Job Rs. 0.00 = Say -


1.5

e) Channels Discharges Over 350 Cusecs

Detail Unit Rate Per Job


Rate
Qty Per Unit Amount

Assumed for 1.5 Job


LABOUR

1 Coolies (Unskilled) 10.00 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE
Labour Rate Per Job Rs. 0.00 = - Say -
1.5

Page 2
2. Dismantling Outlets

Note : These rates are for total dismantlement and removal of material. The rates do
not include earth work for which rates are given in item No. 1 above

a) Old types such as K.G.O's Orifices etc.

Detail Unit Rate for Each


Rate
Qty Per Unit Amount

Assumed for 1.5 Nos.

LABOUR

1 Coolies (Unskilled) 2.50 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = 0 Say -


1.5

b) A.P.M. or O.F.H upto 2.0 Ft. (610mm)

Detail Unit Rate for Each


Rate
Qty Per Unit Amount

Assumed for 1.5 Nos.

LABOUR

1 Coolies (Unskilled) 3.75 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = Say -


1.5

Page 3
c) A.P.M. or O.F.H from 2.1 ft. (635mm) to 3.00 ft. (915mm)

Detail Unit Rate for Each


Rate
Qty Per Unit Amount

Assumed for 1.5 Nos.


LABOUR

1 Coolies (Unskilled) 5.00 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = - Say -


1.5

d) A.P.M. or O.F. 'H' above 3.0 ft. (915mm)

Detail Unit Rate for Each


Rate
Qty Per Unit Amount

Assumed for 1.5 Nos.


LABOUR

1 Coolies (Unskilled) 6.25 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = - Say -


1.5

e) Tail Cluster bifurcation

Detail Unit Rate for Each


Rate
Qty Per Unit Amount

Assumed for 1.5 Nos.


LABOUR

1 Coolies (Unskilled) 3.75 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = - Say -


1.5

Page 4
f) Tail cluster trifurcation

Detail Unit Rate for Each


Rate
Qty Per Unit Amount

Assumed for 1.5 Nos.

LABOUR

1 Coolies (Unskilled) 5.00 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = - Say -


1.5

g) Tail Cluster Quadrification

Detail Unit Rate for Each


Rate
Qty Per Unit Amount

Assumed for 1.5 Nos.

LABOUR

1 Coolies (Unskilled) 6.25 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = - Say -


1.5

Page 5
3 Making Temporary A.P.M. Bricks Block and fixing at Site

Detail Unit Rate for Each


Rate
Qty Per Unit Amount

MATERIAL

1 Brick 20 Nos. Per 1000 No -


2 Cement 0.25 Bag Per Bag -
3 Sand 1 Cft. Cft. 3.50
Total 3.50
Contractor's Profit & Ove 20.00 Percent 0.70
Total 4.20

LABOUR

1 Mason 0.33 No. per day -


Cooly (Unskilled) 0.33 No. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. Say -


Composite Rate for Each Rs. Say -

4 Dismentalling Walls, taking out Temporary A.P.M. Bricks Block and fixing
iron block and rebuilding dismantled walls.

Detail Unit Rate Job


Rate
Qty Per Unit Amount

Assumed for 1.25 Job

LABOUR

1 Mason 0.75 No. per day -


Cooly (Unskilled) 1.00 No. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Job Rs. 0.00 = Say -


1.25

Page 6
5 Dismantling walls and fitting iron block of O.F. Outlets

Detail Unit Rate Each


Rate
Qty Per Unit Amount

Assumed for 1.25 Nos.


LABOUR

1 Mason 0.75 No. per day -


Cooly (Unskilled) 1.00 No. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = Say -


1.25

6 Constructing watching and removing bund for outlet built in running water

Detail Unit Rate Each


Rate
Qty Per Unit Amount

Assumed for 1.25 Nos.

LABOUR
a) Upto 3.0 ft. (915mm) depth

Cooly (Unskilled) 5.00 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = - Say -


1.25

Assumed for 1.25 Nos.

b) Above 3.0 ft. (915mm) depth

Cooly (Unskilled) 6.75 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = Say -


1.25

Page 7
7 Adjusting 'B' of tail cluster by dismantling and rebuilding throat walls.

Detail Unit Rate Each


Rate
Qty Per Unit Amount

MATERIAL

1 Brick 30 Nos. Per 1000 No -


2 Cement 0.30 Bag Per Bag -
3 Sand 2.00 Cft. 100 Cft. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR FOR 1.5 NOS.

Mason 0.40 No. per day -


Cooly (Unskilled) 0.75 No. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = - Say -


1.5
Composite Rate for Each Rs. Say -

8 Adjusting 'Y' of an A.P.M. Outlets including dismantling and rebuilding

Detail Unit Rate Each


Rate
Qty Per Unit Amount

MATERIAL

1 Brick 50 Nos. Per 1000 No -


2 Cement 0.50 Bag Per Bag -
3 Sand 2.00 Cft. 100 Cft. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR FOR 1.5 NOS.

Mason 0.75 No. per day -


Cooly (Unskilled) 1.50 Nos. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE
Labour Rate for Each Rs. 0.00 = - Say -
1.5
Composite Rate for Each Rs. Say -

Page 8
9 Extra Labour in Fixing A.P.M. and O.F. Outlets block including Dressing of Bricks.

Note: Rate to be Rs. 5.00 less in case of O.F.


Outlets when there is no O.F. iron block

a) For Channel Depth of 5.0 ft. (1.5 Metre)

Detail Unit Rate Each


Rate
Qty Per Unit Amount

MATERIAL

1 Cement 0.20 Bag Per Bag


2 Sand 1.00 Cft. 100 Cft. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (FOR 1.25 NOS.)

Mason 1.00 No. per day -


Cooly (Unskilled) 1.00 No. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Grand Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = Say -


1.25
Composite Rate for Each Rs. = Say -

b) For Channel depth of 4.0 ft. (1.2 m)

Detail Unit Rate Each


Rate
Qty Per Unit Amount

MATERIAL

1 Cement 0.20 Bag Per Bag -


2 Sand 1.00 Cft. Per 100 Cft -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (ASSUMED FOR 1.25 NOS.)

Mason 0.75 No. per day -


Cooly (Unskilled) 0.75 No. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE
Labour Rate for Each Rs. 0.00 = Say -
1.25
Composite Rate for Each Rs. = Say -

Page 9
c) For Channel depth of 3.0 ft. (915mm)

Detail Unit Rate Each


Rate
Qty Per Unit Amount

MATERIAL

1 Cement 0.20 Bag Per Bag


2 Sand 1.00 Cft. Per 100 Cft.
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (FOR 1.25 NO.)

Mason 0.60 No. per day -


Cooly (Unskilled) 0.60 No. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Grand Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = - Say -


1.25
Composite Rate for Each Rs. = Say -

d) For Channel depth of 2.0 ft. (610mm)

Detail Unit Rate Each


Rate
Qty Per Unit Amount

MATERIAL

1 Cement 0.15 Bag Per Bag -


2 Sand 1.00 Cft. Per 100 Cft -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (FOR 1.25 NOS.)

Mason 0.50 No. per day -


Cooly (Unskilled) 0.50 No. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = Say -


1.25
Composite Rate for Each Rs. = Say -

Page 10
e) For Channel depth of less than 2.0 ft (610mm)

Detail Unit Rate Each


Rate
Qty Per Unit Amount

MATERIAL

1 Cement 0.10 Bag Per Bag -


2 Sand 1.00 Cft. Per 100 Cft -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR (FOR 1.25 NOS.)

Mason 0.40 No. per day -


Cooly (Unskilled) 0.40 No. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = Say -


1.25
Composite Rate for Each Rs. Say -

10 Repairing damaged reducing collar of Hume Pipe Outlets

Detail Unit Rate Each


Rate
Qty Per Unit Amount

MATERIAL

1 Shingle/Stone Crushed 1.00 Cft. Per 100 Cft -


2 Cement 0.25 Bag Per Bag -
3 Sand 1.00 Cft. Per 100 Cft -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR

Mason 0.33 No. per day -


Cooly (Unskilled) 0.33 No. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate for Each Rs. Say -

Composite Rate for Each Rs. Say -

Page 11
11 Laying Iron Pipes of Outlets

Detail Unit Rate Per Foot


Rate
Qty Per Unit Amount

LABOUR FOR 1.25 RFT.

Mason 0.02 No. per day -


Cooly (Unskilled) 0.02 No. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Grand Total -

ITEM RATE

Labour Rate Per Foot Rs. 0.00 = Say -


1.25
Labour Rate per Metre Rs. Say -

12 Water allowance for constructing outlets or culverts when canal water is not flowing

Note: At the discreation of Engineering-in-charges depending upon


the distance and source or supply

Detail Unit Rate Each


Rate
Qty Per Unit Amount

Assumed for 1.5 Nos


LABOUR

(i) Cooly (Unskilled) 1.22 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Grand Total -

ITEM RATE

Labour Rate Per Each Rs. 0.00 = Say -


1.5

Assumed for 1.5 Nos.


LABOUR

(ii) Coolies (Unskilled) 2.50 Nos. per day -


Sandries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Grand Total -

ITEM RATE

Labour Rate Per Each Rs. 0.00 = Say -


1.5

Page 12
13 Hoisting and placing R.C. slabs or stone in position in outlets or W.C. culverts

Detail Unit Rate Each


Rate
Qty Per Unit Amount

Assumed for 1.5 Nos.

LABOUR

Mason 0.20 No. per day -


Cooly (Unskilled) 0.65 No. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Grand Total -

ITEM RATE

Labour Rate for Each Rs. 0.00 = Say -


1.5

14 Fixing Pipe Outlet Including Back Filling or Earth and Puddling


a) Portion Under Bank

Detail Unit Rate Per Foot


Rate
Qty Per Unit Amount

Assumed for 15 Rft.


MATERIAL

1 Cement for Joining R.C. Collar 0.20 Bag Per Bag


2 Sand 1.00 Cft. Per 100 Cft.
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR
1 Mason 0.25 No. per day -
2 Cooly (Unskilled) 2.00 Nos. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Grand Total -

ITEM RATE
Labour Rate Per Foot Rs. 0.00 = Say -
15
Compsite Rate for Foot Rs. 0.00 = Say -
15
Labour Rate per Metre Rs. = Say -

Composite Rate per Metre Rs. = Say -

Page 13
b) Portion under road beyond bank

Detail Unit Rate (British System) per Rft.


Rate
Qty Per Unit Amount

Assumed for 15 Rft.

MATERIAL

1 Cement for Joining R.C. Collar 0.20 Bag Per Bag -


2 Sand 1.00 Cft. Per 100 Cft -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR

1 Mason 0.20 No. per day -


2 Cooly (Unskilled) 0.75 No. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Grand Total -

ITEM RATE

Labour Rate Per Foot Rs. 0.00 = - Say -


15
Composite Rate Per Foot Rs. 0.00 = - Say -
15
Labour Rate Per Metre Rs. = - Say -

Composite Rate per metre Rs. = - Say -

15 Removing Pipe Outlets Refilling Earth and Pudding

a) Portion Under Bank

Detail Unit Rate (British System) per Rft.


Rate
Qty Per Unit Amount

Analysis for 15 Ft.

LABOUR

Coolies (Unskilled) 2.00 Nos. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 15.0 Feet -

ITEM RATE

Labour Rate Per Foot Rs. 0.00 = Say -


15
Labour Rate Per Metre Rs. = Say -

Page 14
b) Portion Under Road Byond Bank

Detail Unit Rate (British System) per Foot


Rate
Qty Per Unit Amount

Analysis for 15.0 Ft.

LABOUR

Cooly (Unskilled) 0.75 No. per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 15 Feet -

ITEM RATE

Labour Rate Per Foot Rs. 0.00 = Say -


15
Labour Rate Per Metre Rs. = Say -

16 Changing Pipe Outlets by removing One Pipe and replacing it at the same site
with another pipe complete with earth and puddling

a) Portion Under Bank

Detail Unit Rate (British System) per Foot


Rate
Qty Per Unit Amount

Analysis for 15.0 Ft.

MATERIAL

1 Cement for Joining R.C. Collar 0.20 Bag Per Bag -


2 Sand 1.00 Cft. Per 100 Cft -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 12 Feet -

LABOUR

1 Mason 0.20 No. per day -


2 Cooly (Unskilled) 2.50 Nos. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 15 Feet -
ITEM RATE

Labour Rate Per Foot Rs. - Say -


15
Composite Rate per Foot Rs. - Say -
15
Labour Rate Per Metre Rs. Say -
Composite Rate per Metre Rs. Say -

Page 15
b) Portion Under Road Beyond Bank

Detail Unit Rate (British System) per Foot


Rate
Qty Per Unit Amount

Analysis for 15.0 Ft

MATERIAL
1 Cement for Joining R.C. Collar 0.20 Bag Per Bag -
2 Sand 1.00 Cft. Per 100 Cft -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR

1 Mason 0.10 No. per day -


2 Coolies (Unskilled) 1.25 Nos. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Grand Total -

ITEM RATE

Labour Rate Per Foot Rs. 0.00 Say -


15
Composite Rate Per Foot Rs. - Say -
15
Labour Rate Per Metre Rs. Say -
Composite Rate Per Metre Rs. Say -

Page 16
CHAPTER NO. 13

PAINTING AND VARNISHING


Note : Rates for all finished works include the re
surplus debris, unused material and by-prod

DESCRIPTION OF ITEM NO 1:

a) Cleaning painted wood work with oil and wat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Oil Terpen tine 0.5Lbs (0. 26) Ltr P. Ltr -


Brushes (Small) 0.04 No. Each -
Sand Paper 0.16 No. P. Doz -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Unskilled Cooly 0.20 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 1
Item No. 1

b) Oiling wood work with boiled linseed oil.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Linseed oil 0.40 Kg P. Kg -


Brushes (Small) 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Unskilled Cooly 0.20 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Labour Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 2
DESCRIPTION OF ITEM NO 2: Brushing and Scraping blisters of old paint
wood works.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

N I L

Labour
Rate Analysis for 125 Sft
Unskilled Cooly 0.50 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
1.25

Labour Rate Per Sqm Rs. Say -

Page 3
DESCRIPTION OF ITEM NO 3: Scraping, brushing and removing old paints
metal surface.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

N I L

Rate Analysis for 125 Sft


Labour

Unskilled Cooly 2.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
1.25

Labour Rate Per Sqm Rs. Say -

Page 4
DESCRIPTION OF ITEM NO 4: Painting old surfaces.

a) Painting corrugated surfaces, patent roofin


with oil paint.
i) First Coat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 2Lbs (0. 20) Gln P. Gln -


Brushes (Small) 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Painter 0.33 No P. Day -
Unskilled Cooly 0.33 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Labour Rate per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 5
Item No. 4 Painting old surfaces.

a) Painting corrugated surfaces, patent roofin


with oil paint.
ii) Each Subsequent Coat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 1Lbs (0. 10) Gln P. Gln -


Brushes (Small) 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Painter 0.25 No P. Day -
Cooly 0.25 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Labour Rate per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 6
Item No. 4 Painting old surfaces.

b) Painting sashes, fanlights, glazed or gauzed doors


and windows.
i) First Coat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 1Lbs (0. 10) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Painter 0.20 No P. Day -
Unskilled Cooly 0.20 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Labour Rate per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 7
Item No. 4 Painting old surfaces.

b) Painting sashes, fanlights, glazed or gauzed doors


and windows.
ii) Each Subsequent Coat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 0.75Lbs ( 0.08) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Painter 0.17 No P. Day -
Unskilled Cooly 0.17 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Labour Rate per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 8
Item No. 4 Painting old surfaces.

c) Painting doors & windows any type.


i) First Coat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 2Lbs (0. 20) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Painter 0.33 No P. Day -
Unskilled Cooly 0.33 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Labour Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 9
Item No. 4 Painting old surfaces.

c) Painting doors & windows any type.


ii) Each Subsequent Coat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 1.5Lbs (0. 15) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Painter 0.25 No P. Day -
Unskilled Cooly 0.25 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Labour Rate per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 10
Item No. 4 Painting old surfaces.

d) Painting guard bars, gates of iron bars, gratings,


railing (including) standards, braces etc.) and
similar open works.
i) First Coat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 1Lbs (0. 10) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Painter 0.20 No P. Day -
Unskilled Cooly 0.20 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Labour Rate per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 11
Item No. 4 Painting old surfaces.

d) Painting guard bars, gates of iron bars, gratings,


railing (including) standards, braces etc.) and
similar open works.
ii) Each Subsequent Coat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 0.75Lbs ( 0.08) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Painter 0.17 No P. Day -
Unskilled Cooly 0.17 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Labour Rate per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 12
Item No. 4 Painting old surfaces.

e) Painting fillets, framing, skirtings, pipes, gutters


and similar linear work, not exceeding 6" in girth.
i) First Coat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 1Lbs (0. 10) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Rft
Painter 0.17 No P. Day -
Unskilled Cooly 0.17 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Labour Rate per 100 Sft. -
Item Rates
Labour Rate Per 100 Rft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per 100 Rft Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 13
Item No. 4 Painting old surfaces.

e) Painting fillets, framing, skirting, pipes, gutters


and similar linear work, not exceeding 6" in girth.
ii) Each Subsequent Coat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 0.75Lbs ( 0.08) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Rft
Painter 0.12 No P. Day -
Unskilled Cooly 0.12 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Labour Rate per 100 Sft. -
Item Rates
Labour Rate Per 100 Rft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per 100 Rft Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 14
Item No. 4 Painting old surfaces.

f) Painting small detached articles not exceeding one


square foot of painted surface.
i) First Coat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 2Lbs (0. 20) Gln P. Gln -


Brushes (Small) 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 200 Nos
Painter 1.00 No P. Day -
Unskilled Cooly 0.25 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Labour Rate per 100 Nos. -
Item Rates
Labour Rate Per 100 Nos Rs. Say -

Composite Rate Per 100 Nos Rs. Say -

Page 15
Item No. 4 Painting old surfaces.

f) Painting small detached articles not exceeding one


square foot of painted surface.
ii) Each Subsequent Coat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 1Lbs (0. 10) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 175 No.
Painter 0.75 No P. Day -
Unskilled Cooly 0.25 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Labour Rate per 100 Nos. -
Item Rates
Labour Rate Per 100 Nos Rs. Say -

Composite Rate Per 100 Nos Rs. Say -

Page 16
Item No. 4 Painting old surfaces.

g) Painting small detached articles, exceeding one


square foot (0.09 Sqm) but not exceeding three
square foot (0.81 Sqm) of painted surface.
i) First Coat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 6Lbs (0. 60) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 175 No.
Painter 2.00 No P. Day -
Unskilled Cooly 0.50 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Labour Rate per 100 Nos. -
Item Rates
Labour Rate Per 100 Nos Rs. Say -

Composite Rate Per 100 Nos Rs. Say -

Page 17
Item No. 4 Painting old surfaces.

g) Painting small detached articles, exceeding one


square foot but not exceeding three square foot of
painted surface.
ii) Each Subsequent Coat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 3Lbs (0. 30) Gln P. Gln -


Brushes (Small) 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 175 No.
Painter 1.00 No P. Day -
Unskilled Cooly 0.50 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Labour Rate per 100 Nos. -
Item Rates
Labour Rate Per 100 Nos Rs. Say -

Composite Rate Per 100 Nos Rs. Say -

Page 18
DESCRIPTION OF ITEM NO 5:
a) Painting/ new surface preparing surface and
painting corrugated surface, patent roofing etc.

i) Priming Coat

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 3Lbs (0. 30) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Painter 0.50 No P. Day -


Unskilled Cooly 0.12 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 19
Item No. 5

a) Painting/ new surface preparing surface and


painting corrugated surface, patent roofing etc.
ii) Each Subsequent Coat of paint.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 2.50Lbs (0 .25) Gln P. Gln -


Brushes (Small) 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Painter 0.25 No P. Day -
Unskilled Cooly 0.08 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 20
Item No. 5

b) Preparing surface and painting sashes, fan light


glazed or gauzed doors and windows etc. any type
(including edges)
i) Priming Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 1.75Lbs(0 .175) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Painter 0.25 No P. Day -
Unskilled Cooly 0.08 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 21
Item No. 5

b) Preparing surface and painting sashes, fan light,


glazed or gauzed doors and windows etc. any type
(including edges)
ii) Each Subsequent Coat of Paint.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 1.4Lbs (0 .14) Gln P. Gln -


Brushes (Small) 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Painter 0.12 No P. Day -
Unskilled Cooly 0.12 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 22
Item No. 5

c) Preparing surface and painting of doors and


windows any type (including edges).
i) Priming Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 3Lbs (0 .3) Gln P. Gln -


Brushes (Small) 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Painter 0.50 No P. Day -


Unskilled Cooly 0.12 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 23
Item No. 5

c) Preparing surface and painting of doors and


windows any type (including edges).
ii) Each Subsequent Coat of Paint.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 2.50Lbs ( 0.25) Gln P. Gln -


Brushes (Small) 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Painter 0.25 No P. Day -
Cooly 0.08 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate per 100 Sft.
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 24
Item No. 5

d) Preparing surface and painting guard bars, gates of


iron bars, gratings, railing (including standards
braces, etc.) and in similar open work.
i) Priming Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 1.75Lbs(0 .175) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Painter 0.25 No P. Day -


Unskilled Cooly 0.17 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 25
Item No. 5

d) Preparing surface and painting guard bars, gates of


iron bars, gratings, railing (including standards
braces, etc.) and in similar open work.
ii) Each Subsequent Coat of Paint.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 1.4Lbs (0 .14) Gln P. Gln -


Brushes (Small) 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Painter 0.12 No P. Day -
Unskilled Cooly 0.12 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 26
Item No. 5

e) Preparing surface and painting of fillets, framing,


skirtings, pipes gutters and similar linear work not
exceeding 6" girth.
i) Priming Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 1.3Lbs (0 .13) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Painter 0.17 No P. Day -


Unskilled Cooly 0.17 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Item Rates
Labour Rate Per 100 Lft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per 100 Lft Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 27
Item No. 5

e) Preparing surface and painting of fillets, framing,


skirting, pipes gutters and similar linear work not
exceeding 6" girth.
ii) Each Subsequent Coat of Paint.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 1.1Lbs (0 .11) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Rft
Painter 0.08 No P. Gln -
Unskilled Cooly 0.08 No P. Gln -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Rft. -
Item Rates
Labour Rate Per 100 Lft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per 100 Lft Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 28
Item No. 5

f) Preparing surface and painting of small detached


articles not exceeding one square foot of painted
surface.
i) Priming Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 6.25Lbs(0 .625) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Nos
Painter 0.75 No P. Day -
Unskilled Cooly 0.75 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate per 100 Nos. -
Item Rates
Labour Rate Per 100 Nos Rs. Say -

Composite Rate Per 100 Nos Rs. Say -

Page 29
Item No. 5

f) Preparing surface and painting of small detached


articles not exceeding one square foot of painted
surface.
ii) Each Subsequent Coat of Paint.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 5Lbs (0 .50) Gln P. Gln -


Brushes (Small) 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 No
Painter 0.40 No P. Day -
Unskilled Cooly 0.33 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate per 100 Nos. -
Item Rates
Labour Rate Per 100 Nos Rs. Say -

Composite Rate Per 100 Nos Rs. Say -

Page 30
Item No. 5

g) Preparing surface and painting of small detached


articles exceeding one square foot and not
exceeding 3 square foot of painted surface.
i) Priming Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 12Lbs (0 1.2) Gln P. Gln -


Brushes (Small) 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Painter 1.75 No P. Day -


Unskilled Cooly 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Item Rates
Labour Rate Per 100 Nos Rs. Say -

Composite Rate Per 100 Nos Rs. Say -

Page 31
Item No. 5

g) Preparing surface and painting of small detached


articles exceeding one square foot and not
exceeding 3 square foot of painted surface.
ii) Each Subsequent Coats of Paint.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Oil Paint 9Lbs (0 .9) Gln P. Gln -


Brushes (Small) 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 No
Painter 0.75 No P. Day -
Unskilled Cooly 0.50 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate per 100 Nos. -
Item Rates
Labour Rate Per 100 Nos Rs. Say -

Composite Rate Per 100 Nos Rs. Say -

Page 32
Item No. 5

h) Extra for knotting and stopping to priming coats on


new surface of wood.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint etc. 0.018 Gln. P. Gln -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Painter 0.06 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Rft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 33
DESCRIPTION OF ITEM NO 6: Applying Khanki Mixture hot to barrage gate

i) First Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
Coaltar 0.75Cwt ( 38) Kg P. Kg -
Mineralpitch 10Lbs (4. 5) Kg P. Kg -
Slaked lime 9Lbs (4 ) Kg P. Kg -
Kerosene Oil 1Gln (4. 55) Ltr P. Ltr -
Fuel Wood 32.45 Kg. P. Kg -
-
Material
For 100 Sft
i) First Coat

= 0.00
20
Brushes 0.18 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Painter 0.25 No P. Day -
Unskilled Cooly 0.25 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 34
Item No. 6 Applying Khanki Mixture hot to barrage gates.

ii) Second Coats.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
For 100 Sft
ii Second Coat Material 0.62 of Item No. (6-I)

0.62 -

Brushes 0.18 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Painter 0.16 No P. Day -
Unskilled Cooly 0.25 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 35
DESCRIPTION OF ITEM NO 7: French polishing complete.

a) On new works.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

French Polish 0.5Lbs 23) Kg P. Kg -


Brushes 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 175 Sft
Polisher 4.50 No P. Day -
Unskilled Cooly 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 36
Item No. 7 French polishing complete.

b) Old work.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

French Polish 0.25Lbs ( 0.11) Kg P. Kg -


Brushes 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 175 Sft
Polisher 2.00 No P. Day -
Unskilled Cooly 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 37
DESCRIPTION OF ITEM NO 8: Varnishing wood work, including cleaning an
preparing surface.

a) First Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Varnish 0.33Gln ( 1.50) Kg P. Kg -


Brushes 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Polisher 0.20 No P. Day -
Unskilled Cooly 0.20 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 38
Item No. 8 Varnishing wood work including cleaning and
preparing surface.

b) Second Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Varnish 0.25Gln ( 1.13) Kg P. Kg -


Brushes 0.10 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 200 Sft
Polisher 0.10 No P. Day -
Unskilled Cooly 0.10 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 39
Item No. 8 Varnishing wood work including cleaning and
preparing surface.

c) Third Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Varnish 0.2Gln ( 0.91) Kg P. Kg -


Brushes 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 200 Sft
Polisher 0.10 No P. Day -
Unskilled Cooly 0.10 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft.
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 40
DESCRIPTION OF ITEM NO 9: Bitumen coating to plastered or cement conc
surface.

i) 20 Lbs per 100 Sft.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bitumen 20Lbs ( 9.07) Kg P. Kg -


Fuel 4.26 Kg. P. Kg -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Unskilled Cooly 0.50 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 41
Item No. 9 Bitumen coating to plastered or cement concrete
surface.

ii) 14 Lbs per 100 Sft.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bitumen 10Lbs ( 4.54) Kg P. Kg -


Fuel 2.84 Kg. P. Kg -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Cooly 0.40 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 42
Item No. 9 Bitumen coating to plastered or cement concrete
surface.

iii) 10 Lbs per 100 Sft.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bitumen 10Lbs ( 4.54) Kg P. Kg -


Fuel 2.84 Kg. P. Kg -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Cooly 0.33 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 43
DESCRIPTION OF ITEM NO 10: Writing letters or figures per letter, per
height.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 100 Nos

Material

Paint 0.6Lbs (0. 06) Gln P. Gln -


Brushes 0.18 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate Per No. 0.00 -


100
Labour
Rate Analysis for 150 Nos
Painter (Artisit) 1.00 No P. Day -
Unskilled Cooly 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per No. -
Item Rates
Labour Rate Per No. Rs. Say -

Composite Rate Per No. Rs. Say -

Page 44
DESCRIPTION OF ITEM NO 11: Writing letters or figures at any surface w
reflective paint of approved quality and co
letter, per inch height.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
nalysis for 100 Letters, P. Inch Height

Material

Reflective Paint 0.6Lbs (0. 06) Gln P. Gln -


Brushes 0.18 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate Per No. 0.00 -


100
Labour
Rate Analysis for 150 No.
Painter (Artisit) 1.00 No P. Day -
Unskilled Cooly 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per No. -
Item Rates

Labour Rate P. Letter, P. Inch height Rs. Say -

Composite Rate P. Letter, P. Inch height Rs. Say -

Page 45
DESCRIPTION OF ITEM NO 12: Writing letters or figures on any surface w
reflective tape of approved quality and col
letter, per inch height.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
nalysis for 100 Letters, P. Inch Height

Material

Reflective tape/ paper 1.00 Sft P. Sft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -
Rate Per Plinth, Per Inch height 0.59
Labour

Painter (Artisit) 1.00 No P. Day -


Unskilled Cooly 0.50 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per Plinth, Per Inch height -
Item Rates

Labour Rate P. Letter, P. Inch height Rs. Say -

Composite Rate P. Letter, P. Inch height Rs. Say -

Page 46
DESCRIPTION OF ITEM NO 13: Coaltar Painting.

a) First Coat laid hot.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Coaltar 16Lbs (7. 26) Kg P. Kg -


Fuel etc. 2.18 Kg. P. Kg -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Skilled Cooly 0.33 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 47
Item No. 13 Coaltar Painting.

b) Second Coat laid hot.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Coaltar 10Lbs (4 .5) Kg P. Kg -


Fuel etc. 2.18 Kg. P. Kg -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Skilled Cooly 0.20 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 48
DESCRIPTION OF ITEM NO 14: Solignum Painting.

a) One Coat applied hot.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Solignum Paint 0.20Lbs ( 0.02) Gln P. Gln -


Brushes 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Painter 0.33 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 49
Item No. 14 Solignum Painting.

b) Two Coat applied hot.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Solignum Paint 0.34Lbs(0 .034) Gln P. Gln -


Brushes 0.16 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 150 Sft
Painter 0.50 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 50
DESCRIPTION OF ITEM NO 15: Creosote Painting.

a) One Coat applied hot.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Creosote 0.20 Gallon P. Gln -


Brushes fuel 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Painter 0.33 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 51
Item No. 15 Creosote Painting.

b) Two Coat applied hot.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Creosote 0.34 Gln P. Gln -


Brushes fuel 0.16 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Painter 0.50 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 52
DESCRIPTION OF ITEM NO 16: Burning off or rubbing down with pumice sto
paint from wood work.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Burner Charges L.S.


Kerosene Oil L.S.
Scraper L.S. -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Skilled Cooly 1.00 No P. Day -
Unskilled Cooly 0.25 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 53
DESCRIPTION OF ITEM NO 17: Removing with caustic soda, old paint from
work.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Caustic soda 0.09 Kg. P. Kg. -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Cooly 0.50 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 54
DESCRIPTION OF ITEM NO 18: Painting distance marks for white ground an
lettering on both faces.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 10 Nos

Material

Brushes 0.04 No. Each -


White paint 0.5Lbs (0. 05) Gln P. Gln -
Black japan 0.2Lbs (0. 02) Gln P. Gln -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate Per No. 0.00 -


10
Labour
Rate Analysis for 15 No.
Painter (Artist) 0.50 No P. Day -
Unskilled Cooly 0.50 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per No. -
Item Rates
Labour Rate Per No. Rs. Say -

Composite Rate Per No. Rs. Say -

Page 55
DESCRIPTION OF ITEM NO 19: Painting two feet (M) with gauge reading to
a foot (M).

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 10 Rft

Material

Paint white and black 1Lbs (0. 1) Gln P. Gln -


Brushes 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate Per Rft 0.00 -


10
Labour
Rate Analysis for 15 Rft
Painter (Artist) 1.00 No P. Day -
Unskilled Cooly 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per Rft. -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per Rft Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 56
DESCRIPTION OF ITEM NO 20: Painting sounding rods and other gauge, rea
10th of a foot (M).

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 10 Rft

Material

Paint black and white 0.25Lbs ( 0.03) Gln P. Gln -


Brushes 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate Per Rft 0.00 -


10
Labour
Rate Analysis for 15 Rft
Painter (Artist) 0.50 No P. Day -
Unskilled Cooly 0.50 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per Rft. -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per Rft Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 57
DESCRIPTION OF ITEM NO 21: Painting levelling staves.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 10 Rft

Material

Paint black and white 0.5Lbs (0 .05) Gln P. Gln -


Brushes 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -
Rate Per Rft 0.00 -
10
Labour
Rate Analysis for 15 Rft
Painter (Artist) 2.00 Nos P. Day -
Cooly 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per Lft. -
Item Rates
Labour Rate Per Lft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per Lft Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 58
DESCRIPTION OF ITEM NO 22:
a) Painting and lettering mile/Km stones on bo

i) One Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint black and white 0.35Lbs(0 .035) Gln P. Gln -


Brushes 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 2 Nos
Painter (Artist) 1/7 No P. Day
Unskilled Cooly 1/7 No P. Day

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per Each -
Item Rates
Labour Rate Per Each Rs. Say -

Composite Rate Per Each Rs. Say -

Page 59
Item No. 22

a) Painting and lettering mile/Km stones on bo

ii) Two Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint white and black 0.6Lbs (0. 06) Gln P. Gln -


Brushes 0.02 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 2 Nos
Painter (Artist) 0.25 No P. Day -
Cooly 0.25 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per Each -
Item Rates
Labour Rate Per Each Rs. Say -

Composite Rate Per Each Rs. Say -

Page 60
Item No. 22

b) Painting and lettering furlong Km stone o


sides.

i) One Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 8 No.

Material

Paint white and black 0.35Lbs (0 .035) Gln P. Gln -


Brushes 0.02 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate Per Each 0.00 -


8
Labour
Rate Analysis for 15 Nos
Painter (Artist) 1/7 No P. Day
Cooly 1/7 No P. Day

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per No. -
Item Rates
Labour Rate Per Each Rs. Say -

Composite Rate Per Each Rs. Say -

Page 61
Item No. 22

b) Painting and lettering furlong Km stone on both


sides.

ii) Two Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 8 No.

Material

Paint white and black 0.6Lbs (0 .06) Gln P. Gln -


Brushes 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate Per Each 0.00 -


8
Labour
Rate Analysis for 15 No.
Painter (Artist) 0.25 No P. Day -
Cooly 0.25 No P. Day -

Total -
Sundries ##### Percent -
Total -
Rate Per No.
Contractor's Profit & Ove ##### Percent -
Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per Each Rs. Say -

Composite Rate Per Each Rs. Say -

Page 62
Item No. 22

c) Painting and lettering sign posts.

i) One Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1.5 Nos.

Material

Paint white and black 0.35Lbs (0 .035) Gln P. Gln -


Brushes 0.04 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate Per Each 0.00


1.5
Labour
Rate Analysis for 2.5 No.
Painter (Artist) 0.20 No P. Day -
Cooly 0.20 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per Each -
Item Rates
Labour Rate Per Each Rs. Say -

Composite Rate Per Each Rs. Say -

Page 63
Item No. 22

c) Painting and lettering sign posts.

ii) Two Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1.5 Nos

Material

Paint white and black 0.6Lbs (0 .06) Gln P. Gln -


Brushes 0.06 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate Per Each 0.00 -


1.5
Labour
Rate Analysis for 2.5 No.
Painter (Artist) 0.33 No P. Day -
Cooly 0.33 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per Each -
Item Rates
Labour Rate Per Each Rs. Say -

Composite Rate Per Each Rs. Say -

Page 64
DESCRIPTION OF ITEM NO 23: Removing paint or varnish from wall.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Sft

Labour

Unskilled Cooly 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -

Labour Rate Per Sqm Rs. Say -

Page 65
DESCRIPTION OF ITEM NO 24: Scraping from hydraulic gates.

a) Khanki Paint.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Sft

Labour

Unskilled Cooly 2.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -

Labour Rate Per Sqm Rs. Say -

Page 66
Item No. 24 Scraping from hydraulic gates.

b) Aluminium paint.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Sft

Labour

Unskilled Cooly 2.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -

Labour Rate Per Sqm Rs. Say -

Page 67
DESCRIPTION OF ITEM NO 25: Painting lettering with shade.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
nalysis for 100 Letters, P. Inch Height

Material

Paint 0.5Lbs (0 .05) Gln P. Gln -


Brushes 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -
36.85 0.37
Labour 100
Rate Analysis for 150 Letters
Painter (Artist) 1.60 No P. Day -
Unskilled Cooly 1.60 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 litters -
Item Rates
Labour Rate Per 100 Litter Rs. Say -
Labour Rate Per Each Rs. Say -

Composite Rate Per 100 Litter Rs. Say -


Composite Rate Per Each Rs. Say -

Page 68
DESCRIPTION OF ITEM NO 26: Scraping rust for old rail or girders.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Sand Paper 3.00 No. P. Doz -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Unskilled Cooly 1.50 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 69
DESCRIPTION OF ITEM NO 27: Chiselling old paint from brick work.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Steel Scrapper 1.00 No. P. Doz -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Unskilled Cooly 2.00 Nos P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 70
DESCRIPTION OF ITEM NO 28: Cleaning glasses with chalk and spirit etc

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 600 Sft

Material

Chalk 1.00 No. P. Doz -


Spirit 1.00 Litre P. Lit -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate Per 100 Sft 0.00 -


6
Labour
Rate Analysis for 750 Sft
Unskilled Cooly 10.00 Nos P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 71
DESCRIPTION OF ITEM NO 29: Cleaning and oiling rafter or rolled steel

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Oil 0.5Lbs (0 .37) Ltr P. Ltr -


Brushes 0.04 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Cooly 0.50 Nos P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 72
DESCRIPTION OF ITEM NO 30: Cleaning and painting punkha poles, includi
fixing hooks.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 3 Nos
Material

Paint 0.25Lbs (0 .025) Gln P. Gln -


Brushes 0.04 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate for Each 0.00 -


3
Labour
Rate Analysis for 4 Nos
Skilled cooly 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per No. -
Item Rates
Labour Rate Per Each Rs. Say -

Composite Rate Per Each Rs. Say -

Page 73
DESCRIPTION OF ITEM NO 31: Preparing surface and painting with emulsio

a) First Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 1.57Lbs ( 0.16) Gln P. Gln -


Brushes 0.08 No. Each -
Sand Paper 0.33 No. P. Doz -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Painter 0.33 No P. Day -
Unskilled Cooly 0.06 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 74
Item No. 31 Preparing surface and painting with emulsion paint.

b) 2nd Coat and subsequent coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Emulsion Paint 1.18Lbs (0 .118) Gln P. Gln -


Sand paper 1.17 No. P. Doz -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Painter 0.25 No P. Day -
Unskilled Cooly 0.05 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 75
DESCRIPTION OF ITEM NO 32: Preparing surface and painting with water p
coloured cement finish, like duracem, buxce
other finishes with similar specifications
etc.
a) New Surface
i) Ist Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint Durasum 1.50 Kg P. Kg -


Brushes 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Painter 0.33 No P. Day -
Unskilled Cooly 0.06 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 76
Item No. 32 Preparing surface and painting with water proof
coloured cement finish, like duracem, buxcem or
other finishes with similar specifications on walls,
etc.
a) New Surface
ii) 2nd Coat and subsequent coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Emulsion Paint 1.25 Kg P. Kg -


Brushes 0.12 No. Each -
Sand Paper 0.17 No. P. Doz -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 125 Sft
Painter 0.25 No P. Day -
Unskilled Cooly 0.05 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total
Rate Per 100 Sft.
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 77
Item No. 32 Preparing surface and painting with water proof
coloured cement finish, like duracem, buxcem or
other finishes with similar specifications on walls,
etc.
b) Old Surface
i) Ist Coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 1.25Lbs ( 0.57) Kg P. Kg -


Brushes 0.10 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour Rate for 125 Sft.

Painter 0.33 No P. Day -


Unskilled Cooly 0.06 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 78
Item No. 32 Preparing surface and painting with water proof
coloured cement finish, like duracem, buxcem or
other finishes with similar specifications on walls,
etc.
b) Old Surface
ii) 2nd Coat and subsequent coat.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Emulsion Paint 1.10Lbs ( 0.50) Kg P. Kg -


Sand paper 0.67 No. P. Doz -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour for 125 Sft.

Painter 0.25 No P. Day -


Unskilled Cooly 0.05 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total

Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 79
Item No. 32A Providing and applying weather shield paint of approved
quality on external surface of building including
preparation of surface application of primer complete
in all respects.
a) New Surface
i) Ist Coat

Detail Unit Rate (British System) per 10 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

i) Varnish 1 kg P. Kg -
ii) Putty and sand paper (L.S) 1 LS L.S -
iii) Primer (Zine) 1 Kg (for % Sft) @ Rs.80.00 per Kg. 1 P. Kg -
iv) Weather shield paint 0.7 Litre (for 100 Sft) 0.7 -
@ Rs.120.00 per Litre
Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Painter 0.40 No P. Day -


Cooly 0.80 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Item Rates
Labour Rate Per % Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per % Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 80
Item No. 32A Providing and applying weather shield paint of approved
quality on external surface of building including
preparation of surface application of primer complete
in all respects.
a) New Surface
ii) 2nd Coat

Detail Unit Rate (British System) per 10 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

i) Weather Shield paint 0.67 P. Lit -


0.67 litre (for 100 Sft) @ 120/- per litre

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Painter 0.25 No P. Day -


Cooly 0.40 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Item Rates
Labour Rate Per % Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per % Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 81
Item No. 32A Providing and applying weather shield paint of approved
quality on external surface of building including
preparation of surface application of primer complete
in all respects.
b) Old Surface

Detail Unit Rate (British System) per 10 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

i) Weather Shield paint 0.67 P. Lit -


0.67 litre (for 100 Sft) @ 120/- per litre

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Painter 0.25 No P. Day -


Cooly 0.40 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Item Rates
Labour Rate Per % Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per % Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 82
DESCRIPTION OF ITEM NO 33: Painting traffic lanes 5" (125mm) wide with
marking enamel.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 700 Rft

Material

Road marking enamel 7.3Lbs ( 3.32) Ltr P. Ltr -


Brushes 0.18 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate Per Rft 0.00 -


700
Labour
Rate Analysis for 1000 Rft
Painter 1.00 No P. Day -
Cooly 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Rft. -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per P.Rm Rs. Say -

Composite Rate Per Rft Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 83
DESCRIPTION OF ITEM NO 34: Painting traffic lanes 5" (125mm) wide with
paint, complete in all respects. marking en

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 700 Rft

Material

Reflective Paint 7.3Lbs ( 3.32) Ltr P. Ltr -


Brushes 0.18 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate Per Rft 0.00 -


700
Labour
Rate Analysis for 1000 Rft
Painter 1.00 No P. Day -
Cooly 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Rft. -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per P.Rm Rs. Say -

Composite Rate Per Rft Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 84
DESCRIPTION OF ITEM NO 35: Repainting of ceiling fan (all sizes and ty
including painting of blades, canopy, suspe
rod and regulator, with suitable enamel pai

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 0.13Lt (0 .03) Gln P. Gln -


Brush 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 14 No
Painter 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per Job -
Item Rates
Labour Rate Per Job Rs. Say -

Composite Rate Per Job Rs. Say -

Page 85
DESCRIPTION OF ITEM NO 36: Repainting of iron poles with cross arms, w
bitumen or other approved paint.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 0.6Ltr (0 .13) Gln P. Gln -


Brush 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour
Rate Analysis for 6 Nos
Painter 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per Job -
Item Rates
Labour Rate Per Job Rs. Say -

Composite Rate Per Job Rs. Say -

Page 86
DESCRIPTION OF ITEM NO 37: Repainting of pipes and specials of G.I. M
conduit etc. fixed on surface for electric
with approved paint.

i) Upto 40mm (1") dia.

Detail Unit Rate (Metric System) per Meter

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
Rate Analysis for 7 Metre
Paint 0.1Ltr (0. 022) Gln P. Gln -
Brush 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate for One Metre 0.00 -


7
Labour
Rate Analysis for 200 Metre
Painter 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Rate for One Metre -

Item Rates
Labour Rate Per Rm Rs. Say -
Composite Rate Per Rm Rs. Say -

Labour Rate Per Rft Rs. Say -


Composite Rate Per Rft Rs. Say -

Page 87
Item No. 37 Repainting of pipes and specials of G.I. M.S. or
conduit etc. fixed on surface for electric wiring
with approved paint.

ii) Above 40mm (1") to 50mm (2") dia.

Detail Unit Rate (Metric System) per Meter

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
Rate Analysis for 7 Metre
Paint 0.2Ltr (0. 044) Gln P. Gln -
Brushes 0.12 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate for One Metre 0.00 -


7
Labour
Rate Analysis for 100 Metre
Painter 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Rate for One Metre -

Item Rates
Labour Rate Per Rm Rs. Say -
Composite Rate Per Rm Rs. Say -

Labour Rate Per Rft Rs. Say -


Composite Rate Per Rft Rs. Say -

Page 88
Item No. 37 Repainting of pipes and specials of G.I. M.S. or
conduit etc. fixed on surface for electric wiring
with approved paint.

iii) Above 50mm (2") to 100mm (4") dia.

Detail Unit Rate (Metric System) per Meter

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
Rate Analysis for 7 Metre
Paint 0.3Ltr (0. 066) Gln P. Gln -
Brushes 0.18 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Rate for One Metre 0.00 -


7

Labour
Rate Analysis for 60 Metre
Painter 1.00 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Rate for One Metre -

Item Rates
Labour Rate Per Rm Rs. Say -
Composite Rate Per Rm Rs. Say -

Labour Rate Per Rft Rs. Say -


Composite Rate Per Rft Rs. Say -

Page 89
DESCRIPTION OF ITEM NO 38: Repainting main switches and branch distrib
boards of all sizes and types, with approve
(complete set).

Detail Unit Rate (British System) per Job

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Paint 0.2Ltr (0. 044) Gln P. Gln -


Brushes 0.16 No. Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Painter 0.03 No P. Day

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Item Rates
Labour Rate Per Each Rs. Say -

Composite Rate Per Each Rs. Say -

Page 90
DESCRIPTION OF ITEM NO 39: Extra labour for painting, varnishing, etc
(6 M) height and above, for every additiona
(3.05 M) height, or scaffolding.

Detail it Rate (British System) per 100 Sft per Co

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Sft

Labour

Unskilled Cooly 0.16 No P. Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per 100 Sft Per Coat Rs. Say -

Labour Rate Per Sqm Per Coat Rs. Say -

Page 91
CHAPTER NO. 16

PROTECTION & DIVERSION WORKS


DESCRIPTION OF ITEM

1 Cutting pilchi frash or sarkanda including carriage within one mile (1.6 Km.)

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Cft.


LABOUR

Coolies 1.90 Nos. 0.00 per day -


Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total for 125 Cft. -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum Rs. - Say -

DESCRIPTION OF ITEM

2 Weaving matresses

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Cft.

LABOUR

Coolies 3.60 Nos. 0.00 per day -


Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total for 125 Cft. -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum Rs. - Say -

Page 1 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

3 a) Supplying and filling jute bags 1.25 Cft. capacity with sand or earth sewing and
stacking in dry

Detail Unit of Rate Per Bag


Rate
Qty Per Unit (Rs.) Amount (Rs.)

(Rate Analysis for 10 Nos.)

MATERIAL

Empty Jute Bags 1.25 Cft. Capacity 10 Nos. 0.00 Each -


Sutli 1/8 Sr. (0.12 Kg.) 0.00 Per Kg. -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total for 10 Bags -

LABOUR

Cooly 0.45 No. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total for 10 Bags -

ITEM RATE

Labour Rate Per Bag 0.00 = 0.00 -


10

Composite Rate Per Bag - + 0.00 = 0.00 -


10

Page 2 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
b) Supplying and filling jute bags 1.25 Cft. Capacity with sand or earth sewing
and laying in position under water

Detail Unit of Rate Per Bag


Rate
Qty Per Unit (Rs.) Amount (Rs.)

(Rate Analysis for 10 Nos.)

MATERIAL

Empty Jute Bags 1.25 Cft. Capacity 10 Nos. 0.00 Each -


Sutli 1/8 Sr. (0.12 Kg.) 0.00 Per Kg. -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total for 10 Bags -

LABOUR

Cooly 0.70 No. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total for 10 Bags -

ITEM RATE

Labour Rate Per Bag 0.00 = 0.00 -


10

Composite Rate Per Bag - + 0.00 = 0.00 -


10

Page 3 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

4 a) Supplying and filling new jute bags 4 to 5 Cft. capacity, with sand or earth
Sewing and stacking in dry.

Detail Unit of Rate Per Bag


Rate
Qty Per Unit (Rs.) Amount (Rs.)

(Rate Analysis for 65 Bags)

MATERIAL

New jute bags 4 to 5 Cft capacity 50 Nos. 0.00 Each -


Cost of Sutli 1.50 Sr. (1.40 Kg.) 0.00 Per Kg. -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total for 65 Bags -

LABOUR

Coolies required for filling, sewing 7 Nos. 0.00 Per day -


and stacking in dry (50 Nos. bags)
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total for 65 Bags -

ITEM RATE

Labour Rate Per Bag 0.00 = 0.00 -


65

Composite Rate Per Bag - + 0.00 = 0.00 -


65

Page 4 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
b) Supply and filling new jute bags 4 to 5 Cft. capacity with sand or earth, sewing
and laying in position under water.

Detail Unit of Rate Per Bag


Rate
Qty Per Unit (Rs.) Amount (Rs.)

(Rate Analysis for 65 Bags)

MATERIAL

New jute bags 4 to 5 Cft capacity 50 Nos. 0.00 Each -


Cost of Sutli 1.50 Sr. (1.40 Kg.) 0.00 Per Kg. -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total for 65 Bags -

LABOUR

Coolies required for filling, sewing 10 Nos. 0.00 Per day -


and stacking in dry 50 Nos. bags.
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total for 65 Bags -

ITEM RATE

Labour Rate Per Bag 0.00 = 0.00 -


65

Composite Rate Per Bag - + 0.00 = 0.00 -


65

Page 5 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

5 Carriage of jute bags 1.25 Cft. capacity filled with sand or earth

Detail Unit of Rate 100 Bags


Rate
Qty Per Unit (Rs.) Amount (Rs.)

A) First Chain (30.0 Metre)

LABOUR FOR 125 BAGS

Cooly 0.50 No. 0.00 Per Day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

Labour of Rate for 100 Bags Rs. 0.00 Say -

B) Second to Fourth Chain


(Above 30.0 metre to 120 Metre)

LABOUR FOR 125 BAGS

Cooly 0.18 No. 0.00 Per Day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

Labour of Rate for 100 Bags Rs. 0.00 Say -

C) Fifth and Subsequent Chain


(120 metres and above)

LABOUR FOR 125 BAGS

Cooly 0.07 No. 0.00 Per Day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

Labour of Rate for 100 Bags Rs. 0.00 Say -

Page 6 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

6 Carriage of new jute bags 4 to 5 Cft. Capacity filled with sand or earth

Detail Unit of Rate 100 Bags


Rate
Qty Per Unit (Rs.) Amount (Rs.)

A) First Chain

LABOUR FOR 125 BAGS

Cooly 2.00 Nos. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

Labour of Rate for 100 Bags Rs. 0.00 Say -

B) Second to Fourth Chain


(30.0 metre to 120.0 metre)

LABOUR FOR 125 BAGS

Cooly 0.70 No. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

Labour of Rate for 100 Bags/Per Chain Rs. 0.00 Say -

C) Fifth and Subsequent Chain


(120 metres and above)

LABOUR FOR 125 BAGS

Cooly 0.27 No. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

Labour of Rate per 100 Bags/per chain Rs. 0.00 Say -

Page 7 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

7 Rolling matresses to river edge and floating after unrolling

Detail Unit of Rate 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

a) Area of matress upto 2000 Sft

LABOUR

Cooly 0.90 Nos. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

Labour Rate Per 100 Sft. Rs. 0.00 Say -


Labour Rate Per Sqm Rs. 0.00 Say -

b) Area of matresses from 2000


to 2500 Sft.

LABOUR

Cooly 1.50 Nos. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

Labour Rate Per 100 Sft. Rs. 0.00 Say -


Labour Rate Per Sqm Rs. 0.00 Say -

c) Area of matresses over 2500 Sft.

LABOUR

Coolies 1.75 Nos. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

Labour Rate Per 100 Sft. Rs. 0.00 Say -


Labour Rate Per Sqm Rs. 0.00 Say -

Page 8 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

8 Sewing empty cement bags in sheets

Detail Unit of Rate Per 100 Nos.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

1 Sutli, Strings 1 Sr. (0.933 Kg.) 0.00 Per Kg. -


Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Coolies 1.40 No. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Nos. Rs. - Say -


Composite Rate Per 100 Nos. Rs. - Say -

Page 9 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

9 Making compact round pilchi, frash or sarkanda round bundles of specified


size for the work

Detail Unit of Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Munjban
100 x 5 seer = 2.31 Seers (2.1 2.15 Kg. 0.00 Per Kg. -
216 Cft.
Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Coolies 1.95 Nos. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

Page 10 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

10 Launching and placing in position, compact round pilchi, frash or Sarkanda


bundles of specified size.

Detail Unit of Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Cft.

LABOUR

Coolies 1.20 Nos. 0.00 Per Day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -

DESCRIPTION OF ITEM

11 Supplying within 5 chains

a) Boulders 9" and above

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Cft.

LABOUR

Coolies 3.62 Nos. 0.00 Per Day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -

Page 11 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
b) Over size shingle 3" to 9"

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Cft.

LABOUR

Coolies 2.42 Nos. 0.00 Per Day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -

c) Mixed graded shingle

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Cft.

LABOUR

Coolies 2.87 Nos. 0.00 Per Day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -

Page 12 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

12 Supply munj or patha trungers 6" mesh to hold 3 Cft.

Detail Unit of Rate Per No


Rate
Qty Per Unit (Rs.) Amount (Rs.)

(Rate Analysis for Two Nos.)

MATERIAL

Munjban (rough) 2 seer (1.87 Kg.) 0.00 Per kg. -


Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Coolies 0.25 No. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Bag 0.00 = 0.00 -


2

Composite Rate Per Bag - + 0.00 = 0.00 -


2

Page 13 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

13 Providing and weaving G.I. wire netting for wire crates with G.I. wire of approved size
(including siding and partition to make crates).

a) 6" mesh (i) G.I. Wire 15 SWG

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

G.I. Wire No. 15 (500' long) 6.8 Lbs (3.08 Kg.) 1.00 Per Kg. 3.08
Contractor's Profit & Ov 20.00 Percent 0.62
Total 3.70

LABOUR

Black smith 0.70 No. 0.00 Per day -


Coolies 0.70 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say -


Labour Rate Per Sqm. Rs. - Say -
Composite Rate per 100 Sft. Rs. 3.70 Say 3.70
Composite Rate per Sqm. Rs. 0.40 Say 0.40

Page 14 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

13 Providing and weaving G.I. wire netting for wire crates with G.I. wire of approved size
(including siding and partition to make crates).

a) 6" mesh (ii) G.I. Wire 10 SWG

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

G.I. Wire No. 10 (500' long) 22.0 Lbs (10.0 Kg.) 0.00 Per Kg. -
Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Black smith 0.75 No. 0.00 Per day -


Coolies 0.75 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say -


Labour Rate Per Sqm. Rs. - Say -
Composite Rate per 100 Sft. Rs. - Say -
Composite Rate per Sqm. Rs. - Say -

Page 15 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
a) 6" mesh (iii) G.I. Wire 8 SWG

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

G.I. Wire No. 8 (500' long) 34.5 Lbs (15.68 Kg. 0.00 Per Kg. -
Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Black smith 0.75 No. 0.00 Per day -


Cooly 0.75 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say -


Labour Rate Per Sqm. Rs. - Say -
Composite Rate per 100 Sft. Rs. - Say -
Composite Rate per Sqm. Rs. - Say -

Page 16 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
13 b) 4" mesh (i) G.I. Wire 15 SWG

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

G.I. Wire No. 15 750' long 10.20 Lbs (4.63 Kg. 0.00 Per Kg. -
Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Black smith 0.90 No. 0.00 Per day -


Coolies 0.90 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say -


Labour Rate Per Sqm. Rs. - Say -
Composite Rate per 100 Sft. Rs. - Say -
Composite Rate per Sqm. Rs. - Say -

Page 17 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
13 b) 4" mesh (ii) G.I. Wire 10 SWG

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

G.I. Wire No. 10 750' long 33.0 Lbs (14.97 Kg. 0.00 Per Kg. -
Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Black smith 1.00 No. 0.00 Per day -


Coolies 1.00 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say -


Labour Rate Per Sqm. Rs. - Say -
Composite Rate per 100 Sft. Rs. - Say -
Composite Rate per Sqm. Rs. - Say -

Page 18 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
13 b) 4" mesh (iii) G.I. Wire 8 SWG

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

G.I. Wire No. 8 750' long 51.75 Lbs (23.47 Kg 0.00 Per Kg. -
Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Black smith 1.00 No. 0.00 Per day -


Coolies 1.00 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say -


Labour Rate Per Sqm. Rs. - Say -
Composite Rate per 100 Sft. Rs. - Say -
Composite Rate per Sqm. Rs. - Say -

Page 19 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
14 Providing and laying shingle on top of bund, including handling of material within
three chains (90 metres)

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Shingle 110.00 Cft. 0.00 r 100 Cf -


Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Cooly 1.00 No. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. 0.02 Say -

Page 20 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

15 Supply and Dumping at site, without boat, including handling of material within
three chains (90 metres).

a) Stone or boulder

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Boulder 110.00 Cft. 0.00er 100 C -


Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Cooly 1.75 No. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

b) Shingle or Spawl

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Shingle / Spawl 110.00 Cft. 0.00er 100 C -


Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Cooly 1.75 No. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE
Labour Rate Per 100 Cft. Rs. - Say -
Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

c) Brick Bats

Page 21 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit Rate Per 100 Cft.
Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Brick Bat 110.00 Cft. 0.00er 100 C -


Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Cooly 1.35 No. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

Page 22 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

16 Supply and damping by boat including loading into boats within 3 chains lead
and hire charges of boat and boatman

a) Stone, Boulder

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Stone or Boulder 110.00 Cft. 0.00er 100 C -


Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Boatman with large boat 1.00 No. 0.00 Per day -


Coolies 2.00 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

Page 23 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
b) Shingle, Spawl

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL
Spawl 110.00 Cft. 0.00er 100 C -
Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR
Boatman with large boat 1 No. 0.00 Per day -
Coolies 2 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE
Labour Rate Per 100 Cft. Rs. - Say -
Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

c) Brick Bats

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Brick Bat 110.00 Cft. 0.00er 100 C -


Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Boatman with Large Boat 1 No. 0.00 Per day -


Coolies 1.6 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE
Labour Rate Per 100 Cft. Rs. - Say -
Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

DESCRIPTION OF ITEM

17 Providing and filling bricks bats in crates (excluding cost of crates)

Page 24 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit Rate Per 100 Cft.
Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Brick Bat 110.00 Cft. 0.00er 100 C -


Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Skilled Cooly 1.00 No. 0.00 Per day -


Coolies 1.30 Nos. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

Page 25 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

18 Supplying and filling bricks in wire crates and hand packing (excluding cost of crates)

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Bricks 1500.00 Nos. 0.00r 1000 No -


Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Cooly (Skilled) 1.00 No. 0.00 Per day -


Coolies (Unskilled) 1.80 Nos. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate Per 100 Cft. Rs. - Say -
Composite Rate Per Cum. Rs. - Say -

Page 26 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

19 Supplying and filling in wire crates, including sewing crates (excluding cost of crates)

i) Stone or Boulders

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Stone or Boulders 110.00 Cft. 0.00er 100 C -


Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Cooly (Skilled) 1.00 No. 0.00 Per day -


Coolies (unskilled) 2.20 Nos. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate Per 100 Cft. Rs. - Say -
Composite Rate Per Cum. Rs. - Say -

Page 27 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
ii Shingle or Spawl

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Shingle or Sprawl 110.00 Cft. 0.00er 100 C -


Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Cooly (Skilled) 1.00 No. 0.00 Per day -


Coolies 2.20 Nos. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

Page 28 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

20 Extra for anchoring boat for dumping by boats or tipping crates.

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Cft.

LABOUR

Boatman 0.44 No. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -

DESCRIPTION OF ITEM

21 Extra for tipping crates (in addition to anchoring boats)

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Cft.

LABOUR

Coolies 2.00 Nos. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Extra L.s. for ballies -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -

Page 29 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

22 Pilchi revetment, including carriage upto one mile (1.6 Km)

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Supply pilchi lead within one mile ###### Sft. 0.00er 100 S -
(As per item No. 1 of this chapter)
Total -

LABOUR

Cooly 1.00 No. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say -


Labour Rate Per Sqm. Rs. - Say -
Composite Rate per 100 Sft. Rs. - Say -
Composite Rate per Sqm. Rs. - Say -

DESCRIPTION OF ITEM

23 Surface protection with pilchi matresses carriage upto one mile (1.76 Km)

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Supply pilchi lead within one mile 20.00 Cft. 0.00er 100 C -

LABOUR
Coolies 2.50 No. 0.00 Per day -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
Labour Rate Per 100 Sft. Rs. - Say -
Labour Rate Per Sqm. Rs. - Say -
Composite Rate per 100 Sft. Rs. - Say -
Composite Rate per Sqm. Rs. - Say -

Page 30 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

24 Pilchi, sarkanda or frash pitching on slopes, including supply of pilchi,


sarkanda or frash within one mile, also supply and driving of pegs 1' long
sharpened at one end and typing with wire or Munj ban (excluding cost of
placing earth between rolls.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Cutting pilchi and carriage to river ba


lead upto one mile

i. Pilchi rolls 6" dia 10 long


10x10x 22 x x x = 20 Cft.
7
Pilchi rolls 6" dia 5' long
Cross wise
10x20x5x 22 x (0.5)2 x = 196 Cft
7
Total = 20 + 196 = 216 Cft. ###### Cft. 0.00 r 100 Cf -

ii. Kiker wood for pegs 18" long 2" dia=25 N


25 x 1/6 x 1/6 x x 22/7 x 1 = 0.85 Cft.
7

Wastage 2% = 0.17 Cft.


= 1.02 Cft. 1.02 Cft. 0.00 Per Cft. -

Binding wire 1 Lbs (0.454 Kg.) 0.45 Kg. 0.00 Per Kg. -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR FOR 125 SFT.

i. Making pilchi rolls 6" dia . ###### Cft. 0.00 r 100 Cf -

ii. For laying pitchi rolls in position and


dressing page

Coolies (Unskilled) 2.00 Nos. 0.00 Per day -


Coolies (Skilled) 0.50 No. 0.00 Per day -

iii. Sharpening wooden pegs 2" dia and 25.00 Nos. 0.00er 100 No -
18" long
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

Labour Per 100 Sft. 551.06

ITEM RATE

Labour Rate Per 100 Sft. Rs. ###### Say 551.05


Labour Rate Per Sqm. Rs. 59.29 Say 59.30
Composite Rate per 100 Sft. Rs. ###### Say 551.05
Composite Rate per Sqm. Rs. 59.29 Say 59.30

Page 31 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

25 Construction groynes upto 5 feet with single row of woodem vertical stacks 7"
to 12" dia. One average lead one mile

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

LABOUR

Vertical stakes 7" - 12" dia 1 foot a p 21.00 Nos.


Supports 4.00 Nos.
Total 25.00 No.
Wastage 10% 2.50 Nos.
Total 27.50 Nos.
Say 28.00 Nos. 0.00 r 100 No -
Ordinary coir (Ban) 0.35 Sr. (0.33 Kg.) 0.00 Per Kg. -
Royalty charges for 28 Nos. Stakes 28.00 Nos. 0.00 Each -
Total -
Contractor's Profit & Ov 20.00 Percent -
-

LABOUR

Skilled Cooly 0.85 No. 0.00 Per day -


Cooly 1.00 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say -


Labour Rate Per Sqm. Rs. - Say -
Composite Rate per 100 Sft. Rs. - Say -
Composite Rate per Sqm. Rs. - Say -

Page 32 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

26 Constructing groynes upto 10 ft height with double roww of wooden vertical


stackes 7" to 12" dia, 2' apart, average lead one mile.

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

LABOUR

Lai stickes 7" - 12" thick


vertical stakes 9" - 12" thick 22.00 Nos
2' apart or two rows cross wise 3.00 Nos.
Supports 4.00 Nos.
Total 29.00 Nos.
Wastage 10% 2.90 Nos.
Total 31.90 Nos.
Say 32.00 Nos. 0.00 r 100 No -
Ordinary coir (Ban) Seer (0.47 Kg.) 0.00 Per Kg. -
Royalty charges for 32 Nos. Stakes 32.00 Nos. 0.00 Each -
Total -
Contractor's Profit & Ov 20.00 Percent -
-

LABOUR

Skilled Cooly 1.20 No. 0.00 Per day -


Cooly 2.00 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say -


Labour Rate Per Sqm. Rs. - Say -
Composite Rate per 100 Sft. Rs. - Say -
Composite Rate per Sqm. Rs. - Say -

Page 33 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

27 Providing and laying stone pitching/filling, dry hand packed, as filling behind
retaining walls or in pitching and aprons

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Stone ###### Cft. 0.00r 100 C -


Contractor's Profit & Ov 20.00 Percent -
-

LABOUR

Skilled Cooly 1.00 No. 0.00 Per day -


Cooly 1.00 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

Page 34 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

28 Providing and laying stone pitching with hammer dressed stones on surface
laid in courses

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Pitching Stone ###### Cft. 0.00r 100 C -


Contractor's Profit & Ov 20.00 Percent -
-

LABOUR

Mason 2.25 No. 0.00 Per day -


Coolies 3.00 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

Note : Carriage of stone will be paid for separately.

DESCRIPTION OF ITEM

Page 35 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
29 Providing and laying stone pitching for top layer only

a) On slope

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Pitching Stone ###### Cft. 0.00r 100 C -


Contractor's Profit & Ov 20.00 Percent -
-

LABOUR

Mason 1.50 Nos 0.00 Per day -


Coolies 3.00 Nos 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

Note : Carriage of stone will be paid separately.

Page 36 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
29 b) On level

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Pitching Stone ###### Cft. 0.00r 100 C -


Contractor's Profit & Ov 20.00 Percent -
-

LABOUR

Mason 1.50 Nos 0.00 Per day -


Coolies 2.50 Nos 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

Note : Carriage of stone will be paid separately.

Page 37 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

30 Providing and laying stone or spawl filling

a) On level

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Spawl ###### Cft. 0.00r 100 C -


Contractor's Profit & Ov 20.00 Percent -
-

LABOUR

Mason 0.25 No. 0.00 Per day -


Coolies 1.00 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

Page 38 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
b) On Slope

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Spawl ###### Cft. 0.00r 100 C -


Contractor's Profit & Ov 20.00 Percent -
-

LABOUR

Mason 0.48 No. 0.00 Per day -


Cooly 1.00 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

Page 39 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

31 Providing and laying stone pitching hand packed, with surface leveled off to the correct
section and voide filled in 1:8 cement, sand mortar, in floors of bridges along banks
and in aprons, etc.

i) Top layer on slope

Detail Unit Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Pitching Stone ###### Cft. 0.00r 100 C -


Cement 2.70 Bags 0.00 Per Bag -
Sand 26.40 Cft. 0.00r 100 C -
Total -
Contractor's Profit & Ov 20.00 Percent -
-

LABOUR

Mason 2.50 Nos. 0.00 Per day -


Coolies 2.78 Nos. 0.00 Per day -
Bahishti 0.50 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

Note Carriage of stone will be paid for separately

Page 40 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
ii) Top layer on level

Detail Unit of Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Pitching Stone ###### Cft. 0.00r 100 C -


Cement 2.70 Bags 0.00 Per Bag -
Sand 26.40 Cft. 0.00r 100 C -
Total -
Contractor's Profit & Ov 20.00 Percent -
-

LABOUR

Mason 2.50 Nos. 0.00 Per day -


Coolies 2.28 Nos. 0.00 Per day -
Bahishti 0.50 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

Note Carriage of stone will be paid for separately

Page 41 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
iii) Stone pitching/filling on slope or on level (other than top layer)

Detail Unit of Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Pitching Stone ###### Cft. 0.00r 100 C -


Cement 2.70 Pegs 0.00 Per Peg -
Sand 26.40 Cft. 0.00r 100 C -
Total -
Contractor's Profit & Ov 20.00 Percent -
-

LABOUR

Mason 1.25 Nos. 0.00 Per day -


Coolies 1.50 Nos. 0.00 Per day -
Bahishti 0.37 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -

Note Carriage of stone will be paid for separately

Page 42 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

32 Grouting stone pitching or apron, etc. in

a) Cement sand mortar (1:3)

Detail Unit of Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Cement 6.00 Pegs 0.00 Per Peg -


Sand 22.30 Cft. 0.00r 100 C -
Total -
Contractor's Profit & Ov 20.00 Percent -
-

LABOUR

Mason 0.50 No. 0.00 Per day -


Coolies 1.34 Nos. 0.00 Per day -
Bahishti 0.25 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say -


Labour Rate Per Sqm Rs. - Say -
Composite Rate per 100 Sft. Rs. - Say -
Composite Rate per Sqm. Rs. - Say -

Page 43 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Pitching or grouting stone apron etc. in :-

b) Cement sand mortar (1:8)

Detail Unit of Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Cement 2.70 Pegs 0.00 Per Peg -


Sand 26.40 Cft. 0.00r 100 C -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Say 636.00

LABOUR

Mason 0.50 No. 0.00 Per day -


Coolies 1.00 Nos. 0.00 Per day -
Bahishti 0.25 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say -


Labour Rate Per Sqm Rs. - Say -
Composite Rate per 100 Sft. Rs. ###### Say 636.00
Composite Rate per Sqm. Rs. 68.43 Say 68.45

Page 44 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

33 Sand grouting in stone apron, with high pressure hose

Detail Unit of Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Sand 50.00 Cft. 0.00r 100 C -


Contractor's Profit & Ov 20.00 Percent -
Total -
Say 193.00

LABOUR

Mason 0.20 No. 0.00 Per day -


Coolies 0.50 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Say 86.52

ITEM RATE

Labour Rate Per 100 Sft. Rs. 86.52 Say 86.50


Labour Rate Per Sqm Rs. 9.31 Say 9.30
Composite Rate per 100 Sft. Rs. ###### Say 279.50
Composite Rate per Sqm. Rs. 30.08 Say 30.10

Page 45 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

34 Grouting stone filling or pitching with bajri

Detail Unit of Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Pegri 30.00 Cft. 0.00r 100 C -


Contractor's Profit & Ov 20.00 Percent -
-

LABOUR

Coolies 1.25 Nos. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum Rs. - Say -

Page 46 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

35 Removing stone and repitching hand packed on slopes or level after making good
damaged slope/portion.

Detail Unit of Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Cft.


LABOUR

Cooly For Dismantling 0.85 No. 0.00 Per day -


Masons for repitching 1.50 Nos. 0.00 Per day -
Coolies 3.00 Nos. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum Rs. - Say -

Page 47 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

36 Collecting and stacking boulders from nullah beds or loose shale, or from any other
site, within 3 chains lead

Detail Unit of Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Cft.

LABOUR

Coolies 2.00 Nos. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE
Labour Rate Per 100 Cft. Rs. - Say -
Labour Rate Per Cum Rs. - Say -

DESCRIPTION OF ITEM

37 Levelling and dressing stone filling under blocks and grouting with shingle

Detail Unit of Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Shingle 30.00 Cft. 0.00r 100 C -


Contractor's Profit & Ov 20.00 Percent -
-
LABOUR

Masons 0.25 No. 0.00 Per day -


Coolies 1.00 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Say

ITEM RATE
Labour Rate Per 100 Cft. Rs. - Say -
Labour Rate Per Cum Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum Rs. - Say -

DESCRIPTION OF ITEM

38 Grouting jharies between blocks with bajri

Page 48 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit of Rate Per 100 Cft.
Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Bajri 20.00 Cft. 0.00r 100 C -


Contractor's Profit & Ov 20.00 Percent -
-

LABOUR

Masons 0.25 No. 0.00 Per day -


Coolies 1.00 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Say

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum Rs. - Say -

DESCRIPTION OF ITEM
39 Breaking stone into spawls and stacking

Detail Unit of Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Cft.

LABOUR

Coolies 1.50 No. 0.00 Per day -


Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE
Labour Rate Per 100 Cft. Rs. - Say -
Labour Rate Per Cum Rs. - Say -

DESCRIPTION OF ITEM

40 Fixing floating spurs with materials from canal plantation within one mile lead

a) Upto 2 foot F.s. depth

Detail Unit of Rate Per No.


Rate

Page 49 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 225 Nos.


LABOUR

Carpenter 1.00 No. 0.00 Per day -


Mate 1.00 No. 0.00 Per day -
Coolies 7.00 Nos. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per No. Rs. - 0.00 Say -


225

b) 2.0' to 3.0' F.s. Depth

Detail Unit of Rate Per No.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 200 Nos.

LABOUR

Carpenter 1.00 No. 0.00 Per day -


Mate 1.00 No. 0.00 Per day -
Coolies 7.00 Nos. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per No. Rs. - 0.00 Say -


200

Page 50 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
c 3.0' to 4.0' F.s. depth

Detail Unit of Rate Per No.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 150 Nos.

LABOUR

Carpenter 1.00 No. 0.00 Per day -


Mate 1.00 No. 0.00 Per day -
Coolies 7.00 Nos. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per No. Rs. - 0.00 Say -


######

d) Above 4'-0" F.S. Depth

Detail Unit of Rate Per No.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 60 Nos.

LABOUR

Carpenter 1.00 No. 0.00 Per day -


Mate 1.00 No. 0.00 Per day -
Coolies 7.00 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per No. Rs. - 0.00 Say -


60.00

Page 51 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM

41 Staking and bushing from canal plantation within one mile. (Royalty to be paid to
Forest Department or private owner if and when required.

a (i) Cutting and supply un-sharpened pegs 3.5 long, 3" to 6" dia from canal plantation
sites lead within one mile (1.6 Km.)

Detail Unit of Rate Per 100 No. Pegs


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Kikar wood required for 100 No. Pegs


100 x 3.5 x 9/24x9/24 x 1/4x22/7 =38.70 Cft

Add 20% Wastage 7.74 / 46.44


Say 46.50 Cft.

Weight of 46.50 Cft. of green wood at


62 Lbs/ per Cft.
46.50 x 62/82.5 = 35 Mds (1306 Kgs.)
Royalty of Wood @ 70.00 per 100 mds 35.00 Mds. 0.00r 100 Md 24.70
Total 24.70

LABOUR

Coolies for Cutting of wood for Pegs 2 Nos. 0.00 Per No. -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate for 100 Pegs Rs. - Say -


Composite Rate for 100 Pegs. Rs. 24.70 Say 24.70

Page 52 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (a) Sharpening one end of pegs 3.5 long
3" to 6 " dia.

Detail Unit of Rate Per 100 No. Pegs


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Pegs

LABOUR

Carpenter 0.50 No. 0.00 Per day -


Cooly 0.50 No. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate for 100 Pegs Rs. - Say -

41 (a) Driving pegs 3.5 long 3" to 6" (Driven


1.0' below the available bed or ground)

Detail Unit of Rate Per 100 No. Pegs


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Pegs

LABOUR

Cooly Skilled 1.40 Nos. 0.00 Per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate for 100 Pegs Rs. - Say -

Page 53 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (a) Tying pegs with Munj/Patha ban one line including tying around the pegs.

Detail Unit of Rate Per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Requirement of ban for one chain


length of row of killas including a tie
around the pegs.

100 + (50x1 x 9/24 x 22 158.96 Lft.


Add 10% wastage 15.89 Lft.
Total 174.85 Lft.
Say 175.00 Lft.

Length of 1 Seer (0.933 Kg.) of Ban 250'


Hence Weight of 175 Lft 175 = 0.70 Seer
250
a) Supplying Ban Munj /
0.70 Seer (0.65 Kg.) 0.65 Kg. 0.00 Per Kg. -

Contractor's Profit & Ov 20.00 Percent -


Total -

LABOUR

Cooly 0.10 No. 0.00 Per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

Page 54 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (a) Cutting and supplying brushwood from canal plantation on private source (Lead within one mile)
and wattling between stakes and intertwining. (Thickness of wattled brush wood 1.0 average)

Detail Unit Rate Per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL i. Brush wood measured in thoroughly compacted & pa


shapes before filling in the
Requirement of brush wood
Length 100 Ft. ii. The composite rates include the cost of labour
Thickness 1 Ft. royalty and cost of cutting and supplying brus
Height 2.5 Ft. one mile vide item No. 58-A of C.S.R. (Royalty
Contents 100x1.0'x2.5' 250 Cft. the forest Deptt. or private owner if and whe
250 Cft. or 188 Mds.
Royalty charges @ 20.00 % Cft. 188 Mds. Per 100 Mds

LABOUR

Cutting brushwood ###### Mds. Per 100 Md -


Cooly skilled for wattling 1.00 No. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Say -

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

Page 55 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (b) Cutting and supplying un-sharpened pegs 4'.0 long (4 feet) 3"-6" dia from canal plantation l

Detail Unit of Rate Per 100 No. Pegs


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Wood required for 100 No. pegs =


= 100 x 4 x 9/24 x 9/24 x x 22/7 = 44.20 Cft.
20% Wastage 8.84/53.04 = 8.84 Cft.
53.04

Weight of 53 Cft. green wood


@ 62 Lbs per Cft.
= 53 x 62/82.50 = 39.83 Mds.
Royalty of Wood @ 70.00 Per % Mds. 39.83 Mds. 0.00 er % Mds -

LABOUR

Cutting of wood 39.83 Mds. 0.00 er % Mds -


Total Material and Labour

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

41 (b) Sharpening one end of pegs 4'.0 long 3" to 6" dia.

Detail Unit Rate Per 100 No. Pegs


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.

LABOUR

Carpenter 0.50 No. 0.00 Per day -


Cooly (Unskilled) 0.50 No. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Rate Per 100 No. Pegs - -
1.25

ITEM RATE

Labour Rate for 100 No. Pegs Rs. - Say -

41 (b) Driving pegs 4'-0" long 3" to 6" dia (driven 1.25' below the available bed or ground (average)

Page 56 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit of Rate Per 100 No. Pegs
Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.

LABOUR

Cooly Skilled 1.00 No. 0.00 Per day -


Cooly Unskilled 0.73 No. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Rate Per 100 No. Pegs 158.63 -
1.25

ITEM RATE

Labour Rate for 100 No. Pegs Rs. - Say -

41 (b) Tying pegs with Munj / Patha ban (one line including tying around the pegs).

Detail Unit of Rate Per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Same as per item No. 41(a) (iv) -

LABOUR

Same as per item No. 41(a)(iv) -

Total -

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

Page 57 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (b) Cutting and supplying brushwood from canal plantation or private source (lead within one mile)
wattling between stakes and intertwining. (Thickness of wattled brush wood 1.0' (average)

Detail Unit Rate Per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Requirement of brushwood Brushwood measured in thoroughly compacted and packe


shape before filling in the desi
Length 100'

Thickness 1'-0"

Height 2.75'

Content 100x1.0x2.75 = 275 Cft.


Royalty of brush wood 275 Cft. ###### Cft. 20.00 r 100 Cf 55.00

LABOUR

Cooly Unskilled
for cutting brushwood 2.50 Nos. 0.00 Per day -
Cooly skilled for wattling 1.00 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. 55.00 Say 55.00

Page 58 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (c) Cutting and supplying unsharpened pegs 5'-0" long 3" to 6" dia from canal plantation
(lead within one mile)

Detail Unit of Rate Per 100 No. Pegs


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Wood required for 100 No. pegs Brushwood measured in thoroughly compacted and packe
100 x 5'.0 x 9/24 x 9/24 x x 22/7 shape before filling in the desi
55.25 Cft.
Add wastage 20% 11.05
66.30 Cft.

Weight of 66.30 cft green wood


@ 62 Lbs per Cft. (66.30x62) / 82.5 = 49.82 Mds.
Royalty of wood per 100 Mds @ 70.00 % Md 49.82 Mds. 0.00Per % Md -

LABOUR

Cutting wood for pegs


Total Material and Labour 49.82 Mds. 0.02 er % Mds 0.01

ITEM RATE

Labour Rate Per 100 No. Pegs Rs. 0.01 Say -


Composite Rate Per 100 No. Pegs Rs. 0.01 Say -

41 (c) Sharpening one end of pegs 5'-0" long 3" to 6" dia.

Detail Unit Rate Per 100 No. Pegs


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.

LABOUR

Carpenter 0.55 No. 0.00 Per day -


Cooly Unskilled 0.50 No. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE
Labour Rate Per 100 No. Pegs Rs. - Say -

41 c - Driving pegs 5'-0" long 3" to 6" dia (driven 1.5' below the available bed on ground (average).

Page 59 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit Rate Per 100 No. Pegs
Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.

LABOUR

Cooly skilled 1.00 No. 0.00 Per day -


Cooly unskilled 1.00 No. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 No. Pegs Rs. - Say -

41 (c) Tying Peg with Munj / Patha ban one line including tying around the pegs.

Detail Unit Rate Per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Same as per Item 41 (a) (iv) -

LABOUR

Same as per item 41 (a) (iv) -


Total

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

Page 60 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (c) Cutting and supply brushwood from canal plantation or private source (lead within one mile) an
between stakes and intertwining thickness of wattled brush wood 1.0')

Detail Unit Rate Per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Requirement of brush wood


Length 100 Ft.
Thickness 1.0'
Height 3.5'

CONTENTS

100 X 1.0 X 3.5 = 350 Cft.


Weight of brush wood 350x62 263 Mds ###### Mds. 0.00 r 100 Cf -
82.5

MATERIAL

Cooly skilled for wattling brush wood 1.50 No. 0.00 Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

Page 61 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (d) Cutting and supplying unsharpened pegs 6'-0" long 3" to 6" dia from canal plantation (lead wit

Detail Unit Rate Per 100 No. Pegs


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Wood required for 100 No. pegs


100 x 6 x 9/24 x 9/24 x x 22/7 = 66.30 Cft.
Add wastage 20% 13.26 Cft.
Say 79.6 Cft.

Weight of 79.60 Cft green wood


@ 62 Lbs / per cft.
79.6 x 62/82.50 59.80 Mds.

Royalty of wood 59.80 Mds. 0.00 r 100 Md -

LABOUR

Coolies for cutting wood for pegs. 4.00 Nos. 0.00 Per No. -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

41 (d) Sharpening one end of pegs 6'-0" long

Detail Unit Rate Per 100 No. Pegs


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.


MATERIAL
Carpenter 0.65 No. 0.00 Per day -
Cooly 0.60 No. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
Labour Rate Per 100 No. Pegs Rs. 0.01 Say -

Page 62 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (d) Driving pegs 6'-0" long 3'-6" driven 1.75' below the available bed of ground (average)

Detail Unit Rate Per 100 No. Pegs


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.

LABOUR

Cooly Skilled 1.20 Nos. 0.00 Per day -


Cooly Unskilled 1.20 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 No. Pegs Rs. - Say -

41 (d) Tying pegs with Munj / Patha ban (one line including tying around the pegs)

Detail Unit Rate Per Chain of Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Same as per item No. 41 (a)(iv) -

LABOUR

Same as per Item No. 41 (a)(iv) -

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

Page 63 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (d) Cutting and supplying brush wood from canal plantation or private source (lead within one mile
wattling between stakes and intertwining, thickness of wattled brush wood 1'.0 average

Detail Unit Rate Per Chain


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Requirement of brush wood


Length 100 Ft.
Thickness 1 Ft.
Height 4.25 Ft.
Contents 100 x 1.0 x 4.25 = 425 Cft.
Weight of brush wood = 425 x 62 = 319.40 ###### Mds. 0.00 r 100 Md -
82.5
LABOUR

For cutting brush wood 3.00 Nos. 0.00 Per No. -


Coolies skilled for wattling 1.00 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Total Labour Per Chain Rs. - Say -


Composite Rate Per Chain Rs. - Say -

Page 64 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (e) Cutting and supplying un-sharpened pegs 6'-1" to 8'-0" long 4" to 8" dia from canal plantation
within one mile.

Detail Unit Rate Per 100 No. Pegs


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Wood required for 100 No. pegs


100 x 7'.0 x x x x 22 = 137.
7
Add wastage 20% 27.50 Cft.
Total 165.00 Cft.

Weight of 165 Cft. green wood


@ 62 Lbs per Cft.
165 x 62/82.5 = 124.00 Mds
Royalty of wood ###### Mds. 0.00er 100 Md -

LABOUR

Coolies for Cutting Wood 3.00 Nos. 0.00 Per No. -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Total Labour Per 100 No. Pegs Rs. - Say -


Composite Rate Per 100 No. Pegs Rs. - Say -

41 (e) Sharpening one end of pegs 6'-1" to 8'-0" long, 4" to 8" dia.

Detail Unit Rate Per 100 No. Pegs


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.

LABOUR

Carpenter 0.80 No. 0.00 Per day -


Cooly Unskilled 0.80 No. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATES
Labour Rate Per 100 No. Pegs Rs. - Say -

Page 65 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (e) Driving pegs 6'-1" to 8'-0' long 4" to 8" dia driven 2'-0" below the available bed or ground (

Detail Unit Rate Per 100 No. Pegs


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.

LABOUR
Cooly skilled 1.30 Nos. 0.00 Per day -
Cooly unskilled 1.35 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 No. Pegs Rs. - Say -

Page 66 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (e) Tying pegs 4" to 8" dia with Munj / Patha ban (one line including tying around the pegs).

Detail Unit Rate Per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Requirements of Munj / Patha ban for one


Chain length including winding of Peg
100 + (50 x x 22 / 7) = 178.57 Lft.

Add. wastage @ 10% = 17.86


196.43
Total length = 196
Say = 200 Lft.

hence weight of 200'

Length of Munj / Patha ban


@ 250 per sor. 200 / 250 = 080 Sr.

Munj / Patha ban 0.80 Sr. (0.36 Kg.) 0.00 Per Kg. -
Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Same as per Item 41 (a) (iv) -

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

Page 67 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (e) Cutting and supplying brush wood (from canal plantation or private source lead within one mile
wattling between stacks and intertwining (thickness or wattled brush wood 1.0 average).

Detail Unit Rate Per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Requirement of brush wood


Length 100.00 Ft.
Thickness 1.00 Ft.
Height 5.00 Ft.
Contents 100 x 1'.0" x 5'.0" = 500 Cft.
Weight of 500 Cft. Brush Wood
500 x 62 = 375.75 Mds]
Royalty of brush wood 500 Cft. ###### Mds. 0.00er 100 Md -
Total -
Say

LABOUR

Coolies Unskilled
for cutting brush wood 3.00 Nos. 0.00 Per day -
Cooly skilled for wattling 1.50 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Say
ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

Page 68 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
42 Staking with bamboos from market and brushing from canal plantation or private source
(Royalty of brush wood for brushing or cost to private owners if and when required).

a - i) Supplying bamboos 8'-1" to 10' long, 2" to 5" dia

Detail Unit of Rate Per 100 No. Bamboos


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Bamboos ###### Nos. 0.00 Each -


Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Cost of 100 No. Bamboos Rs. - Say -

(a) i Sharpening one end of bamboos 8'-1" to 10' long 2" to 5" dia

Detail Unit of Rate Per 100 No. Bamboos


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.

LABOUR

Carpenter 0.70 No. 0.00 Each -


Cooly 0.70 No. 0.00 Each -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 No. Bamboos Rs. - Say -

Page 69 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
(a) ii Driving bamboos 8'-1" to 10'-0" long 2" to 5" dia. Driven2.5' below the available 'bed or gro

Detail Unit of Rate Per 100 No. Bamboos


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.


LABOUR
Cooly skilled 1.45 Nos. 0.00 Per day -
Cooly unskilled 1.45 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE
Labour Rate Per 100 No. Bamboos Rs. - Say -

2 (a) ivTying bamboos 2" to 5" dia with munj/Patha ban two lines including tying around the bamboos.

Detail Unit of Rate per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Requirement of Munj/Patha ban for


one chain length
200 + 50 (15/48 x 22 / 7) = 249 Lft.
Add wastage 10% = 25 Lft.
Total = 274 Lft.
Say = 275 Lft.

Length of one Sr. Munj/Patha ban=250 Lft.


hence weight of 275 Lft.
Munj/Patha ban 275/250 Lft=1.10 Sr.
Munj/Patha ban 1.10 Sr. 2.26 Lbs (1.02 Kg.) 0.00 Per Kg. -
Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR
Cooly unskilled 0.15 No. 0.00 Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

42 (a) v Cutting and supply brushwood from canal plantation or private source lead within one mile and
between stakes and intertwining (thickness of wattled brushwood 1'.0 average)

Page 70 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit of Rate per Chain of One Row
Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Requirement of brush wood


Length 100.00 Ft.
Thickness 1.00 Ft.
Height 6.50 Ft.
Contents 100 x 1.0' x 6.5 = 650 Cft.
Weight of brush wood = 650 x 62= 488 Mds ###### Mds. 0.00 r 100 Md -
82.5
Total -

LABOUR

Unskilled Coolies
for cutting brushwood 3.50 Nos. 0.00 Per day -
Cooly skilled for wattling 2.00 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

42 (b) i Supplying bamboos 10'-1" to 12'-0" long 2" to 5" dia

Detail Unit of Rate 100 No. Bamboos


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL
Bamboos ###### Nos. 0.00 Each -
Contractor's Profit & Ov 20.00 Percent -

Total -

ITEM RATE
Material Rate Per 100 No. Bamboos Rs. - Say -

2 (b) iiSharpening one end of bamboo 10'-1" to 12'-0" long 2" to 5" dia

Detail Unit of Rate 100 No. Bamboos


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Page 71 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Analysis for 125 Nos.

LABOUR

Carpenter 0.80 No. 0.00 Per day -


Cooly Unskilled 0.80 No. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Total Labour Rate Per 100 No. Bamboos Rs. - Say -

(b) ii Driving bamboos 10'-1" to 12'-0" long 2" to 5" (driven 2.75' below the available bed or groun

Detail Unit of Rate 100 No. Bamboos


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.

LABOUR

Coolies Skilled 1.55 Nos. 0.00 Per day -


Cooly Unskilled 1.60 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Total Labour Rate Per 100 No. Bamboos Rs. - Say -

Page 72 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
2 (b) ivTying bamboos 2" to 5" dia with BSWG No. 10 (two lines including tying around the bamboos and
tie around the topend only)

Detail Unit RatePer Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Requirement of B.S.W.G 10 for one chain


length (two lines 2(100 + 50 x 15/48x22/7)=298 Lft
top and only 50 x 15/48x22/7 = 50 Lft.
Total 348 Lft.
Add 5% wastage = 18 Lft. = 366 Lft.
Weight of 100 yard of
B.S.S.W.G. No. 10(13.12) Lbs.
Weight of 366 Left = 366/300x13.12
= 16 Lbs or 0.143 Cwt.
B.S.W.G. No. 10 16.00 Lbs. (7.27 Kg 0.00 Per Kg. -
Contractor's Profit & Ov 20.00 Percent -
Total -

LABOUR

Cooly Unskilled 0.50 No. 0.00 Per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

Page 73 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
42 (b) v Wattling brushwood between stakes and intertwining (thickness of wattled brush wood 1'.0 avera

Detail Unit of Rate per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Requirement of brush wood lenth=100 Ft.


Thickness = 1'-0"
Height = 8.25 Ft.
Contents 100 x 1 x 8.25 = 825 Cft.
Weight of brush wood = 825 x 62= 620 Mds
82.5
Royality of brush wood ###### Mds. 0.00 r 100 Md -
Total -

LABOUR

Cooly Unskilled
for cutting brush wood 4.50 Nos. 0.00 Per day -
Cooly skilled for wattling 2.25 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

42 (c) i Supplying bamboos 12'-1" to 14' long 2" to 5" dia

Detail Unit of Rate 100 No. Bamboos


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Bamboos ###### Nos. 0.00 Each -


Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Material Rate Per 100 No. Bamboos Rs. - Say -

2 (c) iiSharpening one end of bamboo 12'-1" to 14' long 2" to 5" dia.

Page 74 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit of Rate 100 No. Bamboos
Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.

LABOUR

Carpenter 0.90 No. 0.00 Each -


Cooly Unskilled 0.90 No. 0.00 Each -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 No. Bamboos Rs. - Say -

(c) ii Driving bamboos 12'-1" to 14' long 2" to 5" dia . Driven 3.5' below the available bed or grou

Detail Unit of Rate 100 No. Bamboos


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.

LABOUR

Coolies Skilled 1.80 Nos. 0.00 Each -


Coolies Unskilled 1.80 Nos. 0.00 Each -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 No. Bamboos Rs. - Say -

Page 75 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
2 (c) ivTying bamboos 2" to 5" dia with B.S.W.G. No. 10 Two lines including tying around the bamboo a
third tying around the topend only.

Detail Unit of Rate per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Same as per Item No. 42 (b) (iv) -

LABOUR

Same as per Item No. 42 (b) (iv) -

Total -

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

42 (c) v Cutting and supplying brushwood from canal plantation / private source lead within one mile an
between stakes and intertwining thickness of wattled brush wood 1'-0" average.

Detail Unit of Rate per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL
Requirement of brush wood length=100 Ft.
Thickness = 1'-0"
Height = 9.50 Ft.
Contents 100 x 1 x 9.50 = 950 Cft.
Weight of brush wood = 950x62 =714 Mds
82.5
Royality of brush wood 714 Mds. 0.00r 100 Md -
Total -

LABOUR
Coolies unskilled
for cutting brush wood 5.50 Nos. 0.00 Per day -
Cooly skilled for wattling 2.50 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE
Labour Rate Per Chain of One Row Rs. - Say -
Composite Rate Per Chain of One Row Rs. - Say -

42 (d) i Supplying bamboos 14'-1" to 16'-0" long 2" to 5" dia

Page 76 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit of Rate 100 No. Bamboos
Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Bamboos 100 Nos. 0.00 Each -


Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Material Rate Per 100 No. Bamboos Rs. - Say -

2 (d) iiSharpening one end of bamboo 14'-1" to 16'-0" long 2" to 5" dia.

Detail Unit of Rate 100 No. Bamboos


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.

LABOUR

Carpenter 1.00 No. 0.00 Each -


Cooly Unskilled 1.00 No. 0.00 Each -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Rate per 100 Nos. - -
1.25
ITEM RATE

Labour Rate Per 100 No. Bamboos Rs. - Say -

Page 77 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
(d) ii Driving bamboos 14'-1" to 16'-0" long 2" to 5" dia. Driven 4'-0"' below the available bed or

Detail Unit of Rate 100 No. Bamboos


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Nos.

LABOUR

Cooly Skilled 2.00 Nos. 0.00 Each -


Cooly Unskilled 2.00 Nos. 0.00 Each -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Rate per 100 Nos. - x 100 = -
125

ITEM RATE

Labour Rate Per 100 Nos. Rs. - Say -

(d) ivTying bamboos 2" to 5" dia with B.S.W.G. No. 10 Two lines including tying around the bamboo a
third tying around the top only.

Detail Unit of Rate per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Same as per Item No. 42 (b) (iv) -

LABOUR
Same as per Item No. 42 (b) (iv) -

Total -

ITEM RATE

Labour Rate Per 100 Nos. Rs. - Say -


Comparative Rate Per 100 Nos. Rs. - Say -

Page 78 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
42 (d) v Cutting and supplying brush wood from canal plantation / private source lead within one mile a
between stakes and intertwining thickness of wattled brush wood 1'-0" average.

Detail Unit of Rate per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Requirement of brush wood length=100 Ft.


Thickness = 1'-0"
Height = 11 Ft.
Contents 100 x 1 x 11 = 1100 Cft.
Weight of brush wood = 1100 x 62=826.67
82.5 Mds.

Royalty of brush wood ###### Mds. 0.00er 100 Md -


Total -

LABOUR

Cooly Unskilled
for cutting brush wood 6.20 Nos. 0.00 Per day -
Cooly skilled for wattling 3.00 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

Page 79 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
2 (e) iSupplying bamboos 16'-1" to 20'-0" long 2" to 5" dia

Detail Unit of Rate 100 No. Bamboos


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Bamboos 100 Nos. 0.00 Each -


Contractor's Profit & Ov 20.00 Percent -
-

ITEM RATE

Composite Rate Per 100 Nos. Rs. - Say -

(e) i Sharpening one end of bamboo 16'-1" to 20' long 2" to 5" dia.

Detail Unit of Rate 100 No. Bamboos


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.

LABOUR

Carpenter 1.20 Nos. 0.00 Each -


Cooly 1.20 Nos. 0.00 Each -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Rate for 100 Nos. - -
1.25

ITEM RATE

Labour Rate Per 100 No. Bamboos Rs. - Say -

Page 80 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
(e) ii Driving bamboos 16'-1" to 20'-0" long 2" to 5". Driven 4'-0"' below the available bed or gro

Detail Unit of Rate 100 No. Bamboos


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Analysis for 125 Nos.

LABOUR

Cooly Skilled 2.40 Nos. 0.00 Each -


Cooly Unskilled 2.40 Nos. 0.00 Each -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Rate for 100 Nos. - -
1.25

Labour Rate Per 100 No. Bamboos Rs. - Say -

2 (e) ivTying bamboos 2" to 5" dia with B.S.W.G. No. 10 Two lines including tying around the bamboos
third tying around the top only.

Detail Unit of Rate per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Same as per Item No. 42 (b) (iv) -

LABOUR

Same as per Item No. 42 (b) (iv) -

Total -

ITEM OF RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

Page 81 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
42 (e) v Cutting and supplying brush wood from canal plantation / private source lead within one mile a
between stakes and intertwining thickness of wattled brush wood 4'-0" average

Detail Unit of Rate per Chain of One Row


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL

Requirement of brush wood length=100 Ft.


Thickness = 1'-0"
Height = 14 Ft.
Contents 100 x 1' x 14' = 1400 Cft.
Weigth of brush wood = 1400 x 62 =1052
82.5 Mds.
Royalty of brush wood ###### Mds. 0.00 r 100 Md -

Total -

LABOUR

Cooly Unskilled
for cutting brush wood 7.50 Nos. 0.00 Per day -
Cooly skilled for wattling 4.00 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Say -

ITEM RATE

Labour Rate Per Chain of One Row Rs. - Say -


Composite Rate Per Chain of One Row Rs. - Say -

Page 82 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
43 Cutting and supplying brush wood from canal plantation or from any other source
within one mile

Detail Unit of Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

MATERIAL Remarks Royalty to be paid to the forest department


and when required.
ii) Measured in thoroughly compacted and packed
Weight of 100 Cft. brush wood = 100 x 62 = 75 shapebefore filling.
82.5 Mds.
Royalty of brush wood 75.00 Mds. 0.00 r 100 Md -

LABOUR

Cooly 0.50 No. 0.00 Per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

ITEM RATE

Labour Rate Per 100 Cft. Rs. - Say -


Labour Rate Per Cum Rs. - Say -
Composite Rate Per 100 Cft. Rs. - Say -
Composite Rate Per Cum Rs. - Say -

44 Filling brush wood only thoroughly packed

Detail Unit of Rate Per 100 Cft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Cft.


LABOUR
Cooly Unskilled 0.50 No. 0.00 Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -

Rate per 100 Cft. = - -


1.25

ITEM RATE
Labour Rate Per 100 Cft. Rs. - Say -
Labour Rate Per Cum Rs. - Say -

45 Covering road 10' to 12' wide with 3" sarkanda or jungle upto one chain lead

Page 83 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit Rate per Chain
Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Rft.

LABOUR

Cooly Unskilled 1.20 Nos. 0.00 Per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Rate per 100 Rft. = - -
1.25
ITEM RATE

Labour Rate Per Chain Rs. - Say -


Labour Rate Per 30 Metre Rs. - Say -

46 a) Gachi pitching 1" thick

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Sft.

LABOUR

Cooly Unskilled 6.50 Nos. 0.00 Per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Rate per 100 Sft. = - -
1.25

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say -


Labour Rate Per Sqm. Rs. - Say -

Page 84 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
46 b) Gachi pitching done with silt clearance and berm dressing

Detail Unit Rate Per 100 Sft.


Rate
Qty Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 125 Sft.

LABOUR

Cooly Unskilled 5.50 Nos. 0.00 Per day -


Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Rate per 100 Sft. = - -
1.25

ITEM RATE

Labour Rate Per 100 Sft. Rs. - Say -


Labour Rate Per Sqm. Rs. - Say -

Page 85 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
CHAPTER NO. 19

PLUMBING SANITARY INSTALLATION


& GAS FITTINGS

DESCRIPTION OF ITEM:

Item No. 1 Providing and fitting glazed earthen ware water closet European Typ
excluding seat and cover.

(i) White

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 W.C. European Type 1.00 No. each


2 Rubber Sheet 0.222 Kg. P. Kg.
3 Bolts & Nuts 4.00 Nos. each
4 Cement 0.161 Bag Bag
5 Sand 0.40 Cft. % Cft.
6 Bajri 0.80 Cft. % Cft.

Total
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. per day


2 Skilled Cooly 1.00 No. per day

Total
Sundries 10.00 Percent
Total
Contractor's Profit & Overh 20.00 Percent
Total

ITEM RATES

Labour rate for Each Rs. Say


Composite rate for Each Rs. Say

Page 1
DESCRIPTION OF ITEM:

Item No. 1 Providing and fitting glazed earthen ware water closet European Typ
excluding seat and cover.

(ii) Coloured

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 W.C. European Type 1.00 No. 0.00 each 0.00


2 Rubber Sheet 0.222 Kg. 0.00 P. Kg. 0.00
3 Bolts & Nuts 4.00 Nos. 0.00 each 0.00
4 Cement 0.161 Bag 0.00 Bag 0.00
5 Sand 0.40 Cft. 0.00 % Cft. 0.00
6 Bajri 0.80 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Skilled Cooly 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.05 Say 0.05

Page 2
DESCRIPTION OF ITEM:

Item No. 2 Providing and fixing double seat and cover only.

(i) Bakelite.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Seat and cover double (Bakelite) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 48 Nos.

1 Plumber 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 3
DESCRIPTION OF ITEM:

Item No. 2 Providing and fixing double seat and cover only.

(ii) Plastic.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Seat and cover double (Plastic) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 48 Nos.

1 Plumber 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 4
DESCRIPTION OF ITEM:

Item No. 3 Providing and fitting glazed earthen ware water closet, squatt
(orisa pattern) combined with foot rest.

(i) White

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 W.C Orisa pattern with foot rest 1.00 No. 0.00 each 0.00
2 Cement 0.021 Bag 0.00 Bag 0.00
3 Sand 0.056 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.50 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 5
Item No. 3 Providing and fitting glazed earthen ware water closet, squatt
(orisa pattern) combined with foot rest.

(ii) Coloured.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 W.C Orisa pattern with foot rest 1.00 No. 0.00 each 0.00
coloured
2 Cement 0.021 Bag 0.00 Bag 0.00
3 Sand 0.056 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.50 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 6
DESCRIPTION OF ITEM:

Item No. 4 Providing and fitting white glazed earthen ware water closet, squat
with separate foot rest.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 W.C. squatter type 1.00 No. 0.00 each 0.00


2 Foot rest 2.00 Nos. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.50 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 7
DESCRIPTION OF ITEM:

Item No. 5 Providing and fitting water closet squatter type of terrazzo concre

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 W.C. squatter type of terrazzo concrete 1.00 No. 0.00 each 0.00
2 Cement 0.021 Bag 0.00 Bag 0.00
3 Sand 0.056 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.50 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 8
DESCRIPTION OF ITEM:

Item No. 6 Providing and fitting glazed earthen ware wash hand basin 56 x 40 c
(22" x 16"), including bracket set, waste pipe and waste coupling,

(i) White with padestal.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Glazed earthen ware wash hand basin 1.00 No. 0.00 each 0.00
2 Padestal 1.00 No. 0.00 each 0.00
3 Waste coupling, Bracket, Waste Pipe 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 9
DESCRIPTION OF ITEM:

Item No. 6 Providing and fitting glazed earthen ware wash hand basin 56 x 40 c
(22" x 16"), including bracket set, waste pipe and waste coupling,

(ii) Coloured with padestal.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Earthen ware wash hand basin (coloured) 1.00 No. 0.00 each 0.00
2 Pedestal 1.00 No. 0.00 each 0.00
3 Waste coupling, Bracket Waste
Pipe 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 10
DESCRIPTION OF ITEM:

Item No. 6 Providing and fitting glazed earthen ware wash hand basin 56 x 40 c
(22" x 16"), including bracket set, waste pipe and waste coupling,

(iii) White without padestal.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 W.H. Basin 1.00 No. 0.00 each 0.00


2 Waste coupling, Bracket, Waste Pipe 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.75 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 11
DESCRIPTION OF ITEM:

Item No. 6 Providing and fitting glazed earthen ware wash hand basin 56 x 40 c
(22" x 16"), including bracket set, waste pipe and waste coupling,

(iv) Coloured without padestal.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Coloured W.H. Basin 1.00 No. 0.00 each 0.00


2 Coupling, C.I. Bracket, Waste Pipe 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.75 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 12
DESCRIPTION OF ITEM:

Item No. 7 Providing and fixing stainless steel sink with drain board, size 12
(48" x 24") including bracket set, waste pipe and waste coupling.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Stainless steel sink with drain


board 120 x 60 cm (48" x 24") 1.00 No. 0.00 each 0.00
2 Waste coupling 1.00 No. 0.00 each 0.00
3 Waste pipe 1.00 No. 0.00 each 0.00
4 Bracket 2.00 Nos. 0.00 each 0.00
5 Cement 0.042 Bag 0.00 Bag 0.00
6 Sand 0.130 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.75 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 13
DESCRIPTION OF ITEM:

Item No. 8 Providing and fitting terrazzo concrete sink 60 x 45 cm (24" x 18")
drain board of mosaic including bracket set waste pipe and waste co

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Terrazzo concrete sink


60 x 45 cm (24" x 18") 1.00 No. 0.00 each 0.00
2 C.I. Bracket 2.00 Nos. 0.00 each 0.00
3 Waste coupling 1.00 No. 0.00 each 0.00
4 Waste pipe 1.00 No. 0.00 each 0.00
5 Cement 0.067 Bag 0.00 Bag 0.00
6 Sand 0.280 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.75 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. -0.05 Say 0.00

Page 14
DESCRIPTION OF ITEM:

Item No. 9 Providing and fixing glazed earthen ware sink, including bracket se
pipe and waste coupling.

(i) 60 x 45 cm (24" x 18")

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Glazed earthen ware sink 1.00 No. 0.00 each 0.00


2 C.I. Bracket 2.00 Nos. 0.00 each 0.00
3 Waste pipe 1.00 No. 0.00 each 0.00
4 Waste coupling 1.00 No. 0.00 each 0.00
5 Cement 0.053 Bag 0.00 Bag 0.00
6 Sand 0.144 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.75 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. -0.05 Say 0.00

Page 15
DESCRIPTION OF ITEM:

Item No. 9 Providing and fixing glazed earthen ware sink, including bracket se
pipe and waste coupling.

(ii) 37.5 x 45 cm (15" x 18")

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.E. Sink Size 37.5 x 45 cm


(15" x 18") 1.00 No. 0.00 each 0.00
2 Waste pipe 1.00 No. 0.00 each 0.00
3 Waste coupling 1.00 No. 0.00 each 0.00
4 C.I. Bracket 2.00 Nos. 0.00 each 0.00
6 Cement 0.053 Bag 0.00 Bag 0.00
7 Sand 0.144 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.75 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. -0.05 Say 0.00

Page 16
DESCRIPTION OF ITEM:

Item No. 10 Providing and fixing glazed earthen ware Flat Back Urinal.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.E. flat Back Urinal Complete set 1.00 No. 0.00 each 0.00
2 Gutties 2.00 Nos. 0.00 P. Doz 0.00
3 Screw (75 mm) 3" long 2.00 Nos. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. -0.20 Say -0.20

Page 17
DESCRIPTION OF ITEM:

Item No. 11 Providing and fitting glazed earthen ware low down flushing cistern
litres (3 gallons) capacity, including bracket set, copper connecti

(i) White

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Low down flushing cistern 3 gallon


or 13.63 litters 1.00 No. 0.00 each 0.00
2 C.I. Bracket one pair 0.00 per pair 0.00
3 Copper connection with check nut 1.00 No. 0.00 each 0.00
4 Cement 0.04 Bag 0.00 Bag 0.00
5 Sand 0.23 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.75 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.20 Say 0.20

Page 18
DESCRIPTION OF ITEM:

Item No. 11 Providing and fitting glazed earthen ware low down flushing cistern
litres (3 gallons) capacity, including bracket set, copper connecti

(ii) Coloured

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Low down flushing cistern 1.00 No. 0.00 each 0.00


2 C.I. Bracket one pair 0.00 per pair 0.00
3 Copper connection with check nut 1.00 No. 0.00 each 0.00
4 Cement 0.04 Bag 0.00 Bag 0.00
5 Sand 0.23 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.75 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.20 Say 0.20

Page 19
DESCRIPTION OF ITEM:

Item No. 12 Providing and fitting plastic made low down flushing cistern 13.63
(3 gallons) capacity, including bracket set, copper connection, etc
complete.

Coloured & White.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Low down flushing cistern 1.00 No. 0.00 each 0.00


2 C.I. Bracket one pair 0.00 per pair 0.00
3 Copper connection with check nut 1.00 No. 0.00 each 0.00
4 Cement 0.04 Bag 0.00 Bag 0.00
5 Sand 0.23 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.75 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each (White) Rs. 0.20 Say 0.20
Composite rate for Each (Coloured) Rs. 687.45 Say 687.45

Page 20
DESCRIPTION OF ITEM:

Item No. 13 Providing and fixing white enamelled cast iron low down flushing ci
13.63 litters (3 gallons) capacity, including bracket set, copper c
etc.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 White enamelled C.I low down


flushing cistern 3 gallons or
13.63 litters capacity including
all assessaries. 1.00 No. 0.00 each 0.00
2 C.I. Bracket one pair 0.00 per pair 0.00
3 Cement 0.021 Bag 0.00 Bag 0.00
4 Sand 0.056 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.75 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.05 Say 0.05

Page 21
DESCRIPTION OF ITEM:

Item No. 14 Providing and fixing C.I. highlevel flushing cistern including cost
bracket set copper connection etc.

(i) 13.63 litters (3 gallons) capacity.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.I. High level flushing cistern 1.00 No. 0.00 each 0.00
13.63 letters or 3 gallon
capacity including
accessories.
2 C.I. Bracket one pair 0.00 per pair 0.00
3 Cement 0.021 Bag 0.00 Bag 0.00
4 Sand 0.056 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 4 Nos.

1 Plumber 1.10 Nos. 0.00 per day 0.00


2 Cooly un-skilled 0.75 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.05 Say 0.05

Page 22
DESCRIPTION OF ITEM:

Item No. 14 Providing and fixing C.I. highlevel flushing cistern including cost
bracket set copper connection etc.

(ii) 4.55 liters (1 gallon) capacity.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.I. High level flushing cistern 1.00 No. 0.00 each 0.00
I/C all accessaries
2 C.I. Bracket one pair 0.00 per pair 0.00
3 Cement 0.021 Bag 0.00 Bag 0.00
4 Sand 0.056 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total 0.00

LABOUR For 4 Nos.

1 Plumber 1.10 Nos. 0.00 per day 0.00


2 Cooly un-skilled 0.75 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.05 Say 0.05

Page 23
DESCRIPTION OF ITEM:

Item No. 15 Providing and fixing, chromium plated soap dish.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Chromuim plated soap dish 1.00 No. 0.00 each 0.00


2 Gutties Plastic 2.00 Nos. 0.00 P. Doz 0.00
3 Screws 3/4" 2.00 Nos. 0.00 P. Doz 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 40 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 24
DESCRIPTION OF ITEM:

Item No. 16 Providing and fitting, glazed earthen ware soap dish.

(i) White.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Glazed earthen ware soap dish 1.00 No. 0.00 each 0.00
2 Gutties Plastic 2.00 Nos. 0.00 P. Doz 0.00
3 Screws 3/4" 2.00 Nos. 0.00 P. Doz 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 40 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 25
DESCRIPTION OF ITEM:

Item No. 16 Providing and fitting, glazed earthen ware soap dish.

(ii) Soap dish coloured.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Soap dish coloured 1.00 No. 0.00 each 0.00


2 Gutties Plastic 2.00 Nos. 0.00 P. Doz 0.00
3 Screws 3/4" 2.00 Nos. 0.00 P. Doz 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 40 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 26
DESCRIPTION OF ITEM:

Item No. 17 Providing and fixing chromium plated toilet paper holder.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.P. Toilet holder 1.00 No. 0.00 each 0.00


2 Gutties Plastic 2.00 Nos. 0.00 P. Doz 0.00
3 Screws 3/4" 4.00 Nos. 0.00 P. Doz 0.00
4 Cement 0.010 Bag 0.00 Bag 0.00
5 Sand 0.060 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. -0.01 Say 0.00

Page 27
DESCRIPTION OF ITEM:

Item No. 18 Providing and fixing chromium plated towel rail.

(i) 60 cm (24") long and 2 cm (3/4") dia.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.P. Towel rail 1.00 No. 0.00 each 0.00


2 Gutties 2.00 Nos. 0.00 P. Doz 0.00
3 Screws 4.00 Nos. 0.00 P. Doz 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 28
DESCRIPTION OF ITEM:

Item No. 18 Providing and fixing chromium plated towel rail.

(ii) 50 cm (20") long and 1.5 cm (" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.P. Towel rail 50 cm (20") long


1.5 cm (" dia) 1.00 No. 0.00 each 0.00
2 Gutties 2.00 Nos. 0.00 P. Doz 0.00
3 Screws 4.00 Nos. 0.00 P. Doz 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 29
DESCRIPTION OF ITEM:

Item No. 19 Providing and fixing looking glass 55 x 40 cm (22" x 16") size and
thick first quality.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Looking glass 5 mm thick


55 x 40 cm (22" x 16") 1.00 No. 0.00 each 0.00
2 Gutties 4.00 Nos. 0.00 P. Doz 0.00
3 Screw
4.00 Nos. 0.00 P. Doz 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 16 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 30
DESCRIPTION OF ITEM:

Item No. 20 Providing and fixing glass shelf 60 x 13 cm (24" x 5") with 5 mm th
glass.

(i) With chromium plated brackets and railing.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Glass 60 x 13 cm (24" X 5")


with 5 mm thick glass 1.00 No. 0.00 each 0.00
2 Chromium plated brackets and railing 1.00 No. 0.00 each 0.00
3 Screws 4.00 Nos. 0.00 P. Doz 0.00
4 Gutties 2.00 Nos. 0.00 P. Doz 0.00
5 Cement 0.010 Bag 0.00 Bag 0.00
6 Sand 0.060 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 16 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly skilled 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. -0.01 Say 0.00

Page 31
DESCRIPTION OF ITEM:

Item No. 20 Providing and fixing glass shelf 60 x 13 cm (24" x 5") with 5 mm th
glass.

(ii) Glass Shelf only without chromium plated brackets and railing.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Glass Shelf 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 32
DESCRIPTION OF ITEM:

Item No. 21 Providing and fitting glazed earthen ware shelf 60 x 13 cm (24" x 5
chromium plated bracket and railing.

(i) White.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.E. shelf 60 x 13 cm (24" x 5")


with C.P bracket and railing. 1.00 No. 0.00 each 0.00
2 Gutties 2.00 Nos. 0.00 P. Doz 0.00
3 Screw 4.00 Nos. 0.00 P. Doz 0.00
4 Cement 0.010 Bag 0.00 Bag 0.00
5 Sand 0.060 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 16 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly skilled 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. -0.01 Say 0.00

Page 33
DESCRIPTION OF ITEM:

Item No. 21 Providing and fitting glazed earthen ware shelf 60 x 13 cm (24" x 5
chromium plated bracket and railing.

(ii) Coloured.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.E. shelf 60 x 13 cm (24" x 5")


with C.P bracket and railing. 1.00 No. 0.00 each 0.00
2 Gutties 2.00 Nos. 0.00 P. Doz 0.00
3 Screw 4.00 Nos. 0.00 P. Doz 0.00
4 Cement 0.010 Bag 0.00 Bag 0.00
5 Sand 0.060 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 16 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly skilled 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. -0.01 Say 0.00

Page 34
DESCRIPTION OF ITEM:

Item No. 22 Providing and fitting.

(i) Plastic soap dish.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Plastic soap dish 1.00 No. 0.00 each 0.00


2 Gutties 2.00 Nos. 0.00 P. Doz 0.00
3 Screw 2.00 Nos. 0.00 P. Doz 0.00
4 Cement 0.005 Bag 0.00 Bag 0.00
5 Sand 0.030 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 40 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 35
DESCRIPTION OF ITEM:

Item No. 22 Providing and fitting.

(ii) Plastic toilet paper holder.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Plastic toilet paper holder 1.00 No. 0.00 each 0.00


2 Gutties 2.00 Nos. 0.00 P. Doz 0.00
3 Screw 4.00 Nos. 0.00 P. Doz 0.00
4 Cement 0.010 Bag 0.00 Bag 0.00
5 Sand 0.060 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 36
DESCRIPTION OF ITEM:

Item No. 22 Providing and fitting.

(iii) Plastic towel rail.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Plastic towel rail 1.00 No. 0.00 each 0.00


2 Gutties 2.00 Nos. 0.00 P. Doz 0.00
3 Screw 4.00 Nos. 0.00 P. Doz 0.00
4 Cement 0.010 Bag 0.00 Bag 0.00
5 Sand 0.06 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 37
DESCRIPTION OF ITEM:

Item No. 22 Providing and fitting.

(iv) Plastic Shelf with bracket and railing.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Plastic shelf with railing 1.00 No. 0.00 each 0.00


2 Bracket 2.00 Nos. 0.00 each 0.00
3 Gutties 2.00 Nos. 0.00 P. Doz 0.00
4 Screw 4.00 Nos. 0.00 P. Doz 0.00
5 Cement 0.004 Bag 0.00 Bag 0.00
6 Sand 0.020 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.01 Say 0.00

Page 38
DESCRIPTION OF ITEM:

Item No. 23 Providing and fixing chromium plated pillar - cock, heavy.

(i) 2 cm (").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 2 cm (") Pillar Cock 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 39
DESCRIPTION OF ITEM:

Item No. 23 Providing and fixing chromium plated pillar - cock, heavy.

(ii) 1.5 cm (").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 15 cm (") Pillar Cock heavy 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 40
DESCRIPTION OF ITEM:

Item No. 24 Providing and fixing chromium plated stop Cock Heavy.

(i) 2 cm (").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 2 cm (") stop cock 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 41
DESCRIPTION OF ITEM:

Item No. 24 Providing and fixing chromium plated stop Cock Heavy.

(ii) 1.5 cm (").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 1.5 cm (") stop cock 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 42
DESCRIPTION OF ITEM:

Item No. 25 Providing and fixing underground stop cock 13 mm (") with chromium
plated cover.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Underground stop cock with chromium


plated cover 1.00 No. 0.00 each 0.00
2 Gutties 4.00 Nos. 0.00 P. Doz 0.00
3 Screw 4.00 Nos. 0.00 P. Doz 0.00
4 Cement 0.022 Bag 0.00 Bag 0.00
5 Sand 0.060 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.25 No. 0.00 per day 0.00


2 Cooly un-killed 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.02 Say 0.00

Page 43
DESCRIPTION OF ITEM:

Item No. 26 Providing and fixing chromium plated bib cock.

(i) 2 cm (").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 2 cm (") bib cock 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 44
DESCRIPTION OF ITEM:

Item No. 26 Providing and fixing chromium plated bib cock.

(ii) 1.5 cm (").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 1.5 cm (") bib cock 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 45
DESCRIPTION OF ITEM:

Item No. 27 Providing and fixing chromium plated tee stop cock 1.5 cm (").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 1.5 cm (") Chromium plated


tee stop cock 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 46
DESCRIPTION OF ITEM:

Item No. 28 Providing and fixing, chromium plated shower rose.

(i) 1.5 cm x 10 cm (" x 4")

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Chromium plated shower rose


1.5 cm x 10 cm (" x 4") 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 47
DESCRIPTION OF ITEM:

Item No. 28 Providing and fixing, chromium plated shower rose.

(ii) 2 cm x 15 cm (" x 6")

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Chromium plated shower rose


2 cm x 15 cm (" x 6") 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 48
DESCRIPTION OF ITEM:

Item No. 29 Providing & Fixing, chromium plated mixing valve, for wash hand bas
sinks or shower.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Chromium plated mixing valve 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 24 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.02 Say 0.00

Page 49
DESCRIPTION OF ITEM:

Item No. 30 Providing and fixing gun metal peet/gate valve (screwed).

(i) Peet valve 3 cm (1") dia.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Gun Metal Peet Valve 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 50
DESCRIPTION OF ITEM:

Item No. 30 Providing and fixing gun metal peet/gate valve (screwed).

(ii) Peet valve 4 cm (1") dia.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.M. Peet Valve 4 cm (1") dia 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 51
DESCRIPTION OF ITEM:

Item No. 30 Providing and fixing gun metal peet/gate valve (screwed).

(iii) G.M. Peet Valve 5 cm (2" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.M. Peet Valve 5 cm (2" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 52
DESCRIPTION OF ITEM:

Item No. 30 Providing and fixing gun metal peet/gate valve (screwed).

(iv) G.M. Peet Valve 6.5 cm (2") dia.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.M. Peet Valve 6.5 cm (2" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 53
DESCRIPTION OF ITEM:

Item No. 30 Providing and fixing gun metal peet/gate valve (screwed).

(v) G.M. Peet Valve 7.5 cm (3" dia)

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.M. Peet Valve 7.5 cm (3" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 54
DESCRIPTION OF ITEM:

Item No. 31 Providing and fitting, Chromium plated or brass oxidised, swan neck
1.5 cm (" dia).

(i) Single way 1.5 cm (" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cost of cock 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 55
DESCRIPTION OF ITEM:

Item No. 31 Providing and fitting, Chromium plated or brass oxidised, swan neck
1.5 cm (" dia).

(ii) Two way 1.5 cm (" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cost of cock 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 56
DESCRIPTION OF ITEM:

Item No. 31 Providing and fitting, Chromium plated or brass oxidised, swan neck
1.5 cm (" dia).

(iii) Three way 1.5 cm (" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cost of cock 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 15 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 57
DESCRIPTION OF ITEM:

Item No. 32 Providing and fixing, union brass cock.

(i) 1.5 cm (" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cost of cock 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 58
DESCRIPTION OF ITEM:

Item No. 32 Providing and fixing, union brass cock.

(ii) 2 cm (" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cost of cock 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 59
DESCRIPTION OF ITEM:

Item No. 33 Providing and fixing floor trap of Cast Iron including concrete cha
all-round and C.I grating.
(i) 10 x 5 cm (4" x 2").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.I floor trap including grating


size 10 x 5 cm (4" x 2") 1.00 No. 0.00 each 0.00
2 Cement 0.065 Bag 0.00 Bag 0.00
3 Sand 0.160 Cft. 0.00 % Cft. 0.00
4 Crushed Stone 0.310 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 10 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 60
DESCRIPTION OF ITEM:

Item No. 33 Providing and fixing floor trap of Cast Iron including concrete cha
all-round and C.I grating.

(ii) Floor trap size 10 x 7.5 cm (4" x 3").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.I floor trap including grating


size 10 x 7.5 cm (4" x 3") 1.00 No. 0.00 each 0.00
2 Cement 0.065 Bag 0.00 Bag 0.00
3 Sand 0.160 Cft. 0.00 % Cft. 0.00
4 Crushed Stone 0.310 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 10 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 61
DESCRIPTION OF ITEM:

Item No. 34 Providing and fitting P-trap including concrete chamber with cast i
gully grating.

(i) Cast Iron 10 cm (4" dia)

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.I. P-trap 10 cm (4" dia) 1.00 No. 0.00 each 0.00


2 Cement 0.016 Bag 0.00 Bag 0.00
3 Sand 0.040 Cft. 0.00 % Cft. 0.00
4 Crushed Stone 0.081 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 12 Nos.

1 Plumber/Mason 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES
Labour rate for Each Rs. 0.00 Say 0.00
Composite rate for Each Rs. 0.00 Say 0.00

Page 62
DESCRIPTION OF ITEM:

Item No. 34 Providing and fitting P-trap.

(ii) Glazed 10 cm (4" dia)

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Glazed Pee trap 10 cm (4" dia) 1.00 No. 0.00 each 0.00
2 Cement 0.016 Bag 0.00 Bag 0.00
3 Sand 0.040 Cft. 0.00 % Cft. 0.00
4 Crushed Stone 0.081 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 12 Nos.

1 Plumber/Mason 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate for Each Rs. 0.00 Say 0.00


Composite rate for Each Rs. 0.00 Say 0.00

Page 63
DESCRIPTION OF ITEM:

Item No. 35 Providing and fitting 10 cm (4") gully trap, including cement cncre
costof PVC grating 15 x 15 cm (6" x 6") and Masonry chamber 30 x 30
cm(12" x 12").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Concrete Gully trap 1.00 No. 0.00 each 0.00


2 P.V.C grating 15 x 15 cm (6" x 6") 1.00 No. 0.00 each 0.00
3 Cement 0.119 Bag 0.00 Bag 0.00
4 Sand 0.190 Cft. 0.00 % Cft. 0.00
5 Crushed Stone 0.323 Cft. 0.00 % Cft. 0.00
6 Brick 20.00 No. 0.00 %0 No. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 8 Nos.

1 Plumber/Mason 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES
Labour rate for Each Rs. 0.00 Say 0.00
Composite rate for Each Rs. 0.01 Say 0.00

Page 64
DESCRIPTION OF ITEM:

Item No. 36 (i) Providing & fitting cast iron soil pipe with:

(a) Lead caulked, yarn joint 10 cm (4") dia.

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 2 METRE)

1 C.I Soil 10 cm (4") dia 2.00 Metre 0.00per metre 0.00


Cost of lead joint
a) Lead 2.36 Kg. 0.00 Per Kg. 0.00
b) Yarn 0.25 Lbs 0.00 Lbs 0.00
c) Fuel wood 1.45 Kg. 0.00 Per Kg. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost/metre
0.00 = 0.00 0.00
2

LABOUR For 20 Metre

1 Plumber/Mason 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 2.00 Nos. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Metre Rs. 0.00 Say 0.00


Labour rate per Ft. Rs. 0.00 Say 0.00

Composite rate per Metre Rs. 0.00 Say 0.00


Composite rate per Ft. Rs. 0.00 Say 0.00

Page 65
DESCRIPTION OF ITEM:

Item No. 36 (i) Providing & fitting cast iron soil pipe with:

(b) Lead caulked, yarn joint 5 cm (2") dia.

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 2 METRE)

1 C.I Soil 5 cm (2") dia 2.00 Metre 0.00per metre 0.00


Cost of lead joint
a) Lead 0.23 Kg. 0.00 Per Kg. 0.00
b) Yarn 0.13 Lbs 0.00 Lbs 0.00
c) Fuel wood 0.73 Kg. 0.00 Per Kg. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost/metre
449.46 = 224.73 0
2

LABOUR For 50 Metre

1 Plumber/Mason 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 2.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Metre Rs. 0.00 Say 0.00


Labour rate per Ft. Rs. 0.00 Say 0.00

Composite rate per Metre Rs. -0.01 Say 0.00


Composite rate per Ft. Rs. 0.02 Say 0.00

Page 66
DESCRIPTION OF ITEM:

Item No. 36 (ii) Cement caulked joint.

(a) 10 cm (4") dia.

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 2 METRE)

1 C.I Soil pipe 10 cm (4") dia 2.00 Meter 0.00per metre 0.00
2 Yarn 0.25 Lbs 0.00 Lbs 0.00
3 Cement 0.022 Bag 0.00 Bag 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per metre 0.00

LABOUR For 40 Metres

1 Mason/Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Metre Rs. 0.00 Say 0.00


Labour rate per Ft. Rs. 0.00 Say 0.00

Composite rate per metre Rs. 0.00 Say 0.00


Composite rate per Ft. Rs. 0.00 Say 0.00

Page 67
DESCRIPTION OF ITEM:

Item No. 36 (ii) Cement caulked joint.

(b) 5 cm (2") dia.

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 2 METRE)

1 C.I Soil pipe 5 cm (2") dia 2.00 Metre 0.00per metre 0.00
2 Yarn 0.13 Lbs 0.00 Lbs 0.00
3 Cement 0.011 Bag 0.00 Bag 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per metre 0.00

LABOUR For 100 Metre

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Metre Rs. 0.00 Say 0.00


Labour rate per Ft. Rs. 0.00 Say 0.00

Composite rate per metre Rs. 0.00 Say 0.00


Composite rate per Ft. Rs. 0.00 Say 0.00

Page 68
DESCRIPTION OF ITEM:

Item No. 37 Providing and fitting, A.C Soil pipe with cement caulked joint, inc
specials.

(i) 6 cm i/d.

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 3 Metre


MATERIAL

1 A.C Soil Pipe 3.00 Metre 0.00per metre 0.00


2 Specials @ 10% 0.00
3 Yarn 0.25 Lbs 0.00 Lbs 0.00
4 Cement 0.022 Bag 0.00 Bag 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per metre 0.00

LABOUR For 50 Metre

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Metre Rs. 0.00 Say 0.00


Labour rate per Ft. Rs. 0.00 Say 0.00

Composite rate per Metre Rs. 0.02 Say 0.00


Composite rate per Ft. Rs. 0.01 Say 0.00

Page 69
DESCRIPTION OF ITEM:

Item No. 37 Providing and fitting, A.C Soil pipe with cement caulked joint,
including all specials.

(ii) 7.5 cm (3" dia).

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 3 METRE

1 A.C Soil Pipe 3.00 Metre 0.00per metre 0.00


2 Specials @ 10% 0.00
3 Yarn 0.25 Lbs 0.00 Lbs 0.00
4 Cement 0.022 Bag 0.00 Bag 0.00

0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per metre 0.00

LABOUR For 45 Metre

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Metre Rs. 0.00 Say 0.00


Labour rate per Ft. Rs. 0.00 Say 0.00

Composite rate per Metre Rs. 0.00 Say 0.00


Composite rate per Ft. Rs. 0.00 Say 0.00

Page 70
DESCRIPTION OF ITEM:

Item No. 37 Providing and fitting, A.C Soil pipe with cement caulked joint,
including all specials.

(iii) 10 cm (4" dia).

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 3 METRE

1 A.C Soil Pipe 4.00 Metre 0.00per metre 0.00


2 Specials @ 10% 0.00
3 Yarn 0.31 Lbs 0.00 Lbs 0.00
4 Cement 0.028 Bag 0.00 Bag 0.00

0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per metre 0.00

LABOUR For 40 Metre

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Metre Rs. 0.00 Say 0.00


Labour rate per Ft. Rs. 0.00 Say 0.00

Composite rate per Metre Rs. 0.00 Say 0.00


Composite rate per Ft. Rs. 0.00 Say 0.00

Page 71
DESCRIPTION OF ITEM:

Item No. 37 Providing and fitting, A.C Soil pipe with cement caulked joint,
including all specials.

(iv) 15 cm (6" dia) A/C Soil Pipe.

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 4 METRE

1 A.C Soil pipe 50 cm (6" dia) 4.00 Metre 0.00per metre 0.00
2 Special at 10% 0.00
3 Yarn 0.500 Lbs 0.00 Lbs 0.00
4 Cement 0.044 Bag 0.00 Bag 0.00

0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per metre 0.00

LABOUR For 30 Metre

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Metre Rs. 0.00 Say 0.00


Labour rate per Ft. Rs. 0.00 Say 0.00

Composite rate per Metre Rs. 0.00 Say 0.00


Composite rate per Ft. Rs. 0.00 Say 0.00

Page 72
DESCRIPTION OF ITEM:

Item No. 38 Providing and fitting cast iron specials, such as tee bend, collar,
plain type.

(i) Lead Caulked Joint.

Detail Unit Rate (British System) per Kg

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 5 KG.

1 C.I. bend 100 mm (4" dia) 5.00 kg 0.00 per kg 0.00


2 Lead 0.91 kg 0.00 per kg 0.00
3 Fuel 2.91 kg 0.00 per kg 0.00
4 Yarn 0.50 lbs 0.00 per lbs 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total cost for 5 kg -
Material cost per Kg 0.00

LABOUR FOR 60 NOS.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 1.20 Nos. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Kg Rs. 0.00 Say 0.00


Composite rate per Kg Rs. 0.00 Say 0.00

Page 73
DESCRIPTION OF ITEM:

Item No. 38 Providing and fitting cast iron specials, such as tee bend, collar,
cross, etc. plain type.

(ii) Cement caulked joint.

Detail Unit Rate (British System) per Kg

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 5 KG.

1 C.I. bend 10 cm (4" dia) 5.00 kg 0.00 per kg 0.00


2 Yarn 0.50 lbs 0.00 per lbs 0.00
3 Cement 0.040 Bag 0.00 Bag 0.00
4 Sand 0.230 Cft. 0.00 % Cft. 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per Kg 0.00

LABOUR For 90 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00


2 Cooly un-skilled 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Kg Rs. 0.00 Say 0.00


Composite rate per Kg Rs. 0.00 Say 0.00

Page 74
DESCRIPTION OF ITEM:

Item No. 39 Supply and fitting of cast iron Manhole cover with frame, etc. comp

(i) 30 cm (12" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Manhole cover 30 cm (12" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 75
DESCRIPTION OF ITEM:

Item No. 39 Supply and fitting of cast iron Manhole cover with frame, etc. comp

(ii) 45 cm (18" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.I. manhole cover with frame 45 cm 1.00 No. 0.00 each 0.00
(18" dia)

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 76
DESCRIPTION OF ITEM:

Item No. 39 Supply and fitting of cast iron Manhole cover with frame, etc. comp

(iii) C.I. Manhole cover 60 cm (24" dia)

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.I manhole cover with frame 60 cm (24" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 15 Nos.

1 2 1.00 No. 0.00 per day 0.00


2 Helper (Cooly) 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 77
DESCRIPTION OF ITEM:

Item No. 40 Providing and fitting R.C.C Pipe 10 cm (4" dia) including
laying and jointing in trenches.

Detail Unit Rate (British System) per L.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 2 METRE


2.00 metre
1 R.C.C pipe 10 cm (4" dia) 6.56 Rft 0.00 per Rft 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per metre 0.00

LABOUR For 40 Metre

1 Plumber 1.00 No. 0.00 per day 0.00


2 Helper (Cooly) 2.00 Nos. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Metre Rs. 0.00 Say 0.00


Labour rate per Ft. Rs. 0.00 Say 0.00

Composite rate per Metre Rs. 0.00 Say 0.00


Composite rate per Ft. Rs. 0.00 Say 0.00

Page 78
DESCRIPTION OF ITEM:

Item No. 41 Providing and fitting chromium plated or oxidised gas Cock
6 mm (" dia)

(i) Single way.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Gas Cock of 6 mm (" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 79
DESCRIPTION OF ITEM:

Item No. 41 Providing and fitting chromium plated or oxidised gas Cock
6 mm (" dia)

(ii) Two way cock.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Gas Cock of 6 mm (" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 80
DESCRIPTION OF ITEM:

Item No. 41 Providing and fitting chromium plated or oxidised gas Cock
6 mm (" dia)

(iii) Three way cock.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Gas Cock of three way 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 15 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 81
DESCRIPTION OF ITEM:

Item No. 42 Providing and fitting nipple or bush 6 mm to 10 mm (" - 3/8") i/d.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Nipple or bush 6 mm to 10 mm
(1/4" - 3/8") i/d. 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 40 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 82
DESCRIPTION OF ITEM:

Item No. 43 Providing and fixing, brass gas cock.

(i) 1.5 cm (" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass gas cock 1.5 cm (" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 48 Nos.

1 Plumber 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 83
DESCRIPTION OF ITEM:

Item No. 43 Providing and fixing, brass gas cock.

(ii) 2 cm (" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass gas cock 2 cm (" dia) 1.00 No. 0.00 each 0.00

0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 48 Nos.

1 Plumber 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 84
DESCRIPTION OF ITEM:

Item No. 44 Providing and fixing brass stop cock/bib cock.

(i) 1.5 cm (" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass stop cock/bib cock. 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 85
DESCRIPTION OF ITEM:

Item No. 44 Providing and fixing brass stop cock/bib cock.

(ii) 2 cm (" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass stop cock/brass bib cock 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 30 Nos.

1 Plumber 0.25 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 86
DESCRIPTION OF ITEM:

Item No. 45 Hoisting and placing in position precast R.C latrine seats.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

LABOUR For 8 Nos.

1 Plumber/Mason 1.00 No. 0.00 per day 0.00


2 Coolies skilled 3.00 Nos. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00

Page 87
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 1 Providing and fixing, chromium plated waste coupling.

(i) 3 cm (1" dia)

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.P. coupling 3 cm (1" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber/Mason 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 88
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 1 Providing and fixing, chromium plated waste coupling.

(ii) 4 cm (1" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.P. coupling 4 cm (1" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber/Mason 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 89
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 2 Providing and fixing rubber plug with chain.

(i) 3 cm (1" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Rubber plug with chain 3 cm


(1" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 50 Nos.

1 Plumber 0.10 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 90
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 2 Providing and fixing rubber plug with chain.

(ii) Rubber plug with chain 4 cm (1" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Rubber plug with chain 4 cm


(1" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 50 Nos.

1 Plumber 0.10 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 91
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 3 Providing and fixing waste pipe of PVC.

(i) 3 cm (1" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 P.V.C. waste pipe 3 cm (1" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 40 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 92
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 3 Providing and fixing waste pipe of PVC.

(ii) P.V.C Waste Pipe 4 cm (1" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 P.V.C. waste pipe 4 cm (1" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 40 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 93
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 4 Providing and fixing flushing bend of P.V.C.

(i) 3 cm (1" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 P.V.C. flushing bend 3 cm (1" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 45 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.01 Say 0.00


Composite rate per each Rs. -0.02 Say 0.00

Page 94
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 4 Providing and fixing flushing bend of P.V.C.

(ii) P.V.C Flusing bend 4 cm (1" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 P.V.C. Flusing bend 4 cm (1" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 45 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.01 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 95
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 5 Providing and fixing chromium plated bottle trap with waste
pipe etc. complete.

(i) 3 cm (1" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.P Bottle trap with waste pipe 1.00 No. 0.00 each 0.00

0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 96
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 5 Providing and fixing chromium plated bottle trap with waste
pipe etc. complete.

(ii) C.P. Bottle Trap with waste pipe 4 cm (1" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.P Bottle trap 4 cm with waste pipe 1.00 No. 0.00 each 0.00

0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 97
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 6 Providing and fixing angle iron brackets for

(i) Wash hand basin and cistern.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Angle Iron Bracket 2.00 Nos. 0.00 each 0.00


2 Nail with Cutter 4.00 Nos. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 98
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 6 Providing and fixing angle iron brackets.

(ii) Sink.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Angle Iron Bracket for Sink 2.00 Nos. 0.00 each 0.00
2 Nail with cutter 4.00 Nos. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 20 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 99
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 7 Providing and fixing 1.5 cm (" dia) connection, including check
nuts etc.

(i) Plastic rubber connection.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Rubber connection with


assessories 1.00 Nos. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 50 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 100
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 7 Providing and fixing 1.5 cm (" dia) connection, including check
nuts etc.

(ii) Copper connection.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Copper Connection
assessories 1.00 Nos. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 50 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 101
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 8 Providing and fixing brass ball float valve.

(i) 1.5 cm (" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 1.5 cm (" dia) brass ball valve with


assessaries 1.00 No. 0.00 each 0.00

0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 24 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 102
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 8 Providing and fixing brass ball float valve.

(ii) 2 cm (" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass ball valve 2 cm (" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 24 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 103
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 8 Providing and fixing brass ball float valve.

(iii) 2.5 cm (1" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass ball valve 2.5 cm (1" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 24 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 104
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 8 Providing and fixing brass ball float valve.

(iv) 3 cm (1" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass ball float valve 3 cm (" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 24 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 105
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 8 Providing and fixing brass ball float valve.

(v) 4 cm (1" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass ball float valve 4 cm (1" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 24 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 106
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 8 Providing and fixing brass ball float valve.

(vi) 5 cm (2" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass ball float valve 5 cm (2" dia) 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -

LABOUR For 24 Nos.

1 Plumber 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -

ITEM RATES

Labour rate per Each Rs. 0.00 Say 0.00


Composite rate per each Rs. 0.00 Say 0.00

Page 107
CHAPTER NO. 18

ROAD & ROAD STRUCTURE

DESCRIPTION OF ITEM:

Item No. 1 Providing and laying sub-base course of brick on edge


4" (114 mm)thick including compaction to required
camber and grade.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brick 1400 Nos. 0.00 No. 0.00


2 Sand 22 Cft 0.00 % Cft 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -

LABOUR

1 Mason 1.35 Nos. 0.00 per day 0.00


2 Cooly 2.65 Nos. 0.00 per day 0.00
3 Bahisthi 0.10 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -

COMPACTION CHARGES

1 Working of DRR 0.25 hour 0.00 per hour 0.00


0.00

ITEM RATES

Labour rate per 100 Cft Rs. 0.00 Say 0.00


Labour rate per Cum Rs. 0.00 Say 0.00

Composit rate per 100 Cft Rs. 0.00 Say 0.00


Composite rate per Cum Rs. 0.00 Say 0.00

Page 1
DESCRIPTION OF ITEM:

Item No. 2 Providing and laying sub-base course of brick aggregate


includingcompaction of sub-base course material to
required depth, cambergrade and density.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brick aggregate 122 Cft 0.00 % Cft 0.00


2 Sand 24 Cft 0.00 % Cft 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -

LABOUR

2 Cooly Skilled 2.00 Nos. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -

COMPACTION CHARGES

1 Working of DRR 0.75 hour 0.00 per hour 0.00


0.00

ITEM RATES

Labour rate per 100 Cft Rs. 0.00 Say 0.00


Labour rate per Cum Rs. 0.00 Say 0.00

Composit rate per 100 Cft Rs. -0.55 Say -0.50


Composite rate per Cum Rs. -0.19 Say -0.10

Page 2
DESCRIPTION OF ITEM:

Item No. 3 Providing and laying sub-base course of stone product of approved
quality and grade, including placing, mixing, spreading and compaction
of sub-base material to required depth, grade to achieve 100% maximum
modified AASHO dry density, including carriage of all material to site
work, except gravel and aggregate for which supply within 3 Miles (5 km
is included in the rate.

(i) Pit run or bed run gravel.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Pit run or bed run gravel 120 Cft 0.00 % Cft 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -

LABOUR

2 Cooly Skilled 2.00 Nos. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -

COMPACTION CHARGES

1 Working of DRR 0.75 hour 0.00 per hour 0.00


0.00

ITEM RATES

Labour rate per 100 Cft Rs. 0.00 Say 0.00


Labour rate per Cum Rs. 0.00 Say 0.00

Composit rate per 100 Cft Rs. 0.00 Say 0.00


Composite rate per Cum Rs. 0.00 Say 0.00

Page 3
DESCRIPTION OF ITEM:

Item No. 3 (a) Providing and laying sub-base course of stone product of approved
quality and grade, including placing, mixing, spreading and compaction
of sub-base material to required depth, grade to achieve 100% maximum
modified AASHO dry density, including carriage of all material to site
work, except gravel and aggregate for which supply within 3 Miles (5 km
is included in the rate.

(ii) Crushed stone aggregate.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Crushed stone 120 Cft 0.00 % Cft 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -

LABOUR

2 Cooly Skilled 2.00 Nos. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -

COMPACTION CHARGES

1 Working of DRR 0.75 hour 0.00 per hour 0.00


0.00

ITEM RATES

Labour rate per 100 Cft Rs. 0.00 Say 0.00


Labour rate per Cum Rs. 0.00 Say 0.00

Composit rate per 100 Cft Rs. 0.00 Say 0.00


Composite rate per Cum Rs. 0.00 Say 0.00

Page 4
DESCRIPTION OF ITEM:

Item No. 4 Providing and laying base course of crushed stone aggregate of
approved quality and grade and supply and spreading of stone
screening including placing mixing spreading and compaction of base
course material to required camber and grade to achieve 100% maximum
Modified AASHTO dry density, including carriage of all materials to sit
of work except crushed stone aggregate for which supply within 3 Miles
(5 km) is included in rate.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Crushed Stone aggregate 122 Cft 0.00 % Cft 0.00


2 Screeing 22 Cft 0.00 % Cft 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -

LABOUR

1 Cooly Skilled 2.50 Nos. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -

COMPACTION CHARGES

1 Working of DRR 0.75 hour 0.00 per hour 0.00


0.00

ITEM RATES

Labour rate per 100 Cft Rs. 0.00 Say 0.00


Labour rate per Cum Rs. 0.00 Say 0.00

Composit rate per 100 Cft Rs. 0.00 Say 0.00


Composite rate per Cum Rs. 0.00 Say 0.00

Page 5
DESCRIPTION OF ITEM:

Item No. 5 Providing and laying road edging of 3" (75 mm) wide and 9" (228 mm)
deep brick on end. complete in all respects.

Detail Unit Rate (British System) per Foot

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 feet


MATERIAL

1 Bricks 288 Nos. 0.00 Nos. 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -

LABOUR

1 Mason 0.50 No. 0.00 per day 0.00


2 Cooly skilled 0.50 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -

ITEM RATES

Labour rate per one foot Rs. 0.00 Say 0.00


Labour rate per metre Rs. 0.00 Say 0.00

Composit rate per foot Rs. 0.00 Say 0.00


Composite rate per metre Rs. -0.05 Say 0.00

Page 6
DESCRIPTION OF ITEM:

Item No. 6 Providing and laying bituminous prime coat, using 10 lbs (4.537 liters)
Kerosene Oil and 10 lbs (4.55 kg) binder.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Sft


MATERIAL

1 Binder (Bitumen) 4.55 kg 100.00per tonne 4.55


2 Kerosene oil 4.537 litre 0.00per litre 0.00
3 Fuel wood 0.07 kg 0.00 per kg 0.00

Total 4.55
Contractor's Profit & O 20.00 Percent 0.91
Total 5.46

LABOUR

1 Cooly un-skilled for laying priming


coat after cleaning 0.20 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say 0.00


Labour rate per Sqm Rs. 0.00 Say 0.00

Composit rate per 100 Sft Rs. Say 0.00


Composite rate per Sqm Rs. 0.00 Say 0.00

Page 7
DESCRIPTION OF ITEM:

Item No. 7 Providing and laying bituminous tack coat, using 15 lbs (6.80 kg) of
bitumen.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Sft


MATERIAL

1 Bitumen 6.80 kg per tonne 0.00


2 Fuel wood 0.11 kg 0.00 per kg 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -

LABOUR

1 Cooly un-skilled for cleaning road,


surface and laying tack coat 0.20 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -

ITEM RATES

Labour rate per 100 Sft Rs. 0.00 Say 0.00


Labour rate per Sqm Rs. 0.00 Say 0.00

Composit rate per 100 Sft Rs. 0.00 Say 0.00


Composite rate per Sqm Rs. 0.00 Say 0.00

Page 8
DESCRIPTION OF ITEM:

Item No. 8 (I - i) Providing surface treatment to roads including supply of bitumen and
bajri/crushed stone aggregate of approved quality, including cleaning o
road surface heating and spraying bitumen spreading bajri and rolling
with road roller (including its operation cost, fuel and hire charges,
complete, including carriage of all materials to site of work except
bajri/crushed stone aggregate for which supply within 3 miles (5.0 km)
included in the rate.

1- Ist Coat Using 40 lbs (18.1590 kg) of bitumen and 5.5 Cft (0.156 Cum) bajri of
nominal size 1 inch (25 mm) per 100 Sft.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 10000 Sft Area


MATERIAL

1 Bajri 550 Cft 0.00 % Cft 0.00


2 Bitumen 1.81 Tonne per tonne 0.00
3 Fuel wood 223.92 kg 0.00 per kg 0

Total 0.00
Contractor's Profit & O 20.00 % on 1&0.00 -
Total -
Material cost per 100 Sft 30549.86 x 100
10000 0.00
LABOUR

1 Tar Sprayer 1.00 No. 0.00 per day 0.00


2 Chowkidar 1.00 No RATE per day #VALUE!
3 Cooly 12.00 Nos. 0.00 per day 0.00

Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
Contractor's Profit & O 20.00 Percent #VALUE!
Total #VALUE!

HIRE CHARGES OF MACHINERY


INCLUDING POL AND CREW CHARGES

1 Road Roller 8.00 hrs 0.00 per hour 0.00


2 Tar Boiler 8.00 hrs 0.00 per hour 0.00

Total #VALUE!

ITEM RATES
Labour rate per 100 Sft Rs. #VALUE! Say #VALUE!
Labour rate per Sqm Rs. #VALUE! Say #VALUE!
Composite rate per 100 Sft Rs. #VALUE! Say #VALUE!
Composite rate per Sqm Rs. #VALUE! Say #VALUE!

Page 9
DESCRIPTION OF ITEM:

Item No. 8 (1-ii) FIRST COAT


Using 35 lbs (15.880 kg) bitumen and 4.0 Cft (0.113 cu.m) bajri of nomi
size " (20 mm) per 100 Sft.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 10000 Sft area


MATERIAL

1 Bajri 400 Cft 0.00 % Cft 0.00


2 Bitumen 1.588 Tonne per tonne 0.00
3 Fuel wood 196 kg 0.00 per kg 0.00

Total 0.00
Contractor's Profit & O 20.00 % on 1&0.00 -
Total -
Rate per 100 Sft = 26392.90 x 100
10000 0.00
LABOUR

1 Tar sprayer 1.00 No. 0.00 per day 0.00


2 Chowkidar 1.00 No RATE per day #VALUE!
3 Cooly un-skilled 12.00 Nos. 0.00 per day 0.00

Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
Contractor's Profit & O 20.00 Percent #VALUE!
Total #VALUE!

HIRE CHARGES OF MACHINERY


INCLUDING POL AND CREW CHARGES

1 Road Roller 8.00 hrs 0.00 per hour 0.00


2 Tar Boiler 8.00 hrs 0.00 per hour 0.00

Total #VALUE!

ITEM RATES

Labour rate per 100 Sft Rs. #VALUE! Say #VALUE!


Labour rate per Sqm Rs. #VALUE! Say #VALUE!

Composite rate per 100 Sft Rs. #VALUE! Say #VALUE!


Composite rate per Sqm Rs. #VALUE! Say #VALUE!

Page 10
DESCRIPTION OF ITEM:

Item No. 8 (2-i) SECOND COAT.


Using 25 lbs (11.343 kg) bitumen and 2.75 Cft (0.077 m) bajri of nomin
size " (12 mm) per 100 Sft.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 13000 Sft area


MATERIAL

1 Bajri 357.5 Cft 0.00 % Cft 0.00


2 Bitumen 1.475 Tonne tonne 0.00
3 Fuel wood 182.5 kg 0.00 per Kg 0.00

Total 0.00
Contractor's Profit & O 20.00 % on 1&0.00 -
Total -
Rate per 100 Sft = 24446.69 x 100
13000 0.00
LABOUR

1 Tar sprayer 1.00 No. 0.00 per day 0.00


2 Chowkidar 1.00 No RATE per day #VALUE!
3 Cooly un-skilled 12.00 Nos. 0.00 per day 0.00

Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
Contractor's Profit & O 20.00 Percent #VALUE!
Total #VALUE!

HIRE CHARGES OF MACHINERY


INCLUDING POL AND CREW CHARGES

1 Road Roller 8.00 hrs 0.00 per hour 0.00


2 Tar Boiler 8.00 hrs 0.00 per hour 0.00

Total #VALUE!

ITEM RATES

Labour rate per 100 Sft Rs. Say 0.00


Labour rate per Sqm Rs. 0.00 Say 0.00

Composite rate per 100 Sft Rs. Say 0.00


Composite rate per Sqm Rs. 0.00 Say 0.00

Page 11
DESCRIPTION OF ITEM:

Item No. 8 (2-ii) SECOND COAT


Using 18 lbs (8.17 kg) bitumen and 2.0 Cft (0.056 m) bajri of
nominal size 3/8" (10 mm).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 13000 Sft area


MATERIAL

1 Bajri 260.0 Cft 0.00 % Cft 0.00


2 Bitumen 1.062 Tonne per tonne 0.00
3 Fuel wood 131.38 kg 0.00 per kg 0.00

Total 0.00
Contractor's Profit & O 20.00 % on 1&0.00 -
Total -
Rate per 100 Sft = 17614.43 x 100
13000 0.00
LABOUR

1 Tar sprayer 1.00 No. 0.00 per day 0.00


2 Chowkidar 1.00 No RATE per day #VALUE!
3 Cooly un-skilled 12.00 Nos. 0.00 per day 0.00

Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
Contractor's Profit & O 20.00 Percent #VALUE!
Total #VALUE!

HIRE CHARGES OF MACHINERY


INCLUDING POL AND CREW CHARGES

1 Road Roller 8.00 hrs 0.00 per hour 0.00


2 Tar Boiler 8.00 hrs 0.00 per hour 0.00

Total #VALUE!

ITEM RATES

Labour rate per 100 Sft Rs. 0.00


Labour rate per Sqm Rs. 0.00 Say 0.00

Composite rate per 100 Sft Rs. 0.00 Say 0.00


Composite rate per Sqm Rs. 0.00 Say 0.00

Page 12
DESCRIPTION OF ITEM:

Item No. 8 (3) THIRD COAT


Using 14 lbs (6.35 kg) bitumen and 1.5 Cft (0.0472 m) bajri of
nominal size " (6 mm) per 100 Sft.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 19000 Sft area


MATERIAL

1 Bajri 285.0 Cft 0.00 % Cft 0.00


2 Bitumen 1.207 Tonne per tonne 0.00
3 Fuel wood 149.3 kg 0.00 per kg 0.00

Total 0.00
Contractor's Profit & O 20.00 % on 1&0.00 -
Total -
Rater par 100 Sft = 19967.39 x 100
19000 0.00
LABOUR

1 Tar sprayer 1.00 No. 0.00 per day 0.00


2 Chowkidar 1.00 No RATE per day #VALUE!
3 Cooly un-skilled 12.00 Nos. 0.00 per day 0.00

Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
Contractor's Profit & O 20.00 Percent #VALUE!
Total #VALUE!

HIRE CHARGES OF MACHINERY


INCLUDING POL AND CREW CHARGES

1 Road Roller 8.00 hrs 0.00 per hour 0.00


2 Tar Boiler 8.00 hrs 0.00 per hour 0.00

Total #VALUE!

ITEM RATES

Labour rate per 100 Sft Rs. Say 0.00


Labour rate per Sqm Rs. 0.00 Say 0.00

Composite rate per 100 Sft Rs. 0.00 Say 0.00


Composite rate per Sqm Rs. 0.00 Say 0.00

Page 13
DESCRIPTION OF ITEM:

Item No. 9 (a) Resurfacting of road, including supply of bitumen and bajri/crushed
stone aggregate of approved quality, including cleaning of road surface
heating and spraying of bitumen, and spreading bajri/crushed stone
aggregate and rolling with road roller (including carriage of all mater
to site of work except bajri/crushed stone aggregate for which supply
within 3.0 Miles (5 km) is included in the rate.

(i) Using 22 lbs (9.981 kg) bitumen and 2.5 Cft (0.07 m) bajri of nominal
" (12 mm).

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 15000 Sft area


MATERIAL

1 Bajri 375.0 Cft 0.00 % Cft 0.00


2 Bitumen 1.497 Tonne 0.00
3 Fuel wood 185.11 kg 0.00 per kg 0.00

Total 0.00
Contractor's Profit & O 20.00 % on 1&0.00 -
Total -
Rate per 100 Sft = 24871.21 x 100
15000 -0.01
LABOUR

1 Tar sprayer 1.00 No. 0.00 per day 0.00


2 Chowkidar 1.00 No RATE per day #VALUE!
3 Cooly un-skilled 12.00 Nos. 0.00 per day 0.00

Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
Contractor's Profit & O 20.00 Percent #VALUE!
Total #VALUE!

HIRE CHARGES OF MACHINERY


INCLUDING POL AND CREW CHARGES

1 Road Roller 8.00 hrs 0.00 per hour 0.00


2 Tar Boiler 8.00 hrs 0.00 per hour 0.00

Total #VALUE!

ITEM RATES
Labour rate per 100 Sft Rs. #VALUE! Say #VALUE!
Labour rate per Sqm Rs. #VALUE! Say #VALUE!

Composite rate per 100 Sft Rs. #VALUE! Say #VALUE!


Composite rate per Sqm Rs. #VALUE! Say #VALUE!

Page 14
DESCRIPTION OF ITEM:

Item No. 9 a (ii) Using 20 lbs (9.074 kg) bitumen and 2.0 Cft (0.056 m) bajri of nominal
size 3/8" (10 mm) per 100 Sft.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

Analysis for 15000 Sft area


MATERIAL

1 Bajri 300 Cft 0.00 % Cft 0.00


2 Bitumen 1.361 Tonne per tonne 0.00
3 Fuel wood 168.31 kg 0.00 per kg 0.00

Total 0.00
Contractor's Profit & O 20.00 % on 1&0.00 -
Total -
Rate per 100 Sft = 22409.14 x 100
15000 0.00
LABOUR

1 Tar sprayer 1.00 No. 0.00 per day 0.00


2 Chowkidar 1.00 No RATE per day #VALUE!
3 Cooly un-skilled 12.00 Nos. 0.00 per day 0.00

Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
Contractor's Profit & O 20.00 Percent #VALUE!
Total #VALUE!

HIRE CHARGES OF MACHINERY


INCLUDING POL AND CREW CHARGES

1 Road Roller 8.00 hrs 0.00 per hour 0.00


2 Tar Boiler 8.00 hrs 0.00 per hour 0.00

Total #VALUE!

ITEM RATES

Labour rate per 100 Sft Rs. #VALUE! Say #VALUE!


Labour rate per Sqm Rs. #VALUE! Say #VALUE!

Composite rate per 100 Sft Rs. #VALUE! Say #VALUE!


Composite rate per Sqm Rs. #VALUE! Say #VALUE!

Page 15
DESCRIPTION OF ITEM:

Item No. 10(vii) Providing and laying plant pre-mixed bituminous carpet, including
compaction and finishing to required camber, grade and
density.

Detail Unit Rate (British System) per 100 Sqm.

Qty Rate Per Unit Amount (Rs.)

Analysis for 2" thick Carpet


Mixed Design (9.29 Sqm)

Coarse aggregate = 90 x 3/5 = (54%)


Fine aggregate = 90 x 2/5 = (36%)
Filler (4%)
Bitumen = (6%)

MATERIAL

Unit weight of Mix = 145 lbs/Cft


100 x 2/12 = 16.67 Cft (% Sft)
Total weight = 16.67 x 145 = 2417 lbs/%Sft
Quantity of Materials/100 Sft
1 Course aggregate
2417 x 54 12.43 Cft 0.00 % Cft 0.00
100 x 105
2 Fine aggregate (Herrow sand)
2417 x 36 8.70 Cft 0.00 % Cft 0.00
100 x 100
3 Filler 2417 x 4 1.07 Cft 0.00 % Cft 0.00
100 x 90
4 Bitumen 2417 x 6 145.00 lbs per ton 0.00
100 65.91 kg

Total 0.00
5 Contractor's Profit & O 20.00 on 12&3 0.00 -
6 Cost of Brushes and other special Tool 0.30 0.00 0.00
7 Contractor's Profit & Overheads (20%) on item '6' -

Material cost per 100 Sft (2" thick) 0.00

LABOUR

Labour required at site of work co-ordinating the


working of Machinery of complete unit of premix
plant (Mixing plant, Generator, pick up, including
establishment P.O.L and Depreciation etc.
(Mixing plant, Generator, Pickup, including
establishment POL and depreciation etc.)

Page 16
Plant Running Charges including crew charges

1 Asphalt plant 1.00 No. 0.00 per hour 0.00


2 Dumper 10.00 Nos. 0.00 per hour 0.00
3 Loader 2.00 Nos. 0.00 per hour 0.00
4 Bulldozer 1.00 No. 0.00 per hour 0.00
5 Paver Finisher 1.00 No. 0.00 per hour 0.00
6 Road Roller 1.00 No. 0.00 per hour 0.00
7 Water Loory 1.00 No. 0.00 per hour 0.00
8 Road Roller 1.00 No. 0.00 per hour 0.00
9 Tractor 1.00 No. 0.00 per hour 0.00
10 Misc. i.e. small T&P, working
of Crane & Tar Boiler L.S 0.00

Total cost of working of machinary (P/Hr.) 0.00


Working hours of machining = 6 hours
Total cost for working of machinary per day
0 x 6 = 0
Area completed per day
45 x 6 x 2204 x 6 24624 Sft (2" thick)
145
Rate of machinery per 100 Sft (2" thick) 0.00
Labour charges included in it
Assume at 12.5% of machinery charges
12.5 x 0.00 = 0.00
100
Sundries on Labour 10.00 Percent 0.00 -
Total 0.00
Contractor's Profit & O 20.00 Percent 0.000 -
Total 0.00
Labour rate per 100 Sft (2" thick)
(a) Labour Rate per 100 Sft carpet (1" thick)
0.00 = 0.00 0.00
2
(b) Material cost per 100 Sft (1" thick)
0.0 = 0.00 0.00
2

ITEM RATES

Labour rate per 100 Sft (1" thick) Rs. Say 0.00
Labour Sqm (25 mm thick) Rs. Say 0.00

Composite rate per 100 Sft (1" thick) Rs. Say 0.00
Composite rate per Sqm (25 mm) Rs. Say 0.00

Page 17
DESCRIPTION OF ITEM:

Item No. 11 Scarifying old road surface including removal of debris within 1 chain (30.0 m)

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit Amount (Rs.)

LABOUR

1 Cooly un-skilled 0.33 No. 0.00 per day

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -

ITEM RATES
Labour rate for 100 Sft Rs. 0.00 Say 0.00
Labour rate for 1 Sqm Rs. 0.00 Say 0.00

Page 18
DESCRIPTION OF ITEM:

Item No. 12 Providing R.C.C railing on bridges as per standard drawing.

Detail Unit Rate (British System) per foot

Qty Rate Per Unit Amount (Rs.)

Analyses for 12.5 feet


MATERIAL
Cement concrete 1 : 2 : 4 (Material cost)

1 Post 3 x 3.5' x 10" x 8" = 5.88 Cft


2 Railing 2 x 10 x 9" x 4" = 5.00 Cft
Total 10.88 Cf 10.88 Cft 0.00 per Cft 0.00

Steel bars 3/8" dia


Steel 3/8" dia = 3 x 14 x 22 = 77 ft
12
Railing 18 x 18 = 27 ft. 37.44 lbs
12
Total 104 ft.
104'.0 @ 0.36 lbs/ft 37.44 lbs
Steel 5/8"dia post:3 x 4 x 60 60.0 ft.
12
Railing 8 x 12 = 96.0 ft. 156.00 lbs
156 ft.
156 ft @ 1.0 lbs/ft 156.00
Wastage 15% (37.44 + 156.0 = 193.44 l 29.01 lbs
Total steel 222.45 lbs 0.00 per kg 0.00
100.93 kg including
cost of
binding wire
Total material cost for 12.5 ft. 2524.00
Material cost per foot 201.92

LABOUR

1 Cement concrete1:2:4(item 6a(ii) Chap.6=16.60- 10.88 Cft -0.82 per Cft -8.92
2 Steel 100.93 kg -18.00 per % kg -18.17
Labour rate/foot (item 9(a) Chap 6 =291.81-18.00 = 273.80 448.04
35.84

ITEM RATES

Labour rate per foot Rs. 35.84 Say 35.85


Labour rate per metre Rs. 117.54 Say 117.55

Composite rate per foot Rs. 237.76 Say 237.75


Composit rate per metre Rs. 779.85 Say 779.85

Page 19
DESCRIPTION OF ITEM:

Item No. 13 Providing and fixing G.I pipe railing as per standard drawing.

Detail Unit Rate (British System) per foot

Qty Rate Per Unit Amount (Rs.)

Analysis for 15.5 feet


MATERIAL

1 Iron post 3 No x 4'-4" x 4" x 4" x 3/8" = 22.1 lbs


Wastage 3% = 0.66 l 10.35 kg 0.00 per kg 0
= 22.76 lbs
(10.35 kg)
2 G.I pipe 2" dia
3 x 15'- 6" = 46 - 6" 50' - 2" 0.00per metre 3064.44
2 x 1'-1" = 2' - 3" 15.30 metre
48.9"
Wastage 3% 1.5"
50'.2" = 15.3 mtr
3 Short bend ( elbow) 2" 4.00 Nos. 0.00 0.00
4 Tee 2 x 2" x 2" 2.00 Nos. 0.00 0.00

Total 3064.44
Contractor's Profit & O 20.00 Percent 612.89
Total 3,677.33
Rate per foot 3989.63 = 257.40 257.40
15.50
LABOUR

1 Pipe fitter 1.00 No. 0.00 per day 0.00


2 Cooly 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -

ITEM RATES

Labour rate per foot Rs. 0.00 Say 0.00


Labour rate per metre Rs. 0.00 Say 0.00

Composit rate per foot Rs. 257.45 Say 257.45


Composite rate per metre Rs. 844.24 Say 844.25

Page 20
DESCRIPTION OF ITEM:

Item No. 14 Providing and fixing steel bearings of standard quality and type at sit
work.

Detail Unit Rate (British System) per each

Qty Rated Per Unit Amount (Rs.)

MATERIAL

1 Steel bearing 1.00 No. 0.00 each 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -

ITEM RATES
Composit rate for each Rs. 0.00 Say 0.00

DESCRIPTION OF ITEM:

Item No. 15 Providing and fixing rubber bearing pad at site of work.

Detail Unit Rate (British System) per cubic inch

Qty Rated Per Unit Amount (Rs.)

MATERIAL

1 Rubber bearing pad 1 x 1 x 1 inch 1.00 cubic 0.00 per cub. 0.00
cm.
Total 0.00
Contractor's Profit & O 20.00 Percent -
Total Rate per cubic inch -

ITEM RATES

Composite rate per cub. inch Rs. 0.00 Say 0.00


Composite rate per cub. cm Rs. 0.00 Say 0.00

Page 21
DESCRIPTION OF ITEM:

Item No. 16 Providing and laying expansion joint of neoprine strip 4" x " (100 x 6
and plastic bitumen.

Detail Unit Rate (British System) per foot

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Expansion joint of neoprine strip 0.80 Foot 0.00per metre 0


2 Plastic Bitumen (PB - 3) 1.14 kg per kg 0

Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -

LABOUR

1 Cooly skilled 0.10 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -

ITEM RATES

Labour rate per foot Rs. 0.00 Say 0.00


Labour rate per foot Rs. 0.00 Say 0.00

Composit rate per foot Rs. Say 0.00


Composite rate per metre Rs. Say 0.00

Page 22
DESCRIPTION OF ITEM:

Item No. 17 Providing and fixing rain water outlet of A.C. Pipe.

Detail Unit Rate (British System) per each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 A.C pipe 3" i/d (1.571 = 0.457 m) 0.457 Metre 0.00per metre 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -

LABOUFor 20 Nos.

1 Cooly skilled 1.00 No. 0.00 per day 0.00

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -

ITEM RATES

Labour rate per each Rs. 0.00 Say 0.00

Composit rate per each Rs. 0.00 Say 0.00

Page 23
DESCRIPTION OF ITEM:

Item No. 18 Providing and erection at site of work.

(i) R.C.C Mile/km stone including cost of fabrication etc.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

i) P.C.C 1 : 4: 8 in foundation
1 x 3.5 x 1.875 x 1.75 = 11.48 Cft
D/d mile stone 1 x 2 x 0.375 x 1.5 = 1.13 Cft
Rate as per item 6 (3) 10.35 Cf 10.35 Cft 0.00Per % Cft 0.00
ii) R.C.C 1: 2: 4
1 x 2 x 0.375 x 4.5 = 3.38 Cft
D/d 15 x 0.375 x 0.08 = 0.47 Cft
(Rate as per item 6 (6 b) (i) 2.91 Cft 2.91 Cft Per Cft 0.00
iii) Steel reinforcement " dia
12 x 5 = 60.0'
Tie 4 x 5 20.0
80. 0 Rft @ .17 lbs/Rft
Rate as per item 8(a) =13.6 lbs = 6.1 6.18 kg 0.00 per kg 0.00
iv) Cement plastec 3/8" thick 1:2 moster
1 x 4.75 x 3 = 14.25 Sft
1 x 2 x 0.375 = 0.75 Sft
Rate as per item 11(7.i) 15.00 Sf 15.00 Sft 0.00Per % Sft 0.00
v) Painting 2 coats of mile stone
Rate as per item 13(22 a ii) each 0.00 each 0.00
vi) Lettering 28 Nos. letres 4" height 28.00 Nos. 0.00 each 0.00

Total 0.00

LABOUR

i) Excavation of foundation (Item No.21(b) Chap.3)


1 x 3.5 x 1.875 x 1.25 = 8.20 Cft 8.20 Cft 0.00Per Cft 0.00
Rate as per item 3(1)
ii) P.C.C 1 : 4 : 8 in foundation
as per item (i) above
Rate as per (Item 3(b) of Chapter No.6) 10.35 Cft 0.00 Per Cft 0.00
iii) R.C.C 1 : 2: 4 (as per item (ii) above
Rate as per (Item 6a(i) Chapter No.6) 2.91 Cft Per Cft 0.00
vi) Steel reinforcement " dia
(as per item (iii) above)
(Rate as per (Item 9(a) of Chapter No.6) 6.18 kg 0.00 per kg 0.00
v) Cement plaster 3/8" thick 1 : 2 morar
(as per item (iv) above)
Rate as per (Item 7(i) of Chapter No.11) 15.08 Sft % Sft 0.00

Page 24
vi) Painting 2 coats on mile stone
(as per item (v) above)
Rate as per (Item 22 (a) (ii) of Chapter No.13) each 0.00
vii) Lettering 28 No. letters 4" high 28.00 Nos. each
(Item No.11 of Chapter 13)
Total

ITEM RATES

Labour rate per Mile/Km Stone Rs. Say 0.00


Composite rate per Mile/Km Stone Rs. Say 0.00

Page 25
DESCRIPTION OF ITEM:
Item No. 18 Providing and erection at site of work.

(ii) R.C.C Furlong/ km stone including cost of fabrication etc.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

i) P.C.C 1 : 4: 8 in foundation
1 x 1.5 x 0.75 x 1.0 = 1.13 Cft
D/d mile stone 0.75 x 0.208 x 1.5 = 0.23 Cft
Rate as per item 6 (3) 0.90 Cft 0.90 Cft 0.00Per % Cft 0.00
ii) R.C.C 1: 2: 4
0.75 x 0.23 x 1.50 = 0.23 Cft
D/d 1.5 x 0.375 x 0.083 = 0.05 Cft
(Rate as per item 6 (6 b) (i) 0.18 Cft 0.18 Cft Per % Cft 0.00
iii) Steel reinforcement dia
6 x 1'-1 11.0 ft.
Tie 3 x 1-6" 4.6
15.6 Rft @ 0.17 lbs/Rft
Rate as per item 8(a) =2.64 lbs = 1.2 1.20 kg 0.00 per kg 0.00
iv) Cement plastec 3/8" thick 1:2 master
1 x 1.92 x 0.75 = 1.44 Sft
1 x 0.75 x 0.21 = 0.16 Sft
Rate as per item 11(6 a) 1.60 Sft 1.60 Sft 0.00Per % Sft 0.00
v) Painting lettering 2 coats furlong post 0.00 each 0.00
(Rate as per item No.20(22 bii)
vi) Lettering 3" height each 0.00 each 0.00

Total
LABOUR
i) Excavation of foundation (Item NO.21(b) of Chap.3)
1.50 x 0.75 x 0.50 = 0.56 Cft 0.56 Cft 0.00Per Cft 0.00
ii) P.C.C 1 : 4 : 8 in foundation
as per item (i) above
Rate as per (Item No.3(b) Chapter No.6) 0.90 Cft 0.00Per % Cft 0.00
iii) R.C.C 1 : 2: 4 (as per item (ii) above
Rate as per (Item 6(a)i Chapter No.6) 0.18 Cft Per % Cft 0.00
vi) Steel reinforcement " dia
(as per item (iii) above)
Rate as per (Item 9(b) Chapter No.6) 1.20 kg 0.00 per kg 0.00
v) Cement plaster 3/8" thick 1 : 2 mortar
(as per item (iv) above)
Rate as per (Item 7(i) of Chapter 11) 1.60 Sft 0.01Per % Sft 0.00
vi) Painting 2 coats of Furlong / km
(as per item (v) above)
(Rate as per item 20(b)) (Item No.22(b) (ii) Ch each 0.00 each 0.00
0.00
ITEM RATES

Labour rate per furlong ( Km) Stone Rs. 0.00 Say 0.00
Composite rate per furlong ( Km) Stone Rs. Say 0.00

Page 26
DESCRIPTION OF ITEM:

Item No. 18 Providing and erection at site of work.

(iii) R.C.C Boundry pillar.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

i) R.C.C 1: 2: 4
0.75 x 0.75 x 3 = 1.70 Cft
(Rate as per item 6 (6 b) (i) 1.70 Cft Per Cft 0.00
ii) Steel reinforcement 3/8" dia
1 x 2.5 = 2.5 Rft
2.5 Rft @ 0.37 lbs/Rft
Rate as per item 8(a) = 0.93 lbs = 0.42 0.42 kg 0.00 per kg 0.00

Total 0.00

LABOUR

i) Excavation of foundation (Item No.21(b) Chap.3)


0.75 x 0.75 x 1.50 = 0.84 Cft 0.84 Cft 0.00Per Cft 0.00
ii) R.C.C 1 : 2: 4 (as per item (ii) above)
Rate as per (Item No.6(a) (i) of Chapter No.6) 1.70 Cft Per % Cft 0.00
iii) Steel reinforcement " dia
(as per item (iii) above)
Rate as per (Item No.9(b) Chapter No.6) 0.42 kg 0.00 per kg 0.00

0.00

ITEM RATES

Labour rate for each pillar Rs. 0.00 Say 0.00


Composite rate for each pillar Rs. Say 0.00

Page 27
DESCRIPTION OF ITEM:

Item No. 18 (iv) Providing and erection at site of work.

(a) Sign post of M.S plate 1/8" thick (Mandatory) Road Signs.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

i) P.C.C. 1 : 4 : 8 in foundation
2 x 2 x 2.5 = 10.00 Cft
Rate as per item 6(3) 10.00 Cft 0.00Per % Cft 0.00
ii) Steel
a) T. Iron 0.25 x 0.25 x 0.375 = 9.00 Rft
9 Rft @ 7.17 lbs/ft. = 64.53 lbs
b) M.S plate 1/8" thick
11x2x2 4 = 3.14 Sft @ 5.10 lbs/sft= 16.01 lbs
Total 80.54 lb 36.60 kg 0.00 per kg 0.00
Rate as per item 8(a)
iii) Painting and lettering each 0.00 each 0.00

Total 0.00

LABOUR

i) Excavation and fixing L.S 0.00


ii) P.C.C (1 : 4: 8) in foundation 10.00 Cft 0.00 Per Cft 0.00
(as per item (i) above)
Rate as per (Item 3(b) of Chapter No.6)
iii) Febrication of steel 36.60 kg 0.00 per kg 0.00
(as per item (ii) above)
Rate as per (Item 9(b) Chapter No.6)
iv) Jointing plate with T Iron L.S 0.00
v) Painting & lettering 0.00

0.00

ITEM RATES

Labour rate for each sign Rs. Say 0.00


Composite rate for each sign Rs. Say 0.00

Page 28
DESCRIPTION OF ITEM:

Item No. 18 (iv) Providing and erection at site of work.

(b) Warning/Direction/Informatory, Road Signs.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

i) P.C.C. 1 : 4 : 8 in foundation
2 x 2 x 2.5 = 10.00 Cft
Rate as per item 6(3) 10.00 Cft 0.00Per % Cft 0.00
ii) Steel
a) T. Iron 0.25 x 0.25 x 0.375 = 9.00 Rft
9 Rft @ 7.17 lbs/ft. = 64.53 lbs
b) M.S plate 1/8" thick
1.7.3 2 @ 5.10 lbs/sft= 8.83 lbs
Total 73.36 lb 33.35 kg 0.00 per kg 0.00
Rate as per item 8(a)
iii) Painting and lettering each each 0.00

Total 0.00

LABOUR

i) Excavation and fixing L.S 0.00


ii) P.C.C (1 : 4 : 8) in foundation 10.00 Cft 0.00 Per Cft 0.00
(as per item (i) above)
Rate as per (Item 3(b) of Chapter No.6)
iii) Febrication of steel 33.35 kg 0.00 per kg 0.00
(as per item (ii) above)
Rate as per (Item 9(a) of Chapter No.6)
iv) Jointing of plate with T. Iron L.S 0.00
v) Painting and lettering L.S 0.00
0.00

ITEM RATES

Labour rate for each Post Rs. Say 0.00


Composite rate for each Post Rs. Say 0.00

Page 29
DESCRIPTION OF ITEM:

Item No. 19 Providing and laying dry brick pavement/soling in streets or roads etc.
sand grouted, laid in proper camber including preparation, watering,
compaction of bed to proper camber, and sand cushion.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brick 1400.00 Nos. 0.00 Nos. 0.00


2 Sand 22.00 Cft 0.00 % Cft 0.00

Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -

LABOUR

1 Cooly skilled 1.35 Nos. per day 0


2 Cooly 2.65 Nos. per day 0
3 Bahishti 0.10 No. per day 0

Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
-

ITEM RATES

Labour rate per 100 Cft Rs. 0.00 Say 0.00


Labour rate for m Rs. 0.00 Say 0.00

Composite rate per 100 Cft Rs. 0.00 Say 0.00


Composit rate per m Rs. 0.00 Say 0.00

Page 30
CHAPTER NO. 9
ROOFING
Note 1. Rates for all finished works include the removal of surplus debris, unused
material and by products.
Note 2. Add extra 13%, 32% and 51% on labour rates only or 6%, 15% and 23% on
composite rates for 2nd, 3rd fourth and subsequent floors respectively.

DESCRIPTION OF ITEM NO 1: First class tiles roofing consisting of 4" (100mm)


earth and 1" (25mm) mud plaster with Gobri
leaping over " (12mm) thick cement plaster 1:6
with 34 Ibs of hot bitumen coating sand blinded
provided over two layers of tiles 12" x 6" x 1"
(300x150x32mm) laid in 1:6 cement mortar
with 1" (25mm) thick sand-wiched layer of 1:6
cement mortar including 1:2 cement pointing
under side of tiles, complete including curing etc.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Tiles 12"x6"x1" 400 Nos 1000 Nos


Cement for laying 0.26 Bag
Pointing under side 1:2 0.17 Bag
Plaster of tiles in between and over tiles 1:6 1.10 Bag
Plaster along parapet 0.23 Bag
1.76 Bags P. Bag -

Sand for laying in 1:6 mortar 1.96 Cft


Sand for pointing 1:2 0.41 Cft
Sand for Plaster 1:6 8.28 Cft
Sand for Plaster 1:6 along parapet 1.71 Cft
Sand for blinding of bitumen 1.00 Cft
13.36 Cft P. Cft -
Earth upto 100' (30 M) lead and lift
upto 20' (6 M)
For 1" (25mm) mud plaster 10.00 Cft
For 4" (100mm) filling over tiles 33.00 Cft
43.00 Cft P. Cft -

Page 1
Item No. 1

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Bhoosa for top layer only 17Sr (15 .8)Kg P. Kg -


Clay for gobri leeping 0.75 Cft P. Cft -
Cowdung for Gobri leeping 0.75Cft ( 15) Kg P 100 -
Two coats of bitumen 34Lbs(15 .43)Kg P. Kg -
Fuel wood 0.2Md (7 .44)Kg P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate Analysis for 125 Sft
Masons for laying tiles 1.50 Nos
Mason for pointing 0.75 Nos
Mason for cement plaster 1.00 No
Mason for mud plaster 0.40 No
3.65 Nos Each -

Unskilled Coolies 6.00 Nos P. Day -


Bahishti 1.25 Nos P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate P/ Sqm Rs. -
Say
Composite Rate Per 10 Rs. Say -
Composite Rate P/ Sqm Rs. Say -

Page 2
DESCRIPTION OF ITEM NO 2: Second class tile roofing consisting of 4" (100mm)
earth and 1" (25mm) mud plaster with gobri leeping
over " thick cement plaster 1:6 with 34 lbs per %
Sft or 1.72 Kg/Sqm of hot bitumen coating sand
blinded provided over one layer of 12"x6"x2"
(300x150x50mm) tiles, laid in 1:6 cement pointing
underneath of tiles complete, including curing etc.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material
Per
Tiles 12"x6"x2" 200.00 Nos 1000 N -
Cement for laying in 1:6 mortar 0.23 Bag
Cement for plaster 1:6 0.55 Bag
Cement for pointing 1:2 0.17 Bag
Cement for Plaster along parapet 0.23 Bag
1.18 Bags P. Bag -
Sand for laying in 1:6 mortar 1.68 Cft
Sand for Plaster 1:6 4.14 Cft
Sand for pointing 1:2 0.43 Cft
Sand for Plaster 1:6 along parapet 1.71 Cft
Sand for blinding of bitumen 1.00 Cft
8.96 Cft P. Cft -

Earth upto 100' (30 M) and lift upto


20' (6 M)
For 1" (25mm) mud plaster 10.00 Cft
For 4" (100mm) filling over tiles 33.00 Cft
43.00 Cft P. Cft -
Fine clay for gobri 0.75 Cft P. Cft -
Bhoosa 17Sr (15. 81) Kg P. Kg -
Cowdung 0.75Cft ( 15) Kg P 100 -
Bitumen for 2 coats 1/16" (2mm) thick 34Lbs(15 .43) Kg P. Kg -
Fuel wood 0.2Mds(7 .44) Kg P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Page 3
Item No. 2

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour
Rate Analysis for 125 Sft
Masons 2.50 Nos P. Day -
Unskilled Coolies 5.00 Nos P. Day -
Bahishti 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. -
Say
Composite Rate Per 10 Rs. Say -
Composite Rate Per Sq Rs. Say -

Page 4
DESCRIPTION OF ITEM NO 3: Covering mud roof with coaltar and fine sand.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Coaltar 7.72 Kg. P. Kg -


Fine sand 1.00 Cft P. Cft -
Charcoal for heating coaltar 3.00 Kg. P. Kg. -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Mason 0.12 No P. Day -


Unskilled Cooly 0.25 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total

Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. -
Say
Composite Rate Per 100 Sft Rs. Say -
Composite Rate Per Sqm Rs. Say -

Page 5
Note. The unit of rate is for filling 100 Sft of roof.

DESCRIPTION OF ITEM NO 4: Filling spaces in between.

a) Wooden battons over beams filled with deodar


wood pieces (spacers).

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Deodar wood 2x10 (9"x1"x5") 0.54 Cft


Wastage 20% 0.11 Cft
0.65 Cft P. Cft -

Wire Nails 0.28 Kg. P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate Analysis for 150 Sft
Carpenter for making grooves in batten
and fixing of wooden strips 0.50 No Each -
Unskilled Cooly 0.50 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. -
Say
Composite Rate Per 10 Rs. Say -
Composite Rate Per Sq Rs. Say -

Page 6
Item No. 4 Filling spaces in between.

b) RCC Battens Filled with C.C. Blocks (1:3:6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

9 No x2/3"x5/12" 1.88 Cft


2 No x2/3"x5/12" 0.28 Cft

Cement for blocks 0.27 Bag


For laying 0.17 Bag
0.44 Bag P. Bag -
Sand for blocks 1.02 Cft
For laying 0.65 Cft
1.67 Cft P. Cft -
Bajri 2.04 Cft P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate Analysis for 125 Sft
Mason 0.50 No -
Unskilled Cooly 1.00 No -
Bahishti 0.13 No -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 7
Item No. 4 Filling spaces in between.

c) Spaces filled with bricks

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material
Per
Bricks including wastage (30+15) 45.00 Nos 1000 N -
Cement 0.20 Bag P. Bag -
Sand 0.75 Cft P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate Analysis for 125 Sft
Mason 0.17 No P. Day -
Cooly 0.17 No P. Day -
Bahishti 0.10 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 8
DESCRIPTION OF ITEM NO 5: Single layer of tiles 9"x4x1" (225 x 112.5 x
40mm) laid over 4" (100mm) earth and 1" (25mm)
mud plaster without Bhoosa grouted with cement
sand 1:3 on top of RCC roof slab provided with 34
Ibs. per % Sft bitumen coating sand blinded.

Detail Unit Rate (British System) per 100 Sft


Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material Per
Brick tiles 225 x 112.5 x 40 mm (9"x41/2"x1") 360.00 Nos 1000 N -
Sand for grouting 2.50 Cft
Sand for blinding 1.25 Cft
3.75 Cft P. Cft -
Cement 0.75 Bag P. Bag -
Good earth lead upto 100' (30 M) and lift
upto 20' (6 M) 43.00 Cft P. Cft -
Two coats of bitumen 15.42 4Lbs(15 .42) Kg P. Kg -
Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate Analysis for 150 Sft
Plasterer 0.125 No
Mason for Laying 0.500 No
Mason for Grouting 0.125 No
0.75 No Each -
Cooly for and plaster 0.50 No
Cooly for grouting laying 0.65 No
Cooly for grouting 0.25 No
1.40 Nos Each -
Painter for bitumen 0.50 No Each -
Bahishti 0.50 No Each -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Composite Rate Per 10 Rs. Say -
Composite Rate Per Sq Rs. Say -

Page 9
DESCRIPTION OF ITEM NO 6: Jack arch roofing 4" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with 3" (75mm) earth and 1" (25mm)
plaster soffits of arches cement plastered 1:6
and " (12mm) thick. The rate also includes
bitumen coating centering, laying skew bricks in
cement sand mortar 1:3 and encasing exposed flanges
of the joints with fine cement concrete 1:2:4. Using
stone aggregate.
a) Cement concrete in haunches. (1:6:12)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material
Per
Bricks 9"x4"x3" 550.00 Nos 1000 N -
Cement for laying 1.60 Bag
Cement for plastering Soffits 0.57 Bag
Cement for concrete in haunches 2.00 Bag
Cement for concrete in flanges 0.60 Bag
4.77 Bags P. Bag -

Sand for laying 10.00 Cft


Sand for plastering soffit 4.26 Cft
Sand for concrete in haunches 16.20 Cft
Sand for concrete in flanges 1.50 Cft
31.96 Cft P. Cft -

Stone aggregate for concrete in haunches 32.00 Cft


Stone aggregate for concrete in flanges 3.00 Cft
35.00 Cft P. Cft -

Earth for filling and plastering 33.00 Cft P. Cft -


Bhoosa 17Lbs(15 .81) Kg P. Kg -
Fine Clay 0.75 Cft P. Cft -
Cowdung 0.75 Cft ( 15) Kg P. 100 -

Page 10
a) Cement concrete in haunches. (1:6:12)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Bitumen 34Lbs(15 .42) Kg P. Kg -


Fuel 0.2Mds(7 .44) Kg P. Kg -
Kail wood for centring 0.4 Cft. P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate Analysis for 125 Sft
Masons 3.50 Nos P. Day -
Carpenter 0.50 No P. Day -
Unskilled Coolies 7.00 Nos P. Day -
Bahishti 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 11
Item No. 6 Jack arch roofing 4" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with 3" (75mm) earth and 1" (25mm)
plaster soffits of arches cement plastered 1:6
and " (12mm) thick. The rate also includes
bitumen coating centering, laying skew bricks in
cement sand mortar 1:3 and encasing exposed
flanges of the joints with fine cement concrete
1:2:4. Using stone aggregate.

b) Cement concrete in haunches (1:3:6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material Per
Bricks 9"x4"x3" 550.00 Nos 1000 N -
Cement for laying 1.60 Bag
Cement for plastering Soffits 0.57 Bag
Cement for concrete in haunches 4.10 Bag
Cement for concrete in flanges 0.60 Bag
6.87 Bags P. Bag -

Sand for laying 10.00 Cft


Sand for plastering soffit 4.26 Cft
Sand for concrete in haunches 15.40 Cft
Sand for concrete in flanges 1.50 Cft
31.16 Cft P. Cft -
Stone aggregate for concrete in haunches 31.00 Cft
Stone aggregate for concrete in flanges 3.00 Cft
34.00 Cft P. Cft -

Earth for filling and plastering 33.00 Cft P. Cft -


Bhoosa 17Lbs(15 .81) Kg P. Kg -
Fine Clay 0.75 Cft P. Cft -
Cowdung 0.75Cft ( 15) Kg P.% Kg -
Bitumen 34Lbs(15 .43) Kg P. Kg -
Fuel 0.2Mds(7 .44) Kg P. Kg -
Kail wood for centring 0.411 Cft. P. Cft -

Total
Contractor's Profit & Ove 20 Percent
Total

Page 12
b) Cement concrete in haunches (1:3:6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour
Rate Analysis for 125 Sft
Masons 3.50 Nos P. Day -
Carpenter 0.50 No P. Day -
Unskilled Coolies 7.00 Nos P. Day -
Bahishti 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 13
DESCRIPTION OF ITEM NO 7: Jack arch roofing 4" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with " (12mm) thick cement plaster
1:6 on top (Except earth filling, plaster and gobri),
soffits of arches cement plastered. The rate also
includes bitumen coating centering, laying skew
bricks in cement sand mortar 1:3 and encasing
exposed flanges of the joints with fine cement
concrete 1:2:4. Using stone aggregate.

a) Cement concrete in haunches. (1:6:12)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material
Per
Bricks 9"x4"x3" 550.00 Nos 1000 N -
Cement for laying 1.60 Bag
Cement for plastering top 0.51 Bag
Cement for plastering soffits 0.57 Bag
Cement for concrete in haunches 2.00 Bag
Cement for concrete in flanges 0.60 Bag
5.28 Bags P. Bag -

Sand for laying 10.00 Cft


Cement for plastering top 3.84 Cft
Sand for plastering soffits 4.26 Cft
Sand for concrete in haunches 16.20 Cft
Sand for concrete in flanges 1.50 Cft
35.80 Cft P. Cft -

Stone aggregate for concrete in haunches 32.00 Cft


Stone aggregate for concrete in flanges 3.00 Cft
35.00 Cft P. Cft -

Page 14
a) Cement concrete in haunches. (1:6:12)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Bitumen 34Lbs(15 .43) Kg P. Kg -


Fuel 0.2Mds(7 .44) Kg P. Kg -
Deodar wood (2nd Class) 0.50 Cft P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate Analysis for 125 Sft
Masons 2.75 Nos P. Day -
Carpenter 0.50 No P. Day -
Unskilled Coolies 5.50 Nos P. Day -
Bahishti 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 15
Item No. 7 Jack arch roofing 4" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with " (12mm) thick cement plaster
1:6 on top (Except earth filling, plaster and gobri),
soffits of arches cement plastered. The rate also
includes bitumen coating centering, laying skew
bricks in cement sand mortar 1:3 and encasing
exposed flanges of the joints with fine cement
concrete 1:2:4. Using stone aggregate.

b) Cement concrete in haunches. (1:3:6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material
Per
Bricks 9"x4"x3" 550.00 Nos 1000 N -
Cement for laying 1.60 Bag
Cement for plastering soffits 0.57 Bag
Cement for concrete in haunches 4.10 Bag
Cement for concrete in flanges 0.60 Bag
6.87 Bags P. Bag -

Sand for laying 10.00 Cft


Cement for plastering top 3.84 Cft
Sand for plastering soffits 4.26 Cft
Sand for concrete in haunches 15.40 Cft
Sand for concrete in flanges 1.50 Cft
35.00 Cft P. Cft -

Stone aggregate for concrete in haunches 31.00 Cft


Stone aggregate for concrete in flanges 3.00 Cft
34.00 Cft P. Cft -

Page 16
b) Cement concrete in haunches. (1:3:6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Bitumen 34Lbs(15 .43) Kg P. Kg -


Fuel 0.2Mds(7 .44) Kg P. Kg -
Kail wood centring 0.411 Cft. P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate Analysis for 125 Sft
Masons 2.75 Nos P. Day -
Carpenter 0.50 No P. Day -
Unskilled Coolies 5.50 Nos P. Day -
Bahishti 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 17
DESCRIPTION OF ITEM NO 8: Extra for vaulted jack arch roofing

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour
Rate Analysis for 125 Sft
Masons 1.00 No P. Day -
Carpenter 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Per 1 Rs. -

Labour Rate for P/ Sq Rs. -

Page 18
DESCRIPTION OF ITEM NO 9: Jack arch roofing of shingle and cement concrete
(1:3:6), 4" (112.5mm) thick at crown, with "
(12mm) cement plaster including cost of
supplying erecting and dismantling centering.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Cement 7.46 Bags P. Bag -


Sand 28.00 Cft P. Cft -
Shingle 56.00 Cft P. Cft -
Kail wood 0.411 Cft. P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Masons 0.50 No P. Day -


Coolies for stacking & mixing 3.00 Nos P. Day -
Coolies for ramming 3.00 Nos P. Day -
Coolies for carrying 2.00 Nos P. Day -
Coolies for carpenter 1.00 No P. Day -

Carpenter 1.00 No P. Day -


Bahishti 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 19
DESCRIPTION OF ITEM NO 10: Earth filling over roof including watering
ramming with 1" (25mm) mud plaster finished
with gobri leeping.

a) 3" (75mm) thick earth filling and 1" (25mm) mud


plaster.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Earth lead upto 100' (30 M) and lift upto


20' (6 M) 33 Cft P. Cft -
Bhoosa 17Lbs(15 .81) Kg P. Kg -
Clay 0.75 Cft P. Cft -
Cowdung 0.75Cft ( 15) Kg P % Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate Analysis for 125 Sft
Bahishti 0.12 No P. Day -
Coolies for lifting and ramming earth 1.00 No P. Day -
Mason 0.12 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 20
Item No. 10 Earth filling over roof including watering
ramming with 1" (25mm) mud plaster finished
with gobri leeping.

b) 4" (100mm) thick earth filling and 1" (25mm)


mud plaster.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Earth lead upto 100' (30 M) and lift upto


20' (6 M) 43 Cft P. Cft -
Bhoosa 17Lbs(15 .81) Kg P. Kg -
Fine clay for gobri 0.75 Cft P. Cft -
Cowdung 0.75 Cft ( 15) Kg P % Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Bshishti 0.18 No P. Day -


Coolies for lifting and ramming earth 1.00 No P. Day -
Mason 0.12 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 21
DESCRIPTION OF ITEM NO 11: 1/8"(3mm) thick gobri leeping on roofs or floors.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Fine clay 0.75 Cft P. Cft -


Cowdung 0.75 Cft ( 15) Kg P. 100 -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate Analysis for 150 Sft
Mason 0.12 No P. Day -
Bahishti 0.06 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 22
DESCRIPTION OF ITEM NO 12: 2 coats of bitumen laid hot using 34 lbs
(1.72Kg/Sqm) per % Sft over roof and
blinded with sand at 1 Cft per % Sft.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Bitumen 34Lbs(15 .43) Kg P. Kg -


Sand 1.00 Cft P. Cft -
Fuel wood 0.12Mds( 4.46)Kg P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total

Labour
Rate for 125 Sft
Cooly for heating & laying 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Per 1 Rs. Say -
Labour Rate for P/ Sq Rs. Say -

Composite Rate for Pe Rs. Say -


Composite Rate for P/ Rs. Say -

Page 23
DESCRIPTION OF ITEM NO 13: Fixing corrugated galvanized iron sheets with
G.I. bolts, nuts, limpet and bitumen washers,
wind ties complete in all respect without valleys
and ridges.

a) 20 - S. W. G.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material
Sheets of 20 gauge = 100 Sft.
wastage & overlaping @ 20% = 20 Sft
=120 Sft 2Cwt (102 .65) Kg P. Kg -
Wind tie (rod) 22Lbs(9 .98) Kg P. Kg -
G.I. bolts and nuts 2.00 Doz Doz -
Limpet washers 2.00 Doz Doz -
G.I. Hook, bolts & nuts 1.50 Doz Doz -
Bitumen washers 3.85 Doz Doz -
Charcoal 4 Sr. (3. 75) Kg P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour (for 150 Sft.)

Blacksmith 1.00 No P. Day -


Cooly 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 24
Item No. 13 Fixing corrugated galvanized iron sheets with
G.I. bolts, nuts, limpet and bitumen washers, wind
ties complete in all respect without valleys and
ridges.

b) 22 - S. W. G.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

C.G.I. Sheets of 22 gauge including over


lapping and wastage. 120 Sft 1.7Cwt (8 6.39)Kg P. Kg -

Wind tie (rod) 22Lbs(9 .98) Kg P. Kg -


G.I. bolts and nuts 2.00 Doz Doz -
Limpet washers 2.00 Doz Doz -
G.I. Hook, bolts & nuts 1.50 Doz Doz -
Bitumen washers 3.82 Doz Doz -
Charcoal 4 Sr. (3. 72) Kg P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 150 Sft.

Blacksmith 1.00 No 0.00 P. Day -


Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Per 1 Rs. Say -
Labour Rate for P/ Sq Rs. Say -

Composite Rate for Pe Rs. Say -


Composite Rate for P/ Rs. Say -

Page 25
Item No. 13 Fixing corrugated galvanized iron sheets with
G.I. bolts, nuts, limpet and bitumen washers, wind
ties complete in all respect without valleys and
ridges.

c) 24 - S. W. G.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

C.G.I. Sheets of 24 gauge including over


lapping and wastage. 120 Sft 1.34Cwt(6 8.10)Kg P. Kg -

Wind tie 22Lbs(9 .98) Kg P. Kg -


G.I. bolts and nuts 2.00 Doz Doz -
Limpet washers 2.00 Doz Doz -
G.I. Hook, bolts & nuts 1.50 Doz Doz -
Bitumen washers 3.82 Doz Doz -
Charcoal 4 Sr. (3. 72) Kg P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate for 150 Sft
Blacksmith 1.00 No P. Day -
Cooly 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 26
DESCRIPTION OF ITEM NO 14: Khassi parnalas in cement and sand mortar (1:2)
12" (300mm) outside width finished smooth with
a floating coat of neat cement.

Detail Unit Rate (British System) per 100 Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 15 Rft
Material

Cement for " (12mm) plaster 0.18 Bag


Cement for floating 0.06 Bag
Cement for side filling 0.26 Bag
0.50 Bags P. Bag -
Sand 1.10 Cft P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Mason 0.67 No P. Day -


Unskilled Cooly 0.67 No P. Day -
Bahishti 0.09 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate for Per R Rs. Say -

Composite Rate Per Rf Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 27
DESCRIPTION OF ITEM NO 15: Making Khuras, on roof size 2' x 2' x 4" (600 x 600 x
100mm)

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Cement 0.20 Bag P. Bag -


Sand 0.55 Cft P. Cft -
Aggregate (Stone) 1.25 Cft P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Nos)

Mason 0.20 No P. Day -


Unskilled Cooly 0.20 No P. Day -
Bahishti 0.05 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. Say -

Composite Rate for Ea Rs. Say -

Page 28
DESCRIPTION OF ITEM NO 16: Bottom khuras of brick masonry in cement mortar
(1:6) 4'x2'x4" (1200x600x114mm) over 3"
(75mm) cement concrete (1:4:8)

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Cement 0.37 Bag P. Bag -


Sand 2.00 Cft P. Cft -
Brick Aggregate 2.00 Cft P. Cft -
Bricks 42.00 No 1000 N -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate Analysis for 1.25 No.
Mason 0.20 No P. Day -
Cooly 0.20 No P. Day -
Bahishti 0.05 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. Say -

Composite Rate for Ea Rs. - Say -

Page 29
DESCRIPTION OF ITEM NO 17: Plain galvanized iron sheets of 22 S.W.G. rain
water down pipe including clamp and fixing in
position.

a) 4" (100mm) dia down pipe

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

G.I. sheets = 1.05 Sft


Add. 10% for joints and wastage 0.10 Sft
1.15 Sft @ 1.31 Lbs/Sft 1.5Lbs(0. 68) Kg P. Kg -
Add for clamps bolts nuts and rivets. 0.125 Kg P. Kg. -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate Analysis for 1.25 Rft
Blacksmith 0.03 No P. Day -
Unskilled Cooly 0.03 No P. Day -
Mason 0.03 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate for Per R Rs. Say -

Composite Rate Per Rf Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 30
DESCRIPTION OF ITEM NO 17: Plain galvanized iron sheets of 22 S.W.G. rain
water down pipe including clamp and fixing in
position.

b) 5" (125mm) dia down pipe.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

G.I. sheets 1.31 Sft


Add. 10% for joints and wastage 0.13 Sft
1.44 Sft @ 1.31 Lbs/Sft 1.90Lbs(0 .86) Kg P. Kg -
Add for clamps bolts nuts and rivets. 0.125 Kg P. Kg. -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour 1.25 Rft

Blacksmith 0.03 No P. Day -


Unskilled Cooly 0.03 No P. Day -
Mason 0.03 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate for Per R Rs. Say -

Composite Rate Per Rf Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 31
DESCRIPTION OF ITEM NO 18: Plain galvanized iron sheets flashing of 22 gauge.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

G.I. sheets 1.00 Lbs


22 guage 0.96 Sft
0.96 Sft @ 1.31 Lbs/Sft 1.26Lbs(0 .57) Kg P. Kg -
Fixture L.S. -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 1.25 Sft

Blacksmith 0.03 No P. Day -


Cooly 0.03 No P. Day -
Mason 0.03 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per Sf Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 32
DESCRIPTION OF ITEM NO 19:

Providing and fixing 1/16" (1.5mm) thick lead


flashing over roof expansion joint complete in all
respects.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 100 Sft
Material

Lead flashing 1/16" thick 100.00 Sft Sft -


Nails (Copper) etc. 1.00 Kg. P. Kg. -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Driller 1.00 No P. Day -


Helper 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per Sf Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 33
DESCRIPTION OF ITEM NO 20: Cast iron rain water down pipe fixed in position,
excluding heads and shoes, but including painting
and clamps, etc.

a) 4" (100mm) dia Cast Iron down pipe.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 6 Rft
Material

C.I. pipe 4" (100mm) dia 6.00 Rft P. Rft -


Hold fasts with bolts 1.00 No Each -
Cement mortar for fixing hold fast
Cement 0.07 Bag Bag -
Sand 0.58 Cft % Cft. -
Pig lead 0.5Lbs(0 .23) Kg P. Kg -
Paint 0.05 Gln P. Gln -

Total -
Contractor's Profit & Ove 20 Percent -
Total -
Rate per Rft 0.00
6 -

Labour

Unskilled Cooly 0.20 No P. Day -


Mason 0.20 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per Rf Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 34
Item No. 20 Cast iron rain water down pipe fixed in position,
excluding heads and shoes, but including painting
and clamps, etc.

b) 3" (75mm) dia Cast Iron down pipe.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 6 Rft
Material

C.I. pipe down 3" (75mm) dia 6.00 Rft P. Rft -


Hold fasts with bolts 1.00 No Each -
Cement mortar for fixing hold fast
Cement 0.048 Bag Bag -
Sand 0.39 Cft % Cft. -
Pig lead 0.5Lbs(0 .23) Kg P. Kg -
Paint 0.03 Gln P. Gln -

Total -
Contractor's Profit & Ove 20 Percent -
Total -
Rate for One Reft 0.00
6 -
Labour

Cooly 0.20 No P. Day -


Mason 0.20 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per Rf Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 35
DESCRIPTION OF ITEM NO 21: Rain water down pipe cast iron heads fixed in
place, including cost of clamp, holdfast, and
painting.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

C.I. Heads 4" 1.00 No Each -


Clamps with hold fasts etc. 1.00 No Each -
Cement 0.05 Bag Bag -
Sand 0.29 Cft % Cft. -
Pig lead 0.5Lbs(0 .23) Kg P. Kg -
Paint 0.01 Gln P. Gln -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Cooly 0.09 No P. Day -


Mason 0.09 No P. Day -
Pipe fitter 0.09 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. Say -

Composite Rate for E Rs. Say -

Page 36
DESCRIPTION OF ITEM NO 22: Shoes bends or offsets for cast iron rain water
down pipe including fixing and painting.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

C.I. shoes bend or offsets 4" 1.00 No Each -


Pig lead 0.5Lbs ( 0.23)Kg P. Kg -
Paint 0.01 Gln P. Gln -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Pipe fitter 0.05 No P. Day -


Cooly 0.05 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. Say -

Composite Rate for E Rs. Say -

Page 37
DESCRIPTION OF ITEM NO 23: Plain G.I. sheet iron spouts fixed in position,
including painting.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

G.I. sheets 22 gauge length 28" (712mm)


and width 6" (150mm)
28 x 6 = 1.17 Sft 1.28Lbs ( 0.68)Kg P. Kg -
12 x 12
Cost of cement mortor for fixing
Cement 0.048 Bag Bag -
Sand 0.39 Cft % Cft. -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Cooly 0.10 No P. Day -


Mason 0.10 No P. Day -
Blacksmith 0.10 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. Say -

Composite Rate for E Rs. Say -

Page 38
DESCRIPTION OF ITEM NO 24: Laying " (12mm) thick deodar ceiling complete
(including sawing planing and fixing)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 100 Sft
Material

Deodar wood 5.00 Cft P. Cft -


Screw 11/2" long 4.50 Doz Doz -
Nails of sorts 1.6488Sr (1. 64) Kg P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Unskillied Cooly 3.00 Nos P. Day -


Carpenter 4.00 Nos P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 39
DESCRIPTION OF ITEM NO 25: Flat sheet roof with galvanized iron sheets
including battens, rolls, screw, clips etc. (planking
to be paid for separately).

a) 22 B. W. G. Sheets Roofing.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 400 Sft

Material

a) 22 B.W.G. sheet of size 6'x4' (1.8x1.20


M) in 400 sft (40 Sm) area including over
lapping and wastage 25% for 100 sft
5.85/4 = 1.46 cwt .
Wastage 25% (400+25%) 500 Sft
@ 1.12 Lbs/Sft 5.85Cwt(29 7.20)Kg P. Kg -
Rolls 5" (0.125m) wide 16' (4.86 M)
long or 7 Nos (27 .08) Sft P. Kg -
16x5x7/12 = 0.54/4 = 0.14
Deodar wood for battens 2"x1" size 7

Nos of 16' length = 7x16x1/6x1/8. 2.33 Cft


Add. 23% wastage 0.58 Cft
2.91 Cft P. Cft -

Bolts, nuts 1.00 Kg. P. Kg. -


Limpet Washer 4.00 Doz. Doz. -
U.I. Clips 1.29 Kg. Per Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Rate for 100 Sft 0.00 -


4

Page 40
Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour
Rate Analysis for 500 Sft
Cooly 12.00 Nos P. Day -
Carpenter 1.50 Nos P. Day -
Blacksmith 8.00 Nos P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Rate for 100 Sft -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 41
Item No. 25 Flat sheet roof with galvanized iron sheets
including battens rolls screw clips etc. (planking
to be psid for separately).
b) 24 B. W. G. Sheets Roofing.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 400 Sft
Material

b) 24 B.W.G. sheet roofing


24 B.W.G. sheeting 400 Sft
over laping 100 Sft
Wastage 25% 500 Sft

500 Sft @ 1.12 Lbs/Sft = 560 Lbs 254.08 Kg P. Kg -


Rolls = 47 Sft @ 1.12 = 52.64 Lbs 23.88 Kg P. Sft -
Deodar wood 2.90 Cft P. Cft -
Screws of size 3"&2" 1.60 Kg. P. Kg. -
Clips 1.29 Kg. P. Kg. -
Total -
Contractor's Profit & Ove 20 Percent -
Total -

Rate for 100 Sft 0.00 -


Labour 4
Rate Analysis for 500 Sft
Cooly 12.00 Nos P. Day -
Carpenter 1.50 No P. Day -
Blacksmith 8.00 Nos P. Day -
Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Rate for 100 Sft 0.00 -


5
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Composite Rate Per 10 Rs. Say -
Composite Rate Per Sq Rs. Say -

Page 42
DESCRIPTION OF ITEM NO 26: Asbestos cement corrugated sheet roofing
including necessary over laps and G.I. hooks,
bolts, nuts, screws washers and bitumen washers
etc. (excluding valleys and ridges etc.)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Corrugated A.C. sheets with 25% over


lapping and wastage. 125 Sft P. Sft -
G.I. or limpet washers and bilumatic
washers. 7 Doz Doz -
G.I. bolts with nuts. 2 Doz Doz -
G.I. hook bolts and nuts 6"x5/16" 1.5 Doz Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate for 150 Sft
Cooly 2.00 Nos P. Day -
Carpenter 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 43
DESCRIPTION OF ITEM NO 27: Extra labour for erection of G.I. sheets, flat sheet
or asbestos sheet roofing, above 20' height in
difficult position including lifting with care and
special scaffolding along live electric wires.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Rate Analysis for 150 Sft


Labour

Unskillied Cooly 0.50 No P. Day -


Fitter 0.06 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -

Labour Rate Per Sqm Rs. Say -

Page 44
DESCRIPTION OF ITEM NO 28: Fixing asbestos cement sheet ridges and valleys
" (6mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 61 Rft
Material

A.C. ridge sheet for a shed of 60'x30'


(18x15 M) or 61 Rft 61.00 Rft P. Rft -
G.I. bolts and nut with washers 5.00 Doz Doz -
Bituminous washer 5.00 Doz Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Rate Per Rft 0.00 -


61
Labour
Rate Analysis for 100 Rft
Cooly 2.00 Nos P. Day -
Carpenter 1.50 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per Rf Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 45
DESCRIPTION OF ITEM NO 29: Plain galvanized iron sheet ridging including
fixture, timber for ridge roll and ridge sheeting.

a) 6" (150mm) lap and 18" (450mm) over all of


22 gauge G.I. sheet ridging.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

G.I. Sheet 22 gauge 1.50 Sft


10% for over lapping 0.15 Sft
1.65 Sft
1.65 Sft @ 1.12 Lbs/Sft = 1.85 Lbs 0.84 Kg P. Kg -
Deodar wood 0.08 Cft P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Cooly 0.03 No P. Day -


Carpenter 0.03 No P. Day -
Blacksmith 0.03 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per Rf Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 46
Item No. 29 Plain galvanized iron sheet ridging including
fixture, timber for ridge roll and ridge sheeting.

b) 9" lap and 24" over all of 24 gauge G.I.


sheet ridging.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

G.I. Sheet 24 gauge 2.10 Sft


10% for over lapping 0.21 Sft
2.31 Sft
2.31 Sft @ 0.83 Lbs/Sft = 1.94 Lbs 0.88 Kg P. Kg -
Deodar wood 0.07 Cft P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Cooly 0.06 No P. Day -


Carpenter 0.03 No P. Day -
Blacksmith 0.03 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per Rf Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 47
Item No. 29 Plain galvanized iron sheet ridging including
fixture, timber for ridge roll and ridge sheeting.

c) 12" (300mm) lap and 30" (750mm) over all of


22 gauge G.I. sheet ridging.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

22 Gauge G.I. Sheet 2.50 Sft


Add 10% for over lapping 0.25 Sft
2.75 Sft
2.75 Sft @ 1.12 Lbs/Sft = 3.08 Lbs 1.40 Kg P. Kg -
Deodar wood 0.07 Cft P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Cooly 0.06 No P. Day -


Carpenter 0.03 No P. Day -
Blacksmith 0.03 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per Rf Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 48
DESCRIPTION OF ITEM NO 30: Plain 22 Gauge G.I. sheet gutter semi-circular
8" dia meter.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

G.I. Sheet (22 Guage) 1.38Lbs(0 .63) Kg P. Kg -


Wrought iron bracket complete with bolts,
Nuts and rivets etc. 1.00 No Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Cooly 0.03 No P. Day -


Blacksmith 0.03 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per Rf Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 49
DESCRIPTION OF ITEM NO 31: Making masonry ventilators in cement sand
mortar (1:4)

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material
Per
Pacca bricks 50.00 Nos 1000 N -
Cement 0.17 Bag P. Bag -
Sand 0.88 Cft P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate Analysis for 1.5 No.
Cooly 1.00 No P. Day -
Mason 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. Say -

Composite Rate for Ea Rs. Say -

Page 50
DESCRIPTION OF ITEM NO 32: Fixing water spouts or parnalas.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Rate Analysis for 1.25 No.


Labour

Unskilled Cooly 0.25 No -


Mason 0.25 No -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. Say -

Page 51
DESCRIPTION OF ITEM NO 33: Making drip course 2"x" (50x12mm) under
RCC Slab edges in outer opening, in cement, sand
mortar (1:2)

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 100 Rft
Material

Ready mortar 100 Rft


100x1/6x1/24 = 0.69 Cft Say 0.75 Cft
Cement 0.75 = 0.25 Cft 0.20 Bag P. Bag -
3
Sand 0.50 Cft P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Rate Per Rft 0.00 -


100
Labour
Rate Analysis for 150 Rft
Unskilled Cooly 1.00 No P. Day -
Mason 1.00 No P. Day -
Bahishti 0.03 No P. Day -

For Making Surface

Unskilled Cooly 0.13 No P. Day -


Bahishti 0.44 No P. Day -
Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Metre Rs. Say -
Composite Rate Per Rf Rs. Say -
Composite Rate Per Me Rs. Say -

Page 52
DESCRIPTION OF ITEM NO 34: Supplying and laying twin G.I. sheet 20 SWG
duly painted with bitumen with polythene film 300
gauge in between to provide a sliding joint under
the bearing of beams with 3" long 3/8" (10mm)
bar to act as hold fast on wall & beam.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

G.I. sheet 20 gauge 2'x1'= 2Sft @ 1.44Lbs 2.88Lbs(1 .31) Kg P. Kg -


Bitumen for paint 2.72Lbs(1 .23) Kg P. Kg -
Polythene film 300 gauge 0.05Lbs(0 .03) Kg P. Kg -
4 Nos x 3" (75mm) long 3/8" (10mm)
dia bar = 0.18 Rft 0.03 Kg P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour
Rate Analysis for 2 Sft
Cooly
placing in position 0.02 No P. Day -
Blacksmith for cutting of G.I. sheet 0.03 No P. Day -
Welding of bars 4 points 4.00 Nos P. Poi -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per Sf Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 53
DESCRIPTION OF ITEM NO 35: Providing and laying roof insulation, comprising of
single layer of tiles 9"x4"x1" (225 x 112.5 x
40mm) grouted with cement sand mortar 1:3 laid
over 2" thick earth (including Mud Plaster) over
thermopore sheet, over polythene sheet 300 gauge
over a layer of bitumen, complete in all respect.

i) Thermopore sheet " (13mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material
Per
Brick tiles 9"x4"x1" (225x112.5x40mm) 350.00 Nos 1000 N -
Sand 2.00 Cft P. Cft -
Cement 0.50 Bag P. Bag -
Bitumen 34Lbs(15 .43) Kg P. Kg -
Earth 20.00 Cft P. Cft -
Polythene 0.03" (0.08mm) including
wastage 5% 1.58Lbs(0 .72) Kg P. Kg -
Thermopore " (12mm) thick 1/c 5%
wastage 105.00 Sft P. Sft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Plasterer 0.13 No
Mason for laying 0.50 No
Mason for grouting 0.13 No
0.75 No P. Day -

Coolies for mud 0.50 No


for mud plaster 0.75 No
for tile laying grout 0.25 No
1.50 Nos P. Day -

Page 54
i) Thermopore sheet " (13mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Painter for painting 0.50 No P. Day -


Bahishti 0.50 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 55
Item No. 35 Providing and laying roof insulation, comprising of
single layer of tiles 9"x4"x1" (225 x 112.5 x
40mm) grouted with cement sand mortar 1:3 laid
over 2" thick earth (including Mud Plaster) over
thermopore sheet, over polythene sheet 300 gauge
over a layer of bitumen, complete in all respect.

ii) " (20mm) thick thermopore sheet.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material
Per
Clay tiles 9"x4"x1" (225x112.5x40mm) 350.00 Nos 1000 N -
Sand 2.00 Cft P. Cft -
Cement 0.50 Bag P. Bag -
Bitumen 34Lbs(15 .43) Kg P. Kg -
Earth 20.00 Cft P. Cft -
Polythene 0.03" (0.08mm) 1/c
wastage 5% 1.58Lbs(0 .72) Kg P. Kg -
Thermopore " (19mm) thick 1/c 5%
wastage 105.00 Sft P. Sft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Plasterer 0.13 No
Mason for laying 0.50 No
Mason for grouting 0.13 No
0.75 No P. Day -
0.75 Say

Coolies for mud 0.50 No


for mud plaster 0.75 No
for tile laying grout 0.25 No
1.50 Nos P. Day -

Page 56
ii) " (20mm) thick thermopore sheet.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Painter for painting 0.50 No P. Day -


Bahishti 0.50 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 57
Item No. 35 Providing and laying roof insulation, comprising of
single layer of tiles 9"x4"x1" (225 x 112.5 x
40mm) grouted with cement sand mortar 1:3 laid
over 2" thick earth (including Mud Plaster) over
thermopore sheet, over polythene sheet 300 gauge
over a layer of bitumen, complete in all respect.

iii) Thermopore sheet 1" (25mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material
Per
Brick tiles 9"x4"x1" (225x112.5x40mm) 350.00 Nos 1000 N -
Sand 2.00 Cft P. Cft -
Cement 0.50 Bag P. Bag -
Bitumen 34Lbs(15 .43) Kg P. Kg -
Earth 20.00 Cft P. Cft -
Polythene 0.03" (0.08mm) 1/c
wastage 5% 1.58Lbs(0 .72) Kg P. Kg -
Thermopore 1" (13mm) thick 1/c 5%
wastage 105.00 Sft P. Sft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Plasterer 0.13 No
Mason for laying 0.50 No
Mason for grouting 0.13 No
0.76 No P. Day -

Coolies for mud 0.50 No


for mud plaster 0.75 No
for tile laying grout 0.25 No
1.50 Nos P. Day -

Page 58
Item No. 35
iii) Thermopore sheet 1" (25mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Painter for painting 0.50 No P. Day -


Bahishti 0.50 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per 10 Rs. Say -


Composite Rate Per Sq Rs. Say -

Page 59
DESCRIPTION OF ITEM NO 36: Providing and fixing A.C. rain water down pipe
4" (100mm) dia with shoe, T-bend, clamp etc.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 13 Rft
Material

A.C. pipe 4" (100mm) dia 13.00 Rft P. Rft -


A.C. T-bend 4" (100mm) dia 1.00 No Each -
A.C. shoe 1.00 No Each -
Clamps & Nuts 2.00 Nos Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Rate Per Rft 0.00 -


13
Labour
Rate Analysis for 20 Rft
Plumber 0.20 No P. Day -
Unskilled Cooly 0.20 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per Rf Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 60
DESCRIPTION OF ITEM NO 37: Making jharries in existing brick masonry for
providing recesses for bearing of RCC roof slab
including repairing the damaged face.

i) For slab upto 6" (150mm) thick

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 40 Rft
Material

Cement for repairing Jharry 0.11 Bag Bag -


Sand 0.57 Cft. % Cft. -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Rate Per Rft 0.00 -


40
Labour
Rate Analysis for 50 Rft
Mason 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per Rf Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 61
Item No. 37 Making jharries in existing brick masonry for
providing recesses for hearing of RCC roof slab
including repairing the damaged face.

ii) For slab exceeding 6" (150mm) to 12" (300mm)


thick.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 40 Rft
Material

Cement 0.20 Bag Bag -


Sand 1.15 Cft. % Cft. -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Rate Per Rft 0.00 -


Labour 40
Rate Analysis for 50 Rft
Mason 1.50 No P. Day -
Cooly 0.25 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -

Composite Rate Per Rf Rs. Say -


Composite Rate Per Rm Rs. Say -

Page 62
DESCRIPTION OF ITEM NO 38: Making recess in exixting brick masonery for
bearing of beam, girder, R.S. joist, etc. including
repairing damaged face.

i) Upto 1'.0" (300mm) height of girder or beam.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 12 Holes
Material

Cement 0.111 Bag Bag -


Sand 0.57 Cft. % Cft. -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Mason 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. Say -

Composite Rate for Ea Rs. Say -

Page 63
Item No. 38 Making recess in exixting brick masonery for
bearing of beam, girder, R.S. joist, etc. including
repairing damaged face.

ii) For every 6" (150mm) additional height or part


thereof.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 25 Holes
Material

Cement 0.111 Bag Bag -


Sand 0.57 Cft. % Cft. -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Mason 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. Say -

Composite Rate for Ea Rs. Say -

Page 64
DESCRIPTION OF ITEM NO 39: Hoisting R.S. Beams and wooden beams and
placing in position.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Mason 0.20 No P. Day -


Unskilled Coolies 0.60 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates

Labour Rate for Each Rs. Rs. -

Page 65
DESCRIPTION OF ITEM NO 40: Hoisting and placing in position sahl ballies, over
roof.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 35 Nos

Labour

Mason 1.00 No P. Day -


Unskilled Coolies 1.00 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates

Labour Rate for Each Rs. Rs. -

Page 66
DESCRIPTION OF ITEM NO 41: Hoisting precast RCC/Pre-stressed concrete
battens and placing in position.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Mason 1.00 No P. Day -


Unskilled Coolies 3.00 Nos P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

a) 5' to 6' (1.5 to 1.8 M) long


Labour per No./ Assumed for 70 Nos 0.00 Say -
70
b) 6' to 7' (1.8 to 2.10 M) long
Labour per No./ Assumed for 50 Nos 0.00 Say -
50
c) 7' to 8' (2.10 to 2.40 M) long
Labour per No./ Assumed for 40 Nos 0.00 Say -
40
d) 8' to 9' (2.40 to 2.70 M) long
Labour per No./ Assumed for 30 Nos 0.00 Say -
30
e) Above 9' (2.70 M) length
Labour per No./ Assumed for 25 Nos 0.00 Say -
25

Page 67
DESCRIPTION OF ITEM NO 42: Hoisting and placing in position RC trough.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Mason 1.00 No P. Day -


Unskilled Coolies 3.00 Nos P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

a) Upto 10' (3 M) length


Labour per No./ Assumed for 25 Nos 0.00 Say -
25
b) 10' to 11' (3 to 3.30 M) length
Labour per No./ Assumed for 20 Nos 0.00 Say -
20
c) 11' to 12' (3.30 to 3.60 M) length
Labour per No./ Assumed for 15 Nos 0.00 Say -
15
d) 12' to 13' (3.60 to 3.90 M) length
Labour per No./ Assumed for 13 Nos 0.00 Say -
13
e) 13' to 14' (3.90 to 4.20 M) length
Labour per No./ Assumed for 12 Nos 0.00 Say -
12
f) 14' to 15' (4.20 to 4.50 M) length
Labour per No./ Assumed for 11 Nos 0.00 Say -
11
g) 15' to 16' (4.50 to 4.80 M) length
Labour per No./ Assumed for 10 Nos 0.00 Say -
10
h) 16' to 17' (4.80 to 5.1 M) length
Labour per No./ Assumed for 9 Nos 0.00 Say -
9

Page 68
Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

i) 17' to 18' (5.1 to 5.4 M) length


Labour per No./ Assumed for 7 Nos 0.00 Say -
7
j) 18' to 19' (5.4 to 5.7 M) length
Labour per No./ Assumed for 6.5 Nos 0.00 Say -
6.5
k) 19' to 20' (5.7 to 6 M) length
Labour per No./ Assumed for 6 Nos 0.00 Say -
6

Page 69
DESCRIPTION OF ITEM NO 43: Hoisting and placing in position RC inverted
battens.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Mason 1.00 No P. Day -


Unskilled Coolies 4.00 Nos P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

i) Upto 10' (3 M) Span


Labour per No./ Assumed for 40 Nos 0.00 Say -
40
i) From 10' to 12' (3 to 3.6 M) Span
Labour per No./ Assumed for 18 Nos 0.00 Say -
18
i) From 12' to 13' (3.6 to 3.9 M) Span
Labour per No./ Assumed for 15 Nos 0.00 Say -
15
v) From 13' to 14' (3.9 to 4.2 M) Span
Labour per No./ Assumed for 12 Nos 0.00 Say -
12
v) From 14' to 15' (4.2 to 4.5 M) Span
Labour per No./ Assumed for 11 Nos 0.00 Say -
11
i) From 15' to 16' (4.5 to 4.8 M) Span
Labour per No./ Assumed for 10 Nos 0.00 Say -
10
i) From 16' to 18' (4.8 to 5.4 M) Span
Labour per No./ Assumed for 8 Nos 0.00 Say -
8
i) From 18' to 20' (5.4 to 6 M) Span
Labour per No./ Assumed for 5 Nos 0.00 Say -
5

Page 70
DESCRIPTION OF ITEM NO 44: Reinforced cement concrete spout, including
fixing in position, with top & bottom khurras.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Cement 0.25 Bag P. Bag -


Sand 1.26 Cft P. Cft -
Aggregate 2.53 Cft P. Cft -

Total -

Total -

Contractor's Profit & Ove 20 Percent -


Total -

Labour for 1.5 Nos.

Mason 0.40 No P. Day -


Unskilled Coolies 0.40 No P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. Say -

Composite Rate for Ea Rs. Say -

Page 71
CHAPTER NO. 15

SHEET PILING
1 Unless otherwise stated, the rate includes handling of materials with in 3 chains (90M).
2 Rates for all finished works include the removal of surplus debris, unused material
and by products.
3 For handling of all types of materials for shortleads including carriage upto 3 Chains,
(90 M) nothing is to be paid as extra. Where handling and carriage involves an extra
lead beyond 3 Chains, (90 M) carriage for whole of the distance should be paid.

The above notes are to be referred to all items of the chapter.

DESCRIPTION OF ITEM NO 1: Cutting ransome and larson piles.

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 cut

Labour

Blacksmith 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total -

Item Rates

Labour Rate Per Cut Rs. 0.00 0.00 Say -


1.25

Page 1
DESCRIPTION OF ITEM NO 2: Cutting universal Piles.

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 cut

Labour

Blacksmith 0.37 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total -

Item Rates

Labour Rate Per Cut Rs. 0.00 0.00 Say -


1.25

Page 2
DESCRIPTION OF ITEM NO 3: Driving steel piles 25' to 30' (7.5 to 9 M).

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 125 Sft

Labour

Skilled Cooly 4.25 Nos 0.00 P. Day -


Unskilled Cooly 2.00 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total rate for 125 Sft -

Item Rates

Labour Rate Per 100 Sft Rs. 0.00 0.00 Say -


1.25

Labour Rate Per Sqm Rs. 0.00 Say -

Page 3
DESCRIPTION OF ITEM NO 4: Driving steel piles more than 15' (4.5 M) and
less than 25' (7.5 M).

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 125 Sft

Labour

Skilled Cooly 4.00 Nos 0.00 P. Day -


Unskilled Cooly 2.00 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total rate for 125 Sft -

Item Rates

Labour Rate Per 100 Sft Rs. 0.00 0.00 Say -


1.25
Labour Rate Per Sqm
Rs. 0.00 Say -

Page 4
DESCRIPTION OF ITEM NO 5: Driving steel piles 15' (4.5 M) and under.

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 125 Sft

Labour

Skilled Cooly 2.50 Nos 0.00 P. Day -


Unskilled Cooly 2.00 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total rate for 125 Sft -

Item Rates

Labour Rate Per 100 Sft Rs. 0.00 0.00 Say -


1.25
Labour Rate Per Sqm
Rs. 0.00 Say -

Page 5
DESCRIPTION OF ITEM NO 6: Dolleying piles.

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 No.

Labour

Dolly man (Skilled Cooly) 0.20 No 0.00 P. Day -


Unskilled Cooly 0.20 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total -

Item Rates

Labour Rate for Each Rs. 0.00 0.00 Say -


1.25

Page 6
DESCRIPTION OF ITEM NO 7: Drilling holes in piles by hand.

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 12 Holes

Labour

Blacksmith 0.33 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total -

Item Rates

Labour Rate for Each Rs. 0.00 0.00 Say -


12

Page 7
DESCRIPTION OF ITEM NO 8: Raising and lowering machine.

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.5 Feet

Labour

Fitter 1.00 No 0.00 P. Day -


Skilled Cooly 4.00 Nos 0.00 P. Day -
Unskilled Cooly 2.00 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total -

Item Rates

Labour Rate Per Foot Rs. 0.00 0.00 Say -


1.5

Labour Rate Per Rm Rs. 0.00 Say -

Page 8
DESCRIPTION OF ITEM NO 9: Turning machine 90.

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 Jobs

Labour

Fitter 1.00 No 0.00 P. Day -


Skilled Cooly 3.00 Nos 0.00 P. Day -
Unskilled Cooly 5.00 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total -

Item Rates

Labour Rate Per Job Rs. 0.00 0.00 Say -


1.25

Page 9
DESCRIPTION OF ITEM NO 10: Turning machine 135.

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 Jobs

Labour

Fitter 1.00 No 0.00 P. Day -


Skilled Cooly 5.00 Nos 0.00 P. Day -
Unskilled Cooly 5.00 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total -

Item Rates

Labour Rate Per Job Rs. 0.00 0.00 Say -


1.25

Page 10
DESCRIPTION OF ITEM NO 11: Turning machine 180.

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 Jobs

Labour

Fitter 1.00 No 0.00 P. Day -


Skilled Cooly 7.00 Nos 0.00 P. Day -
Unskilled Cooly 7.00 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total -

Item Rates

Labour Rate Per Job Rs. 0.00 0.00 Say -


1.25

Page 11
DESCRIPTION OF ITEM NO 12: Traveling machine (Light).

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 Chain

Labour

Fitter 1.25 Nos 0.00 P. Day -


Skilled Cooly 8.00 Nos 0.00 P. Day -
Unskilled Cooly 8.50 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total -

Item Rates

Labour Rate Per Chain Rs. 0.00 -0.05 Say -


1.25

Labour Rate Per 30 Meter Rs. -0.05 Say -

Page 12
DESCRIPTION OF ITEM NO 13: Loading and unloading piles.

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 Ton

Labour

Unskilled Cooly 0.37 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total -

Item Rates

Labour Rate Per Ton Rs. 0.00 0.00 Say -


1.25

Labour Rate Per Tonne Rs. -0.05 Say -

Page 13
DESCRIPTION OF ITEM NO 14: Dismantling piling machine.

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.5 No.

Labour

Foreman 3.00 Nos 0.00 P. Day -


Fitter 18.00 Nos 0.00 P. Day -
Skilled Cooly 12.00 Nos 0.00 P. Day -
Unskilled Cooly 9.50 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total -

Item Rates

Labour Rate for Each Rs. 0.00 0.00 Say -


1.5

Page 14
DESCRIPTION OF ITEM NO 15: Erecting pilling machine.

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.3 No.

Labour

Foreman 3.00 Nos 0.00 P. Day -


Fitter 18.00 Nos 0.00 P. Day -
Skilled Cooly 12.00 Nos 0.00 P. Day -
Unskilled Cooly 9.50 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total -

Item Rates

Labour Rate for Each Rs. 0.00 0.00 Say -


1.3

Page 15
DESCRIPTION OF ITEM NO 16: Carriage of pile machine under different
condition.

Detail Unit Rate (British System) per Cut

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 Chain

Labour

Fitter 1.00 No 0.00 P. Day -


Skilled Cooly 2.50 Nos 0.00 P. Day -
Unskilled Cooly 3.75 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ov 20 Percent -


Total -

Item Rates
Labour Rate Per Chain Rs. 0.00 0.00 Say -
1.25

Labour Rate Per 30 Meter Rs. 0.00 Say -

Page 16
CHAPTER NO. 22

SINKING OF WELLS
DESCRIPTION OF ITEM:

Item No. 1

Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within

A) In ordinary soil or sand.

i) from 0' (0 M) to 5' (1.5 M)

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 3.00 Nos


2 Coolies for lifting 4.43 Nos
Total 7.43 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 1
Item No. 1

Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).

A) In ordinary soil or sand.

ii) from 5'-1" (1-55 M) to 10' (3 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 3.00 Nos


2 Coolies for lifting 4.76 Nos
Total 7.76 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 2
Item No. 1

Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).

A) In ordinary soil or sand.

iii) from 10'-1" (3.05 M) to 15' (4.5M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 3.00 Nos


2 Coolies for lifting 5.73 Nos
Total 8.73 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 3
Item No. 1

Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).

A) In ordinary soil or sand.

iv) from 15'-1" (4.55 M) to 20' (6M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 3.00 Nos


2 Coolies for lifting 7.02 Nos
Total 10.02 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 4
Item No. 1

Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).

B) In Hard Soil.

i) from 0' (0 M) to 5' (1.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 4.00 Nos


2 Coolies for lifting 5.05 Nos
Total 9.05 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 5
Item No. 1

Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).

B) In Hard Soil.

ii) from 5'-1" (1.55 M) to 10' (3 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 4.00 Nos


2 Coolies for lifting 5.46 Nos
Total 9.46 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 6
Item No. 1

Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).

B) In Hard Soil.

iii) from 10'-1" (3.05 M) to 15' (4.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 4.00 Nos


2 Coolies for lifting 6.34 Nos
Total 10.34 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 7
Item No. 1

Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).

B) In Hard Soil.

iv) from 15'-1" (4.55 M) to 20' (6 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 4.00 Nos


2 Coolies for lifting 7.63 Nos
Total 11.63 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 8
Item No. 1

Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).

C) In Hard Strata such as Shingle, gravel etc.

i) from 0' (M) to 5' (1.5M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 4.00 Nos


2 Coolies for lifting 15.52 Nos
Total 19.52 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 9
Item No. 1

Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).

C) In Hard Strata such as Shingle, gravel etc.

ii) from 5'-1" (1.55 M) to 10' (3 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 4.00 Nos


2 Coolies for lifting 16.22 Nos
Total 20.22 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 10
Item No. 1

Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).

C) In Hard Strata such as Shingle, gravel etc.

iii) from 10'-1" (3.05 M) to 15' (4.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 4.00 Nos


2 Coolies for lifting 17.08 Nos
Total 21.08 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 11
Item No. 1

Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).

C) In Hard Strata such as Shingle, gravel etc.

iv) from 15'-1" (4.55 M) to 20' (6 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 4.00 Nos


2 Coolies for lifting 18.63 Nos
Total 22.63 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 12
DESCRIPTION OF ITEM :

Item No. 2

Dry sinking of well including loading and removing excavated material, within one chain (30 metre).

A) In ordinary soil.

i) from 10'-1" (3.05 M) to 15' (4.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 10.00 Nos


2 Coolies for lifting 30.00 Nos
Total 40.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 13
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

A) In ordinary soil.

ii) from 15'-1" (4.55 M) to 20' (6 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 10.00 Nos


2 Coolies for lifting 40.00 Nos
Total 50.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 14
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

A) In ordinary soil.

iii) from 20'-1" (6.05 M) to 25' (7.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 10.00 Nos


2 Coolies for lifting 50.00 Nos
Total 60.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 15
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

A) In ordinary soil.

iv) from 25'-1" (7.55 M) to 30' (9 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 10.00 Nos


2 Coolies for lifting 60.00 Nos
Total 70.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 16
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

A) In ordinary soil.

v) from 30'-1" (9.05 M) to 35' (10.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 10.00 Nos


2 Coolies for lifting 70.00 Nos
Total 80.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 17
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

A) In ordinary soil.

vi) from 35'-1" (10.55 M) to 40' (12 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 10.00 Nos


2 Coolies for lifting 80.00 Nos
Total 90.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 18
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

A) In ordinary soil.

vii) from 40'-1" (12.05 M) to 45' (13.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 10.00 Nos


2 Coolies for lifting 90.00 Nos
Total 100.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 19
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

A) In ordinary soil.

viii) from 45' (13.5 M) to any depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 10.00 Nos


2 Coolies for lifting 100.00 Nos
Total 110.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 20
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

B) In Hard Soil.

i) from 10' (3 M) to 15' (4.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 25.00 Nos


2 Coolies for lifting 30.00 Nos
Total 55.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 21
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

B) In Hard Soil.

ii) from 15'-1" (4.55) to 20' (6 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 25.00 Nos


2 Coolies for lifting 40.00 Nos
Total 65.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 22
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

B) In Hard Soil.

iii) from 20'-1" (6.05 M) to 25' (7.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 25.00 Nos


2 Coolies for lifting 50.00 Nos
Total 75.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 23
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

B) In Hard Soil.

iv) from 25'-1" (7.55 M) to 30' (9 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 25.00 Nos


2 Coolies for lifting 60.00 Nos
Total 85.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 24
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

B) In Hard Soil.

v) from 30'-1" (9.05 M) to 35' (10.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 25.00 Nos


2 Coolies for lifting 70.00 Nos
Total 95.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 25
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

B) In Hard Soil.

vi) from 35'-1" (10.55 M) to 40' (12 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 25.00 Nos


2 Coolies for lifting 80.00 Nos
Total 105.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 26
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

B) In Hard Soil.

vii) from 40'-1" (12.05 M) to 45' (13.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 25.00 Nos


2 Coolies for lifting 90.00 Nos
Total 115.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 27
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

B) In Hard Soil.

viii) from 45' (13.5 M) to any depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 25.00 Nos


2 Coolies for lifting 100.00 Nos
Total 125.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 28
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

C) In hard strata such as shingle, gravel etc.

i) from 10' (3 M) to 15' (4.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 40.00 Nos


2 Coolies for lifting 35.00 Nos
Total 75.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 29
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

C) In hard strata such as shingle, gravel etc.

ii) from 15'-1" (4.5 M) to 20' (6 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 40.00 Nos


2 Coolies for lifting 45.00 Nos
Total 85.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 30
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

C) In hard strata such as shingle, gravel etc.

iii) from 20'-1" (6.05 M) to 25' (7.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 40.00 Nos


2 Coolies for lifting 55.00 Nos
Total 95.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 31
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

C) In hard strata such as shingle gravel etc.

iv) from 25'-1" (7.55 M) to 30' (9 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 40.00 Nos


2 Coolies for lifting 65.00 Nos
Total 105.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 32
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

C) In hard strata such as shingle, gravel etc.

v) from 30'-1" (9.05 M) to 35' (10.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 40.00 Nos


2 Coolies for lifting 75.00 Nos
Total 115.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 33
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

C) In hard strata such as shingle, gravel etc.

vi) from 35'-1" (10.55 M) to 40' (12 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 40.00 Nos


2 Coolies for lifting 85.00 Nos
Total 125.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 34
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

C) In hard strata such as shingle, gravel etc.

vii) from 40'-1" (12.05 M) to 45' (13.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 40.00 Nos


2 Coolies for lifting 95.00 Nos
Total 135.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 35
Item No. 2

Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).

C) In hard strata such as shingle, gravel etc.

viii) from 45'-1" (13.55 M) to any depth

Detail Unit Rate (British System) per 1000 Cft


Rate
Qty Per Unit Amount

Rate Analysis for 1250 Cft.

LABOUR

1 Coolies for digging 40.00 Nos


2 Coolies for lifting 105.00 Nos
Total 145.00 Nos. - Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 1250 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 36
DESCRIPTION OF ITEM:

Item No. 3

Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 Metre).

i) from 0' (0 M) to 10' (3 M) depth

Detail Unit Rate (British System) per 1000 Cft

Rate
Qty Per Unit Amount

Rate Analysis for 90 Cft.

LABOUR

1 Divers 2.00 Nos - Per day -


2 Coolies 6.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 170 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. ####### Say 10621.65


Labour Rate per Cum Rs. 198.60 Say 198.60

Page 37
Item No. 3

Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).

ii) from 10' (3.05 M) to 20' 6 M) depth

Detail Unit Rate (British System) per 1000 Cft

Rate
Qty Per Unit Amount

Rate Analysis for 80 Cft.

LABOUR

1 Divers 2.00 Nos - Per day -


2 Coolies 6.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 80 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 38
Item No. 3

Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).

iii) from 20' (6.05 M) to 30' (9 M) depth

Detail Unit Rate (British System) per 1000 Cft

Rate
Qty Per Unit Amount

Rate Analysis for 65 Cft.


3
LABOUR

1 Divers 2.00 Nos - Per day -


2 Coolies 6.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 65 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 39
Item No. 3

Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).

iv) from 30' (9.05 M) to 40' (12 M) depth

Detail Unit Rate (British System) per 1000 Cft

Rate
Qty Per Unit Amount

Rate Analysis for 50 Cft.

LABOUR

1 Divers 2.00 Nos - Per day -


2 Coolies 6.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 50 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 40
Item No. 3

Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).

v) from 40' (12.05 M) to 50' (15 M) depth

Detail Unit Rate (British System) per 1000 Cft

Rate
Qty Per Unit Amount

Rate Analysis for 45 Cft.

LABOUR

1 Divers 2.00 Nos - Per day -


2 Coolies 6.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 45 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 41
Item No. 3

Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).

vi) from 50' (15.05 M) to 60' (18 M) depth

Detail Unit Rate (British System) per 1000 Cft

Rate
Qty Per Unit Amount

Rate Analysis for 40 Cft.

LABOUR

1 Divers 2.00 Nos - Per day -


2 Coolies 6.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 40 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 42
Item No. 3

Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).

vii) from 60' (18.05 M) to 70' (21 M) depth

Detail Unit Rate (British System) per 1000 Cft

Rate
Qty Per Unit Amount

Rate Analysis for 39 Cft.

LABOUR

1 Divers 2.00 Nos - Per day -


2 Coolies 6.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 39 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 43
Item No. 3

Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).

viii) from 70' (21.05 M) to 80' (24 M) depth

Detail Unit Rate (British System) per 1000 Cft

Rate
Qty Per Unit Amount

Rate Analysis for 38 Cft.

LABOUR

1 Divers 2.00 Nos - Per day -


2 Coolies 6.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 38 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 44
Item No. 3

Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).

ix) above 80' (24 M) to any depth

Detail Unit Rate (British System) per 1000 Cft

Rate
Qty Per Unit Amount

Rate Analysis for 35 Cft.

LABOUR

1 Divers 2.00 Nos - Per day -


2 Coolies 6.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 35 Cft. -

ITEM RATE

Labour Rate per 1000 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00

Page 45
DESCRIPTION OF ITEM

Item No. 4

Wet Sinking of Well in cohesive soil (value of C more than 5) for depth below spring level including charges of
machinery, shoring, kentledge and removal of excavated soil within one chain (30 Metre).

Detail Unit Rate (British System) per 1000 Cft

Rate
Qty Per Unit Amount

A. Material (T&P for wet sinking)

1 Winch including cost of tripod, 1.00 No. - Per No. -


tackle etc.
Less Residual Value 25% -
Net Total -

2 3/4" dia steel rope 350.00 Rft. - Per Rft. -

3 Loading gunny bags for one side 100.00 Nos. - er 100 Nos -

4 Sleepers / planks
Cost of 15 Nos. sleeper @ Rs. 0.00
Each 0.00
Depriciation 1/6 = 0.00
Total 0.00

Take 50 time Use, rate per use = 0.00= 0.00


50

Rate Per Sleeper = 0.00 = 0.00 15.00 Nos. - Each -


15

5 Cotton waste 0.38 Kg. - P. Kg. -


Grease 0.40 Kg. - P. Kg. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Sinking in 10 years in term of Cft. ######### Cft.

Assume Cost for 350 Cft. 0.00 x 350 -


26,000

Page 46
B. Pumping for Dewatering

a) One cusic capacity set for dewatering


@ Rs. 60000.00 Each 2.00 Nos. - Each -
Residual Value 1/6 -
Total -

Life of pump - 5 years 40 x 40 = 1600 R


To be used on 40 wells of 40 Rft.
depth each
Per Rft. 0 = 0.00
1600
Maintenance Cost 1/5 =
0.00 + 0.00 = 0.00 -

Running Cost

b) Fuel etc. 1.137 Litre


Diesel Oil gallon/Hrs/Pump

Working 8 Hrs per day after every 3 days


2 x 1.137 x 10 x 8 = 60.64 -
3

c) CREW

Driver 2.00 Nos. - Each

Per Rft of Well 0.00 -


4
Sundries 10.00 Percent -
Total -

Total for a+b+c -


Contractor's Profit & Ove 20.00 Percent -
Total Cost (A+B) for machinery & equipment - + - = - -

Page 47
Item No. 4

Wet sinking of well in cohesive soil (value of C more than 5) for depth below spring level including charges of
machinery, shoring kentledge and removal of excavated soil within one chain (30 metre).

(1)

i) 0' (0 M) to 10' (3 M) depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 150 Cft.
Rate
Qty Per Unit Amount

Material and Equipment as -


per above details.

LABOUR 150

1 Driver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 150 Cft. - + - = -
Total Composite Rate Per 1000 Cft. 0.00 x 1000 -
150

ITEM RATE

Composite Rate per 1000 Cft Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 48
Item No. 4

1)
ii) 10' (3 M) to 20' (6 M) depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 120 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 120 Cft.

Material and Equipment as -


per above details. (4, i)

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 120 Cft. - + - = -
Total Composite Rate Per 1000 Cft. 0.00 x 1000 -
120

ITEM RATE

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 49
Item No. 4
(1)

iii) 20' (6 M) to 30' (9 M) depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 100 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 100 Cft.

Material and Equipment as -


per above details. (4, i)

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 100 Cft. - + - = -
Total Composite Rate Per 1000 Cft. 0.00 x 1000 -
100

ITEM RATE

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 50
Item No. 4

iv) 30' (9 M) to 40' (12 M) depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 75 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 75 Cft.

Material and Equipment as -


per above details. (4, i)

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 75 Cft. - + - = -
Total Composite Rate Per 1000 Cft. 0.00 x 1000 -
75

ITEM RATE

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 51
Item No. 4

v) 40' (12 M) to 50' (15 M) depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 65 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 65 Cft.

Material and Equipment as -


per above details. (4, i)

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 65 Cft. - + - = -
Total Composite Rate Per 1000 Cft. 0.00 x 1000 -
65

ITEM RATE

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 52
Item No. 4

vi) 50' (15 M) to 60' (18 M) depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 60 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 60 Cft.

Material and Equipment as -


per above details. (4, i)

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 60 Cft. - + - = -
Total Composite Rate Per 1000 Cft. 0.00 x 1000 -
60

ITEM RATE

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 53
Item No. 4

(1)

vii) 60' (18 M) to 70' (21 M) depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 55 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 55 Cft.

Material and Equipment as -


per above details. (4, i)

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 55 Cft. - + - = -
Total Composite Rate Per 1000 Cft. 0.00 x 1000 -
55
ITEM RATE

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 54
Item No. 4

viii) 70' (21 M) to 80' (24.5 M) depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 53 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 53 Cft.

Material and Equipment as -


per above details. (4, i)

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 53 Cft. - + - = -
Total Composite Rate Per 1000 Cft. 0.00 x 1000 -
53

ITEM RATE

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 55
Item No. 4

ix) 80' (24 M) - to any depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 50 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 50 Cft.

Material and Equipment as -


per above details. (4, i)

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 50 Cft. - + - = -
Total Composite Rate Per 1000 Cft. 0.00 x 1000 -
50

ITEM RATE

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 56
DETAIL OF SLEEPERS

Detail Unit Rate (British System) per Sleeper


Assuming for 15 No Sleeper
Rate
Qty Per Unit Amount

MATERIAL

Sleeper 15.00 Nos - Each -

Depreciation 1/6 -
-

Take 50 time use of 0.00 = -


Sleepers 50

Rate for 15 Nos. -

ITEM RATE

Rate for 1 Sleeper Rs. -

Page 57
DESCRIPTION OF ITEM:

Item No. 5

Wet sinking of well in shingle, or gravel etc. for depth below spring level, including charges of machinery, sho
removal of excavated spoil within one chain load.

Detail Unit Rate (British System) per 1000 Cft

Rate
Qty Per Unit Amount

A. Material (T&P for wet sinking)

1 Winch including cost of tripod, 1.00 No. - Per No. -


tackle etc.
Less Residual Value 25% -
Net Total -

2 3/4" dia steel rope 350.00 Rft. - Per Rft. -

3 Loading gunny bags for one side 100.00 Nos. - er 100 Nos -

4 Sleepers / planks
Cost of 15 Nos. sleeper @ Rs. 0.00
Each 0.00
Depriciation 1/6 = 0.00
Total 0.00

Take 50 time Use, rate per use = 0.00= 0.00


50

Rate Per Sleeper = 0.00 = 0.00 15.00 Nos. - Each -


15

5 Cotton waste 0.38 Kg. - P. Kg. -


Grease 0.40 Kg. - P. Kg. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Sinking in 10 years in term of Cft. ######### Cft.

Assume Cost for 350 Cft. 0.00 x 350 -


26000.00

B. Pumping for Dewatering

a) One cusic capacity set for dewatering


@ Rs. 60000.00 Each 2.00 Nos. - Each -
Residual Value 1/6 4.00
Total 4.00

Life of pump - 5 years 40 x 40 = 1600 R


To be used on 40 wells of 40 Rft.
depth each
Per Rft. 4 = 0.00
1600
Maintenance Cost 1/5 =
0.00 + 0.00 = 0.00 0.00

Running Cost

b) Fuel etc. 1.137 Litre


Diesel Oil gallon/Hrs/Pump

Working 8 Hrs per day after every 3 days


2 x 1.137 x 10 x 8 = 60.64 -
3

c) CREW

Driver 2.00 Nos. - Each

Rft of Well - -
4

Page 58
Sundries 10.00 Percent -
Total -

Total for a+b+c 0.00


Contractor's Profit & Ove 20.00 Percent 0.00
Total Cost (A+B) for machinery & equipment - + 0.00 = 0.00 0.00

Page 59
Item No. 5

Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain.

i) From 0' to 10' depth

Detail Unit Rate (British System) per 1000 Cft

Rate
Qty Per Unit Amount

Rate Analysis for 110 Cft.

Material and Equipment as -


per above details.

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 195 Cft. - + - = -
Labour Rate Per 1000 Cft. - x 1000 (0.02)
110

Labour Rate per 1000 Cft. Rs. (0.02) Say 0.00


Composite Rate per Cum Rs. (0.01) Say 0.00

Page 60
Item No. 5

Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain.

ii) Above 10' to 20' depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 90 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 90 Cft.

Material and Equipment as -


per above details. (5, i)

LABOUR

As per Item 4 (i) -


Total -
Total Labour Rate Per 90 Cft. - + - = -
Total Composite Rate Per 1000 Cft. - x 1000 -
90

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. (0.01) Say 0.00

Page 61
Item No. 5

Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain.

iii) 20' (6 M) to 30' (9 M) depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 75 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 75 Cft.

Material and Equipment as -


per above details. (5, i, ii)

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 75 Cft. - + - = -
Total Composite Rate Per 1000 Cft. - x 1000 -
75

ITEM RATE

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 62
Item No. 5

Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain.

iv) 30' (9 M) to 40' (12 M) depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 55 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 55 Cft.

Material and Equipment as -


per above details. (5, i, ii)

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 55 Cft. - + - = -
Total Composite Rate Per 1000 Cft. - x 1000 -
55

ITEM RATE

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 63
Item No. 5

Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain (30 metre).

v) 40' (12 M) to 50' (15 M) depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 50 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 50 Cft.

Material and Equipment as -


per above details. (5, i, ii)

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 50 Cft. - + - = -
Total Composite Rate Per 1000 Cft. - x 1000 -
50

ITEM RATE

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 64
Item No. 5

Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain (30 metre)

vi) 50' (15 M) to 60' (18 M) depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 45 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 45 Cft.

Material and Equipment as -


per above details. (5, i, ii)

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 45 Cft. - + - = -
Total Composite Rate Per 1000 Cft. - x 1000 -
45

ITEM RATE

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 65
Item No. 5

Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain (30 metre).

vii) 60' (18 M) to 70' (21 M) depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 43 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 43 Cft.

Material and Equipment as -


per above details. (5, i, ii)

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 43 Cft. - + - = -
Total Composite Rate Per 1000 Cft. - x 1000 -
43

ITEM RATE

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 66
Item No. 5

Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain (30 metre).

viii) 70' (21 M) to 80' (24 M) depth

Detail Unit Rate (British System) per 1000 Cft


Assuming for 42 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 42 Cft.

Material and Equipment as -


per above details. (5, i, ii)

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 42 Cft. - + - = -
Total Composite Rate Per 1000 Cft. - x 1000 -
42

ITEM RATE

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 67
Item No. 5

Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain (30 metre).

ix) 80' (24 M) - above

Detail Unit Rate (British System) per 1000 Cft


Assuming for 38 Cft.
Rate
Qty Per Unit Amount

Rate Analysis for 38 Cft.

Material and Equipment as -


per above details. (5, i, ii)

LABOUR

1 Diver 2.00 Nos - Per day -


2 Coolies 4.00 Nos - Per day -
3 Coolies skilled 1.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total Labour Rate Per 38 Cft. - + - = -
Total Composite Rate Per 1000 Cft. - x 1000 -
38

ITEM RATE

Composite Rate per 1000 Cft. Rs. - Say 0.00


Composite Rate per Cum Rs. - Say 0.00

Page 68
DESCRIPTION OF ITEM:
Item No. 6

Making and fixing in position Keekar wood well curb.

Detail Unit Rate (British System) per Cft


Assuming 2.36 Cft.
Rate
Qty Per Unit Amount

MATERIAL

Kikar Wood 1 x 12/3' x 1


/3' = 0.5 2.36 Cft - Per Cft. -
2 2
(1 /3 + ) x 1 /3' = 1.81 Cft.
= 2.36 Cft.
M.S. Round bar " (7x1.5 / 2.204 = 4.76 kg. 4.76 Kg - Per kg. -
Angle Iron (6"x6"x" = 20 Lbs / 9.07 Kg. 9.07 Kg. - Per Kg. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Material Rate Per Cft. Rs. -

LABOUR

1 Carpenter 1.00 No - Per day -


2 Cooly 1.00 No - Per day -
3 Black Smith 0.50 No - Per day -
4 Hammar Man 0.50 No - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 2.36 Cft. -

ITEM RATE

Labour Rate per Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. 0.15 Say 0.15
Composite Rate per Cft. Rs. - Say 0.00
Composite Rate per Cum Rs. 0.25 Say 0.25

Page 69
DESCRIPTION OF ITEM:
Item No. 7

LAYING WELL CURB IN POSITION ONLY

Detail Unit Rate (British System) per No.

Rate
Qty Per Unit Amount

LABOUR

1 Carpenter 0.40 No - Per day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

ITEM RATE

Labour Rate per Each Rs. - Say 0.00

Page 70
DESCRIPTION OF ITEM:
Item No. 8

MAKING AND LAYING RCC WELL

Providing making and laying RCC Well Curb in position, using coarse sand, including all kinds of
form, moulds, curing, shuttering, rendering and finishing the exposed surface, (including screening
and washing of aggregrate.

(a) Concrete Mix (1: 1: 3)

Detail Unit Rate (British System) per Cft


Assuming 100 Cft.
Rate
Qty Per Unit Amount

MATERIAL

1 Cement 22.50 Bags - Per Bag -


2 Sand (Lawrancepur) 42.00 Cft - Per Cft. -
3 Shingle (Bajri) 84.00 Cft - Per Cft. -
4 Bolts & Nuts 1.75 Kg. - Per Kg. -
5 Partal Wood for Template 1.20 Cft - Per Cft. -
6 Tar Coal 20 .00 Lbs (9.07 Kg. - Per Kg. -
7 Nails 0.25 Lbs (0.11 Kg.) - Per Kg. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR

1 Mason 6.00 Nos - Per day -


2 Carpenter 6.00 Nos - Per day -
3 Coolies 13.00 Nos - Per day -
4 Bahishties 3.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate -

ITEM RATE

Labour Rate per Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00
Composite Rate per Cft. Rs. - Say 0.00
Composite Rate per Cum Rs. - Say 0.00

Page 71
DESCRIPTION OF ITEM:
Item No. 8

MAKING AND LAYING RCC WELL

Providing making and laying RCC Well Curb in position, using coarse sand, including all kinds of
form, moulds, curing, shuttering, rendering and finishing the exposed surface, (including screening
and washing of aggregrate.

(b) Concrete Mix (1:2:4)

Detail Unit Rate (British System) per Cft


Assuming 100 Cft.
Rate
Qty Per Unit Amount

MATERIAL

1 Cement 17.60 Bags - Per Bag -


2 Sand (Lawrancepur) 44.00 Cft - Per Cft -
3 Shingle (Bajri) 88.00 Cft - Per Cft. -
4 Bolts & Nuts 1.75 Kg. - Per Cft. -
5 Partal Wood for Template 1/10th 1.20 Cft. - Per Kg. -
6 Tar Coal 20.00 Lbs (9.07 Kg.) - Per Kg. -
7 Nails 0.25 Lbs (0.11 Kg.) - Per Kg. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

LABOUR

1 Mason 6.00 Nos - Per day -


2 Carpenter 6.00 Nos - Per day -
3 Coolies 13.00 Nos - Per day -
4 Bahishties 3.00 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate -

ITEM RATE

Labour Rate per Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00
Composite Rate per Cft. Rs. - Say 0.00
Composite Rate per Cum Rs. - Say 0.00

Page 72
DESCRIPTION OF ITEM:
Item No. 9

FIXING STRUCTURAL STEEL

Providing and fixing structural steel for cutting edge.

Detail Unit Rate (British System) per 100 Kg.

Rate
Qty Per Unit Amount

MATERIAL FOR 50 KG.

1 L. Iron/ Steel 1.00 Cwt (50.08 Kg.)


Wastage 8% 04.01 Cwt.
Total 54.09 Kg. - Per Kg. -
Contractor's Profit & Ove 20.00 Percent -
Total for 50 Kg. -
Total for 100 Kg. -

LABOUR FOR 100 KG.

Fitter for fabrication of steel


and iron work 0.50 No - Per day -

1 Coolies 0.50 No - Per day -


for Joining ends
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate -

ITEM RATE

Labour Rate Per 100 Kg. Rs. - Say 0.00


Composite Rate per 100 Kg. Rs. - Say 0.00

Page 73
DESCRIPTION OF ITEM:
Item No. 10

MAKING AND REMOVING FALSE MASONRY

Making and removing false masonry on well.

Detail Unit Rate (British System) per 100 Cft

Rate
Qty Per Unit Amount

MATERIAL

Pacca Brick 1,350.00 Nos - er 0/00 Nos -


Cement 2.66 Bags - Per Bag -
Sand 26.67 Cft - er 100 Cft -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Cost of bricks (70% bricks at


depreciated value )
0
1350 x 65 = 950 Nos @ RS. 1000 /00 No 950.00
100
0
Cost of Brick bats 24 Cft @ Rs. 350 /0 Cft 84.00
Net Cost of Material 1,034.00 -
Total -

LABOUR FOR 150 CFT.

1 Masons 2.50 Nos - Per day -


2 Coolies 3.00 Nos - Per day -
4 Coolies 1.00 No - Per day -
5 Bahishti 0.50 No - Per day -
Coolies for demolishing 4.25 Nos - Per day -
Coolies for Scraping mortar of bricks 2.90 Nos - Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total Rate for 150 Cft. -
Total Rate for 100 Cft.

ITEM RATE

Labour Rate per 100 Cft. Rs. - Say 0.00


Labour Rate per Cum Rs. - Say 0.00
Composite Rate per 100 Cft. Rs. - Say 0.00
Composite Rate for Cum Rs. - Say 0.00

Page 74
CHAPTER NO. 8

STONE MASONRY
DESCRIPTION OF ITEM NO 1: Random, rubble masonry (uncoursed), in
foundation and plinth.
a) Dry Masonry

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Headers or through stones


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 2.00 Nos - Per Day -


Unskilled Coolies 3.00 Nos - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 1
Item No. 1 b) In Mud Mortar

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Headers or through stones


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -
Good earth 45 Cft - %Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 2.50 Nos - Per Day -


Unskilled Coolies 3.50 Nos - Per Day -
Bahishti 0.25 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 2
Item No. 1 c) In Lime Mortar, Ratio (1 Lime 2 Sand).

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or headers


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -
Lime Slaked (Ground) 224 Kg - Per Kg. -
Sand 30 Cft - Per %Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 4.00 Nos - Per Day -


Unskilled Coolies 5.00 Nos - Per Day -
Bahishti 0.50 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. (0.05) Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 3
Item No. 1 d) In Cement Sand Mortar
i) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or headers


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -
Cement 9 Bag - P. Bag -
Sand 33.75 Cft - Per %Cft 118.13

Total 118.13
Contractor's Profit & Ove ##### Percent 23.63
Total 141.75

Labour

Mason 4.00 Nos - Per Day -


Unskilled Coolies 5.00 Nos - Per Day -
Bahishti 0.50 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. (0.03) Say -

Composite Rate for 100 Cft Rs. 141.75 Say 141.75


Composite Rate P/ Cum Rs. 50.06 Say 50.05

Page 4
Item No. 1 d) In Cement Sand Mortar
ii) Ratio ( 1:4 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or headers


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -
Cement 7.20 Bag - Each -
Sand 36.0 Cft - Per % Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 4.00 Nos - Per Day -


Unskilled Coolies 5.00 Nos - Per Day -
Bahishti 0.50 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. (0.02) Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 5
Item No. 1 d) In Cement Sand Mortar
iii) Ratio ( 1:6 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or headers


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -
Cement 5.14 Bag - Each -
Sand 38.57 Cft - Per%Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 4.00 Nos - Per Day -


Unskilled Coolies 5.00 Nos - Per Day -
Bahishti 0.50 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. (0.02) Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. (0.05) Say -

Page 6
Item No. 1 d) In Cement Sand Mortar
iv) Ratio ( 1:8 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or headers


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -
Cement 4 Bag - Each -
Sand 40 Cft - Per%Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 4.00 Nos - Per Day -


Unskilled Coolies 5.00 Nos - Per Day -
Bahishti 0.50 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. (0.02) Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 7
DESCRIPTION OF ITEM NO 2: Coursed Rubble Masonry hammer dressed,
foundation and plinth.

a) Dry Masonry

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Headers or through stones


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 3.00 Nos - Per Day -


Unskilled Coolies 3.00 Nos - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 8
Item No. 2 b) In Mud Mortar

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Headers or through stones


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each 300.00
Good earth 45 Cft - Per% Cft -

Total 300.00
Contractor's Profit & Ove ##### Percent 60.00
Total 360.00

Labour

Mason 4.00 Nos - Per Day -


Unskilled Coolies 4.00 Nos - Per Day -
Bahishti 0.50 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. 360.00 Say 360.00


Composite Rate P/ Cum Rs. 127.13 Say 127.15

Page 9
Item No. 2 c) In Lime Sand Mortar. (Ratio 1:2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or headers 20 Nos - Each -


Lime Slaked (Ground) 5.33/ 199 Kg - Per Per Kg -
Sand 26.67 Cft - Per%Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 4.75 Nos - Per Day -


Unskilled Coolies 5.00 Nos - Per Day -
Bahishti 0.75 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. (0.01) Say -

Page 10
Item No. 2 d) In Cement Sand Mortar
i) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or bond stone


Note: Special size of stone for headers
average size = 35x1.5'x8"x10"
(457x200x250mm) 35 Nos. 35 Nos - Each -
Cement 8 Bag - Each -
Sand 30 Cft - Per%Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 4.75 Nos - Per Day -


Unskilled Coolies 5.00 Nos - Per Day -
Bahishti 0.75 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 11
Item No. 2 d) In Cement Sand Mortar
ii) Ratio ( 1:4 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone including wastage 100 Cft - Per % Cft -

Through Stone or bond stone


Note: Special size of stone for headers
average size = 35x1.5'x8"x10"
(450x200x250mm) 35 Nos. 35 Nos - Each -
Cement 6.40 Bag - Each -
Sand 32 Cft - Per%Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 4.75 Nos - Per Day -


Unskilled Coolies 5.00 Nos - Per Day -
Bahishti 0.75 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. 0.01 Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 12
Item No. 2 d) In Cement Sand Mortar
iii) Ratio ( 1:6 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or bond stone


Note: Special size of stone for headers
average size = 35x1.5'x8"x10"
(450x200x250mm) 35 Nos. 35 Nos - Each -
Cement 4.57 Bag - Each -
Sand 34.20 Cft - Per%Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 4.75 Nos - Per Day -


Unskilled Coolies 5.00 Nos - Per Day -
Bahishti 0.75 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 13
Item No. 2 d) In Cement Sand Mortar
iv) Ratio ( 1:8 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or bond stone


Note: Special size of stone for headers
average size = 35x1.5'x8"x10"
(457x200x250mm) 35 Nos. 35 Nos - Each -
Cement 3.56 Bag - Each -
Sand 35.60 Cft - Per%Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 4.75 Nos - Per Day -


Unskilled Coolies 5.00 Nos - Per Day -
Bahishti 0.75 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 14
DESCRIPTION OF ITEM NO 3: Random Rubble Masonry (uncoursed) in ground
floor or 20'(6 M) height,building/other than

a) Dry Masonry

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Headers or through stones


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 2.50 Nos - Per Day -


Unskilled Coolies 3.00 Nos - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 15
Item No. 3 b) In Mud Mortar

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Headers or through stones


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -
Good earth 45 Cft - Per % Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 3.00 Nos - Per Day -


Unskilled Coolies 4.00 Nos - Per Day -
Bahishti 0.50 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. 0.01 Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 16
Item No. 3 c) In Lime Sand Mortar. (Ratio 1:2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or headers


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -
Lime Slaked (Ground) 224 Kg - Per Per Kg -
Sand 30 Cft - Per % Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 4.50 Nos - Per Day -


Unskilled Coolies 5.00 Nos - Per Day -
Bahishti 0.75 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 17
Item No. 3 d) In Cement Sand Mortar
i) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or headers


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -
Cement 9 Bag - Each -
Sand 33.75 Cft - Per % Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 4.50 Nos - Per Day -


Unskilled Coolies 5.00 Nos - Per Day -
Bahishti 0.75 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. 1.20 Say 1.20

Page 18
Item No. 3 d) In Cement Sand Mortar
ii) Ratio ( 1:4 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or bond stone


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -
Cement 7.2 Bag - Each -
Sand 36 Cft - Per % Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 4.50 Nos - Per Day -


Unskilled Coolies 5 Nos - Per Day -
Bahishti 0.75 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 19
Item No. 3 d) In Cement Sand Mortar
iii) Ratio ( 1:6 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100.00 Cft - Per % Cft -

Through Stone or bond stone


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -
Cement 5.14 Bag - Each -
Sand 38.57 Cft - Per % Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 4.50 Nos - Per Day -


Unskilled Coolies 5.00 Nos - Per Day -
Bahishti 0.75 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. 0.01 Say -


Composite Rate P/ Cum Rs. 0.00 Say -

Page 20
Item No. 3 d) In Cement Sand Mortar
iv) Ratio ( 1:8 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or bond stone


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250) 20 Nos. 20 Nos - Each -
Cement 4 Bag - Each -
Sand 40 Cft - Per % Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 4.50 Nos - Per Day -


Unskilled Coolies 5.00 Nos - Per Day -
Bahishti 0.75 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 21
DESCRIPTION OF ITEM NO 4: Coursed Rubble Masonry hammer dressed in
ground floor or 20' (6 M) height, building o
than building.

a) Dry Masonry

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Headers or through stones


Note: Special size of stone for headers
average size = 20x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 3.50 Nos - Per Day -


Unskilled Coolies 3.50 Nos - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. 0.01 Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 22
Item No. 4 b) In Mud Mortar

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Headers or through stones


Note: Special size of stone for headers
average size = 30x1.5'x8"x10"
(457x200x250mm) 20 Nos. 20 Nos - Each -
Good earth 43 Cft - Per % Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 5.00 Nos - Per Day -


Unskilled Coolies 5.00 Nos - Per Day -
Bahishti 0.50 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. 0.01 Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 23
Item No. 4 c) In Lime Sand Mortar. (Ratio 1:2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone including wastage 100 Cft - Per % Cft -

Through Stone or headers 20 Nos - Each -


Lime Slaked (Ground) 5.33 Mds(19 9)Kg - Per Per Kg -
Sand 26.67 Cft - Per % Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 5.50 Nos - Per Day -


Unskilled Coolies 5.50 Nos - Per Day -
Bahishti 0.75 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. 0.01 Say -


Composite Rate P/ Cum Rs. (0.00) Say -

Page 24
Item No. 4 d) In Cement Sand Mortar
i) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or headers


Note: Special size of stone for headers
average size = 35x1.5'x8"x10"
(457x200x250) 35 Nos. 35 Nos - Each -
Cement 8 Bag - Each -
Sand 30 Cft - Per % Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 5.50 Nos - Per Day -


Unskilled Coolies 5.50 Nos - Per Day -
Bahishti 0.75 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 25
Item No. 4 d) In Cement Sand Mortar
ii) Ratio ( 1:4 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or bond stone


Note: Special size of stone for headers
average size = 35x1.5'x8"x10"
(457x200x250mm) 35 Nos. 35 Nos - Each -
Cement 6 Bag - Each -
Sand 32 Cft - Per % Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 5.50 Nos - Per Day -


Unskilled Coolies 5.50 Nos - Per Day -
Bahishti 0.75 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 26
Item No. 4 d) In Cement Sand Mortar
iii) Ratio ( 1:6 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or bond stone


Note: Special size of stone for headers
average size = 35x1.5'x8"x10"
(457x200x250mm) 35 Nos. 35 Nos - Each -
Cement 4.57 Bag - Each -
Sand 34.20 Cft - Per % Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 5.50 Nos - Per Day -


Unskilled Coolies 5.50 Nos - Per Day -
Bahishti 0.75 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 27
Item No. 4 d) In Cement Sand Mortar
iv) Ratio ( 1:8 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft - Per % Cft -

Through Stone or bond stone


Note: Special size of stone for headers
average size = 35x1.5'x8"x10"
(457x200x250mm) 35 Nos. 35 Nos - Each -
Cement 3.56 Bag - Each -
Sand 35.60 Cft - Per % Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 5.50 Nos - Per Day -


Unskilled Coolies 5.50 Nos - Per Day -
Bahishti 0.75 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 28
DESCRIPTION OF ITEM NO 5: Ashlar block in course or scabbled masonry
(including dressing etc.) in ground floor or
(6 M) height, Building other than building.
a) In Lime Sand. (Ratio 1:2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 200 Cft - Per % Cft -


Lime Slaked (Ground) 4Md (149.30 Kg) - Per Kg. -
Sand 20 Cft - Cft -
Charcoal 30Lb (13.61 Kg) - Per Kg. -
Steel 3.3Lb (1.50 Kg) - Per Kg. -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 17.00 Nos - Per Day -


Unskilled Coolies 10.00 Nos - Per Day -
Bahishti 1.00 No - Per Day -
Blacksmith 1.00 No - Per Day -
Bellow-man 1.00 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. (0.01) Say -

Page 29
Item No. 5 b) In Cement Sand Mortar
i) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 200 Cft - Per % Cft -


Cement 6 Bag - Each -
Sand 22.50 Cft - Cft -
Charcoal 30Lb (13.61 Kg) - Per Kg. -
Steel 3.3Lb (1.50 Kg) - Per Kg. -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 17.00 Nos - Per Day -


Unskilled Coolies 10.00 Nos - Per Day -
Bahishti 1.00 No - Per Day -
Blacksmith 1.00 No - Per Day -
Bellow-man 1.00 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. 0.01 Say -

Page 30
Item No. 5 b) In Cement Sand Mortar
ii) Ratio ( 1:4 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 200 Cft - Per % Cft -


Cement 4.80 Bag - Each -
Sand 24 Cft - % Cft -
Charcoal 30Lb (13.61 Kg) - Per Per Kg -
Steel 3.3Lb (1.50 Kg) - Per Per Kg -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 17.00 Nos - Per Day -


Unskilled Coolies 10.00 Nos - Per Day -
Bahishti 1.00 No - Per Day -
Blacksmith 1.00 No - Per Day -
Bellow-man 1.00 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 31
Item No. 5 b) In Cement Sand Mortar
iii) Ratio ( 1:6 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 200 Cft - Per % Cft -


Cement 3.44 Bag - Each -
Sand 25.70 Cft - Cft -
Charcoal 30Lb (13.61 Kg) - Per Per Kg -
Steel 3.3Lb (1.50 Kg) - Per Per Kg -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 17.00 Nos - Per Day -


Unskilled Coolies 10.00 Nos - Per Day -
Bahishti 1.00 No - Per Day -
Blacksmith 1.00 No - Per Day -
Bellow-man 1.00 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 32
DESCRIPTION OF ITEM NO 6: Ashlar fine masonry (including dressing etc.
ground floor or 20' (6 M) height, Building o
than building.
a) In Lime Sand Mortar. (Ratio 1:2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 250 Cft - Per % Cft -


Lime Slaked (Ground) 2Md (74.65 Kg) - Per Per Kg -
Sand 10 Cft - Cft -
Charcoal 0.73Md(27.2 5)Kg - Per Per Kg -
Steel 4Lb (1.82 Kg) - Per Per Kg -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 40.00 Nos - Per Day -


Unskilled Coolies 8.00 Nos - Per Day -
Bahishti 1.00 No - Per Day -
Blacksmith 1.50 No - Per Day -
Bellow-man 1.50 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate Per 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate Per 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 33
Item No. 6 b) In Cement Sand Mortar
i) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 250 Cft - Per % Cft -


Cement 3 Bag - Each -
Sand 11.25 Cft - Per % Cft -
Charcoal 0.73Md (27.25 Kg) - Per Per Kg -
Steel 4Lb (1.82 Kg) - Per Per Kg -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 40.00 Nos - Per Day -


Unskilled Coolies 8.00 Nos - Per Day -
Bahishti 1.00 No - Per Day -
Blacksmith 1.50 No - Per Day -
Bellow-man 1.50 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. 0.01 Say -


Composite Rate P/ Cum Rs. 0.00 Say -

Page 34
Item No. 6 b) In Cement Sand Mortar
ii) Ratio 1:4

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 250 Cft - Per % Cft -


Cement 2.40 Bag - Each -
Sand 12 Cft - Per % Cft -
Charcoal 60Lb (27.22 Kg) - Per Per Kg -
Steel 4Lb (1.82 Kg) - Per Per Kg -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 40.00 Nos - Per Day -


Unskilled Coolies 8.00 Nos - Per Day -
Bahishti 1.00 No - Per Day -
Blacksmith 1.50 No - Per Day -
Bellow-man 1.50 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. - Say -

Page 35
Item No. 6 b) In Cement Sand Mortar
iii) Ratio 1:6

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 250 Cft - Per % Cft -


Cement 1.73 Bag - Each -
Sand 13 Cft - Per % Cft -
Charcoal 60Lb (27.22 Kg) - Per Per Kg -
Steel 4Lb (1.82 Kg) - Per Per Kg -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 40.00 Nos - Per Day -


Unskilled Coolies 8.00 Nos - Per Day -
Bahishti 1.00 No - Per Day -
Blacksmith 1.50 No - Per Day -
Bellow-man 1.50 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. - Say -


Labour Rate P/ Cum Rs. - Say -

Composite Rate for 100 Cft Rs. - Say -


Composite Rate P/ Cum Rs. 0.01 Say -

Page 36
DESCRIPTION OF ITEM NO 7: Extra labour on items 3,4,5 and 6 for work i

i) First Floor

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Labour for 125 Cft.

Mason 0.40 No - Per Day -


Unskilled Coolies 1.35 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate for 100 Cft Rs. 0.01 Say -

Labour Rate P/ Cum Rs. 0.00 Say -

Page 37
tem No. 7 ii) Second Floor

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Labour for 125 Cft.

Mason 1.20 No - Per Day -


Unskilled Coolies 2.60 Nos - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total for 125 Cft. -
Rate for 100 Cft. -

Labour Rate for 100 Cft Rs. - Say -

Labour Rate P/ Cum Rs. - Say -

Page 38
Item No. 7 iii) Third Floor

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Labour for 125 Cft.

Mason 2 Nos - Per Day -


Unskilled Coolies 3.90 Nos - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total for 125 Cft. -
Rate for 100 Cft. -

Labour Rate for 100 Cft Rs. - Say -

Labour Rate P/ Cum Rs. - Say -

Page 39
Item No. 7 iv) Fourth Floor

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Labour for 125 Cft.

Mason 3.60 Nos - Per Day -


Unskilled Coolies 5.60 Nos - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total for 125 Cft. -
Rate for 100 Cft. -

Labour Rate for 100 Cft Rs. - Say -

Labour Rate P/ Cum Rs. - Say -

Page 40
DESCRIPTION OF ITEM NO 8: Extra labour on items 3,4,5 and 6 above for
5ft (1.5 M) additional height building other
building part thereof.

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Labour for 125 Cft.

Mason 0.50 No - Per Day -


Unskilled Coolies 1 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Totalfor 125 Cft. -
Rate for 100 Cft. -

Labour Rate for 100 Cft Rs. - Say -

Labour Rate P/ Cum Rs. - Say -

Page 41
DESCRIPTION OF ITEM NO 9: Extra labour for arch work in stone masonry
including centering and de-centering, etc.

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Semi circular opening 15'x1.5'x1.5' = 33.8 Cft


Kikar wood = 3.75 Cft to be used for
60 times 3.75/60 = 0.06 Cft 0.06 Cft - Per Cft -
Earth 2.00 Cft - % Cft -

-
Contractor's Profit & Ove ##### Percent -
Total for 33.8 Cft -
Total for 100 Cft 19.8 x 100 -
33.8
Labour

Mason 1.50 Nos - Per Day -


Unskilled Coolies 1.50 Nos - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -
Total (i+ii)

Labour Rate for 100 Cft Rs. - Say -

Labour Rate P/ Cum Rs. - Say -

Page 42
DESCRIPTION OF ITEM NO 10: Extra labour for :-

a) Coping and caps etc

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material for 125 Cft.

Stone 12" (300mm) and above 30 Cft - Per % Cft -


Steel 0.75Lb (0.34 Kg) - Per Kg. -
Charcoal 10Lb (4.54 Kg) - Per Kg. -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 18.00 Nos - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total for 125 Cft. -
Rate for 100 Cft. -

Extra Rate Per 100 Cft Rs. - Say -

Extra Rate P/ Cum Rs. - Say -

Page 43
tem No. 10 b) Cornice and string course

Detail Unit Rate (British System) per 100 Rft

Qty Rate
Per Unit (Rs) Amount (Rs)

Labour for 125 Rft

Mason 18 Nos - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total for 125 Rft -
Rate for 100 Rft -

Labour Rate for 100 Rft Rs. - Say -

Labour Rate P/ LM. Rs. - Say -

Page 44
DESCRIPTION OF ITEM NO 11: Dressing Stones

a) Hammer Dressed

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Labour for 125 Sft

Mason 5 Nos - Per Day -


Unskilled Coolies 2.50 Nos - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total for 125 Sft -
Rate for 100 Sft. -

Labour Rate for 100 Sft Rs. - Say -

Labour Rate P/ Sq.m Rs. - Say -

Page 45
tem No. 11 b) Rough tooled dressed

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Labour for 125 Sft

Mason 10 Nos - Per Day -


Unskilled Coolies 4 Nos - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total for 125 Sft -
Rate for 100 Sft -

Labour Rate for 100 Sft Rs. - Say -


Labour Rate P/ Sq.m Rs. - Say -

Page 46
tem No. 11 c) Chisel dressed

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Labour for 125 Sft

Mason 12 Nos - Per Day -


Unskilled Coolies 5 Nos - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total for 125 Sft -
Rate for 100 Sft -

Labour Rate for 100 Sft Rs. - Say -

Labour Rate P/ Sq.m Rs. - Say -

Page 47
tem No. 11 d) Fine dressed

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Labour for 125 Sft

Mason 28 Nos - Per Day -


Unskilled Coolies 5 Nos - Per Day -
Blacksmith 1 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total for 125 Sft -
Rate for 100 Sft -

Labour Rate for 100 Sft Rs. - Say -


Labour Rate P/ Sq.m Rs. - Say -

Page 48
DESCRIPTION OF ITEM NO 12: Dhajji walling 5"x5" (125x125mm) thick
deodar framing with stone laid in 1:6 cement
sand mortar and (1:4) cement sand plaster on
both sides.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 234 Sft

a) Detail of Wood
i)Top bottom
2x18'x5x5 = 6.25 Cft
12x12
iiVertical post 4" (100mm) apart
6x13'x5/12x5/12 = 13.55 Cft
iii) Horizontal Pieces
3x18'x5/12x = 5.62 Cft
iv) Diagonl Strutts
20x6x5/12x1/6 = 6.25 Cft
31.67 Cft
Wastage 20% = 6.33
38.00 Cft
This wood can be used 10 time hence
wood for our operation would be = 38/10 3.80 Cft

b) Stone (Quarried)
1x18x13x5/12 = 98.00 Cft
Deduct Scantling = 32.00 Cft
66.00 Cft
Therefore stone required = 66 x 2 112 Cft

Material

Wood as above 2nd Class 3.80 Cft - Cft -


Spikes " (20mm) 0.333 Kg. - Per Kg. -
Wire nail 4" (100mm) 0.333 Kg. - Per Kg. -
Wood preservative 0.304 Ltr - Per Litre -
Stone quarried 112.00 Cft - Per % Cft -
Cement for 1:6 ratio for laying 3.00 Bag - Per Bag -
Cement for plastering " thick both
side (1:4) 3.40 Bag - Per Bag -

Page 49
Item No. 12

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Sand 40 Cft - % Cft -


Steel 3Lb (1.36 Kg) - Per Kg. -
Coal 0.5Md (18.66 Kg) - Per Kg. -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Carpenters for wood work 4.00 Nos - Per Day -


UnsKilled Coolies 2.00 Nos - Per Day -
Masons for dressing of stones including
laying 10.00 Nos - Per Day -
Unskilled Coolies for laying 5.00 Nos - Per Day -
Masson for plaster 3.00 Nos - Per Day -
Unskilled Coolies 3.00 Nos - Per Day -
Blacksmith 0.50 No - Per Day -
Bellow-man 0.50 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total for 234 Sft -
Rate for 100 Sft -

Labour Rate for 100 Sft Rs. - Say -


Labour Rate P/ Sqm Rs. - Say -

Composite Rate for 100 Sft Rs. - Say -


Composite Rate P/ Sqm Rs. - Say -

Page 50
DESCRIPTION OF ITEM NO 13: Providing and fixing stone blocks from 2 Cft
Cft (0.06 to 017 M) each, including lift up
20' (6 M).

Detail Unit Rate (British System) per Cft

Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 4 Cft

Material

Hand dressed stone average 4 Cft 1 No - Each -


Cement 0.06 Bag - Bag -
Sand 0.30 Cft. - % Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total -

Labour

Mason 0.25 No - Per Day -


Unskilled Coolies 2.00 Nos - Per Day -
Blacksmith 0.12 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total for 4 Cft -
Rate for Per Cft -

Labour Rate Per Cft Rs. - Say -


Labour Rate P/ Cum Rs. (0.08) Say -

Composite Rate Per Cft Rs. - Say -


Composite Rate P/ Cum Rs. (0.30) Say (0.30)

Page 51
DESCRIPTION OF ITEM NO 14: Providing and fixing stone blocks under 2 Cf
(0.05 M) each, including lift upto 20 Cft (

Detail Unit Rate (British System) per Cft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material Rate Analysis for 2 Cft

Hand dressed stone average (2 Cft) 1 No - Each -


Cement 0.03 Bag - Bag -
Sand 0.17 Cft. - % Cft -

Total -
Contractor's Profit & Ove ##### Percent -
Total 0.01 0.01
2.00 0.01
Labour Rate Analysis for 1 Cft

Mason 0.05 No - Per Day -


Unskilled Coolies 0.25 No - Per Day -
Blacksmith 0.03 No - Per Day -

Total -
Sundries ##### Percent -
Total -

Contractor's Profit & Ove ##### Percent -


Total -

Labour Rate Per Cft Rs. - Say -


Labour Rate P/ Cum Rs. 0.25 Say 0.25

Composite Rate Per Cft Rs. 0.01 Say -


Composite Rate P/ Cum Rs. 0.33 Say 0.35

Page 52
CHAPTER NO. 20

SURFACE DRAINAGE
DESCRIPTION OF ITEM NO 1: Tega formed of pacca bricks on end, laid in and over cement
sand mortar projecting to a height of not more than 6"
(150mm) top of drain along the property side where required,
laid to lines, grades, slopes and shape according to the
engineer's drawing.

a) 3" (75mm) Thick.


i) Ratio (1:3)

Detail Unit Rate (British System) per 100 Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.96 Bag 0.00 Each -


Sand 3.20 Cft 0.00 P. Cft -
Bricks 260.00 Nos 0.00 Per 1000 No 312.00

Total 312.00
Contractor's Profit & Ove 20 Percent 62.40
Total 374.40

Labour for 125 Rft

Mason 0.67 No 0.00 P. Day -


Unskilled Cooly 1.00 No 0.00 P. Day -
Bahishti 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -
Item Rates
Labour Rate Per 100 Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -

Composite Rate Per 100 Rft Rs. 374.39 Say 374.40


Composite Rate Per Rm Rs. 12.08 Say 12.10

Page 1
Item No. 1 Tega formed of pacca bricks on end, laid in and over cement
sand mortar projecting to a height of not more than 6"
(150mm) top of drain along the property side where required,
laid to lines, grades, slopes and shape according to the
engineer's drawing.

a) 3" (75mm) Thick.


ii) Ratio (1:5)

Detail Unit Rate (British System) per 100 Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.64 Bag 0.00 Each -


Sand 4.00 Cft 0.00 P. Cft -
Bricks 260.00 Nos 0.00 Per 1000 No -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Rft

Mason 0.67 No 0.00 P. Day -


Unskilled Cooly 1.00 No 0.00 P. Day -
Bahishti 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -

Composite Rate Per 100 Rft Rs. 0.00 Say -


Composite Rate Per Rm Rs. 0.00 Say -

Page 2
Item No. 1 Tega formed of pacca bricks on end, laid in and
over cement sand mortar projecting to a height of
not more than 6" (150mm) top of drain along the
property side where required, laid to lines,
grades, slopes and shape according to the
engineer's drawing.

b) 4" (115mm) Thick.


i) Ratio (1:3)

Detail Unit Rate (British System) per 100 Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 1.30 Bag 0.00 Each -


Sand 4.70 Cft 0.00 P. Cft -
Bricks 380.00 Nos 0.00 Per 1000 No -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Rft

Mason 1.00 No 0.00 P. Day -


Unskilled Cooly 1.50 No 0.00 P. Day -
Bahishti 0.38 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -

Composite Rate Per 100 Rft Rs. 0.01 Say -


Composite Rate Per Rm Rs. 0.00 Say -

Page 3
Item No. 1 Tega formed of pacca bricks on end, laid in and
over cement sand mortar projecting to a height of
not more than 6" (150mm) top of drain along the
property side where required, laid to lines,
grades, slopes and shape according to the
engineer's drawing.

b) 4" (115mm) Thick.


ii) Ratio (1:5)

Detail Unit Rate (British System) per 100 Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.83 Bag 0.00 Each -


Sand 5.20 Cft 0.00 P. Cft -
Bricks 380.00 Nos 0.00 Per 1000 No -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Rft

Mason 1.00 No 0.00 P. Day -


Unskilled Cooly 1.50 No 0.00 P. Day -
Bahishti 0.38 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -

Composite Rate Per 100 Rft Rs. 0.00 Say -


Composite Rate Per Rm Rs. 0.00 Say -

Page 4
DESCRIPTION OF ITEM NO 2: Pacca flat brick 3" (75mm) thick, laid in
reimbursement, in cement, sand mortar on sides
of drains and in other works where required. All
joints to be completely filled and struck flush.

a) Ratio (1:3)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Pacca Bricks 350.00 Nos 0.00 Per 1000 No -


Cement 1.50 Bag 0.00 Each -
Sand 5.60 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Sft

Mason 1.00 No 0.00 P. Day -


Unskilled Cooly 1.50 No 0.00 P. Day -
Bahishti 0.33 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -

Composite Rate Per 100 Sft Rs. 0.01 Say -


Composite Rate Per Sqm Rs. 0.00 Say -

Page 5
Item No. 2 Pacca flat brick 3" (75mm) thick, laid in
reimbursement, in cement, sand mortar on sides
of drains and in other works where required. All
joints to be completely filled and struck flush.

b) Ratio (1:5)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bricks 350.00 Nos 0.00 Per 1000 No -


Cement 1.00 Bag 0.00 Each -
Sand 6.25 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Sft

Mason 1.00 No 0.00 P. Day -


Unskilled Cooly 1.50 No 0.00 P. Day -
Bahishti 0.33 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -

Composite Rate Per 100 Sft Rs. 0.00 Say -


Composite Rate Per Sqm Rs. 0.00 Say -

Page 6
Item No. 2 Pacca flat brick 3" (75mm) thick, laid in
reimbursement, in cement, sand mortar on sides
of drains and in other works where required. All
joints to be completely filled and struck flush.

c) Ratio (1:6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bricks 350.00 Nos 0.00 Per 1000 No -


Cement 0.86 Bag 0.00 Each -
Sand 6.40 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Sft

Mason 1.00 No 0.00 P. Day -


Unskilled Cooly 1.50 No 0.00 P. Day -
Bahishti 0.33 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -

Composite Rate Per 100 Sft Rs. 0.00 Say -


Composite Rate Per Sqm Rs. 0.00 Say -

Page 7
DESCRIPTION OF ITEM NO 3: Pacca brick on edge, laid in reimbursement, in
cement, sand mortar on sides of drains and in
other works where required. All joints to be
completely filled and struck flush.

a) Ratio (1:3)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bricks 525.00 Nos 0.00 Per 1000 No -


Cement 2.30 Bag 0.00 Each -
Sand 8.55 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Sft

Mason 1.50 No 0.00 P. Day -


Unskilled Cooly 2.00 No 0.00 P. Day -
Bahishti 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -

Composite Rate Per 100 Sft Rs. 0.00 Say -


Composite Rate Per Sqm Rs. 0.00 Say -

Page 8
Item No. 3 Pacca brick on edge, laid in reimbursement, in
cement, sand mortar on sides of drains and in
other works where required. All joints to be
completely filled and struck flush.

b) Ratio (1:5)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bricks 525.00 Nos 0.00 Per 1000 No -


Cement 1.50 Bag 0.00 Each -
Sand 9.50 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Sft

Mason 1.50 No 0.00 P. Day -


Unskilled Cooly 2.00 No 0.00 P. Day -
Bahishti 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -

Composite Rate Per 100 Sft Rs. 0.00 Say -


Composite Rate Per Sqm Rs. 0.00 Say -

Page 9
Item No. 3 Pacca brick on edge, laid in reimbursement, in
cement, sand mortar on sides of drains and in
other works where required. All joints to be
completely filled and struck flush.

c) Ratio (1:6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bricks 525.00 Nos 0.00 Per 1000 No -


Cement 1.30 Bag 0.00 Each -
Sand 9.78 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Sft

Mason 1.50 No 0.00 P. Day -


Unskilled Cooly 2.00 No 0.00 P. Day -
Bahishti 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -

Composite Rate Per 100 Sft Rs. 0.00 Say -


Composite Rate Per Sqm Rs. -0.01 Say -

Page 10
DESCRIPTION OF ITEM NO 4: Pacca flat brick, herring bond pitching in cement,
sand mortar laid to lines, grades, shapes and
slopes as per Engineer's Drawing.

a) Ratio (1:3)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bricks 350.00 Nos 0.00 Per 1000 No -


Cement 1.50 Bag 0.00 Each -
Sand 5.60 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Sft

Mason 0.75 No 0.00 P. Day -


Unskilled Cooly 1.50 No 0.00 P. Day -
Bahishti 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -

Composite Rate Per 100 Sft Rs. 0.00 Say -


Composite Rate Per Sqm Rs. 0.00 Say -

Page 11
Item No. 4 Pacca flat brick, herring bond pitching in cement,
sand mortar laid to lines, grades, shapes and
slopes as per Engineer's Drawing.

b) Ratio (1:5)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bricks 350.00 Nos 0.00 Per 1000 No -


Cement 1.00 Bag 0.00 Each -
Sand 6.25 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Sft

Mason 0.75 No 0.00 P. Day -


Unskilled Cooly 1.50 No 0.00 P. Day -
Bahishti 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -

Composite Rate Per 100 Sft Rs. 0.00 Say -


Composite Rate Per Sqm Rs. 0.00 Say -

Page 12
Item No. 4 Pacca flat brick, herring bond pitching in cement,
sand mortar laid to lines, grades, shapes and
slopes as per Engineer's Drawing.

c) Ratio (1:6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bricks 350.00 Nos 0.00 Per 1000 No -


Cement 0.86 Bag 0.00 Each -
Sand 6.40 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Sft

Mason 0.75 No 0.00 P. Day -


Unskilled Cooly 1.50 No 0.00 P. Day -
Bahishti 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -

Composite Rate Per 100 Sft Rs. 0.00 Say -


Composite Rate Per Sqm Rs. 0.00 Say -

Page 13
DESCRIPTION OF ITEM NO 5: Pacca brick on edge, herring bond pitching in
cement, sand mortar laid to lines, grades, shapes
and slopes as per Engineer's Drawing.

a) Ratio (1:3)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bricks 525.00 Nos 0.00 Per 1000 No -


Cement 2.30 Bag 0.00 Each -
Sand 8.55 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Sft

Mason 1.00 No 0.00 P. Day -


Unskilled Cooly 2.80 Nos 0.00 P. Day -
Bahishti 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -

Composite Rate Per 100 Sft Rs. 0.00 Say -


Composite Rate Per Sqm Rs. 0.00 Say -

Page 14
Item No. 5 Pacca brick on edge, herring bond pitching in
cement, sand mortar laid to lines, grades, shapes
and slopes as per Engineer's Drawing.

b) Ratio (1:5)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bricks 525.00 Nos 0.00 Per 1000 No -


Cement 1.50 Bag 0.00 Each -
Sand 9.50 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Sft

Mason 1.00 No 0.00 P. Day -


Unskilled Cooly 2.80 Nos 0.00 P. Day -
Bahishti 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -

Composite Rate Per 100 Sft Rs. 0.00 Say -


Composite Rate Per Sqm Rs. 0.00 Say -

Page 15
Item No. 5 Pacca brick on edge, herring bond pitching in
cement, sand mortar laid to lines, grades, shapes
and slopes as per Engineer's Drawing.

c) Ratio (1:6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bricks 525.00 Nos 0.00 Per 1000 No -


Cement 1.30 Bag 0.00 Each -
Sand 9.78 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 125 Sft

Mason 1.00 No 0.00 P. Day -


Unskilled Cooly 2.80 Nos 0.00 P. Day -
Bahishti 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -

Composite Rate Per 100 Sft Rs. 0.00 Say -


Composite Rate Per Sqm Rs. 0.00 Say -

Page 16
DESCRIPTION OF ITEM NO 6: Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades, slopes
and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).

a) Type I

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

CC 1:6:12
1x100x5/6'x1/6' 13.89 Cft
Say: 13.90 Cft
CC 1:2:5
1x100x5/6'x11/24' 38.19 Cft

D/D 1x100x22/7xxxx 2.45 Cft

D/D 1x100x(6"+10")x" 2.78 Cft


2 32.96 Cft
Say: 33.00 Cft
Surface Rendering

1x100x22/7x3/12' 78.57 Sft


1x100x(2"+2") 33.33 Sft
12 111.90 Sft
Say: 112 Sft
Material

Cement for.
Cement Concrete 1:6:12 0.90 Bag
Cement Concrete 1:2:5 4.78 Bag
" Cement PLaster 1:1 1.03 Bag
6.71 Bag 0.00 Each -
Sand for.
Cement Concrete 1:6:12 6.81 Cft
Cement Concrete 1:2:5 14.95 Cft
" Cement PLaster 1:1 1.29 Cft
23.05 Cft 0.00 P. Cft -

Page 17
a) Type I

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Brick ballast 1:6:12 13.62 Cft 0.00 P. Cft -


Bajri for 1:2:5 29.70 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Mason 1.50 No 0.00 P. Day -


Unskilled Cooly 3.00 Nos 0.00 P. Day -
Bahishti 0.75 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. 0.05 Say 0.05
Labour Rate Per Rm Rs. 0.26 Say 0.25

Composite Rate Per Rft Rs. 0.10 Say 0.10


Composite Rate Per Rm Rs. 0.33 Say 0.35

Page 18
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).

b) Type II

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

CC 1:6:12
1x100x(1'-2"+1'-8")x7" 88.10 Cft
2
Deduction.
1x100x(8"+11")x4" 28.77 Cft
2
Net Total 59.33 Cft
CC 1:2:5
1x100x(11"+8")x4" 28.77 Cft
2
1x100x(1-8")x4" 56.94 Cft
Total 85.71 Cft
Deduction.
1x100x0.82 8.20 Cft
1x100(7 3/8"+10") 2 1/8" 17.34 Cft
2
1x100(10"+1"-8")x0.87 4.21 Cft
2
Total 29.75 Cft
85.71 - 29.75 Net Tot 55.96 Cft
Surface Rendering
With Cement Sand Mortar1:1of" thick 220.00 Sft
Material
Cement for.
Cement Concrete 1:6:12 3.84 Bags
Cement Concrete 1:2:5 5.62 Bags
" Cement PLaster 1:1 2.27 Bags
11.73 Bags 0.00 Each -
Sand for.
Cement Concrete 1:6:12 28.86 Cft
Cement Concrete 1:2:5 17.54 Cft
" Cement PLaster 1:1 2.86 Cft
49.26 Cft 0.00 P. Cft -

Page 19
b) Type II

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Brick ballast for 1:6:12 57.70 Cft 0.00 P. Cft -


Bajri for 1:2:5 35.10 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Mason 3.00 Nos 0.00 P. Day -


Unskilled Cooly 6.00 Nos 0.00 P. Day -
Bahishti 1.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -

Composite Rate Per Rft Rs. 0.00 Say -


Composite Rate Per Rm Rs. 0.00 Say -

Page 20
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).

c) Type III

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
CC 1:6:12
1x100(1'-3 5/8"+1'-11") 117.33 Cft
2
2'x100'x4"x1" 9.38 Cft
Total 126.71 Cft
Deduction.
1x100x(8"+1'-")x5" 40.93 Cft
2
Net Total 85.78 Cft
CC 1:2:5
1x100(8"+1'-2") 5" 43.92 Cft
2
1x100x1'-11"x4" 63.89 Cft
Total 107.81 Cft
Deduction.
1x100x.082 8.20 Cft
1x100(7-3/8"+1'-")6" 41.40 Cft
2

1x100(1'-"+1'-11")x" 9.24 Cft


2
Total 58.84 Cft
107.81 - 58.84 Net Total 48.97 Cft

Surface Rendering.
Surface Area.
1x9.4'x100 78.33 Sft
12

2x6"x100 108.33 Sft


12

Page 21
c) Type III

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

2x5"x100 87.50 Sft


12
274.16 Sft
Material Required. Say: 274.20 Sft
Cement for.
Cement Concrete 1:6:12 5.57 Bags
Cement Concrete 1:2:5 7.10 Bags
Cement for Surface rendering 2.52 Bags
15.19 Bags
Say 15.00 0.00 Each -
Sand for.
Sand for 1:6:12 40.00 Cft
Sand for 1:2:5 22.00 Cft
Sand for Surface rendering 3.00 Cft
65.00 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 84.00 Cft 0.00 P. Cft -
Bajri for 1:2:5 44.07 Cft 0.00 P. Cft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour

Mason 2.75 Nos 0.00 P. Day -


Unskilled Cooly 10.00 Nos 0.00 P. Day -
Bahishti 1.30 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total -

Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Composite Rate Per Rft Rs. 0.00 Say -
Composite Rate Per Rm Rs. 0.00 Say -

Page 22
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).

d) Type IV

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
CC 1:6:12
1x100(1'-3 "+2'-1")x11" 164.73 Cft
2
2x100x4"x1" 9.38 Cft
Total 174.11 Cft
Deduction.
1x100x(8"+1-3")x8" 69.35 Cft
2

Net Total 104.76 Cft


CC 1:2:5
1x100(8"+1'-4") 8" 71.60 Cft
2
1x100x2'-1"x4" 70.14 Cft
Total 141.74 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7'-3/8"+1'-2")x8" 67.20 Cft
2
1x100(1'-2"+2'-1")x" 10.42 Cft
2
Total 85.82 Cft
141.74 - 85.82 Net Total 55.92 Cft
Surface Rendering.
1x9.4/1x100 78.33 Sft
12
2x5x100 87.50 Sft
12
2x9x100 158.33 Sft
12 324.16 Sft
Say: 324.16 Sft

Page 23
d) Type IV

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material Required.
Cement for.
Cement for 1:6:12 6.81 Bags
Cement for 1:2:5 8.11 Bags
Cement for Surface rendering 2.98 Bags
17.90 Bags 0.00 Each -
Sand for.
Sand for 1:6:12 51.33 Cft
Sand for 1:2:5 25.33 Cft
Sand for Surface rendering 3.73 Cft
80.39 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 102.66 Cft 0.00 P. Cft -
Stone Bajri for 1:2:5 50.33 Cft 0.00 P. Cft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour

Mason 3.25 Nos 0.00 P. Day -


Unskilled Cooly 11.83 Nos 0.00 P. Day -
Bahishti 1.67 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. -0.05 Say -

Composite Rate Per Rft Rs. 0.00 Say -


Composite Rate Per Rm Rs. 0.00 Say -

Page 24
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).

e) Type V

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
CC 1:6:12
1x100(1'-7"+2'-3")x10" 170.44 Cft
2

2x100x(6"x4")5" 44.01 Cft


2
Total 214.45 Cft
Deduction.
1x100x(8"+1'-2")x7" 59.24 Cft
2
Net Total 155.21 Cft

CC 1:2:5
1x100(8"+1'-6")x1'-1" 120.75 Cft
2
1x100x2'-3"x4" 77.08 Cft
Total 197.83 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7-3/8"+1'-5")x11" 100.48 Cft
2

1x100(1-5"+2'-3")x" 11.72 Cft


2
Total 120.40 Cft
97.83 - 120.40 Net Total 77.43 Cft
Surface Rendering with 1:1 C/S.
Mortor " thick.
1x9.4"x100 78.33 Sft
12

Page 25
e) Type V

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

2x5"x100 87.50 Sft


12
2x1'-1"x100 216.66 Sft
Total 382.49 Sft
Material Required. Say: 382.50 Sft
Cement for.
Cement for 1:6:12 9.96 Bags
Cement for 1:2:5 11.22 Bags
Cement for Surface rendering 3.52 Bags
24.70 Bags 0.00 Each -
Sand for.
Sand for 1:6:12 75.00 Cft
Sand for 1:2:5 35.00 Cft
Sand for Surface rendering 4.40 Cft
114.40 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 150.15 Cft 0.00 P. Cft -
Stone Bajri for 1:2:5 69.70 Cft 0.00 P. Cft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Mason 4.00 Nos 0.00 P. Day -


Unskilled Cooly 16.00 Nos 0.00 P. Day -
Bahishti 2.20 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. -0.02 Say -
Composite Rate Per Rft Rs. 0.00 Say -
Composite Rate Per Rm Rs. 0.00 Say -

Page 26
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).
f) Type VI

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
CC 1:6:12
1x100(1'-7"+2'-6")x1-1" 230.25 Cft
2
2x100x(6"x4")5" 42.01 Cft
2
Total 272.26 Cft
Deduction.
1x100x(8"+1-5 1/8")x10" 91.58 Cft
2
Net Total 180.68 Cft
CC 1:2:5
1x100(8"+1'-9 1/8")x1'-4" 161.81 Cft
2
1x100x2'-6-1/8"x4" 83.68 Cft
Total 245.49 Cft
Deduction.
1x100(7'-3/8"+1'-7 5/8")x1'-2" 138.28 Cft
2
1x100(1'-7 5/8"+2'-6 1/8")x0.75" 12.96 Cft
2
1x100x0.082 8.20 Cft
Total 159.44 Cft
45.49 - 159.44 Net Total 86.05 Cft
Surface Rendering.
1x9.4x100 78.33 Sft
12
2x5"x100 87.50 Sft
12
2x1'-4/12"x100 266.66 Sft
Total 432.49 Sft
Say: 432.50 Sft

Page 27
f) Type VI

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material Required.
Cement for.
Cement for 1:6:12 11.74 Bags
Cement for 1:2:5 12.48 Bags
Cement for Surface rendering 3.98 Bags
28.20 Bags 0.00 Each -
Sand for.
Sand for 1:6:12 88.53 Cft
Sand for 1:2:5 38.98 Cft
Sand for Surface rendering 4.97 Cft
132.48 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 177.07 Cft 0.00 P. Cft -
Stone Bajri for 1:2:5 77.45 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Mason 4.55 Nos 0.00 P. Day -


Unskilled Cooly 18.50 Nos 0.00 P. Day -
Bahishti 2.50 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -

Composite Rate Per Rft Rs. 0.00 Say -


Composite Rate Per Rm Rs. 0.00 Say -

Page 28
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).

g) Type VII

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
CC 1:6:12
1x100(1'-7"+2'-8")x1-4 3/8" 292.82 Cft
2
2x100x(6"x4")5" 40.10 Cft
2
Total 332.92 Cft

Deduction.
1x100x(8"+9'-7")1'-1 3/8" 127.71 Cft
2
Net Total 205.21 Cft
CC 1:2:5
1x100(8"+1'-11")1'-6.5/8" 203.71 Cft
2
1x100x2'-8"x4" 90.28 Cft
Total 293.99 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7 3/9"+1'-10")1'-5" 178.52 Cft
2
1x100(1'-10"+2'-8")x7/8" 16.56 Cft
2
Total 203.28 Cft
93.99 - 203.28 Net Total 90.71 Cft

Surface Rendering with 1:1 CS mortor.


1x9.4x100 78.33 Sft
12

Page 29
g) Type VII

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

2x5"x100 87.50 Sft


12
2x1'-7/12"x100 316.66 Sft
482.49 Sft
Material Required. Say: 482.50 Sft
Cement for.
Cement for 1:6:12 13.34 Bags
Cement for 1:2:5 13.15 Bags
Cement for Surface rendering 4.44 Bags
30.93 Bags 0.00 Each -
Sand for.
Sand for 1:6:12 100.55 Cft
Sand for 1:2:5 41.09 Cft
Sand for Surface rendering 5.55 Cft
147.19 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 201.00 Cft 0.90 P. Cft -
Stone Bajri for 1:2:5 81.64 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour

Mason 5.04 Nos 0.00 P. Day -


Unskilled Cooly 20.50 Nos 0.00 P. Day -
Bahishti 2.78 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total -

Item Rates
Labour Rate Per Rft Rs. -0.01 Say -
Labour Rate Per Rm Rs. -0.01 Say -
Composite Rate Per Rft Rs. -0.01 Say -
Composite Rate Per Rm Rs. -0.03 Say -

Page 30
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).

h) Type VIII

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

CC 1:6:12
1x100(1'-7"+2'-10 7/8")1' 7" 355.43 Cft
2x100x(6"+4")5" 40.10 Cft
2
Total 395.53 Cft
Deduction.
1x100x(8"+1'-9 7/8")1'-4" 165.97 Cft
2
Net Total 229.56 Cft
CC 1:2:5
1x100(8"+2-1 7/8")1'-9" 249.95 Cft
2
1x100(2'-10 7/8")4" 96.88 Cft
Total 346.83 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7 3/8"+2'-3/8")1'-8" 223.42 Cft
2
1x100(2'-3/8"+2'-10 7/8")x" 15.43 Cft
2
Total 247.05 Cft
6.83 - 247.05 Net Total 99.78 Cft

Surface Rendering with 1:1 CS mortor.


1x9.4/x100 78.33 Sft
12

Page 31
h) Type VIII

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

2x5"x100 87.50 Sft


12
2x1'-10.1/12"x100 375.00 Sft
540.83 Sft
Material Required. Say : 540.85 Sft

Cement for.
Cement for 1:6:12 14.92 Bags
Cement for 1:2:5 14.50 Bags
Cement for Surface rendering 4.98 Bags
34.40 Bags 0.00 Each -
Sand for.
Sand for 1:6:12 112.48 Cft
Sand for 1:2:5 45.30 Cft
Sand for Surface rendering 6.22 Cft
164.00 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 250.00 Cft 0.00 P. Cft -
Stone Bajri for 1:2:5 90.00 Cft 0.00 P. Cft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour

Mason 5.63 Nos 0.00 P. Day -


Unskilled Cooly 22.90 Nos 0.00 P. Day -
Bahishti 3.10 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total -

Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Composite Rate Per Rft Rs. 0.00 Say -
Composite Rate Per Rm Rs. 0.00 Say -

Page 32
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).

i) Type IX

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
CC 1:6:12
1x100(1'-10 3/8"+3'-3")x1'-8" 427.99 Cft
2

2x100x(7"+4")9" 80.30 Cft


2
Total 508.29 Cft
Deduction.
1x100x(9 3/8"+1'-11")x1'-4" 181.22 Cft
2
Net Total 327.07 Cft
CC 1:2:5
1x100(9 3/8"+2'-6")x2'-1" 347.45 Cft
2
1x100(3'-3")4" 122.66 Cft
Total 470.11 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7 3/8"+2'-11/2")x2'-" 278.41 Cft
2
1x100(2'-2"+3'-3")x" 17.19 Cft
2
Total 303.80 Cft
0.11 - 303.80 Net Total 166.31 Cft
Surface Rendering with (1:) C/S Mortar.
1x9.4/x100 78.33 Sft
12
2x6x100 104.17 Sft
12

Page 33
i) Type IX

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

2x1'-10.1/12"x100 375.00 Sft


557.50 Sft
Material Required.
Cement for.
Cement for 1:6:12 21.26 Bags
Cement for 1:2:5 24.11 Bags
Cement for Surface rendering 5.13 Bags
50.50 Bags 0.00 Each -
Sand for.
Sand for 1:6:12 160.26 Cft
Sand for 1:2:5 75.34 Cft
Sand for Surface rendering 6.41 Cft
242.01 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 320.53 Cft 0.00 P. Cft -
Stone Bajri for 1:2:5 149.68 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Mason 6.66 Nos 0.00 P. Day -


Unskilled Cooly 31.91 Nos 0.00 P. Day -
Bahishti 4.03 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Composite Rate Per Rft Rs. 0.00 Say -
Composite Rate Per Rm Rs. 0.00 Say -

Page 34
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).

j) Type X

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

CC 1:6:12
1x100(1'-10"+3'-5")x1'-10" 503.91 Cft
2

2x100x(8"+4")9" 82.47 Cft


2
Total 586.38 Cft

Deduction.
1x100x(9"+2'-1")1'-6" 226.43 Cft
2
Net Total 359.95 Cft
CC 1:2:5
1x100(9"+2'-8")2'-4" 410.76 Cft
2
1x100x3'-5"4" 130.47 Cft
Total 541.23 Cft

Deduction.
1x100x0.082 8.20 Cft
1x100(7' 3/8"+2'-5")2'-2" 333.86 Cft
1x100(2'-5"+3'-5")x" 18.43 Cft
2
Total 360.49 Cft
23 - 360.49 Net Total 180.74 Cft

Surface Rendering with (1:1) Cement


Sand Mortar. 620.00 Sft

Page 35
j) Type X

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material Required.
Cement for.
Cement for 1:6:12 23.40 Bags
Cement for 1:2:5 26.20 Bags
Cement for Surface rendering 5.70 Bags
55.30 Bags 0.00 Each -
Sand for.
Sand for 1:6:12 176.37 Cft
Sand for 1:2:5 81.85 Cft
Sand for Surface rendering 7.13 Cft
265.35 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 352.75 Cft 0.00 P. Cft -
Stone Bajri for 1:2:5 162.61 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour

Mason 7.35 Nos 0.00 P. Day -


Unskilled Cooly 35.00 Nos 0.00 P. Day -
Bahishti 4.43 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Composite Rate Per Rft Rs. 0.00 Say -
Composite Rate Per Rm Rs. 0.00 Say -

Page 36
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).

k) Type XI

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

CC 1:6:12
1x100(1'-10"+3'-8")x2'-1 3/8" 599.05 Cft
2
2x100x(8"+4")9" 82.47 Cft
2
Total 681.52 Cft

Deduction.
1x100x(9"+2'-4")1'-9" 285.09 Cft
2
Net Total 396.43 Cft
CC 1:2:5
1x100(9"+2'-11")2'-7" 490.99 Cft
1x100x3'-8"x4" 138.28 Cft
Total 629.27 Cft

Deduction.
1x100x0.082 8.20 Cft
1x100(7' 3/8"+2'-7")2'-5" 400.71 Cft
2
1x100(2'-7"+3'-8")x" 19.79 Cft
2
Total 428.70 Cft
.27 - 428.70 Net Total 200.57 Cft

Surface Rendering with (1:1) Cement


Sand Mortar. 711.70 Sft

Page 37
k) Type XI

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material Required.
Cement for.
Cement for 1:6:12 25.77 Bags
Cement for 1:2:5 29.08 Bags
Cement for Surface rendering 6.55 Bags
61.40 Bags 0.00 Each -
Sand for.
Sand for 1:6:12 194.25 Cft
Sand for 1:2:5 91.12 Cft
Sand for Surface rendering 8.18 Cft
293.55 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 388.50 Cft 0.00 P. Cft -
Stone Bajri for 1:2:5 180.51 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Mason 8.34 Nos 0.00 P. Day -


Unskilled Cooly 38.94 Nos 0.00 P. Day -
Bahishti 4.96 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -

Composite Rate Per Rft Rs. -0.02 Say -


Composite Rate Per Rm Rs. -0.02 Say -

Page 38
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).

l) Type XII

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

CC 1:6:12
1x100(1'-10"+3'-10")x2'-4" 681.72 Cft
2

2x100x(8"+4")9" 84.63 Cft


2
Total 766.35 Cft
Deduction.
1x100x(9"+2'-6")2'-" 338.91 Cft
2
Total 427.44 Cft

CC 1:2:5
1x100(9"+3'-1")2'-10" 557.81 Cft
1x100x3'-10"x4" 146.09 Cft
Total 703.90 Cft

Deduction.
1x100x0.082 8.20 Cft
1x100(7' 3/8"+2'-10")2'-8" 466.17 Cft
2

1x100(2'-10"+3'-10")x" 21.61 Cft


2
Total 495.98 Cft
90 - 495.98 Net Total 207.92 Cft

Surface Rendering with (1:1) Cement


Sand Mortar. 765.82 Sft

Page 39
l) Type XII

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material Required.
Cement for.
Cement for 1:6:12 27.78 Bags
Cement for 1:2:5 30.15 Bags
Cement for Surface rendering 7.05 Bags
64.98 Bags 0.00 Each -
Sand for.
Sand for 1:6:12 209.45 Cft
Sand for 1:2:5 94.19 Cft
Sand for Surface rendering 7.05 Cft
310.69 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 418.90 Cft 0.00 P. Cft -
Stone Bajri for 1:2:5 187.12 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Mason 8.89 Nos 0.00 P. Day -


Cooly 41.50 Nos 0.00 P. Day -
Bahishti 5.30 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -

Composite Rate Per Rft Rs. -0.05 Say -


Composite Rate Per Rm Rs. -0.01 Say -

Page 40
DESCRIPTION OF ITEM NO 7: Laying RC hume pipes in positions, including
jointing.

a) 6" to 12" (150 to 300mm) Dia.

Detail t Rate (British System) per Rft/Assumed for 40

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.25 Bags 0.00 Each -


Sand 1.20 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 50 Lft

Mason 1.00 No 0.00 P. Day -


Unskilled Cooly 4.00 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -

Composite Rate Per Rft Rs. 0.25 Say 0.25


Composite Rate Per Rm Rs. 0.87 Say 0.85

Page 41
Item No. 7 Laying RC hume pipes in positions, including
jointing.

b) 12" to 24" (300 to 600mm) Dia.

Detail t Rate (British System) per Rft/Assumed for 40

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.50 Bags 0.00 Each -


Sand 2.40 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 50 Lft

Mason 1.00 No 0.00 P. Day -


Unskilled Cooly 7.00 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -

Composite Rate Per Rft Rs. 0.55 Say 0.55


Composite Rate Per Rm Rs. 1.80 Say 1.80

Page 42
Item No. 7 Laying RC hume pipes in positions, including
jointing.

c) 24" to 36" (600 to 900mm) Dia.

Detail t Rate (British System) per Rft/Assumed for 40

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.75 Bags 0.00 Each -


Sand 3.75 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 50 Lft

Mason 2.00 No 0.00 P. Day -


Unskilled Cooly 8.00 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -

Composite Rate Per Rft Rs. 0.80 Say -


Composite Rate Per Rm Rs. 2.62 Say -

Page 43
CHAPTER NO. 12
WOOD WORK
DESCRIPTION OF ITEM NO. 1: Plain wood work sawn wrought planed & fixed
in position including cost of nails & screw
a) Deodar Wood.

Detail Unit Rate (British System) per Cft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Deodar Wood including wastage (II Class) 1.15 Cft 0.00 P. Cft -
Nail 0.020 Kg. 0.00 P. Cft -
Screws above 1" long 1.00 Dozen 0.00 P.Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Carpentre 0.63 No 0.00 P. Day -


Cooly Skilled 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Cft Rs. 0.01 Say -
Labour Rate Per Cum Rs. 0.23 Say 0.25

Composite Rate Per Cft Rs. ##### Say (0.10)


Composite Rate Per Cum Rs. ##### Say (5.00)

Page 1
Item No. 1 Plain wood work sawn wrought planed & fixed
in position including cost of nails & screw
b) Shisham Wood

Detail Unit Rate (British System) per Cft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Shisham wood including 15% wastage 1.15 Cft 0.00 P. Cft -


Nail 0.023 Kg. 0.00 P. Cft -
Screws above 1" long 1.00 Dozen 0.00 P.Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour for 1.50 Cft.

Carpenters 1.00 No 0.00 P. Day -


Cooly Skilled 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -
Labour for 1 Cft. -

Item Rates
Labour Rate Per Cft Rs. - Say -
Labour Rate Per Cum Rs. 0.10 Say 0.10

Composite Rate Per Cft Rs. ##### Say (0.30)


Composite Rate Per Cum Rs. ##### Say (10.40)

Page 2
DESCRIPTION OF ITEM NO. 2: Plain wood work for regulation karries or
needles etc. including sawing plaining
wroughting wood providing & fixing steel pa
of karries i.e. end strips and rods etc.

a) Deodar Wood.

Detail Unit Rate (British System) per Cft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

i) Deodar Wood
5.5x5/12x5/12 = 0.97 0.97 Cft
Wastage 15% 0.15 Cft
1.12 Cft 0.00 P. Cft -
ii)1.6' (480mm) long iron strip 1"
(37mm) wide x1/8" (3mm) thick @
0.625 Lbs/ft. (0.930 Kg/Mtr). 2.00 Lbs
2 Nox1' (380mm) long iron bars
" (20mm) on both ends @ 1.502
Lbs/ft. (2.235 Kg/m). 3.80 Lbs
5.80 Lbs
Wastage 5% 0.29 Lbs
6.09Lb (2 .76)Kg 0.00 P. Kg -
iii) Iron Screw 1" (25mm) long 1.00 Dozen 0.00 P. Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Page 3
Detail Unit Rate (British System) per Cft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Carpenters 0.32 No 0.00 P. Day -


Cooly Skilled 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Cft Rs. - Say -
Labour Rate Per Cum Rs. 0.12 Say 0.10

Composite Rate Per Cft Rs. - Say -


Composite Rate Per Cum Rs. 0.26 Say 0.25

Page 4
Item No. 2 Plain wood work for regulation karries or n
etc. including sawing plaining wroughting w
providing & fixing steel parts of karries i
strips and rods etc.

b) Shisham Wood

Detail Unit Rate (British System) per Cft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

i) Shisham Wood
5.5x5/12x5/12 = 0.97 0.97 Cft
Wastage 15% 0.15 Cft
1.12 Cft 0.00 P. Cft -
ii)Iron Strip
1.6' (480mm) long iron strip 1"
(37mm) wide x1/8" (3mm) thick @
0.625 Lbs/ft. (0.930 Kg/Mtr). 2.00 Lbs
2 Nox1' (380mm) long iron bars
" (20mm) on both ends @ 1.502
Lbs/ft. (2.235 Kg/m). 3.80 Lbs
5.80 Lbs
Wastage 5% 0.29 Lbs
6.09Lb (2 .76)Kg 0.00 P. Kg -
iii) Iron Screw 1" (25mm) long 1.00 Dozen 0.00 P. Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Page 5
Detail Unit Rate (British System) per Cft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Carpenters 0.32 No 0.00 P. Day -


Cooly Skilled 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Cft Rs. - Say -
Labour Rate Per Cum Rs. 0.12 Say 0.10

Composite Rate Per Cft Rs. ##### Say -


Composite Rate Per Cum Rs. ##### Say (0.20)

Page 6
DESCRIPTION OF ITEM NO 3: First class teak wood wrought joinery in do
windows etc. panelled, panelled and glazed
glazed & fixed in position including chowkh
fast tower bolts, chocks rubber stop, cleat
clamps, chords with hooks, nails screws etc
complete (Excluding sliding bolt and lock).

i) 2" (50mm) Thick.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material

Teak Wood
Frame
Top Rail 4'x3"x4" 0.45 Cft
Vertical 2x7'x3"x4" 1.33 Cft
Vertical Style 4x6'-6"x4"x2" 1.46 Cft
Horizental Rail 2x1'-10"x4"x2" 0.20 Cft
Middle Rail 2x1'-10"x6"x2" 0.20 Cft
Lock Rail 2x1'-10"x6"x2" 0.31 Cft
Bottom Rail 2x1'-10"x8"x2" 0.42 Cft

Panells
2x14"x22"x" 0.27 Cft
4x14"x18.5"x" 0.45 Cft

Beading
2(14"+14"+22"+22")x5/8"
(1 + 2) 0.02 Cft
2x8

4(14"+14"+18"+18")5/8"
(1 + 2) 0.02 Cft
2x8
5.13 Cft
Wastage 12% 0.62 Cft
5.75 Cft 0.00 P. Cft -

Page 7
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Fitting

Hinges 4" (100mm) 8.00 Nos 0.00 Each -


Tower Bolts 9" (225mm) 3.00 Nos 0.00 Each -
Handles 6" (150mm) 3.00 Nos 0.00 Each -
Iron Hold Fast 6.00 Nos 0.00 Each -
Rubber Pad 2.00 Nos 0.00 Each -
Hook & Clamps 2.00 Nos 0.00 Each -
Screws above 1" long 2.50 Doz 0.00 P. Doz -
Glue 0.05 Kg. 0.00 P. Kg. -
Spikes 0.20 Kg. 0.00 P. Kg. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -

Rate Per Sft 0.00 = -


27

Labour

Carpenters 3.00 Nos 0.00 P. Day -


Cooly Unskilled 1.25 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 27 Sft. -

Rate Per Sft 730.54 = 27.06


27
Item Rates
Labour Rate Per Sft Rs. ##### Say 27.05
Labour Rate Per Sqm Rs. ##### Say 291.15

Composite Rate Per Sft Rs. ##### Say 27.00


Composite Rate Per Sqm Rs. ##### Say 291.15

Page 8
Item No. 3 First class teak wood wrought joinery in do
windows etc. panelled, panelled and glazed
glazed & fixed in position including chowkh
hold fast tower bolts, chocks rubber stop,
G.I. clamps, chords with hooks, nails screw
complete (Excluding sliding bolt and lock).
ii) 1" (45mm) Thick.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material

Teak Wood
Frame
Top Rail 4'x3"x4" 0.45 Cft
Vertical 2x7'x3"x4" 1.33 Cft
Vertical Style 4x6'-6"x4"x1" 1.25 Cft

Horizontal Rail
Top 2x1'-10"x4"x1" 0.18 Cft
Middle 2x1'-10"x4"x1" 0.18 Cft
Lock 2x1'-10"x6"x1" 0.27 Cft
Bottom 2x1'-10"x8"x1" 0.36 Cft

Panels
2x14"x22"x" 0.27 Cft
4x14"x18.5"x" 0.44 Cft

Beading
2(14"x14"x22"+22")x5/8"
(1 + 2) 0.01 Cft
2x8

4(14"+14"+18.5"+18.5")5/8"
(1 + 2) 0.02 Cft
2x8
4.76 Cft
Wastage 12% 0.57 Cft
5.33 Cft 0.00 P. Cft -

Page 9
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Fitting 7,462.00

Hinges 4" (100mm) 8.00 Nos 0.00 Each -


Tower Bolts 9" (225mm) 3.00 Nos 0.00 Each -
Handles 6" (150mm) 3.00 Nos 0.00 Each -
Iron Hold Fast 6.00 Nos 0.00 Each -
Rubber Pad 2.00 Nos 0.00 Each -
Hook & Clamps 2.00 Nos 0.00 Each -
Screws above 1" long 2.50 Doz 0.00 P. Doz -
Glue 0.05 Kg. 0.00 P. Kg. -
Spikes 0.20 Kg. 0.00 P. Kg. -

Total 7,462.00
Contractor's Profit & Ove 20 Percent 1,492.40
Total for 27 Sft. 8,954.40

Rate Per Sft 8954.40 = 331.64


27
Labour

Carpenters 3.00 Nos 0.00 P. Day -


Cooly Unskilled 1.25 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 27 Sft. -

Rate Per Sft 0.00 = -


27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say 331.60


Composite Rate Per Sqm Rs. ##### Say 3,568.10

Page 10
Item No. 3 First class teak wood wrought joinery in do
windows etc. panelled, panelled and glazed
glazed & fixed in position including chowkh
hold fast tower bolts, chocks rubber stop,
G.I. clamps, chords with hooks, nails screw
complete (Excluding sliding bolt and lock).
iii) 1" (37mm) Thick.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material

Teak Wood for Frame


Frame
Top Rail 1x4'x3"x4" 0.45 Cft
Vertical 2x7'x3"x4" 1.33 Cft
Vertical style 4x6'-6"x4"x1" 1.08 Cft

Leaves
Top Rail 2x1'-10"x4"x1" 0.15 Cft
Middle 2x1'-10"x4"x1" 0.15 Cft
Lock 2x1'-10"x6"x1" 0.23 Cft
Bottom 1x1'-10"x8"x1" 0.30 Cft

Panels
2x14"x22"x5/8" 0.23 Cft
4x14"x18.5"x5/8" 0.44 Cft

Beading
2(14"x14"x22"+22")x5/8"
(1 + 2) 0.01 Cft
2x8

4(14"+14"+18.5"+18.5")5/8"
(1 + 2) 0.02 Cft
2x8
4.39 Cft
Wastage 12% 0.53 Cft
4.92 Cft 0.00 P. Cft -

Page 11
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

6,888.00
Fitting
Hinges 4" (100mm) 8.00 Nos 0.00 Each -
Tower Bolts 9" (225mm) 3.00 Nos 0.00 Each -
Handles 6" (150mm) 3.00 Nos 0.00 Each -
Iron Hold Fast 6.00 Nos 0.00 Each -
Rubber Pad 2.00 Nos 0.00 Each -
Hook & Clamps 2.00 Nos 0.00 Each -
Screws above 1" long 2.50 Doz 0.00 P. Doz -
Glue 0.05 Kg. 0.00 P. Kg. -
Spikes 0.20 Kg. 0.00 P. Kg. -

Total 6,888.00
Contractor's Profit & Ove 20 Percent 1,377.60
Total for 27 Sft. 8,265.60

Rate Per Sft 8265.60 = 306.13


27
Labour

Carpenters 3.00 Nos 0.00 P. Day -


Unskilled Cooly 1.25 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -

Rate Per Sft 0.00 = -


27

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say 306.05


Composite Rate Per Sqm Rs. ##### Say 3,292.95

Page 12
DESCRIPTION OF ITEM NO 4: First class teak wood wrought joinery in wi
gauze doors & windows with frames 22 SWG
galvanized iron wire gauze 12x12 meshes to
square inchs (625mm) including brass fittin
bars etc. complete :

a) Teak wood framing 1" (45mm) thick with wir


gauze fixed in position:
i) Without spring or spring hinges.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material

Teak Wood
Top Rail 1x4'x3"x" 0.04 Cft
Vertical 2x7'x3"x" 0.15 Cft
Fillet 2(15"+15"+25"+25")1"x3/8" 0.02 Cft
Fillet 2(15"+15"+19"+19")x"x3/8" 0.03 Cft

Leaf
Vertical Style 4x6'-6"x4"x1" 1.27 Cft

Horizontal
Top 2x1'-10"x1"x1" 0.06 Cft
Middle 2x1'-10"x3"x1" 0.07 Cft
Lock 2x1'-10"x6"x1" 0.27 Cft
Bottom 2x1'-10"x6"x1" 0.27 Cft
2.18 Cft
Wastage 10% 0.22 Cft
2.40 Cft 0.00 P. Cft -

Page 13
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Fitting 3,360.00

Hinges 4" (100mm) 6.00 Nos 0.00 Each -


Tower Bolts 9" (225mm) 2.00 Nos 0.00 Each -
Handles 6" (150mm) 2.00 Nos 0.00 Each -
Hook & Clamps 2.00 Nos 0.00 Each -
Screws above 1" long 2.00 Doz 0.00 P. Doz -

Wire Gauze
2x1'-2"x2'-1" 4.83 Sft
4x1'-2"x1'-7" 7.33 Sft
12.16 Sft
Wastage 15% 1.82 Sft
13.98 Sft 0.00 Sft -

Total 3,360.00
Contractor's Profit & Ove 20 Percent 672.00
Total for 27 Sft 4,032.00

Rate Per Sft 4032.00 = 149.33


27
Labour

Carpenters 0.50 Nos 0.00 P. Day -


Skilled Cooly 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft -
Rate Per Sft 0.00 = -
27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say 149.30


Composite Rate Per Sqm Rs. ##### Say 1,606.30

Page 14
DESCRIPTION OF ITEM NO 4: First class teak wood wrought joinery in wi
gauze doors & windows with frames 22 SWG
galvanized iron wire gauze 12x12 meshes to
square inch (625mm) including brass fitting
bars etc. complete :

a) Teak wood framing 1" (45mm) thick with wir


gauze fixed in position:
ii) With spring or spring hinges.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material

Teak Wood
Top Rail 1x4'x3"x" 0.04 Cft
Vertical 2x7'x3"x" 0.15 Cft
Fillet 2(15"+15"+25"+25")1"x3/8" 0.02 Cft
Fillet 2(15"+15"+19"+19")1"x3/8" 0.03 Cft

Leaf
Vertical Style = 4'x6'-6"x4"x1" 1.27 Cft

Horizontal
Top 2x1'-10"x1"x1" 0.06 Cft
Middle 2x1'-10"x3"x1" 0.07 Cft
Lock 2x1'-10"x6"x1" 0.27 Cft
Bottom 2x1'-10"x6"x1" 0.27 Cft
2.18 Cft
Wastage 10% 0.22 Cft
2.40 Cft 0.00 P. Cft -

Page 15
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Tower Bolts 9" (225mm) 2.00 Nos 0.00 Each -
Handles 6" (150mm) 2.00 Nos 0.00 Each -
Hook & Clamps 2.00 Nos 0.00 Each -
Screws / Nail 2.00 Doz 0.00 P. Doz -
Spring Hings 2.00 Nos 0.00 Each -

Wire Gauze
2x1'-2"x2'-1" = 4.83 Sft
4x1'-2"x1'-7" = 7.33 Sft
12.16 Sft
Wastage 10% 1.22 Sft
13.38 Sft 0.00 Sft -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. 3,986.80
Rate Per Sft 3986.80 = 147.66
27
Labour

Carpenters 0.50 Nos 0.00 P. Day -


Skilled Cooly 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Rate Per Sft 0.00 = -
27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say 147.65


Composite Rate Per Sqm Rs. ##### Say 1,588.80

Page 16
Item No. 4 First class teak wood wrought joinery in wi
gauze doors & windows with frames 22 SWG
galvanized iron wire gauze 12x12 meshes to
square inch (625mm) including brass fitting
bars etc. complete:

b) Teak wood framing 1" (40mm) thick with wir


gauze fixed in position.
i) Without spring or spring hinges.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material

Ist Class Teak Wood


Vertical Style 4x6'-6"x4"x1" 1.09 Cft

Horizontal
Top Rail 2x1-10"x3"x1" 0.12 Cft
Middle 2x1-10"x1"x1" 0.06 Cft
Lock 2x1'-10"x6"x1" 0.24 Cft
Bottom 2x1'-10"x6"x1" 0.24 Cft
Fillet 2(15"+15"+25"+25")"x3/8" 0.02 Cft
Fillet 2(15"+15"+19"+19")"x3/8" 0.03 Cft
Top Rail 1x4'x3"x" 0.05 Cft
Vertical Rail 2x7'x3"x" 0.15 Cft
2.00 Cft
Wastage 10% 0.20 Cft
2.20 Cft 0.00 P. Cft -
Fitting
Hinges 4" (100mm) 6 Nos 0.00 Each -
Tower Bolts 9" (225mm) 2 Nos 0.00 Each -
Handles 6" (150mm) 2 Nos 0.00 Each -
Hook & Clamps 2 Nos 0.00 Each -
Screws / Nail 2 Doz 0.00 P. Doz -

Page 17
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Wire Gauze
2x1'-2"x2'-1" 4.83 Sft
4x1'-2"x1'-7" 7.33 Sft
12.16 Sft
Wastage 15% 1.82 Sft
13.98 Sft 0.00 Sft -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -

Rate Per Sft 0.00 = -


27
Labour

Carpenters 0.50 Nos 0.00 P. Day -


Skilled Cooly 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 27 Sft. -

Rate Per Sft 0.00 = -


27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. ##### Say -

Page 18
Item No. 4 First class teak wood wrought joinery in wi
gauze doors & windows with frames 22 SWG
galvanized iron wire gauze 12x12 meshes to
square inch (625mm) including brass fitting
bars etc. complete:

b) Teak wood framing 1" (40mm) thick with wir


gauze fixed in position.
ii) With spring or spring hinges.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material
Ist Class Teak Wood
Vertical Style 4x6-6"x4"x1" 1.09 Cft

Horizontal
Top Rail 2x1'-10"x3"x1" 0.12 Cft
Middle 2x1'-10"x1"x1" 0.06 Cft
Lock 2x1'-10"x6"x1" 0.24 Cft
Bottom 2x1'-10"x6"x1" 0.24 Cft
Fillet 2(15"+15"+25"+25")"x3/8" 0.02 Cft
Fillet 2(15"+15"+19"+19")"x3/8" 0.03 Cft
Top Rail 1x4'x3"x" 0.05 Cft
Vertical Rail 2x7'x3"x" 0.15 Cft
2.00 Cft
Wastage 10% 0.20 Cft
2.20 Cft 0.00 P. Cft -
Fitting
Hinges 4" (100mm) 6 Nos 0.00 Each -
Tower Bolts 9" (225mm) 2 Nos 0.00 Each -
Handles 6" (150mm) 2 Nos 0.00 Each -
Hook & Clamps 2 Nos 0.00 Each -
Screws / Nail 2 Doz 0.00 Doz -
Spring hings 2 Nos 0.00 Each -

Page 19
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Wire Gauze
2x1'-2"x2'-1" 4.83 Sft
4x1'-2"x1'-7" 7.33 Sft
12.16 Sft
Wastage 15% 1.82 Sft
13.98 Sft 0.00 Sft -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -

Rate Per Sft 0.00 = -


27
Labour

Carpenters 0.50 Nos 0.00 P. Day -


Skilled Cooly 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 27 Sft. -

Rate Per Sft 0.00 = -


27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. ##### Say -

Page 20
Item No. 4 First class teak wood wrought joinery in wi
gauze doors & windows with frames 22 SWG
galvanized iron wire gauze 12x12 meshes to
square inch (625mm) including brass fitting
bars etc. complete:

c) G.I. Wire gauze 22 SWG 12x12 meshes per Sq


Inch (25mm) fixed to chowkhat with " (20mm
teak wood strips and screws.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3' x 4' = 12 Sft

Material

Teak Wood
Horizontal Strips 2x3'x3"x" 0.09 Cft
Vertital Strips 2x3.5'x3"x" 0.11 Cft
0.2 Cft
Wastage 15% 0.03 Cft
0.23 Cft 0.00 P. Cft -
Wire gauze = 1x3x4 12 Sft
Wastage 10% 1.2 Sft
13.20 Sft 0.00 Sft -

Fitting
Screws above 1" long 2.00 Doz 0.00 Doz 5.28
Nail 0.07 Kg. 0.00 P. Kg. -

Total 5.28
Contractor's Profit & Ove 20 Percent 1.06
Total for 12 Sft. 6.34

Rate Per Sft 6.34 = 0.53


12

Page 21
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Carpenters 0.40 No 0.00 P. Day -


Skilled Cooly 0.20 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 12 Sft. -

Rate Per Sft 0.00 = -


12
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. 0.53 Say 0.55


Composite Rate Per Sqm Rs. 5.69 Say 5.70

Page 22
Item No. 4 First class teak wood wrought joinery in wi
gauze doors & windows with frames 22 SWG
galvanized iron wire gauze 12x12 meshes to
square inch (625mm) including brass fitting
bars etc. complete:

d) G.I. Wire gauze 22 SWG 12x12 meshes per Sq


Inch (25mm) fixed with " (12mm) teak
wood strips and screws.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 2' = 8 Sft

Material

Teak Wood
Horizontal Rail 2x4'x2"x2" 0.22 Cft
Vertital Rail 2x2'x2"x2" 0.11 Cft
Strip Rail 2x4'x2"x2" 0.05 Cft
Strips Rail 2x1 2/3'x2"x2" 0.03 Cft
Moulding 0.15 Cft
0.56 Cft
Wastage 15% 0.09 Cft
0.65 Cft 0.00 P. Cft -

Wire gauze 12x12 meshes/Sq. in (25mm)

Area 4x2 = 8 Sft. 8.00 Sft


Wastage 10% 0.80 Sft
8.80 Sft 0.00 Sft -
Fitting
Screws 2.00 Doz 0.00 P. Doz -
Nail 0.07 Doz 0.00 P. Doz -
Wooden Plug 6.00 Nos 0.00 Each 3.00

Total 3.00
Contractor's Profit & Ove 20 Percent 0.60
Total for 8 Sft 3.60

Rate Per Sft 3.60 = 0.45


8

Page 23
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Carpenters 0.25 No 0.00 P. Day -


Skilled Cooly 0.125 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 8 Sft. -

Rate Per Sft 0.00 = -


8
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. 0.05 Say 0.05

Composite Rate Per Sft Rs. 0.46 Say 0.45


Composite Rate Per Sqm Rs. 4.94 Say 4.95

Page 24
DESCRIPTION OF ITEM NO 5: Providing and fixing expanded metal " to
(12mm to 20mm) mesh 16 gauze fixed to
chowkhat with 1" (25mm) teak wood strips an
screws etc. complete.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 2' = 8 Sft

Material
Teak Wood
Cover moulding/ Strips.
2x2'x1/12'x3/12' 0.08 Cft
2x3x10/12'x1/12'x3/12' 0.16 Cft
0.24 Cft
Wastage 15% 0.04 Cft
0.28 Cft 0.00 P. Cft -
Expended Metal
4'x2' 8.00 Sft
Wastage 5% 0.40 Sft
8.40 Sft 0.00 Sft -
Nail and Screw 2.00 Doz 0.00 P. Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 8 Sft. -
Rate Per Sft 0.00 = -
8

Labour
Carpenters 0.25 No 0.00 P. Day -
Skilled Cooly 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 8 Sft. -
Rate Per Sft 0.00 = -
8
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. 0.01 Say -


Composite Rate Per Sqm Rs. ##### Say -

Page 25
DESCRIPTION OF ITEM NO 6: Providing and fixing expanded metal " to
(12mm to 20mm) mesh 16 gauze fixed to chowk
with 1" (25mm) cover moulding & screws
including teak wood frame 2"x2" (50x50mm).

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 3' = 12 Sft

Material
Teak Wood Frame
2Nox4'x2"x2" 0.23 Cft
2Nox3'x2"x2" 0.17 Cft
Moulding 13 2/3x1/12x2/12 0.20 Cft
0.60 Cft
Wastage 15% 0.09 Cft
0.69 Cft 0.00 P. Cft -
Expanded Metal
1'x4'x3' 12.00 Sft
Wastage 5% 0.60 Sft
12.60 Sft 0.00 Sft -
Nail and Screw L.S. 8.00
Total 8.00
Contractor's Profit & Ove 20 Percent 1.60
Total for 12 Sft. 9.60
Rate Per Sft 9.60
12 = 0.80
Labour
Carpenters 0.50 No 0.00 P. Day -
Skilled Cooly 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 12 Sft. 0.01
Rate Per Sft 0.01 = 0.00
12
Item Rates
Labour Rate Per Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.01 Say -

Composite Rate Per Sft Rs. 0.80 Say 0.80


Composite Rate Per Sqm Rs. 8.62 Say 8.60

Page 26
DESCRIPTION OF ITEM NO 7: First class deodar wood wrought joinery in
windows etc. panelled or panelled or glazed
glazed fixed in position including chowkhat
fast, hinges, tower bolt rubber stop cleats
handles and chord with hooks etc. complete
(excluding sliding bolts or lock)

a) 2" (50mm) thick.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material

Top Rail 4x3"x4" 0.45 Cft


Vertical Rail 2x7'x3"x4" 1.33 Cft
Vertical Style 4x6'x6"x4"x2" 1.46 Cft
Horizotal Style 2x1'-10"x4"x2" 0.20 Cft
Middle Style 2x1'-10"x4"x2" 0.20 Cft
Middle Style 2x1'-10"x4"x2" 0.31 Cft
Bottom Style 2x1'-10"x8"x2" 0.42 Cft

Panells
2'x14"x22"x" 0.27 Cft
4'x14"x18.5"x" 0.45 Cft

Beading
2(14"+14"+22"+22")5/8"(1"+2") 0.02 Cft
2x8
4(14"+18.5"+18.5")5/8"(1"+2") 0.02 Cft
2x8
5.13 Cft
Wastage 15% 0.77 Cft
5.90 Cft 0.00 P. Cft -

Page 27
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Fitting
Hinges 4" (100mm) 8.00 Nos 0.00 Each -
Tower Bolts 9" (225mm) 3.00 Nos 0.00 Each -
Handles 6" (150mm) 3.00 Nos 0.00 Each -
Iron Hold Fast 6.00 Nos 0.00 Each -
Rubber Pad 2.00 Nos 0.00 Each -
Hook & Clamps 2.00 Nos 0.00 Each -
Screws / Nail 2.50 Doz 0.00 Doz -
Glue 0.05 Kg. 0.00 P. Kg. -
Spikes 0.20 Kg. 0.00 P. Kg. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour

Carpenters 3.00 Nos 0.00 P. Day -


Skilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Item Rates
Labour Rate Per Sft Rs. ##### Say -
Labour Rate Per Sqm Rs. ##### Say -

Composite Rate Per Sft Rs. ##### Say -


Composite Rate Per Sqm Rs. ##### Say -

Page 28
Item No. 7 First class deodar wood wrought joinery in
windows etc. panelled or panelled or glazed
glazed fixed in position including chowkhat
fast, hinges, tower bolt rubber stop cleats
handles and chord with hooks etc. complete
(excluding sliding bolts or lock)

b) 1" (45mm) thick.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material

Top Rail 4x3"x4" 0.45 Cft


Vertical Rail 2x7'x3"x4" 1.33 Cft
Vertical Style 4x6-6"x4"x1" 1.25 Cft

Horizontal Rail
Top 2x1'-10"x4"x1" 0.18 Cft
Middle 2x1'-10"x4"x1" 0.18 Cft
Lock 2x1'-10"x6"x1" 0.27 Cft
Bottom 2x1'-10"x8"x1" 0.36 Cft

Panells
2'x14"x22"x" 0.27 Cft
4'x14"x18.5"x" 0.44 Cft

Beadings
2(14"+14"+22"+22")5/8" (1"+2") 0.01 Cft
2x8
4(14"+14"+18.5"+18.5")5/8"(1"+2") 0.02 Cft
2x8
4.76 Cft
Wastage 15% 0.71 Cft
5.47 Cft 0.00 P. Cft -

Page 29
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Fitting
Hinges 4" (100mm) 8.00 Nos 0.00 Each -
Tower Bolts 9" (225mm) 3.00 Nos 0.00 Each -
Handles 6" (150mm) 3.00 Nos 0.00 Each -
Iron Hold Fast 6.00 Nos 0.00 Each -
Rubber Pad 2.00 Nos 0.00 Each -
Hook & Clamps 2.00 Nos 0.00 Each -
Screws / Nail 2.50 Doz 0.00 Doz -
Glue 0.05 Kg. 0.00 P. Kg. -
Spikes 0.20 Kg. 0.00 P. Kg. -

Total for 27 Sft. -


Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = (0.01)
27
Labour

Carpenters 3.00 Nos 0.00 P. Day -


Skilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. 0.01
Rate Per Sft 0.01 = 0.00
27
Item Rates
Labour Rate Per Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. ##### Say -

Composite Rate Per Sft Rs. ##### Say -


Composite Rate Per Sqm Rs. ##### Say (0.10)

Page 30
Item No. 7 First class deodar wood wrought joinery in
windows etc. panelled or panelled or glazed
glazed fixed in position including chowkhat
fast, hinges, tower bolt rubber stop cleats
handles and chord with hooks etc. complete
(excluding sliding bolts or lock)

c) 1" (40mm) thick.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material
Top Rail 1x4x3"x4" 0.45 Cft
Vertical Rail 2x7x3"x4" 1.33 Cft
Vertical Style 4x6'-6"x4"x1" 1.20 Cft

Horizontal Rail
Top 2x1'-10"x4"x1" 0.15 Cft
Middle 2x1'-10"x4"x1" 0.15 Cft
Lock 2x1'-10"x6"x1" 0.23 Cft
Bottom 2x1'-10"x8"x1" 0.30 Cft

Panells
2'x14"x22"x"x5/8" 0.22 Cft
4'x14"x18.5"x5/8" 0.44 Cft

Beadings
2(14"+14"+22"+22")5/8"(1"+2") 0.01 Cft
2x8
4(14"+14"+18.5"+18.5")5/8"(1"+2") 0.02 Cft
2x8
4.50 Cft
Wastage 15% 0.68 Cft
5.18 Cft 0.00 P. Cft -

Page 31
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Tower Bolts 9" (225mm) 3.00 Nos 0.00 Each -
Handles 6" (150mm) 3.00 Nos 0.00 Each -
Iron Hold Fast 6.00 Nos 0.00 Each -
Rubber Pad 2.00 Nos 0.00 Each -
Hook & Clamps 2.00 Nos 0.00 Each -
Screws / Nail 2.50 Doz 0.00 Doz -
Glue 0.05 Kg. 0.00 P. Kg. -
Spibes 0.20 Kg. 0.00 P. Kg. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour

Carpenters 3.00 Nos 0.00 P. Day -


Skilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. ##### Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. ##### Say -

Page 32
DESCRIPTION OF ITEM NO 8: Deodar wood framed braced and battened door
windows complete with iron fitting & fixed
position including chowkhat.

a) 2"(55mm) thick with 1"(32mm) thick planks

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3' x 7' = 21 Sft

Material

Deodar Wood
Top Rail 1x3x3"x4" 0.35 Cft
Vertical Rail 2x7"x3"x4" 1.36 Cft

Leaf
Plank 1x2 2/12x6 17/24x1/12 1.44 Cft
Battens 3x2x1/3'x3/8'x5/8' 0.27 Cft
Braces 2x3 47/48x3/8x5/8 0.31 Cft
3.73 Cft
Wastage 15% 0.56 Cft
4.29 Cft 0.00 P. Cft -
Fitting
Hinges 10" (250mm) 3.00 Nos 0.00 Each -

Tower Bolts 9" (225mm) 1.00 No 0.00 Each -


Bolts 8" (200mm) with staple for pad
lock. 1.00 No 0.00 Each -
Wrought Iron hold fast 6.00 Nos 0.00 Each -
Hinges chocks 4" (100mm) 1.00 No 0.00 Each -
Door stop 6" (150mm) 1.00 No 0.00 Each -
Handles 6" (150mm) 2.00 Nos 0.00 Each -
Screws above 1" long 2.00 Doz 0.00 Doz -
Nails of sorts 0.06 Kg 0.00 P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 21 Sft. -

Rate Per Sft 0.00 = -


21

Page 33
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Carpenters 2.50 Nos 0.00 P. Day -


Skilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 21 Sft. -
Rate Per Sft 0.00 = (0.01)
21
Item Rates
Labour Rate Per Sft Rs. ##### Say -
Labour Rate Per Sqm Rs. ##### Say -

Composite Rate Per Sft Rs. 0.08 Say 0.10


Composite Rate Per Sqm Rs. 1.01 Say 1.00

Page 34
Item No. 8 Deodar wood framed braced and battened door
windows complete with iron fitting & fixed
position including chowkhat.

b) 1" (45mm) thick with 1" (25mm) battens and


planking.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3' x 6.5' = 19.5 Sft

Material

Deodar Wood
Top Rail 1x3'x'x3/8 0.35 Cft
Vertical Rail 2x6'xx3/8 1.17 Cft
Leaf Plank 1x2 7/12x6 5/24x 1/16 1.00 Cft
Ledges 2x3 13/20x1/3x1/12 0.20 Cft
Braces 2x3 13/20x1/3x1/12 0.20 Cft
2.92 Cft
Wastage 15% 0.44 Cft
3.36 Cft 0.00 P. Cft -
Fitting
Hinges 5" (125mm) 3.00 Nos 0.00 Each -
Tower Bolts 9" (225mm) 3.00 Nos 0.00 Each -
Wrought Iron hold fast 4.00 Nos 0.00 Each -
Hinges chocks 4" (100mm) 1.00 No 0.00 Each -
Door stops 6" (150mm) 1.00 No 0.00 Each -
Handles 6" (150mm) 2.00 Nos 0.00 Each -
Screws above 1" long 2.00 Doz 0.00 P. Doz -
Nails of sorts 0.06 Kg 0.00 P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 19.5 Sft. -

Rate Per Sft 0.00 = -


19.5

Page 35
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Carpenters 2.00 Nos 0.00 P. Day -


Skilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 19.5 -

Rate Per Sft 0.00 = -


19.5
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say (0.70)


Composite Rate Per Sqm Rs. ##### Say (7.20)

Page 36
DESCRIPTION OF ITEM NO 9: 1" (25mm) thick battened doors and windows
in position complete with iron fittings wit
chowkhat.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 100 Sft

Material

Deodar Wood 9.50 Cft 0.00 Cft -


T. Hinges 6" (150mm) 4.00 Nos 0.00 Each -
Tower bolt 6" (150mm) 2.00 Nos 0.00 Each -
Stops 2.00 Nos 0.00 Each -
Nails 0.063 Kg. 0.00 Kg. -
Screws 2.00 Dozen 0.00 P. Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
100
Labour

Carpenters 16.00 Nos 0.00 P. Day -


Skilled Cooly 3.00 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 100 Sft. -

Rate Per Sft 0.00 = -


100.0
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 37
DESCRIPTION OF ITEM NO 10: Deodar battened ledged & braced doors and
windows 2" (56mm) thick (1" (30mm) thick
ledge braces and 1" thick battens complete
iron fittings chowkhats and fixed in positi

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3' x 6.5' = 19.5 Sft

Material

Deodar Wood
Chowkhat 2x6'x3"x4" 1.30 Cft
1x3"x3"x4" 0.19 Cft
Leaf Batten 1x2'-7"x6"-3"x1/12 1.35 Cft
Styles 3x2'-5"x4"-1" 0.26 Cft
Braces 2x3.0"x4"x1" 0.20 Cft
3.30 Cft
Wastage 15% 0.50 Cft
3.80 Cft 0.00 P. Cft -
Fitting
Hinges Chocks 4" (100mm) 1.00 No 0.00 Each -
Door Stop 6" (150mm) 1.00 No 0.00 Each -
Tower Bolts 9" (225mm) 2.00 Nos 0.00 Each -
Tower Hinges 8" (200mm) 2.00 Nos 0.00 Each -
Wrought Iron hold fast 4.00 Nos 0.00 Each -
Hasp and staple 1.00 No 0.00 Each -
Handles 2.00 Nos 0.00 Each -
Screws above 1' long 2.00 Doz 0.00 P. Doz -
Nails of sorts 0.13 Kg 0.00 P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 19.5 Sft 2,237.69

Rate Per Sft 2237.69 = 114.75


19.5

Page 38
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour
Carpenters 2.50 Nos 0.00 P. Day -
Skilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 19.5 Sft. -

Rate Per Sft 0.00 = -


19.5
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. 0.05 Say 0.05

Composite Rate Per Sft Rs. ##### Say 114.75


Composite Rate Per Sqm Rs. ##### Say 1,234.75

Page 39
DESCRIPTION OF ITEM NO 11: a Deodar wood framed with braces and 22 SWG
G.I. Sheet facing including hold fast, wood
beading, hinges and locking arrangement, as
Directed by the Engineer Incharge.
i) G.I. Sheet facing one side

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 8' x 8' = 64 Sft

Material

Deodar Wood 7.00 Cft 0.00 Cft -


22 gauge G.I. Plain sheet 64.00 Sft
Wastage 10% 6.40 Sft
70.40 Sft 0.00 Sft -
Hold fast with pivots & clamp 6.00 Nos 0.00 Each -
Screws above 1" long 3.00 Doz 0.00 P. Doz -
Sliding bolts 18" (450mm) long 1.00 No 0.00 Each -
Nails 0.23 Kg 0.00 P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 64 Sft. -
Rate Per Sft 0.00 = -
64

Labour
Carpenters 3.50 Nos 0.00 P. Day -
Skilled Cooly 1.50 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 64 Sft. -
Rate Per Sft 0.00 = -
64.0
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. 0.05 Say 0.05

Page 40
DESCRIPTION OF ITEM NO 11: a Deodar wood framed with braces and 22 SWG
G.I. Sheet facing including hold fast, wood
beading, hinges and locking arrangement, as
Directed by the Engineer Incharge.
ii) G.I. Sheet facing on both side.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 8' x 8' = 64 Sft

Material
Deodar Wood 7.00 Cft 0.00 P. Cft -
22 gauge G.I. Plain sheet 128.00 Sft
Wastage 10% 12.80 Sft
140.80 Sft 0.00 Sft -
Hold fast with pivots & clamp 6.00 Nos 0.00 Each -
Screws above 1" long 3.00 Doz 0.00 P. Doz -
Sliding bolts 1" (450 mm) long 1.00 No 0.00 Each -
Nails 0.47 Kg 0.00 P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 64 Sft. -
Rate Per Sft 0.00 = -
64
Labour
Carpenters 4.00 Nos 0.00 P. Day -
Skilled Cooly 1.50 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 64 Sft. -
Rate Per Sft 0.00 = -
64.0
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. 0.05 Say 0.05

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. 0.05 Say 0.05

Page 41
Item No. 11 Partal wood frame with braces & 22 SWG G.I.
Sheet facing including hold fast wooden bea
hinges and locking arrangement as directed
Engineering incharge.
i) G.I. Sheet facing one side

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 8' x 8' = 64 Sft

Material
Partal Wood 7.00 Cft 0.00 P. Cft -
22 gauge G.I. Plain sheet 64.00 Sft
Wastage 10% 6.40 Sft
70.40 Sft 0.00 Sft -
Hold fast with pivots & clamp 6.00 Nos 0.00 Each -
Screws above 1" long 3.00 Doz 0.00 P. Doz -
Sliding bolts 1" (450 mm) long 1.00 No 0.00 Each -
Nails 0.23 Kg 0.00 P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 64 Sft. -
Rate Per Sft 0.00 = -
64

Labour
Carpenters 3.50 Nos 0.00 P. Day -
Skilled Cooly 1.50 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -
Rate Per Sft 0.00 = -
64.0
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. ##### Say -

Page 42
Item No. 11 Partal wood frame with braces & 22 SWG G.I.
Sheet facing including hold fast wooden bea
hinges and locking arrangement as directed
Engineering incharge.
ii) G.I. Sheet facing on both side

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Anaylsis for 8' x 8' = 64 Sft

Material
Partal Wood 7.00 Cft 0.00 P. Cft -
22 gauge G.I. Plain sheet 128.00 Sft
Wastage 10% 12.80 Sft
140.80 Sft 0.00 Sft -
Hold fast with pivots & clamp 6.00 Nos 0.00 Each -
Screws above 1" long 3.00 Doz 0.00 P. Doz -
Sliding bolts 18" (450 mm) long 1.00 No 0.00 Each -
Nails 0.47 Kg 0.00 P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 64 Sft. -
Rate Per Sft 0.00 = -
64
Labour
Carpenters 4.00 Nos 0.00 P. Day -
Skilled Cooly 1.50 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 64 Sft. -
Rate Per Sft 0.00 = -
64.0
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. 0.05 Say 0.05

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. 0.05 Say 0.05

Page 43
DESCRIPTION OF ITEM NO 12: First class deodar wood wrought joinery wor
wire gauze doors and windows with 22 SWG
galvanized wire gauze 12x12 mashes per squa
inch (625mm) including iron fittings comple

a) Deodar framing 1" (45mm) with wire gauge


fixed in position.
i) Without Springs or Spring Hinges.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material

Deodar Wood Frame


Top Rail 1x4x3"x" 0.04 Cft
Vertical Rail 2x7x3"x" 0.15 Cft
Fillet 2(15+15+25+25)x3/8 0.02 Cft
Leaves 2(15+15+19+19)x3/8 0.03 Cft

Vertical Style
4x6'-6"x4"x1 1.27 Cft

Horizontal
Top 2x1'-10"x3"x1" 0.07 Cft
Middle 2x1'-10"x1"x1" 0.06 Cft
Lock 2x1'-10"x6"x1" 0.27 Cft
Bottom 2x1'-10"x6"x1" 0.27 Cft
2.18 Cft
Wastage 10% 0.22 Cft
2.40 Cft 0.00 P. Cft -
Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Tower Bolts 9" (225mm) 2.00 Nos 0.00 Each -
Handles 6" 2.00 Nos 0.00 Each -
Hook & Clamp 2.00 Nos 0.00 Each -
Screws / Nails 2.00 Doz 0.00 P. Doz -

Page 44
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Wire Gauge
2x1'-2"x2'-1" 4.83 Sft
4x1'-2"x1'-7" 7.33 Sft
12.16 Sft
Wastage 15% 1.82 Sft
13.98 Sft 0.00 Sft -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour

Carpenters 1.50 Nos 0.00 P. Day -


Skilled Cooly 0.75 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 27 Sft. -
Rate Per Sft 0.00 = -
27.0
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 45
Item No. 12 First class deodar wood wrought joinery wor
wire gauze doors and windows with 22 SWG
galvanized wire gauze 12x12 mashes per squa
inch (625mm) including iron fittings comple

a) Deodar wood framing 1" (45mm) thick with


wire gauge fixed in position.
ii) With Springs & Spring Hinges.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material

Deodar Wood Frame


Top Rail 1x4'x3"x" 0.04 Cft
Vertical Rail 2x7'x3"x" 0.15 Cft
Fillet 2(15"+15"+25"+25")"x3/8" 0.02 Cft
Leaves 2(15"+15"+19"+19")"x3/8" 0.03 Cft

Vertical Style
4x6'-6"x4"x1" 1.27 Cft

Horizontal
Top 2x1'-10"x3"x1" 0.07 Cft
Middle 2x1'-10"x1"x1" 0.06 Cft
Lock 2x1'-10"x6"x1" 0.27 Cft
Bottom 2x1'-10"x6"x1" 0.27 Cft
2.18 Cft
Wastage 10% 0.22 Cft
2.40 Cft 0.00 P. Cft -
Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Tower Bolts 2.00 Nos 0.00 Each -
Handles 6" (150mm) 2.00 Nos 0.00 Each -
Hook & Clamp 2.00 Nos 0.00 Each -
Screws / Nails 2.00 Doz 0.00 P. Doz -
Spring Hinges 2.00 Nos 0.00 Each -

Page 46
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Wire Gauge
2x1'-2"x2'-1" 4.83 Sft
4x1'-2"x1'-7" 7.33 Sft
12.16 Sft
Wastage 15% 1.82 Sft
13.98 Sft 0.00 Sft -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour

Carpenters 1.50 Nos 0.00 P. Day -


Skilled Cooly 0.75 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -
Rate Per Sft 0.00 = -
27.0
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. ##### Say -

Page 47
Item No. 12 First class deodar wood wrought joinery wor
wire gauze doors and windows with 22 SWG
galvanized wire gauze 12x12 mashes per squa
inch (625mm) including iron fittings comple

b) Deodar Wood framing 1" (40mm) thick with


wire gauze fixed in position.
i) Without Springs as Spring Hinges.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4'x6.75' = 27 Sft

Material

1st Class Deodar Wood


Vertical Style 4x6'-6"x4"x1" 1.09 Cft

Horizontal
Top 2x1'-10"x3"x1" 0.12 Cft
Middle 2x1'-10"x1"x1" 0.06 Cft
Lock 2x1'-10"x6"x1" 0.24 Cft
Bottom 2x1'-10"x6"x1" 0.24 Cft
Fillets 2(15"+15"25+25) x 3/8 0.02 Cft
Frame 4(15"+15"19+19) x 3/8 0.03 Cft
Top Rail 1x4x3"x1" 0.05 Cft
Vertical Rail 2x7x3"x1" 0.15 Cft
2.00 Cft
Wastage 10% 0.20 Cft
2.20 Cft 0.00 P. Cft -
Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Tower Bolts 9" (228mm) 2.00 Nos 0.00 Each -
Handles 6" (150mm) 2.00 Nos 0.00 Each -
Hook & Clamp 2.00 Nos 0.00 Each -
Screws / Nails 2.00 Doz 0.00 P. Doz -

Page 48
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Wire Gauge
2x1'-2"x2'-1" 4.83 Sft
4x1'-2"x1'-7" 7.33 Sft
12.16 Sft
Wastage 15% 1.82 Sft
13.98 Sft 0.00 Sft -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour

Carpenters 1.50 Nos 0.00 P. Day -


Skilled Cooly 0.75 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -
Rate Per Sft 0.00 = -
27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 49
Item No. 12 First class deodar wood wrought joinery wor
wire gauze doors and windows with 22 SWG
galvanized wire gauze 144 mashes per square
inch (625mm) including iron fittings comple

b) Deodar Wood framing 1" (40mm) thick with


wire gauze fixed in position.
ii) With Springs as Spring Hinges.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4'x6.75' = 27 Sft

Material

1st Class Deodar Wood


Vertical Style 4x6'-6"x4"x1" 1.09 Cft

Horizontal
Top 2x1'-10"x3"x1" 0.12 Cft
Middle 2x1'-10"x1"x1" 0.06 Cft
Lock 2x1'-10"x6"x1" 0.24 Cft
Bottom 2x1'-10"x6"x1" 0.24 Cft
Fillets 2(15"+15"25+25) x 3/8 0.02 Cft
Top Rail 1x4'x3"x1" 0.05 Cft
Vertical Rail 2x7'x3"x1" 0.15 Cft
1.97 Cft
Wastage 10% 0.22 Cft
2.19 Cft 0.00 P. Cft -
Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Tower Bolts 9" (228mm) 2.00 Nos 0.00 Each -
Handles 6" (150mm) 2.00 Nos 0.00 Each -
Hook & Clamp 2.00 Nos 0.00 Each -
Screws / Nails 2.00 Doz 0.00 P. Doz -
Spring 2.00 Nos 0.00 Each -

Page 50
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Wire Gauge
2x1'-2"x2'-1" 4.83 Sft
4x1'-2"x1'-7" 7.33 Sft
12.16 Sft
Wastage 15% 1.82 Sft
13.98 Sft 0.00 Sft -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour

Carpenters 1.50 No 0.00 P. Day -


Skilled Cooly 0.75 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -
Rate Per Sft 0.00 = -
27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 51
Item No. 12 G.I. wire gauze 22 SWG, 12x12 meshes per sq
inch (256mm) fixed to chowkhat with " (20m
thick deodar wood screw and strip.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 3' = 12 Sft

Material

Wood Work
Wood 0.25 Cft 0.00 P. Cft -
Wire gauze 12.00 Sft 0.00 Sft -
Nails L.S. 8.00

Total 8.00
Contractor's Profit & Ove 20 Percent 1.60
Total for 12 Sft. 9.60
Rate Per Sft 9.60 = 0.80
12
Labour

Carpenters 0.50 No 0.00 P. Day -


Skilled Cooly 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -
Rate Per Sft 0.00 = -
12
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. 0.80 Say 0.80


Composite Rate Per Sqm Rs. 8.61 Say 8.60

Page 52
Item No. 12 G.I. wire gauze 22 SWG, 12x12 meshes per
square inch (625mm) fixed to chowkhat with
(12mm) strip on separate frame of deodar wo
2"x2" (50x50mm).

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 2' x 4' = 8 Sft

Material

Deodar Wood

Horizontal Rail 2x4"x2"x2" 0.22 Cft


Vertical Rail 2x2"x2"x2" 0.11 Cft
Strips 2x4"x2"x" 0.05 Cft
Strips 2x1'-8"x2"x" 0.03 Cft
Moulding L.S. 0.06 Cft
0.47 Cft
Wastage 20% 0.09 Cft
0.56 Cft 0.00 P. Cft -
Wire Gauze 144 Mesh/Sqare in CW 4x2 8.00 Sft
Wastage 10% 0.80 Sft
8.80 Cft 0.00 P. Sft -

Fitting

Screws above 1" long 2.00 Doz 0.00 P. Doz -


Nails 0.08 Kg 0.00 P. Kg (0.14)
Wooden Plugs 6.00 Nos 0.50 Each 3.00

Total 2.86
Contractor's Profit & Ove 20 Percent 0.57
Total for 8 Sft. 3.43
Rate Per Sft 3.43 = 0.43
8

Page 53
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Carpenters 0.50 No 0.00 P. Day -


Skilled Cooly 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 8 Sft. -
Rate Per Sft 0.00 = -
8
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. 0.05 Say 0.05

Composite Rate Per Sft Rs. 0.43 Say 0.45


Composite Rate Per Sqm Rs. 4.77 Say 4.75

Page 54
DESCRIPTION OF ITEM NO 13: Making and fixing trellis doors and windows
deodar wood complete.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 18 Sft

Material

Deodar Wood 2.30 Cft 0.00 P. Cft -


Nail 0.126 Kg. 0.00 P. Kg. -
Screws above 1" long 2.50 Doz 0.00 P. Doz -
Hinges 4" (100mm) 4.00 Nos 0.00 Each -
Tower Bolt 9" (225mm) 2.00 Nos 0.00 Each -
Hasp & Staple 1.00 No 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 18 Sft. -
Rate Per Sft 0.00 = -
18
Labour
Carpenter 1.50 No 0.00 P. Day -
Skilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 18 Sft. -
Rate Per Sft 0.00 = -
18
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. 0.05 Say 0.05

Page 55
DESCRIPTION OF ITEM NO 14: Providing & fixing mild steel chowkhat of d
windows, C. Window etc. including hold fast
making and threading holes for hinges etc.
complete

a) M.S. angle iron 1"x1"x" (40x40x6mm)


welded M.S. flat 2"x" (50x6mm)

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material

Structural Steel
M.S. Angle Iron 1"x1"x" (40x40x6mm)
Vertical 2x7 14 Rft
Horizontal 1x4 4 Rft
18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft
18.90 Rft @ 2.32 Lbs/Rft 43.85 Lbs
M.S. Flat 2"x" (50x6mm)
Vertical 2x7 14 Rft
Horizontal 1x4 4 Rft
18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft
18.9 @ 1.68 Lbs/ft 31.75 Lbs
M.S. Flat Patti 1"x1/8" (25x3mm) at
bottom.
4 @ 0.42 Lbs/ft 1.68 Lbs
77.28Lb (3 5.06)Kg 0.00 P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27

Page 56
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Making holes in frame for hinges 4x4 16.00 Nos 0.00 Each -
Welding plate with angle iron 18.00 Nos 0.00 Each -
Welding hold fast with frame 6.00 Nos 0.00 Each -
Welding M.S.Steel bar with frame 2.00 Nos 0.00 Each -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -
Rate Per Sft 0.00 = -
27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 57
Item No. 14 Providing & fixing mild steel chowkhat of d
windows, C. Window etc. including hold fast
making and threading holes for hinges etc.
complete

b) M.S. Tee iron 1"x1"x" (40x40x6mm)


welded with M.S. Flat "x" (12x6mm)

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material

Structural Steel

Tee Iron 1"x1"x" (40x40x6mm)


Vertical 2x7 14 Rft
Horizontal 1x4 4 Rft
18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft
18.90ft @ 2.32 Lbs/ft 44.60 Lbs
M.S. Flat "x" (12x6mm)
18.90ft @ 0.425 Lbs/ft 8.03 Lbs
M.S. Bar " dia 4' @ 0.67 Lbs/ft 2.68 Lbs
55.31Lb (2 5.10) Kg 0.00 P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27

Page 58
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Making holes in frame for hinges 4x4 16.00 Nos 0.00 Each -
Welding plate with angle iron 18.00 Nos 0.00 Each -
Welding hold fast with frame 6.00 Nos 0.00 Each -
Welding M.S.Steel bar with frame 2.00 Nos 0.00 Each -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -
Rate Per Sft 0.00 = -
27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 59
Item No. 15 Providing and fixing M.S. Sheet hollow pres
frame of doors, windows, CW, etc. (Chowkha
only) of 20 SWG welded with M.S. flat
6"x1"x1/8" (150x40x3mm) M.S. hold fast
9"x1"x1/8" (225x25x3mm) welded/ screwed 4"
(100mm) long iron hinges including fitting
chowkhat with cement sand mortar 1:8 and
embedding hold fast in cement concrete 1:2:
complete in all respects.

a) Single Rebate.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 7' = 28 Sft

Material

M.S. Sheet 20 Swg 15"(375mm) wide


18' long x15/12 (5.486x0.380m) 22.50 Kg.
Wastage 10% 2.25 Kg.
24.75 Kg.
SAY 25.00 Kg. Or 0.00 Kg. -
M.S. Flat 6"x"x1/8" (150x6x3mm) 17.02 Kg
3.5 Rft @ 0.531 Lbs/Rft 1.86 Lbs
M.S. Flat hold fast 9"x1"x1/8" (225x25x3mm)
4.5 Rft @ 0.425 Lbs/Rft 1.91 Lbs
3.77Lb (1 .71) Kg 0.00 P. Kg -
Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Screws 3.00 Doz 0.00 P. Doz -
Nails 0.28 Kg. 0.00 P. Kg. -
Welding Charges -
Cement sand mortar ratio 1:8 for
filling hollow space 18'x4'/12"x3/12
including wastage (0.057m)
(5.486x0.100x0.075m) 2.00 Cft

Page 60
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material
Cement 0.20 Bag 0.00 Each -
Sand 2.00 Cft 0.00 P. Cft -
Cement Concrete 1:2:4 for fixing hold fast
Cement 0.08 Bag 0.00 Bag -
Sand 0.20 Cft. 0.00 % Cft. -
Bajri 0.40 Cft. 0.00 % Cft. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 28 Sft. -
Rate Per Sft 0.00 = -
28
Labour

Moulder/ Black Smith 0.50 No 0.00 P. Day -


Cooly 0.50 No 0.00 P. Day -
SKilled Cooly (for Mortor Filling in the
hallow space) 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 28 Sft. -
Rate Per Sft 0.00 = -
28
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. 0.10 Say 0.10

Page 61
Item No. 15 Providing and fixing M.S. Sheet hollow pres
frame of doors, windows, C. window, etc.
(Chowkhat only) of 20 SWG welded with M.S.
6"x1"x1/8" (150x32x3mm) M.S. hold fast
9"x1"x1/8" (225x25x3mm) welded/ screwed 4"
(100mm) long iron hinges including fitting
chowkhat with cement sand mortar 1:8 and
embedding hold fast in cement concrete 1:2:
complete in all respects.

b) Double Rebate.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 7' = 28 Sft

Material

M.S. Sheet 20SWG 17"(432mm) wide


19' longx18x18/17(5.486x0.432)= 25.50 Sft
Wastage 10% 2.55 Sft
28.05 Sft 19.10 Kg 0.00 P. Kg -

M.S. Flat 7.5x1"x1/8(2.30x0.032x0.003)=7 No.


4.50 Rft @ 0.531 Lbs/Rft 2.39 Lbs
M.S. Flat hold fast 9"x1"x1/8"= 6 No
4.50 Rft @ 0.425 Lbs/Rft 1.91 Lbs
4.30Lbs (1 .95) Kg 0.00 P. Kg -
Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Screws 3.00 Doz 0.00 P. Doz -
Nails 0.28 Kg. 0.00 P. Kg. -
Welding Charges -
Cement sand mortar ratio 1:8 for
filling hollow space
18"x11/24x4/12 = (5.486x0.275x0.1m) 2.75 Cft

Page 62
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Cement 0.28 Bag 0.00 Each -


Sand 2.75 Cft 0.00 P. Cft -
Cement Concrete 1:2:4 for (fixing
hold fast)
Cement 0.08 Bag 0.00 Bag -
Sand 0.20 Cft. 0.00 % Cft. -
Bajri 0.40 Cft. 0.00 % Cft. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 28 Sft. -
Rate Per Sft 0.00 = -
28

Moulder/ Black Smith 0.75 No 0.00 P. Day -


Cooly 0.50 No 0.00 P. Day -
SKilled Cooly (for Mortor Filling in the
hollow space) 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 28 Sft. -
Rate Per Sft 0.00 = -
28
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. 1.30 Say 1.30


Composite Rate Per Sqm Rs. 8.49 Say 8.50

Page 63
DESCRIPTION OF ITEM NO 16: Extra for providing & fixing iron double sp
hinges, with brass fittings (it shall inclu
finger plate, 6" tower bolts)

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 21 Sft

Material

4" (100mm) double section spring


hinges iron. 3.00 Nos 0.00 Each -
Brass finger plate 2.00 Nos 0.00 Each -
6" (150mm) brass tower bolt 1.00 No 0.00 Each -
Brass screws 1" (40mm) 2.00 Doz 0.00 P. Doz -
Brass Screw 1" (25mm) 2.50 Doz 0.00 P. Doz -
-

Deduct Cost of Iron Fittings

5" (125mm) Butt Hinges 4.00 Nos 0.50 Each 2.00


9" (225mm) Tower Bolts 2.00 Nos 0.00 Each -
6" (150mm) Handle 2.00 Nos 0.00 Each -
Hinges Chocks 2.00 Nos 0.00 Each -
Door Stops 2.00 Nos 0.00 Each -
Screws 1" 3.00 Doz 0.00 P. Doz -
Screws 1" 3.00 Doz 0.00 P. Doz -
2.00

Total 262.50-112.96 (2.00)


Contractor's Profit & Ove 20 Percent (0.40)
Total for 21 Sft. (2.40)
Rate Per Sft -2.40 = (0.11)
21

Page 64
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Carpenters 0.05 No 0.00 P. Day -


Skilled Cooly 0.05 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -
Rate Per Sft 0.00 = -
21

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. ##### Say -

Composite Rate Per Sft Rs. ##### Say -


Composite Rate Per Sqm Rs. ##### Say (0.20)

Page 65
DESCRIPTION OF ITEM NO 17: Providing and fixing brass spring hinges, t
gauzed doors.

Detail Unit Rate (British System)per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Brass spring hinges Complete with


screws 1 No 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Carpenter 0.05 No 0.00 P. Day -


Skilled Cooly 0.05 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. 0.00 Say -

Composite Rate for Each Rs. 0.00 Say -

Page 66
DESCRIPTION OF ITEM NO 18: Providing and fixing sliding bolt to doors.

i) Iron sliding bolt 10" (250mm) long.

Detail Unit Rate (British System)per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 16 Each

Material

Sliding bolt 10"(250mm) long complete with


screws & nuts. 16 Nos 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Carpenter 1.00 No 0.00 P. Day -


Skilled Cooly 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
16

Composite Rate for Each Rs. 0.00 0.00 Say -


16

Page 67
Item No. 18 Providing and fixing sliding bolt to doors.

ii) Iron sliding bolt 12" (300mm) long.

Detail Unit Rate (British System)per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 16 Each

Material

Sliding bolt 12" (300mm) long complete


with screws with & nuts. 16 Nos 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Carpenter 1.00 No 0.00 P. Day -


Skilled Cooly 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
16

Composite Rate for Each Rs. 0.00 0.00 Say -


16

Page 68
Item No. 18 Providing and fixing sliding bolt to doors.

iii) Brass sliding bolt 10" (250mm) long.

Detail Unit Rate (British System)per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Anaylysis for = 16 Each

Material

Brass sliding bolt 10" (250mm) long


complete with screws & nuts. 16 Nos 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Carpenter 1.00 No 0.00 P. Day -


Skilled Cooly 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
16

Composite Rate for Each Rs. 0.00 0.00 Say -


16

Page 69
Item No. 18 Providing and fixing sliding bolt to doors.

iv) Brass sliding bolt 12" (300mm) long.

Detail Unit Rate (British System)per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 16 Each

Material

Brass sliding bolt 12" (300mm) long


complete with screws & nuts. 16 Nos 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Carpenter 1.00 No 0.00 P. Day -


Skilled Cooly 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
16

Composite Rate for Each Rs. 0.00 0.00 Say -


16

Page 70
DESCRIPTION OF ITEM NO 19: Extra for brass fittings to doors and windo
except for hinges, which shall be of iron.
i) Deodar wood panelled or panelled and glazed
fully glazed.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 7' = 28 Sft

Material (Brass Fittings)


9" (225mm) Tower bolt 3.00 Nos 0.00 Each -
6" (150mm) Handles 3.00 Nos 0.00 Each -
2" (50mm) Butt hinges 2.00 Nos 0.00 Each -
Screws 1" 3.50 Doz 0.00 P. Doz -
-
Deduct Cost of Iron Fittings
9" (225mm) Tower Bolts 3.00 Nos 0.00 Each -
6" (150mm) Handle 3.00 Nos 0.00 Each -
2" (50mm) butt hinges 2.00 Nos 0.00 Each -
Screws above 1" long 3.50 Doz 0.00 P. Doz -
-

Total 222.38-101.04 -
Contractor's Profit & Ove 20 Percent -
Total for 28 Sft. -
Rate Per Sft 0.00 = -
28

Labour
Carpenter 0.04 No 0.00 P. Day -
Skilled Cooly 0.04 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Rate Per Sft 0.00 = -
28

Labour Rate Per Sft Rs. - Say -


Labour Rate Per Sqm Rs. - Say -
Composite Rate Per Sft Rs. 0.08 Say 0.10
Composite Rate Per Sqm Rs. 0.91 Say 0.90

Page 71
Item No. 19 Extra for brass fittings to doors and windo
except for hinges, which shall be of iron.

ii) Deodar wood wire gauzed shutters.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 7' = 28 Sft

Material (Brass Fittings)


9" (225mm) Tower balt 2.00 Nos 0.00 Each -
6" (150mm) Handles 2.00 Nos 0.00 Each -
2" (50mm) butt hinges 2.00 Nos 0.00 Each -
Screws 1" 3.50 Doz 0.00 P. Doz -
-
Deduct Cost of Iron Fittings
9" (225mm) Tower Bolts 2.00 Nos 0.00 Each -
8" (200mm) Handle 2.00 Nos 0.00 Each -
2" (50mm) Butt hinges 2.00 Nos 1.00 Each 2.00
Screws 1" 3.00 Doz 0.00 P. Doz -
2.00

Total 153.75-73.12 = (2.00)


Contractor's Profit & Ove 20 Percent (0.40)
Total for 28 Sft. (2.40)
Rate Per Sft -2.40 = (0.09)
28
Labour
Carpenter 0.04 No 0.00 P. Day -
Skilled Cooly 0.04 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 28 Sft. -
Rate Per Sft 0.00 = -
28
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say -


Composite Rate Per Sqm Rs. ##### Say (0.80)

Page 72
DESCRIPTION OF ITEM NO 20: Extra for providing and fixing, approved qu
rim lock adjustable over the style surface.

Detail Unit Rate (British System)per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Rim lock complete with screws 1.00 No 0.00 Each -


Deduct cost of handle 2.00 Nos 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Carpenter 0.17 No 0.00 P. Day -


Skilled Cooly 0.13 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. 0.00 Say -

Composite Rate for Each Rs. 0.00 Say -

Page 73
DESCRIPTION OF ITEM NO 21: Providing and fixing approved quality morti
lock.

Detail Unit Rate (British System)per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Mortice lock compelte with screws 1.00 No 0.00 Each -


Deduct cost of handles 2.00 Nos 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Carpenter 0.25 No 0.00 P. Day -


Skilled Cooly 0.17 No 0.00 P. Day 14.45

Total 14.45
Sundries 10 Percent 1.45
Total 15.90

Contractor's Profit & Ove 20 Percent 3.18


Total 19.07

Item Rates
Labour Rate for Each Rs. 19.07 Say 19.05

Composite Rate for Each Rs. 19.07 Say 19.05

Page 74
DESCRIPTION OF ITEM NO 22: Providing and fixing expanded metal " to
(12mm to 20mm) mesh 16 gauge.
a) Fixed to chowkhat with 1" (25mm) thick deod
wood strip and screws etc.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 2' = 8 Sft
Material
Deodar Wood
Strips vertical 2x2x"x3/12" 0.08 Cft
Horizontal 2x3-10/12x"x3/12" 0.16 Cft
0.24 Cft
Wastage 20% 0.05 Cft
0.29 Cft
SAY 0.30 Cft 0.00 P. Cft -
Expanded metal 1x4x2 8.00 Sft
Wastage 10% 0.80 Sft
8.80 Sft 0.00 Sft -
Nails / Screws 2.00 Doz 0.00 P. Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 8 Sft. -
Rate Per Sft 0.00 = -
8
Labour
Carpenter 0.25 No 0.00 P. Day -
Skilled Cooly 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 8 Sft. -
Rate Per Sft 0.00 = -
8
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say (0.20)


Composite Rate Per Sqm Rs. ##### Say (1.90)

Page 75
Item No. 22 Providing and fixing expanded metal " to
(12mm to 20mm) mesh 16 gauge.
b) Fixed with 1" (25mm) cover moulding & screw
including deodar wood frame 2"x2" (50x50mm)

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 3' = 12 Sft

Material
Deodar Wood Frame
2 No 4'x2/12"x212" 0.23 Cft
2 No 3'x2/12"x212" 0.17 Cft
Moulding 1x13 2/3'x1/12x2/12 0.20 Cft
0.60 Cft
Wastage 20% 0.12 Cft
0.72 Cft 0.00 P. Cft -
Expended metal 1x4x3 12.00 Sft
Wastage 10% 1.20 Sft
13.20 Sft 0.00 Sft -
Nails / Screws 2.00 Doz 0.00 P. Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 12 Sft. -
Rate Per Sft 0.00 = -
12
Labour
Carpenter 0.50 No 0.00 P. Day -
Skilled Cooly 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 12 Sft. -
Rate Per Sft 0.00 = -
12
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say (0.10)


Composite Rate Per Sqm Rs. ##### Say (1.30)

Page 76
DESCRIPTION OF ITEM NO 23: a Providing and fixing deodar wood almirah 9"
12" (225 to 300mm) depth, including boxing
with back shelves, shutter and brass fittin
complete.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3' x 5' = 15 Sft

Material

Deodar Wood
Sides 2x1'x5'x1/12" 0.84 Cft
Back 1x3'x5'x" 0.94 Cft
Top & Bottom 2x3'x1'x1/12" 0.50 Cft
Plank 3x3'x1'x1/12" 0.75 Cft
Shutters 2x1.5'x5'x1/12" 1.25 Cft
4.28 Cft
Wastage 10% 0.43 Cft
4.71 Cft 0.00 P. Cft -

Fittings Brass
Hings 3" (75mm) 6.00 Nos 0.00 Each -
Hasp & Staple (Brass) 1.00 No 0.00 Each -
Brass Handle 6" (150mm) 2.00 Nos 0.00 Each -
Wooden Plugs 10.00 Nos 0.50 Each 5.00
Nails / Screws L.S. 19.00
Bitumen 1.43 Kg. 0.00 P. Kg. -

Total 24.00
Contractor's Profit & Ove 20 Percent 4.80
Total for 15 Sft. 28.80
Rate Per Sft 28.80 = 1.92
15

Page 77
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Carpenter 2.50 No 0.00 P. Day -


Skilled Cooly 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 15 Sft. -
Rate Per Sft 0.00 = -
15

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. 1.92 Say 1.90


Composite Rate Per Sqm Rs. ##### Say 20.60

Page 78
Item No. 23 Providing and fixing deodar wood almirah 9"
12" (225 to 300mm) depth, with shelves shut
and brass fittings, etc. without boxing & b
complete.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3' x 5' = 15 Sft

Material
Deodar Wood
Plank 3x10x3'x1'x1/12" 0.75 Cft
Shutters 2x1.5'x5'x1/12" 1.25 Cft
2.00 Cft
Wastage 10% 0.20 Cft
2.20 Cft 0.00 P. Cft -
Fittings Brass
Hings 3" (75mm) 6.00 Nos 0.00 Each -
Hasp & Staple (Brass) 1.00 No 0.00 Each -
Brass Handle 6" (150mm) 2.00 Nos 0.00 Each -
Wooden Plugs 6.00 Nos 0.50 Each 3.00
Nails / Screws L.S. 12.00

Total 15.00
Contractor's Profit & Ove 20 Percent 3.00
Total for 15 Sft. 18.00
Rate Per Sft 18.00 = 1.20
15
Labour
Carpenter 1.75 Nos 0.00 P. Day -
Skilled Cooly 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 15 Sft. -
Rate Per Sft 0.00 = -
15
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. 1.20 Say 1.20


Composite Rate Per Sqm Rs. ##### Say 12.90

Page 79
Item No. 24 Providing and fixing class room almirah
consisting of 1" (25mm) thick solid flush s
with deodar wood lipping " (6mm) thick alr
(sterling made) fixed in deodar wood frame
(75x25mm) I/C full hinges C.P. fittings wit
R.C.C. (1:1-:3) shelves 1-" (40mm) thick
coats of painting.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4.5' x 3.5' = 15.75 Sft

Material
Precast reinforced cement concrete
(1:1-"3)
Shelves 2x3-x1-1/8x1/8 0.91 Cft 3.68 P. Cft 3.35
Steel " (12mm) dia
4x3.25 (4x0.975=3.900Rm) 13.00 Rft
5x1 1'/6(5x0.375=1.875Rm) 5.63 Rft
18.63 Rft
Wastage 5% 0.93 Rft
19.56 Rft 1.48 Kg 0.00 Kg -
@ 0.167 Lbs/Rft
Deodar wood frame I/C sawing
2x4'x'x1/12' 0.19 Cft
2x3'xx'x1/12' 0.15 Cft
0.34 Cft
Wastage 35% 0.12 Cft
0.46 Cft 0.00 P. Cft -
1" (25mm) thick solid flush shutter
(Sterling made)
1x3'x4' (1x0.900x1.200 = 1.080) 12.00 Sft
Wastage 5% 0.60 Sft
12.60 Sft 0.00 Sft -
Deodar wood lipping 6mm thick
(Sterling made)
2x4' (2x1.200 = 2.400) 8.00 Rft
2x2x-' (2x2x0.450 = 1.800) 6.00 Rft
14.00 Rft 0.00 Rft -

Page 80
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Full hinges 1" (25mm) I/C screws 2x4 8.00 Nos 0.00 Each -
C.P. dasti I/C screws 2.00 Nos 0.00 Each -
Khunda chapks (Best quality) I/C screws 1.00 No 0.00 Each -
Rawal plug 1-" long 12.00 Nos 0.00 Each -
Screws 1-" long 1.00 Doz 0.00 P. Doz -
Glue 0.20 Kg. 0.00 P.Kg. -
Painting 3 coats 0.428 Gln. 0.00 P. Gln. -

Total 3.35
Contractor's Profit & Ove 20 Percent 0.67
Total for 15.75 Sft. 4.02
Rate Per Sft 4.02 = 0.26
15.75
Labour

For bringing the leaves to proper size


fixing deodar wood lipping with glue
and nail making/ fixing deodar wood
frame & fixing at site with rawal plug &
screws.

Carpenter 1.00 No 0.00 P. Day -


Helper 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 15.75 Sft. -
Rate Per Sft 0.00 = -
15.75

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. 0.26 Say 0.25


Composite Rate Per Sqm Rs. 2.50 Say 2.50

Page 81
DESCRIPTION OF ITEM NO 25: Providing and fixing wooden box type ward r
22" (550mm) deep including " (20mm) thick
boxing and shelves, hanger rods, hard board
drawers, brass fitting locking arrangements
handles internal bolts shoe rods, etc. incl
three coats of enamel paints.
i) Partal wood boxing and deodar wood shelves
leaves etc.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.5' = 26 Sft

Material

Partal Wood
Boxing
Side 2x6-1/3x22/12x3/48 1.45 Cft
Top & Bottom 2x4 22/12x3/48 0.92 Cft
Foot Rack 1x3-7/8x22/12x3/48 0.44 Cft
Vertical Style 1x5x22/12x3/48 0.57 Cft
Strips 6x22/12x1/8x3/48 0.09 Cft
Back 2x1x22/12x3/48 0.34 Cft
3.81 Cft
Wastage 15% 0.57 Cft
4.38 Cft 0.00 P. Cft -
Shutters Deodar Wood
1x1-2/3x6x1/12 0.91 Cft
1x2-1/3x6x1/12 1.26 Cft
2.17 Cft
Wastage 15% 0.33 Cft
2.50 Cft 0.00 P. Cft -
Hard Board
4x6 26.00 Sft
Wastage 10% 2.60 Sft
28.60 Sft 0.00 Sft -
Sawing Charges
6.88x10 68.80 Sft 0.00 Sft -

Page 82
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Fittings

Hings 4" (100mm) 6.00 Nos 0.00 Each -


Handle 2.00 Nos 0.00 Each -
Tie rod welding fixing arragement 2.25 Nos 0.00 Each -
Hanger hook including pull out rod 2.00 Nos 0.00 Each -
Tower bolt 4" (100mm) 1.00 Nos -0.08 Each (0.08)
Bitumen Painting 1.43 Kg. 0.00 Each -

Total (0.08)
Contractor's Profit & Ove 20 Percent (0.02)
Total for 26 Sft. (0.10)
Rate Per Sft -0.10 = (0.00)
26
Labour

Carpenters 4.00 No 0.00 P. Day -


Skilled Cooly 2.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -
Rate Per Sft 0.00 = -
26

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say (3.70)


Composite Rate Per Sqm Rs. ##### Say (39.90)

Page 83
Item No. 25 Providing and fixing wooden box type ward r
22" (550mm) deep including " (20mm) thick
boxing and shelves, hanger rods, hard board
drawers, brass fitting locking arrangements
handles internal bolts shoe rods, etc. incl
three coats of enamel paints.
ii) Deodar wood boxing and shelves & leaves etc

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 8' x 5' = 40 Sft

Material

Deodar Wood
Boxing
Vetical Side 2x8x22/12x3/48 1.83 Cft
Control Side 1x7-7/8x22/12x3/48 0.90 Cft
Horizontal T&B 2x4 11/12x22/12x3/48 1.13 Cft
Shelves 5x2x22/12x3/48 1.15 Cft
Vertical 1x1x22/12x3/48 0.17 Cft
Shoes 2xx1/5x1/12 0.02 Cft
Sutter 2x2 3/5x8x1/12 3.47 Cft
Strips 2x8x1/12x1/24 0.06 Cft
Strips 2x5x1/12x1/24 0.03 Cft
8.76 Cft
Wastage 15% 1.31 Cft
10.07 Cft 0.00 P. Cft -
Hard Wood Board
Back 5x8 40.00 Sft
Wastage 10% 4.00 Sft
44.00 Sft 0.00 Sft -
Sawing Charges :
10.20x10 102.00 Sft 0.00 Sft -

Bitumen Painting 2 Coat 1.43 Kg. 0.00 Each -


Painting 3 Coats 0.27 Kg. 0.00 P. Gln. -

Page 84
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Fittings
Hings 4" (100mm) 6.00 Nos -0.10 Each (0.60)
Handle 2.00 Nos 0.00 Each -
Tie rod welding fixing arragement -
Hanger hook including full out rod 2.00 Nos 0.00 Each -
Screws 4.00 Doz 0.00 P. Doz -
Tower bolt 4" (100mm) 1.00 Nos -0.08 Each (0.08)
Nail 0.19 Kg 0.00 P. Kg -
Locking arrangement 1.00 Nos 0.00 Each -

Total (0.68)
Contractor's Profit & Ove 20 Percent (0.14)
Total for 40 Sft. (0.82)
Rate Per Sft -0.82 = (0.02)
40

Carpenters 6.00 Nos 0.00 P. Day -


Skilled Cooly 2.00 Nos 0.00 P. Day -
Painter 1.00 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 40 Sft. -
Rate Per Sft 0.00 = -
40

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say (0.20)


Composite Rate Per Sqm Rs. ##### Say (2.80)

Page 85
Item No. 26 Providing/ fixing ward robe 22" (550mm) dee
consisting of RCC shelves 1-" (40mm) thick
(12mm) thick vin board boxing and back (one
ply) vin board shutter " (20mm) thick I/c
wood lipping "(6mm) on all edges fixes I/c
wood frame 3"x1" with hanger rod in centre
drawers at bottom and openable shutter on u
portion I/c full hinges C.P. fitting and pa
coats.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 7.5' x 7' = 52.50 Sft

Material
RCC shelves (Precast RCC 1x1-x3 top
and bottom
2x7-x2x1/8 3.62 Cft
4x2-x2x1/8 2.50 Cft
6.12 Cft 0.00 P. Cft -
Steel Reinforcement
6.12x1.50 9.18 Kg 0.00 P. Kg -

" thick vin board (one side ply) for


boxing.
Top/ Bottom 6x2x2-x1-7/8 50.63 Sft
Side 6x2x1-1/8x1-7/8 25.31 Sft
Back 6x2-x1-1/8 15.18 Sft
Top/ Bottom 3x2x2-x1-7/8 25.31 Sft
Vertical 6x2x1-x1-7/8 28.12 Sft
Side 2x4x1-7/8 15.00 Sft
Back 3x2x2-x1- 16.87 Sft
Back 1x2-x4 9.00 Sft
185.42 Sft
Wastage 10% 18.54 Sft
203.96 Sft 0.00 Sft -
Vin board " thick on both side ply
6x2-x1- 16.87 Sft
3x4x2- 27.00 Sft
43.87 Sft
Wastage 10% 4.38 Sft
48.25 Sft 0.00 Sft -

Page 86
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Deodar Wood
Frame 4x7x3/12x1/12 0.58 Cft
Frame 4x7-x3/12x1/12 0.62 Cft
Lipping 3x6x2-x1/16x1/24 0.11 Cft
Lipping 6x2x1-1/8x1/16x1/24 0.04 Cft
Lipping 2x3x4x1/16x1/24 0.06 Cft

For drawers side supporting


3x2x1-7/8x1/12x1/24 0.04 Cft
Drawers 3x2-x1-1/8x1/24 0.32 Cft
Side 2x3x1-7/8x1-1/8x1/24 0.53 Cft
2.30 Cft
Wastage 35% 0.81 Cft
3.11 Cft 0.00 P. Cft -
Hard Board for drawers
3x2-x1-7/8(3x0.686x0.573=1.179 12.65 Sft
Wastage 10% 1.26 Sft
13.91 Sft 0.00 Sft -
Full hinges " (20mm) wide (Imported)
3x4 (3x1.219 = 3.657) 12.00 Rft
3x1-1/8 (3x0.343 = 1.029) 3.37 Rft
15.37 Rft
Wastage 5% (Add Wastage 5%) 0.76 Rft
16.13 Rft 0.00 Rft -

C.P. Handle 9.00 Nos 0.00 Each -


Catcher (Germany) 9.00 Nos 0.00 Each -
China Lock (Glone) 3.00 Nos 0.00 Each -
Rawal Plug 1" (40mm) 30.00 Nos 0.00 Each -
Screws above 1" long 2.50 Doz 0.00 P. Doz -
C.P. Hanger rod with 2 hooks 1.00 No 0.00 Each -
C.P. Hooks 2.00 Nos 0.00 Each -

Page 87
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Glue 2.00 Kg 0.00 P. Kg -


Nail L.S. 32.00
Painting 4(7 x 7) 2.86 Gln. 0.00 P. Gln. -

Total 32.01
Contractor's Profit & Ove 20 Percent 6.40
Total for 52.50 Sft. 38.41
Rate Per Sft 38.41 = 0.73
52.50
Labour

Labour for making ward robe complete 52.50 Sft 29.00 Sft 1,522.50

Total 1,522.50
Sundries 10 Percent 152.25
Total 1,674.75

Contractor's Profit & Ove 20 Percent 334.95


Total 2,009.70
Rate Per Sft 2009.70 = 38.28
52.50

Item Rates
Labour Rate Per Sft Rs. ##### Say 38.30
Labour Rate Per Sqm Rs. ##### Say 411.90

Composite Rate Per Sft Rs. ##### Say 64.75


Composite Rate Per Sqm Rs. ##### Say 696.85

Page 88
DESCRIPTION OF ITEM NO 27: Providing and fixing chowkhat for doors, wi
& C. Windows including hold fast etc.
a) Teak Wood.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material

Teak Wood
Top Rail 1x4x3"x4" 0.45 Cft
Vertical Rail 2x7x3"x4" 1.33 Cft
1.78 Cft
Wastage 12% 0.22 Cft
2.00 Cft 0.00 P. Cft -
Iron hold fast 6.00 Nos 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour

Carpenter 0.70 No 0.00 P. Day -


Skilled Cooly 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 27 Sft. -
Rate Per Sft 0.00 = -
27

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 89
Item No. 27 Providing and fixing chowkhat for doors win
& C. Windows including hold fast etc.
b) Deodar Wood.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material

For Frame
Top Rail 1x4'x3"x4" 0.45 Cft
Vertical Rail 2x7'x3"x4" 1.33 Cft
1.78 Cft
Wastage 15% 0.27 Cft
2.05 Cft 0.00 P. Cft -
Iron hold fast 6.00 Nos 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour

Carpenter 0.50 No 0.00 P. Day -


Skilled Cooly 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 27 Sft. -
Rate Per Sft 0.00 = -
27

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 90
Item No. 27 Providing and fixing chowkhat for doors, wi
& C. Windows including hold fast etc.
c) Shisham Wood.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material
Shishim Wood
Top Rail 1x4'x3"x4" 0.45 Cft
Vertical Rail 2x7'x3"x4" 1.33 Cft
1.78 Cft
Wastage 15% 0.27 Cft
2.05 Cft 0.00 P. Cft -
Iron hold fast 6.00 Nos 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour

Carpenter 0.50 No 0.00 P. Day -


Skilled Cooly 0.40 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 27 Sft. -
Rate Per Sft 0.00 = -
27

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. 0.05 Say 0.05

Page 91
DESCRIPTION OF ITEM NO 28:
Making & fixing deodar wood planking in eav
boards etc. planed on both side related & f
including nails & screws, bolt & brackets.
a) 1" (25mm) Thick.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 100 Sft

Material

Deodar Wood 9.50 Cft 0.00 P. Cft -


Nail & Screws bolt and brackets L.S. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
100
Labour

Carpenters 4.00 Nos 0.00 P. Day -


Skilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 100 Sft. -
Rate Per Sft 0.00 = -
100

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 92
Item No. 28 Making & fixing deodar wood planking in eav
boards etc. planed on both side related & f
including nails & screws, bolt & brackets.

b) " (20mm) Thick.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 100 Sft

Material

Deodar Wood 7.12 Cft 0.00 P. Cft -


Asscessories for fixing L.S. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
100
Labour

Carpenters 4.00 Nos 0.00 P. Day -


Skilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 100 Sft. -
Rate Per Sft 0.00 = -
100

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 93
Item No. 28 Making & fixing deodar wood planking in eav
boards etc. planed on both side related & f
including nails & screws, bolt & brackets.

c) " (12mm) Thick

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 100 Sft

Material

Deodar Wood 4.75 Cft 0.00 P. Cft -


Asscessories for fixing L.S. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
100
Labour

Carpenters 4.00 Nos 0.00 P. Day -


Skilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 100 Sft. -
Rate Per Sft 0.00 = -
100

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. 0.05 Say 0.05

Page 94
DESCRIPTION OF ITEM NO 29:
Making and fixing deodar wood shelves,
including brackets.

i) 1" (25mm) Thick.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 100 Sft

Material

Deodar Wood 9.50 Cft 0.00 P. Cft -


Accessoires for fitting L.S. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
100
Labour

Carpenters 4.00 Nos 0.00 P. Day -


Skilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 100 Sft. -
Rate Per Sft 0.00 = -
100

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 95
Item No. 29 Making and fixing deodar wood shelves,
including brackets.

ii) 1" (40mm) Thick

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 100 Sft

Material

Deodar Wood 14.25 Cft 0.00 P. Cft -


Asscessories for fixing L.S. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
100

Labour

Carpenters 4.00 Nos 0.00 P. Day -


Skilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 100 Sft. -
Rate Per Sft 0.00 = -
100

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. 0.05 Say 0.05

Page 96
Item No. 29 Making and fixing deodar wood shelves,
including brackets.

iii) 2" (50mm) Thick.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 100 Sft

Material

Deodar Wood 19.00 Cft 0.00 P. Cft -


Asscessories for fixing L.S. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
100
Labour

Carpenters 4.00 Nos 0.00 P. Day -


Skilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 100 Sft. -
Rate Per Sft 0.00 = -
100

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 97
DESCRIPTION OF ITEM NO 30: a) Making and fixing cleats for doors and wind
including hinges and screws.

Detail Unit Rate (British System)per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 10 Nos

Material

Hinges 2" (50mm) 10.00 Nos 0.00 Each -


Screws 1" (25mm) 3.50 Doz 0.00 P. Doz -
Deodar wood 0.21 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Carpenters 0.40 No 0.00 P. Day -


Skilled Cooly 0.20 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
10

Composite Rate for Each Rs. 0.00 -0.25 Say (0.20)


10

Page 98
Item No. 30 Making and fixing cleats with brass hooks f
ventilator.

Detail Unit Rate (British System)per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Brass hooks 1 No 0.00 Each -


Deodar Wood 0.01 Cft 0.00 P. Cft -
Screws/ Nails 2.00 Nos 0.00 P. Doz 0.44

Total 0.44
Contractor's Profit & Ove 20 Percent 0.09
Total 0.53

Labour for 1.25 Nos.

Carpenter 0.05 No 0.00 P. Day -


Skilled Cooly 0.05 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
1.25

Composite Rate for Each Rs. 0.48 Say 0.50

Page 99
Item No. 30 Providing and fixing door stops of 1" (40m
dia rubber block.

Detail Unit Rate (British System)per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 30 Nos

Material

Door rubber stopper 30.00 Nos 0.00 Each -


Gutty 30.00 Nos 0.00 Each -
Screws 2.50 Doz 0.00 P. Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Carpenter 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
30

Composite Rate for Each Rs. 0.00 -0.10 Say (0.10)


30

Page 100
Item No. 30 Providing and fixing G.I. hook with clamps
doors.

Detail Unit Rate (British System)per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

G.I. Hook 1.00 No 0.00 Each -


Gutty 1.00 No 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour (Labour for 30 No.)

Carpenter 0.08 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
30

Composite Rate for Each Rs. 0.00 Say -

Page 101
DESCRIPTION OF ITEM:
Item No. 31 Hard wood railing of any shape and design
including bends and corners fixed in positi
including polishing complete as directed
by Engineer Incharge.

a) Shisham Wood.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 12 Rft

Material

Shisham wood 0.90 Cft 0.00 P. Cft -


Sand paper 3.00 Nos 0.00 Each -
Polishing material 0.075 Kg. 0.00 P. Kg. -

Total -
Contractor's Profit & Ove 20 Percent -
Total 12 Rft. -
Rate Per Rft 0.00 = -
12
Labour

Carpenters 1.50 No 0.00 P. Day -


Skilled Cooly 0.75 No 0.00 P. Day -
Polisher 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 12 Rft. -
Rate Per Rft 0.00 = -
12
Item Rates
Labour Rate Per Rft Rs. - Say -
Labour Rate Per Rm Rs. - Say -

Composite Rate Per Rft Rs. - Say -


Composite Rate Per Rm Rs. - Say -

Page 102
Item No. 31 Hard wood railing of any shape and design
including bends and corners fixed in positi
including polishing complete as directed
by Engineer Incharge.

b) Teak Wood.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 10 Rft

Material

Teak wood 0.90 Cft 0.00 P. Cft -


Sand paper 3.00 Nos 0.00 Each -
Polishing material 0.075 Kg. 0.00 P. Kg. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 10 Rft. -
Rate Per Rft 0.00 = -
10
Labour

Carpenters 1.00 No. 0.00 P. Day -


Skilled Cooly 0.50 No 0.00 P. Day -
Polisher 0.20 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 10 Rft. -
Rate Per Rft 0.00 = -
10

Item Rates
Labour Rate Per Rft Rs. - Say -
Labour Rate Per Rm Rs. 0.01 Say -

Composite Rate Per Rft Rs. - Say -


Composite Rate Per Rm Rs. 0.01 Say -

Page 103
DESCRIPTION OF ITEM NO 32:
Deodar wood dado or Picture Rail 3"x1"
(50x40mm) as per approved design including
moulding and fixed in place, cost of screws
plugs and painting complete.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 10 Rft

Material
Deodar wood 0.60 Cft 0.00 P. Cft -
Sand paper 1.00 Sht 0.00 P. Sht -
Rawal Plugs 0.50 No 0.00 Each -
Screws 0.50 Doz 0.00 P. Doz -
Polishing material 0.038 Kg. 0.00 P. Kg. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 10 Rft. -
Rate Per Rft 0.00 = -
10
Labour

Carpenter 0.50 No 0.00 P. Day -


Skilled Cooly 0.25 No 0.00 P. Day -
Polisher 0.10 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 10 Rft. -
Rate Per Rft 0.00 = -
10

Item Rates
Labour Rate Per Rft Rs. - Say -
Labour Rate Per Rm Rs. - Say -

Composite Rate Per Rft Rs. ##### Say -


Composite Rate Per Rm Rs. ##### Say (0.10)

Page 104
DESCRIPTION OF ITEM NO 33: Sawing wood by hand.

a) Soft wood (Deodar Kail, Chir)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 300 Sft

Labour

Sawyer 1.50 Nos 0.00 P. Day -


Skilled Cooly 1.50 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 x 100 =154.28 0.02
300

Labour Rate Per Sqm Rs. 0.00 Say -

Page 105
Item No. 33: Sawing wood by hand.

b) Hard Wood (Shisham, Kikar, Sal or Teak)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit Amount
Rate Analysis for = 450 Sft

Labour

Sawyer 3.00 Nos 0.00 P. Day -


Skilled Cooly 3.00 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 x 100=205.7 S -
450

Labour Rate Per Sqm Rs. 0.00 Say -

Page 106
DESCRIPTION OF ITEM NO 34: Sawing wood by machine.

a) Soft Wood.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 300 Sft

Labour

Sawyer 1.00 No 0.00 P. Day -


Skilled Cooly 0.77 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 x 100=94.97 Say (0.01)
300

Labour Rate Per Sqm Rs. 0.00 Say -

Page 107
Item No. 34 Sawing wood by machine.

b) Hard Wood.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 300 Sft

Labour

Sawyer 1.50 Nos 0.00 P. Day -


Skilled Cooly 1.16 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. 0.00 x 100=142.62 S -
300 -

Labour Rate Per Sqm Rs. 0.00 Say -

Page 108
DESCRIPTION OF ITEM NO 35: Making and fixing sun shade of deodar wood
including fixing brackets.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 5 Sft

Material
Deodar Wood
Horizontal Planks
Top 4x5x1/3x1/24 0.28 Cft
Vertical 2x1x1/6x5/68 0.06 Cft
Supports along sun shade 0.04 Cft
2x3/2x1/8x5/48
Suporting brackets 2x1x1/8x5/48 0.03 Cft
Front ears hard strips 1x5x1/4x1/12 0.10 Cft
0.51 Cft
Wastage 10% 0.05 Cft
0.56 Cft 0.00 P. Cft -
Sawing & Nails L.S. 8.00

Total 8.00
Contractor's Profit & Ove 20 Percent 1.60
Total for 5 Sft. 9.60
Rate Per Sft 9.60 = 1.92
5
Labour
Carpenter 0.25 No 0.00 P. Day -
Cooly Skilled 0.10 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 5 Sft. -
Rate Per Sft 0.00 = -
5
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. 1.92 Say 1.90


Composite Rate Per Sqm Rs. ##### Say 20.65

Page 109
DESCRIPTION OF ITEM NO 36: Making and fixing 1" (25mm) thick Kail or C
wooden notice board with frame.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 18 Sft

Material

Kail or Chir Wood 1.64 Cft 0.00 P. Cft -


Nails 0.093 Kg. 0.00 P. Kg. -
Glue 0.075 Kg. 0.00 P. Kg. -
Iron Hook 1.00 No. 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 18 Sft. -
Rate Per Sft 0.00 = -
18
Labour

Carpenter 0.75 No 0.00 P. Day -


Cooly Skilled 0.75 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 18 Sft. -
Rate Per Sft 0.00 = -
18

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. 0.01 Say -

Page 110
DESCRIPTION OF ITEM NO 37: Making deodar Punkha Pole = 10'x6"x6"
(3.047x0.150x0.150M).

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

Deodar wood 2.50 Cft 0.00 P. Cft -


Hooks 2.00 Doz 0.00 P. Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Carpenter 0.20 No 0.00 P. Day -


Cooly Skilled 0.10 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. - Say -

Composite Rate for Each Rs. 0.00 Say -

Page 111
DESCRIPTION OF ITEM NO 38: Dismantling and refixing eaves boards.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 70 Rft

Labour

Carpenter 1.00 No 0.00 P. Day -


Cooly Skilled 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate Per Rft Rs. 0.00 - Say -
70

Labour Rate Per Rm Rs. 0.00 Say -

Page 112
DESCRIPTION OF ITEM NO 39: Making wooden stair cases complete 2' to 3'
915mm) wide frame 1" (40mm) thick planks o
deodar wood, including hand rails.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 15 Rft
Material
Deodar Wood
Detail of Deodar Wood
2x5/6x15x1/8 3.12 Cft
Stops 14x2x1/8x5/6 3.65 Cft
and Rail 2x15xx 1.88 Cft
and Rail 2x4x3xx 1.50 Cft
10.15 Cft
Wastage L. S 0.35 Cft
10.50 Cft 0.00 P. Cft -
Nails 0.93 Kg 0.00 P. Kg -
Bolts " to 3" (12 to 76mm) long 5.880 Kg. 0.00 P. Kg -
Steel rods dia 3x3'-6" = 10.5 Rft 15.3Lb (7 .5Kg) 0.00 P. Kg -
Washers 12.00 Nos 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 15 Rft. -
Rate Per Rft 0.00 = -
15
Labour
Carpenter 2.00 Nos 0.00 P. Day -
Blacksmith 0.50 No 0.00 P. Day -
Hammer-man 0.50 No 0.00 P. Day -
Cooly Skilled 2.00 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 15 Rft. -
Rate Per Rft 0.00 = -
15
Item Rates
Labour Rate Per Rft Rs. - Say -
Labour Rate Per Rm Rs. 0.01 Say -

Composite Rate Per Rft Rs. ##### Say (7.30)


Composite Rate Per Rm Rs. ##### Say (24.00)

Page 113
DESCRIPTION OF ITEM NO 40: Providing and fixing partition including fr
a - (i) Sheets on one side of frame work.
Hard Board.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 128 Sft
Material
Hard Board Sheet
1x8x16 128.00 Sft
Wastage 5% 6.40 Sft
134.40 Sft 0.00 Sft -
Deodar Wood & other Accessories
Frame work 2x16x3"x2" 1.67 Cft
Horizontal post 1x16x2"x2" 0.56 Cft
2x8x3"x2" 0.83 Cft
3x8x2"x2" 0.83 Cft
3.89 Cft
Wastage 15% 0.58 Cft
4.47 Cft 0.00 P. Cft -
Nails of all sorts 0.47 Kg 0.00 P. Kg -
Screws 2.00 Doz 0.00 P. Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Labour
Carpenter 1.00 Nos 0.00 P. Day -
Cooly Skilled 1.00 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per 100 Sft Rs. ##### Say (1.00)


Composite Rate Per Sqm Rs. ##### Say (0.10)

Page 114
Item No. 40 Providing and fixing partition including fr
a - (ii) Ply wood " (6mm) thick.
One Side.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 128 Sft
Material
Ply Wood 1x8'x16 128.00 Sft
Wastage 5% 6.40 Sft
134.40 Sft 0.00 Sft -
Deodar Wood
Frame work 2x16x3"x2" 1.67 Cft
Horizontal post 1x16x2"x2" 0.56 Cft
Vertical post 3x8x2"x2" 0.83 Cft
Vertical post 3x8x2"x2" 0.83 Cft
3.89 Cft
Wastage 15% 0.58 Cft
4.47 Cft 0.00 P. Cft -
Nails of all sorts 0.47 Kg 0.00 Kg -
Screws 2.00 Doz 0.00 P. Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Labour
Carpenter 1.00 Nos 0.00 P. Day -
Cooly Skilled 1.00 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per 100 Sft Rs. ##### Say (1.00)


Composite Rate Per Sqm Rs. ##### Say (0.10)

Page 115
Item No. 40 Providing and fixing partition including fr
a - (iii) Masonite sheet.
One Side.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 128 Sft

Material
Masonite sheet 1x8x16 128.00 Sft
Wastage 5% 6.40 Sft
134.40 Sft 0.00 Sft -
Deodar Wood & other Accessories
Frame work 2x16x3"x2" 1.67 Cft
Horizontal post 1x16x2"x2" 0.56 Cft
2x8x3"x2" 0.83 Cft
3x8x2"x2" 0.83 Cft
3.89 Cft
Wastage 15% 0.58 Cft
4.47 Cft 0.00 P. Cft -
Nails of all sorts 0.47 Kg 0.00 P. Kg -
Screws 2.00 Doz 0.00 P. Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Labour
Carpenter 1.00 Nos 170.00 P. Day 170.00
Cooly Skilled 1.00 Nos 85.00 P. Day 85.00
Total 255.00
Sundries 10 Percent 25.50
Total 280.50
Contractor's Profit & Ove 20 Percent 56.10
Total for 128 Sft. 336.60
Rate Per Sft 336.60 100 262.97
128
Item Rates
Labour Rate Per 100 Sft Rs. ##### Say 262.95
Labour Rate Per Sqm Rs. ##### Say 28.30

Composite Rate Per 100 Sft Rs. ##### Say 261.90


Composite Rate Per Sqm Rs. ##### Say 28.20

Page 116
Item No. 40 Providing and fixing partition including fr
b (1) Sheets on both sides of frame work.
Hard Board.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 128 Sft
Material
Hard Board Sheet
2 x 16 x 8 256.00 Sft
Wastage 5% 12.80 Sft
268.80 Sft 0.00 Sft -
Deodar Wood & other Accessories
Horizontal Post.
2x16x3"x2" 1.67 Cft
1x16x2"x2" 0.56 Cft
Vertical post 2x8x3"x2" 0.83 Cft
3x8x2"x2" 0.83 Cft
3.89 Cft
Wastage 15% 0.58 Cft
4.47 Cft 0.00 P. Cft -
Nails of all sorts 0.70 Kg 0.00 P. Kg -
Screws of all sorts 2.00 Doz 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Labour
Carpenter 1.20 Nos 0.00 P. Day -
Cooly Skilled 1.20 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per 100 Sft Rs. ##### Say (1.00)


Composite Rate Per Sqm Rs. ##### Say (0.10)

Page 117
Item No. 40 Providing and fixing partition including fr
b - (ii) Ply wood. " (6mm) thick

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 128 Sft

Material
Ply Wood Sheet 2 x 16 x 8 (2 x 4.876 x 256.00 Sft
2.438) = 23.78 M
Wastage 5% 12.80 Sft
268.80 Sft 0.00 Sft -
Deodar Wood for frame work
Horizontal post 2x16x3"x2" 1.67 Cft
Cross 1x16x2"x2" 0.56 Cft
Vertical post 2x8x3"x2" 0.83 Cft
Vertical post 3x8x2"x2" 0.83 Cft
3.89 Cft
Wastage 15% 0.58 Cft
4.47 Cft 0.00 P. Cft -
Nails of all sorts 0.70 Kg 0.00 P. Kg -
Screws 3.00 Doz 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Labour
Carpenter 1.20 Nos 0.00 P. Day -
Cooly Skilled 1.20 Nos 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. ##### Say -

Composite Rate Per 100 Sft Rs. ##### Say (1.60)


Composite Rate Per Sqm Rs. ##### Say (0.10)

Page 118
Item No. 40 Providing and fixing partition including fr
b - (iii) Masonite sheet.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 128 Sft

Material
Masonite sheet 2x16'x8' 256.00 Sft
Wastage 5% 12.80 Sft
268.80 Sft 0.00 Sft -
Deodar Wood & other Accessories
Horizontal Post.
2x16x3"x2" 1.67 Cft
1x16x2"x2" 0.56 Cft
Vertical post 2x8x3"x2" 0.83 Cft
3x8x2"x2" 0.83 Cft
3.89 Cft
Wastage 15% 0.58 Cft
4.47 Cft 0.00 P. Cft -
Nails of all sorts 0.70 Kg 0.00 P. Kg -
Screws 2.00 Doz 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Rate Per Sft 0.00 100 -
128
Labour
Carpenter 1.20 Nos 0.00 P. Day -
Cooly Skilled 1.20 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Rate Per Sft 0.00 100 -
128
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. ##### Say -

Composite Rate Per 100 Sft Rs. ##### Say (1.00)


Composite Rate Per Sqm Rs. ##### Say (0.10)

Page 119
DESCRIPTION OF ITEM NO 41: Providing and fixing ceiling including fram
i) Hard Board.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 192 Sft

Material
Hard Board 16x12 192.00 Sft 0.00 Sft -

Partal Wood
7x16x3"x1" 3.50 Cft
9x16x3"x1" 3.38 Cft
6.88 Cft
Wastage 10% 0.69 Cft
7.57 Cft 0.00 P. Cft -
Hard Wood Gutti 32.00 Nos 0.00 Each -
Screws 3.00 Doz 0.00 P. Doz -
Nail 0.70 Kg 0.00 P. Kg -
Cement for grouting 0.178 Bag 0.00 P. Bag -
M.S clamp 4.00 Nos 0.00 Each -
M.S hook 4.00 Nos 0.00 Each -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 192 Sft. -
Rate Per Sft 0.00 100 -
192
Labour
Carpenter 3.00 Nos 0.00 P. Day -
Cooly Skilled 2.00 Nos 0.00 P. Day -
Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 192 Sft. -
Rate Per Sft 0.00 100 -
192
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per 100 Sft Rs. ##### Say (1.00)


Composite Rate Per Sqm Rs. ##### Say (0.10)

Page 120
Item No. 41 Providing and fixing ceiling including fram
ii) Chip Board Sheets.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 192 Sft

Material
Chip Board 1x16x12 192.00 Sft 0.00 Sft -

Partal Wood & other Accessories


Partal Wood.
7x16x3"x1" 3.50 Cft
9x16x3"x1" 3.38 Cft
6.88 Cft
Wastage 10% 0.69 Cft
7.57 Cft 0.00 P. Cft -
Wooden Hand Gutti 32.00 Nos 0.00 Each -
Screws 3.00 Doz 0.00 P. Doz -
Nail 0.70 Kg 0.00 P. Kg -
Cement for grouting 0.178 Bag 0.00 P. Bag -
M.S clamp 4.00 Nos 0.00 Each -
M.S hook 4.00 Nos 0.00 Each -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 192 Sft. -
Rate Per Sft 0.00 100 -
192
Labour
Carpenter 3.00 Nos 0.00 P. Day -
Cooly Skilled 2.00 Nos 0.00 P. Day -
Cooly 1.00 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 192 Sft. -
Rate Per Sft 0.00 100 -
192
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Composite Rate Per 100 Sft Rs. ##### Say (1.00)
Composite Rate Per Sqm Rs. ##### Say (0.10)

Page 121
Item No. 41 Providing and fixing ceiling including fram
work.
iii) Ply Wood " (6mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 192 Sft
Material
Ply Wood " (6mm) 12x16 192.00 Sft 0.00 Sft -

Partal Wood & other Accessories


Partal Wood :
7x16x3"x1" 3.50 Cft
9x16x3"x1" 3.38 Cft
6.88 Cft
Wastage 10% 0.69 Cft
7.57 Cft 0.00 P. Cft -
Wooden Hand Gutti 32.00 Nos 0.00 Each -
Screws 3.00 Doz 0.00 P. Doz -
Nail 0.70 Kg 0.00 P. Kg -
Cement for grouting 0.178 Bag 0.00 P. Bag -
M.S clamp 4.00 Nos 0.00 Each -
M.S hook 4.00 Nos 0.00 Each -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 192 Sft. -
Rate Per Sft 0.00 100 -
192
Labour
Carpenter 3.00 Nos 0.00 P. Day -
Cooly Skilled 2.00 Nos 0.00 P. Day -
Cooly 1.00 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Rate Per Sft 0.00 100 -
192
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Composite Rate Per 100 Sft Rs. ##### Say (1.00)
Composite Rate Per Sqm Rs. ##### Say (0.10)

Page 122
Item No. 41 Providing and fixing ceiling including fram
iv) Masonite Sheet.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 192 Sft
Material
Masonite Sheet 1x16x12 192.00 Sft 0.00 Sft -

Partal Wood & other Accessories


Partal Wood.
7x16x3"x1" 3.50 Cft
9x16x3"x1" 3.38 Cft
6.88 Cft
Wastage 10% 0.69 Cft
7.57 Cft 0.00 P. Cft -
Wooden Hand Gulli 32.00 Nos 0.00 Each -
Screws 3.00 Doz 0.00 P. Doz -
Nail 0.70 Kg 0.00 P. Kg -
Cement for grating 0.178 Bag 0.00 P. Bag -
M.S clamp 4.00 Nos 0.00 Each -
M.S hook 4.00 Nos 0.00 Each -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 192 Sft. -
Rate Per Sft 0.00 100 -
192
Labour
Carpenter 3.00 Nos 0.00 P. Day -
Cooly Skilled 2.00 Nos 0.00 P. Day -
Cooly Unskilled 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 192 Sft. -
Rate Per Sft 0.00 100 -
192
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per 100 Sft Rs. ##### Say (1.00)


Composite Rate Per Sqm Rs. ##### Say (0.10)

Page 123
Item No. 42 Providing and fixing thermopore false ceili
including wooden frame panelling, cost of M
clamps, making holes in walls and repairing
damaged surface, complete in all respects.

a) Deodar wood frame panelling.


i) " (20mm) Thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 12' x 12' = 144 Sft

Material

Thermopore " thick 144.00 Sft


Wastage 5% 7.20 Sft
151.20 Sft 0.00 Sft -
Deodar Wood
Frame Main 3x12x3"x2" 1.53 Cft
Cross 3x12x1"x2" 0.77 Cft
Wooden Strips 12x1"x" 0.25 Cft
2.55 Cft
Wastage 20% 0.51 Cft
3.06 Cft 0.00 P. Cft -

Sawing charge 3.06 Cft 0.00 P. Cft -


Making holes in walls L.S. -
Wooden gutties 3 interval 16.00 Nos 0.00 Each -
Screws above 1" long 6.00 Doz 0.00 P. Doz -
Nail 0.70 Kg 0.00 P. Kg -
M.S. hooks 4.00 Nos 0.00 Each -
M.S. clamps 4.00 Nos 0.00 Each -
Cement sand for repair 0.083 Bag 0.00 P. Bag -
Sand 1.500 Cft. 0.00 % Cft. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 144 Sft. -
Rate Per Sft 0.00 100 -
144

Page 124
Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Carpenters 2.25 Nos 0.00 P. Day -


Cooly Skilled 2.00 Nos 0.00 P. Day -
Cooly 0.50 No 0.00 P. Day -
Mason 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 144 Sft. -
Rate Per Sft 0.00 100 -
144

Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per 100 Sft Rs. ##### Say (2.90)


Composite Rate Per Sqm Rs. ##### Say (0.30)

Page 125
Item No. 42 Providing and fixing thermopore false ceili
including wooden frame panelling, cost of M
clamps, making holes in walls and repairing
damaged surface, complete in all respects.

a) Deodar wood frame panelling


ii) 1" (25mm) Thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 12' x 12' = 144 Sft

Material

Thermopore 1" thick 144.00 Sft


Wastage 5% 7.20 Sft
151.20 Sft 0.00 Sft -
Deodar Wood
Frame Main 3x12x2"x3" 1.53 Cft
Cross 3x12x1"x2" 0.77 Cft
Wooden Strips 4x12x1"x" 0.25 Cft
2.55 Cft
Wastage 20% 0.51 Cft
3.06 Cft 0.00 P. Cft -
Sawing charge 3.06 Cft 0.00 -
Making holes in walls L.S. -
Screws of all sorts 6.00 Doz 0.00 P. Doz -
Nail 0.70 Kg 0.00 P. Kg -
M.S. hooks 4.00 Nos 0.00 Each -
M.S. clamps 4.00 Nos 0.00 Each -
Cement sand for repair L.S. 20.00

Total 20.00
Contractor's Profit & Ove 20 Percent 4.00
Total for 144 Sft. 24.00
Rate Per Sft 24.00 100 16.67
144

Page 126
Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Carpenter 2.25 Nos 0.00 P. Day -


Cooly Skilled 2.00 Nos 0.00 P. Day -
Cooly 0.50 No 0.00 P. Day -
Mason 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 144 Sft. -
Rate Per Sft 0.00 100 -
144

Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per 100 Sft Rs. ##### Say 13.85


Composite Rate Per Sqm Rs. 1.49 Say 1.50

Page 127
Item No. 42 Providing and fixing thermopore false ceili
including wooden frame panelling, cost of M
clamps, making holes in walls and repairing
damaged surface, complete in all respects.

b) Pertal wood frame panelling


i) " (20mm) Thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 12' x 12' = 144 Sft

Material

Thermopore " thick 144.00 Sft


Wastage 5% 7.20 Sft
151.20 Sft 0.00 Sft -
Pertal Wood
Frame Main Style 3x12x2"x3" 1.53 Cft
Cross Style 3x12x1"x2" 0.77 Cft
Cross Style 4x12x1"x" 0.25 Cft
2.55 Cft
Wastage 20% 0.51 Cft
3.06 Cft 0.00 P. Cft -
Sawing charge 3.06 Cft 0.00 P. Cft -
Making holes in walls L.S. -
Wooden gutties 3 interval 16.00 Nos 0.50 Each 8.00
Screws of all sorts 6.00 Nos 0.00 P. Doz -
Nail 0.70 Kg 0.00 P. Kg -
M.S. hooks 4.00 Nos 0.00 Each -
M.S. clamps 4.00 Nos 0.00 Each -
Cement sand for repair 0.083 Bag 0.00 P. Bag -
Sand 1.500 Cft. 0.00 % Cft. -

Total 8.00
Contractor's Profit & Ove 20 Percent 1.60
Total for 144 Sft. 9.60
Rate Per Sft 9.60 100 = 6.67
144

Page 128
Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Carpenter 2.25 Nos 0.00 P. Day -


Cooly Skilled 2.00 Doz 0.00 P. Day -
Cooly 0.50 No 0.00 P. Day -
Mason 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 144 Sft. -
Rate Per Sft 0.00 100 -
144

Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per 100 Sft Rs. 3.72 Say 3.70


Composite Rate Per Sqm Rs. 0.40 Say 0.40

Page 129
Item No. 42 Providing and fixing thermopore false ceili
including wooden frame panelling, cost of M
clamps, making holes in walls and repairing
damaged surface, complete in all respects.

b) Pertal wood frame panelling


ii) 1" (25mm) Thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit Amount
Rate Analysis for 12' x 12' = 144 Sft

Material

Thermopore 1" thick 144.00 Sft


Wastage 5% 7.20 Sft
151.20 Sft 0.00 Sft -
Pertal Wood
Frame Main Style 3x12x2"x3" 1.53 Cft
Cross Style 3x12x1"x2" 0.77 Cft
Cross Style 4x12x1"x" 0.25 Cft
2.55 Cft
Wastage 20% 0.51 Cft
3.06 Cft 0.00 P. Cft -
Sawing charge 3.06 Cft 0.00 P. Cft -
Making holes in walls L.S. -
Wooden gutties 3 interval 16.00 Nos 0.00 Each -
Screws of all sorts 6.00 Doz 0.00 P. Doz -
Nail 0.70 Kg 0.00 P. Kg -
M.S. hooks 4.00 Nos 0.00 Each -
M.S. clamps 4.00 Nos 0.00 Each -
Cement sand for repair 0.083 Bag 0.00 P. Bag -
Sand 1.500 Cft. 0.00 % Cft. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 144 Sft. -
Rate Per Sft 0.00 100 -
144

Page 130
Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour
Carpenter 2.25 Nos 0.00 P. Day -
Cooly Skilled 2.00 Nos 0.00 P. Day -
Cooly 0.50 No 0.00 P. Day -
Mason 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 144 Sft. -
Rate Per Sft 0.00 100 -
144

Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per 100 Sft Rs. ##### Say (2.80)


Composite Rate Per Sqm Rs. ##### Say (0.30)

Page 131
DESCRIPTION OF ITEM NO 43: a) Fixing door including chowkhat.

Detail Unit Rate (British System)per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Mason 0.25 No 0.00 P. Day -


Cooly 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total 0.01

Item Rates
Labour Rate for Each Rs. 0.01 Say -

Page 132
Item No. 43 Fixing windows including chowkhat.

Detail Unit Rate (British System)per Each

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Mason 0.125 No 0.00 P. Day -


Cooly 0.125 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -

Item Rates
Labour Rate for Each Rs. 0.00 Say -

Page 133
DESCRIPTION OF ITEM NO 44: a) Glazing with panes 160Z to 180Z (454Gm to 5
Gm) including cost of putty.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 14 Sft

Material

Detail of glass panes

Glass Panes 14.00 Sft


Wastage 10% 1.40 Sft
15.40 Sft 0.00 Sft -
Cost of Putty and nails L.S. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 14 Sft. -
Rate Per Sft 0.00 = -
14
Labour

Glazier for cutting and fixing glass


panes including supplying front & back. 0.25 No 0.00 P. Day -
Cooly Skilled 0.25 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 14 Sft. -
Rate Per Sft 0.00 = -
14

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 134
Item No. 44 Glazing with panes 16 Oz. to 18 Oz. (454Gm
Gm) using deodar wooden fillets and putty.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 14 Sft

Material

Glass Panes 14.00 Sft 0.00 Sft -


D. Wood 0.09 Cft 0.00 P. Cft -
Cost of nails and putty. L.S. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 14 Sft. -
Rate Per Sft 0.00 = -
14
Labour

Glazier for cutting and fixing glass


panes including supplying front & back. 0.25 No 0.00 P. Day -
Cooly Skilled 0.25 No 0.00 P. Day -
Cartpenter for 0.13 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 14 Sft. -
Rate Per Sft 0.00 = -
14

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. ##### Say -

Page 135
DESCRIPTION OF ITEM NO 45: Glazing with glass panes 24 Oz. to 26 Oz. (
737Gm) using putty and deodar wooden fillet

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 15 Sft

putty and deodar wooden fillet.


Considering 5 Nos panes of average
size i.e. 5x18"x24" 15 Sft

Material
Glass Panes 15.00 Sft
Wastage 10% 1.50 Sft
16.50 Sft 0.00 Sft -
D. Wood for fillets 0.06 Cft 0.00 P. Cft -
Cost of putty and nails L.S. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 15 Sft. -
Rate Per Sft 0.00 = -
15
Labour

Glazier 0.38 No 0.00 P. Day -


Cooly Skilled 0.38 No 0.00 P. Day -
Cartpenter 0.13 No 0.00 P. Day -
Cooly 0.13 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 15 Sft. -
Rate Per Sft 0.00 = -
15
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 136
DESCRIPTION OF ITEM NO 46:
a) Cutting to required sizes and fixing glass
with putty.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 14 Sft

Material

Cost of nails & putty L.S. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 14 Sft. -
Rate Per Sft 0.00 = -
14
Labour

Glazier 0.20 No 0.00 P. Day -


Cooly Skilled 0.15 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 14 Sft. -
Rate Per Sft 0.00 = -
14

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. ##### Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 137
Item No. 46 Cutting to required sizes and fixing glass
with wooden fillets and putty.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 16 Sft

Material

Deodar wood for fillets 0.10 Cft 0.00 P. Cft -


Putty and nails L.S. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 16 Sft. -
Rate Per Sft 0.00 = -
16
Labour

Glazier 0.20 No 0.00 P. Day -


Cooly Skilled 0.20 No 0.00 P. Day -
Carpenter 0.10 No 0.00 P. Day -
Cooly Skilled 0.10 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 16 Sft. -
Rate Per Sft 0.00 = -
16

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 138
DESCRIPTION OF ITEM NO 47: Glazing with plate glass " (6mm) thick inc
the cost of deodar wood fillets and putty.
a) Glazing upto 8 Sft (0.744M).

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 8 Sft

Material

Plate glass " (6mm) thick 8.00 Sft


Wastage 10% 0.80 Sft
8.80 Sft 0.00 Sft -
Deodar wood for fillets 0.05 Cft 0.00 P. Cft -
Cost of nails and putty L.S. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 8 Sft. -
Rate Per Sft 0.00 = -
8
Labour
Glazier 0.17 No 0.00 P. Day -
Cooly Skilled 0.17 No 0.00 P. Day -
Carpenter 0.06 No 0.00 P. Day -
Cooly Skilled 0.06 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 8 Sft. -
Rate Per Sft 0.00 = -
8

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 139
Item No. 47 Glazing exceeding 8 Sft (0.744M)
and not exceeding 24 Sft (2.230M)

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 16 Sft

Material

Plate glass " (6mm) thick 16.00 Sft


Wastage 10% 1.60 Sft
17.60 Sft 0.00 Sft -
Deodar wood for fillets 0.10 Cft 0.00 P. Cft -
Cost of nails and putty L.S. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 16 Sft. -
Rate Per Sft 0.00 = -
16
Labour

Glazier 0.33 No 0.00 P. Day -


Cooly Skilled 0.33 No 0.00 P. Day -
Carpenter 0.13 No 0.00 P. Day -
Cooly Skilled 0.13 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 16 Sft. -
Rate Per Sft 0.00 = -
16

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say -


Composite Rate Per Sqm Rs. ##### Say (0.20)

Page 140
DESCRIPTION OF ITEM NO 48: Providing and fixing 1" (40mm) thick deoda
wood panelled or panelled and glazed, doors
windows, with mild steel chowkhat (frame),
complete in all respects (excluding sliding
lock) with :
i) M.S. angle iron 1"x1"x" (40x40x6mm)
welded with M.S. flat 2"x" (50x6mm)

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material

Angle Iron 1"x1"x"


Vertical 2 x 7 = 14.00 Rft.
Horizontal l 1 x 4 = 4.00 Rft.
18.00 Rft.
Wastage 5% 0.90 Rft.
18.90 Rft.
18.90 Rft. @ 2.34 lbs/Rft. 44.23 lbs
MS Bar "dia 4' @ 0.67 lbs/Rft. 2.68 lbs
MS Flat 2"x = 18.90 Rft. @ 1.70 lbs/Rft 32.13 lbs
79.04 lbs
35.85 Kgs 0.00 per Kg -
Wood
Vertical Style 4x6'-8"x4"x1" 1.12 Cft
Horizontal Top 2x1'-11"x4"x1" 0.16 Cft
Middle Top 2x1'-11"x4"x1" 0.16 Cft
Local Top 2x1'-11"x6"x1" 0.24 Cft
Bottom Top 2x1'-11"x8"x1" 0.32 Cft

Panells
2x16"x23"x5/8" 0.24 Cft
4x16"x19"x5/8" 0.47 Cft
Beading
2(16+16+23+23) 5/8
(1+2) = 0.01 0.01 Cft
2x8
4(16+16+19+19) 5/8
(1+1) 0.02 Cft
2x8
2.74 Cft
Wastage 30% 0.82 Cft
3.56 Cft 0.00 P. Cft -

Page 141
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Fitting
Hinges 4" (100mm) 8.00 Nos 0.00 Each -
Tower bolt 9: (225mm) 3.00 Nos 0.00 Each -
Handle 6" (150mm) 3.00 Nos 0.00 Each -
Iron hold fast 6.00 Nos 0.00 Each -
Rubber 2.00 Nos 0.00 Each -
Hook & clamp 2.00 Nos 0.00 Each -

Screws 2.50 Doz 0.00 P. Doz -


Glue 0.05 Kg. 0.00 P.Kg. -
Spikes 0.13 Kg. 0.00 P.Kg. -
Sawing charge 35.60 Sft 0.00 Sft -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour

Carpenter 2.40 Nos 0.00 P. Day -


Cooly Skilled 1.80 Nos 0.00 P. Day -
Welder 1.00 No 0.00 P. Day -
Blacksmith 0.57 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say (1.30)


Composite Rate Per Sqm Rs. ##### Say (14.10)

Page 142
Item No. 48 Providing and fixing 1" (40mm) thick deoda
wood panelled or panelled and glazed, doors
windows, with mild steel chowkhat (frame),
complete in all respects (excluding sliding
lock) with :
ii) M.S. Tee Iron 1"x1"x" (40x40x6mm)
welded with M.S. flat "x" (12x6mm).

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material
T-Iron 1"x1"x"
Vetical 2x7 14 Rft
Horizontal 1x4 4 Rft
18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft
18.90 Rft 2.36 Lbs/Rft 44.60 Lbs
M.S. bar " = 4' @ 0.67 Lbs 2.68 Lbs
M.S. flat "x"=18.90 Rft @ 0.425 Lbs 8.03 Lbs
55.31Lbs ( 25.10)Kg 0.00 P. Kg -
Deodar Wood
Vertical Style 4x6'-8"x4"x1" 1.12 Cft
Horizontal Top 2x1'-11"x4"x1" 0.16 Cft
Middle Top 2x1'-11"x4"x1" 0.16 Cft
Local Top 2x1'-11"x6"x1" 0.24 Cft
Bottom Top 2x1'-11"x8"x1" 0.32 Cft

Panells
2x16"x23"x5/8" 0.24 Cft
4x16"x19"x5/8" 0.47 Cft

Beading
2(16+16+23+23) 5/8
(1+2) 0.01 Cft
2x8
4(16+16+19+19) 5/8
(1+1) 0.02 Cft
2x8
2.74 Cft
Wastage 30% 0.82 Cft
3.56 Cft 0.00 P. Cft -

Page 143
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Fitting
Hinges 4" (100mm) 8.00 Nos 0.00 Each -
Tower bolt 9: (225mm) 3.00 Nos 0.00 Each -
Handle 6" (150mm) 3.00 Nos 0.00 Each -
Iron hold fast 6.00 Nos 0.00 Each -
Rubber 2.00 Nos 0.00 Each -
Hook & clamp 2.00 Nos 0.00 Each -
Screws 2.50 Doz 0.00 P. Doz -
Glue 0.05 Kg. 0.00 P.Kg. -
Spikes 0.13 Kg. 0.00 P.Kg. -
Sawing charge 35.60 Sft 0.00 Sft -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour

Carpenter 2.40 Nos 0.00 P. Day -


Cooly Skilled 1.80 Nos 0.00 P. Day -
Welder 1.00 No 0.00 P. Day -
Blacksmith 0.57 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 27 Sft. -
Rate Per Sft 0.00 = -
27

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say (0.10)


Composite Rate Per Sqm Rs. ##### Say (0.60)

Page 144
DESCRIPTION OF ITEM NO 49: Providing and fixing 1" (40mm) thick hollo
doors and windows, with commercial ply (3mm
both faces of deodar wood shutter frame 1"
(32mm) thick and partal wood braces at abou
(76mm) apart and deodar wood lipping 1"x3/
(40x10mm) fixed with M.S. chowkhat (frame),
including chromium plated fittings, etc. co
all respects (without sliding bolt or lock)
a) M.S. Angle Iron 1"x1"x" welded with M.S.
flat 2"x"

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material
Angle Iron 1"x1"x"
Vetical 2x7 14 Rft
Horizontal 1x4 4 Rft
18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft 43.85 Lbs
M.S. flat 2"x" (50x6mm)
Vetical 2x7 14 Rft
Horizontal 1x4 4 Rft
18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft
18.90 Rft @ 1.68 Lbs/Rft 31.75 Lbs
M.S. flat patti 1"x1/8" (25x3mm) at bott 1.68 Lbs
77.28Lbs (35.06 Kg. 0.00 P. Kg -
Deodar Wood
Vertical Style 2x6'-8"x4"x1" 0.47 Cft
Vertical Style 3x6'-8"x2"x1" 0.35 Cft
Horizontal Style 1x3'-11"x4"x1" 0.14 Cft
Middle Style 1x3'-11"x4"x1" 0.14 Cft
Lock Style 1x3'-11"x6"x1" 0.21 Cft
Bottom Style 1x3'-11"x8"x1" 0.27 Cft
Side Strip 2x6'-8"x1"x1/8" 0.02 Cft
Side Strip 2x3'-8"x1"x1/8" 0.01 Cft
1.61 Cft
Wastage 35% 0.56 Cft
2.17 Cft 0.00 P. Cft -

Page 145
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Fitting
Hinges 4" (100mm) 4.00 Nos 0.00 Each -
Tower bolt 9: (225mm) 2.00 Nos 0.00 Each -
Handle 6" (150mm) 2.00 Nos 0.00 Each -
Iron hold fast 6.00 Nos 0.00 Each -
Rubber chocks 1.00 No 0.00 Each -
Hook & clamp 1.00 No 0.00 Each -
Screws 2.50 Doz 0.00 P. Doz -
Glue 0.75 Kg. 0.00 P.Kg. -
Spikes 0.20 Kg. 0.00 P.Kg. -
Sawing charge 21.70 Sft 0.00 Sft -

Commercial Ply (3mm)


2x3'-11"x6'-8" 53.38 Sft
Wastage 15% 8.01 Sft
61.39 Sft 0.00 Sft -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour

Welder for making frame 1 No 0.00 Each -


Black Smith 1 Nos 0.00 Each -

For Panelling pressing and erecting door


Carpentre 1 Nos 0.00 P. Day -
Skilled Cooly 1 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say (1.30)


Composite Rate Per Sqm Rs. ##### Say (14.10)

Page 146
DESCRIPTION OF ITEM NO 49: Providing and fixing 1" (40mm) thick hollo
doors and windows, with commercial ply (3mm
both faces of deodar wood shutter frame 1"
(32mm) thick and partal wood braces at abou
(76mm) apart and deodar wood lipping 1"x3/
(40x10mm) fixed with M.S. chowkhat (frame),
including chromium plated fittings, etc. co
all respects (without sliding bolt or lock)
b) M.S. Tee Iron 1"x1"x" welded with M.S.
flat "x"

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft

Material
Tee Iron 1"x1"x"
Vetical 2x7 14 Rft
Horizontal 1x4 4 Rft
18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft @ 2.36 44.60 Lbs
M.S. flat "x" (40x6mm)
Vetical 2x7 14 Rft
Horizontal 1x4 4 Rft
18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft @ 0.423L 8.03 Lbs
M.S. bar " dia = 4 Rft @ 0.67 Lbs 2.68 Lbs
55.31Lbs ( 25.10 Kg 0.00 P. Kg -
Deodar Wood
Vertical Style 2x6'-8"x4"x1" 0.47 Cft
Vertical Style 3x6'-8"x2"x1" 0.35 Cft
Horizontal Style 1x3'-11"x4"x1" 0.14 Cft
Middle Style 1x3'-11"x4"x1" 0.14 Cft
Lock Style 1x3'-11"x6"x1" 0.21 Cft
Bottom Style 1x3'-11"x8"x1" 0.27 Cft
Side Strip 2x6'-8"x1"x1/8" 0.02 Cft
Side Strip 2x3'-8"x1"x1/8" 0.01 Cft
1.61 Cft
Wastage 35% 0.56 Cft
2.17 Cft 0.00 P. Cft -

Page 147
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Fitting
Hinges 4" (100mm) 4.00 Nos 0.00 Each -
Tower bolt 9: (225mm) 2.00 Nos 0.00 Each -
Handle 6" (150mm) 2.00 Nos 0.00 Each -
Iron hold fast 6.00 Nos 0.00 Each -
Rubber chocks 1.00 No 0.00 Each -
Hook & clamp 1.00 No 0.00 Each -
Screws 2.50 Doz 0.00 P. Doz -
Glue 0.75 Kg. 0.00 P.Kg. -
Spikes 0.20 Kg. 0.00 P.Kg. -
Sawing charge 21.70 Sft 0.00 Sft -

Commercial Ply (3mm)


2x3'-11"x6'-8" 53.38 Sft
Wastage 15% 8.01 Sft
61.39 Sft 0.00 Sft -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour

Welder for making frame 1 No 0.00 Each -


Black Smith 1 Nos 0.00 Each -

For Rendring & Erection Door


Carpentre 1 Nos. 0.00 P. Day -
Skilled Cooly 1 No. 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say (1.30)


Composite Rate Per Sqm Rs. ##### Say (14.10)

Page 148
DESCRIPTION OF ITEM NO 50: Providing and fixing 1" (40mm) thick solid
door shutter sterling or equivalent with co
ply (5mm thick) on both sides double presse
deodar wood lipping 1"x3/8" (40x10mm) arou
shutter including chromium plated fittings,
hinges with aluminium kick plate 22SWG on b
sides & finger plate complete in all respec

Remarks : If C.I. finger plate and kick plate are not


provided/ fixed the composite rate will be
by Rs. 7.60 Per Sft (81.76M).

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3.5' x 7' = 24.5 Sft

Material

Solid flush
Door leaf 1" (40mm) thick sterling
or equivalent with commerical ply
(5mm) thick both sides.
3"x7'-0' = 24.50 Sft 24.50 Sft 0.00 Sft -

Deodar Wood Lipping 3/8"


(3.5+3.5+7.0+7.0) 21.00 Rft 0.00 per/ft. -

Hinges 4" (100mm) 4.00 Nos 0.00 Each -


Tower bolt C.P. 2.00 Nos 0.00 Each -
C.P. Handle best quality 2.00 Nos 0.00 Each -
Door stopper 1.00 No 0.00 Each -
C.P. finger plate with screws 1.00 No 0.00 Each -
Kick plate 22 SWG on both sides 2.00 Nos 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 24.5 Sft. -
Rate Per Sft 0.00 = -
24.5

Page 149
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

For planning & fixing of lipping with


door fitting complete.
Carpentre 1.00 No 0.00 P. Day -
Skilled Cooly 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 24.5 Sft. -
Rate Per Sft 0.00 = -
24.5

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. ##### Say (0.20)

Page 150
DESCRIPTION OF ITEM NO 51: Providing and fixing panelled door of M.S.
with forged door leaves of M.S. Sheet 22 SW
in hollow frame chowkhat 3"x4" (76x114mm)
made of M.S. sheet 18 SWG, filled with plai
concrete 1:3:6 etc. complete, with all fitt
hammer painting, including carriage to site
fixing in position.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 7' = 28 Sft

Material
M.S. Sheet 18 SWG
for chowkhat
18'x15" 23.44 Sft
Wastage 20% 4.69 Sft
28.13 Sft 0.00 Sft -
M.S. Sheet 22 SWG
for shutter
26x7 1/8 31.50 Sft
Wastage 20% 6.30 Sft
37.80 Sft 0.00 Sft -
M.S. Flat 1"x1/16" (25x2mm)
6'-9"x0.21 1.43Lb (065) Kg 0.00 P. Kg -

Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Tower bolt 9: (225mm) 2.00 Nos 0.00 Each -
Handle 6" (150mm) 2.00 Nos 0.00 Each -
Iron hold fast 6.00 Nos 0.00 Each -
Screws L.S. 4.00
Welding electrode 4.00 Nos 0.00 Each -
Electricity Charges L.S. -

Cement concrete (1:3:6)


Cement 0.21 Bag 0.00 Each -
Sand 0.76 Cft 0.00 P. Cft -
Bagri 1.52 Cft 0.00 P. Cft -

Total 4.00
Contractor's Profit & Ove 20 Percent 0.80
Total for 28 Sft. 4.80
Rate Per Sft 4.80 = 0.17
28

Page 151
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Welder 0.50 No 0.00 P. Day -


Blacksmith 2.50 Nos 0.00 P. Day -
Mason 0.25 No 0.00 P. Day -
Coolies 0.75 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 28 Sft. -
Rate Per Sft 0.00 = -
28

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. 0.17 Say 0.15


Composite Rate Per Sqm Rs. 1.84 Say 1.85

Page 152
DESCRIPTION OF ITEM NO 52: Providing and laying 24 SWG aluminium kick
plate 4" (100mm) high fixed with screws 4"
(100mm) Centre to Centre on bottom rail of
doors only. of commercial ply.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4 Rft

Material

Aluminium plate 4" (100mm) wide


and 24 SWG 0.18 Kg 0.00 P. Kg -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 4 Rft. -
Rate Per Rft 0.00 = -
4
Labour

Carpenter 0.12 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 4 Rft. -
Rate Per Rft 0.00 = -
4

Item Rates
Labour Rate Per Rft Rs. - Say -
Labour Rate Per Rm Rs. - Say -

Composite Rate Per Rft Rs. - Say -


Composite Rate Per Rqm Rs. - Say -

Page 153
DESCRIPTION OF ITEM NO 53: Providing and fixing curtain railing to doo
windows, comprising of TOSO-elite Japan mad
superior type of railing or equivalent, fix
4"x" (100x20mm) deodar wood strip, includi
painting.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material
Rate For 10 Rft
Railing 10.00 Rft 0.00 P. Rft -
Cutting of Railing -
Screws 1.00 Dozen 0.00 P, Doz -
Guttis 6.00 Nos 0.00 Each -
Deodar wood 0.21 Cft 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 10 Rft. -

Material Rate Per Rft. 0.00 = -


10
Labour
Rate For 80 Rft
Carpenter 1.00 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total -
Rate Per Sft 0.00 = -
80

Item Rates
Labour Rate Per Rft Rs. - Say -
Labour Rate Per Rm Rs. - Say -

Composite Rate Per Rft Rs. 0.15 Say 0.15


Composite Rate Per Rm Rs. 0.54 Say 0.55

Page 154
DESCRIPTION OF ITEM NO 54: Providing and fixing M.S. flat "1/8" (12x3
grill including "x1/8" (20x3mm) M.S. Flat
of windows of approved design including pai
coat complete in all respect.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 2 x 3 = 8.75 Sft

Material

M.S. Flat Frame for Grill "x1/8"


(20x3mm)
2'+3'+2'+3' 12 Sft
@ 0.32 Lbs/Rft 3.84 Lbs (1 .88)Kg 0.00 P. Kg -
M.S. Flat "x1/8" (12x3mm)
Straight 3x2x3 21.00 Rft.
Flower 6x4x1 30.00 Rft.
Side 6x4x 6.00 Rft.
Front 6x1x2 12.00 Rft.
Total 69.00 Rft.
Wastage 5% 3.45 Rft.
72.45Lb (7.0 )Kg 0.00 P. Kg 154.00
@ 0.21 lbs/rft 15.21 lbs

Hold fast 6" (150mm) long 6.00 Nos 0.00 Each -


Electrical Charges L.S. (11.00)
Electrod 0.33 Pkt 0.00 Pkt 21.12
Paint 0.098Lb (0. 08) Gl 0.00 P. Gl -

Total 164.12
Contractor's Profit & Ove 20 Percent 32.82
Total for 100 Sft. 196.94
Rate Per Sft 196.94 = 22.51
8.75

Page 155
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Welder 0.17 Nos 0.00 P. Day -


Blacksmith 0.17 No 0.00 P. Day -
Masson 0.20 Nos 0.00 P. Day -
Painter 0.09 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 100 Sft. -
Rate Per Sft 0.00 = -
8.75

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. ##### Say 22.45


Composite Rate Per Sqm Rs. ##### Say 241.80

Page 156
DESCRIPTION OF ITEM NO 55: Providing and fixing G.I. Wire gauge 22 SWG
12x12 meshes per Sq Inch (625mm) fixed to s
window complete with flat iron putti "x1/8
(12x3mm) and machine made screws.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4 x 3 = 12 Sft

Material
Wire Gauge 144 (12x12) Mesh 12.00 Sft
Wastage 10% 1.20 Sft
13.20 Sft 0.00 Sft -
Flat Iron "x1/8" (12x3mm)
3+3+4+4+4 18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft @ 0.21 4 Lbs (1. 82) Kg 0.00 P. Kg -
Screws 6.70 Dozen 0.00 P. Doz -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
12

Labour Rate for 55 Sft.


Blacksmith 1.00 No 0.00 P. Day -
Skilled Cooly 0.40 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
55
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 157
DESCRIPTION OF ITEM NO 56: Providing and fixing wooden moulding stoppe
2"x5/8" (63x16mm) on door frame fitted wit
of approved quality complete in all respect
a) Teak Wood Moulding.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 16 Sft

Material Teak Wood


2x(6'-10')+2'-3" 16.00 Rft
16x2"x5/8" 0.17 Cft
Wastage 25% 0.04 Cft
0.22 Cft 0.00 P. Cft -
Glue 0.19 Kg. 0.00 P. Cft -
Nails 0.116 Kg. 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 16 Sft. -
Rate Per Sft 0.00 = -
16
Labour
Labour for sawing, planning and fixing
16 Rft (4.876Rm) moulding in position
carpenter. 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 16 Sft. -
Rate Per Sft 0.00 = -
16

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. 0.05 Say 0.05

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. ##### Say (0.10)

Page 158
Item No. 56 Providing and fixing wooden moulding stoppe
2"x5/8" (63x16mm) on door frame fitted wit
of approved quality complete in all respect
b) Deodar Wood Moulding.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 16 Sft

Material
Deodar wood 2x(6'-10')+2'-3" 16.00 Rft
16x2"x5/8" 0.17 Cft
Wastage 25% 0.04 Cft
0.22 Cft 0.00 P. Cft -
Glue 0.26 Kg. 0.00 P. Cft -
Nails 0.116 Kg. 0.00 P. Cft -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 16 Sft. -
Rate Per Sft 0.00 = -
16
Labour
Labour for sawing, planning and fixing
16 Rft (4.876Rm) moulding in position
carpenter. 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 16 Sft. -
Rate Per Sft 0.00 = -
16

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. 0.05 Say 0.05

Composite Rate Per Sft Rs. 0.05 Say 0.05


Composite Rate Per Sqm Rs. 0.14 Say 0.15

Page 159
DESCRIPTION OF ITEM NO 57: Providing and fixing deodar wood dolly fram
having 1"x1" (40x40mm) vertical and
horizontal double posts with 1"x" (40x40m
full width of jamb braces at 12" (300mm)
including filling of hollow space in betwee
with 1:3:6 P.C.C. fixing of ply of approved
quality there upon & hold fasts complete in
respects.
a) Teak Wood Ply

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 13 Sft

Material (Daodar Wood)

Vertical 2x2x7x1"x1" 0.44 Cft


Horizontal 2x3.5x0.125x0.125 0.11 Cft
Braces 12"x17.25x0.125 0.20 Cft
0.75 Cft
Wastage 25% 0.19 Cft
0.94 Cft 0.00 P. Cft -
PCC (1:3:6) 6"x10"x1" 0.82 Cft
Wastage 10% 0.08 Cft
0.90 Cft 0.00 P. Cft -
Teak Wood Ply 17.25 x 0.75 12.94 Sft
Wastage 10% 1.29 Sft
14.23 Sft 0.00 Sft -
Glue 0.29 Kg. 0.00 P. Cft -
Nails 0.116 Kg. 0.00 P. Cft -
Hold fast 4.00 Nos 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 13 Sft. -
Rate Per Sft 0.00 = -
13

Page 160
Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Carpenter 0.50 No 0.00 P. Day -


Cooly Skilled 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 13 Sft. -
Rate Per Sft 0.00 = -
13

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. ##### Say (0.10)

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. 0.05 Say 0.05

Page 161
Item No. 57 Providing and fixing deodar wood dolly fram
1"x1" (40x40mm) vertical and horizontal d
with 1"x" (40x40mm) full width of jamb br
(300mm) including filling of hollow space i
braces with 1:3:6 P.C.C. fixing of ply of a
there upon & hold fasts complete in all res

b) With Commercial Ply.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 13 Sft

Deodar wood 0.94 Cft 0.00 P. Cft -


PCC (1:3:6) 0.90 Cft 0.31 P. Cft 0.28
Commercial ply 14.23 Sft 0.00 P. Sft -
Glue 0.29 Kg. 0.00 P. Cft -
Nails 0.116 Kg. 0.00 P. Cft -
Hold fast L.S. -
Total 0.28
20 Percent 0.06
Total 0.33
Contractor's Profit & Ove 20 Percent
Total for 13 Sft. 0.33
Rate Per Sft 0.33 = 0.03
13
Labour

Carpenter 0.50 No 0.00 P. Day -


Cooly Skilled 0.50 No 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 13 Sft. -
Rate Per Sft 0.00 = -
13
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. ##### Say (0.10)

Composite Rate Per Sft Rs. ##### Say (0.60)


Composite Rate Per Sqm Rs. ##### Say (6.40)

Page 162
DESCRIPTION OF ITEM NO 58: Providing and fixing ornamental wooden
architrave 3"x" (75x12mm) tapered to "
(6mm) all along the door frame complete in
respects.
a) Teak Wood Architrave.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3.5 x 7 = 24.50 Sft

Material
Length of Architrave
2(7'-0")+3'-6" 17.50 Rft
quantity (3/12'x'x1/12')x17.5' 0.18 Cft
Wastage 25% 0.05 Cft
0.23 Cft 0.00 P. Cft -
Teak Wood
Nails 0.093 Kg. 0.00 P. Kg. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 24.50 Sft. -
Rate Per Sft 0.00 = -
24.50
Labour
Carpenter 0.25 No 0.00 P. Day -
Fixing in position L.S. -

Total -
Sundries 10 Percent -
Total -

Contractor's Profit & Ove 20 Percent -


Total for 24.50 Sft. -
Rate Per Sft 0.00 = -
24.50

Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 163
Item No. 58 Providing and fixing ornamental wooden
architrave 3"x" (75x12mm) tapered to "
(6mm) all along the door frame complete in
respects.
b) Deodar Wood Architrave.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3.5 x 7 = 24.50 Sft

Material
Length of Architrave
2(7')+3'-6" 17.50 Rft
quantity (3/12'x'x1/12')x17.5' 0.18 Cft
Wastage 25% 0.05 Cft
0.23 Cft 0.00 P. Cft -
Deodar wood
Nails 0.186 Kg. 0.00 P. Kg. -

Total -
Contractor's Profit & Ove 20 Percent -
Total for 24.50 Sft. -
Rate Per Sft 0.00 = -
24.50
Labour
Carpenter 0.25 No 0.00 P. Day -
Fixing in position L.S. -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 24.50 -
Rate Per Sft 0.00 = -
24.50
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -

Composite Rate Per Sft Rs. - Say -


Composite Rate Per Sqm Rs. - Say -

Page 164
Item No. 58 Providing and fixing vin board cabinet in k
proofing and polishing / painting with synt
specific with handle and draws screw comple
respects as per drawing

2'-
8'-
Take Qty 8 x 2 = 16 Sft.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Material

a) Vin Board 3/4 2x8x1 = 24.00 Sft.


Vin Board 5x2x1 = 15.00 Sft.
Total 39.00 Sft.
Wastage 20% 7.80
Total 46.80 Sft. 0.00 P. Sft. -

b) Front Shutter Vin Board

4 x 2 x 2 = 16 16.00 Sft. 0.00 P. Sft. -

c) Frame Deodar Wood 3"x1"

2 x 8 = 16 16.00 Ft.
2 x 5 = 10 10.00 Ft.
Total 26.00 Ft.
Wastage 20% 5.20
Total 31.2 Ft.

31.2 x 1 x 3" 0.65 Ft. 0.00 P. Cft. -


12 x 12

d) Termite 0.08 Litre 0.00 P. Litr -

e) Gola 8x2x2 = 32.00 Ft.


Wastage 20% 6.40
Total 38.40 Ft. 0.00 P. Ft. -

f) Painting / polishing including material + labour


Enamal Paint 0.011 Gallon 0.00 P. Gall
Painter 0.041 No. 0.00 P. Day
0.00
16.00 Ft. 0.00 -

g) Handle 4.00 Nos. 0.00 Each -

Page 165
h) Screws 3.75 Dozen 0.00 P. Doz -

i) Hinges 2.00 Nos. 0.00 Each -

Total -
Contractor's Profit & Ove 20 Percent -
Total -

Labour

Carpenter 1.50 Nos. 0.00 P. Day -


Helper 1.25 Nos. 0.00 P. Day -

Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Rate Per Sft 0.00 = -
16
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. Say -

Composite Rate Per Sft Rs. Say -


Composite Rate Per Sqm Rs. Say -

Page 166
37 Providing and Installing PVC Bends of BSS.

(i) Class "B" Working Pressure

Sr. Size MATERIAL LABOUR JOINTING Grand RATE


No. Rate Contractor's Total SOLVENT Daily Daily Amount Total Labour Composite
Each Profit (3 + 4) Quantity Rate Total Contractor Total progress Charges (10 + 13) (5 + 15)
20 Profit
Percent Kgs. Per Kg. 20.00 (8 + 9) (Joints)
1 2 3 4 5 6 7.00 8 9 10 11 12 13 14 15 16
1 3" (75mm) - 0.00 0.00 1/27 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
2 4" (100mm) - 0.00 0.00 1/20 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
3 5" (125mm) - 0.00 0.00 1/16 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00
4 6" (150mm) - 0.00 0.00 1/15 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00

(ii) CLASS "D" WORKING PRESSURE

1 1" (32mm) - 0.00 0.00 1/64 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
2 1" (40mm) - 0.00 0.00 1/50 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
3 2" (50mm) - 0.00 0.00 1/40 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
4 3" (75mm) - 0.00 0.00 1/27 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
5 4" (100mm) - 0.00 0.00 1/20 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
6 5" (125mm) - 0.00 0.00 1/16 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00
7 6" (150mm) - 0.00 0.00 1/15 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00

DAILY PROGRESS

Plumber 1 N 0.00 Per day 0.00 Sundries 10.00 Percent 0.00 Total 0.01
Cooly 0.9 0.00 Per day 0.00 Total 0.00 Say 0.01
Total 0.00 Contractor Profit 20.00 Percent 0.00

1
38 Providing and Installing PVC Tee of BSS.
20
(i) Class "B" Working Pressure

Sr. Size MATERIAL LABOUR JOINTING Grand RATE


No. Rate Contractor's Total SOLVENT Daily Daily Amount Total Labour Composite
Each Profit (3 + 4) Quantity Rate TotalContractor's Total progress Charges (10 + 13) (5 + 15)
20.00 Kgs. Per Kg. 20.00 (8 + 9) (Joints)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 3" (75mm) - 0.00 0.0 1/18 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
2 4" (100mm) - 0.00 0.0 1/13 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
3 5" (125mm) - 0.00 0.0 1/11 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00
4 6" (150mm) - 0.00 0.0 1/10 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00

(ii) CLASS "D" WORKING PRESSURE

1 1" (32mm) - 0.00 0.0 1/40 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
2 1" (40mm) - 0.00 0.0 1/33 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
3 2" (50mm) - 0.00 0.0 1/27 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
4 3" (75mm) - 0.00 0.0 1/18 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
5 4" (100mm) - 0.00 0.0 1/13 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
6 5" (125mm) - 0.00 0.0 1/11 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00
7 6" (150mm) - 0.00 0.0 1/10 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00

DAILY PROGRESS

Plumber 1 N 0.00 Per day 0.00 Sundries 10.00 Percent 0.00 Total 0.01
Cooly 0.9 0.00 Per day 0.00 Total 0.00 Say 0.01
Total 0.00 Contractor Profit 20.00 Percent 0.00

2
39 Providing and Installation of PVC Sockets B.S.S

(i) Class "B" Working Pressure

Sr. Size MATERIAL LABOUR JOINTING Grand RATE


No. Rate Contr- Total SOLVENT No. of Daily Amount Total Labour Composite
Each actor's (3 + 4) Quantity Rate Total Contra- Total Joints Charges (10 + 13) (5 + 15)
10.00 Kgs. Per Kg. ctor's (8 + 9)
10.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 3" (75mm) - 0.00 0.00 1/27 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
2 4" (100mm) - 0.00 0.00 1/20 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
3 5" (125mm) - 0.00 0.00 1/16 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00
4 6" (150mm) - 0.00 0.00 1/15 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00
5 8" (200mm) - 0.00 0.00 1/10 - 0.00 0.00 0.00 30.00 0.01 0.00 0.00 - 0.00
6 10" (250mm) - 0.00 0.00 1/8 - 0.00 0.00 0.00 30.00 0.01 0.00 0.00 - 0.00
7 12" (300mm) - 0.00 0.00 1/7 - 0.00 0.00 0.00 25.00 0.01 0.00 0.00 - 0.00
8 14" (350mm) - 0.00 0.00 1/6 - 0.00 0.00 0.00 25.00 0.01 0.00 0.00 - 0.00

(ii) CLASS "D" WORKING PRESSURE

1 1" (32mm) - 0.00 0.00 1/64 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
2 1" (40mm) - 0.00 0.00 1/50 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
3 2" (50mm) - 0.00 0.00 1/40 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
4 3" (75mm) - 0.00 0.00 1/27 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
5 4" (100mm) - 0.00 0.00 1/20 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
6 5" (125mm) - 0.00 0.00 1/16 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00
7 6" (150mm) - 0.00 0.00 1/15 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00

DAILY PROGRESS

Plumber 1 N 0.00 Per day 0.00 Sundries 10.00 Percent 0.00 Total 0.01
Cooly 0.9 0.00 Per day 0.00 Total 0.00 Say 0.01
Total 0.00 Contractor Profit 20.00 Percent 0.00

3
40 - Providing and installing PVC Tappered Core BSS

41 (i) Class "B" Working Pressure

Sr. Size MATERIAL LABOUR JOINTING Grand RATE


No. Rate Contra- Total SOLVENT Daily Daily Amount Total Labour Composite
Each ctor's (3 + 4) Quantity Rate Total Contra- Total Progress Charges (10 + 13) (5 + 15)
Profit Kgs. Per Kg. ctor's (8 + 9)
20.00 Profit
20.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 3" (75mm) - 0.00 0.00 1/27 - 0.00 0.00 0.00 50.00 0.00 0.00 0.00 - 0.00
2 4" (100mm) - 0.00 0.00 1/20 - 0.00 0.00 0.00 50.00 0.00 0.00 0.00 - 0.00
3 5" (125mm) - 0.00 0.00 1/16 - 0.00 0.00 0.00 40.00 0.00 0.00 0.00 - 0.00
4 6" (150mm) - 0.00 0.00 1/15 - 0.00 0.00 0.00 40.00 0.00 0.00 0.00 - 0.00
5 8" (200mm) - 0.00 0.00 1/10 - 0.00 0.00 0.00 30.00 0.00 0.00 0.00 - 0.00
6 10" (250mm) - 0.00 0.00 1/8 - 0.00 0.00 0.00 30.00 0.00 0.00 0.00 - 0.00
7 12" (300mm) - 0.00 0.00 1/7 - 0.00 0.00 0.00 25.00 0.00 0.00 0.00 - 0.00
8 14" (350mm) - 0.00 0.00 1/6 - 0.00 0.00 0.00 25.00 0.00 0.00 0.00 - 0.00

36 (ii) CLASS "D" WORKING PRESSURE

1 1" (32mm) - 0.00 0.00 1/64 - 0.00 0.00 0.00 60.00 0.00 0.00 0.00 - 0.00
2 1" (40mm) - 0.00 0.00 1/50 - 0.00 0.00 0.00 60.00 0.00 0.00 0.00 - 0.00
3 2" (50mm) - 0.00 0.00 1/40 - 0.00 0.00 0.00 60.00 0.00 0.00 0.00 - 0.00

DAILY PROGRESS

Plumber 1 N 0.00 Per day 0.00 Sundries 10.00 Percent 0.00 Total 0.00
Cooly 0.9 0.00 Per day 0.00 Total 0.00 Say 0.00
Total 0.00 Contractor Profit 20.00 Percent 0.00

4
1- Boring for tube well in all types of soil except shingle and rock from ground level to 100 Ft (30 Metre) depth
including sinking and with-drawing of casing pipe complete.

S. Dia of Time (Day) Daily Labour Hire charges Loading Expenses Repair Petty store Total Contractors, Total Grand Total Rs. per Rate per
No. bore required to labour per foot of boring Per Foot charges bolts & Column (6, Profit& over heads 20% Rate per Ft/ foot Metre
complete charges material No. of Rate per Amount of T & P nuts etc. 9, 10, 11) on Column
100' (30M) installation day day No.12 (12 + 13) (5 + 14) Say
and carriage
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

- -
1 3" 3 #VALUE! #VALUE! 0.00 0.02 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

- -
2 4" 4 #VALUE! #VALUE! 0.00 0.04 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

3 5" 6 #VALUE! #VALUE! 0.00 0.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

4 6" 9 #VALUE! #VALUE! 0.00 0.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

5 8" 11 #VALUE! #VALUE! 0.00 0.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

6 10" 13 #VALUE! #VALUE! 0.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

7 12" 14 #VALUE! #VALUE! 0.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

8 15" 17 #VALUE! #VALUE! 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

9 18" 18 #VALUE! #VALUE! 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

1
2- Boring for tube well in all types of soil except shingle gravel and rock from a depth of 100.10 to 200 Ft (30 to 60 Metre)
below ground level, including sinking and with drawing of casing pipe complete.

S. Dia of Time (Day) Daily Labour Hire charges Loading Expenses Repair Petty store Total Contractors' Total Grand Total Rate per Rate per
No. bore required to labour per foot of boring Per Foot charges bolts & Column (6, Profit& overheads 20% Rate per Ft/ Rft Metre
complete charges material No. of Rate per Amount of T & P nuts etc. 9, 10, 11) on Column
100' (30M) installation day day No.12 (12 + 13) (5 + 14)
and carriage
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

1 5" 10 #VALUE! #VALUE! 0.00 0.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

2 6" 14 #VALUE! #VALUE! 0.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

3 8" 15 #VALUE! #VALUE! 0.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

4 10" 16 #VALUE! #VALUE! 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

5 12" 17 #VALUE! #VALUE! 0.00 0.50 0.00 0.00 20.00 0.00 20.00 2.00 22.00 #VALUE! #VALUE! #VALUE!

6 15" 20 #VALUE! #VALUE! 0.00 0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

7 18" 21 #VALUE! #VALUE! 0.00 0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

2
3- Boring for tube well in all types of soil except shingle gravel and rock from a depth of 200.10 to 300 Ft (60 to 90 Metre)
below ground level including sinking and with drawing of casing pipe complete.

S. Dia of Time (Day) Daily Labour Hire charges Loading Expenses Repair Petty store Total Contractors, Total Total Rate per Rate per
No. bore required to labour per foot of boring Per Foot charges bolts & Column (6, Profit& over heads 20% Rate per Ft/ Rft Metre
complete charges material No. of Rate per Amount of T & P nuts etc. 9, 10, 11) on Column
100' (30M) installation day day No.12 (12 + 13) (5 + 14) Say
and carriage
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

1 5" 14 #VALUE! #VALUE! 0.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

2 6" 18 #VALUE! #VALUE! 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

3 8" 19 #VALUE! #VALUE! 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

4 10" 20 #VALUE! #VALUE! 0.00 0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

5 12" 21 #VALUE! #VALUE! 0.00 0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

6 15" 22 #VALUE! #VALUE! 0.00 0.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

7 18" 23 #VALUE! #VALUE! 0.00 0.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

3
4- Boring for tube well in all types of soil except shingle gravel and rock from a depth of 300.10 to 400 Ft (90 to 120 Metre)
below ground level including sinking and with drawing of casing pipe complete.

S. Dia of Time (Day) Daily Labour Hire charges Loading Expenses Repair Petty store Total Contractors' Total Grand Total Rate per
No. bore required to labour per foot of boring Per Foot charges bolts & Column (6, Profit& overheads 20% Rate per Ft/ Metre
complete charges material No. of Rate per Amount of T & P nuts etc. 9, 10, 11) on Column
100' (30M) installation day bag (7 x 8) No.12 (12 + 13) (5 + 14) Say
and carriage
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

1 8" 23 #VALUE! #VALUE! 0.00 0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

2 10" 24 #VALUE! #VALUE! 0.00 0.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

3 12" 25 #VALUE! #VALUE! 0.00 0.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

4 15" 27 #VALUE! #VALUE! 0.00 0.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

5 18" 27 #VALUE! #VALUE! 0.00 0.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!

4
Daily Labour Charges for :
Daily charges for boring of tube well per 100 ft
(30 M) depth including sinking and with drawing
of casing pipe.

a) For 3" to 4" (75 to 100mm) dia bore.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour for 30 M

Foreman 1.00 No 0 P. Day -


Skilled Cooly 2.00 Nos 0 P. Day -
Unskilled Cooly 1.00 No 0 P. Day -
Chowkidar 1.00 No RATE P. Day #VALUE!

Total #VALUE!
Sundries #### Percent #VALUE!
Total #VALUE!

Contractor's Profit & Ove #### Percent #VALUE!


Total rate for 100 Rft #VALUE!
Say #VALUE!

1
Daily Labour Charges for :
Daily charges for borring of tube well per 100 ft
(30 M) depth including sinking and with drawing
of casing pipe. 20

b) For 5" to 6" (125 to 150mm) dia bore.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Foreman 1.00 No 0.00 P. DAY -


Skilled Cooly 4.00 Nos 0.00 P. DAY -
Unskilled Cooly 1.00 No 0.00 P. DAY -
Chowkidar 1.00 No RATE P. DAY #VALUE!

Total #VALUE!
Contractor's Profit #### Percent #VALUE!
Total #VALUE!

Contractor's Profit & Ove #### Percent #VALUE!


Total rate for 100 feet #VALUE!
Say #VALUE!

2
Daily Labour Charges for :
Daily charges for borring of tube well per 100 ft
(30 M) depth including sinking and with drawing
of casing pipe.

c) For 8" (200mm) dia bore.

Detail Unit Rate (British System) per Foot

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Foreman 1.00 No 0.00 P. Day -


Skilled Cooly 6.00 Nos 0.00 P. Day -
Unskilled Cooly 1.00 No 0.00 P. Day -
Chowkidar 1.00 No RATE P. Day #VALUE!

Total #VALUE!
Sundries #### Percent #VALUE!
Total #VALUE!

Contractor's Profit & Ove #### Percent #VALUE!


Total rate for 100 feet #VALUE!
Say #VALUE!

3
Daily Labour Charges for :
Daily charges for borring of tube well per 100 ft
(30 M) depth including sinking and with drawing
of casing pipe.

d) For 10" to 12" (250 to 300mm) dia bore.

Detail Unit Rate (British System) per Foot

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Foreman 1.00 No 0.00 P. Day -


Skilled Cooly 6.00 Nos 0.00 P. Day -
Unskilled Cooly 2.00 Nos 0.00 P. Day -
Chowkidar 1.00 No RATE P. Day #VALUE!

Total #VALUE!
Sundries #### Percent #VALUE!
Total #VALUE!

Contractor's Profit & Ove #### Percent #VALUE!


Total rate for 100 feet #VALUE!
Say #VALUE!

4
Daily Labour Charges for :
Daily charges for borring of tube well per 100 ft
(30 M) depth including sinking and with drawing
of casing pipe.

e) For 15" to 18" (375 to 450mm) dia bore.

Detail Unit Rate (British System) per Foot

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Foreman 1.00 No 0.00 P. Day -


Skilled Cooly 8.00 Nos 0.00 P. Day -
Unskilled Cooly 2.00 Nos 0.00 P. Day -
Chowkidar 1.00 No RATE P. Day #VALUE!

Total #VALUE!
Sundries #### Percent #VALUE!
Total #VALUE!

Contractor's Profit & Ove #### Percent #VALUE!


Total rate for 100 feet #VALUE!
Say #VALUE!

5
DESCRIPTION OF ITEM NO 5: Direct rotary/ reverse rotary drilling of bore for
tube wells in all type of soil except shingle, gravel
and rock.
(a) From ground level to 250 ft. below ground level.
i) 15" to 18" i/d

Detail Unit Rate (British System) per Foot bore

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

1 Reg pumps etc. 24.00 Hrs 0.00 Ph -


2 Generator set light arrangement 8.00 Hrs 0.00 Ph -
3 Carriage from store to site of work for
reverse rotary drilling reg complete set
and generator set etc. L. S. -
Total -
Labour

Foreman for 3 shifts (One No. per shift 3.00 Nos 0.00 P. Shi -
Driller for 3 shifts (One No. per shift 3.00 Nos 0.00 P. Shi -
Helper for 3 shifts (One No. per shift) 54.00 Nos 0.00 P. Shi -
Electrician for 8 hours 1.00 No 0.00 P. Shi -
Mechanic for 3 shifts 3.00 Nos 0.00 P. Shi -

Total -
Sundries #### Percent -
Total -
Say -

6
Detail Unit Rate (British System) per Foot bore

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material ( P.O.L )
H.S.D. for rig for 24 hours ##### Ltr 0.00 Ltr -
H.S.D. for generator for 8 hours 72.64 Ltr 0.00 Ltr -
Cotton waste for rig for 24 hours 7.90 Kg RATE Kg #VALUE!
Mobil oil 22.70 Ltr 0.00 Ltr -
Mix. Expenditure L. S. -
Total #VALUE!

Machinery -
Labour -
Material (lubricate P.O.L) #VALUE!

Total #VALUE!
Contractor's Profit&overhe #### Percent #VALUE!
Total #VALUE!

Daily Expenditure #VALUE!


Daily Progress ##### Ft
Charges Per Feet #VALUE! #VALUE!
121 say #VALUE!

Rate Charges Per Metre #VALUE!


#VALUE!

7
Item No. 5 Direct rotary/ reverse rotary drilling of bore for
tube wells in all type of soil except shingle, gravel
and rock.

a. From ground level to 250 ft. below ground level.


( ii) 20" to 26" (500 to 650mm) dia

Detail Unit Rate (British System) per Rft of bore

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Daily Expenditure #VALUE!

Daily Progress ##### Ft

Charges Per Foot #VALUE!


115
#VALUE!
say #VALUE!
Rate Per Metre #VALUE!
say #VALUE!

8
Item No. 5 Direct rotary/ reverse rotary drilling of bore for
tube wells in all type of soil except shingle, gravel
and rock.

b. Exceeding 250 ft (75 M) below ground level.


( i) 15" to 18" (375 to 450mm) dia

Detail Unit Rate (British System) per Rft of bore

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Daily Expenditure #VALUE!

Daily Progress 92.00 Ft

Rate Per Rft


#VALUE!
92 #VALUE!
say #VALUE!
Rate Per Metre #VALUE!
say #VALUE!

9
Item No. 5 Direct rotary/ reverse rotary drilling of bore for
tube wells in all type of soil except shingle, gravel
and rock.

b. Exceeding 250 ft (75 M) below ground level.


(ii) 20" to 26" (500 to 650mm) dia

Detail Unit Rate (British System) per Rft of bore

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Daily Expenditure #VALUE!

Daily Progress 88.40 Ft

Boring Charges Per Foot #VALUE!


88.40
#VALUE!
say #VALUE!
Rate Per Metre #VALUE!
say #VALUE!

10
DESCRIPTION OF ITEM NO 6: Boring for tube well in shingle, gravel and rock,
including sinking and with drawing of casing
pipe.

a. From ground level to 200 ft (60 M) below


ground level.
(i) 12" to 18" (300 to 450mm) dia

Detail Unit Rate (British System) per Ft of bore

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Daily Expenditure as per Item No. 5 #VALUE!

Daily Progress 46.00 Ft

Charges Per Foot #VALUE!


46
#VALUE!
say #VALUE!
Rate Per Metre #VALUE!
say #VALUE!

11
Item No. 6 Boring for tube well in shingle, gravel and rock,
including sinking and with drawing of casing
pipe.

a. From ground level to 200 ft (60 M) below


ground level.
(ii) 20" to 26" (500 to 650mm) dia

Detail Unit Rate (British System) per Ft of bore

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Daily Expenditure as per Item No. 5 #VALUE!

Daily Progress 42.58 Ft

Charges Per Foot #VALUE!


42.58
#VALUE!
say #VALUE!
Rate Per Metre #VALUE!
say #VALUE!

12
Item No. 6 Boring for tube well in shingle, gravel and rock,
including sinking and with drawing of casing
pipe.

b. Exceeding 200 ft depth (70 M) below ground level.


(i) 12" to 18" (300 to 450mm) dia

Detail Unit Rate (British System) per Ft of bore

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Daily Expenditure #VALUE!

Daily Progress 38.68 Ft

Boring Charges Per Foot #VALUE!


38.68
#VALUE!
say #VALUE!
Rate Per Metre #VALUE!
say #VALUE!

13
Item No. 6 Boring for tube well in shingle, gravel and rock,
including sinking and with drawing of casing
pipe.

b. Exceeding 200 ft depth (70 M) below ground level.


(ii) 20" to 26" (500 to 650mm) dia

Detail Unit Rate (British System) per Ft of bore

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Daily Expenditure as per Item No. 5 #VALUE!

Daily Progress 28.73 Ft

Charges Per Foot #VALUE!


28.73
#VALUE!
say #VALUE!
Rate Per Metre #VALUE!
say #VALUE!

14
DESCRIPTION OF ITEM NO 7: Providing strong substantially built box of deodar
wood (2nd class) 4'x2'x9' (1.22x0.76x0.228)
with compartments, lock and locking arrangement
for preserving samples of strata from bore hole.

Detail Unit Rate (British System) per Job for Complete


Bore.
Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Deodar Wood (2nd Class)


Top and bottom 2x4'x2.5'x1/12' 1.66 Cft
Sides 2(4'+2'-4")x1/12'x' 0.79 Cft
Partition 9x2'-4"x'x1/24' 0.44 Cft
Strips 6x3'x6"xx1/24 0.44 Cft
3.33 Cft
Wastage 15% 0.50 Cft
Total 3.83 Cft 0.00 P. Cf -
Lock 1.00 No 0.00 Each -
Hinges 2.00 No. 0.00 Each -
Steel Handle 4" (100mm) 2.00 Nos 0.00 Each -

Total -
Contractor's Profit & ove #### Percent -
Total -

Labour

Sawing charges (3.83Cft x 10) 38.30 Sft 0.00 Sft -


Carpenter 0.75 No 0.00 P. Day -

15
Detail Unit Rate (British System) per Job for Complete
Bore.
Qty Rate
Per Unit (Rs.) Amount (Rs.)

Taking and preserving box 2 lbs


sample of strata. L. S. -

Total -
Sundries #### -
Total -

Contractor's Profit & ove #### Percent -


Total -

Labour Rate Per Job for complete bore. Rs. -


say -
Composite Rate per Job for complete bore Rs. -
Say -

16
DESCRIPTION OF ITEM NO 8: Furnishing Sample of Water from Bore Hole.

Detail Unit Rate (British System) per Set of 2 bottles

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bottle 2 lbs capcity 2.00 Nos 0.00 Each -

Total -
Contractor's Profit & ove #### Percent -
Total -

Labour
Taking samples of water from bore
hole including bailing or pumping. L. S. -
Sealing the water sample and
providing necessary packing etc. L. S. -
Handling charges L. S. -

Total -
Contractor's Profit & ove #### Percent -
Total -

Labour Rate Per Set of 2 bottles Rs. -


say -
Composite Rate per Set Rs. -
Say -

17
9- Providing and installing Brass Strainer in Tube Well Bore Hole including Socket, special Socket, Studs
etc. complete.

S. Dia of Thickness Rate of Contractor's Total LABOUR


No. Strainer of strainer Profit Material Daily Daily Labour Lowering Contractor's Total Labour Composite Labour Composite
Strainer (Per Ft i/c 20.00 Progress Expenses Per Ft Equipment Profit & over Labour Rate Rate/Ft Rate Rate
Specials Percent 4+5 in Ft Rs. Charges 20.00 9 + 10 Per Ft. 6 + 12 per Metre per Metre
Stud, and Percent + 11
Socket)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

1 2" 5/32" 0.00 0.00 0.00 200.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!

2 3" 5/32" 0.00 0.00 0.00 200.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!

3 4" 3/16" 0.00 0.00 0.00 150.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!

4 5" 3/16" 0.00 0.00 0.00 130.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!

5 6" 3/16" 0.00 0.00 0.00 120.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!

6 7" 3/16" 0.00 0.00 0.00 100.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!

7 8" 3/16" 0.00 0.00 0.00 80.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!

8 9" 3/16" 0.00 0.00 0.00 80.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!

9 10" 3/16" 0.00 0.00 0.00 70.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!

10 10" 1/4" 0.00 0.00 0.00 70.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!

11 12" 1/4" 0.00 0.00 0.00 70.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!

12 15" 1/4" 0.00 0.00 0.00 60.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!

13 18" 1/4" 0.00 0.00 0.00 60.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!

14 20" 1/4" 0.00 0.00 0.00 50.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!

15 22" 1/4" 0.00 0.00 0.00 50.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!

Contractor's Profit 20

1
2
Daily Labour Charges

Detail Unit Rate (British System) per day

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Foreman 1.00 No 0.00 P. Day -


Skilled Coolies 1.00 No 0.00 P. Day -
Unskilled Coolies 4.00 Nos 0.00 P. Day -
Chowkidar 1.00 No RATE P. Day #VALUE!

Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!

Contractor's Profit & Ove 20.00 Percent #VALUE!


Total #VALUE!

Daily Labour Charges P. Day Rs. #VALUE!

1
Daily Labour Charges

Detail Unit Rate (British System) per Day Charges

Qty Rate
Per Unit (Rs.)Amount (Rs.)

20
Labour

Foreman 1.00 No 0.00 P. Day -


Skilled Coolies 2.00 Nos 0.00 P. Day -
Unskilled Coolies 6.00 Nos 0.00 P. Day -
Chowkidar 1.00 No RATE P. Day #VALUE!

Total #VALUE!
Sundries 10.00 #VALUE!
Total #VALUE!

Contractor's Profit & ove 20.00 #VALUE!


Total #VALUE!

Daily Labou Rs. #VALUE!

2
10 - Providing and Installing M. S. Bail Plug in Tube Well Bore Hole (Eac

M A T E R I A L
S. Dia of Plug Rate Total Wt. of Size of Wt. of Total Wastage Total Wt. in Rate Amount
No. bore Length Per Foot Disc Bars Bars Wt. 10% Wt. Kg Per Kg Rs. Bolts &
Lbs. (Lbs.) (Lbs.) in Lbs Nuts
(3 x 4) (6 + 8) (9 + 10)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 2" 1.50 0.00 0.00 0.14 1/4" 0.53 0.67 0.07 0.74 0.33 0.00 0.00 0.00

2 3" 1.50 0.00 0.00 0.30 1/4" 0.53 0.83 0.08 0.91 0.41 0.00 0.00 0.00

3 4" 2.00 0.00 0.00 0.51 3/8" 1.50 2.01 0.20 2.21 1.00 0.00 0.00 0.00

4 5" 2.00 0.00 0.00 1.22 3/8" 1.50 2.72 0.27 2.99 1.36 0.00 0.00 0.00

5 6" 2.00 0.00 0.00 1.72 3/4" 6.00 7.72 0.77 8.49 3.85 0.00 0.00 0.00

6 7" 2.00 0.00 0.00 2.30 3/4" 6.00 8.30 0.83 9.13 4.14 0.00 0.00 0.00

7 8" 2.00 0.00 0.00 2.97 3/4" 6.00 8.97 0.90 9.87 4.48 0.00 0.00 0.00

8 9" 2.00 0.00 0.00 3.72 3/4" 6.00 9.72 0.97 10.69 4.85 0.00 0.00 0.00

9 10" 2.00 0.00 0.00 6.23 3/4" 6.00 12.23 1.22 13.45 6.10 0.00 0.00 0.00

10 12" 2.00 0.00 0.00 8.83 3/4" 6.00 14.83 1.48 16.31 7.40 0.00 0.00 0.00

1
11 15" 2.00 0.00 0.00 13.57 3/4" 6.00 19.57 1.96 21.53 9.76 0.00 0.00 0.00

12 18" 2.00 0.00 0.00 19.34 3/4" 6.00 25.34 2.53 27.87 12.64 0.00 0.00 0.00

13 20" 2.00 0.00 0.00 23.74 3/4" 6.00 29.74 2.97 32.71 14.84 0.00 0.00 0.00

14 22" 2.00 0.00 0.00 28.60 3/4" 6.00 34.60 3.46 38.06 17.26 0.00 0.00 0.00

2
ch).

L A B O U R C O S T (Rs.)
Material Welding Cutting Total Grand Say Contra- Total Labour for Labour Total Progr- Daily Rate Say Rate Labour Compo-
Total Threading Disc Disc Total ctor's Lowering Contra- ess Charges Per Rft Per Plug Rate site
Clamp Profit Equip- ctor's Daily @ Rs. of Each Length
(5 + 14 (18 + 19) (16 + 20) 20.00 (22 + 23) ment Profit (25 + 26) #VALUE! Plug (31 x 3) (24 + 33)
+ 15) 20.00 per No. (27 + 29)
Percent
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 100 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 100 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 80 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 80 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 56 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 56 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 48 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 48 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 48 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 40 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!

3
0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 40 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 32 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 30 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 30 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!

4
11- Providing and installing PVC Strainer BSS Class "B" in Tube Well Bore Hole including Sockets and Solvents etc. complete.

S. Dia of Rate Contractor's Total Daily Labour Labour Solvent Lowering Contractor's Total Say Rate per Rft Rate per Metre
No. Strainer Per Ft Profit Progress Charges Cost Charges Profit (8 + 9 + Labour Composite Labour Composite
20.00 (3 + 4) in Ft Per Day Per Ft 20.00 10 + 11) (5 + 14)
Percent Percent
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

1 3" 0.00 0.00 0.00 200.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

2 4" 0.00 0.00 0.00 180.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

3 5" 0.00 0.00 0.00 180.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

4 6" 0.00 0.00 0.00 160.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

5 8" 0.00 0.00 0.00 128.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! 0.00 #VALUE! 0.00

6 10" 0.00 0.00 0.00 128.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

7 12" 0.00 0.00 0.00 104.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

8 14" 0.00 0.00 0.00 104.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

1
12- Providing and installing PVC Strainer BSS Class "D" in Tube Well Bore Hole including Sockets and Solvents etc. complete.

MATERIAL LABOURE Rate per Rft Rate per Metre


S. Dia of Rate for Contractor's Total Daily Labour Labour Solvent Lowering Total Contractor's Total Labour Composite Labour Composite
No. Pipe Per Ft Profit Progress Charges Cost Charges Labour Profit (8 + 11 (5 + 13)
20.00 3+4 Per Day Per Ft (9 + 10) 20.00 + 12)
Percent Percent
1 2 3 4 5 6 7 8 9 10 11 4 13 14 15 16 17

1 1" 0.00 0.00 0.00 200.00 ####### #VALUE! 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

2 1" 0.00 0.00 0.00 200.00 ####### #VALUE! 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

3 2" 0.00 0.00 0.00 200.00 ####### #VALUE! 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

4 3" 0.00 0.00 0.00 200.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00

5 4" 0.00 0.00 0.00 180.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00

6 5" 0.00 0.00 0.00 180.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00

7 6" 0.00 0.00 0.00 160.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00

2
13 - i - Providing and installing PVC Bail/ End Plug in Tube Well Bore Hole: BSS Class "B".

MATERIAL LABOURE Rate


S. No. Dia of Cost of Contractor's Total Solvent Contractor's Total Lowering Total Labour Composite
Bail / Bail/ Profit Profit Charges Labour
End Plug End Plug 20.00 (3 + 4) 20.00 6+7 8+9 5 + 10
Percent Percent say
1 2 3 4 5 6 7 8 9 10 11 12

1 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

2 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

3 5" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

4 6" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

5 8" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

6 10" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

7 12" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

8 14" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

3
13 - ii Providing and installing PVC Bail/ End Plug in Tube Well Bore Hole: BSS Class "D".

MATERIAL LABOURE Rate


S. No. Dia of Cost of Contractor's Total Solvent Contractor's Total Lowering Total Labour Composite
Bail / Bail/ Profit Profit Charges Labour
End Plug End Plug 20.00 (3 + 4) 20.00 (6 + 7) (8 + 9) (10 + 5) say
Percent Percent
1 2 3 4 5 6 7 8 9 10 11 12

1 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

2 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

3 2" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

4 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

5 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

6 5" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

7 6" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

4
14- Providing and installing M.S. blind pipe socketed/ welded joint M.S. reducer (where necessary) in
Tube Well Bore Hole including jointing/ welding with strainer etc. complete.

S. Dia of Thickness Rate Contractor's Total Daily Daily Lowering Contractor's Total Grand Rate per Rft Rate per Metre
No. Pipe of Pipe Per Ft Profit Progress Charges Charges Profit 20% Total Labour Composite Labour Composite
20.00 (4 + 5) Rs. (9 + 10) (8 + 11) (6 + 13)
Percent #VALUE!
say
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

1 2" 1/8" 0.00 0.00 0.00 100 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

2 3" 1/8" 0.00 0.00 0.00 100 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

3 4" 1/8" 0.00 0.00 0.00 80 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

4 5" 3/16" 0.00 0.00 0.00 80 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

5 6" 3/16" 0.00 0.00 0.00 56 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

6 7" 3/16" 0.00 0.00 0.00 56 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

7 8" 3/16" 0.00 0.00 0.00 48 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

8 9" 3/16" 0.00 0.00 0.00 48 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

9 10" " 0.00 0.00 0.00 48 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

10 12" " 0.00 0.00 0.00 40 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

11 15" " 0.00 0.00 0.00 40 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

12 18" " 0.00 0.00 0.00 32 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

13 20" " 0.00 0.00 0.00 30 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

14 22" " 0.00 0.00 0.00 30 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

5
6
7
8
9
10
Daily Labour Charges
3" - 6" dia

Detail Unit Rate (British System) per day

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Plumber 1.00 No 0.00 P. Day -


Skilled Coolies 0.50 Nos 0.00 P. Day -
Unskilled Coolies 0.75 Nos 0.00 P. Day -
Chowkidar 1.00 No RATE P. Day #VALUE!

Total #VALUE!
Sundries ##### Percent #VALUE!
Total #VALUE!

Contractor's Profit & Ove ##### Percent #VALUE!


Total #VALUE!

Daily Labour Charges P. Day Rs. #VALUE!


say #VALUE!

1
Daily Labour Charges
8" - 14" dia

Detail Unit Rate (British System) per day

Qty Rate
Per Unit (Rs.)Amount (Rs.) 20

Labour

Plumber 1.00 No 0.00 P. Day -


Skilled Coolies 0.50 Nos 0.00 P. Day -
Unskilled Coolies 1.50 Nos 0.00 P. Day -
Chowkidar 1.00 No RATE P. Day #VALUE!

Total #VALUE!
Sundries ##### Percent #VALUE!
Total #VALUE!

Contractor's Profit & Ove ##### Percent #VALUE!


Total #VALUE!

Contractor's Profit & Overheads Rs. #VALUE!


say #VALUE!

2
Daily Labour Charges
11/4" - 3" dia

Detail Unit Rate (British System) per day

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Plumber 0.50 No 0.00 P. Day -


Skilled Coolies 0.60 Nos 0.00 P. Day -
Unskilled Coolies 1.00 Nos 0.00 P. Day -
Chowkidar 1.00 No RATE P. Day #VALUE!

Total #VALUE!
Sundries ##### Percent #VALUE!
Total #VALUE!

Contractor's Profit & Ove ##### Percent #VALUE!


Total #VALUE!

Daily Labour Charges P. Day Rs. #VALUE!


#VALUE!

3
Daily Labour Charges

Detail Unit Rate (British System) per day

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Foreman 1.00 No 0.00 P. Day -


Skilled Coolies 2.00 Nos 0.00 P. Day -
Unskilled Coolies 6.00 Nos 0.00 P. Day -
Chowkidar 1.00 No RATE P. Day #VALUE!

Total #VALUE!
Sundries ##### Percent #VALUE!
Total #VALUE!

Contractor's Profit & Ove ##### Percent #VALUE!


Total #VALUE!

Daily Labour Charges P. Day Rs. #VALUE!

4
15- Providing and installing PVC blind pipe BSS Class "B" in Tube Well Bore Hole including Sockets and
Solvents and jointing with strainer etc. complete.

S. Dia of Rate Contractor's Total Daily Labour Labour Lowering Solvent Total Contractor's Total Rate per Rft Rate per Metre
No. Strainer Per Ft Profit Progress Charges Per Ft Charges Profit (8 + 11 Labour Composite Labour Composite
20.00 (3 + 4) Per Day (9 + 10) 20.00 + 12) (5 + 13)
Percent Percent
1 2 3 4 5 6 7 8 9 10 11 4 13 14 15 16 16

1 3" 0.00 0.00 0.00 200 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!

2 4" 0.00 0.00 0.00 180 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!

3 5" 0.00 0.00 0.00 180 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!

4 6" 0.00 0.00 0.00 160 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!

5 8" 0.00 0.00 0.00 128 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!

6 10" 0.00 0.00 0.00 128 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!

7 12" 0.00 0.00 0.00 104 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!

8 14" 0.00 0.00 0.00 104 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!

20

1
Daily Labour Charges

a) 3" to 6" (75mm to 150mm) dia.

Detail Unit Rate (British System) per day

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Plumber 1.00 No 0.00 P. Day -


Skilled Coolies 2.00 Nos 0.00 P. Day -
Unskilled Coolies 1.00 No 0.00 P. Day -
Chowkidar 1.00 No RATE P. Day #VALUE!

Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!

Contractor's Profit & ove 20.00 Percent #VALUE!


Total #VALUE!

Daily Labour Charges P. Day Rs. #VALUE!

1
Daily Labour Charges

b) 8" to 14" (200mm to 350mm) dia.


20
Detail Unit Rate (British System) per day

Qty Rate
Per Unit (Rs.)Amount (Rs.)

Labour

Plumber 1.00 No 0.00 P. Day -


Skilled Coolies 2.00 Nos 0.00 P. Day -
Unskilled Coolies 2.00 Nos 0.00 P. Day -
Chowkidar 1.00 No RATE P. Day #VALUE!

Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!

Contractor's Profit & ove 20.00 Percent #VALUE!


Total #VALUE!

Daily Labour Charges P. Day Rs. #VALUE!

2
16- Providing and installing PVC blind pipe BSS Class "D" in Tube Well Bore Hole including Sockets and Solvents
and jointing with strainer etc. complete.

S. Dia of Rate Contractor's Total Daily Daily Labour Solvent Lowering Total Contractor's Total Rate per Rft Rate per Metre
No. Strainer Per Ft Profit Progress Charges Rate Charges Profit (8 + 11 Labour Composite Labour Composite
20.00 (3 + 4) Per Ft (9 + 10) 20.00 12) (5 + 13)
Percent Percent
1 2 3 4 5 6 7 8 9 10 11 4 13 14 15 16 17

1 1" 0.00 0.00 0.00 260 ###### ###### 0.00 0.00 0.00 0.00 ###### #### #VALUE! ###### #VALUE!

2 1" 0.00 0.00 0.00 260 ###### ###### 0.00 0.00 0.00 0.00 ###### #### #VALUE! ###### #VALUE!

3 2" 0.00 0.00 0.00 240 ###### ###### 0.00 0.00 0.00 0.00 ###### #### #VALUE! ###### #VALUE!

4 3" 0.00 0.00 0.00 200 ###### ###### 0.00 0.00 0.00 0.00 ###### #### #VALUE! ###### #VALUE!

5 4" 0.00 0.00 0.00 180 ###### ###### 0.00 0.00 0.00 0.00 ###### #### #VALUE! ###### #VALUE!

6 5" 0.00 0.00 0.00 180 ###### ###### 0.00 0.00 0.00 0.00 ###### #### #VALUE! ###### #VALUE!

7 6" 0.00 0.00 0.00 160 ###### ###### 0.00 0.00 0.00 0.00 ###### #### #VALUE! ###### #VALUE!

1
Contractor's Profit

2
Daily Labour Charges

a) 1" to 3" (32mm to 75mm) dia.

Detail Unit Rate (British System) per day

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Plumber 1.00 No 0.00 P. Day -


Skilled Coolies 1.00 No 0.00 P. Day -
Unskilled Coolies 1.00 No 0.00 P. Day -
Chowkidar 1.00 No RATE P. Day #VALUE!

Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!

Contractor's Profit & Ove 20.00 Percent #VALUE!


Total #VALUE!

Daily Labour Charges P. Day Rs. #VALUE!

1
Daily Labour Charges

b) 4" to 6" (100mm to 150mm) dia.


20
Detail Unit Rate (British System) per day

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Plumber 1.00 No 0.00 P. Day -


Skilled Coolies 2.00 Nos 0.00 P. Day -
Unskilled Coolies 1.00 No 0.00 P. Day -
Chowkidar 1.00 No RATE P. Day #VALUE!

Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!

Contractor's Profit & Ove 20.00 Percent #VALUE!


Total #VALUE!

Daily Labour Cha Rs. #VALUE!

2
DESCRIPTION OF ITEM NO 17: Testing and developing of tube well of size
6" (150mm) inner dia and above Continuously.

i) Upto 1.5 cusacs Discharge.

Detail Unit Rate (British System) per Hours

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material (P. O. L.) For 100 Hours

Diesel Oil 2.50 gallon per hour


for 3 days (72 Hours). ##### Ltr 0.00 P. Ltr -
Mobil Oil 3 gallon (for 72 hrs.) 13.62 Ltr 0.00 P. Ltr -
Grease 2.5 Lbs 1.13 Kg 0.00 P. Kg -
C. Oil L.S. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Composite Rate P Rs. 0.00 -


100

Say -

3
Item No. 17 Testing and developing of tube well of size
6" innner dia and above Continuously.

ii) Upto 1.5 cusacs Discharge.

Detail Unit Rate (British System) per Hour

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material (P. O. L.) For 100 Hours

Diesel Oil 3 gallon per hour


for 3 days (72 Hours). ##### Ltr 0.00 P. Ltr -
Mobil Oil 4 gallon (for 72 hrs.) 18.16 Ltr 0.00 P. Ltr -
Grease 3 Lbs (for 72 hrs.) 1.36 Kg 0.00 P. Kg -
C. Oil L.S. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Composite Rate P Rs. 0.00 -


100

Say -

4
DESCRIPTION OF ITEM NO 18: Shrouding with graded pea gravel 3/8" - 1/8"
(10-3mm) around tube well in bore hole.

Detail Unit Rate (British System) per Cft

Qty Rate
Analysis for 100 Cft Per Unit (Rs.) Amount (Rs.)
Material
Bajri 3/8" - 1/8" (10-3mm) Bajri 3/8" - 1/8 ##### Cft 0.00 % Cft -
Wastage 5% Wastage 5%

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour
Washing and Pouring bag
Skilled Coolies 3.30 Nos 0.00 P. Day -
Unskilled Coolies 1.00 No 0.00 P. Day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour Rate Per Rs. - -


Labour Rate Per Rs. - -
Composite Rate P Rs. -
Composite Rate P Rs. - -

5
19- Laying, cutting, jointing, testing and disinfecting cast iron pipe line in trenches with spigot and socket
caulked lead joint, including cost of materials, such as lead, yarn, etc. complete in all respects.

S. nterna Weight of Weight of Carriage of Lowering Cutting Pluging Testing Jointing Total Composite Composite
No. dia of 18' length 100' length 100' pipe into ends with and with lead charges for rate Per Ft rate Per
pipe of pipe in of pipe in from field trenches chipping, temporary disinfecting joint 100' (30 M) Metre
lbs ton store to site strin- ging & fini- shing wooden (5 + 6 + 7 +
lead four laying to surface to plug +8+9+
chain @ Rs. correct uniform 10)
alignment finish
Tons and grade
1 2 3 4 5 6 7 8 9 10 11 12 13

1 3" 170.00 0.429 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2 4" 190.00 0.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3 5" 324.00 0.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4 6" 410.00 1.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

5 8" 591.00 1.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

6 10" 794.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

7 12" 1018.00 2.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

8 15" 1389.00 3.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

9 18" 1834.00 4.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

1
19 - a - Lowering into trenches, stringing and laying C.I. pipe line to correct alignment and gradient.

S. nterna LABOUR
No. dia Daily Daily Amount per Rate 100 ft
Progress Charges 100 ft Analysis for daily charges

1 3" 400 0.00 0.00 - Plumber 1 No 0.00 0.00

2 4" 400 0.00 0.00 - Coolies 2 Nos 0.00 0.00

3 5" 300 0.00 0.00 - Total 0.00

4 6" 300 0.00 0.00 - Sundries 10.00 Percent -

5 8" 225 0.00 0.00 - Total 20.00 0.00

6 10" 175 0.00 0.00 - Contractor's Profit & Overheads 20.00 Percent -
7 12" 150 0.00 0.00 - Total 0.00

8 15" 125 0.00 0.00 -

9 18" 100 0.00 0.00 -

2
19 - bCutting cast iron pipe, chipping & finishing the face to uniform finish = Cut at every 200ft (60 M)
For 200' (60 M)
S. I/D Labour for Cutting & finishing Rate per
No. of No. of Daily Rate per 100 ft
Pipe cut P. day Charges 200 ft per cut
per cut

1 2 3 4 5 6

1 3" 8.00 0.00 0.00 0.00 Analysis of Daily Charges


2 4" 6.00 0.00 0.00 0.00 LABOUR

3 5" 4.00 0.00 0.00 0.00 Pipe fitter 1 No 0.00 0.00

4 6" 3.00 0.00 0.00 0.00 Unskilled Cooly 2 Nos 0.00 0.00

5 8" 2.00 0.00 0.00 0.00 Total 0.00


6 10" 1.50 0.00 0.00 0.00 Sundries 10.00 Percent -
7 12" 1.25 0.00 0.00 0.00 Total 0.00
8 15" 1.10 0.00 0.00 0.00 Contractor's Profit & Overheads 20.00 Percent -
9 18" 1.00 0.00 0.00 0.00 0.00

3
19 - c Providing and fixing temporary wooden tapered plug of hard wood to each end of pipe line.
Assume for 500 ft. Rate for 100 ft.
S. Size PLUG LABOUR FOR MAKING PLUG LABOUR FOR FIXING Grand Rate for
No. of Area of Length Content Rate Per Amount Daily Daily Amount L. S. Sundries Total Total 100'
plug plug in Cft Progress Charges 10.00 for 500'
Cft (5 X 6) in No. (9 / 8) (11+12) (15+10
+ 7)
1 2 3 4 5 6 7 8 9 10 11 12 13 16 17 18
9x(3)2
1 3" 4x144 0.50 0.02 0.00 0.00 34.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rate of Hard Wood
9x(4)2
2 4" 4x144 0.50 0.04 0.00 0.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Hard Wood
9x(5)2 1 Cft @
3 5" 4x144 0.50 0.07 0.00 0.00 25.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs. 0.00 0.00

Contractor's
9x(6)2 Profit &
4 6" 4x144 0.50 0.10 0.00 0.00 19.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Overheads 20.00 0.00
9x(8)2
5 8" 4x144 0.50 0.17 0.00 0.00 15.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
2
9x(10)
6 10" 4x144 0.75 0.41 0.00 0.00 12.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Daily Charges
9x(12)2 Carpenter
7 12" 4x144 0.75 0.59 0.00 0.00 9.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1 0.00 0.00
9x(15)2 Turner
8 15" 4x144 1.00 1.23 0.00 0.00 7.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1 0.00 0.00
9x(18)2
9 18" 4x144 1.00 1.77 0.00 0.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Sundries 10.00 0.00
Total 0.00
Contractor's
Profit 20.00 0.00
Total 0.00

4
19 - d Testing and disinfecting C.I. Pi
Assume for 1000' (300 M) Rate for 100 ft.
S. I/D of Volume Amount Disin- Amount Hire Total Contra- Total LABOUR Rate Charges
No. pipe in of Water @ Rs fecting @ Rs. Charges ctor's Plugging Labour for Total for 200 Rft
Inch required 0.00 Agent 0.00 of testing (7 + 6 Profit (8 + 9) of Pipe testing &
in Gallon Per Lbs/Kg Per Lbs/Kg operatus + 4) 20.00 disinfecting (11 + 12)
Gallons Percent
1 2 3 4 5 6 7 8 9 10 11 12 13 16

1 3" 310.00 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Mechanic 1 No. 0.00 0.00

2 4" 720.00 0.00 1.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Coolies 2 Nos 0.00 0.00

3 5" 850.00 0.00 1.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00

4 6" 1830.00 0.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Sundries 10.00 Percent -

5 8" 2180.00 0.00 3.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00

6 10" 3410.00 0.00 5.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Contractor's 20.00 Percent -

7 12" 4910.00 0.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Rate per
8 15" 8730.00 0.00 14.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 100 Rft 0.00

9 18" 11000.00 0.00 18.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

5
19 - e Jointing cast iron pipe line in trenches with spigot and socket. Caulked lead joints
including cost of material such as lead, yarn etc., complete in all respect.

Length of pipe Detail


18' (6 per
M) P.
joint
Joint.
= Unit of Rate 100'
S. I/D of Material Per Joint Fuel Total Contra- Total abour Per Join Composite Composite Composite Composite
No. pipe in Lead Rate Amount Yarn Rate P. Amount ctor's Material No. of rate for 18' rate for rate for rate for
Inch Lbs/Kg Lbs/Kg 3x4 Lbs Lbs 6x7 5+8 Profit Per Joint Days length in 100' length Rft Metre
+9 20.00 10 + 11 P. Joint 16 x 100
Percent 12 + 15 18

1 2 3 4 5 6 7 8 9 10 11 12 13 16 17 18 18
1 3" 4.10 0.00 0.00 0.25 0.00 0.00 0.00 0.00 0.00 0.00 0.15 0.00 - - -
2 4" 5.20 0.00 0.00 0.38 0.00 0.00 0.00 0.00 0.00 0.00 0.19 0.00 - - -
3 5" 6.30 0.00 0.00 0.44 0.00 0.00 0.00 0.00 0.00 0.00 0.24 0.00 - - -
4 6" 7.90 0.00 0.00 0.44 0.00 0.00 0.00 0.00 0.00 0.00 0.28 0.00 - - -
5 8" 10.80 0.00 0.00 0.63 0.00 0.00 0.00 0.00 0.00 0.00 0.30 0.00 - - -
6 10" 15.00 0.00 0.00 0.75 0.00 0.00 0.00 0.00 0.00 0.00 0.50 0.00 - - -
7 12" 17.30 0.00 0.00 1.06 0.00 0.00 0.00 0.00 0.00 0.00 0.59 0.00 - - -
8 15" 23.00 0.00 0.00 1.50 0.00 0.00 0.00 0.00 0.00 0.00 0.76 0.00 - - -
9 18" 31.50 0.00 0.00 2.07 0.00 0.00 0.00 0.00 0.00 0.00 0.99 0.00 - - -

Daily Charges
Plumber 1 No 0.00 0.00 Sundires 0.00
Cooly 3 Nos 0.00 0.00 Total 0.00
Assistant Plumber (skilled cooly) 1 No 0.00 0.00 Contractor's Profit & Overheads 0.00
Total 0.00 Total 0.00

6
20- Laying cutting, jointing, testing and disinfecting cast iron pipe line in trenches with flanged and flanged
complete in all respects.

S. Internal Weight of Weight Carriage of Lowering into Cutting ends Pluging Testing and Jointing Total charges Composite Composite
No. dia of 12' length of 100' 100' pipe trenches strin- chipping, fini- with disinfecting with lead for 100' rate per Ft rate per
pipe of pipe in length from field storeging & laying to shing surface temporary joint (30 M) Metre
lbs of pipe to site lead correct alignmen to uniform wooden plug (5 + 6 + 7 +
in ton. four chain Ton and grade finish 8 + 9 + 10)
@ of Rs.

1 2 3 4 5 6 7 8 9 10 11 12 13 say say
1 3" - 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
2 4" - 0.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
3 5" - 0.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
4 6" - 1.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
5 8" - 1.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
6 10" - 2.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
7 12" - 2.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
8 15" - 3.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
9 18" - 4.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -

20 - a Lowering into trenches, stringing and laying C.I. pipe line to correct alignment and gradient.

S. Internal LABOUR
No. dia Daily Daily Amount per Rate 100 ft
Progress Charges 100 ft Analysis for daily charges

1 3" 400 0.00 0.00 - Plumber 1 No 0.00 -


2 4" 400 0.00 0.00 - Coolies 2 Nos 0.00 -
3 5" 300 0.00 0.00 - Total -
4 6" 300 0.00 0.00 - Sundries 10.00 Percent -
5 8" 225 0.00 0.00 - Total -
6 10" 175 0.00 0.00 - Contractor's Profit & Overheads 20.00 Percent -
7 12" 150 0.00 0.00 - Total -
8 15" 125 0.00 0.00 -
9 18" 100 0.00 0.00 -

1
20 - b Cutting cast iron pipe, chipping & finishing the face to uniform finish = Cut at every 200ft (60 M)
For 200' (60 M)
S. I/D Labour for Cutting & finishing Rate per
No. of No. of Daily Rate per 100 ft
Pipe cut P. day Charges 200 ft per cut
per cut

1 2 3 4 5 6
1 3" 8.00 0.00 0.00 0.00 Analysis of Daily Charges
2 4" 6.00 0.00 0.00 0.00 LABOUR
3 5" 4.00 0.00 0.00 0.00 Pipe fitter 1 No 0.00 0.00
4 6" 3.00 0.00 0.00 0.00 Unskilled Cooly 2 Nos 0.00 0.00
5 8" 2.00 0.00 0.00 0.00 Total 0.00
6 10" 1.50 0.00 0.00 0.00 Sundries 10.00 Percent -
7 12" 1.25 0.00 0.00 0.00 Total 0.00
8 15" 1.10 0.00 0.00 0.00 Contractor's Profit & Overheads 20.00 Percent -
9 18" 1.00 0.00 0.00 0.00 0.00

20 - c - Providing and fixing temporary wooden tapered plug of hard wood to each end of pipe line.
Detail 500' Rate for 100'
S. Size PLUG LABOUR FOR MAKING PLUG LABOUR FOR FIXING Grand Rate for
No. of Area of Length Contant Rate Per Amount Daily Daily Amount L. S. Sundries Total Contra- Total Total 100'
plug plug in Cft Progress Charges 10.00 ctor's for 500'
Cft (5 X 6) in No. (9 / 8) (11+12) profit (13+14) (15+10
20.00 + 7)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
x(3)2
1 3" 4x144 0.50 0.02 0.00 0.00 34.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Daily Charges
x(4)2
2 4" 4x144 0.50 0.04 275.00 11.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x(5)2 Hard Wood
3 5" 4x144 0.50 0.07 275.00 19.25 25.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Cft @ Rs. 0.00 0.00
x(6)2
4 6" 4x144 0.50 0.10 275.00 27.50 19.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Contractor's Profit & Overheads 20.00 0.00
x(8)2
5 8" 4x144 0.50 0.17 275.00 46.75 15.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
x(10)2
6 10" 4x144 0.75 0.41 275.00 112.75 12.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x(12)2
7 12" 4x144 0.75 0.59 275.00 162.25 9.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Carpenter 1 No. 0.00 0.00
x(15)2
8 15" 4x144 1.00 1.23 275.00 338.25 7.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Turner 1 No. 0.00 0.00
x(18)2
9 18" 4x144 1.00 1.77 275.00 486.75 5.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Sundries 10.00 Percent -
Total 0.00
Contractor's
Profit &
Overheads 20.00 Percent -
Total 0.00

2
20 - d - Testing and disinfecting C.I. Pipe.
Assume for 1000' (300 M) Rate for 100' Rate for 10'
S. I/D of Volume Amount Disin- Amount Hire Total Contra- Total LABOUR Composite Rate for Rate Charges
No. pipe in of Water @ Rs fecting @ Rs Charges ctor's Plugging Labour for Total for 1000 Rft 100' for 200 Rft
Inch required - Agent 0.00 of testing (7 + 6 Profit (8 + 9) of Pipe testing &
in Gallon Per Lbs/Kg Per Lbs/Kg operatus + 4) 20.00 disinfecting (11+12) (10 + 13)
Gallons Percent
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 3" 310.00 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Mechanic 1 No. 0.00 0.00
2 4" 720.00 0.00 1.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Coolies 2 Nos 0.00 0.00
3 5" 850.00 0.00 1.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
4 6" 1830.00 0.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Sundries 10.00 Percent -
5 8" 2180.00 0.00 3.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Contractor's
Profit &
6 10" 3410.00 0.00 5.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Overheads 20.00 Percent -
7 12" 4910.00 0.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Rate per 100
8 15" 8730.00 0.00 14.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rft 0.00
9 18" 11000.00 0.00 18.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

20 - e Laying, cutting, jointing, testing & disinfecting C.I. pipe line in trenches with flanged &
flanged joint complete in all respects.

Length of pipe 12' (4 M). Rate for 100'


S. I/D of Bolts & Nuts Per Joint Rubber insertion 1/8" Total Contra- Total Labour Composite Rate Per Composite Composite
No. pipe Size No Rate Amount thick per joint. ctor's Material No. of Daily Amount rate 100' pipe rate per rate per
Dia Length of 5x6 Weight in Amount 7+9 Profit P. Joint Joints in Charges P. Joint length Ft Metre
Bolts Lbs/kg 7x8 20.00 10 + 11 One Day 14 / 13 for 12' 16 x 100
Percent 12

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 18
1 3" 5/8" 2" 4.00 0.00 0.00 0.46 0.00 0.00 0.00 0.00 11.00 0.00 0.00 0.00 0.00 0.00 0.00
2 4" 5/8" 2" 4.00 0.00 0.00 0.61 0.00 0.00 0.00 0.00 10.00 0.00 0.00 0.00 0.00 0.00 0.00
3 5" 5/8" 3" 6.00 0.00 0.00 1.00 24.00 24.00 1.20 25.20 9.00 0.00 0.00 0.00 0.00 0.00 0.00
4 6" 5/8" 3" 6.00 0.00 0.00 1.18 28.32 28.32 1.42 29.74 8.00 0.00 0.00 0.00 0.00 0.00 0.00
5 8" 3/4" 3" 8.00 0.00 0.00 1.20 28.80 28.80 1.44 30.24 8.00 0.00 0.00 0.00 0.00 0.00 0.00
6 10" 3/4" 3" 12.00 0.00 0.00 1.86 44.86 44.86 2.24 47.10 6.00 0.00 0.00 0.00 0.00 0.00 0.00
7 12" 3/4" 3" 12.00 0.00 0.00 2.50 60.24 60.24 3.01 63.25 5.00 0.00 0.00 0.00 0.00 0.00 0.00
8 15" 7/8" 4" 12.00 0.00 0.00 2.84 69.36 69.36 3.47 72.83 3.00 0.00 0.00 0.00 0.00 0.00 0.00
9 18" 7/8" 4" 12.00 0.00 0.00 3.42 82.08 82.08 4.10 86.18 2.00 0.00 0.00 0.00 0.00 0.00 0.00

Daily Charges
Plumber 1 No 0.00 Sundires 10.00 Percent 0.00
Cooly 1 No 0.00 Total 0.00
0.00 Contractor's Profit & Overheads 20.00 Percent 0.00
Total 0.00

3
21-
complete in all respects.

S. Internal Weight of Weight Carriage of Lowering into Cutting ends Pluging Testing and Jointing Total charges Composite Composite
No. dia of 12' length of 100' 100' pipe trenches strin- chipping, fini- with disinfecting with lead for 100' rate per Ft rate per
pipe of pipe in length from field store ging & laying to shing surface temporary joint (30 M) Metre
lbs of pipe to site lead correct alignment to uniform wooden plug (5 + 6 + 7 +
in ton. four chain Ton and grade finish 8 + 9 + 10)
@ of Rs.

1 2 3 4 5 6 7 8 9 10 11 12 13
1 3" - 0.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 4" - 0.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 5" - 0.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 6" - 1.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 8" - 1.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 10" - 1.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 12" - 2.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 15" - 3.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 18" - 4.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

21 - a Lowering into trenches, stringing and laying C.I. pipe line to correct alignment and gradient.

S. Internal LABOUR
No. dia Daily Daily Amount per Rate 100 ft
Progress Charges 100 ft Analysis for daily charges

1 3" 400 0.00 0.00 - Plumber 1 No 0.00 -


2 4" 400 0.00 0.00 - Coolies 2 Nos 0.00 -
3 5" 300 0.00 0.00 - Total -
4 6" 300 0.00 0.00 - Sundries 10.00 Percent -
5 8" 225 0.00 0.00 - Total -
6 10" 175 0.00 0.00 - Contractor's Profit & Overhe 20.00 Percent -
7 12" 150 0.00 0.00 - Total -
8 15" 125 0.00 0.00 -
9 18" 100 0.00 0.00 -

1
21 - b Cutting cast iron pipe, chipping & finishing the face to uniform finish = Cut at every 200ft (60 M)
For 200' (60 M)
S. I/D Labour for Cutting & finishing Rate per
No. of No. of Daily Rate per 100 ft
Pipe cut P. day Charges 200 ft per cut
per cut

1 2 3 4 5 6
1 3" 8.00 0.00 0.00 0.00 Analysis of Daily Charges
2 4" 6.00 0.00 0.00 0.00 LABOUR
3 5" 4.00 0.00 0.00 0.00 Pipe fitter 1 No 0.00 0.00
4 6" 3.00 0.00 0.00 0.00 Unskilled Cooly 2 Nos 0.00 0.00
5 8" 2.00 0.00 0.00 0.00 Total 0.00
6 10" 1.50 0.00 0.00 0.00 Sundries 10.00 Percent -
7 12" 1.25 0.00 0.00 0.00 Total 0.00
8 15" 1.10 0.00 0.00 0.00 Contractor's Profit & Overheads 20.00 Percent -
9 18" 1.00 0.00 0.00 0.00 0.00

21 - c - Providing and fixing temporary wooden tapered plug of hard wood to each end of pipe line.
Detail 500' Rate for 100'
S. Size PLUG LABOUR FOR MAKING PLUG LABOUR FOR FIXING Grand Rate for
No. of Area of Length Contant Rate Per Amount Daily Daily Amount L. S. Sundries Total Contra- Total Total 100'
plug plug in Cft Progress Charges 10.00 ctor's for 500'
Cft (5 X 6) in No. (9 / 8) (11+12) profit (13+14) (15+10
20.00 + 7)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
x(3)2
1 3" 4x144 0.50 0.02 0.00 0.00 34.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Daily Charges
x(4)2
2 4" 4x144 0.50 0.04 0.00 0.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

x(5) 2
Hard Wood
3 5" 4x144 0.50 0.07 0.00 0.00 25.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Cft @ Rs. 0.00 0.00
x(6)2
4 6" 4x144 0.50 0.10 0.00 0.00 19.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Contractor's Profit & Over 20.00 0.00
x(8)2
5 8" 4x144 0.50 0.17 0.00 0.00 15.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
x(10)2
6 10" 4x144 0.75 0.41 0.00 0.00 12.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x(12)2
7 12" 4x144 0.75 0.59 0.00 0.00 9.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Carpenter 1 No. 0.00 0.00
x(15)2
8 15" 4x144 1.00 1.23 0.00 0.00 7.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Turner 1 No. 0.00 0.00
x(18)2
9 18" 4x144 1.00 1.77 0.00 0.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Sundries 10.00 Percent -
Total 0.00

Contractor's
Profit &
Overheads 10.00 Percent -
Total 0.00

2
20 - d - Testing and disinfecting C.I. Pipe.
Assume for 1000' (300 M) Rate for 100'
S. I/D of Volume Amount Disin- Amount Hire Total Contra- Total LABOUR Composite Rate for Rate Charges
No. pipe in of Water @ Rs fecting @ Rs. Charges ctor's Plugging Labour for Total for 1000 Rft 100' for 200 Rft
Inch required - Agent 0.00 of testing (7 + 6 Profit (8 + 9) of Pipe testing &
in Gallon Per Lbs/Kg Per Lbs/Kg operatus + 4) 20.00 disinfecting (11+12) (10 + 13)
Gallons Percent
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 3" 310.00 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Mechanic 1 No. 0.00 0.00
2 4" 720.00 0.00 1.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Coolies 2 Nos 0.00 0.00
3 5" 850.00 0.00 1.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
4 6" 1830.00 0.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Sundries 10.00 Percent -
5 8" 2180.00 0.00 3.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00

Contractor'
s Profit &
6 10" 3410.00 0.00 5.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Overheads 10.00 Percent -
7 12" 4910.00 0.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Rate per
8 15" 8730.00 0.00 14.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 100 Rft 0.00
9 18" 11000.00 0.00 18.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3
21 Laying, cutting, jointing, testing & disinfecting cast iron pipe line in trenches with tyton joints
complete in all respect.

Length of pipe 18' (5.4 M).Rate for 100'


S. I/D of Cost of Ring Total Composite
No. pipe in Rate Amount Contra ctor's Total Material rate per
Inche of ring Profit Material for 100' 100 ft
20.00 P. joint 6 x 100
Percent 18

1 2 3 4 5 6 7 8
1 3" 0.00 0.00 0.00 0.00 0.00
2 4" 0.00 0.00 0.00 0.00 0.00
3 5" 0.00 0.00 0.00 0.00 0.00
4 6" 0.00 0.00 0.00 0.00 0.00
5 8" 0.00 0.00 0.00 0.00 0.00
6 10" 0.00 0.00 0.00 0.00 0.00
7 12" 0.00 0.00 0.00 0.00 0.00
8 15" 0.00 0.00 0.00 0.00 0.00
9 18" 0.00 0.00 0.00 0.00 0.00

4
21 Laying,cutting,jointing,testing and disinfecting Cast Iron Pipe line in trenches with Tyton joints,complete in all respect.

S. Internal eight of 10 Carriage of Lowering into Cutting ends Pluging Testing and Jointing Total charges Composite Composite
No. dia of length of 100' pipe trenches strin- chepping, fini- with disinfecting with rubber for 100' rate Per Ft rate Per
pipe pipe in ton from field store ging & laying to shing surface temporary ring (30 M) Metre
to site lead correctalignment to uniform wooden plug (4 + 5 + 6 +
four chain @ and grade finish 7 + 8 +9)
Rs. Tons
1 2 3 4 5 6 7 8 9 10 11 12
1 3" 0.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 4" 0.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 5" 0.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 6" 1.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 8" 1.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 10" 1.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 12" 2.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 15" 3.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 18" 4.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

5
21 - a - Lowering into trenches, stringing and laying C.I. pipe line to correct alignment and gradient.

S. Internal LABOUR
No. dia Daily Daily Amount per Rate 100 ft
Progress Charges 100 ft Analysis for daily charges

1 3" 400 0.00 0.00 0.00 Plumber 1 No 0.00 0.00


2 4" 400 0.00 0.00 0.00 Coolies 2 Nos 0.00 0.00
3 5" 300 0.00 0.00 0.00 Total 0.00
4 6" 300 0.00 0.00 0.00 Sundries 10.00 Percent -
5 8" 225 0.00 0.00 0.00 Total 0.00
6 10" 175 0.00 0.00 0.00 Contractor's Profit & Overhe 20.00 Percent -
7 12" 150 0.00 0.00 0.00 Total 0.00
8 15" 125 0.00 0.00 0.00
9 18" 100 0.00 0.00 0.00

6
21 - b Cutting cast iron pipe, chipping & finishing the face to uniform finish = Cut at every 200ft (60 M)
For 200' (60 M)
S. I/D Labour for Cutting & finishing Rate per
No. of No. of Daily Rate per 100 ft
Pipe cut P. day Charges 200 ft per cut
per cut

1 2 3 4 5 6

1 3" 8.00 0.00 0.00 0.00 Analysis of Daily Charges

2 4" 6.00 0.00 0.00 0.00 LABOUR

3 5" 4.00 0.00 0.00 0.00 Pipe fitter 1 No 0.00 0.00

4 6" 3.00 0.00 0.00 0.00 Unskilled Cooly 2 Nos 0.00 0.00

5 8" 2.00 0.00 0.00 0.00 Total 0.00

6 10" 1.50 0.00 0.00 0.00 Sundries 10.00 Percent -

7 12" 1.25 0.00 0.00 0.00 Total 0.00

8 15" 1.10 0.00 0.00 0.00 Contractor's Profit & Overheads 20.00 Percent -

9 18" 1.00 0.00 0.00 0.00 0.00

7
22 Providing, laying, cutting, jointing, testing and disinfecting GI pipeline in trenches, with socket joint, using GI pipes of BSS 1387 - 1967
complete in all respects, with specials and valves.
(I) Light Quality
Length of pipe 18' (5.4 M). Rate for 100'
Material Labour Rate Rate per Metre
S. Dia of Rate per Adust- Wastage Special Total Contra- Total No of Prog- Daily Cost Total Total Carr- Testing Labour Compo- Labour Composite Labour Composite
No. pipe in 100' for orum 2% 10% ctor's Joints ress Charges per jointing 13 + 14 iage site for for Per ft for per ft
Inche light 1% 3+4+ Profit in line Joint material x 10 15 + 16 100'
quality 5+6 20.00 + 17 9 + 18 18 / 100 19 / 100
Perfect
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

1 " 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 40.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00

2 " 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 35.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00

3 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

5 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

6 2" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 28.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

7 2" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 28.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

8 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 25.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

9 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 23.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Plumber 1 No. 0.00 0.00


Cooly 2 Nos. 0.00 0.00

Total 0.00
Contractor's Profit & Overheads 20.00 Percent - Sundries 20.00 Percent -
Total 0.00 Total 0.00

1
22 Providing, laying, cutting, jointing, testing and disinfecting GI pipeline in trenches, with socket joint, using GI pipes of BSS 1387 - 1967
complete in all respects, with specials and valves.
(ii) Medium Quality
Length of pipe 18' (5.4 20 Rate for 100'
Material Labour Rate Rate per Metre
S. Dia of Rate per Adust- Wastage Special Total Contra- Total No of Prog- Daily Cost Total Total Carr- Testing Labour Compo- Labour Composite Labour Composite
No. pipe in 100' for orum 2% 10% ctor's Joints ress Charges per jointing 13 + 14 iage site for for Per ft for per ft
Inche light 1% 3+4+ Profit in line Joint material x 10 15 + 16 100'
quality 5+6 20.00 + 17 9 + 18 18 / 100 19 / 100
Perfect
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

1 " 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 40.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00

2 " 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 35.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00

3 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

5 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

6 2" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 28.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

7 2" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 28.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

8 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 25.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

9 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 23.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

10 5" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

11 6" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Plumber 1 No. 0.00 0.00


Cooly 2 Nos. 0.00 0.00

Total 0.00
Contractor's Profit & Overheads 20.00 Percent - Sundries 10.00 Percent -
Total 0.00 Total 0.00

2
3
22 Providing, laying, cutting, jointing, testing and disinfecting GI pipeline in trenches, with socket joint, using GI pipes of BSS 1387 - 1967
complete in all respects, with specials and valves.
(iii Heavy Quality
Length of pipe 18' (5.4 M). Rate for 100'
Material Labour Rate Rate per Metre
S. Dia of Rate per Adust- Wastage Special Total Contra- Total No of Prog- Daily Cost Total Total Carr- Testing Labour Compo- Labour Composite Labour Composite
No. pipe in 100' for orum 2% 10% ctor's Joints ress Charges per jointing 13 + 14 iage site for for Per ft for per ft
Inche light 1% 3+4+ Profit in line Joint material x 10 15 + 16 100'
quality 5+6 20.00 + 17 9 + 18 18 / 100 19 / 100
Perfect
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

1 " 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 40.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00

2 " 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 35.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00

3 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

5 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

6 2" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 28.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

7 2" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 28.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

8 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 25.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

9 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 23.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

10 5" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

11 6" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Plumber 1 No. 0.00 0.00


Cooly 2 Nos. 0.00 0.00

Total 0.00
Contractor's Profit & Overheads 20.00 Percent - Sundries 10.00 Percent -
Total 0.00 Total 0.00

4
5
6
7
8
9
10
23 Providing laying, cutting, jointing, testing & disinfecting AC pipeline of BSS with "B" Class working pressure pipe in
trenches with cement joint & rubbering complete in all respect.

Material Labour for 100' Rate per 100 Ft Rate per Ft Rate per Metre
S. Dia Cost of Wast- Total Contra- Total Carriage Grand Lowering Cutting Cleaning Testing Plugging Labour Compo- Labour Composite Labour Composite
No. of pipe with age ctor's for 100' Per ft Total into end end of and wooden site for for per
pipe coment 2% (3 + 4) Profit AC pipe length for 100 Ft trenches pipe disinf- plug Per ft ft
joint & 20.00 (5 + 6) (4 chain) & laying ecting 10 + 16
rubber Percent
ring
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 6" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 8" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 10" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 12" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 14" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 16" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 18" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10 20" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 24" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

1
24 Providing laying, cutting, jointing, testing & disinfecting AC pipeline of BSS with "C" Class working pressure pipe in
trenches with cement joint & rubbering complete in all respect.

Material Labour for 100' Rate per 100 Ft Rate per Ft Rate per Metre
S. Dia Cost of Wast- Total Contra- Total Carriage Grand Lowering Cutting Cleaning Testing Plugging Labour Compo- Labour Composite Labour Composite
No. of pipe with age ctor's for 100' Per ft Total into end end of and wooden site for for per
pipe coment 2% (3 + 4) Profit AC pipe length for 100 Ft trenches pipe disinf- plug Per ft ft
joint & 20.00 (5 + 6) (4 chain) & laying ecting 10 + 16
rubber Percent
ring 20
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 6" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 8" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 10" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 12" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 14" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 16" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 18" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10 20" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 24" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2
25 Providing laying, cutting, jointing, testing & disinfecting AC pipeline of BSS with "D" Class working pressure pipe in
trenches with commet joint & rubbering complete in all respect.

Material Labour for 100' Rate per 100 Ft Rate per Ft Rate per Metre
S. Dia Cost of Wast- Total Contra- Total Carriage Grand Lowering Cutting Cleaning Testing Plugging Labour Compo- Labour Composite Labour Composite
No. of pipe with age ctor's for 100' Per ft Total into end end of and wooden site for for per
pipe coment 2% (3 + 4) Profit AC pipe length for 100 Ft trenches pipe disinf- plug Per ft ft
joint & 20.00 (5 + 6) (4 chain) & laying ecting 10 + 16
rubber Percent
ring
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

1 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3 6" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4 8" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

5 10" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

6 12" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

7 14" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

8 16" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

9 18" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

10 20" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3
re

4
re

5
re

6
23.Cleaning pipe placing rubber in position pressing with assembling machine, of AC pipe.

S. I/D No of Labour Amount Hire Total


# of joining charges Charges
Pipe per day per day of Machine

1 2 3 4 5 6
1 3" 36.00 0.00 0.00 0.00 0.00
2 4" 32.00 0.00 0.00 0.00 0.00 machine, and jointing.
3 6" 28.00 0.00 0.00 0.00 0.00 LABOUR
4 8" 24.00 0.00 0.00 0.00 0.00 Plumber 1 No 0.00 0.00
5 10" 20.00 0.00 0.00 0.00 0.00 Skilled Cooly 1 No 0.00 0.00
6 12" 16.00 0.00 0.00 0.00 0.00 Total 0.00
7 14" 14.00 0.00 0.00 0.00 0.00 Sundries 10.00 Percent 0.00
8 16" 13.00 0.00 0.00 0.00 0.00
9 18" 12.00 0.00 0.00 0.00 0.00 Total 0.00
10 20" 10.00 0.00 0.00 0.00 0.00 Contractor's Profit & Overheads 20.00 Percent 0.00
11 24" 8.00 0.00 0.00 0.00 0.00 0.00

1
23 - Lowering into trenches, stringing and laying to correct alignment AC pipe "Class B" etc.

S. Size No. of Labour for Amount


No. of Days Charges
pipe for 100' per day

1 2 3 4 5

1 3" 0.500 0.00 0.00

2 4" 0.515 0.00 0.00 Daily Labour Charges

3 6" 0.703 0.00 0.00

4 8" 0.974 0.00 0.00 Plumber 1 No 0.00 0.00

5 10" 1.289 0.00 0.00 Unskilled Cooly 2 Nos 0.00 0.00

6 12" 1.673 0.00 0.00 Total 0.00

7 14" 1.915 0.00 0.00 Sundries 10 Percent 0.00

8 16" 2.157 0.00 0.00 Total 0.00

9 18" 2.555 0.00 0.00 Contractor's Profit & Overheads 20 20.00 0.00

10 20" 2.981 0.00 0.00 0.00

11 24" 3.480 0.00 0.00

2
23 Providing, laying, cutting, jointing testing & disinfecting A.C. pipe line of BSS with "B Class" working
pressure pipe in trenches with cement joint and rubber ring complete in all respect.
Detail for 1000' (Disinfecting and testing Rate
rate for 100'
S. Dia Volume of Amount Disin- Amount Hire Total Contra- Total Labour Per Joint Composite Composite Composite Rate
# of Water in @ Rs fecting @ Rs. Charges ctor's Plugging Labour Total rate for rate for Rate per Rate per
pipe P. Gallon 0 agent 0 of testing 4+6 Profit 8+9 of pipe for testing ft % ft. Rft Metre
Per in Lbs Per apparatus +7 20.00 and disin- 11 + 12 10 + 13
Gallons Lbs Percent fecting

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

1 3" 310.00 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

2 4" 720.00 0.00 1.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

3 6" 1820.00 0.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

4 8" 2180.00 0.00 3.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

5 10" 3410.00 0.00 5.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

6 12" 4910.00 0.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
7 14" 6810.00 0.00 11.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

8 16" 8710.00 0.00 14.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

9 18" 11000.00 0.00 18.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

10 20" 13600.00 0.00 22.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

11 24" 19600.00 0.00 32.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -

Labour for Testing 2000 ft

Mechanic 1 No. 0.00 0.00 Sundires 10.00 0.00 0 0.00


2
Cooly 2 Nos 0.00 0.00 Total 0.00

Total 0.00 Contractor's Profit & Overheads 20.00 0.00

Total 0.00

1
Providing and fixing temporary wooden plug.
Assume for 500' Rate for 100'
S. Size PLUG MATERIAL LABOUR FOR MAKING PLUG LABOUR FOR FIXING
# of Area of Length Rate Contents Amount Daily Daily Amount L.S. Sundries Total Contra- Total Grand Rate Rate
pipe Plug Sft per Cft in Cft Progress Rate 20 10 ctor's Total for 100' per Metre
5x6 in No. 9/8 Percent Profit 13 + 14 for 500'
20 7 + 10
Percent + 15
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
9x(3)2
1 3" 4x144 0.50 0.00 0.02 0.00 34.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Daily Charges
9x(4)2
2 4" 4x144 0.50 0.00 0.04 0.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

9x(6)2 Hard Wood


3 6" 4x144 0.50 0.00 0.10 0.00 19.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1 Cft 0.00 0.00

Contractor'
9x(8)2 s Profit &
4 8" 4x144 0.50 0.00 0.17 0.00 15.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Overheads 20.00 0.00
9x(10)2
5 10" 4x144 0.75 0.00 0.41 0.00 12.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
9x(12)2
6 12" 4x144 0.75 0.00 0.59 0.00 9.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9x(14)2 Carpenter
7 14" 4x144 0.75 0.00 1.07 0.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1 No. 0.00 0.00
9x(16)2 Turner
8 16" 4x144 1.00 0.00 1.40 0.00 7.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1 No. 0.00 0.00
9x(18)2
9 18" 4x144 1.00 0.00 1.77 0.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
9x(20)2
10 20" 4x144 1.00 0.00 2.18 0.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Sundries 20.00 0.00
9x(20)2
11 24" 4x144 1.25 0.00 3.93 0.00 3.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00

Contractor'
s Profit &
Overheads 20.00 0.00
Total 0.00

2
Lowering into trenches, stringing and laying to correct alignment AC pipe "Class D" etc.

S. Size No. of Labour for Amount


No. of Days Charges
pipe for 100' per day

1 2 3 4 5
1 3" 0.500 0.00 0.00 Lowering into trenches stringing and laying to correct alignment.
2 4" 0.515 0.00 0.00 Daily Labour Charges
3 6" 0.703 0.00 0.00
4 8" 0.974 0.00 0.00 Plumber 1 No 0.00 0.00
5 10" 1.289 0.00 0.00 Unskilled Cooly 2 Nos 0.00 0.00
6 12" 1.673 0.00 0.00 Total 0.00
7 14" 1.920 0.00 0.00 Sundries 10 Percent 0.00
8 16" 2.157 0.00 0.00 Total 0.00
9 18" 2.555 0.00 0.00 Contractor's Profit & Overheads 20 Percent 0.00
10 20" 2.981 0.00 0.00 0.00
11 24" 3.480 0.00 0.00

3
26 Providing, laying cutting jointing testing and disinfecting PVC pipeline of BSS with Class "B" working
pressure pipe in pipes trenches complete in all respect.
Assume for 500' Rate for P. ft
S. Dia MATERIAL LABOUR Rate per 100' Rate per Rft Rate per Metre
No. of Rate Wastage Total Contra- Total Weight Rate Amount Contra- Total Labour Total Labour Composite Labour Composite Labour Composite
pipe for 100' 2% ctor's in of ctor's as per for 100' for 100' rate rate rate rate
Profit (5 + 6) Kg Lubricant (8 x 9) Profit (10 + 11) detail (12 +13) (7 + 15)
20.00 in Kg 20.00
Percent Percent
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

1 3" 0.00 0.00 0.00 0.00 0.00 0.303 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00

2 4" 0.00 0.00 0.00 0.00 0.00 0.339 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00

3 5" 0.00 0.00 0.00 0.00 0.00 0.464 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00

4 6" 0.00 0.00 0.00 0.00 0.00 0.544 0.00 0.00 0.00 0.00 20.00 20.00 ##### 20.00 0.20 0.20 0.66 0.66

5 8" 0.00 0.00 0.00 0.00 0.00 0.789 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00

6 10" 0.00 0.00 0.00 0.00 0.00 0.865 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00

7 12" 0.00 0.00 0.00 0.00 0.00 1.037 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00

8 14" 0.00 0.00 0.00 0.00 0.00 1.179 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00

1
Labour for laying, cutting, jointing, pipeline in trenches with PVC pipes of BSS with
"B" Class working pressure, complete in all respect.
Rate for 100 ft
S. # Dia CarriageLAYING, FIXING, CUTTING, JOINTING Testing Total Rate
of for lead Time for Daily Amount & for 100'
pipe 4 chains 100' Expenses Disinfecting 6+7

1 2 3 4 5 6 7 8 9

1 2" 0.00 0.10 0.00 0.00 -0.22 -0.22 #####


2 3" 0.00 1/8 0.00 0.00 0.00 0.00 - Plumber 1 No 0.00 0.00
3 4" 0.00 1/6 0.00 0.00 0.00 0.00 - S. Coolies 2 No 0.00 0.00
4 5" 0.00 1/5 0.00 0.00 0.00 0.00 - Total 0.00
5 6" 0.00 1/5 0.00 0.00 0.00 0.00 ##### Sundries 10.00 Percent 0.00
6 8" 0.00 2/7 0.00 0.00 0.00 0.00 - Total 0.00
7 10" 0.00 2/5 0.00 0.00 0.00 0.00 - Contractor's P 20.00 Percent 0.00
8 12" 0.00 1/2 0.00 0.00 0.00 0.00 - Total 0.00
9 14" 0.00 2/3 0.00 0.00 0.00 0.00 -

2
3
4
27 Providing, laying, cutting, jointing, testing & disinfecting pipeline in trenches with PVC pipes of BSS with "D"
Class working pressure, complete in all respect.
Unit of rate per ft.
S. Dia Material Labour Rate per 100' Rate per Ft Rate per Metre
# of Rate for Wastage Total Contra- Total Lubri- Rate Amount Contra- Total Labour Total Labour Composite Labour Composite Labour Composite
pipe 100' 2% ctor's cant per Kgs ctor's as per
(3 + 4) Profit (5 + 6) Kgs (8 x 9) Profit (10+11) detail (12+13) (7 + 15)
20.00 20.00 24
Percent Percent
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

1 2" 0.00 0.00 0.00 0.00 0.00 0.259 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2 3" 0.00 0.00 0.00 0.00 0.00 0.303 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3 4" 0.00 0.00 0.00 0.00 0.00 0.339 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4 5" 0.00 0.00 0.00 0.00 0.00 0.464 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

5 6" 0.00 0.00 0.00 0.00 0.00 0.544 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

1
28 Providing and fixing cast iron special of BSS class "B" (such as bend, tee, cross collar, reducer, tail piece, flanged spigot,
cap, flanged socket, taper, angle branch, plug, etc.) for cast iron pipe line, complete.
a- C-I specials with spigot and socket joint.

Labour Casting material (Supply of specials i/c moulding, painting,


carriage to site of work.
S. Dia Average Labour Material Total Total Total Rate Rate Contractor's Total Rate Rate per Kg
No. of Waight for for Labour for weight Cost per Kg per Cwt Profit per Kg Labour Composite
pipe in 2 Joints 2 Joints 2 Joints of special 20.00 13 + 14
Lbs 4+5 Percent

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 3" 46.00 0.00

4" 61.00 0.00

5" 88.00 0.00


or
138.84
6" 111.00 0.00 Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2 8" 182.00 0.00

10" 273.00 0.00


or
396.55
12" 392.00 0.00 Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3 15" 540.00 0.00


or
583.48
18" 746.00 0.00 Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

1
28 - Providing and fixing cast iron special of BSS class "B" (such as bend, tee, cross collar, reducer, tail piece, flanged spigot,
cap, flanged socket, taper, angle branch, plug, etc.) for cast iron pipe line, complete.
b- CI flanged special with flanged and flanged joints.

Labour Material Rate


S. Dia Average Labour rate for 2 Labour rate per Lbs Supply of special (cost of material, Rate per Kg
No. of Weight joints. weight. with moulding, painting, and carriage to Labour Composite
pipe in Labour Material Total Total Total Rate site of work. rate per rate per
Lbs/Kg weight Amount per Kg Rate Contractor's Total Rate Kg Kg
(4 + 5) 20 P/ Cwt Profit per Kg
20.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 3" 32.00

4" 48.00

5" 83.00
or
116.15
6" 93.00 Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2 8" 161.00

10" 250.00
or
357.08
12" 376.00 Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3 15" 453.00
or
498.00
18" 646.00 Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2
28 Providing and fixing cast iron special of BSS class "B" (such as bend, tee, cross collar, reducer, tail piece, flanged spigot,
cap, flanged socket, taper, angle branch, plug, etc.) for cast iron pipe line, complete.
c- CI specials with tyton joints.

Weight Labour Material Rate


S. Dia Average Labour rate for 2 Labour rate per Lbs Supply of special (cost of material Rate Rate per Kg
No. of Weight joints. weight. with moulding, painting, and per Labour Composite
pipe in Labour Material Total Total Total Rate carriage to site of work. Kg rate per rate per
Lbs weight of cost per Rate Contr- Total Kg Kg
specials Kg per Cwt actor's
Profit
20.00

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 3" 42.00

4" 60.00

5" 84.00
324.76
Lbs or
147.62
6" 109.00 Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2 8" 175.00

10" 265.00
Lbs or
244.20
12" 374.00 Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3 15" 654.00
921.80
Lbs or
419.00
18" 898.00 Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3
29 Providing and fixing C.I. special of BSS Class "B" (such as bend, tee, cross, collar, reducer, tail piece, flanged socket, flanged
spigot, cap, taper, angle branch plug etc.) for AC pipe line with comet joint and rubber ring complete.

Labour Material
S. Dia Average Labour rate for 2 Labour rate per Supply of special (cost of material, Rate per Kg
# of Weight joints. Kg. with moulding, painting, and carriage to Labour Composite
pipe in Labour Material Total Total Total Rate site of work. rate per rate per
Lbs weight Amount per Kg Rate P. Contractor's Total Rate Kg Kg
Cwt Profit per Lbs
20.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 3" 46.00
4" 61.00
204 Lbs
or 92.56
6" 97.00 Kgs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 8" 175.00
10" 250.00
12" 370.00
16" 549.00
2037 Lbs
or
927.23
18" 693.00 Kgs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 20" 937.00

2254 Lbs
or 1022
24" 1317.00 Kgs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4
30 - Providing and fixing sluice valve of BSS quality and weight Class "B" for cast iron pipe

Each
Material Labour Rate
S. Dia of Cost of Contractor's Total No of Daily Total Labour Composite
No. sluice sluice Profit day Labour
valve valve 20 (3 + 4) (5 + 9)
Percent
1 2 3 4 5 6 7 8 9 10

1 3" - 0.00 0.00 0.340 0.00 0.00 - 0.00 Labour 3" to 8"

2 4" - 0.00 0.00 0.370 0.00 0.00 - 0.00 Plumber 1 No 0.00 0.00

3 5" - 0.00 0.00 0.666 0.00 0.00 - 0.00 Skilled Coolies 2 No 0.00 0.00

4 6" - 0.00 0.00 0.710 0.00 0.00 - 0.00 Total 0.00

5 8" - 0.00 0.00 0.829 0.00 0.00 - 0.00 Sundries 10.00 Percent 0.00

6 10" - 0.00 0.00 0.889 0.00 0.00 - 0.00 Total 0.00

7 12" - 0.00 0.00 0.999 0.00 0.00 - 0.00 Contractor's Profit & O 20.00 Percent 0.00

8 15" - 0.00 0.00 1.325 0.00 0.00 - 0.00 Total 0.00

9 18" - 0.00 0.00 1.525 0.00 0.00 - 0.00 Labour 10" to 18"

Plumber 1 No 0.00 0.00

Skilled Coolies 2 No 0.00 0.00

Unskilled Coolies 2 No 0.00 0.00

Total 0.00

Sundries 10.00 Percent 0.00

Total 0.00

Contractor's Profit & O 20.00 Percent 0.00

Total 0.00

1
31 Providing and fixing sluice valve of BSS quality & weight for AC pipeline with
commet joint & rubber ring complete i/c cost of jointing material.

S. Dia Material Labour for 2 joints Rate


No. of Cost of Contractor's Total Labour Material Total Labour Composite
sluice sluice Profit 6+7 rate rate
valve 20.00 (3 + 4) 5+8
Percent
1 2 3 4 5 6 7 8 9 10

1 3" - 0.00 0.00 0.00 0.00 0.00 - 0.00

2 4" - 0.00 0.00 0.00 0.00 0.00 - 0.00

3 6" - 0.00 0.00 0.00 0.00 0.00 - 0.00

4 8" - 0.00 0.00 0.00 0.00 0.00 - 0.00

5 10" - 0.00 0.00 0.00 0.00 0.00 - 0.00

6 12" - 0.00 0.00 0.00 0.00 0.00 - 0.00

7 16" - 0.00 0.00 0.00 0.00 0.00 - 0.00

8 18" - 0.00 0.00 0.00 0.00 0.00 - 0.00

1
31a Providing and fixing sluice valve of BSS quality and weight for A.C. pipe line with cement joint
and rubber ring complete including cost of jointing material.

Labour
Sr. Size No. of Charge Amount Daily Charge
No. Day per day
1 3" 12.30 0.00 0.00
2 4" 11.40 0.00 0.00
3 6" 10.35 0.00 0.00
4 8" 7.40 0.00 0.00
5 10" 9.30 0.00 0.00
6 12" 6.93 0.00 0.00
7 16" 6.10 0.00 0.00
8 18" 5.78 0.00 0.00

Labour 3' to 8'

Plumber 1 No. 0.00 0.00


Skilled Cooly 2 Nos. 0.00 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Pro 20.00 Percent 0.00
0.00
10' to 18"
Plumber 1 No. 0.00 0.00
Skilled Cooly 2 Nos. 0.00 0.00
Coolies 2 Nos. 0.00 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Pro 20.00 Percent 0.00
0.00

1
32 Providing and fixing fire hydrant BSS quality and weight of 2" dia including cost of
jointing material.

Material Fixing (Labour) Rate


Sr. Dia of Cost of Contractor's Total Labour Composite
No. Pipe Hydrant Profit Labour Material Total
20.00

1 2" - - - - - 0.00 - -

33 Providing and fixing Air Valve 3" (75mm) internal dia of BSS quality and weight complete
with jointing material.

Material Fixing (Labour) Rate


Sr. Dia of Cost of Contractor's Total Labour Composite
No. Pipe Air Valve Profit Labour Material Total
20.00

a Single - - - - - 0.00 - -

b Double - - - - - 0.00 - -

20

1
34 Providing and fitting CI flanges on pipes, including turning, threading, facing and fitting etc.
complete in all respects.

Per Flange Rates


S. Dia Labour Material Per Flange Per Kgs
# of No of Daily End Cutting Total Weight cost per cwt Total Labour Compo- Labour Compo-
pipe end Charges thread end per end of site site
thread flange (10 + 11)
P. day (5 + 6) in Lbs

1 2 3 4 5 6 7 8 9 10 11 12 13 14

a 3" 15.00 0.00 0.00 0.00 0.00 8.40 0.00 0.00 0.00 0.00 0.00 0.00 Labour

4" 14.00 0.00 0.00 0.00 0.00 12.60 0.00 0.00 0.00 0.00 0.00 0.00 Turner 1 No 0.00 0.00

5" 12.00 0.00 0.00 0.00 0.00 17.00 0.00 0.00 0.00 0.00 0.00 0.00 Unskilled Coolies 1 No 0.00 0.00

6" 11.00 0.00 0.00 0.00 0.00 21.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00

Average Sundries 10.00 Percen 0.00

b 8" 9.00 0.00 0.00 0.00 0.00 35.70 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00

10" 7.00 0.00 0.00 0.00 0.00 52.50 0.00 0.00 0.00 0.00 0.00 0.00 Contractor's Profi 10.00 Percen 0.00

12" 5.00 0.00 0.00 0.00 0.00 74.55 0.00 0.00 0.00 0.00 0.00 0.00 Mechanic &Total 0.00
Electrical
Average charges L.S.

c 15" 3.00 0.00 0.00 0.00 0.00 110.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00

18" 2.00 0.00 0.00 0.00 0.00 153.00 0.00 0.00 0.00 0.00 0.00 0.00

Average

1
35 Cutting C.I. Pipe and welding spigot or socket, flanged or tyton end after finishing ends of pipes.

Sr. No. Dia of Cutting Circumference Welding Charges Cutting G.Total Say Rate per Rate per
Pipe Inch. End of Pipe in Rate per Total 2 Ends and inch bore cm bore
Inch. Inch. (4 + 5) Finishing
(Double Col. 3)

1 2 3 4 5 6 7 8 9 10 11

1 3" (75mm) 0.00 9.42 0.00 0.00 0.00 0.00 - 0.00

2 4" (100mm) 0.00 12.57 0.00 0.00 0.00 0.00 - 0.00

3 5" (125mm) 0.00 15.71 0.00 0.00 0.00 0.00 - 0.00

4 6" (150mm) 0.00 18.85 0.00 0.00 0.00 0.00 - 0.00

Average

5 8" (20mm) 0.00 25.13 0.00 0.00 0.00 0.00 - 0.00

6 10" (250mm) 0.00 31.42 0.00 0.00 0.00 0.00 - 0.00

7 12" (300mm) 0.00 37.70 0.00 0.00 0.00 0.00 - 0.00

Average

8 15" (385mm) 0.00 47.12 0.00 0.00 0.00 0.00 - 0.00

9 18" (450mm) 0.00 56.55 0.00 0.00 0.00 0.00 - 0.00

Average

1
36 Providing, laying, cutting, jointing, testing and disinfecting G.I. Pipe Line in trenches, with flanged joints, using G.I. pipe of BSS 1387-1967 Heavy Quality complete in a
respects, including specials and valves:-

i) G.I. FLANGED JOINTS

Sr. Dia of Cost Speical Advot Wastage Total Contractor Total No. of Daily Daily Total Material Per Ft. Length
No. Pipe Inch 100' 10% 1% 2% (3 + 4 + Profit Joints Progress Charges Size No. Rate Amount
heavy + 5 + 6) 10% (7 + 8) (15 x 16)
quality

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
a 1" (40mm) - 0.00 0.00 0.00 0.00 0.00 0.00 8 20 0.00 0.00 3/8 3.00 - 0.00
b 2" (50mm) - 0.00 0.00 0.00 0.00 0.00 0.00 8 20 0.00 0.00 3/8 3.00 - 0.00
c 2" (63mm) - 0.00 0.00 0.00 0.00 0.00 0.00 8 20 0.00 0.00 5/8 3.00 - 0.00
d 3" (75mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 15 0.00 0.00 5/8 4.00 - 0.00
e 4" (100mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 12 0.00 0.00 5/8 4.00 - 0.00
f 6" (125mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 10 0.00 0.00 5/8 4.00 - 0.00
g 8" (150mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 10 0.00 0.00 5/8 4.00 - 0.00

DAILY PROGRESS
Mechanic 1 No. 170 0.00 0.00
Cooly 2 No. 75 0.00 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00

36 Providing, laying, cutting, jointing, testing and disinfecting G.I. Pipe Line in trenches, with flanged joints, using G.I. pipe of BSS complete in all 1387-1967 Medium Qua
respects, including specials and valves:-

ii) G.I. FLANGED JOINTS


20
Sr. Dia of Cost of Speical Advot Wastage Total Contr- Total No. of Daily Daily Labour Bolts and Nuts
No. Pipe Flanged 20.00 1% 2% actor's Joints Progress Charges for Size No. Rate Amount
Inch. Pipe Profit 100'
20.00

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
a 1" (40mm) - 0.00 0.00 0.00 0.00 0.00 0.00 8 20 0.00 0.00 3/8 3.00 - 0.00
b 2" (50mm) - 0.00 0.00 0.00 0.00 0.00 0.00 8 20 0.00 0.00 3/8 3.00 - 0.00
c 2" (63mm) - 0.00 0.00 0.00 0.00 0.00 0.00 8 20 0.00 0.00 5/8 3.00 - 0.00
d 3" (75mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 15 0.00 0.00 5/8 4.00 - 0.00
e 4" (100mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 12 0.00 0.00 5/8 4.00 - 0.00
f 6" (125mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 10 0.00 0.00 5/8 4.00 - 0.00
g 8" (150mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 10 0.00 0.00 5/8 4.00 - 0.00

DAILY PROGRESS

Mechanic 1 No. 170 0.00 0.00


Cooly 2 No. 75 0.00 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00

1
all

h of Pipe Total Contrator Total Carriage Testing Grand Rate Per 100 Ft Rate Per Foot Rate Per Metre
Wt. Amount (13 + Profit & Total Labour Composte Labour Composite Labour Composite
Lbs. Rs. 17 + 10% (20 + Disfi- (22 + 23 (9 + 26)
0.00 19) 21) necting + 24)
per Lbs.
18 19 20 21 22 23 24 25 26 27 28 29 30 31
0.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00

uality

Rubber Insertion Total Contr- Total Carriage Testing Grand Rate Per 100 Ft. Rate Per Ft. Rate Per Metre.
Wt. Amount (13 + 17 ator's (20 + 21) and Total Labour Compo- Labour Compo- Labour Composite
Lbs. Rs. + 19) Profit disin- (22 + 23 site site
- 10% fection + 24) (26 + 9)
per Lbs.
18 19 20 21 22 23 24 25 26 27 28 29 30 31
0.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00

2
3
Sr. No. 41

Making Connection for new Water Supply lines with the running main, including excavation of
trench and refilling, complete, but excluding cost of pipe and specials, etc.

i) Upto 150mm (6") i/d

Detail Unit Rate (British System) per Connection

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour
Cooly for excavating/ refilling the
trench 0.50 No 0.00 P. Day -
Plumber for cutting, connecting
pipe, etc. 2 cuts 0.25 No 0.00 P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's 20.00 Percent -


Total -

Bailing out water from the trench


after cutting running main, taking
average quantity of water as 500
Cft. (14 Cum) @ Rs. 272.25% Cft -
(Item No. 35, Chap: Miscellaneous) -
-
Rate Per Connection Say Rs. 0.00

20

1
ii) Upto 200mm (8") i/d

Detail Unit Rate (British System) per Connection

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Cooly for excavating/ refilling the


trench 0.50 No 0.00 P. Day -
Plumber for cutting, connecting
pipe, etc. 2 cuts 0.25 No 0.00 P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's#REF! Percent -
Total -

Bailing out water from the trench


after cutting running main, taking
average quantity of water as 700
Cft. (19.60 Cum) @ Rs. 272.25% Cft -
( Item No. 35, Chap: 26 ) -
-

Rate Per Connection Say Rs. 0.00

2
iii) Upto 250mm (10") i/d

Detail Unit Rate (British System) per Connection

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour
Cooly for excavating/ refilling the
trench 0.50 No 0.00 P. Day -
Plumber for cutting pipe, etc.
2 cuts 0.50 No 0.00 P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's 20.00 Percent -


Total -

Bailing out water from the trench


after cutting running main, taking
average quantity of water as 1000
Rs. -
Cft. (28 Cum %o Cft. -
( Item No. 35, Chap: 26 ) -
-

Labour Rate Per Connection Say Rs. 0.00

3
iv) Upto 300mm (12") i/d

Detail Unit Rate (British System) per Connection

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Cooly for excavating/ refilling the


trench 0.50 No 0.00 P. Day -
Plumber for cutting pipe, etc.
2 cuts 0.50 No 0.00 P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's 20.00 Percent -


Total -

Bailing out water from the trench


after cutting running main, taking
average quantity of water as 1500
Rs. -
Cft. (48 Cum %o Cft. -
( Item No. 35, Chap: 26 ) -
-

Labour Rate Per Connection Say Rs. 0.00

4
v) Upto 400mm (16") i/d

Detail Unit Rate (British System) per Connection

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Cooly for excavating/ refilling the


trench 0.50 No 0.00 P. Day -
Plumber for cutting pipe, etc.
2 cuts 0.75 No 0.00 P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's 20.00 Percent -


Total -

Bailing out water from the trench


after cutting running main, taking
average quantity of water as 1825
Rs. -
Cft.(51.10 Cu %o Cft. -
( Item No. 35, Chap: 26 ) -
-

Labour Rate Per Connection Say Rs. 0.00

5
vi) Upto 500mm (20") i/d

Detail Unit Rate (British System) per Connection

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Cooly for excavating/ refilling the


trench 0.50 No 0.00 P. Day -
Plumber for cutting pipe, etc.
2 cuts 0.75 No 0.00 P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's 20.00 Percent -


Total -

Bailing out water from the trench


after cutting running main, taking
average quantity of water as 2500
Cft.(70 Cum) Rs.
@ - %o Cft. -
( Item No. 35, Chap: 26 ) -
-

Labour Rate Per Connection Say Rs. 0.00

6
vii) Upto 600mm (24") i/d

Detail Unit Rate (British System) per Connection

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Cooly for excavating/ refilling the


trench 0.50 No 0.00 P. Day -
Plumber for cutting pipe, etc.
2 cuts 1.00 No 0.00 P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's 20.00 Percent -


Total -

Bailing out water from the trench


after cutting running main, taking
average quantity of water as 3000
Cft. (85 Cum)Rs. - %o Cft. -
( Item No. 35, Chap: 26 ) -
-

Labour Rate Per Connection Say Rs. 0.00

7
DESCRIPTION OF ITEM NO. 15-A Providing and fixing, 6" (150mm) thick RCC
manhole as per standard drawing STD/PD No.6
of 1977, complete in all respects.

Detail Gully trap frame hinged saUnit Rate (British System) per Set

Qty. Rate Per Amount


Unit (Rs.) (Rs.)

1. RCC Cover

a) 2"x22"x2" size angle iron rings =


1 x 22 x 26 = 6.81 Rft.
7 12
Weight @ 4.04 Lbs/Ft = 27.51 Lbs (12.43) Kg
b) M.S. round bars " dia
Straight bras 1 x 26 = 26 inch
2 x 24 = 48 inch
2 x 18 = 36 inch
bent up bars 1 x 2 = 28 inch
2 x 26 = 52 inch
2 x 20 = 40 inch
230 inch or 19.17 ft. 19.17 Ft.
Bars in upper distribution ring 1x22/7x1.5 = 4.71 Ft.
Bar in lower distribution ring 1x22/7x1.25 = 3.93 Ft.
in overlaps distribution ring 2x = 1.00 Ft.
28.81 Ft. @ 0.667 Lbs/Rft. = 19.22 Lbs 28.81 Ft.
a + b = 27.51 + 19.22 = 46.73 Lbs or
21.20 Kg 21.20 Kg

2. Tee Shaped @ 1 frame 37.324 Kg

Material

Steel 58.524 P. Kg -

Total -
Contractor's Profit & overhead chg: 20% -
Total -
C.O. -

RCC (1:2:4) in situ or precast


1 x 22 x 26 x 26 x x 6+5+5 x 1 = 1.74 Cft.
7 12 12 3 12

D/d for triangular portion


2xx1/6x = 0.04 Cft
Rectangular portion
2xx5/24 = 0.10 Cft 0.14 Cft
0.14 Cft 1.60 Cft P. Cft
(Item 6 b(i) Chapter No. 6) Total -

Labour

1. Welding ends of engle iron rings 1.00 No. Each -


2. Welding ends of M.S. bar to angle iron 20.00 Nos. Each -
3. Fixing manhole cover and frame
including carriage to site complete in all
respect. L.S.
4. Labour for RCC 1:2:4 concrete 1.74 Cft P. Cft
(Item 6 b(i) Chapter No. 6)
Total -
Contractor's profit & overhead chg:20% on 1.2 Rs.
Total -

Item Rates
Labour Rate Per Set Rs. - Say

Composite Rate Per Set Rs. Say


DESCRIPTION OF ITEM

1. Providing and Laying RCC Pipe moulded with cement concrete 1:1:3 with spigot socket or collar joint etc. including cost of reinforcement,
conforming to B.S. 5911 Part 1.1981, Class "L", including Carriage of Pipe from factory to site of work, lowering in trenches to correct
alignment and grade, jointing, cutting pipes where necessary, finishing and testing etc. complete.
h C.I. Gully trap frame hinged safety type.

Dia Material Per Meter Length LABOUR PER PIPE OF 6 FEET Labour Composite
of Pipe Market Wastage Rubber Contractor Carriage Laying Jointing Testing Labour Composite Rate Rate
mm Rate per 2% Ring - Total Profit Total Per Pipe Daily Daily Labour Charges Total Per Per Foot Per Per
Meter Per Inc 20 Amount (Rs)Progress Expenses Per Pipe Foot Metre Metre
Dia Pipe Percent
1 2 3 4 5 6 7 9 10 11 12 13 14 15 16 17 18

4" (100mm) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 180.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6" (150mm) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 150.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9" (225mm) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 120.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00

DESCRIPTON OF ITEM

2 Providing and laying non-reinforced concrete pipe moulded with Cement Concrete 1:1:3 Conforming to ASTM specification 14-73 Class-I including Carriage of
Pipe from Factory to Site of Work, Lowering in Trenches to Correct Alignment and Grade Jointing Cutting Pipe where necessary, finishing and testing etc.
complete.

Dia of Material Per Meter Length of Pipe LABOUR Per Pipe of 6 Ft. Length Labour Composite
Pipe Market Wastage Rubber Contractor Carriage Laying Jointing Testing Labour Composite Rate Rate
mm Rate per 3% Ring - Total Profit Total Wt. in Amount Daily Daily Per Charges Total Per Per Per Per
Metre Per Inc 20 Ton Progress Expenses Pipe Foot Foot Metre Metre
Dia Pipe Percent
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

4" (100mm) 0.00 0.00 0.00 0.00 0.00 0.00 0.043 0.00 180.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6" (150mm) 0.00 0.00 0.00 0.00 0.00 0.00 0.061 0.00 150.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8"(200mm) 0.00 0.00 0.00 0.00 0.00 0.00 0.094 0.00 144.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9" (225mm) 0.00 0.00 0.00 0.00 0.00 0.00 0.127 0.00 136.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10"(250mm 0.00 0.00 0.00 0.00 0.00 0.00 0.133 0.00 135.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Page 1
DESCRIPTION OF ITEM

3 Providing and laying RCC Pipe Sewers, Moulded with Cement Concrete 1:1:3 Confirming to ASTM Specification C-76-79 Class-II, Wall B, Including Carriage of
Pipe from Factory to tWith C.I. Gully trap frame hinged safety type.
etc. Complete.

Sr. Dia of Length Thicknes MATERIAL LABOUR FOR 8 FT. PIPE


No. Pipe of Pipe of Rate Per Wastage Rubber Contractors Carriage Laying Jointing Testing Composite Labour Composite
Inch. Ft. Pipe Ft. 2% Ring Per Total Profit Total Daily Daily Daily Per Charges Total Labour Rate Per Ft. Rate Per Rate Per
(Inches) Inch Rs. 20.00 Progress Amount Progress Expenses Pipe rate per Metre Metre
0.00 ft.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

1. 12" (300mm) 2.439 2.00 0.00 0.00 0.00 0.00 0.00 0.00 23.00 0.00 15.00 - 0.00 0.00 0.00

2. 15"(380mm) 2.439 2.25 0.00 0.00 0.00 0.00 0.00 0.00 17.00 0.00 12.00 - 0.00 0.00 0.00

3. 18"(460mm) 2.439 2.50 0.00 0.00 0.00 0.00 0.00 0.00 13.00 0.00 10.00 - 0.00 0.00 0.00

4. 21"(535mm) 2.439 2.75 0.00 0.00 0.00 0.00 0.00 0.00 10.00 0.00 8.00 - 0.00 0.00 0.00

5. 24"(1610mm 2.439 3.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 0.00 7.00 - 0.00 0.00 0.00

6. 27"(685mm) 2.439 3.25 0.00 0.00 0.00 0.00 0.00 0.00 7.00 0.00 6.00 - 0.00 0.00 0.00

7. 30"(760mm) 2.439 3.50 0.00 0.00 0.00 0.00 0.00 0.00 6.00 0.00 5.00 - 0.00 0.00 0.00

8. 33"(800mm) 2.439 3.75 0.00 0.00 0.00 0.00 0.00 0.00 5.00 0.00 4.00 - 0.00 0.00 0.00

9. 36"(915mm) 2.439 4.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 0.00 3.25 - 0.00 0.00 0.00

10. 42"(1070mm 2.439 4.50 0.00 12.50 0.00 12.50 2.50 15.00 3.00 0.00 2.50 - 0.00 0.00 0.00

11. 48"(1220mm 2.439 5.00 0.00 14.50 0.00 14.50 2.90 17.40 2.00 0.00 7.00 - 0.00 0.00 0.00

12. 54"(1370mm 2.439 5.50 0.00 16.80 0.00 16.80 3.36 20.16 2.00 0.00 5.00 - 0.00 0.00 0.00

13. 60"(1520mm 2.439 6.00 0.00 22.60 0.00 22.60 4.52 27.12 1.00 0.00 4.00 - 0.00 0.00 0.00

14. 66"(1680mm 2.439 6.50 0.00 27.50 0.00 27.50 5.50 33.00 1.00 0.00 2.50 - 0.00 0.00 0.00

15. 72"(1830mm 2.439 7.00 0.00 32.50 0.00 32.50 6.50 39.00 1.00 0.00 2.00 - 0.00 0.00 0.00

Page 2
DESCRIPTION OF ITEM

4 Providing and laying RCC Pipe Sewers, Moulded with Cement Concrete 1:1:3 Confirming to ASTM Specification C-76-79 Class-III wall B, Including Carriage of
Pipe from Factory to the Site of Work, Lowering in Trenches to Correct Alignment and Grade Jointing with Rubber Ring, Cutting Pipes where necessary, Testing
etc. Complete. in all respects.

Sr. Dia of Material Per Metre Length of Pipe LABOUR FOR 8' PIPE
No. Pipe Market Wastage Rubber Contractor Carriage Laying Jointing Total Total
Inch Rate 2% Ring Per Total Profit Total Daily Amount Daily Daily Rate Testing per Labour
Meter Inch Rs. 20.00 Progress Rs. Progress Expenses per Pipe Charges Pipe rate per
0.00 (Pipe) (Pipe) Per Pipe ft.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1. 12" (300mm) 0.00 0.00 0.00 0.00 0.00 0.00 23.00 0.00 15.00 (0.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2. 15"(380mm) 0.00 0.00 0.00 0.00 0.00 0.00 17.00 0.00 12.00 (0.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3. 18"(460mm) 0.00 0.00 0.00 0.00 0.00 0.00 13.00 0.00 10.00 (0.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4. 21"(535mm) 0.00 0.00 0.00 0.00 0.00 0.00 10.00 0.00 8.00 (0.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00

5. 24"(1610mm 0.00 0.00 0.00 0.00 0.00 0.00 8.00 0.00 7.00 (0.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00

6. 27"(685mm) 0.00 0.00 0.00 0.00 0.00 0.00 7.00 0.00 6.00 4.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00

7. 30"(760mm) 0.00 0.00 0.00 0.00 0.00 0.00 6.00 0.00 5.00 4.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00

8. 33"(800mm) 0.00 0.00 0.00 0.00 0.00 0.00 5.00 0.00 4.00 4.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00

9. 36"(915mm) 0.00 0.00 0.00 0.00 0.00 0.00 4.00 0.00 3.25 4.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00

10. 42"(1070mm 0.00 0.00 0.00 0.00 0.00 0.00 3.00 0.00 2.50 4.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00

11. 48"(1220mm 0.00 0.00 0.00 0.00 0.00 0.00 2.00 0.00 7.00 (1.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00

12. 54"(1370mm 0.00 0.00 0.00 0.00 0.00 0.00 2.00 0.00 5.00 (1.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00

13. 60"(1520mm 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 4.00 (1.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00

14. 66"(1680mm 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 2.50 (1.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00

15. 72"(1830mm 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 2.00 (1.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Page 3
DESCRIPTION OF ITEM

5 Providing and laying RCC Pipe Sewers, Moulded with Cement Concrete 1:1:3 Confirming to ASTM Specification C-76-79 Class-IV, Wall B, Including Carriage of
Pipe from Factory to the Site of Work, Lowering in Trenches to Correct Alignment and Grade Jointing with Rubber Ring, Cutting Pipes where necessary, Testing
etc. Complete.

Sr. Dia of MATERIAL PER METRE LENGTH LABOUR FOR 8' FT. PIPE
No. Pipe Market Wastage Rubber Contractors Carriage Laying Jointing Total Labour Labour Composite Labour Composite
mm Rate 2% Ring Per Total Profit Total Daily Amount Daily Daily Rate Testing Total Rate Per Rate Per Rate Per Rate Per Rate Per
Per Inch Rs. 20.00 Progress (Rs.) Progress Expenses Per Charges Per Metre Metre Metre Metre Metre
Metre 0.00 Pipe Pipe Per Pipe Pipe
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 15 16 17 18

1. 12" (300mm) 0.00 0.00 0.00 0.00 0.00 0.00 23.00 0.00 15.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2. 15"(380mm) 0.00 0.00 0.00 0.00 0.00 0.00 17.00 0.00 12.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3. 18"(460mm) 0.00 0.00 0.00 0.00 0.00 0.00 13.00 0.00 10.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4. 21"(535mm) 0.00 0.00 0.00 0.00 0.00 0.00 10.00 0.00 8.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5. 24"(1610mm 0.00 0.00 0.00 0.00 0.00 0.00 8.00 0.00 7.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6. 27"(685mm) 0.00 0.00 0.00 0.00 0.00 0.00 7.00 0.00 6.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7. 30"(760mm) 0.00 0.00 0.00 0.00 0.00 0.00 6.00 0.00 5.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8. 33"(800mm) 0.00 0.00 0.00 0.00 0.00 0.00 5.00 0.00 4.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9. 36"(915mm) 0.00 0.00 0.00 0.00 0.00 0.00 4.00 0.00 3.25 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10. 42"(1070mm 0.00 0.00 0.00 0.00 0.00 0.00 3.00 0.00 2.50 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11. 48"(1220mm 0.00 0.00 0.00 0.00 0.00 0.00 2.00 0.00 7.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12. 54"(1370mm 0.00 0.00 0.00 0.00 0.00 0.00 2.00 0.00 5.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13. 60"(1520mm 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 4.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14. 66"(1680mm 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 2.50 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15. 72"(1830mm 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 2.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Page 4
6 Lowering of Sub Soil Water table by Installation of Tubewell along Sewer Line and Pumping Out Water, for Excavation in Open Cutting below Sub Soil Water Level,
Concreting, Curing, Laying and Jointing Pipes, Filling hauncher etc, till the Completion of Sewer Line, including Disposal of Pumped Out Water

Depth of Distance PUMPING Shifting Depreciation BORING Disposal of Charges


Seria Lowering Between Rate Pump & Charges of pumped out by Pump Contractor Grand Rate Adopted
No. of Bore Hole Hours per Amount Installation Pumping Depth of Rate Amount water Rate Per Profit Total Per in
Meter Meter Hour at New Machinery Bore Per per 30 M Hour Amount Total 20.00 Ft. CSR 1998
Site (Rs.) Boring Meter distance 6+7+8+ 15+16
Equipment 11+12+14
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

1 0-1' 100.00 20 - 0.00 0.00 - 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 0-2' 76.00 64 - 0.00 0.00 - 29.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 0-3' 62.00 70 - 0.00 0.00 - 45.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 0-4' 52.00 75 - 0.00 0.00 - 57.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 0-5' 550.00 80 - 0.00 0.00 - 60.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 0-6' 43.00 88 - 0.00 0.00 - 64.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 0-7' 38.50 92 - 0.00 0.00 - 69.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 0-8' 34.00 94 - 0.00 0.00 - 70.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 0-9' 33.00 96 - 0.00 0.00 - 55.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10 0-10' 31.00 99 - 0.00 0.00 - 60.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 0-11' 30.00 102 - 0.00 0.00 - 65.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12 0-12' 29.00 106 - 0.00 0.00 - 70.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Page 5
SEWERAGE
DESCRIPTION OF ITEM NO 7: Constructing gully grating chamber 12"x12"(300x300mm)

a) With C.I. Gully trap frame hinged safety type.

Detail Unit Rate (British System) per Each

Qty. Rate Amount


Labour Composite Labour Composite

Excavation in ordinary soil upto 5'(1.5m)


7 5
depth 1x3'x2 /8'x2 /8'= 24.5 24.50 Cft 0.00 %0 Cft - 0.00 -
Item 7 (i) of Chapter No. 3
Cement concrete brick or stone ballast 1"
to 2" (40 to 50mm) gauge (1:6:12)
7
1x3'x2 /8'x = 2.34 Cft 2.34 Cft 0.00 % Cft 0.00 % Cft 0.00 0.00
Item 3 (d) of Chapter No. 6
Pacca brick work in foundation and plinth
in cement, sand, mortar (1:3)
3
1x2'xx2 /8' = 4.45'
3
1x2x3/8x2 /8 = 2.23'
3
2x1xx2 /8 = 3.56'
Total 10.24 Cft

Deduction
Sewer
'x'x22/7x = 0.60

Drain
1x'x'x22/7x' = 0.10
0.70 Cft

Net ( 10.24 - 0.70 ) = 9.5 9.54 Cft 0.00 % Cft 0.00 % Cft 0.00 0.00
Item No. 4(i) of Chap. 7
Cement Plaster (1:3) " thick
inside chamber 1x4x2 3/8' = 9.50
outside chamber 2x2'x' = 3.75
2x2 1/8'x' = 3.19
16.44
Top 1x2'x' 1.87
3
1x1 /8'x' 1.00
3
1x2'x /8' 1.00
20.31 Sft -0.01 % Sft -0.01 % Sft 0.00 0.00
Item No. 8(b) Chapter 11
Cement concrete plain 1:2:4 including
placing, compacting finishing and curing
complete.

1
Floor bed 1x1x /12 0.08 Cft 0.00 % Cft 0.00 % Cft 0.00 0.00
Item 5 (f) Chap. No. 6

Detail Unit Rate (British System) per Each

Qty. Rate Amount


Labour Composite Labour Composite

Supplying and fixing C.I. gully grating


12"x12" with hinged safety. Type

weighing 81 Lbs 1.00 No - 0.00 P. No - 0.00

Supplying and fixing 12"x6" iron 2.00 Nos - 0.00 P. No - 0.00

Total Rate for Each 0.00 0.00


Say 0.00 0.00

Page 7
Item No. 7 Constructing gully grating chamber 12"x12" (300x300mm)

b) Concrete Gully Trap.

Detail Unit Rate (British System) per Each

Qty. Rate Amount


Labour Composite Labour Composite

Excavation in ordinary soil upto 5'(1.5m)


7 5
depth 1x3x2 /8x2 /8 = 24.5 Cf 24.50 Cft 0.00 %0 Cft - 0.00 -
(As per item 7 (a))
Cement concrete 1:6:12 of brick or stone
7
ballast 1x3x2 /8x = 2.34 Cft 2.34 Cft 0.00 % Cft 0.00 % Cft 0.00 0.00
(As per item 7 (a))
Pacca brick work in foundation and
plinth (1:3)
3
1x2x'x2 /8 = 4.45
3 3
1x2x /8x2 /8 = 2.23
3
2x1x'x2 /8 = 3.56
10.24 Cft

Deduction as per 3 (a)


Net ( 10.24 - 0.70 ) = 9.5 9.54 Cft 0.00 % Cft 0.00 % Cft 0.00 0.00
(As per item 4(i) Chapter 7
Cement Plaster (1:3)" thick
3
inside chamber 1x4x2 /8 = 9.50
outside chamber 2x2x = 3.75
1
2x2 /8 x = 3.19
16.44
Top 1x2x 1.87
3
1x1 /8 x 1.00
3
1x2x /8 1.00
20.31 Sft -0.01 % Sft -0.01 % Sft 0.00 0.00
As per item 8(b) Chapter 11
Cement concrete plain 1:2:4 including
placing, compacting finishing and curing
complete.

1
Floor bed 1x1x /12 0.08 Cft 0.00 % Cft 0.00 % Cft 0.00 0.00
As per item No. 5 of Chapter 6

Page 8
Detail Unit Rate (British System) per Each

Qty. Rate Amount


Labour Composite Labour Composite

Supplying and fixing 12"x12"


(300x300mm) concrete gully trap. 1.00 No - 0.00 P. No - 0.00

Supplying and fixing 12"x6" (300x150mm)


iron bolt etc. 2.00 Nos - P. No - 0.00

Total Rate for Each 0.00 0.00

Say 0.00 0.00

Page 9
DESCRIPTION OF ITEM NO 8: Constructing standard gully grating chamber 3.0'x1.5'x2.5'
china ware trap as per PHED drawing
No. STD/PD No. 3 of 1977 complete in all respect.

Detail Unit Rate (British System) per Each

Qty. Rate Amount


Labour Composite Labour Composite

Excavation in foundation
1x5'x3'x3' = 53 Cft 53.00 Cft 0.00 %0 Cft - 0.00 -

Cement Concrete (1:6:12)


1
1x5'x3'x /3' = 5.83 Cft 5.83 Cft 0.00 % Cft 0.00 % Cft 0.00 0.00

Providing and laying 2" (50mm) thick CC


1:2:4 in bed of gully grating.
1
1x2.5'x1.5'x /6' = 0.62
Foundation block 1x1'x'x1.0' = 0.75
To 1.37 Cft 0.00 % Cft 0.00 % Cft 0.00 0.00

Pacca brick work (1:3) other than building


in foundation & plinth.
short wall 2x1'x'x2' = 5.62
Long wall 2x4'x'x2' = 16.88
Total 22.50 Cft

D/d opening
1x1x1x0.75 = 0.75
1x0.5x0.5x0.75 = 0.19
Total 0.94 Cft
Net 22.50 - 0.94 = 21.56 Cft 21.56 Cft 0.00 % Cft 0.00 % Cft 0.00 0.00

Item No. 4(i) Chapter 7


Cement Plaster " (12mm) thick (1:3)
1
inside chamber 2(3+1)x2 /3 = 2 21.00 Sft % Sft % Sft 0.00 0.00

Precast RCC (1:2:4) slab excluding cost


of steel.
1
Top slab 1x4x3'x /3' = 4.5 C 4.50 Cft 0.00 % Cft % Cft 0.00 0.00
(Item 6(b.1) of Chap. 6)
Fabrication of steel including cost of steel
bending, binding complete.
4.5 Cft @ 4.5 cwt/100 Cft =
0.20 cwt or 10.16 Kg 10.16 Kg 0.00 P. Kg 0.00 P. Kg 0.00 0.00
(Item 9 (b) Chap. 6)
Small iron work such as gusset plate
knees, bends, stirrups, straps rings etc.
including cutting drilling reviting
handling assembling and fixing M.S.
grating.

a.M.S. flat iron (1"x1/8")= 2x1 = 3.5'


Weight= 3.5 ft @ 0.78 Lbs/ft = 2.73 Lbs

Detail Unit Rate (British System) per Each

Qty. Rate Amount


Labour Composite Labour Composite

b." dia M.S. bars 2" centre to centre


4x1.0 = 4 ft
Weight @ 0.67 Lbs/ft = 2.68 Lbs
= 2.73 + 2.68 Lbs = 5.41 Lbs 2.46 Kg 0.00 P. Kg 0.00 P. Kg 0.00 0.00
(Item 10 of Chap. 25)
Supply and fixing China ware trap with
C.I. screen. 1.00 No - P. No - 0.00

Making hole in existing manhole chamber


wall and rectification of the same after pipe
connection.
1
/3 Mason @ Rs. P. Day 56.67
Sundries 10% = 5.67

Contractor's Profit 20%


Labour for each manhole 1.00 No 68.57 P. No P. No 0.00

Material including Contractor's Profit 9.16


Composite rate per No. 0.00

Total Rate for Each 0.00 0.00

Say 0.00 0.00

Page 10
DESCRIPTION OF ITEM NO 9: Extra for making and finishing benching floor work
in manhole chamber, with 1/8" (3mm) thick cement
finish.

Detail Unit Rate (British System) per 100 Sft


Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Cement for 1/8" thick nero


100x1/8x1/12 = 1.04 Cft= 0.83 cwt 0.83 Bag 0.00 P. Bag -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour

Mason 0.60 Nos P. Day -


Unskilled Coolies 0.60 Nos P. Day -
Bahishti 0.13 No P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate P. Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate P. Sqm Rs. Say -

Page 13
DESCRIPTION OF ITEM NO 10: Restoration of brick pavement on edge, over laid
service line, with 2" (50mm) sand cushion under
soling.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Total bricks required = 525 out of which


33% shall be replaced.
No: of new bricks required 175 Nos 175 Nos %0 Nos -
Sand 16.70 Cft %Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour

Mason 0.65 No P. Day -


Unskilled Coolies 1.25 Nos P. Day -
Bahishti 0.08 No P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate P. Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate P. Sqm Rs. Say -

Page 14
DESCRIPTION OF ITEM NO 11: Restoration of flat brick pavement sand
grouted, over 2" (50mm) thick dry sand
cushion, under soling on laid service line.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 100 Sft

Material

Total bricks required shall be 350 Nos


New brick to be supplied in replacement 33%
1.350x1/3 = 117 Nos 117 Nos %0 Nos -
2.100x1/6 = 16.7 Cft Sand 16.70 Cft %Cft -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour

Mason 0.40 No P. Day -


Unskilled Coolies 0.75 No P. Day -
Bahishti 0.05 No P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -

Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate P. Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate P. Sqm Rs. Say -

Page 15
DESCRIPTION OF ITEM NO 12: Restoration of metalled road, on laid service
line, including compaction.
a) Carpeted road, with 2" (50mm) carpet and 10"
(250mm) depth of stone metal for sub base and
base.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Assuming 67% material received from


dismantling. New material required for
sub-base/base = 100x10x.33= 27.50 Cft
12 100
Carpetting 2" (50mm) thick = 100 Sft (9.291) Sqm

Material

Sub-base/base (Item 3(i) of Chap. 18) 27.50 Cft % Cft -


Carpetting 2" (50mm) thick (Item 10 Chap. 18) 100.00 Sft %Sft -
(Item 10 Chapter 18)
Total -

Labour

Labour (Item 3(i) Chap 18) 27.50 Cft % Cft -


Carpeting (Item 10 Chapter 18) 100.00 Sft % Sft -

Total -

Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate P. Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate P. Sqm Rs. Say -

Page 16
DESCRIPTION OF ITEM NO 12: Restoration of metalled road, cut for laying
service line, including compaction.
b) Carpeted road with 1" (40mm) carpet and 6"
(150mm) depth of stone metal for sub-base and
base.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Assuming 67% material recovered from


dismantling, and 33% new material will be
needed
Total quantity required for= 100x 1 x 6 = 16.7 Cft
sub-base/bas 3 12
Carpetting 1" (40mm) thick = 100 Sft (9.291) Sqm

Material

Sub-base (Item No.3 (i) Chapter 18 16.70 Cft % Cft -


Carpeting 1" (40mm) thick 100.00 Sft % Cft -

Total -

Labour

Sub-base (Item No. 3(i) Chapter 18 16.70 Cft % Cft -


Carpeting 100.00 Sft % Sft -

Total

Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate P. Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate P. Sqm Rs. Say -

Page 17
DESCRIPTION OF ITEM NO 12: Restoration of metalled road, cut for laying
service line, including compaction.
c) Black topped road with two coats of surfacing and
10" (254mm) depth of stone metal for sub-base and
base.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Assuming 33% material will be required


to replanish in restoration.
Quantity = 10 x 10 x 1 = 27.78 Cft
12 3
Black topped road surfacing = 100 Sft -

Material

Sub-base (Item No. 3(i) of Chpater 18 27.78 Cft % Cft -


Bajri 8.25 Cft %Cft -
Bituman 65Lbs (29 .50) Kg P. Kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Item 2 & 3 on 'Rs.
Total -

Labour

Sub base/base (Item No. 3(i) Chap. 18 27.78 Cft % Cft -


100 Sft Surfacing (two coats) 100.00 Sft % Sft -
(Item 8 (1-1) & (2-1) Chap 18)
(Road and Road Structure)
Total -

Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate P. Sqm Rs. Say -

Composite Rate Per 100 Sft Rs. Say -


Composite Rate P. Sqm Rs. Say -

Page 18
DESCRIPTION OF ITEM NO 13: Providing and fixing 1"x1"x3/16"
(32x32x5mm) angle iron step, in manhole
chambers, including carriage and setting the
same in work, to correct lines and levels.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Material

Providing 1"x1"x3/16" (32x32x5mm)


angle iron step of 8"x12" (200x300mm)
5 1
outer over all dimensions 2 /16'x /12'x2' = 0.48 Sft
(0.704x0.025x0.761) = 0.013 M
0.48 Sft @ 7.65 Lbs = 3.69 Lbs or
1.68 Kg. 1.68 Kg P. Kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour

Blacksmith 0.01 No P. Day -


Unskilled Cooly 0.01 No P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -

Labour for Fixing


Fixing mild iron step including carriage
and setting the same to correct line and
levels in masonry/concrete work

Page 19
Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Mason 0.05 No Each -


Carriage from store to site L.S.

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -

Item Rates
Labour Rate for Each Rs. Say -

Composite Rate for Each Rs. Say -

Page 20
DESCRIPTION OF ITEM NO 14: Fixing manhole frame and cover in RCC slab
including carriage to site.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Carriage of Manhole
Frame and cover average weight of
each set = 127 Kg.
cart load up to 4 miles (6.44 Km)
@ Rs. per cart load.

Total -

Labour

Setting the frame to correct and level on


the reinforcement of man hole chamber
top/Rcc slab/ caping.

Unskilled Coolies 0.12 No P. Day -


Mason 0.12 No P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -

Item Rates
Labour Rate Per Set Rs. Say -

Page 21
DESCRIPTION OF ITEM NO 15: Providing and fixing, 3" (75mm) thick RCC
manhole cover, 22" (557mm) dia with tee
shaped C.I. frame of 20" (505mm) clear i/d
(frame weighting 37.324 Kg. or one maund)
as per standard drawing STD/ PD No. 5 of
1977, complete in all respects.

Detail Unit Rate (British System) per Set

Qty Rate
Per Unit (Rs) Amount (Rs)

RCC Cover
1.M.S. flat iron ring 3"x" (75x6mm) =
1 x 22 x 22 x = 1.44 Sft
7 12
1.44 Sft weight @ 10.21 Lbs = 14.70 Lbs (6.67) Kg
2.M.S. round bars " dia
Straight bars 4 x 22 = 7.33 ft
12
Straight bars 4 x 1.75 = 7.00 ft
14.33 Rft
Weight of bars @ 0.667 Lbs/Rft
(0.992 Kg/Rft) = 9.60 Lbs (4.36) Kg
Total 1+2 = 6.67+4.36 = 11.03 Kg

Material

Steel required 11.03 Kg P. Kg -


C.I. frame 1Md (37 .324)Kg P. Kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Precast or cast in situ. RCC (1:2:4)


1 x 22 x 22 x x 3+4+3 x 1 = 0.73 Cft 0.73 Cft P. Cft -
7 12 3 12
(Item 10 Chapter No. 6) -

Page 22
Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Labour

Welding of flat iron 1.00 No Each -


Welding ends of M.S. round bars with
ring. 16.00 Nos Each -
Fixing manhole frame & cover including
carriage to site L. S. -
Labour for Precast Concrete 0.73 Cft P. Cft -
(Item 5 (f) Chapter No. 6)

Total -
Contractor's Profit & Ove 20.00 Percent on R - -
Total -

Item Rates
Labour Rate Per Set Rs. Say -

Composite Rate Per Set Rs. Say -

Page 23
DESCRIPTION OF ITEM NO .16 Providing and fixing, 6" (150mm) thick RCC
manhole cover 22" as per standard drawing STD/ PD
No. 6 of 1977, complete in all respects.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

RCC Cover
a.2"x2"x" size angle iron rings =
1 x 22 x 26 = 6.81 Rft
7 12
Weight @ 4.04 Lbs/ft = 27.51 Lbs (12.430) Kg
b.M.S. round bars " dia
Straight bras 1 x 26 = 26 inches
2 x 24 = 48
2 x 18 = 36
bent up bars 1 x 28 = 28
2 x 26 = 52
2 x 20 = 40
230 Inchs or 19.17 ft 19.17 ft
Bars in upper distribution ring 1x22/7x1.5 = 4.71
Bar in lower distribution ring 1x22/7x1.25 = 3.93
in overlaps distribution ring 2x = 1.00
28.81 ft @ 0.667 Lbs/Rft = 19.22 Lbs 28.81 Ft
a + b = 27.51 + 19.22 = 46.73 Lbs or 21.20
21.20 Kg

Tee Shaped C.I. Frame 37.324 37.324

Material

Steel 58.524 Kg P. Kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Page 24
Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)
-
RCC (1:2:4) in situ or precast
1 x 22 x 26 x 26 x x 6+5+5 x 1 = 1.74 Cft
7 12 12 3 12

D/d for traingular portion.


1
2xx /6x = 0.04 Cft
Rectangular portion
5
2xx /24 = 0.10 Cft 0.14 Cft
0.14 Cft 1.60 Cft P. Cft -
(Item 5 (f) Chapter No. 6) Total -

Labour

1. Welding ends of engle iron rings. 1.00 No Each -


2. Welding ends of M.S. bar to angle iron. 20.00 No Each -
3. Fixing manhole cover and frame
including carriage to site complete in all
respect. L. S. -
4. Labour for RCC 1:2:4 concrete 1.74 Cft P. Cft -
(Item 5 (f) Chapter No. 6)
Total -
Contractor's Profit & Ove 20.00 Percent on Rs. Item 1&2 -
Total -

Item Rates
Labour Rate Per Set Rs. Say -

Composite Rate Per Set Rs. Say -

Page 25
DESCRIPTION OF ITEM NO 17: Providing and fixing, 6" (150mm) thick RCC
manhole cover with 3"x3"x" (75x75x6mm)
angle iron frame, 22" i/d (557mm) as per standard
drawing STD/ PD No. 7 of 1977, complete in all
respects.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Steel :
L. iron for frame 3"x3"x"
1x 22 x 27 = 7.07 ft @ 4.89 Lbs/Rft = 34.57 Lbs
7 12
L. iron for cover 2"x2"x"
1x 22 x 26 = 6.81 ft @ 4.04 Lbs/Rft = 27.51 Lbs
7 12
62.08 Lbs
M.S. round straight bars
1 x 26 = 26 inchs
2 x 24 = 48
2 x 18 = 36
1 x 28 = 28
2 x 26 = 52
2 x 20 = 40
230 Inchs or 19.17 ft 19.17 ft
Bars in upper distribution ring 1x22/7x1.5 4.71 ft
Bar in lower distribution ring 1x22/7x1.25 3.93 ft
Bar in overlaps distribution ring 2x 1.00 ft
Bar in holdfast of frame 4x0.75 3.00 ft
weight @ 0.667Lbs/ft x31.81 = 21.22 lbs 31.81 Ft
= 62.08 + 21.22 = 83.30 Lbs or
37.80 Kg

Material

Steel 37.80 Kg P. Kg -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Page 26
Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

RCC (1:2:4) in situ or precast laid in -


position complete in all respect.
1 x 22 x 26 x 26 x x 6+5+5 x 1 = 1.74 Cft
7 12 12 3 12

D/d for traingular portion.


1
2xx /6x = 0.04
Rectangular portion
5
2xx /24 = 0.10 - 0.14 Cft
0.14 1.60 Cft P. Cft -
(Item 5 (f) Chapter No. 6) Total -

Labour

1.i. Welding ends of engle iron rings for


frame 3"x3"x" 1.00 No Each -
ii. For cover 2"x2"x" 1.00 No Each -
iii. Ends of MS bars to angle iron ring in
RCC cover 20 Nos
iv. End of M.S. holdfast to the ring of the
frame. 4 N 24.00 Nos Each -
2. Fixing manhole frame and cover
including carriage from store complete
in all respects. L.S. -
3. Labour for RCC 1:2:4 concrete 1.60 Cft P. Cft -
(Item 5 (f) Chapter No. 6)
Total -
Contractor's Profit & Ove 20.00 Percent on Item 1 -
Total -

Item Rates
Labour Rate Per Set Rs. Say -

Composite Rate Per Set Rs. Say -

Page 27
DESCRIPTION OF ITEM NO 18: Desilting of disposal work collecting tank including
removal of sludge with in 3 chains (90M).

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)
Analysis Rate for 2100 Cft

T & P Required :

R.S. joist 6"x12" size 25'-0" 1.00 No


Winch crab with steel rope and v-clamps. 1.00 No
M.S. bucket 2'x2'x2' 1.00 No
Tripod of G.I. pipe 3" (75mm) i/d 1.00 No
Chain pully block of one ton capacity 1.00 No
Wooden plank 10"x10"x1"

Cross planks 20 x 12 = 24 Nos


10
Longitudnal = 6 Nos
30 Nos

Rental charges of equipments :


Taking average size of C. Tank 30.00 ft
Depth of silt. 3.00 ft
Quantity = 22 x 30' x 30' x x 3 2121.50 Cft (S2100 Cft)
7
Time for fitting equipment and removing. 0.50 Day
Time for clearing silt. 2.00 Days
Rental charges of all equipments including
carriage, fixing & removing. 2.50 Days P. Day -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Page 28
Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Labour

Coolies Unskilled
For digging 2.00 Nos
For Lifting & removing 8.00 Nos
For carrying 2.00 Nos
12.00 Nos
Unskilled Cooly for 2 days 24.00 Nos Each -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -

Item Rates
Labour Rate Per 100 Cft Rs. Say -
Labour Rate Per Cum Rs. Say -

Composite Rate Per 100 Cft Rs. Say -


Composite Rate Per Cum Rs. Say -

Page 29
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
a) i) 6" (150mm) dia 18' long.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 16 Cwt

Material
C.I. vantilating shaft 18' long weighing
16 cwt = 21.78 md. (813 Kg) including
column pipe, base, cowl, plates, and other
accessories including carriage to site. 813.00 Kg P. Kg -
Foundation bolts & nuts " dia 1' long 4.00 Nos No -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour

Pipe fitter 1.00 No P. Day -


Unskilled Cooly 4.00 Nos P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -
Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -

Composite Rate Per Cwt Rs. Say -


Composite Rate Per 100 Kg Rs. Say -

Page 30
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
a) ii) 6" (150mm) i/d shaft 24' (7.232Rm) long.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 18 Cwt

Material
C.I. vantilating shaft 24' long weighing
18 cwt = 24.50 md. (915 Kg) including
column pipe, base, cowl, and other plates
and accessories including carriage to site. 915.00 Kg P. Kg -
Foundation bolts & nuts " dia 2' long . 4.00 Nos No -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour

Pipe fitter for 1 day = 1 No 1.25 Nos P. Day -


Unskilled Cooly for 1 day = 4 Nos 5.00 Nos P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -
Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -

Composite Rate Per Cwt Rs. Say -


Composite Rate Per 100 Kg Rs. Say -

Page 31
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
a) iii) 6" (150mm) i/d shaft 30' (9.143Rm) long.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 20 Cwt

Material
C.I. vantilating shaft 30' including column pipe,
base, cowl and other accessories including
carriage to site weighing 20 cwt or 1016 kg 1016.00 Kg P. Kg -
Foundation bolts & nuts " dia 2' long . 4.00 Nos No -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour

Pipe fitter 1 No for 1.5 days 1.50 Nos P. Day -


Unskilled Cooly 4 No for 1.5 days 6.00 Nos P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -
Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -

Composite Rate Per Cwt Rs. Say -


Composite Rate Per 100 Kg Rs. Say -

Page 32
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
a) iv) 6" (150mm) i/d vantilating shaft 36' (11 M) long

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 22.3 Cwt

Material
C.I. vantilating shaft 36' long including
column pipe base, cowl, other plates,
accessories & carriage to site 22.3 Cwt
(1133.21 kg). 1133.21 Kg P. Kg -
Foundation bolts & nuts " dia 2' long . 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour

Pipe fitter 1 No for 1 days 1.75 Nos P. Day -


Unskilled Cooly 4 No for 1 days 7.00 Nos P. Day -

Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -

Composite Rate Per Cwt Rs. Say -


Composite Rate Per 100 Kg Rs. Say -

Page 33
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
b) i) 9" (225mm) i/d : shaft 18' (5.48M) long.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 25 Cwt

Material
C.I. vantilating shaft 18' long including
column pipe base, cowl, plates and other
accessories including carriage to site 25 Cwt
(1270.42 kg). 1270.42 Kg P. Kg -
Foundation bolts & nuts " dia 2' long . 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour

Pipe fitter 1.00 Nos P. Day -


Unskilled Cooly 6.00 Nos P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -
Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -

Composite Rate Per Cwt Rs. Say -


Composite Rate Per 100 Kg Rs. Say -

Page 34
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
b) ii) 9" (225mm) i/d : shaft 24' (7M) long.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 29 Cwt

Material
C.I. vantilating shaft 24' long including
base, column pipe, cowl, plates, other
accessories & carriage to site 29 Cwt or
39.47 Mds: cast iron pipe. (1473.68 kg). 1473.68 Kg P. Kg -
Foundation bolts & nuts " dia 2' long . 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour

Pipe fitter 1 No for 1 day 1.25 Nos P. Day -


Unskilled Cooly 6 Nos for 1 day 7.50 Nos P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -

Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -
Composite Rate Per Cwt Rs. Say -
Composite Rate Per 100 Kg Rs. Say -

Page 35
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
b) iii) 9" (225mm) i/d : shaft 30' (9M) long.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 32.5 Cwt

Material
C.I. vantilating shaft 30' long including base,
column pipe, cowl, plates, other accessories &
carriage to site 32.5cwt or 44.24md (1651.54) 1651.54 Kg P. Kg -
Foundation bolts " dia 2' long. 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour

Pipe fitter 1 No for 1 day 1.50 Nos P. Day -


Unskilled Cooly 6 Nos for 1 day 9.00 Nos P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -

Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -
Composite Rate Per Cwt Rs. Say -
Composite Rate Per 100 Kg Rs. Say -

Page 36
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
b) iv) 9" (225mm) i/d : shaft 36' (11M) long.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 36 Cwt

Material
C.I. vantilating shaft 36' long including
base, column pipe, cowl, plates, bolts and
other accessories 36 Cwt or 1829.40 kg. 1829.40 Kg P. Kg -
Foundation bolts " dia 2' long. 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour

Pipe fitter 1 No for 2 day 2.00 Nos P. Day -


Unskilled Cooly 6 Nos for 2 day 12.00 Nos P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -

Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -
Composite Rate Per Cwt Rs. Say -
Composite Rate Per 100 Kg Rs. Say -

Page 37
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
c) i) 12" (300mm) i/d : shaft 18' (5.45M) long.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 36 Cwt

Material
C.I. vantilating shaft including base column
pipe, cowl, plates, bolts, and other
accessories etc. 36 Cwt or 1829.40 kg. 1829.40 Kg P. Kg -
Foundation bolts 7/8" dia 2' long. 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour

Pipe fitter for 1 day 1.00 Nos P. Day -


Unskilled Cooly for 1 day 8.00 Nos P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -

Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -

Composite Rate Per Cwt Rs. Say -


Composite Rate Per 100 Kg Rs. Say -

Page 38
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
c) ii) 12" (300mm) i/d : shaft 24' (7M) long.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 42 Cwt

Material
C.I. vantilating shaft including base column
pipe, cowl, plates, bolts, and other
accessories etc. 42 Cwt or 2134 kg. 2134.00 Kg P. Kg -
Foundation bolts 7/8" dia 2' long. 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour

Pipe fitter 1 No for 1 day 1.50 Nos P. Day -


Unskilled Cooly 8 Nos for 1 day 12.00 Nos P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -

Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -

Composite Rate Per Cwt Rs. Say -


Composite Rate Per 100 Kg Rs. Say -

Page 39
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
c) iii) 12" (300mm) i/d : shaft 30' (9M) long.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 48 Cwt

Material
C.I. vantilating shaft 30' long including base,
cowl, column pipe, plates. studs and other
accessories etc. 48 Cwt or 65.33 Md. = 2439.00 Kg P. Kg -
Foundation bolts 7/8" dia 3' long. 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Hire charges of T & P L. S. -

Total -
Contractor's Profit & Ove 20.00 Percent -
Total -

Labour

Pipe fitter 1 No for 2 day 2.00 Nos P. Day -


Unskilled Cooly 8 Nos for 2 day 16.00 Nos P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -

Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -

Composite Rate Per Cwt Rs. Say -


Composite Rate Per 100 Kg Rs. Say -

Page 40
DESCRIPTION OF ITEM NO 20: Silt clearing 10' (3M) dia wells and removal of
slush out side the compound.
a) Upto 10' (3M) depth of slush.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Labour

Drivers 3.00 Nos P. Day -


Unskilled Cooly 5.50 Nos P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -

Item Rates

Labour Rate Per Well Rs. Say -

Page 41
DESCRIPTION OF ITEM NO 20: Silt clearing 10' (3M) dia wells and removal of
slush out side the compound.
b) Beyond 10' (3M) depth of slush.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs) Amount (Rs)

Labour

Driver 5.00 Nos P. Day -


Unskilled Cooly 12.00 Nos P. Day -

Total -
Sundries 10.00 Percent -
Total -

Contractor's Profit & Ove 20.00 Percent -


Total -

Item Rates

Labour Rate Per Well Rs. Say -

Page 42

You might also like