Professional Documents
Culture Documents
BRICK WORK
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft Rs. Say
Labour rate per Cum Rs. Say
Page 1
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 2
DESCRIPTION OF ITEM:
Item No. 2 Add extra labour in item No.1 for brick work in
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft
Say
Labour rate per Cum
Say
LABOUR for 125 Cft
Second Floor
Page 3
Detail Unit Rate (British System) per 100 Cft
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft
Say
Labour rate per Cum
Say
LABOUR for 125 Cft
4th & Subsequent Floor
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 4
DESCRIPTION OF ITEM:
Item No. 3 Pucca brick work in mud mortar other than building.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 5
DESCRIPTION OF ITEM:
Item No. 3 Pucca brick work in mud morter other than building:
(ii) Extra labour for every 5.0' (1.5 metre) additional height
thereof.
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 6
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 7
DESCRIPTION OF ITEM:
Item No. 4 (i) Pucca brick work in foundation & plinth in:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 8
DESCRIPTION OF ITEM:
Item No. 4 (i) Pucca brick work in foundation & plinth in:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 9
DESCRIPTION OF ITEM:
Item No. 4 (i) Pucca brick work in foundation & plinth in:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 10
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 11
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 12
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 13
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 14
DESCRIPTION OF ITEM:
Item No. 4 (ii) Pucca brick work in foundation & plinth in:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 15
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 16
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 17
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 18
DESCRIPTION OF ITEM:
MATERIAL
1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.
2 Lime Slaked 174.30 Kg. Per Kg.
3 Sand 23.33 Cft % Cft
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft Rs. Say
Labour rate per Cum Rs. Say
Page 19
DESCRIPTION OF ITEM:
Item No. 5 (i) Pacca brick work in ground floor (including striking of jo
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 20
DESCRIPTION OF ITEM:
Item No. 5 (i) Pacca brick work in ground floor (including striking of jo
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 21
DESCRIPTION OF ITEM:
Item No. 5 (i) Pacca brick work in ground floor (including striking of jo
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 22
DESCRIPTION OF ITEM:
Item No. 5 (i) Pacca brick work in ground floor (including striking of jo
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 23
DESCRIPTION OF ITEM:
Item No. 5 (i) Pacca brick work in ground floor (including striking of jo
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 24
DESCRIPTION OF ITEM:
Item No. 5 (i) Pacca brick work in ground floor (including striking of jo
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 25
DESCRIPTION OF ITEM:
Item No. 5 (i) Pacca brick work in ground floor (including striking of jo
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 26
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 27
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 28
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 29
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 30
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 31
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 32
DESCRIPTION OF ITEM:
Item No. 6 Add extra labour in item No.5 for brick work in:-
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft Rs.
Say
Labour rate per Cum Rs.
Say
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft Rs.
Say
Labour rate per Cum Rs.
Say
Page 33
Detail Unit Rate (British System) per 100 Cft
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft
Say
Labour rate per Cum
Say
LABOUR for 125 Cft
4th & Subsequent Floor
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 34
DESCRIPTION OF ITEM:
Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 35
Item No. 7 Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 36
DESCRIPTION OF ITEM:
Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 37
DESCRIPTION OF ITEM:
Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 38
DESCRIPTION OF ITEM:
Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 39
DESCRIPTION OF ITEM:
Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 40
DESCRIPTION OF ITEM:
Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 41
DESCRIPTION OF ITEM:
Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 42
DESCRIPTION OF ITEM:
Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 43
DESCRIPTION OF ITEM:
Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 44
DESCRIPTION OF ITEM:
Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 45
DESCRIPTION OF ITEM:
Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 46
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 47
DESCRIPTION OF ITEM:
Item No. 8 Additional extra labour in item No.7 for every 10 ft. (3 m
additional height.
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 48
DESCRIPTION OF ITEM:
Item No. 9 Extra labour for arch work in brick masonry including labo
centering and de-centering.
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 49
DESCRIPTION OF ITEM:
Item No. 10 Extra for Pacca brick work in steining of wells or any oth
circular masonry.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 50
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 51
DESCRIPTION OF ITEM:
Item No. 12 Extra labour for Pacca brick work in piers and abutment.
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 52
DESCRIPTION OF ITEM:
Item No. 12 Extra labour for Pacca brick work in piers and abutment.
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 53
DESCRIPTION OF ITEM:
Item No. 13 Extra for face work (half brick thick) using special brick
of Ist class bricks.
MATERIAL
Total 783.00
Add 5% wastage 39.15
Total 822.15
Page 54
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 55
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 56
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 57
DESCRIPTION OF ITEM:
Item No. 16 Peforated Pacca brick walling 114 mm (4") thick in ground
floor in
(i) Mud mortar.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 58
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 59
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 60
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 61
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 62
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 63
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 64
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 65
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 66
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 67
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 68
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 69
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 70
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 71
DESCRIPTION OF ITEM:
Item No. 17 Add. extra labour on item No.15 for pacca brick work.
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate for 100 Sft Rs.
Say
Labour rate per Sqm Rs.
Say
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate for 100 Sft Rs.
Say
Labour rate per Sqm Rs.
Say
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate for 100 Sft
Say
Labour rate per Sqm
Say
Page 72
LABOUR for 125 Sft
4th & Subsequent Floor
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 73
DESCRIPTION OF ITEM:
Item No. 18 (i) Perforated pacca brick walling 9" thick in ground floor in
Mud Mortar
MUD MORTAR
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 74
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 75
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 76
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 77
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 78
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 79
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 80
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 81
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 82
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 83
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 84
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 85
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 86
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 87
DESCRIPTION OF ITEM:
Item No. 19 Extra labour in item No.18 for per perforated pacca brick
work in
LABOUR
First Floor
Page 88
DESCRIPTION OF ITEM:
Total
Contractor's Profit & Ov 20 Percent
Total
for mortar
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 89
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 90
DESCRIPTION OF ITEM:
Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with (1") 25 mm wide 18 gauge hoop iron.
(i) 4" (114 mm) thick walling with hoop iron bouding 6"
(150 mm) apart.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 91
DESCRIPTION OF ITEM:
Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with 1" (25 mm) wide 18 gauge hoop iron.
(ii) 4" (114 mm) thick walling with hoop iron bouding
12" (300 mm) apart.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 92
DESCRIPTION OF ITEM:
Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with 1" (25 mm) wide 18 gauge hoop iron.
(iii) 3" (75 mm) thick walling with hoop iron bouding 6"
(150 mm) apart.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 93
DESCRIPTION OF ITEM:
Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with 1" (25 mm) wide 18 gauge hoop iron.
(iv) 3" (75 mm) thick walling with hoop iron bouding 12"
(300 mm) apart.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 94
DESCRIPTION OF ITEM:
MATERIAL
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 95
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 96
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 97
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 98
DESCRIPTION OF ITEM:
Item No. 26 Providing Eave brick moulded weathered and throated with b
brick or drip course cornice in (1 : 3) cement mortar.
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 99
DESCRIPTION OF ITEM:
Item No. 26 Providing Eave brick moulded weathered and throated with b
brick or drip cornice in (1 : 3) cement mortars.
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 100
DESCRIPTION OF ITEM:
Item No. 26 Providing Eave brick moulded weathered and throated with b
brick or drip cornice in (1 : 3) cement mortar.
(iii) 4" (114 mm) thick eave brick with back brick.
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 101
DESCRIPTION OF ITEM:
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 102
DESCRIPTION OF ITEM:
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 103
DESCRIPTION OF ITEM:
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 104
DESCRIPTION OF ITEM:
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 105
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 106
DESCRIPTION OF ITEM:
Item No. 30 Supplying and filling sand under floors or plugging in wel
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 107
DESCRIPTION OF ITEM:
Item No. 31 Providing and laying 2" (50 mm) thick projected tile bank
(1: 2) cement sand mortar with hoop iron 1" (25 mm) wide 1
SWG flat iron sheet 9" (225 mm) apart.
Total
Contractor's Profit & Ov 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 108
DESCRIPTION OF ITEM:
Item No. 32 Ist class brick tiles (9" 4" x 1") 225 x 114 x 40 mm cla
76 mm thick laid in cement sand mortar recifered with hoop
strips placed at 2 ft. (600 mm) apart vertically.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 109
DESCRIPTION OF ITEM:
Item No. 32 Ist class brick tiles (9" 4" x 1") 225 x 114 x 40 mm cla
76 mm thick laid in cement sand mortar recifered with hoop
strips placed at 2 ft. (600 mm) apart vertically.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 110
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
Page 111
DESCRIPTION OF ITEM:
Assume 60 Bricks
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 112
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 113
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
Page 114
CHAPTER NO. 11
SURFACE RENDERING
DESCRIPTION OF ITEM:
Item No. 1 Mud plaster on walls (excluding Gobri leeping) upto 20' (6.10 metre) height.
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 1
DESCRIPTION OF ITEM:
Item No. 1 Mud plaster on walls (excluding Gobiry leaping) upto 20' height
(6.10 metre).
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 2
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 3
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 4
DESCRIPTION OF ITEM:
Item No. 3 Cement lime plaster 1 : 7 : 12 (cemnt lime and sand) up to 20 ft.
(6.10 metre) height.
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 5
DESCRIPTION OF ITEM:
Item No. 3 Cement lime plaster 1 : 7 : 12 (cemnt lime and sand) up to 20 ft.
(6.10 metre) height.
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 6
DESCRIPTION OF ITEM:
Item No. 4 Cement neru plaster 1 : 2 (cement and sand) upto 20 ft. (6.10 metre).
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 7
DESCRIPTION OF ITEM:
Item No. 4 Cement neru plaster 1 : 2 (cement and sand) upto 20 ft. (6.10 metre).
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 8
DESCRIPTION OF ITEM:
Item No. 5 Stucco cement plaster 2" (50 mm) thick 1 : 2 : 4 (cement sand and shingle,
upto 20 ft (6.0 m) height.
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 9
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying machine sprayed plaster " (12 mm) thick, using
cement and chips zero gauge over the existing plastered and roughened
surface, upto 20 ft height (6 metre).
(i) Ratio 1 : 1.
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 10
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying machine sprayed plaster "12 mm thick, using cement
and chips zero gauge over the existing plastered and roughened surface,
upto 20 ft height.
(ii) Ratio 1 : 1.
MATERIAL
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 11
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying machine sprayed plaster "12 mm thick, using cement
and chips zero gauge over the existing plastered and roughened surface,
upto 20 ft height.
(iii) Ratio 1 : 2.
MATERIAL
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 12
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 13
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 14
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 15
DESCRIPTION OF ITEM:
Item No. 8 Cement plaster (1 : 3) cement and sand upto 20 ft height (6.10 metre).
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 16
DESCRIPTION OF ITEM:
Item No. 8 Cement plaster (1 : 3) cement and sand upto 20 ft height (6.10 metre).
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 17
DESCRIPTION OF ITEM:
Item No. 8 Cement plaster (1 : 3) cement and sand upto 20 ft height (6.10 metre).
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 18
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 19
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 20
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 21
DESCRIPTION OF ITEM:
Item No. 10 Cement plaster 3/8" (10 mm) thick under soffit of R.C.C. roof slab only, upto
20 ft. (6.10 meter) height.
(a) Ratio ( 1 : 2 ).
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 22
DESCRIPTION OF ITEM:
Item No. 10 Cement plaster 3/8" (10 mm) thick under soffit of R.C.C. roof slab only, upto
20 ft. (6.10 meter) height.
(b) Ratio ( 1 : 3 ).
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 23
DESCRIPTION OF ITEM:
Item No. 10 Cement plaster 3/8" (10 mm) thick under soffit of R.C.C. roof slab only, upto
20 ft. (6.10 meter) height.
(c) Ratio ( 1 : 4 ).
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 24
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 25
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 26
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 27
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 28
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 29
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 30
DESCRIPTION OF ITEM:
Item No. 13 Applying floating coat of cement 1/32" (0.75 mm) thick.
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 31
DESCRIPTION OF ITEM:
Item No. 14 Lime pointing flush upto 20 ft (6.10 mm) height including raking joints.
Ratio (1 : 2) lime sand mortar.
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 32
DESCRIPTION OF ITEM:
Item No. 15 Lime pointing struck joints on walls, upto 20 ft. (6.10 metre) height
including raking joints Ratio (1 : 2) lime sand mortar.
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 33
DESCRIPTION OF ITEM:
Item No. 16 Cement pointing Flush upto 20 ft. (6.10 metre) height.
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 34
DESCRIPTION OF ITEM:
Item No. 16 Cement pointing Flush upto 20 ft. (6.10 metre) height.
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 35
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 36
DESCRIPTION OF ITEM:
Item No. 18 Cement pointing struck joints on walls upto 20 ft. (6.10 metre) height.
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 37
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 38
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 39
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 40
DESCRIPTION OF ITEM:
MATERIAL
0.54 bag
1 Slaked lime 18.66 kg 0.00 kg -
2 Sand 2.00 Cft 0.00 Cft -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 41
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 42
DESCRIPTION OF ITEM:
Item No. 20 Raking and washing joints of stone masonry (old work).
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say -
Labour rate per Sqm Rs. 0.00 Say -
DESCRIPTION OF ITEM:
Item No. 21 Raking and washing joints of brick masonary (old work).
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say -
Labour rate per Sqm Rs. 0.00 Say -
Page 43
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 44
DESCRIPTION OF ITEM:
MATERIAL
0.15 gln
1 Distemper 1.50 lbs 0.00 per gln -
2 Burshes (Large) 0.04 No. 0.00 Each -
3 Sand Paper 0.014 No. 0.00 Doz -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 45
DESCRIPTION OF ITEM:
MATERIAL
0.20 gln
1 Distemper 2.00 lbs 0.00 per gln -
2 Burshes (Large) 0.04 No. 0.00 Each -
3 Sand Paper 0.014 No. 0.00 Doz -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 46
DESCRIPTION OF ITEM:
MATERIAL
0.25 gln
1 Distemper 2.50 lbs 0.00 per gln -
2 Burshes (Large) 0.04 No. 0.00 Each -
3 Sand Paper 0.014 No. 0.00 Doz -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 47
DESCRIPTION OF ITEM:
MATERIAL
0.10 gln
1 Distemper 1.00 lbs 0.00 per gln -
2 Burshes (Large) 0.04 No. 0.00 Each -
3 Sand Paper 0.014 No. 0.00 Doz -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 48
DESCRIPTION OF ITEM:
MATERIAL
0.10 gln
1 Distemper 1.00 lbs 0.00 per gln -
2 Burshes (Large) 0.04 No. 0.00 Each -
3 Sand Paper 0.014 No. 0.00 Doz -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 49
DESCRIPTION OF ITEM:
MATERIAL
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 50
DESCRIPTION OF ITEM:
MATERIAL
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 51
DESCRIPTION OF ITEM:
MATERIAL
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 52
DESCRIPTION OF ITEM:
MATERIAL
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 53
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 54
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 55
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 56
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 57
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 58
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 59
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 60
DESCRIPTION OF ITEM:
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say -
Labour rate per Sqm Rs. 0.00 Say -
DESCRIPTION OF ITEM:
Item No. 28 Extra for lime Mud or cement plaster and pointing from 20' and above (for
each Addl: 10' height).
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say -
Labour rate per Sqm Rs. 0.00 Say -
Page 61
DESCRIPTION OF ITEM:
Item No. 29 Caulking joint of sleeper wall with sand and coaltar.
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 62
DESCRIPTION OF ITEM:
Item No. 30 Caulking joint of sleepers with mud and chopped straw.
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 63
DESCRIPTION OF ITEM:
Item No. 31 Extra cost of labour and material for red oxide pigment in cement pointing
to match with the colour of bricks.
MATERIAL
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 64
DESCRIPTION OF ITEM:
Item No. 32 (i) Providing grooved cement plaster 3/8" (10 mm) thick ratio (1 : 3) over
existing plastered and rough surface upto 20' height.
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 65
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 66
DESCRIPTION OF ITEM:
Item No. 33 Providing & fitting expanded metal edge bead for corner's with nail on
both sides of edges.
MATERIAL
1 Edge bead (5" wide mesh 3/8" x " 1.00 Rft. 0.00 Per Rft. -
2" wide on each side of siled
strip 1" wide T 1 No.11)
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total rate for 84 Rft -
ITEM RATES
Page 67
DESCRIPTION OF ITEM:
(i) Single
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total (0.01)
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 68
DESCRIPTION OF ITEM:
(ii) Double
MATERIAL
LABOUR
As per item 34 ( - x 2 -
ITEM RATES
Page 69
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 70
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 71
DESCRIPTION OF ITEM:
MATERIAL
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATES
Page 72
DESCRIPTION OF ITEM:
Item No. 38 Extra labour for white washing colour washing, priming coat and
distempering etc from 20 ft. (6 metre) height and above, requiring
scaffolding for every additional 10 ft. (3 metre) height, or part thereof.
Detail Unit Rate (British System) per 100 Sft (per coat)
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total
ITEM RATES
Page 73
CHAPTER NO. 7
BRICK WORK
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft Rs. Say
Labour rate per Cum Rs. Say
Page 1
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 2
DESCRIPTION OF ITEM:
Item No. 2 Add extra labour in item No.1 for brick work in
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft
Say
Labour rate per Cum
Say
LABOUR for 125 Cft
Second Floor
Page 3
Detail Unit Rate (British System) per 100 Cft
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft
Say
Labour rate per Cum
Say
LABOUR for 125 Cft
4th & Subsequent Floor
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 4
DESCRIPTION OF ITEM:
Item No. 3 Pucca brick work in mud mortar other than building.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 5
DESCRIPTION OF ITEM:
Item No. 3 Pucca brick work in mud morter other than building:
(ii) Extra labour for every 5.0' (1.5 metre) additional height
thereof.
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 6
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 7
DESCRIPTION OF ITEM:
Item No. 4 (i) Pucca brick work in foundation & plinth in:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 8
DESCRIPTION OF ITEM:
Item No. 4 (i) Pucca brick work in foundation & plinth in:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 9
DESCRIPTION OF ITEM:
Item No. 4 (i) Pucca brick work in foundation & plinth in:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 10
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 11
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 12
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 13
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 14
DESCRIPTION OF ITEM:
Item No. 4 (ii) Pucca brick work in foundation & plinth in:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 15
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 16
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 17
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 18
DESCRIPTION OF ITEM:
MATERIAL
1 Pacca brick 9" x 4" x 3" 1350.00 Nos. Nos.
2 Lime Slaked 174.30 Kg. Per Kg.
3 Sand 23.33 Cft % Cft
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft Rs. Say
Labour rate per Cum Rs. Say
Page 19
DESCRIPTION OF ITEM:
Item No. 5 (i) Pacca brick work in ground floor (including striking of jo
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 20
DESCRIPTION OF ITEM:
Item No. 5 (i) Pacca brick work in ground floor (including striking of jo
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 21
DESCRIPTION OF ITEM:
Item No. 5 (i) Pacca brick work in ground floor (including striking of jo
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 22
DESCRIPTION OF ITEM:
Item No. 5 (i) Pacca brick work in ground floor (including striking of jo
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 23
DESCRIPTION OF ITEM:
Item No. 5 (i) Pacca brick work in ground floor (including striking of jo
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 24
DESCRIPTION OF ITEM:
Item No. 5 (i) Pacca brick work in ground floor (including striking of jo
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 25
DESCRIPTION OF ITEM:
Item No. 5 (i) Pacca brick work in ground floor (including striking of jo
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 26
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 27
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 28
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 29
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 30
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 31
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 32
DESCRIPTION OF ITEM:
Item No. 6 Add extra labour in item No.5 for brick work in:-
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft Rs.
Say
Labour rate per Cum Rs.
Say
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft Rs.
Say
Labour rate per Cum Rs.
Say
Page 33
Detail Unit Rate (British System) per 100 Cft
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft
Say
Labour rate per Cum
Say
LABOUR for 125 Cft
4th & Subsequent Floor
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 34
DESCRIPTION OF ITEM:
Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 35
Item No. 7 Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 36
DESCRIPTION OF ITEM:
Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 37
DESCRIPTION OF ITEM:
Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 38
DESCRIPTION OF ITEM:
Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 39
DESCRIPTION OF ITEM:
Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 40
DESCRIPTION OF ITEM:
Item No. 7 (i) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 41
DESCRIPTION OF ITEM:
Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 42
DESCRIPTION OF ITEM:
Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 43
DESCRIPTION OF ITEM:
Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 44
DESCRIPTION OF ITEM:
Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 45
DESCRIPTION OF ITEM:
Item No. 7 (ii) Pacca brick work other than building including striking of
upto 10 ft. (3 metre) height.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 46
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 47
DESCRIPTION OF ITEM:
Item No. 8 Additional extra labour in item No.7 for every 10 ft. (3 m
additional height.
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 48
DESCRIPTION OF ITEM:
Item No. 9 Extra labour for arch work in brick masonry including labo
centering and de-centering.
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 49
DESCRIPTION OF ITEM:
Item No. 10 Extra for Pacca brick work in steining of wells or any oth
circular masonry.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 50
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 51
DESCRIPTION OF ITEM:
Item No. 12 Extra labour for Pacca brick work in piers and abutment.
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 52
DESCRIPTION OF ITEM:
Item No. 12 Extra labour for Pacca brick work in piers and abutment.
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 53
DESCRIPTION OF ITEM:
Item No. 13 Extra for face work (half brick thick) using special brick
of Ist class bricks.
MATERIAL
Total 783.00
Add 5% wastage 39.15
Total 822.15
Page 54
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 55
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 56
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 57
DESCRIPTION OF ITEM:
Item No. 16 Peforated Pacca brick walling 114 mm (4") thick in ground
floor in
(i) Mud mortar.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 58
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 59
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 60
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 61
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 62
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 63
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 64
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 65
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 66
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 67
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 68
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 69
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 70
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 71
DESCRIPTION OF ITEM:
Item No. 17 Add. extra labour on item No.15 for pacca brick work.
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate for 100 Sft Rs.
Say
Labour rate per Sqm Rs.
Say
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate for 100 Sft Rs.
Say
Labour rate per Sqm Rs.
Say
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Labour rate for 100 Sft
Say
Labour rate per Sqm
Say
Page 72
LABOUR for 125 Sft
4th & Subsequent Floor
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 73
DESCRIPTION OF ITEM:
Item No. 18 (i) Perforated pacca brick walling 9" thick in ground floor in
Mud Mortar
MUD MORTAR
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 74
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 75
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 76
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 77
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 78
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 79
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 80
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 81
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 82
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 83
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 84
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 85
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 86
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 87
DESCRIPTION OF ITEM:
Item No. 19 Extra labour in item No.18 for per perforated pacca brick
work in
LABOUR
First Floor
Page 88
DESCRIPTION OF ITEM:
Total
Contractor's Profit & Ov 20 Percent
Total
for mortar
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 89
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 90
DESCRIPTION OF ITEM:
Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with (1") 25 mm wide 18 gauge hoop iron.
(i) 4" (114 mm) thick walling with hoop iron bouding 6"
(150 mm) apart.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 91
DESCRIPTION OF ITEM:
Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with 1" (25 mm) wide 18 gauge hoop iron.
(ii) 4" (114 mm) thick walling with hoop iron bouding
12" (300 mm) apart.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 92
DESCRIPTION OF ITEM:
Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with 1" (25 mm) wide 18 gauge hoop iron.
(iii) 3" (75 mm) thick walling with hoop iron bouding 6"
(150 mm) apart.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 93
DESCRIPTION OF ITEM:
Item No. 21 First class brick walling laid in (1 : 3) cement sand mort
reinforced with 1" (25 mm) wide 18 gauge hoop iron.
(iv) 3" (75 mm) thick walling with hoop iron bouding 12"
(300 mm) apart.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 94
DESCRIPTION OF ITEM:
MATERIAL
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 95
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 96
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 97
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 98
DESCRIPTION OF ITEM:
Item No. 26 Providing Eave brick moulded weathered and throated with b
brick or drip course cornice in (1 : 3) cement mortar.
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 99
DESCRIPTION OF ITEM:
Item No. 26 Providing Eave brick moulded weathered and throated with b
brick or drip cornice in (1 : 3) cement mortars.
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 100
DESCRIPTION OF ITEM:
Item No. 26 Providing Eave brick moulded weathered and throated with b
brick or drip cornice in (1 : 3) cement mortar.
(iii) 4" (114 mm) thick eave brick with back brick.
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 101
DESCRIPTION OF ITEM:
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 102
DESCRIPTION OF ITEM:
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 103
DESCRIPTION OF ITEM:
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 104
DESCRIPTION OF ITEM:
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 105
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 106
DESCRIPTION OF ITEM:
Item No. 30 Supplying and filling sand under floors or plugging in wel
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 107
DESCRIPTION OF ITEM:
Item No. 31 Providing and laying 2" (50 mm) thick projected tile bank
(1: 2) cement sand mortar with hoop iron 1" (25 mm) wide 1
SWG flat iron sheet 9" (225 mm) apart.
Total
Contractor's Profit & Ov 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 108
DESCRIPTION OF ITEM:
Item No. 32 Ist class brick tiles (9" 4" x 1") 225 x 114 x 40 mm cla
76 mm thick laid in cement sand mortar recifered with hoop
strips placed at 2 ft. (600 mm) apart vertically.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 109
DESCRIPTION OF ITEM:
Item No. 32 Ist class brick tiles (9" 4" x 1") 225 x 114 x 40 mm cla
76 mm thick laid in cement sand mortar recifered with hoop
strips placed at 2 ft. (600 mm) apart vertically.
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 110
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
Page 111
DESCRIPTION OF ITEM:
Assume 60 Bricks
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 112
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & Ov 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
ITEM RATES
Page 113
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Ov 20 Percent
Total
Page 114
CHAPTER NO. 6
CONCRETE
DESCRIPTION OF ITEM:
Item No. 1 Mud concrete in foundation including watering and ramming using bri
or stone ballast 1" (40 mm) gauge.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 1
DESCRIPTION OF ITEM:
Item No. 2 Dry Ramming brick or stone ballast 1" to 2 (40 mm to 50 mm) gauge.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 2
DESCRIPTION OF ITEM:
Item No. 3 Cement concrete brick or stone ballast 1" to 2" (40 to 50 mm) gaug
foundation and plinth.
(a) Ratio (1 : 3 : 6)
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 3
DESCRIPTION OF ITEM:
Item No. 3 Cement concrete brick or stone ballast 1" to 2" (40 to 50 mm) gaug
foundation and plinth.
(b) Ratio (1 : 4 : 8)
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 4
DESCRIPTION OF ITEM:
Item No. 3 Cement concrete brick or stone ballast 1" to 2" (40 to 50 mm) gaug
foundation and plinth.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 5
DESCRIPTION OF ITEM:
Item No. 3 Cement concrete brick or stone ballast 1" to 2" (40 to 50 mm) gaug
foundation and plinth.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 6
DESCRIPTION OF ITEM:
Item No. 3 Cement concrete brick or stone ballast 1" to 2" (40 to 50 mm) gaug
foundation and plinth.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 7
DESCRIPTION OF ITEM:
Item No. 3 Cement concrete brick or stone ballast 1" to 2" (40 to 50 mm) gaug
foundation and plinth.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 8
DESCRIPTION OF ITEM:
Item No. 4 Extra on item No.3 above for Sedimentation tank or filter beds of P
Health Engineering Works.
(a) in bed.
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Labour rate per 100 Cft Rs. - Say
Labour rate per Cum Rs. - Say
DESCRIPTION OF ITEM:
Item No. 4 Extra on item No.3 above for Sedimentation tank or filter beds of P
Health Engineering Works.
(b) on slope.
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 9
DESCRIPTION OF ITEM:
Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).
(a) Ratio (1 : 1 : 2)
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 10
DESCRIPTION OF ITEM:
Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).
(b) Ratio (1 : 1 : 1)
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 11
DESCRIPTION OF ITEM:
Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).
(c) Ratio (1 : 1 : 3)
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 12
DESCRIPTION OF ITEM:
Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).
(d) Ratio (1 : 2 : 3)
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 13
DESCRIPTION OF ITEM:
Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).
(e) Ratio (1 : 3 : 3)
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 14
DESCRIPTION OF ITEM:
Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).
(f) Ratio (1 : 2 : 4)
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 15
DESCRIPTION OF ITEM:
Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).
(g) Ratio (1 : 2 : 6)
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 16
DESCRIPTION OF ITEM:
Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).
(h) Ratio (1 : 3 : 6)
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 17
DESCRIPTION OF ITEM:
Item No. 5 Cement concrete plain including, placing, compacting, finishing and
complete (including screening and washing of stone aggregate).
(i) Ratio (1 : 4 : 8)
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 18
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).
(a) (i) Reinforced cement concrete in roof slab, beams, columns, lintels, g
and other structural members laid in situ or pre cast laid in posit
stressed members cast in situ complete in all respect.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Page 19
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).
(a) (i) Reinforced cement concrete in roof slab, beams, columns, lintels, g
and other structural members laid in situ or pre cast laid in posit
stressed members cast in situ complete in all respect.
4 Shuttering
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 100 Cft
Rate per Cft
ITEM RATES
Labour rate per Cft Rs. - Say
Labour rate per Cum Rs. Say
Page 20
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).
(a) (i) Reinforced cement concrete in roof slab, beams, columns, lintels, g
and other structural members laid in situ or pre cast laid in posit
stressed members cast in situ complete in all respect.
4 Shuttering
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 100 Cft
Rate per Cft
ITEM RATES
Labour rate per Cft Rs. - Say
Labour rate per Cum Rs. Say
Page 21
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 100 Cft
Rate per Cft
ITEM RATES
Page 22
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 100 Cft
Rate per Cft
ITEM RATES
Page 23
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 100 Cft
Rate per Cft
ITEM RATES
Page 24
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).
4 Shuttering
Assume beam of 12' x 12" x 6" = 6 Cft
Wood
Planks = 2 x 12 1/6 x 13/12 x 2 1/12 = 2.2 Cft
1 x 12 1/6 x 1/12 x = 0.51 Cft
2 x 1/12 x 12/12 x 6/12 = 0.08 Cft
Studs = 2 x 5 x 1/6 x 1/12 = 0.04 Cft
Total 2.93 Cft
For 100 Cft 2.93 6 x 100 = 48.73 Cft
Can be used in 40 operation
One operation 48.73 40.0Cft = 1.22 Cf 1.22 Cft - Per Cft
Nails, nuts & bolts etc. 4.00 No. - Each
Greasing and oiling for shuttering surface 2.11 Kg. - Per Kg.
Total
Contractor's Profit & Overhe 20 Percent
Total
LABOUR
ITEM RATES
Labour rate per Cft Rs. - Say
Labour rate per Cum Rs. Say
Page 25
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).
4 Shuttering
Kail Woood for shuttering as per item 5 (b) (1) 1.22 Cft - Cft
Nails, nuts & bolts etc. 4.00 No. - Each
Greasing and oiling etc. 2.11 Kg. - Per Kg.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 100 Cft
Rate per Cft
ITEM RATES
Page 26
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).
(b) (i) Precast reinforced cement concrete and prestresed reinforced cement
concrete in columns, beams, lintels, stair cases, shelves etc.
4 Shuttering
Kail Woood for shuttering as per item 5 (b) (1) 1.22 Cft - Cft
Nails, nuts & bolts etc. 4.00 No. - Each
Greasing and oiling etc. 1.71 Kg. - Per Kg.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 100 Cft
Rate per Cft
ITEM RATES
Page 27
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 100 Cft
Rate per Cft
ITEM RATES
Page 28
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying reinforced cement concrete (including pre-stre
concrete), using coarse sand and screened graded and washed
aggregated, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing ex
surface, complete (but excluding the cost of steel reinforcement, i
fabrication and placing in position etc).
(d) Add extra labour for R.C. concrete in 2nd and subsequent stories.
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 29
DESCRIPTION OF ITEM:
Item No. 7 Providing and casting in situ bored reinforced concrete pile with t
concrete (Nominal mix 1 : 2: 4), using 10% extra cement in dry mix,
course sand including all labour and material (except the cost of s
reinforcement and its labour for bending and laying in position etc
will be paid separately, including screening and washing of shingle
curing.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent o0.00
Total
Contractor's Profit & Overhea 20 Percent
on Rs. 4725.45 + 472.55 =
Total for 100 Rft
ITEM RATES
Labour rate per Rft Rs. Say
Labour rate per L.M Rs. - Say
Page 30
DESCRIPTION OF ITEM:
Item No. 7 Providing and casting in situ bored reinforced concrete pile with t
concrete (Nominal mix 1 : 2: 4), using 10% extra cement in dry mix,
course sand including all labour and material (except the cost of s
reinforcement and its labour for bending and laying in position etc
will be paid separately, including screening and washing of shingle
curing.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent o 0.00
Total
Contractor's Profit & Overhea 20 Percent
on Rs. 0.00 + - = 0.00
Total for 100 Rft
ITEM RATES
Labour rate per Rft Rs. - Say
Labour rate per L.M Rs. - Say
Page 31
DESCRIPTION OF ITEM:
Item No. 7 Providing and casting in situ bored reinforced concrete pile with t
concrete (Nominal mix 1 : 2: 4), using 10% extra cement in dry mix,
course sand including all labour and material (except the cost of s
reinforcement and its labour for bending and laying in position etc
will be paid separately, including screening and washing of shingle
curing.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
on Rs. 11245.00 + 1124.50 =
Total for 100 Rft
ITEM RATES
Labour rate per Rft Rs. - Say
Labour rate per L.M Rs. - Say
Page 32
DESCRIPTION OF ITEM:
Item No. 7 Providing and casting in situ bored reinforced concrete pile with t
concrete (Nominal mix 1 : 2: 4), using 10% extra cement in dry mix,
course sand including all labour and material (except the cost of s
reinforcement and its labour for bending and laying in position etc
will be paid separately, including screening and washing of shingle
curing.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent o 0.00
Total
Contractor's Profit & Overhea 20 Percent
on Rs. 13528.75 + 1352.88 = Rs. 0.00
Total for 100 Rft
ITEM RATES
Labour rate per Rft Rs. - Say
Labour rate per L.M Rs. - Say
Page 33
DESCRIPTION OF ITEM:
Item No. 8 Fabrication of mild steel reinforcement bar cage for R.C.C bored pi
including cutting bending, laying in position, welding and fastenin
including cost of binding wire and labour charges for binding of st
reinforcement (also includes removal of rust from the bars).
Total
Contractor's Profit & Overhea 20 Percent
Total
Material cost per Cwt
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 34
DESCRIPTION OF ITEM:
Item No. 8 Fabrication of mild steel reinforcement bar cage for R.C.C bored pi
including cutting bending, laying in position, welding and fastenin
including cost of binding wire and labour charges for binding of st
reinforcement (also includes removal of rust from the bars).
Total
Contractor's Profit & Overhea 20 Percent
Total
Material cost per Cwt
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 35
DESCRIPTION OF ITEM:
Item No. 9 Fabrication of mild steel reinforcement for cement concrete, includ
cutting, bending, laying in position, making joints and fastenings,
cost of binding wire and labour charges for binding of steel reinfo
(also includes the removal of rust from bars).
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 36
DESCRIPTION OF ITEM:
Item No. 9 Fabrication of mild steel reinforcement for cement concrete, includ
cutting, bending, laying in position, making joints and fastenings,
cost of binding wire and labour charges for binding of steel reinfo
(also includes the removal of rust from bars).
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 37
DESCRIPTION OF ITEM:
Item No. 10 Pre cast cement concrete solid or face blocks (1 : 2 : 4) including
templates.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 100 Cft
ITEM RATES
Page 38
DESCRIPTION OF ITEM:
Item No. 11 Pre cast cement concrete hollow block (1 : 2 : 4) including cost of
and constructing walls thereof.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 39
DESCRIPTION OF ITEM:
Item No. 12 Providing and fixing ornamental concrete cement Jali 2" (50 mm) thi
(1 : 2 : 4) without steel.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 40
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate for 100 Cft 363.00 x 10 0.00
125
ITEM RATES
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate for 100 Cft 226.88 x 10 0.00
125
ITEM RATES
Page 41
DESCRIPTION OF ITEM:
Item No. 14 Extra labour work of weir, rail or road bridges syphons and concret
super-structure.
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate for 100 Cft 0.00
125
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 15 Making reinforced cement concrete spout, including fixing in positi
(2' x 6" x 5").
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Labour rate per Spout Rs. - Say
Composit rate per Spout Rs. - Say
Page 42
DESCRIPTION OF ITEM:
Item No. 16 Making hole upto 3" (75 mm) dia 18" (450 mm) deep in cement concret
stone masonry walls and repairing.
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate per 100 Cft 750.20 x 10 0.00
150
ITEM RATES
Page 43
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate per 100 Sft x 100
125
ITEM RATES
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate per 100 Sft x 100
125
ITEM RATES
Page 44
DESCRIPTION OF ITEM:
Item No. 19 Preparing, watering and ramming surface for laying concrete (for he
works only).
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate per 100 Sft x 100
125
ITEM RATES
Labour rate per 100 Sft Rs. - Say
Labour rate per Sqm Rs. - Say
DESCRIPTION OF ITEM:
Item No. 19 Preparing, watering and ramming surface for laying concrete (for he
works only).
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate per 100 Sft x 100
125
ITEM RATES
Labour rate per 100 Sft Rs. - Say
Labour rate per Sqm Rs. - Say
Page 45
DESCRIPTION OF ITEM:
Item No. 19 Preparing, watering and ramming surface for laying concrete (for he
works only).
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate per 100 Sft x 100
125
ITEM RATES
Page 46
DESCRIPTION OF ITEM:
Item No. 20 Fabrication of high tensile steel prestressing cables for prestress
(post tensioned) concrete, including assembling by drawing the H.T.
through metal spacer plate, inserting in helix core and taping or t
sheathing in longitudinally welded metal corrugated sheath, positio
anchorage with male and female set of anchorage cone, forming ducts
transverse cable, stressing cables with jack at both ends as per st
schedule, maintaining stressing record and supply the same in the
approved proforma to the Engineering-in-charge, making loop at blin
including all materials required for it, grouting the cable ducts w
cutting projected ends and making good recesses, etc., complete in
respects.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
Rate for 100 Kg 0.00 x 100 =
85.65
Page 47
LABOUR for 4 Nos.
Total
Sundries 10 Percent o 0.00
Total
Contractor's Profit & Overhea 20 Percent
Total for 4 Nos.
Rate for one cable (85.65 Kg) 0 4 =
Rate for 100 Kg - x 100
85.65
ITEM RATES
Page 48
DESCRIPTION OF ITEM:
Total
Contractor's Profit & Overhea 20 Percent
Total
Page 49
DESCRIPTION OF ITEM:
Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam
Girder and other members (excluding battens) etc., in position on
bridge to correct alignment and level, etc., complete.
ITEM RATES
Labour rate per 100 Cft Rs. - Say
Labour rater per Cum Rs. - Say
Page 50
DESCRIPTION OF ITEM:
Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam
Girder and other members (excluding battens) etc., in position on
bridge to correct alignment and level, etc., complete.
EQUIPMENT
Total
ITEM RATES
Page 51
DESCRIPTION OF ITEM:
Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam
Girder and other members (excluding battens) etc., in position on
bridge to correct alignment and level, etc., complete.
(iii) Beam above 75 ft. upto 100 ft (23 metre to 30 metre) length.
EQUIPMENT
Total
ITEM RATES
Page 52
DESCRIPTION OF ITEM:
Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam
Girder and other members (excluding battens) etc., in position on
bridge to correct alignment and level, etc., complete.
(iv) Beam above 100 ft. upto 150 ft (23 metre to 30 metre) length.
EQUIPMENT
Total
ITEM RATES
Page 53
DESCRIPTION OF ITEM:
Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam
Girder and other members (excluding battens) etc., in position on
bridge to correct alignment and level, etc., complete.
(v) Beam above 150 ft. upto 175 ft (46 metre to 53 metre) length.
EQUIPMENT
Total
ITEM RATES
Page 54
DESCRIPTION OF ITEM:
Item No. 23 Providing and laying foam concrete 3" (75 mm) thick, using cement s
the ratio of 1 : 2 and aluminum powder at the rate of 0.2% of the c
mix.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 55
DESCRIPTION OF ITEM:
Item No. 24 Providing and fixing 6" (150 mm) wide curved sheet of required shap
on face of the construction joint with G.I. Screw, 1.5" (40 mm) lon
construction joints vertically.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 56
DESCRIPTION OF ITEM:
Item No. 24 Providing and fixing 6" (150 mm) wide curved sheet of required shap
on face of the construction joint with G.I. Screw, 1.5" (40 mm) lon
construction joints vertically.
1 G.I. Sheet 12' x 6" (3.60 x 0.150 metre) = 6 Sft 5.77 kg - per kg
2 Special shape i.e V shaped 2' (600 mm)
Interval 6.00 Nos. - each
Total
Contractor's Profit & Overhea 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 57
DESCRIPTION OF ITEM:
Item No. 25 Providing and fixing 1/8" (3 mm) thick 3" (75 mm) wide aluminum str
horizontal and vertical expansion joints in walls, columns, ceiling
etc., including cost of clips/screws etc., complete in all respect
Total
Contractor's Profit & Overhea 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 58
DESCRIPTION OF ITEM:
Item No. 25 Providing and fixing 1/8" (3 mm) thick 3" (75 mm) wide aluminum str
horizontal and vertical expansion joints in walls, columns, ceiling
etc., including cost of clips/screws etc., complete in all respect
Total
Contractor's Profit & Overhea 20 Percent
Total
Cost of Material/Rft
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 59
DESCRIPTION OF ITEM:
Item No. 26 Providing and fixing 1/16" (1.6 mm) thick copper flashing on expans
complete in all respects.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 60
DESCRIPTION OF ITEM:
Item No. 27 Providing and fixing 6" (150 mm) wide G.I. sheet 18 SWG stopper to
joint.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 61
DESCRIPTION OF ITEM:
Item No. 28 Providing and embedding 10" (250 mm) wide 1/4" thick (6 mm) thick r
water stopper in expansion joints of R.C.C roof slab complete in al
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 62
DESCRIPTION OF ITEM:
Item No. 29 Filling expansion joints with bitumen sand and sawdust in ratio (1
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 63
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 64
DESCRIPTION OF ITEM:
Item No. 32 Providing and fixing thermopore (foamed polythene) sheet in horizon
vertical expansion joints.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 65
DESCRIPTION OF ITEM:
Item No. 32 Providing and fixing thermopore (foamed polythene) sheet in horizon
vertical expansion joints.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 66
DESCRIPTION OF ITEM:
Item No. 33 Providing and laying damp proof course of cement concrete 1 2 : 4 (
cement sand and shingle) including bitumen coating.
(a) With one coat of bitumen and one coat polythene sheet 500 gauge.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 150 Sft
ITEM RATES
Page 67
DESCRIPTION OF ITEM:
Item No. 33 Providing and laying damp proof course of cement concrete 1 2 : 4 (
cement sand and shingle) including bitumen coating.
(a) With one coat of bitumen and one coat polythene sheet 500 gauge.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 150 Sft
ITEM RATES
Page 68
DESCRIPTION OF ITEM:
Item No. 33 Providing and laying damp proof course of cement concrete 1 2 : 4 (
cement sand and shingle) including bitumen coating.
(a) With one coat of bitumen and one coat polythene sheet 500 gauge.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 150 Sft
ITEM RATES
Page 69
DESCRIPTION OF ITEM:
Item No. 33 Providing and laying damp proof course of cement concrete 1 2 : 4 (
cement sand and shingle) including bitumen coating.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 150 Sft
ITEM RATES
Page 70
DESCRIPTION OF ITEM:
Item No. 33 Providing and laying damp proof course of cement concrete 1 2 : 4 (
cement sand and shingle) including bitumen coating.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total for 150 Sft
ITEM RATES
Page 71
DESCRIPTION OF ITEM:
Item No. 33 Providing and laying damp proof course of cement concrete 1 2 : 4 (
cement sand and shingle) including bitumen coating.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 72
DESCRIPTION OF ITEM:
Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.
(a) With one coat of bitumen and one coat polythen sheet 500 gauge.
(i) Ratio 1 : 4.
(a) " (12 mm) thick.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 73
DESCRIPTION OF ITEM:
Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.
(a) With one coat of bitumen and one coat polythen sheet 500 gauge.
(i) Ratio 1 : 4.
(b) " (20 mm) thick.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 74
DESCRIPTION OF ITEM:
Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.
(a) With one coat of bitumen and one coat polythen sheet 500 gauge.
(ii) Ratio 1 : 3.
(a) " (12 mm) thick.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate fore 150 Sft
ITEM RATES
Page 75
DESCRIPTION OF ITEM:
Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.
(a) With one coat of bitumen and one coat polythen sheet 500 gauge.
(ii) Ratio 1 : 3.
(b) " (20 mm) thick.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 76
DESCRIPTION OF ITEM:
Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.
(a) With one coat of bitumen and one coat polythen sheet 500 gauge.
(iii) Ratio 1 : 2.
(a) " (12 mm) thick.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on items 1, 2, 3,4 & 6
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 77
DESCRIPTION OF ITEM:
Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.
(a) With one coat of bitumen and one coat polythen sheet 500 gauge.
(iii) Ratio 1 : 2.
(b) " (20 mm) thick.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3, 4 & 6
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 78
DESCRIPTION OF ITEM:
Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 79
DESCRIPTION OF ITEM:
Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 80
DESCRIPTION OF ITEM:
Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent in item 1, 2, 3 & 4
i.e. on Rs -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 81
DESCRIPTION OF ITEM:
Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent in item 1, 2, 3 & 4
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 82
DESCRIPTION OF ITEM:
Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent in item 1, 2, 3 & 4
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 83
DESCRIPTION OF ITEM:
Item No. 34 Provding and laying damp proof course with cement sand plaster and
coating.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent in item 1, 2, 3 & 4
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 84
DESCRIPTION OF ITEM:
Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.
(a) With one coat of bitumen & one layer of polythene sheet 500 gauge.
(i) Ratio 1 : 4.
(a) " (12 mm) thick.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3, 4 & 6
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 85
DESCRIPTION OF ITEM:
Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.
(a) With one coat of bitumen & one layer of polythene sheet 500 gauge.
(i) Ratio 1 : 4.
(b) " (20 mm) thick.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3, 4 & 6
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 86
DESCRIPTION OF ITEM:
Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.
(a) With one coat of bitumen & one layer of polythene sheet 500 gauge.
(ii) Ratio 1 : 3.
(a) " (12 mm) thick.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3, 4 & 6
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 87
DESCRIPTION OF ITEM:
Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.
(a) With one coat of bitumen & one layer of polythene sheet 500 gauge.
(ii) Ratio 1 : 3.
(b) " (20 mm) thick.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 4, 5 & 6
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 88
DESCRIPTION OF ITEM:
Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.
(a) With one coat of bitumen & one layer of polythene sheet 500 gauge.
(iii) Ratio 1 : 2.
(a) " (12 mm) thick.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3, 4 & 6
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 89
DESCRIPTION OF ITEM:
Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.
(a) With one coat of bitumen & one layer of polythene sheet 500 gauge.
(iii) Ratio 1 : 2.
(b) " (20 mm) thick.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3, 4 & 6
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 90
DESCRIPTION OF ITEM:
Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 91
DESCRIPTION OF ITEM:
Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 92
DESCRIPTION OF ITEM:
Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 93
DESCRIPTION OF ITEM:
Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 94
DESCRIPTION OF ITEM:
Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 95
DESCRIPTION OF ITEM:
Item No. 35 Providing and laying vertical damp proof course with cement sand pl
bitumen coating.
MATERIAL
Total
Contractor's Profit & Overhea 20 Percent on item 1, 2, 3 & 4
i.e. on Rs. -
Total
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total rate for 150 Sft
ITEM RATES
Page 96
DESCRIPTION OF ITEM:
Item No. 36 Grouting concrete between the grooves of gates including shuttering
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
DESCRIPTION OF ITEM:
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 97
DESCRIPTION OF ITEM:
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
DESCRIPTION OF ITEM:
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 98
DESCRIPTION OF ITEM:
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
DESCRIPTION OF ITEM:
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 99
DESCRIPTION OF ITEM:
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
DESCRIPTION OF ITEM:
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 100
DESCRIPTION OF ITEM:
Item No. 41 Supplying and fixing broken glasses on courtyard walls, including 1
cement concrete coping.
Total
Contractor's Profit & Overhea 20 Percent
Total
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 101
DESCRIPTION OF ITEM:
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
DESCRIPTION OF ITEM:
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 102
DESCRIPTION OF ITEM:
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
DESCRIPTION OF ITEM:
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 103
DESCRIPTION OF ITEM:
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
DESCRIPTION OF ITEM:
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 104
DESCRIPTION OF ITEM:
Item No. 44 Screening and stacking stone ballast shingle or bajri etc.
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
DESCRIPTION OF ITEM:
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 105
DESCRIPTION OF ITEM:
Item No. 46 Erecting and carting sun shades of precast R.C concrete upto 5' x 2
(1.50 x 0.760 metre).
Assume 5 Nos.
LABOUR
Total
Sundries 10 Percent
Total
Contractor's Profit & Overhea 20 Percent
Total
ITEM RATES
Page 106
CHAPTER NO.4
DISMANTLING
DESCRIPTION OF ITEM:
ITEM RATES
Page 1
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
Page 2
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
Page 3
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
Page 4
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
Page 5
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
Page 6
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
Page 7
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
Page 8
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
Page 9
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
Page 10
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
Page 11
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
Page 12
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
Item No. 19 (e) Dismantling D.P.C of cement concrete 1" thick and cleari
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
Page 13
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
Page 14
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
Page 15
DESCRIPTION OF ITEM:
Item No. 23 Dismantling from any height asbestos sheet and ridge copi
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
Item No. 24 (a) Dismantling roof of wooden planks and battens upto any he
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
Page 16
DESCRIPTION OF ITEM:
Item No. 24 (b) Dismantling wooden ceiling above 6 m (20' height) in diff
including lifting with care and special scaffolding along
and with machines underneath.
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
Page 17
DESCRIPTION OF ITEM:
Item No. 26 Dismantling R.B. roof complete with mud and mud plaster i
separating reinforcement, cleaning and straightening the
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
Item No. 27 (a) Stripping and stackings slates or tiles from the truss ro
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
Page 18
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
Item No. 27 (c) Extra for dismantling G.I. sheet roof above 6 m (20') in
position including lifting with special scaffolding alone
wires with machines under-neath.
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
Page 19
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
Page 20
DESCRIPTION OF ITEM:
ITEM RATES
Page 21
DESCRIPTION OF ITEM:
Item No. 31 Dis-jointing R.C.C. pipe inside the trench and dismentlin
the pipes from the trench and stacking them out side.
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
NOTE: 1) Bends, elbows, sluice valves etc should not be paid for e
of pipe line that is being dismantled.
2) The rate does not include the cost of excavation and refi
Page 22
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Page 23
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Page 24
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Page 25
DESCRIPTION OF ITEM:
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATE
Labour rate per No. Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
Item No. 32 (b) Removing window and sky lights with chowkat.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATE
Labour rate per No. Rs. 0.00 Say
Page 26
DESCRIPTION OF ITEM:
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATE
Labour rate per No. Rs. 0.00 Say
DESCRIPTION OF ITEM:
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATE
Labour rate per No. Rs. 0.00 Say 0.00
Page 27
DESCRIPTION OF ITEM:
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATE
Labour rate per No. Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
Page 28
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
Labour rate per Cwt 0.00
ITEM RATES
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per Rft Rs. 0.00 Say 0.00
Labour rate per Metre Rs. 0.00 Say 0.00
Page 29
DESCRIPTION OF ITEM:
Item No. 37 Dismantling iron work of trusses, sheds, water tanks etc.
cutting of rivets.
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
Labour rate per Cwt 0.00
ITEM RATES
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
Labour rate per Cwt 0.00
ITEM RATES
Page 30
DESCRIPTION OF ITEM:
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATE
Labour rate per unit of two seats Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
Item No. 40 Dismantling tees, bends or sluice valves upto 12" bore.
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
Labour rate for 1 No. 12" bore 0.00
ITEM RATES
Labour rate for each per 1" (25mm) bore Rs. 0.00 Say 0.00
Labour rate for each per cm bore Rs. 0.00 Say 0.00
Page 31
DESCRIPTION OF ITEM:
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate for Each Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate for Each Rs. Say 0.00
Page 32
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Rft Rs. 0.00 Say 0.00
Labour rate per R.M Rs. Say
DESCRIPTION OF ITEM:
Item No. 43 Dismantling wire netting of tennis court and frame work.
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
Page 33
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total
ITEM RATES
Labour rate per 100 Sft Rs. Say
Labour rate per Sqm Rs. Say
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
Page 34
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & Ove 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Sft Rs. Say 0.00
Labour rate per Sqm Rs. Say 0.00
Page 35
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
Page 36
DESCRIPTION OF ITEM:
Item No. 49 (b) Scrapping ordinary distemper, oil bound distemper or pain
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Sft Rs. 0.00 Say 0.00
Labour rate per Sqm Rs. 0.00 Say 0.00
Page 37
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00
ITEM RATES
Labour rate per 100 Cft Rs. 0.00 Say 0.00
Labour rate per Cum Rs. 0.00 Say 0.00
Page 38
DESCRIPTION OF ITEM:
Item No. 53 Dismantling of light, fans & call bell point including ca
open type & making good damaged surface (building portion
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00
ITEM RATES
Page 39
DESCRIPTION OF ITEM:
Item No. 54 Dismantling plug point and making good damaged surface (b
portion).
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00
ITEM RATES
Page 40
DESCRIPTION OF ITEM:
(i) On surface.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00
ITEM RATES
Page 41
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor Profit 20.00 Percent 0.00
Total 0.00
ITEM RATES
Page 42
CHAPTER NO.3
EARTH WORK
(EXCAVATION & EMBANKMENT)
DESCRIPTION OF ITEM:
Item No. 1 Earth work excavation undressed lead upto a single throw of kassi,
Phaorah or shovel.
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 1
DESCRIPTION OF ITEM:
Item No. 1 Earth work excavation undressed lead upto a single throw of kassi,
Phaorah or shovel.
b) In ordinary soil.
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 2 Earthwork excavation in ashes, sand and soft soil or silt clearance,
undressed lead upto 50 ft (15 metre).
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 2
DESCRIPTION OF ITEM:
Item No. 3 Bed clearance and dressing slopes of drains to required sections
including the removal of weeds, roots, etc, disposal of excavated
materials within 50 ft (15 metre) lead.
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 3 Bed clearance and dressing slopes of drains to required sections
including the removal of weeds, roots, etc., disposal of excavated
materials within 50 ft (15 metre) lead.
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 3
DESCRIPTION OF ITEM:
Item No. 4 Borrowpit excavation undressed lead upto 100 ft. (30 metre)
a) Ordinary Soil.
1 Coolies unskilled for digging and filling 4.00 Nos. per day -
2 Coolies unskilled for carrying 3.00 Nos. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 4 Borrowpit excavation undressed lead upto 100 ft. (30 metre).
b) Hard Soil.
1 Coolies unskilled for digging and filling 5.60 Nos. per day -
2 Coolies unskilled for carrying 3.00 Nos. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 4
DESCRIPTION OF ITEM:
Item No. 5 Earthwork in ordinary soil for embankments lead upto 100 ft. (30 metre)
including ploughing and mixing with blade grade or disc harrow or
other suitable equipment and compaction by mechanical means at
optimum moisture content and dressing to designed section, complete
in all respects:
(i) 95% to 100% maximum modified AASHTO dry-density with vibratory roller.
Mixing, Moisterning earth to optimum moisture contant in layer etc.
complete with tractor complete with rotorator blade.
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
Total -
ITEM RATES
Page 5
DESCRIPTION OF ITEM:
Item No. 5 Earthwork in ordinary soil for embankments lead upto 100 ft. (30 metre)
including ploughing and mixing with blade grade or disc harrow or
other suitable equipment and compaction by mechanical means at
optimum moisture content and dressing to designed section, complete
in all respects:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
Total -
ITEM RATES
Page 6
DESCRIPTION OF ITEM:
Item No. 5 Earthwork in ordinary soil for embankments lead upto 100 ft. (30 metre)
including ploughing and mixing with blade grade or disc harrow or
other suitable equipment and compaction by mechanical means at
optimum moisture content and dressing to designed section, complete
in all respects:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
Total -
ITEM RATES
Page 7
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 8
DESCRIPTION OF ITEM:
Item No. 7 Earthwork excavation in open cutting upto 5 ft (1500 mm) depth for storm
water channels, drains, sullage drains in open areas, roads, streets, lane
including under pinning of walls and shoring to protect existing works,
shuttering and timbering the trenches, dressed to designed level and
dimensions, trimming, removal of suface water from trenches, back filling
surplus excavated material disposed of and dressed within 50 ft (15 metre)
lead.
i) Ordinary
Total -
Contractor's Profit & Ove ##### Percent -
Total -
LABOUR
1 Coolies unskilled for digging, filling & dagbelling 4.00 Nos. per day -
2 Coolies unskilled for carrying 1.50 Nos. per day -
3 Coolies unskilled for temporary diviation 0.50 No. per day -
4 Coolies unskilled for removal of surplus water 0.50 No. per day -
5 Cooly un-skilled 1.00 No. per day -
6 Dresser 1.00 No. per day -
7 Skilled cooly for fixing and timbering
under pinning 0.20 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 9
DESCRIPTION OF ITEM:
Item No. 7 Earthwork excavation in open cutting upto 5 ft (1500 mm) depth for storm
water channels, drains, sullage drains in open areas, roads, streets, lane
including under pinning of walls and shoring to protect existing works,
shuttering and timbering the trenches, dressed to designed level and
dimensions, trimming, removal of suface water from trenches, back filling
surplus excavated material disposed of and dressed within 50 ft (15 metre)
lead.
ii) Hard
Total -
Contractor's Profit & Ove ##### Percent -
Total -
LABOUR
1 Coolies unskilled for digging, filling & dagbelling 5.60 Nos. per day -
2 Coolies unskilled for carrying 1.50 Nos. per day -
3 Coolies unskilled for temporary diviation 0.50 No. per day -
4 Coolies unskilled for removal of surplus water 0.50 No. per day -
5 Cooly un-skilled 1.00 No. per day -
6 Dresser 1.00 No. per day -
7 Skilled cooly for fixing and timbering
under pinning 0.20 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 10
DESCRIPTION OF ITEM:
Item No. 7 Earthwork excavation in open cutting upto 5 ft (1500 mm) depth for storm
water channels, drains, sullage drains in open areas, roads, streets, lane
including under pinning of walls and shoring to protect existing works,
shuttering and timbering the trenches, dressed to designed level and
dimensions, trimming, removal of suface water from trenches, back filling
surplus excavated material disposed of and dressed within 50 ft (15 metre)
lead.
Total -
Contractor's Profit & Ove ##### Percent -
Total -
LABOUR
1 Coolies unskilled for digging, filling & dagbelling 7.30 Nos. per day -
2 Coolies unskilled for carrying 1.50 Nos. per day -
3 Coolies unskilled for temporary diviation 0.50 No. per day -
4 Coolies unskilled for removal of surplus water 0.50 No. per day -
5 Cooly un-skilled 1.00 No. per day -
6 Dresser 1.00 No. per day -
7 Skilled cooly for fixing and timbering
under pinning 0.20 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 11
DESCRIPTION OF ITEM:
Item No. 7 Earthwork excavation in open cutting upto 5 ft (1500 mm) depth for storm
water channels, drains, sullage drains in open areas, roads, streets, lane
including under pinning of walls and shoring to protect existing works,
shuttering and timbering the trenches, dressed to designed level and
dimensions, trimming, removal of suface water from trenches, back filling
surplus excavated material disposed of and dressed within 50 ft (15 metre)
lead.
iv) Gravel and Shingle.
Total -
Contractor's Profit & Ove ##### Percent -
Total -
LABOUR
1 Coolies unskilled for digging, filling & dagbelling 10.00 Nos. per day -
2 Coolies unskilled for carrying 4.50 No. per day -
3 Coolies unskilled for temporary diviation 2.00 No. per day -
4 Coolies unskilled for removal of surplus water 1.00 No. per day -
5 Cooly un-skilled 0.50 No. per day -
6 Dresser 2.00 No. per day -
7 Skilled cooly for fixing and timbering
under pinning 0.20 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 12
DESCRIPTION OF ITEM:
Item No. 8 Earth work excavation in open cutting 5.01 ft.(1527mm) to 10.0 ft. (3000mm
depth for storm water channels, drains sullage drains in open areas, roads
streets, lanes including under pinning of walls and shoring to protect
existing works, shuttering and timbering the trenches, dressed to disigned
level and dimensions, trimming, removal of surface water from trenches,
back filling and surplus excavated material disposal of and dressed within
100 ft. (30 metre) lead.
i) Ordinary soil
Total -
Contractor's Profit & Ove ##### Percent -
Total -
LABOUR
1 Coolies unskilled for digging and filling 4.00 Nos. per day -
2 Coolies unskilled for carrying 4.00 Nos. per day -
3 Coolies unskilled for removing surface water 0.50 No. per day -
4 Dresser for dressing, fixing shuttering
removing and temporary shuttering 1.00 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 13
DESCRIPTION OF ITEM:
Item No. 8 Earth work excavation in open cutting 5.01 ft.(1527mm) to 10.0 ft. (3000mm
depth for storm water channels, drains sullage drains in open areas, roads
streets, lanes including under pinning of walls and shoring to protect
existing works, shuttering and timbering the trenches, dressed to disigned
level and dimensions, trimming, removal of surface water from trenches,
back filling and surplus excavated material disposal of and dressed within
100 ft. (30 metre) lead.
Total -
Contractor's Profit & Ove ##### Percent -
Total -
LABOUR
1 Coolies unskilled for digging and filling 5.60 Nos. per day -
2 Coolies unskilled for carrying 4.00 Nos. per day -
3 Coolies unskilled for removing surface water 0.50 No. per day -
4 Dresser for dressing, fixing shuttering
removing and temporary shuttering 1.00 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 14
DESCRIPTION OF ITEM:
Item No. 8 Earth work excavation in open cutting 5.01 ft.(1527mm) to 10.0 ft. (3000mm
depth for storm water channels, drains sullage drains in open areas, roads
streets, lanes including under pinning of walls and shoring to protect
existing works, shuttering and timbering the trenches, dressed to disigned
level and dimensions, trimming, removal of surface water from trenches,
back filling and surplus excavated material disposal of and dressed within
100 ft. (30 metre) lead.
Total -
Contractor's Profit & Ove ##### Percent -
Total -
LABOUR
1 Coolies unskilled for digging and filling 7.30 Nos. per day -
2 Coolies unskilled for carrying 4.00 Nos. per day -
3 Coolies unskilled for removing surface water 0.50 No. per day -
4 Dresser for dressing, fixing shuttering
removing and temporary shuttering 1.00 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 15
DESCRIPTION OF ITEM:
Item No. 8 Earth work excavation in open cutting 5.01 ft.(1527mm) to 10.0 ft. (3000mm
depth for storm water channels, drains sullage drains in open areas, roads
streets, lanes including under pinning of walls and shoring to protect
existing works, shuttering and timbering the trenches, dressed to disigned
level and dimensions, trimming, removal of surface water from trenches,
back filling and surplus excavated material disposal of and dressed within
100 ft. (30 metre) lead.
Total -
Contractor's Profit & Ove ##### Percent -
Total -
LABOUR
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 16
DESCRIPTION OF ITEM:
Item No. 9 Excavation in shingle or gravel formation and rock, not, requiring
blasting, undressed lead upto 100 ft. (30 metre).
i) Dry
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 9 Excavation in shingle or gravel formation and rock, not, requiring
blasting, undressed lead upto 100 ft. (30 metre).
ii) Wet
ITEM RATES
Labour rate per 1000 Cft Rs. Say -
Labour rate per Cum Rs. Say -
Page 17
DESCRIPTION OF ITEM:
Item No. 9 Excavation in shingle or gravel formation and rock, not, requiring
blasting, undressed lead upto 100 ft. (30 metre).
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 10 Earth work excavation in irrigation channels, drains, etc., to designed
section, grades and profiles excavated material disposed off and dressed
with in 50 ft (15 metre) lead.
i) Ordinary soil
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Labour rate per 1000 Cft Rs. Say -
Labour rate per Cum Rs. Say -
Page 18
DESCRIPTION OF ITEM:
Item No. 10 Earth work excavation in irrigation channels, drains, etc., to designed
section, grades and profiles excavated material disposed off and dressed
with in 50 ft (15 metre) lead.
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 1000 Cft Rs. Say -
Labour rate per Cum Rs. Say -
Page 19
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 1000 Cft Rs. Say -
Labour rate per Cum Rs. Say -
DESCRIPTION OF ITEM:
Item No. 11 Excavation in rock dressed to designed section, grades and profiles,
excavated material disposed off within 100 ft. (30 metre) and lift upto 5
(1.5 metre).
a) Soft rock, Slate, Shale, Schist or laterite works, with pick & crowbar.
1 Coolies unskilled for digging & carrying 14.00 Nos. per day -
2 Dresser 4.00 Nos. per day -
3 Bahishti 1.00 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Labour rate per 1000 Cft Rs. Say -
Labour rate per Cum Rs. Say -
Page 20
DESCRIPTION OF ITEM:
LABOUR
1 Coolies skilled for boring holes with steel jumper 3.00 Nos. per day -
2 Coolies skilled for tempering & fixing charges 0.13 No. per day -
3 Blowman 1.00 No. per day -
4 Coolies unskilled for digging 12.00 Nos. per day -
5 Breaking coolies un-skilled stone and removing the spoil 9.00 Nos. per day -
6 Mate (skilled cooly) 0.50 No. per day -
7 Dresser 2.00 Nos. per day -
8 Hammerman 1.00 No. per day -
9 Blacksmith for repairing tools etc. 1.00 No per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 21
DESCRIPTION OF ITEM:
Item No. 12 (a) Excavation in hard rock requiring blasting, and disposal of excavated
material (blasted material) upto 50 ft. (15 metre) lead (including dressing
and levelling to designed section etc. complete.
i) Grade-I
Total -
Contractor's Profit & Ove ##### Percent -
Total -
LABOUR
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 22
DESCRIPTION OF ITEM:
Item No. 12 (a) Excavation in hard rock requiring blasting, and disposal of excavated
material (blasted material) upto 50 ft. (15 metre) lead (including dressing
and levelling to designed section etc. complete.
ii) Grade-II
Total -
Contractor's Profit & Ove ##### Percent -
Total -
LABOUR
1 Quarrymen for boring hole and fixing etc. 4.00 Nos. per day -
2 Digging and breaking
large stone into small one 7.00 Nos. per day -
3 Chiselar for dressing 1.00 No. per day -
4 Bahishti 0.50 No. per day -
5 Black-smith for repairing tools etc. 0.50 Nos. per day -
6 Smithy cooly 0.50 No. per day -
7 Coolies unskilled for remaining spoil
upto 50 ft. (15 metre) lead 6.00 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 23
DESCRIPTION OF ITEM:
Item No. 12 (a) Excavation in hard rock requiring blasting, and disposal of excavated
material (blasted material) upto 50 ft. (15 metre) lead (including dressing
and levelling to designed section etc. complete.
iii) Grade-III
Total -
Contractor's Profit & Ove ##### Percent -
Total -
LABOUR
1 Quarrymen for boring hole and fixing etc. 5.00 Nos. per day -
2 Digging and breaking large stones
into small one. 8.50 Nos. per day -
3 Chiselar for dressing 1.50 No per day -
4 Bahishti 0.75 No. per day -
5 Blacksmith for repairing tools 0.75 No. per day -
6 Smithy cooly 0.75 No. per day -
7 Coolies un-skilled for removing spoil upto 50 ft.
(15 metre) 6.00 Nos. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 24
DESCRIPTION OF ITEM:
Item No. 11 (a) Excavation in hard rock requiring blasting, and disposal of excavated
material (blasted material) upto 50 ft. (15 metre) lead (including dressing
and levelling to designed section etc. complete.
iv) Grade-IV
Total -
Contractor's Profit & Ove ##### Percent -
Total -
LABOUR
1 Quarrymen for boring hole and fixing etc. 6.00 Nos. per day -
2 Digging and breaking large stones
into small one. 9.00 Nos. per day -
3 Chiselar for dressing 2.00 No per day -
4 Bahishti 0.75 No. per day -
5 Blacksmith for repairing tools 1.00 No. per day -
6 Smithy cooly 1.00 No. per day -
7 Coolies un-skilled for removing spoil upto 50 ft.
(15 metre) 6.00 Nos. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 25
DESCRIPTION OF ITEM:
Item No. 12 Excavation in hard rock requiring blasting, and disposal of excavated
material (blasted material) upto 50 ft. (15 metre) lead (including dressing
and levelling to designed section etc., complete.
v) Grade-V
Total -
Contractor's Profit & Ove ##### Percent -
Total -
LABOUR
1 Quarrymen for boring hole and fixing etc. 7.00 Nos. per day -
2 Digging and breaking large stones
into small one. 10.00 Nos. per day -
3 Chiselar for dressing 2.50 No per day -
4 Bahishti 1.00 No. per day -
5 Blacksmith for repairing tools 1.00 No. per day -
6 Smithy cooly 1.00 No. per day -
7 Coolies un-skilled for removing spoil upto 50 ft.
(15 metre) 6.00 Nos. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 26
DESCRIPTION OF ITEM:
Item No. 12 Excavation in hard rock requiring blasting, and disposal of excavated
material (blasted material) upto 50 ft. (15 metre) lead (including dressing
and levelling to designed section etc., complete.
vi) Grade-VI
Total -
Contractor's Profit & Ove ##### Percent -
Total -
LABOUR
1 Quarrymen for boring hole and fixing etc. 8.00 Nos. per day -
2 Digging and breaking large stones
into small one. 10.00 Nos. per day -
3 Chiselar for dressing 3.00 No per day -
4 Bahishti 1.00 No. per day -
5 Blacksmith for repairing tools 1.25 No. per day -
6 Smithy cooly 1.25 No. per day -
7 Coolies un-skilled for removing spoil upto 50 ft.
(15 metre) 6.00 Nos. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 27
DESCRIPTION OF ITEM:
Item No. 12 (b) Excavation in hard rock requiring blasting, but blasting prohibited, and
disposal of excavated material within 50 ft. (15 metre) lead (including
dressing and levelling to designed section etc., complete.
i) Grade-I
LABOUR
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 12 (b) Excavation in hard rock requiring blasting, but blasting prohibited, and
disposal of excavated material within 50 ft. (15 metre) lead (including
dressing and levelling to designed section etc., complete).
ii) Grade-II
LABOUR
ITEM RATES
Page 28
DESCRIPTION OF ITEM:
Item No. 12 (b) Excavation in hard rock requiring blasting, but blasting prohibited, and
disposal of excavated material within 50 ft. (15 metre) lead (including
dressing and levelling to designed section etc., complete.
iii) Grade-III
LABOUR
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 12 (b) Excavation in hard rock requiring blasting, but blasting prohibited, and
disposal of excavated material within 50 ft. (15 metre) lead (including
dressing and levelling to designed section etc., complete.
iv) Grade-IV
LABOUR
ITEM RATES
Page 29
DESCRIPTION OF ITEM:
Item No. 12 (b) Excavation in hard rock requiring blasting, but blasting prohibited, and
disposal of excavated material within 50 ft. (15 metre) lead (including
dressing and levelling to designed section etc., complete.
v) Grade-V
LABOUR
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 12 (b) Excavation in hard rock requiring blasting, but blasting prohibited, and
disposal of excavated material within 50 ft. (15 metre) lead (including
dressing and levelling to designed section etc., complete.
vi) Grade-VI
ITEM RATES
Page 30
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 31
DESCRIPTION OF ITEM:
Item No. 14 Rehandling of gravel work or excavated rock, lead upto 50 ft. (15 metre).
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 32
DESCRIPTION OF ITEM:
ii) With new earth excavated from outside, lead upto one chain (30 metre).
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 33
DESCRIPTION OF ITEM:
Item No. 16 Extra for every 50 ft. (15 metre) additional lead or part thereof.
(a) 28 men detailed as below Kharkar (owner) 1.00 No. per month -
Belcha men for excavation 8.00 Nos. per month -
Gantiman (with pick axes) 4.00 Nos. per month -
Topalies (men with donkeys for carrying earth) 10.00 Nos. per month -
Langri (Cooks) 2.00 Nos. per month -
Chowkidars 2.00 Nos. per month -
Dobashi (man for supervision) 1.00 No. per month -
Total -
Exenditure per day 0 0.00 -
30
(b) Jamadari commission for supplying labour on Rs.
0.00 @ 6% -
(c) Food etc as under
i) One seer Atta per man daily for 28 men 28.00 seer per kg -
26.12 kg
ii) Kitchen expenses (tea meat, milk,
fuel, fat & aplienees) L.S. -
iii) Lantern, Patromax lamp depreciation
and K. oil consumption L.S. -
iv) Kitchen Utensil, cost of repair and
replacement etc. L.S. -
Total: = a + b + c = 0.00 -
II - i)Donkeys
28 Nos. Donkeys worker 500 ft. lead in belcha
7 No. Donkey in each belcha
Average working life of one donkey 6 years
Average cost price of one donkey = 0.00
After depriceation cost of one donkey = 0.00
Amount per day 28 x 0 = 0.00
6 x 365 Say -
ii) Food etc as under for 28 donkeys
Phak, 5 seers (4.67 kg) per day per donkey
= 28 x 5 = 3.50 mds 3.50 mds per Md -
40
Grams, 2 seers (0.933 x 2) = 1.866 kg per donkey
Per day 28 x 2 = 1.40 mds 1.40 mds per Md -
40
Total-II -
iii) Material
Page 34
replacement etc. 2.00 Nos. each -
e) Sutli consumption 0.6 Kg. - P. Kg. -
Total - III -
Rate for 1000 Cft lead 50' as per item No. (10-i) SR
of this Chapter 0.00
Difference for lead 450ft 0.00 - 0.00 0.00
Rate for 50 ft. lead 0.00 0.00
9
Rate for every 50 ft. add lead or a part thereof
iii) Progress per belcha in hard soil 1150 Cft
Rate for 1000 Cft lead 500 ft.
0.00 x 1000 = 0.00
1150
Page 35
9
Rate for eveyr 50 ft. Add. lead or part thereof
(i) (iFor gravel, shingle or rock extra labour required This rate shall apply to
for 1000 Cft. The carriage of spoil from these lead upto mile when
formalities over and above that required for soil the lead is more than
is 20% mile lead shall be
paid as carriage of
material by
mechanical mean.
0.00 x 20 0.00 -
100.00
ITEM RATES
Page 36
DESCRIPTION OF ITEM:
Item No. 17 Transportation of earth all types when the total distance, including the l
covered in the item of work, is more than 1000 ft.
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 17 (b) For every 330 ft. additional lead or part-thereof, beyond mile upto one m
ITEM RATES
Page 37
DESCRIPTION OF ITEM:
Item No. 17 (c) For every mile additional lead or part thereof, beyond one mile upto 5 m
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 17 (d) For every mile additional lead or part thereof, beyond 5 miles.
ITEM RATES
Page 38
DESCRIPTION OF ITEM:
Item No. 18 Dressing and levelling of earth work to designed section etc., complete:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 18 Dressing and levelling of earth work to designed section etc., complete:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 39
DESCRIPTION OF ITEM:
Item No. 18 Dressing and levelling of earth work to designed section etc., complete:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 150 Rft -
Rate per 100 Rft
ITEM RATES
Page 40
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Sft -
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 20 (b) Dressing of earth work (done by Machinery or otherwise and left undressed)
to designed section.
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1600 Sft -
ITEM RATES
Page 41
DESCRIPTION OF ITEM:
1 Coolies un-skilled for digging & refilling 5.00 Nos. per day -
2 Coolies un-skilled for carrying earth 3.00 Nos. per day -
3 Dresser 1.00 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
b) In ordinary soil.
1 Coolies un-skilled for digging & refilling 6.00 Nos. per day -
2 Coolies un-skilled for carrying earth 3.00 Nos. per day -
3 Dresser 1.50 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 42
DESCRIPTION OF ITEM:
1 Coolies un-skilled for digging & refilling 7.00 Nos. per day -
2 Coolies un-skilled for carrying earth 3.00 Nos. per day -
3 Dresser 1.75 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 43
DESCRIPTION OF ITEM:
Item No. 22 Cutting hard rock such as granite, ballast hard line, stone or sand stone
with chisels and lammers for small foundations.
1 Steel 50 Lbs
22.69 kg kg -
2 Charcoal 500 Lbs
##### kg kg -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
LABOUR
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 44
DESCRIPTION OF ITEM:
LABOUR
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
ITEM RATES
Labour rate per 1000 Cft Rs. Say -
Labour rate per Cum Rs. Say -
Page 45
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 46
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 47
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
1 Coolies un-skilled for watering & ramming 2.00 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 48
DESCRIPTION OF ITEM:
Item No. 25 Compaction of earthwork with power road roller, including ploughing,
mixing, moistening earth to optimum moisture content in layers etc.
complete.
As per item No. 5 (i) of this chapter for machi 0.00 1000 Cft Cft -
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 25 Compaction of earthwork with power road roller, including ploughing,
mixing, moistening earth to optimum moisture content in layers etc.
complete.
As per item No. 5 (ii) of this chapter for mach 0.00 1000 Cft Cft -
ITEM RATES
Page 49
DESCRIPTION OF ITEM:
Item No. 25 Compaction of earthwork with power road roller, including ploughing,
mixing, moistening earth to optimum moisture content in layers etc.
complete.
As per item No. 5 (iii) of this chapter for mac 0.00 1000 Cft Cft -
ITEM RATES
DESCRIPTION OF ITEM:
1 Coolies un-skilled for digging, filling & lifting 3.50 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 50
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 51
DESCRIPTION OF ITEM:
Item No. 29 Earthwork on small rain water drains along canal banks roads and
plantion drains dressed etc., complete.
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate fore 125 Rft -
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 30 Filling and compacting soil earth and boulders behind retaining walls
(including excavation of soil and lead upto 50 ft. (15 metre).
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 52
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 32 Turfing slopes of banks or lawns with grass sods including ploughing
laying settling and watering (Turf got from within a distance of 5 miles
(8 kilometre) and maintenance for 15 days).
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 300 Sft -
ITEM RATES
Page 53
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
1 Coolies un-skilled for digging filling, dag-belling 4.00 Nos. per day -
2 Carrying 3.00 Nos. per day -
3 Dresser (for slopes and load) 1.00 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 54
DESCRIPTION OF ITEM:
1 Dresser's earthwork (for dag-belling & dressing) 2.00 Nos. per day -
2 Coolies un-skilled coolies (for trimming etc.) 12.00 Nos. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1.5 miles -
ITEM RATES
DESCRIPTION OF ITEM:
1 Dresser's earthwork (for dag-belling & dressing) 3.00 Nos. per day -
2 Coolies un-skilled 15.50 Nos. per day -
3 Mate earthwork for supervision 1.00 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1.5 Miles -
ITEM RATES
Page 55
DESCRIPTION OF ITEM:
1 Dresser's earthwork (for dag-belling & dressing) 4.00 Nos. per day -
2 Coolies un-skilled 25.50 Nos. per day -
3 Mate earthwork for supervision 1.00 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1.5 Miles -
ITEM RATES
DESCRIPTION OF ITEM:
LABOUR
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
ITEM RATES
Page 56
DESCRIPTION OF ITEM:
LABOUR
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 36 Making boundry or service roads including dag-belling, levelling & dressing
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1.5 Chain -
ITEM RATES
Page 57
DESCRIPTION OF ITEM:
Item No. 36 Making boundry or service roads including dag-belling, levelling & dressing
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1.5 Chains -
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 36 Making boundry or service roads including dag-belling, levelling & dressing
LABOUR
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
ITEM RATES
Page 58
DESCRIPTION OF ITEM:
Item No. 36 Making boundry or service roads including dag-belling, levelling & dressing
LABOUR
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
ITEM RATES
DESCRIPTION OF ITEM:
i) Digging and loading into boats upto 50 ft. (15 metre) lead.
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 59
DESCRIPTION OF ITEM:
ITEM RATES
DESCRIPTION OF ITEM:
iii) Extra for every additional one chain (30 metre) or part thereof beyond
10 chain (300 metre).
1 Extra boatman required for one chain (30 metre) 0.20 No. per day -
lead.
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate per 1250 Cft -
ITEM RATES
Page 60
DESCRIPTION OF ITEM:
Item No. 37 Earthwork by boats including hire of boats including hire of boats.
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 38 Unloading earth from B.G. Tracks and clearing 5 ft. (1.5 metre) from rail.
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total Rate for 1250 Cft -
ITEM RATES
Page 61
DESCRIPTION OF ITEM:
Item No. 39 Earthwork by train way, digging and loading in truck, upto 50 ft. (15 metr
lead.
1 Cooly un-skilled for digging and loading 7.00 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate for 1250 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 40 Unloading earth from B.G. trucks and spreading upto 15 ft. (4.5 metre) from
rail.
LABOUR
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
ITEM RATES
Page 62
DESCRIPTION OF ITEM:
Item No. 41 Supplying clean and screened river or pit sand within 5 chain (150 metre).
MATERIAL
LABOUR
-
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
TOTAL -
CARRIAGE
Ist Chain = -
2nd Chain = -
3rd Chain = -
4th Chain = - -
- -
ITEM RATES
Page 63
DESCRIPTION OF ITEM:
Item No. 42 Earth work excavation inopen cutting for sewers and manholes as shown in
drawing including shuttering and timbering, dressing to correct section an
dimension according to templates and levels and removing surface water, in
all types of soil except, shingle gravel and rock.
STRUTS
Ist class sawing charges 0.31 x 10 = 3.10 Sft 3.1 Sft Sft -
Total -
Contractor's Profit & Ove ##### Percent except sawing charges
i.e on Rs. 0.00 -
Total rate for 1750 Cft -
Total rate for 1000 Cft
1 For excavation coolies un-skilled for 1250 Cft 6.50 Nos. per day -
2 Dresser 1.00 No. per day -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate for 1250 Cft -
Labour rate for 1000 Cft -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate per 1250 Cft -
Labour rate per 1000 Cft
Page 64
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate for 1750 Cft -
Total rate for 1000 Cft
ITEM RATES
Page 65
DESCRIPTION OF ITEM:
Item No. 42 Earth work excavation in open cutting for sewers and manholes as shown in
drawing including shuttering and timbering, dressing to correct section an
dimension according to templates and levels and removing surface water, in
all types of soil except shingle, gravel and rock.
2 STRUTS 39 Nos.
Total -
Contractor's Profit & Ove ##### Percent 0.00 -
(except on sawing charges)
Total -
Cost per 1000 Cft 212.69 2 = 0.00 -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate for 2000 Cft -
Total rate for 1000 Cft
Page 66
(b) For Excavation 1250 Cft
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate for 1250 Cft -
Total rate for 1000 Cft -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
ITEM RATES
Page 67
DESCRIPTION OF ITEM:
Item No. 42 Earth work excavation in open cutting for sewers and manholes as shown in
drawing including shuttering and timbering, dressing to correct section an
dimension according to templates and levels and removing surface water, in
all types of soil except shingle gravel and rock.
STRUTS 39 Nos.
Total -
Contractor's Profit & Ove ##### Percent on 189.50 (Except sawing charges) -
Total rate for 2000 Cft -
Cost per 1000 Cft 212.69 2 = 0.00 -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate for 2000 Cft -
Total rate for 1000 Cft
Page 68
(b) For Excavation 1250 Cft
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate for 1250 Cft -
Total rate for 1000 Cft -
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total per 1000 Cft -
ITEM RATES
Page 69
DESCRIPTION OF ITEM:
Item No. 43 Earth work excavation of trenches in open cutting for Sewers and manhole
chambers etc. below sub soil water level to correct section and dimension
according to templates and levels, including shoring, timbering and
shuttering of M.S. Sheets on both sides of the trenches.
MATERIAL
Total -
Contractor's Profit & Ove ##### % Except sawing 0.00 -
Total -
Page 70
LABOUR for 1500 Cft
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate per 1500 Cft -
Total rate per 1000 Cft
ITEM RATES
Page 71
DESCRIPTION OF ITEM:
Item No. 43 Earth work excavation of trenches in open cutting for Sewers and manhole
chambers etc. below sub soil water level to correct section and dimension
according to templates and levels, including shoring, timbering and
shuttering of M.S. Sheets on both sides of the trenches.
(ii) 4 ft. to 8 ft. (1.2 metre to 2.4 metre) depth below SSWL
MATERIAL
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Page 72
LABOUR for 1500 Cft
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate per 1500 Cft -
Total rate per 1000 Cft
ITEM RATES
Page 73
DESCRIPTION OF ITEM:
Item No. 43 Earth work excavation of trenches in open cutting for Sewers and manhole
chambers etc. below sub soil water level to correct section and dimension
according to templates and levels, including shoring, timbering and
shuttering of M.S. Sheets on both sides of the trenches.
MATERIAL
Total -
Contractor's Profit & Ove ##### Percent -
Total Material cost -
Page 74
LABOUR for 1500 Cft
ITEM RATES
Page 75
DESCRIPTION OF ITEM:
Item No. 44 Excavation of trenches in all kind of soil except cutting rock, for water
pipe lines upto to 5 ft. (1.5 metre) depth from ground level including trim
dressing sides, leveling the beds of trenches to correct grade and cutting
pits for joints etc. complete in all respects.
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total rate per 1250 Cft -
Total rate per 1000 Cft -
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 45 Cutting and removing trees within a distance of 100 ft. (30 metre).
LABOUR
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
ITEM RATES
Page 76
DESCRIPTION OF ITEM:
Item No. 45 Cutting and removing trees within a distance of 100 ft. (30 metre).
(b) Above 2.5 ft. (0.75 metre) to 6 ft. (1.8 metre) grith.
LABOUR
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 46 Uprooting stump and removing with in 100 ft. (30 metre) from 2" to 6 ft.
(0.61 metre to 1.83 metre) grith.
LABOUR
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
ITEM RATES
Page 77
DESCRIPTION OF ITEM:
Item No. 47 Jungle clearance and removing within 100 ft. (30 metre).
(a) Light
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total for 1250 Sft -
ITEM RATES
DESCRIPTION OF ITEM:
Item No. 47 Jungle clearance and removing within 100 ft. (30 metre).
(b) Thick
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total for 1250 Sft -
ITEM RATES
Page 78
DESCRIPTION OF ITEM:
Item No. 48 Up rooting sarkanda growth and disposal within 100 ft. (30 metre).
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total for 125 Sft -
ITEM RATES
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
ITEM RATES
Page 79
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total for 150 Sft -
ITEM RATES
DESCRIPTION OF ITEM:
Total -
Sundries ##### Percent -
Total -
Contractor's Profit & Ove ##### Percent -
Total for 150 Sft -
ITEM RATES
Page 80
CHAPTER NO. 24
ELECTRIC INSTALLATION
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
boxes, inspection boxes, bends, tees, etc., complete with all spec
1 G.I. pipe " dia (15 mm i/d) 7.00 metre per mtr.
2 Clamp " dia (15 mm i/d) 10.00 Nos. each
3 G.I bend " dia (15 mm i/d) 1.00 No. each
4 Gutties 20.00 Nos. dozen
5 Screw 1" to " (25 to 20 mm) 1.50 Dozen dozen
6 Inspection box " dia (15 mm) 1.00 No. each
7 Cement 0.021 Cft. P. Bag
8 Sand 0.08 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 479.84 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Labour rate per Metre Rs. Say
Labour rate per Rft Rs. Say
Composite rate per Metre Rs. Say
Composite rate per Rft Rs. Say
Page 1
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. pipe " dia (20 mm i/d) 7.00 metre per mtr.
2 G.I bend " dia (20 mm i/d) 1.00 No. each
3 Clamp " dia (20 mm i/d) 10.00 Nos. each
4 Gutties 20.00 Nos. dozen
5 Screw 1" to " (25 to 20 mm) 1.50 Dozen dozen
6 Inspection box " dia (20 mm) 1.00 No. each
7 Cement 0.021 Cft. P. Bag
8 Sand 0.08 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 626.14 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 2
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. pipe 1" dia (25 mm i/d) 7.00 metre per mtr.
2 G.I bend 1" dia (25 mm i/d) 1.00 No. each
3 Clamp 1" dia (25 mm i/d) 10.00 Nos. each
4 Gutties 20.00 Nos. dozen
5 Screw " to 1" (25 to 20 mm) 1.50 Dozen dozen
6 Inspection box 1" dia (25 mm) 1.00 No. each
7 Cement 0.021 Cft. P. Bag
8 Sand 0.08 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 897.63 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 3
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. pipe 1" dia (32 mm i/d) 7.00 metre per mtr.
2 Clamp 1" dia (32 mm i/d) 10.00 Nos. each
3 G.I bend 1" dia (32 mm i/d) 1.00 No. each
4 M.S. Inspection box 1" dia (32 mm) 1.00 No. each
5 Gutties 20.00 Nos. dozen
6 Screw " to 1" (25 to 20 mm) 1.50 Dozen dozen
7 Cement 0.021 Cft. P. Bag
8 Sand 0.08 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1126.33 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 4
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. pipe 1" dia (40 mm i/d) 7.00 metre per mtr.
2 G.I bend 1" dia (40 mm i/d) 1.00 Nos. each
3 M.S. Inspection box 1" dia (40 mm) 1.00 No. each
4 G.I. Clamp 1" dia (40 mm i/d) 10.00 Nos. each
5 Gutties 20.00 Nos. dozen
6 Screw 1 to " (25 to 20 mm) 1.50 Dozen dozen
7 Cement 0.021 Cft. P. Bag
8 Sand 0.08 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1330.43 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 5
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. pipe 2" dia (50 mm i/d) 7.00 metre per mtr.
2 G.I bend 2" dia (50 mm i/d) 1.00 No. each
3 M.S. Inspection box 2" dia (50 mm) 1.00 No. each
4 G.I. Clamp 2" dia (50 mm i/d) 10.00 Nos. each
5 Gutties 20.00 Nos. dozen
6 Screw 1 to " (25 to 20 mm) 1.50 Dozen dozen
7 Cement 0.021 Cft. P. Bag
8 Sand 0.08 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1758.85 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 6
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. pipe 3" dia (80 mm i/d) 7.00 metre per mtr.
2 G.I. Clamp 3" dia (80 mm i/d) 10.00 Nos. each
3 M.S. Inspection box 3" dia (80 mm) 1.00 No. each
4 G.I bend 3" dia (80 mm i/d) 1.00 No. each
5 Gutties 20.00 Nos. dozen
6 Screw 1 to " (25 to 20 mm) 1.50 Dozen dozen
7 Cement 0.021 Cft. P. Bag
8 Sand 0.08 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 2949.77 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 7
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. Pipe " dia (15 mm i/d) 7.00 metre per mtr.
2 G.I. Bend " dia (15 mm i/d) 1.00 Nos. each
3 Hooks 8.00 No. each
4 M.S. Inspection box " dia (15 mm) 1.00 Nos. each
5 Cement 0.021 Cft. P. Bag
6 Sand 0.08 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 442.55 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 8
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. Pipe " dia (20 mm i/d) 7.00 metre per mtr.
2 G.I. Bend " dia (20 mm i/d) 1.00 Nos. each
3 Hooks 7.00 No. each
4 M.S. Inspection box " dia (20 mm) 1.00 Nos. each
5 Cement 0.021 Cft. P. Bag
6 Sand 0.18 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 564.44 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 9
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. Pipe 1" dia (25 mm i/d) 7.00 metre per mtr.
2 G.I. Bend 1" dia (25 mm i/d) 1.00 Nos. each
3 Hooks 8.00 No. each
4 M.S. Inspection box 1" dia (25 mm) 1.00 Nos. each
5 Cement 0.052 Cft. P. Bag
6 Sand 0.18 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 820.19 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 10
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. Pipe 1" dia (32 mm i/d) 7.00 metre per mtr.
2 G.I. Bend 1" dia (32 mm i/d) 1.00 Nos. each
3 Hooks 8.00 No. each
4 M.S. Inspection box 1" dia (32 mm) 1.00 Nos. each
5 Cement 0.063 Cft. P. Bag
6 Sand 0.18 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1046.69 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 11
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. Pipe 1" dia (40 mm i/d) 7.00 metre per mtr.
2 G.I. Bend 1" dia (40 mm i/d) 1.00 Nos. each
3 M.S. Inspection box 1" dia (40 mm i/d) 1.00 No. each
4 Hooks 8.00 Nos. each
5 Cement 0.074 Cft. P. Bag
6 Sand 0.20 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1252.99 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 12
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. Pipe 2" dia (50 mm i/d) 7.00 metre per mtr.
2 G.I. Bend 2" dia (50 mm i/d) 1.00 Nos. each
3 M.S. Inspection box 2" dia (50 mm i/d) 1.00 No. each
4 Hooks 8.00 Nos. each
5 Cement 0.084 Cft. P. Bag
6 Sand 0.24 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1679.21 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 13
DESCRIPTION OF ITEM:
Item No. 1 Supply and erection of G.I pipes for wiring purposes including pul
inspection boxes, bends, tees, etc., complete with all specials.
1 G.I. Pipe 3" dia (80 mm i/d) 7.00 metre per mtr.
2 G.I. Bend 3" dia (80 mm i/d) 1.00 No. each
3 M.S. Inspection box 3" dia (80 mm) 1.00 No. each
4 Hooks 8.00 Nos. each
5 G.I. Socket 3" dia (80 mm) 1.00 No. each
6 Cement 0.08 Cft. P. Bag
7 Sand 0.24 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 2871.23 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 14
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe " dia (16 mm) 7.00 metre per mtr.
2 M.S. Bend " dia (16 mm) 1.00 No. each
3 M.S. Inspection box " dia (16 mm) 1.00 No. dozen
4 Clamps " dia (16 mm) 10.00 Nos. each
5 Screw 1.20 Dozen dozen
6 Gutties 1.00 Dozen dozen
Total
Contractor's Profit & O ## Percent
Total
Material per metre 251.69 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 15
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe " dia (20 mm) 7.00 metre per mtr.
2 M.S. Bend " dia (20 mm) 1.00 No. each
3 M.S. Inspection box " dia (20 mm) 1.00 No. per doz.
4 M.S. Clamps " dia (20 mm) 10.00 Nos. each
5 Screw 1.20 Dozen dozen
6 Gutties 1.00 Dozen dozen
7 Cement 0.02 Cft. P. Bag
8 Sand 0.06 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 325.92 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 16
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe 1" dia (25 mm) 7.00 metre per mtr.
2 M.S. Bend 1" dia (25 mm) 1.00 No. each
3 M.S. Inspection box 1" dia (25 mm) 1.00 No. per doz.
4 M.S. Clamps 1" dia (25 mm) 10.00 Nos. each
5 Screw 1.20 Dozen dozen
6 Gutties 1.00 Dozen dozen
7 Cement 0.042 Cft. P. Bag
8 Sand 0.12 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 334.40 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 17
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe 1" dia (32 mm) 7.00 metre per mtr.
2 M.S. Conduit Bend 1" dia (32 mm) 1.00 No. each
3 M.S. Inspection box 1" dia (32 mm) 1.00 No. per doz.
4 M.S. Clamps 1" dia (32 mm) 10.00 Nos. each
5 Screw 1.20 Dozen dozen
6 Gutties 1.00 Dozen dozen
7 Cement 0.042 Cft. P. Bag
8 Sand 0.12 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 572.62 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 18
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe 1" dia (40 mm) 7.00 metre per mtr.
2 M.S. Bend 1" dia (40 mm) 1.00 No. each
3 M.S. Inspection box 1" dia (40 mm) 1.00 No. per doz.
4 M.S. Clamps 1" dia (40 mm) 10.00 Nos. each
5 Screw 1.20 Dozen dozen
6 Gutties 1.00 Dozen dozen
7 Cement 0.042 Cft. P. Bag
8 Sand 0.12 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 652.76 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 19
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe 2" dia (50 mm) 7.00 metre per mtr.
2 M.S. Conduit Bend 2" dia (50 mm) 1.00 No. each
3 M.S. Inspection box 2" dia (50 mm) 1.00 No. per doz.
4 M.S. Clamps 2" dia (50 mm) 10.00 Nos. each
5 Screw 1.20 Dozen dozen
6 Gutties 1.00 Dozen dozen
7 Cement 0.042 Cft. P. Bag
8 Sand 0.12 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 822.43 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 20
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe " dia (16 mm) 7.00 metre per mtr.
2 M.S. Bend " dia (16 mm) 1.00 No. each
3 M.S. Inspection box " dia (16 mm) 1.00 No. per doz.
4 M.S. Hooks 10.00 Nos. each
5 Cement 0.021 Cft. P. Bag
6 Sand 0.08 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 247.29 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 21
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Condict pipe " dia (20 mm) 7.00 metre per mtr.
2 M.S. Bend " dia (20 mm) 1.00 No. each
3 M.S. Inspection box " dia (20 mm) 1.00 No. per doz.
4 M.S. Hooks 10.00 Nos. each
5 Cement 0.042 Cft. P. Bag
6 Sand 0.12 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 310.12 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 22
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe 1" dia (25 mm) 7.00 metre per mtr.
2 M.S. Bend 1" dia (25 mm) 1.00 No. each
3 M.S. Inspection box 1" dia (25 mm) 1.00 No. per doz.
4 Hooks 10.00 Nos. each
5 Cement 0.052 Cft. P. Bag
6 Sand 0.18 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 385.81 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 23
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe 1" dia (32 mm) 7.00 metre per mtr.
2 M.S. Conduit Bend 1" dia (32 mm) 1.00 No. each
3 M.S. Inspection box 1" dia (32 mm) 1.00 No. per doz.
4 M.S. Hooks 10.00 Nos. each
5 Cement 0.063 Cft. P. Bag
6 Sand 0.18 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 524.22 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 24
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe 1" dia (40 mm) 7.00 metre per mtr.
2 M.S. Conduit Bend 1" dia (40 mm) 1.00 No. each
3 M.S. Inspection box 1" dia (40 mm) 1.00 No. per doz.
4 M.S. Hooks 10.00 Nos. each
5 Cement 0.074 Cft. P. Bag
6 Sand 0.20 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 606.56 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 25
DESCRIPTION OF ITEM:
Item No. 2 Supply and erection of M.S conduit pipes for wiring, including ins
boxes, pull boxes, bends, tees, etc., complete with all specials.
1 M.S. Conduit pipe 2" dia (50 mm) 7.00 metre per mtr.
2 M.S. Conduit Bend 2" dia (50 mm) 1.00 No. each
3 M.S. Inspection box 2" dia (50 mm) 1.00 No. per doz.
4 Hooks 10.00 Nos. each
5 Cement 0.084 Cft. P. Bag
6 Sand 0.24 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 778.43 7 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 26
DESCRIPTION OF ITEM:
Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in
including inspection boxes, pull boxes, hooks, cutting, jharriers
repairing surface etc., complete with all specials.
1 PVC pipe " dia (12 mm) 10.00 metre per mtr.
2 PVC Bend " dia (12 mm) 2.00 No. each
3 M.S. Hook 10.00 No. each
4 PVC Inspection box " (12 mm) 2.00 Nos. per doz.
5 Cement 0.042 Cft. P. Bag
6 Sand 0.12 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 129.43 1 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 27
DESCRIPTION OF ITEM:
Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in
including inspection boxes, pull boxes, hooks, cutting, jharriers
repairing surface etc., complete with all specials.
1 PVC pipe " dia (20 mm) 10.00 metre per mtr.
2 PVC Bend " dia (20 mm) 2.00 No. each
3 M.S. Hook 10.00 No. each
4 PVC Inspection box " dia (20 mm) 2.00 Nos. per doz.
5 Cement 0.052 Cft. P. Bag
6 Sand 0.18 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 163.53 1 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 28
DESCRIPTION OF ITEM:
Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in
including inspection boxes, pull boxes, hooks, cutting, jharriers
repairing surface etc., complete with all specials.
1 PVC pipe 1" dia (25 mm) 10.00 metre per mtr.
2 PVC Bend 1" dia (25 mm) 2.00 No. each
3 M.S. Hook 10.00 No. each
4 PVC Inspection box 1" dia (25 mm) 2.00 Nos. per doz.
5 Cement 0.063 Cft. P. Bag
6 Sand 0.18 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 235.03 1 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 29
DESCRIPTION OF ITEM:
Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in
including inspection boxes, pull boxes, hooks, cutting, jharriers
repairing surface etc., complete with all specials.
1 PVC pipe 1" dia (30 mm) 10.00 metre per mtr.
2 PVC Bend 1" dia (30 mm) 2.00 No. each
3 M.S. Hook 10.00 No. each
4 PVC Inspection box 1" dia (30 mm) 2.00 Nos. per doz.
5 Cement 0.065 Cft. P. Bag
6 Sand 0.37 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 228.053 1 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 30
DESCRIPTION OF ITEM:
Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in
including inspection boxes, pull boxes, hooks, cutting, jharriers
repairing surface etc., complete with all specials.
1 PVC pipe 1" dia (40 mm) 10.00 metre per mtr.
2 PVC Bend 1" dia (40 mm) 2.00 No. each
3 M.S. Hook 10.00 No. each
4 PVC Inspection box 1" dia (40 mm) 2.00 Nos. per doz.
5 Cement 0.070 Cft. P. Bag
6 Sand 0.40 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 454.67 1 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 31
DESCRIPTION OF ITEM:
Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in
including inspection boxes, pull boxes, hooks, cutting, jharriers
repairing surface etc., complete with all specials.
1 PVC pipe 2" dia (50 mm) 10.00 metre per mtr.
2 PVC Bend 2" dia (50 mm) 2.00 No. each
3 M.S. Hook 10.00 No. each
4 Cement 0.084 Cft. P. Bag
5 Sand 0.24 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 625.35 1 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 32
DESCRIPTION OF ITEM:
Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including
inspection boxes, pull boxes bends, tees repairing surface etc.,
with all specials.
1 PVC pipe " dia (12 mm) 10.00 metre per mtr.
2 PVC Bend " dia (12 mm) 2.00 Nos. each
3 M.S. Clamp/saddle 20.00 Nos. each
4 Gutties 20.00 Nos. each
5 Screws for " dia clamp 20.00 Nos. per doz.
6 PVC Inspection Box " dia (12 mm) 2.00 Nos. per doz.
7 Cement 0.021 Cft. P. Bag
8 Sand 0.06 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 176.37 1 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 33
DESCRIPTION OF ITEM:
Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including
inspection boxes, pull boxes bends, tees repairing surface etc.,
with all specials.
1 PVC pipe " dia (20 mm) 10.00 metre per mtr.
2 PVC Bend " dia (20 mm) 2.00 Nos. each
3 M.S. Clamp " dia (20 mm) 10.00 Nos. each
4 Screws for " dia clamp 20.00 Nos. per doz.
5 PVC Inspection Box " dia (20 mm) 2.00 Nos. per doz.
6 Cement 0.021 Cft. P. Bag
7 Sand 0.06 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 186.27 1 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 34
DESCRIPTION OF ITEM:
Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including
inspection boxes, pull boxes bends, tees repairing surface etc.,
with all specials.
1 PVC pipe 1" dia (25 mm) 10.00 metre per mtr.
2 PVC Bend 1" dia (25 mm) 2.00 Nos. each
3 M.S. Clamp/saddle 1 dia (25 mm) 20.00 Nos. each
4 Screws for 1" dia clamp 20.00 Nos. per doz.
5 Gutties 20.00 Nos. per doz.
6 PVC Inspection Box 1" dia (25 mm) 2.00 Nos. per doz.
7 Cement 0.021 Cft. P. Bag
8 Sand 0.06 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 347.23 1 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 35
DESCRIPTION OF ITEM:
Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including
inspection boxes, pull boxes bends, tees repairing surface etc.,
with all specials.
1 PVC pipe 1" dia (30 mm) 10.00 metre per mtr.
2 PVC Bend 1" dia (30 mm) 2.00 Nos. each
3 M.S. Clamp/saddle 1" dia (30 mm) 20.00 Nos. each
4 Gutties 20.00 Nos. per doz.
5 Screws for 1" dia clamp 20.00 Nos. per doz.
6 PVC Inspection Box 1" dia (30 mm) 2.00 Nos. per doz.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 484.73 1 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 36
DESCRIPTION OF ITEM:
Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including
inspection boxes, pull boxes bends, tees repairing surface etc.,
with all specials.
1 PVC pipe 1" dia (40 mm) 10.00 metre per mtr.
2 PVC Bend 1" dia (40 mm) 2.00 Nos. each
3 M.S. Clamp/saddle 1" dia (40 mm) 20.00 Nos. each
4 Gutties 20.00 Nos. per doz.
5 Screws for 1" dia clamp 20.00 Nos. per doz.
6 PVC Inspection Box 1" dia (40 mm) 2.00 Nos. per doz.
7 Cement 0.021 Cft. P. Bag
8 Sand 0.06 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 619.67 1 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 37
DESCRIPTION OF ITEM:
Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including
inspection boxes, pull boxes bends, tees repairing surface etc.,
with all specials.
1 PVC pipe 2" dia (50 mm) 10.00 metre per mtr.
2 PVC Bend 2" dia (50 mm) 2.00 Nos. each
3 M.S. Clamp/saddle 2" dia (50 mm) 20.00 Nos. each
4 Gutties 20.00 Nos. per doz.
5 Screws for 2" dia clamp 20.00 Nos. per doz.
6 PVC Inspection Box 2" dia (50 mm) 2.00 Nos. per doz.
7 Cement 0.021 Cft. P. Bag
8 Sand 0.06 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 860.02 1 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 38
DESCRIPTION OF ITEM:
Item No. 5 Supply and erection of G.I Flexible pipe for wiring including weld
sockets, nipples and check nuts etc complete.
MATERIAL
1 G.I. Flexible Pipe " dia (12 mm) 1.00 metre per mtr.
2 Socket " dia (12 mm) 2.00 Nos. each
3 Nipple " dia (12 mm) 2.00 Nos. each
4 Check Nuts " dia (12 mm) 2.00 Nos. each
5 Soldering etc. L.S
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 39
DESCRIPTION OF ITEM:
Item No. 5 Supply and erection of G.I Flexible pipe for wiring including weld
sockets, nipples and check nuts etc complete.
MATERIAL
1 G.I. Flexible Pipe " dia (20 mm) 1.00 metre per mtr.
2 G.I. Socket " dia (20 mm) 2.00 Nos. each
3 G.I. Nipple " dia (20 mm) 2.00 Nos. each
4 Check Nuts " dia (20 mm) 2.00 Nos. each
5 Solder joint L.S
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 40
DESCRIPTION OF ITEM:
Item No. 5 Supply and erection of G.I Flexible pipe for wiring including weld
sockets, nipples and check nuts etc complete.
MATERIAL
1 G.I. Flexible Pipe 1" dia (25 mm) 1.00 metre per mtr.
2 G.I. Socket 1" dia (25 mm) 2.00 Nos. each
3 G.I. Nipple 1" dia (25 mm) 2.00 Nos. each
4 Check Nuts 1" dia (25 mm) 2.00 Nos. each
5 Solder L.S
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 41
DESCRIPTION OF ITEM:
Item No. 5 Supply and erection of G.I Flexible pipe for wiring including weld
sockets, nipples and check nuts etc complete.
MATERIAL
1 G.I. Flexible Pipe 1" dia (32 mm) 1.00 metre per mtr.
2 G.I. Socket 1" dia (32 mm) 2.00 Nos. each
3 G.I. Nipple 1" dia (32 mm) 2.00 Nos. each
4 Check Nuts 1" dia (32 mm) 2.00 Nos. each
5 Solder L.S
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 42
DESCRIPTION OF ITEM:
Item No. 5 Supply and erection of G.I Flexible pipe for wiring including weld
sockets, nipples and check nuts etc complete.
MATERIAL
1 G.I. Flexible Pipe 1" dia (40 mm) 1.00 metre per mtr.
2 G.I. Socket 1" dia (40 mm) 2.00 Nos. each
3 G.I. Nipple 1" dia (40 mm) 2.00 Nos. each
4 Check Nuts 1" dia (40 mm) 2.00 Nos. each
5 Solder L.S
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 43
DESCRIPTION OF ITEM:
Item No. 5 Supply and erection of G.I Flexible pipe for wiring including weld
sockets, nipples and check nuts etc complete.
MATERIAL
1 G.I. Flexible Pipe 2" dia (50 mm) 1.00 metre per mtr.
2 G.I. Socket 2" dia (50 mm) 2.00 Nos. each
3 G.I. Nipple 2" dia (50 mm) 2.00 Nos. each
4 Check Nuts 2" dia (50 mm) 2.00 Nos. each
5 Solder L.S
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 44
DESCRIPTION OF ITEM:
Item No. 5 Supply and erection of G.I Flexible pipe for wiring including weld
sockets, nipples and check nuts etc complete.
MATERIAL
1 G.I. Flexible Pipe 3" dia (80 mm) 1.00 metre per mtr.
2 G.I. Socket 3" dia (80 mm) 2.00 Nos. each
3 G.I. Nipple 3" dia (80 mm) 2.00 Nos. each
4 Check Nuts 3" dia (80 mm) 2.00 Nos. each
5 Solder L.S
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 45
DESCRIPTION OF ITEM:
Item No. 6 Supply and erection of PVC pipe for recessed wiring (main and sub-
purposes including bends special etc., in floor, wall or trenches
1 PVC Pipe 2" dia (50 mm) 10.00 metre per mtr.
2 PVC Bend 2" dia (50 mm) 2.00 Nos. each
3 M.S Hooks 10.00 Nos. each
4 PVC Inspection box 2.00 Nos. per doz.
5 Cement 0.084 Cft. P. Bag
6 Sand 0.24 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 631.22 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 46
DESCRIPTION OF ITEM:
Item No. 6 Supply and erection of PVC pipe for recessed wiring (main and sub-
purposes including bends special etc., in floor, wall or trenches
1 PVC Pipe 3" dia (75 mm) 10.00 metre per mtr.
2 PVC Bend 3" dia (75 mm) 2.00 Nos. each
3 PVC Inspection box 2.00 Nos. per doz.
4 Cement 0.106 Cft. P. Bag
5 Sand 0.25 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 818.58 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 47
DESCRIPTION OF ITEM:
Item No. 6 Supply and erection of PVC pipe for recessed wiring (main and sub-
purposes including bends special etc., in floor, wall or trenches
1 PVC Pipe 4" dia (100 mm) 10.00 metre per mtr.
2 PVC Bend 4" dia (100 mm) 2.00 Nos. each
3 PVC Inspection box 2.00 Nos. per doz.
4 Cement 0.106 Cft. P. Bag
5 Sand 0.25 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1141.80 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 48
DESCRIPTION OF ITEM:
Item No. 7 Supply and erection of PVC pipe for on surface wiring (main and su
including clamps bends etc., complete with all specials.
1 PVC Pipe 2" dia (50 mm) 10.00 metre per mtr.
2 PVC Bend 2" dia (50 mm) 2.00 Nos. each
3 M.S Clamp 20.00 Nos. each
4 PVC Inspection boxes 2.00 Nos. per doz.
5 Gutties 20.00 Nos. per doz.
6 Cement 0.021 Cft. P. Bag
7 Sand 0.06 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 802.27 1 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 49
DESCRIPTION OF ITEM:
Item No. 7 Supply and erection of PVC pipe for on surface wiring (main and su
including clamps bends etc., complete with all specials.
1 PVC Pipe 3" dia (75 mm) 10.00 metre per mtr.
2 PVC Bend 3" dia (75 mm) 2.00 Nos. each
3 M.S Clamp 20.00 Nos. each
4 PVC Inspection boxes 2.00 Nos. per doz.
5 Screws for 3" dia clamp 40.00 Nos. per doz.
6 Gutties 40.00 Nos. per doz.
7 Cement 0.042 Cft. P. Bag
8 Sand 0.12 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1155.92 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 50
DESCRIPTION OF ITEM:
Item No. 7 Supply and erection of PVC pipe for on surface wiring (main and su
including clamps bends etc., complete with all specials.
1 PVC Pipe 4" dia (100 mm) 10.00 metre per mtr.
2 PVC Bend 4" dia (100 mm) 2.00 Nos. each
3 M.S Clamp 20.00 Nos. each
4 Gutties 40.00 Nos. per doz.
5 Screws for 4" dia clamp 40.00 Nos. per doz.
6 PVC Inspection boxes 2.00 Nos. per doz.
7 Cement 0.084 Cft. P. Bag
8 Sand 0.24 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1533.77 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 51
DESCRIPTION OF ITEM:
Item No. 8 Supply and erection of wooden strip batten for wiring purposes inc
insulation cleats etc.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 491.70 1 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 52
DESCRIPTION OF ITEM:
Item No. 9 Supply and erection of sahl wood casing and capping for wiring pur
including insulation cleats, screws etc., complete.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 2662.00 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 53
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 439.49 9 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 54
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 636.29 9 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 55
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 908.55 9 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 56
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1150.22 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 57
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1640.70 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 58
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 4371.45 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 59
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 5759.90 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 60
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 13464.0 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 61
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).
(b) 250/440 volts. PVC insulated cotton braided and compounded cables.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 509.85 9 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 62
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).
(b) 250/440 volts. PVC insulated cotton braided and compounded cables.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 611.82 9 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 63
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).
(b) 250/440 volts. PVC insulated cotton braided and compounded cables.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 815.76 9 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 64
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).
(b) 250/440 volts. PVC insulated cotton braided and compounded cables.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 968.72 9 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 65
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).
(b) 250/440 volts. PVC insulated cotton braided and compounded cables.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1529.55 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 66
DESCRIPTION OF ITEM:
Item No. 10 Supply and erection of single core PVC insulated copper conductor
in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/woode
casing and capping/G.I wire/trenches (rate for cable only).
(b) 250/440 volts. PVC insulated cotton braided and compounded cables.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 4078.80 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 67
DESCRIPTION OF ITEM:
Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copp
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pi
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 505.77 9 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 68
DESCRIPTION OF ITEM:
Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copp
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pi
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 740.30 9 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 69
DESCRIPTION OF ITEM:
Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copp
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pi
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1008.48 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 70
DESCRIPTION OF ITEM:
Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copp
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pi
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1517.31 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 71
DESCRIPTION OF ITEM:
Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copp
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pi
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 2143.41 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 72
DESCRIPTION OF ITEM:
Item No. 11 Supply and erection at single core PVC insulated PVC sheathed copp
conductor, 250/440 volts grade cable. (BSS-2004) in prelaid PVC pi
conduit/G.I pipe/wooden strip batten/wooden casing and
capping/trenches etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 4443.85 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 73
DESCRIPTION OF ITEM:
Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed cop
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S con
pipe/G.I wire/trenches etc., (rate per cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 4329.01 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 74
DESCRIPTION OF ITEM:
Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed cop
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S con
pipe/G.I wire/trenches etc., (rate per cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 5759.90 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 75
DESCRIPTION OF ITEM:
Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed cop
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S con
pipe/G.I wire/trenches etc., (rate per cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 7847.16 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 76
DESCRIPTION OF ITEM:
Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed cop
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S con
pipe/G.I wire/trenches etc., (rate per cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 12207.59 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 77
DESCRIPTION OF ITEM:
Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed cop
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S con
pipe/G.I wire/trenches etc., (rate per cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 21264.40 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 78
DESCRIPTION OF ITEM:
Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed cop
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S con
pipe/G.I wire/trenches etc., (rate per cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 26390.11 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 79
DESCRIPTION OF ITEM:
Item No. 12 Supply and erection of single core PVC insulated, PVC sheathed cop
conductor, 660/1100 volts grade cable, in prelaid G.I pipe/M.S con
pipe/G.I wire/trenches etc., (rate per cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre 40719.18 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 80
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 81
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 82
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 83
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 84
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 85
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 86
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 87
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 88
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 89
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 90
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 91
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 92
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cabl
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 93
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cabl
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 94
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cabl
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 95
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cabl
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 96
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cabl
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 97
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cabl
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 98
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(c) PVC insulated, PVC sheathed 4 core, 660/1100 volt non-armored cabl
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 99
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
wire 16 SWG.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 11164.35 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 100
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
wire 16 SWG.
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 101
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
G.I wire 16 SWG.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 21288.60 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 102
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
G.I wire 16 SWG.
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 103
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
wire 16 SWG.
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 104
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
wire 16 SWG.
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 105
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
wire 16 SWG.
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 106
DESCRIPTION OF ITEM:
Item No. 13 Supply and erection of copper conductor cables for service connect
prelaid pipe/G.I wire/trenches, etc., (rate for cable only).
(d) PVC insulated, PVC sheathed, 660/1100 volts grade cable, armoured
wire 16 SWG.
Total
Contractor's Profit & O ## Percent
Total
Material per metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 107
DESCRIPTION OF ITEM:
Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm)
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring
making holes for regulators, switches, plugs, etc.
MATERIAL
1 M.S Box 4" x 4" (100 x 100 mm) 1.00 No. each
2 Cement 0.021 Cft. P. Bag
3 Sand 0.08 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 108
DESCRIPTION OF ITEM:
Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm)
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring
making holes for regulators, switches, plugs, etc.
MATERIAL
1 M.S Box 7" x 4" (175 x 100 mm) 1.00 No. each
2 Cement 0.026 Cft. P. Bag
3 Sand 0.09 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 109
DESCRIPTION OF ITEM:
Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm)
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring
making holes for regulators, switches, plugs, etc.
MATERIAL
1 M.S Box 9" x 4" (225 x 100 mm) 1.00 No. each
2 Cement 0.032 Cft. P. Bag
3 Sand 0.08 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 110
DESCRIPTION OF ITEM:
Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm)
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring
making holes for regulators, switches, plugs, etc.
MATERIAL
1 M.S Box 8" x 10" (200 x 250 mm) 1.00 No. each
2 Cement 0.036 Cft. P. Bag
3 Sand 0.150 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 111
Labour rate for Each Rs. Say
Composite rate for Each Rs. Say
DESCRIPTION OF ITEM:
Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm)
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring
making holes for regulators, switches, plugs, etc.
MATERIAL
1 M.S Box 10" x 12" (250 x 300 mm) 1.00 No. each
2 Cement 0.047 Cft. P. Bag
3 Sand 0.155 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 112
DESCRIPTION OF ITEM:
Item No. 14 Supply and erection of M.S sheet box of 16 SWG, 10 cm 4" (100 mm)
4.75 mm thick 3/16" (6 mm) bakelite sheet top, for recessed wiring
making holes for regulators, switches, plugs, etc.
MATERIAL
1 M.S Box 12" x 14" (300 x 350 mm) 1.00 No. each
2 Cement 0.052 Cft. P. Bag
3 Sand 0.180 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 113
DESCRIPTION OF ITEM:
Item No. 15 Supply and erectionof round block of Sahl wood, 10 x 4 cm 4" x 1"
(100 x 40 mm).
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 114
DESCRIPTION OF ITEM:
Item No. 16 Supply and erection of teak wood board, 4.5 cm 1" (45 mm) thick.
MATERIAL
1 Teak Wood Board 7" x 4" (175 x 100 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 115
DESCRIPTION OF ITEM:
Item No. 16 Supply and erection of teak wood board, 4.5 cm 1" (45 mm) thick.
MATERIAL
1 Teak Wood Board 9" x 4" (225 x 100 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 116
DESCRIPTION OF ITEM:
Item No. 16 Supply and erection of teak wood board, 4.5 cm 1" (45 mm) thick.
MATERIAL
1 Teak Wood Board 8" x 10" (200 x 250 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 117
DESCRIPTION OF ITEM:
Item No. 16 Supply and erection of teak wood board, 4.5 cm 1" (45 mm) thick.
MATERIAL
1 Teak Wood Wooden Board 10" x 12" (250 x 300 mm) 1.00 No. each
2 W. Gutti 4.00 Nos. per dozen
3 Screw 4.00 Nos. per dozen
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 118
DESCRIPTION OF ITEM:
Item No. 16 Supply and erection of teak wood board, 4.5 cm 1" (45 mm) thick.
MATERIAL
1 Teak Wood Board 12" x 14" (300 x 350 mm) 1.00 No. each
2 W. Gutti 4.00 Nos. per dozen
3 Screw 4.00 Nos. per dozen
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 119
DESCRIPTION OF ITEM:
Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1" (45 mm) thick.
MATERIAL
1 Sahl Wood Board 7" x 4" (175 x 100 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 120
DESCRIPTION OF ITEM:
Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1" (45 mm) thick.
MATERIAL
1 Sahl Wood Board 9" x 4" (225 x 100 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 121
DESCRIPTION OF ITEM:
Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1" (45 mm) thick.
MATERIAL
1 Sahl Wood Board 8" x 10" (200 x 250 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 122
DESCRIPTION OF ITEM:
Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1" (45 mm) thick.
MATERIAL
1 Sahl Wood Board 10" x 12" (250 x 300 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 123
DESCRIPTION OF ITEM:
Item No. 17 Supply and erection of Sahl wood board 4.5 cm 1" (45 mm) thick.
MATERIAL
1 Sahl Wood Board 12" x 14" (300 x 350 mm) 1.00 No. each
2 W. Gutti 2.00 Nos. per dozen
3 Screw 2.00 Nos. per dozen
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 124
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 125
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 126
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 127
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 128
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 129
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 130
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 131
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 132
DESCRIPTION OF ITEM:
Item No. 18 Supply and erection of iron/aluminium clad 500 volts main switches
fuses, on angle iron board with 3 mm (1/8") thick M.S. sheet cover
bonding to earth with necessary flexible pipe and thimbles, etc.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 133
DESCRIPTION OF ITEM:
Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switche
pole and neutral link and HRC fuses, on angle iron board with 3 mm
thick M.S sheet covering, including bonding to earth with necessar
pipe and thimbles.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 134
DESCRIPTION OF ITEM:
Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switche
pole and neutral link and HRC fuses, on angle iron board with 3 mm
thick M.S sheet covering, including bonding to earth with necessar
pipe and thimbles.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 135
DESCRIPTION OF ITEM:
Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switche
pole and neutral link and HRC fuses, on angle iron board with 3 mm
thick M.S sheet covering, including bonding to earth with necessar
pipe and thimbles.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 136
DESCRIPTION OF ITEM:
Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switche
pole and neutral link and HRC fuses, on angle iron board with 3 mm
thick M.S sheet covering, including bonding to earth with necessar
pipe and thimbles.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 137
DESCRIPTION OF ITEM:
Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switche
pole and neutral link and HRC fuses, on angle iron board with 3 mm
thick M.S sheet covering, including bonding to earth with necessar
pipe and thimbles.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 138
DESCRIPTION OF ITEM:
Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switche
pole and neutral link and HRC fuses, on angle iron board with 3 mm
thick M.S sheet covering, including bonding to earth with necessar
pipe and thimbles.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 139
DESCRIPTION OF ITEM:
Item No. 19 Supply and erection of iron/aluminium clad, 500 volts main switche
pole and neutral link and HRC fuses, on angle iron board with 3 mm
thick M.S sheet covering, including bonding to earth with necessar
pipe and thimbles.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 140
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 141
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 142
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 143
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 144
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 145
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 146
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 147
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 148
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 149
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 150
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 151
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 152
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 153
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 154
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 155
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 156
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 157
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 158
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 159
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 160
DESCRIPTION OF ITEM:
Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply
copper bars, including glazed porcelain bridges, on angle iron boa
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:
(i) 60 Amp. with 4 copper bars size 1" x 1/8" (40 x 3 mm)
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 161
DESCRIPTION OF ITEM:
Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply
copper bars, including glazed porcelain bridges, on angle iron boa
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:
(ii) 100 Amp. with 4 copper bars size 1" x 1/8" (40 x 3 mm)
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 162
DESCRIPTION OF ITEM:
Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply
copper bars, including glazed porcelain bridges, on angle iron boa
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:
(iii) 200 Amp. with 4 copper bars size 2" x 1/8" (50 x 3 mm)
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 163
DESCRIPTION OF ITEM:
Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply
copper bars, including glazed porcelain bridges, on angle iron boa
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:
(iv) 300 Amp. with 4 copper bars size 2" x 3/16" (50 x 4 mm)
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 164
DESCRIPTION OF ITEM:
Item No. 21 Supply and erection of bus bars, for 500 volts 3 phase A.C supply
copper bars, including glazed porcelain bridges, on angle iron boa
with rag bolts and M.S sheet box 1.5 mm thick, etc., complete:
(v) 500 Amp. with 4 copper bars size 2" x " (50 x 6 mm)
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 165
DESCRIPTION OF ITEM:
Item No. 22 (i) Supply and erection of plain pendent lamp holder, complete, with b
holder and flexible twin wire 23/0.0076" upto 2 metre length (with
shade).
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 166
DESCRIPTION OF ITEM:
Item No. 22 (ii) Extra for additional length of flexible wire, beyond 2 metres.
MATERIAL
2 Flexible twin wire 23/0.0076 (23/0.195 mm) 1.00 metre per mtr.
Total
Contractor's Profit & O ## Percent
Total
ITEM RATE
Page 167
DESCRIPTION OF ITEM:
Item No. 23 Supply and erection of counter weight pendent with porcelain count
and fitting on bakelite lamp holder, with flexible twin wire 23/0.
(without bulb & shade).
MATERIAL
1 Flexible twin wire 23/0.0076 (23/0.195 mm) 3.00 metre per mtr.
2 Bakelite lamp holder 1.00 No. each
3 Counter weight with accessories 1.00 No. each
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 168
DESCRIPTION OF ITEM:
Item No. 24 Supply and erection of stiff pendent with brass/metal pipe 6.3 cm
15 mm (") dia brass oxidised or painted along lamp holder with VI
3/0.74 mm (3/0.029").
MATERIAL
1 Brass pipe " dia (12 mm) 2.00 metre per mtr.
2 Canopy nipple & hook 1.00 job per job
3 Brass lamp holder 1.00 No. each
4 VIR/PVC cable 3/0.29 2.00 metre per mtr.
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 169
DESCRIPTION OF ITEM:
Item No. 25 Supply and erection of 22.5 cm (9") long swan neck plain brass/ste
oxidised bracket lamp holder, complete.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 170
DESCRIPTION OF ITEM:
Item No. 26 Supply and erection of wall type/pole type bracket, with double co
tight reflector, flexible wire and brass holder.
MATERIAL
1 G.I. Pipe " dia (20 mm) 1.00 metre per mtr.
2 Brass nipple 1.00 No. each
3 Brass lamp holder 1.00 No. each
4 Double cone reflector 1.00 No. each
5 Flexible wire 1.00 metre per mtr.
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 171
DESCRIPTION OF ITEM:
Item No. 27 Supply and erection of bakelite button holder shade, large size.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 172
DESCRIPTION OF ITEM:
Item No. 28 Supply and erection of call bell 220/250 volts, fixed on teak wood
17.5 x 10 cm (7" x 4").
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 173
DESCRIPTION OF ITEM:
Item No. 29 Supply and erection of bell push or bed switch, with 5 metre twin
wire 23/0.0076"
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 174
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 175
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 176
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 177
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 178
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 179
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 180
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 181
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 182
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 183
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 184
DESCRIPTION OF ITEM:
Item No. 33 Supply and erection of wall socket with 3 pin 5 Amp. shoe.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 185
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 186
DESCRIPTION OF ITEM:
Item No. 35 Supply and erection of 3 pin 10/15 Amp. wall socket.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 187
DESCRIPTION OF ITEM:
Item No. 35 Supply and erection of 3 pin 10/15 Amp. wall socket.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 188
DESCRIPTION OF ITEM:
Item No. 36 Supply and erection of 3 pin switch and plug combined, recessed ty
(i) 5 Amp.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 189
DESCRIPTION OF ITEM:
Item No. 36 Supply and erection of 3 pin switch and plug combined, recessed ty
MATERIAL
1 Plugs 3 pin and switch (combine) 10/15 Amp. 1.00 No. each
2 Machine Screw 5.00 Nos. P. Doz.
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 190
DESCRIPTION OF ITEM:
Item No. 37 Supply and erection of 3 pin 10/15 Amp. wall socket with shoe open
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 191
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 192
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 193
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 194
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 195
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 196
DESCRIPTION OF ITEM:
Item No. 41 Supply and erection of bell push, open/recessed type (without flex
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 197
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 198
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 199
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 200
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 201
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 202
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 203
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 204
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 205
DESCRIPTION OF ITEM:
Item No. 43 Supply and erection of tube light, including rod, choke, starter w
flexible wire, including connection from ceiling rose, etc., compl
(i) Double rod (80 watts) with two chokes and 2 starters.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 206
DESCRIPTION OF ITEM:
Item No. 43 Supply and erection of tube light, including rod, choke, starter w
flexible wire, including connection from ceiling rose, etc., compl
(ii) Single rod (40 watts) with one choke and one starter.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 207
DESCRIPTION OF ITEM:
Item No. 43 Supply and erection of tube light, including rod, choke, starter w
flexible wire, including connection from ceiling rose, etc., compl
(iii) Single round tube, 32 watts, with one choke and one starter, witho
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 208
DESCRIPTION OF ITEM:
Item No. 43 Supply and erection of tube light, including rod, choke, starter w
flexible wire, including connection from ceiling rose, etc., compl
(iv) Round tube, 32 watts, with one choke and one starter, with cover.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 209
DESCRIPTION OF ITEM:
Item No. 44 Providing and fixing M.S iron box for housing main switches, made
(1/16") thick M.S sheet, with locking arrangement, including paint
MATERIAL
1 M.S sheet 1.5 mm thick
Base side 1 x 24/12 x 14/12 (1 x 600 x 350 mm)
Long side 2 x 24/12 x 7 12 (2x600x190mm)
Short side 2 x 14/12 x 7 12 (2x350x190mm)
Top 1 x 24 x 12 x 14 (600 x 350 x 150 mm)
1.04 Sqm @ 12.20 Kg/Sqm 12.68 kg per kg
2 Angle Iron 25 x 25 x 3 mm/Sqm
2 x 24" = 48" (2 x 600 mm)
2 x 14" = 28" (2 x 350 mm)
4 x 7.12 = 30" (4 x 190 mm)
=
0.82 Sqm @ 6.08 Kg/Sqm 1.70 kg 1.70 kg each
3 Handle chromium plated 1.00 No. each
4 Painting 0.178 Gallon Gallon
5 Hinges 3.00 Nos. each
6 Locking arrangement L.S
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 210
DESCRIPTION OF ITEM:
Item No. 44 Providing and fixing M.S iron box for housing main switches, made
(1/16") thick M.S sheet, with locking arrangement, including paint
MATERIAL
1 M.S sheet 38"x16"x 8" thick (1965x406x200mm)
Base side 1x38/12x16/12 (965x406mm) = 0.39 Sqm
Long side 2x38/12x8/12 (2x965x200mm) = 0.39 Sqm
Short side 2x16/12x8/12 (2x406x200mm) 0.17 Sqm
Top 1x38/12x16/12 (1x965x406mm) = 0.39 Sqm
1.34 Sqm
1.34 Sqm @ 12.45 Kg/Sqm 16.70 kg per kg
2 Angle Iron 1" x 1" x 1/8" (25 x 25 x 3mm)
2 x 965 mm = 1.93 R/m
2 x 406 mm = 0.82 R/m
4 x 200 mm = 0.80 R/m
3.55 R/m
3.55 R/m @ 0.632 Kg/R/m 2.25 kg per kg
3 Handle chromium plated 1.00 No. each
4 Paint 0.045 Gallon Gallon
5 Hinges 3.00 Nos. each
6 Locking arrangement L.S
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Labour rate for Each Rs. Say
Composite rate for Each Rs. Say
Page 211
DESCRIPTION OF ITEM:
Item No. 44 Providing and fixing M.S iron box for housing main switches, made
(1/16") thick M.S sheet, with locking arrangement, including paint
MATERIAL
1 M.S sheet 42" x 21" x 9" thick (1067 x 534 x 225mm)
Base side 1 x 42/12 x 21/12 (1076x534mm)
Long side 2 x 42/12 x 9/12 (2x1067x225mm)
Short side 2 x 21/12 x 9/12 (2x534x225mm)
Top 1 x 42 (1x1067x534mm)
12 12 1.872 Sqm
1872 Sqm @ 27.44 Per Sqm (51.36 lbs) 23.30 kg per kg
2 Angle Iron 1" x 1" x 1/8 (25x25x3mm)
2 x 42" = 84" (2x1076)
2 x 21" = 42" (2x534)
4 x 9" = 36" (4x225mm)
162" or 13.5 ft. (4.12 R/m)
412 ft. 1.394 lbs/PRM 5.74 lbs 2.60 kg per kg
3 P/F chromium plated 1.00 No. each
4 P/F Hinges 3.00 Nos. each
Paint 0.054 Gallon Gallon
Locking arrangement L.S
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 212
DESCRIPTION OF ITEM:
Item No. 44 Providing and fixing M.S iron box for housing main switches, made
(1/16") thick M.S sheet, with locking arrangement, including paint
MATERIAL
1 M.S sheet (54" x 28" 11") thick (1372x710x280mm)
Base side 1 x 54/12 x 28/12 (1372x710mm)
Long side 2 x 54/12 x 11/12 (2x1372x280mm)
Short side 2 x 28/12 x 11/12 (2x710x280mm)
Top 1 x 54/12 x 28/12 (1x1372x710mm)
3.12 Sqm
3.12 Sqm @ 27.44 lbs/Per Sqm (85.50 lbs) 38.78 kg per kg
2 Angle Iron 1" x 1" x 1/8" (25x25x3mm)
1x2 x 54"= 108" (2x1372mm)
2 x 28" = 56" (2x710mm)
4 x 11" = 44 (4x280mm)
5.28 R/M
5.28 R/M @ 1.39 lbs/Per R/M
7.36 lbs (7.36 lbs) 3.34 kg per kg
3 Handle chromium plated 1.00 No. each
4 Hinges with screws 4.00 Nos. each
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Labour rate for Each Rs. Say
Composite rate for Each Rs. Say
Page 213
DESCRIPTION OF ITEM:
Item No. 45 Supply and erection of girder clamp hook, 16 mm (5/8") with M.S pl
with bolts and nuts for hanging ceiling fans.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 214
DESCRIPTION OF ITEM:
Item No. 46 Supply and erection of girder strut, of M.S tee section 40 x 40 x
1" x ") complete with clamp, bolts and nuts, etc., including fix
cement concrete 1 : 3 : 6.
MATERIAL
5.00 kg
1 T - Iron " x 1" x 1" x 5" (11.00 lbs)
Clamps 1.00 kg per kg
2 Nut & Bolts 1" (25 mm) 3.00 No. each
3 Manufacturing 1.00 No. each
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 215
DESCRIPTION OF ITEM:
Item No. 47 Supply and erection of roof suspension hook,16mm (5/8" dia) rod wi
(3 x 1" x 1/8") M.S Steel Channel, with clamp, bolts & nuts etc.,
with cement concrete 1:3:6.
MATERIAL
1 Steel channel 75 x 40 x 3 mm
1.5 R/m @ 6.90 Kg/R/m 10.35 kg 10.35 kg per kg
2 Hook 5/8" (16 mm) with nut & bolts 1.00 No. each
3 Clamp 1.00 No. each
4 Cement 0.042 Cft. P. Bag
5 Sand 0.12 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 216
DESCRIPTION OF ITEM:
Item No. 48 Supply and erection of roof suspension hook, of M.S plate 75 x 40
(3 x 1" x ") with 16 mm (5/8") hook, complete with bolts and nut
with cement concrete 1 : 3 : 6.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 217
DESCRIPTION OF ITEM:
Item No. 49 Supply and erection of 3/8" (10 mm) dia M.S bar fan hook placed at
casting of slab.
MATERIAL
1 M.S bar hook 3/8" (!0 mm) dia 1.00 No. each
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 218
DESCRIPTION OF ITEM:
MATERIAL
1 Cement concrete 1:3:6 (1.22x.300x1.0) 0.3714 Cum 0.3714 Cum Per Cum
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 219
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 220
DESCRIPTION OF ITEM:
MATERIAL
1 Steel channel 75 x 13 x 6 mm
1.322 m @ 5.22 Kg/Rm 6.35 Kg
Iron plate 75 x 20 x 6 mm 0.80 Kg
7.15 Kg 7.15 Kg per kg
Bolts and nuts 5/8" dia (16 mm) 2.00 Nos. each
Manufacturing charges 1 job per job
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 221
DESCRIPTION OF ITEM:
Item No. 52 Supply and erection of anchor rod Henley type for pole, including
clamps and 7/12" stay wire, straining screws, etc., erected in cem
1 : 3 : 6 and collar of cement concrete.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 235.40 1 0
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 222
DESCRIPTION OF ITEM:
Item No. 53 Supply and erection of stay for house service pipe, erected with s
screws and 7/14" stay wire, complete.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 129.80 5 0
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 223
DESCRIPTION OF ITEM:
Item No. 54 Supply and erection of house service pipe Henley (G.I pipe water q
pole, type, 50 mm (2" dia) erected to install insulated overhead l
shackle insulator for holding insulated wire and straining devices
wire and other accessories, etc., complete.
1 G.I. pipe 2" dia (50 mm) 4.00 metre per mtr.
2 Shakle insulator 1.00 No. each
3 Clamp double 1.00 No. each
4 Clamp 2" dia (50 mm) 1.00 No. each
5 Rag bolts 5/8" 9" (16 x 225 mm) 1.00 No. each
6 G.I bend 2" (50 mm) cap 2.00 Nos. each
7 G.I Reducing socket 2 x " dia (50 x 20 mm) 1.00 No. each
8 M.S bolts for suport 1.00 No. each
9 Cement 0.064 Cft. P. Bag
10 Sand 0.16 Cft. Per % Cft.
11 Bajri 0.322 P. Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1090.45 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 224
DESCRIPTION OF ITEM:
Item No. 55 Supply and erection of house service pipe 50 mm (2" dia) G.I pipe
pole type, for bare copper wire overhead line, including shackle i
straining devices and other accessories, etc.
Total
Contractor's Profit & O ## Percent
Total
Material per metre 1081.65 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 225
DESCRIPTION OF ITEM:
Item No. 56 Supply and erection of lightening arrestor horn type, complete.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 226
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 227
DESCRIPTION OF ITEM:
Item No. 58 Supply and erection of pin insulator, green medium size.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 228
DESCRIPTION OF ITEM:
Item No. 59 Supply and erection of bare copper conductor wire, No.2 to No.10 S
including binding wire No.16 SWG.
MATERIAL
13.61 kg
1 Copper wire No.2 to 10 (30.00 lbs) per kg
2 Binding wire No.16 1.00 lbs per kg
0.454 kg
Total
Contractor's Profit & O ## Percent
Total
Per Kg 1211.65 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 229
DESCRIPTION OF ITEM:
Item No. 60 Supply and erection of G.I wire of all sizes, including binding wi
for support of rubber wire or earthing wire, pole to pole, etc.
MATERIAL
13.61 kg
1 G.I wire (all size) (30.00 lbs) per kg
2 Binding wire No.16 (1.00 lbs) per kg
0.454 kg
Total
Contractor's Profit & O ## Percent
Total
Material cost per Kg 418.20 1 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 230
DESCRIPTION OF ITEM:
Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on
No.8 SWG bearer wire and in house service pipe, including connecti
through joint box:
Total
Contractor's Profit & O ## Percent
Total
Material cost per metre 573.62 4 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 231
DESCRIPTION OF ITEM:
Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on
No.8 SWG bearer wire and in house service pipe, including connecti
through joint box:
Total
Contractor's Profit & O ## Percent
Total
Material cost per metre 880.13 47 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 232
DESCRIPTION OF ITEM:
Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on
No.8 SWG bearer wire and in house service pipe, including connecti
through joint box:
Total
Contractor's Profit & O ## Percent
Total
Material cost per metre 1230.76 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 233
DESCRIPTION OF ITEM:
Item No. 61 Wiring overhead line in 2 single core, PVC/weather proof cable, on
No.8 SWG bearer wire and in house service pipe, including connecti
through joint box:
Total
Contractor's Profit & O ## Percent
Total
Material cost per metre 1437.56 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 234
DESCRIPTION OF ITEM:
Item No. 62 Supply and erection of all aluminium stranded hard drawn bare cond
size 7/3.099 mm (7/0.122").
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 235
DESCRIPTION OF ITEM:
Item No. 63 Supply and erection of street light pole bracket 30 mm (1") G.I p
long, complete with 2 No. pole clamp.
MATERIAL
1 G.I. Pipe 1" dia (32 mm) 7 ft. (2.13 metre) 2.13 metre per mtr.
2 Cost of clamp 2.00 Nos. each
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 236
DESCRIPTION OF ITEM:
Item No. 64 Supply and erection of pole mounted street light, holders, shade a
etc., for fitting 125/250 watts mercury vapour lamp (excluding cos
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 237
DESCRIPTION OF ITEM:
Item No. 64 Supply and erection of pole mounted street light, holders, shade a
etc., for fitting 125/250 watts mercury vapour lamp (excluding cos
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 238
DESCRIPTION OF ITEM:
Item No. 65 Supply and fitting of mercury vapour lamp, complete with choke set
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 239
DESCRIPTION OF ITEM:
Item No. 65 Supply and fitting of mercury vapour lamp, complete with choke set
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 240
DESCRIPTION OF ITEM:
Item No. 66 Manufacture and erection of angle iron lattice steel structure pol
long (9348 mm ground level) 355 mm square at base & 204 mm square
electric distribution line, using 1"x1"x3/16" angle iron legs an
angle iron bracings 420 mm long fixed between legs on all the four
diagonal position, and 1" x 1" x 3/16" angle iron on top and 4 b
flat iron 2" x ", 305 mm centre to centre, as per standard drawin
silverpainting of pole 3 coats, excavation and refilling of founda
concrete 1 : 2 : 4, 1807 x 500 x 500 mm for foundation, etc., comp
respects.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Page 241
Detail Unit Rate (Metric System) for Each
LABOUR
ITEM RATES
Page 242
DESCRIPTION OF ITEM:
Item No. 67 Manufacture and erection of galvanized angle iron lattice steel st
pole 11.30 metre long (9.85 metre above ground level), 875mm squar
base, 350mm square at top, for electric distribution line, using 5
high tensile steel angle iron legs, and 310x310x3mm M.S angle iro
fixed between legs on all the four sides in diagonal position, as
drawing including silver painting of pole, excavation and refilli
foundation, one ft. thick cement concrete 1:3:6 foundation of oute
2.44x1.067x1.067 metre complete in all respects.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Page 243
Detail Unit Rate (Metric System) for Each
LABOUR
8 Earth filling(1.5x.5 x 6.5) (Item 15(14.63 Cft 14.630 Cft per Cft
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 244
DESCRIPTION OF ITEM:
Item No. 68 Earthing of iron clad/aluminium switches, etc., with G.I wire No.8
pipe 15 mm (" dia) recessed or on surface of wall and floor, comp
1.5 metre long G.I pipe, 50 mm (2" dia) with reducing socket 4 to
below ground level, and 2 metre away from building plinth.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 245
DESCRIPTION OF ITEM:
Item No. 69 Earthing of Metallic cases, etc., with G.I wire No.8 SWG, in 15 mm
pipe, best quality:
1 G.I pipe " dia (12 mm) 7.00 metre per mtr.
0.454 kg
2 G.I wire No.8 SWG (1.00 lbs) per kg
3 G.I clamp " dia (12 mm) 6.00 Nos. each
4 G.I bolts 2" x " dia (50 x 6 mm) 1.00 No. each
5 Gutties 10.00 Nos. per doz.
6 Screw " (20 mm) 10.00 Nos. each
7 G.I bend " dia (12 mm) 1.00 No. each
Total
Contractor's Profit & O ## Percent
Total
Material per Metre 145.48 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 246
DESCRIPTION OF ITEM:
Item No. 69 Earthing of Metallic cases, etc., with G.I wire No.8 SWG, in 15 mm
pipe, best quality:
(ii) Recessed in wall, including hooks, jharries and making good surfac
1 G.I pipe " dia (12 mm) 7.00 metre per mtr.
0.454 kg
2 G.I wire No.8 SWG (1.00 lbs) kg
3 G.I bolts 2" x " dia (50 x 6 mm) 1.00 No. each
4 Hooks 6.00 Nos. each
5 G.I bend " dia (12 mm) 1.00 Nos. each
6 Cement 0.063 Cft. P. Bag
7 Sand 0.18 Cft. Per % Cft.
Total
Contractor's Profit & O ## Percent
Total
Material per Metre 470.64 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 247
DESCRIPTION OF ITEM:
Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.
(i) 8 SWG
Total
Contractor's Profit & O ## Percent
Total
Material per Metre 51.00 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 248
DESCRIPTION OF ITEM:
Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.
(ii) 16 SWG
Total
Contractor's Profit & O ## Percent
Total
Material per Metre
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 249
DESCRIPTION OF ITEM:
Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.
(i) 16 SWG
Total
Contractor's Profit & O ## Percent
Total
Material per Metre 28.56 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 250
DESCRIPTION OF ITEM:
Item No. 70 Bonding to earth with wire on surface, including cost of wire,
clamps, thimbles, etc.
(ii) 20 SWG
Total
Contractor's Profit & O ## Percent
Total
Material per Metre 15.04 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 251
DESCRIPTION OF ITEM:
Item No. 71 Erection only, of lightening conductor of copper staple, and coppe
cement, sand mortar.
Total
Contractor's Profit & O ## Percent
Total
Material per Metre 44.00 0.00
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 252
DESCRIPTION OF ITEM:
Item No. 72 Supply and erection of 600 x 600x3mm (2'x2x1/8") copper plate, inc
riveting to copper tape and placing in mixture of salt & charcoal,
MATERIAL
9.98 kg
1 Copper plate 600x600x3mm=0.00133 Cum (22.00 lbs) per kg
@ 550 lbs/cft 22 lbs 36.30 kg
2 Char coal (80.00 lbs) per kg
18.15 kg
3 Salt (40.00 lbs) per kg
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 253
DESCRIPTION OF ITEM:
Item No. 73 Supply and erection of copper tape, including copper staple copper
cement, sand, etc.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 254
DESCRIPTION OF ITEM:
Item No. 73 Supply and erection of copper tape, including copper staple copper
cement, sand, etc.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 255
DESCRIPTION OF ITEM:
Item No. 74 Supply and erection of 25 mm (1"/dia) and one metre long lightning
copper rod with 5 spikes on ball and base, etc., complete.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 256
DESCRIPTION OF ITEM:
Item No. 75 Supply and erection of electric energy metre, including metre test
MATERIAL
1 Energy metre 10 Amp. Single phase 250 Volts 1.00 No. each
2 Testing Fee L.S
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 257
DESCRIPTION OF ITEM:
Item No. 75 Supply and erection of electric energy metre, including metre test
MATERIAL
1 Energy metre 30 Amp. Single phase 250 Volts 1.00 No. each
2 Testing Fee L.S
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 258
DESCRIPTION OF ITEM:
Item No. 75 Supply and erection of electric energy metre, including metre test
MATERIAL
1 Energy metre 3 x 15 Amp. Three phase 400 Volts 1.00 No. each
2 Testing Fee L.S
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 259
DESCRIPTION OF ITEM:
Item No. 75 Supply and erection of electric energy metre, including metre test
MATERIAL
1 Energy metre 3 x 50 Amp. Three phase 400 Volts 1.00 No. each
2 Testing Fee L.S
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 260
DESCRIPTION OF ITEM:
Item No. 75 Supply and erection of electric energy metre, including metre test
MATERIAL
1 Energy metre 3 x 80 Amp. Three phase 400 Volts 1.00 No. each
2 Testing Fee L.S
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 261
DESCRIPTION OF ITEM:
Item No. 76 Rewinding of A.C ceiling fan, capacitor type, including cost of wi
paper cotton tape, soldering, etc.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 262
DESCRIPTION OF ITEM:
Item No. 76 Rewinding of A.C ceiling fan, capacitor type, including cost of
wire, leatheride paper cotton tape, soldering, etc.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 263
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 264
DESCRIPTION OF ITEM:
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 265
DESCRIPTION OF ITEM:
Item No. 78 Rewinding of pedestal fan 600 mm (24") sweep, and 900 - 950
RPM, including wire, leatheride paper, cotton, tape, etc.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 266
DESCRIPTION OF ITEM:
Item No. 79 Supply and fitting of regulator nob with shaft and plate of
electric fan regulator.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 267
DESCRIPTION OF ITEM:
Item No. 80 Supply and fitting of capacitor 2.2 uf, for ceiling fans.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 268
DESCRIPTION OF ITEM:
Item No. 81 Supply and fitting of ball bearing of size 6201, 6202 or 6203, for
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 269
DESCRIPTION OF ITEM:
Item No. 82 Rewinding regulator of ceiling fan (1200/1400 mm) sweep, to contro
3/4 speeds.
MATERIAL
0.18 kg
1 Enamel copper wire No.26 SWG to 32 SWG (0.403 lbs) kg
2 Leathoride paper, cotten tape and vinishing L.S
3 Deduct cost of old material (0.403 lbs) per kg
0.18 kg
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 270
DESCRIPTION OF ITEM:
Item No. 83 Erection of ceiling fan alongwith regulator (all sizes), including
from local Railway Station/Store to site of work, electric wire/ca
suspension rod and board connection, and cutting threading on the
where necessary.
MATERIAL
Total
Contractor's Profit & O ## Percent
Total
Total
Sundries ## Percent
Total
Contractor's Profit & O ## Percent
Total
ITEM RATES
Page 271
LIST EQUIPMENT
S. No. NAME OF MACHINERY CAPACITY COST
EQ-01 Bull Dozer D-6 (16 Ton) Per Hour
EQ-02 Motor Grader Per Hour
EQ-03 Wheel Loader (15 Ton) Per Hour
EQ-04 Rental Charges of equipment for desilting Per Day
EQ-05 3 Wheel Roller (10-15 Ton) Per Hour
EQ-06 Pneumatic Tyre Roller (8-13 Ton) Per Hour
EQ-07 Tandum/Road Roller (8-12 Ton) Per Hour
EQ-08 Vibratory Roller (8 Ton) Per Hour
EQ-09 Asphalt Plant (45-46 Ton) Per Hour
EQ-10 Asphalt Finishers (Paver) Per Hour
EQ-11 Electric Power Plant (Generator) (100 KW) Per Hour
EQ-12 Truck 2-Axle (Local) (10 Ton) Per Hour
EQ-13 Truck 3-Axle (Local) (15 Ton) Per Hour
EQ-14 Truck 3-Axle (Imported) (15-18 Ton) Per Hour
EQ-15 Dumper Truck (Imported) (15 Ton) Per Hour
EQ-16 Water Lorry (Local) Per Hour
EQ-17 Donkey Each
EQ-18 Wheel Tractor with Plough Per Hour
EQ-19 Wheel Tractor with Trolley Per Hour
EQ-20 Wheel Tractor with Sheep foot Roller Per Hour
EQ-21 Wheel Tractor with Water Tank Per Hour
EQ-22 Wheel Tractor with Blade Per Hour
EQ-23 Concrete Mixer 2 Bag
EQ-24 Concrete Mixer 1 Bag
EQ-25 Concrete Vibrator Per Hour
EQ-26 Plate Compactor Per Hour
EQ-27 Tar Boiler Per Hour
EQ-28 Cost of lifting machinery including carriage Each
EQ-29 Cost of trollies Each
EQ-30 Road Roller Per Day
EQ-31 Hire charges for a cart having a capacity of about 20 Cft/one ton Per Day
EQ-32 Hire charges of Rig Per Hour
EQ-33 Hire charges of truck (5 ton - 10 tons) excluding POL but including crew Per Day
EQ-34 Hire Charges of testing apparatus Per Day
EQ-35 Reg Pump Per Hour
EQ-36 Cost of pump set 6"x5" with 15 HP Diesel Engine Each
EQ-37 Generator set light Per Hour
EQ-38 Pumping for out water 0-1' to 0-8' Per Hour
EQ-39 Pumping for out water 0-9' to 0-12' Per Hour
EQ-40 Pumping Machinery Boring 0-1' to 0-8' Per Day
EQ-41 Pumping Machinery Boring 0-9' to 0-12' Per Day
EQ-42 Pump charges for pumping out water from 0-1' to 0-8' depth Per Hour
EQ-43 Pump charages for pumping out water from 0-9' to 0-12' depth Per Hour
EQ-44 Hire Charges of Assembling Machine for A.C. Pipe 3" to 6" --
EQ-45 Hire Charges of Assembling Machine for A.C. Pipe 8" to 10" --
EQ-46 Hire Charges of Assembling Machine for A.C. Pipe 12" to 18" --
EQ-47 Hire Charges of Assembling Machine for A.C. Pipe 20" to 24" --
EQ-48 Disposal of Pumped Out Water upto 100' distance for 1' depth --
EQ-49 Disposal of Pumped Out Water upto 100' distance upto 3' depth --
EQ-50 Disposal of Pumped Out Water upto 100' distance upto 5' depth --
EQ-51 Disposal of Pumped Out Water upto 100' distance upto 6' depth --
EQ-52 Disposal of Pumped Out Water upto 100' distance upto 7' to 12' depth --
EQ-53 Cost of Bulldozer-D6 140 HP
EQ-54 Cost of Motor Grader 135 HP
Page 1
LIST EQUIPMENT
S. No. NAME OF MACHINERY CAPACITY COST
EQ-55 Cost Wheel Loader 100 HP
EQ-56 Cost of 3 wheel-Static Roller (local) 10-12 Ton
EQ-57 Cost of Pneumatic Roller 8-13 Ton
EQ-58 Cost of Tandem Roller 8-12 Ton
EQ-59 Cost of Vibratory Roller 8-Ton
EQ-60 Cost of Asphalt Plant 45-46 Ton.
EQ-61 Cost of Asphalt Paver 145 HP
EQ-62 Cost of Electric power Generator 100 KW
EQ-63 Cost of Truck-2axle (local) 10 Ton
EQ-64 Cost of Truck-3axle (local) 15-18 Ton
EQ-65 Cost of Truck-3axle (imported) 18 Ton
EQ-66 Cost of Dump truck 18.0 Ton
EQ-67 Cost of Water lorry (local) --
EQ-68 Cost of Wheel Tractor with Plough --
EQ-69 Cost of Wheel Tractor with Trolley --
EQ-70 Cost of Wheel Tractor with Sheep foot roller --
EQ-71 Cost of Wheel Tractor with Water Tank --
EQ-72 Cost of Wheel Tractor with Blade --
EQ-73 Cost of Concrete Mixer 2 bags
EQ-74 Cost of Concrete Mixer 1 bag
EQ-75 Cost of Concrete vibrator --
EQ-76 Cost of Plate Compactor --
EQ-77 Cost of Tar Boiler 1000Ltr.
Page 2
CHAPTER NO. 10
FLOORING
i) Rates for all finished works include the removal of surplus debris, unused
material and by products.
ii) For handling of all types of material for short lead including carriage upto
3 chains (90m) nothing is to be paid as extra. Where handling and carriage
involves an extra lead beyond 3 chains, (90m) carriage for whole of the distance
should be paid
DESCRIPTION OF ITEM
1 Laying Muram flooring consisting of 1" (25m) layer of fine powdery or flakey variety of M
laid over 6" (150mm) good hard layer of Muram spreaded over 9" (225mm) thick sub base
comprising of hand packed rubble or broken bricks properly watered and rammed provided
over well rammed earth
MATERIAL
1 9" thick rubble or broken hard bricks 80.00 Cft 0.00Per 100 Cft -
2 6" Hard Muram 55.00 Cft 0.00Per 100 Cft -
3 1" Fine Powdery Muram 9.00 Cft. 0.00Per 100 Cft -
Total -
Contractor's Profit & Ove ## Percent -
Total -
LABOUR
ITEM RATE
Page 1
DESCRIPTION OF ITEM
MATERIAL
LABOUR
ITEM RATE
Page 2
DESCRIPTION OF ITEM
3 Providing, laying, watering and ramming brick ballast 1" - 2" gauge mixed with
25% sand, for floor foundation, complete in all respects.
MATERIAL
LABOUR
ITEM RATE
Page 3
4 Mud Flooring
DESCRIPTION OF ITEM
Mud flooring consisting of 6" thick consolidated layer of moistured earth and
finished off with 1" mud plaster and gobri leeping.
MATERIAL
LABOUR
ITEM RATE
Page 4
5 Brick Flooring
DESCRIPTION OF ITEM
Dry brick paving laid flat, sand grouted including preparation of bed by watering, rammin
bringing the same to proper camber by " mud plaster
MATERIAL
ITEM RATE
Page 5
DESCRIPTION OF ITEM
6 Dry brick on edge paving sand grouted including preparation of bed by watering,
ramming and bringing the same to proper camber by thick mud plaster
MATERIAL
LABOUR
ITEM RATE
Page 6
DESCRIPTION OF ITEM
7 Grouting 4" dry brick work with cement mortar ratio 1:5
MATERIAL
ITEM RATE
Page 7
DESCRIPTION OF ITEM
3
8 Flat brick flooring laid in 1:6 cement mortar over a bed of /4" thick cement mortar 1:6
MATERIAL
ITEM RATE
Page 8
DESCRIPTION OF ITEM
9 Brick on edge flooring laid in 1:6 cement mortar over a bed of 3/4" thick cement mortar (
MATERIAL
ITEM RATE
Page 9
DESCRIPTION OF ITEM
10 Brick tiles (12"x6"x2") laid in (1:6) cement mortar, over a bed of 3/4" thick cement mort
MATERIAL
LABOUR
ITEM RATE
Page 10
DESCRIPTION OF ITEM
11 Brick tiles (9" x 4" x 1") laid flat in 1:3 cement mortar over a bed of 3/4" thick ceme
MATERIAL
LABOUR
ITEM RATE
Page 11
DESCRIPTION OF ITEM
12 Cement tiles (8"x8"x") laid fiat in 1:2 cement mortar over 3/4" thick bed of cement mort
MATERIAL
ITEM RATE
Page 12
DESCRIPTION OF ITEM
13 Cement concrete tiles laid in 1:2 cement mortar over 3/4" thick bed of cement mortar 1:2
MATERIAL
ITEM RATE
Page 13
b) 9" x 9" x 3/4"
MATERIAL
ITEM RATE
Page 14
c) 6" x 6" x 3/4"
MATERIAL
ITEM RATE
Page 15
DESCRIPTION OF ITEM
14 Coloured cement tiles (8"x8"3/4") of approved dark shade laid flat in 1:2 cement
mortar over 3/4" bedding mortar of 1:2
MATERIAL
ITEM RATE
Page 16
DESCRIPTION OF ITEM
MATERIAL
LABOUR
ITEM RATE
Page 17
b) 1" (30mm) Thick
MATERIAL
LABOUR
ITEM RATE
Page 18
c) 1" (40mm) Thick
MATERIAL
LABOUR
ITEM RATE
Page 19
3
d) 1 /4" (45mm) Thick
MATERIAL
LABOUR
ITEM RATE
Page 20
e) 2" (50mm) Thick
MATERIAL
LABOUR
ITEM RATE
Page 21
f) 2" (55mm) Thick
MATERIAL
LABOUR
ITEM RATE
Page 22
g) 2" (60mm) Thick
MATERIAL
LABOUR
ITEM RATE
Page 23
h) 2 3/4" (70mm) Thick
MATERIAL
LABOUR
ITEM RATE
Page 24
i) 3" (75mm) Thick
MATERIAL
LABOUR
ITEM RATE
Page 25
DESCRIPTION OF ITEM
16 Providing and laying conglomerate flooring (two coat work) with top layer of " thick
wearing surface, consisting of one part of cement and two parts of stone chips passing
3/16" sieave, over bottom layer of cement concrete 1:3:6 including surface finishing and
dividing in panels:-
MATERIAL
LABOUR
ITEM RATE
Page 26
b) 1 3/4" (45mm) Thick
MATERIAL
LABOUR
ITEM RATE
Page 27
c) 2" (50mm) Thick
MATERIAL
LABOUR
ITEM RATE
Page 28
DESCRIPTION OF ITEM
17 Add extra in cement concrete floor topping, if finished with pigment and polishing
MATERIAL
1 Grey Cement for Finishing 1/16" Thick 0.40 Bags 0.00 Per Bag -
2 Pigment 4.5 Lbs (2.04 Kg 0.00 Per Kg. -
3 Polish 0.5 Lbs (0.23 Kg. 0.00 Per Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -
ITEM RATE
Page 29
DESCRIPTION OF ITEM
18 Extra labour for each storey above ground floor for moasic, conglomerate, tiles
stone and wooden floor
ITEM RATE
DESCRIPTION OF ITEM
19 Flag stone flooring laid in lime mortar 1:2 over 3/4" bedding mortar in plat forms
and floors etc.
MATERIAL
LABOUR
ITEM RATE
Page 30
b) 3" (75mm) Thick
MATERIAL
LABOUR
ITEM RATE
Page 31
DESCRIPTION OF ITEM
20 Asphalt flooring including preparation of proper base, remelting, setting out and
finishing complete
MATERIAL
LABOUR
Mason for Setting out and laying 0.25 No. 0.00 Per day -
Coolies 2.00 No. 0.00 Per day -
Carpenter 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total 0.00
ITEM RATE
Page 32
b) " Thick Topping
MATERIAL
LABOUR
ITEM RATE
Page 33
c) " Thick Topping
MATERIAL
LABOUR
ITEM RATE
Page 34
DESCRIPTION OF ITEM
21 1 3/8" thick mosaic flooring consisting of 3/8" mosaic topping of one part of
cement and marble powder in the ratio 3:1 and two parts of marble chips laid
over 1" thick flooring of 1:2:4 cement concrete including rubbing and polishing
complete.
ITEM RATE
Page 35
b) Using White Cement
LABOUR
ITEM RATE
Page 36
DESCRIPTION OF ITEM
22 1" thick mosaic flooring consisting of " mosaic topping of one part of
cement and marble powder in the ratio of 3:1 and two parts of marble chips laid
over 1" thick flooring of 1:2:4 cement concrete including rubbing and polishing
complete.
MATERIAL
1 Grey Cement for " Topping 1.27 Bag 0.00 Per Bag -
2 Marble Chips 3.00 Cwt (152.40 Kg 0.00 Per Kg. -
3 Carborandom Stone 2.00 Nos. 0.00 Each -
4 Wax Polish 0.50 Lbs (0.23 Kg 0.00Packet 3 Kg -
5 Linen Cotton etc. 0.72 Kg. 0.00 P. Kg. -
6 Tar Taric Acid 0.34 Lbs / (0.15 Kg 0.00 Per Kg. -
7 Marble Poweder 0.42 Cwt (21.34 Kg 0.00Per 100 Kg. -
Total -
Contractor's Profit & Ove ## Percent -
Total -
ITEM RATE
Page 37
b) Using White Cement
MATERIAL
ITEM RATE
Page 38
DESCRIPTION OF ITEM
23 Providing and laying floor of mosaic marble chips tiles 1" thick of approved quality and
laid in white cement and pigment over 3/4" bedding of cement sand mortar 1:2, incluidng
finishing and polishing complete.
MATERIAL
LABOUR
ITEM RATE
Page 39
DESCRIPTION OF ITEM
24 Laying floor of approved white glazed tile 1/4" thick in white cement 1:2 over
3/4" thick cement mortar 1:2 complete.
MATERIAL
LABOUR
ITEM RATE
Page 40
DESCRIPTION OF ITEM
25 Laying floors of a approved coloured glazed tiles 1/4" thick laid in white
cement and pigment on a bed of 3/4" thick cement mortar 1:2
MATERIAL
LABOUR
ITEM RATE
Page 41
DESCRIPTION OF ITEM
26 Rubbing and polishing old grit/mosaic floor including repairing voids, un-even
surface complete in all respects.
MATERIAL
Skilled Cooly for rubbing and polishing 1.00 No. 0.00 Per day -
Cooly 1.00 No. 0.00 Per day -
Bahishti 0.25 No. 0.00 Per day -
Total -
Sundries ## Percent -
Total 0.00
Contractor's Profit & Ove ## Percent -
Total
ITEM RATE
Page 42
DESCRIPTION OF ITEM
27 Rubbing and Polishing grit floor, including repairing voids, uneven surface
complete in all respects.
MATERIAL
ITEM RATE
Page 43
DESCRIPTION OF ITEM
28 Cleaning and washing mosaic or marble floor with caustic soda mixture
MATERIAL
ITEM RATE
Page 44
DESCRIPTION OF ITEM
29 Shisham wood boarding or strips flooring 3/4" thick (sawn to required sizes)
tongued and grooved or splayed rebated fixed with brass screws on deedar wood
battens 1"x2" placed at 12" centre to centre including two coats of bitumen laid
hot on the base.
MATERIAL
Shisham Wood
ITEM RATE
Page 45
DESCRIPTION OF ITEM
MATERIAL
ITEM RATE
Page 46
DESCRIPTION OF ITEM
MATERIAL
1
Teak Wood (100x' x /12' 4.20 Cft.
Add 5% for rebate 0.20 Cft.
Total 4.40 Cft.
Add 20% Wastage 0.88 Cft
Total 5.28 Cft. 0.00 Per Cft. -
ITEM RATE
Page 47
DESCRIPTION OF ITEM
32 Shisham wood block flooring 1" thick cut to required size, fixed on a layer of
asphalt bitumen laid on base
MATERIAL
Bitumen for laying and dipping blocks 80 Lbs (36.32 Kg. 0.00 Per Kg. -
Primer 5.00 Lbs (2.27 Kg 0.00 Per Kg. -
Fire Wood 0.25 Md (9.33 Kg. 0.00 Per Kg. -
Sand Paper 2.00 Dozen 0.00 Per Dozen -
Total -
Contractor's Profit & Ove ## Percent -
Total -
ITEM RATE
Page 48
DESCRIPTION OF ITEM
33 Teak wood block 1" thick cut to required size fixed on a layer of asphalt bitumen laid on
MATERIAL
ITEM RATE
Page 49
DESCRIPTION OF ITEM
34 Laying wooden paving of hard wood on edge in coal tar and asphalt
a) Shisham Wood
MATERIAL
ITEM RATE
Page 50
b) Kikar Wood
MATERIAL
ITEM RATE
Page 51
DESCRIPTION OF ITEM
35 Tile skirting laid in 1:2 cement mortar over 3/4" thick cement mortar 1:2 including
cement washing and filling joints complete.
a) Cement Tiles
MATERIAL
ITEM RATE
Page 52
b) Mosaic Tiles
MATERIAL
LABOUR
ITEM RATE
Page 53
DESCRIPTION OF ITEM
36 Providing grey cement skirting or dado 3/8" thick including rounding of corner and
straightening of top edge and finishing to smooth surface after plastering
MATERIAL
ITEM RATE
Page 54
b) 1:3 Cement Sand Mortar
MATERIAL
ITEM RATE
Page 55
c) Extra if skirting or dado is finished with pigment of any colour
MATERIAL
ITEM RATE
Page 56
DESCRIPTION OF ITEM
37 White glazed tiles " thick dado jointed in white cement and laid over 1:2 cement
sand mortar 3/4" thick including finishing complete
MATERIAL
LABOUR
ITEM RATE
Page 57
DESCRIPTION OF ITEM
3
38 Glazed tile dado " thick dado laid in pigment over 1:2 cement sand mortar /4" thick
including finishing
MATERIAL
LABOUR
ITEM RATE
Page 58
DESCRIPTION OF ITEM
39 Masaic dado or skirting with one part of cement and marble powder in the ratio of
3:! and two parts of marble chips, laid over " thick cement plaster 1:3 including
rubbing and polishing complete with finishing:
MATERIAL
LABOUR
ITEM RATE
Page 59
a-ii) Using Grey Cement " Thick
MATERIAL
LABOUR
ITEM RATE
Page 60
b-i) Using White Cement 3/8" thick
MATERIAL
i) 3/8" Thick
LABOUR
ITEM RATE
Page 61
b-ii) Using White Cement (" thick)
MATERIAL
i) Thick
LABOUR
ITEM RATE
Page 62
DESCRIPTION ITEM
MATERIAL
LABOUR
ITEM RATE
Page 63
DESCRIPTION OF ITEM
41 Providing and Fixing Glass Strip 5mm thick and 1" wide
for dividing mosaic flooring into panels.
MATERIAL
ITEM RATE
Note :Labour for fixing already included in item 15 & 22 of this chapter
Page 64
DESCRIPTION OF ITEM
42 Providing and fixing marble strip of any shade for dividing the mosaic flooring into pann
MATERIAL
ITEM RATE
Page 65
b) Size 1" x "
MATERIAL
ITEM RATE
Page 66
CHAPTER NO. 25
IRON WORK
DESCRIPTION OF ITEM:
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 1
2. Dismantling Tramway track.
ITEM RATE
Page 2
3. Laying, Linking of B.G Track including packing, straightening and levelling.
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 3
4. Linking points and crossings complete with fastenings.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total Say 0.00
ITEM RATE
Page 4
5. Bending or straightening B.G. rail with Jim crow
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total Say 0.00
ITEM RATE
Page 5
6. Fixing street lamp post.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 6
7. Binding ends of sleepers and timbers of all sizes and kinds including spreading and
restacking.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
Say
ITEM RATE
Page 7
8. Opening stacks of sleepers and Timbers of all kinds and sizes including spreading for
inspection and restacking within chain lead.
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
Say 0.00
ITEM RATE
Page 8
9. Small Iron work such as gusset plates, knees, bends, strips, straps, rings etc. including
cutting, drilling, revitting, bending assembling & fixing but excluding erection in position.
Total
Contractor's Profit & O 20.00 Percent
Total
LABOUR
Total
Sundries 10.00 Percent
Total
Contractor's Profit & O 20.00 Percent
Total
Say
ITEM RATE
Labour Rate for 1 Cwt. Rs. Say
Page 9
10. Fabrication of heavy steel work, with angle, tees, flat iron, round iron and sheet iron for
making trusses, girders, tanks etc. including cutting, drilling, revitting handling,
assembling and fixing but excluding erection in position.
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 10
11. Erection and fitting in position of iron trusses, staging of water tanks.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
Page 11
12. Fixing corrugated iron sheet including revitting.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 12
13. Erecting corrugated iron sheet tanks upto 20 ft. height.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
Page 13
14. Erecting rolled steel beams on old rails in roofs etc., erection and fixing in position.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 14
15. Erecting rolled steel beams or rails, erection for posts etc. (other than in roofs).
LABOUR
Page 15
16. Making bolts and nuts of iron rods.
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Labour Rate/ Cwt. Rs. 0.00 Say 0.00
Page 16
17. Cutting rails, rolled steel joists and beams with hack saw:-
a) upto 6" size.
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 17
17. b) Above 6" size.
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 18
18. Cutting rails or rolled steel beams of size below 6" with Jim.
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 19
19. Bending rolled steel beams on rails.
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
ITEM RATE
Page 20
20. Drilling holes in plates upto 1/2" thick per inch dia or part thereof.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 21
21. Extra for drilling holes in plates over each 1/2" thick per inch dia or part thereof.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 22
22. Riveting 1/8" dia
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 23
23. Cutting out rivets, all sizes.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 24
24. Fitting and erection of gutters of sheet iron.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 25
25. Cutting and fixing iron bars for barred windows
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 26
26. Cutting GI sheets.
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 27
27. Notching web or foot of rail posts for housing rail beams.
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Labour Rate/Notch Rs. 0.00 Say 0.00
Page 28
28. Hoop Iron netted trellis work fixed with nails.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 29
29. Fixing zinc Iron or GI Sheets on table tops.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 30
30. Making and fixing steel grated doors, complete with locking arrangement, angle iron frame 2"x2"x3
3/4" square bars 4" center to center
b Hold fast with pivot and fixed 6.00 Nos. 0.00 Each 0.00
c Locking arrangement with sliding bolt 1 long
and 1" dia 1.00 No. 0.00 Each 0.00
d Coal 15.00 Kg. 0.00 Per Kg. 0.00
e Rivets and bolts 2.27 Kg. 0.00 Per Kg. 0.00
f Steel 1.13 Kg. 0.00 Per Kg. 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
ITEM RATE
Page 31
31. Making and fixing steel grated door with 1/16" thick sheeting including angle iron frame
2"x2"x3/8" and 3/4" square bars 4" center to center with locking arrangement.
MATERIAL
LABOUR
Total
Sundries 10.00 Percent
Total
Contractor's Profit & O 20.00 Percent
Total
Say
ITEM RATE
Page 32
32. Making and fixing grating in opening, including fixing at site with flat iron 2"x3/8" and 3/4"
square bars at 4" cetnre to center.
1 Steel
a Frame 2" x 3/8"
3 x 6' = 18 Rft. @ 2.51 lb/Rft. = 45 lb 20.50 Kg.
b Grating 3/4"x3/4" 14x 8' = 112 Rft. @ 1.88 lb/ft.
= 210.5 95.54 Kg.
Total 116.04
Wastage @ 5% 5.80 Kg.
Total 121.84 Kg. 0.00 Per Kg. 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 33
33. Providing and fixing stair railing (all types and designs) of hard wood, including bends
and corners, screwed to 5/8"x5/8" M.S. square bars 2.75 ft. high, at 5.5 inch center to
center, fixed in steps of stairs, M.S. flat 1"x1/8" welded to bars, painting/polishing 3 coats,
etc. complete.
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
ITEM RATE
Page 34
34. Providing/fixing stair railing consisting of M.S. Box section size 1-1/2"x3" of 16 SWG
welded with M.S. flat 1"x1/8" continuously and welded over M.S. square bars 5/8"x5/8"
punched in M.S. flat 2 ' high @ 5" c/c fixed in steps of stair I/C painting 3 coats
complete.
MATERIAL
ITEM RATE
Page 35
35. Providing and fixing terrace railing of 2" i/d conduit pipe 16 SWG welded with 5/8"x5/8"
square bars 2.75 ft. high fixed at 5" center to center in reinforced cement concrete slab
with suitable arrangement, complete in all respects as per design and drawing.
LABOUR
ITEM RATE
Page 36
36. Providing and fixing collapsible gate made of 2"x2"x1/4" tee iron at top and bottom,
channel iron vertical 3/4"x1/4"x1/4"x1/8" at 3" to 5" center to center (Approximately) and flat
iron crosses 3"x3/16" and best quality rollers at bottom of 3" dia meter including holdfast,
handles 12" long of 3/4"x1/4"x1/4"x 1/8" channel iron, locking arrangement inside and out
side, painting 3 coats of black Japan enameled, complete in working order.
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
Page 37
Detail Unit Rate Per Sft.
Rate
Qty Per Unit Amount
LABOUR
ITEM RATE
Page 38
37. Providing and fixing 24 SWG GI sheet rolling shutter, consisting of steel frame of M.S.
channel 2"x1"x1/8", angle iron 1"x1"x1/8", M.S. plat 1'x1'x1/8", GI pipe 1" dia, spring
2' center to center, rollers, 24 SWG, GI covering 1'x1', handles, holdfast & painting three
coats, complete in all respects.
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATES
Page 40
38. Providing and fixing M.S. angle iron 1"x1"x" edge protector nozing of steps of stairs,
having holdfast of 3/8" dia M.S. bars 8" long welded at 2' center to center and embedded
in cement concrete on steps complete in all respects.
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
1 Welding charges of angle iron 4.00 No.weld 0.00 Each weld 0.00
2 Fixing charge 0.00 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 41
39. Providing and fixing stair railing of 2' i/d GI pipe, welded with 5/8"x5/8" square M.S.
bars 2'-9" high, fixed in each step, complete in all respects, including painting, polishing
three coats.
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
ITEM RATE
Page 42
40. Providing and fixing galvanized wire gauze 24 SWG 144 mesh per square inch fixed to
steel window, complete in all respects.
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 43
41. Providing and fixing steel windows with openable glazed panels, using beam section for
frame 1"1x5/8"x1/8" Z section for beams 3/4"x1"x3/4"x1/8", T section sashes 1"x1"x1/8"
glass panes, wooden screeds for glazing, embedded over a thin layer of putty duly
screwed with beams, brass fittings, holdfast, duly painted, complete in all respects,
including all costs of material and labour, etc., as per approved design and as directed by the En
5 Window hinges 1/4" thick with 5/16 dia pins 8.00 Nos 0.00 Each 0.00
8 Wooden strips for fixing glass pans 68.00 Rft. 0.00 Per Rft. 0.00
Page 44
41 a (i) Using Glass Pans 2 mm thick
Material as per item No. 41 (a) above 1333.90
Cost of glass 2 mm thick 24.00 Sft. 0.00 Per Sft. 0.00
Total 1333.90
Contractor's Profit & O 20.00 Percent 266.78
Total 1600.68
LABOUR
2 Labour for 24 Sft. for fixing 12 Nos. glass pa 24.00 Sft. 0.00 Per Sft. 0.00
position by fixing 96 Nos. glazing clips in
position and then applying wooden strips
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 45
41 a (ii Using 2.5 mm thick glass of Panes
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
Total 0.00
ITEM RATE
Page 46
41 a (i Using 3 mm thick glass panes
LABOUR
Total 0.01
ITEM RATE
Page 47
41 a (ivUsing 4 mm thick glass panes
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
Total 0.01
ITEM RATE
Page 48
41 a (v Using 5 mm thick glass panes
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
Total 0.01
ITEM RATE
Page 49
41 - b Fixed with Wire Gauze 22 SWG.
Page 50
8 Window hinges 1/4" thick with 5/16" dia 8.00 Nos 0.00 Each 0.00
9 Mild steel casement handles 6" with screwing 4.00 Nos. 0.00 Each 0.00
flat & catching hook 4 Nos. @ Rs. 4.00 each
10 Mild steel casement, 15" long with gap flat an 4.00 Nos. 0.00 Each 0.00
catch pins
11 Wooden screeds to form the glass panes 68.00 Rft. 0.00 Per Rft. 0.00
12 96 Nos steel glazing clips for fixing glass pa 96.00 Nos. 0.00 Each 0.00
in position before applying putty
Total 0.00
Page 51
41 - b ( Using glass panes 2 mm thick
Total 240.00
Contractor's Profit & O 20.00 Percent 48.00
Total 288.00
LABOUR
1 Labour for fabrication, welding & fixing 42.00 welds 0.00 per weld 0.00
fixture 42 welds for 24 Sft.
2 Labour for fixing 12 Nos. Glass panes in 24.00 Sft. 0.00 P.Sft 0.00
position by making 128 No. holes & fixing
128 Nos screws
5 Painting with black Japan paint i/c cost of pa 24.00 Sft. 0.00 Per Sft. 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Labour Rate per Sft Rs. 0.00 Say 0.00
Composite Rate/Sft. Rs. 11.95 Say 11.95
Page 52
41 - b ( Using 2.5 mm thick glass panes
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
2 Labour for fixing 12 Nos. Glass panes in 24.00 Sft. 0.00 Per Sft. 0.00
position by making 128 No. holes & fixing
128 Nos screws
5 Painting with black Japan paint i/c cost of pa 24.00 Sft. 0.00 per Sft/ 0.00
ITEM RATE
Page 53
41 - b ( Using 3 mm thick glass panes
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
1 Labour for fabrication, welding & fixing 42.00 welds 0.00 per weld 0.00
fixture, 42 welds for 24 Sft.
2 Labour for fixing 12 Nos. Glass panes in 24.00 Sft. 0.00 Per Sft. 0.00
position by making 128 No. holes & fixing
128 Nos screws
3 Labour for fixing 12 No. glass panes in 24.00 Sft. 0.00 Per Sft. 0.00
position by fixing 96 Nos. glazing clips in position
and then fixing wooden strips with screws
@ Rs. 0.75 per Sft.
5 Painting with black Japan paint i/c cost of pa 24.00 Sft, 0.00 Per Sft. 0.00
ITEM RATE
Page 54
41 - b ( Using 4 mm thick glass panes
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
1 Labour for fabrication, welding & fixing 42.00 Weld 0.00 per weld 0.00
fixture 42 welds for 24 Sft.
2 Labour for fixing 12 Nos. Glass panes in 24.00 Sft 0.00 Per Sft. 0.00
position by making 128 No. holes & fixing
128 Nos screws
3 Labour for fixing 12 No glass panes in 24.00 Sft. 0.00 Per Sft. 0.00
position by fixing 96 Nos. glazing clips in position
and then fixing wooden strips with screws
@ Rs. 0.75 per Sft.
5 Painting with black Japan paint i/c cost of pa 24.00 Sft. 0.00 Per Sft. 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 55
41 - b (vUsing 5 mm thick glass panes
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
1 Labour for fabrication, welding & fixing 42.00 Weld 0.00 per weld 0.00
fixture, 42 welds for 24 Sft.
2 Labour for fixing 12 Nos. Glass panes in 24.00 Sft 0.00 Per Sft. 0.00
position by making 128 No. holes & fixing
128 Nos screws
3 Labour for fixing 12 No glass panes in 24.00 Sft. 0.00 Per Sft. 0.00
position by fixing 96 Nos. glazing clips in position
and then fixing wooden strips with screws
5 Painting with black Japan paint i/c cost of pa 24.00 Sft. 0.00 Per Sft. 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 56
42. Providing and fixing steel windows using M.S. sheet (16 SWG) moulded tubuler pipe
1"x1" for frame and 1"x1" for leaves including M.S. Square bars "x" welded around
each panel of frame, 5 mm thick glass panes fixed with double M.S. square tubular pipe
3/8"x3/8" (22 SWG) beading with 'U' shapped rubber lining, brass fitting, holdfast,
including painting three coats complete in all respects.
a) For openable pannels fixed with wire gauze 24 SWG, 12x12 mesh and glass panes 5 mm
thick
Lower Portion
ii) Horizontal 2x3x (1'-10") 11.00 Rft.
iv) Vertical 3x2 x (4'-1") 24.25 Rft.
Lower Portion
ii) Horizontal 2x3 x(1'-7") 9.75 Rft.
iv) Vertical 3x2 x (3'-11") 23.87 Rft.
50.00 Rft.
For both sides 50x2 = 100 Rft.
Add 5% wastage 5 Rft.
@ 0.478 lb/ft. 105 Rf 22.77 Kg. 0.00 Per Kg. 0.00
Page 57
a) Upper Portion
i) Horizontal 2x3x (1'-10") 11.00 Rft.
ii) Vertical 3x2 x (1'-4") 8.00 Rft.
b) Lower Portion
iii) Horizontal 2x3x (1'-10") 11.00 Rft.
6 5 mm thick glass
3x(1'-7")x(4'-1") 19.70 Sft.
3x(1-7")x(1'-2") 5.68 Sft.
25.38 Sft.
Add 5% wastage 1.25 Sft.
26.63 26.63 Sft. 0.00 Per Sft. 0.00
7 U' shapped rubber linning (" thick) single 50.00 Rft. 0.00per Per Rft 0.00
quality as in item No. 2
8 24 SWG (12x12) mesh wire gauze galvanized 36.00 Sft. 0.00 Per Sft. 0.00
Page 58
42.
b) For fixed pannels without wire gauze
Lower Portion
ii) Horizontal 2x3 (1'-10") 11.00 Rft.
iv) Vertical 3x2 (4'-2") 25.12 Rft.
Total 55 Rft.
5 Screws (25 mm) for fixing 15.00 Dozen 0.00 per dozen 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
ITEM RATE
Page 60
43. Providing and fixing windows consisting of M.S. Box section frame 2"x1", leaves frame
1-"x1" Box section frame for glazing 3/8"x3/8" using 16 SWG sheet 'U' shaped rubber
supported with 1"x1/8" M.S. flat for fixing 5 mm thick glass panes M.S. box section frame
"x" of 16 SWG for fixing 24 SWG wire gauze on outer side by means of "x1/8" M.S. flat
and screws I/C all C.P. fitting and painting 3 coats complete in all respect.
12 M.S. hinges special type 3x2 (100 mm long) 6.00 Nos. 0.00 Each 0.00
13 C.P. tower bolt (225 mm long) 2.00 Nos. 0.00 Each 0.00
Total
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 63
44. Providing and fixing windows consisting of M.S. Box section frames 2"1" leaves frame
1"1" box section frame for glazing 3/8"x3/8" using 16 SWG sheet 'U' shaped rubber
supported with 1"x1/8" M.S. flat for fixing 5 mm thick glass panes M.S. box section frame
"x" of 16 SWG for fixing 24 SWG wire gauze on outer side by means of "x1/8" M.S. flat
and screws including grill of M.S. flat "x1/8" or "x" square bar with independent frame
of "x" box section of 16 SWG i/c all C.P. fitting and painting 3 coats complete in all
respect.
7 Holdfast of angle iron 1-"x1" 2.59 Kg. 0.00per Per Kg. 0.00
6x = 4.50 Rft.
Page 65
11 U' shape rubber
2x2x4-' 17.00 Rft.
2x2x1-13/16' 7.25 Rft.
2x2x21-3/8 5.50 Rft.
2x2x1-13/16 7.25 Rft.
Total 37.00 Rft.
Add 5% wastage 3.70 Rft.
Total 40.70 40.70 Rft. 0.00per Per Rft 0.00
13 M.S. hinges special type 3x2 (100 mm long) 6.00 Nos. 0.00 Each 0.00
14 C.P. tower bolt (225 mm long) 2.00 Nos. 0.00 Each 0.00
Total
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 66
45. Flapping G.I. Pipes for bathroom drains
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 67
46. Supply & Fixing iron grating for fire places
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 68
47. Fixing Copper flashing, including cutting of sheets, grooving and rivetting.
LABOUR
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Page 69
48. Providing and fixing angle Iron railing, using 2"x2"x3/8" angle iron post 4 foot long, 5' to 6'
2"x2"x3/8" angle iron top rail and two rows of M.S. flat 2"x" including fixing to side of bri
structure with "U" bolt 1' long " dia, painting etc complete in all respects.
3 1 ft. long M.S. U-Clamp 3/4" dia threaded at 5 Nos. 0.00 Each 0.00
both ends including nuts complete.
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
LABOUR
ITEM RATE
Labour Rate /Rft. Rs. - Say 0.00
Composite Rate/Rft. Rs. - Say 0.00
Page 70
49. Providing and fixing barbed wire fencing, consisting of 1"x1"3/16" angle iron post 3 ft.
long 5 to 6 ft. centre to centre embedded in cement concrete 1:4:8 base of size 9"x9"12"
and three rows of barbed wire painting posts etc complete in all respects.
Total 0.00
Contractor's Profit & O 20.00 Percent Item 1 &3 0.00
Total 0.00
LABOUR
Page 71
50. Providing and fixing barbed wire fencing on compound wall consisting of 1"x1"3/16"
angle iron post 3 ft. long 4 apart embedded in cement concrete 1:4:8 base of size 6"x6"x9"
and 4 rows of barbed wire , including binding wire, painting posts, etc. complete in all
respects.
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00 0.00
Total 0.00
LABOUR
Page 72
51 Providing and fixing all types of partly fixed and partly openable glazed anodized bronze colour a
delux section of M/s. Al-Cop or Pakistan cables boring showkhat frame of size 40mm x 100mm and lea
x 40mm wide sections i/c the cos tof 5mm thick imported tinted glass with aluminium triangular gol
to support the glass and leaf edgings using approved standard fittings, locks, 3" wide long handle
required as approved by the engineer inchrage (Follow Note Below).
MATERIAL 3
a) 1.6 mm thick
Unit = 4 x 10 = 40 Sft.
7
Cost of Material 4'x1"
3 x 4 = 12.00 Rft.
2 x 10 = 20.00 Rft.
1 x 3 3.00 Rft.
Total 35.00 Rft.
Add Wastage 10% 3.50
Total 38.50 Rft. 0.00 Rft 0.00
4 x 7 = 28.00 Rft.
2 x 4 = 8.00 Rft.
Total 36.00 Rft.
Add Wastage 5% 1.80
Total 37.80 Rft. 0.00 per No. 0.00
to 4 (2 + 3) = 20.00 Rft.
Leaver 4 x 7 = 28.00 Rft.
4 x 1.375 = 5.50 Rft.
Total 53.50 Rft.
Add Wastage 10% 5.35
Total 58.85 Rft. 0.00 per No. 0.00
Page 73
vi) Pivots 4.00 Nos. 0.00 Each 0.00
Total 0.00
B) Labour
a) Labour Charges
b) Labour for Fixing the Glass Panes 40.00 Sft. 0.00 Sft. 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent 0.00
Total 0.00
ITEM RATE
Note :
i) Increase rate by 20/- P. Sft,. If sections will be of 2mm thickness
ii) Reduce rate by 20/- P. Sft. If sections will be of dull aluminium shade
iii) Reduce rate by 20/- P. Sft if using local pain glass
Page 74
ANALYSIS OF RATE
IRON WORK
52 Providing and fixing all types of glazed aluminium windows of anodized bronze colour partly fixed and
party sliding using deluxe section of M/s. Al-Cop or Pakistan Cables having Frame of size 100mm x
20mm and leaf frame sections of 50mm x 20mm, all of 1.6mm thickness i/c 5mm thick imported
tinted glass with rubber gasket using approved standard latches, hardware etc., as approved by the
engineer incharge.
6'-0
(A) COST OF MATERIAL
@ Rs. Rs. -
c) Rubber gasket
@ Rs. Rs. -
Rs. -
B/F Rs. -
e) Latches of matching
shade 1 No. Rs. -
g) Polistevene or polisulphide
for water tight L.S Rs. -
Total Rs. -
Contractor's 20% Prof Rs. -
Total Rs. -
(B) LABOUR
Notes :
Page 76
S.No. Labour UNIT RATE
LB-001 Chowkidar Per day
LB-002 Gate Keeper Per day
LB-003 Beldar Per day
LB-004 Boatman Per day
LB-005 Bullockman Per day
LB-006 Cartman Per day
LB-007 Camelman Per day
LB-008 Donkeyman Per day
LB-009 Greaser Per day
LB-010 Oiler Per day
LB-011 Punkha Cooly Per day
LB-012 Sweeper Per day
LB-013 Sewerman Per day
LB-014 White Washer Per day
LB-015 Cooly Un-skilled (all types) Per day
LB-016 Waherman Per day
LB-017 Bahishti Per day
LB-018 Chainman Per day
LB-019 Dresser Earthwork Per day
LB-020 Head Khalasi Survey Per day
LB-021 Hammar Man Per day
LB-022 Mali Per day
LB-023 Quarryman Per day
LB-024 Skilled Cooly Per day
LB-025 Tar Sprayer Per day
LB-026 Armature Winder Per day
LB-027 Auto Electric Mechanic Per day
LB-028 Blacksmith Per day
LB-029 Carpenter Per day
LB-030 Caner Per day
LB-031 Chiseler Per day
LB-032 Denter Per day
LB-033 Driller Per day
LB-034 Driver Per day
LB-035 Electrician Per day
LB-036 Furniture Polisher Per day
LB-037 Glazier Per day
LB-038 Instrument Machanic Per day
LB-039 Machine Man Per day
LB-040 Mason Per day
LB-041 Electric Motor Winder Per day
LB-042 Moulder Per day
LB-043 Mechanic Per day
LB-044 Pettern Maker Per day
LB-045 Pipe Fitter Per day
LB-046 Plumber Per day
LB-047 Spray Painter Per day
LB-048 Sawyer Per day
LB-049 Turner Per day
LB-050 Tailor Per day
LB-051 Tin Smith Per day
LB-052 Welder Per day
LB-053 Boatman with large boat Per day
LB-054 Boatman with small boat Per day
LB-055 Bullock (each) (without attendant) Per day
LB-056 Camel (each) (without attendant) Per day
LB-057 Donkey (each) (without attendant) Per day
LB-058 Bullock Cart (without bullock & attendant) Per day
Page 1
LB-059 Camel Cart (without bullock & attendant) Per day
LB-060 Donkey or Mule Cart (without animal & attendant) Per day
LB-061 Helper Per Day
LB-062 Painter Per day
LB-063 Polisher Per day
LB-064 Foreman Per day
LB-065 Mate Per day
LB-066 Diggers Per day
LB-067 Kharkar P.Month
LB-068 Belcha men P.Month
LB-069 Gantiman (with pick axes) P.Month
LB-070 Topalies (men with donkeys for carrying earth) P.Month
LB-071 Langri (Cooks) P.Month
LB-072 Dobashi (man for supervision) P.Month
LB-073 Bullockman with pair of bullocks P.Day
LB-074 Charkhara-man P.Day
LB-075 Aluminum Technician Per Day
LB-076 Riveted Per Day
LB-077 Blowman Per Day
LB-078 Crane operator P.Day
LB-079 Hire charges of cart with Bullock & Bullock man Per Day
LB-080 Diver Sinker Per Day
LB-081 Ploughing Charges P. Acre
LB-082 Carriage Charges of RCC Pipe 4" (Class L) Per Pipe
LB-083 Carriage Charges of RCC Pipe 6" (Class L) Per Pipe
LB-084 Carriage Charges of RCC Pipe 9" (Class L) Per Pipe
LB-085 Testing Charges of RCC Pipes 4" (Class L) Per Pipe
LB-086 Testing Charges of RCC Pipes 6" (Class L) Per Pipe
LB-087 Testing Charges of RCC Pipes 9" (Class L) Per Pipe
LB-088 Carriage Charges of Non-reinforced Concrete Pipe 4"(Class I) Per Pipe
LB-089 Carriage Charges of Non-reinforced Concrete Pipe 6"(Class I) Per Pipe
LB-090 Carriage Charges of Non-reinforced Concrete Pipe 8"(Class I) Per Pipe
LB-091 Carriage Charges of Non-reinforced Concrete Pipe 9"(Class I) Per Pipe
LB-092 Carriage Charges of Non-reinforced Concrete Pipe 10"(Class I) Per Pipe
LB-093 Testing Charges of Non-reinforced Concrete Pipe 4"(Class I) Per Pipe
LB-094 Testing Charges of Non-reinforced Concrete Pipe 6"(Class I) Per Pipe
LB-095 Testing Charges of Non-reinforced Concrete Pipe 8"(Class I) Per Pipe
LB-096 Testing Charges of Non-reinforced Concrete Pipe 9"(Class I) Per Pipe
LB-097 Testing Charges of Non-reinforced Concrete Pipe 10"(Class I) Per Pipe
LB-098 Carriage Charges of RCC Pipe 12" (Class II, III & IV) Per Pipe
LB-099 Carriage Charges of RCC Pipe 15" (Class II, III & IV) Per Pipe
LB-100 Carriage Charges of RCC Pipe 18" (Class II, III & IV) Per Pipe
LB-101 Carriage Charges of RCC Pipe 21" (Class II, III & IV) Per Pipe
LB-102 Carriage Charges of RCC Pipe 24" (Class II, III & IV) Per Pipe
LB-103 Carriage Charges of RCC Pipe 27" (Class II, III & IV) Per Pipe
LB-104 Carriage Charges of RCC Pipe 30" (Class II, III & IV) Per Pipe
LB-105 Carriage Charges of RCC Pipe 33" (Class II, III & IV) Per Pipe
LB-106 Carriage Charges of RCC Pipe 36" (Class II, III & IV) Per Pipe
LB-107 Carriage Charges of RCC Pipe 42" (Class II, III & IV) Per Pipe
LB-108 Carriage Charges of RCC Pipe 48" (Class II, III & IV) Per Pipe
LB-109 Carriage Charges of RCC Pipe 54" (Class II, III & IV) Per Pipe
LB-110 Carriage Charges of RCC Pipe 60" (Class II, III & IV) Per Pipe
LB-111 Carriage Charges of RCC Pipe 66" (Class II, III & IV) Per Pipe
LB-112 Carriage Charges of RCC Pipe 72" (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 12"
LB-113 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 15"
LB-114 (Class II, III & IV) Per Pipe
Page 2
Carriage Charges of Non-reinforced Concrete Pipe 18"
LB-115 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 21"
LB-116 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 24"
LB-117 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 27"
LB-118 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 30"
LB-119 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 33"
LB-120 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 36"
LB-121 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 42"
LB-122 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 48"
LB-123 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 54"
LB-124 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 60"
LB-125 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 66"
LB-126 (Class II, III & IV) Per Pipe
Carriage Charges of Non-reinforced Concrete Pipe 72"
LB-127 (Class II, III & IV) Per Pipe
Page 3
CHAPTER NO. 14
LINING OF CANAL
a) In Bed.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Rate Analyses for 125 Sft
Dresser 0.33 No P. Day -
Unskilled Cooly 0.77 No P. Day -
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Sft Rs. Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Page 1
Item No. 1 Formation, dressing and preparing sub-grade.
b) On Slope.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Rate Analyses for 125 Sft
Dresser 0.50 No P. Day -
Unskilled Cooly 1.00 No P. Day -
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Sft Rs. Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Page 2
DESCRIPTION OF ITEM NO 2: Stabilized layer of cement sand ratio 1:30 2"
(50mm) thick on slope.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Rate Analyses for 125 Sft
Mason 0.50 No P. Day -
Unskilled Cooly 1.50 No P. Day -
Bahishti 0.50 No P. Day -
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Sft Rs. Say -
Labour Rate for 1 Sqm Rs. Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Page 3
DESCRIPTION OF ITEM NO 3: Cement plaster " (12mm) thick, ratio 1:10.
a) In Bed.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Rate Analyses for 125 Sft
Mason 0.33 No P. Day -
Unskilled Cooly 1.00 No P. Day -
Bahishti 0.50 No P. Day -
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Sft Rs. Say -
Labour Rate for 1 Sqm Rs. Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Page 4
Item No. 3 Cement plaster " (12mm) thick, ratio 1:10.
b) On Slope.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Rate Analyses for 125 Sft
Mason 0.50 No P. Day -
Unskilled Cooly 1.25 No P. Day -
Bahishti 0.50 No P. Day -
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Sft Rs. Say -
Labour Rate for 1 Sqm Rs. Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Page 5
DESCRIPTION OF ITEM NO 4: Cement plaster 3/8"(10mm) thick, ratio 1:3
a) In Bed.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Rate Analyses for 125 Sft
Mason 0.33 No P. Day -
Unskilled Cooly 1.00 No P. Day -
Bahishti 0.50 No P. Day -
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Sft Rs. Say -
Labour Rate for 1 Sqm Rs. Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Page 6
Item No. 4 Cement plaster 3/8"(10mm) thick, ratio 1:3.
b) On Slope.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Rate Analyses for 125 Sft
Mason 0.50 No P. Day -
Unskilled Cooly 1.25 No P. Day -
Bahishti 0.50 No P. Day -
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Sft Rs. Say -
Labour Rate for 1 Sqm Rs. Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Page 7
DESCRIPTION OF ITEM NO 5: Cement plaster 1" (40mm) thick, ratio 1:6.
a) In Bed.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Sft Rs. Say -
Labour Rate for 1 Sqm Rs. Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Page 8
Item No. 5 Cement plaster 1" (40mm) thick, ratio 1:6.
b) On Slope.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Sft Rs. Say -
Labour Rate for 1 Sqm Rs. Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Page 9
DESCRIPTION OF ITEM NO 6: Tile lining (12"x6"x2") (300x150x50mm) in 1:6
cement sand mortar.
a) In Bed.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Per
Brick Tiles ###### Nos 1000 Nos
Cement 3.44 Bag P. Bag -
Sand 25.70 Cft Cft -
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Mason 2.50 No -
Unskilled Cooly 5.00 No -
Bahishti 0.75 No -
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying tiles over 1/8" (6mm) thick layer of 1:6 mortar items 1 to 5
above are payable separately.
Page 10
Item No. 6 Tile lining (12"x6"x2") (300x150x50mm) in 1:6
cement sand mortar.
b) On Slope.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying tiles over 1/8" (6mm) thick layer of 1:6 mortar items 1 to 5
above are payable separately.
Page 11
DESCRIPTION OF ITEM NO 7: Tile lining (12"x6"x2") (300x150x50mm) in 1:3
cement sand mortar.
a) In Bed.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying tiles over 1/8" (6mm) thick layer of 1:3 mortar items
1 to 5 above are payable separately.
Page 12
Item No. 7 Tile lining (12"x6"x2") (300x150x50mm) in 1:3
cement sand mortar.
b) On Slope.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying tiles over 1/8" (6mm) thick layer of 1:3 mortar items
1 to 5 above are payable separately.
Page 13
DESCRIPTION OF ITEM 8: Brick lining (9"x4"x3") (225x114x75mm) in
1:6 cement sand mortar.
a) In Bed.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:6 mortar items
1 to 5 above are payable separately.
Page 14
Item No. 8 Brick lining (9"x4"x3") (225x114x75mm) in
1:6 cement sand mortar.
b) On Slope.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:6 mortar items
1 to 5 above are payable separately.
Page 15
DESCRIPTION OF ITEM No 9: Brick lining (9"x4"x3") (225x114x75mm) in
1:3 cement sand mortar.
a) In Bed.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:3 mortar items
1 to 5 above are payable separately.
Page 16
Item No. 9 Brick lining (9"x4"x3") (225x114x75mm) in
1:3 cement sand mortar.
b) On Slope.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:3 mortar items
1 to 5 above are payable separately.
Page 17
DESCRIPTION OF ITEM NO 10: Cement concrete lining, using washed screened
and graded stone aggregate.
a) In Bed.
i) Ratio 1:2:4
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Page 18
Item No. 10 Cement concrete lining, using washed screened
and graded stone aggregate.
a) In Bed.
ii) Ratio 1:3:6
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Page 19
Item No. 10 Cement concrete lining, using washed screened
and graded stone aggregate.
a) In Bed.
iii) Ratio 1:4:8
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Page 20
Item No. 10 Cement concrete lining, using washed screened
and graded stone aggregate.
b) On Slope.
i) Ratio 1:2:4
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Page 21
Item No. 10 Cement concrete lining, using washed screened
and graded stone aggregate.
b) On Slope.
ii) Ratio 1:3:6
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Page 22
Item No. 10 Cement concrete lining, using washed screened
and graded stone aggregate.
b) On Slope.
iii) Ratio 1:4:8
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ov ## Percent -
Total -
Labour
Total -
Sundries ## Percent -
Total -
Item Rates
Labour Rate for 100 Cft Rs. - Say -
Labour Rate for 1 Cum Rs. - Say -
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Page 23
CHAPTER NO. 2
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Bricks
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 1
DESCRIPTION OF ITEM NO 2: Loading or unloading bricks into or from Railway
Wagons laid and stacked lead within one chain.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Bricks
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 2
Item No. 2 Loading or unloading bricks into or from Railway
Wagons laid and stacked lead within one chain.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Bricks
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 3
DESCRIPTION OF ITEM NO 3: Loading or unloading into or from Railway
Wagons cement in bags (from inside or outside
the go-down) and stacking within one chain.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Bags
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 4
DESCRIPTION OF ITEM NO 4: Loading or unloading into of from Railway
Wagons empty cement bags (from inside or
outside the go-down) and stacking.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos.
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Labour Rate Per 100 Nos Rs. 0.00 0.00 Say 0.00
125
Page 5
DESCRIPTION OF ITEM NO 5: Loading or unloading into or from Railway
Wagons (from inside or outside the go-down) and
stacking white lime in bags.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Mds
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 6
DESCRIPTION OF ITEM NO 6: Loading or unloading into or from Railway
Wagons structural steel, joists, broad, narrow or
meter gauge rail and rail fastening etc.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Ton
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 7
DESCRIPTION OF ITEM NO 7: Loading or unloading 45 gallons drum full into
or from Railway Wagons lead upto one chain.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 8
DESCRIPTION OF ITEM NO 8: Loading or unloading packages or stock of all
sorts upto I cwt. except cement in jute or paper
bags.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 9
DESCRIPTION OF ITEM NO 9: Loading or unloading sleepers other than wooden
including stacking lead within one chan in.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos.
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 10
Item No. 9 Loading or unloading sleepers other than wooden
including stacking load within one chan in.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 11
DESCRIPTION OF ITEM NO 10: Loading or unloading timber logs or timber for
shuttering into or from Railway Wagons of any
gauge including stacking, lead within one chain.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 20 Ton
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 12
DESCRIPTION OF ITEM NO 11: Loading or unloading bhoosa in Railway Wagons
lead upto 150 feet.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Mds
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 13
DESCRIPTION OF ITEM NO 12: Loading or unloading timber scrap or wooden
plugs into or from Railway Wagons and stacking
within one chain lead.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1.25 Ton
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 14
DESCRIPTION OF ITEM NO 13: Loading or unloading pitching stone or spawl
from Railway Wagons of any gauge (including
clearing 5 feet away from the rail)
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft.
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 15
DESCRIPTION OF ITEM NO 14: Loading or unloading building stone (including
clearing 5 feet away from rails)
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft.
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 16
DESCRIPTION OF ITEM NO 15: Unloading oil, bitumen tar etc.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Gallons
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 17
Item No. 15 Unloading oil, bitumen tar etc.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Gallons
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 18
Item No. 15 Unloading oil, bitumen tar etc.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 19
Item No. 15 Unloading oil, bitumen tar etc.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 45 Ton
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 20
Item No. 15 Unloading oil, bitumen tar etc.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 21
Item No. 15 Unloading oil, bitumen tar etc.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 22
DESCRIPTION OF ITEM NO 16: Removing and stacking within one chain lead.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 23
Item No. 16 Removing and stacking within one chain lead.
b) Bricks
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 15,000 Nos
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 24
Item No. 16 Removing and stacking within one chain lead.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 2,500 Nos
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 25
Item No. 16 Removing and stacking within one chain lead.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 4,200 Nos
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 26
Item No. 16 Removing and stacking within one chain lead.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 90 Ton
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 27
Item No. 16 Removing and stacking within one chain lead.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 750 Nos
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 28
DESCRIPTION OF ITEM NO 17: Loading into Wagons Girders, Rails, permanent
way material (except wooden sleepers) iron work,
M.S. Bars, Pipes, etc. including lead one chain
and stacking inside Wagons.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 40 Ton
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 29
DESCRIPTION OF ITEM NO 18: Unloading from Wagons Girders, Rails,
permanent way material (except wooden sleepers)
iron work, M.S. Bars, Pipes, etc. lead upto one
chain but excluding stacking.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 70 Ton
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 30
DESCRIPTION OF ITEM NO 19: Loading into Wagons, wooden broad gauge
sleepers including one chain lead and stacking.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1,000 Nos
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 31
DESCRIPTION OF ITEM NO 20: Unloading wooden broad gauge sleepers from
Wagons including one chain lead and stacking.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 2,100 Nos
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 32
DESCRIPTION OF ITEM NO 21: Loading metre gauge or narrow gauge wooden
sleepers including one chain lead and stacking
inside Wagons.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 2,000 Nos
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 33
DESCRIPTION OF ITEM NO 22: Unloading metre gauge or narrow gauge wooden
sleepers including one chain lead but excluding
stacking
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 3,800 Nos
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 34
DESCRIPTION OF ITEM NO 23: Loading Bridge and grossing timber including
one chain lead and stacking.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 35
DESCRIPTION OF ITEM NO 24: Unloading Bridge and crossing timber including
one chain lead but excluding stacking.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
NOTE :
Rate for loading and unloading for Mobile trucks/ boats, item 1-15 will be 80%
of the rate of Railway Wagons.
Page 36
DESCRIPTION OF ITEM NO 25: Loading or unloading bitumen, asphalt or tar in
drums, into or from Railway Wagons lead upto
one chain.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 25 Ton
Labour
Total -
Sundries #### Percent -
Total -
Item Rates
Page 37
LIST OF LUMPSUM ITEMS-1
Page 1
LIST OF LUMPSUM ITEMS-1
Page 2
LIST OF MATERIAL
ITEM MATERIAL UNIT RATE
01.001Cotton waste Per Kg
01.002Grease Per Kg
01.003H.S. Diesel oil Per Ltr.
01.004Kerosine oil Per Ltr.
01.005Mobil oil Per Ltr.
01.006Average diesel consumption of a truck miles/gallon
01.007Average mobile oil consumption of a truck miles/gallon
03.001Gun powder and fuse for blasting (1 pound and 1 fuse) Each
03.002Jhambs Each
03.003Charakharies complete Each
03.004Manila Rope 1" Rft
03.005Cost of repair and replacement of 4 Nos. picks axes and 8 No Per Day
03.006Palana with namda for one donkey Each
03.007Repair and replacement of sacks Each
03.008Tent Each
03.009Donkey hut Each
03.010Royalty for pit sand % Cft
03.011Nail bolts and nuts Kg.
03.012Atta P.Kg.
03.013Phak per Md
03.014Grams per Md
06.001Brick Ballast 1" (at site) 100 Cft
06.002Brick Ballast 1" to 1" (at site) 100 Cft
06.003Stone Ballast 1" to 1" (at source) 100 Cft
06.004Brick Bats 100 Cft
06.005Coarse sand (Chenab) (at site) 100 Cft
06.006Harrow/Sand (at site) 100 Cft
06.007Sand (Local) (at site) 100 Cft
06.008Cement (Grey) Per Bag
06.009Cement (White) Per Bag
06.010Shingle (Naturally Graded) at site (Bajri) 100 Cft
06.011Aggregate/Stone Crushed " to 1" (Graded) (at site) 100 Cft
06.012M.S. Bars (Plain) " and above (36000 PSI) M. Ton
06.013M.S. Bars (Deformed) (40 grade) M. Ton
06.014M.S. bars (Tor Steel 60 grade) M. Ton
06.015Cost of casing pipe of 18" dia Per Rft
06.016Cost of casing pipe of 20" dia Per Rft
06.017Cost of casing pipe of 22" dia Per Rft
06.018Cost of casing pipe of 24" dia Per Rft
06.019Nail and Screw (Copper) Per. Kg.
06.020Brush (Large) Each
06.021Brush (Small) Each
06.022Binding wire Kg
06.023Special Clamps with bolts and nuts Each
06.024Welding electrode P.Bundle
06.025Prestressing Cable having 12 Nos. wire P.Ton
06.026Anchorage cone per set
06.027Corrugated sheath of 1-9/16" for 12/0.276" (7mm) cable per metre
06.028Making good recesses Each end
06.029Steel rope 1" Rft
06.030U Clamp i/c 5/8" bolts & nuts each
06.031Steel rope " dia Rft
06.032Railway track including sleepers bolts & nuts complete Rft
06.033Crow bar Each
06.034Aluminum powder per kg
06.035Aluminum sheet 1/16" to 1/8" (1.6 to 3 mm) thick per kg
06.036Helical core (compressed for 10 tons) per metre
06.037G.I. Sheet special "V shaped " each
06.038Mastic strip P.Rft
06.039Copper flashing 1/16" thick P.Sft
06.040Rubber water stopper 10" wide and 1/4" thick P.Rft
06.041Bitumen P.Kg.
06.042Sawdust P.Cft
06.043Wood for heating P.Kg.
06.044Thermopore sheet 1" (40 mm) thick m
06.045Thermopore sheet 1" (25 mm) thick m
06.046Polythene @ 1.13 kg % Sft P.Kg.
06.047Broken glass % kg
07.001Ist class bricks 9" x 4" x 3" (225 x 112.5 x 75 mm) %o Nos.
07.002Fire Clay Bricks 225 x 112.5 x 75 mm Each
07.003Good earth/clay 100 Cft
07.004Fire resistant cement 0 Kg per bag
Page 1
ITEM MATERIAL UNIT RATE
07.005Moulded Special bricks 9" x 4" x 3" %o Nos.
07.006Sun dried bricks %o Nos.
07.007Lime (Slaked) Kg
07.008Lime (Unslaked) Kg
07.009Brick grinded and sand Cft
07.010Hoop Iron Per Kg.
08.001Quarried Stone at source 100 Cft
08.002Headers or through stone (1.5" x 8" x 10") Each
08.003Pitching stone at source % Cft
08.004Charcoal Per Kg
08.005Wood preservative (Heptaclore) Per Ltr.
08.006Steel Per Kg.
08.007Hand dressed stone average (2 Cft) Each
08.008Hand dressed stone average (4 Cft.) Each
09.001Brick tiles 300 x 150 x 50 mm (12"x6"x2" ) %o Nos.
1
09.002 Brick tiles 300 x 150 x 40 mm 12"x6"x1 /2") %o Nos.
09.003Brick tiles 300 x 150 x 32 mm (12"x6"x1" ) %o Nos.
09.004 Brick tiles 225 x 112.5 x 50 mm (9"x41/2"x2") %o Nos.
09.005Brick tiles 225 x 112.5 x 40 mm (9"x41/2"x1") %o Nos.
09.006G.I. Plain Sheet 18 - 20 SWG Per kg
09.007G.I Plain Sheet 22 - 24 SWG Kg
09.008G.I. Corrugated sheet 18 - SWG Per Kg
09.009G.I. Corrugated sheet 22 - 24 SWG Per Kg
09.010G.I. Corrugated sheet 20 SWG Per Kg
09.011G.I. Hook, Nuts and Bolts Doz
09.012G.I. Washers Per Kg
09.013Washers Limpet Per Dozen
09.014Bhoosa Kg
09.015Pig lead Kg
09.016Cowdung (wet) % Kg
09.017A.C. T-bend 100 mm Each
09.018A.C. Shoe 100 mm Each
09.019A.C. Ridge Sheet (6mm) Rft
09.020Fuel wood Per Kg.
09.021Wire Nails Per Kg.
09.022Wind tie (rod) P Kg.
09.023Bitumen washers Doz
09.024Brick Aggregate P. Cft
09.025Lead flashing 1/16" thick P. Sft
09.026C.I. Heads 4" Each
09.027Clamps with hold fasts etc. (For Rain Water Pipe) Each
09.028C.I. water down pipe 4" (100mm) dia P. Rft
09.029C.I. water down pipe down 3" (75mm) dia P. Rft.
09.030C.I. shoes bend or offsets 4" Each
09.031Corrugated A.C. sheets P.Sft
09.032G.I. or limpet washers and bitumastic washers Doz
09.033Wrought iron bracket complete with bolts, Nuts and rivets et Each
09.034Polythene 0.03" (0.08 mm) Pr. Kg.
09.035Thermopore " (12mm) thick Per Sft.
09.036Thermopore " (19mm) thick Per Sft.
09.037Thermopore 1" (25mm) thick Per Sft.
09.038A.C. pipe 4" (100mm) dia P.Rft
09.039U.I. Clips Kg.
09.040Screws 3" & 2" Kg.
10.001Murrum powder fine. % Cft
10.002Cement concrete tiles 200 x 200 x 20 mm (8" x 8" x ") Each
10.003Cement Concrete tiles 300 x 300 x 25 mm (12" x 12" x 1") Each
10.004Cement Concrete tiles 225 x 225 x 20 mm (9" x 9" ") Each
10.005Cement concrete tiles 150 x 150 x 20 mm (6" x 6" x ") Each
10.006White Tile (Glazed) 6"x6"x" Each
10.007Coloured Glazed tiles 150 x 150 x 6 mm (6" x 6" x ") Each
10.008Coloured Glazed tiles 300 x 300 x 6 mm (12" x 12" ") Each
10.009Mosaic marble chips tiles300 x 300 x 25 mm (12" x 12" x 1") Each
10.010Rubber tiles 300 x 300 x 3 mm (12" x 12" x 1/8") Each
10.011White glazed tiles 300 x 300 x 6mm (12" x 12" x ") Each
10.012Dressed Stone 2'x2'x2" Each
10.013Dressed Stone 2'x2'x3" Each
10.014Carborandum Stone Each
10.015Pigment for Cement/Concrete Per Kg
10.016Marble Chips Per Kg
10.017Marble Powder 100 Kg
10.018Neoprene strip 100 x 6 mm P. Foot
10.019Wax Polish 3 Kg.
Page 2
ITEM MATERIAL UNIT RATE
10.020Tartaric Acid Per Kg
10.021Hessian Cloth Per Mtr.
10.022Linen Cloth P. Kg.
10.023Asphalt P. Kg.
10.024Sand Paper Per Doz.
10.025Brass Screws 50 mm long Per Doz.
10.026Glass stip 3 mm thick 40 mm wide % Rft
10.027Glass Strips 4 mm thick 40 mm wide % Rft
10.028Glass Strips 5 mm thick 50 mm wide % Rft
10.029Marble strips 6 mm thick 40 mm wide Rft
10.030Marble strips 10 mm thick 40 mm wide Rft
10.031Sutli Per Kg
10.032Steam coal Kg
10.0339" thick rubble or broken hard bricks %Cft.
10.034Hard Marrum %Cft.
10.035Floor Polish P. Kg.
10.036Adhesive Mixture dry Per Kg.
10.037Surkhi P. % Cft.
10.038Fine Aggregate % Cft.
10.039Primer P.Kg.
11.001Chopped Jute Per Kg
11.002Distemper (Vinyle Emulsion) Per Gallon
11.003Distemper Plastic bound (Plastic Emulsion) Per Gallon
11.004Distemper Water bound Per Gallon
11.005Rice Per Kg
11.006Pigment for colour wash Per Kg
11.007Primer/red oxide pigment Per Gln.
11.008Chopped Straw P.Kg
11.009Expended metal edge bead 5" wide P. Rft
12.001Chir Ist Class CFT
12.002Deodar Wood best quality CFT
12.003Deodar Wood 2nd class CFT
12.004Fire Wood Kg
12.005Kail Ist class CFT
12.006Shisham wood Ist class CFT
12.007Teak wood CFT
12.008Partal wood CFT
12.009Kikar wood CFT
12.010Sheets Aluminum 8 - SWG - 24 SWG (local) Per Kg
12.011Sheets Aluminum " thick and above (local) Per Kg
12.012Copper sheet 0.80 mm to 2.50 mm Per Kg
12.013Copper sheet 3.00 mm to 6.00 mm Per Kg
12.014Formica sheet (8' x 4') Per sheet
12.015Plain Galvanized iron sheet Per Kg
12.016Corrugated Galvanized iron sheet Per Kg
12.017Commercial ply 6 mm thick SFT
12.018Commercial ply 3 mm thick SFT
12.019Shisham wood ply (6 mm thick) SFT
12.020Teak wood ply (6 mm thick) SFT
12.021Thermopore sheet " (12 mm) thick 20 kg/m (39" x 39") P. sheet
12.022Thermopore sheet " (20 mm) thick 20 kg/m (39" x 39") P. sheet
12.023Thermopore sheet 1" (25 mm) thick 20 kg/m (39" x 39") P. sheet
12.024Masonite sheet 5 mm thick for partitions P. Sft
12.025Masonite Sheet for ceiling P.Sft
12.026Bacolite sheet (2.50 mm) thick (size 4' x 4') eet 4'x4' size
12.027Bacolite sheet (3.75 mm) thick (size 4' x 4') eet 4'x4' size
12.028Bacolite sheet (4.00 mm) thick (size 4' x 4') eet 4'x4' size
12.029Rubber sheet 5 mm (size 4' x 6') eet 4'x6' size
12.030Zinc Plate 525 x 11 mm Kg
12.031Spike Per Kg
12.032Glass pan 3 mm thick 16 x to 18 oz SFT
12.033Glass pan 3 mm thick 24 x to 26 oz SFT
12.034Glass plate " (6 mm) thick upto 8 SFT SFT
12.035Glass plate " (6 mm) thick not exceeding 24 SFT SFT
12.036Glass Plate 6 mm thick SFT
12.037Glass Plate 8 mm SFT
12.038Glass Plate " (12 mm) thick PSF
12.039Glue Per Kg
12.040Machine Screws 38.10 x 7.35 mm Per Doz.
12.041Iron strips 1" x 1/8" Kg
12.042Brass finger plate Each
12.043Brass hinges 50 mm Each
12.044Brass hinges 63 mm Each
Page 3
ITEM MATERIAL UNIT RATE
12.045Brass hinges 75 mm Each
12.046Brass hinges 100 mm Each
12.047Brass hinges 125 mm Each
12.048Brass tower bolts 300 mm Each
12.049Brass tower bolts 225 mm Each
12.050Brass tower bolts 200 mm Each
12.051Brass tower bolts 150 mm Each
12.052Steel nut and bolts (all sizes) Per Kg
12.053Iron hold fast (for doors/windows) Each
12.054Iron handle 100 mm 4" Each
12.055Iron handle 150 mm (6") Each
12.056Iron handle 200 mm (8") Each
12.057Brass handle 100 mm Each
12.058Brass handle 150 mm Each
12.059C.P. handles 4" (2nd Quality) Rft
12.060C.P. handles 4" Each
12.061C.P Handle 6" P.Doz
12.062C.P. handles 6" (Best Quality) Each
12.063Handle Each
12.064Iron sliding bolt 200 mm (8") with screws Each
12.065Iron sliding bolt 250 mm (10") with screws Each
12.066Iron sliding bolt 300 mm (12") with screws Each
12.067Racal plugs 1" (40mm) long Each
12.068Racal Plug (small) Each
12.069Push plate (Stainless) Each
12.070Kikai plate (Aluminum) 4" wide 22 gauge 12" long Each
12.071Rim lock (China) Each
12.072Mortise lock (Local) Each
12.073Sliding bolts Brass 300 mm (12") Each
12.074Hinges (Iron) 50 mm Each
12.075Hinges (Iron) 75 mm Each
12.076Hinges (Iron) 100 mm Each
12.077Hinges (Iron) 125 mm Each
12.078Double action spring Hinges (Brass) Medium 4" - 5" (100 to 1 Per pair
12.079Double action spring Hinges (Iron) 4"-5" (100 to 125 mm) Each set
12.080Brass screw 20 mm Doz.
12.081Brass screw 25 mm Doz.
12.082Brass screw 40 mm Doz.
12.083Door Stops 150 mm Each
12.084Door stopper 150 mm (wooden) Each
12.085Foot hinges 1" Each
12.086Tee hinges 250 mm Each
12.087Tee hinges 150 mm Each
12.088Tee hinges 200 mm Each
12.089Butt Hinges (125mm) Each
12.090Butt Hinges (150mm) Each
12.091Hasp & staples (medium size) Each
12.092Iron tower bolt 100 mm long Per Doz.
12.093Iron tower bolt 150 mm long Per Doz.
12.094Iron tower bolt 225mm long Per Doz.
12.095Iron tower bolt 250 mm long Per Doz.
12.096Iron tower bolt 300 mm long Per Doz.
12.097Hold fast with pivot & clamp 4" Each
12.098Hold fast with pivot & clamp 6" Each
12.099Hold fast with pivot & clamp 8" Each
12.100spring hinges (doors/windows) Each
12.101Wrought Iron Hold Fast (small) Each
12.102Wrought Iron Hold Fast (Large) Each
12.103Deodar wooden beading (1" x ") Rft
12.104Deodar wooden lipping 6 mm Rft
12.105Deodar wooden lipping 3/8 Rft
12.106Chord with hook (" x ") Each
12.107Wooden cleat for door Each
12.108G.I. hook with clamp (doors/windows) Each
12.109Khunda - Chapka (For Almirah) Each
12.110Rubber Pad Stopper Each
12.111Wire Gauze (12x12) Sft.
12.112Wooden Plug for door Each
12.113Expended Metal (12mm to 20mm mesh of 16 gauge) Sft.
12.114Hinges 10" (250mm) Each
12.115Hinges chocks 4" (100mm) (for battened doors) Each
12.116Hasp and staple Each
12.117Hold fast with pivots & clamp for framed and braced doors Each
Page 4
ITEM MATERIAL UNIT RATE
12.118Sliding bolts 18" (450mm) long Each
12.119M.S. Angle Iron 1"x1"x" (40x40x6mm) P.Kg.
12.120M.S. Flat 6"x"x1/8" (150x6x3mm) P.Kg.
12.121Hinges Chocks 3" (75mm) Each
12.122Screws upto 1" long Doz
12.123Screws above 1" long Per Doz.
12.124Nails of sorts Pr. Kg.
12.125Brass spring hinges Complete with Screws Each
12.126Brass sliding bolt 10" (250mm) long 'complete with screws & Each
12.1271" (25mm) thick solid flush shutter Sft.
12.128Solid flush door 1" thick Sft.
12.129C.P. dasti I/C screws Each
12.130Hard Board Sft
12.131Brass butt hinges 2" (50mm) Each
12.132Brass butt hinges 6" (150mm) Each
12.133Sawing Charges Sft
12.134Tie rod welding and fixing arragement Each
12.135Vin board " thick Sft.
12.136Vin board " thick Sft.
12.137Chip Board " (20mm) 700 density P.Sft
12.138Chip Board " (12mm) 700 density P.Sft
12.139Full hinges " (20mm) wide (Imported) Rft
12.140Catcher Each
12.141lock China Each
12.142C.P. Hanger rod with 2 hooks Each
12.143Hanger hook including pull out rod Each
12.144Brass hooks Each
12.145Door rubber stopper Each
12.146G.I. Hook Each
12.147Hooks forPunkha Pole Per Dozen
12.148Nails P.Kg.
12.149Washers Each
12.150Hard Wood Gutty Each
12.151M.S clamp Each
12.152M.S hook Each
12.153Sand Paper Each
12.154Tower bolt C.P. Each
12.155C.P. finger plate with screws Each
12.156M.S. sheets (plain) 20 SWG Kg
12.157M.S. Sheet 18 SGW Sft
12.158M.S. Sheet 22 SGW Sft
12.159Curtain Railing Rft.
12.160Electrod Pkt
12.161Gola (Wood) P. Ft.
13.001Black Japan paint Gln.
13.002Chalk powder Per Kg
13.003Dana Lakh Per Kg
13.004Emulsion paint Per Gallon
13.005Paint Enamel P. Gln
13.006French Polish Per Kg
13.007Gum and Gun rasin Per Gallon
13.008Linseed oil Per Kg
13.009Road marking enamel Per Ltr.
13.010Solignum paint (Imported) Per Gallon
13.011Spirit Per Ltr.
13.012Varnish Kg
13.013White Enamel paint Per Gln.
13.014Caustic Soda Kg
13.015Painting Brushes (average rate) Each
13.016Mineral Pitch Kg
13.017Primer Paint P.Gln
13.018Reflective Paint P. Gln
13.019Reflective Tape/Paper P. Sft.
13.020Creosote P. Gln
13.021Steel Scrapper Each
13.022Kerosine Oil Litre
13.023Terpentine oil Per Ltr.
13.024Water Proofing Emulsion Paint P.Kg.
16.001Jute bag (Empty) (1.25 Cft.) Each
16.002New jute bag (4 to 5 Cft.) Each
16.003Pitching Stone % Cft
16.004Munj patha ban Per Kg
16.005G.I Wire No.15 Per Kg
Page 5
ITEM MATERIAL UNIT RATE
16.006Bamboo (60 - 120 mm dia) 2.5 meter to 3.0 metre long Each
16.007Bamboo (60 - 120 mm dia) 3.0 meter to 3.75 metre long Each
16.008Bamboo (60 - 120 mm dia) 3.75 meter to 4.25 metre long Each
16.009Bamboo (60 - 120 mm dia) 4.25 meter to 4.90 metre long Each
16.010Bamboo (60 - 120 mm dia) 4.90 meter to 6.25 metre long Each
16.011G.I Wire No. 8 to 10 Per Kg
16.012Sutli P.Kg
16.013wooden vertical stakes 7" to 12" dia for groynes P. % Nos.
16.014Royality charges of wooden stakes Each
16.015Shingle / spawl P.% Cft
16.016Boulder P.% Cft
16.017Supply pilchi lead within one mile P.% Cft
16.018Pilchi Roll 6" dia 5' long P.% Cft
16.019Bajri / shingle P.% Cft
16.020Royality kikar brush wood P.% Mds
16.021Kikar wood for pegs P. Cft
18.001Course aggregate (bajri) for surface dressing (Quarry site) 100 Cft
18.002Graded stone for base course (Quarry site) 100 Cft
18.003Brick Aggregate For Sub Base course (Quarry site) 100 Cft
18.004Pit-run/Bedrun graval (Quarry site) 100 Cft
18.005Stone screaned (Crusher site) 100 Cft
18.006Stone Dust (Quarry/Plant site) 100 Cft
18.007Steel bars (including binding wire) Per Kg.
18.008Iron post Per Kg
18.009Elbow 2" Each
18.010Tee 2" x 2" x 2" Each
18.011Steel bearing (standard quality) Each
18.012Rubber bearing pad 1" x 1" x 1" (2.5x2.5x2.5 cm) P.Cub
18.013A.C pipe 3" i/d per metre
18.014T.Iron and M.S Plate P. Kg.
18.015Lettering 4" height Each
18.016Lettering 3" height Each
19.001Cast iron head 4" Per Kg
19.002Cast iron shoe 4" Per Kg
19.003Cast iron bend 4" Per Kg
19.004Cast iron off set 4" Per Kg
19.005G.I spout 4" 460 mm long Each
19.006AC - bend 4" (100 mm) Each
19.007AC Shoe 4" (100 mm) Each
19.008AC Tee (100 mm) Each
19.009Angle Iron Bracket Set for W.H.B & Cistern Each
19.010'Angle Iron Bracket Set for Sink Each
19.011Waste pipe 3 cm (1") (PVC) Each
19.012Waste pipe 4 cm (1") (PVC) Each
19.013C.P. waste coupling 3 cm (1") Each
19.014C.P. waste coupling 4 cm (1") Each
19.015Rubber plug with chain 3 cm (1") Each
19.016Rubber plug with chain 4 cm (1") Each
19.017PVC Flushing bend 3 cm (1") Each
19.018PVC Flushing bend 4 cm (1") Each
19.019Plastic rubber connection with check nut Each
19.020Copper connectionn with check nut: Each
19.021C.P. Shower rose 1.5 x 10 cm (" x 4") Each
19.022C.P. Shower rose 2.0 x 15 cm (" x 6") Each
19.023C.I brackets for high level flushing cistern Per pair
19.024C.I. Bracket for Wash hand basin Each
19.025White Glazed earthen ware low down cistern 13.63 ltr. (3/Gln Each
19.026Coloured Glazed earthen ware low down cistern 13.63 ltr. (3/ Each
19.027White Glazed cast iron low down cistern 13.63 ltr. (3/Gln) Each
19.028RCC Pipe 4" dia Rft.
19.029Plastic made low down flushing cistern 13.63 litre (3 gallo Each
19.030Pedestal for W.H.B Each
19.031Bolt and Nuts for W.C. (European Type) Each
19.032A.C soil pipe 6cm (2" dia) Metre
19.033A.C soil pipe 7.5cm (3" dia) Metre
19.034A.C soil pipe 10cm (4" dia) Metre
19.035A.C soil pipe 15cm (6" dia) Metre
19.036C.I. Soil Down 50 mm (2") dia Metre
19.037C.I Soil Down 100 mm (4") dia (30 PSI) Metre
19.038Yarn per lbs
19.039Chromium plated T-stop cock 1.5 c.m (") Each
19.040Brass gas cock 1.5 c.m (") Each
19.041Brass gas cock 2.0 c.m (") Each
Page 6
ITEM MATERIAL UNIT RATE
19.042Brass bib cock " (1.5 cm) Each
19.043Brass bib cock " (2 cm) / brass stop cock Each
19.044Glazed Earthenware sink 60 x 45 cm (24" x 18") Each
19.045Glazed Earthenware sink 37.5 x 45 cm (15" x 18") Each
19.046Statinless steel sink with drain board 120 x 60 cm (48 x 24 Each
Terazzo concrete sink 60 x 45 cm (24" x 18") With drain
19.047 Each
board
19.048Brass ball float valves 15 mm (") dia Each
19.049Brass ball float valves 20 mm (") dia Each
19.050Brass ball float valves 25 mm (1") dia Each
19.051Brass ball float valves 30 mm (1") dia Each
19.052Brass ball float valves 40 mm (1") dia Each
19.053Brass ball float valves 50 mm (2") dia Each
19.054C.P. Mixing Valves " dia (Mixer) Each
19.055Glass Shelf 60 x 13 cm (24" x 5") Each
19.056Chromium plated bracket and railling for glass shelf Each
Glazed earthen ware shelf 60 x 13 cm (24" x 5") with
19.057 Each
chromium plated bracket and railing (Coloured)
Glazed earthen ware shelf 60 x 13 cm (24" x 5")
19.058 Each
withchromium plated bracket and railing (White)
19.059Soap dish chromium plated Each
19.060Soap dish glazed earthen ware white colour Each
19.061Soap dish plastic Each
19.062Toilet Paper Holder (Chromium plated) Each
19.063Toilet Paper Holder (Plastic) Each
19.064Towel Rail With Brackets (Chromium plated) 60 x 2 cm (24" x Each
19.065Towel Rail With Brackets (Chromium plated) 50 x 1.5 cm (20" Each
19.066Towel Rail With Brackets (Plastic) Each
19.067C.I floor trap including grating size 10 x 5 cm (4" x 2") Each
19.068Chromium plated bottle trap 3 cm (1") (with waste pipe) Each
19.069Chromium plated bottle trap 4 cm (1") (with waste pipe) Each
19.070Cast iron P-trap 10 cm (4") Each
19.071Concrete gully trap 4" Each
19.072Glazed Pee trap 10 cm (4" dia) Each
19.073PVC grating 15 x 15 cm (6" x 6") Each
White Glazed earthenware Wash Hand Basins (22" x 16") (56
19.074 Each
cm x 40 cm) with padestal
19.075Wash Hand Basin (22" x 16") (56 cm x 40 cm)} without pedesta Each
19.076Coloured wash hand basin with pedestal (22" x 16") (56 cm x Each
19.077Coloured wash hand basin without pedestal (22" x 16") (56 cm Each
19.078European type water closet without seat and cover (coloured) Each
19.079European type water closet without seat and cover (white) Each
19.080Double seat and cover Bekelite Each
19.081Double seat and cover Plastic Each
White Glazed earthenware squater (Orisa pattern) WC
19.082 Each
combined with footrest
Coloured {Glazed earthenware squater (Orisa pattern) WC
19.083 Each
combined with footrest}
19.084Terazzo concrete water closet squater type Each
Glazed earthen ware W.C squater type with seperate foot
19.085 Each
rest (Orisa pattern)
19.086Urinal Glazed earthenware flat back Each
19.087Pillar cock chromium plated heavy duty 2 cm (") Each
19.088Pillar cock chromium plated heavy duty 1.5 cm (") Each
19.089Stop cock under ground 15 mm (") with C.P cover Each
19.090Stop cock chromium plated heavy duty 2 cm (") Each
19.091Stop cock chromium plated heavy duty 1.5 cm (") Each
19.092Swan neck cock single way chromium plated 1.5 cm (") Each
19.093Swan neck cock double way chromium plated 1.5 cm (") Each
19.094Swan neck cock three way chromium plated 1.5 cm (") Each
19.095Gas cock chromium plated oxidised (") single way Each
19.096Gas cock chromium plated oxidised (") double way Each
19.097Gas cock chromium plated oxidised (") three way Each
19.098Looking glass 5 mm thick 55 x 40 cm (22" x 16") Each
19.099Hanger hook with pullout rod Each
19.100Gun metal peat/gate valve (screwed) 15 mm (") dia Each
19.101Gun metal peat/gate valve (screwed) 20 mm (") dia Each
19.102Gun metal peat/gate valve (screwed) 25 mm (1") dia Each
19.103 Gun metal peat/gate valve (screwed) 30 mm (1") dia Each
19.104 Gun metal peat/gate valve (screwed) 40 mm (1") dia Each
19.105Gun metal peat/gate valve (screwed) 50 mm (2") dia Each
19.106Gun metal peat/gate valve (screwed) 65 mm (2") dia Each
19.107Gun metal peat/gate valve (screwed) 80 mm (3") dia Each
19.108Foot rest for squatter type W.C. Each
19.109Waste coupling with bracket and waste pipe Each
19.110Screw (75 mm) 3" long Each
Page 7
ITEM MATERIAL UNIT RATE
C.I. High level flushing cistern 13.63 litre or 3 gallon
19.111 Each
capacity including accessories
19.112C.I. High level flushing cistern I/C all accessaries (1 gall Each
19.113Soap dish coloured (glazed earthen weare) Each
19.114Plastic shelf with railing Each
19.115Bracket Each
19.1162 cm (") bib cock Each
19.1171.5 cm (") bib cock Each
19.118Union brass cock " (1.5 cm) Each
19.119Union brass cock " (2 cm) Each
19.120C.I floor trap including grating size 10 x 7.5 cm (4" x 3") Each
19.121Manhole cover 30 cm (12" dia) Each
19.122C.I. manhole cover with frame 45 cm (18" dia) Each
19.123C.I. manhole cover with frame 60 cm (24" dia) Each
19.124 C.P Bottle trap with waste pipe 3cm (11/4" dia) Each
19.125 C.P Bottle trap with waste pipe 4cm (11/2" dia) Each
19.126Nail with Cutter for angle iron brackets Each
19.127 Copper connection with assessories " dia Each
19.1281.5 cm (" dia) brass ball valve with assessaries Each
21.001C.I. gully grating 12" x 12" with hinged safety type (81 lbs Each
21.002Concrete gully trap 12" x 12" Each
21.003China ware trap with C.I screen Each
21.004Iron Bolt 12" Each
21.005C.I Ventilating Shaft tool 6" to 12" I/d 18' to 36' long Kg
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.006 Per Ft.
B) 300
RCC mmpipes
sewer (12")confirming
i/d to ASTM C-76-79 (class III wall
21.007 Per Ft.
B) 375
RCC mm pipes
sewer (15") i/d
confirming to ASTM C-76-79 (class III wall
21.008 Per Ft.
B)
RCC450 mm pipes
sewer (18") i/d
confirming to ASTM C-76-79 (class III wall
21.009 Per Ft.
B) 525 mm (21") i/d
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.010 Per Ft.
B)
RCC600 mm pipes
sewer (24") i/d
confirming to ASTM C-76-79 (class III wall
21.011 Per Ft.
B) 675
RCC mm pipes
sewer (27") i/d
confirming to ASTM C-76-79 (class III wall
21.012 Per Ft.
B) 750
RCC mm pipes
sewer (30") i/d
confirming to ASTM C-76-79 (class III wall
21.013 Per Ft.
B) 825
RCC mm pipes
sewer (33") i/d
confirming to ASTM C-76-79 (class III wall
21.014 Per Ft.
B) 900 mm (36") i/d
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.015 Per Ft.
B) 1070 mm (42") i/d
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.016 Per Ft.
B) 1220 mm (48") i/d
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.017 Per Ft.
B) 1370 mm (54") i/d
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.018 Per Ft.
B) 1520 mm (60") i/d
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.019 Per Ft.
B) 1680 mm (66") i/d
RCC sewer pipes confirming to ASTM C-76-79 (class III wall
21.020 Per Ft.
B) 1830 mm (72") i/d
RCC Pipes conforming (to BS 5911 part I, 1981 class 'L')
21.021 Rft
'100 mm (4")
RCC Pipes i/d
conforming (to BS 5911 part I, 1981 class 'L')
21.022 Rft
'150Pipes
RCC mm (6") i/d
conforming (to BS 5911 part I, 1981 class 'L')
21.023 Rft
225 mm (9") i/d
Non/reinforced concrete pipe 100 mm (4") dia conforming to
21.024 Rft
ASTM C-14-73 Class I
Non/reinforced concrete pipe 150 mm (6") dia conforming to
21.025 Rft
ASTM C-14-73 Class I
Non/reinforced concrete pipe 200 mm (8") dia conforming to
21.026 Rft
ASTM C-14-73 Class I
Non/reinforced concrete pipe 225 mm (9") dia conforming to
21.027 Rft
ASTM C-14-73 Class I
Non/reinforced concrete pipe 250 mm (10") dia conforming to
21.028 Rft
ASTM C-14-73 Class I
dia RCC Sewer pipe 300 mm (12") Conforming to ASTM C-76-79
21.029 Per Ft.
(ClassII
RCC Sewerwall
pipe'B')
'375 cc (15") dia Conforming to ASTM C-76-79
21.030 Per Ft.
(ClassII
RCC Sewerwall
pipe'B')
450 mm (18") dia Conforming to ASTM C-76-79
21.031 Per Ft.
(ClassII wall 'B')
RCC Sewer pipe 525 mm (21") dia Conforming to ASTM C-76-79
21.032 Per Ft.
(ClassII
RCC Sewerwall
pipe'B')
600 mm (24") dia Conforming to ASTM C-76-79
21.033 Per Ft.
(ClassII
RCC Sewer pipe'B')
wall 675 mm (27") dia Conforming to ASTM C-76-79
21.034 Per Ft.
(ClassII
RCC Sewerwall
pipe'B')
750 mm (30") dia Conforming to ASTM C-76-79
21.035 Per Ft.
(ClassII
RCC Sewerwall
pipe'B')
825 mm (33") dia Conforming to ASTM C-76-79
21.036 Per Ft.
(ClassII
RCC Sewerwall
pipe'B')
900 mm (36") dia Conforming to ASTM C-76-79
21.037 Per Ft.
(ClassII wall 'B')
RCC Sewer pipe 1070 mm (42") dia Conforming to ASTM C-76-79
21.038 Per Ft.
(ClassII wall 'B')
RCC Sewer pipe 1220 mm (48") dia Conforming to ASTM C-76-79
21.039 Per Ft.
(ClassII wall 'B')
RCC Sewer pipe 1370 mm (54") dia Conforming to ASTM C-76-79
21.040 Per Ft.
(ClassII wall 'B')
Page 8
ITEM MATERIAL UNIT RATE
RCC Sewer pipe 1520 mm (60") dia Conforming to ASTM C-76-79
21.041 Per Ft.
(ClassII wall 'B')
RCC Sewer pipe 1680 mm (66") dia Conforming to ASTM C-76-79
21.042 Per Ft.
(ClassII wall 'B')
RCC Sewer pipe 1830 mm (72") dia Conforming to ASTM C-76-79
21.043 Per Ft.
(ClassII wall 'B')
Per Inch
21.044Rubber Ring dia of
pipe
RCC Sewer pipe 300 mm (12") dia Conforming to ASTM C-76-79
21.045 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 380 mm (15") dia Conforming to ASTM C-76-79
21.046 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 460 mm (18") dia Conforming to ASTM C-76-79
21.047 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 535 mm (21") dia Conforming to ASTM C-76-79
21.048 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 610 mm (24") dia Conforming to ASTM C-76-79
21.049 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 685 mm (27") dia Conforming to ASTM C-76-79
21.050 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 760 mm (30") dia Conforming to ASTM C-76-79
21.051 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 800 mm (33") dia Conforming to ASTM C-76-79
21.052 Per Ft.
(class IV wall 'B'
RCC Sewer pipe 915 mm (36") dia Conforming to ASTM C-76-79
21.053 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 1070 mm (42") dia Conforming to ASTM C-76-79
21.054 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 1220 mm (48") dia Conforming to ASTM C-76-79
21.055 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 1370 mm (54") dia Conforming to ASTM C-76-79
21.056 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 1520 mm (60") dia Conforming to ASTM C-76-79
21.057 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 1680 mm (66") dia Conforming to ASTM C-76-79
21.058 Per Ft.
(class IV wall 'B')
RCC Sewer pipe 1830 mm (72") dia Conforming to ASTM C-76-79
21.059 Per Ft.
(class IV wall 'B')
21.060Steel bolt 12" long Each
21.061Foundation bolts & nuts " dia 2' long . Each
21.062Rubber sheet 1/8" thick P.Kg
21.063Foundation bolts & nuts " dia 1' long Each
21.064Foundation bolts " dia 2' long. Each
21.065 Foundation bolts 7/8" dia 2' long. Each
22.001Winch including cost of tripod, tackle etc. for sinking of w Each
22.002Steel rope 3/4" dia Per Rft.
22.003One cusic capacity pumping set for dewatering Each
22.004Sleeper Each
22.005Bolts & Nuts P.Kg
A.C pressure pipe '80mm (3") dia Class 'B' BSS with comet
23.001 Per Ft.
joint and rubber rings
A.C pressure pipe 100 mm (4") dia Class 'B' BSS with comet
23.002 Per Ft.
joint and rubber rings.
A.C pressure pipe 150 mm (6") dia Class 'B' BSS with comet
23.003 Per Ft.
joint and rubber rings.
A.C pressure pipe 200 mm (8") dia Class 'B' BSS with comet
23.004 Per Ft.
joint and rubber rings.
A.C pressure pipe 250 mm (10") dia Class 'B' BSS with comet
23.005 Per Ft.
joint and rubber rings.
A.C pressure pipe 300 mm (12") dia Class 'B' BSS with comet
23.006 Per Ft.
joint and rubber rings.
A.C pressure pipe 350 mm (14") dia Class 'B' BSS with comet
23.007 Per Ft.
joint and rubber rings.
A.C pressure pipe 400 mm (16") dia Class 'B' BSS with comet
23.008 Per Ft.
joint and rubber rings.
A.C pressure pipe 450 mm (18") dia Class 'B' BSS with comet
23.009 Per Ft.
joint and rubber rings.
A.C pressure pipe 500 mm (20") dia Class 'B' BSS with comet
23.010 Per Ft.
joint and rubber rings.
A.C pressure pipe 600 mm (24") dia Class 'B' BSS with comet
23.011 Per Ft.
joint and rubber rings.
A.C pressure pipe 80 mm (3") dia Class 'C' BSS with comet
23.012 Per Ft.
joint and rubber rings
A.C pressure pipe 100 mm (4") dia Class 'C' BSS with comet
23.013 Per Ft.
joint and rubber rings.
Page 9
ITEM MATERIAL UNIT RATE
A.C pressure pipe 150 mm (6") dia Class 'C' BSS with comet
23.014 Per Ft.
joint and rubber rings.
A.C pressure pipes 200 mm (8") dia Class 'C' BSS with comet
23.015 Per Ft.
joint and rubber rings.
A.C pressure pipe 250 mm (10") dia Class 'C' BSS with comet
23.016 Per Ft.
joint and rubber rings.
A.C pressure pipe 300 mm (12") dia Class 'C' BSS with comet
23.017 Per Ft.
joint and rubber rings.
A.C pressure pipe 350 mm (14") dia Class 'C' BSS with comet
23.018 Per Ft.
joint and rubber rings.
A.C pressure pipe 400 mm (16") dia Class 'C' BSS with comet
23.019 Per Ft.
joint and rubber rings.
A.C pressure pipe 450 mm (18") dia Class 'C' BSS with comet
23.020 Per Ft.
joint and rubber rings.
A.C pressure pipe '500 mm (20") dia Class 'C' BSS with
23.021 Per Ft.
comet joint and rubber rings.
A.C pressure pipe 600 mm (24") dia Class 'C' BSS with comet
23.022 Per Ft.
joint and rubber rings.
A.C pressure pipe 80 mm (3") dia Class 'D' BSS with comet
23.023 Per Ft.
joint and rubber rings
A.C pressure pipe 100 mm (4") dia Class 'D' BSS with comet
23.024 Per Ft.
joint and rubber rings.
A.C pressure pipe 150 mm (6") dia Class 'D' BSS with comet
23.025 Per Ft.
joint and rubber rings.
A.C pressure pipe 200 mm (8") dia Class 'D' BSS with comet
23.026 Per Ft.
joint and rubber rings.
A.C pressure pipe 250 mm (10") dia Class 'D' BSS with comet
23.027 Per Ft.
joint and rubber rings.
A.C pressure pipe 300 mm (12") dia Class 'D' BSS with comet
23.028 Per Ft.
joint and rubber rings.
A.C pressure pipe 350 mm (14") dia Class 'D' BSS with comet
23.029 Per Ft.
joint and rubber rings.
A.C pressure pipe 400 mm (16") dia Class 'D' BSS with comet
23.030 Per Ft.
joint and rubber rings.
A.C pressure pipe 450 mm (18") dia Class 'D' BSS with comet
23.031 Per Ft.
joint and rubber rings.
A.C pressure pipe 500 mm (20") dia Class 'D' BSS with comet
23.032 Per Ft.
joint and rubber rings.
23.033G.I. pressure pipe 15 mm (") dia BSS-1387 - 1967 (light qua Per Ft.
23.034G.I. pressure pipe 20 mm (") dia BSS-1387 - 1967 (light qua Per Ft.
23.035G.I. pressure pipe 25 mm (1") dia BSS-1387 - 1967 (light qua Per Ft.
23.036G.I. pressure pipe 30 mm (1") dia BSS-1387 - 1967 (light qu Per Ft.
23.037G.I. pressure pipe 40 mm (1") dia BSS-1387 - 1967 (light qu Per Ft.
23.038G.I. pressure pipe 50 mm (2") dia BSS-1387 - 1967 (light qua Per Ft.
23.039G.I. pressure pipe 65 mm (2") dia BSS-1387 - 1967 (light qu Per Ft.
23.040G.I. pressure pipe 80 mm (3") dia BSS-1387 - 1967 (light qua Per Ft.
23.041G.I. pressure pipe 100 mm (4") dia BSS-1387 - 1967 (light qu Per Ft.
23.042G.I. pressure pipe 15 mm (") dia BSS-1387 - 1967 (medium qu Per Ft.
23.043G.I. pressure pipe 20 mm (") dia BSS-1387 - 1967 (medium q Per Ft.
23.044G.I. pressure pipe 25 mm (1") dia BSS-1387 - 1967 (medium q Per Ft.
23.045G.I. pressure pipe 30 mm (1") dia BSS-1387 - 1967 (medium Per Ft.
23.046G.I. pressure pipe 40 mm (1") dia BSS-1387 - 1967 (medium Per Ft.
23.047G.I. pressure pipe 50 mm (2") dia BSS-1387 - 1967 (medium q Per Ft.
23.048G.I. pressure pipe 65 mm (2") dia BSS-1387 - 1967 (medium Per Ft.
23.049G.I. pressure pipe 75 mm (3") dia BSS-1387 - 1967 (medium q Per Ft.
23.050G.I. pressure pipe 100 mm (4") dia BSS-1387 - 1967 (medium Per Ft.
23.051G.I. pressure pipe 125 mm (5") dia BSS-1387 - 1967 (medium Per Ft.
23.052G.I. pressure pipe 150 mm (6") dia BSS-1387 - 1967 (Medium q Per Ft.
23.053G.I. pressure pipe 15 mm (") dia BSS-1387 - 1967 (heavy qua Per Ft.
23.054G.I. pressure pipe 20 mm (") dia BSS-1387 - 1967 (heavy qua Per Ft.
23.055G.I. pressure pipe 25 mm (1") dia BSS-1387 - 1967 (heavy qua Per Ft.
23.056G.I. pressure pipe 30 mm (1") dia BSS-1387 - 1967 (heavy qu Per Ft.
23.057G.I. pressure pipe 40 mm (1") dia BSS-1387 - 1967 (heavy qu Per Ft.
23.058G.I. pressure pipe 50 mm (2") dia BSS-1387 - 1967 (heavy qua Per Ft.
23.059G.I. pressure pipe 65 mm (2") dia BSS-1387 - 1967 (heavy qu Per Ft.
23.060G.I. pressure pipe 75 mm (3") dia BSS-1387 - 1967 (heavy qua Per Ft.
23.061G.I. pressure pipe 100 mm (4") dia BSS-1387 - 1967 (heavy qu Per Ft.
23.062G.I. pressure pipe '125 mm (5") dia BSS-1387 - 1967 (heavy q Per Ft.
23.063G.I. pressure pipe 150 mm (6") dia BSS-1387 - 1967 (heavy qu Per Ft.
23.064 Jointing Material of Socket Joint for 1/2" dia G.I. Pipe for Per % Rft.
23.065 Jointing Material of Socket Joint for 3/4" dia G.I. Pipe fo Per % Rft.
23.066Jointing Material of Socket Joint for 1" dia G.I. Pipe for 1Per % Rft.
23.067 Jointing Material of Socket Joint for 11/4" dia G.I. Pipe fo Per % Rft.
23.068 Jointing Material of Socket Joint for 11/2" dia G.I. Pipe fo Per % Rft.
Page 10
ITEM MATERIAL UNIT RATE
23.069Jointing Material of Socket Joint for 2" dia G.I. Pipe for 1Per % Rft.
23.070 Jointing Material of Socket Joint for 21/2" dia G.I. Pipe fo Per % Rft.
23.071Jointing Material of Socket Joint for 3" dia G.I. Pipe for 1Per % Rft.
23.072Jointing Material of Socket Joint for 4" dia G.I. Pipe for 1Per % Rft.
23.073Jointing Material of Socket Joint for 5" dia G.I. Pipe for 1Per % Rft.
23.074Jointing Material of Socket Joint for 6" dia G.I. Pipe for 1Per % Rft.
23.075Testing charges of G.I. Pipes for 1" dia Per % Rft.
23.076Testing charges of G.I. Pipes for 1" dia Per % Rft.
23.077Testing charges of G.I. Pipes for 1" dia Per % Rft.
23.078Testing charges of G.I. Pipes for 2" dia Per % Rft.
23.079Testing charges of G.I. Pipes for 2" dia Per % Rft.
23.080Testing charges of G.I. Pipes for 3" dia Per % Rft.
23.081Testing charges of G.I. Pipes for 4" dia Per % Rft.
23.082Testing charges of G.I. Pipes for 5" dia Per % Rft.
23.083Testing charges of G.I. Pipes for 6" dia Per % Rft.
23.08450 mm (2") dia 3 mm (1/8") thick M.S blind pipes Per Ft.
23.08580 mm (3") dia 3 mm (1/8") thick M.S blind pipes Per Ft.
23.086100 mm (4") dia 3 mm (1/8") thick M.S blind pipes Per Ft.
23.087125 mm (5") dia 5 mm (3/16") thick M.S blind pipes Per Ft.
23.088150 mm (6") dia 5 mm (3/16") thick M.S blind pipes Per Ft.
23.089175 mm (7") dia 5 mm (3/16") thick M.S blind pipe Per Ft.
23.090200 mm (8") dia 5 mm (3/16") thick M.S blind pipes Per Ft.
23.091225 mm (9") dia 5 mm (3/16") thick M.S blind pipes Per Ft.
23.092250 mm (10") dia 6 mm (3/16") thick {M.S blind pipe Per Ft.
23.093300 mm (12") dia 6 mm (3/16") thick {M.S blind pipe Per Ft.
23.094375 mm (15") dia 6 mm (3/16") thick {M.S blind pipes Per Ft.
23.095450 mm (18") dia 6 mm (3/16") thick {M.S blind pipes Per Ft.
23.096500 mm (20") dia 6 mm (3/16") thick {M.S blind pipes Per Ft.
23.097550 mm (22") dia 6 mm (3/16") thick {M.S blind pipes Per Ft.
80-600 mm (3"-24") dia {C.I specials (with Commet joint and
23.098 Per Kg
rubber ring) For A.C Pipes}
23.09980-450 mm (3"- 18") dia C.I Specials of BSS Class B with S Per Kg
23.10080-450 mm (3"- 18") dia C.I Specials of BSS Class B With Fla Per Kg
23.10180-450 mm (3"- 18") dia C.I Specials of BSS Class B with Tyt Per Kg
23.10280 mm (3") dia Sluice Valves of BSS for AC & CI pipe line Each
23.103100 mm (4") dia Sluice Valves of BSS for AC & CI pipe line Each
23.104125 mm (5") dia Sluice Valves of BSS for AC & CI pipe line Each
23.105150 mm (6") dia Sluice Valves of BSS for AC & CI pipe line Each
23.106200 mm (8") dia Sluice Valves of BSS for AC & CI pipe line Each
23.107250 mm (10") dia Sluice Valves of BSS for AC & CI pipe line Each
23.108300 mm (12") dia Sluice Valves of BSS for AC & CI pipe line Each
23.109375 mm (14") dia Sluice Valves of BSS for AC & CI pipe line Each
23.110450 mm (18") dia Sluice Valves of BSS for AC & CI pipe line Each
23.111Single Air Valve 75 mm (3") Each
23.112Double Air Valve 75 mm (3") Each
23.113Fire Hydrant BSS 65 mm (2") Each
23.11480 mm (3") dia P.V.C tapperd core BSS Class 'B' Each
23.115100 mm (4") dia P.V.C tapperd core BSS Class 'B' Each
23.116125 mm (5") dia P.V.C tapperd core BSS Class 'B' Each
23.117150 mm (6") dia P.V.C tapperd core BSS Class 'B' Each
23.118200 mm (8") dia P.V.C tapperd core BSS Class 'B' Each
23.119250 mm (10") dia P.V.C tapperd core BSS Class 'B' Each
23.120300 mm (12") dia P.V.C tapperd core BSS Class 'B' Each
23.121350 mm (14") dia P.V.C tapperd core BSS Class 'B' Each
1
23.122 15 mm (1 /4") dia P.V.C tapperd core BSS Class 'D' Each
23.12340 mm (1") dia P.V.C tapperd core BSS Class 'D' Each
23.12450 mm (2") P.V.C tapperd core BSS Class 'D' Each
23.12575 mm (3") dia P.V.C Bends BSS class 'B' Each
23.126100 mm (4") dia P.V.C Bends BSS class 'B' Each
23.127100 mm (5") dia P.V.C Bends BSS class 'B' Each
23.128150 mm (6") dia P.V.C Bends BSS class 'B' Each
23.12930 mm (1") dia P.V.C Bends BSS class 'D' Each
23.13040 mm (1") dia P.V.C Bends BSS class 'D' Each
23.13150 mm (2") dia P.V.C Bends BSS class 'D' Each
23.13280 mm (3") dia P.V.C Bends BSS class 'D' Each
23.133100 mm (4") dia P.V.C Bends BSS class 'D' Each
23.134125 mm (5") dia P.V.C Bends BSS class 'D' Each
23.135150 mm (6") dia P.V.C Bends BSS class 'D' Each
23.13680 mmm (3") dia P.V.C Tee BSS Class 'B' Each
23.137100 mm (4") dia P.V.C Tee BSS Class 'B' Each
23.138125 mm (5") dia P.V.C Tee BSS Class 'B' Each
23.139150 mm (6") dia P.V.C Tee BSS Class 'B' Each
23.140200 mm (8") dia P.V.C Tee BSS Class 'B' Each
Page 11
ITEM MATERIAL UNIT RATE
23.141250 mm (10") dia P.V.C Tee BSS Class 'B' Each
23.142300 mm (12") dia P.V.C Tee BSS Class 'B' Each
23.143350 mm (14") dia P.V.C Tee BSS Class 'B' Each
23.14430 mm (1") dia P.V.C Tee BSS Class 'D' Each
23.14540 mm (1") dia P.V.C Tee BSS Class 'D' Each
23.14650 mm (2") dia P.V.C Tee BSS Class 'D' Each
23.14780 mm (3") dia P.V.C Tee BSS Class 'D' Each
23.148100 mm (4") dia P.V.C Tee BSS Class 'D' Each
23.149125 mm (5") dia P.V.C Tee BSS Class 'D' Each
23.150150 mm (6") dia P.V.C Tee BSS Class 'D' Each
23.15180 mmm (3") dia P.V.C sockets BSS Class 'B' Each
23.152100 mm (4") dia P.V.C sockets BSS Class 'B' Each
23.153125 mm (5") dia P.V.C sockets BSS Class 'B' Each
23.154150 mm (6") dia P.V.C sockets BSS Class 'B' Each
23.155200 mm (8") dia P.V.C sockets BSS Class 'B' Each
23.156250 mm (8") dia P.V.C sockets BSS Class 'B' Each
23.157300 mm (12") dia P.V.C sockets BSS Class 'B' Each
23.158350 mm (14") dia P.V.C sockets BSS Class 'B' Each
23.15930 mm (1") dia P.V.C sockets BSS Class 'D' Each
23.16040 mm (1") dia P.V.C sockets BSS Class 'D' Each
23.16150 mm (2") dia P.V.C sockets BSS Class 'D' Each
23.16280 mm (3") dia P.V.C sockets BSS Class 'D' Each
23.163100 mm (4") dia P.V.C sockets BSS Class 'D' Each
23.164125 mm (5") dia P.V.C sockets BSS Class 'D' Each
23.165150 mm (6") dia P.V.C sockets BSS Class 'D' Each
23.166Bleaching powder/chlorine Per Kg
23.16750 mm (2") dia 4 mm (5/32") Brass strainer incluidng specia Per Ft.
23.16875 mm (3") dia 4 mm (5/32") Brass strainer incluidng specia Per Ft.
23.169100 mm (4") dia 5 mm (3/16") Brass strainer incluidng spec Per Ft.
23.170125 mm (5") dia 5 mm (3/16") Brass strainer incluidng speci Per Ft.
23.171150 mm (6") dia 5 mm (3/16") Brass strainer incluidng speci Per Ft.
23.172175 mm (7") dia 5 mm (3/16") Brass strainer incluidng speci Per Ft.
23.173200 mm (8") dia 5 mm (3/16") Brass strainer incluidng speci Per Ft.
23.174225 mm (9") dia 5 mm (3/16") Brass strainer incluidng speci Per Ft.
23.175250 mm (10") dia 5 mm (3/16") Brass strainer incluidng spec Per Ft.
23.176250 mm (10") dia 6 mm (") Brass strainer incluidng special Per Ft.
23.177300 mm (12") dia 6 mm (") Brass strainer incluidng special Per Ft.
23.178375 mm (15") dia 6 mm (") Brass strainer incluidng special Per Ft.
23.179450 mm (18") dia 6 mm (") Brass strainer incluidng special Per Ft.
23.180500 mm (20") dia 6 mm (") Brass strainer incluidng special Per Ft.
23.181550 mm (22") dia 6 mm (") Brass strainer incluidng special Per Ft.
23.18275 mm (3") dia P.V.C strainer Class 'B' Per Ft.
23.183100 mm (4") dia P.V.C strainer Class 'B' Per Ft.
23.184125 mm (5") dia 60 cm P.V.C strainer Class 'B' Per Ft.
23.185150 mm (6") dia 60 cm P.V.C strainer Class 'B' Per Ft.
23.186200 mm (7") dia 60 cm P.V.C strainer Class 'B' Per Ft.
23.187250 mm (8") dia 60 cm P.V.C strainer Class 'B' Per Ft.
23.188300 mm (9") dia 60 cm P.V.C strainer Class 'B' Per Ft.
23.189350 mm (10") dia 60 cm P.V.C strainer Class 'B' Per Ft.
23.190PVC Stainer Class D 1" dia (30mm) Per Ft.
23.191PVC Stainer Class D 1 dia (40 mm) Per Ft.
23.192PVC Stainer Class D 2" dia (50 mm) Per Ft.
23.193PVC Stainer Class D 3" dia (75 mm) Per Ft.
23.194PVC Stainer Class D 4" dia (100 mm) Per Ft.
23.195PVC Stainer Class D 5" dia (125 mm) Per Ft.
23.196PVC Stainer Class D 6" dia (150 mm) Per Ft.
23.19750 mm (2") i/d, Bail Plug-mild steel Per Ft.
23.19875 mm (3") i/d Bail Plug-mild steel Per Ft.
23.199100 mm (4") i/dBail Plug-mild steel Per Ft.
23.200125 mm (5") i/d Bail Plug-mild steel Per Ft.
23.201150 mm (6") i/d Bail Plug-mild steel Per Ft.
23.202175 mm (7") i/d Bail Plug-mild steel Per Ft.
23.203200 mm (8") i/d Bail Plug-mild steel Per Ft.
23.204225 mm (9") i/d Bail Plug-mild steel Per Ft.
23.205250 mm (10") i/d Bail Plug-mild steel Per Ft.
23.206300 mm (12") i/d Bail Plug-mild steel Per Ft.
23.207375 mm (15") i/d Bail Plug-mild steel Per Ft.
23.208450 mm (18") i/d Bail Plug-mild steel Per Ft.
23.209500 mm (20") i/d Bail Plug-mild steel Per Ft.
23.210550 mm (22") i/d Bail Plug-mild steel Per Ft.
23.21175 mm (3") dia PVC BSS Class 'B' Bail Plug Each
23.212100 mm (4") dia PVC BSS Class 'B' Bail Plug Each
23.213125 mm (5") dia PVC BSS Class 'B' Bail Plug Each
Page 12
ITEM MATERIAL UNIT RATE
23.214150 mm (6") dia PVC BSS Class 'B' Bail Plug Each
23.215200 mm (8") dia PVC BSS Class 'B' Bail Plug Each
23.216250 mm (10") dia PVC BSS Class 'B' Bail Plug Each
23.217300 mm (12") dia PVC BSS Class 'B' Bail Plug Each
23.218350 mm (14") dia PVC BSS Class 'B' Bail Plug Each
23.21930 mm (1") dia P.V.C. Class 'D' Bail Plug Each
23.22040 mm (1") dia P.V.C. Class 'D' Bail Plug Each
23.22150 mm (2") dia P.V.C. Class 'D' Bail Plug Each
23.22280 mm (3") dia P.V.C. Class 'D' Bail Plug Each
23.223100 mm (4") dia P.V.C. Class 'D' Bail Plug Each
23.224125 mm (5") dia P.V.C. Class 'D' Bail Plug Each
23.225150 mm (6") dia P.V.C. Class 'D' Bail Plug Each
23.226G.I. pipe with flanged joint 1" dia 40mm (Heavy Quality) Per Ft.
23.227G.I. pipe with G.I. flanged joint 2" dia 50 mm (Heavy Qualit Per Ft.
23.228G.I. pipe with GI. flanged joint 2" dia 65 mm (Heavy Qualit Per Ft.
23.229G.I. pipe with G.I. flanged joint 3" dia 75 mm (Heavy Quali Per Ft.
23.230G.I. pipe with G.I. flanged joint 4" dia 100 mm (Heavy Quali Per Ft.
23.231G.I. pipe with G.I. flanged joint 5" dia 125 mm (Heavy Quali Per Ft.
23.232G.I. pipe with G.I. flanged joint 6" dia 150 mm (Heavy Quali Per Ft.
23.233G.I. pipe with C.I. flanged joint 1" dia 40mm (Medium Quali Per Ft.
23.234G.I. pipe with C.I. flanged joint 2" dia 50 mm (Medium Quali Per Ft.
23.235G.I. pipe with C.I. flanged joint 2" dia 65 mm (Medium Qual Per Ft.
23.236G.I. pipe with C.I. flanged joint 3" dia 75 mm (Medium Qual Per Ft.
23.237G.I. pipe with C.I. flanged joint 4" dia 100 mm (Medium Qual Per Ft.
23.238G.I. pipe with C.I. flanged joint 5" dia 125 mm (Medium Qual Per Ft.
23.239G.I. pipe with C.I. flanged joint 6" dia 150 mm (Medium Qual Per Ft.
23.24075 mm Sluice Valve for A.C. Pipe Line with commet joint & ru Each
23.241100 mm Sluice Valve for A.C. Pipe Line with commet joint & r Each
23.242150 mm Sluice Valve for A.C. Pipe Line with commet joint & r Each
23.243200 mm Sluice Valve for A.C. Pipe Line with commet joint & r Each
23.244250 mm Sluice Valve for A.C. Pipe Line with commet joint & r Each
23.245300 mm Sluice Valve for A.C. Pipe Line with commet joint & r Each
23.246400 mm Sluice Valve for A.C. Pipe Line with commet joint & r Each
23.247450 mm Sluice Valve for A.C. Pipe Line with commet joint & r Each
23.248Lock for wooden box for pressuring samples off strata from b Each
23.249Cost of Lubricant for PVC Pipe Per Kg.
23.250Steel Handle 4" (100mm) Each
23.25175 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.252100 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.253125 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.254150 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.255200 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.256250 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.257300 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.258350 mm PVC Blind/Pressure Pipe Class "B" Per Ft.
23.25930 mm PVC Blind/Pressure Pipe Class "D" Per Ft.
23.26040 mm PVC Blind/Pressure Pipe Class "D" Per Ft.
23.26150 mm PVC Blind/Pressure Pipe Class "D" Per Ft.
23.26275 mm PVC Blind/Pressure Pipe Class "D" Per Ft.
23.263100 mm PVC Blind/Pressure Pipe Class "D" Per Ft.
23.264125 mm PVC Blind/Pressure Pipe Class "D" Per Ft.
23.265150 mm PVC Blind/Pressure Pipe Class "D" Per Ft.
23.266Loading expenses for pipes P. Day
23.267(Petty store) bolts & nuts etc. for 5" dia bore Per Ft.
23.268(Petty store) bolts & nuts etc. for 6" dia bore Per Ft.
23.269(Petty store) bolts & nuts etc. for 8" dia bore Per Ft.
23.270(Petty store) bolts & nuts etc. for10" dia bore Per Ft.
23.271(Petty store) bolts & nuts etc. for 12" dia bore Per Ft.
23.272(Petty store) bolts & nuts etc. for15" dia bore Per Ft.
23.273(Petty store) bolts & nuts etc. for 18" dia bore Per Ft.
23.274Hire charges of boring material, installation & Carriage (3 Per Ft.
23.275Hire charges of boring material, installation & Carriage (4 Per Ft.
23.276Hire charges of boring material, installation & Carriage (5 Per Ft.
23.277Hire charges of boring material, installation & Carriage (6 Per Ft.
23.278Hire charges of boring material, installation & Carriage (8 Per Ft.
23.279Hire charges of boring material, installation & Carriage (10 Per Ft.
23.280Hire charges of boring material, installation & Carriage (12 Per Ft.
23.281Hire charges of boring material, installation & Carriage (15 Per Ft.
23.282Hire charges of boring material, installation & Carriage (18 Per Ft.
Hire charges of boring material, installation & Carriage
23.283 Per Ft.
for (5" dia bore) from 100.10 to 200 Ft. depth
Hire charges of boring material, installation & Carriage
23.284 Per Ft.
for (6" dia bore) from 100.10 to 200 Ft. depth
Page 13
ITEM MATERIAL UNIT RATE
Hire charges of boring material, installation & Carriage
23.285 Per Ft.
for (8" dia bore) from 100.10 to 200 Ft. depth
Hire charges of boring material, installation & Carriage
23.286 Per Ft.
for (10" dia bore) from 100.10 to 200 Ft. depth
Hire charges of boring material, installation & Carriage
23.287 Per Ft.
for (12" dia bore) from 100.10 to 200 Ft. depth
Hire charges of boring material, installation & Carriage
23.288 Per Ft.
for (15" dia bore) from 100.10 to 200 Ft. depth
Hire charges of boring material, installation & Carriage
23.289 Per Ft.
for (18" dia bore) from 100.10 to 200 Ft. depth
Hire charges of boring material, installation & Carriage
23.290 Per Ft.
for (5" dia bore) from 200.10 to 300 Ft. depth
Hire charges of boring material, installation & Carriage
23.291 Per Ft.
for (6" dia bore) from 200.10 to 300 Ft. depth
Hire charges of boring material, installation & Carriage
23.292 Per Ft.
for (8" dia bore) from 200.10 to 300 Ft. depth
Hire charges of boring material, installation & Carriage
23.293 Per Ft.
for (10" dia bore) from 200.10 to 300 Ft. depth
Hire charges of boring material, installation & Carriage
23.294 Per Ft.
for (12" dia bore) from 200.10 to 300 Ft. depth
Hire charges of boring material, installation & Carriage
23.295 Per Ft.
for (15" dia bore) from 200.10 to 300 Ft. depth
Hire charges of boring material, installation & Carriage
23.296 Per Ft.
for (18" dia bore) from 200.10 to 300 Ft. depth
Hire charges of boring material, installation & Carriage
23.297 Per Ft.
for (8" dia bore) from 300.10 to 400 Ft. depth
Hire charges of boring material, installation & Carriage
23.298 Per Ft.
for (10" dia bore) from 300.10 to 400 Ft. depth
Hire charges of boring material, installation & Carriage
23.299 Per Ft.
for (12" dia bore) from 300.10 to 400 Ft. depth
Hire charges of boring material, installation & Carriage
23.300 Per Ft.
for (15" dia bore) from 300.10 to 400 Ft. depth
Hire charges of boring material, installation & Carriage
23.301 Per Ft.
for (18" dia bore) from 300.10 to 400 Ft. depth
23.302Repair charges of T&P for 5" dia bore hole Per Ft.
23.303Repair charges of T&P for 6" dia bore hole Per Ft.
23.304Repair charges of T&P for 8" dia bore hole Per Ft.
23.305Repair charges of T&P for 10" dia bore hole Per Ft.
23.306Repair charges of T&P for 12" dia bore hole Per Ft.
23.307Repair charges of T&P for 15" dia bore hole Per Ft.
23.308Repair charges of T&P for 18" dia bore hole Per Ft.
23.309Solvent for PVC Strainer 3" dia (Class B) Per Ft.
23.310Solvent for PVC Strainer 4" - 5" dia (Class B) Per Ft.
23.311Solvent for PVC Strainer 6" dia (Class B) Per Ft.
23.312Solvent for PVC Strainer 8" - 10" dia (Class B) Per Ft.
23.313Solvent for PVC Strainer 12" - 14" dia (Class B) Per Ft.
23.314Solvent for PVC Strainer 1" dia (Class D) Per Ft.
23.315Solvent for PVC Strainer 1" dia (Class D) Per Ft.
23.316Solvent for PVC Strainer 2" dia (Class D) Per Ft.
23.317Solvent for PVC Strainer 3" dia (Class D) Per Ft.
23.318Solvent for PVC Strainer 4" dia (Class D) Per Ft.
23.319Solvent for PVC Strainer 5" dia (Class D) Per Ft.
23.320Solvent for PVC Strainer 6" dia (Class D) Per Ft.
23.321Solvent for PVC Bail Plug 3" dia (Class B) Each
23.322Solvent for PVC Bail Plug 4" dia (Class B) Each
23.323Solvent for PVC Bail Plug 5" dia (Class B) Each
23.324Solvent for PVC Bail Plug 6" dia (Class B) Each
23.325Solvent for PVC Bail Plug 8" dia (Class B) Each
23.326Solvent for PVC Bail Plug 10" dia (Class B) Each
23.327Solvent for PVC Bail Plug 12" dia (Class B) Each
23.328Solvent for PVC Bail Plug 14" dia (Class B) Each
23.329Solvent for PVC Bail Plug 1" dia (Class D) Each
23.330Solvent for PVC Bail Plug 1" dia (Class D) Each
23.331Solvent for PVC Bail Plug 2" dia (Class D) Each
23.332Solvent for PVC Bail Plug 3" dia (Class D) Each
23.333Solvent for PVC Bail Plug 4" dia (Class D) Each
23.334Solvent for PVC Bail Plug 5" dia (Class D) Each
23.335Solvent for PVC Bail Plug 6" dia (Class D) Each
23.336Testing and Disinfecting of PVC Pipe 3" dia 100 Ft.
23.337Testing and Disinfecting of PVC Pipe 4" dia 100 Ft.
23.338Testing and Disinfecting of PVC Pipe 5" dia 100 Ft.
23.339Testing and Disinfecting of PVC Pipe 6" dia 100 Ft.
23.340Testing and Disinfecting of PVC Pipe 8" dia 100 Ft.
Page 14
ITEM MATERIAL UNIT RATE
23.341Testing and Disinfecting of PVC Pipe 10" dia 100 Ft.
23.342Testing and Disinfecting of PVC Pipe 12" dia 100 Ft.
23.343Testing and Disinfecting of PVC Pipe 14" dia 100 Ft.
23.344Testing and Disinfecting of G.I Pipe 40mm (1") dia 100 Ft.
23.345Testing and Disinfecting of G.I Pipe 50mm (2") dia 100 Ft.
23.346Testing and Disinfecting of G.I Pipe 63mm (2") dia 100 Ft.
23.347Testing and Disinfecting of G.I Pipe 75mm (3") dia 100 Ft.
23.348Testing and Disinfecting of G.I Pipe 100mm (4") dia 100 Ft.
23.349Testing and Disinfecting of G.I Pipe 125mm (6") dia 100 Ft.
23.350Testing and Disinfecting of G.I Pipe 150mm (7") dia 100 Ft.
23.351Disc for bail plugs P. Kg.
23.352Testing and Disinfecting of G.I Pipe P. Lbs
23.353Bottle 2 lbs capacity Each
23.35475 mm to 450 mm dia CI flanges for pipes P. Kg.
23.355Cost of C.I. Flanges for Pipe 100 cwt
23.356Welding Charges of spigot or socket, flanged or tyton ends er Inch Bore
23.357Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.358Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.359Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.360Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.361Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.362Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.363Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.364Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.365Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.366Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.367Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.368Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.369Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.370Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.371Equipment Charges for lowering Brass Stainer in Tubewel Bore Per Ft.
23.372M.S. Bolt & Nut 6" to 22" dia bore hole bail plug Each
23.373M.S. Bolt & Nut 2" to 5" dia bore hole bail plug Each
23.374Threading Clamp 2" to 6" Each
23.375Threading Clamp 7" to 22" Each
23.376Water for testing and disinfecting of pipes %0 Gallon
23.377Lead Per Kg.
23.378Yarn Per Kg.
23.379Disinfecting agent for C.I. Pipe P. Kg.
23.380Bolt and nuts (3" to 4") for flanged joint Each
23.381Bolt and nuts (5" to 12") for flanged joint Each
23.382Bolt and nuts (15" to 18") for flanged joint Each
23.383Cost of ring for cast iron pipe(3") with tyton joints Each
23.384Cost of ring for cast iron pipe(4") with tyton joints Each
23.385Cost of ring for cast iron pipe(5") with tyton joints Each
23.386Cost of ring for cast iron pipe(6") with tyton joints Each
23.387Cost of ring for cast iron pipe(8") with tyton joints Each
23.388Cost of ring for cast iron pipe(10") with tyton joints Each
23.389Cost of ring for cast iron pipe(12") with tyton joints Each
23.390Cost of ring for cast iron pipe(15") with tyton joints Each
23.391Cost of ring for cast iron pipe(18") with tyton joints Each
23.392Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.393Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.394Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.395Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.396Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.397Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.398Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.399Cost of material for joints of sluice Valve for A.C. pipe wi 2 joints
23.400Material for jointing of fire hydrant Each
23.401Material for jointing of air valve Each
23.402Cost of Bolt and nuts for G.I. Flanged Joints 1" to 2" Each
23.403Cost of Bolt and nuts for G.I. Flanged Joints 2" to 7" Each
23.404Rubber Insertion for G.I. flanged joints Per Lbs
23.405Solvent for PVC bends Per Kg.
23.406Lubricant Per Kg.
23.407Material for C-I specials with spigot and socket joint fo 2 joints
23.408Material for C-I specials with spigot and socket joint fo 2 joints
23.409Material for C-I specials with spigot and socket joint fo 2 joints
23.410Material for C-I specials with spigot and socket joint fo 2 joints
23.411Material for C-I specials with spigot and socket joint fo 2 joints
23.412Material for C-I specials with spigot and socket joint fo 2 joints
23.413Material for C-I specials with spigot and socket joint fo 2 joints
Page 15
ITEM MATERIAL UNIT RATE
23.414Material for C-I specials with spigot and socket joint fo 2 joints
23.415Material for C-I specials with spigot and socket joint fo 2 joints
23.416Material for CI flanged speical with flanged and flanged joi 2 joints
23.417Material for CI flanged speical with flanged and flanged joi 2 joints
23.418Material for CI flanged speical with flanged and flanged joi 2 joints
23.419Material for CI flanged speical with flanged and flanged joi 2 joints
23.420Material for CI flanged speical with flanged and flanged joi 2 joints
23.421Material for CI flanged speical with flanged and flanged joi 2 joints
23.422Material for CI flanged speical with flanged and flanged joi 2 joints
23.423Material for CI flanged speical with flanged and flanged joi 2 joints
23.424Material for CI flanged speical with flanged and flanged joi 2 joints
Casting material (supply of speicals I/c moulding, painting
23.425 carriage to site of work) CI specials with Per Cwt
spigot an socket joint
Casting material (supply of speicals I/c moulding, painting
23.426 carriage to site of work) CI flanged Per Cwt
speical with flanged and flanged joints
Casting material (supply of speicals I/c moulding, painting
23.427 carriage to site of work) CI speicals with Per Cwt
tyton joints / with comet joint and rubber ring complete
23.428Material for AC pipe line with comet joint and rubber ring 2 joints
23.429Material for AC pipe line with comet joint and rubber ring 2 joints
23.430Material for AC pipe line with comet joint and rubber ring 2 joints
23.431Material for AC pipe line with comet joint and rubber ring 2 joints
23.432Material for AC pipe line with comet joint and rubber ring 2 joints
23.433Material for AC pipe line with comet joint and rubber ring 2 joints
23.434Material for AC pipe line with comet joint and rubber ring 2 joints
23.435Material for AC pipe line with comet joint and rubber ring 2 joints
23.436Material for AC pipe line with comet joint and rubber ring 2 joints
23.437Material for AC pipe line with comet joint and rubber ring 2 joints
24.00117.5 x 10 x cm (7" x 4") {Sal Wood Boards (4.5 cm) 1" thic Each
24.00222.5 x 10 x cm (9" x 4") {Sal Wood Boards (4.5 cm) 1" thic Each
24.00322.0 x 25 x cm (8" x 10") {Sal Wood Boards (4.5 cm) 1" thi Each
24.00425.0 x 30 x cm (10" x 12") {Sal Wood Boards (4.5 cm) 1" th Each
24.00530.0 x 37 x cm (12" x 14") {Sal Wood Boards (4.5 cm) 1" th Each
24.00617.5 x 10 x cm (7" x 4") {Teak Wood Boards (4.5 cm) 1.75" t Each
24.00722.5 x 10 x cm (9" x 4") {Teak Wood Boards (4.5 cm) 1.75" t Each
24.00820.0 x 25 x cm (8" x 10") {Teak Wood Boards (4.5 cm) 1.75" Each
24.00925.0 x 30 x cm (10" x 12") {Teak Wood Boards (4.5 cm) 1.75 Each
24.01030.0 x 37 x cm (12" x 14") {Teak Wood Boards (4.5 cm) 1.75 Each
2 way 15 Amp Branch distribution board iron/aluminium clad
24.011 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
3 way 15 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.012 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
4 way 15 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.013 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
5 way 15 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.014 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
6 way 15 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.015 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
7 way 15 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.016 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
8 way 15 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.017 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
9 way 15 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.018 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
10 way 15for
AmpBDB 250 volts
Branch distribution board iron/aluminium clad
24.019 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
11 way 15for
AmpBDB 250 volts
Branch distribution board iron/aluminium clad
24.020 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
12 way 15for
AmpBDB 250 volts
Branch distribution board iron/aluminium clad
24.021 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
2 way 30 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.022 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
3 way 30 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.023 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
4 way 30 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.024 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
5 way 30 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.025 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
6 way 30 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.026 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering
7 way 30 for
Amp BDB 250distribution
Branch volts board iron/aluminium clad
24.027 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering for BDB 250 volts
Page 16
ITEM MATERIAL UNIT RATE
8 way 30 Amp Branch distribution board iron/aluminium clad
24.028 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering for BDB 250 volts
9 way 30 Amp Branch distribution board iron/aluminium clad
24.029 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering for BDB 250 volts
10 way 30 Amp Branch distribution board iron/aluminium clad
24.030 250 volts angle iron frame with 3 mm (1/8") M.S. sheet Each
covering for BDB 250 volts
24.031PVC insulated single core copper conductor cable 3/0.029" 25 Metre
24.032PVC insulated single core copper conductor cable 3/0.036" 2 Metre
24.033PVC insulated single core copper conductor cable 7/0.029" 2 Metre
24.034PVC insulated single core copper conductor cable 7/0.036" 2 Metre
24.035PVC insulated single core copper conductor cable 7/0.044" 2 Metre
24.036PVC insulated single core copper conductor cable 7/0.064" 2 Metre
24.037PVC insulated single core copper conductor cable 19/0.052" 2 Metre
24.038PVC insulated single core copper conductor cable 19/0.064" Per Metre
PVC insulated cotton braided and compounded copper
24.039 Per Metre
conductor cable 3/0.029" 250/440 Volts
PVC insulated cotton braided and compounded copper
24.040 Per Metre
conductor cable 3/0.036" 250/440 Volts
PVC insulated cotton braided and compounded copper
24.041 Per Metre
conductor cable 7/0.029" 250/440 Volts
PVC insulated cotton braided and compounded copper
24.042 Per Metre
conductor cable 7/0.036" 250/440 Volts
PVC insulated cotton braided and compounded copper
24.043 Per Metre
conductor cable 7/0.044" 250/440 Volts
PVC insulated cotton braided and compounded copper
24.044 Per Metre
conductor cable 7/0.064" 250/440 Volts
PVC insulated sheathed single core copper conductor cable
24.045 Per Metre
3/0.029" 250/440 Volts
PVC insulated PVC sheathed single core copper conductor
24.046 Per Metre
cable 3/0.036" 250/440 Volts
PVC insulated PVC sheathed single core copper conductor
24.047 Per Metre
cable 7/0.074" 250/440 Volts
PVC insulated PVC sheathed single core copper conductor
24.048 Per Metre
cable 7/0.036" 250/440 Volts
PVC insulated PVC sheathed single core copper conductor
24.049 Per Metre
cable 7/0.044" 250/440 Volts
PVC insulated PVC sheathed single core copper conductor
24.050 Per Metre
cable 7/0.064" 250/440 Volts
PVC insulated PVC sheathed single core copper conductor
24.051 Per Metre
cable 7/0.064" 660/1100 volts grade
PVC insulated PVC sheathed single core copper conductor
24.052 Per Metre
cable 19/0.064" 660/1100 volts grade
PVC insulated PVC sheathed single core copper conductor
24.053 Per Metre
cable 19/0.064" 660/1100 volts grade
PVC insulated PVC sheathed single core, copper conductor
24.054 Per Metre
cable 19/0.083" 660/1100 volts grade
PVC insulated PVC sheathed single core, copper conductor
24.055 Per Metre
cable 37/0.072" 660/1100 volts grade
PVC insulated PVC sheathed single core, copper conductor
24.056 Per Metre
cable 37/0.083" 660/1100 volts grade
PVC insulated PVC sheathed single core, copper conductor
24.057 Per Metre
cable 37/0.103" 660/1100 volts grade
PVC insulated, PVC sheathed twin core copper conductor
24.058 Per Metre
cable 3/0.029" 250/440 volts
PVC insulated, PVC sheathed twin core copper conductor
24.059 Per Metre
cable 3/0.036" 250/440 volts
PVC insulated, PVC sheathed twin core copper conductor
24.060 Per Metre
cable 7/0.029" 250/440 volts
PVC insulated, PVC sheathed twin core copper conductor
24.061 Per Metre
cable 7/0.036" 250/440 volts
PVC insulated, PVC sheathed twin core copper conductor
24.062 Per Metre
cable 7/0.044" 250/440 volts
PVC insulated, PVC sheathed twin core copper conductor
24.063 Per Metre
cable 7/0.064" 250/440 volts
24.064PVC insulated, PVC sheathed three core cable 660/1100 volts Per Metre
24.065PVC insulated, PVC sheathed three core cable 660/1100 voltsPer Metre
24.066PVC insulated, PVC sheathed three core cable 7/0.029" 66Per Metre
24.067PVC insulated, PVC sheathed three core cable 7/0.036" 660Per Metre
24.068PVC insulated, PVC sheathed three core cable 7/0.044" 660Per Metre
24.069PVC insulated, PVC sheathed three core cable 7/0.064" 660/Per Metre
24.070PVC sheathed 4 core non armoured cable 3/0.029" 660/1100 vPer Metre
24.071PVC sheathed 4 core non armoured cable 3/0.036" 660/1100 vPer Metre
24.072PVC sheathed 4 core non armoured cable 7/0.029" 660/1100 vPer Metre
Page 17
ITEM MATERIAL UNIT RATE
24.073PVC sheathed 4 core non armoured cable 7/0.036" 660/1100 vPer Metre
24.074PVC sheathed 4 core non armoured cable 7/0.044" 660/1100 vPer Metre
24.075PVC sheathed 4 core non armoured cable 7/0.064" 660/1100 vPer Metre
24.076PVC sheathed 4 core non armoured cable 19/0.052" 660/1100 vPer Metre
PVC sheathed armoured with G.I. WIRE 16 SWG cable
24.077 Per Metre
19/0 052" 660/1100
PVC sheathed volts
armoured with G.I. WIRE 16 SWG cable
24.078 Per Metre
19/0sheathed
PVC 064" 660/1100 volts
armoured with G.I. WIRE 16 SWG cable
24.079 Per Metre
19/0sheathed
PVC 072" 660/1100 volts
armoured with G.I. WIRE 16 SWG cable
24.080 Per Metre
19/0sheathed
PVC 083" 660/1100 volts
armoured with G.I. WIRE 16 SWG cable
24.081 Per Metre
37/0sheathed
PVC 072" 660/1100 volts
armoured with G.I. WIRE 16 SWG cable
24.082 Per Metre
37/0sheathed
PVC 083" 660/1100 volts
armoured with G.I. WIRE 16 SWG cable
24.083 Per Metre
37/0 093" 660/1100 volts
PVC sheathed armoured with G.I. WIRE 16 SWG cable
24.084 Per Metre
37/0 103" stranded
Aluminium 660/1100hard
volts
drawn bare conductor 7/3.099 mm
24.085 Per Metre
(7/0 122")
Flexible wire 7/3.099 mm (7/.122") {PVC insulated PVC
24.086 sheathed armoured with G.I wire 16 SWG for service Per Metre
conneciton 3 core:}
24.087Flexible twin wire 23/.0076" (23/0.195mm) Per Metre
24.088PVC wire (3/.029") Per Metre
24.089Capacitor 2.2 UF for ceiling fan Each
24.090M.S Clamp " dia (16mm) Each
24.091M.S Clamp 3/4" dia (20mm) Each
24.092M.S Clamp 1" dia (25mm) Each
24.093M.S Clamp 11/4" dia (32mm) Each
24.094M.S Clamp 1" dia (40mm) Each
24.095M.S Clamp 2" dia (50mm) Each
24.096M.S Clamp 4" dia (100mm) Each
24.097Clamps for electric wiring 15 mm (") Each
24.098Clamps for electric wiring 20 mm (") Each
24.099Clamps for electric wiring '25 mm (1") Each
24.100Clamps for electric wiring '32 mm (1") Each
24.101Clamps for electric wiring 40 mm (1") Each
24.102Clamps for electric wiring 50 mm (2") Each
24.103Clamps for electric wiring '63 mm (2") Each
24.104Clamps for electric wiring '80 mm (3") Each
24.105Clamps for electric wiring 100 mm (4") Each
24.106PVC Inspection Boxes 15 mm (") Per Doz.
24.107PVC Inspection Boxes 20 mm (") Per Doz.
24.108PVC Inspection Boxes 25 mm (1") Per Doz.
24.109PVC Inspection Boxes 30 mm (1") Per Doz.
24.110PVC Inspection Boxes 40 mm (1") Per Doz.
24.111PVC Inspection Boxes 50 mm (2") Per Doz.
24.112PVC Inspection Boxes 75 mm (3") Per Doz.
24.113PVC Inspection Boxes 100 mm (4") Per Doz.
24.114Chokes 40 watts Each
24.115Chokes 20 watts Each
24.116Round block of Sahl wood Each
GEC design Pole mounted street light with holder shade and
24.117 glass for fitting 125/250 watts mercury Vapour lamp Each
(excluding cost of lamp) with bracket clamp nuts & bolts
24.118Street light pole bracket Each
24.119Cost of bracket 1" (32 mm) G.I pipe 7 ft. long half round Each
24.120Shackle Insulator for holding insulated wire Each
24.121Pin Insulator greeen (medium size) Each
24.122Staining screws for stay wire of electric pole Each
24.123Stay wire for electric pole 7/12" Metre
24.124Stay wire for electric pole 7/14" Metre
24.125Bakelite button holder shade large size Each
24.126Bakelite button holder shade Large size Each
24.127Bakelite Button Holder large size Each
24.128Bell push or bed switch Each
24.129Bakelite lamp holder Each
24.130Braket lamp holder Each
24.131Brass bracket with holder Each
24.132Brass bracket with holder Each
24.133Brass Button Holder Each
24.134Call bell 220/250 volts Each
24.135Ceiling rose bakelite Each
24.136Cut out bakelite open type Each
24.137Cut out backolite recessed type Each
24.138Electric Energy Metre Single Phase} 250 volts 10 AMP Each
24.139Electric Energy Metre Single Phase 250 volts 30 AMP Each
24.140Electric Energy Metre Single Phase 250 volts 60 AMP Each
24.141Three phase 4 wires, 400 volts: 3 x 15 Amps Each
24.142Three phase 4 wires, 400 volts:3 x 50 Amps Each
Page 18
ITEM MATERIAL UNIT RATE
24.143Three phase 4 wires, 400 volts: 3 x 80 Amps Each
24.144Electric shoe 3 pin 10/15 Amps Each
24.145Wall Shoe 3 pin 5 Amps Each
24.146Wall socket 3 pin 5 Amps Each
24.147Wall socket 3 pin 5 Amps without Shoe. Each
24.148Wall socket 3 pin 10/15 Amp open type Each
24.149Wall socket 3 pin 10/15 Amp recessed type Each
24.150Wall socket 3 pin 10/15 Amp with shoe Each
24.151Flouresent tube 40 watts Each
24.152Starter for Flourscent Tube 40 watts Each
24.153Kit kat fuses 500 volt 15/20 Amp Each
24.154Kit kat fuses 500 volt 30/35 Amp Each
24.155Kit kat fuses 500 volt 60/65 Amp Each
24.156Kit kat fuses 500 volt 100 Amp Each
24.157Kit kat fuses 500 volt 200 Amp Each
24.158Kit kat fuses 500 volt 300 Amp Each
24.159Kit kat fuses 500 volt 400 Amp Each
24.160Kit kat fuses 500 volt 500 Amp Each
24.161Leathoride paper Job
24.162Cooper nail 2" / 3" Each
24.163Cooper plates 600 x 600 x 3 mm (2' x 2' x 1/8") Kg
24.164Lightining arrestor Horn type Each
24.165Copper enamel wire No. 26 to 32 Kg
24.166Soldering and varnishing for A.C. ceiling fan each
24.167Wooden Gutties Dozen
24.168Switch double control open type (5 Amp) Each
24.169Switch double control piano type (5 Amp) Each
24.170Switch double controil ring type recessed (5 Amp) Each
24.171Switch Piano type (5 Amp) Each
24.172Switch plate type recessed (5 Amp) Each
24.173Switch ring type (5 Amp) Each
Double pole 15/20 Amp {Iron/Alminum clad 500 volt main
24.174 Each
switch with kit kat fuse}
Double pole 30/35 Amp {Iron/Alminum clad 500 volt main
24.175 Each
switch with kit kat fuse}
Double pole 60/65 Amp {Iron/Alminum clad 500 volt main
24.176 Each
switch with kit kat fuse}
Double pole 100 Amp {Iron/Alminum clad 500 volt main switch
24.177 Each
with kit kat fuse}
Tripple pole 15/20 Amp {Iron/Alminum clad 500 volt main
24.178 Each
switch with kit kat fuse}
Tripple pole 30/35 Amp {Iron/Alminum clad 500 volt main
24.179 Each
switch with kit kat fuse}
24.180Tripple pole with neutral link 30/35 Amp main switch Each
24.181Tripple pole with neutral link 60/65 Amp main switch Each
24.182Tripple pole with neutral link 100 Amp main switch Each
Iron/Aluminum clad 500 volt main switch with tripple pole
24.183 Each
and neutral link with HRC fueses: 60/65 Amps
Iron/Aluminum clad 500 volt main switch with tripple pole
24.184 Each
and neutral link with HRC fueses: 100 Amps.
Iron/Aluminum clad 500 volt main switch with tripple pole
24.185 Each
and neutral link with HRC fueses: 150 Amps.
Iron/Aluminum clad 500 volt main switch with tripple pole
24.186 Each
and neutral link with HRC fueses: 200 Amps.
Iron/Aluminum clad 500 volt main switch with tripple pole
24.187 Each
and neutral link with HRC fueses: 300 Amps.
Iron/Aluminum clad 500 volt main switch with tripple pole
24.188 Each
and neutral link with HRC fueses: 400 Amps.
Iron/Aluminum clad 500 volt main switch with tripple pole
24.189 Each
and neutral link with HRC fueses: 500 Amps.
24.190Thimble copper 60/65 Amp Each
24.191Thimble copper 100 Amp Each
24.192Thimble 150 Amp. each
24.193Thimble copper 200 Amp Each
24.194Thimble copper 300 Amp Each
24.195Thimble copper 400 Amp Each
24.196Thimble copper 500 Amp Each
24.197G.I bend " (15 mm) dia Each
24.198G.I bend " (20 mm) dia Each
24.199G.I bend 1" (25 mm) dia Each
24.200G.I bend 1" (32 mm) dia Each
24.201G.I bend 1" (40 mm) dia Each
24.202G.I. Bend 2" dia (50 mm) dia Each
24.203G.I bend 3" (80 mm) dia Each
Page 19
ITEM MATERIAL UNIT RATE
24.204M.S. Bend " (15 mm) dia Each
24.205M.S. Bend " (20 mm) dia each
24.206M.S. Bend 1" (25 mm) dia each
24.207M.S. Bend 1" (40 mm) dia each
24.208M.S. Conduit Bend 1" (32 mm) dia each
24.209M.S. Conduit Bend 1" (40 mm) dia each
24.210M.S. Conduit Bend 2" (50 mm) dia each
24.211PVC Bend " (12 mm) dia ordinary each
24.212PVC Bend " (20 mm) dia ordinary each
24.213PVC Bend 1" (25 mm) dia ordinary each
24.214PVC Bend 1" (30 mm) dia ordinary each
24.215PVC Bend 1" (40 mm) dia ordinary each
24.216PVC Bend 2" (50 mm) dia ordinary each
24.217PVC Bend 3" dia (75 mm) ordinary each
24.218PVC Bend 4" dia (100 mm) ordinary each
24.219Inspection box " (15 mm) dia Each
24.220Inspection box " (20 mm) dia Each
24.221Inspection box 1" (25 mm) dia Each
24.222M.S. Inspection box 1" (32 mm) dia per doz.
24.223M.S. Inspection box 1" (40 mm) dia to 3" (80mm) dia per doz.
24.224Hooks for " to 1" dia pipe Each
24.225 Hooks for 11/4" to 1" dia pipe Each
24.226Hook for 2" dia pipe Each
24.227Hook for 3" dia pipe Each
24.228 M.S. Conduit pipe " (15 mm) dia Per Mtr
24.229M.S. Conduit pipe " (20 mm) dia Per Mtr
24.230M.S. Conduit pipe 1" (25 mm) dia Per Mtr
24.231M.S. Conduit pipe 1" (32 mm) dia Per Mtr
24.232M.S. Conduit pipe 1" (40 mm) dia Per Mtr
24.233M.S. Conduit pipe 2" (50 mm) dia Per Mtr
24.234PVC pipe " (12 mm) dia ordinary Per Mtr
24.235PVC pipe " (20 mm) dia ordinary Per Mtr
24.236PVC pipe 1" (25 mm) dia ordinary Per Mtr
24.237PVC pipe 1" (30 mm) dia ordinary Per Mtr
24.238PVC pipe 1" (40 mm) dia ordinary Per Mtr
24.239PVC pipe 2" (50 mm) dia ordinary Per Mtr
24.240PVC Pipe 3" dia (75 mm) ordinary per mtr.
24.241PVC Pipe 4" dia (100 mm) ordinary per mtr.
24.242PVC Flexible Pipe " (12 mm) dia Per Mtr
24.243G.I. pipe " dia (15 mm i/d) Per Mtr
24.244G.I. Pipe " dia (20 mm i/d) Per Mtr
24.245G.I. Pipe 1" dia (25 mm i/d) Per Mtr
24.246G.I. pipe 1" dia (32 mm i/d) Per Mtr
24.247G.I. pipe 1" dia (40 mm i/d) Per Mtr
24.248G.I. pipe 2" dia (50 mm i/d) Per Mtr
24.249G.I. pipe 3" dia (75 mm i/d) Per Mtr
24.250G.I. Flexible Pipe " (12 mm) dia per mtr.
24.251G.I. Flexible Pipe " (20 mm) dia per mtr.
24.252G.I. Flexible Pipe 1" (25 mm) dia per mtr.
24.253G.I. Flexible Pipe 1" (32 mm) dia per mtr.
24.254G.I. Flexible Pipe 1" (40 mm) dia per mtr.
24.255G.I. Flexible Pipe 2" (50 mm) dia per mtr.
24.256G.I. Flexible Pipe 3" (80 mm) dia per mtr.
24.257G.I. Flexible pipe 4" (100 mm) each
24.258Screws 1" (25 mm) long Dozen
24.259Screws 2" (25 mm) long Dozen
24.260Screws 3" (25 mm) long Dozen
24.261Screws 4" (25 mm) long Dozen
24.262Screws 6" (25 mm) long Dozen
24.263G.I reducing socket size 2 x " (50 x 13 mm) each
24.264G.I Reducing socket 2 x " dia (50 x 20 mm) each
24.265Boring " dia Metre
24.266G.I. Socket " (12 mm) dia each
24.267G.I. Socket " (20 mm) dia each
24.268G.I. Socket 1" (25 mm) dia each
24.269G.I. Socket 1" (32 mm) dia each
24.270G.I. Socket 1" (40 mm) dia each
24.271G.I. Socket 2" (50 mm) dia each
24.272G.I. Socket 3" (80 mm) dia each
24.273Brass Socket 1" (40 mm) dia each
24.274Brass Socket 2" (50 mm) dia each
24.275Brass Socket 4" (100 mm) dia each
24.276PVC Socket " (12 mm) dia each
Page 20
ITEM MATERIAL UNIT RATE
24.277G.I. Nipple " (12 mm) dia each
24.278G.I. Nipple " (20 mm) dia each
24.279G.I. Nipple 1" (25 mm) dia each
24.280G.I. Nipple 1" (32 mm) dia each
24.281G.I. Nipple 1" (40 mm) dia each
24.282G.I. Nipple 2" (50 mm) dia each
24.283G.I. Nipple 3" (80 mm) dia each
24.284Brass nipple 1" dia (25mm) each
24.285Brass Nipple 1" dia (32 mm) each
24.286Brass Nipple 1" (40 mm) dia each
24.287Brass Nipple 2" (50 mm) dia each
24.288Brass Nipple 4" (100 mm) dia each
24.289PVC Nipple " (12 mm) dia each
24.290Brass Check nut " (12 mm) dia each
24.291Brass check nut 1" (40 mm) each
24.292Brass check nut 1" (25 mm) each
24.293Brass check nut 1" (32 mm) each
24.294Brass check nut 2" (50 mm) each
24.295Brass check nut 4" (100 mm) each
24.296Check Nuts " (12 mm) dia each
24.297Check Nuts " (20 mm) dia each
24.298Check Nuts 1" (25 mm) dia each
24.299Check Nuts 1" (32 mm) dia each
24.300Check Nuts 1" (40 mm) dia each
24.301Check Nuts 2" (50 mm) dia each
24.302Check Nuts 3" (80 mm) dia each
24.303M.S Box 4" x 4" (100 x 100 mm) each
24.304M.S Box 7" x 4" (175 x 100 mm) each
24.305M.S Box 9" x 4" (225 x 100 mm) each
24.306M.S Box 8" x 10" (200 x 250 mm) each
24.307M.S Box 10" x 12" (250 x 300 mm) each
24.308M.S Box 12" x 14" (300 x 350 mm) each
24.309Angle iron board including paints (9"x9"x1") each
24.310Angle Iron board including paint (9"x12"x1") each
24.311Angle Iron board including paint (10"x12"x1") each
24.312Angle Iron board including paint (12"x15"x1") each
24.313Angle Iron board including paint (12"x18"x1") each
24.314Angle Iron board including paint (10"x15"x1") each
24.315Anle Iron board including paint (15"x18"x1") each
24.316Copper strip 1" x 1/8" x 14" (40 x 3 x 350 mm) each
24.317Copper strip 14" x 2" x 1/8" to 3/16" (350 x 50 x 3 mm to 6 each
24.318Copper strip 14" x 2" x 1/4" (350 x 50 x 6 mm) to 6mm each
24.319Rag bolts 9" x 5/8" (225 x 16 mm) each
24.320Reg bolts 12" x 5/8" (300 x 16 mm) each
24.321Eye bolts Each
24.322Eye bolts (bigger size) for straining posts, stiffening post Each
24.323PVC/weather proof cable 3/0.029" (3/0.74 mm) Single core per mtr.
24.324PVC/weather proof cable /0.029" (7/0.74 mm) Single core per mtr.
24.325PVC/weather proof cable /0.036" (7/0.91 mm) Single core per mtr.
24.326PVC/weather proof cable /0.044" (7/1.12 mm) Single core per mtr.
24.327Nut & Screw Each
24.328Straining Screw for electric pole Each
24.329Sal wood casing for wiring Per mtr.
24.330Wooden strip casing Per % mtr.
24.331Insulated cleat (small) each
24.332Insulated cleat (big size) each
24.333Leather or wooden cleats each
24.334M.S Hooks each
24.335M.S bar hook 3/8" (!0 mm) dia each
24.336Canopy nipple & hook Per Job
24.337Hook 5/8" (16 mm) with nut & bolts each
24.338Girder clamp hook 5/8" (16 mm) each
24.339PVC bushes " (12 mm) dia each
24.340Glazed porcelain (Imported) each
24.341Glazed Porcelain counter weight with accessories each
24.342VIR/PVC cable 3/0.29 per mtr.
24.343Brass lamp holder each
24.344Brass lamp holder each
24.345Brass lamp holder each
24.346Double cone reflector each
24.347Switch ring type each
24.348Switch 10/15 Amp each
24.349Switch 10/15 Amp. recessed each
Page 21
ITEM MATERIAL UNIT RATE
24.350Plug 3 pin and switch (combined) 10/15 Amp. each
24.351Plug 3 pin and switch (recessed) 10/15 Amp. each
24.352Pole mounted street light holder shade and glass each
24.353Frame with holder Per Job
24.354Frame set Per Job
24.355Round tube 32 watts each
24.356Starter each
24.357Choke each
24.358Holder each
24.359Base patti for tube light each
24.360Ball bearing size (6201, 6202, 6203) each
24.361Plastic cover each
24.362Handle chromium plated for iron box each
24.363Nut & bolts " (12 mm) dia 1" (40 mm) long each
24.364T - Iron " x 1" x 1" x 5" P.kg
24.365Clamps P. Kg.
24.366Steel channel 75 x 40 x 3 mm P.Kg.
24.367steel plate 3"x1"x" )75x40x40 mm) P.Kg.
24.368 Steel plate 3"x 3/4 x 3/4 (75 x 20 x 20 mm) per kg
24.369Bolts and nuts 5/8" dia (16 mm) Each
24.370Double clamp for anchor rod henley type for pole Each
24.371Double clamp 9" dia (225 mm) Each
24.372Clamps with bolts & nuts etc. for street pole each
24.373Clamp double for erection of house service pipe Henley each
24.374Clamp 2" dia (50 mm) each
24.375Steel clamp " dia (12 mm) each
24.376G.I clamp (small) each
24.377G.I. Clamp (large) each
24.378Pole clamp with bolt & nuts for street light pole each
24.379Shakle insulator each
24.380M.S bolts for suport each
24.381Copper wire No.2 to 10 per kg
24.382G.I wire (all size) per kg
24.383Cut out each
24.384Wooden & leather cleats each
24.385Vapour mercury lamp 125 watt with choke set each
24.386Vapour mercury lamp 250 watt with choke set each
24.387Silver paint P.Gln
24.388G.I Nuts & Bolts 2" long " (50 mm x 13 mm) each
24.389G.I Nuts & Bolts 1" x " long (40 x 6 mm) each
24.390Copper wire No.16 & 20 SWG per kg
24.391Copper Wire Old per kg
24.392Enemal wire No.26 SWG to 32 SWG per kg
24.393 Copper tap 1" to 2" x1/8" per kg
24.394Copper rod 1" dia (25 mm) per kg
24.395Copper nail (small) each
24.396Copper stapple each
24.397Soldering and Vernishing each
24.398Salt per kg
24.399Loop wire 4 loop 3/0.029 (3/0.74 mm) Rft
24.400Knob with shaff and plate each
25.001Locking arrangements with sliding bolt 1' long and 1" dia Each
25.002Hard wood stair railing Rft
25.003M.S. Channels Kg
25.004Steel beam Kg
25.005Steel chisel P.Kg.
25.006Grating 3/4"x3/4" size P.Kg.
25.007M.S. Box section of 16 SWG 1" x 3" hand rail P.Rft
25.008Conduit pipe 2" dia including specials P.Ft
25.009Roller 3" dia each
25.010Rivets with heads 2" long Each
25.011Rivets 1" long Each
25.012Locking arrangement collapsible gate Each
25.013 Handles 12" long of 3/4"x1/4" steel channels for collapsibl Each
25.014GI sheet 24 SWG P.Kg.
25.015GI bracket for railing shutter Each
25.016GI Holdfast for railing shutter Each
25.017GI Pipe 1" dia (light quality) P. Rft
25.018Handle for railing shutter Each
25.019GI spring for railing shutter Each
25.020Rolling gear for railing shutter Each
25.021Iron Holdfast for steel windows Each
25.022GI pipe 2" dia (light quality) P. Foot
Page 22
ITEM MATERIAL UNIT RATE
1 5
25.023 Window hinges /4" thick with /16" dia pins Each
25.024Brass casement handle 6" for steel windows Each
25.025Mild steel casement stay 15" long for steel windows Each
25.026Wooden strips for fixing glass pans P.Rft
25.027Steel glazing clips for fixing glass panes Each
25.028Glass panes 2 mm thick P. Sft.
25.029Glass panes 2.5 mm thick P. Sft.
25.030Glass panes 3 mm thick P. Sft.
25.031Glass panes 4 mm thick P. Sft.
25.032Glass panes 5 mm thick P. Sft.
25.033M.S. moulded tubular pipe of 18 SWG P.Kg.
25.034Brass hinges (4" long) Each
25.035Brass Handles (4" long) Each
25.036U' shapped rubber linning (" thick) P. Rft
25.037Wire gauze galvanized 24 SWG (12x 12 mesh) P.Sft.
25.038 x M.S square box of 16 SWG for fixing wire gauge P. Kg.
25.039C.P. tower bolt (225 mm long) Each
25.040Brass handle special type for steel windows Each
25.041G.I. Stay for windows Each
1
25.042 Grill of M.S. flat "x /8" with frame P. Sft.
25.043Cost of flaps including hinges for G.I. Pipes Each
25.044Steel grating P.Sft
25.0451 ft. long M.S. U-Clamp 3/4" dia threaded at both ends incl Each
25.046Painting small detached articles not exceding 1" sft. Each
3
25.047 Aluminum frame 100x20mm (4"x /4") Rft
25.048Aluminum frame 100x40mm (4 x1") Rft.
25.049Aluminum frame 60x40mm (1" x 2") Rft.
3
25.050 Aluminum frame 50x20mm (2" x /4") Rft.
25.051Aluminum leaf edging for aluminium windows Rft.
25.052Tinted glass 5mm thick Sft.
25.053Aluminum tringular gola and gasket Rft.
25.054Pivot for aluminium doors each
25.055Alimuninum tower bolt 9" long each
25.056locking arrangement each
25.057Handle Large Rft
25.058Rubber gasket for Aluminium Windows Rft.
25.059Latch for Aluminium Windows each
25.060Steam Coal P. Kg.
26.0017 Strand barbed wire P.Kg.
26.002Anti termite (Heptachlore) P-Ltr
26.003Cane Singapore Per Kg.
26.0043/16" dia washers for straining posts, stiffening posts & in Dozn
26.005Cost of bamboo 10' to 12' long Each
26.006Cost of iron shoes for survey Jhandy Each
26.007Cost of red cloth for survey Jhandy Each
26.008Cost of ordinary wood for pegs P. Cft.
26.009Hooks for fixing iron gauges Dozen
26.010Filling cement bags with coal Per Kg.
26.011Cost of manure per Cart
26.012Polythene sheet of 300 gauge (0.003 thick) P.Kg.
26.013Soap P. Kg.
26.014Eye bolt Each
26.015Primer (Zinc) P. Kg.
26.016Weather Sheet Paint P. Lt
Page 23
CHAPTER NO. 26
MISCELLANEOUS
DESCRIPTION OF ITEM:
Note : The board is to be of cement plaster " (12 mm) thick with 2" (50
1" (25mm) thick beading
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
ITEM RATE
Page 1
2. Fixing handles to iron hammers.
FOR 12 NOS.
LABOUR
ITEM RATE
Page 2
3. Providing and fixing barbed wire fencing with 4 horizontal and 2 number cross wires fixed
(1:2:4) straining posts 7'x9"x9" (2.14m x 225mm) at 100' (30m) centre to centre stiffenin
x 15 mmx 50mm) at 50' (15m) interval and intermediate posts 7'x5"x5" at 8' centre to centr
steel, its fabrication and placing of steel reinforcement, eye bolt, washers, etc. complet
Page 3
B / F : -
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent # -
Total -
i) R.C.C. work (Item 6a(ii) Chap. 6) 9.25 Cft. 0.00 Per Cft. -
ii) Fabrication of steel work 9Item 9(b) Chap. 6) 38.89 Kg. 0.00 Per Kg. -
iii) Blacksmith for wire fencing
erection. 0.75 No. 0.00 Per day -
iv) Coolies 2.00 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
4. Supplying bamboo jhandies 10' to 12' (3m to 2054m) with iron shoes and flag 15" (375 mm) s
Page 4
Rate
Qty Per Unit Amount
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 5
5. Supplying wooden pegs for leveling 1" (40mm) dia 6" (150mm) long
LABOUR
ITEM RATE
Page 6
6. Supplying wooden pegs for alignment 2" to 3" (50 to 75mm) dia 9" (225mm) long
MATERIAL
Total -
LABOUR
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 7
7. Fixing enamalled iron gauges flush with masonry including cost of hooks.
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total for 20 Lft. -
LABOUR
ITEM RATE
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 30 Nos. -
ITEM RATE
Page 8
9. Fixing mainline iron distance marks in position including making 1:3;6 cement concrete blo
size of block 10x14"x15" = 14.58 Cft.
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 9
10. Cutting Pipes upto 2" (50mm) dia.
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 30 Nos. -
ITEM RATE
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 25 Nos. -
ITEM RATE
Page 10
12. Threading pipe ends 1" to 4" (40 mm to 100 mm) dia
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 30 Nos. -
ITEM RATE
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 800 Lft. -
ITEM RATE
Page 11
14. Boring and fixing 1" (40mm) dia pressure pipe
a) In ordinary soil
Fitter 1.00 No. 0.00 Per day -
Coolies 3.50 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 40 Lft. -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 40 Rft. -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 40 Rft. -
ITEM RATE
Page 12
15. Repair to hand pumps pulling out and re-fitting.
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 50 Rft. -
ITEM RATE
LABOUR
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 13
17. Washing Niwar of Bed
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 14
18. Washing Durries
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
-
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 15
19 Recaning Chairs.
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 16
19 (i Office chairs double caning seat only
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 17
19 (i Office chairs single caning back only
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 18
19 (i Office chairs double caning back only
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total for 5 Nos. -
LABOUR
Total -
Sundries 10.00 Percent -
-
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 19
19 (v Easy chairs single caning seat only
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
-
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 20
19 (v Easy chairs double caning seat only
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 21
19 (v Easy chairs, single caning only back and seat in one piece.
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 22
19 (v Easy chairs double caning back and seat in one piece or couches (caned area
about 16 Sft. 1.50 Sqm)
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 23
20 Making and fixing hat pegs ordinary
MATERIAL
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 24
21. Weaving charpoys
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Say -
ITEM RATE
22 Sweeping Chimneys
MATERIAL
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 25
23. Picture, railing including making, fixing and painting
1 Deodar wood for 0.3' x 0.1' x 1.5' = 0.45 Cft 0.50 Cft 0.00 Per Cft. -
+ coastage 10% = 0.05
2 Paint 0.38 / 0.04 Gallon 0.00Per Gallon
3 Nails 0.006 Kg. 0.00 Per Kg. -
4 Brush 0.05 No. 0.00 Each -
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
-
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 26
24. Cutting fuel wood from plantation
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 385 Kg. -
ITEM RATE
Page 27
26 Burning charcoal including loading unloading and repairing kiln
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
27. Filling cement bags with coal and sewing including cost of string.
LABOUR
1 Coolies Unskilled 10.25 Nos 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Labour Rate Per 100 Cft. Rs. Say 0.00
Labour Rate Per Cum Rs. Say 0.00
Composite Rate Per 100 Cft. Rs. Say 0.00
Composite Rate Per Cum Rs. Say 0.00
Page 28
28. Supply manure (capacity of cart 200 ft. or 0.57 cum)
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 29
30 Washing
a) Table Cloth
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 10 Nos. -
ITEM RATE
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 15 Nos. -
ITEM RATE
Page 30
31 Hoisting and placing sleepers for centring, including carriage within one chain.
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 40 No.s -
ITEM RATE
32. Dismantling sleeper from centring including stacking within one chain
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 31
33. Dredging sumps
LABOUR
ITEM RATE
34. Fixing 'U' bolt in masonry or concrete including leveling and tying for fixing angle iron
post.
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 12 Nos. -
ITEM RATE
Page 32
35. Bailing out water
a) By hand
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 33
35 b) By pump (Rate including cost of pump P.O.L etc. and operational charges)
i) Depreciation
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 34
36 Drilling holes in R.C. trough
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total for 12 Nos. -
ITEM RATE
Page 35
37. Supplying and Laying polythene sheet over D.P.C., under floor and on roof etc.
MATERIAL
Total
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 36
37 ii 500 Gauge (0.005" thick)
MATERIAL
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 37
38. Laying 2" thick sand and bitumen carpet on top of foundation of oil tanks
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 38
39 Cutting hole 4" x 6" in stone masonry or brick wall with chisel, repairing masonry and
removing debris within one chain lead.
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
40 Making 1"x1" groove in wall of stone or brick masonry in cement for fixing planks upto
9" deep.
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 39
41. Drilling holes in stone or bricks masonry upto 2" dia, per inch depth.
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Labour Rate Per Hole per Inch Depth Rs. - Say 0.00
Per CM Rs/ - Say 0.00
Page 40
42 Spraying anti termite liquid mixed with water in the ratio of (1.40)
Detail Unit Rate Per 100 Sft. / Assumed for 1000 Sft.
Rate
Qty Per Unit Amount
Total -
Contractor's Profit & Ove 20.0 Percent -
Total -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 41
43 Providing and fixing barbed wire fencing with 4 horizontal and two cross wires, with RCC
1:2:4 posts 5.5' x 6" x9" at 8 ft. centre to centre. Reinforced with 4 number 3/8" dia ve
1/8" dia stirrups 12" centre to centre, complete in all respects.
LABOUR
i) RCC as per item 6 - a (i) Chap. Concrete 13.40per Cft 0.00 Per Cft. -
ii) Fabrication of steel as per item 9 (b) Chap. 25.51 Per Kg. 0.00 Per Kg. -
iii) Fixing barbed wire black smith 0.75 No. 0.00 Per day -
Coolies 2.00 Nos. 0.00 Per day -
Total -
Sundries (Item-III) 10.00 Percent # -
Contractor's Profit & Ove 20.00 Percent # -
Total for 48 Rft. -
Page 42
ii) In cement concrete base. (1:4:8) of size 12"x12"x21")
i) RCC Post (1:2:4) as per part (i) Ref. 6 a (i) 13.40 Cft. Per Cft.
i) RCC (1:2:4) (Rate as per item 6 a (i) of Chap 13.40 Cft. 0.00 Per Cft. -
ii) PCC (1:4:8) (Rate as per item 3 b of Chap No. 9.55 Cft. 0.00 Per Cft.
iii) Fabrication of steel as per item 9 (b) of Chap 25.51 Kg. 0.00 Per Kg.
Page 43
CHAPTER NO. 17
OUTLETS
DESCRIPTION OF ITEM:
1.0 Earth Work for Outlet excavation, refilling, ramming and Puddling
Rate for all finished works include the removal of the surplus debris un-used material and by
LABOUR
ITEM RATE
LABOUR
ITEM RATE
Page 1
c) Channels discharge from 101-200 Cs.
ITEM RATE
ITEM RATE
ITEM RATE
Labour Rate Per Job Rs. 0.00 = - Say -
1.5
Page 2
2. Dismantling Outlets
Note : These rates are for total dismantlement and removal of material. The rates do
not include earth work for which rates are given in item No. 1 above
LABOUR
ITEM RATE
LABOUR
ITEM RATE
Page 3
c) A.P.M. or O.F.H from 2.1 ft. (635mm) to 3.00 ft. (915mm)
ITEM RATE
ITEM RATE
ITEM RATE
Page 4
f) Tail cluster trifurcation
LABOUR
ITEM RATE
LABOUR
ITEM RATE
Page 5
3 Making Temporary A.P.M. Bricks Block and fixing at Site
MATERIAL
LABOUR
ITEM RATE
4 Dismentalling Walls, taking out Temporary A.P.M. Bricks Block and fixing
iron block and rebuilding dismantled walls.
LABOUR
ITEM RATE
Page 6
5 Dismantling walls and fitting iron block of O.F. Outlets
ITEM RATE
6 Constructing watching and removing bund for outlet built in running water
LABOUR
a) Upto 3.0 ft. (915mm) depth
ITEM RATE
ITEM RATE
Page 7
7 Adjusting 'B' of tail cluster by dismantling and rebuilding throat walls.
MATERIAL
ITEM RATE
MATERIAL
ITEM RATE
Labour Rate for Each Rs. 0.00 = - Say -
1.5
Composite Rate for Each Rs. Say -
Page 8
9 Extra Labour in Fixing A.P.M. and O.F. Outlets block including Dressing of Bricks.
MATERIAL
ITEM RATE
MATERIAL
ITEM RATE
Labour Rate for Each Rs. 0.00 = Say -
1.25
Composite Rate for Each Rs. = Say -
Page 9
c) For Channel depth of 3.0 ft. (915mm)
MATERIAL
ITEM RATE
MATERIAL
ITEM RATE
Page 10
e) For Channel depth of less than 2.0 ft (610mm)
MATERIAL
ITEM RATE
MATERIAL
LABOUR
ITEM RATE
Page 11
11 Laying Iron Pipes of Outlets
ITEM RATE
12 Water allowance for constructing outlets or culverts when canal water is not flowing
ITEM RATE
ITEM RATE
Page 12
13 Hoisting and placing R.C. slabs or stone in position in outlets or W.C. culverts
LABOUR
ITEM RATE
LABOUR
1 Mason 0.25 No. per day -
2 Cooly (Unskilled) 2.00 Nos. per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Grand Total -
ITEM RATE
Labour Rate Per Foot Rs. 0.00 = Say -
15
Compsite Rate for Foot Rs. 0.00 = Say -
15
Labour Rate per Metre Rs. = Say -
Page 13
b) Portion under road beyond bank
MATERIAL
LABOUR
ITEM RATE
LABOUR
ITEM RATE
Page 14
b) Portion Under Road Byond Bank
LABOUR
ITEM RATE
16 Changing Pipe Outlets by removing One Pipe and replacing it at the same site
with another pipe complete with earth and puddling
MATERIAL
LABOUR
Page 15
b) Portion Under Road Beyond Bank
MATERIAL
1 Cement for Joining R.C. Collar 0.20 Bag Per Bag -
2 Sand 1.00 Cft. Per 100 Cft -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
LABOUR
ITEM RATE
Page 16
CHAPTER NO. 13
DESCRIPTION OF ITEM NO 1:
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 1
Item No. 1
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Unskilled Cooly 0.20 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 2
DESCRIPTION OF ITEM NO 2: Brushing and Scraping blisters of old paint
wood works.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
N I L
Labour
Rate Analysis for 125 Sft
Unskilled Cooly 0.50 No P. Day -
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
1.25
Page 3
DESCRIPTION OF ITEM NO 3: Scraping, brushing and removing old paints
metal surface.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
N I L
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
1.25
Page 4
DESCRIPTION OF ITEM NO 4: Painting old surfaces.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Painter 0.33 No P. Day -
Unskilled Cooly 0.33 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 5
Item No. 4 Painting old surfaces.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Painter 0.25 No P. Day -
Cooly 0.25 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 6
Item No. 4 Painting old surfaces.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Painter 0.20 No P. Day -
Unskilled Cooly 0.20 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 7
Item No. 4 Painting old surfaces.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Painter 0.17 No P. Day -
Unskilled Cooly 0.17 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 8
Item No. 4 Painting old surfaces.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Painter 0.33 No P. Day -
Unskilled Cooly 0.33 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 9
Item No. 4 Painting old surfaces.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Painter 0.25 No P. Day -
Unskilled Cooly 0.25 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 10
Item No. 4 Painting old surfaces.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Painter 0.20 No P. Day -
Unskilled Cooly 0.20 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 11
Item No. 4 Painting old surfaces.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Painter 0.17 No P. Day -
Unskilled Cooly 0.17 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 12
Item No. 4 Painting old surfaces.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Rft
Painter 0.17 No P. Day -
Unskilled Cooly 0.17 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 13
Item No. 4 Painting old surfaces.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Rft
Painter 0.12 No P. Day -
Unskilled Cooly 0.12 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 14
Item No. 4 Painting old surfaces.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 200 Nos
Painter 1.00 No P. Day -
Unskilled Cooly 0.25 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 15
Item No. 4 Painting old surfaces.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 175 No.
Painter 0.75 No P. Day -
Unskilled Cooly 0.25 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 16
Item No. 4 Painting old surfaces.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 175 No.
Painter 2.00 No P. Day -
Unskilled Cooly 0.50 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 17
Item No. 4 Painting old surfaces.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 175 No.
Painter 1.00 No P. Day -
Unskilled Cooly 0.50 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 18
DESCRIPTION OF ITEM NO 5:
a) Painting/ new surface preparing surface and
painting corrugated surface, patent roofing etc.
i) Priming Coat
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 19
Item No. 5
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Painter 0.25 No P. Day -
Unskilled Cooly 0.08 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 20
Item No. 5
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Painter 0.25 No P. Day -
Unskilled Cooly 0.08 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 21
Item No. 5
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Painter 0.12 No P. Day -
Unskilled Cooly 0.12 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 22
Item No. 5
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 23
Item No. 5
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Painter 0.25 No P. Day -
Cooly 0.08 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 24
Item No. 5
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 25
Item No. 5
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Painter 0.12 No P. Day -
Unskilled Cooly 0.12 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 26
Item No. 5
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per 100 Lft Rs. Say -
Labour Rate Per Rm Rs. Say -
Page 27
Item No. 5
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Rft
Painter 0.08 No P. Gln -
Unskilled Cooly 0.08 No P. Gln -
Total -
Sundries ##### Percent -
Total -
Page 28
Item No. 5
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Nos
Painter 0.75 No P. Day -
Unskilled Cooly 0.75 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 29
Item No. 5
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 No
Painter 0.40 No P. Day -
Unskilled Cooly 0.33 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 30
Item No. 5
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per 100 Nos Rs. Say -
Page 31
Item No. 5
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 No
Painter 0.75 No P. Day -
Unskilled Cooly 0.50 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 32
Item No. 5
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Painter 0.06 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 33
DESCRIPTION OF ITEM NO 6: Applying Khanki Mixture hot to barrage gate
i) First Coat.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Coaltar 0.75Cwt ( 38) Kg P. Kg -
Mineralpitch 10Lbs (4. 5) Kg P. Kg -
Slaked lime 9Lbs (4 ) Kg P. Kg -
Kerosene Oil 1Gln (4. 55) Ltr P. Ltr -
Fuel Wood 32.45 Kg. P. Kg -
-
Material
For 100 Sft
i) First Coat
= 0.00
20
Brushes 0.18 No. Each -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Painter 0.25 No P. Day -
Unskilled Cooly 0.25 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 34
Item No. 6 Applying Khanki Mixture hot to barrage gates.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
For 100 Sft
ii Second Coat Material 0.62 of Item No. (6-I)
0.62 -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Painter 0.16 No P. Day -
Unskilled Cooly 0.25 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 35
DESCRIPTION OF ITEM NO 7: French polishing complete.
a) On new works.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 175 Sft
Polisher 4.50 No P. Day -
Unskilled Cooly 1.00 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 36
Item No. 7 French polishing complete.
b) Old work.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 175 Sft
Polisher 2.00 No P. Day -
Unskilled Cooly 1.00 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 37
DESCRIPTION OF ITEM NO 8: Varnishing wood work, including cleaning an
preparing surface.
a) First Coat.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Polisher 0.20 No P. Day -
Unskilled Cooly 0.20 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 38
Item No. 8 Varnishing wood work including cleaning and
preparing surface.
b) Second Coat.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 200 Sft
Polisher 0.10 No P. Day -
Unskilled Cooly 0.10 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 39
Item No. 8 Varnishing wood work including cleaning and
preparing surface.
c) Third Coat.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 200 Sft
Polisher 0.10 No P. Day -
Unskilled Cooly 0.10 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 40
DESCRIPTION OF ITEM NO 9: Bitumen coating to plastered or cement conc
surface.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Unskilled Cooly 0.50 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 41
Item No. 9 Bitumen coating to plastered or cement concrete
surface.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Cooly 0.40 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 42
Item No. 9 Bitumen coating to plastered or cement concrete
surface.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Cooly 0.33 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 43
DESCRIPTION OF ITEM NO 10: Writing letters or figures per letter, per
height.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 100 Nos
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Page 44
DESCRIPTION OF ITEM NO 11: Writing letters or figures at any surface w
reflective paint of approved quality and co
letter, per inch height.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
nalysis for 100 Letters, P. Inch Height
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Page 45
DESCRIPTION OF ITEM NO 12: Writing letters or figures on any surface w
reflective tape of approved quality and col
letter, per inch height.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
nalysis for 100 Letters, P. Inch Height
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Rate Per Plinth, Per Inch height 0.59
Labour
Total -
Sundries ##### Percent -
Total -
Page 46
DESCRIPTION OF ITEM NO 13: Coaltar Painting.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Skilled Cooly 0.33 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 47
Item No. 13 Coaltar Painting.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Skilled Cooly 0.20 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 48
DESCRIPTION OF ITEM NO 14: Solignum Painting.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Painter 0.33 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 49
Item No. 14 Solignum Painting.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 150 Sft
Painter 0.50 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 50
DESCRIPTION OF ITEM NO 15: Creosote Painting.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Painter 0.33 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 51
Item No. 15 Creosote Painting.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Painter 0.50 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 52
DESCRIPTION OF ITEM NO 16: Burning off or rubbing down with pumice sto
paint from wood work.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Skilled Cooly 1.00 No P. Day -
Unskilled Cooly 0.25 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 53
DESCRIPTION OF ITEM NO 17: Removing with caustic soda, old paint from
work.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Cooly 0.50 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 54
DESCRIPTION OF ITEM NO 18: Painting distance marks for white ground an
lettering on both faces.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 10 Nos
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Page 55
DESCRIPTION OF ITEM NO 19: Painting two feet (M) with gauge reading to
a foot (M).
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 10 Rft
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Page 56
DESCRIPTION OF ITEM NO 20: Painting sounding rods and other gauge, rea
10th of a foot (M).
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 10 Rft
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Page 57
DESCRIPTION OF ITEM NO 21: Painting levelling staves.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 10 Rft
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Rate Per Rft 0.00 -
10
Labour
Rate Analysis for 15 Rft
Painter (Artist) 2.00 Nos P. Day -
Cooly 1.00 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 58
DESCRIPTION OF ITEM NO 22:
a) Painting and lettering mile/Km stones on bo
i) One Coat.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 2 Nos
Painter (Artist) 1/7 No P. Day
Unskilled Cooly 1/7 No P. Day
Total -
Sundries ##### Percent -
Total -
Page 59
Item No. 22
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 2 Nos
Painter (Artist) 0.25 No P. Day -
Cooly 0.25 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 60
Item No. 22
i) One Coat.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 8 No.
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Page 61
Item No. 22
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 8 No.
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Rate Per No.
Contractor's Profit & Ove ##### Percent -
Total -
Rate Per 100 Sft. -
Item Rates
Labour Rate Per Each Rs. Say -
Page 62
Item No. 22
i) One Coat.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1.5 Nos.
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Page 63
Item No. 22
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1.5 Nos
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Page 64
DESCRIPTION OF ITEM NO 23: Removing paint or varnish from wall.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Sft
Labour
Total -
Sundries ##### Percent -
Total -
Page 65
DESCRIPTION OF ITEM NO 24: Scraping from hydraulic gates.
a) Khanki Paint.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Sft
Labour
Total -
Sundries ##### Percent -
Total -
Page 66
Item No. 24 Scraping from hydraulic gates.
b) Aluminium paint.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Sft
Labour
Total -
Sundries ##### Percent -
Total -
Page 67
DESCRIPTION OF ITEM NO 25: Painting lettering with shade.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
nalysis for 100 Letters, P. Inch Height
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
36.85 0.37
Labour 100
Rate Analysis for 150 Letters
Painter (Artist) 1.60 No P. Day -
Unskilled Cooly 1.60 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 68
DESCRIPTION OF ITEM NO 26: Scraping rust for old rail or girders.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Unskilled Cooly 1.50 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 69
DESCRIPTION OF ITEM NO 27: Chiselling old paint from brick work.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Unskilled Cooly 2.00 Nos P. Day -
Total -
Sundries ##### Percent -
Total -
Page 70
DESCRIPTION OF ITEM NO 28: Cleaning glasses with chalk and spirit etc
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 600 Sft
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Page 71
DESCRIPTION OF ITEM NO 29: Cleaning and oiling rafter or rolled steel
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Cooly 0.50 Nos P. Day -
Total -
Sundries ##### Percent -
Total -
Page 72
DESCRIPTION OF ITEM NO 30: Cleaning and painting punkha poles, includi
fixing hooks.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 3 Nos
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Page 73
DESCRIPTION OF ITEM NO 31: Preparing surface and painting with emulsio
a) First Coat.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Painter 0.33 No P. Day -
Unskilled Cooly 0.06 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 74
Item No. 31 Preparing surface and painting with emulsion paint.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Painter 0.25 No P. Day -
Unskilled Cooly 0.05 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 75
DESCRIPTION OF ITEM NO 32: Preparing surface and painting with water p
coloured cement finish, like duracem, buxce
other finishes with similar specifications
etc.
a) New Surface
i) Ist Coat.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Painter 0.33 No P. Day -
Unskilled Cooly 0.06 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 76
Item No. 32 Preparing surface and painting with water proof
coloured cement finish, like duracem, buxcem or
other finishes with similar specifications on walls,
etc.
a) New Surface
ii) 2nd Coat and subsequent coat.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 125 Sft
Painter 0.25 No P. Day -
Unskilled Cooly 0.05 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 77
Item No. 32 Preparing surface and painting with water proof
coloured cement finish, like duracem, buxcem or
other finishes with similar specifications on walls,
etc.
b) Old Surface
i) Ist Coat.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 78
Item No. 32 Preparing surface and painting with water proof
coloured cement finish, like duracem, buxcem or
other finishes with similar specifications on walls,
etc.
b) Old Surface
ii) 2nd Coat and subsequent coat.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 79
Item No. 32A Providing and applying weather shield paint of approved
quality on external surface of building including
preparation of surface application of primer complete
in all respects.
a) New Surface
i) Ist Coat
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
i) Varnish 1 kg P. Kg -
ii) Putty and sand paper (L.S) 1 LS L.S -
iii) Primer (Zine) 1 Kg (for % Sft) @ Rs.80.00 per Kg. 1 P. Kg -
iv) Weather shield paint 0.7 Litre (for 100 Sft) 0.7 -
@ Rs.120.00 per Litre
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per % Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 80
Item No. 32A Providing and applying weather shield paint of approved
quality on external surface of building including
preparation of surface application of primer complete
in all respects.
a) New Surface
ii) 2nd Coat
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per % Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 81
Item No. 32A Providing and applying weather shield paint of approved
quality on external surface of building including
preparation of surface application of primer complete
in all respects.
b) Old Surface
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per % Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 82
DESCRIPTION OF ITEM NO 33: Painting traffic lanes 5" (125mm) wide with
marking enamel.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 700 Rft
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Page 83
DESCRIPTION OF ITEM NO 34: Painting traffic lanes 5" (125mm) wide with
paint, complete in all respects. marking en
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 700 Rft
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Page 84
DESCRIPTION OF ITEM NO 35: Repainting of ceiling fan (all sizes and ty
including painting of blades, canopy, suspe
rod and regulator, with suitable enamel pai
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 14 No
Painter 1.00 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 85
DESCRIPTION OF ITEM NO 36: Repainting of iron poles with cross arms, w
bitumen or other approved paint.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 6 Nos
Painter 1.00 No P. Day -
Total -
Sundries ##### Percent -
Total -
Page 86
DESCRIPTION OF ITEM NO 37: Repainting of pipes and specials of G.I. M
conduit etc. fixed on surface for electric
with approved paint.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Rate Analysis for 7 Metre
Paint 0.1Ltr (0. 022) Gln P. Gln -
Brush 0.12 No. Each -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per Rm Rs. Say -
Composite Rate Per Rm Rs. Say -
Page 87
Item No. 37 Repainting of pipes and specials of G.I. M.S. or
conduit etc. fixed on surface for electric wiring
with approved paint.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Rate Analysis for 7 Metre
Paint 0.2Ltr (0. 044) Gln P. Gln -
Brushes 0.12 No. Each -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per Rm Rs. Say -
Composite Rate Per Rm Rs. Say -
Page 88
Item No. 37 Repainting of pipes and specials of G.I. M.S. or
conduit etc. fixed on surface for electric wiring
with approved paint.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Rate Analysis for 7 Metre
Paint 0.3Ltr (0. 066) Gln P. Gln -
Brushes 0.18 No. Each -
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Rate Analysis for 60 Metre
Painter 1.00 No P. Day -
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per Rm Rs. Say -
Composite Rate Per Rm Rs. Say -
Page 89
DESCRIPTION OF ITEM NO 38: Repainting main switches and branch distrib
boards of all sizes and types, with approve
(complete set).
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Item Rates
Labour Rate Per Each Rs. Say -
Page 90
DESCRIPTION OF ITEM NO 39: Extra labour for painting, varnishing, etc
(6 M) height and above, for every additiona
(3.05 M) height, or scaffolding.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Sft
Labour
Total -
Sundries ##### Percent -
Total -
Page 91
CHAPTER NO. 16
1 Cutting pilchi frash or sarkanda including carriage within one mile (1.6 Km.)
ITEM RATE
DESCRIPTION OF ITEM
2 Weaving matresses
LABOUR
ITEM RATE
Page 1 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
3 a) Supplying and filling jute bags 1.25 Cft. capacity with sand or earth sewing and
stacking in dry
MATERIAL
LABOUR
ITEM RATE
Page 2 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
b) Supplying and filling jute bags 1.25 Cft. Capacity with sand or earth sewing
and laying in position under water
MATERIAL
LABOUR
ITEM RATE
Page 3 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
4 a) Supplying and filling new jute bags 4 to 5 Cft. capacity, with sand or earth
Sewing and stacking in dry.
MATERIAL
LABOUR
ITEM RATE
Page 4 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
b) Supply and filling new jute bags 4 to 5 Cft. capacity with sand or earth, sewing
and laying in position under water.
MATERIAL
LABOUR
ITEM RATE
Page 5 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
5 Carriage of jute bags 1.25 Cft. capacity filled with sand or earth
Page 6 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
6 Carriage of new jute bags 4 to 5 Cft. Capacity filled with sand or earth
A) First Chain
Page 7 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
LABOUR
LABOUR
LABOUR
Page 8 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
MATERIAL
LABOUR
ITEM RATE
Page 9 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
MATERIAL
Munjban
100 x 5 seer = 2.31 Seers (2.1 2.15 Kg. 0.00 Per Kg. -
216 Cft.
Contractor's Profit & Ov 20.00 Percent -
Total -
LABOUR
ITEM RATE
Page 10 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
LABOUR
ITEM RATE
DESCRIPTION OF ITEM
LABOUR
ITEM RATE
Page 11 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
b) Over size shingle 3" to 9"
LABOUR
ITEM RATE
LABOUR
ITEM RATE
Page 12 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
MATERIAL
LABOUR
ITEM RATE
Page 13 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
13 Providing and weaving G.I. wire netting for wire crates with G.I. wire of approved size
(including siding and partition to make crates).
MATERIAL
G.I. Wire No. 15 (500' long) 6.8 Lbs (3.08 Kg.) 1.00 Per Kg. 3.08
Contractor's Profit & Ov 20.00 Percent 0.62
Total 3.70
LABOUR
ITEM RATE
Page 14 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
13 Providing and weaving G.I. wire netting for wire crates with G.I. wire of approved size
(including siding and partition to make crates).
MATERIAL
G.I. Wire No. 10 (500' long) 22.0 Lbs (10.0 Kg.) 0.00 Per Kg. -
Contractor's Profit & Ov 20.00 Percent -
Total -
LABOUR
ITEM RATE
Page 15 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
a) 6" mesh (iii) G.I. Wire 8 SWG
MATERIAL
G.I. Wire No. 8 (500' long) 34.5 Lbs (15.68 Kg. 0.00 Per Kg. -
Contractor's Profit & Ov 20.00 Percent -
Total -
LABOUR
ITEM RATE
Page 16 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
13 b) 4" mesh (i) G.I. Wire 15 SWG
MATERIAL
G.I. Wire No. 15 750' long 10.20 Lbs (4.63 Kg. 0.00 Per Kg. -
Contractor's Profit & Ov 20.00 Percent -
Total -
LABOUR
ITEM RATE
Page 17 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
13 b) 4" mesh (ii) G.I. Wire 10 SWG
MATERIAL
G.I. Wire No. 10 750' long 33.0 Lbs (14.97 Kg. 0.00 Per Kg. -
Contractor's Profit & Ov 20.00 Percent -
Total -
LABOUR
ITEM RATE
Page 18 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
13 b) 4" mesh (iii) G.I. Wire 8 SWG
MATERIAL
G.I. Wire No. 8 750' long 51.75 Lbs (23.47 Kg 0.00 Per Kg. -
Contractor's Profit & Ov 20.00 Percent -
Total -
LABOUR
ITEM RATE
Page 19 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
14 Providing and laying shingle on top of bund, including handling of material within
three chains (90 metres)
MATERIAL
LABOUR
ITEM RATE
Page 20 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
15 Supply and Dumping at site, without boat, including handling of material within
three chains (90 metres).
a) Stone or boulder
MATERIAL
LABOUR
ITEM RATE
b) Shingle or Spawl
MATERIAL
LABOUR
ITEM RATE
Labour Rate Per 100 Cft. Rs. - Say -
Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -
c) Brick Bats
Page 21 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit Rate Per 100 Cft.
Rate
Qty Per Unit (Rs.) Amount (Rs.)
MATERIAL
LABOUR
ITEM RATE
Page 22 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
16 Supply and damping by boat including loading into boats within 3 chains lead
and hire charges of boat and boatman
a) Stone, Boulder
MATERIAL
LABOUR
ITEM RATE
Page 23 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
b) Shingle, Spawl
MATERIAL
Spawl 110.00 Cft. 0.00er 100 C -
Contractor's Profit & Ov 20.00 Percent -
Total -
LABOUR
Boatman with large boat 1 No. 0.00 Per day -
Coolies 2 No. 0.00 Per day -
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
Labour Rate Per 100 Cft. Rs. - Say -
Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -
c) Brick Bats
MATERIAL
LABOUR
ITEM RATE
Labour Rate Per 100 Cft. Rs. - Say -
Labour Rate Per Cum. Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum. Rs. - Say -
DESCRIPTION OF ITEM
Page 24 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit Rate Per 100 Cft.
Rate
Qty Per Unit (Rs.) Amount (Rs.)
MATERIAL
LABOUR
ITEM RATE
Page 25 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
18 Supplying and filling bricks in wire crates and hand packing (excluding cost of crates)
MATERIAL
LABOUR
ITEM RATE
Page 26 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
19 Supplying and filling in wire crates, including sewing crates (excluding cost of crates)
i) Stone or Boulders
MATERIAL
LABOUR
ITEM RATE
Page 27 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
ii Shingle or Spawl
MATERIAL
LABOUR
ITEM RATE
Page 28 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
LABOUR
ITEM RATE
DESCRIPTION OF ITEM
LABOUR
ITEM RATE
Page 29 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
MATERIAL
Supply pilchi lead within one mile ###### Sft. 0.00er 100 S -
(As per item No. 1 of this chapter)
Total -
LABOUR
ITEM RATE
DESCRIPTION OF ITEM
23 Surface protection with pilchi matresses carriage upto one mile (1.76 Km)
MATERIAL
Supply pilchi lead within one mile 20.00 Cft. 0.00er 100 C -
LABOUR
Coolies 2.50 No. 0.00 Per day -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
Labour Rate Per 100 Sft. Rs. - Say -
Labour Rate Per Sqm. Rs. - Say -
Composite Rate per 100 Sft. Rs. - Say -
Composite Rate per Sqm. Rs. - Say -
Page 30 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
MATERIAL
Binding wire 1 Lbs (0.454 Kg.) 0.45 Kg. 0.00 Per Kg. -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
iii. Sharpening wooden pegs 2" dia and 25.00 Nos. 0.00er 100 No -
18" long
Total -
Sundries (10%) 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
Page 31 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
25 Construction groynes upto 5 feet with single row of woodem vertical stacks 7"
to 12" dia. One average lead one mile
LABOUR
LABOUR
ITEM RATE
Page 32 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
LABOUR
LABOUR
ITEM RATE
Page 33 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
27 Providing and laying stone pitching/filling, dry hand packed, as filling behind
retaining walls or in pitching and aprons
MATERIAL
LABOUR
ITEM RATE
Page 34 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
28 Providing and laying stone pitching with hammer dressed stones on surface
laid in courses
MATERIAL
LABOUR
ITEM RATE
DESCRIPTION OF ITEM
Page 35 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
29 Providing and laying stone pitching for top layer only
a) On slope
MATERIAL
LABOUR
ITEM RATE
Page 36 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
29 b) On level
MATERIAL
LABOUR
ITEM RATE
Page 37 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
a) On level
MATERIAL
LABOUR
ITEM RATE
Page 38 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
b) On Slope
MATERIAL
LABOUR
ITEM RATE
Page 39 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
31 Providing and laying stone pitching hand packed, with surface leveled off to the correct
section and voide filled in 1:8 cement, sand mortar, in floors of bridges along banks
and in aprons, etc.
MATERIAL
LABOUR
ITEM RATE
Page 40 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
ii) Top layer on level
MATERIAL
LABOUR
ITEM RATE
Page 41 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
iii) Stone pitching/filling on slope or on level (other than top layer)
MATERIAL
LABOUR
ITEM RATE
Page 42 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
MATERIAL
LABOUR
ITEM RATE
Page 43 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Pitching or grouting stone apron etc. in :-
MATERIAL
LABOUR
ITEM RATE
Page 44 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
MATERIAL
LABOUR
ITEM RATE
Page 45 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
MATERIAL
LABOUR
ITEM RATE
Page 46 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
35 Removing stone and repitching hand packed on slopes or level after making good
damaged slope/portion.
ITEM RATE
Page 47 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
36 Collecting and stacking boulders from nullah beds or loose shale, or from any other
site, within 3 chains lead
LABOUR
ITEM RATE
Labour Rate Per 100 Cft. Rs. - Say -
Labour Rate Per Cum Rs. - Say -
DESCRIPTION OF ITEM
37 Levelling and dressing stone filling under blocks and grouting with shingle
MATERIAL
ITEM RATE
Labour Rate Per 100 Cft. Rs. - Say -
Labour Rate Per Cum Rs. - Say -
Composite Rate per 100 Cft. Rs. - Say -
Composite Rate per Cum Rs. - Say -
DESCRIPTION OF ITEM
Page 48 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit of Rate Per 100 Cft.
Rate
Qty Per Unit (Rs.) Amount (Rs.)
MATERIAL
LABOUR
ITEM RATE
DESCRIPTION OF ITEM
39 Breaking stone into spawls and stacking
LABOUR
ITEM RATE
Labour Rate Per 100 Cft. Rs. - Say -
Labour Rate Per Cum Rs. - Say -
DESCRIPTION OF ITEM
40 Fixing floating spurs with materials from canal plantation within one mile lead
Page 49 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Qty Per Unit (Rs.) Amount (Rs.)
ITEM RATE
LABOUR
ITEM RATE
Page 50 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
c 3.0' to 4.0' F.s. depth
LABOUR
ITEM RATE
LABOUR
ITEM RATE
Page 51 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
DESCRIPTION OF ITEM
41 Staking and bushing from canal plantation within one mile. (Royalty to be paid to
Forest Department or private owner if and when required.
a (i) Cutting and supply un-sharpened pegs 3.5 long, 3" to 6" dia from canal plantation
sites lead within one mile (1.6 Km.)
MATERIAL
LABOUR
Coolies for Cutting of wood for Pegs 2 Nos. 0.00 Per No. -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
Page 52 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (a) Sharpening one end of pegs 3.5 long
3" to 6 " dia.
LABOUR
ITEM RATE
LABOUR
ITEM RATE
Page 53 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (a) Tying pegs with Munj/Patha ban one line including tying around the pegs.
MATERIAL
LABOUR
ITEM RATE
Page 54 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (a) Cutting and supplying brushwood from canal plantation on private source (Lead within one mile)
and wattling between stakes and intertwining. (Thickness of wattled brush wood 1.0 average)
LABOUR
ITEM RATE
Page 55 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (b) Cutting and supplying un-sharpened pegs 4'.0 long (4 feet) 3"-6" dia from canal plantation l
MATERIAL
LABOUR
ITEM RATE
41 (b) Sharpening one end of pegs 4'.0 long 3" to 6" dia.
LABOUR
ITEM RATE
41 (b) Driving pegs 4'-0" long 3" to 6" dia (driven 1.25' below the available bed or ground (average)
Page 56 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit of Rate Per 100 No. Pegs
Rate
Qty Per Unit (Rs.) Amount (Rs.)
LABOUR
ITEM RATE
41 (b) Tying pegs with Munj / Patha ban (one line including tying around the pegs).
MATERIAL
LABOUR
Total -
ITEM RATE
Page 57 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (b) Cutting and supplying brushwood from canal plantation or private source (lead within one mile)
wattling between stakes and intertwining. (Thickness of wattled brush wood 1.0' (average)
MATERIAL
Thickness 1'-0"
Height 2.75'
LABOUR
Cooly Unskilled
for cutting brushwood 2.50 Nos. 0.00 Per day -
Cooly skilled for wattling 1.00 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
Page 58 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (c) Cutting and supplying unsharpened pegs 5'-0" long 3" to 6" dia from canal plantation
(lead within one mile)
MATERIAL
Wood required for 100 No. pegs Brushwood measured in thoroughly compacted and packe
100 x 5'.0 x 9/24 x 9/24 x x 22/7 shape before filling in the desi
55.25 Cft.
Add wastage 20% 11.05
66.30 Cft.
LABOUR
ITEM RATE
41 (c) Sharpening one end of pegs 5'-0" long 3" to 6" dia.
LABOUR
ITEM RATE
Labour Rate Per 100 No. Pegs Rs. - Say -
41 c - Driving pegs 5'-0" long 3" to 6" dia (driven 1.5' below the available bed on ground (average).
Page 59 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit Rate Per 100 No. Pegs
Rate
Qty Per Unit (Rs.) Amount (Rs.)
LABOUR
ITEM RATE
41 (c) Tying Peg with Munj / Patha ban one line including tying around the pegs.
MATERIAL
LABOUR
ITEM RATE
Page 60 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (c) Cutting and supply brushwood from canal plantation or private source (lead within one mile) an
between stakes and intertwining thickness of wattled brush wood 1.0')
MATERIAL
CONTENTS
MATERIAL
Cooly skilled for wattling brush wood 1.50 No. 0.00 Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
Page 61 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (d) Cutting and supplying unsharpened pegs 6'-0" long 3" to 6" dia from canal plantation (lead wit
MATERIAL
LABOUR
Coolies for cutting wood for pegs. 4.00 Nos. 0.00 Per No. -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
Page 62 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (d) Driving pegs 6'-0" long 3'-6" driven 1.75' below the available bed of ground (average)
LABOUR
ITEM RATE
41 (d) Tying pegs with Munj / Patha ban (one line including tying around the pegs)
MATERIAL
LABOUR
ITEM RATE
Page 63 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (d) Cutting and supplying brush wood from canal plantation or private source (lead within one mile
wattling between stakes and intertwining, thickness of wattled brush wood 1'.0 average
MATERIAL
ITEM RATE
Page 64 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (e) Cutting and supplying un-sharpened pegs 6'-1" to 8'-0" long 4" to 8" dia from canal plantation
within one mile.
MATERIAL
LABOUR
ITEM RATE
41 (e) Sharpening one end of pegs 6'-1" to 8'-0" long, 4" to 8" dia.
LABOUR
Page 65 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (e) Driving pegs 6'-1" to 8'-0' long 4" to 8" dia driven 2'-0" below the available bed or ground (
LABOUR
Cooly skilled 1.30 Nos. 0.00 Per day -
Cooly unskilled 1.35 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
Page 66 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (e) Tying pegs 4" to 8" dia with Munj / Patha ban (one line including tying around the pegs).
MATERIAL
Munj / Patha ban 0.80 Sr. (0.36 Kg.) 0.00 Per Kg. -
Contractor's Profit & Ov 20.00 Percent -
Total -
LABOUR
ITEM RATE
Page 67 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
41 (e) Cutting and supplying brush wood (from canal plantation or private source lead within one mile
wattling between stacks and intertwining (thickness or wattled brush wood 1.0 average).
MATERIAL
LABOUR
Coolies Unskilled
for cutting brush wood 3.00 Nos. 0.00 Per day -
Cooly skilled for wattling 1.50 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Say
ITEM RATE
Page 68 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
42 Staking with bamboos from market and brushing from canal plantation or private source
(Royalty of brush wood for brushing or cost to private owners if and when required).
MATERIAL
ITEM RATE
(a) i Sharpening one end of bamboos 8'-1" to 10' long 2" to 5" dia
LABOUR
ITEM RATE
Page 69 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
(a) ii Driving bamboos 8'-1" to 10'-0" long 2" to 5" dia. Driven2.5' below the available 'bed or gro
ITEM RATE
Labour Rate Per 100 No. Bamboos Rs. - Say -
2 (a) ivTying bamboos 2" to 5" dia with munj/Patha ban two lines including tying around the bamboos.
MATERIAL
LABOUR
Cooly unskilled 0.15 No. 0.00 Per day -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
42 (a) v Cutting and supply brushwood from canal plantation or private source lead within one mile and
between stakes and intertwining (thickness of wattled brushwood 1'.0 average)
Page 70 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit of Rate per Chain of One Row
Rate
Qty Per Unit (Rs.) Amount (Rs.)
MATERIAL
LABOUR
Unskilled Coolies
for cutting brushwood 3.50 Nos. 0.00 Per day -
Cooly skilled for wattling 2.00 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
MATERIAL
Bamboos ###### Nos. 0.00 Each -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
Material Rate Per 100 No. Bamboos Rs. - Say -
2 (b) iiSharpening one end of bamboo 10'-1" to 12'-0" long 2" to 5" dia
Page 71 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Analysis for 125 Nos.
LABOUR
ITEM RATE
(b) ii Driving bamboos 10'-1" to 12'-0" long 2" to 5" (driven 2.75' below the available bed or groun
LABOUR
ITEM RATE
Page 72 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
2 (b) ivTying bamboos 2" to 5" dia with BSWG No. 10 (two lines including tying around the bamboos and
tie around the topend only)
MATERIAL
LABOUR
ITEM RATE
Page 73 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
42 (b) v Wattling brushwood between stakes and intertwining (thickness of wattled brush wood 1'.0 avera
MATERIAL
LABOUR
Cooly Unskilled
for cutting brush wood 4.50 Nos. 0.00 Per day -
Cooly skilled for wattling 2.25 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
MATERIAL
ITEM RATE
2 (c) iiSharpening one end of bamboo 12'-1" to 14' long 2" to 5" dia.
Page 74 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit of Rate 100 No. Bamboos
Rate
Qty Per Unit (Rs.) Amount (Rs.)
LABOUR
ITEM RATE
(c) ii Driving bamboos 12'-1" to 14' long 2" to 5" dia . Driven 3.5' below the available bed or grou
LABOUR
ITEM RATE
Page 75 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
2 (c) ivTying bamboos 2" to 5" dia with B.S.W.G. No. 10 Two lines including tying around the bamboo a
third tying around the topend only.
MATERIAL
LABOUR
Total -
ITEM RATE
42 (c) v Cutting and supplying brushwood from canal plantation / private source lead within one mile an
between stakes and intertwining thickness of wattled brush wood 1'-0" average.
MATERIAL
Requirement of brush wood length=100 Ft.
Thickness = 1'-0"
Height = 9.50 Ft.
Contents 100 x 1 x 9.50 = 950 Cft.
Weight of brush wood = 950x62 =714 Mds
82.5
Royality of brush wood 714 Mds. 0.00r 100 Md -
Total -
LABOUR
Coolies unskilled
for cutting brush wood 5.50 Nos. 0.00 Per day -
Cooly skilled for wattling 2.50 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
Labour Rate Per Chain of One Row Rs. - Say -
Composite Rate Per Chain of One Row Rs. - Say -
Page 76 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit of Rate 100 No. Bamboos
Rate
Qty Per Unit (Rs.) Amount (Rs.)
MATERIAL
ITEM RATE
2 (d) iiSharpening one end of bamboo 14'-1" to 16'-0" long 2" to 5" dia.
LABOUR
Page 77 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
(d) ii Driving bamboos 14'-1" to 16'-0" long 2" to 5" dia. Driven 4'-0"' below the available bed or
LABOUR
ITEM RATE
(d) ivTying bamboos 2" to 5" dia with B.S.W.G. No. 10 Two lines including tying around the bamboo a
third tying around the top only.
MATERIAL
LABOUR
Same as per Item No. 42 (b) (iv) -
Total -
ITEM RATE
Page 78 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
42 (d) v Cutting and supplying brush wood from canal plantation / private source lead within one mile a
between stakes and intertwining thickness of wattled brush wood 1'-0" average.
MATERIAL
LABOUR
Cooly Unskilled
for cutting brush wood 6.20 Nos. 0.00 Per day -
Cooly skilled for wattling 3.00 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
ITEM RATE
Page 79 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
2 (e) iSupplying bamboos 16'-1" to 20'-0" long 2" to 5" dia
MATERIAL
ITEM RATE
(e) i Sharpening one end of bamboo 16'-1" to 20' long 2" to 5" dia.
LABOUR
ITEM RATE
Page 80 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
(e) ii Driving bamboos 16'-1" to 20'-0" long 2" to 5". Driven 4'-0"' below the available bed or gro
LABOUR
2 (e) ivTying bamboos 2" to 5" dia with B.S.W.G. No. 10 Two lines including tying around the bamboos
third tying around the top only.
MATERIAL
LABOUR
Total -
ITEM OF RATE
Page 81 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
42 (e) v Cutting and supplying brush wood from canal plantation / private source lead within one mile a
between stakes and intertwining thickness of wattled brush wood 4'-0" average
MATERIAL
Total -
LABOUR
Cooly Unskilled
for cutting brush wood 7.50 Nos. 0.00 Per day -
Cooly skilled for wattling 4.00 Nos. 0.00 Per day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ov 20.00 Percent -
Total -
Say -
ITEM RATE
Page 82 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
43 Cutting and supplying brush wood from canal plantation or from any other source
within one mile
LABOUR
ITEM RATE
ITEM RATE
Labour Rate Per 100 Cft. Rs. - Say -
Labour Rate Per Cum Rs. - Say -
45 Covering road 10' to 12' wide with 3" sarkanda or jungle upto one chain lead
Page 83 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
Detail Unit Rate per Chain
Rate
Qty Per Unit (Rs.) Amount (Rs.)
LABOUR
LABOUR
ITEM RATE
Page 84 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
46 b) Gachi pitching done with silt clearance and berm dressing
LABOUR
ITEM RATE
Page 85 C:\SCHD-RAT\PROT-DIV.XLS/ZAK
CHAPTER NO. 19
DESCRIPTION OF ITEM:
Item No. 1 Providing and fitting glazed earthen ware water closet European Typ
excluding seat and cover.
(i) White
MATERIAL
Total
Contractor's Profit & Overh 20.00 Percent -
Total -
Total
Sundries 10.00 Percent
Total
Contractor's Profit & Overh 20.00 Percent
Total
ITEM RATES
Page 1
DESCRIPTION OF ITEM:
Item No. 1 Providing and fitting glazed earthen ware water closet European Typ
excluding seat and cover.
(ii) Coloured
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 2
DESCRIPTION OF ITEM:
Item No. 2 Providing and fixing double seat and cover only.
(i) Bakelite.
MATERIAL
1 Seat and cover double (Bakelite) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 3
DESCRIPTION OF ITEM:
Item No. 2 Providing and fixing double seat and cover only.
(ii) Plastic.
MATERIAL
1 Seat and cover double (Plastic) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 4
DESCRIPTION OF ITEM:
Item No. 3 Providing and fitting glazed earthen ware water closet, squatt
(orisa pattern) combined with foot rest.
(i) White
MATERIAL
1 W.C Orisa pattern with foot rest 1.00 No. 0.00 each 0.00
2 Cement 0.021 Bag 0.00 Bag 0.00
3 Sand 0.056 Cft. 0.00 % Cft. 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 5
Item No. 3 Providing and fitting glazed earthen ware water closet, squatt
(orisa pattern) combined with foot rest.
(ii) Coloured.
MATERIAL
1 W.C Orisa pattern with foot rest 1.00 No. 0.00 each 0.00
coloured
2 Cement 0.021 Bag 0.00 Bag 0.00
3 Sand 0.056 Cft. 0.00 % Cft. 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 6
DESCRIPTION OF ITEM:
Item No. 4 Providing and fitting white glazed earthen ware water closet, squat
with separate foot rest.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 7
DESCRIPTION OF ITEM:
Item No. 5 Providing and fitting water closet squatter type of terrazzo concre
MATERIAL
1 W.C. squatter type of terrazzo concrete 1.00 No. 0.00 each 0.00
2 Cement 0.021 Bag 0.00 Bag 0.00
3 Sand 0.056 Cft. 0.00 % Cft. 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 8
DESCRIPTION OF ITEM:
Item No. 6 Providing and fitting glazed earthen ware wash hand basin 56 x 40 c
(22" x 16"), including bracket set, waste pipe and waste coupling,
MATERIAL
1 Glazed earthen ware wash hand basin 1.00 No. 0.00 each 0.00
2 Padestal 1.00 No. 0.00 each 0.00
3 Waste coupling, Bracket, Waste Pipe 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 9
DESCRIPTION OF ITEM:
Item No. 6 Providing and fitting glazed earthen ware wash hand basin 56 x 40 c
(22" x 16"), including bracket set, waste pipe and waste coupling,
MATERIAL
1 Earthen ware wash hand basin (coloured) 1.00 No. 0.00 each 0.00
2 Pedestal 1.00 No. 0.00 each 0.00
3 Waste coupling, Bracket Waste
Pipe 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 10
DESCRIPTION OF ITEM:
Item No. 6 Providing and fitting glazed earthen ware wash hand basin 56 x 40 c
(22" x 16"), including bracket set, waste pipe and waste coupling,
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 11
DESCRIPTION OF ITEM:
Item No. 6 Providing and fitting glazed earthen ware wash hand basin 56 x 40 c
(22" x 16"), including bracket set, waste pipe and waste coupling,
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 12
DESCRIPTION OF ITEM:
Item No. 7 Providing and fixing stainless steel sink with drain board, size 12
(48" x 24") including bracket set, waste pipe and waste coupling.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 13
DESCRIPTION OF ITEM:
Item No. 8 Providing and fitting terrazzo concrete sink 60 x 45 cm (24" x 18")
drain board of mosaic including bracket set waste pipe and waste co
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 14
DESCRIPTION OF ITEM:
Item No. 9 Providing and fixing glazed earthen ware sink, including bracket se
pipe and waste coupling.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 15
DESCRIPTION OF ITEM:
Item No. 9 Providing and fixing glazed earthen ware sink, including bracket se
pipe and waste coupling.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 16
DESCRIPTION OF ITEM:
Item No. 10 Providing and fixing glazed earthen ware Flat Back Urinal.
MATERIAL
1 G.E. flat Back Urinal Complete set 1.00 No. 0.00 each 0.00
2 Gutties 2.00 Nos. 0.00 P. Doz 0.00
3 Screw (75 mm) 3" long 2.00 Nos. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 17
DESCRIPTION OF ITEM:
Item No. 11 Providing and fitting glazed earthen ware low down flushing cistern
litres (3 gallons) capacity, including bracket set, copper connecti
(i) White
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 18
DESCRIPTION OF ITEM:
Item No. 11 Providing and fitting glazed earthen ware low down flushing cistern
litres (3 gallons) capacity, including bracket set, copper connecti
(ii) Coloured
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 19
DESCRIPTION OF ITEM:
Item No. 12 Providing and fitting plastic made low down flushing cistern 13.63
(3 gallons) capacity, including bracket set, copper connection, etc
complete.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 20
DESCRIPTION OF ITEM:
Item No. 13 Providing and fixing white enamelled cast iron low down flushing ci
13.63 litters (3 gallons) capacity, including bracket set, copper c
etc.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 21
DESCRIPTION OF ITEM:
Item No. 14 Providing and fixing C.I. highlevel flushing cistern including cost
bracket set copper connection etc.
MATERIAL
1 C.I. High level flushing cistern 1.00 No. 0.00 each 0.00
13.63 letters or 3 gallon
capacity including
accessories.
2 C.I. Bracket one pair 0.00 per pair 0.00
3 Cement 0.021 Bag 0.00 Bag 0.00
4 Sand 0.056 Cft. 0.00 % Cft. 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 22
DESCRIPTION OF ITEM:
Item No. 14 Providing and fixing C.I. highlevel flushing cistern including cost
bracket set copper connection etc.
MATERIAL
1 C.I. High level flushing cistern 1.00 No. 0.00 each 0.00
I/C all accessaries
2 C.I. Bracket one pair 0.00 per pair 0.00
3 Cement 0.021 Bag 0.00 Bag 0.00
4 Sand 0.056 Cft. 0.00 % Cft. 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total 0.00
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 23
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 24
DESCRIPTION OF ITEM:
Item No. 16 Providing and fitting, glazed earthen ware soap dish.
(i) White.
MATERIAL
1 Glazed earthen ware soap dish 1.00 No. 0.00 each 0.00
2 Gutties Plastic 2.00 Nos. 0.00 P. Doz 0.00
3 Screws 3/4" 2.00 Nos. 0.00 P. Doz 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 25
DESCRIPTION OF ITEM:
Item No. 16 Providing and fitting, glazed earthen ware soap dish.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 26
DESCRIPTION OF ITEM:
Item No. 17 Providing and fixing chromium plated toilet paper holder.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 27
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 28
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 29
DESCRIPTION OF ITEM:
Item No. 19 Providing and fixing looking glass 55 x 40 cm (22" x 16") size and
thick first quality.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 30
DESCRIPTION OF ITEM:
Item No. 20 Providing and fixing glass shelf 60 x 13 cm (24" x 5") with 5 mm th
glass.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 31
DESCRIPTION OF ITEM:
Item No. 20 Providing and fixing glass shelf 60 x 13 cm (24" x 5") with 5 mm th
glass.
(ii) Glass Shelf only without chromium plated brackets and railing.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 32
DESCRIPTION OF ITEM:
Item No. 21 Providing and fitting glazed earthen ware shelf 60 x 13 cm (24" x 5
chromium plated bracket and railing.
(i) White.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 33
DESCRIPTION OF ITEM:
Item No. 21 Providing and fitting glazed earthen ware shelf 60 x 13 cm (24" x 5
chromium plated bracket and railing.
(ii) Coloured.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 34
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 35
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 36
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 37
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 38
DESCRIPTION OF ITEM:
Item No. 23 Providing and fixing chromium plated pillar - cock, heavy.
(i) 2 cm (").
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 39
DESCRIPTION OF ITEM:
Item No. 23 Providing and fixing chromium plated pillar - cock, heavy.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 40
DESCRIPTION OF ITEM:
Item No. 24 Providing and fixing chromium plated stop Cock Heavy.
(i) 2 cm (").
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 41
DESCRIPTION OF ITEM:
Item No. 24 Providing and fixing chromium plated stop Cock Heavy.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 42
DESCRIPTION OF ITEM:
Item No. 25 Providing and fixing underground stop cock 13 mm (") with chromium
plated cover.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 43
DESCRIPTION OF ITEM:
(i) 2 cm (").
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 44
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 45
DESCRIPTION OF ITEM:
Item No. 27 Providing and fixing chromium plated tee stop cock 1.5 cm (").
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 46
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 47
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 48
DESCRIPTION OF ITEM:
Item No. 29 Providing & Fixing, chromium plated mixing valve, for wash hand bas
sinks or shower.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 49
DESCRIPTION OF ITEM:
Item No. 30 Providing and fixing gun metal peet/gate valve (screwed).
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 50
DESCRIPTION OF ITEM:
Item No. 30 Providing and fixing gun metal peet/gate valve (screwed).
MATERIAL
1 G.M. Peet Valve 4 cm (1") dia 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 51
DESCRIPTION OF ITEM:
Item No. 30 Providing and fixing gun metal peet/gate valve (screwed).
MATERIAL
1 G.M. Peet Valve 5 cm (2" dia) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 52
DESCRIPTION OF ITEM:
Item No. 30 Providing and fixing gun metal peet/gate valve (screwed).
MATERIAL
1 G.M. Peet Valve 6.5 cm (2" dia) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 53
DESCRIPTION OF ITEM:
Item No. 30 Providing and fixing gun metal peet/gate valve (screwed).
MATERIAL
1 G.M. Peet Valve 7.5 cm (3" dia) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 54
DESCRIPTION OF ITEM:
Item No. 31 Providing and fitting, Chromium plated or brass oxidised, swan neck
1.5 cm (" dia).
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 55
DESCRIPTION OF ITEM:
Item No. 31 Providing and fitting, Chromium plated or brass oxidised, swan neck
1.5 cm (" dia).
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 56
DESCRIPTION OF ITEM:
Item No. 31 Providing and fitting, Chromium plated or brass oxidised, swan neck
1.5 cm (" dia).
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 57
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 58
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 59
DESCRIPTION OF ITEM:
Item No. 33 Providing and fixing floor trap of Cast Iron including concrete cha
all-round and C.I grating.
(i) 10 x 5 cm (4" x 2").
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 60
DESCRIPTION OF ITEM:
Item No. 33 Providing and fixing floor trap of Cast Iron including concrete cha
all-round and C.I grating.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 61
DESCRIPTION OF ITEM:
Item No. 34 Providing and fitting P-trap including concrete chamber with cast i
gully grating.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Labour rate for Each Rs. 0.00 Say 0.00
Composite rate for Each Rs. 0.00 Say 0.00
Page 62
DESCRIPTION OF ITEM:
MATERIAL
1 Glazed Pee trap 10 cm (4" dia) 1.00 No. 0.00 each 0.00
2 Cement 0.016 Bag 0.00 Bag 0.00
3 Sand 0.040 Cft. 0.00 % Cft. 0.00
4 Crushed Stone 0.081 Cft. 0.00 % Cft. 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 63
DESCRIPTION OF ITEM:
Item No. 35 Providing and fitting 10 cm (4") gully trap, including cement cncre
costof PVC grating 15 x 15 cm (6" x 6") and Masonry chamber 30 x 30
cm(12" x 12").
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Labour rate for Each Rs. 0.00 Say 0.00
Composite rate for Each Rs. 0.01 Say 0.00
Page 64
DESCRIPTION OF ITEM:
Item No. 36 (i) Providing & fitting cast iron soil pipe with:
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost/metre
0.00 = 0.00 0.00
2
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 65
DESCRIPTION OF ITEM:
Item No. 36 (i) Providing & fitting cast iron soil pipe with:
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost/metre
449.46 = 224.73 0
2
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 66
DESCRIPTION OF ITEM:
1 C.I Soil pipe 10 cm (4") dia 2.00 Meter 0.00per metre 0.00
2 Yarn 0.25 Lbs 0.00 Lbs 0.00
3 Cement 0.022 Bag 0.00 Bag 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per metre 0.00
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 67
DESCRIPTION OF ITEM:
1 C.I Soil pipe 5 cm (2") dia 2.00 Metre 0.00per metre 0.00
2 Yarn 0.13 Lbs 0.00 Lbs 0.00
3 Cement 0.011 Bag 0.00 Bag 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per metre 0.00
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 68
DESCRIPTION OF ITEM:
Item No. 37 Providing and fitting, A.C Soil pipe with cement caulked joint, inc
specials.
(i) 6 cm i/d.
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per metre 0.00
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 69
DESCRIPTION OF ITEM:
Item No. 37 Providing and fitting, A.C Soil pipe with cement caulked joint,
including all specials.
0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per metre 0.00
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 70
DESCRIPTION OF ITEM:
Item No. 37 Providing and fitting, A.C Soil pipe with cement caulked joint,
including all specials.
0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per metre 0.00
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 71
DESCRIPTION OF ITEM:
Item No. 37 Providing and fitting, A.C Soil pipe with cement caulked joint,
including all specials.
1 A.C Soil pipe 50 cm (6" dia) 4.00 Metre 0.00per metre 0.00
2 Special at 10% 0.00
3 Yarn 0.500 Lbs 0.00 Lbs 0.00
4 Cement 0.044 Bag 0.00 Bag 0.00
0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per metre 0.00
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 72
DESCRIPTION OF ITEM:
Item No. 38 Providing and fitting cast iron specials, such as tee bend, collar,
plain type.
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total cost for 5 kg -
Material cost per Kg 0.00
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 73
DESCRIPTION OF ITEM:
Item No. 38 Providing and fitting cast iron specials, such as tee bend, collar,
cross, etc. plain type.
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per Kg 0.00
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 74
DESCRIPTION OF ITEM:
Item No. 39 Supply and fitting of cast iron Manhole cover with frame, etc. comp
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 75
DESCRIPTION OF ITEM:
Item No. 39 Supply and fitting of cast iron Manhole cover with frame, etc. comp
MATERIAL
1 C.I. manhole cover with frame 45 cm 1.00 No. 0.00 each 0.00
(18" dia)
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 76
DESCRIPTION OF ITEM:
Item No. 39 Supply and fitting of cast iron Manhole cover with frame, etc. comp
MATERIAL
1 C.I manhole cover with frame 60 cm (24" dia) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 77
DESCRIPTION OF ITEM:
Item No. 40 Providing and fitting R.C.C Pipe 10 cm (4" dia) including
laying and jointing in trenches.
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Material cost per metre 0.00
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 78
DESCRIPTION OF ITEM:
Item No. 41 Providing and fitting chromium plated or oxidised gas Cock
6 mm (" dia)
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 79
DESCRIPTION OF ITEM:
Item No. 41 Providing and fitting chromium plated or oxidised gas Cock
6 mm (" dia)
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 80
DESCRIPTION OF ITEM:
Item No. 41 Providing and fitting chromium plated or oxidised gas Cock
6 mm (" dia)
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 81
DESCRIPTION OF ITEM:
Item No. 42 Providing and fitting nipple or bush 6 mm to 10 mm (" - 3/8") i/d.
MATERIAL
1 Nipple or bush 6 mm to 10 mm
(1/4" - 3/8") i/d. 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 82
DESCRIPTION OF ITEM:
MATERIAL
1 Brass gas cock 1.5 cm (" dia) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 83
DESCRIPTION OF ITEM:
MATERIAL
1 Brass gas cock 2 cm (" dia) 1.00 No. 0.00 each 0.00
0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 84
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 85
DESCRIPTION OF ITEM:
MATERIAL
1 Brass stop cock/brass bib cock 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 86
DESCRIPTION OF ITEM:
Item No. 45 Hoisting and placing in position precast R.C latrine seats.
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 87
REPLACEMENT
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 88
REPLACEMENT
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 89
REPLACEMENT
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 90
REPLACEMENT
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 91
REPLACEMENT
DESCRIPTION OF ITEM:
MATERIAL
1 P.V.C. waste pipe 3 cm (1" dia) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 92
REPLACEMENT
DESCRIPTION OF ITEM:
MATERIAL
1 P.V.C. waste pipe 4 cm (1" dia) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 93
REPLACEMENT
DESCRIPTION OF ITEM:
MATERIAL
1 P.V.C. flushing bend 3 cm (1" dia) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 94
REPLACEMENT
DESCRIPTION OF ITEM:
MATERIAL
1 P.V.C. Flusing bend 4 cm (1" dia) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 95
REPLACEMENT
DESCRIPTION OF ITEM:
Item No. 5 Providing and fixing chromium plated bottle trap with waste
pipe etc. complete.
MATERIAL
1 C.P Bottle trap with waste pipe 1.00 No. 0.00 each 0.00
0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 96
REPLACEMENT
DESCRIPTION OF ITEM:
Item No. 5 Providing and fixing chromium plated bottle trap with waste
pipe etc. complete.
MATERIAL
1 C.P Bottle trap 4 cm with waste pipe 1.00 No. 0.00 each 0.00
0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 97
REPLACEMENT
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 98
REPLACEMENT
DESCRIPTION OF ITEM:
(ii) Sink.
MATERIAL
1 Angle Iron Bracket for Sink 2.00 Nos. 0.00 each 0.00
2 Nail with cutter 4.00 Nos. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 99
REPLACEMENT
DESCRIPTION OF ITEM:
Item No. 7 Providing and fixing 1.5 cm (" dia) connection, including check
nuts etc.
MATERIAL
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 100
REPLACEMENT
DESCRIPTION OF ITEM:
Item No. 7 Providing and fixing 1.5 cm (" dia) connection, including check
nuts etc.
MATERIAL
1 Copper Connection
assessories 1.00 Nos. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 101
REPLACEMENT
DESCRIPTION OF ITEM:
MATERIAL
0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 102
REPLACEMENT
DESCRIPTION OF ITEM:
MATERIAL
1 Brass ball valve 2 cm (" dia) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 103
REPLACEMENT
DESCRIPTION OF ITEM:
MATERIAL
1 Brass ball valve 2.5 cm (1" dia) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 104
REPLACEMENT
DESCRIPTION OF ITEM:
MATERIAL
1 Brass ball float valve 3 cm (" dia) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 105
REPLACEMENT
DESCRIPTION OF ITEM:
MATERIAL
1 Brass ball float valve 4 cm (1" dia) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 106
REPLACEMENT
DESCRIPTION OF ITEM:
MATERIAL
1 Brass ball float valve 5 cm (2" dia) 1.00 No. 0.00 each 0.00
Total 0.00
Contractor's Profit & Overh 20.00 Percent -
Total -
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & Overh 20.00 Percent -
Total -
ITEM RATES
Page 107
CHAPTER NO. 18
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -
LABOUR
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -
COMPACTION CHARGES
ITEM RATES
Page 1
DESCRIPTION OF ITEM:
MATERIAL
Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -
LABOUR
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -
COMPACTION CHARGES
ITEM RATES
Page 2
DESCRIPTION OF ITEM:
Item No. 3 Providing and laying sub-base course of stone product of approved
quality and grade, including placing, mixing, spreading and compaction
of sub-base material to required depth, grade to achieve 100% maximum
modified AASHO dry density, including carriage of all material to site
work, except gravel and aggregate for which supply within 3 Miles (5 km
is included in the rate.
MATERIAL
1 Pit run or bed run gravel 120 Cft 0.00 % Cft 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -
LABOUR
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -
COMPACTION CHARGES
ITEM RATES
Page 3
DESCRIPTION OF ITEM:
Item No. 3 (a) Providing and laying sub-base course of stone product of approved
quality and grade, including placing, mixing, spreading and compaction
of sub-base material to required depth, grade to achieve 100% maximum
modified AASHO dry density, including carriage of all material to site
work, except gravel and aggregate for which supply within 3 Miles (5 km
is included in the rate.
MATERIAL
Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -
LABOUR
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -
COMPACTION CHARGES
ITEM RATES
Page 4
DESCRIPTION OF ITEM:
Item No. 4 Providing and laying base course of crushed stone aggregate of
approved quality and grade and supply and spreading of stone
screening including placing mixing spreading and compaction of base
course material to required camber and grade to achieve 100% maximum
Modified AASHTO dry density, including carriage of all materials to sit
of work except crushed stone aggregate for which supply within 3 Miles
(5 km) is included in rate.
MATERIAL
Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -
LABOUR
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -
COMPACTION CHARGES
ITEM RATES
Page 5
DESCRIPTION OF ITEM:
Item No. 5 Providing and laying road edging of 3" (75 mm) wide and 9" (228 mm)
deep brick on end. complete in all respects.
Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -
LABOUR
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -
ITEM RATES
Page 6
DESCRIPTION OF ITEM:
Item No. 6 Providing and laying bituminous prime coat, using 10 lbs (4.537 liters)
Kerosene Oil and 10 lbs (4.55 kg) binder.
Total 4.55
Contractor's Profit & O 20.00 Percent 0.91
Total 5.46
LABOUR
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -
ITEM RATES
Page 7
DESCRIPTION OF ITEM:
Item No. 7 Providing and laying bituminous tack coat, using 15 lbs (6.80 kg) of
bitumen.
Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -
LABOUR
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -
ITEM RATES
Page 8
DESCRIPTION OF ITEM:
Item No. 8 (I - i) Providing surface treatment to roads including supply of bitumen and
bajri/crushed stone aggregate of approved quality, including cleaning o
road surface heating and spraying bitumen spreading bajri and rolling
with road roller (including its operation cost, fuel and hire charges,
complete, including carriage of all materials to site of work except
bajri/crushed stone aggregate for which supply within 3 miles (5.0 km)
included in the rate.
1- Ist Coat Using 40 lbs (18.1590 kg) of bitumen and 5.5 Cft (0.156 Cum) bajri of
nominal size 1 inch (25 mm) per 100 Sft.
Total 0.00
Contractor's Profit & O 20.00 % on 1&0.00 -
Total -
Material cost per 100 Sft 30549.86 x 100
10000 0.00
LABOUR
Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
Contractor's Profit & O 20.00 Percent #VALUE!
Total #VALUE!
Total #VALUE!
ITEM RATES
Labour rate per 100 Sft Rs. #VALUE! Say #VALUE!
Labour rate per Sqm Rs. #VALUE! Say #VALUE!
Composite rate per 100 Sft Rs. #VALUE! Say #VALUE!
Composite rate per Sqm Rs. #VALUE! Say #VALUE!
Page 9
DESCRIPTION OF ITEM:
Total 0.00
Contractor's Profit & O 20.00 % on 1&0.00 -
Total -
Rate per 100 Sft = 26392.90 x 100
10000 0.00
LABOUR
Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
Contractor's Profit & O 20.00 Percent #VALUE!
Total #VALUE!
Total #VALUE!
ITEM RATES
Page 10
DESCRIPTION OF ITEM:
Total 0.00
Contractor's Profit & O 20.00 % on 1&0.00 -
Total -
Rate per 100 Sft = 24446.69 x 100
13000 0.00
LABOUR
Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
Contractor's Profit & O 20.00 Percent #VALUE!
Total #VALUE!
Total #VALUE!
ITEM RATES
Page 11
DESCRIPTION OF ITEM:
Total 0.00
Contractor's Profit & O 20.00 % on 1&0.00 -
Total -
Rate per 100 Sft = 17614.43 x 100
13000 0.00
LABOUR
Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
Contractor's Profit & O 20.00 Percent #VALUE!
Total #VALUE!
Total #VALUE!
ITEM RATES
Page 12
DESCRIPTION OF ITEM:
Total 0.00
Contractor's Profit & O 20.00 % on 1&0.00 -
Total -
Rater par 100 Sft = 19967.39 x 100
19000 0.00
LABOUR
Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
Contractor's Profit & O 20.00 Percent #VALUE!
Total #VALUE!
Total #VALUE!
ITEM RATES
Page 13
DESCRIPTION OF ITEM:
Item No. 9 (a) Resurfacting of road, including supply of bitumen and bajri/crushed
stone aggregate of approved quality, including cleaning of road surface
heating and spraying of bitumen, and spreading bajri/crushed stone
aggregate and rolling with road roller (including carriage of all mater
to site of work except bajri/crushed stone aggregate for which supply
within 3.0 Miles (5 km) is included in the rate.
(i) Using 22 lbs (9.981 kg) bitumen and 2.5 Cft (0.07 m) bajri of nominal
" (12 mm).
Total 0.00
Contractor's Profit & O 20.00 % on 1&0.00 -
Total -
Rate per 100 Sft = 24871.21 x 100
15000 -0.01
LABOUR
Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
Contractor's Profit & O 20.00 Percent #VALUE!
Total #VALUE!
Total #VALUE!
ITEM RATES
Labour rate per 100 Sft Rs. #VALUE! Say #VALUE!
Labour rate per Sqm Rs. #VALUE! Say #VALUE!
Page 14
DESCRIPTION OF ITEM:
Item No. 9 a (ii) Using 20 lbs (9.074 kg) bitumen and 2.0 Cft (0.056 m) bajri of nominal
size 3/8" (10 mm) per 100 Sft.
Total 0.00
Contractor's Profit & O 20.00 % on 1&0.00 -
Total -
Rate per 100 Sft = 22409.14 x 100
15000 0.00
LABOUR
Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
Contractor's Profit & O 20.00 Percent #VALUE!
Total #VALUE!
Total #VALUE!
ITEM RATES
Page 15
DESCRIPTION OF ITEM:
Item No. 10(vii) Providing and laying plant pre-mixed bituminous carpet, including
compaction and finishing to required camber, grade and
density.
MATERIAL
Total 0.00
5 Contractor's Profit & O 20.00 on 12&3 0.00 -
6 Cost of Brushes and other special Tool 0.30 0.00 0.00
7 Contractor's Profit & Overheads (20%) on item '6' -
LABOUR
Page 16
Plant Running Charges including crew charges
ITEM RATES
Labour rate per 100 Sft (1" thick) Rs. Say 0.00
Labour Sqm (25 mm thick) Rs. Say 0.00
Composite rate per 100 Sft (1" thick) Rs. Say 0.00
Composite rate per Sqm (25 mm) Rs. Say 0.00
Page 17
DESCRIPTION OF ITEM:
Item No. 11 Scarifying old road surface including removal of debris within 1 chain (30.0 m)
LABOUR
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -
ITEM RATES
Labour rate for 100 Sft Rs. 0.00 Say 0.00
Labour rate for 1 Sqm Rs. 0.00 Say 0.00
Page 18
DESCRIPTION OF ITEM:
LABOUR
1 Cement concrete1:2:4(item 6a(ii) Chap.6=16.60- 10.88 Cft -0.82 per Cft -8.92
2 Steel 100.93 kg -18.00 per % kg -18.17
Labour rate/foot (item 9(a) Chap 6 =291.81-18.00 = 273.80 448.04
35.84
ITEM RATES
Page 19
DESCRIPTION OF ITEM:
Item No. 13 Providing and fixing G.I pipe railing as per standard drawing.
Total 3064.44
Contractor's Profit & O 20.00 Percent 612.89
Total 3,677.33
Rate per foot 3989.63 = 257.40 257.40
15.50
LABOUR
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -
ITEM RATES
Page 20
DESCRIPTION OF ITEM:
Item No. 14 Providing and fixing steel bearings of standard quality and type at sit
work.
MATERIAL
Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -
ITEM RATES
Composit rate for each Rs. 0.00 Say 0.00
DESCRIPTION OF ITEM:
Item No. 15 Providing and fixing rubber bearing pad at site of work.
MATERIAL
1 Rubber bearing pad 1 x 1 x 1 inch 1.00 cubic 0.00 per cub. 0.00
cm.
Total 0.00
Contractor's Profit & O 20.00 Percent -
Total Rate per cubic inch -
ITEM RATES
Page 21
DESCRIPTION OF ITEM:
Item No. 16 Providing and laying expansion joint of neoprine strip 4" x " (100 x 6
and plastic bitumen.
MATERIAL
Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -
LABOUR
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -
ITEM RATES
Page 22
DESCRIPTION OF ITEM:
Item No. 17 Providing and fixing rain water outlet of A.C. Pipe.
MATERIAL
1 A.C pipe 3" i/d (1.571 = 0.457 m) 0.457 Metre 0.00per metre 0.00
Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -
LABOUFor 20 Nos.
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
Total -
ITEM RATES
Page 23
DESCRIPTION OF ITEM:
MATERIAL
i) P.C.C 1 : 4: 8 in foundation
1 x 3.5 x 1.875 x 1.75 = 11.48 Cft
D/d mile stone 1 x 2 x 0.375 x 1.5 = 1.13 Cft
Rate as per item 6 (3) 10.35 Cf 10.35 Cft 0.00Per % Cft 0.00
ii) R.C.C 1: 2: 4
1 x 2 x 0.375 x 4.5 = 3.38 Cft
D/d 15 x 0.375 x 0.08 = 0.47 Cft
(Rate as per item 6 (6 b) (i) 2.91 Cft 2.91 Cft Per Cft 0.00
iii) Steel reinforcement " dia
12 x 5 = 60.0'
Tie 4 x 5 20.0
80. 0 Rft @ .17 lbs/Rft
Rate as per item 8(a) =13.6 lbs = 6.1 6.18 kg 0.00 per kg 0.00
iv) Cement plastec 3/8" thick 1:2 moster
1 x 4.75 x 3 = 14.25 Sft
1 x 2 x 0.375 = 0.75 Sft
Rate as per item 11(7.i) 15.00 Sf 15.00 Sft 0.00Per % Sft 0.00
v) Painting 2 coats of mile stone
Rate as per item 13(22 a ii) each 0.00 each 0.00
vi) Lettering 28 Nos. letres 4" height 28.00 Nos. 0.00 each 0.00
Total 0.00
LABOUR
Page 24
vi) Painting 2 coats on mile stone
(as per item (v) above)
Rate as per (Item 22 (a) (ii) of Chapter No.13) each 0.00
vii) Lettering 28 No. letters 4" high 28.00 Nos. each
(Item No.11 of Chapter 13)
Total
ITEM RATES
Page 25
DESCRIPTION OF ITEM:
Item No. 18 Providing and erection at site of work.
MATERIAL
i) P.C.C 1 : 4: 8 in foundation
1 x 1.5 x 0.75 x 1.0 = 1.13 Cft
D/d mile stone 0.75 x 0.208 x 1.5 = 0.23 Cft
Rate as per item 6 (3) 0.90 Cft 0.90 Cft 0.00Per % Cft 0.00
ii) R.C.C 1: 2: 4
0.75 x 0.23 x 1.50 = 0.23 Cft
D/d 1.5 x 0.375 x 0.083 = 0.05 Cft
(Rate as per item 6 (6 b) (i) 0.18 Cft 0.18 Cft Per % Cft 0.00
iii) Steel reinforcement dia
6 x 1'-1 11.0 ft.
Tie 3 x 1-6" 4.6
15.6 Rft @ 0.17 lbs/Rft
Rate as per item 8(a) =2.64 lbs = 1.2 1.20 kg 0.00 per kg 0.00
iv) Cement plastec 3/8" thick 1:2 master
1 x 1.92 x 0.75 = 1.44 Sft
1 x 0.75 x 0.21 = 0.16 Sft
Rate as per item 11(6 a) 1.60 Sft 1.60 Sft 0.00Per % Sft 0.00
v) Painting lettering 2 coats furlong post 0.00 each 0.00
(Rate as per item No.20(22 bii)
vi) Lettering 3" height each 0.00 each 0.00
Total
LABOUR
i) Excavation of foundation (Item NO.21(b) of Chap.3)
1.50 x 0.75 x 0.50 = 0.56 Cft 0.56 Cft 0.00Per Cft 0.00
ii) P.C.C 1 : 4 : 8 in foundation
as per item (i) above
Rate as per (Item No.3(b) Chapter No.6) 0.90 Cft 0.00Per % Cft 0.00
iii) R.C.C 1 : 2: 4 (as per item (ii) above
Rate as per (Item 6(a)i Chapter No.6) 0.18 Cft Per % Cft 0.00
vi) Steel reinforcement " dia
(as per item (iii) above)
Rate as per (Item 9(b) Chapter No.6) 1.20 kg 0.00 per kg 0.00
v) Cement plaster 3/8" thick 1 : 2 mortar
(as per item (iv) above)
Rate as per (Item 7(i) of Chapter 11) 1.60 Sft 0.01Per % Sft 0.00
vi) Painting 2 coats of Furlong / km
(as per item (v) above)
(Rate as per item 20(b)) (Item No.22(b) (ii) Ch each 0.00 each 0.00
0.00
ITEM RATES
Labour rate per furlong ( Km) Stone Rs. 0.00 Say 0.00
Composite rate per furlong ( Km) Stone Rs. Say 0.00
Page 26
DESCRIPTION OF ITEM:
MATERIAL
i) R.C.C 1: 2: 4
0.75 x 0.75 x 3 = 1.70 Cft
(Rate as per item 6 (6 b) (i) 1.70 Cft Per Cft 0.00
ii) Steel reinforcement 3/8" dia
1 x 2.5 = 2.5 Rft
2.5 Rft @ 0.37 lbs/Rft
Rate as per item 8(a) = 0.93 lbs = 0.42 0.42 kg 0.00 per kg 0.00
Total 0.00
LABOUR
0.00
ITEM RATES
Page 27
DESCRIPTION OF ITEM:
(a) Sign post of M.S plate 1/8" thick (Mandatory) Road Signs.
MATERIAL
i) P.C.C. 1 : 4 : 8 in foundation
2 x 2 x 2.5 = 10.00 Cft
Rate as per item 6(3) 10.00 Cft 0.00Per % Cft 0.00
ii) Steel
a) T. Iron 0.25 x 0.25 x 0.375 = 9.00 Rft
9 Rft @ 7.17 lbs/ft. = 64.53 lbs
b) M.S plate 1/8" thick
11x2x2 4 = 3.14 Sft @ 5.10 lbs/sft= 16.01 lbs
Total 80.54 lb 36.60 kg 0.00 per kg 0.00
Rate as per item 8(a)
iii) Painting and lettering each 0.00 each 0.00
Total 0.00
LABOUR
0.00
ITEM RATES
Page 28
DESCRIPTION OF ITEM:
MATERIAL
i) P.C.C. 1 : 4 : 8 in foundation
2 x 2 x 2.5 = 10.00 Cft
Rate as per item 6(3) 10.00 Cft 0.00Per % Cft 0.00
ii) Steel
a) T. Iron 0.25 x 0.25 x 0.375 = 9.00 Rft
9 Rft @ 7.17 lbs/ft. = 64.53 lbs
b) M.S plate 1/8" thick
1.7.3 2 @ 5.10 lbs/sft= 8.83 lbs
Total 73.36 lb 33.35 kg 0.00 per kg 0.00
Rate as per item 8(a)
iii) Painting and lettering each each 0.00
Total 0.00
LABOUR
ITEM RATES
Page 29
DESCRIPTION OF ITEM:
Item No. 19 Providing and laying dry brick pavement/soling in streets or roads etc.
sand grouted, laid in proper camber including preparation, watering,
compaction of bed to proper camber, and sand cushion.
MATERIAL
Total 0.00
Contractor's Profit & O 20.00 Percent -
Total -
LABOUR
Total 0.00
Sundries 10.00 Percent -
Total -
Contractor's Profit & O 20.00 Percent -
-
ITEM RATES
Page 30
CHAPTER NO. 9
ROOFING
Note 1. Rates for all finished works include the removal of surplus debris, unused
material and by products.
Note 2. Add extra 13%, 32% and 51% on labour rates only or 6%, 15% and 23% on
composite rates for 2nd, 3rd fourth and subsequent floors respectively.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Page 1
Item No. 1
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Rate Analysis for 125 Sft
Masons for laying tiles 1.50 Nos
Mason for pointing 0.75 Nos
Mason for cement plaster 1.00 No
Mason for mud plaster 0.40 No
3.65 Nos Each -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate P/ Sqm Rs. -
Say
Composite Rate Per 10 Rs. Say -
Composite Rate P/ Sqm Rs. Say -
Page 2
DESCRIPTION OF ITEM NO 2: Second class tile roofing consisting of 4" (100mm)
earth and 1" (25mm) mud plaster with gobri leeping
over " thick cement plaster 1:6 with 34 lbs per %
Sft or 1.72 Kg/Sqm of hot bitumen coating sand
blinded provided over one layer of 12"x6"x2"
(300x150x50mm) tiles, laid in 1:6 cement pointing
underneath of tiles complete, including curing etc.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Per
Tiles 12"x6"x2" 200.00 Nos 1000 N -
Cement for laying in 1:6 mortar 0.23 Bag
Cement for plaster 1:6 0.55 Bag
Cement for pointing 1:2 0.17 Bag
Cement for Plaster along parapet 0.23 Bag
1.18 Bags P. Bag -
Sand for laying in 1:6 mortar 1.68 Cft
Sand for Plaster 1:6 4.14 Cft
Sand for pointing 1:2 0.43 Cft
Sand for Plaster 1:6 along parapet 1.71 Cft
Sand for blinding of bitumen 1.00 Cft
8.96 Cft P. Cft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Page 3
Item No. 2
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Rate Analysis for 125 Sft
Masons 2.50 Nos P. Day -
Unskilled Coolies 5.00 Nos P. Day -
Bahishti 1.00 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. -
Say
Composite Rate Per 10 Rs. Say -
Composite Rate Per Sq Rs. Say -
Page 4
DESCRIPTION OF ITEM NO 3: Covering mud roof with coaltar and fine sand.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate Per Sqm Rs. -
Say
Composite Rate Per 100 Sft Rs. Say -
Composite Rate Per Sqm Rs. Say -
Page 5
Note. The unit of rate is for filling 100 Sft of roof.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Rate Analysis for 150 Sft
Carpenter for making grooves in batten
and fixing of wooden strips 0.50 No Each -
Unskilled Cooly 0.50 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. -
Say
Composite Rate Per 10 Rs. Say -
Composite Rate Per Sq Rs. Say -
Page 6
Item No. 4 Filling spaces in between.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Rate Analysis for 125 Sft
Mason 0.50 No -
Unskilled Cooly 1.00 No -
Bahishti 0.13 No -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 7
Item No. 4 Filling spaces in between.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Per
Bricks including wastage (30+15) 45.00 Nos 1000 N -
Cement 0.20 Bag P. Bag -
Sand 0.75 Cft P. Cft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Rate Analysis for 125 Sft
Mason 0.17 No P. Day -
Cooly 0.17 No P. Day -
Bahishti 0.10 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 8
DESCRIPTION OF ITEM NO 5: Single layer of tiles 9"x4x1" (225 x 112.5 x
40mm) laid over 4" (100mm) earth and 1" (25mm)
mud plaster without Bhoosa grouted with cement
sand 1:3 on top of RCC roof slab provided with 34
Ibs. per % Sft bitumen coating sand blinded.
Labour
Rate Analysis for 150 Sft
Plasterer 0.125 No
Mason for Laying 0.500 No
Mason for Grouting 0.125 No
0.75 No Each -
Cooly for and plaster 0.50 No
Cooly for grouting laying 0.65 No
Cooly for grouting 0.25 No
1.40 Nos Each -
Painter for bitumen 0.50 No Each -
Bahishti 0.50 No Each -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Composite Rate Per 10 Rs. Say -
Composite Rate Per Sq Rs. Say -
Page 9
DESCRIPTION OF ITEM NO 6: Jack arch roofing 4" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with 3" (75mm) earth and 1" (25mm)
plaster soffits of arches cement plastered 1:6
and " (12mm) thick. The rate also includes
bitumen coating centering, laying skew bricks in
cement sand mortar 1:3 and encasing exposed flanges
of the joints with fine cement concrete 1:2:4. Using
stone aggregate.
a) Cement concrete in haunches. (1:6:12)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Per
Bricks 9"x4"x3" 550.00 Nos 1000 N -
Cement for laying 1.60 Bag
Cement for plastering Soffits 0.57 Bag
Cement for concrete in haunches 2.00 Bag
Cement for concrete in flanges 0.60 Bag
4.77 Bags P. Bag -
Page 10
a) Cement concrete in haunches. (1:6:12)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Rate Analysis for 125 Sft
Masons 3.50 Nos P. Day -
Carpenter 0.50 No P. Day -
Unskilled Coolies 7.00 Nos P. Day -
Bahishti 1.00 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 11
Item No. 6 Jack arch roofing 4" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with 3" (75mm) earth and 1" (25mm)
plaster soffits of arches cement plastered 1:6
and " (12mm) thick. The rate also includes
bitumen coating centering, laying skew bricks in
cement sand mortar 1:3 and encasing exposed
flanges of the joints with fine cement concrete
1:2:4. Using stone aggregate.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material Per
Bricks 9"x4"x3" 550.00 Nos 1000 N -
Cement for laying 1.60 Bag
Cement for plastering Soffits 0.57 Bag
Cement for concrete in haunches 4.10 Bag
Cement for concrete in flanges 0.60 Bag
6.87 Bags P. Bag -
Total
Contractor's Profit & Ove 20 Percent
Total
Page 12
b) Cement concrete in haunches (1:3:6)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Rate Analysis for 125 Sft
Masons 3.50 Nos P. Day -
Carpenter 0.50 No P. Day -
Unskilled Coolies 7.00 Nos P. Day -
Bahishti 1.00 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 13
DESCRIPTION OF ITEM NO 7: Jack arch roofing 4" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with " (12mm) thick cement plaster
1:6 on top (Except earth filling, plaster and gobri),
soffits of arches cement plastered. The rate also
includes bitumen coating centering, laying skew
bricks in cement sand mortar 1:3 and encasing
exposed flanges of the joints with fine cement
concrete 1:2:4. Using stone aggregate.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Per
Bricks 9"x4"x3" 550.00 Nos 1000 N -
Cement for laying 1.60 Bag
Cement for plastering top 0.51 Bag
Cement for plastering soffits 0.57 Bag
Cement for concrete in haunches 2.00 Bag
Cement for concrete in flanges 0.60 Bag
5.28 Bags P. Bag -
Page 14
a) Cement concrete in haunches. (1:6:12)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Rate Analysis for 125 Sft
Masons 2.75 Nos P. Day -
Carpenter 0.50 No P. Day -
Unskilled Coolies 5.50 Nos P. Day -
Bahishti 1.00 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 15
Item No. 7 Jack arch roofing 4" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with " (12mm) thick cement plaster
1:6 on top (Except earth filling, plaster and gobri),
soffits of arches cement plastered. The rate also
includes bitumen coating centering, laying skew
bricks in cement sand mortar 1:3 and encasing
exposed flanges of the joints with fine cement
concrete 1:2:4. Using stone aggregate.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Per
Bricks 9"x4"x3" 550.00 Nos 1000 N -
Cement for laying 1.60 Bag
Cement for plastering soffits 0.57 Bag
Cement for concrete in haunches 4.10 Bag
Cement for concrete in flanges 0.60 Bag
6.87 Bags P. Bag -
Page 16
b) Cement concrete in haunches. (1:3:6)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Rate Analysis for 125 Sft
Masons 2.75 Nos P. Day -
Carpenter 0.50 No P. Day -
Unskilled Coolies 5.50 Nos P. Day -
Bahishti 1.00 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 17
DESCRIPTION OF ITEM NO 8: Extra for vaulted jack arch roofing
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Rate Analysis for 125 Sft
Masons 1.00 No P. Day -
Carpenter 1.00 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Per 1 Rs. -
Page 18
DESCRIPTION OF ITEM NO 9: Jack arch roofing of shingle and cement concrete
(1:3:6), 4" (112.5mm) thick at crown, with "
(12mm) cement plaster including cost of
supplying erecting and dismantling centering.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 19
DESCRIPTION OF ITEM NO 10: Earth filling over roof including watering
ramming with 1" (25mm) mud plaster finished
with gobri leeping.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Rate Analysis for 125 Sft
Bahishti 0.12 No P. Day -
Coolies for lifting and ramming earth 1.00 No P. Day -
Mason 0.12 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 20
Item No. 10 Earth filling over roof including watering
ramming with 1" (25mm) mud plaster finished
with gobri leeping.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 21
DESCRIPTION OF ITEM NO 11: 1/8"(3mm) thick gobri leeping on roofs or floors.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Rate Analysis for 150 Sft
Mason 0.12 No P. Day -
Bahishti 0.06 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 22
DESCRIPTION OF ITEM NO 12: 2 coats of bitumen laid hot using 34 lbs
(1.72Kg/Sqm) per % Sft over roof and
blinded with sand at 1 Cft per % Sft.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total
Labour
Rate for 125 Sft
Cooly for heating & laying 1.00 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Per 1 Rs. Say -
Labour Rate for P/ Sq Rs. Say -
Page 23
DESCRIPTION OF ITEM NO 13: Fixing corrugated galvanized iron sheets with
G.I. bolts, nuts, limpet and bitumen washers,
wind ties complete in all respect without valleys
and ridges.
a) 20 - S. W. G.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Sheets of 20 gauge = 100 Sft.
wastage & overlaping @ 20% = 20 Sft
=120 Sft 2Cwt (102 .65) Kg P. Kg -
Wind tie (rod) 22Lbs(9 .98) Kg P. Kg -
G.I. bolts and nuts 2.00 Doz Doz -
Limpet washers 2.00 Doz Doz -
G.I. Hook, bolts & nuts 1.50 Doz Doz -
Bitumen washers 3.85 Doz Doz -
Charcoal 4 Sr. (3. 75) Kg P. Kg -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 24
Item No. 13 Fixing corrugated galvanized iron sheets with
G.I. bolts, nuts, limpet and bitumen washers, wind
ties complete in all respect without valleys and
ridges.
b) 22 - S. W. G.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Per 1 Rs. Say -
Labour Rate for P/ Sq Rs. Say -
Page 25
Item No. 13 Fixing corrugated galvanized iron sheets with
G.I. bolts, nuts, limpet and bitumen washers, wind
ties complete in all respect without valleys and
ridges.
c) 24 - S. W. G.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Rate for 150 Sft
Blacksmith 1.00 No P. Day -
Cooly 1.00 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 26
DESCRIPTION OF ITEM NO 14: Khassi parnalas in cement and sand mortar (1:2)
12" (300mm) outside width finished smooth with
a floating coat of neat cement.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 15 Rft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate for Per R Rs. Say -
Page 27
DESCRIPTION OF ITEM NO 15: Making Khuras, on roof size 2' x 2' x 4" (600 x 600 x
100mm)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. Say -
Page 28
DESCRIPTION OF ITEM NO 16: Bottom khuras of brick masonry in cement mortar
(1:6) 4'x2'x4" (1200x600x114mm) over 3"
(75mm) cement concrete (1:4:8)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Rate Analysis for 1.25 No.
Mason 0.20 No P. Day -
Cooly 0.20 No P. Day -
Bahishti 0.05 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. Say -
Page 29
DESCRIPTION OF ITEM NO 17: Plain galvanized iron sheets of 22 S.W.G. rain
water down pipe including clamp and fixing in
position.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Rate Analysis for 1.25 Rft
Blacksmith 0.03 No P. Day -
Unskilled Cooly 0.03 No P. Day -
Mason 0.03 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate for Per R Rs. Say -
Page 30
DESCRIPTION OF ITEM NO 17: Plain galvanized iron sheets of 22 S.W.G. rain
water down pipe including clamp and fixing in
position.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate for Per R Rs. Say -
Page 31
DESCRIPTION OF ITEM NO 18: Plain galvanized iron sheets flashing of 22 gauge.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 32
DESCRIPTION OF ITEM NO 19:
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 100 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 33
DESCRIPTION OF ITEM NO 20: Cast iron rain water down pipe fixed in position,
excluding heads and shoes, but including painting
and clamps, etc.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 6 Rft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Rate per Rft 0.00
6 -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -
Page 34
Item No. 20 Cast iron rain water down pipe fixed in position,
excluding heads and shoes, but including painting
and clamps, etc.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 6 Rft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Rate for One Reft 0.00
6 -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -
Page 35
DESCRIPTION OF ITEM NO 21: Rain water down pipe cast iron heads fixed in
place, including cost of clamp, holdfast, and
painting.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. Say -
Page 36
DESCRIPTION OF ITEM NO 22: Shoes bends or offsets for cast iron rain water
down pipe including fixing and painting.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. Say -
Page 37
DESCRIPTION OF ITEM NO 23: Plain G.I. sheet iron spouts fixed in position,
including painting.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. Say -
Page 38
DESCRIPTION OF ITEM NO 24: Laying " (12mm) thick deodar ceiling complete
(including sawing planing and fixing)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 100 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 39
DESCRIPTION OF ITEM NO 25: Flat sheet roof with galvanized iron sheets
including battens, rolls, screw, clips etc. (planking
to be paid for separately).
a) 22 B. W. G. Sheets Roofing.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 400 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Page 40
Detail Unit Rate (British System) per 100 Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Rate Analysis for 500 Sft
Cooly 12.00 Nos P. Day -
Carpenter 1.50 Nos P. Day -
Blacksmith 8.00 Nos P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 41
Item No. 25 Flat sheet roof with galvanized iron sheets
including battens rolls screw clips etc. (planking
to be psid for separately).
b) 24 B. W. G. Sheets Roofing.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 400 Sft
Material
Page 42
DESCRIPTION OF ITEM NO 26: Asbestos cement corrugated sheet roofing
including necessary over laps and G.I. hooks,
bolts, nuts, screws washers and bitumen washers
etc. (excluding valleys and ridges etc.)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Rate for 150 Sft
Cooly 2.00 Nos P. Day -
Carpenter 1.00 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 43
DESCRIPTION OF ITEM NO 27: Extra labour for erection of G.I. sheets, flat sheet
or asbestos sheet roofing, above 20' height in
difficult position including lifting with care and
special scaffolding along live electric wires.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Page 44
DESCRIPTION OF ITEM NO 28: Fixing asbestos cement sheet ridges and valleys
" (6mm) thick.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 61 Rft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -
Page 45
DESCRIPTION OF ITEM NO 29: Plain galvanized iron sheet ridging including
fixture, timber for ridge roll and ridge sheeting.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -
Page 46
Item No. 29 Plain galvanized iron sheet ridging including
fixture, timber for ridge roll and ridge sheeting.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -
Page 47
Item No. 29 Plain galvanized iron sheet ridging including
fixture, timber for ridge roll and ridge sheeting.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -
Page 48
DESCRIPTION OF ITEM NO 30: Plain 22 Gauge G.I. sheet gutter semi-circular
8" dia meter.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -
Page 49
DESCRIPTION OF ITEM NO 31: Making masonry ventilators in cement sand
mortar (1:4)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Per
Pacca bricks 50.00 Nos 1000 N -
Cement 0.17 Bag P. Bag -
Sand 0.88 Cft P. Cft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Rate Analysis for 1.5 No.
Cooly 1.00 No P. Day -
Mason 1.00 No P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. Say -
Page 50
DESCRIPTION OF ITEM NO 32: Fixing water spouts or parnalas.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. Say -
Page 51
DESCRIPTION OF ITEM NO 33: Making drip course 2"x" (50x12mm) under
RCC Slab edges in outer opening, in cement, sand
mortar (1:2)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 100 Rft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Metre Rs. Say -
Composite Rate Per Rf Rs. Say -
Composite Rate Per Me Rs. Say -
Page 52
DESCRIPTION OF ITEM NO 34: Supplying and laying twin G.I. sheet 20 SWG
duly painted with bitumen with polythene film 300
gauge in between to provide a sliding joint under
the bearing of beams with 3" long 3/8" (10mm)
bar to act as hold fast on wall & beam.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Rate Analysis for 2 Sft
Cooly
placing in position 0.02 No P. Day -
Blacksmith for cutting of G.I. sheet 0.03 No P. Day -
Welding of bars 4 points 4.00 Nos P. Poi -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 53
DESCRIPTION OF ITEM NO 35: Providing and laying roof insulation, comprising of
single layer of tiles 9"x4"x1" (225 x 112.5 x
40mm) grouted with cement sand mortar 1:3 laid
over 2" thick earth (including Mud Plaster) over
thermopore sheet, over polythene sheet 300 gauge
over a layer of bitumen, complete in all respect.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Per
Brick tiles 9"x4"x1" (225x112.5x40mm) 350.00 Nos 1000 N -
Sand 2.00 Cft P. Cft -
Cement 0.50 Bag P. Bag -
Bitumen 34Lbs(15 .43) Kg P. Kg -
Earth 20.00 Cft P. Cft -
Polythene 0.03" (0.08mm) including
wastage 5% 1.58Lbs(0 .72) Kg P. Kg -
Thermopore " (12mm) thick 1/c 5%
wastage 105.00 Sft P. Sft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Plasterer 0.13 No
Mason for laying 0.50 No
Mason for grouting 0.13 No
0.75 No P. Day -
Page 54
i) Thermopore sheet " (13mm) thick.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 55
Item No. 35 Providing and laying roof insulation, comprising of
single layer of tiles 9"x4"x1" (225 x 112.5 x
40mm) grouted with cement sand mortar 1:3 laid
over 2" thick earth (including Mud Plaster) over
thermopore sheet, over polythene sheet 300 gauge
over a layer of bitumen, complete in all respect.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Per
Clay tiles 9"x4"x1" (225x112.5x40mm) 350.00 Nos 1000 N -
Sand 2.00 Cft P. Cft -
Cement 0.50 Bag P. Bag -
Bitumen 34Lbs(15 .43) Kg P. Kg -
Earth 20.00 Cft P. Cft -
Polythene 0.03" (0.08mm) 1/c
wastage 5% 1.58Lbs(0 .72) Kg P. Kg -
Thermopore " (19mm) thick 1/c 5%
wastage 105.00 Sft P. Sft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Plasterer 0.13 No
Mason for laying 0.50 No
Mason for grouting 0.13 No
0.75 No P. Day -
0.75 Say
Page 56
ii) " (20mm) thick thermopore sheet.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 57
Item No. 35 Providing and laying roof insulation, comprising of
single layer of tiles 9"x4"x1" (225 x 112.5 x
40mm) grouted with cement sand mortar 1:3 laid
over 2" thick earth (including Mud Plaster) over
thermopore sheet, over polythene sheet 300 gauge
over a layer of bitumen, complete in all respect.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Per
Brick tiles 9"x4"x1" (225x112.5x40mm) 350.00 Nos 1000 N -
Sand 2.00 Cft P. Cft -
Cement 0.50 Bag P. Bag -
Bitumen 34Lbs(15 .43) Kg P. Kg -
Earth 20.00 Cft P. Cft -
Polythene 0.03" (0.08mm) 1/c
wastage 5% 1.58Lbs(0 .72) Kg P. Kg -
Thermopore 1" (13mm) thick 1/c 5%
wastage 105.00 Sft P. Sft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Plasterer 0.13 No
Mason for laying 0.50 No
Mason for grouting 0.13 No
0.76 No P. Day -
Page 58
Item No. 35
iii) Thermopore sheet 1" (25mm) thick.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 S Rs. Say -
Labour Rate Per Sqm Rs. Say -
Page 59
DESCRIPTION OF ITEM NO 36: Providing and fixing A.C. rain water down pipe
4" (100mm) dia with shoe, T-bend, clamp etc.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 13 Rft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -
Page 60
DESCRIPTION OF ITEM NO 37: Making jharries in existing brick masonry for
providing recesses for bearing of RCC roof slab
including repairing the damaged face.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 40 Rft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -
Page 61
Item No. 37 Making jharries in existing brick masonry for
providing recesses for hearing of RCC roof slab
including repairing the damaged face.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 40 Rft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. Say -
Labour Rate Per Rm Rs. Say -
Page 62
DESCRIPTION OF ITEM NO 38: Making recess in exixting brick masonery for
bearing of beam, girder, R.S. joist, etc. including
repairing damaged face.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 12 Holes
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. Say -
Page 63
Item No. 38 Making recess in exixting brick masonery for
bearing of beam, girder, R.S. joist, etc. including
repairing damaged face.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 25 Holes
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. Say -
Page 64
DESCRIPTION OF ITEM NO 39: Hoisting R.S. Beams and wooden beams and
placing in position.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 65
DESCRIPTION OF ITEM NO 40: Hoisting and placing in position sahl ballies, over
roof.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 35 Nos
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 66
DESCRIPTION OF ITEM NO 41: Hoisting precast RCC/Pre-stressed concrete
battens and placing in position.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Page 67
DESCRIPTION OF ITEM NO 42: Hoisting and placing in position RC trough.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Page 68
Detail Unit Rate (British System) per Each
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Page 69
DESCRIPTION OF ITEM NO 43: Hoisting and placing in position RC inverted
battens.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Page 70
DESCRIPTION OF ITEM NO 44: Reinforced cement concrete spout, including
fixing in position, with top & bottom khurras.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. Say -
Page 71
CHAPTER NO. 15
SHEET PILING
1 Unless otherwise stated, the rate includes handling of materials with in 3 chains (90M).
2 Rates for all finished works include the removal of surplus debris, unused material
and by products.
3 For handling of all types of materials for shortleads including carriage upto 3 Chains,
(90 M) nothing is to be paid as extra. Where handling and carriage involves an extra
lead beyond 3 Chains, (90 M) carriage for whole of the distance should be paid.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 cut
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 1
DESCRIPTION OF ITEM NO 2: Cutting universal Piles.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 cut
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 2
DESCRIPTION OF ITEM NO 3: Driving steel piles 25' to 30' (7.5 to 9 M).
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 125 Sft
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 3
DESCRIPTION OF ITEM NO 4: Driving steel piles more than 15' (4.5 M) and
less than 25' (7.5 M).
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 125 Sft
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 4
DESCRIPTION OF ITEM NO 5: Driving steel piles 15' (4.5 M) and under.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 125 Sft
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 5
DESCRIPTION OF ITEM NO 6: Dolleying piles.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 No.
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 6
DESCRIPTION OF ITEM NO 7: Drilling holes in piles by hand.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 12 Holes
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 7
DESCRIPTION OF ITEM NO 8: Raising and lowering machine.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.5 Feet
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 8
DESCRIPTION OF ITEM NO 9: Turning machine 90.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 Jobs
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 9
DESCRIPTION OF ITEM NO 10: Turning machine 135.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 Jobs
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 10
DESCRIPTION OF ITEM NO 11: Turning machine 180.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 Jobs
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 11
DESCRIPTION OF ITEM NO 12: Traveling machine (Light).
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 Chain
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 12
DESCRIPTION OF ITEM NO 13: Loading and unloading piles.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 Ton
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 13
DESCRIPTION OF ITEM NO 14: Dismantling piling machine.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.5 No.
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 14
DESCRIPTION OF ITEM NO 15: Erecting pilling machine.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.3 No.
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Page 15
DESCRIPTION OF ITEM NO 16: Carriage of pile machine under different
condition.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Assumed for 1.25 Chain
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Chain Rs. 0.00 0.00 Say -
1.25
Page 16
CHAPTER NO. 22
SINKING OF WELLS
DESCRIPTION OF ITEM:
Item No. 1
Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within
LABOUR
ITEM RATE
Page 1
Item No. 1
Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).
LABOUR
ITEM RATE
Page 2
Item No. 1
Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).
LABOUR
ITEM RATE
Page 3
Item No. 1
Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).
LABOUR
ITEM RATE
Page 4
Item No. 1
Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).
B) In Hard Soil.
LABOUR
ITEM RATE
Page 5
Item No. 1
Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).
B) In Hard Soil.
LABOUR
ITEM RATE
Page 6
Item No. 1
Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).
B) In Hard Soil.
LABOUR
ITEM RATE
Page 7
Item No. 1
Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).
B) In Hard Soil.
LABOUR
ITEM RATE
Page 8
Item No. 1
Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).
LABOUR
ITEM RATE
Page 9
Item No. 1
Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).
LABOUR
ITEM RATE
Page 10
Item No. 1
Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).
LABOUR
ITEM RATE
Page 11
Item No. 1
Excavation of well in dry upto 20' (6 M) below ground level and disposal of soil within one chain (30 M).
LABOUR
ITEM RATE
Page 12
DESCRIPTION OF ITEM :
Item No. 2
Dry sinking of well including loading and removing excavated material, within one chain (30 metre).
A) In ordinary soil.
LABOUR
ITEM RATE
Page 13
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
A) In ordinary soil.
LABOUR
ITEM RATE
Page 14
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
A) In ordinary soil.
LABOUR
ITEM RATE
Page 15
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
A) In ordinary soil.
LABOUR
ITEM RATE
Page 16
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
A) In ordinary soil.
LABOUR
ITEM RATE
Page 17
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
A) In ordinary soil.
LABOUR
ITEM RATE
Page 18
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
A) In ordinary soil.
LABOUR
ITEM RATE
Page 19
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
A) In ordinary soil.
LABOUR
ITEM RATE
Page 20
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
B) In Hard Soil.
LABOUR
ITEM RATE
Page 21
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
B) In Hard Soil.
LABOUR
ITEM RATE
Page 22
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
B) In Hard Soil.
LABOUR
ITEM RATE
Page 23
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
B) In Hard Soil.
LABOUR
ITEM RATE
Page 24
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
B) In Hard Soil.
LABOUR
ITEM RATE
Page 25
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
B) In Hard Soil.
LABOUR
ITEM RATE
Page 26
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
B) In Hard Soil.
LABOUR
ITEM RATE
Page 27
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
B) In Hard Soil.
LABOUR
ITEM RATE
Page 28
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
LABOUR
ITEM RATE
Page 29
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
LABOUR
ITEM RATE
Page 30
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
LABOUR
ITEM RATE
Page 31
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
LABOUR
Page 32
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
LABOUR
ITEM RATE
Page 33
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
LABOUR
ITEM RATE
Page 34
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
LABOUR
ITEM RATE
Page 35
Item No. 2
Dry sinking of well including loading and removing excavated material, with in one chain (30 metre).
LABOUR
ITEM RATE
Page 36
DESCRIPTION OF ITEM:
Item No. 3
Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 Metre).
Rate
Qty Per Unit Amount
LABOUR
ITEM RATE
Page 37
Item No. 3
Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).
Rate
Qty Per Unit Amount
LABOUR
ITEM RATE
Page 38
Item No. 3
Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).
Rate
Qty Per Unit Amount
ITEM RATE
Page 39
Item No. 3
Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).
Rate
Qty Per Unit Amount
LABOUR
ITEM RATE
Page 40
Item No. 3
Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).
Rate
Qty Per Unit Amount
LABOUR
ITEM RATE
Page 41
Item No. 3
Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).
Rate
Qty Per Unit Amount
LABOUR
ITEM RATE
Page 42
Item No. 3
Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).
Rate
Qty Per Unit Amount
LABOUR
ITEM RATE
Page 43
Item No. 3
Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).
Rate
Qty Per Unit Amount
LABOUR
ITEM RATE
Page 44
Item No. 3
Wet Sinking of Well in ordinary soil (value of C upto 5) for depths below spring level including charges of
machinery shoring, kentlege and removal of excavated soil within one chain (30 metre).
Rate
Qty Per Unit Amount
LABOUR
ITEM RATE
Page 45
DESCRIPTION OF ITEM
Item No. 4
Wet Sinking of Well in cohesive soil (value of C more than 5) for depth below spring level including charges of
machinery, shoring, kentledge and removal of excavated soil within one chain (30 Metre).
Rate
Qty Per Unit Amount
3 Loading gunny bags for one side 100.00 Nos. - er 100 Nos -
4 Sleepers / planks
Cost of 15 Nos. sleeper @ Rs. 0.00
Each 0.00
Depriciation 1/6 = 0.00
Total 0.00
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Page 46
B. Pumping for Dewatering
Running Cost
c) CREW
Page 47
Item No. 4
Wet sinking of well in cohesive soil (value of C more than 5) for depth below spring level including charges of
machinery, shoring kentledge and removal of excavated soil within one chain (30 metre).
(1)
LABOUR 150
ITEM RATE
Page 48
Item No. 4
1)
ii) 10' (3 M) to 20' (6 M) depth
LABOUR
ITEM RATE
Page 49
Item No. 4
(1)
LABOUR
ITEM RATE
Page 50
Item No. 4
LABOUR
ITEM RATE
Page 51
Item No. 4
LABOUR
ITEM RATE
Page 52
Item No. 4
LABOUR
ITEM RATE
Page 53
Item No. 4
(1)
LABOUR
Page 54
Item No. 4
LABOUR
ITEM RATE
Page 55
Item No. 4
LABOUR
ITEM RATE
Page 56
DETAIL OF SLEEPERS
MATERIAL
Depreciation 1/6 -
-
ITEM RATE
Page 57
DESCRIPTION OF ITEM:
Item No. 5
Wet sinking of well in shingle, or gravel etc. for depth below spring level, including charges of machinery, sho
removal of excavated spoil within one chain load.
Rate
Qty Per Unit Amount
3 Loading gunny bags for one side 100.00 Nos. - er 100 Nos -
4 Sleepers / planks
Cost of 15 Nos. sleeper @ Rs. 0.00
Each 0.00
Depriciation 1/6 = 0.00
Total 0.00
Running Cost
c) CREW
Rft of Well - -
4
Page 58
Sundries 10.00 Percent -
Total -
Page 59
Item No. 5
Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain.
Rate
Qty Per Unit Amount
LABOUR
Page 60
Item No. 5
Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain.
LABOUR
Page 61
Item No. 5
Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain.
LABOUR
ITEM RATE
Page 62
Item No. 5
Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain.
LABOUR
ITEM RATE
Page 63
Item No. 5
Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain (30 metre).
LABOUR
ITEM RATE
Page 64
Item No. 5
Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain (30 metre)
LABOUR
ITEM RATE
Page 65
Item No. 5
Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain (30 metre).
LABOUR
ITEM RATE
Page 66
Item No. 5
Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain (30 metre).
LABOUR
ITEM RATE
Page 67
Item No. 5
Wet sinking of well in shingle or gravel etc. for depths below spring level including charges of machinery,
shoring, kentledge and removal of excavated soil with in one chain (30 metre).
LABOUR
ITEM RATE
Page 68
DESCRIPTION OF ITEM:
Item No. 6
MATERIAL
LABOUR
ITEM RATE
Page 69
DESCRIPTION OF ITEM:
Item No. 7
Rate
Qty Per Unit Amount
LABOUR
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
ITEM RATE
Page 70
DESCRIPTION OF ITEM:
Item No. 8
Providing making and laying RCC Well Curb in position, using coarse sand, including all kinds of
form, moulds, curing, shuttering, rendering and finishing the exposed surface, (including screening
and washing of aggregrate.
MATERIAL
LABOUR
ITEM RATE
Page 71
DESCRIPTION OF ITEM:
Item No. 8
Providing making and laying RCC Well Curb in position, using coarse sand, including all kinds of
form, moulds, curing, shuttering, rendering and finishing the exposed surface, (including screening
and washing of aggregrate.
MATERIAL
LABOUR
ITEM RATE
Page 72
DESCRIPTION OF ITEM:
Item No. 9
Rate
Qty Per Unit Amount
ITEM RATE
Page 73
DESCRIPTION OF ITEM:
Item No. 10
Rate
Qty Per Unit Amount
MATERIAL
ITEM RATE
Page 74
CHAPTER NO. 8
STONE MASONRY
DESCRIPTION OF ITEM NO 1: Random, rubble masonry (uncoursed), in
foundation and plinth.
a) Dry Masonry
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 1
Item No. 1 b) In Mud Mortar
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 2
Item No. 1 c) In Lime Mortar, Ratio (1 Lime 2 Sand).
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 3
Item No. 1 d) In Cement Sand Mortar
i) Ratio ( 1:3 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total 118.13
Contractor's Profit & Ove ##### Percent 23.63
Total 141.75
Labour
Total -
Sundries ##### Percent -
Total -
Page 4
Item No. 1 d) In Cement Sand Mortar
ii) Ratio ( 1:4 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 5
Item No. 1 d) In Cement Sand Mortar
iii) Ratio ( 1:6 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 6
Item No. 1 d) In Cement Sand Mortar
iv) Ratio ( 1:8 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 7
DESCRIPTION OF ITEM NO 2: Coursed Rubble Masonry hammer dressed,
foundation and plinth.
a) Dry Masonry
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 8
Item No. 2 b) In Mud Mortar
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total 300.00
Contractor's Profit & Ove ##### Percent 60.00
Total 360.00
Labour
Total -
Sundries ##### Percent -
Total -
Page 9
Item No. 2 c) In Lime Sand Mortar. (Ratio 1:2)
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 10
Item No. 2 d) In Cement Sand Mortar
i) Ratio ( 1:3 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 11
Item No. 2 d) In Cement Sand Mortar
ii) Ratio ( 1:4 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 12
Item No. 2 d) In Cement Sand Mortar
iii) Ratio ( 1:6 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 13
Item No. 2 d) In Cement Sand Mortar
iv) Ratio ( 1:8 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 14
DESCRIPTION OF ITEM NO 3: Random Rubble Masonry (uncoursed) in ground
floor or 20'(6 M) height,building/other than
a) Dry Masonry
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 15
Item No. 3 b) In Mud Mortar
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 16
Item No. 3 c) In Lime Sand Mortar. (Ratio 1:2)
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 17
Item No. 3 d) In Cement Sand Mortar
i) Ratio ( 1:3 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 18
Item No. 3 d) In Cement Sand Mortar
ii) Ratio ( 1:4 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 19
Item No. 3 d) In Cement Sand Mortar
iii) Ratio ( 1:6 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 20
Item No. 3 d) In Cement Sand Mortar
iv) Ratio ( 1:8 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 21
DESCRIPTION OF ITEM NO 4: Coursed Rubble Masonry hammer dressed in
ground floor or 20' (6 M) height, building o
than building.
a) Dry Masonry
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 22
Item No. 4 b) In Mud Mortar
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 23
Item No. 4 c) In Lime Sand Mortar. (Ratio 1:2)
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 24
Item No. 4 d) In Cement Sand Mortar
i) Ratio ( 1:3 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 25
Item No. 4 d) In Cement Sand Mortar
ii) Ratio ( 1:4 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 26
Item No. 4 d) In Cement Sand Mortar
iii) Ratio ( 1:6 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 27
Item No. 4 d) In Cement Sand Mortar
iv) Ratio ( 1:8 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 28
DESCRIPTION OF ITEM NO 5: Ashlar block in course or scabbled masonry
(including dressing etc.) in ground floor or
(6 M) height, Building other than building.
a) In Lime Sand. (Ratio 1:2)
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 29
Item No. 5 b) In Cement Sand Mortar
i) Ratio ( 1:3 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 30
Item No. 5 b) In Cement Sand Mortar
ii) Ratio ( 1:4 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 31
Item No. 5 b) In Cement Sand Mortar
iii) Ratio ( 1:6 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 32
DESCRIPTION OF ITEM NO 6: Ashlar fine masonry (including dressing etc.
ground floor or 20' (6 M) height, Building o
than building.
a) In Lime Sand Mortar. (Ratio 1:2)
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 33
Item No. 6 b) In Cement Sand Mortar
i) Ratio ( 1:3 )
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 34
Item No. 6 b) In Cement Sand Mortar
ii) Ratio 1:4
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 35
Item No. 6 b) In Cement Sand Mortar
iii) Ratio 1:6
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 36
DESCRIPTION OF ITEM NO 7: Extra labour on items 3,4,5 and 6 for work i
i) First Floor
Qty Rate
Per Unit (Rs) Amount (Rs)
Total -
Sundries ##### Percent -
Total -
Page 37
tem No. 7 ii) Second Floor
Qty Rate
Per Unit (Rs) Amount (Rs)
Total -
Sundries ##### Percent -
Total -
Page 38
Item No. 7 iii) Third Floor
Qty Rate
Per Unit (Rs) Amount (Rs)
Total -
Sundries ##### Percent -
Total -
Page 39
Item No. 7 iv) Fourth Floor
Qty Rate
Per Unit (Rs) Amount (Rs)
Total -
Sundries ##### Percent -
Total -
Page 40
DESCRIPTION OF ITEM NO 8: Extra labour on items 3,4,5 and 6 above for
5ft (1.5 M) additional height building other
building part thereof.
Qty Rate
Per Unit (Rs) Amount (Rs)
Total -
Sundries ##### Percent -
Total -
Page 41
DESCRIPTION OF ITEM NO 9: Extra labour for arch work in stone masonry
including centering and de-centering, etc.
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
-
Contractor's Profit & Ove ##### Percent -
Total for 33.8 Cft -
Total for 100 Cft 19.8 x 100 -
33.8
Labour
Total -
Sundries ##### Percent -
Total -
Page 42
DESCRIPTION OF ITEM NO 10: Extra labour for :-
Qty Rate
Per Unit (Rs) Amount (Rs)
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 43
tem No. 10 b) Cornice and string course
Qty Rate
Per Unit (Rs) Amount (Rs)
Total -
Sundries ##### Percent -
Total -
Page 44
DESCRIPTION OF ITEM NO 11: Dressing Stones
a) Hammer Dressed
Qty Rate
Per Unit (Rs) Amount (Rs)
Total -
Sundries ##### Percent -
Total -
Page 45
tem No. 11 b) Rough tooled dressed
Qty Rate
Per Unit (Rs) Amount (Rs)
Total -
Sundries ##### Percent -
Total -
Page 46
tem No. 11 c) Chisel dressed
Qty Rate
Per Unit (Rs) Amount (Rs)
Total -
Sundries ##### Percent -
Total -
Page 47
tem No. 11 d) Fine dressed
Qty Rate
Per Unit (Rs) Amount (Rs)
Total -
Sundries ##### Percent -
Total -
Page 48
DESCRIPTION OF ITEM NO 12: Dhajji walling 5"x5" (125x125mm) thick
deodar framing with stone laid in 1:6 cement
sand mortar and (1:4) cement sand plaster on
both sides.
Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 234 Sft
a) Detail of Wood
i)Top bottom
2x18'x5x5 = 6.25 Cft
12x12
iiVertical post 4" (100mm) apart
6x13'x5/12x5/12 = 13.55 Cft
iii) Horizontal Pieces
3x18'x5/12x = 5.62 Cft
iv) Diagonl Strutts
20x6x5/12x1/6 = 6.25 Cft
31.67 Cft
Wastage 20% = 6.33
38.00 Cft
This wood can be used 10 time hence
wood for our operation would be = 38/10 3.80 Cft
b) Stone (Quarried)
1x18x13x5/12 = 98.00 Cft
Deduct Scantling = 32.00 Cft
66.00 Cft
Therefore stone required = 66 x 2 112 Cft
Material
Page 49
Item No. 12
Qty Rate
Per Unit (Rs) Amount (Rs)
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 50
DESCRIPTION OF ITEM NO 13: Providing and fixing stone blocks from 2 Cft
Cft (0.06 to 017 M) each, including lift up
20' (6 M).
Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 4 Cft
Material
Total -
Contractor's Profit & Ove ##### Percent -
Total -
Labour
Total -
Sundries ##### Percent -
Total -
Page 51
DESCRIPTION OF ITEM NO 14: Providing and fixing stone blocks under 2 Cf
(0.05 M) each, including lift upto 20 Cft (
Qty Rate
Per Unit (Rs) Amount (Rs)
Total -
Contractor's Profit & Ove ##### Percent -
Total 0.01 0.01
2.00 0.01
Labour Rate Analysis for 1 Cft
Total -
Sundries ##### Percent -
Total -
Page 52
CHAPTER NO. 20
SURFACE DRAINAGE
DESCRIPTION OF ITEM NO 1: Tega formed of pacca bricks on end, laid in and over cement
sand mortar projecting to a height of not more than 6"
(150mm) top of drain along the property side where required,
laid to lines, grades, slopes and shape according to the
engineer's drawing.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total 312.00
Contractor's Profit & Ove 20 Percent 62.40
Total 374.40
Total -
Sundries 10 Percent -
Total -
Page 1
Item No. 1 Tega formed of pacca bricks on end, laid in and over cement
sand mortar projecting to a height of not more than 6"
(150mm) top of drain along the property side where required,
laid to lines, grades, slopes and shape according to the
engineer's drawing.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Page 2
Item No. 1 Tega formed of pacca bricks on end, laid in and
over cement sand mortar projecting to a height of
not more than 6" (150mm) top of drain along the
property side where required, laid to lines,
grades, slopes and shape according to the
engineer's drawing.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Page 3
Item No. 1 Tega formed of pacca bricks on end, laid in and
over cement sand mortar projecting to a height of
not more than 6" (150mm) top of drain along the
property side where required, laid to lines,
grades, slopes and shape according to the
engineer's drawing.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Page 4
DESCRIPTION OF ITEM NO 2: Pacca flat brick 3" (75mm) thick, laid in
reimbursement, in cement, sand mortar on sides
of drains and in other works where required. All
joints to be completely filled and struck flush.
a) Ratio (1:3)
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -
Page 5
Item No. 2 Pacca flat brick 3" (75mm) thick, laid in
reimbursement, in cement, sand mortar on sides
of drains and in other works where required. All
joints to be completely filled and struck flush.
b) Ratio (1:5)
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -
Page 6
Item No. 2 Pacca flat brick 3" (75mm) thick, laid in
reimbursement, in cement, sand mortar on sides
of drains and in other works where required. All
joints to be completely filled and struck flush.
c) Ratio (1:6)
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -
Page 7
DESCRIPTION OF ITEM NO 3: Pacca brick on edge, laid in reimbursement, in
cement, sand mortar on sides of drains and in
other works where required. All joints to be
completely filled and struck flush.
a) Ratio (1:3)
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -
Page 8
Item No. 3 Pacca brick on edge, laid in reimbursement, in
cement, sand mortar on sides of drains and in
other works where required. All joints to be
completely filled and struck flush.
b) Ratio (1:5)
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -
Page 9
Item No. 3 Pacca brick on edge, laid in reimbursement, in
cement, sand mortar on sides of drains and in
other works where required. All joints to be
completely filled and struck flush.
c) Ratio (1:6)
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -
Page 10
DESCRIPTION OF ITEM NO 4: Pacca flat brick, herring bond pitching in cement,
sand mortar laid to lines, grades, shapes and
slopes as per Engineer's Drawing.
a) Ratio (1:3)
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -
Page 11
Item No. 4 Pacca flat brick, herring bond pitching in cement,
sand mortar laid to lines, grades, shapes and
slopes as per Engineer's Drawing.
b) Ratio (1:5)
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -
Page 12
Item No. 4 Pacca flat brick, herring bond pitching in cement,
sand mortar laid to lines, grades, shapes and
slopes as per Engineer's Drawing.
c) Ratio (1:6)
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -
Page 13
DESCRIPTION OF ITEM NO 5: Pacca brick on edge, herring bond pitching in
cement, sand mortar laid to lines, grades, shapes
and slopes as per Engineer's Drawing.
a) Ratio (1:3)
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -
Page 14
Item No. 5 Pacca brick on edge, herring bond pitching in
cement, sand mortar laid to lines, grades, shapes
and slopes as per Engineer's Drawing.
b) Ratio (1:5)
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -
Page 15
Item No. 5 Pacca brick on edge, herring bond pitching in
cement, sand mortar laid to lines, grades, shapes
and slopes as per Engineer's Drawing.
c) Ratio (1:6)
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.00 Say -
Page 16
DESCRIPTION OF ITEM NO 6: Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades, slopes
and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).
a) Type I
Qty Rate
Per Unit (Rs.) Amount (Rs.)
CC 1:6:12
1x100x5/6'x1/6' 13.89 Cft
Say: 13.90 Cft
CC 1:2:5
1x100x5/6'x11/24' 38.19 Cft
Cement for.
Cement Concrete 1:6:12 0.90 Bag
Cement Concrete 1:2:5 4.78 Bag
" Cement PLaster 1:1 1.03 Bag
6.71 Bag 0.00 Each -
Sand for.
Cement Concrete 1:6:12 6.81 Cft
Cement Concrete 1:2:5 14.95 Cft
" Cement PLaster 1:1 1.29 Cft
23.05 Cft 0.00 P. Cft -
Page 17
a) Type I
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. 0.05 Say 0.05
Labour Rate Per Rm Rs. 0.26 Say 0.25
Page 18
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).
b) Type II
Qty Rate
Per Unit (Rs.) Amount (Rs.)
CC 1:6:12
1x100x(1'-2"+1'-8")x7" 88.10 Cft
2
Deduction.
1x100x(8"+11")x4" 28.77 Cft
2
Net Total 59.33 Cft
CC 1:2:5
1x100x(11"+8")x4" 28.77 Cft
2
1x100x(1-8")x4" 56.94 Cft
Total 85.71 Cft
Deduction.
1x100x0.82 8.20 Cft
1x100(7 3/8"+10") 2 1/8" 17.34 Cft
2
1x100(10"+1"-8")x0.87 4.21 Cft
2
Total 29.75 Cft
85.71 - 29.75 Net Tot 55.96 Cft
Surface Rendering
With Cement Sand Mortar1:1of" thick 220.00 Sft
Material
Cement for.
Cement Concrete 1:6:12 3.84 Bags
Cement Concrete 1:2:5 5.62 Bags
" Cement PLaster 1:1 2.27 Bags
11.73 Bags 0.00 Each -
Sand for.
Cement Concrete 1:6:12 28.86 Cft
Cement Concrete 1:2:5 17.54 Cft
" Cement PLaster 1:1 2.86 Cft
49.26 Cft 0.00 P. Cft -
Page 19
b) Type II
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Page 20
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).
c) Type III
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-3 5/8"+1'-11") 117.33 Cft
2
2'x100'x4"x1" 9.38 Cft
Total 126.71 Cft
Deduction.
1x100x(8"+1'-")x5" 40.93 Cft
2
Net Total 85.78 Cft
CC 1:2:5
1x100(8"+1'-2") 5" 43.92 Cft
2
1x100x1'-11"x4" 63.89 Cft
Total 107.81 Cft
Deduction.
1x100x.082 8.20 Cft
1x100(7-3/8"+1'-")6" 41.40 Cft
2
Surface Rendering.
Surface Area.
1x9.4'x100 78.33 Sft
12
Page 21
c) Type III
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Composite Rate Per Rft Rs. 0.00 Say -
Composite Rate Per Rm Rs. 0.00 Say -
Page 22
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).
d) Type IV
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-3 "+2'-1")x11" 164.73 Cft
2
2x100x4"x1" 9.38 Cft
Total 174.11 Cft
Deduction.
1x100x(8"+1-3")x8" 69.35 Cft
2
Page 23
d) Type IV
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material Required.
Cement for.
Cement for 1:6:12 6.81 Bags
Cement for 1:2:5 8.11 Bags
Cement for Surface rendering 2.98 Bags
17.90 Bags 0.00 Each -
Sand for.
Sand for 1:6:12 51.33 Cft
Sand for 1:2:5 25.33 Cft
Sand for Surface rendering 3.73 Cft
80.39 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 102.66 Cft 0.00 P. Cft -
Stone Bajri for 1:2:5 50.33 Cft 0.00 P. Cft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. -0.05 Say -
Page 24
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).
e) Type V
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-7"+2'-3")x10" 170.44 Cft
2
CC 1:2:5
1x100(8"+1'-6")x1'-1" 120.75 Cft
2
1x100x2'-3"x4" 77.08 Cft
Total 197.83 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7-3/8"+1'-5")x11" 100.48 Cft
2
Page 25
e) Type V
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. -0.02 Say -
Composite Rate Per Rft Rs. 0.00 Say -
Composite Rate Per Rm Rs. 0.00 Say -
Page 26
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).
f) Type VI
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-7"+2'-6")x1-1" 230.25 Cft
2
2x100x(6"x4")5" 42.01 Cft
2
Total 272.26 Cft
Deduction.
1x100x(8"+1-5 1/8")x10" 91.58 Cft
2
Net Total 180.68 Cft
CC 1:2:5
1x100(8"+1'-9 1/8")x1'-4" 161.81 Cft
2
1x100x2'-6-1/8"x4" 83.68 Cft
Total 245.49 Cft
Deduction.
1x100(7'-3/8"+1'-7 5/8")x1'-2" 138.28 Cft
2
1x100(1'-7 5/8"+2'-6 1/8")x0.75" 12.96 Cft
2
1x100x0.082 8.20 Cft
Total 159.44 Cft
45.49 - 159.44 Net Total 86.05 Cft
Surface Rendering.
1x9.4x100 78.33 Sft
12
2x5"x100 87.50 Sft
12
2x1'-4/12"x100 266.66 Sft
Total 432.49 Sft
Say: 432.50 Sft
Page 27
f) Type VI
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material Required.
Cement for.
Cement for 1:6:12 11.74 Bags
Cement for 1:2:5 12.48 Bags
Cement for Surface rendering 3.98 Bags
28.20 Bags 0.00 Each -
Sand for.
Sand for 1:6:12 88.53 Cft
Sand for 1:2:5 38.98 Cft
Sand for Surface rendering 4.97 Cft
132.48 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 177.07 Cft 0.00 P. Cft -
Stone Bajri for 1:2:5 77.45 Cft 0.00 P. Cft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Page 28
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).
g) Type VII
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-7"+2'-8")x1-4 3/8" 292.82 Cft
2
2x100x(6"x4")5" 40.10 Cft
2
Total 332.92 Cft
Deduction.
1x100x(8"+9'-7")1'-1 3/8" 127.71 Cft
2
Net Total 205.21 Cft
CC 1:2:5
1x100(8"+1'-11")1'-6.5/8" 203.71 Cft
2
1x100x2'-8"x4" 90.28 Cft
Total 293.99 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7 3/9"+1'-10")1'-5" 178.52 Cft
2
1x100(1'-10"+2'-8")x7/8" 16.56 Cft
2
Total 203.28 Cft
93.99 - 203.28 Net Total 90.71 Cft
Page 29
g) Type VII
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Item Rates
Labour Rate Per Rft Rs. -0.01 Say -
Labour Rate Per Rm Rs. -0.01 Say -
Composite Rate Per Rft Rs. -0.01 Say -
Composite Rate Per Rm Rs. -0.03 Say -
Page 30
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).
h) Type VIII
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-7"+2'-10 7/8")1' 7" 355.43 Cft
2x100x(6"+4")5" 40.10 Cft
2
Total 395.53 Cft
Deduction.
1x100x(8"+1'-9 7/8")1'-4" 165.97 Cft
2
Net Total 229.56 Cft
CC 1:2:5
1x100(8"+2-1 7/8")1'-9" 249.95 Cft
2
1x100(2'-10 7/8")4" 96.88 Cft
Total 346.83 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7 3/8"+2'-3/8")1'-8" 223.42 Cft
2
1x100(2'-3/8"+2'-10 7/8")x" 15.43 Cft
2
Total 247.05 Cft
6.83 - 247.05 Net Total 99.78 Cft
Page 31
h) Type VIII
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Cement for.
Cement for 1:6:12 14.92 Bags
Cement for 1:2:5 14.50 Bags
Cement for Surface rendering 4.98 Bags
34.40 Bags 0.00 Each -
Sand for.
Sand for 1:6:12 112.48 Cft
Sand for 1:2:5 45.30 Cft
Sand for Surface rendering 6.22 Cft
164.00 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 250.00 Cft 0.00 P. Cft -
Stone Bajri for 1:2:5 90.00 Cft 0.00 P. Cft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Composite Rate Per Rft Rs. 0.00 Say -
Composite Rate Per Rm Rs. 0.00 Say -
Page 32
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).
i) Type IX
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-10 3/8"+3'-3")x1'-8" 427.99 Cft
2
Page 33
i) Type IX
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Composite Rate Per Rft Rs. 0.00 Say -
Composite Rate Per Rm Rs. 0.00 Say -
Page 34
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).
j) Type X
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-10"+3'-5")x1'-10" 503.91 Cft
2
Deduction.
1x100x(9"+2'-1")1'-6" 226.43 Cft
2
Net Total 359.95 Cft
CC 1:2:5
1x100(9"+2'-8")2'-4" 410.76 Cft
2
1x100x3'-5"4" 130.47 Cft
Total 541.23 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7' 3/8"+2'-5")2'-2" 333.86 Cft
1x100(2'-5"+3'-5")x" 18.43 Cft
2
Total 360.49 Cft
23 - 360.49 Net Total 180.74 Cft
Page 35
j) Type X
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material Required.
Cement for.
Cement for 1:6:12 23.40 Bags
Cement for 1:2:5 26.20 Bags
Cement for Surface rendering 5.70 Bags
55.30 Bags 0.00 Each -
Sand for.
Sand for 1:6:12 176.37 Cft
Sand for 1:2:5 81.85 Cft
Sand for Surface rendering 7.13 Cft
265.35 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 352.75 Cft 0.00 P. Cft -
Stone Bajri for 1:2:5 162.61 Cft 0.00 P. Cft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Composite Rate Per Rft Rs. 0.00 Say -
Composite Rate Per Rm Rs. 0.00 Say -
Page 36
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).
k) Type XI
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-10"+3'-8")x2'-1 3/8" 599.05 Cft
2
2x100x(8"+4")9" 82.47 Cft
2
Total 681.52 Cft
Deduction.
1x100x(9"+2'-4")1'-9" 285.09 Cft
2
Net Total 396.43 Cft
CC 1:2:5
1x100(9"+2'-11")2'-7" 490.99 Cft
1x100x3'-8"x4" 138.28 Cft
Total 629.27 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7' 3/8"+2'-7")2'-5" 400.71 Cft
2
1x100(2'-7"+3'-8")x" 19.79 Cft
2
Total 428.70 Cft
.27 - 428.70 Net Total 200.57 Cft
Page 37
k) Type XI
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material Required.
Cement for.
Cement for 1:6:12 25.77 Bags
Cement for 1:2:5 29.08 Bags
Cement for Surface rendering 6.55 Bags
61.40 Bags 0.00 Each -
Sand for.
Sand for 1:6:12 194.25 Cft
Sand for 1:2:5 91.12 Cft
Sand for Surface rendering 8.18 Cft
293.55 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 388.50 Cft 0.00 P. Cft -
Stone Bajri for 1:2:5 180.51 Cft 0.00 P. Cft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Page 38
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar "(6mm)
thick as per Engineers Drawing (excluding
Excavation).
l) Type XII
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-10"+3'-10")x2'-4" 681.72 Cft
2
CC 1:2:5
1x100(9"+3'-1")2'-10" 557.81 Cft
1x100x3'-10"x4" 146.09 Cft
Total 703.90 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7' 3/8"+2'-10")2'-8" 466.17 Cft
2
Page 39
l) Type XII
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material Required.
Cement for.
Cement for 1:6:12 27.78 Bags
Cement for 1:2:5 30.15 Bags
Cement for Surface rendering 7.05 Bags
64.98 Bags 0.00 Each -
Sand for.
Sand for 1:6:12 209.45 Cft
Sand for 1:2:5 94.19 Cft
Sand for Surface rendering 7.05 Cft
310.69 Cft 0.00 P. Cft -
Brick ballast for 1:6:12 418.90 Cft 0.00 P. Cft -
Stone Bajri for 1:2:5 187.12 Cft 0.00 P. Cft -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Page 40
DESCRIPTION OF ITEM NO 7: Laying RC hume pipes in positions, including
jointing.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Page 41
Item No. 7 Laying RC hume pipes in positions, including
jointing.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Page 42
Item No. 7 Laying RC hume pipes in positions, including
jointing.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. 0.00 Say -
Labour Rate Per Rm Rs. 0.00 Say -
Page 43
CHAPTER NO. 12
WOOD WORK
DESCRIPTION OF ITEM NO. 1: Plain wood work sawn wrought planed & fixed
in position including cost of nails & screw
a) Deodar Wood.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Deodar Wood including wastage (II Class) 1.15 Cft 0.00 P. Cft -
Nail 0.020 Kg. 0.00 P. Cft -
Screws above 1" long 1.00 Dozen 0.00 P.Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Cft Rs. 0.01 Say -
Labour Rate Per Cum Rs. 0.23 Say 0.25
Page 1
Item No. 1 Plain wood work sawn wrought planed & fixed
in position including cost of nails & screw
b) Shisham Wood
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Cft Rs. - Say -
Labour Rate Per Cum Rs. 0.10 Say 0.10
Page 2
DESCRIPTION OF ITEM NO. 2: Plain wood work for regulation karries or
needles etc. including sawing plaining
wroughting wood providing & fixing steel pa
of karries i.e. end strips and rods etc.
a) Deodar Wood.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
i) Deodar Wood
5.5x5/12x5/12 = 0.97 0.97 Cft
Wastage 15% 0.15 Cft
1.12 Cft 0.00 P. Cft -
ii)1.6' (480mm) long iron strip 1"
(37mm) wide x1/8" (3mm) thick @
0.625 Lbs/ft. (0.930 Kg/Mtr). 2.00 Lbs
2 Nox1' (380mm) long iron bars
" (20mm) on both ends @ 1.502
Lbs/ft. (2.235 Kg/m). 3.80 Lbs
5.80 Lbs
Wastage 5% 0.29 Lbs
6.09Lb (2 .76)Kg 0.00 P. Kg -
iii) Iron Screw 1" (25mm) long 1.00 Dozen 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Page 3
Detail Unit Rate (British System) per Cft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Cft Rs. - Say -
Labour Rate Per Cum Rs. 0.12 Say 0.10
Page 4
Item No. 2 Plain wood work for regulation karries or n
etc. including sawing plaining wroughting w
providing & fixing steel parts of karries i
strips and rods etc.
b) Shisham Wood
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
i) Shisham Wood
5.5x5/12x5/12 = 0.97 0.97 Cft
Wastage 15% 0.15 Cft
1.12 Cft 0.00 P. Cft -
ii)Iron Strip
1.6' (480mm) long iron strip 1"
(37mm) wide x1/8" (3mm) thick @
0.625 Lbs/ft. (0.930 Kg/Mtr). 2.00 Lbs
2 Nox1' (380mm) long iron bars
" (20mm) on both ends @ 1.502
Lbs/ft. (2.235 Kg/m). 3.80 Lbs
5.80 Lbs
Wastage 5% 0.29 Lbs
6.09Lb (2 .76)Kg 0.00 P. Kg -
iii) Iron Screw 1" (25mm) long 1.00 Dozen 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Page 5
Detail Unit Rate (British System) per Cft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Cft Rs. - Say -
Labour Rate Per Cum Rs. 0.12 Say 0.10
Page 6
DESCRIPTION OF ITEM NO 3: First class teak wood wrought joinery in do
windows etc. panelled, panelled and glazed
glazed & fixed in position including chowkh
fast tower bolts, chocks rubber stop, cleat
clamps, chords with hooks, nails screws etc
complete (Excluding sliding bolt and lock).
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Teak Wood
Frame
Top Rail 4'x3"x4" 0.45 Cft
Vertical 2x7'x3"x4" 1.33 Cft
Vertical Style 4x6'-6"x4"x2" 1.46 Cft
Horizental Rail 2x1'-10"x4"x2" 0.20 Cft
Middle Rail 2x1'-10"x6"x2" 0.20 Cft
Lock Rail 2x1'-10"x6"x2" 0.31 Cft
Bottom Rail 2x1'-10"x8"x2" 0.42 Cft
Panells
2x14"x22"x" 0.27 Cft
4x14"x18.5"x" 0.45 Cft
Beading
2(14"+14"+22"+22")x5/8"
(1 + 2) 0.02 Cft
2x8
4(14"+14"+18"+18")5/8"
(1 + 2) 0.02 Cft
2x8
5.13 Cft
Wastage 12% 0.62 Cft
5.75 Cft 0.00 P. Cft -
Page 7
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Fitting
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Labour
Total -
Sundries 10 Percent -
Total -
Page 8
Item No. 3 First class teak wood wrought joinery in do
windows etc. panelled, panelled and glazed
glazed & fixed in position including chowkh
hold fast tower bolts, chocks rubber stop,
G.I. clamps, chords with hooks, nails screw
complete (Excluding sliding bolt and lock).
ii) 1" (45mm) Thick.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Teak Wood
Frame
Top Rail 4'x3"x4" 0.45 Cft
Vertical 2x7'x3"x4" 1.33 Cft
Vertical Style 4x6'-6"x4"x1" 1.25 Cft
Horizontal Rail
Top 2x1'-10"x4"x1" 0.18 Cft
Middle 2x1'-10"x4"x1" 0.18 Cft
Lock 2x1'-10"x6"x1" 0.27 Cft
Bottom 2x1'-10"x8"x1" 0.36 Cft
Panels
2x14"x22"x" 0.27 Cft
4x14"x18.5"x" 0.44 Cft
Beading
2(14"x14"x22"+22")x5/8"
(1 + 2) 0.01 Cft
2x8
4(14"+14"+18.5"+18.5")5/8"
(1 + 2) 0.02 Cft
2x8
4.76 Cft
Wastage 12% 0.57 Cft
5.33 Cft 0.00 P. Cft -
Page 9
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Fitting 7,462.00
Total 7,462.00
Contractor's Profit & Ove 20 Percent 1,492.40
Total for 27 Sft. 8,954.40
Total -
Sundries 10 Percent -
Total -
Page 10
Item No. 3 First class teak wood wrought joinery in do
windows etc. panelled, panelled and glazed
glazed & fixed in position including chowkh
hold fast tower bolts, chocks rubber stop,
G.I. clamps, chords with hooks, nails screw
complete (Excluding sliding bolt and lock).
iii) 1" (37mm) Thick.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Leaves
Top Rail 2x1'-10"x4"x1" 0.15 Cft
Middle 2x1'-10"x4"x1" 0.15 Cft
Lock 2x1'-10"x6"x1" 0.23 Cft
Bottom 1x1'-10"x8"x1" 0.30 Cft
Panels
2x14"x22"x5/8" 0.23 Cft
4x14"x18.5"x5/8" 0.44 Cft
Beading
2(14"x14"x22"+22")x5/8"
(1 + 2) 0.01 Cft
2x8
4(14"+14"+18.5"+18.5")5/8"
(1 + 2) 0.02 Cft
2x8
4.39 Cft
Wastage 12% 0.53 Cft
4.92 Cft 0.00 P. Cft -
Page 11
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
6,888.00
Fitting
Hinges 4" (100mm) 8.00 Nos 0.00 Each -
Tower Bolts 9" (225mm) 3.00 Nos 0.00 Each -
Handles 6" (150mm) 3.00 Nos 0.00 Each -
Iron Hold Fast 6.00 Nos 0.00 Each -
Rubber Pad 2.00 Nos 0.00 Each -
Hook & Clamps 2.00 Nos 0.00 Each -
Screws above 1" long 2.50 Doz 0.00 P. Doz -
Glue 0.05 Kg. 0.00 P. Kg. -
Spikes 0.20 Kg. 0.00 P. Kg. -
Total 6,888.00
Contractor's Profit & Ove 20 Percent 1,377.60
Total for 27 Sft. 8,265.60
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 12
DESCRIPTION OF ITEM NO 4: First class teak wood wrought joinery in wi
gauze doors & windows with frames 22 SWG
galvanized iron wire gauze 12x12 meshes to
square inchs (625mm) including brass fittin
bars etc. complete :
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Teak Wood
Top Rail 1x4'x3"x" 0.04 Cft
Vertical 2x7'x3"x" 0.15 Cft
Fillet 2(15"+15"+25"+25")1"x3/8" 0.02 Cft
Fillet 2(15"+15"+19"+19")x"x3/8" 0.03 Cft
Leaf
Vertical Style 4x6'-6"x4"x1" 1.27 Cft
Horizontal
Top 2x1'-10"x1"x1" 0.06 Cft
Middle 2x1'-10"x3"x1" 0.07 Cft
Lock 2x1'-10"x6"x1" 0.27 Cft
Bottom 2x1'-10"x6"x1" 0.27 Cft
2.18 Cft
Wastage 10% 0.22 Cft
2.40 Cft 0.00 P. Cft -
Page 13
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Fitting 3,360.00
Wire Gauze
2x1'-2"x2'-1" 4.83 Sft
4x1'-2"x1'-7" 7.33 Sft
12.16 Sft
Wastage 15% 1.82 Sft
13.98 Sft 0.00 Sft -
Total 3,360.00
Contractor's Profit & Ove 20 Percent 672.00
Total for 27 Sft 4,032.00
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft -
Rate Per Sft 0.00 = -
27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 14
DESCRIPTION OF ITEM NO 4: First class teak wood wrought joinery in wi
gauze doors & windows with frames 22 SWG
galvanized iron wire gauze 12x12 meshes to
square inch (625mm) including brass fitting
bars etc. complete :
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Teak Wood
Top Rail 1x4'x3"x" 0.04 Cft
Vertical 2x7'x3"x" 0.15 Cft
Fillet 2(15"+15"+25"+25")1"x3/8" 0.02 Cft
Fillet 2(15"+15"+19"+19")1"x3/8" 0.03 Cft
Leaf
Vertical Style = 4'x6'-6"x4"x1" 1.27 Cft
Horizontal
Top 2x1'-10"x1"x1" 0.06 Cft
Middle 2x1'-10"x3"x1" 0.07 Cft
Lock 2x1'-10"x6"x1" 0.27 Cft
Bottom 2x1'-10"x6"x1" 0.27 Cft
2.18 Cft
Wastage 10% 0.22 Cft
2.40 Cft 0.00 P. Cft -
Page 15
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Tower Bolts 9" (225mm) 2.00 Nos 0.00 Each -
Handles 6" (150mm) 2.00 Nos 0.00 Each -
Hook & Clamps 2.00 Nos 0.00 Each -
Screws / Nail 2.00 Doz 0.00 P. Doz -
Spring Hings 2.00 Nos 0.00 Each -
Wire Gauze
2x1'-2"x2'-1" = 4.83 Sft
4x1'-2"x1'-7" = 7.33 Sft
12.16 Sft
Wastage 10% 1.22 Sft
13.38 Sft 0.00 Sft -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. 3,986.80
Rate Per Sft 3986.80 = 147.66
27
Labour
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Rate Per Sft 0.00 = -
27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 16
Item No. 4 First class teak wood wrought joinery in wi
gauze doors & windows with frames 22 SWG
galvanized iron wire gauze 12x12 meshes to
square inch (625mm) including brass fitting
bars etc. complete:
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Horizontal
Top Rail 2x1-10"x3"x1" 0.12 Cft
Middle 2x1-10"x1"x1" 0.06 Cft
Lock 2x1'-10"x6"x1" 0.24 Cft
Bottom 2x1'-10"x6"x1" 0.24 Cft
Fillet 2(15"+15"+25"+25")"x3/8" 0.02 Cft
Fillet 2(15"+15"+19"+19")"x3/8" 0.03 Cft
Top Rail 1x4'x3"x" 0.05 Cft
Vertical Rail 2x7'x3"x" 0.15 Cft
2.00 Cft
Wastage 10% 0.20 Cft
2.20 Cft 0.00 P. Cft -
Fitting
Hinges 4" (100mm) 6 Nos 0.00 Each -
Tower Bolts 9" (225mm) 2 Nos 0.00 Each -
Handles 6" (150mm) 2 Nos 0.00 Each -
Hook & Clamps 2 Nos 0.00 Each -
Screws / Nail 2 Doz 0.00 P. Doz -
Page 17
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Wire Gauze
2x1'-2"x2'-1" 4.83 Sft
4x1'-2"x1'-7" 7.33 Sft
12.16 Sft
Wastage 15% 1.82 Sft
13.98 Sft 0.00 Sft -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Total -
Sundries 10 Percent -
Total -
Page 18
Item No. 4 First class teak wood wrought joinery in wi
gauze doors & windows with frames 22 SWG
galvanized iron wire gauze 12x12 meshes to
square inch (625mm) including brass fitting
bars etc. complete:
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Ist Class Teak Wood
Vertical Style 4x6-6"x4"x1" 1.09 Cft
Horizontal
Top Rail 2x1'-10"x3"x1" 0.12 Cft
Middle 2x1'-10"x1"x1" 0.06 Cft
Lock 2x1'-10"x6"x1" 0.24 Cft
Bottom 2x1'-10"x6"x1" 0.24 Cft
Fillet 2(15"+15"+25"+25")"x3/8" 0.02 Cft
Fillet 2(15"+15"+19"+19")"x3/8" 0.03 Cft
Top Rail 1x4'x3"x" 0.05 Cft
Vertical Rail 2x7'x3"x" 0.15 Cft
2.00 Cft
Wastage 10% 0.20 Cft
2.20 Cft 0.00 P. Cft -
Fitting
Hinges 4" (100mm) 6 Nos 0.00 Each -
Tower Bolts 9" (225mm) 2 Nos 0.00 Each -
Handles 6" (150mm) 2 Nos 0.00 Each -
Hook & Clamps 2 Nos 0.00 Each -
Screws / Nail 2 Doz 0.00 Doz -
Spring hings 2 Nos 0.00 Each -
Page 19
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Wire Gauze
2x1'-2"x2'-1" 4.83 Sft
4x1'-2"x1'-7" 7.33 Sft
12.16 Sft
Wastage 15% 1.82 Sft
13.98 Sft 0.00 Sft -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Total -
Sundries 10 Percent -
Total -
Page 20
Item No. 4 First class teak wood wrought joinery in wi
gauze doors & windows with frames 22 SWG
galvanized iron wire gauze 12x12 meshes to
square inch (625mm) including brass fitting
bars etc. complete:
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3' x 4' = 12 Sft
Material
Teak Wood
Horizontal Strips 2x3'x3"x" 0.09 Cft
Vertital Strips 2x3.5'x3"x" 0.11 Cft
0.2 Cft
Wastage 15% 0.03 Cft
0.23 Cft 0.00 P. Cft -
Wire gauze = 1x3x4 12 Sft
Wastage 10% 1.2 Sft
13.20 Sft 0.00 Sft -
Fitting
Screws above 1" long 2.00 Doz 0.00 Doz 5.28
Nail 0.07 Kg. 0.00 P. Kg. -
Total 5.28
Contractor's Profit & Ove 20 Percent 1.06
Total for 12 Sft. 6.34
Page 21
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 12 Sft. -
Page 22
Item No. 4 First class teak wood wrought joinery in wi
gauze doors & windows with frames 22 SWG
galvanized iron wire gauze 12x12 meshes to
square inch (625mm) including brass fitting
bars etc. complete:
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 2' = 8 Sft
Material
Teak Wood
Horizontal Rail 2x4'x2"x2" 0.22 Cft
Vertital Rail 2x2'x2"x2" 0.11 Cft
Strip Rail 2x4'x2"x2" 0.05 Cft
Strips Rail 2x1 2/3'x2"x2" 0.03 Cft
Moulding 0.15 Cft
0.56 Cft
Wastage 15% 0.09 Cft
0.65 Cft 0.00 P. Cft -
Total 3.00
Contractor's Profit & Ove 20 Percent 0.60
Total for 8 Sft 3.60
Page 23
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Page 24
DESCRIPTION OF ITEM NO 5: Providing and fixing expanded metal " to
(12mm to 20mm) mesh 16 gauze fixed to
chowkhat with 1" (25mm) teak wood strips an
screws etc. complete.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 2' = 8 Sft
Material
Teak Wood
Cover moulding/ Strips.
2x2'x1/12'x3/12' 0.08 Cft
2x3x10/12'x1/12'x3/12' 0.16 Cft
0.24 Cft
Wastage 15% 0.04 Cft
0.28 Cft 0.00 P. Cft -
Expended Metal
4'x2' 8.00 Sft
Wastage 5% 0.40 Sft
8.40 Sft 0.00 Sft -
Nail and Screw 2.00 Doz 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 8 Sft. -
Rate Per Sft 0.00 = -
8
Labour
Carpenters 0.25 No 0.00 P. Day -
Skilled Cooly 0.25 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 8 Sft. -
Rate Per Sft 0.00 = -
8
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 25
DESCRIPTION OF ITEM NO 6: Providing and fixing expanded metal " to
(12mm to 20mm) mesh 16 gauze fixed to chowk
with 1" (25mm) cover moulding & screws
including teak wood frame 2"x2" (50x50mm).
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 3' = 12 Sft
Material
Teak Wood Frame
2Nox4'x2"x2" 0.23 Cft
2Nox3'x2"x2" 0.17 Cft
Moulding 13 2/3x1/12x2/12 0.20 Cft
0.60 Cft
Wastage 15% 0.09 Cft
0.69 Cft 0.00 P. Cft -
Expanded Metal
1'x4'x3' 12.00 Sft
Wastage 5% 0.60 Sft
12.60 Sft 0.00 Sft -
Nail and Screw L.S. 8.00
Total 8.00
Contractor's Profit & Ove 20 Percent 1.60
Total for 12 Sft. 9.60
Rate Per Sft 9.60
12 = 0.80
Labour
Carpenters 0.50 No 0.00 P. Day -
Skilled Cooly 0.25 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 12 Sft. 0.01
Rate Per Sft 0.01 = 0.00
12
Item Rates
Labour Rate Per Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. 0.01 Say -
Page 26
DESCRIPTION OF ITEM NO 7: First class deodar wood wrought joinery in
windows etc. panelled or panelled or glazed
glazed fixed in position including chowkhat
fast, hinges, tower bolt rubber stop cleats
handles and chord with hooks etc. complete
(excluding sliding bolts or lock)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Panells
2'x14"x22"x" 0.27 Cft
4'x14"x18.5"x" 0.45 Cft
Beading
2(14"+14"+22"+22")5/8"(1"+2") 0.02 Cft
2x8
4(14"+18.5"+18.5")5/8"(1"+2") 0.02 Cft
2x8
5.13 Cft
Wastage 15% 0.77 Cft
5.90 Cft 0.00 P. Cft -
Page 27
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Fitting
Hinges 4" (100mm) 8.00 Nos 0.00 Each -
Tower Bolts 9" (225mm) 3.00 Nos 0.00 Each -
Handles 6" (150mm) 3.00 Nos 0.00 Each -
Iron Hold Fast 6.00 Nos 0.00 Each -
Rubber Pad 2.00 Nos 0.00 Each -
Hook & Clamps 2.00 Nos 0.00 Each -
Screws / Nail 2.50 Doz 0.00 Doz -
Glue 0.05 Kg. 0.00 P. Kg. -
Spikes 0.20 Kg. 0.00 P. Kg. -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour
Total -
Sundries 10 Percent -
Total -
Page 28
Item No. 7 First class deodar wood wrought joinery in
windows etc. panelled or panelled or glazed
glazed fixed in position including chowkhat
fast, hinges, tower bolt rubber stop cleats
handles and chord with hooks etc. complete
(excluding sliding bolts or lock)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Horizontal Rail
Top 2x1'-10"x4"x1" 0.18 Cft
Middle 2x1'-10"x4"x1" 0.18 Cft
Lock 2x1'-10"x6"x1" 0.27 Cft
Bottom 2x1'-10"x8"x1" 0.36 Cft
Panells
2'x14"x22"x" 0.27 Cft
4'x14"x18.5"x" 0.44 Cft
Beadings
2(14"+14"+22"+22")5/8" (1"+2") 0.01 Cft
2x8
4(14"+14"+18.5"+18.5")5/8"(1"+2") 0.02 Cft
2x8
4.76 Cft
Wastage 15% 0.71 Cft
5.47 Cft 0.00 P. Cft -
Page 29
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Fitting
Hinges 4" (100mm) 8.00 Nos 0.00 Each -
Tower Bolts 9" (225mm) 3.00 Nos 0.00 Each -
Handles 6" (150mm) 3.00 Nos 0.00 Each -
Iron Hold Fast 6.00 Nos 0.00 Each -
Rubber Pad 2.00 Nos 0.00 Each -
Hook & Clamps 2.00 Nos 0.00 Each -
Screws / Nail 2.50 Doz 0.00 Doz -
Glue 0.05 Kg. 0.00 P. Kg. -
Spikes 0.20 Kg. 0.00 P. Kg. -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. 0.01
Rate Per Sft 0.01 = 0.00
27
Item Rates
Labour Rate Per Sft Rs. 0.00 Say -
Labour Rate Per Sqm Rs. ##### Say -
Page 30
Item No. 7 First class deodar wood wrought joinery in
windows etc. panelled or panelled or glazed
glazed fixed in position including chowkhat
fast, hinges, tower bolt rubber stop cleats
handles and chord with hooks etc. complete
(excluding sliding bolts or lock)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Top Rail 1x4x3"x4" 0.45 Cft
Vertical Rail 2x7x3"x4" 1.33 Cft
Vertical Style 4x6'-6"x4"x1" 1.20 Cft
Horizontal Rail
Top 2x1'-10"x4"x1" 0.15 Cft
Middle 2x1'-10"x4"x1" 0.15 Cft
Lock 2x1'-10"x6"x1" 0.23 Cft
Bottom 2x1'-10"x8"x1" 0.30 Cft
Panells
2'x14"x22"x"x5/8" 0.22 Cft
4'x14"x18.5"x5/8" 0.44 Cft
Beadings
2(14"+14"+22"+22")5/8"(1"+2") 0.01 Cft
2x8
4(14"+14"+18.5"+18.5")5/8"(1"+2") 0.02 Cft
2x8
4.50 Cft
Wastage 15% 0.68 Cft
5.18 Cft 0.00 P. Cft -
Page 31
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Tower Bolts 9" (225mm) 3.00 Nos 0.00 Each -
Handles 6" (150mm) 3.00 Nos 0.00 Each -
Iron Hold Fast 6.00 Nos 0.00 Each -
Rubber Pad 2.00 Nos 0.00 Each -
Hook & Clamps 2.00 Nos 0.00 Each -
Screws / Nail 2.50 Doz 0.00 Doz -
Glue 0.05 Kg. 0.00 P. Kg. -
Spibes 0.20 Kg. 0.00 P. Kg. -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour
Total -
Sundries 10 Percent -
Total -
Page 32
DESCRIPTION OF ITEM NO 8: Deodar wood framed braced and battened door
windows complete with iron fitting & fixed
position including chowkhat.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3' x 7' = 21 Sft
Material
Deodar Wood
Top Rail 1x3x3"x4" 0.35 Cft
Vertical Rail 2x7"x3"x4" 1.36 Cft
Leaf
Plank 1x2 2/12x6 17/24x1/12 1.44 Cft
Battens 3x2x1/3'x3/8'x5/8' 0.27 Cft
Braces 2x3 47/48x3/8x5/8 0.31 Cft
3.73 Cft
Wastage 15% 0.56 Cft
4.29 Cft 0.00 P. Cft -
Fitting
Hinges 10" (250mm) 3.00 Nos 0.00 Each -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 21 Sft. -
Page 33
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Page 34
Item No. 8 Deodar wood framed braced and battened door
windows complete with iron fitting & fixed
position including chowkhat.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3' x 6.5' = 19.5 Sft
Material
Deodar Wood
Top Rail 1x3'x'x3/8 0.35 Cft
Vertical Rail 2x6'xx3/8 1.17 Cft
Leaf Plank 1x2 7/12x6 5/24x 1/16 1.00 Cft
Ledges 2x3 13/20x1/3x1/12 0.20 Cft
Braces 2x3 13/20x1/3x1/12 0.20 Cft
2.92 Cft
Wastage 15% 0.44 Cft
3.36 Cft 0.00 P. Cft -
Fitting
Hinges 5" (125mm) 3.00 Nos 0.00 Each -
Tower Bolts 9" (225mm) 3.00 Nos 0.00 Each -
Wrought Iron hold fast 4.00 Nos 0.00 Each -
Hinges chocks 4" (100mm) 1.00 No 0.00 Each -
Door stops 6" (150mm) 1.00 No 0.00 Each -
Handles 6" (150mm) 2.00 Nos 0.00 Each -
Screws above 1" long 2.00 Doz 0.00 P. Doz -
Nails of sorts 0.06 Kg 0.00 P. Kg -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 19.5 Sft. -
Page 35
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Page 36
DESCRIPTION OF ITEM NO 9: 1" (25mm) thick battened doors and windows
in position complete with iron fittings wit
chowkhat.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 100 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
100
Labour
Total -
Sundries 10 Percent -
Total -
Page 37
DESCRIPTION OF ITEM NO 10: Deodar battened ledged & braced doors and
windows 2" (56mm) thick (1" (30mm) thick
ledge braces and 1" thick battens complete
iron fittings chowkhats and fixed in positi
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3' x 6.5' = 19.5 Sft
Material
Deodar Wood
Chowkhat 2x6'x3"x4" 1.30 Cft
1x3"x3"x4" 0.19 Cft
Leaf Batten 1x2'-7"x6"-3"x1/12 1.35 Cft
Styles 3x2'-5"x4"-1" 0.26 Cft
Braces 2x3.0"x4"x1" 0.20 Cft
3.30 Cft
Wastage 15% 0.50 Cft
3.80 Cft 0.00 P. Cft -
Fitting
Hinges Chocks 4" (100mm) 1.00 No 0.00 Each -
Door Stop 6" (150mm) 1.00 No 0.00 Each -
Tower Bolts 9" (225mm) 2.00 Nos 0.00 Each -
Tower Hinges 8" (200mm) 2.00 Nos 0.00 Each -
Wrought Iron hold fast 4.00 Nos 0.00 Each -
Hasp and staple 1.00 No 0.00 Each -
Handles 2.00 Nos 0.00 Each -
Screws above 1' long 2.00 Doz 0.00 P. Doz -
Nails of sorts 0.13 Kg 0.00 P. Kg -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 19.5 Sft 2,237.69
Page 38
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Carpenters 2.50 Nos 0.00 P. Day -
Skilled Cooly 1.00 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Page 39
DESCRIPTION OF ITEM NO 11: a Deodar wood framed with braces and 22 SWG
G.I. Sheet facing including hold fast, wood
beading, hinges and locking arrangement, as
Directed by the Engineer Incharge.
i) G.I. Sheet facing one side
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 8' x 8' = 64 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 64 Sft. -
Rate Per Sft 0.00 = -
64
Labour
Carpenters 3.50 Nos 0.00 P. Day -
Skilled Cooly 1.50 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 64 Sft. -
Rate Per Sft 0.00 = -
64.0
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 40
DESCRIPTION OF ITEM NO 11: a Deodar wood framed with braces and 22 SWG
G.I. Sheet facing including hold fast, wood
beading, hinges and locking arrangement, as
Directed by the Engineer Incharge.
ii) G.I. Sheet facing on both side.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 8' x 8' = 64 Sft
Material
Deodar Wood 7.00 Cft 0.00 P. Cft -
22 gauge G.I. Plain sheet 128.00 Sft
Wastage 10% 12.80 Sft
140.80 Sft 0.00 Sft -
Hold fast with pivots & clamp 6.00 Nos 0.00 Each -
Screws above 1" long 3.00 Doz 0.00 P. Doz -
Sliding bolts 1" (450 mm) long 1.00 No 0.00 Each -
Nails 0.47 Kg 0.00 P. Kg -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 64 Sft. -
Rate Per Sft 0.00 = -
64
Labour
Carpenters 4.00 Nos 0.00 P. Day -
Skilled Cooly 1.50 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Page 41
Item No. 11 Partal wood frame with braces & 22 SWG G.I.
Sheet facing including hold fast wooden bea
hinges and locking arrangement as directed
Engineering incharge.
i) G.I. Sheet facing one side
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 8' x 8' = 64 Sft
Material
Partal Wood 7.00 Cft 0.00 P. Cft -
22 gauge G.I. Plain sheet 64.00 Sft
Wastage 10% 6.40 Sft
70.40 Sft 0.00 Sft -
Hold fast with pivots & clamp 6.00 Nos 0.00 Each -
Screws above 1" long 3.00 Doz 0.00 P. Doz -
Sliding bolts 1" (450 mm) long 1.00 No 0.00 Each -
Nails 0.23 Kg 0.00 P. Kg -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 64 Sft. -
Rate Per Sft 0.00 = -
64
Labour
Carpenters 3.50 Nos 0.00 P. Day -
Skilled Cooly 1.50 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Page 42
Item No. 11 Partal wood frame with braces & 22 SWG G.I.
Sheet facing including hold fast wooden bea
hinges and locking arrangement as directed
Engineering incharge.
ii) G.I. Sheet facing on both side
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Anaylsis for 8' x 8' = 64 Sft
Material
Partal Wood 7.00 Cft 0.00 P. Cft -
22 gauge G.I. Plain sheet 128.00 Sft
Wastage 10% 12.80 Sft
140.80 Sft 0.00 Sft -
Hold fast with pivots & clamp 6.00 Nos 0.00 Each -
Screws above 1" long 3.00 Doz 0.00 P. Doz -
Sliding bolts 18" (450 mm) long 1.00 No 0.00 Each -
Nails 0.47 Kg 0.00 P. Kg -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 64 Sft. -
Rate Per Sft 0.00 = -
64
Labour
Carpenters 4.00 Nos 0.00 P. Day -
Skilled Cooly 1.50 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Page 43
DESCRIPTION OF ITEM NO 12: First class deodar wood wrought joinery wor
wire gauze doors and windows with 22 SWG
galvanized wire gauze 12x12 mashes per squa
inch (625mm) including iron fittings comple
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Vertical Style
4x6'-6"x4"x1 1.27 Cft
Horizontal
Top 2x1'-10"x3"x1" 0.07 Cft
Middle 2x1'-10"x1"x1" 0.06 Cft
Lock 2x1'-10"x6"x1" 0.27 Cft
Bottom 2x1'-10"x6"x1" 0.27 Cft
2.18 Cft
Wastage 10% 0.22 Cft
2.40 Cft 0.00 P. Cft -
Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Tower Bolts 9" (225mm) 2.00 Nos 0.00 Each -
Handles 6" 2.00 Nos 0.00 Each -
Hook & Clamp 2.00 Nos 0.00 Each -
Screws / Nails 2.00 Doz 0.00 P. Doz -
Page 44
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Wire Gauge
2x1'-2"x2'-1" 4.83 Sft
4x1'-2"x1'-7" 7.33 Sft
12.16 Sft
Wastage 15% 1.82 Sft
13.98 Sft 0.00 Sft -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour
Total -
Sundries 10 Percent -
Total -
Page 45
Item No. 12 First class deodar wood wrought joinery wor
wire gauze doors and windows with 22 SWG
galvanized wire gauze 12x12 mashes per squa
inch (625mm) including iron fittings comple
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Vertical Style
4x6'-6"x4"x1" 1.27 Cft
Horizontal
Top 2x1'-10"x3"x1" 0.07 Cft
Middle 2x1'-10"x1"x1" 0.06 Cft
Lock 2x1'-10"x6"x1" 0.27 Cft
Bottom 2x1'-10"x6"x1" 0.27 Cft
2.18 Cft
Wastage 10% 0.22 Cft
2.40 Cft 0.00 P. Cft -
Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Tower Bolts 2.00 Nos 0.00 Each -
Handles 6" (150mm) 2.00 Nos 0.00 Each -
Hook & Clamp 2.00 Nos 0.00 Each -
Screws / Nails 2.00 Doz 0.00 P. Doz -
Spring Hinges 2.00 Nos 0.00 Each -
Page 46
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Wire Gauge
2x1'-2"x2'-1" 4.83 Sft
4x1'-2"x1'-7" 7.33 Sft
12.16 Sft
Wastage 15% 1.82 Sft
13.98 Sft 0.00 Sft -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour
Total -
Sundries 10 Percent -
Total -
Page 47
Item No. 12 First class deodar wood wrought joinery wor
wire gauze doors and windows with 22 SWG
galvanized wire gauze 12x12 mashes per squa
inch (625mm) including iron fittings comple
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4'x6.75' = 27 Sft
Material
Horizontal
Top 2x1'-10"x3"x1" 0.12 Cft
Middle 2x1'-10"x1"x1" 0.06 Cft
Lock 2x1'-10"x6"x1" 0.24 Cft
Bottom 2x1'-10"x6"x1" 0.24 Cft
Fillets 2(15"+15"25+25) x 3/8 0.02 Cft
Frame 4(15"+15"19+19) x 3/8 0.03 Cft
Top Rail 1x4x3"x1" 0.05 Cft
Vertical Rail 2x7x3"x1" 0.15 Cft
2.00 Cft
Wastage 10% 0.20 Cft
2.20 Cft 0.00 P. Cft -
Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Tower Bolts 9" (228mm) 2.00 Nos 0.00 Each -
Handles 6" (150mm) 2.00 Nos 0.00 Each -
Hook & Clamp 2.00 Nos 0.00 Each -
Screws / Nails 2.00 Doz 0.00 P. Doz -
Page 48
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Wire Gauge
2x1'-2"x2'-1" 4.83 Sft
4x1'-2"x1'-7" 7.33 Sft
12.16 Sft
Wastage 15% 1.82 Sft
13.98 Sft 0.00 Sft -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour
Total -
Sundries 10 Percent -
Total -
Page 49
Item No. 12 First class deodar wood wrought joinery wor
wire gauze doors and windows with 22 SWG
galvanized wire gauze 144 mashes per square
inch (625mm) including iron fittings comple
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4'x6.75' = 27 Sft
Material
Horizontal
Top 2x1'-10"x3"x1" 0.12 Cft
Middle 2x1'-10"x1"x1" 0.06 Cft
Lock 2x1'-10"x6"x1" 0.24 Cft
Bottom 2x1'-10"x6"x1" 0.24 Cft
Fillets 2(15"+15"25+25) x 3/8 0.02 Cft
Top Rail 1x4'x3"x1" 0.05 Cft
Vertical Rail 2x7'x3"x1" 0.15 Cft
1.97 Cft
Wastage 10% 0.22 Cft
2.19 Cft 0.00 P. Cft -
Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Tower Bolts 9" (228mm) 2.00 Nos 0.00 Each -
Handles 6" (150mm) 2.00 Nos 0.00 Each -
Hook & Clamp 2.00 Nos 0.00 Each -
Screws / Nails 2.00 Doz 0.00 P. Doz -
Spring 2.00 Nos 0.00 Each -
Page 50
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Wire Gauge
2x1'-2"x2'-1" 4.83 Sft
4x1'-2"x1'-7" 7.33 Sft
12.16 Sft
Wastage 15% 1.82 Sft
13.98 Sft 0.00 Sft -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour
Total -
Sundries 10 Percent -
Total -
Page 51
Item No. 12 G.I. wire gauze 22 SWG, 12x12 meshes per sq
inch (256mm) fixed to chowkhat with " (20m
thick deodar wood screw and strip.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 3' = 12 Sft
Material
Wood Work
Wood 0.25 Cft 0.00 P. Cft -
Wire gauze 12.00 Sft 0.00 Sft -
Nails L.S. 8.00
Total 8.00
Contractor's Profit & Ove 20 Percent 1.60
Total for 12 Sft. 9.60
Rate Per Sft 9.60 = 0.80
12
Labour
Total -
Sundries 10 Percent -
Total -
Page 52
Item No. 12 G.I. wire gauze 22 SWG, 12x12 meshes per
square inch (625mm) fixed to chowkhat with
(12mm) strip on separate frame of deodar wo
2"x2" (50x50mm).
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 2' x 4' = 8 Sft
Material
Deodar Wood
Fitting
Total 2.86
Contractor's Profit & Ove 20 Percent 0.57
Total for 8 Sft. 3.43
Rate Per Sft 3.43 = 0.43
8
Page 53
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Page 54
DESCRIPTION OF ITEM NO 13: Making and fixing trellis doors and windows
deodar wood complete.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 18 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 18 Sft. -
Rate Per Sft 0.00 = -
18
Labour
Carpenter 1.50 No 0.00 P. Day -
Skilled Cooly 1.00 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Page 55
DESCRIPTION OF ITEM NO 14: Providing & fixing mild steel chowkhat of d
windows, C. Window etc. including hold fast
making and threading holes for hinges etc.
complete
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Structural Steel
M.S. Angle Iron 1"x1"x" (40x40x6mm)
Vertical 2x7 14 Rft
Horizontal 1x4 4 Rft
18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft
18.90 Rft @ 2.32 Lbs/Rft 43.85 Lbs
M.S. Flat 2"x" (50x6mm)
Vertical 2x7 14 Rft
Horizontal 1x4 4 Rft
18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft
18.9 @ 1.68 Lbs/ft 31.75 Lbs
M.S. Flat Patti 1"x1/8" (25x3mm) at
bottom.
4 @ 0.42 Lbs/ft 1.68 Lbs
77.28Lb (3 5.06)Kg 0.00 P. Kg -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Page 56
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Making holes in frame for hinges 4x4 16.00 Nos 0.00 Each -
Welding plate with angle iron 18.00 Nos 0.00 Each -
Welding hold fast with frame 6.00 Nos 0.00 Each -
Welding M.S.Steel bar with frame 2.00 Nos 0.00 Each -
Total -
Sundries 10 Percent -
Total -
Page 57
Item No. 14 Providing & fixing mild steel chowkhat of d
windows, C. Window etc. including hold fast
making and threading holes for hinges etc.
complete
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Structural Steel
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Page 58
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Making holes in frame for hinges 4x4 16.00 Nos 0.00 Each -
Welding plate with angle iron 18.00 Nos 0.00 Each -
Welding hold fast with frame 6.00 Nos 0.00 Each -
Welding M.S.Steel bar with frame 2.00 Nos 0.00 Each -
Total -
Sundries 10 Percent -
Total -
Page 59
Item No. 15 Providing and fixing M.S. Sheet hollow pres
frame of doors, windows, CW, etc. (Chowkha
only) of 20 SWG welded with M.S. flat
6"x1"x1/8" (150x40x3mm) M.S. hold fast
9"x1"x1/8" (225x25x3mm) welded/ screwed 4"
(100mm) long iron hinges including fitting
chowkhat with cement sand mortar 1:8 and
embedding hold fast in cement concrete 1:2:
complete in all respects.
a) Single Rebate.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 7' = 28 Sft
Material
Page 60
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Cement 0.20 Bag 0.00 Each -
Sand 2.00 Cft 0.00 P. Cft -
Cement Concrete 1:2:4 for fixing hold fast
Cement 0.08 Bag 0.00 Bag -
Sand 0.20 Cft. 0.00 % Cft. -
Bajri 0.40 Cft. 0.00 % Cft. -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 28 Sft. -
Rate Per Sft 0.00 = -
28
Labour
Total -
Sundries 10 Percent -
Total -
Page 61
Item No. 15 Providing and fixing M.S. Sheet hollow pres
frame of doors, windows, C. window, etc.
(Chowkhat only) of 20 SWG welded with M.S.
6"x1"x1/8" (150x32x3mm) M.S. hold fast
9"x1"x1/8" (225x25x3mm) welded/ screwed 4"
(100mm) long iron hinges including fitting
chowkhat with cement sand mortar 1:8 and
embedding hold fast in cement concrete 1:2:
complete in all respects.
b) Double Rebate.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 7' = 28 Sft
Material
Page 62
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 28 Sft. -
Rate Per Sft 0.00 = -
28
Total -
Sundries 10 Percent -
Total -
Page 63
DESCRIPTION OF ITEM NO 16: Extra for providing & fixing iron double sp
hinges, with brass fittings (it shall inclu
finger plate, 6" tower bolts)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 21 Sft
Material
Page 64
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. ##### Say -
Page 65
DESCRIPTION OF ITEM NO 17: Providing and fixing brass spring hinges, t
gauzed doors.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. 0.00 Say -
Page 66
DESCRIPTION OF ITEM NO 18: Providing and fixing sliding bolt to doors.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 16 Each
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
16
Page 67
Item No. 18 Providing and fixing sliding bolt to doors.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 16 Each
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
16
Page 68
Item No. 18 Providing and fixing sliding bolt to doors.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Anaylysis for = 16 Each
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
16
Page 69
Item No. 18 Providing and fixing sliding bolt to doors.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 16 Each
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
16
Page 70
DESCRIPTION OF ITEM NO 19: Extra for brass fittings to doors and windo
except for hinges, which shall be of iron.
i) Deodar wood panelled or panelled and glazed
fully glazed.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 7' = 28 Sft
Total 222.38-101.04 -
Contractor's Profit & Ove 20 Percent -
Total for 28 Sft. -
Rate Per Sft 0.00 = -
28
Labour
Carpenter 0.04 No 0.00 P. Day -
Skilled Cooly 0.04 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Rate Per Sft 0.00 = -
28
Page 71
Item No. 19 Extra for brass fittings to doors and windo
except for hinges, which shall be of iron.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 7' = 28 Sft
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 28 Sft. -
Rate Per Sft 0.00 = -
28
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 72
DESCRIPTION OF ITEM NO 20: Extra for providing and fixing, approved qu
rim lock adjustable over the style surface.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. 0.00 Say -
Page 73
DESCRIPTION OF ITEM NO 21: Providing and fixing approved quality morti
lock.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total 14.45
Sundries 10 Percent 1.45
Total 15.90
Item Rates
Labour Rate for Each Rs. 19.07 Say 19.05
Page 74
DESCRIPTION OF ITEM NO 22: Providing and fixing expanded metal " to
(12mm to 20mm) mesh 16 gauge.
a) Fixed to chowkhat with 1" (25mm) thick deod
wood strip and screws etc.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 2' = 8 Sft
Material
Deodar Wood
Strips vertical 2x2x"x3/12" 0.08 Cft
Horizontal 2x3-10/12x"x3/12" 0.16 Cft
0.24 Cft
Wastage 20% 0.05 Cft
0.29 Cft
SAY 0.30 Cft 0.00 P. Cft -
Expanded metal 1x4x2 8.00 Sft
Wastage 10% 0.80 Sft
8.80 Sft 0.00 Sft -
Nails / Screws 2.00 Doz 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 8 Sft. -
Rate Per Sft 0.00 = -
8
Labour
Carpenter 0.25 No 0.00 P. Day -
Skilled Cooly 0.25 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 8 Sft. -
Rate Per Sft 0.00 = -
8
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 75
Item No. 22 Providing and fixing expanded metal " to
(12mm to 20mm) mesh 16 gauge.
b) Fixed with 1" (25mm) cover moulding & screw
including deodar wood frame 2"x2" (50x50mm)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 3' = 12 Sft
Material
Deodar Wood Frame
2 No 4'x2/12"x212" 0.23 Cft
2 No 3'x2/12"x212" 0.17 Cft
Moulding 1x13 2/3'x1/12x2/12 0.20 Cft
0.60 Cft
Wastage 20% 0.12 Cft
0.72 Cft 0.00 P. Cft -
Expended metal 1x4x3 12.00 Sft
Wastage 10% 1.20 Sft
13.20 Sft 0.00 Sft -
Nails / Screws 2.00 Doz 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 12 Sft. -
Rate Per Sft 0.00 = -
12
Labour
Carpenter 0.50 No 0.00 P. Day -
Skilled Cooly 0.25 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 12 Sft. -
Rate Per Sft 0.00 = -
12
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 76
DESCRIPTION OF ITEM NO 23: a Providing and fixing deodar wood almirah 9"
12" (225 to 300mm) depth, including boxing
with back shelves, shutter and brass fittin
complete.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3' x 5' = 15 Sft
Material
Deodar Wood
Sides 2x1'x5'x1/12" 0.84 Cft
Back 1x3'x5'x" 0.94 Cft
Top & Bottom 2x3'x1'x1/12" 0.50 Cft
Plank 3x3'x1'x1/12" 0.75 Cft
Shutters 2x1.5'x5'x1/12" 1.25 Cft
4.28 Cft
Wastage 10% 0.43 Cft
4.71 Cft 0.00 P. Cft -
Fittings Brass
Hings 3" (75mm) 6.00 Nos 0.00 Each -
Hasp & Staple (Brass) 1.00 No 0.00 Each -
Brass Handle 6" (150mm) 2.00 Nos 0.00 Each -
Wooden Plugs 10.00 Nos 0.50 Each 5.00
Nails / Screws L.S. 19.00
Bitumen 1.43 Kg. 0.00 P. Kg. -
Total 24.00
Contractor's Profit & Ove 20 Percent 4.80
Total for 15 Sft. 28.80
Rate Per Sft 28.80 = 1.92
15
Page 77
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 78
Item No. 23 Providing and fixing deodar wood almirah 9"
12" (225 to 300mm) depth, with shelves shut
and brass fittings, etc. without boxing & b
complete.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3' x 5' = 15 Sft
Material
Deodar Wood
Plank 3x10x3'x1'x1/12" 0.75 Cft
Shutters 2x1.5'x5'x1/12" 1.25 Cft
2.00 Cft
Wastage 10% 0.20 Cft
2.20 Cft 0.00 P. Cft -
Fittings Brass
Hings 3" (75mm) 6.00 Nos 0.00 Each -
Hasp & Staple (Brass) 1.00 No 0.00 Each -
Brass Handle 6" (150mm) 2.00 Nos 0.00 Each -
Wooden Plugs 6.00 Nos 0.50 Each 3.00
Nails / Screws L.S. 12.00
Total 15.00
Contractor's Profit & Ove 20 Percent 3.00
Total for 15 Sft. 18.00
Rate Per Sft 18.00 = 1.20
15
Labour
Carpenter 1.75 Nos 0.00 P. Day -
Skilled Cooly 0.50 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 15 Sft. -
Rate Per Sft 0.00 = -
15
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 79
Item No. 24 Providing and fixing class room almirah
consisting of 1" (25mm) thick solid flush s
with deodar wood lipping " (6mm) thick alr
(sterling made) fixed in deodar wood frame
(75x25mm) I/C full hinges C.P. fittings wit
R.C.C. (1:1-:3) shelves 1-" (40mm) thick
coats of painting.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4.5' x 3.5' = 15.75 Sft
Material
Precast reinforced cement concrete
(1:1-"3)
Shelves 2x3-x1-1/8x1/8 0.91 Cft 3.68 P. Cft 3.35
Steel " (12mm) dia
4x3.25 (4x0.975=3.900Rm) 13.00 Rft
5x1 1'/6(5x0.375=1.875Rm) 5.63 Rft
18.63 Rft
Wastage 5% 0.93 Rft
19.56 Rft 1.48 Kg 0.00 Kg -
@ 0.167 Lbs/Rft
Deodar wood frame I/C sawing
2x4'x'x1/12' 0.19 Cft
2x3'xx'x1/12' 0.15 Cft
0.34 Cft
Wastage 35% 0.12 Cft
0.46 Cft 0.00 P. Cft -
1" (25mm) thick solid flush shutter
(Sterling made)
1x3'x4' (1x0.900x1.200 = 1.080) 12.00 Sft
Wastage 5% 0.60 Sft
12.60 Sft 0.00 Sft -
Deodar wood lipping 6mm thick
(Sterling made)
2x4' (2x1.200 = 2.400) 8.00 Rft
2x2x-' (2x2x0.450 = 1.800) 6.00 Rft
14.00 Rft 0.00 Rft -
Page 80
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Full hinges 1" (25mm) I/C screws 2x4 8.00 Nos 0.00 Each -
C.P. dasti I/C screws 2.00 Nos 0.00 Each -
Khunda chapks (Best quality) I/C screws 1.00 No 0.00 Each -
Rawal plug 1-" long 12.00 Nos 0.00 Each -
Screws 1-" long 1.00 Doz 0.00 P. Doz -
Glue 0.20 Kg. 0.00 P.Kg. -
Painting 3 coats 0.428 Gln. 0.00 P. Gln. -
Total 3.35
Contractor's Profit & Ove 20 Percent 0.67
Total for 15.75 Sft. 4.02
Rate Per Sft 4.02 = 0.26
15.75
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 81
DESCRIPTION OF ITEM NO 25: Providing and fixing wooden box type ward r
22" (550mm) deep including " (20mm) thick
boxing and shelves, hanger rods, hard board
drawers, brass fitting locking arrangements
handles internal bolts shoe rods, etc. incl
three coats of enamel paints.
i) Partal wood boxing and deodar wood shelves
leaves etc.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.5' = 26 Sft
Material
Partal Wood
Boxing
Side 2x6-1/3x22/12x3/48 1.45 Cft
Top & Bottom 2x4 22/12x3/48 0.92 Cft
Foot Rack 1x3-7/8x22/12x3/48 0.44 Cft
Vertical Style 1x5x22/12x3/48 0.57 Cft
Strips 6x22/12x1/8x3/48 0.09 Cft
Back 2x1x22/12x3/48 0.34 Cft
3.81 Cft
Wastage 15% 0.57 Cft
4.38 Cft 0.00 P. Cft -
Shutters Deodar Wood
1x1-2/3x6x1/12 0.91 Cft
1x2-1/3x6x1/12 1.26 Cft
2.17 Cft
Wastage 15% 0.33 Cft
2.50 Cft 0.00 P. Cft -
Hard Board
4x6 26.00 Sft
Wastage 10% 2.60 Sft
28.60 Sft 0.00 Sft -
Sawing Charges
6.88x10 68.80 Sft 0.00 Sft -
Page 82
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Fittings
Total (0.08)
Contractor's Profit & Ove 20 Percent (0.02)
Total for 26 Sft. (0.10)
Rate Per Sft -0.10 = (0.00)
26
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 83
Item No. 25 Providing and fixing wooden box type ward r
22" (550mm) deep including " (20mm) thick
boxing and shelves, hanger rods, hard board
drawers, brass fitting locking arrangements
handles internal bolts shoe rods, etc. incl
three coats of enamel paints.
ii) Deodar wood boxing and shelves & leaves etc
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 8' x 5' = 40 Sft
Material
Deodar Wood
Boxing
Vetical Side 2x8x22/12x3/48 1.83 Cft
Control Side 1x7-7/8x22/12x3/48 0.90 Cft
Horizontal T&B 2x4 11/12x22/12x3/48 1.13 Cft
Shelves 5x2x22/12x3/48 1.15 Cft
Vertical 1x1x22/12x3/48 0.17 Cft
Shoes 2xx1/5x1/12 0.02 Cft
Sutter 2x2 3/5x8x1/12 3.47 Cft
Strips 2x8x1/12x1/24 0.06 Cft
Strips 2x5x1/12x1/24 0.03 Cft
8.76 Cft
Wastage 15% 1.31 Cft
10.07 Cft 0.00 P. Cft -
Hard Wood Board
Back 5x8 40.00 Sft
Wastage 10% 4.00 Sft
44.00 Sft 0.00 Sft -
Sawing Charges :
10.20x10 102.00 Sft 0.00 Sft -
Page 84
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Fittings
Hings 4" (100mm) 6.00 Nos -0.10 Each (0.60)
Handle 2.00 Nos 0.00 Each -
Tie rod welding fixing arragement -
Hanger hook including full out rod 2.00 Nos 0.00 Each -
Screws 4.00 Doz 0.00 P. Doz -
Tower bolt 4" (100mm) 1.00 Nos -0.08 Each (0.08)
Nail 0.19 Kg 0.00 P. Kg -
Locking arrangement 1.00 Nos 0.00 Each -
Total (0.68)
Contractor's Profit & Ove 20 Percent (0.14)
Total for 40 Sft. (0.82)
Rate Per Sft -0.82 = (0.02)
40
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 85
Item No. 26 Providing/ fixing ward robe 22" (550mm) dee
consisting of RCC shelves 1-" (40mm) thick
(12mm) thick vin board boxing and back (one
ply) vin board shutter " (20mm) thick I/c
wood lipping "(6mm) on all edges fixes I/c
wood frame 3"x1" with hanger rod in centre
drawers at bottom and openable shutter on u
portion I/c full hinges C.P. fitting and pa
coats.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 7.5' x 7' = 52.50 Sft
Material
RCC shelves (Precast RCC 1x1-x3 top
and bottom
2x7-x2x1/8 3.62 Cft
4x2-x2x1/8 2.50 Cft
6.12 Cft 0.00 P. Cft -
Steel Reinforcement
6.12x1.50 9.18 Kg 0.00 P. Kg -
Page 86
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Deodar Wood
Frame 4x7x3/12x1/12 0.58 Cft
Frame 4x7-x3/12x1/12 0.62 Cft
Lipping 3x6x2-x1/16x1/24 0.11 Cft
Lipping 6x2x1-1/8x1/16x1/24 0.04 Cft
Lipping 2x3x4x1/16x1/24 0.06 Cft
Page 87
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Total 32.01
Contractor's Profit & Ove 20 Percent 6.40
Total for 52.50 Sft. 38.41
Rate Per Sft 38.41 = 0.73
52.50
Labour
Labour for making ward robe complete 52.50 Sft 29.00 Sft 1,522.50
Total 1,522.50
Sundries 10 Percent 152.25
Total 1,674.75
Item Rates
Labour Rate Per Sft Rs. ##### Say 38.30
Labour Rate Per Sqm Rs. ##### Say 411.90
Page 88
DESCRIPTION OF ITEM NO 27: Providing and fixing chowkhat for doors, wi
& C. Windows including hold fast etc.
a) Teak Wood.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Teak Wood
Top Rail 1x4x3"x4" 0.45 Cft
Vertical Rail 2x7x3"x4" 1.33 Cft
1.78 Cft
Wastage 12% 0.22 Cft
2.00 Cft 0.00 P. Cft -
Iron hold fast 6.00 Nos 0.00 Each -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 89
Item No. 27 Providing and fixing chowkhat for doors win
& C. Windows including hold fast etc.
b) Deodar Wood.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
For Frame
Top Rail 1x4'x3"x4" 0.45 Cft
Vertical Rail 2x7'x3"x4" 1.33 Cft
1.78 Cft
Wastage 15% 0.27 Cft
2.05 Cft 0.00 P. Cft -
Iron hold fast 6.00 Nos 0.00 Each -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 90
Item No. 27 Providing and fixing chowkhat for doors, wi
& C. Windows including hold fast etc.
c) Shisham Wood.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Shishim Wood
Top Rail 1x4'x3"x4" 0.45 Cft
Vertical Rail 2x7'x3"x4" 1.33 Cft
1.78 Cft
Wastage 15% 0.27 Cft
2.05 Cft 0.00 P. Cft -
Iron hold fast 6.00 Nos 0.00 Each -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 91
DESCRIPTION OF ITEM NO 28:
Making & fixing deodar wood planking in eav
boards etc. planed on both side related & f
including nails & screws, bolt & brackets.
a) 1" (25mm) Thick.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 100 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
100
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 92
Item No. 28 Making & fixing deodar wood planking in eav
boards etc. planed on both side related & f
including nails & screws, bolt & brackets.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 100 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
100
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 93
Item No. 28 Making & fixing deodar wood planking in eav
boards etc. planed on both side related & f
including nails & screws, bolt & brackets.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 100 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
100
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 94
DESCRIPTION OF ITEM NO 29:
Making and fixing deodar wood shelves,
including brackets.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 100 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
100
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 95
Item No. 29 Making and fixing deodar wood shelves,
including brackets.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 100 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
100
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 96
Item No. 29 Making and fixing deodar wood shelves,
including brackets.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 100 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
100
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 97
DESCRIPTION OF ITEM NO 30: a) Making and fixing cleats for doors and wind
including hinges and screws.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 10 Nos
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
10
Page 98
Item No. 30 Making and fixing cleats with brass hooks f
ventilator.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total 0.44
Contractor's Profit & Ove 20 Percent 0.09
Total 0.53
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
1.25
Page 99
Item No. 30 Providing and fixing door stops of 1" (40m
dia rubber block.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 30 Nos
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
30
Page 100
Item No. 30 Providing and fixing G.I. hook with clamps
doors.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. 0.00 0.00 Say -
30
Page 101
DESCRIPTION OF ITEM:
Item No. 31 Hard wood railing of any shape and design
including bends and corners fixed in positi
including polishing complete as directed
by Engineer Incharge.
a) Shisham Wood.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 12 Rft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total 12 Rft. -
Rate Per Rft 0.00 = -
12
Labour
Total -
Sundries 10 Percent -
Total -
Page 102
Item No. 31 Hard wood railing of any shape and design
including bends and corners fixed in positi
including polishing complete as directed
by Engineer Incharge.
b) Teak Wood.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 10 Rft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 10 Rft. -
Rate Per Rft 0.00 = -
10
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. - Say -
Labour Rate Per Rm Rs. 0.01 Say -
Page 103
DESCRIPTION OF ITEM NO 32:
Deodar wood dado or Picture Rail 3"x1"
(50x40mm) as per approved design including
moulding and fixed in place, cost of screws
plugs and painting complete.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 10 Rft
Material
Deodar wood 0.60 Cft 0.00 P. Cft -
Sand paper 1.00 Sht 0.00 P. Sht -
Rawal Plugs 0.50 No 0.00 Each -
Screws 0.50 Doz 0.00 P. Doz -
Polishing material 0.038 Kg. 0.00 P. Kg. -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 10 Rft. -
Rate Per Rft 0.00 = -
10
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. - Say -
Labour Rate Per Rm Rs. - Say -
Page 104
DESCRIPTION OF ITEM NO 33: Sawing wood by hand.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 300 Sft
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 x 100 =154.28 0.02
300
Page 105
Item No. 33: Sawing wood by hand.
Qty Rate
Per Unit Amount
Rate Analysis for = 450 Sft
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 x 100=205.7 S -
450
Page 106
DESCRIPTION OF ITEM NO 34: Sawing wood by machine.
a) Soft Wood.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 300 Sft
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 x 100=94.97 Say (0.01)
300
Page 107
Item No. 34 Sawing wood by machine.
b) Hard Wood.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 300 Sft
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. 0.00 x 100=142.62 S -
300 -
Page 108
DESCRIPTION OF ITEM NO 35: Making and fixing sun shade of deodar wood
including fixing brackets.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 5 Sft
Material
Deodar Wood
Horizontal Planks
Top 4x5x1/3x1/24 0.28 Cft
Vertical 2x1x1/6x5/68 0.06 Cft
Supports along sun shade 0.04 Cft
2x3/2x1/8x5/48
Suporting brackets 2x1x1/8x5/48 0.03 Cft
Front ears hard strips 1x5x1/4x1/12 0.10 Cft
0.51 Cft
Wastage 10% 0.05 Cft
0.56 Cft 0.00 P. Cft -
Sawing & Nails L.S. 8.00
Total 8.00
Contractor's Profit & Ove 20 Percent 1.60
Total for 5 Sft. 9.60
Rate Per Sft 9.60 = 1.92
5
Labour
Carpenter 0.25 No 0.00 P. Day -
Cooly Skilled 0.10 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Page 109
DESCRIPTION OF ITEM NO 36: Making and fixing 1" (25mm) thick Kail or C
wooden notice board with frame.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 18 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 18 Sft. -
Rate Per Sft 0.00 = -
18
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 110
DESCRIPTION OF ITEM NO 37: Making deodar Punkha Pole = 10'x6"x6"
(3.047x0.150x0.150M).
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. - Say -
Page 111
DESCRIPTION OF ITEM NO 38: Dismantling and refixing eaves boards.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 70 Rft
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. 0.00 - Say -
70
Page 112
DESCRIPTION OF ITEM NO 39: Making wooden stair cases complete 2' to 3'
915mm) wide frame 1" (40mm) thick planks o
deodar wood, including hand rails.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 15 Rft
Material
Deodar Wood
Detail of Deodar Wood
2x5/6x15x1/8 3.12 Cft
Stops 14x2x1/8x5/6 3.65 Cft
and Rail 2x15xx 1.88 Cft
and Rail 2x4x3xx 1.50 Cft
10.15 Cft
Wastage L. S 0.35 Cft
10.50 Cft 0.00 P. Cft -
Nails 0.93 Kg 0.00 P. Kg -
Bolts " to 3" (12 to 76mm) long 5.880 Kg. 0.00 P. Kg -
Steel rods dia 3x3'-6" = 10.5 Rft 15.3Lb (7 .5Kg) 0.00 P. Kg -
Washers 12.00 Nos 0.00 Each -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 15 Rft. -
Rate Per Rft 0.00 = -
15
Labour
Carpenter 2.00 Nos 0.00 P. Day -
Blacksmith 0.50 No 0.00 P. Day -
Hammer-man 0.50 No 0.00 P. Day -
Cooly Skilled 2.00 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 15 Rft. -
Rate Per Rft 0.00 = -
15
Item Rates
Labour Rate Per Rft Rs. - Say -
Labour Rate Per Rm Rs. 0.01 Say -
Page 113
DESCRIPTION OF ITEM NO 40: Providing and fixing partition including fr
a - (i) Sheets on one side of frame work.
Hard Board.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 128 Sft
Material
Hard Board Sheet
1x8x16 128.00 Sft
Wastage 5% 6.40 Sft
134.40 Sft 0.00 Sft -
Deodar Wood & other Accessories
Frame work 2x16x3"x2" 1.67 Cft
Horizontal post 1x16x2"x2" 0.56 Cft
2x8x3"x2" 0.83 Cft
3x8x2"x2" 0.83 Cft
3.89 Cft
Wastage 15% 0.58 Cft
4.47 Cft 0.00 P. Cft -
Nails of all sorts 0.47 Kg 0.00 P. Kg -
Screws 2.00 Doz 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Labour
Carpenter 1.00 Nos 0.00 P. Day -
Cooly Skilled 1.00 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 114
Item No. 40 Providing and fixing partition including fr
a - (ii) Ply wood " (6mm) thick.
One Side.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 128 Sft
Material
Ply Wood 1x8'x16 128.00 Sft
Wastage 5% 6.40 Sft
134.40 Sft 0.00 Sft -
Deodar Wood
Frame work 2x16x3"x2" 1.67 Cft
Horizontal post 1x16x2"x2" 0.56 Cft
Vertical post 3x8x2"x2" 0.83 Cft
Vertical post 3x8x2"x2" 0.83 Cft
3.89 Cft
Wastage 15% 0.58 Cft
4.47 Cft 0.00 P. Cft -
Nails of all sorts 0.47 Kg 0.00 Kg -
Screws 2.00 Doz 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Labour
Carpenter 1.00 Nos 0.00 P. Day -
Cooly Skilled 1.00 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 115
Item No. 40 Providing and fixing partition including fr
a - (iii) Masonite sheet.
One Side.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 128 Sft
Material
Masonite sheet 1x8x16 128.00 Sft
Wastage 5% 6.40 Sft
134.40 Sft 0.00 Sft -
Deodar Wood & other Accessories
Frame work 2x16x3"x2" 1.67 Cft
Horizontal post 1x16x2"x2" 0.56 Cft
2x8x3"x2" 0.83 Cft
3x8x2"x2" 0.83 Cft
3.89 Cft
Wastage 15% 0.58 Cft
4.47 Cft 0.00 P. Cft -
Nails of all sorts 0.47 Kg 0.00 P. Kg -
Screws 2.00 Doz 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Labour
Carpenter 1.00 Nos 170.00 P. Day 170.00
Cooly Skilled 1.00 Nos 85.00 P. Day 85.00
Total 255.00
Sundries 10 Percent 25.50
Total 280.50
Contractor's Profit & Ove 20 Percent 56.10
Total for 128 Sft. 336.60
Rate Per Sft 336.60 100 262.97
128
Item Rates
Labour Rate Per 100 Sft Rs. ##### Say 262.95
Labour Rate Per Sqm Rs. ##### Say 28.30
Page 116
Item No. 40 Providing and fixing partition including fr
b (1) Sheets on both sides of frame work.
Hard Board.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 128 Sft
Material
Hard Board Sheet
2 x 16 x 8 256.00 Sft
Wastage 5% 12.80 Sft
268.80 Sft 0.00 Sft -
Deodar Wood & other Accessories
Horizontal Post.
2x16x3"x2" 1.67 Cft
1x16x2"x2" 0.56 Cft
Vertical post 2x8x3"x2" 0.83 Cft
3x8x2"x2" 0.83 Cft
3.89 Cft
Wastage 15% 0.58 Cft
4.47 Cft 0.00 P. Cft -
Nails of all sorts 0.70 Kg 0.00 P. Kg -
Screws of all sorts 2.00 Doz 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Labour
Carpenter 1.20 Nos 0.00 P. Day -
Cooly Skilled 1.20 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 117
Item No. 40 Providing and fixing partition including fr
b - (ii) Ply wood. " (6mm) thick
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 128 Sft
Material
Ply Wood Sheet 2 x 16 x 8 (2 x 4.876 x 256.00 Sft
2.438) = 23.78 M
Wastage 5% 12.80 Sft
268.80 Sft 0.00 Sft -
Deodar Wood for frame work
Horizontal post 2x16x3"x2" 1.67 Cft
Cross 1x16x2"x2" 0.56 Cft
Vertical post 2x8x3"x2" 0.83 Cft
Vertical post 3x8x2"x2" 0.83 Cft
3.89 Cft
Wastage 15% 0.58 Cft
4.47 Cft 0.00 P. Cft -
Nails of all sorts 0.70 Kg 0.00 P. Kg -
Screws 3.00 Doz 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 128 Sft. -
Rate Per Sft 0.00 100 -
128
Labour
Carpenter 1.20 Nos 0.00 P. Day -
Cooly Skilled 1.20 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Page 118
Item No. 40 Providing and fixing partition including fr
b - (iii) Masonite sheet.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 128 Sft
Material
Masonite sheet 2x16'x8' 256.00 Sft
Wastage 5% 12.80 Sft
268.80 Sft 0.00 Sft -
Deodar Wood & other Accessories
Horizontal Post.
2x16x3"x2" 1.67 Cft
1x16x2"x2" 0.56 Cft
Vertical post 2x8x3"x2" 0.83 Cft
3x8x2"x2" 0.83 Cft
3.89 Cft
Wastage 15% 0.58 Cft
4.47 Cft 0.00 P. Cft -
Nails of all sorts 0.70 Kg 0.00 P. Kg -
Screws 2.00 Doz 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Rate Per Sft 0.00 100 -
128
Labour
Carpenter 1.20 Nos 0.00 P. Day -
Cooly Skilled 1.20 Nos 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Rate Per Sft 0.00 100 -
128
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. ##### Say -
Page 119
DESCRIPTION OF ITEM NO 41: Providing and fixing ceiling including fram
i) Hard Board.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 192 Sft
Material
Hard Board 16x12 192.00 Sft 0.00 Sft -
Partal Wood
7x16x3"x1" 3.50 Cft
9x16x3"x1" 3.38 Cft
6.88 Cft
Wastage 10% 0.69 Cft
7.57 Cft 0.00 P. Cft -
Hard Wood Gutti 32.00 Nos 0.00 Each -
Screws 3.00 Doz 0.00 P. Doz -
Nail 0.70 Kg 0.00 P. Kg -
Cement for grouting 0.178 Bag 0.00 P. Bag -
M.S clamp 4.00 Nos 0.00 Each -
M.S hook 4.00 Nos 0.00 Each -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 192 Sft. -
Rate Per Sft 0.00 100 -
192
Labour
Carpenter 3.00 Nos 0.00 P. Day -
Cooly Skilled 2.00 Nos 0.00 P. Day -
Cooly 1.00 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 192 Sft. -
Rate Per Sft 0.00 100 -
192
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 120
Item No. 41 Providing and fixing ceiling including fram
ii) Chip Board Sheets.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 192 Sft
Material
Chip Board 1x16x12 192.00 Sft 0.00 Sft -
Page 121
Item No. 41 Providing and fixing ceiling including fram
work.
iii) Ply Wood " (6mm) thick.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 192 Sft
Material
Ply Wood " (6mm) 12x16 192.00 Sft 0.00 Sft -
Page 122
Item No. 41 Providing and fixing ceiling including fram
iv) Masonite Sheet.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 192 Sft
Material
Masonite Sheet 1x16x12 192.00 Sft 0.00 Sft -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 192 Sft. -
Rate Per Sft 0.00 100 -
192
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 123
Item No. 42 Providing and fixing thermopore false ceili
including wooden frame panelling, cost of M
clamps, making holes in walls and repairing
damaged surface, complete in all respects.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 12' x 12' = 144 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 144 Sft. -
Rate Per Sft 0.00 100 -
144
Page 124
Detail Unit Rate (British System) per 100 Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 125
Item No. 42 Providing and fixing thermopore false ceili
including wooden frame panelling, cost of M
clamps, making holes in walls and repairing
damaged surface, complete in all respects.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 12' x 12' = 144 Sft
Material
Total 20.00
Contractor's Profit & Ove 20 Percent 4.00
Total for 144 Sft. 24.00
Rate Per Sft 24.00 100 16.67
144
Page 126
Detail Unit Rate (British System) per 100 Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 127
Item No. 42 Providing and fixing thermopore false ceili
including wooden frame panelling, cost of M
clamps, making holes in walls and repairing
damaged surface, complete in all respects.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 12' x 12' = 144 Sft
Material
Total 8.00
Contractor's Profit & Ove 20 Percent 1.60
Total for 144 Sft. 9.60
Rate Per Sft 9.60 100 = 6.67
144
Page 128
Detail Unit Rate (British System) per 100 Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 129
Item No. 42 Providing and fixing thermopore false ceili
including wooden frame panelling, cost of M
clamps, making holes in walls and repairing
damaged surface, complete in all respects.
Qty Rate
Per Unit Amount
Rate Analysis for 12' x 12' = 144 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 144 Sft. -
Rate Per Sft 0.00 100 -
144
Page 130
Detail Unit Rate (British System) per 100 Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Carpenter 2.25 Nos 0.00 P. Day -
Cooly Skilled 2.00 Nos 0.00 P. Day -
Cooly 0.50 No 0.00 P. Day -
Mason 0.25 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 131
DESCRIPTION OF ITEM NO 43: a) Fixing door including chowkhat.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. 0.01 Say -
Page 132
Item No. 43 Fixing windows including chowkhat.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate for Each Rs. 0.00 Say -
Page 133
DESCRIPTION OF ITEM NO 44: a) Glazing with panes 160Z to 180Z (454Gm to 5
Gm) including cost of putty.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 14 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 14 Sft. -
Rate Per Sft 0.00 = -
14
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 134
Item No. 44 Glazing with panes 16 Oz. to 18 Oz. (454Gm
Gm) using deodar wooden fillets and putty.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 14 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 14 Sft. -
Rate Per Sft 0.00 = -
14
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 135
DESCRIPTION OF ITEM NO 45: Glazing with glass panes 24 Oz. to 26 Oz. (
737Gm) using putty and deodar wooden fillet
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 15 Sft
Material
Glass Panes 15.00 Sft
Wastage 10% 1.50 Sft
16.50 Sft 0.00 Sft -
D. Wood for fillets 0.06 Cft 0.00 P. Cft -
Cost of putty and nails L.S. -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 15 Sft. -
Rate Per Sft 0.00 = -
15
Labour
Total -
Sundries 10 Percent -
Total -
Page 136
DESCRIPTION OF ITEM NO 46:
a) Cutting to required sizes and fixing glass
with putty.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 14 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 14 Sft. -
Rate Per Sft 0.00 = -
14
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. ##### Say -
Page 137
Item No. 46 Cutting to required sizes and fixing glass
with wooden fillets and putty.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 16 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 16 Sft. -
Rate Per Sft 0.00 = -
16
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 138
DESCRIPTION OF ITEM NO 47: Glazing with plate glass " (6mm) thick inc
the cost of deodar wood fillets and putty.
a) Glazing upto 8 Sft (0.744M).
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 8 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 8 Sft. -
Rate Per Sft 0.00 = -
8
Labour
Glazier 0.17 No 0.00 P. Day -
Cooly Skilled 0.17 No 0.00 P. Day -
Carpenter 0.06 No 0.00 P. Day -
Cooly Skilled 0.06 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 139
Item No. 47 Glazing exceeding 8 Sft (0.744M)
and not exceeding 24 Sft (2.230M)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for = 16 Sft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 16 Sft. -
Rate Per Sft 0.00 = -
16
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 140
DESCRIPTION OF ITEM NO 48: Providing and fixing 1" (40mm) thick deoda
wood panelled or panelled and glazed, doors
windows, with mild steel chowkhat (frame),
complete in all respects (excluding sliding
lock) with :
i) M.S. angle iron 1"x1"x" (40x40x6mm)
welded with M.S. flat 2"x" (50x6mm)
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Panells
2x16"x23"x5/8" 0.24 Cft
4x16"x19"x5/8" 0.47 Cft
Beading
2(16+16+23+23) 5/8
(1+2) = 0.01 0.01 Cft
2x8
4(16+16+19+19) 5/8
(1+1) 0.02 Cft
2x8
2.74 Cft
Wastage 30% 0.82 Cft
3.56 Cft 0.00 P. Cft -
Page 141
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Fitting
Hinges 4" (100mm) 8.00 Nos 0.00 Each -
Tower bolt 9: (225mm) 3.00 Nos 0.00 Each -
Handle 6" (150mm) 3.00 Nos 0.00 Each -
Iron hold fast 6.00 Nos 0.00 Each -
Rubber 2.00 Nos 0.00 Each -
Hook & clamp 2.00 Nos 0.00 Each -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour
Total -
Sundries 10 Percent -
Total -
Page 142
Item No. 48 Providing and fixing 1" (40mm) thick deoda
wood panelled or panelled and glazed, doors
windows, with mild steel chowkhat (frame),
complete in all respects (excluding sliding
lock) with :
ii) M.S. Tee Iron 1"x1"x" (40x40x6mm)
welded with M.S. flat "x" (12x6mm).
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
T-Iron 1"x1"x"
Vetical 2x7 14 Rft
Horizontal 1x4 4 Rft
18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft
18.90 Rft 2.36 Lbs/Rft 44.60 Lbs
M.S. bar " = 4' @ 0.67 Lbs 2.68 Lbs
M.S. flat "x"=18.90 Rft @ 0.425 Lbs 8.03 Lbs
55.31Lbs ( 25.10)Kg 0.00 P. Kg -
Deodar Wood
Vertical Style 4x6'-8"x4"x1" 1.12 Cft
Horizontal Top 2x1'-11"x4"x1" 0.16 Cft
Middle Top 2x1'-11"x4"x1" 0.16 Cft
Local Top 2x1'-11"x6"x1" 0.24 Cft
Bottom Top 2x1'-11"x8"x1" 0.32 Cft
Panells
2x16"x23"x5/8" 0.24 Cft
4x16"x19"x5/8" 0.47 Cft
Beading
2(16+16+23+23) 5/8
(1+2) 0.01 Cft
2x8
4(16+16+19+19) 5/8
(1+1) 0.02 Cft
2x8
2.74 Cft
Wastage 30% 0.82 Cft
3.56 Cft 0.00 P. Cft -
Page 143
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Fitting
Hinges 4" (100mm) 8.00 Nos 0.00 Each -
Tower bolt 9: (225mm) 3.00 Nos 0.00 Each -
Handle 6" (150mm) 3.00 Nos 0.00 Each -
Iron hold fast 6.00 Nos 0.00 Each -
Rubber 2.00 Nos 0.00 Each -
Hook & clamp 2.00 Nos 0.00 Each -
Screws 2.50 Doz 0.00 P. Doz -
Glue 0.05 Kg. 0.00 P.Kg. -
Spikes 0.13 Kg. 0.00 P.Kg. -
Sawing charge 35.60 Sft 0.00 Sft -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 144
DESCRIPTION OF ITEM NO 49: Providing and fixing 1" (40mm) thick hollo
doors and windows, with commercial ply (3mm
both faces of deodar wood shutter frame 1"
(32mm) thick and partal wood braces at abou
(76mm) apart and deodar wood lipping 1"x3/
(40x10mm) fixed with M.S. chowkhat (frame),
including chromium plated fittings, etc. co
all respects (without sliding bolt or lock)
a) M.S. Angle Iron 1"x1"x" welded with M.S.
flat 2"x"
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Angle Iron 1"x1"x"
Vetical 2x7 14 Rft
Horizontal 1x4 4 Rft
18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft 43.85 Lbs
M.S. flat 2"x" (50x6mm)
Vetical 2x7 14 Rft
Horizontal 1x4 4 Rft
18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft
18.90 Rft @ 1.68 Lbs/Rft 31.75 Lbs
M.S. flat patti 1"x1/8" (25x3mm) at bott 1.68 Lbs
77.28Lbs (35.06 Kg. 0.00 P. Kg -
Deodar Wood
Vertical Style 2x6'-8"x4"x1" 0.47 Cft
Vertical Style 3x6'-8"x2"x1" 0.35 Cft
Horizontal Style 1x3'-11"x4"x1" 0.14 Cft
Middle Style 1x3'-11"x4"x1" 0.14 Cft
Lock Style 1x3'-11"x6"x1" 0.21 Cft
Bottom Style 1x3'-11"x8"x1" 0.27 Cft
Side Strip 2x6'-8"x1"x1/8" 0.02 Cft
Side Strip 2x3'-8"x1"x1/8" 0.01 Cft
1.61 Cft
Wastage 35% 0.56 Cft
2.17 Cft 0.00 P. Cft -
Page 145
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Fitting
Hinges 4" (100mm) 4.00 Nos 0.00 Each -
Tower bolt 9: (225mm) 2.00 Nos 0.00 Each -
Handle 6" (150mm) 2.00 Nos 0.00 Each -
Iron hold fast 6.00 Nos 0.00 Each -
Rubber chocks 1.00 No 0.00 Each -
Hook & clamp 1.00 No 0.00 Each -
Screws 2.50 Doz 0.00 P. Doz -
Glue 0.75 Kg. 0.00 P.Kg. -
Spikes 0.20 Kg. 0.00 P.Kg. -
Sawing charge 21.70 Sft 0.00 Sft -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 146
DESCRIPTION OF ITEM NO 49: Providing and fixing 1" (40mm) thick hollo
doors and windows, with commercial ply (3mm
both faces of deodar wood shutter frame 1"
(32mm) thick and partal wood braces at abou
(76mm) apart and deodar wood lipping 1"x3/
(40x10mm) fixed with M.S. chowkhat (frame),
including chromium plated fittings, etc. co
all respects (without sliding bolt or lock)
b) M.S. Tee Iron 1"x1"x" welded with M.S.
flat "x"
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Tee Iron 1"x1"x"
Vetical 2x7 14 Rft
Horizontal 1x4 4 Rft
18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft @ 2.36 44.60 Lbs
M.S. flat "x" (40x6mm)
Vetical 2x7 14 Rft
Horizontal 1x4 4 Rft
18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft @ 0.423L 8.03 Lbs
M.S. bar " dia = 4 Rft @ 0.67 Lbs 2.68 Lbs
55.31Lbs ( 25.10 Kg 0.00 P. Kg -
Deodar Wood
Vertical Style 2x6'-8"x4"x1" 0.47 Cft
Vertical Style 3x6'-8"x2"x1" 0.35 Cft
Horizontal Style 1x3'-11"x4"x1" 0.14 Cft
Middle Style 1x3'-11"x4"x1" 0.14 Cft
Lock Style 1x3'-11"x6"x1" 0.21 Cft
Bottom Style 1x3'-11"x8"x1" 0.27 Cft
Side Strip 2x6'-8"x1"x1/8" 0.02 Cft
Side Strip 2x3'-8"x1"x1/8" 0.01 Cft
1.61 Cft
Wastage 35% 0.56 Cft
2.17 Cft 0.00 P. Cft -
Page 147
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Fitting
Hinges 4" (100mm) 4.00 Nos 0.00 Each -
Tower bolt 9: (225mm) 2.00 Nos 0.00 Each -
Handle 6" (150mm) 2.00 Nos 0.00 Each -
Iron hold fast 6.00 Nos 0.00 Each -
Rubber chocks 1.00 No 0.00 Each -
Hook & clamp 1.00 No 0.00 Each -
Screws 2.50 Doz 0.00 P. Doz -
Glue 0.75 Kg. 0.00 P.Kg. -
Spikes 0.20 Kg. 0.00 P.Kg. -
Sawing charge 21.70 Sft 0.00 Sft -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 27 Sft. -
Rate Per Sft 0.00 = -
27
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 148
DESCRIPTION OF ITEM NO 50: Providing and fixing 1" (40mm) thick solid
door shutter sterling or equivalent with co
ply (5mm thick) on both sides double presse
deodar wood lipping 1"x3/8" (40x10mm) arou
shutter including chromium plated fittings,
hinges with aluminium kick plate 22SWG on b
sides & finger plate complete in all respec
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3.5' x 7' = 24.5 Sft
Material
Solid flush
Door leaf 1" (40mm) thick sterling
or equivalent with commerical ply
(5mm) thick both sides.
3"x7'-0' = 24.50 Sft 24.50 Sft 0.00 Sft -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 24.5 Sft. -
Rate Per Sft 0.00 = -
24.5
Page 149
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 150
DESCRIPTION OF ITEM NO 51: Providing and fixing panelled door of M.S.
with forged door leaves of M.S. Sheet 22 SW
in hollow frame chowkhat 3"x4" (76x114mm)
made of M.S. sheet 18 SWG, filled with plai
concrete 1:3:6 etc. complete, with all fitt
hammer painting, including carriage to site
fixing in position.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4' x 7' = 28 Sft
Material
M.S. Sheet 18 SWG
for chowkhat
18'x15" 23.44 Sft
Wastage 20% 4.69 Sft
28.13 Sft 0.00 Sft -
M.S. Sheet 22 SWG
for shutter
26x7 1/8 31.50 Sft
Wastage 20% 6.30 Sft
37.80 Sft 0.00 Sft -
M.S. Flat 1"x1/16" (25x2mm)
6'-9"x0.21 1.43Lb (065) Kg 0.00 P. Kg -
Fitting
Hinges 4" (100mm) 6.00 Nos 0.00 Each -
Tower bolt 9: (225mm) 2.00 Nos 0.00 Each -
Handle 6" (150mm) 2.00 Nos 0.00 Each -
Iron hold fast 6.00 Nos 0.00 Each -
Screws L.S. 4.00
Welding electrode 4.00 Nos 0.00 Each -
Electricity Charges L.S. -
Total 4.00
Contractor's Profit & Ove 20 Percent 0.80
Total for 28 Sft. 4.80
Rate Per Sft 4.80 = 0.17
28
Page 151
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 152
DESCRIPTION OF ITEM NO 52: Providing and laying 24 SWG aluminium kick
plate 4" (100mm) high fixed with screws 4"
(100mm) Centre to Centre on bottom rail of
doors only. of commercial ply.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4 Rft
Material
Total -
Contractor's Profit & Ove 20 Percent -
Total for 4 Rft. -
Rate Per Rft 0.00 = -
4
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. - Say -
Labour Rate Per Rm Rs. - Say -
Page 153
DESCRIPTION OF ITEM NO 53: Providing and fixing curtain railing to doo
windows, comprising of TOSO-elite Japan mad
superior type of railing or equivalent, fix
4"x" (100x20mm) deodar wood strip, includi
painting.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
Rate For 10 Rft
Railing 10.00 Rft 0.00 P. Rft -
Cutting of Railing -
Screws 1.00 Dozen 0.00 P, Doz -
Guttis 6.00 Nos 0.00 Each -
Deodar wood 0.21 Cft 0.00 P. Cft -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 10 Rft. -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Rft Rs. - Say -
Labour Rate Per Rm Rs. - Say -
Page 154
DESCRIPTION OF ITEM NO 54: Providing and fixing M.S. flat "1/8" (12x3
grill including "x1/8" (20x3mm) M.S. Flat
of windows of approved design including pai
coat complete in all respect.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 2 x 3 = 8.75 Sft
Material
Total 164.12
Contractor's Profit & Ove 20 Percent 32.82
Total for 100 Sft. 196.94
Rate Per Sft 196.94 = 22.51
8.75
Page 155
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 156
DESCRIPTION OF ITEM NO 55: Providing and fixing G.I. Wire gauge 22 SWG
12x12 meshes per Sq Inch (625mm) fixed to s
window complete with flat iron putti "x1/8
(12x3mm) and machine made screws.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 4 x 3 = 12 Sft
Material
Wire Gauge 144 (12x12) Mesh 12.00 Sft
Wastage 10% 1.20 Sft
13.20 Sft 0.00 Sft -
Flat Iron "x1/8" (12x3mm)
3+3+4+4+4 18.00 Rft
Wastage 5% 0.90 Rft
18.90 Rft @ 0.21 4 Lbs (1. 82) Kg 0.00 P. Kg -
Screws 6.70 Dozen 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
12
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 100 Sft. -
Rate Per Sft 0.00 = -
55
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 157
DESCRIPTION OF ITEM NO 56: Providing and fixing wooden moulding stoppe
2"x5/8" (63x16mm) on door frame fitted wit
of approved quality complete in all respect
a) Teak Wood Moulding.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 16 Sft
Total -
Contractor's Profit & Ove 20 Percent -
Total for 16 Sft. -
Rate Per Sft 0.00 = -
16
Labour
Labour for sawing, planning and fixing
16 Rft (4.876Rm) moulding in position
carpenter. 0.50 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. 0.05 Say 0.05
Page 158
Item No. 56 Providing and fixing wooden moulding stoppe
2"x5/8" (63x16mm) on door frame fitted wit
of approved quality complete in all respect
b) Deodar Wood Moulding.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 16 Sft
Material
Deodar wood 2x(6'-10')+2'-3" 16.00 Rft
16x2"x5/8" 0.17 Cft
Wastage 25% 0.04 Cft
0.22 Cft 0.00 P. Cft -
Glue 0.26 Kg. 0.00 P. Cft -
Nails 0.116 Kg. 0.00 P. Cft -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 16 Sft. -
Rate Per Sft 0.00 = -
16
Labour
Labour for sawing, planning and fixing
16 Rft (4.876Rm) moulding in position
carpenter. 0.50 No 0.00 P. Day -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. 0.05 Say 0.05
Page 159
DESCRIPTION OF ITEM NO 57: Providing and fixing deodar wood dolly fram
having 1"x1" (40x40mm) vertical and
horizontal double posts with 1"x" (40x40m
full width of jamb braces at 12" (300mm)
including filling of hollow space in betwee
with 1:3:6 P.C.C. fixing of ply of approved
quality there upon & hold fasts complete in
respects.
a) Teak Wood Ply
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 13 Sft
Total -
Contractor's Profit & Ove 20 Percent -
Total for 13 Sft. -
Rate Per Sft 0.00 = -
13
Page 160
Detail Unit Rate (British System) per Sft
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. ##### Say (0.10)
Page 161
Item No. 57 Providing and fixing deodar wood dolly fram
1"x1" (40x40mm) vertical and horizontal d
with 1"x" (40x40mm) full width of jamb br
(300mm) including filling of hollow space i
braces with 1:3:6 P.C.C. fixing of ply of a
there upon & hold fasts complete in all res
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 13 Sft
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 13 Sft. -
Rate Per Sft 0.00 = -
13
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. ##### Say (0.10)
Page 162
DESCRIPTION OF ITEM NO 58: Providing and fixing ornamental wooden
architrave 3"x" (75x12mm) tapered to "
(6mm) all along the door frame complete in
respects.
a) Teak Wood Architrave.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3.5 x 7 = 24.50 Sft
Material
Length of Architrave
2(7'-0")+3'-6" 17.50 Rft
quantity (3/12'x'x1/12')x17.5' 0.18 Cft
Wastage 25% 0.05 Cft
0.23 Cft 0.00 P. Cft -
Teak Wood
Nails 0.093 Kg. 0.00 P. Kg. -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 24.50 Sft. -
Rate Per Sft 0.00 = -
24.50
Labour
Carpenter 0.25 No 0.00 P. Day -
Fixing in position L.S. -
Total -
Sundries 10 Percent -
Total -
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 163
Item No. 58 Providing and fixing ornamental wooden
architrave 3"x" (75x12mm) tapered to "
(6mm) all along the door frame complete in
respects.
b) Deodar Wood Architrave.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Rate Analysis for 3.5 x 7 = 24.50 Sft
Material
Length of Architrave
2(7')+3'-6" 17.50 Rft
quantity (3/12'x'x1/12')x17.5' 0.18 Cft
Wastage 25% 0.05 Cft
0.23 Cft 0.00 P. Cft -
Deodar wood
Nails 0.186 Kg. 0.00 P. Kg. -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 24.50 Sft. -
Rate Per Sft 0.00 = -
24.50
Labour
Carpenter 0.25 No 0.00 P. Day -
Fixing in position L.S. -
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total for 24.50 -
Rate Per Sft 0.00 = -
24.50
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. - Say -
Page 164
Item No. 58 Providing and fixing vin board cabinet in k
proofing and polishing / painting with synt
specific with handle and draws screw comple
respects as per drawing
2'-
8'-
Take Qty 8 x 2 = 16 Sft.
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Material
2 x 8 = 16 16.00 Ft.
2 x 5 = 10 10.00 Ft.
Total 26.00 Ft.
Wastage 20% 5.20
Total 31.2 Ft.
Page 165
h) Screws 3.75 Dozen 0.00 P. Doz -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Labour
Total -
Sundries 10 Percent -
Total -
Contractor's Profit & Ove 20 Percent -
Total -
Rate Per Sft 0.00 = -
16
Item Rates
Labour Rate Per Sft Rs. - Say -
Labour Rate Per Sqm Rs. Say -
Page 166
37 Providing and Installing PVC Bends of BSS.
1 1" (32mm) - 0.00 0.00 1/64 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
2 1" (40mm) - 0.00 0.00 1/50 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
3 2" (50mm) - 0.00 0.00 1/40 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
4 3" (75mm) - 0.00 0.00 1/27 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
5 4" (100mm) - 0.00 0.00 1/20 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
6 5" (125mm) - 0.00 0.00 1/16 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00
7 6" (150mm) - 0.00 0.00 1/15 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00
DAILY PROGRESS
Plumber 1 N 0.00 Per day 0.00 Sundries 10.00 Percent 0.00 Total 0.01
Cooly 0.9 0.00 Per day 0.00 Total 0.00 Say 0.01
Total 0.00 Contractor Profit 20.00 Percent 0.00
1
38 Providing and Installing PVC Tee of BSS.
20
(i) Class "B" Working Pressure
1 1" (32mm) - 0.00 0.0 1/40 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
2 1" (40mm) - 0.00 0.0 1/33 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
3 2" (50mm) - 0.00 0.0 1/27 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
4 3" (75mm) - 0.00 0.0 1/18 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
5 4" (100mm) - 0.00 0.0 1/13 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
6 5" (125mm) - 0.00 0.0 1/11 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00
7 6" (150mm) - 0.00 0.0 1/10 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00
DAILY PROGRESS
Plumber 1 N 0.00 Per day 0.00 Sundries 10.00 Percent 0.00 Total 0.01
Cooly 0.9 0.00 Per day 0.00 Total 0.00 Say 0.01
Total 0.00 Contractor Profit 20.00 Percent 0.00
2
39 Providing and Installation of PVC Sockets B.S.S
1 1" (32mm) - 0.00 0.00 1/64 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
2 1" (40mm) - 0.00 0.00 1/50 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
3 2" (50mm) - 0.00 0.00 1/40 - 0.00 0.00 0.00 60.00 0.01 0.00 0.00 - 0.00
4 3" (75mm) - 0.00 0.00 1/27 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
5 4" (100mm) - 0.00 0.00 1/20 - 0.00 0.00 0.00 50.00 0.01 0.00 0.00 - 0.00
6 5" (125mm) - 0.00 0.00 1/16 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00
7 6" (150mm) - 0.00 0.00 1/15 - 0.00 0.00 0.00 40.00 0.01 0.00 0.00 - 0.00
DAILY PROGRESS
Plumber 1 N 0.00 Per day 0.00 Sundries 10.00 Percent 0.00 Total 0.01
Cooly 0.9 0.00 Per day 0.00 Total 0.00 Say 0.01
Total 0.00 Contractor Profit 20.00 Percent 0.00
3
40 - Providing and installing PVC Tappered Core BSS
1 1" (32mm) - 0.00 0.00 1/64 - 0.00 0.00 0.00 60.00 0.00 0.00 0.00 - 0.00
2 1" (40mm) - 0.00 0.00 1/50 - 0.00 0.00 0.00 60.00 0.00 0.00 0.00 - 0.00
3 2" (50mm) - 0.00 0.00 1/40 - 0.00 0.00 0.00 60.00 0.00 0.00 0.00 - 0.00
DAILY PROGRESS
Plumber 1 N 0.00 Per day 0.00 Sundries 10.00 Percent 0.00 Total 0.00
Cooly 0.9 0.00 Per day 0.00 Total 0.00 Say 0.00
Total 0.00 Contractor Profit 20.00 Percent 0.00
4
1- Boring for tube well in all types of soil except shingle and rock from ground level to 100 Ft (30 Metre) depth
including sinking and with-drawing of casing pipe complete.
S. Dia of Time (Day) Daily Labour Hire charges Loading Expenses Repair Petty store Total Contractors, Total Grand Total Rs. per Rate per
No. bore required to labour per foot of boring Per Foot charges bolts & Column (6, Profit& over heads 20% Rate per Ft/ foot Metre
complete charges material No. of Rate per Amount of T & P nuts etc. 9, 10, 11) on Column
100' (30M) installation day day No.12 (12 + 13) (5 + 14) Say
and carriage
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
- -
1 3" 3 #VALUE! #VALUE! 0.00 0.02 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
- -
2 4" 4 #VALUE! #VALUE! 0.00 0.04 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
3 5" 6 #VALUE! #VALUE! 0.00 0.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
4 6" 9 #VALUE! #VALUE! 0.00 0.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
5 8" 11 #VALUE! #VALUE! 0.00 0.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
6 10" 13 #VALUE! #VALUE! 0.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
7 12" 14 #VALUE! #VALUE! 0.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
8 15" 17 #VALUE! #VALUE! 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
9 18" 18 #VALUE! #VALUE! 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
1
2- Boring for tube well in all types of soil except shingle gravel and rock from a depth of 100.10 to 200 Ft (30 to 60 Metre)
below ground level, including sinking and with drawing of casing pipe complete.
S. Dia of Time (Day) Daily Labour Hire charges Loading Expenses Repair Petty store Total Contractors' Total Grand Total Rate per Rate per
No. bore required to labour per foot of boring Per Foot charges bolts & Column (6, Profit& overheads 20% Rate per Ft/ Rft Metre
complete charges material No. of Rate per Amount of T & P nuts etc. 9, 10, 11) on Column
100' (30M) installation day day No.12 (12 + 13) (5 + 14)
and carriage
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
1 5" 10 #VALUE! #VALUE! 0.00 0.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
2 6" 14 #VALUE! #VALUE! 0.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
3 8" 15 #VALUE! #VALUE! 0.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
4 10" 16 #VALUE! #VALUE! 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
5 12" 17 #VALUE! #VALUE! 0.00 0.50 0.00 0.00 20.00 0.00 20.00 2.00 22.00 #VALUE! #VALUE! #VALUE!
6 15" 20 #VALUE! #VALUE! 0.00 0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
7 18" 21 #VALUE! #VALUE! 0.00 0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
2
3- Boring for tube well in all types of soil except shingle gravel and rock from a depth of 200.10 to 300 Ft (60 to 90 Metre)
below ground level including sinking and with drawing of casing pipe complete.
S. Dia of Time (Day) Daily Labour Hire charges Loading Expenses Repair Petty store Total Contractors, Total Total Rate per Rate per
No. bore required to labour per foot of boring Per Foot charges bolts & Column (6, Profit& over heads 20% Rate per Ft/ Rft Metre
complete charges material No. of Rate per Amount of T & P nuts etc. 9, 10, 11) on Column
100' (30M) installation day day No.12 (12 + 13) (5 + 14) Say
and carriage
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
1 5" 14 #VALUE! #VALUE! 0.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
2 6" 18 #VALUE! #VALUE! 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
3 8" 19 #VALUE! #VALUE! 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
4 10" 20 #VALUE! #VALUE! 0.00 0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
5 12" 21 #VALUE! #VALUE! 0.00 0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
6 15" 22 #VALUE! #VALUE! 0.00 0.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
7 18" 23 #VALUE! #VALUE! 0.00 0.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
3
4- Boring for tube well in all types of soil except shingle gravel and rock from a depth of 300.10 to 400 Ft (90 to 120 Metre)
below ground level including sinking and with drawing of casing pipe complete.
S. Dia of Time (Day) Daily Labour Hire charges Loading Expenses Repair Petty store Total Contractors' Total Grand Total Rate per
No. bore required to labour per foot of boring Per Foot charges bolts & Column (6, Profit& overheads 20% Rate per Ft/ Metre
complete charges material No. of Rate per Amount of T & P nuts etc. 9, 10, 11) on Column
100' (30M) installation day bag (7 x 8) No.12 (12 + 13) (5 + 14) Say
and carriage
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
1 8" 23 #VALUE! #VALUE! 0.00 0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
2 10" 24 #VALUE! #VALUE! 0.00 0.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
3 12" 25 #VALUE! #VALUE! 0.00 0.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
4 15" 27 #VALUE! #VALUE! 0.00 0.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
5 18" 27 #VALUE! #VALUE! 0.00 0.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE!
4
Daily Labour Charges for :
Daily charges for boring of tube well per 100 ft
(30 M) depth including sinking and with drawing
of casing pipe.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour for 30 M
Total #VALUE!
Sundries #### Percent #VALUE!
Total #VALUE!
1
Daily Labour Charges for :
Daily charges for borring of tube well per 100 ft
(30 M) depth including sinking and with drawing
of casing pipe. 20
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Total #VALUE!
Contractor's Profit #### Percent #VALUE!
Total #VALUE!
2
Daily Labour Charges for :
Daily charges for borring of tube well per 100 ft
(30 M) depth including sinking and with drawing
of casing pipe.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Total #VALUE!
Sundries #### Percent #VALUE!
Total #VALUE!
3
Daily Labour Charges for :
Daily charges for borring of tube well per 100 ft
(30 M) depth including sinking and with drawing
of casing pipe.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Total #VALUE!
Sundries #### Percent #VALUE!
Total #VALUE!
4
Daily Labour Charges for :
Daily charges for borring of tube well per 100 ft
(30 M) depth including sinking and with drawing
of casing pipe.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Total #VALUE!
Sundries #### Percent #VALUE!
Total #VALUE!
5
DESCRIPTION OF ITEM NO 5: Direct rotary/ reverse rotary drilling of bore for
tube wells in all type of soil except shingle, gravel
and rock.
(a) From ground level to 250 ft. below ground level.
i) 15" to 18" i/d
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Foreman for 3 shifts (One No. per shift 3.00 Nos 0.00 P. Shi -
Driller for 3 shifts (One No. per shift 3.00 Nos 0.00 P. Shi -
Helper for 3 shifts (One No. per shift) 54.00 Nos 0.00 P. Shi -
Electrician for 8 hours 1.00 No 0.00 P. Shi -
Mechanic for 3 shifts 3.00 Nos 0.00 P. Shi -
Total -
Sundries #### Percent -
Total -
Say -
6
Detail Unit Rate (British System) per Foot bore
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material ( P.O.L )
H.S.D. for rig for 24 hours ##### Ltr 0.00 Ltr -
H.S.D. for generator for 8 hours 72.64 Ltr 0.00 Ltr -
Cotton waste for rig for 24 hours 7.90 Kg RATE Kg #VALUE!
Mobil oil 22.70 Ltr 0.00 Ltr -
Mix. Expenditure L. S. -
Total #VALUE!
Machinery -
Labour -
Material (lubricate P.O.L) #VALUE!
Total #VALUE!
Contractor's Profit&overhe #### Percent #VALUE!
Total #VALUE!
7
Item No. 5 Direct rotary/ reverse rotary drilling of bore for
tube wells in all type of soil except shingle, gravel
and rock.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
8
Item No. 5 Direct rotary/ reverse rotary drilling of bore for
tube wells in all type of soil except shingle, gravel
and rock.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
9
Item No. 5 Direct rotary/ reverse rotary drilling of bore for
tube wells in all type of soil except shingle, gravel
and rock.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
10
DESCRIPTION OF ITEM NO 6: Boring for tube well in shingle, gravel and rock,
including sinking and with drawing of casing
pipe.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
11
Item No. 6 Boring for tube well in shingle, gravel and rock,
including sinking and with drawing of casing
pipe.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
12
Item No. 6 Boring for tube well in shingle, gravel and rock,
including sinking and with drawing of casing
pipe.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
13
Item No. 6 Boring for tube well in shingle, gravel and rock,
including sinking and with drawing of casing
pipe.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
14
DESCRIPTION OF ITEM NO 7: Providing strong substantially built box of deodar
wood (2nd class) 4'x2'x9' (1.22x0.76x0.228)
with compartments, lock and locking arrangement
for preserving samples of strata from bore hole.
Material
Total -
Contractor's Profit & ove #### Percent -
Total -
Labour
15
Detail Unit Rate (British System) per Job for Complete
Bore.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Total -
Sundries #### -
Total -
16
DESCRIPTION OF ITEM NO 8: Furnishing Sample of Water from Bore Hole.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bottle 2 lbs capcity 2.00 Nos 0.00 Each -
Total -
Contractor's Profit & ove #### Percent -
Total -
Labour
Taking samples of water from bore
hole including bailing or pumping. L. S. -
Sealing the water sample and
providing necessary packing etc. L. S. -
Handling charges L. S. -
Total -
Contractor's Profit & ove #### Percent -
Total -
17
9- Providing and installing Brass Strainer in Tube Well Bore Hole including Socket, special Socket, Studs
etc. complete.
1 2" 5/32" 0.00 0.00 0.00 200.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!
2 3" 5/32" 0.00 0.00 0.00 200.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!
3 4" 3/16" 0.00 0.00 0.00 150.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!
4 5" 3/16" 0.00 0.00 0.00 130.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!
5 6" 3/16" 0.00 0.00 0.00 120.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!
6 7" 3/16" 0.00 0.00 0.00 100.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!
7 8" 3/16" 0.00 0.00 0.00 80.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!
8 9" 3/16" 0.00 0.00 0.00 80.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!
9 10" 3/16" 0.00 0.00 0.00 70.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!
10 10" 1/4" 0.00 0.00 0.00 70.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!
11 12" 1/4" 0.00 0.00 0.00 70.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!
12 15" 1/4" 0.00 0.00 0.00 60.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!
13 18" 1/4" 0.00 0.00 0.00 60.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!
14 20" 1/4" 0.00 0.00 0.00 50.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!
15 22" 1/4" 0.00 0.00 0.00 50.00 #VALUE! ####### 0.00 0.00 ###### #VALUE! #VALUE! ###### #VALUE!
Contractor's Profit 20
1
2
Daily Labour Charges
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
1
Daily Labour Charges
Qty Rate
Per Unit (Rs.)Amount (Rs.)
20
Labour
Total #VALUE!
Sundries 10.00 #VALUE!
Total #VALUE!
2
10 - Providing and Installing M. S. Bail Plug in Tube Well Bore Hole (Eac
M A T E R I A L
S. Dia of Plug Rate Total Wt. of Size of Wt. of Total Wastage Total Wt. in Rate Amount
No. bore Length Per Foot Disc Bars Bars Wt. 10% Wt. Kg Per Kg Rs. Bolts &
Lbs. (Lbs.) (Lbs.) in Lbs Nuts
(3 x 4) (6 + 8) (9 + 10)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1 2" 1.50 0.00 0.00 0.14 1/4" 0.53 0.67 0.07 0.74 0.33 0.00 0.00 0.00
2 3" 1.50 0.00 0.00 0.30 1/4" 0.53 0.83 0.08 0.91 0.41 0.00 0.00 0.00
3 4" 2.00 0.00 0.00 0.51 3/8" 1.50 2.01 0.20 2.21 1.00 0.00 0.00 0.00
4 5" 2.00 0.00 0.00 1.22 3/8" 1.50 2.72 0.27 2.99 1.36 0.00 0.00 0.00
5 6" 2.00 0.00 0.00 1.72 3/4" 6.00 7.72 0.77 8.49 3.85 0.00 0.00 0.00
6 7" 2.00 0.00 0.00 2.30 3/4" 6.00 8.30 0.83 9.13 4.14 0.00 0.00 0.00
7 8" 2.00 0.00 0.00 2.97 3/4" 6.00 8.97 0.90 9.87 4.48 0.00 0.00 0.00
8 9" 2.00 0.00 0.00 3.72 3/4" 6.00 9.72 0.97 10.69 4.85 0.00 0.00 0.00
9 10" 2.00 0.00 0.00 6.23 3/4" 6.00 12.23 1.22 13.45 6.10 0.00 0.00 0.00
10 12" 2.00 0.00 0.00 8.83 3/4" 6.00 14.83 1.48 16.31 7.40 0.00 0.00 0.00
1
11 15" 2.00 0.00 0.00 13.57 3/4" 6.00 19.57 1.96 21.53 9.76 0.00 0.00 0.00
12 18" 2.00 0.00 0.00 19.34 3/4" 6.00 25.34 2.53 27.87 12.64 0.00 0.00 0.00
13 20" 2.00 0.00 0.00 23.74 3/4" 6.00 29.74 2.97 32.71 14.84 0.00 0.00 0.00
14 22" 2.00 0.00 0.00 28.60 3/4" 6.00 34.60 3.46 38.06 17.26 0.00 0.00 0.00
2
ch).
L A B O U R C O S T (Rs.)
Material Welding Cutting Total Grand Say Contra- Total Labour for Labour Total Progr- Daily Rate Say Rate Labour Compo-
Total Threading Disc Disc Total ctor's Lowering Contra- ess Charges Per Rft Per Plug Rate site
Clamp Profit Equip- ctor's Daily @ Rs. of Each Length
(5 + 14 (18 + 19) (16 + 20) 20.00 (22 + 23) ment Profit (25 + 26) #VALUE! Plug (31 x 3) (24 + 33)
+ 15) 20.00 per No. (27 + 29)
Percent
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 100 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!
0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 100 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!
0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 80 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!
0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 80 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!
0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 56 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!
0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 56 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!
0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 48 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!
0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 48 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!
0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 48 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!
0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 40 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!
3
0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 40 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!
0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 32 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!
0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 30 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!
0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 30 #VALUE! ###### #VALUE! #VALUE! ###### #VALUE!
4
11- Providing and installing PVC Strainer BSS Class "B" in Tube Well Bore Hole including Sockets and Solvents etc. complete.
S. Dia of Rate Contractor's Total Daily Labour Labour Solvent Lowering Contractor's Total Say Rate per Rft Rate per Metre
No. Strainer Per Ft Profit Progress Charges Cost Charges Profit (8 + 9 + Labour Composite Labour Composite
20.00 (3 + 4) in Ft Per Day Per Ft 20.00 10 + 11) (5 + 14)
Percent Percent
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
1 3" 0.00 0.00 0.00 200.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
2 4" 0.00 0.00 0.00 180.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
3 5" 0.00 0.00 0.00 180.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
4 6" 0.00 0.00 0.00 160.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
5 8" 0.00 0.00 0.00 128.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! 0.00 #VALUE! 0.00
6 10" 0.00 0.00 0.00 128.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
7 12" 0.00 0.00 0.00 104.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
8 14" 0.00 0.00 0.00 104.00 ####### #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
1
12- Providing and installing PVC Strainer BSS Class "D" in Tube Well Bore Hole including Sockets and Solvents etc. complete.
1 1" 0.00 0.00 0.00 200.00 ####### #VALUE! 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
2 1" 0.00 0.00 0.00 200.00 ####### #VALUE! 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
3 2" 0.00 0.00 0.00 200.00 ####### #VALUE! 0.00 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
4 3" 0.00 0.00 0.00 200.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00
5 4" 0.00 0.00 0.00 180.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00
6 5" 0.00 0.00 0.00 180.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00
7 6" 0.00 0.00 0.00 160.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00
2
13 - i - Providing and installing PVC Bail/ End Plug in Tube Well Bore Hole: BSS Class "B".
1 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
2 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
3 5" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
4 6" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
5 8" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
6 10" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
7 12" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
8 14" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
3
13 - ii Providing and installing PVC Bail/ End Plug in Tube Well Bore Hole: BSS Class "D".
1 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
2 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
3 2" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
4 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
5 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
6 5" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
7 6" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
4
14- Providing and installing M.S. blind pipe socketed/ welded joint M.S. reducer (where necessary) in
Tube Well Bore Hole including jointing/ welding with strainer etc. complete.
S. Dia of Thickness Rate Contractor's Total Daily Daily Lowering Contractor's Total Grand Rate per Rft Rate per Metre
No. Pipe of Pipe Per Ft Profit Progress Charges Charges Profit 20% Total Labour Composite Labour Composite
20.00 (4 + 5) Rs. (9 + 10) (8 + 11) (6 + 13)
Percent #VALUE!
say
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2" 1/8" 0.00 0.00 0.00 100 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
2 3" 1/8" 0.00 0.00 0.00 100 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
3 4" 1/8" 0.00 0.00 0.00 80 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
4 5" 3/16" 0.00 0.00 0.00 80 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
5 6" 3/16" 0.00 0.00 0.00 56 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
6 7" 3/16" 0.00 0.00 0.00 56 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
7 8" 3/16" 0.00 0.00 0.00 48 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
8 9" 3/16" 0.00 0.00 0.00 48 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
9 10" " 0.00 0.00 0.00 48 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
10 12" " 0.00 0.00 0.00 40 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
11 15" " 0.00 0.00 0.00 40 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
12 18" " 0.00 0.00 0.00 32 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
13 20" " 0.00 0.00 0.00 30 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
14 22" " 0.00 0.00 0.00 30 #VALUE! 0.00 0.00 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
5
6
7
8
9
10
Daily Labour Charges
3" - 6" dia
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total #VALUE!
Sundries ##### Percent #VALUE!
Total #VALUE!
1
Daily Labour Charges
8" - 14" dia
Qty Rate
Per Unit (Rs.)Amount (Rs.) 20
Labour
Total #VALUE!
Sundries ##### Percent #VALUE!
Total #VALUE!
2
Daily Labour Charges
11/4" - 3" dia
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total #VALUE!
Sundries ##### Percent #VALUE!
Total #VALUE!
3
Daily Labour Charges
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total #VALUE!
Sundries ##### Percent #VALUE!
Total #VALUE!
4
15- Providing and installing PVC blind pipe BSS Class "B" in Tube Well Bore Hole including Sockets and
Solvents and jointing with strainer etc. complete.
S. Dia of Rate Contractor's Total Daily Labour Labour Lowering Solvent Total Contractor's Total Rate per Rft Rate per Metre
No. Strainer Per Ft Profit Progress Charges Per Ft Charges Profit (8 + 11 Labour Composite Labour Composite
20.00 (3 + 4) Per Day (9 + 10) 20.00 + 12) (5 + 13)
Percent Percent
1 2 3 4 5 6 7 8 9 10 11 4 13 14 15 16 16
1 3" 0.00 0.00 0.00 200 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!
2 4" 0.00 0.00 0.00 180 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!
3 5" 0.00 0.00 0.00 180 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!
4 6" 0.00 0.00 0.00 160 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!
5 8" 0.00 0.00 0.00 128 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!
6 10" 0.00 0.00 0.00 128 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!
7 12" 0.00 0.00 0.00 104 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!
8 14" 0.00 0.00 0.00 104 ###### ###### 0.00 0.00 0.00 0.00 ##### ##### #VALUE! ###### #VALUE!
20
1
Daily Labour Charges
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
1
Daily Labour Charges
Qty Rate
Per Unit (Rs.)Amount (Rs.)
Labour
Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
2
16- Providing and installing PVC blind pipe BSS Class "D" in Tube Well Bore Hole including Sockets and Solvents
and jointing with strainer etc. complete.
S. Dia of Rate Contractor's Total Daily Daily Labour Solvent Lowering Total Contractor's Total Rate per Rft Rate per Metre
No. Strainer Per Ft Profit Progress Charges Rate Charges Profit (8 + 11 Labour Composite Labour Composite
20.00 (3 + 4) Per Ft (9 + 10) 20.00 12) (5 + 13)
Percent Percent
1 2 3 4 5 6 7 8 9 10 11 4 13 14 15 16 17
1 1" 0.00 0.00 0.00 260 ###### ###### 0.00 0.00 0.00 0.00 ###### #### #VALUE! ###### #VALUE!
2 1" 0.00 0.00 0.00 260 ###### ###### 0.00 0.00 0.00 0.00 ###### #### #VALUE! ###### #VALUE!
3 2" 0.00 0.00 0.00 240 ###### ###### 0.00 0.00 0.00 0.00 ###### #### #VALUE! ###### #VALUE!
4 3" 0.00 0.00 0.00 200 ###### ###### 0.00 0.00 0.00 0.00 ###### #### #VALUE! ###### #VALUE!
5 4" 0.00 0.00 0.00 180 ###### ###### 0.00 0.00 0.00 0.00 ###### #### #VALUE! ###### #VALUE!
6 5" 0.00 0.00 0.00 180 ###### ###### 0.00 0.00 0.00 0.00 ###### #### #VALUE! ###### #VALUE!
7 6" 0.00 0.00 0.00 160 ###### ###### 0.00 0.00 0.00 0.00 ###### #### #VALUE! ###### #VALUE!
1
Contractor's Profit
2
Daily Labour Charges
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
1
Daily Labour Charges
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Total #VALUE!
Sundries 10.00 Percent #VALUE!
Total #VALUE!
2
DESCRIPTION OF ITEM NO 17: Testing and developing of tube well of size
6" (150mm) inner dia and above Continuously.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Say -
3
Item No. 17 Testing and developing of tube well of size
6" innner dia and above Continuously.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Say -
4
DESCRIPTION OF ITEM NO 18: Shrouding with graded pea gravel 3/8" - 1/8"
(10-3mm) around tube well in bore hole.
Qty Rate
Analysis for 100 Cft Per Unit (Rs.) Amount (Rs.)
Material
Bajri 3/8" - 1/8" (10-3mm) Bajri 3/8" - 1/8 ##### Cft 0.00 % Cft -
Wastage 5% Wastage 5%
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Washing and Pouring bag
Skilled Coolies 3.30 Nos 0.00 P. Day -
Unskilled Coolies 1.00 No 0.00 P. Day -
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
5
19- Laying, cutting, jointing, testing and disinfecting cast iron pipe line in trenches with spigot and socket
caulked lead joint, including cost of materials, such as lead, yarn, etc. complete in all respects.
S. nterna Weight of Weight of Carriage of Lowering Cutting Pluging Testing Jointing Total Composite Composite
No. dia of 18' length 100' length 100' pipe into ends with and with lead charges for rate Per Ft rate Per
pipe of pipe in of pipe in from field trenches chipping, temporary disinfecting joint 100' (30 M) Metre
lbs ton store to site strin- ging & fini- shing wooden (5 + 6 + 7 +
lead four laying to surface to plug +8+9+
chain @ Rs. correct uniform 10)
alignment finish
Tons and grade
1 2 3 4 5 6 7 8 9 10 11 12 13
1 3" 170.00 0.429 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 4" 190.00 0.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 5" 324.00 0.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 6" 410.00 1.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 8" 591.00 1.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 10" 794.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 12" 1018.00 2.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 15" 1389.00 3.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 18" 1834.00 4.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1
19 - a - Lowering into trenches, stringing and laying C.I. pipe line to correct alignment and gradient.
S. nterna LABOUR
No. dia Daily Daily Amount per Rate 100 ft
Progress Charges 100 ft Analysis for daily charges
6 10" 175 0.00 0.00 - Contractor's Profit & Overheads 20.00 Percent -
7 12" 150 0.00 0.00 - Total 0.00
2
19 - bCutting cast iron pipe, chipping & finishing the face to uniform finish = Cut at every 200ft (60 M)
For 200' (60 M)
S. I/D Labour for Cutting & finishing Rate per
No. of No. of Daily Rate per 100 ft
Pipe cut P. day Charges 200 ft per cut
per cut
1 2 3 4 5 6
4 6" 3.00 0.00 0.00 0.00 Unskilled Cooly 2 Nos 0.00 0.00
3
19 - c Providing and fixing temporary wooden tapered plug of hard wood to each end of pipe line.
Assume for 500 ft. Rate for 100 ft.
S. Size PLUG LABOUR FOR MAKING PLUG LABOUR FOR FIXING Grand Rate for
No. of Area of Length Content Rate Per Amount Daily Daily Amount L. S. Sundries Total Total 100'
plug plug in Cft Progress Charges 10.00 for 500'
Cft (5 X 6) in No. (9 / 8) (11+12) (15+10
+ 7)
1 2 3 4 5 6 7 8 9 10 11 12 13 16 17 18
9x(3)2
1 3" 4x144 0.50 0.02 0.00 0.00 34.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rate of Hard Wood
9x(4)2
2 4" 4x144 0.50 0.04 0.00 0.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Hard Wood
9x(5)2 1 Cft @
3 5" 4x144 0.50 0.07 0.00 0.00 25.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs. 0.00 0.00
Contractor's
9x(6)2 Profit &
4 6" 4x144 0.50 0.10 0.00 0.00 19.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Overheads 20.00 0.00
9x(8)2
5 8" 4x144 0.50 0.17 0.00 0.00 15.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
2
9x(10)
6 10" 4x144 0.75 0.41 0.00 0.00 12.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Daily Charges
9x(12)2 Carpenter
7 12" 4x144 0.75 0.59 0.00 0.00 9.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1 0.00 0.00
9x(15)2 Turner
8 15" 4x144 1.00 1.23 0.00 0.00 7.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1 0.00 0.00
9x(18)2
9 18" 4x144 1.00 1.77 0.00 0.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Sundries 10.00 0.00
Total 0.00
Contractor's
Profit 20.00 0.00
Total 0.00
4
19 - d Testing and disinfecting C.I. Pi
Assume for 1000' (300 M) Rate for 100 ft.
S. I/D of Volume Amount Disin- Amount Hire Total Contra- Total LABOUR Rate Charges
No. pipe in of Water @ Rs fecting @ Rs. Charges ctor's Plugging Labour for Total for 200 Rft
Inch required 0.00 Agent 0.00 of testing (7 + 6 Profit (8 + 9) of Pipe testing &
in Gallon Per Lbs/Kg Per Lbs/Kg operatus + 4) 20.00 disinfecting (11 + 12)
Gallons Percent
1 2 3 4 5 6 7 8 9 10 11 12 13 16
1 3" 310.00 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Mechanic 1 No. 0.00 0.00
2 4" 720.00 0.00 1.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Coolies 2 Nos 0.00 0.00
3 5" 850.00 0.00 1.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
4 6" 1830.00 0.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Sundries 10.00 Percent -
5 8" 2180.00 0.00 3.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
6 10" 3410.00 0.00 5.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Contractor's 20.00 Percent -
7 12" 4910.00 0.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Rate per
8 15" 8730.00 0.00 14.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 100 Rft 0.00
9 18" 11000.00 0.00 18.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5
19 - e Jointing cast iron pipe line in trenches with spigot and socket. Caulked lead joints
including cost of material such as lead, yarn etc., complete in all respect.
1 2 3 4 5 6 7 8 9 10 11 12 13 16 17 18 18
1 3" 4.10 0.00 0.00 0.25 0.00 0.00 0.00 0.00 0.00 0.00 0.15 0.00 - - -
2 4" 5.20 0.00 0.00 0.38 0.00 0.00 0.00 0.00 0.00 0.00 0.19 0.00 - - -
3 5" 6.30 0.00 0.00 0.44 0.00 0.00 0.00 0.00 0.00 0.00 0.24 0.00 - - -
4 6" 7.90 0.00 0.00 0.44 0.00 0.00 0.00 0.00 0.00 0.00 0.28 0.00 - - -
5 8" 10.80 0.00 0.00 0.63 0.00 0.00 0.00 0.00 0.00 0.00 0.30 0.00 - - -
6 10" 15.00 0.00 0.00 0.75 0.00 0.00 0.00 0.00 0.00 0.00 0.50 0.00 - - -
7 12" 17.30 0.00 0.00 1.06 0.00 0.00 0.00 0.00 0.00 0.00 0.59 0.00 - - -
8 15" 23.00 0.00 0.00 1.50 0.00 0.00 0.00 0.00 0.00 0.00 0.76 0.00 - - -
9 18" 31.50 0.00 0.00 2.07 0.00 0.00 0.00 0.00 0.00 0.00 0.99 0.00 - - -
Daily Charges
Plumber 1 No 0.00 0.00 Sundires 0.00
Cooly 3 Nos 0.00 0.00 Total 0.00
Assistant Plumber (skilled cooly) 1 No 0.00 0.00 Contractor's Profit & Overheads 0.00
Total 0.00 Total 0.00
6
20- Laying cutting, jointing, testing and disinfecting cast iron pipe line in trenches with flanged and flanged
complete in all respects.
S. Internal Weight of Weight Carriage of Lowering into Cutting ends Pluging Testing and Jointing Total charges Composite Composite
No. dia of 12' length of 100' 100' pipe trenches strin- chipping, fini- with disinfecting with lead for 100' rate per Ft rate per
pipe of pipe in length from field storeging & laying to shing surface temporary joint (30 M) Metre
lbs of pipe to site lead correct alignmen to uniform wooden plug (5 + 6 + 7 +
in ton. four chain Ton and grade finish 8 + 9 + 10)
@ of Rs.
1 2 3 4 5 6 7 8 9 10 11 12 13 say say
1 3" - 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
2 4" - 0.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
3 5" - 0.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
4 6" - 1.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
5 8" - 1.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
6 10" - 2.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
7 12" - 2.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
8 15" - 3.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
9 18" - 4.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - -
20 - a Lowering into trenches, stringing and laying C.I. pipe line to correct alignment and gradient.
S. Internal LABOUR
No. dia Daily Daily Amount per Rate 100 ft
Progress Charges 100 ft Analysis for daily charges
1
20 - b Cutting cast iron pipe, chipping & finishing the face to uniform finish = Cut at every 200ft (60 M)
For 200' (60 M)
S. I/D Labour for Cutting & finishing Rate per
No. of No. of Daily Rate per 100 ft
Pipe cut P. day Charges 200 ft per cut
per cut
1 2 3 4 5 6
1 3" 8.00 0.00 0.00 0.00 Analysis of Daily Charges
2 4" 6.00 0.00 0.00 0.00 LABOUR
3 5" 4.00 0.00 0.00 0.00 Pipe fitter 1 No 0.00 0.00
4 6" 3.00 0.00 0.00 0.00 Unskilled Cooly 2 Nos 0.00 0.00
5 8" 2.00 0.00 0.00 0.00 Total 0.00
6 10" 1.50 0.00 0.00 0.00 Sundries 10.00 Percent -
7 12" 1.25 0.00 0.00 0.00 Total 0.00
8 15" 1.10 0.00 0.00 0.00 Contractor's Profit & Overheads 20.00 Percent -
9 18" 1.00 0.00 0.00 0.00 0.00
20 - c - Providing and fixing temporary wooden tapered plug of hard wood to each end of pipe line.
Detail 500' Rate for 100'
S. Size PLUG LABOUR FOR MAKING PLUG LABOUR FOR FIXING Grand Rate for
No. of Area of Length Contant Rate Per Amount Daily Daily Amount L. S. Sundries Total Contra- Total Total 100'
plug plug in Cft Progress Charges 10.00 ctor's for 500'
Cft (5 X 6) in No. (9 / 8) (11+12) profit (13+14) (15+10
20.00 + 7)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
x(3)2
1 3" 4x144 0.50 0.02 0.00 0.00 34.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Daily Charges
x(4)2
2 4" 4x144 0.50 0.04 275.00 11.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x(5)2 Hard Wood
3 5" 4x144 0.50 0.07 275.00 19.25 25.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Cft @ Rs. 0.00 0.00
x(6)2
4 6" 4x144 0.50 0.10 275.00 27.50 19.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Contractor's Profit & Overheads 20.00 0.00
x(8)2
5 8" 4x144 0.50 0.17 275.00 46.75 15.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
x(10)2
6 10" 4x144 0.75 0.41 275.00 112.75 12.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x(12)2
7 12" 4x144 0.75 0.59 275.00 162.25 9.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Carpenter 1 No. 0.00 0.00
x(15)2
8 15" 4x144 1.00 1.23 275.00 338.25 7.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Turner 1 No. 0.00 0.00
x(18)2
9 18" 4x144 1.00 1.77 275.00 486.75 5.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Sundries 10.00 Percent -
Total 0.00
Contractor's
Profit &
Overheads 20.00 Percent -
Total 0.00
2
20 - d - Testing and disinfecting C.I. Pipe.
Assume for 1000' (300 M) Rate for 100' Rate for 10'
S. I/D of Volume Amount Disin- Amount Hire Total Contra- Total LABOUR Composite Rate for Rate Charges
No. pipe in of Water @ Rs fecting @ Rs Charges ctor's Plugging Labour for Total for 1000 Rft 100' for 200 Rft
Inch required - Agent 0.00 of testing (7 + 6 Profit (8 + 9) of Pipe testing &
in Gallon Per Lbs/Kg Per Lbs/Kg operatus + 4) 20.00 disinfecting (11+12) (10 + 13)
Gallons Percent
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 3" 310.00 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Mechanic 1 No. 0.00 0.00
2 4" 720.00 0.00 1.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Coolies 2 Nos 0.00 0.00
3 5" 850.00 0.00 1.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
4 6" 1830.00 0.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Sundries 10.00 Percent -
5 8" 2180.00 0.00 3.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Contractor's
Profit &
6 10" 3410.00 0.00 5.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Overheads 20.00 Percent -
7 12" 4910.00 0.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Rate per 100
8 15" 8730.00 0.00 14.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rft 0.00
9 18" 11000.00 0.00 18.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
20 - e Laying, cutting, jointing, testing & disinfecting C.I. pipe line in trenches with flanged &
flanged joint complete in all respects.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 18
1 3" 5/8" 2" 4.00 0.00 0.00 0.46 0.00 0.00 0.00 0.00 11.00 0.00 0.00 0.00 0.00 0.00 0.00
2 4" 5/8" 2" 4.00 0.00 0.00 0.61 0.00 0.00 0.00 0.00 10.00 0.00 0.00 0.00 0.00 0.00 0.00
3 5" 5/8" 3" 6.00 0.00 0.00 1.00 24.00 24.00 1.20 25.20 9.00 0.00 0.00 0.00 0.00 0.00 0.00
4 6" 5/8" 3" 6.00 0.00 0.00 1.18 28.32 28.32 1.42 29.74 8.00 0.00 0.00 0.00 0.00 0.00 0.00
5 8" 3/4" 3" 8.00 0.00 0.00 1.20 28.80 28.80 1.44 30.24 8.00 0.00 0.00 0.00 0.00 0.00 0.00
6 10" 3/4" 3" 12.00 0.00 0.00 1.86 44.86 44.86 2.24 47.10 6.00 0.00 0.00 0.00 0.00 0.00 0.00
7 12" 3/4" 3" 12.00 0.00 0.00 2.50 60.24 60.24 3.01 63.25 5.00 0.00 0.00 0.00 0.00 0.00 0.00
8 15" 7/8" 4" 12.00 0.00 0.00 2.84 69.36 69.36 3.47 72.83 3.00 0.00 0.00 0.00 0.00 0.00 0.00
9 18" 7/8" 4" 12.00 0.00 0.00 3.42 82.08 82.08 4.10 86.18 2.00 0.00 0.00 0.00 0.00 0.00 0.00
Daily Charges
Plumber 1 No 0.00 Sundires 10.00 Percent 0.00
Cooly 1 No 0.00 Total 0.00
0.00 Contractor's Profit & Overheads 20.00 Percent 0.00
Total 0.00
3
21-
complete in all respects.
S. Internal Weight of Weight Carriage of Lowering into Cutting ends Pluging Testing and Jointing Total charges Composite Composite
No. dia of 12' length of 100' 100' pipe trenches strin- chipping, fini- with disinfecting with lead for 100' rate per Ft rate per
pipe of pipe in length from field store ging & laying to shing surface temporary joint (30 M) Metre
lbs of pipe to site lead correct alignment to uniform wooden plug (5 + 6 + 7 +
in ton. four chain Ton and grade finish 8 + 9 + 10)
@ of Rs.
1 2 3 4 5 6 7 8 9 10 11 12 13
1 3" - 0.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 4" - 0.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 5" - 0.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 6" - 1.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 8" - 1.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 10" - 1.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 12" - 2.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 15" - 3.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 18" - 4.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
21 - a Lowering into trenches, stringing and laying C.I. pipe line to correct alignment and gradient.
S. Internal LABOUR
No. dia Daily Daily Amount per Rate 100 ft
Progress Charges 100 ft Analysis for daily charges
1
21 - b Cutting cast iron pipe, chipping & finishing the face to uniform finish = Cut at every 200ft (60 M)
For 200' (60 M)
S. I/D Labour for Cutting & finishing Rate per
No. of No. of Daily Rate per 100 ft
Pipe cut P. day Charges 200 ft per cut
per cut
1 2 3 4 5 6
1 3" 8.00 0.00 0.00 0.00 Analysis of Daily Charges
2 4" 6.00 0.00 0.00 0.00 LABOUR
3 5" 4.00 0.00 0.00 0.00 Pipe fitter 1 No 0.00 0.00
4 6" 3.00 0.00 0.00 0.00 Unskilled Cooly 2 Nos 0.00 0.00
5 8" 2.00 0.00 0.00 0.00 Total 0.00
6 10" 1.50 0.00 0.00 0.00 Sundries 10.00 Percent -
7 12" 1.25 0.00 0.00 0.00 Total 0.00
8 15" 1.10 0.00 0.00 0.00 Contractor's Profit & Overheads 20.00 Percent -
9 18" 1.00 0.00 0.00 0.00 0.00
21 - c - Providing and fixing temporary wooden tapered plug of hard wood to each end of pipe line.
Detail 500' Rate for 100'
S. Size PLUG LABOUR FOR MAKING PLUG LABOUR FOR FIXING Grand Rate for
No. of Area of Length Contant Rate Per Amount Daily Daily Amount L. S. Sundries Total Contra- Total Total 100'
plug plug in Cft Progress Charges 10.00 ctor's for 500'
Cft (5 X 6) in No. (9 / 8) (11+12) profit (13+14) (15+10
20.00 + 7)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
x(3)2
1 3" 4x144 0.50 0.02 0.00 0.00 34.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Daily Charges
x(4)2
2 4" 4x144 0.50 0.04 0.00 0.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x(5) 2
Hard Wood
3 5" 4x144 0.50 0.07 0.00 0.00 25.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Cft @ Rs. 0.00 0.00
x(6)2
4 6" 4x144 0.50 0.10 0.00 0.00 19.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Contractor's Profit & Over 20.00 0.00
x(8)2
5 8" 4x144 0.50 0.17 0.00 0.00 15.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
x(10)2
6 10" 4x144 0.75 0.41 0.00 0.00 12.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x(12)2
7 12" 4x144 0.75 0.59 0.00 0.00 9.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Carpenter 1 No. 0.00 0.00
x(15)2
8 15" 4x144 1.00 1.23 0.00 0.00 7.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Turner 1 No. 0.00 0.00
x(18)2
9 18" 4x144 1.00 1.77 0.00 0.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Sundries 10.00 Percent -
Total 0.00
Contractor's
Profit &
Overheads 10.00 Percent -
Total 0.00
2
20 - d - Testing and disinfecting C.I. Pipe.
Assume for 1000' (300 M) Rate for 100'
S. I/D of Volume Amount Disin- Amount Hire Total Contra- Total LABOUR Composite Rate for Rate Charges
No. pipe in of Water @ Rs fecting @ Rs. Charges ctor's Plugging Labour for Total for 1000 Rft 100' for 200 Rft
Inch required - Agent 0.00 of testing (7 + 6 Profit (8 + 9) of Pipe testing &
in Gallon Per Lbs/Kg Per Lbs/Kg operatus + 4) 20.00 disinfecting (11+12) (10 + 13)
Gallons Percent
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 3" 310.00 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Mechanic 1 No. 0.00 0.00
2 4" 720.00 0.00 1.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Coolies 2 Nos 0.00 0.00
3 5" 850.00 0.00 1.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
4 6" 1830.00 0.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Sundries 10.00 Percent -
5 8" 2180.00 0.00 3.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Contractor'
s Profit &
6 10" 3410.00 0.00 5.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Overheads 10.00 Percent -
7 12" 4910.00 0.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Rate per
8 15" 8730.00 0.00 14.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 100 Rft 0.00
9 18" 11000.00 0.00 18.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3
21 Laying, cutting, jointing, testing & disinfecting cast iron pipe line in trenches with tyton joints
complete in all respect.
1 2 3 4 5 6 7 8
1 3" 0.00 0.00 0.00 0.00 0.00
2 4" 0.00 0.00 0.00 0.00 0.00
3 5" 0.00 0.00 0.00 0.00 0.00
4 6" 0.00 0.00 0.00 0.00 0.00
5 8" 0.00 0.00 0.00 0.00 0.00
6 10" 0.00 0.00 0.00 0.00 0.00
7 12" 0.00 0.00 0.00 0.00 0.00
8 15" 0.00 0.00 0.00 0.00 0.00
9 18" 0.00 0.00 0.00 0.00 0.00
4
21 Laying,cutting,jointing,testing and disinfecting Cast Iron Pipe line in trenches with Tyton joints,complete in all respect.
S. Internal eight of 10 Carriage of Lowering into Cutting ends Pluging Testing and Jointing Total charges Composite Composite
No. dia of length of 100' pipe trenches strin- chepping, fini- with disinfecting with rubber for 100' rate Per Ft rate Per
pipe pipe in ton from field store ging & laying to shing surface temporary ring (30 M) Metre
to site lead correctalignment to uniform wooden plug (4 + 5 + 6 +
four chain @ and grade finish 7 + 8 +9)
Rs. Tons
1 2 3 4 5 6 7 8 9 10 11 12
1 3" 0.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 4" 0.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 5" 0.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 6" 1.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 8" 1.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 10" 1.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 12" 2.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 15" 3.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 18" 4.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5
21 - a - Lowering into trenches, stringing and laying C.I. pipe line to correct alignment and gradient.
S. Internal LABOUR
No. dia Daily Daily Amount per Rate 100 ft
Progress Charges 100 ft Analysis for daily charges
6
21 - b Cutting cast iron pipe, chipping & finishing the face to uniform finish = Cut at every 200ft (60 M)
For 200' (60 M)
S. I/D Labour for Cutting & finishing Rate per
No. of No. of Daily Rate per 100 ft
Pipe cut P. day Charges 200 ft per cut
per cut
1 2 3 4 5 6
4 6" 3.00 0.00 0.00 0.00 Unskilled Cooly 2 Nos 0.00 0.00
8 15" 1.10 0.00 0.00 0.00 Contractor's Profit & Overheads 20.00 Percent -
7
22 Providing, laying, cutting, jointing, testing and disinfecting GI pipeline in trenches, with socket joint, using GI pipes of BSS 1387 - 1967
complete in all respects, with specials and valves.
(I) Light Quality
Length of pipe 18' (5.4 M). Rate for 100'
Material Labour Rate Rate per Metre
S. Dia of Rate per Adust- Wastage Special Total Contra- Total No of Prog- Daily Cost Total Total Carr- Testing Labour Compo- Labour Composite Labour Composite
No. pipe in 100' for orum 2% 10% ctor's Joints ress Charges per jointing 13 + 14 iage site for for Per ft for per ft
Inche light 1% 3+4+ Profit in line Joint material x 10 15 + 16 100'
quality 5+6 20.00 + 17 9 + 18 18 / 100 19 / 100
Perfect
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 " 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 40.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00
2 " 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 35.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00
3 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 2" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 28.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 2" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 28.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 25.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 23.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total 0.00
Contractor's Profit & Overheads 20.00 Percent - Sundries 20.00 Percent -
Total 0.00 Total 0.00
1
22 Providing, laying, cutting, jointing, testing and disinfecting GI pipeline in trenches, with socket joint, using GI pipes of BSS 1387 - 1967
complete in all respects, with specials and valves.
(ii) Medium Quality
Length of pipe 18' (5.4 20 Rate for 100'
Material Labour Rate Rate per Metre
S. Dia of Rate per Adust- Wastage Special Total Contra- Total No of Prog- Daily Cost Total Total Carr- Testing Labour Compo- Labour Composite Labour Composite
No. pipe in 100' for orum 2% 10% ctor's Joints ress Charges per jointing 13 + 14 iage site for for Per ft for per ft
Inche light 1% 3+4+ Profit in line Joint material x 10 15 + 16 100'
quality 5+6 20.00 + 17 9 + 18 18 / 100 19 / 100
Perfect
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 " 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 40.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00
2 " 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 35.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00
3 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 2" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 28.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 2" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 28.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 25.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 23.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10 5" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 6" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total 0.00
Contractor's Profit & Overheads 20.00 Percent - Sundries 10.00 Percent -
Total 0.00 Total 0.00
2
3
22 Providing, laying, cutting, jointing, testing and disinfecting GI pipeline in trenches, with socket joint, using GI pipes of BSS 1387 - 1967
complete in all respects, with specials and valves.
(iii Heavy Quality
Length of pipe 18' (5.4 M). Rate for 100'
Material Labour Rate Rate per Metre
S. Dia of Rate per Adust- Wastage Special Total Contra- Total No of Prog- Daily Cost Total Total Carr- Testing Labour Compo- Labour Composite Labour Composite
No. pipe in 100' for orum 2% 10% ctor's Joints ress Charges per jointing 13 + 14 iage site for for Per ft for per ft
Inche light 1% 3+4+ Profit in line Joint material x 10 15 + 16 100'
quality 5+6 20.00 + 17 9 + 18 18 / 100 19 / 100
Perfect
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 " 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 40.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00
2 " 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 35.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00
3 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 1" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 2" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 28.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 2" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 28.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 25.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 23.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10 5" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 6" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total 0.00
Contractor's Profit & Overheads 20.00 Percent - Sundries 10.00 Percent -
Total 0.00 Total 0.00
4
5
6
7
8
9
10
23 Providing laying, cutting, jointing, testing & disinfecting AC pipeline of BSS with "B" Class working pressure pipe in
trenches with cement joint & rubbering complete in all respect.
Material Labour for 100' Rate per 100 Ft Rate per Ft Rate per Metre
S. Dia Cost of Wast- Total Contra- Total Carriage Grand Lowering Cutting Cleaning Testing Plugging Labour Compo- Labour Composite Labour Composite
No. of pipe with age ctor's for 100' Per ft Total into end end of and wooden site for for per
pipe coment 2% (3 + 4) Profit AC pipe length for 100 Ft trenches pipe disinf- plug Per ft ft
joint & 20.00 (5 + 6) (4 chain) & laying ecting 10 + 16
rubber Percent
ring
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 6" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 8" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 10" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 12" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 14" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 16" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 18" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10 20" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 24" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1
24 Providing laying, cutting, jointing, testing & disinfecting AC pipeline of BSS with "C" Class working pressure pipe in
trenches with cement joint & rubbering complete in all respect.
Material Labour for 100' Rate per 100 Ft Rate per Ft Rate per Metre
S. Dia Cost of Wast- Total Contra- Total Carriage Grand Lowering Cutting Cleaning Testing Plugging Labour Compo- Labour Composite Labour Composite
No. of pipe with age ctor's for 100' Per ft Total into end end of and wooden site for for per
pipe coment 2% (3 + 4) Profit AC pipe length for 100 Ft trenches pipe disinf- plug Per ft ft
joint & 20.00 (5 + 6) (4 chain) & laying ecting 10 + 16
rubber Percent
ring 20
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 6" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 8" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 10" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 12" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 14" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 16" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 18" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10 20" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 24" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2
25 Providing laying, cutting, jointing, testing & disinfecting AC pipeline of BSS with "D" Class working pressure pipe in
trenches with commet joint & rubbering complete in all respect.
Material Labour for 100' Rate per 100 Ft Rate per Ft Rate per Metre
S. Dia Cost of Wast- Total Contra- Total Carriage Grand Lowering Cutting Cleaning Testing Plugging Labour Compo- Labour Composite Labour Composite
No. of pipe with age ctor's for 100' Per ft Total into end end of and wooden site for for per
pipe coment 2% (3 + 4) Profit AC pipe length for 100 Ft trenches pipe disinf- plug Per ft ft
joint & 20.00 (5 + 6) (4 chain) & laying ecting 10 + 16
rubber Percent
ring
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 3" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 4" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 6" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 8" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 10" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 12" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 14" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 16" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 18" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10 20" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3
re
4
re
5
re
6
23.Cleaning pipe placing rubber in position pressing with assembling machine, of AC pipe.
1 2 3 4 5 6
1 3" 36.00 0.00 0.00 0.00 0.00
2 4" 32.00 0.00 0.00 0.00 0.00 machine, and jointing.
3 6" 28.00 0.00 0.00 0.00 0.00 LABOUR
4 8" 24.00 0.00 0.00 0.00 0.00 Plumber 1 No 0.00 0.00
5 10" 20.00 0.00 0.00 0.00 0.00 Skilled Cooly 1 No 0.00 0.00
6 12" 16.00 0.00 0.00 0.00 0.00 Total 0.00
7 14" 14.00 0.00 0.00 0.00 0.00 Sundries 10.00 Percent 0.00
8 16" 13.00 0.00 0.00 0.00 0.00
9 18" 12.00 0.00 0.00 0.00 0.00 Total 0.00
10 20" 10.00 0.00 0.00 0.00 0.00 Contractor's Profit & Overheads 20.00 Percent 0.00
11 24" 8.00 0.00 0.00 0.00 0.00 0.00
1
23 - Lowering into trenches, stringing and laying to correct alignment AC pipe "Class B" etc.
1 2 3 4 5
9 18" 2.555 0.00 0.00 Contractor's Profit & Overheads 20 20.00 0.00
2
23 Providing, laying, cutting, jointing testing & disinfecting A.C. pipe line of BSS with "B Class" working
pressure pipe in trenches with cement joint and rubber ring complete in all respect.
Detail for 1000' (Disinfecting and testing Rate
rate for 100'
S. Dia Volume of Amount Disin- Amount Hire Total Contra- Total Labour Per Joint Composite Composite Composite Rate
# of Water in @ Rs fecting @ Rs. Charges ctor's Plugging Labour Total rate for rate for Rate per Rate per
pipe P. Gallon 0 agent 0 of testing 4+6 Profit 8+9 of pipe for testing ft % ft. Rft Metre
Per in Lbs Per apparatus +7 20.00 and disin- 11 + 12 10 + 13
Gallons Lbs Percent fecting
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
1 3" 310.00 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
2 4" 720.00 0.00 1.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
3 6" 1820.00 0.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
4 8" 2180.00 0.00 3.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
5 10" 3410.00 0.00 5.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
6 12" 4910.00 0.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
7 14" 6810.00 0.00 11.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
8 16" 8710.00 0.00 14.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
9 18" 11000.00 0.00 18.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
10 20" 13600.00 0.00 22.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
11 24" 19600.00 0.00 32.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 -
Total 0.00
1
Providing and fixing temporary wooden plug.
Assume for 500' Rate for 100'
S. Size PLUG MATERIAL LABOUR FOR MAKING PLUG LABOUR FOR FIXING
# of Area of Length Rate Contents Amount Daily Daily Amount L.S. Sundries Total Contra- Total Grand Rate Rate
pipe Plug Sft per Cft in Cft Progress Rate 20 10 ctor's Total for 100' per Metre
5x6 in No. 9/8 Percent Profit 13 + 14 for 500'
20 7 + 10
Percent + 15
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
9x(3)2
1 3" 4x144 0.50 0.00 0.02 0.00 34.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Daily Charges
9x(4)2
2 4" 4x144 0.50 0.00 0.04 0.00 30.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Contractor'
9x(8)2 s Profit &
4 8" 4x144 0.50 0.00 0.17 0.00 15.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Overheads 20.00 0.00
9x(10)2
5 10" 4x144 0.75 0.00 0.41 0.00 12.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
9x(12)2
6 12" 4x144 0.75 0.00 0.59 0.00 9.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9x(14)2 Carpenter
7 14" 4x144 0.75 0.00 1.07 0.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1 No. 0.00 0.00
9x(16)2 Turner
8 16" 4x144 1.00 0.00 1.40 0.00 7.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1 No. 0.00 0.00
9x(18)2
9 18" 4x144 1.00 0.00 1.77 0.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
9x(20)2
10 20" 4x144 1.00 0.00 2.18 0.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Sundries 20.00 0.00
9x(20)2
11 24" 4x144 1.25 0.00 3.93 0.00 3.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
Contractor'
s Profit &
Overheads 20.00 0.00
Total 0.00
2
Lowering into trenches, stringing and laying to correct alignment AC pipe "Class D" etc.
1 2 3 4 5
1 3" 0.500 0.00 0.00 Lowering into trenches stringing and laying to correct alignment.
2 4" 0.515 0.00 0.00 Daily Labour Charges
3 6" 0.703 0.00 0.00
4 8" 0.974 0.00 0.00 Plumber 1 No 0.00 0.00
5 10" 1.289 0.00 0.00 Unskilled Cooly 2 Nos 0.00 0.00
6 12" 1.673 0.00 0.00 Total 0.00
7 14" 1.920 0.00 0.00 Sundries 10 Percent 0.00
8 16" 2.157 0.00 0.00 Total 0.00
9 18" 2.555 0.00 0.00 Contractor's Profit & Overheads 20 Percent 0.00
10 20" 2.981 0.00 0.00 0.00
11 24" 3.480 0.00 0.00
3
26 Providing, laying cutting jointing testing and disinfecting PVC pipeline of BSS with Class "B" working
pressure pipe in pipes trenches complete in all respect.
Assume for 500' Rate for P. ft
S. Dia MATERIAL LABOUR Rate per 100' Rate per Rft Rate per Metre
No. of Rate Wastage Total Contra- Total Weight Rate Amount Contra- Total Labour Total Labour Composite Labour Composite Labour Composite
pipe for 100' 2% ctor's in of ctor's as per for 100' for 100' rate rate rate rate
Profit (5 + 6) Kg Lubricant (8 x 9) Profit (10 + 11) detail (12 +13) (7 + 15)
20.00 in Kg 20.00
Percent Percent
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 3" 0.00 0.00 0.00 0.00 0.00 0.303 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
2 4" 0.00 0.00 0.00 0.00 0.00 0.339 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
3 5" 0.00 0.00 0.00 0.00 0.00 0.464 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
4 6" 0.00 0.00 0.00 0.00 0.00 0.544 0.00 0.00 0.00 0.00 20.00 20.00 ##### 20.00 0.20 0.20 0.66 0.66
5 8" 0.00 0.00 0.00 0.00 0.00 0.789 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
6 10" 0.00 0.00 0.00 0.00 0.00 0.865 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
7 12" 0.00 0.00 0.00 0.00 0.00 1.037 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
8 14" 0.00 0.00 0.00 0.00 0.00 1.179 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
1
Labour for laying, cutting, jointing, pipeline in trenches with PVC pipes of BSS with
"B" Class working pressure, complete in all respect.
Rate for 100 ft
S. # Dia CarriageLAYING, FIXING, CUTTING, JOINTING Testing Total Rate
of for lead Time for Daily Amount & for 100'
pipe 4 chains 100' Expenses Disinfecting 6+7
1 2 3 4 5 6 7 8 9
2
3
4
27 Providing, laying, cutting, jointing, testing & disinfecting pipeline in trenches with PVC pipes of BSS with "D"
Class working pressure, complete in all respect.
Unit of rate per ft.
S. Dia Material Labour Rate per 100' Rate per Ft Rate per Metre
# of Rate for Wastage Total Contra- Total Lubri- Rate Amount Contra- Total Labour Total Labour Composite Labour Composite Labour Composite
pipe 100' 2% ctor's cant per Kgs ctor's as per
(3 + 4) Profit (5 + 6) Kgs (8 x 9) Profit (10+11) detail (12+13) (7 + 15)
20.00 20.00 24
Percent Percent
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 2" 0.00 0.00 0.00 0.00 0.00 0.259 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 3" 0.00 0.00 0.00 0.00 0.00 0.303 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 4" 0.00 0.00 0.00 0.00 0.00 0.339 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 5" 0.00 0.00 0.00 0.00 0.00 0.464 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 6" 0.00 0.00 0.00 0.00 0.00 0.544 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1
28 Providing and fixing cast iron special of BSS class "B" (such as bend, tee, cross collar, reducer, tail piece, flanged spigot,
cap, flanged socket, taper, angle branch, plug, etc.) for cast iron pipe line, complete.
a- C-I specials with spigot and socket joint.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1
28 - Providing and fixing cast iron special of BSS class "B" (such as bend, tee, cross collar, reducer, tail piece, flanged spigot,
cap, flanged socket, taper, angle branch, plug, etc.) for cast iron pipe line, complete.
b- CI flanged special with flanged and flanged joints.
1 3" 32.00
4" 48.00
5" 83.00
or
116.15
6" 93.00 Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 8" 161.00
10" 250.00
or
357.08
12" 376.00 Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 15" 453.00
or
498.00
18" 646.00 Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2
28 Providing and fixing cast iron special of BSS class "B" (such as bend, tee, cross collar, reducer, tail piece, flanged spigot,
cap, flanged socket, taper, angle branch, plug, etc.) for cast iron pipe line, complete.
c- CI specials with tyton joints.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1 3" 42.00
4" 60.00
5" 84.00
324.76
Lbs or
147.62
6" 109.00 Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 8" 175.00
10" 265.00
Lbs or
244.20
12" 374.00 Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 15" 654.00
921.80
Lbs or
419.00
18" 898.00 Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3
29 Providing and fixing C.I. special of BSS Class "B" (such as bend, tee, cross, collar, reducer, tail piece, flanged socket, flanged
spigot, cap, taper, angle branch plug etc.) for AC pipe line with comet joint and rubber ring complete.
Labour Material
S. Dia Average Labour rate for 2 Labour rate per Supply of special (cost of material, Rate per Kg
# of Weight joints. Kg. with moulding, painting, and carriage to Labour Composite
pipe in Labour Material Total Total Total Rate site of work. rate per rate per
Lbs weight Amount per Kg Rate P. Contractor's Total Rate Kg Kg
Cwt Profit per Lbs
20.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1 3" 46.00
4" 61.00
204 Lbs
or 92.56
6" 97.00 Kgs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 8" 175.00
10" 250.00
12" 370.00
16" 549.00
2037 Lbs
or
927.23
18" 693.00 Kgs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 20" 937.00
2254 Lbs
or 1022
24" 1317.00 Kgs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4
30 - Providing and fixing sluice valve of BSS quality and weight Class "B" for cast iron pipe
Each
Material Labour Rate
S. Dia of Cost of Contractor's Total No of Daily Total Labour Composite
No. sluice sluice Profit day Labour
valve valve 20 (3 + 4) (5 + 9)
Percent
1 2 3 4 5 6 7 8 9 10
1 3" - 0.00 0.00 0.340 0.00 0.00 - 0.00 Labour 3" to 8"
2 4" - 0.00 0.00 0.370 0.00 0.00 - 0.00 Plumber 1 No 0.00 0.00
3 5" - 0.00 0.00 0.666 0.00 0.00 - 0.00 Skilled Coolies 2 No 0.00 0.00
5 8" - 0.00 0.00 0.829 0.00 0.00 - 0.00 Sundries 10.00 Percent 0.00
7 12" - 0.00 0.00 0.999 0.00 0.00 - 0.00 Contractor's Profit & O 20.00 Percent 0.00
9 18" - 0.00 0.00 1.525 0.00 0.00 - 0.00 Labour 10" to 18"
Total 0.00
Total 0.00
Total 0.00
1
31 Providing and fixing sluice valve of BSS quality & weight for AC pipeline with
commet joint & rubber ring complete i/c cost of jointing material.
1
31a Providing and fixing sluice valve of BSS quality and weight for A.C. pipe line with cement joint
and rubber ring complete including cost of jointing material.
Labour
Sr. Size No. of Charge Amount Daily Charge
No. Day per day
1 3" 12.30 0.00 0.00
2 4" 11.40 0.00 0.00
3 6" 10.35 0.00 0.00
4 8" 7.40 0.00 0.00
5 10" 9.30 0.00 0.00
6 12" 6.93 0.00 0.00
7 16" 6.10 0.00 0.00
8 18" 5.78 0.00 0.00
1
32 Providing and fixing fire hydrant BSS quality and weight of 2" dia including cost of
jointing material.
1 2" - - - - - 0.00 - -
33 Providing and fixing Air Valve 3" (75mm) internal dia of BSS quality and weight complete
with jointing material.
a Single - - - - - 0.00 - -
b Double - - - - - 0.00 - -
20
1
34 Providing and fitting CI flanges on pipes, including turning, threading, facing and fitting etc.
complete in all respects.
1 2 3 4 5 6 7 8 9 10 11 12 13 14
a 3" 15.00 0.00 0.00 0.00 0.00 8.40 0.00 0.00 0.00 0.00 0.00 0.00 Labour
4" 14.00 0.00 0.00 0.00 0.00 12.60 0.00 0.00 0.00 0.00 0.00 0.00 Turner 1 No 0.00 0.00
5" 12.00 0.00 0.00 0.00 0.00 17.00 0.00 0.00 0.00 0.00 0.00 0.00 Unskilled Coolies 1 No 0.00 0.00
6" 11.00 0.00 0.00 0.00 0.00 21.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
b 8" 9.00 0.00 0.00 0.00 0.00 35.70 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
10" 7.00 0.00 0.00 0.00 0.00 52.50 0.00 0.00 0.00 0.00 0.00 0.00 Contractor's Profi 10.00 Percen 0.00
12" 5.00 0.00 0.00 0.00 0.00 74.55 0.00 0.00 0.00 0.00 0.00 0.00 Mechanic &Total 0.00
Electrical
Average charges L.S.
c 15" 3.00 0.00 0.00 0.00 0.00 110.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 0.00
18" 2.00 0.00 0.00 0.00 0.00 153.00 0.00 0.00 0.00 0.00 0.00 0.00
Average
1
35 Cutting C.I. Pipe and welding spigot or socket, flanged or tyton end after finishing ends of pipes.
Sr. No. Dia of Cutting Circumference Welding Charges Cutting G.Total Say Rate per Rate per
Pipe Inch. End of Pipe in Rate per Total 2 Ends and inch bore cm bore
Inch. Inch. (4 + 5) Finishing
(Double Col. 3)
1 2 3 4 5 6 7 8 9 10 11
Average
Average
Average
1
36 Providing, laying, cutting, jointing, testing and disinfecting G.I. Pipe Line in trenches, with flanged joints, using G.I. pipe of BSS 1387-1967 Heavy Quality complete in a
respects, including specials and valves:-
Sr. Dia of Cost Speical Advot Wastage Total Contractor Total No. of Daily Daily Total Material Per Ft. Length
No. Pipe Inch 100' 10% 1% 2% (3 + 4 + Profit Joints Progress Charges Size No. Rate Amount
heavy + 5 + 6) 10% (7 + 8) (15 x 16)
quality
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
a 1" (40mm) - 0.00 0.00 0.00 0.00 0.00 0.00 8 20 0.00 0.00 3/8 3.00 - 0.00
b 2" (50mm) - 0.00 0.00 0.00 0.00 0.00 0.00 8 20 0.00 0.00 3/8 3.00 - 0.00
c 2" (63mm) - 0.00 0.00 0.00 0.00 0.00 0.00 8 20 0.00 0.00 5/8 3.00 - 0.00
d 3" (75mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 15 0.00 0.00 5/8 4.00 - 0.00
e 4" (100mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 12 0.00 0.00 5/8 4.00 - 0.00
f 6" (125mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 10 0.00 0.00 5/8 4.00 - 0.00
g 8" (150mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 10 0.00 0.00 5/8 4.00 - 0.00
DAILY PROGRESS
Mechanic 1 No. 170 0.00 0.00
Cooly 2 No. 75 0.00 0.00
Total 0.00
Sundries 10.00 Percent 0.00
Total 0.00
36 Providing, laying, cutting, jointing, testing and disinfecting G.I. Pipe Line in trenches, with flanged joints, using G.I. pipe of BSS complete in all 1387-1967 Medium Qua
respects, including specials and valves:-
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
a 1" (40mm) - 0.00 0.00 0.00 0.00 0.00 0.00 8 20 0.00 0.00 3/8 3.00 - 0.00
b 2" (50mm) - 0.00 0.00 0.00 0.00 0.00 0.00 8 20 0.00 0.00 3/8 3.00 - 0.00
c 2" (63mm) - 0.00 0.00 0.00 0.00 0.00 0.00 8 20 0.00 0.00 5/8 3.00 - 0.00
d 3" (75mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 15 0.00 0.00 5/8 4.00 - 0.00
e 4" (100mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 12 0.00 0.00 5/8 4.00 - 0.00
f 6" (125mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 10 0.00 0.00 5/8 4.00 - 0.00
g 8" (150mm) - 0.00 0.00 0.00 0.00 0.00 0.00 6 10 0.00 0.00 5/8 4.00 - 0.00
DAILY PROGRESS
1
all
h of Pipe Total Contrator Total Carriage Testing Grand Rate Per 100 Ft Rate Per Foot Rate Per Metre
Wt. Amount (13 + Profit & Total Labour Composte Labour Composite Labour Composite
Lbs. Rs. 17 + 10% (20 + Disfi- (22 + 23 (9 + 26)
0.00 19) 21) necting + 24)
per Lbs.
18 19 20 21 22 23 24 25 26 27 28 29 30 31
0.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
uality
Rubber Insertion Total Contr- Total Carriage Testing Grand Rate Per 100 Ft. Rate Per Ft. Rate Per Metre.
Wt. Amount (13 + 17 ator's (20 + 21) and Total Labour Compo- Labour Compo- Labour Composite
Lbs. Rs. + 19) Profit disin- (22 + 23 site site
- 10% fection + 24) (26 + 9)
per Lbs.
18 19 20 21 22 23 24 25 26 27 28 29 30 31
0.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00
2
3
Sr. No. 41
Making Connection for new Water Supply lines with the running main, including excavation of
trench and refilling, complete, but excluding cost of pipe and specials, etc.
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Cooly for excavating/ refilling the
trench 0.50 No 0.00 P. Day -
Plumber for cutting, connecting
pipe, etc. 2 cuts 0.25 No 0.00 P. Day -
Total -
Sundries 10.00 Percent -
Total -
20
1
ii) Upto 200mm (8") i/d
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Total -
Sundries 10.00 Percent -
Total -
Contractor's#REF! Percent -
Total -
2
iii) Upto 250mm (10") i/d
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Cooly for excavating/ refilling the
trench 0.50 No 0.00 P. Day -
Plumber for cutting pipe, etc.
2 cuts 0.50 No 0.00 P. Day -
Total -
Sundries 10.00 Percent -
Total -
3
iv) Upto 300mm (12") i/d
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Total -
Sundries 10.00 Percent -
Total -
4
v) Upto 400mm (16") i/d
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Total -
Sundries 10.00 Percent -
Total -
5
vi) Upto 500mm (20") i/d
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Total -
Sundries 10.00 Percent -
Total -
6
vii) Upto 600mm (24") i/d
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Total -
Sundries 10.00 Percent -
Total -
7
DESCRIPTION OF ITEM NO. 15-A Providing and fixing, 6" (150mm) thick RCC
manhole as per standard drawing STD/PD No.6
of 1977, complete in all respects.
Detail Gully trap frame hinged saUnit Rate (British System) per Set
1. RCC Cover
Material
Steel 58.524 P. Kg -
Total -
Contractor's Profit & overhead chg: 20% -
Total -
C.O. -
Labour
Item Rates
Labour Rate Per Set Rs. - Say
1. Providing and Laying RCC Pipe moulded with cement concrete 1:1:3 with spigot socket or collar joint etc. including cost of reinforcement,
conforming to B.S. 5911 Part 1.1981, Class "L", including Carriage of Pipe from factory to site of work, lowering in trenches to correct
alignment and grade, jointing, cutting pipes where necessary, finishing and testing etc. complete.
h C.I. Gully trap frame hinged safety type.
Dia Material Per Meter Length LABOUR PER PIPE OF 6 FEET Labour Composite
of Pipe Market Wastage Rubber Contractor Carriage Laying Jointing Testing Labour Composite Rate Rate
mm Rate per 2% Ring - Total Profit Total Per Pipe Daily Daily Labour Charges Total Per Per Foot Per Per
Meter Per Inc 20 Amount (Rs)Progress Expenses Per Pipe Foot Metre Metre
Dia Pipe Percent
1 2 3 4 5 6 7 9 10 11 12 13 14 15 16 17 18
4" (100mm) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 180.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6" (150mm) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 150.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9" (225mm) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 120.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
DESCRIPTON OF ITEM
2 Providing and laying non-reinforced concrete pipe moulded with Cement Concrete 1:1:3 Conforming to ASTM specification 14-73 Class-I including Carriage of
Pipe from Factory to Site of Work, Lowering in Trenches to Correct Alignment and Grade Jointing Cutting Pipe where necessary, finishing and testing etc.
complete.
Dia of Material Per Meter Length of Pipe LABOUR Per Pipe of 6 Ft. Length Labour Composite
Pipe Market Wastage Rubber Contractor Carriage Laying Jointing Testing Labour Composite Rate Rate
mm Rate per 3% Ring - Total Profit Total Wt. in Amount Daily Daily Per Charges Total Per Per Per Per
Metre Per Inc 20 Ton Progress Expenses Pipe Foot Foot Metre Metre
Dia Pipe Percent
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
4" (100mm) 0.00 0.00 0.00 0.00 0.00 0.00 0.043 0.00 180.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6" (150mm) 0.00 0.00 0.00 0.00 0.00 0.00 0.061 0.00 150.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8"(200mm) 0.00 0.00 0.00 0.00 0.00 0.00 0.094 0.00 144.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9" (225mm) 0.00 0.00 0.00 0.00 0.00 0.00 0.127 0.00 136.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10"(250mm 0.00 0.00 0.00 0.00 0.00 0.00 0.133 0.00 135.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Page 1
DESCRIPTION OF ITEM
3 Providing and laying RCC Pipe Sewers, Moulded with Cement Concrete 1:1:3 Confirming to ASTM Specification C-76-79 Class-II, Wall B, Including Carriage of
Pipe from Factory to tWith C.I. Gully trap frame hinged safety type.
etc. Complete.
1. 12" (300mm) 2.439 2.00 0.00 0.00 0.00 0.00 0.00 0.00 23.00 0.00 15.00 - 0.00 0.00 0.00
2. 15"(380mm) 2.439 2.25 0.00 0.00 0.00 0.00 0.00 0.00 17.00 0.00 12.00 - 0.00 0.00 0.00
3. 18"(460mm) 2.439 2.50 0.00 0.00 0.00 0.00 0.00 0.00 13.00 0.00 10.00 - 0.00 0.00 0.00
4. 21"(535mm) 2.439 2.75 0.00 0.00 0.00 0.00 0.00 0.00 10.00 0.00 8.00 - 0.00 0.00 0.00
5. 24"(1610mm 2.439 3.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 0.00 7.00 - 0.00 0.00 0.00
6. 27"(685mm) 2.439 3.25 0.00 0.00 0.00 0.00 0.00 0.00 7.00 0.00 6.00 - 0.00 0.00 0.00
7. 30"(760mm) 2.439 3.50 0.00 0.00 0.00 0.00 0.00 0.00 6.00 0.00 5.00 - 0.00 0.00 0.00
8. 33"(800mm) 2.439 3.75 0.00 0.00 0.00 0.00 0.00 0.00 5.00 0.00 4.00 - 0.00 0.00 0.00
9. 36"(915mm) 2.439 4.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 0.00 3.25 - 0.00 0.00 0.00
10. 42"(1070mm 2.439 4.50 0.00 12.50 0.00 12.50 2.50 15.00 3.00 0.00 2.50 - 0.00 0.00 0.00
11. 48"(1220mm 2.439 5.00 0.00 14.50 0.00 14.50 2.90 17.40 2.00 0.00 7.00 - 0.00 0.00 0.00
12. 54"(1370mm 2.439 5.50 0.00 16.80 0.00 16.80 3.36 20.16 2.00 0.00 5.00 - 0.00 0.00 0.00
13. 60"(1520mm 2.439 6.00 0.00 22.60 0.00 22.60 4.52 27.12 1.00 0.00 4.00 - 0.00 0.00 0.00
14. 66"(1680mm 2.439 6.50 0.00 27.50 0.00 27.50 5.50 33.00 1.00 0.00 2.50 - 0.00 0.00 0.00
15. 72"(1830mm 2.439 7.00 0.00 32.50 0.00 32.50 6.50 39.00 1.00 0.00 2.00 - 0.00 0.00 0.00
Page 2
DESCRIPTION OF ITEM
4 Providing and laying RCC Pipe Sewers, Moulded with Cement Concrete 1:1:3 Confirming to ASTM Specification C-76-79 Class-III wall B, Including Carriage of
Pipe from Factory to the Site of Work, Lowering in Trenches to Correct Alignment and Grade Jointing with Rubber Ring, Cutting Pipes where necessary, Testing
etc. Complete. in all respects.
Sr. Dia of Material Per Metre Length of Pipe LABOUR FOR 8' PIPE
No. Pipe Market Wastage Rubber Contractor Carriage Laying Jointing Total Total
Inch Rate 2% Ring Per Total Profit Total Daily Amount Daily Daily Rate Testing per Labour
Meter Inch Rs. 20.00 Progress Rs. Progress Expenses per Pipe Charges Pipe rate per
0.00 (Pipe) (Pipe) Per Pipe ft.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1. 12" (300mm) 0.00 0.00 0.00 0.00 0.00 0.00 23.00 0.00 15.00 (0.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2. 15"(380mm) 0.00 0.00 0.00 0.00 0.00 0.00 17.00 0.00 12.00 (0.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3. 18"(460mm) 0.00 0.00 0.00 0.00 0.00 0.00 13.00 0.00 10.00 (0.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4. 21"(535mm) 0.00 0.00 0.00 0.00 0.00 0.00 10.00 0.00 8.00 (0.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5. 24"(1610mm 0.00 0.00 0.00 0.00 0.00 0.00 8.00 0.00 7.00 (0.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6. 27"(685mm) 0.00 0.00 0.00 0.00 0.00 0.00 7.00 0.00 6.00 4.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7. 30"(760mm) 0.00 0.00 0.00 0.00 0.00 0.00 6.00 0.00 5.00 4.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8. 33"(800mm) 0.00 0.00 0.00 0.00 0.00 0.00 5.00 0.00 4.00 4.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9. 36"(915mm) 0.00 0.00 0.00 0.00 0.00 0.00 4.00 0.00 3.25 4.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10. 42"(1070mm 0.00 0.00 0.00 0.00 0.00 0.00 3.00 0.00 2.50 4.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11. 48"(1220mm 0.00 0.00 0.00 0.00 0.00 0.00 2.00 0.00 7.00 (1.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12. 54"(1370mm 0.00 0.00 0.00 0.00 0.00 0.00 2.00 0.00 5.00 (1.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13. 60"(1520mm 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 4.00 (1.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14. 66"(1680mm 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 2.50 (1.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15. 72"(1830mm 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 2.00 (1.25) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Page 3
DESCRIPTION OF ITEM
5 Providing and laying RCC Pipe Sewers, Moulded with Cement Concrete 1:1:3 Confirming to ASTM Specification C-76-79 Class-IV, Wall B, Including Carriage of
Pipe from Factory to the Site of Work, Lowering in Trenches to Correct Alignment and Grade Jointing with Rubber Ring, Cutting Pipes where necessary, Testing
etc. Complete.
Sr. Dia of MATERIAL PER METRE LENGTH LABOUR FOR 8' FT. PIPE
No. Pipe Market Wastage Rubber Contractors Carriage Laying Jointing Total Labour Labour Composite Labour Composite
mm Rate 2% Ring Per Total Profit Total Daily Amount Daily Daily Rate Testing Total Rate Per Rate Per Rate Per Rate Per Rate Per
Per Inch Rs. 20.00 Progress (Rs.) Progress Expenses Per Charges Per Metre Metre Metre Metre Metre
Metre 0.00 Pipe Pipe Per Pipe Pipe
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 15 16 17 18
1. 12" (300mm) 0.00 0.00 0.00 0.00 0.00 0.00 23.00 0.00 15.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2. 15"(380mm) 0.00 0.00 0.00 0.00 0.00 0.00 17.00 0.00 12.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3. 18"(460mm) 0.00 0.00 0.00 0.00 0.00 0.00 13.00 0.00 10.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4. 21"(535mm) 0.00 0.00 0.00 0.00 0.00 0.00 10.00 0.00 8.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5. 24"(1610mm 0.00 0.00 0.00 0.00 0.00 0.00 8.00 0.00 7.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6. 27"(685mm) 0.00 0.00 0.00 0.00 0.00 0.00 7.00 0.00 6.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7. 30"(760mm) 0.00 0.00 0.00 0.00 0.00 0.00 6.00 0.00 5.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8. 33"(800mm) 0.00 0.00 0.00 0.00 0.00 0.00 5.00 0.00 4.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9. 36"(915mm) 0.00 0.00 0.00 0.00 0.00 0.00 4.00 0.00 3.25 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10. 42"(1070mm 0.00 0.00 0.00 0.00 0.00 0.00 3.00 0.00 2.50 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11. 48"(1220mm 0.00 0.00 0.00 0.00 0.00 0.00 2.00 0.00 7.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12. 54"(1370mm 0.00 0.00 0.00 0.00 0.00 0.00 2.00 0.00 5.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13. 60"(1520mm 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 4.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14. 66"(1680mm 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 2.50 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15. 72"(1830mm 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 2.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Page 4
6 Lowering of Sub Soil Water table by Installation of Tubewell along Sewer Line and Pumping Out Water, for Excavation in Open Cutting below Sub Soil Water Level,
Concreting, Curing, Laying and Jointing Pipes, Filling hauncher etc, till the Completion of Sewer Line, including Disposal of Pumped Out Water
1 0-1' 100.00 20 - 0.00 0.00 - 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 0-2' 76.00 64 - 0.00 0.00 - 29.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 0-3' 62.00 70 - 0.00 0.00 - 45.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 0-4' 52.00 75 - 0.00 0.00 - 57.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 0-5' 550.00 80 - 0.00 0.00 - 60.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 0-6' 43.00 88 - 0.00 0.00 - 64.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 0-7' 38.50 92 - 0.00 0.00 - 69.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 0-8' 34.00 94 - 0.00 0.00 - 70.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 0-9' 33.00 96 - 0.00 0.00 - 55.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10 0-10' 31.00 99 - 0.00 0.00 - 60.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 0-11' 30.00 102 - 0.00 0.00 - 65.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12 0-12' 29.00 106 - 0.00 0.00 - 70.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Page 5
SEWERAGE
DESCRIPTION OF ITEM NO 7: Constructing gully grating chamber 12"x12"(300x300mm)
Deduction
Sewer
'x'x22/7x = 0.60
Drain
1x'x'x22/7x' = 0.10
0.70 Cft
Net ( 10.24 - 0.70 ) = 9.5 9.54 Cft 0.00 % Cft 0.00 % Cft 0.00 0.00
Item No. 4(i) of Chap. 7
Cement Plaster (1:3) " thick
inside chamber 1x4x2 3/8' = 9.50
outside chamber 2x2'x' = 3.75
2x2 1/8'x' = 3.19
16.44
Top 1x2'x' 1.87
3
1x1 /8'x' 1.00
3
1x2'x /8' 1.00
20.31 Sft -0.01 % Sft -0.01 % Sft 0.00 0.00
Item No. 8(b) Chapter 11
Cement concrete plain 1:2:4 including
placing, compacting finishing and curing
complete.
1
Floor bed 1x1x /12 0.08 Cft 0.00 % Cft 0.00 % Cft 0.00 0.00
Item 5 (f) Chap. No. 6
Page 7
Item No. 7 Constructing gully grating chamber 12"x12" (300x300mm)
1
Floor bed 1x1x /12 0.08 Cft 0.00 % Cft 0.00 % Cft 0.00 0.00
As per item No. 5 of Chapter 6
Page 8
Detail Unit Rate (British System) per Each
Page 9
DESCRIPTION OF ITEM NO 8: Constructing standard gully grating chamber 3.0'x1.5'x2.5'
china ware trap as per PHED drawing
No. STD/PD No. 3 of 1977 complete in all respect.
Excavation in foundation
1x5'x3'x3' = 53 Cft 53.00 Cft 0.00 %0 Cft - 0.00 -
D/d opening
1x1x1x0.75 = 0.75
1x0.5x0.5x0.75 = 0.19
Total 0.94 Cft
Net 22.50 - 0.94 = 21.56 Cft 21.56 Cft 0.00 % Cft 0.00 % Cft 0.00 0.00
Page 10
DESCRIPTION OF ITEM NO 9: Extra for making and finishing benching floor work
in manhole chamber, with 1/8" (3mm) thick cement
finish.
Material
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate P. Sqm Rs. Say -
Page 13
DESCRIPTION OF ITEM NO 10: Restoration of brick pavement on edge, over laid
service line, with 2" (50mm) sand cushion under
soling.
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate P. Sqm Rs. Say -
Page 14
DESCRIPTION OF ITEM NO 11: Restoration of flat brick pavement sand
grouted, over 2" (50mm) thick dry sand
cushion, under soling on laid service line.
Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 100 Sft
Material
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate P. Sqm Rs. Say -
Page 15
DESCRIPTION OF ITEM NO 12: Restoration of metalled road, on laid service
line, including compaction.
a) Carpeted road, with 2" (50mm) carpet and 10"
(250mm) depth of stone metal for sub base and
base.
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Labour
Total -
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate P. Sqm Rs. Say -
Page 16
DESCRIPTION OF ITEM NO 12: Restoration of metalled road, cut for laying
service line, including compaction.
b) Carpeted road with 1" (40mm) carpet and 6"
(150mm) depth of stone metal for sub-base and
base.
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Labour
Total
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate P. Sqm Rs. Say -
Page 17
DESCRIPTION OF ITEM NO 12: Restoration of metalled road, cut for laying
service line, including compaction.
c) Black topped road with two coats of surfacing and
10" (254mm) depth of stone metal for sub-base and
base.
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove 20.00 Percent -
Item 2 & 3 on 'Rs.
Total -
Labour
Item Rates
Labour Rate Per 100 Sft Rs. Say -
Labour Rate P. Sqm Rs. Say -
Page 18
DESCRIPTION OF ITEM NO 13: Providing and fixing 1"x1"x3/16"
(32x32x5mm) angle iron step, in manhole
chambers, including carriage and setting the
same in work, to correct lines and levels.
Qty Rate
Per Unit (Rs) Amount (Rs)
Material
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Page 19
Detail Unit Rate (British System) per 100 Sft
Qty Rate
Per Unit (Rs) Amount (Rs)
Total -
Sundries 10.00 Percent -
Total -
Item Rates
Labour Rate for Each Rs. Say -
Page 20
DESCRIPTION OF ITEM NO 14: Fixing manhole frame and cover in RCC slab
including carriage to site.
Qty Rate
Per Unit (Rs) Amount (Rs)
Carriage of Manhole
Frame and cover average weight of
each set = 127 Kg.
cart load up to 4 miles (6.44 Km)
@ Rs. per cart load.
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Item Rates
Labour Rate Per Set Rs. Say -
Page 21
DESCRIPTION OF ITEM NO 15: Providing and fixing, 3" (75mm) thick RCC
manhole cover, 22" (557mm) dia with tee
shaped C.I. frame of 20" (505mm) clear i/d
(frame weighting 37.324 Kg. or one maund)
as per standard drawing STD/ PD No. 5 of
1977, complete in all respects.
Qty Rate
Per Unit (Rs) Amount (Rs)
RCC Cover
1.M.S. flat iron ring 3"x" (75x6mm) =
1 x 22 x 22 x = 1.44 Sft
7 12
1.44 Sft weight @ 10.21 Lbs = 14.70 Lbs (6.67) Kg
2.M.S. round bars " dia
Straight bars 4 x 22 = 7.33 ft
12
Straight bars 4 x 1.75 = 7.00 ft
14.33 Rft
Weight of bars @ 0.667 Lbs/Rft
(0.992 Kg/Rft) = 9.60 Lbs (4.36) Kg
Total 1+2 = 6.67+4.36 = 11.03 Kg
Material
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Page 22
Detail Unit Rate (British System) per 100 Sft
Qty Rate
Per Unit (Rs) Amount (Rs)
Labour
Total -
Contractor's Profit & Ove 20.00 Percent on R - -
Total -
Item Rates
Labour Rate Per Set Rs. Say -
Page 23
DESCRIPTION OF ITEM NO .16 Providing and fixing, 6" (150mm) thick RCC
manhole cover 22" as per standard drawing STD/ PD
No. 6 of 1977, complete in all respects.
Qty Rate
Per Unit (Rs) Amount (Rs)
RCC Cover
a.2"x2"x" size angle iron rings =
1 x 22 x 26 = 6.81 Rft
7 12
Weight @ 4.04 Lbs/ft = 27.51 Lbs (12.430) Kg
b.M.S. round bars " dia
Straight bras 1 x 26 = 26 inches
2 x 24 = 48
2 x 18 = 36
bent up bars 1 x 28 = 28
2 x 26 = 52
2 x 20 = 40
230 Inchs or 19.17 ft 19.17 ft
Bars in upper distribution ring 1x22/7x1.5 = 4.71
Bar in lower distribution ring 1x22/7x1.25 = 3.93
in overlaps distribution ring 2x = 1.00
28.81 ft @ 0.667 Lbs/Rft = 19.22 Lbs 28.81 Ft
a + b = 27.51 + 19.22 = 46.73 Lbs or 21.20
21.20 Kg
Material
Steel 58.524 Kg P. Kg -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Page 24
Detail Unit Rate (British System) per 100 Sft
Qty Rate
Per Unit (Rs) Amount (Rs)
-
RCC (1:2:4) in situ or precast
1 x 22 x 26 x 26 x x 6+5+5 x 1 = 1.74 Cft
7 12 12 3 12
Labour
Item Rates
Labour Rate Per Set Rs. Say -
Page 25
DESCRIPTION OF ITEM NO 17: Providing and fixing, 6" (150mm) thick RCC
manhole cover with 3"x3"x" (75x75x6mm)
angle iron frame, 22" i/d (557mm) as per standard
drawing STD/ PD No. 7 of 1977, complete in all
respects.
Qty Rate
Per Unit (Rs) Amount (Rs)
Steel :
L. iron for frame 3"x3"x"
1x 22 x 27 = 7.07 ft @ 4.89 Lbs/Rft = 34.57 Lbs
7 12
L. iron for cover 2"x2"x"
1x 22 x 26 = 6.81 ft @ 4.04 Lbs/Rft = 27.51 Lbs
7 12
62.08 Lbs
M.S. round straight bars
1 x 26 = 26 inchs
2 x 24 = 48
2 x 18 = 36
1 x 28 = 28
2 x 26 = 52
2 x 20 = 40
230 Inchs or 19.17 ft 19.17 ft
Bars in upper distribution ring 1x22/7x1.5 4.71 ft
Bar in lower distribution ring 1x22/7x1.25 3.93 ft
Bar in overlaps distribution ring 2x 1.00 ft
Bar in holdfast of frame 4x0.75 3.00 ft
weight @ 0.667Lbs/ft x31.81 = 21.22 lbs 31.81 Ft
= 62.08 + 21.22 = 83.30 Lbs or
37.80 Kg
Material
Steel 37.80 Kg P. Kg -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Page 26
Detail Unit Rate (British System) per 100 Sft
Qty Rate
Per Unit (Rs) Amount (Rs)
Labour
Item Rates
Labour Rate Per Set Rs. Say -
Page 27
DESCRIPTION OF ITEM NO 18: Desilting of disposal work collecting tank including
removal of sludge with in 3 chains (90M).
Qty Rate
Per Unit (Rs) Amount (Rs)
Analysis Rate for 2100 Cft
T & P Required :
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Page 28
Detail Unit Rate (British System) per 100 Sft
Qty Rate
Per Unit (Rs) Amount (Rs)
Labour
Coolies Unskilled
For digging 2.00 Nos
For Lifting & removing 8.00 Nos
For carrying 2.00 Nos
12.00 Nos
Unskilled Cooly for 2 days 24.00 Nos Each -
Total -
Sundries 10.00 Percent -
Total -
Item Rates
Labour Rate Per 100 Cft Rs. Say -
Labour Rate Per Cum Rs. Say -
Page 29
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
a) i) 6" (150mm) dia 18' long.
Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 16 Cwt
Material
C.I. vantilating shaft 18' long weighing
16 cwt = 21.78 md. (813 Kg) including
column pipe, base, cowl, plates, and other
accessories including carriage to site. 813.00 Kg P. Kg -
Foundation bolts & nuts " dia 1' long 4.00 Nos No -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Page 30
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
a) ii) 6" (150mm) i/d shaft 24' (7.232Rm) long.
Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 18 Cwt
Material
C.I. vantilating shaft 24' long weighing
18 cwt = 24.50 md. (915 Kg) including
column pipe, base, cowl, and other plates
and accessories including carriage to site. 915.00 Kg P. Kg -
Foundation bolts & nuts " dia 2' long . 4.00 Nos No -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Page 31
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
a) iii) 6" (150mm) i/d shaft 30' (9.143Rm) long.
Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 20 Cwt
Material
C.I. vantilating shaft 30' including column pipe,
base, cowl and other accessories including
carriage to site weighing 20 cwt or 1016 kg 1016.00 Kg P. Kg -
Foundation bolts & nuts " dia 2' long . 4.00 Nos No -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Page 32
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
a) iv) 6" (150mm) i/d vantilating shaft 36' (11 M) long
Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 22.3 Cwt
Material
C.I. vantilating shaft 36' long including
column pipe base, cowl, other plates,
accessories & carriage to site 22.3 Cwt
(1133.21 kg). 1133.21 Kg P. Kg -
Foundation bolts & nuts " dia 2' long . 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -
Page 33
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
b) i) 9" (225mm) i/d : shaft 18' (5.48M) long.
Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 25 Cwt
Material
C.I. vantilating shaft 18' long including
column pipe base, cowl, plates and other
accessories including carriage to site 25 Cwt
(1270.42 kg). 1270.42 Kg P. Kg -
Foundation bolts & nuts " dia 2' long . 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Page 34
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
b) ii) 9" (225mm) i/d : shaft 24' (7M) long.
Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 29 Cwt
Material
C.I. vantilating shaft 24' long including
base, column pipe, cowl, plates, other
accessories & carriage to site 29 Cwt or
39.47 Mds: cast iron pipe. (1473.68 kg). 1473.68 Kg P. Kg -
Foundation bolts & nuts " dia 2' long . 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -
Composite Rate Per Cwt Rs. Say -
Composite Rate Per 100 Kg Rs. Say -
Page 35
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
b) iii) 9" (225mm) i/d : shaft 30' (9M) long.
Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 32.5 Cwt
Material
C.I. vantilating shaft 30' long including base,
column pipe, cowl, plates, other accessories &
carriage to site 32.5cwt or 44.24md (1651.54) 1651.54 Kg P. Kg -
Foundation bolts " dia 2' long. 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -
Composite Rate Per Cwt Rs. Say -
Composite Rate Per 100 Kg Rs. Say -
Page 36
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
b) iv) 9" (225mm) i/d : shaft 36' (11M) long.
Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 36 Cwt
Material
C.I. vantilating shaft 36' long including
base, column pipe, cowl, plates, bolts and
other accessories 36 Cwt or 1829.40 kg. 1829.40 Kg P. Kg -
Foundation bolts " dia 2' long. 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -
Composite Rate Per Cwt Rs. Say -
Composite Rate Per 100 Kg Rs. Say -
Page 37
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
c) i) 12" (300mm) i/d : shaft 18' (5.45M) long.
Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 36 Cwt
Material
C.I. vantilating shaft including base column
pipe, cowl, plates, bolts, and other
accessories etc. 36 Cwt or 1829.40 kg. 1829.40 Kg P. Kg -
Foundation bolts 7/8" dia 2' long. 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -
Page 38
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
c) ii) 12" (300mm) i/d : shaft 24' (7M) long.
Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 42 Cwt
Material
C.I. vantilating shaft including base column
pipe, cowl, plates, bolts, and other
accessories etc. 42 Cwt or 2134 kg. 2134.00 Kg P. Kg -
Foundation bolts 7/8" dia 2' long. 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Rental charges of T & P L. S. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -
Page 39
DESCRIPTION OF ITEM NO 19: Providing and installing C.I. vantilating shaft
painted with bituminous paint with foundation
bolts as per PHED standard drawing STD/PD
No. 4 of 1977 complete in all respects (except
concrete foundation block).
c) iii) 12" (300mm) i/d : shaft 30' (9M) long.
Qty Rate
Per Unit (Rs) Amount (Rs)
Rate Analysis for 48 Cwt
Material
C.I. vantilating shaft 30' long including base,
cowl, column pipe, plates. studs and other
accessories etc. 48 Cwt or 65.33 Md. = 2439.00 Kg P. Kg -
Foundation bolts 7/8" dia 3' long. 4.00 Nos Each -
Rubber sheets 1/8" thick 10"x8" =
0.55 Sft @ 1.5 Lbs/Sft 0.37 Kg P. Kg -
Hire charges of T & P L. S. -
Total -
Contractor's Profit & Ove 20.00 Percent -
Total -
Labour
Total -
Sundries 10.00 Percent -
Total -
Item Rates
Labour Rate Per Cwt Rs. Say -
Labour Rate Per 100 Kg Rs. Say -
Page 40
DESCRIPTION OF ITEM NO 20: Silt clearing 10' (3M) dia wells and removal of
slush out side the compound.
a) Upto 10' (3M) depth of slush.
Qty Rate
Per Unit (Rs) Amount (Rs)
Labour
Total -
Sundries 10.00 Percent -
Total -
Item Rates
Page 41
DESCRIPTION OF ITEM NO 20: Silt clearing 10' (3M) dia wells and removal of
slush out side the compound.
b) Beyond 10' (3M) depth of slush.
Qty Rate
Per Unit (Rs) Amount (Rs)
Labour
Total -
Sundries 10.00 Percent -
Total -
Item Rates
Page 42