1. SCOPE: -
Requirement of water flushing operation in connection with Hydro testing.
2. SPECIFICATION: -
MEDIUM:
3. PROCEDURE:-
The draining out of water used for hydrostatic test can be the first
flushing of pipe works, but additional flushing will be made, where
require.
For line size 8 and smaller. Utility water or firewater hose shall be
connected to the line to be flushed.
Doc.No.WKI-QC-03-01
Page 3 of 3
FUNCTIONALPROCEDURE Rev.00
Date:
Rev.0024/07/2011
FLUSHING
For line size 10 and larger, In order to get water flow speed for flushing
out the debris, air hose shall be connected in addition to water hose. At
first, line shall be depressurized after Hydro test and while still full of
water then flushed out by air. A continuous supply of air and water shall
be put into line until the outlet water is clean. Air shall be supplied by
temporary compressor or plant air.
Line, 24 inches and larger, may be cleaned by air blowing or hand
cleaning instead of water flushing where thorough cleaning is assured
subject to Albayroni approval.
4. DRYING:-
After completion of cleaning, pipes and equipments shall be thoroughly
drained. Dry air blown and ends shall be sealed to prevent from the
ingress of atmospheric moisture.
5. SAFETY: -
Water will be drained thoroughly from lines and equipment after
water flushing is completed. The vents must be opened during the
draining period.
When lines are flushed in place, the protection must be providing to
other equipment from water flushing (i.e., cold insulation, electrical
etc.)
Barricading & Warning signs must be hung in the area to indicate
that water flushing is in progress.
Any line requiring personnel to enter into pipes for cleaning purpose must be
adequately ventilated and checked by safety personnel. A vessel entry safety
permit will be required before entry into pipe. (Confined space permit to work).