You are on page 1of 11

Designation: D 1143 81 (Reapproved 1994)e1

AMERICAN SOCIETY FOR TESTING AND MATERIALS


100 Barr Harbor Dr., West Conshohocken, PA 19428
Reprinted from the Annual Book of ASTM Standards. Copyright ASTM

Standard Test Method for


Piles Under Static Axial Compressive Load1
This standard is issued under the fixed designation D 1143; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (e) indicates an editorial change since the last revision or reapproval.

This standard has been approved for use by agencies of the Department of Defense.

e1 NOTESection 10 was added editorially in May 1994.

INTRODUCTION

This standard has been prepared to cover routine methods of testing to determine if a pile has
adequate bearing capacity. The provisions permit the introduction of more detailed requirements and
procedures when required to satisfy the objectives of the test program. While the procedures herein
produce a relationship between applied load and pile settlement, the results may not represent
long-term performance.

1. Scope interpret the test results for predicting pile performance and capacity. The
term failure as used in this method indicates rapid progressive settle-
1.1 This test method covers procedures for testing vertical ment of the pile or pile group under a constant load.
or batter piles individually or groups of vertical piles to
determine response of the pile or pile group to a static 1.3 This standard does not purport to address all of the
compressive load applied axially to the pile or piles within the safety concerns, if any, associated with its use. It is the
group. This test method is applicable to all deep foundation responsibility of the user of this standard to establish appro-
units that function in a manner similar to piles regardless of priate safety and health practices and determine the applica-
their method of installation. This test method is divided into the bility of regulatory limitations prior to use.
following sections: 2. Referenced Documents
Section
Referenced Documents 2 2.1 ASTM Standards:
Apparatus for Applying Loads 3 D 3689 Method of Testing Individual Piles Under Static
Apparatus for Measuring Movements 4
Loading Procedures 5
Axial Tensile Load2
Procedures for Measuring Pile Movements 6 2.2 American National Standards Institute Standard:
Safety Requirements 7 B30.1 Safety Code for Jacks3
Report 8
Precision and Bias 9 3. Apparatus for Applying Loads
1.2 The values stated in inch-pound units are to be regarded 3.1 General:
as the standard. 3.1.1 The apparatus for applying compressive loads to the
NOTE 1Apparatus and procedures designated optional are to be test pile or pile group shall be as described in 3.3, 3.4, or 3.5
required only when included in the project specifications or if not or as otherwise specified and shall be constructed so that the
specified, may be used only with the approval of the engineer responsible loads are applied to the central longitudinal axis of the pile or
for the foundation design. The word shall indicates a mandatory pile group to minimize eccentric loading. Paragraph 3.3 is
provision and should indicates a recommended or advisory provision. suitable for applying axial loads to individual vertical or batter
Imperative sentences indicate mandatory provisions. Notes, illustrations,
piles; 3.4 and 3.5 are suitable for applying vertical loads only.
and appendixes included herein are explanatory or advisory.
NOTE 2This test method does not include the interpretation of test NOTE 3When a pile group is subject to vertical test loads, cap
results or the application of test results to foundation design. See rotations and horizontal displacements could occur. The occurrence of
Appendix X1 for comments regarding some of the factors influencing the such movements and the necessary reactions to resist such movements if
interpretation of test results. A qualified geotechnical engineer should they are prohibited should be considered when designing and constructing
the loading apparatus for the group test.
NOTE 4If it is not feasible to apply axial test loads to a batter pile, the
1 results of a test on a similar nearby vertical pile generally may be used to
This test method is under the jurisdiction of ASTM Committee D-18 on Soil
and Rock and is the direct responsibility of Subcommittee D18.11 on Deep
2
Foundations. Annual Book of ASTM Standards, Vol 04.08.
3
Current edition approved March 2, 1981. Published May 1981. Originally Available from American National Standards Institute, 1430 Broadway, New
published as D 1143 50 T. Last previous edition D 1143 74. York, NY 10018.

1
D 1143
evaluate the axial bearing capacity of the batter pile. high-strength quick-setting grout, if necessary.
3.1.2 Where feasible, the immediate area of the test pile or 3.2 Testing Equipment:
pile group shall be excavated to the proposed pile cut-off 3.2.1 Hydraulic jacks including their operation shall con-
elevation. The test pile(s) shall be cut off or built up to the form to ANSI B30.1.
proper grade as necessary to permit construction of the 3.2.2 Unless a calibrated load cell(s) is used, the complete
load-application apparatus, placement of the necessary testing, jacking system including the hydraulic jack(s), hydraulic
and instrumentation equipment, and observation of the instru- pump, and pressure gage shall be calibrated as a unit before
mentation. Where necessary, the unsupported length of the test each test or series of tests in a test program to an accuracy of
pile(s) shall be braced to prevent buckling without influencing not less than 5 % of the applied load. The hydraulic jack(s)
the test results. shall be calibrated over its complete range of ram travel for
3.1.3 If the head of the pile has been damaged during increasing and decreasing applied loads. If two or more jacks
driving, the damaged portion shall be removed prior to the test. are to be used to apply the test load, they shall be of the same
For tests on piles groups, the piles shall be capped with a ram diameter, connected to a common manifold and pressure
reinforced concrete cap designed and constructed in accor- gage, and operated by a single hydraulic pump.
dance with accepted engineering practice for the anticipated NOTE 6If it is not feasible to calibrate the complete jacking system as
loads. a unit, the pressure gage may be calibrated independently, in which case
the jack piston(s) should be measured to verify the area(s).
NOTE 5Consideration should be given to providing a nominal clear
space between the cap and the ground surface to eliminate any support 3.2.3 When an accuracy greater than that obtainable with
offered by the soil under short-term loading. A properly constructed steel the jacking system is required, a properly constructed load
grillage may serve as an adequate pile cap for testing purposes.
cell(s) or equivalent device(s) shall be used in series with the
3.1.4 In 3.3 and 3.4 and for a test on an individual pile in hydraulic jack(s). Load cell(s) or equivalent device(s) shall be
3.5, a steel bearing plate(s) (test plate(s)) of sufficient thickness calibrated prior to the test to an accuracy of not less than 2 %
to prevent it from bending under the loads involved (but not of the applied load and shall be equipped with a spherical
less than 2 in. (50 mm)) shall be centered on the pile or pile cap bearing(s).
and set perpendicular to the longitudinal axis of the pile or piles 3.2.4 If the hydraulic jack pump is to be left unattended at
within the group, except that for tests on pile groups involving any time during the test, it shall be equipped with an automatic
the use of two or more separate loading points, a test plate shall regulator to hold the load constant as pile settlement occurs.
be used at each loading point and such plates shall be arranged 3.2.5 Calibration reports shall be furnished for all testing
symmetrically about the centroid of the group. For tests on equipment for which calibration is required, and shall show the
individual piles, the size of the test plate shall be not less than temperature at which the calibration was done.
the size of the pile butt nor less than the area covered by the
NOTE 7Considerations should be given to employing a dual load-
base(s) of the hydraulic jack(s); for tests on pile groups, the measuring system (gage and load cell) to provide as a check and as a
size of the test plate(s) shall be not less than twice the area back-up in case one system malfunctions. Hydraulic jack rams should
covered by the base(s) of the hydraulic jack(s). have sufficient travel to provide for anticipated pile settlements, deflec-
3.1.5 For tests on precast or cast-in-place concrete piles or tions of the test beam, and elongation of connections to anchoring devices
on pile groups, the test plate when used shall be set in with 3.3. The use of a single high-capacity jack is preferred to the use of
high-strength quick-setting grout. For tests on individual steel multiple jack(s). If a multiple jacking system is used, each jack should be
fitted with a pressure gage (in addition to the master gage) in order to
H-piles, the test plate shall be welded to the pile. For tests on
detect malfunctions.
individual timber piles, the test plate may be set directly on the
top of the pile which shall be sawed off to provide full bearing 3.3 Load Applied to Pile or Pile Group by Hydraulic Jack(s)
for the test plate or, alternatively, the test plate may be set in Acting Against Anchored Reaction Frame (See Fig. 1 and Fig.
high-strength quick-setting grout. 2):
3.1.6 In 3.3 and 3.4, the hydraulic jack(s) shall be centered 3.3.1 Install a sufficient number of anchor piles or suitable
on the test plate(s) with a steel bearing plate of adequate anchoring device(s) so as to provide adequate reactive capacity
thickness between the top(s) of the jack ram(s) and the and a clear distance from the test pile or pile group at least five
bottom(s) of the test beam(s). If a load cell(s) or equivalent times the maximum diameter of the largest anchor or test
device(s) is to be used, it shall be centered on the bearing plate pile(s) but not less than 7 ft (2 m). When testing individual
above the ram(s) with another steel bearing plate of sufficient batter piles, the anchor piles shall be battered in the same
thickness between the load cell(s) or equivalent device(s) and direction and angle as the test pile.
the bottom(s) of the test beam(s). Bearing plates shall be of 3.3.2 Center over the test pile or pile group a test beam(s) of
sufficient size to accommodate the jack ram(s) and the load sufficient size and strength to avoid excessive deflection under
cell(s) or equivalent device(s) and properly bear against the load with sufficient clearance between the bottom flange(s) of
bottom(s) of the test beam(s). the test beam(s) and the top of the test pile or pile group to
3.1.7 In 3.5 for tests on pile groups a test plate may be used provide for the necessary bearing plates, hydraulic jack(s) (and
in accordance with the appropriate provisions of 3.1 or, load cell(s) if used). When applying axial loads to an individual
alternatively, the test beam(s) may be set directly on the pile batter pile, the test beam(s) should be oriented perpendicular to
cap or the loading material applied directly on the cap. Test the direction of batter. For test loads of high magnitude
beam(s) set directly on the cap shall obtain full bearing using requiring several anchors, a steel framework may be required

2
D 1143

FIG. 1 Schematic Set-Up for Applying Loads to Pile Using Hydraulic Jack Acting Against Anchored Reaction Frame

Methods shown in Fig. 3 and Fig. 4 could be used.


FIG. 2 Typical Arrangement for Applying Load Test to Pile Group Using Method Illustrated in Fig. 1

to transfer the applied loads from the test beam(s) to the ends of the test beam(s) on temporary cribbing or other
anchors. devices.
3.3.3 Attach the test beam(s) (or reaction framework if 3.4.2 Center a box or platform on the test beam(s) with the
used) to the anchoring devices with connections designed to edges of the box or platform parallel to the test beam(s)
adequately transfer the applied loads to the anchors so as to supported by cribbing or piles placed as far from the test pile
prevent slippage, rupture or excessive elongation of the con- or pile group as practicable but in no case less than a clear
nections under maximum required test load. distance of 5 ft (1.5 m). If cribbing is used, the bearing area of
3.3.4 Apply the test load in accordance with the standard the cribbing at ground surface shall be sufficient to prevent
loading procedure 5.1 or as otherwise specified to the test pile adverse settlement of the weighted box or platform.
or pile group with the hydraulic jack(s) reacting against the test 3.4.3 Load the box or platform with any suitable material
beam(s). such as soil, rock, concrete, steel, or water-filled tanks with a
3.4 Load Applied to Pile or Pile Group by Hydraulic Jack(s) total weight (including that of the test beam(s) and the box or
Acting Against a Weighted Box or Platform (See Fig. 3): platform) at least 10 % greater than the anticipated maximum
3.4.1 Center over the test pile or pile group a test beam(s) of test load.
sufficient size and strength to avoid excessive deflection under 3.4.4 Apply the test loads to the pile or pile group in
load allowing sufficient clearance between the top of the test accordance with the standard procedure in 5.1 or as otherwise
pile or pile cap and the bottom(s) of the beam(s) after specified with the hydraulic jack(s) reacting against the test
deflection under load to accommodate the necessary bearing beam(s).
plates, hydraulic jack(s) (and load cell(s) if used). Support the 3.5 Load Applied Directly to the Pile or Pile Group with

3
D 1143

FIG. 3 Schematic Set-Up for Applying Loads to Pile Using Hydraulic Jack Acting Against Weighted Box or Platform

Known Weights (See Fig. 4, Fig. 5, and Fig. 6): wedges along the bottom edges of the platform so that the
3.5.1 Center on the test plate or pile cap a test beam(s) of platform is stable. Load the platform in accordance with the
known weight and of sufficient size and strength to avoid standard loading procedures in 5.1 or as otherwise specified
excessive deflection under load with the ends supported on using material such as steel or concrete so that the weight of
temporary cribbing if necessary to stabilize the beam(s). incremental loads can be determined within 5 %.
Alternatively the known test weights or loading material may
be applied directly on the pile or pile cap. NOTE 8With the loading apparatus described in 3.5, provisions can be
made for taking target rod level readings directly on the center of the pile
3.5.2 Center and balance a platform of known weight on the
butt or pile cap or center of the test plate to measure pile butt movements
test beam(s) or directly on the pile cap with overhanging edges in 4.2.3. For tests on concrete piles, or on pile groups, a hole would be
of the platform parallel to the test beam(s) supported by required in the center of the test plate through which would extend a steel
cribbing or by piles capped with timber beams, so that a clear pin embedded in the top of the pile or pile cap. For tests on steel H or
distance of not less than 5 ft. (1.5 m) is maintained between the timber piles, readings would be taken on the test plate. To accommodate
supports and the test pile or pile group. the target rod, a double test beam must be used with sufficient space
3.5.3 Place sufficient pairs of timber wedges between the between the beams and a hole must be left through the platform. To permit
sighting on the target rod it may be necessary to leave a space between the
top of the cribbing or timber cap beams and the bottom edges
test weights in line with the line of sight.
of the platform so that the platform can be stabilized during
loading or unloading. 3.6 Other Types of Loading Apparatus (Optional)Any
3.5.4 When ready to load the platform, remove any tempo- other type of loading apparatus satisfying the basic require-
rary supports at the ends of the test beam(s) and tighten the ments of 3.3 or 3.4 may be used.

FIG. 4 Schematic Set-Up for Applying Loads Directly to Pile Using Weighted Platform

4
D 1143

FIG. 5 Possible Arrangement for Applying Load Test to Pile Group Using Weighted Platform

FIG. 6 Arrangement for Applying Tests Loads Directly on Pile Cap for Group Tests

4. Apparatus for Measuring Movement 4.1.3 All dial gages, scales and reference points shall be
4.1 General: clearly marked with a reference number or letter to assist in
4.1.1 All reference beams and wires shall be independently recording data accurately. Provisions shall be made to protect
supported with supports firmly embedded in the ground at a the measuring system, reference system, and instrumentation
clear distance of not less than 8 ft (2.5 m) from the test pile or from adverse temperature variations and from disturbance. All
pile group and as far as practical from the anchor piles or gages, scales, or reference points attached to the test pile or pile
cribbing. Reference beams shall be sufficiently stiff to support cap shall be mounted so as to prevent movement relative to the
the instrumentation such that excessive variations in readings test pile or pile cap during the test.
do not occur and should be cross connected to provide 4.2 Pile Butt Axial Movements (See Fig. 7)The apparatus
additional rigidity. If steel reference beams are used, one end of for measuring axial movement of the butt of the test pile or
each beam shall be free to move horizontally as the beam piles within the group shall consist of a primary and secondary
length changes with temperature variations. system in accordance with the following methods.
4.1.2 Dial gages shall have at least a 2-in. (50-mm) travel; NOTE 9Two separate measuring systems are required in order to have
longer gage stems or sufficient gage blocks shall be provided to a check on the observed data, to provide for accidental disturbance of the
allow for greater travel if anticipated. Except as required in measuring system, and to permit continuity of data in case it becomes
4.4.2, gages shall have a precision of at least 0.01 in. (0.25 necessary to reset the gages or scales.
mm). Smooth bearing surfaces (such as glass) perpendicular to 4.2.1 Dial GagesTwo parallel reference beams, one on
the direction of gage-stem travel shall be provided for the gage each side of the test pile or pile cap, shall be oriented in a
stems. Scales used to measure pile movements shall read to direction that permits placing their supports as far as practi-
1/64th of an inch or to 0.01 in. (0.25 mm). Target rods shall cable from anchor piles or cribbing. A minimum of two dial
read to 0.001 ft (0.3 mm). gages shall be mounted on the reference beams approximately

5
D 1143
directly from the scale by lining up the wire and its image in
the mirror. The wire shall be not more than 1 in. (25 mm) from
the face of the scale. A suitable method shall be used to
maintain tension in the wires throughout the test so that when
plucked or tapped, the wire will return to its original position.
Piano wire or equivalent type shall be used.
4.2.3 Surveyors Level or Laser BeamReadings using a
surveyors level or laser beam shall be taken on a target rod or
a scale and shall be referenced to a permanent bench mark
located outside of the immediate test area or, alternatively, the
surveyors level shall be mounted on an object of fixed
elevation (for example a driven pile) outside of the immediate
test area. Reference points or scales used in taking settlement
readings shall be mounted on the sides of the test pile or pile
cap and located on opposite sides except that reference points
may be on top of the pile cap or readings may be taken on a
single fixed point in the center of the test pile top, test plate or
pile cap or on scales mounted on the test plate provided that
relative movements between the test plate and the top of the
pile are measured in accordance with 4.2.1 (see Fig. 7).
4.2.4 Other Types of Measuring Apparatus (Optional)
Any other type of measuring device such as electric or optical
gages of proven reliability and that yield an accuracy of 0.01
in. (0.25 mm) may be used.
4.3 Lateral Movements (Optional) The lateral movements of
FIG. 7 Possible Arrangement of Instrumentation for Measuring the top of the test pile or pile group shall be measured to an
Vertical Movements of Pile accuracy of 0.1 in. (2.5 mm) using either of the following
methods: (a) two dial gages mounted on the reference beam
90 apart with their stems perpendicular to the longitudinal
equidistant from the center of and on opposite sides of the test axis of the test pile(s) and bearing against the sides of the test
pile or pile cap with stems parallel to the longitudinal axis of pile or pile cap, or (b) an engineers transit reading from fixed
the pile(s) and bearing on lugs firmly attached to the sides of positions scales mounted horizontally on the sides of the test
the pile or pile cap below the test plate. Alternatively, the two pile or pile cap 90 apart with readings referenced to fixed
dial gages shall be mounted on opposite sides of the test pile or foresights or backsights. For tests on batter piles, one of the
pile cap below the test plate with stems parallel to the gages or scales shall be oriented in the direction of the batter.
longitudinal axis of the pile(s) and bearing on lugs firmly 4.4 Incremental Strain Measurements (Optional):
attached to the reference beams. However, gages may be 4.4.1 The test pile(s) shall be instrumented as specified to
mounted to bear on the top of the pile cap or on the test plate determine distribution of load transfer from the pile to the soil.
provided that two additional gages shall be mounted on If strain rods or telltales (see Fig. 7, Fig. 8, Fig. 9, and Fig. 10)
opposite sides of the test plate to measure relative movements are used, they shall be installed in or on the test pile
between the test plate and the pile or pile cap (see Fig. 7). For terminating at the pile tip and at other points along the pile as
tests on individual batter piles, the dial gages shall be mounted required and shall be sheathed or encased to insure free
along a line perpendicular to the direction of batter. movement of the rods during the test. The influence of the
NOTE 10The use of four dial gages mounted 90 apart is recom- sheathing on the elastic properties of the pile section shall be
mended to compensate for lateral movement or rotation of the pile butt considered. If electric resistant strain gages are used, the gage
due to accidental eccentric loading. type and installation shall be as specified and shall include
NOTE 11For tests on batter piles, it is recommended that a dial gage temperature compensating gages.
be mounted in line with the direction of batter through the center of the
test pile with the gage stem perpendicular to the longitudinal axis of the NOTE 12Where feasible, measurement programs involving strain
pile and bearing against a lubricated glass plate to measure lateral gages should include calibration of the fully instrumented pile and a
movements. complete strain history starting before the pile is installed.
4.2.2 Wire, Mirror, and ScaleTwo parallel wires, one on 4.4.2 Pile butt axial movements shall be measured with dial
each side of the test pile or pile cap, shall be oriented in a gages (see 4.2.1). The movements of the top of each strain rod
direction that permits placing the wire supports as far as relative to the top of the test pile shall be measured with a dial
practicable from anchor piles or cribbing. Each wire shall pass gage reading to 0.001 in. (0.025 mm). Dial gages shall be
across and be clear of the face of a scale that is mounted referenced to points on the test pile below the test plate except
parallel to the axis of the test pile or piles within the group and that they may be referenced to the top of the test plate if the
that is attached to a mirror fixed to the test pile or pile cap so plate is welded to the pile or if relative movements between the
that consistent readings of axial movement can be made top of the test pile and the test plate are measured in accordance

6
D 1143

FIG. 8 Possible Installation of Telltales for Steel H-Piles

FIG. 9 Possible Installation of Telltales for Pipe Piles


FIG. 10 Possible Installation of Telltales for Timber Piles

with 4.2.1 (see Fig. 7).


25 % of the total test load with 1 h between decrements. If pile
5. Loading Procedures failure occurs continue jacking the pile until the settlement
5.1 Standard Loading ProcedureUnless failure occurs equals 15 % of the pile diameter or diagonal dimension.
first, load the pile to 200 % of the anticipated pile design load 5.1.1 Direct Loading MethodWhen using the loading
for tests on individual piles or to 150 % of the group design method described in 3.5, include in the first load increment the
load for tests on pile groups, applying the load in increments of weight of the test beam(s) and the platform. Before adding or
25 % of the individual pile or group design load. Maintain each removing load increments, tighten the wedges along the
load increment until the rate of settlement is not greater than platform edges to stabilize the platform. Place or remove load
0.01 in. (0.25 mm)/h but not longer than 2 h. Provided that the increments in a manner which avoids impact and maintains the
test pile or pile group has not failed, remove the total test load load balanced at all times. After each load increment has been
anytime after 12 h if the butt settlement over a one-hour period added, loosen (but do not remove) the wedges and keep them
is not greater than 0.01 in. (0.25 mm); otherwise allow the total loose to permit the full load to act on the pile as settlement
load to remain on the pile or pile group for 24 h. After the occurs.
required holding time, remove the test load in decrements of NOTE 13Testing a pile to failure provides valuable information to the

7
D 1143
design engineer and is recommended for pile tests performed prior to the specified penetration rate until the total pile penetration is at
foundation design or to evaluate comparative performances of different least 15 % of the average pile diameter or diagonal dimension
type piles. Such testing permits the selection of optimum pile type and at which time release the load. If the pile stops penetrating
design load.
under the maximum applied load, release the load.
NOTE 14If the test pile(s) may exhibit or has exhibited negligible
settlement at the design load or may approach or has approached incipient
5.5.3 The rate of penetration may be controlled by checking
failure at the full test load, consideration may be given to increasing the the time taken for successive small equal increments of
standard loading increments at the start of the test or subsequent tests or penetration and by adjusting the rate of jacking accordingly.
to decreasing the standard loading increments during the latter stages of Alternatively, any mechanical or electrical device may be used
the test or subsequent tests. to monitor and control the penetration rate so that it remains
5.2 Cyclic Loading (Optional)For the first application of constant.
test load increments, apply such increments in accordance with 5.5.4 See 6.3 for measurement procedures.
5.1. After the application of loads equal to 50, 100, and 150 % 5.6 Quick Load Test Method for Individual Piles (Optional):
of the pile design load for tests on individual piles or 50 and 5.6.1 The apparatus for applying the load shall have a
100 % of the group design load for tests on pile groups, capacity as specified and shall be in accordance with 3.3 or 3.4.
maintain the total load in each case for 1 h and remove the 5.6.2 Apply the load in increments of 10 to 15 % of the
applied load in decrements equal to the loading increments, proposed design load with a constant time interval between
allowing 20 min between decrements. After removing each increments of 212 min or as otherwise specified. Add load
total applied load, reapply the load to each preceding load level increments until continuous jacking is required to maintain the
in increments equal to 50 % of the design load, allowing 20 test load or until the specified capacity of the loading apparatus
min between increments. Apply additional loads in accordance is reached, whichever occurs first, at which time stop the
with 5.1. After the total required test load has been applied, jacking. After a 5-min interval or as otherwise specified,
hold and remove the test load in accordance with 5.1. remove the full load from the pile.
5.3 Loading in Excess of Standard Test Load (Optional) 5.6.3 See 6.4 for measurement procedures.
After the load has been applied and removed in accordance NOTE 15For 5.5 and 5.6 it is recommended that the full test load be
with 5.1, reload the test pile or pile group to the standard test removed in four approximately equal decrements with 5 min between
load in increments of 50 % of the pile or pile group design decrements so the shape of the rebound curve may be determined.
load, allowing 20 min between load increments. Then increase 5.7 Constant Settlement Increment Loading Method for
the load in increments of 10 % of the design load for the pile Individual Piles (Optional):
or pile group until the maximum required load has been applied 5.7.1 The apparatus for applying the load shall have a
or until failure of the test pile or pile group occurs, allowing 20 capacity as specified and shall be in accordance with 3.3 or 3.4.
min between load increments. If failure does not occur, hold 5.7.2 Apply test loads in increments required to produce
the full load for 2 h and then remove the load in four equal pile butt settlement increments equal to approximately 1 % of
decrements, allowing 20 min between decrements. the average pile diameter or diagonal dimension. Vary the
5.4 Constant Time Interval Loading (Optional)Follow the applied load as necessary to maintain each settlement incre-
procedures of 5.1 except apply load in increments of 20 % of ment, and do not apply additional load until the rate of load
the pile or group design load with 1 h between load increments variation to hold that settlement increment constant is less than
and unload the piles with 1 h between load decrements. 1 % of the total applied load per hour. Continue loading the pile
5.5 Constant Rate of Penetration Method for Individual in such increments until the total butt settlement equals about
Piles (Optional): 10 % of the average pile diameter or diagonal dimensions or
5.5.1 The apparatus for applying loads shall have a capacity until the specified capacity of the loading apparatus is reached.
as specified and shall be in accordance with either 3.3 or 3.4. 5.7.3 Remove the full test load in four equal decrements
The hydraulic jack ram(s) shall have a travel greater than the after maintaining the final settlement increment until the rate of
anticipated total movement of the pile but not less than 25 % of load variation is less than 1 % of the total applied load per hour.
the average pile diameter or diagonal dimension. A mechanical After removing the first load decrement, do not remove
pump equipped with a bleed valve, variable speed device, or additional decrements until the rate of pile rebound for the
other means for providing a smooth variable delivery shall be preceding load decrement is less than 0.3 % of the average pile
used. If a video recording system is used to record the test data, diameter or diagonal dimension per hour.
a digital clock reading to seconds should be used and the clock 5.7.4 See 6.5 for measurement procedures.
as well as all gages shall be easily readable and located within NOTE 16For piles driven into cohesive soils, the elapsed time
the camera field. between driving and testing should be sufficient to allow dissipation of any
5.5.2 Vary the applied load as necessary to maintain a pile excess pore water pressure resulting from pile driving and to permit the
penetration rate of 0.01 to 0.05 in. (0.25 to 1.25 mm)/min for regain of the soil strength (known as soil freeze). The waiting period will
cohesive soil or 0.03 to 0.10 in. (0.75 to 2.5 mm)/min for depend on such things as the amount of excess pore water pressure built
up, the degree of soil structure disturbance resulting from pile driving, and
granular soils, or as otherwise specified. Continue loading the the soil properties. It could range from a minimum of 3 days to as long as
pile until no further increase in the load is necessary for 30 days or longer and the actual required waiting period may be
continuous pile penetration at the specified rate unless the determined by testing (for example redriving piles) or by prior experience.
specified capacity of the loading apparatus is reached. If pile NOTE 17To avoid excessive creep of green concrete in cast-in-place
penetration continues, hold the load required to achieve the concrete piles, the elapsed time between concrete placement and pile

8
D 1143
testing should be sufficient to permit the concrete to cure and harden Take readings of time, load, and settlement, and record
properly, recognizing that the curing time for the concrete in the pile immediately before and after each settlement increment with
generally will be longer than that for the sampled concrete in standard test sufficient intermediate readings so as to determine the rate of
cylinders.
load variation and the actual load required to maintain each
6. Procedures for Measuring Pile Movements settlement increment. During unloading, take readings of time,
load, and rebound, and record immediately before and after the
6.1 GeneralFor axial movements, take readings on the
removal of each load decrement with sufficient intermediate
test pile or pile cap; readings may be taken on the test plate,
readings so as to determine the rate of pile rebound. Take final
provided that the requirements of 4.2.1 are satisfied. For lateral
readings and record 12 h after all load has been removed.
movements, taken readings on the sides of the test pile or pile
cap. Take required readings at each properly identified gage, NOTE 19Level readings should be taken on the reference beams and
scale, or reference point as nearly simultaneously as practi- on the reaction system using a surveyors level or transit and target rod or
cable. When using the loading method described in 3.5, take scale to determine if any excessive movement occurs. Such readings
should be taken and recorded before any test load is applied, at the
the no-load reading before the test beam(s) and platform are
proposed design load, at the maximum test load, and after all load has
permitted to bear on the pile(s). Clearly indicate and explain been removed. Intermediate readings may be required if results during
any adjustments made to instrumentation or to data recorded in testing appear unusual.
the field. NOTE 20When testing piles in granular soils in dewatered excava-
6.2 Standard Measuring ProceduresTake readings of tions which will be submerged during service, the groundwater level
time, load, and movement, and record them before and after the should be maintained as near to the existing ground surface as possible
application of each load increment or the removal of each load and the depth to the groundwater level should be measured and recorded
decrement. During loading, provided that the test pile or pile during the test. If the groundwater level during the test is more than 5 ft
(1.5 m) below the ground surface, a correction to the pile bearing capacity
group has not failed, take additional readings and record them as determined by the test should be made.
at intervals not exceeding 10 min during the first 12 h nor 20
min thereafter for each load increment. After the total load has 7. Safety Requirements
been applied, provided that the test pile or pile group has not
7.1 All operations in connection with pile load testing shall
failed, take readings and record at intervals not exceeding 20
be carried out in such a manner so as to minimize, avoid, or
min during the first 2 h, not exceeding 1 h for the next 10 h, and
eliminate the exposure of people to hazard. The following
not exceeding 2 h for the next 12 h. If pile failure occurs, take
safety rules are in addition to general safety requirements
readings immediately before removing the first load decre-
applicable to construction operations:
ment. During unloading, take readings and record at intervals
not exceeding 20 min. Take a final rebound reading 12 h after 7.1.1 All work areas, walkways, platforms, etc., shall be
all load has been removed. kept clear of scrap, debris, small tools, and accumulations of
snow, ice, mud, grease, oil, or other slippery substances.
NOTE 18If incremental strain measurements as in 4.4 are made using 7.1.2 All timbers, blocking and cribbing materials shall be
strain gages, gage readings should be taken and recorded before and after
of quality material and be in good serviceable condition with
the pile is installed and immediately before the application of test loads so
that a complete strain history is obtained and residual stresses can be flat surfaces and without rounded edges.
accounted for. 7.1.3 Hydraulic jacks shall be equipped with spherical
bearing plates or shall be in complete and firm contact with the
6.3 Readings for Constant Rate of Penetration Loading
bearing surfaces and shall be aligned so as to avoid eccentric
Take readings of time, load, and settlement, and record at least
loading.
every 30 s or at sufficient intervals to determine the rate of
penetration being achieved. If automatic monitoring and re- 7.1.4 Loads shall not be hoisted, swung, or suspended over
cording devices are used, operate them continuously during anyone and shall be controlled by tag lines.
each test. When the test pile has achieved its specified rate of 7.1.5 The attachments of the test beam(s) or reaction frame
penetration, continue to take and record readings for the to the anchor piles or other anchoring devices shall be designed
duration of the loading, and determine the maximum load and installed to transmit the required loads with an adequate
applied. Immediately after unloading, take and record readings factor of safety.
of time, load, and rebound. Take final readings and record 1 h 7.1.6 For tests on batter piles, all inclined jacks, bearing
after all load has been removed. plates, test beam(s), or frame members shall be firmly fixed
6.4 Readings for Quick Load Test MethodTake readings into place or adequately blocked to prevent slippage upon
of time, load, and settlement, and record immediately before release of load.
and after the application of each load increment and at 7.1.7 All reaction loads shall be stable and balanced. When
intermediate time intervals as specified. When the maximum using loading method in 3.5, safety wedges shall be in place at
load has been applied, take readings and record when the all times to prevent the platform from tipping. During testing,
jacking is stopped. Repeat after 212 min and again at 5 min movements of the reaction load or system should be monitored
thereafter. If a longer holding period than in 5.7.2 is specified, to detect impending unstable conditions.
take and record additional readings as specified. Take readings 7.1.8 All test beams, reaction frames, platforms, and boxes
of time and rebound, and record after all load has been shall be adequately supported at all times.
removed. Repeat after 212 min and again at 5 min thereafter. 7.1.9 Only authorized personnel shall be permitted within
6.5 Readings for Constant Settlement Increment Method the immediate test area.

9
D 1143
8. Report cracks, head surface, and straightness of piles.
8.1 The report of the load test shall include the following 8.1.3.18 Effective prestress,
information when applicable: 8.1.3.19 Which piles vertical or batter,
8.1.1 General: 8.1.3.20 Degree of batter,
8.1.1.1 Project identification, 8.1.3.21 Length of test pile during driving,
8.1.1.2 Project location, 8.1.3.22 Embedded lengthtest and anchor piles,
8.1.1.3 Test site location, 8.1.3.23 Tested length of test pile, and
8.1.1.4 Owner, 8.1.3.24 Final elevation of test pile butt(s) referenced to
8.1.1.5 Structural engineer, fixed datum.
8.1.1.6 Geotechnical engineer, 8.1.4 Pile InstallationTest and Anchor:
8.1.1.7 Pile contractor, 8.1.4.1 Date driven (installed),
8.1.1.8 Test boring contractor, 8.1.4.2 Date concreted (cast-in-place),
8.1.1.9 Designation and location of nearest test boring with 8.1.4.3 Volume of concrete or grout placed in pile,
reference to test pile or group, 8.1.4.4 Grout pressure used,
8.1.1.10 Log of nearest test boring, 8.1.4.5 Description of pre-excavation or jetting (depth, size,
8.1.1.11 Horizontal control datum, and pressure, duration),
8.1.1.12 Vertical control (elevation) datum. 8.1.4.6 Operating pressure for double-acting and differential
8.1.2 Pile Installation Equipment: type hammers,
8.1.2.1 Make, model, type and size of hammer, 8.1.4.7 Throttle settingdiesel hammer (at final driving),
8.1.2.2 Weight of hammer and ram, 8.1.4.8 Fuel typediesel hammer,
8.1.2.3 Stroke or ram, 8.1.4.9 Horsepower delivered and frequency of vibratory
8.1.2.4 Rated energy of hammer, driver during final 10 ft (3 m) of pile penetration,
8.1.2.5 Rated capacity of boiler or compressor, 8.1.4.10 Description of special installation procedures used
8.1.2.6 Type and dimensions of capblock and pile cushion, such as piles cased off,
8.1.2.7 Weight and dimensions of drive cap and follower, 8.1.4.11 Type and location of pile splices,
8.1.2.8 Size of predrilling or jetting equipment, 8.1.4.12 Driving logs (blows per foot),
8.1.2.9 Weight of clamp, follower, adaptor, and oscillator 8.1.4.13 Final penetration resistance (blows per inch),
for vibratory driver. 8.1.4.14 Rate of pile penetration for last 10 ft (3 m) s/ft,
8.1.2.10 Type, size, length, and weight of mandrel, vibratory driving,
8.1.2.11 Type, size, and length of auger, 8.1.4.15 When capblock replaced (indicate on log),
8.1.2.12 Type and size of grout pump, and 8.1.4.16 When pile cushion replaced (indicate on log),
8.1.2.13 Type, size, wall thickness, and length of drive 8.1.4.17 Cause and duration of interruptions in pile instal-
casing. lation, and
8.1.3 Test and Anchor Piles: 8.1.4.18 Notation of any unusual occurrences during instal-
8.1.3.1 Identification and location of test and anchor piles, lation.
8.1.3.2 Design load of pile or pile group, 8.1.5 Pile Testing:
8.1.3.3 Type of pile(s)test and anchor, 8.1.5.1 Date tested,
8.1.3.4 Test pile material including basic specifications, 8.1.5.2 Type test,
8.1.3.5 Tip and butt dimensions of pile(s), 8.1.5.3 Number of piles in group test,
8.1.3.6 General quality of timber test piles including occur- 8.1.5.4 Brief description of load application apparatus, in-
rence of knots, splits, checks and shakes, and straightness of cluding jack capacity,
piles, 8.1.5.5 Description of instrumentation used to measure pile
8.1.3.7 Preservative treatment and conditioning process movement including location of gages or other reference points
used for timber test piles including inspection certificates, with respect to pile butt (see Note 21),
8.1.3.8 Wall thickness of pipe test pile, 8.1.5.6 Description of special instrumentation such as strain
8.1.3.9 Weight per foot of H test pile, rods or gages including location of such with reference to pile
butt,
8.1.3.10 Description of test pile tip reinforcement or protec-
tion, 8.1.5.7 Special testing procedures used,
8.1.5.8 Tabulation of all time, load, and movement readings,
8.1.3.11 Description of bandingtimber piles,
8.1.5.9 Identification and location sketch of all gages,
8.1.3.12 Description of special coatings used,
scales, and reference points (see Note 21),
8.1.3.13 Test pile (mandrel) weight as driven,
8.1.5.10 Description and explanation of adjustments made
8.1.3.14 Date precast test piles made,
to instrumentation or field data, or both,
8.1.3.15 Concrete cylinder strengths when test pile driven
8.1.5.11 Notation of any unusual occurrences during testing,
and when pile tested (approximate),
8.1.5.12 Test jack and other required calibration reports,
8.1.3.16 Description of internal reinforcement used in test
8.1.5.13 Groundwater level (see Note 20), and
pile (size, length, number longitudinal bars, arrangement,
8.1.5.14 Temperature and weather conditions during tests.
spiral, or tie steel),
8.1.3.17 Condition of precast piles including spalled areas, NOTE 21Suitable photographs can be very helpful in showing the

10
D 1143
instrumentation set-up, location of gages, scales, and reference points. 9.2 BiasA statement on bias is not possible because there
NOTE 22In addition to the above required information to be reported, are no standard reference materials.
the results of any in-place and laboratory soil tests should be made
available for the proper evaluation of test results.
10. Keywords
9. Precision and Bias 10.1 field testing; load cell; loading procedure; piles; refer-
9.1 PrecisionData are being evaluated to determine the ence beam
precision of this test method. In addition, Subcommittee
D18.11 is seeking pertiment data from users of this test
method.

APPENDIX

(Nonmandatory Information)

X1. SOME FACTORS INFLUENCING INTERPRETATION OF TEST RESULTS

X1.1 Potential residual loads in the pile which could X1.6 Possible differences in the performance of a pile in a
influence the interpreted distribution of load at the pile tip and group or of a pile group from that of a single isolated pile.
along the pile shaft.
X1.7 Affect on long-term pile performance of factors such
X1.2 Possible interaction of friction loads from test pile as creep, environmental effects on pile material, negative
with upward friction transferred to the soil from anchor piles friction loads not previously accounted for, and strength losses.
obtaining part or all of their support in soil at levels above the
tip level of the test pile. X1.8 Type of structure to be supported, including sensitiv-
ity of structure to settlements and relation between live and
X1.3 Changes in pore water pressure in the soil caused by dead loads.
pile driving, construction fill, and other construction operations
which may influence the test results for frictional support in X1.9 Special testing procedures which may be required for
relatively impervious soils such as clay and silt. the application of certain acceptance criteria or methods of
interpretation.
X1.4 Differences between conditions at time of testing and
after final construction such as changes in grade or groundwa- X1.10 Requirement that all conditions for nontested piles
ter level. be basically identical to those for test pile including such things
as subsurface conditions, pile type, length, size and stiffness,
X1.5 Potential loss of soil supporting test pile from such and pile installation methods and equipment so that application
things as excavation and scour. or extrapolation of the test results to such other piles is valid.

The American Society for Testing and Materials takes no position respecting the validity of any patent rights asserted in connection
with any item mentioned in this standard. Users of this standard are expressly advised that determination of the validity of any such
patent rights, and the risk of infringement of such rights, are entirely their own responsibility.

This standard is subject to revision at any time by the responsible technical committee and must be reviewed every five years and
if not revised, either reapproved or withdrawn. Your comments are invited either for revision of this standard or for additional standards
and should be addressed to ASTM Headquarters. Your comments will receive careful consideration at a meeting of the responsible
technical committee, which you may attend. If you feel that your comments have not received a fair hearing you should make your
views known to the ASTM Committee on Standards, 100 Barr Harbor Drive, West Conshohocken, PA 19428.

11

You might also like