Professional Documents
Culture Documents
Structures (NCRACCESS-2015)
major district road, state highway road, national The cost of the project includes
highway roads, major bridges and flyovers are expenditure on various items from planning to
being constructed for easy flow traffic. The the yearly maintenance up to the end of useful
flyover or over bridges are to be designed Class life of the project. Generally they are,
A loading and AA loading.
1) Cost of preliminary survey
Necessity of flyover or over bridges: 2) Cost of acquisition of land
3) Cost of various structure
For easy traffic flow of agricultural 4) Maintenance cost
goods and industrial goods without traffic 5) Operation cost
congestion flyover or over bridges is essentially 6) Cost of tools and plants
to overcome the traffic congestion required. 7) Cost of establishment of construction.
Location:
Traffic censes: Construction of a flyover across salem-
For designing any bridges or flyover the Krishnagiri road in Salem town. The length of
traffic censes is essential to ascertain the traffic flyover 40m and length of approaches is 600m.
censes we have to observe the vehicles censes. The total length of flyover is 640m and width of
8m.
Selection of site:
The component of the project:
1) The following points are the guiding
factors for selection of suitable site, This project is consist of main deck slab,
2) The roads are crossing deck beam, piers, girders, foundation, handrails,
perpendicular to each other. wings of slope is 1 in 30. Soil available is clay
3) The site should have more traffic mixed with gravel. The bearing capacity of soil
congestion. is 245 kN/m. The width of road is 8m, length of
4) The availability of men and deck is 40m, c/c of pier is 20m, cross beam as
materials are to be ascertained also being placed at 4m c/c. The dia of pier is
Selection of types of flyover: 1.2m.
As per IRC: 92-2000, the traffic volume limit is Net BM along shorter span = 17.15KNm
10000PCUs/hour. The capacity of junction was Net BM along longer span = 3.05KNm
estimated at 6547 PCSs / hour. The design
period is taken as 30 years. One year would be BM due to wheel 5:
taken for the construction. So traffic is Net BM along shorter span = 17.15KNm
projection. So traffic is projected for 32 years, Net BM along longer span = 3.05KNm
and then the design is made and it was 11068. BM due to wheel 6:
Net BM along shorter span = 8.92KNm
III.PRELIMINARY DESIGN: Net BM along longer span = 1.59KNm
Total BM along shorter span = 67.18KNm
Clear road way = 8 m Total BM along longer span = 54.26KNm
Assume five T-beams spaced at 2.5m c/c Design of BM
Width of bearing (assumed) = 0.8 m Design BM along shorterspan= 84.046KNm
Effective span of T- beam = 20 m Design BM along longer span = 66.30KNm
Assume cross beams at 4 m centers. Reinforcement
M20 grade concrete according to IS : 456-2000 Shorter span:
and Fe415 steel confirming to IS : 432-1982 will Use 16mm dia bars at 120mm c/c spacing as
be used. main reinforcement.
Longer span:
IV.DESIGN OF DECK SLAB Use 16mm dia bars at 200 mm c/c.
Cantilever slab design
Slab is supported on the four sides by the beams. Moment due to unit load:
Thickness of the slab = 250 mm Total max. moment due to dead load =
Thickness of the wearing coat = 80 mm 18.33KNm
Span in transverse direction = 2.5 m c/c Moment due to live load:
Span in longitudinal direction = 4 m c/c Max. moment due to live load= 55.73KNm
Reinforcement:
Max.BM. Due to dead load: Total moment due to DL.&LL. =
Total weight = 8.2KN/m2 111.84KNm
Total dead load = 57.646KN Area of main reinforcement:
Moment along longer span = 0.992KNm Provide 16mm dia bars at 110mm c/c
Moment along shorter span = 2.85KNm BM for distribution reinforcement:
Use 12mm dia bars at 220mm c/c
Class AA loading track located for Max. BM Design of cross beam
on deck slab. Dead load for design:
Track contact length taken from IRC:6-1996 Total slab load = 6.25KN/m2
bridge code section II Total load of cross beam = 11.88KN/m
BM. along shorter span = 31.18KNm BM at a distance 1.475 = 16.28KNm Check
BM. along longer span = 10.32KNm for shear:
Live load BM due to IRC class AA wheeled Shear stress, v = 1.56N/mm2
vehicle: From table 19 of IS456:2000 for Pt value
BM. Due to wheel 1: Nominal shear stress c =3.1N/mm2
BM. along shorter span = 16.28KNm v < c
BM. along longer span = 13.21KNm Hence safe.
BM. Due to wheel 2:
Net BM along shorter span = 0.690KNm V.DESIGN OF FOOTING
Net BM along longer span = 0.37KNm
BM. Due to wheel 3: Axial load = 5000 kN
Net BM along shorter span = 4.58KNm S.B.C. of Soil, q0 = 245 kN/m
Net BM along longer span = 4.01KNm BM Angle of repose, = 30
due to wheel 4: Weight of soil, We = 20 kN/m
= 20 kN/m
Angle of response
= 30
Safe bearing capacity of soil TRAFFIC FLOW AFTER CONSTRUCTION
= 245 kN/m
Co-efficient of friction
= 0.5
Use M25 concrete and Fe415steel
SALEM KRISHNAGIRI
Design of toe slab:
Provide 16mm dia bars at 220mm c/c
Design of Shear key:
Provide 16mm dia bars at 200mm c/c. 8000.00