You are on page 1of 5

National Conference on Research Advances in Communication, Computation, Electrical Science and

Structures (NCRACCESS-2015)

ANALYSIS AND DESIGN OF FLYOVER


Kavitha.N1, Jaya kumari.R1, Jeeva.K1, Bavithra.K1, Kokila.K2.
1
Student, 2Assistant professor in Department of Civil Engineering,
Bharathiyar Institute of Engineering for Women, Deviyakurichi, Salem.

ABSTRACT Our project deals with the Design of a


grade separator in an intersection. The location
Our project deals with the Design of a is at four roads junction at SALEM town, which
grade separator in an intersection. The location is is facing major traffic problems due to the
at four roads junction at SALEM town, which is construction.
facing major traffic problems due to the
construction. We have done a traffic survey and We have done a traffic survey and
designed all the structural parts for this grade designed all the structural parts for this grade
separator. separator.
The grade separator is of 640 m length with 21 All the drawings are drafted by Auto-
spans, 20m per span. It consists of a deck slab, CAD 2013 and analysis by STAAD pro vis8.
longitudinal girders, cross girders, deck beam,
pier and foundation. Structural design of one span I. INTRODUCTION
was made for all the above components.
Present trend of development:
Slab is designed by Working stress method as
per the recommendation of IRC:21-2000, Clause Our nation being primarily an
304.2.1. Cantilever slab is designed for maximum
agricultural country. 90% of population is
moment due to cantilever action. Longitudinal
girders are designed by Courbons method. Cross
depending upon it and 10% of population
girders are designed mainly for stiffness to depending upon industrial activities. For
longitudinal girders. Elastomeric reinforced conveying the product materials such as food
bearing plate is used. grains, industrial goods the roads are essential.
The roads and bridges are very important for
The deck beam is designed as a cantilever on a growth of economy of the country. Now our
pier. The Pier is designed for the axial dead load country is being developed by developing roads
and live load from the slab, girders, deck beam. and bridges.
Foundation designed as footing for the safe load
bearing in the soil. All the elements are designed Types of roads and bridges:
by using M25
grade concrete and Fe415grade steel. Designs are In our country there are so many types of
based on Working stress and Limit state method roads are being constructed,
as per IRC: 21-2000 and IS: 456-2000.
1) Cart roads
OBJECTIVE
2) Minor district roads
The project area is having very high density 3) Major district roads
of traffic flow. The public felt inconvenient to 4) Sate highway roads
cross the busy Salem-krishnagiri highways & 5) National highways roads
therefore the flyover is essentially required at the Accordingly the culverts bridges,
junction. flyover, are being constructed as mentioned
below,
For easy traffic flow of agricultural goods
and industrial goods without traffic congestion For small cart road and minor district
flyover or over bridges is essential to overcome roads, small culverts bridges, small flyover are
the traffic congestion required. constructed with minimum class A load. For

ISSN: 2348 8352 www.internationaljournalssrg.org Page 40


National Conference on Research Advances in Communication, Computation, Electrical Science and
Structures (NCRACCESS-2015)

major district road, state highway road, national The cost of the project includes
highway roads, major bridges and flyovers are expenditure on various items from planning to
being constructed for easy flow traffic. The the yearly maintenance up to the end of useful
flyover or over bridges are to be designed Class life of the project. Generally they are,
A loading and AA loading.
1) Cost of preliminary survey
Necessity of flyover or over bridges: 2) Cost of acquisition of land
3) Cost of various structure
For easy traffic flow of agricultural 4) Maintenance cost
goods and industrial goods without traffic 5) Operation cost
congestion flyover or over bridges is essentially 6) Cost of tools and plants
to overcome the traffic congestion required. 7) Cost of establishment of construction.
Location:
Traffic censes: Construction of a flyover across salem-
For designing any bridges or flyover the Krishnagiri road in Salem town. The length of
traffic censes is essential to ascertain the traffic flyover 40m and length of approaches is 600m.
censes we have to observe the vehicles censes. The total length of flyover is 640m and width of
8m.
Selection of site:
The component of the project:
1) The following points are the guiding
factors for selection of suitable site, This project is consist of main deck slab,
2) The roads are crossing deck beam, piers, girders, foundation, handrails,
perpendicular to each other. wings of slope is 1 in 30. Soil available is clay
3) The site should have more traffic mixed with gravel. The bearing capacity of soil
congestion. is 245 kN/m. The width of road is 8m, length of
4) The availability of men and deck is 40m, c/c of pier is 20m, cross beam as
materials are to be ascertained also being placed at 4m c/c. The dia of pier is
Selection of types of flyover: 1.2m.

We have to select types of flyover Design and drawings:


according to traffic censes By adopting the AA loading and being
Land acquisition: capability of soil the foundation as been
designed. The piers, wings, decks slab, main
If the highways or government beams and crossbeams are designed suitably.
promboke land are not available at site the
private land to be acquired for construction of II.TRAFFIC SURVEY
our bridges. Traffic survey was made on 06.01.2015, in
Benefit cost ratio: the project site from 6.00 pm to7.00 pm. This
time was selected on the basic of the past traffic
The annual cost of above ratio is study as an average of peak hour. All the four
calculated by taking 10% of interest at 1% of arms of the site was observed and the number of
depreciation on the incurred expenditure of the vehicles passed was converted to PCUs
project and administrative expenses of the (Passenger car unit).
project. Now the ratio between the cost networks
overcomes of indirect income such that road tax TRAFFIC PROJECTION:
is to be calculated for reasonable periods. For The passenger car unit of a vehicle type
any project these ratio should be 1:1 has been found to be depends up on the size, and
Estimate: speed of the vehicle type and environment. They
are not dependent on the flow and road width.

ISSN: 2348 8352 www.internationaljournalssrg.org Page 41


National Conference on Research Advances in Communication, Computation, Electrical Science and
Structures (NCRACCESS-2015)

As per IRC: 92-2000, the traffic volume limit is Net BM along shorter span = 17.15KNm
10000PCUs/hour. The capacity of junction was Net BM along longer span = 3.05KNm
estimated at 6547 PCSs / hour. The design
period is taken as 30 years. One year would be BM due to wheel 5:
taken for the construction. So traffic is Net BM along shorter span = 17.15KNm
projection. So traffic is projected for 32 years, Net BM along longer span = 3.05KNm
and then the design is made and it was 11068. BM due to wheel 6:
Net BM along shorter span = 8.92KNm
III.PRELIMINARY DESIGN: Net BM along longer span = 1.59KNm
Total BM along shorter span = 67.18KNm
Clear road way = 8 m Total BM along longer span = 54.26KNm
Assume five T-beams spaced at 2.5m c/c Design of BM
Width of bearing (assumed) = 0.8 m Design BM along shorterspan= 84.046KNm
Effective span of T- beam = 20 m Design BM along longer span = 66.30KNm
Assume cross beams at 4 m centers. Reinforcement
M20 grade concrete according to IS : 456-2000 Shorter span:
and Fe415 steel confirming to IS : 432-1982 will Use 16mm dia bars at 120mm c/c spacing as
be used. main reinforcement.
Longer span:
IV.DESIGN OF DECK SLAB Use 16mm dia bars at 200 mm c/c.
Cantilever slab design
Slab is supported on the four sides by the beams. Moment due to unit load:
Thickness of the slab = 250 mm Total max. moment due to dead load =
Thickness of the wearing coat = 80 mm 18.33KNm
Span in transverse direction = 2.5 m c/c Moment due to live load:
Span in longitudinal direction = 4 m c/c Max. moment due to live load= 55.73KNm
Reinforcement:
Max.BM. Due to dead load: Total moment due to DL.&LL. =
Total weight = 8.2KN/m2 111.84KNm
Total dead load = 57.646KN Area of main reinforcement:
Moment along longer span = 0.992KNm Provide 16mm dia bars at 110mm c/c
Moment along shorter span = 2.85KNm BM for distribution reinforcement:
Use 12mm dia bars at 220mm c/c
Class AA loading track located for Max. BM Design of cross beam
on deck slab. Dead load for design:
Track contact length taken from IRC:6-1996 Total slab load = 6.25KN/m2
bridge code section II Total load of cross beam = 11.88KN/m
BM. along shorter span = 31.18KNm BM at a distance 1.475 = 16.28KNm Check
BM. along longer span = 10.32KNm for shear:
Live load BM due to IRC class AA wheeled Shear stress, v = 1.56N/mm2
vehicle: From table 19 of IS456:2000 for Pt value
BM. Due to wheel 1: Nominal shear stress c =3.1N/mm2
BM. along shorter span = 16.28KNm v < c
BM. along longer span = 13.21KNm Hence safe.
BM. Due to wheel 2:
Net BM along shorter span = 0.690KNm V.DESIGN OF FOOTING
Net BM along longer span = 0.37KNm
BM. Due to wheel 3: Axial load = 5000 kN
Net BM along shorter span = 4.58KNm S.B.C. of Soil, q0 = 245 kN/m
Net BM along longer span = 4.01KNm BM Angle of repose, = 30
due to wheel 4: Weight of soil, We = 20 kN/m

ISSN: 2348 8352 www.internationaljournalssrg.org Page 42


National Conference on Research Advances in Communication, Computation, Electrical Science and
Structures (NCRACCESS-2015)

Concrete grade = M20 The Deck slab is designed by using IRC:6-2000


Steel grade = Fe 415 codal provisions.
Load:
Load of column = 5000kN Here after in futher we have to consider
Self weight = 500kN the analysis, longitudinal girder, estimation,
Total load = 5500 kN steel requirement and cost of Analysis and
Reinforcement: Design of flyover.
Ast = 6378.82 mm
Provide 28mm dia bars at 90mm c/c.
Check for shear:
c = 3.1 N/mm
v = 2.05 N/mm EXISTING PROFILE
v < c
KRISHNAGIRI
Hence safe. SALEM

VI.DESIGN OF RETAINING WALL:


16000.00

Height of embankment above ground level


= 4.4m All dimention are in mm

Unit weight of soil 12000.00

= 20 kN/m
Angle of response
= 30
Safe bearing capacity of soil TRAFFIC FLOW AFTER CONSTRUCTION
= 245 kN/m
Co-efficient of friction
= 0.5
Use M25 concrete and Fe415steel
SALEM KRISHNAGIRI
Design of toe slab:
Provide 16mm dia bars at 220mm c/c
Design of Shear key:
Provide 16mm dia bars at 200mm c/c. 8000.00

VII. CONCLUSION 16000.00 All dimenstion are in mm

In this project traffic survey was conducted to


know the hourly Passenger Car Unit (HPCU) at
FOUR ROADS Intersection, SALEM. From 12000.00
survey the value of HPCU of the intersection is
6547, by considering future taking the design
period of 30 years, the value of HPCU is found
65273. From the above result it is proposed a REFERENCES
grade separator at that round about.
In this grade separator the main 1) K.S.RAKSHIT, Design and Construction of
components consists of Deck slab, longitudinal Highway Bridges New Central Book Agency, Kolkata.
girder, Cross girder, Bearing plate, Pier and 2) JAYARAM,T.R. JAGADEESH AND M.A.
Design of Bridge Structures Prentice Hall of India
Foundation. The geometric design of the grade
Pvt.Ltd., New Delhi
separator was done by using IRC Code Books. 3) D.JOHNSON VICTOR, Essentials of Bridge
Engineering Oxford and IBH Publishing Co. Pvt. Ltd.

ISSN: 2348 8352 www.internationaljournalssrg.org Page 43


National Conference on Research Advances in Communication, Computation, Electrical Science and
Structures (NCRACCESS-2015)
4) C.S. PAPACOSTAS, Fundamentals of
Transportation Engineering Prentice Hall of India Pvt Ltd,
New Delhi.
5) IRC 21-2000 STANDARD
SPECIFICATIONS AND CODE OF
PRACTICE FOR ROAD BRIDGES SECTION II
Cement Concrete (Plain
and Reinforced)
6) IRC 5-2000 STANDARD
SPECIFICATIONS AND CODE OF
PRACTICE FOR ROAD BRIDGES SECTION I - General
Features of
Design
7) IRC 6-2000 STANDARD
SPECIFICATIONS AND CODE OF
PRACTICE FOR ROAD BRIDGES SECTION II - Loads
and Stresses
8) IRC 78-2000 STANDARD
SPECIFICATIONS AND CODE OF
PRACTICE FOR ROAD BRIDGES SECTION VII
(Foundation And
Substructure)
9) IS 456-2000 PLAIN AND
REINFORCED CONCRETE CODE OF
PRACTICE
10) PERUMAL R.VAIDYANATHAN AND
P. Structural Analysis-Volume II Lakshmi Publications
Pvt. Ltd., New Delhi
11) KRISHNA RAJU,N. Structural Design &
Drawing Reinforced Concrete and Steel Universities Press
12) Treasure of R.C.C. Designs SUSHIL
KUMAR

ISSN: 2348 8352 www.internationaljournalssrg.org Page 44

You might also like