SpecificationforHandling,Transporting

andStoringofLinePipeandRelatedEquipment

SpecificationforHandling,TransportingandStoringofLinePipeandRelatedEquip 1of10
TABLEOFCONTENTS

1. SCOPE
2. DEFINITIONS
3. REFERENCES
4. CONTRACTORRESPONSIBILITIES
5. GENERALSPECIFICATIONS
6. PIPEINSPECTION

APPENDIXA: SUMMARYOFCONTRACTORDELIVERABLEDOCUMENTS

SpecificationforHandling,TransportingandStoringofLinePipeandRelatedEquip 2of10
1. SCOPE
AARSectionNo.2 AAR General
Thisspecificationsetsoutrequirementsfor RulesGoverningTheLoadingOfPipe
the handling, transporting, stacking and OnOpenTopCars
storing and inventory control of coated or c) COMPANYMaterialSpecifications
uncoated line pipe and related equipment. PS1001 Seamless Line Pipe for
Itappliestoallsuchactivitiesfromthetime Flowlines
the pipe or related equipment is loaded at PS1002 Specification for Material
the inspection facility and unloaded at the andApplicationofFusion
Worksite. Bonded Epoxy Corrosion
Coating for Steel Line
2. DEFINITIONS Pipe
PS1019 External Protective
COMPANY Coatings for Subsea
Components
CONTRACTOR Theorganization,person SP001 Specification for Steel
or company that contracts with COMPANY Line Pipe for Bundle
toperformserviceswhichrequirehandling, CasingandRiserCasing
transportation, storage and inventory SP002 Specification for Flowline
controloflinepipeandrelatedequipment. BundleSpacersandRiser
Spacers
CONTRACT The entire written SP004 Specification for Material
procurement agreement between and Application of
CONTRACTORandCOMPANY. Abrasion Resistant
Coating for Steel Line
NONCONFORMITY Aninstanceoffailureto Pipe
meet contractual requirements, including SP006 Specification for Pipe
physical, procedural or performance Bends
deficiencies. SP007 Specification for
SacrificialAnodes
3. REFERENCES SP008 SpecificationforSyntactic
3.1 GENERAL FoamBuoyancyUnits
The appropriate sections of the latest SP009 Specification for Thermal
versions of the following codes, standards InsulationforFlowlinesin
and guidelines are incorporated by the Bundle and in the
referenceasapartofthisspecification. Riser
SP010 Specification for Heating
3.2 CODES,STANDARDSANDGUIDELINES PipeandBuoyancyPipe
SP011 Specification for Steel
a) AmericanPetroleumInstitute LinePipeforAnnulusLine
APIRP5LWTransportationOfLine SP012 Specification for Towing
PipeOnBargesAndMarineVessels Gear
b) AssociationofAmericanRailways SP015 Specification for Pipe
AARSectionNo.1 AAR General Flanges
Rules Governing The Loading Of SP016 Specification for Pipe
CommoditiesOnOpenTopCars Fittings
SpecificationforHandling,TransportingandStoringofLinePipeandRelatedEquip 3of10
SP020 Specification for materialsfoundtobedamagedatthetime
Neoprene Coating of CONTRACTOR assumes custody shall be
RiserCasing replaced or repaired by CONTRACTOR,
unless CONTRACTOR can produce verified
4. CONTRACTORRESPONSIBILITIES inspection records showing that the
4.1 GENERAL materialwasdamagedwhenCONTRACTOR
CONTRACTORS who handle, transport or received it. Replacements or repairs shall
store line pipe shall be totally responsible conform to the appropriate COMPANY
forpropercareofthepipeduringthetime specification from the list in Section 3.2.c
they have custody of the pipe. and shall be approved by COMPANY.
CONTRACTOR will be considered to have CONTRACTOR shall provide a schedule for
custody during the period from collection material replacement for COMPANY
through final delivery at the locations approval. At COMPANY option,
specifiedinCONTRACT.CONTRACTORshall CONTRACTOR shall replace or pay for the
provide all labor, materials, tools, dunnage material which is missing when custody is
and equipment and shall undertake all transferred.
preparation of permit applications,
inspections, handling, reporting, storage 4.5 REPORTINGANDAPPROVALS
andshippingnecessarytoperformthework 4.5.1 CONTRACTORWorkPlan
required herein. If CONTRACTOR believes Atleast45daysbeforebeginningthework,
that this specification conflicts with other CONTRACTOR shall submit plans and
termsoftheCONTRACT,CONTRACTORshall procedures for performing the work
informCOMPANYandtheconflictsshallbe required in this specification and the
resolvedbythemethodsandproceduresof CONTRACT. Work shall not begin until
theCONTRACT. CONTRACTOR receives COMPANY written
approvalofCONTRACTORworkplan,which
4.2 SUBCONTRACTORS shallincludebutnotbelimitedto:
CONTRACTOR shall be responsible for the
actions and performance of its a) Procedures for loading, unloading
Subcontractors. transporting and handling all of the
materials with a description of
4.3 PROJECTDOCUMENTS equipment and means of
Project documents shall be in English, transportationtobeused
prepared in basic US sizes of 8.5" wide by b) Procedures for storing all of the
11" long and progressively larger related materials,themethodofsupporting
papersizes. and the maximum number that can
bestacked
The system of units for project documents c) Calculations showing that the
shallbecustomaryUSunits. stacking procedure will not over
stress the pipe or coatings,
In addition, a summary of CONTRACTOR according to the applicable method
DeliverableDocumentsislistedinAppendix of API RP5L1 or API RP5LW, using
A. mechanical properties given in the
applicable COMPANY specifications
4.4 RESPONSIBILITY FOR DAMAGED OR listedinSection3.2andinthesame
MISSINGMATERIAL CONTRACT.
PipelineBundlematerialsandotherrelated d) Procedures for inspection,
SpecificationforHandling,TransportingandStoringofLinePipeandRelatedEquip 4of10
identifying, documenting, recordedinenoughdetailthattheycanbe
segregating or disposing of any accessed and understood by a qualified,
damagedmaterial independent third party. In absence of
e) Locations and toscale layout otherinstructions,CONTRACTORshallkeep
drawings of the temporary and these records available to COMPANY for
permanent storage areas, showing inspection or photocopying for five years.
meansofaccess Therecordsshallinclude:
f) Means of communication with
storagesites a) ResultsofCONTRACTOR'Sinspection
g) Planneddurationofstorageandthe of materials at the time
means of preventing/minimizing CONTRACTOR receives custody of
deterioration during storage and thematerials
transitofallmaterials b) The name and qualifications or
h) Inventory Control and Inventory authorityoftheinspector
trackingProcedures c) Pertinent information about non
conformingmaterials,including:
4.5.2 AccidentReports Material condition that caused
CONTRACTOR shall inform the COMPANY rejection
within24hoursofanyaccidentorincident Methodofdetection
thatoccursinperformanceoftheworkand Number of items involved, if
results in injury or damage to the pipe or morethanone
otherproperty. Proposedandactualdisposition
Preventiveactiontaken
4.5.3 DispositionofNonConformingMaterials d) Inventory control records including
CONTRACTOR must submit a summary receiving and shipping reports,
report of all damaged materials and its NCRs,dispositionofmaterials
disposition, whether the damage was
caused by the CONTRACTOR or existed 4.8 INTERACTIONS BETWEEN CONTRACTOR
whenCONTRACTORtookcustody.Approval ANDCOMPANY
of such disposition must be in writing by a CONTRACTOR shall allow COMPANY access
COMPANY Representative whose authority to his facilities, work areas, storage areas
has been established with the and processes during any portion of the
CONTRACTOR by the terms of the work for monitoring, surveillance and
CONTRACT. inspection,including,butnotlimitedto:
a) Reviewofadequacyoffacilitiesand
4.6 DEVIATIONSANDDISCLAIMERS equipment
Workdoneunderthisspecificationshallbe b) Reviewofpersonnelqualifications
according to all requirements herein, c) Monitoring materials conveyance
withoutdeviationsanddisclaimers. activities
d) Performing or witnessing
4.7 RECORDS inspections
CONTRACTORshallkeepuptodaterecords
adequate to confirm that the work, The COMPANY Representative shall have
including inspections, inventory control, the right to stop materials handling or
reports and reviews, has been carried out storage operations which, in his judgment,
according to this specification. These areimproper,andtosuspendtheworkuntil
records shall be indexed and legibly theproblemisresolvedorcorrected.
SpecificationforHandling,TransportingandStoringofLinePipeandRelatedEquip 5of10

TheCOMPANYRepresentativeshallinspect Allmaterialshallbetalliedreceiptandload
allmaterialsforanyvisualdamagepriorto out.
loadingorunloading.Anyvisualdamageor
indication that the material has been 5.2 MARINETRANSPORTATION
damaged due to intransit shipping of the
load shall be noted and brought to the Marine transportation and loading shall be
attention of the CONTRACTOR prior to the performed according to API RP 5LW. In
commencement of the handling or addition sea fastening, loading height,
transportationoperations. loading scheme shall be approved by the
COMPANY. All sea fastening shall be
Thematerialshallnotbeloaded,unloaded, designedtopreventdamagetothematerial
transportedorhandledwithouttheexpress fromthedynamicmotionsofthevesseland
knowledge,concurrenceandobservationof shall be reviewed by the COMPANYs
theCOMPANYRepresentative. marinesurveyorforacceptance.

The COMPANY reserves the right to All ship and barge accessories shall be
determine the disposition of any and all properly padded in such a manner to
damagedmaterial. prevent damage to the material coatings.
All pipes shall be shipped nested with
4.9 ONSITEDOCUMENTS proper approved padding in sufficient
CONTRACTOR shall have this specification, quantities to prevent damage to the pipe
referenced specifications, standards and andcoatingsbetweenlayersofpipe.
other work related documents onsite for
CONTRACTORandCOMPANYreference. Hardwood bearers with an overall bearing
surface area of at least 2500 mm2 shall be
5. GENERALSPECIFICATIONS placed underneath the bottom (first) layer
5.1 GENERAL ofpipes.
Transportation, handling and storage of
materials shall be carried out according to 5.3 TRANSPORTATIONBYROAD
CONTRACTOR'S Work Plan described in 5.3.1 General
Paragraph4.4.1.Specificrequirementsare Loadingandtransportationbyroadshallbe
described in the following sections and carriedoutaccordingtoAPIRP5L1andAAR
shouldbeincludedinCONTRACTORsWork General Rules, Sections One and Two,
Plan. where these provisions can reasonably be
applied.
Only equipment acceptable to the
COMPANY shall be used in handling the 5.3.2 StackingonMotorCarriers
material. Pipestransportedonmotorcarriersshallbe
stacked in unitized, nested pyramids with
All material shall be handled, transported approvedpaddingplacedbetweenlayersto
and stored such that it is not damaged or prevent damage to the coating. Padded
subjecttodeterioration. chainsornylonstrapsshallbeused.

Other Companys material shall not be 5.4 TRANSPORTING PIPE WITH
stored on or in the same area as the CORROSION/ABRASION RESISTANT
COMPANYsmaterial. COATING
SpecificationforHandling,TransportingandStoringofLinePipeandRelatedEquip 6of10
Line pipe coated with corrosion/abrasion adequate protection is given to the
resistant coating shall be stacked on the pipeends.
carrier or storage place so there is no e) CONTRACTOR shall take all
contact between pipe joints. If separator necessary precautions to ensure
rings are on the pipe when CONTRACTOR that line pipe joints do not come
takes custody of the pipe, it is into contact while being moved.
CONTRACTOR'S responsibility to decide Contact could result in denting or
whether they are adequate to prevent outofroundness of the line pipe
contact or damage. If not, CONTRACTOR bodyorpipeends.
shallproposeothermeanstoseparatepipe f) CONTRACTOR shall unload all line
joints and submit the proposal for pipe at a controlled rate according
COMPANY approval. Under no to the agreed rate in the
circumstance shall abrasive coatings be CONTRACTORworkplan.
allowed to come into contact with bare or g) Chains, cables, stanchions or other
other coated materials during handling or means of fastening or tying down
storage. Wooden stripping shall not be thelinepipefortransportationshall
used and the pipe must be shipped with beproperlypadded.Dunnage,skids
approved padding between layers and the or padding shall be used to protect
pipenested. the bottom layer of line pipe and
shallbeofsufficientquantitytonot
5.5 HANDLINGANDSTORAGEOFPIPE allow damage to the pipe or
a) Lifting slings used in direct contact coatings.
with line pipe shall be wide non h) CONTRACTOR shall follow
abrasive belts or padded cable instructions and precautions given
loops.Forkliftsutilizedtomovethe bytheCOMPANYRepresentative.
pipe shall be properly padded. The i) Use of pipe wrenches, pry bars or
pipes shall be raised or lowered turning forks against any surface of
from the barge, truck trailer or thematerialisstrictlyprohibited.
storagerackusingaspreaderbarof j) All pipe shall be stored as directed
theappropriatelength. by COMPANY, on concrete of
b) Whenhooksareusedforliftingline wooden sillswith2x4hardwood
pipe, the end hooks shall be runners supporting the material in
designed to prevent end damage at least three support points.
andshouldbelinedwithsoftmetal, Storage racks shall meet all
rubber or plastic. Under no applicable API specifications, shall
circumstances shall brass hooks be have a load capacity of 400 tons,
used. The end hooks shall have a andassurethatallmaterialisstored
length of bearing area which aminimumof18fromtheground.
exceeds onto third the The storage sills are to be flat and
circumferenceofthepipe. parallel, resting on firm supports
c) CONTRACTOR shall handle line pipe which will not settle or tilt and are
in a manner which shall prevent spaced in such a manner as to
impact loads that can cause local prevent contact with the
dentingordamagetothecoating. connections.
d) CONTRACTOR shall ensure that all k) Racks,roadsandstorageareasshall
line pipe joints being lifted have have sufficient drainage to prevent
bevelendprotectorsfitted,andthat flooding. Roads and other access
SpecificationforHandling,TransportingandStoringofLinePipeandRelatedEquip 7of10
areas shall be kept well maintained knowledge, concurrence and
atalltimes. observation of COMPANYs
l) Pipe shall be stacked in a pyramid Representative.
fashion. Pipe shall never be placed f) Rough handling or dropping of the
on the ground or on racks that do material requires reinspection of
not have the proper 2 x 4 the material with the responsible
hardwoodrunners. party held liable for all costs
m) Plastic or wooden chocks shall be including, but not limited to,
utilized on both storage racks to handling,transportation,inspection,
prevent movement of the material. costofmaterial,etc.
The area underneath and around g) Any material damaged during
the material is to be kept free of handling shall be set aside for
grass,weedsandstandingwater. investigative examination.
Examinations shall be performed in
5.6 HANDLING AND STORAGE OF OTHER accordance with procedures
MATERIALS approvedbytheCOMPANY.
a) The rigid foam insulation sections h) Personnel moving or handling the
are easily crushed and therefore, materialshallbequalifiedintheuse
theyshallbehandledcarefully.The oftheequipmentoperatedandshall
storageoftheinsulationshallbeina be thoroughly familiar with
cabin that is temperature and appropriate API and COMPANY
humidity controlled. Moisture shall specifications
not be allowed to condense on the
insulationsurface. 5.7 SAFETYANDYARDSECURITY
b) Care shall be taken in handling the CONTRACTORshallhandlematerialssafely,
spacer half with the wheels. The according to all applicable legal
wheels shall be checked for ease of requirements,recognizedstandardsofgood
rotation.Nuts,boltsandwashersof practice and CONTRACTOR written safety
each spacer shall be proper stored policiesandprocedures.CONTRACTORsite
assets. personnel shall review and understand the
c) Stainless steel tubing will be CONTRACTOR written safety procedures
supplied on reels. Handling and andpolicies.Thesepoliciesandprocedures
storage of the reels shall be such shall also be available for review by
that no contamination of the COMPANY.
stainless steel occurs. Other
materialsshallnotbeallowedtobe Access to the storage yard shall be
contactwiththetubing. controlled 24 hours per day, 365 days per
d) Specificstorageracksandareasshall year.Thestorageareashallbecompletely
be allocated to COMPANY and shall fenced or secured in such a manner as to
be designated for the storage of prevent unauthorized access or property
COMPANYmaterial. removal.
e) Material shall be racked by size,
weight, grade and purchase order Sufficient inventory control records and
number. Different sizes, grades of procedures shall be maintained by the
material numbers shall be racked CONTRACTOR to ensure physical control of
separately. Material shall not be thematerial.
moved at any time without the
SpecificationforHandling,TransportingandStoringofLinePipeandRelatedEquip 8of10
5.8 PIPESTORAGE ofdamagedmaterialshallberecordedwith
a) The CONTRACTOR methods of line a description of the extent and nature of
pipe storage shall ensure that no thedamage.Thedamageassessmentshall
damageoccurstothelinepipejoints bebasedonwhetherthematerialcomplies
or any coating materials at any with applicable COMPANY specifications
stage. listedinsection3.2.c.
b) Coated line pipe shall be stacked
usingonlysuitablemeanstoprevent 6.2 SEGREGATING DAMAGED OR NON
pipes contacting each other. CONFORMINGMATERIAL
Dunnage or supports shall be made CONTRACTOR shall be responsible for
of soft material such as wood, separating damaged material from
rubber or plastic and shall have acceptable material. CONTRACTOR shall
enough bearing area to prevent also be responsible for discriminating
damagetothecoatings. between material damaged before and
c) Line pipe shall be stored so that afterCONTRACTORtakescustody.
watercannotcollectinsidethebore.
d) Linepipeshallbestoredatleastsix
(18")inchesabovegroundleveland 6.3 DAMAGESURVEY
shallbeprotectedfromcontactwith CONTRACTORshallperformafinaldamage
oil. survey in the presence of COMPANY, the
e) Threetierracksshallbeutilized. CONTRACTOR and any subcontractors or
insurance company that may be involved.
5.9 TRACEABILITY CONTRACTOR shall report the results as
Traceability of each item received to the required in Section 4.4.3. The report shall
mill certification papers, logs, or shipping besignedbytheCOMPANYRepresentative.
papersshallbeverifiedpriortoacceptance
bytheCONTRACTOR.

Pipe or other materials not specifically
traceable to thosemillcertificationpapers,
logs or shipping papers shall not be
acceptedbytheCONTRACTOR.

Documentation and traceability of the
materialshallbemaintainedatalltimes.

Theoriginaljointnumbersforpipeshallbe
utilized for traceability purposes. The
materialsshallnotberenumbered.

6. PIPEINSPECTIONS
6.1 INSPECTIONATTHERECEIVINGPOINT
CONTRACTOR shall visually inspect the
materials before it is loaded or offloaded
where custody of the materials is taken or
given. Each item shall be marked as
"acceptable"or"damaged".Serialnumbers
SpecificationforHandling,TransportingandStoringofLinePipeandRelatedEquip 9of10
APPENDIXA
SUMMARYOFCONTRACTORDELIVERABLEDOCUMENTS

DocumentstobedeliveredbyCONTRACTORinaccordancewiththisspecificationarelistedbelowforeaseof
referenceonly.

ITEM SECTION DESCRIPTION REQUIREDBY

1. 4.5.1 CONTRACTORworkplan 45daysbeforeworkstart

2. 4.5.2 Accidentreport Within24hoursafteroccurrence

3. 4.7 Records WhenrequestedbyCOMPANY

4. 4.5.1 Stackingprocedurecalculation 45daysbeforeworkstart

5. 6. Inspectionreport WhenrequestedbyCOMPANY

6. 5.7 CONTRACTORsafetyprocedure 45daysbeforeworkstart

7. 6. CONTRACTORsupervisor/inspector 45daysbeforestartname
andresume