Professional Documents
Culture Documents
April 2015
KRC Consortium
Korea Rural Community Corporation (KRC), Korea
Korea Engineering Consultant Corp.(KECC), Korea
PT. Indra Karya (Persero), Indonesia
PT. Wiratman, Indonesia
PT. Mettana, Indonesia
- CONTENT -
<Design Certification of Karian Dam, 2007>
<Technical Issues for the Design Certification>
<Review Design>
1. Outline of the Project
2. Hydrology & hydraulics
3. Geology & Geo-technology
4. Construction Materials
5. Design of Dam
6. Stability Analysis
7. Measurement Plans
8. River Diversion
9. Spillway
10. Intake & Outlet Facilities
11. Protection of Excavated Slope
12. Conclusion 2
<Design Certification of Karian Dam>
3
<Technical Issues for the Design Certification>
Review Design/
No Comments from Balai Bendungan
Answers
Additional geological and geotechnical investigations in 6 additional borings
tunnel site, and to check the existence of fault zone,
1
potential leakage and sliding in inundation area.:
The condition of groundwater level around the tunnel for the Reviewed tunnel
dewatering. In addition, classification using Bieniawskis excavation, dewatering
2
method along the tunnel and supporting
A geological expert has to observe the excavation result and Just recommended
3 do mapping on the form of surface geology map
To avoid the water conflict in the future, the distribution of Just recommended
10
the water has to be dealt with together
The Dam Safety Commission Team and Balai Bendungan Just recommended
11 Study Teams site inspection at every important stages
during the construction of dam.
<Other technical Issues>
12 Updating hydrological analysis for Coffer Dam Hydraulic analysis for
Coffer Dam
13 Review mutual behavior interference due to the adjacent Reviewed tunneling
blasting for tunnel excavation method and stability
5
1. Outline of the Project
Project Objectives
DMI water supply to Tangerang, Banten. (9.1 m3/sec)
Flood control (60.8 million m3) and Small hydro-power generation
Supplementary DMI water supply to Serang, Cilegon cities & supplementary irrigation
water supply to the existing areas of Ciujung irrigation scheme. (5.5 m3/sec)
Project Location
Karian Dam : Ciberang river (a tributary of Ciujung river)
About 3 hours by car from Serang city, Banten.
Administration
Karian dam scheme: in the southeast of Kabupaten Lebak.
Karian dam site: Pasir Tanjung village, Rangkasbitung Sub District.
The dam and its reservoir site copes about 11 villages from 4 sub-districts such as
Rangkasbitung, Maja, Cimarga, and Sajira.
6
7
<Main Features and Details of Project>
8
(1) River Diversion Works
Design Flood (Peak) : 775 m3/s (25-year flood)
Primary & Downstream Coffer Dam
Type : Random Earth Fill Dam
Dam Crest Elevation : EL 31.00 m (Primary), EL 24.50m (D/S)
Crest Width : 8.0 m
Slope
Primary : 1:1.8 (Up & Downstream)
D/S : 1:3.0 (Up & Downstream)
Upstream Coffer Dam
Type : Central Cored Rockfill Dam
Dam Crest Elevation : EL 39.00 m
Crest Width : 10.0 m
Dam Crest Length : 137.0 m
Slope : 1:3.0 (Upstream), 1:2.5 (Downstream)
Diversion Tunnel
Location : On the right side of the dam
Length : Diversion tunnel No. 1: 512.6 m, No. 2: 506.35 m
Inside diameter : 4.5 m
Type : Horseshoe-shaped tunnel
Closing gate : Steel sliding gate
Bottom elevation : EL. 20.0 m (inlet portal), EL. 19.0 m (outlet portal)
Tunneling Method : A.S.S.M
Plug Concrete Length : 20.0 m
9
(1) Main & Saddle Dams
Main Dam
Type : Central Cored Rockfill Dam
Length : 516 m
Dam Crest Elevation : EL 72.5 m
Crest Width : 10.0 m
Slope : 1:3.0 (Upstream), 1:2.5 (Downstream)
Slope Protection : Random-Dumped Riprap (t=1.5 m, Upstream)
Hand-Placed Riprap (t=1.0 m, Downstream)
Saddle Dam 1, 2 & 3
Type : Central Cored Rockfill Dam
Length : 113 m (No 1), 447m (No 2), 342 m (No. 3)
Dam Crest Elevation : EL 72.5 m
Crest Width : 6.0 m
Slope : 1:3.0 (Upstream), 1:2.5 (Downstream)
Slope Protection : Random-Dumped Riprap (t=1.5 m, Upstream)
Hand-Placed Riprap (t=1.0 m, Downstream)
10
(1) Spillway
Hydraulic Features
Design Flood (Inflow) : 3,671 m3/s (PMF)
Design Discharge
Control Structure : 3,190 m3/s (PMF)
Chuteway : 3,190 m3/s (PMF)
Plunge Pool : 266 m3/s(100-year Frequency)
Structural Features
Approach Channel : Max. 92.7m long (Ogee Spillway)
: Max. 13.5m long (Side Channel Spillway)
Side Channel Type
Weir Length : 50 m
Weir Crest : EL. 67.50 m (N.H.W.L)
Gated Ogee Type
Weir Length : 25.0 m
Weir Crest : EL. 57.50 m
Regulating Gate : Radial Gate, 12.5m(W)13.4(H)2 gates
Chuteway
Slope : 1 / 4.0
Length : 117.4 m
Width : 49.0 m
Plunge Pool
Length : 88.0 m
Bottom Width : 49.0 m
11
Radial Gate (out of this package: Hydro-Mechanical works)
Number of gate : 2 Sets
Crest elevation : EL 67.5
Sill elevation : EL 67.2 (about)
Clear span : 12.5 m
Clear height : 13.4 m
Gate height : 13.7 m (13.4 + 0.3)
Type of hoist : 1-motor, 2-drums wire rope winding type (including:
gate position indicator, limit s/w, brake, cover, etc.)
Lifting height : 10 m
Lifting speed : 0.3 m/min 10%
Lofting capacity : 180 Ton
Capacity of motor : 22 x 6 P x 3 phase, 380V 50Hz
Hoist deck elevation : EL 72.5
Stop log (out of this package: Hydro-Mechanical works)
Type of stop log : Steel girder type
Clear span : 12.5 m
Clear height : 10.0 m (1.25 m x 8 blocks)
Lifting beam : 1 set of hook type lifting beam
Lifting device : Truck crane
Downstream Transition Channel
Design Discharge : 128 m3/s (10-year Frequency)
Channel Length : Approx. 111.0 m
12
<Summary of Dam Scale>
Normal High Water EL. 67.5 m Water supply capacity of 14.6 90 % of reliability
Level m3/sec
Flood Water Level EL. 70.85 m 1/2 PMF Flood Control Storage:
60.8mil.m3
Maximum Water Level EL. 71.22 m PMF
Dam Crest Level EL. 72.5 m Freeboard 1.28 m If gated spillway, freeboard
should be more than 1.25m
above from M.W.L (Maximum
Water Level).
13
. MAIN DAM
+
L.W.L : EL of 46.0m: Intake Tunnel EL of 45.0m
- Core zone Crest width = 5 m U/S & D/S slope = 1 : 0.2 EL= 72.0 m
15
<Summary of Dam Design>
PMF outflow
- Control structure EL. 57.5 m Capable of discharging 2,410 m3/s at
EL = 71.22m.
5. Energy dissipater
16
<Summary of Dam Design>
Culvert Master
- Diversion tunnel Diameter 4.5 m x a 25-year flood selected as the design program by Haestad
Methods and the
size 2 lanes flood (Q=775/sec).
calculation by using
the HEC-5.
17
2. Hydrology & hydraulics
Low Flow Analysis
Flow discharge
Catchment
Station Period of Remarks
area ()
95% (/sec)
35 years
DD 2006 Rangkasbitung 288 4.00 O
(1970~2004)
Review Design 40 years
Rangkasbitung 288 3.36
2014 (1970~2009)
19
Available rainfall data
Study Rainfall station PMP
DD 2006 1982 ~ 2003 680 mm (Isohyet map 2003)
(22 years)
Review Design 1982 ~ 2013 800 mm (Isohyet map 2013)
2014 (32 years) 633 mm (Gumbel EV-1)
Review Design
506 664 790 937 1,418 1,731 4,295
2014
4,500
PMF=4295 m3/sec
PMF=3671
1,500
DGWR PMF
Review PMF
0
1 4 7 11 14 17 21 24 27 31 34 37
Time (hour)
21
PMF Values of the Karian Dam Compared with Saguling Dam, Cirata,
Jatiluhur and other Dams in Indonesia (Review of 2014)
22
. MAIN DAM
<Operation Rule>
Flood
10-yr 25-yr 100-yr 1/2PMF PMF
frequency
Peak inflow
615 775 1,010 1,850 3,671
(m3/s)
Peak outflow
128 173 266 658 3,190
(m3/s)
23
<Reservoir Flood Routing - PMF>
<PMF 2006> <PMF 2014>
Figure 6.12d. The Graph of Flood Routing of Spillway with Q- PMF.
4800
4400
Qi peak = 4.295,40 m3/s
4000
Qmax=3671m3/s 3600
Discharge (m3/s)
2800
2400
in-flow
out-flow
2000
1600
EL=71.22 m
1200
800
400
0
0 6 12 18 24 30 36 42 48
Time (hour)
PMF
Section
DD 2006 Design Review 2014
Calculation results of reservoir peak inflow (/sec) 3,671 m3/s 4,295 m3/s
flood routing peak outflow (/sec) 3,190 m3/s 3,170 m3/s
Peak inflow
490 615 775 890 1,010 1,421 1,850 3,671
(m3/s)
Peak outflow
94 128 173 218 266 434 658 3,190
(m3/s)
Maximum water
level 68.42 68.65 68.95 69.16 69.37 70.08 70.85 71.22
(EL. m)
Storage Cofferda
m
D Diversion Tunnel Q out
Diameter Tunnel
28
<Geological Profile of Dam Axis>
29
KB-30 (55~60m) KB-30 (60~65m)
Boring 2005
30
BH-01 Depth 00.00 05.00 meter
Additional
Inclined
Boring- at
BH-01 Depth 05.00 10.00 meter
Dam site
Year 2013
WATER LEVEL
CORE QUALITY
ROCK CLASS
SAMPLING
COULUM DESIGNATION
GROUND
SOIL/ SOIL/ RECOVERY
DATE
DEPTH (RQD)
(m)
(m)
ROCK ROCK Description Cm %
UNIT TYPE SECTION (%) (%)
0 50 100 0 50 100
00.00 Top Soil Clay v v 0,00 - 0,60 M
Top Soil, clay, brown, soft, non plastisity, contain of root. 150
01.00
0,60 - 4,10 m
Boring Log of Clay, brown, soft, medium plastisity.
Clay
150
Inclined 03.00
150
Boring, 2013 04.00
Gravelly sand
06.00
December,
03, 2013
100
07.00
90
08.00
90
09.00
December, 04, 2013
90
9,30 - 11,35 m
10.00
Sand, blackish grey, sand loose, fine to medium sand, wet.
Sand
100
0%
10,00 m
11.00
100
12.00
Tuffaceous 11,35 - 12,20 m
sand
v v v Tuffaceous sand, yellowish white, medium loose, medium to coarse sand.
100
12,20 - 14,50 m
Tuffaceous
13.00
v Tuffaceous clay, yellowish grey, soft, medium plastisity.
clay
100
v v
14.00
December, 05, 2013
Tuffaceous Sandstone
100
14,50 - 20,80 m
15.00
v Tuffaceous sandy clay, brownish grey, soft, mediun to coarse sand, sub-
100
v v angular to rounded. CL
Tuffaceous sandy clay
16.00
100
17.00
v
100
v v
18.00
December,
06, 2013
100
19.00
v
v v
20.00
100
32
<Geological Profile of Other 5 Boring Holes, 2013>
33
Confirmation of Fault
Zone at Dam Site,
2013
Inclined
Boring
34
<Confirmation of Fault Zone at Dam Site>
Review of JICA survey report, found fault zone from aerial photographs, but this site has too dense
existing report forest even hard to walk.
If the fault zone could be found, they should have found the evidence from the field
geological survey but they did not mention about it.
Even in the elastic wave exploration, there was no mention fault zone.
Also in explaining map there was no sign of clear fault, in the same way in the boring survey.
Field geological In sedimentation stage of the river, the soft part of the upper was cut little by little by
survey streams of river, and
sediments of river such as sand and gravel are deposited in 5-10m thickness.
35
4. Construction Materials
Location of Previous Borrow & Quarry
Volume of Materials Site
Target
(103 m3)
Available
Materials Upstream
Main Saddle (103 m3)
Coffer Sum
dam Dams
Dam
38
Cross section of Quarry area Geblegan hill
39
Core Box of
QBH-1,
Geblegan Mt,
New Quarry
40
Drilling Log of QBH-1, Geblegan Mt, New Quarry
41
New Borrow Area
42
<Access Road for New Quarry>
<Necessity of New Access Road>
To shorten the distance
If through existing provincial road the length of the access road will be about 35.4
kilometer meanwhile if using the new access road passing through the existing village
road it will be about 19.2 kilometer.
To avoid damage to the existing provincial road
The volume of embankment material is estimated to be 1.2 million cubic meter. They will
be transported by trucks weighing > 10 tons, while the existing provincial road has
been designed and constructed to resist the truck traffic weighing < 10 tons. Thus it is
very apparent to damage the road upon using the existing provincial road as an access
road without upgrading.
To keep off traffic jam in provincial road
The width of the existing provincial road is only 6.00 meters, and is an important
network of transportation linking Lebak county to Bogor county. Traffic jam will take
place whenever the carrier trucks with upload of embankment material are passing
there slowly. 43
<Specification of construction materials>
Material Specification
Core material permeability: under 110-5 cm/sec
15-20% of less 0.05mm particles to be included.
Plasticity index: 15-30% and low plasticity.
USCS (Unified Standard Classification System): GC, SC, CL,
SM and CH.
maximum dry density: more than 95%.
Fine filter material coefficient of permeability: 10 to 100 times higher than core
materials.
not have viscosity
soil particle with below 0.074mm diameter: less 5%
Coarse filter the particle size of the materials: smaller than that of rock zone
material materials.
less than 5% of less 0.074 mm
maximum size of particle: less than 75 mm 44
<Specification of construction materials>
Material Specification
Rock material Fresh and hard rock
maximum diameter of particles: 45 to 60 cm
the particles with diameter of less than 10 cm: less than 5%.
Specific gravity: more than 2.5
compression strength: more than 700kgf/cm2
Durability: less than 15%.
+
L.W.L : EL of 46.0m: Intake Tunnel EL of 45.0m
48
. MAIN DAM
Excavation
51
. MAIN DAM
<Grouting Plan>
Item Description
Foundation - Permeability : Around 110-4cm/s (sepuluh pangkat minus empat)
Condition - Rock Class : CL, D
Curtain - 2 rows (hole spacing: 1.5m, row spacing: 2.0m)
Grouting - Depth (45m to 27m)
52
. MAIN DAM
3,000
Consolidation Grouting Hole
Downstrea
Depth 35m Depth 35m
Curtain Grouting Hole
2,000
Grouting
m
Depth 45m
Dam Axis
for
2,000
Upstream
spillway
2,000
1,500 1,500 1,500 1,500 1,500
Curtain Grouting
3,000 3,000
3,000
Grouting Type Drilling Curtain Grouting
Curtain Grouting 27,932
Blanket Grouting
Blanket Grouting 748
Consolidation Grouting 6,880 Consolidation Grouting
Rim Grouting 620
Total 36,180m
53
. MAIN DAM
6. Stability Analysis
Scoring of Karian Dam: Capacity (6) + Height (6) + Population (12) + Damage (12) = 36
54
. MAIN DAM
Seismic or
0-6 I (Low) IV 100-200
Seismic coeff.
10,000
dynamic coeff.
N=50-100 Ad 0.1g (MDE)
58
. MAIN DAM
<Seismic Coefficient>
59
. MAIN DAM
60
. MAIN DAM
61
. MAIN DAM
1.667
100
95
90
85
100 80
95 75
90
70
85
80 65
75 60
70 55
65 50
60 45
Elevation (EL-m)
55 40
50 35
45
Elevation (EL-m)
30
40
35 25
30 20
25 15
20 10
15 5
10 0
5 -5
0 -10
-5
-10
-15
-15 -20
-20 -25
-25 -30
-30 -35
-35 -40
-40 -45
-45 -50
-50
-55
-55
-60
-60
0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300 320 340 360 380 400 420 440 0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300 320 340 360 380 400 420 440
Figures of Analysis result for all cases are attached in the Review Design Report
62
. MAIN DAM
1.667
1.177
100
95
100 90
95 85
90 80
85 75
80 70
75 65
70 60
65
55
60
50
55
45
Elevation (EL-m)
50
45 40
Elevation (EL-m)
40 35
35 30
30 25
25 20
20 15
15 10
10 5
5 0
0 -5
-5 -10
-10 -15
-15 -20
-20
-25
-25
-30
-30
-35 -35
-40 -40
-45 -45
-50 -50
-55 -55
-60 -60
0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300 320 340 360 380 400 420 4400 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300 320 340 360 380 400 420 440
Result of slope stability analysis with OBE, MDE and MEC conditions by y/h values
Hydraulic Return Period
y/h 100-year 5000 years 10,000 years Remarks
Conditions U/S D/S U/S D/S U/S D/S
0.25 1.340 1.667 0.503 0.851 0.389 0.735
After Construction 0.25 2.310 2.018 1.522 1.337 1.222 1.376 1/2 of seismic
64
. MAIN DAM
Based on the above formula, seepage is 4.3610-5m3/sec and is considerably smaller than 20.2
m3/sec, annual inflow. This value is far less than 1 percent of allowable limit seepage
65
. MAIN DAM
Permeability coefficient (K) of new borrow area for the core zone shall be 3.1110-9m/sec and porosity of 50%, the maximum
flow velocity inside the core shall be estimated as below
K io 3.80 10 7 2.0
Vmax 1.52 10 6 cm/sec
n 0.5
herein, i0: maximum hydraulic gradient
In addition , the maximum flow velocity inside (9.68 x 10-6 m/s) the core was found to be much slower than critical flow
velocity to cause piping phenomenon and no piping phenomenon is thought to occur inside the core.
66
. MAIN DAM
ic -of core zone is 0.945 and safety factor of 4.73 higher than required safety factor for critical
hydraulic gradient of 4.
67
. MAIN DAM
40
35
30
25
20
15
10
5
0
-5
-10
-15
-20
-25
-30
-35
-40
-45
-50
-55
-60
0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300 320 340 360 380 400 420 440
Distance (m)
68
. MAIN DAM
Pore-Water Preassure
4.2692e-007 m/sec
100
95
90
85
80
75
70
65
60 1.2
55
0.8
50
45
Elevation (EL-m)
40
35
2
30
25
20
0.20.2
1.6
0.6
0.4 0.2
15 0.2
0.6
0.2
0.4
10 1.2
0.4
0.8
5
0.2
0
-5
-10
-15
-20
-25
0.2
-30
-35
0.2
-40
-45
-50
-55
-60
0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300 320 340 360 380 400 420 440
Distance (m)
4.2692e-007 m/sec
100
95
90
85
80
75
70
65
60
55 30
50
45
Elevation (EL-m)
40
35
30
25
20
15
45
20
50
10
35
5
25
0
-5
55
40
-10
65
-15
-20
60
-25
-30
-35
-40
-45
-50
-55
-60
0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300 320 340 360 380 400 420 440
Distance (m)
70
. MAIN DAM
7. Measurement Plans
Kinds & Quantity of Measuring Instrument
Classification Instrument Qty
Settlement Multi-Layer Settlement 1
Inclinometer & Horizontal
Horizontal Displacement 1
Strainmeter
Pore Pressure Piezometer 24
Earth Pressure Earth Pressure meter 11
Seismic Seismic Accesero graph 3
Leakage Leakage pit 1
71
. MAIN DAM
7. Measurement Plans
Kinds & Quantity of Measuring Instrument
72
<Technical Specification>
No Instrument Name Specification of Instruments
1 Piezometer Material : Stainless steel
Excitation : Pluck or swept frequency
Over voltage protection : 90V gas plasma arrester
Thermistor : 3k Ohms @ 25C
Range : 2200-3500Hz
Nominal zero value : 3130Hz
Thermal effect : 0.05% F.S/C
Pressure range option (kPa) : 345 ~ 6895
Over range : 2x rated pressure
Resolution : 0.025% FS
Accuracy : 0.1% FS
Non-linearity : < 0.5% FS
Temp range : -20 to +80C
Thermal effect : < 0.05% FS
Diameter x length : 20 x 140 mm
2 Earth pressure cell Pressure range option (kPa) : 344 ~ 1034
Over range : 150 % FS
Signal output : 2000 3500 Hz
Resolution : 0.025% FS
Accuracy : 0.1% FS
Linearity : < 0.5% FS
Outer diameter : 165, 245, 320mm
Active diameter : 150, 230, 305mm
Thickness : 7mm
Operating temp : -20 to +80C 73
<Technical Specification>
74
<Technical Specification>
No Instrument Name Specification of Instruments
5 Displacement monitor Wheelbase : 0.5m
set Probe diameter : 25.4mm
Probe length (include connector) : 710mm
Standard range : 30C from vertical
Data resolution : 0.005mm per 500mm
Repeatability : 0.002
System accuracy : 2mm per 25m
Temperature rating : -40C to 70C
Compatible casing sizes : 40-85mm
PDA operating system : WindowsMobile
Software : Field book 5
Memory : 128 MB
Data storage : 256/12mb
Battery life : 20 hours
Temperature range : -30C to 50C
Enclosure : IP67
6 Leakage pit Design standard : BS 3684 Pt 4
Material : stainless steel
Geometry option : 90, 45, 22.5 degree
Flow : 10 to 60 litres/second
Standard ranges option : 150, 300,500, 1500mm
Resolution : 0.025% FS
Accuracy : 0.1% FS
Operating temperature range : -20C to +80C
75
. MAIN DAM
8. River Diversion
<Coffer Dam Scale>
Temporary Upstream Downstream
Coffer dam Coffer dam Coffer dam
D.C.L: EL39.0m
F.W.L: EL37.8m
D.C.L: EL31.0m
F.W.L: EL30.4m
D.C.L: EL24.5m
F.W.L: EL23.1m
1,50
Total 141,184m3
0
1:2.
5
ROCK
.3
1:0
1:0.2
0
1:3. K
1:0.2
ROC
1:0
.3
4 Origial ground line
3 3
2 1 2
Tunnel Scale
- Diameter: 4.5m 2 Lanes
Dimension
- Elevation: Inlet EL.20.0m, Outlet EL.19.0m
- No.1: 512.6m
Length
- No.2: 506.3m
77
<Layout & Profile of Diversion Tunnel >
Tunnel No. 1
Tunnel No. 2
78
<Typical Section of Tunnel>
79
. MAIN DAM
80
<Tunneling Method and Stability>
<Dewatering & Waterproof method>
Assumed Groundwater Level
Waterproof Method
UAM
Item Pre-grouting
(Umbrella Arch Method)
Conceptual
Diagram
Dewatering
construct the diversion tunnel
Making a waterproof zone by putting the Making a waterproof zone and a
during the dry season. grouting liquid in with pressure around reinforced zone by putting the grouting
Concept the tunnel excavation line liquid through the hollow steel pipe with
Nevertheless, when the If it is necessary, it can be applied to the pressure around the tunnel excavation line
face of the tunnel
groundwater flows into the
diversion tunnel excessively Very good waterproof effect Very good waterproof effect
Feature Good reinforcement effect Very good reinforcement effect
waterproof method should be
Cost-effective Uneconomical
applied if needs waterproof.
81
<Other Technical Issues for Tunneling>
Unconfined Compressive
Review mutual behavior interference due to Strength along the diversion Tunnel
the adjacent blasting for tunnel excavation Unconfined Compressive
Hole. No Depth
Strength (kg/cm)
Excavation Workability according to Geotechnical KB-29 30.0 ~ 30.6 2.97
Condition (Atkinson, 1970)
Unconfined KB-30 62.6 ~ 63.0 3.32
Seismic
Excavation Compressive Spacing of Joint KB-31 54.5 ~ 54.9 0.95
Velocity
Workability Strength (cm)
Vp (km/s)
(kg/cm) 13.8 ~ 14.0 10.51
KB-32
Easy to rip 0.45~1.2 17~30 <5 14.2 ~ 14.3 1.79
Medium to
1.2~1.5 30~100 5~30
rip In this site, the excavation with machines is
Hard to rip 1.5~1.85 100~200 30~100 more appropriate than that with blasting and
82
<Analysis of application of one large
diversion tunnel>
The tunnel for diversion was planned as two parallel small tunnels.
It was suggested to make one large tunnel for diversion, because construction process
can be simpler and constructability can be better by the larger area.
<Comparison between parallel small tunnels and one large tunnel>
Conceptual
Diagram
9. Spillway
Hydraulic Design of Spillway
85
Scale of Spillway
Side Channel - The scale of the side channel spillway was determined so
Spillway that 10-years frequency flood can be decreased to 5-years
frequency flood in the Rangkasbitung as a main control
point in the downstream according to The Ciujung River
Basin Basic plans
- So the crest length of side channel spillway was designed
50m
Gated Ogee - After completing flood routing of the reservoir on the basis of a
Spillway wide range of the gates sizes and examining construction costs as
well as hydraulic aspects, the scale of the gated ogee spillway is
determined to be
12.5m(B) x 13.4m(H) x 2gates
86
. MAIN DAM
<Flood Control Plans>
Basic Direction
10-year frequency flood shall be decreased to be 5-year frequency
flood in the Rankasbitung as a main control point by the Karian dam
(Ciujung River Basic Plan 1998)
87
. MAIN DAM
Details of Spillway
Control Structure
[ Side Channel Type ]
- Weir Length : 50.0 m (18m wide side channel)
- Weir Crest : EL 67.5m (N.H.W.L)
[Gated Ogee Type]
- Weir Length : 25.0 m (B12.5mH13.4m 2gates)
- Weir Crest : EL 57.5m
Chute
- Chute Slope : 1 : 4.0
- Chute Length : 117.4m
- Chute Width : 49.0m
Plunge Pool
- Length : 88.0m
- Bottom Width : 49.0m
88
. MAIN DAM
89
. MAIN DAM
To Rangkasbitung
Advantage of 3D Numerical Model Test
1. Easy to check serious design and test errors between design calculation and physical
model test and 3 D numerical model test through comparison the results.
2. Easy to make alternative designs by changing numeric model. Crest of the
approach guide wall was changed to 72.5 m, to be same as the dam crest.
90
. MAIN DAM
91
92
. MAIN DAM
Intake Tower Profile
PROFILE
A A
Section A - A
. MAIN DAM
Detailed Section of Outlet Facility
94
11. Protection of Excavated Slope
Item Reinforcement (Soil Nail) Decrease of the Gradient
Conceptual
Diagram
95
12. Conclusion
Field Point Cause Review Design Remarks
Dam body slope New quarry and Applied new earthquake map Safe from OBE condition by
stability borrow area (Earthquake Zone Map 2010) limited equilibrium method
Fault zone Comments from 2 inclined borings and 4 vertical No need to take any special
Stability Balai Bendungan borings and measures concerning a fault
or an active fault
field geological survey and
review previous reports
Excavated Slope Steep slope (1:0.5) Reinforce a slope with soil nail, Can be protected.
at right side of anchor and etc.
plunge pool
Freeboard of main New PMF (4,295 Reservoir flood routing by using F= 1.32 m, safe (criteria:
dam m3/sec) HEC-5 1.25 m)
Hydrology &
Diversion tunnel Design Flood (25- Hydraulic analysis for the height Safe
Hydraulics
capacity years) of the U/S coffer dam by using
HEC-5
Piping Analysis New borrow area Re-analyzed piping safety by Safe from piping by Justin
Seepage Justin Method and critical Method and critical gradient
gradient
In conclusion, the review design can be fully acceptable for the further stage of the
project, the implementation of the Karian Dam construction. 96
Thank you very much !!!
97