Professional Documents
Culture Documents
Project Name
TABLE OF CONTENTS
1.0 General Information..................................................................................................................................................................................................... 3
2.0 Project Tenets and Principles....................................................................................................................................................................................... 4
3.0 Job Scope Overview.................................................................................................................................................................................................... 5
2012 Chevron Pipe Line Company. All Rights Reserved. Page: 1 of 15 Reviewed: November 2012. Uncontrolled when printed.
CONTRACTOR JOB SAFETY PLAN (CJSP)
Job ID:
Job Description:
2012 Chevron Pipe Line Company. All Rights Reserved. Page: 2 of 15 Reviewed: November 2012. Uncontrolled when printed.
CONTRACTOR JOB SAFETY PLAN (CJSP)
Always:
1. Operate within design or environmental limits.
2. Operate in a safe and controlled condition.
3. Ensure safety devices are in place and functioning.
4. Follow safe work practices and procedures.
5. Meet or exceed customers requirements.
6. Maintain integrity of dedicated systems.
7. Comply with all applicable rules and regulations.
8. Address abnormal conditions.
9. Follow written procedures for high risk or unusual situations.
10. Involve the right people in decisions that affect procedures and equipment.
2012 Chevron Pipe Line Company. All Rights Reserved. Page: 3 of 15 Reviewed: November 2012. Uncontrolled when printed.
CONTRACTOR JOB SAFETY PLAN (CJSP)
2012 Chevron Pipe Line Company. All Rights Reserved. Page: 4 of 15 Reviewed: November 2012. Uncontrolled when printed.
CONTRACTOR JOB SAFETY PLAN (CJSP)
2012 Chevron Pipe Line Company. All Rights Reserved. Page: 5 of 15 Reviewed: November 2012. Uncontrolled when printed.
CONTRACTOR JOB SAFETY PLAN (CJSP)
2012 Chevron Pipe Line Company. All Rights Reserved. Page: 6 of 15 Reviewed: November 2012. Uncontrolled when printed.
CONTRACTOR JOB SAFETY PLAN (CJSP)
2012 Chevron Pipe Line Company. All Rights Reserved. Page: 7 of 15 Reviewed: November 2012. Uncontrolled when printed.
CONTRACTOR JOB SAFETY PLAN (CJSP)
Vessels/Tanks Communication (SimOps) Safe Work Electrical Safe Work Isolation of Hazardous Energy
Hoses Communication (Language) Bypassing Critical Protection Excavation Simultaneous Operations
Other: Other: Confined Space Lifting and Rigging Working at Heights
Other: Diving Hot Work Other:
2012 Chevron Pipe Line Company. All Rights Reserved. Page: 8 of 15 Reviewed: November 2012. Uncontrolled when printed.
CONTRACTOR JOB SAFETY PLAN (CJSP)
Energized equipment Sunlight Certified Welder Qualified Gas tester Asbestos Abatement
Static charges X-rays Qualified Crane Operator Confined Space Attendant Lead Abatement
Wiring NORM scale Qualified Rigger Fire Watch Other:
Batteries Other: Qualified Signal Man Equipment Operator
Other: Sound Competent Person Other:
Pressure Equipment noise Scaffolding Inspector
Piping Impact noise Safe Work Practices
Cylinders Venting noise Safe Work Electrical Safe Work Isolation of Hazardous Energy
Vessels/Tanks Communication (SimOps) Bypassing Critical Protection Excavation Simultaneous Operations
Hoses Communication (Language) Confined Space Lifting and Rigging Working at Heights
Other: Other: Diving Hot Work Other:
Other:
2012 Chevron Pipe Line Company. All Rights Reserved. Page: 9 of 15 Reviewed: November 2012. Uncontrolled when printed.
CONTRACTOR JOB SAFETY PLAN (CJSP)
2012 Chevron Pipe Line Company. All Rights Reserved. Page: 10 of 15 Reviewed: November 2012. Uncontrolled when printed.
CONTRACTOR JOB SAFETY PLAN (CJSP)
Ammonia Nitrate
-Valve/Pump
Packing -Gaskets
-Pipe -Brakes Operations and
Asbestos Coating Maintenance
-Building
-Pipe Materials
-Insulation
-Sampling
-Tank
-Crudes -Spill Clean Cleaning
up
-Products -Tank
Benzene -Checking Inspections
-Solvents
Leaks
-Condensates -Waste
-Confined Handling
Space
Rescue or Emergency
Bloodborne Pathogens Contact with blood
Activities
-Welding
Burns -Hot Equipment Welding and Maintenance
-Sunlight
-Vehicle Emissions
Operations and
Carbon Monoxide -Fire Combustion
Maintenance
-Product
-Weather -Old
buildings Operations and
Dust -Abrasive Maintenance
blasting -Vaults
2012 Chevron Pipe Line Company. All Rights Reserved. Page: 11 of 15 Reviewed: November 2012. Uncontrolled when printed.
CONTRACTOR JOB SAFETY PLAN (CJSP)
Operations and
Fiberglass Insulation
Maintenance, Repairs
Operations and
Repairs,Grinding on
Grinding Dusts Maintenance, Pipeline
equipment, fabrication
Repairs
Operations and
H2S Crude Oil, Oil fields
Maintenance
-Environmental -Furnaces
-Offices Operations and
-Switch Gear
Heat Maintenance, Pipeline
-Engines -Hot Crude Repairs
-Steam lines Lines
Operations and
Hydrocarbon Liquid Crude Oil, Oil fields Maintenance, Pipeline
Repairs
Operations and
Hydrocarbon Vapors Crude Oil, Oil fields Maintenance, Pipeline
Repairs
Operations and
LPG Facilities, pipelines,
L.P.G. Maintenance, Pipeline
tankers
Repairs
Engines, pumps, rotating Operations and
Lube Oils equipment Maintenance
ROW clearing
Lyme Disease Ticks
Job Walks in high brush
-Light Crude Oil, Oil fields, Pipeline repairs, Operations
Mercury and Maintenance
-Switches
2012 Chevron Pipe Line Company. All Rights Reserved. Page: 12 of 15 Reviewed: November 2012. Uncontrolled when printed.
CONTRACTOR JOB SAFETY PLAN (CJSP)
-Hand Tools
Heavy
equipment
Operations and
Sewage lines, treatment
Sewage Maintenance, pipeline
facilities
repairs and installs
Operations and
Equipment, tools, broken
Sharps Maintenance, pipeline
glass, pipeline, etc
repairs and installs
Operations and
Abrasive blasting, mud
Silica/sand Maintenance, pipeline
mixing on drills, excavations
repairs and installs
Operations and
Maintenance, pipeline
Snake Bites Snakes
repairs and installs, ROW
clearings
-Lab chemicals
Operations and
Solvents -Degreasers Maintenance, pipeline
repairs and installs
-Paints
2012 Chevron Pipe Line Company. All Rights Reserved. Page: 13 of 15 Reviewed: November 2012. Uncontrolled when printed.
CONTRACTOR JOB SAFETY PLAN (CJSP)
8.0 Environmental
Wastes Generated:
14.0 Communication
2012 Chevron Pipe Line Company. All Rights Reserved. Page: 14 of 15 Reviewed: November 2012. Uncontrolled when printed.
CONTRACTOR JOB SAFETY PLAN (CJSP)
HAZWOPER Emergency Plan: (Refer to instructions for requirements. This section should be discussed in detail. Append additional documents as
appropriate.)
2012 Chevron Pipe Line Company. All Rights Reserved. Page: 15 of 15 Reviewed: November 2012. Uncontrolled when printed.