Professional Documents
Culture Documents
BCEE 451
Construction Engineering
Lecture 5
Excavations
Learning Objectives
Learners will:
Understand what is excavation and be introduced to the types of
excavations
Understand soil-volume change characteristics associated with
excavating
Be introduced to the types of spoil banks and learn to estimate
their sizes
Be able to estimate the amount of material to be excavated
References
Andres, C. K & Smith, R.C. 1998. Principles and Practices of Heavy
Construction. 5th Edition. Prentice Hall. Pp 18-43
Knutson et al. 2009. Construction Management Fundamentals, McGraw Hill
Construction, pp 369-413
Nunally, S.W. 2010. Construction Methods and Management, Prentice Hall
Dr
C.J.
Willis,
CAPM,
P.Eng
2
1
1/23/14
What is Excavating?
Types of Excavations
2
1/23/14
3
1/23/14
4
1/23/14
Example
Find the shrinkage of a soil that weighs 1661 kg/
m3 in its natural state (Bank) and 2077 kg/m3
after compaction.
5
1/23/14
6
1/23/14
Spoil Bank
7
48 CCM
1/23/14
33 S. El-Omari BCEE 6831 / 492 Lecture 2 34
Spoil Bank
Triangular
g Spoil
p Banks
the Volume
Spoil banks are characterized
= Section area X Lengthby a triangular
its width,
idth it is cross-section
L
H
the spoil R B
the volume
Spoil Pile
Spoil Pile
8
Find the base width
idth and height of a triangular
triang lar spoil Find the base width
idth a
bank containing 76.5 BCM if the pile length is bank containing 76
9 14 m,
9.14 m the soil's angle of repose is 37,
37 and its 9 14 m,
9.14 m the soil's a
swell is 25%. swell is 25%.
1/23/14
Loose volume = 76.5
76 5 X 1.25
1 25
Base width
Height
g =
Spoil Pile
Spoil Bank/Pile
9
1/23/14
Angle of Repose
Angle of Repose
10
1/23/14
Angle of Repose
Spoil Banks
Example
Find the base width and height of a triangular spoil
bank containing 76.5 BCM if the pile length is
9.14m, the soils angle of repose is 37, and its
swell is 25%.
Loose volume = 76.5 x 1.25 = 95.6 m3
Base width = (4 x 95.6 / 9.14 x tan 37)1/2 = 7.45m
Height = (7.45 x tan 37) / 2 = 2.80m
Dr
C.J.
Willis,
CAPM,
P.Eng
22
11
1/23/14
Spoil Pile
Example
Find the base diameter and height of a conical spoil pile
that will contain 76.5 BCM of excavation if the soils
angle of repose is 32 and its swell is 12%.
Loose volume = 76.5 x 1.12 = 85.7 m3
Pit excavations
These are small, relatively deep excavations
those required for basements and foundations.
To determine the volume we simply multiply the
horizontal area by the average depth of the
excavation.
Volume = Horizontal Area x Average Depth
To perform this calculation, first divide the
horizontal area into a convenient set of rectangles,
triangles or circular segments.
12
1/23/14
13
1/23/14
14
1/23/14
Example
Find the volume (bank measure) of excavation
required for a trench 0.92m wide, 1.83m deep and
152m long. Assume that the trench sides will be
approximately vertical.
15
1/23/14
16
1/23/14
17
1/23/14
18
1/23/14
Example:
A rectangular excavation measures 6m X 9m at surface grade. If
the slope of the sides is 1:2 and the excavation is 3.6m deep,
calculate the amount of material that has to be removed in m3.
A = top area= 6 X 9=54m2
Depth of excavation: H=3.6m
B = bottom area= [6 (3.6/2) X 2] X [9 (3.6/2) x 2] = 2.4 x
5.4 = 12.96 m3, say 13m3
Volume of material removed
V = [3.6/3 X (54 +13 + (54 X 13)] = 112.2 m3
Mass Diagram
19
1/23/14
Mass Diagram
Balance Line
20
1/23/14
21
1/23/14
22
1/23/14
Stations (Column1)
A listing of all survey stations at which cross-sectional
areas have been recorded. Usually a full station is a
100ft or 30m interval.
Area of Cut (Column 2)
The cross-sectional area of the cut at each station.
Usually this area must be computed from the project
cross-sections
Area of Fill (Column 3)
The cross-sectional area of fill at each station. Usually
this area must be computed from the project cross-
sections.
Dr
C.J.
Willis,
CAPM,
P.Eng
46
23
1/23/14
24
1/23/14
25
1/23/14
Vol
40000
Mass
Diagram
um
30000
20000
10000
0
0+00
0+50
1+00
2+00
2+50
3+00
4+00
5+00
6+00
6+50
7+00
8+00
8+50
-10000
-20000
-30000
26
1/23/14
?
See Moodle for Assignment 2
27