CONTRACT NO : 010/SP/DIR/XI/2015
JOB NO : 781502
DOC NO : GGCP-00-P0-ES-009-PP
REV :0
DISTRIBUTION ORDER
CONSTRUCTION MANAGER
PROCUREMENT MANAGER
SHE MANAGER
QC MANAGER
CHIEF ENGINEERING
TABLE OF CONTENT
1. INTRODUCTION...........................................................................................................................................
1.1. Scope....................................................................................................................................................
1.2. Definition...............................................................................................................................................
Page 2 of 8
JOB NO : 781502
REV :0
1. INTRODUCTION
1.1. Scope
This procedure covers general procedure for precommissioning activity for Gresik Gas
Cogeneration Plant. This procedure intended as a guideline for precommissioning of package
system in this plant. Whenever the specific precommissioning guideline from related vendor is
submitted, these documents should be used as the execution guideline.
1.2. Definition
Page 3 of 8
JOB NO : 781502
REV :0
The following words shall have the meaning indicated when used herein:
Owner : PT. PUPUK INDONESIA ENERGI
1.4. Abbreviations
NDT : Non-Destructive Test
UBB : Unit Batu Bara
2. GENERAL GUIDELINES
2.1. Precommissioning Execution
Precommissioning is the physically/ mechanically finishing of construction works, and cold alignment
check of each system, unit and overall area that conducted by Contractor and also non-operating
adjustment and testing of each equipment (Mechanical, Instrument, Electrical and Piping), system,
unit and area.
Precommissioning will be conducted when the installation works or construction activity of the
equipment in each system have been finished.
Precommissioning activity will be conducted by Contractors Precommissioning team that consist of
personnel that have been familiar with each system in the facilities and experience in each discipline.
During the precommissioning activity, the Owners operation team members are already present at
site for training and familiarizing the facilities.
Page 4 of 8
JOB NO : 781502
REV :0
All check lists, test sheets and function test report of all precommissioning activities that have
been signed by Owner including punch list will be compiled in Mechanical Completion Dossier.
After finish all precommissioning activities in system, Contractor shall issue Certificate of
Installation Acceptance to Owner for approval for that system that means the system is ready for
commissioning.
Page 5 of 8
JOB NO : 781502
REV :0
REV :0
ATTACHMENT 1
LIST OF SUBSYSTEM AND SYSTEM
System/ Subsystem Re
C mar
ks
Gas Turbine Generator
0
Package Boiler
0
REV :0
IA & PA system
1
HVAC
1
Main Transformer
1
Page 8 of 8