Professional Documents
Culture Documents
Present:
CARPIO, J.,
-versus- Chairperson,
BRION,
PEREZ,
SERENO, and
REYES, JJ.
x-----------------------------------------------------------------------------------------x
DECISION
PEREZ, J.:
The Antecedents
xxx
5. Bank account. TPI shall open and maintain bank accounts in the
United States, which will be used exclusively to deposit funds that it will
collect and to disburse cash it will be obligated to spend in connection
with the implementation of this Agreement.
xxx
13.1 Within thirty (30) days from the date of transmittal of this Award to the
Parties, pursuant to the terms of this award, the total sum to be paid by
RESPONDENT KINGFORD to CLAIMANT TPI, is the sum of ONE MILLION
SEVEN HUNDRED FIFTY THOUSAND EIGHT HUNDRED FORTY SIX
DOLLARS AND TEN CENTS ($1,750,846.10).
(A) For breach of the MOA by not paying past due assessments,
RESPONDENT KINGFORD shall pay CLAIMANT the total sum
of TWO HUNDRED TWENTY NINE THOUSAND THREE
HUNDRED AND FIFTY FIVE DOLLARS AND NINETY CENTS
($229,355.90) which is 20% of MOA assessments since
September 1, 2005[;]
(B) For breach of the MOA in failing to cooperate with CLAIMANT TPI in
fulfilling the objectives of the MOA, RESPONDENT KINGFORD
shall pay CLAIMANT the total sum of TWO HUNDRED
SEVENTY ONE THOUSAND FOUR HUNDRED NINETY
DOLLARS AND TWENTY CENTS ($271,490.20)[;][if !supportFootnotes]
[14][endif]
and
(C) For violation of THE LANHAM ACT and infringement of the
YAMAOKA 619 PATENT, RESPONDENT KINGFORD shall pay
CLAIMANT the total sum of ONE MILLION TWO HUNDRED
FIFTY THOUSAND DOLLARS AND NO CENTS
($1,250,000.00). xxx
xxx[if !supportFootnotes][15][endif]
Petitioner TPI now seeks to nullify, in this instant Petition for Review on
Certiorari under Rule 45, the order of the trial court dismissing its Petition for
Confirmation, Recognition, and Enforcement of Foreign Arbitral Award.
Issue
The core issue in this case is whether or not the court a quo was
correct in so dismissing the petition on the ground of petitioners lack of legal
capacity to sue.
Our Ruling
It is pursuant to the aforequoted provision that the court a quo dismissed the
petition. Thus:
Herein plaintiff TPIs Petition, etc. acknowledges that it is a foreign corporation
established in the State of California and was given the exclusive right to
license or sublicense the Yamaoka Patent and was assigned the exclusive right
to enforce the said patent and collect corresponding royalties in the
Philippines. TPI likewise admits that it does not have a license to do business
in the Philippines.
In several cases, this Court had the occasion to discuss the nature and
applicability of the Corporation Code of the Philippines, a general law, viz-a-viz
other special laws. Thus, in Koruga v. Arcenas, Jr.,[if !supportFootnotes][25][endif] this Court
rejected the application of the Corporation Code and applied the New Central
Bank Act. It ratiocinated:
xxx
Article V
(a) The parties to the agreement referred to in article II were, under the
law applicable to them, under some incapacity, or the said
agreement is not valid under the law to which the parties have
subjected it or, failing any indication thereon, under the law of
the country where the award was made; or
(b) The party against whom the award is invoked was not given proper
notice of the appointment of the arbitrator or of the arbitration
proceedings or was otherwise unable to present his case; or
(c) The award deals with a difference not contemplated by or not falling
within the terms of the submission to arbitration, or it contains
decisions on matters beyond the scope of the submission to
arbitration, provided that, if the decisions on matters submitted
to arbitration can be separated from those not so submitted,
that part of the award which contains decisions on matters
submitted to arbitration may be recognized and enforced; or
(d) The composition of the arbitral authority or the arbitral procedure
was not in accordance with the agreement of the parties, or,
failing such agreement, was not in accordance with the law of
the country where the arbitration took place; or
(e) The award has not yet become binding on the parties, or has been set
aside or suspended by a competent authority of the country in
which, or under the law of which, that award was made.
Clearly, not one of these exclusive grounds touched on the capacity to sue of
the party seeking the recognition and enforcement of the award.
Rule 13.1 of the Special Rules provides that [a]ny party to a foreign
arbitration may petition the court to recognize and enforce a foreign arbitral
award. The contents of such petition are enumerated in Rule 13.5. [if !supportFootnotes]
[32][endif]
Capacity to sue is not included. Oppositely, in the Rule on local arbitral
awards or arbitrations in instances where the place of arbitration is in the
Philippines,[if !supportFootnotes][33][endif] it is specifically required that a petition to
determine any question concerning the existence, validity and enforceability of
such arbitration agreement[if !supportFootnotes][34][endif] available to the parties before the
commencement of arbitration and/or a petition for judicial relief from the
ruling of the arbitral tribunal on a preliminary question upholding or declining
its jurisdiction[if !supportFootnotes][35][endif] after arbitration has already commenced
should state [t]he facts showing that the persons named as petitioner or
respondent have legal capacity to sue or be sued.[if !supportFootnotes][36][endif]
Finally, even assuming, only for the sake of argument, that the court a
quo correctly observed that the Model Law, not the New York Convention,
governs the subject arbitral award,[if !supportFootnotes][39][endif] petitioner may still seek
recognition and enforcement of the award in Philippine court, since the Model
Law prescribes substantially identical exclusive grounds for refusing
recognition or enforcement.[if !supportFootnotes][40][endif]
Premises considered, petitioner TPI, although not licensed to do
business in the Philippines, may seek recognition and enforcement of the
foreign arbitral award in accordance with the provisions of the Alternative
Dispute Resolution Act of 2004.
II
Second. Respondent cannot fault petitioner for not filing a motion for
reconsideration of the assailed Resolution dated 21 November 2008 dismissing
the case. We have, time and again, ruled that the prior filing of a motion for
reconsideration is not required in certiorari under Rule 45.[if !supportFootnotes][41][endif]
Third. While we agree that petitioner failed to observe the principle of hierarchy
of courts, which, under ordinary circumstances, warrants the outright
dismissal of the case,[if !supportFootnotes][42][endif] we opt to relax the rules following the
pronouncement in Chua v. Ang,[if !supportFootnotes][43][endif] to wit:
Moreover, the novelty and the paramount importance of the issue herein raised
should be seriously considered.[if !supportFootnotes][46][endif] Surely, there is a need to
take cognizance of the case not only to guide the bench and the bar, but if only
to strengthen arbitration as a means of dispute resolution, and uphold the
policy of the State embodied in the Alternative Dispute Resolution Act of 2004,
to wit:
Fifth. Respondent claims that petitioner failed to furnish the court of origin a
copy of the motion for time to file petition for review on certiorari before the
petition was filed with this Court.[if !supportFootnotes][47][endif] We, however, find
petitioners reply in order. Thus:
26. Admittedly, reference to Branch 67 in petitioner TPIs Motion for Time to File
a Petition for Review on Certiorari under Rule 45 is a typographical error. As
correctly pointed out by respondent Kingford, the order sought to be assailed
originated from Regional Trial Court, Makati City, Branch 61.
FACTS:
Due to a series of events not mentioned in the Petition, the tuna processors,
including Respondent KINGFORD, withdrew from Petitioner TPI and
correspondingly reneged on their obligations. Petitioner TPI submitted the
dispute for arbitration before the International Centre for Dispute Resolution in
the State of California, United States and won the case against Respondent
KINGFORD.
Hence, the present Petition for Review on Certiorari under Rule 45.
ISSUE:
ARGUMENT:
Petitioner TPI contends that it is entitled to seek for the recognition and
enforcement of the subject foreign arbitral award in accordance with RA No.
9285 (Alternative Dispute Resolution Act of 2004), the Convention on the
Recognition and Enforcement of Foreign Arbitral Awards drafted during the
United Nations Conference on International Commercial Arbitration in 1958
(New York Convention), and the UNCITRAL Model Law on International
Commercial Arbitration (Model Law), as none of these specifically requires that
the party seeking for the enforcement should have legal capacity to sue.
RULING:
RATIO DECIDENDI:
Sec. 45 of the Alternative Dispute Resolution Act of 2004 provides that the
opposing party in an application for recognition and enforcement of the arbitral
award may raise only those grounds that were enumerated under Article V of
the New York Convention, to wit:
Article V
a. The parties to the agreement referred to in Article II were, under the law
applicable to them, under some incapacity, or the said agreement is not valid
under the law to which the parties have subjected it or, failing any indication
thereon, under the law of the country where the award was made;
b. The party against whom the award is invoked was not given proper notice of
the appointment of the arbitrator or of the arbitration proceedings or was
otherwise unable to present his case;
c. The award deals with a difference not contemplated by or not falling within
the terms of the submission to arbitration, or it contains decisions on matters
beyond the scope of the submission to arbitration, provided that, if the
decisions on matters submitted to arbitration can be separated from those not
so submitted, that part of the award which contains decisions on matters
submitted to arbitration may be recognized and enforced;
d. The composition of the arbitral authority or the arbitral procedure was not
in accordance with the agreement of the parties, or, failing such agreement,
was not in accordance with the law of the country where the arbitration took
place; or
e. The award has not yet become binding on the parties, or has been set aside
or suspended by a competent authority of the country in which, or under the
law of which, that award was made.
Rule 13.1 of the Special Rules provides that [a]ny party to a foreign arbitration
may petition the court to recognize and enforce a foreign arbitral award. The
contents of such petition are enumerated in Rule 13.5. Capacity to sue is not
included. Oppositely, in the rule on local arbitral awards or arbitrations in
instances where the place of arbitration is in the Philippines, it is specifically
required that a petition to determine any question concerning the existence,
validity and enforceability of such arbitration agreement available to the
parties before the commencement of arbitration and/or a petition for judicial
relief from the ruling of the arbitral tribunal on a preliminary question
upholding or declining its jurisdiction after arbitration has already
commenced should state [t]he facts showing that the persons named as
petitioner or respondent have legal capacity to sue or be sued.
THIRD DIVISION
PANGANIBAN, J.:
The Case
The Facts
On April 25, 1985, respondent took over some of the work contracted to
petitioner.6 Allegedly, the latter had failed to finish it because of its inability to
procure materials.7
Upon completing its task under the Contract, petitioner billed respondent in
the amount of P6,711,813.90.8 Contesting the accuracy of the amount of
advances and billable accomplishments listed by the former, the latter refused
to pay. Respondent also took refuge in the termination clause of the
Agreement.9 That clause allowed it to set off the cost of the work that petitioner
had failed to undertake -- due to termination or take-over -- against the
amount it owed the latter.
Because of the dispute, petitioner filed with the Regional Trial Court (RTC) of
Makati (Branch 141) a Complaint10 for the collection of the amount
representing the alleged balance due it under the Subcontract. Instead of
submitting an Answer, respondent filed a Motion to Dismiss,11 alleging that
the Complaint was premature, because there was no prior recourse to
arbitration.
In its Order12 dated September 15, 1987, the RTC denied the Motion on the
ground that the dispute did not involve the interpretation or the
implementation of the Agreement and was, therefore, not covered by the
arbitral clause.13
After trial on the merits, the RTC14 ruled that the take-over of some work
items by respondent was not equivalent to a termination, but a mere
modification, of the Subcontract. The latter was ordered to give full payment for
the work completed by petitioner.
On appeal, the CA reversed the RTC and ordered the referral of the case to
arbitration. The appellate court held as arbitrable the issue of whether
respondents take-over of some work items had been intended to be a
termination of the original contract under Letter "K" of the Subcontract. It
ruled likewise on two other issues: whether petitioner was liable under the
warranty clause of the Agreement, and whether it should reimburse
respondent for the work the latter had taken over.15
The Issues
In its Memorandum, petitioner raises the following issues for the Courts
consideration:
"A
First Issue:
Whether Dispute Is Arbitrable
We side with respondent. Essentially, the dispute arose from the parties
ncongruent positions on whether certain provisions of their Agreement could
be applied to the facts. The instant case involves technical discrepancies that
are better left to an arbitral body that has expertise in those areas. In any
event, the inclusion of an arbitration clause in a contract does not ipso facto
divest the courts of jurisdiction to pass upon the findings of arbitral bodies,
because the awards are still judicially reviewable under certain conditions.18
In the case before us, the Subcontract has the following arbitral clause:
"6. The Parties hereto agree that any dispute or conflict as regards to
interpretation and implementation of this Agreement which cannot be settled
between [respondent] and [petitioner] amicably shall be settled by means of
arbitration x x x."19
Clearly, the resolution of the dispute between the parties herein requires a
referral to the provisions of their Agreement. Within the scope of the arbitration
clause are discrepancies as to the amount of advances and billable
accomplishments, the application of the provision on termination, and the
consequent set-off of expenses.
A review of the factual allegations of the parties reveals that they differ on the
following questions: (1) Did a take-over/termination occur? (2) May the
expenses incurred by respondent in the take-over be set off against the
amounts it owed petitioner? (3) How much were the advances and billable
accomplishments?
The resolution of the foregoing issues lies in the interpretation of the provisions
of the Agreement. According to respondent, the take-over was caused by
petitioners delay in completing the work. Such delay was in violation of the
provision in the Agreement as to time schedule:
"[Petitioner] shall adhere strictly to the schedule related to the WORK and
complete the WORK within the period set forth in Annex C hereof. NO time
extension shall be granted by [respondent] to [petitioner] unless a
corresponding time extension is granted by [the Ministry of Public Works and
Highways] to the CONSORTIUM."20
Because of the delay, respondent alleges that it took over some of the work
contracted to petitioner, pursuant to the following provision in the Agreement:
"[Respondent] has the right to terminate and/or take over this Agreement for
any of the following causes:
"If the total direct and indirect cost of completing the remaining part of the
WORK exceed the sum which would have been payable to [petitioner] had it
completed the WORK, the amount of such excess [may be] claimed by
[respondent] from either of the following:
1. Any amount due [petitioner] from [respondent] at the time of the termination
of this Agreement."22
"[Respondent shall open the letters of credit for the importation of equipment
and materials listed in Annex E hereof after the drawings, brochures, and other
technical data of each items in the list have been formally approved by [the
Ministry of Public Works and Highways]. However, petitioner will still be fully
responsible for all imported materials and equipment.
"2. All customs duties, import duties, contractors taxes, income taxes, and
other taxes that may be required by any government agencies in connection
with this Agreement shall be for the sole account of [petitioner]."23
Second Issue:
Prior Request for Arbitration
On the other hand, Section 1 of Article III of the new Rules of Procedure
Governing Construction Arbitration has dispensed with this requirement and
recourse to the CIAC may now be availed of whenever a contract "contains a
clause for the submission of a future controversy to arbitration," in this wise:
The difference in the two provisions was clearly explained in China Chang Jiang
Energy Corporation (Philippines) v. Rosal Infrastructure Builders et al.32 (an
extended unsigned Resolution) and reiterated in National Irrigation
Administration v. Court of Appeals,33 from which we quote thus:
"Under the present Rules of Procedure, for a particular construction contract to
fall within the jurisdiction of CIAC, it is merely required that the parties agree
to submit the same to voluntary arbitration Unlike in the original version of
Section 1, as applied in the Tesco case, the law as it now stands does not
provide that the parties should agree to submit disputes arising from their
agreement specifically to the CIAC for the latter to acquire jurisdiction over the
same. Rather, it is plain and clear that as long as the parties agree to submit to
voluntary arbitration, regardless of what forum they may choose, their
agreement will fall within the jurisdiction of the CIAC, such that, even if they
specifically choose another forum, the parties will not be precluded from
electing to submit their dispute before the CIAC because this right has been
vested upon each party by law, i.e., E.O. No. 1008."34
Clearly, there is no more need to file a request with the CIAC in order to vest it
with jurisdiction to decide a construction dispute.
Since petitioner has already filed a Complaint with the RTC without prior
recourse to arbitration, the proper procedure to enable the CIAC to decide on
the dispute is to request the stay or suspension of such action, as provided
under RA 876 [the Arbitration Law].37
SO ORDERED.
SECOND DIVISION
DECISION
When KOGIES deposited the checks, these were dishonored for the
reason PAYMENT STOPPED. Thus, on May 8, 1998, KOGIES sent a demand
letter[if !supportFootnotes][6][endif] to PGSMC threatening criminal action for violation of
Batas Pambansa Blg. 22 in case of nonpayment. On the same date, the wife of
PGSMCs President faxed a letter dated May 7, 1998 to KOGIES President who
was then staying at a Makati City hotel. She complained that not only did
KOGIES deliver a different brand of hydraulic press from that agreed upon but
it had not delivered several equipment parts already paid for.
On May 14, 1998, PGSMC replied that the two checks it issued
KOGIES were fully funded but the payments were stopped for reasons
previously made known to KOGIES.[if !supportFootnotes][7][endif]
On June 15, 1998, KOGIES wrote PGSMC informing the latter that
PGSMC could not unilaterally rescind their contract nor dismantle and transfer
the machineries and equipment on mere imagined violations by KOGIES. It
also insisted that their disputes should be settled by arbitration as agreed upon
in Article 15, the arbitration clause of their contract.
After the parties submitted their Memoranda, on July 23, 1998, the
RTC issued an Order denying the application for a writ of preliminary
injunction, reasoning that PGSMC had paid KOGIES USD 1,224,000, the value
of the machineries and equipment as shown in the contract such that KOGIES
no longer had proprietary rights over them. And finally, the RTC held that Art.
15 of the Contract as amended was invalid as it tended to oust the trial court
or any other court jurisdiction over any dispute that may arise between the
parties. KOGIES prayer for an injunctive writ was denied. [if !supportFootnotes][10][endif]
The dispositive portion of the Order stated:
On July 29, 1998, KOGIES filed its Reply to Answer and Answer to
Counterclaim.[if !supportFootnotes][11][endif] KOGIES denied it had altered the quantity and
lowered the quality of the machinery, equipment, and facilities it delivered to
the plant. It claimed that it had performed all the undertakings under the
contract and had already produced certified samples of LPG cylinders. It
averred that whatever was unfinished was PGSMCs fault since it failed to
procure raw materials due to lack of funds. KOGIES, relying on Chung Fu
Industries (Phils.), Inc. v. Court of Appeals,[if !supportFootnotes][12][endif] insisted that the
arbitration clause was without question valid.
On September 21, 1998, the trial court issued an Order (1) granting
PGSMCs motion for inspection; (2) denying KOGIES motion for reconsideration
of the July 23, 1998 RTC Order; and (3) denying KOGIES motion to dismiss
PGSMCs compulsory counterclaims as these counterclaims fell within the
requisites of compulsory counterclaims.
Ten days after, on October 12, 1998, without waiting for the resolution
of its October 2, 1998 urgent motion for reconsideration, KOGIES filed before
the Court of Appeals (CA) a petition for certiorari [if !supportFootnotes][18][endif] docketed as
CA-G.R. SP No. 49249, seeking annulment of the July 23, 1998 and September
21, 1998 RTC Orders and praying for the issuance of writs of prohibition,
mandamus, and preliminary injunction to enjoin the RTC and PGSMC from
inspecting, dismantling, and transferring the machineries and equipment in
the Carmona plant, and to direct the RTC to enforce the specific agreement on
arbitration to resolve the dispute.
In the meantime, on October 19, 1998, the RTC denied KOGIES urgent
motion for reconsideration and directed the Branch Sheriff to proceed with the
inspection of the machineries and equipment in the plant on October 28, 1998.
[if !supportFootnotes][19][endif]
On November 11, 1998, the Branch Sheriff filed his Sheriffs Report [if !
supportFootnotes][21][endif]
finding that the enumerated machineries and equipment were
not fully and properly installed.
On May 30, 2000, the CA rendered the assailed Decision [if !supportFootnotes][22]
[endif]
affirming the RTC Orders and dismissing the petition for certiorari filed by
KOGIES. The CA found that the RTC did not gravely abuse its discretion in
issuing the assailed July 23, 1998 and September 21, 1998 Orders. Moreover,
the CA reasoned that KOGIES contention that the total contract price for USD
1,530,000 was for the whole plant and had not been fully paid was contrary to
the finding of the RTC that PGSMC fully paid the price of USD 1,224,000,
which was for all the machineries and equipment. According to the CA, this
determination by the RTC was a factual finding beyond the ambit of a petition
for certiorari.
On the issue of the validity of the arbitration clause, the CA agreed
with the lower court that an arbitration clause which provided for a final
determination of the legal rights of the parties to the contract by arbitration
was against public policy.
Furthermore, the CA held that the petition for certiorari had been filed
prematurely since KOGIES did not wait for the resolution of its urgent motion
for reconsideration of the September 21, 1998 RTC Order which was the plain,
speedy, and adequate remedy available. According to the CA, the RTC must be
given the opportunity to correct any alleged error it has committed, and that
since the assailed orders were interlocutory, these cannot be the subject of a
petition for certiorari.
Hence, we have this Petition for Review on Certiorari under Rule 45.
The Issues
Before we delve into the substantive issues, we shall first tackle the
procedural issues.
On July 17, 1998, at the time PGSMC filed its Answer incorporating its
counterclaims against KOGIES, it was not liable to pay filing fees for said
counterclaims being compulsory in nature. We stress, however, that effective
August 16, 2004 under Sec. 7, Rule 141, as amended by A.M. No. 04-2-04-SC,
docket fees are now required to be paid in compulsory counterclaim or cross-
claims.
The September 21, 1998 RTC Order directing the branch sheriff to
inspect the plant, equipment, and facilities when he is not competent and
knowledgeable on said matters is evidently flawed and devoid of any legal
support. Moreover, there is an urgent necessity to resolve the issue on the
dismantling of the facilities and any further delay would prejudice the interests
of KOGIES. Indeed, there is real and imminent threat of irreparable destruction
or substantial damage to KOGIES equipment and machineries. We find the
resort to certiorari based on the gravely abusive orders of the trial court sans
the ruling on the October 2, 1998 motion for reconsideration to be proper.
Petitioner is correct.
Established in this jurisdiction is the rule that the law of the place
where the contract is made governs. Lex loci contractus. The contract in this
case was perfected here in the Philippines. Therefore, our laws ought to govern.
Nonetheless, Art. 2044 of the Civil Code sanctions the validity of mutually
agreed arbitral clause or the finality and binding effect of an arbitral award.
Art. 2044 provides, Any stipulation that the arbitrators award or decision
shall be final, is valid, without prejudice to Articles 2038, 2039 and 2040.
(Emphasis supplied.)
Having said that the instant arbitration clause is not against public
policy, we come to the question on what governs an arbitration clause
specifying that in case of any dispute arising from the contract, an arbitral
panel will be constituted in a foreign country and the arbitration rules of the
foreign country would govern and its award shall be final and binding.
Under Sec. 24, the RTC does not have jurisdiction over disputes that
are properly the subject of arbitration pursuant to an arbitration clause, and
mandates the referral to arbitration in such cases, thus:
xxxx
xxxx
It is now clear that foreign arbitral awards when confirmed by the RTC
are deemed not as a judgment of a foreign court but as a foreign arbitral award,
and when confirmed, are enforced as final and executory decisions of our
courts of law.
Thus, it can be gleaned that the concept of a final and binding arbitral
award is similar to judgments or awards given by some of our quasi-judicial
bodies, like the National Labor Relations Commission and Mines Adjudication
Board, whose final judgments are stipulated to be final and binding, but not
immediately executory in the sense that they may still be judicially reviewed,
upon the instance of any party. Therefore, the final foreign arbitral awards are
similarly situated in that they need first to be confirmed by the RTC.
xxxx
Thus, while the RTC does not have jurisdiction over disputes governed
by arbitration mutually agreed upon by the parties, still the foreign arbitral
award is subject to judicial review by the RTC which can set aside, reject, or
vacate it. In this sense, what this Court held in Chung Fu Industries (Phils.),
Inc. relied upon by KOGIES is applicable insofar as the foreign arbitral awards,
while final and binding, do not oust courts of jurisdiction since these arbitral
awards are not absolute and without exceptions as they are still judicially
reviewable. Chapter 7 of RA 9285 has made it clear that all arbitral awards,
whether domestic or foreign, are subject to judicial review on specific grounds
provided for.
(4) Grounds for judicial review different in domestic and foreign arbitral
awards
For final domestic arbitral awards, which also need confirmation by the
RTC pursuant to Sec. 23 of RA 876[if !supportFootnotes][44][endif] and shall be recognized
as final and executory decisions of the RTC, [if !supportFootnotes][45][endif] they may only be
assailed before the RTC and vacated on the grounds provided under Sec. 25 of
RA 876.[if !supportFootnotes][46][endif]
Having ruled that the arbitration clause of the subject contract is valid
and binding on the parties, and not contrary to public policy; consequently,
being bound to the contract of arbitration, a party may not unilaterally rescind
or terminate the contract for whatever cause without first resorting to
arbitration.
What this Court held in University of the Philippines v. De Los Angeles [if !
supportFootnotes][47][endif]
and reiterated in succeeding cases,[if !supportFootnotes][48][endif] that the
act of treating a contract as rescinded on account of infractions by the other
contracting party is valid albeit provisional as it can be judicially assailed, is
not applicable to the instant case on account of a valid stipulation on
arbitration. Where an arbitration clause in a contract is availing, neither of the
parties can unilaterally treat the contract as rescinded since whatever
infractions or breaches by a party or differences arising from the contract must
be brought first and resolved by arbitration, and not through an extrajudicial
rescission or judicial action.
The issues arising from the contract between PGSMC and KOGIES on
whether the equipment and machineries delivered and installed were properly
installed and operational in the plant in Carmona, Cavite; the ownership of
equipment and payment of the contract price; and whether there was
substantial compliance by KOGIES in the production of the samples, given the
alleged fact that PGSMC could not supply the raw materials required to
produce the sample LPG cylinders, are matters proper for arbitration. Indeed,
we note that on July 1, 1998, KOGIES instituted an Application for Arbitration
before the KCAB in Seoul, Korea pursuant to Art. 15 of the Contract as
amended. Thus, it is incumbent upon PGSMC to abide by its commitment to
arbitrate.
For these reasons, the September 21, 1998 and October 19, 1998 RTC
Orders pertaining to the grant of the inspection of the equipment and
machineries have to be recalled and nullified.
Petitioner assails the CA ruling that the issue petitioner raised on whether the
total contract price of USD 1,530,000 was for the whole plant and its
installation is beyond the ambit of a Petition for Certiorari.
Anent the July 23, 1998 Order denying the issuance of the injunctive
writ paving the way for PGSMC to dismantle and transfer the equipment and
machineries, we find it to be in order considering the factual milieu of the
instant case.
Firstly, while the issue of the proper installation of the equipment and
machineries might well be under the primary jurisdiction of the arbitral body
to decide, yet the RTC under Sec. 28 of RA 9285 has jurisdiction to hear and
grant interim measures to protect vested rights of the parties. Sec. 28
pertinently provides:
(g) A party who does not comply with the order shall be
liable for all damages resulting from noncompliance, including
all expenses, and reasonable attorney's fees, paid in obtaining
the orders judicial enforcement. (Emphasis ours.)
(b) Take action that would prevent, or refrain from taking action that is likely to
cause, current or imminent harm or prejudice to the arbitral process itself;
(c) Provide a means of preserving assets out of which a subsequent award may
be satisfied; or
(d) Preserve evidence that may be relevant and material to the resolution of the
dispute.
Art. 17 J of UNCITRAL Model Law on ICA also grants courts power and
jurisdiction to issue interim measures:
It is thus beyond cavil that the RTC has authority and jurisdiction to
grant interim measures of protection.
Finally, while PGSMC may have been granted the right to dismantle
and transfer the subject equipment and machineries, it does not have the right
to convey or dispose of the same considering the pending arbitral proceedings
to settle the differences of the parties. PGSMC therefore must preserve and
maintain the subject equipment and machineries with the diligence of a good
father of a family[if !supportFootnotes][51][endif] until final resolution of the arbitral
proceedings and enforcement of the award, if any.
(2) The September 21, 1998 and October 19, 1998 RTC Orders in Civil
Case No. 98-117 are REVERSED and SET ASIDE;
No pronouncement as to costs.
SO ORDERED.
PUNO, C. J.,
Chairperson,
[if !supportLists]- [endif]versus AUSTRIA-MARTINEZ,
CALLEJO, SR.,
TINGA, and
NAZARIO, JJ.
CLIMAX MINING LTD.,
CLIMAX-ARIMCO MINING CORP.,
and AUSTRALASIAN PHILIPPINES Promulgated:
MINING INC.,
Respondents. January 22, 2007
x--------------------------------------------------------------------------------- x
R E S O L U T I ON
TINGA, J.:
Respondents Climax Mining Ltd., et al., (respondents) filed their Motion for
Partial Reconsideration and/or Clarification[if !supportFootnotes][3][endif] seeking
reconsideration of that part of the Decision holding that the case should not be
brought for arbitration under Republic Act (R.A.) No. 876, also known as the
Arbitration Law.[if !supportFootnotes][4][endif] Respondents, citing American jurisprudence[if
!supportFootnotes][5][endif]
and the UNCITRAL Model Law,[if !supportFootnotes][6][endif] argue that the
arbitration clause in the Addendum Contract should be treated as an
agreement independent of the other terms of the contract, and that a claimed
rescission of the main contract does not avoid the duty to arbitrate.
Respondents add that Gonzaless argument relating to the alleged invalidity of
the Addendum Contract still has to be proven and adjudicated on in a proper
proceeding; that is, an action separate from the motion to compel arbitration.
Pending judgment in such separate action, the Addendum Contract remains
valid and binding and so does the arbitration clause therein. Respondents add
that the holding in the Decision that the case should not be brought under the
ambit of the Arbitration Law appears to be premised on Gonzaless having
impugn[ed] the existence or validity of the addendum contract. If so, it
supposedly conveys the idea that Gonzaless unilateral repudiation of the
contract or mere allegation of its invalidity is all it takes to avoid arbitration.
Hence, respondents submit that the courts holding that the case should not be
brought under the ambit of the Arbitration Law be understood or clarified as
operative only where the challenge to the arbitration agreement has been
sustained by final judgment.
Both parties were required to file their respective comments to the other partys
motion for reconsideration/clarification.[if !supportFootnotes][7][endif] Respondents filed
their Comment on 17 August 2005, [if !supportFootnotes][8][endif] while Gonzales filed his
only on 25 July 2006.[if !supportFootnotes][9][endif]
On the other hand, G.R. No. 167994 is a Rule 65 petition filed on 6 May 2005,
or while the motions for reconsideration in G.R. No. 161957 [if !supportFootnotes][10][endif]
were pending, wherein Gonzales challenged the orders of the Regional Trial
Court (RTC) requiring him to proceed with the arbitration proceedings as
sought by Climax-Arimco Mining Corporation (Climax-Arimco).
On 5 June 2006, the two cases, G.R. Nos. 161957 and 167994, were
consolidated upon the recommendation of the Assistant Division Clerk of Court
since the cases are rooted in the same Addendum Contract.
We first tackle the more recent case which is G.R. No. 167994. It stemmed from
the petition to compel arbitration filed by respondent Climax-Arimco before the
RTC of Makati City on 31 March 2000 while the complaint for the nullification
of the Addendum Contract was pending before the DENR Panel of Arbitrators.
On 23 March 2000, Climax-Arimco had sent Gonzales a Demand for
Arbitration pursuant to Clause 19.1 [if !supportFootnotes][11][endif] of the Addendum
Contract and also in accordance with Sec. 5 of R.A. No. 876. The petition for
arbitration was subsequently filed and Climax-Arimco sought an order to
compel the parties to arbitrate pursuant to the said arbitration clause. The
case, docketed as Civil Case No. 00-444, was initially raffled to Br. 132 of the
RTC of Makati City, with Judge Herminio I. Benito as Presiding Judge.
Respondent Climax-Arimco filed on 5 April 2000 a motion to set the application
to compel arbitration for hearing.
On 14 April 2000, Gonzales filed a motion to dismiss which he however failed
to set for hearing. On 15 May 2000, he filed an Answer with Counterclaim, [if !
supportFootnotes][12][endif]
questioning the validity of the Addendum Contract containing
the arbitration clause. Gonzales alleged that the Addendum Contract
containing the arbitration clause is void in view of Climax-Arimcos acts of
fraud, oppression and violation of the Constitution. Thus, the arbitration
clause, Clause 19.1, contained in the Addendum Contract is also null and void
ab initio and legally inexistent.
On 31 May 2000, Gonzales asked the RTC to set the case for pre-trial. [if !
supportFootnotes][14][endif]
This the RTC denied on 16 June 2000, holding that the
petition for arbitration is a special proceeding that is summary in nature. [if !
supportFootnotes][15][endif]
However, on 7 July 2000, the RTC granted Gonzaless motion
for reconsideration of the 16 June 2000 Order and set the case for pre-trial on
10 August 2000, it being of the view that Gonzales had raised in his answer the
issue of the making of the arbitration agreement.[if !supportFootnotes][16][endif]
Gonzales moved for reconsideration on 20 March 2001 but this was denied in
the Order dated 7 March 2005.[if !supportFootnotes][21][endif]
Gonzales thus filed the Rule 65 petition assailing the Orders dated 13
February 2001 and 7 March 2005 of Judge Pimentel. Gonzales contends that
public respondent Judge Pimentel acted with grave abuse of discretion in
immediately ordering the parties to proceed with arbitration despite the proper,
valid, and timely raised argument in his Answer with Counterclaim that the
Addendum Contract, containing the arbitration clause, is null and void.
Gonzales has also sought a temporary restraining order to prevent the
enforcement of the assailed orders directing the parties to arbitrate, and to
direct Judge Pimentel to hold a pre-trial conference and the necessary hearings
on the determination of the nullity of the Addendum Contract.
Gonzales also cites Sec. 24 of R.A. No. 9285 or the Alternative Dispute
Resolution Act of 2004:
Climax-Arimco mentions that the special civil action for certiorari employed by
Gonzales is available only where there is no appeal or any plain, speedy, and
adequate remedy in the ordinary course of law against the challenged orders or
acts. Climax-Arimco then points out that R.A. No. 876 provides for an appeal
from such orders, which, under the Rules of Court, must be filed within 15
days from notice of the final order or resolution appealed from or of the denial
of the motion for reconsideration filed in due time. Gonzales has not denied
that the relevant 15-day period for an appeal had elapsed long before he filed
this petition for certiorari. He cannot use the special civil action of certiorari as
a remedy for a lost appeal.
Thus, the main issue raised in the Petition for Certiorari is whether it was
proper for the RTC, in the proceeding to compel arbitration under R.A. No. 876,
to order the parties to arbitrate even though the defendant therein has raised
the twin issues of validity and nullity of the Addendum Contract and,
consequently, of the arbitration clause therein as well. The resolution of both
Climax-Arimcos Motion for Partial Reconsideration and/or Clarification in G.R.
No. 161957 and Gonzaless Petition for Certiorari in G.R. No. 167994 essentially
turns on whether the question of validity of the Addendum Contract bears
upon the applicability or enforceability of the arbitration clause contained
therein. The two pending matters shall thus be jointly resolved.
We address the Rule 65 petition in G.R. No. 167994 first from the
remedial law perspective. It deserves to be dismissed on procedural grounds, as
it was filed in lieu of appeal which is the prescribed remedy and at that far
beyond the reglementary period. It is elementary in remedial law that the use
of an erroneous mode of appeal is cause for dismissal of the petition for
certiorari and it has been repeatedly stressed that a petition for certiorari is not
a substitute for a lost appeal. As its nature, a petition for certiorari lies only
where there is no appeal, and no plain, speedy and adequate remedy in the
ordinary course of law.[if !supportFootnotes][25][endif] The Arbitration Law specifically
provides for an appeal by certiorari, i.e., a petition for review under certiorari
under Rule 45 of the Rules of Court that raises pure questions of law. [if !
supportFootnotes][26][endif]
There is no merit to Gonzaless argument that the use of the
permissive term may in Sec. 29, R.A. No. 876 in the filing of appeals does not
prohibit nor discount the filing of a petition for certiorari under Rule 65. [if !
supportFootnotes][27][endif]
Proper interpretation of the aforesaid provision of law shows
that the term may refers only to the filing of an appeal, not to the mode of
review to be employed. Indeed, the use of may merely reiterates the principle
that the right to appeal is not part of due process of law but is a mere statutory
privilege to be exercised only in the manner and in accordance with law.
The Court did not uphold BF Corporations argument. The issue raised
before the Court was whether SPI had taken the proper mode of appeal before
the Court of Appeals. The question before the Court of Appeals was whether
the trial court had prematurely assumed jurisdiction over the controversy. The
question of jurisdiction in turn depended on the question of existence of the
arbitration clause which is one of fact. While on its face the question of
existence of the arbitration clause is a question of fact that is not proper in a
petition for certiorari, yet since the determination of the question obliged the
Court of Appeals as it did to interpret the contract documents in accordance
with R.A. No. 876 and existing jurisprudence, the question is likewise a
question of law which may be properly taken cognizance of in a petition for
certiorari under Rule 65, so the Court held.[if !supportFootnotes][31][endif]
Disputes do not go to arbitration unless and until the parties have agreed to
abide by the arbitrators decision. Necessarily, a contract is required for
arbitration to take place and to be binding. R.A. No. 876 recognizes the
contractual nature of the arbitration agreement, thus:
The special proceeding under Sec. 6 of R.A. No. 876 recognizes the
contractual nature of arbitration clauses or agreements. It provides:
This special proceeding is the procedural mechanism for the enforcement of the
contract to arbitrate. The jurisdiction of the courts in relation to Sec. 6 of R.A.
No. 876 as well as the nature of the proceedings therein was expounded upon
in La Naval Drug Corporation v. Court of Appeals.[if !supportFootnotes][39][endif] There it was
held that R.A. No. 876 explicitly confines the court's authority only to the
determination of whether or not there is an agreement in writing providing for
arbitration. In the affirmative, the statute ordains that the court shall issue an
order "summarily directing the parties to proceed with the arbitration in
accordance with the terms thereof." If the court, upon the other hand, finds
that no such agreement exists, "the proceeding shall be dismissed." [if !
supportFootnotes][40][endif]
The cited case also stressed that the proceedings are
summary in nature.[if !supportFootnotes][41][endif] The same thrust was made in the earlier
case of Mindanao Portland Cement Corp. v. McDonough Construction Co. of
Florida[if !supportFootnotes][42][endif] which held, thus:
The separability doctrine was dwelt upon at length in the U.S. case of
Prima Paint Corp. v. Flood & Conklin Manufacturing Co. [if !supportFootnotes][49][endif] In
that case, Prima Paint and Flood and Conklin (F & C) entered into a consulting
agreement whereby F & C undertook to act as consultant to Prima Paint for six
years, sold to Prima Paint a list of its customers and promised not to sell paint
to these customers during the same period. The consulting agreement
contained an arbitration clause. Prima Paint did not make payments as
provided in the consulting agreement, contending that F & C had fraudulently
misrepresented that it was solvent and able for perform its contract when in
fact it was not and had even intended to file for bankruptcy after executing the
consultancy agreement. Thus, F & C served Prima Paint with a notice of
intention to arbitrate. Prima Paint sued in court for rescission of the consulting
agreement on the ground of fraudulent misrepresentation and asked for the
issuance of an order enjoining F & C from proceeding with arbitration. F & C
moved to stay the suit pending arbitration. The trial court granted F & Cs
motion, and the U.S. Supreme Court affirmed.
The U.S. Supreme Court did not address Prima Paints argument that it
had been fraudulently induced by F & C to sign the consulting agreement and
held that no court should address this argument. Relying on Sec. 4 of the
Federal Arbitration Actwhich provides that if a party [claims to be] aggrieved by
the alleged failure x x x of another to arbitrate x x x, [t]he court shall hear the
parties, and upon being satisfied that the making of the agreement for
arbitration or the failure to comply therewith is not in issue, the court shall
make an order directing the parties to proceed to arbitration x x x. If the
making of the arbitration agreement or the failure, neglect, or refusal to
perform the same be in issue, the court shall proceed summarily to the trial
thereofthe U.S. High Court held that the court should not order the parties to
arbitrate if the making of the arbitration agreement is in issue. The parties
should be ordered to arbitration if, and only if, they have contracted to submit
to arbitration. Prima Paint was not entitled to trial on the question of whether
an arbitration agreement was made because its allegations of fraudulent
inducement were not directed to the arbitration clause itself, but only to the
consulting agreement which contained the arbitration agreement. [if !supportFootnotes]
[50][endif]
Prima Paint held that arbitration clauses are separable from the
contracts in which they are embedded, and that where no claim is made that
fraud was directed to the arbitration clause itself, a broad arbitration clause
will be held to encompass arbitration of the claim that the contract itself was
induced by fraud.[if !supportFootnotes][51][endif]
These are the same issues that Gonzales raised in his Rule 45 petition
in G.R. No. 161957 which were resolved against him in the Decision of 28
February 2005. Gonzales does not raise any new argument that would sway
the Court even a bit to alter its holding that the complaint filed before the
DENR Panel of Arbitrators involves judicial issues which should properly be
resolved by the regular courts. He alleged fraud or misrepresentation in the
execution of the Addendum Contract which is a ground for the annulment of a
voidable contract. Clearly, such allegations entail legal questions which are
within the jurisdiction of the courts.
The question of whether Gonzales had ceded his claims over the
mineral deposits in the Addendum Area of Influence is a factual question which
is not proper for determination before this Court. At all events, moreover, the
question is irrelevant to the issue of jurisdiction of the DENR Panel of
Arbitrators. It should be pointed out that the DENR Panel of Arbitrators made a
factual finding in its Order dated 18 October 2001, which it reiterated in its
Order dated 25 June 2002, that Gonzales had, through the various
agreements, assigned his interest over the mineral claims all in favor of
[Climax-Arimco] as well as that without the complainant [Gonzales] assigning
his interest over the mineral claims in favor of [Climax-Arimco], there would be
no FTAA to speak of.[if !supportFootnotes][52][endif] This finding was affirmed by the Court
of Appeals in its Decision dated 30 July 2003 resolving the petition for
certiorari filed by Climax-Arimco in regard to the 18 October 2001 Order of the
DENR Panel.[if !supportFootnotes][53][endif]
The Court of Appeals likewise found that Gonzaless complaint alleged
fraud but did not provide any particulars to substantiate it. The complaint
repeatedly mentioned fraud, oppression, violation of the Constitution and
similar conclusions but nowhere did it give any ultimate facts or particulars
relative to the allegations.[if !supportFootnotes][54][endif]
SO ORDERED.
FIRST DIVISION
INSULAR SAVINGS BANK, G.R. No. 141818
Petitioner,
Present:
Panganiban, C.J.
(Chairperson),
- versus - Ynares-Santiago,
Austria-Martinez,
Callejo, Sr., and
Chico-Nazario, JJ.
FAR EAST BANK AND
TRUST COMPANY, Promulgated:
Respondent.
June 22, 2006
x ---------------------------------------------------------------------------------------- x
DECISION
YNARES-SANTIAGO, J.:
On December 11, 1991, Far East Bank and Trust Company (Respondent) filed
a complaint against Home Bankers Trust and Company (HBTC)[if !supportFootnotes][4]
[endif]
with the Philippine Clearing House Corporations (PCHC) Arbitration
Committee docketed as Arbicom Case No. 91-069. [if !supportFootnotes][5][endif] Respondent
sought to recover from the petitioner, the sum of P25,200,000.00 representing
the total amount of the three checks drawn and debited against its clearing
account. HBTC sent these checks to respondent for clearing by operation of the
PCHC clearing system. Thereafter, respondent dishonored the checks for
insufficiency of funds and returned the checks to HBTC. However, the latter
refused to accept them since the checks were returned by respondent after the
reglementary regional clearing period.[if !supportFootnotes][6][endif]
The above Omnibus Order was amended by the trial court in its
October 1, 1992 Order,[if !supportFootnotes][10][endif] the dispositive portion of which reads
as follows:
SO ORDERED.[if !supportFootnotes][11][endif]
In view of the facts found by the committee, no attorneys fees nor other
damages are awarded.
SO ORDERED.[if !supportFootnotes][13][endif]
The motion for reconsideration filed by petitioner was denied by the Arbitration
Committee.[if !supportFootnotes][14][endif] Consequently, to appeal the decision of the
Arbitration Committee in Arbicom Case No. 91-069, petitioner filed a petition
for review in the earlier case filed by respondent in Branch 135 of the RTC
of Makati and docketed as Civil Case No. 92-145.[if !supportFootnotes][15][endif] In an
order dated January 20, 1999, the RTC directed both petitioner and
respondent to file their respective memoranda, after which, said petition would
be deemed submitted for resolution.[if !supportFootnotes][16][endif]
On November 9, 1999, the RTC rendered the assailed Order which held, thus:
Petitioner contends that Civil Case No. 92-145 was merely suspended to await
the outcome of the arbitration case pending before the PCHC. Thus, any
petition questioning the decision of the Arbitration Committee must be filed in
Civil Case No. 92-145 and should not be docketed as a separate action.
Likewise, petitioner avers that had it filed a separate action, this would have
resulted in a multiplicity of suits, which is abhorred in procedure.
SEC. 23. Confirmation of award. At any time within one month after
the award is made, any party to the controversy which was
arbitrated may apply to the court having jurisdiction, as
provided in Section 28, for an order confirming the award;
and thereupon the court must grant such order unless the
award is vacated, modified or corrected, as prescribed
herein. Notice of such motion must be served upon the
adverse party or his attorney as prescribed by law for the
service of such notice upon an attorney in action in the same
court.
SEC. 24. Grounds for vacating award. In any one of the following cases,
the court must make an order vacating the award upon the
petition of any party to the controversy when such party proves
affirmatively that in the arbitration proceedings:
xxxx
SEC. 25. Grounds for modifying or correcting award. In any one of the
following cases, the court must make an order modifying or
correcting the award, upon the application of any party to the
controversy which was arbitrated:
x x x x. (Emphasis supplied)
In the instant case, petitioner and respondent have agreed that the
PCHC Rules would govern in case of controversy. However, since the PCHC
Rules came about only as a result of an agreement between and among
member banks of PCHC and not by law, it cannot confer jurisdiction to the
RTC. Thus, the portion of the PCHC Rules granting jurisdiction to the RTC to
review arbitral awards, only on questions of law, cannot be given effect.
SO ORDERED.
FIRST DIVISION
September 1, 2010
x- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -x
DECISION
The facts of this case, as culled from the records, are as follows:
Being a member state of the International Civil Aviation Organization (ICAO), [if !
supportFootnotes][3][endif]
the Philippines has to comply with the commitments and
standards set forth in ICAO Document No. 9303[if !supportFootnotes][4][endif] which
requires the ICAO member states to issue machine readable travel documents
(MRTDs)[if !supportFootnotes][5][endif] by April 2010.
Thus, in line with the DFAs mandate to improve the passport and visa issuance
system, as well as the storage and retrieval of its related application records,
and pursuant to our governments ICAO commitments, the DFA secured the
approval of the President of the Philippines, as Chairman of the Board of the
National Economic and Development Authority (NEDA), for the implementation
of the Machine Readable Passport and Visa Project (the MRP/V Project) under
the Build-Operate-and-Transfer (BOT) scheme, provided for by Republic Act No.
6957, as amended by Republic Act No. 7718 (the BOT Law), and its
Implementing Rules and Regulations (IRR). Thus, a Pre-qualification, Bids and
Awards Committee (PBAC) published an invitation to pre-qualify and bid for the
supply of the needed machine readable passports and visas, and conducted the
public bidding for the MRP/V Project on January 10, 2000. Several bidders
responded and BCA was among those that pre-qualified and submitted its
technical and financial proposals. On June 29, 2000, the PBAC found BCAs bid
to be the sole complying bid; hence, it permitted the DFA to engage in direct
negotiations with BCA. On even date, the PBAC recommended to the DFA
Secretary the award of the MRP/V Project to BCA on a BOT arrangement.
In compliance with the Notice of Award dated September 29, 2000 and Section
11.3, Rule 11 of the IRR of the BOT Law, [if !supportFootnotes][6][endif] BCA incorporated a
project company, the Philippine Passport Corporation (PPC) to undertake and
implement the MRP/V Project.
xxxx
Phase 1. Project Planning Phase The Project Proponent [BCA] shall prepare
detailed plans and specifications in accordance with Annex A of this [Amended]
BOT Agreement within three (3) months from issuance of the NTP (Notice to
Proceed) [from the date of effectivity of this Amended BOT Agreement]. This
phase shall be considered complete upon the review, acceptance and approval
by the DFA of these plans and the resulting Master Plan, including the Master
Schedule, the business process specifications, the acceptance criteria, among
other plans.
xxxx
xxxx
Within six (6) months from issuance of CA for Phase 2, the Project
Proponent [BCA] shall complete site preparation and
implementation of the approved systems in the ten (10) RCOs,
including a fully functional network connection between all
equipment at the Central Facility and the RCOs.
On the other hand, BCA contends that the DFA failed to perform its
reciprocal obligation to issue to BCA a Certificate of Acceptance of Phase 1
within 14 working days of operation purportedly required by Section 14.04 of
the Amended BOT Agreement. BCA bewailed that it took almost three years for
the DFA to issue the said Certificate allegedly because every appointee to the
position of DFA Secretary wanted to review the award of the project to BCA.
BCA further alleged that it was the DFAs refusal to approve the location of the
DFA Central Facility which prevented BCA from proceeding with Phase 2 of the
MRP/V Project.
Later, the DFA sought the opinion of the Department of Finance (DOF)
and the Department of Justice (DOJ) regarding the appropriate legal actions in
connection with BCAs alleged delays in the completion of the MRP/V Project. In
a Letter dated February 21, 2005, [if !supportFootnotes][14][endif] the DOJ opined that the
DFA should issue a final demand upon BCA to make good on its obligations,
specifically on the warranties and responsibilities regarding the necessary
capitalization and the required financing to carry out the MRP/V Project. The
DOJ used as basis for said recommendation, the Letter dated April 19, 2004 [if !
supportFootnotes][15][endif]
of DOF Secretary Juanita Amatong to then DFA Secretary
Delia Albert stating, among others, that BCA may not be able to infuse more
capital into PPC to use for the completion of the MRP/V Project.
In reply to DFAs letter, BCA, through PPC, informed the former of its position
that its financial capacity was already passed upon during the prequalification
process and that the Amended BOT Agreement did not call for any additional
financial requirements for the implementation of the MRP/V Project.
Nonetheless, BCA submitted its financial statements for the years 2001 and
2002 and requested for additional time within which to comply with the other
financial requirements which the DFA insisted on.[if !supportFootnotes][18][endif]
According to the DFA, BCAs financial warranty is a continuing
warranty which requires that it shall have the necessary capitalization to
finance the MRP/V Project in its entirety and not on a per phase basis as BCA
contends. Only upon sufficient proof of its financial capability to complete and
implement the whole project will the DFAs obligation to choose and approve the
location of its Central Facility arise. The DFA asserted that its approval of a
Central Facility site was not ministerial and upon its review, BCAs proposed
site for the Central Facility was purportedly unacceptable in terms of security
and facilities. Moreover, the DFA allegedly received conflicting official letters
and notices[if !supportFootnotes][19][endif] from BCA and PPC regarding the true ownership
and control of PPC. The DFA implied that the disputes among the shareholders
of PPC and between PPC and BCA appeared to be part of the reason for the
hampered implementation of the MRP/V Project.
BCA, in turn, submitted various letters and documents to prove its financial
capability to complete the MRP/V Project. [if !supportFootnotes][20][endif] However, the DFA
claimed these documents were unsatisfactory or of dubious authenticity. Then
on August 1, 2005, BCA terminated its Assignment Agreement with PPC and
notified the DFA that it would directly implement the MRP/V Project.[if !
supportFootnotes][21][endif]
BCA further claims that the termination of the Assignment
Agreement was upon the instance, or with the conformity, of the DFA, a claim
which the DFA disputed.
On December 14, 2005, BCA sent a letter [if !supportFootnotes][24][endif] to the DFA
demanding that it immediately reconsider and revoke its previous notice of
termination, otherwise, BCA would be compelled to declare the DFA in default
pursuant to the Amended BOT Agreement. When the DFA failed to respond to
said letter, BCA issued its own Notice of Default dated December 22, 2005 [if !
supportFootnotes][25][endif]
against the DFA, stating that if the default is not remedied
within 90 days, BCA will be constrained to terminate the MRP/V Project and
hold the DFA liable for damages.
BCAs request for mutual discussion under Section 19.01 of the Amended BOT
Agreement[if !supportFootnotes][26][endif] was purportedly ignored by the DFA and left the
dispute unresolved through amicable means within 90 days. Consequently,
BCA filed its Request for Arbitration dated April 7, 2006 [if !supportFootnotes][27][endif] with
the Philippine Dispute Resolution Center, Inc. (PDRCI), pursuant to Section
19.02 of the Amended BOT Agreement which provides:
BCAs Request for Arbitration filed with the PDRCI sought the following reliefs:
PDRCI, through a letter dated April 26, 2006, [if !supportFootnotes][30][endif] invited
the DFA to submit its Answer to the Request for Arbitration within 30 days
from receipt of said letter and also requested both the DFA and BCA to
nominate their chosen arbitrator within the same period of time.
Initially, the DFA, through a letter dated May 22, 2006, [if !supportFootnotes][31][endif]
requested for an extension of time to file its answer, without prejudice to
jurisdictional and other defenses and objections available to it under the law.
Subsequently, however, in a letter dated May 29, 2006,[if !supportFootnotes][32][endif] the
DFA declined the request for arbitration before the PDRCI. While it expressed
its willingness to resort to arbitration, the DFA pointed out that under Section
19.02 of the Amended BOT Agreement, there is no mention of a specific body
or institution that was previously authorized by the parties to settle their
dispute. The DFA further claimed that the arbitration of the dispute should be
had before an ad hoc arbitration body, and not before the PDRCI which has as
its accredited arbitrators, two of BCAs counsels of record. Likewise, the DFA
insisted that PPC, allegedly an indispensable party in the instant case, should
also participate in the arbitration.
The DFA then sought the opinion of the DOJ on the Notice of Termination
dated December 9, 2005 that it sent to BCA with regard to the MRP/V Project.
In DOJ Opinion No. 35 (2006) dated May 31, 2006, [if !supportFootnotes][33][endif] the DOJ
concurred with the steps taken by the DFA, stating that there was basis in law
and in fact for the termination of the MRP/V Project. Moreover, the DOJ
recommended the immediate implementation of the project (presumably by a
different contractor) at the soonest possible time.
Thereafter, the DFA and the BSP entered into a Memorandum of Agreement for
the latter to provide the former passports compliant with international
standards. The BSP then solicited bids for the supply, delivery, installation and
commissioning of a system for the production of Electronic Passport Booklets
or e-Passports.[if !supportFootnotes][34][endif]
For BCA, the BSPs invitation to bid for the supply and purchase of e-Passports
(the e-Passport Project) would only further delay the arbitration it requested
from the DFA. Moreover, this new e-Passport Project by the BSP and the DFA
would render BCAs remedies moot inasmuch as the e-Passport Project would
then be replacing the MRP/V Project which BCA was carrying out for the DFA.
Thus, BCA filed a Petition for Interim Relief[if !supportFootnotes][35][endif] under Section 28
of the Alternative Dispute Resolution Act of 2004 (R.A. No. 9285), [if !supportFootnotes]
[36][endif]
with the Regional Trial Court (RTC) of Pasig City, Branch 71, presided
over by respondent Judge Falcon. In that RTC petition, BCA prayed for the
following:
(c) render judgment affirming the interim relief granted to BCA until the
dispute between the parties shall have been resolved with
finality.
BCA also prays for such other relief, just and equitable under the
premises.[if !supportFootnotes][37][endif]
BCA alleged, in support for its application for a Temporary Restraining Order
(TRO), that unless the DFA and the BSP were immediately restrained, they
would proceed to undertake the project together with a third party to defeat the
reliefs BCA sought in its Request for Arbitration, thus causing BCA to suffer
grave and irreparable injury from the loss of substantial investments in
connection with the implementation of the MRP/V Project.
Thereafter, the DFA filed an Opposition (to the Application for Temporary
Restraining Order and/or Writ of Preliminary Injunction) dated January 18,
2007,[if !supportFootnotes][38][endif] alleging that BCA has no cause of action against it as
the contract between them is for machine readable passports and visas which
is not the same as the contract it has with the BSP for the supply of electronic
passports. The DFA also pointed out that the Filipino people and the
governments international standing would suffer great damage if a TRO would
be issued to stop the e-Passport Project. The DFA mainly anchored its
opposition on Republic Act No. 8975, which prohibits trial courts from issuing
a TRO, preliminary injunction or mandatory injunction against the bidding or
awarding of a contract or project of the national government.
On January 23, 2007, after summarily hearing the parties oral arguments on
BCAs application for the issuance of a TRO, the trial court ordered the
issuance of a TRO restraining the DFA and the BSP, their agents,
representatives, awardees, suppliers and assigns from awarding a new contract
to implement the Project or any similar electronic passport or visa project, or if
such contract has been awarded, from implementing such or similar projects. [if !
supportFootnotes][39][endif]
The trial court also set for hearing BCAs application for
preliminary injunction.
In the hearings set for BCAs application for preliminary injunction, BCA
presented as witnesses, Mr. Bonifacio Sumbilla, its President, Mr. Celestino
Mercader, Jr. from the Independent Verification and Validation Contractor
commissioned by the DFA under the Amended BOT Agreement, and DFA
Assistant Secretary Domingo Lucenario, Jr. as adverse party witness.
The DFA and the BSP did not present any witness during the hearings for
BCAs application for preliminary injunction. According to the DFA and the
BSP, the trial court did not have any jurisdiction over the case considering that
BCA did not pay the correct docket fees and that only the Supreme Court could
issue a TRO on the bidding for a national government project like the e-
Passport Project pursuant to the provisions of Republic Act No. 8975. Under
Section 3 of Republic Act No. 8975, the RTC could only issue a TRO against a
national government project if it involves a matter of extreme urgency involving
a constitutional issue, such that unless a TRO is issued, grave injustice and
irreparable injury will arise.
On February 14, 2007, the trial court issued an Order granting BCAs
application for preliminary injunction, to wit:
WHEREFORE, in view of the above, the court resolves
that it has jurisdiction over the instant petition and to issue
the provisional remedy prayed for, and therefore, hereby
GRANTS petitioners [BCAs] application for preliminary
injunction. Accordingly, upon posting a bond in the amount of
Ten Million Pesos (P10,000,000.00), let a writ of preliminary
injunction issue ordering respondents [DFA and BSP], their
agents, representatives, awardees, suppliers and assigns to
desist (i) from awarding a new contract to implement the
project or any similar electronic passport or visa project or (ii)
if such contract has been awarded from implementing such
project or similar projects.
Hence, on March 2, 2007, the DFA and the BSP filed the instant Petition for
Certiorari[if !supportFootnotes][47][endif] and prohibition under Rule 65 of the Rules of
Court with a prayer for the issuance of a temporary restraining order and/or a
writ of preliminary injunction, imputing grave abuse of discretion on the trial
court when it granted interim relief to BCA and issued the assailed Order dated
February 14, 2007 and the writ of preliminary injunction dated February 23,
2007.
The DFA and the BSP later filed an Urgent Motion for Issuance of a Temporary
Restraining Order and/or Writ of Preliminary Injunction dated March 5, 2007. [if
!supportFootnotes][48][endif]
On March 12, 2007, the Court required BCA to file its comment on the said
petition within ten days from notice and granted the Office of the Solicitor
Generals urgent motion for issuance of a TRO and/or writ of preliminary
injunction,[if !supportFootnotes][49][endif] thus:
After deliberating on the petition for certiorari and
prohibition with temporary restraining order and/or writ of
preliminary injunction assailing the Order dated 14 February
2007 of the Regional Trial Court, Branch 71, Pasig City, in
Civil Case No. 71079, the Court, without necessarily giving
due course thereto, resolves to require respondents to
COMMENT thereon (not to file a motion to dismiss) within ten
(10) days from notice.
BCA filed on April 2, 2007 its Comment with Urgent Motion to Lift TRO, [if !
supportFootnotes][50][endif]
to which the DFA and the BSP filed their Reply dated August
[if !supportFootnotes][51][endif]
14, 2007.
Petitioners DFA and BSP submit the following issues for our consideration:
ISSUES
I
II
The Court deems it proper to adopt a similarly liberal attitude in the present
case in consideration of the transcendental importance of an issue raised
herein. This is the first time that the Court is confronted with the question of
whether an information and communication technology project, which does not
conform to our traditional notion of the term infrastructure, is covered by the
prohibition on the issuance of court injunctions found in Republic Act No.
8975, which is entitled An Act to Ensure the Expeditious Implementation and
Completion of Government Infrastructure Projects by Prohibiting Lower Courts
from Issuing Temporary Restraining Orders, Preliminary Injunctions or
Preliminary Mandatory Injunctions, Providing Penalties for Violations Thereof,
and for Other Purposes. Taking into account the current trend of
computerization and modernization of administrative and service systems of
government offices, departments and agencies, the resolution of this issue for
the guidance of the bench and bar, as well as the general public, is both timely
and imperative.
Anent BCAs claim that Mr. Edsel T. Custodio (who verified the Petition
on behalf of the DFA) did not have personal knowledge of the facts of the case
and was appointed to his position as Acting Secretary under purportedly
irregular circumstances, we find that BCA failed to sufficiently prove such
allegations. In any event, we have previously held that [d]epending on the
nature of the allegations in the petition, the verification may be based either
purely on personal knowledge, or entirely on authentic records, or on both
sources.[if !supportFootnotes][57][endif] The alleged lack of personal knowledge of Mr.
Custodio (which, as we already stated, BCA failed to prove) would not
necessarily render the verification defective for he could have verified the
petition purely on the basis of authentic records.
In their petition, the DFA and the BSP argue that respondent Judge
Falcon gravely abused his discretion amounting to lack or excess of jurisdiction
when he issued the assailed orders, which effectively enjoined the bidding
and/or implementation of the e-Passport Project. According to petitioners, this
violated the clear prohibition under Republic Act No. 8975 regarding the
issuance of TROs and preliminary injunctions against national government
projects, such as the e-Passport Project.
If after due hearing the court finds that the award of the contract is
null and void, the court may, if appropriate under the
circumstances, award the contract to the qualified and winning
bidder or order a rebidding of the same, without prejudice to
any liability that the guilty party may incur under existing
laws.
What then are the national government projects over which the lower
courts are without jurisdiction to issue the injunctive relief as mandated by
Republic Act No. 8975?
Under Section 2(a) of the BOT Law as amended by Republic Act No.
7718, !supportFootnotes][61][endif] private sector infrastructure or development
[if
projects are those normally financed and operated by the public sector
but which will now be wholly or partly implemented by the private sector,
including but not limited to, power plants, highways, ports, airports, canals,
dams, hydropower projects, water supply, irrigation, telecommunications,
railroads and railways, transport systems, land reclamation projects, industrial
estates or townships, housing, government buildings, tourism projects,
markets, slaughterhouses, warehouses, solid waste management, information
technology networks and database infrastructure, education and health
facilities, sewerage, drainage, dredging, and other infrastructure and
development projects as may be authorized by the appropriate agency.
In the present petition, the DFA and the BSP contend that the bidding
for the supply, delivery, installation and commissioning of a system for the
production of Electronic Passport Booklets, is a national government project
within the definition of Section 2 of Republic Act No. 8975. Petitioners also
point to the Senate deliberations on Senate Bill No. 2038 [if !supportFootnotes][63][endif]
(later Republic Act No. 8975) which allegedly show the legislatives intent to
expand the scope and definition of national government projects to cover not
only the infrastructure projects enumerated in Presidential Decree No. 1818,
but also future projects that may likewise be considered national government
infrastructure projects, like the e-Passport Project, to wit:
Senator Cayetano. x x x Mr. President, the present bill, the Senate Bill
No. 2038, is actually an improvement of P.D. No. 1818 and
definitely not a repudiation of what I have earlier said, as my
good friend clearly stated. But this is really an effort to improve
both the scope and definition of the term government projects
and to ensure that lower court judges obey and observe this
prohibition on the issuance of TROs on infrastructure projects
of the government.
xxxx
Senator Cayetano. That is why, Mr. President, I did try to explain why
I would accept the proposed amendment, meaning the totality
of the repeal of P.D. 1818 which is not found in the original
version of the bill, because of my earlier explanation that the
definition of the term government infrastructure project covers
all of those enumerated in Section 1 of P.D. No. 1818. And the
reason for that, as we know, is we do not know what else could
be considered government infrastructure project in the next 10
or 20 years.
Using the foregoing discussions to establish that the intent of the framers of
the law was to broaden the scope and definition of national government
projects and national infrastructure projects, the DFA and the BSP submit that
the said scope and definition had since evolved to include the e-Passport
Project. They assert that the concept of infrastructure must now refer to any
and all elements that provide support, framework, or structure for a given
system or organization, including information technology, such as the e-
Passport Project.
Respondent BSPs request for bid, for the supply, delivery, installation
and commissioning of a system for the production of Electronic
Passport Booklets appears to be beyond the scope of the term
civil works. Respondents did not present evidence to prove
otherwise.[if !supportFootnotes][65][endif] (Emphases ours.)
From the foregoing, it can be gleaned that the trial court accepted BCAs
reasoning that, assuming the e-Passport Project is a project under the BOT
Law, Section 2 of the BOT Law must be read in conjunction with Section 5(c) of
Republic Act No. 9184 or the Government Procurement Reform Act to the effect
that only the civil works component of information technology projects are to be
considered infrastructure. Thus, only said civil works component of an
information technology project cannot be the subject of a TRO or writ of
injunction issued by a lower court.
Although the Court finds that the trial court had jurisdiction to issue the writ
of preliminary injunction, we cannot uphold the theory of BCA and the trial
court that the definition of the term infrastructure project in Republic Act No.
9184 should be applied to the BOT Law.
Section 5 of Republic Act No. 9184 prefaces the definition of the terms therein,
including the term infrastructure project, with the following phrase: For
purposes of this Act, the following terms or words and phrases shall mean or
be understood as follows x x x.
This Court has stated that the definition of a term in a statute is not conclusive
as to the meaning of the same term as used elsewhere. [if !supportFootnotes][66][endif] This
is evident when the legislative definition is expressly made for the purposes of
the statute containing such definition.[if !supportFootnotes][67][endif]
In the BOT Law as amended by Republic Act No. 7718, the national
infrastructure and development projects covered by said law are enumerated in
Section 2(a) as follows:
A similar provision appears in the Revised IRR of the BOT Law as amended, to
wit:
xxxx
xxxx
Undeniably, under the BOT Law, wherein the projects are to be privately
funded, the entire information technology project, including the civil works
component and the technological aspect thereof, is considered an
infrastructure or development project and treated similarly as traditional
infrastructure projects. All the rules applicable to traditional infrastructure
projects are also applicable to information technology projects. In fact, the
MRP/V Project awarded to BCA under the BOT Law appears to include both
civil works (i.e., site preparation of the Central Facility, regional DFA offices and
foreign service posts) and non-civil works aspects (i.e., development,
installation and maintenance in the Philippines and foreign service posts of a
computerized passport and visa issuance system, including creation of
databases, storage and retrieval systems, training of personnel and provision of
consumables).
The idea that the definitions of terms found in the Government Procurement
Reform Act were not meant to be applied to projects under the BOT Law is
further reinforced by the following provision in the IRR of the Government
Procurement Reform Act:
However, petitioners presented no proof that the e-Passport Project was a BOT
project. On the contrary, evidence adduced by both sides tended to show that
the e-Passport Project was a procurement contract under Republic Act No.
9184.
The BSPs on-line request for expression of interest and to bid for the e-Passport
Project[if !supportFootnotes][69][endif] from the BSP website and the newspaper clipping [if !
supportFootnotes][70][endif]
of the same request expressly stated that [t]he two stage
bidding procedure under Section 30.4 of the Implementing Rules and
Regulation (sic) Part-A of Republic Act No. 9184 relative to the bidding and
award of the contract shall apply. During the testimony of DFA Assistant
Secretary Domingo Lucenario, Jr. before the trial court, he admitted that the e-
Passport Project is a BSP procurement project and that it is the BSP that will
pay the suppliers.[if !supportFootnotes][71][endif] In petitioners Manifestation dated July 29,
2008[if !supportFootnotes][72][endif] and the Erratum[if !supportFootnotes][73][endif] thereto, petitioners
informed the Court that a contract for the supply of a complete package of
systems design, technology, hardware, software, and peripherals, maintenance
and technical support, ecovers and datapage security laminates for the
centralized production and personalization of Machine Readable Electronic
Passport was awarded to Francois Charles Oberthur Fiduciaire. In the Notice of
Award dated July 2, 2008[if !supportFootnotes][74][endif] attached to petitioners pleading, it
was stated that the failure of the contractor/supplier to submit the required
performance bond would be sufficient ground for the imposition of
administrative penalty under Section 69 of the IRR-A of Republic Act No. 9184.
Being a government procurement contract under Republic Act No. 9184, only
the civil works component of the e-Passport Project would be considered an
infrastructure project that may not be the subject of a lower court-issued writ
of injunction under Republic Act No. 8975.
Could the e-Passport Project be considered as engineering works or a service
contract or as related and necessary activities under Republic Act No. 8975
which may not be enjoined?
We hold in the negative. Under Republic Act No. 8975, a service contract refers
to infrastructure contracts entered into by any department, office or agency of
the national government with private entities and nongovernment organizations
for services related or incidental to the functions and operations of the
department, office or agency concerned. On the other hand, the phrase other
related and necessary activities obviously refers to activities related to a
government infrastructure, engineering works, service contract or project
under the BOT Law. In other words, to be considered a service contract or
related activity, petitioners must show that the e-Passport Project is an
infrastructure project or necessarily related to an infrastructure project. This,
petitioners failed to do for they saw fit not to present any evidence on the
details of the e-Passport Project before the trial court and this Court. There is
nothing on record to indicate that the e-Passport Project has a civil works
component or is necessarily related to an infrastructure project.
Indeed, the reference to Section 30.4 [if !supportFootnotes][75][endif] of the IRR of Republic
Act No. 9184 (a provision specific to the procurement of goods) in the BSPs
request for interest and to bid confirms that the e-Passport Project is a
procurement of goods and not an infrastructure project. Thus, within the
context of Republic Act No. 9184 which is the governing law for the e-Passport
Project the said Project is not an infrastructure project that is protected from
lower court issued injunctions under Republic Act No. 8975, which, to
reiterate, has for its purpose the expeditious and efficient implementation and
completion of government infrastructure projects.
We note that under Section 28, Republic Act No. 9285 or the
Alternative Dispute Resolution Act of 2004,[if !supportFootnotes][76][endif] the grant of an
interim measure of protection by the proper court before the constitution of an
arbitral tribunal is allowed:
[if !supportLists](6) [endif]Either party may apply with the Court for
assistance in implementing or enforcing an interim measure ordered by an
arbitral tribunal.
[if !supportLists](7) [endif]A party who does not comply with the order
shall be liable for all damages resulting from noncompliance, including all
expenses and reasonable attorneys fees, paid in obtaining the orders judicial
enforcement.
Section 3(h) of the same statute provides that the "Court" as referred to
in Article 6 of the Model Law shall mean a Regional Trial Court.
Republic Act No. 9285 is a general law applicable to all matters and
controversies to be resolved through alternative dispute resolution methods.
This law allows a Regional Trial Court to grant interim or provisional relief,
including preliminary injunction, to parties in an arbitration case prior to the
constitution of the arbitral tribunal. This general statute, however, must give
way to a special law governing national government projects, Republic Act No.
8975 which prohibits courts, except the Supreme Court, from issuing TROs
and writs of preliminary injunction in cases involving national government
projects.
Given the above ruling that the trial court had jurisdiction to issue a
writ of injunction and going to the second issue raised by petitioners, we
answer the question: Was the trial courts issuance of a writ of injunction
warranted under the circumstances of this case?
To support their claim that BCA has no clear right to injunctive relief,
petitioners mainly allege that the MRP/V Project and the e-Passport Project are
not the same project. Moreover, the MRP/V Project purportedly involves a
technology (the 2D optical bar code) that has been rendered obsolete by the
latest ICAO developments while the e-Passport Project will comply with the
latest ICAO standards (the contactless integrated circuit). Parenthetically, and
not as a main argument, petitioners imply that BCA has no clear contractual
right under the Amended BOT Agreement since BCA had previously assigned
all its rights and obligations under the said Agreement to PPC.
BCA, on the other hand, claims that the Amended BOT Agreement also
contemplated the supply and/or delivery of e-Passports with the integrated
circuit technology in the future and not only the machine readable passport
with the 2D optical bar code technology. Also, it is BCAs assertion that the
integrated circuit technology is only optional under the ICAO issuances. On the
matter of its assignment of its rights to PPC, BCA counters that it had already
terminated (purportedly at DFAs request) the assignment agreement in favor of
PPC and that even assuming the termination was not valid, the Amended BOT
Agreement expressly stated that BCA shall remain solidarily liable with its
assignee, PPC.
With respect to petitioners contention that BCA will suffer no grave and
irreparable injury so as to justify the grant of injunctive relief, the Court finds
that this particular argument merits consideration.
Under the BOT Law and the Amended BOT Agreement, in the event of
default on the part of the government (in this case, the DFA) or on the part of
the proponent, the non-defaulting party is allowed to terminate the agreement,
again subject to proper compensation in the manner set forth in the
agreement.
Time and again, this Court has held that to be entitled to injunctive relief the
party seeking such relief must be able to show grave, irreparable injury that is
not capable of compensation.
Significantly, in BCAs Request for Arbitration with the PDRCI, it prayed for,
among others, a judgment ordering respondent [DFA] to pay damages to
Claimant [BCA], reasonably estimated at P50,000,000.00 as of [the date of the
Request for Arbitration], representing lost business opportunities; financing
fees, costs and commissions; travel expenses; legal fees and expenses; and
costs of arbitration, including the fees of the arbitrator/s. [if !supportFootnotes][80][endif] All
the purported damages that BCA claims to have suffered by virtue of the DFAs
termination of the Amended BOT Agreement are plainly determinable in
pecuniary terms and can be reasonably estimated according to BCAs own
words.
Indeed, the right of BCA, a party which may or may not have been in default on
its BOT contract, to have the termination of its BOT contract reversed is not
guaranteed by the BOT Law. Even assuming BCAs innocence of any breach of
contract, all the law provides is that BCA should be adequately compensated
for its losses in case of contract termination by the government.
There is one point that none of the parties has highlighted but is worthy of
discussion. In seeking to enjoin the government from awarding or
implementing a machine readable passport project or any similar electronic
passport or visa project and praying for the maintenance of the status quo ante
pending the resolution on the merits of BCAs Request for Arbitration, BCA
effectively seeks to enjoin the termination of the Amended BOT Agreement for
the MRP/V Project.
There is no doubt that the MRP/V Project is a project covered by the BOT Law
and, in turn, considered a national government project under Republic Act No.
8795. Under Section 3(d) of that statute, trial courts are prohibited from
issuing a TRO or writ of preliminary injunction against the government to
restrain or prohibit the termination or rescission of any such national
government project/contract.
The rationale for this provision is easy to understand. For if a project proponent
that the government believes to be in default is allowed to enjoin the
termination of its contract on the ground that it is contesting the validity of
said termination, then the government will be unable to enter into a new
contract with any other party while the controversy is pending litigation.
Obviously, a courts grant of injunctive relief in such an instance is prejudicial
to public interest since government would be indefinitely hampered in its duty
to provide vital public goods and services in order to preserve the private
proprietary rights of the project proponent. On the other hand, should it turn
out that the project proponent was not at fault, the BOT Law itself presupposes
that the project proponent can be adequately compensated for the termination
of the contract. Although BCA did not specifically pray for the trial court to
enjoin the termination of the Amended BOT Agreement and thus, there is no
direct violation of Republic Act No. 8795, a grant of injunctive relief as prayed
for by BCA will indirectly contravene the same statute.
Verily, there is valid reason for the law to deny preliminary injunctive relief to
those who seek to contest the governments termination of a national
government contract. The only circumstance under which a court may grant
injunctive relief is the existence of a matter of extreme urgency involving a
constitutional issue, such that unless a TRO or injunctive writ is issued, grave
injustice and irreparable injury will result.
Now, BCA likewise claims that unless it is granted injunctive relief, it would
suffer grave and irreparable injury since the bidding out and award of the e-
Passport Project would be tantamount to a violation of its right against
deprivation of property without due process of law under Article III, Section 1
of the Constitution. We are unconvinced.
Article III, Section 1 of the Constitution provides [n]o person shall be deprived
of life, liberty, or property without due process of law, nor shall any person be
denied the equal protection of the laws. Ordinarily, this constitutional provision
has been applied to the exercise by the State of its sovereign powers such as,
its legislative power,[if !supportFootnotes][81][endif] police power,[if !supportFootnotes][82][endif] or its
power of eminent domain.[if !supportFootnotes][83][endif]
In the instant case, the State action being assailed is the DFAs termination of
the Amended BOT Agreement with BCA. Although the said agreement involves
a public service that the DFA is mandated to provide and, therefore, is imbued
with public interest, the relationship of DFA to BCA is primarily contractual
and their dispute involves the adjudication of contractual rights. The propriety
of the DFAs acts, in relation to the termination of the Amended BOT
Agreement, should be gauged against the provisions of the contract itself and
the applicable statutes to such contract. These contractual and statutory
provisions outline what constitutes due process in the present case. In all, BCA
failed to demonstrate that there is a constitutional issue involved in this case,
much less a constitutional issue of extreme urgency.
In all, we agree with petitioners DFA and BSP that the trial courts issuance of a
writ of preliminary injunction, despite the lack of sufficient legal justification
for the same, is tantamount to grave abuse of discretion.
To be very clear, the present decision touches only on the twin issues of (a) the
jurisdiction of the trial court to issue a writ of preliminary injunction as an
interim relief under the factual milieu of this case; and (b) the entitlement of
BCA to injunctive relief. The merits of the DFA and BCAs dispute regarding the
termination of the Amended BOT Agreement must be threshed out in the
proper arbitration proceedings. The civil case pending before the trial court is
purely for the grant of interim relief since the main case is to be the subject of
arbitration proceedings.
BCAs petition for interim relief before the trial court is essentially a petition for
a provisional remedy (i.e., preliminary injunction) ancillary to its Request for
Arbitration in PDRCI Case No. 30-2006/BGF. BCA specifically prayed that the
trial court grant it interim relief pending the constitution of the arbitral
tribunal in the said PDRCI case. Unfortunately, during the pendency of this
case, PDRCI Case No. 30-2006/BGF was dismissed by the PDRCI for lack of
jurisdiction, in view of the lack of agreement between the parties to arbitrate
before the PDRCI.[if !supportFootnotes][84][endif] In Philippine National Bank v. Ritratto
Group, Inc.,[if !supportFootnotes][85][endif] we held:
It does not escape the attention of the Court that the delay in the submission
of this controversy to arbitration was caused by the ambiguity in Section 19.02
of the Amended BOT Agreement regarding the proper body to which a dispute
between the parties may be submitted and the failure of the parties to agree on
such an arbitral tribunal. However, this Court cannot allow this impasse to
continue indefinitely. The parties involved must sit down together in good faith
and finally come to an understanding regarding the constitution of an arbitral
tribunal mutually acceptable to them.
No pronouncement as to costs.
SO ORDERED.
SECOND DIVISION
x--------------------------------------------------x
DECISION
PERALTA, J.:
Before us is a petition for review on certiorari seeking to reverse and set aside
the Decision[if !supportFootnotes][1][endif] dated July 31, 2006 and the Resolution [if !
supportFootnotes][2][endif]
dated November 13, 2006 of the Court of Appeals (CA) in CA
G.R. SP No. 50304.
On June 18, 1998, respondent San Fernando Regala Trading, Inc. filed with
the Regional Trial Court (RTC) of Makati City a Complaint for Rescission of
Contract with Damages[if !supportFootnotes][3][endif] against petitioner Cargill Philippines,
Inc. In its Complaint, respondent alleged that it was engaged in buying and
selling of molasses and petitioner was one of its various sources from whom it
purchased molasses. Respondent alleged that it entered into a contract dated
July 11, 1996 with petitioner, wherein it was agreed upon that respondent
would purchase from petitioner 12,000 metric tons of Thailand origin cane
blackstrap molasses at the price of US$192 per metric ton; that the delivery of
the molasses was to be made in January/February 1997 and payment was to
be made by means of an Irrevocable Letter of Credit payable at sight, to be
opened by September 15, 1996; that sometime prior to September 15, 1996,
the parties agreed that instead of January/February 1997, the delivery would
be made in April/May 1997 and that payment would be by an Irrevocable
Letter of Credit payable at sight, to be opened upon petitioner's advice.
Petitioner, as seller, failed to comply with its obligations under the contract,
despite demands from respondent, thus, the latter prayed for rescission of the
contract and payment of damages.
ARBITRATION
Any dispute which the Buyer and Seller may not be able to settle by
mutual agreement shall be settled by arbitration in the City of
New York before the American Arbitration Association. The
Arbitration Award shall be final and binding on both parties.[if !
supportFootnotes][5][endif]
that respondent must first comply with the arbitration clause before resorting
to court, thus, the RTC must either dismiss the case or suspend the
proceedings and direct the parties to proceed with arbitration, pursuant to
Sections 6[if !supportFootnotes][6][endif] and 7[if !supportFootnotes][7][endif] of Republic Act (R.A.) No.
876, or the Arbitration Law.
In its Reply, petitioner maintained that the cited decisions were already
inapplicable, having been rendered prior to the effectivity of the New Civil Code
in 1950 and the Arbitration Law in 1953.
In its Rejoinder, respondent argued that the arbitration clause relied upon by
petitioner is invalid and unenforceable, considering that the requirements
imposed by the provisions of the Arbitration Law had not been complied with.
In denying the motion, the RTC found that there was no clear basis for
petitioner's plea to dismiss the case, pursuant to Section 7 of the Arbitration
Law. The RTC said that the provision directed the court concerned only to stay
the action or proceeding brought upon an issue arising out of an agreement
providing for the arbitration thereof, but did not impose the sanction of
dismissal. However, the RTC did not find the suspension of the proceedings
warranted, since the Arbitration Law contemplates an arbitration proceeding
that must be conducted in the Philippines under the jurisdiction and control of
the RTC; and before an arbitrator who resides in the country; and that the
arbitral award is subject to court approval, disapproval and modification, and
that there must be an appeal from the judgment of the RTC. The RTC found
that the arbitration clause in question contravened these procedures, i.e., the
arbitration clause contemplated an arbitration proceeding in New York before a
non-resident arbitrator (American Arbitration Association); that the arbitral
award shall be final and binding on both parties. The RTC said that to apply
Section 7 of the Arbitration Law to such an agreement would result in
disregarding the other sections of the same law and rendered them useless and
mere surplusages.
Petitioner filed its Motion for Reconsideration, which the RTC denied in an
Order[if !supportFootnotes][10][endif] dated November 25, 1998.
Petitioner filed a petition for certiorari with the CA raising the sole issue that
the RTC acted in excess of jurisdiction or with grave abuse of discretion in
refusing to dismiss or at least suspend the proceedings a quo, despite the fact
that the party's agreement to arbitrate had not been complied with.
Respondent filed its Comment and Reply. The parties were then required to file
their respective Memoranda.
On July 31, 2006, the CA rendered its assailed Decision denying the petition
and affirming the RTC Orders.
In denying the petition, the CA found that stipulation providing for arbitration
in contractual obligation is both valid and constitutional; that arbitration as an
alternative mode of dispute resolution has long been accepted in our
jurisdiction and expressly provided for in the Civil Code; that R.A. No. 876 (the
Arbitration Law) also expressly authorized the arbitration of domestic disputes.
The CA found error in the RTC's holding that Section 7 of R.A. No. 876 was
inapplicable to arbitration clause simply because the clause failed to comply
with the requirements prescribed by the law. The CA found that there was
nothing in the Civil Code, or R.A. No. 876, that require that arbitration
proceedings must be conducted only in the Philippines and the arbitrators
should be Philippine residents. It also found that the RTC ruling effectively
invalidated not only the disputed arbitration clause, but all other agreements
which provide for foreign arbitration. The CA did not find illegal or against
public policy the arbitration clause so as to render it null and void or
ineffectual.
Notwithstanding such findings, the CA still held that the case cannot be
brought under the Arbitration Law for the purpose of suspending the
proceedings before the RTC, since in its Motion to Dismiss/Suspend
proceedings, petitioner alleged, as one of the grounds thereof, that the subject
contract between the parties did not exist or it was invalid; that the said
contract bearing the arbitration clause was never consummated by the parties,
thus, it was proper that such issue be first resolved by the court through an
appropriate trial; that the issue involved a question of fact that the RTC should
first resolve. Arbitration is not proper when one of the parties repudiated the
existence or validity of the contract.
defenses are inconsistent with each other; and (d) the complaint filed by
respondent with the trial court is premature.
Petitioner alleges that the CA adopted inconsistent positions when it found the
arbitration clause between the parties as valid and enforceable and yet in the
same breath decreed that the arbitration cannot proceed because petitioner
assailed the existence of the entire agreement containing the arbitration clause.
Petitioner claims the inapplicability of the cited Gonzales case decided in 2005,
because in the present case, it was respondent who had filed the complaint for
rescission and damages with the RTC, which based its cause of action against
petitioner on the alleged agreement dated July 11, 2006 between the parties;
and that the same agreement contained the arbitration clause sought to be
enforced by petitioner in this case. Thus, whether petitioner assails the
genuineness and due execution of the agreement, the fact remains that the
agreement sued upon provides for an arbitration clause; that respondent
cannot use the provisions favorable to him and completely disregard those that
are unfavorable, such as the arbitration clause.
In its Reply, petitioner insists that respondent filed an action for rescission and
damages on the basis of the contract, thus, respondent admitted the existence
of all the provisions contained thereunder, including the arbitration clause;
that if respondent relies on said contract for its cause of action against
petitioner, it must also consider itself bound by the rest of the terms and
conditions contained thereunder notwithstanding that respondent may find
some provisions to be adverse to its position; that respondents citation of the
Gonzales case, decided in 2005, to show that the validity of the contract cannot
be the subject of the arbitration proceeding and that it is the RTC which has
the jurisdiction to resolve the situation between the parties herein, is not
correct since in the resolution of the Gonzales' motion for reconsideration in
2007, it had been ruled that an arbitration agreement is effective
notwithstanding the fact that one of the parties thereto repudiated the main
contract which contained it.
Section 29.
In the Gonzales case, Climax-Arimco filed before the RTC of Makati a petition
to compel arbitration under R.A. No. 876, pursuant to the arbitration clause
found in the Addendum Contract it entered with Gonzales. Judge Oscar
Pimentel of the RTC of Makati then directed the parties to arbitration
proceedings. Gonzales filed a petition for certiorari with Us contending that
Judge Pimentel acted with grave abuse of discretion in immediately ordering
the parties to proceed with arbitration despite the proper, valid and timely
raised argument in his Answer with counterclaim that the Addendum Contract
containing the arbitration clause was null and void. Climax-Arimco assailed
the mode of review availed of by Gonzales, citing Section 29 of R.A. No. 876
contending that certiorari under Rule 65 can be availed of only if there was no
appeal or any adequate remedy in the ordinary course of law; that R.A. No. 876
provides for an appeal from such order. We then ruled that Gonzales' petition
for certiorari should be dismissed as it was filed in lieu of an appeal by
certiorari which was the prescribed remedy under R.A. No. 876 and the petition
was filed far beyond the reglementary period.
We found that Gonzales petition for certiorari raises a question of law, but not a
question of jurisdiction; that Judge Pimentel acted in accordance with the
procedure prescribed in R.A. No. 876 when he ordered Gonzales to proceed
with arbitration and appointed a sole arbitrator after making the determination
that there was indeed an arbitration agreement. It had been held that as long
as a court acts within its jurisdiction and does not gravely abuse its discretion
in the exercise thereof, any supposed error committed by it will amount to
nothing more than an error of judgment reviewable by a timely appeal and not
assailable by a special civil action of certiorari.[if !supportFootnotes][14][endif]
In this case, petitioner raises before the CA the issue that the respondent
Judge acted in excess of jurisdiction or with grave abuse of discretion in
refusing to dismiss, or at least suspend, the proceedings a quo, despite the fact
that the partys agreement to arbitrate had not been complied with. Notably, the
RTC found the existence of the arbitration clause, since it said in its decision
that hardly disputed is the fact that the arbitration clause in question
contravenes several provisions of the Arbitration Law x x x and to apply Section
7 of the Arbitration Law to such an agreement would result in the disregard of
the afore-cited sections of the Arbitration Law and render them useless and
mere surplusages. However, notwithstanding the finding that an arbitration
agreement existed, the RTC denied petitioner's motion and directed petitioner
to file an answer.
Any dispute which the Buyer and Seller may not be able to settle by
mutual agreement shall be settled by arbitration in the City of
New York before the American Arbitration Association, The
Arbitration Award shall be final and binding on both parties.
The CA ruled that arbitration cannot be ordered in this case, since petitioner
alleged that the contract between the parties did not exist or was invalid and
arbitration is not proper when one of the parties repudiates the existence or
validity of the contract. Thus, said the CA:
Consequently, the petitioner herein cannot claim that the contract was
never consummated and, at the same time, invokes the
arbitration clause provided for under the contract which it
alleges to be non-existent or invalid. Petitioner claims that
private respondent's complaint lacks a cause of action due to
the absence of any valid contract between the parties.
Apparently, the arbitration clause is being invoked merely as a
fallback position. The petitioner must first adduce evidence in
support of its claim that there is no valid contract between
them and should the court a quo find the claim to be
meritorious, the parties may then be spared the rigors and
expenses that arbitration in a foreign land would surely entail.
[if !supportFootnotes][24][endif]
However, the Gonzales case,[if !supportFootnotes][25][endif] which the CA relied upon for not
ordering arbitration, had been modified upon a motion for reconsideration in
this wise:
x x x The adjudication of the petition in G.R. No. 167994 effectively
modifies part of the Decision dated 28 February 2005 in G.R. No. 161957.
Hence, we now hold that the validity of the contract containing the
agreement to submit to arbitration does not affect the applicability of the
arbitration clause itself. A contrary ruling would suggest that a party's
mere repudiation of the main contract is sufficient to avoid arbitration.
That is exactly the situation that the separability doctrine, as well as
jurisprudence applying it, seeks to avoid. We add that when it was declared
in G.R. No. 161957 that the case should not be brought for arbitration, it
should be clarified that the case referred to is the case actually filed by
Gonzales before the DENR Panel of Arbitrators, which was for the nullification
of the main contract on the ground of fraud, as it had already been determined
that the case should have been brought before the regular courts involving as it
did judicial issues.[if !supportFootnotes][26][endif]
Respondent contends that assuming that the existence of the contract and the
arbitration clause is conceded, the CA's decision declining referral of the
parties' dispute to arbitration is still correct. It claims that its complaint in the
RTC presents the issue of whether under the facts alleged, it is entitled to
rescind the contract with damages; and that issue constitutes a judicial
question or one that requires the exercise of judicial function and cannot be the
subject of an arbitration proceeding. Respondent cites our ruling in Gonzales,
wherein we held that a panel of arbitrator is bereft of jurisdiction over the
complaint for declaration of nullity/or termination of the subject contracts on
the grounds of fraud and oppression attendant to the execution of the
addendum contract and the other contracts emanating from it, and that the
complaint should have been filed with the regular courts as it involved issues
which are judicial in nature.
Such argument is misplaced and respondent cannot rely on the Gonzales case
to support its argument.
In Pearson v. Intermediate Appellate Court, this Court observed that the trend
has been to make the adjudication of mining cases a purely administrative
matter. Decisions of the Supreme Court on mining disputes have recognized a
distinction between (1) the primary powers granted by pertinent provisions of
law to the then Secretary of Agriculture and Natural Resources (and the
bureau directors) of an executive or administrative nature, such as granting of
license, permits, lease and contracts, or approving, rejecting, reinstating or
canceling applications, or deciding conflicting applications, and (2)
controversies or disagreements of civil or contractual nature between litigants
which are questions of a judicial nature that may be adjudicated only by the
courts of justice. This distinction is carried on even in Rep. Act No. 7942. [if !
supportFootnotes][28][endif]
We found that since the complaint filed before the DENR Panel of
Arbitrators charged respondents with disregarding and ignoring the addendum
contract, and acting in a fraudulent and oppressive manner against petitioner,
the complaint filed before the Panel was not a dispute involving rights to
mining areas, or was it a dispute involving claimholders or concessionaires, but
essentially judicial issues. We then said that the Panel of Arbitrators did not
have jurisdiction over such issue, since it does not involve the application of
technical knowledge and expertise relating to mining. It is in this context that
we said that:
SO ORDERED.
SECOND DIVISION
- versus -
Promulgated:
RCBC CAPITAL CORPORATION,
Respondent. December 18, 2008
x-----------------------------------------------------------------------------------------x
DECISION
The Case
This Petition for Review on Certiorari under Rule 45 seeks the reversal
of the January 8, 2008[if !supportFootnotes][2][endif] and March 17, 2008[if !supportFootnotes][3][endif]
Orders of the Regional Trial Court (RTC), Branch 148 in Makati City in SP Proc.
Case No. 6046, entitled In the Matter of ICC Arbitration Ref. No.
13290/MS/JB/JEM Between RCBC Capital Corporation, (Claimant), and
Equitable PCI Banking Corporation, Inc. et al., (Respondents). The assailed
January 8, 2008 Order confirmed the Partial Award dated September 27,
2007[if !supportFootnotes][4][endif] rendered by the International Chamber of Commerce-
International Court of Arbitration (ICC-ICA) in Case No. 13290/MS/JB/JEM,
entitled RCBC Capital Corporation (Philippines) v. Equitable PCI Bank, Inc. &
Others (Philippines). The March 17, 2008 Order denied petitioners motion for
reconsideration of the January 8, 2008 Order.
The Facts
On May 24, 2000, petitioners Equitable PCI Bank, Inc. (EPCIB) and the
individual shareholders of Bankard, Inc., as sellers, and respondent RCBC
Capital Corporation (RCBC), as buyer, executed a Share Purchase Agreement[if !
supportFootnotes][5][endif]
(SPA) for the purchase of petitioners interests in Bankard,
representing 226,460,000 shares, for the price of PhP 1,786,769,400. To
expedite the purchase, RCBC agreed to dispense with the conduct of a due
diligence audit on the financial status of Bankard.
xxxx
ii) the statements of Bankards profit and loss accounts for the fiscal
years 1996 to 1999, as prepared and certified by SGV,
and the unaudited profit and loss accounts for the first
quarter ended 31 March 2000, fairly and accurately
present the results of the operations of Bankard for
the periods indicated, and are complete in all material
respects.
where
X = ------------------------------------------- (1.925)
338,000,000
xxxx
xxxx
On December 28, 2000, RCBC paid the balance of the contract price.
The corresponding deeds of sale for the shares in question were executed in
January 2001.
Thereafter, in a letter of May 5, 2003, RCBC informed petitioners of its
having overpaid the purchase price of the subject shares, claiming that there
was an overstatement of valuation of accounts amounting to PhP 478 million,
resulting in the overpayment of over PhP 616 million. Thus, RCBC claimed that
petitioners violated their warranty, as sellers, embodied in Sec. 5(g) of the SPA
(Sec. 5[g] hereinafter).
After drawn out proceedings with each party alleging deviation and
non-compliance by the other with arbitration rules, the tribunal, with Justice
Kapunan dissenting, rendered a Partial Award dated September 27, 2007, [if !
supportFootnotes][10][endif]
the dispositive portion of which states:
The tribunal also exonerated RCBC from laches, the latter having
sought relief within the three (3)-year period prescribed in the SPA. On the
matter of estoppel suggested in petitioners answer, the tribunal stated in par.
10.27 of the Partial Award the following:
Notably, the tribunal considered the rescission of the SPA and ASPA as
impracticable and totally out of the question.[if !supportFootnotes][12][endif]
xxxx
On October 26, 2007, RCBC filed with the RTC a Motion to Confirm
Partial Award. On the same day, petitioners countered with a Motion to Vacate
the Partial Award. On November 9, 2007, petitioners again filed a Motion to
Suspend and Inhibit Barker and Kaplan.
The Issues
As earlier recited, the ICC-ICAs Partial Award dated September 27, 2007 was
confirmed by the RTC in its first assailed order of January 8, 2008. Thereafter,
the RTC, by order of March 17, 2008, denied petitioners motion for
reconsideration. Therefrom, petitioners came directly to this Court on a petition
for review under Rule 45 of the Rules of Court.
This is a procedural miscue for petitioners who erroneously bypassed the Court
of Appeals (CA) in pursuit of its appeal. While this procedural gaffe has not
been raised by RCBC, still we would be remiss in not pointing out the proper
mode of appeal from a decision of the RTC confirming, vacating, setting aside,
modifying, or correcting an arbitral award.
Rule 45 is not the remedy available to petitioners as the proper mode of appeal
assailing the decision of the RTC confirming as arbitral award is an appeal
before the CA pursuant to Sec. 46 of Republic Act No. (RA) 9285, otherwise
known as the Alternative Dispute Resolution Act of 2004, or completely, An Act
to Institutionalize the Use of an Alternative Dispute Resolution System in the
Philippines and to Establish the Office for Alternative Dispute Resolution, and for
other Purposes, promulgated on April 2, 2004 and became effective on April 28,
2004 after its publication on April 13, 2004.
In Korea Technologies Co., Ltd v. Lerma, we explained, inter alia, that the RTC
decision of an assailed arbitral award is appealable to the CA and may further
be appealed to this Court, thus:
The losing party who appeals from the judgment of the court
confirming an arbitral award shall be required by the appellate
court to post a counterbond executed in favor of the prevailing
party equal to the amount of the award in accordance with the
rules to be promulgated by the Supreme Court.
It is clear from the factual antecedents that RA 9285 applies to the instant
case. This law was already effective at the time the arbitral proceedings were
commenced by RCBC through a request for arbitration filed before the ICC-ICA
on May 12, 2004. Besides, the assailed confirmation order of the RTC was
issued on March 17, 2008. Thus, petitioners clearly took the wrong mode of
appeal and the instant petition can be outright rejected and dismissed.
As a rule, the award of an arbitrator cannot be set aside for mere errors of
judgment either as to the law or as to the facts. Courts are without power
to amend or overrule merely because of disagreement with matters of law
or facts determined by the arbitrators. They will not review the findings of
law and fact contained in an award, and will not undertake to substitute
their judgment for that of the arbitrators, since any other rule would
make an award the commencement, not the end, of litigation. Errors of
law and fact, or an erroneous decision of matters submitted to the
judgment of the arbitrators, are insufficient to invalidate an award fairly
and honestly made. Judicial review of an arbitration is, thus, more limited
than judicial review of a trial.
xxxx
The instant petition dwells on the alleged manifest disregard of the law
by the ICC-ICA.
The US case of Merrill Lynch, Pierce, Fenner & Smith, Inc. v. Jaros [if !
supportFootnotes][18][endif]
expounded on the phrase manifest disregard of the law in the
following wise:
On the other hand, the remedy under Sec. 5(g) in conjunction with
Sec. 7 can include specific performance, damages, and other reliefs excluding
price reduction.
(2) Sec. 5(g) warranty covers the audited financial statements (AFS)
for the three (3) years ending December 31, 1997 to 1999 and the unaudited
financial statements (UFS) for the first quarter ending March 31, 2000. On the
other hand, the Sec. 5(h) warranty refers only to the AFS for the year ending
December 31, 1999 and the UFS up to May 31, 2000. It is undenied that Sec.
5(h) refers to price reduction as it covers only the most up-to-date audited and
unaudited financial statements upon which the price must have been based. [if !
supportFootnotes][19][endif]
(3) Under Sec. 5(h), the responsibility of petitioners for its warranty
shall exclude the disclosures and reservations made in AFS of Bankard as of
December 31, 1999 and its UFS up to May 31, 2000. No such exclusions were
made under Sec. 5(g) with respect to the warranty of petitioners in the AFS and
UFS of Bankard.
(4) Sec. 5(h) gives relief only if there is material adverse effect in the
net worth in excess of PhP 100 million and it provides a formula for price
reduction.[if !supportFootnotes][20][endif] On the other hand, Sec. 5(g) can be the basis for
remedies like specific performance, damages, and other reliefs, except price
reduction, even if the overvaluation is less or above PhP 100 million and there
is no formula for computation of damages.
(5) Under Sec. 7, the aggrieved party shall present its written demand
to the defaulting party within three (3) years from closing date. Under Sec. 5(h),
the written demand shall be presented within six (6) months from closing date.
In accordance with par. 2(c) of the ASPA, the deadline to file the demand under
Sec. 5(h) was extended to December 31, 2000.
From the above determination, it becomes clear that the aggrieved party is
entitled to two (2) separate alternative remedies under Secs. 5 and 7 of the SPA,
thus:
1. A claim for price reduction under Sec. 5(h) and/or damages based on the
breach of warranty by Bankard on the absence of liabilities, omissions and
mistakes on the financial statements as of 31 December 1999 and the UFS as
of 31 May 2000, provided that the material adverse effect on the net worth
exceeds PhP 100M and the written demand is presented within six (6) months
from closing date (extended to 31 December 2000); and
Has RCBC the option to choose between Sec. 5(g) or Sec. 5(h)?
The answer is yes. Sec. 5 and Sec. 7 are clear that it is discretionary on the
aggrieved parties to avail themselves of any remedy mentioned above. They may
choose one and dispense with the other. Of course, the relief for price reduction
under Sec. 5(h) will have to conform to the prerequisites and time frame of six
(6) months; otherwise, it is waived.
Preliminarily, petitioners basic posture that RCBCs claim is for the recovery of
overpayment is specious. The records show that in its Request for Arbitration
dated May 12, 2004, RCBC prayed for the rescission of the SPA, restitution of
the whole purchase price, and damages not for reduction of price or for the
return of any overpayment. Even in its May 5, 2000 letter, [if !supportFootnotes][21][endif]
RCBC did not ask for the recovery of any overpayment or reduction of price,
merely stating in it that the accounts of Bankard, as reflected in its AFS for
1999, were overstated which, necessarily, resulted in an overpayment situation.
RCBC was emphatic and unequivocal that petitioners violated their warranty
covered by Sec. 5(g) of the SPA.
It is thus evident that RCBC did not avail itself of the option under Sec. 5(h),
i.e., for price reduction or the return of any overpayment arising from the
overvaluation of Bankards financial condition. Clearly, RCBC invoked Sec. 5(g)
to claim damages from petitioners which is one of the alternative reliefs granted
under Sec. 7 in addition to rescission and restitution of purchase price.
Petitioners do not deny that RCBC formally filed its claim under Sec. 5(g) which
is anchored on the material overstatement or overvaluation of Bankards
revenues, assets, and net worth and, hence, the overstatement of the purchase
price. They, however, assert that such claim for overpayment is actually a claim
under Sec. 5(h) of the SPA for price reduction which it forfeited after December
31, 2000.
A scrutiny of Sec. 5(g) and Sec. 5(h) in relation to Sec. 7 of the SPA
would indicate the following remedies available to RCBC should it be
discovered, as of closing date, that there is overvaluation which will constitute
breach of the warranty clause under either Sec. 5(g) or (h), to wit:
Moreover, the language employed in Sec. 5(g) and Sec. 5(h) is clear and
bereft of any ambiguity. The SPAs stipulations reveal that the non-use or waiver
of Sec. 5(h) does not preclude RCBC from availing itself of the second relief
under Sec. 5(g). Article 1370 of the Civil Code is explicit that if terms of a
contract are clear and leave no doubt upon the intention of the contracting
parties the literal meaning of its stipulations shall control. Since the terms of a
contract have the force of law between the parties, [if !supportFootnotes][22][endif] then the
parties must respect and strictly conform to it. Lastly, it is a long held cardinal
rule that when the terms of an agreement are reduced to writing, it is deemed
to contain all the terms agreed upon and no evidence of such terms can be
admitted other than the contents of the agreement itself. [if !supportFootnotes][23][endif]
Since the SPA is unambiguous, and petitioners failed to adduce evidence to the
contrary, then they are legally bound to comply with it.
The Court sustains the finding in the Partial Award that Sec. 5(g) of the
SPA is a free standing warranty and not constricted by Sec. 5(h) of the said
agreement.
Upon the foregoing premises and in the light of the undisputed facts on
record, RCBCs claim for rescission of the SPA and damages due to
overvaluation of Bankards accounts was properly for a breach of the warranty
under Sec. 5(g) and was not time-barred. To repeat, RCBC presented its written
claim on May 5, 2003, or a little less than a month before closing date, well
within the three (3)-year prescriptive period provided under Sec. 7 for the
exercise of the right provided under Sec. 5(g).
Petitioners bemoan the fact that the arbitrators liability award (a)
disregarded the 6-month contractual limitation for RCBCs overprice claim,
and [b] substituted in its place the 3-year limitation under the contract for
other claims,[if !supportFootnotes][25][endif] adopting in that regard the interpretation of
the SPA made by arbitral tribunal member, retired Justice Kapunan, in his
Dissenting Opinion, in which he asserted:
xxxx
xxxx
The Claim is for recovery of the excess price by way of actual damages.[if !
supportFootnotes][27][endif]
x x x (Emphasis supplied.)
Justice Kapunan noted that without Sec. 5(h), RCBCs claim would fall
under Sec. 5(g), impliedly admitting that both provisions could very well cover
RCBCs claim, except that Sec. 5(h) excludes the situation contemplated in it
from the general terms of Sec. 5(g).
More importantly, a scrutiny of the four corners of the SPA does not
explicitly reveal any stipulation nor even impliedly that the parties intended to
limit the scope of the warranty in Sec. 5(g) or gave priority to Sec. 5(h) over Sec.
5(g).
The arbitral tribunal did not find any legal basis in the SPA that Sec.
5(h) somehow cuts down the scope of Sec. 5(g), thus:
The Court upholds the conclusion of the tribunal and rules that the
claim of RCBC under Sec. 5(g) is not time-barred.
On May 17, 2004, the ICC-ICA received the Request for Arbitration
dated May 12, 2004 from RCBC seeking rescission of the SPA and restitution of
all the amounts paid by RCBC to petitioners, with actual and moral damages,
interest, and costs of suit.
Then, the tribunal issued Procedural Order No. 1 dated January 12,
[if !supportFootnotes][38][endif]
2005, denying the motion to dismiss and setting the initial
hearing of the case on April 11, 2005.
On March 23, 2005, RCBC paid the balance of the advance on costs. [if !
supportFootnotes][48][endif]
On April 22, 2005, petitioners sent the tribunal a letter, [if !supportFootnotes][49]
[endif]
requesting for the postponement of the hearing scheduled on June 13 to
16, 2005 on the ground that they could not submit their witness statements
due to the volume of data that they acquired from RCBC.
On July 29, 2005, the parties held a meeting wherein it was agreed
that petitioners would be provided with hard and soft copies of the inventory of
the journal vouchers earlier presented to its representatives, while making the
journal vouchers available to petitioners for two weeks for examination and
photocopying.[if !supportFootnotes][53][endif]
On October 21, 2005, the tribunal issued Procedural Order No. 6, [if !
supportFootnotes][56][endif]
postponing the November 21, 2005 hearing by virtue of an
order issued by the RTC in Makati City directing the tribunal to reset the
hearing for April 21 and 24, 2006.
Later, petitioners sent to the tribunal a letter dated February 10, 2006,
[if !supportFootnotes][59][endif]
asking that it direct RCBC to provide petitioners with the
supporting documents that RCBC mentioned in its letter dated January 31,
2006. Petitioners wrote that should RCBC fail to present such documents,
RCBCs summaries should be excluded from the records.
Thus, on September 27, 2007, the Partial Award was rendered by the
Tribunal.
Later, petitioners moved to vacate the said award before the RTC. Such
motion was denied by the trial court in the first assailed order dated January
8, 2008. Petitioners then moved for a reconsideration of such order, but their
motion was also denied in the second assailed order dated March 17, 2008.
The doctrine of estoppel is based upon the grounds of public policy, fair
dealing, good faith, and justice; and its purpose is to forbid one to speak
against ones own acts, representations, or commitments to the injury of one to
whom they were directed and who reasonably relied on them.[if !supportFootnotes][72][endif]
It must be emphasized that it was only after a second audit that RCBC
presented its claim to petitioners for violation of Sec. 5(g), within the three (3)-
year period prescribed. In other words, RCBC, prior to such second audit, did
not have full and thorough knowledge of the correctness of Bankards accounts,
in relation to Sec. 5(g). RCBC, therefore, could not have misrepresented itself
considering that it was still in the process of verifying the warranties covered
under Sec. 5(g). Considering that there must be a concurrence of the elements
of estoppel for it to arise, on this ground alone such claim is already negated.
As will be shown, however, all the other elements of estoppel are likewise
absent in the case at bar.
The element that petitioners relied on the acts and conduct of RCBC is
absent. The Court finds that there was no reliance on the part of petitioners on
the acts of RCBC that would lead them to believe that the RCBC will forego the
filing of a claim under Sec. 5(g). The allegation that RCBC knew that the
Bankard accounts did not comply with generally accepted accounting
principles before payment and, hence, it cannot question the financial
statements of Bankard is meritless. Precisely, the SPA explicitly provides that
claims for violation of the warranties under Sec. 5(g) can still be filed within
three (3) years from the closing date. Petitioners contention that RCBC had full
control of Bankard operations after payment of the price and that an audit
undertaken by the Rubio team did not find anything wrong with the accounts
could not have plausibly misled petitioners into believing that RCBC will waive
its right to file a claim under Sec. 5(g). After all, the period to file a claim under
Sec. 5(g) is three (3) years under Sec. 7, much longer than the six (6)-month
period under Sec. 5(h). Petitioners are fully aware that the warranties under
Sec. 5(g) (1997 up to March 2000) are of a wider scope than that of Sec. 5(h)
(AFS of 1999 and UFS up to May 31, 2000), necessitating a longer audit period
than the six (6)-month period under Sec. 5(h).
10.18 The audit exercise conducted by Mr. Legaspi and Mr. Rubio was
clearly not one comprehensive enough to have
discovered the problems later unearthed by Dr. Laya
and Dean Ledesma. x x x
10.20 But neither the Claimant nor the TC did anything, in the
Tribunals view, which would have given the
Respondents the impression that they were being
relieved over the next three years of susceptibility to a
claim under clause 5(g). Maybe the TC could have been
more proactive in commissioning further or more in-
depth audits but it was not. It did not have to be. It is
commercially unlikely that it have been done so, with
the necessary degree of attention to detail, within the
relatively short time between the appointment of the
TC and the ultimate settlement date of the purchase a
period of some three months. An interim arrangement
was obviously sensible to enable the Claimant and its
staff to become familiar with the practices and
procedures of Bankard.
xxxx
10.42 The Tribunal is not the appropriate forum for deciding whether
there have been any regulatory or ethical infractions
by Bankard and/or the Claimant in setting the buy-
back price. It has no bearing on whether the Claimant
must be considered as having waived its right to claim
against the Respondents.
10.45 Whatever the status of Mr. Rubios and Mr. Legaspis enquiries in
late 2000, the Claimant was quite entitled to
commission subsequent reports from Dr. Laya and Dr.
Echanis and, on the basis of those reports, make a
timeous claim under clause 5(g) of the SPA.
It becomes evident from all of the foregoing findings that the ICC-ICA is
not guilty of any manifest disregard of the law on estoppel. As shown above, the
findings of the ICC-ICA in the Partial Award are well-supported in law and
grounded on facts. The Partial Award must be upheld.
SO ORDERED.
DECISION
TINGA, J.:
Subject of this case is the letter of credit which has evolved as the ubiquitous
and most important device in international trade. A creation of commerce and
businessmen, the letter of credit is also unique in the number of parties
involved and its supranational character.
Petitioner has appealed from the Decision1 of the Court of Appeals in CA-G.R.
SP No. 61901 entitled "Transfield Philippines, Inc. v. Hon. Oscar Pimentel, et
al.," promulgated on 31 January 2001.2
The Turnkey Contract provides that: (1) the target completion date of the
Project shall be on 1 June 2000, or such later date as may be agreed upon
between petitioner and respondent LHC or otherwise determined in accordance
with the Turnkey Contract; and (2) petitioner is entitled to claim extensions of
time (EOT) for reasons enumerated in the Turnkey Contract, among which are
variations, force majeure, and delays caused by LHC itself.5 Further, in case of
dispute, the parties are bound to settle their differences through mediation,
conciliation and such other means enumerated under Clause 20.3 of the
Turnkey Contract.6
In the course of the construction of the project, petitioner sought various EOT
to complete the Project. The extensions were requested allegedly due to several
factors which prevented the completion of the Project on target date, such as
force majeure occasioned by typhoon Zeb, barricades and demonstrations. LHC
denied the requests, however. This gave rise to a series of legal actions between
the parties which culminated in the instant petition.
The first of the actions was a Request for Arbitration which LHC filed before the
Construction Industry Arbitration Commission (CIAC) on 1 June 1999.10 This
was followed by another Request for Arbitration, this time filed by petitioner
before the International Chamber of Commerce (ICC)11 on 3 November 2000.
In both arbitration proceedings, the common issues presented were: [1)
whether typhoon Zeb and any of its associated events constituted force majeure
to justify the extension of time sought by petitioner; and [2) whether LHC had
the right to terminate the Turnkey Contract for failure of petitioner to complete
the Project on target date.
Meanwhile, foreseeing that LHC would call on the Securities pursuant to the
pertinent provisions of the Turnkey Contract,12 petitionerin two separate
letters13 both dated 10 August 2000advised respondent banks of the
arbitration proceedings already pending before the CIAC and ICC in connection
with its alleged default in the performance of its obligations. Asserting that
LHC had no right to call on the Securities until the resolution of disputes
before the arbitral tribunals, petitioner warned respondent banks that any
transfer, release, or disposition of the Securities in favor of LHC or any person
claiming under LHC would constrain it to hold respondent banks liable for
liquidated damages.
Dissatisfied with the trial court's denial of its application for a writ of
preliminary injunction, petitioner elevated the case to the Court of Appeals via
a Petition for Certiorari under Rule 65, with prayer for the issuance of a
temporary restraining order and writ of preliminary injunction.20 Petitioner
submitted to the appellate court that LHC's call on the Securities was
premature considering that the issue of its default had not yet been resolved
with finality by the CIAC and/or the ICC. It asserted that until the fact of delay
could be established, LHC had no right to draw on the Securities for liquidated
damages.
However, the appellate court failed to act on the application for preliminary
injunction until the temporary restraining order expired on 27 January 2001.
Immediately thereafter, representatives of LHC trooped to ANZ Bank and
withdrew the total amount of US$4,950,000.00, thereby reducing the balance
in ANZ Bank to US$1,852,814.00.
On 2 February 2001, the appellate court dismissed the petition for certiorari.
The appellate court expressed conformity with the trial court's decision that
LHC could call on the Securities pursuant to the first principle in credit law
that the credit itself is independent of the underlying transaction and that as
long as the beneficiary complied with the credit, it was of no moment that he
had not complied with the underlying contract. Further, the appellate court
held that even assuming that the trial court's denial of petitioner's application
for a writ of preliminary injunction was erroneous, it constituted only an error
of judgment which is not correctible by certiorari, unlike error of jurisdiction.
Undaunted, petitioner filed the instant Petition for Review raising the following
issues for resolution:
WHETHER LHC HAS THE RIGHT TO CALL AND DRAW ON THE SECURITIES
BEFORE THE RESOLUTION OF PETITIONER'S AND LHC'S DISPUTES BY THE
APPROPRIATE TRIBUNAL.
A. LHC IS ALLOWED TO CALL AND DRAW ON, AND ANZ BANK AND
SECURITY BANK ARE ALLOWED TO RELEASE, THE REMAINING BALANCE
OF THE SECURITIES PRIOR TO THE RESOLUTION OF THE DISPUTES
BETWEEN PETITIONER AND LHC.
Petitioner asserts that LHC should be ordered to return the proceeds of the
Securities pursuant to the principle against unjust enrichment and that, under
the premises, injunction was the appropriate remedy obtainable from the
competent local courts.
On 25 August 2003, petitioner filed a Supplement to the Petition22 and
Supplemental Memorandum,23 alleging that in the course of the proceedings
in the ICC Arbitration, a number of documentary and testimonial evidence
came out through the use of different modes of discovery available in the ICC
Arbitration. It contends that after the filing of the petition facts and admissions
were discovered which demonstrate that LHC knowingly misrepresented that
petitioner had incurred delays notwithstanding its knowledge and admission
that delays were excused under the Turnkey Contractto be able to draw
against the Securities. Reiterating that fraud constitutes an exception to the
independence principle, petitioner urges that this warrants a ruling from this
Court that the call on the Securities was wrongful, as well as contrary to law
and basic principles of equity. It avers that it would suffer grave irreparable
damage if LHC would be allowed to use the proceeds of the Securities and not
ordered to return the amounts it had wrongfully drawn thereon.
The letter of credit evolved as a mercantile specialty, and the only way to
understand all its facets is to recognize that it is an entity unto itself. The
relationship between the beneficiary and the issuer of a letter of credit is not
strictly contractual, because both privity and a meeting of the minds are
lacking, yet strict compliance with its terms is an enforceable right. Nor is it a
third-party beneficiary contract, because the issuer must honor drafts drawn
against a letter regardless of problems subsequently arising in the underlying
contract. Since the bank's customer cannot draw on the letter, it does not
function as an assignment by the customer to the beneficiary. Nor, if properly
used, is it a contract of suretyship or guarantee, because it entails a primary
liability following a default. Finally, it is not in itself a negotiable instrument,
because it is not payable to order or bearer and is generally conditional, yet the
draft presented under it is often negotiable.29
Article 3 of the UCP provides that credits, by their nature, are separate
transactions from the sales or other contract(s) on which they may be based
and banks are in no way concerned with or bound by such contract(s), even if
any reference whatsoever to such contract(s) is included in the credit.
Consequently, the undertaking of a bank to pay, accept and pay draft(s) or
negotiate and/or fulfill any other obligation under the credit is not subject to
claims or defenses by the applicant resulting from his relationships with the
issuing bank or the beneficiary. A beneficiary can in no case avail himself of
the contractual relationships existing between the banks or between the
applicant and the issuing bank.
Thus, the engagement of the issuing bank is to pay the seller or beneficiary of
the credit once the draft and the required documents are presented to it. The
so-called "independence principle" assures the seller or the beneficiary of
prompt payment independent of any breach of the main contract and precludes
the issuing bank from determining whether the main contract is actually
accomplished or not. Under this principle, banks assume no liability or
responsibility for the form, sufficiency, accuracy, genuineness, falsification or
legal effect of any documents, or for the general and/or particular conditions
stipulated in the documents or superimposed thereon, nor do they assume any
liability or responsibility for the description, quantity, weight, quality, condition,
packing, delivery, value or existence of the goods represented by any
documents, or for the good faith or acts and/or omissions, solvency,
performance or standing of the consignor, the carriers, or the insurers of the
goods, or any other person whomsoever.39
The independent nature of the letter of credit may be: (a) independence in toto
where the credit is independent from the justification aspect and is a separate
obligation from the underlying agreement like for instance a typical standby; or
(b) independence may be only as to the justification aspect like in a commercial
letter of credit or repayment standby, which is identical with the same
obligations under the underlying agreement. In both cases the payment may be
enjoined if in the light of the purpose of the credit the payment of the credit
would constitute fraudulent abuse of the credit.40
Petitioner insists that the independence principle does not apply to the instant
case and assuming it is so, it is a defense available only to respondent banks.
LHC, on the other hand, contends that it would be contrary to common sense
to deny the benefit of an independent contract to the very party for whom the
benefit is intended. As beneficiary of the letter of credit, LHC asserts it is
entitled to invoke the principle.
Letters of credit are employed by the parties desiring to enter into commercial
transactions, not for the benefit of the issuing bank but mainly for the benefit
of the parties to the original transactions. With the letter of credit from the
issuing bank, the party who applied for and obtained it may confidently
present the letter of credit to the beneficiary as a security to convince the
beneficiary to enter into the business transaction. On the other hand, the other
party to the business transaction, i.e., the beneficiary of the letter of credit, can
be rest assured of being empowered to call on the letter of credit as a security
in case the commercial transaction does not push through, or the applicant
fails to perform his part of the transaction. It is for this reason that the party
who is entitled to the proceeds of the letter of credit is appropriately called
"beneficiary."
Petitioner's argument that any dispute must first be resolved by the parties,
whether through negotiations or arbitration, before the beneficiary is entitled to
call on the letter of credit in essence would convert the letter of credit into a
mere guarantee. Jurisprudence has laid down a clear distinction between a
letter of credit and a guarantee in that the settlement of a dispute between the
parties is not a pre-requisite for the release of funds under a letter of credit. In
other words, the argument is incompatible with the very nature of the letter of
credit. If a letter of credit is drawable only after settlement of the dispute on the
contract entered into by the applicant and the beneficiary, there would be no
practical and beneficial use for letters of credit in commercial transactions.
Professor John F. Dolan, the noted authority on letters of credit, sheds more
light on the issue:
The standby credit is an attractive commercial device for many of the same
reasons that commercial credits are attractive. Essentially, these credits are
inexpensive and efficient. Often they replace surety contracts, which tend to
generate higher costs than credits do and are usually triggered by a factual
determination rather than by the examination of documents.
Because parties and courts should not confuse the different functions of the
surety contract on the one hand and the standby credit on the other, the
distinction between surety contracts and credits merits some reflection. The
two commercial devices share a common purpose. Both ensure against the
obligor's nonperformance. They function, however, in distinctly different ways.
Traditionally, upon the obligor's default, the surety undertakes to complete the
obligor's performance, usually by hiring someone to complete that
performance. Surety contracts, then, often involve costs of determining whether
the obligor defaulted (a matter over which the surety and the beneficiary often
litigate) plus the cost of performance. The benefit of the surety contract to the
beneficiary is obvious. He knows that the surety, often an insurance company,
is a strong financial institution that will perform if the obligor does not. The
beneficiary also should understand that such performance must await the
sometimes lengthy and costly determination that the obligor has defaulted. In
addition, the surety's performance takes time.
The standby credit has different expectations. He reasonably expects that he
will receive cash in the event of nonperformance, that he will receive it
promptly, and that he will receive it before any litigation with the obligor (the
applicant) over the nature of the applicant's performance takes place. The
standby credit has this opposite effect of the surety contract: it reverses the
financial burden of parties during litigation.
In the standby credit case, however, the beneficiary avoids that litigation
burden and receives his money promptly upon presentation of the required
documents. It may be that the applicant has, in fact, performed and that the
beneficiary's presentation of those documents is not rightful. In that case, the
applicant may sue the beneficiary in tort, in contract, or in breach of warranty;
but, during the litigation to determine whether the applicant has in fact
breached the obligation to perform, the beneficiary, not the applicant, holds the
money. Parties that use a standby credit and courts construing such a credit
should understand this allocation of burdens. There is a tendency in some
quarters to overlook this distinction between surety contracts and standby
credits and to reallocate burdens by permitting the obligor or the issuer to
litigate the performance question before payment to the beneficiary.42
While it is the bank which is bound to honor the credit, it is the beneficiary
who has the right to ask the bank to honor the credit by allowing him to draw
thereon. The situation itself emasculates petitioner's posture that LHC cannot
invoke the independence principle and highlights its puerility, more so in this
case where the banks concerned were impleaded as parties by petitioner itself.
Furthermore, LHC has a right rooted in the Contract to call on the Securities.
The relevant provisions of the Contract read, thus:
4.2.1. In order to secure the performance of its obligations under this Contract,
the Contractor at its cost shall on the Commencement Date provide security to
the Employer in the form of two irrevocable and confirmed standby letters of
credit (the "Securities"), each in the amount of US$8,988,907, issued and
confirmed by banks or financial institutions acceptable to the Employer. Each
of the Securities must be in form and substance acceptable to the Employer
and may be provided on an annually renewable basis.44
8.7.1 If the Contractor fails to comply with Clause 8.2, the Contractor shall pay
to the Employer by way of liquidated damages ("Liquidated Damages for Delay")
the amount of US$75,000 for each and every day or part of a day that shall
elapse between the Target Completion Date and the Completion Date, provided
that Liquidated Damages for Delay payable by the Contractor shall in the
aggregate not exceed 20% of the Contract Price. The Contractor shall pay
Liquidated Damages for Delay for each day of the delay on the following day
without need of demand from the Employer.
8.7.2 The Employer may, without prejudice to any other method of recovery,
deduct the amount of such damages from any monies due, or to become due to
the Contractor and/or by drawing on the Security."45
A contract once perfected, binds the parties not only to the fulfillment of what
has been expressly stipulated but also to all the consequences which according
to their nature, may be in keeping with good faith, usage, and law.46 A careful
perusal of the Turnkey Contract reveals the intention of the parties to make the
Securities answerable for the liquidated damages occasioned by any delay on
the part of petitioner. The call upon the Securities, while not an exclusive
remedy on the part of LHC, is certainly an alternative recourse available to it
upon the happening of the contingency for which the Securities have been
proffered. Thus, even without the use of the "independence principle," the
Turnkey Contract itself bestows upon LHC the right to call on the Securities in
the event of default.
Next, petitioner invokes the "fraud exception" principle. It avers that LHC's call
on the Securities is wrongful because it fraudulently misrepresented to ANZ
Bank and SBC that there is already a breach in the Turnkey Contract knowing
fully well that this is yet to be determined by the arbitral tribunals. It asserts
that the "fraud exception" exists when the beneficiary, for the purpose of
drawing on the credit, fraudulently presents to the confirming bank,
documents that contain, expressly or by implication, material representations
of fact that to his knowledge are untrue. In such a situation, petitioner insists,
injunction is recognized as a remedy available to it.
It is worthy of note that the propriety of LHC's call on the Securities is largely
intertwined with the fact of default which is the self-same issue pending
resolution before the arbitral tribunals. To be able to declare the call on the
Securities wrongful or fraudulent, it is imperative to resolve, among others,
whether petitioner was in fact guilty of delay in the performance of its
obligation. Unfortunately for petitioner, this Court is not called upon to rule
upon the issue of defaultsuch issue having been submitted by the parties to
the jurisdiction of the arbitral tribunals pursuant to the terms embodied in
their agreement.47
Would injunction then be the proper remedy to restrain the alleged wrongful
draws on the Securities?
In its complaint for injunction before the trial court, petitioner alleged that it is
entitled to a total extension of two hundred fifty-three (253) days which would
move the target completion date. It argued that if its claims for extension would
be found meritorious by the ICC, then LHC would not be entitled to any
liquidated damages.50
In the instant case, petitioner failed to show that it has a clear and
unmistakable right to restrain LHC's call on the Securities which would justify
the issuance of preliminary injunction. By petitioner's own admission, the right
of LHC to call on the Securities was contractually rooted and subject to the
express stipulations in the Turnkey Contract.55 Indeed, the Turnkey Contract
is plain and unequivocal in that it conferred upon LHC the right to draw upon
the Securities in case of default, as provided in Clause 4.2.5, in relation to
Clause 8.7.2, thus:
4.2.5 The Employer shall give the Contractor seven days' notice of calling upon
any of the Securities, stating the nature of the default for which the claim on
any of the Securities is to be made, provided that no notice will be required if
the Employer calls upon any of the Securities for the payment of Liquidated
Damages for Delay or for failure by the Contractor to renew or extend the
Securities within 14 days of their expiration in accordance with Clause
4.2.2.56
8.7.2 The Employer may, without prejudice to any other method of recovery,
deduct the amount of such damages from any monies due, or to become due,
to the Contractor and/or by drawing on the Security.57
The pendency of the arbitration proceedings would not per se make LHC's
draws on the Securities wrongful or fraudulent for there was nothing in the
Contract which would indicate that the parties intended that all disputes
regarding delay should first be settled through arbitration before LHC would be
allowed to call upon the Securities. It is therefore premature and absurd to
conclude that the draws on the Securities were outright fraudulent given the
fact that the ICC and CIAC have not ruled with finality on the existence of
default.
Nowhere in its complaint before the trial court or in its pleadings filed before
the appellate court, did petitioner invoke the fraud exception rule as a ground
to justify the issuance of an injunction.58 What petitioner did assert before the
courts below was the fact that LHC's draws on the Securities would be
premature and without basis in view of the pending disputes between them.
Petitioner should not be allowed in this instance to bring into play the fraud
exception rule to sustain its claim for the issuance of an injunctive relief.
Matters, theories or arguments not brought out in the proceedings below will
ordinarily not be considered by a reviewing court as they cannot be raised for
the first time on appeal.59 The lower courts could thus not be faulted for not
applying the fraud exception rule not only because the existence of fraud was
fundamentally interwoven with the issue of default still pending before the
arbitral tribunals, but more so, because petitioner never raised it as an issue in
its pleadings filed in the courts below. At any rate, petitioner utterly failed to
show that it had a clear and unmistakable right to prevent LHC's call upon the
Securities.
With respect to the issue of whether the respondent banks were justified in
releasing the amounts due under the Securities, this Court reiterates that
pursuant to the independence principle the banks were under no obligation to
determine the veracity of LHC's certification that default has occurred. Neither
were they bound by petitioner's declaration that LHC's call thereon was
wrongful. To repeat, respondent banks' undertaking was simply to pay once the
required documents are presented by the beneficiary.
Settled is the rule that injunction would not lie where the acts sought to be
enjoined have already become fait accompli or an accomplished or
consummated act.63 In Ticzon v. Video Post Manila, Inc.64 this Court ruled
that where the period within which the former employees were prohibited from
engaging in or working for an enterprise that competed with their former
employerthe very purpose of the preliminary injunction has expired, any
declaration upholding the propriety of the writ would be entirely useless as
there would be no actual case or controversy between the parties insofar as the
preliminary injunction is concerned.
In the instant case, the consummation of the act sought to be restrained had
rendered the instant petition mootfor any declaration by this Court as to
propriety or impropriety of the non-issuance of injunctive relief could have no
practical effect on the existing controversy.65 The other issues raised by
petitioner particularly with respect to its right to recover the amounts
wrongfully drawn on the Securities, according to it, could properly be threshed
out in a separate proceeding.
One final point. LHC has charged petitioner of forum-shopping. It raised the
charge on two occasions. First, in its Counter-Manifestation dated 29 June
200466 LHC alleges that petitioner presented before this Court the same claim
for money which it has filed in two other proceedings, to wit: ICC Case No.
11264/TE/MW and Civil Case No. 04-332 before the RTC of Makati. LHC
argues that petitioner's acts constitutes forum-shopping which should be
punished by the dismissal of the claim in both forums. Second, in its Comment
to Petitioner's Motion for Leave to File Addendum to Petitioner's Memorandum
dated 8 October 2004, LHC alleges that by maintaining the present appeal and
at the same time pursuing Civil Case No. 04-332wherein petitioner pressed
for judgment on the issue of whether the funds LHC drew on the Securities
should be returnedpetitioner resorted to forum-shopping. In both instances,
however, petitioner has apparently opted not to respond to the charge.
SO ORDERED.