BuildingPermitRequirements,Fees,

ApplicationFormsandProcedure
ByFehl Dungo294 Comments

How to get building permit in the Philippines? Im sharing you here the requirements, fees, and
application procedure for the issuance of building permit in the country.

Whydo you need a building permit?


It is simply in compliance with the proper construction of a house or a building following the
requirements set by law or theNational Building Code. Of course you want to make sure all the
proper technical, mechanical, electrical, and structural plans for the construction of the building are
met.

In addition, if you build a house or a building without a permit from your municipality, construction
will be stopped until a permit has been issued or released. Youll receive a strict notice to apply for
a permit.

Building Permit Requirements in the Philippines


1. Properly lled-up application forms duly signed and sealed by engineers concerned:

Building Permit Forms (5 copies)


Electrical Permit Forms (3 copies)
Sanitary Permit Forms (3 copies)

2. Five (5) complete sets of Detailed Plans


3. For construction of two-storey building:

Structural Design Analysis signed and sealed by Civil Engineer at every page

4. For construction of more than two-storey building:

Boring and Plate Load Test


Seismic Analysis

5. Proof of Property

Photocopy of Transfer Certicate if Title (TCT)


Photocopy of tax Declaration of Property-lot (Certied True Copy) 5 copies
Photocopy of Current Tax Receipt (5 copies)

6. If property is not registered under the name of the applicant:

Submit 5 copies of any of the following:


Contract of Lease
Contract of Sale
Afdavit of Consent of the Lot Owner for the construction of building/house
Deed of Absolute Sale

7. Permit Billboard (0.60 X 0.90 Plywood with the following contents):


8. Bill of Materials and Specication (5 copies) signed and sealed by an engineer or an
architect at every page
9. Locational Clearance
10. Photocopy of PTR # and PRC license of all concerned engineers and architects
11. Clearance from the DPWH if the construction is located along National Highway
12. DOLE Clearance

Those are the usual application forms you need gather and prepare.

How to get Building Permit in the Philippines


Procedures
1. Get a Requirements-Checklist and application forms from your municipals ofce(Ofce of the
Building Ofcial). Your architect mostly knows them but you need to get the documents from
your municipals ofce since every form bears the municipals seal. Your architect and engineers
then will be the ones who will ll them up.

2. Go to theOfce of the Building Ofcialand submit the papers. They will tell you then where
to go next, in this caseAssessors Ofce. If youre in the city hall, they usually have windows
where you have to submit each folder of each set of forms. But in the provinces, each section are
usually close to each other if not on the same unit.

3. You will be issuedAcknowledgement Slipwhich bears the date of the status of your
application. Its usually around10 working days.

If your application is approved and in compliant with the National Building Code, youll be given
anOrder of Paymentto pay the necessary building permit fees.

4. Present theOrder of Paymentat theTreasurers Ofceand pay the fees. Fees range from
P6,000 and above depending on the your construction size, municipality location and the
assessment plan. Fees in the provinces are usually cheaper than in the cities.

5. Photocopy the OR(Ofcial Receipt)and bring a copy to theOfce of the Building


Ofcialreleasing section.

6. After5 working days, go back to the releasing section of theOfce of the Building
Ofcialand claim your building permit.