Professional Documents
Culture Documents
www.elsevier.com/locate/ress
Abstract
This paper describes an application of the Analytic Hierarchy Process (AHP) for selecting the best maintenance strategy for an important
Italian oil refinery (an Integrated Gasification and Combined Cycle plant). Five possible alternatives are considered: preventive, predictive,
condition-based, corrective and opportunistic maintenance. The best maintenance policy must be selected for each facility of the plant (about
200 in total). The machines are clustered in three homogeneous groups after a criticality analysis based on internal procedures of the oil
refinery. With AHP technique, several aspects, which characterise each of the above-mentioned maintenance strategies, are arranged in a
hierarchic structure and evaluated using only a series of pairwise judgements. To improve the effectiveness of the methodology AHP is
coupled with a sensitivity analysis. q 2000 Elsevier Science Ltd. All rights reserved.
Keywords: Maintenance; Process plant; Failure mode effect and criticality analysis technique; Analytic hierarchy process
intangible and complex nature. Besides, the nature of the effectiveness the methodology is coupled with a sensitivity
weights of importance that the maintenance staff must give analysis phase.
to these factors during the selection process is highly subjec-
tive. Finally, bearing in mind that the plant is still in the
construction phase, some tangible aspects such as MTBF
2. The API oil refinery IGCC plant: a brief description
and MTTR can be only estimated from failure data concern-
ing machines working in other plants (in this case oil refi-
The Integrated Gasification and Combined Cycle
neries) under more or less similar operating conditions.
(IGCC) plant [6], currently being assembled at The
Furthermore, they will affect each single facility analysed
Falconara Marittima API oil refinery, will make it
in a particular way and, as a consequence, the final main-
possible to transform the oil refinement residuals into
tenance policy selection.
the synthesis gases which will be used as fuel to
It is therefore clear that the analysis and justification of
produce electricity. The IGCC plan will be placed in
maintenance strategy selection is a critical and complex task
a 47,000 m 2 area inside the oil refinery.
due to the great number of attributes to be considered, many
The electricity produced by the IGCC plant will be sold to
of which are intangible. As an aid to the resolution of this
ENEL (Italian electrical energy firm) while some
problem, some multi-criteria decision making (MCDM)
65,000 ton/h of steam will be used inside the oil refinery
approaches are proposed in the literature. Almeida and
for process requirements. The total cost of the project
Bohoris [1] discuss the application of decision making
amounts to about 750 million dollars.
theory to maintenance with particular attention to multi-
In recent years, economic and legislative changes
attribute utility theory. Triantaphyllou et al. [2] suggest
have led to increased co-operation between petrochem-
the use of Analytical Hierarchy Process (AHP) considering
ical and electrical firms. The adoption of strict environ-
only four maintenance criteria: cost, reparability, reliability
mental standards, both in Europe and in the United
and availability. The Reliability Centered Maintenance
States, is forcing oil refinery firms to reduce the emis-
(RCM) methodology (see, for example, Ref. [3]) is probably
sions of pollutants from the process plants and reduce
the most widely used technique. RCM represents a method
the potential pollution of the refined products. The same
for preserving functional integrity and is designed to mini-
pollution control requirements, mainly a reduction in the
mise maintenance costs by balancing the higher cost of
level of nitrogen and sulphur oxides, together with the
corrective maintenance against the cost of preventive main-
increasing need to control operating and investments
tenance, taking into account the loss of potential life of the
costs, is pushing electrical firms to search for more
unit in question [4].
economic and cleaner production methods.
One of the tools more frequently adopted by the compa-
The combined effect of the above-mentioned factors has
nies to categorise the machines in several groups of risk is
led several oil refineries to adopt IGCC technology for oil
based on the concepts of failure mode effect and criticality
refinement heavy residuals processing. IGCC technology
analysis technique (FMECA). This methodology has been
has proved to be a valid solution to the market requirement
proposed in different possible variants, in terms of relevant
of efficient, clean, low consuming and environmentally
criteria considered and/or risk priority number formulation
orientated production technologies.
[5]. Using this approach, the selection of a maintenance
The API oil refinery uses a thermal conversion process
policy is performed through the analysis of obtained priority
and has a production capacity of about 4,000,000 tons of oil
risk number. An example of this approach has also been
per year (80,000 barrels per day). The production cycle is
followed by our oil company, which has developed its
typical of oil refineries with a similar production capacity:
own methodology internally. This approach makes it
the current distilled yield is higher than 70% and the resi-
possible to obtain a satisfying criticality clustering of
duals are used to produce fuel oil and bitumen. Oil refine-
the 200 facilities into three homogeneous groups. The
ment heavy residuals with a high sulphur content will be
problem is to define the best maintenance strategy for
partly converted into the synthesis gases syngas (which
each group.
will be cleaned in the IGCC gasifiers) and partly used to
To integrate the internal self-made criticality approach,
produce bitumen.
this paper presents a multi-attribute decision method based
The three main objectives of the oil refinery management
on the AHP approach to select the most appropriate main-
are the following:
tenance strategy for each machine group. In this procedure,
several costs and benefits for each alternative maintenance 1. the elimination of heavy residuals used to produce fuel
strategy are arranged in a hierarchic structure and evaluated, oil with high and low sulphur content;
for each facility, through the use of a series of pairwise 2. the ability to process almost every type of heavy oil with
judgements. Finally, considering that the maintenance a high sulphur content;
manager can never be sure about the relative importance 3. the substitution of the present low efficiency thermoelec-
of decision making criteria selected when dealing with trical power plant with a more efficient system, with
this complex maintenance problem, to improve the AHP lower levels of pollutant emissions.
M. Bevilacqua, M. Braglia / Reliability Engineering and System Safety 70 (2000) 7183 73
3. Possible alternative maintenance strategies since the maintenance program must combine technical
requirements with the firms managerial strategy. The
Five alternative maintenance policies are evaluated in this IGCC plant complex configuration requires an optimal
case study. Briefly, they are the following. maintenance policy mix, in order to increase the plant avail-
ability and reduce the operating costs.
Corrective maintenance. The main feature of corrective Maintenance design deals with the definition of the best
maintenance is that actions are only performed when a strategies for each plant machine or component, depending
machine breaks down. There are no interventions until a on the availability request and global maintenance budget.
failure has occurred. Every component, in accordance with its failure rate, cost
Preventive maintenance. Preventive maintenance is and breakdown impact over the whole system, must be
based on component reliability characteristics. This studied in order to assess the best solution; whether it is
data makes it possible to analyse the behaviour of the better to wait for the failure or to prevent it. In the latter
element in question and allows the maintenance engineer case the maintenance staff must evaluate whether it is better
to define a periodic maintenance program for the to perform periodic checks or use a progressive operating
machine. The preventive maintenance policy tries to conditions analysis.
determine a series of checks, replacements and/or It is clear that a good maintenance program must define
component revisions with a frequency related to the fail- different strategies for different machines. Some of these
ure rate. In other words, preventive (periodic) mainte- will mainly affect the normal operation of the plant, some
nance is effective in overcoming the problems will concern relevant safety problems, and others will
associated with the wearing of components. It is evident involve high maintenance costs. The overlapping of these
that, after a check, it is not always necessary to substitute effects enables us to assign a different priority to every plant
the component: maintenance is often sufficient. component or machine, and to concentrate economic and
Opportunistic maintenance. The possibility of using technical efforts on the areas that can produce the best
opportunistic maintenance is determined by the nearness results.
or concurrence of control or substitution times for differ- One relevant IGCC plant feature is the lack of historical
ent components on the same machine or plant. This type reliability and maintenance costs data (the plant start-up is
of maintenance can lead to the whole plant being shut proposed for March 2000). Initially, the definition of the
down at set times to perform all relevant maintenance maintenance plan will be based upon reliability data from
interventions at the same time. the literature and on the technical features of the machines.
Condition-based maintenance. A requisite for the appli- This information will then be updated using the data
cation of condition-based maintenance is the availability acquired during the working life of the plant. The analysis
of a set of measurements and data acquisition systems to system has been structured in a rational way so as to keep
monitor the machine performance in real time. The the update process as objective as possible. This has been
continuous survey of working conditions can easily and accomplished through the use of a charting procedure, using
clearly point out an abnormal situation (e.g. the exceed- well-understood evaluations of different parameters and a
ing of a controlled parameter threshold level), allowing simple and clear analysis of corrective interventions. The
the process administrator to punctually perform the maintenance plan developed for the machines of the IGCC
necessary controls and, if necessary, stop the machine plant is based on the well-known FMECA technique [7,8].
before a failure can occur. The analysis results have provided a criticality index for
Predictive maintenance. Unlike the condition-based every machine, allowing the best maintenance policy to
maintenance policy, in predictive maintenance the be selected.
acquired controlled parameters data are analysed to find
a possible temporal trend. This makes it possible to 4.1. The maintenance strategy adopted by the oil refinery
predict when the controlled quantity value will reach or company
exceed the threshold values. The maintenance staff will
then be able to plan when, depending on the operating The internal methodology developed by the company to
conditions, the component substitution or revision is solve the maintenance strategy selection problem for the
really unavoidable. new IGCC plant is based on a criticality analysis which
may be considered as an extension of the FMECA techni-
que. This analysis takes into account the following six
parameters:
4. The IGCC plant maintenance program definition
safety;
An electrical power plant based on IGCC technology is a machine importance for the process;
very complex facility, with a lot of different machines and maintenance costs;
equipment with very different operating conditions. Decid- failure frequency;
ing on the best maintenance policy is not an easy matter, downtime length;
74 M. Bevilacqua, M. Braglia / Reliability Engineering and System Safety 70 (2000) 7183
the complexity of the problem. The steps of this methodol- f. the partitioning of the elements and the extraction
ogy are briefly the following [18]: of the structural model, termed ISM is then
a. identification of elements which are relevant to the performed.
decision making problem;
b. a contextually relevant subordinate relation is chosen; The relevant factors defining the damage criteria are iden-
c. a structural self-interaction matrix (SSIM) is developed tified as loss of production, damages to facilities, to product,
based on pairwise comparison of elements; to environment, to people, and to company image. The
d. SSIM is converted into a reachability matrix and its production loss is linked to facility downtime derived
transitivity is checked; from a failure (time required for detection, repair or repla-
e. once the transitivity has been achieved, the conversion cement and re-starting) and divided in MTBF and MTTR in
of an object system into a well-defined matrix model is a successive hierarchy level. The facility damages are
obtained; divided into direct and indirect: the direct damage deals
78 M. Bevilacqua, M. Braglia / Reliability Engineering and System Safety 70 (2000) 7183
Table 4
Pairwise comparison example with respect to damages attribute for machines of Group 1. Note: row element is x (or 1/x) times more (or less) important than
column element
Production loss Plant damage Product damage Environmental damage People damage Image damage Local Priority
with the tangible effects of the failure on the machine, between a suitable level of detail and a manageable
the indirect damage takes into account the possible complexity of the hierarchy structure for actual
influences (i.e. reduction) of the failure on the working industrial applications.
life of the plant as a consequence of a domino effect
on other facilities and instruments. Finally, the environ-
mental damage is divided into internal and external to 7. The AHP analysis
the plant.
For the maintenance policy applicability factor, two Once the hierarchy structure of the maintenance decision
sub-criteria are taken into account: the costs required making problem has been defined, the priorities of the
for the policy implementation and the reliability. The scheme have been calculated using pairwise comparisons
maintenance costs are divided into hardware (i.e. and the Delphi technique.
sensors), software (i.e. a reliability commercial soft- The three machine groups previously described have
ware), and training costs. The reliability criterion been analysed through the use of the AHP methodology.
includes the technical aspect of the maintenance strat- In this situation five different alternative maintenance poli-
egy adopted in terms of fault detection capability and cies have been considered. The pairwise judgements used to
facility restoring capability. perform the AHP analysis were stated by the oil refinery
The added-value criterion deals with the indirect benefit maintenance management that developed the modified
of a particular maintenance policy. This category includes FMECA analysis shown in Section 4.
the improvements in terms of product quality, safety, and Table 4 gives an example of the damages factor for the
internal skills (i.e. an overall better knowledge of the machines of Group 1, with the relative judgements of impor-
machines employed). tance (IR results equal to 0:03 , 0:1 obtained by adopting
With respect to the policy cost factor, four sub- the quantitative scale showed in Table 3.
criteria have been considered for the successive hierar- It is clear that the most important aspect, in terms of
chy level: MTBF, MTTR, saving in the stock of spare damages, is the plant damage attribute. This consid-
parts, and assurance aspects (i.e. possible decreases in eration is due to the fact that the highest cost derived
insurance premiums that can be obtained by adopting a from an accident is due to production plant damages
particular maintenance policy). Note that the investment (direct and indirect, i.e. domino effect). Environmen-
required to implement the policy is not included as sub- tal damage is the least important element because of the
criterion. This is due to the fact that the maintenance presence of modern and sophisticated safety systems
investment for a single machine is negligible with that guarantee limited consequences for the environ-
respect to the other sub-criteria of the policy cost ment.
factor. For this reason, the investment required attri- Fig. 2 shows the global priority indices for each criterion,
bute has been introduced only as sub-criterion of the sub-criterion and alternative included in the AHP hierarchy
policy applicability factor in the hierarchy. structure for a particular Group 1 machine (a 23MW power
The proposed hierarchy must not be intended as a air compressor).
general for any process plant application, with some As can be seen, the overall inconsistency index is equal to
choices concerning only the particular IGCC plant 0.046, which is less than the critical value of 0.1. For brev-
here analysed. Besides, it is possible to note how ity, the partial IR values are not shown in the figure. Never-
some possible dependencies among the attributes have theless, all the IR values result lower than 0.1.
not been treated. These structure simplification choices Table 5 shows the final ranking for three machines, each
derive from the necessity to obtain a good trade-off representative of a different group.
As shown, the AHP results generally confirm the FMECA increases, the priorities of the remaining criteria must
indications. Once again, for the Group 1 facility the best decrease proportionately, and the global priorities of the
maintenance policy proves to be the predictive one. For alternatives must be recalculated. All the results reported
these machines the most expensive and sophisticated stra- in Tables 68 were obtained using the Expertchoice soft-
tegies (i.e. predictive and condition-based) are highly ware, a multi-attribute decision making tool which was used
preferable with respect to the others because of the critical to support all the AHP applications reported in this paper.
aspect of their failures. For example, from Table 6, one can clearly see the
The Group 2 machine shows a slight preference for robustness of the predictive maintenance strategy for the
opportunistic maintenance even if preventive and predictive machines that belong to Group 1. This policy remains the
policies should not be neglected. best solution, increasing or decreasing the priorities of each
The analysis performed for the machine belonging to criterion. It is only when one increases the priority of the
Group 3 shows that corrective and preventive maintenance applicability factor to an improbable 96% that we obtain a
are equally appropriate. So, the decision to use corrective change in the final ranking with the condition-based main-
maintenance for this group of machines should be carefully tenance strategy.
considered. The limited failure consequence in terms of For the Group 2 machines (Table 7), the final solution is
production loss is not sufficient to clearly and immediately less stable. Opportunistic and predictive maintenance stra-
state that no maintenance action should be performed before tegies show some alternations in priority positions. In parti-
the failure. cular, the maintenance staff must take into consideration
The three machines selected for the AHP analysis can be applicability and added-value priority evaluations.
considered as representative of the corresponding groups. In There are no situations where catastrophic changes in the
other words, they represent more or less the average char- final ranking are observed.
acteristics of the facilities which belong to the same cluster. An analysis of the Group 3 machines (Table 8), highlights
For this reason, the results obtained for this representative more reversals in the final ranking. Corrective, opportunistic
equipment have been extended to all facilities of the groups. and predictive maintenance strategies can all be considered
This position has been considered sufficient and satisfactory to be the best solution, depending on which weighting
by the maintenance staff. In any case, a more detailed analy- criteria are used. It can, therefore, be seen that the sensitivity
sis requiring a new set of pairwise judgements for each analysis shows how, in the case study under examination,
facility of each group can be always performed. This is the maintenance staff should concentrate their attention on
probably the best solution for the extreme equipment the pairwise evaluation of the four criteria. It is clear that a
characterised by the CI values near to the limit of the few changes in the judgement evaluations can lead to modi-
belonging cluster. fications in the final priority ranking. But it must also be
remembered that the importance of corrective maintenance
never goes away. In other words, we have three different
8. Sensitivity analysis strategies, all of which can provide the best solution, and the
differences among them are never of great importance.
Although the ranking solution showed a possible scenario Summarising the considerations discussed above, one can
where, for example, damages aspects are clearly the most affirm that the AHP selections presented in Section 7, which
important criteria for Group 1 machines (see Fig. 2), the concern the best possible maintenance strategies for the
AHP solution can change in accordance with shifts in IGCC machines, can be accepted with a good degree of
analyst logic. To explore the response of model solutions confidence by the company maintenance staff.
(i.e. the solution robustness) to potential shifts in the priority We conclude this section with two final considerations.
of maintenance strategies, a series of sensitivity analyses of First, the sensitivity analysis proposed here is only relevant
criteria weights can be performed by changing the priority to the priorities of the four first-level criteria. Second,
(relative importance) of weights. Each criterion can be char- because we have changed each attribute weight one at a
acterised by an important degree of sensitivity, i.e. the rank- time, only the main effects have been considered. In
ing of all strategies changes dramatically over the entire other words, interaction effects of the changes made to
weight range [19]. The problem is to check whether a few two or more weights have been ignored. These simplifica-
changes in the judgement evaluations can lead to significant tions have been adopted for the following reasons:
modifications in the priority final ranking. For this reason,
sensitivity analysis is used to investigate the sensitivity of 1. the final solution is mainly sensible to changes in the
the alternatives to changes in the priorities of the criteria at priorities at the highest level of the hierarchy;
the level immediately below the goal. The analysis proposed 2. the introduction of the interaction effects makes the
emphasises the priorities of the four first-level criteria in sensitivity analysis too complex for actual applications.
the AHP model reported in Fig. 1 and shows how changing Nevertheless, one should note that the main effects are
the priority of one criterion affects the priorities of the generally the most important aspects in a sensitivity
others. It is clear that as the priority of one of the criteria analysis.
M. Bevilacqua, M. Braglia / Reliability Engineering and System Safety 70 (2000) 7183 81
Corrective maintenance
to be a good compromise between efficiency and efficacy.
9. Conclusions
0.043
0.174
0.227
The definition of the most appropriate maintenance poli-
cies for a large system such as an IGCC plant requires the
development of the appropriate decision support systems.
Preventive maintenance
maintenance staff:
a. AHP technique makes it possible to approach the deci-
sion making problem in a more complete and thorough
way, taking several factors into account. This capacity is
more difficult to obtain when using conventional meth-
odologies such as FMECA. It must also be considered
AHP final ranking for three machines, each one representative of a different group
0.333
0.195
0.165
Centrifugal pump
Centrifugal pump
Table 6
Observations derived from sensitivity analysis of the criteria priority values with machines of Group 1
Damages Predictive maintenance is always the best 56.6 Predictive maintenance is always the best
strategy strategy
Applicability Predictive maintenance is always the best 36.8 Predictive maintenance strategy is reached
strategy and overcame by condition-based
maintenance but only when applicability
priority is equal to 96%.
Added-value Predictive maintenance is always the best 36.8 Predictive maintenance is always the best
strategy strategy
Cost Predictive maintenance is always the best 26.7 Predictive maintenance is always the best
strategy strategy
Table 7
Observations derived from sensitivity analysis of the criteria priority values with machines of Group 2
Table 8
Observations derived from sensitivity analysis of the criteria priority values with machines of Group 3
Damages Corrective maintenance is always the best 15.1 Corrective maintenance is reached and
strategy overcame by opportunistic maintenance just
when damages priority is became to
17.1%. Predictive is the new best strategy
when priority is equal to 53.1%
Applicability Corrective maintenance is reached and 63.5 Corrective maintenance is always the best
overcame by opportunistic maintenance just strategy
when applicability priority is reduced to
61.5%. Predictive is the new best strategy
when priority is reduced to 47.5%
Added-value Corrective maintenance is always the best 6.2 Corrective maintenance is reached and
strategy overcame by opportunistic maintenance
when damages priority is became to
10.2%. Predictive is the new best strategy
when priority is equal to 20.2%
Cost Corrective maintenance is always the best 11.8 Corrective maintenance is reached and
strategy overcame by opportunistic maintenance
when damages priority is became to
19.1%. Predictive is the new best strategy
when priority is equal to 33.1%
M. Bevilacqua, M. Braglia / Reliability Engineering and System Safety 70 (2000) 7183 83