Professional Documents
Culture Documents
PIPE-_____
Specification Section _______
Project: __________________________________ Project No: __________
Associated Checklists:
___chillers, ___cooling towers, ___pumps, ___CHW pumps, ___AHUs, ___ emergency
power system
___Other_______________________
1. Submittal / Approvals
Submittal. The above equipment and systems integral to them are complete and
ready for functional testing. The checklist items are complete and have been checked
off only by parties having direct knowledge of the event, as marked below, respective to
each responsible contractor. This prefunctional checklist is submitted for approval,
subject to an attached list of outstanding items yet to be completed. A Statement of
Correction will be submitted upon completion of any outstanding areas. ___ List
attached.
Prefunctional checklist items are to be completed as part of startup & initial checkout,
preparatory to functional testing.
This checklist does not take the place of the manufacturers recommended
checkout and startup procedures or report.
Contractors assigned responsibility for sections of the checklist shall be
responsible to see that checklist items by their subcontractors are completed
and checked off.
Approvals. This filled-out checklist has been reviewed. Its completion is approved.
3. Pipe Verification
Item Specified Submitted Installed
Pipe: Manufacturer
Material
ASTM No. / Grade / Type
Service
Fitting Type (Flanged,
welded, Victaulic, screwed,
etc.)
Gaskets
Pipe Coating
Wall Thickness/Sch. No.
Insulation Type
Insulation Thickness
4. Installation Checks
a) Piping and Supports/Hangers
i) Pipe installed per shop drawings: Yes / No
ii) Pipe installed per construction drawings: Yes / No
d) TAB
i) Installation of required system balancing devices complete: N/A / Yes / No
ii) Hydronic TAB completed and accepted: N/A / Yes / No
e) Final
i) Pressure test complete with acceptable results per specifications: Yes / No
ii) Containment system tested for leaks with acceptable results: N/A / Yes /
No
iii) Prefunctional testing complete for all connected equipment: Yes / No
iv) Flushing/water quality test complete: Yes / No
v) Water quality test results accepted by MDAD: N/A / Yes / No
vi) Piping system charged: Yes / No
vii) Water treatment test results accepted by water treatment company:
N/A / Yes / No
PREFUNCTIONAL TEST CHECKLIST
PIPE
03/02 15997-08-4 OF 6 D:\DOCS\DIV1\03-02\15997-08.DOC
PREFUNCTIONAL TEST CHECKLIST
PIPE-_____
viii) Sterilization test results accepted: N/A / Yes / No
ix) Bacterial test results accepted: N/A / Yes / No
x) Building and Zoning final inspection complete/approved: N/A / Yes / No
xi) MDAD approval obtained (attached) to open to existing systems:
N/A / Yes / No
6. Sensor and Actuator Calibration
All field-installed temperature and pressure sensors and gages, and all actuators shall
be calibrated.
All test instruments have had a certified calibration within the last 12 months:
Y/N______.
All sensors are calibrated within required tolerances ___ YES ___ NO
-- END OF CHECKLIST--