Professional Documents
Culture Documents
Peter Breen
Introduction
What lessons have been learnt by others from their experience to date?
Estimate
Estimates are produced at various stages throughout the life of a project or program for a variety of purposes.
The type of estimate to be prepared as well as the methodology used is dependent on what estimate will be used
practices
Estimate Categories
100 Class 5
Estimate Expected Accuracy (%)
From standard by AACE,
Association for the Advancement of
80
Cost Engineering
Class 4
60
Class 3
40 Class 2
Class 1
20
0 Check
Control
-20 Budgetary
Feasibility
-40 Conceptual
-60
-80 10 20 30 40 50 60 70 80 90 100
-100 Level of Project Definition (%)
D Project Definition Estimate Accuracy
Estimate FEED = Front End Engineering Definition
Accuracy
MP = Master Planning
Initial Funding
Interim Funding
Estimate based on benchmarking, early information
50% Final Funding
25% Estimate based on early equipment quotes, approximate quantities, outline schedule
Detailed Design
Pre-Conceptual Preliminary
Reference to
existing facilities
H: +20% to +50% H: +20% to +50% H: +10% to +30% H: +5% to +20% H: +3% to +10%
Estimating Method Capacity factored, Equipment factored Possible tenders for Contracts for major Based on bids,
parametric, and parametric major equipment. equipment. Detailed variations, final
judgement model Quantification. quantities quantities
Some approximate
estimating
Top down Top Down Bottom Up Bottom up Bottom up
AACE Class Class 5 Class 4 Class 3 Class 2 Class 1
Typical Preliminary Schedule Overview
Initiate
Technology Procurement
Design Certification
72 Months
Full Capital
Site Specific Engineering Authorisation
48 Months
Ground First Fuel
Breaking Concrete UNIT 1 Load COD
01 02 03 04 05 06 07 08 09 10 11 12
Benchmarking
There is an unbreakable link between the scope, schedule, and execution methodology
with the estimate.
There is a fundamental need for quantification to help determine the cost and schedule be it
the design man-hours, volume of concrete, meters of pipes, electrical I/O points;
The site layout impacts the quantities in terms of civil works, mechanical and electrical
distribution
IAEA Economic Evaluation of Bids for Nuclear Power Plants 1999 Edition;
edited
Estimating Best Practices Explored
Estimating Behaviours
shared ownership
Consider a QRA to provide for risks in order to compare differences between bids
Develop an Assessment process that recognises challenges
Strategic
Drivers
Business
Case / Best Managing
Deal Procurement
Challenges
External
Site(s) Specifics
Influences
Vendors /
Delivery
Teams
Basis of Technology Assessment and Selection
Owners Project Delivery Strategy for the integration of NI, CI and BOP
How the technology projects integrates into the overall programme eg Grid, fuel...
Vendor Evaluation Criteria
Factual Evidence for Decision
Cash Flow
Assessment of Risks to be included in decision
Net Output.
Life expectancy.
Priced Risks
Project Documentation
Specialist Input
Risk Categories
Risk Classifications
Probability Analysis
IDENTIFY key Sensitivities
Key Criticalities
The NSSS also influences other aspects such as Balance of NI, BoP, fuel, number of
operators
The total cost of the NSSS will reflect the maturity of the technology and the extent of
design & licensing already complete. First of a kind has a premium price
Claims made by the vendors should be verified and base assumptions understood
Indicative Roadmap to Evidence Based Decision
Procurement
Planning
How many bidders?
Request for
Information Selection of Preferred Bidder(s)
Request for
Quotation
Negotiation
Early Design /
Works Agreement
Revised Offer(s)
1. There needs to be a robust economic business case for developing new nuclear.
2. The cost to develop a scheme to full authorisation is expensive to the Owner.
3. Do not under estimate the impact on the Owner of resources needed to develop a scheme, select a
vendor while interfacing with Regulators, Grid, Decommissioning authority, Permits and
Government.
4. Owner resources need to be clear on their remit, process and procedures.
5. Owners need to have a clear decision making process between any JV companies.
6. Develop a clear procurement strategy with roadmap route to contract for Vendor.
7. Maintain competition between vendors for as long as possible.
8. Establish Early Contractor Involvement with the Preferred Bidders for site specific designs.
9. Clarify the in country regulatory requirements (particularly in respect of safety systems); site
specific issues, such as geology and Planning restrictions.
10. Selecting Most Economically Advantageous Tender needs to be underpinned with a strong risk
management process.
11. Consider establishing bid evaluation criteria that is based on cost and priced risks.
12. Contractors have more confidence in productivity on CI & BOP compared with the NI and BNI -
this is due to understanding of the regulator requirements in country.
Learning to date continued..
13. Having robust contracting arrangements are essential as are those that adopt contracting
strategies that promote constructive relationships, rather than adversarial ones, between
parties.
14. Contractors willingness to take on Risk is limited.
15. Contract negotiations with vendors and delivery teams are protracted.
16. Agreement of pricing mechanism with escalation provision given term is a challenge.
17. The bidding costs are expensive to the supply chain who fear projects that do not go ahead.
18. Security of information is imperative.
19. Provide a central team location with good IT.
20. Owners need to take the lead - the costs of project risk rest with the Owner. Their
leadership is critical to success and it is Owners that should ensure that best practice is
used on their projects.
21. Use integrated project teams from the start of the project.
22. Allow sufficient time and resources for planning and engineering design and for appointing
contractors based primarily on competency. Supplement Owner team with industry experts.
23. Recognise the shortage of good supervisory staff and particular skilled staff welders,
planners, project managers and engineering designers develop proposals to mitigate.
24. Nuclear projects need early, proactive and collaborative action by Owners, vendors,
contractors, the workforce, unions and Governments
Learning to date continued..
25. The Owners licensing manager arrangements need to be reflected in the contract.
26. The vendors need to understand the procurement process to commit to the bidding process.
27. The first estimate prepared is the most important one. Accuracy range should be stated.
28. Use career professionals to estimate.
29. Develop a clear set of assumptions addressing issues such as productivity levels, logistics,
local labour v travelling v accommodated personnel, economic conditions escalation.
30. Develop a Policy for Foreign Exchanges / Currency Hedging.
31. Adopt coding system before preparing estimating to allow for analysis.
32. Quantities drive prices.
33. Instil good behaviour and attitude within the project team to respect the budget.
34. Link the scope, schedule and estimate to the procurement strategy this is the basis for
control including change management. Control scope with change management.
35. Commissioning Costs & Start-up costs are considerable and should be capitalised.
36. Be aware that the benefit of a low cost on-shore base for some aspects can be out
weighted by expensive off-shore resources.
Summary Considerations
Remember the cost differential between NSSS technologies may be a small part of the
estimate development
Consider seeking to increase the level of Certainty of the costs (ie reduce Risk) at