ARCHITECT DATE
No work shall be made inaccessible until this form has been completed and work has been approved by the I.O.R.
Issuance of an Inspection Request form by the Contractor indicates that the Contractor has reviewed its own work
and found the work to be complete and in compliance with the Contract Documents.
Construction as described above has NOT been accepted. I.O. R. Initial / Date Stamp
Explanation:
cc: Architect/Engineer
Project Manager/Construction Inspector Construction Mgmt.
University 702.24 10/06